  1. Measurement and control system for ITER remote maintenance equipment

    Energy Technology Data Exchange (ETDEWEB)

    Oka, Kiyoshi; Kakudate, Satoshi; Takeda, Nobukazu; Takiguchi, Yuji; Akou, Kentaro [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    1998-04-01

    ITER in-vessel components such as blankets and divertors are categorized as scheduled maintenance components because they are subjected to severe plasma heat and particle loads. Blanket maintenance requires remote handling equipment and tools able to handle Heavy payloads of about 4 tons within a 2 mm precision tolerance. Divertor maintenance requires remote replacement of 60 cassettes with a dead weight of about 25 tons each. In the ITER R and D program, full-scale remote handling equipment for blanket and divertor maintenance has been designed and assembled for demonstration tests. This paper reviews the measurement and control system developed for full-scale remote handling equipment, the Japan Home Team contribution. (author)

  2. Measurement and control system for ITER remote maintenance equipment

    International Nuclear Information System (INIS)

    Oka, Kiyoshi; Kakudate, Satoshi; Takeda, Nobukazu; Takiguchi, Yuji; Akou, Kentaro

    1998-01-01

    ITER in-vessel components such as blankets and divertors are categorized as scheduled maintenance components because they are subjected to severe plasma heat and particle loads. Blanket maintenance requires remote handling equipment and tools able to handle Heavy payloads of about 4 tons within a 2 mm precision tolerance. Divertor maintenance requires remote replacement of 60 cassettes with a dead weight of about 25 tons each. In the ITER R and D program, full-scale remote handling equipment for blanket and divertor maintenance has been designed and assembled for demonstration tests. This paper reviews the measurement and control system developed for full-scale remote handling equipment, the Japan Home Team contribution. (author)

  3. Control room concept for remote maintenance in high radiation areas

    International Nuclear Information System (INIS)

    Clarke, M.M.; Kreifeldt, J.G.

    1984-01-01

    This paper summarizes the design of a control room concept for an operator interface with remote maintenance equipment consisting of force-reflecting manipulators, tools, hoists, cranes, cameras, and lights. The design development involved two major activities. First, detailed requirements were defined for foreseeable functions that will be performed by the control room operators. Second, concepts were developed, tested, and refined to meet these requirements. Each of these activities is summarized below. 6 references, 3 figures

  4. Control room concept for remote maintenance in high radiation areas

    International Nuclear Information System (INIS)

    Clarke, M.M.; Kreifeldt, J.G.

    1984-01-01

    This paper summarizes the design of a control room concept for an operator interface with remote maintenance equipment consisting of force-reflecting manipulators, tools, hoists, cranes, cameras, and lights. The design development involved two major activities. First, detailed requirements were defined for foreseeable functions that will be performed by the control room operators. Second, concepts were developed, tested, and refined to meet these requirements. 6 references, 3 figures

  5. Remote maintenance development

    International Nuclear Information System (INIS)

    Zook, C.R.

    1979-01-01

    The concept of remote maintenance as it pertains to nuclear fuel fabrication facilities is quite unique. The future may require completely remote facilities where maintenance will be performed by hybrid manipulators/robots. These units will be capable of being preprogrammed for automatic operation or manually operated with the operator becoming a part of the closed loop control system. These robots will mesh television, computer control, and direct force feedback manual control in a usable new concept of robotics

  6. Design of a multisystem remote maintenance control room

    International Nuclear Information System (INIS)

    Draper, J.V.; Handel, S.J.; Kring, C.T.; Kawatsuma, S.

    1988-01-01

    The Remote Systems Development Section of the Consolidated Fuel Reprocessing Program at the Oak Ridge National Laboratory (ORNL) and Japan's Power Reactor and Nuclear Fuel Development Corporation (PNC) recently collaborated in the development of a control room concept for remote operations. This report describes design methods and the resulting control room concept. The design project included five stages. The first was compilation of a complete function list; functions are tasks performed by operators in the control room while operating equipment located in the remote area. The second step was organization of the function list into ''function groups;'' function groups are sets of functions that operate one piece of equipment. The third stage was determination of crew size and requirements for supervision. The fourth stage was development of conceptual designs of displays and controls. The fifth stage was development of plans for placement of crew stations within the control room. 5 figs., 1 tab

  7. Remote Maintenance Monitoring System -

    Data.gov (United States)

    Department of Transportation — The Remote Maintenance and Monitoring System (RMMS) is a collection of subsystems that includes telecommunication components, hardware, and software, which serve to...

  8. The ITER remote maintenance system

    International Nuclear Information System (INIS)

    Tesini, A.; Palmer, J.

    2007-01-01

    ITER is a joint international research and development project that aims to demonstrate the scientific and technological feasibility of fusion power. As soon as the plasma operation begins using tritium, the replacement of the vacuum vessel internal components will need to be done with remote handling techniques. To accomplish these operations ITER has equipped itself with a Remote Maintenance System; this includes the Remote Handling equipment set and the Hot Cell facility. Both need to work in a cooperative way, with the aim of minimizing the machine shutdown periods and to maximize the machine availability. The ITER Remote Handling equipment set is required to be available, robust, reliable and retrievable. The machine components, to be remotely handle-able, are required to be designed simply so as to ease their maintenance. The baseline ITER Remote Handling equipment is described. The ITER Hot Cell Facility is required to provide a controlled and shielded area for the execution of repair operations (carried out using dedicated remote handling equipment) on those activated components which need to be returned to service, inside the vacuum vessel. The Hot Cell provides also the equipment and space for the processing and temporary storage of the operational and decommissioning radwaste. A conceptual ITER Hot Cell Facility is described. (orig.)

  9. TPX remote maintenance and shielding

    International Nuclear Information System (INIS)

    Rennich, M.J.; Nelson, B.E.

    1994-01-01

    The Tokamak Physics Experiment machine design incorporates comprehensive planning for efficient and safe component maintenance. Three programmatic decisions have been made to insure the successful implementation of this objective. First, the tokamak incorporates radiation shielding to reduce activation of components and limit the dose rate to personnel working on the outside of the machine. This allows most of the ex-vessel equipment to be maintained through conventional ''hands-on'' procedures. Second, to the maximum extent possible, low activation materials will be used inside the shielding volume. This resulted in the selection of Titanium (Ti-6Al-4V) for the vacuum vessel and PFC structures. The third decision stipulated that the primary in-vessel components will be replaced or repaired via remote maintenance tools specifically provided for the task. The component designers have been given the responsibility of incorporating maintenance design and for proving the maintainability of the design concepts in full-scale mockup tests prior to the initiation of final fabrication. Remote maintenance of the TPX machine is facilitated by general purpose tools provided by a special purpose design team. Major tools will include an in-vessel transporter, a vessel transfer system and a large component transfer container. In addition, tools such as manipulators and remotely operable impact wrenches will be made available to the component designers by this group. Maintenance systems will also provide the necessary controls for this equipment

  10. Remote maintenance development for ITER

    International Nuclear Information System (INIS)

    Tada, Eisuke; Shibanuma, Kiyoshi

    1998-01-01

    This paper describes the overall ITER remote maintenance design concept developed mainly for in-vessel components such as diverters and blankets, and outlines the ITER R and D program to develop remote handling equipment and radiation hard components. Reactor structures inside the ITER cryostat must be maintained remotely due to DT operation, making remote handling technology basic to reactor design. The overall maintenance scenario and design concepts have been developed, and maintenance design feasibility, including fabrication and testing of full-scale in-vessel remote maintenance handling equipment and tool, is being verified. (author)

  11. Remote maintenance development for ITER

    Energy Technology Data Exchange (ETDEWEB)

    Tada, Eisuke [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment; Shibanuma, Kiyoshi

    1998-04-01

    This paper describes the overall ITER remote maintenance design concept developed mainly for in-vessel components such as diverters and blankets, and outlines the ITER R and D program to develop remote handling equipment and radiation hard components. Reactor structures inside the ITER cryostat must be maintained remotely due to DT operation, making remote handling technology basic to reactor design. The overall maintenance scenario and design concepts have been developed, and maintenance design feasibility, including fabrication and testing of full-scale in-vessel remote maintenance handling equipment and tool, is being verified. (author)

  12. Remote maintenance development for ITER

    International Nuclear Information System (INIS)

    Tada, Eisuke; Shibanuma, Kiyoshi

    1997-01-01

    This paper both describes the overall design concept of the ITER remote maintenance system, which has been developed mainly for use with in-vessel components such as divertor and blanket, and outlines of the ITER R and D program, which has been established to develop remote handling equipment/tools and radiation hard components. In ITER, the reactor structures inside cryostat have to be maintained remotely because of activation due to DT operation. Therefore, remote-handling technology is fundamental, and the reactor-structure design must be made consistent with remote maintainability. The overall maintenance scenario and design concepts of the required remote handling equipment/tools have been developed according to their maintenance classification. Technologies are also being developed to verify the feasibility of the maintenance design and include fabrication and testing of a fullscale remote-handling equipment/tools for in-vessel maintenance. (author)

  13. Remote handling maintenance of ITER

    International Nuclear Information System (INIS)

    Haange, R.

    1999-01-01

    The remote maintenance strategy and the associated component design of the International Thermonuclear Experimental Reactor (ITER) have reached a high degree of completeness, especially with respect to those components that are expected to require frequent or occasional remote maintenance. Large-scale test stands, to demonstrate the principle feasibility of the remote maintenance procedures and to develop the required equipment and tools, were operational at the end of the Engineering Design Activities (EDA) phase. The initial results are highly encouraging: major remote equipment deployment and component replacement operations have been successfully demonstrated. (author)

  14. Remote maintenance for fusion experimental reactor

    International Nuclear Information System (INIS)

    Koizumi, Koichi; Takeda, Nobukazu

    2000-01-01

    Here was introduced on maintenance of reactor core portion operated by remote control among maintenance of the International Thermonuclear Experimental Reactor (ITER) begun on its design since 1988 under international cooperation of U.S.A., Europe, Russia and Japan. Every appliances constructing the reactor core portion is necessary to carry out all of their inspection and maintenance by using remote controlled apparatus because of their radiation due to neutron generated by DT combustion of plasma. For engineering design activity (EDA) in ITER, not only design and development of the remote control appliances but also design under consideration of remote maintenance for from structural design of maintained objective appliances to access method to appliances, transportation and preservation method of radiated matters, and out-reactor maintenance in a hot cell, is now under progress. Here were also reported on basic concept on maintenance and conservation of ITER, maintenance design of diverter and blanket with high maintenance frequency and present state on development of maintenance appliances. (G.K.)

  15. The ITER remote maintenance system

    International Nuclear Information System (INIS)

    Tesini, A.; Palmer, J.

    2008-01-01

    The aim of this paper is to summarize the ITER approach to machine components maintenance. A major objective of the ITER project is to demonstrate that a future power producing fusion device can be maintained effectively and offer practical levels of plant availability. During its operational lifetime, many systems of the ITER machine will require maintenance and modification; this can be achieved using remote handling methods. The need for timely, safe and effective remote operations on a machine as complex as ITER and within one of the world's most hostile remote handling environments represents a major challenge at every level of the ITER Project organization, engineering and technology. The basic principles of fusion reactor maintenance are presented. An updated description of the ITER remote maintenance system is provided. This includes the maintenance equipment used inside the vacuum vessel, inside the hot cell and the hot cell itself. The correlation between the functions of the remote handling equipment, of the hot cell and of the radwaste processing system is also described. The paper concludes that ITER has equipped itself with a good platform to tackle the challenges presented by its own maintenance and upgrade needs

  16. Maintenance of remote reconnaissance vehicle

    International Nuclear Information System (INIS)

    Schein, D.C.

    1985-01-01

    A description is provided of the maintenance program developed for remote reconnaissance vehicles, such as RRV-1, in use at the Three Mile Island Unit 2. The described approach, which is simple, effective, and flexible, helped to make the effort successful. It will be applied to future projects

  17. Remote maintenance system for nuclear facilities

    International Nuclear Information System (INIS)

    Maeda, Masafumi

    1993-01-01

    In the facilities related to atomic energy, from the viewpoint of the reduction of radiation exposure of workers and the heightening of the rate of operation of the facilities, the development of remote maintenance system is regarded as important. Meidensha Electric Manufacturing Co., Ltd. developed the bilateral control type manipulator, BILARM-83, in 1979, and has developed high performance manipulator systems. As the design of the plant that realizes the remote operation maintenance of process machinery and equipment during plant operation, the remote maintenance system by canyon cell techniques, which was adopted in Savannah River plant, USA, and has been operated for nearly 50 years, has been known. The concept of the full remote maintenance system by large scale cell techniques was shown and has been developed by Power Reactor and Nuclear Fuel Development Corp. In order to realize the remote maintenance of such large scale cells, Meidensha is developing the both arm type bilateral servo manipulator, the single arm type power manipulator, the transport system for moving them, the power and signal system and so on. Those systems were adopted for the glass solidification facilities. (K.I.)

  18. Remote assembly and maintenance of fusion reactors

    International Nuclear Information System (INIS)

    Becquet, M.C.; Farfaletti-Casali, F.

    1991-01-01

    This paper intend to present the state of the art in the field of remote assembly and maintenance, including system analysis design and operation for controlled fusion device such as JET, and the next NET and ITER reactors. The operational constraints of fusion reactors with respect to temperature, radiations dose rates and cumulated doses are considered with the resulting design requirements. Concepts like articulated boom, in-vessel vehicle and blanket handling device are presented. The close relations between computer simulations and experimental validation of those concepts are emphasized to ensure reliability of the operational behavior. Mockups and prototypes in reduced and full scale, as operating machines are described to illustrate the progress in remote operations for fusion reactors. The developments achieved at the Institute for System Engineering and Informatics of the Joint Research Center, in the field of remote blanket maintenance, reliability assessment of RH systems and remote cut and welding of lips joints are considered. (author)

  19. The ITER Remote Maintenance Management System

    International Nuclear Information System (INIS)

    Tesini, Alessandro; Rolfe, A.C.

    2009-01-01

    A major challenge for the ITER project is to develop and implement a Remote Maintenance System, which can deliver high Tokamak availability within the constraints of the overall ITER programme objectives. Much of the maintenance of ITER will be performed using remote handling methods and some with combined manual and remote activities working together. The organization and management of the ITER remote handling facilities will be of a scale unlike any other remote handling application in the world. The ITER remote handling design and procurement activities will require co-ordination and management across many different sites throughout the world. It will be a major challenge for the ITER project to ensure a consistent quality and technical approach in all of the contributing parties. To address this issue the IO remote handling team are implementing the ITER Maintenance Management Plan (IMMP) comprising an overarching document defining the policies and methodologies (ITER Remote Maintenance Management System or IMMS) and an associated ITER remote handling code of practise (IRHCOP). The IMMS will be in document form available as a pdf file or similar. The IRHCOP will be implemented as a web based application and will provide access to the central resource of the entire code of practise from any location in the world. The IRHCOP data library will be centrally controlled in order that users can be assured of the data relevance and authenticity. This paper will describe the overall approach being taken to deal with this challenge and go on to detail the structure and content of both the IMMS and the IRHCOP.

  20. Remote maintenance development, July 1975--July 1976

    International Nuclear Information System (INIS)

    Fletcher, R.D.

    1977-04-01

    The results of the second year's efforts on remote handling development and studies for remote maintenance of failure-prone areas of the New Waste Calcining Facility (NWCF) are presented. Test arrangements and results for specific viewing situations and component remote installation and removal in the Remote Maintenance Development Facility (RMDF) and component material evaluations are discussed

  1. The divertor remote maintenance project

    International Nuclear Information System (INIS)

    Maisonnier, D.; Martin, E.; Akou, K.

    2001-01-01

    Remote replacement of the ITER divertor will be required several times during the life of ITER. To facilitate its regular exchange, the divertor is assembled in the ITER vacuum vessel from 60 cassettes. Radial movers transport each cassette along radial rails through the handling ports and into the vessel where a toroidal mover lifts and transports the cassette around a pair of toroidal rails. Once at its final position the cassette is locked to the toroidal rails and is accurately aligned in both poloidal and toroidal directions. A further requirement on the divertor is to minimise the amount of activated waste to be sent to a repository. To this end the cassettes have been designed to allow the remote replacement, in a hot cell, of their plasma facing components. The paper describes the two facilities built at ENEA Brasimone, Italy, whose aim is to demonstrate the reliable remote maintenance of the divertor cassettes. (author)

  2. The divertor remote maintenance project

    International Nuclear Information System (INIS)

    Maisonnier, D.; Martin, E.; Akou, K.

    1999-01-01

    Remote replacement of the ITER divertor will be required several times during the life of ITER. To facilitate its regular exchange, the divertor is assembled in the ITER vacuum vessel from 60 cassettes. Radial movers transport each cassette along radial rails through the handling ports and into the vessel where a toroidal mover lifts and transports the cassette around a pair of toroidal rails. Once at its final position the cassette is locked to the toroidal rails and is accurately aligned in both poloidal and toroidal directions. A further requirement on the divertor is to minimise the amount of activated waste to be sent to a repository. To this end the cassettes have been designed to allow the remote replacement, in a hot cell, of their plasma facing components. The paper describes the two facilities built at ENEA Brasimone, Italy, whose aim is to demonstrate the reliable remote maintenance of the divertor cassettes. (author)

  3. The operational challenge of remote maintenance

    International Nuclear Information System (INIS)

    Forsythe, L.

    2015-01-01

    Full text of publication follows. With the declining supply of fossil fuels that are used in power stations today, and the ongoing concern over climate change, nuclear fusion is one of the most promising options for generating large amounts of carbon-free energy in the future. Fuel supplies for fusion will be available for millions of years, with 1 kg of fusion fuel providing the same amount of energy as 10 thousand tonnes of fossil fuel. Unlike conventional fission reactors, the radioactive waste produced from fusion is short-lived, and will be safe to dispose of conventionally within 100 years. Although fusion has the huge advantage of being a carbon free energy source, there are complexities when it comes to maintaining the machine. Due to the nature of the fusion reaction, the components within the area of the reactor vacuum vessel become radioactive, which requires maintenance and modifications to be conducted remotely to protect human operators. Remote maintenance is the use of manipulators to carry out tasks in challenging or hostile environments, which would otherwise cause harm to humans. Remote handling slave manipulators do the work of a human by mimicking the movements from a master robotic manipulator that is controlled by a human operator. This means that remote handling can be used in many other areas other too, such as space; fission power plants; sub-sea; and nuclear material handling or in adverse environments such as: low or high temperature; chemically contaminated; combustible and low oxygen environments. Remote maintenance requires specialist engineers to take into consideration many aspects normally taken for granted when carrying out a task manually. Constraints such as the space around us; viewing and lighting; the human body's dexterity and flexibility; the weight and centre of gravity of tools and components, and how we securely grip and handle them; and access to fixings and fastenings. All these are factors that require careful

  4. STARFIRE remote maintenance and reactor facility concept

    International Nuclear Information System (INIS)

    Graumann, D.W.; Field, R.E.; Lutz, G.R.; Trachsel, C.A.

    1981-01-01

    A total remote maintenance facility has been designed for all equipment located within the reactor building and hot cell, although operational flexibility has been provided by design of the reactor shielding such that personnel access into the reactor building within 24 hours after reactor shutdown is possible. The reactor design permits removal and replacement of all components if necessary, however, the vacuum pumps, isolation valves and blanket require scheduled, routine maintenance. Reactor scheduled maintenance does not dominate annual plant downtime, therefore, several scheduled operations can be added without affecting reactor availability. The maintenance facilities consist of the reactor building, the hot cell, the reactor service area and the remote maintenance control room. The reactor building contains the reactor, selected support system modules, and required maintenance equipment. The reactor and the support systems are maintained with (1) equipment that is mounted on a monorail system; (2) overhead cranes; and (3) bridge-mounted electromechanical manipulators. The hot cell is located outside of the reactor building to localize contamination products and permit independent operation. An equipment air lock connects the reactor building to the hot cell

  5. Remote maintenance in nuclear fuel reprocessing

    International Nuclear Information System (INIS)

    Herndon, J.N.

    1985-01-01

    Remote maintenance techniques applied in large-scale nuclear fuel reprocessing plants are reviewed with particular attention to the three major maintenance philosophy groupings: contact, remote crane canyon, and remote/contact. Examples are given, and the relative success of each type is discussed. Probable future directions for large-scale reprocessing plant maintenance are described along with advanced manipulation systems for application in the plants. The remote maintenance development program within the Consolidated Fuel Reprocessing Program at the Oak Ridge National Laboratory is also described. 19 refs., 19 figs

  6. Development of blanket remote maintenance system

    International Nuclear Information System (INIS)

    Kakudate, Satoshi; Nakahira, Masataka; Oka, Kiyoshi; Taguchi, Kou

    1998-01-01

    ITER in-vessel components such as blankets are scheduled maintenance components, including complete shield blanket replacement for breeding blankets. In-vessel components are activated by 14 MeV neutrons, so blanket maintenance requires remote handling equipment and tools able to handle heavy payloads of about 4 tons within a positioning accuracy of 2 mm under intense gamma radiation. To facilitate remote maintenance, blankets are segmented into 730 modules and rail-mounted vehicle remote maintenance was developed. According to the ITER R and D program, critical technology related to blanket maintenance was developed extensively through joint efforts of the Japan, EU, and U.S. home teams. This paper summarizes current blanket maintenance technology conducted by the Japan Home Team, including development of full-scale remote handling equipment and tools for blanket maintenance. (author)

  7. Development of divertor remote maintenance system

    Energy Technology Data Exchange (ETDEWEB)

    Takeda, Nobukazu; Oka, Kiyoshi; Akou, Kentaro; Takiguchi, Yuji [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    1998-04-01

    The ITER divertor is categorized as a scheduled maintenance component because of extreme heat and particle loads it is exposed to by plasma. It is also highly activated by 14 MeV neutrons. Reliable remote handling equipment and tools are required for divertor maintenance under intense gamma radiation. To facilitate remote maintenance, the divertor is segmented into 60 cassettes, and each cassette weighing about 25 tons and maintained and replaced through four maintenance ports each 90 degrees. Divertor cassettes must be transported toroidally and radially for replacement through maintenance ports. Remote handling involving cassette movers and carriers for toroidal and radial transport has been developed. Under the ITER R and D program, technology critical to divertor cassette maintenance is being developed jointly by Japan, E.U., and U.S. home teams. This paper summarizes divertor remote maintenance design and the status of technology development by the Japan Home Team. (author)

  8. Development of blanket remote maintenance system

    Energy Technology Data Exchange (ETDEWEB)

    Kakudate, Satoshi; Nakahira, Masataka; Oka, Kiyoshi; Taguchi, Kou [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    1998-04-01

    ITER in-vessel components such as blankets are scheduled maintenance components, including complete shield blanket replacement for breeding blankets. In-vessel components are activated by 14 MeV neutrons, so blanket maintenance requires remote handling equipment and tools able to handle heavy payloads of about 4 tons within a positioning accuracy of 2 mm under intense gamma radiation. To facilitate remote maintenance, blankets are segmented into 730 modules and rail-mounted vehicle remote maintenance was developed. According to the ITER R and D program, critical technology related to blanket maintenance was developed extensively through joint efforts of the Japan, EU, and U.S. home teams. This paper summarizes current blanket maintenance technology conducted by the Japan Home Team, including development of full-scale remote handling equipment and tools for blanket maintenance. (author)

  9. Development of divertor remote maintenance system

    International Nuclear Information System (INIS)

    Takeda, Nobukazu; Oka, Kiyoshi; Akou, Kentaro; Takiguchi, Yuji

    1998-01-01

    The ITER divertor is categorized as a scheduled maintenance component because of extreme heat and particle loads it is exposed to by plasma. It is also highly activated by 14 MeV neutrons. Reliable remote handling equipment and tools are required for divertor maintenance under intense gamma radiation. To facilitate remote maintenance, the divertor is segmented into 60 cassettes, and each cassette weighing about 25 tons and maintained and replaced through four maintenance ports each 90 degrees. Divertor cassettes must be transported toroidally and radially for replacement through maintenance ports. Remote handling involving cassette movers and carriers for toroidal and radial transport has been developed. Under the ITER R and D program, technology critical to divertor cassette maintenance is being developed jointly by Japan, E.U., and U.S. home teams. This paper summarizes divertor remote maintenance design and the status of technology development by the Japan Home Team. (author)

  10. Remote maintenance of future fusion reactors - a challenge for rad-hard components and smart control strategies

    International Nuclear Information System (INIS)

    Decreton, M.; Geeter, J. De

    1996-01-01

    The future fusion reactor will need frequent maintenance turns, involving inspection, repair and parts replacement inside the vacuum vessel. These operations will require high payload manipulations in constrained space under very high gamma-radiation dose-rates and temperature. Present research is being undertaken to qualify the components of the handling machine under representative conditions, in the framework of the ITER international consortium. Simultaneously, challenging control strategies will be needed to achieve reliable tasking under very poor viewing conditions and elementary sensing help. The paper reviews the present state of the art on both issues and present results of the ongoing research themes among the partners of the ITER programme. In particular, SCK''centre-dot''CEN coordinates the ITER T252 task on Radiation Tolerance Assessment of Remote Handling Components. (UK)

  11. Fusion reactor remote maintenance study. Final report

    International Nuclear Information System (INIS)

    Sniderman, M.

    1979-04-01

    An analysis of a major maintenance operation, the remote replacement of a modular sector of a tokamak reactor, was performed in substantial detail. Specific assumptions were developed which included concepts from various existing designs so that the operation which was studied includes some design features generic to any fusion reactor design. Based on the work performed in this study, the principal conclusions are: (1) It appears feasible to design a tokamak fusion reactor plant with availability comparable to existing fossil and fission plants, but this will require diligence and comprehensive planning during the complete design phase. (2) Since the total fusion program is paced by the success of each device, maintenance considerations must be incorporated into each device during design, even if the device is an experimental unit. (3) Innovative approaches, such as automatic computer controlled operations, should be developed so that large step reductions in planned maintenance times can be achieved

  12. Remote maintenance of tandem mirror hybrid coils

    International Nuclear Information System (INIS)

    Dietz, L.P.

    1983-01-01

    Hybrid Coils (superconducting coils with normal conducting inserts) are being employed with increasing frequency on Tandem Mirror Devices to obtain high field strengths. The normal conducting copper inserts are short lived in comparison to their encircling superconductors. It becomes desirable, therefore, to devise design features and maintenance procedures to replace the inner normal conducting coils without simultaneously replacing the longer lived (and significantly more costly) superconducting coils. The high neutron wall loadings require that the task be accomplished by remote control. The approach is to permanently mount the coil assemblies on track mounted carriages which serve, during machine operation merely as structural supports, but during maintenance procedures as moveable transport devices. The carriages incorporate all necessary provisions to facilitate remote maintenance operations and to adjust and align the coil assemblies with respect to adjacent machine components. The vacuum vessel is severed on both sides of the hybrid coil by means of a remote cutting machine. The entire coil is transported horizontally, normal to the machine axis to a nearby repair station. Prepositioned carriage mounted repair equipment at the repair station withdraws the damaged normal coil as a single entity and inserts a preassembled spare unit. The repaired hybrid coil is reassembled to the reactor. A cost and risk effective procedure has been evolved to maintain one of the more critical components of a Tandem Mirror Machine

  13. General Guidelines for Remote Operation and Maintenance of Pyroprocess Equipment

    Energy Technology Data Exchange (ETDEWEB)

    Kim, S. H.; Park, B. S.; Park, H. S.; Lee, H. J.; Choi, C. W.; Lee, J. K

    2007-12-15

    As the pyroprocess handle the high radioactive materials, a high radioactive material handling facility required high safety, radioactive shielding, strict quality control, and the remote handling equipment of high technology. This report describes the guidelines of for pyroprocess based the design guides for radioactive material handling facility and equipment from American Nuclear Society(ANS), design guidelines for remotely maintained equipment from Oak Ridge National Laboratory(ORNL), and the experience of design for ACP equipment installed at the ACPF(Advanced Conditioning Process Facility). The General guidelines in this report are as follows. The General guidelines for remote operation and maintenance of pyroprocess equipment: Pyroprocess, Remote handling equipment for pyroprocess, General guide for remote operation and maintenance, general guidelines for the design of remotely operated and maintained equipment, Estimation and analysis for remote maintenance.

  14. Remote operation and maintenance support services for nuclear power plants

    International Nuclear Information System (INIS)

    Yamamoto, Hiroki; Higuma, Koji; Shimizu, Shunichi; Sakuma, Masatake; Sonoda, Yukio; Kanemoto, Shigeru

    2004-01-01

    Toshiba Corporation constructed e-Toshiba Operating Plant Service (e-TOPS TM ) system and began remote operation and maintenance support service for nuclear power plants. The service put into practice remote operation and maintenance by harmony of information technologies such as internet and mobile, and nuclear power measurement/diagnostic technologies and security techniques. Outline of e-TOPS TM , remote-control service, -inspection system, -diagnostic service and technologies support service are explained. Construction, objects and application effects of e-TOPS TM , remote diagnostic system using image treatment techniques, construction of device record card control system are illustrated. (S.Y.)

  15. TPX in-vessel remote maintenance tooling

    International Nuclear Information System (INIS)

    Rennich, M.J.; Silke, G.W.

    1995-01-01

    The Tokamak Physics Experiment (TPX) has used the lessons learned from successful remote maintenance and remote handling facilities to develop both a concept and philosophy for incorporation of remote design from the earliest phases of the project. Initiation of mockup testing during the conceptual design phase leads to significant improvements in the basic maintenance equipment configuration. In addition, remote handling features and capabilities have been incorporated into the design of the plasma-facing components (PFCs) as part of the total PFC design effort

  16. NET test blanket design and remote maintenance

    International Nuclear Information System (INIS)

    Holloway, C.; Hubert, P.

    1991-01-01

    The NET machine has three horizontal ports reserved for testing tritium breeding blanket designs during the physics phase and possibly five during the technology phase. The design of the ports and test blankets are modular to accept a range of blanket options, provide radiation shielding and allow routine replacement. Radiation levels during replacement or maintenance require that all operations must be carried out remotely. The paper describes the problems overcome in providing a port design which includes attachment to the vacuum vessel with double vacuum seals, an integrated cooled first wall and support guides for the test blanket module. The method selected to remotely replace the test module whilst controlling the spread of contamination is also adressed. The paper concludes that the provisions of a test blanket facility based on the NET machine design is feasible. (orig.)

  17. A remote maintenance robot system for a pulsed nuclear reactor

    International Nuclear Information System (INIS)

    Thunborg, S.

    1987-01-01

    This paper presents a remote maintenance robot system for use in a hazardous environment. The system consists of turntable, robot and hoist subsystems which operate under the control of a supervisory computer to perform coordinated programmed maintenance operations on a pulsed nuclear reactor. The system is operational

  18. Remote controlled transport device

    International Nuclear Information System (INIS)

    Nakahira, Masataka; Oka, Kiyoshi; Ito, Akira; Tada, Eisuke; Sato, Masaki

    1998-01-01

    The present invention provides a device for transporting equipments for maintenance and parts between a maintenance port and a facility for maintenance by remote control in a radioactive material handling facility such as a nuclear power plant. Namely, a power supply bus bar is disposed along a transferring path in order to supply power to a transporting means, and is divided into every region having a predetermined length. Each of the power supply bus bar regions is controlled for the power supply by a control device. Accordingly, the transporting means can be moved and driven successively being independent on every power supply bus bar region. Accordingly, a plurality of transporting means can be operated independently in a transferring path without laying around power cables and control signal cables. (I.S.)

  19. Setting up and managing a remote maintenance operation for fusion

    International Nuclear Information System (INIS)

    Haist, Bernhard

    2008-01-01

    Trying to set up and manage a remote maintenance operation for a thermonuclear fusion reactor is a complex undertaking. There are many problems and challenges which need addressing. This paper tries to guide the reader through this process by composing a list of generic problems and by analysing possible solutions. The first challenge before setting up a remote maintenance operation for a fusion reactor is the systematic analysis of all the remote handling requirements. Based upon this the remote handling concept, including facility layout and equipment, can be defined. The following aspects have to be considered and incorporated into the remote handling concept: - Remote handling task development. - Remote handling task logistics and resource management. - Command, control and human-machine interface system. - Viewing and camera systems. - Virtual reality and Augmented Reality software. - Automatic path planning and collision avoidance. - Remote transfer of heavy loads. - Maintainability of RH equipment. - Reliability, redundant systems and safety. - Rationalisation and modularity in both hardware and software. - Recovery from failure modes. - Condition monitoring and fault detection/prediction. - Ability to deal with unforeseen problems. Oxford Technologies Ltd. has a proven track record in setting up and running the Remote Handling group at the JET Joint Undertaking in Culham, UK. Based on the unique experience gained at JET, Oxford Technologies Ltd. also developed the current design and remote handling concept of the ITER Hot Cell during a study in 2004. Examples of both the JET remote handling experience and the ITER Hot Cell design and layout are given throughout this paper

  20. Setting up and managing a remote maintenance operation for fusion

    International Nuclear Information System (INIS)

    Haist, B.

    2007-01-01

    Trying to set up and manage a remote maintenance operation for a thermonuclear fusion reactor is a complex undertaking. There are many problems and challenges which need addressing. This paper tries to guide the reader through this process by composing a list of generic problems and by analysing possible solutions. The first challenge before setting up a remote maintenance operation for a fusion reactor is the systematic analysis of all the remote handling requirements. Based upon this the remote handling concept, including facility layout and equipment, can be defined. The following aspects have to be considered and incorporated into the remote handling concept: - Remote handling task development - Remote handling task logistics and resource management - Command, control and human-machine interface system - Viewing and camera systems - Virtual Reality and Augmented Reality software - Automatic path planning and collision avoidance - Remote transfer of heavy loads - Maintainability of RH Equipment - Reliability, redundant systems and safety - Rationalisation and modularity in both hardware and software - Recovery from failure modes - Condition monitoring and fault detection/prediction - Ability to deal with unforeseen problems Oxford Technologies Ltd has a proven track record in setting up and running the Remote Handling group at the JET Joint Undertaking in Culham, UK. Based on the unique experience gained at JET, Oxford Technologies Ltd also developed the current design and remote handling concept of the ITER Hot Cell during a study in 2004. Examples of both the JET Remote Handling experience and the ITER Hot Cell design and layout are given throughout this paper. (orig.)

  1. Setting up and managing a remote maintenance operation for fusion

    Energy Technology Data Exchange (ETDEWEB)

    Haist, Bernhard [Oxford Technologies Ltd., 7 Nuffield Way, Abingdon, Oxon OX14 1RJ (United Kingdom)], E-mail: Bernhard.Haist@oxfordtechnologies.co.uk

    2008-12-15

    Trying to set up and manage a remote maintenance operation for a thermonuclear fusion reactor is a complex undertaking. There are many problems and challenges which need addressing. This paper tries to guide the reader through this process by composing a list of generic problems and by analysing possible solutions. The first challenge before setting up a remote maintenance operation for a fusion reactor is the systematic analysis of all the remote handling requirements. Based upon this the remote handling concept, including facility layout and equipment, can be defined. The following aspects have to be considered and incorporated into the remote handling concept: - Remote handling task development. - Remote handling task logistics and resource management. - Command, control and human-machine interface system. - Viewing and camera systems. - Virtual reality and Augmented Reality software. - Automatic path planning and collision avoidance. - Remote transfer of heavy loads. - Maintainability of RH equipment. - Reliability, redundant systems and safety. - Rationalisation and modularity in both hardware and software. - Recovery from failure modes. - Condition monitoring and fault detection/prediction. - Ability to deal with unforeseen problems. Oxford Technologies Ltd. has a proven track record in setting up and running the Remote Handling group at the JET Joint Undertaking in Culham, UK. Based on the unique experience gained at JET, Oxford Technologies Ltd. also developed the current design and remote handling concept of the ITER Hot Cell during a study in 2004. Examples of both the JET remote handling experience and the ITER Hot Cell design and layout are given throughout this paper.

  2. BPX commitment to total remote maintenance

    International Nuclear Information System (INIS)

    Davis, F.C.; Burgess, T.W.

    1991-01-01

    The Burning Plasma Experiment (BPX), to be located at Princeton Plasma Physics Laboratory, is the next major experimental machine in the US Fusion Program. It will be fueled with deuterium-tritium (D-T) that, when burned, will generate high-energy neutrons. This will activate the various materials used in construction of the machine, which will result in high levels of gamma radiation. Any subsequent maintenance activities on the machine or in the test cell area must be performed remotely. The initial criteria for BPX assumed that failure of toroidal field (TF) coil or poloidal field (PF) coil was an unlikely event. Therefore, no provisions were made for remote replacement. Expected failures were limited to the plasma-facing components and the external auxiliary equipment such as heating systems and diagnostics. Recent coil failures experienced at the Tokamak Fusion Test Reactor (TFTR), the Joint European Torus (JET), JT-60, and Tore Supra caused the BPX project staff to reconsider the need for remote replacement. A study was undertaken to investigate how the project would be affected if the capability to recover from a coil failure were required. Potential effects including configuration changes to the machine and facility, project cost, and project operation were considered. The study revealed that it is indeed feasible to design BPX for remote recovery from any coil failure. However, for this to be accomplished effectively, it is imperative to incorporate the necessary remote maintenance features of the components to be remotely replaced into the original design along with all of the other functional features. The remote maintenance capability cannot be retrofitted after the design is complete or the equipment is built. This paper discusses the impacts of the coil remote replacement study and the subsequent changes to the design. 4 figs., 1 tab

  3. Proceedings of FED remote maintenance equipment workshop

    International Nuclear Information System (INIS)

    Sager, P.; Garin, J.; Hager, E.R.; Spampinato, P.T.; Tobias, D.; Young, N.

    1981-11-01

    A workshop was convened in two sessions in January and March 1981, on the remote maintenance equipment for the Fusion Engineering Device (FED). The objectives of the first session were to familiarize the participants with the status of the design of the FED and to develop a remote maintenance equipment list for the FED. The objective of the second session was to have the participants present design concepts for the equipment which had been identified in the first session. The equipment list was developed for general purpose and special purpose equipment. The general purpose equipment was categorized as manipulators and other, while the special purpose equipment was subdivided according to the reactor subsystem it serviced: electrical, magnetic, and nuclear. Both mobile and fixed base manipulators were identified. Handling machines were identified as the major requirement for special purpose equipment

  4. New remote maintenance approach for TPX

    International Nuclear Information System (INIS)

    Davis, F.C.; Walker, M.S.; Brown, T.G.

    1993-01-01

    The Tokamak Physics Experiment (TPX), to be located at Princeton Plasma Physics Laboratory, will be a steady-state, high-performance fusion machine. It will use hydrogen fuel during its original operation, deuterium-deuterium (D-D) fuel for an extended intermediate period of time and then a limited number of runs using deuterium-tritium (D-T) fuel. The D-D operations wig generate neutron fluxes that will activate materials of the vacuum vessel. From that point on, the resulting ionizing radiation, which will continue to increase, particularly during D-T operation, will prevent personnel access into the vessel to perform either scheduled or unscheduled maintenance activities. All activities performed within the vacuum vessel must be accomplished using remote means. TPX has taken a new approach for remote maintenance of the components within the vacuum vessel. This document describes the system that is being developed

  5. ITER Remote Maintenance System (IRMS) lifecycle management

    Energy Technology Data Exchange (ETDEWEB)

    Tesini, Alessandro, E-mail: alessandro.tesini@iter.org [ITER Organization, CS 90 046, 13067 St. Paul Lez Durance Cedex (France); Otto' , Bede [Oxford Technologies Ltd, 7, Nuffield Way, Abingdon, Oxon OX14 1RJ (United Kingdom); Blight, John [FAAST 31c Allee de la Granette, 13600 Ceyreste (France); Choi, Chang-Hwan; Friconneau, Jean-Pierre; Gotewal, Krishan Kumar; Hamilton, David [ITER Organization, CS 90 046, 13067 St. Paul Lez Durance Cedex (France); Heckendorn, Frank [FD Technologies, PO Box 6686, Aiken, SC (United States); Martins, Jean-Pierre [ITER Organization, CS 90 046, 13067 St. Paul Lez Durance Cedex (France); Marty, Thomas [Westinghouse, 122, avenue de Hambourg, 13008 Marseille (France); Nakahira, Masataka; Palmer, Jim; Subramanian, Rajendran [ITER Organization, CS 90 046, 13067 St. Paul Lez Durance Cedex (France)

    2011-10-15

    The availability of the ITER machine to perform its scientific program is strongly dependent on the performance of the different Remote Handling (RH) systems constituting the ITER Remote Maintenance System (IRMS). The lifecycle of the IRMS will largely exceed 40 years from initial concept design and proof testing through to machine decommissioning. Such a long lifecycle requires that a rigorous approach is put in place to guarantee the technical capabilities of the highly innovative IRMS, its efficiency and its availability. For this purpose, an IRMS System Engineering and IRMS lifecycle management approach has been adopted by ITER. The approach aims at ensuring the IRMS full operability and availability at an acceptable cost of ownership over the full ITER machine assembly and operations period. The IRMS lifecycle management method described in this paper covers such subjects as specific requirements for IRMS design reviews, monitoring during manufacture, factory and site acceptance testing, integrated commissioning, decontamination, maintenance and re-qualification strategies, requirements for Integrated Logistical Support during operations. The updating and implementation of the IRMS lifecycle strategy and this procedure will be managed and monitored by the Remote Handling Integrated Product Team (RH-IPT). Although developed for the IRMS, the basic principles and procedures of lifecycle management could be applied to other ITER plant systems whose reliability and availability will be essential for the continued operation of the ITER machine.

  6. ITER Remote Maintenance System (IRMS) lifecycle management

    International Nuclear Information System (INIS)

    Tesini, Alessandro; Otto', Bede; Blight, John; Choi, Chang-Hwan; Friconneau, Jean-Pierre; Gotewal, Krishan Kumar; Hamilton, David; Heckendorn, Frank; Martins, Jean-Pierre; Marty, Thomas; Nakahira, Masataka; Palmer, Jim; Subramanian, Rajendran

    2011-01-01

    The availability of the ITER machine to perform its scientific program is strongly dependent on the performance of the different Remote Handling (RH) systems constituting the ITER Remote Maintenance System (IRMS). The lifecycle of the IRMS will largely exceed 40 years from initial concept design and proof testing through to machine decommissioning. Such a long lifecycle requires that a rigorous approach is put in place to guarantee the technical capabilities of the highly innovative IRMS, its efficiency and its availability. For this purpose, an IRMS System Engineering and IRMS lifecycle management approach has been adopted by ITER. The approach aims at ensuring the IRMS full operability and availability at an acceptable cost of ownership over the full ITER machine assembly and operations period. The IRMS lifecycle management method described in this paper covers such subjects as specific requirements for IRMS design reviews, monitoring during manufacture, factory and site acceptance testing, integrated commissioning, decontamination, maintenance and re-qualification strategies, requirements for Integrated Logistical Support during operations. The updating and implementation of the IRMS lifecycle strategy and this procedure will be managed and monitored by the Remote Handling Integrated Product Team (RH-IPT). Although developed for the IRMS, the basic principles and procedures of lifecycle management could be applied to other ITER plant systems whose reliability and availability will be essential for the continued operation of the ITER machine.

  7. Rigid hoist articulated grapple system development for enhanced remote maintenance

    International Nuclear Information System (INIS)

    Witham, C.; White, P.; Garin, J.

    1979-01-01

    Remote maintenance and repair within nuclear environments have become more demanding of remote manipulation equipment in the last few years. A deficiency exists in the array of tools available for dexterous operations of loads in the 180-kg range. The development of a manipulation system with enhanced operator controls is discussed. This system is a six-degree-of-freedom manipulator with bilateral servo control. It is to be attached to a mobile support boom in order to operate throughout the nuclear cell. The manipulator is intended to work in conjunction with light duty servomanipulators, overhead crane systems, and through-the-wall mechanical master slaves

  8. Remote systems and remote maintenance of a reprocessing plant in Japan

    International Nuclear Information System (INIS)

    Funaya, T.

    1977-01-01

    The design concept and overall maintenance philosophy applied in the Power Reactor and Nuclear Fuel Development Corporation Reprocessing Plant at Tokai-mura, Japan, are briefly introduced. Details on remote systems and remote maintenance in mechanical processing areas are described

  9. In-vessel maintenance remote manipulator system

    International Nuclear Information System (INIS)

    Jimenez, E.

    1978-01-01

    The radiation environment within the Tokamak Fusion Test Reactor (TFTR) vacuum vessel necessitates the development of a Remote Manipulator System (RMS) to perform required periodic inspection and maintenance tasks. The RMS must be able to perform dexterous operations and handle loads that exceed human capabilities. The limited size of the access ports on the TFTR vacuum vessel and the performance profile, defined by the various handling requirements, present unique design constraints. The design approach and formulation of a RMS configuration which satisfies TFTR requirements is presented herein

  10. The European contribution to the ITER Remote Maintenance

    Energy Technology Data Exchange (ETDEWEB)

    Damiani, C., E-mail: carlo.damiani@f4e.europa.eu [Fusion for Energy, Torres Diagonal Litoral B3, Josep Pla 2, 08019 Barcelona (Spain); Annino, C.; Balagué, S.; Bates, P.; Ceccanti, F.; Di Mascio, T.; Dubus, G.; Esqué, S.; Gonzalez, C.; Lewczanin, M.; Locke, D.; Mont, L.; Olajos, K.; Ranz, R.; Shuff, R.; Puiu, A.; Van Hille, C.; Van Uffelen, M. [Fusion for Energy, Torres Diagonal Litoral B3, Josep Pla 2, 08019 Barcelona (Spain); Choi, C.H.; Friconneau, J.P. [ITER Organization, Route de Vinon sur Verdon, 13115 Saint Paul Lez Durance (France); and others

    2014-10-15

    Highlights: •The article introduces the needs for remote maintenance in ITER. •It also discusses some of the issues related to the cultural transition from tokamaks as plasma physics to nuclear reactors. •It highlights the related cultural change and the implications on plant topology and maintenance. •Then, it presents those remote handling systems that will be procured by Europe. •The article emphasises the need of a major involvement of industries from now on. -- Abstract: For a first-of-a-kind nuclear fusion reactor like ITER, remote maintainability of neutron-activated components is one of the key aspects of plant design and operations, and a fundamental ingredient for the demonstration of long-term viability of fusion as energy source. The European Domestic Agency (EU DA, i.e. Fusion for Energy, F4E) is providing important support to the ITER Organisation (IO) in specifying the functional requirements of the Remote Handling (RH) Procurement Packages (i.e. the subsystems allocated to EU DA belonging to the overall ITER Remote Maintenance Systems IRMS), and in performing design and R and D activities – with the support of national laboratories and industries – in order to define a sound concept for these packages. Furthermore, domestic industries are being involved in the subsequent detailed design, validation, manufacturing and installation activities, in order to actually fulfil our procurement-in-kind obligations. After an introduction to ITER Remote Maintenance, this paper will present status and next stages for the RH systems allocated to EU DA, and will also illustrate complementary aspects related to cross cutting technologies like radiation tolerant components and RH control systems. Finally, the way all these efforts are coordinated will be presented together with the overall implementation scenario and key milestones.

  11. A remote control valve

    International Nuclear Information System (INIS)

    Cachard, Maurice de; Dumont, Maurice.

    1976-01-01

    This invention concerns a remote control valve for shutting off or distributing a fluid flowing at a high rate and low pressure. Among the different valves at present in use, electric valves are the most recommended for remote control but their reliability is uncertain and they soon become costly when large diameter valves are used. The valve described in this invention does away with this drawback owing to its simplicity and the small number of moving parts, this makes it particularly reliable. It mainly includes: a tubular body fitted with at least one side opening; at least one valve wedge for this opening, coaxial with the body, and mobile; a mobile piston integral with this wedge. Several valves to the specifications of this invention can be fitted in series (a shut-off valve can be used in conjunction with one or more distribution valves). The fitting and maintenance of the valve is very simple owing to its design. It can be fabricated in any material such as metals, alloys, plastics and concrete. The structure of the valve prevents the flowing fluid from coming into contact with the outside environment, thereby making it particularly suitable in the handling of dangerous or corrosive fluids. Finally, the opening and shutting of the valve occurs slowly, thereby doing away with the water hammer effect so frequent in large bore pipes [fr

  12. Development of a control system for a heavy object handling manipulator. Application to a remote maintenance system for ITER blanket module

    International Nuclear Information System (INIS)

    Yoshimi, Takashi; Tsuji, Kouichi; Miyagawa, Shinichi; Kubo, Tomomi; Kakudate, Satoshi; Tada, Eisuke

    2001-01-01

    This paper describes a control system for the heavy object handling manipulator. It has been developed for the blanket module remote maintenance system of ITER (International Thermonuclear Fusion Experimental Reactor). A rail-mounted vehicle-type manipulator is proposed for the precise handling of a blanket module which is about 4 tons in weight. Basically, this manipulator is controlled by teaching-playback technique. When grasping or releasing the module, the manipulator sags and the position of the end-effector changes about 50 [mm]. Applying only the usual teaching-playback control makes the smooth operation of setting/removing modules to/from the vacuum vessel wall difficult due to this position change. To solve this proper problem of heavy object handling manipulator, we have developed a system which uses motion patterns generated from two kinds of teaching points. These motion patterns for setting/removing heavy objects are generated by combining teaching points for positioning the manipulator with and without grasping the object. When these motion patterns are applied, the manipulator can transfer the object's weight smoothly at the setting/removing point. This developed system has been applied to the real-scale mock-up of the vehicle manipulator and through the actual module setting/removing experiments, we have verified its effectiveness and realized smooth maintenance operation. (author)

  13. Overview of progress on the European DEMO remote maintenance strategy

    Energy Technology Data Exchange (ETDEWEB)

    Crofts, Oliver, E-mail: oliver.crofts@ccfe.ac.uk [RACE/UKAEA, Culham Science Centre, Abingdon OX14 3DB, Oxon (United Kingdom); Loving, Antony; Iglesias, Daniel [RACE/UKAEA, Culham Science Centre, Abingdon OX14 3DB, Oxon (United Kingdom); Coleman, Matti [EUROfusion Consortium, PPP& T Department, Boltzmannstraße 2, 85748 Garching (Germany); Siuko, Mikko [VTT Technical Research Centre of Finland, PO Box 1000, FI-02044 VTT, Espoo (Finland); Mittwollen, Martin [KIT Institut für Fördertechnik und Logistiksysteme, Gotthard-Franz-Straße 8, Geb.50.38, 76131 Karlsruhe (Germany); Queral, Vicente [CIEMAT Laboratorio Nacional de Fusión, Edif. 66, Avenida Complutense 40, 28040 Madrid (Spain); Vale, Alberto [IST, Instituto Superior Técnico, Av. Rovisco Pais 1, 1049-001 Lisboa (Portugal); Villedieu, Eric [CEA, IRFM, 13108 St Paul lez Durance (France)

    2016-11-01

    Highlights: • The remote maintenance strategy is applicable to the range of tokamak and component options currently under consideration in Europe • The remote maintenance development work is concentrating on the application and limits of the immature technologies that pose the greatest risk to the feasibility of the maintenance strategy • Position control during the handling of the in-vessel components is one of the areas of high risk and a system is being developed and will be tested prior to concept design to demonstrate the feasibility and capability of a system capable of real time incorporation of changing kinematic data provided by a structural simulator running in parallel • In-vessel recovery and rescue and the pipe joining technology form two more of the high risk areas where developments are being concentrated - Abstract: The EU-DEMO remote maintenance strategy must be relevant for a range of in-vessel component design options. The remote maintenance project must provide an understanding of the limits of the strategy and technologies so as to inform the developing plant design of the maintenance constraints. A comprehensive set of maintenance requirements has been produced, in conjunction with the plant designers, against which design options can be assessed. The proposed maintenance solutions are based around a strategy that deploys casks above each of the vertical ports to exchange the blanket segments and at each of the divertor ports to exchange the divertor cassettes. The casks deploy remote handling equipment to open and close the vacuum vessel, remove and re-install pipework, and replace the in-vessel components. A technical design risk assessment has shown that the largest risks are common to all of the proposed solutions and that they are associated with two key issues, first; the ability to handle the large blanket and divertor components to the required positional accuracy with limited viewing and position feedback, and second; to

  14. Overview of progress on the European DEMO remote maintenance strategy

    International Nuclear Information System (INIS)

    Crofts, Oliver; Loving, Antony; Iglesias, Daniel; Coleman, Matti; Siuko, Mikko; Mittwollen, Martin; Queral, Vicente; Vale, Alberto; Villedieu, Eric

    2016-01-01

    Highlights: • The remote maintenance strategy is applicable to the range of tokamak and component options currently under consideration in Europe • The remote maintenance development work is concentrating on the application and limits of the immature technologies that pose the greatest risk to the feasibility of the maintenance strategy • Position control during the handling of the in-vessel components is one of the areas of high risk and a system is being developed and will be tested prior to concept design to demonstrate the feasibility and capability of a system capable of real time incorporation of changing kinematic data provided by a structural simulator running in parallel • In-vessel recovery and rescue and the pipe joining technology form two more of the high risk areas where developments are being concentrated - Abstract: The EU-DEMO remote maintenance strategy must be relevant for a range of in-vessel component design options. The remote maintenance project must provide an understanding of the limits of the strategy and technologies so as to inform the developing plant design of the maintenance constraints. A comprehensive set of maintenance requirements has been produced, in conjunction with the plant designers, against which design options can be assessed. The proposed maintenance solutions are based around a strategy that deploys casks above each of the vertical ports to exchange the blanket segments and at each of the divertor ports to exchange the divertor cassettes. The casks deploy remote handling equipment to open and close the vacuum vessel, remove and re-install pipework, and replace the in-vessel components. A technical design risk assessment has shown that the largest risks are common to all of the proposed solutions and that they are associated with two key issues, first; the ability to handle the large blanket and divertor components to the required positional accuracy with limited viewing and position feedback, and second; to

  15. Remote maintenance system technology development for nuclear fuel cycle plants

    International Nuclear Information System (INIS)

    Kashihara, Hidechiyo

    1984-01-01

    The necessity of establishing the technology of remote maintenance, the kinds of maintenance techniques and the change, the image of a facility adopting remote maintenance canyon process, and the outline of the R and D plan to put remote maintenance canyon process in practical use are described. As the objects of development, there are twin arm type servo manipulator system, rack system, remote tube connectors, solution sampling system, inspection system for in-cell equipment, and large plugs for wall penetration. The outline of those are also reported. The development of new remote maintenance technology has been forwarded in the Tokai Works aiming at the application to a glass solidification pilot plant and a FBR fuel recycling test facility. The lowering of the rate of utilization of cells due to poor accessibility and the increase of radiation exposure of workers must be overcome to realize nuclear fuel cycle technology. The maintenance technology is classified into crane canyon method, direct maintenance cell method, remote maintenance cell method and remote maintenance canyon method, and those are described briefly. The development plan of remote maintenance technology is outlined. (Kako, I.)

  16. Analysis of ITER upper port plug remote handling maintenance scenarios

    International Nuclear Information System (INIS)

    Koning, J.F.; Baar, M.R. de; Elzendoorn, B.S.Q.; Heemskerk, C.J.M.; Ronden, D.M.S.; Schuth, W.J.

    2012-01-01

    Highlights: ► Remote Handling Study Centre: providing RH compatibility analysis. ► Simulation: virtual reality including kinematics and realtime physics simulator. ► Applied on analysis of RH compatibility of Upper Launcher component replacement. ► Resulting in lowered maintenance procedure time and lessons learned. - Abstract: The ITER tokamak has a modular design, with port plugs, blanket modules and divertor cassettes. This set-up allows for maintenance of diagnostics, heating systems and first wall elements. The maintenance can be done in situ, or in the Hot Cell. Safe and effective remote handling (RH) will be ensured by the RH requirements and standards. Compliance is verified through remote handling compatibility assessments at the ITER Design Review milestones. The Remote Handling Study Centre at FOM Institute DIFFER is created to study ITER RH maintenance processes at different levels of complexity, from relatively simple situational awareness checks using snap-shots in the CAD system, time studies using virtual reality (VR) animations, to extensive operational sequence validation with multiple operators in real-time. The multi-operator facility mimics an RH work-cell as presently foreseen in the ITER RH control room. Novel VR technology is used to create a realistic setting in which a team of RH operators can interact with virtual ITER environments. A physics engine is used to emulate real-time contact interaction as to provide realistic haptic feed-back. Complex interactions between the RH operators and the control room system software are tested. RH task performance is quantified and operational resource usage estimated. The article provides a description and lessons learned from a recent study on replacement of the Steering Mirror Assembly on the ECRH (Electron Cyclotron Resonance Heating) Upper Launcher port plug.

  17. Analysis of ITER upper port plug remote handling maintenance scenarios

    Energy Technology Data Exchange (ETDEWEB)

    Koning, J.F., E-mail: j.f.koning@heemskerk-innovative.nl [FOM Institute DIFFER - Dutch Institute for Fundamental Energy Research, Association EURATOM-FOM, Partner in the Trilateral Euregio Cluster and ITER-NL, PO Box 1207, 3430 BE Nieuwegein (Netherlands); Baar, M.R. de; Elzendoorn, B.S.Q. [FOM Institute DIFFER - Dutch Institute for Fundamental Energy Research, Association EURATOM-FOM, Partner in the Trilateral Euregio Cluster and ITER-NL, PO Box 1207, 3430 BE Nieuwegein (Netherlands); Heemskerk, C.J.M. [Heemskerk Innovative Technology, Noordwijk (Netherlands); Ronden, D.M.S.; Schuth, W.J. [FOM Institute DIFFER - Dutch Institute for Fundamental Energy Research, Association EURATOM-FOM, Partner in the Trilateral Euregio Cluster and ITER-NL, PO Box 1207, 3430 BE Nieuwegein (Netherlands)

    2012-08-15

    Highlights: Black-Right-Pointing-Pointer Remote Handling Study Centre: providing RH compatibility analysis. Black-Right-Pointing-Pointer Simulation: virtual reality including kinematics and realtime physics simulator. Black-Right-Pointing-Pointer Applied on analysis of RH compatibility of Upper Launcher component replacement. Black-Right-Pointing-Pointer Resulting in lowered maintenance procedure time and lessons learned. - Abstract: The ITER tokamak has a modular design, with port plugs, blanket modules and divertor cassettes. This set-up allows for maintenance of diagnostics, heating systems and first wall elements. The maintenance can be done in situ, or in the Hot Cell. Safe and effective remote handling (RH) will be ensured by the RH requirements and standards. Compliance is verified through remote handling compatibility assessments at the ITER Design Review milestones. The Remote Handling Study Centre at FOM Institute DIFFER is created to study ITER RH maintenance processes at different levels of complexity, from relatively simple situational awareness checks using snap-shots in the CAD system, time studies using virtual reality (VR) animations, to extensive operational sequence validation with multiple operators in real-time. The multi-operator facility mimics an RH work-cell as presently foreseen in the ITER RH control room. Novel VR technology is used to create a realistic setting in which a team of RH operators can interact with virtual ITER environments. A physics engine is used to emulate real-time contact interaction as to provide realistic haptic feed-back. Complex interactions between the RH operators and the control room system software are tested. RH task performance is quantified and operational resource usage estimated. The article provides a description and lessons learned from a recent study on replacement of the Steering Mirror Assembly on the ECRH (Electron Cyclotron Resonance Heating) Upper Launcher port plug.

  18. Remote maintenance challenges presented in the ITER engineering design

    International Nuclear Information System (INIS)

    Burgess, T.W.; Herndon, J.N.; Schrock, S.L.; Lousteau, D.C.

    1995-01-01

    Leading fusion energy research institutions are currently engaged in the Engineering Design Activity for the International Thermonuclear Experimental Reactor (ITER). A tokamak reactor design is evolving which emphasizes high system performance in a minimum overall reactor and building size. The resulting high component density dictates careful attention to ITER remote maintenance considerations in the development of the configuration. The complexity and scale of ITER remote maintenance tasks are well beyond the scope of today's experience and technology. This paper discusses the remote maintenance philosophy, describes the basic configuration as it relates to maintenance, and describes the basic procedures and equipment required. Key enabling technology research and development needs are also addressed

  19. Comparative evaluation of remote maintenance schemes for fusion DEMO reactor

    Energy Technology Data Exchange (ETDEWEB)

    Utoh, Hiroyasu, E-mail: uto.hiroyasu@jaea.go.jp; Tobita, Kenji; Someya, Youji; Asakura, Nobuyuki; Sakamoto, Yoshiteru; Hoshino, Kazuo; Nakamura, Makoto

    2015-10-15

    Highlights: • Various remote maintenance schemes for DEMO were comparatively assessed based on requirements for DEMO remote maintenance. • The banana shape segment transport using all vertical maintenance ports would be more probable DEMO reactor maintenance scheme. • The key engineering issues are in-vessel transferring mechanism of segment, pipe connection and conducting shell design for plasma vertical stability. - Abstract: Maintenance schemes are one of the critical issues in DEMO design, significantly affecting the configuration of in-vessel components, the size of toroidal field (TF) coil, the arrangement of poloidal field (PF) coils, reactor building, hot cell and so forth. Therefore, the maintenance schemes should satisfy many design requirements and criteria to assure reliable and safe plant operation and to attain reasonable plant availability. The plant availability depends on reliability of remote maintenance scheme, inspection of pipe connection and plasma operation. In this paper, various remote maintenance schemes for DEMO were comparatively assessed based on requirements for DEMO remote maintenance. From the view points of the reliability of inspection on hot cell, TF coil size, stored energy of PF coil and portability of segment, the banana shape segment transport using all vertical maintenance ports would be more probable DEMO reactor maintenance scheme, and it has key engineering issues such as in-vessel transferring mechanism of segment, pipe connection and conducting shell design for plasma vertical stability.

  20. Comparative evaluation of remote maintenance schemes for fusion DEMO reactor

    International Nuclear Information System (INIS)

    Utoh, Hiroyasu; Tobita, Kenji; Someya, Youji; Asakura, Nobuyuki; Sakamoto, Yoshiteru; Hoshino, Kazuo; Nakamura, Makoto

    2015-01-01

    Highlights: • Various remote maintenance schemes for DEMO were comparatively assessed based on requirements for DEMO remote maintenance. • The banana shape segment transport using all vertical maintenance ports would be more probable DEMO reactor maintenance scheme. • The key engineering issues are in-vessel transferring mechanism of segment, pipe connection and conducting shell design for plasma vertical stability. - Abstract: Maintenance schemes are one of the critical issues in DEMO design, significantly affecting the configuration of in-vessel components, the size of toroidal field (TF) coil, the arrangement of poloidal field (PF) coils, reactor building, hot cell and so forth. Therefore, the maintenance schemes should satisfy many design requirements and criteria to assure reliable and safe plant operation and to attain reasonable plant availability. The plant availability depends on reliability of remote maintenance scheme, inspection of pipe connection and plasma operation. In this paper, various remote maintenance schemes for DEMO were comparatively assessed based on requirements for DEMO remote maintenance. From the view points of the reliability of inspection on hot cell, TF coil size, stored energy of PF coil and portability of segment, the banana shape segment transport using all vertical maintenance ports would be more probable DEMO reactor maintenance scheme, and it has key engineering issues such as in-vessel transferring mechanism of segment, pipe connection and conducting shell design for plasma vertical stability.

  1. The remote control system

    International Nuclear Information System (INIS)

    Jansweijer, P.P.M.

    1988-01-01

    The remote-control system is applied in order to control various signals in the car of the spectrometer at distance. The construction (hardware and software) as well as the operation of the system is described. (author). 20 figs

  2. Remote maintenance systems requirements are being developed to provide design guidelines for machine components, to define maintenance interfaces, and to quantify maintenance equipment and procedures needed

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Tabor, M.A.

    1988-01-01

    Remote maintenance systems requirements are being developed to provide design guidelines for machine components, to define maintenance interfaces, and to quantify maintenance equipment and procedures needed

  3. Research and development of remote maintenance equipment for ITER divertor maintenance

    International Nuclear Information System (INIS)

    Takeda, Nobukazu; Kakudate, Satoshi; Nakahira, Masataka

    2005-02-01

    To facilitate easy remote maintainability, the ITER divertor is divided into 60 cassettes, which are transported in the toroidal and radial directions for replacement through maintenance ports located every 90 degrees using the divertor remote maintenance equipment such as in- and ex-vessel transporters. The cassette of 25 tons has to be transported and installed in the vacuum vessel with a positioning accuracy less than 2 mm in the limited space of the vacuum vessel and maintenance port under the intense gamma radiation field. Based on these requirements, the following design and tests were performed. (1) Link mechanism was studied to apply to the transportation of the heavy cassette in the restricted space. A compact mechanism with links for transportation of heavy cassette is designed through the optimization of the link angle taking account of space requirement and force efficiency. As a test result, the lifting capacity of 30 tons (larger than the cassette weight of 25 tons) using two link mechanisms has been demonstrated in the limited space. (2) Compact link mechanism was also studied to apply for locking of the cassette through the optimization of the link angle taking account of space requirement and force efficiency. As a test result, the final positioning accuracy of 0.03 mm for the 25 tons-cassette installation on the vacuum vessel from the initial positioning error of 5 mm has been demonstrated, so that the test result satisfies the requirement less than 2 mm using the link mechanisms in the limited space. (3) Sensor-based control using simple sensors such as optical fiber for divertor maintenance was tested using the full-scale mock-up divertor cassette and remote maintenance equipment. As a result, it is found that the positioning accuracy of 0.16 mm has been achieved by the optical fiber sensor and this value is sufficient for sensor-based control. In addition, the maintenance operation has been carried out through the human-machine interface

  4. Potential application of nuclear remote-handling technology to underwater inspection and maintenance

    International Nuclear Information System (INIS)

    Eccleston, M.J.

    1990-01-01

    Examples are given of remote handling equipment developed within the nuclear industry and employing telemanipulative or telerobotic principles. In telerobotics the nuclear industry has been following a trend towards increased levels of autonomy, delegating operator control to a computer, for example, in resolved rate manipulator tip control, teach-and-repeat control and collision avoidance. Illustrations are presented of remote-handling techniques from the nuclear industry which may be carried over into undersea remote inspection, maintenance and repair systems. (author)

  5. Head-end reprocessing equipment remote maintenance demonstration

    International Nuclear Information System (INIS)

    Evans, J.H.; Metz, C.F. III.

    1989-01-01

    Prototype equipment for reprocessing breeder reactor nuclear fuel was installed in the Remote Operation and Maintenance Demonstration (ROMD) area of the Consolidated Fuel Reprocessing Program (CFRP) facility at the Oak Ridge National Laboratory (ORNL) in order to evaluate the design of this equipment in a cold mock-up of a remotely maintained hot cell. This equipment included the Remote Disassembly System (RDS) and the Remote Shear System (RSS). These systems were disassembled and reassembled remotely by using the extensive remote handling systems that are installed in this simulated hot-cell environment. 5 refs., 5 figs

  6. Equipment and special tool design for remote maintenance

    International Nuclear Information System (INIS)

    Northey, L.M.; Thomson, J.D.

    1985-01-01

    Maintenance tasks performed in locations with hostile environments and/or limited space accesses often require equipment that is operated remotely. This paper discusses considerations that should be addressed in the design of remote maintenance equipment. Some of the topics include proper material selection, interface identifications, operational feedback devices and cost limitations. These considerations add ''human engineering'' to the equipment design to assure protection of the tool and the operating personnel. Examples of remote maintenance and inspection systems that were developed by the Westinghouse Hanford Company and that utilize many of these design considerations are included

  7. Remote handling design for moderator-reflector maintenance in JSNS

    International Nuclear Information System (INIS)

    Teshigawara, Makoto; Aizawa, Hideyuki; Harada, Masahide; Kinoshita, Hidetaka; Meigo, Shinichiro; Maekawa, Fujio; Kaminaga, Masanori; Kato, Takashi; Ikeda, Yujiro

    2005-05-01

    This report introduces the present design status of remote-handling devices for activated and used components such as moderator and reflector in a spallation neutron source of the Material and Life Science Facility (MLF) at J-PARC (Japan Proton Accelerator Research Complex). The design concept and maintenance scenario are also mentioned. A key maintenance scenario adopts that the used components should be taken out from the MLF to the other storage facility after the volume reduction of them. Almost full remote handling is available to the maintenance work except for the connection/disconnection pipes of the cooling water. Remote handling for the cooling water system is under designing and it will be prepared before being significant radiation dose by accumulation of beryllium ( 7 Be) in future. Total six remote handling devices are used for moderator-reflector maintenance. They are also available to the proton beam window and muon target maintenance. Maintenance scenario is separated into two works. One is to replace used components to new ones during beam-stop and the other is dispose used components during beam operation. Required period of replacement work is estimated to be ∼15 days, on the other hand, the disposal work is ∼26 days after dry up work (∼30 days), respectively. Study of the maintenance scenario and the remote handling design brings about the reasonable procedures and period of the maintenance work. (author)

  8. Remote Operation and Maintenance Demonstration Facility at ORNL

    International Nuclear Information System (INIS)

    Harvey, H.W.; Floyd, S.D; Kuban, D.P.; Singletary, B.H.; Stradley, J.G.

    1978-01-01

    The Remote Operation and Maintenance Facility is a versatile facility arranged to mock-up various hot-cell configurations. Modular units of simulated shielding and viewing windows were built to provide flexibility in arrangement. The facility is fully equipped with hoists, manipulators, television, and the other basic equipment and services necessary to provide capability for both remote operation and maintenance of several selected functional process equipment groups. 6 figures

  9. Remote operation and maintenance demonstration facility at ORNL

    International Nuclear Information System (INIS)

    Harvey, H.W.; Floyd, S.D.; Kuban, D.P.; Singletary, B.H.; Stradley, J.G.

    1978-01-01

    The Remote Operation and Maintenance Facility is a versatile facility arranged to mock up various hot cell configurations. Modular units of simulated shielding and viewing windows were built to provide flexibility in arrangement. The facility is fully equipped with hoists, manipulators, television, and other basic equipment and services necessary to provide capability for both remote operation and maintenance of several selected functional process equipment groups

  10. Remote maintenance in the building of the reactor of power plants

    International Nuclear Information System (INIS)

    Bonin, R.

    1984-01-01

    Examples describing the different operations requiring remote control for reactor maintenance are given. These operations include: refueling machines (for closure stud, vessel flange cleaning, screwing plug for channel head, swimming pool decontamination) in-service inspection machines (MIS, spider for eddy current testing of steam generator, television) and routine or accidental maintenance (leak detection in water boxes, maintenance spider, opening or closing primary manways, decontamination manipulators and various automatic control devices) [fr

  11. Tandem mirror next step: remote maintenance

    International Nuclear Information System (INIS)

    Doggett, J.N.; Damm, C.C.; Hanson, C.L.

    1980-01-01

    This study of the next proposed experiment in the Mirror Fusion Program, the Tandem Mirror Next Step (TMNS), has included serious consideration of the maintenance requirements of such a large source of high energy neutrons with its attendant throughput of tritium. Although maintenance will be costly in time and money, our conclusion is that with careful attention to a design for maintenance plan such a device can be reliably operated

  12. Robotics and remote maintenance concepts for fusion machines

    International Nuclear Information System (INIS)

    1989-02-01

    Descriptions of operation and maintenance of current tokamaks (TFTR, JET, JT-60) is discussed in the context of radioactivation resulting from thermonuclear reactions. Plans for future devices (NET, CIT, FGR) with respect to remote handling, maintenance, measurements, and robotics are discussed. Refs, figs and tabs

  13. Remotely controlled spray gun

    Science.gov (United States)

    Cunningham, William C. (Inventor)

    1987-01-01

    A remotely controlled spray gun is described in which a nozzle and orifice plate are held in precise axial alignment by an alignment member, which in turn is held in alignment with the general outlet of the spray gun by insert. By this arrangement, the precise repeatability of spray patterns is insured.

  14. Ex-vessel remote maintenance for the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Macdonald, D.

    1987-01-01

    The use of deuterium-tritium (D-T) fuel for operation of the Compact Ignition Tokamak (CIT) requires the use of remote handling technology to carry out maintenance operations on the machine. These operations consist in removing and repairing such components as diagnostic modules by using remotely operated maintenance equipment. The major equipment being developed for maintenance external to the plasma chamber includes a bridge-mounted manipulator system for test cell operations, decontamination (decon) equipment, hot cell equipment, and solid-radiation-waste-handling equipment. Wherever possible, the project will use commercially available equipment. Several areas of the maintenance system design were addressed in fiscal year (FY) 1987, including conceptual designs of manipulator systems, the start of a remote equipment research and development (RandD) program, and definition of the hot cell, decon, and equipment repair facility requirements. R and D work included preliminary demonstrations of remote handling operations on full-size, partial mock-ups of the CIT machine at the Oak Ridge National Laboratory (ORNL) Remote Operations and Maintenance Development (ROMD) Facility. 1 ref., 6 figs

  15. Remote maintenance concepts for the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Davis, F.C.; Hager, E.R.

    1988-01-01

    Because deuterium-tritium fuel will be used in the Compact Ignition Tokamak (CIT), remote handling technology is needed to carry out some maintenance operations on the machine. In keeping with the compact, low-cost nature of CIT, remote maintenance is provided only for systems with the highest probability of failure. Remote operations include removing, repairing (if feasible), and replacing such components as thermal protection tiles on the first wall, radio-frequency (rf) heating modules, and diagnostic modules. For maintenance inside the vacuum vessel, major pieces of equipment under development include an articulated boom manipulator with servomanipulators, an inspection manipulator, and special tooling. For maintenance outside the cryostat, remote equipment includes a bridge-mounted manipulator system, equipment for decontamination and hot cell activities, and for handling and packaging solid radioactive waste. The conceptual design phase of the CIT project is nearing completion; research and development activities in support of the project include demonstrations of remote maintenance operations on full-size partial mock-ups. 9 figs

  16. In-vessel remote maintenance of the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Tabor, M.A.; Hager, E.R.; Creedon, R.L.; Fisher, M.V.; Atkin, S.D.

    1987-01-01

    The Compact Ignition Tokamak (CIT) is the first deuterium-tritium (D-T) fusion device that will study the physics of an ignited plasma. The ability of the tokamak vacuum vessel to be maintained remotely while under vacuum has not been fully demonstrated on previous machines, and this ability will be critical to the efficient and safe operation of ignition devices. Although manned entry into the CIT vacuum vessel will be possible during the nonactivated stages of operation, remotely automated equipment will be used to assist in initial assembly of the vessel as well as to maintain all in-vessel components once the D-T burn is achieved. Remote maintenance and operation will be routinely required for replacement of thermal protection tiles, inspection of components, leak detection, and repair welding activities. Conceptual design to support these remote maintenance activities has been integrated with the conceptual design of the in-vessel components to provide a complete and practical remote maintenance system for CIT. The primary remote assembly and maintenance operations on CIT will be accomplished through two dedicated 37- x 100-cm ports on the main toroidal vessel. Each port contains a single articulated boom manipulator (ABM), which is capable of accessing half of the torus. The proposed ABM consists of a movable carriage assembly, telescoping two-part mast, and articulated link sections. 1 ref

  17. Remote maintenance lessons learned on prototypical reprocessing equipment

    International Nuclear Information System (INIS)

    Kring, C.T.; Schrock, S.L.

    1990-01-01

    A major objective of the Consolidated Fuel Reprocessing Program at the Oak Ridge National Laboratory is to develop and demonstrate the technology required to reprocess spent nuclear fuel. The Fuel Recycle Division, over the past 16 years, has undertaken this objective by designing and testing prototypical hardware representing essentially every major equipment item currently included in most fuel reprocessing plant conceptual designs. These designs are based on total remote maintenance to increase plant availability and reduce radiation exposure to plant operators. The designs include modular equipment to facilitate maintainability and the remote manipulation necessary to accomplish maintenance tasks. Prototypic equipment has been installed and tested in a cold mock-up of a reprocessing hot cell, called the remote operations and maintenance demonstration facility. The applied maintenance concept utilizes the dexterity and mobility of bridge-mounted, force-reflecting servomanipulators. Prototypic processing equipment includes a remote disassembly system, a remote shear system, a rotary dissolver, a remote automated sampler system, removable equipment racks to support chemical process equipment items, and the advanced servomanipulators. Each of these systems and a brief description of functions are discussed

  18. Pre-conceptual design assessment of DEMO remote maintenance

    Energy Technology Data Exchange (ETDEWEB)

    Loving, A., E-mail: antony.loving@ccfe.ac.uk [EURATOM/Culham Center Fusion Energy, Culham Science Centre, OX14 3DB, Abingdon (United Kingdom); Crofts, O.; Sykes, N.; Iglesias, D.; Coleman, M.; Thomas, J. [EURATOM/Culham Center Fusion Energy, Culham Science Centre, OX14 3DB, Abingdon (United Kingdom); Harman, J. [EFDA Close Support Unit Garching, Boltzmannstaße 2, D-85748 Garching Bei München (Germany); Fischer, U. [Karlsruhe Institute of Technology, Institute for Neutron Physics and Reactor Technology, Hermann-von-Helmholtz-Platz 1, D-76344 Eggenstein-Leopoldshafen (Germany); Sanz, J. [Instituto de Fusión Nuclear/UPM, Madrid (Spain); Siuko, M. [VTT Technical Research Centre of Finland, P.O. Box 1000, FI-02044 VTT (Finland); Mittwollen, M. [Karlsruhe Institute of Technology, Institut für Fördertechnik und Logistiksysteme, Gotthard-Franz-Straße 8, Geb.50.38, 76131 Karlsruhe (Germany)

    2014-10-15

    EDFA, as part of the Power Plant Physics and Technology programme, has been working on the pre-conceptual design of a Demonstration Power Plant (DEMO). As part of this programme, a review of the remote maintenance strategy considered maintenance solutions compatible with expected environmental conditions, whilst showing potential for meeting the plant availability targets. A key finding was that, for practical purposes, the expected radiation levels prohibit the use of complex remote handling operations to replace the first wall. In 2012/2013, these remote maintenance activities were further extended, providing an insight into the requirements, constraints and challenges. In particular, the assessment of blanket and divertor maintenance, in light of the expected radiation conditions and availability, has elaborated the need for a very different approach from that of ITER. This activity has produced some very informative virtual reality simulations of the blanket segments and pipe removal that are exceptionally valuable in communicating the complexity and scale of the required operations. Through these simulations, estimates of the maintenance task durations have been possible demonstrating that a full replacement of the blankets within 6 months could be achieved. The design of the first wall, including the need to use sacrificial limiters must still be investigated. In support of the maintenance operations, a first indication of the requirements of an Active Maintenance Facility (AMF) has been elaborated.

  19. ITER L 6 equatorial maintenance duct remote handling study

    International Nuclear Information System (INIS)

    Millard, J.

    1996-09-01

    The status and conclusions of a preliminary study of equatorial maintenance duct remote handling is reported. Due to issues with the original duct design a significant portion of the study had to be refocused on equatorial duct layout studies. The study gives an overview of some of the options for design of these ducts and the impact of the design on the equipment to work in the duct. To develop a remote handling concept for creating access through the ducts the following design tasks should be performed: define the operations sequences for equatorial maintenance duct opening and closing; review the remote handling requirements for equatorial maintenance duct opening and closing; design concept for door and pipe handling equipment and to propose preliminary procedures for material handling outsides the duct. 35 figs

  20. Guidelines for Remote Handling Maintenance of ITER Neutral Beam Components

    International Nuclear Information System (INIS)

    Cordier, J.-J.; Hemsworth, R.; Bayetti, P.

    2006-01-01

    Remote handling maintenance of ITER components is one of the main challenges of the ITER project. This type of maintenance shall be operational for the nuclear phase of exploitation of ITER, and be considered at a very early stage since it significantly impacts on the components design, interfaces management and integration business. A large part of the R/H equipment will be procured by the EU partner, in particular the whole Neutral Beam Remote Handling (RH) equipment package. A great deal of work has already been done in this field during the EDA phase of ITER project, but improvements and alternative option that are now proposed by ITER lead to added RH and maintenance engineering studies. The Neutral Beam Heating -and- Current Drive system 1 is being revisited by the ITER project. The vertical maintenance scheme that is presently considered by ITER, may significantly impact on the reference design of the Neutral Beam (NB) system and associated components and lead to new design of the NB box itself. In addition, revision of both NB cell radiation level zoning and remote handling classification of the beam line injector will also significantly impact on components design and maintenance. Based on the experience gained on the vertical maintenance scheme, developed in detail for the ITER Neutral Beam Test Facility 2 to be built in Europe in a near future, guidelines for the revision of the design and preliminary feasibility study of the remote handling vertical maintenance scheme of beam line components are described in the paper. A maintenance option for the SINGAP3 accelerator is also presented. (author)

  1. Remote maintenance design for Fusion Experimental Reactor (FER)

    International Nuclear Information System (INIS)

    Tachikawa, K.; Iida, H.; Nishio, S.; Tone, T.; Aota, T.; Iwamoto, T.; Niikura, S.; Nishizawa, H.

    1984-01-01

    Design of Fusion Experimental Reactor, FER, has been conducted by Japan Atomic Energy Research Institute (JAERI) since 1981. Two typical reactors can be classified in general from the viewpoints of remote maintenance among four design concepts of FER. In the case of the type 1 FER, the torus module consists of shield structure and blanket, and the connective joints between toruses provided at the outer region of the reactor. As for the type 2 FER, the shield structure is joined with the vacuum cryostat, and only the blanket module is allowed to move, but connection between toruses are located in the inner region of the reactor. Comparing type 1 with type 2 FER, this paper describes on the remote maintenance of FER including reactor configurations, work procedures, remote systems/equipments, repairing facility and future R and D problems. Reviewing design studies and investigation for the existing robotics technologies, R and D for FER remote maintenance technology should be performed under the reasonable long-term program. The main items of remote technology required to start urgently are multi-purpose manipulator system with performance of dextrousity, tele-viewing system which reduces operator fatigue and remote tests for commercially available components

  2. Remote Maintenance Design Guide for Compact Processing Units

    Energy Technology Data Exchange (ETDEWEB)

    Draper, J.V.

    2000-07-13

    Oak Ridge National Laboratory (ORNL) Robotics and Process Systems (RPSD) personnel have extensive experience working with remotely operated and maintained systems. These systems require expert knowledge in teleoperation, human factors, telerobotics, and other robotic devices so that remote equipment may be manipulated, operated, serviced, surveyed, and moved about in a hazardous environment. The RPSD staff has a wealth of experience in this area, including knowledge in the broad topics of human factors, modular electronics, modular mechanical systems, hardware design, and specialized tooling. Examples of projects that illustrate and highlight RPSD's unique experience in remote systems design and application include the following: (1) design of a remote shear and remote dissolver systems in support of U.S. Department of Energy (DOE) fuel recycling research and nuclear power missions; (2) building remotely operated mobile systems for metrology and characterizing hazardous facilities in support of remote operations within those facilities; (3) construction of modular robotic arms, including the Laboratory Telerobotic Manipulator, which was designed for the National Aeronautics and Space Administration (NASA) and the Advanced ServoManipulator, which was designed for the DOE; (4) design of remotely operated laboratories, including chemical analysis and biochemical processing laboratories; (5) construction of remote systems for environmental clean up and characterization, including underwater, buried waste, underground storage tank (UST) and decontamination and dismantlement (D&D) applications. Remote maintenance has played a significant role in fuel reprocessing because of combined chemical and radiological contamination. Furthermore, remote maintenance is expected to play a strong role in future waste remediation. The compact processing units (CPUs) being designed for use in underground waste storage tank remediation are examples of improvements in systems

  3. Remote maintenance for fusion: Requirements vs technology gap

    International Nuclear Information System (INIS)

    Davis, F.C.; Kuban, D.P.

    1989-01-01

    Today's remote handling technology was developed in response to the remote maintenance (RM) requirements of the fission community's nuclear fuel recycle process. The needs of the fusion community present new challenges to the remote handling experts of the world. New difficulties are superimposed on the difficulties experienced in maintaining fission processes. Today's technology must be enhanced to respond to the RM needs of these future huge investments. This paper first discusses the current RM needs for fusion based on existing facilities and designs of future machines. It then exposes the gap between these requirements and existing RM technology and recommends ways to extend the state of the art to close this gap

  4. Managing and controlling maintenance

    International Nuclear Information System (INIS)

    Chavez, G.; Perla, H.F.

    1980-01-01

    A well-planned maintenance-management program can bring organized yet flexible scheduling, improved productivity, and a ready-access data bank. The system detailed in the article, developed for a nuclear power plant, has application to any equipment-intensive facility. Key features of the system include: documentation of all work requirements and their completion; automated prioritizing of work orders; automatic generation of work orders for repetitive work, when due; work lists in priority sequence; deferred, standby, and outage work reports; labor and work-order backlog information; equipment work histories and cumulative failure data

  5. Remote maintenance for a new generation of hot cells

    International Nuclear Information System (INIS)

    Feldman, M.J.; Grant, N.R.

    1987-01-01

    For several years the Consolidated Fuel Reprocessing Program at the Oak Ridge National Laboratory has been developing facility concepts, designing specialized equipment, and testing prototypical hardware for reprocessing spent fuel from fast breeder reactors. The major facility conceptual design, the Hot Experimental Facility, was based on total remote maintenance to increase plant availability and to reduce radiation exposure. This thrust included designing modular equipment to facilitate maintenance and the manipulation necessary to accomplish maintenance. Included in the design repetoire was the development effort in advanced servomanipulator systems, a remote sampling system, television viewing, and a transporter system, television viewing, and a transporter for manipulator positioning. Demonstration of these developed items is currently ongoing, and the technology is available for applications where production operations in highly radioactive environments are required

  6. Remote maintenance for a new generation of hot cells

    International Nuclear Information System (INIS)

    Feldman, M.J.; Grant, N.R.

    1987-01-01

    For several years the Consolidated Fuel Reprocessing Program (CFRP) at Oak Ridge National Laboratory (ORNL) has been developing facility concepts, designing specialized equipment, and testing prototypical hardware for reprocessing spent fuel from fast breeder reactors. The major facility conceptual design, the Hot Experimental Facility, was based on total remote maintenance to increase plant availability and to reduce radiation exposure. This thrust included designing modular equipment to facilitate maintenance and the manipulation necessary to accomplish maintenance. Included in the design repetoire was the development effort in advanced servomanipulator systems, a remote sampling system, television viewing, and a transporter for manipulator positioning. Demonstration of these developed items is currently ongoing, and the technology is available for applications where production operations in highly radioactive environments are required

  7. Wireless Remote Control System

    Directory of Open Access Journals (Sweden)

    Adrian Tigauan

    2012-06-01

    Full Text Available This paper presents the design of a wireless remote control system based on the ZigBee communication protocol. Gathering data from sensors or performing control tasks through wireless communication is advantageous in situations in which the use of cables is impractical. An Atmega328 microcontroller (from slave device is used for gathering data from the sensors and transmitting it to a coordinator device with the help of the XBee modules. The ZigBee standard is suitable for low-cost, low-data-rate and low-power wireless networks implementations. The XBee-PRO module, designed to meet ZigBee standards, requires minimal power for reliable data exchange between devices over a distance of up to 1600m outdoors. A key component of the ZigBee protocol is the ability to support networking and this can be used in a wireless remote control system. This system may be employed e.g. to control temperature and humidity (SHT11 sensor and light intensity (TSL230 sensor levels inside a commercial greenhouse.

  8. Remote maintenance techniques in the furnace cell of a high level waste vitrification plant

    International Nuclear Information System (INIS)

    Selig, M.

    1983-01-01

    Remote controlled maintenance and changing techniques for the furnace of a vitrification plant for radioactive waste was developed and tested on a 1:1 model. The model was fitted out with imitation main components, remote control equipment, lead-ins and the complete tubing so that the trials could be carried out in a manner replicating as closely as possible the situation found under operating conditions. The development of remote-handled tube cable connectors, tube cable jumpers and plugs and sockets was an important aspect of the developmental programme. (orig.) [de

  9. Remote maintenance ''lessons learned'' on prototypical reprocessing equipment

    International Nuclear Information System (INIS)

    Kring, C.T.; Schrock, S.L.

    1990-01-01

    Hardware representative of essentially every major equipment item necessary for reprocessing breeder reactor nuclear fuel has been installed and tested for remote maintainability. This testing took place in a cold mock-up of a remotely maintained hot cell operated by the Consolidated Fuel Reprocessing Program (CFRP) within the Fuel Recycle Division at Oak Ridge National Laboratory (ORNL). The reprocessing equipment tested included a Disassembly System, a Shear System, a Dissolver System, an Automated Sampler System, removable Equipment Racks on which various chemical process equipment items were mounted, and an advanced servomanipulator (ASM). These equipment items were disassembled and reassembled remotely by using the remote handling systems that are available within the cold mock-up area. This paper summarizes the ''lessons learned'' as a result of the numerous maintenance activities associated with each of these equipment items. 4 refs., 3 figs., 1 tab

  10. Remote maintenance of Compact Ignition Tokamak ex-vessel systems

    International Nuclear Information System (INIS)

    DePew, R.E.; Macdonald, D.

    1989-01-01

    The use of deuterium-tritium (D-T) fuel in the Compact Ignition Tokamak (CIT) will require applying remote handling technology for ex-vessel maintenance and replacement of machine components. Highly activated and contaminated components of the fusion device's auxiliary systems, such as diagnostics and RF heating, must be replaced using remotely operated maintenance equipment in the test cell. Throughout the CIT remote maintenance (RM) studies conducted to date, computer modeling has been used extensively to investigate manipulator access in these complex, tightly packed, and cluttered surroundings. A recent refinement of computer modeling involves the use of an intelligent engineering work station for realtime interactive display of task simulations. This paper discusses the use of three-dimensional (3-D) kinematic computer models of the CIT machines that are proving to be powerful tools in our efforts to evaluate RM requirements. This presentation includes a video-taped simulation of remote replacement of a plasma viewing assembly. The simulation illustrates some of the constraints associated with typical RM activities and the ways in which computer modeling enhances the design process. 1 ref., 3 figs

  11. Remote-maintenance features of the Fusion Materials Irradiation Test (FMIT) facility lithium system

    International Nuclear Information System (INIS)

    Kelly, V.P.

    1981-01-01

    The FMIT Facitlity has been redesigned to allow remote maintenance of lithium system components such as the main lithium pump, heat exchanger, traps, and valves. Remote versus contact maintenance is required due to the limited effectiveness of methods planned for control of the radioisotope 7 Be which is formed in the lithium during the neutron generating process. The altered FMIT arrangement provides cubicles for isolation of the main pump and system dump valve to allow personnel access for completing welds on large diameter piping after replacing failed components. Maintenance on other components such as the main heat exchanger and traps will be done remotely. The resulting arrangement provides full capability to meet the required facility availability criteria with minimum impact on the facility and with minimum associated development costs

  12. Remote control manipulator

    Energy Technology Data Exchange (ETDEWEB)

    Sugawara, T

    1970-02-28

    A prior-art remote control manipulator comprises a horizontal suspension section, a master arm and a slave arm which are coupled to ends of the suspension section in a manner to pivotally move relative to the suspension section, and a connecting device which includes a tape and which joins both the arms. When the connecting device malfunctions, the slave arm can neither be extended nor contracted. Means to keep the tension of the tape is required which restricts the extension length of the slave arm. Further, the slave arm can be moved only in the axial direction. The invention described provides an improved remote control manipulator of the specified type. A moving device which moves the slave arm relative to the master arm without the intervention of the connecting device is mounted on a movable part of the slave arm, while pulleys which maintain the joining relationship of the connecting device are mounted on the movable part and fixed part of the slave arm. Owing to this construction, movement of the slave arm is assured despite troubles which may arise in the connecting device. In addition, no slack arises in the tape. By applying a similar construction to the horizontal suspension section, the suspension section can be stretched, and hence, the slave arm can be moved in a direction orthogonal to its axis.

  13. Development of remote maintenance technology for nuclear fuel reprocessing plants

    International Nuclear Information System (INIS)

    Kawahara, Akira; Saito, Masayuki; Kawamura, Hironobu; Yamade, Atsushi; Sugiyama, Sen; Sugiyama, Sakae.

    1986-01-01

    In the plants for reprocessing spent nuclear fuel containing fission products, due to the facts that the facilities are in high radiations fields, and the surfaces of equipments are contaminated with radioactive substances, the troubles of process equipments are directly connected to the remarkable drop of the rate of operation of the facilities. Therefore, the development of various remote maintenance techniques has been carried out so far, but this time, Hitachi Ltd. got a chance to take part in the repair of spent fuel dissolving tanks in the Tokai Reprocessing Plant of Power Reactor and Nuclear Fuel Development Corp. and the development of several kinds of remote checkup equipment related to the repair work. Especially in the repair of the dissolving tanks, a radiation-withstanding checkup and repair apparatus which has high remote operability taking the conditions of radioactive environment and the restriction of the repaired objects in consideration was required, and a dissolving tank repairing robot composed of six kinds has been developed. The key points of the development were the selective use of high radiation-withstanding parts and materials, small size structure and the realization of full remote operability. The full remote maintenance apparatus of this kind is unique in the world, and applicable to wide fields. (Kako, I.)

  14. Blanket maintenance by remote means using the cassette blanket approach

    International Nuclear Information System (INIS)

    Werner, R.W.

    1978-01-01

    Induced radioactivity in the blanket and other parts of a fusion reactor close to the plasma zone will dictate remote assembly, disassembly, and maintenance procedures. Time will be of the essence in these procedures. They must be practicable and certain. This paper discusses the reduction of a complicated Tokamak reactor to a simpler assembly via the use of a vacuum building in which to house the reactor and the introduction in this new model of cassette blanket modules. The cassettes significantly simplify remote handling

  15. Manipulator system for remote maintenance of fusion experimental reactor

    International Nuclear Information System (INIS)

    Shibanuma, Kiyoshi; Munakata, Tadashi; Murakami, Shin; Kondoh, Mitsunori.

    1991-01-01

    We have completed the conceptual design for a rail-mounted vehicle type remote maintenance system for the fusion experimental reactor (FER), which will be the first D-T burning reactor in Japan. We have fabricated a 1/5-scale model and confirmed the feasibility of the design. In this system, a rail is deployed into the vessel and supported at four horizontal ports. A vehicle then moves along the rail and handles in-vessel components with manipulators. The advantages of this concept are the high stiffness and high reliability of the rail, and the high mobility of the vehicle for efficient maintenance operations. In the FER, this concept is considered to be the first option for in-vessel maintenance. This paper describes the conceptual design of the system and the feasibility study using the 1/5-scale model. (author)

  16. Remote maintenance considerations for swimming pool tokamak reactor

    International Nuclear Information System (INIS)

    Niikura, S.; Yamada, M.; Kasai, M.

    1983-01-01

    Swimming Pool Tokamak Reactor (SPTR) is one of the candidate devices which are expected to demonstrate physical and engineering feasibility for fusion power reactors. In SPTR, water shield is adopted instead of solid shield structures. Among the advantages of SPTR are, from viewpoint of remote maintenance, small handling weight and high space availability between TF coils and a vacuum vessel. On the other hand, high dose rate during reactor repair and adverse effects on remote maintenance equipment by the shielding water might be the disadvantage of SPTR, where it is assumed that the shielding water is drained during reactor repair. Since the design of SPTR is still at the preliminary stage, for remote maintenance, much effort has been directed to clarification of design conditions such as environment and handling weight. As for the remote maintenance system concepts, studies have been focussed on those for a vacuum vessel and its internal structure (blanket, divertor and protection walls) expected to be repaired more frequently. The vacuum vessel assembly is divided into 21 sectors and number of TF coils is 14. A pair of TF coils are connected with each other by antitorque beams on the whole side surface. Vacuum vessel cassettes and associated blanket, divertor and protection walls are replaced through seven windows between TF coils pairs. Therefore each vacuum vessel cassette is required moving mechanisms in toroidal and radial directions. Options for slide mechanisms are wheels, balls, rollers and water bearings. Options for driving the cassette are self-driving by hydraulic motors and external driving by rack-pinion, wires or specific vehicles. As a result of studies, the moving mechanism with wheels and hydraulic motors has been selected for the reference design, and the system with water bearings and rack-pinion as an alternative. Furthermore typical concepts have been obtained for remote maintenance equipment such as wall-mounted manipulators, tools for

  17. Human factors in remote control engineering development activities

    International Nuclear Information System (INIS)

    Clarke, M.M.; Hamel, W.R.; Draper, J.V.

    1983-01-01

    Human factors engineering, which is an integral part of the advanced remote control development activities at the Oak Ridge National Laboratory, is described. First, work at the Remote Systems Development Facility (RSDF) has shown that operators can perform a wide variety of tasks, some of which were not specifically designed for remote systems, with a dextrous electronic force-reflecting servomanipulator and good television remote viewing capabilities. Second, the data collected during mock-up remote maintenance experiments at the RSDF have been analyzed to provide guidelines for the design of human interfaces with an integrated advanced remote maintenance system currently under development. Guidelines have been provided for task allocation between operators, remote viewing systems, and operator controls. 6 references, 5 figures, 2 tables

  18. Current status of research and development on remote maintenance for fusion components

    International Nuclear Information System (INIS)

    Takeda, Nobukazu; Kakudate, Satoshi; Nakahira, Masataka; Shibanuma, Kiyoshi

    2008-01-01

    There is a growing attention to remote maintenance of nuclear fusion reactors. Remote maintenance is planned in ITER tokamak to keep the health of in-vessel components like blankets and divertors. In this article, current status of the development in the remote maintenance equipments and methods, especially for ITER tokamak are reviewed. The newly developed vehicle type and boom type maintenance devices, manipulator, and transfer cask are illustrated. (J.P.N.)

  19. Hand-eye coordinative remote maintenance in a tokamak vessel

    Energy Technology Data Exchange (ETDEWEB)

    Qiu, Qiang, E-mail: qiu6401@sjtu.edu.cn; Gu, Kai, E-mail: gukai0707@sjtu.edu.cn; Wang, Pengfei, E-mail: wpf790714@163.com; Bai, Weibang, E-mail: 654253204@qq.com; Cao, Qixin, E-mail: qxcao@sjtu.edu.cn

    2016-03-15

    Highlights: • If there is not rotation between the visual coordinate frame (O{sub e}X{sub e}Y{sub e}) and hand coordinate frame (O{sub h}X{sub h}Y{sub h}), a person can coordinate the movement between hand and eye easily. • We establish an alignment between the movement of the operator's hand and the visual scene of the end-effector as displayed on the monitor. • A potential function is set up in a simplified vacuum vessel model to provide a fast collision checking, and the alignment between repulsive force and Omega 7 feedback force is accomplished. • We carry out an experiment to evaluate its performance in a remote handling task. - Abstract: The reliability is vitally important for the remote maintenance in a tokamak vessel. In order to establish a more accurate and safer remote handling system, a hand-eye coordination method and an artificial potential function based collision avoidance method were proposed in this paper. At the end of this paper, these methods were implemented to a bolts tightening maintenance task, which was carried out in our 1/10 scale tokamak model. Experiment results have verified the value of the hand-eye coordination method and the collision avoidance method.

  20. Hand-eye coordinative remote maintenance in a tokamak vessel

    International Nuclear Information System (INIS)

    Qiu, Qiang; Gu, Kai; Wang, Pengfei; Bai, Weibang; Cao, Qixin

    2016-01-01

    Highlights: • If there is not rotation between the visual coordinate frame (O_eX_eY_e) and hand coordinate frame (O_hX_hY_h), a person can coordinate the movement between hand and eye easily. • We establish an alignment between the movement of the operator's hand and the visual scene of the end-effector as displayed on the monitor. • A potential function is set up in a simplified vacuum vessel model to provide a fast collision checking, and the alignment between repulsive force and Omega 7 feedback force is accomplished. • We carry out an experiment to evaluate its performance in a remote handling task. - Abstract: The reliability is vitally important for the remote maintenance in a tokamak vessel. In order to establish a more accurate and safer remote handling system, a hand-eye coordination method and an artificial potential function based collision avoidance method were proposed in this paper. At the end of this paper, these methods were implemented to a bolts tightening maintenance task, which was carried out in our 1/10 scale tokamak model. Experiment results have verified the value of the hand-eye coordination method and the collision avoidance method.

  1. Potential applications of advanced remote handling and maintenance technology to future waste handling facilities

    International Nuclear Information System (INIS)

    Kring, C.T.; Herndon, J.N.; Meacham, S.A.

    1987-01-01

    The Consolidated Fuel Reprocessing Program (CFRP) at the Oak Ridge National Laboratory (ORNL) has been advancing the technology in remote handling and remote maintenance of in-cell systems planned for future US nuclear fuel reprocessing plants. Much of the experience and technology developed over the past decade in this endeavor are directly applicable to the in-cell systems being considered for the facilities of the Federal Waste Management System (FWMS). The ORNL developments are based on the application of teleoperated force-reflecting servomanipulators controlled by an operator completely removed from the hazardous environment. These developments address the nonrepetitive nature of remote maintenance in the unstructured environments encountered in a waste handling facility. Employing technological advancements in dexterous manipulators, as well as basic design guidelines that have been developed for remotely maintained equipment and processes, can increase operation and maintenance system capabilities, thereby allowing the attainment of two Federal Waste Management System major objectives: decreasing plant personnel radiation exposure and increasing plant availability by decreasing the mean-time-to-repair in-cell maintenance and process equipment

  2. Potential applications of advanced remote handling and maintenance technology to future waste handling facilities

    International Nuclear Information System (INIS)

    Kring, C.T.; Herndon, J.N.; Meacham, S.A.

    1987-01-01

    The Consolidated Fuel Reprocessing Program (CFRP) at the Oak Ridge National Laboratory (ORNL) has been advancing the technology in remote handling and remote maintenance of in-cell systems planned for future U.S. nuclear fuel reprocessing plants. Much of the experience and technology developed over the past decade in this endeavor are directly applicable to the in-cell systems being considered for the facilities of the Federal Waste Management System (FWMS). The ORNL developments are based on the application of teleoperated force-reflecting servomanipulators controlled by an operator completely removed from the hazardous environment. These developments address the nonrepetitive nature of remote maintenance in the unstructured environments encountered in a waste handling facility. Employing technological advancements in dexterous manipulators, as well as basic design guidelines that have been developed for remotely maintained equipment and processes, can increase operation and maintenance system capabilities, thereby allowing the attainment of two Federal Waste Management System major objectives: decreasing plant personnel radiation exposure and increasing plant availability by decreasing the mean-time-to-repair in-cell maintenance and process equipment

  3. Designing remote monitoring systems for long term maintenance and reliability

    International Nuclear Information System (INIS)

    Davis, G.E.; Johnson, G.L.; Schrader, F.D.; Stone, M.A.; Wilson, E.F.

    2001-01-01

    Full text: As part of the effort to modernize safeguards equipment, the IAEA is continuing to acquire and install equipment for upgrading obsolete surveillance systems with digital technology; and providing remote-monitoring capabilities where and when economically justified. Remote monitoring is expected to reduce inspection effort, particularly at storage facilities and reactor sites. Remote monitoring technology will not only involve surveillance, but will also include seals, sensors, and other unattended measurement equipment. LLNL's experience with the Argus Security System offers lessons for the design, deployment, and maintenance of remote monitoring systems. Argus is an integrated security system for protection of high-consequence U.S. Government assets, including nuclear materials. Argus provides secure transmission of sensor data, administrative data, and video information to support intrusion detection and access control functions. LLNL developed and deployed the Argus system on its own site in 1988. Since that time LLNL has installed, maintained, and upgraded Argus systems at several Department of Energy and Department of Defense sites in the US as well as at the original LLNL site. Argus has provided high levels of reliability and integrity, as well as reducing overall lifecycle cost through incremental improvements to hardware and software. This philosophy permits expansion of functional capability, hardware upgrade and software upgrade without system outages and with minimum outage of local functions. This presentation will describe Argus design strategies and lessons learned from the Argus program as they apply to the design, development, and maintenance of a remote monitoring network. Hardware failures, software failures, and communication outages are expected and must be addressed by astute selection of system architecture. A combination of redundancy, diversity, and effective functional allocation between field and system level components should

  4. Development of a standard methodology for optimizing remote visual display for nuclear maintenance tasks

    Science.gov (United States)

    Clarke, M. M.; Garin, J.; Prestonanderson, A.

    A fuel recycle facility being designed at Oak Ridge National Laboratory involves the Remotex concept: advanced servo-controlled master/slave manipulators, with remote television viewing, will totally replace direct human contact with the radioactive environment. The design of optimal viewing conditions is a critical component of the overall man/machine system. A methodology was developed for optimizing remote visual displays for nuclear maintenance tasks. The usefulness of this approach was demonstrated by preliminary specification of optimal closed circuit TV systems for such tasks.

  5. Development of radiation hardness components for ITER remote maintenance

    Energy Technology Data Exchange (ETDEWEB)

    Obara, Kenjiro; Kakudate, Satoshi; Oka, Kiyoshi; Ito, Akira [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment; Yagi, Toshiaki; Morita, Yousuke

    1998-04-01

    In the ITER, in-vessel remote handling is required to assemble and maintain in-vessel components in DT operations. Since in-vessel remote handling systems must operate under intense gamma ray radiation exceeding 30 kGy/h, their components must have sufficiently high radiation hardness to allow maintenance long enough in ITER in-vessel environments. Thus, extensive radiation tests and quality improvement, including optimization of material compositions, have been conducted through the ITER R and D program to develop radiation hardness components that meet radiation doses from 10 to 100 MGy at 10 kGy/h. This paper presents the latest on radiation hardness component development conducted by the Japan Home Team as a contribution to the ITER. The remote handling components tested are categorized for use in robotic or viewing systems, or as common components. Radiation tests have been conducted on commercially available products for screening, on modified products, and on new products to improve the radiation hardness. (author)

  6. Development of radiation hardness components for ITER remote maintenance

    International Nuclear Information System (INIS)

    Obara, Kenjiro; Kakudate, Satoshi; Oka, Kiyoshi; Ito, Akira; Yagi, Toshiaki; Morita, Yousuke

    1998-01-01

    In the ITER, in-vessel remote handling is required to assemble and maintain in-vessel components in DT operations. Since in-vessel remote handling systems must operate under intense gamma ray radiation exceeding 30 kGy/h, their components must have sufficiently high radiation hardness to allow maintenance long enough in ITER in-vessel environments. Thus, extensive radiation tests and quality improvement, including optimization of material compositions, have been conducted through the ITER R and D program to develop radiation hardness components that meet radiation doses from 10 to 100 MGy at 10 kGy/h. This paper presents the latest on radiation hardness component development conducted by the Japan Home Team as a contribution to the ITER. The remote handling components tested are categorized for use in robotic or viewing systems, or as common components. Radiation tests have been conducted on commercially available products for screening, on modified products, and on new products to improve the radiation hardness. (author)

  7. Systematic approach to remote maintenance in the fuels and materials examination facility

    International Nuclear Information System (INIS)

    Frandsen, G.B.; Nash, C.R.; Divona, C.J.; May, R.F.

    1979-01-01

    The Fuels and Materials Examination Facility (FMEF) is systematically analyzed from a remote maintenance standpoint using functional analysis methods. From the analysis the remote maintainability of equipment is ascertained, required tooling lists are formed, and maintenance downtimes are established. These techniques identify deficiencies or inefficiencies in the early design stage where changes have a minimum impact on cost. Special tooling and fixture requirements are minimized by standardizing remote maintenance design features

  8. Design, fabrication, and mockup testing in the Remote Maintenance Development Facility

    International Nuclear Information System (INIS)

    Carter, J.A.; Jacobs, R.T.; Bingham, G.E.

    1978-01-01

    The Remote Maintenance Development Facility (RMDF) at the Idaho National Engineering Laboratory (INEL) was installed and used extensively for full-scale development, mockup and testing of remote maintenance requirements for the New Waste Calcining Facility (NWCF). By performing remote handling tests, the NWCF handling concepts, techniques and remote capabilities were proven workable prior to construction. Presented in this paper is a description of the RMDF and its purpose, functions, and handling capabilities as they were used in support of the NWCF

  9. Design, fabrication, and mockup testing in the remote maintenance development facility

    International Nuclear Information System (INIS)

    Carter, J.A.; Jacobs, R.T.; Bingham, G.E.

    1978-01-01

    The Remote Maintenance Development Facility at the Idaho National Engineering Laboratory was installed and used extensively for full-scale development, mockup, and testing of remote maintenance requirements for the New Waste Calcining Facility (NWCF). By performing remote handling tests, the NWCF handling concepts, techniques, and remote capabilities were proven workable prior to construction. A description of the RMDF and its purpose, functions, and handling capabilities as they were used in support of the NWCF is presented

  10. Adaptive Control Of Remote Manipulator

    Science.gov (United States)

    Seraji, Homayoun

    1989-01-01

    Robotic control system causes remote manipulator to follow closely reference trajectory in Cartesian reference frame in work space, without resort to computationally intensive mathematical model of robot dynamics and without knowledge of robot and load parameters. System, derived from linear multivariable theory, uses relatively simple feedforward and feedback controllers with model-reference adaptive control.

  11. Remotely controllable liquid marbles

    KAUST Repository

    Zhang, Lianbin

    2012-07-26

    Liquid droplets encapsulated by self-organized hydrophobic particles at the liquid/air interface - liquid marbles - are prepared by encapsulating water droplets with novel core/shell-structured responsive magnetic particles, consisting of a responsive block copolymer-grafted mesoporous silica shell and magnetite core (see figure; P2VP-b-PDMS: poly(2-vinylpyridine-b- dimethylsiloxane)). Desirable properties of the liquid marbles include that they rupture upon ultraviolet illumination and can be remotely manipulated by an external magnetic field. 2012 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim.

  12. Remote maintenance in TOR fast reactor fuel reprocessing facility

    International Nuclear Information System (INIS)

    Eymery, R.; Constant, M.; Malterre, G.

    1986-11-01

    The TOR facility which is undergoing commissioning tests has a capacity of 5 T. HM/year which is enough for reprocessing all the Phenix fuel, with an excess capacity which is to be used for other fast reactors fuels. It is the result of enlargement and renovation of the old Marcoule pilot facility. A good load factor is expected through the use of equipment with increased reliability and easy maintenance. TOR will also be used to test new equipment developed for the large breeder fuel reprocessing plant presently in the design stage. The latter objective is specifically important for the parts of the plant involving mechanical equipment which are located in a new building: TOR 1. High reliability and flexibility will be obtained in this building thanks to the attention given to the integrated remote handling system [fr

  13. Development of a standard methodology for optimizing remote visual display for nuclear-maintenance tasks

    International Nuclear Information System (INIS)

    Clarke, M.M.; Garin, J.; Preston-Anderson, A.

    1981-01-01

    The aim of the present study is to develop a methodology for optimizing remote viewing systems for a fuel recycle facility (HEF) being designed at Oak Ridge National Laboratory (ORNL). An important feature of this design involves the Remotex concept: advanced servo-controlled master/slave manipulators, with remote television viewing, will totally replace direct human contact with the radioactive environment. Therefore, the design of optimal viewing conditions is a critical component of the overall man/machine system. A methodology has been developed for optimizing remote visual displays for nuclear maintenance tasks. The usefulness of this approach has been demonstrated by preliminary specification of optimal closed circuit TV systems for such tasks

  14. Analysis of the ITER ECH Upper Port Launcher remote maintenance using virtual reality

    NARCIS (Netherlands)

    Elzendoorn, B.; Baar, M. de; Chavan, R.; Goodman, T.; Heemskerk, C.; Heidinger, R.; Kleefeldt, K.; Koning, J.; Sanders, S.; Späh, P.; Strauss, D.; Verhoeven, T.; Vreede, F. de

    2009-01-01

    All ITER sub-systems of remote handling (RH) classes 1 and 2 have to be remotely maintainable. The maintenance strategy for these components has to ensure system availability after failure or scheduled maintenance. This paper shows how virtual reality (VR) simulation [1] can be used as a tool to

  15. Advanced remote handling for future applications: The advanced integrated maintenance system

    International Nuclear Information System (INIS)

    Herndon, J.N.; Kring, C.T.; Rowe, J.C.

    1986-01-01

    The Consolidated Fuel Reprocessing Program at Oak Ridge National Laboratory has been developing advanced techniques for remote maintenance of future US fuel reprocessing plants. The developed technology has a wide spectrum of application for other hazardous environments. These efforts are based on the application of teleoperated, force-reflecting servomanipulators for dexterous remote handling with television viewing for large-volume hazardous applications. These developments fully address the nonrepetitive nature of remote maintenance in the unstructured environments encountered in fuel reprocessing. This paper covers the primary emphasis in the present program; the design, fabrication, installation, and operation of a prototype remote handling system for reprocessing applications, the Advanced Integrated Maintenance System

  16. Remote maintenance demonstration tests at a pilot plant for high level waste vitrification

    International Nuclear Information System (INIS)

    Selig, M.

    1984-01-01

    The remote maintenance and replacement technique designed for a radioactive vitrification plant have been developed and tested in a full scale handling mockup and in an inactive pilot plants by the Central Engineering Department of the Karlsruhe Nuclear Research Center. As a result of the development work and the tests it has been proved that the remote maintenance technique and remote handling equipment can be used without any technical problems and are suited for application in a radioactive waste vitrification plant

  17. Remote manipulation techniques in the maintenance and repair of nuclear power plants

    International Nuclear Information System (INIS)

    Rininsland, H.; Boehme, G.

    1986-01-01

    Remote manipulation means the application of multi-purpose devices featuring high mobility and universal applicability. The paper describes such a remote manipulation system (manipulation vehicle MF1 and MF2, master-slave manipulator, TFTR maintenance manipulator) which can be used flexibly in the NNP during maintenance and repair and in incident and accident situations. Connecting elements and tools can be redesigned for remote manipulation to meet the specific application environments. (DG) [de

  18. Remote mixed oxide fabrication facility development. Volume 2. State-of-the-art review of remote maintenance system technology

    International Nuclear Information System (INIS)

    Horgos, R.M.; Masch, M.L.

    1979-06-01

    This report provides a state-of-the-art review of remote systems technology, which includes manipulators, process connectors, vision systems and specialized process systems. A proposed mixed oxide fuel fabrication facility was reviewed and evaluated for identification of major remote maintenance and repair tasks. The technological areas were evaluated on the basis of their suitability or applicability for remote maintenance and repair of a proposed fully remote operating mixed oxide fuel fabrication facility. A technological base exists from which the design criteria for a reliable, remote operating facility can be established. Commercially available systems and components, along with those remote technologies now in development, will require modifications to adapt them to specific plant designs and requirements

  19. Issues in radioactivity for fusion energy: remote maintenance rating

    International Nuclear Information System (INIS)

    Dorn, D.W.; Maninger, R.C.

    1983-01-01

    Recent technical progress in fusion research has been sufficient to encourage the development of conceptual designs for fusion power systems. These design efforts suggest that more attention should be paid to the safety and environmental effects of the radioactivity induced in the structural materials by the fusion neutrons. In particular, radioactivity from neutron activation of the structural components of a fusion power system will be a concern for occupational exposure of personnel. Careful choice of structural materials can significantly reduce this exposure. We propose the Remote Maintenance Rating (RMR) as a numerical means of comparing materials and machine designs with respect to occupational exposures. The RMR is defined as the dose rate at the surface of a uniformly activated, thick, infinite slab with the same composition and density as the machine component. We used the RMR rating system to evaluate the suitability of several different iron-based alloys. The specific fusion power system design used in our evaluation was a conceptual design from the Mirror Advanced Reactor Study (MARS). We determined that HT-9 is significantly better in terms of radiological dose rates at early times than the other iron-based alloys (by a factor of 3 to 7). We also calculated the behavior of both silicon carbide (SiC) and aluminum (Al), two low activation materials often proposed for reactors

  20. Man-rem exposure--a forcing function in remote maintenance of nuclear plants

    International Nuclear Information System (INIS)

    Erion, T.L.

    1979-01-01

    The purpose of this paper is to show the need for remote tooling systems in order to comply with the proposed NRC strategies relative to occupational radiation exposure (ORE) during maintenance outages. In addition to developing tooling to help or remove man from a radiation environment, present efforts to make that environment a less hostile one in the future are underway. A program to decontaminate the channelhead is underway. The obvious benefit of reducing the radiation source strength, and therefore man-rem exposure, has been indicated. Specialized tooling for local decontamination purposes, development of an advanced computer-controlled manipulator, and comprehensive personnel training programs can all reduce downtime and personnel exposures

  1. Large remote manipulator operating and maintenance experience at IEM cell

    International Nuclear Information System (INIS)

    Hicks, D.F.; McGuinness, P.W.

    1985-01-01

    The Interim Examination and Maintenance (IEM) Cell at the Fast Flux Test Facility (FFTF) has two large Electro-Mechanical Manipulators (EMM's). These manipulators are used for cell operations (processing of reactor core components) as well as general cell maintenance. From our eleven years of operation and maintenance experience with these large EMM's, we have learned many lessons concerning manipulator design. This paper describes the IEM Cell EMM design features and discusses operating and maintenance experience at the IEM Cell

  2. Rugged, remotely maintainable pipetter using microprocessor control

    International Nuclear Information System (INIS)

    Dykes, F.W.; Shurtliff, R.M.; Henscheid, J.P.; Baldwin, J.M.

    1979-01-01

    At the Idaho Chemical Processing Plant (ICPP), the chemical analysis of future nuclear fuel reprocessing solutions will require improved analytical apparatus. Remote pipetters are crucial components in the analysis procedures. Major improvements required for a new pipetter were: greater accuracy for better accounting of fissile material, greater corrosion resistance to handle new fuel reprocessing schemes, and drastic reduction in contact maintenance to reduce personnel radiation exposure to as low as reasonably achievable. The 20-year old Model B pipetter was used as the basis for an improved design. The existing pipetters are positive displacement, servo-controlled units developed from Oak Ridge National Laboratory (ORNL) designs created at the time the ICPP was built. The new pipetter is identified as the Model C

  3. Concept for a vertical maintenance remote handling system for multi module blanket segments in DEMO

    International Nuclear Information System (INIS)

    Coleman, M.; Sykes, N.; Cooper, D.; Iglesias, D.; Bastow, R.; Loving, A.; Harman, J.

    2014-01-01

    Highlights: •A conceptual architectural model for a vertical maintenance DEMO is presented. •Novel concepts for a set of DEMO remote handling equipment are put forward. •Remote maintenance of a multi module segment blanket is found to be feasible. •The criticality of space in the vertical port is highlighted. -- Abstract: The anticipated high neutron flux, and the consequent damage to plasma-facing components in DEMO, results in the need to regularly replace the tritium breeding and radiation shielding blanket. The current European multi module segment (MMS) blanket concept favours a less invasive small port entry maintenance system over large sector transport concepts, because of the reduced impact on other tokamak systems – particularly the magnetic coils. This paper presents a novel conceptual remote maintenance strategy for a Vertical Maintenance Scheme DEMO, incorporating substantiated designs for an in-vessel mover, to detach and attach the blanket segments, and cask-housed vertical maintenance devices to open and close access ports, cut and join service connections, and extract blanket segments from the vessel. In addition, a conceptual architectural model for DEMO was generated to capture functional and spatial interfaces between the remote maintenance equipment and other systems. Areas of further study are identified in order to comprehensively establish the feasibility of the proposed maintenance system

  4. The remote infrared remote control system based on LPC1114

    Science.gov (United States)

    Ren, Yingjie; Guo, Kai; Xu, Xinni; Sun, Dayu; Wang, Li

    2018-05-01

    In view of the shortcomings such as the short control distance of the traditional air conditioner remote controller on the market nowadays and combining with the current smart home new mode "Cloud+ Terminal" mode, a smart home system based on internet is designed and designed to be fully applied to the simple and reliable features of the LPC1114 chip. The controller is added with temperature control module, timing module and other modules. Through the actual test, it achieved remote control air conditioning, with reliability and stability and brought great convenience to people's lives.

  5. Remote Operation and Maintenance Demonstration Facility at the Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Burgess, T.W.

    1986-01-01

    The Remote Operation and Maintenance Demonstration (ROMD) Facility at the Oak Ridge National Laboratory has been developed by the Consolidated Fuel Reprocessing Program to demonstrate remote handling concepts on advanced nuclear fuel reprocessing equipment and for other programs of national interest. The ROMD facility is a large-volume high-bay area that encloses a complete, technologically advanced remote maintenance system and full-scale development reprocessing equipment. The maintenance system consists of a full complement of teleoperated manipulators, manipulator transport systems, and overhead hoists that provide the capability of performing a large variety of remote handling tasks. This system has been used to demonstrate remote manipulation techniques for the US Department of Energy (DOE), the Power Reactor and Nuclear Fuels Development Corporation of Japan, the US Navy, and the National Aeronautics and Space Administration. Extensive tests of manipulative systems and remote maintainability of process equipment have been performed. This paper describes the ROMD facility and key remote maintenance equipment and presents a summary of major experimental activities. 7 refs., 6 figs

  6. Evaluation of remote maintenance schemes by plasma equilibrium analysis in Tokamak DEMO reactor

    International Nuclear Information System (INIS)

    Utoh, Hiroyasu; Tobita, Kenji; Asakura, Nobuyuki; Sakamoto, Yoshiteru

    2014-01-01

    Highlights: • The remote maintenance schemes in DEMO reactor were evaluated by the plasma equilibrium analysis. • Horizontal sector transport maintenance scheme requires the largest total PF coil current. • The difference of total PF coil current for MHD equilibrium in between the large segmented divertor maintenance and the segmentalized divertor maintenance was about 10%. - Abstract: The remote maintenance schemes in a DEMO reactor are categorized by insertion direction, blanket segmentation, and divertor maintenance scheme, and are quantitatively evaluated by analysing the plasma equilibrium. The positions of the poloidal field (PF) coil are limited by the size of the toroidal field (TF) coil and the maintenance port layout of each remote maintenance scheme. Because the PF coils are located near the larger TF coil and far from the plasma surface, the horizontal sector transport maintenance scheme requires the largest part of total PF coil current, 25% larger than that required for separated sector transport using vertical maintenance ports with segmented divertor maintenance (SDM). In the unsegmented divertor maintenance (UDM) scheme, the total magnetic stored energy in the PF coils at plasma equilibrium is about 30% larger than that stored in the SDM scheme, but the time required for removal and installation of all the divertor cassettes in the UDM scheme is roughly a third of that required in the SDM scheme because the number of divertor cassettes in the UDM scheme is a third of that in the SDM scheme. From the viewpoint of simple maintenance operations, the merit of the UDM scheme has more merit than the SDM scheme

  7. Ex-vessel remote maintenance design for the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Macdonald, D.

    1987-01-01

    The use of deuterium-tritium (D-T) fuel for operation of the Compact Ignition Tokamak (CIT) imposes a requirement for remote handling technology for ex-vessel maintenance operations on auxiliary machine components. These operations consist of repairing and replacing components such as diagnostic, radio-frequency (rf) heating, and fueling systems using remotely operated maintenance equipment in the test cell. In addition, ex-vessel maintenance design also includes developing hot cell facilities for equipment decontamination, repair, and solid radioactive waste handling. The test cell maintenance philosophy is markedly influenced by the neutron/gamma shield surrounding the machine that allows personal access into the test cell one day after shutdown. Hence, maintenance operations can be performed hands-on in the test cell with the shield intact and must be remotely performed when the shield is disassembled for machine access. The constricted access to the auxiliary components of the machine affect the design requirements for the maintenance equipment and impose major spatial constraints. Several major areas of the maintenance system design are being addressed in fiscal year 1987. These include conceptual design of the manipulator system, preliminary remote equipment research and development, and definition of the hot cell, decontamination, and equipment repair facility requirements. The manipulator work includes investigating transporters and viewing/lighting subsystems. 2 figs

  8. Remote-automation of nuclear power plant equipment inspection and maintenance

    International Nuclear Information System (INIS)

    Sasaki, Masayoshi; Kawamura, Hironobu; Nakano, Yoshiyuki; Izumi, Shigeru.

    1984-01-01

    The remotely operated automation of the checkup and maintenance of nuclear power generation facilities has largely contributed to the rise of capacity ratio of plants due to the shortening of regular inspection period and to the reduction of radiation exposure dose during working, the labor saving in working and so on. In this paper, the new technologies adopted in an automatic fuel exchanger, a remotely operated automatic CRD exchanger, a new type channel handling machine, pressure-withstanding main steam line plugs and so on for No.2 plant in the Fukushima No.2 Nuclear Power Station, Tokyo Electric Power Co., Inc., are reported. Besides, the state of development of new remotely operated automatic machines for nuclear power use, such as CRD disassembling and cleaning device, volume reduction equipment for spent fuel channel boxes and control rods, multi-functional robots for use under high radiation and so on is described. Also the trend of development of latest robot technology which will be put in practical use in near future is outlined, such as a running manipulator for checkup and inspection, a variable form crawler vehicle and a five-leg movable manipulator. (Kako, I.)

  9. Remote-automated inspection and maintenance of nuclear power plant equipment

    Energy Technology Data Exchange (ETDEWEB)

    Sasaki, Masayoshi; Nakano, Yoshiyuki

    1984-12-01

    Employing remote-control inspection and maintenance equipment in nuclear power plants increases the plant availability by decreasing the annual shutdown time (outage), as well as radiation exposure and man-power. This paper presents an outline of the latest designs for an automatic refueling machine, a control rod drive handling machine, a fuel preparation machine, and a main steam line plug, which were supplied to the Fukushima Dai-Ni No. 2 Plant of the Tokyo Electric Power Co., Inc. (Fukushima 2-2). Also, the up-to-date developments of other new automatic machines, such as a CRD disassembly and cleaning system, spent fuel channel box volume reduction equipment, and robotics for nuclear plant use are presented.

  10. Comparison of all-remote and personnel access maintenance operations for INTOR

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Finn, P.A.; Gohar, M.Y.; Stasko, R.R.

    1985-01-01

    The INTOR reference design was developed to permit limited maintenance operations external to the reactor in a ''hands-on'' mode; all internal operations would be remotely accomplished. The design embodies those requirements for shielding, tritium containment and cleanup, and confinement of contaminated particulate matter to permit personnel access. The cost reflects these requirements, at least first order. The impact of personnel access on the reactor design and its costs are cause to reexamine the maintenance approach on which much of the present configuration is based. The purpose of this study is to compare the benefits and costs associated with personnel access maintenance procedures to those associated with all-remote maintenance procedures and to identify modifications to the baseline design that could enhance maintenance operations

  11. Ex-vessel remote maintenance design for the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Macdonald, D.

    1987-01-01

    The use of deuterium-tritium (D-T) fuel for operation of the Compact Ignition Tokamak (CIT) imposes a requirement for remote handling technology to carry out maintenance operations on auxiliary machine components. These operations consist of removing and repairing components such as diagnostics and radio frequency (rf) heating modules using remotely operated maintenance equipment. The major equipment that is being developed to accomplish maintenance external to the plasma chamber includes the bridge-mounted manipulator system for test cell operations, decontamination (decon) equipment, hot cell equipment, and solid rad-waste handling equipment. Wherever possible, the project will use commercially available equipment. Several areas of the maintenance system design have been addressed in fiscal year (FY) 1987. These included conceptual designs of manipulator systems, the start of a remote equipment research and development (R and D) program, and definition of the hot cell, decon, and equipment repair facility requirements. The manipulator work included investigating transporters and viewing/lighting subsystems. In each case, existing commercial units are being assessed initially, along with viable alternative approaches. R and D work also included demonstrations of remote handling operations on full-size, partial mock-ups of the CIT machine at the Oak Ridge National Laboratory (ORNL) Remote Operations and Maintenance Development Facility

  12. Remote maintenance design activities and research and development accomplishments for the compact ignition tokamak

    International Nuclear Information System (INIS)

    Spampinato, P.T.

    1989-01-01

    The use of deuterium-tritium (D-T) fuel for the Compact Ignition Tokamak (CIT) requires the use of remote handling technology in order to carry out maintenance operations. The remote operations consist of removing and replacing such components as first wall armor protection tiles, radio-frequency (RF) heating modules, and diagnostic modules. The major pieces of equipment being developed for maintenance operations internal to the vacuum vessel include an articulated boom manipulator (ABM), an inspection manipulator, and special tooling. For operations external to the vessel, the equipment includes a bridge-mounted manipulator system, decontamination equipment, hot cell equipment, and solid radioactive waste (rad-waste) handling and packaging equipment. The CIT Project is completing the conceptual design phase; research and development (R and D) activities, which include demonstrations of remote maintenance operations on full-size partial mock-ups are under way. (orig.)

  13. Remote maintenance design activities and research and development accomplishments for the Compact Ignition Tokamak

    International Nuclear Information System (INIS)

    Spampinato, P.T.

    1988-01-01

    The use of deuterium-tritium (D-T) fuel for the Compact Ignition Tokamak (CIT) requires the use of remote handling technology to carry out maintenance operations. The remote operations consist of removing and replacing such components as first wall armor protection tiles, radio-frequency (rf) heating modules, and diagnostic modules. The major pieces of equipment being developed for maintenance activities internal to the vacuum vessel include an articulated boom manipulator (ABM), an inspection manipulator, and special tooling. For activities external to the vessel, the equipment includes a bridge-mounted manipulator system, decontamination equipment, hot cell equipment, and solid radiation-waste (rad-waste) handling and packaging equipment. The CIT Project is completing the conceptual design phase; research and development (R and D) activities, which include demonstrations of remote maintenance operations on full-size partial mock-ups are under way. 5 figs

  14. Assessment of remote maintenance technologies and their potential application in the Federal Waste Management System [FWMS

    International Nuclear Information System (INIS)

    Kring, C.T.; Meacham, S.A.; Peishel, F.L.

    1988-10-01

    The 40 plus years of remote operating experience in nuclear facilities are summarized, with emphasis on the evolution and capabilities of the remote systems. Current commercially available systems and major development activities are described. The advanced servomanipulator is described, which represents new remote technology that has been developed for the Department of Energy-Nuclear Energy and that can significantly improve remote operations by extending the range of admissible remote tasks and increasing remote work efficiency. Also based upon past ORNL experience with remote facilities for reprocessing fuel, the guidelines and concepts that are utilized in the design, fabrication, and remote operation of mechanical process equipment and facilities are outlined. The currently available remote handling systems that can be applied, in various combinations, to large-volume in-cell operations are described, and requirements for waste storage facilities are reviewed. A basic trade-off analysis of these remote systems considering waste plant requirements is given. Justification is given for selecting the overhead crane/servomanipulator-based maintenance concept as the option most desirable for future waste processing plant in-cell maintenance. The Robotics/Remote Handling workshop that was implemented by the Office of Storage and Transportation System during the period that this assessment was being performed, helped focus the remaining time allocated to this effort on the future implementation of an overall program plan using a total systems approach. The concluding recommendation of this assessment is that this Robotics/Remote Handling program plan be developed and implemented as soon as possible. 43 refs., 17 figs., 9 tabs

  15. Assessment of remote maintenance technologies and their potential application in the Federal Waste Management System (FWMS)

    Energy Technology Data Exchange (ETDEWEB)

    Kring, C.T.; Meacham, S.A.; Peishel, F.L.

    1988-10-01

    The 40 plus years of remote operating experience in nuclear facilities are summarized, with emphasis on the evolution and capabilities of the remote systems. Current commercially available systems and major development activities are described. The advanced servomanipulator is described, which represents new remote technology that has been developed for the Department of Energy-Nuclear Energy and that can significantly improve remote operations by extending the range of admissible remote tasks and increasing remote work efficiency. Also based upon past ORNL experience with remote facilities for reprocessing fuel, the guidelines and concepts that are utilized in the design, fabrication, and remote operation of mechanical process equipment and facilities are outlined. The currently available remote handling systems that can be applied, in various combinations, to large-volume in-cell operations are described, and requirements for waste storage facilities are reviewed. A basic trade-off analysis of these remote systems considering waste plant requirements is given. Justification is given for selecting the overhead crane/servomanipulator-based maintenance concept as the option most desirable for future waste processing plant in-cell maintenance. The Robotics/Remote Handling workshop that was implemented by the Office of Storage and Transportation System during the period that this assessment was being performed, helped focus the remaining time allocated to this effort on the future implementation of an overall program plan using a total systems approach. The concluding recommendation of this assessment is that this Robotics/Remote Handling program plan be developed and implemented as soon as possible. 43 refs., 17 figs., 9 tabs.

  16. Remote manipulator experience in target train maintenance at Fermilab

    International Nuclear Information System (INIS)

    Butala, S.W.

    1984-01-01

    When Fermilab was designed in the late 1960's and early 1970's, it was anticipated that Neutrino target train servicing could be costly in terms of personnel radiation exposure. This was based in part on the expectation that target intensities of at least 1E13 protons/pulse would be required to produce several neutrino interactions in a large bubble chamber detector. This was indeed later proven to be the case and historically the Neutrino beamline has been targeted with about one half of the protons available from the Main Ring. It was believed that much of the occupational radiation dose from the Neutrino Area could be spared by utilization of a remote manipulator system, which was eventually installed. It is the purpose of this report to examine the use of the Fermilab remote manipulator system and evaluate its cost effectiveness and success as an ALARA (As Low As Reasonably Achievable) tool. 16 references, 11 figures

  17. Design and operation of remote maintenance systems in JET

    International Nuclear Information System (INIS)

    Raimondi, T.

    1987-01-01

    The JET tokamak is a joint European project aimed at proving the viability of nuclear fusion as a source of energy. A remote handling system is being developed for this large experimental facility. Force feedback servomanipulators and TV cameras are positioned at work locations by large transporters. Positioning and tele-operation are computer-assisted. Special tools are being devised to facilitate difficult tasks

  18. Development of radiation hard components for remote maintenance

    International Nuclear Information System (INIS)

    Oka, Kiyoshi; Obara, Kenjiro; Kakudate, Satoshi; Tominaga, Ryuichiro; Akada, Tamio; Morita, Hirosuke.

    1997-01-01

    In International Thermonuclear Experimental Reactor (ITER), in-vessel remote-handling is inevitably required to assemble and maintain activated in-vessel components due to D-T operation. The components of the in-vessel remote-handling system must have sufficient radiation hardness to allow for operation under an intense gamma-ray radiation of over 30 kGy/h for periods up to more than 1,000 hours. To this end, extensive irradiation tests and quality improvements including the optimization of material composition have been conducted through the ITER R and D program in order to develop radiation hard components which satisfy radiation doses from 10 MGy to 100 MGy at the dose rate of 10 kGy/h. This paper outlines the latest status of the radiation hard component development that has been conducted as the Japan Home Team's contribution to ITER. The remote-handling components tested are categorized into either robotics, viewing systems or common components. The irradiation tests include commercial base products for screening both modified and newly developed products to improve their radiation hardness. (author)

  19. Tokamak Fusion Core Experiment (TFCX) special-purpose remote maintenance systems

    International Nuclear Information System (INIS)

    Masson, L.S.; Welland, H.J.

    1985-01-01

    A key element in the preconceptual design of the Tokamak Fusion Core Experiment (TFCX) was the development of design concepts for special-purpose remote maintenance systems. Included were systems for shield sector replacement, vacuum vessel sector and toroidal field coil replacement, limiter blade replacement, protective tile replacement, and general-purpose maintenance. This paper addresses these systems as they apply to the copper toroidal field (TF) coil version of the TFCX

  20. Maintenance of BWR control rod drive mechanisms

    International Nuclear Information System (INIS)

    Greene, R.H.

    1991-01-01

    Control rod drive mechanism (CRDM) replacement and rebuilding is one of the highest dose, most physically demanding, and complicated maintenance activities routinely accomplished by BWR utilities. A recent industry workshop sponsored by the Oak Ridge National Laboratory, which dealt with the effects of CRDM aging, revealed enhancements in maintenance techniques and tooling which have reduced ALARA, improved worker comfort and productivity, and have provided revised guidelines for CRDM changeout selection. Highlights of this workshop and ongoing research on CRDM aging are presented in this paper

  1. An example of remote maintenance in high radiation fields

    International Nuclear Information System (INIS)

    Pothier, N.E.; Brisbois, L.U.

    Six auxiliary low pressure small (diameter <=5.0 cm) pipes located inside the reactor vault of the Douglas Point Nuclear Generating Station failed due to fretting wear at U-bolt supports: two had worn through the wall and developed leaks, and the others had worn <= 50% through the pipe wall. Human entry into the vault was not possible because of high radiation fields; hence, hands-on repair was not possible. The pipes were repaired and resupported to prevent further fretting wear failures during February-September, 1980. The repair work was performed using custom designed and developed remotely operated tooling and closed-circuit TV viewing. Three main groups were involved in the repair work: Atomic Energy of Canada Engineering Company (AECEC) - the reactor owner; Ontario Hydro - the reactor operator; and, Chalk River Nuclear Laboratories (CRNL). In this report, the contributions made by CRNL are summarized and discussed

  2. Analysis of the ITER ECH Upper Port Launcher remote maintenance using virtual reality

    International Nuclear Information System (INIS)

    Elzendoorn, Ben; de Baar, Marco; Chavan, Rene; Goodman, Timothy; Heemskerk, Cock; Heidinger, Roland; Kleefeldt, Klaus; Koning, Jarich; Sanders, Stephen; Spaeh, Peter; Strauss, Dirk; Verhoeven, Toon; Vreede, Fred de

    2009-01-01

    All ITER sub-systems of remote handling (RH) classes 1 and 2 have to be remotely maintainable. The maintenance strategy for these components has to ensure system availability after failure or scheduled maintenance. This paper shows how virtual reality (VR) simulation can be used as a tool to analyze the maintenance process, to predict the mean time to repair and to ensure the RH compatibility of one ITER sub-system, the Upper Port Launcher (UPL) . Special emphasis is put on the development of RH procedures and the identification of tooling requirements. The possibility to simulate RH logistics and repair actions in an early stage of the design process allows for the identification of those maintenance actions that require dedicated tests in the Launcher Handling Test Facility at Karlsruhe. The VR analysis, together with dedicated mock-up tests will demonstrate the RH compatibility of the UPL plug, provide input to the design of the Port Plug maintenance area in the ITER Hot Cell, and support the development of RH maintenance tooling.

  3. Vehicle Remote Health Monitoring and Prognostic Maintenance System

    Directory of Open Access Journals (Sweden)

    Uferah Shafi

    2018-01-01

    Full Text Available In many industries inclusive of automotive vehicle industry, predictive maintenance has become more important. It is hard to diagnose failure in advance in the vehicle industry because of the limited availability of sensors and some of the designing exertions. However with the great development in automotive industry, it looks feasible today to analyze sensor’s data along with machine learning techniques for failure prediction. In this article, an approach is presented for fault prediction of four main subsystems of vehicle, fuel system, ignition system, exhaust system, and cooling system. Sensor is collected when vehicle is on the move, both in faulty condition (when any failure in specific system has occurred and in normal condition. The data is transmitted to the server which analyzes the data. Interesting patterns are learned using four classifiers, Decision Tree, Support Vector Machine, K Nearest Neighbor, and Random Forest. These patterns are later used to detect future failures in other vehicles which show the similar behavior. The approach is produced with the end goal of expanding vehicle up-time and was demonstrated on 70 vehicles of Toyota Corolla type. Accuracy comparison of all classifiers is performed on the basis of Receiver Operating Characteristics (ROC curves.

  4. Remote system for monitoring and control of controlled area of nuclear installation

    International Nuclear Information System (INIS)

    Assuncao, Daniel Gomes de; Minhoni, Danilo Carlos Rossetto; Farias, Marcos Sant'anna de; Santos, Isaac J.A. Luquetti dos

    2011-01-01

    The maintenance activities in controlled areas of nuclear facilities require adequate planning and control so that these activities do not cause to the worker an undue exposure to radioactivity. For maximum safety of workers from these places, there are standards that determine the maximum radiation dose that a worker can receive. From this context, the objective of this research is to develop a remote system that shows remotely the maintenance tasks being carried out in this work environment; monitors information provided by radiation monitoring devices installed at workplace; tracks the time to carry out scheduled maintenance, reporting alarm if this time is exceeded or not. The system has video camera, radiation monitoring device, interface card to transmit data via ethernet and graphical user interface, developed using the LABVIEW application. The principal objective is to improve the safety and to preserve the worker's health. (author)

  5. Remote system for monitoring and control of controlled area of nuclear installation

    Energy Technology Data Exchange (ETDEWEB)

    Assuncao, Daniel Gomes de; Minhoni, Danilo Carlos Rossetto [Departamento de Ciencias da Administracao e Tecnologia. Centro Universitario de Araraquara (UNIARA) Araraquara, SP (Brazil); Farias, Marcos Sant' anna de; Santos, Isaac J.A. Luquetti dos, E-mail: luquetti@ien.gov.br [Instituto Engenharia Nuclear (IEN/CNEN-RJ), Rio Janeiro, RJ (Brazil). Divisao de Instrumentacao e Confiabilidade Humana

    2011-07-01

    The maintenance activities in controlled areas of nuclear facilities require adequate planning and control so that these activities do not cause to the worker an undue exposure to radioactivity. For maximum safety of workers from these places, there are standards that determine the maximum radiation dose that a worker can receive. From this context, the objective of this research is to develop a remote system that shows remotely the maintenance tasks being carried out in this work environment; monitors information provided by radiation monitoring devices installed at workplace; tracks the time to carry out scheduled maintenance, reporting alarm if this time is exceeded or not. The system has video camera, radiation monitoring device, interface card to transmit data via ethernet and graphical user interface, developed using the LABVIEW application. The principal objective is to improve the safety and to preserve the worker's health. (author)

  6. Remote tool development at the interim examination and maintenance (IEM) cell

    International Nuclear Information System (INIS)

    Kalk, J.J.

    1986-01-01

    In the interim examination and maintenance (IEM) cell at the Fast Flux Test Facility, radioactive fuel assemblies from the reactor are disassembled remotely for examination. The cell has an argon atmosphere and all of the equipment in the IEM cell must be either removed or worked on in place remotely for maintenance and repair. Equipment is mounted either on the cell walls or on other equipment with remote fasteners. These fasteners are required to be tightened to torque values ranging from 4 to 102 N m, and will be loosened and torqued several times during the lifetime of the cell. The purpose of this paper is to discuss the development philosophy for tools, specifically those relating to remote fasteners used in IEM cell work. The IEM cell fastener tightening system is now a series of wrenches and attachments instead of the one tool originally proposed. This set of tools allows use of relatively inexpensive commercially available equipment to tighten remote fasteners, while giving the cell operators the flexibility to use the tool they fell is best for the job. If the first choice is not available, use of an optional tool is possible with no loss of torque accuracy

  7. FFTF/IEM [Fast Flux Test Facility/Interim Examination and Maintenance] cell fuel pin weighing system: Remote maintenance design considerations

    International Nuclear Information System (INIS)

    Gibbons, P.W.

    1986-06-01

    A Fuel Pin Weighing Machine has been developed for use in the Fast Flux Test Facility (FFTF) Interim Examination and Maintenance (IEM) Cell to assist in identifying an individual breached fuel pin from its fuel assembly pin bundle. Optimum configuration for remote maintenance was a major consideration in the design of each element of the Pin Weighing System

  8. Maintenance and control of apparatus for radiotherapy

    International Nuclear Information System (INIS)

    Wakui, Sho

    1979-01-01

    In order to perform the safe operation of radiotherapy apparatuses and to secure the accuracy in positioning patients and in setting up radiation beam, proper checking-up and maintenance schedule is necessary. Such schedule is described briefly and also the mechanical or electrical equipments designed for securing the safety and accuracy or eliminating in adequate operation are explained, especially on treatment tables and accessories, such as wedge filters, irradiation field indicators and pointers, and the devices for observing patients. The structures and the practical control of the following equipments are explained; standard treatment table, treatment table with a lifting column by oil pressure, mobile positioning control pedestal, positioning control pendaut, mechanical fuse cutter for the safeguard of table height movement, safety interlock to protect table from physical contact with radiation head in rotation and safeguard for arms of a patient in longitudinal movement of treatment table. For the maintenance and control of wedge filters, the kind of filter angle in use, the direction of filter in use and whether filter is used or not are exactly confirmed by adequate display. The direction mechanism of radiation field and the pointers are required to be strict for exact focusing of radiation. Various control apparatuses and monitoring apparatuses are described. (Kobatake, H.)

  9. Remote system of data acquisition and equipment maintenance with communication door Series; Sistema remoto de aquisicao de dados e manutencao de equipamentos com portas de comunicacao Serie

    Energy Technology Data Exchange (ETDEWEB)

    Marques, Ailton; Cabrera, Fernando [TRANSIERRA S.A., Santa Cruz (Bolivia)

    2005-07-01

    The present work has for objective to present the Remote System of Data Acquisition and Equipment Maintenance with Communication door Series - GASYRG. The solution is based on a converter of protocol (Serial -Ethernet) and a panel that the function of commutator (switch) managed by control system assumes (SCADA). (author)

  10. Development and performance tests of the bridge-transported servo manipulator system for remote maintenance jobs in a hot cell

    International Nuclear Information System (INIS)

    Jin, Jae Hyun; Park, Byung Suk; Ko, Byung Seung; Yoon, Ji Sup; Jung, Ki Jung

    2005-01-01

    In this paper, a prototype of the Bridge-Transported Servo Manipulator (BTSM) system introduced, which has been developed to do operation and maintenance jobs remotely in a hot cell. The system consists of a telescopic transporter, a slave arm, a master arm, and a control system. Several tests such as a positional tracking, a weight handling, reliability, and operability have been performed and test results are presented. Based on the test results, an upgraded system which will be used during demonstrations of the advanced spent fuel conditioning process (ACP) has been designed.

  11. Underground ventilation remote monitoring and control system

    International Nuclear Information System (INIS)

    Strever, M.T.; Wallace, K.G. Jr.; McDaniel, K.H.

    1995-01-01

    This paper presents the design and installation of an underground ventilation remote monitoring and control system at the Waste Isolation Pilot Plant. This facility is designed to demonstrate safe underground disposal of U.S. defense generated transuranic nuclear waste. To improve the operability of the ventilation system, an underground remote monitoring and control system was designed and installed. The system consists of 15 air velocity sensors and 8 differential pressure sensors strategically located throughout the underground facility providing real-time data regarding the status of the ventilation system. In addition, a control system was installed on the main underground air regulators. The regulator control system gives indication of the regulator position and can be controlled either locally or remotely. The sensor output is displayed locally and at a central surface location through the site-wide Central Monitoring System (CMS). The CMS operator can review all sensor data and can remotely operate the main underground regulators. Furthermore, the Virtual Address Extension (VAX) network allows the ventilation engineer to retrieve real-time ventilation data on his personal computer located in his workstation. This paper describes the types of sensors selected, the installation of the instrumentation, and the initial operation of the remote monitoring system

  12. Remote Experiments in Control Engineering Education Laboratory

    Directory of Open Access Journals (Sweden)

    Milica B Naumović

    2008-05-01

    Full Text Available This paper presents Automatic Control Engineering Laboratory (ACEL - WebLab, an under-developed, internet-based remote laboratory for control engineering education at the Faculty of Electronic Engineering in Niš. Up to now, the remote laboratory integrates two physical systems (velocity servo system and magnetic levitation system and enables some levels of measurement and control. To perform experiments in ACEL-WebLab, the "LabVIEW Run Time Engine"and a standard web browser are needed.

  13. Optimized hardware design for the divertor remote handling control system

    Energy Technology Data Exchange (ETDEWEB)

    Saarinen, Hannu [Tampere University of Technology, Korkeakoulunkatu 6, 33720 Tampere (Finland)], E-mail: hannu.saarinen@tut.fi; Tiitinen, Juha; Aha, Liisa; Muhammad, Ali; Mattila, Jouni; Siuko, Mikko; Vilenius, Matti [Tampere University of Technology, Korkeakoulunkatu 6, 33720 Tampere (Finland); Jaervenpaeae, Jorma [VTT Systems Engineering, Tekniikankatu 1, 33720 Tampere (Finland); Irving, Mike; Damiani, Carlo; Semeraro, Luigi [Fusion for Energy, Josep Pla 2, Torres Diagonal Litoral B3, 08019 Barcelona (Spain)

    2009-06-15

    A key ITER maintenance activity is the exchange of the divertor cassettes. One of the major focuses of the EU Remote Handling (RH) programme has been the study and development of the remote handling equipment necessary for divertor exchange. The current major step in this programme involves the construction of a full scale physical test facility, namely DTP2 (Divertor Test Platform 2), in which to demonstrate and refine the RH equipment designs for ITER using prototypes. The major objective of the DTP2 project is the proof of concept studies of various RH devices, but is also important to define principles for standardizing control hardware and methods around the ITER maintenance equipment. This paper focuses on describing the control system hardware design optimization that is taking place at DTP2. Here there will be two RH movers, namely the Cassette Multifuctional Mover (CMM), Cassette Toroidal Mover (CTM) and assisting water hydraulic force feedback manipulators (WHMAN) located aboard each Mover. The idea here is to use common Real Time Operating Systems (RTOS), measurement and control IO-cards etc. for all maintenance devices and to standardize sensors and control components as much as possible. In this paper, new optimized DTP2 control system hardware design and some initial experimentation with the new DTP2 RH control system platform are presented. The proposed new approach is able to fulfil the functional requirements for both Mover and Manipulator control systems. Since the new control system hardware design has reduced architecture there are a number of benefits compared to the old approach. The simplified hardware solution enables the use of a single software development environment and a single communication protocol. This will result in easier maintainability of the software and hardware, less dependence on trained personnel, easier training of operators and hence reduced the development costs of ITER RH.

  14. Planning and control of maintenance systems modelling and analysis

    CERN Document Server

    Duffuaa, Salih O

    2015-01-01

    Analyzing maintenance as an integrated system with objectives, strategies and processes that need to be planned, designed, engineered, and controlled using statistical and optimization techniques, the theme of this book is the strategic holistic system approach for maintenance. This approach enables maintenance decision makers to view maintenance as a provider of a competitive edge not a necessary evil. Encompassing maintenance systems; maintenance strategic and capacity planning, planned and preventive maintenance, work measurements and standards, material (spares) control, maintenance operations and control, planning and scheduling, maintenance quality, training, and others, this book gives readers an understanding of the relevant methodology and how to apply it to real-world problems in industry. Each chapter includes a number exercises and is suitable as a textbook or a reference for a professionals and practitioners whilst being of interest to industrial engineering, mechanical engineering, electrical en...

  15. Remote maintenance of a combined regeneration-isolation valve for the ITER Torus vacuum pumping system

    International Nuclear Information System (INIS)

    Stringer, J.; Blevins, J.

    1992-01-01

    A large diameter valve suitable for high vacuum operation is under study for ITER Torus evacuation. The valves must comply with specifications for leak-tightness, radiation resistance, dust tolerance, overpressure, and thermal gradients. Remote maintenance of the seal and valve moving parts without disturbance to the rest of the valve system is a requirement. This paper describes tow methods of seal exchange by remote means. In the first method, a flask is proposed for the valve moving parts exchange in inert gas, when the machine is shut down. In the second method a novel concept is described for seal exchange while under vacuum, without having to bring the machine up to atmosphere. The advantages of this method are that scheduled remote handling (RH) operations and outages for seal replacement are not required. Also, the need for a flask is avoided

  16. Ex-vessel remote maintenance development plans for the Burning Plasma Experiment

    International Nuclear Information System (INIS)

    Burgess, T.W.; Davis, F.C.

    1991-01-01

    Remote maintenance (RM) is fundamental to the basic design requirements of the Burning Plasma Experiment (BPX), and an extensive RM development and demonstration program is planned to meet these requirements. The program first draws from the experience base that exists in the fission community and Europe's Joint European Torus (JET) Project. Successful solutions are applied where possible and, in many cases, improved in order to achieve the performance demanded by a multiyear program that must be capable of efficiently executing RM procedures. Early, concurrent efforts in the design and fabrication of prototype remote handling (RH) equipment, remote tooling, and maintainable machine components will precede an extensive use of mock-up equipment in order to test, develop, and demonstrate the technology. 7 refs,. 5 figs

  17. Telemanipulation - a special activity in remotely controlled operations

    International Nuclear Information System (INIS)

    Rose, K.W.; Andre, Y.

    1992-01-01

    Work to be done in areas hostile to humans needs special and careful preparation. If short-term entry is possible, groups of men can be trained to do the necessary work. If not, special devices have to be designed, built, and tested on mockups before the real work can be executed. Based on experience gained from maintenance in car production and test programs for a reprocessing facility, it was decided to train a special group of men to do remotely controlled work in hostile areas without endangering them and to use their personal experience as the basis for future work. This is the old-fashioned way of all professions. Some needs to be able to do that remotely controlled work with normally existing operational means and combinations of them like cranes, mechanical and electromechanical master slave manipulators (MMSMs and EMSMs), saws, files, hammer, tig-welding equipment, etc., in air as well as underwater. This paper discusses use of a remote operator manipulator (ROM), remote operator welder (ROW), a test of underwater work, and the repair of two activated jets pumps of a boiling water reactor BWR with a fueling machine, reactor crane, EMSM, and conventional tools

  18. Remote controlled mover for disposal canister transfer

    Energy Technology Data Exchange (ETDEWEB)

    Suikki, M. [Optimik Oy, Turku (Finland)

    2013-10-15

    This working report is an update for an earlier automatic guided vehicle design (Pietikaeinen 2003). The short horizontal transfers of disposal canisters manufactured in the encapsulation process are conducted with remote controlled movers both in the encapsulation plant and in the underground areas at the canister loading station of the disposal facility. The canister mover is a remote controlled transfer vehicle mobile on wheels. The handling of canisters is conducted with the assistance of transport platforms (pallets). The very small automatic guided vehicle of the earlier design was replaced with a commercial type mover. The most important reasons for this being the increased loadbearing requirement and the simpler, proven technology of the vehicle. The larger size of the vehicle induced changes to the plant layouts and in the principles for dealing with fault conditions. The selected mover is a vehicle, which is normally operated from alongside. In this application, the vehicle steering technology must be remote controlled. In addition, the area utilization must be as efficient as possible. This is why the vehicle was downsized in its outer dimensions and supplemented with certain auxiliary equipment and structures. This enables both remote controlled operation and improves the vehicle in terms of its failure tolerance. Operation of the vehicle was subjected to a risk analysis (PFMEA) and to a separate additional calculation conserning possible canister toppling risks. The total cost estimate, without value added tax for manufacturing the system amounts to 730 000 euros. (orig.)

  19. Coded ultrasonic remote control without batteries

    International Nuclear Information System (INIS)

    Gerhardy, C; Burlage, K; Schomburg, W K

    2009-01-01

    A concept for battery-less remote controls has been developed based on mechanically actuated beams and micro whistles generating ultrasound signals. These signals need to be frequency or time coded to increase the number of signals which can be distinguished from each other and environmental ultrasound. Several designs for generating coded ultrasonic signals have been investigated

  20. Remote controlled mover for disposal canister transfer

    International Nuclear Information System (INIS)

    Suikki, M.

    2013-10-01

    This working report is an update for an earlier automatic guided vehicle design (Pietikaeinen 2003). The short horizontal transfers of disposal canisters manufactured in the encapsulation process are conducted with remote controlled movers both in the encapsulation plant and in the underground areas at the canister loading station of the disposal facility. The canister mover is a remote controlled transfer vehicle mobile on wheels. The handling of canisters is conducted with the assistance of transport platforms (pallets). The very small automatic guided vehicle of the earlier design was replaced with a commercial type mover. The most important reasons for this being the increased loadbearing requirement and the simpler, proven technology of the vehicle. The larger size of the vehicle induced changes to the plant layouts and in the principles for dealing with fault conditions. The selected mover is a vehicle, which is normally operated from alongside. In this application, the vehicle steering technology must be remote controlled. In addition, the area utilization must be as efficient as possible. This is why the vehicle was downsized in its outer dimensions and supplemented with certain auxiliary equipment and structures. This enables both remote controlled operation and improves the vehicle in terms of its failure tolerance. Operation of the vehicle was subjected to a risk analysis (PFMEA) and to a separate additional calculation conserning possible canister toppling risks. The total cost estimate, without value added tax for manufacturing the system amounts to 730 000 euros. (orig.)

  1. Design and implementation of wormlike creeping mobile robot for EAST remote maintenance system

    Energy Technology Data Exchange (ETDEWEB)

    Zhang, Qiang, E-mail: zhangqiang@iim.ac.cn [Institute of Intelligent Machines, Chinese Academy of Sciences, Hefei, Anhui 230031 (China); Department of Automation, University of Science and Technology of China, Hefei, Anhui 230026 (China); Zhou, Ling [Institute of Intelligent Machines, Chinese Academy of Sciences, Hefei, Anhui 230031 (China); Wang, Zengfu, E-mail: zfwang@ustc.edu.cn [Institute of Intelligent Machines, Chinese Academy of Sciences, Hefei, Anhui 230031 (China); Department of Automation, University of Science and Technology of China, Hefei, Anhui 230026 (China)

    2017-05-15

    Highlights: • Wormlike creeping robot walking on the V-shaped circular slot in EAST fusion vessel. • Mobile platform to carry equipments or assist manipulators for maintenance tasks. • Chain structure design with n(n ≥ 2) creeping units each of which has three segments. • Creeping gait planning to construct a multi-axis coordinating control scheme. • Evaluation and verification of basic motion performance and mechanical properties. - Abstract: Maintenance for nuclear fusion vessel is crucial, yet it faces great difficulty due to the complex internal physical and geometric conditions. Since the limitation on inherent strength, load, size, etc, a manipulator robot can only complete very limited tasks. Robotic arm systems for remote operation such as JET and MPD can carry certain tools to complete a variety of operating tasks, but it is difficult to achieve the system which is very complex. Therefore, if the inherent idea of using a single robot to complete the specified functions can change, it is possible to make the problems simpler and easier to solve by adding auxiliary robots working together with the robotic arm systems to complete the assigned tasks. Under the above background, based on the deeply analyzing and refining the functional requirements of the vessel operation robot, proceeding from the perspective of ability to move and carry a certain operating device, this paper presents a wormlike creeping mobile robot walking on the V-shaped circular slot inside a nuclear fusion vessel such as EAST (Experimental Advanced Superconducting Tokamak). We have designed and implemented the principle prototype of the robot which has chain structure with n (n ≥2) creeping units. Each creeping unit is of three-part structure, which consists of fore segment, mid segment and back segment connected by bidirectional universal joint. The fore and back segments stretch the paws to contact the surface of V-shaped slot, while the mid segment realizes the overall

  2. Design and implementation of wormlike creeping mobile robot for EAST remote maintenance system

    International Nuclear Information System (INIS)

    Zhang, Qiang; Zhou, Ling; Wang, Zengfu

    2017-01-01

    Highlights: • Wormlike creeping robot walking on the V-shaped circular slot in EAST fusion vessel. • Mobile platform to carry equipments or assist manipulators for maintenance tasks. • Chain structure design with n(n ≥ 2) creeping units each of which has three segments. • Creeping gait planning to construct a multi-axis coordinating control scheme. • Evaluation and verification of basic motion performance and mechanical properties. - Abstract: Maintenance for nuclear fusion vessel is crucial, yet it faces great difficulty due to the complex internal physical and geometric conditions. Since the limitation on inherent strength, load, size, etc, a manipulator robot can only complete very limited tasks. Robotic arm systems for remote operation such as JET and MPD can carry certain tools to complete a variety of operating tasks, but it is difficult to achieve the system which is very complex. Therefore, if the inherent idea of using a single robot to complete the specified functions can change, it is possible to make the problems simpler and easier to solve by adding auxiliary robots working together with the robotic arm systems to complete the assigned tasks. Under the above background, based on the deeply analyzing and refining the functional requirements of the vessel operation robot, proceeding from the perspective of ability to move and carry a certain operating device, this paper presents a wormlike creeping mobile robot walking on the V-shaped circular slot inside a nuclear fusion vessel such as EAST (Experimental Advanced Superconducting Tokamak). We have designed and implemented the principle prototype of the robot which has chain structure with n (n ≥2) creeping units. Each creeping unit is of three-part structure, which consists of fore segment, mid segment and back segment connected by bidirectional universal joint. The fore and back segments stretch the paws to contact the surface of V-shaped slot, while the mid segment realizes the overall

  3. The ITER EC H&CD Upper Launcher: Analysis of vertical Remote Handling applied to the BSM maintenance

    NARCIS (Netherlands)

    Grossetti, G.; Aiello, G.; Heemskerk, C.; Elzendoorn, B.; Geßner, R.; Koning, J.; Meier, A.; Ronden, D.; Späh, P.; Scherer, T.; Schreck, S.; Strauß, D.; Vaccaro, A.

    2013-01-01

    This paper deals with Remote Handling activities foreseen on the Blanket Shield Module, the plasma facing component of the ITER Electron Cyclotron Heating and Current Drive Upper Launcher. The maintenance configuration considered here is the Vertical Remote Handling, meaning gravity acting along the

  4. Quantum processing by remote quantum control

    Science.gov (United States)

    Qiang, Xiaogang; Zhou, Xiaoqi; Aungskunsiri, Kanin; Cable, Hugo; O'Brien, Jeremy L.

    2017-12-01

    Client-server models enable computations to be hosted remotely on quantum servers. We present a novel protocol for realizing this task, with practical advantages when using technology feasible in the near term. Client tasks are realized as linear combinations of operations implemented by the server, where the linear coefficients are hidden from the server. We report on an experimental demonstration of our protocol using linear optics, which realizes linear combination of two single-qubit operations by a remote single-qubit control. In addition, we explain when our protocol can remain efficient for larger computations, as well as some ways in which privacy can be maintained using our protocol.

  5. Computer control for remote wind turbine operation

    Energy Technology Data Exchange (ETDEWEB)

    Manwell, J.F.; Rogers, A.L.; Abdulwahid, U.; Driscoll, J. [Univ. of Massachusetts, Amherst, MA (United States)

    1997-12-31

    Light weight wind turbines located in harsh, remote sites require particularly capable controllers. Based on extensive operation of the original ESI-807 moved to such a location, a much more sophisticated controller than the original one has been developed. This paper describes the design, development and testing of that new controller. The complete control and monitoring system consists of sensor and control inputs, the control computer, control outputs, and additional equipment. The control code was written in Microsoft Visual Basic on a PC type computer. The control code monitors potential faults and allows the turbine to operate in one of eight states: off, start, run, freewheel, low wind shut down, normal wind shutdown, emergency shutdown, and blade parking. The controller also incorporates two {open_quotes}virtual wind turbines,{close_quotes} including a dynamic model of the machine, for code testing. The controller can handle numerous situations for which the original controller was unequipped.

  6. Association of remote dexterity and remote lifting for maintenance in fuel reprocessing industry

    International Nuclear Information System (INIS)

    Streiff, G.; Auchapt, P.; Vertut, J.

    1984-01-01

    The MA23M is an articulated bilateral servomanipulator with theoretically unlimited distance between master and slave stations. The last developments being carried on enable its good utilization in the large cells that will exist in the next reprocessing plants. Recent developments concerning computer aided operations like automatic TV tracking of the effector and manipulative assistance of MA23 and transporter enable realistic application in the large cells of the future reprocessing plants. In another hand manipulator containment, transfer and maintenance, in a glove box have been demonstrated. Concerning the in-cell process equipment to be maintained, extensive testing has shown that the association with a hoist is an excellent trade off in power and dexterity enabling solution of practically all expected or unexpected operations. According to the in-cell machinery and to the difficulty of the operation, one or two dextrous arms can be associated with one hoist. Dismantling of machines or dismantling of the whole facility will be possible by developing special tooling handled by the dextrous manipulator or, if too heavy, oriented by the manipulator but suspended to the hoist

  7. Remote radio control of insect flight

    Directory of Open Access Journals (Sweden)

    Hirotaka Sato

    2009-10-01

    Full Text Available We demonstrated the remote control of insects in free flight via an implantable radio-equipped miniature neural stimulating system. The pronotum mounted system consisted of neural stimulators, muscular stimulators, a radio transceiver-equipped microcontroller and a microbattery. Flight initiation, cessation and elevation control were accomplished through neural stimulus of the brain which elicited, suppressed or modulated wing oscillation. Turns were triggered through the direct muscular stimulus of either of the basalar muscles. We characterized the response times, success rates, and free-flight trajectories elicited by our neural control systems in remotely-controlled beetles. We believe this type of technology will open the door to in-flight perturbation and recording of insect flight responses.

  8. Remote radio control of insect flight.

    Science.gov (United States)

    Sato, Hirotaka; Berry, Christopher W; Peeri, Yoav; Baghoomian, Emen; Casey, Brendan E; Lavella, Gabriel; Vandenbrooks, John M; Harrison, Jon F; Maharbiz, Michel M

    2009-01-01

    We demonstrated the remote control of insects in free flight via an implantable radio-equipped miniature neural stimulating system. The pronotum mounted system consisted of neural stimulators, muscular stimulators, a radio transceiver-equipped microcontroller and a microbattery. Flight initiation, cessation and elevation control were accomplished through neural stimulus of the brain which elicited, suppressed or modulated wing oscillation. Turns were triggered through the direct muscular stimulus of either of the basalar muscles. We characterized the response times, success rates, and free-flight trajectories elicited by our neural control systems in remotely controlled beetles. We believe this type of technology will open the door to in-flight perturbation and recording of insect flight responses.

  9. Remote control of nanoscale devices

    Science.gov (United States)

    Högberg, Björn

    2018-01-01

    Processes that occur at the nanometer scale have a tremendous impact on our daily lives. Sophisticated evolved nanomachines operate in each of our cells; we also, as a society, increasingly rely on synthetic nanodevices for communication and computation. Scientists are still only beginning to master this scale, but, recently, DNA nanotechnology (1)—in particular, DNA origami (2)—has emerged as a powerful tool to build structures precise enough to help us do so. On page 296 of this issue, Kopperger et al. (3) show that they are now also able to control the motion of a DNA origami device from the outside by applying electric fields.

  10. System for remote control of underground device

    International Nuclear Information System (INIS)

    Brumleve, T.D.; Hicks, M.G.; Jones, M.O.

    1975-01-01

    A system is described for remote control of an underground device, particularly a nuclear explosive. The system includes means at the surface of the ground for transmitting a seismic signal sequence through the earth having controlled and predetermined signal characteristics for initiating a selected action in the device. Additional apparatus, located with or adjacent to the underground device, produces electrical signals in response to the seismic signals received and compares these electrical signals with the predetermined signal characteristics

  11. System for remote control of underground device

    Science.gov (United States)

    Brumleve, T.D.; Hicks, M.G.; Jones, M.O.

    1975-10-21

    A system is described for remote control of an underground device, particularly a nuclear explosive. The system includes means at the surface of the ground for transmitting a seismic signal sequence through the earth having controlled and predetermined signal characteristics for initiating a selected action in the device. Additional apparatus, located with or adjacent to the underground device, produces electrical signals in response to the seismic signals received and compares these electrical signals with the predetermined signal characteristics.

  12. Regulatory control of maintenance activities in Argentine nuclear power plants

    International Nuclear Information System (INIS)

    Calvo, J.C.; Caruso, G.

    2000-01-01

    The main maintenance objective is to assure that the safety features of structures, components and systems of nuclear power plants are kept as designed. Therefore, there is a direct relationship between safety and maintenance. Owing to the above mentioned, maintenance activities are considered a relevant regulatory issue for the Argentine Nuclear Regulatory Authority (ARN). This paper describes the regulatory control to maintenance activities of Argentine nuclear power plants. It also addresses essential elements for maintenance control, routine inspections, special inspections during planned outages, audits and license conditions and requirements. (author)

  13. Remote control of a fusion facility

    Energy Technology Data Exchange (ETDEWEB)

    Schissel, D.P. [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States)], E-mail: schissel@fusion.gat.com; Abla, G.; Humphreys, D.A.; Penaflor, B.G.; Sammuli, B.S.; Walker, M.L. [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States)

    2009-06-15

    Magnetic fusion experiments keep growing in size and complexity resulting in a concurrent growth in collaboration between experimental sites and laboratories worldwide. This scientific collaboration activity is strong at existing experimental sites, is a major element of machines just coming on line, and is also a thrust of experiments that will come on line in the next decade. Computer science research into enhancing the ability to scientifically participate in a fusion experiment remotely has been growing in size in an attempt to better address the needs of fusion scientists worldwide. The natural progression of this research is to examine how to move from remote scientific participation to remote hardware control. This paper examines the challenges associated with remote experimental device control and proposes a solution based on a semantic approach that defines a Gatekeeper software system that will be the only channel of interaction for incoming requests to the experimental site. The role of the Gatekeeper is to validate the identification and access privilege of the requestor and to ensure the validity of the proposed request. The Gatekeeper will be a modular system, transparent to end-users, and allow a high volume of activity.

  14. Remote control of a fusion facility

    International Nuclear Information System (INIS)

    Schissel, D.P.; Abla, G.; Humphreys, D.A.; Penaflor, B.G.; Sammuli, B.S.; Walker, M.L.

    2009-01-01

    Magnetic fusion experiments keep growing in size and complexity resulting in a concurrent growth in collaboration between experimental sites and laboratories worldwide. This scientific collaboration activity is strong at existing experimental sites, is a major element of machines just coming on line, and is also a thrust of experiments that will come on line in the next decade. Computer science research into enhancing the ability to scientifically participate in a fusion experiment remotely has been growing in size in an attempt to better address the needs of fusion scientists worldwide. The natural progression of this research is to examine how to move from remote scientific participation to remote hardware control. This paper examines the challenges associated with remote experimental device control and proposes a solution based on a semantic approach that defines a Gatekeeper software system that will be the only channel of interaction for incoming requests to the experimental site. The role of the Gatekeeper is to validate the identification and access privilege of the requestor and to ensure the validity of the proposed request. The Gatekeeper will be a modular system, transparent to end-users, and allow a high volume of activity.

  15. An investigation of secure remote instrument control

    International Nuclear Information System (INIS)

    Schissel, D.P.; Abla, G.; Fredian, T.; Greenwald, M.; Penaflor, B.G.; Stillerman, J.; Walker, M.L.; Ciarlette, D.J.

    2010-01-01

    This paper examines the computer science issues associated with secure remote instrumentation control for magnetic fusion experiments. Computer science research into enhancing the ability to scientifically participate in a fusion experiment remotely has been growing in size in an attempt to better address the needs of fusion scientists worldwide. The natural progression of this research is to examine how to move from remote scientific participation to remote hardware control. The vision is to define a gatekeeper software system that will be the only channel of interaction for incoming requests to the secured area of the experimental site. The role of the gatekeeper is to validate the identification and access privilege of the requestor and to insure the general validity of the proposed request. The vision for the gatekeeper is that it be a modular system that is simple in design and defined in a way that makes its implementation and operation transparent and obvious. The architecture of the module interface is flexible enough that it can easily allow the future addition of new modules. At the same time, it should be transparent to end-users and allow a high volume of activity so as to not provide a work bottleneck. The results of the gatekeeper design and initial implementation are presented as well as a discussion on the implication of this research on the operation of fusion experimental machines such as ITER.

  16. An investigation of secure remote instrument control

    Energy Technology Data Exchange (ETDEWEB)

    Schissel, D.P., E-mail: schissel@fusion.gat.co [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States); Abla, G. [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States); Fredian, T.; Greenwald, M. [Massachusetts Institute of Technology, Cambridge, MA (United States); Penaflor, B.G. [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States); Stillerman, J. [Massachusetts Institute of Technology, Cambridge, MA (United States); Walker, M.L. [General Atomics, P.O. Box 85608, San Diego, CA 92186-5608 (United States); Ciarlette, D.J. [US ITER Project Office, Oak Ridge National Laboratory, Oak Ridge, TN (United States)

    2010-07-15

    This paper examines the computer science issues associated with secure remote instrumentation control for magnetic fusion experiments. Computer science research into enhancing the ability to scientifically participate in a fusion experiment remotely has been growing in size in an attempt to better address the needs of fusion scientists worldwide. The natural progression of this research is to examine how to move from remote scientific participation to remote hardware control. The vision is to define a gatekeeper software system that will be the only channel of interaction for incoming requests to the secured area of the experimental site. The role of the gatekeeper is to validate the identification and access privilege of the requestor and to insure the general validity of the proposed request. The vision for the gatekeeper is that it be a modular system that is simple in design and defined in a way that makes its implementation and operation transparent and obvious. The architecture of the module interface is flexible enough that it can easily allow the future addition of new modules. At the same time, it should be transparent to end-users and allow a high volume of activity so as to not provide a work bottleneck. The results of the gatekeeper design and initial implementation are presented as well as a discussion on the implication of this research on the operation of fusion experimental machines such as ITER.

  17. Remotex: a new concept for efficient remote operation and maintenance in nuclear fuel reprocessing

    International Nuclear Information System (INIS)

    Feldman, M.J.; White, J.R.

    1980-01-01

    Remotex is a concept of remote operation and maintenance that utilizes advanced manipulator design to improve plant operating efficiency, reduce personnel exposure, and improve safeguards and diversion resistance. It is a concept developed over the past two years in the conceptual design of the Hot Experimental Facility (HEF), a mechanically intense pilot plant facility designed to demonstrate reprocessng technology for early US breeder demonstration reactors. The Remotex concept is directly applicable to all segments of nuclear and nonnuclear industries where work tasks or conditions exist that are hazardous to the health of man

  18. Development of laser cutting/welding system for remote maintenance of ITER manifold

    Energy Technology Data Exchange (ETDEWEB)

    Yamaoka, Hiroto; Tsuchiya, Kazuyuki; Awano, Toshihiko [Ishikawajima-Harima Heavy Industries Co. Ltd., Tokyo (Japan); Oka, Kiyoshi [Japan Atomic Energy Research Inst., Naka, Ibaraki (Japan). Naka Fusion Research Establishment

    2002-09-01

    A remote pipe cutting/welding system using a YAG laser was designed and fabricated for the maintenance of the main structural parts of ITER (International Thermonuclear Experimental Reactor), and a mock-up test carried out. The functions of this system are to cut 100A x Sch 40 pipes of SUS316L by internal access, to adjust the core gap between the as-cut pipe and new pipe, and to weld the pipes automatically. The core gap of the pipes could be decreased within the proper welding conditions by the mock-up test, and sound beads were obtained. (author)

  19. Remote Controlling and Monitoring of Microscopic Slides

    International Nuclear Information System (INIS)

    Mustafa, G.; Qadri, M.T.; Daraz, U.

    2016-01-01

    Remotely controlled microscopic slide was designed using especial Graphical User Interface (GUI) which interfaces the user at remote location with the real microscope using site and the user can easily view and control the slide present on the microscope's stage. Precise motors have been used to allow the movement in all the three dimensions required by a pathologist. The pathologist can easily access these slides from any remote location and so the physical presence of the pathologist is now made easy. This invention would increase the health care efficiency by reducing the time and cost of diagnosis, making it very easy to get the expert's opinion and supporting the pathologist to relocate himself for his work. The microscope is controlled with computer with an attractive Graphical User Interface (GUI), through which a pathologist can easily monitor, control and record the image of the slide. The pathologist can now do his work regardless of his location, time, cost and physically presence of lab equipment. The technology will help the specialist in viewing the patients slide from any location in the world. He would be able to monitor and control the stage. This will also help the pathological laboratories in getting opinion from senior pathologist who are present at any far location in the world. This system also reduces the life risks of the patients. (author)

  20. The Remotely Controlled Robot System for Nuclear Power Plants

    International Nuclear Information System (INIS)

    Koh, Kwangill; Lee, Gwangnam; Lim, Kyeyoung

    1993-01-01

    The problem of radioactivity has been our major concern. So, it makes the needs of remotely controlled robot system necessary for maintenance and repair services. Up to now, several foreign companies have been contracted for the maintenance of the steam generators of nuclear power plants in Korea, to acquire its own capability of maintaining the steam generators of it impossible for Korea to acquire its own capability of maintaining the steam generators. In case of emergency, it is difficult to take appropriate steps on its own. In order to resolve the above problems, it seems inevitable to develop the robot system for the inspection and repair of steam generator. This project intends to acquire domestic capabilities of maintaining steam generators, so that this advanced skills could be applied to the related areas. As a result, it will save immense money in the future. the purposes of development of the remotely controlled robot system are : to perform the desired tasks at the polluted area without requiring entry of personnel. to closely inspect the steam generator U-tubes at high speed. to inspect the steam generator intelligently and efficiently under the extreme circumstances where radioactivity problem is very severe. to use for the repair of steam generator tube. Considering from the social and technical standpoint, we can say that the development of the remotely controlled robot system for nuclear power plants resulted in great achievements. From the social standpoint, it should be recognized that domestic robot for nuclear power plant was successfully developed and operator was protected against radioactivity. Also, we advanced our skills in the area of mechanical and control system design for an articulated robot. Using the robot controller in hierarchical structure, it was possible to control the robot remotely. In addition, resolver feedback typed A C servo drive was proven to be sturdy in hazardous environment. Now we are confident that our robot will

  1. Remote Control of TJ-II Diagnostics

    International Nuclear Information System (INIS)

    Lopez Sanchez, A.; Vega, J.; Montoro, A.; Encabo, J.

    2001-01-01

    The present paper is about the design and development of ten remote control diagnostic systems used in the study of plasma fusion in the TJ-II device installed at CIEMAT. This development goes from the definition of sensors and devices necessary in carrying out these remote controls, to its assembly, wiring, development of electronic circuits inserted between sensors and PLC, development of programs for these PLC, connections and administration of the real time automation network, and later development of the necessary programs via the appropriate software tools for web access through a navigator to a specific web page, allowing visual and real time access over the auxiliary systems that make up all the diagnostics. (Author)

  2. Virtual Machine Language Controls Remote Devices

    Science.gov (United States)

    2014-01-01

    Kennedy Space Center worked with Blue Sun Enterprises, based in Boulder, Colorado, to enhance the company's virtual machine language (VML) to control the instruments on the Regolith and Environment Science and Oxygen and Lunar Volatiles Extraction mission. Now the NASA-improved VML is available for crewed and uncrewed spacecraft, and has potential applications on remote systems such as weather balloons, unmanned aerial vehicles, and submarines.

  3. The role of the restructured Mobile Remote Service Base System (MBS) in support of Space Station maintenance and servicing

    Science.gov (United States)

    Darlington, T.; Krukewich, K.

    1992-08-01

    The critical parameters resulting from the restructuring of Space Station Freedom which necessitated the redesign of the Mobile Remote Service Base System (MBS) are described. These include optimization of robotic attachment locations for access to the Space Station truss-mounted orbital replacement units, transport of logistics carriers to the maintenance sites, minimization of EVA overhead associated with maintenance, self-maintenance of other mobile servicing system (MSS) elements on the MBS, and balancing of station EVA and extravehicular robotics in a complementary fashion to minimize maintenance overhead in general. Consideration is given to the configuration of the resulting MBS, which provides the program with maximum flexibility to utilize the assets of the MSS and optimizes end-to-end maintenance with regard to the use of station resources such as crew time and power. Maintenance and servicing scenarios which are instrumental to the reconfigured MBS as well as the results of improved maintenance capability are presented.

  4. Assistance tools for generic definition of ITER maintenance tasks and scenarios in advanced supervisory control systems

    International Nuclear Information System (INIS)

    Zieba, Stéphane; Russotto, François-Xavier; Da Silva Simoes, Max; Measson, Yvan

    2013-01-01

    Highlights: ► Improve supervisory control systems for ITER in-vessel and hot cell maintenance. ► Optimize remote handling operations effectiveness, reliability and safety. ► Provide a generic description of the maintenance tasks and scenarios. ► Development of context-based assistances for operators and supervisor. ► Improvement of operator's situation awareness. -- Abstract: This paper concerns the improvement of supervisory control systems in the context of remote handling for the maintenance tasks in ITER. This work aims at providing a single formalism and tools to define in a generic way the ITER maintenance tasks and scenarios for in-vessel and hot cell operations. A three-layered approach is proposed to model these tasks and scenarios. Physical actions are defined for the scene elements. From these physical actions, behaviours are defined to represent high-level functionalities. Finally, interaction modes define the way that behaviours are achieved in terms of human–machine interactions. Case study concerning the blanket maintenance procedure is discussed concerning the contributions of the descriptive model and the context-based assistances to the activities of supervisory control

  5. Wind turbine remote control using Android devices

    Science.gov (United States)

    Rat, C. L.; Panoiu, M.

    2018-01-01

    This paper describes the remote control of a wind turbine system over the internet using an Android device, namely a tablet or a smartphone. The wind turbine workstation contains a LabVIEW program which monitors the entire wind turbine energy conversion system (WECS). The Android device connects to the LabVIEW application, working as a remote interface to the wind turbine. The communication between the devices needs to be secured because it takes place over the internet. Hence, the data are encrypted before being sent through the network. The scope was the design of remote control software capable of visualizing real-time wind turbine data through a secure connection. Since the WECS is fully automated and no full-time human operator exists, unattended access to the turbine workstation is needed. Therefore the device must not require any confirmation or permission from the computer operator in order to control it. Another condition is that Android application does not have any root requirements.

  6. 46 CFR 111.54-3 - Remote control.

    Science.gov (United States)

    2010-10-01

    ... 46 Shipping 4 2010-10-01 2010-10-01 false Remote control. 111.54-3 Section 111.54-3 Shipping COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED) ELECTRICAL ENGINEERING ELECTRIC SYSTEMS-GENERAL REQUIREMENTS Circuit Breakers § 111.54-3 Remote control. Remotely controlled circuit breakers must have local...

  7. An Investigation of Secure Remote Instrument Control

    Energy Technology Data Exchange (ETDEWEB)

    Schissel, D.; Abla, G.; Penaflor, B. [General Atomics, San Diego (United States); Ciarlette, D. [Oak Ridge National Laboratory, Oak Ridge (United States)

    2009-07-01

    This paper examines the computer science issues associated with secure remote instrumentation control for magnetic fusion experiments. Computer science research into enhancing the ability to scientifically participate in a fusion experiment remotely has been growing in size in an attempt to better address the needs of fusion scientists worldwide. The natural progression of this research is to examine how to move from remote scientific participation to remote hardware control. The vision is to define a gatekeeper software system that will be the only channel of interaction for incoming requests to the experimental site. The role of the gatekeeper is to validate the identification and access privilege of the requester and to insure the validity of the proposed request. The vision for the gatekeeper is that it be a modular system that is simple in design and defined in a way that makes its implementation and operation transparent and obvious. The architecture of the module interface is flexible enough that it can easily allow the future addition of new modules. At the same time, it should be transparent to end-users and allow a high volume of activity so as to not provide a work bottleneck. Appropriate security requires the ability to verify identity (authentication), verify access control (authorization), and validate the appropriateness of requests. The validation process can include provenance and semantic methodologies. The results of the gatekeeper design and initial prototype testing will be presented as well as a discussion on the implication of this research on the operation of fusion experimental machines such as ITER. (authors)

  8. Development of inspection and maintenance program for reactor and reactivity control units in HANARO

    International Nuclear Information System (INIS)

    Cho, Yeong-Garp

    1998-01-01

    This paper summarizes the overall program for inspection and maintenance of reactor structure and Reactivity Control Units (RCU) of HANARO during lifetime. The long-term plan for in-service inspection is introduced in the viewpoint of the structural integrity of reactor and RCU, and the operability of RCU mechanism. This program includes the list of components to be inspected, the schedule of inspection and maintenance, and the development of special tools and test rig that are required for the remote inspection and maintenance of reactor and RCU components. Preliminary results of the evaluation on the lifetime of RCU components are summarized based on the operation history since the installation of reactor. A test rig will be designed and constructed for the purposes of verifying the prolonged lifetime of RCU components being used, the performance of special tools, and the rehearsal of maintenance work as well. (author)

  9. Remotely controlled repair at Douglas Point

    International Nuclear Information System (INIS)

    Anon.

    1981-01-01

    The Douglas Point nuclear generating station, completed in 1966, was Canada's first venture in commercial nuclear power. The discovery, 11 years later, of two perforations in auxiliary piping in a high radiation area led Atomic Energy of Canada Ltd and Ontario Hydro to develop new approaches to remotely controlled repair that will have much wider applications. Eddy current and ultrasonic testing were used to determine the pattern and extent of wear in a pipe encircled by a U-bolt, without first removing the U-bolt. Progress was monitored using remote TV cameras. Welding tools were designed and fabricated for the repairs, and a manipulator was also designed to transport the tool into its place of work. (author)

  10. Exposure control during high maintenance jobs

    International Nuclear Information System (INIS)

    Hinson, C.S.; Wigginton, J.E.

    1991-01-01

    Occupational radiation doses at US light-water-cooled reactors (LWRs) have been decreasing every year since 1983. In 1989, the LWR average dose per reactor reached its lowest point since 1973. Historically, maintenance-related activities have accounted for between 70 and 75% of the total occupational doses at US LWRs, and most of this maintenance-related dose is accrued during plant outages. This paper will focus on high dose maintenance jobs such as steam generator replacement, recirculation pipe replacement/crack repair, induction heating stress improvement, and steam generator tube plugging/sleeving and will discuss how the doses associated with these jobs have declined over the past several years through the implementation of various ALARA techniques

  11. A remote control room at DIII-D

    International Nuclear Information System (INIS)

    Abla, G.; Schissel, D.P.; Penaflor, B.G.; Wallace, G.

    2008-01-01

    This paper describes a remote control room built at DIII-D to support remote participation activities of DIII-D research staff. In order to create a persistent, efficient, and reliable remote participation environment for DIII-D scientists, a remote control room has been built in a 640-ft 2 dedicated area. The purpose of this room is to experiment and define a remote control room framework that can facilitate the remote participation needs of current and future fusion experiments such as ITER. A variety of hardware equipment has been installed and several remote participation and collaboration technologies have been deployed. Objectivity and practical consideration has been the key while designing the room and deploying the technologies. Although, the DIII-D remote control room is still a work in progress and new software tools are being implemented, it has been already useful for a number of international remote participation activities. For example, it has been used for remote support of the EAST Tokamak in China during the start up operation and proven effective for other collaborative experiment activities. The description of the remote control room design is given along with technologies deployed for remote collaboration needs. We will also discuss our recent experiences involving the DIII-D remote control room as well as future plans for improvements

  12. Controls from remote through Social networks

    Directory of Open Access Journals (Sweden)

    Alessandra Ingrao

    2016-03-01

    Full Text Available The Author focuses on the recently reformed provisions regulating the employer’s power to control from remote the employees’ activities (art. 4 of the Workers Statute, with particular regard to controls performed by means of Social networks.Such controls are in fact extremely powerful due to the versatile and multi-purpose character of Social networks, which may also be used as a working device. A widespread case law shows indeed that employer’s controls may cost a worker his job.Therefore, after the reform, all employees will have to read carefully the employer’s Privacy policies, before accessing socials during the worktime to express opinions and/or frustrations.

  13. Remotely controlled repairs at Douglas Point NGS

    International Nuclear Information System (INIS)

    Broad, Les

    In September, 1977, leakage of heavy water at a rate of 125 kg/hr was detected in an area of the Douglas Point NGS reactor vault below the calandria known as the lower labyrinth. Radiation in the area ranges up to 5000 R/hr and the only ready access was through four 75 mm inspection ports that open into the moderator room. Remote-controlled equipment was designed and built to diagnose the problems and carry out repairs. All damaged piping was fixed, supports were replaced as needed, and system vibration was reduced. The work was done with no injuries and little radiation dose

  14. High aspect ratio, remote controlled pumping assembly

    Science.gov (United States)

    Brown, Steve B.; Milanovich, Fred P.

    1995-01-01

    A miniature dual syringe-type pump assembly which has a high aspect ratio and which is remotely controlled, for use such as in a small diameter penetrometer cone or well packer used in water contamination applications. The pump assembly may be used to supply and remove a reagent to a water contamination sensor, for example, and includes a motor, gearhead and motor encoder assembly for turning a drive screw for an actuator which provides pushing on one syringe and pulling on the other syringe for injecting new reagent and withdrawing used reagent from an associated sensor.

  15. Integrated digital control and man-machine interface for complex remote handing systems

    International Nuclear Information System (INIS)

    Rowe, J.C.; Spille, R.F.; Zimmermann, S.D.

    1987-01-01

    The Advanced Integrated Maintenance System (AIMS) is part of a continuing effort within the Consolidated Fuel Reprocessing Program at Oak Ridge National Laboratory to develop and extend the capabilities of remote manipulation and maintenance technology. The AIMS is a totally integrated approach to remote handling in hazardous environments. State-of-the-art computer systems connected through a high-speed distributed control system that supports the flexibility and expandability needed for large integrated maintenance applications. A man-Machine Interface provides high-level human interaction through a powerful color graphics menu-controlled operator console. An auxiliary control system handles the real-time processing needs for a variety of support hardware. A pair of dedicated fiber-optic-linked master/slave computer systems control the Advanced Servomanipulator master/slave arms using powerful distributed digital processing methods. The FORTH language was used as a real-time operating and development environment for the entire system, and all of these components are integrated into a control room concept that represents the latest advancements in the development of remote maintenance facilities for hazardous environments

  16. Integrated digital control and man-machine interface for complex remote handling systems

    International Nuclear Information System (INIS)

    Rowe, J.C.; Spille, R.F.; Zimmermann, S.D.

    1986-12-01

    The Advanced Integrated Maintenance System (AIMS) is part of a continuing effort within the Consolidated Fuel Reprocessing Program at Oak Ridge National Laboratory to develop and extend the capabilities of remote manipulation and maintenance technology. The AIMS is a totally integrated approach to remote handling in hazardous environments. State-of-the-art computer systems connected through a high-speed communication network provide a real-time distributed control system that supports the flexibility and expandability needed for large integrated maintenance applications. A Man-Machine Interface provides high-level human interaction through a powerful color graphics menu-controlled operator console. An auxiliary control system handles the real-time processing needs for a variety of support hardware. A pair of dedicated fiber-optic-linked master/slave computer system control the Advanced Servomanipulator master/slave arms using powerful distributed digital processing methods. The FORTH language was used as a real-time operating and development environment for the entire system, and all of these components are integrated into a control room concept that represents the latest advancements in the development of remote maintenance facilities for hazardous environments

  17. A Self-Calibrating Remote Control Chemical Monitoring System

    Energy Technology Data Exchange (ETDEWEB)

    Jessica Croft

    2007-06-01

    The Susie Mine, part of the Upper Tenmile Mining Area, is located in Rimini, MT about 15 miles southwest of Helena, MT. The Upper Tenmile Creek Mining Area is an EPA Superfund site with 70 abandoned hard rock mines and several residential yards prioritized for clean up. Water from the Susie mine flows into Tenmile Creek from which the city of Helena draws part of its water supply. MSE Technology Applications in Butte, Montana was contracted by the EPA to build a treatment system for the Susie mine effluent and demonstrate a system capable of treating mine waste water in remote locations. The Idaho National Lab was contracted to design, build and demonstrate a low maintenance self-calibrating monitoring system that would monitor multiple sample points, allow remote two-way communications with the control software and allow access to the collected data through a web site. The Automated Chemical Analysis Monitoring (ACAM) system was installed in December 2006. This thesis documents the overall design of the hardware, control software and website, the data collected while MSE-TA’s system was operational, the data collected after MSE-TA’s system was shut down and suggested improvements to the existing system.

  18. Sensor-driven, fault-tolerant control of a maintenance robot

    International Nuclear Information System (INIS)

    Moy, M.M.; Davidson, W.M.

    1987-01-01

    A robot system has been designed to do routine maintenance tasks on the Sandia Pulsed Reactor (SPR). The use of this Remote Maintenance Robot (RMR) is expected to significantly reduce the occupational radiation exposure of the reactor operators. Reactor safety was a key issue in the design of the robot maintenance system. Using sensors to detect error conditions and intelligent control to recover from the errors, the RMR is capable of responding to error conditions without creating a hazard. This paper describes the design and implementation of a sensor-driven, fault-tolerant control for the RMR. Recovery from errors is not automatic; it does rely on operator assistance. However, a key feature of the error recovery procedure is that the operator is allowed to reenter the programmed operation after the error has been corrected. The recovery procedure guarantees that the moving components of the system will not collide with the reactor during recovery

  19. Remote tool development at the Interim Examination and Maintenance (IEM) cell

    International Nuclear Information System (INIS)

    Kalk, J.J.

    1986-07-01

    Tightening fasteners remotely in a hot cell can be a very exasperating experience. In many places, viewing is difficult and work sometimes must be done using mirrors and/or cameras for viewing. If electromechanical manipulators are used, the operator has no ''feel'', which often can result in broken equipment. At the Interim Examination and Maintenance (IEM) Cell, where reactor components from the Fast Flux Test Facility (FFTF) are disassembled, several tools have been developed for tightening fasteners under these conditions. The philosophy used for this tool development is to use inexpensive commercially available tools with minimal modification for in-cell use. This philosophy was adopted after spending several years unsuccessfully trying to develop a special electric impact wrench

  20. Improving the development, use and control of maintenance procedures

    International Nuclear Information System (INIS)

    Morgenstern, M.H.; Barnes, V.E.; Radford, L.R.; Wheeler, W.A.; Badalamente, R.V.

    1985-12-01

    This paper describes the results of a project conducted for the US Nuclear Regulatory Commission (NRC) to assess and document the need for guidance or regulatory involvement by the NRC in the development, upgrading, use and control of maintenance procedures in US nuclear power plants. Presented are the findings of the following activities: (1) a survey of current maintenance procedure practices in seven US nuclear power plants; (2) a review and analysis of plant administrative and maintenance procedures; (3) a survey of maintenance procedure practices in industries that share some characteristics with the nuclear industry; and (4) a review of the research pertaining to job performance aids and a brief analysis of their applicability to maintenance in nuclear power plants. Based on these findings, several recommendations to upgrade maintenance procedures are offered

  1. Improvement of robustness of optical see-through AR for a remote maintenance support system

    International Nuclear Information System (INIS)

    Nagamatsu, Takashi; Kaieda, Yohei; Kitagawa, Yuki; Shimada, Hiroyuki; Otsuji, Tomoo; Yoshikawa, Hidekazu

    2005-01-01

    A remote maintenance support system using optical see-through AR has been developed to keep safety and reliability in preparation for old experts' retirement. It enables plant workers to collaborate with a remote expert (supervisor) by using a wearable computer, an optical see-through AR (Augmented Reality) technology and eye-gaze information. The optical see-through AR enables a user to see the real world through a transparent display and it contributes to keeping safety of plant workers and acquiring detail information of machines. On the contrary, the registration between computer-generated objects and the real world is difficult, so we developed a method to correct the geometrical consistency for practical use of optical see-through AR. The developed method has two steps: (1) detection of the shift amount of HMD by the eye camera image and (2) adjustment of the display position on the HMD screen. This method made it possible to allow user's moving and physical shift of HMD, so it is capable of wide application to practical works

  2. Aspects of remote maintenance in an FRG reprocessing plant from the manufacturer's viewpoint

    International Nuclear Information System (INIS)

    Zeitzchel, G.; Tennie, M.; Saal, G.

    1986-01-01

    In April 1986 a consortium led by Kraftwerk Union AG was commissioned by the German society for nuclear fuel reprocessing (DWK) to build the first West German commercial reprocessing plant for spent fuel assemblies. The main result of the planning efforts regarding remote maintenance operations inside the main process building was the introduction of FEMO technology (FEMO is an acronym based on German for remote handling modular technique). According to this technology the two cells in which the actual reprocessing (which is based on the PUREX technique) takes place are provided with frames to accommodate the process components (tanks, pumps, agitators, etc.), each frame together with the components which it supports forming one module. The two cells are inaccessible and windowless. For handling operations each cell is equipped with an overhead crane and a crane-like manipulator carrier system (MTS) with power manipulator. Viewing of the operations from outside the cells is made possible by television (TV) cameras installed at the crane, the MTS, and the manipulator. This paper addresses some examples of problems that still need to be solved in connection with FEMO handling. In particular, the need for close cooperation between the equipment operator, the component designer, the process engineer, the planning engineer, and the licensing authorities will be demonstrated

  3. Web based remote instrumentation and control

    International Nuclear Information System (INIS)

    Dhekne, P.S.; Patil, Jitendra; Kulkarni, Jitendra; Babu, Prasad; Lad, U.C.; Rahurkar, A.G.; Kaura, H.K.

    2001-01-01

    The Web-based technology provides a very powerful communication medium for transmitting effectively multimedia information containing data generated from various sources, which may be in the form of audio, video, text, still or moving images etc. Large number of sophisticated web based software tools are available that can be used to monitor and control distributed electronic instrumentation projects. For example data can be collected online from various smart sensors/instruments such as images from CCD camera, pressure/ humidity sensor, light intensity transducer, smoke detectors etc and uploaded in real time to a central web server. This information can be processed further, to take control action in real time from any remote client, of course with due security care. The web-based technology offers greater flexibility, higher functionality, and high degree of integration providing standardization. Further easy to use standard browser based interface at the client end to monitor, view and control the desired process parameters allow you to cut down the development time and cost to a great extent. A system based on a web client-server approach has been designed and developed at Computer division, BARC and is operational since last year to monitor and control remotely various environmental parameters of distributed computer centers. In this paper we shall discuss details of this system, its current status and additional features which are currently under development. This type of system is typically very useful for Meteorology, Environmental monitoring of Nuclear stations, Radio active labs, Nuclear waste immobilization plants, Medical and Biological research labs., Security surveillance and in many such distributed situations. A brief description of various tools used for this project such as Java, CGI, Java Script, HTML, VBScript, M-JPEG, TCP/IP, UDP, RTP etc. along with their merits/demerits have also been included

  4. Software Development for Remote Control and Firing Room Displays

    Science.gov (United States)

    Zambrano Pena, Jessica

    2014-01-01

    The Launch Control System (LCS) developed at NASA's Kennedy Space Center (KSC) will be used to launch future spacecraft. Two of the many components of this system are the Application Control Language (ACL) and remote displays. ACL is a high level domain specific language that is used to write remote control applications for LCS. Remote displays are graphical user interfaces (GUIs) developed to display vehicle and Ground Support Equipment (GSE) data, they also provide the ability to send commands to control GSE and the vehicle. The remote displays and the control applications have many facets and this internship experience dealt with several of them.

  5. Unidirectional Quantum Remote Control:Teleportation of Control-State

    Institute of Scientific and Technical Information of China (English)

    ZHENG Yi-Zhuang; GU Yong-Jian; WU Gui-Chu; GUO Guang-Can

    2003-01-01

    We investigate the problem of teleportation of unitary operations by unidirectional control-state telepor-tation and propose a scheme called unidirectional quantum remote control. The scheme is based on the isomorphismbetween operation and state. It allows us to store a unitary operation in a control state, thereby teleportation of theunitary operation can be implemented by unidirectional teleportation of the control-state. We find that the probabilityof success for implementing an arbitrary unitary operation on arbitrary M-qubit state by unidirectional control-stateteleportation is 4-M, and 2M ebits and 4M cbits are consumed in each teleportation.

  6. Control software architecture and operating modes of the Model M-2 maintenance system

    Energy Technology Data Exchange (ETDEWEB)

    Satterlee, P.E. Jr.; Martin, H.L.; Herndon, J.N.

    1984-04-01

    The Model M-2 maintenance system is the first completely digitally controlled servomanipulator. The M-2 system allows dexterous operations to be performed remotely using bilateral force-reflecting master/slave techniques, and its integrated operator interface takes advantage of touch-screen-driven menus to allow selection of all possible operating modes. The control system hardware for this system has been described previously. This paper describes the architecture of the overall control system. The system's various modes of operation are identified, the software implementation of each is described, system diagnostic routines are described, and highlights of the computer-augmented operator interface are discussed. 3 references, 5 figures.

  7. Control software architecture and operating modes of the Model M-2 maintenance system

    International Nuclear Information System (INIS)

    Satterlee, P.E. Jr.; Martin, H.L.; Herndon, J.N.

    1984-04-01

    The Model M-2 maintenance system is the first completely digitally controlled servomanipulator. The M-2 system allows dexterous operations to be performed remotely using bilateral force-reflecting master/slave techniques, and its integrated operator interface takes advantage of touch-screen-driven menus to allow selection of all possible operating modes. The control system hardware for this system has been described previously. This paper describes the architecture of the overall control system. The system's various modes of operation are identified, the software implementation of each is described, system diagnostic routines are described, and highlights of the computer-augmented operator interface are discussed. 3 references, 5 figures

  8. A randomized controlled trial of interim methadone maintenance.

    Science.gov (United States)

    Schwartz, Robert P; Highfield, David A; Jaffe, Jerome H; Brady, Joseph V; Butler, Carol B; Rouse, Charles O; Callaman, Jason M; O'Grady, Kevin E; Battjes, Robert J

    2006-01-01

    Effective alternatives to long waiting lists for entry into methadone hydrochloride maintenance treatment are needed to reduce the complications of continuing heroin dependence and to increase methadone treatment entry. To compare the effectiveness of interim methadone maintenance with that of the usual waiting list condition in facilitating methadone treatment entry and reducing heroin and cocaine use and criminal behavior. Randomized, controlled, clinical trial using 2 conditions, with treatment assignment on a 3:2 basis to interim maintenance-waiting list control. A methadone treatment program in Baltimore. A total of 319 individuals meeting the criteria for current heroin dependence and methadone maintenance treatment. Participants were randomly assigned to either interim methadone maintenance, consisting of an individually determined methadone dose and emergency counseling only for up to 120 days, or referral to community-based methadone treatment programs. Entry into comprehensive methadone maintenance therapy at 4 months from baseline; self-reported days of heroin use, cocaine use, and criminal behavior; and number of urine drug test results positive for heroin and cocaine at the follow-up interview conducted at time of entry into comprehensive methadone treatment (or at 4 months from baseline for participants who did not enter regular treatment). Significantly more participants assigned to the interim methadone maintenance condition entered comprehensive methadone maintenance treatment by the 120th day from baseline (75.9%) than those assigned to the waiting list control condition (20.8%) (Pmethadone maintenance results in a substantial increase in the likelihood of entry into comprehensive treatment, and is an effective means of reducing heroin use and criminal behavior among opioid-dependent individuals awaiting entry into a comprehensive methadone treatment program.

  9. Maintenance and adjustment of control systems of central heating turbines

    International Nuclear Information System (INIS)

    Karasyuk, V.A.; Balashov, A.M.

    1994-01-01

    Principles of operation and design of systems of automatic control of steam turbines with controlled heating stem extraction are described. Specific features of maintenance and adjustment of the most common domestic turbines are considered. Recommendations on testing state of turbine control systems and improving reliability of their operation are given. 22 refs., 51 refs

  10. Tools for remote computing in accelerator control

    International Nuclear Information System (INIS)

    Anderssen, P.S.; Frammery, V.; Wilcke, R.

    1990-01-01

    In modern accelerator control systems, the intelligence of the equipment is distributed in the geographical and the logical sense. Control processes for a large variety of tasks reside in both the equipment and the control computers. Hence successful operation hinges on the availability and reliability of the communication infrastructure. The computers are interconnected by a communication system and use remote procedure calls and message passing for information exchange. These communication mechanisms need a well-defined convention, i.e. a protocol. They also require flexibility in both the setup and changes to the protocol specification. The network compiler is a tool which provides the programmer with a means of establishing such a protocol for his application. Input to the network compiler is a single interface description file provided by the programmer. This file is written according to a grammar, and completely specifies the interprocess communication interfaces. Passed through the network compiler, the interface description file automatically produces the additional source code needed for the protocol. Hence the programmer does not have to be concerned about the details of the communication calls. Any further additions and modifications are made easy, because all the information about the interface is kept in a single file. (orig.)

  11. Reduced waste arise in a reprocessing plant by the use of remote control

    International Nuclear Information System (INIS)

    Issel, W.A.

    1988-01-01

    This paper discusses how the increasing use of remote controlled processes, which is unavoidable with respect to work in hostile environment and which after serious further development and experience may improve plant production rate lead to another benefit in handling nuclear material, the benefit of reducing waste production and by this the avoidance of radioactive dispersal. The example of reprocessing of spent fuel is shown, what consequences and what improvements can be expected in the waste management by remote handling and maintenance instead of direct intervention by men

  12. Dynamical model of birdsong maintenance and control

    Science.gov (United States)

    Abarbanel, Henry D. I.; Talathi, Sachin S.; Mindlin, Gabriel; Rabinovich, Misha; Gibb, Leif

    2004-11-01

    The neuroethology of song learning, production, and maintenance in songbirds presents interesting similarities to human speech. We have developed a biophysical model of the manner in which song could be maintained in adult songbirds. This model may inform us about the human counterpart to these processes. In songbirds, signals generated in nucleus High Vocal center (HVc) follow a direct route along a premotor pathway to the robust nucleus of the archistriatum (RA) as well as an indirect route to RA through the anterior forebrain pathway (AFP): the neurons of RA are innervated from both sources. HVc expresses very sparse bursts of spikes having interspike intervals of about 2ms . The expressions of these bursts arrive at the RA with a time difference ΔT≈50±10ms between the two pathways. The observed combination of AMPA and NMDA receptors at RA projection neurons suggests that long-term potentiation and long-term depression can both be induced by spike timing plasticity through the pairing of the HVc and AFP signals. We present a dynamical model that stabilizes this synaptic plasticity through a feedback from the RA to the AFP using known connections. The stabilization occurs dynamically and is absent when the RA→AFP connection is removed. This requires a dynamical selection of ΔT . The model does this, and ΔT lies within the observed range. Our model represents an illustration of a functional consequence of activity-dependent plasticity directly connected with neuroethological observations. Within the model the parameters of the AFP, and thus the magnitude of ΔT , can also be tuned to an unstable regime. This means that destabilization might be induced by neuromodulation of the AFP.

  13. 21 CFR 892.5700 - Remote controlled radionuclide applicator system.

    Science.gov (United States)

    2010-04-01

    ... radionuclide applicator system. (a) Identification. A remote controlled radionuclide applicator system is an... 21 Food and Drugs 8 2010-04-01 2010-04-01 false Remote controlled radionuclide applicator system... include patient and equipment supports, component parts, treatment planning computer programs, and...

  14. Guidelines for remote handling maintenance of ITER neutral beam line components: Proposal of an alternate supporting system

    International Nuclear Information System (INIS)

    Cordier, J.J.; Bayetti, P.; Hemsworth, R.; David, O.; Friconneau, J.P.

    2007-01-01

    Remote handling (R/H) maintenance of ITER components is one of the main challenges of the ITER project. This type of maintenance shall be operational for the assembly and nuclear phase of exploitation of ITER. It must be considered at a very early stage since it significantly impacts on the components design, interfaces management, assembly, maintenance and integration aspects. A large part of the R/H equipment will be procured by the EU Participating Team, including the whole Neutral Beam R/H Equipment. The Neutral Beam Heating and Current Drive system (NB and CD) design is being revisited by the ITER project. A vertical maintenance scheme is presently considered which may significantly impact on the reference design and associated components and lead to a new design of the NB and CD vacuum tank. In addition, NB line components remote handling solutions are being studied. The neutral beam test facility ITER to be built in Europe in the near future is also based on the vertical NB maintenance scheme of beam line components. New design guidelines compliant for both the ITER NB and CD system and the NB test facility proposed by the CEA association are described in the paper

  15. Maintenance of Occupational Control: The Case of Professions.

    Science.gov (United States)

    Child, John; Fulk, Janet

    1982-01-01

    Contemporary conditions relevant to the maintenance of occupational control are examined for five professions (accounting, architecture, civil engineering, law, and medicine) in the United Kingdom and the United States as an impetus for the analysis of control by occupations in general. (Author/CT)

  16. Remote device control and monitor system for the LHD deuterium experiments

    Energy Technology Data Exchange (ETDEWEB)

    Nakanishi, Hideya, E-mail: nakanisi@nifs.ac.jp [National Institute for Fusion Science (NIFS), Toki, Gifu 509-5292 (Japan); Dept. Fusion Science, SOKENDAI (The Graduate University for Advanced Studies), Toki, Gifu 509-5292 (Japan); Ohsuna, Masaki; Ito, Tatsuki; Nonomura, Miki; Imazu, Setsuo; Emoto, Masahiko; Iwata, Chie; Yoshida, Masanobu; Yokota, Mitsuhiro; Maeno, Hiroya; Aoyagi, Miwa; Ogawa, Hideki; Nakamura, Osamu; Morita, Yoshitaka; Inoue, Tomoyuki; Watanabe, Kiyomasa [National Institute for Fusion Science (NIFS), Toki, Gifu 509-5292 (Japan); Ida, Katsumi; Ishiguro, Seiji; Kaneko, Osamu [National Institute for Fusion Science (NIFS), Toki, Gifu 509-5292 (Japan); Dept. Fusion Science, SOKENDAI (The Graduate University for Advanced Studies), Toki, Gifu 509-5292 (Japan)

    2016-11-15

    Highlights: • Device remote control will be significant for the LHD deuterium experiments. • A central management GUI to control the power distribution for devices. • For safety, power management is separated from operational commanding. • Wi-Fi was tested and found to be not reliable with fusion plasmas. - Abstract: Upon beginning the LHD deuterium experiment, the opportunity for maintenance work in the torus hall will be conspicuously reduced such that all instruments must be controlled remotely. The LHD data acquisition (DAQ) and archiving system have been using about 110 DAQ front-end, and the DAQ central control and monitor system has been implemented for their remote management. This system is based on the “multi-agent” model whose communication protocol has been unified. Since DAQ front-end electronics would suffer from the “single-event effect” (SEE) of D-D neutrons, software-based remote operation might become ineffective, and then securely intercepting or recycling the electrical power of the device would be indispensable for recovering from a non-responding fault condition. In this study, a centralized control and monitor system has been developed for a number of power distribution units (PDUs). This system adopts the plug-in structure in which the plug-in modules can absorb the differences among the commercial products of numerous vendors. The combination of the above-mentioned functionalities has led to realizing the flexible and highly reliable remote control infrastructure for the plasma diagnostics and the device management in LHD.

  17. AUTOMATIC CONTROL SYSTEM OF WINTER AUTOMOBILE-ROAD MAINTENANCE

    Directory of Open Access Journals (Sweden)

    I. I. Leonovich

    2008-01-01

    Full Text Available In order to ensure a rational usage of financial and material resources directed on winter automobile-road maintenance in theRepublicofBelarusan automatic control system of winter maintenance is under its development and introduction.  The main purpose of the system is to obtain and use meteorological information on the state of a road network that allows to take necessary organizational and technological solutions ensuring safety and continuity of traffic during winter. This system also presupposes to ensure constant control over the state of roadway covering, expenditure of anti-glazed frost materials at all levels of management.The paper considers main aspects pertaining to introduction of the automatic control system of winter maintenance

  18. Dynamic analysis of space robot remote control system

    Science.gov (United States)

    Kulakov, Felix; Alferov, Gennady; Sokolov, Boris; Gorovenko, Polina; Sharlay, Artem

    2018-05-01

    The article presents analysis on construction of two-stage remote control for space robots. This control ensures efficiency of the robot control system at large delays in transmission of control signals from the ground control center to the local control system of the space robot. The conditions for control stability of and high transparency are found.

  19. A remotely operated drug delivery system with dose control

    KAUST Repository

    Yi, Ying; Kosel, Jü rgen

    2017-01-01

    include an effective actuation stimulus and a controllable dose release mechanism. This work focuses on remotely powering an implantable drug delivery system and providing a high degree of control over the released dose. This is accomplished by integration

  20. Study on compact design of remote handling equipment for ITER blanket maintenance

    International Nuclear Information System (INIS)

    Takeda, Nobukazu; Kakudate, Satoshi; Nakahira, Masataka; Shibanuma, Kiyoshi

    2006-03-01

    In the ITER, the neutrons created by D-T reactions activate structural materials, and thereby, the circumstance in the vacuum vessel is under intense gamma radiation field. Thus, the in-vessel components such as blanket are handled and replaced by remote handling equipment. The objective of this report is to study the compactness of the remote handling equipment (a vehicle/manipulator) for the ITER blanket maintenance. In order to avoid the interferences between the blanket and the equipment during blanket replacement in the restricted vacuum vessel, a compact design of the equipment is required. Therefore, the compact design is performed, including kinematic analyses aiming at the reduction of the sizes of the vehicle equipped with a manipulator handling the blanket and the rail for the vehicle traveling in the vacuum vessel. Major results are as follows: 1. The compact vehicle/manipulator is designed concentration on the reduction of the rail size and simplification of the guide roller mechanism as well as the reduction of the gear diameter for vehicle rotation around the rail. Height of the rail is reduced from 500 mm to 400 mm by a parameter survey for weight, stiffness and stress of the rail. The roller mechanism is divided into two simple functional mechanisms composed of rollers and a pad, that is, the rollers support relatively light loads during rail deployment and vehicle traveling while a pad supports heavy loads during blanket replacement. Regarding the rotation mechanism, the double helical gear is adopted, because it has higher contact ratio than the normal spur gear and consequently can transfer higher force. The smaller double helical gear, 996 mm in diameter, can achieve 26% higher output torque, 123.5 kN·m, than that of the original spur gear of 1,460 mm in diameter, 98 kN·m. As a result, the manipulator becomes about 30% lighter, 8 tons, than the original weight, 11.2 tons. 2. Based on the compact design of the vehicle/manipulator, the

  1. The ITER EC H and CD Upper Launcher: Analysis of vertical Remote Handling applied to the BSM maintenance

    International Nuclear Information System (INIS)

    Grossetti, Giovanni; Aiello, Gaetano; Heemskerk, Cock; Elzendoorn, Ben; Geßner, Robby; Koning, Jarich; Meier, Andreas; Ronden, Dennis; Späh, Peter; Scherer, Theo; Schreck, Sabine; Strauß, Dirk; Vaccaro, Alessandro

    2013-01-01

    This paper deals with Remote Handling activities foreseen on the Blanket Shield Module, the plasma facing component of the ITER Electron Cyclotron Heating and Current Drive Upper Launcher. The maintenance configuration considered here is the Vertical Remote Handling, meaning gravity acting along the launcher radial axis. The plant, where the maintenance under consideration is occurring, is the Hot Cell Facility Work Cell. The study here reported has been carried out within the presently ongoing EFDA Goal Oriented Training program on Remote Handling (GOT-RH), which aims to support ITER activities. This document and its contents have to be considered as part of a more vast RAMI analysis to be developed within the GOT-RH, which aims to maximize the Electron Cyclotron Heating and Current Drive system availability. The Baseline CAD model of the Electron Cyclotron Heating and Current Drive Upper Launcher is currently in its preliminary design phase and does not provide enough details for developing a fully detailed maintenance strategy. Therefore, through a System Engineering approach, a set of assumptions was conceived on the launcher structure, as a basis for development of a Remote Handling strategy. Moreover, to compare different design solutions related to the possibility of integrating a quasi-optical component into the Blanket Shield Module, a Trade-Off was made, and its contents are shown here. The outcome of this System Engineering approach has been formalized into Task Definition Forms whose contents are reported here. The Remote Handling strategy presented in this work will be tested in the near future both through Virtual Reality simulations and through prototype experiments

  2. The ITER EC H and CD Upper Launcher: Analysis of vertical Remote Handling applied to the BSM maintenance

    Energy Technology Data Exchange (ETDEWEB)

    Grossetti, Giovanni, E-mail: giovanni.grossetti@kit.edu [Karlsruhe Institute of Technology, Association KIT-EURATOM, P.O. Box 3640, D-76021 Karlsruhe (Germany); Aiello, Gaetano [Karlsruhe Institute of Technology, Association KIT-EURATOM, P.O. Box 3640, D-76021 Karlsruhe (Germany); Heemskerk, Cock [Heemskerk Innovative Technology, Merelhof 2, 2172 HZ Sassenheim (Netherlands); Elzendoorn, Ben [FOM Institute DIFFER, P.O. Box 1207, 3430 BE Nieuwegein (Netherlands); Geßner, Robby [Karlsruhe Institute of Technology, Association KIT-EURATOM, P.O. Box 3640, D-76021 Karlsruhe (Germany); Koning, Jarich [Heemskerk Innovative Technology, Merelhof 2, 2172 HZ Sassenheim (Netherlands); Meier, Andreas [Karlsruhe Institute of Technology, Association KIT-EURATOM, P.O. Box 3640, D-76021 Karlsruhe (Germany); Ronden, Dennis [FOM Institute DIFFER, P.O. Box 1207, 3430 BE Nieuwegein (Netherlands); Späh, Peter; Scherer, Theo; Schreck, Sabine; Strauß, Dirk; Vaccaro, Alessandro [Karlsruhe Institute of Technology, Association KIT-EURATOM, P.O. Box 3640, D-76021 Karlsruhe (Germany)

    2013-10-15

    This paper deals with Remote Handling activities foreseen on the Blanket Shield Module, the plasma facing component of the ITER Electron Cyclotron Heating and Current Drive Upper Launcher. The maintenance configuration considered here is the Vertical Remote Handling, meaning gravity acting along the launcher radial axis. The plant, where the maintenance under consideration is occurring, is the Hot Cell Facility Work Cell. The study here reported has been carried out within the presently ongoing EFDA Goal Oriented Training program on Remote Handling (GOT-RH), which aims to support ITER activities. This document and its contents have to be considered as part of a more vast RAMI analysis to be developed within the GOT-RH, which aims to maximize the Electron Cyclotron Heating and Current Drive system availability. The Baseline CAD model of the Electron Cyclotron Heating and Current Drive Upper Launcher is currently in its preliminary design phase and does not provide enough details for developing a fully detailed maintenance strategy. Therefore, through a System Engineering approach, a set of assumptions was conceived on the launcher structure, as a basis for development of a Remote Handling strategy. Moreover, to compare different design solutions related to the possibility of integrating a quasi-optical component into the Blanket Shield Module, a Trade-Off was made, and its contents are shown here. The outcome of this System Engineering approach has been formalized into Task Definition Forms whose contents are reported here. The Remote Handling strategy presented in this work will be tested in the near future both through Virtual Reality simulations and through prototype experiments.

  3. Development of a Remote Handling Robot for the Maintenance of an ITER-Like D-Shaped Vessel

    Directory of Open Access Journals (Sweden)

    Peihua Chen

    2014-01-01

    Full Text Available Robotic operation is one of the major challenges in the remote maintenance of ITER vacuum vessel (VV and future fusion reactors as inner operations of Tokamak have to be done by robots due to the internal adverse conditions. This paper introduces a novel remote handling robot (RHR for the maintenance of ITER-like D-shaped vessel. The modular designed RHR, which is an important part of the remote handling system for ITER, consists of three parts: an omnidirectional transfer vehicle (OTV, a planar articulated arm (PAA, and an articulated teleoperated manipulator (ATM. The task of RHR is to carry processing tools, such as the viewing system, leakage detector, and electric screwdriver, to inspect and maintain the components installed inside the D-shaped vessel. The kinematics of the OTV, as well as the kinematic analyses of the PAA and ATM, is studied in this paper. Because of its special length and heavy payload, the dynamics of the PAA is also investigated through a dynamic simulation system based on robot technology middleware (RTM. The results of the path planning, workspace simulations, and dynamic simulation indicate that the RHR has good mobility together with satisfying kinematic and dynamic performances and can well accomplish its maintenance tasks in the ITER-like D-shaped vessel.

  4. Digital, remote control system for a 2-MW research reactor

    International Nuclear Information System (INIS)

    Battle, R.E.; Corbett, G.K.

    1988-01-01

    A fault-tolerant programmable logic controller (PLC) and operator workstations have been programmed to replace the hard-wired relay control system in the 2-MW Bulk Shielding Reactor (BSR) at Oak Ridge National Laboratory. In addition to the PLC and remote and local operator workstations, auxiliary systems for remote operation include a video system, an intercom system, and a fiber optic communication system. The remote control station, located at the High Flux Isotope Reactor 2.5 km from the BSR, has the capability of rector startup and power control. The system was designed with reliability and fail-safe features as important considerations. 4 refs., 3 figs

  5. The remote control of nuclear microprobes over the Internet

    International Nuclear Information System (INIS)

    Churms, C.L.; Prozesky, V.M.; Springhorn, K.A.

    1999-01-01

    Whereas the concept of remote control is not new, the required equipment and data link have typically been costly and specialized. With the growing availability of reliable Internet connection, it has however become possible and increasingly attractive to be able to control complex equipment remotely over the Internet. Some methods of Internet Remote control are discussed, bearing in mind the specific needs of nuclear microprobe control. One such system has been implemented at the NAC nuclear microprobe, and even though improvements are envisaged, it is already functioning satisfactorily

  6. Master--slave manipulators and remote maintenance at the Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Jenness, R.G.; Wicker, C.D.

    1975-01-01

    The volume of master-slave manipulator maintenance at Oak Ridge National Laboratory has necessitated the establishment of a repair facility and the organization of a specially trained group of craftsmen. Emphasis on cell containment requires the use of manipulator boots and the development of precise procedures for accomplishing the maintenance of 283 installed units. To provide the most economical type of preventive maintenance, a very satisfactory computer-programmed maintenance system has been established at the Laboratory. (auth)

  7. Data acquisition, remote control and equipment monitoring for ISOLDE RILIS

    CERN Document Server

    Rossel, R E; Richter, D; Wendt, K D A; Rothe, S; Marsh, B A

    2013-01-01

    With a steadily increasing on-line operation time up to a record 3000 h in the year 2012, the Resonance Ionization Laser Ion Source (RILIS) is one of the key components of the ISOLDE on-line isotope user facility at CERN. Ion beam production using the RILIS is essential for many experiments due to the unmatched combination of ionization efficiency and selectivity. To meet the reliability requirements the RILIS is currently operated in shift duty for continuous maintenance of crucial laser parameters such as wavelength, power, beam position and timing, as well as ensuring swift intervention in case of an equipment malfunction. A recent overhaul of the RILIS included the installation of new pump lasers, commercial dye lasers and a complementary, fully solid-state titanium:sapphire laser system. The framework of the upgrade also required the setup of a network-extended, LabVIEW-based system for data acquisition, remote control and equipment monitoring, to support RILIS operators as well as ISOLDE users. The syst...

  8. Data acquisition, remote control and equipment monitoring for ISOLDE RILIS

    Science.gov (United States)

    Rossel, R. E.; Fedosseev, V. N.; Marsh, B. A.; Richter, D.; Rothe, S.; Wendt, K. D. A.

    2013-12-01

    With a steadily increasing on-line operation time up to a record 3000 h in the year 2012, the Resonance Ionization Laser Ion Source (RILIS) is one of the key components of the ISOLDE on-line isotope user facility at CERN. Ion beam production using the RILIS is essential for many experiments due to the unmatched combination of ionization efficiency and selectivity. To meet the reliability requirements the RILIS is currently operated in shift duty for continuous maintenance of crucial laser parameters such as wavelength, power, beam position and timing, as well as ensuring swift intervention in case of an equipment malfunction. A recent overhaul of the RILIS included the installation of new pump lasers, commercial dye lasers and a complementary, fully solid-state titanium:sapphire laser system. The framework of the upgrade also required the setup of a network-extended, LabVIEW-based system for data acquisition, remote control and equipment monitoring, to support RILIS operators as well as ISOLDE users. The system contributes to four key aspects of RILIS operation: equipment monitoring, machine protection, automated self-reliance, and collaborative data acquisition. The overall concept, technologies used, implementation status and recent applications during the 2012 on-line operation period will be presented along with a summary of future developments.

  9. Energy: Systems for Control, Maintenance, and Storage. A Bibliography.

    Science.gov (United States)

    Thomas, Gerald, Comp.; McKane, Irving, Comp.

    This publication is a bibliography of available periodical literature on specific aspects of energy and today's technology. The Applied Science and Technology Indexes were searched for articles that related to these specific areas: (1) Energy control systems; (2) Maintenance of Energy Systems; and (3) Energy storage. The articles and papers…

  10. Virtual and remote control tower research, design, development and validation

    CERN Document Server

    2016-01-01

    The interdisciplinary research and development work carried out in the last ten years which is presented in this book aimed at replacing the conventional airport control tower by a new “remote tower operation” work environment (RTO) which should enhance work efficiency and safety and reduce costs. This revolutionary human–system interface allows for remote aerodrome traffic control without a physical tower building and enables the establishment of remote airport traffic control centers (RTC) of which each may serve several airports from a central location.

  11. Preventive maintenance basis: Volume 30 -- Relays -- control. Final report

    International Nuclear Information System (INIS)

    Worledge, D.; Hinchcliffe, G.

    1998-07-01

    US nuclear power plants are implementing preventive maintenance (PM) tasks with little documented basis beyond fundamental vendor information to support the tasks or their intervals. The Preventive Maintenance Basis project provides utilities with the technical basis for PM tasks and task intervals associated with 40 specific components such as valves, electric motors, pumps, and HVAC equipment. This document provides a program of preventive maintenance tasks suitable for application to control relays. The PM tasks that are recommended provide a cost-effective way to intercept the causes and mechanisms that lead to degradation and failure. They can be used in conjunction with material from other sources, to develop a complete PM program or to improve an existing program

  12. Remote monitoring and fault recovery for FPGA-based field controllers of telescope and instruments

    Science.gov (United States)

    Zhu, Yuhua; Zhu, Dan; Wang, Jianing

    2012-09-01

    As the increasing size and more and more functions, modern telescopes have widely used the control architecture, i.e. central control unit plus field controller. FPGA-based field controller has the advantages of field programmable, which provide a great convenience for modifying software and hardware of control system. It also gives a good platform for implementation of the new control scheme. Because of multi-controlled nodes and poor working environment in scattered locations, reliability and stability of the field controller should be fully concerned. This paper mainly describes how we use the FPGA-based field controller and Ethernet remote to construct monitoring system with multi-nodes. When failure appearing, the new FPGA chip does self-recovery first in accordance with prerecovery strategies. In case of accident, remote reconstruction for the field controller can be done through network intervention if the chip is not being restored. This paper also introduces the network remote reconstruction solutions of controller, the system structure and transport protocol as well as the implementation methods. The idea of hardware and software design is given based on the FPGA. After actual operation on the large telescopes, desired results have been achieved. The improvement increases system reliability and reduces workload of maintenance, showing good application and popularization.

  13. Development of Remote Control Laboratory for Radiation Detection via Internet

    International Nuclear Information System (INIS)

    Park, Sang Tae; Lee, Hee Bok; Yuk, Keun Chul

    2002-01-01

    The role of experiments in science education is essential for understanding the natural phenomena and principle related to a subject. Therefore, the remote control experiment via Internet is one of key solution for distance learners in science education. The remote experiments are also necessary for the time-consuming experiment which takes several days, collaborative experiment between distance learners, expensive laboratory equipment which is not usually available to students, experimental procedure which is dangerous, etc. In this study, we have developed a general method for a remote control laboratory system using internet and interface techniques. It is possible for students to learn the nuclear physics to control the real instruments and conduct physics experimentation with internet techniques. We proposed the remote control radiation measurement system as a sample application. This system could be useful for the monitoring near a nuclear power plants in order to improve the environment data credibility to the public

  14. Virtual and Remote Laboratories in Process of Control Education

    Directory of Open Access Journals (Sweden)

    Martin Kalúz

    2012-02-01

    Full Text Available This paper describes the progress in the development of virtual and remote laboratories at Department of Information Engineering and Process Control, FCFT STU in Bratislava. Article is the overview of technical solutions used for online education purposes. These comprise software technologies, most commonly used in virtual and remote laboratory design at our department, as MATLAB Web Server, Java, C/C++, and Adobe Flash. We have created virtual laboratories as online Web applications, which provide features of mathematical computing and simulations of technological plants. We also describe a technology of remote control laboratory with a real experimental device.

  15. Remote control systems evolution in the new open energy market

    International Nuclear Information System (INIS)

    Castiglioni, L.

    2001-01-01

    Considering new energy market in Italy, the new role of remote control applications is discussed. In the open market the whole electric process is managed by several different actors; common protocol scheme and additional sharing data policies are necessaries facing the increased communications requirements due to deregulation. Remote control systems evolution then will lead from process oriented to data management oriented systems; related methodologies and solutions are described [it

  16. Development of radiation-hard electric connector with ball bearing for in-vessel remote maintenance equipment of ITER

    International Nuclear Information System (INIS)

    Ito, Akira; Obara, Kenjiro; Tada, Eisuke; Morita, Yousuke; Yagi, Toshiaki; Iida, Kazuhisa; Sato, Masaru.

    1997-12-01

    Development of radiation-hard electric connector with ball bearing for in-vessel remote maintenance equipment of ITER (International Thermonuclear Experimental Reactor) has been conducted. Since the in-vessel remote maintenance equipment is operated under the condition of 10 6 R/h gamma ray dose rate, the electric connector has to be radiation hard for an accumulation dose of 10 10 R. In addition, the simple attachment/removal mechanism is essential for remote operation. For this, the alumina (Al203) ceramics and a ball bearing were adopted to electric insulator and plug (male) of connector, respectively. The handling tests on attachment/removal of the connector were conducted by using master slave manipulator and general purpose robot with handling tool, and as a result, the validity of the attachment/removal mechanism was verified. In the gamma ray irradiation tests, which are under way, no degradation in break down voltage (1000V 1min.) up to 10 10 R was confirmed. However insulation resistance and contact resistance between contact pin and contact socket were deteriorated in proportion to the accumulation dose. Increase of contact resistance is considered due to an erosion of contact pin. (author)

  17. New achievements of the Divertor Test Platform programme for the ITER divertor remote maintenance R and D

    International Nuclear Information System (INIS)

    Damiani, C.; Baldi, L.; Galbiati, L.; Irving, M.; Lorenzelli, L.; Micciche, G.; Muro, L.; Nucci, S.; Varocchi, G.; Poggianti, A.; Fermani, G.; Maisonnier, D.; Palmer, J.; Martin, E.; Friconneau, J.P.; Gravez, P.; Takeda, N.

    2001-01-01

    The divertor assembly for the ITER fusion reactor consists of a number of rail mounted cassettes (54 now in ITER FEAT) located in the bottom region of the vacuum vessel. These cassettes shall be removed/installed remotely during the life of the reactor by means of specific devices. To demonstrate and optimise the feasibility of the in-vessel maintenance process the Divertor Test Platform (DTP) has been established at the ENEA Research Centre in Brasimone, Italy, as a major part of the large ITER R and D project L7. A first set of tests has been already carried out and reported during 1998, when the basic feasibility of the divertor replacement was demonstrated. In the present period (January 1999-July 2000), new activities, including both site tests and other 'external' R and D works, have been carried out in order to refine and improve the ITER divertor maintenance scenario. These include the study of abnormal maintenance operations and of possible handling equipment failure and its consequences; the procurement and testing of new sub-systems (e.g. a force reflection manipulator arm), and the development of remote handling techniques including a virtual reality system. Following a short description of the DTP, this paper reports on the new results and achievements, draws the relevant conclusions, and finally discusses future activities

  18. Rail deployment and storage procedure and test for ITER blanket remote maintenance

    International Nuclear Information System (INIS)

    Kakudate, S.; Shibanuma, K.

    2003-01-01

    A concept of rail-mounted vehicle manipulator system has been developed to apply to the maintenance of the ITER blanket composed of ∼400 modules in the vacuum vessel. The most critical issue of the vehicle manipulator system is the feasibility of the deployment and storage of the articulated rail, composed of eight rail links without any driving mechanism in the joints. To solve this issue, a new driving mechanism and procedure for the rail deployment and storage has been proposed, taking account of the repeated operation of the multi-rail links deployed and stored in the same kinematical manner. The new driving mechanism, which is different from those of a usual articulated manipulator or 'articulated boom' equipped with actuators in every joint for movement, is composed of three external mechanisms installed outside the articulated rail, i.e. a vehicle traveling mechanism as main driver and two auxiliary driving mechanisms. A simplified synchronized control of three driving mechanisms has also been proposed, including 'torque-limit control' for suppression of the overload of the mechanisms. These proposals have been tested using a full-scale vehicle manipulator system, in order to demonstrate the proof of principle for rail deployment and storage. As a result, the articulated rail has been successfully deployed and stored within 6 h each, less than the target of 8 h, by means of the three external driving mechanisms and the proposed synchronized control. In addition, the overload caused by an unexpected mismatch of the synchronized control of three driving mechanisms has also been successfully suppressed less than the rated torque by the proposed 'torque-limit control'. It is therefore concluded that the feasibility of the rail deployment and storage of the vehicle manipulator system has been demonstrated

  19. Remotely controlled large container disposal methodology

    International Nuclear Information System (INIS)

    Amir, S.J.

    1994-09-01

    Remotely Handled Large Containers (RHLC), also called drag-off boxes, have been used at the Hanford Site since the 1940s to dispose of large pieces of radioactively contaminated equipment. These containers are typically large steel-reinforced concrete boxes, which weigh as much as 40 tons. Because large quantities of high-dose waste can produce radiation levels as high as 200 mrem/hour at 200 ft, the containers are remotely handled (either lifted off the railcar by crane or dragged off with a cable). Many of the existing containers do not meet existing structural and safety design criteria and some of the transportation requirements. The drag-off method of pulling the box off the railcar using a cable and a tractor is also not considered a safe operation, especially in view of past mishaps

  20. Design of special purpose equipment - remote control dozer

    International Nuclear Information System (INIS)

    Aprameyan, K.

    1990-01-01

    Operation environment in handling hot slag, radio active material, clearing/dismantling buildings and loose rocky zones pose hazards with the operation of heavy duty vehicles. Under such hazardous environment conditions, elimination of operator becomes the prime criteria. Remote control of heavy vehicles is resorted to operate the equipment in various working conditions. Radio control systems coupled with penumatic/hydraulic actuators and proportional control logics aim total control of the equipment from a distance using hand pendants. Bharat Earth Moovers Limited has successfully developed remote control system for dozers of 200hp and 300hp. (author). 3 figs

  1. Techniques for remote maintenance of in-cell material-handling system in the HFEF/N main cell

    International Nuclear Information System (INIS)

    Tobias, D.A.; Frickey, C.A.

    1975-01-01

    Operations in the main cell of HFEF/N have required development of remote handling equipment and unique techniques for maintaining the in-cell material-handling system. Specially designed equipment is used to remove a disabled crane or electromechanical manipulator bridge from its support rails and place it on floor stands for repair or maintenance. Support areas for the main cell, such as the spray chamber and hot repair area, provide essential decontamination, repair, and staging areas for the in-cell material-handling-system equipment and tools. A combined engineering and technical effort in upgrading existing master-slave manipulators has definitely reduced the requirements for their maintenance. The cell is primarily for postirradiation examination of LMFBR materials and fuel elements

  2. Research issues in implementing remote presence in teleoperator control

    Science.gov (United States)

    Corker, K.; Mishkin, A. H.; Lyman, J.

    1981-01-01

    The concept of remote presence in telemanipulation is presented. A conceptual design of a prototype teleoperator system incorporating remote presence is described. The design is presented in functional terms, sensor, display, and control subsystem. An intermediate environment, in which the human operator is made to feel present, is explicated. The intermediate environment differs from the task environment due to the quantity and type of information presented to an operator and due to scaling factors protecting the operator from the hazards of the task environment. Potential benefits of remote presence systems, both for manipulation and for the study of human cognition and preception are discussed.

  3. An intelligent remote control system for ECEI on EAST

    Science.gov (United States)

    Chen, Dongxu; Zhu, Yilun; Zhao, Zhenling; Qu, Chengming; Liao, Wang; Xie, Jinlin; Liu, Wandong

    2017-08-01

    An intelligent remote control system based on a power distribution unit (PDU) and Arduino has been designed for the electron cyclotron emission imaging (ECEI) system on Experimental Advanced Superconducting Tokamak (EAST). This intelligent system has three major functions: ECEI system reboot, measurement region adjustment and signal amplitude optimization. The observation region of ECEI can be modified for different physics proposals by remotely tuning the optical and electronics systems. Via the remote adjustment of the attenuation level, the ECEI intermediate frequency signal amplitude can be efficiently optimized. The remote control system provides a feasible and reliable solution for the improvement of signal quality and the efficiency of the ECEI diagnostic system, which is also valuable for other diagnostic systems.

  4. Expert operator preferences in remote manipulator control systems

    International Nuclear Information System (INIS)

    Sundstrom, E.; Draper, J.V.; Fausz, A.; Woods, H.

    1995-06-01

    This report describes a survey of expert remote manipulator operators designed to identify features of control systems related to operator efficiency and comfort. It provides information for designing the control center for the Single-Shell Tank Waste Retrieval Manipulator System (TWRMS) Test Bed, described in a separate report. Research questions concerned preferred modes of control, optimum work sessions, sources of operator fatigue, importance of control system design features, and desired changes in control rooms. Participants comprised four expert remote manipulator operators at Oak Ridge National Laboratory, who individually have from 9 to 20 years of experience using teleoperators. The operators had all used rate and position control, and all preferred bilateral (force-reflecting) position control. They reported spending an average of 2.75 h in control of a teleoperator system during a typical shift. All were accustomed to working in a crew of two and alternating control and support roles in 2-h rotations in an 8-h shift. Operators reported that fatigue in using remote manipulator systems came mainly from watching TV monitors and making repetitive motions. Three of four experienced symptoms, including headaches and sore eyes, wrists, and back. Of 17 features of control rooms rated on importance, highest ratings went to comfort and support provided by the operator chair, location of controls, location of video monitors, video image clarity, types of controls, and control modes. When asked what they wanted to change, operators said work stations designed for comfort; simpler, lighter hand-controls; separate controls for each camera; better placement of remote camera; color monitors; and control room layouts that support crew interaction. Results of this small survey reinforced the importance of ergonomic factors in remote manipulation

  5. Remotely powered and controlled EAPap actuator by amplitude modulated microwaves

    International Nuclear Information System (INIS)

    Yang, Sang Yeol; Mahadeva, Suresha K; Kim, Jaehwan

    2013-01-01

    This paper reports on a remotely powered and controlled Electro-Active Paper (EAPap) actuator without onboard controller using amplitude modulated microwaves. A rectenna is a key element for microwave power transmission that converts microwaves into dc power through coupling and rectification. In this study, the concept of a remotely controlled and powered EAPap actuator is proposed by means of modulating microwaves with a control signal and demodulating it through the rectenna rectification. This concept is applied to a robust EAPap actuator, namely cellulose–polypyrrole–ionic liquid (CPIL) EAPap. Details of fabrication and characterization of the rectenna and the CPIL-EAPap actuator are explained. Also, the charge accumulation problem of the actuator is explained and resolved by connecting an additional resistor. Since this idea can eliminate the onboard controller by supplying the operating signal through modulation, a compact and lightweight actuator can be achieved, which is useful for biomimetic robots and remotely driven actuators. (technical note)

  6. Remote control of microcontroller-based infant stimulating system.

    Science.gov (United States)

    Burunkaya, M; Güler, I

    2000-04-01

    In this paper, a remote-controlled and microcontroller-based cradle is designed and constructed. This system is also called Remote Control of Microcontroller-Based Infant Stimulation System or the RECOMBIS System. Cradle is an infant stimulating system that provides relaxation and sleeping for the baby. RECOMBIS system is designed for healthy full-term newborns to provide safe infant care and provide relaxation and sleeping for the baby. A microcontroller-based electronic circuit was designed and implemented for RECOMBIS system. Electromagnets were controlled by 8-bit PIC16F84 microcontroller, which is programmed using MPASM package. The system works by entering preset values from the keyboard, or pulse code modulated radio frequency remote control system. The control of the system and the motion range were tested. The test results showed that the system provided a good performance.

  7. Remote operation and automation of the maintenance works under the radiation field

    Energy Technology Data Exchange (ETDEWEB)

    Asai, T; Koga, A; Shirasu, I; Miida, T

    1983-06-01

    More than ninety per cent of the personnel radiation exposure at the nuclear power station is attributable to the maintenance works during the plant shutdown. The maintenance robots have effectively contributed in reducing the annual inspection and refueling schedule and the personnel radiation exposure. Future prospects of robotics depend on the grade of development in robot technology and plant engineering itself to accommodate such robot tools, since plant facilities and maintenance procedure today is difficult to replace with machines due to their diversified and complex nature.

  8. Remote operation and automation of the maintenance works under the radiation field

    Energy Technology Data Exchange (ETDEWEB)

    Asai, Takashi; Koga, Akihiko; Shirasu, Isao; Miida, Toshiro [Mitsubishi Heavy Industries Ltd., Tokyo (Japan)

    1983-08-01

    More than ninety per cent of the personnel radiation exposure at the nuclear power station is attributable to the maintenence works during the plant shutdown. The maintenance robots have effectively contributed in reducing the annual inspection and refueling schedule and the personnel radiation exposure. Future prospects of robotics depend on the grade of development in robot technology and plant engineering itself to accommodate such robot tools, since plant facilities and maintenance procedure today are so difficult to replace with machines due to their deversified and complexed nature.

  9. Remote operation and automation of the maintenance works under the radiation field

    Energy Technology Data Exchange (ETDEWEB)

    Asai, Takashi; Koga, Akihiko; Shirasu, Isao; Miida, Toshiro [Mitsubishi Heavy Industries Ltd., Tokyo (Japan)

    1983-01-01

    More than ninety per cent of the personnel radiation exposure at the nuclear power station is attributable to the maintenance works during the plant shutdown. The maintenance robots have effectively contributed in reducing the annual inspection and refueling schedule and the personnel radiation exposure. Future prospects of robotics depend on the grade of development in robot technology and plant engineering itself to accommodate such robot tools, since plant facilities and maintenance procedure today is so defficult to replace with machines due to their diversified and complexed nature.

  10. Remote operation and automation of the maintenance works under the radiation field

    International Nuclear Information System (INIS)

    Asai, Takashi; Koga, Akihiko; Shirasu, Isao; Miida, Toshiro

    1983-01-01

    More than ninety per cent of the personnel radiation exposure at the nuclear power station is attributable to the maintenence works during the plant shutdown. The maintenance robots have effectively contributed in reducing the annual inspection and refueling schedule and the personnel radiation exposure. Future prospects of robotics depend on the grade of development in robot technology and plant engineering itself to accommodate such robot tools, since plant facilities and maintenance procedure today is so difficult to replace with machines due to their deversified and complexed nature. (author)

  11. Data acquisition, remote control and equipment monitoring for ISOLDE RILIS

    Energy Technology Data Exchange (ETDEWEB)

    Rossel, R.E., E-mail: ralf.erik.rossel@cern.ch [CERN, Geneva (Switzerland); Institut für Physik, Johannes Gutenberg-Universität, Mainz (Germany); Hochschule RheinMain, Fachbereich Design Informatik Medien, Wiesbaden (Germany); Fedosseev, V.N.; Marsh, B.A. [CERN, Geneva (Switzerland); Richter, D. [Hochschule RheinMain, Fachbereich Design Informatik Medien, Wiesbaden (Germany); Rothe, S. [CERN, Geneva (Switzerland); Institut für Physik, Johannes Gutenberg-Universität, Mainz (Germany); Wendt, K.D.A. [Institut für Physik, Johannes Gutenberg-Universität, Mainz (Germany)

    2013-12-15

    Highlights: • The requirements for continuous and automated RILIS operation are outlined. • Laser wavelength, power, beam position and pulse timing are continuously monitored. • A network-extended LabVIEW-based equipment operation framework was developed. • The system serves as a foundation for collaborative laser spectroscopy data acquisition. • Example applications have been successfully tested with ISOLDE experiment setups. -- Abstract: With a steadily increasing on-line operation time up to a record 3000 h in the year 2012, the Resonance Ionization Laser Ion Source (RILIS) is one of the key components of the ISOLDE on-line isotope user facility at CERN. Ion beam production using the RILIS is essential for many experiments due to the unmatched combination of ionization efficiency and selectivity. To meet the reliability requirements the RILIS is currently operated in shift duty for continuous maintenance of crucial laser parameters such as wavelength, power, beam position and timing, as well as ensuring swift intervention in case of an equipment malfunction. A recent overhaul of the RILIS included the installation of new pump lasers, commercial dye lasers and a complementary, fully solid-state titanium:sapphire laser system. The framework of the upgrade also required the setup of a network-extended, LabVIEW-based system for data acquisition, remote control and equipment monitoring, to support RILIS operators as well as ISOLDE users. The system contributes to four key aspects of RILIS operation: equipment monitoring, machine protection, automated self-reliance, and collaborative data acquisition. The overall concept, technologies used, implementation status and recent applications during the 2012 on-line operation period will be presented along with a summary of future developments.

  12. The design of remote participation platform for EAST plasma control

    Energy Technology Data Exchange (ETDEWEB)

    Yuan, Q.P., E-mail: qpyuan@ipp.ac.cn [Institute of Plasma Physics, Chinese Academy of Sciences, Hefei (China); Xiao, B.J. [Institute of Plasma Physics, Chinese Academy of Sciences, Hefei (China); University of Science & Technology of China, Hefei (China); Zhang, R.R. [Institute of Plasma Physics, Chinese Academy of Sciences, Hefei (China); Chai, W.T.; Liu, J.; Xiao, R.; Zhou, Z.C.; Pei, X.F. [Institute of Plasma Physics, Chinese Academy of Sciences, Hefei (China); University of Science & Technology of China, Hefei (China)

    2016-11-15

    Highlights: • The remote participation platform for EAST plasma control is composed of real time control service and scenario management. • The web based interface has been developed for supporting remote participation. • The functionality module has been designed and assistant tools have been developed. - Abstract: EAST has become a physics experimental platform for high parameter and steady-state long-pulse plasma operation. A new remote participation platform for EAST plasma control is designed, which is composed of gatekeeper system, web-based user interface system, discharge scenario management system, online simulation system and data interface with on-site plasma control system (PCS). The identification and access privilege of remote participator is validated by the gatekeeper system. Only authorized users can set control parameters for next shot plasma control or making discharge scenario for future shot through WebPCS which is a web-based user interface and designed based on B/S structure. The systematic architecture design and preliminary deployment of such remote platform will be presented in this paper.

  13. A proposed protocol for remote control of automated assessment devices

    International Nuclear Information System (INIS)

    Kissock, P.S.; Pritchard, D.A.

    1996-01-01

    Systems and devices that are controlled remotely are becoming more common in security systems in the US Air Force and other government agencies to provide protection of valuable assets. These systems reduce the number of needed personnel while still providing a high level of protection. However, each remotely controlled device usually has its own communication protocol. This limits the ability to change devices without changing the system that provides the communications control to the device. Sandia is pursuing a standard protocol that can be used to communicate with the different devices currently in use, or may be used in the future, in the US Air Force and other government agencies throughout the security community. Devices to be controlled include intelligent pan/tilt mounts, day/night video cameras, thermal imaging cameras, and remote data processors. Important features of this protocol include the ability to send messages of varying length, identify the sender, and more importantly, control remote data processors. This paper describes the proposed public domain protocol, features, and examples of use. The authors hope to elicit comments from security technology developers regarding format and use of remotely controlled automated assessment devices

  14. A remote telepresence robotic system for inspection and maintenance of a nuclear power plant

    International Nuclear Information System (INIS)

    Crane, C.D. III; Tulenko, J.S.

    1993-01-01

    Progress in reported in the areas of environmental hardening; database/world modeling; man-machine interface; development of the Advanced Liquid Metal Reactor (ALMR) maintenance inspection robot design; and Articulated Transporter/Manipulator System (ATMS) development

  15. CP monitoring by IR free potential probe through a remote control system

    Energy Technology Data Exchange (ETDEWEB)

    Lazzari, L. [Politecnico di Milano, Milan (Italy); Bazzoni, B. [Cescor srl, Milan (Italy); Benedetto, S. [Italgas SpA, Turin (Italy)

    2004-07-01

    This paper presents the results of field tests on measurement of true potential of pipelines by means of a IR drop free potential probe and a remote control system. The probe used is composed of a steel coupon, simulating a coating defect, and a reference electrode of Mixed Metal Oxide (MMO) titanium activated type, both embedded in an alkaline mortar. Laboratory and field tests confirmed the probe to be reliable and enable to eliminate the IR drop contribution in all conditions and especially in presence of stray current. A remote control system was tested for a reliable and continuous monitoring of CP parameters with the aim to operate CP systems in compliance with regulations and to reduce maintenance costs. The remote control system consists of Acquisition Units for continuous field data gathering, a Data Centre pilot all functions such as query, download and processing data, and an Internet web site for remote connections. Field data obtained in various situations are presented and discussed. (authors)

  16. Measuring robustness of port plug maintenance schedules in fusion remote handling

    Energy Technology Data Exchange (ETDEWEB)

    Schoen, P.W., E-mail: p.w.schoen@heemskerk-innovative.nl [Heemskerk Innovative Technology, Sassenheim (Netherlands); Thomas, J. [CCFE EURATOM/CCFE Fusion Association, Culham Science Centre, Abingdon OX14 3DB (United Kingdom); Boessenkool, H. [FOM Institute DIFFER, Association EURATOM-FOM, Partner in the Trilateral Euregio Cluster, PO Box 1207, 3430 BE Nieuwegein (Netherlands); Heemskerk, C.J.M. [Heemskerk Innovative Technology, Sassenheim (Netherlands)

    2015-12-15

    Unexpected events during maintenance operations of a fusion plant like JET or ITER may require rescheduling, suspending the execution of the current procedure to pick it up later. In this paper, we look at how the introduction of slack influences the port plug maintenance schedule robustness. We introduce a metrics to measure the robustness. Simulating disruptions we evaluate the effect on a schedule. Finally, we show how the robustness is affected when introducing different amounts of slack.

  17. Measuring robustness of port plug maintenance schedules in fusion remote handling

    International Nuclear Information System (INIS)

    Schoen, P.W.; Thomas, J.; Boessenkool, H.; Heemskerk, C.J.M.

    2015-01-01

    Unexpected events during maintenance operations of a fusion plant like JET or ITER may require rescheduling, suspending the execution of the current procedure to pick it up later. In this paper, we look at how the introduction of slack influences the port plug maintenance schedule robustness. We introduce a metrics to measure the robustness. Simulating disruptions we evaluate the effect on a schedule. Finally, we show how the robustness is affected when introducing different amounts of slack.

  18. Development of wireless vehicle remote control for fuel lid operation

    Science.gov (United States)

    Sulaiman, N.; Jadin, M. S.; Najib, M. S.; Mustafa, M.; Azmi, S. N. F.

    2018-04-01

    Nowadays, the evolution of the vehicle technology had made the vehicle especially car to be equipped with a remote control to control the operation of the locking and unlocking system of the car’s door and rear’s bonnet. However, for the fuel or petrol lid, it merely can be opened from inside the car’s cabin by handling the fuel level inside the car’s cabin to open the fuel lid. The petrol lid can be closed by pushing the lid by hand. Due to the high usage of using fuel lever to open the fuel lid when refilling the fuel, the car driver might encounter the malfunction of fuel lid (fail to open) when pushing or pulling the fuel lever. Thus, the main aim of the research is to enhance the operation of an existing car remote control where the car fuel lid can be controlled using two techniques; remote control-based and smartphone-based. The remote control is constructed using Arduino microcontroller, wireless sensors and XCTU software to set the transmitting and receiving parameters. Meanwhile, the smartphone can control the operation of the fuel lid by communicating with Arduino microcontroller which is attached to the fuel lid using Bluetooth sensor to open the petrol lid. In order to avoid the conflict of instruction between wireless systems with the existing mechanical-based system, the servo motor will be employed to release the fuel lid merely after receiving the instruction from Arduino microcontroller and smartphone. As a conclusion, the prototype of the multipurpose vehicle remote control is successfully invented, constructed and tested. The car fuel lid can be opened either using remote control or smartphone in a sequential manner. Therefore, the outcome of the project can be used to serve as an alternative solution to solve the car fuel lid problem even though the problem rarely occurred.

  19. Control and robotics remote laboratory for engineering education

    Directory of Open Access Journals (Sweden)

    Gregor Pačnik

    2005-06-01

    Full Text Available The new tools for education of engineering emerged and one of the most promising is a remote rapid control prototyping (RRCP, which is very useful also for control and robotics development in industry and in education. Examples of introductory remote control and simple robotics courses with integrated hands on experiments are presented in the paper. The aim of integration of remote hands on experiments into control and/or robotics course is to minimize the gap between the theory and practice to teach students the use of RRCP and to decrease the education costs. Developed RRCP experiments are based on MATLAB/Simulink, xPC target, custom developed embedded target

  20. Power-over-ethernet for remote measurement and control

    International Nuclear Information System (INIS)

    Behera, Rajendra Prasad; Murali, N.

    2011-01-01

    Power-Over-Ethernet (PoE) technology (IEEE standard 802.3af) allows Remote Measurement and Control in harsh environment where human access is difficult in various nuclear research fields. The terminal measurement and control unit receives power for its operation and communicates data over the same LAN cable, without needing to provide power supplies from different source. Almost all data acquisition systems require both data connectivity and a power supply. In a familiar example, telephones are powered from the telephone exchange through the same twisted pair that carries the voice. Now we can do the same thing with Ethernet devices by combining power and data. Only one set of wires is required to bring to the end measurement and control unit which will simplify installation and save space. Remote unit can be easily moved, to wherever a LAN cable can be laid with minimal disruption to the workplace. It is safer as no mains supply is required. Uninterrupted power supply can be guaranteed to the terminal unit during mains power failure. The terminal unit can be shut down and reset remotely without needing for a reset button and power switch. Simple Network Management Protocol (SNMP) can be used to monitor and control the remote unit. PoE will enable to deploy many more embedded systems in nuclear and other industry like Voice over Internet Protocol (VoIP), Security Camera, Tele-information System, Remote Access Control System, Intruder Detection System, and Tele-Medicine System, etc. (author)

  1. "O.K. Where's the Remote?" Children, Families, and Remote Control Devices.

    Science.gov (United States)

    Krendl, Kathy A.; And Others

    This paper, part of a larger study of new television technologies, examines how preschool children integrate remote control devices (RCDs) into their television viewing behavior, preschoolers' competence with and knowledge of RCDs, and the role of the RCD in shaping family viewing styles. Subjects, 50 children aged 4 to 6 years attending 3…

  2. Smart Remote for the Setup Box Using Gesture Control

    OpenAIRE

    Surepally Uday Kumar; K. Shamini

    2016-01-01

    The basic purpose of this project is to provide a means to control a set top box (capable of infrared communication), in this case Hathway using hand gestures. Thus, this system will act like a remote control for operating set top box, but this will be achieved through hand gestures instead of pushing buttons. To send and receive remote control signals, this project uses an infrared LED as Transmitter. Using an infrared receiver, an Arduino can detect the bits being sent by a remo...

  3. Intelligent control system Cellular Robotics Approach to Nuclear Plant control and maintenance

    International Nuclear Information System (INIS)

    Fukuda, Toshio; Sekiyama, Kousuke; Xue Guoqing; Ueyama, Tsuyoshi.

    1994-01-01

    This paper presents the concept of Cellular Robotic System (CEBOT) and describe the strategy of a distributed sensing, control and planning as a Cellular Robotics Approach to the Nuclear Plant control and maintenance. Decentralized System is effective in large plant and The CEBOT possesses desirable features for realization of Nuclear Plant control and maintenance because of its flexibility and adaptability. Also, as related on going research work, self-organizing manipulator and communication issues are mentioned. (author)

  4. INTOR critical issue D: maintainability. Tritium containment and personnel access vs remote maintenance, Chapter VI of the US INTOR report for Phase Two A, Part 2

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Finn, P.A.; Gohar, Y.

    1984-01-01

    The purpose of this study is to compare the benefits and costs associated with personnel access mmaintenance procedures compared to those of all-remote maintenance procedures. The INTOR Phase Two A, Part I configuration was used to make this comparison. For both approaches, capital and operating costs were considered to first order, maintenance equipment requirements were investigated, maintenance requirements common to both approaches and unique to each were identified, tritium handling requirements were outlined, and maintenance scenarios and device downtime were developed for both. In addition, estimates of person-rem exposure were made for the personnel access approach

  5. Remotely controlled working equipment and mobile systems for damage assessment

    International Nuclear Information System (INIS)

    Koehler, G.W.; Salaske, M.

    1975-01-01

    All functions of the MF3 vehicle with its variable geometry chassis were verified in accordance with specifications. Fixed price bids have now been submitted by industries on the action control system and the EMSM II manipulators. Tests of the EMSM I manipulator with supplements especially the remotely controlled application of tools, have been started. (orig.) [de

  6. Synthesis of the unmanned aerial vehicle remote control augmentation system

    International Nuclear Information System (INIS)

    Tomczyk, Andrzej

    2014-01-01

    Medium size Unmanned Aerial Vehicle (UAV) usually flies as an autonomous aircraft including automatic take-off and landing phases. However in the case of the on-board control system failure, the remote steering is using as an emergency procedure. In this reason, remote manual control of unmanned aerial vehicle is used more often during take-of and landing phases. Depends on UAV take-off mass and speed (total energy) the potential crash can be very danger for airplane and environment. So, handling qualities of UAV is important from pilot-operator point of view. In many cases the dynamic properties of remote controlling UAV are not suitable for obtaining the desired properties of the handling qualities. In this case the control augmentation system (CAS) should be applied. Because the potential failure of the on-board control system, the better solution is that the CAS algorithms are placed on the ground station computers. The method of UAV handling qualities shaping in the case of basic control system failure is presented in this paper. The main idea of this method is that UAV reaction on the operator steering signals should be similar - almost the same - as reaction of the 'ideal' remote control aircraft. The model following method was used for controller parameters calculations. The numerical example concerns the medium size MP-02A UAV applied as an aerial observer system

  7. Synthesis of the unmanned aerial vehicle remote control augmentation system

    Energy Technology Data Exchange (ETDEWEB)

    Tomczyk, Andrzej, E-mail: A.Tomczyk@prz.edu.pl [Department of Avionics and Control Systems, Faculty of Mechanical Engineering and Aeronautics, Rzeszów University of Technology, Al. Powstañców Warszawy 12, 35-959 Rzeszów (Poland)

    2014-12-10

    Medium size Unmanned Aerial Vehicle (UAV) usually flies as an autonomous aircraft including automatic take-off and landing phases. However in the case of the on-board control system failure, the remote steering is using as an emergency procedure. In this reason, remote manual control of unmanned aerial vehicle is used more often during take-of and landing phases. Depends on UAV take-off mass and speed (total energy) the potential crash can be very danger for airplane and environment. So, handling qualities of UAV is important from pilot-operator point of view. In many cases the dynamic properties of remote controlling UAV are not suitable for obtaining the desired properties of the handling qualities. In this case the control augmentation system (CAS) should be applied. Because the potential failure of the on-board control system, the better solution is that the CAS algorithms are placed on the ground station computers. The method of UAV handling qualities shaping in the case of basic control system failure is presented in this paper. The main idea of this method is that UAV reaction on the operator steering signals should be similar - almost the same - as reaction of the 'ideal' remote control aircraft. The model following method was used for controller parameters calculations. The numerical example concerns the medium size MP-02A UAV applied as an aerial observer system.

  8. Development of HWVP melter/turntable components for canyon-remote maintenance and replacement

    International Nuclear Information System (INIS)

    Siemens, D.H.; Beary, M.M.; Berger, D.N.; Heath, W.O.; Larson, D.E.

    1985-03-01

    Remote operability and maintainability of vitrification equipment were assessed under shielded-cell conditions. The equipment tested will be applied to immobilize high-level and transuranic liquid waste slurries that resulted from plutonium production for defense weapons. Equipment tested included: (1) a turntable for handling waste canisters under the melter; (2) a removable discharge cone in the melter overflow section; (3) a thermocouple jumper that extends into a shielded cell; (4) remote instrument and electrical connectors; (5) remote, mechanical, and heat transfer aspects of the melter glass overflow section; (6) a reamer to clean out plugged nozzles in the melter top; (7) a closed circuit camera to view the melter interior; and (8) a device to retrieve samples of the glass product. 14 figs

  9. Closed-circuit television and remote crane control for vitrification facilities

    International Nuclear Information System (INIS)

    Bennett, P.R.; Morrison, J.E.

    1986-01-01

    The Defense Waste Processing Facility is currently under construction at the Savannah River Plant. Within the main process cell (MPC), a 117-ton capacity bridge crane is to be installed to facilitate remote handling and processing operations. E. I. du Pont de Nemours and Company defined and PRC designed and built an operational prototype closed-circuit television (CCTV) and remote control system. Phase I of the program developed the CCTV system to prove the feasibility of a remote viewing system. The phase II program added full crane functional remote control and installed it on an existing hot canyon crane. This prototype system established the criteria for the development of the MPC crane and future crane systems. Parameters were: (a) failsafe assurance, (b) high liability, (c) ease of maintenance for dressed-out personnel, (d) rapid malfunction diagnosis, (e) ergonomics, (f) known picture orientation, and (g) audio system to monitor operational sounds. The complete system has undergone a total demonstration of its operational capabilities using simulator circuits for crane functions and is now being integrated with the crane for a full operational demonstration. The system will then be mothballed pending installation by construction personnel ready for cold startup of the plant in 1988

  10. Quantum gates via relativistic remote control

    Energy Technology Data Exchange (ETDEWEB)

    Martín-Martínez, Eduardo, E-mail: emartinm@uwaterloo.ca [Institute for Quantum Computing, University of Waterloo, Waterloo, Ontario, N2L 3G1 (Canada); Dept. Applied Math., University of Waterloo, Ontario, N2L 3G1 (Canada); Perimeter Institute for Theoretical Physics, Waterloo, Ontario N2L 2Y5 (Canada); Sutherland, Chris [Institute for Quantum Computing, University of Waterloo, Waterloo, Ontario, N2L 3G1 (Canada)

    2014-12-12

    We harness relativistic effects to gain quantum control on a stationary qubit in an optical cavity by controlling the non-inertial motion of a different probe atom. Furthermore, we show that by considering relativistic trajectories of the probe, we enhance the efficiency of the quantum control. We explore the possible use of these relativistic techniques to build 1-qubit quantum gates.

  11. Cyber security for remote monitoring and control of small reactors

    Energy Technology Data Exchange (ETDEWEB)

    Trask, D., E-mail: dave.trask@cnl.ca [Atomic Energy of Canada Limited, Chalk River, ON (Canada); Jung, C. [Canadian Nuclear Safety Commission, Ottawa, ON (Canada); MacDonald, M., E-mail: marienna.macdonald@cnl.ca [Atomic Energy of Canada Limited, Chalk River, ON (Canada)

    2014-07-01

    There is growing international interest and activity in the development of small nuclear reactor technology with a number of vendors interested in building small reactors in Canada to serve remote locations. A common theme of small reactor designs proposed for remote Canadian locations is the concept of a centrally located main control centre operating several remotely located reactors via satellite communications. This theme was echoed at a recent IAEA conference where a recommendation was made to study I&C for remotely controlled small modular reactors, including satellite links and cyber security. This paper summarizes the results of an AECL-CNSC research project to analyze satellite communication technologies used for remote monitoring and control functions in order to provide cyber security regulatory considerations. The scope of this research included a basic survey of existing satellite communications technology and its use in industrial control applications, a brief history of satellite vulnerabilities and a broad review of over 50 standards, guidelines, and regulations from recognized institutions covering safety, cyber security, and industrial communication networks including wireless communications in general. This paper concludes that satellite communications should not be arbitrarily excluded by standards or regulation from use for the remote control and monitoring of small nuclear reactors. Instead, reliance should be placed on processes that are independent of any particular technology, such as reducing risks by applying control measures and demonstrating required reliability through good design practices and testing. Ultimately, it is compliance to well-developed standards that yields the evidence to conclude whether a particular application that uses satellite communications is safe and secure. (author)

  12. Cyber security for remote monitoring and control of small reactors

    International Nuclear Information System (INIS)

    Trask, D.; Jung, C.; MacDonald, M.

    2014-01-01

    There is growing international interest and activity in the development of small nuclear reactor technology with a number of vendors interested in building small reactors in Canada to serve remote locations. A common theme of small reactor designs proposed for remote Canadian locations is the concept of a centrally located main control centre operating several remotely located reactors via satellite communications. This theme was echoed at a recent IAEA conference where a recommendation was made to study I&C for remotely controlled small modular reactors, including satellite links and cyber security. This paper summarizes the results of an AECL-CNSC research project to analyze satellite communication technologies used for remote monitoring and control functions in order to provide cyber security regulatory considerations. The scope of this research included a basic survey of existing satellite communications technology and its use in industrial control applications, a brief history of satellite vulnerabilities and a broad review of over 50 standards, guidelines, and regulations from recognized institutions covering safety, cyber security, and industrial communication networks including wireless communications in general. This paper concludes that satellite communications should not be arbitrarily excluded by standards or regulation from use for the remote control and monitoring of small nuclear reactors. Instead, reliance should be placed on processes that are independent of any particular technology, such as reducing risks by applying control measures and demonstrating required reliability through good design practices and testing. Ultimately, it is compliance to well-developed standards that yields the evidence to conclude whether a particular application that uses satellite communications is safe and secure. (author)

  13. Conceptual design of nuclear fusion power reactor DREAM. Reactor structures and remote maintenance

    International Nuclear Information System (INIS)

    Nishio, Satoshi; Seki, Yasushi; Ueda, Shuzo; Kurihara, Ryoichi; Adachi, Junichi; Yamazaki, Seiichiro; Hashimoto, Toshiyuki.

    1997-01-01

    Nuclear fusion reactors are required to be able to compete another energy sources in economy, reliability, safety and environmental integrity for commercial use. In the DREAM (DRastically EAsy Maintenance) reactor, a very low activated material of SiC/SiC composite has been introduced for the structural material, a reactor configuration for very easy maintenance and the helium gas of a high temperature for the cooling system, and hence DREAM has been proven to be very attractively as the commercial power reactor due to the high availability and efficiency of the plant and minimization of radioactive wastes. (author)

  14. Dose management: weighing up the costs and benefits of remote maintenance

    International Nuclear Information System (INIS)

    Lefaure, C.; Lochard, J.; Blain, A.

    1989-01-01

    Reducing occupational exposure during maintenance, while at the same time preserving the economic viability of nuclear power plants, will be one of the major challenges to be faced by the industry over the next decade. Increased use of robotics is a possibility. The costs and benefits are examined in this paper. (author)

  15. Development of Automatic Remote Exposure Controller for Gamma Radiography

    International Nuclear Information System (INIS)

    Joo, Gwang Tae; Shin, Jin Seong; Kim, Dong Eun; Song, Jung Ho; Choo, Seung Hwan; Chang, Hong Keun

    2002-01-01

    Recently, gamma radiographic equipment have been used about 1,000 sets manually and operated by about 2,500 persons in Korea. In order for a radiography to work effectively with avoiding any hazard of the high level radiation from the source, many field workers have expected developing a wireless automatic remote exposure controller. The KlTCO research team has developed an automatic remote exposure controller that can regulate the speed of 0.4∼1.2m/s by BLDC motor of 24V 200W which has output of 54 kgf·, suitable torque and safety factor for the work. And the developed automatic remote exposure controller can control rpm of motor, pigtail position by photo-sensor and exposure time by timer to RF sensor. Thus, the developed equipment is expected that the unit can be used in many practical applications with benefits in economical advantage to combine the use of both automatic and manual type because attachment is possible existent manual remote exposure controller, AC and DC combined use

  16. Development of remote control software for multiformat test signal generator

    Directory of Open Access Journals (Sweden)

    Gao Yang

    2017-01-01

    Full Text Available The multi format test signal generator mentioned in this paper is the video signal generator named TG8000 produced by Tektronix Company. I will introduce the function about remote control for signal generator, how to connect the computer to the instrument, and how to remote control. My topic uses my computer to connect the instrument through the 10/100/1000 BASE-T port on the rear panel of TG8000. Then I write program to transmit SCPI (Standard Commands for Programmable Instruments to control TG8000. The application is running on the Windows operating system, the programming language is C#, development environment is Microsoft Visual Studio 2010, using the TCP/IP protocol based on Socket. And the method of remote control refers to the application called TGSetup which is developed by Tektronix Company. This paper includes a brief summary of the basic principle, and introduce for details about the process of remote control software development, and how to use my software. In the end, I will talk about the advantages of my software compared with another one.

  17. Remote control and data processing for measurement of radiation dose

    International Nuclear Information System (INIS)

    Zhou Yu; Luo Yisheng; Guo Yong; Ji Gang; Wang Xinggong; Zhang Hong; Zhang Wenzhong

    2004-01-01

    Objective: To protect the workers from the reactor radiation and to improve the accuracy and efficiency of neutron dose measurement. Methods: With the application of remote control technology, a remote control and automatic measurement system for radiation dose measurement(especially for neutron dose) was set up. A Model 6517A electrometer was operated all automatically over RS-232 serial interface using SCPI commands with a computer. Results: The workers could stay far from the reactor and be able to control the portable computer in site though internet or LAN and then to control the 6517A electrometer to implement the dose measurement. After the measurement, the data were transferred to the remote computer near the workers and shared by many experts at the first time through the net. Conclusion: This is the first time that the remote control technology is applied in radiation dose measurement, which has so far been considered can only be performed at a near place. This new system can meet the need of neutron radiobiology researches as well as of the safety and health of the workers. (author)

  18. Instrument Remote Control via the Astronomical Instrument Markup Language

    Science.gov (United States)

    Sall, Ken; Ames, Troy; Warsaw, Craig; Koons, Lisa; Shafer, Richard

    1998-01-01

    The Instrument Remote Control (IRC) project ongoing at NASA's Goddard Space Flight Center's (GSFC) Information Systems Center (ISC) supports NASA's mission by defining an adaptive intranet-based framework that provides robust interactive and distributed control and monitoring of remote instruments. An astronomical IRC architecture that combines the platform-independent processing capabilities of Java with the power of Extensible Markup Language (XML) to express hierarchical data in an equally platform-independent, as well as human readable manner, has been developed. This architecture is implemented using a variety of XML support tools and Application Programming Interfaces (API) written in Java. IRC will enable trusted astronomers from around the world to easily access infrared instruments (e.g., telescopes, cameras, and spectrometers) located in remote, inhospitable environments, such as the South Pole, a high Chilean mountaintop, or an airborne observatory aboard a Boeing 747. Using IRC's frameworks, an astronomer or other scientist can easily define the type of onboard instrument, control the instrument remotely, and return monitoring data all through the intranet. The Astronomical Instrument Markup Language (AIML) is the first implementation of the more general Instrument Markup Language (IML). The key aspects of our approach to instrument description and control applies to many domains, from medical instruments to machine assembly lines. The concepts behind AIML apply equally well to the description and control of instruments in general. IRC enables us to apply our techniques to several instruments, preferably from different observatories.

  19. The remote maintenance of mechanically attached first wall armour tiles in NET

    International Nuclear Information System (INIS)

    Reeve, T.; Shaw, R.; Suppan, A.; Haferkamp, B.

    1991-01-01

    Protection of a substantial proportion of the NET First Wall (FW) with low-Z armour is envisaged for at least the early operating period of the machine. This armour will take the form of carbon tiles directly attached to the FW. Complete coverage of the FW will require the installation of 20 000-40 000 tiles. The uncertainties existing in FW operating conditions make it difficult to predict the lifetime of the armour components. However, based on present experience, a number of component failures is to be expected in addition to the general wear by plasma erosion. Bearing in mind the hostile environment within the machine, the remote maintainability of these components is thus of fundamental importance and has strongly influenced their design. Mechanical attachment is considered to be the only viable approach for remotely maintainable armour tiles. A series of tools for mounting and demounting such tiles is currently under development at KfK, Karlsruhe. Handling trials are being carried out on a local FW mock-up to optimise the tile attachment designs for efficient remote handling, to provide input to the overall system design and to facilitate the progressive evolution of effective remote handling tools. Such, tools will subsequently be tested in conjunction with The NET Articulated Boom prototype articulated boom transporter to prove their fitness for purpose. The paper reports the current status of this work and outlines the design and principles of operation of the tools developed. The results and conclusions of the investigations to date, including any practical modifications considered necessary to either the original tile attachment arrangements or the preliminary tool designs, are presented. The philosophy behind the attachment and detachment procedures envisaged is also described. (orig.)

  20. Performance-based maintenance of gas turbines for reliable control of degraded power systems

    Science.gov (United States)

    Mo, Huadong; Sansavini, Giovanni; Xie, Min

    2018-03-01

    Maintenance actions are necessary for ensuring proper operations of control systems under component degradation. However, current condition-based maintenance (CBM) models based on component health indices are not suitable for degraded control systems. Indeed, failures of control systems are only determined by the controller outputs, and the feedback mechanism compensates the control performance loss caused by the component deterioration. Thus, control systems may still operate normally even if the component health indices exceed failure thresholds. This work investigates the CBM model of control systems and employs the reduced control performance as a direct degradation measure for deciding maintenance activities. The reduced control performance depends on the underlying component degradation modelled as a Wiener process and the feedback mechanism. To this aim, the controller features are quantified by developing a dynamic and stochastic control block diagram-based simulation model, consisting of the degraded components and the control mechanism. At each inspection, the system receives a maintenance action if the control performance deterioration exceeds its preventive-maintenance or failure thresholds. Inspired by realistic cases, the component degradation model considers random start time and unit-to-unit variability. The cost analysis of maintenance model is conducted via Monte Carlo simulation. Optimal maintenance strategies are investigated to minimize the expected maintenance costs, which is a direct consequence of the control performance. The proposed framework is able to design preventive maintenance actions on a gas power plant, to ensuring required load frequency control performance against a sudden load increase. The optimization results identify the trade-off between system downtime and maintenance costs as a function of preventive maintenance thresholds and inspection frequency. Finally, the control performance-based maintenance model can reduce

  1. Development of remote control integrator system on Tokamak

    International Nuclear Information System (INIS)

    Wu Yichun; Wang Lingzhi; Shu Shuangbao

    2014-01-01

    In order to meet with the requirement of electromagnetic diagnosis to the J-TEXT Tokamak, a remote control integrator system was developed. With modular design method, the integrator system is composed of the integrator cards, a control card, a linear power card and the BNC interface cards, and it uses the PC control soft- ware to conduct network control. An integrator system provides 32 integrator channels, and all integral channels have four kinds of integral time constants for remote selection and provide three kinds of integrator running control methods. According to laboratory and J-TEXT field testing, it shows that the output voltage range is -10-10 V, output noise is not more than 5 mV, and for the four kinds of integral time constants, the integral output drifts are all less than 5 mV within 100 s for each integrator channel. (authors)

  2. Remote Control of a Mobile Robot for Indoor Patrol

    Directory of Open Access Journals (Sweden)

    Shih-Yao Juang

    2016-03-01

    Full Text Available This study applies smartphone, Bluetooth, and Wi-Fi wireless network to control a wheeled mobile robot (WMR remotely. The first part of this study demonstrates that the WMR can be controlled manually by a smartphone. The smartphone can remotely control the WMR for forward, backward, left-turn, and right-turn operations. The second part of this article presents object tracking. The WMR can follow a moving object through the use of image processing for object tracking and distance detection. In the third part, infrared sensor and fuzzy system algorithms are integrated into the control scheme. Through wall-following and obstacle-avoidance control, the WMR can successfully perform indoor patrol.

  3. A graphics based remote handling control system

    International Nuclear Information System (INIS)

    Leinemann, K.

    1984-08-01

    A control and simulation system with an interactive graphic man-machine interface is proposed for the articulated boom in JET. The system shall support 1. the study of boom movements in the planning phase, 2. the training of operators by appropriate simulations, 3. the programming of boom movements, and 4. the on-line control of the boom. A combination of computer graphic display and TV-images is proposed for providing optimum recognition of the actual situation and for echoing to the operator actions. (orig.) [de

  4. VME-based remote instrument control without ground loops

    CERN Document Server

    Belleman, J; González, J L

    1997-01-01

    New electronics has been developed for the remote control of the pick-up electrodes at the CERN Proton Synchrotron (PS). Communication between VME-based control computers and remote equipment is via full duplex point-to-point digital data links. Data are sent and received in serial format over simple twisted pairs at a rate of 1 Mbit/s, for distances of up to 300 m. Coupling transformers are used to avoid ground loops. The link hardware consists of a general-purpose VME-module, the 'TRX' (transceiver), containing four FIFO-buffered communication channels, and a dedicated control card for each remote station. Remote transceiver electronics is simple enough not to require micro-controllers or processors. Currently, some sixty pick-up stations of various types, all over the PS Complex (accelerators and associated beam transfer lines) are equipped with the new system. Even though the TRX was designed primarily for communication with pick-up electronics, it could also be used for other purposes, for example to for...

  5. A Flexible and Configurable Architecture for Automatic Control Remote Laboratories

    Science.gov (United States)

    Kalúz, Martin; García-Zubía, Javier; Fikar, Miroslav; Cirka, Luboš

    2015-01-01

    In this paper, we propose a novel approach in hardware and software architecture design for implementation of remote laboratories for automatic control. In our contribution, we show the solution with flexible connectivity at back-end, providing features of multipurpose usage with different types of experimental devices, and fully configurable…

  6. 47 CFR 78.51 - Remote control operation.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 4 2010-10-01 2010-10-01 false Remote control operation. 78.51 Section 78.51 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES CABLE TELEVISION RELAY... shall also be equipped with suitable devices for observing the overall characteristics of the...

  7. Remote-controlled afterloading for intracavitary brachytherapy in gynecological carcinomas

    International Nuclear Information System (INIS)

    Rotte, K.

    1983-01-01

    Classical radiotherapy is gradually being replaced by remote-controlled afterloading procedures in the intracavitary treatment of tumors found during gynecological examination. These new procedures practically eliminate the exposure of the clinic staff to radiation. The possibilities of this new method are discussed with regard to the physics and biology of radiation. Our own results with this new method are reported. (orig.)

  8. Remote Voltage Control Using the Holomorphic Embedding Load Flow Method

    DEFF Research Database (Denmark)

    Liu, Chengxi; Qin, Nan; Sun, Kai

    2018-01-01

    such that the approach can remotely control the voltage magnitudes of desired buses. The proposed approach is compared with a conventional Newton-Raphson approach by study cases on the IEEE New England 39-bus system. The results show that the proposed approach achieves a larger convergence region....

  9. Simulation of CIFF (Centralized IFF) remote control displays

    Science.gov (United States)

    Tucker, D. L.; Leibowitz, L. M.

    1986-06-01

    This report presents the software simulation of the Remote-Control-Display (RCS) proposed to be used in the Centralized IFF (CIFF) system. A description of the simulation programs along with simulated menu formats are presented. A sample listing of the simulation programs and a brief description of the program operation are also included.

  10. Challenges for remote monitoring and control of small reactors

    Energy Technology Data Exchange (ETDEWEB)

    Trask, D., E-mail: traskd@aecl.ca [Atomic Energy of Canada Limited, Fredericton, New Brunswick (Canada)

    2013-07-01

    This paper considers a model for small, unmanned, remotely located reactors and discusses the ensuing cyber security and operational challenges for monitoring and control and how these challenges might be overcome through some of AECL's research initiatives and experience. (author)

  11. Medical Equipment Tele- and Condition-Based Maintenance with Enhanced Remote Diagnostic Access (RDA) and Computer Vision

    Science.gov (United States)

    2010-04-01

    failing to comply with a collection of information if it does not display a currently valid OMB control number. 1. REPORT DATE APR 2010 2. REPORT...The second is a ‘mechanical’ part that is controlled by circuit boards and is accessible by the technician via the serial console and running...was the use of conventional remote access solution designed for telecommuters or teleworkers in the Information Technology (IT) world, such as a

  12. Remote maintenance of in-vessel components in Tokamak Fusion Test Reactor

    International Nuclear Information System (INIS)

    Loesser, G.D.; Heitzenroeder, P.; Kungl, D.; Dylla, H.F.; Cerdan, G.

    1990-01-01

    The Tokamak Fusion Test Reactor (TFTR) will generate a total of 3 x 10 21 neutrons during its planned D-T operational period. A maintenance manipulator has been designed and tested to minimize personnel radiation during in-vessel maintenance activities. Its functions include visual inspection, first-wall tile replacement, cleaning, diagnostics calibrations and leak detection. To meet these objectives, the TFTR maintenance manipulator is required to be operable in the TFTR high vacuum environment, typically -8 torr, ( -6 Pa). Geometrically, the manipulator must extend 180 0 in either direction around the torus to assure complete coverage of the vessel first-wall. The manipulator consists of a movable carriage, and movable articulated link sections which are driven by electrical actuators. The boom has vertical load capacity of 455 kg and lateral load capacity of 46 kg. The boom can either be fitted with a general inspection arm or dextrous slave arms. The general inspection arm is designed to hold the leak detector and an inspection camera; it is capable of rotation along two axes and has a linkage system which permits motion normal to the vacuum vessel wall. All systems except the dextrous slave arms are operable in a vacuum. (author)

  13. Remote Control of an Inverted Pendulum System for Intelligent Control Education

    Directory of Open Access Journals (Sweden)

    Seul Jung

    2011-08-01

    Full Text Available This paper presents a remote control task of an inverted pendulum system for intelligent control education. The inverted pendulum moving on the guided rail is required to maintain balancing while it follows the desired trajectory commanded remotely by a joystick operated by a user. Position commands for the inverted pendulum system are given by a joystick through the network. The inverted pendulum system is controlled by a neural network control method. The corresponding control results are confirmed through experimental studies.

  14. Remotely controlled inspection and handling systems for decommissioning tasks in nuclear facilities

    International Nuclear Information System (INIS)

    Schreck, G.; Bach, W.; Haferkamp, H.

    1993-01-01

    The Institut fur Werkstoffkunde at the University of Hanover has recently developed three remotely controlled systems for different underwater inspection and dismantling tasks. ODIN I is a tool guiding device, particularly being designed for the dismantling of the steam dryer housing of the KRB A power plant at Gundremmingen, Germany. After being approved by the licencing organization TUEV Bayern, hot operation started in November 1992. The seven axes remotely controlled handling system ZEUS, consisting of a three translatory axes guiding machine and a tool handling device with four rotatory axes, has been developed for the demonstration of underwater plasma arc cutting of spherical metallic components with great wall thicknesses. A specially designed twin sensor system and a modular torch, exchanged by means of a remote controlled tool changing device, will be used for different complex cutting tasks. FAUST, an autonomous, freediving underwater vehicle, was designed for complex inspection, maintenance and dismantling tasks. It is equipped with two video cameras, an ultrasonic and a radiologic sensor and a small plasma torch. A gripper and a subsidiary vehicle for inspection may be attached. (author)

  15. Transfusion management using a remote-controlled, automated blood storage.

    Science.gov (United States)

    Pagliaro, Pasqualepaolo; Turdo, Rosalia

    2008-04-01

    Generally, the safety of transfusion terapies for patients depends in part on the distribution of the blood products. The prevention of adverse events can be aided by technological means, which, besides improving the traceability of the process, make errors less likely. In this context, the latest frontier in automation and computerisation is the remote-controlled, automated refrigerator for blood storage. Computer cross-matching is an efficient and safe method for assigning blood components, based on Information Technology applied to typing and screening. This method can be extended to the management of an automated blood refrigerator, the programme of which is interfaced with the Transfusion Service's information system. The connection we made in our Service between EmoNet and Hemosafe enables real-time, remote-controlled management of the following aspects of blood component distribution: a) release of autologous and allogeneic units already allocated to a patient, b) release of available units, which can be allocated by remote-control to known patients, in the presence of a valid computer cross-match, c) release of O-negative units of blood for emergencies. Our system combines an information database, which enables computer cross-matching, with an automated refrigerator for blood storage with controlled access managed remotely by the Transfusion Service. The effectiveness and safety of the system were validated during the 4 months of its routine use in the Transfusion Service's outpatient department. The safety and efficiency of the distribution of blood products can and must be increased by the use of technological innovations. With the EmoNet/Hemosafe system, the responsibility for the remote-controlled distribution of red blood cell concentrates remains with the chief of the Transfusion Services, through the use of automated computer procedures and supported by continuous training of technicians and nursing staff.

  16. Proceedings of the third international conference on CANDU maintenance

    International Nuclear Information System (INIS)

    1995-01-01

    The third international conference on Candu maintenance included sessions on the following topics: predictive maintenance, reliability improvements, steam generator monitoring, tools and instrumentation, valve performance, fuel channel inspection and maintenance, steam generator maintenance, environmental qualification, predictive maintenance, instrumentation and control, steam generator cleaning, decontamination and radiation protection, inspection techniques, maintenance program strategies and valve packing experience, remote tooling/ robotics and fuel handling. The individual papers have been abstracted separately

  17. Proceedings of the third international conference on CANDU maintenance

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-31

    The third international conference on Candu maintenance included sessions on the following topics: predictive maintenance, reliability improvements, steam generator monitoring, tools and instrumentation, valve performance, fuel channel inspection and maintenance, steam generator maintenance, environmental qualification, predictive maintenance, instrumentation and control, steam generator cleaning, decontamination and radiation protection, inspection techniques, maintenance program strategies and valve packing experience, remote tooling/ robotics and fuel handling. The individual papers have been abstracted separately.

  18. Modernization Of Electrical Installation By Using Wireless Remote Control

    Directory of Open Access Journals (Sweden)

    Mawlood M Al – Hamad

    2013-05-01

    Full Text Available Great benefits can be achieved by using wireless remote control in electrical wiring systems of buildings.     Probably the main advantage of this application is the drastic saving in wiring installations, which in turn will give higher reliability, safety and economy.     The idea of this application can be summarized in the following explanation. '' Instead off connecting each point of electrical system to individual switch by wires, a remote receiver can be situated in a place near to the point. The transmitter is used to operate the point remotely. The mains are connected to the receiver which will connect or disconnect the load as required. Many points can be connected to one receiver and can be operated by one or more transmitter.

  19. Development of plant maintenance systems

    International Nuclear Information System (INIS)

    Tomita, Jinji; Ike, Masae; Nakayama, Kenji; Kato, Hisatomo

    1989-01-01

    Toshiba is making active efforts for the continuing improvement of reliability and maintainability of operating nuclear power plants. As a part of these efforts, the company has developed new maintenance administration systems, diagnostic monitoring facilities for plant equipments, computer-aided expert systems, and remote-controlled machines for maintenance work. The maintenance administration systems provide efficient work plans and data acquisition capabilities for the management of personnel and equipments involved in nuclear power plant maintenance. The plant diagnostic facilities monitor and diagnose plant conditions for preventive maintenance, as well as enabling rapid countermeasures to be carried out should they be required. Expert systems utilizing artificial intelligence (AI) technology are also employed. The newly developed remote-controlled machines are useful tools for the maintenance inspection of equipment which can not be easily accessed. (author)

  20. Plasma density remote control system of experimental advanced superconductive tokamak

    International Nuclear Information System (INIS)

    Zhang Mingxin; Luo Jiarong; Li Guiming; Wang Hua; Zhao Dazheng; Xu Congdong

    2007-01-01

    In Tokamak experiments, experimental data and information on the density control are stored in the local computer system. Therefore, the researchers have to be in the control room for getting the data. Plasma Density Remote Control System (DRCS), which is implemented by encapsulating the business logic on the client in the B/S module, conducts the complicated science computation and realizes the synchronization with the experimental process on the client. At the same time, Web Services and Data File Services are deployed for the data exchange. It is proved in the experiments that DRCS not only meets the requirements for the remote control, but also shows an enhanced capability on the data transmission. (authors)

  1. THE ARCHITECTURE OF THE REMOTE CONTROL SYSTEM OF ROBOTICS OBJECTS

    Directory of Open Access Journals (Sweden)

    S.V. Shavetov

    2014-03-01

    Full Text Available The paper deals with the architecture for the universal remote control system of robotics objects over the Internet global network. Control objects are assumed to be located at a considerable distance from a reference device or end-users. An overview of studies on the subject matter of remote control of technical objects is given. A structure chart of the architecture demonstrating the system usage in practice is suggested. Server software is considered that makes it possible to work with technical objects connected to the server as with a serial port and organize a stable tunnel connection between the controlled object and the end-user. The proposed architecture has been successfully tested on mobile robots Parallax Boe-Bot and Lego Mindstorms NXT. Experimental data about values of time delays are given demonstrating the effectiveness of the considered architecture.

  2. Applying virtual reality to remote control of mobile robot

    Directory of Open Access Journals (Sweden)

    Chen Chin-Shan

    2017-01-01

    Full Text Available The purpose of this research is based on virtual reality to assisted pick and place tasks. Virtual reality can be utilized to control remote robot for pick and place element. The operator monitored and controlled the situation information of working site by Human Machine Interface. Therefore, we worked in harsh or dangerous environments that thing can be avoided. The procedure to operate mobile robot in virtual reality describes as follow: An experiment site with really experimental equipment is first established. Then, the experimental equipment and scene modeling are input to virtual reality for establishing a environment similar to the reality. Finally, the remote mobile robot is controlled to operate pick and place tasks through wireless communication by the object operation in virtual reality. The robot consists of a movable robot platform and robotic arm. The virtual reality is constructed by EON software; the Human Machine Interface is established by Visual Basic. The wireless connection is equipped the wireless Bluetooth, which is set the PC and PLC controller. With experimental tests to verify the robot in virtual reality and the wireless remote control, the robot could be operated and controlled to successfully complete pick and place tasks in reality by Human Machine Interface.

  3. Maintenance quality surveillance for nuclear reactor instrument and control systems

    International Nuclear Information System (INIS)

    Clement, T.M.

    1976-01-01

    A description is given of a formal program of mandatory testing and inspection for assurance of reliability at the N-reactor. The techniques and procedures are called Equipment Maintenance Standards (EMS) and cover the nuclear plant systems which affect nuclear safety, environmental control, continuity of operation and reactor life. The scope of the program is such that all electrical, chemical, mechanical, and nuclear devices with interconnecting circuitry, linkages, and piping are functionally checked and/or inspected from sensors through actuating media necessary for carrying out the defined functions under startup, operating, and shutdown conditions and also under any credible accident condition. Records are kept of the AS FOUND results of the tests and inspections along with adjustments and repairs required to correct any out-of-limits conditions found. These records are accumulated and are used as a source for quantitative reliability information and for evaluating wear-out or design problems

  4. Designing communication and remote controlling of virtual instrument network system

    Science.gov (United States)

    Lei, Lin; Wang, Houjun; Zhou, Xue; Zhou, Wenjian

    2005-01-01

    In this paper, a virtual instrument network through the LAN and finally remote control of virtual instruments is realized based on virtual instrument and LabWindows/CVI software platform. The virtual instrument network system is made up of three subsystems. There are server subsystem, telnet client subsystem and local instrument control subsystem. This paper introduced virtual instrument network structure in detail based on LabWindows. Application procedure design of virtual instrument network communication, the Client/the programming mode of the server, remote PC and server communication far realizing, the control power of the workstation is transmitted, server program and so on essential technical were introduced. And virtual instruments network may connect to entire Internet on. Above-mentioned technology, through measuring the application in the electronic measurement virtual instrument network that is already built up, has verified the actual using value of the technology. Experiment and application validate that this design is resultful.

  5. Designing communication and remote controlling of virtual instrument network system

    International Nuclear Information System (INIS)

    Lei Lin; Wang Houjun; Zhou Xue; Zhou Wenjian

    2005-01-01

    In this paper, a virtual instrument network through the LAN and finally remote control of virtual instruments is realized based on virtual instrument and LabWindows/CVI software platform. The virtual instrument network system is made up of three subsystems. There are server subsystem, telnet client subsystem and local instrument control subsystem. This paper introduced virtual instrument network structure in detail based on LabWindows. Application procedure design of virtual instrument network communication, the Client/the programming mode of the server, remote PC and server communication far realizing, the control power of the workstation is transmitted, server program and so on essential technical were introduced. And virtual instruments network may connect to entire Internet on. Above-mentioned technology, through measuring the application in the electronic measurement virtual instrument network that is already built up, has verified the actual using value of the technology. Experiment and application validate that this design is resultful

  6. Remote network control plasma diagnostic system for Tokamak T-10

    International Nuclear Information System (INIS)

    Troynov, V I; Zimin, A M; Krupin, V A; Notkin, G E; Nurgaliev, M R

    2016-01-01

    The parameters of molecular plasma in closed magnetic trap is studied in this paper. Using the system of molecular diagnostics, which was designed by the authors on the «Tokamak T-10» facility, the radiation of hydrogen isotopes at the plasma edge is investigated. The scheme of optical radiation registration within visible spectrum is described. For visualization, identification and processing of registered molecular spectra a new software is developed using MatLab environment. The software also includes electronic atlas of electronic-vibrational-rotational transitions for molecules of protium and deuterium. To register radiation from limiter cross-section a network control system is designed using the means of the Internet/Intranet. Remote control system diagram and methods are given. The examples of web-interfaces for working out equipment control scenarios and viewing of results are provided. After test run in Intranet, the remote diagnostic system will be accessible through Internet. (paper)

  7. The Fermilab CMTF cryogenic distribution remote control system

    Energy Technology Data Exchange (ETDEWEB)

    Pei, L.; Theilacker, J.; Klebaner, A.; Martinez, A.; Bossert, R. [Fermi National Accelerator Laboratory Batavia, IL, 60510 (United States)

    2014-01-29

    The Cryomodule Test Facility (CMTF) is able to provide the necessary test bed for measuring the performance of Superconducting Radio Frequency (SRF) cavities in a cryomodule (CM). The CMTF have seven 300 KW screw compressors, two liquid helium refrigerators, and two Cryomodule Test Stands (CMTS). CMTS1 is designed for 1.3 GHz cryomodule operating in a pulsed mode (PM) and CMTS2 is for cryomodule operating in Half-Wave (HW) and Continuous Wave (CW) mode. Based on the design requirement, each subsystem has to be far away from each other and be placed in distant locations. Therefore choosing Siemens Process Control System 7-400, DL205 PLC, Synoptic and Fermilab ACNET are the ideal choices for CMTF cryogenic distribution real-time remote control system. This paper presents a method which has been successfully used by many Fermilab distribution cryogenic real-time remote control systems.

  8. PLC based control system and maintenance activities at NCAR, Bilaspur

    International Nuclear Information System (INIS)

    Dewangan, Jaidev; Trivedi, T.; Patel, Shiv P.; Malik, C.; Kumar, Rakesh; Gupta, Santosh Kumar; Bajpai, P.K.

    2015-01-01

    A 3.0 MV high current low energy Pelletron Accelerator facility (Model 9SDH-4, NEC, USA) with TORUIS (ion source for H + and He 2+ beam current H + ion ∼ 50μA @ 6 MeV, He 2+ at ∼ 10μA) and SNICS-II ion source for heavy ions has been commissioned as 'National Centre for Accelerator Based Research' in the Department of Pure and Applied Physics, Guru Ghasidas Vishwavidyalaya. In this paper, we detail out the control system developed and implemented at NCAR. The basic idea of controlling the machine is by providing the output signal through PLC to ACPC of accelerator using user interface points provided by the manufacturer. The PLC based system generates output signal once it receives the feedback signals from search and secure switches, door lock switches and scram switches interlocked with PLC. The output is controlled by ladder logic and is activated only when all the radiation monitors are in healthy state and outside radiations monitor having low radiation level. The details of control system and maintenance activities will be discussed in the paper

  9. Conceptual design of Remote Control System for EAST tokamak

    International Nuclear Information System (INIS)

    Sun, X.Y.; Wang, F.; Wang, Y.; Li, S.

    2014-01-01

    Highlights: • A new design conception for remote control for EAST tokamak is proposed. • Rich Internet application (RIA) was selected to implement the user interface. • Some security mechanism was used to fulfill security requirement. - Abstract: The international collaboration becomes popular in tokamak research like in many other fields of science, because the experiment facilities become larger and more expensive. The traditional On-site collaboration Model that has to spend much money and time on international travel is not fit for the more frequent international collaboration. The Remote Control System (RCS), as an extension of the Central Control System for the EAST tokamak, is designed to provide an efficient and economical way to international collaboration. As a remote user interface, the RCS must integrate with the Central Control System for EAST tokamak to perform discharge control function. This paper presents a design concept delineating a few key technical issues and addressing all significant details in the system architecture design. With the aim of satisfying system requirements, the RCS will select rich Internet application (RIA) as a user interface, Java as a back-end service and Secure Socket Layer Virtual Private Network (SSL VPN) for securable Internet communication

  10. Conceptual design of Remote Control System for EAST tokamak

    Energy Technology Data Exchange (ETDEWEB)

    Sun, X.Y., E-mail: xysun@ipp.ac.cn; Wang, F.; Wang, Y.; Li, S.

    2014-05-15

    Highlights: • A new design conception for remote control for EAST tokamak is proposed. • Rich Internet application (RIA) was selected to implement the user interface. • Some security mechanism was used to fulfill security requirement. - Abstract: The international collaboration becomes popular in tokamak research like in many other fields of science, because the experiment facilities become larger and more expensive. The traditional On-site collaboration Model that has to spend much money and time on international travel is not fit for the more frequent international collaboration. The Remote Control System (RCS), as an extension of the Central Control System for the EAST tokamak, is designed to provide an efficient and economical way to international collaboration. As a remote user interface, the RCS must integrate with the Central Control System for EAST tokamak to perform discharge control function. This paper presents a design concept delineating a few key technical issues and addressing all significant details in the system architecture design. With the aim of satisfying system requirements, the RCS will select rich Internet application (RIA) as a user interface, Java as a back-end service and Secure Socket Layer Virtual Private Network (SSL VPN) for securable Internet communication.

  11. Remote-controlled vision-guided mobile robot system

    Science.gov (United States)

    Ande, Raymond; Samu, Tayib; Hall, Ernest L.

    1997-09-01

    Automated guided vehicles (AGVs) have many potential applications in manufacturing, medicine, space and defense. The purpose of this paper is to describe exploratory research on the design of the remote controlled emergency stop and vision systems for an autonomous mobile robot. The remote control provides human supervision and emergency stop capabilities for the autonomous vehicle. The vision guidance provides automatic operation. A mobile robot test-bed has been constructed using a golf cart base. The mobile robot (Bearcat) was built for the Association for Unmanned Vehicle Systems (AUVS) 1997 competition. The mobile robot has full speed control with guidance provided by a vision system and an obstacle avoidance system using ultrasonic sensors systems. Vision guidance is accomplished using two CCD cameras with zoom lenses. The vision data is processed by a high speed tracking device, communicating with the computer the X, Y coordinates of blobs along the lane markers. The system also has three emergency stop switches and a remote controlled emergency stop switch that can disable the traction motor and set the brake. Testing of these systems has been done in the lab as well as on an outside test track with positive results that show that at five mph the vehicle can follow a line and at the same time avoid obstacles.

  12. Configuration control during maintenance of safety related equipment

    International Nuclear Information System (INIS)

    Irish, C.S.

    2001-01-01

    Possibly the most important aspect of performing maintenance of safety related equipment is maintaining the component's original design basis. Assuring that the repaired item will perform the same safety function within the original performance and equipment qualification parameters is commonly referred to as configuration control. Maintaining configuration control of a technologically current well documented item is easy. Unfortunately, this does not describe most safety related items requiring maintenance within the global nuclear industry. Items such as motors, transformers, metal clad switchgear (low and medium voltage circuit breakers), refrigeration compressors, and electronic components (i.e. circuit boards, power supplies, regulators, etc.) which routinely require repair have been in service for twenty plus years. As a result, finding replacement parts and or material to repair the items to the original condition is becoming more and more difficult. An added difficulty is the lack of original technical documentation available on the item which is being repaired. The lack of technical documentation makes it difficult to identify replacement material and parts when the original part or material is not available. The lack of documentation also makes it difficult to test the repaired item to make sure that the original configuration has been maintained after the repair. The presentation will discuss the details of repairing various items including motors, metal clad switchgear, refrigeration compressors and power supplies and the controls which are necessary to maintain the configuration of the original item. The discussion will include the Quality Assurance and engineering necessary to identify and evaluate replacement material and parts necessary to perform repairs on safety related equipment when the original material or part is not available. Examples of repairs which required different parts or materials than the original to be used in the repair will be

  13. Configuration control during maintenance of safety related equipment

    International Nuclear Information System (INIS)

    Irish, C.S.

    2003-01-01

    Possibly the most important aspect of performing maintenance of safety related equipment is maintaining the component's original design basis. Assuring that the repaired item will perform the same safety function within the original performance and equipment qualification parameters is commonly referred to as configuration control. Maintaining configuration control of a technologically current well documented item is easy. Unfortunately, this does not describe most safety related items requiring maintenance within the global nuclear industry. Items such as motors, transformers, metal clad switchgear (low and medium voltage circuit breakers), refrigeration compressors, and electronic components (i.e. circuit boards, power supplies, regulators, etc.) which routinely require repair have been in service for twenty plus years. As a result, finding replacement parts and or material to repair the items to the original condition is becoming more and more difficult. An added difficulty is the lack of original technical documentation available on the item which is being repaired. The lack of technical documentation makes it difficult to identify replacement material and parts when the original part or material is not available. The lack of documentation also makes it difficult to test the repaired item to make sure that the original configuration has been maintained after the repair. The presentation will discuss the details of repairing various items including motors, metal clad switchgear, refrigeration compressors and power supplies and the controls which are necessary to maintain the configuration of the original item. The discussion will include the Quality Assurance and engineering necessary to identify and evaluate replacement material and parts necessary to perform repairs on safety related equipment when the original material or part is not available. Examples of repairs which required different parts or materials than the original to be used in the repair will be

  14. Remote controlled capsules in human drug absorption (HDA) studies.

    Science.gov (United States)

    Wilding, Ian R; Prior, David V

    2003-01-01

    The biopharmaceutical complexity of today's new drug candidates provides significant challenges for pharmaceutical scientists in terms of both candidate selection and optimizing subsequent development strategy. In addition, life cycle management of marketed drugs has become an important income stream for pharmaceutical companies, but the selection of least risk/highest benefit strategies is far from simple. The proactive adoption of human drug absorption (HDA) studies using remote controlled capsules offers the pharmaceutical scientist significant guidance for planning a route through the maze of product development. This review examines the position of HDA studies in drug development, using a variety of case histories and an insightful update on remote controlled capsules to achieve site-specific delivery.

  15. Measurements in Concentrated Sun using a Remote Controlled Robot

    Directory of Open Access Journals (Sweden)

    Dan Floroian

    2013-04-01

    Full Text Available Nowdays, using the concentrated sunlight is a big issue because the amount of energy is very high and the light is concentrated in a very small area. The main problem in this situation is the heating, and in order to make safe measurements a remote controlled robot is needed. After that, a remote controlled robot will assume the duty of protect the measured sample and to expose it for a precise time to the concentrated sun in order to reduce heating of the sample. For easy operating, and for automatize the process, all the duties, starting with initial conditions, continuing with triggering the measurements, and conditioning the signals and finalizing with data saving must be assured by the robot.

  16. Note to remote control of GPS observatory using GSM modem

    Czech Academy of Sciences Publication Activity Database

    Kottnauer, Pavel; Rucký, A.; Schenk, Vladimír; Schenková, Zdeňka

    24(131) (2003), s. 163-165 ISSN 1211-1910. [Czech-Polish Workshop on Recent Geodynamics of the Sudety Mts. and Adjacent Areas/4./. Lubawka, 07.11.2002-09.11.2002] R&D Projects: GA MŠk LN00A005 Institutional research plan: CEZ:AV0Z3046908 Keywords : GPS measurement * remote control Subject RIV: DB - Geology ; Mineralogy

  17. Web based remote monitoring and controlling system for vulnerable environments

    Science.gov (United States)

    Thomas, Aparna; George, Minu

    2016-03-01

    The two major areas of concern in industrial establishments are monitoring and security. The remote monitoring and controlling can be established with the help of Web technology. Managers can monitor and control the equipment in the remote area through a web browser. The targeted area includes all type of susceptible environment like gas filling station, research and development laboratories. The environmental parameters like temperature, light intensity, gas etc. can be monitored. Security is a very important factor in an industrial setup. So motion detection feature is added to the system to ensure the security. The remote monitoring and controlling system makes use of the latest, less power consumptive and fast working microcontroller like S3C2440. This system is based on ARM9 and Linux operating system. The ARM9 will collect the sensor data and establish real time video monitoring along with motion detection feature. These captured video data as well as environmental data is transmitted over internet using embedded web server which is integrated within the ARM9 board.

  18. A new remote control room for tokamak operations

    Energy Technology Data Exchange (ETDEWEB)

    Schissel, D.P., E-mail: schissel@fusion.gat.com [General Atomics, P.O. Box 85608, San Diego, CA (United States); Abla, G.; Flanagan, S.; Kim, E.N. [General Atomics, P.O. Box 85608, San Diego, CA (United States)

    2012-12-15

    This paper presents a summary of a new remote tokamak control room constructed near the offices of DIII-D's scientific staff. This integrated system combines hardware, software, data, and control of the room (R-232) into a unified package that has been designed and constructed in a generic fashion so that it can be used with any tokamak operating worldwide. The room is approximately 300 ft{sup 2} and can accommodate up to 12 seated participants. Mounted on the wall facing each scientist are five 52 Double-Prime LCD televisions and mounted to the wall on their right are six 24 Double-Prime LCD monitors. Each seat has associated with it a 24 Double-Prime monitor, network connection, and power and the scientist is either provided with a computer or they can use their own. The room has been used for operation of DIII-D, EAST, and KSTAR. Due to the long distances, data from EAST and KSTAR was brought back to local DIII-D computers in one large parallel network transfer and subsequently served to scientists in the remote control room to other US collaborators. This parallel data transfer allowed the data to be available to US participants between pulses making remote experimental participation highly effective.

  19. Design of an overhead crane for the ITER NB cell remote handling maintenance operations

    Energy Technology Data Exchange (ETDEWEB)

    Taubmann, Gonzalo; Brochet, Laurent [IBERTEF A.I.E., Iberica de Tecnologia de Fusion, C/Magallanes 3, 28015 Madrid (Spain); Liniers, Macarena [Asociacion EURATOM-CIEMAT para la Fusion, Av. Complutense 22, 28040 Madrid (Spain)], E-mail: macarena.liniers@ciemat.es; Medrano, Mercedes; Sarasola, Xabier; Botija, Jose; Alonso, Javier [Asociacion EURATOM-CIEMAT para la Fusion, Av. Complutense 22, 28040 Madrid (Spain); Damiani, Carlo [FUSION FOR ENERGY, Josep Pla 2, Torres Diagonal Litoral Ed B3, 08019 Barcelona (Spain)

    2009-06-15

    In the neutral beam cell of ITER all the maintenance operations on the neutral beam components (BLC's) must be performed by an overhead crane of large payload capability (30-50 tonnes). A crane system is presented consisting of a monorail, a carriage, and a lifting mechanism. The monorail must give access to the BLC's in the beam line vessel, the front components connecting the NB vessel with the Tokamak, and a storage area at the north end of the NB cell. Rail switching points are required at the intersections between radial and toroidal branches. A translational switching mechanism is proposed. The crane carriage consists of two independent sub-carriages, each composed of four wheels. A set of four secondary wheels attached to the main carriage prevents the crane tilting due to the CoG misalignment of some loads. The elevation system proposed consists of an electromechanical crane of four independent drums and 50 tonnes payload. In parallel with the crane design, a logistics and space availability study has been carried out, leading to the detection of clearance or transport problems that could be taken into account in the final crane design.

  20. Design of an overhead crane for the ITER NB cell remote handling maintenance operations

    International Nuclear Information System (INIS)

    Taubmann, Gonzalo; Brochet, Laurent; Liniers, Macarena; Medrano, Mercedes; Sarasola, Xabier; Botija, Jose; Alonso, Javier; Damiani, Carlo

    2009-01-01

    In the neutral beam cell of ITER all the maintenance operations on the neutral beam components (BLC's) must be performed by an overhead crane of large payload capability (30-50 tonnes). A crane system is presented consisting of a monorail, a carriage, and a lifting mechanism. The monorail must give access to the BLC's in the beam line vessel, the front components connecting the NB vessel with the Tokamak, and a storage area at the north end of the NB cell. Rail switching points are required at the intersections between radial and toroidal branches. A translational switching mechanism is proposed. The crane carriage consists of two independent sub-carriages, each composed of four wheels. A set of four secondary wheels attached to the main carriage prevents the crane tilting due to the CoG misalignment of some loads. The elevation system proposed consists of an electromechanical crane of four independent drums and 50 tonnes payload. In parallel with the crane design, a logistics and space availability study has been carried out, leading to the detection of clearance or transport problems that could be taken into account in the final crane design.

  1. Operation and Maintenance of Water Pollution Control Facilities: A WPCF White Paper.

    Science.gov (United States)

    Hill, William R.; And Others

    1979-01-01

    Presented are the recommendations of the Water Pollution Control Federation for operation and maintenance consideration during the planning design, construction, and operation of wastewater treatment facilities. (CS)

  2. H∞ control of a remotely operated underwater vehicle

    International Nuclear Information System (INIS)

    Conte, G.; Serrani, A.

    1994-01-01

    The paper discusses the application of H∞ control techniques to the design of a control system for a remotely operated underwater vehicle. As the main problem in defining a control strategy for such vehicles is the nonlinear and uncertain nature of the modeled dynamics, the robustness properties of H∞ controllers can in principle be used to provide stability and nominal performances for the closed loop system. Therefore, a control strategy based on a scheduling of such controllers has been proposed, and the overall performance of the closed loop system have been evaluated by means of nonlinear simulation in a broad range of working conditions, with particular attention to the effects of the underwater current that acts on the vehicle

  3. Remotely controlled repair of piping at Douglas Point

    International Nuclear Information System (INIS)

    Conrath, J.J.

    1983-06-01

    The 200 MWe Douglas Point Nuclear Generating Station which started operation in 1966 was Canada's first commercial nuclear power plant. In 1977, after 11 years of operation, leakage of heavy water was detected and traced to the Moderator Piping System (pipe sizes 19 mm to 76 mm) located in a vault below the reactor where the radiation fields during shutdown ranged up to 5000 R/Hr. Inspection using remotely operated TV cameras showed that a 'U' bolt clamp support had worn through the wall of one pipe and resulted in the leakage and also that wear was occurring on other pipes. An extensive repair plan was subsequently undertaken in the form of a joint venture of the designer-owner Atomic Energy of Canada Limited, and the builder-operator, Ontario Hydro. This paper describes the equipment and procedures used in remotely controlled repairs at Douglas Point

  4. Remote Control and Monitoring of VLBI Experiments by Smartphones

    Science.gov (United States)

    Ruztort, C. H.; Hase, H.; Zapata, O.; Pedreros, F.

    2012-12-01

    For the remote control and monitoring of VLBI operations, we developed a software optimized for smartphones. This is a new tool based on a client-server architecture with a Web interface optimized for smartphone screens and cellphone networks. The server uses variables of the Field System and its station specific parameters stored in the shared memory. The client running on the smartphone by a Web interface analyzes and visualizes the current status of the radio telescope, receiver, schedule, and recorder. In addition, it allows commands to be sent remotely to the Field System computer and displays the log entries. The user has full access to the entire operation process, which is important in emergency cases. The software also integrates a webcam interface.

  5. A remotely controlled CCTV system for nuclear reactor retube operations

    International Nuclear Information System (INIS)

    Stovman, J.A.

    1984-01-01

    This paper describes the CCTV Vault Observation Subsystem (VOS) under development for Ontario Hydro for the Pickering 'A' Nuclear Power Plant Large Scale Retubing program. This subsystem will be used by a supervisor and several operators to observe fuel channel replacement operations following plant shutdown and removal of the fuel bundles. VOS basically comprises 23 monochrome television camera driven circuits, a matrix switcher, 15 monitors, 9 tape recorders and 4 microphone driven sound circuits. Remote control of the camera's zoom lenses and mounts is via a digitally multiplexed control system. Design considerations include viewing requirements, reliability, radiation, redundance, and economic factors

  6. A remote data acquisition and control system for Moessbauer spectroscopy

    International Nuclear Information System (INIS)

    Zhou Qingguo; Wang Li; Wang Yanlong; Zhao Hong; Zhou Rongjie

    2004-01-01

    A remote data acquisition and control system for Moessbauer spectroscopy based on an embedded computer with the Mini Real-Time Linux operating system is presented. This system can be accessed by an Internet browser or a Java application program, which is designed especially for this purpose. So controlling this system is simple and the interface is user friendly. The components of this system can easily be obtained. So it could be built in most laboratories. We have succeeded in designing and developing this system, as well as using the system at the Key Laboratory for Magnetism and Magnetic Material of Ministry of Education, Lanzhou University, PR China

  7. In-vessel maintenance concepts for tokamak fusion reactors

    International Nuclear Information System (INIS)

    Kelly, V.P.; Berger, J.D.; Yount, J.A.

    1983-01-01

    Concepts for rail-mounted and guided in-vessel handling machines (IVM) for remote maintenance inside tokamak fusion reactors are described. The IVM designs are based on concepts for tethered remotely operated vehicles and feature the use of multiple manipulator arms for remote handling and remote-controlled TV cameras for remote viewing. The concepts include IVMs for both single or dual rail systems located in the top or bottom of the reactor vessel

  8. The installations maintenance control using SAP R/3; O controle de manutencao de instalacoes utilizando o SAP R/3

    Energy Technology Data Exchange (ETDEWEB)

    Ribeiro, Robison Tirre; Pereira, Paulo Manoel Borges; Jorge, Kemal Vieira [Transportadora Brasileira Gasoduto Bolivia Brasil S.A., Rio de Janeiro, RJ (Brazil)

    2004-07-01

    TBG (Transportadora Brasileira Gasoduto Bolivia Brasil S.A.) began their operations in 1999 and since the beginning the SAP R/3 PM module (Plant Maintenance) is used for the control of the maintenance activities and to manager the Master Maintenance and Inspection Plans. On these five years, a series of reports and SAP functionalities were developed or configured to adapt the system R/3 to the needs of TBG maintenance. Now, the whole management and control of the surface facilities maintenance (compression station, city gate, measurement station, etc) is accomplished by SAP R/3 system. (author)

  9. Development of a Control System for PRIDE Remote Servo-manipulator

    International Nuclear Information System (INIS)

    Lee, Jong Kwang; Park, Byung Suk; Lee, Hyo Jik; Kim, Kyung Tae; Kim, Sung Hyun; Park, Hee Sung; Kim, Young Hwan; Jung, Jae Hoo; Kim, Ki Ho; Kim, Ho Dong

    2009-12-01

    KAERI is developing the PRIDE(PyRoprocess Integrated inactive DEmonstration) facility to verify the integrated performance of full Pyroprocess flow. A main process cell in the PRIDE facility will be filled with argon gas which prohibits direct access by human operators. Therefore, all the operation and maintenance of the process equipment is performed remotely through a master-slave manipulation. This research focuses on the design, fabrication, and interface of a control system which integrates several hardware systems such as a dual arm master-slave servo-manipulator, a horizontally moving transporter for a master manipulator, a bridge transporter for a slave manipulator, a chain hoist, camera systems and their display system, a manual console, and a pendant, etc. Also, a bilateral force-reflection controller considering an elasticity and vibration modes of wire cable has been developed for master-slave remote manipulation. The results obtained in this study will be applied for the force-reflection control of the bridge-transported master-slave servo-manipulator system for use in the PRIDE facility. Since this research is an essential work in robotics related fields, the results would be widely used for developing power manipulators and process automation equipment

  10. Development of a Control System for PRIDE Remote Servo-manipulator

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Jong Kwang; Park, Byung Suk; Lee, Hyo Jik; Kim, Kyung Tae; Kim, Sung Hyun; Park, Hee Sung; Kim, Young Hwan; Jung, Jae Hoo; Kim, Ki Ho; Kim, Ho Dong

    2009-12-15

    KAERI is developing the PRIDE(PyRoprocess Integrated inactive DEmonstration) facility to verify the integrated performance of full Pyroprocess flow. A main process cell in the PRIDE facility will be filled with argon gas which prohibits direct access by human operators. Therefore, all the operation and maintenance of the process equipment is performed remotely through a master-slave manipulation. This research focuses on the design, fabrication, and interface of a control system which integrates several hardware systems such as a dual arm master-slave servo-manipulator, a horizontally moving transporter for a master manipulator, a bridge transporter for a slave manipulator, a chain hoist, camera systems and their display system, a manual console, and a pendant, etc. Also, a bilateral force-reflection controller considering an elasticity and vibration modes of wire cable has been developed for master-slave remote manipulation. The results obtained in this study will be applied for the force-reflection control of the bridge-transported master-slave servo-manipulator system for use in the PRIDE facility. Since this research is an essential work in robotics related fields, the results would be widely used for developing power manipulators and process automation equipment.

  11. Local control station for development, testing and maintenance of mirror fusion facility subsystem controls

    International Nuclear Information System (INIS)

    Ables, E.; Kelly, M.F.

    1985-01-01

    A Local Control Station (LCS) was designed and built to provide a simplified ad easily configurable means of controlling any Mirror Fusion Test Facility (MFTF-B) subsystem for the purpose of development, testing and maintenance of the subsystem. All MFTF-B Subsystems incorporate at least one Local Control Computer (LCC) that is connected to and accepts high level commands from one of the Supervisory Control and Diagnostic System (SCDS) computers. The LCS connects directly to the LCC in place of SCDS. The LCS communicates with the subsystem hardware using the same SCDS commands that the local control computer recognizes and as such requires no special configuration of the LCC

  12. Advantage of redundancy in the controllability of remote handling manipulator

    International Nuclear Information System (INIS)

    Muhammad, Ali; Mattila, Jouni; Vilenius, Matti; Siuko, Mikko; Semeraro, Luigi

    2011-01-01

    To carry out a variety of remote handling operations inside the ITER divertor a Water Hydraulic MANipulator (WHMAN) and its control system have been designed and developed at Tampere University of Technology. The manipulator is installed on top of Cassette Multifunctional Mover (CMM) to assist during the cassette removal and installation operations. While CMM is designed to carry heavy components such as cassettes through the service ducts relying on positioning accuracy and repeatability, WHMAN is designed to execute a mix of remote handling operations using position trajectories and master-slave telemanipulation. WHMAN is composed of eight joints: six rotational and two translational. Since a manipulator requires only six joints to acquire the desired position and orientation in operational-space, the two additional joints of WHMAN provide the redundant degrees of mobility. This paper presents how this redundancy of WHMAN can be an advantage to optimize the execution of remote handling tasks. The paper also discusses an effective way to practically exploit the redundancy. The results show that the additional degrees of freedom can be utilized to improve the dynamic behavior of the manipulator.

  13. Remote diagnosis system for control and instrumentation systems

    International Nuclear Information System (INIS)

    Ito, Tetsuo; Suzuki, Satoshi; Nagaoka, Yukio.

    1990-01-01

    Control and instrumentation (C and I) systems for nuclear power plants tend to consist of many distributed digital controllers connected with transmission networks. Important parts of the C and I systems are redundantly constructed so that the failure of a component does not readily have a critical effect on the plant operation. It is necessary, however, to localize the faulty component for establishing better availability and maintainability of the plant. To diagnose failure of the C and I systems effectively, a remote diagnosis system is required that diagnoses anomalies of their controllers remotely from a central control room and identifies the fault location. Various fault diagnosis methods that apply artificial intelligence have been proposed for electronic circuits. Their knowledge bases are classified into two categories. One is rule-based knowledge, describing relations between anomaly phenomena and causes. The other is structure-based knowledge, which represents the configuration and functions of diagnosed objects. Though the latter is more suitable for deep inference, it is difficult to use for describing the detailed structure of large-scaled digital C and I systems. Then, a fault diagnosis system was developed that uses both knowledge bases and offers substantial man/machine interface functions for practical use

  14. Remote Monitoring of the Polarized Target's Control for E1039

    Science.gov (United States)

    Fox, David; SeaQuest Collaboration

    2017-09-01

    The 1039 experiment at FNAL will further our understanding of spin structure by measuring the contribution that sea quarks orbital angular momentum provide to overall nucleon spin. It is accepted that the valence-quarks of nucleons only provide 30% of the total nucleon spin. To study the nucleon's sea quark contribution, E1039 will use the Drell-Yan process by colliding 120 GeV un-polarized beam protons with polarized ammonia targets of hydrogen and deuterium. The asymmetric spin distributions of resulting dimuons will be measured. These asymmetries are sensitive, among other effects, to the orbital angular momentum contribution of the sea quarks. The polarized target requires a multi-stage vacuum pump located near the target. Since access to its present controls will not be possible during running, remote control and monitoring upgrades were required. A secondary control panel was purchased and tested. Information from the programmable logic controller (PLC) must be fed into our data stream to enable remote monitoring and to signal possible alarm conditions. This solution and the program created using explicit TCP/IP messaging to extract data tags from the PLC and log it within our databases will be presented. Supported by U.S. D.O.E. Medium Energy Nuclear Physics under Grant DE-FG02-03ER41243.

  15. Internet remote control interface for a multipurpose robotic arm

    Directory of Open Access Journals (Sweden)

    Matthew W. Dunnigan

    2008-11-01

    Full Text Available This paper presents an Internet remote control interface for a MITSUBISHI PA10-6CE manipulator established for the purpose of the ROBOT museum exhibition during spring and summer 2004. The robotic manipulator is a part of the Intelligent Robotic Systems Laboratory at Heriot ? Watt University, which has been established to work on dynamic and kinematic aspects of manipulator control in the presence of environmental disturbances. The laboratory has been enriched by a simple vision system consisting of three web-cameras to broadcast the live images of the robots over the Internet. The Interface comprises of the TCP/IP server providing command parsing and execution using the open controller architecture of the manipulator and a client Java applet web-site providing a simple robot control interface.

  16. Remote fabrication of breeder reactor fuel

    International Nuclear Information System (INIS)

    Gerber, E.W.; Hoitink, N.C.; Graham, R.A.

    1984-06-01

    The Secure Automated Fabrication (SAF) Line, a remotely operable plutonium fuel fabrication facility, incorporates advanced automation techniques. Included in the plant are 24 robots used to perform complex operations, and to enhance equipment standardization and ease of maintenance. Automated equipment is controlled remotely from centrally located supervisory computer control consoles or alternatively from control consoles dedicated to individual systems

  17. Advanced remote handling developments for high radiation applications

    International Nuclear Information System (INIS)

    Herndon, J.N.; Kring, C.T.; Feldman, M.J.; Kuban, D.P.; Martin, H.L.; Rowe, J.C.; Hamel, W.R.

    1985-01-01

    The Remote Control Engineering Task of the Consolidated Fuel Reprocessing Program at Oak Ridge National Laboratory has been developing advanced techniques for remote maintenance of future US fuel reprocessing plants. These efforts are based on the application of teleoperated, force-reflecting servomanipulators for dexterous remote handling with television viewing for large-volume hazardous applications. These developments fully address the nonrepetitive nature of remote maintenance in the unstructured environments encountered in fuel reprocessing. This paper covers the primary emphasis in the present program; the design, fabrication, and installation of a prototype remote handling system for reprocessing applications, the Advanced Integrated Maintenance System

  18. Haptic shared control improves hot cell remote handling despite controller inaccuracies

    NARCIS (Netherlands)

    van Oosterhout, J.; Abbink, D. A.; Koning, J. F.; Boessenkool, H.; Wildenbeest, J. G. W.; Heemskerk, C. J. M.

    2013-01-01

    A promising solution to improve task performance in ITER hot cell remote handling is the use of haptic shared control. Haptic shared control can assist the human operator along a safe and optimal path with continuous guiding forces from an intelligent autonomous controller. Previous research tested

  19. An improved control system for a remotely operated vessel

    Science.gov (United States)

    Bachnak, Rafic; Mendez, Marc; Esparza, Jack; Fahed, Oliver

    2006-05-01

    Collecting environmental data in coastal bays presents several challenges to the scientist. One of the most pressing issues is how to efficiently and reliably gather data in shallow water areas-environments that often preclude the use of traditional boats. Obstacles that are encountered in such environments include difficulty in covering large territories and the presence of inaccessible areas due to a variety of reasons, such as soft bottoms or contamination. There is also a high probability of disturbing the test area while placing the sensors. This paper outlines the development of a remotely operated boat and its real-time control system.

  20. Fermilab Muon Campus g-2 Cryogenic Distribution Remote Control System

    Energy Technology Data Exchange (ETDEWEB)

    Pei, L.; Theilacker, J.; Klebaner, A.; Soyars, W.; Bossert, R.

    2015-11-05

    The Muon Campus (MC) is able to measure Muon g-2 with high precision and comparing its value to the theoretical prediction. The MC has four 300 KW screw compressors and four liquid helium refrigerators. The centerpiece of the Muon g-2 experiment at Fermilab is a large, 50-foot-diameter superconducting muon storage ring. This one-of-a-kind ring, made of steel, aluminum and superconducting wire, was built for the previous g-2 experiment at Brookhaven. Due to each subsystem has to be far away from each other and be placed in the distant location, therefore, Siemens Process Control System PCS7-400, Automation Direct DL205 & DL05 PLC, Synoptic and Fermilab ACNET HMI are the ideal choices as the MC g-2 cryogenic distribution real-time and on-Line remote control system. This paper presents a method which has been successfully used by many Fermilab distribution cryogenic real-time and On-Line remote control systems.

  1. Control, data acquisition, data analysis and remote participation in LHD

    International Nuclear Information System (INIS)

    Nagayama, Y.; Emoto, M.; Nakanishi, H.; Sudo, S.; Imazu, S.; Inagaki, S.; Iwata, C.; Kojima, M.; Nonomura, M.; Ohsuna, M.; Tsuda, K.; Yoshida, M.; Chikaraishi, H.; Funaba, H.; Horiuchi, R.; Ishiguro, S.; Ito, Y.; Kubo, S.; Mase, A.; Mito, T.

    2008-01-01

    This paper presents the control, data acquisition, data analysis and remote participation facilities of the Large Helical Device (LHD), which is designed to confine the plasma in steady state. In LHD the plasma duration exceeds 3000 s by controlling the plasma position, the density and the ICRF heating. The 'LABCOM' data acquisition system takes both the short-pulse and the steady-state data. A two-layer Mass Storage System with RAIDs and Blu-ray Disk jukeboxes in a storage area network has been developed to increase capacity of storage. The steady-state data can be monitored with a Web browser in real time. A high-level data analysis system with Web interfaces is being developed in order to provide easier usage of LHD data and large FORTRAN codes in a supercomputer. A virtual laboratory system for the Japanese fusion community has been developed with Multi-protocol Label Switching Virtual Private Network Technology. Collaborators at remote sites can join the LHD experiment or use the NIFS supercomputer system as if they were working in the LHD control room

  2. Progress in standardization for ITER Remote Handling control system

    International Nuclear Information System (INIS)

    Hamilton, David Thomas; Tesini, Alessandro; Ranz, Roberto; Kozaka, Hiroshi

    2014-01-01

    Graphical abstract: - Highlights: • Standard parts specified for ITER Remote Handling (RH) control system. • Standard approach for VR modeling of structural deformations in real-time. • RH Core System produced as standard platform for RH controller applications. • Synthetic Viewing investigated and demonstrated. • Structured language defined for RH operation procedures and motion sequences. - Abstract: An integrated control system architecture has been defined for the ITER Remote Handling (RH) equipment systems, and work has been continuing to develop and validate standards for this architecture. Evaluations of standard parts and a standard control room work-cell have contributed to an update of the RH Control System Design Handbook, while R and D activities have been carried out to validate concepts for standard solutions to ITER RH problems: the use of a standard master arm with different slave arms, the achievement of high accuracy tracking of RH operations within virtual reality, and condition monitoring of RH equipment systems. The standardization efforts have been consolidated through the development of a freely distributable software platform to support the adoption of the ITER RH standards. The RH Core System installs on top of the CODAC Core System and provides the basic platform for the development of ITER RH equipment controller applications. The standardization work has continued in the areas of RH viewing, network communication protocols, and a structured language for programming ITER RH operations. Prototyping has been done on high-level control system applications, and R and D has been carried out in the area of synthetic viewing for ITER RH. These developments will be reflected in a new version of the RH Core System to be produced during 2013

  3. Progress in standardization for ITER Remote Handling control system

    Energy Technology Data Exchange (ETDEWEB)

    Hamilton, David Thomas, E-mail: david.hamilton@iter.org [ITER Organization, Route de Vinon, 13115 St. Paul-lez-Durance (France); Tesini, Alessandro [ITER Organization, Route de Vinon, 13115 St. Paul-lez-Durance (France); Ranz, Roberto [Fusion for Energy, Torres Diagonal Litoral B3, Josep Pla 2, 08019 Barcelona (Spain); Kozaka, Hiroshi [Japan Atomic Energy Agency, Fusion Research and Development Directorate, Naka, Ibaraki-ken 311-0193 (Japan)

    2014-10-15

    Graphical abstract: - Highlights: • Standard parts specified for ITER Remote Handling (RH) control system. • Standard approach for VR modeling of structural deformations in real-time. • RH Core System produced as standard platform for RH controller applications. • Synthetic Viewing investigated and demonstrated. • Structured language defined for RH operation procedures and motion sequences. - Abstract: An integrated control system architecture has been defined for the ITER Remote Handling (RH) equipment systems, and work has been continuing to develop and validate standards for this architecture. Evaluations of standard parts and a standard control room work-cell have contributed to an update of the RH Control System Design Handbook, while R and D activities have been carried out to validate concepts for standard solutions to ITER RH problems: the use of a standard master arm with different slave arms, the achievement of high accuracy tracking of RH operations within virtual reality, and condition monitoring of RH equipment systems. The standardization efforts have been consolidated through the development of a freely distributable software platform to support the adoption of the ITER RH standards. The RH Core System installs on top of the CODAC Core System and provides the basic platform for the development of ITER RH equipment controller applications. The standardization work has continued in the areas of RH viewing, network communication protocols, and a structured language for programming ITER RH operations. Prototyping has been done on high-level control system applications, and R and D has been carried out in the area of synthetic viewing for ITER RH. These developments will be reflected in a new version of the RH Core System to be produced during 2013.

  4. Overview of remote handling technologies developed for inspection and maintenance of spent fuel management facilities in France

    Energy Technology Data Exchange (ETDEWEB)

    Desbats, Philippe [CEA - Direction de la Recherche Technologique / LIST, BP 6 - 92265, Fontenay-aux-Roses cedex (France); Piolain, Gerard [COGEMA-HAG/DMCO, AREVA NC SA, 2, rue Paul Dautier, BP 4, 78 141 Velizy Cedex (France)

    2006-07-01

    In the facilities of the end of the nuclear fuel cycle, like spent fuel storage pools, reprocessing plants, Plutonium-based fuel manufacturing plants or waste temporary storage units, materials handling must be carried out remotely, taking into account the nuclear radiating environment. In addition to the automation requirement, robotics equipment in the nuclear industry must be substituted to human operators in order to respect the ALARA principle. More over, remote handling technologies aim to improve the working conditions, as well as the quality of the work achieved by the operators. Ten years ago, COGEMA (AREVA Group) and CEA (French Atomic Energy Agency) started an ambitious R and D program in robotics and remote handling technologies applied to COGEMA spent fuel management facilities in France, with the aim to cover the requirements of the different plant life cycle steps. The paper gives an overview of the important developments that have been carried out by CEA and then transferred to the COGEMA industrial group. The range includes the next generation of servo-manipulators, long range inspection tools and carriers, nuclear versions of industrial robots, radiation hardened electronic systems, interactive environment modeling tools, as well as force-feedback master-slave generic control software for tele-operation systems. Some applications of this development are presented in the paper: - rad-hard electronic modules for robotic equipment which are used by COGEMA in high radiating environment; - long reach articulated carrier for inspection of spent full management blind cells; - new electrical force feedback master/slave system to improve the tele-operation of standard tele-manipulators; - generic control software for tele-manipulators. The results of the robotic program carried out by COGEMA and CEA have been very valuable for the introduction of new technologies inside nuclear industry. Innovative products and sub-systems can be integrated now in a large

  5. Remote control of SMM behaviour via DTE ligands.

    Science.gov (United States)

    Cosquer, Goulven; Breedlove, Brian K; Yamashita, Masahiro

    2015-02-21

    Chemists and physicists are continuously working to understand the mechanisms controlling molecular magnetism, especially single-molecule magnetism, to improve the magnetic properties, such as the blocking temperature. With the current research focused on preparing molecular devices, methods to control the components of the devices are necessary. Extensive research has shown that stimuli, such as light, electric current, etc., can be used to change the properties of the molecules making up the devices. Bis(carboxylato)dithienylethene (DTE) derivatives can be photo-isomerized between open and closed forms, i.e., unconjugated and π-conjugated forms, and because of the carboxylate groups, it can be used to link 3d and/or 4f metal ions. Herein the use of DTE ligands to remotely control the magnetic properties of single-molecule magnets is discussed.

  6. Design of remote control alarm system by microwave detection

    Science.gov (United States)

    Wang, Junli

    2018-04-01

    A microwave detection remote control alarm system is designed, which is composed of a Microwave detectors, a radio receiving/transmitting module and a digital encoding/decoding IC. When some objects move into the surveillance area, microwave detectors will generate a control signal to start transmitting system. A radio control signal will be spread by the transmitting module, once the signal can be received, and it will be disposed by some circuits, arousing some voices that awake the watching people. The whole device is a modular configuration, it not only has some advantage of frequency stable, but also reliable and adjustment-free, and it is suitable for many kinds of demands within the distance of 100m.

  7. Control maintenance training program for special safety systems at Bruce B

    International Nuclear Information System (INIS)

    Reinwald, G.

    1997-01-01

    It was recognized from the early days of commissioning of Bruce B that Control Maintenance staff would require a level of expertise to be able to maintain Special Safety Systems in proper running order. In the early 80's this was achieved through hands on experience during the original commissioning, troubleshooting and placing of the various systems in service. Control maintenance procedures were developed and implemented as the new systems came available for commissioning, as were operating manuals,training manuals etc. Under the development of the Maintenance Manager, a Conduct of Maintenance section was organized. One of the responsibilities of this section was to develop a series of Maintenance Administrative Procedures (MAPs) that set the standards for maintenance activities including training

  8. A remotely operated drug delivery system with dose control

    KAUST Repository

    Yi, Ying

    2017-05-08

    “On demand” implantable drug delivery systems can provide optimized treatments, due to their ability to provide targeted, flexible and precise dose release. However, two important issues that need to be carefully considered in a mature device include an effective actuation stimulus and a controllable dose release mechanism. This work focuses on remotely powering an implantable drug delivery system and providing a high degree of control over the released dose. This is accomplished by integration of a resonance-based wireless power transfer system, a constant voltage control circuit and an electrolytic pump. Upon the activation of the wireless power transfer system, the electrolytic actuator is remotely powered by a constant voltage regardless of movements of the device within an effective range of translation and rotation. This in turn contributes to a predictable dose release rate and greater flexibility in the positioning of external powering source. We have conducted proof-of-concept drug delivery studies using the liquid drug in reservoir approach and the solid drug in reservoir approach, respectively. Our experimental results demonstrate that the range of flow rate is mainly determined by the voltage controlled with a Zener diode and the resistance of the implantable device. The latter can be adjusted by connecting different resistors, providing control over the flow rate to meet different clinical needs. The flow rate can be maintained at a constant level within the effective movement range. When using a solid drug substitute with a low solubility, solvent blue 38, the dose release can be kept at 2.36μg/cycle within the effective movement range by using an input voltage of 10Vpp and a load of 1.5 kΩ, which indicates the feasibility and controllability of our system without any complicated closed-loop sensor.

  9. Diverse Planning for UAV Control and Remote Sensing

    Directory of Open Access Journals (Sweden)

    Jan Tožička

    2016-12-01

    Full Text Available Unmanned aerial vehicles (UAVs are suited to various remote sensing missions, such as measuring air quality. The conventional method of UAV control is by human operators. Such an approach is limited by the ability of cooperation among the operators controlling larger fleets of UAVs in a shared area. The remedy for this is to increase autonomy of the UAVs in planning their trajectories by considering other UAVs and their plans. To provide such improvement in autonomy, we need better algorithms for generating alternative trajectory variants that the UAV coordination algorithms can utilize. In this article, we define a novel family of multi-UAV sensing problems, solving task allocation of huge number of tasks (tens of thousands to a group of configurable UAVs with non-zero weight of equipped sensors (comprising the air quality measurement as well together with two base-line solvers. To solve the problem efficiently, we use an algorithm for diverse trajectory generation and integrate it with a solver for the multi-UAV coordination problem. Finally, we experimentally evaluate the multi-UAV sensing problem solver. The evaluation is done on synthetic and real-world-inspired benchmarks in a multi-UAV simulator. Results show that diverse planning is a valuable method for remote sensing applications containing multiple UAVs.

  10. Conceptual design studies of special-purpose equipment for Fusion Engineering Device torus-sector remote maintenance

    International Nuclear Information System (INIS)

    Masson, L.S.; Watts, K.D.; Aldrich, W.E.; McPherson, R.S.

    1982-01-01

    One of the major maintenance operations anticipated for fusion reactors of the Tokamak configuration is remote removal and replacement of torus sectors. This operation will be difficult due to the massive nature of the sector (375 tonnes), and also due to the precision with which it must be positioned within the fixed structure. The same problem, only to a lesser degree, applies to sub-components of the sector such as the limiter blades, shielding, test assemblies, etc. General and specific design requirements have been generated and trade studies conducted on reactor interfacing details as well as handling machine concepts. On the basis of the design requirements and trade studies, a perferred concept for the sector handling machine was developed. In addition, a similar machine was developed for handling the intermediate sized sector sub-components. While most operations will be performed by special purpose machines such as described above, there is a need for a versatile, relatively high capacity mobile system. A concept suitable for this mobile application was also developed as part of these studies. The general conclusion, to the extent these studies have been completed, was that special single-purpose machines will be required to perform the operations requiring high load capacity and handling precision. The machine concepts developed were felt to be within the state-of-the-art, and will make extensive use of commercially available components. The most serious problem was felt to be development of simple methods to obtain the required precision in positioning massive objects such as the torus sector

  11. Remotely Piloted Vehicles for Experimental Flight Control Testing

    Science.gov (United States)

    Motter, Mark A.; High, James W.

    2009-01-01

    A successful flight test and training campaign of the NASA Flying Controls Testbed was conducted at Naval Outlying Field, Webster Field, MD during 2008. Both the prop and jet-powered versions of the subscale, remotely piloted testbeds were used to test representative experimental flight controllers. These testbeds were developed by the Subsonic Fixed Wing Project s emphasis on new flight test techniques. The Subsonic Fixed Wing Project is under the Fundamental Aeronautics Program of NASA's Aeronautics Research Mission Directorate (ARMD). The purpose of these testbeds is to quickly and inexpensively evaluate advanced concepts and experimental flight controls, with applications to adaptive control, system identification, novel control effectors, correlation of subscale flight tests with wind tunnel results, and autonomous operations. Flight tests and operator training were conducted during four separate series of tests during April, May, June and August 2008. Experimental controllers were engaged and disengaged during fully autonomous flight in the designated test area. Flaps and landing gear were deployed by commands from the ground control station as unanticipated disturbances. The flight tests were performed NASA personnel with support from the Maritime Unmanned Development and Operations (MUDO) team of the Naval Air Warfare Center, Aircraft Division

  12. A Three-Year Feedback Study of a Remote Laboratory Used in Control Engineering Studies

    Science.gov (United States)

    Chevalier, Amélie; Copot, Cosmin; Ionescu, Clara; De Keyser, Robin

    2017-01-01

    This paper discusses the results of a feedback study for a remote laboratory used in the education of control engineering students. The goal is to show the effectiveness of the remote laboratory on examination results. To provide an overview, the two applications of the remote laboratory are addressed: 1) the Stewart platform, and 2) the quadruple…

  13. Remote control of ATLAS-MPX Network and Data Visualization

    International Nuclear Information System (INIS)

    Turecek, D.; Holy, T.; Pospisil, S.; Vykydal, Z.

    2011-01-01

    The ATLAS-MPX Network is a network of 15 Medipix2-based detector devices, installed in various positions in the ATLAS detector at CERN, Geneva. The aim of the network is to perform a real-time measurement of the spectral characteristics and the composition of radiation inside the ATLAS detector during its operation. The remote control system of ATLAS-MPX controls and configures all the devices from one place, via a web interface, accessible from different operating systems. The Data Visualization application, also with a web interface, has been developed in order to present measured data to the scientific community. It allows to browse through recorded frames from all devices and to search for specific frames by date and time. Charts containing the number of different types of tracks in each frame as a function of time may be rendered from the database.

  14. Control-limit preventive maintenance policies for components subject to imperfect preventive maintenance and variable operational conditions

    International Nuclear Information System (INIS)

    You Mingyi; Li Hongguang; Meng Guang

    2011-01-01

    This paper develops two component-level control-limit preventive maintenance (PM) policies for systems subject to the joint effect of partial recovery PM acts (imperfect PM acts) and variable operational conditions, and investigates the properties of the proposed policies. The extended proportional hazards model (EPHM) is used to model the system failure likelihood influenced by both factors. Several numerical experiments are conducted for policy property analysis, using real lifetime and operational condition data and typical characterization of imperfect PM acts and maintenance durations. The experimental results demonstrate the necessity of considering both factors when they do exist, characterize the joint effect of the two factors on the performance of an optimized PM policy, and explore the influence of the loading sequence of time-varying operational conditions on the performance of an optimized PM policy. The proposed policies extend the applicability of PM optimization techniques.

  15. Application of telerobotic control to remote processing of nuclear material

    International Nuclear Information System (INIS)

    Merrill, R.D.; Grasz, E.L.; Herget, C.J.; Gavel, D.T.; Addis, R.B.; DeMinico, G.A.

    1991-01-01

    In processing radioactive material there are certain steps which have customarily required operators working at glove box enclosures. This can subject the operators to low level radiation dosages and the risk of accidental contamination, as well as generate significant radioactive waste to accommodate the human interaction. An automated system is being developed to replace the operator at the glove box and thus remove the human from these risks, and minimize waste. Although most of the processing can be automated with very little human operator interaction, there are some tasks where intelligent intervention is necessary to adapt to unexpected circumstances and events. These activities will require that the operator be able to interact with the process using a remote manipulator in a manner as natural as if the operator were actually in the work cell. This robot-based remote manipulation system, or telerobot, must provide the operator with an effective means of controlling the robot arm, gripper and tools. This paper describes the effort in progress in Lawrence Livermore National Laboratory to achieve this capability. 8 refs

  16. Mechanism of remote controlled after-loading radiotherapy unit

    International Nuclear Information System (INIS)

    Morimoto, Masaki

    1980-01-01

    Employing a small amount of Radium-226 or Cesium-137 source was to be used hitherto for the treatment of carcinoma of the uterine cervix in used After-loading techniques. It involved, however, radiation risk to the staff and patient. The long treatment time are also a pain (strain) on the patient. In recent years, we have developed a remote control after-loading unit, which was named as RALSTRON, which was complete eliminated the disadvantage of conventional radium therapy. This unit also has disadvantage, however, that the design for the remote after-loader for intracavitary applicators present considerable difficulties, because many sources of different active lengths and loading patterns are required. A solution to this problem was carried out by using small point source, placed in Tandem applicator, of high activity and moving them back slowly during the treatment. Recently, this unit was installed many hospitals about 80 units in Japan, and are used. In this paper are given about a mechanism and safety deviced of this unit. (author)

  17. Cooperative Remote Monitoring, Arms control and nonproliferation technologies: Fourth quarter 1995

    Energy Technology Data Exchange (ETDEWEB)

    Alonzo, G M [ed.

    1995-01-01

    The DOE`s Cooperative Remote Monitoring programs integrate elements from research and development and implementation to achieve DOE`s objectives in arms control and nonproliferation. The contents of this issue are: cooperative remote monitoring--trends in arms control and nonproliferation; Modular Integrated Monitoring System (MIMS); Authenticated Tracking and Monitoring Systems (ATMS); Tracking and Nuclear Materials by Wide-Area Nuclear Detection (WAND); Cooperative Monitoring Center; the International Remote Monitoring Project; international US and IAEA remote monitoring field trials; Project Dustcloud: monitoring the test stands in Iraq; bilateral remote monitoring: Kurchatov-Argonne-West Demonstration; INSENS Sensor System Project.

  18. Multicriteria selection in concept design of a divertor remote maintenance port in the EU DEMO reactor using an AHP participative approach

    Energy Technology Data Exchange (ETDEWEB)

    Carfora, D. [Tampere University of Technology, Korkeakoulunkatu 6, 33720 Tampere (Finland); Gironimo, G. Di, E-mail: giuseppe.digironimo@unina.it [CREATE, University of Naples Federico II, P.le Tecchio 80, 80125 Napoli (Italy); Esposito, G. [CREATE, University of Naples Federico II, P.le Tecchio 80, 80125 Napoli (Italy); Huhtala, K. [Tampere University of Technology, Korkeakoulunkatu 6, 33720 Tampere (Finland); Määttä, T.; Mäkinen, H. [VTT Technical Research Centre of Finland, P.O. Box 1300, FI-33101 Tampere (Finland); Miccichè, G. [ENEA Brasimone, I:40032 Camugnano (Italy); Mozzillo, R. [CREATE, University of Naples Federico II, P.le Tecchio 80, 80125 Napoli (Italy)

    2016-11-15

    Highlights: • Concept Studies in Divertor Remote Handling. • Prioritization of concept alternatives. • Comparison and evaluation of product alternatives using AHP. - Abstract: The work behind this paper took place in the Eurofusion remote maintenance system project (WPRM) for the EU Demonstration Fusion Power Reactor (DEMO). Following ITER, the aim of DEMO is to demonstrate the capability of generating several hundreds of MW of net electricity by 2050. The main objective of this paper was the study of the most efficient design of the maintenance port for replacing the divertor cassettes in a Remote Handling (RH) point of view. In DEMO overall design, one important consideration is the availability and short down time operations. The inclination of the divertor port has a very important impact on all the RH tasks such as the design of the divertor mover, the divertor locking systems and the end effectors. The current reference scenario of the EU DEMO foresees a 45° inclined port for the remote maintenance (RM) of the divertor in the lower part of the reactor. Nevertheless, in the optic of the systems engineering (SE) approach, in early concept design phase, all possible configurations shall be taken into account. Even the solutions which seem not feasible at all need to be investigated, because they could lead to new and innovative engineering proposals. The different solutions were compared using an approach based on the Analytic Hierarchy Process (AHP). The technique is a multi-criteria decision making approach in which the factors that are important in making a decision are arranged in a hierarchic structure. The results of these studies show how the application of the AHP improved and focused the selection on the concept which is closer to the requirements arose from technical meetings with the experts of the RH field.

  19. Multicriteria selection in concept design of a divertor remote maintenance port in the EU DEMO reactor using an AHP participative approach

    International Nuclear Information System (INIS)

    Carfora, D.; Gironimo, G. Di; Esposito, G.; Huhtala, K.; Määttä, T.; Mäkinen, H.; Miccichè, G.; Mozzillo, R.

    2016-01-01

    Highlights: • Concept Studies in Divertor Remote Handling. • Prioritization of concept alternatives. • Comparison and evaluation of product alternatives using AHP. - Abstract: The work behind this paper took place in the Eurofusion remote maintenance system project (WPRM) for the EU Demonstration Fusion Power Reactor (DEMO). Following ITER, the aim of DEMO is to demonstrate the capability of generating several hundreds of MW of net electricity by 2050. The main objective of this paper was the study of the most efficient design of the maintenance port for replacing the divertor cassettes in a Remote Handling (RH) point of view. In DEMO overall design, one important consideration is the availability and short down time operations. The inclination of the divertor port has a very important impact on all the RH tasks such as the design of the divertor mover, the divertor locking systems and the end effectors. The current reference scenario of the EU DEMO foresees a 45° inclined port for the remote maintenance (RM) of the divertor in the lower part of the reactor. Nevertheless, in the optic of the systems engineering (SE) approach, in early concept design phase, all possible configurations shall be taken into account. Even the solutions which seem not feasible at all need to be investigated, because they could lead to new and innovative engineering proposals. The different solutions were compared using an approach based on the Analytic Hierarchy Process (AHP). The technique is a multi-criteria decision making approach in which the factors that are important in making a decision are arranged in a hierarchic structure. The results of these studies show how the application of the AHP improved and focused the selection on the concept which is closer to the requirements arose from technical meetings with the experts of the RH field.

  20. Deployment and Maintenance of Wave Energy Converters at the Lysekil Research Site: A Comparative Study on the Use of Divers and Remotely-Operated Vehicles

    Directory of Open Access Journals (Sweden)

    Flore Rémouit

    2018-04-01

    Full Text Available Ocean renewable technologies have been rapidly developing over the past years. However, current high installation, operation, maintenance, and decommissioning costs are hindering these offshore technologies to reach a commercialization stage. In this paper we focus on the use of divers and remotely-operated vehicles during the installation and monitoring phase of wave energy converters. Methods and results are based on the wave energy converter system developed by Uppsala University, and our experience in offshore deployments obtained during the past eleven years. The complexity of underwater operations, carried out by either divers or remotely-operated vehicles, is emphasized. Three methods for the deployment of wave energy converters are economically and technically analyzed and compared: one using divers alone, a fully-automated approach using remotely-operated vehicles, and an intermediate approach, involving both divers and underwater vehicles. The monitoring of wave energy converters by robots is also studied, both in terms of costs and technical challenges. The results show that choosing an autonomous deployment method is more advantageous than a diver-assisted method in terms of operational time, but that numerous factors prevent the wide application of robotized operations. Technical solutions are presented to enable the use of remotely-operated vehicles instead of divers in ocean renewable technology operations. Economically, it is more efficient to use divers than autonomous vehicles for the deployment of six or fewer wave energy converters. From seven devices, remotely-operated vehicles become advantageous.

  1. Design of auxiliary shield for remote controlled metallographic microscope

    International Nuclear Information System (INIS)

    Matsui, Hiroki; Okamoto, Hisato

    2014-06-01

    The remote controlled optical microscope installed in the lead cell at the Reactor Fuel Examination Facility (RFEF) in Japan Atomic Energy Agency (JAEA) has been upgraded to a higher performance unit to study the effect of the microstructural evolution in clad material on the high burn-up fuel behavior under the accident condition. The optical pass of the new microscope requires a new through hole in the shielding lead wall of the cell. To meet safety regulations, auxiliary lead shieldings were designed to cover the lost shielding function of the cell wall. Particle and Heavy Ion Transport Code System (PHITS) was used to calculate and determine the shape and setting positions of the shielding unit. Seismic assessments of the unit were also performed. (author)

  2. Conveying equipment for various inspection devices through remote control

    International Nuclear Information System (INIS)

    Kihara, Shizo; Ibe, Tomoyoshi.

    1976-01-01

    Purpose: To rapidly and accurately convey a flaw detector by means of remote control to a member to be inspected, which is not accessible by an operator, for example, such as a suitable desired wall surface within a reactor. Constitution: Guide tracks are fixedly mounted along the wall surface of the structure by support members. A TV camera mounted on a sliding truck catches an image reflected from a concave reflecting mirror within the flaw detector to obtain information by which a driving mechanism of the self-travelling truck and winch mechanisms of the self-travelling truck and sliding truck may be driven to move the flaw detector to the desired position. In this case, the automatic connecting mechanism is disconnected, and a cable is suitably expanded by a group of travelling trucks and an expansion adjusting mechanism. (Yoshino, Y.)

  3. Development of the predictive maintenance system prototype for the rod control system

    International Nuclear Information System (INIS)

    Lim, H. S.; Hong, H. P.; Koo, J. M.; Kim, Y. B.; Han, H. W.

    2003-01-01

    The demand for safety and reliability of Nuclear Power Plants (NPPs) has been constantly increasing and economical operation is also an important issue. Developing and adopting predictive maintenance technology for the major systems or equipment is considered as a way to achieve these goals. This paper describes the development of a predictive maintenance system prototype for the Rod Control System, which adopts an advanced methodology. Bayesian Belief Networks (BBN) has been adopted for the real time fault diagnosis and prediction of the system. Through a simulation test, it was confirmed that the prototype monitors and secures sound operability of rod drive mechanism and its control system, and also provides the predictive maintenance information

  4. Remote control scanning electron microscope with Web operation

    International Nuclear Information System (INIS)

    Yamada, A.; Hirahara, O.; Date, M.; Lozbin, V.; Tsuchida, T.; Sugano, N.

    2002-01-01

    Full text: Recently, SEM (Scanning Electron Microscope) and the other observation instruments are coming to use a LAN (Local Area Network) to save the image in the database. We developed a remote control system in which SEM image and Control interface is indicated on the WEB Browser. In this system, SEM can be controlled by an external (client) PC installed in a general WEB Browser (Internet Explorer). Accordingly, operation interface can be indicated on the WEB browser. A JSM-6700F is connected to a LAN, and so a client PC can control the microscope. The JSM-6700F has two lines to the LAN for image transfer and communication with the SEM control. In order to transfer the image, the image size squeezes from 1280 x 1024-pixels (SEM image size) to 640x480-pixels for quick transfer. The image signal (640 x 480-pixels) is connected to the video server only, and then the image transfers to the client PC via LAN. The SEM control communicates with client PC for external command. On the other hand, the SEM control interface and the image are indicated on WEB Browser (Internet explorer). The SEM control interface is composed of the SEM image area and the SEM control part. The SEM image indicates the 640x480-pixels live image. This live image is being used as a high resolution live image transfer in the image transfer technology which a network is used for at present. If it is LAN beyond 10 base, this indication of an image can be transferred fully. When it is connected in the small line of the capacity, the refresh speed of the image becomes slow because of image data doesn't finish transferring it. In such a case, image size can be changed smaller by the LAN conditions. When a high quality image is necessary, the image of 1280 x 1024-pixels is saved on a SEM (server) side by choosing the image save button. At the same time, the file kept in SEM (server) is transferred to the client PC automatically, so that we can display a high quality image on the client PC side. The

  5. Versatile cable handling mechanisms for remote operator control

    Energy Technology Data Exchange (ETDEWEB)

    Collie, A.A.; White, T.S.; Christopher, M.D.; Hewer, N.D. [Portech Ltd., Portsmouth (United Kingdom)

    1996-12-31

    This paper describes a system of cable management for keeping the umbilical cables of remote operating vehicles and manipulators tidy and contained without direct intervention by operators. Two distinct types of winding mechanism have been designed. One mechanism is a fixed reel type where the cable is wound onto the reel by a rotating bail arm. The other mechanism consists of a pair of curved belts held against each other between which cable is passed. The complete system includes tension measuring and slack loop take-up devices. The whole system is controlled by a servo system in conjunction with a PC based visual graphic environment which allows a variety of mechanisms to be built up into a system able to handle up to four umbilical cables simultaneously. The control system provides additional tension sensors and cable odometers connected to the control system so that the operator has immediate perception of all the cable parameters, and by defining rules, can set up a variety of alarm situations. (Author).

  6. Versatile cable handling mechanisms for remote operator control

    International Nuclear Information System (INIS)

    Collie, A.A.; White, T.S.; Christopher, M.D.; Hewer, N.D.

    1996-01-01

    This paper describes a system of cable management for keeping the umbilical cables of remote operating vehicles and manipulators tidy and contained without direct intervention by operators. Two distinct types of winding mechanism have been designed. One mechanism is a fixed reel type where the cable is wound onto the reel by a rotating bail arm. The other mechanism consists of a pair of curved belts held against each other between which cable is passed. The complete system includes tension measuring and slack loop take-up devices. The whole system is controlled by a servo system in conjunction with a PC based visual graphic environment which allows a variety of mechanisms to be built up into a system able to handle up to four umbilical cables simultaneously. The control system provides additional tension sensors and cable odometers connected to the control system so that the operator has immediate perception of all the cable parameters, and by defining rules, can set up a variety of alarm situations. (Author)

  7. Versatile cable handling mechanisms for remote operator control

    International Nuclear Information System (INIS)

    Collie, A.A.; White, T.S.; Christopher, M.D.; Hewer, N.D.

    1996-01-01

    This paper describes a system of cable management for keeping the umbilical cables of remote operating vehicles and manipulators tidy and contained without direct intervention by operators. Two distinct types of winding mechanism have been designed. One mechanism is a fixed reel type where the cable is wound onto the reel by a rotating bail arm. The other mechanism consists of a pair of curved belts held against each other, between which cable is passed. The complete system includes tension measuring and slack loop take-up devices. The whole system is controlled by a servo system in conjunction with a PC based visual graphic environment which allows a variety of mechanisms to be built up into a system able to handle up to four umbilical cables simultaneously. The control system provides additional tension sensors and cable odometers connected to the control system so that the operator has immediate perception of all the cable parameters, and by defining rules, can set up a variety of alarm situations. (UK)

  8. Remote controlled gate controller using a GSM network and Arduino platform

    Directory of Open Access Journals (Sweden)

    Pospisilik Martin

    2016-01-01

    Full Text Available Most remote controllers for entrance gates operate on free frequencies 433 or 868 MHz. However, this technology limits the user comfort, as it is usually not common that bi-directional communication is established. A higher comfort of controlling the entrance gates can be achieved by employing the GSM network for transmission of commands and messages between the gate controller and the user. In this case, only a conventional GSM cellular phone is needed to control the gate. A description of such a controller based on the GSM module and Arduino controller is provided in this paper.

  9. State-of-the-art Model M-2 Maintenance System

    International Nuclear Information System (INIS)

    Herndon, J.N.; Martin, H.L.; Satterlee, P.E. Jr.; Jelatis, D.G.; Jennrich, C.E.

    1984-04-01

    The Model M-2 Maintenance System is part of an ongoing program within the Consolidated Fuel Reprocessing Program (CFRP) at Oak Ridge National Laboratory (ORNL) to improve remote manipulation technology for future nuclear fuel reprocessing and other remote applications. Techniques, equipment, and guidelines which can improve the efficiency of remote maintenance are being developed. The Model M-2 Maintenance System, installed in the Integrated Equipment Test (IET) Facility at ORNL, provides a complete, integrated remote maintenance system for the demonstration and development of remote maintenance techniques. The system comprises a pair of force-reflecting servomanipulator arms, television viewing, lighting, and auxiliary lifting capabilities, thereby allowing manlike maintenance operations to be executed remotely within the remote cell mockup area in the IET. The Model M-2 Maintenance System incorporates an upgraded version of the proven Central Research Laboratories' Model M servomanipulator. Included are state-of-the-art brushless dc servomotors for improved performance, remotely removable wrist assemblies, geared azimuth drive, and a distributed microprocessor-based digital control system. 5 references, 8 figures

  10. Research on wireless remote control scheme for the water source well of a uranium mine

    International Nuclear Information System (INIS)

    Wang Yun; Bao Feng

    2013-01-01

    Traditional wired electrical control method is applicable to simple control for the short-distance industrial equipment, but it is not suitable for the water source well of uranium mines requiring remote control. A kind of wireless remote control system based on high-speed radio modem communication technology was presented for the water source wells of a uranium mine, and the water source wells can be remotely controlled with the system. The component, implementation and characteristics of the control system are introduced. (authors)

  11. Network communication for remote technology and NDT controls on current nuclear power plants

    International Nuclear Information System (INIS)

    Capitaine, A.

    2001-01-01

    Among the most important targets for ''UTILITIES'' are to increase nuclear power plant availability and reduce the workers dosimetry. A possible way to reach these targets is to reduce the duration of the refueling period and to limit the number of operators in the work areas It is necessary to use remote technology and to provide much equipment to support the main activities during refueling. Remote technology is a possible solution to remove operators from the maintenance area. The main activities concerned are the NDT inspection on the primary components and fuel handling system. Recent progress on remote technology made by the electronic industry and network communication has increased their capacities. It is easier now to use them, and more and more people are familiar with these technologies. Internet, manufacturing, supervision, and surgery use these technologies. Now it seems appropriate to examine these technologies for current maintenance in nuclear plants. Remote technologies and communication network can help to solve current difficulties in the maintenance field and dosimetry limits. For a long time, many people thought that the cost and the difficulty of applying new technologies would be not extremely expensive, but this is no longer the case. Now with the first feed back we can show that these technologies are a good answer for increased availability and reduction of dosimetry. (author)

  12. Network communication for remote technology and NDT controls on current nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Capitaine, A. [Electricite de France, 92 - Clamart (France). Service Etudes et Projets Thermiques et Nucleaires

    2001-07-01

    Among the most important targets for ''UTILITIES'' are to increase nuclear power plant availability and reduce the workers dosimetry. A possible way to reach these targets is to reduce the duration of the refueling period and to limit the number of operators in the work areas It is necessary to use remote technology and to provide much equipment to support the main activities during refueling. Remote technology is a possible solution to remove operators from the maintenance area. The main activities concerned are the NDT inspection on the primary components and fuel handling system. Recent progress on remote technology made by the electronic industry and network communication has increased their capacities. It is easier now to use them, and more and more people are familiar with these technologies. Internet, manufacturing, supervision, and surgery use these technologies. Now it seems appropriate to examine these technologies for current maintenance in nuclear plants. Remote technologies and communication network can help to solve current difficulties in the maintenance field and dosimetry limits. For a long time, many people thought that the cost and the difficulty of applying new technologies would be not extremely expensive, but this is no longer the case. Now with the first feed back we can show that these technologies are a good answer for increased availability and reduction of dosimetry. (author)

  13. Mini-remote-control Antenna for On-body Wireless Communication Systems

    DEFF Research Database (Denmark)

    Larsen, Lauge K.; Kvist, Søren Helstrup; Yatman, William H.

    2012-01-01

    Two commercially available, compact antennas are evaluated for use in a small 55mm 39mm 15mm Remote Control (RC). The influence of the body on the path gain (jS21j) at 2:45 GHz between the remote control and a monopole parallel to the side of the head is evaluated. The measurements are made on two...

  14. Remote Control Childhood: Combating the Hazards of Media Culture in Schools

    Science.gov (United States)

    Levin, Diane

    2010-01-01

    Background: Media culture touches most aspects of the lives of children growing up today, beginning at the earliest ages. It is profoundly the lessons children learn as well as how they learn, thereby contributing to what this article characterizes as "remote control childhood." Educators need to understand remote control childhood so…

  15. Man/machine interface for a nuclear cask remote handling control station: system design requirements

    International Nuclear Information System (INIS)

    Clarke, M.M.; Kreifeldt, J.G.; Draper, J.V.

    1984-01-01

    Design requirements are presented for a control station of a proposed semi-automated facility for remote handling of nuclear waste casks. Functional and operational man/machine interface: controls, displays, software format, station architecture, and work environment. In addition, some input is given to the design of remote sensing systems in the cask handling areas. 18 references, 9 figures, 12 tables

  16. Estimating the Infrared Radiation Wavelength Emitted by a Remote Control Device Using a Digital Camera

    Science.gov (United States)

    Catelli, Francisco; Giovannini, Odilon; Bolzan, Vicente Dall Agnol

    2011-01-01

    The interference fringes produced by a diffraction grating illuminated with radiation from a TV remote control and a red laser beam are, simultaneously, captured by a digital camera. Based on an image with two interference patterns, an estimate of the infrared radiation wavelength emitted by a TV remote control is made. (Contains 4 figures.)

  17. Maintenance of Process Control Algorithms based on Dynamic Program Slicing

    DEFF Research Database (Denmark)

    Hansen, Ole Fink; Andersen, Nils Axel; Ravn, Ole

    2010-01-01

    Today’s industrial control systems gradually lose performance after installation and must be regularly maintained by means of adjusting parameters and modifying the control algorithm, in order to regain high performance. Industrial control algorithms are complex software systems, and it is partic...

  18. SCAN- a maintenance-free flowrate meter with direct digital read-out for computerised control applications in radiochemical plants

    Energy Technology Data Exchange (ETDEWEB)

    Shah, B V; Siddiqui, I A; Theyyunni, T K [Process Engineering and Systems Division, Bhabha Atomic Research Centre, Mumbai (India)

    1994-06-01

    In radiochemical plants, the choice of flowrate sensor is subject to stringent requirements of fail-safe design and freedom from maintenance. The SCAN remote digital direct indicating flowrate meter described in this paper was developed to meet the requirements of flowrate and transmitting it to the control room, and to a computerised control system. SCAN is designed on the principle that flowrate through an orifice is a function of the head of liquid acting upon it. SCAN consists of a small chamber which receives the flow, and discharges it through an orifice located in bottom. The level of liquid in the pot represents the flowrate of the input stream. SCAN has been developed into an accurate, rugged and practical device by refinements in the design of internals, and by introducing a special end-section which makes the calibration insensitive to location. An important feature of SCAN is that it is passive, maintenance free, fail-safe device and contains no moving parts. There is no liquid hold up in the SCAN when idle, which is a desirable feature for the radiochemical plant environment. (author). 3 figs., 2 tabs.

  19. Remote controlled stud bolt handling device for reactor pressure vessel

    International Nuclear Information System (INIS)

    Shindo, Takenori; Shigehiro, Katsuya; Ito, Morio; Okada, Kenji

    1988-01-01

    In nuclear power stations, at the time of regular inspection, the works of opening and fixing the upper covers of reactor pressure vessels are carried out for inspecting the inside of reactor pressure vessels and exchanging fuel rods. These upper covers are fastened with many stud bolts, therefore, the works of opening and fixing require a large amount of labor, and are done under the restricted condition of wearing protective clothings and masks. Babcock Hitachi K.K. has completed the development of a remotely controlled automatic bolt tightenig device for this purpose, therefore, its outline is reported. The conventional method of these works and the problems in it are described. The design of the new device aimed at the parallel execution of cleaning screw threads, loosening and tightening nuts, and taking off and putting on nuts and washers, thus contributing to the shortening of regular inspection period, the reduction of the radiation exposure of workers, and the decrease of the number of workers. The function, reliability and endurance of the new device were confirmed by the verifying test using a device made for trial. The device is composed of a stand, a rail and four stations each with a cleaning unit, a stud tensioner and a nut handling unit. (K.I.)

  20. Development and maintenance of the Hanford Site Radiological Control Manual

    International Nuclear Information System (INIS)

    Munson, L.H.; Selby, J.M.; Vargo, G.J.; Clark, D.L.

    1993-04-01

    In June 1992 the US Department of Energy (DOE) issued DOE N5480.6, Radiological Control, which set forth DOE's Radiological Control Program and established the framework for its implementation at sites nationwide. Accompanying the Order was the DOE Radiological Control Manual (DOE RCM), which provided the detailed requirements for the program. The Order also mandated Field Office issuance of site-specific radiological control manuals by December 1, 1992. This paper presents the approach taken to develop, review, approve, implement, and subsequently maintain the site-specific manual for the DOE Richland Field Office (RL) at Hanford Site

  1. Remote control radioactive-waste removal system uses modulated laser transmitter

    Science.gov (United States)

    Burcher, E. E.; Kopia, L. P.; Rowland, C. W.; Sinclair, A. R.

    1971-01-01

    Laser remote control system consists of transmitter, auto tracker, and receiver. Transmitter and tracker, packaged together and bore sighted, constitute control station, receiver is slave station. Model has five command channels and optical link operating range of 110 m.

  2. Study on remote control technology of airflow during a mine fire

    Energy Technology Data Exchange (ETDEWEB)

    Wang, D.; Wang, Y; Zhou, Y.; Zhou, F. [China University of Mining and Technology, Jiangsu (China). College of Mineral and Energy Resource

    2001-07-01

    In order to realize remote control of airflow during a mine fire and minimize fire losses, two kinds of the airflow remote control systems have been developed. One uses compressed air as power source, and transmits control signals by a monitor system for mine environment. Another uses electric power and transmits control signals through a telephone network underground. The mine door controllers of the remote airflow controlling systems are developed with a single-chip microcomputer. Then the controller can not only do logical analysis and judgement, but also has a strong anti-disturb ability and sufficient reliability. The two kinds of airflow remote control system have been successfully applied in some coal mines in China. Their effects of running are very good. 2 refs., 5 figs.

  3. Deft Control Software (DCS) for Remote Robotic Operations with Underlying Structure, Phase I

    Data.gov (United States)

    National Aeronautics and Space Administration — BluHaptics proposes Deft Control Software (DCS), which utilizes machine learning to enable intuitive and efficient control of robotic arms in remote operations with...

  4. Electrical power supply and controls for a remotely operated glass melter for nuclear waste

    International Nuclear Information System (INIS)

    Haideri, A.Q.

    1985-01-01

    An electrical power supply, controls and instruments used for a joule heated glass melter for nuclear waste are discussed. Remotely replaceable interconnection wiring assemblies for power, controls and instruments are also described

  5. Space teleoperation research. American Nuclear Society Executive conference: Remote operations and robotics in the nuclear industry; remote maintenance in other hostile environments

    Science.gov (United States)

    Meintel, A. J., Jr.; Will, R. W.

    1985-01-01

    This presentation consists of four sections. The first section is a brief introduction to the NASA Space Program. The second portion summarized the results of a congressionally mandated study of automation and robotics for space station. The third portion presents a number of concepts for space teleoperator systems. The remainder of the presentation describes Langley Research Center's teleoperator/robotic research to support remote space operations.

  6. Development of a compact and user-friendly ion irradiation system controlled remotely through the internet

    International Nuclear Information System (INIS)

    Ishikawa, Ippei; Kada, Wataru; Sato, Fuminobu; Kato, Yushi; Iida, Toshiyuki; Tanaka, Teruya; Yamamoto, Junji

    2007-01-01

    A compact and user-friendly ion irradiation system controlled remotely through the Internet was developed for the execution of collaboration experiments together with researchers at remote sites. Several hardware instruments and software programs were constructed and provided for the remote control of the system and for its connection to the Internet. Surface modification and analysis experiments with this system were remotely performed through the Internet. It was confirmed from the experiments that the present ion irradiation system was precisely controlled through the Internet and could be easily and safely used for the surface modification and analysis, that the normal communication speed of around 10 Mbps for the Internet was fast enough for the execution of such typical remote-controlled experiments, and also that an access to the system by a mobile phone was convenient and useful enough to check the condition of the system and experimental data. (author)

  7. Remotely controllable WDM-PON technology for wireless fronthaul/backhaul application

    DEFF Research Database (Denmark)

    Eiselt, Michael H.; Wagner, Christoph; Lawin, Mirko

    2016-01-01

    Low-cost WDM-PON solutions for fronthaul and backhaul applications will include remotely controlled tail-end transceivers. We report on control aspects of these transceivers and how standardization is evolving to enable these applications.......Low-cost WDM-PON solutions for fronthaul and backhaul applications will include remotely controlled tail-end transceivers. We report on control aspects of these transceivers and how standardization is evolving to enable these applications....

  8. Maintenance standards, care and control of the radiation protection material

    International Nuclear Information System (INIS)

    Brasesco, L.

    2004-01-01

    The present protocol in Radiology, Tomography, surgical block and intensive care unit in the Britanic Hospital from Uruguay.Between their topics find care procedures in protective clothes, periodic and control methods, material record,and staff assigned

  9. Remote Control of TJ-II Diagnostics; Control Remoto de Diagnosticos del Dispositivo TJ-II

    Energy Technology Data Exchange (ETDEWEB)

    Lopez Sanchez, A.; Vega, J.; Montoro, A.; Encabo, J.

    2001-07-01

    The present paper is about the design and development of ten remote control diagnostic systems used in the study of plasma fusion in the TJ-II device installed at CIEMAT. This development goes from the definition of sensors and devices necessary in carrying out these remote controls, to its assembly, wiring, development of electronic circuits inserted between sensors and PLC, development of programs for these PLC, connections and administration of the real time automation network, and later development of the necessary programs via the appropriate software tools for web access through a navigator to a specific web page, allowing visual and real time access over the auxiliary systems that make up all the diagnostics. (Author)

  10. 24-channel dual microcontroller-based voltage controller for ion optics remote control

    Science.gov (United States)

    Bengtsson, L.

    2018-05-01

    The design of a 24-channel voltage control instrument for Wenzel Elektronik N1130 NIM modules is described. This instrument is remote controlled from a LabVIEW GUI on a host Windows computer and is intended for ion optics control in electron affinity measurements on negative ions at the CERN-ISOLDE facility. Each channel has a resolution of 12 bits and has a normally distributed noise with a standard deviation of <1 mV. The instrument is designed as a standard 2-unit NIM module where the electronic hardware consists of a printed circuit board with two asynchronously operating microcontrollers.

  11. A remote control system to offer information for nuclear power plant operation

    International Nuclear Information System (INIS)

    Ohga, Yukiharu; Yuchi, Hiroyuki; Arita, Setsuo

    1995-01-01

    A new man-machine system was proposed to simplify input operation so as to get needed plant information and to control information items and output devices for the operator crew, working in a control room. The system controls the shared information for the operator crew, on a large screen display, and private information for individual operators and maintenance personnel, on CRTs, based on the speech input and remote pointing input to the large screen display by a portable pointer, which emits laser beams. The system recognizes the indicating point of the pointer beam by processing the image on the large screen as obtained by an ITV camera. An infrared laser beam and a camera with a visible ray cut filter are used to remove distortion of the image caused by lens aberration, etc. and to provide rapid image processing. The operator performs the input operation while monitoring a cursor displayed by the system. The information items offered and their output devices are automatically determined according to the input operator. A prototype system was developed using three CRTs, one of which served as a substitute for the large screen display. Input to the system is performed using a speech input device and three kinds of pointers; each pointer is identified during image processing based on the number of laser beams emitted. The evaluation test confirmed that precise and smooth input by pointers as well as arbitrary combinations with speech input realized natural dialog without being aware of any waiting time. The appropriate information items were offered to output devices, CRTs and the speech output device, according to the pointers used, namely the input operators. The system can simplify input operation and effectively control the offered information items and output devices in a plant control room. (author)

  12. Weight loss maintenance in relation to locus of control: The MedWeight study.

    Science.gov (United States)

    Anastasiou, Costas A; Fappa, Evaggelia; Karfopoulou, Eleni; Gkza, Anastasia; Yannakoulia, Mary

    2015-08-01

    Locus of control, i.e. the degree of an individual's belief on the control of his/her life, has been related to many health outcomes, including weight loss in overweight/obese individuals. No information is available on the impact of locus of control in maintaining weight loss. We aimed to investigate the effect of locus of control in weight loss maintenance and explore potential associations with lifestyle factors. Study participants included 239 individuals (41% males) who had lost at least 10% of body weight in the past and either maintained the loss (maintainers: weight maintenance of at least 10% of initial weight) or regained it (regainers). Locus of control was defined by a relevant multi-dimensional scale; participants were categorised to internals and externals, based on "internal" and "others" sub-scales. A significant interaction was found between locus of control and weight loss maintenance status (p locus of control. Individualised treatment, according to locus of control, may increase weight loss maintenance rates in former overweight/obese individuals. Copyright © 2015 Elsevier Ltd. All rights reserved.

  13. System maintenance test plan for the TWRS controlled baseline database system

    International Nuclear Information System (INIS)

    Spencer, S.G.

    1998-01-01

    TWRS [Tank Waste Remediation System] Controlled Baseline Database, formally known as the Performance Measurement Control System, is used to track and monitor TWRS project management baseline information. This document contains the maintenance testing approach for software testing of the TCBD system once SCR/PRs are implemented

  14. Web Environment for Programming and Control of a Mobile Robot in a Remote Laboratory

    Science.gov (United States)

    dos Santos Lopes, Maísa Soares; Gomes, Iago Pacheco; Trindade, Roque M. P.; da Silva, Alzira F.; de C. Lima, Antonio C.

    2017-01-01

    Remote robotics laboratories have been successfully used for engineering education. However, few of them use mobile robots to to teach computer science. This article describes a mobile robot Control and Programming Environment (CPE) and its pedagogical applications. The system comprises a remote laboratory for robotics, an online programming tool,…

  15. Control of occupational exposure using remote monitoring systems

    Energy Technology Data Exchange (ETDEWEB)

    Lunn, M. P. [British Energy Generation Ltd. Sizewell B Power Station, Leiston, Suffolk (United Kingdom)

    2004-07-01

    Advances in electronic dosimetry, portable radio technology and digital video have enabled the development of Remote Monitoring Systems (RMS) that provide a powerful dose control tool for the Operational Health Physicist. North American utilities have led the implementation of these systems, often with coverage of the entire plant, feeding back to a centralized control room. These large-scale systems typically cost around EURO 500,000. In Europe, and especially the UK, implementation of RMS technology has been slower and on a smaller scale. US utilities have justified the high capital cost of their systems by significantly reducing the number of contract RP technicians required during refuelling outages, saving up to EURO 1,000,000. In the UK, the number of contract RP technicians employed during outages is already minimal, and with the generally low dose rates found on Gas-Cooled Reactors, RP engineers have traditionally considered RMS to be an extravagance. However, the commissioning of the UK's first PWR and a significant increase in the number of AGR Vessel entries, have increased the radiological protection challenges facing the British Health Physicist, thus prompting a re-evaluation of this view. The benefit derived from a system that combines telemetry, video and voice communications is synergistic. We found that the system can be used in a variety of ways to significantly enhance radiological protection control in high radiation areas and to significantly reduce the dose received by RP staff covering such jobs. Indeed, it is estimated that the use of RMS saved at least 10 man.mSv of Radiological Protection dose during RF06 However, it is important to note that RMS is a monitoring tool to support existing monitoring techniques and arrangements. Suitably qualified and experienced staff are required to interpret the data and provide suitable advice to the work party. In addition, detailed training on the limitations of RMS, explicit procedures for

  16. Development of Ethernet Based Remote Monitoring and Controlling of MST Radar Transmitters using ARM Cortex Microcontroller

    Directory of Open Access Journals (Sweden)

    Lakshmi Narayana ROSHANNA

    2013-01-01

    Full Text Available The recently emerging Web Services technology has provided a new and excellent solution to Industrial Automation in online control and remote monitoring. In this paper, a Web Service Based Remote Monitoring & Controlling of Radar Transmitters for safety management (WMCT developed for MST Radar is described. It achieved the MST radar transmitters’ remote supervisory, data logging and controlling activities. The system is developed using an ARM Cortex M3 processor to monitor and control the 32 triode-based transmitters of the 53-MHz Radar. The system controls transmitters via the internet using an Ethernet client server and store health status in the Database for radar performance analysis. The system enables scientists to operate and control the radar transmitters from a remote client machine Webpage.

  17. New design centrifugal contactor remotely controlled for solvent extraction operations for feed clarification

    International Nuclear Information System (INIS)

    Candelieri, T.; Gerardi, A.; Petrigliano, G.; Siepe, V.

    1987-01-01

    The project concept of the nuclear facilities has gone through an important evolution in the past years in relation to the need of: garantiing the remote maintenance reducing workers exposure when operating in high-risk areas; making easier final decommissioning operations of the plants. In this way the ITREC pilot plant (built in 1970s') for its modular characteristic based on Rack Removal System (R.R.S.) was the first example of this new concept of project. A further development, in the field of remote maintenance and decommissioning operations, we can obtain associating to the R.R.S. concept that of projecting the single components (only for the critical ones) remotely demountable in their higher radioactive parts to consent the maintenance-substitution and/or decommissioning operations without interfering with remaining parts of the plant which it is connected. All of this helps in the realization of the aim making better plant operations reducing drastically work time and therefore non-functioning period of the plants. These principles have been applicated in the realization of two important components in reprocessing plant: the centrifugal contactor for solvent extraction and feed clarification centrifuge

  18. Maintenance cost control at the Pacific Missile Test Center.

    OpenAIRE

    Jenson, Richard J.

    1980-01-01

    Approved for public release; distribution is unlimited The Pacific Missile Test Center (PMTC) is the Navy's largest Major Range and Test Facility Base, with an investment of over one billion dollars. The majority of this investment is in range test equipment and facilities including radar, telemetry, communication and command/ control systems. Concern is growing over the "excessively obsolete condition of PMTC technical equipment." Improvement of factors concerned with...

  19. Consistency maintenance for constraint in role-based access control model

    Institute of Scientific and Technical Information of China (English)

    韩伟力; 陈刚; 尹建伟; 董金祥

    2002-01-01

    Constraint is an important aspect of role-based access control and is sometimes argued to be the principal motivation for role-based access control (RBAC). But so far few authors have discussed consistency maintenance for constraint in RBAC model. Based on researches of constraints among roles and types of inconsistency among constraints, this paper introduces corresponding formal rules, rule-based reasoning and corresponding methods to detect, avoid and resolve these inconsistencies. Finally, the paper introduces briefly the application of consistency maintenance in ZD-PDM, an enterprise-oriented product data management (PDM) system.

  20. Consistency maintenance for constraint in role-based access control model

    Institute of Scientific and Technical Information of China (English)

    韩伟力; 陈刚; 尹建伟; 董金祥

    2002-01-01

    Constraint is an important aspect of role-based access control and is sometimes argued to be the principal motivation for role-based access control (RBAC). But so far'few authors have discussed consistency maintenance for constraint in RBAC model. Based on researches of constraints among roles and types of inconsistency among constraints, this paper introduces correaponding formal rules, rulebased reasoning and corresponding methods to detect, avoid and resolve these inconsistencies. Finally,the paper introduces briefly the application of consistency maintenance in ZD-PDM, an enterprise-ori-ented product data management (PDM) system.

  1. Distributed process control system for remote control and monitoring of the TFTR tritium systems

    International Nuclear Information System (INIS)

    Schobert, G.; Arnold, N.; Bashore, D.; Mika, R.; Oliaro, G.

    1989-01-01

    This paper reviews the progress made in the application of a commercially available distributed process control system to support the requirements established for the Tritium REmote Control And Monitoring System (TRECAMS) of the Tokamak Fusion Test REactor (TFTR). The system that will discussed was purchased from Texas (TI) Instruments Automation Controls Division), previously marketed by Rexnord Automation. It consists of three, fully redundant, distributed process controllers interfaced to over 1800 analog and digital I/O points. The operator consoles located throughout the facility are supported by four Digital Equipment Corporation (DEC) PDP-11/73 computers. The PDP-11/73's and the three process controllers communicate over a fully redundant one megabaud fiber optic network. All system functionality is based on a set of completely integrated databases loaded to the process controllers and the PDP-11/73's. (author). 2 refs.; 2 figs

  2. Job maintenance through Supported Employment PLUS: A randomized controlled trial

    Directory of Open Access Journals (Sweden)

    Nils-Torge Telle

    2016-09-01

    Full Text Available Sickness absence from work due to experienced distress and mental health issues has continuously increased over the past years in Germany. To investigate how this alarming development can be counteracted, we conducted a randomized controlled trial evaluating a job coaching intervention to maintain the working capacity of members of staff and ultimately prevent sickness absence. Our sample included N = 99 employees who reported mental distress due to work-related problems. The intervention group (n = 58 received between 8 and 12 individual job coaching sessions in which they worked with a professional job coach to reduce their mental distress. The control group (n = 41 received a brochure about mental distress. Data were collected before the start of the study, at the end of the job coaching intervention and at a 3-month follow up. These data included the number of sickness absence days as the primary outcome and questionnaire measures to assess burnout indicators, life satisfaction and work-related experiences and behaviors. Compared with the control group, the results indicated no reduction in sickness absence in the intervention group but fewer depressive symptoms, a heightened ability of the participants to distance themselves from work, more experience of work-related success, less depletion of emotional resources and a greater satisfaction with life when participants had received the job coaching. Thus, although we could not detect a reduction in sickness absence between the groups, job coaching was shown to be a viable intervention technique to benefit employees by contributing to re-establish their mental health. We discuss the implications of the study and outline future research.

  3. Job Maintenance through Supported Employment PLUS: A Randomized Controlled Trial.

    Science.gov (United States)

    Telle, Nils-Torge; Moock, Jörn; Heuchert, Sandra; Schulte, Vivian; Rössler, Wulf; Kawohl, Wolfram

    2016-01-01

    Sickness absence from work due to experienced distress and mental health issues has continuously increased over the past years in Germany. To investigate how this alarming development can be counteracted, we conducted a randomized controlled trial evaluating a job coaching intervention to maintain the working capacity of members of staff and ultimately prevent sickness absence. Our sample included N  = 99 employees who reported mental distress due to work-related problems. The intervention group ( n  = 58) received between 8 and 12 individual job coaching sessions in which they worked with a professional job coach to reduce their mental distress. The control group ( n  = 41) received a brochure about mental distress. Data were collected before the start of the study, at the end of the job coaching intervention, and at a 3-month follow-up. These data included the number of sickness absence days as the primary outcome and questionnaire measures to assess burnout indicators, life satisfaction, and work-related experiences and behaviors. Compared with the control group, the results indicated no reduction in sickness absence in the intervention group but fewer depressive symptoms, a heightened ability of the participants to distance themselves from work, more experience of work-related success, less depletion of emotional resources, and a greater satisfaction with life when participants had received the job coaching. Thus, although we could not detect a reduction in sickness absence between the groups, job coaching was shown to be a viable intervention technique to benefit employees by contributing to re-establish their mental health. We discuss the implications of the study and outline future research.

  4. The remote methods for radwaste and SNF control

    International Nuclear Information System (INIS)

    Ivanov, O; Stepanov, V; Danilovich, A; Potapov, V

    2017-01-01

    With the examples of developments carried out in the Kurchatov Institute and by the world leaders in the field the presentation considers the devices and methods to obtain remotely information on the distribution of radioactivity in radwaste and SNF. It describes the different types of light portable gamma cameras. The application of scanning spectrometric systems is considers also. The methods of recording UV radiation for detection of alpha contamination with the luminescence of air are presented. We discuss the scope and tasks that can be solved using remote and non-destructive methods. (paper)

  5. Development of a remote controlled fatigue testing apparatus at elevated temperature in controlled environment

    International Nuclear Information System (INIS)

    Ohmi, Masao; Mimura, Hideaki; Ishii, Toshimitsu

    1996-02-01

    The fatigue characteristics of reactor structural materials at high temperature are necessary to be evaluated for ensuring the safety of the High Temperature engineering Test Reactor (HTTR). Especially, the high temperature test data on safety research such as low cycle fatigue property and crack propagation property for reactor pressure vessel material are important for the development of the HTTR. Responding to these needs, a remote controlled type fatigue testing machine has been developed and installed in a hot cell of JMTR Hot Laboratory to get the fatigue data of irradiated materials. The machine was developed modifying a commercially available electro-hydraulic servo type fatigue testing machine to withstand radiation and be remotely operated, and mainly consists of a testing machine frame, environment chamber, extensometer, actuator and vacuum exhaust system. It has been confirmed that the machine has good performance to obtain low cycle fatigue data through many demonstration tests on unirradiated and irradiated specimens. (author)

  6. Measurement and control system for the ITER remote handling mock-up test

    International Nuclear Information System (INIS)

    Oka, K.; Kakudate, S.; Takiguchi, Y.; Ako, K.; Taguchi, K.; Tada, E.; Ozaki, F.; Shibanuma, K.

    1998-01-01

    The mock-up test platforms composed of full-scale remote handling (RH) equipment were developed for demonstrating remote replacement of the ITER blanket and divertor. In parallel, the measurement and control system for operating these RH equipment were constructed on the basis of open architecture with object oriented feature, aiming at realization of fully-remoted automatic operation required for ITER. This paper describes the design concept of the measurement and control system for the remote handling equipment of ITER, and outlines the measured performances of the fabricated measurement system for the remote handling mock-up tests, which includes Data Acquisition System (DAS), Visual Monitoring System (VMS) and Virtual Reality System (VRS). (authors)

  7. Future-oriented maintenance strategy based on automated processes is finding its way into large astronomical facilities at remote observing sites

    Science.gov (United States)

    Silber, Armin; Gonzalez, Christian; Pino, Francisco; Escarate, Patricio; Gairing, Stefan

    2014-08-01

    With expanding sizes and increasing complexity of large astronomical observatories on remote observing sites, the call for an efficient and recourses saving maintenance concept becomes louder. The increasing number of subsystems on telescopes and instruments forces large observatories, like in industries, to rethink conventional maintenance strategies for reaching this demanding goal. The implementation of full-, or semi-automatic processes for standard service activities can help to keep the number of operating staff on an efficient level and to reduce significantly the consumption of valuable consumables or equipment. In this contribution we will demonstrate on the example of the 80 Cryogenic subsystems of the ALMA Front End instrument, how an implemented automatic service process increases the availability of spare parts and Line Replaceable Units. Furthermore how valuable staff recourses can be freed from continuous repetitive maintenance activities, to allow focusing more on system diagnostic tasks, troubleshooting and the interchanging of line replaceable units. The required service activities are decoupled from the day-to-day work, eliminating dependencies on workload peaks or logistic constrains. The automatic refurbishing processes running in parallel to the operational tasks with constant quality and without compromising the performance of the serviced system components. Consequentially that results in an efficiency increase, less down time and keeps the observing schedule on track. Automatic service processes in combination with proactive maintenance concepts are providing the necessary flexibility for the complex operational work structures of large observatories. The gained planning flexibility is allowing an optimization of operational procedures and sequences by considering the required cost efficiency.

  8. Remote control of restricted sets of operations: Teleportation of angles

    International Nuclear Information System (INIS)

    Huelga, S.F.; Vaccaro, J.A.; Plenio, M.B.

    2002-01-01

    We study the remote implementation of a unitary transformation on the state of a qubit. We show the existence of nontrivial protocols (i.e., using less resources than bidirectional state teleportation) that allow the perfect remote implementation of certain continuous sets of quantum operations. We prove that, up to a local change of basis, only two subsets exist that can be implemented remotely with a nontrivial protocol: Arbitrary rotations around a fixed direction n-vector and a π rotation about an arbitrary direction lying in a plane orthogonal to n-vector. The former operations effectively constitute the teleportation of arbitrary angles. The overall classical information and distributed entanglement cost required for the remote implementation depends on whether it is known, a priori, in which of the two teleportable subsets the transformation belongs. If it is known, the optimal protocol consumes one e-bit of entanglement and one c-bit in each direction. If it is not known in which subset the transformation belongs, two e-bits of entanglement need to be consumed and the classical channel becomes asymmetric with two c-bits being conveyed from Alice to Bob but only one from Bob to Alice

  9. Remote observing from the bottom up: the architecture of the WIYN telescope control system

    Science.gov (United States)

    Percival, Jeffrey W.

    1995-06-01

    Remote observing has many definitions, ranging from unattended batch-mode use through simple remote logins to fully faithful off-site observing centers indistinguishable from the on- site telescope control room. There are problems with each of these ideas: batch mode operation, for example, precludes remote interactive target acquisition and remote access to targets of opportunity. Simple remote login suffers from network problems such as full-duplex character latency; shipping screens instead of the underlying data can cause bandwidth problems and interferes with analyzing or archiving data. Brute-force reproduction of the control room requires expensive fiber or satellite connections. The WIYN Telescope control system was designed to be inexpensive to build and inexpensive to maintain. We emphasized the use of standard tools, portable implementations, and network friendliness. These techniques and features are precisely those that underlie a powerful remote observing capability. The WIYN Telescope control system therefore supports remote observing from the very lowest levels, and does so effectively and inexpensively using a carefully planned architecture, standard software and network tools, and innovative methods to ship large digital images over low bandwidth connections such as phone lines. Even before the construction was complete, these techniques proved their value by allowing remote access for the purposes of eavesdropping, troubleshooting, and servo tuning. This paper presents a block diagram and detailed descriptions of the WIYN Telescope control system architecture. Each aspect of the control system is discussed with respect to its contribution to the overall goal of remote observing, including multi-user access, bandwidth conservation, interoperability, and portability.

  10. Remote Supervision and Control of Air Conditioning Systems in Different Modes

    Science.gov (United States)

    Rafeeq, Mohammed; Afzal, Asif; Rajendra, Sree

    2018-01-01

    In the era of automation, most of the application of engineering and science are interrelated with system for optimal operation. To get the efficient result of an operation and desired response, interconnected systems should be controlled by directing, regulating and commanding. Here, air conditioning (AC) system is considered for experimentation, to supervise and control its functioning in both, automated and manual mode. This paper reports the work intended to design and develop an automated and manual AC system working in remote and local mode, to increase the level of comfort, easy operation, reducing human intervention and faults occurring in the system. The Programmable Logical Controller (PLC) and Supervisory Control and Data Acquisition (SCADA) system were used for remote supervision and monitoring of AC systems using series ninety protocol and remote terminal unit modbus protocol as communication module to operate in remote mode. PLC was used as remote terminal for continuous supervision and control of AC system. SCADA software was used as a tool for designing user friendly graphical user interface. The proposed SCADA AC system successfully monitors and controls in accordance within the parameter limits like temperature, pressure, humidity and voltage. With all the features, this designed system is capable of efficient handling of the resources like the compressor, humidifier etc., with all the levels of safety and durability. This system also maintains the temperature and controls the humidity of the remote location and also looks after the health of the compressor.

  11. Test of remote control cutting equipment by Nd:YAG laser

    Energy Technology Data Exchange (ETDEWEB)

    Shimizu, Akio [Fuji Electric Corp. Research and Development Ltd., Yokosuka, Kanagawa (Japan); Hosoda, Hiroshi

    1997-11-01

    Technology of remote controlled cutting and reduction of generative secondary products have been required to the cutting system for decommissioning nuclear equipments. At a point of view that laser cutting technology by use of a Nd:YAG laser is effective, we have developed the laser cutting machine and carried out cutting tests for several stainless steel plates. This report is described the result of experiment by test equipment, about element technology of remote controlled cutting nuclear equipments. (author)

  12. Research prototype of remote controlled engineering vehicle system for CBRN threat. Phase 2

    International Nuclear Information System (INIS)

    Uemura, Keisuke; Naruse, Masahiro; Shigematsu, Kosuke; Morishita, Masahiro

    2015-01-01

    This research was triggered by the nuclear accident that successively happened after the Great East Japan Earthquake. The project focuses on the Remote Controlled Engineering Vehicle System that can be used for multi purposes such as debris/obstacle clearing operation, various reconnaissance operation, under CBRN threat. In this report, we describe research prototype of remote controlled engineering vehicle system for CBRN threat (phase 2). (author)

  13. Test of remote control cutting equipment by Nd:YAG laser

    International Nuclear Information System (INIS)

    Shimizu, Akio; Hosoda, Hiroshi.

    1997-01-01

    Technology of remote controlled cutting and reduction of generative secondary products have been required to the cutting system for decommissioning nuclear equipments. At a point of view that laser cutting technology by use of a Nd:YAG laser is effective, we have developed the laser cutting machine and carried out cutting tests for several stainless steel plates. This report is described the result of experiment by test equipment, about element technology of remote controlled cutting nuclear equipments. (author)

  14. Maintenance of medical nuclear equipment. A proposal for quality control in radiotherapy

    International Nuclear Information System (INIS)

    Becker, Paulo H.B.

    1996-01-01

    A project of quality control in radiotherapy that is been implemented by Instituto de Radioprotecao e Dosimetria from Brazilian National Energy Commission (CNEN) in cooperation with International Atomic Energy Agency is described. The establishment of a laboratory for the maintenance of medical dosemeters is proposed

  15. 40 CFR 63.2251 - What are the requirements for the routine control device maintenance exemption?

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 12 2010-07-01 2010-07-01 true What are the requirements for the routine control device maintenance exemption? 63.2251 Section 63.2251 Protection of Environment... and Composite Wood Products General Compliance Requirements § 63.2251 What are the requirements for...

  16. Electrical Procedures and Environmental Control Systems. Building Maintenance. Module IV. Instructor's Guide.

    Science.gov (United States)

    Sloan, Garry

    This curriculum guide, one of six modules keyed to the building maintenance competency profile developed by industry and education professionals, provides materials for two units on electrical procedures and environmental control systems. Unit 1, on electrical procedures, includes the following lessons: electrical safety; troubleshooting and…

  17. Measuring young children's perceptions of support, control, and maintenance in their own social networks

    NARCIS (Netherlands)

    Boosman, K.P.A.; Van der Meulen, Matty; Van Geert, P. L. C.; Jackson, A.E.

    2002-01-01

    Thirty-eight children (aged 3;7-7;6) and one of their parents took part in a study concerning children perceptions of their social networks. The study made use of a newly developed instrument-the Support, Control and Maintenance Pictures Interview (SCAMPI). The SCAMPI offers an individualized

  18. A modeling framework for deteriorating control system and predictive maintenance of actuators

    International Nuclear Information System (INIS)

    Langeron, Y.; Grall, A.; Barros, A.

    2015-01-01

    Actuators play a central role in industrial automation systems. They are costly, and therefore studying their dependability needs all attention. Usually, an actuator is inserted in a feedback control system, and its mission is to implement a control action delivered by a controller. In this paper, a monotonic actuator deterioration is considered and it is assumed that a relationship exists between the control action and the physical actuator's deterioration. A modeling framework is proposed including a non-decreasing stochastic degradation process driving the inability for an actuator to fully implement its role. The prognosis of the actuator's residual useful lifetime is derived and used to update the controller's setting. The controller reconfiguration completes the maintenance corrective and preventive actions. This new action is suggested as an alternative for maintenance strategy. - Highlights: • A degrading control system model is proposed focusing on actuator deterioration. • It is assumed a relationship between this degradation and its loss of efficiency. • The actuator RUL is quantified as a quantile of its conditional survival function. • RUL prognosis is used to reconfigure the control input law. • This new action is suggested as an alternative for maintenance strategy

  19. A randomized controlled trial testing an Internet delivered cost-benefit approach to weight loss maintenance.

    Science.gov (United States)

    Leahey, Tricia M; Fava, Joseph L; Seiden, Andrew; Fernandes, Denise; Doyle, Caroline; Kent, Kimberly; La Rue, Molly; Mitchell, Marc; Wing, Rena R

    2016-11-01

    Weight loss maintenance is a significant challenge in obesity treatment. During maintenance the "costs" of adhering to weight management behaviors may outweigh the "benefits." This study examined the efficacy of a novel approach to weight loss maintenance based on modifying the cost-benefit ratio. Individuals who achieved a 5% weight loss (N=75) were randomized to one of three, 10-month maintenance interventions. All interventions were delivered primarily via the Internet. The Standard arm received traditional weight maintenance strategies. To increase benefits, or rewards, for maintenance behaviors, the two cost-benefit intervention conditions received weekly monetary rewards for self-monitoring and social reinforcement via e-coaching. To decrease behavioral costs (boredom) and increase novelty, participants in the cost-benefit conditions also monitored different evidence-based behaviors every two weeks (e.g., Weeks 1 & 2: steps; Week 3 & 4: red foods). The primary difference between the cost-benefit interventions was type of e-coach providing social reinforcement: Professional (CB Pro) or Peer (CB Peer). Study procedures took place in Providence, RI from 2013 to 2014. Retention was 99%. There were significant group differences in weight regain (p=.01). The Standard arm gained 3.5±5.7kg. In contrast, participants in CB Pro and CB Peer lost an additional 1.8±7.0kg and 0.5±6.4kg, respectively. These results suggest that an Internet delivered cost-benefit approach to weight loss maintenance may be effective for long-term weight control. In addition, using peer coaches to provide reinforcement may be a particularly economic alternative to professionals. These data are promising and provide support for a larger, longer trial. Copyright © 2016 Elsevier Inc. All rights reserved.

  20. Working memory load and distraction: dissociable effects of visual maintenance and cognitive control.

    Science.gov (United States)

    Konstantinou, Nikos; Beal, Eleanor; King, Jean-Remi; Lavie, Nilli

    2014-10-01

    We establish a new dissociation between the roles of working memory (WM) cognitive control and visual maintenance in selective attention as measured by the efficiency of distractor rejection. The extent to which focused selective attention can prevent distraction has been shown to critically depend on the level and type of load involved in the task. High perceptual load that consumes perceptual capacity leads to reduced distractor processing, whereas high WM load that reduces WM ability to exert priority-based executive cognitive control over the task results in increased distractor processing (e.g., Lavie, Trends in Cognitive Sciences, 9(2), 75-82, 2005). WM also serves to maintain task-relevant visual representations, and such visual maintenance is known to recruit the same sensory cortices as those involved in perception (e.g., Pasternak & Greenlee, Nature Reviews Neuroscience, 6(2), 97-107, 2005). These findings led us to hypothesize that loading WM with visual maintenance would reduce visual capacity involved in perception, thus resulting in reduced distractor processing-similar to perceptual load and opposite to WM cognitive control load. Distractor processing was assessed in a response competition task, presented during the memory interval (or during encoding; Experiment 1a) of a WM task. Loading visual maintenance or encoding by increased set size for a memory sample of shapes, colors, and locations led to reduced distractor response competition effects. In contrast, loading WM cognitive control with verbal rehearsal of a random letter set led to increased distractor effects. These findings confirm load theory predictions and provide a novel functional distinction between the roles of WM maintenance and cognitive control in selective attention.

  1. Magnetogenetics: Remote Control of Cellular Signaling with Magnetic Fields

    Science.gov (United States)

    Sauer, Jeremy P.

    Means for temporally regulating gene expression and cellular activity are invaluable for elucidating the underlying physiological processes and have therapeutic implications. Here we report the development of a system for remote regulation of gene expression by low frequency radiowaves (RF) or by a static magnetic field. We accomplished this by first adding iron oxide nanoparticles - either exogenously or as genetically encoded ferritin/ferric oxyhydroxide particle. These particles have been designed with affinity to the plasma membrane ion channel Transient Receptor Potential Vanilloid 1 (TRPV1) by a conjugated antibody. Application of a magnetic field stimulates the particle to gate the ion channel and this, in turn, initiates calcium-dependent transgene expression. We first demonstrated in vitro that TRPV1 can be actuated to cause calcium flux into the cell by directly applying a localized magnetic field. In mice expressing these genetically encoded components, application of external magnetic field caused remote stimulation of insulin transgene expression and significantly lowered blood glucose. In addition, we are investigating mechanisms by which iron oxide nanoparticles can absorb RF, and transduce this energy to cause channel opening. This robust, repeatable method for remote cellular regulation in vivo may ultimately have applications in basic science, as well as in technology and therapeutics.

  2. Remote controlled tool systems for nuclear sites have subsea applications

    International Nuclear Information System (INIS)

    Bath, B.; Yemington, C.; Kuhta, B.

    1995-10-01

    Remotely operated underwater tool systems designed to operate in Nuclear Fuel Storage Basins can be applied to deep water, subsea oilfield applications. Spent nuclear fuel rods re stored underwater in large indoor swimming pool-like facilities where the water cover shields the workers from the radiation. This paper describes three specialized tooling systems that were designed and built by Sonsub for work at the Department of Energy's Hanford site. The Door Seal Tool removed an existing seal system, cleaned a 20 ft. tall, carbon steel, underwater hatch and installed a new stainless steel gasket surface with underwater epoxy. The Concrete Sampling Tool was built to take core samples from the vertical, concrete walls of the basins. The tool has three hydraulic drills with proprietary hollow core drill bits to cut and retrieve the concrete samples. The Rack Saw remotely attached itself to a structure, cut a variety of steel shapes and pipes, and retained the cut pieces for retrieval. All of these systems are remotely operated with onboard video cameras and debris collection systems. The methods and equipment proven in this application are available to refurbish sealing surfaces and to drill or sample concrete in offshore oil field applications

  3. Operation Request Gatekeeper: A software system for remote access control of diagnostic instruments in fusion experiments

    International Nuclear Information System (INIS)

    Abla, G.; Schissel, D. P.; Fredian, T. W.; Stillerman, J. A.; Greenwald, M. J.; Stepanov, D. N.; Ciarlette, D. J.

    2010-01-01

    Tokamak diagnostic settings are repeatedly modified to meet the changing needs of each experiment. Enabling the remote diagnostic control has significant challenges due to security and efficiency requirements. The Operation Request Gatekeeper (ORG) is a software system that addresses the challenges of remotely but securely submitting modification requests. The ORG provides a framework for screening all the requests before they enter the secure machine zone and are executed by performing user authentication and authorization, grammar validation, and validity checks. A prototype ORG was developed for the ITER CODAC that satisfies their initial requirements for remote request submission and has been tested with remote control of the KSTAR Plasma Control System. This paper describes the software design principles and implementation of ORG as well as worldwide test results.

  4. Longwall strata control and maintenance system - a stethoscope for longwall mining

    Energy Technology Data Exchange (ETDEWEB)

    Park, D.W.; Deb, D. [University of Alabama, Tuscaloosa, AL (US). Dept. of Civil and Environmental Engineering

    1999-10-01

    The Longwall Strata-Control and Maintenance System (LoSCo-MS) is a software and data-communication system developed at the University of Alabama. This system integrates real-time shield monitoring, data presentation, analysis and the forecasting of forthcoming events. The main objective of this system is to provide stability information on longwall panels, including excessive shield load, low setting pressure, leg leakage, poor shield performance and imminent maintenance problems. Analyses of various mining and geological parameters were also performed to determine past and present roof characteristics and to forecast roof loading patterns for the following mining cycles, the next periodic weighting, etc. A local coal mine in the Warrior Coal Basin has adopted this system to provide daily evaluation of ground stability and maintenance problems in their longwall panels. Two years of experience with this system is covered in this paper. 4 refs., 10 figs.

  5. Maintenance Free and Sustainable High-Level Control in Cement and Mining Industry

    DEFF Research Database (Denmark)

    Hansen, Ole Fink

    2009-01-01

    High-level control systems have been utilized in the process industry for decades, and also in cement production their use is well established. In comparison to manual control their ability to increase production and quality of end product, while reducing energy consumption and emission, is well...... but nevertheless still require maintenance. For the 10% of the algorithm that is control related, the maintenance issue is to some extent addressed by research topics such as adaptive control, which aim at retuning the parameters of the algorithm to match the changing process. In this project however, it has been...... chosen to focus on the remaining 90% of the algorithm which still require manual modifications to cope with a changed process. Although this issue has gained limited attention from academia so far it is well recognized by the industry. In the process of maintaining an algorithm it has turned out...

  6. An integrated model of statistical process control and maintenance based on the delayed monitoring

    International Nuclear Information System (INIS)

    Yin, Hui; Zhang, Guojun; Zhu, Haiping; Deng, Yuhao; He, Fei

    2015-01-01

    This paper develops an integrated model of statistical process control and maintenance decision. The proposal of delayed monitoring policy postpones the sampling process till a scheduled time and contributes to ten-scenarios of the production process, where equipment failure may occur besides quality shift. The equipment failure and the control chart alert trigger the corrective maintenance and the predictive maintenance, respectively. The occurrence probability, the cycle time and the cycle cost of each scenario are obtained by integral calculation; therefore, a mathematical model is established to minimize the expected cost by using the genetic algorithm. A Monte Carlo simulation experiment is conducted and compared with the integral calculation in order to ensure the analysis of the ten-scenario model. Another ordinary integrated model without delayed monitoring is also established as comparison. The results of a numerical example indicate satisfactory economic performance of the proposed model. Finally, a sensitivity analysis is performed to investigate the effect of model parameters. - Highlights: • We develop an integrated model of statistical process control and maintenance. • We propose delayed monitoring policy and derive an economic model with 10 scenarios. • We consider two deterioration mechanisms, quality shift and equipment failure. • The delayed monitoring policy will help reduce the expected cost

  7. Methodology for testing a system for remote monitoring and control on auxiliary machines in electric vehicles

    Directory of Open Access Journals (Sweden)

    Dimitrov Vasil

    2017-01-01

    Full Text Available A laboratory system for remote monitoring and control of an asynchronous motor controlled by a soft starter and contemporary measuring and control devices has been developed and built. This laboratory system is used for research and in teaching. A study of the principles of operation, setting up and examination of intelligent energy meters, soft starters and PLC has been made as knowledge of the relevant software products is necessary. This is of great importance because systems for remote monitoring and control of energy consumption, efficiency and proper operation of the controlled objects are very often used in different spheres of industry, in building automation, transport, electricity distribution network, etc. Their implementation in electric vehicles for remote monitoring and control on auxiliary machines is also possible and very useful. In this paper, a methodology of tests is developed and some experiments are presented. Thus, an experimental verification of the developed methodology is made.

  8. Quality Control Activities Related to Mechanical Maintenance of Safety Related Components at Krsko NPP

    International Nuclear Information System (INIS)

    Djakovic, D.

    2016-01-01

    For successful, safe and reliable operation of nuclear power plant, maintenance processes have to be systematically controlled and procedures for quality control of maintenance activities shall be established. This is requested by the quality assurance program, which shall provide control over activities affecting the quality of structures, systems, and components, considering their importance to safety. As a part of Quality and Nuclear Oversight Division (QNOD; SKV), the Quality Control Department (QC) provides quality control activities, which are deeply involved in maintenance processes at Krsko NPP, both on safety related and non-safety related (non-nuclear safety) components. QC activities on safety related components have to fulfil all requirements, which will enable the components to perform their intended safety functions. This paper describes quality control activities related to mechanical maintenance of safety related components at Krsko NPP and significant role of the Krsko plant QC Department in three particular maintenance cases connected with safety related components. In these three specific cases, the QC has confirmed its importance in compliance with quality assurance program and presented its significant added value in providing safe and reliable operation of the plant. The first maintenance activity was installation of nozzle check valves in the scope of a modification for improving regulation of spent fuel pit pumps. The QC Department performed receipt inspection of the valves. Using non-destructive examination methods and X-ray spectrometry, it was found out that the valve diffuser was made of improper material, which could cause progressive corrosion of the valve diffuser in borated water and consequently a loss of safety function of the valves followed by long-term consequences. The second one was the receipt inspection of containment ventilation fan coolers. The coolers were claimed and sent back to the supplier because the QC Department

  9. CAD-model based remote handling control system for NET and JET

    International Nuclear Information System (INIS)

    Leinemann, K.; Kuehneapfel, U.; Ludwig, A.

    1989-01-01

    For maintenance work in fusion plants a supervisory control system concept was developed, which organized a close, problem-suited cooperation of man and machine, based on shared control and mutual help. The central module on the task control level of the control system is a real-time simulator based on a three-dimensional CAD-model. This simulator serves for planning and of-line programming of maintenance sequences, and, in th execution phase, for integrated viewing, combining TV and synthetic scene presentation. A first implementation of a geometric simulator and its integration in an overall control system was realized for JET. (author). 5 refs.; 7 figs

  10. Computer programme for control and maintenance and object oriented database: application to the realisation of an particle accelerator, the VIVITRON

    International Nuclear Information System (INIS)

    Diaz, A.

    1996-01-01

    The command and control system for the Vivitron, a new generation electrostatic particle accelerator, has been implemented using workstations and front-end computers using VME standards, the whole within an environment of UNIX/VxWorks. This architecture is distributed over an Ethernet network. Measurements and commands of the different sensors and actuators are concentrated in the front-end computers. The development of a second version of the software giving better performance and more functionality is described. X11 based communication has been utilised to transmit all the necessary informations to display parameters within the front-end computers on to the graphic screens. All other communications between processes use the Remote Procedure Call method (RPC). The conception of the system is based largely on the object oriented database O 2 which integrates a full description of equipments and the code necessary to manage it. This code is generated by the database. This innovation permits easy maintenance of the system and bypasses the need of a specialist when adding new equipments. The new version of the command and control system has been progressively installed since August 1995. (author)

  11. Research of remote control system in turn by turn timing system

    International Nuclear Information System (INIS)

    Zhan Zhifeng; Xiao Yanguo; Ma Kui; Yin Zejie; Wu Xiaoyi

    2003-01-01

    In this paper, we introduce a remote control system which is used in a frequency dividing and time-delay module. This control system is based on client/server architecture, and RS232 serial communication protocol. This control system is used in timing system of NSRL turn by turn beam position monitor

  12. Remote control of a cooling system; Regelen en controleren op afstand

    Energy Technology Data Exchange (ETDEWEB)

    Bassa, E [ed.

    1996-10-01

    The renovation of a supermarket building in Nieuw-Lekkerland, Netherlands, included the replacement of the existing refrigerating facility. One of the arguments to choose a new unit was the introduction of the Hazard Analysis Critical Control Points (HACCP) quality control system. The new unit is equipped with a remote control system, using the most up-to-date instruments

  13. Remote Instrument Control with CIMA Web Services and Web 2.0 Technology

    Directory of Open Access Journals (Sweden)

    Douglas John du Boulay

    2008-02-01

    Full Text Available The Common Instrument Middleware Architecture (CIMA model for Web services based monitoring of remote scientific instruments is being extended and enhanced to provide a capability for remote instrument control. X-ray diffraction has been selected as an ideal domain for prototype development, with the goal being a comprehensive and feature rich portal system for access to remote instruments and their data. The system has two principle components, one of which serves the instrument and data, and the second serves the client user. Plugin modules are used to provide flexibility and re-use, and the notion of plugin control is being developed. The architecture supports remote access to multiple instruments from a single portal. The use of Web 2.0 Pushlet and AJAX technologies has been introduced for push based portlet refresh and updating. An X3D based 3D virtual representation of the instrument provides data collection simulation and (pseudo real time instrument representation.

  14. Shuttle Flight Operations Contract Generator Maintenance Facility Land Use Control Implementation Plan (LUCIP)

    Science.gov (United States)

    Applegate, Joseph L.

    2014-01-01

    This Land Use Control Implementation Plan (LUCIP) has been prepared to inform current and potential future users of the Kennedy Space Center (KSC) Shuttle Flight Operations Contract Generator Maintenance Facility (SFOC; SWMU 081; "the Site") of institutional controls that have been implemented at the Site1. Although there are no current unacceptable risks to human health or the environment associated with the SFOC, an institutional land use control (LUC) is necessary to prevent human health exposure to antimony-affected groundwater at the Site. Controls will include periodic inspection, condition certification, and agency notification.

  15. Oak Ridge TNS/PEPR Program is considering modified physics and engineering criteria to ease remote maintenance problems

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Shannon, T.E.

    1978-01-01

    Early work on TNS/PEPR at ORNL consisted of systems trade studies to establish a baseline design. Representative parameters are shown in Table 1. Development of these parameters into a mechanical design focussed on the complexity of the device disassembly. Three modifications to the physics and engineering criteria are being studied to ease these problems of remote disassembly: (1) Increase allowable field ripple from 1% to a maximum of 3%, thereby reducing the number of TF coils. The result is increased access between coils. (2) Provide sufficient clearance in the bore of the toroidal coils to raise and lower the EF coils during torus segment removal. This assumes a requirement for equilibrium field (EF) coils close to the plasma. (3) Investigate a secondary vacuum enclosure (e.g., vacuum building concept) to eliminate the need for welded torus joints and TF coil dewars. This paper discusses these modifications, as well as some overall cost implications relating to ripple

  16. Remote control of an MR imaging study via tele-collaboration tools

    Science.gov (United States)

    Sullivan, John M., Jr.; Mullen, Julia S.; Benz, Udo A.; Schmidt, Karl F.; Murugavel, Murali; Chen, Wei; Ghadyani, Hamid

    2005-04-01

    In contrast to traditional 'video conferencing' the Access Grid (AG), developed by Argonne National Laboratory, is a collaboration of audio, video and shared application tools which provide the 'persistent presence' of each participant. Among the shared application tools are the ability to share viewing and control of presentations, browsers, images and movies. When used in conjunction with Virtual Network Computing (VNC) software, an investigator can interact with colleagues at a remote site, and control remote systems via local keyboard and mouse commands. This combination allows for effective viewing and discussion of information, i.e. data, images, and results. It is clear that such an approach when applied to the medical sciences will provide a means by which a team of experts can not only access, but interact and control medical devices for the purpose of experimentation, diagnosis, surgery and therapy. We present the development of an application node at our 4.7 Tesla MR magnet facility, and a demonstration of remote investigator control of the magnet. A local magnet operator performs manual tasks such as loading the test subject into the magnet and administering the stimulus associated with the functional MRI study. The remote investigator has complete control of the magnet console. S/he can adjust the gradient coil settings, the pulse sequence, image capture frequency, etc. A geographically distributed audience views and interacts with the remote investigator and local MR operator. This AG demonstration of MR magnet control illuminates the potential of untethered medical experiments, procedures and training.

  17. Administration and maintenance of distributed control digital systems; Administracion y mantenimiento de sistemas digitales de control distribuido (SDCD)

    Energy Technology Data Exchange (ETDEWEB)

    Ferreiro, Jorge M. [Administracion Nacional de Combustibles Alcohol y Portland (ANCAP), Montevideo (Uruguay)

    1998-07-01

    The demand for increased competitiveness has produced a growing presence of Distributed Control Systems (DCS) in the industrial environment. Regardless of size and function, all DCSs have in common very high availability and reliability requirements, and significant hardware, software and configuration complexity. The persons in charge of DCS management and maintenance are thus faced with a task of great responsibility and complexity, with little support in the form of voluminous, complex, non methodological documentation. This work aims to help these persons by giving them advice taken from real-life DCS management experience. As an initial framework, concepts on availability, fault tolerance, modularity, redundancy and maintainability are introduced. Then a DCS maintenance methodology is presented: teamwork, attitude, how to carry on routine work and how to face emergencies. Advice is given on how to develop maintenance procedures based on DCS maintenance tools, with an emphasis on using the DCS event and performance information for predictive maintenance. An overview of DCS hardware and software configuration management. (author)

  18. The effect of supragingival glycine air polishing on periodontitis during maintenance therapy: a randomized controlled trial

    Directory of Open Access Journals (Sweden)

    Hongye Lu

    2018-02-01

    Full Text Available Background Glycine air polishing has been proved to be safe, comfortable and time-saving. Whether it could substitute ultrasonic scaling to remove dental plaque biofilm during periodontal maintenance remains unclear. The purposes of this study were to evaluate the effect of supragingival glycine air polishing (SGAP on the subgingival periodontal pathogens during maintenance therapy and to check the association of periodontal pathogens and clinical parameters. Methods Twenty-three chronic periodontitis patients during their maintenance therapy were enrolled in the 12-week study. According to randomized split-mouth design, the test side was treated with SGAP (65 μm, while the control side was treated with supragingival ultrasonic scaling and polishing (SUSP with rubber cup. Clinical examination including plaque index (PLI, probing depth (PD, bleeding index (BI were performed at baseline and 12 weeks post-treatment. Sampling of the subgingival plaque at each investigational site (mesiobuccal site of the mandibular first molar was performed at baseline and 2, 4, 8, 12 weeks after maintenance treatment. Four periodontal pathogens including Porphyromonas gingivalis, Tannerella forsythia, Treponema denticola and Fusobacterium nucleatum were detected by 16S rDNA polymerase chain reaction. Results Clinical status generally improved after treatment in both groups. PLI in both groups, PD in SGAP group and bleeding on probing (% in SUSP group significantly decreased after treatment (p < 0.05. There was no significant difference of clinical parameters between two groups before and after treatment. The detection rates of P. gingivalis, T. denticola in both groups, T. forsythia in SUSP group and F. nucleatum in SGAP group decreased after maintenance treatment in both groups, although no significant difference was found, and it rebound to baseline level at 12 weeks after maintenance treatment. There was no significant difference between SGAP group and SUSP

  19. Development of Remote Monitoring and a Control System Based on PLC and WebAccess for Learning Mechatronics

    OpenAIRE

    Wen-Jye Shyr; Te-Jen Su; Chia-Ming Lin

    2013-01-01

    This study develops a novel method for learning mechatronics using remote monitoring and control, based on a programmable logic controller (PLC) and WebAccess. A mechatronics module, a Web‐CAM and a PLC were integrated with WebAccess software to organize a remote laboratory. The proposed system enables users to access the Internet for remote monitoring and control of the mechatronics module via a web browser, thereby enhancing work flexibility by enabling personnel to control mechatronics equ...

  20. Haptic shared control improves hot cell remote handling despite controller inaccuracies

    International Nuclear Information System (INIS)

    Oosterhout, J. van; Abbink, D.A.; Koning, J.F.; Boessenkool, H.; Wildenbeest, J.G.W.; Heemskerk, C.J.M.

    2013-01-01

    Highlights: Haptic shared control is generally based upon perfect environment information. A realistic implementation holds model errors with respect to the environment. Operators were aided with inaccurate guiding forces during a peg-in-hole task. The results showed that small guiding inaccuracies still aid the operator. -- Abstract: A promising solution to improve task performance in ITER hot cell remote handling is the use of haptic shared control. Haptic shared control can assist the human operator along a safe and optimal path with continuous guiding forces from an intelligent autonomous controller. Previous research tested such controllers with accurate knowledge of the environment (giving flawless guiding forces), while in a practical implementation guidance forces will sometimes be flawed due to inaccurate models or sensor information. This research investigated the effect of zero and small (7.5 mm) errors on task performance compared to normal (unguided) operation. In a human factors experiment subjects performed a three dimensional virtual reality peg-in-hole type task (30 mm diameter; 0.1 mm clearance), with and without potentially flawed haptic shared control. The results showed that the presence of guiding forces, despite of small guiding errors, still improved task performance with respect to unguided operations

  1. Haptic shared control improves hot cell remote handling despite controller inaccuracies

    Energy Technology Data Exchange (ETDEWEB)

    Oosterhout, J. van, E-mail: J.vanOosterhout@differ.nl [Delft University of Technology, Faculty of 3mE, BioMechanical Engineering Department, Mekelweg 2, 2628 CD Delft (Netherlands); Abbink, D.A. [Delft University of Technology, Faculty of 3mE, BioMechanical Engineering Department, Mekelweg 2, 2628 CD Delft (Netherlands); Koning, J.F. [Heemskerk Innovative Technology B.V., Jonckerweg 12, 2201 DZ Noordwijk (Netherlands); Boessenkool, H. [FOM Institute DIFFER (Dutch Institute for Fundamental Energy Research), Association EURATOM-FOM, Partner in the Trilateral Euregio Cluster, PO Box 1207, 3430 BE Nieuwegein (Netherlands); Wildenbeest, J.G.W. [Delft University of Technology, Faculty of 3mE, BioMechanical Engineering Department, Mekelweg 2, 2628 CD Delft (Netherlands); Heemskerk Innovative Technology B.V., Jonckerweg 12, 2201 DZ Noordwijk (Netherlands); Heemskerk, C.J.M. [Heemskerk Innovative Technology B.V., Jonckerweg 12, 2201 DZ Noordwijk (Netherlands)

    2013-10-15

    Highlights: Haptic shared control is generally based upon perfect environment information. A realistic implementation holds model errors with respect to the environment. Operators were aided with inaccurate guiding forces during a peg-in-hole task. The results showed that small guiding inaccuracies still aid the operator. -- Abstract: A promising solution to improve task performance in ITER hot cell remote handling is the use of haptic shared control. Haptic shared control can assist the human operator along a safe and optimal path with continuous guiding forces from an intelligent autonomous controller. Previous research tested such controllers with accurate knowledge of the environment (giving flawless guiding forces), while in a practical implementation guidance forces will sometimes be flawed due to inaccurate models or sensor information. This research investigated the effect of zero and small (7.5 mm) errors on task performance compared to normal (unguided) operation. In a human factors experiment subjects performed a three dimensional virtual reality peg-in-hole type task (30 mm diameter; 0.1 mm clearance), with and without potentially flawed haptic shared control. The results showed that the presence of guiding forces, despite of small guiding errors, still improved task performance with respect to unguided operations.

  2. Design and Research of Intelligent Remote Control Fan Based on Single Chip Microcomputer and Bluetooth Technology

    Directory of Open Access Journals (Sweden)

    Zhang Xue-Xia

    2017-01-01

    Full Text Available This paper is designed for intelligent remote control fans. The design of the microcontroller as the core, the sensor, Bluetooth and Andrews system applied to the design of intelligent remote control fan. According to the temperature sensor to achieve the indoor temperature collection, to achieve and set the temperature comparison, thus affecting the fan speed. At the same time, the system according to the infrared sensor components to detect external factors, in order to achieve the running or stopping of the fan, that is, to achieve intelligent control of the fan. In addition, the system achieve the Bluetooth and mobile phone Andrews system of effective combination, and through the software program to complete the fan remote operation and wind speed control.

  3. Steelmaking process control using remote ultraviolet atomic emission spectroscopy

    Science.gov (United States)

    Arnold, Samuel

    Steelmaking in North America is a multi-billion dollar industry that has faced tremendous economic and environmental pressure over the past few decades. Fierce competition has driven steel manufacturers to improve process efficiency through the development of real-time sensors to reduce operating costs. In particular, much attention has been focused on end point detection through furnace off gas analysis. Typically, off-gas analysis is done with extractive sampling and gas analyzers such as Non-dispersive Infrared Sensors (NDIR). Passive emission spectroscopy offers a more attractive approach to end point detection as the equipment can be setup remotely. Using high resolution UV spectroscopy and applying sophisticated emission line detection software, a correlation was observed between metal emissions and the process end point during field trials. This correlation indicates a relationship between the metal emissions and the status of a steelmaking melt which can be used to improve overall process efficiency.

  4. Remote Control and Testing of the Interactive TV-Decoder

    Directory of Open Access Journals (Sweden)

    K. Vlcek

    1995-12-01

    Full Text Available The article deals with assembling and application of a complex sequential circuit VHDL (VHSIC (Very High-Speed Integrated Circuit Hardware Description Language model. The circuit model is a core of a cryptographic device for the signal encoding and decoding of discreet transmissions by TV-cable net. The cryptographic algorithm is changable according to the user's wishes. The principles of creation and example implementations are presented in the article. The behavioural model is used to minimize mistakes in the ASICs (Application Specific Integrated Circuits. The circuit implementation uses the FPGA (Field Programmable Gate Array technology. The diagnostics of the circuit is based on remote testing by the IEEE Std 1149.1-1990. The VHDL model of diagnostic subsystem is created as an orthogonal model in relation to the cryptographic circuit VHDL model.

  5. Voltage magnitude and margin controller for remote industrial microgrid with high wind penetration

    DEFF Research Database (Denmark)

    Cai, Yu; Lin, Jin; Song, Yonghua

    2013-01-01

    It is well known that the remote industrial microgrid is located at the periphery of the grid, which is weakly connected to the main grid. In order to enhance the voltage stability and ensure a good power quality for industries, a voltage magnitude and margin controller based on wind turbines...... is proposed in this paper. This controller includes two parts to improve voltage stability in different time scales by using local measurements. Case studies conducted for a remote microgrid with high wind penetration have proved the effectiveness of the proposed control scheme....

  6. Self-powered remotely controlled machines and tools for safety improvement in mining

    Energy Technology Data Exchange (ETDEWEB)

    Mirzaeva, G. [University of Newcastle, Callaghan, NSW (Australia)

    2005-07-01

    This paper addresses the problem of meeting the safety requirements of mining industry for implementation of control and monitoring equipment without external wiring. Local power generation and accumulation combined with remote control and wireless data transmission are suggested as an appropriate way to make the implementation of such device safe and convenient, which in its turn would facilitate their wider application for automation and safety improvement. A rope shovel dipper trip system is discussed in detail as an example of a self-powered remotely-controlled system. Other possible applications of the concept are also identified, such as Armoured Face Conveyor (AFC) and water jet drilling operation monitoring. 5 refs., 6 figs.

  7. Operations and maintenance plans for the TFTR

    International Nuclear Information System (INIS)

    Allen, H.L.; Fedor, B.J.

    1978-01-01

    Princeton University Plasma Physics Laboratory (PPPL) is constructing a Tokamak Fusion Test Reactor (TFTR) scheduled to begin operation for fusion research experiments in late 1981, first with hydrogen and deuterium plasmas and later, in the second phase, using tritium for high power fusion studies. This latter mode will introduce considerable complexity to operation and maintenance of the TFTR in terms of meeting requirements for tritium handling, adequate radiation shielding, and corrective and preventive maintenance procedures. In this paper we discuss plans for the installation and preoperational testing of the major subsystems of TFTR, proposed start-up and operating scenarios for the device and the system of operational control. In addition, the TFTR Maintenance Plan and related procedures for specific major maintenance tasks are described, including the use of remote handling equipment and remote manipulators. Each of these topics is addressed in terms of the current status of planning and development

  8. Remote crane control techniques and closed-circuit television for the U.S. Department of Energy, Defense Waste Processing Facility

    International Nuclear Information System (INIS)

    DaSilva, D.A.

    1988-01-01

    The Defense Waste Processing Facility (DWPF) located at the Savannah River Plant (SRP), South Carolina is a nuclear waste facility being built to vitrify and containerize high level radioactive waste products. DWPF has a unique requirement for an unmanned crane system to install and replace equipment in the high humidity, high radiation and harsh chemical environment of permanently inaccessible processing cells. A radio control system is provided to control a 117 ton capacity bridge crane that is equipped with various power tools for remote handling of crane replaceable and maintained equipment. High resolution black and white closed circuit television (CTV) assemblies mounted on the crane and on the walls of the various processing cells are provided for viewing the equipment during normal operations and maintenance. The main process cell (MPC) crane is designed as the vehicle to be the eyes, ears and hands for remote in-cell operations and maintenance. The crane runs on elevated rails above the process cells. A trailer-like-electrical equipment compartment (EEC) containing control and radio communications equipment for the crane; is dragged along on rails in a heavily shielded corridor by a drag bar mounted to the crane. A two way RF system is the communications link for all control and video signals between the crane and two stationary crane control consoles

  9. Opportune maintenance and predictive maintenance decision support

    OpenAIRE

    Thomas , Edouard; Levrat , Eric; Iung , Benoît; Cocheteux , Pierre

    2009-01-01

    International audience; Conventional maintenance strategies on a single component are being phased out in favour of more predictive maintenance actions. These new kinds of actions are performed in order to control the global performances of the whole industrial system. They are anticipative in nature, which allows a maintenance expert to consider non-already-planned maintenance actions. Two questions naturally emerge: when to perform a predictive maintenance action; how a maintenance expert c...

  10. Software solutions manage the definition, operation, maintenance and configuration control of the National Ignition Facility

    International Nuclear Information System (INIS)

    Dobson, D.; Churby, A.; Krieger, E.; Maloy, D.; White, K.

    2011-01-01

    The National Ignition Facility (NIF) is the world's largest laser composed of millions of individual parts brought together to form one massive assembly. Maintaining control of the physical definition, status and configuration of this structure is a monumental undertaking yet critical to the validity of the shot experiment data and the safe operation of the facility. The NIF business application suite of software provides the means to effectively manage the definition, build, operation, maintenance and configuration control of all components of the National Ignition Facility. State of the art Computer Aided Design software applications are used to generate a virtual model and assemblies. Engineering bills of material are controlled through the Enterprise Configuration Management System. This data structure is passed to the Enterprise Resource Planning system to create a manufacturing bill of material. Specific parts are serialized then tracked along their entire lifecycle providing visibility to the location and status of optical, target and diagnostic components that are key to assessing pre-shot machine readiness. Nearly forty thousand items requiring preventive, reactive and calibration maintenance are tracked through the System Maintenance and Reliability Tracking application to ensure proper operation. Radiological tracking applications ensure proper stewardship of radiological and hazardous materials and help provide a safe working environment for NIF personnel.

  11. Information system design of inventory control spare parts maintenance (valuation class 5000) (case study: plant kw)

    Science.gov (United States)

    Fitriana, Rina; Moengin, Parwadi; Riana, Mega

    2016-02-01

    Plat KW hadn't using optimal inventory level planning yet and hadn't have an information system that well computerized. The research objective is to be able to design an information system related inventory control of spare parts maintenance. The study focused on five types of spare parts with the highest application rate during February 2013- March 2015 and included in the classification of fast on FSN analysis Grinding stones Cut 4". Cable Tie 15". Welding RB 26-32MM. Ring Plat ½" and Ring Plate 5/8 ". Inventory calculation used Economic Order Quantity (EOQ). Safety Stock (SS) and Reorder Point (ROP) methods. System analysis conducted using the framework PIECES with the proposed inventory control system. the performance of the plant KW relating to the supply of spare parts maintenance needs can be more efficient as well as problems at the company can be answered and can perform inventory cost savings amounting Rp.267.066. A computerized information system of inventory control spare parts maintenance provides a menu that can be accessed by each departments as the user needed.

  12. Software solutions manage the definition, operation, maintenance and configuration control of the National Ignition Facility

    Energy Technology Data Exchange (ETDEWEB)

    Dobson, D; Churby, A; Krieger, E; Maloy, D; White, K

    2011-07-25

    The National Ignition Facility (NIF) is the world's largest laser composed of millions of individual parts brought together to form one massive assembly. Maintaining control of the physical definition, status and configuration of this structure is a monumental undertaking yet critical to the validity of the shot experiment data and the safe operation of the facility. The NIF business application suite of software provides the means to effectively manage the definition, build, operation, maintenance and configuration control of all components of the National Ignition Facility. State of the art Computer Aided Design software applications are used to generate a virtual model and assemblies. Engineering bills of material are controlled through the Enterprise Configuration Management System. This data structure is passed to the Enterprise Resource Planning system to create a manufacturing bill of material. Specific parts are serialized then tracked along their entire lifecycle providing visibility to the location and status of optical, target and diagnostic components that are key to assessing pre-shot machine readiness. Nearly forty thousand items requiring preventive, reactive and calibration maintenance are tracked through the System Maintenance & Reliability Tracking application to ensure proper operation. Radiological tracking applications ensure proper stewardship of radiological and hazardous materials and help provide a safe working environment for NIF personnel.

  13. Design of a MGy radiation tolerant resolver-to-digital convertor IC for remotely operated maintenance in harsh environments

    Energy Technology Data Exchange (ETDEWEB)

    Leroux, Paul, E-mail: paul.leroux@kuleuven.be [KU Leuven, Dept. of Electrical Engineering (ESAT), AdvISe, Kleinhoefstraat 4, 2440 Geel (Belgium); Van Koeckhoven, Wesley; Verbeeck, Jens [KU Leuven, Dept. of Electrical Engineering (ESAT), AdvISe, Kleinhoefstraat 4, 2440 Geel (Belgium); Van Uffelen, Marco; Esqué, Salvador; Ranz, Roberto; Damiani, Carlo [Fusion for Energy, Torres Diagonal Litoral B3, Josep Pla 2, 08019 Barcelona (Spain); Hamilton, David [ITER Organization, Route de Vinon sur Verdon, 13115 Saint Paul-lez-Durance (France)

    2014-10-15

    During future ITER maintenance operations, sensors and their embarked electronics will be exposed to a hostile and radioactive environment. This paper presents the design of a MGy radiation tolerant 16 bit resolver-to-digital converter (RDC) in 130 nm CMOS technology. The RDC features a Type II digital tracking loop, able to track resolvers with speeds up to 300 rps, and excitation frequencies up to 4 kHz. The RDC uses two integrated ΔΣ-analog-to-digital converters (ADCs) to digitize the resolver outputs. The 16 bit, 10 kHz ADCs utilize a correlated double sampling technique to remove radiation induced offset and 1/f-noise. The front-end features a static angular resolution of 16 bits (4.2 arcsec{sub rms}) and a resolution of 10 bits (6 arcmin{sub rms}) at a rotor speed of 100 rps. The circuit has a simulated radiation tolerance exceeding 1 MGy. It has the ability to operate under temperatures up to 125 °C, and to allow multiplexing with signals from other conventional sensors for compact, robust read-out architectures.

  14. The state-of-the-art Model M-2 Maintenance System

    International Nuclear Information System (INIS)

    Herndon, J.N.; Martin, H.L.; Satterlee, P.E. Jr.; Jelatis, D.G.; Jennrich, C.E.

    1984-01-01

    The Model M-2 Maintenance System is part of an ongoing program within the Consolidated Fuel Reprocessing Program (CFRP) at Oak Ridge National Laboratory (ORNL) to improve remote manipulation technology for future nuclear fuel reprocessing and other remote applications. Techniques, equipment, and guidelines which can improve the efficiency of remote maintenance are being developed. The Model M-2 Maintenance System, installed in the Integrated Equipment Test (IET) Facility at ORNL, provides a complete, integrated remote maintenance system for the demonstration and development of remote maintenance techniques. The system comprises a pair of force-reflecting servomanipulator arms, television viewing, lighting, and auxiliary lifting capabilities, thereby allowing manlike maintenance operations to be executed remotely within the remote cell mockup area in the IET. The Model M-2 Maintenance System incorporates an upgraded version of the proven Central Research Laboratories' Model M servomanipulator. Included are state-of-the-art brushless dc servomotors for improved performance, remotely removable wrist assemblies, geared azimuth drive, and a distributed microprocessor-based digital control system

  15. A placebo-controlled trial of dextromethorphan as an adjunct in opioid-dependent patients undergoing methadone maintenance treatment.

    Science.gov (United States)

    Lee, Sheng-Yu; Chen, Shiou-Lan; Chang, Yun-Hsuan; Chu, Chun-Hsien; Chen, Shih-Heng; Chen, Po See; Huang, San-Yuan; Tzeng, Nian-Sheng; Wang, Liang-Jen; Lee, I Hui; Wang, Tzu-Yun; Chen, Kao Chin; Yang, Yen Kuang; Hong, Jau-Shyong; Lu, Ru-Band

    2015-02-25

    Low-dose dextromethorphan (DM) might have anti-inflammatory and neurotrophic effects mechanistically remote from an NMDA receptor. In a randomized, double-blind, controlled 12 week study, we investigated whether add-on dextromethorphan reduced cytokine levels and benefitted opioid-dependent patients undergoing methadone maintenance therapy (MMT). Patients were randomly assigned to a group: DM60 (60mg/day dextromethorphan; n = 65), DM120 (120mg/day dextromethorphan; n = 65), or placebo (n = 66). Primary outcomes were the methadone dose required, plasma morphine level, and retention in treatment. Plasma tumor necrosis factor (TNF)-α, C-reactive protein, interleukin (IL)-6, IL-8, transforming growth factor-β1, and brain-derived neurotrophic factor (BDNF) levels were examined during weeks 0, 1, 4, 8, and 12. Multiple linear regressions with generalized estimating equation methods were used to examine the therapeutic effect. After 12 weeks, the DM60 group had significantly longer treatment retention and lower plasma morphine levels than did the placebo group. Plasma TNF-α was significantly decreased in the DM60 group compared to the placebo group. However, changes in plasma cytokine levels, BDNF levels, and the methadone dose required in the three groups were not significantly different. We provide evidence-decreased concomitant heroin use-of low-dose add-on DM's efficacy for treating opioid-dependent patients undergoing MMT. © The Author 2015. Published by Oxford University Press on behalf of CINP.

  16. Construction of a remote controlled monitoring system with GPIB devices and EPICS

    International Nuclear Information System (INIS)

    Yoshikawa, Takeshi; Yamamoto, Noboru.

    1995-01-01

    The Experimental Physics and Industrial Control System (EPICS) has been used for the accelerator control system in recent years. EPICS has rich set of tools to create application with Graphical User Interface (GUI). It reduces the load of complex programming for GUI and shortens the application development period. This paper will describe the remote temperature monitoring system using EPICS. (author)

  17. Organisation of maintenance of health semi-portable detectors. IPAB-CFA-CABP control bench; Organisation de la maintenance des detecteurs semi-portatifs de sante. Banc de controle des IPAB-CFA-CABP

    Energy Technology Data Exchange (ETDEWEB)

    De Choudens, H.; Rage, P. [Commissariat a l' energie atomique et aux energies alternatives - CEA, Centre d' Etudes Nucleaires de Grenoble (France)

    1963-07-01

    As the number of electronic semi-portable health measurement devices is (was) increasing, it appears (appeared) important to organise their maintenance. In this report, the authors describe the implemented organisation. They indicate how a device is identified, which are the performed tests, and discuss results which have been obtained during the first year of implementation of this maintenance organisation. Then, they present the control bench, its operation (supply, measurement circuits), its use (control process for different devices, performed measurements and controls)

  18. Life cycle - a wide vision of the control valves maintenance; Life cycle - uma visao ampla de manutencao de valvulas de controle

    Energy Technology Data Exchange (ETDEWEB)

    Souza, Jorge Marcos de [Metso Automation do Brasil, ES (Brazil)

    2005-07-01

    Nowadays the industry search more and more contracts which involve the total responsibility by the maintenance of its equipment. What could not be different for the control valves because of its importance and critic to the process. Because of this, the maintenance concept Life Cycle targets to involve all the phases of the life of each control valve, since the project until the day to day maintenance activities, maximizing the performance and generating benefits to the process. (author)

  19. Software development and maintenance: An approach for a large accelerator control system

    International Nuclear Information System (INIS)

    Casalegno, L.; Orsini, L.; Sicard, C.H.

    1990-01-01

    Maintenance costs presently form a large part of the total life-cycle cost of a software system. In case of large systems, while the costs of eliminating bugs, fixing analysis and design errors and introducing updates must be taken into account, the coherence of the system as a whole must be maintained while its parts are evolving independently. The need to devise and supply tools to aid programmers in housekeeping and updating has been strongly felt in the case of the LEP preinjector control system. A set of utilities has been implemented to create a safe interface between the programmers and the files containing the control software. Through this interface consistent naming schemes, common compiling and object-building procedures can be enforced, so that development and maintenance staff need not be concerned with the details of executable code generation. Procedures have been built to verify the consistency, generate maintenance diagnostics and automatically update object and executable files, taking into account multiple releases and versions. The tools and the techniques reported in this paper are of general use in the UNIX environment and have already been adopted for other projects. (orig.)

  20. Design and remote fiber communication of NSRL electron gun controller

    International Nuclear Information System (INIS)

    Wang Weibing; Gao Hui; Hong Jun; Chen Jun; Wang Guicheng; He Duohui; Chen Gang

    2005-01-01

    A new kind of pulse electron gun controller for 200 MeV LINAC at National Synchrotron Radiation Laboratory was introduced in this paper, including the working principle of the pulse electron gun, the applications of I 2 C serial bus and embedded microcontroller in controlling system. The emphasis is on the hardware design of digital controlled current regulator, digital controlled switch voltage source and high voltage pulse power supply. The software design of fiber communication and PC controlling is also presented. The electron gun controller has successfully been used in NSRL. The result shows that it is quite reliable and the performance is good. This electronic digital system has completely replaced the old mechanical control system. (authors)

  1. Development of a remote monitoring and control system for nuclear power plants

    International Nuclear Information System (INIS)

    Lee, Seung Jun; Kim, Jong Hyun; Seong, Poong Hyun

    2002-01-01

    Nuclear Power Plants (NPPs) will be highly connected network enabled system and need to be monitored and controlled round the clock for high safety and availability. Using the network and web enabled tools, NPPs can be monitored remotely by operators at anytime from any place connected to the network via a general web browser. However, there are security and performance issues associated with such tools, as will be further discussed further. We developed a web-based Remote Monitoring and Control System (RMCS) that uses prevalent web technology. This work, as a preliminary study, performed the conceptual design of the web-based RMCS and developed the prototype

  2. Improvement of remote control system of automatic ultrasonic equipment for inspection of reactor pressure vessel

    International Nuclear Information System (INIS)

    Cheong, Yong Moo; Jung, H. K.; Joo, Y. S.; Koo, K. M.; Hyung, H.; Sim, C. M.; Gong, U. S.; Kim, S. H.; Lee, J. P.; Rhoo, H. C.; Kim, M. S.; Ryoo, S. K.; Choi, C. H.; Oh, K. I.

    1999-12-01

    One of the important issues related to the nuclear safety is in-service inspection of reactor pressure vessel (RPV). A remote controlled automatic ultrasonic method is applied to the inspection. At present the automatic ultrasonic inspection system owned by KAERI is interrupted due to degradation of parts. In order to resume field inspection new remote control system for the equipment was designed and installed to the existing equipment. New ultrasonic sensors and their modules for RPV inspection were designed and fabricated in accordance with the new requirements of the inspection codes. Ultrasonic sensors were verified for the use in the RPV inspection. (author)

  3. Improvement of remote control system of automatic ultrasonic equipment for inspection of reactor pressure vessel

    Energy Technology Data Exchange (ETDEWEB)

    Cheong, Yong Moo; Jung, H. K.; Joo, Y. S.; Koo, K. M.; Hyung, H.; Sim, C. M.; Gong, U. S.; Kim, S. H.; Lee, J. P.; Rhoo, H. C.; Kim, M. S.; Ryoo, S. K.; Choi, C. H.; Oh, K. I

    1999-12-01

    One of the important issues related to the nuclear safety is in-service inspection of reactor pressure vessel (RPV). A remote controlled automatic ultrasonic method is applied to the inspection. At present the automatic ultrasonic inspection system owned by KAERI is interrupted due to degradation of parts. In order to resume field inspection new remote control system for the equipment was designed and installed to the existing equipment. New ultrasonic sensors and their modules for RPV inspection were designed and fabricated in accordance with the new requirements of the inspection codes. Ultrasonic sensors were verified for the use in the RPV inspection. (autho0008.

  4. A remote control system for the LELA experiment

    International Nuclear Information System (INIS)

    Castellano, M.; Cavallo, N.; Cevenini, F.; Patteri, P.

    1983-01-01

    A modular system for closed loop computer control of stepping motors has been realized and used for optical component movement of LELA experiment in radiation risk area. A CAMAC module, controlling up to 15 stepping motors, a NIM dual motor driver and a special purpose circuit for computer interfacing are described

  5. Quality upgrading and cost reducing effects of using an operation control system for performance of maintenance tasks

    International Nuclear Information System (INIS)

    Ramler, K.

    1996-01-01

    According to available results, the use of an operation control system has come up to expections with respect to a quality enhancement of maintenance work. The tasks are performed more safely and there is more insight into the processes. so that, as indirect results, cost savings and rationalisation effects are to be expected. However, the cost savings achieved through the operation control system for maintenance tasks will remain modest. The truly cost-effective optimisation potentials in the maintenance area primarily consist in a reduction of preventive measures to the required scope, i.e reduction of the envisaged quantity of processes for maintenance and recurrent inspection. In order to extend savings to the organisational level, with respect to personnel expenditure, by DP supported maintenance planning, a suitable optimisation of the organisational structure and personnel employment is inevitable, because otherwise the rationalisation potentials will remain utopia. (orig.) [de

  6. NET remote workstation

    International Nuclear Information System (INIS)

    Leinemann, K.

    1990-10-01

    The goal of this NET study was to define the functionality of a remote handling workstation and its hardware and software architecture. The remote handling workstation has to fulfill two basic functions: (1) to provide the man-machine interface (MMI), that means the interface to the control system of the maintenance equipment and to the working environment (telepresence) and (2) to provide high level (task level) supporting functions (software tools) during the maintenance work and in the preparation phase. Concerning the man-machine interface, an important module of the remote handling workstation besides the standard components of man-machine interfacing is a module for graphical scene presentation supplementing viewing by TV. The technique of integrated viewing is well known from JET BOOM and TARM control using the GBsim and KISMET software. For integration of equipment dependent MMI functions the remote handling workstation provides a special software module interface. Task level support of the operator is based on (1) spatial (geometric/kinematic) models, (2) remote handling procedure models, and (3) functional models of the equipment. These models and the related simulation modules are used for planning, programming, execution monitoring, and training. The workstation provides an intelligent handbook guiding the operator through planned procedures illustrated by animated graphical sequences. For unplanned situations decision aids are available. A central point of the architectural design was to guarantee a high flexibility with respect to hardware and software. Therefore the remote handling workstation is designed as an open system based on widely accepted standards allowing the stepwise integration of the various modules starting with the basic MMI and the spatial simulation as standard components. (orig./HP) [de

  7. Design and Manufacturing of Remote Control for Children Viewing Using Children Inspiration

    OpenAIRE

    Madani, R.; Moroz, Adam

    2012-01-01

    N/A The recruitment of children’s imagination in the development of new product design provides an interesting source of new ideas for product development, including for products for children. This study is related to the design and manufacture of a prototype for a remote control that controls television viewing content for children, to protect them from inappropriate content, control their viewing time and keep them at a safe distance from the television screen. For security reasons this ...

  8. Single-channel ground airborne radio system (SINCGARS) based remote control for the M1 Abrahms

    Science.gov (United States)

    Urda, Joseph R.

    1995-04-01

    Remote control of the Ml Abrahms Main Battle Tank through a minefield breach operation will remove the vehicle crew from the inherent hazard. A successful remote control system will provide automotive control yet not impair normal operation. This requires a minimum of physical parts, and an unobtrusive installation. Most importantly, a system failure must not impair the regular operation as a manned system. The system itself need not be complex. A minefield breach only requires simple control of automotive function and a mine plow interface. Control hardware for the Ml-Al can be reduced to two linear actuators, an electrical interface for the engine control unit, an interface for the mine plow, and the associated cables. Communication between vehicle control and operator control takes place over the vehicles organic radio (typically SINCGARS). This helps reduce the number of special purpose components for the remote control device. The device is currently awaiting an automotive safety test to prepare for its safety release. Because of the specific nature of the MDL-STD 1553-B data bus the device will not control an M1-A2 Main Battle Tank. The architecture will allow control of the M1-A2 through the 1553-B data bus however the physical hardware has not been constructed. The control scheme will not change. The communication interface will provide greater flexibility when interfacing to the vehicle tactical radio. Operational utility will be determined by U.S. Army Training and Doctrine Command personnel. The obvious benefit is that if a remote tank is lost during a minefield breach the crew is saved.

  9. Maintenance of reactor safety and control computers at a large government facility

    International Nuclear Information System (INIS)

    Brady, H.G.

    1985-01-01

    In 1950 the US Government contracted the Du Pont Company to design, build, and operate the Savannah River Plant (SRP). At the time, it was the largest construction project ever undertaken by man. It is still the largest of the Department of Energy facilities. In the nearly 35 years that have elapsed, Du Pont has met its commitments to the US Government and set world safety records in the construction and operation of nuclear facilities. Contributing factors in achieving production goals and setting the safety records are a staff of highly qualified personnel, a well maintained plant, and sound maintenance programs. There have been many ''first ever'' achievements at SRP. These ''firsts'' include: (1) computer control of a nuclear rector, and (2) use of computer systems as safety circuits. This presentation discusses the maintenance program provided for these computer systems and all digital systems at SRP. An in-house computer maintenance program that was started in 1966 with five persons has grown to a staff of 40 with investments in computer hardware increasing from $4 million in 1970 to more than $60 million in this decade. 4 figs

  10. Peripheral Lymphoid Volume Expansion and Maintenance Are Controlled by Gut Microbiota via RALDH+ Dendritic Cells.

    Science.gov (United States)

    Zhang, Zongde; Li, Jianjian; Zheng, Wencheng; Zhao, Guang; Zhang, Hong; Wang, Xiaofei; Guo, Yaqian; Qin, Chuan; Shi, Yan

    2016-02-16

    Lymphocyte homing to draining lymph nodes is critical for the initiation of immune responses. Secondary lymphoid organs of germ-free mice are underdeveloped. How gut commensal microbes remotely regulate cellularity and volume of secondary lymphoid organs remains unknown. We report here that, driven by commensal fungi, a wave of CD45(+)CD103(+)RALDH(+) cells migrates to the peripheral lymph nodes after birth. The arrival of these cells introduces high amounts of retinoic acid, mediates the neonatal to adult addressin switch on endothelial cells, and directs the homing of lymphocytes to both gut-associated lymphoid tissues and peripheral lymph nodes. In adult mice, a small number of these RALDH(+) cells might serve to maintain the volume of secondary lymphoid organs. Homing deficiency of these cells was associated with lymph node attrition in vitamin-A-deficient mice, suggesting a perpetual dependence on retinoic acid signaling for structural and functional maintenance of peripheral immune organs. Copyright © 2016 Elsevier Inc. All rights reserved.

  11. Software solutions manage the definition, operation, maintenance and configuration control of the National Ignition Facility

    International Nuclear Information System (INIS)

    Dobson, Darwin; Churby, Al; Krieger, Ed; Maloy, Donna; White, Kevin

    2012-01-01

    Highlights: ► NIF is a complex experimental facility composed of ∼4 million components. ► We describe business tools to define, build, operate, and maintain all components. ► CAD tools generate virtual models and assemblies under configuration control. ► Items requiring preventive, reactive, and/or calibration maintenance are tracked. ► Radiological or hazardous materials undergo additional controls. - Abstract: The National Ignition Facility (NIF) is the world's largest laser composed of millions of individual parts brought together to form one massive assembly. Maintaining control of the physical definition, status and configuration of this structure is a monumental undertaking yet critical to the validity of experimental data and the safe operation of the facility. A major programmatic challenge is to deploy software solutions to effectively manage the definition, build, operation, and maintenance, and configuration control of all components of NIF. The strategy for meeting this challenge involves deploying and integrating an enterprise application suite of solutions consisting of both Commercial-Off-The-Shelf (COTS) products and custom developed software.This paper describes how this strategy has been implemented along with a discussion on the successes realized and the ongoing challenges associated with this approach.

  12. Operations and maintenance manual for the LDUA supervisory control and data acquisition system (LDUA System 4200) and control network (LDUA System 4400)

    International Nuclear Information System (INIS)

    Barnes, G.A.

    1998-01-01

    This document defines the requirements applicable to the operation, maintenance and storage of the Supervisory Control and Data Acquisition System (SCADAS) and Control Network in support of the Light Duty Utility Arm (LDUA) operations

  13. Remotely controlled working gear and mobile systems for damage assessment

    International Nuclear Information System (INIS)

    Koehler, G.W.; Salaske, M.; Selig, M.

    1975-01-01

    The chassis of the light MF3 manipulator vehicle and the necessary electric control system have reached and advanced stage of construction. Bids will soon be invited for the mission control system with multiplexers of whole MF3 unit and for simple equipment for damage assessment. All major problems have been clarified in the course of the design phase of the light electric EMSM II Master-Slave manipulators intended for this service. The prototype of the electric EMSM I Master-Slave manipulator has been equipped with some of the supplementary tools required for test missions. (orig.) [de

  14. Exploring Children’s Use of a Remotely Controlled Surfacebot Character for Storytelling

    NARCIS (Netherlands)

    Catala, Alejandro; Theune, Mariet; Reidsma, Dennis; ter Stal, Silke; Heylen, Dirk K.J.

    This paper explores the use of a remotely controlled character to be used by children in storytelling activities. The character is implemented in a moveable tablet or surfacebot, which supports the development of inexpensive expressive agents capable of moving around in real space, applicable in

  15. DESAIN DAN IMPLEMENTASI SISTEM KENDALI INTENSITAS CAHAYA PPR MENGGUNAKAN SMS BERBASIS REMOTE CONTROL

    Directory of Open Access Journals (Sweden)

    Mohammad Khairuddin

    2015-06-01

    Full Text Available Makalah ini membahas kendali jarak jauh intensitas cahaya piranti penerangan ruang (PPR secara efisien menggunakan short message service (SMS berbasis remote control. Dengan sistem kendali berbasis SMS sebagai remote control maka semua PPR dapat dikendalikan dari manapun di seluruh penjuru tanah air dengan syarat tempat tersebut terjangkau oleh sinyal telekomunikasi yang disediakan oleh provider. Sistem ini didesain untuk memenuhi arahan hemat energi oleh Kementerian Energi dan Pertambangan. Sistem kendali intensitas cahaya PPR menggunakan SMS berbasis remote control ini sebagai terobosan sistem saklar manual yang selama ini dibatasi oleh ruang secara fisik. Kemudahan penggunaan handphone (HP telah menjadi peluang bagi sistem saklar PPR. Didukung dengan semakin murahnya biaya berkomunikasi melalui SMS. Peluang ini mendukung kemudahan pengguna HP dengan menambah fitur sistem kendali intensitas cahaya PPR menggunakan SMS berbasis remote control. Sistem kendali jarak jauh menggunakan server modem wavecom fastrack supreme. Sistem ini menggunakan prosesor ATmega8 dengan interfacing menggunakan RS232. Hasil eksperimen menunjukan bahwa tidak ada perbedaan waktu terhadap variabel jarak posisi PPR dengan HP pengirim SMS selaku comander untuk eksekusi pengaturan intensitas cahaya. Dengan rerata waktu jeda 4,38 detik. Semakin besar prosentase sudut pemicuan TRIAC maka akan semakin besar nilai intensitas cahaya. Tidak ada perbedaan signifikan terhadap lama waktu hasil eksekusi terhadap variasi provider yang digunakan.

  16. A Semi-Automatic, Remote-Controlled Video Observation System for Transient Luminous Events

    DEFF Research Database (Denmark)

    Allin, Thomas Højgaard; Neubert, Torsten; Laursen, Steen

    2003-01-01

    In support for global ELF/VLF observations, HF measurements in France, and conjugate photometry/VLF observations in South Africa, we developed and operated a semi-automatic, remotely controlled video system for the observation of middle-atmospheric transient luminous events (TLEs). Installed...

  17. High social impact of medical applications in nuclear technology: gynecological brachitherapy remote control in Uruguay

    International Nuclear Information System (INIS)

    Zubizarreta, E.

    1996-01-01

    In the present article is studied many systems for uterine carcinoma therapy. Among modern therapy systems it was found Fletcher applicator compound with Cesium and Iridium sources. This new technology by remote control has improved radioprotection levels in the exposition workers and disappear radioactive sources mislead, increasing sources activities and decreasing the exposition time

  18. What works in Indigenous tobacco control? The perceptions of remote Indigenous community members and health staff.

    Science.gov (United States)

    Johnston, Vanessa; Thomas, David P

    2010-04-01

    To explore the perceptions of remote Indigenous community members and health staff regarding the acceptability and effectiveness of different tobacco control health promotion interventions. Qualitative methods were used for this exploratory study, including interviews with remote Indigenous community members and health staff, as well as observations of the delivery of different tobacco control activities in three remote communities in the Northern Territory (NT). Several tobacco control interventions for which there is strong evidence in other settings were generally perceived as acceptable and efficacious in the remote Indigenous setting. Primary care interventions, such as brief advice and pharmaceutical quitting aids, when available and accessible, were perceived as important and effective strategies to help people quit, as were the promotion of smokefree areas. By contrast unmodified Quit programs were perceived to have questionable application in this context and there were conflicting findings regarding taxation increases on tobacco and social marketing campaigns. Several evidence-based 'mainstream' activities are perceived to be acceptable to this population, but we may also need to address the concerns raised by health staff and community members about the acceptability of some unmodified activities. Additionally, organisational barriers within the health system may be contributing to the reduced effectiveness of tobacco control in this setting.

  19. Remote sensing bio-control damage on aquatic invasive alien plant ...

    African Journals Online (AJOL)

    Naeem

    Satellite based remote sensing provides a synoptic view of ... information system for multi-temporal analysis (Albright et al., 2004) which ... control damage based on the colour of the foliage using aerial photography and conventional .... It was reported that the ratio of two chlorophyll fluorescence bands can be used to detect ...

  20. Hyperspectral remote sensing analysis of short rotation woody crops grown with controlled nutrient and irrigation treatments

    Science.gov (United States)

    Jungho Im; John R. Jensen; Mark Coleman; Eric. Nelson

    2009-01-01

    Hyperspectral remote sensing research was conducted to document the biophysical and biochemical characteristics of controlled forest plots subjected to various nutrient and irrigation treatments. The experimental plots were located on the Savannah River Site near Aiken, SC. AISA hyperspectral imagery were analysed using three approaches, including: (1) normalized...

  1. New generation detector for monitoring using remote-controlled ground-based and airborne systems

    International Nuclear Information System (INIS)

    Cespirova, Irena; Gryc, Lubomir; Helebrant, Jan; Sladek, Petr

    2015-01-01

    A new generation detector for monitoring with the use of remote-controlled ground (UAG, robotic rovers) or aircraft (UAV, drones) means was developed and tested within a security project. The main characteristics of the detector and the results of field tests with the detector placed on unmanned aerial means (drones) are described. (orig.)

  2. Automation of pharmaceutical warehouse using groups robots with remote climate control and video surveillance

    OpenAIRE

    Zhuravska, I. M.; Popel, M. I.

    2015-01-01

    In this paper, we present a complex solution for automation pharmaceutical warehouse, including the implementation of climate-control, video surveillance with remote access to video, robotics selection of medicine with the optimization of the robot motion. We describe all the elements of local area network (LAN) necessary to solve all these problems.

  3. Remote control of data acquisition devices by means of message oriented middleware

    International Nuclear Information System (INIS)

    Sanchez, E.; Portas, A.; Pereira, A.; Vega, J.; Kirpitchev, I.

    2007-01-01

    The TJ-II autonomous acquisition systems are computers running dedicated applications for programming and controlling data acquisition channels and also integrating acquired data into the central database. These computers are located in the experimental hall and have to be remotely controlled during plasma discharges. A remote control for these systems has been implemented by taking advantage of the message-oriented middleware recently introduced into the TJ-II data acquisition system. Java Message Service (JMS) is used as the messaging application program interface. All the acquisition actions that are available through the system console of the data acquisition computers (starting or aborting an acquisition, restarting the system or updating the acquisition application) can now be initiated remotely. Command messages are sent to the acquisition systems located in the experimental hall close to the TJ-II device by using the messaging software, without having to use a remote desktop application that produces heavy network traffic and requires manual operation. Action commands can be sent to only one or to several/many acquisition systems at the same time. This software is integrated into the TJ-II remote participation system and the acquisition systems can be commanded from inside or outside the laboratory. All this software is integrated into the security framework provided by PAPI, thus preventing non-authorized users commanding the acquisition computers. In order to dimension and distribute messaging services some performance tests of the message oriented middleware software have been carried out. Results of the tests are presented. As suggested by the tests results different transport connectors are used: TCP transport protocol is used for the local environment, while HTTP protocol is used for remote accesses, thereby allowing the system performance to be optimized

  4. Remote control of data acquisition devices by means of message oriented middleware

    Energy Technology Data Exchange (ETDEWEB)

    Sanchez, E. [Asociacion EURATOM/CIEMAT para Fusion, Madrid (Spain)], E-mail: edi.sanchez@ciemat.es; Portas, A.; Pereira, A.; Vega, J.; Kirpitchev, I. [Asociacion EURATOM/CIEMAT para Fusion, Madrid (Spain)

    2007-10-15

    The TJ-II autonomous acquisition systems are computers running dedicated applications for programming and controlling data acquisition channels and also integrating acquired data into the central database. These computers are located in the experimental hall and have to be remotely controlled during plasma discharges. A remote control for these systems has been implemented by taking advantage of the message-oriented middleware recently introduced into the TJ-II data acquisition system. Java Message Service (JMS) is used as the messaging application program interface. All the acquisition actions that are available through the system console of the data acquisition computers (starting or aborting an acquisition, restarting the system or updating the acquisition application) can now be initiated remotely. Command messages are sent to the acquisition systems located in the experimental hall close to the TJ-II device by using the messaging software, without having to use a remote desktop application that produces heavy network traffic and requires manual operation. Action commands can be sent to only one or to several/many acquisition systems at the same time. This software is integrated into the TJ-II remote participation system and the acquisition systems can be commanded from inside or outside the laboratory. All this software is integrated into the security framework provided by PAPI, thus preventing non-authorized users commanding the acquisition computers. In order to dimension and distribute messaging services some performance tests of the message oriented middleware software have been carried out. Results of the tests are presented. As suggested by the tests results different transport connectors are used: TCP transport protocol is used for the local environment, while HTTP protocol is used for remote accesses, thereby allowing the system performance to be optimized.

  5. Autonomous control systems: applications to remote sensing and image processing

    Science.gov (United States)

    Jamshidi, Mohammad

    2001-11-01

    One of the main challenges of any control (or image processing) paradigm is being able to handle complex systems under unforeseen uncertainties. A system may be called complex here if its dimension (order) is too high and its model (if available) is nonlinear, interconnected, and information on the system is uncertain such that classical techniques cannot easily handle the problem. Examples of complex systems are power networks, space robotic colonies, national air traffic control system, and integrated manufacturing plant, the Hubble Telescope, the International Space Station, etc. Soft computing, a consortia of methodologies such as fuzzy logic, neuro-computing, genetic algorithms and genetic programming, has proven to be powerful tools for adding autonomy and semi-autonomy to many complex systems. For such systems the size of soft computing control architecture will be nearly infinite. In this paper new paradigms using soft computing approaches are utilized to design autonomous controllers and image enhancers for a number of application areas. These applications are satellite array formations for synthetic aperture radar interferometry (InSAR) and enhancement of analog and digital images.

  6. Measuring Instruments Control Methodology Performance for Analog Electronics Remote Labs

    Directory of Open Access Journals (Sweden)

    Unai Hernandez-Jayo

    2012-12-01

    Full Text Available This paper presents the work that has been developed in parallel to the VISIR project. The objective of this paper is to present the results of the validations processes that have been carried out to check the control methodology. This method has been developed with the aim of being independent of the instruments of the labs.

  7. Recent developments in the remote radio control of insect flight.

    Science.gov (United States)

    Sato, Hirotaka; Maharbiz, Michel M

    2010-01-01

    The continuing miniaturization of digital circuits and the development of low power radio systems coupled with continuing studies into the neurophysiology and dynamics of insect flight are enabling a new class of implantable interfaces capable of controlling insects in free flight for extended periods. We provide context for these developments, review the state-of-the-art and discuss future directions in this field.

  8. Remote control video cameras on a suborbital rocket

    International Nuclear Information System (INIS)

    Wessling, Francis C.

    1997-01-01

    Three video cameras were controlled in real time from the ground to a sub-orbital rocket during a fifteen minute flight from White Sands Missile Range in New Mexico. Telemetry communications with the rocket allowed the control of the cameras. The pan, tilt, zoom, focus, and iris of two of the camera lenses, the power and record functions of the three cameras, and also the analog video signal that would be sent to the ground was controlled by separate microprocessors. A microprocessor was used to record data from three miniature accelerometers, temperature sensors and a differential pressure sensor. In addition to the selected video signal sent to the ground and recorded there, the video signals from the three cameras also were recorded on board the rocket. These recorders were mounted inside the pressurized segment of the rocket payload. The lenses, lens control mechanisms, and the three small television cameras were located in a portion of the rocket payload that was exposed to the vacuum of space. The accelerometers were also exposed to the vacuum of space

  9. Remote control and motion coordination of mobile robots

    NARCIS (Netherlands)

    Alvarez Aguirre, A.

    2011-01-01

    As robots destined for personal and professional applications advance towards becoming part of our daily lives, the importance and complexity of the control algorithms which regulate them should not be underestimated. This thesis is related to two fields within robotics which are of major importance

  10. Prosthodontic maintenance of overdentures on zirconia implants: 1-year results of a randomized controlled trial.

    Science.gov (United States)

    Osman, Reham B; Ma, Sunyoung

    2014-01-01

    The purpose of this study was to determine the prosthodontic outcomes of one-piece zirconia implants and their attachment systems in edentulous participants with maxillary and mandibular overdentures after 1 year of a randomized controlled trial. Random allocation of 24 edentulous participants (age range: 45 to 86 years) into titanium (control) or zirconia (test) groups using onepiece implants and a planned unsplinted prosthodontic design was performed. Four maxillary implants (one midpalatal; three anterior crestal) and three mandibular implants (one midsymphyseal; two bilateral distal) were conventionally loaded with the overdentures. Similar attachment systems were used throughout: ball abutment-type patrices (diameter: 2.25 to 3.1 mm as part of the one-piece implants) and custommade plastic matrices (with or without metal housings depending on the patrix size). Prosthodontic outcomes were documented during the first year of the clinical trial. Following three deaths and two dropouts, there were 19 participants who were available at the 1-year recall. Of these participants, 3 had early maxillary implant failure and had to be converted to conventional maxillary complete dentures opposing mandibular implant overdentures. There were 79 maintenance events, 34 in the titanium (control) group and 45 in the zirconia (test) group. Patrix loss occurred as a result of three zirconia implant fractures (one mandibular and two crestal maxillary implants). Maintenance events were principally the replacement of matrices and overdenture fracture. Although relines and replacement overdentures also occurred, overall there were no significant differences in prosthodontic maintenance between the control and test groups. A six-field prosthodontic-success analysis table showed no statistically significant difference between the two groups; however, 50% of participants in each group were allocated to the retreatment (repair) field, which produced a low prosthodontic success rate

  11. Neuropeptide Y2 receptors in anteroventral BNST control remote fear memory depending on extinction training.

    Science.gov (United States)

    Verma, Dilip; Tasan, Ramon; Sperk, Guenther; Pape, Hans-Christian

    2018-03-01

    The anterior bed nucleus of stria terminalis (BNST) is involved in reinstatement of extinguished fear, and neuropeptide Y2 receptors influence local synaptic signaling. Therefore, we hypothesized that Y2 receptors in anteroventral BNST (BNSTav) interfere with remote fear memory and that previous fear extinction is an important variable. C57BL/6NCrl mice were fear-conditioned, and a Y2 receptor-specific agonist (NPY 3-36 ) or antagonist (JNJ-5207787) was applied in BNSTav before fear retrieval at the following day. Remote fear memory was tested on day 16 in two groups of mice, which had (experiment 1) or had not (experiment 2) undergone extinction training after conditioning. In the group with extinction training, tests of remote fear memory revealed partial retrieval of extinction, which was prevented after blockade of Y2 receptors in BNSTav. No such effect was observed in the group with no extinction training, but stimulation of Y2 receptors in BNSTav mimicked the influence of extinction during tests of remote fear memory. Pharmacological manipulation of Y2 receptors in BNSTav before fear acquisition (experiment 3) had no effect on fear memory retrieval, extinction or remote fear memory. Furthermore, partial retrieval of extinction during tests of remote fear memory was associated with changes in number of c-Fos expressing neurons in BNSTav, which was prevented or mimicked upon Y2 blockade or stimulation in BNSTav. These results indicate that Y2 receptor manipulation in BNSTav interferes with fear memory and extinction retrieval at remote stages, likely through controlling neuronal activity in BNSTav during extinction training. Copyright © 2018 Elsevier Inc. All rights reserved.

  12. Intelligent controller of a flexible hybrid robot machine for ITER assembly and maintenance

    International Nuclear Information System (INIS)

    Al-saedi, Mazin I.; Wu, Huapeng; Handroos, Heikki

    2014-01-01

    Highlights: • Studying flexible multibody dynamic of hybrid parallel robot. • Investigating fuzzy-PD controller to control a hybrid flexible hydraulically driven robot. • Investigating ANFIS-PD controller to control a hybrid flexible robot. Compare to traditional PID this method gives better performance. • Using the equilibrium of reaction forces between the parallel and serial parts of hybrid robot to control the serial part hydraulically driven. - Abstract: The assembly and maintenance of International Thermonuclear Experimental Reactor (ITER) vacuum vessel (VV) is highly challenging since the tasks performed by the robot involve welding, material handling, and machine cutting from inside the VV. To fulfill the tasks in ITER application, this paper presents a hybrid redundant manipulator with four DOFs provided by serial kinematic axes and six DOFs by parallel mechanism. Thus, in machining, to achieve greater end-effector trajectory tracking accuracy for surface quality, a robust control of the actuators for the flexible link has to be deduced. In this paper, the intelligent control of a hydraulically driven parallel robot part based on the dynamic model and two control schemes have been investigated: (1) fuzzy-PID self tuning controller composed of the conventional PID control and with fuzzy logic; (2) adaptive neuro-fuzzy inference system-PID (ANFIS-PID) self tuning of the gains of the PID controller, which are implemented independently to control each hydraulic cylinder of the parallel robot based on rod position predictions. The obtained results of the fuzzy-PID and ANFIS-PID self tuning controller can reduce more tracking errors than the conventional PID controller. Subsequently, the serial component of the hybrid robot can be analyzed using the equilibrium of reaction forces at the universal joint connections of the hexa-element. To achieve precise positional control of the end effector for maximum precision machining, the hydraulic cylinder should

  13. Intelligent controller of a flexible hybrid robot machine for ITER assembly and maintenance

    Energy Technology Data Exchange (ETDEWEB)

    Al-saedi, Mazin I., E-mail: mazin.al-saedi@lut.fi; Wu, Huapeng; Handroos, Heikki

    2014-10-15

    Highlights: • Studying flexible multibody dynamic of hybrid parallel robot. • Investigating fuzzy-PD controller to control a hybrid flexible hydraulically driven robot. • Investigating ANFIS-PD controller to control a hybrid flexible robot. Compare to traditional PID this method gives better performance. • Using the equilibrium of reaction forces between the parallel and serial parts of hybrid robot to control the serial part hydraulically driven. - Abstract: The assembly and maintenance of International Thermonuclear Experimental Reactor (ITER) vacuum vessel (VV) is highly challenging since the tasks performed by the robot involve welding, material handling, and machine cutting from inside the VV. To fulfill the tasks in ITER application, this paper presents a hybrid redundant manipulator with four DOFs provided by serial kinematic axes and six DOFs by parallel mechanism. Thus, in machining, to achieve greater end-effector trajectory tracking accuracy for surface quality, a robust control of the actuators for the flexible link has to be deduced. In this paper, the intelligent control of a hydraulically driven parallel robot part based on the dynamic model and two control schemes have been investigated: (1) fuzzy-PID self tuning controller composed of the conventional PID control and with fuzzy logic; (2) adaptive neuro-fuzzy inference system-PID (ANFIS-PID) self tuning of the gains of the PID controller, which are implemented independently to control each hydraulic cylinder of the parallel robot based on rod position predictions. The obtained results of the fuzzy-PID and ANFIS-PID self tuning controller can reduce more tracking errors than the conventional PID controller. Subsequently, the serial component of the hybrid robot can be analyzed using the equilibrium of reaction forces at the universal joint connections of the hexa-element. To achieve precise positional control of the end effector for maximum precision machining, the hydraulic cylinder should

  14. Controlled Remote State Preparation via General Pure Three-Qubit State

    Directory of Open Access Journals (Sweden)

    Yuebo Zha

    2015-07-01

    Full Text Available The protocols for controlled remote state preparation of a single qubit and a general two-qubit state are presented in this paper. The general pure three-qubit states are chosen as shared quantum channel, which are not Local operations and classical communication (LOCC equivalent to the mostly used GHz state. This is the first time that general pure three-qubit states have been introduced to complete remote state preparation. The probability of successful preparation is presented. Moreover, in some special cases, the successful probability could reach a unit value.

  15. THE REMOTE AND MOBILE AIR TRAFFIC CONTROL TOWER AND ITS POSSIBLE APPLICATION TO THE OPERATIONAL AREA

    Directory of Open Access Journals (Sweden)

    Tímea VAS

    2014-10-01

    Full Text Available The concept of remote and mobile Air Traffic Control Tower (ATC TWR and its development has started in Europe, Australia and also in the USA, in order to improve the efficiency of Air Traffic Management (ATM systems in terms of air transportation safety. These new technologies are applicable in many countries in peace time, but on mobility reasons these are promoted to achieve commitments in the operational area. This article describes the devices and range of equipment of mobile and remote tower, and their specifications, which can even serve a medium sized airport, furthermore examines, whether how can those provide the air traffic services at an operational airfield.

  16. Remote control of the industry processes. POWERLINK protocol application

    Science.gov (United States)

    Wóbel, A.; Paruzel, D.; Paszkiewicz, B.

    2017-08-01

    The present technological development enables the use of solutions characterized by a lower failure rate, and work with greater precision. This allows you to obtain the most efficient production, high speed production and reliability of individual components. The main scope of this article was POWERLINK protocol application for communication with the controller B & R through communication Ethernet for recording process parameters. This enables control of run production cycle using an internal network connected to the PC industry. Knowledge of the most important parameters of the production in real time allows detecting of a failure immediately after occurrence. For this purpose, the position of diagnostic use driver X20CP1301 B&R to record measurement data such as pressure, temperature valve between the parties and the torque required to change the valve setting was made. The use of POWERLINK protocol allows for the transmission of information on the status of every 200 μs.

  17. Device for remote control of monitoring of a conveyor line

    Energy Technology Data Exchange (ETDEWEB)

    Shubin, N F; Rybak, Yu I

    1981-01-01

    The known device under mine conditions because of the decrease of resistance of the insulation of the current-carrying lines of the transfer line does not guarantee reliable protection from false triggering. The purpose of the invention is to improve the reliability of monitoring and control by improving interference-resistance of the device. This goal is achieved because the compensation block is equipped with a transistor, seven diodes, three stabilitrons and resistors united into two compensation circuits which are connected in parallel. The first of them is formed by two stabilitrons connected in series, where the cathode of one of them through a resistor and the counter-connected first diode is connected to a common lead and to the first pole of the block of monitoring and control. The anode of the other through the second counter-connected diode is connected to the second pole of the block of monitoring and control. The second compensation circuit is formed of a transistor, whose collector is connected to the common lead. The emitter is connected through the resistor to the cathode of the third diode whose anode is connected to the lead of the communications line and to the anodes of the fourth diode directly, and the fifth through the resistor, and with the cathode of the third stabilitron whose anode is connected to the transistor base and through the resistor to the common lead. The cathode of the fourth diode is connected to the common point of the first and second stabilitrons through the resistor, connected through the sixth diode, connected by cathode to the cathode of the fourth diode, parallel to the information block. The cathode of the fifth diode is connected to the anode of the second diode, and the second pole of the block of monitoring and control is connected to the communications lead through the seventh diode, connected counter to the fourth and fifth diodes.

  18. Hierarchical Controlled Remote State Preparation by Using a Four-Qubit Cluster State

    Science.gov (United States)

    Ma, Peng-Cheng; Chen, Gui-Bin; Li, Xiao-Wei; Zhan, You-Bang

    2018-06-01

    We propose a scheme for hierarchical controlled remote preparation of an arbitrary single-qubit state via a four-qubit cluster state as the quantum channel. In this scheme, a sender wishes to help three agents to remotely prepare a quantum state, respectively. The three agents are divided into two grades, that is, an agent is in the upper grade and other two agents are in the lower grade. In this process of remote state preparation, the agent of the upper grade only needs the assistance of any one of the other two agents for recovering the sender's original state, while an agent of the lower grade needs the collaboration of all the other two agents. In other words, the agents of two grades have different authorities to reconstruct sender's original state.

  19. Hierarchical Controlled Remote State Preparation by Using a Four-Qubit Cluster State

    Science.gov (United States)

    Ma, Peng-Cheng; Chen, Gui-Bin; Li, Xiao-Wei; Zhan, You-Bang

    2018-02-01

    We propose a scheme for hierarchical controlled remote preparation of an arbitrary single-qubit state via a four-qubit cluster state as the quantum channel. In this scheme, a sender wishes to help three agents to remotely prepare a quantum state, respectively. The three agents are divided into two grades, that is, an agent is in the upper grade and other two agents are in the lower grade. In this process of remote state preparation, the agent of the upper grade only needs the assistance of any one of the other two agents for recovering the sender's original state, while an agent of the lower grade needs the collaboration of all the other two agents. In other words, the agents of two grades have different authorities to reconstruct sender's original state.

  20. Automation and Control Learning Environment with Mixed Reality Remote Experiments Architecture

    Directory of Open Access Journals (Sweden)

    Frederico M. Schaf

    2007-05-01

    Full Text Available This work aims to the use of remotely web-based experiments to improve the learning process of automation and control systems theory courses. An architecture combining virtual learning environments, remote experiments, students guide and experiments analysis is proposed based on a wide state of art study. The validation of the architecture uses state of art technologies and new simple developed programs to implement the case studies presented. All implementations presented use an internet accessible virtual learning environment providing educational resources, guides and learning material to create a distance learning course associated with the remote mixed reality experiment. This work is part of the RExNet consortium, supported by the European Alfa project.