  2. Regulation of chemical safety at fuel cycle facilities by the United States Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Ramsey, Kevin M.

    2013-01-01

    When the U.S. Nuclear Regulatory Commission (NRC) was established in 1975, its regulations were based on radiation dose limits. Chemical hazards rarely influenced NRC regulations. After the Three Mile Island reactor accident in 1979, the NRC staff was directed to address emergency planning at non-reactor facilities. Several fuel cycle facilities were ordered to submit emergency plans consistent with reactor emergency plans because no other guidance was available. NRC published a notice that it was writing regulations to codify the requirements in the Orders and upgrade the emergency plans to address all hazards, including chemical hazards. The legal authority of NRC to regulate chemical safety was questioned. In 1986, an overfilled uranium hexafluoride cylinder ruptured and killed a worker. The NRC staff was directed to address emergency planning for hazardous chemicals in its regulations. The final rule included a requirement for fuel cycle facilities to certify compliance with legislation requiring local authorities to establish emergency plans for hazardous chemicals. As with emergency planning, NRC's authority to regulate chemical safety during routine operations was limited. NRC established memoranda of understanding (MOUs) with other regulatory agencies to encourage exchange of information between the agencies regarding occupational hazards. In 2000, NRC published new, performance-based, regulations for fuel cycle facilities. The new regulations required an integrated safety analysis (ISA) which used quantitative standards to assess chemical exposures. Some unique chemical exposure cases were addressed while implementing the new regulations. In addition, some gaps remain in the regulation of hazardous chemicals at fuel cycle facilities. The status of ongoing efforts to improve regulation of chemical safety at fuel cycle facilities is discussed. (authors)

  3. Federal Energy Regulatory Commission (FERC) Regions

    Data.gov (United States)

    Department of Homeland Security — Federal Energy Regulatory Commission (FERC) Regions. FERC is an independent agency that regulates the interstate transmission of electricity, natural gas, and oil....

  4. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1992-01-01

    This is the thirty-sixth volume of issuances (1-396) of the Nuclear Regulatory Commission and its Atomic Safety and Licensing Boards, Administrative Law Judges, and Office Directors. It covers the period from July 1, 1992-December 31, 1992. Atomic Safety and Licensing Boards are authorized by Section 191 of the Atomic Energy Act of 1954. These Boards, comprised of three members conduct adjudicatory hearings on applications to construct and operate nuclear power plants and related facilities and issue initial decisions which, subject to internal review and appellate procedures, become the final Commission action with respect to those applications. Boards are drawn from the Atomic Safety and Licensing Board Panel, comprised of lawyers, nuclear physicists and engineers, environmentalists, chemists, and economists. The Atomic Energy Commission first established Licensing Boards in 1962 and the Panel in 1967

  5. Nuclear Regulatory Commission information digest

    International Nuclear Information System (INIS)

    1990-03-01

    The Nuclear Regulatory Commission information digest provides summary information regarding the US Nuclear Regulatory Commission, its regulatory responsibilities, and areas licensed by the commission. This is an annual publication for the general use of the NRC Staff and is available to the public. The digest is divided into two parts: the first presents an overview of the US Nuclear Regulatory Commission and the second provides data on NRC commercial nuclear reactor licensees and commercial nuclear power reactors worldwide

  6. Total System Performance Assessment Sensitivity Analyses for Final Nuclear Regulatory Commission Regulations

    International Nuclear Information System (INIS)

    Bechtel SAIC Company

    2001-01-01

    This Letter Report presents the results of supplemental evaluations and analyses designed to assess long-term performance of the potential repository at Yucca Mountain. The evaluations were developed in the context of the Nuclear Regulatory Commission (NRC) final public regulation, or rule, 10 CFR Part 63 (66 FR 55732 [DIRS 156671]), which was issued on November 2, 2001. This Letter Report addresses the issues identified in the Department of Energy (DOE) technical direction letter dated October 2, 2001 (Adams 2001 [DIRS 156708]). The main objective of this Letter Report is to evaluate performance of the potential Yucca Mountain repository using assumptions consistent with performance-assessment-related provisions of 10 CFR Part 63. The incorporation of the final Environmental Protection Agency (EPA) standard, 40 CFR Part 197 (66 FR 32074 [DIRS 155216]), and the analysis of the effect of the 40 CFR Part 197 EPA final rule on long-term repository performance are presented in the Total System Performance Assessment--Analyses for Disposal of Commercial and DOE Waste Inventories at Yucca Mountain--Input to Final Environmental Impact Statement and Site Suitability Evaluation (BSC 2001 [DIRS 156460]), referred to hereafter as the FEIS/SSE Letter Report. The Total System Performance Assessment (TSPA) analyses conducted and documented prior to promulgation of the NRC final rule 10 CFR Part 63 (66 FR 55732 [DIRS 156671]), were based on the NRC proposed rule (64 FR 8640 [DIRS 101680]). Slight differences exist between the NRC's proposed and final rules which were not within the scope of the FEIS/SSE Letter Report (BSC 2001 [DIRS 156460]), the Preliminary Site Suitability Evaluation (PSSE) (DOE 2001 [DIRS 155743]), and supporting documents for these reports. These differences include (1) the possible treatment of ''unlikely'' features, events and processes (FEPs) in evaluation of both the groundwater protection standard and the human-intrusion scenario of the individual

  7. Nuclear Regulatory Commission: more aggressive leadership needed

    International Nuclear Information System (INIS)

    Staats, E.B.

    1980-01-01

    The Energy Reorganization Act of 1974 which established the Nuclear Regulatory Commission required GAO to evaluate the Commission's performance by January 18, 1980. This report responds to that requirement. GAO concluded that, although improvements have been made, the Commission's nuclear regulatory performance can be characterized best as slow, indecisive, cautious - in a word, complacent. This has largely resulted from a lack of aggressive leadership as evidenced by the Commissioners' failure to establish regulatory goals, control policymaking, and most importantly, clearly define their roles in nuclear regulation

  8. The Energy Regulatory Commission. The Regulation of Natural Gas in Mexico

    International Nuclear Information System (INIS)

    1995-01-01

    In May of 1995 the Congress approved amendments to the Regulatory Law of Constitutional article 27 on Petroleum. This legal reform fundamentally redefined the petroleum industry and authorizes the private sector to construct, operate, and own natural gas transportation, storage and distribution systems-activities previously reserved to the state. To complement these reforms and to implement the legislative mandate of the Regulatory Law on Petroleum, the Natural Gas Regulation (Reglamento de Gas Natural) was issued in November 1995. The regulation reconciles the interests of the various natural gas industry participants and signifies a Federal Commitment to promote comprehensive development of the industry. In parallel with the development of the substantive legal framework, the law of the Comision Reguladora de Energia (CRE) was also enacted by Congress in October 1995 to strength the institutional framework and implemented the legal changes. This law defines the CRE as an agency of the Energy Ministry with technical, operational, and budgetary autonomy, and responsibility for implementing natural gas industry regulation. (Author)

  9. Nuclear Regulatory Commission Issuances

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM).

  10. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1993-08-01

    This report includes the issuances received during the specified period from the commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors; Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  11. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1992-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  13. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1994-03-01

    This report includes the issuances received during the specified period from Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  14. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1996-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  15. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Nuclear Regulatory Commission issuances

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    This report includes the issuances received during the specified period from Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM).

  17. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-11-01

    This report includes the issuances received during the specified period from the Commission (CLl), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  18. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1994-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Director's Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  19. Nuclear Regulatory Commission Issuance

    International Nuclear Information System (INIS)

    1994-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (AU), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1994-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  2. 75 FR 11166 - Joint Meeting of the Nuclear Regulatory Commission and the Federal Energy Regulatory Commission...

    Science.gov (United States)

    2010-03-10

    ... the Nuclear Regulatory Commission and the Federal Energy Regulatory Commission; Notice of Joint Meeting of the Nuclear Regulatory Commission and the Federal Energy Regulatory Commission March 2, 2010. The Federal Energy Regulatory Commission (FERC) and the Nuclear Regulatory Commission (NRC) will hold...

  3. Review of NRC Commission Papers on Regulatory Basis for Licensing and Regulating Reprocessing Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Park, Jae Yeong; Shin, Hyeong Ki [KINS, Daejeon (Korea, Republic of)

    2016-05-15

    Spent nuclear fuel (SNF) accumulated in nuclear power plant has been a serious issue in most countries with operating nuclear power plants. Direct disposal of SNF could be a solution of the problem but many countries including the Republic of Korea have had a hard time selecting a site for high level waste repository because of low public acceptance. SNF recycling technologies consisting of reprocessing and transmutation have been developed so as to reduce the final volume of the disposed radioactive waste and to diminish the radiotoxicity of the waste. The Republic of Korea is now developing pyroprocessing and sodium-cooled fast reactor (SFR) technology to be used for the recycling of the wastes. KAERI has a plan to construct a pyroprocessing facility with a capacity of 30 tHM/y and a facility manufacturing TRU fuel for SFR by 2025. However, to license these facility and secure the safety, the current regulatory system related to SNF treatment needs to be improved and amended since the system has been developed focusing on facilities to examine irradiated nuclear materials. Status of reprocessing facility regulations developed by U.S.NRC was reviewed based on SECY papers. U.S.NRC has approved the development of a new rule referred to nationally as '10CFR Part 7x'. Existing 10CFR 50 and 70 has been evolved mainly for nuclear power plants and fuel cycle facilities whose radiological hazard is much lower than reprocessing plants respectively. U.S.NRC also derived many regulatory gaps including safety assessment methods, technical specification, general design criteria and waste classification and continue to develop the regulatory framework limited in scope to the resolution of Gap 5.

  4. Nuclear regulatory commission issuances

    International Nuclear Information System (INIS)

    1989-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1982-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking

  6. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1986-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  7. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1994-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  8. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1997-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  9. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1989-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Danials of Petitions for Rulemaking (DPRM)

  11. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1989-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1987-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  13. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1990-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  14. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  15. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1982-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Director's Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1981-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking

  17. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1987-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  18. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1988-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  19. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1989-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear regulatory commission issuances

    International Nuclear Information System (INIS)

    1990-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1997-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  2. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1986-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  4. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1988-01-01

    This report includes the issuance received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Nuclear Regulatory Commission issuances

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance.

  6. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1988-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  7. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1988-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  8. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1991-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  9. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1990-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1988-06-01

    This report includes the issuances received during the specified period from the commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  11. Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1981-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1987-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  13. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1982-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking

  14. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1990-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety And Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  15. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1985-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1990-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  17. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1982-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  18. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1988-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  19. PRA research and the development of risk-informed regulation at the U.S. nuclear regulatory commission

    International Nuclear Information System (INIS)

    Siu, Nathan; Collins, Dorothy

    2008-01-01

    Over the years, Probabilistic Risk Assessment (PRA) research activities conducted at the U.S. Nuclear Regulatory Commission (NRC) have played an essential role in support of the agency's move towards risk-informed regulation. These research activities have provided the technical basis for NRC's regulatory activities in key areas; provided PRA methods, tools, and data enabling the agency to meet future challenges; supported the implementation of NRC's 1995 PRA Policy Statement by assessing key sources of risk; and supported the development of necessary technical and human resources supporting NRC's risk-informed activities. PRA research aimed at improving the NRC's understanding of risk can positively affect the agency's regulatory activities, as evidenced by three case studies involving research on fire PRA, Human Reliability Analysis (HRA), and Pressurized Thermal Shock (PTS) PRA. These case studies also show that such research can take a considerable amount of time, and that the incorporation of research results into regulatory practice can take even longer. The need for sustained effort and appropriate lead time is an important consideration in the development of a PRA research program aimed at helping the agency address key sources of risk for current and potential future facilities

  20. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1982-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions For Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or to have any independent legal significance

  1. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1989-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety nd Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  2. Nuclear Regulatory Commission issuances

    International Nuclear Information System (INIS)

    1996-04-01

    This report includes the issuances received during the April 1996 reporting period from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking. Included are issuances pertaining to: (1) Yankee Nuclear Power Station, (2) Georgia Tech Research Reactor, (3) River Bend Station, (4) Millstone Unit 1, (5) Thermo-Lag fire barrier material, and (6) Louisiana Energy Services

  3. Nuclear Regulatory Commission issuances

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-04-01

    This report includes the issuances received during the April 1996 reporting period from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors` Decisions, and the Decisions on Petitions for Rulemaking. Included are issuances pertaining to: (1) Yankee Nuclear Power Station, (2) Georgia Tech Research Reactor, (3) River Bend Station, (4) Millstone Unit 1, (5) Thermo-Lag fire barrier material, and (6) Louisiana Energy Services.

  4. NRC [Nuclear Regulatory Commission] safety research in support of regulation, 1987

    International Nuclear Information System (INIS)

    1988-05-01

    This report, the third in a series of annual reports, was prepared in response to congressional inquiries concerning how nuclear regulatory research is used. It summarizes the accomplishments of the Office of Nuclear Regulatory Research during 1987. The goal of this office is to ensure that research provides the technical bases for rulemaking and for related decisions in support of NRC licensing and inspection activities. This report describes both the direct contributions to scientific and technical knowledge with regard to nuclear safety and their regulatory applications

  5. Nuclear Regulatory Commission 1989 Information Digest

    International Nuclear Information System (INIS)

    1989-03-01

    The Nuclear Regulatory Commission 1989 Information Digest provides summary information regarding the US Nuclear Regulatory Commission, its regulatory responsibilities, and areas licensed by the Commission. This is the first of an annual publication for the general use of the NRC staff and is available to the public. The Digest is divided into two parts: the first presents an overview of the US Nuclear Regulatory Commission and the second provides data on NRC commercial nuclear reactor licensees and commercial nuclear power reactors worldwide

  6. U.S. Nuclear Regulatory Commission seismic regulations, research, and emerging trends

    Energy Technology Data Exchange (ETDEWEB)

    Chokshi, N C; Shao, L C [Nuclear Regulatory Commission, Washington, DC (United States). Office of Nuclear Regulatory Research; Apostolakis, G

    1997-03-01

    Historically in the United States, seismic issues have played an important role in determining site suitability and, in some cases, have determined the ultimate fate of power plants. During the late 1960s and early 1970s, a seismic design philosophy evolved as the licensing of the earlier plants was in progress. Concepts such as the Safe Shutdown Earthquake (SSE) and the Operating Basis Earthquake (OBE) emerged and were codified into the federal regulations with the publication in December 1973 of Appendix A, `Seismic and Geologic Siting Criteria for Nuclear Power Plants,` to 10 CFR Part 100, `Reactor Site Criteria.` Seismic considerations are also important in siting and design of other fuel cycle and waste facilities. In this paper, a brief overview of the current seismic siting and design regulations are described along with some recent and planned changes based on the past experience, advancement in the state-of-the-art, and research results. In particular, the recently revised siting rule and use of the probabilistic seismic hazard analysis in implementation of the rule will be described in more detail. The paper includes discussion of some recent seismic issues and research activities, including issues related to aging. Some emerging trends are highlighted. In particular, the paper focuses on use of `expert opinion` in the probabilistic analysis and risk informed regulations and their implications to the seismic design. An additional focus is on international cooperative programs and how to initiate such programs such that better use can be made of limited resources to resolve issues of common interest. (author)

  7. U.S. Nuclear Regulatory Commission seismic regulations, research, and emerging trends

    International Nuclear Information System (INIS)

    Chokshi, N.C.; Shao, L.C.; Apostolakis, G.

    1997-01-01

    Historically in the United States, seismic issues have played an important role in determining site suitability and, in some cases, have determined the ultimate fate of power plants. During the late 1960s and early 1970s, a seismic design philosophy evolved as the licensing of the earlier plants was in progress. Concepts such as the Safe Shutdown Earthquake (SSE) and the Operating Basis Earthquake (OBE) emerged and were codified into the federal regulations with the publication in December 1973 of Appendix A, 'Seismic and Geologic Siting Criteria for Nuclear Power Plants,' to 10 CFR Part 100, 'Reactor Site Criteria.' Seismic considerations are also important in siting and design of other fuel cycle and waste facilities. In this paper, a brief overview of the current seismic siting and design regulations are described along with some recent and planned changes based on the past experience, advancement in the state-of-the-art, and research results. In particular, the recently revised siting rule and use of the probabilistic seismic hazard analysis in implementation of the rule will be described in more detail. The paper includes discussion of some recent seismic issues and research activities, including issues related to aging. Some emerging trends are highlighted. In particular, the paper focuses on use of 'expert opinion' in the probabilistic analysis and risk informed regulations and their implications to the seismic design. An additional focus is on international cooperative programs and how to initiate such programs such that better use can be made of limited resources to resolve issues of common interest. (author)

  8. Nuclear Regulatory Commission Information Digest 1992 edition

    International Nuclear Information System (INIS)

    Olive, K.

    1992-03-01

    The Nuclear Regulatory Commission Information Digest provides a summary of information about the US Nuclear Regulatory Commission (NRC), NRC's regulatory responsibilities, the activities NRC licenses, and general information on domestic and worldwide nuclear energy. This digest is a compilation of nuclear- and NRC-related data and is designed to provide a quick reference to major facts about the agency and industry it regulates. In general, the data cover 1975 through 1991, with exceptions noted. Information on generating capacity and average capacity factor for operating US commercial nuclear power reactors is obtained from monthly operating reports that are submitted directly to the NRC by the licensee. This information is reviewed by the NRC for consistency only and no independent validation and/or verification is performed

  9. Nuclear Regulatory Commission Information Digest, 1991 edition

    International Nuclear Information System (INIS)

    Olive, K.L.

    1991-03-01

    The Nuclear Regulatory Commission Information Digest provides a summary of information about the US Nuclear Regulatory Commission (NRC), NRC's regulatory responsibilities, and the areas NRC licenses. This digest is a compilation of NRC-related data and is designed to provide a quick reference to major facts about the agency and the industry it regulates. In general, the data cover 1975 through 1990, with exceptions noted. For operating US commercial nuclear power reactors, information on generating capacity and average capacity factor is obtained from Monthly Operating Reports submitted to the NRC directly by the licensee. This information is reviewed for consistency only. No independent validation and/or verification is performed by the NRC. For detailed and complete information about tables and figures, refer to the source publications. This digest is published annually for the general use of the NRC staff and is available to the public. 30 figs., 12 tabs

  10. Nuclear Regulatory Commission Information Digest: 1993 edition

    International Nuclear Information System (INIS)

    1993-03-01

    The Nuclear Regulatory Commission Information Digest (digest) provides a summary of information about the U.S. Nuclear Regulatory Commission (NRC), NRC's regulatory responsibilities, the activities NRC licenses, and general information on domestic and worldwide nuclear energy. The digest, published annually, is a compilation of nuclear- and NRC-related data and is designed to provide a quick reference to major facts about the agency and the industry it regulates. In general, the data cover 1975 through 1992, with exceptions noted. Information on generating capacity and average capacity factor for operating U.S. commercial nuclear power reactors is obtained from monthly operating reports that are submitted directly to the NRC by the licensee. This information is reviewed by the NRC for consistency only and no independent validation and/or verification is performed. Comments and/or suggestions on the data presented are welcomed and should be directed to Karen Olive, United States Nuclear Regulatory Commission, Office of the Controller, Division of Budget and Analysis, Washington, D.C. 20555. For detailed and complete information about tables and figures, refer to the source publications

  11. Regulation of Federal radioactive waste activities. Report to Congress on extending the Nuclear Regulatory Commission's licensing or regulatory authority to Federal radioactive waste storage and disposal activities

    International Nuclear Information System (INIS)

    1979-09-01

    The report contains two recommendations for extending the Commission's regulatory authority: (1) NRC licensing authority should be extended to cover all new DOE facilities for disposal of transuranic (TRU) waste and nondefense low-level waste. (2) A pilot program, focused on a few specific DOE waste management activities, should be established to test the feasibility of extending NRC regulatory authority on a consultative basis to DOE waste management activities not now covered by NRC's licensing authority or its extension as recommended in Recommendation 1

  12. Federal Energy Regulatory Commission fiscal year 1997 annual financial statements

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-02-24

    This report presents the results of the independent certified public accountants` audit of the Federal Energy Regulatory commission`s statements of financial position, and the related statements of operations and changes in net position. The auditors` work was conducted in accordance with generally accepted government auditing standards. An independent public accounting firm conducted the audit. The auditors` reports on the Commission`s internal control structure and compliance with laws and regulations disclosed no reportable conditions or instances of noncompliance.

  13. Nuclear Regulatory Commission: 1981 annual report

    International Nuclear Information System (INIS)

    1981-01-01

    This seventh annual report of the US Nuclear Regulatory Commission covers major actions, events and planning that occurred during fiscal year 1981, with some coverage of later events, where appropriate. Chapters of the report address the agency's various functions or areas of activity: regulating nuclear power plants; evaluating reactor operating experience; licensing nuclear materials and their transportation; safeguarding nuclear plants and materials; managing nuclear wastes; inspection and enforcement; cooperation with state governments; international activities; research and standards development; hearings; decisions and litigation; and administrative and public communications matters. Each chapter presents a detailed review of program accomplishments during the report period, fiscal year 1981

  14. Regulating Nuclear Reactor Construction and Commissioning, and Preparation for Operation – Challenges for a New Regulatory Body

    International Nuclear Information System (INIS)

    Viktorsson, C.

    2016-01-01

    Following an introduction with a description of the peaceful nuclear energy program in the United Arab Emirates (UAE) and an overview of the regulatory framework for safety, security and safeguards, this paper describes the regulatory approach for oversight of construction and the granting of an Operating Licence for the first nuclear power plant in the UAE. The paper describes the inspection programme set up by the Federal Authority for Nuclear Regulation (FANR) to verify construction and preoperational testing by the licensee. Moreover, it outlines the content of the operating licence application and focus areas for the regulatory review and assessment. Also, the paper describes the basic elements required by FANR for the decision-making regarding the issuance of the Operating Licence including integration of the results of review and assessment and the implementation of a systematic inspection programme to ensure operational readiness to operate and maintain the plant in accordance with FANR regulations. Finally, the paper addresses the preparation for regulatory oversight and the skill-set needed at FANR to ensure an effective and efficient oversight of safety, security of the nuclear energy power in the UAE. (author)

  15. Status report on the Nuclear Regulatory Commission regulations for land disposal of low-level radioactive wastes and geologic repository disposal of high-level wastes

    International Nuclear Information System (INIS)

    Browning, R.E.; Bell, M.J.; Dragonette, K.S.; Johnson, T.C.; Roles, G.W.; Lohaus, P.H.; Regnier, E.P.

    1984-01-01

    On 27 December 1982, the United States Nuclear Regulatory Commission (NRC) amended its regulations to provide specific requirements for licensing the land disposal of low-level radioactive wastes. The regulations establish performance objectives for land disposal of waste; technical requirements for the siting, design, operations, and closure activities for a near-surface disposal facility; technical requirements concerning waste form and classification that waste generators must meet for the land disposal of waste; institutional requirements; financial assurance requirements; and administrative and procedural requirements for licensing a disposal facility. Waste generators must comply with the waste form and classification provisions of the new rule, on 27 December 1983, one year later. During this implementation period, licensees must develop programmes to ensure compliance with the new waste form and classification provisions. The NRC is also promulgating regulations specifying the technical criteria for disposal of high-level radioactive wastes in geological repositories. The proposed rule was published for public comment in July 1981. Public comments have been received and considered by the Commission staff. The Commission will soon approve and publish a revised final rule. While the final rule being considered by the Commission is fundamentally the same as the proposed rule, provisions have been added to permit flexibility in the application of numerical criteria, some detailed design requirements have been deleted, and other changes have been made in response to comments. The rule is consistent with the recently enacted Nuclear Waste Policy Act of 1982. (author)

  16. US Nuclear Regulatory Commission annual report, 1985. Volume 2

    International Nuclear Information System (INIS)

    1986-01-01

    The decisions and actions of the Nuclear Regulatory Commission (NRC) during fiscal year 1985 are reported. Areas covered include reactor regulation, cleanup at Three Mile Island, analysis and evaluation of operational experience, nuclear materials, waste management, safeguards, inspection, enforcement, quality assurance, emergency preparedness, and nuclear regulatory research. Also, cooperation with the states, international programs, proceedings and litigation, and management are discussed

  17. 77 FR 8095 - Technical Corrections to Commission Regulations

    Science.gov (United States)

    2012-02-14

    ... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission 18 CFR Part 2 [Docket No. RM11-30-000; Order No. 756] Technical Corrections to Commission Regulations Issued February 8, 2012. AGENCY: Federal Energy Regulatory Commission, DOE. ACTION: Final rule: correcting amendment. SUMMARY: This document adds...

  18. Nuclear Regulatory Commission Issuances, November 1980

    International Nuclear Information System (INIS)

    1980-11-01

    Contents: Issuances of the Nuclear Regulatory Commission; Issuances of the Atomic Safety and Licensing Appeal Boards; Issuances of the Atomic Safety and Licensing Boards; and Issuances of the Directors Denial

  19. Nuclear Regulatory Commission Issuances, December 1980

    International Nuclear Information System (INIS)

    1980-12-01

    Contents: Issuances of the Nuclear Regulatory Commission; Issuances of the Atomic Safety and Licensing Appeal Boards; Issuances of the Atomic Safety and Licensing Boards; and Issuances of the Directors Denial

  20. Nuclear Regulatory Commission issuances, October 1993

    International Nuclear Information System (INIS)

    1993-10-01

    This document contains a Commission issuance in which the Commission denies the petitioners' motion to quash or modify a subpoena issued by the NRC staff in the course of an investigation to determine if the petitioners' have violated NRC regulations and to determine if safety-related problems exist at NRC-licensed facilities. The pertinent regulations and the Commission's Memorandum and Order are included

  1. Audit of the Federal Energy Regulatory Commission`s Office of Chief Accountant

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-04-07

    The Federal Energy Regulatory Commission`s (Commission) mission is to oversee America`s natural gas and oil pipeline transportation, electric utility, and hydroelectric power industries to ensure that consumers receive adequate energy supplies at just and reasonable rates. To carry out this mission, the Commission issues regulations covering the accounting, reporting, and rate-making requirements of the regulated utility companies. The Commission`s Office of Chief Accountant performs financial related audits at companies to ensure compliance with these regulations. The purpose of this audit was to evaluate the office of Chief Accountant`s audit performance. Specifically, the objectives were to determine if the most appropriate audit approach was used and if a quality assurance process was in place to ensure reports were accurate and supported by the working papers.

  2. 78 FR 44165 - Nuclear Regulatory Commission Enforcement Policy

    Science.gov (United States)

    2013-07-23

    ... NUCLEAR REGULATORY COMMISSION [NRC-2013-0159] Nuclear Regulatory Commission Enforcement Policy AGENCY: Nuclear Regulatory Commission. ACTION: Enforcement policy; request for comment. SUMMARY: The U.S... Policy. In SRM-SECY-12-0047, ``Revisions to the Nuclear Regulatory Commission Enforcement Policy,'' dated...

  3. 1992 Nuclear Regulatory Commission Annual Report

    International Nuclear Information System (INIS)

    1993-01-01

    This is the 18th annual report of the US Nuclear Regulatory Commission (NRC), covering events and activities occurring in fiscal year 1992 (the year ending September 30, 1992), with some treatment of events from the last quarter of calendar year 1992. The NRC was created by enactment in the Congress of the Energy Reorganization Act of 1974. It is an independent agency of the Federal Government. The five NRC Commissioners are nominated by the President and confirmed by the United States Senate. The Chairman of the Commission is appointed by the President from among the Commissioners confirmed

  4. Law of the Energy Regulatory Commission

    International Nuclear Information System (INIS)

    1995-01-01

    This Decree-Law consist of three chapters each on divided in articles and subsections and came into force in November 1 st., 1995. Chapter I, with the heading 'Nature and Powers', defines the Energy Regulatory Commission as a decentralized organ of the Energy Secretariat with technical and operative autonomy in terms of the law, and establish the conditions for the sell, generation, exportation and importation of electricity with destination to particular and public services. The sell transport, storage and distribution of natural gas, as well as the gas liquefied from petroleum are also considered. Chapter II with the heading 'Organization and duties' establish that the Commission is integrated by five Committee, the President included. The Committee members will deliberate in collegiate manner and the decisions are by majority, having the President a vote of quality. Chapter III for 'General provisions' is related to the lawsuits arises between the Commission and the users of services. (Author)

  5. Nuclear Regulatory Commission issuances, May 1993

    International Nuclear Information System (INIS)

    1993-05-01

    This report contains the issuances received during the specified period (May 1993) from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not deemed a part of these opinions or have any independent legal significance. Contents of this document include an Issuance of the Nuclear Regulatory Commission with respect to the Sacramento Municipal Utility District and Issuances of Directors' Decisions concerning the Interstate Nuclear Service Corporation; Niagara Mohawk Power Corporation; and Texas Utilities Electric Company, et al. and All Nuclear Power Plants with Thermo-Lag Fire Barriers

  6. Nuclear Regulatory Commission issuances, March 1975

    International Nuclear Information System (INIS)

    1975-04-01

    Reactor licensing actions taken by the Nuclear Regulatory Commission, the Atomic Safety and Licensing Appeal Board and the Atomic Safety and Licensing Boards for March 1975 are presented. Action was included for the following reactors: Big Rock Point Nuclear Plant; West Valley Reprocessing Plant; Limerick Generating Station, Units 1 and 2; Midland Plants, Units 1 and 2; Wolf Creek Generating Station, Unit 1; Monticello Nuclear Generating Plant, Unit 1; Douglas Point Nuclear Generating Station, Units 1 and 2; Seabrook Station, Units 1 and 2; Vermont Yankee Nuclear Power Station; and WPPSS Hanford Units 1 and 4. (U.S.)

  7. US Nuclear Regulatory Commission 1983 annual report

    International Nuclear Information System (INIS)

    1984-01-01

    The thirteen chapters of this annual report are titled: 1983 highlights/1984 planning; reactor regulation; cleanup at TMI-2; operational experience; nuclear materials; safeguards; waste management; inspection, enforcement and emergency preparedness; cooperation with the states; international programs; nuclear regulatory research; proceedings and litigation; and management and communication

  8. US Nuclear Regulatory Commission, 1984 annual report. Volume 1

    International Nuclear Information System (INIS)

    1985-01-01

    This is the 10th annual report of the US Nuclear Regulatory Commission (NRC). This report covers the major activities, events, decisions and planning that took place during fiscal year 1984 (October 1983 through September 1984) within the NRC or involving the NRC. Information is presented concerning 1984 highlights and planning for 1985; reactor regulation; cleanup at Three Mile Island Unit 2; operational experience; nuclear materials; safeguards; waste management; inspection, enforcement, quality assurance, and emergency preparedness; cooperation with the States; international programs; nuclear regulatory research; proceedings and litigation; and management and communication

  9. Securities and Exchange Commission Semiannual Regulatory Agenda

    Science.gov (United States)

    2010-04-26

    ...: 3235-AK58 420. REVISIONS TO REGULATION D Legal Authority: 15 USC 77b(a)(15); 15 USC 77b(b); 15 USC 77d; 15 USC 77r; 15 USC 77s; 15 USC 77s(a); 15 USC 77z-3 Abstract: The Division is considering... SOLICITATION ENHANCEMENTS Legal Authority: 15 USC 78n Abstract: The Commission proposed amendments to its proxy...

  10. 77 FR 34379 - Notice of Joint Meeting of the Nuclear Regulatory Commission and the Federal Energy Regulatory...

    Science.gov (United States)

    2012-06-11

    ... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD06-6-000] Notice of Joint Meeting of the Nuclear Regulatory Commission and the Federal Energy Regulatory Commission The Federal Energy Regulatory Commission (FERC) and the Nuclear Regulatory Commission (NRC) will hold a joint meeting...

  11. Nuclear Regulatory Commission Issuances, August 1981

    International Nuclear Information System (INIS)

    1981-01-01

    Contents include: Issuances of the Nuclear Regulatory Commission--Metropolitan Edison Company (Three Mile Island Nuclear Station, Unit No. 1), Metropolitan Edison Company, et al. (Three Mile Island Nuclear Station, Unit 1), Westinghouse Electric Corp. (Export of LEU to the Philippines); Issuances of Atomic Safety and Licensing Appeal Boards--Duke Power Company (Amendment to Materials License SNM-1773--Transportation of Spent Fuel from Oconee Nuclear Station for Storage at McGuire Nuclear Station); Issuances of the Atomic Safety Licensing Boards--Commonwealth Edison Company (Byron Station, Units 1 and 2), Dairyland Power Cooperative (La Crosse Boiling Water Reactor, Operating License and Show Cause), Florida Power and Light Company (St. Lucie Plant, Unit No. 2), Florida Power and Light Company (Turkey Point Nuclear Generating, Units 3 and 4), Metropolitan Edison Company (Three Mile Island Nuclear Station, Unit 1) Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2), The Regents of the University of California (UCLA Research Reactor), The Toledo Edison Company, et al. (Davis-Besse Nuclear Power Station, Units 2 and 3: Terminiation of Proceedings); Issuances of the Directors Denial--Florida Power and Light Company

  12. Nuclear Regulatory Commission Issuances, September 1981

    International Nuclear Information System (INIS)

    1981-01-01

    Contents include: Issuances of the Nuclear Regulatory Commission--Commonwealth Edison Company (Dresden Nuclear Power Station, Unit 1), Consolidated Edison Company of New York (Indian Point, Unit 2), Metropolitan Edison Company, et al. (Three Mile Island Nuclear Station, Unit 1), Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2), Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2), Power Authority of the State of New York (Indian Point, Unit 3), Texas Utilities Generating Company, et al. (Comanche Peak Steam Electric Station, Units 1 and 2); Issuances of Atomic Safety and Licensing Appeal Boards--Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2), Philadelphia Electric Company, et al. (Peach Bottom Atomic Power Statin, Units 2 and 3), Metropolitan Edison Company, et al. (Three Mile Island Nuclear Statin, Unit No. 2), Public Service Electric and Gas Company (Hope Creek Generating Station, Units 1 and 2), The Toledo Edison Company, et al. (Davis-Besse Nuclear Power Station, Units 2 and 3); Issuances of the Atomic Safety Licensing Boards--Cleveland Electric Illuminating Company, et al. (Perry Nuclear Power Plant, Units 1 and 2), Commonwealth Edison Company (Dresden Station, Units 2 and 3), Houston Lighting and Power Company (Allens Creek Nuclear Generating Station, Unit 1), Southern California Edison Company, et al. (San Onofre Nuclear Generating Station, Units 2 and 3), Texas Utilities Generating Company, et al. (Comanche Peak Steam Electric Station, Units 1 and 2), Texas Utilities Generating Company, et al

  13. The role of effective communications in Nuclear Regulatory Commission licensing

    International Nuclear Information System (INIS)

    Counsil, W.G.

    1991-01-01

    Communications are essential to the licensing and general regulatory program of the Nuclear Regulatory Commission. This paper attempts to identify and address certain aspects of, and approaches to, maintaining effective and efficient communications. It considers, from the perspective of the high-level radioactive waste repository program, both internal communication within the DOE itself and external communication with the Nuclear Regulatory Commission and interested parties. Many of the points presented are based on lessons learned from electric utility experience with nuclear plants

  14. Nuclear Regulatory Commission Issuances, May 81

    International Nuclear Information System (INIS)

    1981-05-01

    Contents: Issuances of the Nuclear Regulatory Commission--Consolidated Edison Company of New York, Inc. (Indian Point, Unit No. 2), Power Authority of the State of New York (Indian Point, No. 3 Nuclear Power Plant), Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2), Statement of Policy on Conduct of Licensing Proceedings, Uranium Mill Licensing Requirements; Issuances of Atomic Safety and Licensing Appeal Boards--Houston Lighting and Power Company, et al. (South Texas Project, Units 1 and 2), Metropolitan Edison Company, et al. (Three Mile Island Nuclear Station, Unit No. 2), Pennsylvania Power and Light Company and Allegheny Electric Cooperative, Inc. (Susquehanna Steam Electric Station, Units 1 and 2), Philadelphia Electric Company et al. (Peach Bottom Atomic Power Station, Units 2 and 3), Public Service Electric and Gas Company (Hope Creek Generating Station, Units 1 and 2); Issuances of the Atomic Safety and Licensing Boards--Duke Power Company (William B. McGuire Nuclear Station, Units 1 and 2), Florida Light and Power Company (Turkey Point Nuclear Generating, Units 3 and 4), Illinois Power Company, et al. (Clinton Power Station, Units 1 and 2), Sacramento Municipal Utility District (Rancho Seco Nuclear Generating Station); Issuances of the Directors Denial--Commonwealth Edison Company (Byron Station, Units 1 and 2), Consolidated Edison Company of New York, Inc. (Indian Point Unit No. 2), Gulf States Utilities Company (River Bend Station Units 1 and 2), Petition to Suspend All Operating Licenses for Pressurized Water Reactors (River Bend Station Units 1 and 2), Portland General Electric Company (Trojan Nuclear

  15. H.R. 5448: a bill to amend the Atomic Energy Act of 1954, as amended, to reorganize the functions of the Nuclear Regulatory Commission by abolishing the Commission and in its place establishing the Nuclear Regulation and Safety Agency. Introduced in the House of Representatives, Ninety-Ninth Congress, Second Session, August 15, 1986

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    The Omnibus Nuclear Safety Act of 1986 amends the Atomic Energy Act of 1954 by replacing the Nuclear Regulatory Commission with a new entity, the Nuclear Regulation and Safety Agency. The purposes are to promote an energy policy that is better coordinated and more consistent with the protection of public health and safety. The new agency would also expedite licensing for construction and operation of nuclear power plants by using pre-approved standardized designs and sites

  16. Nuclear Regulatory Commission and its role in environmental standards

    International Nuclear Information System (INIS)

    Mattson, R.J.

    1976-01-01

    The NRC and its predecessors in the Atomic Energy Commission represent considerable experience in environmental standards setting. The Atomic Energy Act of 1954, the 1970 Supreme Court decision on Federal pre-emption of radiation standards, the Calvert Cliffs decision of 1971, the Energy Reorganization Act of 1974, and the Appendix I ''as low as reasonably achievable'' decision of 1975, to name a few of our landmarks, are representative of the scars and the achievements of being in a role of national leadership in radiation protection. The NRC, through a variety of legislative authorities, administrative regulations, regulatory guides, and national consensus standards regulates the commercial applications of nuclear energy. The purposes of regulation are the protection of the environment, public health and safety, and national security. To understand NRC's responsibilities relative to those of other Federal and state agencies concerned with environmental protection, we will briefly review the legislative authorities which underlie our regulatory program. Then we will examine the intent or the spirit of that program as embodied in our system of regulations, guides, and standards. Finally we will speak to what's happening today and what we see in the future for environmental standards

  17. Regulation of Federal radioactive waste activities. Summary of report to Congress on extending the Nuclear Regulatory Commission's licensing or regulatory authority to Federal radioactive waste storage and disposal activities

    International Nuclear Information System (INIS)

    Smith, R.D.

    1979-09-01

    The NRC Authorization Bill for FY 1979 directed NRC to conduct a study of extending the Commission's licensing or regulatory authority to include categories of existing and future Federal radioactive waste storage and disposal activities not presently subject to such authority. The report includes a complete listing and inventory of all radioactive waste storage and disposal activities now being conducted or planned by Federal agencies. The NRC study has attempted to present a general comparison of the relative hazards associated with defense-generated and commercial wastes. Options for extending Commission authority were developed and analyzed. The implications of NEPA were analyzed in the context of these options. The national security implications of extending NRC's regulatory authority over DOE programs are examined and evaluated. Costs and benefits are identified and assessed. The Commission's recommendations, based on the study, are to extend licensing authority over new DOE disposal activities involving transuranic wastes and non-defense low-level waste and to initiate a pilot program to test the feasibility of NRC playing a consultative role in the evaluation of existing DOE activities

  18. The Spanish energy regulatory body: the national energy commission (CNE)

    International Nuclear Information System (INIS)

    Merono, P. M.

    2002-01-01

    The National Energy Commission (CNE) is the Spanish Energy Regulatory body. This paper presents its scope and purpose, organisation, resources and financing, financial and performance control, functions, and legal provisions. (author)

  19. Nuclear Regulatory Commission issuances, January 1992

    International Nuclear Information System (INIS)

    1992-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Defense (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear Regulatory Commission issuances, May 1992

    International Nuclear Information System (INIS)

    1992-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances, July 1992

    International Nuclear Information System (INIS)

    1992-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  2. Nuclear Regulatory Commission issuances, June 1992

    International Nuclear Information System (INIS)

    1992-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Nuclear Regulatory Commission issuances, April 1994

    International Nuclear Information System (INIS)

    1994-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  4. Nuclear Regulatory Commission issuances, December 1991

    International Nuclear Information System (INIS)

    1991-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Nuclear Regulatory Commission issuances, December 1993

    International Nuclear Information System (INIS)

    1993-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  6. Nuclear Regulatory Commission issuances, December 1992

    International Nuclear Information System (INIS)

    1992-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  7. Nuclear Regulatory Commission issuances, September 1992

    International Nuclear Information System (INIS)

    1992-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  8. Nuclear Regulatory Commission issuances, February 1992

    International Nuclear Information System (INIS)

    1992-01-01

    This report includes the issuances received during the specified period from the Commission (CLl), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Director's Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  9. Nuclear Regulatory Commission issuances, March 1993

    International Nuclear Information System (INIS)

    1993-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuances, July 1993

    International Nuclear Information System (INIS)

    1993-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  11. Nuclear Regulatory Commission issuances, August 1992

    International Nuclear Information System (INIS)

    1992-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances, May 1982

    International Nuclear Information System (INIS)

    1982-01-01

    This report includes the issuances received during the specified period from the Commission, the Atomic Safety and Licensing Appeal Boards, the Atomic Safety and Licensing Boards, the Administrative Law Judge, the Directors' Decision, and the Denials of Petitions for Rulemaking

  13. Nuclear Regulatory Commission issuances, August 1991

    International Nuclear Information System (INIS)

    1991-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  14. Nuclear Regulatory Commission issuances, February 1993

    International Nuclear Information System (INIS)

    1993-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  15. Nuclear Regulatory Commission issuances, November 1992

    International Nuclear Information System (INIS)

    1992-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Nuclear Regulatory Commission issuances, April 1993

    International Nuclear Information System (INIS)

    1993-04-01

    This report includes the issuances received during the specified period from the commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  17. Nuclear Regulatory Commission issuances: August 1994. Volume 40, Number 2

    International Nuclear Information System (INIS)

    1994-08-01

    This report contains the collected issuances of the US Nuclear Regulatory Commission for the month of August, 1994. The report includes issuances of the Commission, the Atomic Safety and Licensing Boards, and the Directors' Decisions. Some of the entities involved include Gulf States Utility company, Sequoyah Fuels Corporation and General Atomics, Georgia Power Company, and Arizona Public Service Company

  18. United States Nuclear Regulatory Commission staff practice and procedure digest

    International Nuclear Information System (INIS)

    1990-03-01

    This document contains procedures for review by US Nuclear Regulatory Commission for reviewing and deciding on matters pertaining to nuclear power plant licensing. Also, contained within the document are decisions the Commission has made between July 1972 to September 1989. (F.S.D.)

  19. Nuclear Regulatory Commission issuances, April 1989

    International Nuclear Information System (INIS)

    1989-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear Regulatory Commission issuances, July 1989

    International Nuclear Information System (INIS)

    1989-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances, March 1989

    International Nuclear Information System (INIS)

    1989-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  2. Nuclear Regulatory Commission issuances, August 1990

    International Nuclear Information System (INIS)

    1990-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Nuclear Regulatory Commission issuances, December 1989

    International Nuclear Information System (INIS)

    1989-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  4. Nuclear Regulatory Commission issuances, May 1989

    International Nuclear Information System (INIS)

    1989-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Nuclear Regulatory Commission issuances, September 1987

    International Nuclear Information System (INIS)

    1987-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  6. Nuclear Regulatory Commission issuances, May 1990

    International Nuclear Information System (INIS)

    1990-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  7. Nuclear Regulatory Commission issuances, May 1987

    International Nuclear Information System (INIS)

    1987-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  8. Nuclear Regulatory Commission issuances, July 1988

    International Nuclear Information System (INIS)

    1988-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  9. Nuclear Regulatory Commission Issuances, October 1986

    International Nuclear Information System (INIS)

    1986-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuances, February 1989

    International Nuclear Information System (INIS)

    1989-02-01

    This report includes the issuances received during the specified period from the Commission (CLl), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  11. Nuclear Regulatory Commission issuances, June 1987

    International Nuclear Information System (INIS)

    1987-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decision (DD), and the Denials of Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances, October 1989

    International Nuclear Information System (INIS)

    1989-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  13. Nuclear Regulatory Commission issuances, December 1990

    International Nuclear Information System (INIS)

    1990-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  14. Nuclear Regulatory Commission issuances, April 1991

    International Nuclear Information System (INIS)

    1991-04-01

    This report includes the issuances received during the specified period (April 1991) from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  15. Nuclear Regulatory Commission issuances, April 1987

    International Nuclear Information System (INIS)

    1987-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Nuclear Regulatory Commission Issuances, August 1986

    International Nuclear Information System (INIS)

    1986-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  17. Nuclear Regulatory Commission issuances, November 1988

    International Nuclear Information System (INIS)

    1988-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  18. Nuclear Regulatory Commission Issuances, March 1990

    International Nuclear Information System (INIS)

    1990-01-01

    The report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  19. Nuclear Regulatory Commission issuances, November 1987

    International Nuclear Information System (INIS)

    1987-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear Regulatory Commission issuances, June 1990

    International Nuclear Information System (INIS)

    1990-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances, February 1985

    International Nuclear Information System (INIS)

    1985-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  2. Nuclear Regulatory Commission issuances, November 1990

    International Nuclear Information System (INIS)

    1990-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Securities and Exchange Commission Semiannual Regulatory Agenda

    Science.gov (United States)

    2010-12-20

    ... Flexibility Analysis Required: Yes Agency Contact: Alicia Goldin, Division of Trading and Markets, Securities...: Alicia Goldin, Division of Trading and Markets, Securities and Exchange Commission, 100 F Street NE... Flexibility Analysis Required: Yes Agency Contact: Alicia Goldin, Division of Trading and Markets, Securities...

  4. Federal Energy Regulatory Commission`s fiscal year 1996 financial statement audit

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-02-14

    This report presents the results of the independent certified public accountants` audit of the Federal Energy Regulatory Commission`s (FERC) financial statements as of September 30, 1996. The auditors have expressed an unqualified opinion on the 1996 statement of financial position and the related statements of operations and changes in net position.

  5. Federal Trade Commission Semiannual Regulatory Agenda

    Science.gov (United States)

    2010-12-20

    ...) Retail Food Store Advertising and Marketing Practices, 16 CFR 424; (8) the Negative Option Rule, 16 CFR... Deregulatory Actions includes The Regulatory Plan, which appears in both the online Unified Agenda and in part... available online at www.reginfo.gov , in a format that offers users a greatly enhanced ability to obtain...

  6. Nuclear Regulatory Commission issuances, September 1988

    International Nuclear Information System (INIS)

    1988-09-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or to have any independent legal significance

  7. Indexes to Nuclear Regulatory Commission Issuances

    International Nuclear Information System (INIS)

    1996-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and licensing Board Panel (LBP), the Administrative Law Judges (ALJ) the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Headers and Digests; Legal Citations Index; Subject Index; and Facility Index

  8. Indexes to Nuclear Regulatory Commission Issuances

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-31

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and licensing Board Panel (LBP), the Administrative Law Judges (ALJ) the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Headers and Digests; Legal Citations Index; Subject Index; and Facility Index.

  9. Review of hazardous chemical regulation at nuclear facilities by the Nuclear Regulatory Commission and other federal agencies. Hearing before a Subcommittee of the Committee on Government Operations, House of Representatives, Ninety-Ninth Congress, Second Session, March 14, 1986

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    Seven witnesses from agencies and the nuclear industry testified on the status of chemical regulation at nuclear facilities, the potential for accidents, and the quality of emergency plans in the event of a release of chemical substances. Impetus for the review came from incidents at Kerr-McGhee's Sequoyah plant in Oklahoma and the release of uranium hexafluoride, as well as a pattern of accidents which occur after the potential hazard has already been identified. The witnesses included Richard Krimm of the Federal Emergency Management Agency, James Makris of the Environmental Protection Agency, John Miles of the Occupational Safety and Health Administration, Nunxio Palladino of the Nuclear Regulatory Commission, and representatives of DOE and Kerr-McGee. Additional materials submitted for the record follows the testimony

  10. Nuclear Regulatory Commission issuances, September 1995. Volume 42, Number 3

    International Nuclear Information System (INIS)

    1995-09-01

    This book contains an issuance of the Atomic Safety and Licensing Board and a Director's Decision, both of the US Nuclear Regulatory Commission. The issuance concerns the dismissal of a case by adopting a settlement reached by the Staff of the Nuclear Regulatory Commission and a Radiation Safety Officer of a hospital in which the safety officer pled guilty to deliberate misconduct. The Director's Decision was to deny a petition to impose a fine on Tennessee Valley Authority concerning alleged harassment of the petitioner and to appoint an independent arbitration board to review all past complaints filed against TVA concerning the Watts Bar Nuclear Plant

  11. Nuclear Regulatory Commission issuances, September 1995. Volume 42, Number 3

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    This book contains an issuance of the Atomic Safety and Licensing Board and a Director`s Decision, both of the US Nuclear Regulatory Commission. The issuance concerns the dismissal of a case by adopting a settlement reached by the Staff of the Nuclear Regulatory Commission and a Radiation Safety Officer of a hospital in which the safety officer pled guilty to deliberate misconduct. The Director`s Decision was to deny a petition to impose a fine on Tennessee Valley Authority concerning alleged harassment of the petitioner and to appoint an independent arbitration board to review all past complaints filed against TVA concerning the Watts Bar Nuclear Plant.

  12. U.S. Nuclear Regulatory Commission natural analogue research program

    International Nuclear Information System (INIS)

    Kovach, L.A.; Ott, W.R.

    1995-01-01

    This article describes the natural analogue research program of the U.S. Nuclear Regulatory Commission (US NRC). It contains information on the regulatory context and organizational structure of the high-level radioactive waste research program plan. It also includes information on the conditions and processes constraining selection of natural analogues, describes initiatives of the US NRC, and describes the role of analogues in the licensing process

  13. KWOC [Key-Word-Out-of-Context] Index of US Nuclear Regulatory Commission Regulatory Guide Series

    International Nuclear Information System (INIS)

    Jennings, S.D.

    1990-04-01

    To meet the objectives of the program funded by the Department of Energy (DOE)-Nuclear Energy (NE) Technology Support Programs, the Performance Assurance Project Office (PAPO) administers a Performance Assurance Information Program that collects, compiles, and distributes program-related information, reports, and publications for the benefit of the DOE-NE program participants. THE ''KWOC Index of US Nuclear Regulatory Commission Regulatory Guide Series'' is prepared as an aid in searching for specific topics in the US Nuclear Regulatory Commission, Regulatory Guide Series

  14. Indexes to Nuclear Regulatory Commission issuances, January--March 1997

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-08-01

    This document provides digests and indexes for issuances of the Nuclear Regulatory Commission, the Atomic Safety and Licensing Board Panel, the Administrative Law Judges, the Directors Decisions, and the Decisions on Petitions for Rulemaking. These indexes and digests are intended to serve as a guide to the issuances.

  15. US Nuclear Regulatory Commission organization charts and functional statements

    International Nuclear Information System (INIS)

    1997-01-01

    This document contains organization charts for the U.S. Nuclear Regulatory Commission (NRC) and for the five offices of the NRC. Function statements are provided delineating the major responsibilities and operations of each office. Organization and function are provided to the branch level. The head of each office, division, and branch is also listed

  16. Indexes to Nuclear Regulatory Commission issuances, January--March 1997

    International Nuclear Information System (INIS)

    1997-01-01

    This document provides digests and indexes for issuances of the Nuclear Regulatory Commission, the Atomic Safety and Licensing Board Panel, the Administrative Law Judges, the Directors Decisions, and the Decisions on Petitions for Rulemaking. These indexes and digests are intended to serve as a guide to the issuances

  17. US Nuclear Regulatory Commission organization charts and functional statements

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-11-01

    This document contains organization charts for the U.S. Nuclear Regulatory Commission (NRC) and for the five offices of the NRC. Function statements are provided delineating the major responsibilities and operations of each office. Organization and function are provided to the branch level. The head of each office, division, and branch is also listed.

  18. Nuclear Regulatory Commission Issuances: February 1995. Volume 41, Number 2

    International Nuclear Information System (INIS)

    1995-02-01

    This book contains an issuance of the Nuclear Regulatory Commission and a Director's Decision. The issuance concerns consideration by the Commission of appeals from both the Initial Decision and a Reconsideration Order issued by the Presiding Officer involving two materials license amendment applications filed by the University of Missouri. The Director's Decision from the Office of Enforcement denies petitions filed by Northeast Utilities employees requesting that accelerated enforcement action be taken against Northeast Utilities for activities concerned with NU's fitness-for-duty program

  19. Indexes to Nuclear Regulatory Commission issuances, July--September 1997

    International Nuclear Information System (INIS)

    1998-01-01

    This digest and index lists the Nuclear Regulatory Commission (NRC) issuances for July to September 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking. There are five sections to this index: (1) case name index, (2) headers and digests, (3) legal citations index, (4) subject index, and (5) facility index. The digest provides a brief narrative of the issue, including the resolution of the issue and any legal references used for resolution

  20. Commission of energy regulation. 2004 activity report

    International Nuclear Information System (INIS)

    2004-01-01

    The commission of energy regulation (CRE) is an independent administrative authority in charge of the control of the operation of gas and electricity markets. This document is the fifth activity report of CRE and covers the July 1, 2003 - June 30, 2004 period, which corresponds to the era of opening of energy markets as a consequence of the enforcement of the June 26, 2003 European directive. In the framework of the stakes made by energy markets liberalization, this document presents the situation of the gas and electricity markets during this period (European framework, regulation of both markets, public utility mission..) and describes CRE's means for the monitoring of these markets. (J.S.)

  1. Nuclear Regulatory Commission issuances, January 1997. Volume 45, Number 1

    International Nuclear Information System (INIS)

    1997-01-01

    This book contains issuances of the Atomic Safety and Licensing Board, Nuclear Regulatory Commission and Director's Decision for January 1997. The issuances concern Sequoyah Fuels Corporation and General Atomics Gore, Oklahoma Site decontamination and decommissioning funding; Louisiana Energy Services, Claiborne Enrichment Center denies appeal to review emergency planning; General Public Utilities Nuclear Corporation, Oyster Creek Nuclear Generating station, challenges to technical specifications concerning spent fuel pool; and Consumers Power Company, Palisades Nuclear Plant dry cask storage of spent nuclear fuel

  2. U.S. Nuclear Regulatory Commission, annual report, 1978

    International Nuclear Information System (INIS)

    1978-01-01

    The report contains the following chapters: (1) overview and summary, (2) reactor regulation, (3) materials regulation, (4) domestic safeguards, (5) waste management, (6) injection and enforcement, (7) operating experience, (8) state programs, (9) international activities, (10) standards development, (11) regulatory research, (12) informing and involving the public, (13) proceedings and litigation, and (14) administration and mangement

  3. Steam Generator tube integrity -- US Nuclear Regulatory Commission perspective

    International Nuclear Information System (INIS)

    Murphy, E.L.; Sullivan, E.J.

    1997-01-01

    In the US, the current regulatory framework was developed in the 1970s when general wall thinning was the dominant degradation mechanism; and, as a result of changes in the forms of degradation being observed and improvements in inspection and tube repair technology, the regulatory framework needs to be updated. Operating experience indicates that the current U.S. requirements should be more stringent in some areas, while in other areas they are overly conservative. To date, this situation has been dealt with on a plant-specific basis in the US. However, the NRC staff is now developing a proposed steam generator rule as a generic framework for ensuring that the steam generator tubes are capable of performing their intended safety functions. This paper discusses the current U.S. regulatory framework for assuring steam generator (SG) tube integrity, the need to update this regulatory framework, the objectives of the new proposed rule, the US Nuclear Regulatory Commission (NRC) regulatory guide (RG) that will accompany the rule, how risk considerations affect the development of the new rule, and some outstanding issues relating to the rule that the NRC is still dealing with

  4. Deliberation of the French Energy Regulatory Commission of 18 January 2017 forming a decision on the tariffs for the use of regulated LNG terminals

    International Nuclear Information System (INIS)

    Ladoucette, Philippe de; Chauvet, Christine; Edwige, Catherine; Gassin, Helene; Sotura, Jean-Pierre

    2017-01-01

    The new tariffs for the use of regulated LNG terminals in Montoir-de-Bretagne (Montoir) and Fos Tonkin, which are operated by Elengy, and for the Fos Cavaou terminal, which is operated by Fosmax LNG, known as 'ATTM51', take effect on 1 April 2017 for a period of approximately four years. They were adopted after a broad consultation of stakeholders and following studies that were made public. The ATTM5 tariffs offer all stakeholders visibility on the changes to tariffs between 2017 and 2021, and provide incentive to LNG terminal operators to improve their efficiency in terms of both cost control and the service quality provided to the users of their terminals. The ATTM5 tariffs show a significant reduction compared to the ATTM4 tariffs: the decrease of the average unit tariff for the ATTM5 period is of 6.5 % for Montoir, 18.2 % for Fos Tonkin, and 18.6 % for Fos Cavaou. These decreases are mainly due to the lower return on assets. To a lesser extent, the reduced operating expenses reinforce the tariff reduction. They can be partly explained by the reduced expenditure related to the decrease in activity, and by the higher productivity achieved by Elengy and Fosmax LNG over the ATTM4 period, enabling the LNG terminal users to benefit from this. The ATTM5 tariffs introduce a change to the structure of the services offer. They create in particular a basic service, the main offer of the LNG terminal operators, which can be supplemented by the subscription to a uniform option. They extend several experimental services initiated during the ATTM4 tariff period. They increase the flexibility available to the terminal's clients on their subscriptions. Finally, they give Fosmax LNG the possibility to offer over the long-term the 10 % capacity previously restricted to the short-term subscriptions

  5. The United States nuclear regulatory commission license renewal process

    International Nuclear Information System (INIS)

    Holian, B.E.

    2009-01-01

    The United States (U.S.) Nuclear Regulatory Commission (NRC) license renewal process establishes the technical and administrative requirements for the renewal of operating power plant licenses. Reactor ope-rating licenses were originally issued for 40 years and are allowed to be renewed. The review process for license renewal applications (L.R.A.) provides continued assurance that the level of safety provided by an applicant's current licensing basis is maintained for the period of extended operation. The license renewal review focuses on passive, long-lived structures and components of the plant that are subject to the effects of aging. The applicant must demonstrate that programs are in place to manage those aging effects. The review also verifies that analyses based on the current operating term have been evaluated and shown to be valid for the period of extended operation. The NRC has renewed the licenses for 52 reactors at 30 plant sites. Each applicant requested, and was granted, an extension of 20 years. Applications to renew the licenses of 20 additional reactors at 13 plant sites are under review. As license renewal is voluntary, the decision to seek license renewal and the timing of the application is made by the licensee. However, the NRC expects that, over time, essentially all U.S. operating reactors will request license renewal. In 2009, the U.S. has 4 plants that enter their 41. year of ope-ration. The U.S. Nuclear Industry has expressed interest in 'life beyond 60', that is, requesting approval of a second renewal period. U.S. regulations allow for subsequent license renewals. The NRC is working with the U.S. Department of Energy (DOE) on research related to light water reactor sustainability. (author)

  6. Canada's regulatory framework: The Canadian Nuclear Safety Commission's regulatory framework

    International Nuclear Information System (INIS)

    Howard, D.

    2011-01-01

    This paper will discuss the Canadian Nuclear Safety Commission and Canada's Regulatory Framework with respect to Low- and Intermediate-Level Radioactive Waste. The management of low and intermediate level radioactive waste must be ensured in a consistent, environmentally responsible and economical manner throughout its lifecycle -- from its production to the final disposal option. Radioactive waste has been produced in Canada since the early 1930s when the first radium/uranium mine began operating at Port Radium in the Northwest Territories. Pitchblende ore was transported from the Port Radium mine to Port Hope, Ontario where it was refined to produce radium for medical purposes. At present, radioactive waste is generated in Canada from the various stages and uses associated with the nuclear fuel cycle from uranium mining/milling to nuclear reactor operations to radioisotope manufacture and use. The Canadian Nuclear Safety Commission (CNSC regulates the use of nuclear energy and materials to protect the health, safety and security of Canadians and the environment; and to implement Canada's international commitments on the peaceful use of nuclear energy. The CNSC was established in 2000 under the Nuclear Safety and Control Act and reports to Parliament through the Minister of Natural Resources. The CNSC was created to replace the former Atomic Energy Control Board (AECB), which was founded in 1946. Under the Nuclear Safety and Control Act, CNSC's mandate involves four major areas: regulation of the development, production and use of nuclear energy in Canada to protect health, safety and the environment; regulation of the production, possession, use and transport of nuclear substances, and the production, possession and use of prescribed equipment and prescribed information; implementation of measures respecting international control of the development, production, transport and use of nuclear energy and substances, including measures respecting the

  7. United States Nuclear Regulatory Commission information digest: 1997 edition. Volume 9

    International Nuclear Information System (INIS)

    1997-05-01

    The Nuclear Regulatory Commission Information Digest (digest) provides a summary of information about the US Nuclear Regulatory Commission (NRC), NRC's regulatory responsibilities, NRC licensed activities, and general information on domestic and world-wide nuclear energy. The digest, published annually, is a compilation of nuclear- and NRC-related data and is designed to provide a quick reference to major facts about the agency and the industry it regulates. In general, the data cover 1975 through 1996, with exceptions noted. Information on generating capacity and average capacity factor for operating US commercial nuclear power reactors is obtained from monthly operating reports that are submitted directly to the NRC by the licensee. This information is reviewed by the NRC for consistency only and no independent validation and/or verification is performed

  8. Commission for Energy regulation (CRE) - Activity report june 2008

    International Nuclear Information System (INIS)

    2008-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2008 activity report of CRE. Content: A - How CRE works: CRE regulatory authority and organisation: Powers, Organisation; Budget resources; Personnel; B - The Standing Committee for Dispute Settlement and Sanctions (CoRDiS) activity: Admissibility, Authority; C - Building a single European energy market: Overview; Organisation and coordination of the main European regulators (Work carried out collectively by European regulators, Regulator organisation and development, CRE's relations with European Community institutions, Development of CEER activities outside the European Union); CRE's European activities (The contribution of European regulators to the Third Energy Package, Integration of gas markets, Integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, Opening up markets to benefit consumers); European Community activities (The European Commission's proposals for the internal energy market: the Third Energy Package, The European Commission's proposals for fighting climate change: the Climate Package, Infringement

  9. Nuclear Regulatory Commission issuances: Volume 39, Number 6

    International Nuclear Information System (INIS)

    1994-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). Issuances of the Nuclear Regulatory Commission include: (1) Advanced Medical Systems, Inc.; (2) Henry Allen, Diane Marrone, and Susan Settino; and (3) Westinghouse Electric Corporation. Issuances of the Atomic Safety and Licensing Boards include: (1) Sequoyah Fuels Corporation and General Atomics Corporation and (2) Umetco Minerals Corporation. Issuances of Director's Decisions include: (1) Advanced Medical Systems, Inc., and (2) Boston Edison Company and all boiling water reactors. The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  10. Managing the high level waste nuclear regulatory commission licensing process

    International Nuclear Information System (INIS)

    Baskin, K.P.

    1992-01-01

    This paper reports that the process for obtaining Nuclear Regulatory Commission permits for the high level waste storage facility is basically the same process commercial nuclear power plants followed to obtain construction permits and operating licenses for their facilities. Therefore, the experience from licensing commercial reactors can be applied to the high level waste facility. Proper management of the licensing process will be the key to the successful project. The management of the licensing process was categorized into four areas as follows: responsibility, organization, communication and documentation. Drawing on experience from nuclear power plant licensing and basic management principles, the management requirement for successfully accomplishing the project goals are discussed

  11. Nuclear Regulatory Commission probabilistic risk assessment implementation program: A status report

    International Nuclear Information System (INIS)

    Rubin, M.P.; Caruso, M.A.

    1996-01-01

    The US Nuclear Regulatory Commission (NRC) is undertaking a number of activities intended to increase the consideration of risk significance in its decision processes and the effective use of risk-based technologies in its regulatory activities. Although the NRC is moving toward risk-informed regulation throughout its areas of responsibilities, this paper focuses primarily on those issues associated with reactor regulation. As the NRC completed significant milestones in its development of probabilistic risk assessment (PRA) methodology and gained considerable experience in the limited application of risk assessment to selected regulatory activities, it became evident that a much broader use of risk informed approaches offered advantages to both the NRC and the US commercial nuclear industry. This desire to enhance the use of risk assessment is driven by the clear belief that application of PRA methods will result in direct improvements in nuclear power plant operational safety from the perspective of both the regulator and the plant operator. The NRC believed that an overall policy on the use of PRA methods in nuclear regulatory activities should be established so that the many potential applications of PRA could be implemented in a consistent and predictable manner that would promote regulatory stability and efficiency. This paper describes the key activities that the NRC has undertaken to implement the initial stages of an integrated risk-informed regulatory framework

  12. Organizational behavior of regulatory agencies: a case study of the Bureau of Consumer Services in the Pennsylvania Public Utility Commission

    Energy Technology Data Exchange (ETDEWEB)

    Silver, J.H.

    1981-01-01

    Regulatory agencies operate in a complex field of organizations and interest groups. The variety of behaviors that occur in the regulatory field are not satisfactorily explained by current interpretative frameworks. Regulatory agencies are at once criticized and praised. They flourish as organizational entities, yet they exhibit behavior that is often inexplicable. Notions like clientele capture, the politics of regulation, exchange theory, and institutionalized organizations do not singly explain the vagaries of regulatory behavior. A merger of these viewpoints, however, provides a foundation for a comprehensive interpretative framework. A bureau of consumer services within a state public utility commission is viewed as an institutionalized organization. From this perspective, a variety of ritual behaviors, based upon symbolic and tangible interorganizational exchanges are observed and characterized. The outcome of these exchanges is the establishment of the Bureau of Consumer Services as a legitimate regulatory agent with significant impact upon the formulation of regulatory policy in the formal proceedings of the Pennsylvania Public Utility Commission.

  13. United States Nuclear Regulatory Commission staff practice and procedure digest

    International Nuclear Information System (INIS)

    1991-02-01

    This Revision 9 of the fifth edition of the NRC Staff Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period from July 1, 1972 to September 30, 1990 interpreting the NRC's Rules of Practice in 10 CFR Part 2. This Revision 9 replaces in part earlier editions and revisions and includes appropriate changes reflecting the amendments to the Rules of Practice effective through September 30, 1990. This edition of the Digest was prepared by attorneys from Aspen Systems Corporation pursuant to Contract number 18-89-346. Persons using this Digest are placed on notice that it may not be used as an authoritative citation in support of any position before the Commission or any of its adjudicatory tribunals. Persons using this Digest are also placed on notice that it is intended for use only as an initial research tool, that it may, and likely does, contain errors, including errors in analysis and interpretation of decisions, and that the user should not rely on the Digest analyses and interpretations but must read, analyze and rely on the user's own analysis of the actual Commission, Appeal Board and Licensing Board decisions cited. Further, neither the United States, the Nuclear Regulatory Commission, Aspen Systems Corporation, nor any of their employees makes any expressed or implied warranty or assumes liability or responsibility for the accuracy, completeness or usefulness of any material presented in the Digest. The Digest is roughly structured in accordance with the chronological sequence of the nuclear facility licensing process as set forth in Appendix A to 10 CFR Part 2. Those decisions which did not fit into that structure are dealt with in a section on general matters. Where appropriate, particular decisions are indexed under more than one heading. (JF)

  14. Toward introduction of risk informed safety regulation. Nuclear Safety Commission taskforce's interim report

    International Nuclear Information System (INIS)

    2006-01-01

    Nuclear Safety Commission's taskforce on 'Introduction of Safety Regulation Utilizing Risk Information' completed the interim report on its future subjects and directions in December 2005. Although current safety regulatory activities have been based on deterministic approach, this report shows the risk informed approach is expected to be very useful for making nuclear safety regulation and assurance activities reasonable and also for appropriate allocation of regulatory resources. For introduction of risk informed regulation, it also recommends pileups of experiences with gradual introduction and trial of the risk informed approach, improvement of plant maintenance rules and regulatory requirements utilizing risk information, and establishment of framework to assure quality of risk evaluation. (T. Tanaka)

  15. 17 CFR 201.421 - Commission consideration of determinations by self-regulatory organizations.

    Science.gov (United States)

    2010-04-01

    ... determinations by self-regulatory organizations. 201.421 Section 201.421 Commodity and Securities Exchanges... Commission Review § 201.421 Commission consideration of determinations by self-regulatory organizations. (a..., order review of any determination by a self-regulatory organization that could be subject to an...

  16. Commission for energy regulation - 2012 Activity Report

    International Nuclear Information System (INIS)

    2013-06-01

    After a presentation of the organisation, role and missions of the French Commission for Energy Regulation (CRE), and of its relationship with other institutional actors, this report describes and comments the action of the CRE in the fields of dialogue and transparency. It presents and comments key figures regarding the electricity and gas retail markets. It reports and comments the European reaction to the cold peak of February 2012 (historical peak for consumption and prices, inquiry on the causes of these price peaks, need of a European market). The next part addresses the relationship between electricity grids and territories (solidarity between electricity grids as the basis of the Europe of energy, evolution of French grids to face new needs and to take regional and local dimensions into account). Another part addresses gas infrastructures which are considered as the cornerstone of a good operation for the French market and for the integration of the European energy market (gas world market in 2012, definition of a target model for the gas market by European regulators, evolution of the French market in compliance with the European target model, new tariffs for the use of natural gas transport networks). The report then addresses the development of renewable energies: actions of CRE (bidding, opinion of tariffs), influence of renewable energy development on electricity prices on gross markets, needed evolution of electricity grids. A last part addresses the issues of energy cost, demand management, and struggle against energy poverty

  17. U.S. Nuclear Regulatory Commission Process for Risk-Informing the Nuclear Waste Arena

    International Nuclear Information System (INIS)

    Leslie, B. W.

    2003-01-01

    The U.S. Nuclear Regulatory Commission (NRC) is increasing the use of risk insights and information in its regulation of nuclear materials and waste. The objective of this risk-informed regulatory effort is to improve the effectiveness and efficiency of the agency, while maintaining or increasing its focus on safety. The agency's Office of Nuclear Material Safety and Safeguards (NMSS) proposed a five-step process to carry out a framework for increasing the use of risk information and insights in its regulation of nuclear materials and waste. The office is carrying out the five-step process to risk-inform the nuclear materials and waste arenas. NMSS's actions included forming a Risk Task Group and the use of case studies to test and complete screening criteria for identifying candidate regulatory applications amenable for risk-informing. Other actions included involving stakeholders through enhanced public participation, developing safety goals for materials and waste regulatory applications, and establishing a risk training program for staff. Through the case studies, NRC staff found the draft screening criteria to be effective in deciding regulatory areas that may be amenable to an increased use of risk insights. NRC staff also found that risk information may have the potential to reduce regulatory burden and improve staff's efficiency in making decisions, while maintaining safety. Finally, staff found that it would be possible to develop safety goals for the nuclear materials and waste arenas

  18. 75 FR 54917 - Criteria for Nominating Materials Licensees for the U.S. Nuclear Regulatory Commission's Agency...

    Science.gov (United States)

    2010-09-09

    ... NUCLEAR REGULATORY COMMISSION [NRC-2010-0294] Criteria for Nominating Materials Licensees for the U.S. Nuclear Regulatory Commission's Agency Action Review Meeting AGENCY: Nuclear Regulatory Commission. ACTION: Request for comment. SUMMARY: It is the policy of the U.S. Nuclear Regulatory Commission...

  19. U.S. Nuclear Regulatory Commission human factors program plan

    International Nuclear Information System (INIS)

    1986-04-01

    The purpose of the U.S. Nuclear Regulatory Commission (NRC) Human Factors Program Plan is to ensure that proper consideration is given to human factors in the design and operation of nuclear facilities. This revised plan addresses human factors issues related to the operation of nuclear power plants (NPPs). The three issues of concern are (1) the activities planned to provide the technical bases to resolve the remaining tasks related to human factors as described in NUREG-0660, The NRC Action Plan Developed as a Result of the TMI-2 Accident, and NUREG-0737, Clarification of TMI Action Plan Requirements; (2) the need to address the additional human factors efforts that were identified during implementation of the Action Plan; and (3) the actual fulfillment of those developmental activities specified in Revision 1 of this plan. The plan represents a systematic approach for addressing high priority human factors concerns important to NPP safety in FY 1986 through 1987

  20. Nuclear Regulatory Commission issuances, April 1995. Volume 41, Number 4

    International Nuclear Information System (INIS)

    1995-04-01

    This book contains issuances of the Nuclear Regulatory Commission and of the Atomic Safety and Licensing Boards, and an issuance of the Director's decision. The issuances concern a petition filed by Dr. James E Bauer seeking interlocutory Commission review of the Atomic Safety and Licensing Board's order imposing several restrictions on Dr. Bauer; a denial of an Interveners' Petition for Review addressing the application of Babcock and Wilcox for a renewal of its Special Nuclear Materials License; granting a motion for a protective order, by Sequoyah Fuel Corporation and General Atomics, limiting the use of the protected information to those individuals participating in the litigation and for the purposes of the litigation only; granting a Petitioner's petition for leave to intervene and request for a hearing concerning Georgia Institute of Technology (Georgia Tech Research Reactor) renewal of a facility license; and a denial of a petition filed by Mr. Ted Dougherty requesting a shutdown of the San Onofre Nuclear Generating Station based on concerns regarding the vulnerability of the plant to earthquakes and defensibility of the plant to a terrorist threat

  1. Nuclear Regulatory Commission issuances, April 1995. Volume 41, Number 4

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-04-01

    This book contains issuances of the Nuclear Regulatory Commission and of the Atomic Safety and Licensing Boards, and an issuance of the Director`s decision. The issuances concern a petition filed by Dr. James E Bauer seeking interlocutory Commission review of the Atomic Safety and Licensing Board`s order imposing several restrictions on Dr. Bauer; a denial of an Interveners` Petition for Review addressing the application of Babcock and Wilcox for a renewal of its Special Nuclear Materials License; granting a motion for a protective order, by Sequoyah Fuel Corporation and General Atomics, limiting the use of the protected information to those individuals participating in the litigation and for the purposes of the litigation only; granting a Petitioner`s petition for leave to intervene and request for a hearing concerning Georgia Institute of Technology (Georgia Tech Research Reactor) renewal of a facility license; and a denial of a petition filed by Mr. Ted Dougherty requesting a shutdown of the San Onofre Nuclear Generating Station based on concerns regarding the vulnerability of the plant to earthquakes and defensibility of the plant to a terrorist threat.

  2. Nuclear Regulatory Commission Staff practice and procedure digest. Commission, Appeal Board and Licensing Board Decision, July 1972 - June 1995

    International Nuclear Information System (INIS)

    1996-04-01

    This is the seventh edition of the Nuclear Regulatory Commission (NRC) Staff Practice and Procedure Digest. It contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period from July 1, 1972 to June 1995 interpreting the NRC rules of practice in 10 CFR part 2

  3. Regulatory Oversight for New Projects - Challenges and Improvement in Regulation

    International Nuclear Information System (INIS)

    Lall, F.

    2016-01-01

    From inception, there has been rise in number of Nuclear Power Plants (NPP) even though very few accidents / events led to intermittent setbacks. However these accidents / events have posed challenges towards enhancement of safety and scope of regulation in all phases of NPP such as siting, design, construction, commissioning and decommissioning. It is essential to ensure compliance to these enhanced safety requirements during all phases of NPP. New and evolutionary reactors are under threshold for regulatory consideration world over. The variety of technologies and genres by themselves pose challenges to regulatory bodies. These challenges are to be addressed through systematic enhancement of the regulation including updating of regulatory documents. The paper touches upon some key elements to be considered towards such enhancement of regulation during all stages of NPP. These being; ensuring quality assurance, regulatory oversight especially over supply chain and contractors, counterfeit material specifically in case of international dealings, emergency handling in case of multi-unit site, feedback and associated enhancements from international events, construction experience database and feedback for safety enhancement, qualification and acceptance of first of a kind systems, regulatory enforcement specifically in case of imported reactors and maintaining interface between safety and security. Regulation in present context has become dynamic and Regulatory bodies need to continue enhancement of its current regulation taking into account the technological developments, feedback from construction, operation and accidents in the current fleet of plants. The paper touches upon some of these elements and highlights the challenges and improvements in regulation. (author)

  4. Performance-Based (Risk-Informed) Regulation: A Regulatory Perspective

    International Nuclear Information System (INIS)

    Kadambi, N. Prasad

    2005-01-01

    Performance-based regulation (PBR) has been mandated at the national level in the United States and at the agency level, where appropriate, at the U.S. Nuclear Regulatory Commission (USNRC). Guidance has been developed that implements the USNRC's definitions of PBR and other such conceptual regulatory improvements. This paper describes why PBR is important, what constitutes PBR in the context of direction provided at the USNRC, and how PBR can be implemented using a five-step process. The process steps articulate questions to be posed by the analyst regarding various aspects of a regulatory issue so that a suitably performance-based resolution can be developed. A regulatory alternative thus developed can be included among other options to be considered as part of the regulatory decision-making process

  5. [The Commission of Health Regulation: chronicle of an end foretold].

    Science.gov (United States)

    Martínez, Alberto

    2015-07-01

    This article aims to establish some difficulties presented in the Commission of Health Regulation (CRES, Comisión de Regulación en Salud) during its short period of operation and the need for a regulatory body separate from the Ministry of Health and Social Protection that has a more pluralistic, participatory and inclusive character. We mention that the National Council of Social Security in Health (CNSSS -Consejo Nacional de Seguridad Social en Salud) sought to correct certain problematic situations, among other things, by creating the CRES. However, the national government intended to liquidate the newly formed body as already hinted in Law 1438 of 2012. We conclude that despite difficulties in the regulatory function, the CRES was eventually liquidated. The creation of a body such as the CNSSS that has a wider and more equitable base and that includes all social, governmental, and private stakeholders is necessary. This can be deduced from the proposed Statutory Law No. 105 of 2012 of the Senate of the Republic, which was presented by various social forces.

  6. 77 FR 9273 - WORKSHOP Sponsored by the Nuclear Regulatory Commission and the Electric Power Research Institute...

    Science.gov (United States)

    2012-02-16

    ... Commission and the Electric Power Research Institute on the Treatment of Probabilistic Risk Assessment.... SUMMARY: The U.S. Nuclear Regulatory Commission (NRC), Office of Nuclear Regulatory Research (RES), in cooperation with the Electric Power Research Institute (EPRI), will hold a joint workshop on the Treatment of...

  7. 76 FR 61402 - Draft Nuclear Regulatory Commission Fiscal Year 2012-2016 Strategic Plan

    Science.gov (United States)

    2011-10-04

    ...-2016 Strategic Plan AGENCY: Nuclear Regulatory Commission. ACTION: Draft NUREG; request for comment... comment on draft NUREG-1614, Volume 5. ``U.S. Nuclear Regulatory Commission, FY 2012-2016 Strategic Plan,'' dated September 2011. The NRC's draft FY 2012-2016 strategic plan describes the agency's mission and...

  8. 77 FR 15142 - Updated Nuclear Regulatory Commission Fiscal Years 2008-2013 Strategic Plan

    Science.gov (United States)

    2012-03-14

    ... 2008-2013 Strategic Plan AGENCY: Nuclear Regulatory Commission. ACTION: Strategic plan. SUMMARY: The U...-1614, Volume 5, ``U.S. Nuclear Regulatory Commission, Fiscal Years [FY] 2008-2013 Strategic Plan,'' dated February 2012. The updated FY 2008-2013 strategic plan describes the agency's mission and...

  9. Regional and International Networking to Support the Energy Regulatory Commission of Thailand

    Energy Technology Data Exchange (ETDEWEB)

    Lavansiri, Direk; Bull, Trevor

    2010-09-15

    The Energy Regulatory Commission of Thailand is a new regulatory agency. The structure of the energy sector; the tradition of administration; and, the lack of access to experienced personnel in Thailand all pose particular challenges. The Commission is meeting these challenges through regional and international networking to assist in developing policies and procedures that allow it to meet international benchmarks.

  10. Indexes to Nuclear Regulatory Commission issuances, January--June 1993

    International Nuclear Information System (INIS)

    1993-11-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full text reference (volume and pagination); Issuance number; Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (for construction permit, operating license, etc.); Type of issuance (memorandum, order, decision, etc.). These information elements are displayed in one or more of five separate formats arranged as follows: (1) Case Name Index; (2) Digests and Headers; (3) Legal Citations Index; (4) Subject Index; (5) Facility Index

  11. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1980-02-01

    This first supplement to the second edition of the NRC Staff Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board and Atomic Safety and Licensing Board decisions issued during the period from April 1, 1978 to September 30, 1978 interpreting the NRC's Rules of Practice in 10 CFR Part 2. The supplement also includes additional material from adjudicatory decisions rendered prior to April 1, 1978 and, to a very limited degree, material from adjudicatory decisions and regulation changes after September 30, 1978. The supplement, which is intended to be used as a pocket-part supplement to the Digest itself, includes a number of new subsections and topics not covered in the Digest. The new subsections are noted in the index for the supplement

  12. Indexes to Nuclear Regulatory Commission Issuances, January-March 1981

    International Nuclear Information System (INIS)

    1981-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors Denials (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owners of facility), Full text reference (volume and pagination), Issuance number, Issues raised by appellants, Legal citations (cases, regulations, and statutes), Name of facility, Docket number, Subject matter of issues and/or rulings, Type of hearing (for construction permit, operating license, etc.), and Type of issuance

  13. Indexes to Nuclear Regulatory Commission issuances, July-December 1997

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-05-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Board Panel, the Administrative Law Judges, the Directors` Decisions, and the Decisions on Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full text reference (volume and pagination); Issuance number Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (operating license, operating license amendment, etc); Type of issuance (memorandum, order, decision, etc.). These information elements are displayed in one or more of five separate formats: Case Name Index, Headers and Digests, Legal Citations Index, Subject Index, and Facility Index.

  14. Indexes to Nuclear Regulatory Commission issuances, January-March 1988

    International Nuclear Information System (INIS)

    1988-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full test reference (volume and pagination); Issuance number; Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (for construction permit, operating license, etc.); and Type of issuance (memorandum, order, decision, etc.)

  15. Indexes to Nuclear Regulatory Commission issuances, January--June 1988

    International Nuclear Information System (INIS)

    1988-09-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administration Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petition of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by appellants; legal citations (cases, regulations, and statutes); name of facility, docket number; subject matter of issues and/or rulings; type of hearing (for construction permit, operating license, etc.); and type of issuance (memorandum, order, decision, etc.)

  16. Indexes to Nuclear Regulatory Commission Issuances, January-June 1981

    International Nuclear Information System (INIS)

    1982-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owners of facility); Full text reference (volume and pagination); Issuance number; Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (for construction permit, operating license, etc.); and Type of issuance (memorandum, order, decision, etc.). These information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index, Digests and Headers, Legal Citations Index, Subject Index, and Facility Index

  17. Indexes to Nuclear Regulatory Commission Issuances, January--March 1990

    International Nuclear Information System (INIS)

    1990-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by appellants; legal citations (cases, regulations, and statutes); name of facility, Docket number; subject matter of issues and/or rulings; type of hearing (for construction permit, operating license, etc.); and type of issuance (memorandum, order, decision, etc.). These information elements are displayed in one or more of five separate formats arranged as follows: case name index; digests and headers; legal citations index; subject index; and facility index

  18. Indexes to Nuclear Regulatory Commission issuances, July-December 1997

    International Nuclear Information System (INIS)

    1998-01-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Board Panel, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full text reference (volume and pagination); Issuance number Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (operating license, operating license amendment, etc); Type of issuance (memorandum, order, decision, etc.). These information elements are displayed in one or more of five separate formats: Case Name Index, Headers and Digests, Legal Citations Index, Subject Index, and Facility Index

  19. Indexes to Nuclear Regulatory Commission issuances, July--September 1992

    International Nuclear Information System (INIS)

    1993-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: 1. Case Name Index: The case name index is an alphabetical arrangement of the case names of the issuances. Each case name is followed by the type of hearing, the type of issuance, docket number, issuance number, and full text reference. 2. Digests and Headers: The headers and digests are presented in issuance number order as follows: the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The header identifies the issuance by issuance number, case name, facility name, docket number, type of hearing, date of issuance, and type of issuance. 3. Legal Citations Index: This index is divided into four parts and consists of alphabetical or alpha-numerical arrangements of Cases, Regulations, Statutes, and Others. These citations are listed as given in the issuances. Changes in regulations and statutes may have occurred to cause changes in the number or name and/or applicability of the citation. It is therefore important to consider the date of the issuance. 4. Subject Index: Subject words and/or phrases, arranged alphabetically, indicate the issues and subjects covered in the issuances. 5. Facility Index: The index consists of an alphabetical arrangement of facility names from the issuance. The name is followed by docket number, type of hearing, data, type of issuance, issuance number, and full text reference

  20. 76 FR 57006 - Proposed Generic Communications; Draft NRC Regulatory Issue Summary 2011-XX; NRC Regulation of...

    Science.gov (United States)

    2011-09-15

    ... NUCLEAR REGULATORY COMMISSION 10 CFR Parts 30 and 150 [NRC-2011-0146] Proposed Generic Communications; Draft NRC Regulatory Issue Summary 2011-XX; NRC Regulation of Military Operational Radium-226... published for public comment the proposed draft RIS 2011-XX; NRC Regulation of Military Operational Radium...

  1. Regulatory requirements for demonstration of the achieved safety level at the Mochovce NPP before commissioning

    International Nuclear Information System (INIS)

    Lipar, M.

    1997-01-01

    A review of regulatory requirements for demonstration of the achieved safety level at the Mochovce NPP before commissioning is given. It contains licensing steps in Slovakia during commissioning; Status and methodology of Mochovce safety analysis report; Mochovce NPP safety enhancement program; Regulatory body policy towards Mochovce NPP safety enhancement; Recent development in Mochovce pre-operational safety enhancement program review and assessment process; Licensing steps in Slovakia during commissioning

  2. The EU commission and national governments as partners: EC regulatory expansion in telecommunications 1979-2000

    OpenAIRE

    Mark Thatcher

    2001-01-01

    Explicitly or implicitly, general models of European integration claim that EC regulatory expansion involves a struggle for power between Commission and national governments. The Commission is seen as a policy entrepreneur, taking the initiative to drive forward integration (Sandholtz and Zysman 1989). It seeks regulatory expansion due to constraints on its expenditure (Majone 1996, ch4). Neo-functionalists emphasise the Commission's ability to expand its role against the wishes of government...

  3. Reactor safety: a discussion by officials of the Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Anders, W.A.; Rusche, B.C.; Stello, V. Jr.; Minogue, R.B.

    1976-01-01

    William A. Anders, Chairman of the Nuclear Regulatory Commission (NRC), and several senior officials spoke to the Joint Committee on Atomic Energy on the subject of nuclear safety, improvements in reactor plant safety, and quality assurance. The NRC, during its first year of organization, has developed new initiatives to improve safety and safeguards regulations. Anders stressed that NRC is not stifling internal discussion of opposing views, that it has been honest with the public, and that operating reactors are meeting rigorous safety standards. Other speakers discussed comparative safety of old and new reactors. Backfitting of older plants with new features is done when substantial safety protection can be added, but detuning an integrated system is not done indiscriminately. Officials of NRC do not agree with former General Electric employees, who testified that the regulatory procedure is inadequate. Safety improvements since August 28, 1962 and outlines of the review process are included in the Appendixes

  4. Commission for Energy regulation (CRE) - Activity report June 2007

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2007-07-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2007 activity report of CRE. Content: A - Towards a single European energy market: Birth of a single European energy market (Origins of Europe of Energy, Emergence of a European energy policy); Main European Community guiding lines (European governance as regards energy, Guiding principles for the internal energy market); European Community activities (European Commission reports, Electricity and gas Regional Initiatives); Organisation and coordination of European regulators (Joint organisation of European regulators, CRE's relations with European Community institutions); CRE's European activities (Regional integration of gas markets, Regional integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, CRE's other European activities); B - CRE action at national level: Grids/networks and infrastructures (General information, Electricity grids, Regulation of gas networks and infrastructures); Markets (Changes in the regulatory and legislative contexts of electricity and natural gas markets, Electricity markets

  5. Commission for Energy regulation (CRE) - Activity report June 2007

    International Nuclear Information System (INIS)

    2007-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2007 activity report of CRE. Content: A - Towards a single European energy market: Birth of a single European energy market (Origins of Europe of Energy, Emergence of a European energy policy); Main European Community guiding lines (European governance as regards energy, Guiding principles for the internal energy market); European Community activities (European Commission reports, Electricity and gas Regional Initiatives); Organisation and coordination of European regulators (Joint organisation of European regulators, CRE's relations with European Community institutions); CRE's European activities (Regional integration of gas markets, Regional integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, CRE's other European activities); B - CRE action at national level: Grids/networks and infrastructures (General information, Electricity grids, Regulation of gas networks and infrastructures); Markets (Changes in the regulatory and legislative contexts of electricity and natural gas markets, Electricity markets, Natural gas

  6. Nuclear Regulatory Commission Human Factors Program Plan. Revision 2

    International Nuclear Information System (INIS)

    1986-04-01

    This document is the Second Annual Revision to the NRC Human Factors Program Plan. The first edition was published in August 1983. Revision 1 was published in July of 1984. Purpose of the NRC Human Factors Program is to ensure that proper consideration is given to human factors in the design and operation of nuclear power plants. This document describes the plans of the Office of Nuclear Reactor Regulation to address high priority human factors concerns of importance to reactor safety in FY 1986 and FY 1987. Revision 2 of the plan incorporates recent Commission decisions and policies bearing on the human factors aspects of reactor safety regulation. With a few exceptions, the principal changes from prior editions reflect a shift from developing new requirements to staff evaluation of industry progress in resolving human factors issues. The plan addresses seven major program elements: (1) Training, (2) Licensing Examinations, (3) Procedures, (4) Man-Machine Interface, (5) Staffing and Qualifications, (6) Management and Organization, and (7) Human Performance

  7. Leak testing United States Nuclear Regulatory Commission type b packaging

    International Nuclear Information System (INIS)

    Lacy, K.A.

    1995-01-01

    The Waste Isolation Pilot Plant (WTPP) is a one of its kind research and development facility operated by the Department of Energy, Carlsbad Area Office. Located in southeastern New Mexico, the WTPP is designed to demonstrate the safe, permanent disposal of transuranic (TRU) radioactive nuclear waste, accumulated from 40 years of nuclear weapons production. Before the waste can be disposed of, it must first be safely transported from generator storage sites to the WIPP. To accomplish this, the TRUPACT-II was designed and fabricated. This double containment, non-vented waste packaging successfully completed a rigorous testing program, and in 1989 received a Certificate of Compliance (C of C) from the Nuclear Regulatory Commission (NRC). Currently, the TRUPACT-II is in use at Idaho National Engineering Laboratory to transport waste on site for characterization. The DOE/CAO is responsible for maintaining the TRUPACT-II C of C. The C of C requires performance of nondestructive examination (NDE), e.g., visual testing (VT), dimensional inspections, Liquid Dye Penetrant testing (PT), and Helium Leak Detection (HLD). The Waste Isolation Division (WID) uses HLD for verification of the containment integrity. The following HLD tests are performed on annual basis or when required, i.e. repairs or component replacement: (1) fabrication verification leak tests on both the outer containment vessel (OCV) and the inner containment vessel (ICV); (2) assembly verification leak tests on the OCV and ICV upper main o-rings; and (3) assembly verification leak tests on the OCV and the ICV vent port plugs. These tests are addressed in detail as part of this presentation

  8. Commission for Energy regulation (CRE) - Activity report June 2005

    International Nuclear Information System (INIS)

    2005-01-01

    texts specify the competitive framework); Opening of the gas markets (Opening of the markets in European Union countries, Opening of the French gas market); CRE: regulator of the French gas market (Major obstacles to efficient operation of the French gas market were raised during 2004 and early 2005, Changes in natural gas regulated sales tariffs, Regulated infrastructure tariffs and utilisation conditions, Gaz de France and Total commitments made to the European Commission, Opening of the non-household market on 1 July 2004 and work of the 2004 Gas Working Group (GTG 2004), Audits of the un-bundled accounts of integrated gas operators, CRE's opinions on the regulatory texts, Codes of good conduct for network operators); The work programme (Independence of network operators, Feedback, Preparation of total opening on 1 July 2007, Preparation of the new tariffs for use of regulated gas infrastructures, Comparison of offers of access to storage facilities in Europe, Distribution system operators' investment criteria, Works in the European context); C - Regulation of the electricity market: actors and electricity markets; access to public power networks; the public electric utility in the regulated market; D - The working of CRE: How CRE exercises its jurisdiction (A working method based on responsiveness, consultation and transparency, Disputes solved help to guarantee the right of access to networks for consumers, suppliers and producers, Control and sanction powers); Tools (Professionalism and a multi-disciplinary approach, Some resources remain insufficient to meet the deadline for total opening of the energy markets on 1 July 2007, Independence and budgetary structure); European and international activity (Relations with European Union institutions, Relations with other regulators, Other international relations); E - Glossary, Acronyms, Units and conversions, Index of insets, tables and figures, Council of European Energy Regulators (CEER)

  9. United States nuclear regulatory commission program for inspection of decommissioning nuclear power plants

    International Nuclear Information System (INIS)

    Harris, P.W.

    2001-01-01

    The United States Nuclear Regulatory Commission (USNRC or Commission) has been inspecting decommissioning commercial nuclear power plants in the United States (U.S.) since the first such facility permanently shutdown in September 1967. Decommissioning inspections have principally focused on the safe storage and maintenance of spent reactor fuel; occupational radiation exposure; environmental radiological releases; the dismantlement and decontamination of structures, systems, and components identified to contain or potentially contain licensed radioactive material; and the performance of final radiological survey of the site and remaining structures to support termination of the USNRC-issued operating license. Over the last 5 years, USNRC inspection effort in these areas has been assessed and found to provide reasonable confidence that decommissioning can be conducted safely and in accordance with Commission rules and regulations. Recently, the staff has achieved a better understanding of the risks associated with particular decommissioning accidents 1 and plans to apply these insights to amendments proposed to enhance decommissioning rules and regulations. The probabilities, scenarios, and conclusions resulting from this effort are being assessed as to their applicability to the inspection of decommissioning commercial power reactors. (author)

  10. United States nuclear regulatory commission program for inspection of decommissioning nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Harris, P.W. [U.S. Nuclear Regulatory Commission, Washington, DC (United States)

    2001-07-01

    The United States Nuclear Regulatory Commission (USNRC or Commission) has been inspecting decommissioning commercial nuclear power plants in the United States (U.S.) since the first such facility permanently shutdown in September 1967. Decommissioning inspections have principally focused on the safe storage and maintenance of spent reactor fuel; occupational radiation exposure; environmental radiological releases; the dismantlement and decontamination of structures, systems, and components identified to contain or potentially contain licensed radioactive material; and the performance of final radiological survey of the site and remaining structures to support termination of the USNRC-issued operating license. Over the last 5 years, USNRC inspection effort in these areas has been assessed and found to provide reasonable confidence that decommissioning can be conducted safely and in accordance with Commission rules and regulations. Recently, the staff has achieved a better understanding of the risks associated with particular decommissioning accidents 1 and plans to apply these insights to amendments proposed to enhance decommissioning rules and regulations. The probabilities, scenarios, and conclusions resulting from this effort are being assessed as to their applicability to the inspection of decommissioning commercial power reactors. (author)

  11. US Nuclear Regulatory Commission organization charts and functional statements

    International Nuclear Information System (INIS)

    1996-01-01

    This document is the US NRC organizational structure and chart as of July 1, 1996. It contains the org charts for the Commission, ACRS, ASLAB, Commission staff offices, Executive Director for Operations, Office of the Inspector General, Program offices, and regional offices

  12. US Nuclear Regulatory Commission organization charts and functional statements

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-07-01

    This document is the US NRC organizational structure and chart as of July 1, 1996. It contains the org charts for the Commission, ACRS, ASLAB, Commission staff offices, Executive Director for Operations, Office of the Inspector General, Program offices, and regional offices.

  13. 39 CFR Appendix A to Part 3002 - Postal Regulatory Commission, Mission Statement of the Office of the Consumer Advocate

    Science.gov (United States)

    2010-07-01

    ... 39 Postal Service 1 2010-07-01 2010-07-01 false Postal Regulatory Commission, Mission Statement of the Office of the Consumer Advocate A Appendix A to Part 3002 Postal Service POSTAL REGULATORY COMMISSION PERSONNEL ORGANIZATION Pt. 3002, App. A Appendix A to Part 3002—Postal Regulatory Commission, Mission Statement of the Office of the Consumer...

  14. Indexes to Nuclear Regulatory Commission issuance, July-December 1980. Index of Volume 12, Number 4

    International Nuclear Information System (INIS)

    1980-01-01

    Issuances of the Atomic Safety and Licensing Board (ASLB), the Atomic Safety and Licensing Appeal Boards (ALAB), the Administrative Law Judge (ALJ), regulatory issuances of the Commission (CLI), the Directors Denial (DD), and the Denials of Petitions for Rulemaking for the period July through December 1980 appear in Nuclear Regulatory Commission Issuances, 12 NRC No. 1, Pages 1-136, through 12 NRC No. 6, Pages 607-742. Digests and indexes for these issuances are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owners of facility); Name of facility, docket number; Type of hearing (for construction permit, operating licenses, etc.); Issues raised by appellants; Issuance number; Type of issuance (memorandum, order, decision, etc.); Issuance pagination; Legal citations (cases, regulations, and statutes); and Subject matter of issues and/or rulings. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; Digests and headers; Legal citation index; Subject index; and Facility index

  15. Reactor aging research. United States Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Vassilaros, M.G.

    1998-01-01

    The reactor ageing research activities in USA described, are focused on the research of reactor vessel integrity, including regulatory issues and technical aspects. Current emphasis are described for fracture analysis, embrittlement research, inspection capabilities, validation od annealing rule, revision of regulatory guide

  16. Nuclear Regulatory Commission staff approaches to improving the integration of regulatory guidance documents and prelicensing reviews

    International Nuclear Information System (INIS)

    Johnson, R.L.

    1994-01-01

    The Nuclear Regulatory Commission staff is conducting numerous activities to improve the integration of its regulatory guidance documents (i.e., License Application Review Plan (LARP) and open-quotes Format and Content for the License Application for the High-Level Waste repositoryclose quotes (FCRG)) and pre-license application (LA) reviews. Those activities related to the regulatory guidance documents consist of: (1) developing an hierarchy of example evaluation findings for LARP; (2) identifying LARP review plan interfaces; (3) conducting an integration review of LARP review strategies; (4) correlating LARP to the ongoing technical program; and (5) revising the FCRG. Some of the more important strategies the staff is using to improve the integration of pre-LA reviews with the LA review include: (1) use of the draft LARP to guide the staff's pre-LA reviews; (2) focus detailed pre-LA reviews on key technical uncertainties; (3) identify and track concerns with DOE's program; and (4) use results of pre-LA reviews in LA reviews. The purpose of this paper is to describe these ongoing activities and strategies and discuss some of the new work that is planned to be included in LARP Revision 1 and the final FCRG, which are scheduled to be issued in late 1994. These activities reflect both the importance the staff has placed on integration and the staff's approach to improving integration in these areas. The staff anticipates that the results of these activities, when incorporated in the FCRG, LARP, and pre-LA reviews, will improve its guidance for DOE's ongoing site characterization program and LA annotated outline development

  17. Nuclear Regulatory Commission issuances, March 1995. Volume 41, No. 3

    International Nuclear Information System (INIS)

    1995-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  18. Nuclear Regulatory Commission issuances, May 1995. Volume 41, No. 5

    International Nuclear Information System (INIS)

    1995-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (AU), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  19. Nuclear Regulatory Commission issuances. Volume 42, No. 6

    International Nuclear Information System (INIS)

    1995-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (AU), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  20. Regulatory view on licensing and commissioning of Temelin NPP

    International Nuclear Information System (INIS)

    Drabova, D.; Boehm, K.; Brandejs, P.; Tipek, Z.

    2004-01-01

    The competencies delegated to the Czech State Office for Nuclear Safety by Czech legislation are highlighted and the history of construction and commissioning of the Temelin nuclear power plant in relation to the licensing process is described. (P.A.)

  1. Nuclear Regulatory Commission issuances, April 1994. Volume 39, No. 4

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM).

  2. Nuclear Regulatory Commission issuances, March 1995. Volume 41, No. 3

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM).

  3. Nuclear Regulatory commission issuances, Volume 42, No. 5

    International Nuclear Information System (INIS)

    1995-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  4. Nuclear Regulatory Commission issuances. Volume 42, No. 4

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM).

  5. Nuclear Regulatory Commission issuances, September 1994. Volume 40, No. 3

    International Nuclear Information System (INIS)

    1994-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (AU), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  6. Nuclear Regulatory Commission issuances, December 1994. Volume 40, No. 6

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM).

  7. Nuclear Regulatory Commission issuances, Volume 47, No. 1

    International Nuclear Information System (INIS)

    1998-01-01

    This report includes the issuances received during the specified period from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking

  8. Nuclear Regulatory Commission issuances, May 1995. Volume 41, No. 5

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (AU), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM).

  9. Nuclear Regulatory Commission issuances, Volume 45, No. 2

    International Nuclear Information System (INIS)

    1997-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Director's Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuances. Volume 23, No. 3

    International Nuclear Information System (INIS)

    1986-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), and the Directors' Decisions (DD)

  11. Nuclear Regulatory Commission issuances. Volume 42, No. 4

    International Nuclear Information System (INIS)

    1995-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  12. Nuclear Regulatory Commission issuances, February 1996: Volume 43, No. 2

    International Nuclear Information System (INIS)

    1996-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  13. Nuclear Regulatory Commission issuances. Volume 38, No. 2

    Energy Technology Data Exchange (ETDEWEB)

    1993-08-01

    This report includes the issuances received during the specified period from the commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors; Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM).

  14. Nuclear Regulatory Commission issuances, February 1996: Volume 43, No. 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM).

  15. Nuclear Regulatory Commission issuances. Volume 47, Number 3

    International Nuclear Information System (INIS)

    1998-03-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The two issuances included here are: (1) the Commission issuance to the US Enrichment Corporation and (2) the Director's Decision to the North Atlantic Energy Service Corporation

  16. Study of the Nuclear Regulatory Commission's Appellate System

    International Nuclear Information System (INIS)

    Bickwit, L.; Malsch, M.; Ostrach, S.; Christenson, K.

    1979-12-01

    At the Chairman's request the Office of the General Counsel studied the Commission's appellate system. The study included examination of the development of the study, analysis of the current workload, investigation of the practices of other agencies, and consideration of alternatives to the present system. The study recommends retention of the present system with some limited modifications to enable the Commission to more effectively use its existing appellate powers

  17. First update to the US Nuclear Regulatory Commission's regulatory strategy for the high-level waste repository program

    International Nuclear Information System (INIS)

    Johnson, R.L.; Linehan, J.J.

    1991-01-01

    The US Nuclear Regulatory Commission (NRC) staff has updated its initial regulatory strategy for the High-Level Waste Repository Licensing Program. The update describes changes to the initial strategy and summarizes progress and future activities. This paper summarizes the first update of the regulatory strategy. In general the overall strategy of identifying and reducing uncertainties is unchanged. Identifying regulatory and institutional uncertainties is essentially complete, and therefore, the current and future emphasis is on reducing those regulatory and institutional uncertainties identified to date. The NRC staff has improved the methods of reducing regulatory uncertainties by (1) enhancing the technical basis preparation process for potential rulemakings and guidance and (2) designing a new guidance document, called a staff position, for clarifying regulatory uncertainties. For guiding the US DOE's reduction of technical uncertainties, the NRC staff will give more emphasis to prelicense application reviews and less emphasis on preparing staff technical positions

  18. Understanding utility regulation : a participants' guide to the British Columbia Utilities Commission

    International Nuclear Information System (INIS)

    1996-10-01

    Information regarding British Columbia's regulated energy industries is presented with particular emphasis on the regulatory functions of the British Columbia Utilities Commission (BCUC). The objective of providing the information is to make the regulatory process as transparent as possible and to make it easy for ratepayers to effectively and economically participate in the regulation of energy utilities. The issue of why electricity and natural gas utilities are regulated is addressed, but the greater part of the report is devoted to describing opportunities for public participation at the BCUC, explaining how to get involved in the Commission's proceedings and the nature of the hearings used by the Commission. An introduction to rate making is also presented, along with an overview of other institutions involved in energy regulation. Appendices contain the text of the Utilities Commission Act (App. A), the Negotiated Settlement Process Policy, Procedures and Guidelines (App. B), Participant Funding and Cost Awards (App. C), and the Integrated Resource Planning Guide (App. D). tabs., figs., 4 appendices

  19. The latest occupational radiation exposure data from U.S. Nuclear Regulatory Commission Licensees

    International Nuclear Information System (INIS)

    Brock, T.

    2007-01-01

    This presentation summarizes the latest - 2005 occupational exposure data that are maintained in the U.S. Nuclear Regulatory Commission (NRC) Radiation Exposure Information and Reporting System. The bulk of the information contained in the paper was compiled from the 2005 annual reports submitted by NRC licensees subject to the reporting requirements of U.S. regulations (10 CFR 20.2206). Those licensees subject to reporting include commercial nuclear power plants, industrial radiographers, fuel processors, independent spent fuel storage installations, manufacturers and distributors of by-product material, facilities for low-level waste disposal, and geologic repositories for high-level waste. The annual reports submitted by these licensees consist of radiation exposure records for each monitored individual. These records are analyzed for trends and presented in terms of collective dose and the distribution of doses by licensee category. (author)

  20. The Canadian Nuclear Safety Commission regulatory process for decommissioning a uranium mining facility

    International Nuclear Information System (INIS)

    Scissons, K.; Schryer, D.M.; Goulden, W.; Natomagan, C.

    2002-01-01

    The Canadian Nuclear Safety Commission (CNSC) regulates uranium mining in Canada. The CNSC regulatory process requires that a licence applicant plan for and commit to future decommissioning before irrevocable decisions are made, and throughout the life of a uranium mine. These requirements include conceptual decommissioning plans and the provision of financial assurances to ensure the availability of funds for decommissioning activities. When an application for decommissioning is submitted to the CNSC, an environmental assessment is required prior to initiating the licensing process. A case study is presented for COGEMA Resources Inc. (COGEMA), who is entering the decommissioning phase with the CNSC for the Cluff Lake uranium mine. As part of the licensing process, CNSC multidisciplinary staff assesses the decommissioning plan, associated costs, and the environmental assessment. When the CNSC is satisfied that all of its requirements are met, a decommissioning licence may be issued. (author)

  1. Nuclear Regulatory Commission issuances, April 1986. Volume 23, No. 4

    International Nuclear Information System (INIS)

    1986-04-01

    This report includes the issuances recieved during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  2. Nuclear Regulatory Commission issuances, Volume 18, No. 5

    International Nuclear Information System (INIS)

    1983-11-01

    This report includes the issuances received during November, 1983, from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Nuclear Regulatory Commission issuances. Volume 46, Number 2

    International Nuclear Information System (INIS)

    1997-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  4. Nuclear Regulatory Commission issuances. Volume 17, No. 4

    International Nuclear Information System (INIS)

    1983-04-01

    This report includes the issuances received during the specified period from the Commission (CLi), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Indexes to Nuclear Regulatory Commission issuances, January-June 1987

    International Nuclear Information System (INIS)

    1988-02-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  6. Nuclear Regulatory Commission issuances. Vol. 16, No. 5

    International Nuclear Information System (INIS)

    1982-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions For Rulemaking (DPRM)

  7. Nuclear Regulatory Commission Issuances. Volume 23, No. 1

    International Nuclear Information System (INIS)

    1986-01-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  8. US Nuclear Regulatory Commission organization charts and functional statements

    International Nuclear Information System (INIS)

    1996-01-01

    This document is the organizational chart for the US NRC. It contains organizational structure and functional statements for the following: (1) the Commission, (2) committees and boards, (3) staff offices, (4) office of the Inspector General, (5) executive director for operations, (6) program offices, and (7) regional offices

  9. Nuclear Regulatory Commission issuances: Volume 46, Number 6

    International Nuclear Information System (INIS)

    1997-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decision (DD), and the Decision on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  10. Indexes to Nuclear Regulatory Commission issuances, January-March 1987

    International Nuclear Information System (INIS)

    1987-09-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Appeal Panel, the Atomic Safety and Licensing Board Panel, the Administrative Law Judge, the Directors' Decisions, and the Denials of Petitions of Rulemaking are presented in this document

  11. Indexes to Nuclear Regulatory Commission issuances, January--March 1989

    International Nuclear Information System (INIS)

    1989-07-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document

  12. Indexes to Nuclear Regulatory Commission issuances, January-June 1982

    International Nuclear Information System (INIS)

    1982-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  13. Nuclear Regulatory Commission issuances. Volume 20, No. 4

    International Nuclear Information System (INIS)

    1984-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  14. Indexes to Nuclear Regulatory Commission issuances, July-December 1986

    International Nuclear Information System (INIS)

    1987-07-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  15. Nuclear Regulatory Commission issuances. Volume 47, Number 2

    International Nuclear Information System (INIS)

    1998-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). They involve: 21st Century Technologies, Inc.; Hydro Resources, Inc.; Northeast Utilities; and Northern States Power Company

  16. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1992-08-01

    This 2nd revision of the sixth edition of the NRC Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period of July 1, 1972 to September 30, 1991, interpreting the NRC's Rules of Pratice in 10 CFR Part 2

  17. United States Nuclear Regulatory Commission Staff practice and procedure digest

    International Nuclear Information System (INIS)

    1990-08-01

    This Revision Number 7 of the fifth edition of the NRC Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period July 1, 1972 to March 31, 1990, interpreting the NRC's Rules of Practice in 10 CFR Part 2

  18. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1992-02-01

    This revision of the sixth edition of the NRC Practice and Procedure Digest contains a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period of July 1, 1972 to March 31, 1991, interpreting the NRC's Rules of Practice in 10 CFR Part 2

  19. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1992-05-01

    This 2nd revision of the sixth edition of the NRC Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period of July 1, 1972 to June 30, 1991, interpreting the NRC's Rules of Practice in 10 CFR Part 2

  20. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1993-08-01

    This 7th revision of the sixth edition of the NRC Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period of July 1, 1972 to September 30, 1992, interpreting the NRC's Rules of Practice in 10 CFR Part 2

  1. United States Nuclear Regulatory Commission Staff practice and procedure digest

    International Nuclear Information System (INIS)

    1993-05-01

    This 6th revision of the sixth edition of the NRC Practice and Procedure Digest contains a digest of a number of commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period of July 1, 1972 to June 30, 1992, interpreting the NRC's Rules of Practice in 10 CFR Part 2

  2. Nuclear Regulatory Commission issuances. Volume 20, No. 2

    International Nuclear Information System (INIS)

    1984-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  3. Nuclear Regulatory Commission issuances. Volume 21, No. 6

    International Nuclear Information System (INIS)

    1985-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  4. Nuclear Regulatory Commission issuances. Volume 21, No. 5

    International Nuclear Information System (INIS)

    1985-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  5. Nuclear Regulatory Commission issuances. Vol. 16, No. 4

    International Nuclear Information System (INIS)

    1982-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions For Rulemaking (DPRM)

  6. Nuclear Regulatory Commission issuances. Volume 46, Number 1

    International Nuclear Information System (INIS)

    1997-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  7. Nuclear Regulatory Commission issuances, June 1997. Volume 45, Number 6

    International Nuclear Information System (INIS)

    1997-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  8. US Nuclear Regulatory Commission organization charts and functional statements

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-08-19

    This document is the organizational chart for the US NRC. It contains organizational structure and functional statements for the following: (1) the Commission, (2) committees and boards, (3) staff offices, (4) office of the Inspector General, (5) executive director for operations, (6) program offices, and (7) regional offices.

  9. Nuclear Regulatory Commission issuances, December 1982. Vol. 16, No. 6

    International Nuclear Information System (INIS)

    1982-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  10. Nuclear Regulatory Commission issuance, pages 933-1089

    International Nuclear Information System (INIS)

    1981-11-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors Denial (DD), and the Denial of Petitions for Rulemaking

  11. Nuclear Regulatory Commission issuances: June 1995. Volume 41, Number 6

    International Nuclear Information System (INIS)

    1995-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decision on Petitions for Rulemaking (DPRM). This report contains four issuances by the CLI, 5 issuances by the LBP, and 1 issuance by the DD

  12. Nuclear Regulatory Commission issuances, Volume 45, No. 5

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance.

  13. Indexes to Nuclear Regulatory Commission Issuances, January--June 1994

    International Nuclear Information System (INIS)

    1994-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Director's Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  14. Nuclear Regulatory Commission issuances: Volume 46, Number 6

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decision (DD), and the Decision on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance.

  15. Nuclear Regulatory Commission issuances. Volume 22, No. 6

    International Nuclear Information System (INIS)

    1985-12-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  16. Indexes to Nuclear Regulatory Commission issuances, July-September 1986

    International Nuclear Information System (INIS)

    1987-06-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  17. Indexes to Nuclear Regulatory Commission issuances, July-December 1987

    International Nuclear Information System (INIS)

    1988-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  18. Nuclear Regulatory Commission Issuances. Volume 22, No. 1

    International Nuclear Information System (INIS)

    1985-07-01

    This report includes the issuances received during July 1985 from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  19. Nuclear Regulatory Commission issuances, June 1986. Volume 23, No. 6

    International Nuclear Information System (INIS)

    1986-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  20. Nuclear Regulatory Commission issuances. Vol. 16, No. 1

    International Nuclear Information System (INIS)

    1982-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Director's Decisions (DD), and the Denials of Petitions For Rulemaking (DPRM)

  1. Nuclear Regulatory Commission issuances, Volume 45, No. 5

    International Nuclear Information System (INIS)

    1997-05-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or have any independent legal significance

  2. Indexes to Nuclear Regulatory Commission issuances, July-September 1983

    International Nuclear Information System (INIS)

    1983-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as guide to the issuances

  3. Indexes to Nuclear Regulatory Commission issuances, July--December 1989

    International Nuclear Information System (INIS)

    1990-05-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  4. Indexes to Nuclear Regulatory Commission issuances, January--March 1996

    International Nuclear Information System (INIS)

    1996-01-01

    This publication is the 1st quarter 1996 index to issuances by the US NRC. These include issuances by the Commission, the Atomic Safety and Licensing Board Panel, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking

  5. Nuclear Regulatory Commission issuances: June 1995. Volume 41, Number 6

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-06-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decision on Petitions for Rulemaking (DPRM). This report contains four issuances by the CLI, 5 issuances by the LBP, and 1 issuance by the DD.

  6. Nuclear Regulatory Commission Issuances. Volume 23, No. 2

    International Nuclear Information System (INIS)

    1986-02-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  7. Nuclear Regulatory Commission issuances. Volume 22, No. 5

    International Nuclear Information System (INIS)

    1985-11-01

    This report includes the issuances received during November 1985 from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM)

  8. Commission for Energy regulation (CRE) - Activity report june 2006

    International Nuclear Information System (INIS)

    2006-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2006 activity report of CRE. Content: A - Opening of the electricity and natural gas markets to household consumers on 1 July 2007: CRE at the service of eligible customers (Information for eligible customers, Improved knowledge of non-household customers); Monitoring of the non-discrimination, transparency and independence of system operators (Drafting and distribution of codes of good conduct for system operators, The necessary improvement of system operator independence); Preparing the practical methods of opening: GTE 2007 and GTG 2007 (The necessary simplification of relations between operators and customers, Achieving a greater level of consumer information and protection, The clearly defined stages of the 'customer pathway', Profiling and settlement mechanisms: turning experience feedback from 2004 to good account); Persisting uncertainties and hurdles (The need for a suitable regulatory and legislative platform, Hurdles to the opening of the household market); B - Regulation of the natural gas market: The gas market in the European context (Increasing weight of imports in gas

  9. Commission for Energy regulation (CRE) - Activity report june 2006

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2006-07-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2006 activity report of CRE. Content: A - Opening of the electricity and natural gas markets to household consumers on 1 July 2007: CRE at the service of eligible customers (Information for eligible customers, Improved knowledge of non-household customers); Monitoring of the non-discrimination, transparency and independence of system operators (Drafting and distribution of codes of good conduct for system operators, The necessary improvement of system operator independence); Preparing the practical methods of opening: GTE 2007 and GTG 2007 (The necessary simplification of relations between operators and customers, Achieving a greater level of consumer information and protection, The clearly defined stages of the 'customer pathway', Profiling and settlement mechanisms: turning experience feedback from 2004 to good account); Persisting uncertainties and hurdles (The need for a suitable regulatory and legislative platform, Hurdles to the opening of the household market); B - Regulation of the natural gas market: The gas market in the European context (Increasing weight of

  10. Nuclear Regulatory Commission Issuances. Volume 45, No. 3

    International Nuclear Information System (INIS)

    1997-03-01

    This report includes the issuances received in March 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors' Decisions. 10 issuances were received: Louisiana Energy Services (2 issuances); Illinois Power Company and Soyland Power Cooperative; Ralph. L. Tetrick; University of Cincinnati; Consumers Power Company; Entergy Operations, Inc.; Georgia Power Company; Westinghouse Electric Corporation; and Wisconsin Electric Power Company. No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking

  11. Nuclear Regulatory Commission issuances. Volume 22, No. 4

    International Nuclear Information System (INIS)

    1985-10-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM). The summaries and headnotes preceding the opinions reported herein are not to be deemed a part of those opinions or to have any independent legal significance

  12. Indexes to Nuclear Regulatory Commission issuances, January--March 1992

    International Nuclear Information System (INIS)

    1992-06-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; Digests and headers; Legal citations index; subject index; and facility index

  13. United States Nuclear Regulatory Commission Staff practice and procedure digest

    International Nuclear Information System (INIS)

    1991-12-01

    This sixth edition of the NRC Staff Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board, and Atomic Safety and Licensing Board decisions issued during the period from July 1, 1972 to December 31, 1990 interpreting the NRC's Rules of Practice in 10 CFR Part 2. This sixth edition replaces in part earlier editions and revisions and includes appropriate changes reflecting the amendments to the Rules of Practice effective through December 31, 1990

  14. Indexes to Nuclear Regulatory Commission Issuances, July--December 1993

    International Nuclear Information System (INIS)

    1994-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Digests and Headers; Legal Citations Index; Subject Index, and Facility Index

  15. Indexes to Nuclear Regulatory Commission Issuances, January 1996--June 1996

    International Nuclear Information System (INIS)

    1996-09-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Board Panel, The Administrative Law Judges, the Director's Decisions, and the Decisions on Petitions for Rulemaking are presented in this document. The digests and indexes are intended to serve as a guide to the issuances. Information elements common the cases hear and ruled upon are displayed in one or more of five formats: case name index, headers and digests, legal citations index, subject index, and facility index

  16. Indexes to Nuclear Regulatory Commission issuances, January--June 1992

    International Nuclear Information System (INIS)

    1992-09-01

    Digests and indexes for insurances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index; and facility index

  17. Nuclear regulatory commission issuances. Volume 40, Number 1

    International Nuclear Information System (INIS)

    1994-07-01

    This report includes issuances concerning the following items. The Commission denies General Atomics' motion seeking to stay discovery in this proceeding until (1) the Commission determines whether it will grant General Atomics' Petition for Review of LBP-94-17 and/or Motion for Directed Certification; and (2) assuming that the commission grants the Petition/Motion, the Commission determines with finality the jurisdictional issues raised in General Atomics' previously filed Motion for Summary Disposition or for an Order of Dismissal. In this proceeding concerning an NRC Staff enforcement order issues in accordance with 10 C.F.R. section 2.202, the Licensing Board concludes that a Native American tribe wishing to participate in the proceeding to support the Staff's enforcement order has established its standing and presented two litigable contentions. This informal adjudicatory proceeding, convened under 10 C.F.R. Part 2, Subpart L, involves an application by the Chemetron Corporation (Licensee) for a license amendment. The proposed amendment concerns the decommissioning of the Licensee's Bert Avenue site in Newburgh Heights, Ohio, and its Harvard Avenue site and associated buildings at the McGean-Rohco property in Cuyahoga Heights, Ohio. In this license suspension and modification enforcement proceeding, the Licensing Board rules on prediscovery dispositive motions regarding ten issues specified by the parties for litigation. The Licensing Board determines that an Intervenor may move to admit into the proceeding a new basis for an already admitted contention. When it does so, the requirements for a late-filed contention are not applicable, but the Intervenor must show that it is timely to consider the new basis, in light of its seriousness and the timelines with which it has been raised. The Licensing Board also permitted Intervenor to file a reply to Applicant's response to his motion to add a new basis to his contention

  18. Indexes to Nuclear Regulatory Commission issuances, July--September 1993

    International Nuclear Information System (INIS)

    1994-01-01

    Digest and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. these digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index, and facility index

  19. Nuclear Regulatory Commission Issuances. Volume 45, No. 3

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-03-01

    This report includes the issuances received in March 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors` Decisions. 10 issuances were received: Louisiana Energy Services (2 issuances); Illinois Power Company and Soyland Power Cooperative; Ralph. L. Tetrick; University of Cincinnati; Consumers Power Company; Entergy Operations, Inc.; Georgia Power Company; Westinghouse Electric Corporation; and Wisconsin Electric Power Company. No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking.

  20. Indexes to Nuclear Regulatory Commission issuances, January--June 1989

    International Nuclear Information System (INIS)

    1989-09-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Appeal Panel, the Atomic Safety and Licensing Board Panel, the Administrative Law Judge, the Directors' Decisions, and the Denials of Petitions of Rulemaking are presented in this document. The information elements are displayed in one or more of five separate formats. These formats are case named index digests and headers, legal citations index, subject index, and facility index

  1. Indexes to Nuclear Regulatory Commission Issuances, January 1996--June 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-09-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Board Panel, The Administrative Law Judges, the Director`s Decisions, and the Decisions on Petitions for Rulemaking are presented in this document. The digests and indexes are intended to serve as a guide to the issuances. Information elements common the cases hear and ruled upon are displayed in one or more of five formats: case name index, headers and digests, legal citations index, subject index, and facility index.

  2. Indexes to Nuclear Regulatory Commission issuances, July--December, 1991

    International Nuclear Information System (INIS)

    1991-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Digests and Headers; Legal Citations Index; Subject Index; and Facility Index

  3. Indexes to Nuclear Regulatory Commission issuances, January--March 1993

    International Nuclear Information System (INIS)

    1993-07-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index; and facility index

  4. Indexes to Nuclear Regulatory Commission issuances, July--December 1988

    International Nuclear Information System (INIS)

    1989-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These information elements are displayed in one or more of five separate formats arranged as follows: case name index, digests and headers, legal citations index, subject index, and facility index

  5. Indexes to Nuclear Regulatory Commission issuances, July--September 1988

    International Nuclear Information System (INIS)

    1989-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These information elements are displayed in one or more of five separate formats. These formats are case name index, digests and headers, legal citations index, subject index and facility index

  6. Overview of the Nuclear Regulatory Commission's safety research program

    International Nuclear Information System (INIS)

    Beckjord, E.S.

    1989-01-01

    Accomplishments during 1988 of the Office of Nuclear Regulatory Research and the program of safety research are highlighted, and plans, expections, and needs of the next year and beyond are discussed. Topics discussed include: ECCS Appendix K Revision; pressurized thermal shock; NUREG-1150, or the PRA method performance document; resolution of station blackout; severe accident integration plan; nuclear safety research review committee; and program management

  7. Energy Regulation Commission. Activity report. 1 July - 31 December 2008

    International Nuclear Information System (INIS)

    2009-01-01

    After a description of the scope of activities, organisation and operation of the CRE (Commission de Regulation de l'Energie, Energy regulation commission) and of the CorDIS (Comite de reglement des differents et des sanctions de la CRE, CRE's Committee for settlements of controversies and sanctions), this report outlines the importance of the grid manager independence and of the regulation reinforcement for the building up of a domestic energy market. It discusses the role of the regulation authority in the interconnection of European grids, their operation security and supply security, but also in pricing and in investments. It highlights the relationship between the reduction of carbon emission, energy demand management, strengthening of electric grids, financial incentives, and advanced metering systems. It describes how the CRE ensures a good operation of electricity and natural gas markets

  8. Commission for Energy regulation (CRE) - Activity report june 2008; Commission de regulation de l'energie (CRE) - Rapport d'activite juin 2008

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2008-07-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2008 activity report of CRE. Content: A - How CRE works: CRE regulatory authority and organisation: Powers, Organisation; Budget resources; Personnel; B - The Standing Committee for Dispute Settlement and Sanctions (CoRDiS) activity: Admissibility, Authority; C - Building a single European energy market: Overview; Organisation and coordination of the main European regulators (Work carried out collectively by European regulators, Regulator organisation and development, CRE's relations with European Community institutions, Development of CEER activities outside the European Union); CRE's European activities (The contribution of European regulators to the Third Energy Package, Integration of gas markets, Integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, Opening up markets to benefit consumers); European Community activities (The European Commission's proposals for the internal energy market: the Third Energy Package, The European Commission's proposals for fighting climate change: the Climate Package, Infringement

  9. Commission for Energy regulation (CRE) - Activity report june 2008; Commission de regulation de l'energie (CRE) - Rapport d'activite juin 2008

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2008-07-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2008 activity report of CRE. Content: A - How CRE works: CRE regulatory authority and organisation: Powers, Organisation; Budget resources; Personnel; B - The Standing Committee for Dispute Settlement and Sanctions (CoRDiS) activity: Admissibility, Authority; C - Building a single European energy market: Overview; Organisation and coordination of the main European regulators (Work carried out collectively by European regulators, Regulator organisation and development, CRE's relations with European Community institutions, Development of CEER activities outside the European Union); CRE's European activities (The contribution of European regulators to the Third Energy Package, Integration of gas markets, Integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, Opening up markets to benefit consumers); European Community activities (The European Commission's proposals for the internal energy market: the Third Energy Package, The European Commission's proposals for fighting climate change: the Climate

  10. Indexes to Nuclear Regulatory Commission issuances, July-December 1981

    International Nuclear Information System (INIS)

    1981-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: case name index; digests and headers; legal citations index; subject index; and facility index

  11. Nuclear Regulatory Commission issuances, Volume 44, No. 4

    International Nuclear Information System (INIS)

    1996-10-01

    This report includes the issuances received in October 1996. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors' Decisions. 15 issuances were received and are abstracted individually in the database: Louisiana Energy Services, U.S. Enrichment Corporation, Yankee Atomic Electric Company, General Public Utilities Nuclear Corporation, James L. Shelton, Juan Guzman, Northern States Power Company, TESTCO Inc., Washington Public Power Supply System, all nuclear plants, Cleveland Electric Illuminating Company, Duke Power Company, Florida Power Corporation, and Northeast Nuclear Energy Company (2 issuances). No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking

  12. Nuclear Regulatory Commission issuances. Volume 44, Number 2

    International Nuclear Information System (INIS)

    1996-08-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decision on Petitions for Rulemaking (DPRM). The topics of this publication include the dismissal of a suit brought against Georgia Power Company in the transfer of Vogtle Electric Generating Plant, units 1 and 2 to Southern Nuclear; and denial of a petition to review the entire licensing process for Watts Bar Nuclear Plant, Unit 1 operated by the Tennessee Valley Authority

  13. Indexes to Nuclear Regulatory Commission Issuances, January--June 1997

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-10-01

    This report indexes the issuances heard and ruled upon from January through June 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors` Decisions, and the Decisions on Petitions for Rulemaking. Information provided for each case includes the case name, full test reference, issuance number, issues raised by appellants, legal citations, facility name and docket number, subject matter of issues and/or rulings, type of hearing, and type of issuance. Each issuance is displayed in one or more of five separate formats: (1) case name index, (2) headers and digests, (3) legal citations index, (4) subject index, and (5) facility index.

  14. Indexes to Nuclear Regulatory Commission Issuances, January--June 1997

    International Nuclear Information System (INIS)

    1997-01-01

    This report indexes the issuances heard and ruled upon from January through June 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, the Administrative Law Judges, the Directors' Decisions, and the Decisions on Petitions for Rulemaking. Information provided for each case includes the case name, full test reference, issuance number, issues raised by appellants, legal citations, facility name and docket number, subject matter of issues and/or rulings, type of hearing, and type of issuance. Each issuance is displayed in one or more of five separate formats: (1) case name index, (2) headers and digests, (3) legal citations index, (4) subject index, and (5) facility index

  15. Nuclear Regulatory Commission issuances, Volume 46, No. 4

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-10-01

    This report includes the issuances received in October 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors` Decisions. Five issuances were received on the following subjects: (1) decontamination and decommissioning funding for Sequoyah Fuels Corporation and General Atomics; (2) involvement in NRC-licensed activities by Aharon Ben-Haim; (3) Barnett Industrial X-Ray, Inc.; (4) spent fuel storage installation at Northern States Power Company; and (5) Vermont Yankee Nuclear Power Station. No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking.

  16. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest

    International Nuclear Information System (INIS)

    1990-11-01

    This Revision 8 of the fifth edition of the NRC Staff Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board and Atomic Safety and Licensing Board decisions issued during the period from July 1, 1972 to June 30, 1990 interpreting the NRC's Rules of Practice in 10 CFR Part 2. This Revision 8 replaces in part earlier editions and revisions and includes appropriate changes reflecting the amendments to the Rules of Practice effective through June 30, 1990

  17. Nuclear Regulatory Commission issuances, Volume 46, No. 4

    International Nuclear Information System (INIS)

    1997-10-01

    This report includes the issuances received in October 1997. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors' Decisions. Five issuances were received on the following subjects: (1) decontamination and decommissioning funding for Sequoyah Fuels Corporation and General Atomics; (2) involvement in NRC-licensed activities by Aharon Ben-Haim; (3) Barnett Industrial X-Ray, Inc.; (4) spent fuel storage installation at Northern States Power Company; and (5) Vermont Yankee Nuclear Power Station. No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking

  18. Indexes to Nuclear Regulatory Commission issuances, January--June 1991

    International Nuclear Information System (INIS)

    1991-10-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index, digest and headers, legal citations index, subject index, and facility index

  19. Indexes to Nuclear Regulatory Commission issuances, July--September 1990

    International Nuclear Information System (INIS)

    1990-12-01

    Digests and indexes for issuances of the commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. The information elements are displayed in one or more of five separate formats arranged as follows: case name index, digests and headers, legal citations index, subject index, and facility index

  20. Indexes to Nuclear Regulatory Commission issuances, July--December 1990

    International Nuclear Information System (INIS)

    1991-03-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: case name index, digests and headers legal citations index, subject index, and facility index

  1. Indexes to Nuclear Regulatory Commission issuances, January-March 1982

    International Nuclear Information System (INIS)

    1982-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. This information is displayed in one or more of five separate formats arranged as follows: case name index; digests and headers; legal citations index; subject index; and facility index

  2. Indexes to Nuclear Regulatory Commission issuances, January--June 1990

    International Nuclear Information System (INIS)

    1990-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALI), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: case name index, digests and headers, legal citations index, subject index, and facility index

  3. Indexes to Nuclear Regulatory Commission issuances, January--March 1991

    International Nuclear Information System (INIS)

    1991-06-01

    Digests and indexes for Issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: case name index, digests and headers, logical citations index, subject index and facility index

  4. Nuclear Regulatory Commission Issuances, Volume 44, No. 5

    International Nuclear Information System (INIS)

    1996-11-01

    This report includes the issuances received in November 1996. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors' Decisions. Seven issuances were received and are abstracted individually in the database: Emerick S. McDaniel, U.S. Enrichment Corporation, Sequoyah Fuels Corporation and General Atomics, all power reactor licensees, Florida Power and Light Company, Maine Yankee Atomic Power Company, and Northern States Power Company. No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking

  5. Nuclear Regulatory Commission issuances, Volume 44, No. 4

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-10-01

    This report includes the issuances received in October 1996. Issuances are from the Commission, the Atomic Safety and Licensing Boards, and the Directors` Decisions. 15 issuances were received and are abstracted individually in the database: Louisiana Energy Services, U.S. Enrichment Corporation, Yankee Atomic Electric Company, General Public Utilities Nuclear Corporation, James L. Shelton, Juan Guzman, Northern States Power Company, TESTCO Inc., Washington Public Power Supply System, all nuclear plants, Cleveland Electric Illuminating Company, Duke Power Company, Florida Power Corporation, and Northeast Nuclear Energy Company (2 issuances). No issuances were received from the the Administrative Law Judges or the Decisions on Petitions for Rulemaking.

  6. Overview of the Nuclear Regulatory Commission's revised 10 CFR Part 20

    International Nuclear Information System (INIS)

    Peterson, H.T. Jr.

    1990-01-01

    The principal Nuclear Regulatory Commission (NRC) regulations covering radiation protection are in Part 20 of Title 10 of the Code of Federal Regulations (10 CFR Part 20). These regulations apply to almost all NRC licensed activities including nuclear power and research reactors, nuclear medicine, industrial radiography and the use of most radioactive isotopes in research. The revised 10 CFR Part 20 is based on the 1977 recommendations of the International Commission on Radiological Protection (ICRP) in ICRP Publication No. 26, implements the 1987 Federal Radiation Guidance on Occupational Exposure and is generally consistent with the 1987 recommendations of the U.S. National Council on Radiation Protection and Measurements (NCRP) in NCRP Report No. 91. There are a number of areas where the Revised Part 20 employs new and more up-to-date scientific information and concepts. One major change is in the use of revised lung and GI tract models and more recent metabolic retention data to calculate Annual Limits on Intake (ALI's) and Derived Air Concentration limits (DAC's). The Appendix B in the Revised Part 20 employs new and more up-to-date scientific information and concepts. One major change is in the use of revised lung and GI tract models and more recent metabolic retention data to calculate Annual Limits on Intake (ALI's) and Derived Air Concentration limits (DAC's). The Appendix B in the Revised Part 20 contains data on occupational ALI's and DCA's and radionuclide concentration limits for releases to the general environment for over 750 radionuclides. The final rule is expected to be published early in September with an implementation data of January 1, 1992

  7. Nuclear Regulatory Commission Issuances, Volume 42, No. 2

    International Nuclear Information System (INIS)

    1995-08-01

    This report include the issuances received during the specificed period (August 1995) from the NRC, the Atomic Safety and Licensing Boards, the Administrative Law Judges, and the Decisions on Petitions for Rule Making. In these issuances, the following areas were addressed: (1) Emergency planning at the University of Missouri, (2) Transfer of operating license at Plant Vogtle, (3) Discriminatory action against a whistle-blower at Millstone Units 1 ampersand 2, (4) Regulatory issues related to embittlement and cracking at Oyster Creek, and (5) Age-related deterioration of reactor internals components at Pilgrim

  8. Improving nuclear regulation. NEA regulatory guidance booklets volumes 1-14

    International Nuclear Information System (INIS)

    2011-01-01

    A common theme throughout the series of NEA regulatory guidance reports, or 'green booklets', is the premise that the fundamental objective of all nuclear safety regulatory bodies is to ensure that nuclear facilities are continuously maintained and operated in an acceptably safe manner. In meeting this objective the regulator must bear in mind that it is the operator that has responsibility for safely operating the nuclear facility; the role of the regulator is to assess and to provide assurance regarding the operator's activities in terms of assuming that responsibility. The full series of these reports was brought together in one edition for the first time in 2009 and was widely found to be a useful resource. This second edition comprises 14 volumes, including the latest on The Nuclear Regulator's Role in Assessing Licensee Oversight of Vendor and Other Contracted Services. The reports address various challenges that could apply throughout the lifetime of a nuclear facility, including design, siting, manufacturing, construction, commissioning, operation, maintenance and decommissioning. The compilation is intended to serve as a knowledge management tool both for current regulators and the new nuclear professionals and organisations entering the regulatory field. Contents: Executive Summary; Regulatory Challenges: 1. The Role of the Nuclear Regulator in Promoting and Evaluating Safety Culture; 2. Regulatory Response Strategies for Safety Culture Problems; 3. Nuclear Regulatory Challenges Related to Human Performance; 4. Regulatory Challenges in Using Nuclear Operating Experience; 5. Nuclear Regulatory Review of Licensee Self-assessment (LSA); 6. Nuclear Regulatory Challenges Arising from Competition in Electricity Markets; 7. The Nuclear Regulatory Challenge of Judging Safety Back-fits; 8. The Regulatory Challenges of Decommissioning Nuclear Reactors; 9. The Nuclear Regulator's Role in Assessing Licensee Oversight of Vendor and Other Contracted Services

  9. Nuclear Regulatory Commission issuances: Opinions and decisions of the Nuclear Regulatory Commission with selected orders, July 1 - December 31, 1996. Volume 44, Pages 1 - 432

    International Nuclear Information System (INIS)

    1997-01-01

    The hardbound edition of the Nuclear Regulatory Commission Issuances is a final compilation of the monthly issuances. It includes all of the legal precedents for the agency within a six-month period. Any opinions, decisions, denials, memoranda and orders of the Commission inadvertently omitted from the monthly softbounds and any corrections submitted by the NRC legal staff to the printed softbound issuances are contained in the hardbound edition. Cross references in the text and indexes are to the NRCI page numbers which are the same as the page numbers in this publication. Issuances are referred to as follows: Commission--CLI, Atomic Safety and Licensing Boards--LBP, Administrative Law Judges--ALJ, Directors' Decisions--DD, and Decisions on Petitions for Rulemaking--DPRM

  10. Nuclear Regulatory Commission issuances: Opinions and decisions of the Nuclear Regulatory Commission with selected orders, July 1--December 31, 1996. Volume 44, Pages 1--432

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-10-01

    The hardbound edition of the Nuclear Regulatory Commission Issuances is a final compilation of the monthly issuances. It includes all of the legal precedents for the agency within a six-month period. Any opinions, decisions, denials, memoranda and orders of the Commission inadvertently omitted from the monthly softbounds and any corrections submitted by the NRC legal staff to the printed softbound issuances are contained in the hardbound edition. Cross references in the text and indexes are to the NRCI page numbers which are the same as the page numbers in this publication. Issuances are referred to as follows: Commission--CLI, Atomic Safety and Licensing Boards--LBP, Administrative Law Judges--ALJ, Directors` Decisions--DD, and Decisions on Petitions for Rulemaking--DPRM.

  11. Nuclear Regulatory Commission Issuances. Opinions and decisions of the Nuclear Regulatory Commission with selected orders: July 1, 1992--December 31, 1992, Volume 36, Pages 1--396

    Energy Technology Data Exchange (ETDEWEB)

    1992-12-31

    This is the thirty-sixth volume of issuances (1-396) of the Nuclear Regulatory Commission and its Atomic Safety and Licensing Boards, Administrative Law Judges, and Office Directors. It covers the period from July 1, 1992-December 31, 1992. Atomic Safety and Licensing Boards are authorized by Section 191 of the Atomic Energy Act of 1954. These Boards, comprised of three members conduct adjudicatory hearings on applications to construct and operate nuclear power plants and related facilities and issue initial decisions which, subject to internal review and appellate procedures, become the final Commission action with respect to those applications. Boards are drawn from the Atomic Safety and Licensing Board Panel, comprised of lawyers, nuclear physicists and engineers, environmentalists, chemists, and economists. The Atomic Energy Commission first established Licensing Boards in 1962 and the Panel in 1967.

  12. Nuclear Regulatory Commission issuances. Volume 17, No. 3

    International Nuclear Information System (INIS)

    1983-03-01

    This report contains the Issuances received during March 1983 from the Commission (CLI), the Atomic Safety and Licensing Appeal Boards (ALAB), the Atomic Safety and Licensing Boards (LBP), the Administrative Law Judge (ALJ), the Directors Decisions (DD), and the Denials of Petition for Rulemaking (DPRM). The Issuances concerned the following facilities: Three Mile Island Nuclear Station, Unit No. 1; Comanche Peak Steam Electric Station, Units 1 and 2; Vallecitos Nuclear Center; Floating Nuclear Power Plants; San Onofre Nuclear Generating Station, Units 2 and 3; Point Beach Nuclear Plant, Unit 1; Perry Nuclear Power Plant, Units 1 and 2; Shoreham Nuclear Power Station, Unit 1; Western New York Nuclear Service Center; Limerick Generating Station, Units 1 and 2; Seabrook Station, Units 1 and 2; Black Fox Station, Units 1 and 2; WmH Zimmer Nuclear Power Station, Unit 1; WPPSS Nuclear Project No. 1; Zion Nuclear Plant, Units 1 and 2; and South Texas Project, Units 1 and 2

  13. Indexes to Nuclear Regulatory Commission issuances, July--December 1992

    International Nuclear Information System (INIS)

    1993-06-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Digests and Legal Citations Index, Subject Index, and Facility Index. Subject words and/or phrases arranged alphabetically, indicate the issues and subjects covered in the issuances. The subject headings are followed by phrases that give specific information about the subject, as discussed in the issuances being indexed. These phrases are followed by the issuance number and the full text reference

  14. The commission of energy regulation: statute, missions and authority

    International Nuclear Information System (INIS)

    Laffaille, D.; Bossoutrot, Ch.

    2008-01-01

    The commission of energy regulation (CRE), which has superseded the commission of electricity regulation, was created by the law no. 2000-108 from February 10, 2000, relative to the modernization and development of the French electric utility. This article presents the situation of CRE's statute, missions and authority seven years after its creation. The statute of CRE warrants its independence, autonomy and impartiality. Its operation means consist in budgetary and personnel resources. Its main mission is the control of the conditions of use of gas and electricity networks and the respect of competition rules: free and transparent access to networks and infrastructures, control of the good operation and development of networks and facilities, regulation of markets, strengthening of the public utility mission. Its authority concerns the management of networks, the book-keeping control of energy operators, the settlement of disputes, the attribution of sanctions, the monitoring of energy markets operation etc. (J.S.)

  15. Risk-based regulation: A regulatory perspective

    International Nuclear Information System (INIS)

    Scarborough, J.C.

    1993-01-01

    In the early development of regulations for nuclear power plants, risk was implicitly considered through qualitative assessments and engineering reliability principles and practices. Examples included worst case analysis, defense in depth, and the single failure criterion. However, the contributions of various systems, structures, components and operator actions to plant safety were not explicitly assessed since a methodology for this purpose had not been developed. As a consequence of the TMI accident, the use of more quantitative risk methodology and information in regulation such as probabilistic risk analysis (PRA) increased. The use of both qualitative and quantitative consideration of risk in regulation has been a set of regulations and regulatory guides and practices that ensure adequate protection of public health and safety. Presently, the development of PRA techniques has developed to the point that safety goals, expressed in terms of risk, have been established to help guide further regulatory decision making. This paper presents the personal opinions of the author as regards the use of risk today in nuclear power plant regulation, areas of further information needs, and necessary plans for moving toward a more systematic use of risk-based information in regulatory initiatives in the future

  16. U.S. Nuclear Regulatory Commission bases for control of solid materials

    International Nuclear Information System (INIS)

    Meck, R.A.; Cardille, F.P.; Feldman, C.; Gnugnoli, G.N.; Huffert, A.M.; Klementowicz, S.P.

    2002-01-01

    The U.S. Nuclear Regulatory Commission (NRC) is considering whether to proceed with rulemaking on the control of solid materials with very low levels of associated radioactivity. The current implementation of clearance by NRC licensees is the context for the decision. Inputs to the decision include information gathering efforts of the Commission in the areas of public workshops, dose assessments and inventories, the recommendations of the National Academies' National Research Council (NAs) on regulatory alternatives, and participation in international efforts by the International Atomic Energy Agency (IAEA). (author)

  17. Study of the Nuclear Regulatory Commission quality assurance program

    International Nuclear Information System (INIS)

    Muller, F.W.

    1977-08-01

    Recommendations from a three month study are presented for quality assurance in nuclear power plants as it is practiced in industry and regulated by the NRC. Requested by the NRC, the study was accomplished through on-site visits by Sandia personnel at NRC offices and industry locations and through discussion with relevant technical society groups and interested individuals. The study group recommended changes to improve QA regulation by the NRC, to improve industry application of 10CFR50, Appendix B criteria, and to extend and expand the scope of QA activities by both industry and NRC

  18. Problems and experience of regulatory review associated with plant construction and commissioning

    International Nuclear Information System (INIS)

    Commander, W.

    1979-01-01

    The work of the Assessment Branch of NII covering the regulatory review during design safety assessment, construction, commissioning and operation is described commencing with the nuclear licensing procedure through licence variations and conditions attached to the licence, to the final stages of plant construction up to commercial operation and full power production. The importance of the application of safety assessment principles is outlined, the importance of the Safety Inspectorate Schedule described, and the need to retain organisational and regulatory flexibility emphasised. (author)

  19. Recommended revisions to nuclear regulatory commission seismic design criteria

    International Nuclear Information System (INIS)

    Coats, D.W.

    1981-01-01

    Task Action Plan (TAP) A-40 was developed by consolidating specific technical assistance studies initiated to identify and quantify the conservatism inherent in the seismic design sequence of current NRC criteria. Task 10 of TAP A-40 provided a technical review of the results of the other nine engineering and seismological tasks in TAP A-40 and recommended changes to the existing NRC criteria based on this review. We used the team approach to accomplish the objectives of Task 10 in an efficient manner and to provide the best technical product possible within the limited time available. The team consisted of a core group of Lawrence Livermore National Laboratory personnel and selected consultants. The recommendations summarized in this paper were not based solely on the results of the tasks in TAP A-40 but went far beyond that data base to encompass all available and appropriate literature. Some recommendations are based on the expertise of core members and consultants that stem from unpublished data, research, and experience. Copies of the pertinent sections of the Standard Review Plan (SRP) and Regulatory Guides as well as the reports developed under TAP A-40 were provided to the participants. These reports, other available engineering literature, and the experience of the consultants and core group provided technical basis for the recommendations. (orig./HP)

  20. European Commission action aimed at constructing a European regulatory framework

    International Nuclear Information System (INIS)

    Ristori, D.

    2010-01-01

    The challenge of a low-carbon economy provides a new incentive for the development of renewable energies as well as of nuclear energy. The latter calls for a high level of safety and security. The EU has a role in providing a legal framework for this purpose as well as ensuring that these standards are respected internationally. For over 50 years the EURATOM Treaty has offered the legal basis for a wide range of initiatives supporting this policy. The EU has competences under chapter 3, 'Health and Safety', for the establishment of basic safety standards for the protection against ionizing radiation. These have extended beyond the scope of nuclear energy and now include medical exposures as well as natural radiation sources. The latest revision of the BSS-Directive, to be proposed in 2011, was an opportunity for the consolidation of all Community legislation. A ruling of the Court of Justice in 1999 paved the way for the establishment of standards on the safety of nuclear installations. A common vision on this matter was achieved through the creation of a body of European Safety Regulators (ENSREG) and the adoption of a specific Safety Directive in 2009. This new Directive translates internationally agreed safety standards into legally binding EU legislation and strengthens the position of national Regulators. (author)

  1. U.S. Nuclear Regulatory Commission Safety Culture Oversight

    International Nuclear Information System (INIS)

    Sieracki, D. J.

    2016-01-01

    The NRC recognises that it is important for all organizations performing or overseeing regulated activities to establish and maintain a positive safety culture commensurate with the safety and security significance of their activities and the nature and complexity of their organizations and functions. The NRC’s approach to safety culture is based on the premise that licencees bear the primary responsibility for safety. The NRC provides oversight of safety culture through expectations detailed in policy statements, safety culture assessor training for NRC inspectors, the oversight process, and the Allegations and Enforcement Programs. The NRC’s Safety Culture Policy Statement (SCPS) sets forth the Commission’s expectation that individuals and organizations establish and maintain a positive safety culture commensurate with the safety and security significance of their activities and the nature and complexity of their organizations and functions. The SCPS is not a regulation. It applies to all licencees, certificate holders, permit holders, authorisation holders, holders of quality assurance program approvals, vendors and suppliers of safety-related components, and applicants for a licence, certificate, permit, authorisation, or quality assurance program approval, subject to NRC authority.

  2. Nuclear Regulatory Commission's antitrust review process: an analysis of the impacts

    International Nuclear Information System (INIS)

    1981-06-01

    The Nuclear Regulatory Commission's (NRC) antitrust process is reviewed and its impacts to small systems and applicant systems are studied. This process takes the form of a description of the NRC's antitrust review process as implemented, a generic categorization of potential impacts and individual case-by-case studies of four different utilities

  3. The U.S. Nuclear Regulatory Commission's role in the management of radioactive wastes

    International Nuclear Information System (INIS)

    Bernero, R.M.; Kalman, K.L.

    1991-01-01

    This paper discusses the U.S. Nuclear Regulatory Commission's (NRC's) role in the management of radioactive waste. It provides an overview of the NRC's programs for the management of High-Level and Low-Level radioctive wastes and uranium mill tailings. (author) 7 refs

  4. Information system of the U.S. Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Farber, G.

    1982-09-01

    On the basis of legal regulations the U.S. NRC maintain a far-reaching information system by means of which their documents are easily made available to the interested public. The essential parts of the information system are - the central Public Document Room in Washington, D.C., - the National Technical Information Center in the Department of Commerce, - the co-operation with the Government Printing Office, - the Nuclear Safety Information Center in the Oak Ridge National Laboratory, and - the National Energy Software Center in the Argonne National Laboratory. Via these facilities the NRC provide all interested institutions with information on the activities in connection with their statutory tasks. Accordingly numerous documents concerning of approval and monitoring of nuclear facilities as well as the use, transport and storage of fissionable material, are granted for perusion. (orig.) [de

  5. Nuclear Regulatory Commission issuances. Opinions and decisions of the Nuclear Regulatory Commission with selected orders, July 1, 1994--December 31, 1994. Volume 40, Pages 1--387

    International Nuclear Information System (INIS)

    1994-01-01

    The hardbound edition of the Nuclear Regulatory Commission Issuances is a final compilation of the monthly issuances. It includes all of the legal precedents for the agency within a six-month period. Any opinions, decisions, denials, memoranda and orders of the Commission inadvertently omitted from the monthly softbounds and any corrections submitted by the NRC legal staff to the printed softbound issuances are contained in the hardbound edition. Cross references in the text and indexes are to the NRCI page numbers which are the same as the page numbers in this publication. This book covers the following: issuances of the NRC; issuances of the Atomic Safety and Licensing Boards; and issuances of Directors' decisions

  6. Nuclear Regulatory Commission issuances. Opinions and decisions of the Nuclear Regulatory Commission with selected orders, July 1, 1994--December 31, 1994. Volume 40, Pages 1--387

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-12-31

    The hardbound edition of the Nuclear Regulatory Commission Issuances is a final compilation of the monthly issuances. It includes all of the legal precedents for the agency within a six-month period. Any opinions, decisions, denials, memoranda and orders of the Commission inadvertently omitted from the monthly softbounds and any corrections submitted by the NRC legal staff to the printed softbound issuances are contained in the hardbound edition. Cross references in the text and indexes are to the NRCI page numbers which are the same as the page numbers in this publication. This book covers the following: issuances of the NRC; issuances of the Atomic Safety and Licensing Boards; and issuances of Directors` decisions.

  7. The Energy Regulatory Commission (1). Law of the Comision Reguladora de Energia

    International Nuclear Information System (INIS)

    1995-01-01

    The Energy Regulatory Commission. Reforms to the Electric Energy Public Service Law (1992) and the Regulatory Law of Article 27 on Petroleum (1995) have brought about fundamental changes in the electric and natural gas industries. The legal reforms explicitly permit the private sector to construct, operate, and own, systems of electric generation and natural gas transportation, storage and distribution. The participation of the private sector in these areas required a redefinition in the government regulatory institutions. Accordingly the Federal Congress enacted the law of the Comision Reguladora de Energia (CRE) in 1995. The CRE law expands the scope of the CRE's authority and the breadth of its powers beyond those established when it was initially created in 1993. The CRE commenced operations in January 1994 as a decentralized technical and consultative body of the Energy Ministry. The decree that created the Commission limited the scope of its authority to an analysis and consultative role applicable only to the electric industry. (Author)

  8. Report on the establishment and operation of the Federal Energy Regulatory Commission's Daycare Center

    Energy Technology Data Exchange (ETDEWEB)

    1991-09-16

    We have completed an inspection of the Federal Energy Regulatory Commission's (FERC) Daycare Center (Center). The purpose of the inspection was to review for efficiency, economy and compliance with laws and regulations, FERC's establishment and operation of the Center. The inspection objectives were to review: (1) FERC's compliance with Federal laws and requirements of the General Services Administration and the District of Columbia; (2) the source and amount of funds for establishing and operating the Center; and (3) the organizational relationships between FERC, the Center and the contractor operating the Center.

  9. 75 FR 52046 - Development of U.S. Nuclear Regulatory Commission Safety Culture Policy Statement: Public Meeting

    Science.gov (United States)

    2010-08-24

    ... is working towards increasing the attention that is given to safety culture as part of its efforts to... NUCLEAR REGULATORY COMMISSION Development of U.S. Nuclear Regulatory Commission Safety Culture..., Nevada hearing facility to solicit comments on the revision of its draft safety culture policy statement...

  10. Commission of energy regulation. 2004 activity report; Commission de regulation de l'energie. Rapport d'activite 2004

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2004-07-01

    The commission of energy regulation (CRE) is an independent administrative authority in charge of the control of the operation of gas and electricity markets. This document is the fifth activity report of CRE and covers the July 1, 2003 - June 30, 2004 period, which corresponds to the era of opening of energy markets as a consequence of the enforcement of the June 26, 2003 European directive. In the framework of the stakes made by energy markets liberalization, this document presents the situation of the gas and electricity markets during this period (European framework, regulation of both markets, public utility mission..) and describes CRE's means for the monitoring of these markets. (J.S.)

  11. NRC [Nuclear Regulatory Commission] staff evaluation of the General Electric Company Nuclear Reactor Study (''Reed Report'')

    International Nuclear Information System (INIS)

    1987-07-01

    In 1975, the General Electric Company (GE) published a Nuclear Reactor Study, also referred to as ''the Reed Report,'' an internal product-improvement study. GE considered the document ''proprietary'' and thus, under the regulations of the Nuclear Regulatory Commission (NRC), exempt from mandatory public disclosure. Nonetheless, members of the NRC staff reviewed the document in 1976 and determined that it did not raise any significant new safety issues. The staff also reached the same conclusion in subsequent reviews. However, in response to recent inquiries about the report, the staff reevaluated the Reed Report from a 1987 perspective. This re-evaluation, documented in this staff report, concluded that: (1) there are no issues raised in the Reed Report that support a need to curtail the operation of any GE boiling water reactor (BWR); (2) there are no new safety issues raised in the Reed Report of which the staff was unaware; and (3) although certain issues addressed by the Reed Report are still being studied by the NRC and the industry, there is no basis for suspending licensing and operation of GE BWR plants while these issues are being resolved

  12. The European Commission's light bulb decree: Another costly regulation?

    International Nuclear Information System (INIS)

    Frondel, Manuel; Lohmann, Steffen

    2011-01-01

    Since September 2009, Regulation 244/2009 of the European Commission enforces the gradual phase-out of incandescent light bulbs. As of September 2012, only energy-efficient lighting sources will be allowed for sale. Among these are halogen light bulbs, light-emitting diodes (LED), or compact fluorescent light bulbs-often referred to as energy-saving light bulbs. The Commission's justification for the phase-out of conventional light bulbs maintains that a reduction in the electricity consumed will not only lead to lower energy cost for private households and industrial consumers, but at the same time lead to a decrease in greenhouse gas emissions. This article discusses possible reasons for the slow market diffusion of energy-saving light bulbs and shows that the investment in energy-efficient light bulbs does not necessarily lead to significant cost reductions. Drawing on some illustrative examples, we demonstrate that the use of cheaper incandescent bulbs instead of energy-saving light bulbs can be economically rational in cases of rather low usage times, in which the higher initial purchasing price might only pay off after very long time spans. Furthermore, due to the coexistence with the European Emissions Trading Scheme (ETS), this regulation attains no additional emission reductions beyond those achieved by the ETS alone. We thus conclude that the general ban of incandescent light bulbs is inappropriate and should be abolished by the Commission. - Research highlights: → This article discusses reasons for the slow market diffusion of energy-saving light bulbs. → We show that using incandescent bulbs can be rational in cases of rather low usage times. → We conclude that the general ban of incandescent light bulbs should be abolished by the Commission.

  13. Ratemaking treatment of decommissioning costs by the Federal Energy Regulatory Commission

    International Nuclear Information System (INIS)

    Lenart, R.J.

    1985-01-01

    The Nuclear Regulatory Commission (NRC) has the responsibility for the assurance of funds at the time of decommissioning. The Federal Energy Regulatory Commission (FERC), in conjunction with the State Public Utility Commissions, have the responsibilty to ensure that utilities have just and reasonable rates and an opportunity to collect an appropriate amount of dollars to decommission a nuclear reactor at the conclusion of its service life. Therefore, the Federal Energy Regulatory Commission allows utilities to include nuclear power plant decommissioning costs in rates based on the following ratemaking concepts: (1) that the methodology used by a utility equitably allocates costs between present and future ratepayers who receive service from a nuclear unit; (2) that, given the uncertainty and imprecision that are included in cost estimates for events that will transpire 20-40 years in the future, the FERC chose to err on the low side rather than run the risk of overcharging current customers for future decommissioning expense; and (3) that, as decommissioning experience accumulates, as decommissioning technology improves, and as decommissioning estimates become more refined, utilities would continue to seek revised decommissioning expense allowances from FERC in order to ensure that actual decommissioning costs are recovered over the useful life in which the plant provides service

  14. System engineering in the Nuclear Regulatory Commission licensing process: Program architecture process and structure

    International Nuclear Information System (INIS)

    Romine, D.T.

    1989-01-01

    In October 1987, the U.S. Nuclear Regulatory Commission (NRC) established the Center for Nuclear Waste Regulatory Analyses at Southwest Research Institute in San Antonio, Texas. The overall mission of the center is to provide a sustained level of high-quality research and technical assistance in support of NRC regulatory responsibilities under the Nuclear Waste Policy Act (NWPA). A key part of that mission is to assist the NRC in the development of the program architecture - the systems approach to regulatory analysis for the NRC high-level waste repository licensing process - and the development and implementation of the computer-based Program Architecture Support System (PASS). This paper describes the concept of program architecture, summarizes the process and basic structure of the PASS relational data base, and describes the applications of the system

  15. Overall review strategy for the Nuclear Regulatory Commission's High-Level Waste Repository Program

    International Nuclear Information System (INIS)

    Johnson, R.L.

    1994-11-01

    The Overall Review Strategy gives general guidance to the Nuclear Regulatory Commission staff for conducting it's license application and pre-license application reviews. These reviews are in support of the Commission's construction authorization decision for a geologic repository for the disposal of high-level radioactive waste. Objectives and strategies are defined that focus the staff's reviews on determining compliance with requirements of 10 CFR Part 60. These strategies define how the staff prioritizes its reviews on those key technical uncertainties considered to be most important to repository performance. Strategies also give guidance for developing, in an integrated way, the License Application Review Plan together with supporting performance assessments, analyses, and research

  16. Commission for Energy regulation (CRE) - Activity report June 2004

    International Nuclear Information System (INIS)

    2004-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2004 activity report of CRE. Content: A - Opening of the gas and electricity markets for professional customers on 1 July 2004; B - Regulation of the gas market: Gas markets and players (The European environment, The French gas market); Regulation of the gas market (Implementing regulation, Works planned for the coming year; C - Regulation of the electricity market: The electricity markets and players (The European electricity markets, The French electricity market, Monitoring the electricity market); Regulation of the French electricity market (Access to public grid, Cross-border exchanges, Un-bundled accounting principles); The public electricity service in the regulated market (Content of the public service, Public service charges, Electricity production public service financing, Electricity sales tariffs) D - The working of CRE: How CRE exercises its jurisdiction, Tools; E - Appendices: Glossary, Units and conversions, Council of European Energy Regulators, Index of tables and figures

  17. Commission for Energy regulation (CRE) - Activity report June 2004

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2004-07-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2004 activity report of CRE. Content: A - Opening of the gas and electricity markets for professional customers on 1 July 2004; B - Regulation of the gas market: Gas markets and players (The European environment, The French gas market); Regulation of the gas market (Implementing regulation, Works planned for the coming year; C - Regulation of the electricity market: The electricity markets and players (The European electricity markets, The French electricity market, Monitoring the electricity market); Regulation of the French electricity market (Access to public grid, Cross-border exchanges, Un-bundled accounting principles); The public electricity service in the regulated market (Content of the public service, Public service charges, Electricity production public service financing, Electricity sales tariffs) D - The working of CRE: How CRE exercises its jurisdiction, Tools; E - Appendices: Glossary, Units and conversions, Council of European Energy Regulators, Index of tables and figures.

  18. Pilot program: NRC severe reactor accident incident response training manual: US Nuclear Regulatory Commission response

    International Nuclear Information System (INIS)

    Sakenas, C.A.; McKenna, T.J.; Perkins, K.; Miller, C.W.; Hively, L.M.; Sharpe, R.W.; Giitter, J.G.; Watkins, R.M.

    1987-02-01

    This pilot training manual has been written to fill the need for a general text on NRC response to reactor accidents. The manual is intended to be the foundation for a course for all NRC response personnel. US Nuclear Regulatory Commission Response is the fifth in a series of volumes that collectively summarize the US Nuclear Regulatory Commission (NRC) emergency response during severe power reactor accidents and provide necessary background information. This volume describes NRC response modes, organizations, and official positions; roles of other federal agencies are also described briefly. Each volume serves, respectively, as the text for a course of instruction in a series of courses for NRC response personnel. These materials do not provide guidance or license requirements for NRC licensees. Each volume is accompanied by an appendix of slides that can be used to present this material. The slides are called out in the text

  19. Independent regulatory authorities - a comparative study of European energy regulators

    International Nuclear Information System (INIS)

    Sander Johansen, K.; Holm Pedersen, L.; Moll Soerensen, E.

    2004-04-01

    Independent regulatory authorities are widely recommended as part of the institutional design of liberalised energy markets - not least by the European Commission. This report describes and compares the regulatory authorities for energy in the EU. Arguments for regulatory independence are presented and discussed, and an index is developed to measure the degree of conformance to theories of regulatory independence. It is established that the main pattern of variation is that countries, which formerly had strong state-owned companies, have chosen to create regulatory authorities at state level with many institutional safeguards for independence. (au)

  20. Legal principles of regulatory administration and nuclear safety regulation

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Kyeong Hui; Cheong, Sang Kee [Hannam Univ., Taejon (Korea, Republic of)

    2000-12-15

    This research presents a critical analysis and evaluation of principles of administrative laws in order to provide framework of structural reform on the nuclear safety regulation system. The focus of this analysis and evaluation is centered around the area of origin of regulatory administrative laws; authorities of regulation; procedures of regulatory actions; regulatory enforcement; and administrative relief system. In chapter 2 the concept of regulatory administration is analysed. Chapter 3 identifies the origin of regulatory administration and the principles of administration laws. It also examines legal nature of the nuclear safety standard. In relation to regulatory authorities. Chapter 4 identifies role and responsibility of administration authorities and institutions. It also examines fundamental principles of delegation of power. Then the chapter discusses the nuclear safety regulation authorities and their roles and responsibilities. Chapter 5 classifies and examines regulatory administration actions. Chapter 6 evaluates enforcement measure for effectiveness of regulation. Finally, chapter 7 discusses the administrative relief system for reviewing unreasonable regulatory acts.

  1. Specific problems and practical experience of regulatory inspection during commissioning in the United Kingdom

    International Nuclear Information System (INIS)

    Lewis, G.

    1977-01-01

    The commissioning of nine Magnox and two Advanced Gas-cooled Reactor Nuclear Power Plants in the United Kingdom during the last sixteen years under the regulatory control of the Nuclear Installations Inspectorate of the Health and Safety Executive has been based on a Stage Approval Philosophy starting with proof-testing of the primary gas circuit and concluding with tests on the reactor at full power. The practical experience gained during this period has enabled the Nuclear Installations Inspectorate to rationalise the procedures and test requirements without comporomising safety standards. The Operating Rules and Maintenance Schedules are approved for commissioning and during this period are reviewed for their adequacy for future power operation of the plant. The organisation, documentation, test procedures and the commissioning programme used for the Advanced Gas-cooled Reactors are briefly explained. (author)

  2. Transforming public utility commissions in the new regulatory environment: Some issues and ideas for managing change

    Energy Technology Data Exchange (ETDEWEB)

    Wirick, D.W.; Davis, V.W.; Burns, R.E.; Jones, D.N.

    1996-07-01

    In the face of sweeping changes in utility markets and regulatory practices, public utility commissions are being forced to change in fundamental ways--to substantially transform themselves rather than to make only incremental changes in their operations. Managing this process of radical change is complicated by the fact that for the foreseeable future some portions of utility markets (e.g., water utilities) will function much as they have before. Some envision commissions in the future that are more externally focussed, that rely more on dispute resolution than adjudicatory proceedings, that concentrate on identifying and understanding competitive markets, that are more automated, and that are more likely to question old assumptions and definitions. This report identifies the considerations commissions might apply for identifying what mix of skills or fields of experise should compromise the technical staff. Factors are also identified which point towards a sectoral arrangement of staff and those factors which point toward a functional approach.

  3. U.S. Nuclear Regulatory Commission 1980 annual report. Annual report No. 6

    International Nuclear Information System (INIS)

    1981-01-01

    Contents include: Overview; Aftermath of the accident at Three Mile Island; Emergency preparedness; Reactor regulation; Operating experience; Materials regulation and transportation; Domestic safeguards; Waste management; Inspection and enforcement; Cooperation with the states; International cooperation; Standards development; Nuclear regulatory research; Communicating with the public; Proceedings and litigation; Administration and management; Appendices

  4. Public consultation by the French Energy Regulatory Commission of 14 September 2016 relating to the new tariffs for the use of regulated LNG terminals. Evolution of the ATM5 offer Proposals from Elengy and Fosmax LNG

    International Nuclear Information System (INIS)

    2016-01-01

    The aim of this public consultation is to gather input from the market regarding the options envisaged by the CRE for the ATTM5 tariffs. These concern the tariff regulation framework, the level of tariffs and the structure of the tariff offerings of the LNG terminals. Items from the tariff documentation sent to the CRE by Elengy and Fosmax LNG would lead to a change in unit tariffs of -0.7% for Montoir, -13.9% for Fos Tonkin and -11.9% for Fos Cavaou. At this stage, with regard to the requests from Elengy and Fosmax LNG, the CRE is planning: - to adjust the trajectories of the net operational charges requested by the LNG terminal operators; - to decide on a weighted average cost of capital (WACC) equal to that of the transmission network operators, within a range from 4.75% to 5.5% actual before tax, plus a bonus reflecting the specific risks to LNG terminals, within a range from 1.0% to 2.4%. Depending on the rate of remuneration applied, and the direction of the net operational charges selected, the change in the ATTM5 tariff may be between -2.5% and -10.6% inclusive for Montoir, between -14.4% and -18.5% inclusive for Fos Tonkin and between -14.8% and -26.1% inclusive on average per year for Fos Cavaou. The CRE is planning the following schedule for drawing up the ATTM5 tariff and its entry into force: - this public consultation is open up to 14 October 2016; - the CRE's tariff deliberation, having consulted the French Higher Energy Council (CSE), will be adopted at the end of 2016; - the ATTM5 tariff will enter into force on 1 April 2017. At the same time as this public consultation, the CRE is publishing an audit of the request from LNG terminal operators on the rate of remuneration for the period of the ATTM5

  5. Safety regulation: The lessons of workplace safety rule management for managing the regulatory burden

    OpenAIRE

    Hale, A.R.; Borys, D.; Adams, M.

    2012-01-01

    There is a strong political consensus in a number of countries that occupational safety and health regulation is stifling industrial innovation and development and is feeding a culture of damaging risk aversion and petty bureaucracy. In a number of countries this has led to proposals to repeal regulations and reduce the regulatory burden. The authors were commissioned to prepare a discussion paper on this issue by the Mercatus Center of George Mason University in Arlington, Virginia, aimed pa...

  6. The use of information systems to transform utilities and regulatory commissions: The application of geographic information systems

    Energy Technology Data Exchange (ETDEWEB)

    Wirick, D.W.; Montgomery, G.E.; Wagman, D.C.; Spiers, J.

    1995-09-01

    One technology that can assist utilities remain financially viable in competitive markets and help utilities and regulators to better serve the public is information technology. Because geography is an important part of an electric, natural gas, telecommunications, or water utility, computer-based Geographic Information Systems (GIS) and related Automated Mapping/Facilities Management systems are emerging as core technologies for managing an ever-expanding variety of formerly manual or paper-based tasks. This report focuses on GIS as an example of the types of information systems that can be used by utilities and regulatory commissions. Chapter 2 provides general information about information systems and effects of information on organizations; Chapter 3 explores the conversion of an organization to an information-based one; Chapters 4 and 5 set out GIS as an example of the use of information technologies to transform the operations of utilities and commissions; Chapter 6 describes the use of GIS and other information systems for organizational reengineering efforts; and Chapter 7 examines the regulatory treatment of information systems.

  7. 10 CFR Appendix A to Part 73 - U.S. Nuclear Regulatory Commission Offices and Classified Mailing Addresses

    Science.gov (United States)

    2010-01-01

    ... PROTECTION OF PLANTS AND MATERIALS Pt. 73, App. A Appendix A to Part 73—U.S. Nuclear Regulatory Commission..., Louisiana, Montana, Nebraska, Nevada, New Mexico, North Dakota, Oklahoma, Oregon, South Dakota, Texas, Utah...

  8. Commission de regulation de l'energie. Activity report 2013

    International Nuclear Information System (INIS)

    2014-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2013 activity report of CRE. Contents: 1 - Message from the board; 2 - The Energy Regulatory Commission; 3 - 2013: the energy market/S; 4 - The action of the regulator under the control of the judge; 5 - The usage tariff for public electricity networks; 6 - Smart grids; 7 - Consumers; 8 - Annex; 9 - Acronyms

  9. The role of the Nuclear Regulatory Commission in the management of nuclear waste

    International Nuclear Information System (INIS)

    Thompson, H.L. Jr.

    1988-01-01

    In general, the US Nuclear Regulatory Commission (NRC) is responsible for reviewing and making licensing decisions to ensure that the US Department of Energy's (DOE's) high-level waste repository is designed, constructed, and operated without unreasonable risk to public health and safety. In implementing this responsibility, however, the commission's guidance to the staff is that, in the absence of unresolved safety concerns, the NRC regulatory program will not delay the executive branch's program as set forth in the DOE project decision schedule. The NRC role for the next several years will be to develop its licensing framework and to consult with DOE on its plans. An essential ingredient in the success of both NRC's and DOE's respective missions is the need for free and open exchange of information, which will assure us that the concerns of all parties are addressed. With regard to low-level radioactive waste, the states have the lead responsibility for disposal. The NRC also provides assistance to the states and compacts on such items as regulatory programs, site characterization, and mixed waste disposal. Another of the NRC's roles is in the management of uranium mill tailings. Currently, most of the NRC's attention is focused on ensuring adequate long-term stabilization of tailings

  10. Risk Assessment Review Group report to the U.S. Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Lewis, H.W.; Budnitz, R.J.; Kouts, H.J.C.; Loewenstein, W.B.; Rowe, W.D.; von Hippel, F.; Zachariasen, F.

    1978-09-01

    The Risk Assessment Review Group was organized by the U.S. Nuclear Regulatory Commission on July 1, 1977, with four elements to its charter: clarify the achievements and limitations of WASH-1400, the ''Rasmussen Report''; assess the peer comments thereon, and responses to those comments; study the present state of such risk assessment methodology; and recommend to the Commission how (and whether) such methodology can be used in the regulatory and licensing process. Areas of study include: risk assessment methodologies; statistical issues; completeness; the data base; and the WASH-1400 assessment of the damage to human health from radiation after a postulated accident. Specific items discussed include: Browns Ferry; common cause failure; human factors; format and scrutability; the peer review process; earthquakes; risk perception; allegations by UCS concerning WASH-1400 treatment of quality assurance and quality control; current role of probabilistic methods in the regulatory process; acts of violence; ATWS; influence of design defects in quality assurance failures; and calculation of population doses from given releases of radionuclides

  11. Implementing 'Continuous Improvement' in the U.S. Nuclear Regulatory Commission's Decommissioning Program

    International Nuclear Information System (INIS)

    Orlando, D. A.; Buckley, J. T.; Johnson, R. L.; Gillen, D. M.

    2006-01-01

    The United States Nuclear Regulatory Commission's (US NRC's) comprehensive decommissioning program encompasses the decommissioning of all US NRC licensed facilities, ranging from the termination of routine licenses for sealed sources, to the closure of complex materials sites and nuclear power reactor facilities. Of the approximately 200 materials licenses that are terminated each year, most are routine and require little, if any, remediation to meet the US NRC unrestricted release criteria. However, some present technical and policy challenges that require large expenditures of resources, including a few complex materials sites that have requested license termination under the restricted-use provisions of 10 CFR 20.1403. Fiscal constraints to reduce budgeted resources in the decommissioning program, as well as concerns over the time to complete the decommissioning process have led to actions to improve the program and use resources more efficiently. In addition, the US NRC's Strategic Plan requires efforts to identify and implement improvements to US NRC programs in order to improve efficiency, effectiveness, timeliness, and openness, of the US NRC's activities, while maintaining the necessary focus on safety. Decommissioning regulations, and more recently the analysis of several issues associated with implementing those regulations, also have been significant catalysts for improvements in the decommissioning program. Actions in response to these catalysts have resulted in a program focused on the management of complex sites in a comprehensive, consistent, and risk-informed manner, as opposed to the past practice of focusing on sites deemed to be problematic. This paper describes the current status of the decommissioning of US NRC-licensed nuclear facilities, including an overview of recent decommissioning project completion efforts. It provides a detailed summary of past, current, and future improvements in the US NRC decommissioning program including the

  12. 75 FR 62153 - Notice of the Nuclear Regulatory Commission Issuance of Materials License SUA-1596 for Uranium...

    Science.gov (United States)

    2010-10-07

    ... Commission Issuance of Materials License SUA-1596 for Uranium One Americas, Inc. Moore Ranch In Situ Recovery.... SUPPLEMENTARY INFORMATION: The Nuclear Regulatory Commission (NRC) has issued a license to Uranium One Americas, Inc. (Uranium One) for its Moore Ranch uranium in situ recovery (ISR) facility in Campbell County...

  13. Recommended revisions to Nuclear Regulatory Commission seismic design criteria. Technical report

    International Nuclear Information System (INIS)

    Coats, D.W.

    1980-05-01

    This report recommends changes in the Nuclear Regulatory Commission's (NRC's) criteria now used in the seismic design of nuclear power plants. Areas covered include ground motion, soil-structure interaction, structures, and equipment and components. Members of the Engineering Mechanics Section of the Nuclear Test Engineering Division at Lawrence Livermore Laboratory (LLL) generally agreed upon the recommendations, which are based on (1) reports developed under the NRC's Task Action Plan A-40, (2) other available engineering literature, and (3) recommendations of nationally recognized experts retained by LLL specifically for this task

  14. Technical support to the Nuclear Regulatory Commission for the boiling water reactor blowdown heat transfer program

    International Nuclear Information System (INIS)

    Rice, R.E.

    1976-09-01

    Results are presented of studies conducted by Aerojet Nuclear Company (ANC) in FY 1975 to support the Nuclear Regulatory Commission (NRC) on the boiling water reactor blowdown heat transfer (BWR-BDHT) program. The support provided by ANC is that of an independent assessor of the program to ensure that the data obtained are adequate for verification of analytical models used for predicting reactor response to a postulated loss-of-coolant accident. The support included reviews of program plans, objectives, measurements, and actual data. Additional activity included analysis of experimental system performance and evaluation of the RELAP4 computer code as applied to the experiments

  15. The U.S. Nuclear Regulatory Commission seismic safety research program

    International Nuclear Information System (INIS)

    Kenneally, R.M.; Guzy, D.J.; Murphy, A.J.

    1988-01-01

    The seismic safety research program sponsored by the U.S. Nuclear Regulatory Commission is directed toward improving the evaluation of potential earthquake effects on nuclear power plant operations. The research has been divided into three major program areas: earth sciences, seismic design margins, and fragilities and response. A major thrust of this research is to assess plant behavior for seismic events more severe and less probable than those considered in design. However, there is also research aimed at improving the evaluation of earthquake input and plant response at plant design levels

  16. The enforcement program of the nuclear regulatory commission in the United States

    International Nuclear Information System (INIS)

    Thornburg, H.D.

    1977-01-01

    The enforcement program of the United States Nuclear Regulatory Commission consists of a clearly spelled out, evenly applied program of deterrents which escalate according to the nature of the offense and the past history of the licensee's noncompliances. Ninety-eight percent of all enforcement actions are normally handled by the five Regional offices. Only one percent of noncompliances have been classed as violations where significant safety consequences occurred. A strong and timely enforcement program is essential to insure that licensees fulfill their obligations to protect the public and the environment. (Auth.) [fr

  17. Improved cost-benefit techniques in the US Nuclear Regulatory Commission

    Energy Technology Data Exchange (ETDEWEB)

    Cronin, F.J.; Nesse, R.J.; Vaeth, M.; Wusterbarth, A.R.; Currie, J.W.

    1983-06-01

    The major objective of this report is to help the US Nuclear Regulatory Commission (NRC) in its regulatory mission, particularly with respect to improving the use of cost-benefit analysis and the economic evaluation of resources within the NRC. The objectives of this effort are: (1) to identify current and future NRC requirements (e.g., licensing) for valuing nonmarket goods; (2) to identify, highlight, and present the relevant efforts of selected federal agencies, some with over two decades of experience in valuing nonmarket goods, in this area; and (3) to review methods for valuing nonmarket impacts and to provide estimats of their magnitudes. Recently proposed legislation may result in a requirement for not only more sophisticated valuation analyses, but more extensive applications of these techniques to issues of concern to the NRC. This paper is intended to provide the NRC with information to more efficiently meet such requirements.

  18. U.S. Nuclear Regulatory Commission fiscal year 1980 supplemental budget request

    International Nuclear Information System (INIS)

    1979-01-01

    The proposed supplemental will enable the Nuclear Regulatory Commission to implement necessary additional effort arising from the agency's assessment of the accident at the Three Mile Island Unit 2 facility on March 28, 1979. The TMI accident has had a major impact on all NRC program areas, in particular on research activities and reactor operations. In addition, funds are requested to enhance the agency's Waste Management program to reflect the recommendations of the President's Interagency Review Group on Waste Management. Specific activities involved in this effort will include developing regulatory guidance, developing a licensing review capability and completing a plan for the site characterization review, all in support of the preparation of NRC guidelines necessary to conduct a construction authorization review. FY 1980 appropriations did not include funds to cover these requirements. A detailed analysis across program lines of the supplemental request is contained in this report

  19. Commission for Energy regulation (CRE) - Activity report June 2005; Commission de regulation de l'energie (CRE) - Rapport d'activite juin 2005

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    texts specify the competitive framework); Opening of the gas markets (Opening of the markets in European Union countries, Opening of the French gas market); CRE: regulator of the French gas market (Major obstacles to efficient operation of the French gas market were raised during 2004 and early 2005, Changes in natural gas regulated sales tariffs, Regulated infrastructure tariffs and utilisation conditions, Gaz de France and Total commitments made to the European Commission, Opening of the non-household market on 1 July 2004 and work of the 2004 Gas Working Group (GTG 2004), Audits of the un-bundled accounts of integrated gas operators, CRE's opinions on the regulatory texts, Codes of good conduct for network operators); The work programme (Independence of network operators, Feedback, Preparation of total opening on 1 July 2007, Preparation of the new tariffs for use of regulated gas infrastructures, Comparison of offers of access to storage facilities in Europe, Distribution system operators' investment criteria, Works in the European context); C - Regulation of the electricity market: actors and electricity markets; access to public power networks; the public electric utility in the regulated market; D - The working of CRE: How CRE exercises its jurisdiction (A working method based on responsiveness, consultation and transparency, Disputes solved help to guarantee the right of access to networks for consumers, suppliers and producers, Control and sanction powers); Tools (Professionalism and a multi-disciplinary approach, Some resources remain insufficient to meet the deadline for total opening of the energy markets on 1 July 2007, Independence and budgetary structure); European and international activity (Relations with European Union institutions, Relations with other regulators, Other international relations); E - Glossary, Acronyms, Units and conversions, Index of insets, tables and figures, Council of European Energy Regulators (CEER)

  20. Commission for Energy regulation (CRE) - Activity report June 2005; Commission de regulation de l'energie (CRE) - Rapport d'activite juin 2005

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    European texts specify the competitive framework); Opening of the gas markets (Opening of the markets in European Union countries, Opening of the French gas market); CRE: regulator of the French gas market (Major obstacles to efficient operation of the French gas market were raised during 2004 and early 2005, Changes in natural gas regulated sales tariffs, Regulated infrastructure tariffs and utilisation conditions, Gaz de France and Total commitments made to the European Commission, Opening of the non-household market on 1 July 2004 and work of the 2004 Gas Working Group (GTG 2004), Audits of the un-bundled accounts of integrated gas operators, CRE's opinions on the regulatory texts, Codes of good conduct for network operators); The work programme (Independence of network operators, Feedback, Preparation of total opening on 1 July 2007, Preparation of the new tariffs for use of regulated gas infrastructures, Comparison of offers of access to storage facilities in Europe, Distribution system operators' investment criteria, Works in the European context); C - Regulation of the electricity market: actors and electricity markets; access to public power networks; the public electric utility in the regulated market; D - The working of CRE: How CRE exercises its jurisdiction (A working method based on responsiveness, consultation and transparency, Disputes solved help to guarantee the right of access to networks for consumers, suppliers and producers, Control and sanction powers); Tools (Professionalism and a multi-disciplinary approach, Some resources remain insufficient to meet the deadline for total opening of the energy markets on 1 July 2007, Independence and budgetary structure); European and international activity (Relations with European Union institutions, Relations with other regulators, Other international relations); E - Glossary, Acronyms, Units and conversions, Index of insets, tables and figures, Council of European Energy Regulators (CEER)

  1. Special committee review of the Nuclear Regulatory Commission's severe accident risks report (NUREG--1150)

    International Nuclear Information System (INIS)

    Kouts, H.J.C.; Apostolakis, G.; Kastenberg, W.E.; Birkhofer, E.H.A.; Hoegberg, L.G.; LeSage, L.G.; Rasmussen, N.C.; Teague, H.J.; Taylor, J.J.

    1990-08-01

    In April 1989, the Nuclear Regulatory Commission's (NRC) Office of Nuclear Regulatory Research (RES) published a draft report ''Severe Accident Risks: An Assessment for Five US Nuclear Power Plants,'' NUREG-1150. This report updated, extended and improved upon the information presented in the 1974 ''Reactor Safety Study,'' WASH-1400. Because the information in NUREG-1150 will play a significant role in implementing the NRC's Severe Accident Policy, its quality and credibility are of critical importance. Accordingly, the Commission requested that the RES conduct a peer review of NUREG-1150 to ensure that the methods, safety insights and conclusions presented are appropriate and adequately reflect the current state of knowledge with respect to reactor safety. To this end, RES formed a special committee in June of 1989 under the provisions of the Federal Advisory Committee Act. The Committee, composed of a group of recognized national and international experts in nuclear reactor safety, was charged with preparing a report reflecting their review of NUREG-1150 with respect to the adequacy of the methods, data, analysis and conclusions it set forth. The report which precedes reflects the results of this peer review

  2. 77 FR 4891 - Technical Corrections to Commission Regulations

    Science.gov (United States)

    2012-02-01

    ... 20426. 12. From the Commission's homepage on the Internet, this information is available in the Commission's document management system, eLibrary. The full text of this document is available on eLibrary in...Library, type the docket number excluding the last three digits of this document in the docket number...

  3. Preservation and Implementation of Decommissioning Lessons Learned in the United States Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Rodriguez, Rafael L.

    2008-01-01

    Over the past several years, the United States Nuclear Regulatory Commission (NRC) has actively worked to capture and preserve lessons learned from the decommissioning of nuclear facilities. More recently, NRC has involved industry groups, the Organization of Agreement States (OAS), and the Department of Energy (DOE) in the effort to develop approaches to capture, preserve and disseminate decommissioning lessons learned. This paper discusses the accomplishments of the working group, some lessons learned by the NRC in the recent past, and how NRC will incorporate these lessons learned into its regulatory framework. This should help ensure that the design and operation of current and future nuclear facilities will result in less environmental impact and more efficient decommissioning. In summary, the NRC will continue capturing today's experience in decommissioning so that future facilities can take advantage of lessons learned from today's decommissioning projects. NRC, both individually and collectively with industry groups, OAS, and DOE, is aggressively working on the preservation and implementation of decommissioning lessons learned. The joint effort has helped to ensure the lessons from the whole spectrum of decommissioning facilities (i.e., reactor, fuel cycle, and material facilities) are better understood, thus maximizing the amount of knowledge and best practices obtained from decommissioning activities. Anticipated regulatory activities at the NRC will make sure that the knowledge gained from today's decommissioning projects is preserved and implemented to benefit the nuclear facilities that will decommission in the future

  4. Introductory user's manual for the US Nuclear Regulatory Commission Reactor Safety Research Data Bank

    International Nuclear Information System (INIS)

    Scofield, N.R.; Hardy, H.A.; Laats, E.T.

    1983-02-01

    The United States Nuclear Regulatory Commission (NRC) has established the NRC/Division of Accident Evaluation (DAE) Data Bank Program to collect, store, and make available data from the many domestic and foreign water safety research programs. Local direction of the program is provided by E G and G Idaho, Inc., prime contractor for the Department of Energy (DOE) at the Idaho National Engineering Laboratory (INEL). The NRC/DAE Data Bank Program provides a central computer storage mechanism and access software for data that is to be used by code development and assessment groups in meeting the code and correlation needs of the nuclear industry. The administrative portion of the program provides data entry, documentation, training, and advisory services to users and the NRC. The NRC/DAE Data Bank and the capabilities of the data access software are described

  5. Demonstration of a repository performance assessment capability at the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Codell, R.; Eisenberg, N.; McCartin, T.; Park, J.

    1991-01-01

    In order to better review licensing submittals for a High-Level Waste Repository, the US Nuclear Regulatory Commission staff has expanded and improved its capability to conduct performance assessments. A demonstration of this capability used the limited data from Yucca Mountain, Nevada to investigate a small set of scenario classes. Models of release and transport of radionuclides from a repository via the groundwater and direct release pathways provided preliminary estimates of releases to the accessible environment for a 10,000 year simulation time. Latin hypercube sampling of input parameters was used to express results as distributions and to investigate model sensitivities. This methodology demonstration should not be interpreted as an estimate of performance of the proposed repository at Yucca Mountain, Nevada

  6. Report to the US Nuclear Regulatory Commission on Analysis and Evaluation of Operational Data, 1986

    International Nuclear Information System (INIS)

    1987-05-01

    This annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during calendar year 1986. Comments and observations are provided on operating experience at nuclear power plants and other NRC licensees, including results from selected AEOD studies; summaries of abnormal occurrences involving US nuclear plants; reviews of licensee event reports and their quality, reactor scram experience from 1984 to 1986, engineered safety features actuations, and the trends and patterns analysis program; and assessments of nonreactor and medical misadministration events. In addition, the report provides the year-end status of all recommendations included in AEOD studies, and listings of all AEOD reports issued from 1980 through 1986

  7. Introductory user's manual for the US Nuclear Regulatory Commission Reactor Safety Research Data Bank. Revision 3

    International Nuclear Information System (INIS)

    Hardy, H.A.; Laats, E.T.

    1985-03-01

    The United States Nuclear Regulatory Commission (USNRC) has established the NRC/Division of Accident Evaluation (DAE) Data Bank Program to collect, store, and make available data from the many domestic and foreign water reactor safety research programs. Local direction of the program is provided by EG and G Idaho, Inc., prime contractor for the Department of Energy (DOE) at the Idaho National Engineering Laboratory (INEL). The NRC/DAE Data Bank Program provides a central computer storage mechanism and access software for data to be used by code development and assessment groups in meeting the code correlation needs of the nuclear industry. The administrative portion of the program provides data entry, documentation, training, and advisory services to users and the USNRC. The NRC/DAE Data Bank and the capabilities of the data access software are described in this document

  8. Interim report to the Nuclear Regulatory Commission on radioactive waste classification

    International Nuclear Information System (INIS)

    King, W.C.; Cohen, J.J.

    1977-01-01

    The Lawrence Livermore Laboratory assisted the Nuclear Regulatory Commission in the development of a radioactive waste classification system that will satisfy technical, environmental, and societal concerns. This is an interim report to the NRC on work accomplished to date. It describes a proposed waste-classification system that is based on the final disposition of waste material. The system consists of three classes of radioactive waste. The classification of any radioactive waste will depend primarily on its hazard potential. Other characteristics such as longevity (half-size) will be considered also. The levels of hazard that differentiate the three classes of radioactive waste will be determined by ongoing work. This report describes other work to be completed before a suitable radioactive waste-classificaion system is established

  9. Report to the US Nuclear Regulatory Commission on Analysis and Evaluation of Operational Data, 1987: Nonreactors

    International Nuclear Information System (INIS)

    1988-10-01

    This annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1987. The report is published in two volumes. NUREG-1272, Vol. 2, No. 1, covers Power Reactors and presents an overview of the operating experience of the nuclear power industry, with comments regarding the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year, and summarizes information from Licensee Event Reports, the NRC's Operations Center, and Diagnostic Evaluations. NUREG-1272, Vol. 2, No. 2, covers Nonreactors and presents a review of the nonreactor events and misadministration reports that were reported in 1987 and a brief synopsis of AEOD studies published in 1987. Each volume contains a list of the AEOD reports issued for 1980-1987

  10. Yellin's review of the Nuclear Regulatory Commission's Reactor Safety Study: comment

    International Nuclear Information System (INIS)

    Wilson, R.

    1976-01-01

    Joel Yellin (Bell J. Economics, Vol. 7, No. 1 (Spr. 1976)) reviewed the Reactor Safety Study (WASH-1400, or Rasmussen Report) published by the Nuclear Regulatory Commission and makes several criticisms. Wilson finds that some of these criticisms are much overstated, while others, although valid, are mainly criticisms of presentation. To be useful for public policy, reactor risks--and indeed all nuclear risks--must be compared with other risks society faces. Wilson feels that the Rasmussen Report is weak in these comparisons, primarily because there exist few estimates of risk in other places, but that the comparisons he does make indeed confirm that the risk is smaller than Yellin suggests. 20 references

  11. Federal Trade Commission's authority to regulate marketing to children: deceptive vs. unfair rulemaking.

    Science.gov (United States)

    Pomeranz, Jennifer L

    2011-01-01

    Food and beverage marketing directed at children is of increasing concern to the public health and legal communities. The new administration at the Federal Trade Commission and abundant science on the topic make it a particularly opportune time for the government to reconsider regulating marketing directed at youth. This Article analyzes the Commission's authority to regulate food and beverage marketing directed at children under its jurisdiction over unfair and deceptive acts and practices to determine which avenue is most viable. The author finds that the Federal Trade Commission has the authority to regulate deceptive marketing practices directed at vulnerable populations. Although the Commission can issue individual orders, its remedial power to initiate rules would better address the pervasiveness of modern marketing practices. The Commission does not currently have the power to regulate unfair marketing to children; however, even if Congress reinstated this authority, the Commission's authority over deceptive marketing may be preferable to regulate these practices. Deceptive communications are not protected by the First Amendment and the deceptive standard matches the science associated with marketing to children. The Federal Trade Commission has the authority to initiate rulemaking in the realm of food and beverage marketing to children as deceptive communications in interstate commerce, in violation of the Federal Trade Commission Act. However, to effectuate this process, Congress would need to grant the Commission the authority to do so under the Administrative Procedures Act.

  12. Regulatory control, nuclear safety regulation and waste management in Spain

    International Nuclear Information System (INIS)

    Martin, A.

    2000-01-01

    This article presents the challenges that faces the spanish regulatory authority. The deregulation of electricity industry imposes severe changes in nuclear power economics and forces nuclear power to compete with other sources of electricity. A pressure is perceived for regulatory effectiveness primarily since the cost of regulation is a component of the cost of the product. This effectiveness gain in regulatory control will be reached through systematic strategic analysis, formulation and implementation. The regulatory aspects of plant life extension and of waste management are examined

  13. Site-specific parameter values for the Nuclear Regulatory Commission's food pathway dose model

    International Nuclear Information System (INIS)

    Hamby, D.M.

    1992-01-01

    Routine operations at the Savannah River Site (SRS) in Western South Carolina result in radionuclide releases to the atmosphere and to the Savannah River. The resulting radiation doses to the off-site maximum individual and the off-site population within 80 km of the SRS are estimated on a yearly basis. These estimates are currently generated using dose models prescribed for the commercial nuclear power industry by the Nuclear Regulatory Commission (NRC). The NRC provides default values for dose-model parameters for facilities without resources to develop site-specific values. A survey of land- and water-use characteristics for the Savannah River area has been conducted to determine site-specific values for water recreation, consumption, and agricultural parameters used in the NRC Regulatory Guide 1.109 (1977) dosimetric models. These site parameters include local characteristics of meat, milk, and vegetable production; recreational and commercial activities on the Savannah River; and meat, milk, vegetable, and seafood consumption rates. This paper describes how parameter data were obtained at the Savannah River Site and the impacts of such data on off-site dose. Dose estimates using site-specific parameter values are compared to estimates using the NRC default values

  14. Commission de regulation de l'energie. Activity report june 2007

    International Nuclear Information System (INIS)

    2007-06-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2007 activity report of CRE. Content: A - Towards a single European energy market: Birth of a single European energy market (Origins of Europe of Energy, Emergence of a European energy policy); Main European Community guiding lines (European governance as regards energy, Guiding principles for the internal energy market); European Community activities (European Commission reports, Electricity and gas Regional Initiatives); Organisation and coordination of European regulators (Joint organisation of European regulators, CRE's relations with European Community institutions); CRE's European activities (Regional integration of gas markets, Regional integration of electricity markets, Operation of the European interconnected electricity grid and security of supply, CRE's other European activities); B - CRE action at national level: Grids/networks and infrastructures (General information, Electricity grids, Regulation of gas networks and infrastructures); Markets (Changes in the regulatory and legislative contexts of electricity and natural gas markets, Electricity markets

  15. Arrangement between the US Nuclear Regulatory Commission (USNRC) and the Belgian Government for Exchange of Technical Information in Regulatory Matters and in Cooperation in Safety Research and in Standards Development

    International Nuclear Information System (INIS)

    1978-01-01

    This Arrangement was concluded on 6 June 1978 between the United States Nuclear Regulatory Commission and the Belgian Government for exchange of technical information in regulatory matters and in co-operation in safety research and in standards development. Both Parties agree to exchange, as available, technical information related to the regulation of safety and the environmental impact of designated nuclear energy facilities and to safety research of designated types of nuclear facilities. As regards co-operation in safety research, the execution of joint programmes and projects under which activities are divided between the two Parties will be agreed on a case by case basis. The Parties further agree to co-operate in the development of regulatory standards applicable to the designated nuclear facilities. The Arrangement is valid for 5 years and may be extended. (NEA) [fr

  16. Training related research and development conducted at Oak Ridge National Laboratory for the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Haas, P.M.

    1985-01-01

    For a number of years Oak Ridge National Laboratory (ORNL) has conducted a sizeable program of human factors research and development in support of the Office of Nuclear Regulatory Research of the US Nuclear Regulatory Commission (NRC). The history of this effort has in many ways paralleled the growth of human factors R and D throughout the nuclear industry and the program has contributed to advances in the industry as well as to NRC regulatory and research programs. This paper reviews the major projects and products of the program relevant to training and concludes with an identification of future R and D needs

  17. 10 CFR Appendix A to Part 5 - List of Federal Financial Assistance Administered by the Nuclear Regulatory Commission to Which...

    Science.gov (United States)

    2010-01-01

    ... COMMISSION NONDISCRIMINATION ON THE BASIS OF SEX IN EDUCATION PROGRAMS OR ACTIVITIES RECEIVING FEDERAL... regulatory programs and related matters at NRC facilities and offices, or other locations. (b) Orientations... recovery, to receive orientation and on-the-job instruction at NRC facilities and offices, or other...

  18. Review and evaluation of the Nuclear Regulatory Commission safety research program for Fiscal Year 1983. Report to the Congress

    International Nuclear Information System (INIS)

    1982-02-01

    Public Law 95-209 includes a requirement that the Advisory Committee on Reactor Safeguards submit an annual report to Congress on the safety research program of the Nuclear Regulatory Commission. This report presents the results of the ACRS review and evaluation of the NRC safety research program for Fiscal Year 1983. The report contains a number of comments and recommendations

  19. 76 FR 31997 - Final Memorandum of Understanding Between the U.S. Nuclear Regulatory Commission and the U.S...

    Science.gov (United States)

    2011-06-02

    ... responsibility between the parties, based on their legal authorities, for the security of high-risk chemical.... Nuclear Regulatory Commission and the U.S. Department of Homeland Security on Chemical Facility Anti... INFORMATION CONTACT: R. Clyde Ragland, Project Manager (Security), Fuel Cycle and Transportation Security...

  20. Improving nuclear regulation. Compilation of Nea regulatory guidance booklets

    International Nuclear Information System (INIS)

    2009-01-01

    A common theme throughout the series of NEA regulatory guidance reports, or 'green booklets', is the premise that the fundamental objective of all nuclear safety regulatory bodies is to ensure that nuclear facilities are operated at all times and later decommissioned in an acceptably safe manner. In meeting this objective the regulator must keep in mind that it is the operator that has responsibility for safely operating a nuclear facility; the role of the regulator is to oversee the operator's activities as related to assuming that responsibility. For the first time, the full series of these reports have been brought together in one edition. As such, it is intended to serve as a knowledge management tool both for current regulators and the younger generation of nuclear experts entering the regulatory field. While the audience for this publication is primarily nuclear regulators, the information and ideas may also be of interest to nuclear operators, other nuclear industry organisations and the general public. (author)

  1. 77 FR 60619 - Removal of Obsolete Regulation: Use of the Centennial of Flight Commission Name

    Science.gov (United States)

    2012-10-04

    ... Removal of Obsolete Regulation: Use of the Centennial of Flight Commission Name AGENCY: National... section 1204. 506 entitled ``Delegation of Authority to License the Use of the Centennial of Flight Commission Name.'' Section 506, Delegation of Authority to License the Use of the Centennial of Flight...

  2. A compilation of reports of the Advisory Committee on Reactor Safeguards, 1997 annual, U.S. Nuclear Regulatory Commission. Volume 19

    International Nuclear Information System (INIS)

    1998-04-01

    This compilation contains 67 ACRS reports submitted to the Commission, or to the Executive Director for Operations, during calendar year 1997. It also includes a report to the Congress on the NRC Safety Research Program. Specific topics include: (1) advanced reactor designs, (2) emergency core cooling systems, (3) fire protection, (4) generic letters and issues, (5) human factors, (6) instrumentation, control and protection systems, (7) materials engineering, (8) probabilistic risk assessment, (9) regulatory guides and procedures, rules, regulations, and (10) safety research, philosophy, technology and criteria

  3. A compilation of reports of the Advisory Committee on Reactor Safeguards, 1997 annual, U.S. Nuclear Regulatory Commission. Volume 19

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-04-01

    This compilation contains 67 ACRS reports submitted to the Commission, or to the Executive Director for Operations, during calendar year 1997. It also includes a report to the Congress on the NRC Safety Research Program. Specific topics include: (1) advanced reactor designs, (2) emergency core cooling systems, (3) fire protection, (4) generic letters and issues, (5) human factors, (6) instrumentation, control and protection systems, (7) materials engineering, (8) probabilistic risk assessment, (9) regulatory guides and procedures, rules, regulations, and (10) safety research, philosophy, technology and criteria.

  4. 25 CFR 518.10 - Under what circumstances may the Commission remove a certificate of self-regulation?

    Science.gov (United States)

    2010-04-01

    ... certificate of self-regulation? 518.10 Section 518.10 Indians NATIONAL INDIAN GAMING COMMISSION, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS SELF REGULATION OF CLASS II GAMING § 518.10 Under what circumstances may the Commission remove a certificate of self-regulation? The Commission may, after an opportunity...

  5. The Cold War legacy of regulatory risk analysis: The Atomic Energy Commission and radiation safety

    Science.gov (United States)

    Boland, Joseph B.

    From its inception in 1946 the Atomic Energy Commission pioneered the use of risk analysis as a mode of regulatory rationality and political rhetoric, yet historical treatments of risk analysis nearly always overlook the important role it played in the administration of atomic energy during the early Cold War. How this absence from history has been achieved and why it characterizes most historical accounts are the subjects of Chapter II. From there, this study goes on to develop the thesis that the advent of the atomic bomb was a world-shattering event that forced the Truman administration to choose between two novel alternatives: (1) movement towards global governance based initially on cooperative control of atomic energy or (2) unsparing pursuit of nuclear superiority. I refer to these as nuclear internationalism and nuclear nationalism, respectively. Each defined a social risk hierarchy. With the triumph of nuclear nationalism, nuclear annihilation was designated the greatest risk and a strong nuclear defense the primary means of prevention. The AEC's mission in the 1950s consisted of the rapid development of a nuclear arsenal, continual improvements in weapons technologies, and the promotion of nuclear power. The agency developed a risk-based regulatory framework through its dominant position within the National Committee on Radiation Protection. It embraced a technocratic model of risk analysis whose articulation and application it controlled, largely in secret. It used this to undergird a public rhetoric of reassurance and risk minimization. In practice, safety officials adjusted exposure levels within often wide parameters and with considerable fluidity in order to prevent safety concerns from interfering with operations. Secrecy, the political climate of the time, and a lack of accountability enabled the agency to meld technical assessments with social value judgments in a manner reflective of nuclear nationalism's risk hierarchy. In the late fifties

  6. U.S. Nuclear Regulatory Commission accountability report, fiscal year 1995. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-05-01

    The US Nuclear Regulatory Commission (NRC) is one of six Federal agencies participating in a pilot project to streamline financial management reporting. The goal of this pilot is to consolidate performance-related reporting into a single accountability report. The project, which is being carried out under the guidance of the Chief Financial Officers Council, was undertaken in accordance with the Government Management Reform Act (GMRA) of 1994. The GMRA permits the streamlining of financial management reports in consultation with the appropriate Congressional Committees through a liaison in the US Office of Management and Budget (OMB). The results of the pilot project will determine the method to be used for reporting financial management information for fiscal year (FY) 1996. This report consolidates the information previously reported in the following documents: (1) the NRC`s annual financial statement required by the Chief Financial Officers Act of 1990; (2) the Chairman`s annual report to the President and the Congress, required by the Federal Managers` Financial Integrity Act of 1982; (3) the Chairman`s semiannual report to the Congress on management decisions and final actions on Office of Inspector General audit recommendations, required by the Inspector General Act of 1978, as amended. This report also includes performance measures, as required by the Chief Financial Officers Act of 1990.

  7. A materials engineering view of license renewal at the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Banic, M.

    1999-01-01

    This paper discusses the treatment of license renewal at the US Nuclear Regulatory Commission (NRC) with emphasis on the review process by the staff of the Materials and Chemical Engineering Branch (EMCB). The paper covers the rules governing license renewal, the applications received, the schedule, the approach, and the technical issues. The NRC has a tight schedule of 30-36 months to renew a license. To date, Baltimore Gas and Electric (BG and E) and Duke Power have applied for license renewal. Expecting more applicants, the staff has taken steps to address the public's concern that the effects of aging will be adequately managed and the industry's concern that the reviews will be timely, efficient, and uniform. These steps include identifying aging effects and making the results available in a report and computerized database, approving topical reports and aging management programs for generic use, and reviewing aging management programs according to specific criteria. Materials Engineering staff have a major role because many of the aging issues are materials related. (author)

  8. U.S. Nuclear Regulatory Commission accountability report, fiscal year 1995. Volume 1

    International Nuclear Information System (INIS)

    1996-01-01

    The US Nuclear Regulatory Commission (NRC) is one of six Federal agencies participating in a pilot project to streamline financial management reporting. The goal of this pilot is to consolidate performance-related reporting into a single accountability report. The project, which is being carried out under the guidance of the Chief Financial Officers Council, was undertaken in accordance with the Government Management Reform Act (GMRA) of 1994. The GMRA permits the streamlining of financial management reports in consultation with the appropriate Congressional Committees through a liaison in the US Office of Management and Budget (OMB). The results of the pilot project will determine the method to be used for reporting financial management information for fiscal year (FY) 1996. This report consolidates the information previously reported in the following documents: (1) the NRC's annual financial statement required by the Chief Financial Officers Act of 1990; (2) the Chairman's annual report to the President and the Congress, required by the Federal Managers' Financial Integrity Act of 1982; (3) the Chairman's semiannual report to the Congress on management decisions and final actions on Office of Inspector General audit recommendations, required by the Inspector General Act of 1978, as amended. This report also includes performance measures, as required by the Chief Financial Officers Act of 1990

  9. NRC [Nuclear Regulatory Commission] perspective of software QA [quality assurance] in the nuclear history

    International Nuclear Information System (INIS)

    Weiss, S.H.

    1988-01-01

    Computer technology has been a part of the nuclear industry since its inception. However, it is only recently that computers have been integrated into reactor operations. During the early history of commercial nuclear power in the United States, the US Nuclear Regulatory Commission (NRC) discouraged the use of digital computers for real-time control and monitoring of nuclear power plant operation. At the time, this position was justified since software engineering was in its infancy, and horror stories on computer crashes were plentiful. Since the advent of microprocessors and inexpensive computer memories, significant advances have been made in fault-tolerant computer architecture that have resulted in highly reliable, durable computer systems. The NRC's requirement for safety parameter display system (SPDS) stemmed form the results of studies and investigations conducted on the Three Mile Island Unit 2 (TMI-2) accident. An NRC contractor has prepared a handbook of software QA techniques applicable to the nuclear industry, published as NUREG/CR-4640 in August 1987. Currently, the NRC is considering development of an inspection program covering software QA. Future efforts may address verification and validation as applied to expert systems and artificial intelligence programs

  10. Indexes to Nuclear Regulatory Commission issuances, July--December 1996. Volume 44, Index 2

    International Nuclear Information System (INIS)

    1997-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decision on Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by apellants; legal citations (cases, regulations, and statutes); name of facility, docket number; subject matter of issues and/or rulings; type of hearing (operating license, operating license amendment, etc.); type of issuance (memorandum, order, decision, etc.)

  11. Indexes to Nuclear Regulatory Commission issuances, January 19, 1975 through December 31, 1979

    International Nuclear Information System (INIS)

    1981-03-01

    The document contains indexes for adjudicatory decisions of the Commission (CLI), the Atomic Safety and Licensing Appeal Board (ALAB), the Atomic Safety and Licensing Board (LBP), the Administrative Law Judge (ALJ), the Directors Denials (DD), and the Denials of Petitions for Rulemaking (DPRM). The Directors Denials and Denials of Petition for Rulemaking are new categories, added in 1979. Information elements common to the cases heard and ruled upon are: Case name (owners of facility); Name of facility, Docket number; Type of hearing (for construction permit, operating license, etc.); Issues raised by appellants; Issuance number; Type of issuance (memorandum, order, decision, etc.); Issuance pagination; Legal citations (cases, regulations, and statutes); and Subject matter of issues and/or rulings. These information elements are displayed in one or more of five separate formats arranged as follows: Case name index; Digests and headers; Legal citation index; Subject index; and Facility index

  12. Indexes to Nuclear Regulatory Commission issuances, July--September 1995. Volume 42, Index 1

    International Nuclear Information System (INIS)

    1995-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by appellants; legal citations (cases, regulations, and statutes); name of facility, docket number; subject matter of issues and/or rulings; type of hearing (for construction permit, operating license, etc.); and type of issuance (memorandum, order, decision, etc.)

  13. Indexes to Nuclear Regulatory Commission issuances, July--December 1994. Volume 40, Index 2

    International Nuclear Information System (INIS)

    1994-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board panel (LBP), the Administrative Law Judges, the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full text reference (volume and pagination); Issuance number; Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (for construction permit, operating license, etc.); Type of issuance (memorandum, order, decision, etc.)

  14. Indexes to Nuclear Regulatory Commission issuances: July--September 1994. Volume 40, Index 1

    International Nuclear Information System (INIS)

    1994-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decision (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility), full text reference (volume and pagination), issuance number, issues raised by apellants, legal citations (cases, regulations, and statutes), name of facility, docket number, subject matter of issues and/or rulings, type of hearing (for construction permit, operating license, etc.), type of issuance (Memorandum, order, decision, etc.)

  15. Indexes to Nuclear Regulatory Commission issuances, July--December 1996. Volume 44, Index 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Decision on Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by apellants; legal citations (cases, regulations, and statutes); name of facility, docket number; subject matter of issues and/or rulings; type of hearing (operating license, operating license amendment, etc.); type of issuance (memorandum, order, decision, etc.).

  16. Indexes to Nuclear Regulatory Commission issuances, January--March 1995. Volume 41, Index 1

    International Nuclear Information System (INIS)

    1995-06-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility); full text reference (volume and pagination); issuance number; issues raised by appellants; legal citations (cases, regulations, and statutes); name of facility, docket number; subject matter of issues and/or rulings; type of hearing (for construction permit, operating license, etc.); and type of issuance (memorandum, order, decision, etc.)

  17. Indexes to Nuclear Regulatory Commission issuances, January-June 1983. Volume 17, Index 2

    International Nuclear Information System (INIS)

    1983-10-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owners of facility); full text reference (volume and pagination); issuance number; issues raised by appellants; legal citations (cases, regulations, and statutes); name of facility, Docket number; subject matter of issues and/or rulings; type of hearing (for construction permit, operating license, etc.); and type of issuance (memorandum, order, decision, etc.)

  18. Indexes to Nuclear Regulatory Commission issuances, July--December 1994. Volume 40, Index 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-12-31

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board panel (LBP), the Administrative Law Judges, the Directors` Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: Case name (owner(s) of facility); Full text reference (volume and pagination); Issuance number; Issues raised by appellants; Legal citations (cases, regulations, and statutes); Name of facility, Docket number; Subject matter of issues and/or rulings; Type of hearing (for construction permit, operating license, etc.); Type of issuance (memorandum, order, decision, etc.).

  19. Indexes to Nuclear Regulatory Commission issuances: July--September 1994. Volume 40, Index 1

    Energy Technology Data Exchange (ETDEWEB)

    1994-12-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors` Decision (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements common to the cases heard and ruled upon are: case name (owner(s) of facility), full text reference (volume and pagination), issuance number, issues raised by apellants, legal citations (cases, regulations, and statutes), name of facility, docket number, subject matter of issues and/or rulings, type of hearing (for construction permit, operating license, etc.), type of issuance (Memorandum, order, decision, etc.).

  20. Report to the Nuclear Regulatory Commission from the staff panel on the Commission's determination of an Extraordinary Nuclear Occurrence (ENO)

    International Nuclear Information System (INIS)

    1980-01-01

    The Panel finds that the first criterion, pertaining to whether the accident caused a discharge of radioactive material or levels of radiation offsite as defined in 10 CFR 140.84, has not been met. It further finds that there is presently insufficient information to support any definitive finding as to whether or not the second criterion, relating to damage to persons or property offsite as defined in 10 CFR 140.85, has been met. Since the Panel has not found that both criteria have been met, it recommends that the Commission determine that the accident at Three Mile Island did not constitute an extraordinary nuclear occurrence

  1. Report to the Nuclear Regulatory Commission from the staff panel on the Commission's determination of an Extraordinary Nuclear Occurrence (ENO)

    Energy Technology Data Exchange (ETDEWEB)

    None

    1980-01-01

    The Panel finds that the first criterion, pertaining to whether the accident caused a discharge of radioactive material or levels of radiation offsite as defined in 10 CFR 140.84, has not been met. It further finds that there is presently insufficient information to support any definitive finding as to whether or not the second criterion, relating to damage to persons or property offsite as defined in 10 CFR 140.85, has been met. Since the Panel has not found that both criteria have been met, it recommends that the Commission determine that the accident at Three Mile Island did not constitute an extraordinary nuclear occurrence.

  2. Energy regulation at EU level. The role of the European Commission and ACER in the context of REMIT

    International Nuclear Information System (INIS)

    Konar, Selma

    2015-01-01

    The regulatory act of promulgating REMIT, the Regulation on Wholesale Market Integrity and Transparency, has highlighted the commanding position of both the European Commission and ACER, the Agency for the Cooperation of Energy Regulators, in the regulation of energy affairs in the European Union. Furthermore it has led to major changes in how surveillance is organized at the national level. The first part of this publication is dedicated to the organization of market surveillance following the promulgation of REMIT. It depicts the tasks of the European Commission and ACER in this context. The Regulation has accorded the authorities a central role in managing the European Union's responsibilities with regard to energy wholesale trade. The act of delegating such far-reaching competence to the authorities deserves careful review however. The article shows how, given ACER's lack of practical experience in market surveillance, as well as its lack of human resources, the task of surveilling the European energy wholesale market confronts the agency with a significant challenge. How successfully the EU energy agency will master this challenge will depend on a number of different factors. Stringent requirements will be needed for the data registration offices in order to ensure optimal data processing. National authorities and supervisory bodies should be made to participate in the data monitoring process. ACER's efficiency in surveilling the market will furthermore depend decisively on its IT infrastructure.

  3. U.S. Department of Energy & Nuclear Regulatory Commission Advanced Fuel Cycle Research & Development Seminar Series FY 2007 & 2008

    Energy Technology Data Exchange (ETDEWEB)

    Grandy, Christopher [Argonne National Lab. (ANL), Argonne, IL (United States)

    2008-08-01

    In fiscal year 2007, the Advanced Burner Reactor project initiated an educational seminar series for the Department of Energy (DOE) and Nuclear Regulatory Commission (NRC) personnel on various aspects of fast reactor fuel cycle closure technologies. This important work was initiated to inform DOE and NRC personnel on initial details of sodium-cooled fast reactor, separations, waste form, and safeguard technologies being considered for the Advanced Fuel Cycle Research and Development program, and to learn the important lesson from the licensing process for the Clinch River Breeder Reactor Plant that educating the NRC staff early in the regulatory process is very important and critical to a project success.

  4. Towards new regulatory concepts for the regulation of audiovisual media

    NARCIS (Netherlands)

    Schulz, W.; van Eijk, N.

    2016-01-01

    European media regulation currently faces several challenges: technology, media and markets have become convergent, while – at the same time – the situations in the individual member states differ in respect of media use, the usage of end devices as well as regulatory aims and frameworks. These

  5. Methods for ensuring compliance with regulatory requirements: regulators and operators

    International Nuclear Information System (INIS)

    Fleischmann, A.W.

    1989-01-01

    Some of the methods of ensuring compliance with regulatory requirements contained in various radiation protection documents such as Regulations, ICRP Recommendations etc. are considered. These include radiation safety officers and radiation safety committees, personnel monitoring services, dissemination of information, inspection services and legislative power of enforcement. Difficulties in ensuring compliance include outmoded legislation, financial and personnel constraints

  6. International certification of nuclear power reactors design. A proposal from the U.S. NRC (Nuclear Regulatory Commission)

    International Nuclear Information System (INIS)

    Felizia, Eduardo R.

    2006-01-01

    The proposal foundations of the Nuclear Regulatory Commission Board Chairman are briefly described, which were enunciated at a meeting on Fourth Generation Reactors (Washington, March 2005). This proposal is analyzed mainly from the point of view of its consequences in third countries buyers of nuclear technology. The analysis is complemented by descriptions of the current process of the NRC design certification and of Third and Fourth Generation Reactors. (author) [es

  7. Commission de regulation de l'energie. activity report 2015 - Reference document, 15 years of regulation

    International Nuclear Information System (INIS)

    2016-06-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the June 2015 activity report of CRE. The report comes in two volumes. The first provides comprehensive details of the CRE's activities in 2015, while the second highlights just how far the CRE has come since it was established in 2000. Content: A - Message from the Board; B - The Energy Regulatory Commission: The organisation and missions of CRE (organisation of CRE, missions of CRE, CRE and other institutional actors, CRE consultation and transparency, Human resources and budgetary means; CRE playing a role at the heart of Europe (CRE within ACER and CEER, Cooperation with other regulators; C - CRE and the markets: As part of its monitoring task, CRE assesses the wholesale market (The wholesale energy market has been affected by the significant fall in prices, The European regulation (REMIT) is a legal tool for monitoring the markets at European level, The capacity mechanism has been defined to promote the security of supply at national level); The retail market was growing fast in 2015 (The implementation of the NOME law provides a new legal framework for regulated tariffs

  8. 78 FR 8417 - 2006 Biennial Regulatory Review-Revision of the Commission's Rules

    Science.gov (United States)

    2013-02-06

    ... ordered that the Commission's Consumer and Governmental Affairs Bureau, Reference Information Center shall... of orbital planes. (i) * * * (2) A demonstration that the proposed system is capable of providing...

  9. Overview of the Nuclear Regulatory Commission Low-Level Waste Management Program

    International Nuclear Information System (INIS)

    Bishop, W.P.; Bell, M.J.; Dragonette, K.S.; Adam, J.

    1979-01-01

    Environmental impacts from Table S-3 of 10 CFR Part 51 are included in individual environmental impact statements for LWR's. In response to a U.S. Court of Appeals finding of inadequate documentation to support Table S-3, ''Environmental Survey of Reprocessing and Waste Management Portions of the LWR Fuel Cycle'' (NUREG-0116) and ''Public Comments and Task Force Responses Regarding Environmental Survey of the Reprocessing and Waste Portions of the LWR Fuel Cycle'' (NUREG-0216) were published. As a result of these in-house studies, an interim rule revising Table S-3 has been published. These documents include discussions of shallow land burial of low-level waste, past experiences and sensitivity calculations estimating potential dose commitments from the groundwater migration of the wastes. An NRC task force report (NUREG-0217) examining the Federal and Agreement State programs for regulating commercial low-level waste disposal recommends increasing the federal role in low-level waste disposal. The need to investigate alternatives to shallow land burial is identified. The NRC is developing a radioactive waste management program which includes a plan for the implementation of the task force recommendations, the development of environmental impacts for low-level waste disposal, development of standards and criteria, and the establishment of a regulatory framework and licensing procedures for the disposal of low-level radioactive waste

  10. Advancing towards commonsense regulation of mixed waste: Regulatory update

    International Nuclear Information System (INIS)

    Porter, C.L.

    1996-01-01

    The author previously presented the basis for regulating mixed waste according to the primary hazard (either chemical or radiological) in order to avoid the inefficient practice of open-quotes dual regulationclose quotes of mixed waste. In addition to covering the technical basis, recommendations were made on how to capitalize upon a window of opportunity for implementation of a open-quotes primary hazards approachclose quotes. Some of those recommendations have been pursued and the resulting advances on the regulatory front are exciting. This paper chronicles those pursuits, presents in capsule form the massive amount of data assembled, and summarizes the changing regulatory framework. The data supports the premise that disposal of stabilized mixed waste in a low-level radioactive waste (LLW) disposal facility is protective of human health and the environment. Based on that premise, proposed regulatory changes, if finalized, will eliminate much of the open-quotes dual regulationclose quotes of mixed waste

  11. Commission de regulation de l'energie. Activity report june 2006

    International Nuclear Information System (INIS)

    2006-06-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the 2006 activity report of CRE. Content: A - Opening of the electricity and natural gas markets to household consumers on 1 July 2007: CRE at the service of eligible customers (Information for eligible customers, Improved knowledge of non-household customers); Monitoring of the non-discrimination, transparency and independence of system operators (Drafting and distribution of codes of good conduct for system operators, The necessary improvement of system operator independence); Preparing the practical methods of opening: GTE 2007 and GTG 2007 (The necessary simplification of relations between operators and customers, Achieving a greater level of consumer information and protection, The clearly defined stages of the 'customer pathway', Profiling and settlement mechanisms: turning experience feedback from 2004 to good account); Persisting uncertainties and hurdles (The need for a suitable regulatory and legislative platform, Hurdles to the opening of the household market); B - Regulation of the natural gas market: The gas market in the European context (Increasing weight of

  12. US Nuclear Regulatory Commission organization charts and functional statements. Revision 17

    International Nuclear Information System (INIS)

    1994-01-01

    This document is a detailed organizational chart detailing the different staffing and board offices. They include: the commission, the several committees and boards, the commission staff offices, the office of the Inspector General, the executive director for operations and staff offices, and the regional and program offices

  13. Optimising implementation of reforms to better prevent and respond to child sexual abuse in institutions: Insights from public health, regulatory theory, and Australia's Royal Commission.

    Science.gov (United States)

    Mathews, Ben

    2017-12-01

    The Australian Royal Commission Into Institutional Responses to Child Sexual Abuse has identified multiple systemic failures to protect children in government and non-government organizations providing educational, religious, welfare, sporting, cultural, arts and recreational activities. Its recommendations for reform will aim to ensure organizations adopt more effective and ethical measures to prevent, identify and respond to child sexual abuse. However, apart from the question of what measures institutions should adopt, an under-explored question is how to implement and regulate those measures. Major challenges confronting reform include the diversity of organizations providing services to children; organizational resistance; and the need for effective oversight. Failure to adopt theoretically sound strategies to overcome implementation barriers will jeopardize reform and compromise reduction of institutional child sexual abuse. This article first explains the nature of the Royal Commission, and focuses on key findings from case studies and data analysis. It then analyzes public health theory and regulatory theory to present a novel analysis of theoretically justified approaches to the implementation of measures to prevent, identify and respond to CSA, while isolating challenges to implementation. The article reviews literature on challenges to reform and compliance, and on prevention of institutional CSA and situational crime prevention, to identify measures which have attracted emerging consensus as recommended practice. Finally, it applies its novel integration of regulatory theory and public health theory to the context of CSA in institutional contexts, to develop a theoretical basis for a model of implementation and regulation, and to indicate the nature and functions of a regulatory body for this context. Copyright © 2017 The Author. Published by Elsevier Ltd.. All rights reserved.

  14. Regulation of Telecommunications: The Choice Between Market and Regulatory Failures

    Directory of Open Access Journals (Sweden)

    Dmitrii Trubnikov

    2017-04-01

    Full Text Available Purpose – The paper examines the main regulatory frameworks of the telecommunications industry through the concept of market failure and analyses how and why the policy often leads to undesirable outcomes that might be considered as regulatory failure. Methodology/approach/design – The research uses the EU regulatory framework for electronic communications as a base for the analysis of the main policy objectives through the prism of the market failure theory with an eye to the interests of the main market players in the telecommunications markets. Findings – About any aspect of regulation allows to find ways to create opportunities for some groups of the industry and stifle activity of others. Despite the theory of market failure provides reasonable justifications for regulation of telecommunications markets, it is possible to argue that many of these problems are mainly the consequence of the policy and could be better solved by market mechanisms. Originality/value – The results of the research allow to look at the problems of telecommunications development and issues of the high level of concentration of the telecommunications markets as regulatory formed problems rather than consequences of the inherited industry’s characteristics.

  15. Review report: safety and reliability issues on digital instrumentation and control systems in nuclear power plants and United States Nuclear Regulatory Commission`s dispositions

    Energy Technology Data Exchange (ETDEWEB)

    Watanabe, Norio; Suzudo, Tomoaki [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    1998-09-01

    Recently, digital instrumentation and control (I and C) systems have been applied to nuclear power plants (NPPs) in various countries. Introduction of digital I and C systems, however, raises special issues on design, implementation, safety and licensing. Since FY 1997, the Japan Atomic Energy Research Institute (JAERI) has been carrying out a project, Study on Reliability of Digital I and C Systems, which includes extensive reviews of design approaches, technical standards, regulatory processes, especially, in the United States. This report summarizes the results from the study of National Research Council (NRC) and the U.S. Nuclear Regulatory Commission`s (USNRC`s) responses to the recommendations made by the NRC`s study. That study identified six technical key issues (system aspects of digital I and C technology, software quality assurance, common-mode software failure potential, safety and reliability assessment methods, human factors and man-machine interface, dedication of commercial off-the-shelf hardware and software) and two strategic key issues (case-by-case licensing process, adequacy of technical infrastructure) that arise from the introduction of digital I and C technology and then, made recommendations to the USNRC for coping with digital I and C applications. The USNRC responded to each recommendation and showed their own dispositions in which the USNRC agreed with most of the recommendations. In Japan, it is expected that introduction of digital I and C technology is inevitable in NPPs because the vendors are gradually discontinuing support and stocking of analog components. To cope with such situations, there is a need to develop and update the standards and guidelines applicable to digital I and C technology. The key issues and the USNRC`s dispositions provided in this report is believed to be useful for developing and updating them. (J.P.N.)

  16. 77 FR 33253 - Regulatory Guide 8.33, Quality Management Program

    Science.gov (United States)

    2012-06-05

    ... NUCLEAR REGULATORY COMMISSION [NRC-2012-0126] Regulatory Guide 8.33, Quality Management Program... Regulatory Commission (NRC or Commission) is withdrawing Regulatory Guide (RG) 8.33, ``Quality Management... Quality Management Program was deleted from the regulations as part of an overall revision in 2002 of the...

  17. Nuclear Regulatory Commission Issuances. Volume 42, No. 1, Pages 1--45

    International Nuclear Information System (INIS)

    1995-07-01

    This report includes the issuances received during the specified period from the Commission (CLI), the Atomic safety and Licensing Boards (LBP), the Administrative Law Judges (ALJ), the Directors' Decisions (DD), and the Decisions on Petitions for Rulemaking (DPRM)

  18. 76 FR 1335 - Supplemental Standards of Ethical Conduct for Employees of the Federal Energy Regulatory Commission

    Science.gov (United States)

    2011-01-10

    ... following: (1) Natural gas companies; (2) Interstate oil pipelines; (3) Hydroelectric licensees or exemptees... programs and processes. These rules were designed to prevent Commission employees from taking actions that...

  19. Future directions for the US Nuclear Regulatory Commission's low-level waste management program

    International Nuclear Information System (INIS)

    Starmer, R.J.

    1986-01-01

    The Low-Level Radioactive Waste Policy Act envisioned that all states would be able to dispose of commercial low-level waste generated within their borders by 1986, either individually or through interstate compacts. Based on the current status of state and compact efforts, it is clear that no new disposal sites will be available by 1986 or for some period thereafter. In the short-term, there is uncertainty that the existing disposal sites will remain open after January 1, 1986, or if restrictions will apply after that time. If restrictions occur, storage, treatment or even curtailed generation may result for individual waste producers. Other uncertainties clouding implementation of the Policy Act include the final configuration of regional compacts - in the northeast in particular - clear assignment of responsibility for disposal of classes of waste, the method of disposal - shallow land burial or alternatives - that will be employed for low-level waste, and regulation of mixed wastes, wastes which have both radioactive and non-radioactive hazardous constituents. The NRC strategy for low-level waste management aims to resolve or reduce these uncertainties, and to encourage transition to a stable, national system based on timely state action. NRC will continue development of regulatory and technical guidance for disposal site licensing and build on its capabilities to address specific areas of state concern, such as alternatives to shallow land burial, and site characterization and modeling. NRC also plans to expand state and compact outreach efforts to help ensure that our technical work is properly focused. The authors will also be directly assisting those states and compacts on technical matters they confront in actual disposal site development and licensing

  20. From franchise to state commission: Regulation of the electric utility industry, 1907 to 1932

    Science.gov (United States)

    Reutter, Keith Alan

    1997-09-01

    Empirical research into the effects of regulation on industry has been around since the early 1960s. Over the last thirty plus years a number of interesting results have been brought to the fore. For instance, it has been found that regulation of the trucking industry limits entry and increases prices. A similar result has been pointed to in other industries such as commercial airlines and banking. The effect of the state commission form of regulation on the electric utility industry has been less conclusive. State commissions became dominant during the period 1910-1930, replacing local franchising as a method of regulating the electric utility industry. Two competing theories suggest why this transformation took place, the "capture" and "public interest" theories of regulation. The capture theory of regulation suggests that the electric utility industry demanded state regulation as a way to earn above normal profits and reduce competition. The public interest theory suggests the purpose of regulation by state commissions was to benefit the general public by forcing the industry to be competitive. Few studies have tried to determine which theory more aptly describes the actual events that took place. The empirical model developed in Chapter V, is an extension of the current literature. A set of simultaneous equations describing the natural gas and electricity markets is estimated using cross-sectional time-series data from 1907 to 1932. The effect of regulation on the electric utility industry is modeled with a dummy variable taking on a value of one to designate that a state commission had been established. The results suggest the capture theory of regulation best describes the period under study. The empirical estimates indicate that state commissions (1) reduced the rate at which the real price of electricity was falling, (2) had a negative impact on firms entering the industry, (3) had a positive influence on the cost of producing a kwh of electricity, and (4

  1. Nuclear Regulatory Commission authorizations for Fiscal Years 1984 and 1985. House of Representatives, Ninety-Eighth Congress, First Session

    International Nuclear Information System (INIS)

    Anon.

    1983-01-01

    H.R. 2510, as amended, authorizes $466.8 million to cover Nuclear Regulatory Commission salaries and expenses for fiscal year 1984 and $460 million for the following year in a two-year authorization. The bill substitutes certain expenditures for those recommended in the NRC request, while keeping the funding level the same. The committee report reviews and summarizes the two-year budget appropriation and the hearings before giving a section-by-section analysis. It notes that 46% is earmarked for waste management, and emphasizes the safety factors which have caused delays in construction and modifications in existing plants. 13 tables

  2. Basis for revision 2 of the U.S. Nuclear Regulatory Commission's Regulatory Guide 1.99

    International Nuclear Information System (INIS)

    Randall, P.N.

    1986-01-01

    Regulatory Guide 1.99. ''Radiation Damage to Reactor Vessel Materials,'' is being updated to reflect recent studies of the physical basis for neutron radiation damage and efforts to correlate damage to chemical composition and fluence. Revision 2 of the Guide contains several significant changes. Welds and base metal are treated separately. Nickel content is added as a variable and phosphorus removed. The exponent in the fluence factor is reduced, especially at high fluences. And, guidance is given for calculating attenuation of damage through the vessel wall. This paper describes the basis for these changes in the Guide

  3. Nuclear Regulatory Commission staff development of the license application review plan for a high-level radioactive waste repository

    International Nuclear Information System (INIS)

    Johnson, R.L.; Holonich, J.J.; Lee, M.P.; Delligatti, M.S.

    1993-01-01

    The Nuclear Regulatory Commission staff has recently started a new initiative to develop the License Application Review Plan (LARP) which the staff will use in its reviews of the U.S. Department of Energy's (DOE's) license application (LA) for a geologic repository for the disposal of high-level radioactive waste (HLW). This paper describes the staff's approach for developing the LARP, the development schedule and current status, the organization and content of the LARP, and the staff's LA review strategy. Therefore, it gives a preview of the draft LARP which will be made available in late 1993. It also describes how the LARP will be used as guidance to the staff in conducting reviews of regulatory and technical issues important to the licensing of a geologic repository. Finally, the benefits to the NRC staff, DOE, and other parties are discussed

  4. Corporate Political Strategies related to Decisions of European Competition Commission on Regulatory Issues in the European Telecommunications Industry

    NARCIS (Netherlands)

    Kranenburg, H.L. van; Ross, T.

    2014-01-01

    The European regulatory institution has the tasks to protect fair competition and equal opportunities for all companies in the European telecommunications industry and to protect the welfare of the consumers. This regulator is responsible for the adherence of telecommunications companies to

  5. Commission of energy regulation. 2004 activity report; Commission de regulation de l'energie. Rapport d'activite 2004

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2004-07-01

    The commission of energy regulation (CRE) is an independent administrative authority in charge of the control of the operation of gas and electricity markets. This document is the fifth activity report of CRE and covers the July 1, 2003 - June 30, 2004 period, which corresponds to the era of opening of energy markets as a consequence of the enforcement of the June 26, 2003 European directive. In the framework of the stakes made by energy markets liberalization, this document presents the situation of the gas and electricity markets during this period (European framework, regulation of both markets, public utility mission..) and describes CRE's means for the monitoring of these markets. (J.S.)

  6. The regulatory consequences of Publication 60 of the ICRP (International Commission on Radiological Protection)

    International Nuclear Information System (INIS)

    Sugier, Annie

    1992-01-01

    The system of radiological protection recommended by the ICRP for future and existing proposed and continuing practices is based on the following general principles: justification, optimisation and limitation of exposure levels. This means that no practice involving exposures to radiation should be adopted unless it produces sufficient benefit to the exposed individuals or to the society to offset the radiation detriment it causes. In relation to any particular source within a practice, the magnitude of individual doses, the number of people exposed, and the likelihood of incurring exposures where these are not certain to be received should all be kept as low as reasonably achievable, economic and social factors being taken into account. The exposure of individuals resulting from the combination of all the relevant practices should be subject to dose limits, or to some control of risk in the case of potential exposures. The system for radiological protection and the values of the limits associated with it, are related the state of knowledge of the effects of radiation. This explains the periodic revision of the corresponding regulatory texts. In a field of such complexity, concerned by disciplines as diverse as medicine, biology, chemistry, statistics, etc., the question naturally arises as to which authority has the capacity to determine an agreed policy. As far as the European Community is concerned, the basic standards related to radiation protection are the subject of Directives which have to be incorporated into national laws by each member state. These directives are under review taking into account explicitly the ICRP recommendations. International agencies whose mission is concerned with the effects of ionising radiation, publish also basic standards related to radiological protection which are not imposed to the participating states except when they collaborate with those bodies, and which mainly act as international references. Such norms also comply with

  7. Indexes to Nuclear Regulatory Commission issuances, July-September 1981. Index 1

    International Nuclear Information System (INIS)

    1981-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  8. Indexes to Nuclear Regulatory Commission issuances, January--March 1994. Volume 39, Index 1

    International Nuclear Information System (INIS)

    1994-07-01

    Digests and indexes for issuances of the Commission, Atomic Safety and Licensing Board Panel, Administrative Law Judges, Directors' Decisions, and Denials of Petitions for Rulemaking are presented in this document. They are intended to serve as a guide to the issuances

  9. Indexes to Nuclear Regulatory Commission issuances, January 1, 1980--December 31, 1985

    International Nuclear Information System (INIS)

    1989-11-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document

  10. 78 FR 17604 - 2006 Biennial Regulatory Review-Revision of the Commission's Rules

    Science.gov (United States)

    2013-03-22

    ... March 22, 2013. FOR FURTHER INFORMATION CONTACT: William Bell, Satellite Division, International Bureau... amended various provisions of Part 25 of its rules pertaining to licensing and operation of satellite... Commission rules or recommendations of the International Telecommunication Union (ITU), and corrected...

  11. Indexes to Nuclear Regulatory Commission issuances, July-December 1985. Volume 22, Index 2

    International Nuclear Information System (INIS)

    1986-03-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document

  12. Indexes to Nuclear Regulatory Commission issuances, July-September 1982. Vol. 16. Index 1

    International Nuclear Information System (INIS)

    1982-01-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  13. Joint ANSI-INMM 8.1: Nuclear Regulatory Commission study of uranium hexafluoride cylinder material accountability bulk measurements

    International Nuclear Information System (INIS)

    Pontius, P.E.; Doher, L.W.

    1977-01-01

    This paper reports the progress to date in a demonstration of the procedures in ANSI N15.18-1975, ''Mass Calibration Techniques for Nuclear Material Control,'' sponsored and funded by the Nuclear Regulatory Commission (NRC). The philosophy of mass measurement as a production process, as promulgated in ANSI N15.18-1975, is reviewed. Special emphasis is placed on the use of artifact Reference Mass Standards (RMS) as references for uranium hexafluoride (UF 6 ) calibration and bulk measurement processes. The history of the creation of the artifact concept and its adoption by ANSI N15.18-1975 and the Nuclear Regulatory Commission is narrated. The program now under way is specifically described; including descriptions of the RMS, their calibration, and the assignment of uncertainties to them by the National Bureau of Standards (NBS). Instrument tests, in-house standards (IHS), and assignment of values relative to the RMS-NBS values at nuclear facilities which measure UF 6 cylinders are described. Comparisons and the data base are detailed to provide realistic measurement process parameters associated with accountable transfer of UF 6 . The as yet uncompleted part of the demonstration is described, that is, to further close the measurement loop by verification both between and within facilities

  14. Overview Of The U.S. Department Of Energy And Nuclear Regulatory Commission Performance Assessment Approaches: Cementitious Barriers Partnership

    International Nuclear Information System (INIS)

    Langton, C.; Burns, H.

    2009-01-01

    a need to assess the behavior of cementitious materials for applications in environmental remediation and decontamination and decommissioning (D and D) applications. The ability to assess the use and benefits of cementitious materials for these applications can significantly affect decisions related to cleanup activities. For example the need for costly remedial actions may not be necessary if existing or new cementitious barriers were adequately represented. The sections dealing with regulatory considerations include summaries of the different regulations that are relevant for various applications involving cementitious materials. A summary of regulatory guidance and/or policies pertaining to performance assessment of cementitious materials and sensitivity and uncertainty analyses is also provided in the following chapters. Numerous examples of specific applications are provided in each report. The examples are organized into traditional waste disposal applications (performance assessments), applications related to environmental remediation and D and D, and reactor and spent fuel related assessments. Sections that discuss specific facilities or sites contain: (1) descriptions of the role of the cementitious barriers or sensitivity/uncertainty analysis, (2) parameter assumptions and conceptual models, and (3) a relative discussion of the significance in the context of the assessment. Examples from both the U.S. Department of Energy Sites and the U.S. Nuclear Regulatory Commission are provided to illustrate the variety of applications and approaches that have been used. In many cases, minimal credit was taken for cementitious barriers. However, in some of those cases, benefits of being able to take credit for barriers were identified. The examples included: (1) disposal facilities (vaults, trenches, tank closures, cementitious waste forms and containers, etc.), (2) environmental remediation (old disposal facilities), (3) reactor and large structure decommissioning

  15. OVERVIEW OF THE U.S. DEPARTMENT OF ENERGY AND NUCLEAR REGULATORY COMMISSION PERFORMANCE ASSESSMENT APPROACHES: CEMENTITIOUS BARRIERS PARTNERSHIP

    Energy Technology Data Exchange (ETDEWEB)

    Langton, C.; Burns, H.

    2009-05-29

    a need to assess the behavior of cementitious materials for applications in environmental remediation and decontamination and decommissioning (D&D) applications. The ability to assess the use and benefits of cementitious materials for these applications can significantly affect decisions related to cleanup activities. For example the need for costly remedial actions may not be necessary if existing or new cementitious barriers were adequately represented. The sections dealing with regulatory considerations include summaries of the different regulations that are relevant for various applications involving cementitious materials. A summary of regulatory guidance and/or policies pertaining to performance assessment of cementitious materials and sensitivity and uncertainty analyses is also provided in the following chapters. Numerous examples of specific applications are provided in each report. The examples are organized into traditional waste disposal applications (performance assessments), applications related to environmental remediation and D&D, and reactor and spent fuel related assessments. Sections that discuss specific facilities or sites contain: (1) descriptions of the role of the cementitious barriers or sensitivity/uncertainty analysis, (2) parameter assumptions and conceptual models, and (3) a relative discussion of the significance in the context of the assessment. Examples from both the U.S. Department of Energy Sites and the U.S. Nuclear Regulatory Commission are provided to illustrate the variety of applications and approaches that have been used. In many cases, minimal credit was taken for cementitious barriers. However, in some of those cases, benefits of being able to take credit for barriers were identified. The examples included: (1) disposal facilities (vaults, trenches, tank closures, cementitious waste forms and containers, etc.), (2) environmental remediation (old disposal facilities), (3) reactor and large structure decommissioning, and (4

  16. Safety experts complete second IAEA regulatory review of UK nuclear regulator

    International Nuclear Information System (INIS)

    2009-01-01

    Full text: Nuclear safety experts today concluded a 10-day mission to peer-review the UK Nuclear Regulator: Health and Safety Executive (HSE), Nuclear Directorate (ND). At the request of the UK Government, the International Atomic Energy Agency assembled a team of ten high-level regulatory experts from eight nations to conduct the Integrated Regulatory Review Service (IRRS) mission. The mission was the second of three planned IRRS missions for the United Kingdom. The first was held in March 2006 to begin a process to assess the nation's readiness to regulate and license new reactor designs, considered as a result of the Energy Policy review initiated by the British Prime Minister and the Secretary of State for Trade and Industry (DTI) in 2005. The IRRS team leader Mr. William Borchardt, Executive Director of Operations from the US Nuclear Regulatory Commission, stated, ''The IAEA IRRS serves an important role in both benchmarking against its safety standards and in promoting dialogue between nuclear safety regulators from around the world.'' During the 2nd mission the IRRS the team reviewed HSE/ND progress since the first IRRS mission and recent regulatory developments, the regulation of operating power plants and fuel cycle facilities, the inspection and enforcement programme for nuclear power plants and fuel cycle facilities, and the emergency preparedness and response programme. The IAEA found that HSE/ND has made significant progress toward improving its effectiveness in regulating existing nuclear power plants and in preparing to license new nuclear reactors designs. Many of the findings identified in the 2006 report had been fully addressed and therefore could be considered closed, the others are being addressed in accordance with a comprehensive action plan. IRRS team members visited the Heysham 1 Nuclear Power Plant near Lancaster, the Sellafield site at Cumbria and the Strategic Control Centre at Hutton, and they met senior managers from HSE and a UK

  17. Indexes to Nuclear Regulatory Commission issuances, January-June 1984. Vol. 19, Index 2

    International Nuclear Information System (INIS)

    1984-11-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. The information elements are displayed in one or more of five separate formats: case name index, digests and headers, legal citations index, subject index, and facility index

  18. Indexes to Nuclear Regulatory Commission issuances, January-June 1986. Volume 23, Index 2

    International Nuclear Information System (INIS)

    1986-01-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Appeal Panel, the Atomic Safety and Licensing Board Panel, the Administrative Law Judge, the Directors' Decisions, and the Denials of Petitions of Rulemaking are presented in this document. The information elements are displayed in one or more of five separate formats. These formats are case name index, digests and headers, legal citations index, subject index, and facility index

  19. Indexes to Nuclear Regulatory Commission issuances, July-December 1984. Volume 20, Index 2

    International Nuclear Information System (INIS)

    1985-03-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking for the period July-December 1984 are presented in this document. These digests and indexes are intended to serve as a guide to the issuances

  20. Indexes to Nuclear Regulatory Commission Issuances, July-September 1985. Volume 22, Index 1

    International Nuclear Information System (INIS)

    1985-12-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. The period from July through September 1985 is covered

  1. Indexes to Nuclear Regulatory Commission issuances, January-March 1984. Volume 19, Index 1

    International Nuclear Information System (INIS)

    1984-01-01

    Digests and indexes for issuances of the Commission, the Atomic Safety and Licensing Appeal Panel, the Atomic Safety and Licensing Board Panel, the Administrative Law Judge, the Directors' Decisions, and the Denials of Petitions of Rulemaking are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. Information elements are displayed in one or more of five separate formats: Case Name Index, Digests and Headers, Legal Citations Index, Subject Index, and Facility Index

  2. Indexes to Nuclear Regulatory Commission issuances, January--June 1995. Volume 41, Index 2

    International Nuclear Information System (INIS)

    1995-09-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the directors' Decisions (DD), and the Denials of Petitions for rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. The information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index; and facility index

  3. Indexes to Nuclear Regulatory Commission Issuances, July--December 1993. Volume 38, Index 2

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the Directors` Decisions (DD), and the Denials of Petitions for Rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. These information elements are displayed in one or more of five separate formats arranged as follows: Case Name Index; Digests and Headers; Legal Citations Index; Subject Index, and Facility Index.

  4. Indexes to Nuclear Regulatory Commission issuances, January--June 1995. Volume 41, Index 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    Digests and indexes for issuances of the Commission (CLI), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judges (ALJ), the directors` Decisions (DD), and the Denials of Petitions for rulemaking (DPRM) are presented in this document. These digests and indexes are intended to serve as a guide to the issuances. The information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index; and facility index.

  5. Indexes to Nuclear Regulatory Commission issuances, January 1, 1986-- December 31, 1990

    International Nuclear Information System (INIS)

    1992-11-01

    Digests and indexes for issuances of the commission (CLI), the Atomic Safety and Licensing Appeal Panel (ALAB), the Atomic Safety and Licensing Board Panel (LBP), the Administrative Law Judge (ALJ), the Directors' Decisions (DD), and the Denials of Petitions for Rulemaking are presented in this document. The information elements are displayed in one or more of five separate formats arranged as follows: Case name index; digests and headers; legal citations index; subject index; and facility index

  6. Deliberation of the commission of electricity regulation relative to the definition of the modalities of allocation, for the year 2002, of the transfrontier transit capacities between France and Italy; Deliberation de la Commission de Regulation de l'Electricite relative a la definition des modalites d'attribution pour l'annee 2002 des capacites de transit transfrontalier entre la France et l'Italie

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-07-01

    This regulatory text from the French commission of electricity regulation (CRE) defines the annual and secondary allocation of electricity transit capacity between France and Italy. Transit capacity allocations are jointly implemented by the French and Italian public network management authorities (RTE and GRTN, respectively). (J.S.)

  7. U.S. Nuclear Regulatory Commission nuclear safety assistance to the CEE and NIS countries

    International Nuclear Information System (INIS)

    Blaha, J.

    2001-01-01

    NRC participates in bilateral and multilateral efforts to strengthen the regulatory authorities of countries in which Soviet design NPPs are operated. Countries involved are the New Independent States of the Soviet Union (Armenia, Kazakhstan, Russia and Ukraine) and of Central and Eastern Europe (Bulgaria, Czech Republic, Hungary, Lithuania and Slovak Republic). NRC's goal is to see that its counterparts receive the basic tools, knowledge and understanding needed to exercise effective regulatory oversight, consistent with internationally accepted norms and standards. The bilateral assistance started in 1991. $44 mill. are provided to the countries. The multilateral activities NRC participates in include: H-7 Nuclear Safety Working Group, EBRD - Administered Nuclear Safety Account and Chernobyl Sarcophagus Fund and IAEA

  8. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest. Digest No. 2

    International Nuclear Information System (INIS)

    1978-08-01

    This second edition of the NRC Staff Practice and Procedure Digest contains a digest of a number of Commission, Atomic Safety and Licensing Appeal Board and Atomic Safety and Licensing Board decisions issued during the period from July 1, 1972 to March 31, 1978 interpreting the NRC's Rules of Practice in 10 CFR Part 2. This second edition replaces the first edition and its supplements and includes appropriate changes reflecting the recent amendments to the Rules of Practice which became effective on May 26, 1978

  9. Law as an organizational variable: an examination of the impact of law on the performance of the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Montgomery, J.M.

    1984-01-01

    The role of law in a federal regulatory agency is examined from an organizational perspective. While law is usually viewed in terms of its legal, political, and social value consequences, it is postulated that it also has significant organizational consequences. The impact of those consequences is examined in the case of a single agency, the US Nuclear Regulatory Commission. The legal process is shown to be a powerful organizational characteristic of the government administrative agency, beginning with statuatory definition of organization goals, structure, and procedures and ending with judicial review of actions. Agency lawyers are shown to represent a distinct professional subculture within this agency. Their values and orientations toward business, the role of regulation, and the role of nuclear utilities are different from the 95% of agency employees subculture based on a physical science/engineering background. It is concluded that agency effectiveness suffers from the cultural polarization resulting from the disparities in belief systems of the two major identifiable professional groups, lawyers and scientist/engineers. It is also concluded that the impact of law on organizational performance and effectiveness attributes is largely dysfunctional. Such dysfunctionalism could be lessened with modified legal interpretation or statutory change, improved science/law relationship, and better understanding of the legal process by nonlawyer policymakers

  10. Report to the US Nuclear Regulatory Commission on analysis and evaluation of operational data - 1987: Power reactors

    Energy Technology Data Exchange (ETDEWEB)

    None

    1988-10-01

    This annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1987. The report is published in two volumes. NUREG-1272, Vol. 2, No. 1, covers Power Reactors and presents an overview of the operating experience of the nuclear power industry, with comments regarding the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year, and summarizes information from Licensee Event Reports, the NRC's Operations Center, and Diagnostic Evaluations. NUREG-1272, Vol. 2, No. 2, covers Nonreactors and presents a review of the nonreactors events and misadministration reports that were reported in 1987 and a brief synopsis of AEOD studies published in 1987. Each volume contains a list of the AEOD Reports issued for 1980-1987.

  11. Review and evaluation of the Nuclear Regulatory Commission Safety Research Program for Fiscal Years 1984 and 1985

    International Nuclear Information System (INIS)

    1983-02-01

    This is the sixth report by the Advisory Committee on Reactor Safeguards (ACRS) that has been prepared in response to the Congressional requirement for an annual report on the Nuclear Regulatory Commission (NRC) Reactor Safety Research Program. Part I is a compilation of our general comments and recommendations regarding the NRC Safety Research Program, and includes budget recommendations and an identification of matters of special importance that deserve increased emphasis. It is intended to serve as an Executive Summary. Part II is divided into ten chapters, each of which represents a Decision Unit of the NRC research program. In each chapter, specific comments are included on the research involved in the Decision Unit, an assessment of priorities, and recommendations regarding new directions and levels of funding

  12. Federal guide for a radiological response: Supporting the Nuclear Regulatory Commission during the initial hours of a serious accident

    International Nuclear Information System (INIS)

    Hogan, R.T.

    1993-11-01

    This document is a planning guide for those Federal agencies that work with the Nuclear Regulatory commission (NRC) during the initial hours of response to a serious radiological emergency in which the NRC is the Lead Federal Agency (LFA). These Federal agencies are: DOE, EPA, USDA, HHS, NOAA, and FEMA. This guide is intended to help these agencies prepare for a prompt response. Instructions are provided on receiving the initial notification, the type of person to send to the scene, the facility at which people are needed, how to get them to that facility, and what they should do when they arrive. Federal agencies not specifically mentioned in this guide may also be asked to support the NRC

  13. The U.S. Nuclear Regulatory Commission Thermal-Hydraulic Research Program: Maintaining expertise in a changing environment

    International Nuclear Information System (INIS)

    Sheron, B.W.; Shotkin, L.M.; Baratta, A.J.

    1993-01-01

    Throughout the 1970s and early 1980s, the U.S. Nuclear Regulatory Commission's (NRC's) thermal-hydraulic research program enjoyed ample funding, sponsored extensive experimental and analytical development programs, and attracted worldwide expertise. With the completion of the major experimental programs and with the promulgation of the revised emergency core-cooling system rule, both the funding and prominence of thermal-hydraulic research at the NRC have declined in recent years. This has led justifiably to the concern by some that the program may no longer have the minimal elements needed to maintain both expertise and world-class status. The purpose of this article is to describe the NRC's current thermal-hydraulic research program and to show how this program ensures maintenance of a viable, robust research effort and retention of needed expertise and international leadership

  14. Commission de regulation de l'electricite. Activity Report 30 June 2000

    International Nuclear Information System (INIS)

    2000-01-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity market for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity sector, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the June 2000 activity report of CRE. Content: A - Opening of the European electricity market: transposition into French law of the European Directive, access to the European power transportation network, obstacles to market deregulation, segmentation of the European market, deregulation impact on electricity market: the German example, state of the French market openness; B - The first regulation projects: network access, account un-bundling, production opening to competition modalities, studies relative to the creation of an electricity stock-exchange in France; C - The Commission: means, operation. D - Appendixes: Glossary; Units; Council of European Energy Regulators

  15. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest. Supplement 2 to Digest No. 1

    International Nuclear Information System (INIS)

    1978-02-01

    This is the second in a series of Supplements to the NRC Practice and Procedure Digest. This Supplement updates the Digest by including pertinent Commission, Appeal Board, and Licensing Board rulings for the period April 1, 1977 to September 30, 1977. The Supplement also adds a number of new topics. The Supplement is structured in the same manner as the Digest. For the convenience of users, the text of the Supplement is preceded by an index which lists the Digest topic headings which are supplemented. In using the main Digest, this index to Supplement 2 as well as the index to Supplement 1 should be consulted to assure that the Digest discussion has not been superseded or updated by information in the Supplements

  16. An approach to regulatory compliance with radioactive mixed waste regulations

    International Nuclear Information System (INIS)

    Baker, G.G.; Mihalovich, G.S.; Provencher, R.B.

    1991-01-01

    On May 7, 1990, radioactive mixed waste (RMW) at the West Valley Demonstration Project (WVDP) became subject to the State Of New York hazardous waste regulations. The facility was required to be in full compliance by June 6, 1990. Achievement of this goal was difficult because of the short implementation time frame. Compliance with the hazardous waste regulations also presented some potential conflicts between the hazardous waste requirements and other regulatory requirements specifically applicable to nuclear facilities. The potential conflicts involved construction, operation, and control measures. However, the facility had been working extensively with EPA Region 2 and the New York State Department of Environmental Conservation (NYSDEC) on the application of the hazardous waste regulations to the facility. During these preliminary contacts, WVDP identified three issues that related to the potential conflicts: 1. Equivalency of Design and Equipment, 2. Land Disposal Restrictions (LDR), and 3. The Principle of As Low As Reasonable Achievable (ALARA) Radiation Exposure. The equivalency of nuclear facility design and equipment to the hazardous waste requirements is based in part on the increased construction criteria for nuclear facilities, the use of remote radiological monitoring for leak detection, and testing of system components that are not accessible to personnel due to high levels of radiation. This paper discusses in detail: 1. The implementation and results of the WVDP's interaction with its regulators, 2. How the regulators were helped to understand the different situations and conditions of nuclear and chemical facilities, and 3. How, by working together, the result was not only mutually advantageous to the NWDP and the agencies, but it also assured that the health and safety of workers, the public, and the environment were protected

  17. Study of the impacts of regulations affecting the acceptance of Integrated Community Energy Systems: public utility, energy facility siting and municipal franchising regulatory programs in Illinois. Preliminary background report

    Energy Technology Data Exchange (ETDEWEB)

    Feurer, D A; Weaver, C L; Gallagher, K C; Hejna, D; Rielley, K J

    1980-01-01

    The authority to regulate public utilities is vested generally in the Illinois Commerce Commission, comprised of five members appointed by the governor with the advice and consent of the senate and appointed for five year terms. They must be free from any employment or pecuniary interests in any business subject to regulation by the Commission. Local governments may exercise a large degree of regulatory authority over public utilities providing services within a municipality. The question of whether a municipality will exercise regulatory control over local public utilities must be put to the voters of the city. If the proposition is approved by a majority of the voters, the municipality may regulate services and rates and exercise most of the regulatory functions otherwise assigned to the Commission. If any public utility is dissatisfied with any action of a municipality, the utility is entitled to apply to the Commission for review of the action. On review, the Commission may take any determination which it deems just and reasonable. In addition, municipally-owned utilities are excluded specifically from the definition of public utility. These utilities are not within the jurisdiction of the Commission and are regulated locally. Public utility regulatory statutes, energy facility siting programs, and municipal franchising authority are examined to identify how they may impact on the ability of an organization, whether or not it be a regulated utility, to construct and operate an ICES.

  18. The U.S. Nuclear Regulatory Commission's antitrust review of nuclear power plants: the conditioning of licenses

    International Nuclear Information System (INIS)

    Penn, D.W.; Delaney, J.B.; Honeycutt, T.C.

    1976-04-01

    The 1970 amendments to Section 105 of the Atomic Energy Act require the Nuclear Regulatory Commission to conduct a prelicensing antitrust review of applications for licenses to construct and operate nuclear power plants. The Commission must make a finding as to whether the granting of a license 'would create or maintain a situation inconsistent with the antitrust laws,' and it has the authority to issue or continue a license, to refuse to issue a license, to rescind or amend a license, and to issue a license with conditions that it deems appropriate. This report provides information about the antitrust license conditions that have resulted from the NRC's antitrust review process. The process itself is described and a catalog of the applications requiring antitrust license conditions is presented. For each application, the license conditions are put into the general categories of unit access, transmission services, coordination, and contractual provisions. For completeness, the report also catalogs applications requiring no antitrust license conditions, and lists applications that were exempted from the 1970 amendments, are the subject of litigation, or have been withdrawn

  19. The European Commission's light bulb decree: Another costly regulation?

    Energy Technology Data Exchange (ETDEWEB)

    Frondel, Manuel, E-mail: frondel@rwi-essen.de [Ruhr-University Bochum (RUB), Ruhr-Graduate School in Economics (RGS Econ) (Germany); Rheinisch-Westfaelisches Institut fuer Wirtschaftsforschung (RWI), Hohenzollernstr. 1-3, 45128 Essen (Germany); Lohmann, Steffen [Rheinisch-Westfaelisches Institut fuer Wirtschaftsforschung (RWI), Hohenzollernstr. 1-3, 45128 Essen (Germany); Tinbergen Institute (Netherlands)

    2011-06-15

    Since September 2009, Regulation 244/2009 of the European Commission enforces the gradual phase-out of incandescent light bulbs. As of September 2012, only energy-efficient lighting sources will be allowed for sale. Among these are halogen light bulbs, light-emitting diodes (LED), or compact fluorescent light bulbs-often referred to as energy-saving light bulbs. The Commission's justification for the phase-out of conventional light bulbs maintains that a reduction in the electricity consumed will not only lead to lower energy cost for private households and industrial consumers, but at the same time lead to a decrease in greenhouse gas emissions. This article discusses possible reasons for the slow market diffusion of energy-saving light bulbs and shows that the investment in energy-efficient light bulbs does not necessarily lead to significant cost reductions. Drawing on some illustrative examples, we demonstrate that the use of cheaper incandescent bulbs instead of energy-saving light bulbs can be economically rational in cases of rather low usage times, in which the higher initial purchasing price might only pay off after very long time spans. Furthermore, due to the coexistence with the European Emissions Trading Scheme (ETS), this regulation attains no additional emission reductions beyond those achieved by the ETS alone. We thus conclude that the general ban of incandescent light bulbs is inappropriate and should be abolished by the Commission. - Research Highlights: > This article discusses reasons for the slow market diffusion of energy-saving light bulbs. > We show that using incandescent bulbs can be rational in cases of rather low usage times. > We conclude that the general ban of incandescent light bulbs should be abolished by the Commission.

  20. PWR and BWR anticipated and abnormal plant transient research sponsored by the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Beckner, W.D.; Sullivan, L.H.

    1984-01-01

    This chapter reviews the regulatory activities of the US NRC since the realization that anticipated transients with multiple failures (including operator actions) are the major contributors to risk from reactor operations and that the low probability design basis accidents (DBA) are relatively small contributors to risk. The Three Mile Island-2 accident demonstrated that anticipated transients, combined with multiple equipment and/or operator failures, can result in significant core damage. Topics considered include research in direct response to Three Mile Island-2, research in response to specific safety issues, and research to improve the overall understanding of transients (experimental facilities, computer codes). It is concluded that the US NRC has made significant progress in improving its ability to analyze and evaluate abnormal and anticipated transients

  1. An assessment of the contribution of NRC [Nuclear Regulatory Commission] regulatory growth to nuclear plant cost growth using engineering scope changes

    International Nuclear Information System (INIS)

    Cohen, S.

    1987-03-01

    The purpose of this study is to determine the contribution of NRC regulations to the growth in nuclear power plant capital costs using the case study method. The two plants selected for the case studies are Florida Power and Light Company's (FP and L) St. Lucie Unit 1 (SL1) and St. Lucie Unit 2 (SL2). SL1 was constructed in the early 1970s and was granted an operating license in 1976. SL2 was constructed in the late 1970s and early 1980s, and was granted an operating license in 1983. The information bases were the amendments to the contracts between FP and L and its architect-engineer/constructor, i.e., the ''scope changes''. These were examined and analyzed for causation, i.e., NRC-initiated or utility-initiated, and all of the costs associated with scope changes of each type were aggregated to determine the contribution of each. Although the scope changes accounted for only a small fraction of the total cost growth for either plant, they were still used to determine the relative contribution of regulatory growth to cost growth. Unexpectedly, a significantly higher percentage of out-of-scope work (approximately 84%) was attributable to NRC regulatory requirements for SL1 than SL2 (approximately 47%). These results were unexpected because SL2 was constructed during a period in which regulation was considered to be particularly unstable. However, a more detailed analysis of causation indicates that a shift occurred from an ad-hoc mode of regulation in the early 1970s to a more prescriptive process in the late 1970s. Thus the number of formal NRC requirements may not be a valid measure of regulatory stability

  2. Uranium recovery research sponsored by the Nuclear Regulatory Commission at Pacific Northwest Laboratory. Annual progress report, May 1982-May 1983

    International Nuclear Information System (INIS)

    Foley, M.G.; Opitz, B.E.; Deutsch, W.J.

    1983-06-01

    Pacific Northwest Laboratory (PNL) is currently conducting research for the US Nuclear Regulatory Commission (NRC) on uranium recovery process wastes for both active and inactive operations. NRC-sponsored uranium recovery research at PNL is focused on NRC regulatory responsibilities for uranium-recovery operations: license active milling and in situ extraction operations; concur on the acceptability of DOE remedial-action plans for inactive sites; and license DOE to maintain inactive sites following remedial actions. PNL's program consists of four coordinated projects comprised of a program management task and nine research tasks that address the critical technical and safety issues for uranium recovery. Specifically, the projects endeavor to find and evaluate methods to: prevent erosion of tailings piles and prevent radon release from tailings piles; evaluate the effectiveness of interim stabilization techniques to prevent wind erosion and transport of dry tailings from active piles; estimate the dewatering and consolidation behavior of slurried tailings to promote early cover placement; design a cover-protection system to prevent erosion of the cover by expected environmental stresses; reduce seepage into ground water and prevent ground-water degradation; control solution movement and reaction with ground water in in-situ extraction operations; evaluate natural and induced restoration of ground water in in-situ extraction operations; and monitor releases to the environment from uranium recovery facilities

  3. Uranium recovery research sponsored by the Nuclear Regulatory Commission at Pacific Northwest Laboratory. Annual progress report, May 1982-May 1983

    Energy Technology Data Exchange (ETDEWEB)

    Foley, M.G.; Opitz, B.E.; Deutsch, W.J.; Peterson, S.R.; Gee, G.W.; Serne, R.J.; Hartley, J.N.; Thomas, V.W.; Kalkwarf, D.R.; Walters, W.H.

    1983-06-01

    Pacific Northwest Laboratory (PNL) is currently conducting research for the US Nuclear Regulatory Commission (NRC) on uranium recovery process wastes for both active and inactive operations. NRC-sponsored uranium recovery research at PNL is focused on NRC regulatory responsibilities for uranium-recovery operations: license active milling and in situ extraction operations; concur on the acceptability of DOE remedial-action plans for inactive sites; and license DOE to maintain inactive sites following remedial actions. PNL's program consists of four coordinated projects comprised of a program management task and nine research tasks that address the critical technical and safety issues for uranium recovery. Specifically, the projects endeavor to find and evaluate methods to: prevent erosion of tailings piles and prevent radon release from tailings piles; evaluate the effectiveness of interim stabilization techniques to prevent wind erosion and transport of dry tailings from active piles; estimate the dewatering and consolidation behavior of slurried tailings to promote early cover placement; design a cover-protection system to prevent erosion of the cover by expected environmental stresses; reduce seepage into ground water and prevent ground-water degradation; control solution movement and reaction with ground water in in-situ extraction operations; evaluate natural and induced restoration of ground water in in-situ extraction operations; and monitor releases to the environment from uranium recovery facilities.

  4. U.S. Nuclear Regulatory Commission Role and Activities Related to U.S. Department of Energy Incidental Waste Determinations

    International Nuclear Information System (INIS)

    Bradford, A.H.; Esh, D.W.; Ridge, A.C.

    2006-01-01

    Section 3116 of the Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 (NDAA) requires the U.S. Department of Energy (DOE) to consult with the U.S. Nuclear Regulatory Commission (NRC) for certain non-high level waste (HLW) determinations. Under the NDAA, NRC performs consultative technical reviews of DOE's waste determinations and monitors DOE's disposal actions for such waste, but the NRC does not have regulatory authority over DOE's waste disposal activities. The NDAA provides the criteria that must be met to determine that waste is not HLW. The criteria require that the waste does not need to be disposed of in a geologic repository, that highly radioactive radionuclides be removed to the maximum extent practical, and that the performance objectives of 10 CFR 61, Subpart C, be met. The performance objectives contain criteria for protection of the public, protection of inadvertent intruders, protection of workers, and stability of the disposal site after closure. This paper describes NRC's approach to implementing its responsibilities under the NDAA, as well as similar activities being performed for sites not covered by the NDAA. (authors)

  5. Industry perceptions of the impact of the U.S. Nuclear Regulatory Commission on nuclear power plant activities. Draft report

    Energy Technology Data Exchange (ETDEWEB)

    Davis, A Bert; Pederson, Cynthia D

    1990-03-01

    Teams of senior managers from the U.S. Nuclear Regulatory Commission (NRC) surveyed licensee staff members representing 13 nuclear power utilities from across the country to obtain their candid views of the effectiveness and impact of NRC regulatory activities. Licensee comments addressed the full scope of NRC activities and the impact of agency actions on licensee resources, staff performance, planning and scheduling, and organizational effectiveness. The principal themes of the survey respondents' comments are that (1) licensees acquiesce to NRC requests to avoid poor ratings on NRC Systematic Assessment of Licensee Performance (SALP) reports and the consequent financial and public perception problems that result, even if the requests require the expenditure of significant resources on matters of marginal safety significance, and (2) NRC so dominates licensee resources through its existing and changing formal and informal requirements that licensees believe that their plants, though not unsafe, would have better reliability, and may even achieve a higher degree of safety, if licensees were freer to manage their own resources. This draft report does not attempt to defend any NRC position; endorse or refute licensee perceptions; or explain any action taken by NRC in fulfilling its responsibilities to protect the health and safety of the public. Senior RC managers have made a preliminary evaluation of the information in this report and have made recommendations to address licensee concerns in some areas. The final evaluation and recommendations will be published at a later date as the final NUREG. (author)

  6. Court-agency interaction in environmental policymaking: the cases of the Nuclear Regulatory Commission and the Environmental Protection Agency

    International Nuclear Information System (INIS)

    Thomas, L.W.

    1981-01-01

    This study examines the increasingly active participation of courts in the administrative process as well as agency responses to court-imposed policy shifts. More specifically, it is an investigation of the interaction between the federal courts, primarily the Supreme Court and the District of Columbia Court of Appeals, and two federal regulatory agencies, the Nuclar Regulatory Commission and the Environmental Protection Agency. There are five objectives to the study. The first is to examine the natura of court-agency interaction and to determine the extent to which patterns of judicial review of administrative actions can be discerned. The second is to examine the effect of court orders on agency programs and policies. The third is to assess the anticipatory dimension of court-agency relations. The fourth is to inquire into the recurring dimension of court-agency interaction and to determine its effect on subsequent court decisions. The last is to assess the institutional capacity of courts to deal with scientific and technological issues. This study indicates that judicial review has a substantial effect on the NRC's and the EPA's decision-making activities. Few, if any, recent major policy decisions of the two agencies have not been scrutinized closely by federal appellate courts. During the past decade, the courts have blocked policy initiative on numerous occasions and have been the primary source of change in others. In addition, the mere anticipation of judicial review was found to be a factor motivating the two agencies to make reasoned decisions

  7. United States Nuclear Regulatory Commission Staff Practice and Procedure Digest. Supplement 3 to Digest No. 1

    International Nuclear Information System (INIS)

    1978-04-01

    This is the third of a series of Supplements to the NRC Practice and Procedure Digest. This Supplement updates the Digest by including pertinent Commission, Appeal Board, and Licensing Board rulings for the period October 1, 1977 to December 31, 1977. The Supplement also adds several new topics. The Supplement is structured in the same manner as the Digest. For the convenience of users, the text of the Supplement is preceded by an index which lists the Digest topic headings which are supplemented. In using the main Digest, this index to Supplement 3 as well as those to Supplements 1 and 2 should be consulted to assure that the Digest discussion has not been superseded or updated by information in the Supplements. Supplement 3 is intended for use as a ''pocket part''. It should be inserted after Supplements 1 and 2, following the main Digest. Notice is hereby given that all disclaimers with respect to content, accuracy and completeness of information, express or implied warranties, and use of or reliance upon information presented, set forth in regard to the Digest itself, are equally applicable to this Supplement

  8. Commission de regulation de l'energie. Activity Report June 2003

    International Nuclear Information System (INIS)

    2003-06-01

    CRE is the French commission for energy regulation. CRE's remit is to assist in ensuring the proper operation of the electricity and natural gas markets for the benefit of the end-user. In particular, CRE ensures that the conditions of access to electricity and natural gas transmission and distribution systems do not hinder the development of competition. It monitors, for the electricity and natural gas sectors, all transactions made between suppliers, traders and producers, all transactions made on the organised markets and cross-border trading. It ensures that suppliers, traders and producers propose offers that are consistent with their financial and technical constraints. It monitors the implementation of and compliance with regulations giving consumers the right to choose their supplier in a competitive market, and allowing new suppliers to enter the market. This document is the June 2003 activity report of CRE. Content: A - Energy markets regulation: a new step; B - Gas market regulation: gas markets and actors, gas market regulation (legal and institutional framework, networks access, methane terminals and modulation services, freedom spaces, European market regulation, gas utility, CRE gas activities and priorities in 2003); C - Electricity market regulation: electricity markets (European markets, operators activity on the French market), French electricity market regulation (public networks access, trans-border power exchanges, EDF's un-bundled accounts audit, market operation), electric utility in the regulated market (public utility content, public utility charges, power generation public utility financing, electricity pre-tax sale tariffs for non-eligible customers); D - CRE operation (means and resources, exercise of its implementing powers, European and international activities); E - Appendixes: Glossary; Units and conversions; Council of European Energy Regulators, Index of figures and tables

  9. Integrated systems approach identifies risk regulatory pathways and key regulators in coronary artery disease.

    Science.gov (United States)

    Zhang, Yan; Liu, Dianming; Wang, Lihong; Wang, Shuyuan; Yu, Xuexin; Dai, Enyu; Liu, Xinyi; Luo, Shanshun; Jiang, Wei

    2015-12-01

    Coronary artery disease (CAD) is the most common type of heart disease. However, the molecular mechanisms of CAD remain elusive. Regulatory pathways are known to play crucial roles in many pathogenic processes. Thus, inferring risk regulatory pathways is an important step toward elucidating the mechanisms underlying CAD. With advances in high-throughput data, we developed an integrated systems approach to identify CAD risk regulatory pathways and key regulators. Firstly, a CAD-related core subnetwork was identified from a curated transcription factor (TF) and microRNA (miRNA) regulatory network based on a random walk algorithm. Secondly, candidate risk regulatory pathways were extracted from the subnetwork by applying a breadth-first search (BFS) algorithm. Then, risk regulatory pathways were prioritized based on multiple CAD-associated data sources. Finally, we also proposed a new measure to prioritize upstream regulators. We inferred that phosphatase and tensin homolog (PTEN) may be a key regulator in the dysregulation of risk regulatory pathways. This study takes a closer step than the identification of disease subnetworks or modules. From the risk regulatory pathways, we could understand the flow of regulatory information in the initiation and progression of the disease. Our approach helps to uncover its potential etiology. We developed an integrated systems approach to identify risk regulatory pathways. We proposed a new measure to prioritize the key regulators in CAD. PTEN may be a key regulator in dysregulation of the risk regulatory pathways.

  10. Experience of regulatory body functioning in energy industry of Ukraine: Prospects for future development of state regulation of energy

    International Nuclear Information System (INIS)

    Oruskaya, M.

    2002-01-01

    Materials collected (presented) in the paper introduce to (familiarise) the audience with the main forms, methods and phases of the state regulation of energy industry in Ukraine in the period of transition to market economy. Special attention was paid to the following aspects: 1. Necessity and history of establishment of special regulatory body in Ukraine - The National Electricity Regulatory Commission (NERC); 2. The main tasks and authorities of NERC according to the Ukraine Law on Energy Sector; 3. Regulation mechanisms of the main processes in the energy industry used by the Commission on the current level of energy sector development and economic results of its introduction; 4. Problems with functioning of the wholesale energy market specifically as the main component of the Ukraine energy industry and trends of future development (improvement of energy industry's financial situation, intensification of competition between energy producers and suppliers, improvement of tariff and investment policies, etc.); 5. Necessity and ways of future improvement of the standards and legal basis for regulation in Ukraine. (author)

  11. Food safety regulatory systems in Europe and China:A study of how co-regulation can improve regulatory effectiveness

    Institute of Scientific and Technical Information of China (English)

    Kevin Chen; WANG Xin-xin; SONG Hai-ying

    2015-01-01

    Food safety has received a great deal of attention in both developed and developing countries in recent years. In China, the numerous food scandals and scares that have struck over the past decade have spurred signiifcant food safety regulatory reform, which has been increasingly oriented towards the public-private partnership model adopted by the Europe Union’s (EU) food safety regulatory system. This paper analyzes the development of both the EU’s and China’s food safety regu-latory systems, identiifes the current chalenges for China and additionaly considers the role of public-private partnership. The success of co-regulation in the food regulatory system would bring signiifcant beneifts and opportunities for China. Finaly, this paper recommends additional measures like training and grants to improve the private’s sector effectiveness in co-regulating China’s food safety issues.

  12. Investigation report from the commission for energy regulation about the outage of Saturday November 4, 2006

    International Nuclear Information System (INIS)

    2007-01-01

    On November 4, 2006, a large-scale incident occurred on the European high-voltage interconnected power network which left 15 million people without electricity in Western Europe during about 2 hours. Considering the European dimension of the outage, the European Regulators Group for Electricity and Gas (ERGEG) conducted an investigation, the final report of which being made publically available on February 6, 2007. Considering the impact of this incident on the French territory, the French commission for energy regulation (CRE) decided as soon as November 5, 2006 to carry out its own investigation in order to inform the French consumers about the chronology of facts and the precise causes of this incident. This document summarises the CRE's report and presents its conclusions and recommendations as well as the technical report of the incident

  13. Respirator studies for the Nuclear Regulatory Commission. Protection factors for supplied-air respirators. Progress report, October 1, 1976--September 30, 1977

    International Nuclear Information System (INIS)

    Hack, A.; Bradley, O.D.; Trujillo, A.

    1977-12-01

    This report describes the work performed during FY 1977 for the Nuclear Regulatory Commission. The Protection Factors (efficiency) provided by 25 NIOSH approved supplied-air respirators were determined while the devices were worn by a panel of anthropometrically selected test subjects. The major recommendation was that demand-type respirators should neither be used nor approved

  14. Reactor safety research program. A description of current and planned reactor safety research sponsored by the Nuclear Regulatory Commission's Division of Reactor Safety Research

    International Nuclear Information System (INIS)

    1975-06-01

    The reactor safety research program, sponsored by the Nuclear Regulatory Commission's Division of Reactor Safety Research, is described in terms of its program objectives, current status, and future plans. Elements of safety research work applicable to water reactors, fast reactors, and gas cooled reactors are presented together with brief descriptions of current and planned test facilities. (U.S.)

  15. Government Performance and Results Act: Performance plan FY 1999, U.S. Nuclear Regulatory Commission. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Fuches, J.L.

    1998-02-01

    The Nuclear Regulatory Commission`s (NRC) strategic plan [NUREG-1614, Vol. 1, September 1997] establishes a strategic framework that will guide future decision-making and will help the NRC continue to meet its responsibility for protecting public health and safety, promoting the common defense and security, and protecting the environment. This performance plan complements the agency`s strategic plan by setting annual goals with measurable target levels of performance for FY 1999, as required by the Government Performance and Results Act. No significant contribution was made to the preparation of the performance plan by any non-Federal entity. However, a contractor was used to help facilitate discussions and resolution of issues. Within six months after the close of FY 1999, the NRC will submit to the President and the Congress a report on program performance for FY 1999. This performance report will review the success of the agency in achieving the performance goals established for FY 1999. Where those goals have been achieved, the underlying assumptions and strategies will be examined to ensure that continued applicability is warranted in the future. If any of the FY 1999 performance goals are not met, the agency will conduct a thorough analysis of why it did not meet the goal and the actions necessary to meet-the goal in the future. One result of this analysis will be the documentation of plans and schedules for achieving the established performance goal. If the analysis should indicate that the performance goal is impractical or infeasible, the performance report will document why that is the case and what action is recommended.

  16. Ground-water protection activities of the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    1987-02-01

    This report evaluates the internal consistency of NRC's ground-water protection programs. These programs have evolved consistently with growing public concerns about the significance of ground-water contamination and environmental impacts. Early NRC programs provided for protection of the public health and safety by minimizing releases of radionuclides. More recent programs have included provisions for minimizing releases of nonradiological constituents, mitigating environmental impacts, and correcting ground-water contamination. NRC's ground-water protection programs are categorized according to program areas, including nuclear materials and waste management (NMSS), nuclear reactor operation (NRR), confirmatory research and standards development (RES), inspection and enforcement (IE), and agreement state programs (SP). Based on analysis of existing ground-water protection programs within NRC, the interoffice Ground-water Protection Group has identified several inconsistencies between and within program areas. These inconsistencies include: (1) different definitions of the term ''ground-water,'' (2) variable regulation of nonradiological constituents in ground water, (3) different design periods for ground-water protection, and (4) different scopes and rigor of ground-water assessments. The second inconsistency stems from differences in statutory authority granted to the NRC. The third inconsistency is rationalized by recognizing differences in perceived risks associated with nuclear facilities. The Ground-water Protection Group will document its analysis of the remaining inconsistencies and make recommendations to reconcile or eliminate them in a subsequent report

  17. The evolving regulation of uranium recovery operations in the United States: Inovative approaches are necessary for cost effective regulatory oversight

    International Nuclear Information System (INIS)

    Thompson, A.J.; Lehrenbaum, W.U.; Lashway, D.C.

    2000-01-01

    The US domestic uranium industry is at a crossroads. Historic low prices for uranium, combined with stringent and often irrational regulatory requirements, pose a very real threat to the industry's continued viability. The Nuclear Regulatory Commission has taken a number of innovative steps to reform and rationalize its regulatory program. However, if the domestic uranium recovery industry is to remain viable, additional steps toward innovation and reform are needed, and effective implementation of reforms adopted by the Commission is essential. (author)

  18. Regulation for continuous improvements - the new regulatory strategy of SKI

    International Nuclear Information System (INIS)

    Hoegberg, L.; Svensson, G.; Viktorsson, C.

    1998-01-01

    This paper describes the new regulatory objectives and strategy of the Swedish Nuclear Power Inspectorate. Factors that have influenced the development of the regulatory strategy, including an international peer review, are discussed. In addition to general technical requirements for a defence in depth, the new strategy strongly focuses on the quality of plant safety management processes, to be monitored by process-oriented inspections. Also, quality assurance of regulatory activities is stressed. Experience gained so far shows that the regulatory approach chosen in Sweden promotes utility self assessment, quality of safety management and ownership of safety work within the utility staff. (author)

  19. U.S. Nuclear Regulatory Commission Extremely Low Probability of Rupture pilot study: xLPR framework model user's guide

    International Nuclear Information System (INIS)

    Kalinich, Donald A.; Sallaberry, Cedric M.; Mattie, Patrick D.

    2010-01-01

    For the U.S. Nuclear Regulatory Commission (NRC) Extremely Low Probability of Rupture (xLPR) pilot study, Sandia National Laboratories (SNL) was tasked to develop and evaluate a probabilistic framework using a commercial software package for Version 1.0 of the xLPR Code. Version 1.0 of the xLPR code is focused assessing the probability of rupture due to primary water stress corrosion cracking in dissimilar metal welds in pressurizer surge nozzles. Future versions of this framework will expand the capabilities to other cracking mechanisms, and other piping systems for both pressurized water reactors and boiling water reactors. The goal of the pilot study project is to plan the xLPR framework transition from Version 1.0 to Version 2.0; hence the initial Version 1.0 framework and code development will be used to define the requirements for Version 2.0. The software documented in this report has been developed and tested solely for this purpose. This framework and demonstration problem will be used to evaluate the commercial software's capabilities and applicability for use in creating the final version of the xLPR framework. This report details the design, system requirements, and the steps necessary to use the commercial-code based xLPR framework developed by SNL.

  20. Description of Multimedia Environment Pollutant Assessment System (MEPAS) version 3.2 modification for the Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Buck, J.W.; Strenge, D.L.; Hoopes, B.L.

    1997-11-01

    The Multimedia Environmental Pollutant Assessment System (MEPAS) is a software tool developed by Pacific Northwest National Laboratory (PNNL) for the U.S. Department of Energy (DOE) to allow DOE to conduct human health risk analyses nation-wide. This report describes modifications to the MEPAS to meet the requirements of the U.S. Nuclear Regulatory Commission (NRC) staff in their analyses of Site Decommissioning Management Plan sites. In general, these modifications provide the MEPAS, Version 3.2, with the capability of calculating and reporting annual dose/risk information. Modifications were made to the exposure pathway and health impact modules and the water and atmospheric transport modules. Several example cases used to test the MEPAS, Version 3.2, are also presented. The MEPAS, Version 3.2, also contains a new source-term release component that includes models for estimating contaminant loss from three different types of source zones (contaminated aquifer, contaminated pond/surface impoundment, and contaminated vadose zone) due to decay/degradation, leaching, wind suspension, water erosion, overland flow, and/or volatilization. When multiple loss routes are assumed to occur simultaneously, the models account for their interaction and calculate an appropriate pollutant mass budget to each loss route over time