WorldWideScience

Sample records for project requirements document

  1. Supplemental design requirements document, Project W026

    International Nuclear Information System (INIS)

    Weidert, J.R.

    1993-01-01

    This document supplements and extends the Functional Design Criteria, SP-W026-FDC-001, for the Waste Receiving and Processing Facility (WRAP), Module 1. It provides additional detailed requirements, summarizes key Westinghouse Hanford Company design guidance, and establishes baseline technical agreements to be used in definitive design of the WRAP-1 facility. Revision 3 of the Supplemental Design Requirements Document has been assigned an Impact Level of 3ESQ based on the content of the entire revision. The actual changes made from Revision 2 have an Impact Level of 3S and the basis for these changes was previously reviewed and approved per WHC correspondence No. 9355770

  2. Project W-441 cold vacuum drying facility design requirements document

    International Nuclear Information System (INIS)

    O'Neill, C.T.

    1997-01-01

    This document has been prepared and is being released for Project W-441 to record the design basis for the design of the Cold Vacuum Drying Facility. This document sets forth the physical design criteria, Codes and Standards, and functional requirements that were used in the design of the Cold Vacuum Drying Facility. This document contains section 3, 4, 6, and 9 of the Cold Vacuum Drying Facility Design Requirements Document. The remaining sections will be issued at a later date. The purpose of the Facility is to dry, weld, and inspect the Multi-Canister Overpacks before transport to dry storage

  3. Preliminary Design Requirements Document for Project W-314

    Energy Technology Data Exchange (ETDEWEB)

    MCGREW, D.L.

    2000-04-27

    This document sets forth functional requirements, performance requirements, and design constraints for the tank farm systems elements identified in Section 3.1 of this document. These requirements shall be used to develop the Design Requirements Baseline for those system elements. System Overview--The tank farm system at Hanford Site currently consists of 149 single shell tanks and 28 double shell tanks with associated facilities and equipment, located in 18 separate groupings. Each grouping is known as a tank farm. They are located in the areas designated as 200 West and 200 East. Table 1-1 shows the number of tanks in each farm. The farms are connected together through a transfer system consisting of piping, diversion boxes, Double Contained Receiver Tanks (DCRT) and other miscellaneous facilities and elements. The tank farm system also connects to a series of processing plants which generate radioactive and hazardous wastes. The primary functions of the tank farm system are to store, transfer, concentrate, and characterize radioactive and hazardous waste generated at Hanford, until the waste can be safely retrieved, processed and dispositioned. The systems provided by Project W-314 support the store and transfer waste functions. The system elements to be upgraded by Project W-314 are identified in Section 3.1.

  4. Preliminary Design Requirements Document for Project W-314

    International Nuclear Information System (INIS)

    MCGREW, D.L.

    2000-01-01

    This document sets forth functional requirements, performance requirements, and design constraints for the tank farm systems elements identified in Section 3.1 of this document. These requirements shall be used to develop the Design Requirements Baseline for those system elements. System Overview--The tank farm system at Hanford Site currently consists of 149 single shell tanks and 28 double shell tanks with associated facilities and equipment, located in 18 separate groupings. Each grouping is known as a tank farm. They are located in the areas designated as 200 West and 200 East. Table 1-1 shows the number of tanks in each farm. The farms are connected together through a transfer system consisting of piping, diversion boxes, Double Contained Receiver Tanks (DCRT) and other miscellaneous facilities and elements. The tank farm system also connects to a series of processing plants which generate radioactive and hazardous wastes. The primary functions of the tank farm system are to store, transfer, concentrate, and characterize radioactive and hazardous waste generated at Hanford, until the waste can be safely retrieved, processed and dispositioned. The systems provided by Project W-314 support the store and transfer waste functions. The system elements to be upgraded by Project W-314 are identified in Section 3.1

  5. Design requirements document for Project W-465, immobilized low-activity waste interim storage

    International Nuclear Information System (INIS)

    Burbank, D.A.

    1998-01-01

    The scope of this Design Requirements Document (DRD) is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste (ILAW) produced by the privatized Tank Waste Remediation System (TWRS) treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the TWRS ILAW Interim Storage facility project and provides traceability from the program level requirements to the project design activity. Technical and programmatic risk associated with the TWRS planning basis are discussed in the Tank Waste Remediation System Decisions and Risk Assessment (Johnson 1994). The design requirements provided in this document will be augmented by additional detailed design data documented by the project

  6. Design requirements document for project W-520, immobilized low-activity waste disposal

    International Nuclear Information System (INIS)

    Ashworth, S.C.

    1998-01-01

    This design requirements document (DRD) identifies the functions that must be performed to accept, handle, and dispose of the immobilized low-activity waste (ILAW) produced by the Tank Waste Remediation System (TWRS) private treatment contractors and close the facility. It identifies the requirements that are associated with those functions and that must be met. The functional and performance requirements in this document provide the basis for the conceptual design of the Tank Waste Remediation System Immobilized Low-Activity Waste disposal facility project (W-520) and provides traceability from the program-level requirements to the project design activity

  7. Design requirements document for project W-520, immobilized low-activity waste disposal

    Energy Technology Data Exchange (ETDEWEB)

    Ashworth, S.C.

    1998-08-06

    This design requirements document (DRD) identifies the functions that must be performed to accept, handle, and dispose of the immobilized low-activity waste (ILAW) produced by the Tank Waste Remediation System (TWRS) private treatment contractors and close the facility. It identifies the requirements that are associated with those functions and that must be met. The functional and performance requirements in this document provide the basis for the conceptual design of the Tank Waste Remediation System Immobilized Low-Activity Waste disposal facility project (W-520) and provides traceability from the program-level requirements to the project design activity.

  8. Supplemental design requirements document enhanced radioactive and mixed waste storage Phase V Project W-112

    International Nuclear Information System (INIS)

    Ocampo, V.P.; Boothe, G.F.; Greager, T.M.; Johnson, K.D.; Kooiker, S.L.; Martin, J.D.

    1994-11-01

    This document provides additional and supplemental information to WHC-SD-W112-FDC-001, Project W-112 for radioactive and mixed waste storage. It provides additional requirements for the design and summarizes Westinghouse Hanford Company key design guidance and establishes the technical baseline agreements to be used for definitive design of the Project W-112 facilities

  9. Preliminary design requirements document (DRD) for Project W-236B, ''Initial Pretreatment Module''

    International Nuclear Information System (INIS)

    Swanson, L.M.

    1995-01-01

    The scope of this Design Requirements Document (DRD) is to identify and define the functions, with associated requirements, which must be performed to separate Hanford Site tank waste supernatants into low-level and high-level fractions. This documents sets forth function requirements, performance requirements, and design constraints necessary to begin conceptual design for the Initial Pretreatment Module (IPM). System and physical interfaces between the IPM project and the Tank Waste Remediation System (TWRS) are identified. The constraints, performance requirements, and transfer of information and data across a technical interface will be documented in an Interface Control Document. Supplemental DRDs will be prepared to provide more detailed requirements specific to systems described in the DRD

  10. Project W-236A, work plan for preparation of a design requirements document

    International Nuclear Information System (INIS)

    Groth, B.D.

    1995-01-01

    This work plan outlines the tasks necessary, and defines the organizational responsibilities for preparing a Design Requirements Document (DRD) for project W-236A, Multi-Function Waste Tank Facility (MWTF). A DRD is a Systems Engineering document which bounds, at a high level, the requirements of a discrete system element of the Tank Waste Remediation System (TWRS) Program. This system element is usually assigned to a specific project, in this case the MWTF. The DRD is the document that connects the TWRS program requirements with the highest level projects requirements and provides the project's link to the overall TWRS mission. The MWTF DRD effort is somewhat unique in that the project is already in detailed design, whereas a DRO is normally prepared prior to preliminary design. The MWTF design effort was initiated with a Functional Design Criteria (FDC) and a Supplemental Design Requirements Document (SDRD) bounding the high level requirements. Another unique aspect of this effort is that some of the TWRS program requirements are still in development. Because of these unique aspects of the MWTF DRD development, the MWTF will be developed from existing TWRS Program requirements and project specific requirements contained in the FDC and SDRD. The following list describes the objectives of the MWTF DRD: determine the primary functions of the tanks through a functional decomposition of the TWRS Program high level functions; allocate the primary functions to a sub-system architecture for the tanks; define the fundamental design features in terms of performance requirements for the system and subsystems; identify system interfaces and design constraints; and document the results in a DRD

  11. Supplmental design requirements document enhanced radioactive and mixed waste storage: Phase 5, Project W-113

    International Nuclear Information System (INIS)

    Ocampo, V.P.

    1994-11-01

    This Supplemental Design Requirements Document (SDRD) is used to communicate Project W-113 specific plant design information from Westinghouse Hanford Company (WHC) to the United States Department of Energy (DOE) and the cognizant Architect Engineer (A/E). The SDRD is prepared after the completion of the project Conceptual Design report (CDR) and prior to the initiation of definitive design. Information in the SDRD serves two purposes: to convey design requirements that are too detailed for inclusion in the Functional Design Criteria (FDC) report and to serve as a means of change control for design commitments in the Title I and Title II design. The Solid Waste Retrieval Project (W-113) SDRD has been restructured from the equipment based outline used in previous SDRDs to a functional systems outline. This was done to facilitate identification of deficiencies in the information provided in the initial draft SDRD and aid design confirmation. The format and content of this SDRD adhere as closely as practicable to the requirements of WHC-CM-6-1, Standard Engineering Practices for Functional Design Criteria

  12. TRANSPORTATION SYSTEM REQUIREMENTS DOCUMENT

    International Nuclear Information System (INIS)

    2004-01-01

    This document establishes the Transportation system requirements for the U.S. Department of Energy's (DOE's) Civilian Radioactive Waste Management System (CRWMS). These requirements are derived from the Civilian Radioactive Waste Management System Requirements Document (CRD). The Transportation System Requirements Document (TSRD) was developed in accordance with LP-3.1Q-OCRWM, Preparation, Review, and Approval of Office of National Transportation Level-2 Baseline Requirements. As illustrated in Figure 1, the TSRD forms a part of the DOE Office of Civilian Radioactive Waste Management (OCRWM) Technical Baseline

  13. Transportation System Requirements Document

    International Nuclear Information System (INIS)

    1993-09-01

    This Transportation System Requirements Document (Trans-SRD) describes the functions to be performed by and the technical requirements for the Transportation System to transport spent nuclear fuel (SNF) and high-level radioactive waste (HLW) from Purchaser and Producer sites to a Civilian Radioactive Waste Management System (CRWMS) site, and between CRWMS sites. The purpose of this document is to define the system-level requirements for Transportation consistent with the CRWMS Requirement Document (CRD). These requirements include design and operations requirements to the extent they impact on the development of the physical segments of Transportation. The document also presents an overall description of Transportation, its functions, its segments, and the requirements allocated to the segments and the system-level interfaces with Transportation. The interface identification and description are published in the CRWMS Interface Specification

  14. Human Document Project

    NARCIS (Netherlands)

    de Vries, Jeroen; Abelmann, Leon; Manz, A; Elwenspoek, Michael Curt

    2012-01-01

    “The Human Document Project‿ is a project which tries to answer all of the questions related to preserving information about the human race for tens of generations of humans to come or maybe even for a future intelligence which can emerge in the coming thousands of years. This document mainly

  15. Supplemental design requirements document, Multifunction Waste Tank Facility, Project W-236A. Revision 1

    International Nuclear Information System (INIS)

    Groth, B.D.

    1995-01-01

    The Multi-Function Waste Tank Facility (MWTF) consists of four, nominal 1 million gallon, underground double-shell tanks, located in the 200-East area, and two tanks of the same capacity in the 200-West area. MWTF will provide environmentally safe storage capacity for wastes generated during remediation/retrieval activities of existing waste storage tanks. This document delineates in detail the information to be used for effective implementation of the Functional Design Criteria requirements

  16. Lifecycle management for nuclear engineering project documents

    International Nuclear Information System (INIS)

    Zhang Li; Zhang Ming; Zhang Ling

    2010-01-01

    The nuclear engineering project documents with great quantity and various types of data, in which the relationships of each document are complex, the edition of document update frequently, are managed difficultly. While the safety of project even the nuclear safety is threatened seriously by the false documents and mistakes. In order to ensure the integrality, veracity and validity of project documents, the lifecycle theory of document is applied to build documents center, record center, structure and database of document lifecycle management system. And the lifecycle management is used to the documents of nuclear engineering projects from the production to pigeonhole, to satisfy the quality requirement of nuclear engineering projects. (authors)

  17. Functions and requirements document, WESF decoupling project, low-level liquid waste system

    Energy Technology Data Exchange (ETDEWEB)

    Rasmussen, J.H., Fluor Daniel Hanford

    1997-02-27

    The Waste Encapsulation and Storage Facility (WESF) was constructed in 1974 to encapsulate and store cesium and strontium which were isolated at B Plant from underground storage tank waste. The WESF, Building 225-B, is attached physically to the west end of B Plant, Building 221-B, 200 East area. The WESF currently utilizes B Plant facilities for disposing liquid and solid waste streams. With the deactivation of B Plant, the WESF Decoupling Project will provide replacement systems allowing WESF to continue operations independently from B Plant. Four major systems have been identified to be replaced by the WESF Decoupling Project, including the following: Low Level Liquid Waste System, Solid Waste Handling System, Liquid Effluent Control System, and Deionized Water System.

  18. NRC review of Electric Power Research Institute's Advanced Light Reactor Utility Requirements Document - Program summary, Project No. 669

    International Nuclear Information System (INIS)

    1992-08-01

    The staff of the US Nuclear Regulatory Commission has prepared Volume 1 of a safety evaluation report (SER), ''NRC Review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document -- Program Summary,'' to document the results of its review of the Electric Power Research Institute's ''Advanced Light Water Reactor Utility Requirements Document.'' This SER provides a discussion of the overall purpose and scope of the Requirements Document, the background of the staff's review, the review approach used by the staff, and a summary of the policy and technical issues raised by the staff during its review

  19. The European Utility Requirement Document

    International Nuclear Information System (INIS)

    Roche, I.I.

    1999-01-01

    The major European electricity producers work on a common requirement document for future LWR plants since 1992. They aim at requirements acceptable together by the owners, the public and the authorities. Thus the designers can develop standard LWR designs acceptable everywhere in Europe and the utilities can open their consultations to vendors on common bases. Such a standardisation promotes an improvement of generation costs and of safety : public and authorities acceptance should be improved as well ; significant savings are expected in development and construction costs. Since the early stages of the project, the EUR group has grown significantly. It now includes utilities from nine European countries. Utilities from two other European countries are joining the group. Specific cooperation agreements are also in progress with a few extra-European partners

  20. Waste management system requirements document

    International Nuclear Information System (INIS)

    1991-02-01

    This volume defines the top level requirements for the Mined Geologic Disposal System (MGDS). It is designed to be used in conjunction with Volume 1 of the WMSR, General System Requirements. It provides a functional description expanding the requirements allocated to the MGDS in Volume 1 and elaborates on each requirement by providing associated performance criteria as appropriate. Volumes 1 and 4 of the WMSR provide a minimum set of requirements that must be satisfied by the final MGDS design. This document sets forth specific requirements that must be fulfilled. It is not the intent or purpose of this top level document to describe how each requirement is to be satisfied in the final MGDS design. Each subsequent level of the technical document hierarchy must provide further guidance and definition as to how each of these requirements is to be implemented in the design. It is expected that each subsequent level of requirements will be significantly more detailed. Section 2 of this volume provides a functional description of the MGDS. Each function is addressed in terms of requirements, and performance criteria. Section 3 provides a list of controlling documents. Each document cited in a requirement of Chapter 2 is included in this list and is incorporated into this document as a requirement on the final system. The WMSR addresses only federal requirements (i.e., laws, regulations and DOE orders). State and local requirements are not addressed. However, it will be specifically noted at the potentially affected WMSR requirements that there could be additional or more stringent regulations imposed by a state or local requirements or administering agency over the cited federal requirements

  1. Waste Management System Requirement document

    International Nuclear Information System (INIS)

    1990-04-01

    This volume defines the top level technical requirements for the Monitored Retrievable Storage (MRS) facility. It is designed to be used in conjunction with Volume 1, General System Requirements. Volume 3 provides a functional description expanding the requirements allocated to the MRS facility in Volume 1 and, when appropriate, elaborates on requirements by providing associated performance criteria. Volumes 1 and 3 together convey a minimum set of requirements that must be satisfied by the final MRS facility design without unduly constraining individual design efforts. The requirements are derived from the Nuclear Waste Policy Act of 1982 (NWPA), the Nuclear Waste Policy Amendments Act of 1987 (NWPAA), the Environmental Protection Agency's (EPA) Environmental Standards for the Management and Disposal of Spent Nuclear Fuel (40 CFR 191), NRC Licensing Requirements for the Independent Storage of Spent Nuclear and High-Level Radioactive Waste (10 CFR 72), and other federal statutory and regulatory requirements, and major program policy decisions. This document sets forth specific requirements that will be fulfilled. Each subsequent level of the technical document hierarchy will be significantly more detailed and provide further guidance and definition as to how each of these requirements will be implemented in the design. Requirements appearing in Volume 3 are traceable into the MRS Design Requirements Document. Section 2 of this volume provides a functional breakdown for the MRS facility. 1 tab

  2. Tank Waste Remediation System Projects Document Control Plan

    International Nuclear Information System (INIS)

    Slater, G.D.; Halverson, T.G.

    1994-01-01

    The purpose of this Tank Waste Remediation System Projects Document Control Plan is to provide requirements and responsibilities for document control for the Hanford Waste Vitrification Plant (HWVP) Project and the Initial Pretreatment Module (IPM) Project

  3. From document to database: modernizing requirements management

    International Nuclear Information System (INIS)

    Giajnorio, J.; Hamilton, S.

    2007-01-01

    The creation, communication, and management of design requirements are central to the successful completion of any large engineering project, both technically and commercially. Design requirements in the Canadian nuclear industry are typically numbered lists in multiple documents created using word processing software. As an alternative, GE Nuclear Products implemented a central requirements management database for a major project at Bruce Power. The database configured the off-the-shelf software product, Telelogic Doors, to GE's requirements structure. This paper describes the advantages realized by this scheme. Examples include traceability from customer requirements through to test procedures, concurrent engineering, and automated change history. (author)

  4. Project Documentation as a Risk for Public Projects

    Directory of Open Access Journals (Sweden)

    Vladěna Štěpánková

    2015-08-01

    Full Text Available Purpose of the article: The paper presents the different methodologies used for creating documentation and focuses on public projects and their requirements for this documentation. Since documentation is also incorporated in the overall planning of the project and its duration is estimated using expert qualified estimate, can any change in this documentation lead to project delays, or increase its cost as a result of consuming administration, and therefore the documentation is seen as a risk, which may threaten the project as a public contract by which a company trying to achieve and obtains it, and generally any project. Methodology/methods: There are used methods of obtaining information in this paper. These are mainly structured interviews in combination with a brainstorming, furthermore also been used questionnaire for companies dealing with public procurement. As a data processing program was used MS Excel and basic statistical methods based on regression analysis. Scientific aim: The article deals with the construction market in the Czech Republic and examines the impact of changes in project documentation of public projects on their turnover. Findings: In this paper we summarize the advantages and disadvantages of having project documentation. In the case of public contracts and changes in legislation it is necessary to focus on creating documentation in advance, follow the new requirements and try to reach them in the shortest possible time. Conclusions: The paper concludes with recommendations on how to proceed, if these changes and how to reduce costs, which may cause the risk of documentation.

  5. The Darfur Atrocities Documentation Project

    Science.gov (United States)

    Totten, Samuel

    2004-01-01

    One of the many important aspects of the Darfur Atrocities Documentation Project was that it set a precedent for what the U.S. and/or other nations can, and should do, when future cases of potential genocide arise. Far too often in the recent past, the international community (the United Nations, individual governments, many nongovernmental…

  6. Documentation requirements for radiation sterilization

    DEFF Research Database (Denmark)

    Miller, A.

    1995-01-01

    Several standards are recently approved or are under development by the standard organizations ISO and CEN in the field of radiation sterilization. Particularly in Europe these standards define new requirements on some issues and on other issues they emphasize the necessary documentation for appr......Several standards are recently approved or are under development by the standard organizations ISO and CEN in the field of radiation sterilization. Particularly in Europe these standards define new requirements on some issues and on other issues they emphasize the necessary documentation...... for approval of radiation sterilized products. The impact of these standards on the radiation sterilization is discussed, with special attention given to a few special issues, mainly traceability and uncertainty of measurement results....

  7. Monitored Geologic Repository Project Description Document

    International Nuclear Information System (INIS)

    Curry, P. M.

    2001-01-01

    The primary objective of the Monitored Geologic Repository Project Description Document (PDD) is to allocate the functions, requirements, and assumptions to the systems at Level 5 of the Civilian Radioactive Waste Management System (CRWMS) architecture identified in Section 4. It provides traceability of the requirements to those contained in Section 3 of the ''Monitored Geologic Repository Requirements Document'' (MGR RD) (YMP 2000a) and other higher-level requirements documents. In addition, the PDD allocates design related assumptions to work products of non-design organizations. The document provides Monitored Geologic Repository (MGR) technical requirements in support of design and performance assessment in preparing for the Site Recommendation (SR) and License Application (LA) milestones. The technical requirements documented in the PDD are to be captured in the System Description Documents (SDDs) which address each of the systems at Level 5 of the CRWMS architecture. The design engineers obtain the technical requirements from the SDDs and by reference from the SDDs to the PDD. The design organizations and other organizations will obtain design related assumptions directly from the PDD. These organizations may establish additional assumptions for their individual activities, but such assumptions are not to conflict with the assumptions in the PDD. The PDD will serve as the primary link between the technical requirements captured in the SDDs and the design requirements captured in US Department of Energy (DOE) documents. The approved PDD is placed under Level 3 baseline control by the CRWMS Management and Operating Contractor (M and O) and the following portions of the PDD constitute the Technical Design Baseline for the MGR: the design characteristics listed in Table 1-1, the MGR Architecture (Section 4.1), the Technical Requirements (Section 5), and the Controlled Project Assumptions (Section 6)

  8. World energy projection system: Model documentation

    Science.gov (United States)

    1992-06-01

    The World Energy Project System (WEPS) is an accounting framework that incorporates projects from independently documented models and assumptions about the future energy intensity of economic activity (ratios of total energy consumption divided by gross domestic product) and about the rate of incremental energy requirements met by hydropower, geothermal, coal, and natural gas to produce projections of world energy consumption published annually by the Energy Information Administration (EIA) in the International Energy Outlook (IEO). Two independently documented models presented in Figure 1, the Oil Market Simulation (OMS) model and the World Integrated Nuclear Evaluation System (WINES), provide projections of oil and nuclear power consumption published in the IEO. Output from a third independently documented model, and the International Coal Trade Model (ICTM), is not published in the IEO but is used in WEPS as a supply check on projections of world coal consumption produced by WEPS and published in the IEO. A WEPS model of natural gas production documented in this report provides the same type of implicit supply check on the WEPS projections of world natural gas consumption published in the IEO. Two additional models are included in Figure 1, the OPEC Capacity model and the Non-OPEC Oil Production model. These WEPS models provide inputs to the OMS model and are documented in this report.

  9. World energy projection system: Model documentation

    International Nuclear Information System (INIS)

    1992-06-01

    The World Energy Project System (WEPS) is an accounting framework that incorporates projects from independently documented models and assumptions about the future energy intensity of economic activity (ratios of total energy consumption divided by gross domestic product) and about the rate of incremental energy requirements met by hydropower, geothermal, coal, and natural gas to produce projections of world energy consumption published annually by the Energy Information Administration (EIA) in the International Energy Outlook (IEO) (Figure 1). Two independently documented models presented in Figure 1, the Oil Market Simulation (OMS) model and the World Integrated Nuclear Evaluation System (WINES) provide projections of oil and nuclear power consumption published in the IEO. Output from a third independently documented model, and the International Coal Trade Model (ICTM), is not published in the IEO but is used in WEPS as a supply check on projections of world coal consumption produced by WEPS and published in the IEO. A WEPS model of natural gas production documented in this report provides the same type of implicit supply check on the WEPS projections of world natural gas consumption published in the IEO. Two additional models are included in Figure 1, the OPEC Capacity model and the Non-OPEC Oil Production model. These WEPS models provide inputs to the OMS model and are documented in this report

  10. Hanford Tanks Initiative requirements and document management process guide

    International Nuclear Information System (INIS)

    Schaus, P.S.

    1998-01-01

    This revision of the guide provides updated references to project management level Program Management and Assessment Configuration Management activities, and provides working level directions for submitting requirements and project documentation related to the Hanford Tanks Initiative (HTI) project. This includes documents and information created by HTI, as well as non-HTI generated materials submitted to the project

  11. Managing Requirements-Documents to Data

    Science.gov (United States)

    Orr, Kevin; Hudson, Abe

    2017-01-01

    Managing Requirements on long term projects like International Space Station (ISS) can go thru many phases, from initial product development to almost over 20 years of operations and sustainment. Over that time many authorized changes have been made to the requirement set, that apply to any new systems that would visit the ISS today, like commercial cargo/crew vehicles or payloads. Explore the benefits of managing requirements in a database while satisfying traditional documents needs for contracts and stakeholder/user consumption that are not tied into the database.

  12. Monitored Geologic Repository Project Description Document

    International Nuclear Information System (INIS)

    Curry, P.

    2000-01-01

    The primary objective of the Monitored Geologic Repository Project Description Document (PDD) is to allocate the functions, requirements, and assumptions to the systems at Level 5 of the Civilian Radioactive Waste Management System (CRWMS) architecture identified in Section 4. It provides traceability of the requirements to those contained in Section 3 of the ''Monitored Geologic Repository Requirements Document'' (MGR RD) (CRWMS M and O 2000b) and other higher-level requirements documents. In addition, the PDD allocates design related assumptions to work products of non-design organizations. The document provides Monitored Geologic Repository (MGR) engineering design basis in support of design and performance assessment in preparing for the Site Recommendation (SR) and License Application (LA) milestones. The engineering design basis documented in the PDD is to be captured in the System Description Documents (SDDs) which address each of the systems at Level 5 of the CRWMS architecture. The design engineers obtain the engineering design basis from the SDDs and by reference from the SDDs to the PDD. The design organizations and other organizations will obtain design related assumptions directly from the PDD. These organizations may establish additional assumptions for their individual activities, but such assumptions are not to conflict with the assumptions in the PDD. The PDD will serve as the primary link between the engineering design basis captured in the SDDs and the design requirements captured in U.S. Department of Energy (DOE) documents. The approved PDD is placed under Level 3 baseline control by the CRWMS Management and Operating Contractor (M and O) and the following portions of the PDD constitute the Technical Design Baseline for the MGR: the design characteristics listed in Table 2-1, the MGR Architecture (Section 4.1),the Engineering Design Bases (Section 5), and the Controlled Project Assumptions (Section 6)

  13. Waste Management System Requirements Document

    International Nuclear Information System (INIS)

    1992-02-01

    This DCP establishes an interim plan for the Office of Civilian Radioactive Waste Management (OCRWM) technical baseline until the results of the OCRWM Document Hierarchy Task Force can be implemented. This plan is needed to maintain continuity in the Program for ongoing work in the areas of Waste Acceptance, Transportation, Monitored Retrievable Storage (MRS) and Yucca Mountain Site Characterization

  14. NRC review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document - Evolutionary plant designs, Chapter 1, Project No. 669

    International Nuclear Information System (INIS)

    1992-08-01

    The staff of the US Nuclear Regulatory Commission has prepared Volume 2 (Parts 1 and 2) of a safety evaluation report (SER), ''NRC Review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document -- Evolutionary Plant Designs,'' to document the results of its review of the Electric Power Research Institute's ''Advanced Light Water Reactor Utility Requirements Document.'' This SER gives the results of the staff's review of Volume II of the Requirements Document for evolutionary plant designs, which consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant (approximately 1300 megawatts-electric)

  15. NRC review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document - Evolutionary plant designs, Chapters 2--13, Project No. 669

    International Nuclear Information System (INIS)

    1992-08-01

    The staff of the US Nuclear Regulatory Commission has prepared Volume 2 (Parts 1 and 2) of a safety evaluation report (SER), ''NRC Review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document -- Evolutionary Plant Designs,'' to document the results of its review of the Electric Power Research Institute's ''Advanced Light Water Reactor Utility Requirements Document.'' This SER gives the results of the staff's review of Volume II of the Requirements Document for evolutionary plant designs, which consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant (approximately 1300 megawatts-electric)

  16. Civilian Radioactive Waste Management System Requirements Document

    International Nuclear Information System (INIS)

    1992-12-01

    This document specifies the top-level requirements for the Civilian Radioactive Waste Management System (CRWMS). The document is referred to herein as the CRD, for CRWMS Requirements document. The OCRWM System Engineering Management Plan (SEMP) establishes the technical document hierarchy (hierarchy of technical requirements and configuration baseline documents) for the CRWMS program. The CRD is the top-level document in this hierarchy. The immediate subordinate documents are the System Requirements Documents (SRDS) for the four elements of the CRWMS and the Interface Specification (IFS). The four elements of the CRWMS are the Waste Acceptance System, the Transportation System, the Monitored Retrievable Storage (MRS) System and the Mined Geologic Disposal System (MGDS). The Interface Specification describes the six inter-element interfaces between the four elements. This hierarchy establishes the requirements to be addressed by the design of the system elements. Many of the technical requirements for the CRWMS are documented in a variety of Federal regulations, DOE directives and other Government documentation. It is the purpose of the CRD to establish the technical requirements for the entire program. In doing so, the CRD summarizes source documentation for requirements that must be addressed by the program, specifies particular requirements, and documents derived requirements that are not covered in regulatory and other Government documentation, but are necessary to accomplish the mission of the CRWMS. The CRD defines the CRWMS by identifying the top-level functions the elements must perform (These top-level functions were derived using functional analysis initially documented in the Physical System Requirements (PSR) documents). The CRD also defines the top-level physical architecture of the system and allocates the functions and requirements to the architectural elements of the system

  17. Requirements in engineering projects

    CERN Document Server

    Fernandes, João M

    2016-01-01

    This book focuses on various topics related to engineering and management of requirements, in particular elicitation, negotiation, prioritisation, and documentation (whether with natural languages or with graphical models). The book provides methods and techniques that help to characterise, in a systematic manner, the requirements of the intended engineering system.  It was written with the goal of being adopted as the main text for courses on requirements engineering, or as a strong reference to the topics of requirements in courses with a broader scope. It can also be used in vocational courses, for professionals interested in the software and information systems domain.   Readers who have finished this book will be able to: - establish and plan a requirements engineering process within the development of complex engineering systems; - define and identify the types of relevant requirements in engineering projects; - choose and apply the most appropriate techniques to elicit the requirements of a giv...

  18. World Energy Projection System model documentation

    International Nuclear Information System (INIS)

    Hutzler, M.J.; Anderson, A.T.

    1997-09-01

    The World Energy Projection System (WEPS) was developed by the Office of Integrated Analysis and Forecasting within the Energy Information Administration (EIA), the independent statistical and analytical agency of the US Department of Energy. WEPS is an integrated set of personal computer based spreadsheets containing data compilations, assumption specifications, descriptive analysis procedures, and projection models. The WEPS accounting framework incorporates projections from independently documented models and assumptions about the future energy intensity of economic activity (ratios of total energy consumption divided by gross domestic product GDP), and about the rate of incremental energy requirements met by natural gas, coal, and renewable energy sources (hydroelectricity, geothermal, solar, wind, biomass, and other renewable resources). Projections produced by WEPS are published in the annual report, International Energy Outlook. This report documents the structure and procedures incorporated in the 1998 version of the WEPS model. It has been written to provide an overview of the structure of the system and technical details about the operation of each component of the model for persons who wish to know how WEPS projections are produced by EIA

  19. World Energy Projection System model documentation

    Energy Technology Data Exchange (ETDEWEB)

    Hutzler, M.J.; Anderson, A.T.

    1997-09-01

    The World Energy Projection System (WEPS) was developed by the Office of Integrated Analysis and Forecasting within the Energy Information Administration (EIA), the independent statistical and analytical agency of the US Department of Energy. WEPS is an integrated set of personal computer based spreadsheets containing data compilations, assumption specifications, descriptive analysis procedures, and projection models. The WEPS accounting framework incorporates projections from independently documented models and assumptions about the future energy intensity of economic activity (ratios of total energy consumption divided by gross domestic product GDP), and about the rate of incremental energy requirements met by natural gas, coal, and renewable energy sources (hydroelectricity, geothermal, solar, wind, biomass, and other renewable resources). Projections produced by WEPS are published in the annual report, International Energy Outlook. This report documents the structure and procedures incorporated in the 1998 version of the WEPS model. It has been written to provide an overview of the structure of the system and technical details about the operation of each component of the model for persons who wish to know how WEPS projections are produced by EIA.

  20. Mined Geologic Disposal System Requirements Document

    International Nuclear Information System (INIS)

    1993-01-01

    This Mined Geologic Disposal System Requirements document (MGDS-RD) describes the functions to be performed by, and the requirements for, a Mined Geologic Disposal System (MGDS) for the permanent disposal of spent nuclear fuel (SNF) and commercial and defense high level radioactive waste (HLW) in support of the Civilian Radioactive Waste Management System (CRWMS). The development and control of the MGDS-RD is quality-affecting work and is subject to the Department of Energy (DOE) Office of Civilian Radioactive Waste Management (OCRWM) Quality Assurance Requirements Document (QARD). As part of the technical requirements baseline, it is also subject to Baseline Management Plan controls. The MGDS-RD and the other program-level requirements documents have been prepared and managed in accordance with the Technical Document Preparation Plan (TDPP) for the Preparation of System Requirements Documents

  1. NRC review of Electric Power Research Institute's advanced light water reactor utility requirements document. Passive plant designs, chapter 1, project number 669

    International Nuclear Information System (INIS)

    1994-08-01

    The Electric Power Research Institute (EPRI) is preparing a compendium of technical requirements, referred to as the open-quotes Advanced Light Water Reactor [ALWR] Utility Requirements Documentclose quotes, that is acceptable to the design of an ALWR power plant. When completed, this document is intended to be a comprehensive statement of utility requirements for the design, construction, and performance of an ALWR power plant for the 1990s and beyond. The Requirements Document consists of three volumes. Volume 1, open-quotes ALWR Policy and Summary of Top-Tier Requirementsclose quotes, is a management-level synopsis of the Requirements Document, including the design objectives and philosophy, the overall physical configuration and features of a future nuclear plant design, and the steps necessary to take the proposed ALWR design criteria beyond the conceptual design state to a completed, functioning power plant. Volume II consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant [approximately 1350 megawatts-electric (MWe)]. Volume III contains utility design requirements for nuclear plants for which passive features will be used in their designs (approximately 600 MWe). In April 1992, the staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, issued Volume 1 and Volume 2 (Parts 1 and 2) of its safety evaluation report (SER) to document the results of its review of Volumes 1 and 2 of the Requirements Document. Volume 1, open-quotes NRC Review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document - Program Summaryclose quotes, provided a discussion of the overall purpose and scope of the Requirements Document, the background of the staff's review, the review approach used by the staff, and a summary of the policy and technical issues raised by the staff during its review

  2. NRC review of Electric Power Research Institute's advanced light water reactor utility requirements document. Passive plant designs, chapters 2-13, project number 669

    International Nuclear Information System (INIS)

    1994-08-01

    The Electric Power Research Institute (EPRI) is preparing a compendium of technical requirements, referred to as the open-quotes Advanced Light Water Reactor [ALWR] Utility Requirements Documentclose quotes, that is acceptable to the design of an ALWR power plant. When completed, this document is intended to be a comprehensive statement of utility requirements for the design, construction, and performance of an ALWR power plant for the 1990s and beyond. The Requirements Document consists of three volumes. Volume I, open-quotes ALWR Policy and Summary of Top-Tier Requirementsclose quotes, is a management-level synopsis of the Requirements Document, including the design objectives and philosophy, the overall physical configuration and features of a future nuclear plant design, and the steps necessary to take the proposed ALWR design criteria beyond the conceptual design state to a completed, functioning power plant. Volume II consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant [approximately 1350 megawatts-electric (MWe)]. Volume III contains utility design requirements for nuclear plants for which passive features will be used in their designs (approximately 600 MWe). In April 1992, the staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, issued Volume 1 and Volume 2 (Parts 1 and 2) of its safety evaluation report (SER) to document the results of its review of Volumes 1 and 2 of the Requirements Document. Volume 1, open-quotes NRC Review of Electric Power Research Institute's Advanced Light Water Reactor Utility Requirements Document - Program Summaryclose quotes, provided a discussion of the overall purpose and scope of the Requirements Document, the background of the staff's review, the review approach used by the staff, and a summary of the policy and technical issues raised by the staff during its review

  3. Spent Nuclear Fuel Project Document Management Plan

    International Nuclear Information System (INIS)

    Connor, M.D.; Harizison, G.L.; Rice, W.C.

    1995-12-01

    The SNF Project Document Management Plan identifies and describes the currently available systems and processes for implementing and maintaining an effective document control and records management program. This program governs the methods by which documents are generated, released, distributed, maintained current, retired, and ultimately disposed

  4. Document Management Projects: implementation guide

    Directory of Open Access Journals (Sweden)

    Beatriz Bagoin Guimarães

    2016-12-01

    Full Text Available Records Management System implementation is a complex process that needs to be executed by a multidisciplinary team and involves components of apparently non-related areas such as archival science, computer engineering, law, project management and human resource management. All of them are crucial and complementary to guarantee a full and functional implementation of a system and a perfect fusion with the connected processes and procedures. The purpose of this work is to provide organizations with a basic guide to Records Management Project implementation beginning with the steps prior to acquiring the system, following with the main project activities and concluding with the post implementation procedures of continuous improvement and system maintenance.

  5. Document Management Projects: implementation guide

    OpenAIRE

    Beatriz Bagoin Guimarães

    2016-01-01

    Records Management System implementation is a complex process that needs to be executed by a multidisciplinary team and involves components of apparently non-related areas such as archival science, computer engineering, law, project management and human resource management. All of them are crucial and complementary to guarantee a full and functional implementation of a system and a perfect fusion with the connected processes and procedures. The purpose of this work is to provide organizations...

  6. TWRS configuration management requirement source document

    International Nuclear Information System (INIS)

    Vann, J.M.

    1997-01-01

    The TWRS Configuration Management (CM) Requirement Source document prescribes CM as a basic product life-cycle function by which work and activities are conducted or accomplished. This document serves as the requirements basis for the TWRS CM program. The objective of the TWRS CM program is to establish consistency among requirements, physical/functional configuration, information, and documentation for TWRS and TWRS products, and to maintain this consistency throughout the life-cycle of TWRS and the product, particularly as changes are being made

  7. Fiscal year 1999 waste information requirements document

    International Nuclear Information System (INIS)

    Adams, M.R.

    1998-01-01

    The Waste Information Requirements Document (WIRD) has the following purposes: To describe the overall drivers that require characterization information and to document their source; To define how characterization is going to satisfy the drivers, close issues, and measure and report progress; and To describe deliverables and acceptance criteria for characterization. Characterization information is required to maintain regulatory compliance, perform operations and maintenance, resolve safety issues, and prepare for disposal of waste. Commitments addressing these requirements are derived from the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement; the Recommendation 93-5 Implementation Plan (DOE-RL 1996a) to the Defense Nuclear Facilities Safety Board (DNFSB); and other requirement sources listed in Section 2.0. The Waste Information Requirements Document replaces the tank waste analysis plans and the tank characterization plan previously required by the Tri-Party Agreement, Milestone M-44-01 and M-44-02 series

  8. Waste Acceptance System Requirements document (WASRD)

    International Nuclear Information System (INIS)

    1993-01-01

    This Waste Acceptance System Requirements document (WA-SRD) describes the functions to be performed and the technical requirements for a Waste Acceptance System for accepting spent nuclear fuel (SNF) and high-level radioactive waste (HLW) into the Civilian Radioactive Waste Management System (CRWMS). This revision of the WA-SRD addresses the requirements for the acceptance of HLW. This revision has been developed as a top priority document to permit DOE's Office of Environmental Restoration and Waste Management (EM) to commence waste qualification runs at the Savannah River Site's (SRS) Defense Waste Processing Facility (DWPF) in a timely manner. Additionally, this revision of the WA-SRD includes the requirements from the Physical System Requirements -- Accept Waste document for the acceptance of SNF. A subsequent revision will fully address requirements relative to the acceptance of SNF

  9. ISS Crew Transportation and Services Requirements Document

    Science.gov (United States)

    Bayt, Robert L. (Compiler); Lueders, Kathryn L. (Compiler)

    2016-01-01

    The ISS Crew Transportation and Services Requirements Document (CCT-REQ-1130) contains all technical, safety, and crew health medical requirements that are mandatory for achieving a Crew Transportation System Certification that will allow for International Space Station delivery and return of NASA crew and limited cargo. Previously approved on TN23183.

  10. Monitored Retrievable Storage System Requirements Document

    International Nuclear Information System (INIS)

    1994-03-01

    This Monitored Retrievable Storage System Requirements Document (MRS-SRD) describes the functions to be performed and technical requirements for a Monitored Retrievable Storage (MRS) facility subelement and the On-Site Transfer and Storage (OSTS) subelement. The MRS facility subelement provides for temporary storage, at a Civilian Radioactive Waste Management System (CRWMS) operated site, of spent nuclear fuel (SNF) contained in an NRC-approved Multi-Purpose Canister (MPC) storage mode, or other NRC-approved storage modes. The OSTS subelement provides for transfer and storage, at Purchaser sites, of spent nuclear fuel (SNF) contained in MPCs. Both the MRS facility subelement and the OSTS subelement are in support of the CRWMS. The purpose of the MRS-SRD is to define the top-level requirements for the development of the MRS facility and the OSTS. These requirements include design, operation, and decommissioning requirements to the extent they impact on the physical development of the MRS facility and the OSTS. The document also presents an overall description of the MRS facility and the OSTS, their functions (derived by extending the functional analysis documented by the Physical System Requirements (PSR) Store Waste Document), their segments, and the requirements allocated to the segments. In addition, the top-level interface requirements of the MRS facility and the OSTS are included. As such, the MRS-SRD provides the technical baseline for the MRS Safety Analysis Report (SAR) design and the OSTS Safety Analysis Report design

  11. Mined Geologic Disposal System Requirements Document

    International Nuclear Information System (INIS)

    1994-03-01

    This Mined Geologic Disposal System Requirements Document (MGDS-RD) describes the functions to be performed by, and the requirements for, a Mined Geologic Disposal System (MGDS) for the permanent disposal of spent nuclear fuel (SNF) (including SNF loaded in multi-purpose canisters (MPCs)) and commercial and defense high-level radioactive waste (HLW) in support of the Civilian Radioactive Waste Management System (CRWMS). The purpose of the MGDS-RD is to define the program-level requirements for the design of the Repository, the Exploratory Studies Facility (ESF), and Surface Based Testing Facilities (SBTF). These requirements include design, operation, and decommissioning requirements to the extent they impact on the physical development of the MGDS. The document also presents an overall description of the MGDS, its functions (derived using the functional analysis documented by the Physical System Requirements (PSR) documents as a starting point), its segments as described in Section 3.1.3, and the requirements allocated to the segments. In addition, the program-level interfaces of the MGDS are identified. As such, the MGDS-RD provides the technical baseline for the design of the MGDS

  12. Making project documentation a positive tool for management

    International Nuclear Information System (INIS)

    Shirley, C.G.

    1986-01-01

    Sandia National Laboratories is constructing Particle Beam Fusion Accelerator II, a research facility built as a major project of the U.S. Department of Energy and theoretically capable of controlled nuclear fusion. To manage technical development, the project team has evolved a documentation system with both conventional and unconventional elements. Project documentation is functional because it is usable and authoritative. Usability results from layering by audience and purpose, appropriate sequence and format, accessibility, directness, and currency. Authority results from comprehensiveness, document control, insistence on written requirements, and consistency in applying procedures. As basic communication models illustrate, every document needs a producer, a recipient, a subject, and a feedback path. Managers can promote functional documentation by planning for feedback, using fulltime documentors wisely, setting priorities, planning for effective data collection, and treating documentation as a subproject

  13. 200 Area Deactivation Project Facilities Authorization Envelope Document

    International Nuclear Information System (INIS)

    DODD, E.N.

    2000-01-01

    Project facilities as required by HNF-PRO-2701, Authorization Envelope and Authorization Agreement. The Authorization Agreements (AA's) do not identify the specific set of environmental safety and health requirements that are applicable to the facility. Therefore, the facility Authorization Envelopes are defined here to identify the applicable requirements. This document identifies the authorization envelopes for the 200 Area Deactivation

  14. Guidance and Control Software Project Data - Volume 2: Development Documents

    Science.gov (United States)

    Hayhurst, Kelly J. (Editor)

    2008-01-01

    The Guidance and Control Software (GCS) project was the last in a series of software reliability studies conducted at Langley Research Center between 1977 and 1994. The technical results of the GCS project were recorded after the experiment was completed. Some of the support documentation produced as part of the experiment, however, is serving an unexpected role far beyond its original project context. Some of the software used as part of the GCS project was developed to conform to the RTCA/DO-178B software standard, "Software Considerations in Airborne Systems and Equipment Certification," used in the civil aviation industry. That standard requires extensive documentation throughout the software development life cycle, including plans, software requirements, design and source code, verification cases and results, and configuration management and quality control data. The project documentation that includes this information is open for public scrutiny without the legal or safety implications associated with comparable data from an avionics manufacturer. This public availability has afforded an opportunity to use the GCS project documents for DO-178B training. This report provides a brief overview of the GCS project, describes the 4-volume set of documents and the role they are playing in training, and includes the development documents from the GCS project. Volume 2 contains three appendices: A. Guidance and Control Software Development Specification; B. Design Description for the Pluto Implementation of the Guidance and Control Software; and C. Source Code for the Pluto Implementation of the Guidance and Control Software

  15. Guidance and Control Software Project Data - Volume 1: Planning Documents

    Science.gov (United States)

    Hayhurst, Kelly J. (Editor)

    2008-01-01

    The Guidance and Control Software (GCS) project was the last in a series of software reliability studies conducted at Langley Research Center between 1977 and 1994. The technical results of the GCS project were recorded after the experiment was completed. Some of the support documentation produced as part of the experiment, however, is serving an unexpected role far beyond its original project context. Some of the software used as part of the GCS project was developed to conform to the RTCA/DO-178B software standard, "Software Considerations in Airborne Systems and Equipment Certification," used in the civil aviation industry. That standard requires extensive documentation throughout the software development life cycle, including plans, software requirements, design and source code, verification cases and results, and configuration management and quality control data. The project documentation that includes this information is open for public scrutiny without the legal or safety implications associated with comparable data from an avionics manufacturer. This public availability has afforded an opportunity to use the GCS project documents for DO-178B training. This report provides a brief overview of the GCS project, describes the 4-volume set of documents and the role they are playing in training, and includes the planning documents from the GCS project. Volume 1 contains five appendices: A. Plan for Software Aspects of Certification for the Guidance and Control Software Project; B. Software Development Standards for the Guidance and Control Software Project; C. Software Verification Plan for the Guidance and Control Software Project; D. Software Configuration Management Plan for the Guidance and Control Software Project; and E. Software Quality Assurance Activities.

  16. Supplemental design requirements document solid waste operations complex

    International Nuclear Information System (INIS)

    Ocampo, V.P.; Boothe, G.F.; Broz, D.R.; Eaton, H.E.; Greager, T.M.; Huckfeldt, R.A.; Kooiker, S.L.; Lamberd, D.L.; Lang, L.L.; Myers, J.B.

    1994-11-01

    This document provides additional and supplemental information to the WHC-SD-W112-FDC-001, WHC-SD-W113-FDC-001, and WHC-SD-W100-FDC-001. It provides additional requirements for the design and summarizes Westinghouse Hanford Company key design guidance and establishes the technical baseline agreements to be used for definitive design common to the Solid Waste Operations Complex (SWOC) Facilities (Project W-112, Project W-113, and WRAP 2A)

  17. Guidance and Control Software Project Data - Volume 3: Verification Documents

    Science.gov (United States)

    Hayhurst, Kelly J. (Editor)

    2008-01-01

    The Guidance and Control Software (GCS) project was the last in a series of software reliability studies conducted at Langley Research Center between 1977 and 1994. The technical results of the GCS project were recorded after the experiment was completed. Some of the support documentation produced as part of the experiment, however, is serving an unexpected role far beyond its original project context. Some of the software used as part of the GCS project was developed to conform to the RTCA/DO-178B software standard, "Software Considerations in Airborne Systems and Equipment Certification," used in the civil aviation industry. That standard requires extensive documentation throughout the software development life cycle, including plans, software requirements, design and source code, verification cases and results, and configuration management and quality control data. The project documentation that includes this information is open for public scrutiny without the legal or safety implications associated with comparable data from an avionics manufacturer. This public availability has afforded an opportunity to use the GCS project documents for DO-178B training. This report provides a brief overview of the GCS project, describes the 4-volume set of documents and the role they are playing in training, and includes the verification documents from the GCS project. Volume 3 contains four appendices: A. Software Verification Cases and Procedures for the Guidance and Control Software Project; B. Software Verification Results for the Pluto Implementation of the Guidance and Control Software; C. Review Records for the Pluto Implementation of the Guidance and Control Software; and D. Test Results Logs for the Pluto Implementation of the Guidance and Control Software.

  18. AFSC Laboratory Management Information Requirements Project

    National Research Council Canada - National Science Library

    1982-01-01

    This document was developed under the auspices of the Laboratory IRM (LIRM) Management Working Group in response to AFSC Program Directive 0008-81-1, Management Information Requirement Project (23 February 1981...

  19. Leveraging Text Content for Management of Construction Project Documents

    Science.gov (United States)

    Alqady, Mohammed

    2012-01-01

    The construction industry is a knowledge intensive industry. Thousands of documents are generated by construction projects. Documents, as information carriers, must be managed effectively to ensure successful project management. The fact that a single project can produce thousands of documents and that a lot of the documents are generated in a…

  20. PROJECT ENGINEERING DATA MANAGEMENT AT AUTOMATED PREPARATION OF DESIGN DOCUMENTATION

    Directory of Open Access Journals (Sweden)

    A. V. Guryanov

    2017-01-01

    Full Text Available We have developed and realized instrumental means for automated support of end-to-end design process for design documentation on a product at the programming level. The proposed decision is based on processing of the engineering project data that are contained in interdependent design documents: tactical technical characteristics of products, data on the valuable metals contained in them, the list of components applied in a product and others. Processing of engineering data is based on their conversion to the form provided by requirements of industry standards for design documentation preparation. The general graph of the design documentation developed on a product is provided. The description of the developed software product is given. Automated preparation process of interdependent design documents is shown on the example of preparation of purchased products list. Results of work can be used in case of research and development activities on creation of perspective samples of ADP equipment.

  1. Project structure plan requirements for the deconstruction projects

    International Nuclear Information System (INIS)

    Petrasch, Peter; Schmitt, Christian; Stapf, Meike

    2011-01-01

    The deconstruction of nuclear facilities requires due to the particular conditions and the size of the project a special project planning. The authors analyze the possible requirements to be fulfilled by a project structure plan for nuclear facilities, including personnel resources, organization structure, budget questions, operation and project oriented measures, possibility of modifications and supplements. Further topics include controlling and project realization procedures, documentation, third party activities (authorities, consultants, surveyors), logistics and transport, and radiation protection issues. Several questions remain for plants-specific planning, including the integration of the plant personnel, administrative work, project management, economic and financial issues, radioactive waste management issues.

  2. Video-documentation: 'The Pannonic ozon project'

    International Nuclear Information System (INIS)

    Loibl, W.; Cabela, E.; Mayer, H. F.; Schmidt, M.

    1998-07-01

    Goal of the project was the production of a video film as documentation of the Pannonian Ozone Project- POP. The main part of the video describes the POP-model consisting of the modules meteorology, emissions and chemistry, developed during the POP-project. The model considers the European emission patterns of ozone precursors and the actual wind fields. It calculates ozone build up and depletion within air parcels due to emission and weather situation along trajectory routes. Actual ozone concentrations are calculated during model runs simulating the photochemical processes within air parcels moving along 4 day trajectories before reaching the Vienna region. The model computations were validated during extensive ground and aircraft-based measurements of ozone precursors and ozone concentration within the POP study area. Scenario computations were used to determine how much ozone can be reduced in north-eastern Austria by emissions control measures. The video lasts 12:20 minutes and consists of computer animations and life video scenes, presenting the ozone problem in general, the POP model and the model results. The video was produced in co-operation by the Austrian Research Center Seibersdorf - Department of Environmental Planning (ARCS) and Joanneum Research - Institute of Informationsystems (JR). ARCS was responsible for idea, concept, storyboard and text while JR was responsible for computer animation and general video production. The speaker text was written with scientific advice by the POP - project partners: Institute of Meteorology and Physics, University of Agricultural Sciences- Vienna, Environment Agency Austria - Air Quality Department, Austrian Research Center Seibersdorf- Environmental Planning Department/System Research Division. The film was produced as German and English version. (author)

  3. 13. Project Management Documentation and Communications

    DEFF Research Database (Denmark)

    Kampf, Constance Elizabeth

    2014-01-01

    This chapter discusses the relationship between documentation and communication practices in organizational contexts.......This chapter discusses the relationship between documentation and communication practices in organizational contexts....

  4. Project W-320, 241-C-106 sluicing supporting documentation bibliography

    International Nuclear Information System (INIS)

    Bailey, J.W.

    1998-01-01

    This supporting document has been prepared to make the listing of documentation used to develop, or in support of Project W-320, readily retrievable. All documents are sorted by document number and list the document type. Tank 241-C-106 has been included on the High Heat Load Watch List

  5. Fluor Daniel Hanford contract standards/requirements identification document

    Energy Technology Data Exchange (ETDEWEB)

    Bennett, G.L.

    1997-04-24

    This document, the Standards/Requirements Identification Document (S/RID) for the Fluor Daniel Hanford Contract, represents the necessary and sufficient requirements to provide an adequate level of protection of the worker, public health and safety, and the environment.

  6. Fluor Daniel Hanford company standards requirements identification document

    International Nuclear Information System (INIS)

    Bennett, G.L.

    1997-01-01

    This document, the Standards/Requirements Identification Document (S/RID) for the Fluor Daniel Hanford Contract, represents the necessary and sufficient requirements to provide an adequate level of protection of the worker, public health and safety, and the environment

  7. Fiscal year 1997-1998 waste information requirements document

    International Nuclear Information System (INIS)

    Poppiti, J.A.

    1997-01-01

    The Waste Information Requirements Document describes the activities of the Tank Waste Remediation System (TWRS) Characterization Project that provide characterization information on Hanford Site waste tanks. The characterization information is required to perform operations and meet the commitments of TWRS end users. These commitments are derived from the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement; the Recommendation 93-5 Implementation Plan to the Defense Nuclear Facilities Safety Board (DNFSB); and other directives as listed in Section 4.0. This Waste Information Requirement Document applies to Fiscal Years 1997 and 1998 activities. Its contents are based on the best information available in August 1997. The format and content are based on the directions of DOE-RL (Sieracki, 1997) and Fluor Daniel Hanford Incorporated (Umek, 1997). Activities, such as the revision of the Tank Characterization Technical Sampling Basis (Brown et al. 1997), the revision of the data quality objectives (DQOs), issue closures, discussions with Ecology, and management decisions may cause subsequent updates to the Waste Information Requirements Document

  8. 22 CFR 40.71 - Documentation requirements for immigrants.

    Science.gov (United States)

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false Documentation requirements for immigrants. 40... NONIMMIGRANTS AND IMMIGRANTS UNDER THE IMMIGRATION AND NATIONALITY ACT, AS AMENDED Documentation Requirements § 40.71 Documentation requirements for immigrants. INA 212(a)(7)(A) is not applicable at the time of...

  9. Tank waste remediation system functions and requirements document

    International Nuclear Information System (INIS)

    Carpenter, K.E

    1996-01-01

    This is the Tank Waste Remediation System (TWRS) Functions and Requirements Document derived from the TWRS Technical Baseline. The document consists of several text sections that provide the purpose, scope, background information, and an explanation of how this document assists the application of Systems Engineering to the TWRS. The primary functions identified in the TWRS Functions and Requirements Document are identified in Figure 4.1 (Section 4.0) Currently, this document is part of the overall effort to develop the TWRS Functional Requirements Baseline, and contains the functions and requirements needed to properly define the top three TWRS function levels. TWRS Technical Baseline information (RDD-100 database) included in the appendices of the attached document contain the TWRS functions, requirements, and architecture necessary to define the TWRS Functional Requirements Baseline. Document organization and user directions are provided in the introductory text. This document will continue to be modified during the TWRS life-cycle

  10. Tank waste remediation system functions and requirements document

    Energy Technology Data Exchange (ETDEWEB)

    Carpenter, K.E

    1996-10-03

    This is the Tank Waste Remediation System (TWRS) Functions and Requirements Document derived from the TWRS Technical Baseline. The document consists of several text sections that provide the purpose, scope, background information, and an explanation of how this document assists the application of Systems Engineering to the TWRS. The primary functions identified in the TWRS Functions and Requirements Document are identified in Figure 4.1 (Section 4.0) Currently, this document is part of the overall effort to develop the TWRS Functional Requirements Baseline, and contains the functions and requirements needed to properly define the top three TWRS function levels. TWRS Technical Baseline information (RDD-100 database) included in the appendices of the attached document contain the TWRS functions, requirements, and architecture necessary to define the TWRS Functional Requirements Baseline. Document organization and user directions are provided in the introductory text. This document will continue to be modified during the TWRS life-cycle.

  11. Making project documentation a positive tool for management

    International Nuclear Information System (INIS)

    Shirley, C.G.

    1985-01-01

    Since 1980, Sandia National Laboratory has been designing and constructing Particle Beam Fusion Accelerator II. One managerial challenge of a large project is the problem of handling information. The scope of the PBFA-II projet may be gauged by its cost: $19.4 million for the accelerator itself, $9.5 million for buildings and standard utilities, and $9.6 million for specialized utilities and support systems. The first need of the project at its outset, then, was communication, and this remains a chief function of the CPO. If the nature or magnitude of the risk changes in any one area, the entire project team must know. If a design is changed, persons working on interdependent efforts must know. Some of this communication takes place naturally and informally. But project procedures must guarantee that all important communication is received by all necessary people, that the communication creates accountability, and that management receives timely, accurate reports. To put it another way, important communication requires project documentation. Documentation is both a record of the project and a tool for management

  12. Spectrum analysis on quality requirements consideration in software design documents.

    Science.gov (United States)

    Kaiya, Haruhiko; Umemura, Masahiro; Ogata, Shinpei; Kaijiri, Kenji

    2013-12-01

    Software quality requirements defined in the requirements analysis stage should be implemented in the final products, such as source codes and system deployment. To guarantee this meta-requirement, quality requirements should be considered in the intermediate stages, such as the design stage or the architectural definition stage. We propose a novel method for checking whether quality requirements are considered in the design stage. In this method, a technique called "spectrum analysis for quality requirements" is applied not only to requirements specifications but also to design documents. The technique enables us to derive the spectrum of a document, and quality requirements considerations in the document are numerically represented in the spectrum. We can thus objectively identify whether the considerations of quality requirements in a requirements document are adapted to its design document. To validate the method, we applied it to commercial software systems with the help of a supporting tool, and we confirmed that the method worked well.

  13. Performance assurance of the re-applying project documentation

    Science.gov (United States)

    Kozlova, Olga

    2017-10-01

    Usage of the re-applying project documentation is cost effective measure. Saving of budgetary funds for purchases for development of new project documentation occurs by means of it. It also becomes possible to consider better decisions and prevent the repetition of mistakes. Nowadays, state authorities in construction management are forming separate institute for re-applying project documentation. The article shows the main tasks of such events and the issues to be solved for achievement of a high positive result.

  14. Civilian Radioactive Waste Management System Requirements Document (CRP)

    International Nuclear Information System (INIS)

    C.A. Kouts

    2006-01-01

    The CRD addresses the requirements of Department of Energy (DOE) Order 413.3-Change 1, ''Program and Project Management for the Acquisition of Capital Assets'', by providing the Secretarial Acquisition Executive (Level 0) scope baseline and the Program-level (Level 1) technical baseline. The Secretarial Acquisition Executive approves the Office of Civilian Radioactive Waste Management's (OCRWM) critical decisions and changes against the Level 0 baseline; and in turn, the OCRWM Director approves all changes against the Level 1 baseline. This baseline establishes the top-level technical scope of the CRMWS and its three system elements, as described in section 1.3.2. The organizations responsible for design, development, and operation of system elements described in this document must therefore prepare subordinate project-level documents that are consistent with the CRD. Changes to requirements will be managed in accordance with established change and configuration control procedures. The CRD establishes requirements for the design, development, and operation of the CRWMS. It specifically addresses the top-level governing laws and regulations (e.g., ''Nuclear Waste Policy Act'' (NWPA), 10 Code of Federal Regulations (CFR) Part 63, 10 CFR Part 71, etc.) along with specific policy, performance requirements, interface requirements, and system architecture. The CRD shall be used as a vehicle to incorporate specific changes in technical scope or performance requirements that may have significant program implications. Such may include changes to the program mission, changes to operational capability, and high visibility stakeholder issues. The CRD uses a systems approach to: (1) identify key functions that the CRWMS must perform, (2) allocate top-level requirements derived from statutory, regulatory, and programmatic sources, and (3) define the basic elements of the system architecture and operational concept. Project-level documents address CRD requirements by further

  15. Online mass storage system detailed requirements document

    Science.gov (United States)

    1976-01-01

    The requirements for an online high density magnetic tape data storage system that can be implemented in a multipurpose, multihost environment is set forth. The objective of the mass storage system is to provide a facility for the compact storage of large quantities of data and to make this data accessible to computer systems with minimum operator handling. The results of a market survey and analysis of candidate vendor who presently market high density tape data storage systems are included.

  16. Spent Nuclear Fuel Project document control and Records Management Program Description

    International Nuclear Information System (INIS)

    MARTIN, B.M.

    2000-01-01

    The Spent Nuclear Fuel (SNF) Project document control and records management program, as defined within this document, is based on a broad spectrum of regulatory requirements, Department of Energy (DOE) and Project Hanford and SNF Project-specific direction and guidance. The SNF Project Execution Plan, HNF-3552, requires the control of documents and management of records under the auspices of configuration control, conduct of operations, training, quality assurance, work control, records management, data management, engineering and design control, operational readiness review, and project management and turnover. Implementation of the controls, systems, and processes necessary to ensure compliance with applicable requirements is facilitated through plans, directives, and procedures within the Project Hanford Management System (PHMS) and the SNF Project internal technical and administrative procedures systems. The documents cited within this document are those which directly establish or define the SNF Project document control and records management program. There are many peripheral documents that establish requirements and provide direction pertinent to managing specific types of documents that, for the sake of brevity and clarity, are not cited within this document

  17. FIREX mission requirements document for renewable resources

    Science.gov (United States)

    Carsey, F.; Dixon, T.

    1982-01-01

    The initial experimental program and mission requirements for a satellite synthetic aperture radar (SAR) system FIREX (Free-Flying Imaging Radar Experiment) for renewable resources is described. The spacecraft SAR is a C-band and L-band VV polarized system operating at two angles of incidence which is designated as a research instrument for crop identification, crop canopy condition assessments, soil moisture condition estimation, forestry type and condition assessments, snow water equivalent and snow wetness assessments, wetland and coastal land type identification and mapping, flood extent mapping, and assessment of drainage characteristics of watersheds for water resources applications. Specific mission design issues such as the preferred incidence angles for vegetation canopy measurements and the utility of a dual frequency (L and C-band) or dual polarization system as compared to the baseline system are addressed.

  18. CH2M Hill Hanford Group, Inc., Standards and Requirements Identification Document (SRID) Requirements Management System and Requirements Specification

    International Nuclear Information System (INIS)

    JOHNSON, A.L.

    2000-01-01

    The current Tank Farm Contractor (TFC) for the U. S. Department of Energy, Office of River Protection (ORP), River Protection Project (RPP), CH2M Hill Hanford Group, Inc. (CHG), will use a computer based requirements management system. The system will serve as a tool to assist in identifying, capturing, and maintaining the Standards/Requirements Identification Document (S/RID) requirements and links to implementing procedures and other documents. By managing requirements as one integrated set, CHG will be able to carry out its mission more efficiently and effectively. CHG has chosen the Dynamic Object Oriented Requirements System (DOORS(trademark)) as the preferred computer based requirements management system. Accordingly, the S/RID program will use DOORS(trademark). DOORS(trademark) will replace the Environmental Requirements Management Interface (ERMI) system as the tool for S/RID data management. The DOORS(trademark) S/RID test project currently resides on the DOORSTM test server. The S/RID project will be migrated to the DOORS(trademark) production server. After the migration the S/RID project will be considered a production project and will no longer reside on the test server

  19. Databases in the documentation management for big industrial projects

    International Nuclear Information System (INIS)

    Cauchet, A.; Chevillard, F.; Parisot, Y.; Tirefort, C.

    1990-05-01

    The documentation management of a big industrial project involves a continuous update of information, both in the study and realization phase or in the operation phase. The organization of the technical documentation for big industrial projects requests complex information systems. In the first part of this paper are presented the methods appropriate for the analysis of documentation management procedures and in the second part are presented the tools by the combination of which a documentation system for the user is provided. The case of the documentation centres for the Hague reprocessing plant is described

  20. Technical requirements document for the waste flow analysis

    International Nuclear Information System (INIS)

    Shropshire, D.E.

    1996-05-01

    Purpose of this Technical Requirements Document is to define the top level customer requirements for the Waste Flow Analysis task. These requirements, once agreed upon with DOE, will be used to flow down subsequent development requirements to the model specifications. This document is intended to be a ''living document'' which will be modified over the course of the execution of this work element. Initial concurrence with the technical functional requirements from Environmental Management (EM)-50 is needed before the work plan can be developed

  1. Richland Environmental Restoration Project management action process document

    International Nuclear Information System (INIS)

    1996-04-01

    This document is the prescribed means for providing direct input to the US Department of Energy Headquarters regarding the status, accomplishments, strategy, and issues of the Richland Environmental Restoration Project. The project mission, organizational interfaces, and operational history of the Hanford Site are provided. Remediation strategies are analyzed in detail. The document includes a status of Richland Environmental Restoration project activities and accomplishments, and it presents current cost summaries, schedules, and technical baselines

  2. Richland Environmental Restoration Project management action process document

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-04-01

    This document is the prescribed means for providing direct input to the US Department of Energy Headquarters regarding the status, accomplishments, strategy, and issues of the Richland Environmental Restoration Project. The project mission, organizational interfaces, and operational history of the Hanford Site are provided. Remediation strategies are analyzed in detail. The document includes a status of Richland Environmental Restoration project activities and accomplishments, and it presents current cost summaries, schedules, and technical baselines.

  3. Transportation system requirements document. Revision 1 DCN01. Supplement

    International Nuclear Information System (INIS)

    1995-05-01

    The original Transportation System Requirements Document described the functions to be performed by and the technical requirements for the Transportation System to transport spent nuclear fuel (SNF) and high-level radioactive waste (HLW) from Purchaser and Producer sites to a Civilian Radioactive Waste Management System (CRWMS) site, and between CRWMS sites. The purpose of that document was to define the system-level requirements. These requirements include design and operations requirements to the extent they impact on the development of the physical segments of Transportation. The document also presented an overall description of Transportation, its functions, its segments, and the requirements allocated to the segments and the system-level interfaces with Transportation. This revision of the document contains only the pages that have been modified

  4. Documentation assessment, Project C-018H, 200-E area effluent treatment facility

    International Nuclear Information System (INIS)

    Peres, M.W.; Connor, M.D.; Mertelendy, J.I.

    1994-01-01

    Project C-018H is one of the fourteen subprojects to the Hanford Environmental Compliance (HEC) Project. Project C-018H provides treatment and disposal for the 242-A Evaporator and PUREX plant process condensate waste streams. This project used the Integrated Management Team (IMT) approach proposed by RL. The IMT approach included all affected organizations on the project team to coordinate and execute all required project tasks, while striving to integrate and satisfy all technical, operational, functional, and organizational objectives. The HEC Projects were initiated in 1989. Project C-018H began in early 1990, with completion of construction currently targeted for mid-1995. This assessment was performed to evaluate the effectiveness of the management control on design documents and quality assurance records developed and submitted for processing, use, and retention for the Project. The assessment focused primarily on the overall adequacy and quality of the design documentation currently being submitted to the project document control function

  5. Using electronic document management systems to manage highway project files.

    Science.gov (United States)

    2011-12-12

    "WisDOTs Bureau of Technical Services is interested in learning about the practices of other state departments of : transportation in developing and implementing an electronic document management system to manage highway : project files"

  6. Functions and requirements document for interim store solidified high-level and transuranic waste

    Energy Technology Data Exchange (ETDEWEB)

    Smith-Fewell, M.A., Westinghouse Hanford

    1996-05-17

    The functions, requirements, interfaces, and architectures contained within the Functions and Requirements (F{ampersand}R) Document are based on the information currently contained within the TWRS Functions and Requirements database. The database also documents the set of technically defensible functions and requirements associated with the solidified waste interim storage mission.The F{ampersand}R Document provides a snapshot in time of the technical baseline for the project. The F{ampersand}R document is the product of functional analysis, requirements allocation and architectural structure definition. The technical baseline described in this document is traceable to the TWRS function 4.2.4.1, Interim Store Solidified Waste, and its related requirements, architecture, and interfaces.

  7. Documentation and verification required for type A packaging use

    Energy Technology Data Exchange (ETDEWEB)

    O`Brien, J.H.

    1997-07-30

    This document furnishes knowledge and methods for verifying compliance with the U.S. Department of Transportation (DOT) packaging requirements for shipping Type A quantities of radioactive material. The primary emphasis is on the requirements identified in 49 CFR 173.415(a), which states, ``Each offeror of a Specification 7A package must maintain on file for at least one year after the shipment, and shall provide to DOT on request, complete documentation of tests and an engineering evaluation of comparative data showing that the construction methods, packaging design, and materials of construction comply with that specification.`` This guidance document uses a checklist to show compliance.

  8. Documentation and verification required for type A packaging use

    International Nuclear Information System (INIS)

    O'Brien, J.H.

    1997-01-01

    This document furnishes knowledge and methods for verifying compliance with the U.S. Department of Transportation (DOT) packaging requirements for shipping Type A quantities of radioactive material. The primary emphasis is on the requirements identified in 49 CFR 173.415(a), which states, ''Each offeror of a Specification 7A package must maintain on file for at least one year after the shipment, and shall provide to DOT on request, complete documentation of tests and an engineering evaluation of comparative data showing that the construction methods, packaging design, and materials of construction comply with that specification.'' This guidance document uses a checklist to show compliance

  9. Environmental Restoration Remedial Action quality assurance requirements document

    International Nuclear Information System (INIS)

    1991-01-01

    This document defines the quality assurance requirements for the US Department of Energy-Richland Operations Office Environmental Restoration Remedial Action program at the Hanford Site. The Environmental Restoration Remedial Action program implements significant commitments made by the US Department of Energy in the Hanford Federal Facility Agreement and Consent Order entered into with the Washington State Department of Ecology and the US Environmental Protection Agency. This document combines quality assurance requirements from various source documents into one set of requirements for use by the US Department of Energy-Richland Operations Office and other Environmental Restoration Remedial Action program participants. This document will serve as the basis for developing Quality Assurance Program Plans and implementing procedures by the participants. The requirements of this document will be applied to activities affecting quality, using a graded approach based on the importance of the item, service, or activity to the program objectives. The Quality Assurance Program that will be established using this document as the basis, together with other program and technical documents, form an integrated management control system for conducting the Environmental Restoration Remedial Action program activities in a manner that provides safety and protects the environment and public health

  10. Monitored Retrievable Storage System Requirements Document. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    This Monitored Retrievable Storage System Requirements Document (MRS-SRD) describes the functions to be performed and technical requirements for a Monitored Retrievable Storage (MRS) facility subelement and the On-Site Transfer and Storage (OSTS) subelement. The MRS facility subelement provides for temporary storage, at a Civilian Radioactive Waste Management System (CRWMS) operated site, of spent nuclear fuel (SNF) contained in an NRC-approved Multi-Purpose Canister (MPC) storage mode, or other NRC-approved storage modes. The OSTS subelement provides for transfer and storage, at Purchaser sites, of spent nuclear fuel (SNF) contained in MPCs. Both the MRS facility subelement and the OSTS subelement are in support of the CRWMS. The purpose of the MRS-SRD is to define the top-level requirements for the development of the MRS facility and the OSTS. These requirements include design, operation, and decommissioning requirements to the extent they impact on the physical development of the MRS facility and the OSTS. The document also presents an overall description of the MRS facility and the OSTS, their functions (derived by extending the functional analysis documented by the Physical System Requirements (PSR) Store Waste Document), their segments, and the requirements allocated to the segments. In addition, the top-level interface requirements of the MRS facility and the OSTS are included. As such, the MRS-SRD provides the technical baseline for the MRS Safety Analysis Report (SAR) design and the OSTS Safety Analysis Report design.

  11. Guidance and Control Software Project Data - Volume 4: Configuration Management and Quality Assurance Documents

    Science.gov (United States)

    Hayhurst, Kelly J. (Editor)

    2008-01-01

    The Guidance and Control Software (GCS) project was the last in a series of software reliability studies conducted at Langley Research Center between 1977 and 1994. The technical results of the GCS project were recorded after the experiment was completed. Some of the support documentation produced as part of the experiment, however, is serving an unexpected role far beyond its original project context. Some of the software used as part of the GCS project was developed to conform to the RTCA/DO-178B software standard, "Software Considerations in Airborne Systems and Equipment Certification," used in the civil aviation industry. That standard requires extensive documentation throughout the software development life cycle, including plans, software requirements, design and source code, verification cases and results, and configuration management and quality control data. The project documentation that includes this information is open for public scrutiny without the legal or safety implications associated with comparable data from an avionics manufacturer. This public availability has afforded an opportunity to use the GCS project documents for DO-178B training. This report provides a brief overview of the GCS project, describes the 4-volume set of documents and the role they are playing in training, and includes configuration management and quality assurance documents from the GCS project. Volume 4 contains six appendices: A. Software Accomplishment Summary for the Guidance and Control Software Project; B. Software Configuration Index for the Guidance and Control Software Project; C. Configuration Management Records for the Guidance and Control Software Project; D. Software Quality Assurance Records for the Guidance and Control Software Project; E. Problem Report for the Pluto Implementation of the Guidance and Control Software Project; and F. Support Documentation Change Reports for the Guidance and Control Software Project.

  12. Functional requirements document for measuring emissions of airborne radioactive materials

    International Nuclear Information System (INIS)

    Glissmeyer, J.A.; Alvarez, J.L.; Hoover, M.D.; Newton, G.C.; McFarland, A.R.; Rodgers, J.C.

    1994-11-01

    This document states the general functional requirements for systems and procedures for measuring emissions of airborne radioactive materials from facilities administered by the Westinghouse Hanford Company (WHC). The following issues are addressed in this document: lg-bullet definition of the program objectives lg-bullet selection of the overall approach to collecting the samples lg-bullet sampling equipment design lg-bullet sampling equipment maintenance and quality assurance issues. The following issues are not addressed in this document: lg-bullet air sampling in work areas or containments lg-bullet selection of specific on-line sample monitoring instrumentation lg-bullet analyzing collected samples lg-bullet reporting and interpreting results. The document provides equipment design guidance that is performance based rather than prescriptive. Locations from which samples are obtained should exhibit mixing of the contaminants with the airstream and acceptable air flow characteristics. Sample collection equipment and effluent and sample flow elements should meet defined performance standards. Quality control and assurance requirements specific to sample collection, equipment inspection, and calibration are presented. Key sample collection performance requirements are summarized in Section 5.4. The intent of this document is to assist WHC in demonstrating a high quality of air emission measurements with verified system performance based on documented system design, testing, inspection, and maintenance

  13. B plant standards/requirements identification document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    Maddox, B.S., Westinghouse Hanford

    1996-07-29

    This Standards/Requirements Identification Document (S/RID) set forth the Environmental Safety and Health (ES{ampersand}H) standards/requirements for the B Plant. This S/RID is applicable to the appropriate life cycle phases of design, construction,operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  14. Standards/requirements identification documents (S/RIDS)

    International Nuclear Information System (INIS)

    Beckman, W.H.; Alhadeff, N.

    1994-01-01

    This paper describes the Fernald Environmental Restoration Management Corporation's (FERMCO) Standards/Requirement Identification Documents (S/RIDs) Development Program, the unique process used to implement it, and the status of the program. We will also discuss the lessons learned as the development program was implemented. The Department of Energy (DOE) established the Fernald site to produce uranium metals for the nation's defense programs in 1953. In 1989, DOE suspended production and, in 1991, the mission of the site was formally changed to one of environmental cleanup and restoration. The site was renamed the Fernald Environmental Management Project (FEMP) to reflect this change. From its inception until November 1992, the site was managed under a Management and Operating contract. As a result in the change in mission, DOE awarded an Environmental Restoration Management Contract (ERMC), focusing on restoration. FERMCO assumed management of the site December 1, 1992. The joint DOE/FERMCO mission is to protect human health and the environment through the safe, early, and least-cost final clean-up of the site in compliance with all applicable regulations and commitments while addressing stakeholder concerns. DOE has managed nuclear facilities primarily through its oversight of Management and Operating contractors. These contractors were responsible for formulating, selecting, and administering standards controlling design, construction, operations, and maintenance. The DOE Operations Office Manager was responsible for approving individual contractor practices and the governing site standards and requirements to be met. Due to the absence of comprehensive nuclear industry standards when most DOE sites were first established, Management and Operating contractors had to apply existing non-nuclear industry standards and, in many cases, formulate new technical standards to address unique applications

  15. SNF fuel retrieval sub project safety analysis document

    International Nuclear Information System (INIS)

    BERGMANN, D.W.

    1999-01-01

    This safety analysis is for the SNF Fuel Retrieval (FRS) Sub Project. The FRS equipment will be added to K West and K East Basins to facilitate retrieval, cleaning and repackaging the spent nuclear fuel into Multi-Canister Overpack baskets. The document includes a hazard evaluation, identifies bounding accidents, documents analyses of the accidents and establishes safety class or safety significant equipment to mitigate accidents as needed

  16. SNF fuel retrieval sub project safety analysis document

    Energy Technology Data Exchange (ETDEWEB)

    BERGMANN, D.W.

    1999-02-24

    This safety analysis is for the SNF Fuel Retrieval (FRS) Sub Project. The FRS equipment will be added to K West and K East Basins to facilitate retrieval, cleaning and repackaging the spent nuclear fuel into Multi-Canister Overpack baskets. The document includes a hazard evaluation, identifies bounding accidents, documents analyses of the accidents and establishes safety class or safety significant equipment to mitigate accidents as needed.

  17. Detector Control System for an LHC experiment - User Requirements Document

    CERN Document Server

    CERN. Geneva

    1997-01-01

    The purpose of this document is to provide the user requirements for a detector control system kernel for the LHC experiments following the ESA standard PSS-05 [1]. The first issue will be used to provide the basis for an evaluation of possible development philosophies for a kernel DCS. As such it will cover all the major functionality but only to a level of detail sufficient for such an evaluation to be performed. Many of the requirements are therefore intentionally high level and generic, and are meant to outline the functionality that would be required of the kernel DCS, but not yet to the level of the detail required for implementation. The document is also written in a generic fashion in order not to rule out any implementation technology.

  18. 7 CFR 1488.8 - Documents required after delivery.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 10 2010-01-01 2010-01-01 false Documents required after delivery. 1488.8 Section... delivery. (a) CCC will purchase an exporter's account receivable only if the Treasurer, Commodity Credit... or Assistant Treasurer, CCC, after date of delivery of commodities exported or to be exported under...

  19. Tank waste remediation system privatization infrastructure program requirements and document management process guide

    International Nuclear Information System (INIS)

    ROOT, R.W.

    1999-01-01

    This guide provides the Tank Waste Remediation System Privatization Infrastructure Program management with processes and requirements to appropriately control information and documents in accordance with the Tank Waste Remediation System Configuration Management Plan (Vann 1998b). This includes documents and information created by the program, as well as non-program generated materials submitted to the project. It provides appropriate approval/control, distribution and filing systems

  20. Future CANDU nuclear power plant design requirements document executive summary

    International Nuclear Information System (INIS)

    Lee, Duk Su; Chang, Woo Hyun; Lee, Nam Young; S. A. Usmani

    1996-03-01

    The future CANDU Requirements Document (FCRED) describes a clear and complete statement of utility requirements for the next generation of CANDU nuclear power plants including those in Korea. The requirements are based on proven technology of PHWR experience and are intended to be consistent with those specified in the current international requirement documents. Furthermore, these integrated set of design requirements, incorporate utility input to the extent currently available and assure a simple, robust and more forgiving design that enhances the performance and safety. The FCRED addresses the entire plant, including the nuclear steam supply system and the balance of the plant, up to the interface with the utility grid at the distribution side of the circuit breakers which connect the switchyard to the transmission lines. Requirements for processing of low level radioactive waste at the plant site and spent fuel storage requirements are included in the FCRED. Off-site waste disposal is beyond the scope of the FCRED. 2 tabs., 1 fig. (Author) .new

  1. Advanced Air Transportation Technologies Project, Final Document Collection

    Science.gov (United States)

    Mogford, Richard H.; Wold, Sheryl (Editor)

    2008-01-01

    This CD ROM contains a compilation of the final documents of the Advanced Air Transportation Technologies (AAIT) project, which was an eight-year (1996 to 2004), $400M project managed by the Airspace Systems Program office, which was part of the Aeronautics Research Mission Directorate at NASA Headquarters. AAIT focused on developing advanced automation tools and air traffic management concepts that would help improve the efficiency of the National Airspace System, while maintaining or enhancing safety. The documents contained in the CD are final reports on AAIT tasks that serve to document the project's accomplishments over its eight-year term. Documents include information on: Advanced Air Transportation Technologies, Autonomous Operations Planner, Collaborative Arrival Planner, Distributed Air/Ground Traffic Management Concept Elements 5, 6, & 11, Direct-To, Direct-To Technology Transfer, Expedite Departure Path, En Route Data Exchange, Final Approach Spacing Tool - (Active and Passive), Multi-Center Traffic Management Advisor, Multi Center Traffic Management Advisor Technology Transfer, Surface Movement Advisor, Surface Management System, Surface Management System Technology Transfer and Traffic Flow Management Research & Development.

  2. Hanford analytical services quality assurance requirements documents. Volume 1: Administrative Requirements

    International Nuclear Information System (INIS)

    Hyatt, J.E.

    1997-01-01

    Hanford Analytical Services Quality Assurance Requirements Document (HASQARD) is issued by the Analytical Services, Program of the Waste Management Division, US Department of Energy (US DOE), Richland Operations Office (DOE-RL). The HASQARD establishes quality requirements in response to DOE Order 5700.6C (DOE 1991b). The HASQARD is designed to meet the needs of DOE-RL for maintaining a consistent level of quality for sampling and field and laboratory analytical services provided by contractor and commercial field and laboratory analytical operations. The HASQARD serves as the quality basis for all sampling and field/laboratory analytical services provided to DOE-RL through the Analytical Services Program of the Waste Management Division in support of Hanford Site environmental cleanup efforts. This includes work performed by contractor and commercial laboratories and covers radiological and nonradiological analyses. The HASQARD applies to field sampling, field analysis, and research and development activities that support work conducted under the Hanford Federal Facility Agreement and Consent Order Tri-Party Agreement and regulatory permit applications and applicable permit requirements described in subsections of this volume. The HASQARD applies to work done to support process chemistry analysis (e.g., ongoing site waste treatment and characterization operations) and research and development projects related to Hanford Site environmental cleanup activities. This ensures a uniform quality umbrella to analytical site activities predicated on the concepts contained in the HASQARD. Using HASQARD will ensure data of known quality and technical defensibility of the methods used to obtain that data. The HASQARD is made up of four volumes: Volume 1, Administrative Requirements; Volume 2, Sampling Technical Requirements; Volume 3, Field Analytical Technical Requirements; and Volume 4, Laboratory Technical Requirements. Volume 1 describes the administrative requirements

  3. Army Materiel Requirements Documents: Qualitative Analysis of Efficiency and Effectiveness

    Science.gov (United States)

    2013-06-01

    focuses on the program’s time to execute their mission based off the MRDs/MCDs. We measure efficiency based on two BPP initiatives: (1) Build...definitions of each BPP initiative during our interviews. A poor rating indicates the requirement documents did not sufficiently support the program...in terms of efficiency and effectiveness according to BPP initiatives. For efficiency, we assign a qualitative measure based on SME responses across

  4. Environmental restoration remedial action quality assurance requirements document

    International Nuclear Information System (INIS)

    Cote, R.F.

    1991-01-01

    The environmental Restoration Remedial Action Quality Assurance Requirements Document (DOE/RL 90-28) defines the quality assurance program requirements for the US Department of Energy-Richland Field Office Environmental Restoration Remedial Action Program at the Hanford Site, Richland, Washington. This paper describes the objectives outlined in DOE/RL 90-28. The Environmental Restoration Remedial Action Program implements significant commitments made by the US Department of Energy in the Hanford Federal Facility Agreement and Consent Order entered into with the Washington State Department of Ecology and the US Environmental Protection Agency

  5. Improving the quality of nursing documentation: An action research project

    Directory of Open Access Journals (Sweden)

    Elisha M. Okaisu

    2014-12-01

    Conclusion: Improving nursing documentation involved complex challenges in this setting and demanded multiple approaches. Evidence-based practise was the foundation of changes in systems required to produce visible improvement in practise. The involved role of leadership in these efforts was very important.

  6. Spent Nuclear Fuel Project Canister Storage Building Functions and Requirements

    International Nuclear Information System (INIS)

    KLEM, M.J.

    2000-01-01

    In 1998, a major change in the technical strategy for managing Multi Canister Overpacks (MCO) while stored within the Canister Storage Building (CSB) occurred. The technical strategy is documented in Baseline Change Request (BCR) No. SNF-98-006, Simplified SNF Project Baseline (MCO Sealing) (FDH 1998). This BCR deleted the hot conditioning process initially adopted for the Spent Nuclear Fuel Project (SNF Project) as documented in WHC-SD-SNF-SP-005, Integrated Process Strategy for K Basins Spent Nuclear Fuel (WHC 199.5). In summary, MCOs containing Spent Nuclear Fuel (SNF) from K Basins would be placed in interim storage following processing through the Cold Vacuum Drying (CVD) facility. With this change, the needs for the Hot Conditioning System (HCS) and inerting/pressure retaining capabilities of the CSB storage tubes and the MCO Handling Machine (MHM) were eliminated. Mechanical seals will be used on the MCOs prior to transport to the CSB. Covers will be welded on the MCOs for the final seal at the CSB. Approval of BCR No. SNF-98-006, imposed the need to review and update the CSB functions and requirements baseline documented herein including changing the document title to ''Spent Nuclear Fuel Project Canister Storage Building Functions and Requirements.'' This revision aligns the functions and requirements baseline with the CSB Simplified SNF Project Baseline (MCO Sealing). This document represents the Canister Storage Building (CSB) Subproject technical baseline. It establishes the functions and requirements baseline for the implementation of the CSB Subproject. The document is organized in eight sections. Sections 1.0 Introduction and 2.0 Overview provide brief introductions to the document and the CSB Subproject. Sections 3.0 Functions, 4.0 Requirements, 5.0 Architecture, and 6.0 Interfaces provide the data described by their titles. Section 7.0 Glossary lists the acronyms and defines the terms used in this document. Section 8.0 References lists the

  7. Software requirements specification document for the AREST code development

    International Nuclear Information System (INIS)

    Engel, D.W.; McGrail, B.P.; Whitney, P.D.; Gray, W.J.; Williford, R.E.; White, M.D.; Eslinger, P.W.; Altenhofen, M.K.

    1993-11-01

    The Analysis of the Repository Source Term (AREST) computer code was selected in 1992 by the U.S. Department of Energy. The AREST code will be used to analyze the performance of an underground high level nuclear waste repository. The AREST code is being modified by the Pacific Northwest Laboratory (PNL) in order to evaluate the engineered barrier and waste package designs, model regulatory compliance, analyze sensitivities, and support total systems performance assessment modeling. The current version of the AREST code was developed to be a very useful tool for analyzing model uncertainties and sensitivities to input parameters. The code has also been used successfully in supplying source-terms that were used in a total systems performance assessment. The current version, however, has been found to be inadequate for the comparison and selection of a design for the waste package. This is due to the assumptions and simplifications made in the selection of the process and system models. Thus, the new version of the AREST code will be designed to focus on the details of the individual processes and implementation of more realistic models. This document describes the requirements of the new models that will be implemented. Included in this document is a section describing the near-field environmental conditions for this waste package modeling, description of the new process models that will be implemented, and a description of the computer requirements for the new version of the AREST code

  8. High level waste storage tanks 242-A evaporator standards/requirement identification document

    International Nuclear Information System (INIS)

    Biebesheimer, E.

    1996-01-01

    This document, the Standards/Requirements Identification Document (S/RIDS) for the subject facility, represents the necessary and sufficient requirements to provide an adequate level of protection of the worker, public health and safety, and the environment. It lists those source documents from which requirements were extracted, and those requirements documents considered, but from which no requirements where taken. Documents considered as source documents included State and Federal Regulations, DOE Orders, and DOE Standards

  9. MORE: Management of Requirements in NPP Modernisation Projects, final report

    International Nuclear Information System (INIS)

    Fredriksen, R.; Katta, V.; Raspotnig, C.; Valkonen, J.

    2008-09-01

    This report documents the work and related activities of the MORE (Management of Requirements in NPP Modernisation Projects) (NKS-R project number NKS-R-2005-47) project. This report also provides a summary of the project activities and deliverables, and discusses possible application areas. The project has aimed at the industrial utilisation of the results from the TACO: (Traceability and Communication of Requirements in Digital I and C Systems Development) (NKS-R project number NKS-R-2002-16, completed June, 2005) project, and practical application of improved approaches and methods for requirements engineering and change management. Finally, the report provides a brief description of the extended industrial network and disseminations of the results in Nordic and NKS related events such as seminars and workshops. (au)

  10. MORE: Management of Requirements in NPP Modernisation Projects, final report

    Energy Technology Data Exchange (ETDEWEB)

    Fredriksen, R.; Katta, V.; Raspotnig, C. (Inst. for energiteknikk (IFE) (Norway)); Valkonen, J. (Technical Research Centre of Finland (VTT) (Finland))

    2008-09-15

    This report documents the work and related activities of the MORE (Management of Requirements in NPP Modernisation Projects) (NKS-R project number NKS-R-2005-47) project. This report also provides a summary of the project activities and deliverables, and discusses possible application areas. The project has aimed at the industrial utilisation of the results from the TACO: (Traceability and Communication of Requirements in Digital I and C Systems Development) (NKS-R project number NKS-R-2002-16, completed June, 2005) project, and practical application of improved approaches and methods for requirements engineering and change management. Finally, the report provides a brief description of the extended industrial network and disseminations of the results in Nordic and NKS related events such as seminars and workshops. (author)

  11. UMTRA Surface Project management action process document: Final. Revision 2

    International Nuclear Information System (INIS)

    1996-06-01

    Title 1 of the UMTRCA authorized the DOE to undertake remedial actions at these designed sites and associated vicinity properties (VP), which contain uranium mill tailings and other residual radioactive materials (RRM) derived from the processing sites. Title 2 of the UMTRCA addresses uranium mill sites that were licensed at the time the UMTRCA was enacted. Cleanup of these Title 2 sites is the responsibility of the licensees. The cleanup of the Title 1 sites has been split into two separate projects: the Surface Project, which deals with the mill buildings, tailings, and contaminated soils at the sites and VPs; and the Ground Water Project, which is limited to the contaminated ground water at the sites. This management action process (MAP) document discusses the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project. Since its inception through March 1996, the Surface Project (hereinafter called the Project) has cleaned up 16 of the 24 designated processing sites and approximately 5,000 VPs, reducing the risk to human health and the environment posed by the uranium mill tailings. Two of the 24 sites, Belfield and Bowman, North Dakota, will not be remediated at the request of the state, reducing the total number of sites to 22. By the start of FY1998, the remaining 6 processing sites and associated VPs will be cleaned up. The remedial action activities to be funded in FY1998 by the FY1998 budget request are remediation of the remaining Grand Junction, Colorado, VPs; closure of the Cheney disposal cell in Grand Junction, Colorado; and preparation of the completion reports for 4 completed sites

  12. UMTRA Surface Project management action process document: Final. Revision 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    Title 1 of the UMTRCA authorized the DOE to undertake remedial actions at these designed sites and associated vicinity properties (VP), which contain uranium mill tailings and other residual radioactive materials (RRM) derived from the processing sites. Title 2 of the UMTRCA addresses uranium mill sites that were licensed at the time the UMTRCA was enacted. Cleanup of these Title 2 sites is the responsibility of the licensees. The cleanup of the Title 1 sites has been split into two separate projects: the Surface Project, which deals with the mill buildings, tailings, and contaminated soils at the sites and VPs; and the Ground Water Project, which is limited to the contaminated ground water at the sites. This management action process (MAP) document discusses the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project. Since its inception through March 1996, the Surface Project (hereinafter called the Project) has cleaned up 16 of the 24 designated processing sites and approximately 5,000 VPs, reducing the risk to human health and the environment posed by the uranium mill tailings. Two of the 24 sites, Belfield and Bowman, North Dakota, will not be remediated at the request of the state, reducing the total number of sites to 22. By the start of FY1998, the remaining 6 processing sites and associated VPs will be cleaned up. The remedial action activities to be funded in FY1998 by the FY1998 budget request are remediation of the remaining Grand Junction, Colorado, VPs; closure of the Cheney disposal cell in Grand Junction, Colorado; and preparation of the completion reports for 4 completed sites.

  13. Requirements Document for Development of a Livermore Tomography Tools Interface

    Energy Technology Data Exchange (ETDEWEB)

    Seetho, I. M. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)

    2017-02-09

    In this document, we outline an exercise performed at LLNL to evaluate the user interface deficits of a LLNL-developed CT reconstruction software package, Livermore Tomography Tools (LTT). We observe that a difficult-to-use command line interface and the lack of support functions compound to generate a bottleneck in the CT reconstruction process when input parameters to key functions are not well known. Through the exercise of systems engineering best practices, we generate key performance parameters for a LTT interface refresh, and specify a combination of back-end (“test-mode” functions) and front-end (graphical user interface visualization and command scripting tools) solutions to LTT’s poor user interface that aim to mitigate issues and lower costs associated with CT reconstruction using LTT. Key functional and non-functional requirements and risk mitigation strategies for the solution are outlined and discussed.

  14. Idaho National Laboratory Ten-Year Site Plan Project Description Document

    Energy Technology Data Exchange (ETDEWEB)

    Not Listed

    2012-03-01

    This document describes the currently active and proposed infrastructure projects listed in Appendix B of the Idaho National Laboratory 2013-2022 Ten Year Site Plan (DOE/ID-11449). It was produced in accordance with Contract Data Requirements List I.06. The projects delineated in this document support infrastructure needs at INL's Research and Education Campus, Materials and Fuels Complex, Advanced Test Reactor Complex and the greater site-wide area. The projects provide critical infrastructure needed to meet current and future INL opereational and research needs. Execution of these projects will restore, rebuild, and revitalize INL's physical infrastructure; enhance program execution, and make a significant contribution toward reducing complex-wide deferred maintenance.

  15. Emergency Response Capability Baseline Needs Assessment - Requirements Document

    Energy Technology Data Exchange (ETDEWEB)

    Sharry, J A

    2016-10-04

    This document was prepared by John A. Sharry, LLNL Fire Marshal and LLNL Division Leader for Fire Protection and reviewed by LLNL Emergency Management Department Head James Colson. The document follows and expands upon the format and contents of the DOE Model Fire Protection Baseline Capabilities Assessment document contained on the DOE Fire Protection Web Site, but only addresses emergency response.

  16. Electronic document management meets environmental restoration recordkeeping requirements: A case study

    International Nuclear Information System (INIS)

    Burnham, S.L.

    1995-01-01

    Efforts at migrating records management at five Department of Energy sites operated under management by Lockheed Martin Energy Systems, Inc. for Environmental Restoration (ER) business activities are described. The corporate environment, project definition, records keeping requirements are described first. Then an evaluation of electronic document management technologies and of internal and commercially available systems are provided. Finally adopted incremental implementation strategy and lessons learned are discussed

  17. Determining if a change to a proposal requires additional NEPA documentation: the Smithsonian Solution; TOPICAL

    International Nuclear Information System (INIS)

    ECCLESTON, C.H.

    1999-01-01

    Proposed actions tend to evolve over time. Once National Environmental Policy Act (NEPA) documentation is completed, agencies are at risk that subsequent changes may not be adequately covered or that existing NEPA documentation maybe completely invalidated. Neither NEPA nor its subsequent regulations provide sufficient direction for determining the degree to which a proposed action may change before preparation of new or supplemental documentation is necessary. Yet, decisionmakers are routinely involved in determining if a change to a proposed action departs, to such an extent, from the description presented in the NEPA document that additional documentation is necessary. Experience demonstrates that no two decisionmakers will completely agree, one decisionmaker might believe that a particular change would not require additional documentation, while the other concludes the exact opposite. Lacking definitive direction, decisionmakers and critics alike may point to a universe of potential considerations as the basis for defending their claim that a change in an action does or does not require new or additional NEPA documentation. Assertions are often based on equivocal opinions that can be neither proved nor disproved. Moreover, decisionmakers are frequently placed in an arduous dilemma of justifying a decision, for which there is no generally accepted methodology on which to base the decision. Lack of definitive direction can prolong the decisionmaking process, resulting in project delays. This can also lead to inappropriate levels of NEPA documentation, inconsistencies in decisionmaking, and increased risk of a legal challenge because of insufficient documentation. Clearly, a more systematic and less subjective approach is needed, A tool for streamlining the NEPA process, by reducing this degree of subjectivity, is presented in this paper

  18. Interface control document for tank waste remediation system privatization phase 1 infrastructure support Project W-519

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This document describes the functional and physical interfaces between the Tank Waste Remediation System (TWRS) Privatization Phase 1 Infrastructure Project W-519 and the various other projects (i.e., Projects W-314, W-464, W-465, and W-520) supporting Phase 1 that will require the allocation of land in and about the Privatization Phase 1 Site and/or interface with the utilities extended by Project W-519. Project W-519 will identify land use allocations and upgrade/extend several utilities in the 200-East Area into the Privatization Phase 1 Site (formerly the Grout Disposal Compound) in preparation for the Privatization Contractors (PC) to construct treatment facilities. The project will upgrade/extend: Roads, Electrical Power, Raw Water (for process and fire suppression), Potable Water, and Liquid Effluent collection. The replacement of an existing Sanitary Sewage treatment system that may be displaced by Phase 1 site preparation activities may also be included

  19. 24 CFR 234.26 - Project requirements.

    Science.gov (United States)

    2010-04-01

    ... Commissioner for the purpose of constructing or converting the project in phases or stages, any special right..., the management company, the real estate broker, and the project developer, but the lender must ensure... 24 Housing and Urban Development 2 2010-04-01 2010-04-01 false Project requirements. 234.26...

  20. Project Interface Requirements Process Including Shuttle Lessons Learned

    Science.gov (United States)

    Bauch, Garland T.

    2010-01-01

    Most failures occur at interfaces between organizations and hardware. Processing interface requirements at the start of a project life cycle will reduce the likelihood of costly interface changes/failures later. This can be done by adding Interface Control Documents (ICDs) to the Project top level drawing tree, providing technical direction to the Projects for interface requirements, and by funding the interface requirements function directly from the Project Manager's office. The interface requirements function within the Project Systems Engineering and Integration (SE&I) Office would work in-line with the project element design engineers early in the life cycle to enhance communications and negotiate technical issues between the elements. This function would work as the technical arm of the Project Manager to help ensure that the Project cost, schedule, and risk objectives can be met during the Life Cycle. Some ICD Lessons Learned during the Space Shuttle Program (SSP) Life Cycle will include the use of hardware interface photos in the ICD, progressive life cycle design certification by analysis, test, & operations experience, assigning interface design engineers to Element Interface (EI) and Project technical panels, and linking interface design drawings with project build drawings

  1. 22 CFR 203.7 - IPVO initial documentation requirements.

    Science.gov (United States)

    2010-04-01

    ... structure; (4) Statement of tax exemption or a comparable document from the country of its origin; (5... IPVO's country of domicile by an independent certified public accountant (CPA) and in U.S. dollars; (6...

  2. Spent Nuclear Fuel Project technical baseline document. Fiscal year 1995: Volume 1, Baseline description

    International Nuclear Information System (INIS)

    Womack, J.C.; Cramond, R.; Paedon, R.J.

    1995-01-01

    This document is a revision to WHC-SD-SNF-SD-002, and is issued to support the individual projects that make up the Spent Nuclear Fuel Project in the lower-tier functions, requirements, interfaces, and technical baseline items. It presents results of engineering analyses since Sept. 1994. The mission of the SNFP on the Hanford site is to provide safety, economic, environmentally sound management of Hanford SNF in a manner that stages it to final disposition. This particularly involves K Basin fuel, although other SNF is involved also

  3. Data management for the Clinch River Breeder Reactor Plant Project by use of document status and hold systems

    International Nuclear Information System (INIS)

    Hunt, C.S.; Beck, A.E.; Akhtar, M.S.

    1982-01-01

    This paper describes the development, framework, and scope of the Document Status System and the Document Hold System for the Clinch River Breeder Reactor Plant Project. It shows how data are generated at five locations and transmitted to a central computer for processing and storage. The resulting computerized data bank provides reports needed to perform day-to-day management and engineering planning. Those reports also partially satisfy the requirements of the Project's Quality Assurance Program

  4. 24 CFR 92.612 - Project requirements.

    Science.gov (United States)

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Project requirements. 92.612 Section 92.612 Housing and Urban Development Office of the Secretary, Department of Housing and Urban Development HOME INVESTMENT PARTNERSHIPS PROGRAM American Dream Downpayment Initiative § 92.612 Project...

  5. Radiation requirements for uranium project approvals

    International Nuclear Information System (INIS)

    Hondros, J.

    2014-01-01

    Uranium mining projects in Australia must receive approval under both state and national laws based on a wide ranging impact assessment of the project. The process may take a number of years and involves multiple levels and parts of government and public consultation and scrutiny. The impact assessment is broad and usually covers; environmental, social, health, public safety and economic aspects. Information provided in the approvals documentation needs to be presented in a credible and understandable manner for all audiences. This means making complex information simpler, while making sure that it maintains its technical integrity. Poorly communicated information, which is overly complex, overly simplified or incomplete, can result in significant delays to the project approval which can potentially impact on project timelines. For uranium projects, along with other projects involving radioactive materials, such as minerals sands and rare earths, radiation and its impacts usually draw a disproportionate amount of both government and public scrutiny compared to other potential impacts and risks. It is therefore of key importance that radiation assessments are properly performed and results clearly presented and communicated with sufficient detail for stakeholders to make informed decisions. It is also important to ensure that the radiation risk is presented in perspective with other risks of the project. This presentation outlines a structure for a radiation impact assessment based on experience from a number of projects in Australia. The structure aims to be clear and simple and ensure the right balance between scientific fact, digestible information and demonstrable competence. (author)

  6. A Cognitive Model of Document Use during a Research Project. Study I. Document Selection.

    Science.gov (United States)

    Wang, Peiling; Soergel, Dagobert

    1998-01-01

    Proposes a model of document selection by real users of a bibliographic retrieval system. Reports on Part I of a longitudinal study of decision making on document use by academics (25 faculty and graduate students in Agricultural Economics). Examines what components are relevant to the users' decisions and what cognitive process may have occurred…

  7. Documenter le futur: fantasmes, projections et decalages spatiotemporels

    Directory of Open Access Journals (Sweden)

    Alice Forge

    2015-10-01

    Full Text Available Le concept de documentation future recèle un paradoxe : le mot documenter renvoie à des traces relevées dans un passé factuel, tandis que le futur ne peut, par définition, être qu’incertain, que l’objet de fantasmes, de projections. L’analyse suivante questionne ce paradoxe à travers l’analyse d’un motif cinématographique : un homme et une femme face à une tranche de séquoia, représentation symbolique du temps. Ce motif apparait dans trois oeuvres majeures du cinéma : Vertigo, d’Alfred Hitchcock, La Jetée de Chris Marker, et l’Armée des douze singes, de Terry Gilliam. La répétition de ce motif est mise en rapport avec l’ouvrage de Pierre Bayard, Le plagiat par anticipation, afin de l’envisager sous l’angle du paradoxe temporel, plutôt que sous le régime de la chronologie historique. Cette analyse prend pour point de départ une oeuvre intitulée Vozes Fantasmas, qui sur le principe de la documentation future propose d’écouter des murmures de spectateurs visitant une exposition qui n’a pas eu lieu. RESUMO O conceito de documentação do futuro evoca um paradoxo: o verbo documentar refere-se a traços ou rastros preservados de um passado factual, enquanto o futuro por definição é algo incerto, objeto de especulações, fantasias e projeções. Nossa reflexão questiona este paradoxo a partir da análise de uma cena cinematográfica: um homem e uma mulher em frente de um corte de sequoia, que é a representação simbólica do tempo. Esta cena aprece em três grandes obras do cinema: Vertigo (Um corpo que cai de Alfred Hitchcock, La Jetée de Chris Marker, e Os Doze Macacos de Terry Gilliam. A repetição desta cena é abordada em relação à obra de Pierre Bayard, Plágio por antecipação, a fim de considerá-la em termos de paradoxo temporal, e não como uma cronologia histórica. Esta análise tem como ponto de partida um trabalho artístico intitulado Vozes Fantasmas, que seguindo o princípio de

  8. The Role of Requirements in the Success or Failure of Software Projects

    OpenAIRE

    Hussain, Azham; Mkpojiogu, Emmanuel O.C.; Kamal, Fazillah Mohmad

    2016-01-01

    Requirements engineering is pivotal and central to every successful software development project. There are several reasons why software projects fail; however, poorly elicited, documented, validated and managed requirements contribute grossly to software projects failure. Software project failures are normally very costly and risky and these could even a times be life threatening also. Projects that overlook requirements engineering processes often suffer or are most likely to suffer from fa...

  9. 24 CFR 511.11 - Project requirements.

    Science.gov (United States)

    2010-04-01

    ... low income occupancy or rent projections, or restrictions on return on investment or other similar policies that prevent an owner, whether for-profit or non-profit, from maximizing return or setting rent... requirements and with the affirmative marketing requirements and procedures adopted under § 511.13, for the...

  10. Understanding the technical content of requirements in specification document

    DEFF Research Database (Denmark)

    Sudin, Mohd Nizam Bin; Ahmed-Kristensen, Saeema

    2011-01-01

    development process, is essential to be devised in advance. To achieve this aim, understanding how to formulate a good requirement is necessary and it is only possible if design engineers understand the technical content of a requirement. In aiming to understand the technical content of a requirement...

  11. Exploration on Automated Software Requirement Document Readability Approaches

    OpenAIRE

    Chen, Mingda; He, Yao

    2017-01-01

    Context. The requirements analysis phase, as the very beginning of software development process, has been identified as a quite important phase in the software development lifecycle. Software Requirement Specification (SRS) is the output of requirements analysis phase, whose quality factors play an important role in the evaluation work. Readability is a quite important SRS quality factor, but there are few available automated approaches for readability measurement, because of the tight depend...

  12. Repository of not readily available documents for project W-320

    Energy Technology Data Exchange (ETDEWEB)

    Conner, J.C.

    1997-04-18

    The purpose of this document is to provide a readily available source of the technical reports needed for the development of the safety documentation provided for the waste retrieval sluicing system (WRSS), designed to remove the radioactive and chemical sludge from tank 241-C-106, and transport that material to double-shell tank 241-AY-102 via a new, temporary, shielded, encased transfer line.

  13. Consolidated Cab Display (CCD) System, Project Planning Document (PPD),

    Science.gov (United States)

    1981-02-01

    1980 1981 I 2 3 4 5 6 7 8 9 10 1112 1 2 3 4 5 6 7 8 9 1011112 1 2 31 12. Software Documentation a. Overall Computer Program Description ( OCPD ) b...Approve OCPD c. Computer Program Functional Specifications (CPFS) d. Data Base Table Design Specification (DBTDS) e. Software Interface Control Document...Parts List Master Pattern and Plan View Reproducible Drawings Instruction Book Training Aids/Materials b. Software: OCPD CPFS SI CD PDS DBTDS SDD

  14. Repository of not readily available documents for project W-320

    International Nuclear Information System (INIS)

    Conner, J.C.

    1997-01-01

    The purpose of this document is to provide a readily available source of the technical reports needed for the development of the safety documentation provided for the waste retrieval sluicing system (WRSS), designed to remove the radioactive and chemical sludge from tank 241-C-106, and transport that material to double-shell tank 241-AY-102 via a new, temporary, shielded, encased transfer line

  15. 76 FR 24507 - HUD Multifamily Rental Project Closing Documents: Notice Announcing Final Approved Documents and...

    Science.gov (United States)

    2011-05-02

    ... transactions, although these are familiar roles in commercial lending transactions. Accordingly, HUD has... advantage of this language is that it identifies the specific, longstanding, and familiar types of... the documents, HUD is limiting its role and giving lenders more ability to address any problems that...

  16. Guidelines on preparation of documentation required in PET radiopharmaceutical manufacturing

    International Nuclear Information System (INIS)

    2001-01-01

    This article made by the Nuclear Pharmacy Working Group, subcommittee on Medical Application of Cyclotron-Produced Radionuclides, Medical Science and Pharmaceutical Committee, Japan Radioisotope Association, described the actual examples of Standards, Standard Operating Procedure, Documents and so on for the purpose of operation along the Standards of Compounds Labeled with Positron Nuclides Approved as Established Techniques for Medical Use (2001 Revision). Examples were the organization for manufacturing and management, standard format of the product (for [ 18 F]2-deoxy-2-fluoro-D-glucose), standard for process control of manufacture, standard for control of manufacturing and hygiene, standard for quality, and standard operating procedures for entering and leaving the manufacturing facility, for the clean-bench and for the test of floating micro-particles. The second item involved the definition of the cyclotron target ( 18 O), generation of 18 F by the reaction (p, n), purification of the product, and prescription: the third item; storage of the product and manufacturing process control: and the fourth; education and training of personnel, and health management. (K.H.)

  17. International power projections and capital requirements

    International Nuclear Information System (INIS)

    Ann, H.

    1989-01-01

    This work is related to the international power projections and capital requirements of all kinds of energy and the share of electricity. It is also related to the so-called greenhouse effect carbon dioxide concentration in atmosphere. (A.C.A.S.)

  18. 42 CFR 65.4 - Project requirements.

    Science.gov (United States)

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false Project requirements. 65.4 Section 65.4 Public Health PUBLIC HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES FELLOWSHIPS, INTERNSHIPS, TRAINING... appropriate academic disciplines and talents. Joint applications must describe the cooperative arrangements...

  19. 50 CFR 23.19 - What CITES documents are required to export Appendix-I plants?

    Science.gov (United States)

    2010-10-01

    ... 50 Wildlife and Fisheries 6 2010-10-01 2010-10-01 false What CITES documents are required to... ENDANGERED SPECIES OF WILD FAUNA AND FLORA (CITES) Prohibitions, Exemptions, and Requirements § 23.19 What CITES documents are required to export Appendix-I plants? Answer the questions in the following decision...

  20. EUR, an European utility requirements documents for future LWR power stations

    International Nuclear Information System (INIS)

    Berbey, Pierre; Lienard, Michel; Redon, Ramon; Essmann, Juergen; Taylor, David T.

    2004-01-01

    A group of the major European utilities are developing a common requirement document which will be used for the LWR nuclear power plants to be built in Europe from the beginning of the next century. This document provides harmonised policies and technical requirements that will allow the implementation of a design developed in one country into another one. The objectives and contents of the document, the organisation set up for its production and the main requirements are summarised in the paper. (author)

  1. The Human Genome Diversity (HGD) Project. Summary document

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1993-12-31

    In 1991 a group of human geneticists and molecular biologists proposed to the scientific community that a world wide survey be undertaken of variation in the human genome. To aid their considerations, the committee therefore decided to hold a small series of international workshops to explore the major scientific issues involved. The intention was to define a framework for the project which could provide a basis for much wider and more detailed discussion and planning--it was recognized that the successful implementation of the proposed project, which has come to be known as the Human Genome Diversity (HGD) Project, would not only involve scientists but also various national and international non-scientific groups all of which should contribute to the project`s development. The international HGD workshop held in Sardinia in September 1993 was the last in the initial series of planning workshops. As such it not only explored new ground but also pulled together into a more coherent form much of the formal and informal discussion that had taken place in the preceding two years. This report presents the deliberations of the Sardinia workshop within a consideration of the overall development of the HGD Project to date.

  2. Requirements Analysis Study for Master Pump Shutdown System Project Development Specification [SEC 1 and 2

    International Nuclear Information System (INIS)

    BEVINS, R.R.

    2000-01-01

    This document has been updated during the definitive design portion of the first phase of the W-314 Project to capture additional software requirements and is planned to be updated during the second phase of the W-314 Project to cover the second phase of the Project's scope. The objective is to provide requirement traceability by recording the analysis/basis for the functional descriptions of the master pump shutdown system. This document identifies the sources of the requirements and/or how these were derived. Each requirement is validated either by quoting the source or an analysis process involving the required functionality, performance characteristics, operations input or engineering judgment

  3. 17 CFR 4.31 - Required delivery of Disclosure Document to prospective clients.

    Science.gov (United States)

    2010-04-01

    ... Disclosure Document to prospective clients. 4.31 Section 4.31 Commodity and Securities Exchanges COMMODITY... Advisors § 4.31 Required delivery of Disclosure Document to prospective clients. (a) Each commodity trading... prospective client a Disclosure Document containing the information set forth in §§ 4.34 and 4.35 for the...

  4. Uranium Mill Tailings Remedial Action Project: technical approach document

    International Nuclear Information System (INIS)

    1986-05-01

    The Uranium Mill Tailings Radiation Control Act of 1978, PL95-604, grants the Secretary of Energy authority and responsibility to perform such actions as are necessary to minimize radiation health hazards and other environmental hazards from inactive uranium mill sites. These cleanup actions are to be performed in compliance with the EPA standards (40 CFR Part 192) which became final on March 7, 1983. This document describes the general technical approaches and design criteria that are adopted by the US Department of Energy (DOE) in order to implement Remedial Action Plans (RAPs) and final designs that comply with EPA standards

  5. Projected uranium requirements of developing countries

    International Nuclear Information System (INIS)

    Anon.

    1990-01-01

    The objective of this paper is to examine the uranium requirements of developing countries both in aggregate and individually. Although the cumulative uranium requirements of these countries are expected to account for less than eight percent of total requirements, the fact that many of these countries are expressing renewed interest in nuclear is, in itself, encouraging. The countries analyzed in this paper are Argentina, Brazil, Egypt, India, Israel, Mexico, Pakistan, South Africa, South Korea and Taiwan. For each country, the existing and planned nuclear capacity levels have been identified and capacity factors have been projected. For countries with no previous nuclear power, the world weighted average capacity factor for the specific reactor type is utilized. Other factors influencing nuclear power demand and operations of these developing countries will be discussed, and finally, uranium requirements based on a calculated optimal tails assay of .30 will be provided

  6. Knowledge Communication Through Visualizations in Project Management Documents

    DEFF Research Database (Denmark)

    Kampf, Constance

    Trust is difficult to locate, measure and define.  Yet, in terms of knowledge communication, Nonaka et al include trust as an experiential knowledge asset (2000). In 2000, Nonaka et al limited experiential knowledge assets to face-to-face interactions.  However, since then, technologies...... for supporting multimodal features of the Internet have developed to the point where it could be argued that virtual and face-to-face interactions can no longer be distinguished in terms of shared experience (Woolgar 2002). Thus, trust and other experiential knowledge assets can be understood to be present...... in Internet based communication.  To examine online trust from a knowledge communication perspective, this paper looks at the I35W bridge reconstruction project in Minneapolis through web-based communication by the Minnesota Department of Transportation (MnDOT) about the project. The MnDOT bridge...

  7. UMTRA Ground Water Project management action process document

    International Nuclear Information System (INIS)

    1996-03-01

    A critical U.S. Department of Energy (DOE) mission is to plan, implement, and complete DOE Environmental Restoration (ER) programs at facilities that were operated by or in support of the former Atomic Energy Commission (AEC). These facilities include the 24 inactive processing sites the Uranium Mill Tailings Radiation Control Act (UMTRCA) (42 USC Section 7901 et seq.) identified as Title I sites, which had operated from the late 1940s through the 1970s. In UMTRCA, Congress acknowledged the potentially harmful health effects associated with uranium mill tailings and directed the DOE to stabilize, dispose of, and control the tailings in a safe and environmentally sound manner. The UMTRA Surface Project deals with buildings, tailings, and contaminated soils at the processing sites and any associated vicinity properties (VP). Surface remediation at the processing sites will be completed in 1997 when the Naturita, Colorado, site is scheduled to be finished. The UMTRA Ground Water Project was authorized in an amendment to the UMTRCA (42 USC Section 7922(a)), when Congress directed DOE to comply with U.S. Environmental Protection Agency (EPA) ground water standards. The UMTRA Ground Water Project addresses any contamination derived from the milling operation that is determined to be present at levels above the EPA standards

  8. Defining project scenarios for the agile requirements engineering product-line development questionnaire

    OpenAIRE

    Feng, Kunwu; Lempert, Meli; Tang, Yan; Tian, Kun; Cooper, Kendra M.L.; Franch Gutiérrez, Javier

    2007-01-01

    Current agile methods are focused on practices of small, rapid developing and iteration, more people oriented, less documentation projects, and the use of the methods in large, product line projects are somehow difficult. UTD and GESSI have started a project to develop an expert system that can assist a requirements enginer in selecting a requirements engineering process that is well suited for their project, in particular with respect to the use of agile and product line engineering methods....

  9. Requirements Analysis Study for Master Pump Shutdown System Project Development Specification

    International Nuclear Information System (INIS)

    BEVINS, R.R.

    2000-01-01

    This study is a requirements document that presents analysis for the functional description for the master pump shutdown system. This document identifies the sources of the requirements and/or how these were derived. Each requirement is validated either by quoting the source or an analysis process involving the required functionality, performance characteristics, operations input or engineering judgment. The requirements in this study apply to the first phase of the W314 Project. This document has been updated during the definitive design portion of the first phase of the W314 Project to capture additional software requirements and is planned to be updated during the second phase of the W314 Project to cover the second phase of the project's scope

  10. PROJECT ANQA: DIGITIZING AND DOCUMENTING CULTURAL HERITAGE IN THE MIDDLE EAST

    Directory of Open Access Journals (Sweden)

    S. Akhtar

    2017-08-01

    Full Text Available The practice of digitizing cultural heritage sites is gaining ground among conservation scientists and scholars in architecture, art history, computer science, and related fields. Recently, the location of such sites in areas of intense conflict has highlighted the urgent need for documenting cultural heritage for the purposes of preservation and posterity. The complex histories of such sites requires more than just their digitization, and should also include the meaningful interpretation of buildings and their surroundings with respect to context and intangible values. Project Anqa is an interdisciplinary and multi-partner effort that goes beyond simple digitization to record at-risk heritage sites throughout the Middle East and Saharan Africa, most notably in Syria and Iraq, before they are altered or destroyed. Through a collaborative process, Anqa assembles documentation, historically contextualizes it, and makes data accessible and useful for scholars, peers, and the wider public through state-of-the-art tools. The aim of the project is to engage in capacity-building on the ground in Syria and Iraq, as well as to create an educational web platform that informs viewers about cultural heritage in the region through research, digital storytelling, and the experience of virtual environments.

  11. Project Anqa: Digitizing and Documenting Cultural Heritage in the Middle East

    Science.gov (United States)

    Akhtar, S.; Akoglu, G.; Simon, S.; Rushmeier, H.

    2017-08-01

    The practice of digitizing cultural heritage sites is gaining ground among conservation scientists and scholars in architecture, art history, computer science, and related fields. Recently, the location of such sites in areas of intense conflict has highlighted the urgent need for documenting cultural heritage for the purposes of preservation and posterity. The complex histories of such sites requires more than just their digitization, and should also include the meaningful interpretation of buildings and their surroundings with respect to context and intangible values. Project Anqa is an interdisciplinary and multi-partner effort that goes beyond simple digitization to record at-risk heritage sites throughout the Middle East and Saharan Africa, most notably in Syria and Iraq, before they are altered or destroyed. Through a collaborative process, Anqa assembles documentation, historically contextualizes it, and makes data accessible and useful for scholars, peers, and the wider public through state-of-the-art tools. The aim of the project is to engage in capacity-building on the ground in Syria and Iraq, as well as to create an educational web platform that informs viewers about cultural heritage in the region through research, digital storytelling, and the experience of virtual environments.

  12. Compiling Utility Requirements For New Nuclear Power Plant Project

    International Nuclear Information System (INIS)

    Patrakka, Eero

    2002-01-01

    Teollisuuden Voima Oy (TVO) submitted in November 2000 to the Finnish Government an application for a Decision-in-Principle concerning the construction of a new nuclear power plant in Finland. The actual investment decision can be made first after a positive decision has been made by the Government and the Parliament. Parallel to the licensing process, technical preparedness has been upheld so that the procurement process can be commenced without delay, when needed. This includes the definition of requirements for the plant and preliminary preparation of bid inquiry specifications. The core of the technical requirements corresponds to the specifications presented in the European Utility Requirement (EUR) document, compiled by major European electricity producers. Quite naturally, an amount of modifications to the EUR document are needed that take into account the country- and site-specific conditions as well as the experiences gained in the operation of the existing NPP units. Along with the EUR-related requirements concerning the nuclear island and power generation plant, requirements are specified for scope of supply as well as for a variety of issues related to project implementation. (author)

  13. Requirements Definition for ORNL Trusted Corridors Project

    Energy Technology Data Exchange (ETDEWEB)

    Walker, Randy M [ORNL; Hill, David E [ORNL; Smith, Cyrus M [ORNL; DeNap, Frank A [ORNL; White, James D [ORNL; Gross, Ian G [ORNL; Gorman, Bryan L [ORNL; Hively, Lee M [ORNL; Abercrombie, Robert K [ORNL

    2008-02-01

    The ORNL Trusted Corridors Project has several other names: SensorNet Transportation Pilot; Identification and Monitoring of Radiation (in commerce) Shipments (IMR(ic)S); and Southeastern Transportation Corridor Pilot (SETCP). The project involves acquisition and analysis of transportation data at two mobile and three fixed inspection stations in five states (Kentucky, Mississippi, South Carolina, Tennessee, and Washington DC). Collaborators include the State Police organizations that are responsible for highway safety, law enforcement, and incident response. The three states with fixed weigh-station deployments (KY, SC, TN) are interested in coordination of this effort for highway safety, law enforcement, and sorting/targeting/interdiction of potentially non-compliant vehicles/persons/cargo. The Domestic Nuclear Detection Office (DNDO) in the U.S. Department of Homeland Security (DHS) is interested in these deployments, as a Pilot test (SETCP) to identify Improvised Nuclear Devices (INDs) in highway transport. However, the level of DNDO integration among these state deployments is presently uncertain. Moreover, DHS issues are considered secondary by the states, which perceive this work as an opportunity to leverage these (new) dual-use technologies for state needs. In addition, present experience shows that radiation detectors alone cannot detect DHS-identified IND threats. Continued SETCP success depends on the level of integration of current state/local police operations with the new DHS task of detecting IND threats, in addition to emergency preparedness and homeland security. This document describes the enabling components for continued SETCP development and success, including: sensors and their use at existing deployments (Section 1); personnel training (Section 2); concept of operations (Section 3); knowledge discovery from the copious data (Section 4); smart data collection, integration and database development, advanced algorithms for multiple sensors, and

  14. Requirements Definition for ORNL Trusted Corridors Project

    International Nuclear Information System (INIS)

    Walker, Randy M; Hill, David E; Smith, Cyrus M; DeNap, Frank A; White, James D; Gross, Ian G; Gorman, Bryan L; Hively, Lee M; Abercrombie, Robert K

    2008-01-01

    The ORNL Trusted Corridors Project has several other names: SensorNet Transportation Pilot; Identification and Monitoring of Radiation (in commerce) Shipments (IMR(ic)S); and Southeastern Transportation Corridor Pilot (SETCP). The project involves acquisition and analysis of transportation data at two mobile and three fixed inspection stations in five states (Kentucky, Mississippi, South Carolina, Tennessee, and Washington DC). Collaborators include the State Police organizations that are responsible for highway safety, law enforcement, and incident response. The three states with fixed weigh-station deployments (KY, SC, TN) are interested in coordination of this effort for highway safety, law enforcement, and sorting/targeting/interdiction of potentially non-compliant vehicles/persons/cargo. The Domestic Nuclear Detection Office (DNDO) in the U.S. Department of Homeland Security (DHS) is interested in these deployments, as a Pilot test (SETCP) to identify Improvised Nuclear Devices (INDs) in highway transport. However, the level of DNDO integration among these state deployments is presently uncertain. Moreover, DHS issues are considered secondary by the states, which perceive this work as an opportunity to leverage these (new) dual-use technologies for state needs. In addition, present experience shows that radiation detectors alone cannot detect DHS-identified IND threats. Continued SETCP success depends on the level of integration of current state/local police operations with the new DHS task of detecting IND threats, in addition to emergency preparedness and homeland security. This document describes the enabling components for continued SETCP development and success, including: sensors and their use at existing deployments (Section 1); personnel training (Section 2); concept of operations (Section 3); knowledge discovery from the copious data (Section 4); smart data collection, integration and database development, advanced algorithms for multiple sensors, and

  15. Reducing failures rate within the project documentation using Building Information Modelling, especially Level of Development

    Directory of Open Access Journals (Sweden)

    Prušková Kristýna

    2018-01-01

    Full Text Available Paper´s focus is on differences between traditional modelling in 2D software and modelling within the BIM technology. Research uncovers failures connected to the traditional way of designing and construction of project documentation. There are revealed and shown mismatches within the project documentation. Solution within the Building information modelling Technology is outlined. As a reference, there is used experience with design of specific building in both ways of construction of project documentation: in the way of traditional modelling and in the way when using BIM technology, especially using Level of Development. Output of this paper is pointing to benefits of using advanced technology in building design, thus Building Information Modelling, especially Level of Development, which leads to reducing failures rate within the project documentation.

  16. Requirements for the data transfer during the examination of design documentation

    Directory of Open Access Journals (Sweden)

    Karakozova Irina

    2017-01-01

    Full Text Available When you transfer the design documents to the examination office, number of incompatible electronic documents increases dramatically. The article discusses the way to solve the problem of transferring of the text and graphic data of design documentation for state and non-state expertise, as well as verification of estimates and requirement management. The methods for the recognition of the system elements and requirements for the transferring of text and graphic design documents are provided. The need to use the classification and coding of various elements of information systems (structures, objects, resources, requirements, contracts, etc. in data transferring systems is indicated separately. The authors have developed a sequence of document processing and transmission of data during the examination, and propose a language for describing the construction of the facility, taking into account the classification criteria of the structures and construction works.

  17. DOE Integrated Safeguards and Security (DISS) historical document archival and retrieval analysis, requirements and recommendations

    Energy Technology Data Exchange (ETDEWEB)

    Guyer, H.B.; McChesney, C.A.

    1994-10-07

    The overall primary Objective of HDAR is to create a repository of historical personnel security documents and provide the functionality needed for archival and retrieval use by other software modules and application users of the DISS/ET system. The software product to be produced from this specification is the Historical Document Archival and Retrieval Subsystem The product will provide the functionality to capture, retrieve and manage documents currently contained in the personnel security folders in DOE Operations Offices vaults at various locations across the United States. The long-term plan for DISS/ET includes the requirement to allow for capture and storage of arbitrary, currently undefined, clearance-related documents that fall outside the scope of the ``cradle-to-grave`` electronic processing provided by DISS/ET. However, this requirement is not within the scope of the requirements specified in this document.

  18. HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered.

  19. HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-03-01

    This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered

  20. 50 CFR 23.53 - What are the requirements for obtaining a retrospective CITES document?

    Science.gov (United States)

    2010-10-01

    ... retrospective CITES document? 23.53 Section 23.53 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE... ENDANGERED SPECIES OF WILD FAUNA AND FLORA (CITES) Application Procedures, Criteria, and Conditions § 23.53 What are the requirements for obtaining a retrospective CITES document? (a) Purpose. Retrospective...

  1. Westinghouse Hanford Company (WHC) standards/requirements identification document (S/RID)

    International Nuclear Information System (INIS)

    Bennett, G.L.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) set forth the Environmental Safety and Health (ES ampersand amp;H) standards/requirements for Westinghouse Hanford Company Level Programs, where implementation and compliance is the responsibility of these organizations. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment

  2. Westinghouse Hanford Company (WHC) standards/requirements identification document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    Bennett, G.L.

    1996-03-15

    This Standards/Requirements Identification Document (S/RID) set forth the Environmental Safety and Health (ES&H) standards/requirements for Westinghouse Hanford Company Level Programs, where implementation and compliance is the responsibility of these organizations. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  3. Text extraction method for historical Tibetan document images based on block projections

    Science.gov (United States)

    Duan, Li-juan; Zhang, Xi-qun; Ma, Long-long; Wu, Jian

    2017-11-01

    Text extraction is an important initial step in digitizing the historical documents. In this paper, we present a text extraction method for historical Tibetan document images based on block projections. The task of text extraction is considered as text area detection and location problem. The images are divided equally into blocks and the blocks are filtered by the information of the categories of connected components and corner point density. By analyzing the filtered blocks' projections, the approximate text areas can be located, and the text regions are extracted. Experiments on the dataset of historical Tibetan documents demonstrate the effectiveness of the proposed method.

  4. System requirements and design description for the document basis database interface (DocBasis)

    International Nuclear Information System (INIS)

    Lehman, W.J.

    1997-01-01

    This document describes system requirements and the design description for the Document Basis Database Interface (DocBasis). The DocBasis application is used to manage procedures used within the tank farms. The application maintains information in a small database to track the document basis for a procedure, as well as the current version/modification level and the basis for the procedure. The basis for each procedure is substantiated by Administrative, Technical, Procedural, and Regulatory requirements. The DocBasis user interface was developed by Science Applications International Corporation (SAIC)

  5. The database system for the management of technical documentations of PWR fuel design project using CD-ROM

    International Nuclear Information System (INIS)

    Park, Bong Sik; Lee, Won Jae; Ryu, Jae Kwon; Jo, In Hang; Chang, Jong Hwa.

    1996-12-01

    In this report, the database system developed for the management of technical documentation of PWR fuel design project using CD-ROM (compact disk - read only memory) is described. The database system, KIRDOCM (KAERI Initial and Reload Fuel project technical documentation management), is developed and installed on PC using Visual Foxpro 3.0. Descriptions are focused on the user interface of the KIRDOCM. Introduction addresses the background and concept of the development. The main chapter describes the user requirements, the analysis of computing environment, the design of KIRDOCM, the implementation of the KIRDOCM, user's manual of KIRDOCM and the maintenance of the KIRDOCM for future improvement. The implementation of KIRDOCM system provides the efficiency in the management, maintenance and indexing of the technical documents. And, it is expected that KIRDOCM may be a good reference in applying Visual Foxpro for the development of information management system. (author). 2 tabs., 13 figs., 8 refs

  6. Advanced light water reactor utility requirements document: Volume 1--ALWR policy and summary of top-tier requirements

    International Nuclear Information System (INIS)

    Anon.

    1990-01-01

    The U.S. utilities are leading an industry wide effort to establish the technical foundation for the design of the Advanced Light Water Reactor (ALWR). This effort, the ALWR Program, is being managed for the U.S. electric utility industry by the Electric Power Research Institute (EPRI) and includes participation and sponsorship of several international utility companies and close cooperation with the U.S. Department of Energy (DOE). The cornerstone of the ALWR Program is a set of utility design requirements which are contained in the ALWR Requirements Document. The purpose of the Requirement Document is to present a clear, complete statement of utility desires for their next generation of nuclear plants. The Requirements Document covers the entire plant up to the grid interface. It therefore is the basis for an integrated plant design, i.e., nuclear steam supply system and balance of plant, and it emphasizes those areas which are most important to the objective of achieving an ALWR which is excellent with respect to safety, performance, constructibility, and economics. The document applies to both Pressurized Water Reactors (PWRs) and Boiling Water Reactors (BWRs). The Requirements Document is organized in three volumes. Volume 1 summarizes AlWR Program policy statements and top-tier requirements. The top-tier design requirements are categorized by major functions, including safety and investment protection, performance, and design process and constructibility. There is also a set of general design requirements, such as simplification and proven technology, which apply broadly to the ALWR design, and a set of economic goals for the ALWR program. The top-tier design requirements are described further in Volume 1 and are formally invoked as requirements in Volumes 2 and 3

  7. National Land Imaging Requirements (NLIR) Pilot Project summary report: summary of moderate resolution imaging user requirements

    Science.gov (United States)

    Vadnais, Carolyn; Stensaas, Gregory

    2014-01-01

    Under the National Land Imaging Requirements (NLIR) Project, the U.S. Geological Survey (USGS) is developing a functional capability to obtain, characterize, manage, maintain and prioritize all Earth observing (EO) land remote sensing user requirements. The goal is a better understanding of community needs that can be supported with land remote sensing resources, and a means to match needs with appropriate solutions in an effective and efficient way. The NLIR Project is composed of two components. The first component is focused on the development of the Earth Observation Requirements Evaluation System (EORES) to capture, store and analyze user requirements, whereas, the second component is the mechanism and processes to elicit and document the user requirements that will populate the EORES. To develop the second component, the requirements elicitation methodology was exercised and refined through a pilot project conducted from June to September 2013. The pilot project focused specifically on applications and user requirements for moderate resolution imagery (5–120 meter resolution) as the test case for requirements development. The purpose of this summary report is to provide a high-level overview of the requirements elicitation process that was exercised through the pilot project and an early analysis of the moderate resolution imaging user requirements acquired to date to support ongoing USGS sustainable land imaging study needs. The pilot project engaged a limited set of Federal Government users from the operational and research communities and therefore the information captured represents only a subset of all land imaging user requirements. However, based on a comparison of results, trends, and analysis, the pilot captured a strong baseline of typical applications areas and user needs for moderate resolution imagery. Because these results are preliminary and represent only a sample of users and application areas, the information from this report should only

  8. IRPhE-DRAGON-DPR, OECD High Temperature Reactor Dragon Project, Primary Documents

    International Nuclear Information System (INIS)

    2004-01-01

    Description: The DRAGON Reactor Experiment (DRE): The first demonstration High temperature gas reactor (HTGR) was built in the 1960's. Thirteen OECD countries began a project in 1959 to build an experimental reactor known as Dragon at Winfrith in the UK. The reactor - which operated successfully between 1966 and 1975 - had a thermal output of 20 MW and achieved a gas outlet temperature of 750 deg. C. The High Temperature Reactor concept, if it justified its expectations, was seen as having its place as an advanced thermal reactor between the current thermal reactor types such as the PWR, BWR, and AGR and the sodium cooled fast breeder reactor. It was expected that the HTR would offer better thermal efficiency, better uranium utilisation, either with low enriched uranium fuel or high enriched uranium thorium fuel, better inherent safety and lower unit power costs. In the event all these potential advantages were demonstrated to be in principle achievable. This view is still shared today. In fact Very High Temperature Reactors is one of the concepts retained for Generation IV. Projects on constructing Modular Pebble Bed Reactors are under way. Here all available Dragon Project Reports (DPR) - approximately 1000 - are collected in electronic form. An index points to the reports (PDF format); each table in the report is accessible in EXCEL format with the aim of facilitating access to the data. These reports describe the design, experiments and modelling carried out over a period of 17 years. 2 - Related or auxiliary information: IRPHE-HTR-ARCH-01, Archive of HTR Primary Documents NEA-1728/01. 3 - Software requirements: Acrobat Reader, Microsoft Word, HTML Browser required

  9. When Serious Project Management is a Critical Business Requirement

    Science.gov (United States)

    Jansma, P. A.; Gibby, L.; Chambers, C.; Joines, J.; Egger, R.

    2000-01-01

    When serious project management is a critical business requirement, project managers need to integrate cost, schedule and technical scope of work across the project, and apply earned value management (EVM).

  10. A Framework for Requirement Elicitation, Analysis, Documentation and Prioritisation under Uncertainty

    NARCIS (Netherlands)

    Rajabali Nejad, Mohammadreza; Mladenov, V.

    2015-01-01

    This paper offers a pluralistic framework for coping with requirements in the early phases of design where there is lack of knowledge about a system, its architect and functions. The framework is used to elicit, analyze, document and prioritize the requirements. It embeds probabilistic approach and

  11. 42 CFR 495.336 - Health information technology planning advance planning document requirements (HIT PAPD).

    Science.gov (United States)

    2010-10-01

    ... 42 Public Health 5 2010-10-01 2010-10-01 false Health information technology planning advance... STANDARDS FOR THE ELECTRONIC HEALTH RECORD TECHNOLOGY INCENTIVE PROGRAM Requirements Specific to the Medicaid Program § 495.336 Health information technology planning advance planning document requirements...

  12. Commercial agreements and documentation relevant for project financing renewable energy schemes

    International Nuclear Information System (INIS)

    1997-01-01

    Renewable energy projects covered by the NFFO Orders are distinguished by the fact that the key contract in any project is in effect a standard form contract in the form of the Power Purchase Agreement with the Non-Fossil Purchasing Agency Limited (''NFPA''). However our research has indicated that general contract standardization is unlikely to be practicable in the short term, although it is thought that the production of a range of specimen documents in the context of this study with input from various representative industry associations could lead to a more consistent approach to the negotiation and structuring of projects and facilitate the presentation of projects at the funding stage. We have produced a suite of documents which are specimens of the sorts of agreements that lenders are likely to find acceptable. The range of documents which we have produced covers the principal contractual arrangements for a typical renewable energy project (including full text or abridged agreements), for a land lease and for agreements for design and build, operation and maintenance, waste supply, wind lease, landfill gas, and forestry residue supply. We have produced an insurance scope of cover and financing documentation including a due diligence check list, term sheet, and a facility agreement with related security documentation. (author)

  13. Technical Requirements Analysis and Control Systems (TRACS) Initial Operating Capability (IOC) documentation

    Science.gov (United States)

    Hammond, Dana P.

    1991-01-01

    The Technical Requirements Analysis and Control Systems (TRACS) software package is described. TRACS offers supplemental tools for the analysis, control, and interchange of project requirements. This package provides the fundamental capability to analyze and control requirements, serves a focal point for project requirements, and integrates a system that supports efficient and consistent operations. TRACS uses relational data base technology (ORACLE) in a stand alone or in a distributed environment that can be used to coordinate the activities required to support a project through its entire life cycle. TRACS uses a set of keyword and mouse driven screens (HyperCard) which imposes adherence through a controlled user interface. The user interface provides an interactive capability to interrogate the data base and to display or print project requirement information. TRACS has a limited report capability, but can be extended with PostScript conventions.

  14. Metric Documentation of Cultural Heritage: Research Directions from the Italian Gamher Project

    Science.gov (United States)

    Bitelli, G.; Balletti, C.; Brumana, R.; Barazzetti, L.; D'Urso, M. G.; Rinaudo, F.; Tucci, G.

    2017-08-01

    GAMHer is a collaborative project that aims at exploiting and validating Geomatics algorithms, methodologies and procedures in the framework of new European regulations, which require a more extensive and productive use of digital information, as requested by the Digital Agenda for Europe as one of the seven pillars of the Europe 2020 Strategy. To this aim, GAMHer focuses on the need of a certified accuracy for surveying and monitoring projects with photogrammetry and laser scanning technologies, especially when used in a multiscale approach for landscape and built heritage documentation, conservation, and management. The approach used follows a multi-LoD (level of detail) transition that exploits GIS systems at the landscape scale, BIM technology and "point cloud based" 3d modelling for the scale of the building, and an innovative BIM/GIS integrated approach to foster innovation, promote users' collaboration and encourage communication between users. The outcomes of GAMHer are not intended to be used only by a community of Geomatics specialists, but also by a heterogeneous user community that exploit images and laser scans in their professional activities.

  15. METRIC DOCUMENTATION OF CULTURAL HERITAGE: RESEARCH DIRECTIONS FROM THE ITALIAN GAMHER PROJECT

    Directory of Open Access Journals (Sweden)

    G. Bitelli

    2017-08-01

    Full Text Available GAMHer is a collaborative project that aims at exploiting and validating Geomatics algorithms, methodologies and procedures in the framework of new European regulations, which require a more extensive and productive use of digital information, as requested by the Digital Agenda for Europe as one of the seven pillars of the Europe 2020 Strategy. To this aim, GAMHer focuses on the need of a certified accuracy for surveying and monitoring projects with photogrammetry and laser scanning technologies, especially when used in a multiscale approach for landscape and built heritage documentation, conservation, and management. The approach used follows a multi-LoD (level of detail transition that exploits GIS systems at the landscape scale, BIM technology and “point cloud based” 3d modelling for the scale of the building, and an innovative BIM/GIS integrated approach to foster innovation, promote users’ collaboration and encourage communication between users. The outcomes of GAMHer are not intended to be used only by a community of Geomatics specialists, but also by a heterogeneous user community that exploit images and laser scans in their professional activities.

  16. Documenting cost and performance for environmental remediation projects: Department of Energy Office of Environmental Management

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-08-08

    The purpose of this DOE guide is to facilitate the use of consistent procedures to document cost and performance information for projects involving the remediation of media contaminated with hazardous and radioactive wastes. It provides remedial action project managers with a standardized set of data to document completed remediation projects. Standardized reporting of data will broaden the utility of the information, increase confidence in the effectiveness of future remedial technologies, and enhance the organization, storage and retrieval of relevant information for future cleanup projects. The foundation for this guide was laid down by the Federal Remediation Technologies Roundtable (FRTR) in their publication, Guide to Documenting Cost and Performance for Remediation Projects, EPA-542-B- 95-002. Member agencies of the FRTR include the US EPA, the US DOD, the US DOE, and the US DOI. All the member agencies are involved in site remediation projects and anticipate following the guidance provided in the above reference. Therefore, there is much to be gained for DOE to be consistent with the other member agencies as it will be easier to compare projects across different agencies and also to learn from the experiences of a wider spectrum of prior completed projects.

  17. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  18. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    International Nuclear Information System (INIS)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment

  19. Waste encapsulation storage facility (WESF) standards/requirements identification document (S/RIDS)

    Energy Technology Data Exchange (ETDEWEB)

    Maddox, B.S., Westinghouse Hanford

    1996-07-29

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ES{ampersand}H) standards/requirements for the Waste Encapsulation Storage Facility (WESF). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  20. Performing the processing required for automatically get a PDF/A version of the CERN Library documentation

    CERN Document Server

    Molina Garcia-Retamero, Antonio

    2015-01-01

    The aim of the project was to perform the processing required for automatically get a PDF/A version of the CERN Library documentation. For this, it is necessary to extract as much metadata as possible from the sources files, inject the required data into the original source files creating new ones ready for being compiled with all related dependencies. Besides, I’ve proposed the creation of a HTML version consistent with the PDF and navigable for easy access, I’ve been trying to perform some Natural Language Processing for extracting metadata, I’ve proposed the injection of the cern library documentation into the HTML version of the long writeups where it is referenced (for instance, when a CERN Library function is referenced in a sample code) Finally, I’ve designed and implemented a Graphical User Interface in order to simplify the process for the user.

  1. Functions and requirements for Project W-236B, Initial Pretreatment Module: Revision 1

    International Nuclear Information System (INIS)

    Swanson, L.M.

    1994-01-01

    Hanford Site tank waste supernatants will be pretreated to separate the low-level and high-level fractions. The low-level waste fraction, containing the bulk of the chemical constituents, must be processed into a vitrified waste product which will be disposed of onsite, in a safe, environmentally sound, and cost effective manner. The high-level waste fraction separated during supernatant pretreatment (primarily cesium) will be recombined with an additional high-level waste fraction generated from pretreatment of the tank waste sludges and solids. This combined high-level waste fraction will be immobilized as glass and disposed in a geological repository. The purpose of this document is to establish the functional requirements baseline for Project W-236B, Initial Pretreatment Module, by defining the level 5 and 6 functions and requirements for the project. A functional analysis approach has been used to break down the program functions and associated physical requirements that each function must meet. As the systems engineering process evolves, the design requirements document will replace this preliminary functions and requirements document. The design requirements document (DRD) will identify key decisions and associated uncertainties that impact the project. A revision of this document to a DRD is not expected to change the performance requirements or open issues. However, additional requirements and issues may be identified

  2. Global Change Data Base Pilot (Diskette) Project for Africa. Dase base documentation version 1.1

    Science.gov (United States)

    1992-06-01

    The data base for Africa contains vegetation data, climate data, and other thematic data for a recent three and a half year period. The documentation contains separate chapters of material edited about separate data sets of the overall Global Change Data Base, Pilot (diskette) Project for Africa. Descriptions of data formats, authors, and contributors are accompanied by documentation of the development/use of the data. These materials have been suggested and contributed directly by the authors of the individual data sets. To avoid confusion, some information contained in the documentation that is not directly relevant to the data base has been either omitted, crossed out, or blanked out.

  3. ENHANCED CHARACTERIZATION OF THE REPOSITORY BLOCK REQUIREMENTS DOCUMENT (ECRB-RD)

    International Nuclear Information System (INIS)

    G.M. Teraoka

    1998-01-01

    This Enhanced Characterization of the Repository Block Requirements Document (ECRB-RD) provides applicable design and construction requirements for the Enhanced Characterization of the Repository Block (ECRB) East-West Drift and its associated equipment. This document also identifies the applicable requirements from the Exploratory Studies Facilities Design Requirements (ESFDR) Document (YMPICM-00 19, Revision 2, ICN- 1) for design and construction of the ECRB East-West Drift, ground support, constructor support utilities and components. These requirements have been tailored specifically for the ECRB East-West Drift design and construction. The allocated requirements for the ECRB East-West Drift are in Sections III through VI. The requirements in sections III through VI contain requirement numbers from the ESFDR, Rev 2, ICN-1 for reference back to the ESFDR. Each requirement in the ECRB-RD also identifies a trace to the Site Design and Test Requirements Document (YMP/CM-0021, Rev. 2, ICN-1) and 10CFR60 similar to the style used in the ESFDR. These traces to 10CFR60 are consistent with the 1995 version of 10CFR60 used by the SD and TRD and the ESFDR. Those ESFDR requirements statements that were technically modified are identified as such and those that were derived as part of this allocation are also identified. An activity evaluation has been performed in accordance with QAP-2-0 and has determined that the QA program is applicable to this document. Therefore, the development of this document was performed in compliance with QAP-3-5, Revision 7, Development of Technical Documents and checked and reviewed in compliance with Section 5.3. This is consistent with the IOC from R. Stambaugh to M. Lugo on the subject of ECRB-RD, Revision 1, TDPP Applicability (LV.SEI.,RMS.03/98-0 12, Dated 3/12/98). The ECRB East-West Drift includes those excavated underground openings to support enhanced characterization testing activities for the repository block and provides potential

  4. Safeguards Guidance Document for Designers of Commercial Nuclear Facilities: International Nuclear Safeguards Requirements and Practices For Uranium Enrichment Plants

    Energy Technology Data Exchange (ETDEWEB)

    Robert Bean; Casey Durst

    2009-10-01

    This report is the second in a series of guidelines on international safeguards requirements and practices, prepared expressly for the designers of nuclear facilities. The first document in this series is the description of generic international nuclear safeguards requirements pertaining to all types of facilities. These requirements should be understood and considered at the earliest stages of facility design as part of a new process called “Safeguards-by-Design.” This will help eliminate the costly retrofit of facilities that has occurred in the past to accommodate nuclear safeguards verification activities. The following summarizes the requirements for international nuclear safeguards implementation at enrichment plants, prepared under the Safeguards by Design project, and funded by the U.S. Department of Energy (DOE) National Nuclear Security Administration (NNSA), Office of NA-243. The purpose of this is to provide designers of nuclear facilities around the world with a simplified set of design requirements and the most common practices for meeting them. The foundation for these requirements is the international safeguards agreement between the country and the International Atomic Energy Agency (IAEA), pursuant to the Treaty on the Non-proliferation of Nuclear Weapons (NPT). Relevant safeguards requirements are also cited from the Safeguards Criteria for inspecting enrichment plants, found in the IAEA Safeguards Manual, Part SMC-8. IAEA definitions and terms are based on the IAEA Safeguards Glossary, published in 2002. The most current specification for safeguards measurement accuracy is found in the IAEA document STR-327, “International Target Values 2000 for Measurement Uncertainties in Safeguarding Nuclear Materials,” published in 2001. For this guide to be easier for the designer to use, the requirements have been restated in plainer language per expert interpretation using the source documents noted. The safeguards agreement is fundamentally a

  5. Perceived Effects of Prevalent Errors in Contract Documents on Construction Projects

    Directory of Open Access Journals (Sweden)

    Oluwaseun Sunday Dosumu

    2018-03-01

    Full Text Available One of the highly rated causes of poor performance is errors in contract documents. The objectives of this study are to investigate the prevalent errors in contract documents and their effects on construction projects. Questionnaire survey and 51 case study projects (mixed method were adopted for the study. The study also involved the use of Delphi technique to extract the possible errors that may be contained in contract documents; it did not however constitute the empirical data for the study. The sample of the study consists of 985 consulting and 275 contracting firms that engaged in the construction of building projects that were completed between 2013 and 2016 and were above the ground floor. The two-stage stratified random sampling technique was adopted for the study. The data for the study were analysed with descriptive and inferential statistics (based on Shapiro-Wilk’s test. The results of the study indicate that errors in contract documents were moderately prevalent. However, overmeasurement in bill of quantities was prevalent in private, institutional and management procured projects. Traditionally procured projects contain 68% of the errors in contract documents among the procurement methods. Drawings contain the highest number of errors, followed by bill of quantities and specifications. The severe effects of errors in contract documents were structural collapse, deterioration of buildings and contractors’ claims among others. The result of the study implies that, management procurement method is the route to error minimization in developing countries, but it may need to be backed by law and guarded against overmeasurement.

  6. Functions and requirements for tank farm restoration and safe operations, Project W-314. Revision 3

    International Nuclear Information System (INIS)

    Garrison, R.C.

    1995-01-01

    This Functions and Requirements document (FRD) establishes the basic performance criteria for Project W-314, in accordance with the guidance outlined in the letter from R.W. Brown, RL, to President, WHC, ''Tank Waste Remediation System (TWRS) Project Documentation Methodology,'' 94-PRJ-018, dated 3/18/94. The FRD replaces the Functional Design Criteria (FDC) as the project technical baseline documentation. Project W-314 will improve the reliability of safety related systems, minimize onsite health and safety hazards, and support waste retrieval and disposal activities by restoring and/or upgrading existing Tank Farm facilities and systems. The scope of Project W-314 encompasses the necessary restoration upgrades of the Tank Farms' instrumentation, ventilation, electrical distribution, and waste transfer systems

  7. IDC Re-Engineering Phase 2 System Requirements Document V1.3.

    Energy Technology Data Exchange (ETDEWEB)

    Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Burns, John F. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Satpathi, Meara Allena [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2015-12-01

    This System Requirements Document (SRD) defines waveform data processing requirements for the International Data Centre (IDC) of the Comprehensive Nuclear Test Ban Treaty Organization (CTBTO). The IDC applies, on a routine basis, automatic processing methods and interactive analysis to raw International Monitoring System (IMS) data in order to produce, archive, and distribute standard IDC products on behalf of all States Parties. The routine processing includes characterization of events with the objective of screening out events considered to be consistent with natural phenomena or non-nuclear, man-made phenomena. This document does not address requirements concerning acquisition, processing and analysis of radionuclide data but includes requirements for the dissemination of radionuclide data and products.

  8. IDC Re-Engineering Phase 2 System Requirements Document Version 1.4

    Energy Technology Data Exchange (ETDEWEB)

    Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Burns, John F. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Satpathi, Meara Allena [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2017-01-01

    This System Requirements Document (SRD) defines waveform data processing requirements for the International Data Centre (IDC) of the Comprehensive Nuclear Test Ban Treaty Organization (CTBTO). The IDC applies, on a routine basis, automatic processing methods and interactive analysis to raw International Monitoring System (IMS) data in order to produce, archive, and distribute standard IDC products on behalf of all States Parties. The routine processing includes characterization of events with the objective of screening out events considered to be consistent with natural phenomena or non-nuclear, man-made phenomena. This document does not address requirements concerning acquisition, processing and analysis of radionuclide data, but includes requirements for the dissemination of radionuclide data and products.

  9. Step 1: Human System Interface (HSI) Functional Requirements Document (FRD). Version 2

    Science.gov (United States)

    2006-01-01

    This Functional Requirements Document (FRD) establishes a minimum set of Human System Interface (HSI) functional requirements to achieve the Access 5 Vision of "operating High Altitude, Long Endurance (HALE) Unmanned Aircraft Systems (UAS) routinely, safely, and reliably in the National Airspace System (NAS)". Basically, it provides what functions are necessary to fly UAS in the NAS. The framework used to identify the appropriate functions was the "Aviate, Navigate, Communicate, and Avoid Hazards" structure identified in the Access 5 FRD. As a result, fifteen high-level functional requirements were developed. In addition, several of them have been decomposed into low-level functional requirements to provide more detail.

  10. 1 CFR 5.2 - Documents required to be filed for public inspection and published.

    Science.gov (United States)

    2010-01-01

    ... inspection and published. 5.2 Section 5.2 General Provisions ADMINISTRATIVE COMMITTEE OF THE FEDERAL REGISTER THE FEDERAL REGISTER GENERAL § 5.2 Documents required to be filed for public inspection and published... Register and published in the Federal Register: (a) Presidential proclamations and Executive orders in the...

  11. 45 CFR 400.43 - Requirements for documentation of refugee status.

    Science.gov (United States)

    2010-10-01

    ... 45 Public Welfare 2 2010-10-01 2010-10-01 false Requirements for documentation of refugee status. 400.43 Section 400.43 Public Welfare Regulations Relating to Public Welfare OFFICE OF REFUGEE RESETTLEMENT, ADMINISTRATION FOR CHILDREN AND FAMILIES, DEPARTMENT OF HEALTH AND HUMAN SERVICES REFUGEE...

  12. 42 CFR 495.338 - Health information technology implementation advance planning document requirements (HIT IAPD).

    Science.gov (United States)

    2010-10-01

    ... 42 Public Health 5 2010-10-01 2010-10-01 false Health information technology implementation... CERTIFICATION STANDARDS FOR THE ELECTRONIC HEALTH RECORD TECHNOLOGY INCENTIVE PROGRAM Requirements Specific to the Medicaid Program § 495.338 Health information technology implementation advance planning document...

  13. 50 CFR 23.20 - What CITES documents are required for international trade?

    Science.gov (United States)

    2010-10-01

    ... international trade? 23.20 Section 23.20 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE..., EXPORTATION, AND IMPORTATION OF WILDLIFE AND PLANTS (CONTINUED) CONVENTION ON INTERNATIONAL TRADE IN... CITES documents are required for international trade? (a) Purpose. Articles III, IV, and V of the Treaty...

  14. 50 CFR 23.18 - What CITES documents are required to export Appendix-I wildlife?

    Science.gov (United States)

    2010-10-01

    ... 50 Wildlife and Fisheries 6 2010-10-01 2010-10-01 false What CITES documents are required to export Appendix-I wildlife? 23.18 Section 23.18 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE..., EXPORTATION, AND IMPORTATION OF WILDLIFE AND PLANTS (CONTINUED) CONVENTION ON INTERNATIONAL TRADE IN...

  15. 48 CFR 752.7005 - Submission requirements for development experience documents.

    Science.gov (United States)

    2010-10-01

    ... (referenced in paragraph (a)(1) of this clause) in electronic format and hard copy (one copy) to U.S. Agency... final equivalent of the hard copy submitted. (iv) Acceptable software formats for electronic documents... paragraph (b)(1)(i) of this clause. (2) Format. (i) Descriptive information is required for all Contractor...

  16. IDC System Specification Document.

    Energy Technology Data Exchange (ETDEWEB)

    Clifford, David J.

    2014-12-01

    This document contains the system specifications derived to satisfy the system requirements found in the IDC System Requirements Document for the IDC Reengineering Phase 2 project. Revisions Version Date Author/Team Revision Description Authorized by V1.0 12/2014 IDC Reengineering Project Team Initial delivery M. Harris

  17. Determination of Waste Isolation Pilot Plant (WIPP) management and institutional requirements documents for contact-handled (CH) critical systems

    International Nuclear Information System (INIS)

    1990-01-01

    This document lists the critical requirements documents applicable to the receipt of contact-handled waste at the Waste Isolation Pilot Plant. It also describes the processes used to determine the applicability of each document. This analysis is based on the applicable documents that were in effect in the February 1988 time frame. 2 refs

  18. Lawrence Livermore National Laboratory Emergency Response Capability Baseline Needs Assessment Requirement Document

    Energy Technology Data Exchange (ETDEWEB)

    Sharry, J A

    2009-12-30

    This revision of the LLNL Fire Protection Baseline Needs Assessment (BNA) was prepared by John A. Sharry, LLNL Fire Marshal and LLNL Division Leader for Fire Protection and reviewed by Martin Gresho, Sandia/CA Fire Marshal. The document follows and expands upon the format and contents of the DOE Model Fire Protection Baseline Capabilities Assessment document contained on the DOE Fire Protection Web Site, but only address emergency response. The original LLNL BNA was created on April 23, 1997 as a means of collecting all requirements concerning emergency response capabilities at LLNL (including response to emergencies at Sandia/CA) into one BNA document. The original BNA documented the basis for emergency response, emergency personnel staffing, and emergency response equipment over the years. The BNA has been updated and reissued five times since in 1998, 1999, 2000, 2002, and 2004. A significant format change was performed in the 2004 update of the BNA in that it was 'zero based.' Starting with the requirement documents, the 2004 BNA evaluated the requirements, and determined minimum needs without regard to previous evaluations. This 2010 update maintains the same basic format and requirements as the 2004 BNA. In this 2010 BNA, as in the previous BNA, the document has been intentionally divided into two separate documents - the needs assessment (1) and the compliance assessment (2). The needs assessment will be referred to as the BNA and the compliance assessment will be referred to as the BNA Compliance Assessment. The primary driver for separation is that the needs assessment identifies the detailed applicable regulations (primarily NFPA Standards) for emergency response capabilities based on the hazards present at LLNL and Sandia/CA and the geographical location of the facilities. The needs assessment also identifies areas where the modification of the requirements in the applicable NFPA standards is appropriate, due to the improved fire protection

  19. Radiation Requirements for Uranium Mining Projects

    International Nuclear Information System (INIS)

    Hondros, Jim

    2014-01-01

    Conclusions: • Radiation impact can be complex and confusing; • Aim to be credible and competent; • Process can be straightforward; – Baseline monitoring; – Project emissions; – Impact of emission; – Management measures. • “Tell the story” (what does it all mean)

  20. Preliminary waste acceptance requirements - Konrad repository project

    International Nuclear Information System (INIS)

    Brennecke, P.W.; Warnecke, E.H.

    1991-01-01

    In Germany, the planned Konrad repository is proposed for the disposal of all types of radioactive wastes whose thermal influence upon the host rock is negligible. The Bundesamt fuer Strahlenschutz has established Preliminary Waste Acceptance Requirements (as of April 1990) for this facility. The respective requirements were developed on the basis of the results of site-specific safety assessments. They include general requirements on the waste packages to be disposed of as well as more specific requirements on the waste forms, the packaging and the radionuclide inventory per waste package. In addition, the delivery of waste packages was regulated. An outline of the structure and the elements of the Preliminary Waste Acceptance Requirements of April 1990 is given including comments on their legal status. (Author)

  1. Fiscal Year 2001 Tank Characterization Technical Sampling Basis and Waste Information Requirements Document

    International Nuclear Information System (INIS)

    ADAMS, M.R.

    2000-01-01

    The Fiscal Year 2001 Tank Characterization Technical Sampling Basis and Waste Information Requirements Document (TSB-WIRD) has the following purposes: (1) To identify and integrate sampling and analysis needs for fiscal year (FY) 2001 and beyond. (2) To describe the overall drivers that require characterization information and to document their source. (3) To describe the process for identifying, prioritizing, and weighting issues that require characterization information to resolve. (4) To define the method for determining sampling priorities and to present the sampling priorities on a tank-by-tank basis. (5) To define how the characterization program is going to satisfy the drivers, close issues, and report progress. (6)To describe deliverables and acceptance criteria for characterization deliverables

  2. Guidance for preparing user requirements documents for small and medium reactors and their application

    International Nuclear Information System (INIS)

    2000-08-01

    During the past decade, several countries with highly developed nuclear power programs established user required documents (URDs) to guide the development and implementation of advanced light water reactors. These efforts built upon the extensive experience with operating reactors and included new insights from ongoing research and development to enhance the economic performance and safety of future nuclear power plants. Subsequently, a number of developing countries with plans for introducing nuclear energy into their national programs expressed strong interest in establishing analogous requirements. The IAEA has therefore taken the initiative to assist in the elaboration of such requirements. Building upon relevant documents this report recommends a URD structure and content outline to support developing countries in preparing their URDs for various applications of small and medium reactors (e.g. electricity generation and/or desalination). This report was prepared by representatives from both developing and developed Member States

  3. Requirements: Towards an understanding on why software projects fail

    Science.gov (United States)

    Hussain, Azham; Mkpojiogu, Emmanuel O. C.

    2016-08-01

    Requirement engineering is at the foundation of every successful software project. There are many reasons for software project failures; however, poorly engineered requirements process contributes immensely to the reason why software projects fail. Software project failure is usually costly and risky and could also be life threatening. Projects that undermine requirements engineering suffer or are likely to suffer from failures, challenges and other attending risks. The cost of project failures and overruns when estimated is very huge. Furthermore, software project failures or overruns pose a challenge in today's competitive market environment. It affects the company's image, goodwill, and revenue drive and decreases the perceived satisfaction of customers and clients. In this paper, requirements engineering was discussed. Its role in software projects success was elaborated. The place of software requirements process in relation to software project failure was explored and examined. Also, project success and failure factors were also discussed with emphasis placed on requirements factors as they play a major role in software projects' challenges, successes and failures. The paper relied on secondary data and empirical statistics to explore and examine factors responsible for the successes, challenges and failures of software projects in large, medium and small scaled software companies.

  4. Analysis of compatibility of current Czech initial documentation in the area of technical assurance of nuclear safety with the requirements of the EUR document

    International Nuclear Information System (INIS)

    Zdebor, J.; Zdebor, R.; Kratochvil, L.

    2001-11-01

    The publication is structured as follows: Description of existing documentation. General requirements, goals, principles and design principles: Documents being compared; Method of comparison; Results and partial evaluation of comparison of requirements between EUR and Czech regulations (basic goals and safety philosophy; quantitative safety objectives; basic design requirements; extended design requirements; external and internal threats; technical requirements; site conditions); Summary of the comparison of safety requirements. Comparison of requirements for the systems: Requirements for the nuclear reactor unit systems; Barrier systems (fuel system; reactor cooling system; containment system); Remaining systems (control systems; protection systems; coolant makeup and purification system; residual heat removal system; emergency cooling system; power systems); Common technical requirements for systems (technical requirements for systems; internal and external events). (P.A.)

  5. Functional Requirements Document for HALE UAS Operations in the NAS: Step 1. Version 3

    Science.gov (United States)

    2006-01-01

    The purpose of this Functional Requirements Document (FRD) is to compile the functional requirements needed to achieve the Access 5 Vision of "operating High Altitude, Long Endurance (HALE) Unmanned Aircraft Systems (UAS) routinely, safely, and reliably in the national airspace system (NAS)" for Step 1. These functional requirements could support the development of a minimum set of policies, procedures and standards by the Federal Aviation Administration (FAA) and various standards organizations. It is envisioned that this comprehensive body of work will enable the FAA to establish and approve regulations to govern safe operation of UAS in the NAS on a routine or daily "file and fly" basis. The approach used to derive the functional requirements found within this FRD was to decompose the operational requirements and objectives identified within the Access 5 Concept of Operations (CONOPS) into the functions needed to routinely and safely operate a HALE UAS in the NAS. As a result, four major functional areas evolved to enable routine and safe UAS operations for an on-demand basis in the NAS. These four major functions are: Aviate, Navigate, Communicate, and Avoid Hazards. All of the functional requirements within this document can be directly traceable to one of these four major functions. Some functions, however, are traceable to several, or even all, of these four major functions. These cross-cutting functional requirements support the "Command / Control: function as well as the "Manage Contingencies" function. The requirements associated to these high-level functions and all of their supporting low-level functions are addressed in subsequent sections of this document.

  6. MORE - Management of requirements in NPP modernisation projects. Project report 2006

    Energy Technology Data Exchange (ETDEWEB)

    Thunem, A.P.J.; Thunem, H.P.J. [IFE (Norway); Valkonen, J. [VTT (Finland)

    2007-02-15

    The purpose of the report is to document the work and related activities in the period January 1 December 31 in 2006, including dissemination activities. The work in this period has been concentrated on further research for adopting an approach for dependable requirements engineering and its supporting tool. The majority of the efforts in 2006, however, was spent on making the researchers, developers, utilities and licensees more aware of the importance of the area of requirements engineering, and in that respect organising an international seminar on dependable requirements engineering. This seminar was defined as a deliverable in the Activity Plan for 2006 and became also the most important deliverable for 2006. Therefore, this report naturally features a detailed summary of the seminar, which proved to be a true success and at the same time a door opener for more initiatives within the topic, proposed by several participants. More efforts within dissemination of the background and objectives of the project MORE within the nuclear community and towards NPPs that do carry out modernisation projects continued to be one important focus. (au)

  7. MORE - Management of requirements in NPP modernisation projects. Project report 2006

    International Nuclear Information System (INIS)

    Thunem, A.P.J.; Thunem, H.P.J.; Valkonen, J.

    2007-02-01

    The purpose of the report is to document the work and related activities in the period January 1 December 31 in 2006, including dissemination activities. The work in this period has been concentrated on further research for adopting an approach for dependable requirements engineering and its supporting tool. The majority of the efforts in 2006, however, was spent on making the researchers, developers, utilities and licensees more aware of the importance of the area of requirements engineering, and in that respect organising an international seminar on dependable requirements engineering. This seminar was defined as a deliverable in the Activity Plan for 2006 and became also the most important deliverable for 2006. Therefore, this report naturally features a detailed summary of the seminar, which proved to be a true success and at the same time a door opener for more initiatives within the topic, proposed by several participants. More efforts within dissemination of the background and objectives of the project MORE within the nuclear community and towards NPPs that do carry out modernisation projects continued to be one important focus. (au)

  8. Functional requirements document for NASA/MSFC Earth Science and Applications Division: Data and information system (ESAD-DIS). Interoperability, 1992

    Science.gov (United States)

    Stephens, J. Briscoe; Grider, Gary W.

    1992-01-01

    These Earth Science and Applications Division-Data and Information System (ESAD-DIS) interoperability requirements are designed to quantify the Earth Science and Application Division's hardware and software requirements in terms of communications between personal and visualization workstation, and mainframe computers. The electronic mail requirements and local area network (LAN) requirements are addressed. These interoperability requirements are top-level requirements framed around defining the existing ESAD-DIS interoperability and projecting known near-term requirements for both operational support and for management planning. Detailed requirements will be submitted on a case-by-case basis. This document is also intended as an overview of ESAD-DIs interoperability for new-comers and management not familiar with these activities. It is intended as background documentation to support requests for resources and support requirements.

  9. Projections of energy requirements and their implications

    International Nuclear Information System (INIS)

    Hogroian, P.

    1978-01-01

    The subject is covered in sections, entitled as shown. Numerical data are indicated in parenthesis. The record of nuclear power forecasting (estimates of the growth of world nuclear power, penetration of the electric power market by nuclear power); brief review of energy forecasting techniques and problems; some views of future world energy demand (estimates of world primary energy requirements); possible allocations of energy resources to needs (allocation of resources (oil, oil from tar sands, shale, natural gas, coal, coal to gasification, hydroelectricity, renewable resources, nuclear) to the world's primary energy needs in the year 2000); observations on the adequacy of energy resources; implications for nuclear energy (postulated growth of world nuclear power, annual fuel cycle requirements of the world, annual uranium requirements of the world). (U.K.)

  10. Program prioritization system user requirements document for Gas Cooled Reactor Associates

    International Nuclear Information System (INIS)

    1981-01-01

    Efficient management of the national HTGR program requires the establishment of an information system that will facilitate a more rational allocation of resources and task prioritization consistent with program policies. The system described in this document provides a data analysis mechanism for processing top level summary status and planning information in a rapid, timely and selective manner. Data produced by the system can be used by management to provide a rational basis for prioritizing tasks, evaluating program changes and program planning regarding costs, schedules and overall program development logic. The purpose of this document is to delineate the program prioritization system (PPS) requirements for use as a guide to acquiring and implementing the system

  11. Meeting the requirements for a DOE environmental restoration project. The Fernald strategy

    International Nuclear Information System (INIS)

    Vanoss, R.L.; Risenhoover, G.M.

    1994-01-01

    Environmental Restoration (ER) of five Operable Units (OU) at Fernald Environmental Management Project (FEMP) includes compliance with the requirements of Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), Resource Conservation Recovery Act (RCRA), National Environmental Policy Act (NEPA), and DOE Orders. Each regulatory driver has differing procedural requirements for documenting calculations, decisions, and actions involved in site cleanup. Integration of documentation and avoidance of duplication can save time and money. Such savings are being achieved by OU specific application of supporting studies, revised procedures, and guidance documents. Each OU is seeking appropriate opportunities to produce single documents that simultaneously fulfill the important requirements of the other regulations and DOE orders. These opportunities are evaluated at all phases of decision making, remedial design, and remedial action. Three essential processes precede environmental restoration/remedial action at a DOE site/project: 1. Completion of decision-making documents required by governing or applicable statutes. 2. Completion of important scientific and engineering analyses of remedial alternatives, and design and implementation of the remedial solution established in the CERCLA Record of Decision (ROD). 3. Preparation of DOE-mandated documentation to record engineering evaluations and cost estimates required for budgeting, decision making, and project management. Methodology and requirements for each process have developed from long, successful practice, but independently of each other. FERMCO, as new DOE contractor at Fernald and first Environmental Restoration Management Contractor (ERMC), is committed to a process of Continuous Performance Improvement (CPI). A major reevaluation of documentation and processes for support of environmental decision-making and design of cleanup activities to remediate the five OUs at the FEMP is being undertaken

  12. Use of communication technologies in document exchange for the management of construction projects

    Science.gov (United States)

    Mesároš, Peter; Mandičák, Tomáš

    2016-06-01

    Information and communication technologies represent a set of people, processes, technical and software tools providing collection, transport, storage and processing of data for distribution and presentation of information. Particularly communication systems are the main tool for information exchange. Of the other part, these technologies have a broad focus and use. One of them is the exchange of documents in the management of construction projects. Paper discusses the issue of exploitation level of communication technologies in construction project management. The main objective of this paper is to analyze exploitation level of communication technologies. Another aim of the paper is to compare exploitation level or rate of document exchange by electronic communication devices and face-to-face communication.

  13. Use of communication technologies in document exchange for the management of construction projects

    Directory of Open Access Journals (Sweden)

    Mesároš Peter

    2016-06-01

    Full Text Available Information and communication technologies represent a set of people, processes, technical and software tools providing collection, transport, storage and processing of data for distribution and presentation of information. Particularly communication systems are the main tool for information exchange. Of the other part, these technologies have a broad focus and use. One of them is the exchange of documents in the management of construction projects. Paper discusses the issue of exploitation level of communication technologies in construction project management. The main objective of this paper is to analyze exploitation level of communication technologies. Another aim of the paper is to compare exploitation level or rate of document exchange by electronic communication devices and face-to-face communication.

  14. UMTRA Surface Project management action process document. Final report: Revision 1

    International Nuclear Information System (INIS)

    1996-04-01

    A critical mission of the US Department of Energy (DOE) is the planning, implementation, and completion of environmental restoration (ER) programs at facilities that were operated by or in support of the former Atomic Energy Commission (AEC) from the late 1940s into the 1970s. Among these facilities are the 24 former uranium mill sites designed in the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (42 USC section 7901 et seq.) Title 1 of the UMTRCA authorized the DOE to undertake remedial actions at these designated sites and associated vicinity properties (VP), which contain uranium mill tailings and other residual radioactive materials (RRM) derived from the processing sites. Title 2 of the UMTRCA addresses uranium mill sites that were licensed at the time the UMTRCA was enacted. Cleanup of these Title 2 sites is the responsibility of the licensees. The cleanup of the Title 1 sites has been split into two separate projects: the Surface Project, which deals with the mill buildings, tailings, and contaminated soils at the sites and VPs; and the Ground Water Project, which is limited to the contaminated ground water at the sites. This management action process (MAP) document discusses the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project only; a separate MAP document has been prepared for the UMTRA Ground Water Project

  15. 50 CFR 300.185 - Documentation, reporting and recordkeeping requirements for consignment documents and re-export...

    Science.gov (United States)

    2010-10-01

    ... of presenting entry documentation for clearance by customs authorities (e.g., CBP Forms 7533 or 3461... apply to all imports of fish or fish products regulated under this subpart, into the Customs territory... landed overseas (HTS heading 9815). For insular possessions with customs territories separate from the...

  16. Projecting India's energy requirements for policy formulation

    International Nuclear Information System (INIS)

    Parikh, Kirit S.; Karandikar, Vivek; Rana, Ashish; Dani, Prasanna

    2009-01-01

    Energy policy has to have a long-term perspective. To formulate it one needs to know the contours of energy requirements and options. Different approaches have been followed in literature, each with their own problems. A top down econometric approach provides little guidance on policies, while a bottom up approval requires too much knowledge and too many assumptions. Using top-down econometric approach for aggregate overall benchmarking and a detailed activity analysis model, Integrated Energy System Model, for a few large sectors, provides a unique combination for easing the difficulties of policy formulation. The model is described in this paper. Eleven alternate scenarios are built, designed to map out extreme points of feasible options. Results show that even after employing all domestic energy resource to their full potential, there will be a continued rise of fossil fuel use, continued importance of coal, and continued rise of import dependence. Energy efficiency emerges as a major option with a potential to reduce energy requirement by as much as 17%. Scenario results point towards pushing for development of alternative sources. (author)

  17. Bibliography of documents and related materials collected for the Hawaii Geothermal Project Environmental Impact Statement

    Energy Technology Data Exchange (ETDEWEB)

    Glenn, F.M.; Boston, C.R.; Burns, J.C.; Hagan, C.W. Jr.; Saulsbury, J.W.; Wolfe, A.K.

    1995-03-01

    This report has been prepared to make available and archive information developed during preparation of the Environmental Impact Statement for Phases 3 and 4 of the Hawaii Geothermal Project as defined by the state of Hawaii in its April 1989 proposal to Congress. On May 17, 1994, the USDOE published a notice in the Federal Register withdrawing its Notice of Intent of February 14, 1992, to prepare the HGP EIS. Since the state of Hawaii is no longer pursuing or planning to pursue the HGP, DOE considers the project to be terminated. This report provides a bibliography of documents, published papers, and other reference materials that were obtained or used. The report provides citations for approximately 642 documents, published papers, and other reference materials that were gathered to describe the potentially affected environment on the islands of Hawaii, Maui, and Oahu. The listing also does not include all the reference materials developed by support subcontractors and cooperating agencies who participated in the project. This listing does not include correspondence or other types of personal communications. The documents listed in this report can be obtained from original sources or libraries.

  18. 18 CFR 806.4 - Projects requiring review and approval.

    Science.gov (United States)

    2010-04-01

    ... result of a change of the name, identity, internal corporate structure or place of organization and does... period, and undergoing a change of ownership, unless such project satisfies the requirements of..., and undergoing a change of ownership, unless such project satisfies the requirements of paragraphs (b...

  19. HALE UAS Command and Control Communications: Step 1 - Functional Requirements Document. Version 4.0

    Science.gov (United States)

    2006-01-01

    The High Altitude Long Endurance (HALE) unmanned aircraft system (UAS) communicates with an off-board pilot-in-command in all flight phases via the C2 data link, making it a critical component for the UA to fly in the NAS safely and routinely. This is a new requirement in current FAA communications planning and monitoring processes. This document provides a set of comprehensive C2 communications functional requirements and performance guidelines to help facilitate the future FAA certification process for civil UAS to operate in the NAS. The objective of the guidelines is to provide the ability to validate the functional requirements and in future be used to develop performance-level requirements.

  20. Documenting genomics: Applying archival theory to preserving the records of the Human Genome Project.

    Science.gov (United States)

    Shaw, Jennifer

    2016-02-01

    The Human Genome Archive Project (HGAP) aimed to preserve the documentary heritage of the UK's contribution to the Human Genome Project (HGP) by using archival theory to develop a suitable methodology for capturing the results of modern, collaborative science. After assessing past projects and different archival theories, the HGAP used an approach based on the theory of documentation strategy to try to capture the records of a scientific project that had an influence beyond the purely scientific sphere. The HGAP was an archival survey that ran for two years. It led to ninety scientists being contacted and has, so far, led to six collections being deposited in the Wellcome Library, with additional collections being deposited in other UK repositories. In applying documentation strategy the HGAP was attempting to move away from traditional archival approaches to science, which have generally focused on retired Nobel Prize winners. It has been partially successful in this aim, having managed to secure collections from people who are not 'big names', but who made an important contribution to the HGP. However, the attempt to redress the gender imbalance in scientific collections and to improve record-keeping in scientific organisations has continued to be difficult to achieve. Copyright © 2015 The Author. Published by Elsevier Ltd.. All rights reserved.

  1. Waste Receiving and Packaging, Module 2A, Supplemental Design Requirements Document

    International Nuclear Information System (INIS)

    Lamberd, D.L.; Boothe, G.F.; Hinkle, A.L.; Horgos, R.M.; LeClair, M.D.; Nash, C.R.; Ocampo, V.P.; Pauly, T.R.; Stroup, J.L.; Weingardt, K.M.

    1994-01-01

    The Supplemental Design Requirements Document (SDRD) is used to communicate plant design information from Westinghouse Hanford Company (WHC) to the US Department of Energy (DOE) and the cognizant Architect Engineer (A/E). Information in the SDRD serves two purposes: to convey design requirements that are too detailed for inclusion in a Functional Design Criteria (FDC) report; and to serve as a means of change control for design commitments in the Conceptual Design Report. The mission of WRAP 2A on the Hanford site is the treatment of contact handled low level mixed waste (MW) for final disposal. The overall systems engineering steps used to reach construction and operation of WRAP 2A are depicted in Figure 1. The WRAP 2A SDRD focuses on the requirements to address the functional analysis provided in Figure 1. This information is provided in sections 2 through 5 of this SDRD. The mission analysis and functional analysis are to be provided in a separate supporting document. The organization of sections 2 through 5 corresponds to the requirements identified in the WRAP 2A functional analysis

  2. Documentation of medical findings in radiation workers in the GDR to meet the requirements of ICRP publication 26

    International Nuclear Information System (INIS)

    Wolff, H.R.; Neumeister, K.

    1979-01-01

    Based on ICRP Publication 26, the future organization of the medical surveillance system for radiation workers in the GDR is considered in this paper. These radiation workers will also in future be medically supervised by means of pre-employment and routine examinations. It is considered necessary to have as extensive a registration as possible of information on medical examinations, working place analyses and incidents. Such data have to be collected and stored to be compared with other national and international projects (e.g. in the field of occupational health). In addition, they should permit epidemiological studies to be internationally co-ordinated. For this purpose, a documentation system has been prepared in the German Democratic Republic which is based on GDR experiences and makes it possible to specify the requirements of ICRP Publication 26. This system forms a new basis for mass examinations of occupationally exposed persons. Uniform examination methods tailored to meet the task of assuring occupational health in the GDR will be introduced. The documentation cards are meant to be used as clear-text cards suited for automatic reading by optical character recognition. The examination form consists of ten parts and comprises all details from working place situation to medical findings to laboratory results. It is felt that this new documentation system permits registration of all relevant data required for the effective radiation protection of man. On the basis of this documentation of findings, participation is scheduled in the respective international IAEA programmes and the studies proposed by the ICRP for problems of radiation-induced carcinogenesis and radiogenetics

  3. A fully updated version of the European utility requirement (EUR) documents is to be available

    International Nuclear Information System (INIS)

    Chatry, J.P.; Berbey, P.

    2001-01-01

    The major European electricity producers have worked on a common requirement document for future LWR plants since 1992 to get specifications acceptable together by the owners, the public and the authorities. Thus the designers can develop standard LWR designs that could be acceptable everywhere in Europe and the utilities can open their consultations to vendors on common bases. Public and authority's acceptance should be improved as well. Significant savings are expected in development and construction costs. Since the release of the last versions of the EUR texts in 1996, a lot of work has been carried out: reviews by the regulators and other external organisations, comparisons, assessment of compliance of designs vs. EUR and clarification works on the controversial topics that deserved changes or clarification. At the beginning of 1999 enough material was available to start a complete revision of the EUR document. Volumes 1 and 2 of the EUR document list generic nuclear island requirements. The main NPP vendors are developing advanced LWR designs for the European market, with reference to the EUR document. Volume 3 deals with the application of EUR to those designs. The EUR utilities -with contributions of the vendors- are writing specific parts of the EUR document that address some of these designs. Each part includes a plant description and an assessment of its level of compliance with EUR. The first three parts deal with EPR (1500 MW PWR developed by NPI, Framatome and Siemens), EPP (1000 MW PWR with passive safety features developed by Westinghouse and Ansaldo) and BWR 90 (1300 MW BWR developed by ABB Atom). Two other subsets are: one for ABWR (1300 MW BWR developed by GE), the other one for SWR 1000 (1000 MW BWR with passive safety features developed by Siemens). This large and diverse set of designs actually gives the EUR document a very strong base. Revision B of Volume 4 incorporates responses to the comments collected on revision A. Considering all that

  4. Two-stage Framework for a Topology-Based Projection and Visualization of Classified Document Collections

    Energy Technology Data Exchange (ETDEWEB)

    Oesterling, Patrick; Scheuermann, Gerik; Teresniak, Sven; Heyer, Gerhard; Koch, Steffen; Ertl, Thomas; Weber, Gunther H.

    2010-07-19

    During the last decades, electronic textual information has become the world's largest and most important information source available. People have added a variety of daily newspapers, books, scientific and governmental publications, blogs and private messages to this wellspring of endless information and knowledge. Since neither the existing nor the new information can be read in its entirety, computers are used to extract and visualize meaningful or interesting topics and documents from this huge information clutter. In this paper, we extend, improve and combine existing individual approaches into an overall framework that supports topological analysis of high dimensional document point clouds given by the well-known tf-idf document-term weighting method. We show that traditional distance-based approaches fail in very high dimensional spaces, and we describe an improved two-stage method for topology-based projections from the original high dimensional information space to both two dimensional (2-D) and three dimensional (3-D) visualizations. To show the accuracy and usability of this framework, we compare it to methods introduced recently and apply it to complex document and patent collections.

  5. Guidance document for preparing water sampling and analysis plans for UMTRA Project sites. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    A water sampling and analysis plan (WSAP) is prepared for each Uranium Mill Tailings Remedial Action (UMTRA) Project site to provide the rationale for routine ground water sampling at disposal sites and former processing sites. The WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the routine ground water monitoring stations at each site. This guidance document has been prepared by the Technical Assistance Contractor (TAC) for the US Department of Energy (DOE). Its purpose is to provide a consistent technical approach for sampling and monitoring activities performed under the WSAP and to provide a consistent format for the WSAP documents. It is designed for use by the TAC in preparing WSAPs and by the DOE, US Nuclear Regulatory Commission, state and tribal agencies, other regulatory agencies, and the public in evaluating the content of WSAPS

  6. Requirements Verification Report AN Farm to 200E Waste Transfer System for Project W-314, Tank Farm Restoration and Safe Operations

    International Nuclear Information System (INIS)

    MCGREW, D.L.

    1999-01-01

    This Requirements Verification Report (RVR) for Project W-314 ''AN Farm to 200E Waste Transfer System'' package provides documented verification of design compliance to all the applicable Project Development Specification (PDS) requirements. Additional PDS requirements verification will be performed during the project's procurement, construction, and testing phases, and the RVR will be updated to reflect this information as appropriate

  7. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 5

    International Nuclear Information System (INIS)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 5) outlines the standards and requirements for the Fire Protection and Packaging and Transportation sections

  8. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 4

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 4) presents the standards and requirements for the following sections: Radiation Protection and Operations.

  9. High level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 6

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 6) outlines the standards and requirements for the sections on: Environmental Restoration and Waste Management, Research and Development and Experimental Activities, and Nuclear Safety.

  10. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Document (S/RID) is contained in multiple volumes. This document (Volume 2) presents the standards and requirements for the following sections: Quality Assurance, Training and Qualification, Emergency Planning and Preparedness, and Construction.

  11. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 2

    International Nuclear Information System (INIS)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Document (S/RID) is contained in multiple volumes. This document (Volume 2) presents the standards and requirements for the following sections: Quality Assurance, Training and Qualification, Emergency Planning and Preparedness, and Construction

  12. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID)

    International Nuclear Information System (INIS)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 3) presents the standards and requirements for the following sections: Safeguards and Security, Engineering Design, and Maintenance

  13. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 3) presents the standards and requirements for the following sections: Safeguards and Security, Engineering Design, and Maintenance.

  14. 50 CFR 23.25 - What additional information is required on a non-Party CITES document?

    Science.gov (United States)

    2010-10-01

    ... a non-Party CITES document? 23.25 Section 23.25 Wildlife and Fisheries UNITED STATES FISH AND... IN ENDANGERED SPECIES OF WILD FAUNA AND FLORA (CITES) Prohibitions, Exemptions, and Requirements § 23.25 What additional information is required on a non-Party CITES document? (a) Purpose. Under Article...

  15. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 4

    International Nuclear Information System (INIS)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 4) presents the standards and requirements for the following sections: Radiation Protection and Operations

  16. 23 CFR 420.111 - What are the documentation requirements for use of FHWA planning and research funds?

    Science.gov (United States)

    2010-04-01

    ... and Research Funds § 420.111 What are the documentation requirements for use of FHWA planning and... 23 Highways 1 2010-04-01 2010-04-01 false What are the documentation requirements for use of FHWA planning and research funds? 420.111 Section 420.111 Highways FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF...

  17. 20 CFR 669.660 - What planning documents and information are required in the application for MSFW youth grants and...

    Science.gov (United States)

    2010-04-01

    ... 20 Employees' Benefits 3 2010-04-01 2010-04-01 false What planning documents and information are... PROGRAM UNDER TITLE I OF THE WORKFORCE INVESTMENT ACT The MSFW Youth Program § 669.660 What planning...? The required planning documents and other required information and the submission dates for filing are...

  18. High level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 6

    International Nuclear Information System (INIS)

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 6) outlines the standards and requirements for the sections on: Environmental Restoration and Waste Management, Research and Development and Experimental Activities, and Nuclear Safety

  19. Integrating model of the Project Independence Evaluation System. Volume VI. Data documentation. Part I

    Energy Technology Data Exchange (ETDEWEB)

    Allen, B J

    1979-02-01

    This documentation describes the PIES Integrating Model as it existed on January 1, 1978. This volume contains two chapters. In Chapter I, Overview, the following subjects are briefly described: supply data, EIA projection series and scenarios, demand data and assumptions, and supply assumptions - oil and gas availabilities. Chapter II contains supply and demand data tables and sources used by the PIES Integrating Model for the mid-range scenario target years 1985 and 1990. Tabulated information is presented for demand, price, and elasticity data; coal data; imports data; oil and gas data; refineries data; synthetics, shale, and solar/geothermal data; transportation data; and utilities data.

  20. Evaluation of aspect-oriented frameworks in Python for extending a project with provenance documentation features

    Directory of Open Access Journals (Sweden)

    2011-08-01

    Full Text Available In this paper we describe two sides of a real life use case of introducing an aspect-oriented framework into an industrial-grade project. This paper is divided into two parts: the selection process for an AOP framework in the Python programming language, and its use for modularized non-invasive recording of provenance data in a distributed data management tool. Criteria for the choice of such a framework are discussed and the background of provenance documentation is laid out.

  1. 42 CFR 50.208 - Program or project requirements.

    Science.gov (United States)

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false Program or project requirements. 50.208 Section 50.208 Public Health PUBLIC HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES GRANTS POLICIES OF GENERAL APPLICABILITY Sterilization of Persons in Federally Assisted Family Planning Projects § 50.208...

  2. MORE: Management of requirements in NPP modernisation projects. Project report 2007

    International Nuclear Information System (INIS)

    Fredriksen, R.; Katta, V.; Raspotnig, C.; Valkonen, J.

    2008-03-01

    This report documents the work and related activities of the MORE project in the period January 1 - December 31 in 2007. The focus of this report is on improvements of the former project results, to identify and apply a couple of case studies from NPP projects, and activities in order to initiate and implement the industrial take-up and utilisation of the research results in real modernisation projects. The report also provides a brief description of the extended industrial network and disseminations of the results in Nordic and NKS related events such as seminars and workshops. (au)

  3. MORE: Management of requirements in NPP modernisation projects. Project report 2007

    Energy Technology Data Exchange (ETDEWEB)

    Fredriksen, R.; Katta, V.; Raspotnig, C. [Institutt for energiteknikk (IFE) (Norway); Valkonen, J. [Technical Research Centre of Finland (VTT) (Finland)

    2008-03-15

    This report documents the work and related activities of the MORE project in the period January 1 - December 31 in 2007. The focus of this report is on improvements of the former project results, to identify and apply a couple of case studies from NPP projects, and activities in order to initiate and implement the industrial take-up and utilisation of the research results in real modernisation projects. The report also provides a brief description of the extended industrial network and disseminations of the results in Nordic and NKS related events such as seminars and workshops. (au)

  4. Summary of flat-plate solar array project documentation: Abstracts of published documents, 1975-1986, revision 1

    Science.gov (United States)

    Phillips, M. J.

    1986-01-01

    Abstracts of final reports, or the latest quarterly or annual, of the Flat-Plate Solar Array (FSA) Project Contractor of Jet Propulsion Laboratory (JPL) in-house activities are presented. Also presented is a list of proceedings and publications, by author, of work connected with the project. The aim of the program has been to stimulate the development of technology that will enable the private sector to manufacture and widely use photovoltaic systems for the generation of electricity in residential, commercial, industrial, and Government applications at a cost per watt that is competitive with utility generated power. FSA Project activities have included the sponsoring of research and development efforts in silicon refinement processes, advanced silicon sheet growth techniques, higher efficiency solar cells, solar cell/module fabrication processes, encapsulation, module/array engineering and reliability, and economic analyses.

  5. Terrestrial laser scanning for heritage conservation: the Cologne Cathedral documentation project

    Science.gov (United States)

    Pritchard, D.; Sperner, J.; Hoepner, S.; Tenschert, R.

    2017-08-01

    Contemporary terrestrial laser scanners and photogrammetric imaging systems are an invaluable tool in providing objectively precise, as-built records of existing architectural, engineering and industrial sites. The comprehensive three-dimensional (3D) recording of culturally important sites such as heritage buildings, monuments, and sites can serve a variety of invaluable purposes; the data can assist in the conservation, management, and repair of a structure, as well as provide a visually engaging educational resource for both the public and scholars. The acquired data acts as a form of digital preservation, a timeless virtual representation of the as-built structure. The technical capability of these systems is particularly suited for the documentation of a richly articulated and detailed building such as the high Gothic Cologne Cathedral. The 3D documentation of the Cologne Cathedral UNESCO World Heritage Site is a multiphase project developed by Heriot-Watt University, Edinburgh in partnership with the Fresenius University of Applied Sciences, Cologne, and the Metropolitankapitel der Hohen Domkirche Köln Dombauhütte. The project has also received generous support from Zoller + Fröhlich (Z+F) and the City of Cologne.

  6. The computer integrated documentation project: A merge of hypermedia and AI techniques

    Science.gov (United States)

    Mathe, Nathalie; Boy, Guy

    1993-01-01

    To generate intelligent indexing that allows context-sensitive information retrieval, a system must be able to acquire knowledge directly through interaction with users. In this paper, we present the architecture for CID (Computer Integrated Documentation). CID is a system that enables integration of various technical documents in a hypertext framework and includes an intelligent browsing system that incorporates indexing in context. CID's knowledge-based indexing mechanism allows case based knowledge acquisition by experimentation. It utilizes on-line user information requirements and suggestions either to reinforce current indexing in case of success or to generate new knowledge in case of failure. This allows CID's intelligent interface system to provide helpful responses, based on previous experience (user feedback). We describe CID's current capabilities and provide an overview of our plans for extending the system.

  7. A fully updated version of the european utility requirement (EUR) document is available

    International Nuclear Information System (INIS)

    Berbey, P.

    2001-01-01

    The major European electricity producers have worked on a common requirement document for future LWR plants since 1992 to get specifications acceptable together by the owners, the public and the authorities. Thus the designers can develop standard LWR designs that could be acceptable everywhere in Europe and the utilities can open their consultations to vendors on common bases. Public and authority's acceptance should be improved as well. Significant savings are expected in development and construction costs. Since the release of the last versions of the EUR texts in 1996, a lot of work has been carried out: reviews by the regulators and other external organisations, comparisons, assessment of compliance of designs vs. EUR and clarification works on the controversial topics that deserved changes or clarification. At the beginning of 1999 enough material was available to start a complete revision of the EUR document. In-depth works have been carried out during the last couple of year to develop this revision. The European utilities and the vendors have now an updated and well-tuned tool that allow them to develop, to assess and eventually to order modern LWR designs well fitted to their actual needs. (author)

  8. H2FIRST Hydrogen Contaminant Detector Task: Requirements Document and Market Survey

    Energy Technology Data Exchange (ETDEWEB)

    Terlip, Danny [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Ainscough, Chris [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Buttner, William [National Renewable Energy Laboratory (NREL), Golden, CO (United States); McWhorter, Scott [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL)

    2015-04-20

    The rollout of hydrogen fueling stations, and the fuel cell electric vehicles (FCEV) they support, requires the assurance of high quality hydrogen at the dispensing point. Automotive fuel cells are sensitive to a number of chemicals that can be introduced into the dispensed fuel at multiple points. Quality assurance and quality control methods are employed by the industry to ensure product quality, but they are not completely comprehensive and can fail at various points in the hydrogen pathway from production to dispensing. This reality leaves open the possibility of a station unknowingly dispensing harmful contaminants to a FCEV which, depending on the contaminant, may not be discovered until the FCEV is irreparably damaged. This situation is unacceptable. A hydrogen contaminant detector (HCD), defined as a combination of a gas analyzer and the components necessary for fuel stream integration, installed at hydrogen stations is one method for preventing poor quality gas from reaching an FCEV. This document identifies the characteristics required of such a device by industry and compares those requirements with the current state of commercially available gas analysis technology.

  9. 10-MWe pilot-plant-receiver panel test requirements document solar thermal test facility

    Energy Technology Data Exchange (ETDEWEB)

    1978-08-25

    Testing plans for a full-scale test receiver panel and supporting hardware which essentially duplicate both physically and functionally, the design planned for the Barstow Solar Pilot Plant are presented. Testing is to include operation during normal start and shutdown, intermittent cloud conditions, and emergencies to determine the panel's transient and steady state operating characteristics and performance under conditions equal to or exceeding those expected in the pilot plant. The effects of variations of input and output conditions on receiver operation are also to be investigated. Test hardware are described, including the pilot plant receiver, the test receiver assembly, receiver panel, flow control, electrical control and instrumentation, and structural assembly. Requirements for the Solar Thermal Test Facility for the tests are given. The safety of the system is briefly discussed, and procedures are described for assembly, installation, checkout, normal and abnormal operations, maintenance, removal and disposition. Also briefly discussed are quality assurance, contract responsibilities, and test documentation. (LEW)

  10. How to scope configuration projects and manage the knowledge they require

    DEFF Research Database (Denmark)

    Shafiee, Sara; Kristjansdottir, Katrin; Hvam, Lars

    2018-01-01

    Purpose This paper aims to explore the use of the knowledge management (KM) perspective for configuration projects. Configuration projects implement configurators as information technology systems that help companies manage the specification process of customised products. An effective method...... of retrieving and formalising knowledge for configurators is essential, because it can reduce the risk of unsuccessful implementation and the time and effort required for development. Unfortunately, no standard KM frameworks are available specifically for configuration projects. This study identifies...... the knowledge necessary for different phases of a configuration project (which knowledge, for what purpose and from what sources), examines how it is transformed during a configuration project (what KM activities and tools are used) and establishes how the knowledge can be documented for future maintenance...

  11. IT Requirements Integration in High-Rise Construction Design Projects

    Science.gov (United States)

    Levina, Anastasia; Ilin, Igor; Esedulaev, Rustam

    2018-03-01

    The paper discusses the growing role of IT support for the operation of modern high-rise buildings, due to the complexity of managing engineering systems of buildings and the requirements of consumers for the IT infrastructure. The existing regulatory framework for the development of design documentation for construction, including high-rise buildings, is analyzed, and the lack of coherence in the development of this documentation with the requirements for the creation of an automated management system and the corresponding IT infrastructure is stated. The lack of integration between these areas is the cause of delays and inefficiencies both at the design stage and at the stage of putting the building into operation. The paper proposes an approach to coordinate the requirements of the IT infrastructure of high-rise buildings and design documentation for construction. The solution to this problem is possible within the framework of the enterprise architecture concept by coordinating the requirements of the IT and technological layers at the design stage of the construction.

  12. Functions and Requirements for Debris Removal System-Project A.2

    International Nuclear Information System (INIS)

    PRECECHTEL, D.R.

    1999-01-01

    This revision of the Functions and Requirements Document updates the approved Functions and Requirements for Debris Removal Subproject WHC-SD-SNF-FRD-009, Rev. 0. It has been revised in its entirety to reflect the current scope of work for Debris Removal as canisters and lids under the K Basin Projects work breakdown structure (WBS). In this revision the canisters and lids will be consider debris and a new set of Functions and Requirements have been developed to remove the canisters and lids from the basin

  13. Technical support document for proposed 1994 revision of the MEC thermal envelope requirements

    Energy Technology Data Exchange (ETDEWEB)

    Conner, C.C.; Lucas, R.G.

    1994-03-01

    This report documents the development of the proposed revision of the Council of American Building Officials` (CABO) 1994 supplement to the 1993 Model Energy Code (MEC) building thermal envelope requirements for maximum component U{sub 0}-value. The 1994 amendments to the 1993 MEC were established in last year`s code change cycle and did not change the envelope requirements. The research underlying the proposed MEC revision was conducted by Pacific Northwest Laboratory (PNL) for the US Department of Energy (DOE) Building Energy Standards program. The goal of this research was to develop revised guidelines based on an objective methodology that determines the most cost-effective (least total cost) combination of energy conservation measures (ECMs) (insulation levels and window types) for residential buildings. This least-cost set of ECMs was used as a basis for proposing revised MEC maximum U{sub 0}-values (thermal transmittances). ECMs include window types (for example, double-pane vinyl) and insulation levels (for example, R-19) for ceilings, walls, and floors.

  14. Financial effect of instituting Deficit Reduction Act documentation requirements in family planning clinics in Oregon.

    Science.gov (United States)

    Rodriguez, Maria Isabel; Angus, Lisa; Elman, Emily; Darney, Philip D; Caughey, Aaron B

    2011-06-01

    The study was conducted to estimate the long-term costs for implementing citizenship documentation requirements in a Medicaid expansion program for family planning services in Oregon. A decision-analytic model was developed using two perspectives: the state and society. Our primary outcome was future reproductive health care costs due to pregnancy in the next 5 years. A Markov structure was utilized to capture multiple future pregnancies. Model inputs were retrieved from the existing literature and local hospital and Medicaid data related to reimbursements. One-way and multi-way sensitivity analyses were conducted. A Monte Carlo simulation was performed to simultaneously incorporate uncertainty from all of the model inputs. Screening for citizenship results in a loss of $3119 over 5 years ($39,382 vs. $42,501) for the state and $4209 for society ($63,391 compared to $59,182) for adult women. Among adolescents, requiring proof of identity and citizenship results in a loss of $3123 for the state ($39,378 versus $42,501) and $4214 for society ($63,391 instead of $59,177). Screening for citizenship status in publicly funded family planning clinics leads to financial losses for the state and society. Copyright © 2011 Elsevier Inc. All rights reserved.

  15. International environmental issues and requirements for new power projects

    Energy Technology Data Exchange (ETDEWEB)

    Newman, J.R. [Golder Associates Inc., Gainesville, FL (United States); Maltby, J.H. [Golder Associates Inc., Washington, DC (United States)

    1997-12-31

    The purpose of this presentation was to discuss the emerging role of financial entities in determining environmental requirements for international power projects. The paper outlines the following: emerging conditions; examples of announced privatization energy projects by country; types of government and international financial entity sources; problems for IPPs; similarity and differences between the World Bank and the USEPA; comparison of the international standards and regulations for power plants; recent trends/issues involving international power project approval; and recommendations for understanding/expediting the financial entities` environmental approval process and how to expedite this process.

  16. Joint Simulation System (JSIMS) Functional Requirements Document (FRD); A User's Perspective on the Future, Version 1.O

    National Research Council Canada - National Science Library

    1996-01-01

    The purpose of this document is to define JSIMS functional requirements in a level of detail that is meaningful to both the JSIMS developmental community and the expected future users of the system...

  17. MORE. Management of Requirements in NPP modernisation projects - Project report 2005

    International Nuclear Information System (INIS)

    Thunem, A.P.J.; Fredriksen, R.; Thunem, H.P.J.; Ventae, O.; Valkonen, J.; Holmberg, J.E.

    2006-04-01

    The overall objective of the project MORE is to improve the means for managing the large amounts of evolving requirements in Nordic NPP modernisation projects. In accordance to this objective, the activity will facilitate the industrial utilisation of the research results from the project TACO. On the basis of experiences in the Nordic countries, the overall aim of the TACO project has been to identify the best practices and most important criteria for ensuring effective communication in relation to requirements elicitation and analysis, understandability of requirements to all parties, and traceability of requirements. The project resulted in the development of a traceability model for handling requirements from their origins and through their final shapes. Particular emphasis for the MORE project in 2005 was put on utilising a prototype of a tool (TRACE) intended to support an adopted approach to dependable requirements engineering, suitable for modelling and handling large amounts of requirements related to all stages of the systems development process and not only those traditionally including requirements at high-level stages. (au)

  18. MORE. Management of Requirements in NPP modernisation projects - Project report 2005

    Energy Technology Data Exchange (ETDEWEB)

    Thunem, A.P.J.; Fredriksen, R.; Thunem, H.P.J. [IFE (Norway); Ventae, O.; Valkonen, J.; Holmberg, J.E. [VTT Technical Research Centre of Finland (Finland)

    2006-04-15

    The overall objective of the project MORE is to improve the means for managing the large amounts of evolving requirements in Nordic NPP modernisation projects. In accordance to this objective, the activity will facilitate the industrial utilisation of the research results from the project TACO. On the basis of experiences in the Nordic countries, the overall aim of the TACO project has been to identify the best practices and most important criteria for ensuring effective communication in relation to requirements elicitation and analysis, understandability of requirements to all parties, and traceability of requirements. The project resulted in the development of a traceability model for handling requirements from their origins and through their final shapes. Particular emphasis for the MORE project in 2005 was put on utilising a prototype of a tool (TRACE) intended to support an adopted approach to dependable requirements engineering, suitable for modelling and handling large amounts of requirements related to all stages of the systems development process and not only those traditionally including requirements at high-level stages. (au)

  19. Projection of US LWR spent fuel storage requirements

    International Nuclear Information System (INIS)

    Fletcher, J.F.; Cole, B.M.; Purcell, W.L.; Rau, R.G.

    1982-11-01

    The spent fuel storage requirements projection is based on data supplied for each operating or planned nuclear power power plant by the operting utilities. The data supplied by the utilities encompassed details of plant operating history, past records of fuel discharges, current inventories in reactor spent fuel storage pools, and projections of future discharge patterns. Data on storage capacity of storage pools and on characterization of the discharged fuel are also included. The data supplied by the utilities, plus additional data from other appropriate sources, are maintained on a computerized data base by Pacific Northwest Laboratory. The spent fuel requirements projection was based on utility data updated and verified as of December 31, 1981

  20. 45 CFR 2553.72 - What are project funding requirements?

    Science.gov (United States)

    2010-10-01

    ... local funding sources during the first three years of operations; or (2) An economic downturn, the... sources of local funding support; or (3) The unexpected discontinuation of local support from one or more... 45 Public Welfare 4 2010-10-01 2010-10-01 false What are project funding requirements? 2553.72...

  1. 50 CFR 23.51 - What are the requirements for issuing a partially completed CITES document?

    Science.gov (United States)

    2010-10-01

    ..., BARTER, EXPORTATION, AND IMPORTATION OF WILDLIFE AND PLANTS (CONTINUED) CONVENTION ON INTERNATIONAL TRADE... CITES documents only when: (i) The permitted trade will have a negligible impact or no impact on the... completed documents benefits both the permit holder and the issuing Management Authority. (2) The proposed...

  2. 75 FR 80517 - HUD Multifamily Rental Project Closing Documents-Revisions and Updates Notice of Information...

    Science.gov (United States)

    2010-12-22

    ... familiar with the updated closing documents, the existing closing documents, which these updated closing... assures the industry and the public that sufficient staff will be available and thoroughly familiar with... documents that are updated for current commercial legal standards, balanced with the public policy role that...

  3. TECHNICAL BASIS FOR VENTILATION REQUIREMENTS IN TANK FARMS OPERATING SPECIFICATIONS DOCUMENTS

    Energy Technology Data Exchange (ETDEWEB)

    BERGLIN, E J

    2003-06-23

    This report provides the technical basis for high efficiency particulate air filter (HEPA) for Hanford tank farm ventilation systems (sometimes known as heating, ventilation and air conditioning [HVAC]) to support limits defined in Process Engineering Operating Specification Documents (OSDs). This technical basis included a review of older technical basis and provides clarifications, as necessary, to technical basis limit revisions or justification. This document provides an updated technical basis for tank farm ventilation systems related to Operation Specification Documents (OSDs) for double-shell tanks (DSTs), single-shell tanks (SSTs), double-contained receiver tanks (DCRTs), catch tanks, and various other miscellaneous facilities.

  4. Database requirements for the Advanced Test Accelerator project

    International Nuclear Information System (INIS)

    Chambers, F.W.

    1984-01-01

    The database requirements for the Advanced Test Accelerator (ATA) project are outlined. ATA is a state-of-the-art electron accelerator capable of producing energetic (50 million electron volt), high current (10,000 ampere), short pulse (70 billionths of a second) beams of electrons for a wide variety of applications. Databasing is required for two applications. First, the description of the configuration of facility itself requires an extended database. Second, experimental data gathered from the facility must be organized and managed to insure its full utilization. The two applications are intimately related since the acquisition and analysis of experimental data requires knowledge of the system configuration. This report reviews the needs of the ATA program and current implementation, intentions, and desires. These database applications have several unique aspects which are of interest and will be highlighted. The features desired in an ultimate database system are outlined. 3 references, 5 figures

  5. Low-complexity camera digital signal imaging for video document projection system

    Science.gov (United States)

    Hsia, Shih-Chang; Tsai, Po-Shien

    2011-04-01

    We present high-performance and low-complexity algorithms for real-time camera imaging applications. The main functions of the proposed camera digital signal processing (DSP) involve color interpolation, white balance, adaptive binary processing, auto gain control, and edge and color enhancement for video projection systems. A series of simulations demonstrate that the proposed method can achieve good image quality while keeping computation cost and memory requirements low. On the basis of the proposed algorithms, the cost-effective hardware core is developed using Verilog HDL. The prototype chip has been verified with one low-cost programmable device. The real-time camera system can achieve 1270 × 792 resolution with the combination of extra components and can demonstrate each DSP function.

  6. Hanford spent nuclear fuel project recommended path forward, volume III: Alternatives and path forward evaluation supporting documentation

    International Nuclear Information System (INIS)

    Fulton, J.C.

    1994-10-01

    Volume I of the Hanford Spent Nuclear Fuel Project - Recommended Path Forward constitutes an aggressive series of projects to construct and operate systems and facilities to safely retrieve, package, transport, process, and store K Basins fuel and sludge. Volume II provided a comparative evaluation of four Alternatives for the Path Forward and an evaluation for the Recommended Path Forward. Although Volume II contained extensive appendices, six supporting documents have been compiled in Volume III to provide additional background for Volume II

  7. TA-55 facility control system upgrade project - human-system interface functional requirements

    International Nuclear Information System (INIS)

    Atkins, W.H.; Pope, N.G.; Turner, W.J.; Brown, R.E.

    1995-11-01

    The functional requirements for that part of the Technical Area (TA)-55 Operations Center Upgrade Project that involves the human-system interface (HSI) are described in this document. The upgrade project seeks to replace completely the center's existing computerized data acquisition and display system, which consists of the field multiplexer units, Data General computer systems, and associated peripherals and software. The upgrade project has two parts-the Facility Data Acquisition Interface System (FDAIS) and the HSI. The HSI comprises software and hardware to provide a high-level graphical operator interface to the data acquisition system, as well as data archiving, alarm annunciation, and logging. The new system will be built with modern, commercially available components; it will improve reliability and maintainability, and it can be expanded for future needs

  8. [Efficiency of computer-based documentation in long-term care--preliminary project].

    Science.gov (United States)

    Lüngen, Markus; Gerber, Andreas; Rupprecht, Christoph; Lauterbach, Karl W

    2008-06-01

    In Germany the documentation of processes in long-term care is mainly paper-based. Planning, realization and evaluation are not supported in an optimal way. In a preliminary study we evaluated the consequences of the introduction of a computer-based documentation system using handheld devices. We interviewed 16 persons before and after introducing the computer-based documentation and assessed costs for the documentation process and administration. The results show that reducing costs is likely. The job satisfaction of the personnel increased, more time could be spent for caring for the residents. We suggest further research to reach conclusive results.

  9. Iraqi Perspectives Project. Saddam and Terrorism: Emerging Insights from Captured Iraqi Documents. Volume 1 (Redacted)

    National Research Council Canada - National Science Library

    Woods, Kevin M; Lacey, James

    2007-01-01

    Captured Iraqi documents have uncovered evidence that links the regime of Saddam Hussein to regional and global terrorism, including a variety of revolutionary, liberation, nationalist, and Islamic...

  10. Pilot production system cost/benefit analysis: Digital document storage project

    Science.gov (United States)

    1989-01-01

    The Digital Document Storage (DDS)/Pilot Production System (PPS) will provide cost effective electronic document storage, retrieval, hard copy reproduction, and remote access for users of NASA Technical Reports. The DDS/PPS will result in major benefits, such as improved document reproduction quality within a shorter time frame than is currently possible. In addition, the DDS/PPS will provide an important strategic value through the construction of a digital document archive. It is highly recommended that NASA proceed with the DDS Prototype System and a rapid prototyping development methodology in order to validate recent working assumptions upon which the success of the DDS/PPS is dependent.

  11. Structural requirements of research tissue banks derived from standardized project surveillance.

    Science.gov (United States)

    Herpel, E; Koleganova, N; Schreiber, B; Walter, B; Kalle, C V; Schirmacher, P

    2012-07-01

    Tissue banks constitute decisive and rate-limiting resource and technology platforms for basic and translational biomedical research, notably in the area of cancer. Thus, it is essential to plan and structure tissue banking and allocate resources according to research needs, but essential requirements are still incompletely defined. The tissue bank of the National Center of Tumor Diseases Heidelberg (NCT) was founded with the intention to provide tissues of optimal quality and to prioritize the realization of research projects. We analysed its structure and prospective project management registration as well as tracking records for all projects of the NCT tissue bank as of its start in 2005 in order to obtain information that may be relevant for tissue bank planning. All project proposals submitted to the NCT tissue bank (n = 681) were included in the study. For a detailed evaluation of provided services, only projects that were completed until July 2011 (n = 605) were analysed. For these 605 projects, NCT tissue bank provided 769 specific services. In all projects/services, we recorded project leader, type and amount of material provided, type of research (basic/translational), work load of project and project completion. Furthermore, all completed projects were tracked after 90 days according to a standard protocol to determine principal investigators' (PI) satisfaction and quality of the provided material. Until July 2011, 605 projects had been successfully completed as documented by material transfer agreement. Of the projects, 72.7 % addressed basic research, 22.3 % were translational research projects and 3 % concerned epidemiological research; 91 % (n = 546) concerned a single PI and the NTC tissue bank. For these projects, 769 specific services were provided. Of these services, 288 concerned providing formalin-fixed and paraffin-embedded (FFPE) tissue (extracts, full size sections), 126 providing fresh frozen materials (including fresh frozen

  12. An Engineering Method of Civil Jet Requirements Validation Based on Requirements Project Principle

    Science.gov (United States)

    Wang, Yue; Gao, Dan; Mao, Xuming

    2018-03-01

    A method of requirements validation is developed and defined to meet the needs of civil jet requirements validation in product development. Based on requirements project principle, this method will not affect the conventional design elements, and can effectively connect the requirements with design. It realizes the modern civil jet development concept, which is “requirement is the origin, design is the basis”. So far, the method has been successfully applied in civil jet aircraft development in China. Taking takeoff field length as an example, the validation process and the validation method of the requirements are detailed introduced in the study, with the hope of providing the experiences to other civil jet product design.

  13. Detailed requirements document for the Interactive Financial Management System (IFMS), volume 1

    Science.gov (United States)

    Dodson, D. B.

    1975-01-01

    The detailed requirements for phase 1 (online fund control, subauthorization accounting, and accounts receivable functional capabilities) of the Interactive Financial Management System (IFMS) are described. This includes information on the following: systems requirements, performance requirements, test requirements, and production implementation. Most of the work is centered on systems requirements, and includes discussions on the following processes: resources authority, allotment, primary work authorization, reimbursable order acceptance, purchase request, obligation, cost accrual, cost distribution, disbursement, subauthorization performance, travel, accounts receivable, payroll, property, edit table maintenance, end-of-year, backup input. Other subjects covered include: external systems interfaces, general inquiries, general report requirements, communication requirements, and miscellaneous. Subjects covered under performance requirements include: response time, processing volumes, system reliability, and accuracy. Under test requirements come test data sources, general test approach, and acceptance criteria. Under production implementation come data base establishment, operational stages, and operational requirements.

  14. 10 CFR 2.304 - Formal requirements for documents; signatures; acceptance for filing.

    Science.gov (United States)

    2010-01-01

    ... through the E-Filing system written testimony or hearing exhibits in advance of a hearing, the written... for filing. 2.304 Section 2.304 Energy NUCLEAR REGULATORY COMMISSION RULES OF PRACTICE FOR DOMESTIC...; signatures; acceptance for filing. (a) Docket numbers and titles. Each document filed in an adjudication to...

  15. 7 CFR 1484.53 - What are the requirements for documenting and reporting contributions?

    Science.gov (United States)

    2010-01-01

    ... contribution must be documented by the Cooperator, showing the method of computing non-cash contributions, salaries, and travel expenses. (b) Each Cooperator must keep records of the methods used to compute the value of non-cash contributions, and (1) Copies of invoices or receipts for expenses paid by the U.S...

  16. 41 CFR 102-118.565 - What documentation is required when filing an administrative claim?

    Science.gov (United States)

    2010-07-01

    ... 41 Public Contracts and Property Management 3 2010-07-01 2010-07-01 false What documentation is... Management Federal Property Management Regulations System (Continued) FEDERAL MANAGEMENT REGULATION..., reports and information available to GSA and/or to the agency involved and the written and documentary...

  17. Development and maintenance of product configuration systems: Requirements for a documentation tool

    DEFF Research Database (Denmark)

    Hvam, Lars; Christensen, Simon Pape; Jensen, Klaes Ladeby

    2005-01-01

    by letting a documentation tool handle trivial time consuming tasks (notification on change, consistency check etc.), as a computer often handles these tasks in a better way. Thus, a serious bottleneck in the maintenance of configuration systems can be eliminated by applying Information System (IS...

  18. Alternative Compliance: Guidelines for Preparing and Submitting a Waiver Request Application and Other Documentation Requirements (Book)

    Energy Technology Data Exchange (ETDEWEB)

    2010-11-01

    This document is designed to assist covered fleets interested in taking advantage of more flexible compliance options and to facilitate the transition from Standard Compliance to Alternative Compliance. It is designed to help fleets better understand the Alternative Compliance option and successfully complete the waiver application process.

  19. 75 FR 14361 - Notification, Documentation, and Recordkeeping Requirements for Inspected Establishments

    Science.gov (United States)

    2010-03-25

    ... error. Table 3--Number of Establishments, and Total and Average Cost in Size (x $1,000) Recall Number of... Activities (2010) (2011) (2012) (2013) (2014) Total Very Small 2,856 Recall-Procedures 2,030 278 286 295 304... 461 Total All 6,300 Recall-Procedures 4,454 610 628 647 666 7,005 development & updating. Documenting...

  20. Alternative Compliance: Guidelines for Preparing and Submitting a Waiver Request Application and Other Documentation Requirements

    Energy Technology Data Exchange (ETDEWEB)

    2013-03-01

    This document is designed to assist covered fleets interested in taking advantage of more flexible compliance options and to facilitate the transition from Standard Compliance to Alternative Compliance. It is designed to help fleets better understand the Alternative Compliance option and successfully complete the waiver application process.

  1. Alternative Compliance: Guidelines for Preparing and Submitting a Waiver Request Application and Other Documentation Requirements (Brochure)

    Energy Technology Data Exchange (ETDEWEB)

    2014-06-01

    This document is designed to assist covered fleets interested in taking advantage of more flexible compliance options and to facilitate the transition from Standard Compliance to Alternative Compliance. It is designed to help fleets better understand the Alternative Compliance option and successfully complete the waiver application process.

  2. Alternative Compliance: Guidelines for Preparing and Submitting a Waiver Request Application and Other Documentation Requirements

    Energy Technology Data Exchange (ETDEWEB)

    Sears, Ted [National Renewable Energy Lab. (NREL), Golden, CO (United States)

    2014-06-01

    This document is designed to assist covered fleets interested in taking advantage of more flexible compliance options and to facilitate the transition from Standard Compliance to Alternative Compliance. It is designed to help fleets better understand the Alternative Compliance option and successfully complete the waiver application process.

  3. Revk - a Tool for the Fulfilment of Requirements from National Rules for Tracking and Documentation of Radioactive Residual Material and Radioactive Waste

    International Nuclear Information System (INIS)

    Hartmann, B.; Haeger, M.; Gruendler, D.

    2006-01-01

    According to the German Radiation Protection Ordinance treatment, storage, whereabouts of radioactive material etc. have to be documented. Due to legal requirements an electronic documentation system for radioactive waste has to be installed. Within the framework of the currently largest decommissioning project of nuclear facilities by Energiewerke Nord GmbH, a material flow-waste tracking and control system (ReVK) has been developed, tailored to the special needs of the decommissioning of nuclear facilities. With this system it is possible to record radioactive materials which can be released after treatment or decay storage for restricted and unrestricted utilization. Radioactive waste meant for final storage can be registered and documented as well. Based on ORACLE, ReVK is a client/server data base system with the following modules: 1. data registration, 2. transport management, 3. waste tracking, 4. storage management, 5. container management, 6. reporting, 7. activity calculation, 8. examination of technical acceptance criteria for storages and final repositories. Furthermore ReVK provides a multitude of add-ons to meet special user needs, which enlarge the spectrum of application enormously. ReVK is validated and qualified, accepted by experts and authorities and fulfils the requirements for a radioactive waste documentation system. (authors)

  4. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 7

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    This Requirements Identification Document (RID) describes an Occupational Health and Safety Program as defined through the Relevant DOE Orders, regulations, industry codes/standards, industry guidance documents and, as appropriate, good industry practice. The definition of an Occupational Health and Safety Program as specified by this document is intended to address Defense Nuclear Facilities Safety Board Recommendations 90-2 and 91-1, which call for the strengthening of DOE complex activities through the identification and application of relevant standards which supplement or exceed requirements mandated by DOE Orders. This RID applies to the activities, personnel, structures, systems, components, and programs involved in maintaining the facility and executing the mission of the High-Level Waste Storage Tank Farms.

  5. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 7

    International Nuclear Information System (INIS)

    1994-04-01

    This Requirements Identification Document (RID) describes an Occupational Health and Safety Program as defined through the Relevant DOE Orders, regulations, industry codes/standards, industry guidance documents and, as appropriate, good industry practice. The definition of an Occupational Health and Safety Program as specified by this document is intended to address Defense Nuclear Facilities Safety Board Recommendations 90-2 and 91-1, which call for the strengthening of DOE complex activities through the identification and application of relevant standards which supplement or exceed requirements mandated by DOE Orders. This RID applies to the activities, personnel, structures, systems, components, and programs involved in maintaining the facility and executing the mission of the High-Level Waste Storage Tank Farms

  6. Regulatory document R-104, Regulatory objectives, requirements and guidelines for the disposal of radioactive wastes - long-term aspects

    International Nuclear Information System (INIS)

    1987-01-01

    The purpose and scope of this document is to present the regulatory basis for judging the long-term acceptability of radioactive waste disposal options. The basic objectives of radioactive waste disposal are given as are the regulatory requirements to be satisfied. (NEA)

  7. Environmental management requirements/defensible costs project. Final report

    International Nuclear Information System (INIS)

    1996-02-01

    Lockheed Idaho Technologies Company (LITCO) used a systems engineering approach to develop the first formal requirements baseline for Idaho National Engineering Laboratory (INEL) Environmental Management (EM) Programs. The recently signed Settlement Agreement with the State of Idaho (Batt Agreement), along with dramatically reduced EM funding targets from Department of Energy (DOE) headquarters, drove the immediacy of this effort. Programs have linked top-level requirements to work scope to cost estimates. All EM work, grouped by decision units, was scrubbed by INEL EM programs and by an independent open-quotes Murder Board.close quotes Direct participation of upper level management from LITCO and the DOE-Idaho Operations Office ensured best information and decisions. The result is a scrubbed down, defensible budget tied to top-level requirements for use in the upcoming DOE-Headquarters' budget workout, the Internal Review Board, the FY98 Activity Data Sheets submittal, and preparation of the FY97 control accounts and out-year plans. In addition to the remarkable accomplishments during the past eight weeks, major issues were identified and documented and follow-on tasks are underway which will lead to further improvements in INEL EM program management

  8. Environmental management requirements/defensible costs project. Final report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-02-01

    Lockheed Idaho Technologies Company (LITCO) used a systems engineering approach to develop the first formal requirements baseline for Idaho National Engineering Laboratory (INEL) Environmental Management (EM) Programs. The recently signed Settlement Agreement with the State of Idaho (Batt Agreement), along with dramatically reduced EM funding targets from Department of Energy (DOE) headquarters, drove the immediacy of this effort. Programs have linked top-level requirements to work scope to cost estimates. All EM work, grouped by decision units, was scrubbed by INEL EM programs and by an independent {open_quotes}Murder Board.{close_quotes} Direct participation of upper level management from LITCO and the DOE-Idaho Operations Office ensured best information and decisions. The result is a scrubbed down, defensible budget tied to top-level requirements for use in the upcoming DOE-Headquarters` budget workout, the Internal Review Board, the FY98 Activity Data Sheets submittal, and preparation of the FY97 control accounts and out-year plans. In addition to the remarkable accomplishments during the past eight weeks, major issues were identified and documented and follow-on tasks are underway which will lead to further improvements in INEL EM program management.

  9. Design criteria document, electrical system, K-Basin essential systems recovery, Project W-405

    International Nuclear Information System (INIS)

    Hoyle, J.R.

    1994-01-01

    This Design Criteria Document provides the criteria for design and construction of electrical system modifications for 100K Area that are essential to protect the safe operation and storage of spent nuclear fuel in the K-Basin facilities

  10. Magnetohydrodynamics (MHD) Engineering Test Facility (ETF) 200 MWe power plant. Design Requirements Document (DRD)

    Science.gov (United States)

    Rigo, H. S.; Bercaw, R. W.; Burkhart, J. A.; Mroz, T. S.; Bents, D. J.; Hatch, A. M.

    1981-01-01

    A description and the design requirements for the 200 MWe (nominal) net output MHD Engineering Test Facility (ETF) Conceptual Design, are presented. Performance requirements for the plant are identified and process conditions are indicated at interface stations between the major systems comprising the plant. Also included are the description, functions, interfaces and requirements for each of these major systems. The lastest information (1980-1981) from the MHD technology program are integrated with elements of a conventional steam electric power generating plant.

  11. Workplace Literacy Pilot Projects: A Discussion Paper = Les Projects-pilotes en alphabetisation en milieu de travail: document de discussion.

    Science.gov (United States)

    de Wolff, Alice

    From 1995-1998, 12 of the 79 organizations funded by Canada's National Literacy Secretariat (NLS) conducted approximately 40 workplace literacy pilot projects across Canada. Those projects were reviewed to determine their effectiveness in increasing the number and quality of Canadian workplace literacy programs. Information for the review was…

  12. Management of technical documents: a projection at the University of Zulia

    Directory of Open Access Journals (Sweden)

    Ana Judith Paredes Chacin

    2015-11-01

    Full Text Available Objective. This paper analyze comprehensively and systematically the principles of organization and technical procedure, which support document management based on the use of information technologies. Method. We developed a study based on the documentary descriptive method in the context of the Dirección de Infraestructura (Dinfra from the Universidad del Zulia. Results. We find evidence of efficiency in the processes that support the management of technical documents: Plans, metrics and memories generated by the Dinfra. Conclusion. The conceptual basis of organizational and technical archives contribute to the systematization, shelter save and documental preservation, and ensure the timely retrieval of technical information for the management of the University of Zulia.

  13. Station set requirements document. Volume 82: Fire support. Book 2: Preliminary functional fire plan

    Science.gov (United States)

    Gray, N. C.

    1974-01-01

    The fire prevention/protection requirements for all shuttle facility and ground support equipment are presented for the hazardous operations. These include: preparing the orbiter for launch, launch operations, landing operations, safing operations, and associated off-line activities.

  14. Development of functional requirements for electronic health communication: preliminary results from the ELIN project.

    Science.gov (United States)

    Christensen, Tom; Grimsmo, Anders

    2005-01-01

    User participation is important for developing a functional requirements specification for electronic communication. General practitioners and practising specialists, however, often work in small practices without the resources to develop and present their requirements. It was necessary to find a method that could engage practising doctors in order to promote their needs related to electronic communication. Qualitative research methods were used, starting a process to develop and study documents and collect data from meetings in project groups. Triangulation was used, in that the participants were organised into a panel of experts, a user group, a supplier group and an editorial committee. The panel of experts created a list of functional requirements for electronic communication in health care, consisting of 197 requirements, in addition to 67 requirements selected from an existing Norwegian standard for electronic patient records (EPRs). Elimination of paper copies sent in parallel with electronic messages, optimal workflow, a common electronic 'envelope' with directory services for units and end-users, and defined requirements for content with the possibility of decision support were the most important requirements. The results indicate that we have found a method of developing functional requirements which provides valid results both for practising doctors and for suppliers of EPR systems.

  15. Projecting future solid waste management requirements on the Hanford Site

    International Nuclear Information System (INIS)

    Shaver, S.R.; Stiles, D.L.; Holter, G.M.; Anderson, B.C.

    1990-09-01

    The problem of treating and disposing of hazardous transuranic (TRU), low-level radioactive, and mixed waste has become a major concern of the public and the government. At the US Department of Energy's Hanford Site in Washington state, the problem is compounded by the need to characterize, retrieve, and treat the solid waste that was generated and stored for retrieval during the past 20 years. This paper discusses the development and application of a Solid Waste Projection Model that uses forecast volumes and characteristics of existing and future solid waste to address the treatment, storage, and disposal requirements at Hanford. The model uses a data-driven, object-oriented approach to assess the storage and treatment throughout requirements for each operation for each of the distinct waste classes and the accompanying cost of the storage and treatment operations. By defining the elements of each alternative for the total waste management system, the same database can be used for numerous analyses performed at different levels of detail. This approach also helps a variety of users with widely varying information requirements to use the model and helps achieve the high degree of flexibility needed to cope with changing regulations and evolving treatment and disposal technologies. 2 figs

  16. Projected requirements for radiation oncologists and trainees in Australia and New Zealand to 2007

    International Nuclear Information System (INIS)

    Morgan, G.; Wigg, D.; Childs, J.

    2000-01-01

    Workloads in radiation oncology facilities in Australia and New Zealand have been increasing steadily for many years and it is anticipated that this trend will continue. In the present paper the projected number of radiation oncologists required to meet this demand to the year 2007 are estimated, along with the number of trainees required. The estimates are based on data from regular surveys by the Royal Australian and New Zealand College of Radiologists (RANZCR) for the years 1988-97 (inclusive). From these surveys profiles of numbers, age and gender of specialists and trainees are documented together with increases from the training programme and losses from retirement. It is concluded that if the current trainee numbers are increased by 12 in Australia and two in New Zealand, there will be approximately 10 radiation oncologists per million of population by the year 2007. This number is considered appropriate vue the anticipated increase in demands and complexity of treatment. Because projections too far forward are unreliable, careful monitoring of progress is essential to obtain the appropriate balance between requirement and supply. Comparisons are made with other estimates of needs including the 1998 Australian Medical Workforce Advisory Committee (AMWAC) Report and the New Zealand Clinical Agency Workforce Project Report in 1997. Copyright (1999) Blackwell Science Pty Ltd

  17. Spent nuclear fuel project-criteria document Cold Vacuum Drying Facility phase 2 safety analysis report

    International Nuclear Information System (INIS)

    Garvin, L.J.

    1998-01-01

    The criteria document provides the criteria and guidance for developing the SNF CVDF Phase 2 SAR. This SAR will support the US Department of Energy, Richland Operations Office decision to authorize the procurement, installation, and installation acceptance testing of the CVDF systems

  18. The processed neutron activation cross-section data files of the FENDL project. Summary documentation

    International Nuclear Information System (INIS)

    Ganesan, S.; Pashchenko, A.B.; Lemmle, H.D.; Mann, F.M.

    1994-01-01

    This document summarises a neutron activation cross-section database which has been processed in two formats for input to MCNP Monte Carlo codes and to REAC transmutation codes. The data are available from the IAEA Nuclear Data Section online via INTERNET by FTP command. (author)

  19. System requirements for the Los Alamos foil-implosion project

    International Nuclear Information System (INIS)

    Brownell, J.; Bowers, R.; Greene, A.; Lindemuth, I.; Nickel, G.; Oliphant, T.; Weiss, D.

    1983-01-01

    The goal of the Los Alamos imploding foil project is the development of an intense source of soft x rays and hot plasma produced from the thermalization of 1 to 10 MJ of plasma kinetic energy. The source will be used for material studies and fusion experiments. Specifically, thin, current-carrying cylindrical metallic plasmas are imploded via their self-magnetic forces. Features of this project are the use of high-explosive-driven flux-compression generators as the prime power source to achieve very high energies and fast opening switches to shorten the electrical pulses. To reach a load kinetic energy of 10 MJ, it is expected that the foil-plasma must carry about 50 MA of current and must implode in less than 1/2 μsec. This imposes the requirements that switch opening times must be less than 1/2 μsec and the transmission line must withstand voltages of about 1 MV. The system being pursued at Los Alamos is described, and model calculations are presented

  20. National projections of forest and rangeland condition indicators: a supporting technical document for the 1999 RPA assessment.

    Science.gov (United States)

    John Hof; Curtis Flather; Tony Baltic; Stephen. Davies

    1999-01-01

    The 1999 forest and rangeland condition indicator model is a set of independent econometric production functions for environmental outputs (measured with condition indicators) at the national scale. This report documents the development of the database and the statistical estimation required by this particular production structure with emphasis on two special...

  1. 40 CFR 60.2095 - What site-specific documentation is required?

    Science.gov (United States)

    2010-07-01

    .... (5) Procedures for operating the incinerator and associated air pollution control systems within the... incinerator operating limits. (7) Reporting and recordkeeping procedures. (8) The waste management plan... required? 60.2095 Section 60.2095 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR...

  2. Synthesis of the IRSN report on its analysis of the safety guidance package (DOrS) of the ASTRID reactor project. Safety guidance document for the ASTRID prototype: Referral to the GPR. Opinion related to the safety guidance document of the ASTRID reactor project. ASTRID prototype: Safety guidance document for the ASTRID prototype

    International Nuclear Information System (INIS)

    Lachaume, Jean-Luc; Niel, Jean-Christophe

    2013-01-01

    A first document indicates the improvement guidelines for the ASTRID project based on the French experience in the field of sodium-cooled fast neutron reactors, addresses the safety objectives as they are presented for the ASTRID project, discusses how the project includes a regulation and design referential, and how it addresses various aspects of the design approach (ranking and analysis of operation situations, defence in depth, use of probabilistic studies, safety classification and qualification to accidental situations, taking internal and external aggressions into account and taking severe accidents into account at the design level). It comments the guidelines related to the first two barriers, to main safety functions (control of reactivity and of reactor cooling, containment of radioactive and toxic materials), to dismantling, to R and D for safety support. A second document is a letter sent by the ASN to the GPR (permanent group of experts in charge of nuclear reactors) about the safety guidance document for the ASTRID prototype. The third document is the answer and contains comments and recommendations by this group about the content of this document, and therefore addresses the same topics as the first document. The last document defines the framework of the approach to this document

  3. 7 CFR 3402.23 - Documentation of progress on funded projects.

    Science.gov (United States)

    2010-01-01

    ... RESEARCH, EDUCATION, AND EXTENSION SERVICE, DEPARTMENT OF AGRICULTURE FOOD AND AGRICULTURAL SCIENCES... of Fellows supported by any special international study or thesis/dissertation research allowance and... Research Information System (CRIS). The CRIS database contains narrative project information, progress...

  4. Experimental conditions and monitoring items of the prototype repository project (PRP). Research document

    International Nuclear Information System (INIS)

    Sugita, Yutaka; Ito, Akira; Kawakami, Susumu

    2003-03-01

    Various experiments are ongoing in the underground research facility 'the Hard Rock Laboratory (HRL)' of SKB in Sweden for the geological disposal of the high-level radioactive waste. International joint project Prototype Repository Project (PRP) is one of the experiments in the HRL which has some engineered barrier systems and to study the coupled behavior happening in and around the engineered barrier system. JNC has joined this international joint project PRP to obtain the information of the coupled behavior on such systematic engineered barrier system and to apply the JNC's coupled THMC analytical code to the prediction and back analysis of the PRP. The analytical code will be verified through these analyses in this project. JNC can apply the verified analytical code to assess the coupled behavior in Japan. This report summarizes the experimental conditions and monitoring items of the PRP. (author)

  5. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 1

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The purpose of this Requirements Identification Document (RID) section is to identify, in one location, all of the facility specific requirements and good industry practices which are necessary or important to establish an effective Issues Management Program for the Tank Farm Facility. The Management Systems Functional Area includes the site management commitment to environmental safety and health (ES&H) policies and controls, to compliance management, to development and management of policy and procedures, to occurrence reporting and corrective actions, resource and issue management, and to the self-assessment process.

  6. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 1

    International Nuclear Information System (INIS)

    1994-04-01

    The purpose of this Requirements Identification Document (RID) section is to identify, in one location, all of the facility specific requirements and good industry practices which are necessary or important to establish an effective Issues Management Program for the Tank Farm Facility. The Management Systems Functional Area includes the site management commitment to environmental safety and health (ES ampersand H) policies and controls, to compliance management, to development and management of policy and procedures, to occurrence reporting and corrective actions, resource and issue management, and to the self-assessment process

  7. Functional and operational requirements document : building 1012, Battery and Energy Storage Device Test Facility, Sandia National Laboratories, New Mexico.

    Energy Technology Data Exchange (ETDEWEB)

    Johns, William H. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2013-11-01

    This report provides an overview of information, prior studies, and analyses relevant to the development of functional and operational requirements for electrochemical testing of batteries and energy storage devices carried out by Sandia Organization 2546, Advanced Power Sources R&D. Electrochemical operations for this group are scheduled to transition from Sandia Building 894 to a new Building located in Sandia TA-II referred to as Building 1012. This report also provides background on select design considerations and identifies the Safety Goals, Stakeholder Objectives, and Design Objectives required by the Sandia Design Team to develop the Performance Criteria necessary to the design of Building 1012. This document recognizes the Architecture-Engineering (A-E) Team as the primary design entity. Where safety considerations are identified, suggestions are provided to provide context for the corresponding operational requirement(s).

  8. The Army Materiel Requirements Documents: Qualitative Analysis of Efficiency and Effectiveness

    Science.gov (United States)

    2013-06-30

    65 - k~î~ä=mçëíÖê~Çì~íÉ=pÅÜççä= We measure efficiency based on two BPP initiatives: (1) Build Stronger Partnerships With the Requirements...poor,” “average,” or “excellent” based on comments received from SMEs in relation to the definitions of each BPP initiative during our interviews. A...M-ATV, and JLTV and how well they rank in terms of efficiency and effectiveness according to BPP initiatives. For efficiency, we assign a

  9. Detailed requirements document for common software of shuttle program information management system

    Science.gov (United States)

    Everette, J. M.; Bradfield, L. D.; Horton, C. L.

    1975-01-01

    Common software was investigated as a method for minimizing development and maintenance cost of the shuttle program information management system (SPIMS) applications while reducing the time-frame of their development. Those requirements satisfying these criteria are presented along with the stand-alone modules which may be used directly by applications. The SPIMS applications operating on the CYBER 74 computer, are specialized information management systems which use System 2000 as a data base manager. Common software provides the features to support user interactions on a CRT terminal using form input and command response capabilities. These features are available as subroutines to the applications.

  10. Databases in the documentation management for big industrial projects; Les bases de donnees dans la gestion documentaire des grands projets industriels

    Energy Technology Data Exchange (ETDEWEB)

    Cauchet, A; Chevillard, F; Parisot, Y; Tirefort, C [Societe EURODOC, Saint Quentin en Yvenlines (France)

    1990-05-01

    The documentation management of a big industrial project involves a continuous update of information, both in the study and realization phase or in the operation phase. The organization of the technical documentation for big industrial projects requests complex information systems. In the first part of this paper are presented the methods appropriate for the analysis of documentation management procedures and in the second part are presented the tools by the combination of which a documentation system for the user is provided. The case of the documentation centres for the Hague reprocessing plant is described.

  11. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 2

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The Quality Assurance Functional Area Requirements Identification Document (RID), addresses the programmatic requirements that ensure risks and environmental impacts are minimized, ensure safety, reliability, and performance are maximized through the application of effective management systems commensurate with the risks posed by the Tank Farm Facility and its operation. This RID incorporates guidance intended to provide Tank Farms management with the necessary requirements information to develop, upgrade, or assess the effectiveness of a Quality Assurance Program in the performance of organizational and functional activities. Quality Assurance is defined as all those planned and systematic actions necessary to provide adequate confidence that a facility, structure, system, or component will perform satisfactorily and safely in service. This document will provide the specific requirements to meet DNFSB recommendations and the guidance provided in DOE Order 5700.6C, utilizing industry codes, standards, regulatory guidelines, and industry good practices that have proven to be essential elements for an effective and efficient Quality Assurance Program as the nuclear industry has matured over the last thirty years.

  12. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 2

    International Nuclear Information System (INIS)

    1994-04-01

    The Quality Assurance Functional Area Requirements Identification Document (RID), addresses the programmatic requirements that ensure risks and environmental impacts are minimized, ensure safety, reliability, and performance are maximized through the application of effective management systems commensurate with the risks posed by the Tank Farm Facility and its operation. This RID incorporates guidance intended to provide Tank Farms management with the necessary requirements information to develop, upgrade, or assess the effectiveness of a Quality Assurance Program in the performance of organizational and functional activities. Quality Assurance is defined as all those planned and systematic actions necessary to provide adequate confidence that a facility, structure, system, or component will perform satisfactorily and safely in service. This document will provide the specific requirements to meet DNFSB recommendations and the guidance provided in DOE Order 5700.6C, utilizing industry codes, standards, regulatory guidelines, and industry good practices that have proven to be essential elements for an effective and efficient Quality Assurance Program as the nuclear industry has matured over the last thirty years

  13. International review on safety requirements for the prototype fast breeder reactor “Monju” (Translated document)

    International Nuclear Information System (INIS)

    2016-02-01

    In response to the lessons learned from the serious nuclear accidents at the TEPCO's Fukushima Daiichi Nuclear Power Stations, an advisory committee, which was set up by the Japan Atomic Energy Agency, issued the report “Safety Requirements Expected to the Prototype Fast Breeder Reactor Monju” taking into account the SFR specific safety characteristics in July 2014. The report was reviewed by the leading international experts on SFR safety from five countries and one international organization in order to obtain independent and objective evaluation. The international review comments on each subsection were collected and compiled, and then a summary of results was derived through the discussion at the review meeting and individual feedbacks. As a result the basic concept for prevention of severe accidents and mitigation of their consequences of Monju is appropriate in consideration of SFR specific safety characteristics, and is in accordance with international common understanding. (author)

  14. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 5

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The Fire Protection functional area for the Hanford Site Tank Farm facilities and support structures is based on the application of relevant DOE orders, regulations, and industry codes and standards. The fire protection program defined in this document may be divided into three areas: (1) organizational, (2) administrative programmatic features, and (3) technical features. The information presented in each section is in the form of program elements and orders, regulations, industry codes, and standards that serve as the attributes of a fire protection program for the Tank Farm facilities. Upon completion this document will be utilized as the basis to evaluate compliance of the fire protection program being implemented for the Tank Farm facilities with the requirements of DOE orders and industry codes and standards.

  15. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 5

    International Nuclear Information System (INIS)

    1994-04-01

    The Fire Protection functional area for the Hanford Site Tank Farm facilities and support structures is based on the application of relevant DOE orders, regulations, and industry codes and standards. The fire protection program defined in this document may be divided into three areas: (1) organizational, (2) administrative programmatic features, and (3) technical features. The information presented in each section is in the form of program elements and orders, regulations, industry codes, and standards that serve as the attributes of a fire protection program for the Tank Farm facilities. Upon completion this document will be utilized as the basis to evaluate compliance of the fire protection program being implemented for the Tank Farm facilities with the requirements of DOE orders and industry codes and standards

  16. Design requirements document for the phase 1 privatization electrical power system

    Energy Technology Data Exchange (ETDEWEB)

    Singh, G.

    1997-10-31

    The electrical system for the Phase 1 privatization facilities will support the TWRS mission by providing the electrical power to the Phase 1 privatized facilities. This system will receive power from the Department of Energy-Richland Operations (RL) A4-8 230 kV transmission system powered from Bonneville Power Administration (BPA) Ashe and Midway 230 kV Substations. The existing RL 230 kV transmission line will be modified and looped 1021 into the new 230 kV substation bus. The new substation will be located in the vicinity of the privatized facilities, approximately 3.2 km (2 mi) south of the existing RL A4-8 230 kV transmission line. The substation will be capable of providing up to 40 MW of electrical power to support the Phase 1 privatization facilities and has space for accommodating future expansions. The substation will require at least two 230-13.8 kV transformers, 13.8 kV split bus switchgear, switchgear building, grounding transformers, instrument transformers, control and monitoring equipment, associated protection and isolation devices, lightning protection, yard lighting, cable and raceways, and infrastructure needed to provide desired availability and reliability. The power from the 13.8 kV switchgear located in the switchgear building will be delivered at the privatization facilities site boundaries. The 13.8 kV distribution system inside the privatization facilities site boundaries is the responsibility of the privatization contract.

  17. Design requirements document for the phase 1 privatization electrical power system

    International Nuclear Information System (INIS)

    Singh, G.

    1997-01-01

    The electrical system for the Phase 1 privatization facilities will support the TWRS mission by providing the electrical power to the Phase 1 privatized facilities. This system will receive power from the Department of Energy-Richland Operations (RL) A4-8 230 kV transmission system powered from Bonneville Power Administration (BPA) Ashe and Midway 230 kV Substations. The existing RL 230 kV transmission line will be modified and looped 1021 into the new 230 kV substation bus. The new substation will be located in the vicinity of the privatized facilities, approximately 3.2 km (2 mi) south of the existing RL A4-8 230 kV transmission line. The substation will be capable of providing up to 40 MW of electrical power to support the Phase 1 privatization facilities and has space for accommodating future expansions. The substation will require at least two 230-13.8 kV transformers, 13.8 kV split bus switchgear, switchgear building, grounding transformers, instrument transformers, control and monitoring equipment, associated protection and isolation devices, lightning protection, yard lighting, cable and raceways, and infrastructure needed to provide desired availability and reliability. The power from the 13.8 kV switchgear located in the switchgear building will be delivered at the privatization facilities site boundaries. The 13.8 kV distribution system inside the privatization facilities site boundaries is the responsibility of the privatization contract

  18. Design criteria document, Fire Protection Task, K Basin Essential Systems Recovery, Project W-405

    International Nuclear Information System (INIS)

    Johnson, B.H.

    1994-01-01

    The K Basin were constructed in the early 1950's with a 20 year design life. The K Basins are currently in their third design life and are serving as a near term storage facility for irradiated N Reactor fuel until an interim fuel storage solution can be implemented. In April 1994, Project W-405, K Basin Essential Systems Recovery, was established to address (among other things) the immediate fire protection needs of the 100K Area. A Fire Barrier Evaluation was performed for the wall between the active and inactive areas of the 105KE and 105KW buildings. This evaluation concludes that the wall is capable of being upgraded to provide an equivalent level of fire resistance as a qualified barrier having a fire resistance rating of 2 hours. The Fire Protection Task is one of four separate Tasks included within the scope of Project W405, K Basin Essential systems Recovery. The other three Tasks are the Water Distribution System Task, the Electrical System Task, and the Maintenance Shop/Support Facility Task. The purpose of Project W-405's Fire Protection Task is to correct Life Safety Code (NFPA 101) non-compliances and to provide fire protection features in Buildings 105KE, 105KW and 190KE that are essential for assuring the safe operation and storage of spent nuclear fuel at the 100K Area Facilities' Irradiated Fuel Storage Basins (K Basins)

  19. SEISMIC DESIGN REQUIREMENTS SELECTION METHODOLOGY FOR THE SLUDGE TREATMENT and M-91 SOLID WASTE PROCESSING FACILITIES PROJECTS

    International Nuclear Information System (INIS)

    RYAN GW

    2008-01-01

    In complying with direction from the U.S. Department of Energy (DOE), Richland Operations Office (RL) (07-KBC-0055, 'Direction Associated with Implementation of DOE-STD-1189 for the Sludge Treatment Project,' and 08-SED-0063, 'RL Action on the Safety Design Strategy (SDS) for Obtaining Additional Solid Waste Processing Capabilities (M-91 Project) and Use of Draft DOE-STD-I 189-YR'), it has been determined that the seismic design requirements currently in the Project Hanford Management Contract (PHMC) will be modified by DOE-STD-1189, Integration of Safety into the Design Process (March 2007 draft), for these two key PHMC projects. Seismic design requirements for other PHMC facilities and projects will remain unchanged. Considering the current early Critical Decision (CD) phases of both the Sludge Treatment Project (STP) and the Solid Waste Processing Facilities (M-91) Project and a strong intent to avoid potentially costly re-work of both engineering and nuclear safety analyses, this document describes how Fluor Hanford, Inc. (FH) will maintain compliance with the PHMC by considering both the current seismic standards referenced by DOE 0 420.1 B, Facility Safety, and draft DOE-STD-1189 (i.e., ASCE/SEI 43-05, Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities, and ANSI ANS 2.26-2004, Categorization of Nuclear Facility Structures, Systems and Components for Seismic Design, as modified by draft DOE-STD-1189) to choose the criteria that will result in the most conservative seismic design categorization and engineering design. Following the process described in this document will result in a conservative seismic design categorization and design products. This approach is expected to resolve discrepancies between the existing and new requirements and reduce the risk that project designs and analyses will require revision when the draft DOE-STD-1189 is finalized

  20. DOCUMENTATION PROJECT FOR THE HISTORICAL GARDEN COMPLEX OF MOFAKHAM IN BOJNOURD – IRAN

    Directory of Open Access Journals (Sweden)

    S. Mehralizadeh

    2013-07-01

    Full Text Available The historical garden complex of Mofakham was built in the late nineteenth century as a formal pavilion garden in the city of Bojnourd in north-east Iran for the Persian monarch's local governor (hakem of the time. At least five main buildings and other secondary buildings of the garden complex have disappeared over the years. Although the surrounding context has changed totally, the axial route of the garden and two buildings of the complex remain. The documentation includes: 1. A precise two dimensional map of the complex (Figures 1–3, 2. A number of three dimensional images based on total 3D making (Images 4–5, 3. A 1/150 model

  1. The Sea Around Us Project: documenting and communicating global fisheries impacts on marine ecosystems.

    Science.gov (United States)

    Pauly, Daniel

    2007-06-01

    The Sea Around Us Project, initiated by the Pew Charitable Trusts in Philadelphia, PA, and located at the Fisheries Centre, University of British Columbia, Vancouver, Canada, started in mid 1999. Its goal was (and still is) to investigate the impact of fisheries on marine ecosystems and to propose policies to mitigate these impacts. Although conceived as a global activity, the project first emphasized the data-rich North Atlantic as a test bed for developing its approaches, which rely on mapping of catch data and indicators of ecosystem health derived from the analysis of long catch time series data. Initial achievements included mapping the decline, throughout the North Atlantic basin, of high-trophic level fishes from 1900 to the present and the presentation of compelling evidence of change in the functioning of the North Atlantic ecosystems, summarized in a 2003 book. The Central and South Atlantic were the next basins to be tackled, with emphasis on the distant-water fleet off West Africa, culminating in a major conference in Dakar, Senegal, in 2002. The project then emphasized the North Pacific, Antarctica, and marine mammals and the multiplicity of tropical Indo-Pacific fisheries before it turned completely global, with all our major analyses and reports (e.g., on the interactions between marine mammals and fisheries, on fuel consumption by fleets, on the catches of small-scale fisheries, on subsidies to fisheries) being based on global studies. Broadly, the work of the project is aimed at a reappraisal of fisheries, from the benign activity that many interested people still perceive them to be, to a realization that they have become the driver for massive loss of biodiversity in the ocean. Moreover, the emphasis on global estimates (rather than local estimates of dubious generality) has allowed the project to contribute to various global initiatives (e.g., developing the Marine Trophic Index for the Convention on Biological Diversity, quantifying marine

  2. 42 CFR 59.5 - What requirements must be met by a family planning project?

    Science.gov (United States)

    2010-10-01

    ... requirements must be met by a family planning project? (a) Each project supported under this part must: (1... (iii) Promote continued participation in the project by persons to whom family planning services may be... services purchased for project participants will be authorized by the project director or his designee on...

  3. A Text Mining Approach for Extracting Lessons Learned from Project Documentation: An Illustrative Case Study

    Directory of Open Access Journals (Sweden)

    Benjamin Matthies

    2017-12-01

    Full Text Available Lessons learned are important building blocks for continuous learning in project-based organisations. Nonetheless, the practical reality is that lessons learned are often not consistently reused for organisational learning. Two problems are commonly described in this context: the information overload and the lack of procedures and methods for the assessment and implementation of lessons learned. This paper addresses these problems, and appropriate solutions are combined in a systematic lesson learned process. Latent Dirichlet Allocation is presented to solve the first problem. Regarding the second problem, established risk management methods are adapted. The entire lessons learned process will be demonstrated in a practical case study

  4. Diffusion of the technology of the biogas in Colombia: Documentation of the Project. Cali (CO)

    International Nuclear Information System (INIS)

    1998-01-01

    The manual shows the general limits and considerations that should be kept in mind to implement the systems of biogas production in the Colombian rural zones. In this project they participated the Regional Autonomous Corporation of the Cauca C.V.C., the German Society of Technical Cooperation GTZ and the consultant German signature Dekotup; society for Adapted Technologies in Areas in Development Ltda. The importance of the biogas systems like technology adapted by the advantages is shown: they Reduce the danger and the contamination of the residuals payees of germs pathogens, they eliminate the unpleasant scent of the waste, they don't produce imbalance in the ecosystem and eat non by-product an effluent it is obtained with high properties bio fertilizing. Initially it is described the phases of the process of fermentation: hydrolysis, acidification and methanization, the types of biogas plants are described used floating bell, fixed dome and the ball plant; the methods for the planning and the design of the plants as well as the dimensions. It is presented a classic example of the design and construction of a plant. It is included the composition of the biogas and their use forms. The different biogas plants are shown that were built and those that were in project; the use of effluents of gas like bio-fertilizer, the form of determining the activities for the popularization of the biogas technology

  5. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 7. Revision 1

    International Nuclear Information System (INIS)

    Burt, D.L.

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 7) presents the standards and requirements for the following sections: Occupational Safety and Health, and Environmental Protection

  6. High-level waste storage tank farms/242-A evaporator Standards/Requirements Identification Document (S/RID), Volume 7. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    Burt, D.L.

    1994-04-01

    The High-Level Waste Storage Tank Farms/242-A Evaporator Standards/Requirements Identification Document (S/RID) is contained in multiple volumes. This document (Volume 7) presents the standards and requirements for the following sections: Occupational Safety and Health, and Environmental Protection.

  7. [A documentation procedure for community social psychiatry services--a pilot project in Bielefeld and Minden].

    Science.gov (United States)

    Hellmeier, W; Genin, G; Klewe-Niemann, S

    1996-04-01

    The status of health reporting (on community levels) has improved considerably during recent years. It is being increasingly used as an instrument for planning, controlling and evaluating political processes. In addition to individual studies the statistics within the departments of the health authorities are an important factor for meaningful health reporting on a local level. The IDIS (from Jan. 1st, 1995 LOGD) and the social psychiatric services on the Minden-Lübbecke district and the city of Bielefeld have developed a programme for automation-aided management of the statistics for social psychiatric services on a local level. Details on the personal situation and illnesses of the clients as well as on the activities of the services staff are recorded and analysed. Based on the WHO programme EPI-info 6.01 the documentation programme SPD-STAT was developed. This programme is menudriven and, in addition to the functions for the statistical data input and retrieval of fixed table sets, also offers the possibility of processing data with the full functionality of the ANALYSIS-module of EPI-Info. Thus interactive ad-hoc evaluations for current questions are made possible. Using SPD-STAT in as many local regions in NRW as possible may be a big step forward for health reporting on local levels as well as for health reporting on a state level.

  8. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 3

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    The Safeguards and Security (S&S) Functional Area address the programmatic and technical requirements, controls, and standards which assure compliance with applicable S&S laws and regulations. Numerous S&S responsibilities are performed on behalf of the Tank Farm Facility by site level organizations. Certain other responsibilities are shared, and the remainder are the sole responsibility of the Tank Farm Facility. This Requirements Identification Document describes a complete functional Safeguards and Security Program that is presumed to be the responsibility of the Tank Farm Facility. The following list identifies the programmatic elements in the S&S Functional Area: Program Management, Protection Program Scope and Evaluation, Personnel Security, Physical Security Systems, Protection Program Operations, Material Control and Accountability, Information Security, and Key Program Interfaces.

  9. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 3

    International Nuclear Information System (INIS)

    1994-04-01

    The Safeguards and Security (S ampersand S) Functional Area address the programmatic and technical requirements, controls, and standards which assure compliance with applicable S ampersand S laws and regulations. Numerous S ampersand S responsibilities are performed on behalf of the Tank Farm Facility by site level organizations. Certain other responsibilities are shared, and the remainder are the sole responsibility of the Tank Farm Facility. This Requirements Identification Document describes a complete functional Safeguards and Security Program that is presumed to be the responsibility of the Tank Farm Facility. The following list identifies the programmatic elements in the S ampersand S Functional Area: Program Management, Protection Program Scope and Evaluation, Personnel Security, Physical Security Systems, Protection Program Operations, Material Control and Accountability, Information Security, and Key Program Interfaces

  10. Horonobe Underground Research Laboratory project investigation program for the 2007 fiscal year (Translated document)

    International Nuclear Information System (INIS)

    Matsui, Hiroya; Nakayama, Masashi; Sanada, Hiroyuki; Yamaguchi, Takehiro

    2008-09-01

    As past of the research and development program on the geological disposal of high-level radioactive waste (HLW), the Horonobe Underground Research Center, a division of the Japan Atomic Energy Agency (JAEA), is implementing the Horonobe Underground Research Laboratory Project (Horonobe URL Project) with the aim at investigating sedimentary rock formations. According to the research plan described in the Midterm Plan of JAEA, geological investigations are to be carried out during the drilling of a shaft down to intermediate depth, while research and development in the areas of engineering technology and safety assessment are to be promoted by collaboration with other research organizations. The results of the R and D activities will be systematized as a 'knowledge base' that supports a wide range of arguments related to the safety of geological disposal. The Horonobe URL Project is planned to extend over a period of 20 years. The investigations will be conducted in three phases, namely 'Phase 1: Surface-based investigations', 'Phase 2: Construction phase' (investigations during construction of the underground facilities) and 'Phase 3: Operation phase' (research in the underground facilities). This report summarizes the investigation program for the 2007 fiscal year (2007/2008), the third year of the Phase 2 investigations. In the 2007 fiscal year, investigations in geoscientific research', including 'development of techniques for investigating the geological environment', 'development of techniques for use in the deep underground environment' and 'studies on the long-term stability of the geological environment', is continuously carried out. Investigations in 'research and development on geological disposal technology', including improving the reliability of disposal technologies' and 'enhancement of safety assessment methodologies' are also continuously carried out. Construction of the underground facilities is ongoing at the Ventilation Shaft and the East Shaft

  11. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 4

    Energy Technology Data Exchange (ETDEWEB)

    1994-04-01

    Radiation protection of personnel and the public is accomplished by establishing a well defined Radiation Protection Organization to ensure that appropriate controls on radioactive materials and radiation sources are implemented and documented. This Requirements Identification Document (RID) applies to the activities, personnel, structures, systems, components, and programs involved in executing the mission of the Tank Farms. The physical boundaries within which the requirements of this RID apply are the Single Shell Tank Farms, Double Shell Tank Farms, 242-A Evaporator-Crystallizer, 242-S, T Evaporators, Liquid Effluent Retention Facility (LERF), Purgewater Storage Facility (PWSF), and all interconnecting piping, valves, instrumentation, and controls. Also included is all piping, valves, instrumentation, and controls up to and including the most remote valve under Tank Farms control at any other Hanford Facility having an interconnection with Tank Farms. The boundary of the structures, systems, components, and programs to which this RID applies, is defined by those that are dedicated to and/or under the control of the Tank Farms Operations Department and are specifically implemented at the Tank Farms.

  12. High-level waste storage tank farms/242-A evaporator standards/requirements identification document (S/RID), Vol. 4

    International Nuclear Information System (INIS)

    1994-04-01

    Radiation protection of personnel and the public is accomplished by establishing a well defined Radiation Protection Organization to ensure that appropriate controls on radioactive materials and radiation sources are implemented and documented. This Requirements Identification Document (RID) applies to the activities, personnel, structures, systems, components, and programs involved in executing the mission of the Tank Farms. The physical boundaries within which the requirements of this RID apply are the Single Shell Tank Farms, Double Shell Tank Farms, 242-A Evaporator-Crystallizer, 242-S, T Evaporators, Liquid Effluent Retention Facility (LERF), Purgewater Storage Facility (PWSF), and all interconnecting piping, valves, instrumentation, and controls. Also included is all piping, valves, instrumentation, and controls up to and including the most remote valve under Tank Farms control at any other Hanford Facility having an interconnection with Tank Farms. The boundary of the structures, systems, components, and programs to which this RID applies, is defined by those that are dedicated to and/or under the control of the Tank Farms Operations Department and are specifically implemented at the Tank Farms

  13. Biodegradation of hazardous waste using white rot fungus: Project planning and concept development document

    International Nuclear Information System (INIS)

    Luey, J.; Brouns, T.M.; Elliott, M.L.

    1990-11-01

    The white rot fungus Phanerochaete chrysosporium has been shown to effectively degrade pollutants such as trichlorophenol, polychlorinated biphenyls (PCBs), dioxins and other halogenated aromatic compounds. These refractory organic compounds and many others have been identified in the tank waste, groundwater and soil of various US Department of Energy (DOE) sites. The treatment of these refractory organic compounds has been identified as a high priority for DOE's Research, Development, Demonstration, Testing, and Evaluation (RDDT ampersand E) waste treatment programs. Unlike many bacteria, the white rot fungus P. chrysosporium is capable of degrading these types of refractory organics and may be valuable for the treatment of wastes containing multiple pollutants. The objectives of this project are to identify DOE waste problems amenable to white rot fungus treatment and to develop and demonstrate white rot fungus treatment process for these hazardous organic compounds. 32 refs., 6 figs., 7 tabs

  14. Comment and response document for the UMTRA Project vitro processing site completion report Salt Lake City, Utah. Revision 1

    International Nuclear Information System (INIS)

    1995-03-01

    This Comment and Response Document is a series of UMTRA document review forms regarding the UMTRA Project Vitro Processing Site Completion Report for Salt Lake City, Utah in March, 1995. The completion report provides evidence that the final Salt Lake City, Utah, processing site property conditions are in accordance with the approved design and that all U.S. Environmental Protection Agency (EPA) standards have been satisfied. Included as appendices to support the stated conclusions are the record drawings; a summary of grid test results; contract specifications and construction drawings, the EPA standards (40 CFR Part 192); the audit, inspection, and surveillance summary; the permit information; and project photographs. The principal objective of the remedial action at Salt Lake City is to remove the tailings from the processing site, render the site free of contamination to EPA standards, and restore the site to the final design grade elevations. Each section is evaluated in detail to check all aspects of above report, especially the inclusion of adequate verification data. Each review form contains a section entitled State of Utah Response and Action, which is an explanation or correction of DOE criticisms of the report

  15. Applicability of PSD Requirements to the Wisconsin Electric Power Company Port Washington Life Extension Project

    Science.gov (United States)

    This document may be of assistance in applying the New Source Review (NSR) air permitting regulations including the Prevention of Significant Deterioration (PSD) requirements. This document is part of the NSR Policy and Guidance Database. Some documents in the database are a scanned or retyped version of a paper photocopy of the original. Although we have taken considerable effort to quality assure the documents, some may contain typographical errors. Contact the office that issued the document if you need a copy of the original.

  16. Data requirement comparison between the fixed site upgrade rule guidance compendium and the Structured Assessment Approach Licensee Submittal Document

    Energy Technology Data Exchange (ETDEWEB)

    Parziale, A.A.; Sacks, I.J.

    1980-12-01

    We compared the Structured Assessment Approach's (SAA) Licensee Submittal Document (LSD) with the Fixed Site Physical Protection Upgrade Rule Guidance Compendium Standard Format and Content (SFC) Guide using correlation matrices to see how well the data requirements of the SFC Guide coincided with those of a specific automated vulnerability assessment technique for fixed-site nuclear fuel cycle facilities, namely, SAA. We found that a limited SAA assessment is possible using the SFC Guide, but significant and critical safeguards vulnerabilities might be missed. Also, it was found that in some cases the organization and format of the SFC Guide input data and information made the preparation of data for the SAA somewhat awkward. 2 refs., 2 tabs.

  17. Extremely secure identification documents

    International Nuclear Information System (INIS)

    Tolk, K.M.; Bell, M.

    1997-09-01

    The technology developed in this project uses biometric information printed on the document and public key cryptography to ensure that an adversary cannot issue identification documents to unauthorized individuals or alter existing documents to allow their use by unauthorized individuals. This process can be used to produce many types of identification documents with much higher security than any currently in use. The system is demonstrated using a security badge as an example. This project focused on the technologies requiring development in order to make the approach viable with existing badge printing and laminating technologies. By far the most difficult was the image processing required to verify that the picture on the badge had not been altered. Another area that required considerable work was the high density printed data storage required to get sufficient data on the badge for verification of the picture. The image processing process was successfully tested, and recommendations are included to refine the badge system to ensure high reliability. A two dimensional data array suitable for printing the required data on the badge was proposed, but testing of the readability of the array had to be abandoned due to reallocation of the budgeted funds by the LDRD office

  18. Requirements for the project management in the client / engineering contractor relationship

    International Nuclear Information System (INIS)

    Hack, W.L.

    1995-01-01

    Investment projects impose a multitude of requirements upon clients and engineering contractors to cope with the management of project inherent conflicts. The paper reviews certain aspects on why such conflicts develop, and how they may be resolved. (orig.)

  19. 78 FR 53712 - Surface Transportation Project Delivery Program Application Requirements

    Science.gov (United States)

    2013-08-30

    ... application, and discussion of classes of multimodal projects that may be best handled on a case-by-case basis... submissions; a paragraph discussing the joint application process; and a paragraph authorizing the Agencies to... early enough to allow for a joint application of the Secretary's responsibilities before the...

  20. Required doses for projection methods in X-ray diagnosis

    International Nuclear Information System (INIS)

    Hagemann, G.

    1992-01-01

    The ideal dose requirement has been stated by Cohen et al. (1981) by a formula basing on parallel beam, maximum quantum yield and Bucky grid effect depending on the signal to noise ratio and object contrast. This was checked by means of contrast detail diagrams measured at the hole phantom, and was additionally compared with measurement results obtained with acrylic glass phantoms. The optimal dose requirement is obtained by the maximum technically possible approach to the ideal requirement level. Examples are given, besides for x-ray equipment with Gd 2 O 2 S screen film systems for grid screen mammography, and new thoracic examination systems for mass screenings. Finally, a few values concerning the dose requirement or the analogous time required for fluorscent screening in angiography and interventional radiology, are stated, as well as for dentistry and paediatric x-ray diagnostics. (orig./HP) [de

  1. Fear extinction requires infralimbic cortex projections to the basolateral amygdala.

    Science.gov (United States)

    Bloodgood, Daniel W; Sugam, Jonathan A; Holmes, Andrew; Kash, Thomas L

    2018-03-06

    Fear extinction involves the formation of a new memory trace that attenuates fear responses to a conditioned aversive memory, and extinction impairments are implicated in trauma- and stress-related disorders. Previous studies in rodents have found that the infralimbic prefrontal cortex (IL) and its glutamatergic projections to the basolateral amygdala (BLA) and basomedial amygdala (BMA) instruct the formation of fear extinction memories. However, it is unclear whether these pathways are exclusively involved in extinction, or whether other major targets of the IL, such as the nucleus accumbens (NAc) also play a role. To address this outstanding issue, the current study employed a combination of electrophysiological and chemogenetic approaches in mice to interrogate the role of IL-BLA and IL-NAc pathways in extinction. Specifically, we used patch-clamp electrophysiology coupled with retrograde tracing to examine changes in neuronal activity of the IL and prelimbic cortex (PL) projections to both the BLA and NAc following fear extinction. We found that extinction produced a significant increase in the intrinsic excitability of IL-BLA projection neurons, while extinction appeared to reverse fear-induced changes in IL-NAc projection neurons. To establish a causal counterpart to these observations, we then used a pathway-specific Designer Receptors Exclusively Activated by Designer Drugs (DREADD) strategy to selectively inhibit PFC-BLA projection neurons during extinction acquisition. Using this approach, we found that DREADD-mediated inhibition of PFC-BLA neurons during extinction acquisition impaired subsequent extinction retrieval. Taken together, our findings provide further evidence for a critical contribution of the IL-BLA neural circuit to fear extinction.

  2. Experimentation on accuracy of non functional requirement prioritization approaches for different complexity projects

    OpenAIRE

    Raj Kumar Chopra; Varun Gupta; Durg Singh Chauhan

    2016-01-01

    Non functional requirements must be selected for implementation together with functional requirements to enhance the success of software projects. Three approaches exist for performing the prioritization of non functional requirements using the suitable prioritization technique. This paper performs experimentation on three different complexity versions of the industrial software project using cost-value prioritization technique employing three approaches. Experimentation is conducted to analy...

  3. Technical documentation in support of the project-specific analysis for construction and operation of the National Ignition Facility

    Energy Technology Data Exchange (ETDEWEB)

    Lazaro, M.A.; Vinikour, W. [Argonne National Lab., IL (United States). Environmental Assessment Div.; Allison, T. [Argonne National Lab., IL (United States). Decision and Information Sciences Div.] [and others

    1996-09-01

    This document provides information that supports or supplements the data and impact analyses presented in the National Ignition Facility (NIF) Project-Specific Analysis (PSA). The purposes of NIF are to achieve fusion ignition in the laboratory for the first time with inertial confinement fusion (ICF) technology and to conduct high- energy-density experiments ins support of national security and civilian application. NIF is an important element in the DOE`s science-based SSM Program, a key mission of which is to ensure the reliability of the nation`s enduring stockpile of nuclear weapons. NIF would also advance the knowledge of basic and applied high-energy- density science and bring the nation a large step closer to developing fusion energy for civilian use. The NIF PSA includes evaluations of the potential environmental impacts of constructing and operating the facility at one of five candidate site and for two design options.

  4. Impact of Requirements Elicitation Processes on Success of Information System Development Projects

    Directory of Open Access Journals (Sweden)

    Bormane Līga

    2016-12-01

    Full Text Available Requirements articulating user needs and corresponding to enterprise business processes are a key to successful implementation of information system development projects. However, the parties involved in projects frequently are not able to agree on a common development vision and have difficulties expressing their needs. Several industry experts have acknowledged that requirements elicitation is one of the most difficult tasks in development projects. This study investigates the impact of requirements elicitation processes on project outcomes depending on the applied project development methodology.

  5. M2 priority screening system for near-term activities: Project documentation. Final report December 11, 1992--May 31, 1994

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1993-08-12

    From May through August, 1993, the M-2 Group within M Division at LANL conducted with the support of the LANL Integration and Coordination Office (ICO) and Applied Decision Analysis, Inc. (ADA), whose purpose was to develop a system for setting priorities among activities. This phase of the project concentrated on prioritizing near-tenn activities (i.e., activities that must be conducted in the next six months) necessary for setting up this new group. Potential future project phases will concentrate on developing a tool for setting priorities and developing annual budgets for the group`s operations. The priority screening system designed to address the near-term problem was developed, applied in a series of meeting with the group managers, and used as an aid in the assignment of tasks to group members. The model was intended and used as a practical tool for documenting and explaining decisions about near-term priorities, and not as a substitute for M-2 management judgment and decision-making processes.

  6. The tail wags the dog: managing large telescope construction projects with lagging requirements and creeping scope

    Science.gov (United States)

    Warner, Mark

    2014-08-01

    In a perfect world, large telescopes would be developed and built in logical, sequential order. First, scientific requirements would be agreed upon, vetted, and fully developed. From these, instrument designers would define their own subsystem requirements and specifications, and then flesh out preliminary designs. This in turn would then allow optic designers to specify lens and mirror requirements, which would permit telescope mounts and drives to be designed. Finally, software and safety systems, enclosures and domes, buildings, foundations, and infrastructures would be specified and developed. Unfortunately, the order of most large telescope projects is the opposite of this sequence. We don't live in a perfect world. Scientists usually don't want to commit to operational requirements until late in the design process, instrument designers frequently change and update their designs due to improving filter and camera technologies, and mount and optics engineers seem to live by the words "more" and "better" throughout their own design processes. Amplifying this is the fact that site construction of buildings and domes are usually the earliest critical path items on the schedule, and are often subject to lengthy permitting and environmental processes. These facility and support items therefore must quickly get underway, often before operational requirements are fully considered. Mirrors and mounts also have very long lead times for fabrication, which in turn necessitates that they are specified and purchased early. All of these factors can result in expensive and time-consuming change orders when requirements are finalized and/or shift late in the process. This paper discusses some of these issues encountered on large, multi-year construction projects. It also presents some techniques and ideas to minimize these effects on schedule and cost. Included is a discussion on the role of Interface Control Documents (ICDs), the importance (and danger) of making big

  7. Design criteria document, Maintenance Shop/Support Facility, K-Basin Essential Systems Recovery, Project W-405

    International Nuclear Information System (INIS)

    Strehlow, M.W.B.

    1994-01-01

    During the next 10 years a substantial amount of work is scheduled in the K-Basin Area related to the storage and eventual removal of irradiated N-Reactor fuel. Currently, maintenance support activities are housed in existing structures that were constructed in the early 1950's. These forty-year-old facilities and their supporting services are substandard, leading to inefficiencies. Because of numerous identified deficiencies and the planned increase in the numbers of K-Basin maintenance personnel, adequate maintenance support facilities that allow efficient operations are needed. The objective of this sub-project of Project W-405 is to provide a maintenance and storage facility which meets the K-Basin Maintenance Organization requirements as defined in Attachment 1. In Reference A, existing guidelines and requirements were used to allocate space for the maintenance activities and to provide a layout concept (See Attachment 2). The design solution includes modifying the existing 190 K-E building to provide space for shops, storage, and administration support functions. The primary reason for the modification is to simplify siting/permitting and make use of existing infrastructure. In addition, benefits relative to design loads will be realized by having the structure inside 190K-E. The new facility will meet the Maintenance Organization approved requirements in Attachment 1 relating to maintenance activities, storage areas, and personnel support services. This sub-project will also resolve outstanding findings and/or deficiencies relating to building fire protection, HVAC requirements, lighting replacement/upgrades, and personnel facilities. Compliance with building codes, local labor agreements and safety standards will result

  8. Alcan Kitimat smelter modernization project remedial action scheme functional requirements

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2008-09-09

    This paper identified remedial actions for reducing islanding and voltage collapse at the Alcan Kitimat smelter modernization project. The study was conducted after an earlier study indicated that the proposed project significantly increased electricity loads and stresses on Alcan's power system. Remedial actions included shedding the appropriate number of Kemano (KMO) generators; reducing Kitimat potline loads by de-saturating saturable reactors and lowering tap changers; and shedding potlines to preserve the Kitimat auxiliary load and facilitate power restoration. Power flow and transient stability studies were conducted to evaluate the impact of the remedial actions on the KMO generators and the transmission system. Results showed that fast load reduction improved power system response. Load reduction by changing the converter transformer tap reduced significant amounts of loads, but was too slow to be effective during fast voltage collapse. The study showed that although the remedial action scheme (RAS) reduced the impact of various contingencies on the Alcan system, performance was degraded due to the significant load increase. Fast load shedding capability was also reduced. It was concluded that further research is needed to develop and implement the RAS. 3 tabs., 7 figs.

  9. Projected transuranic waste loads requiring treatment, storage, and disposal

    International Nuclear Information System (INIS)

    Hong, K.; Kotek, T.

    1996-01-01

    This paper provides information on the volume of TRU waste loads requiring treatment, storage, and disposal at DOE facilities for three siting configurations. Input consisted of updated inventory and generation data from. Waste Isolation Pilot plant Transuranic Waste Baseline Inventory report. Results indicate that WIPP's design capacity is sufficient for the CH TRU waste found throughout the DOE Complex

  10. Using Project Complexity Determinations to Establish Required Levels of Project Rigor

    Energy Technology Data Exchange (ETDEWEB)

    Andrews, Thomas D.

    2015-10-01

    This presentation discusses the project complexity determination process that was developed by National Security Technologies, LLC, for the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office for implementation at the Nevada National Security Site (NNSS). The complexity determination process was developed to address the diversity of NNSS project types, size, and complexity; to fill the need for one procedure but with provision for tailoring the level of rigor to the project type, size, and complexity; and to provide consistent, repeatable, effective application of project management processes across the enterprise; and to achieve higher levels of efficiency in project delivery. These needs are illustrated by the wide diversity of NNSS projects: Defense Experimentation, Global Security, weapons tests, military training areas, sensor development and testing, training in realistic environments, intelligence community support, sensor development, environmental restoration/waste management, and disposal of radioactive waste, among others.

  11. Tolerancing requirements for remote handling at the Hanford vitrification project

    International Nuclear Information System (INIS)

    Keenan, R.M.; Bullis, R.E.; Van Katwijk, C.

    1993-01-01

    The Hanford Waste Vitrification Plant is being designed by Fluor Daniel, Inc. with WasteChem Corporation as Fluor Daniel's major subcontractor specializing in vitrification and remote system technologies. United Engineers and Constructors/Catalytic (UE ampersand C) will construct the plant. Westinghouse Hanford Company (WHC) is the Project Integration manager, manager and as the plant operator provides technical direction to the Architect/Engineer team (A/E) and constructor on behalf of the Department of Energy - Richland Field Office. The A/E has developed, in cooperation with UE ampersand C, WHC and DOE, a new and innovative approach to installations of the many remote nozzles and electrical connectors that must be installed to demanding tolerances. This paper summarizes the key elements of the HWVP approach

  12. Large-scale dam removal in the northeast United States: documenting ecological responses to the Penobscot River Restoration Project

    Science.gov (United States)

    Collins, M. J.; Aponte Clarke, G.; Baeder, C.; McCaw, D.; Royte, J.; Saunders, R.; Sheehan, T.

    2012-12-01

    The Penobscot River Restoration Project aims to improve aquatic connectivity in New England's second largest watershed ( 22,000 km2) by removing the two lowermost, mainstem dams and bypassing a third dam on a principal tributary upstream. Project objectives include: restoring unobstructed access to the entire historic riverine range for five lower river diadromous species including Atlantic and shortnose sturgeon; significantly improving access to upstream habitat for six upper river diadromous species including Atlantic salmon; reconnecting trophic linkages between headwater areas and the Gulf of Maine; restoring fluvial processes to the former impoundments; improving recreational and Penobscot Nation cultural opportunities; and maintaining basin-wide hydropower output. The project is expected to have landscape-scale benefits and the need for a significant investment in long-term monitoring and evaluation to formally quantify ecosystem response has been recognized. A diverse group of federal, state, tribal, NGO, and academic partners has developed a long-term monitoring and evaluation program composed of nine studies that began in 2009. Including American Recovery and Reinvestment Act (ARRA) funding that leveraged partner contributions, we have invested nearly $2M to date in pre- and post-removal investigations that evaluate geomorphology/bed sediment, water quality, wetlands, and fisheries. Given the number of affected diadromous species and the diversity of their life histories, we have initiated six distinct, but related, fisheries investigations to document these expected changes: Atlantic salmon upstream and downstream passage efficiency using passive integrated transponder (PIT) and acoustic telemetry; fish community structure via an index of biotic integrity (IBI); total diadromous fish biomass through hydroacoustics; shortnose sturgeon spawning and habitat use via active and passive acoustic telemetry; and freshwater-marine food web interactions by

  13. ELECTRICAL POWER SYSTEM DESCRIPTION DOCUMENT

    Energy Technology Data Exchange (ETDEWEB)

    M. Maniyar

    2004-06-22

    The purpose of this revision of the System Description Document (SDD) is to establish requirements that drive the design of the electrical power system and their bases to allow the design effort to proceed to License Application. This SDD is a living document that will be revised at strategic points as the design matures over time. This SDD identifies the requirements and describes the system design as they exist at this time, with emphasis on those attributes of the design provided to meet the requirements. This SDD has been developed to be an engineering tool for design control. Accordingly, the primary audience are design engineers. This type of SDD leads and follows the design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential to performing the design process. This SDD follows the design with regard to the description of the system. The description provided in the SDD is a reflection of the results of the design process to date. Functional and operational requirements applicable to this system are obtained from ''Project Functional and Operational Requirements'' (F&OR) (Siddoway, 2003). Other requirements to support the design process have been taken from higher level requirements documents such as ''Project Design Criteria Document'' (PDC) (Doraswamy 2004), the fire hazards analyses, and the preclosure safety analysis. The above mentioned low-level documents address ''Project Requirements Document'' (PRD) (Canori and Leitner 2003) requirements. This SDD includes several appendices with supporting information. Appendix B lists key system charts, diagrams, drawings, and lists; and Appendix C is a list of system procedures.

  14. Synthesized research report in the second mid-term research phase. Mizunami Underground Research Laboratory project, Horonobe Underground Research Laboratory project and geo-stability project (Translated document)

    International Nuclear Information System (INIS)

    Hama, Katsuhiro; Sasao, Eiji; Iwatsuki, Teruki; Onoe, Hironori; Sato, Toshinori; Yasue, Kenichi; Asamori, Koichi; Niwa, Masakazu; Osawa, Hideaki; Nagae, Isako; Natsuyama, Ryoko; Fujita, Tomoo; Sasamoto, Hiroshi; Matsuoka, Toshiyuki; Takeda, Masaki; Aoyagi, Kazuhei; Nakayama, Masashi; Miyakawa, Kazuya; Ito, Hiroaki; Ohyama, Takuya; Senba, Takeshi; Amano, Kenji

    2016-08-01

    We have synthesized the research results from the Mizunami/Horonobe Underground Research Laboratories (URLs) and geo-stability projects in the second mid-term research phase. This report can be used as a technical basis for the Nuclear Waste Management Organization of Japan/Regulator at each decision point from siting to beginning of disposal (Principal Investigation to Detailed Investigation Phase). High-quality construction techniques and field investigation methods have been developed and implemented, which will be directly applicable to the National Disposal Program (together with general assessments of hazardous natural events and processes). Acquisition of technical knowledge on decisions of partial backfilling and final closure from actual field experiments in the Mizunami/Horonobe URLs will be crucial as the main theme for the next phases. (author)

  15. Molten Salt Reactor Experiment Facility (Building 7503) standards/requirements identification document adherence assessment plan at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-02-01

    This is the Phase 2 (adherence) assessment plan for the Building 7503 Molten Salt Reactor Experiment (MSRE) Facility standards/requirements identification document (S/RID). This document outlines the activities to be conducted from FY 1996 through FY 1998 to ensure that the standards and requirements identified in the MSRE S/RID are being implemented properly. This plan is required in accordance with the Department of Energy Implementation Plan for Defense Nuclear Facilities Safety Board Recommendation 90-2, November 9, 1994, Attachment 1A. This plan addresses the major aspects of the adherence assessment and will be consistent with Energy Systems procedure QA-2. 7 ''Surveillances.''

  16. Private capital requirements for international biomass energy projects

    Energy Technology Data Exchange (ETDEWEB)

    Goldemberg, J [University of Sao Paulo, Sao Paulo (Brazil)

    1995-12-01

    In developing countries, the use of biomass for energy production faces two contradictory pressures. On the one hand, biomass costs very little and it is used inefficiently for fuel or charcoal production, leading to widespread destruction of forested areas and environmental degradation; this problem is being attenuated by the promotion, through aid programmes, of more efficient cook stoves for poor people. On the other hand, the conversion of biomass into high-grade fuel such as ethanol from sugar cane or burning urban refuse or gasifying it to produce electricity is not economically competitive at this time and requires subsidies of approximately 30% to make it as attractive as conventional fuels. Only electricity production using residues from sawmills, crops and other biomass by-products is competitive, and a number of plants are in operation in some countries, particularly the United States. For such plants, the usual rates of return and long-term contract purchases that characterize investments of this kind are applied. Although technologies are available for the widespread efficient use of biomass, the financial hurdle of high initial costs has impeded their market penetration, which in turn precludes any decline in costs that might otherwise have come from production increases. Intervention by governments or by GEF, justified on grounds of environmental protection, is needed to accelerate the introduction of the new technologies. The only private flows that are taking place at the moment are those from enlightened investors wishing to guarantee themselves a strong position in the area for the future or to preempt command and control regulations, such as carbon taxes, imposed by governments. The joint implementation of biomass technologies between industrialized and developing countries might be one method of accelerating this flow. (author) 9 refs, 4 figs, 3 tabs

  17. Private capital requirements for international biomass energy projects

    International Nuclear Information System (INIS)

    Goldemberg, J.

    1995-01-01

    In developing countries, the use of biomass for energy production faces two contradictory pressures. On the one hand, biomass costs very little and it is used inefficiently for fuel or charcoal production, leading to widespread destruction of forested areas and environmental degradation; this problem is being attenuated by the promotion, through aid programmes, of more efficient cook stoves for poor people. On the other hand, the conversion of biomass into high-grade fuel such as ethanol from sugar cane or burning urban refuse or gasifying it to produce electricity is not economically competitive at this time and requires subsidies of approximately 30% to make it as attractive as conventional fuels. Only electricity production using residues from sawmills, crops and other biomass by-products is competitive, and a number of plants are in operation in some countries, particularly the United States. For such plants, the usual rates of return and long-term contract purchases that characterize investments of this kind are applied. Although technologies are available for the widespread efficient use of biomass, the financial hurdle of high initial costs has impeded their market penetration, which in turn precludes any decline in costs that might otherwise have come from production increases. Intervention by governments or by GEF, justified on grounds of environmental protection, is needed to accelerate the introduction of the new technologies. The only private flows that are taking place at the moment are those from enlightened investors wishing to guarantee themselves a strong position in the area for the future or to preempt command and control regulations, such as carbon taxes, imposed by governments. The joint implementation of biomass technologies between industrialized and developing countries might be one method of accelerating this flow. (author)

  18. A Study on the Quantitative Assessment Method of Software Requirement Documents Using Software Engineering Measures and Bayesian Belief Networks

    International Nuclear Information System (INIS)

    Eom, Heung Seop; Kang, Hyun Gook; Park, Ki Hong; Kwon, Kee Choon; Chang, Seung Cheol

    2005-01-01

    One of the major challenges in using the digital systems in a NPP is the reliability estimation of safety critical software embedded in the digital safety systems. Precise quantitative assessment of the reliability of safety critical software is nearly impossible, since many of the aspects to be considered are of qualitative nature and not directly measurable, but they have to be estimated for a practical use. Therefore an expert's judgment plays an important role in estimating the reliability of the software embedded in safety-critical systems in practice, because they can deal with all the diverse evidence relevant to the reliability and can perform an inference based on the evidence. But, in general, the experts' way of combining the diverse evidence and performing an inference is usually informal and qualitative, which is hard to discuss and will eventually lead to a debate about the conclusion. We have been carrying out research on a quantitative assessment of the reliability of safety critical software using Bayesian Belief Networks (BBN). BBN has been proven to be a useful modeling formalism because a user can represent a complex set of events and relationships in a fashion that can easily be interpreted by others. In the previous works we have assessed a software requirement specification of a reactor protection system by using our BBN-based assessment model. The BBN model mainly employed an expert's subjective probabilities as inputs. In the process of assessing the software requirement documents we found out that the BBN model was excessively dependent on experts' subjective judgments in a large part. Therefore, to overcome the weakness of our methodology we employed conventional software engineering measures into the BBN model as shown in this paper. The quantitative relationship between the conventional software measures and the reliability of software were not identified well in the past. Then recently there appeared a few researches on a ranking of

  19. Cold vacuum drying facility design requirements

    International Nuclear Information System (INIS)

    IRWIN, J.J.

    1999-01-01

    This document provides the detailed design requirements for the Spent Nuclear Fuel Project Cold Vacuum Drying Facility. Process, safety, and quality assurance requirements and interfaces are specified

  20. Cold vacuum drying facility design requirements

    Energy Technology Data Exchange (ETDEWEB)

    IRWIN, J.J.

    1999-07-01

    This document provides the detailed design requirements for the Spent Nuclear Fuel Project Cold Vacuum Drying Facility. Process, safety, and quality assurance requirements and interfaces are specified.

  1. The control of documents maintained in the electronic media and the requirements of NBR ISO/IEC 17025 and adequacy for PNQ

    Directory of Open Access Journals (Sweden)

    Anselmo Ferreira de Castro

    2006-01-01

    Full Text Available During the assessments carried out by the authors at the diverse laboratories pertaining to the network of accredited laboratories - known as the Brazilian Calibration Network (RBC - the authors verified the difficulties that these laboratories had in meeting the requirements of NBR ISO/IEC 17025:2001 (Standard, related to the maintenance of documents in the electronic media. More and more laboratories are substituting traditional control with electronic document control, which allows for more agility in the recovery of information. These laboratories implement policies and procedures; however, they still feel insecure, in some way, as to how to meet all of these requirements, thereby giving rise to difficulties in the implementation of such. The aim of this paper is to discuss the control of documents stored in the electronic media, adopting requirement 4.3 of the Standard as the reference, and aiming, in this manner, to harmonize the assessment process of the procedures of document management in the electronic media, and to assist the laboratories in the interpretation of the Standard, so that they may implement systems that are adequate to their actual necessities and to their structural size, while at the same time complying with the referred to requirement. This work will not broach the treatment given to the records (requirement 4.12 of the Standard, facts (requirement 5.4.7 nor to the electronic transmission of results (requirement 5.10.7, leaving these subjects for posterior discussions.

  2. Site specific statutory compliance planning for the salt repository project at the Deaf Smith County Site, Texas: Requirements, strategy, and status: Revision 4

    International Nuclear Information System (INIS)

    1986-06-01

    This document and the requirements and actions it presents are addressed to the Deaf Smith County Site, Texas. The proposed actions upon which the plan is based are those described in Chapters 4 and 5 of the final EA for the site. Similarly, the environmental and health and safety requirements covered in the plan are those identified in the EA as being potentially applicable to the salt repository project at the Deaf Smith site. 12 figs., 8 tabs

  3. Traceability and communication of requirements in digital and I and C systems development - Project report 2003

    International Nuclear Information System (INIS)

    Sivertsen, T.; Frederiksen, R.; Thunem, A.P.J.; Holmberg, J.E.; Valkonen, J.; Ventae, O.

    2004-03-01

    The overall objective of the TACO project is to improve the knowledge on principles and best practices related to the issues concretised in the preproject. On basis of experiences in the Nordic countries, the project aims at identifying the best practices and most important criteria for ensuring effective communication in relation to requirements elicitation and analysis, understandability of requirements to all parties, and traceability of requirements through the different design phases. It is expected that the project will provide important input to the development of guidelines and establishment of recommended practices related to these activities. In the year 2003, the TACO-project concentrated on four central issues: 1) Representation of requirements origins. 2) Traceability techniques. 3) Configuration management and the traceability of requirements. 4) Identification and categorisation of system aspects and their models The work was presented at the first TACO Industrial Seminar, which took place in Stockholm on the 12th of December 2003. The seminar was hosted by SKI. (au)

  4. BENCHPAR PROJECT. How to Incorporate ThermaI-Hydro-Mechanical Coupled Processes into Performance Assessments and Design Studies for Radioactive Waste Disposal in Geological Formations. Guidance Document

    International Nuclear Information System (INIS)

    Stephansson, O.; Andersson, Johan

    2005-02-01

    The objective of this Guidance Document is to provide advice on how to incorporate thermo-hydro-mechanical (THM) coupled processes into Performance Assessments (PAS) and design studies for radioactive waste disposal in geological formations to be experienced in a European context. The document has been generated by the EU research project BENCHPAR: Benchmark Tests and Guidance on Coupled Processes for Performance Assessment of Nuclear Waste Repositories. The document starts in Section 1 with an explanation of why numerical analyses incorporating THM mechanisms are required for radioactive waste studies and provides background material on the subject. Then, the THM processes and their interactions are explained in Section 2. Three case examples of THM numerical analysis are presented in Section 3 to illustrate the type of work that can be conducted to study the near-field, upscaling, and the far-field. For the three cases, there is discussion on the main findings, the relevance to a safety case, the relative importance of the different couplings, and the uncertainties involved. The importance and priority of the THM couplings are then summarized in Section 4. It is especially important to be able to technically audit the numerical analyses in order to establish that all the relevant variables, parameters and mechanisms have been included in the modelling and hence that the numerical model adequately represents the rock and engineering reality. Accordingly, recommended soft and hard auditing procedures are presented in Section 5. In this Guidance Document, we emphasize especially that the most important step in numerical modelling is not executing the calculations per se, but the earlier conceptualization of the problem regarding the dominant processes, the material properties and parameters, the engineering perturbations, and their mathematical presentations. The associated modelling component of addressing the uncertainties and estimating their influence on the

  5. Medical Isotopes Production Project: Molybdenum-99 and related isotopes - environmental impact statement. Volume II, comment response document

    International Nuclear Information System (INIS)

    1996-04-01

    This Environmental Impact Statement (EIS) provides environmental and technical information concerning the U.S. Department of Energy's (DOE) proposal to establish a domestic source to produce molybdenum-99 (Mo-99) and related isotopes (iodine-131, xenon-133, and iodine-125). Mo-99, a radioactive isotope of the element molybdenum, decays to form metastable technetium-99 (Tc-99m), a radioactive isotope used thousands of times daily in medical diagnostic procedures in the U.S. Currently, all Mo-99 used in the U.S. is obtained from a single Canadian source. DOE is pursuing the Medical Isotopes Production Project in order to ensure that a reliable supply of Mo-99 is available to the U.S. medical community as soon as practicable. Under DOE's preferred alternative, the Chemistry and Metallurgy Research Facility at the Los Alamos National Laboratory (LANL) and the Annular Core Research Reactor and Hot Cell Facility at Sandia National Laboratories/New Mexico (SNL/NM) would be used for production of the medical isotopes. In addition, three other reasonable alternatives and a No Action alternative are analyzed in detail, The sites for these three reasonable alternatives are LANL, Oak Ridge National Laboratory (ORNL), and Idaho National Engineering Laboratory (INEL). The analyses in this EIS indicate no significant difference in the potential environmental impacts among the alternatives. Each of the alternatives would use essentially the same technology for the production of the medical isotopes. Minor differences in environmental impacts among alternatives relate to the extent of activity necessary to modify and restart (as necessary) existing reactors and hot cell facilities at each of the sites, the quantities of low-level radioactive waste generated, how such waste would be managed, and the length of time needed for initial and full production capacity. This document contains comments recieved from meetings held regarding the site selection for isotope production

  6. ELECTRICAL SUPPORT SYSTEM DESCRIPTION DOCUMENT

    Energy Technology Data Exchange (ETDEWEB)

    S. Roy

    2004-06-24

    The purpose of this revision of the System Design Description (SDD) is to establish requirements that drive the design of the electrical support system and their bases to allow the design effort to proceed to License Application. This SDD is a living document that will be revised at strategic points as the design matures over time. This SDD identifies the requirements and describes the system design as they exist at this time, with emphasis on those attributes of the design provided to meet the requirements. This SDD has been developed to be an engineering tool for design control. Accordingly, the primary audience/users are design engineers. This type of SDD both ''leads'' and ''trails'' the design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. The SDD trails the design with regard to the description of the system. The description provided in the SDD is a reflection of the results of the design process to date. Functional and operational requirements applicable to electrical support systems are obtained from the ''Project Functional and Operational Requirements'' (F&OR) (Siddoway 2003). Other requirements to support the design process have been taken from higher-level requirements documents such as the ''Project Design Criteria Document'' (PDC) (Doraswamy 2004), and fire hazards analyses. The above-mentioned low-level documents address ''Project Requirements Document'' (PRD) (Canon and Leitner 2003) requirements. This SDD contains several appendices that include supporting information. Appendix B lists key system charts, diagrams, drawings, and lists, and Appendix C includes a list of system procedures.

  7. ELECTRICAL SUPPORT SYSTEM DESCRIPTION DOCUMENT

    International Nuclear Information System (INIS)

    Roy, S.

    2004-01-01

    The purpose of this revision of the System Design Description (SDD) is to establish requirements that drive the design of the electrical support system and their bases to allow the design effort to proceed to License Application. This SDD is a living document that will be revised at strategic points as the design matures over time. This SDD identifies the requirements and describes the system design as they exist at this time, with emphasis on those attributes of the design provided to meet the requirements. This SDD has been developed to be an engineering tool for design control. Accordingly, the primary audience/users are design engineers. This type of SDD both ''leads'' and ''trails'' the design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. The SDD trails the design with regard to the description of the system. The description provided in the SDD is a reflection of the results of the design process to date. Functional and operational requirements applicable to electrical support systems are obtained from the ''Project Functional and Operational Requirements'' (F andOR) (Siddoway 2003). Other requirements to support the design process have been taken from higher-level requirements documents such as the ''Project Design Criteria Document'' (PDC) (Doraswamy 2004), and fire hazards analyses. The above-mentioned low-level documents address ''Project Requirements Document'' (PRD) (Canon and Leitner 2003) requirements. This SDD contains several appendices that include supporting information. Appendix B lists key system charts, diagrams, drawings, and lists, and Appendix C includes a list of system procedures

  8. Structuring Requirements in a Multi-Project Environment in the Construction Industry

    DEFF Research Database (Denmark)

    Wörösch, Michael

    2012-01-01

    Being in control of requirements in building projects is vital, since it helps securing the often small profit margins and the reputation of the responsible company. Hence this research aims to introduce requirements management to the construction industry. By means of case study and action...... in this industry, yet, success is here defined as an accomplished and accepted implementation of requirements management processes that are used by the relevant project members in their daily work and where the benefits of implementing requirements management outweighs the cost of invested resources. Furthermore...... it is argued that when running technology development, product development, product platform development, and a portfolio of building projects at the same time the use of requirements management is advantageous and an intelligent way of structuring requirements is needed. This article also demonstrates...

  9. Iraqi Perspectives Project. Primary Source Materials for Saddam and Terrorism: Emerging Insights from Captured Iraqi Documents. Volume 2 (Redacted)

    National Research Council Canada - National Science Library

    Woods, Kevin M

    2007-01-01

    Captured Iraqi documents have uncovered evidence that links the regime of Saddam Hussein to regional and global terrorism, including a variety of revolutionary, liberation, nationalist, and Islamic...

  10. Iraqi Perspectives Project. Primary Source Materials for Saddam and Terrorism: Emerging Insights from Captured Iraqi Documents. Volume 5 (Redacted)

    National Research Council Canada - National Science Library

    Woods, Kevin M

    2007-01-01

    Captured Iraqi documents have uncovered evidence that links the regime of Saddam Hussein to regional and global terrorism, including a variety of revolutionary, liberation, nationalist, and Islamic...

  11. Iraqi Perspectives Project. Primary Source Materials for Saddam and Terrorism: Emerging Insights from Captured Iraqi Documents. Volume 3 (Redacted)

    National Research Council Canada - National Science Library

    Woods, Kevin M

    2007-01-01

    Captured Iraqi documents have uncovered evidence that links the regime of Saddam Hussein to regional and global terrorism, including a variety of revolutionary, liberation, nationalist, and Islamic...

  12. Iraqi Perspectives Project. Primary Source Materials for Saddam and Terrorism: Emerging Insights from Captured Iraqi Documents. Volume 4 (Redacted)

    National Research Council Canada - National Science Library

    Woods, Kevin M

    2007-01-01

    Captured Iraqi documents have uncovered evidence that links the regime of Saddam Hussein to regional and global terrorism, including a variety of revolutionary, liberation, nationalist, and Islamic...

  13. Projecting climate change in the United States: A technical document supporting the Forest Service RPA 2010 Assessment

    Science.gov (United States)

    Linda A. Joyce; David T. Price; David P. Coulson; Daniel W. McKenney; R. Martin Siltanen; Pia Papadopol; Kevin. Lawrence

    2014-01-01

    A set of climate change projections for the United States was developed for use in the 2010 USDA Forest Service RPA Assessment. These climate projections, along with projections for population dynamics, economic growth, and land use change in the United States, comprise the RPA scenarios and are used in the RPA Assessment to project future renewable resource conditions...

  14. Managing one thousand designs documents: what the success of project has about that?; Gerenciando mil documentos de projetos: o que o sucesso do empreendimento tem com isso?

    Energy Technology Data Exchange (ETDEWEB)

    Oliveira, Ailton C.; Pio, Bruno P. [PETROBRAS S.A., Rio de Janeiro, RJ (Brazil)

    2008-07-01

    Project Management Techniques based on PMI- Project Management Institute have become widely disseminated with showing results in performance improvements. In this paper is presented the improvement obtained in supervising projects in gas pipeline network deployments in Northeast of Brazil by the use of project good practices. The clear definition of project phases; the use of integrated management system; the application of check lists and the prioritization of the issue/approval of documents are examples of tools that impact on the processes of management, with emphasis on control of scope, time, quality and communication. To evaluate the results obtained with the use of these tools is made a comparison between the project of deployment of City Gates TermoFortaleza (CE) and Pedras de Fogo (PB), both belonging to the Program Extension of network Northeast pipeline. (author)

  15. Evaluation of data requirements for computerized constructability analysis of pavement rehabilitation projects.

    Science.gov (United States)

    2013-08-01

    This research aimed to evaluate the data requirements for computer assisted construction planning : and staging methods that can be implemented in pavement rehabilitation projects in the state of : Georgia. Results showed that two main issues for the...

  16. 42 CFR 137.360 - Does the Secretary approve project planning and design documents prepared by the Self-Governance...

    Science.gov (United States)

    2010-10-01

    ... design documents prepared by the Self-Governance Tribe? 137.360 Section 137.360 Public Health PUBLIC... HUMAN SERVICES TRIBAL SELF-GOVERNANCE Construction Roles of the Secretary in Establishing and... documents prepared by the Self-Governance Tribe? The Secretary shall have at least one opportunity to...

  17. SNF AGING SYSTEM DESCRIPTION DOCUMENT

    International Nuclear Information System (INIS)

    L.L. Swanson

    2005-01-01

    The purpose of this system description document (SDD) is to establish requirements that drive the design of the spent nuclear fuel (SNF) aging system and associated bases, which will allow the design effort to proceed. This SDD will be revised at strategic points as the design matures. This SDD identifies the requirements and describes the system design, as it currently exists, with emphasis on attributes of the design provided to meet the requirements. This SDD is an engineering tool for design control; accordingly, the primary audience and users are design engineers. This SDD is part of an iterative design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. The SDD follows the design with regard to the description of the system. The description provided in the SDD reflects the current results of the design process. Throughout this SDD, the term aging cask applies to vertical site-specific casks and to horizontal aging modules. The term overpack is a vertical site-specific cask that contains a dual-purpose canister (DPC) or a disposable canister. Functional and operational requirements applicable to this system were obtained from ''Project Functional and Operational Requirements'' (F andOR) (Curry 2004 [DIRS 170557]). Other requirements that support the design process were taken from documents such as ''Project Design Criteria Document'' (PDC) (BSC 2004 [DES 171599]), ''Site Fire Hazards Analyses'' (BSC 2005 [DIRS 172174]), and ''Nuclear Safety Design Bases for License Application'' (BSC 2005 [DIRS 171512]). The documents address requirements in the ''Project Requirements Document'' (PRD) (Canori and Leitner 2003 [DIRS 166275]). This SDD includes several appendices. Appendix A is a Glossary; Appendix B is a list of key system charts, diagrams, drawings, lists and additional supporting information; and Appendix C is a list of

  18. Traceability and communication of requirements in digital I and C systems development - the TACO project

    International Nuclear Information System (INIS)

    Sivertsen, Terje; Fredriksen, Rune; Thunem, Atoosa P-J.

    2004-01-01

    This paper summarizes some of the issues studied in the TACO project, a current activity partially funded by Nordic nuclear safety research through the NKS-R programme (NKS-R project number NKS R2 002 1 6). For more details, the reader is referred to the two project reports already delivered by the project (see section 9). On basis of experiences in the Nordic countries, the TACO project aims at identifying the best practices and most important criteria for ensuring effective communication in relation to requirements elicitation and analysis, understandability of requirements to all parties, and traceability of requirements through the different design phases. It is expected that the project will provide important input to the development of guidelines and establishment of recommended practices related to these activities. The overall aim of the preproject, which was carried out in the second half of 2002, was to identify the main issues related to traceability and communication of requirements in digital I and C systems development. By focusing on the identification of main issues, the preproject provided a basis for prioritising further work, while at the same time providing some initial recommendations related to these issues. The establishment of a Nordic expert network within the subject was another important result of the preproject. Further work has concentrated on four central and related issues, viz.; Representation of requirements origins; Traceability techniques; Configuration management and the traceability of requirements; Identification and categorisation of system aspects and their models. (Author)

  19. I-15 integrated corridor management : system requirements.

    Science.gov (United States)

    2011-07-01

    This document is intended as a listing and discussion of the Requirements for the I-15 Integrated Corridor Management System : (ICMS) Demonstration Project in San Diego. This document describes what the system is to do (the functional requirements), ...

  20. Documentation Panels Enhance Teacher Education Programs

    Science.gov (United States)

    Warash, Bobbie Gibson

    2005-01-01

    Documentation of children's projects is advantageous to their learning process and is also a good method for student teachers to observe the process of learning. Documentation panels are a unique way to help student teachers understand how children learn. Completing a panel requires a student teacher to think through a process. Teachers must learn…

  1. Salt Repository Project transportation system interface requirements: Transportation system/repository receiving facility interface requirements

    International Nuclear Information System (INIS)

    Smith, L.A.; Insalaco, J.W.; Trainer, T.A.

    1988-01-01

    This report is a preliminary review of the interface between the transportation system and the repository receiving facility for a nuclear waste mined geologic disposal system in salt. Criteria for generic cask and facility designs are developed. These criteria are derived by examining the interfaces that occur as a result of the operations needed to receive nuclear waste at a repository. These criteria provide the basis for design of a safe, operable, practical nuclear waste receiving facility. The processing functions required to move the shipping unit from the gate into the unloading area and back to the gate for dispatch are described. Criteria for a generic receiving facility are discussed but no specific facility design is presented or evaluated. The criteria are stated in general terms to allow application to a wide variety of cask and facility designs. 9 refs., 6 figs., 4 tabs

  2. Graphics Standards in the Computer-aided Acquisition and Logistic Support (CALS) Program, Fiscal Year 1989. Volume 1. Test Requirements Document and Extended CGM (CGEM)

    Science.gov (United States)

    1990-07-01

    at the firet meng in Munich, it was foyud isthere exis•s some avedap between the stated goals of• • DG Standards and t•e CGt e SG con ded t in cumin ... stressing importance of liaison and harmonization with closely related groups; Japan - making suggestions that the NWI and Requirements Document be improved

  3. South African CSP projects under the REIPPP programme - Requirements, challenges and opportunities

    Science.gov (United States)

    Relancio, Javier; Cuellar, Alberto; Walker, Gregg; Ettmayr, Chris

    2016-05-01

    Thus far seven Concentrated Solar Power (CSP) projects have been awarded under the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), totalling 600MW: one project is in operation, four under construction and two on their way to financial close. This provides an excellent opportunity for analysis of key features of the projects that have contributed to or detracted from the programme's success. The paper draws from Mott MacDonald's involvement as Technical Advisor on the seven CSP projects that have been successful under the REIPPPP to date as well as other global CSP developments. It presents how various programme requirements have affected the implementation of projects, such as the technical requirements, time of day tariff structure, economic development requirements and the renewable energy grid code. The increasingly competitive tariffs offered have encouraged developers to investigate efficiency maximising project configurations and cost saving mechanisms, as well as featuring state of the art technology in their proposals. The paper assesses the role of the project participants (developers, lenders and government) with regards to these innovative technologies and solutions. In our paper we discuss the status of projects and the SA market, analysing the main challenges and opportunities that in turn have influenced various aspects such as technology choice, operational regimes and supply chain arrangements.

  4. Presentation of the Results from the Project of Making Base Documents for Low-Emission Development Strategy for Croatia Until 2030 with an Outlook to 2050

    International Nuclear Information System (INIS)

    Jelavic, V.; Delija, V.; Herencic, L.

    2016-01-01

    Paris Climate Agreement is United Nations' Framework Convention on Climate Change way of encouraging countries to prepare Low-Emission development strategies and shows that climate change require long-term development strategies that support sustainable development, with the purpose of limiting the increase of global temperature to the maximal 2 degrees Celsius by the end of the century. The starting point of EU's policy towards low-emission economy is a goal of reducing greenhouse gas emissions by 80-95 percent by 2050. In accordance with that goal, The European Council adopted a climate-energy framework 2030 in October 2014, which sets a goal of reducing emissions - 40 percent by 2030. It also sets a goal of renewable energy sources share of up to 27 percent and an indicative goal of reducing energy consumption - 27 percent. At this moment, a process of accepting and consultations for regulatory climate-energy framework is taking part, as well as a change of greenhouse gas market directive, distribution of load on countries regulation and calculations of emissions from the sector of Land use, Land-use Change and Forestry (LULUCF) regulation. In 2015, The Ministry of Environment and Energy has started a project of making base documents for Low-Emission Development Strategy until 2030 with an outlook to 2050. This strategy applies to every economy and human activity sector and is especially linked to energy sector, industrial, transport, agriculture, forestry and waste management sectors. In the process of making base documents for the Strategy, a number of scenarios were analysed, models for simulations and optimisation were applied and an integral model for national greenhouse gas projections was developed. The Strategy outlines three scenarios: Reference scenario represents the application of the existing legislation while the other two scenarios present a transition towards low-emission economy: Gradual Transition Scenario (NU1) and Strong Transition Scenario

  5. Optimizing experimental parameters for the projection requirement in HAADF-STEM tomography

    Energy Technology Data Exchange (ETDEWEB)

    Aveyard, R., E-mail: r.a.aveyard@tudelft.nl [Department of Imaging Physics, Delft University of Technology, 2628CJ Delft (Netherlands); Zhong, Z.; Batenburg, K.J. [Centrum Wiskunde and Informatica, Science Park 123, NL-1098 XG Amsterdam (Netherlands); Rieger, B., E-mail: b.rieger@tudelft.nl [Department of Imaging Physics, Delft University of Technology, 2628CJ Delft (Netherlands)

    2017-06-15

    Highlights: • The extent to which HAADF-STEM meets the projection requirement has been studied. • Multislice simulations used to model beam propagation and study signal linearity. • Propagation in crystalline and amorphous materials considered. • Optimal experimental set-up for the projection requirement is discussed. - Abstract: Tomographic reconstruction algorithms offer a means by which a tilt-series of transmission images can be combined to yield a three dimensional model of the specimen. Conventional reconstruction algorithms assume that the measured signal is a linear projection of some property, typically the density, of the material. Here we report the use of multislice simulations to investigate the extent to which this assumption is met in HAADF-STEM imaging. The use of simulations allows for a systematic survey of a range of materials and microscope parameters to inform optimal experimental design. Using this approach it is demonstrated that the imaging of amorphous materials is in good agreement with the projection assumption in most cases. Images of crystalline specimens taken along zone-axes are found to be poorly suited for conventional linear reconstruction algorithms due to channelling effects which produce enhanced intensities compared with off-axis images, and poor compliance with the projection requirement. Off-axis images are found to be suitable for reconstruction, though they do not strictly meet the linearity requirement in most cases. It is demonstrated that microscope parameters can be selected to yield improved compliance with the projection requirement.

  6. Optimizing experimental parameters for the projection requirement in HAADF-STEM tomography

    International Nuclear Information System (INIS)

    Aveyard, R.; Zhong, Z.; Batenburg, K.J.; Rieger, B.

    2017-01-01

    Highlights: • The extent to which HAADF-STEM meets the projection requirement has been studied. • Multislice simulations used to model beam propagation and study signal linearity. • Propagation in crystalline and amorphous materials considered. • Optimal experimental set-up for the projection requirement is discussed. - Abstract: Tomographic reconstruction algorithms offer a means by which a tilt-series of transmission images can be combined to yield a three dimensional model of the specimen. Conventional reconstruction algorithms assume that the measured signal is a linear projection of some property, typically the density, of the material. Here we report the use of multislice simulations to investigate the extent to which this assumption is met in HAADF-STEM imaging. The use of simulations allows for a systematic survey of a range of materials and microscope parameters to inform optimal experimental design. Using this approach it is demonstrated that the imaging of amorphous materials is in good agreement with the projection assumption in most cases. Images of crystalline specimens taken along zone-axes are found to be poorly suited for conventional linear reconstruction algorithms due to channelling effects which produce enhanced intensities compared with off-axis images, and poor compliance with the projection requirement. Off-axis images are found to be suitable for reconstruction, though they do not strictly meet the linearity requirement in most cases. It is demonstrated that microscope parameters can be selected to yield improved compliance with the projection requirement.

  7. 18 CFR 401.36 - Water supply projects-Conservation requirements.

    Science.gov (United States)

    2010-04-01

    ... 18 Conservation of Power and Water Resources 2 2010-04-01 2010-04-01 false Water supply projects-Conservation requirements. 401.36 Section 401.36 Conservation of Power and Water Resources DELAWARE RIVER BASIN... Compact § 401.36 Water supply projects—Conservation requirements. Maximum feasible efficiency in the use...

  8. Development of a traceability analysis method based on case grammar for NPP requirement documents written in Korean language

    International Nuclear Information System (INIS)

    Yoo, Yeong Jae; Seong, Poong Hyun; Kim, Man Cheol

    2004-01-01

    Software inspection is widely believed to be an effective method for software verification and validation (V and V). However, software inspection is labor-intensive and, since it uses little technology, software inspection is viewed upon as unsuitable for a more technology-oriented development environment. Nevertheless, software inspection is gaining in popularity. KAIST Nuclear I and C and Information Engineering Laboratory (NICIEL) has developed software management and inspection support tools, collectively named 'SIS-RT.' SIS-RT is designed to partially automate the software inspection processes. SIS-RT supports the analyses of traceability between a given set of specification documents. To make SIS-RT compatible for documents written in Korean, certain techniques in natural language processing have been studied. Among the techniques considered, case grammar is most suitable for analyses of the Korean language. In this paper, we propose a methodology that uses a case grammar approach to analyze the traceability between documents written in Korean. A discussion regarding some examples of such an analysis will follow

  9. Standardizing instream flow requirements at hydropower projects in the Cascade Mountains, Washington

    Energy Technology Data Exchange (ETDEWEB)

    Smith, I.M.; Sale, M.J.

    1993-06-01

    Instream flow requirements are common mitigation measures instituted in the bypassed reaches of hydroelectric diversion projects. Currently, there are two extremes among the ways to determine instream flow requirements: generic standard-setting methods and detailed, habitat-based, impact assessment methods such as the Instream Flow Incremental Methodology (IFIM). Data from streams in Washington state show a consistent pattern in the instream flow requirements resulting from the IFIM. This pattern can be used to refine the simpler standard-setting approaches and thereby provide better estimates of flow needs during early stages of project design.

  10. 76 FR 2683 - Notice of a Project Waiver of Section 1605: (Buy American Requirement) of the American Recovery...

    Science.gov (United States)

    2011-01-14

    ... to delay shovel ready projects by requiring entities, like the IEUA, to revise their design and... the ``shovel ready'' status for this project. Further delay of this project would contravene the most...

  11. 76 FR 18218 - Notice of a Project Waiver of Section 1605 (Buy American Requirement) of the American Recovery...

    Science.gov (United States)

    2011-04-01

    ... delay projects that are ``shovel ready'' by requiring cities such as Salt Lake City to revise their... unreasonable delay and thus displace the ``shovel ready'' status for this project. To further delay project...

  12. 76 FR 2684 - Notice of a Project Waiver of Section 1605 (Buy American Requirement) of the American Recovery...

    Science.gov (United States)

    2011-01-14

    ... construction, not to delay shovel ready projects by requiring entities, like Lake County, to revise their... thus displace the ``shovel ready'' status for this project. Further delay of this project would...

  13. Experimentation on accuracy of non functional requirement prioritization approaches for different complexity projects

    Directory of Open Access Journals (Sweden)

    Raj Kumar Chopra

    2016-09-01

    Full Text Available Non functional requirements must be selected for implementation together with functional requirements to enhance the success of software projects. Three approaches exist for performing the prioritization of non functional requirements using the suitable prioritization technique. This paper performs experimentation on three different complexity versions of the industrial software project using cost-value prioritization technique employing three approaches. Experimentation is conducted to analyze the accuracy of individual approaches and the variation of accuracy with the complexity of the software project. The results indicate that selecting non functional requirements separately, but in accordance with functionality has higher accuracy amongst the other two approaches. Further, likewise other approaches, it witnesses the decrease in accuracy with increase in software complexity but the decrease is minimal.

  14. Computer system requirements specification for 101-SY hydrogen mitigation test project data acquisition and control system (DACS-1)

    International Nuclear Information System (INIS)

    McNeece, S.G.; Truitt, R.W.

    1994-01-01

    The system requirements specification for SY-101 hydrogen mitigation test project (HMTP) data acquisition and control system (DACS-1) documents the system requirements for the DACS-1 project. The purpose of the DACS is to provide data acquisition and control capabilities for the hydrogen mitigation testing of Tank SY-101. Mitigation testing uses a pump immersed in the waste, directed at varying angles and operated at different speeds and time durations. Tank and supporting instrumentation is brought into the DACS to monitor the status of the tank and to provide information on the effectiveness of the mitigation test. Instrumentation is also provided for closed loop control of the pump operation. DACS is also capable for being expanded to control and monitor other mitigation testing. The intended audience for the computer system requirements specification includes the SY-101 hydrogen mitigation test data acquisition and control system designers: analysts, programmers, instrument engineers, operators, maintainers. It is intended for the data users: tank farm operations, mitigation test engineers, the Test Review Group (TRG), data management support staff, data analysis, Hanford data stewards, and external reviewers

  15. 40 CFR 80.591 - What are the product transfer document requirements for additives to be used in diesel fuel?

    Science.gov (United States)

    2010-07-01

    ... Motor Vehicle Diesel Fuel; Nonroad, Locomotive, and Marine Diesel Fuel; and ECA Marine Fuel... content requirements for use in diesel motor vehicles and nonroad engines.”; or (2) For those additives... requirements for use in model year 2007 and newer diesel motor vehicles or model year 2011 and newer diesel...

  16. IDC System Specification Document Version 1.1.

    Energy Technology Data Exchange (ETDEWEB)

    Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Lober, Randall R. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2015-02-01

    This document contains the system specifications derived to satisfy the system requirements found in the IDC System Requirements Document for the IDC Reengineering Phase 2 project. Revisions Version Date Author/Team Revision Description Authorized by V1.0 12/2014 IDC Reengineering Project Team Initial delivery M. Harris V1.1 2/2015 IDC Reengineering Project Team Iteration I2 Review Comments M. Harris

  17. Tree cover and aridity projections to 2060: a technical document supporting the Forest Service 2010 RPA assessment

    Science.gov (United States)

    Eric J. Greenfield; David J. Nowak

    2013-01-01

    Future projections of tree cover and climate change are useful to natural resource managers as they illustrate potential changes to our natural resources and the ecosystem services they provide. This report a) details three projections of tree cover change across the conterminous United States based on predicted land-use changes from 2000 to 2060; b) evaluates nine...

  18. AN APPROACH TO REDUCE THE STORAGE REQUIREMENT FOR BIOMETRIC DATA IN AADHAR PROJECT

    Directory of Open Access Journals (Sweden)

    T. Sivakumar

    2013-02-01

    Full Text Available AADHAR is an Indian Government Project to provide unique identification to each Citizen of India. The objective of the project is to collect all the personal details and the biometric traits from each individual. Biometric traits such as iris, face and fingerprint are being collected for authentication. All the information will be stored in a centralized data repository. Considering about the storage requirement for the biometric data of the entire population of India, approximately 20,218 TB of storage space will be required. Since 10 fingerprint data are stored, fingerprint details will take most of the space. In this paper, the storage requirement for the biometric data in the AADHAR project is analyzed and a method is proposed to reduce the storage by cropping the original biometric image before storing. This method can reduce the storage space of the biometric data drastically. All the measurements given in this paper are approximate only.

  19. KWIKPLAN: a computer program for projecting the annual requirements of nuclear fuel cycle operations

    International Nuclear Information System (INIS)

    Salmon, R.; Kee, C.W.

    1977-06-01

    The computer code KWIKPLAN was written to facilitate the calculation of projected nuclear fuel cycle activities. Using given projections of power generation, the code calculates annual requirements for fuel fabrication, fuel reprocessing, uranium mining, and plutonium use and production. The code uses installed capacity projections and mass flow data for six types of reactors to calculate projected fuel cycle activities and inventories. It calculates fissile uranium and plutonium flows and inventories after allowing for an economy with limited reprocessing capacity and a backlog of unreprocessed fuel. All calculations are made on a quarterly basis; printed and punched output of the projected fuel cycle activities are made on an annual basis. Since the punched information is used in another code to determine waste inventories, the code punches a table from which the effective average burnup can be calculated for the fuel being reprocessed

  20. Is Your Biobank Up to Standards? A Review of the National Canadian Tissue Repository Network Required Operational Practice Standards and the Controlled Documents of a Certified Biobank.

    Science.gov (United States)

    Hartman, Victoria; Castillo-Pelayo, Tania; Babinszky, Sindy; Dee, Simon; Leblanc, Jodi; Matzke, Lise; O'Donoghue, Sheila; Carpenter, Jane; Carter, Candace; Rush, Amanda; Byrne, Jennifer; Barnes, Rebecca; Mes-Messons, Anne-Marie; Watson, Peter

    2018-02-01

    Ongoing quality management is an essential part of biobank operations and the creation of high quality biospecimen resources. Adhering to the standards of a national biobanking network is a way to reduce variability between individual biobank processes, resulting in cross biobank compatibility and more consistent support for health researchers. The Canadian Tissue Repository Network (CTRNet) implemented a set of required operational practices (ROPs) in 2011 and these serve as the standards and basis for the CTRNet biobank certification program. A review of these 13 ROPs covering 314 directives was conducted after 5 years to identify areas for revision and update, leading to changes to 7/314 directives (2.3%). A review of all internal controlled documents (including policies, standard operating procedures and guides, and forms for actions and processes) used by the BC Cancer Agency's Tumor Tissue Repository (BCCA-TTR) to conform to these ROPs was then conducted. Changes were made to 20/106 (19%) of BCCA-TTR documents. We conclude that a substantial fraction of internal controlled documents require updates at regular intervals to accommodate changes in best practices. Reviewing documentation is an essential aspect of keeping up to date with best practices and ensuring the quality of biospecimens and data managed by biobanks.

  1. Criteria Document for B-plant's Surveillance and Maintenance Phase Safety Basis Document

    International Nuclear Information System (INIS)

    SCHWEHR, B.A.

    1999-01-01

    This document is required by the Project Hanford Managing Contractor (PHMC) procedure, HNF-PRO-705, Safety Basis Planning, Documentation, Review, and Approval. This document specifies the criteria that shall be in the B Plant surveillance and maintenance phase safety basis in order to obtain approval of the DOE-RL. This CD describes the criteria to be addressed in the S and M Phase safety basis for the deactivated Waste Fractionization Facility (B Plant) on the Hanford Site in Washington state. This criteria document describes: the document type and format that will be used for the S and M Phase safety basis, the requirements documents that will be invoked for the document development, the deactivated condition of the B Plant facility, and the scope of issues to be addressed in the S and M Phase safety basis document

  2. Requirement Volatility, Standardization and Knowledge Integration in Software Projects: An Empirical Analysis on Outsourced IS Development Projects

    Directory of Open Access Journals (Sweden)

    Rajesri Govindaraju

    2015-08-01

    Full Text Available Information systems development (ISD projects are highly complex, with different groups of people having  to collaborate and exchange their knowledge. Considering the intensity of knowledge exchange that takes place in outsourced ISD projects, in this study a conceptual model was developed, aiming to examine the influence of four antecedents, i.e. standardization, requirement volatility, internal integration, and external integration, on two dependent variables, i.e. process performance and product performance. Data  were collected from 46 software companies in four big cities in Indonesia. The collected data were examined to verify the proposed theoretical model using the partial least square structural equation modeling (PLS-SEM technique. The results show that process performance is significantly influenced by internal integration and standardization, while product performance is  significantly influenced by external integration and  requirement volatility. This study contributes  to a better understanding of how knowledge integration can be managed in outsourced ISD projects in view of increasing their success.

  3. Spent nuclear fuel project multi-canister overpack, additional NRC requirements

    International Nuclear Information System (INIS)

    Garvin, L.J.

    1998-01-01

    The US Department of Energy (DOE), established in the K Basin Spent Nuclear Fuel Project Regulatory Policy, dated August 4, 1995 (hereafter referred to as the Policy), the requirement for new Spent Nuclear Fuel (SNF) Project facilities to achieve nuclear safety equivalency to comparable US Nuclear Regulatory Commission (NRC)-licensed facilities. For activities other than during transport, when the Multi-Canister Overpack (MCO) is used and resides in the Canister Storage Building (CSB), Cold Vacuum Drying (CVD) facility or Hot Conditioning System, additional NRC requirements will also apply to the MCO based on the safety functions it performs and its interfaces with the SNF Project facilities. An evaluation was performed in consideration of the MCO safety functions to identify any additional NRC requirements needed, in combination with the existing and applicable DOE requirements, to establish nuclear safety equivalency for the MCO. The background, basic safety issues and general comparison of NRC and DOE requirements for the SNF Project are presented in WHC-SD-SNF-DB-002

  4. Documentation of Cultural Heritage Objects

    Directory of Open Access Journals (Sweden)

    Jon Grobovšek

    2013-09-01

    Full Text Available EXTENDED ABSTRACT:The first and important phase of documentation of cultural heritage objects is to understand which objects need to be documented. The entire documentation process is determined by the characteristics and scope of the cultural heritage object. The next question to be considered is the expected outcome of the documentation process and the purpose for which it will be used. These two essential guidelines determine each stage of the documentation workflow: the choice of the most appropriate data capturing technology and data processing method, how detailed should the documentation be, what problems may occur, what the expected outcome is, what it will be used for, and the plan for storing data and results. Cultural heritage objects require diverse data capturing and data processing methods. It is important that even the first stages of raw data capturing are oriented towards the applicability of results. The selection of the appropriate working method can facilitate the data processing and the preparation of final documentation. Documentation of paintings requires different data capturing method than documentation of buildings or building areas. The purpose of documentation can also be the preservation of the contemporary cultural heritage to posterity or the basis for future projects and activities on threatened objects. Documentation procedures should be adapted to our needs and capabilities. Captured and unprocessed data are lost unless accompanied by additional analyses and interpretations. Information on tools, procedures and outcomes must be included into documentation. A thorough analysis of unprocessed but accessible documentation, if adequately stored and accompanied by additional information, enables us to gather useful data. In this way it is possible to upgrade the existing documentation and to avoid data duplication or unintentional misleading of users. The documentation should be archived safely and in a way to meet

  5. SNF project's MCO compliance assessment with DOE ''general design criteria,'' order 6430.1A and ''SNF project MCO additional NRC requirements,'' HNF-SD-SNF-DB-005

    International Nuclear Information System (INIS)

    GOLDMANN, L.H.

    1999-01-01

    This document is presented to demonstrate the MCOs compliance to the major design criteria invoked on the MCO. This document is broken down into a section for the MCO's evaluation against DOE Order 6430.1A General Design Criteria sixteen divisions and then the evaluation of the MCO against HNF-SD-SNF-DB-005 ''Spent Nuclear Fuel Project Multi-Canister Overpack Additional NRC Requirements.'' The compliance assessment is presented as a matrix in tabular form. The MCO is the primary container for the K-basin's spent nuclear fuel as it leaves the basin pools and through to the 40 year interim storage at the Canister Storage Building (CSB). The MCO and its components interface with; the K basins, shipping cask and transportation system, Cold Vacuum Drying facility individual process bays and equipment, and CSB facility including the MCO handling machine (MHM), the storage tubes, and the MCO work stations where sampling, welding, and inspection of the MCO is performed. As the MCO is the primary boundary for handling, process, and storage, its main goals are to minimize the spread of its radiological contents to the outside of the MCO and provide for nuclear criticality control. The MCO contains personnel radiation shielding only on its upper end, in the form of a shield plug, where the process interfaces are located. Shielding beyond the shield plug is the responsibility of the using facilities. The design of the MCO and its components is depicted in drawings H-2-828040 through H-2-828075. Not every drawing number in the sequence is used. The first drawing number, H-2-828040, is the drawing index for the MCO. The design performance specification for the MCO is HW-S-0426, and was reviewed and approved by the interfacing design authorities, the safety, regulatory, and operations groups, and the local DOE office. The current revision for the design performance specification is revision 5. The designs of the MCO have been reviewed and approved in a similar way and the reports

  6. Projected irrigation requirements for upland crops using soil moisture model under climate change in South Korea

    Science.gov (United States)

    An increase in abnormal climate change patterns and unsustainable irrigation in uplands cause drought and affect agricultural water security, crop productivity, and price fluctuations. In this study, we developed a soil moisture model to project irrigation requirements (IR) for upland crops under cl...

  7. 75 FR 41875 - Technical Processing Requirements for Multifamily Project Mortgage Insurance

    Science.gov (United States)

    2010-07-19

    ... is used to determine if key principals are acceptable and have the ability to manage the development... principals are acceptable and have the ability to manage the development, construction, completion, and... Requirements for Multifamily Project Mortgage Insurance AGENCY: Office of the Chief Information Officer, HUD...

  8. Capstone Interdisciplinary Team Project: A Requirement for the MS in Sustainability Degree

    Science.gov (United States)

    Jiji, Latif M.; Schonfeld, Irvin Sam; Smith, George A.

    2015-01-01

    Purpose: This paper aims to describe experience gained with a required six-credit year-long course, the Capstone Interdisciplinary Team Project, a key component of the Master of Science (MS) in Sustainability degree at the City College of New York. A common feature of sustainability problems is their interdisciplinary nature. Solutions to…

  9. A Quantitative Study of Global Software Development Teams, Requirements, and Software Projects

    Science.gov (United States)

    Parker, Linda L.

    2016-01-01

    The study explored the relationship between global software development teams, effective software requirements, and stakeholders' perception of successful software development projects within the field of information technology management. It examined the critical relationship between Global Software Development (GSD) teams creating effective…

  10. 34 CFR 350.10 - What are the general requirements for Disability and Rehabilitation Research Projects?

    Science.gov (United States)

    2010-07-01

    ... more of the following types of activities, as specified in §§ 350.13-350.19: (1) Research. (2... 34 Education 2 2010-07-01 2010-07-01 false What are the general requirements for Disability and Rehabilitation Research Projects? 350.10 Section 350.10 Education Regulations of the Offices of the Department of...

  11. 7 CFR 4280.29 - Supplemental financing required for the Ultimate Recipient Project.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 15 2010-01-01 2010-01-01 false Supplemental financing required for the Ultimate Recipient Project. 4280.29 Section 4280.29 Agriculture Regulations of the Department of Agriculture... AND GRANTS Rural Economic Development Loan and Grant Programs § 4280.29 Supplemental financing...

  12. Projecting county-level populations under three future scenarios: a technical document supporting the Forest Service 2010 RPA Assessment

    Science.gov (United States)

    Stanley J. Zarnoch; H. Ken Cordell; Carter J. Betz

    2010-01-01

    County-level population projections from 2010 to 2060 are developed under three national population growth scenarios for reporting in the 2010 Renewable Resources Planning Act (RPA) Assessment. These population growth scenarios are tied to global futures scenarios defined by the Intergovernmental Panel on Climate Change (IPCC), a program within the United Nations...

  13. SigmaPlot 2000, Version 6.00, SPSS Inc. Computer Software Project Management, Requirements, and Design Document

    Energy Technology Data Exchange (ETDEWEB)

    HURLBUT, S.T.

    2000-10-24

    SigmaPlot is a vendor software product that will be used to convert the area under an absorbance curve generated by a Fourier transform infrared spectrometer (FTIR) to a relative area. SigmaPlot will be used in conjunction with procedure ZA-565-301, ''Determination of Moisture by Supercritical Fluid Extraction and Infrared Detection.''

  14. Systems Engineering Plan and project record Configuration Management Plan for the Mixed Waste Disposal Initiative

    International Nuclear Information System (INIS)

    Bryan, W.E.; Oakley, L.B.

    1993-04-01

    This document summarizes the systems engineering assessment that was performed for the Mixed Waste Disposal Initiative (MWDI) Project to determine what types of documentation are required for the success of the project. The report also identifies the documents that will make up the MWDI Project Record and describes the Configuration Management Plan describes the responsibilities and process for making changes to project documentation

  15. Mobile health systems for bipolar disorder: the relevance of non-functional requirements in MONARCA project

    DEFF Research Database (Denmark)

    Mayora, Oscar; Frost, Mads; Arnrich, Bert

    2016-01-01

    This paper presents a series of challenges for developing mobile health solutions for mental health as a result of MONARCA project three-year activities. The lessons learnt on the design, development and evaluation of a mobile health system for supporting the treatment of bipolar disorder....... The findings presented here are the result of over 3 years of activity within the MONARCA EU project. The challenges listed and detailed in this paper may be used in future research as a starting point for identifying important non-functional requirements involved in mobile health provisioning...

  16. Crosscutting Requirements in the International Project on Innovative Reactors and Fuel Cycles (INPRO)

    International Nuclear Information System (INIS)

    Steur, Ronald; Lyubenov Yaven, Yanko; Gueorguiev, Boris; Mahadeva, Rao; Shen, Wenquan

    2002-01-01

    There are two categories of requirements: (i) user requirements that need to be met by the designers and manufacturers of innovative reactors and fuel cycles, and (ii) a wide spectrum of requirements that need to be met by countries, willing to successfully deploy innovative nuclear reactors for energy production. This part of the International Project on Innovative Reactors and Fuel Cycles will mainly deal with the second category of requirements. Both categories of requirements will vary depending on the institutional development, infrastructure availability and social attitude in any given country. Out of the need for sustainable development requirements will also more specific in the future. Over a 50-year time frame both categories of requirements will evolve with social and economic development as nuclear technology develops further. For example, the deployment of innovative reactors in countries with marginal or non-existing nuclear infrastructures would be possible only if the reactors are built, owned and operated by an international nuclear utility or if they are inherently safe and can be delivered as a 'black box - nuclear battery'. A number of issues will need to be addressed and conditions and requirements developed if this is going to become a reality. One general requirement for wider utilization of innovative nuclear power will be the public and environmental considerations, which will play a role in the decision making processes. Five main clusters of topics will be handled: - Infra-structural aspects, typology and consequences for nuclear development. - Industrial requirements for the different innovative concepts. - Institutional developments and requirements for future deployment of nuclear energy. (National as well as international) - Socio-political aspects, a.o. public acceptance and role of governments. - Sustainability: requirements following the need for sustainability Analysis will be made of the evolution of national and international

  17. 75 FR 10258 - Notice of a Project Waiver of Section 1605: (Buy American Requirement) of the American Recovery...

    Science.gov (United States)

    2010-03-05

    ... recovery by funding current infrastructure construction, not to delay shovel ready projects by requiring... would result in unreasonable delay and thus displace the ``shovel ready'' status for this project...

  18. Functions and Requirements for West Valley Demonstration Project Tank Lay-up

    International Nuclear Information System (INIS)

    Elmore, Monte R.; Henderson, Colin

    2002-01-01

    Documents completion of Milestone A.1-1, ''Issue Functions and Requirements for WVDP Tank Lay-Up,'' in Technical Task Plan TTP RL3-WT21A - ''Post-Retrieval and Pre-Closure HLW Tank Lay-Up.'' This task is a collaborative effort among Pacific Northwest National Laboratory, Jacobs Engineering Group Inc., and West Valley Nuclear Services (WVNS). Because of the site-specific nature of this task, the involvement of WVNS personnel is critical to the success of this task

  19. Environmental restoration value engineering guidance document

    International Nuclear Information System (INIS)

    1995-07-01

    This document provides guidance on Value Engineering (VE). VE is an organized team effort led by a person trained in the methodology to analyze the functions of projects, systems, equipment, facilities, services, and processes for achieving the essential functions at the lowest life cycle cost while maintaining required performance, reliability, availability, quality, and safety. VE has proven to be a superior tool to improve up-front project planning, cut costs, and create a better value for each dollar spent. This document forms the basis for the Environmental Restoration VE Program, describes the VE process, and provides recommendations on when it can be most useful on ER projects

  20. Cold vacuum drying facility design requirements

    Energy Technology Data Exchange (ETDEWEB)

    Irwin, J.J.

    1997-09-24

    This release of the Design Requirements Document is a complete restructuring and rewrite to the document previously prepared and released for project W-441 to record the design basis for the design of the Cold Vacuum Drying Facility.

  1. Cold vacuum drying facility design requirements

    International Nuclear Information System (INIS)

    Irwin, J.J.

    1997-01-01

    This release of the Design Requirements Document is a complete restructuring and rewrite to the document previously prepared and released for project W-441 to record the design basis for the design of the Cold Vacuum Drying Facility

  2. Surveillance Analysis Computer System (SACS) software requirements specification (SRS)

    International Nuclear Information System (INIS)

    Glasscock, J.A.; Flanagan, M.J.

    1995-09-01

    This document is the primary document establishing requirements for the Surveillance Analysis Computer System (SACS) Database, an Impact Level 3Q system. The purpose is to provide the customer and the performing organization with the requirements for the SACS Project

  3. Government programs for climate change mitigation in Japan. An analysis based on public budget documents and Government Project Review Sheets

    International Nuclear Information System (INIS)

    Kimura, Osamu

    2016-01-01

    The Japanese government has been spending huge public budgets for various programs to mitigate climate change, such as subsidy programs for energy efficient and renewable technologies, and R and D programs to develop innovative low carbon technologies. This report makes a comprehensive review of government projects and expenditure related to climate change mitigation in order to grasp their total expenditure and to analyze portfolio of supported technology and activity types, outcome, and the cost-effectiveness. It is estimated that the total expenditure for climate change mitigation excluding nuclear energy and forest sink projects amounts to 4.8 trillion JPY (approximately 40 billion USD) in the period of 2008 to 2014. 40% of the total expenditure went to only three largest programs, namely the Eco Car Subsidy, the Eco Point Programs for Appliances and Houses, all of which have gone through virtually no or only poor evaluations by the implementing ministries. While some programs had decent cost-effectiveness of reducing carbon dioxide emission at below 10,000 JPY/t-CO 2 (approximately 90 USD), there are also programs with very low cost-effectiveness at more than 100,000 JPY/t-CO 2 . Moreover, all of the evaluation was based on 'gross' reduction, not on 'net' of freeriders, rebound and other factors, which may lead to overestimation of performances. The result shows the need for a much larger resource for evaluation activities by the government. (author)

  4. A Systematic Mapping on Supporting Approaches for Requirements Traceability in the Context of Software Projects

    Directory of Open Access Journals (Sweden)

    MALCHER, P R.C.

    2015-12-01

    Full Text Available The Requirements Traceability is seen as a quality factor with regard to software development, being present in standards and quality models. In this context, several techniques, models, frameworks and tools have been used to support it. Thus, the purpose of this paper is to present a systematic mapping carried out in order to find in the literature approaches to support the requirements traceability in the context of software projects and make the categorization of the data found in order to demonstrate, by means of a reliable, accurate and auditable method, how this area has developed and what are the main approaches are used to implement it.

  5. Application of Total Quality Management (TQM Requirements in Risk Management in Construction Projects in Iraq

    Directory of Open Access Journals (Sweden)

    Entisar K. Al-Geelawee

    2016-06-01

    Full Text Available Total quality management considers one of the modern scientific entrances which practiced by productivity service organizations alike to provide appropriate quality required outputs according to the needs and desires of customers manage , enable the organization seeking to continue and grow in light of the increasing competition from the satisfy and provide the appropriate total quality management requirements whenever led to face risks that they may have in a manner in which they can be addressed and find ways to avoid them in the future when repeated. The research has consist of two main parts firstly have included a review of the most important concepts of total quality management in addition to the concept of risk analysis and management in construction projects and how to apply the concept of total quality management in the risk analysis and management. Second part included the practical part of the research, which was open and closed questionnaire for experts in the construction industry to obtain required informations for the application of total quality management requirements in risk management in construction projects in Iraq. One of the main findings of the research is that top management support has a high impact on risk management in addition to continuous improvement, training and education, while the participation of all employees in the organization and constant stimulation and focusing on the customer as one of the total quality management requirements had a moderate impact on risk management.

  6. NASA software documentation standard software engineering program

    Science.gov (United States)

    1991-01-01

    The NASA Software Documentation Standard (hereinafter referred to as Standard) can be applied to the documentation of all NASA software. This Standard is limited to documentation format and content requirements. It does not mandate specific management, engineering, or assurance standards or techniques. This Standard defines the format and content of documentation for software acquisition, development, and sustaining engineering. Format requirements address where information shall be recorded and content requirements address what information shall be recorded. This Standard provides a framework to allow consistency of documentation across NASA and visibility into the completeness of project documentation. This basic framework consists of four major sections (or volumes). The Management Plan contains all planning and business aspects of a software project, including engineering and assurance planning. The Product Specification contains all technical engineering information, including software requirements and design. The Assurance and Test Procedures contains all technical assurance information, including Test, Quality Assurance (QA), and Verification and Validation (V&V). The Management, Engineering, and Assurance Reports is the library and/or listing of all project reports.

  7. Capital planning for operating theatres based on projecting future theatre requirements.

    Science.gov (United States)

    Sheehan, Jennifer A; Tyler, Peter; Jayasinha, Hirani; Meleady, Kathleen T; Jones, Neill

    2011-05-01

    During 2006, NSW and ACT Health Departments jointly engaged KPMG to develop an Operating Theatre Requirements' Projection Model and an accompanying planning guideline. A research scan was carried out to identify drivers of surgical demand, theatre capacity and theatre performance, as well as locating existing approaches to modelling operating theatre requirements for planning purposes. The project delivered a Microsoft Excel-based model for projecting future operating theatre requirements, together with an accompanying guideline for use of the model and interpretation of its outputs. It provides a valuable addition to the suite of tools available to Health staff for service and capital planning. The model operates with several limitations, largely due to being data dependent, and the state and completeness of available theatre activity data. However, the operational flexibility built into the model allows users to compensate for these limitations, on a case by case basis, when the user has access to suitable, local data. The design flexibility of the model means that updating the model as improved data become available is not difficult; resulting in revisions being able to be made quickly, and disseminated to users rapidly.

  8. Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 3 with Errata Sheet

    Energy Technology Data Exchange (ETDEWEB)

    Tim Echelard

    2006-03-01

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for Corrective Action Unit (CAU) 447, Project Shoal Area (PSA)-Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Springs Mountains in Churchill County, Nevada, approximately 48 kilometers (30 miles) southeast of Fallon, Nevada. The CADD/CAP combines the decision document (CADD) with the Corrective Action Plan (CAP) and provides or references the specific information necessary to recommend corrective actions for CAU 447, as provided in the FFACO. Corrective Action Unit 447 consists of two corrective action sites (CASs): CAS 57-49-01, Emplacement Shaft, and CAS 57-57-001, Cavity. The emplacement shaft (CAS-57-49-01) was backfilled and plugged in 1996 and will not be evaluated further. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at PSA. To achieve this, the following tasks were required: (1) Develop corrective action objectives. (2) Identify corrective action alternative screening criteria. (3) Develop corrective action alternatives. (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria. (5) Recommend a preferred corrective action alternative for the subsurface at PSA. The original Corrective Action Investigation Plan (CAIP) for the PSA was approved in September 1996 and described a plan to drill and test four characterization wells, followed by flow and transport modeling (DOE/NV, 1996). The resultant drilling is described in a data report (DOE/NV, 1998e) and the data analysis and modeling in an interim modeling report (Pohll et al., 1998). After considering the results of the modeling effort

  9. SNF AGING SYSTEM DESCRIPTION DOCUMENT

    Energy Technology Data Exchange (ETDEWEB)

    L.L. Swanson

    2005-04-06

    The purpose of this system description document (SDD) is to establish requirements that drive the design of the spent nuclear fuel (SNF) aging system and associated bases, which will allow the design effort to proceed. This SDD will be revised at strategic points as the design matures. This SDD identifies the requirements and describes the system design, as it currently exists, with emphasis on attributes of the design provided to meet the requirements. This SDD is an engineering tool for design control; accordingly, the primary audience and users are design engineers. This SDD is part of an iterative design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. The SDD follows the design with regard to the description of the system. The description provided in the SDD reflects the current results of the design process. Throughout this SDD, the term aging cask applies to vertical site-specific casks and to horizontal aging modules. The term overpack is a vertical site-specific cask that contains a dual-purpose canister (DPC) or a disposable canister. Functional and operational requirements applicable to this system were obtained from ''Project Functional and Operational Requirements'' (F&OR) (Curry 2004 [DIRS 170557]). Other requirements that support the design process were taken from documents such as ''Project Design Criteria Document'' (PDC) (BSC 2004 [DES 171599]), ''Site Fire Hazards Analyses'' (BSC 2005 [DIRS 172174]), and ''Nuclear Safety Design Bases for License Application'' (BSC 2005 [DIRS 171512]). The documents address requirements in the ''Project Requirements Document'' (PRD) (Canori and Leitner 2003 [DIRS 166275]). This SDD includes several appendices. Appendix A is a Glossary; Appendix B is a list of key system charts

  10. Guideline on radiation protection in medicine requires documentation of radioiodine therapy and follow-up. What are the benefits of an electronic database?

    International Nuclear Information System (INIS)

    Koch, W.; Rosa, F.; Knesewitsch, P.; Hahn, K.

    2005-01-01

    The lately updated German guideline on radiation protection in medicine (Richtlinie Strahlenschutz in der Medizin) requires the physician who administers radioactive substances for therapy, to perform and document follows-up. In order to decrease the administrative burden, an electronic database was developed that interfaces with a word processing software to generate written reports and statistic analysis. Methods: Based on Microsoft registered Access and Microsoft registered Visual Basic a database was created to monitor patients with benign and malignant thyroid disorders after radioiodine therapy. It permits automatic creation of therapy documents and necessary patient reports in Microsoft registered Word. Intuitive handling, third level of normalization in database architecture and automatic plausibility checks guarantee integrity of the data and the efficacy of the database. Results, conclusion: The new software has been a success in over 1500 patients and over 3800 in- and outpatient therapies and visits. The effort of data entry is easily offset by the automatic generation of the necessary patient reports. The required supervision of the follow-up appointments is now also user-friendly and efficient. (orig.)

  11. Automated Test Requirement Document Generation

    Science.gov (United States)

    1987-11-01

    DIAGNOSTICS BASED ON THE PRINCIPLES OF ARTIFICIAL INTELIGENCE ", 1984 International Test Conference, 01Oct84, (A3, 3, Cs D3, E2, G2, H2, 13, J6, K) 425...j0O GLOSSARY OF ACRONYMS 0 ABBREVIATION DEFINITION AFSATCOM Air Force Satellite Communication Al Artificial Intelligence ASIC Application Specific...In-Test Equipment (BITE) and AI ( Artificial Intelligence) - Expert Systems - need to be fully applied before a completely automated process can be

  12. PROJECTS ON AIRPORTS, AIRFIELDS, HELICOPTER AERODROMES AND LANDING GROUNDS SANITARY PROTECTION AREAS AS THE BASIS OF THEIR ACTIVITY COMPLIANCE ASSESSMENT TO ECOLOGICAL REQUIREMENTS

    Directory of Open Access Journals (Sweden)

    Oleg A. Kartyshev

    2017-01-01

    Full Text Available Ten years experience of the development of domestic airports sanitary protection zones projects in civil aviation based on Sanitary Regulations and Norms 2.2.1/2.1.1.1200-03 requirements is analyzed, the reasons of loss of quality of project works and delaying of coordination terms at the last stage of the development are established. It is shown that among the main reasons for current negative situation with projects development and coordination are: absence of a check algorithm of settlement borders of areas and contours of aviation noise with the use of natural researches methods in Sanitary Regulations and Norms 2.2.1/2.1.1.1200-03; absence of methods of amendment in projects and regulations of establishment of the airport sanitary protection zones final dimensions. Examples of oversized and undersized noise areas and ones of the polluting substances dispersion as well as the reasons of local authorities’ interests in it are given.Conceptional strategies which should be used in the edition of a new Russian conservancy normative document regulating the development of projects on sanitary protection areas. New document will allow to consider various factors of negative environmental impact of the airports, airfields, helicopter aerodromes and landing grounds activities.It is offered to introduce the concept of "aviation noise set index operational card", which will solve the legitimation problem of the aviation noise account in the State Immovable Property Cadaster. Suggestions on equivalent and maximum level magnitude of the sound made at the residential territory of cities and urban-type settlements by flights and aircraft ground operation are given.Standards are supposed to be harmonized with similar international rules and have to provide zone gradation by 5 dBA.Suggestions on the considerations of the revealed deficiencies are made, requirements to project sections structure of sanitary protection zones are formulated, proposals on the

  13. RGMDV: An approach to requirements gathering and the management of data virtualization projects

    Science.gov (United States)

    Mousa, Ayad Hameed; Shiratuddin, Norshuhada; Bakar, Muhamad Shahbani Abu

    2015-12-01

    Data virtualization (DV) refers to a set of data stores that enable users to query, access, and manipulate data in a unified, abstracted, and encapsulated manner regardless of data location. Apart from reducing data movement, this system provides a unified, abstracted, real-time, and encapsulated view of information for query purposes. Through its provision of live, virtual data in a timely manner, the DV technique can overcome the obstacles faced by organizations and companies as a result of using other data integration techniques. The systematic planning for the period that precedes DV deployment enables organizations to avoid many challenges related to manageability, usability, data quality, and performance. DV requirements are among the most significant and challenging aspects of a DV project. In this study, an approach has been developed to gather and manage the requirements of a DV design model as an initial step in developing such projects. Expert methods are reviewed to validate and evaluate the proposed approach in terms of usability and related components; the results of this review demonstrate that the applied approaches benefit DV development projects.

  14. International shock-wave database project : report of the requirements workshop.

    Energy Technology Data Exchange (ETDEWEB)

    Aidun, John Bahram (Institute of Problems of chemical Physics of Russian Academy of Sciences); Lomonosov, Igor V. (Institute of Problems of chemical Physics of Russian Academy of Sciences); Levashov, Pavel R. (Joint Institute for High Temperatures of Russian Academy of Sciences)

    2012-03-01

    We report on the requirements workshop for a new project, the International Shock-Wave database (ISWdb), which was held October 31 - November 2, 2011, at GSI, Darmstadt, Germany. Participants considered the idea of this database, its structure, technical requirements, content, and principles of operation. This report presents the consensus conclusions from the workshop, key discussion points, and the goals and plan for near-term and intermediate-term development of the ISWdb. The main points of consensus from the workshop were: (1) This international database is of interest and of practical use for the shock-wave and high pressure physics communities; (2) Intermediate state information and off-Hugoniot information is important and should be included in ISWdb; (3) Other relevant high pressure and auxiliary data should be included to the database, in the future; (4) Information on the ISWdb needs to be communicated, broadly, to the research community; and (5) Operating structure will consist of an Advisory Board, subject-matter expert Moderators to vet submitted data, and the database Project Team. This brief report is intended to inform the shock-wave research community and interested funding agencies about the project, as its success, ultimately, depends on both of these groups finding sufficient value in the database to use it, contribute to it, and support it.

  15. The HAW project. Test storage of high-level radiation sources in the Asse salt mine. Documentation and assessment of the storage system

    International Nuclear Information System (INIS)

    Mueller, K.; Rothfuchs, T.

    1994-01-01

    The HAW project aimed primarily at studying the interaction between high-level radioactive waste moulds and rock salt as the respository medium. Another priority was the prototype development and testing of a technical system for the emplacement of high-level radioactive moulds in deep storage boreholes. To simulate real high-level radioactive wastes, special high-level radiation sources (Cs-137, Sr-90) were produced in the United States of America under a German-American cooperation contract, for carrying out the tests at the Asse salt mine. The components of the storage system are described, their position and task within the entire handling procedure explained. Questions of radiation protection and accident protection, of functioning and operating reliability, of quality assurance and examination of documents, materials, of manufacture and functioning, and of documentation are dealt with in detail. With a view to the planning of storage techniques for a mine respository, the experience of development and operation is recorded, and recommendation of further developments are given. Problems which arose during work on the HAW project were partly due to test-specific reasons and will not or not in this form occur in a mine respository. It was planned to start the test emplacement in 1987, and it could have been executed in 1993 after appropriate preparation and approval of the storage system by the mining authority and the Hanover TUEV in 1991. In December 1992, however, the Federal Government decided to give up to the project due to the uncertain licensing situation, and to immediately stop all preparatory work. (orig./HP) [de

  16. Regulatory guidance document

    International Nuclear Information System (INIS)

    1994-05-01

    The Office of Civilian Radioactive Waste Management (OCRWM) Program Management System Manual requires preparation of the OCRWM Regulatory Guidance Document (RGD) that addresses licensing, environmental compliance, and safety and health compliance. The document provides: regulatory compliance policy; guidance to OCRWM organizational elements to ensure a consistent approach when complying with regulatory requirements; strategies to achieve policy objectives; organizational responsibilities for regulatory compliance; guidance with regard to Program compliance oversight; and guidance on the contents of a project-level Regulatory Compliance Plan. The scope of the RGD includes site suitability evaluation, licensing, environmental compliance, and safety and health compliance, in accordance with the direction provided by Section 4.6.3 of the PMS Manual. Site suitability evaluation and regulatory compliance during site characterization are significant activities, particularly with regard to the YW MSA. OCRWM's evaluation of whether the Yucca Mountain site is suitable for repository development must precede its submittal of a license application to the Nuclear Regulatory Commission (NRC). Accordingly, site suitability evaluation is discussed in Chapter 4, and the general statements of policy regarding site suitability evaluation are discussed in Section 2.1. Although much of the data and analyses may initially be similar, the licensing process is discussed separately in Chapter 5. Environmental compliance is discussed in Chapter 6. Safety and Health compliance is discussed in Chapter 7

  17. Regulation No. 56/2006 Coll. of the Nuclear Regulatory Authority of the Slovak Republic dated as of January 12, 2006 on details concerning requirements for quality system documentation of authorisation holder, as well as details concerning quality requirements for nuclear installations, details concerning quality requirements for classified equipment and details concerning the scope of their approval

    International Nuclear Information System (INIS)

    2006-01-01

    This Regulation provides details of the requirements for quality system documentation holder, details of the quality requirements for nuclear installations, details concerning quality requirements for classified equipment and details of the scope of their approval. This Regulation came into force on March 1, 2006.

  18. Financing biotechnology projects: lender due diligence requirements and the role of independent technical consultants.

    Science.gov (United States)

    Keller, J B; Plath, P B

    1999-01-01

    An increasing number of biotechnology projects are being brought to commercialization using conventional structured finance sources, which have traditionally only been available to proven technologies and primary industries. Attracting and securing competitive cost financing from mainstream lenders, however, will require the sponsor of a new technology or process to undergo a greater level of due diligence. The specific areas and intensity of investigation, which are typically required by lenders in order to secure long-term financing for biotechnology-based manufacturing systems, is reviewed. The processes for evaluating the adequacy of prior laboratory testing and pilot plant demonstrations is discussed. Particular emphasis is given to scale-up considerations and the ability of the proposed facility design to accommodate significant modifications, in the event that scale-up problems are encountered.

  19. 7 CFR 1753.49 - Closeout documents.

    Science.gov (United States)

    2010-01-01

    ... Construction Change Orders 1 1 224 Waiver and Release of Lien (from each supplier) 1 1 231 Certificate of... by inspection company or supplier) 1 None Final Key Map (when applicable) 1 1 None Final Central... the engineer that the project and all required documentation are satisfactory and complete...

  20. Waste Management System Description Document (WMSD)

    International Nuclear Information System (INIS)

    1992-02-01

    This report is an appendix of the ''Waste Management Description Project, Revision 1''. This appendix is about the interim approach for the technical baseline of the waste management system. It describes the documentation and regulations of the waste management system requirements and description. (MB)

  1. PIT Coating Requirements Analysis

    International Nuclear Information System (INIS)

    MINTEER, D.J.

    2000-01-01

    This study identifies the applicable requirements for procurement and installation of a coating intended for tank farm valve and pump pit interior surfaces. These requirements are intended to be incorporated into project specification documents and design media. This study also evaluates previously recommended coatings and identifies requirement-compliant coating products

  2. PIT Coating Requirements Analysis

    Energy Technology Data Exchange (ETDEWEB)

    MINTEER, D.J.

    2000-10-20

    This study identifies the applicable requirements for procurement and installation of a coating intended for tank farm valve and pump pit interior surfaces. These requirements are intended to be incorporated into project specification documents and design media. This study also evaluates previously recommended coatings and identifies requirement-compliant coating products.

  3. Transcallosal Projections Require Glycoprotein M6-Dependent Neurite Growth and Guidance.

    Science.gov (United States)

    Mita, Sakura; de Monasterio-Schrader, Patricia; Fünfschilling, Ursula; Kawasaki, Takahiko; Mizuno, Hidenobu; Iwasato, Takuji; Nave, Klaus-Armin; Werner, Hauke B; Hirata, Tatsumi

    2015-11-01

    The function of mature neurons critically relies on the developmental outgrowth and projection of their cellular processes. It has long been postulated that the neuronal glycoproteins M6a and M6b are involved in axon growth because these four-transmembrane domain-proteins of the proteolipid protein family are highly enriched on growth cones, but in vivo evidence has been lacking. Here, we report that the function of M6 proteins is required for normal axonal extension and guidance in vivo. In mice lacking both M6a and M6b, a severe hypoplasia of axon tracts was manifested. Most strikingly, the corpus callosum was reduced in thickness despite normal densities of cortical projection neurons. In single neuron tracing, many axons appeared shorter and disorganized in the double-mutant cortex, and some of them were even misdirected laterally toward the subcortex. Probst bundles were not observed. Upon culturing, double-mutant cortical and cerebellar neurons displayed impaired neurite outgrowth, indicating a cell-intrinsic function of M6 proteins. A rescue experiment showed that the intracellular loop of M6a is essential for the support of neurite extension. We propose that M6 proteins are required for proper extension and guidance of callosal axons that follow one of the most complex trajectories in the mammalian nervous system. © The Author 2014. Published by Oxford University Press. All rights reserved. For Permissions, please e-mail: journals.permissions@oup.com.

  4. Preparation of plant and system design description documents

    International Nuclear Information System (INIS)

    1989-01-01

    This standard prescribes the purpose, scope, organization, and content of plant design requirements (PDR) documents and system design descriptions (SDDs), to provide a unified approach to their preparation and use by a project as the principal means to establish the plant design requirements and to establish, describe, and control the individual system designs from conception and throughout the lifetime of the plant. The Electric Power Research Institute's Advanced Light Water Reactor (LWR) Requirements Document should be considered for LWR plants

  5. Specifying semantic information on functional requirements

    OpenAIRE

    YAO, WUPING

    2012-01-01

    Requirements engineering is a challenging process in software development projects. Requirements, in general, are documented in natural language. They often have issues related to ambiguity, completeness and consistency. How to improve the quality of requirements documentation remains a classic research topic. This research aims at improving the way of editing and documenting functional requirements. We propose a meta-model to specify the semantic information of functional requirements, and d...

  6. PUREX Deactivation Health and Safety documentation

    International Nuclear Information System (INIS)

    Dodd, E.N. III.

    1995-01-01

    The purpose of the PUREX Deactivation Project is to establish a passively safe and environmentally secure configuration of PUREX at the Hanford Site, and to preserve that configuration for a 10-year horizon. The 10-year horizon is used to predict future maintenance requirements and represents they typical time duration expended to define, authorize, and initiate the follow-on Decontamination and Decommissioning (D ampersand D) activities. This document was prepared to increase attention to worker safety issues during the deactivation project and, as such, identifies the documentation and programs associated with PUREX Deactivation Health and Safety

  7. PUREX Deactivation Health and Safety documentation

    Energy Technology Data Exchange (ETDEWEB)

    Dodd, E.N. III

    1995-01-01

    The purpose of the PUREX Deactivation Project is to establish a passively safe and environmentally secure configuration of PUREX at the Hanford Site, and to preserve that configuration for a 10-year horizon. The 10-year horizon is used to predict future maintenance requirements and represents they typical time duration expended to define, authorize, and initiate the follow-on Decontamination and Decommissioning (D&D) activities. This document was prepared to increase attention to worker safety issues during the deactivation project and, as such, identifies the documentation and programs associated with PUREX Deactivation Health and Safety.

  8. Traceability and communication of requirements in digital and I and C systems development - Project report 2003[TACO. Reactor safety

    Energy Technology Data Exchange (ETDEWEB)

    Sivertsen, T.; Frederiksen, R.; Thunem, A.P.J. [Institute for Energy Technology (IFE), Kjeller (Norway); Holmberg, J.E.; Valkonen, J.; Ventae, O. [VTT, Espoo (Finland)

    2004-03-01

    The overall objective of the TACO project is to improve the knowledge on principles and best practices related to the issues concretised in the preproject. On basis of experiences in the Nordic countries, the project aims at identifying the best practices and most important criteria for ensuring effective communication in relation to requirements elicitation and analysis, understandability of requirements to all parties, and traceability of requirements through the different design phases. It is expected that the project will provide important input to the development of guidelines and establishment of recommended practices related to these activities. In the year 2003, the TACO-project concentrated on four central issues: 1) Representation of requirements origins. 2) Traceability techniques. 3) Configuration management and the traceability of requirements. 4) Identification and categorisation of system aspects and their models The work was presented at the first TACO Industrial Seminar, which took place in Stockholm on the 12th of December 2003. The seminar was hosted by SKI. (au)

  9. Assessing data quality for a federal environmental restoration project: Rationalizing the requirements of multiple clients

    International Nuclear Information System (INIS)

    Kiszka, V.R.; Carlsen, T.M.

    1994-07-01

    Most environmental restoration projects at federal facilities face the difficult task of melding the quality assurance (QA) requirements of multiple clients, as well as dealing with historical data that are often of unknown quality. At Lawrence Livermore National Laboratory (LLNL), we have successfully integrated the requirements of our multiple clients by carefully developing a QA program that efficiently meets our clients' needs. The Site 300 Experimental Test Site is operated by LLNL in support of its national defense program. The responsibility for conducting environmental contaminant investigations and restoration at Site 300 is vested in the Site 300 Environmental Restoration Project (Site 300 ERP) of LLNL's Environmental Restoration Division. LLNL Site 300 ERP must comply with the QA requirements of several clients, which include: the LLNL Environmental Protection Department, the DOE, the US Environmental Protection Agency-Region IX (EPA), the California Regional Water Quality Control Board -- Central Valley Region, and the California Department of Toxic Substances Control. This comprehensive QA program was used to determine the acceptability of historical data. The Site 300 ERP began soil and ground water investigations in 1982. However, we did not begin receiving analytical quality assurance/quality control (QA/QC) data until 1989; therefore, the pre-1989 data that were collected are of unknown quality. The US EPA QAMS-005/80 defines data quality as the totality of features and characteristics of data that bears on its ability to satisfy a given purpose. In the current context, the characteristics of major importance are accuracy, precision, completeness, representativeness, and comparability. Using our established QA program, we determined the quality of this historical data based on its comparability to the post-1989 data. By accepting this historical data, we were able to save a considerable amount of money in recharacterization costs

  10. MIV project: Architectural Design Document

    DEFF Research Database (Denmark)

    Parisch, Manlio; Paulsen, Thomas Eide; Neefs, Marc

    1997-01-01

    Under the ESA contract #11453/95/NL/JG(SC), aiming at assessing the feasibility of Rendez-vous and docking of unmanned spacecrafts, a reference mission scenario was defined. This report describes the structure of the software produced within the contract...

  11. Contemporary hygienic and engineering requirements to the projecting and exploitation of the positron-emission tomography in medicine

    International Nuclear Information System (INIS)

    Chekmarev, O.; Paltseva, A.

    2004-01-01

    The positron-emission tomography (PET) centres, attached to a large medical establishment as a rule include except PET a compact cyclotron for producing positron-radiant ultra-temporary product radionuclides (carbon-11, Nitrogen-14, oxygen-15, fluorine-18 and etc.) based on water and gaseous targets. At present there are no information about regulating and setting up such medical centres, moreover, requirements which must be presented to the Sanitary Inspection Agency at the documents examination are incompletely represented. During 2001-2003 years specialists of the Moscow Medical Centre (MMC) have been reviewing the hygienic expert examination of the 5 versions of the PET's cabinets installation in therapeutic and prophylactic offices. One of the projects for operating ultra-temporary products is submitted in this report. It foresees the usage of proton beam of the self-protected cyclotron RDS/111 (CTJ PET System (USA)). Its energy of irradiation (proton beam) is 11 MeV. The cyclotron is placed in the additional building of the radiological trunk on the territory of the Moscow Clinical hospital. The technological process of producing the ultra-temporary radionuclides is presented. The block of the radiodiagnostic research include: a treatment room for PET; an operating room; an area for information handling; a treatment room for intake of the radio-pharm-preparations; a filling room; a laboratory for express-analysis of blood before and after research; a WC for patients (with radio-pharm-preparations); and at last - an area for transient (30 - 40 min.) staying for the patients in the lay position before the research. All probable accidents, which can happen in the case of any technology violation, are discussed. There were worked out special requirements to the clarification tanks equipment for liquid radioactive waste and to the time of being a patient in the department after diagnostic researches using fluorine-18

  12. Standardization Documents

    Science.gov (United States)

    2011-08-01

    Specifications and Standards; Guide Specifications; CIDs; and NGSs . Learn. Perform. Succeed. STANDARDIZATION DOCUMENTS Federal Specifications Commercial...national or international standardization document developed by a private sector association, organization, or technical society that plans ...Maintain lessons learned • Examples: Guidance for application of a technology; Lists of options Learn. Perform. Succeed. DEFENSE HANDBOOK

  13. 41 CFR 102-72.65 - What are the requirements for obtaining a delegation of individual repair and alteration project...

    Science.gov (United States)

    2010-07-01

    ... for other individual alteration projects when they demonstrate the ability to perform the delegated... 41 Public Contracts and Property Management 3 2010-07-01 2010-07-01 false What are the requirements for obtaining a delegation of individual repair and alteration project authority from GSA? 102-72...

  14. Project W-320, tank 241-C-106 sluicing acceptance for beneficial use

    International Nuclear Information System (INIS)

    BAILEY, J.W.

    1999-01-01

    The purpose of this document is to identify the Project W-320 Chiller Documentation required to be turned over from the Projects Organization to Tank Farm Operations as part of the acceptance of the new equipment for beneficial use

  15. Designing for Change: Minimizing the Impact of Changing Requirements in the Later Stages of a Spaceflight Software Project

    Science.gov (United States)

    Allen, B. Danette

    1998-01-01

    In the traditional 'waterfall' model of the software project life cycle, the Requirements Phase ends and flows into the Design Phase, which ends and flows into the Development Phase. Unfortunately, the process rarely, if ever, works so smoothly in practice. Instead, software developers often receive new requirements, or modifications to the original requirements, well after the earlier project phases have been completed. In particular, projects with shorter than ideal schedules are highly susceptible to frequent requirements changes, as the software requirements analysis phase is often forced to begin before the overall system requirements and top-level design are complete. This results in later modifications to the software requirements, even though the software design and development phases may be complete. Requirements changes received in the later stages of a software project inevitably lead to modification of existing developed software. Presented here is a series of software design techniques that can greatly reduce the impact of last-minute requirements changes. These techniques were successfully used to add built-in flexibility to two complex software systems in which the requirements were expected to (and did) change frequently. These large, real-time systems were developed at NASA Langley Research Center (LaRC) to test and control the Lidar In-Space Technology Experiment (LITE) instrument which flew aboard the space shuttle Discovery as the primary payload on the STS-64 mission.

  16. Medicinal Chemistry Projects Requiring Imaginative Structure-Based Drug Design Methods.

    Science.gov (United States)

    Moitessier, Nicolas; Pottel, Joshua; Therrien, Eric; Englebienne, Pablo; Liu, Zhaomin; Tomberg, Anna; Corbeil, Christopher R

    2016-09-20

    Computational methods for docking small molecules to proteins are prominent in drug discovery. There are hundreds, if not thousands, of documented examples-and several pertinent cases within our research program. Fifteen years ago, our first docking-guided drug design project yielded nanomolar metalloproteinase inhibitors and illustrated the potential of structure-based drug design. Subsequent applications of docking programs to the design of integrin antagonists, BACE-1 inhibitors, and aminoglycosides binding to bacterial RNA demonstrated that available docking programs needed significant improvement. At that time, docking programs primarily considered flexible ligands and rigid proteins. We demonstrated that accounting for protein flexibility, employing displaceable water molecules, and using ligand-based pharmacophores improved the docking accuracy of existing methods-enabling the design of bioactive molecules. The success prompted the development of our own program, Fitted, implementing all of these aspects. The primary motivation has always been to respond to the needs of drug design studies; the majority of the concepts behind the evolution of Fitted are rooted in medicinal chemistry projects and collaborations. Several examples follow: (1) Searching for HDAC inhibitors led us to develop methods considering drug-zinc coordination and its effect on the pKa of surrounding residues. (2) Targeting covalent prolyl oligopeptidase (POP) inhibitors prompted an update to Fitted to identify reactive groups and form bonds with a given residue (e.g., a catalytic residue) when the geometry allows it. Fitted-the first fully automated covalent docking program-was successfully applied to the discovery of four new classes of covalent POP inhibitors. As a result, efficient stereoselective syntheses of a few screening hits were prioritized rather than synthesizing large chemical libraries-yielding nanomolar inhibitors. (3) In order to study the metabolism of POP inhibitors by

  17. Documentation: Records and Reports.

    Science.gov (United States)

    Akers, Michael J

    2017-01-01

    This article deals with documentation to include the beginning of documentation, the requirements of Good Manufacturing Practice reports and records, and the steps that can be taken to minimize Good Manufacturing Practice documentation problems. It is important to remember that documentation for 503a compounding involves the Formulation Record, Compounding Record, Standard Operating Procedures, Safety Data Sheets, etc. For 503b outsourcing facilities, compliance with Current Good Manufacturing Practices is required, so this article is applicable to them. For 503a pharmacies, one can see the development and modification of Good Manufacturing Practice and even observe changes as they are occurring in 503a documentation requirements and anticipate that changes will probably continue to occur. Copyright© by International Journal of Pharmaceutical Compounding, Inc.

  18. Waste management project technical baseline description

    International Nuclear Information System (INIS)

    Sederburg, J.P.

    1997-01-01

    A systems engineering approach has been taken to describe the technical baseline under which the Waste Management Project is currently operating. The document contains a mission analysis, function analysis, requirement analysis, interface definitions, alternative analysis, system definition, documentation requirements, implementation definitions, and discussion of uncertainties facing the Project

  19. Italian chapter of the International Society of cardiovascular ultrasound expert consensus document on training requirements for noncardiologists using hand-carried ultrasound devices.

    Science.gov (United States)

    Pelliccia, Francesco; Palmiero, Pasquale; Maiello, Maria; Losi, Maria-Angela

    2012-07-01

    Hand-carried ultrasound devices (HCDs), also named personal use echo, are pocket-size, compact, and battery-equipped echocardiographic systems. They have limited technical capabilities but offer some advantages compared with standard echocardiographic devices due to their simplicity of use, immediate availability at the patient's bedside, transportability, and relatively low cost. Current HCDs are considered as screening tools and are used to complement the physical examination by cardiologists. Many noncardiologic subspecialists, however, have adopted this technologic advancement rapidly raising the concern of an inappropriate use of HCD by health professionals who do not have any specific training. In keeping with the mission of the International Society of Cardiovascular Ultrasound to advance the science and art of cardiovascular ultrasound and encourage the knowledge of this subject, the purpose of this Expert Consensus document is to focus on the training for all health care professionals considering the use of HCD. Accordingly, this paper summarizes general aspects of HCD, such as technical characteristics and clinical indications, and then details the specific training requirements for noncardiologists (i.e., training program, minimum case load, duration, and certification of competence). © 2012, Wiley Periodicals, Inc.

  20. Independent Verification and Validation Of SAPHIRE 8 Software Requirements Project Number: N6423 U.S. Nuclear Regulatory Commission

    Energy Technology Data Exchange (ETDEWEB)

    Kent Norris

    2009-09-01

    The purpose of the Independent Verification and Validation (IV&V) role in the evaluation of the SAPHIRE requirements definition is to assess the activities that results in the specification, documentation, and review of the requirements that the software product must satisfy, including functionality, performance, design constraints, attributes and external interfaces. The IV&V team began this endeavor after the software engineering and software development of SAPHIRE had already been in production. IV&V reviewed the requirements specified in the NRC Form 189s to verify these requirements were included in SAPHIRE’s Software Verification and Validation Plan (SVVP).

  1. Software use cases to elicit the software requirements analysis within the ASTRI project

    Science.gov (United States)

    Conforti, Vito; Antolini, Elisa; Bonnoli, Giacomo; Bruno, Pietro; Bulgarelli, Andrea; Capalbi, Milvia; Fioretti, Valentina; Fugazza, Dino; Gardiol, Daniele; Grillo, Alessandro; Leto, Giuseppe; Lombardi, Saverio; Lucarelli, Fabrizio; Maccarone, Maria Concetta; Malaguti, Giuseppe; Pareschi, Giovanni; Russo, Federico; Sangiorgi, Pierluca; Schwarz, Joseph; Scuderi, Salvatore; Tanci, Claudio; Tosti, Gino; Trifoglio, Massimo; Vercellone, Stefano; Zanmar Sanchez, Ricardo

    2016-07-01

    The Italian National Institute for Astrophysics (INAF) is leading the Astrofisica con Specchi a Tecnologia Replicante Italiana (ASTRI) project whose main purpose is the realization of small size telescopes (SST) for the Cherenkov Telescope Array (CTA). The first goal of the ASTRI project has been the development and operation of an innovative end-to-end telescope prototype using a dual-mirror optical configuration (SST-2M) equipped with a camera based on silicon photo-multipliers and very fast read-out electronics. The ASTRI SST-2M prototype has been installed in Italy at the INAF "M.G. Fracastoro" Astronomical Station located at Serra La Nave, on Mount Etna, Sicily. This prototype will be used to test several mechanical, optical, control hardware and software solutions which will be used in the ASTRI mini-array, comprising nine telescopes proposed to be placed at the CTA southern site. The ASTRI mini-array is a collaborative and international effort led by INAF and carried out by Italy, Brazil and South-Africa. We present here the use cases, through UML (Unified Modeling Language) diagrams and text details, that describe the functional requirements of the software that will manage the ASTRI SST-2M prototype, and the lessons learned thanks to these activities. We intend to adopt the same approach for the Mini Array Software System that will manage the ASTRI miniarray operations. Use cases are of importance for the whole software life cycle; in particular they provide valuable support to the validation and verification activities. Following the iterative development approach, which breaks down the software development into smaller chunks, we have analysed the requirements, developed, and then tested the code in repeated cycles. The use case technique allowed us to formalize the problem through user stories that describe how the user procedurally interacts with the software system. Through the use cases we improved the communication among team members, fostered

  2. Spent Nuclear Fuel project stage and store K basin SNF in canister storage building functions and requirements. Revision 1

    International Nuclear Information System (INIS)

    Womack, J.C.

    1995-01-01

    This document establishes the functions and requirements baseline for the implementation of the Canister Storage Building Subproject. The mission allocated to the Canister Storage Building Subproject is to provide safe, environmentally sound staging and storage of K Basin SNF until a decision on the final disposition is reached and implemented

  3. Maury Documentation

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Supporting documentation for the Maury Collection of marine observations. Includes explanations from Maury himself, as well as guides and descriptions by the U.S....

  4. Documentation Service

    International Nuclear Information System (INIS)

    Charnay, J.; Chosson, L.; Croize, M.; Ducloux, A.; Flores, S.; Jarroux, D.; Melka, J.; Morgue, D.; Mottin, C.

    1998-01-01

    This service assures the treatment and diffusion of the scientific information and the management of the scientific production of the institute as well as the secretariat operation for the groups and services of the institute. The report on documentation-library section mentions: the management of the documentation funds, search in international databases (INIS, Current Contents, Inspects), Pret-Inter service which allows accessing documents through DEMOCRITE network of IN2P3. As realizations also mentioned are: the setup of a video, photo database, the Web home page of the institute's library, follow-up of digitizing the document funds by integrating the CD-ROMs and diskettes, electronic archiving of the scientific production, etc

  5. Emergency monitoring strategy and radiation measurements document of the NKS project emergency management and radiation monitoring in nuclear and radiological accidents (EMARAD)

    Energy Technology Data Exchange (ETDEWEB)

    Lahtinen, J. [Radiation and Nuclear Safety Authority (STUK) (Finland)

    2006-04-15

    This report is one of the deliverables of the NKS Project Emergency management and radiation monitoring in nuclear and radiological accidents (EMARAD) (20022005). The project and the overall results are briefly described in the NKS publication 'Emergency Management and Radiation Monitoring in Nuclear and Radiological Accidents. Summary Report on the NKS Project EMARAD' (NKS-137, April 2006). In a nuclear or radiological emergency, all radiation measurements must be performed efficiently and the results interpreted correctly in order to provide the decision-makers with adequate data needed in analysing the situation and carrying out countermeasures. Managing measurements in different situations in a proper way requires the existence of pre-prepared emergency monitoring strategies. Preparing a comprehensive yet versatile strategy is not an easy task to perform because there are lots of different factors that have to be taken into account. The primary objective of this study was to discuss the general problematics concerning emergency monitoring strategies and to describe a few important features of an efficient emergency monitoring system as well as factors affecting measurement activities in practise. Some information concerning the current situation in the Nordic countries has also been included. (au)

  6. Emergency monitoring strategy and radiation measurements. Working document of the NKS project emergency management and radiation monitoring in nuclear and radiological accidents (EMARAD)

    International Nuclear Information System (INIS)

    Lahtinen, J.

    2006-04-01

    This report is one of the deliverables of the NKS Project Emergency management and radiation monitoring in nuclear and radiological accidents (EMARAD) (20022005). The project and the overall results are briefly described in the NKS publication 'Emergency Management and Radiation Monitoring in Nuclear and Radiological Accidents. Summary Report on the NKS Project EMARAD' (NKS-137, April 2006). In a nuclear or radiological emergency, all radiation measurements must be performed efficiently and the results interpreted correctly in order to provide the decision-makers with adequate data needed in analysing the situation and carrying out countermeasures. Managing measurements in different situations in a proper way requires the existence of pre-prepared emergency monitoring strategies. Preparing a comprehensive yet versatile strategy is not an easy task to perform because there are lots of different factors that have to be taken into account. The primary objective of this study was to discuss the general problematics concerning emergency monitoring strategies and to describe a few important features of an efficient emergency monitoring system as well as factors affecting measurement activities in practise. Some information concerning the current situation in the Nordic countries has also been included. (au)

  7. Computerising documentation

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    The nuclear power generation industry is faced with public concern and government pressures over safety, efficiency and risk. Operators throughout the industry are addressing these issues with the aid of a new technology - technical document management systems (TDMS). Used for strategic and tactical advantage, the systems enable users to scan, archive, retrieve, store, edit, distribute worldwide and manage the huge volume of documentation (paper drawings, CAD data and film-based information) generated in building, maintaining and ensuring safety in the UK's power plants. The power generation industry has recognized that the management and modification of operation critical information is vital to the safety and efficiency of its power plants. Regulatory pressure from the Nuclear Installations Inspectorate (NII) to operate within strict safety margins or lose Site Licences has prompted the need for accurate, up-to-data documentation. A document capture and management retrieval system provides a powerful cost-effective solution, giving rapid access to documentation in a tightly controlled environment. The computerisation of documents and plans is discussed in this article. (Author)

  8. Applications for electronic documents

    International Nuclear Information System (INIS)

    Beitel, G.A.

    1995-01-01

    This paper discusses the application of electronic media to documents, specifically Safety Analysis Reports (SARs), prepared for Environmental Restoration and Waste Management (ER ampersand WM) programs being conducted for the Department of Energy (DOE) at the Idaho National Engineering Laboratory (INEL). Efforts are underway to upgrade our document system using electronic format. To satisfy external requirements (DOE, State, and Federal), ER ampersand WM programs generate a complement of internal requirements documents including a SAR and Technical Safety Requirements along with procedures and training materials. Of interest, is the volume of information and the difficulty in handling it. A recently prepared ER ampersand WM SAR consists of 1,000 pages of text and graphics; supporting references add 10,000 pages. Other programmatic requirements documents consist of an estimated 5,000 pages plus references

  9. Health physics documentation

    International Nuclear Information System (INIS)

    Stablein, G.

    1980-01-01

    When dealing with radioactive material the health physicist receives innumerable papers and documents within the fields of researching, prosecuting, organizing and justifying radiation protection. Some of these papers are requested by the health physicist and some are required by law. The scope, quantity and deposit periods of the health physics documentation at the Karlsruhe Nuclear Research Center are presented and rationalizing methods discussed. The aim of this documentation should be the application of physics to accident prevention, i.e. documentation should protect those concerned and not the health physicist. (H.K.)

  10. Models of Co2 emission trading system for projections in MSG6. Documentation and guidance; Utviklingen i stroemforbruket, prisfoelsomheten og stroemmarkedet

    Energy Technology Data Exchange (ETDEWEB)

    Faehn, Taran; Stroem, Birger

    2012-08-15

    Present context of the EU Co2 Emission Trading System (EU ETS) from 2008, involves new measures directed towards a large portion of present emissions sources. Currently there is no basis in statistics figures to offset the consequences of these international obligations in SSB models. In the model projections is nevertheless necessary to model both the current instruments and expected future changes in the rules and forms of association. This paper documents the Ministry of Finance to establish a arrangements for implementing Norway's association with the EU ETS in the model MSG6. It also addresses the EU ETS policy instruments interacting with other objectives and instruments of climate policy, including the Kyoto commitments and various domestic Climate tax systems. The European emissions trading price affect the Norwegian economy through several channels. Firstly, allowances mean that the EU ETS will cover activities that gets an emission rate equal to the permit price, which will influence the players to reduce emissions through various adaptations. Second, the remaining emissions occur subject to quotas, and the proportion who do not receive free allowances will give the state the auction revenue / proceeds. Third, quotas purchased in international markets will affect account surplus. This paper outlines various solutions and concludes by recommending a system that easily can be adapted for studies of any interaction between the EU ETS system and other climate policy objectives. The system can also be easily updated to new data.(eb)

  11. Southwest Project: resource/institutional requirements analysis. Volume II. Technical studies

    Energy Technology Data Exchange (ETDEWEB)

    Ormsby, L. S.; Sawyer, T. G.; Brown, Dr., M. L.; Daviet, II, L. L.; Weber, E. R.; Brown, J. E.; Arlidge, J. W.; Novak, H. R.; Sanesi, Norman; Klaiman, H. C.; Spangenberg, Jr., D. T.; Groves, D. J.; Maddox, J. D.; Hayslip, R. M.; Ijams, G.; Lacy, R. G.; Montgomery, J.; Carito, J. A.; Ballance, J. W.; Bluemle, C. F.; Smith, D. N.; Wehrey, M. C.; Ladd, K. L.; Evans, Dr., S. K.; Guild, D. H.; Brodfeld, B.; Cleveland, J. A.; Hicks, K. L.; Noga, M. W.; Ross, A. M.

    1979-12-01

    The project provides information which could be used to accelerate the commercialization and market penetration of solar electric generation plants in the southwestern region of the United States. The area of concern includes Arizona, California, Colorado, Nevada, New Mexico, Utah, and sections of Oklahoma and Texas. The project evaluated the potential integration of solar electric generating facilities into the existing electric grids of the region through the year 2000. The technologies included wind energy conversion, solar thermal electric, solar photovoltaic conversion, and hybrid solar electric systems. Each of the technologies considered, except hybrid solar electric, was paired with a compatible energy storage system to improve plant performance and enhance applicability to a utility grid system. The hybrid concept utilizes a conventionally-fueled steam generator as well as a solar steam generator so it is not as dependent upon the availability of solar energy as are the other concepts. Operation of solar electric generating plants in conjunction with existing hydroelectric power facilities was also studied. The participants included 12 electric utility companies and a state power authority in the southwestern US, as well as a major consulting engineering firm. An assessment of the state-of-the-art of solar electric generating plants from an electric utility standpoint; identification of the electric utility industry's technical requirements and considerations for solar electric generating plants; estimation of the capital investment, operation, and maintenance costs for solar electric generating plants; and determination of the capital investment of conventional fossil and nuclear electric generating plants are presented. (MCW)

  12. 42 CFR 137.351 - Is a Self-Governance Tribe required to submit construction project progress and financial reports...

    Science.gov (United States)

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false Is a Self-Governance Tribe required to submit..., DEPARTMENT OF HEALTH AND HUMAN SERVICES TRIBAL SELF-GOVERNANCE Construction Roles of Self-Governance Tribe in Establishing and Implementing Construction Project Agreements § 137.351 Is a Self-Governance Tribe required to...

  13. 23 CFR 636.116 - What organizational conflict of interest requirements apply to design-build projects?

    Science.gov (United States)

    2010-04-01

    ... nature of the potential conflict as seen by the owner; (iii) States the nature of the proposed restraint... 23 Highways 1 2010-04-01 2010-04-01 false What organizational conflict of interest requirements... What organizational conflict of interest requirements apply to design-build projects? (a) State...

  14. Effects of Using Requirements Catalogs on Effectiveness and Productivity of Requirements Specification in a Software Project Management Course

    Science.gov (United States)

    Fernández-Alemán, José Luis; Carrillo-de-Gea, Juan Manuel; Meca, Joaquín Vidal; Ros, Joaquín Nicolás; Toval, Ambrosio; Idri, Ali

    2016-01-01

    This paper presents the results of two educational experiments carried out to determine whether the process of specifying requirements (catalog-based reuse as opposed to conventional specification) has an impact on effectiveness and productivity in co-located and distributed software development environments. The participants in the experiments…

  15. W-320 Department of Health documentation

    International Nuclear Information System (INIS)

    Bailey, J.W.

    1998-01-01

    The purpose of this document is to gather information required to show that Project W-320 is in compliance with Washington State Department of Health requirements as specified in Radioactive Air Emissions Notice of Construction Project W-320, Tank 241-C-106 Sluicing, DOE/RL-95-45. Specifically, that W-320 is in compliance with ASME N509-1989 (Nuclear Power Plant Air-Cleaning Units and Components) and ASME N5 10-1989 (Testing of Nuclear Air Treatment Systems) for the 296-C-006 exhaust system

  16. W-320 Department of Health documentation

    Energy Technology Data Exchange (ETDEWEB)

    Bailey, J.W.

    1998-08-07

    The purpose of this document is to gather information required to show that Project W-320 is in compliance with Washington State Department of Health requirements as specified in Radioactive Air Emissions Notice of Construction Project W-320, Tank 241-C-106 Sluicing, DOE/RL-95-45. Specifically, that W-320 is in compliance with ASME N509-1989 (Nuclear Power Plant Air-Cleaning Units and Components) and ASME N5 10-1989 (Testing of Nuclear Air Treatment Systems) for the 296-C-006 exhaust system.

  17. Metrology for hydrogen energy applications: a project to address normative requirements

    Science.gov (United States)

    Haloua, Frédérique; Bacquart, Thomas; Arrhenius, Karine; Delobelle, Benoît; Ent, Hugo

    2018-03-01

    Hydrogen represents a clean and storable energy solution that could meet worldwide energy demands and reduce greenhouse gases emission. The joint research project (JRP) ‘Metrology for sustainable hydrogen energy applications’ addresses standardisation needs through pre- and co-normative metrology research in the fast emerging sector of hydrogen fuel that meet the requirements of the European Directive 2014/94/EU by supplementing the revision of two ISO standards that are currently too generic to enable a sustainable implementation of hydrogen. The hydrogen purity dispensed at refueling points should comply with the technical specifications of ISO 14687-2 for fuel cell electric vehicles. The rapid progress of fuel cell technology now requires revising this standard towards less constraining limits for the 13 gaseous impurities. In parallel, optimized validated analytical methods are proposed to reduce the number of analyses. The study aims also at developing and validating traceable methods to assess accurately the hydrogen mass absorbed and stored in metal hydride tanks; this is a research axis for the revision of the ISO 16111 standard to develop this safe storage technique for hydrogen. The probability of hydrogen impurity presence affecting fuel cells and analytical techniques for traceable measurements of hydrogen impurities will be assessed and new data of maximum concentrations of impurities based on degradation studies will be proposed. Novel validated methods for measuring the hydrogen mass absorbed in hydrides tanks AB, AB2 and AB5 types referenced to ISO 16111 will be determined, as the methods currently available do not provide accurate results. The outputs here will have a direct impact on the standardisation works for ISO 16111 and ISO 14687-2 revisions in the relevant working groups of ISO/TC 197 ‘Hydrogen technologies’.

  18. Rigorous project for existing houses. Energy conservation requires evolution; Rigoureus project voor bestaande woningen. Evolutie voor energiebesparing nodig

    Energy Technology Data Exchange (ETDEWEB)

    Clocquet, R. [DHV, Amersfoort (Netherlands); Koene, F. [ECN Efficiency and Infrastructure, Petten (Netherlands)

    2010-05-15

    How can existing terraced houses be renovated in such a way that their energy use decreases with 75 percent? The Rigorous project of the Energy research Centre of the Netherlands (ECN), TNO, Delft University of Technology and DHV, developed innovative renovation concepts that make such savings feasible by combining constructional measures with installation concepts. On top of that it is also essential that consumer behavior is addressed. [Dutch] Hoe kunnen bestaande rijtjeswoningen zo worden gerenoveerd dat het totale energiegebruik met 75 procent afneemt? In het Rigoureus-project hebben ECN, TNO, TU Delft en DHV innovatieve renovatieconcepten ontwikkeld die dat, door een combinatie van bouwkundige maatregelen en uitgeldende installatieconcepten, mogelijk maken. Daarbij blijkt het van essentieel belang ook het gebruikersgedrag aan te pakken.

  19. Projections of cost and on-site manual-labor requirements for constructing electric-generating plants, 1980-1990

    International Nuclear Information System (INIS)

    1982-02-01

    This report represents part of a continuing effort by the Federal Government to forecast the capital and labor required for constructing electric generating capacity additions necessary to accommodate projected economic and population growth in the US and its regions. Information is included on anticipated additions to electric generating capacity, labor requirements for these additions, capital cost requirements, and forecasting models. Coal-fired, nuclear, hydro, and pumped storage power plants are considered in these forecasts

  20. IDC Re-Engineering Phase 2 System Specification Document Version 1.5

    Energy Technology Data Exchange (ETDEWEB)

    Satpathi, Meara Allena [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Burns, John F. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2017-01-01

    This document contains the system specifications derived to satisfy the system requirements found in the IDC System Requirements Document for the IDC Re-Engineering Phase 2 project. This System Specification Document (SSD) defines waveform data processing requirements for the International Data Centre (IDC) of the Comprehensive Nuclear Test Ban Treaty Organization (CTBTO). The routine processing includes characterization of events with the objective of screening out events considered to be consistent with natural phenomena or non-nuclear, man-made phenomena. This document does not address requirements concerning acquisition, processing and analysis of radionuclide data but does include requirements for the dissemination of radionuclide data and products.

  1. REXIC project: retrospective cross-sectional study of documentation of informed consent for research biobanking in a public research and teaching hospital

    Directory of Open Access Journals (Sweden)

    Marta Nobile

    2013-07-01

    Full Text Available Background. The Center for Transfusion Medicine, Cell Therapy and Cryobiology, Milan, Northern Italy, is the headquarter of the POLI-MI biobank. It co-ordinates the biobank activities of the Fondazione Ca’ Granda Ospedale Maggiore Policlinico of Milan. Such activities require specific safeguarding of donors’ rights and protection of sensitive and genetic data. The Fondazione Ca’ Granda Ospedale Maggiore Policlinico has set up a project on informed consent with the aim of developing awareness and understanding of this issue. Within this project, it has been decided to evaluate how consent for biobanking material is expressed. Design and methods. The aim of the study was to evaluate the quality and completeness of consent to biobanking in the POLI-MI biobank. This was a retrospective study carried out in 2012 on samples of consent declarations collected by biobank units in 2011. Some units used a single, standard consent model available from a previous POLI-MI biobank workgroup. Other units used models which had been previouly formulated. Evaluation was made using a form that indicated the essential elements of consent. Results. A total of 48 consent declarations were collected using the single, standard model and 84 were collected using other models. The consent declarations that used the single, standard model were found to be the most complete and were filled in better than other models. Conclusions. Progressive adoption of a simple, standard consent model is expected to improve the quality of consent acquisition. Regular audit of the compliance of consent practices with ethical and legal requirements is mandatory to improve the quality of research biobanking.

  2. A Requirements-Based Exploration of Open-Source Software Development Projects--Towards a Natural Language Processing Software Analysis Framework

    Science.gov (United States)

    Vlas, Radu Eduard

    2012-01-01

    Open source projects do have requirements; they are, however, mostly informal, text descriptions found in requests, forums, and other correspondence. Understanding such requirements provides insight into the nature of open source projects. Unfortunately, manual analysis of natural language requirements is time-consuming, and for large projects,…

  3. Monitoring Marcellus: A Case Study of a Collaborative Volunteer Monitoring Project to Document the Impact of Unconventional Shale Gas Extraction on Small Streams

    Directory of Open Access Journals (Sweden)

    Candie C. Wilderman

    2016-05-01

    Full Text Available The rapid growth of the natural gas extraction industry in Pennsylvania and neighboring states has stirred concerned citizens to seek ways to collect data on water quality impacts from the extraction activities. As a response to requests from community members, the Alliance for Aquatic Resource Monitoring (ALLARM developed a volunteer-friendly protocol in 2010 for early detection and reporting of surface water contamination by shale gas extraction activities in small streams. To date, ALLARM has trained more than 2,000 volunteers in Pennsylvania, New York, and West Virginia to monitor water quality (conductivity, barium, strontium, and total dissolved solids and physical parameters (stream stage and visual observations prior to, during, and after shale gas wells have been developed. This paper documents the operational models of Public Participation in Scientific Research (PPSR used by ALLARM, describes the volunteer monitoring protocol developed, and examines three years of water quality results from hundreds of monitoring sites in Pennsylvania and New York. The majority of watersheds monitored are small, forested, headwater streams. Results indicate that mean conductivity in streams is strongly and positively related to the percentage of development and the percentage of limestone in the watersheds. Mean conductivity is not significantly related to number or density of drilled wells, although the dataset did not lend itself to finding a signal from shale gas activities because only 20% of the watersheds had wells drilled at the time of sampling. This fact enables the use of these data as baseline data for future documentation of shale gas impacts on water quality. Volunteers have reported multiple cases of visual pollution related to shale gas activities, but have not identified water contamination events based on stream water chemistry. The results of the volunteer dataset are compared with results from the scientific literature, affirming

  4. Soil Moisture Active Passive (SMAP) Project Algorithm Theoretical Basis Document SMAP L1B Radiometer Data Product: L1B_TB

    Science.gov (United States)

    Piepmeier, Jeffrey; Mohammed, Priscilla; De Amici, Giovanni; Kim, Edward; Peng, Jinzheng; Ruf, Christopher; Hanna, Maher; Yueh, Simon; Entekhabi, Dara

    2016-01-01

    The purpose of the Soil Moisture Active Passive (SMAP) radiometer calibration algorithm is to convert Level 0 (L0) radiometer digital counts data into calibrated estimates of brightness temperatures referenced to the Earth's surface within the main beam. The algorithm theory in most respects is similar to what has been developed and implemented for decades for other satellite radiometers; however, SMAP includes two key features heretofore absent from most satellite borne radiometers: radio frequency interference (RFI) detection and mitigation, and measurement of the third and fourth Stokes parameters using digital correlation. The purpose of this document is to describe the SMAP radiometer and forward model, explain the SMAP calibration algorithm, including approximations, errors, and biases, provide all necessary equations for implementing the calibration algorithm and detail the RFI detection and mitigation process. Section 2 provides a summary of algorithm objectives and driving requirements. Section 3 is a description of the instrument and Section 4 covers the forward models, upon which the algorithm is based. Section 5 gives the retrieval algorithm and theory. Section 6 describes the orbit simulator, which implements the forward model and is the key for deriving antenna pattern correction coefficients and testing the overall algorithm.

  5. Implementation of the EU directive on the energy performance of buildings: Development of the Latvian Scheme for energy auditing of buildings and inspection of boilers. Project document

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    'Development of the Latvian Scheme for energy auditing of buildings and inspection of boilers' includes major steps in implementing the EU EPB directive in Latvia. The EPB directive includes a number of efforts: 1. A methodology for calculation of the integrated energy performance of buildings 2. Application of minimum requirements on the energy performance for new buildings 3. Application of minimum requirements on the energy performance for larger existing buildings subject to major renovation 4. Energy performance certification (energy labelling) of buildings 5. Regular inspection of boilers and of air-conditioning systems in buildings, and assessment of heating installations in older systems. The present project includes activities connected to point 4 and point 5. The results will include 4 steps in implementing the EU EPB directive: 1) A Latvian training of certified independent energy auditors to be active conducting energy audits and issuing energy performance certificates. Including a handbook in energy auditing. 2) A Latvian training of certified independent experts for inspection of boilers, air-con systems and assessing older heating systems. Including a handbook in boiler inspection. 3) A proposal for the institutional set-up for a connected scheme for energy auditing and a scheme for boiler inspection 4) Initial information on the scheme of energy auditors and of the boiler inspection. (au)

  6. Recommended HSE-7 documents hierarchy

    International Nuclear Information System (INIS)

    Klein, R.B.; Jennrich, E.A.; Lund, D.M.; Danna, J.G.; Davis, K.D.; Rutz, A.C.

    1990-01-01

    This report recommends a hierarchy of waste management documents at Los Alamos National Laboratory (LANL or ''Laboratory''). The hierarchy addresses documents that are required to plan, implement, and document waste management programs at Los Alamos. These documents will enable the waste management group and the six sections contained within that group to satisfy requirements that are imposed upon them by the US Department of Energy (DOE), DOE Albuquerque Operations, US Environmental Protection Agency, various State of New Mexico agencies, and Laboratory management

  7. Text document classification

    Czech Academy of Sciences Publication Activity Database

    Novovičová, Jana

    č. 62 (2005), s. 53-54 ISSN 0926-4981 R&D Projects: GA AV ČR IAA2075302; GA AV ČR KSK1019101; GA MŠk 1M0572 Institutional research plan: CEZ:AV0Z10750506 Keywords : document representation * categorization * classification Subject RIV: BD - Theory of Information

  8. Course documentation report

    DEFF Research Database (Denmark)

    Buus, Lillian; Bygholm, Ann; Walther, Tina Dyngby Lyng

    A documentation report on the three pedagogical courses developed during the MVU project period. The report describes the three processes taking departure in the structure and material avaiable at the virtual learning environment. Also the report describes the way the two of the courses developed...

  9. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ General - CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. LHC Symposiums Management - CB - MB - FB - FMC Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2006 Annual reviews are posted.   CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat a...

  10. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ General - CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. LHC Symposiums Management - CB - MB - FB - FMC Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2006 Annual reviews are posted. CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat about the natu...

  11. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ General - CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. LHC Symposiums Management - CB - MB - FB - FMC Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2006 Annual reviews are posted. CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat about the natur...

  12. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ Management- CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. Management - CB - MB - FB Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2007 Annual reviews are posted. CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat about the nature of employment and ...

  13. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ Management- CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. Management - CB - MB - FB Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2007 Annual reviews are posted. CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat about the nature of em¬pl...

  14. CMS DOCUMENTATION

    CERN Multimedia

    CMS TALKS AT MAJOR MEETINGS The agenda and talks from major CMS meetings can now be electronically accessed from the iCMS Web site. The following items can be found on: http://cms.cern.ch/iCMS/ General - CMS Weeks (Collaboration Meetings), CMS Weeks Agendas The talks presented at the Plenary Sessions. LHC Symposiums Management - CB - MB - FB - FMC Agendas and minutes are accessible to CMS members through their AFS account (ZH). However some linked documents are restricted to the Board Members. FB documents are only accessible to FB members. LHCC The talks presented at the ‘CMS Meetings with LHCC Referees’ are available on request from the PM or MB Country Representative. Annual Reviews The talks presented at the 2006 Annual reviews are posted. CMS DOCUMENTS It is considered useful to establish information on the first employment of CMS doctoral students upon completion of their theses. Therefore it is requested that Ph.D students inform the CMS Secretariat about the na...

  15. Report and recommendations of the Pingston Hydroelectric Project Committee with respect to the issuance of a project approval certificate pursuant to the Environmental Assessment Act, R.S.B.C. 1966, c.119 and fulfilling the requirements for a screening report pursuant to the Canadian Environmental Assessment Act, 1992 c.37, V.1

    International Nuclear Information System (INIS)

    1999-05-01

    A final application was submitted in March 1998 by Canadian Hydro Developers (CHD) with the intent of obtaining a Project Approval certificate under the Act for development of the Project. The purpose of the project committee report is to summarize the application and project report, to describe the potential environmental, economic, social, cultural, heritage and health effects of the project and measures required to mitigate significant adverse effects and to document the recommendations of the committee. The Project is composed of five main parts including the headworks, tunnel, penstock, powerhouse and transmission line. The potential environmental effects of the Project relate mainly to fisheries resources including entrainment at the intake, instream flow needs downstream from the headworks, alteration of fish habitat, sedimentation, and blockage of fish passage. CHD expects to minimize these effects through facility design modifications, operational changes and monitoring programs as required. Other concerns such as alteration of creek temperature, generation of methyl mercury in reservoirs, greenhouse gas flux in reservoirs and total gas pressures have been examined in light of the Project's size and operational schenarios, and the proponent expects these effects to be of minor concern. The Project Committee concluded that the project, with successful implementation and compliance of mitigation and compensation strategies, is not expected to cause significant adverse effects

  16. Enhancing Documentation of Pressure Ulcer Prevention Interventions: A Quality Improvement Strategy to Reduce Pressure Ulcers.

    Science.gov (United States)

    Jacobson, Therese M; Thompson, Susan L; Halvorson, Anna M; Zeitler, Kristine

    2016-01-01

    Prevention of hospital-acquired pressure ulcers requires the implementation of evidence-based interventions. A quality improvement project was conducted to provide nurses with data on the frequency with which pressure ulcer prevention interventions were performed as measured by documentation. Documentation reports provided feedback to stakeholders, triggering reminders and reeducation. Intervention reports and modifications to the documentation system were effective both in increasing the documentation of pressure ulcer prevention interventions and in decreasing the number of avoidable hospital-acquired pressure ulcers.

  17. CASK/MSC/WP PREPARATION SYSTEM DESCRIPTION DOCUMENT

    International Nuclear Information System (INIS)

    S. Drummond

    2005-01-01

    The purpose of this system description document (SDD) is to establish requirements that drive the design of the Cask/MSC/WP preparation system and their bases to allow the design effort to proceed to license application. This SDD is a living document that will be revised at strategic points as the design matures over time. This SDD identifies the requirements and describes the system design, as they exist at this time, with emphasis on those attributes of the design provided to meet the requirements. This SDD has been developed to be an engineering tool for design control. Accordingly, the primary audience and users are design engineers. This type of SDD both leads and trails the design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. This SDD trails the design with regard to the description of the system. The description provided in the SDD is a reflection of the results of the design process to date. This SDD addresses the ''Project Requirements Document'' (PRD) (Canori and Leitner 2003 [DIRS 166275]) requirements. Additional PRD requirements may be cited, as applicable, to drive the design of specific aspects of the system, with justifications provided in the basis. Functional and operational requirements applicable to this system are obtained from the ''Project Functional and Operational Requirements'' (F and OR) (Curry 2004 [DIRS 170557]) document. Other requirements to support the design process have been taken from higher-level requirements documents such as the ''Project Design Criteria Document'' (PDC) (BSC 2004 [DIRS 171599]) and the preclosure safety analyses

  18. CASK/MSC/WP PREPARATION SYSTEM DESCRIPTION DOCUMENT

    Energy Technology Data Exchange (ETDEWEB)

    S. Drummond

    2005-04-12

    The purpose of this system description document (SDD) is to establish requirements that drive the design of the Cask/MSC/WP preparation system and their bases to allow the design effort to proceed to license application. This SDD is a living document that will be revised at strategic points as the design matures over time. This SDD identifies the requirements and describes the system design, as they exist at this time, with emphasis on those attributes of the design provided to meet the requirements. This SDD has been developed to be an engineering tool for design control. Accordingly, the primary audience and users are design engineers. This type of SDD both leads and trails the design process. It leads the design process with regard to the flow down of upper tier requirements onto the system. Knowledge of these requirements is essential in performing the design process. This SDD trails the design with regard to the description of the system. The description provided in the SDD is a reflection of the results of the design process to date. This SDD addresses the ''Project Requirements Document'' (PRD) (Canori and Leitner 2003 [DIRS 166275]) requirements. Additional PRD requirements may be cited, as applicable, to drive the design of specific aspects of the system, with justifications provided in the basis. Functional and operational requirements applicable to this system are obtained from the ''Project Functional and Operational Requirements'' (F&OR) (Curry 2004 [DIRS 170557]) document. Other requirements to support the design process have been taken from higher-level requirements documents such as the ''Project Design Criteria Document'' (PDC) (BSC 2004 [DIRS 171599]) and the preclosure safety analyses.

  19. Yeu and Noirmoutier islands - Electric connection to the offshore wind farm. Brochure 'Electric connection of the offshore wind farm to the Yeu and Noirmoutier islands' - Consultation file, December 2015, District of Vendee. Document of contribution to the public debate. Yeu and Noirmoutier islands offshore wind farm project - Project commissioner file

    International Nuclear Information System (INIS)

    Boyadjis, Jean-Marc; Corallo, Christian

    2015-05-01

    After a brief presentation of the context, a first document presents the connection characteristics, the general route of the electrical connection, how the sea and ground environment is taken into account, how the population is consulted for the project, the organisation of the public inquiry. The second document presents the consultation file with a description of the adopted solution and main characteristics of the project of connection of offshore wind farms about the Yeu and Noirmoutier islands, an analysis of the initial condition of the environment (physical and natural environment, landscapes and heritage, human and social-economic context), a description and a comparative analysis of proposed beams for the underwater connection, landfall and underground connection, and the planned continuation of the project (consultation, administrative procedure, planning). The next document aims at presenting the project before public consultation: objectives, underwater and underground connections with some of their technical characteristics, planning. Another document also presents the offshore wind farm project, its energetic and technical characteristics, how it is integrated into its environment (stakes and challenges, impacts on landscape and on activities), how it is an example of the development of offshore wind energy sector. It is completed by several appendices containing a variety of data on these issues. A last document is a presentation of the project by the project commissioner (RTE) which notably addresses how technical and environmental issues are to be addressed

  20. THE PLANNING OF A CUSTOMER RELATIONSHIP MANAGEMENT PROJECT: REQUIREMENTS AND OPPORTUNITIES

    Directory of Open Access Journals (Sweden)

    Adriana OLARU

    2007-01-01

    Full Text Available After a brief presentation of the aspects regarding the planning of a customer relationship management (CRM project, we emphasize the factors that assure the success of such an approach. In order to obtain the attended results, an organization needs the best selection of the project manager and the most efficient teamwork, which implies employees from the company’s departments and also IT specialists. In the final part, we made appreciations concerning the efficiency of a CRM project and the opportunities created by its implementation.