WorldWideScience

Sample records for lhc accelerator tunnel

  1. Computer graphic of LHC in the tunnel

    CERN Multimedia

    1996-01-01

    A computer-generated image of the LHC particle accelerator at CERN in the tunnel originally built for the LEP accelerator that was closed in 2000. The cross-section of an LHC superconducting dipole magnet is also seen.

  2. Proposal for the award of a contract for the supply and installation of pipelines for the LHC accelerator tunnel

    CERN Document Server

    2001-01-01

    This document concerns the award of a contract for the supply and installation of pipelines for the LHC accelerator tunnel. Following a market survey carried out among 92 firms in fifteen Member States, a call for tenders (IT-2682/ST/LHC) was sent on 7 September 2001 to seven firms, seven consortia consisting of two firms and three consortia consisting of four firms, in twelve Member States. By the closing date, CERN had received 11 tenders from five firms and six consortia in ten Member States. The Finance Committee is invited to agree to the negotiation of a contract with RENCO (IT), the lowest compliant bidder, for the supply and installation of pipelines for the LHC accelerator tunnel for a total amount of 21 995 304 Swiss francs, not subject to revision. The firm has indicated the following distribution by country of the contract value covered by this adjudication proposal: IT - 100%.

  3. Plan of SPS to LHC transfer tunnels

    CERN Multimedia

    Laurent Guiraud

    2001-01-01

    This diagram shows the LHC and the SPS pre-accelerator (in blue) and the transfer lines that will connect them (in red). Spanning the France-Swiss border (shown by green crosses), the 27-km LHC tunnel will receive a beam that has been pre-accelerated to 450 GeV in the smaller SPS storage ring. The transfer lines will remove each beam from the SPS and inject them into the LHC where they will be accelerated to the full energy of 7 TeV.

  4. 7 March 2013 -Stanford University Professor N. McKeown FREng, Electrical Engineering and Computer Science and B. Leslie, Creative Labs visiting CERN Control Centre and the LHC tunnel with Director for Accelerators and Technology S. Myers.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    7 March 2013 -Stanford University Professor N. McKeown FREng, Electrical Engineering and Computer Science and B. Leslie, Creative Labs visiting CERN Control Centre and the LHC tunnel with Director for Accelerators and Technology S. Myers.

  5. Acceleration and support post deformation measurements during surface and tunnel transport of a LHC Short Straight Section

    CERN Document Server

    Capatina, O; CERN. Geneva. TS Department

    2004-01-01

    This technical note is a complement to the technical note [1]. The former technical note dealt with the experimental modal analysis and the road transport with transport restraints and special suspension. The present note describes the measured accelerations and support post deformations during road transport at reduced speed without end restraints or special suspension. This note also reports the accelerations and support post deformations during handling and tunnel transport with the dedicated tunnel vehicle. The measured accelerations are compared with the specified acceleration limits.

  6. Le LHC, un tunnel cosmique

    CERN Multimedia

    CERN. Geneva

    2009-01-01

    Et si la lumière au bout du tunnel du LHC était cosmique ? En d’autres termes, qu’est-ce que le LHC peut nous apporter dans la connaissance de l’Univers ? Car la montée en énergie des accélérateurs de particules nous permet de mieux appréhender l’univers primordial, chaud et dense. Mais dans quel sens dit-on que le LHC reproduit des conditions proches du Big bang ? Quelles informations nous apporte-t-il sur le contenu de l’Univers ? La matière noire est-elle détectable au LHC ? L’énergie noire ? Pourquoi l’antimatière accumulée au CERN est-elle si rare dans l’Univers ? Et si le CERN a bâti sa réputation sur l’exploration des forces faibles et fortes qui opèrent au sein des atomes et de leurs noyaux, est-ce que le LHC peut nous apporter des informations sur la force gravitationnelle qui gouverne l’évolution cosmique ? Depuis une trentaine d’années, notre compréhension de l’univers dans ses plus grandes dimensions et l’appréhension de son comportement aux plus peti...

  7. LHC Dipoles Accelerate

    CERN Multimedia

    2001-01-01

    Andrezej Siemko (left), Peter Sievers (centre), and Lucio Rossi (right), have the exciting challenge of preparing and testing 2000 magnets for the LHC. The LHC is going to require a lot of powerful magnets by the time it begins operation in 2006. More specifically, it is going to need 130 special magnets, 400 quadrupoles, and a whopping 1250 dipoles! Preparing and testing these magnets for the conditions they will encounter in the LHC is not an easy task. But evaluation of the most recently received magnet, from the German company Noell, is showing that while the monumental task of receiving and testing nearly 2000 magnets is going to be exhausting, the goals are definitely attainable. At the moment and over the next year, pre-series magnets (the magnets that CERN uses to fine tune performance) are arriving slowly (90 in total will arrive), but by 2003 the rate of series magnet arrival will accelerate to 9 per week, that's over 450 in a single year! And working with these magnets when they arrive is tough. ...

  8. 6 March 2013 - Committee for Employment and Learning, Northern Ireland Legislative Assembly, United Kingdom of Great Britain and Northern Ireland in the LHC tunnel and visiting the LHCb experiment at LHC Point 8. Director for Accelerators and Technology S. Myers with Vice-Chair T. Buchanan.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    6 March 2013 - Committee for Employment and Learning, Northern Ireland Legislative Assembly, United Kingdom of Great Britain and Northern Ireland in the LHC tunnel and visiting the LHCb experiment at LHC Point 8. Director for Accelerators and Technology S. Myers with Vice-Chair T. Buchanan.

  9. The 27-km circular path of the LHC tunnel

    CERN Multimedia

    AC-DI-MM

    1994-01-01

    This aerial view of the CERN site shows the path of the 27-km circumference tunnel that housed the LEP accelerator and now contains the accelerator for CERN's new flagship project, the LHC. The ring stretches from Geneva airport, which can be seen on the lower left, to the French countryside.

  10. Demineralised water cooling in the LHC accelerator

    CERN Document Server

    Peón-Hernández, G

    2002-01-01

    In spite of the LHC accelerator being a cryogenic machine, it remains nevertheless a not negligible heat load to be removed by conventional water-cooling. About 24MW will be taken away by demineralised water cooled directly by primary water from the LHC cooling towers placed at the even points. This paper describes the demineralised water network in the LHC tunnel including pipe diameters, lengths, water speed, estimated friction factor, head losses and available supply and return pressures for each point. It lists all water cooled equipment, highlights the water cooled cables as the most demanding equipment followed by the radio frequency racks and cavities, and by the power converters. Their main cooling requirements and their positions in the tunnel are also presented.

  11. HL-LHC Accelerator

    CERN Document Server

    Zimmermann, F

    2013-01-01

    The tentative schedule, key ingredients, as well as progress of pertinent R&D and component prototypes for the LHC luminosity upgrade, "HL-LHC," are reviewed. Also alternative scenarios based on performance-improving consolidations (PICs) instead of a full upgrade are discussed. Tentative time schedules and expected luminosity evolutions for the different scenarios are sketched. The important role of HL-LHC development as a step towards a future HE-LHC or VHE-LHC is finally highlighted. Presented at "Higgs & Beyond" Conference Tohoku University, Sendai 7 June 2013.

  12. Post-LHC accelerator magnets

    International Nuclear Information System (INIS)

    Gourlay, Stephen A.

    2001-01-01

    The design and practicality of future accelerators, such as hadron colliders and neutrino factories being considered to supercede the LHC, will depend greatly on the choice of superconducting magnets. Various possibilities will be reviewed and discussed, taking into account recent progress and projected improvements in magnet design and conductor development along with the recommendations from the 2001 Snowmass workshop

  13. A worker inside the LHC tunnel

    CERN Multimedia

    Maximilien Brice

    2006-01-01

    Technicians and engineers worked days and nights, carefully installing 20 magnets a week between 7 March 2005 and 26 April 2006. Each dipole weighs 34 tonnes and is 15 m long. Once they have been lowered down the specially constructed shaft, they begin a slow progression to their final destinations in the LHC tunnel, taking about 10 hours to arrive at the furthest point on the LHC ring.

  14. View of the LHC tunnel with worker.

    CERN Multimedia

    Maximilien Brice

    2006-01-01

    The 616th dipole out of 1232, on its way to its final position in the tunnel of the LHC. Technicians and engineers continue to work day and night carefully installing 20 magnets a week. Each of the dipoles weighs 34 tonnes and is 15 m long. Once they have been lowered down the specially constructed shaft on the Meyrin site, they begin a slow progression to their final destinations in the LHC tunnel, taking about 10 hours to arrive at Point 6, the furthest point on the LHC ring. Upon arrival, each of the dipoles is aligned and interconnected to the magnets that are already installed.Bigger files available (39Mpx)

  15. TunnelVision: LHC Tunnel Photogrammetry System for Structural Monitoring

    CERN Document Server

    Fallas, William

    2014-01-01

    In this document an algorithm to detect deformations in the LHC Tunnel of CERN is presented. It is based on two images, one represents the ideal state of the tunnel and the other one the actual state. To find the differences between both, the algorithm is divided in three steps. First, an image enhancement is applied to make easier the detection. Second, two different approaches to reduce noise are applied to one or both images. And third, it is defined a group of characteristics about the type of deformation desired to detect. Finally, the conclusions show the effectiveness of the algorithm in the experimental results.

  16. LHC Accelerator Fault Tracker - First Experience

    CERN Document Server

    Apollonio, Andrea; Roderick, Chris; Schmidt, Ruediger; Todd, Benjamin; Wollmann, Daniel

    2016-01-01

    Availability is one of the key performance indicators of LHC operation, being directly correlated with integrated luminosity production. An effective tool for availability tracking is a necessity to ensure a coherent capture of fault information and relevant dependencies on operational modes and beam parameters. At the beginning of LHC Run 2 in 2015, the Accelerator Fault Tracking (AFT) tool was deployed at CERN to track faults or events affecting LHC operation. Information derived from the AFT is crucial for the identification of areas to improve LHC availability, and hence LHC physics production. For the 2015 run, the AFT has been used by members of the CERN Availability Working Group, LHC Machine coordinators and equipment owners to identify the main contributors to downtime and to understand the evolution of LHC availability throughout the year. In this paper the 2015 experience with the AFT for availability tracking is summarised and an overview of the first results as well as an outlook to future develo...

  17. 14 November 2013 - Director of Indian Institute of Technology Indore P. Mathur with members of the Indian community working at CERN; visiting the LHC tunnel at Point 2, the ALICE experimental area and SM18 with ALICE Collaboration Spokesperson, Istituto Nazionale Fisica Nucleare P. Giubellino and Technology Department, Accelerator Beam Transfer Group Leader V. Mertens

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    14 November 2013 - Director of Indian Institute of Technology Indore P. Mathur with members of the Indian community working at CERN; visiting the LHC tunnel at Point 2, the ALICE experimental area and SM18 with ALICE Collaboration Spokesperson, Istituto Nazionale Fisica Nucleare P. Giubellino and Technology Department, Accelerator Beam Transfer Group Leader V. Mertens

  18. 9 April 2013 - Minister for Universities and Science United Kingdom of Great Britain and Northern Ireland D. Willetts in the ATLAS experimental cavern with ATLAS Collaboration Spokesperson D. Charlton and in the LHC tunnel at Point 1 with Beams Department Head P. Collier. Director for Accelerators and Technology S. Myers, Editor at the Communication Group K. Kahle and Beams Department Engineer R. Veness present.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    9 April 2013 - Minister for Universities and Science United Kingdom of Great Britain and Northern Ireland D. Willetts in the ATLAS experimental cavern with ATLAS Collaboration Spokesperson D. Charlton and in the LHC tunnel at Point 1 with Beams Department Head P. Collier. Director for Accelerators and Technology S. Myers, Editor at the Communication Group K. Kahle and Beams Department Engineer R. Veness present.

  19. Controlled Cold Helium Spill Test in the LHC Tunnel at CERN

    Science.gov (United States)

    Koettig, T.; Casas-Cubillos, J.; Chorowski, M.; Dufay-Chanat, L.; Grabowski, M.; Jedrusyna, A.; Lindell, G.; Nonis, M.; Vauthier, N.; van Weelderen, R.; Winkler, T.; Bremer, J.

    The helium cooled magnets of the LHC particle accelerator are installed in a confined space, formed by a 27 km circumference 3.8 m diameter underground tunnel. The vacuum enclosures of the superconducting LHC magnets are protected by a lift plate against excessive overpressure created by eventual leaks from the magnet helium bath, or from the helium supply headers. A three-meter long no stay zone has been defined centered to these plates, based on earlier scale model studies, to protect the personnel against the consequences of an eventual opening of such a lift plate. More recently several simulation studies have been carried out modelling the propagation of the resulting helium/air mixture along the tunnel in case of such a cold helium release at a rate in the range of 1 kg/s. To validate the different scale models and simulation studies, real life mock-up tests have been performed in the LHC, releasing about 1000 liter of liquid helium under standard operational tunnel conditions. Data recorded during these tests include oxygen level, temperature and flow speed as well as video recordings, taken up- and downstream of the spill point (-100 m to +200 m) with respect to the ventilation direction in the LHC tunnel. The experimental set-up and measurement results are presented. Generic effects found during the tests will be discussed to allow the transposal to possible cold helium release cases in similar facilities.

  20. Demonstration of the LHC Safety Training Tunnel Mock-Up

    CERN Multimedia

    Brice, Maximilien

    2014-01-01

    Members of CERN's management visit the LHC tunnel mock-up at the Safety Training Centre on the Prévessin site. The facility is used to train personnel in emergency responses including the use of masks and safe evacuation.

  1. LHC Report: Even accelerators need a break

    CERN Multimedia

    CERN Bulletin

    2011-01-01

    The LHC technical stop is in full swing, with a lot of essential maintenance work on the accelerator services, such as electricity distribution, cooling, ventilation, cryogenic systems, access and safety systems, vacuum, cranes and lifts, being crammed into the few weeks before the start of the 2011 run in February.   Team changing a magnet in the SPS accelerator.  In addition to the maintenance work a number of modifications are being made to the accelerator for 2011. These include the installation of small solenoids to combat the build-up of electrons inside the vacuum chamber with the increasing proton beam intensity; the replacement of a number of UPS (Uninterruptible Power Supply) installations, which are vital to ensuring the continuity of the electrical supply to essential systems such as the cryogenics; the installation of additional capacitors on the QPS (Quench Protection system) to prepare for a possible increase in beam energy in 2011; the completion of the programme to repla...

  2. Nonlinear predictive control in the LHC accelerator

    CERN Document Server

    Blanco, E; Cristea, S; Casas, J

    2009-01-01

    This paper describes the application of a nonlinear model-based control strategy in a real challenging process. A predictive controller based on a nonlinear model derived from physical relationships, mainly heat and mass balances, has been developed and commissioned in the inner triplet heat exchanger unit (IT-HXTU) of the large hadron collider (LHC) particle accelerator at European Center for Nuclear Research (CERN). The advanced regulation\\ maintains the magnets temperature at about 1.9 K. The development includes a constrained nonlinear state estimator with a receding horizon estimation procedure to improve the regulator predictions.

  3. CERN-LHC accelerator superconducting magnet. Development and international cooperation

    International Nuclear Information System (INIS)

    Yamamoto, Akira; Nakamoto, Tatsushi; Sasaki, Ken-ichi

    2009-01-01

    CERN-LHC accelerator superconducting magnets and a cooperative work for interaction region quadrupole magnets are introduced. The accelerator commissioning and the incident happened during the commissioning in 2008 is also briefly discussed. (author)

  4. The HL-LHC accelerator physics challenges

    CERN Document Server

    Fartoukh, S

    2014-01-01

    We review the conceptual baseline of the HL-LHC project, putting into perspective the main beam physics challenges of this new collider in comparison with the existing LHC, and the series of solutions and possible mitigation measures presently envisaged.

  5. The HL-LHC Accelerator Physics Challenges

    Science.gov (United States)

    Fartoukh, S.; Zimmermann, F.

    The conceptual baseline of the HL-LHC project is reviewed, putting into perspective the main beam physics challenges of this new collider in comparison with the existing LHC, and the series of solutions and possible mitigation measures presently envisaged.

  6. The HL-LHC accelerator physics challenges

    CERN Document Server

    Fartoukh, S

    2015-01-01

    The conceptual baseline of the HL-LHC project is reviewed, putting into perspective the main beam physics challenges of this new collider in comparison with the existing LHC, and the series of solutions and possible mitigation measures presently envisaged.

  7. Electron accelerator for tunneling through hard rock

    International Nuclear Information System (INIS)

    Avery, R.T.; Keefe, D.

    1975-10-01

    Earlier work demonstrated that intense sub-microsecond bursts of energetic electrons cause significant pulverization and spalling of a variety of rock types. The spall debris generally consists of sand, dust, and small flakes. If carried out at rapid repetition rate, this can lead to a promising technique for increasing the speed and reducing the cost of underground excavation of tunnels, mines, and storage spaces. The conceptual design features of a Pulsed Electron Tunnel Excavator capable of tunneling approximately ten times faster than conventional drill/blast methods are presented, with primary emphasis on the electron accelerator and only a brief description of the tunneling aspects. Of several candidate types of accelerators, a linear induction accelerator producing electron pulses (5 MV, 5 kA, 1.0 μs = 25 kJ) at a 360 Hz rate was selected for the conceptual example. This provides the required average electron beam power output of 9 MW. The feasibility of such an accelerator is discussed

  8. Electron accelerator for tunneling through hard rock

    International Nuclear Information System (INIS)

    Avery, R.T.; Keefe, D.

    1975-01-01

    Earlier work demonstrated that intense sub-microsecond bursts of energetic electrons cause significant pulverization and spalling of a variety of rock types. The spall debris generally consists of sand, dust, and small flakes. If carried out at rapid repetition rate, this can lead to a promising technique for increasing the speed and reducing the cost of underground excavation of tunnels, mines, and storage spaces. The conceptual design features of a Pulsed Electron Tunnel Excavator capable of tunneling approximately ten times faster than conventional drill/blast methods are presented with primary emphasis on the electron accelerator and only a brief description of the tunneling aspects. Of several candidate types of accelerators, a linear induction accelerator producing electron pulses (5 MV, 5 kA, 1.0 μs = 25 kJ) at a 360 Hz rate was selected for the conceptual example. This provides the required average electron beam power output of 9 MW. The feasibility of such an accelerator is discussed

  9. Breaking through the tranfer tunnel

    CERN Document Server

    Laurent Guiraud

    2001-01-01

    This image shows the tunnel boring machine breaking through the transfer tunnel into the LHC tunnel. Proton beams will be transferred from the SPS pre-accelerator to the LHC at 450 GeV through two specially constructed transfer tunnels. From left to right: LHC Project Director, Lyn Evans; CERN Director-General (at the time), Luciano Maiani, and Director for Accelerators, Kurt Hubner.

  10. The commissioning of the instrumentation for the LHC tunnel cryogenics

    CERN Document Server

    Avramidou, R; Bamis, C; Casas-Cubillos, J; Dragoneas, A; Fampris, X; Fernandez-Penacoba, G; Gomes, P; Gousiou, E; Jeanmonod, N; Karagiannis, F; Koumparos, A; Leontsinis, S; Lopez-Lorente, A; Patsouli, A; Polychroniadis, I; Suraci, A; Theodoropoulos, G; Vauthier, N; Vottis, C

    2007-01-01

    The Large Hadron Collider (LHC) at CERN is a superconducting accelerator and proton-proton collider of circumference of 27 km, lying about 100 m underground. Its operation relies on 1232 superconducting dipoles with a field of 8.3 T and 392 superconducting quadrupoles with a field gradient of 223 T/m powered at 11.8 kA and operating in superfluid helium at 1.9 K. This paper describes the cryogenic instrumentation commissioning, the challenges and the project organization based on our 2.5 years experience.

  11. Baseline review of the U.S. LHC Accelerator project

    International Nuclear Information System (INIS)

    1998-02-01

    The Department of Energy (DOE) Review of the U.S. Large Hadron Collider (LHC) Accelerator project was conducted February 23--26, 1998, at the request of Dr. John R. O'Fallon, Director, Division of High Energy Physics, Office of Energy Research, U.S. DOE. This is the first review of the U.S. LHC Accelerator project. Overall, the Committee found that the U.S. LHC Accelerator project effort is off to a good start and that the proposed scope is very conservative for the funding available. The Committee recommends that the project be initially baselined at a total cost of $110 million, with a scheduled completion data of 2005. The U.S. LHC Accelerator project will supply high technology superconducting magnets for the interaction regions (IRs) and the radio frequency (rf) straight section of the LHC intersecting storage rings. In addition, the project provides the cryogenic support interface boxes to service the magnets and radiation absorbers to protect the IR dipoles and the inner triplet quadrupoles. US scientists will provide support in analyzing some of the detailed aspects of accelerator physics in the two rings. The three laboratories participating in this project are Brookhaven National Laboratory, Fermi National Accelerator Laboratory (Fermilab), and Lawrence Berkeley National Laboratory. The Committee was very impressed by the technical capabilities of the US LHC Accelerator project team. Cost estimates for each subsystem of the US LHC Accelerator project were presented to the Review Committee, with a total cost including contingency of $110 million (then year dollars). The cost estimates were deemed to be conservative. A re-examination of the funding profile, costs, and schedules on a centralized project basis should lead to an increased list of deliverables. The Committee concluded that the proposed scope of US deliverables to CERN can be readily accomplished with the $110 million total cost baseline for the project. The current deliverables should serve as

  12. Run II of the LHC: The Accelerator Science

    Science.gov (United States)

    Redaelli, Stefano

    2015-04-01

    In 2015 the Large Hadron Collider (LHC) at the European Organization for Nuclear Research (CERN) starts its Run II operation. After the successful Run I at 3.5 TeV and 4 TeV in the 2010-2013 period, a first long shutdown (LS1) was mainly dedicated to the consolidation of the LHC magnet interconnections, to allow the LHC to operate at its design beam energy of 7 TeV. Other key accelerator systems have also been improved to optimize the performance reach at higher beam energies. After a review of the LS1 activities, the status of the LHC start-up progress is reported, addressing in particular the status of the LHC hardware commissioning and of the training campaign of superconducting magnets that will determine the operation beam energy in 2015. Then, the plans for the Run II operation are reviewed in detail, covering choice of initial machine parameters and strategy to improve the Run II performance. Future prospects of the LHC and its upgrade plans are also presented.

  13. LHC Report: Rehearsing the LHC accelerator systems for the Run 2 start-up with beam

    CERN Multimedia

    Reyes Alemany Fernandez

    2015-01-01

    While the commissioning of the superconducting circuits is ongoing, great care is also being taken to make sure that the other key LHC accelerator systems are qualified for beam. Since spring 2014, small-scale integration tests on the accelerator systems have been scheduled and carried out successfully to exercise them fully and thoroughly debug their multiple interfaces. The LHC Operations team leads this activity in tight collaboration with the equipment experts and the essential support of the Accelerator Controls group. The tests start once individual system qualification has been performed by the equipment owners and they are ready to be handed over to operations. These tests performed by Operations are called dry runs – dry because they are performed without beam – and they are carried out from the CERN Control Centre (CCC) using the same high-level software applications that will be used during beam operation. The dry runs are the first step towards a global integration test ...

  14. Tunnel flexibility effect on the ground surface acceleration response

    Science.gov (United States)

    Baziar, Mohammad Hassan; Moghadam, Masoud Rabeti; Choo, Yun Wook; Kim, Dong-Soo

    2016-09-01

    Flexibility of underground structures relative to the surrounding medium, referred to as the flexibility ratio, is an important factor that influences their dynamic interaction. This study investigates the flexibility effect of a box-shaped subway tunnel, resting directly on bedrock, on the ground surface acceleration response using a numerical model verified against dynamic centrifuge test results. A comparison of the ground surface acceleration response for tunnel models with different flexibility ratios revealed that the tunnels with different flexibility ratios influence the acceleration response at the ground surface in different ways. Tunnels with lower flexibility ratios have higher acceleration responses at short periods, whereas tunnels with higher flexibility ratios have higher acceleration responses at longer periods. The effect of the flexibility ratio on ground surface acceleration is more prominent in the high range of frequencies. Furthermore, as the flexibility ratio of the tunnel system increases, the acceleration response moves away from the free field response and shifts towards the longer periods. Therefore, the flexibility ratio of the underground tunnels influences the peak ground acceleration (PGA) at the ground surface, and may need to be considered in the seismic zonation of urban areas.

  15. Preliminary accelerator plans for maximizing the integrated LHC luminosity

    CERN Document Server

    Benedikt, Michael; Ruggiero, F; Ostojic, R; Scandale, Walter; Shaposhnikova, Elena; Wenninger, J

    2006-01-01

    A working group on "Proton Accelerators for the Future" (PAF) has been created in May 2005 by the CERN direction to elaborate a baseline scenario of the possible development and upgrade of the present Proton Accelerator Complex. This report is the result of the investigation conducted until the end of 2005, in close connection with the working group on "Physics Opportunities with Future Proton Accelerators" (POFPA) and is consistent with their recommendations. Focused on the goal of maximizing the integrated luminosity for the LHC experiments, a scenario of evolution is proposed, subject to further refinement using the future experience of commissioning and running-in the collider and its injector complex. The actions to be taken in terms of consolidation, R & D and improvement are outlined. The benefits for other types of physics are mentioned and will be investigated in more detail in the future.

  16. Electron cloud in the CERN accelerators (PS, SPS, LHC)

    International Nuclear Information System (INIS)

    Iadarola, G; Rumolo, G

    2013-01-01

    Several indicators have pointed to the presence of an Electron Cloud (EC) in some of the CERN accelerators, when operating with closely spaced bunched beams. In particular, spurious signals on the pick ups used for beam detection, pressure rise and beam instabilities were observed at the Proton Synchrotron (PS) during the last stage of preparation of the beams for the Large Hadron Collider (LHC), as well as at the Super Proton Synchrotron (SPS). Since the LHC has started operation in 2009, typical electron cloud phenomena have appeared also in this machine, when running with trains of closely packed bunches (i.e. with spacings below 150ns). Beside the above mentioned indicators, other typical signatures were seen in this machine (due to its operation mode and/or more refined detection possibilities), like heat load in the cold dipoles, bunch dependent emittance growth and degraded lifetime in store and bunch-by-bunch stable phase shift to compensate for the energy loss due to the electron cloud. An overview of the electron cloud status in the different CERN machines (PS, SPS, LHC) will be presented in this paper, with a special emphasis on the dangers for future operation with more intense beams and the necessary countermeasures to mitigate or suppress the effect. (author)

  17. Coldbox installation for HL-LHC crab cavity test in the SPS tunnel (BA6)

    CERN Document Server

    Ordan, Julien Marius

    2018-01-01

    The Cold-box, produced by Linde Kryotechnik for the SPS crab-cavity test stand for HL-LHC, on its arrival at CERN. It wll be transported into the tunnel in horizontal position and then will have to be tilted in its operational position, on its vertical axis, before connecting it to cryogenics lines.

  18. A true-to-life fire alert in the LHC tunnel

    CERN Multimedia

    2008-01-01

    Around 40 men from the fire brigades of CERN and the two Host States were put through their paces in an exercise with a scenario involving a fire between Points 6 and 7 of the LHC tunnel and the mysterious disappearance of a member of personnel.

  19. LHC 2008 lectures
    The LHC: an accelerator of science

    CERN Multimedia

    2008-01-01

    In 2008, CERN will be switching on the greatest physics experiment ever undertaken. The Large Hadron Collider, or LHC, is a particle accelerator that will provide many answers to our questions about the Universe - What is the reason for mass? Where is the invisible matter in the Universe hiding? What is the relationship between matter and antimatter? Will we have to use a theory claiming more than four dimensions? … and what about "time" ? To understand better the raison d’être of the LHC, this gigantic, peerless scientific instrument and all the knowledge it can bring to us, members of the general public are invited to a series of lectures at the Globe of Science and Innovation. Thursday 8 May 2008 at 8.00 p.m. « Comment fonctionne l’Univers ? Ce que le LHC peut nous apprendre » Alvaro de Rujula, CERN physicist Thursday 15 May 2008 at 8.00 p.m. – « Une nouvelle vision du monde » Jean-Pierre Luminet, Director of...

  20. Remotely Operated Train for Inspection and Measurement in CERN's LHC Tunnel

    CERN Document Server

    Kershaw, K; Bestmann, P; Feniet, T; Forkel-Wirth, D; Grenard, J L; Rousset, N

    2010-01-01

    Personnel access to the LHC tunnel will be restricted to varying extents during the life of the machine due to radiation and cryogenic hazards. For this reason a remotely operated modular inspection train, (TIM) running on the LHC tunnel’s overhead monorail has been developed. In order to be compatible with the LHC personnel access system, a small section train that can pass through small openings at the top of sector doors has now been produced. The basic train can be used for remote visual inspection; additional modules give the capability of carrying out remote measurement of radiation levels, environmental conditions around the tunnel, and even remote measurement of the precise position of machine elements such as collimators. The paper outlines the design, development and operation of the equipment including preparation of the infrastructure. Key features of the trains are described along with future developments and intervention scenarios.

  1. Final report on the Controlled Cold Helium Spill Test in the LHC tunnel at CERN

    International Nuclear Information System (INIS)

    Dufay-Chanat, L; Bremer, J; Casas-Cubillos, J; Koettig, T; Vauthier, N; Van Weelderen, R; Winkler, T; Chorowski, M; Grabowski, M; Jedrusyna, A; Lindell, G; Nonis, M

    2015-01-01

    The 27 km circumference LHC underground tunnel is a space in which the helium cooled LHC magnets are installed. The vacuum enclosures of the superconducting magnets are protected by over-pressure safety relief devices that open whenever cold helium escapes either from the magnet cold enclosure or from the helium supply headers, into this vacuum enclosure. A 3-m long no stay zone around these devices is defined based on scale model studies, protecting the personnel against cold burns or asphyxia caused by such a helium release event. Recently, several simulation studies have been carried out modelling the propagation of the helium/air mixture, resulting from the opening of such a safety device, along the tunnel. The released helium flows vary in the range between 1 kg/s and 0.1 kg/s. To validate these different simulation studies, real life mock-up tests have been performed inside the LHC tunnel, releasing helium flow rates of 1 kg/s, 0.3 kg/s and 0.1 kg/s. For each test, up to 1000 liters of liquid helium were released under standard operational tunnel conditions. The data recorded include oxygen concentration, temperature and flow speed measurements, and video footage used to assess qualitatively the visibility. These measurements have been made in the up- and downstream directions, with respect to the air ventilation flow, of the spill point.This paper presents the experimental set-up under which these release tests were made, the effects of these releases on the atmospheric tunnel condition as a function of the release flow rate. We discuss the modification to the personnel access conditions to the LHC tunnel that are presently implemented as a result of these tests. (paper)

  2. Final report on the Controlled Cold Helium Spill Test in the LHC tunnel at CERN

    Science.gov (United States)

    Dufay-Chanat, L.; Bremer, J.; Casas-Cubillos, J.; Chorowski, M.; Grabowski, M.; Jedrusyna, A.; Lindell, G.; Nonis, M.; Koettig, T.; Vauthier, N.; van Weelderen, R.; Winkler, T.

    2015-12-01

    The 27 km circumference LHC underground tunnel is a space in which the helium cooled LHC magnets are installed. The vacuum enclosures of the superconducting magnets are protected by over-pressure safety relief devices that open whenever cold helium escapes either from the magnet cold enclosure or from the helium supply headers, into this vacuum enclosure. A 3-m long no stay zone around these devices is defined based on scale model studies, protecting the personnel against cold burns or asphyxia caused by such a helium release event. Recently, several simulation studies have been carried out modelling the propagation of the helium/air mixture, resulting from the opening of such a safety device, along the tunnel. The released helium flows vary in the range between 1 kg/s and 0.1 kg/s. To validate these different simulation studies, real life mock-up tests have been performed inside the LHC tunnel, releasing helium flow rates of 1 kg/s, 0.3 kg/s and 0.1 kg/s. For each test, up to 1000 liters of liquid helium were released under standard operational tunnel conditions. The data recorded include oxygen concentration, temperature and flow speed measurements, and video footage used to assess qualitatively the visibility. These measurements have been made in the up- and downstream directions, with respect to the air ventilation flow, of the spill point. This paper presents the experimental set-up under which these release tests were made, the effects of these releases on the atmospheric tunnel condition as a function of the release flow rate. We discuss the modification to the personnel access conditions to the LHC tunnel that are presently implemented as a result of these tests.

  3. Some LHC milestones...

    CERN Multimedia

    2008-01-01

    October 1995 The LHC technical design report is published. This document details the operation and the architecture of the future accelerator. November 2000 The first of the 1232 main dipole magnets for the LHC are delivered. May 2005 The first interconnection between two magnets of the accelerator is made. To carry out the 1700 interconnections of the LHC, 123 000 operations are necessary. February 2006 The new CERN Control Centre, which combines all the control rooms for the accelerators, the cryogenics and the technical infrastructure, starts operation. The LHC will be controlled from here. October 2006 Construction of the largest refrigerator in the world is complete. The 27 km cryogenic distribution line inside the LHC tunnel will circulate helium in liquid and gas phases to provide cryogenic conditions for the superconducting magnets of the accelerator. November 2006 Magnet production for the LHC is complete. The last of t...

  4. Discovery Mondays - 'The LHC: an accelerator of science'

    CERN Multimedia

    2006-01-01

    Is the LHC about to turn the theories of the infinitesimally small on their heads? Whether or not this proves to be the case, physicists hope that the 27-kilometre-long accelerator due to be commissioned at the end of 2007 will shake up the Standard Model. This theory, which describes elementary particles and forces, leaves many questions unanswered. The LHC and its experiments have been designed to shed light on them. Unresolved questions include how elementary particles acquire mass and why their masses differ. The disappearance of antimatter from our Universe is another such mystery. Physicists want to know what matter was like just after the Big Bang and what the dark matter in the Universe could be: only 5% of the matter of the Universe is visible, and the effects of gravity indicate the presence of another type of matter that cannot be seen by the instruments available today. The theory of supersymmetry, which predicts that each particle has a corresponding superparticle, could go some way towards exp...

  5. Quench simulations for superconducting elements in the LHC accelerator

    Science.gov (United States)

    Sonnemann, F.; Schmidt, R.

    2000-08-01

    The design of the protection system for the superconducting elements in an accelerator such as the large Hadron collider (LHC), now under construction at CERN, requires a detailed understanding of the thermo-hydraulic and electrodynamic processes during a quench. A numerical program (SPQR - simulation program for quench research) has been developed to evaluate temperature and voltage distributions during a quench as a function of space and time. The quench process is simulated by approximating the heat balance equation with the finite difference method in presence of variable cooling and powering conditions. The simulation predicts quench propagation along a superconducting cable, forced quenching with heaters, impact of eddy currents induced by a magnetic field change, and heat transfer through an insulation layer into helium, an adjacent conductor or other material. The simulation studies allowed a better understanding of experimental quench data and were used for determining the adequate dimensioning and protection of the highly stabilised superconducting cables for connecting magnets (busbars), optimising the quench heater strip layout for the main magnets, and studying quench back by induced eddy currents in the superconductor. After the introduction of the theoretical approach, some applications of the simulation model for the LHC dipole and corrector magnets are presented and the outcome of the studies is compared with experimental data.

  6. Rock samples from LEP/LHC tunnel excavation

    CERN Multimedia

    1985-01-01

    Rock samples taken from 0 to 170 m below ground on the CERN site when the LEP (Large Electron Positron collider) pit number 6 was drilled in Bois-chatton (Versonnex). The challenges of LHC civil engineering: A mosaic of works, structures and workers of differents crafts and origins. Three consulting consortia for the engineering and the follow-up of the works. Four industrial consortia for doing the job. A young team of 25 CERN staff, 30 surface buildings, 32 caverns of all sizes, 170 000 m3 of concrete, 420 000 m3 excavated. 1998-2004 : six years of work and 340 millions Swiss Francs.

  7. The Real-Time Data Analysis and Decision System for Particle Flux Detection in the LHC Accelerator at CERN.

    CERN Document Server

    Zamantzas, C; Dehning, B

    2006-01-01

    The superconducting Large Hadron Collider (LHC) under construction at the European Organisation for Nuclear Research (CERN) is an accelerator unprecedented in terms of beam energy, particle production rate and also in the potential of self-destruction. Its operation requires a large variety of instrumentation, not only for the control of the beams, but also for the protection of the complex hardware systems. The Beam Loss Monitoring (BLM) system has to prevent the superconducting magnets from becoming normal conducting and protect the machine components against damages making it one of the most critical elements for the protection of the LHC. For its operation, the system requires 3600 detectors to be placed at various locations around the 27 km ring. The measurement system is sub-divided to the tunnel electronics, which are responsible for acquiring, digitising and transmitting the data, and the surface electronics, which receive the data via 2 km optical data links, process, analyze, store and issue warning...

  8. Biocell Training course mandatory for accessing the LHC tunnel from 1 December 2010

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    Following the incident in Sector 3-4 on 19 September 2008, which led to a major helium release in the LHC tunnel, measures have been put in place to reinforce safety awareness and training for all those accessing the tunnel.   One of the actions taken was to create a hands-on safety course on how to put the Self Rescue Breathing Apparatus (Biocell) on. The course is entitled “Biocell Training” and started late summer 2009. To date some 1350 people have been trained, although roughly 1700 people have access to the LHC machine tunnel. With the training capacity in place, it is feasible to train everyone with access before the coming Christmas technical stop, which will start in December 2010. The “Biocell Training” course has clearly shown the necessity of training the personnel. In addition, the feedback from the participants is very positive. Decision In the light of the conclusion reached by HSE, DSOs and the GLIMOS of the LHC experiments, successful comple...

  9. Final report on the Controlled Cold Helium Spill Test in the LHC tunnel at CERN

    CERN Document Server

    Dufay-Chanat, L; Casas-Cubillos, J; Chorowski, M; Grabowski, M; Jedrusyna, A; Lindell, G; Nonis, M; Koettig, T; Vauthier, N; van Weelderen, R; Winkler, T

    2015-01-01

    The 27 km circumference LHC underground tunnel is a space in which the helium cooled LHC magnets are installed. The vacuum enclosures of the superconducting magnets are protected by over-pressure safety relief devices that open whenever cold helium escapes either from the magnet cold enclosure or from the helium supply headers, into this vacuum enclosure. A 3-m long no stay zone around these devices is defined based on scale model studies, protecting the personnel against cold burns or asphyxia caused by such a helium release event. Recently, several simulation studies have been carried out modelling the propagation of the helium/air mixture, resulting from the opening of such a safety device, along the tunnel. The released helium flows vary in the range between 1 kg/s and 0.1 kg/s. To validate these different simulation studies, real life mock-up tests have been performed inside the LHC tunnel, releasing helium flow rates of 1 kg/s, 0.3 kg/s and 0.1 kg/s. For each test, up to 1000 liters of liquid helium wer...

  10. Cryogenic Risk Assessments before Works in the LHC Tunnel

    CERN Multimedia

    CERN. Geneva

    2016-01-01

    Tests conducted in 2013/4 demonstrated that a small, residual risk to expose personnel to a helium spill exists in the LHC. Helium spills with a mass flow of less than 100 g s^-1 could be caused by workers accidentally damaging sensitive equipment in the cryogenic distribution system, such as instrumentation feedthroughs. In order to control this risk, a cryogenic risk assessment for all works taking place in the vicinity of such sensitive equipment is mandatory. The risk assessment and its recommendations are approved by the hierarchy and the complex manager before work can start. After introducing the risk assessment procedure, I will give some feedback on its implementation and present status.

  11. The Control System for the Cryogenics in the LHC Tunnel

    CERN Document Server

    Gomes, P; Antoniotti, F; Avramidou, R; Balle, Ch; Blanco-Viñuela, E; Carminati, Ch; Casas-Cubillos, J; Ciechanowski, M; Dragoneas, A; Dubert, P; Fampris, X; Fluder, C; Fortescue, E; Gaj, W; Gousiou, E; Jeanmonod, N; Jodłowski, P; Karagiannis, F; Klisch, M; López, A; Macuda, P; Malinowski, P; Molina, E; Paiva, S; Patsouli, A; Penacoba, G; Sosin, M; Soubiran, M; Suraci, A; Tovar, A; Vauthier, N; Wolak, T; Zwalinski, L

    2009-01-01

    The Large Hadron Collider makes extensive use of superconductors, in magnets for bending and focusing the particles, and in RF cavities for accelerating them, which are operated at 1.9 K and 4.5 K. The process automation for the cryogenic distribution around the accelerator circumference is based on 16 Programmable Logic Controllers, each running 250 control loops, 500 alarms and interlocks, and a phase sequencer. Spread along 27 km and under ionizing radiation, 15 000 cryogenic sensors and actuators are accessed through industrial field networks. We describe the main hardware and software components of the control system, their deployment and commissioning, together with the project organization, challenges faced, and solutions found.

  12. ST/EL and ST/CV services for TI2 & TI8 LHC injection tunnels

    CERN Document Server

    Akhtar, S; CERN. Geneva. ST Division

    2002-01-01

    This paper describes the ST/EL and ST/CV services for TI2 & TI8 LHC injection tunnels. The cooling and ventilation part describes the requirements for design and installation of more than 10 km of pipeline that is going to be laid down in the tunnels. Main operating parameters as well as manufacture procedures are explained. Preliminary work schedule with the cost estimate is also presented. Electrical power will be distributed from the LHC side and the SPS side for the machine and the general services. All power converters will be installed on surface buildings. The link between the main bend converters and the main bend magnets will be realised with water-cooled cables. Rest of the magnets will be cabled by using conventional copper and aluminium cables. Due to long lengths of the injection tunnels a dry 18kV transformer will be installed in TJ8 to serve the general services for TI8. The same will apply to TI2 by installing a transformer at the bottom of the PMI2 shaft.

  13. LHC: Collisions on course for 2007

    CERN Document Server

    2006-01-01

    In the LHC tunnel and caverns, a particle accelerator and detectors are rapidly taking shape. At last week's Council meeting, delegates took stock of the year's progress towards first collisions in 2007.

  14. QPS/LHC Activities requiring important Tunnel Work During a future long Shutdown

    CERN Document Server

    Dahlerup-Petersen, K

    2011-01-01

    The MPE/circuit protection section is presently establishing a road map for its future LHC activities. The tasks comprise essential consolidation work, compulsory upgrades and extensions of existing machine facilities. The results of a first round of engineering exertion were presented and evaluated at a MPE activity review in December 2010. The technical and financial aspects of this program will be detailed in the ‘QPS Medium and Long-Term Improvement Plan’, to be published shortly. The QPS activities in the LHC tunnel during a future, long shutdown are closely related to this improvement chart. A project-package based program for the interventions has been established and will be presented in this report, together with estimates for the associated human and financial resources necessary for its implementation.

  15. The Development of the Control System for the Cryogenics in the LHC Tunnel

    CERN Document Server

    Fluder, C; Casas-Cubillos, J; Dubert, P; Gomes, P; Pezzetti, M; Tovar-Gonzalez, A; Zwalinski, L

    2011-01-01

    The Large Hadron Collider (LHC) was commissioned at CERN and started operation with beams in 2008. The LHC makes extensive use of superconductors, in magnets, electrical feed boxes and accelerating cavities, which are operated at cryogenic temperatures. The process automation for the cryogenic distribution around the 27 km accelerator circumference is based on 18 Programmable Logic Controllers (PLCs); overall, they handle 4 000 control loops and 8 000 alarms and interlocks; 16 000 cryogenic sensors and actuators are accessed through industrial field networks. This paper reviews the control system architecture and the main hardware and software components; presents the hardware commissioning and software production methodologies; and illustrates some of the problems faced during development, commissioning and nominal cryogenics operation, together with the solutions applied.

  16. Powering and Machine Protection of the Superconducting LHC Accelerator

    OpenAIRE

    Zerlauth, M; Schmidt, R

    2004-01-01

    A very large number of magnets, both superconducting and conventional copper conductor magnets, are installed in the LHC (Large Hadron Collider) for the guidance of the two proton beams around the circumference. In total, the LHC counts 1614 different electrical circuits with 1712 power converters for DC powering of the superconducting and normal conducting magnets. Besides the electrical circuits connecting main magnets for bending and focusing of the two counter-rotating beams, the demandin...

  17. Displacement measurements in the cryogenically cooled dipoles of the new CERN-LHC particle accelerator

    CERN Document Server

    Inaudi, D; Scandale, Walter; Pérez, J G; Billan, J; Redaelli, S

    2001-01-01

    The LHC will use the most advanced superconducting magnet and accelerator technologies ever employed. One of the main challenges in this new machine resides in the design and production of the superconducting dipoles used to steer the particles around the 27 km underground tunnel. These so-called cryodipoles are composed of an external vacuum tube and an insert, appropriately named the cold mass, that contains the particle tubes, the superconducting coil and will be cooled using superfluid helium to 1.9 K. The particle beam must be placed inside the magnetic field with a submillimeter accuracy; this requires in turn that the relative displacements between the vacuum tube and the cold-mass must be monitored with accuracy. Due to the extreme condition environmental conditions (the displacement measurement must be made in vacuum and between two points with a temperature difference of more than 200 degrees C) no adequate existing monitoring system was found for this application. It was therefore decided to develo...

  18. Flat bunch creation and acceleration: a possible path for the LHC luminosity upgrade

    International Nuclear Information System (INIS)

    Bhat, C.M.

    2009-01-01

    Increasing the collider luminosity by replacing bunches having Gaussian line-charge distribution with flat bunches, but with same beam-beam tune shift at collision, has been studied widely in recent years. But, creation of 'stable' flat bunches (and their acceleration) using a multiple harmonic RF system has not been fully explored. Here, we review our experience with long flat bunches in the barrier RF buckets at Fermilab.We presentsome preliminary results from beam dynamics simulations and recent beam studies in the LHC injectors to create stable flat bunches using double harmonic RF systems. The results deduced from these studies will be used to model the necessary scheme for luminosity upgrade in the LHC. We have also described a viable (and economical) way for creation and acceleration of flat bunches in the LHC. The flat bunch scheme may have many advantages over the LHC baseline scenario, particularly because of the reduced momentum spread of the bunch for increased intensities.

  19. Powering and Machine Protection of the Superconducting LHC Accelerator

    CERN Document Server

    Zerlauth, M

    2004-01-01

    A very large number of magnets, both superconducting and conventional copper conductor magnets, are installed in the LHC (Large Hadron Collider) for the guidance of the two proton beams around the circumference. In total, the LHC counts 1614 different electrical circuits with 1712 power converters for DC powering of the superconducting and normal conducting magnets. Besides the electrical circuits connecting main magnets for bending and focusing of the two counter-rotating beams, the demanding requirements on the quality of the magnetic fields require a large number of circuits for corrector magnets distributed around the circumference. In total, more than 10000 magnets will need to be connected to the power converters via a large inventory of electrical components such as normal conducting cables and tubes, energy extraction systems, current feedthroughs and superconducting busbars. Depending on the complexity and importance of these electrical circuits and their components, various systems will interact for...

  20. Excavating a transfer tunnel

    CERN Multimedia

    Laurent Guiraud

    2000-01-01

    The transfer tunnel being dug here will take the 450 GeV beam from the SPS and inject it into the LHC where the beam energies will be increased to 7 TeV. In order to transfer this beam from the SPS to the LHC, two transfer tunnels are used to circulate the beams in opposite directions. When excavated, the accelerator components, including magnets, beam pipes and cryogenics will be installed and connected to both the SPS and LHC ready for operation to begin in 2008.

  1. The surveyors get the measure of the LHC

    CERN Multimedia

    2002-01-01

    The first to start work in the LHC tunnel, the surveyors are precisely marking out the positions of the future accelerator's magnets. A total of 7000 reference points will have to be marked out over two years.

  2. Work on a transfer tunnel access shaft

    CERN Multimedia

    Laurent Guiraud

    2000-01-01

    Civil engineers work on one of the access shafts from the SPS to the LHC transfer tunnel, which will allow components and equipment to be lowered directly so that minimal transport is required. The transfer tunnel will take a proton beam from the SPS pre-accelerator and inject it into the clockwise circulating ring in the LHC where the beam will be accelerated to a final energy of 7 TeV.

  3. Activation Assessment of the Soil Around the ESS Accelerator Tunnel

    Energy Technology Data Exchange (ETDEWEB)

    Rakhno, I. L. [Fermilab; Mokhov, N. V. [Fermilab; Tropin, I. S. [Fermilab; Ene, D. [ESS, Lund

    2017-01-01

    Activation of the soil surrounding the ESS accelerator tunnel calculated by the MARS15 code is presented. A detailed composition of the soil, that comprises about 30 different chemical elements, is considered. Spatial distributions of the produced activity are provided in both transverse and longitudinal direction. A realistic irradiation profile for the entire planned lifetime of the facility is used. The nuclear transmutation and decay of the produced radionuclides is calculated with the DeTra code which is a built-in tool for the MARS15 code. Radionuclide production by low-energy neutrons is calculated using the ENDF/B-VII evaluated nuclear data library. In order to estimate quality of this activation assessment, a comparison between calculated and measured activation of various foils in a similar radiation environment is presented.

  4. Magnet R and D for the US LHC Accelerator Research Program (LARP)

    International Nuclear Information System (INIS)

    Gourlay, S.A.; Ambrosio, G.; Andreev, N.; Anerella, M.; Barzi, E.; Bossert, R.; Caspi, S.; Dietderich, D.R.; Ferracin, P.; Gupta, R.; Ghosh, A.; Hafalia, A.R.; Hannaford, C.R.; Harrison, M.; Kashikhin, V.S.; Kashikhin, V.V.; Lietzke, A.F.; Mattafirri, S.; McInturff, A.D.; Nobrega, F.; Novitsky, I.; Sabbi, G.L.; Schmazle, J.; Stanek, R.; Turrioni, D.; Wanderer, P.; Yamada, R.; Zlobin, A.V.

    2006-01-01

    In 2004, the US DOE established the LHC Accelerator Research Program (LARP) with the goal of developing a technology base for future upgrades of the LHC. The focus of the magnet program, which is a collaboration of three US laboratories, BNL, FNAL and LBNL, is on development of high gradient quadrupoles using Nb 3 Sn superconductor. Other program components address issues regarding magnet design, radiation-hard materials, long magnet scale-up, quench protection, fabrication techniques and conductor and cable R and D. This paper presents an overall view of the program with emphasis on the current quadrupole project and outlines the long-term goals of the program

  5. Quench simulations for superconducting elements in the LHC accelerator

    CERN Document Server

    Sonnemann, F

    2000-01-01

    The design of he protection system for he superconducting elements in an accel- erator such as the Large Hadron Collider (LHC),now under construction at CERN, requires a detailed understanding of the hermo-hydraulic and electrodynamic pro- cesses during a quench.A numerical program (SPQR -Simulation Program for Quench Research)has been developed o evaluate temperature and voltage dis ri- butions during a quench as a func ion of space and ime.The quench process is simulated by approximating the heat balance equation with the finite di fference method in presence of variable cooling and powering conditions.The simulation predicts quench propagation along a superconducting cable,forced quenching with heaters,impact of eddy curren s induced by a magnetic field change,and heat trans- fer hrough an insulation layer in o helium,an adjacen conductor or other material. The simulation studies allowed a better understanding of experimental quench data and were used for determining the adequ...

  6. Electromagnetic and mechanical design of a 56 mm aperture mode dipole for the LHC

    International Nuclear Information System (INIS)

    Ahlbaeck, J.; Ikaeheimo, J.; Jaervi, J.

    1994-01-01

    The Large Hadron Collider (LHC) project is proposed as the future extension of the CERN accelerator complex. The LHC requires twin aperture superconducting dipoles of highest possible field to guide the proton beams in the existing LEP tunnel of 26.7 km circumference. This paper describes the electromagnetic and mechanical design of a 56 mm aperture model dipole for the LHC

  7. Superconducting link bus design for the accelerator project for upgrade of LHC

    International Nuclear Information System (INIS)

    Nobrega, F.; Brandt, J.; Cheban, S.; Feher, S.; Kaducak, M.; Kashikhin, V.; Peterson, T.

    2011-01-01

    The Accelerator Project for Upgrade of LHC (APUL) is a U.S. project participating in and contributing to CERN's Large Hadron Collider (LHC) upgrade program. Fermi National Accelerator Laboratory in collaboration with Brookhaven National Laboratory was developing sub-systems for the upgrade of the LHC final focus magnet systems. Part of the upgrade called for various lengths of superconducting power transmission lines known as SC Links which were up to 100 m long. The SC Link electrically connects the current leads in the Distribution Feed Boxes to the interaction region magnets. The SC Link is an extension of the magnet bus housed within a cryostat. The present concept for the bus consists of 22 power cables, 4 x 13 kA, 2 x 7 kA, 8 x 2.5 kA and 8 x 0.6 kA bundled into one bus. Different cable and strand possibilities were considered for the bus design including Rutherford cable. The Rutherford cable bus design potentially would have required splices at each sharp elbow in the SC Link. The advantage of the round bus design is that splices are only required at each end of the bus during installation at CERN. The round bus is very flexible and is suitable for pulling through the cryostat. Development of the round bus prototype and of 2 splice designs is described in this paper. Magnetic analysis and mechanical test results of the 13 kA cable and splices are presented.

  8. Restart of the LHC. CERN and the accelerators. The world machine illustratively explained; Neustart des LHC. CERN und die Beschleuniger. Die Weltmaschine anschaulich erklaert

    Energy Technology Data Exchange (ETDEWEB)

    Hauschild, Michael

    2016-07-01

    The following topics are dealt with: The development of the European research center for particle physics CERN, the standard model of elementary-particle physics, the detection of the W and Z bosons with the SPS collider, the principles of particle accelerators, the way to the LHC. (HSI)

  9. LHC Magnet test failure

    CERN Multimedia

    2007-01-01

    "On Tueday, March 22, a Fermilab-built quadrupole magnet, one of an "inner triplet" of three focusing magnets, failed a high-pressure test at Point 5 in the tunnel of the LHC accelerator at CERN. Since Tuesday, teams at CERN and Fermilab have worked closely together to address the problem and have identified the cause of the failure. Now they are at work on a solution.:" (1 page)

  10. Support for the LHC experiments

    CERN Document Server

    Butin, François; Gastal, M; Lacarrère, D; Macina, D; Perrot, A L; Tsesmelis, E; Wilhelmsson, M; CERN. Geneva. TS Department

    2008-01-01

    Experimental Area Teams have been put in place and charged with the general co-ordination and management of the LHC experimental areas and of the zones in the LHC tunnel hosting near-beam detectors of the experiments. This organization is responsible for the in situ co-ordination of work with the aim of providing a structure that enables the experiment collaborations and accelerator groups to carry out their work effectively and safely. This presentation will review some key elements in the support given to the LHC experimental areas and, given the track record and successful implementation during the LHC installation and commissioning phase, will argue that such an organization structure will be required also for the period of LHC exploitation for physics.

  11. Remote Inspection, Measurement and Handling for LHC

    CERN Document Server

    Kershaw, K; Coin, A; Delsaux, F; Feniet, T; Grenard, J L; Valbuena, R

    2007-01-01

    Personnel access to the LHC tunnel will be restricted to varying extents during the life of the machine due to radiation, cryogenic and pressure hazards. The ability to carry out visual inspection, measurement and handling activities remotely during periods when the LHC tunnel is potentially hazardous offers advantages in terms of safety, accelerator down time, and costs. The first applications identified were remote measurement of radiation levels at the start of shut-down, remote geometrical survey measurements in the collimation regions, and remote visual inspection during pressure testing and initial machine cool-down. In addition, for remote handling operations, it will be necessary to be able to transmit several real-time video images from the tunnel to the control room. The paper describes the design, development and use of a remotely controlled vehicle to demonstrate the feasibility of meeting the above requirements in the LHC tunnel. Design choices are explained along with operating experience to-dat...

  12. First Assessment of Reliability Data for the LHC Accelerator and Detector Cryogenic System Components

    CERN Document Server

    Perinic, G; Alonso-Canella, I; Balle, C; Barth, K; Bel, J F; Benda, V; Bremer, J; Brodzinski, K; Casas-Cubillos, J; Cuccuru, G; Cugnet, M; Delikaris, D; Delruelle, N; Dufay-Chanat, L; Fabre, C; Ferlin, G; Fluder, C; Gavard, E; Girardot, R; Haug, F; Herblin, L; Junker, S; Klabi , T; Knoops, S; Lamboy, J P; Legrand, D; Metselaar, J; Park, A; Perin, A; Pezzetti, M; Penacoba-Fernandez, G; Pirotte, O; Rogez, E; Suraci, A; Stewart, L; Tavian, L J; Tovar-Gonzalez, A; Van Weelderen, R; Vauthier, N; Vullierme, B; Wagner, U

    2012-01-01

    The Large Hadron Collider (LHC) cryogenic system comprises eight independent refrigeration and distribution systems that supply the eight 3.3 km long accelerator sectors with cryogenic refrigeration power as well as four refrigeration systems for the needs of the detectors ATLAS and CMS. In order to ensure the highest possible reliability of the installations, it is important to apply a reliability centred approach for the maintenance. Even though large scale cryogenic refrigeration exists since the mid 20th century, very little third party reliability data is available today. CERN has started to collect data with its computer aided maintenance management system (CAMMS) in 2009, when the accelerator has gone into normal operation. This paper presents the reliability observations from the operation and the maintenance side, as well as statistical data collected by the means of the CAMMS system.

  13. The LHC at level best

    CERN Multimedia

    Katarina Anthony

    2013-01-01

    On 10 March, a team of CERN surveyors descended into the LHC tunnel. Their aim: to take measurements of the height of the LHC magnets to see how geological shifts might be affecting the machine and to take reference positions of the machine before the interconnects are opened.    CERN surveyors take levelling measurements of the LHC magnets during LS1. The LHC tunnel is renowned for its geological stability: set between layers of sandstone and molasse, it has allowed the alignment of the world’s largest accelerators to be within sub-millimetre precision. But even the most stable of tunnels can be affected by geological events. To ensure the precise alignment of the LHC, the CERN survey team performs regular measurements of the vertical position of the magnets (a process known as “levelling”). Over the past month, the team has been taking measurements of the LHC before the temperature of the magnets reaches 100 K, beyond which there may be some mechanic...

  14. Accelerators

    CERN Multimedia

    CERN. Geneva

    2001-01-01

    The talk summarizes the principles of particle acceleration and addresses problems related to storage rings like LEP and LHC. Special emphasis will be given to orbit stability, long term stability of the particle motion, collective effects and synchrotron radiation.

  15. Installation of wireless LAN system into the SuperKEKB accelerator tunnel

    International Nuclear Information System (INIS)

    Iwasaki, Masako; Satoh, Masanori

    2014-01-01

    We have installed a wireless LAN system of the accelerator control network into the accelerator tunnel for SuperKEKB, which is the upgrade plan of the KEKB B-factory project. The wireless LAN system is used for the construction and maintenance of the accelerator components. The leaky coaxial cable (LCX) antennas are installed into the arc sections of SuperKEKB tunnel, and the collinear antennas are installed into the straight sections and the injector Linac. We have selected the LCX and collinear antennas with good radiation hardness of more than 1 MGy. After the installation, we evaluated the wireless LAN system and obtained the good network speed performance in the whole tunnel area. (author)

  16. Maintenance des équipements de transport pour l'installation des cryo-aimants dans le tunnel LHC

    CERN Document Server

    Chevalley, JM

    2005-01-01

    Le transport et l’installation de quelque 1800 cryo-aimants dans le tunnel LHC seront réalisés à l’aide d’équipements de transport et de manutention de haute technologie spécialement développés par le groupe TS-IC. La section HM devra assurer la maintenance de toute cette chaîne d’équipements : le pont roulant pour la descente des cryo-aimants dans le tunnel LHC, les véhicules de transport spéciaux alimentés dans le tunnel par la gaine monorail et enfin les tables de transfert utilisées pour la mise en place finale des cryo-aimants sur leurs vérins. Dans ce cadre, plusieurs aspects seront développés dans ce document : la mise en place et l’organisation de la maintenance, l’analyse des modes de défaillance et de leur criticité (AMDEC), les différentes méthodes possibles pour la recherche et résolution des pannes, ainsi que le suivi du projet, et ce dans le but de fiabiliser et d†™assurer le bon fonctionnement de t...

  17. Wall-Current-Monitor based Ghost and Satellite Bunch Detection in the CERN PS and the LHC Accelerators

    CERN Document Server

    Steinhagen, R J; Belleman, J; Bohl, T; Damerau, H

    2012-01-01

    While most LHC detectors and instrumentation systems are optimised for a nominal bunch spacing of 25 ns, the LHC RF cavities themselves operate at the 10th harmonic of the maximum bunch frequency. Due to the beam production scheme and transfers in the injector chain, part of the nominally ‘empty’ RF buckets may contain particles, referred to as ghost or satellite bunches. These populations must be accurately quantified for high-precision experiments, luminosity calibration and control of parasitic particle encounters at the four LHC interaction points. This contribution summarises the wall-current-monitor based ghost and satellite bunch measurements in CERN’s PS and LHC accelerators. Instrumentation set-up, post-processing and achieved performance are discussed.

  18. Some of the QRL team in UJ22 of the LHC tunnel, where the last sector of the cryogenic distribution line was installed.

    CERN Multimedia

    Viviane Li

    2006-01-01

    The cryogenic distribution line "the QRL" is a circle built in 8 sectors, each approximately 3 km in length. It will circulate helium in liquid and gas phases, at different temperatures and pressures, to provide the cryogenic conditions for the superconducting magnets in the LHC tunnel.

  19. Further analysis of MHD acceleration for a hypersonic wind tunnel

    International Nuclear Information System (INIS)

    Christiansen, M.J.; Schmidt, H.J.; Chapman, J.N.

    1995-01-01

    A previously completed MHD study of the use of an MHD accelerator with seeded air from a state-of-the-art arc heater, was generally hailed as showing that the system studied has some promise of meeting the most critical hypersonic testing requirements. However, some concerns existed about certain aspects of the results. This paper discusses some of these problems and presents analysis of potential solutions. Specifically the problems addressed are; reducing the amount of seed in the flow, reducing test chamber temperatures, and reducing the oxygen dissociation. Modeling techniques are used to study three design variables of the MHD accelerator. The accelerator channel inlet Mach number, the accelerator channel divergence angle, and the magnetic field strength are all studied. These variables are all optimized to meet the goals for seed, temperature, and dissociated oxygen reduction. The results of this paper are encouraging, showing that all three goals can be met. General relationships are observed as to how the design variables affect the performance of the MHD accelerator facility. This paper expands on the results presented in the UTSI report and further supports the feasibility of MHD acceleration as a means to provide hypersonic flight simulation

  20. A large scale flexible real-time communications topology for the LHC accelerator

    CERN Document Server

    Lauckner, R J; Ribeiro, P; Wijnands, Thijs

    1999-01-01

    The LHC design parameters impose very stringent beam control requirements in order to reach the nominal performance. Prompted by the lack of accurate models to predict field behaviour in superconducting magnet systems the control system of the accelerator will provide flexible feedback channels between monitors and magnets around the 27 Km circumference machine. The implementation of feedback systems composed of a large number of sparsely located elements presents some interesting challenges. Our goal was to find a topology where the control loop requirements: number and distribution of nodes, latency and throughput could be guaranteed without compromising the flexibility. Our proposal is to federate a number of well known technologies and concepts, namely ATM, WorldFIP and RTOS, into a general framework. (6 refs).

  1. Design of a 0-50 mbar pressure measurement channel compatible with the LHC tunnel radiation environment

    Science.gov (United States)

    Casas, Juan; Jelen, Dorota; Trikoupis, Nikolaos

    2017-02-01

    The monitoring of cryogenic facilities often require the measurement of pressure in the sub 5’000 Pa range that are used for flow metering applications, for saturated superfluid helium, etc. The pressure measurement is based on the minute displacement of a sensing diaphragm often through contactless techniques by using capacitive or inductive methods. The LHC radiation environment forbid the use of standard commercial sensors because of the embedded electronics that are affected both by radiation induced drift and transient Single Event Effects (SEE). Passive pressure sensors from two manufacturers were investigated and a CERN designed radiation-tolerant electronics has been developed for measuring variable-reluctance sensors. During the last maintenance stop of the LHC accelerator, four absolute pressure sensors were installed in some of the low pressure bayonet heat exchangers and four differential pressure sensors on the venturi flowmeters that monitor the cooling flow of the 20.5 kA current leads of the ATLAS end-cap superconducting toroids. The pressure sensors operating range is about 1000 to 5000 Pa and the targeted uncertainty is +/- 50 Pa which would permit to measure the equivalent saturation temperature at 1.8 K within better than 0.01 K. This paper describes the radiation hard measuring head that is based on an inductive bridge, its associated radiation-tolerant electronics that is installed under the LHC superconducting magnets or the ATLAS detector cavern; and the first operational experience.

  2. Radioactive airborne species formed in the air in high energy accelerator tunnels

    International Nuclear Information System (INIS)

    Kondo, K.

    2005-01-01

    Many radioactive airborne species have been observed in the air of high energy accelerator tunnels during machine operation. Radiation protection against these induced airborne radioactivities is one of the key issues for radiation safety, especially at high-energy and high-intense proton accelerators such as the J-PARC (Japan Proton Accelerator Research Complex, Joint project of KEK and JAERI), which is now under construction at the TOKAI site of JAERI. Information on the chemical forms and particle sizes of airborne radioactivities is essential for the estimation of internal doses. For that purpose, the study on radioactive airborne species formed in the air of beam-line tunnels at high-energy accelerators have been extensively conducted by our group. For Be-7, Na-24, S-38, Cl-38,-39, C-11, and N-13, formed by various types of nuclear reactions including nuclear spallation reactions, their aerosol and gaseous fractions are determined by a filter technique. A parallel plate diffusion battery is used for the measurement of aerosol size distributions, and the formation of radioactive aerosols is explained by the attachment of radionuclides to ambient non-radioactive aerosols which are formed through radiation induced reactions. The chemical forms of gaseous species are also determined by using a selective collection method based on a filter technique. A review is given of the physico-chemical properties of these airborne radionuclides produced in the air of accelerator beam-line tunnels.

  3. Accelerator physics studies on the effects from an asynchronous beam dump onto the LHC experimental region collimators

    CERN Document Server

    Lari, L; Boccone, V; Bruce, R; Cerutti, F; Rossi, A; Vlachoudis, V; Mereghetti, A; Faus-Golfe, A

    2012-01-01

    Asynchronous beam aborts at the LHC are estimated to occur on average once per year. Accelerator physics studies of asynchronous dumps have been performed at different beam energies and beta-stars. The loss patterns are analyzed in order to identify the losses in particular on the Phase 1 Tertiary Collimators (TCT), since their tungsten-based active jaw insert has a lower damage threshold than the carbon-based other LHC collimators. Settings of the tilt angle of the TCTs are discussed with the aim of reducing the thermal loads on the TCT themselves.

  4. Remote Qualification of HLS and WPS Systems in the LHC Tunnel

    CERN Document Server

    Mainaud Durand, Helene; Marin, Antonio; Rousseau, Michel; Sosin, Mateusz

    2014-01-01

    The position of the inner triplets of the LHC is monitored using Hydrostatic Levelling System (HLS) and Wire Positioning System (WPS). A regulation of these systems is needed to guarantee the sensors’ function. Such a regulation was done in-situ up to now, but the level of residual radiation at the level of the inner triplets will significantly increase with the next steps of LHC operation. Two systems have been designed to perform such a remote qualification: a filling/purging system for the HLS system and a wire displacer system for the WPS. In the paper, the requirements and the solutions proposed are described, with the emphasis on the conceptual design and the results obtained.

  5. The Control System for the Cryogenics in the LHC Tunnel [First Experience and Improvements

    CERN Document Server

    Gomes, P; Casas, J; Fluder, C; Fortescue, E; Le Roux, P; Penacoba, G; Pezzetti, M; Soubiran, M; Tovar, A; Zwalinski, L

    2010-01-01

    The Large Hadron Collider (LHC) was commissioned at CERN and started operation with beams in 2008. Several months of operation in nominal cryogenic conditions have triggered an optimisation of the process functional analysis. This lead to a few revisions of the control logic, which were realised on-the-fly. During the 2008-09 shut-down, and in order to enhance the safety, availability and operability of the LHC cryogenics, a major rebuild of the logic and several hardware modifications were implemented. The databases, containing instruments and controls in-formation, are being rationalized; the automatic tool, that extracts data for the control software, is being simplified. This paper describes the main improvements and sug-gests perspectives of further developments.

  6. 16 February 2012 - Chinese Taipei Ambassador to Switzerland F. Hsieh in the ATLAS visitor centre, ATLAS experimental area and LHC tunnel at Point 1 with Collaboration Deputy Sookesperson A. Lankford, throughout accompanied by International Relations Adviser R. Voss.

    CERN Multimedia

    Jean-Claude Gadmer

    2012-01-01

    16 February 2012 - Chinese Taipei Ambassador to Switzerland F. Hsieh in the ATLAS visitor centre, ATLAS experimental area and LHC tunnel at Point 1 with Collaboration Deputy Sookesperson A. Lankford, throughout accompanied by International Relations Adviser R. Voss.

  7. 27 September 2013 -Lithuanian Minister of Culture Š. Birutis in the LHC tunnel with International Relations Adviser T. Kurtyka and visiting CMS experimental area with Deputy Spokesperson T. Camporesi. Also present: V. Rapsevicius, CMS Collaboration.

    CERN Multimedia

    Laurent Egli

    2013-01-01

    27 September 2013 -Lithuanian Minister of Culture Š. Birutis in the LHC tunnel with International Relations Adviser T. Kurtyka and visiting CMS experimental area with Deputy Spokesperson T. Camporesi. Also present: V. Rapsevicius, CMS Collaboration.

  8. 20 Novemnber 2013 - Ambassador of the Kingdom of the Netherlands to Switzerland B. Twaalfhoven in the LHC tunnel with CERN scientists G. De Rijk and H. Ten Kate; signing the guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    20 Novemnber 2013 - Ambassador of the Kingdom of the Netherlands to Switzerland B. Twaalfhoven in the LHC tunnel with CERN scientists G. De Rijk and H. Ten Kate; signing the guest book with CERN Director-General R. Heuer.

  9. 28 June 2012 - Members of the European Brain Council led by President Mary Baker visiting the LHC tunnel at Point 5 with Technology Department Group Leader L. Bottura and CMS experimental area with Run Coordinator M. Chamizo-Llatas.

    CERN Multimedia

    Jean-Claude Gadmer

    2012-01-01

    28 June 2012 - Members of the European Brain Council led by President Mary Baker visiting the LHC tunnel at Point 5 with Technology Department Group Leader L. Bottura and CMS experimental area with Run Coordinator M. Chamizo-Llatas.

  10. 30 March 2009 - Representatives of the Danish Council for Independent Research Natural Sciences visiting the LHC tunnel at Point 1 with Collaboration Spokesperson F. Gianotti, Former Spokesperson P. Jenni and Transition Radiation Tracker Project Leader C. Rembser.

    CERN Document Server

    Maximilien Brice

    2009-01-01

    30 March 2009 - Representatives of the Danish Council for Independent Research Natural Sciences visiting the LHC tunnel at Point 1 with Collaboration Spokesperson F. Gianotti, Former Spokesperson P. Jenni and Transition Radiation Tracker Project Leader C. Rembser.

  11. 20 January 2014 - Members of the Regional Assemblies and Parliaments United Kingdom of Great Britain and Northern Ireland visiting the LHC tunnel at Point 8 with Technology Department, Vacuum, Surfaces and Coatings Group P. Cruikshank.

    CERN Document Server

    Pantelia, Anna

    2014-01-01

    20 January 2014 - Members of the Regional Assemblies and Parliaments United Kingdom of Great Britain and Northern Ireland visiting the LHC tunnel at Point 8 with Technology Department, Vacuum, Surfaces and Coatings Group P. Cruikshank.

  12. 4 April 2013 - Spanish State Secretary of Science, Development and Innovation C. Vela Olmo in the LHC tunnel with Technology Department Head F. Bordry and signing the guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    4 April 2013 - Spanish State Secretary of Science, Development and Innovation C. Vela Olmo in the LHC tunnel with Technology Department Head F. Bordry and signing the guest book with CERN Director-General R. Heuer.

  13. 14 December 2011 - Czech Republic Delegation to CERN Council and Finance Committees visiting ATLAS experimental area, LHC tunnel and ATLAS visitor centre with Former Collaboration Spokesperson P. Jenni, accompanied by Physicist R. Leitner and Swiss student A. Lister.

    CERN Multimedia

    Estelle Spirig

    2011-01-01

    14 December 2011 - Czech Republic Delegation to CERN Council and Finance Committees visiting ATLAS experimental area, LHC tunnel and ATLAS visitor centre with Former Collaboration Spokesperson P. Jenni, accompanied by Physicist R. Leitner and Swiss student A. Lister.

  14. The LHC machine Exhibition Lepton-Photon 2001

    CERN Multimedia

    2001-01-01

    The LHC will enable the study of proton-proton and ion-ion collisions. The existing chain of injectors (LINAC, booster, PS, SPS) will provide the necessary particles. The LHC superconducting magnets will generate the highest magnetic fields ever reached in an accelerator of this scale. The dipoles and quadrupoles will be interconnected so as to form a continuous cryogenic "pipe" installed in the 27 km-long LEP/LHC tunnel with its separate cryoline. The superconducting RF accelerating cavities, along with the beam cleaning and beam dump systems, will complete the machine.

  15. Proposal to negotiate amendments to an existing contract for the supply of steel structures for the LHC shafts, tunnels, caverns and experimental areas

    CERN Document Server

    2005-01-01

    This document concerns the proposal to negotiate amendments to an existing contract for the supply of additional steel structures for the LHC shafts, tunnels, caverns and experimental areas. For the reasons explained in this document, the Finance Committee is invited to approve amendments to the existing contract with the firm INIZIATIVE INDUSTRIALI (IT) for the supply of additional steel structures for the LHC shafts, tunnels, caverns and experimental areas for an amount of 500 000 euros (775 000 Swiss francs), subject to revision for inflation, bringing the total to 6 525 745 euros (10 114 905 Swiss francs), subject to revision for inflation. The amounts in Swiss francs have been calculated using the present rate of exchange.

  16. 28th January 2011-Vice-President Max Planck Society-Prof. Martin Stratmann-Germany-visiting the ATLAS experimental area and the LHC Tunnel at CERN

    CERN Multimedia

    Jean-Claude Gadmer

    2011-01-01

    Photo 1:ATLAS visitor Center with P. Jenni, ATLAS Collaboration former spokesperson Photo 2-10:visiting the ATLAS cavern Photo 10:D. Hoppe,P. Jenni,M. Stratmann,S. Bethke,S. Braun,D. Klammer Photo 11-15:visiting the LHC tunnel Photo 16-18:Signature of the Guest Book with S. Lettow,Director for Administration and General Infrastructure

  17. The LHC demystified or how to dispel misconceptions about the accelerator

    CERN Multimedia

    2007-01-01

    As the start-up of the LHC approaches, some people are worried about the possible dangers posed by such a powerful machine. Here are a few key points to reassure them... Drawing done by Rafel Carreras published in his book «  quand l’énergie devient matière... » This book explains particle physics and the notions of scale and energy in a simple and entertaining way. It is available in French at the CERN reception (only 5 CHF).Does your neighbour think that the LHC’s collisions will transform the pays de Gex into a huge Emmental cheese? Do you get strange e-mails warning you that you’re going to be sucked into black holes in the accelerator? Of course you know that it’s all just pure fantasy, but do you know how to reply? You can start by reading the following explanations: You are not going to be destroyed by a Big Bang... The LHC’s beams do indeed contain a lot of energy, equivalent to a TGV travelling at 150 km per ho...

  18. LHC magnets

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    Preparations for the LHC proton collider to be built in CERN's LEP tunnel continue to make good progress. In particular development work for the high field superconducting magnets to guide the almost 8 TeVproton beams through the 'tight' curve of the 27-kilometre ring are proceeding well, while the magnet designs and lattice configuration are evolving in the light of ongoing experience. At the Evian LHC Experiments meeting, this progress was covered by Giorgio Brianti

  19. Radiation environment in the tunnel of a high-energy proton accelerator at energies near 1 TeV

    International Nuclear Information System (INIS)

    McCaslin, J.B.; Sun, R.K.S.; Swanson, W.P.

    1987-12-01

    Neutron energy spectra, fluence distributions and rates in the FNAL Tevatron tunnel are summarized. This work has application to radiation damage to electronics and research equipment at high energy accelerators, as well as to radiological protection. 7 refs., 4 figs

  20. 18 January 2011 - The British Royal Academy of Engineering in the LHC tunnel with CMS Collaboration Spokesperson G. Tonelli and Beams Department Head P. Collier; in the CERN Control Centre with P. Collier and LHC superconducting magnet test hall with Technology Department Head F. Bordry.

    CERN Multimedia

    Jean-Claude Gadmer

    2011-01-01

    18 January 2011 - The British Royal Academy of Engineering in the LHC tunnel with CMS Collaboration Spokesperson G. Tonelli and Beams Department Head P. Collier; in the CERN Control Centre with P. Collier and LHC superconducting magnet test hall with Technology Department Head F. Bordry.

  1. 18 January 2011 - Ing. Vittorio Malacalza, ASG Superconductors S.p.A, Italy in the LHC superconducting magnet test hall with Deputy Department Head L. Rossi, in the LHC tunnel at Point 5 and CMS experimental area with Spokesperson G. Tonelli.

    CERN Multimedia

    Maximilien Brice

    2011-01-01

    18 January 2011 - Ing. Vittorio Malacalza, ASG Superconductors S.p.A, Italy in the LHC superconducting magnet test hall with Deputy Department Head L. Rossi, in the LHC tunnel at Point 5 and CMS experimental area with Spokesperson G. Tonelli.

  2. 27 January 2012 - Mitglieder des Stiftungsrates Academia Engelberg und Gesellschaft zum Bettag Luzern Schweiz welcomed by Head of International Relations F. Pauss; visiting LHC tunnel at Point 5 and CMS experimental cavern; in the LHC superconducting magnet test hall SM18.

    CERN Multimedia

    Maximilien Brice

    2012-01-01

    27 January 2012 - Mitglieder des Stiftungsrates Academia Engelberg und Gesellschaft zum Bettag Luzern Schweiz welcomed by Head of International Relations F. Pauss; visiting LHC tunnel at Point 5 and CMS experimental cavern; in the LHC superconducting magnet test hall SM18.

  3. The LHC personnel safety system

    International Nuclear Information System (INIS)

    Ninin, P.; Valentini, F.; Ladzinski, T.

    2011-01-01

    Large particle physics installations such as the CERN Large Hadron Collider require specific Personnel Safety Systems (PSS) to protect the personnel against the radiological and industrial hazards. In order to fulfill the French regulation in matter of nuclear installations, the principles of IEC 61508 and IEC 61513 standard are used as a methodology framework to evaluate the criticality of the installation, to design and to implement the PSS.The LHC PSS deals with the implementation of all physical barriers, access controls and interlock devices around the 27 km of underground tunnel, service zones and experimental caverns of the LHC. The system shall guarantee the absence of personnel in the LHC controlled areas during the machine operations and, on the other hand, ensure the automatic accelerator shutdown in case of any safety condition violation, such as an intrusion during beam circulation. The LHC PSS has been conceived as two separate and independent systems: the LHC Access Control System (LACS) and the LHC Access Safety System (LASS). The LACS, using off the shelf technologies, realizes all physical barriers and regulates all accesses to the underground areas by identifying users and checking their authorizations.The LASS has been designed according to the principles of the IEC 61508 and 61513 standards, starting from a risk analysis conducted on the LHC facility equipped with a standard access control system. It consists in a set of safety functions realized by a dedicated fail-safe and redundant hardware guaranteed to be of SIL3 class. The integration of various technologies combining electronics, sensors, video and operational procedures adopted to establish an efficient personnel safety system for the CERN LHC accelerator is presented in this paper. (authors)

  4. Warmer amps for the LHC

    CERN Multimedia

    Anaïs Schaeffer

    2012-01-01

    CERN is working together with an Italian company to develop superconducting cables that can function at temperatures of up to 25 K (-248°C). This will make it possible to move LHC magnet power supplies out of the tunnel, protecting them from exposure to the showers of very high-energy particles produced by the accelerator.   Figure 1: devices of this type, which measure approximately 10 metres in length, are inserted between the accelerating magnets at different points along the LHC. When it comes to consuming electricity, the magnets that steer particles through large accelerators can be characterised with just one word: greedy. For the LHC, the total current can reach 1.5 million amps. At the present time, this current is brought in via copper cables of up to 10 cm in diameter. In the tunnel, these cables connect the current leads - which provide the transition between the ambient-temperature cables and the magnets in their bath of superfluid helium - to the power supply. In the a...

  5. LHC milestone

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    At the December meeting of CERN's Council, the Organization's Governing Body, the delegates from the 16 Member States unanimously agreed that the LHC proton-proton collider proposed for the 27-kilometre LEP tunnel is the 'right machine for the advance of the subject and of the future of CERN'

  6. Chamonix 2016: setting the future course for the LHC and the accelerator complex

    CERN Multimedia

    Mike Lamont

    2016-01-01

    The LHC Performance Workshop took place in Chamonix between Tuesday, 25 and Thursday, 28 January. The programme included a review of the machine’s performance in 2015, a forward look at Run 2, and discussion of the status of the LHC injectors upgrade (LIU) and HL-LHC projects. The final session was dedicated to the 2019-2020 long shutdown (LS2).   The 2016 LHC Performance Workshop participants. Last year was the first year of operations following the major maintenance work of the 2013 – 2014 long shutdown (LS1). It was a tough but ultimately successful year. An analysis of operations and efficiency was performed with the aim of identifying possible improvements for 2016. The performance of key systems – e.g. machine protection, collimation, RF, transverse damper, magnetic circuits and beam diagnostics – has been good but nonetheless efforts are still being made to provide, for example, better reliability, improved functionality and monitoring. A number of c...

  7. Validation of the Data Consolidation in Layout Database for the LHC Tunnel Cryogenics Controls Upgrade

    CERN Document Server

    Tovar-Gonzalez, A; Blanco, E; Fortescue-Beck, E; Fluder, C; Inglese, V; Pezzetti, M; Gomes, P; Wolak, T; Dudek, M; Frassinelli, F; Drozd, A; Zapolski, M

    2014-01-01

    The control system of the Large Hadron Collider cryogenics manages over 34’000 instrumentation and actuator channels. The complete information on their characteristics and parameters can be extracted from a set of views on the Layout database, to generate the specifications of the control system; from these, the code to populate PLCs (Programmable Logic Controller) and SCADA (Supervisory Control & Data Acquisition) is automatically produced, within the UNICOS framework (Unified Industrial Control System). The Layout database is, since 2003, progressively integrating and centralizing information on the whole CERN Accelerator complex. It models topographical organization (layouts) as functional positions and relationships. After three years of machine operation, many parameters have been manually adjusted in SCADA and PLCs; they now differ from their original values in the Layout database. Furthermore, to accommodate the upgrade of the UNICOS Continuous Process Control package to version 6, some data stru...

  8. Suitability of tunneling ionization produced plasmas for the plasma beat wave accelerator

    International Nuclear Information System (INIS)

    Leeman, W.P.; Clayton, C.E.; Marsh, K.A.; Dyson, A.; Joshi, C.

    1991-01-01

    Tunneling ionization can be thought of as the high intensity, low frequency limit of multi-photon ionization (MPI). Extremely uniform plasmas were produced by the latter process at Rutherford lab for beat wave excitation experiments using a 0.5 μm laser. Plasmas with 100% ionization were produced with densities exceeding 10 17 cm -3 . The experiment uses a CO 2 laser (I max ∼ 5 x 10 14 W/cm 2 ) which allows the formation of plasmas via the tunneling process. For the experiments the authors need plasmas with densities in the range of 5 to 10 x 10 16 cm -3 . Using Thomson scattering as a diagnostic they have explored the density and temperature regime of tunneling ionization produced plasmas. They find that plasmas with densities up to 10 16 cm -3 can indeed be produced and that these plasmas are hot. Beyond this density strong refraction of laser radiation occurs due to the radial profile of the plasma. Implications of this work to the Beat Wave Accelerator program will be discussed

  9. Tunneling dynamics of superfluid Fermi gases in an accelerating optical lattice

    International Nuclear Information System (INIS)

    Tie Lu; Xue Jukui

    2010-01-01

    The nonlinear Landau-Zener tunneling and the nonlinear Rabi oscillations of superfluid Fermi gases between Bloch bands in an accelerating optical lattice are discussed. Within the hydrodynamic theory and a two-level model, the tunneling probability of superfluid Fermi gases between Bloch bands is obtained. We find that, as the system crosses from the Bose-Einstein condensation (BEC) side to the BCS side, the tunneling rate is closely related to the particle density: when the density is smaller (larger) than a critical value, the tunneling rate at unitarity is larger (smaller) than that in the BEC limit. This is well explained in terms of an effective interaction and an effective potential. Furthermore, the nonlinear Rabi oscillations of superfluid Fermi gases between the bands are discussed by imposing a periodic modulation on the level bias and the strength of the lattice. Analytical expressions of the critical density for suppressing or enhancing the Rabi oscillations are obtained. It is shown that, as the system crosses from the BEC side to the BCS side, the critical density strongly depends on the modulation parameters (i.e., the modulation amplitude and the modulation frequency). For a fixed density, a high-frequency or low-frequency modulation can suppress or enhance the Rabi oscillations both at unitarity and in the BEC limit. For an intermediate modulation frequency, the Rabi oscillations are chaotic along the entire BEC-BCS crossover, especially, on the BCS side. Interestingly, we find that the modulation of the lattice strength only with an intermediate modulation frequency has significant effect on the Rabi oscillations both in the BEC limit and at unitarity; that is, an intermediate-frequency modulation can enhance the Rabi oscillations, especially on the BCS side.

  10. 1st February 2011-CERN Cultural Board for Engaging with the Arts, visiting CMS experimental area and LHC Tunnel at Point 5

    CERN Multimedia

    Michael Hoch

    2011-01-01

    Photo 1-4: Visit to CMS Control Room with G. Tonelli,CMS Collaboration Spokesperson Photo 5-9,16-20:CMS experimental area Photo 10-15:LHC Tunnel at Point 5 Photo 21:F. Madlener,Director of IRCAM Paris+S. Dorny,Director-General Lyon Opera House+C. Bollman,Art by Genève+M. Doser,AEgIS Collaboration Spokesperson,Former Physics Department Deputy Head+A. Koek,International Arts Development+G. Tonelli+M. Monje Cano,Arts Development Assistant (part-time work experience)+B. Ruf,Director of Kunsthalle Zürich

  11. The High-Luminosity upgrade of the LHC: Physics and Technology Challenges for the Accelerator and the Experiments

    Science.gov (United States)

    Schmidt, Burkhard

    2016-04-01

    In the second phase of the LHC physics program, the accelerator will provide an additional integrated luminosity of about 2500/fb over 10 years of operation to the general purpose detectors ATLAS and CMS. This will substantially enlarge the mass reach in the search for new particles and will also greatly extend the potential to study the properties of the Higgs boson discovered at the LHC in 2012. In order to meet the experimental challenges of unprecedented pp luminosity, the experiments will need to address the aging of the present detectors and to improve the ability to isolate and precisely measure the products of the most interesting collisions. The lectures gave an overview of the physics motivation and described the conceptual designs and the expected performance of the upgrades of the four major experiments, ALICE, ATLAS, CMS and LHCb, along with the plans to develop the appropriate experimental techniques and a brief overview of the accelerator upgrade. Only some key points of the upgrade program of the four major experiments are discussed in this report; more information can be found in the references given at the end.

  12. Investigation of physico-chemical processes in hypervelocity MHD-gas acceleration wind tunnels

    International Nuclear Information System (INIS)

    Alfyorov, V.I.; Dmitriev, L.M.; Yegorov, B.V.; Markachev, Yu.E.

    1995-01-01

    The calculation results for nonequilibrium physicochemical processes in the circuit of the hypersonic MHD-gas acceleration wind tunnel are presented. The flow in the primary nozzle is shown to be in thermodynamic equilibrium at To=3400 K, Po=(2∼3)x10 5 Pa, M=2 used in the plenum chamber. Variations in the static pressure due to oxidation reaction of Na, K are pointed out. The channels of energy transfer from the electric field to different degrees of freedom of an accelerated gas with Na, K seeds are considered. The calculation procedure for gas dynamic and kinetic processes in the MHD-channel using measured parameters is suggested. The calculated results are compared with the data obtained in a thermodynamic gas equilibrium assumption. The flow in the secondary nozzle is calculated under the same assumptions and the gas parameters at its exit are evaluated. Particular attention is given to the influence of seeds on flows over bodies. It is shown that the seeds exert a very small influence on the flow behind a normal shock wave. The seeds behind an oblique shock wave accelerate deactivation of vibrations of N 2 , but this effect is insignificant

  13. Latin American collaboration to the CERN-LHC accelerator assembly and its projects

    Energy Technology Data Exchange (ETDEWEB)

    Sajo B, L. [Universidad Simon Bolivar, Nuclear Physics Laboratory, Caracas 1080-A (Venezuela, Bolivarian Republic of)

    2016-10-15

    Summary of Latin American (LA) scientists main contributions to the construction of a heavy ion detector assembly currently operating at the Large Hadron Collider (LHC) at CERN, Geneva,Switzerland is given with description of the provided support for posterior data analysis. This joint effort highlights the much needed recognition of LA as a technologically emerging region. It has also shown a net benefit in development of science for our region. Details are given on the LHC-Alice experiment where several LA countries have contributed with innovative technological solutions. These include the ability to build part of the numerous detectors, including the central barrel as well as acquired knowledge on aspects concerning high energy dosimetry and radiation damage. (Author)

  14. Accelerator Magnet Quench Heater Technology and Quality Control Tests for the LHC High Luminosity Upgrade

    CERN Document Server

    AUTHOR|(CDS)2132435; Seifert, Thomas

    The High Luminosity upgrade of the Large Hadron Collider (HL-LHC) foresees the installation of new superconducting Nb$_{3}$Sn magnets. For the protection of these magnets, quench heaters are placed on the magnet coils. The quench heater circuits are chemically etched from a stainless steel foil that is glued onto a flexible Polyimide film, using flexible printed circuit production technology. Approximately 500 quench heaters with a total length of about 3000 m are needed for the HL-LHC magnets. In order to keep the heater circuit electrical resistance in acceptable limits, an approximately 10 µm-thick Cu coating is applied onto the steel foil. The quality of this Cu coating has been found critical in the quench heater production. The work described in this thesis focuses on the characterisation of Cu coatings produced by electrolytic deposition, sputtering and electron beam evaporation. The quality of the Cu coatings from different manufacturers has been assessed for instance by ambient temperature electrica...

  15. Latin American collaboration to the CERN-LHC accelerator assembly and its projects

    International Nuclear Information System (INIS)

    Sajo B, L.

    2016-10-01

    Summary of Latin American (LA) scientists main contributions to the construction of a heavy ion detector assembly currently operating at the Large Hadron Collider (LHC) at CERN, Geneva,Switzerland is given with description of the provided support for posterior data analysis. This joint effort highlights the much needed recognition of LA as a technologically emerging region. It has also shown a net benefit in development of science for our region. Details are given on the LHC-Alice experiment where several LA countries have contributed with innovative technological solutions. These include the ability to build part of the numerous detectors, including the central barrel as well as acquired knowledge on aspects concerning high energy dosimetry and radiation damage. (Author)

  16. Assembly and Test of SQ01b, a Nb3Sn Quadrupole Magnet for the LHC Accelerator Research Program

    Energy Technology Data Exchange (ETDEWEB)

    Ferracin, P.; Ambrosio, G.; Bartlett, S. E.; Bordini, B.; Carcagno, R.H.; Caspi, S.; Dietderich, D.R.; Feher, S.; Gourlay, S.A.; Hafalia, A.R.; Lamm, M.J.; Lietzke, A.F.; Mattafirri, S.; McInturff, A.D.; Orris, D.F.; Pischalnikov, Y.M.; Sabbi, G.L.; Sylvester, C.D.; Tartaglia, M.A.; Velev, G.V.; Zlobin, A.V.; Kashikhin, V.V.

    2006-06-01

    The US LHC Accelerator Research Program (LARP) consists of four US laboratories (BNL, FNAL, LBNL, and SLAC) collaborating with CERN to achieve a successful commissioning of the LHC and to develop the next generation of Interaction Region magnets. In 2004, a large aperture Nb{sub 3}Sn racetrack quadrupole magnet (SQ01) has been fabricated and tested at LBNL. The magnet utilized four subscale racetrack coils and was instrumented with strain gauges on the support structure and directly over the coil's turns. SQ01 exhibited training quenches in two of the four coils and reached a peak field in the conductor of 10.4 T at a current of 10.6 kA. After the test, the magnet was disassembled, inspected with pressure indicating films, and reassembled with minor modifications. A second test (SQ01b) was performed at FNAL and included training studies, strain gauge measurements and magnetic measurements. Magnet inspection, test results, and magnetic measurements are reported and discussed, and a comparison between strain gauge measurements and 3D finite element computations is presented

  17. Assembly and Test of SQ01b, a Nb3Sn Quadrupole Magnet for the LHC Accelerator Research Program

    International Nuclear Information System (INIS)

    Ferracin, P.; Ambrosio, G.; Bartlett, S. E.; Bordini, B.; Carcagno, R.H.; Caspi, S.; Dietderich, D.R.; Feher, S.; Gourlay, S.A.; Hafalia, A.R.; Lamm, M.J.; Lietzke, A.F.; Mattafirri, S.; McInturff, A.D.; Orris, D.F.; Pischalnikov, Y.M.; Sabbi, G.L.; Sylvester, C.D.; Tartaglia, M.A.; Velev, G.V.; Zlobin, A.V.; Kashikhin, V.V.

    2006-01-01

    The US LHC Accelerator Research Program (LARP) consists of four US laboratories (BNL, FNAL, LBNL, and SLAC) collaborating with CERN to achieve a successful commissioning of the LHC and to develop the next generation of Interaction Region magnets. In 2004, a large aperture Nb 3 Sn racetrack quadrupole magnet (SQ01) has been fabricated and tested at LBNL. The magnet utilized four subscale racetrack coils and was instrumented with strain gauges on the support structure and directly over the coil's turns. SQ01 exhibited training quenches in two of the four coils and reached a peak field in the conductor of 10.4 T at a current of 10.6 kA. After the test, the magnet was disassembled, inspected with pressure indicating films, and reassembled with minor modifications. A second test (SQ01b) was performed at FNAL and included training studies, strain gauge measurements and magnetic measurements. Magnet inspection, test results, and magnetic measurements are reported and discussed, and a comparison between strain gauge measurements and 3D finite element computations is presented

  18. Expected damage to accelerator equipment due to the impact of the full LHC beam: beam instrumentation, experiments and simulations

    CERN Document Server

    Burkart, Florian

    The Large Hadron Collider (LHC) is the biggest and most powerful particle accelerator in the world, designed to collide two proton beams with particle momentum of 7 TeV/c each. The stored energy of 362MJ in each beam is sufficient to melt 500 kg of copper or to evaporate about 300 liter of water. An accidental release of even a small fraction of the beam energy can cause severe damage to accelerator equipment. Reliable machine protection systems are necessary to safely operate the accelerator complex. To design a machine protection system, it is essential to know the damage potential of the stored beam and the consequences in case of a failure. One (catastrophic) failure would be, if the entire beam is lost in the aperture due to a problem with the beam dumping system. This thesis presents the simulation studies, results of a benchmarking experiment, and detailed target investigation, for this failure case. In the experiment, solid copper cylinders were irradiated with the 440GeV proton beam delivered by the ...

  19. 4-13 kA DC current transducers enabling accurate in-situ calibration for a new particle accelerator project, LHC

    CERN Document Server

    Hudson, G

    2005-01-01

    CERN's next generation particle accelerator, the large hadron collider (LHC) requires accurate current measurement up to 13 kA to enable current tracking between individual power converters. DC current transducers (DCCTs) have been developed to allow in-situ calibrations to 10/sup -6/ uncertainty. This paper describes the principle, design and initial evaluations.

  20. CERN-HI-1202040 tirage 29 (front row) Russian Federation Secretary of the Security Council N. Patrushev with Adviser T. Kurtyka and Permanent Mission to the UN Adviser A. Petrov in the LHC tunnel at Point 1.

    CERN Multimedia

    Maximilien Brice

    2012-01-01

    On 14 February Nikolai Patrushev, secretary of the Security Council for the Russian Federation, was welcomed to CERN. He visited the ATLAS underground experimental area, the LHC tunnel and ATLAS Visitor Centre before viewing the Universe of Particles exhibition at the Globe of Science and Innovation.

  1. 16 December 2011 - Israeli Minister of Industry, Trade and Labour S.Simhon visiting ATLAS undeground area, ATLAS visitor centre and LHC tunnel with Senior Physicist G. Mikenberg. ATLAS Collaboration Former Spokesperson is also present.

    CERN Multimedia

    Maximilien Brice

    2011-01-01

    Israeli minister of industry, trade and labour, Shalom Simhon, was welcomed in the ATLAS visitor centre before he toured the ATLAS underground experimental area, where he could see the ATLAS detector. He also had a chance to see the LHC tunnel and the CERN Control Centre.

  2. 3 May 2014 - His Excellency Dr Karolos Papoulias President of the Hellenic Republic in the LHC tunnel at Point 1 and in ATLAS experimental cavern with Director-General R. Heuer.

    CERN Multimedia

    Brice, Maximilien

    2014-01-01

    In the LHC tunnel at Point 1: Beams Department, Controls Group Leader E. Hatziangeli and Technology Department, Cryogenics Group Deputy Leader D. Delikaris. In the ATLAS cavern: ATLAS Deputy Spokesperson B. Heinemann and ATLAS Collaboration National contact person and CAST Collaboration National Technical University of Athens Team Leader E. Gazis.

  3. Towards LHC experiments

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    As plans for the LHC proton collider to be built in CERN's 27-kilometre LEP tunnel take shape, interest widens to bring in the experiments exploiting the big machine. The first public presentations of 'expressions of interest' for LHC experiments featured from 5-8 March at Evian-les-Bains on the shore of Lake Geneva, some 50 kilometres from CERN, at the special Towards the LHC Experimental Programme' meeting

  4. Charged vector particle tunneling from a pair of accelerating and rotating and 5D gauged super-gravity black holes

    Energy Technology Data Exchange (ETDEWEB)

    Javed, Wajiha; Ali, Riasat [University of Education, Division of Science and Technology, Lahore (Pakistan); Abbas, G. [The Islamia University of Bahawalpur, Department of Mathematics, Bahawalpur (Pakistan)

    2017-05-15

    The aim of this paper is to study the quantum tunneling process for charged vector particles through the horizons of more generalized black holes by using the Proca equation. For this purpose, we consider a pair of charged accelerating and rotating black holes with Newman-Unti-Tamburino parameter and a black hole in 5D gauged super-gravity theory, respectively. Further, we study the tunneling probability and corresponding Hawking temperature for both black holes by using the WKB approximation. We find that our analysis is independent of the particles species whether or not the background black hole geometries are more generalized. (orig.)

  5. Little band at big accelerators: Heavy ion physics from AGS to LHC

    International Nuclear Information System (INIS)

    Schukraft, J.

    2001-01-01

    The field of ultra-relativistic heavy ion physics, which started some 10 years ago at the Brookhaven AGS and the CERN SPS with fixed target experiments, has entering today a new era with the recent (July 2000) start-up of the Relativistic Heavy Ion Collider RHIC and preparations well under way for a new large heavy ion experiment at the Large Hadron Collider LHC. This overview, which is the combined write-up of talks given at this conference [1] and in [2], will sketch a rough picture of the heavy ion program at current and future machines and concentrate on a few important topics, in particular the question if current results show any of the signs predicted for the phase transition between normal hadronic matter and the Quark-Gluon Plasma

  6. A word from the DG - Major progress for the LHC

    CERN Multimedia

    2006-01-01

    The return to work after the summer holiday period has been marked by significant progress in the installation of the LHC machine and its detectors. At the beginning of the month, the one thousandth superconducting magnet was positioned in the accelerator tunnel. Passing this symbolic milestone is a testament to the successful efforts of the hundreds of LHC collaborators who are working day and night to install the machine in time, and I would like to take this opportunity to congratulate them. Despite the significant technical and organisational difficulties associated with different types of activities being carried out in parallel in a tunnel where space is limited, the LHC installation teams have achieved remarkable feats. As a result, the delays incurred owing to the problems encountered with the cryogenic distribution line in 2004 have been partly recouped. The cryoline is almost complete, with seven out of eight sectors accepted while installation of the eighth is expected to be completed at the...

  7. Design, construction and start up by Air Liquide of two 18 kW at 45 K helium refrigerators for the new CERN accelerator (LHC)

    CERN Document Server

    Dauguet, P; Delcayre, F; Ghisolfi, A; Gistau-Baguer, Guy M; Guerin, C A; Hilbert, B; Marot, G; Monneret, E

    2004-01-01

    CERN in Switzerland is presently building a new particle accelerator labeled as the LHC. This 27 km accelerator will, for the first time at such a large scale, operate at cryogenic temperatures with superconducting magnets and radio-frequency cavities. For that purpose, Air Liquide has designed, constructed and started up two custom designed refrigerators. The cryogenic power of each of these refrigerators is equivalent to 18 kW at 4.5 K. In order to produce the cryogenic power requested by the LHC accelerator at the different temperature levels with a very high efficiency, a custom design thermodynamic cycle has been chosen. This cycle, the major components of the refrigerators and the results obtained during the reception tests of the refrigerators are presented in this paper.

  8. Snapshots to shed light on LHC performance

    CERN Multimedia

    2006-01-01

    With the impressive size and unprecedented power of the LHC, it is all too easy to overlook the smaller devices that have the difficult task of monitoring the new accelerator. You don't have to stand too far back from the big picture to see examples of clever technology inside the LHC. One of the undulators installed in the LHC tunnel can be seen on the right of the photo. From right to left, back row: Lucio Rossi (group leader, MCS), Davide Tommasini (conceptual design, MCS), Thierry Tenaglia (integration design,TS-MME), Remo Maccaferri (project leader, MCS) and Hans Kummer (MCS/ME); front row: Gilles Trachez (MCS-ME) and Bruno Meunier (FSU-AT12). In contrast to the usual articles about the LHC's big number statistics, examples of clever problem-solving found in beam monitoring machinery show that smaller things can be beautiful too. The design of the LHC accelerator brought new challenges for monitoring the shape of the particle beam, known as the beam profile. The size of the beam shrinks as higher energi...

  9. CERN Technical training 2008 - Learning for the LHC: Special Workshop demonstrating reliability with accelerated testing

    CERN Multimedia

    2008-01-01

    Larry Edson’s workshop will show examples of quantitative reliability predictions based upon accelerated testing and demonstrates that reliability testing during the prototyping phase will help ascertain product shortcomings. When these weak points are addressed and the redesigned product is re-tested, the reliability of that product will become much higher. These methodologies successfully used in industry might be exceedingly useful also for component development in particle physics where reliability is of utmost importance. This training will provide participants with the skills necessary to demonstrate reliability requirements using accelerated testing methods. The workshop will focus on accelerated test design that employs increased stress levels. This approach has the advantage of reducing test time, sample size and test facility resources. The methodologies taught are applicable to all types of stresses, spanning the electro...

  10. CERN Technical training 2008 - Learning for the LHC: Special Workshop demonstrating reliability with accelerated testing

    CERN Multimedia

    2008-01-01

    Larry Edson’s workshop will show examples of quantitative reliability predictions based upon accelerated testing and demonstrate that reliability testing during the prototyping phase will help ascertain product shortcomings. When these weak points are addressed and the redesigned product is re-tested, the reliability of that product will become much higher. These methodologies successfully used in industry might be exceedingly useful also for component development in particle physics where reliability is of the utmost importance. This training will provide participants with the skills necessary to demonstrate reliability requirements using accelerated testing methods. The workshop will focus on accelerated test design that employs increased stress levels. This approach has the advantage of reducing test time, sample size and test facility resources. The methodologies taught are applicable to all types of stresses, spanning the elec...

  11. CERN Technical training 2008 - Learning for the LHC: Special workshop demonstrating reliability with accelerated testing

    CERN Multimedia

    2008-01-01

    Larry Edson’s workshop will show examples of quantitative reliability predictions based upon accelerated testing and demonstrate that reliability testing during the prototyping phase will help ascertain product shortcomings. When these weak points are addressed and the redesigned product is re-tested, the reliability of that product will become much higher. These methodologies successfully used in industry might be exceedingly useful also for component development in particle physics where reliability is of the utmost importance. This training will provide participants with the skills necessary to demonstrate reliability requirements using accelerated testing methods. The workshop will focus on accelerated test design that employs increased stress levels. This approach has the advantage of reducing test time, sample size and test facility resources. The methodologies taught are applicable to all types of stresses, spanning the elec...

  12. CERN Technical Training 2003: Learning for the LHC! : AXEL-2003  -  Introduction to Particle Accelerators

    CERN Multimedia

    2003-01-01

    AXEL-2003 is a course given at CERN within the framework of the Technical Training Programme. The course will present an introduction to particle accelerators. Known in the past as the PS Complex Operation Course (or the "PS Shutdown Course"), and organised by the ex-PS division until last year, it is now organised as a joint venture between the AB division and Technical Training, and open to a wider CERN community. The AXEL-2003 course series is designed for technicians who are operating an accelerator, or whose work is closely linked to accelerators, but it is open to all people (technicians, engineers, physicists) interested in this field. The course does not require any prior knowledge on accelerators. However, some basic knowledge on trigonometry, matrices and differential equations, and some basic notions of magnetism would be an advantage. The course and the course supports will be in English, with questions and answers also in French. Lectures will be recorded and available online via the Web Lectu...

  13. Acoustic measurements in the collimation region of the LHC

    CERN Document Server

    Deboy, D; Baccigalupi, C; Burkart, F; Cauchi, M; Derrez, C S; Lendaro, J; Masi, A; Spiezia, G; Wollmann, D

    2011-01-01

    The LHC accelerator at CERN has the most advanced collimation system ever being installed. The collimators intercept unavoidable particle losses and therefore are essential to avoid beam induced quenches of the superconducting magnets. In addition, they provide passive machine protection against mis-kicked beams. During material robustness tests on a LHC collimator prototype in 2004 and 2006, vibration and acoustic measurements have shown that a beam impact detection system should be feasible using accelerometers and microphones as sensors in the LHC. Recently, such sensors have been installed close to the primary collimators in the LHC tunnel. First analyses of raw data show that the system is sensitive enough to detect beam scraping on collimators. Therefore, the implementation of a sophisticated acousticmonitoring system is under investigation. It may be useful not only to detect beam impacts on primary collimators in case of failure, but also to derive further information on beam losses that occur during ...

  14. Vacuum system for LHC

    International Nuclear Information System (INIS)

    Groebner, O.

    1995-01-01

    The Large Hadron Collider (LHC) which is planned at CERN will be housed in the tunnel of the Large Electron Positron collider (LEP) and will store two counter-rotating proton beams with energies of up to 7 TeV in a 27 km accelerator/storage ring with superconducting magnets. The vacuum system for the LHC will be at cryogenic temperatures (between 1.9 and 20 K) and will be exposed to synchrotron radiation emitted by the protons. A stringent limitation on the vacuum is given by the energy deposition in the superconducting coils of the magnets due to nuclear scattering of the protons on residual gas molecules because this may provoke a quench. This effect imposes an upper limit to a local region of increased gas density (e.g. a leak), while considerations of beam lifetime (100 h) will determine more stringent requirements on the average gas density. The proton beam creates ions from the residual gas which may strike the vacuum chamber with sufficient energy to lead to a pressure 'run-away' when the net ion induced desorption yield exceeds a stable limit. These dynamic pressure effects will be limited to an acceptable level by installing a perforated 'beam screen' which shields the cryopumped gas molecules at 1.9 K from synchrotron radiation and which also absorbs the synchrotron radiation power at a higher and, therefore, thermodynamically more efficient temperature. (author)

  15. Estimated characteristics modification of silicon detectors due to their use at the LHC-accelerator and in AMS space conditions

    International Nuclear Information System (INIS)

    Lazanu, I.; Lazanu, S.

    2003-01-01

    In this talk, the phenomenological model developed by the authors in previous papers has been used to evaluate the degradation induced in high resistivity silicon detectors by pion and proton irradiation at the future accelerator facilities or by cosmic protons considering the continuous irradiation for ten years of work. The equations governing the degradation of the lattice are explicitly considered. The damage has been analysed at the microscopic level (defects production and their evolution toward equilibrium) and at the macroscopic level (only the changes in the leakage current of the p-n junction was considered). The rates of production of primary defects, as well as their evolution toward equilibrium have been evaluated considering explicitly irradiation field of the specified applications, by the type of the projectile particle and its energy. The influence of these defects on the leakage current density has been compared with experimental data from the literature, and predictions for the LHC radiation fields, as well as for space missions in the near Earth orbits have been done, in the frame of the Schokley-Read-Hall model. (authors)

  16. LHC train control system for autonomous inspections and measurements

    OpenAIRE

    Di Castro, Mario; Baiguera Tambutti, Maria Laura; Gilardoni, Simone; Losito, Roberto; Lunghi, Giacomo; Masi, Alessandro

    2018-01-01

    Intelligent robotic systems are becoming essential for inspection and measurements in harsh environments, such as the European Organization for Nuclear Research (CERN) accelerators complex. Aiming at increasing safety and machine availability, robots can help to perform repetitive or dangerous tasks, reducing the risk for the personnel as the exposure to radiation. The Large Hadron Collider (LHC) tunnel at CERN has been equipped with fail-safe trains on monorail able to perform autonomously d...

  17. LHC Supertable

    International Nuclear Information System (INIS)

    Pereira, M.; Lahey, T.E.; Lamont, M.; Mueller, G.J.; Teixeira, D.D.; McCrory, E.S.

    2012-01-01

    LHC operations generate enormous amounts of data. This data is being stored in many different databases. Hence, it is difficult for operators, physicists, engineers and management to have a clear view on the overall accelerator performance. Until recently the logging database, through its desktop interface TIMBER, was the only way of retrieving information on a fill-by-fill basis. The LHC Supertable has been developed to provide a summary of key LHC performance parameters in a clear, consistent and comprehensive format. The columns in this table represent main parameters that describe the collider operation such as luminosity, beam intensity, emittance, etc. The data is organized in a tabular fill-by-fill manner with different levels of detail. Particular emphasis was placed on data sharing by making data available in various open formats. Typically the contents are calculated for periods of time that map to the accelerator's states or beam modes such as Injection, Stable Beams, etc. Data retrieval and calculation is triggered automatically after the end of each fill. The LHC Supertable project currently publishes 80 columns of data on around 100 fills. (authors)

  18. Engineers win award for Swiss tunnel

    CERN Multimedia

    2003-01-01

    A Derby engineering consultancy has won the Tunnelling Industry Award 2003 for Excellence in Tunnel Design, offered by the British Tunnelling Society, for its work on the LHC in Geneva, Switzerland (1/2 page).

  19. 15 February 2012 - Geneva United Nations Office Director-General K.-J. Tokayev in the LHC tunnel with Adviser for Relations with international organisations M. Bona and Technology Department Head F. Bordry.

    CERN Multimedia

    Jean-claude Gadmer

    2012-01-01

    Kassym-Jomart Tokayev, director-general of the United Nations Office at Geneva, (centre picture 02), visited CERN on 15 February. He toured the LHC tunnel with Maurizio Bona, CERN’s adviser to the director-general, relations with international organizations, left, and Frédérick Bordry, CERN’s technology department head. He also visited the ATLAS underground experimental area, as well as the exhibition at the Globe of Science and Innovation.

  20. Electronic system of the RPC Muon Trigger in CMS experiment at LHC accelerator (Elektroniczny system trygera mionowego RPC w eksperymencie CMS akceleratora LHC

    CERN Document Server

    Bialkowska, H

    2009-01-01

    This paper presents implementation of distributed, multichannel electronic measurement system for RPC - based Muon Trigger in the CMS experiment at LHC. The introduction shortly describes the research aims of LHC and shows the metrological requirements for CMS - good spatial and time resolution, and possibility to estimate multiple physical parameters from registered collisions of particles. Further the paper describes RPC Muon Trigger consisting of 200 000 independent channels for position measurement. The first part of the paper presents the functional structure of the system in the context of requirements put by the CMS experiment, like global triggering system and data acquisition. The second part describes the hardware solutions used in particular parts of the RPC detector measuremnt system and shows some test results. The paper has a digest and overview nature.

  1. LHC Report: The machine under maintenance

    CERN Multimedia

    Katy Foraz for the LHC Team

    2012-01-01

    The LHC Christmas break started on 12 December. Since then, teams have been working hard to complete all the maintenance work planned to ensure the reliable operation of the LHC in 2012.   Installation of shielding at Point 1. The maintenance work is being carried out on key infrastructure such as the cooling, ventilation, electricity and safety systems. Maintenance work is being carried out not just in the LHC but also across the whole accelerator complex, which makes planning the work even more complicated. At the time of going to print, 50% of the cryogenics system maintenance has been finished, which, according to the schedule, will allow the LHC teams to start cooling down the first sectors next week to have the entire machine cold by the end of February. A lot of activity is going on in order to mitigate the effects of radiation on equipment installed in the LHC tunnel and underground areas during 2012 operation. To this end, teams have installed additional shielding at Point 1 (see ph...

  2. LHC synchronization test successful

    CERN Multimedia

    The synchronization of the LHC's clockwise beam transfer system and the rest of CERN's accelerator chain was successfully achieved last weekend. Tests began on Friday 8 August when a single bunch of a few particles was taken down the transfer line from the SPS accelerator to the LHC. After a period of optimization, one bunch was kicked up from the transfer line into the LHC beam pipe and steered about 3 kilometres around the LHC itself on the first attempt. On Saturday, the test was repeated several times to optimize the transfer before the operations group handed the machine back for hardware commissioning to resume on Sunday. The anti-clockwise synchronization systems will be tested over the weekend of 22 August.Picture:http://lhc-injection-test.web.cern.ch/lhc-injection-test/

  3. Digital Signal Processing Applications and Implementation for Accelerators Digital Notch Filter with Programmable Delay and Betatron Phase Adjustment for the PS, SPS and LHC Transverse Dampers

    CERN Document Server

    Rossi, V

    2002-01-01

    In the framework of the LHC project and the modifications of the SPS as its injector, I present the concept of global digital signal processing applied to a particle accelerator, using Field Programmable Gate Array (FPGA) technology. The approach of global digital synthesis implements in numerical form the architecture of a system, from the start up of a project and the very beginning of the signal flow. It takes into account both the known parameters and the future evolution, whenever possible. Due to the increased performance requirements of today's projects, the CAE design methodology becomes more and more necessary to handle successfully the added complexity and speed of modern electronic circuits. Simulation is performed both for behavioural analysis, to ensure conformity to functional requirements, and for time signal analysis (speed requirements). The digital notch filter with programmable delay for the SPS Transverse Damper is now fully operational with fixed target and LHC-type beams circulating in t...

  4. LHC superconducting strand

    CERN Multimedia

    Patrice Loiez

    1999-01-01

    This cross-section through a strand of superconducting matieral as used in the LHC shows the 8000 Niobium-Titanium filaments embedded like a honeycomb in copper. When cooled to 1.9 degrees above absolute zero in the LHC accelerator, these filaments will have zero resistance and so will carry a high electric current with no energy loss.

  5. 6 February 2012 - Supreme Audit Institutions from Norway, Poland, Spain and Switzerland visiting the LHC tunnel at Point 5, CMS underground experimental area, CERN Control Centre and LHC superconducting magnet test hall. Delegations are throughout accompanied by Swiss P. Jenni, Polish T. Kurtyka, Spanish J. Salicio, Norwegian S. Stapnes and International Relations Adviser R. Voss. (Riksrevisjonen, Oslo; Tribunal de Cuentas , Madrid; the Court of Audit of Switzerland and Najwyzsza Izba Kontroli, Varsaw)

    CERN Multimedia

    Jean-Claude Gadmer

    2012-01-01

    6 February 2012 - Supreme Audit Institutions from Norway, Poland, Spain and Switzerland visiting the LHC tunnel at Point 5, CMS underground experimental area, CERN Control Centre and LHC superconducting magnet test hall. Delegations are throughout accompanied by Swiss P. Jenni, Polish T. Kurtyka, Spanish J. Salicio, Norwegian S. Stapnes and International Relations Adviser R. Voss. (Riksrevisjonen, Oslo; Tribunal de Cuentas , Madrid; the Court of Audit of Switzerland and Najwyzsza Izba Kontroli, Varsaw)

  6. First Experience with the LHC Cryogenic Instrumentation

    CERN Document Server

    Vauthier, N; Balle, Ch; Casas-Cubillos, J; Ciechanowski, M; Fernandez-Penacoba, G; Fortescue-Beck, E; Gomes, P; Jeanmonod, N; Lopez-Lorente, A; Suraci, A

    2008-01-01

    The LHC under commissioning at CERN will be the world's largest superconducting accelerator and therefore makes extensive use of cryogenic instruments. These instruments are installed in the tunnel and therefore have to withstand the LHC environment that imposes radiation-tolerant design and construction. Most of the instruments require individual calibration; some of them exhibit several variants as concerns measuring span; all relevant data are therefore stored in an Oracle® database. Those data are used for the various quality assurance procedures defined for installation and commissioning, as well as for generating tables used by the control system to configure automatically the input/output channels. This paper describes the commissioning of the sensors and the corresponding electronics, the first measurement results during the cool-down of one machine sector; it discusses the different encountered problems and their corresponding solutions.

  7. LHC brochure (Italian version)

    CERN Multimedia

    Lefevre, Christiane

    2011-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  8. LHC brochure (German version)

    CERN Multimedia

    Lefevre, Christiane

    2011-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which will start-up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  9. LHC brochure (French version)

    CERN Multimedia

    Lefevre, C

    2010-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  10. LHC brochure (Danish version)

    CERN Multimedia

    Lefevre, C

    2010-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  11. LHC brochure (English version)

    CERN Multimedia

    Lefevre, C

    2010-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  12. LHC brochure (French version)

    CERN Multimedia

    Marcastel, Fabienne

    2014-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  13. LHC brochure (English version)

    CERN Multimedia

    AUTHOR|(CDS)2070305

    2014-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  14. LHC Brochure (german version)

    CERN Multimedia

    Vanoli, C.

    2006-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which will start-up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  15. LHC brochure (German version)

    CERN Multimedia

    Lefevre, C

    2008-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which will start-up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  16. LHC brochure (German version)

    CERN Multimedia

    Marcastel, Fabienne

    2014-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which started up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  17. LHC brochure (Spanish version)

    CERN Multimedia

    Lefevre, C

    2008-01-01

    A presentation of the largest and the most powerful particle accelerator in the world, the Large Hadron Collider (LHC), which will start-up in 2008. Its role, characteristics, technologies, etc. are explained for the general public.

  18. The LHC goes 3G

    CERN Multimedia

    Anaïs Schaeffer

    2013-01-01

    A new telecommunications network has been installed in the LHC tunnel to facilitate operations during the long shutdown. Anyone using a smartphone, tablet or laptop computer will now be able to access the Internet from the tunnel.   Results of a download (green) and upload (yellow) test carried out in the LHC tunnel using the new Universal Mobile Telecommunications System (UMTS). The first long shutdown has officially begun, and the teams are about to enter the various tunnels around the Laboratory. It’s a good opportunity to talk telecommunications. As you can well imagine, even the highest of high-tech smartphones remains stubbornly silent and unresponsive 100 metres below the ground. Except at CERN… The IT-CS Group has implemented an impressive state-of-the-art solution to tackle this problem - a new Universal Mobile Telecommunications System (UMTS), better known as “3G”, covering the entire 27-km circumference of the LHC tunnel. Established on th...

  19. The LHC Superconducting RF System

    CERN Document Server

    Boussard, Daniel

    1999-01-01

    The European Laboratory for Particle Physics (CERN), the largest high energy physics laboratory worldwide, is constructing the Large Hadron Collider (LHC) in the existing 27 km circumference LEP (Large Electron Positron) collider tunnel. For the LHC, superconducting cavities, operating at 4.5 K, will provide the required acceleration field for ramping the beam energy up to 7 TeV and for keeping the colliding proton beams tightly bunched. Superconducting cavities were chosen, not only because of their high acceleration field leading to a small contribution to the machine impedance, but also because of their high stored energy which minimises the effects of periodic transient beam loading associated with the high beam intensity (0.5 A). There will be eight single-cell cavities per beam, each delivering 2 MV (5.3 MV/m) at 400 MHz. The cavities themselves are now being manufactured by industrial firms, using niobium on copper technology which gives full satisfaction at LEP. A complete cavity prototype assembly in...

  20. Accelerator magnet R/D in the perspective of a LHeC and HE-LHC, synergy or competition?

    International Nuclear Information System (INIS)

    Bottura, L.; Auchmann, B.; Bajko, M.; Ballarino, A.; Borgnolutti, F.; Ferracin, P.; Fessia, P.; Karppinen, M.; Kirby, G.; Oberli, L.; Perez, J.C.; Rossi, L.; Rijk, G. de; Russenschuck, S.; Smekens, D.; Todesco, E.; Tommasini, D.

    2012-01-01

    Beyond HL-LHC, CERN has a number of physics options that offer potential and challenges. This contribution dwells on the long-term projects HE-LHC and LHeC to put the magnet research and development at CERN (resistive and superconducting, slow and fast) in a long-term perspective. In particular synergies and parallel road-maps will be highlighted. We will show how the on-going development (2012-2015) on low-field, high-field, and low-loss magnets can be used towards longer term objectives. (authors)

  1. Accelerator Magnet R&D in the Perspective of a LHeC and HE-LHC - Synergy or Competion?

    CERN Document Server

    Bottura, L; Bajko, M; Ballarino, A; Borgnolutti, F; Ferracin, P; Fessia, P; Karppinen, M; Kirby, G; Oberli, L; Perez, J C; Rossi, L; De Rijk, G; Russenschuck, S; Smekens, D; Todesco, E; Tommasini, D

    2012-01-01

    Beyond HL-LHC, CERN has a number of physics options that offer potential and challenges. This contribution dwells on the long-term projects HE-LHC and LHeC to put the magnet R&D at CERN (resistive and superconducting, slow and fast) in a long-term perspective. In particular synergies and parallel roadmaps will be highlighted. We will show how the on-going development (2012-2015) on low-field, high-field, and low-loss magnets can be used towards longer term objectives.

  2. Large-Scale Experimental and Numerical Study of Blast Acceleration Created by Close-In Buried Explosion on Underground Tunnel Lining

    Directory of Open Access Journals (Sweden)

    Mohamad Reza Soheyli

    2016-01-01

    Full Text Available Despite growing demands for structures in water transportation tunnels, underground installations, subsurface dams, and subterranean channels, there is limited field knowledge about the dynamic behavior of these structures in the face of near-fault earthquakes or impulse excitations. This study conducted a large-scale test on underground tunnel excited by two close-in subsurface explosions. The horizontal and vertical acceleration were recorded on the vertical wall of the tunnel and the free field data including the acceleration on the ground surface at 11-meter distance from the tunnel. The frequency domain analysis of recorded results determined the frequency 961 Hz and 968 Hz for 1.69 kg and 2.76 kg equivalent T.N.T., respectively. Then, finite element analysis results were compared with the test data. The comparisons demonstrated a good correlation and satisfied the field data. Finally, based on numerical modeling, a parametric study was applied to determine the effects of shear wave velocity distance of the crater with respect to the tunnel on impulse response of the tunnel.

  3. LHC Supertable

    CERN Document Server

    Pereira, M; Lamont, M; Muller, GJ; Teixeira, D D; McCrory, ES

    2011-01-01

    LHC operations generate enormous amounts of data. This data is being stored in many different databases. Hence, it is difficult for operators, physicists, engineers and management to have a clear view on the overall accelerator performance. Until recently the logging database, through its desktop interface TIMBER, was the only way of retrieving information on a fill-by-fill basis. The LHC Supertable has been developed to provide a summary of key LHC performance parameters in a clear, consistent and comprehensive format. The columns in this table represent main parameters that describe the collider’s operation such as luminosity, beam intensity, emittance, etc. The data is organized in a tabular fill-by-fill manner with different levels of detail. Particular emphasis was placed on data sharing by making data available in various open formats. Typically the contents are calculated for periods of time that map to the accelerator’s states or beam modes such as Injection, Stable Beams, etc. Data retrieval and ...

  4. LHC Report

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    During last week the commissioning effort has been devoted to beam development work, required to accelerate beams with nominal bunch intensity to 3.5 TeV. Significant progress has been done with the commissioning of the systems required to control the beam size and bunch length during the ramp and accelerate the beam with reproducible characteristics. The setting-up of the collimation system for the operation with higher intensity is presently ongoing with the aim of delivering physics with nominal bunch intensity towards the end of next week. For more information about the LHC and a video of the presentation recently done by LHC operators, please visit: http://lpcc.web.cern.ch/LPCC/ http://indico.cern.ch/categoryDisplay.py?categId=2687

  5. LHC physics

    National Research Council Canada - National Science Library

    Binoth, T

    2012-01-01

    "Exploring the phenomenology of the Large Hadron Collider (LHC) at CERN, LHC Physics focuses on the first years of data collected at the LHC as well as the experimental and theoretical tools involved...

  6. Precision transport of LHC superconducting magnet

    CERN Multimedia

    Maximilien Brice

    2003-01-01

    These photos show tests of the first convoy with a prototype short straight section (SSS) quadrupole in the LHC tunnel. There is little free space in the tunnel as the SSS convoy passes alongside a dipole vacuum vessel. These convoys feature infrared guidance, which offsets the minimal clearance in the tunnel and limits vibration, both of which could damage the fragile magnets.

  7. Quantum Diaries Blog: Is the moon full? Just ask the LHC operators

    CERN Multimedia

    Pauline Gagnon

    2012-01-01

    Corrections to proton orbits in the LHC appear as regular dips in the instantaneous luminosity measured by CMS (beige) and ATLAS (green).   The LHC is so large that the gravitational force exerted by the moon is not the same at all points, which creates small distortions of the tunnel. And the machine is sensitive enough to detect minute deformations created by the small differences in gravitational force across its diameter. Therefore, the orbits of protons in the accelerator have to be adjusted regularly to account for the gravitational effect of the moon. Read more on the Quantum Diaries Blog post.

  8. 11 June 2013- Autrian Federal President Dr Heinz Fischer and Federal Minister Prof. Dr Karlheinz Töchterle visit CMS cavern and LHC tunnel at Point 5 and the ASACUSA and AEGIS experiments on the AD. Signature of the guest book in the Globe of Science and Innovation after a round table with 10 young austrian scientists. Family photograph in front of an LHC magnet.

    CERN Multimedia

    TEAM VMO

    2013-01-01

    Welcome line: on French territory by the Representative of the French Republic S. Donnot, Sous-Préfet de Gex; CERN Director-General R. Heuer; Director for Research and Scientific Computing S. Bertolucci; Director for Accelerators and Technology S. Myers; Director for Administration and general Infrastructure S. Lettow; Head of Technology Department F. Bordry; CERN Austrian Circle Spokesperson F. Eder and CERN Protocol S. Molinari. First Lady and Federal Minister Töchterle follow. CERN-HI-1306154 19-32: in CMS conference room, building 3562: general presentation of the Laboratory by the DG; CERN-HI-1306154 33-43: visiting the LHC tunnel at Point 5 with Head of Technology Department F. Bordry CERN-HI-1306154 44-64: in the CMS cavern with Collaboration Spokesperson J. Incandela and CMS and Austrian Academy of Sciences C. Wulz; CERN-HI-1306154 65-90: ASACUSA with E. Widmann and AEGIS with M. Doser. CERN-HI-1306154 91-115: round table, signatures and exchange of gifts in the Globe of Science and Innovation; fa...

  9. 2008 LHC Open Days LHC magnets on display

    CERN Multimedia

    2008-01-01

    Over the last few years you’ve probably seen many of the 15 m long blue LHC dipole magnets being ferried around the site. Most of them are underground now, but on the LHC Open Days on 5 and 6 April the magnets will also play a central role on the surface. Installation of one of the LHC dipole magnets on the Saint-Genis roundabout on 7 March. The LHC dipole testing facility with several magnets at various stages of testing. The 27 km ring of the LHC consists of 1232 double-aperture superconducting dipole magnets, 360 short straight sections (SSS) and 114 special SSS for the insertion regions. On the Open Day, you will be able to "Follow the LHC magnets" through different stages around the site, culminating in their descent into the tunnel. Discover all the many components that have to be precisely integrated in the magnet casings, and talk to the engine...

  10. Commissioning of the LHC Cryogenic System Subsystems Cold Commissioning in Preparation of Full Sector Tests

    CERN Document Server

    Serio, L; Ferlin, G; Gilbert, N; Gruehagen, Henning; Knoops, S; Parente, C; Sanmartí, M

    2006-01-01

    The cryogenic system for the Large Hadron Collider accelerator is presently in its final phase of installation and commissioning at nominal operating temperatures. The refrigeration capacity for the LHC will be produced using eight large cryogenic plants installed on five technical sites and distributed around the 26.7-km circumference ring located in a deep underground tunnel. The status of the cryogenic system commissioning is presented together with the experience gained in operating and commissioning it.

  11. SEU tests performed on the digital communication system for LHC cryogenic instrumentation

    International Nuclear Information System (INIS)

    Casas-Cubillos, J.; Faccio, F.; Gomes, P.; Martin, M.A.; Rodriguez-Ruiz, M.A.

    2002-01-01

    The future LHC particle accelerator will use a large number of cryogenic sensors and actuators, most of which are located inside the machine tunnel and therefore in a radiation environment. These elements will communicate through a fieldbus. This paper reports the irradiation study carried out on WorldFIP fieldbus communication system. A digital communication system based on WorldFIP fieldbus protocol has been implemented and single event effects and total ionizing dose radiation tests have been performed on it

  12. Super High Energy Colliding Beam Accelerators

    International Nuclear Information System (INIS)

    Abdelaziz, M.E.

    2009-01-01

    This lecture presents a review of cyclic accelerators and their energy limitations. A description is given of the phase stability principle and evolution of the synchrotron, an accelerator without energy limitation. Then the concept of colliding beams emerged to yield doubling of the beam energy as in the Tevatron 2 trillion electron volts (TeV) proton collider at Fermilab and the Large Hadron Collider (LHC) which is now planned as a 14-TeV machine in the 27 kilometer tunnel of the Large Electron Positron (LEP) collider at CERN. Then presentation is given of the Superconducting Supercollider (SSC), a giant accelerator complex with energy 40-TeV in a tunnel 87 kilometers in circumference under the country surrounding Waxahachie in Texas, U.S.A. These superhigh energy accelerators are intended to smash protons against protons at energy sufficient to reveal the nature of matter and to consolidate the prevailing general theory of elementary particle.

  13. HL-LHC alternatives

    CERN Document Server

    Tomás, R; White, S

    2014-01-01

    The HL-LHC parameters assume unexplored regimes for hadron colliders in various aspects of accelerator beam dynamics and technology. This paper reviews three alternatives that could potentially improve the LHC performance: (i) the alternative filling scheme 8b+4e, (ii) the use of a 200 MHz RF system in the LHC and (iii) the use of proton cooling methods to reduce the beam emittance (at top energy and at injection). The alternatives are assessed in terms of feasibility, pros and cons, risks versus benefits and the impact on beam availability.

  14. The super-LHC

    CERN Document Server

    Mangano, Michelangelo L

    2010-01-01

    We review here the prospects of a long-term upgrade programme for the Large Hadron Collider (LHC), CERN laboratory's new proton-proton collider. The super-LHC, which is currently under evaluation and design, is expected to deliver of the order of ten times the statistics of the LHC. In addition to a non-technical summary of the principal physics arguments for the upgrade, I present a pedagogical introduction to the technological challenges on the accelerator and experimental fronts, and a review of the current status of the planning.

  15. LHC preparations change gear

    International Nuclear Information System (INIS)

    Anon.

    1995-01-01

    After the formal approval by CERN Council in December (January, page 1) of the LHC protonproton collider for CERN's 27- kilometre LEP tunnel, preparations for the new machine change gear. Lyndon Evans becomes LHC Project Leader, and CERN's internal structure will soon be reorganized to take account of the project becoming a definite commitment. On the experimental side, the full Technical Proposals for the big general purpose ATLAS and CMS detectors were aired at a major meeting of the LHC Committee at CERN in January. These Technical Proposals are impressive documents each of some several hundred pages. (Summaries of the detector designs will appear in forthcoming issues of the CERN Courier.) The ALICE heavy ion experiment is not far behind, and plans for other LHC experiments are being developed. Playing an important role in this groundwork has been the Detector Research and Development Committee (DRDC), founded in 1990 to foster detector development for the LHC experimental programme and structured along the lines of a traditional CERN Experiments Committee. Established under the Director Generalship of Carlo Rubbia and initially steered by Research Director Walter Hoogland, the DRDC has done sterling work in blazing a trail for LHC experiments. Acknowledging that the challenge of LHC experimentation needs technological breakthroughs as well as specific detector subsystems, DRDC proposals have covered a wide front, covering readout electronics and computing as well as detector technology. Its first Chairman was Enzo larocci, succeeded in 1993 by Michal Turala. DRDC's role was to evaluate proposals, and make recommendations to CERN's Research Board for approval and resource allocation, not an easy task when the LHC project itself had yet to be formally approved. Over the years, a comprehensive portfolio of detector development has been built up, much of which has either led to specific LHC detector subsystems for traditional detector tasks

  16. Accelerator update

    International Nuclear Information System (INIS)

    Anon.

    1995-01-01

    When the Accelerator Conference, combined International High Energy and US Particle versions, held in Dallas in May, was initially scheduled, progress nearby for the US Superconducting Supercollider was high on the preliminary agenda. With the SSC voted down by Congress in October 1993, this was no longer the case. However the content of the meeting, in terms of both its deep implications for ambitious new projects and the breadth of its scope, showed that the worldwide particle accelerator field is far from being moribund. A traditional feature of such accelerator conferences is the multiplicity of parallel sessions. No one person can attend all sessions, so that delegates can follow completely different paths and emerge with totally different impressions. Despite this overload, and despite the SSC cancellation, the general picture is one of encouraging progress over a wide range of major new projects throughout the world. At the same time, spinoff from, and applications of, accelerators and accelerator technology are becoming increasingly important. Centrestage is now CERN's LHC proton-proton collider, where a test string of superconducting magnets is operating over long periods at the nominal LHC field of 8.36 tesla or more. The assignment of the underground areas in the existing 27- kilometre LEP tunnel is now quasidefinitive (see page 3). For CERN's existing big machine, the LEP electron-positron collider, ongoing work concentrates on boosting performance using improved optics and bunch trains. But the main objective is the LEP2 scheme using superconducting accelerating cavities to boost the beam energy (see page 6). After some initial teething problems, production and operation of these cavities appears to have been mastered, at least under test conditions. A highlight at CERN last year was the first run with lead ions (December 1994, page 15). Handling these heavy particles with systems originally designed for protons calls for ingenuity. The SPS

  17. Accelerator update

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    1995-09-15

    When the Accelerator Conference, combined International High Energy and US Particle versions, held in Dallas in May, was initially scheduled, progress nearby for the US Superconducting Supercollider was high on the preliminary agenda. With the SSC voted down by Congress in October 1993, this was no longer the case. However the content of the meeting, in terms of both its deep implications for ambitious new projects and the breadth of its scope, showed that the worldwide particle accelerator field is far from being moribund. A traditional feature of such accelerator conferences is the multiplicity of parallel sessions. No one person can attend all sessions, so that delegates can follow completely different paths and emerge with totally different impressions. Despite this overload, and despite the SSC cancellation, the general picture is one of encouraging progress over a wide range of major new projects throughout the world. At the same time, spinoff from, and applications of, accelerators and accelerator technology are becoming increasingly important. Centrestage is now CERN's LHC proton-proton collider, where a test string of superconducting magnets is operating over long periods at the nominal LHC field of 8.36 tesla or more. The assignment of the underground areas in the existing 27- kilometre LEP tunnel is now quasidefinitive (see page 3). For CERN's existing big machine, the LEP electron-positron collider, ongoing work concentrates on boosting performance using improved optics and bunch trains. But the main objective is the LEP2 scheme using superconducting accelerating cavities to boost the beam energy (see page 6). After some initial teething problems, production and operation of these cavities appears to have been mastered, at least under test conditions. A highlight at CERN last year was the first run with lead ions (December 1994, page 15). Handling these heavy particles with systems originally designed for protons calls for ingenuity. The SPS has managed

  18. LS1 Report: across the accelerator complex

    CERN Multimedia

    Simon Baird

    2013-01-01

    The warm-up of the first LHC sector (5-6) is now complete; it is at room temperature for the first time in over three years. Next week, the W bellows in this sector will be opened in preparation for the consolidation of the superconducting circuits, splices and interconnections (the SMACC project). Elsewhere in the LHC, the ELQA tests and the warm-up of the remaining seven sectors are proceeding as planned.   Vacuum leak tests are performed on the magnets before the LHC is brought up to ambient temperature. The SPS magnet test programme was completed on 26 March and work has already begun in the SPS tunnel. Among the activities being carried out is the installation of 16 specially coated vacuum chambers in the SPS main dipole magnets around BA5. The first of these dipole magnets were removed from the SPS tunnel today, Friday 5 April. By reducing the build-up of electron clouds around the LHC beam during acceleration in the SPS, this activity will play a key role in the increase of LHC beam in...

  19. 13 September 2013 - Chairman of the Board of Directors of the von Karman Institute Kingdom of Belgium J.-P. Contzen visiting the ATLAS experimental cavern with ATLAS Former Spokesperson P. Jenni; visiting the LHC tunnel at Point 1 with Technology Department N. Delruelle and signing the guest book with Technology Department Head F. Bordry. International Relations Adviser T. Kurtyka present.

    CERN Multimedia

    Laurent Egli (visit)

    2013-01-01

    13 September 2013 - Chairman of the Board of Directors of the von Karman Institute Kingdom of Belgium J.-P. Contzen visiting the ATLAS experimental cavern with ATLAS Former Spokesperson P. Jenni; visiting the LHC tunnel at Point 1 with Technology Department N. Delruelle and signing the guest book with Technology Department Head F. Bordry. International Relations Adviser T. Kurtyka present.

  20. 18 December 2013 - P. Kron Chairman and Chief Executive Officer of ALSTOM signing the Guest Book with the Director-General R. Heuer and visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry. Accompanied by P. Fassnacht throughout.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    18 December 2013 - P. Kron Chairman and Chief Executive Officer of ALSTOM signing the Guest Book with the Director-General R. Heuer and visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry. Accompanied by P. Fassnacht throughout.

  1. 29 November 2013 - U. Humphrey Orjiako Nigerian Ambassador Extraordinary and Plenipotentiary Permanent Mission to the United Nations Office and other international organisations in Geneva signing the Guest Book with Head of International Relations R. Voss, visiting the LHC tunnel at Point 2 and the ALICE cavern with ALICE Collaboration Deputy Spokesperson Y. Schutz.

    CERN Multimedia

    Noemi Caraban

    2013-01-01

    29 November 2013 - U. Humphrey Orjiako Nigerian Ambassador Extraordinary and Plenipotentiary Permanent Mission to the United Nations Office and other international organisations in Geneva signing the Guest Book with Head of International Relations R. Voss, visiting the LHC tunnel at Point 2 and the ALICE cavern with ALICE Collaboration Deputy Spokesperson Y. Schutz.

  2. 9th January 2012 - Indonesian Extraordinary and Plenipotentiary Ambassador Triansyah Djani to to the United Nations, WTO and other International Organisations in Geneva signing the guest book with Head of International Relations F. Pauss and Adviser E. Tsesmelis, visiting the LHC tunnel at Point 5 and CMS underground experimental area with Collaboration Spokesperson J. Incandela.

    CERN Document Server

    Estelle Spirig

    2012-01-01

    9th January 2012 - Indonesian Extraordinary and Plenipotentiary Ambassador Triansyah Djani to to the United Nations, WTO and other International Organisations in Geneva signing the guest book with Head of International Relations F. Pauss and Adviser E. Tsesmelis, visiting the LHC tunnel at Point 5 and CMS underground experimental area with Collaboration Spokesperson J. Incandela.

  3. Senior Senator from Florida and Chairman, Senate Committee on Space, Aeronautics and Related Sciences W. Nelson, visiting the ATLAS cavern and LHC tunnel with ATLAS Collaboration Spokesperson P. Jenni and AMS Collaboration Spokesperson S.C.C.Ting, 16 March 2008.

    CERN Multimedia

    Maximilien Brice

    2008-01-01

    Senior Senator from Florida and Chairman, Senate Committee on Space, Aeronautics and Related Sciences W. Nelson, visiting the ATLAS cavern and LHC tunnel with ATLAS Collaboration Spokesperson P. Jenni and AMS Collaboration Spokesperson S.C.C.Ting, 16 March 2008.

  4. 10 February 2012 - Permanent Representative of the Republic of India to the Conference on Disarmament, United Nations Office at Geneva Ambassador Mehta signing the guest book with International Relations Adviser R. Voss;in the LHC tunnel at Point 2 and ALICE underground experimental area with Collaboration Deputy Spokesperson Y. Schutz.

    CERN Document Server

    Maximilien Brice

    2012-01-01

    10 February 2012 - Permanent Representative of the Republic of India to the Conference on Disarmament, United Nations Office at Geneva Ambassador Mehta signing the guest book with International Relations Adviser R. Voss;in the LHC tunnel at Point 2 and ALICE underground experimental area with Collaboration Deputy Spokesperson Y. Schutz.

  5. 17 October 2013 - C. Ashton High Representative of the European Union for Foreign Affairs and Security Policy, Vice-President of the European Commission visiting the ATLAS cavern with ATLAS Collaboration Spokesperson D. Charlton; visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the Guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Maximilien Brice

    2013-01-01

    17 October 2013 - C. Ashton High Representative of the European Union for Foreign Affairs and Security Policy, Vice-President of the European Commission visiting the ATLAS cavern with ATLAS Collaboration Spokesperson D. Charlton; visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the Guest book with CERN Director-General R. Heuer.

  6. 5 June 2013 - European Union Ambassador to Switzerland and the Principality of Liechtenstein R. Jones in the ATLAS cavern with ATLAS Collaboration Deputy Spokesperson T. Wengler, in the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the guest book with Director-General R. Heuer. Head of the EU Projects Office S. Stavrev present.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    5 June 2013 - European Union Ambassador to Switzerland and the Principality of Liechtenstein R. Jones in the ATLAS cavern with ATLAS Collaboration Deputy Spokesperson T. Wengler, in the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the guest book with Director-General R. Heuer. Head of the EU Projects Office S. Stavrev present.

  7. 21 May 2013 - Slovakian State Secretary, Ministry of Health V. Čislák signing the Guest Book with CERN Director-General R. Heuer; in the LHC tunnel at Point 2 with V. Senaj (Technology Department); in the ALICE experimental cavern with P. Chochula (Physics Department). M. Cirilli (Knowledge Transfer Group) present.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    21 May 2013 - Slovakian State Secretary, Ministry of Health V. Čislák signing the Guest Book with CERN Director-General R. Heuer; in the LHC tunnel at Point 2 with V. Senaj (Technology Department); in the ALICE experimental cavern with P. Chochula (Physics Department). M. Cirilli (Knowledge Transfer Group) present.

  8. 20 December 2013 - R. M. Cordeiro Dunlop Ambassador Permanent Representative of Brazil to the United Nations Office and other international organisations in Geneva visiting the LHC tunnel at Point 5 with CMS Collaboration, CERN Team Leader A. Petrilli and signing the Guest Book with CERN Director-General. Accompanied by J. Salicio and R. Voss throughout.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    20 December 2013 - R. M. Cordeiro Dunlop Ambassador Permanent Representative of Brazil to the United Nations Office and other international organisations in Geneva visiting the LHC tunnel at Point 5 with CMS Collaboration, CERN Team Leader A. Petrilli and signing the Guest Book with CERN Director-General. Accompanied by J. Salicio and R. Voss throughout.

  9. 27 June 2012 - Ambassador K. Pierce, Permanent Representative of the United Kingdom of Great Britain and Northern Ireland to the United Nations Office and other international organisations in Geneva visiting the LHC tunnel at Point 5 with Department Head P. Collier and CMS control room with Former Collaboration Spokesperson J. Virdee.

    CERN Multimedia

    Laurent Egli

    2012-01-01

    27 June 2012 - Ambassador K. Pierce, Permanent Representative of the United Kingdom of Great Britain and Northern Ireland to the United Nations Office and other international organisations in Geneva visiting the LHC tunnel at Point 5 with Department Head P. Collier and CMS control room with Former Collaboration Spokesperson J. Virdee.

  10. 12 December 2013 - Sir Konstantin Novoselov, Nobel Prize in Physics 2010, signing the guest book with International Relations Adviser E. Tsesmelis; visiting the ATLAS experimental cavern with Spokesperson D. Charlton; in the LHC tunnel with Technology Department Head F. Bordry. I. Antoniadis, CERN Theory Group Leader, accompanies throughout.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    12 December 2013 - Sir Konstantin Novoselov, Nobel Prize in Physics 2010, signing the guest book with International Relations Adviser E. Tsesmelis; visiting the ATLAS experimental cavern with Spokesperson D. Charlton; in the LHC tunnel with Technology Department Head F. Bordry. I. Antoniadis, CERN Theory Group Leader, accompanies throughout.

  11. 1 April 2014 - President of the Parliament of the Principality of Liechtenstein A. Frick and his delegation visiting the LHC tunnel at Point 1 with Technology Department Head J.M. Jiménez and signing the Guest book with CERN Director-General R. Heuer. Deputy Head of International Relations E. Tsesmelis present throughout.

    CERN Multimedia

    Pantelia, Anna

    2014-01-01

    1 April 2014 - President of the Parliament of the Principality of Liechtenstein A. Frick and his delegation visiting the LHC tunnel at Point 1 with Technology Department Head J.M. Jiménez and signing the Guest book with CERN Director-General R. Heuer. Deputy Head of International Relations E. Tsesmelis present throughout.

  12. 17 September 2013 - Estonian Minister of Education and Research J. Aaviksoo signing the guest book with CERN Director-General R- Heuer; visiting the TOTEM facility with TOTEM Collaboration Spokesperson S. Giani; in the LHC tunnel at Point 5 with International Relations Adviser T. Kurtyka and visiting the CMS cavern with CMS Collaboration Spokesperson J. Incandela. International Relations Adviser R. Voss present.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    17 September 2013 - Estonian Minister of Education and Research J. Aaviksoo signing the guest book with CERN Director-General R- Heuer; visiting the TOTEM facility with TOTEM Collaboration Spokesperson S. Giani; in the LHC tunnel at Point 5 with International Relations Adviser T. Kurtyka and visiting the CMS cavern with CMS Collaboration Spokesperson J. Incandela. International Relations Adviser R. Voss present.

  13. 19 January 2011 - Korean Vice Minister II of Education, Science and Technology K.Chang-Kyung with Adviser R. Voss, Director-General R. Heuer and head of International Relations F. Pauss; in the LHC tunnel at Point 5 and CMS experimental cavern with Collaboration Spokesperson G. Tonelli.

    CERN Multimedia

    Maximilien Brice

    2011-01-01

    Korean vice-minister II of education, science and technology, Kim Chang-Kyung, visiting the CMS experimental area at CERN on 19 January. He also had the opportunity to view part of the LHC tunnel, as well as to visit the CERN Control Centre.

  14. 16 Augur 2013 -Bulgarian Minister of Education and Sciences A. Klisarova visiting the LHC tunnel with S. Russenschuck and CMS experimental cavern with Deputy Spokesperson T. Camporesi and V. Genchev ; signing the guest book with CERN Director-General R. Heuer. Accompanied throughout by P. Hristov, L. Litov, R. Voss and Z. Zaharieva.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    16 Augur 2013 -Bulgarian Minister of Education and Sciences A. Klisarova visiting the LHC tunnel with S. Russenschuck and CMS experimental cavern with Deputy Spokesperson T. Camporesi and V. Genchev ; signing the guest book with CERN Director-General R. Heuer. Accompanied throughout by P. Hristov, L. Litov, R. Voss and Z. Zaharieva.

  15. 7 May 2013 - Ambassador of the Federal Republic of Germany to Switzerland and Liechtenstein P. Gottwald and Mrs Gottwald in the ATLAS experimental cavern and LHC tunnel with Collaboration Deputy Spokesperson T. Wengler and German Scientists A. Schopper and V. Mertens.

    CERN Multimedia

    Maximilien Brice

    2013-01-01

    7 May 2013 - Ambassador of the Federal Republic of Germany to Switzerland and Liechtenstein P. Gottwald and Mrs Gottwald in the ATLAS experimental cavern and LHC tunnel with Collaboration Deputy Spokesperson T. Wengler and German Scientists A. Schopper and V. Mertens.

  16. 16 December 2013 - P. Lavie President of the Technion Institute of Technology in Israel visiting the ATLAS cavern with ATLAS Deputy Spokesperson T. Wengler; visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the Guest Book with CERN Director-General R. Heuer. G. Mikenberg, E. Rabinovici, Y. Rozen and S. Tarem present throughout.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    16 December 2013 - P. Lavie President of the Technion Institute of Technology in Israel visiting the ATLAS cavern with ATLAS Deputy Spokesperson T. Wengler; visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and signing the Guest Book with CERN Director-General R. Heuer. G. Mikenberg, E. Rabinovici, Y. Rozen and S. Tarem present throughout.

  17. 14 February 2012 - Ambassadors from Algeria, Brunei Darussalam, Canada, Chad, Tunisia, Permanent Representatives to the United Nations Office at Geneva in the LHC tunnel at Point 1, ATLAS visitor centre, and ATLAS underground experimental area, throughout accompanied by Advisers P. Fassnacht, E. Tsesmelis and R. Voss

    CERN Multimedia

    Jean-Claude Gadmer

    2012-01-01

    14 February 2012 - Ambassadors from Algeria, Brunei Darussalam, Canada, Chad, Tunisia, Permanent Representatives to the United Nations Office at Geneva in the LHC tunnel at Point 1, ATLAS visitor centre, and ATLAS underground experimental area, throughout accompanied by Advisers P. Fassnacht, E. Tsesmelis and R. Voss

  18. 8 April 2013 - Indian Hon'ble Minister for Ministry of Science & Technology and Ministry of Earth Sciences Shri Sudini Jaipal Reddy in the LHC tunnel with K. Foraz, visiting the CMS cavern with Technical Coordinator A. Ball and Former Spokesperson T. Virdee, signing the guest book with Director-General R. Heuer.

    CERN Multimedia

    Samuel Morier-Genoud

    2013-01-01

    8 April 2013 - Indian Hon'ble Minister for Ministry of Science & Technology and Ministry of Earth Sciences Shri Sudini Jaipal Reddy in the LHC tunnel with K. Foraz, visiting the CMS cavern with Technical Coordinator A. Ball and Former Spokesperson T. Virdee, signing the guest book with Director-General R. Heuer.

  19. 17 January 2014 - Y. Sakurada Japanese Senior Vice Minister of Education, Culture, Sports, Science and Technology signing the Guest book with CERN Director-General R. Heuer and visiting the LHC tunnel at Point 1 with Technology Department Head J.M. Jiménez. Head of International Relations R. Voss present throughout.

    CERN Multimedia

    Pantelia, Anna

    2014-01-01

    17 January 2014 - Y. Sakurada Japanese Senior Vice Minister of Education, Culture, Sports, Science and Technology signing the Guest book with CERN Director-General R. Heuer and visiting the LHC tunnel at Point 1 with Technology Department Head J.M. Jiménez. Head of International Relations R. Voss present throughout.

  20. 30 August 2013 - Senior Vice Minister for Foreign Affairs in Japan M. Matsuyama signing the guest book with CERN Director-General; visit the ATLAS experimental cavern with ATLAS Spokesperson D. Charlton and visiting the LHC tunnel at Point 1 with former ATLAS Japan national contact physicist T. Kondo. R. Voss and K. Yoshida present throughout.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    30 August 2013 - Senior Vice Minister for Foreign Affairs in Japan M. Matsuyama signing the guest book with CERN Director-General; visit the ATLAS experimental cavern with ATLAS Spokesperson D. Charlton and visiting the LHC tunnel at Point 1 with former ATLAS Japan national contact physicist T. Kondo. R. Voss and K. Yoshida present throughout.

  1. 5 June 2013 - Sri Lankan Senior Minister of Scientific Affairs T. Vitharana signing the guest book with Director-General R. Heuer, in the LHC tunnel at Point 5 with International Relations Adviser R. Voss and in the CMS cavern with CERN Team leader A. Petrilli.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    5 June 2013 - Sri Lankan Senior Minister of Scientific Affairs T. Vitharana signing the guest book with Director-General R. Heuer, in the LHC tunnel at Point 5 with International Relations Adviser R. Voss and in the CMS cavern with CERN Team leader A. Petrilli.

  2. 16 July 2013 - Israel Ministry of Education Director-General D. Stauber in the LHC tunnel at Point 1 with L. Tavian, visiting the ATLAS experimental cavern with Senior Physicist G. Mikenberg; Israeli Delegate to CERN Council E. Rabinovici and CERN Adviser for Israel E. Tsesmelis present; signing the guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    16 July 2013 - Israel Ministry of Education Director-General D. Stauber in the LHC tunnel at Point 1 with L. Tavian, visiting the ATLAS experimental cavern with Senior Physicist G. Mikenberg; Israeli Delegate to CERN Council E. Rabinovici and CERN Adviser for Israel E. Tsesmelis present; signing the guest book with CERN Director-General R. Heuer.

  3. 24 May 2013 - Rector of the Polish Stanislaw Staszic AGH University of Science and Technology T. Slomka in the LHC tunnel at Point 8 with Senior Polish Staff Member A. Siemko, in LHCb experimental cavern with LHCb Collaboration Spokesperson P. Campana and signing the guest book with Director-General R. Heuer. Adviser for Eastern Europe T. Kurtyka present.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    24 May 2013 - Rector of the Polish Stanislaw Staszic AGH University of Science and Technology T. Slomka in the LHC tunnel at Point 8 with Senior Polish Staff Member A. Siemko, in LHCb experimental cavern with LHCb Collaboration Spokesperson P. Campana and signing the guest book with Director-General R. Heuer. Adviser for Eastern Europe T. Kurtyka present.

  4. 31 Jannuary 2012 - Pakistan COMSATS Executive Director I. E. Qureshi visiting the LHC tunnel at Point 2 with ALICE Collaboration Spokesperson P. Giubellino and International Relations Adviser R. Voss; Exchange of gifts and signature of the guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Maximilien Brice

    2012-01-01

    31 Jannuary 2012 - Pakistan COMSATS Executive Director I. E. Qureshi visiting the LHC tunnel at Point 2 with ALICE Collaboration Spokesperson P. Giubellino and International Relations Adviser R. Voss; Exchange of gifts and signature of the guest book with CERN Director-General R. Heuer.

  5. 1 October 2013 - British Minister of State for Trade and Investment Lord Green of Hurstpierpoint signing the guest book with Head of Internationals Relations R. Voss; visiting the LHC tunnel at Point 1 and the ATLAS experimental cavern with ATLAS Collaboration Members K. Behr and J. Catmore.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    1 October 2013 - British Minister of State for Trade and Investment Lord Green of Hurstpierpoint signing the guest book with Head of Internationals Relations R. Voss; visiting the LHC tunnel at Point 1 and the ATLAS experimental cavern with ATLAS Collaboration Members K. Behr and J. Catmore.

  6. Design approach for the development of a cryomodule for compact crab cavities for Hi-Lumi LHC

    Science.gov (United States)

    Pattalwar, Shrikant; Jones, Thomas; Templeton, Niklas; Goudket, Philippe; McIntosh, Peter; Wheelhouse, Alan; Burt, Graeme; Hall, Ben; Wright, Loren; Peterson, Tom

    2014-01-01

    A prototype Superconducting RF (SRF) cryomodule, comprising multiple compact crab cavities is foreseen to realise a local crab crossing scheme for the "Hi-Lumi LHC", a project launched by CERN to increase the luminosity performance of LHC. A cryomodule with two cavities will be initially installed and tested on the SPS drive accelerator at CERN to evaluate performance with high-intensity proton beams. A series of boundary conditions influence the design of the cryomodule prototype, arising from; the complexity of the cavity design, the requirement for multiple RF couplers, the close proximity to the second LHC beam pipe and the tight space constraints in the SPS and LHC tunnels. As a result, the design of the helium vessel and the cryomodule has become extremely challenging. This paper assesses some of the critical cryogenic and engineering design requirements and describes an optimised cryomodule solution for the evaluation tests on SPS.

  7. Optical fibres bringing the LHC into focus

    CERN Multimedia

    2003-01-01

    New components are being added to CERN's optical fibre network, which will transport the torrents of data produced by the LHC. 1500 kilometres of cables will be installed in the tunnels and at ground level.

  8. LHC Cryogenics on the mend

    CERN Multimedia

    2004-01-01

    On 29 September, repairs began on the LHC cryogenic distribution line, or QRL, to replace a faulty part that occurs in the hundreds of elements of the line that are already on-site. The Accelerator Technology Department is designing a work programme to finish the repairs as soon as possible and minimize delays to the rest of the LHC project.

  9. The LHC's equipment all in step

    CERN Multimedia

    2005-01-01

    Over 80% of the control equipment for the LHC will be connected by a special communication network known as WorldFIP, which has been chosen for its very precise timing, excellent operating performance and robustness in difficult environments. Over 350 kilometres of this network are currently being installed in the LHC tunnel and checked for compliance with the required standards.

  10. Protons on the doorstep of the LHC

    CERN Multimedia

    Mertens, Volker

    2005-01-01

    The first of the two new beam transfer lines to the LHC was successfully commissioned in autumn 2004. At the first attempt a low-intensity proton beam passed down the line to a few meters before the LHC tunnel (3 pages)

  11. The last LHC dipole magnet is lowered

    CERN Multimedia

    Claudia Marcelloni

    2007-01-01

    A ceremony is held as the last of 1746 superconducting magnets is lowered into the 27-km circumference tunnel that houses the LHC. The LHC project leader, Lyn Evans, changes a banner reading ‘first magnet for the LHC’ to ‘last magnet for the LHC’ in his native Welsh.

  12. arXiv Analytical methods for vacuum simulations in high energy accelerators for future machines based on LHC performances

    CERN Document Server

    Aichinger, Ida; Chiggiato, Paolo

    The Future Circular Collider (FCC), currently in the design phase, will address many outstanding questions in particle physics. The technology to succeed in this 100 km circumference collider goes beyond present limits. Ultra-high vacuum conditions in the beam pipe is one essential requirement to provide a smooth operation. Different physics phenomena as photon-, ion- and electron- induced desorption and thermal outgassing of the chamber walls challenge this requirement. This paper presents an analytical model and a computer code PyVASCO that supports the design of a stable vacuum system by providing an overview of all the gas dynamics happening inside the beam pipes. A mass balance equation system describes the density distribution of the four dominating gas species $\\text{H}_2, \\text{CH}_4$, $\\text{CO}$ and $\\text{CO}_2$. An appropriate solving algorithm is discussed in detail and a validation of the model including a comparison of the output to the readings of LHC gauges is presented. This enables the eval...

  13. Radiation tolerance assurance of technical equipment in the LHC radiation monitoring for technical equipment at the LHC

    CERN Document Server

    Wijnands, Thijs; CERN. Geneva. TS Department

    2005-01-01

    In contrast with other accelerators at CERN, a large amount of technical equipment will be located in the LHC tunnel, the underground areas and in the experimental caverns where they will be exposed to radiation. Nearly all this equipment makes, to a certain extent, use of commercial microelectronics which is extremely sensitive to radiation damage, both instantaneous damage and cumulative damage. Examples in the TS Department are the electronics for the position sensors of the low beta quadrupoles, the access system, the cooling and ventilation units, the electronics for the electrical distribution, the oxygen deficiency monitors and fire detection systems. The basic effects of radiation on electronic systems and components are well understood because similar problems with radiation are encountered in the aerospace and aviation industry. Since 1998, an efficient and original Radiation Tolerance Assurance approach for the LHC machine has been established. Its aim is to minimise the effects of radiation damage...

  14. CERN Open Days 2013, Point 4: LHC Radio Frequency

    CERN Multimedia

    CERN Photolab

    2013-01-01

    Stand description: At Point 4 visitors will descend into the LHC tunnel to see the "engine" of the collider: the accelerating cavities where the circulating particles get a small kick of energy as they pass by 11,000 times each second. During your visit underground, you will see the superconducting magnets as well as instruments for observing the beams. You will also walk through the huge cavern containing the Radio Frequency power plants which provide the particle beams with energy. On surface no restricted access  Above ground, you will see the cryogenics installations which keep the accelerator at a just few degrees above absolute zero. Lots of fascinating information and exhibits about CERN's accelerators and experiments will be on display, with CERN engineers and physicists on hand all day to answer your questions.

  15. LHC magnet string in 1994

    CERN Multimedia

    1994-01-01

    On 6-7 December 1994, a string of powerful superconducting magnets for CERN's next particle accelerator, the Large Hadron Collider (LHC), ran successfully at 8.36 tesla for 24 hours. This magnetic field is 100 000 times that of the Earth and is required to keep beams of protons travelling on the correct circular path over 27 km at 7 TeV in the new LHC accelerator.

  16. Handling and Transport of Oversized Accelerator Components and Physics Detectors

    CERN Document Server

    Prodon, S; Guinchard, M; Minginette, P

    2006-01-01

    For cost, planning and organisational reasons, it is often decided to install large pre-built accelerators components and physics detectors. As a result surface exceptional transports are required from the construction to the installation sites. Such heavy transports have been numerous during the LHC installation phase. This paper will describe the different types of transport techniques used to fit the particularities of accelerators and detectors components (weight, height, acceleration, planarity) as well as the measurement techniques for monitoring and the logistical aspects (organisation with the police, obstacles on the roads, etc). As far as oversized equipment is concerned, the lowering into the pit is challenging, as well as the transport in tunnel galleries in a very scare space and without handling means attached to the structure like overhead travelling cranes. From the PS accelerator to the LHC, handling systems have been developed at CERN to fit with these particular working conditions. This pap...

  17. Robert Aymar seals the last interconnect in the LHC

    CERN Multimedia

    Maximilien Brice

    2007-01-01

    The LHC completes the circle. On 7 November, in a brief ceremony in the LHC tunnel, CERN Director General Robert Aymar (Photo 1) sealed the last interconnect between the main magnets of the Large Hadron Collider (LHC). Jean-Philippe Tock, leader of the Interconnections team, tightens the last bolt (Photos 4-8).

  18. Using permanent magnets to boost the dipole field for the High-Energy LHC

    CERN Document Server

    Zimmermann, Frank

    2012-01-01

    The High-Energy LHC (HE-LHC) will be a new accelerator in the LHC tunnel based on novel dipole magnets, with a field up to 20 T, which are proposed to be realized by a hybrid-coil design, comprising blocks made from Nb- Ti, Nb$_{3}$Sn and HTS, respectively. Without the HTS the field would be only 15 T. In this note we propose and study the possibility of replacing the inner HTS layer by (weaker) permanent magnets that might contribute a field of 1-2 T, so that the final field would reach 16-17 T. Advantages would be the lower price of permanent magnets compared with HTS magnets and their availability in principle.

  19. EXERGY ANALYSIS OF THE CRYOGENIC HELIUM DISTRIBUTION SYSTEM FOR THE LARGE HADRON COLLIDER (LHC)

    International Nuclear Information System (INIS)

    Claudet, S.; Lebrun, Ph.; Tavian, L.; Wagner, U.

    2010-01-01

    The Large Hadron Collider (LHC) at CERN features the world's largest helium cryogenic system, spreading over the 26.7 km circumference of the superconducting accelerator. With a total equivalent capacity of 145 kW at 4.5 K including 18 kW at 1.8 K, the LHC refrigerators produce an unprecedented exergetic load, which must be distributed efficiently to the magnets in the tunnel over the 3.3 km length of each of the eight independent sectors of the machine. We recall the main features of the LHC cryogenic helium distribution system at different temperature levels and present its exergy analysis, thus enabling to qualify second-principle efficiency and identify main remaining sources of irreversibility.

  20. Exergy Analysis of the Cryogenic Helium Distribution System for the Large Hadron Collider (LHC)

    CERN Document Server

    Claudet, S; Tavian, L; Wagner, U

    2010-01-01

    The Large Hadron Collider (LHC) at CERN features the world’s largest helium cryogenic system, spreading over the 26.7 km circumference of the superconducting accelerator. With a total equivalent capacity of 145 kW at 4.5 K including 18 kW at 1.8 K, the LHC refrigerators produce an unprecedented exergetic load, which must be distributed efficiently to the magnets in the tunnel over the 3.3 km length of each of the eight independent sectors of the machine. We recall the main features of the LHC cryogenic helium distribution system at different temperature levels and present its exergy analysis, thus enabling to qualify second-principle efficiency and identify main remaining sources of irreversibility..

  1. The LHC dipole test control architecture

    International Nuclear Information System (INIS)

    Gorskaya, E.; Samojlov, V.; Raimondo, A.; Rijllart, A.

    2003-01-01

    The next large accelerator project at CERN is the Large Hadron Collider, which is foreseen to be installed in the existing LEP tunnel, and scheduled to be commissioned in 2007. For this project, 1200 15-metre long dipole magnets need to be tested at CERN in warm and cold conditions on dedicated test benches that are under development. The final LHC dipole series test set-up will consist of 12 benches organized in 6 clusters of two benches sharing the largest and most expensive devices. This sharing is made possible by a deliberate de-phasing of the tests among magnets, ensuring an optimum use of resources, such as cryogenics and power equipment, without limiting the total throughput. An offered two-level control architecture includes: 1) the Test 'Master' that drives the test for a cluster; 2) the Resource 'Manager' that allocates common devices and central resources. The implementation of this architecture is done in the LabVIEW environment

  2. Mobilizing for the LHC

    CERN Multimedia

    2008-01-01

    A follow-up report on the incident that occurred in LHC Sector 3-4 was published on 5 December. It confirms that the accelerator will be restarted in the summer of 2009. From now until then, the teams will be pulling out all the stops to repair the sector and enhance the operational safety of the machine.

  3. LHC INAUGURATION, LHC Fest highlights: exhibition time!

    CERN Multimedia

    2008-01-01

    David Gross, one of the twenty-one Nobel Laureates who have participated in the project.Tuesday 21 October 2008 Accelerating Nobels Colliding Charm, Atomic Cuisine, The Good Anomaly, A Quark Somewhere on the White Paper, Wire Proliferation, A Tale of Two Liquids … these are just some of the titles given to artworks by Physics Nobel Laureates who agreed to make drawings of their prize-winning discoveries (more or less reluctantly) during a special photo session. Science photographer Volker Steger made portraits of Physics Nobel Laureates and before the photo sessions he asked them to make a drawing of their most important discovery. The result is "Accelerating Nobels", an exhibition that combines unusual portraits of and original drawings by twenty-one Nobel laureates in physics whose work is closely related to CERN and the LHC. This exhibition will be one of the highlights of the LHC celebrations on 21 October in the SM18 hall b...

  4. LHC - latest in a long line of rings

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    The LHC - Large Hadron Collider - ring in CERN's 27-kilometre LEP tunnel is the natural next link in an accelerator chain first forged in the mid-1950s with the decision to build Europe's first state-of-the-art high energy synchrotron at CERN. A lot of ground has been covered since the LHC idea was launched over a decade ago. While the basic machine design has moved through several iterations, preparations for the experimental programme are well underway. CERN is now responding to the December 1991 request from its governing body, Council, to supply detailed information on the technical feasibility of the machine, its costs, and its experimental programme. In the late 1970s, when plans for CERN's LEP electron-positron collider were being pieced together, far-sighted people were already looking further ahead. With the LEP tunnel itself a major investment for the future, the circumference of the ring and the tunnel cross-section were kept as large as possible, so that another ring could be fitted in when the time came. On the physics front, the ultimate quest was the mysterious higgs mechanism which controls electroweak symmetry breaking. The symmetry of the vacuum is broken by the higgs field. Somewhere along the line, this fundamental field has to show itself as one or more higgs particles

  5. LHC - latest in a long line of rings

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    1993-12-15

    The LHC - Large Hadron Collider - ring in CERN's 27-kilometre LEP tunnel is the natural next link in an accelerator chain first forged in the mid-1950s with the decision to build Europe's first state-of-the-art high energy synchrotron at CERN. A lot of ground has been covered since the LHC idea was launched over a decade ago. While the basic machine design has moved through several iterations, preparations for the experimental programme are well underway. CERN is now responding to the December 1991 request from its governing body, Council, to supply detailed information on the technical feasibility of the machine, its costs, and its experimental programme. In the late 1970s, when plans for CERN's LEP electron-positron collider were being pieced together, far-sighted people were already looking further ahead. With the LEP tunnel itself a major investment for the future, the circumference of the ring and the tunnel cross-section were kept as large as possible, so that another ring could be fitted in when the time came. On the physics front, the ultimate quest was the mysterious higgs mechanism which controls electroweak symmetry breaking. The symmetry of the vacuum is broken by the higgs field. Somewhere along the line, this fundamental field has to show itself as one or more higgs particles.

  6. Installation of the LHC transfer lines begins

    CERN Multimedia

    2003-01-01

    On 19 February, the very first magnet was installed in one of the two tunnels that will house the transfer lines leading to the LHC. This magnet, recycled from a previous facility, was transported and positioned using a novel system designed for conveying large objects through narrow tunnels.

  7. LHC magnets: the great descent

    CERN Multimedia

    2005-01-01

    A first dipole magnet was delivered to its final location in the LHC tunnel on Monday, 7 March. This achievement coincides with another important milestone in the installation of the future collider, the completion of the delivery of half the dipole magnets.

  8. LHC Injection Beam Quality During LHC Run I

    CERN Document Server

    AUTHOR|(CDS)2079186; Kain, Verena; Stapnes, Steinar

    The LHC at CERN was designed to accelerate proton beams from 450 GeV to 7 TeV and collide them in four large experiments. The 450 GeV beam is extracted from the last pre-accelerator, the SPS, and injected into the LHC via two 3 km long transfer lines, TI 2 and TI 8. The injection process is critical in terms of preservation of beam quality and machine protection. During LHC Run I (2009-2013) the LHC was filled with twelve high intensity injections per ring, in batches of up to 144 bunches of 1.7*10^11 protons per bunch. The stored beam energy of such a batch is already an order of magnitude above the damage level of accelerator equipment. Strict quality and machine protection requirements at injection have a significant impact on operational efficiency. During the first years of LHC operation, the injection phase was identified as one of the limiting factors for fast LHC turnaround time. The LHC Injection Quality Check (IQC) software framework was developed as a part of this thesis to monitor the beam quality...

  9. Important step towards the LHC

    CERN Document Server

    2001-01-01

    The TI2 tunnel, one of the two tunnels that will transfer protons from the SPS to the LHC, broke through into the LEP/LHC ring on 15 May. TI2 will carry clockwise-moving protons from under the Laboratory's West Area to Point 2, future home of the ALICE experiment. It is coming up to 16:00 on 15 May and a group of some 50 people, fully kitted out in boots, helmets, and masks is intently watching a point on the wall in front of them. They are down in the LEP/LHC tunnel waiting for civil engineers to excavate the last few centimetres separating them from the TI2 transfer tunnel. The noise of machines begins, and just five minutes later the wall comes tumbling down. The excavator breaks through right on target, bringing a two-year project to a happy conclusion. Later, the survey team published the outstanding result that the tunnel junction was made within 6 millimetres of target. TI2 measures 2648 metres in length and three metres in diameter. Around 32,000 cubic metres of rock have been excavated to make it, so...

  10. LHC: forwards and onwards

    CERN Multimedia

    2008-01-01

    Following the recent incident in Sector 3-4, which has brought the start-up of the LHC to a halt, the various teams are working hard to establish the cause, evaluate the situation and plan the necessary repairs. The LHC will be started up again in spring 2009 following the winter shutdown for the maintenance of all the CERN installations. The LHC teams are at work on warming up Sector 3-4 and establishing the cause of the serious incident that occurred on Friday, 19 September. Preliminary investigations suggest that the likely cause of the problem was a faulty electrical connection between two magnets. The connections probably melted, leading to a mechanical failure and a large leak of helium into the tunnel. However, the teams will not be able to carry out a full evaluation and assess the repairs needed until the sector has been warmed up again and inspected. "We are not worried about repairing the magnets as spare parts are available", said Lyn Evans, the LHC Project Leade...

  11. The LHC in numbers

    CERN Multimedia

    Alizée Dauvergne

    2010-01-01

    What makes the LHC the biggest particle accelerator in the world? Here are some of the numbers that characterise the LHC, and their equivalents in terms that are easier for us to imagine.   Feature Number Equivalent Circumference ~ 27 km   Distance covered by beam in 10 hours ~ 10 billion km a round trip to Neptune Number of times a single proton travels around the ring each second 11 245   Speed of protons first entering the LHC 299 732 500 m/s 99.9998 % of the speed of light Speed of protons when they collide 299 789 760 m/s 99.9999991 % of the speed of light Collision temperature ~ 1016 °C ove...

  12. Winter therapy for the accelerators

    CERN Multimedia

    Corinne Pralavorio

    2016-01-01

    Hundreds of people are hard at work during the year-end technical stop as all the accelerators are undergoing maintenance, renovation and upgrade operations in parallel.   The new beam absorber on its way to Point 2 before being lowered into the LHC tunnel for installation. The accelerator teams didn’t waste any time before starting their annual winter rejuvenation programme over the winter. At the end of November, as the LHC ion run was beginning, work got under way on the PS Booster, where operation had already stopped. On 14 December, once the whole complex had been shut down, the technical teams turned their attention to the other injectors and the LHC. The year-end technical stop (YETS) provides an opportunity to carry out maintenance work on equipment and repair any damage as well as to upgrade the machines for the upcoming runs. Numerous work projects are carried out simultaneously, so good coordination is crucial. Marzia Bernardini's team in the Enginee...

  13. LHC report

    CERN Multimedia

    CERN. Geneva

    2010-01-01

    This week's Report, by Gianluigi Arduini,  will be included in the LHC Physics Day, dedicated to the reviews of the LHC physics results presented at ICHEP 2010. Seehttp://indico.cern.ch/conferenceDisplay.py?confId=102669 

  14. LHC status report

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    Following the great success of the first 3.5 TeV collisions in all four LHC experiments on 30 March, the focus of the LHC commissioning teams has turned to consolidating the beam injection and acceleration procedures.   During the last two weeks, the operators have adopted a cycle of beam commissioning studies by day and the preparation and delivery of collisions during the night shifts. The injection and acceleration processes for the beams are by now well established and almost all feedback systems, which are an essential ingredient for establishing reliable and safe machine operation, have been commissioned. Thanks to special current settings for the quadrupoles that are situated near the collision points, the LHC luminosity at high energy has been increased by a factor of 5 in three of the four experiments. Similar improvements are under way for the fourth experiment. The next steps include adjustments of the LHC machine protection and collimation devices, which will ensure 'stable beam' co...

  15. Installation and Quality Assurance of the Interconnections between Cryo-assemblies of the LHC Long Straight Sections

    CERN Document Server

    Garion, C; Tock, J P

    2006-01-01

    The interconnections between the cryomagnets and cryogenic utilities in the LHC long Straight Sections constitute the last machine installation activity. They are ensuring continuity of the beam and insulation vacuum systems, cryogenic fluid and electrical circuits and thermal insulation. The assembly is carried out in a constraining tunnel environment with restricted space. Therefore, the assembly sequence has to be well defined and specific tests have to be performed during the interconnection work to secure the reliability of the system and thus to ensure the global accelerator availability. The LHC has 8 long straight insertion zones composed of special cryomagnets involving specific interconnection procedures and QA plans. The aim of this paper is to present the installation and quality assurance procedures implemented for the LHC LSS interconnections. Technologies such as manual and automatic welding and resistive soldering will be described as well as the different quality controls, such as visual and ...

  16. 16 March 2009 - HRH Princess Maha Chakri Sirindhorn, Kingdom of Thailand, visiting CMS experimental area and LHC tunnel with Coordinator for external relations F. Pauss and Collaboration Spokesperson T. Virdee.

    CERN Multimedia

    Maximilien Brice

    2009-01-01

    Photo 1: Relations with Non-Member State E. Tsesmelis, CMS Collaboration Spokesperson T. Virdee, HRH Princess Maha Chakri Sirindhorn and Coordinator for External relations F. Pauss, in CMS experimental area. Photo 2-12: Arrival of HRH at building 160: Posy presented to HRH by E. and F. Breedon; Welcome line: Director-General R. Heuer who introduces S. Bertolucci, F. Pauss, E. Tsesmelis, A. de Roeck, R. Breedon and Protocol Officer W. Korda. Photo 13-26:Presentation by Director-General R. Heuer and Head of Education R. Landua. Photo 27-30: Welcome at CMS by Spokesperson T. Virdee Photo 31-43: LHC tunnel visit Photo 44 - 60: CMS underground area visit Photo 61-63: HRH signs the guest book in the SCX5 conference room Photo 64-69: Signature of an expression of interest between SLRI and CMS Photo 75-88: Final discussion with Coordinator for External relation F. Pauss and Director-General R. Heuer.

  17. LHC beam stability and feedback control

    Energy Technology Data Exchange (ETDEWEB)

    Steinhagen, Ralph

    2007-07-20

    This report presents the stability and the control of the Large Hadron Collider's (LHC) two beam orbits and their particle momenta using beam-based feedback systems. The aim of this report is to contribute to a safe and reliable LHC commissioning and machine operation. The first part of the analysis gives an estimate of the expected sources of orbit and energy perturbations that can be grouped into environmental sources, machine-inherent sources and machine element failures: the slowest perturbation due to ground motion, tides, temperature fluctuations of the tunnel and other environmental influences are described in this report by a propagation model that is both qualitatively and quantitatively supported by geophone and beam motion measurements at LEP and other CERN accelerators. The second part of this analysis deals with the control of the two LHC beams' orbit and energy through automated feedback systems. Based on the reading of the more than 1056 beam position monitors (BPMs) that are distributed over the machine, a central global feedback controller calculates new deflection strengths for the more than 1060 orbit corrector magnets (CODs) that are suitable to correct the orbit and momentum around their references. this report provides an analysis of the BPMs and CODs involved in the orbit and energy feedback. The BPMs are based on a wide-band time normaliser circuit that converts the transverse beam position reading of each individual particle bunch into two laser pulses that are separated by a time delay and transmitted through optical fibres to an acquisition card that converts the delay signals into a digital position. A simple error model has been tested and compared to the measurement accuracy of LHC type BPMs, obtained through beam-based measurements in the SPS. The average beam position is controlled through 1060 superconducting and individually powered corrector dipole magnets. The proposed correction in 'time-domain' consists of a

  18. LHC beam stability and feedback control

    International Nuclear Information System (INIS)

    Steinhagen, Ralph

    2007-01-01

    This report presents the stability and the control of the Large Hadron Collider's (LHC) two beam orbits and their particle momenta using beam-based feedback systems. The aim of this report is to contribute to a safe and reliable LHC commissioning and machine operation. The first part of the analysis gives an estimate of the expected sources of orbit and energy perturbations that can be grouped into environmental sources, machine-inherent sources and machine element failures: the slowest perturbation due to ground motion, tides, temperature fluctuations of the tunnel and other environmental influences are described in this report by a propagation model that is both qualitatively and quantitatively supported by geophone and beam motion measurements at LEP and other CERN accelerators. The second part of this analysis deals with the control of the two LHC beams' orbit and energy through automated feedback systems. Based on the reading of the more than 1056 beam position monitors (BPMs) that are distributed over the machine, a central global feedback controller calculates new deflection strengths for the more than 1060 orbit corrector magnets (CODs) that are suitable to correct the orbit and momentum around their references. this report provides an analysis of the BPMs and CODs involved in the orbit and energy feedback. The BPMs are based on a wide-band time normaliser circuit that converts the transverse beam position reading of each individual particle bunch into two laser pulses that are separated by a time delay and transmitted through optical fibres to an acquisition card that converts the delay signals into a digital position. A simple error model has been tested and compared to the measurement accuracy of LHC type BPMs, obtained through beam-based measurements in the SPS. The average beam position is controlled through 1060 superconducting and individually powered corrector dipole magnets. The proposed correction in 'time-domain' consists of a proportional

  19. The LHC

    CERN Multimedia

    2002-01-01

    The LHC will use the latest technologies on an enormous scale. 8000 superconducting magnets will keep the beams on track. The entire 27 km ring will be cooled by 700 000 litres of liquid helium to a temperature of -271 degrees Celsius , making the LHC the world's largest superconducting installation. Conventional superconducting wire will form the magnet coils, while high-temperature superconductors will carry a total of 2 300 000 amperes from the power supplies into the magnet cryostat

  20. LHC an unprecedented technological challenge

    International Nuclear Information System (INIS)

    Baruch, J.O.

    2002-01-01

    This article presents the future LHC (large hadron collider) in simple terms and gives some details concerning radiation detectors and supra-conducting magnets. LHC will take the place of the LEP inside the 27 km long underground tunnel near Geneva and is scheduled to operate in 2007. 8 years after its official launching the LHC project has piled up 2 year delay and has exceeded its initial budget (2 milliard euros) by 18%. Technological challenges and design difficulties are the main causes of these shifts. The first challenge has been carried out successfully, it was the complete clearing out of the LEP installation. In order to release 14 TeV in each proton-proton collision, powerful magnetic fields (8,33 Tesla) are necessary. 1248 supra-conducting 15 m-long bipolar magnets have to be built. 30% of the worldwide production of niobium-titanium wires will be used each year for 5 years in the design of these coils. The global cryogenic system will be gigantic and will use 94 tons of helium. 4 radiation detectors are being built: ATLAS (a toroidal LHC apparatus), CMS (compact muon solenoid), ALICE (a large ion collider experiment) and LHC-b (large hadron collider beauty). The 2 first will search after the Higgs boson, ALICE will be dedicated to the study of the quark-gluon plasma and LHC-b will gather data on the imbalance between matter and anti-matter. (A.C.)

  1. The High Luminosity LHC Project

    Science.gov (United States)

    Rossi, Lucio

    The High Luminosity LHC is one of the major scientific project of the next decade. It aims at increasing the luminosity reach of LHC by a factor five for peak luminosity and a factor ten in integrated luminosity. The project, now fully approved and funded, will be finished in ten years and will prolong the life of LHC until 2035-2040. It implies deep modifications of the LHC for about 1.2 km around the high luminosity insertions of ATLAS and CMS and relies on new cutting edge technologies. We are developing new advanced superconducting magnets capable of reaching 12 T field; superconducting RF crab cavities capable to rotate the beams with great accuracy; 100 kA and hundred meter long superconducting links for removing the power converter out of the tunnel; new collimator concepts, etc... Beside the important physics goals, the High Luminosity LHC project is an ideal test bed for new technologies for the next hadron collider for the post-LHC era.

  2. CERN: LHC progress

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    The push for CERN's next major project, the LHC proton collider to be built in the 27-kilometre LEP tunnel, is advancing on a wide front. For the machine itself, there has been considerable progress in the detailed design. While the main thrust is for proton-proton collisions, heavy ions are also on the LHC collision menu. On the experimental side, proposals are coming into sharper focus. For the machine, the main aim is for the highest possible proton collision energies and collision rates in the confines of the existing LEP tunnel, and the original base design looked to achieve these goals in three collision regions. Early discussions on the experimental programme quickly established that the most probable configuration would have two collision regions rather than three. This, combined with hints that the electronics of several detectors would have to handle several bunch crossings at a time, raised the question whether the originally specified bunch spacing of 15 ns was still optimal

  3. LEP sees the end of the tunnel

    CERN Multimedia

    2002-01-01

    After 14 months, which have seen the removal of 30,000 tonnes of material from the tunnel, the LEP dismantling operation has now been completed. LHC installation, which will be subject to new safety rules, can go ahead.

  4. Steel septum magnets for the LHC beam injection and extraction

    CERN Document Server

    Bidon, S; Guinand, M; Gyr, Marcel; Sassowsky, M; Weisse, E; Weterings, W; Abramov, A; Ivanenko, A I; Kolatcheva, E; Lapyguina, O; Ludmirsky, E; Mishina, N; Podlesny, P; Riabov, A; Tyurin, N

    2002-01-01

    The Large Hadron Collider (LHC) will be a superconducting accelerator and collider to be installed in the existing underground LEP ring tunnel at CERN. It will provide proton-proton collisions with a centre of mass energy of 14 TeV. The proton beams coming from the SPS will be injected into the LHC at 450 GeV by vertically deflecting kicker magnets and horizontally deflecting steel septum magnets (MSI). The proton beams will be dumped from the LHC with the help of two extraction systems comprising horizontally deflecting kicker magnets and vertically deflecting steel septum magnets (MSD). The MSI and MSD septa are laminated iron-dominated magnets using an all welded construction. The yokes are constructed from two different half cores, called coil core and septum core. The septum cores comprise circular holes for the circulating beams. This avoids the need for careful alignment of the usually wedge-shaped septum blades used in classical Lambertson magnets. The MSI and MSD septum magnets were designed and buil...

  5. LHC computing (WLCG) past, present, and future

    CERN Document Server

    Bird, I G

    2016-01-01

    The LCG project, and the WLCG Collaboration, represent a more than 10-year investment in building and operating the LHC computing environment. This article gives some of the history of how the WLCG was constructed and the preparations for the accelerator start-up. It will discuss the experiences and lessons learned during the first 3 year run of the LHC, and will conclude with a look forwards to the planned upgrades of the LHC and the experiments, discussing the implications for computing.

  6. 20 September 2013 - Ambassador Z. Akram , Permanent Representative of the Islamic Republic of Pakistan to the United Nations Office and other international organisations in Geneva (3rd) with Mechanical and Materials Engineering Group Leader F. Bertinelli, Head of International Relations R. Voss, CMS Collaboration, Quaid-i-Azam University H. Hoorani, Permanent Mission First Secretary U. Iqbal Jadoon and LHC Consolidation, Industrial Services, Technology Department JP. Tock in front of the lift to the LHC tunnel at Point 1. Site Manager M. Décombaz on the back.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    20 September 2013 - Ambassador Z. Akram , Permanent Representative of the Islamic Republic of Pakistan to the United Nations Office and other international organisations in Geneva (3rd) with Mechanical and Materials Engineering Group Leader F. Bertinelli, Head of International Relations R. Voss, CMS Collaboration, Quaid-i-Azam University H. Hoorani, Permanent Mission First Secretary U. Iqbal Jadoon and LHC Consolidation, Industrial Services, Technology Department JP. Tock in front of the lift to the LHC tunnel at Point 1. Site Manager M. Décombaz on the back.

  7. LHC Report: Ion Age

    CERN Multimedia

    John Jowett for the LHC team

    2013-01-01

    The LHC starts the New Year facing a new challenge: proton-lead collisions in the last month before the shutdown in mid-February.    Commissioning this new and almost unprecedented mode of collider operation is a major challenge both for the LHC and its injector chain. Moreover, it has to be done very quickly to achieve a whole series of physics goals, requiring modifications of the LHC configuration, in a very short time. These include a switch of the beam directions halfway through the run, polarity reversals of the ALICE spectrometer magnet and Van der Meer scans.    The Linac3 team kept the lead source running throughout the end-of-year technical stop, and recovery of the accelerator complex was very quick. New proton and lead beams were soon ready, with a bunch filling pattern that ensures they will eventually match up in the LHC. The LEIR machine has even attained a new ion beam intensity record.  On Friday 11 January the first single bunches o...

  8. The LHC road at CERN

    International Nuclear Information System (INIS)

    Anon.

    1989-01-01

    To explore the 1 TeV energy scale where fundamental particle interactions should encounter new conditions, two major routes were proposed - a high magnetic field proton collider in the LEP tunnel, dubbed LHC for Large Hadron Collider, and the CERN Linear Collider (CLIC) to supply beams of electrons and positrons. Exploratory studies have shown that while CLIC remains a valid long-term goal, LHC appears as the most cost-effective way for CERN to enter the 1 TeV arena. High-field superconducting magnet prototype work demonstrates that a 'two-in-one' design supplying the 10 tesla fields needed to handle LHC's 8 TeV proton beams (collision energy 16 TeV) is a practical proposition. (orig./HSI).

  9. The LHC magnets' trip underground

    CERN Multimedia

    2002-01-01

    Buildings SMI 2 and SDI 2 are currently a big blue construction at the end of the Meyrin site. When they are finished, in 2003, they will be the departure point from where the magnets for the LHC will be lowered down into the tunnel. View of the new building at the end of the Meyrin site. If you live in neighbouring France, you have probably noticed a new blue steel construction that has changed the view from Saint Genis Pouilly since last March. It's the first of two contiguous buildings, SMI 2 and SDI 2, which will make it possible to prepare and lower the 1232 dipole magnets, the 400 short straight sections and some 60 insertion magnets down into the TI2 tunnel, and from there, to their final location in the LHC tunnel. According to Paul Faugeras, Technical Co-ordinator for the LHC machine, 'the installation of the magnets will start in early 2004, and hopefully everything will be done by October 2006'. The first part of the magnets' journey will take place on surface. The 15 metre-long dipole magnets a...

  10. An intelligent and networking solution of radiation monitoring system for LHC

    International Nuclear Information System (INIS)

    Shao Beibei; Gong Guanghua

    2001-01-01

    The LHC (the Large Hadron Collider), the largest accelerator in the world, is under designing and construction at CERN. It shares the 27 km LEP tunnel and is expected to be on the air in 2005. The Radiation Monitoring System of LEP was a central system with non-intelligent detectors. While as the proposed new RMS for LHC is a distributing intelligent networked system. Around 350 detectors will be employed. To save the cost, the design should make the old LEP's non-intelligent detectors reusable. To allow the detector controller automatic reports the detector database and net location through the world Fip bus, 1 wire components are embedded into the detectors and the network sockets. The radiation tolerance and the reliability of the communication of the wire components have been tested in a strong radiation field at CERN. The low cost components based position detection technique is valuable for most networked control system

  11. Risk analysis of the LHC underground area fire risk due to faulty electrical equipment

    CERN Document Server

    Harrison, A

    2007-01-01

    The European Organisation for Nuclear Research (CERN) in Geneva, Switzerland, is currently building the latest generation of particle accelerators, the LHC (Large Hadron Collider). The machine is housed in a circular tunnel of 27 km of circumference and is situated approximately 100 metres beneath the surface astride the Franco-Swiss border. Electrically induced fires in the LHC are a major concern, since an incident could present a threat to CERN personnel as well as the public. Moreover, the loss of equipment would result in significant costs and downtime. However, the amount of electrical equipment in the underground area required for operation, supervision and control of the machine is essential. Thus the present thesis is assessing the risk of fire due to faulty electrical equipment in both a qualitative as well as quantitative way. The recommendations following the qualitative analysis suggest the introduction of fire protection zones for the areas with the highest risk of fire due to a combination of p...

  12. The LHC detectors and the first CMS data

    CERN Document Server

    Green, Dan

    2015-01-01

    This chapter describes the subsystems of a generic LHC detector and explains how the values of the detector parameters were selected. The design of the LHC detectors follows from the requirement of confronting electroweak symmetry breaking in a decisive fashion. The LHC accelerator also meets those requirements.

  13. Successful test of SPS-to-LHC beamline

    CERN Multimedia

    Maximilien Brice

    2004-01-01

    On 23 October there was great excitement in the Prevessin control room when, on the first attempt, a beam passed over 2.5 km down the new SPS-to-LHC transfer line, TI8, to within a few metres of the LHC tunnel.

  14. Successful test of SPS-to-LHC beamline

    CERN Multimedia

    Maximilien Brice

    2004-01-01

    On 23 October there was great excitement in the Prevessin control room when, on the first attempt, a beam passed over 2.5 km down the new SPS-to-LHC transfer line, TI8, to within a few metres of the LHC tunnel. Members of the AB, AT and TS departments involved in the beamline and its test, celebrate their success with the Director General, Robert Aymar, and the LHC Project Leader, Lyn Evans.

  15. Successful test of SPS-to-LHC beamline

    CERN Multimedia

    2004-01-01

    On 23 October there was great excitement in the Prevessin control room when, on the first attempt, a beam passed over 2.5 km down the new SPS-to-LHC transfer line, TI8, to within a few metres of the LHC tunnel. Above: members of the AB, AT and TS departments involved in the beamline and its test, celebrate their success with the Director General, Robert Aymar, and the LHC Project Leader, Lyn Evans.

  16. LHC Report: machine development

    CERN Multimedia

    Rogelio Tomás García for the LHC team

    2015-01-01

    Machine development weeks are carefully planned in the LHC operation schedule to optimise and further study the performance of the machine. The first machine development session of Run 2 ended on Saturday, 25 July. Despite various hiccoughs, it allowed the operators to make great strides towards improving the long-term performance of the LHC.   The main goals of this first machine development (MD) week were to determine the minimum beam-spot size at the interaction points given existing optics and collimation constraints; to test new beam instrumentation; to evaluate the effectiveness of performing part of the beam-squeezing process during the energy ramp; and to explore the limits on the number of protons per bunch arising from the electromagnetic interactions with the accelerator environment and the other beam. Unfortunately, a series of events reduced the machine availability for studies to about 50%. The most critical issue was the recurrent trip of a sextupolar corrector circuit –...

  17. The LHC superconducting cavities

    CERN Document Server

    Boussard, Daniel; Häbel, E; Kindermann, H P; Losito, R; Marque, S; Rödel, V; Stirbet, M

    1999-01-01

    The LHC RF system, which must handle high intensity (0.5 A d.c.) beams, makes use of superconducting single-cell cavities, best suited to minimizing the effects of periodic transient beam loading. There will be eight cavities per beam, each capable of delivering 2 MV (5 MV/m accelerating field) at 400 MHz. The cavities themselves are now being manufactured by industry, using niobium-on-copper technology which gives full satisfaction at LEP. A cavity unit includes a helium tank (4.5 K operating temperature) built around a cavity cell, RF and HOM couplers and a mechanical tuner, all housed in a modular cryostat. Four-unit modules are ultimately foreseen for the LHC (two per beam), while at present a prototype version with two complete units is being extensively tested. In addition to a detailed description of the cavity and its ancillary equipment, the first test results of the prototype will be reported.

  18. Cryogenics for LHC experiments

    CERN Multimedia

    2001-01-01

    Cryogenic systems will be used by LHC experiments to maximize their performance. Institutes around the world are collaborating with CERN in the construction of these very low temperature systems. The cryogenic test facility in hall 180 for ATLAS magnets. High Energy Physics experiments have frequently adopted cryogenic versions of their apparatus to achieve optimal performance, and those for the LHC will be no exception. The two largest experiments for CERN's new flagship accelerator, ATLAS and CMS, will both use large superconducting magnets operated at 4.5 Kelvin - almost 270 degrees below the freezing point of water. ATLAS also includes calorimeters filled with liquid argon at 87 Kelvin. For the magnets, the choice of a cryogenic version was dictated by a combination economy and transparency to emerging particles. For the calorimeters, liquid argon was selected as the fluid best suited to the experiment's physics requirements. High Energy Physics experiments are the result of worldwide collaborations and...

  19. End of the road for the LHC magnets...well, above ground that is!

    CERN Multimedia

    2003-01-01

    The first LHC dipole cryomagnet has been delivered to the SMI2 building for final assembly prior to lowering it into the LHC tunnel. Over the next 3 years, all LHC cryomagnets will pass through these doors before starting their journey underground.

  20. The LHC access system LACS and LASS

    CERN Document Server

    Ninin, P

    2005-01-01

    The LHC complex is divided into a number of zones with different levels of access controls.Inside the interlocked areas, the personnel protection is ensured by the LHC Access System.The system is made of two parts:the LHC Access Safety System and the LHC Access Control System. During machine operation,the LHC Access Safety System ensures the collective protection of the personnel against the radiation hazards arising from the operation of the accelerator by interlocking the LHC key safety elements. When the beams are off, the LHC Access Control System regulates the access to the accelerator and its many subsystems.It allows a remote, local or automatic operation of the access control equipment which verifies and identifies all users entering the controlled areas.The global architecture of the LHC Access System is now designed and is being validated to ensure that it meets the safety requirements for operation of the LHC.A pilot installation will be tested in the summer 2005 to validate the concept with the us...

  1. The LHC magnet system and its status of development

    Science.gov (United States)

    Bona, Maurizio; Perin, Romeo; Vlogaert, Jos

    1995-01-01

    CERN is preparing for the construction of a new high energy accelerator/collider, the Large Hadron Collider (LHC). This new facility will mainly consist of two superconducting magnetic beam channels, 27 km long, to be installed in the existing LEP tunnel. The magnetic system comprises about 1200 twin-aperture dipoles, 13.145 m long, with an operational field of 8.65 T, about 600 quadrupoles, 3 m long, and a very large number of other superconducting magnetic components. A general description of the system is given together with the main features of the design of the regular lattice magnets. The paper also describes the present state of the magnet R & D program. Results from short model work, as well as from full scale prototypes will be presented, including the recently tested 10 m long full-scale prototype dipole manufactured in industry.

  2. The beam dump tunnels

    CERN Multimedia

    Patrice Loïez

    2002-01-01

    In these images workers are digging the tunnels that will be used to dump the counter-circulating beams. Travelling just a fraction under the speed of light, the beams at the LHC will each carry the energy of an aircraft carrier travelling at 12 knots. In order to dispose of these beams safely, a beam dump is used to extract the beam and diffuse it before it collides with a radiation shielded graphite target.

  3. LHC Create

    CERN Multimedia

    CERN. Geneva

    2017-01-01

    LHC Create is an upcoming 2-day workshop held at IdeaSquare in November. Participants from CERN and IPAC school of design will compete to design an exhibit that explains why CERN does what it does. The winner will have their exhibit fully realised and made available to experiments, institutes, and tourism agencies around the world.

  4. Open Access to the LHC takes on a new meaning

    CERN Multimedia

    2008-01-01

    Complete scientific documentation on the LHC machine and detectors is now freely available on the Web. The ATLAS collaboration, shown here, contributed to the 1,600-page scientific documentation of the LHC, along with staff from the other five detectors and the LHC machine.Now that the LHC tunnel and the experimental caverns are shut down for public visits, "Open Access to the LHC" has taken on an entirely new meaning. Last Thursday, 14 August, seven major articles were published electronically in a special issue of the Journal of Instrumentation (JINST). Together they form the complete scientific documentation on the design and construction of the LHC machine and the six detectors (ALICE, ATLAS, CMS, LHCb, LHCf and TOTEM), and thus on the entire LHC project, well before start-up on 10 September. For many years to come, these papers will serve as key references for the stream of scientific results that will begin to emerge from the ...

  5. LHC Olympics flex physicists' brains

    CERN Multimedia

    2006-01-01

    Physicists from around the world met at CERN to strengthen their data-deciphering skills at the second LHC Olympics workshop. Physicists gather for the second LHC Olympics workshop. Coinciding with the kick-off of the winter Olympics in Turin, more than 70 physicists gathered at CERN from across the globe for the second LHC Olympics workshop on 9-10 February. Their challenge, however, involved brains rather than brawn. As the switch-on date for the LHC draws near, scientists excited by the project want to test and improve their ability to decipher the unprecedented amount of data that the world's biggest and most powerful particle accelerator is expected to generate. The LHC Olympics is a coordinated effort to do just that, minus the gold, silver and bronze of the athletics competition. 'In some ways, the LHC is not a precision instrument. It gives you the information that something is there but it's hard to untangle and interpret what it is,' said University of Michigan physicist Gordy Kane, who organiz...

  6. Last cast for the LHC

    CERN Multimedia

    2005-01-01

    The first major contract signed for the LHC is drawing to a close. Belgian firm Cockerill Sambre (a member of the Arcelor Group) has just completed production of 50,000 tonnes of steel sheets for the accelerator's superconducting magnet yokes, in what has proved to be an exemplary partnership with CERN. Philippe Lebrun, Head of the AT Department, Lyn Evans, LHC Project Leader, and Lucio Rossi, Head of the AT-MAS Group, in front of the last batch of steel for the LHC at Cockerill Sambre. It was a bright red-letter day at the end of May, when Belgian firm Cockerill Sambre of the Arcelor Group marked the completion of one of the largest contracts for the LHC machine by casting the last batch of steel sheets for the LHC superconducting magnet yokes in the presence of LHC Project Leader Lyn Evans, AT Department Head Philippe Lebrun, Magnets and Superconductors (AT-MAS) Group Leader Lucio Rossi and Head of the AT-MAS Group's components centre Francesco Bertinelli. The yokes constitute approximately 80% of the acc...

  7. High-field Magnet Development toward the High Luminosity LHC

    Energy Technology Data Exchange (ETDEWEB)

    Apollinari, Giorgio [Fermilab

    2014-07-01

    The upcoming Luminosity upgrade of the LHC (HL-LHC) will rely on the use of Accelerator Quality Nb3Sn Magnets which have been the focus of an intense R&D effort in the last decade. This contribution will describe the R&D and results of Nb3Sn Accelerator Quality High Field Magnets development efforts, with emphasis on the activities considered for the HL-LHC upgrades.

  8. How elementary paticles are discovered. From the cyclotron to the LHC - an expedition through the world of the particle accelerators; Wie man Elementarteilchen entdeckt. Vom Zyklotron zum LHC - ein Streifzug durch die Welt der Teilchenbeschleuniger

    Energy Technology Data Exchange (ETDEWEB)

    Freytag, Carl; Osterhage, Wolfgang W.

    2016-07-01

    This book explains the physical foundations and the technology of the elementary-particle research and describes the particle accelerators, the detector, and their concerted acting. On some milestones of the research - from the production of transuranium elements via the discovery of exotic mesons until the Higgs particle - the way from theory via the experiment to the research result is shown.

  9. LHC Power Distribution

    CERN Document Server

    Pedersen, J

    1999-01-01

    The power distribution for the LHC machine and its experiments will be realised making extensive use of the existing infrastructure for the LEP. The overall power requirement is approximately the same, about 125 MW. The load distribution will however change. The even points will loose in importance and the points 1 and 5 will, due to the installation of ATLAS and CMS, gain. A thorough reorganisation of the 18 kV distribution will thus be necessary. Due to the important cryogenic installations required for the LHC, the 3.3 kV distribution system, supplying mainly cryogenic compressors, will be extended with a number of new substations. The important number of new surface buildings, underground caverns and other underground structures all will receive general service installations: Lighting and power. The new injection tunnels will require complete installations: A.C. supplies for the power converters and for general service, and D.C. cabling for the magnets of the beam line. Special safe power installations ar...

  10. 2 March 2012 - US Google Management Team Executive Chairman E. Schmidt visiting the LHC superconducting magnet test hall with Director for Accelerators and Technology S. Myers and Head of Technology Department F. Bordry; signing the guest book with CERN Director-General R. Heuer.

    CERN Multimedia

    Maximilien Brice

    2012-01-01

    2 March 2012 - US Google Management Team Executive Chairman E. Schmidt visiting the LHC superconducting magnet test hall with Director for Accelerators and Technology S. Myers and Head of Technology Department F. Bordry; signing the guest book with CERN Director-General R. Heuer.

  11. Low energy accelerators for research and applications

    International Nuclear Information System (INIS)

    Bhandari, R.K.

    2013-01-01

    Charged particle accelerators are instruments for producing a variety of radiations under controlled conditions for basic and applied research as well as applications. They have helped enormously to study the matter, atoms, nuclei, sub-nuclear particles and their constituents, forces involved in the related phenomena etc. No other man-made instrument has been so effective in such studies as the accelerator. The large accelerator constructed so far is the Large Hadron Collider (LHC) housed in a tunnel of 27 km circumference, while a small accelerator can fit inside a room. Small accelerators accelerate charged particles such as electrons, protons, deuterons, alphas and, in general ions to low energy, generally, below several MeV. These particle beams are used for studies in nuclear astrophysics, atomic physics, material science, surface physics, bio sciences etc. They are used for ion beam analysis such as RBS, PIXE, NRA, AMS, CPAA etc. More importantly, the ion beams have important industrial applications like ion implantation, surface modification, isotope production etc. while electron beams are used for material processing, material modification, sterilization, food preservation, non destructive testing etc. In this talk, role of low energy accelerators in research and industry as well as medicine will be discussed. (author)

  12. LHC progress report

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    Last weekend saw a record physics fill with a tenfold increase in instantaneous luminosity (event rate from collisions), marking an important milestone for the LHC. This physics fill did not only establish luminosities above 1.1 x 1028 cm-2 s-1 in all four experiments but was also kept in "stable beam" mode for a new record length of 30 hours. The particle physics experiments were able to more than double the total number of events so far recorded at 3.5 TeV.   The LHC screen indicating that squeezed stable beams have been achieved for the first time. The very successful weekend had been preceded by hard work on the accelerator side. A factor 5 improvement in luminosity was achieved by "squeezing" (reducing) the beam sizes at all four interaction points. This process, one of the most complex stages in the operation of the accelerator, was finalised the week before. Once the machine is "squeezed", the experimental insertions become aperture bot...

  13. M. G.-F. Leclerc, Préfet de la Haute-Savoie lors de sa visite dans le tunnel du LHC au Point 2 avec D. Delikaris, Département Technologie; dans la caverne de l'expérience ALICE avec B. Erazmus, Collaboration ALICE et lors de la signature du livre d'or avec F. Bordry, Chef du Département Technologie. P. Fassnacht, Conseiller au Bureau des Relations internationales présent.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    M. G.-F. Leclerc, Préfet de la Haute-Savoie lors de sa visite dans le tunnel du LHC au Point 2 avec D. Delikaris, Département Technologie; dans la caverne de l'expérience ALICE avec B. Erazmus, Collaboration ALICE et lors de la signature du livre d'or avec F. Bordry, Chef du Département Technologie. P. Fassnacht, Conseiller au Bureau des Relations internationales présent.

  14. 28 August 2013 - Ambassador Extraordinary and Plenipotentiary Permanent Representative of Ireland to the United Nations Office and specialized institutions in Geneva Mr G. Corr signing the guest book with CERN Director-General R. Heuer; visiting the LHCb experimental area with LHCb Collaboration Spokesperson P. Campana and visiting the LHC tunnel at Point 8 with International Relations Adviser for Ireland E. Tsesmelis. Accompanied throughout by R. McNulty.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    28 August 2013 - Ambassador Extraordinary and Plenipotentiary Permanent Representative of Ireland to the United Nations Office and specialized institutions in Geneva Mr G. Corr signing the guest book with CERN Director-General R. Heuer; visiting the LHCb experimental area with LHCb Collaboration Spokesperson P. Campana and visiting the LHC tunnel at Point 8 with International Relations Adviser for Ireland E. Tsesmelis. Accompanied throughout by R. McNulty.

  15. 18 December 2012 -Portuguese President of FCT M. Seabra visiting the Computing Centre with IT Department Head F. Hemmer, ATLAS experimental area with Collaboration Spokesperson F. Gianotti and A. Henriques Correia, in the LHC tunnel at Point 2 and CMS experimental area with Deputy Spokesperson J. Varela, signing an administrative agreement with Director-General R. Heuer; LIP President J. M. Gago and Delegate to CERN Council G. Barreia present.

    CERN Multimedia

    Samuel Morier-Genoud

    2012-01-01

    18 December 2012 -Portuguese President of FCT M. Seabra visiting the Computing Centre with IT Department Head F. Hemmer, ATLAS experimental area with Collaboration Spokesperson F. Gianotti and A. Henriques Correia, in the LHC tunnel at Point 2 and CMS experimental area with Deputy Spokesperson J. Varela, signing an administrative agreement with Director-General R. Heuer; LIP President J. M. Gago and Delegate to CERN Council G. Barreia present.

  16. 9 February 2012 - Permanent Representative of the Kingdom of Spain to the United Nations Office at Geneva and other International Organisations, Ambassador A. Santos Maraver signing the guest book with CERN Director-General; in the CERN Control Centre with N. Catalan; visiting the LHC tunnel at Point 5 and CMS underground experimental area with Collaboration Spokesperson J. Incandela; throughout accompanied by Adviser J. Salicio Diez and Former Physics Deputy Department Head L. Alvarez Gaumé.

    CERN Multimedia

    Visual Media Office

    2012-01-01

    9 February 2012 - Permanent Representative of the Kingdom of Spain to the United Nations Office at Geneva and other International Organisations, Ambassador A. Santos Maraver signing the guest book with CERN Director-General; in the CERN Control Centre with N. Catalan; visiting the LHC tunnel at Point 5 and CMS underground experimental area with Collaboration Spokesperson J. Incandela; throughout accompanied by Adviser J. Salicio Diez and Former Physics Deputy Department Head L. Alvarez Gaumé.

  17. 28 November 2013 - N. N. Kudryavtsev, Russian Rector of the Moscow Institute of Physics and Technology signing an Agreement and the Guest Book with CERN Director-General R. Heuer; visiting the ATLAS cavern with ATLAS Deputy Spokesperson B. Heinemann and visiting the LHC tunnel at Point 1 with AGH University of Science and Technology A. Erokhin. M. Savino, Physics Department, Joint Institute for Nuclear Research also present.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    28 November 2013 - N. N. Kudryavtsev, Russian Rector of the Moscow Institute of Physics and Technology signing an Agreement and the Guest Book with CERN Director-General R. Heuer; visiting the ATLAS cavern with ATLAS Deputy Spokesperson B. Heinemann and visiting the LHC tunnel at Point 1 with AGH University of Science and Technology A. Erokhin. M. Savino, Physics Department, Joint Institute for Nuclear Research also present.

  18. 10 September 2013 - Italian Minister for Economic Development F. Zanonato visiting the ATLAS cavern with Collaboration Spokesperson D. Charlton and Italian scientists F. Gianotti and A. Di Ciaccio; signing the guest book with CERN Director-General R. Heuer and Director for Research and Scientific Computing S. Bertolucci; in the LHC tunnel with S. Bertolucci, Technology Deputy Department Head L. Rossi and Engineering Department Head R. Saban; visiting CMS cavern with Scientists G. Rolandi and P. Checchia.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    10 September 2013 - Italian Minister for Economic Development F. Zanonato visiting the ATLAS cavern with Collaboration Spokesperson D. Charlton and Italian scientists F. Gianotti and A. Di Ciaccio; signing the guest book with CERN Director-General R. Heuer and Director for Research and Scientific Computing S. Bertolucci; in the LHC tunnel with S. Bertolucci, Technology Deputy Department Head L. Rossi and Engineering Department Head R. Saban; visiting CMS cavern with Scientists G. Rolandi and P. Checchia.

  19. 29 October 2013 - Former Director-General of IAEA H. Blix on the occasion of the Thorium Energy Conference at CERN with Chair of the ThEC13 Organization Committee E. Lillestol and Author of the book “Atome Vert” (Green Atom) J.-C. de Mestral; in the LHC tunnel at Point 1 with Technology Department, Machine Protection & Electrical Integrity Group, Performance Evaluation Section Member A. Verweij.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    29 October 2013 - Former Director-General of IAEA H. Blix on the occasion of the Thorium Energy Conference at CERN with Chair of the ThEC13 Organization Committee E. Lillestol and Author of the book “Atome Vert” (Green Atom) J.-C. de Mestral; in the LHC tunnel at Point 1 with Technology Department, Machine Protection & Electrical Integrity Group, Performance Evaluation Section Member A. Verweij.

  20. 28 August 2013 - Director of Technical Quality Management Head of ESTEC Establishment European Space Agency F. Ongaro visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and Technology Department J.-P. Tock; visiting the ATLAS experimental area with ATLAS Deputy Spokesperson T. Wengler and signing the guest book with CERN Director-General R. Heuer. Accompanied throughout by F. Bordry and V. Parma.

    CERN Multimedia

    Jean-Claude Gadmer

    2013-01-01

    28 August 2013 - Director of Technical Quality Management Head of ESTEC Establishment European Space Agency F. Ongaro visiting the LHC tunnel at Point 1 with Technology Department Head F. Bordry and Technology Department J.-P. Tock; visiting the ATLAS experimental area with ATLAS Deputy Spokesperson T. Wengler and signing the guest book with CERN Director-General R. Heuer. Accompanied throughout by F. Bordry and V. Parma.

  1. 10 October 2013 - D. Braun First Deputy Minister for Regional Development, Czech Republic, P. Styczeń Deputy Minister of Transport, Construction and Maritime Economy, Republic of Poland and F. Palko State Secretary, Ministry of Transport, Construction and Regional Development, Slovak Republic visiting the LHC tunnel at Point 1 with Technology Department, Vacuum, Surfaces and Coatings Group Leader J. M. Jimenez and signing the Guest book with CERN Director-General R. Heuer

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    10 October 2013 - D. Braun First Deputy Minister for Regional Development, Czech Republic, P. Styczeń Deputy Minister of Transport, Construction and Maritime Economy, Republic of Poland and F. Palko State Secretary, Ministry of Transport, Construction and Regional Development, Slovak Republic visiting the LHC tunnel at Point 1 with Technology Department, Vacuum, Surfaces and Coatings Group Leader J. M. Jimenez and signing the Guest book with CERN Director-General R. Heuer

  2. 6 January 2011 - Extraordinary and plenipotentiary Ambassador M. Kovačič, Permanent Representative of the Republic of Slovenia to the United Nations Office and other international Organisations at Geneva (and Permanent Mission Staff)signing the guest book with CERN Director-General R. Heuer; in the ATLAS visitor centre, ATLAS underground area and LHC tunnel with Collaboration Spokesperson F. Gianotti and Adviser T. Kurtyka.

    CERN Multimedia

    Jean-Claude Gadmer

    2011-01-01

    6 January 2011 - Extraordinary and plenipotentiary Ambassador M. Kovačič, Permanent Representative of the Republic of Slovenia to the United Nations Office and other international Organisations at Geneva (and Permanent Mission Staff)signing the guest book with CERN Director-General R. Heuer; in the ATLAS visitor centre, ATLAS underground area and LHC tunnel with Collaboration Spokesperson F. Gianotti and Adviser T. Kurtyka.

  3. 3rd May 2009 - Japanese Minister of State for Science and Technology Policy, Food Safety, Minister of Consumer Affairs, Minister of Space Policy S. Noda, visiting ATLAS experimental area, LHC tunnel and CERN Control Centre with CERN Director-General R. Heuer, Collaboration Spokesperson F. Gianotti and Beams Department Head P. Collier.

    CERN Document Server

    Maximilien Brice

    2009-01-01

    090506101-08: signature of the guest book and exchange of gifts; 090506109 + 46-64: Japanese Ambassador to the United Nations Office S. Kitajima, Japanese Minister of State for Science and Technology Policy, Food Safety, Minister of Consumer Affairs, Minister of Space Policy S. Noda, CERN Director-General R. Heuer, Non Member-State relations Adviser J. Ellis and ATLAS Collaboration Spokesperson F. Gianotti visiting the LHC tunnel at Point 1; 090506110-11 + 28-45: Japanese Minister of State for Science and Technology Policy, Food Safety, Minister of Consumer Affairs, Minister of Space Policy S. Noda and his delegation visiting ATLAS experimental area with CERN Japanese users and Management; 090506112 + 86-94: Japanese Minister of State for Science and Technology Policy, Food Safety, Minister of Consumer Affairs, Minister of Space Policy S. Noda, CERN Director-General R. Heuer and Japanese users in front of an LHC superconducting magnet; sLHC Project Leader also present. 090506113-19: Arrival of Japanese Min...

  4. The first LHC insertion quadrupole

    CERN Multimedia

    2004-01-01

    An important milestone was reached in December 2003 at the CERN Magnet Assembly Facility. The team from the Accelerator Technology - Magnet and Electrical Systems group, AT-MEL, completed the first special superconducting quadrupole for the LHC insertions which house the experiments and major collider systems. The magnet is 8 metres long and contains two matching quadrupole magnets and an orbit corrector, a dipole magnet, used to correct errors in quadrupole alignment. All were tested in liquid helium and reached the ultimate performance criteria required for the LHC. After insertion in the cryostat, the superconducting magnet will be installed as the Q9 quadrupole in sector 7-8, the first sector of the LHC to be put in place in 2004. Members of the quadrupole team, from the AT-MEL group, gathered around the Q9 quadrupole at its inauguration on 12 December 2003 in building 181.

  5. Considerations on Energy Frontier Colliders after LHC

    Energy Technology Data Exchange (ETDEWEB)

    Shiltsev, Vladimir [Fermilab

    2016-11-15

    Since 1960’s, particle colliders have been in the forefront of particle physics, 29 total have been built and operated, 7 are in operation now. At present the near term US, European and international strategies of the particle physics community are centered on full exploitation of the physics potential of the Large Hadron Collider (LHC) through its high-luminosity upgrade (HL-LHC). The future of the world-wide HEP community critically depends on the feasibility of possible post-LHC colliders. The concept of the feasibility is complex and includes at least three factors: feasibility of energy, feasibility of luminosity and feasibility of cost. Here we overview all current options for post-LHC colliders from such perspective (ILC, CLIC, Muon Collider, plasma colliders, CEPC, FCC, HE-LHC) and discuss major challenges and accelerator R&D required to demonstrate feasibility of an energy frontier accelerator facility following the LHC. We conclude by taking a look into ultimate energy reach accelerators based on plasmas and crystals, and discussion on the perspectives for the far future of the accelerator-based particle physics. This paper largely follows previous study [1] and the presenta ion given at the ICHEP’2016 conference in Chicago [2].

  6. LHC Report: a record start for LHC ion operation

    CERN Multimedia

    Jan Uythoven for the LHC Team

    2011-01-01

    After the technical stop, the LHC switched over to ion operation, colliding lead-ions on lead-ions. The recovery from the technical stop was very smooth, and records for ion luminosity were set during the first days of ion operation.   The LHC technical stop ended on the evening of Friday, 11 November. The recovery from the technical stop was extremely smooth, and already that same evening ion beams were circulating in the LHC. ‘Stable beams’ were declared the same night, with 2 x 2 bunches of ions circulating in the LHC, allowing the experiments to have their first look at ion collisions this year. However, the next step-up in intensity – colliding 170 x 170 bunches – was postponed due to a vacuum problem in the PS accelerator, so the collisions on Sunday, 13 November were confined to 9 x 9 bunches. The vacuum problem was solved, and on the night of Monday, 14 November, trains of 24 lead bunches were injected into the LHC and 170 x 170 bunches were brough...

  7. Status of the LHCf apparatus at LHC

    CERN Document Server

    Bonechi, L; Bongi, M; Castellini, G; D’Alessandro, R; Faus, A; Fukui, K; Haguenauer, M; Itow, Y; Kasahara, K; Macina, D; Mase, T; Masuda, K; Matsubara, Y; Menjo, H; Mizuishi, M; Muraki, Y; Papini, P; Perrot, A L; Ricciarini, S; Sako, T; Shimizu, Y; Taki, K; Tamura, T; Torii, S; Tricomi, A; Turner, W C; Velasco, J; Viciani, A; Yoshida, K

    2009-01-01

    The LHCf experiment at the LHC accelerator is ready for data taking. Both the LHCf detectors have been successfully tested and installed in their running configuration. The status of the apparatus, control software and some results of the last beam test at the SPS accelerator are presented in this work.

  8. Rejuvenating CERN's Accelerators

    CERN Multimedia

    2004-01-01

    In the coming years and especially in 2005, CERN's accelerators are going to receive an extensive renovation programme to ensure they will perform reliably and effectively when the LHC comes into service.

  9. LHC Startup

    CERN Document Server

    AUTHOR|(CDS)2067853

    2008-01-01

    The Large Hadron Collider will commence operations in the latter half of 2008. The plans of the LHC experiments ALICE, ATLAS, CMS and LHCb are described. The scenario for progression of luminosity and the strategies of these 4 experiments to use the initial data are detailed. There are significant measurements possible with integrated luminosities of 1, 10 and 100 pb^-1. These measurements will provide essential calibration and tests of the detectors, understanding of the Standard Model backgrounds and a first oportunity to look for new physics.

  10. Co-operation Agreement relating to LHC Commissioning

    CERN Multimedia

    2005-01-01

    CERN Director-General Robert Aymar and Ryszard Tadeusiewicz, the Rector of the AGH University of Science and Technology in Cracow, after signing the agreement. On 29 July, the Rector of the AGH University of Science and Technology in Cracow, Ryszard Tadeusiewicz, and CERN Director-General Robert Aymar signed a collaboration agreement relating to the commissioning of the instrumentation and monitoring equipment for the LHC cryogenic system. Under the agreement, a team consisting of a dozen physicists, engineers and technicians from the AGH University in Cracow will lend a helping hand to the teams at CERN for the commissioning of the cryogenic system in the tunnel. This is the first in what will be a series of agreements relating to the commissioning of the LHC's various systems. From the end of this year until the summer of 2007, CERN will require reinforcements of physicists, engineers and technicians in order to complete the many tasks associated with the start-up of the accelerator. CERN is therefore pre...

  11. Plans for the upgrade of the LHC injectors

    CERN Document Server

    Garoby, R; Goddard, B; Hanke, K; Meddahi, M; Vretenar, M

    2011-01-01

    The LHC injectors upgrade (LIU) project has been launched at the end of 2010 to prepare the CERN accelerator complex for reliably providing beam with the challenging characteristics required by the high luminosity LHC until at least 2030. Based on the work already started on Linac4, PS Booster, PS and SPS, the LIU project coordinates studies and implementation, and interfaces with the high luminosity LHC (HL-LHC) project which looks after the upgrade of the LHC itself, expected by the end of the present decade. The anticipated beam characteristics are described, as well as the status of the studies and the solutions envisaged for improving the injector performances.

  12. CERN Open Days 2013, Point 6: Accelerator Systems

    CERN Multimedia

    CERN Photolab

    2013-01-01

    Stand description: Each beam of protons that races around the Large Hadron Collider can contain as much energy as a French TGV train travelling at 150 km/hour.  When it's time to shut the machine down, the Beam Dump System ensures that this energy is safely dissipated. In the tunnel at Point 6 you will be able to see the devices which form part of this system, as well as the blue LHC dipole magnets curving away into the distance. On surface no restricted access  On the surface, you can explore a fascinating exhibition of equipment used in CERN's accelerators, with CERN engineers and physicists on hand all day to answer your questions. You will also see one of the cryogenics installations which keep the LHC at just few degrees above absolute zero and you can find out about the measures CERN has put in place to ensure safety and protect the environment.

  13. Hybrid beams in the LHC

    CERN Multimedia

    CERN Bulletin

    2011-01-01

    The first proton-ion beams were successfully circulated in the LHC a couple of weeks ago. Everything went so smoothly that the LHC teams had planned the first p-Pb collisions for Wednesday, 16 November. Unfortunately, a last-minute problem with a component of the PS required for proton acceleration prevented the LHC teams from making these new collisions. However, the way is open for a possible physics run with proton-lead collisions in 2012.   Members of the LHC team photographed when the first hybrid beams got to full energy. The proton and lead beams are visible on the leftmost screen up on the wall (click to enlarge the photo). The technical challenge of making different beams circulate in the LHC is by no means trivial. Even if the machine is the same, there are a number of differences when it is operated with beams of protons, beams of lead or beams of proton and lead. Provided that the beams are equal, irrespective of whether they consist of protons or lead nuclei, they revolve at the...

  14. The LHC and its successors

    CERN Multimedia

    Anaïs Schaeffer

    2012-01-01

    Not too long before the first long technical stop of the LHC, engineers and physicists are already working on the next generation of accelerators: HL-LHC and LHeC. The first would push proton-proton collisions to an unprecedented luminosity rate; the second would give a second wind to electron-proton collisions.   The ring-ring configuration of the LHeC would need this type of magnets, currently being studied for possible future use. In one year, the LHC will begin to change. During the first long shutdown, from December 2012 to late 2014, the machine will go through a first phase of major upgrades, with the objective of running at 7 TeV per beam at the beginning of 2015. With this long technical stop and the two others that will follow (in 2018 and 2022), a new project will see the light of day. Current plans include the study of something that looks more like a new machine rather than a simple upgrade: the High Luminosity LHC (HL-LHC). Much more powerful than the current machine, the HL-...

  15. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. In this way the magnet is delivered directly to its installation point, but beneath the beamline. It is then raised into its final position in the beamline using air cushions, which form an integrated part of the transport system.Photos 01, 02: Pictured with the newly installed magnet and transport system in the transfer line tunnel are LHC project leader Lyn Evans (second left, white helmet); Volker Mertens, responsible for the LHC injecti...

  16. Beam-gas Background Observations at LHC

    CERN Document Server

    AUTHOR|(INSPIRE)INSPIRE-00214737; The ATLAS collaboration; Alici, Andrea; Lazic, Dragoslav-Laza; Alemany Fernandez, Reyes; Alessio, Federico; Bregliozzi, Giuseppe; Burkhardt, Helmut; Corti, Gloria; Guthoff, Moritz; Manousos, Athanasios; Sjoebaek, Kyrre; D'Auria, Saverio

    2017-01-01

    Observations of beam-induced background at LHC during 2015 and 2016 are presented in this paper. The four LHC experiments use the non-colliding bunches present in the physics-filling pattern of the accelerator to trigger on beam-gas interactions. During luminosity production the LHC experiments record the beam-gas interactions using dedicated background monitors. These data are sent to the LHC control system and are used to monitor the background levels at the experiments during accelerator operation. This is a very important measurement, since poor beam-induced background conditions can seriously affect the performance of the detectors. A summary of the evolution of the background levels during 2015 and 2016 is given in these proceedings.

  17. Japanese contributions to CERN-LHC

    International Nuclear Information System (INIS)

    Kondo, Takahiko; Shintomi, Takakazu; Kimura, Yoshitaka

    2001-01-01

    The Large Hadron Collider (LHC) is now under construction at CERN, Geveva, to study frontier researches of particle physics. The LHC is the biggest superconducting accelerator using the most advanced cryogenics and applied superconductivities. The accelerator and large scale detectors for particle physics experiments are being constructed by collaboration with European countries and also by participation with non-CERN countries worldwide. In 1995, the Japanese government decided to take on a share in the LHC project with funding and technological contributions. KEK contributes to the development of low beta insertion superconducting quadrupole magnets and of components of the ATLAS detector by collaboration with university groups. Some Japanese companies have received contracts for technically key elements such as superconducting cable, cold compressor, nonmagnetic steel, polyimide film, and so on. An outline of the LHC project and Japanese contributions are described. (author)

  18. LHC Report: focus on luminosity

    CERN Document Server

    Reyes Alemany Fernandez for the LHC team

    2016-01-01

    The intensity ramp-up of the LHC beams resumed last Friday after the main powering system of the PS accelerator was put back in service.    The image above shows the last twenty four hours of fill #4947 in the machine. The LHC operations team kept the beams of this fill in the machine for a record 35 and a half hours.  Beams are back in the LHC. On Friday, the accelerator resumed the intensity ramp-up, reaching 1752 bunches per beam last week-end. The intensity ramp-up was interrupted on 20 May because of a problem with the PS’s main power supply (see box). A steady increase in the total number of bunches per beam is required to check out all aspects of beam operation and make sure the LHC is fully safe before the nominal number of bunches per beam can be brought into collision. At present, four intensity steps have been completed: 313, 601, 889, and 1177 bunches per beam. The qualification of the next step with 1752 bunches is in progress. At every s...

  19. Application of diamond based beam loss monitors at LHC

    Energy Technology Data Exchange (ETDEWEB)

    Hempel, Maria

    2013-04-15

    The Large Hadron Collider (LHC) was conceived in the 1980s and started the operation in 2008. It needed more than 20 years to plan and construct this accelerator and its experiments. Four main experiments are located around the ring, Compact Muon Solenoid (CMS), A Toroidal LHC Apparatus(ATLAS), A Large Ion Collider Experiment (ALICE) and LHC beauty (LHCb). Two beams that traveling in opposite direction in the LHC tunnel, collide in each of the experiments to study the questions: ''What is mass?'', ''What is the universe made of?'' and ''Why is there no antimatter?''. The four experiments take data of the collision products and try to answer the fundamental questions of physics. The two larger detectors, CMS and ATLAS, are looking for the Higgs boson to study the electroweak symmetry breaking. Both detectors were built with contrasting concepts to exclude potential error sources and to rea rm the results. The smaller experiment LHCb studies the matter-antimatter asymmetry with a focus of the beauty quark. Another smaller experiment is ALICE that studies the conditions right after the Big Bang by colliding heavy ions. The navigation of the beams is done by over 10000 magnets and each beam has a stored energy of 362MJ which correspond to the kinetic energy of a train like the TGV travelling of 150 km/h. Only a small percentage of that energy can damage the material in the LHC ring or the magnets. This would mean a repair time of months or years, without taking any data. To avoid such a scenario, it is important to monitor the beam condition and measure the amount of losses of the beam. Such losses can for example happen due to dust particles in the vacuum chambers or due to deviations of the beam parameters. Several systems called beam loss monitors (BLMs) can measure beam losses. This thesis concentrates on two of them, ionization chambers and diamond detectors. Over 3600 ionization chambers are installed in

  20. Application of diamond based beam loss monitors at LHC

    International Nuclear Information System (INIS)

    Hempel, Maria

    2013-04-01

    The Large Hadron Collider (LHC) was conceived in the 1980s and started the operation in 2008. It needed more than 20 years to plan and construct this accelerator and its experiments. Four main experiments are located around the ring, Compact Muon Solenoid (CMS), A Toroidal LHC Apparatus(ATLAS), A Large Ion Collider Experiment (ALICE) and LHC beauty (LHCb). Two beams that traveling in opposite direction in the LHC tunnel, collide in each of the experiments to study the questions: ''What is mass?'', ''What is the universe made of?'' and ''Why is there no antimatter?''. The four experiments take data of the collision products and try to answer the fundamental questions of physics. The two larger detectors, CMS and ATLAS, are looking for the Higgs boson to study the electroweak symmetry breaking. Both detectors were built with contrasting concepts to exclude potential error sources and to rea rm the results. The smaller experiment LHCb studies the matter-antimatter asymmetry with a focus of the beauty quark. Another smaller experiment is ALICE that studies the conditions right after the Big Bang by colliding heavy ions. The navigation of the beams is done by over 10000 magnets and each beam has a stored energy of 362MJ which correspond to the kinetic energy of a train like the TGV travelling of 150 km/h. Only a small percentage of that energy can damage the material in the LHC ring or the magnets. This would mean a repair time of months or years, without taking any data. To avoid such a scenario, it is important to monitor the beam condition and measure the amount of losses of the beam. Such losses can for example happen due to dust particles in the vacuum chambers or due to deviations of the beam parameters. Several systems called beam loss monitors (BLMs) can measure beam losses. This thesis concentrates on two of them, ionization chambers and diamond detectors. Over 3600 ionization chambers are installed in the LHC, especially near each quadrupole and next to

  1. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. The first installation phase will continue until mid-April. In addition to the magnets, a beam dump facility also has to be installed. The second installation phase will take place later this year and should be completed in 2004, when the TI 8 transfer line is due to be tested. The second transfer line, in tunnel TI 2, should be ready in April 2007, once the LHC magnets have been transported through the downstream section of this tunnel.Pho...

  2. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. The first installation phase will continue until mid-April. In addition to the magnets, a beam dump facility also has to be installed. The second installation phase will take place later this year and should be completed in 2004, when the TI 8 transfer line is due to be tested. The second transfer line, in tunnel TI 2, should be ready in April 2007, once the LHC magnets have been transported through the downstream section of this tunnel. Th...

  3. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. The first installation phase will continue until mid-April. In addition to the magnets, a beam dump facility also has to be installed. The second installation phase will take place later this year and should be completed in 2004, when the TI 8 transfer line is due to be tested. The second transfer line, in tunnel TI 2, should be ready in April 2007, once the LHC magnets have been transported through the downstream section of this tunnel. We...

  4. A Virtual CAD Model of the LHC

    CERN Document Server

    Chemli, S; Messerli, R; Muttoni, Y; Prin, H; Van Uytvinck, E

    2000-01-01

    Integrating the large and complex LHC machine into the existing LEP tunnel is a major challenge. Space was not really a problem to fit the LEP machine into its tunnel, but LHC cryostats are much larger than the LEP quadrupoles and the external cryogenic line fills even more the tunnel. Space problems lead to small clearances. Possible conflicts, or at least the most penalising ones, between installed equipment or with transport, must be solved beforehand in order to avoid unacceptable delays and extra costs during the installation. Experience gained with LEP has already shown the help that Computer-Aided Engineering tools could provide for the integration. A virtual model of the LHC is presently prepared. The actual LEP tunnel, known with a quite good accuracy (centimetre level), has been modelled and all the elements of the machine constructed as 3D objects with the CAD system are positioned accurately on the basis of data generated from the theoretical definition. These layouts are used to generate the refe...

  5. Status and prospects from the LHC

    International Nuclear Information System (INIS)

    Hawkings, Richard

    2010-01-01

    This article reviews the status of the CERN Large Hadron Collider and associated experiments as of July 2010. After a brief discussion of the progress in accelerator and experiment commissioning, the LHC physics landscape is presented, together with a selection of the experimental results achieved so far. Finally the prospects for the 2010-11 LHC physics run are reviewed, with an emphasis on possible discoveries in the Higgs and supersymmetry sectors.

  6. CERN prepares for the LHC and beyond

    Energy Technology Data Exchange (ETDEWEB)

    Rodgers, Peter

    2000-05-01

    The phrase ''needle in a haystack'' - the challenge of finding something small but important in the midst of a much, much larger object - is often used to describe CERN. It could be applied to searching for someone's office in one of the 373 buildings that occupy the laboratory's site at Meyrin, just outside Geneva on the Swiss rench border, but the real needle in the haystack at CERN is the Higgs boson. The Higgs is the particle that is responsible for other fundamental particles such as quarks and Z-bosons having mass. It is also the main reason that CERN is building a machine called the Large Hadron Collider (LHC) at a cost of SwFr 2bn. Particles predicted by supersymmetry the theory that every particle has a supersymmetric partner with the same mass and charge but different ''spin'' are the other top priority. There is a chance, albeit it a small one, that particle physicists might find the Higgs boson at CERN's large electron positron (LEP) collider before it is shut down to make way for the LHC. It all depends on how high the beam energy at LEP which currently stands at 103 GeV (103 X 109 electron volts) can be raised. ''1 GeV can matter at this stage'', says Luciano Maiani, the lab's director general. ''Exploring up to a mass of 114 GeV is optimistic but not impossible. Unless we see the Higgs, the current plan is for LEP to be dismantled after it stops running at the end of September. Installation of the LHC in the LEP tunnel will then start in October.'' The LHC will collide protons at a centre-of-mass energy of 14 TeV (14 000 GeV), and two massive general-purpose detectors ATLAS and CMS will search for evidence of the Higgs and supersymmetry. A third experiment called LHC-b will probe the difference between matter and antimatter, while the ALICE experiment will study the extreme state of matter known as the quark gluon plasma. Meanwhile, two massive teams

  7. The whole world behind the LHC

    CERN Multimedia

    2001-01-01

    The LHC Board, which includes representatives of the non-Member State organisations directly involved in the construction of the LHC accelerator and representatives of CERN, held its fourth meeting on Monday 21 May 2001. From left to right: 1st row, A. Yamamoto (KEK, Japan), P. Pfund (FNAL, United States), L. Maiani (CERN Director-General), L. Evans (LHC Project Leader), F. Dupont (IN2P3, France), D.D. Bhawalkar (CAT, India) ; 2nd row, P. Brossier (CEA, France), N. Tyurin (IHEP, Russia), A. Skrinsky (BINP, Russia), A. Astbury (TRIUMF, Canada), P. Lebrun (LHC Division Leader, CERN); 3rd row, T. Taylor (Deputy Division Leader LHC Division, CERN), A. Shotter (TRIUMF, Canada), P. Bryant (LHC, CERN), K. Hübner (Director for Accelerators, CERN), J. van der Boon (Director of Administration, CERN). Although Canada, the United States, India, Japan and the Russian Federation are not members of CERN, they are all playing an active part in the construction of the LHC through important technical and financial co...

  8. Links between astroparticle physics and the LHC

    International Nuclear Information System (INIS)

    Pinfold, James L

    2005-01-01

    Research into the fundamental nature of matter at the high energy frontier takes place in three main areas: accelerator-based particle physics, high energy astrophysics, and the cosmology of the early universe. As a consequence the study of astroparticle physics can have significant implications for collider physics at the LHC. Likewise, the LHC project provides the laboratory to perform measurements of great importance for cosmic ray astrophysics and cosmology. This paper reviews some of the important synergistic links between astroparticle and LHC physics. (topical review)

  9. The metrology of the LHC project: what news?

    International Nuclear Information System (INIS)

    Chambardon, M.; Missiaen, D.; Quesnel, J.P.; Scandale, W.; Naegely, A.V.; Naegely, P.

    1999-01-01

    The Large Hadron Collider (LHC), under construction at CERN, uses superconducting magnets operating at a temperature of 1.9 K to guide the circulating particles. A specific feature of the main magnets (dipoles and quadrupoles) is the two-in-one design with two magnetic channels in one common retaining structure. Indeed, the accelerator is made of two rings, mechanically linked, that have to be simultaneously aligned during the installation in the already existing LEP tunnel. The assembly tolerances of the LHC main magnets have been reconsidered to take into account the tight constraints on geometry. The dipoles are bent to follow closely the curvature of the circulating particles and to make a larger mechanical aperture available for the circulating particles. In order to minimise the geometrical errors the dipole assembly procedure is assisted by high precision survey measurements based on laser trackers. By this we hope to reduce to ± 1 mm the positioning error along the axis of the magnets. In addition the ends of the dipoles and quadrupoles should be aligned with even better precision to reduce to below ± 0.3 mm the displacement of the bellows in the magnet-to-magnet interconnection. All these precautions are expected to make easier the installation and to improve the LHC machine operation. In Section 2, we discuss the survey activity related to the civil engineering work. In section 3 we discuss the alignment of the dipoles in their cryostats. In Section 4 we present our geodetic network and in Section 5 we draw our conclusions. (authors)

  10. Development of the System Test for the LHC Tune Measurement and Abort Gap Monitoring

    CERN Document Server

    Beccati, B

    2008-01-01

    The Large Hadron Collider (LHC) is the largest accelerator in the world and it will collide opposing beams of 7 TV protons together. It is built inside a 27km tunnel on the border between France and Switzerland. Within the framework of the project IUSS- Ferrara, I collaborated with the members of the AB-BI section at CERN: Accelerator Beam - Beam Instrumentation. My degree thesis is the result of this cooperation. My project is made of two sections, one for each themes analyzed during this year at CERN: the first one concerns the Tune, the second one is about the Abort gap. LHC is a synchrotron, an accelerator using dipole magnets to bending and quadrupole magnets to transverse focusing. Passing through this pattern of magnets, particles make oscillations. We refer to these ones as Betatron oscillations. The number of such oscillations/turn is called Tune. The ability tomeasure the tune is important for many kinds of diagnostic. In the base band tune (BBQ) measurement system developed at CERN the signal is di...

  11. The last stage of LHC construction

    International Nuclear Information System (INIS)

    Serin, L.

    2006-01-01

    A few months ago the setting of the LHC (large hadron collider) machine began in the Lep's tunnel at CERN. The LHC is composed of 1200 dipole magnets that are progressively installed in the 27 km long underground circular facility, 2 universal experiments ATLAS and CMS, huge by the size of their respective detector: 40 x 20 x 20 m as well as by their number of participants: 1500 people for each one are being built in gigantic carves. All the efforts are concentrated to make every component of the machine fully installed by summer 2007 in order to get the first collisions before 2008

  12. Chasseurs de Higgs au LHC - A la Recherche des l'Origines

    CERN Multimedia

    Yves Sirois

    To increase understanding of the LHC, why scientists collaborate on this experiment and what they hope to achieve with the LHC. A 51 slide presentation in French for a general audience. Delivered at the "Cité des Sciences" in Paris, "Rencontres du Ciel et de l'Espace," November, 2010 This presentation covers the following topics: - The LHC --what it is --what it looks like --where it is located --the international nature of CERN & experiment collaborations --the experiments - Accelerators --a brief history on accelerators --what accelerators can do - The scientific goals of the LHC - Particle Physics in General --history & the basics - Impact on Technology and Society - First LHC Results - Concluding remarks

  13. LHC beampipe section

    CERN Multimedia

    A short section of the LHC beam-pipe including beam screen. In the LHC, particles circulate under vacuum. The vacuum chamber can be at room temperature (for example, in the experimental areas), or at cryogenic temperature, in the superconductive magnets. This piece is located in the superconductive magnets. The outer pipe is the vacuum chamber, which is in contact with the magnets, at cryogenic temperature (1.9K). It is called the “cold bore”. The inner tube is the beam screen. Its main goal is to protect the magnets from the heat load coming from the synchrotron radiation. Indeed, when high energy protons’ trajectory is bent, photons are emitted by the beam. They are intercepted by the beam screen. The temperature of the beam screen is kept between 5 and 20K by a circulation of gaseous helium in the small pipes on both sides of the beam screen. As those surfaces are at cryogenic temperature. The residual gas present in the accelerator is sticking on the surfaces. This phenomenon called “adsorption”...

  14. LIGHT and LUMINOSITY, from Einstein to LHC

    CERN Multimedia

    CERN. Geneva; Prof. ROSSI, Lucio

    2015-01-01

    After an introduction on the concept of light in physics, this talk will focus on CERN’s High Luminosity LHC project, aiming at extending the discovery potential of CERN’s flagship accelerator by increasing its “luminosity” (ie the number of particles that can be squeezed inside the accelerator to maximize the number of collisions). To achieve this objective, many new technologies are being developed at CERN and many collaborating institutes worldwide, especially in the field of superconductivity. Lucio Rossi, the main speaker, is the head of the HL-LHC project, based at CERN. Giorgio Apollinari, Director for the LHC Accelerator Research Program (LARP) will speak through a videoconference from Fermilab (USA). The event is webcast live and will be followed by Fermilab and other institutes in the USA.

  15. Big advance towards the LHC upgrade

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    The LHC is currently the world’s most powerful accelerator. With its technical achievements it has already set world records. However, big science looks very far ahead in time and is already preparing already for the LHC’s magnet upgrade, which should involve a 10-fold increase of the collision rates toward the end of the next decade. The new magnet technology involves the use of an advanced superconducting material that has just started to show its potential.   The first Long Quadrupole Shell (LQS01) model during assembly at Fermilab. The first important step in the qualification of the new technology for use in the LHC was achieved at the beginning of December when the US LHC Accelerator Research Program (LARP) – a consortium of Brookhaven National Laboratory, Fermilab, Lawrence Berkeley National Laboratory and the SLAC National Accelerator Laboratory founded by US Department Of Energy (DOE) in 2003 – successfully tested the first long focussing magnet th...

  16. Does One Need a 4.5 K Screen in Cryostats of Superconducting Accelerator Devices Operating in Superfluid Helium? Lessons from the LHC

    CERN Document Server

    Lebrun, Ph; Tavian, L

    2014-01-01

    Superfluid helium is increasingly used as a coolant for superconducting devices in particle accelerators: the lower temperature enhances the performance of superconductors in high-field magnets and reduces BCS losses in RF acceleration cavities, while the excellent transport properties of superfluid helium can be put to work in efficient distributed cooling systems. The thermodynamic penalty of operating at lower temperature however requires careful management of the heat loads, achieved inter alia through proper design and construction of the cryostats. A recurrent question appears to be that of the need and practical feasibility of an additional screen cooled by normal helium at around 4.5 K surrounding the cold mass at about 2 K, in such cryostats equipped with a standard 80 K screen. We introduce the issue in terms of first principles applied to the configuration of the cryostats, discuss technical constraints and economical limitations, and illustrate the argumentation with examples taken from large proj...

  17. No access to LHC from 7 to 13 January 2008

    CERN Multimedia

    ST Department

    2007-01-01

    From 7 to 13 January 2008, tests of the LHC access system will be carried out to validate its role in the operational safety of the LHC. During this period, no access will be permitted to the controlled zones of LHC: service zones, experimental areas and tunnels. Access to the machine shafts and the tunnels will only be possible for emergency interventions coordinated with the CCC operators or for fire brigade interventions. The biometric access card integrated with the dosimeter, as issued by Bldg. 55, must be used to access these areas during this period. Access to the experimental caverns will be managed by the respective technical coordinator. After the tests, the access system will be restored to installation mode, i.e. access will again be possible using the CERN access cards for authorised personnel. Please communicate this information to your contractors. Thank you in advance for your comprehension and collaboration. Pierre Ninin - "LHC Access" project leader

  18. Fast Automatic Beam-Based Alignment of the LHC Collimator Jaws

    CERN Document Server

    AUTHOR|(CDS)2080813; Assmann, R W

    2014-01-01

    The CERN Large Hadron Collider (LHC) in Geneva, Switzerland is the largest and most powerful particle accelerator ever built. With a circumference of 27 km, it is designed to collide particles in two counter-rotating beams at a centre-of-mass energy of 14 TeV to explore the fundamental forces and constituents of matter. Due to its potentially destructive high energy particle beams, the LHC is equipped with several machine protection systems. The LHC collimation system is tasked with scattering and absorbing beam halo particles before they can quench the superconducting magnets. The 108 collimators also protect the machine from damage in the event of very fast beam losses, and shields sensitive devices in the tunnel from radiation over years of operation. Each collimator is made up of two blocks or ‘jaws’ of carbon, tungsten or copper material. The collimator jaws need be placed symmetrically on either side of the beam trajectory, to clean halo particles with maximum efficiency. The beam orbit and beam siz...

  19. LHC(ATLAS, CMS, LHCb) Run 2 commissioning status

    CERN Document Server

    Zimmermann, Stephanie; The ATLAS collaboration

    2015-01-01

    After a very successful run-1, the LHC accelerator and the LHC experiments had undergone intensive consolidation, maintenance and upgrade activities during the last 2 years in what has become known as Long-Shutdown-1 (LS1). LS1 ended in February this year, with beams back in the LHC since Easter. This talk will give a summary on the major shutdown activities of ATLAS, CMS and LHCb and review the status of commissioning for run-2 physics data taking.

  20. The latest from the LHC

    CERN Multimedia

    2009-01-01

    Work on closing up sectors in the LHC tunnel. The foreseen shutdown work on the LHC is proceeding well, including the powering tests with the new quench protection system. However, during the past week vacuum leaks have been found in two "cold" sectors of the LHC. The leaks were found in Sectors 8-1 and 2-3 while they were being prepared for the electrical tests on the copper stabilizers at around 80 K. In both cases the leak is at one end of the sector, where the electrical feedbox, DFBA, joins Q7, the final magnet in the sector. Unfortunately, the repair necessitates a partial warm-up of both sectors. This involves the end sub-sector being warmed to room temperature, while the adjacent sub-sector "floats" in temperature and the remainder of the sector is kept at 80 K. As the leak is from the helium circuit to the insulating vacuum, the repair work will have no impact on the vacuum in the beam pipe. However the intervention wil...

  1. Mechanical Behaviour of the LHC Cryodipoles

    CERN Document Server

    Buenaventura, A; Skoczen, Blazej

    2000-01-01

    The LHC cryodipoles are slender and heavy objects more than 15-m long. The major components of the cryodipole assembly are the 28-tonne cold mass, supported on its three Glass-Fibre-Reinforced-Epoxy support posts and the 4-tonne vacuum vessel. The performance of the LHC depends very much upon the accurate positioning of the dipoles and the beam tubes, in particular to maximise the useful beam apertures. The cryodipoles will be conditioned and measured in surface assembly buildings, then handled and transported to their positions in the tunnel and, finally, aligned. This paper presents the static and dynamic studies of the cryodipole in different configurations. The tests and analyses carried out have led to a thorough understanding of the mechanical behaviour of the cryodipoles. From the static analysis, an hyperstatic supporting system is proposed in order to minimise the systematic deflections and the effects due to changing temperature conditions in the tunnel. The dynamic analysis has shown that the cryod...

  2. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. In this way the magnet is delivered directly to its installation point, but beneath the beamline. It is then raised into its final position in the beamline using air cushions, which form an integrated part of the transport system. Here we see the transport vehicle alongside the magnet supports. Visible in the background is the first magnet in place.

  3. Analysis of the Dependability of the LHC Quench Detection System During LHC Run 2 and Further System Evolution

    OpenAIRE

    Podzorny, Tomasz; Calcoen, Daniel; Denz, Reiner; Siemko, Andrzej; Spasic, Jelena; Steckert, Jens

    2017-01-01

    The quench detection system (QDS) of the LHC superconducting circuits is an essential part of the LHC machine protection and ensures the integrity of key elements of the accelerator. The large amount of hardwired and software interlock channels of the QDS requires a very high system dependability in order to reduce the risk of affecting the successful operation of the LHC. This contribution will present methods and tools for systematic fault tracking and analysis, and will discuss recent resu...

  4. LHC Report: Back in operation

    CERN Multimedia

    2016-01-01

    With the machine back in their hands since Friday, 4 March, the LHC operators are now performing the powering tests on the magnets. This is a crucial step before receiving the first beams and restarting Run 2 for physics.   A Distribution Feed-Box (DFB) brings power to the LHC magnets and maintains the stability of the current in the superconducting circuits. The LHC was the last machine to be handed back to operators after the completion of maintenance work carried out during the Year-End Technical Stop (YETS) that had started on 14 December 2015. During the eleven weeks of scheduled maintenance activities, several operations took place in all the accelerators and beam lines. They included the maintenance in several points of the cryogenic system, the replacement of 18 magnets in the Super Proton Synchrotron; an extensive campaign to identify and remove thousands of obsolete cables; the replacement of the LHC beam absorbers for injection (TDIs) that are used to absorb the SPS b...

  5. Keeping the LHC in power

    CERN Multimedia

    CERN Bulletin

    2013-01-01

    The critical safety equipment around the LHC, including the machine protection systems, is connected to Uninterruptible Power Supplies (UPS).  In case of mains failure, the UPS systems continue to power, for a limited time, these critical systems and ensure a safe shutdown of the accelerator. This week, work began to upgrade and replace over 100 UPS systems in the LHC.   The new UPS installations. For the LHC, even a perturbation on the mains is more than just an inconvenience: it often results in beam dumps and, in some cases, requires an energy extraction from superconducting circuits. When this occurs, machine protection systems, and in particular the Quench Protection System, must remain active to correctly carry out the shutdown procedure. With the UPS systems, 10 minutes of crucial power can be provided to the protection systems during this critical phase. There are currently two UPS systems in place in each one of the 32 LHC UPS zones. Originally one was used as a backup if ...

  6. Great excavations refitting an existing tunnel ring at CERN for a new, more complex particle accelerator challenged designers to succeed under extraordinary conditions

    CERN Multimedia

    Wallis, S

    2001-01-01

    Caverns up to 35 m wide, 42 m high and 82 m long are now under construction at CERN to house the detectors which will be used for the LHC. The size and difficult geological conditions have made this a very challenging project (8 pages).

  7. Quench Performance of the LHC Insertion Magnets

    CERN Document Server

    Lasheras, N C; Siemko, A; Ostojic, R; Kirby, G

    2009-01-01

    After final installation in the LHC tunnel, the MQM and MQY quadrupole magnets of the LHC insertions are now being commissioned to their nominal currents. These two types of magnets operate at 1.9 K and 4.5 K and with nominal currents ranging from 3600 A to 5390 A. From the very first acceptance tests of the bare magnets coming from the manufacturers, they have been powered using different cycles, in different configurations, at different temperatures and in different tests facilities. In this paper we present the global results of these powering tests. We aim at separating common from individual features of these groups of magnets. Temperature dependence of the training, temperature margin, and ultimate current can be extracted from these tests. As these magnets are used to match the optics and the dispersion in the machine, the projected ultimate current at which they can be operated is critical in view of operation of LHC.

  8. LHC vacuum system

    CERN Document Server

    Gröbner, Oswald

    1999-01-01

    The Large Hadron Collider (LHC) project, now in the advanced construction phase at CERN, comprises two proton storage rings with colliding beams of 7-TeV energy. The machine is housed in the existing LEP tunnel with a circumference of 26.7 km and requires a bending magnetic field of 8.4 T with 14-m long superconducting magnets. The beam vacuum chambers comprise the inner 'cold bore' walls of the magnets. These magnets operate at 1.9 K, and thus serve as very good cryo-pumps. In order to reduce the cryogenic power consumption, both the heat load from synchrotron radiation emitted by the proton beams and the resistive power dissipation by the beam image currents have to be absorbed on a 'beam screen', which operates between 5 and 20 K and is inserted inside the vacuum chamber. The design of this beam screen represents a technological challenge in view of the numerous and often conflicting requirements and the very tight mechanical tolerances imposed. The synchrotron radiation produces strong outgassing from the...

  9. 30th August 2010 - Permanent Representative of the People's Republic of China to the United Nations Office at Geneva, Ambassador Y. He visiting the CMS underground experimental area and LHC tunnel with CERN Director-General R. Heuer and Collaboration Spokesperson G. Tonelli.

    CERN Multimedia

    Maximilien Brice

    2010-01-01

    CERN-HI-1008197 01: in the LHC tunnel at Point 5: CMS Collaboaration Spokesperson G. Tonelli, Mrs L. Jianping (Ambassador's spouse), Mrs B. Heuer, Permanent Representative of the People's Republic of China to the United Nations Office at Geneva, Ambassador Y. He, CERN Director-General R. Heuer and Adviser R. Voss; CERN-HI-1008197 57: in front of the CMS experiment at LHC point 5: CMS technical Coordinator A. Ball, Mrs L. Jianping (Ambassador's spouse), Permanent Representative of the People's Republic of China to the United Nations Office at Geneva, Ambassador Y. He; Mrs B. Heuer, CERN Director-General R. Heuer, CMS Collaboaration Spokesperson G. Tonelli and Adviser R. Voss. CERN-HI-1008197 02 - 14: Welcome in front of building 3562 at CMS. Head of International relations F: Pauss gives the introduction talk to the delegation. CERN-HI-1008197 15 - 25: visiting CMS control room at Point 5 with Collaboration Spokesperson G. Tonelli; CERN-HI-1008197 26 - 29: visiting the service cavern in the CMS underground ar...

  10. Helium II heat transfer in LHC magnets : polyimide cable insulation

    NARCIS (Netherlands)

    Winkler, Tiemo

    2017-01-01

    Today’s large particle accelerators like the LHC at CERN are using superconducting materials as a construction material for magnets. These magnets need to be cooled constantly to temperatures below the critical surface of the superconducting material. In the LHC this is achieved by using liquid

  11. Working on an LHC dipole end-cap

    CERN Multimedia

    Laurent Guiraud

    1999-01-01

    A metal worker constructs an end-cap for an LHC dipole magnet. These magnets will be used to bend the proton beams around the LHC, which is due to start up in 2008. The handmade prototype seen here will be used to make a mold from which the final set of components will be made for the accelerator.

  12. Tunneling works. Tunnel koji

    Energy Technology Data Exchange (ETDEWEB)

    Higo, M [Hazam Gumi, Ltd., Tokyo (Japan)

    1991-10-25

    A mountain tunneling method for rock-beds used to be applied mainly to construction works in the mountains under few restrictions by environmental problems. However, construction works near residential sreas have been increasing. There are such enviromental problems due to tunneling works as vibration, noise, lowering of ground-water level, and influences on other structures. This report mainly describes the measurement examples of vibration and noise accompanied with blasting and the effects of the measures to lessen such influences. When the tunneling works for the railroad was carried out on the natural ground mainly composed of basalt, vibration of the test blasting was measured at three stations with piezoelectric accelerometers. Then, ordinary blasting, mutistage blasting, and ABM blasting methods were used properly besed on the above results, and only a few complaints were made. In the different works, normal noise and low-frequency sound were mesured at 22 stations around the pit mouth. As countermeasures for noise, sound-proof sheets, walls, and single and double doors were installed and foundto be effective. 1 ref., 6 figs., 1 tab.

  13. Installation of the LHC transfer lines begins

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. In this way the magnet is delivered directly to its installation point, but beneath the beamline. It is then raised into its final position in the beamline using air cushions, which form an integrated part of the transport system.Photo 01: Pictured with the newly installed magnet and transport system in the transfer line tunnel are (left to right) Volker Mertens, responsible for the LHC injection and transfer lines; personnel involved in tr...

  14. HL-LHC updates in Japan

    CERN Multimedia

    Antonella Del Rosso

    2014-01-01

    At a recent meeting in Japan, updates on the High Luminosity LHC (HL-LHC) project were presented, including the progress made so far and the deadlines still to be met for the upgraded machine to be operational from 2020.   New magnets made with advanced superconductor Nb3Sn in the framework of the HL-LHC project. These magnets are currently under construction at CERN by the TE-MSC group. The LHC is the world’s most powerful particle accelerator, and in 2015 it will reach yet another new record for the energy of its colliding beams. One key factor of its discovery potential is its ability to produce collisions described in mathematical terms by the parameter known as “luminosity”. In 2025, the HL-LHC project will allow the total number of collisions in the LHC to increase by a factor of 10. The first step in this rich upgrade programme is the delivery of the Preliminary Design Report (PDR), which is also a key milestone of the HiLumi LHC Design Study partly fund...

  15. Accelerators Beyond The Tevatron?

    Energy Technology Data Exchange (ETDEWEB)

    Lach, Joseph; /Fermilab

    2010-07-01

    Following the successful operation of the Fermilab superconducting accelerator three new higher energy accelerators were planned. They were the UNK in the Soviet Union, the LHC in Europe, and the SSC in the United States. All were expected to start producing physics about 1995. They did not. Why?

  16. Superconducting magnet development for the LHC upgrades

    International Nuclear Information System (INIS)

    Rossi, Lucio

    2012-01-01

    LHC is now delivering proton and heavy ion collisions at the highest energy. Upgrading the LHC beyond its design performance is a long term program that started during the LHC construction, with some fundamental R and D programs. The upgrade program is based on a vigorous superconductor and magnet R and D, aimed at increasing the field in accelerator magnets from 8 T to 12 T for the luminosity upgrade, with the scope of increasing the collider luminosity by a factor 5 to 10 from 2022. The upgrade program might continue with the LHC energy upgrade, which would require magnets producing field in the range of 16-20 T. The results obtained so far and the future challenges are discussed together with the possible plan to reach the goals. (author)

  17. Literature in Focus Perspectives on LHC Physics

    CERN Multimedia

    2008-01-01

    The CERN Library invites you to a book presentation, a Literature in Focus event. The Large Hadron Collider (LHC) will be the world’s largest, highest energy and highest intensity particle accelerator. This is a timely book with several perspectives on the hoped-for discoveries from the LHC. This book provides an overview of the techniques that will be crucial for finding new physics at the LHC, as well as perspectives on the importance and implications of the discoveries. Among the accomplished contributors to this book are leaders and visionaries in the field of particle physics beyond the Standard Model, including two Nobel Laureates (Steven Weinberg and Frank Wilczek). With its blend of popular and technical contents, the book will have wide appeal, not only to physical scientists but also to those in related fields. Perspectives on LHC Physics (World Scientific Publishing) Gordon Kane and Aaron Pierce (eds.) Tuesday 12 August, 4.30pm Council Chamber Refresh...

  18. First beam splashes at the LHC

    CERN Multimedia

    CERN Bulletin

    2015-01-01

    After a two-year shutdown, the first beams of Run 2 circulated in the LHC last Sunday. On Tuesday, the LHC operators performed dedicated runs to allow some of the experiments to record their first signals coming from particles splashed out when the circulating beams hit the collimators. Powerful reconstruction software then transforms the electronic signals into colourful images.     “Splash” events are used by the experiments to test their numerous subdetectors and to synchronise them with the LHC clock. These events are recorded when the path of particles travelling in the LHC vacuum pipe is intentionally obstructed using collimators – one-metre-long graphite or tungsten jaws that are also used to catch particles that wander too far from the beam centre and to protect the accelerator against unavoidable regular and irregular beam losses. The particles sprayed out of the collision between the beam and the collimators are mostly muons. ATLAS and CMS&...

  19. CERN confident of LHC start-up in 2007

    CERN Document Server

    2007-01-01

    "Delegates attending the 140th meeting of CERN Council heard a confident report from the Laboratory about the scheduled start-up of the world's highest energy particle accelerator, the Large Hadron Collier (LHC), in 2007." (1 page)

  20. Status of superconducting magnet development (SSC, RHIC, LHC)

    International Nuclear Information System (INIS)

    Wanderer, P.

    1993-01-01

    This paper summarize recent superconducting accelerator magnet construction and test activities at the Superconducting Super Collider Laboratory (SSC), the Large Hadron Collider at CERN (LHC), and the Relativistic Heavy Ion Collider at Brookhaven (RHIC). Future plan are also presented

  1. Big Bang test delayed at CERN's LHC until 2008

    CERN Multimedia

    Atkins, William

    2007-01-01

    "Scientists at the proton-proton Large Hadron Collider (LHC) particle accelerator and collider will postpone a test that could help solve the mystery of what happened a few nanoseconds after the Big Bang." (1 page)

  2. Status of superconducting magnet development (SSC, RHIC, LHC)

    International Nuclear Information System (INIS)

    Wanderer, P.

    1993-01-01

    This paper summarizes recent superconducting accelerator magnet construction and test activities at the Superconducting Super Collider Laboratory (SSC), the Large Hardon Collider at CERN (LHC), and the Relativistic Heavy Ion Collider at Brookhaven (RHIC). Future plans are also presented

  3. Spring 
start-up for the LHC

    CERN Multimedia

    2007-01-01

    A new schedule for the commissioning of the LHC was presented to the Council at its Session in June. The start-up of the accelerator is scheduled for May 2008, to allow all technical problems to be resolved.

  4. Taiwan links up to world's first LHC computing grid project

    CERN Multimedia

    2003-01-01

    "Taiwan's Academia Sinica was linked up to the Large Hadron Collider (LHC) Computing Grid Project last week to work jointly with 12 other countries to construct the world's largest and most powerful particle accelerator" (1/2 page).

  5. Crystals in the LHC

    CERN Multimedia

    Antonella Del Rosso

    2012-01-01

    Bent crystals can be used to deflect charged particle beams. Their use in high-energy accelerators has been investigated for almost 40 years. Recently, a bent crystal was irradiated for the first time in the HiRadMat facility with an extreme particle flux, which crystals would have to withstand in the LHC. The results were very encouraging and confirmed that this technology could play a major role in increasing the beam collimation performance in future upgrades of the machine.   UA9 bent crystal tested with a laser. Charged particles interacting with a bent crystal can be trapped in channelling states and deflected by the atomic planes of the crystal lattice (see box). The use of bent crystals for beam manipulation in particle accelerators is a concept that has been well-assessed. Over the last three decades, a large number of experimental findings have contributed to furthering our knowledge and improving our ability to control crystal-particle interactions. In modern hadron colliders, su...

  6. Slice of LHC dipole wiring

    CERN Multimedia

    Dipole model slice made in 1994 by Ansaldo. The high magnetic fields needed for guiding particles around the Large Hadron Collider (LHC) ring are created by passing 12’500 amps of current through coils of superconducting wiring. At very low temperatures, superconductors have no electrical resistance and therefore no power loss. The LHC is the largest superconducting installation ever built. The magnetic field must also be extremely uniform. This means the current flowing in the coils has to be very precisely controlled. Indeed, nowhere before has such precision been achieved at such high currents. 50’000 tonnes of steel sheets are used to make the magnet yokes that keep the wiring firmly in place. The yokes constitute approximately 80% of the accelerator's weight and, placed side by side, stretch over 20 km!

  7. LHC technical data goes mobile

    CERN Multimedia

    Jordan Juras

    2010-01-01

    The Computerized Maintenance Management System (CMMS), which has been in use at CERN for many years, has recently been enhanced with an innovative new feature for managing and exploiting existing information regarding the LHC: a system to read the barcodes on the LHC components and easily obtain data and information on the many thousands of items of equipment that make up the accelerator. The feature will eventually be made available for any other scientific instrumentation located at CERN.   Example of a magnet's barcode Systems like CERN's CMMS, which is based on an Enterprise Asset Management (EAM) system from Infor, are today standard practice in organizations managing large volumes of information about their facilities. However, the way in which CERN has adapted its system is rather unique: the CMMS not only manages the manufacturing, installation, maintenance and disposal of the components of CERN’s infrastructure but now has the potential to provide equipment information interact...

  8. LEP tunnel monorail

    CERN Multimedia

    1985-01-01

    A monorail from CERN's Large Electron Positron collider (LEP, for short). It ran around the 27km tunnel, transporting equipment and personnel. With its 27-kilometre circumference, LEP was the largest electron-positron accelerator ever built and ran from 1989 to 2000. During 11 years of research, LEP's experiments provided a detailed study of the electroweak interaction. Measurements performed at LEP also proved that there are three – and only three – generations of particles of matter. LEP was closed down on 2 November 2000 to make way for the construction of the Large Hadron Collider in the same tunnel.

  9. Use of a strontium-enriched calcium phosphate cement in accelerating the healing of soft-tissue tendon graft within the bone tunnel in a rabbit model of anterior cruciate ligament reconstruction.

    Science.gov (United States)

    Kuang, G M; Yau, W P; Lu, W W; Chiu, K Y

    2013-07-01

    We investigated whether strontium-enriched calcium phosphate cement (Sr-CPC)-treated soft-tissue tendon graft results in accelerated healing within the bone tunnel in reconstruction of the anterior cruciate ligament (ACL). A total of 30 single-bundle ACL reconstructions using tendo Achillis allograft were performed in 15 rabbits. The graft on the tested limb was treated with Sr-CPC, whereas that on the contralateral limb was untreated and served as a control. At timepoints three, six, nine, 12 and 24 weeks after surgery, three animals were killed for histological examination. At six weeks, the graft-bone interface in the control group was filled in with fibrovascular tissue. However, the gap in the Sr-CPC group had already been completely filled in with new bone, and there was evidence of the early formation of Sharpey fibres. At 24 weeks, remodelling into a normal ACL-bone-like insertion was found in the Sr-CPC group. Coating of Sr-CPC on soft tissue tendon allograft leads to accelerated graft healing within the bone tunnel in a rabbit model of ACL reconstruction using Achilles tendon allograft.

  10. Accelerating News Issue 3

    CERN Document Server

    Kahle, K; Tanguy, C; Wildner, E

    2012-01-01

    This summer saw CERN announce to a worldwide audience the discovery of a Higgs-like boson, so this issue takes a look at the machine behind the discovery, the LHC, as well as future plans for a possible Higgs factory in the form of LEP3. Looking ahead too are European strategies for particle physics and accelerator-based neutrino physics. In addition, taking stock of the work so far, HiLumi LHC and EuCARD showcase their latest results.

  11. CERN prepares for the LHC and beyond

    International Nuclear Information System (INIS)

    Rodgers, Peter

    2000-01-01

    The phrase ''needle in a haystack'' - the challenge of finding something small but important in the midst of a much, much larger object - is often used to describe CERN. It could be applied to searching for someone's office in one of the 373 buildings that occupy the laboratory's site at Meyrin, just outside Geneva on the Swiss rench border, but the real needle in the haystack at CERN is the Higgs boson. The Higgs is the particle that is responsible for other fundamental particles such as quarks and Z-bosons having mass. It is also the main reason that CERN is building a machine called the Large Hadron Collider (LHC) at a cost of SwFr 2bn. Particles predicted by supersymmetry the theory that every particle has a supersymmetric partner with the same mass and charge but different ''spin'' are the other top priority. There is a chance, albeit it a small one, that particle physicists might find the Higgs boson at CERN's large electron positron (LEP) collider before it is shut down to make way for the LHC. It all depends on how high the beam energy at LEP which currently stands at 103 GeV (103 X 109 electron volts) can be raised. ''1 GeV can matter at this stage'', says Luciano Maiani, the lab's director general. ''Exploring up to a mass of 114 GeV is optimistic but not impossible. Unless we see the Higgs, the current plan is for LEP to be dismantled after it stops running at the end of September. Installation of the LHC in the LEP tunnel will then start in October.'' The LHC will collide protons at a centre-of-mass energy of 14 TeV (14 000 GeV), and two massive general-purpose detectors ATLAS and CMS will search for evidence of the Higgs and supersymmetry. A third experiment called LHC-b will probe the difference between matter and antimatter, while the ALICE experiment will study the extreme state of matter known as the quark gluon plasma. Meanwhile, two massive teams of physicists are preparing the two detectors for the LHC. Both ATLAS and CMS have the same basic

  12. HL-LHC kicker magnet (MKI)

    CERN Multimedia

    Brice, Maximilien

    2018-01-01

    HL-LHC kicker magnet (MKI): last vacuum test, preparation for transport to LHC transfer line in underground tunnel.The LHC injection kicker systems (MKIs) generate fast field pulses to inject the clockwise rotating beam at Point 2 and the anti-clockwise rotating beam at Point 8: there are eight MKI magnets installed in total. Each MKI magnet contains a high purity alumina tube: if an MKI magnet is replaced this tube requires conditioning with LHC beam: until it is properly conditioned, there can be high vacuum pressure due to the beam. This high pressure can also cause electrical breakdowns in the MKI magnets. A special coating (Cr2O3) has been applied to the inside of the alumina tube of an upgraded MKI magnet – this is expected to greatly reduce the pressure rise with beam. In addition, HL-LHC beam would result in excessive heating of the MKI magnets: the upgraded design includes modifications that will reduce heating, and move the power deposition to parts that will be easier to cool. Experience during 2...

  13. The LHC Project Status and Prospects

    CERN Document Server

    Faugeras, Paul E

    2001-01-01

    The Large Hadron Collider (LHC), CERN's future major facility for high-energy physics, has entered into the construction and preparation for installation phases. After recalling briefly the main machine design choices and challenges, one will review the progress of civil works for the machine and experimental areas and the status of the main LHC components, which are presently series-built and for some of them procured in kind through world-wide collaborations. Report will also be given on the full-scale prototype of an elementary LHC lattice cell, called String 2, which is being commissioned and used for optimising the installation and testing procedures of the LHC. The size and duration of the LHC Project, its intrinsic complexity and the large number of world-wide collaborations involved require rather elaborate project management tools, which will be shortly described. Finally, following the extended running of the LEP and the delay for emptying of the machine tunnel, a new planning for project completion...

  14. Validation and Performance of the LHC Cryogenic System through Commissioning of the First Sector

    CERN Document Server

    Serio, L; Casas-Cubillos, J; Chakravarty, A; Claudet, S; Gicquel, F; Gomes, P; Kumar, M; Kush, PK; Millet, F; Perin, A; Rabehl, R; Singh, MR; Soubiran, M; Tavian, L

    2008-01-01

    The cryogenic system [1] for the Large Hadron Collider accelerator is presently in its final phase of commissioning at nominal operating conditions. The refrigeration capacity for the LHC is produced using eight large cryogenic plants and eight 1.8 K refrigeration units installed on five cryogenic islands. Machine cryogenic equipment is installed in a 26.7-km circumference ring deep underground tunnel and are maintained at their nominal operating conditions via a distribution system consisting of transfer lines, cold interconnection boxes at each cryogenic island and a cryogenic distribution line. The functional analysis of the whole system during all operating conditions was established and validated during the first sector commissioning in order to maximize the system availability. Analysis, operating modes, main failure scenarios, results and performance of the cryogenic system are presented.

  15. LHC opening delayed, operating schedule extended

    CERN Multimedia

    2009-01-01

    "The Large Hadron Collider (LHC) will reportedly reopen in October rather than this summer [...]. The $ 6.5 billion particle accelerator has 1'232 superconducting dipole magnets out of a total of more than 1'700 large magnets" (0.5 page)

  16. LHC Availability 2017: Standard Proton Physics

    CERN Document Server

    Todd, Benjamin; Apollonio, Andrea; Walsh, David John; CERN. Geneva. ATS Department

    2017-01-01

    This document summarises the LHC machine availability for the period from restart to the end of standard proton physics in 2017. This covers the whole standard proton physics production period. This note has been produced and ratified by the Availability Working Group which has complied fault information for the period in question using the Accelerator Fault Tracker.

  17. Safe LHC beam commissioning

    International Nuclear Information System (INIS)

    Uythoven, J.; Schmidt, R.

    2007-01-01

    Due to the large amount of energy stored in magnets and beams, safety operation of the LHC is essential. The commissioning of the LHC machine protection system will be an integral part of the general LHC commissioning program. A brief overview of the LHC Machine Protection System will be given, identifying the main components: the Beam Interlock System, the Beam Dumping System, the Collimation System, the Beam Loss Monitoring System and the Quench Protection System. An outline is given of the commissioning strategy of these systems during the different commissioning phases of the LHC: without beam, injection and the different phases with stored beam depending on beam intensity and energy. (author)

  18. LHC? Of course we’ve heard of the LHC!

    CERN Multimedia

    2009-01-01

    Well, more or less. After its first outing in Meyrin (see last Bulletin issue), our street poll hits the streets of Divonne-les-Bains and the corridors of the University of Geneva. While many have heard of the LHC, the raison d’être of this "scientific whatsit" often remains a mystery.On first questioning, the "man-in-the-street" always pleads ignorance. "Lausanne Hockey Club?" The acronym LHC is not yet imprinted on people’s minds. "Erm, Left-Handed thingamajig?" But as soon as we mention the word "CERN", the accelerator pops straight into people’s minds. Variously referred to as "the circle" or "the ring", it makes you wonder whether people would have been so aware of the LHC if it had been shaped like a square. Size is another thing people remember: "It’s the world’s biggest. Up to now…" As for its purpose, well that’s another kettle of fish. &...

  19. LHC Report: Beams are back in the LHC

    CERN Multimedia

    CERN Bulletin

    2011-01-01

    The LHC has shaken itself awake after the winter break, and, as the snow melts on the lower slopes, the temperature in the magnets has dropped to a chilly 1.9 K once more.   Following the cool-down, the last few weeks have seen an intense few tests of the magnets, power supplies and associated protection systems. These tests, referred to as hardware commissioning, have been completed in record time. At the same time the other accelerator systems have been put through the preparatory machine checkout. In parallel, the injectors (LINAC2, Booster, PS and SPS) have also come out of the technical stop in order to prepare to deliver beam to the LHC very early in the season. Of particular note here was the remarkably seamless transition to POPS, the PS's new main power supply system. All this work culminated in the LHC taking beam again for the first time in 2011 on Saturday, 19 February. The careful preparation paid off, with circulating beams being rapidly re-established. There then followed a programme ...

  20. Accelerators at school

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    Latest subject covered by the CERN Accelerator School was 'Applied Geodesy of Particle Accelerators', which attracted an impressive number of outside participants to CERN for a week in April. Since the forerunners of today's particle accelerators were demonstrated over 50 years ago, the positioning of accelerator components has progressed from the laboratory bench-top to tunnels tens of kilometres long. Despite this phenomenal growth in size, sub-millimetre accuracy is still required

  1. Accelerators at school

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    1986-06-15

    Latest subject covered by the CERN Accelerator School was 'Applied Geodesy of Particle Accelerators', which attracted an impressive number of outside participants to CERN for a week in April. Since the forerunners of today's particle accelerators were demonstrated over 50 years ago, the positioning of accelerator components has progressed from the laboratory bench-top to tunnels tens of kilometres long. Despite this phenomenal growth in size, sub-millimetre accuracy is still required.

  2. High Luminosity LHC: challenges and plans

    Science.gov (United States)

    Arduini, G.; Barranco, J.; Bertarelli, A.; Biancacci, N.; Bruce, R.; Brüning, O.; Buffat, X.; Cai, Y.; Carver, L. R.; Fartoukh, S.; Giovannozzi, M.; Iadarola, G.; Li, K.; Lechner, A.; Medina Medrano, L.; Métral, E.; Nosochkov, Y.; Papaphilippou, Y.; Pellegrini, D.; Pieloni, T.; Qiang, J.; Redaelli, S.; Romano, A.; Rossi, L.; Rumolo, G.; Salvant, B.; Schenk, M.; Tambasco, C.; Tomás, R.; Valishev, S.; Van der Veken, F. F.

    2016-12-01

    The Large Hadron Collider (LHC) is one of the largest scientific instruments ever built. Since opening up a new energy frontier for exploration in 2010, it has gathered a global user community working in fundamental particle physics and the physics of hadronic matter at extreme temperature and density. To sustain and extend its discovery potential, the LHC will undergo a major upgrade in the 2020s. This will increase its rate of collisions by a factor of five beyond the original design value and the integrated luminosity by a factor ten. The new configuration, known as High Luminosity LHC (HL-LHC), will rely on a number of key innovations that push accelerator technology beyond its present limits. Among these are cutting-edge 11-12 T superconducting magnets, including Nb3Sn-based magnets never used in accelerators before, compact superconducting cavities for longitudinal beam rotation, new technology and physical processes for beam collimation. The dynamics of the HL-LHC beams will be also particularly challenging and this aspect is the main focus of this paper.

  3. LHC Highlights, from dream to reality

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    The idea of the Large Hadron Collider (LHC) was born in the early 1980s. Although LEP (CERN’s previous large accelerator) was still under construction at that time, scientists were already starting to think about re-using the 27-kilometre ring for an even more powerful machine. Turning this ambitious scientific plan into reality proved to be an immensely complex task. Civil engineering work, state-of-the-art technologies, a new approach to data storage and analysis: many people worked hard for many years to accomplish all this.   Here are some of the highlights: 1984. A symposium organized in Lausanne, Switzerland, is the official starting point for the LHC. LHC prototype of the two beam pipes (1992). 1989. The first embryonic collaborations begin. 1992. A meeting in Evian, France, marks the beginning of the LHC experiments. 1994. The CERN Council approves the construction of the LHC accelerator. 1995. Japan becomes an Observer of CERN and announces a financial contribution to ...

  4. High Luminosity LHC: Challenges and plans

    International Nuclear Information System (INIS)

    Arduini, G.; Barranco, J.; Bertarelli, A.; Biancacci, N.; Bruce, R.

    2016-01-01

    The Large Hadron Collider (LHC) is one of the largest scientific instruments ever built. Since opening up a new energy frontier for exploration in 2010, it has gathered a global user community working in fundamental particle physics and the physics of hadronic matter at extreme temperature and density. To sustain and extend its discovery potential, the LHC will undergo a major upgrade in the 2020s. This will increase its rate of collisions by a factor of five beyond the original design value and the integrated luminosity by a factor ten. The new configuration, known as High Luminosity LHC (HL-LHC), will rely on a number of key innovations that push accelerator technology beyond its present limits. Among these are cutting-edge 11–12 T superconducting magnets, including Nb 3 Sn-based magnets never used in accelerators before, compact superconducting cavities for longitudinal beam rotation, new technology and physical processes for beam collimation. As a result, the dynamics of the HL-LHC beams will be also particularly challenging and this aspect is the main focus of this paper.

  5. Press Conference: LHC Restart, Season 2

    CERN Multimedia

    CERN. Geneva

    2015-01-01

    PRESS BRIEFING ON THE LARGE HADRON COLLIDER (LHC) RE-START, SEASON 2 AT CERN, GLOBE OF SCIENCE AND INNOVATION Where :   http://cern.ch/directions   at the Globe of Science and Innovation When : Thursday, 12 March from 2.30 to 3.30pm - Open seating as from 2.15pm Speakers : CERN’s Director General, Rolf Heuer and Director of Accelerators, Frédérick Bordry, and representatives of the LHC experiments Webcast : https://webcast.web.cern.ch/webcast/ Dear Journalists, CERN is pleased to invite you to the above press briefing which will take place on Thursday 12 March, in the Globe of Science and Innovation, 1st floor, from 2.30 to 3.30pm. The Large Hadron Collider (LHC) is ready to start up for its second three-year run. The 27km LHC is the largest and most powerful particle accelerator in the world operating at a temperature of -217 degrees Centigrade and powered to a current of 11,000 amps. Run 2 of the LHC follows a two-year technical s...

  6. Radiation Levels around the LHC

    CERN Document Server

    Mala, P; Calviani, M; Nordt, A

    2013-01-01

    This work discuss on the radiation levels measured around the LHC machine during the 2012 operational year. The doses and particle fluences are measured primarily by RadMon detectors – about 300 RadMons are installed around the accelerator – and by thermoluminescent detectors. In addition, BLMs, IG5/PMI ionisation chambers as well as FGCs can be used for corresponding cumulated dose evaluations. The probability of SEE depends directly on the high-energy hadron (HEH) fluence, so this is the main parameter that is calculated based on RadMons counts.

  7. Luminosity Optimization for a Higher-Energy LHC

    CERN Document Server

    Dominguez, O

    2011-01-01

    A Higher-Energy Large Hadron Collider (HE-LHC) is an option to further push the energy frontier of particle physics beyond the present LHC. A beam energy of 16.5 TeV would require 20 T dipole magnets in the existing LHC tunnel, which should be compared with 7 TeV and 8.33 T for the nominal LHC. Since the synchrotron radiation power increases with the fourth power of the energy, radiation damping becomes significant for the HE-LHC. It calls for transverse and longitudinal emittance control vis-a-vis beam-beam interaction and Landau damping. The heat load from synchrotron radiation, gas scattering, and electron cloud also increases with respect to the LHC. In this paper we discuss the proposed HE-LHC beam parameters; the time evolution of luminosity, beam-beam tune shifts, and emittances during an HE-LHC store; the expected heat load; and luminosity optimization schemes for both round and flat beams.

  8. LHC gets the ball rolling

    CERN Multimedia

    2007-01-01

    A technique involving a small ball with a transmitter embedded inside it has been successfully tested in Sector 7-8. The ball is sent through the LHC beam pipes to check the LHC interconnections. The multidisciplinary team responsible for the RF ball project to check the interconnections. From left to right: Rhodri Jones (AB/BI), Eva Calvo (AB/BI), Francesco Bertinelli (AT/MCS), Sonia Bartolome Jimenez (TS/IC), Sylvain Weisz (TS/IC), Paul Cruikshank (AT/VAC), Willemjan Maan (AT/VAC), Alain Poncet (AT/MCS), Marek Gasior (AB/BI). During the tests the ball is inserted very carefully into the vacuum chamber.A game of ping-pong at the LHC? On 13 September a rather unusual test was carried out in Sector 7-8 of the accelerator. A ball just a bit smaller than a ping-pong ball was carefully introduced into one of the accelerator’s two vacuum pipes, where it travelled 800 metres in the space of a few mi...

  9. Switch on to the LHC!

    CERN Multimedia

    CERN Bulletin

    2010-01-01

    The LHC is preparing to collide beams at 3.5 TeV for the first time ever! Be part of the event and follow live what goes on at the world’s most powerful particle accelerator by connecting to LHC1. Hereafter we give you a key to understand the display as well as a typical event display from the ATLAS and CMS experiments. Click on the image to enlarge it 1. This is the energy of beams. 1 TeV=1000 GeV. The LHC set the energy world’s record of 3.48 TeV per beam, today, 19 March 2010. 2. Intensity of, respectively, B1 (blue) and B2 (red). 3. The information in these boxes can vary. Operators display the graphs that are relevant to the specific operation. 4. Most of the flags are set automatically. They provide a quick summary of the machine status. In order to have collisions the ‘Stable Beams’ flag must be set to green. 5. Here operators write down their messages to the experiments. Often, they write the ongoing activity, followed by the plan for the coming hou...

  10. The LHC on an envelope

    CERN Multimedia

    2007-01-01

    The series of envelopes featuring CERN issued this summer was a huge success. The French postal services of the Pays de Gex will shortly be launching the second set of pre-paid envelopes issued in collaboration with the Laboratory this year, this time highlighting the LHC. Five thousand envelopes describing the accelerator’s capabilities will go on sale on 12 November, and some of the packs will even contain a small sample of the cables from the heart of the LHC magnets. The sets of ten pre-paid envelopes will tell you everything about CERN’s flagship accelerator, from its astounding technical capabilities to its spin-offs in the fields of technology and human resources. Each envelope will feature a different attribute or spin-off of the LHC. People will be invited to consult CERN’s public website for more detailed explanations if they want to know more. The new envelopes will be available from five post offices in the Pays ...

  11. The LHC in an envelope

    CERN Multimedia

    2007-01-01

    The series of envelopes featuring CERN issued this summer was a huge success. The French postal services of the Pays de Gex will shortly be launching the second set of pre-paid envelopes issued in collaboration with the Laboratory this year, this time highlighting the LHC. Five thousand envelopes describing the accelerator’s capabilities will go on sale on 12 November, and some of the packs will even contain a small sample of the cables from the heart of the LHC magnets. The sets of ten pre-paid envelopes will tell you everything about CERN’s flagship accelerator, from its astounding technical capabilities to its spin-offs in the fields of technology and human resources. Each envelope will feature a different attribute or spin-off of the LHC. People will be invited to consult CERN’s public website for more detailed explanations if they want to know more. The new envelopes will be available from five post offices in the Pays de Gex (Ferney-Voltaire, Prévessin...

  12. An FMM-FFT accelerated integral equation solver for characterizing electromagnetic wave propagation in mine tunnels and galleries loaded with conductors

    KAUST Repository

    Yücel, Abdulkadir C.

    2014-07-01

    Reliable wireless communication and tracking systems in underground mines are of paramount importance to increase miners\\' productivity while monitoring the environmental conditions and increasing the effectiveness of rescue operations. Key to the design and optimization of such systems are electromagnetic (EM) simulation tools capable of analyzing wave propagation in electromagnetically large mine tunnels and galleries loaded with conducting cables (power, telephone) and mining equipment (trolleys, rails, carts), and potentially partially obstructed by debris from a cave-in. Current tools for simulating EM propagation in mine environments leverage (multi-) modal decompositions (Emslie et. al., IEEE Trans. Antennas Propag., 23, 192-205, 1975; Sun and Akyildiz, IEEE Trans. Commun., 58, 1758-1768, 2010), ray-tracing techniques (Zhang, IEEE Tran. Vehic. Tech., 5, 1308-1314, 2003), or full wave methods. Modal approaches and ray-tracing techniques cannot accurately account for the presence of conductors, intricate details of transmitters/receivers, wall roughness, or unstructured debris from a cave-in. Classical full-wave methods do not suffer from such restrictions. However, they require prohibitively large computational resources when applied to the analysis of electromagnetically large tunnels loaded with conductors. Recently, an efficient hybrid method of moment and transmission line solver has been developed to analyze the EM wave propagation inside tunnels loaded with conductors (Brocker et. al., in Proc IEEE AP-S Symp, pp.1,2, 2012). However, the applicability of the solver is limited to the characterization of EM wave propagation at medium frequency band.

  13. The latest from the LHC

    CERN Multimedia

    2009-01-01

    View of the LHC tunnel after the repairs.Three weeks ago vacuum leaks occurred in both Sector 8-1 and 2-3 (See previous update). While the cause and exact locations of the leaks are still unknown, it is suspected that they occurred in both cases from a flexible hose in the liquid helium transport circuits, which vented helium into the vacuum insulation. In Sector 8-1 the leaks occurred while it was being maintained at 80 K in order to perform the resistance measurements on the copper part of the superconducting busbars. Less than 24 hours later a similar leak occurred in Sector 2-3 while it was being warmed from superconducting temperatures to 80 K to perform the busbar resistance measurement. Both leaks happened where the final magnet of the sector (known as Q7) joins the electrical feedbox (called the DFBA). The end vacuum subsectors – a 200-metre stretch of the LHC sealed off by vacuum barriers – will be warmed to room temp...

  14. Electron cloud buildup studies for the LHC

    CERN Document Server

    AUTHOR|(CDS)2160803; Boine-Frankenheim, Oliver

    Electron clouds can develop in accelerators operating with positively charged particles. The con- sequences of e-cloud related effects are very important for the operation of the Large Hadron Collider (LHC) at CERN, and for the design of future accelerators including the LHC luminosity upgrade (HL-LHC). High electron densities are generated by an interaction between the beam and the confining chamber. Primary electrons, that can be generated through various mecha- nisms, are accelerated by the beam and impinge on the chamber walls, thereby extracting more electrons from the material. Furthermore they also deposit their kinetic energy in the process, which has to be compensated by the cooling system. Especially in cryogenic environments, as it is the case for a large part of the LHC, high heat loads can pose a serious problem. In order to improve the understanding of the electron cloud, simulation studies are performed with the code PyECLOUD, developed at CERN. The work of the first half of the project is desc...

  15. Experience with the Quality Assurance of the Superconducting Electrical Circuits of the LHC Machine

    CERN Document Server

    Bozzini, D; Kotarba, A; Mess, Karl Hubert; Olek, S; Russenschuck, Stephan

    2006-01-01

    The coherence between the powering reference database for the LHC and the Electrical Quality Assurance (ELQA) is guaranteed on the procedural level. However, a challenge remains the coherence between the database, the magnet test and assembly procedures, and the connection of all superconducting circuits in the LHC machine. In this paper, the methods, tooling, and procedures for the ELQA during the assembly phase of the LHC will be presented in view of the practical experience gained in the LHC tunnel. Some examples of detected polarity errors and electrical non-conformities will be presented. The parameters measured at ambient temperature, such as the dielectric insulation of circuits, will be discussed.

  16. High-precision performance testing of the LHC power converters

    CERN Document Server

    Bastos, M; Dreesen, P; Fernqvist, G; Fournier, O; Hudson, G

    2007-01-01

    The magnet power converters for LHC were procured in three parts, power part, current transducers and control electronics, to enable a maximum of industrial participation in the manufacturing and still guarantee the very high precision (a few parts in 10-6) required by LHC. One consequence of this approach was several stages of system tests: factory reception tests, CERN reception tests, integration tests , short-circuit tests and commissioning on the final load in the LHC tunnel. The majority of the power converters for LHC have now been delivered, integrated into complete converter and high-precision performance testing is well advanced. This paper presents the techniques used for high-precision testing and the results obtained.

  17. Acceleration of the LHC commissioning tests

    CERN Multimedia

    2008-01-01

    The quadrupole and main dipole circuits have been powered up to 10,200 amps in Sector 4-5. Sector 5-6 is currently being cooled and will be the next to undergo electrical tests, which will be stepped up over the next few weeks.

  18. The LHC enters a new phase

    CERN Document Server

    CERN Bulletin

    2010-01-01

    After achieving the world record energy of 1.18 TeV per proton beam last November, the LHC is now preparing for higher energy and luminosity.   The teams are working in the tunnel to improve the electrical reliability of the magnet protection system.   Before the 2009 running period began, all the necessary preparations to run the LHC at the collision energy of 1.18 TeV per beam had been carried out. The goal of the technical stop, which will end mid-February, is to prepare the machine for running at 3.5 TeV per beam. In order to achieve that, a current as high as 6 kAmps will have to flow into the LHC magnets. The main work is taking place on the new quench protection system (nQPS) where teams are improving the electrical reliability of the connection between the Instrumentation Feedthrough Systems (IFS) on the magnets and the nQPS equipment. There are around 500 of these connectors for each of the eight sectors in the LHC that need to be repaired. These operations are necessary to en...

  19. Dipoles for High-Energy LHC

    CERN Document Server

    Todesco, E; De Rijk, G; Rossi, L

    2014-01-01

    For the High Energy LHC, a study of a 33 TeV center of mass collider in the LHC tunnel, main dipoles of 20 T operational field are needed. In this paper we first review the conceptual design based on block coil proposed in the Malta workshop, addressing the issues related to coil fabrication and assembly. We then propose successive simplifications of this design, associating a cost estimate of the conductor. We then analyse a block layout for a 15 T magnet. Finally, we consider two layouts based on the D20 and HD2 short models built by LBL. A first analysis of the aspects related to protection of these challenging magnets is given.

  20. QCD-instantons at LHC. Theoretical aspects

    International Nuclear Information System (INIS)

    Petermann, M.

    2007-06-01

    Instantons are nonperturbative, topologically nontrivial field configurations, which occur in every nonabelian gauge theory. They can be understood as tunneling processes between topologically distinct vacua. Although being a basic theoretical aspect of the Standard Model, a direct experimental verification of instanton processes is still lacking. In this thesis the general discovery potential for QCD-instantons at the LHC is studied in detail by means of instanton perturbation theory. In this context the close correspondence between the leading instanton induced processes at HERA and at LHC becomes important. Essential aspects and differences to deep inelastic scattering can already be revealed by studying the simplest process. Based on these results inclusive cross sections are calculated including the emission of final state gluons. Compared to deep inelastic scattering, a large enhancement of the cross section is found. (orig.)

  1. The physics behind LHC

    CERN Multimedia

    CERN. Geneva

    2006-01-01

    What do physicists want to discover with experiments at the LHC? What is the Higgs boson? What are the new phenomena that could be observed at the LHC?I will try to answer these questions using language accessible also to non-experts. Organiser(s): L. Alvarez-Gaume / PH-THNote: * Tea & coffee will be served at 16:00.

  2. The LHC Collimator Controls Architecture - Design and beam tests

    CERN Document Server

    Redaelli, S; Gander, P; Jonker, M; Lamont, M; Losito, R; Masi, A; Sobczak, M

    2007-01-01

    The LHC collimation system will require simultaneous management by the LHC control system of more than 500 jaw positioning mechanisms in order to ensure the required beam cleaning and machine protection performance in all machine phases, from injection at 450 GeV to collision at 7 TeV. Each jaw positionis a critical parameter for the machine safety. In this paper, the architecture of the LHC collimator controls is presented. The basic design to face the accurate control of the LHC collimators and the interfaces to the other components of LHC Software Application and control infrastructures are described. The full controls system has been tested in a real accelerator environment in the CERN SPS during beam tests with a full scale collimator prototype. The results and the lessons learned are presented.

  3. Fast Beam Current Change Monitor for the LHC

    CERN Document Server

    Kral, Jan

    Stringent demands on the LHC safety and protection systems require improved methods of detecting fast beam losses. The Fast Beam Current Transformer (FBCT) is a measurement instrument, providing information about bunch-to-bunch intensity of the accelerated beam. This thesis describes the development of a new protection system based on the FBCT signal measurements. This system, the Fast Beam Current Change Monitor (FBCCM), measures the FBCT signal in a narrow frequency band and computes time derivation of the beam signal magnitude. This derivation is proportional to the beam losses. When the losses exceed a certain level, the FBCCM requests a beam dump in order to protect the LHC. The LHC protection will be ensured by four FBCCMs which will be installed into the LHC in July 2014. Six FBCCMs have been already constructed and their characteristics were measured with satisfactory results. The FBCCMs were tested by a laboratory simulation of the real LHC environment.

  4. The LHC is safe

    CERN Document Server

    CERN. Geneva; Alvarez-Gaumé, Luís

    2008-01-01

    Concerns have been expressed from time to time about the safety of new high-energy colliders, and the LHC has been no exception. The LHC Safety Assessment Group (LSAG)(*) was asked last year by the CERN management to review previous LHC safety analyses in light of additional experimental results and theoretical understanding. LSAG confirms, updates and extends previous conclusions that there is no basis for any conceivable threat from the LHC. Indeed, recent theoretical and experimental developments reinforce this conclusion. In this Colloquium, the basic arguments presented by LSAG will be reviewed. Cosmic rays of much higher effective centre-of-mass energies have been bombarding the Earth and other astronomical objects for billions of years, and their continued existence shows that the Earth faces no dangers from exotic objects such as hypothetical microscopic black holes that might be produced by the LHC - as discussed in a detailed paper by Giddings and Mangano(**). Measurements of strange particle produc...

  5. Particles are back in the LHC

    CERN Multimedia

    CERN Bulletin

    2016-01-01

    The LHC has introduced beam for the first time since the year-end technical stop began in December 2015.   CERN Management and LHC operators applaud as the first beam circulates in the LHC, on Friday 25 March.   On Friday, the LHC opened its doors to allow particles to travel around the ring for the first time since the year-end technical stop (YETS) began in December 2015. At 10:30 a.m., a first bunch was circulating and by midday the beam was circulating in both directions. Progress over the weekend has been good and low intensity beam has already been taken to 6.5 TeV and through the squeeze. Last week, the LHC underwent the final phase of preparation before beam -known as the machine checkout. During this phase all the systems of the LHC are put through their paces without beam. A key part of the process is driving the magnetic circuits, radiofrequency accelerating cavities, collimators, transverse dampers etc. repeatedly through the nominal LHC cycle. A fu...

  6. The first LHC sector is fully interconnected

    CERN Multimedia

    2006-01-01

    Sector 7-8 is the first sector of the LHC to become fully operational. All the magnets, cryogenic line, vacuum chambers and services are interconnected. The cool down of this sector can soon commence. LHC project leader Lyn Evans, the teams from CERN's AT/MCS, AT/VAC and AT/MEL groups, and the members of the IEG consortium celebrate the completion of the first LHC sector. The 10th of November was a red letter day for the LHC accelerator teams, marking the completion of the first sector of the machine. The magnets of sector 7-8, together with the cryogenic line, the vacuum chambers and the distribution feedboxes (DFBs) are now all completely interconnected. Sector 7-8 has thus been closed and is the first LHC sector to become operational. The interconnection work required several thousand electrical, cryogenic and insulating connections to be made on the 210 interfaces between the magnets in the arc, the 30 interfaces between the special magnets and the interfaces with the cryogenic line. 'This represent...

  7. LHC Power Converters: A Precision Game

    CERN Multimedia

    2001-01-01

    The LHC test-bed, String 2, is close to commissioning and one important element to get a first chance to prove what it can do is the power converter system. In String 2 there are 16 converters, in the full LHC there will be almost 1800. This article takes a look at what is so special about the power converters for the LHC. The 13 000 Amps power converters with the watercooled cables going to the String 2 feedboxes. The LHC's superconducting magnets will be the pinnacle of high technology. But to work, they'll need the help of high-precision power converters to supply them with extremely stable DC current. Perfection will be the name of the game, with an accuracy of just 1-2 parts per million (ppm) required. LEP, for the sake of comparison, could live with 10-20 ppm. The LHC's power converters will be very different from those of LEP or the SPS since the new accelerator's magnets are mostly superconducting. That means that they require much higher currents at a lower voltage since superconductors have no re...

  8. The CERN accelerator complex

    CERN Multimedia

    Mobs, Esma Anais

    2016-01-01

    The LHC is the last ring (dark blue line) in a complex chain of particle accelerators. The smaller machines are used in a chain to help boost the particles to their final energies and provide beams to a whole set of smaller experiments, which also aim to uncover the mysteries of the Universe.

  9. The CERN accelerator complex

    CERN Multimedia

    Christiane Lefèvre

    2008-01-01

    The LHC is the last ring (dark grey line) in a complex chain of particle accelerators. The smaller machines are used in a chain to help boost the particles to their final energies and provide beams to a whole set of smaller experiments, which also aim to uncover the mysteries of the Universe.

  10. Accelerating News Issue 5

    CERN Document Server

    Szeberenyi, A

    2013-01-01

    In this spring issue, we look at developments towards higher luminosity and higher energy colliders. We report on the technology developed for the remote powering of the LHC magnets and studies of diagnostics based on higher order mode port signals. We also inform you about the main outcome of the TIARA survey on market needs for accelerator scientists.

  11. The CERN accelerator complex

    CERN Multimedia

    Haffner, Julie

    2013-01-01

    The LHC is the last ring (dark grey line) in a complex chain of particle accelerators. The smaller machines are used in a chain to help boost the particles to their final energies and provide beams to a whole set of smaller experiments, which also aim to uncover the mysteries of the Universe.

  12. The Interconnections of the LHC Cryomagnets

    CERN Document Server

    Jacquemod, A; Skoczen, Blazej; Tock, J P

    2001-01-01

    The main components of the LHC, the next world-class facility in high-energy physics, are the twin-aperture high-field superconducting cryomagnets to be installed in the existing 26.7-km long tunnel. After installation and alignment, the cryomagnets have to be interconnected. The interconnections must ensure the continuity of several functions: vacuum enclosures, beam pipe image currents (RF contacts), cryogenic circuits, electrical power supply, and thermal insulation. In the machine, about 1700 interconnections between cryomagnets are necessary. The interconnections constitute a unique system that is nearly entirely assembled in the tunnel. For each of them, various operations must be done: TIG welding of cryogenic channels (~ 50 000 welds), induction soldering of main superconducting cables (~ 10 000 joints), ultrasonic welding of auxiliary superconducting cables (~ 20 000 welds), mechanical assembly of various elements, and installation of the multi-layer insulation (~ 200 000 m2). Defective junctions cou...

  13. The LHC cryogenic operation for first collisions and physics run

    CERN Document Server

    Brodzinski, K; Benda, V; Bremer, J; Casas-Cubillos, J; Claudet, S; Delikaris, D; Ferlin, G; Fernandez Penacoba, G; Perin, A; Pirotte, O; Soubiran, M; Tavian, L; van Weelderen, R; Wagner, U

    2011-01-01

    The Large Hadron Collider (LHC) cryogenic system was progressively and successfully run for the LHC accelerator operation period starting from autumn 2009. The paper recalls the cryogenic system architecture and main operation principles. The system stability during magnets powering and availability periods for high energy beams with first collisions at 3.5 TeV are presented. Treatment of typical problems, weak points of the system and foreseen future consolidations will be discussed.

  14. Mutual seismic interaction between tunnels and the surrounding granular soil

    Directory of Open Access Journals (Sweden)

    Mohamed Ahmed Abdel-Motaal

    2014-12-01

    Study results show that the maximum exerted straining actions in tunnel lining are directly proportional to the relative stiffness between tunnel and surrounding soil (lining thickness and soil shear modulus. Moreover, it is highly affected by the peak ground acceleration and the tunnel location (embedment depth. A comprehensive study is performed to show the effect of tunnel thickness and tunnel diameter on both the induced bending moment and lining deformation. In general, it is concluded that seismic analysis should be considered in regions subjected to peak ground acceleration greater than 0.15g.

  15. Commissioning of the cryogenics of the LHC long straight sections

    International Nuclear Information System (INIS)

    Perin, A.; Casas-Cubillos, J.; Claudet, S.; Darve, C.; Ferlin, G.; Millet, F.; Parente, C.; Rabehl, R.; Soubiran, M.; van Weelderen, R.; Wagner, U.

    2010-01-01

    The LHC is made of eight circular arcs interspaced with eight Long Straight Sections (LSS). Most powering interfaces to the LHC are located in these sections where the particle beams are focused and shaped for collision, cleaning and acceleration. The LSSs are constituted of several unique cryogenic devices and systems like electrical feed-boxes, standalone superconducting magnets, superconducting links, RF cavities and final focusing superconducting magnets. This paper presents the cryogenic commissioning and the main results obtained during the first operation of the LHC Long Straight Sections.

  16. Measurements at LHC and their relevance for cosmic ray physics

    CERN Multimedia

    CERN. Geneva

    2016-01-01

    Many LHC measurements are already used to improve hadronic interaction models used in cosmic ray analyses. This already had a positive effect on the model dependence of crucial data analyses. Some of the data and the model tuning is reviewed. However, the LHC still has a lot more potential to provide crucial information. Since the start of Run2 the highest accelerator beam energies are reached and no further increase can be expected for a long time. First data of Run2 are published and the fundamental performance of cosmic ray hadronic interaction models can be scrutinized. The relevance of LHC data in general for cosmic ray data analyses is demonstrated.

  17. Commissioning of the Cryogenics of the LHC Long Straight Sections

    CERN Document Server

    Perin, A; Claudet, S; Darve, C; Ferlin, G; Millet, F; Parente, C; Rabehl, R; Soubiran, M; van Weelderen, R; Wagner, U

    2010-01-01

    The LHC is made of eight circular arcs interspaced with eight Long Straight Sections (LSS). Most powering interfaces to the LHC are located in these sections where the particle beams are focused and shaped for collision, cleaning and acceleration. The LSSs are constituted of several unique cryogenic devices and systems like electrical feed-boxes, standalone superconducting magnets, superconducting links, RF cavities and final focusing superconducting magnets. This paper presents the cryogenic commissioning and the main results obtained during the first operation of the LHC Long Straight Sections.

  18. The Commissioning of the LHC Technical Systems

    CERN Document Server

    Saban, R; Baggiolini, V; Ballarino, A; Barbero-Soto, E; Bellesia, B; Bordry, Frederick; Bozzini, D; Casas-Lino, M-P; Chareyre, V; Claudet, S; Coelingh, G-J; Dahlerup-Petersen, K; Denz, R; Fehér, S; Flora, R; Gruwé, M; Kain, V; Kirby, G; Koratzinos, M; Lauckner, R; Le Naour, S; Mess, K-H; Millet, F; Montabonnet, V; Nisbet, D; Perea-Solano, B; Pojer, M; Principe, R; Rabehl, R; Rijllart, A; Redaelli, S; Rodríguez-Mateos, F; Schmidt, R; Serio, L; Siemko, A; Solfaroli-Camillocci, M; Thiesen, H; Venturini, W; Vergara-Fernandez, A; Verweij, A; Zerlauth, M

    2007-01-01

    The LHC is an accelerator with unprecedented complexity where the energy stored in magnets and the beams exceeds other accelerators by one-to-two orders of magnitude. To ensure a safe and efficient machine start-up without being plagued by technical problems, a phase of "hardware commissioning" was introduced: a thorough commissioning of technical systems without beam. This activity started in June 2005 with the commissioning of individual systems, followed by operating a full sector, one eighth of the machine; the commissioning is expected to last until spring 2008 when commissioning with beam will start. The LHC architecture allows the commissioning of each of the eight sectors independently from the others, before the installation of other sectors is complete. An important effort went into the definition of the programme and the organization of the coordination in the field, as well as in the preparation of the tools to record and analyze test results. This paper discusses the experience with this approach...

  19. LHC Report: LHC hit the target!

    CERN Multimedia

    Enrico Bravin for the LHC team

    2016-01-01

    Last week, the accumulated integrated luminosity reached the target value for 2016 of 25 fb-1 in both ATLAS and CMS.   The integrated luminosity delivered to ATLAS and CMS reached (and already passed!) 25 fb-1– the target for the whole year! Tuesday, 30 August was just a regular day for the 2016 LHC run. However,  on that day, the integrated luminosity delivered to ATLAS and CMS reached 25 fb-1 – the target for the whole year! How did we get here? A large group of committed scientists and technical experts work behind the scenes at the LHC, ready to adapt to the quirks of this truly impressive machine. After the push to produce as many proton-proton collisions as possible before the summer conferences, several new ideas and production techniques (such as Bunch Compression Multiple Splitting, BCMS) have been incorporated in the operation of LHC in order to boost its performance even further. Thanks to these improvements, the LHC was routinely operated with peak luminos...

  20. The LHC babies

    CERN Multimedia

    Laëtitia Pedroso

    2011-01-01

    With the machine restart and first collisions at 3.5 TeV, 2009 and 2010 were two action-packed years at the LHC. The events were a real media success, but one important result that remained well hidden was the ten births in the LHC team over the same period. The mothers – engineers, cryogenics experts and administrative assistants working for the LHC – confirm that it is possible to maintain a reasonable work-life balance. Two of them tell us more…   Verena Kain (left) and Reyes Alemany (right) in the CERN Control Centre. With the LHC running around the clock, LHC operations engineers have high-pressure jobs with unsociable working hours. These past two years, which will undoubtedly go down in the annals of CERN history, the LHC team had their work cut out, but despite their high-octane professional lives, several female members of the team took up no less of a challenge in their private lives, creating a mini-baby-boom by which the LHC start-up will also be remembe...

  1. Transport and installation of the LHC cryo-magnets

    CERN Document Server

    Artoos, K; Capatina, O; Chevalley, JM; Foraz, K; Guinchard, M; Hauviller, Claude; Kershaw, K; Prodon, S; Rühl, Ingo; Trinquart, G; Weisz, S; Ponsot, P

    2007-01-01

    Eleven years have passed between the beginning of transport and handling studies in 1996 and the completion of the LHC cryo-magnets installation in 2007. More than 1700 heavy, long and fragile cryo-magnets had to be transported and installed in the 27 km long LHC tunnel with very restricted available space. The size and complexity of the project involved challenges in the field of equipment design and manufacturing, maintenance, training and follow-up of operators and logistics. The paper presents the milestones, problems to be overcome and lessons learned during this project.

  2. CERN reacts to increased costs to completion of the LHC

    CERN Multimedia

    2002-01-01

    Aspects of LHC construction. The CERN Council, where the representatives of the 20 Member States of the Organization decide on scientific programmes and financial resources, held its 120th session on 14 December under the chairmanship of Prof. Maurice Bourquin (CH). CERN adjusts to the LHC Director-General, Luciano Maiani, stressed that CERN was now fully engaged in the LHC and outlined the first moves to react to the increased cost to completion of the LHC. The new accelerator is an extremely complex, high-tech project which CERN is building under very severe conditions. However, the technical challenges are solved and industrial production of accelerator elements, and installation are starting. Professor Maiani said that 2001 had been a very hard but decisive year for CERN. An important milestone had been passed during this meeting with the approval of the LHC dipole magnets contract, the last major contract for the accelerator. The new costs to completion of the LHC project are now clear. A first propos...

  3. Highlights of LHC experiments – Part I

    CERN Document Server

    AUTHOR|(INSPIRE)INSPIRE-00072301; The ATLAS collaboration

    2017-01-01

    The superb performance of the LHC accelerator in 2016, in both live time and peak luminosity, has provided a large data sample of collisions at 13 TeV. Excellent performances of the ATLAS and LHCb detectors, together with highly performant offline and analysis systems, mean that a wealth of results are already available from 13 TeV data. Selected highlights are reported here.

  4. Cold dark matter and the LHC

    International Nuclear Information System (INIS)

    Battaglia, Marco; Hinchliffe, Ian; Tovey, Daniel

    2004-01-01

    The recent determination of the dark matter density in the universe by the WMAP satellite has brought new attention to the interplay of results from particle physics experiments at accelerators and from cosmology. In this paper we discuss the prospects for finding direct evidence for a candidate dark matter particle at the LHC and the measurements which would be crucial for testing its compatibility with the cosmology data. (topical review)

  5. The LHC string2 supervision system

    CERN Document Server

    Mayya, Y S; Sicard, Claude Henri

    2002-01-01

    This paper describes the implementation of the supervision system for the LHC Prototype Full-Cell also known as String 2. The supervision application is based on a commercial package targeted to industrial controls, but because of the complexity and the specifics of such a system, integration with custom components is necessary in order to merge the industrial requirements with the specificity of the accelerator controls.

  6. Conference: STANDARD MODEL @ LHC

    CERN Multimedia

    2012-01-01

    HCØ institute Universitetsparken 5 DK-2100 Copenhagen Ø Denmark Room: Auditorium 2 STANDARD MODEL @ LHC Niels Bohr International Academy and Discovery Center 10-13 April 2012 This four day meeting will bring together both experimental and theoretical aspects of Standard Model phenomenology at the LHC. The very latest results from the LHC experiments will be under discussion. Topics covered will be split into the following categories:     * QCD (Hard,Soft & PDFs)     * Vector Boson production     * Higgs searches     * Top Quark Physics     * Flavour physics

  7. The Lhc beam commissioning

    International Nuclear Information System (INIS)

    Redarelli, S.; Bailey, R.

    2008-01-01

    The plans for the Lhc proton beam commissioning are presented. A staged commissioning approach is proposed to satisfy the request of the Lhc experiments while minimizing the machine complexity in early commissioning phases. Machine protection and collimation aspects will be tackled progressively as the performance will be pushed to higher beam intensities. The key parameters are the number of bunches, k b , the proton intensity pe bunch, N, and the β in the various interaction points. All together these parameters determine the total beam power and the complexity of the machine. We will present the proposed trade off between the evolution of these parameters and the Lhc luminosity performance.

  8. The Latest from the LHC

    CERN Multimedia

    In SM18 six magnets have been cold tested with good results. It has also been a good week for cyostating with five more magnets completed. In sector 3-4 interconnection work and welding has started in the area damaged on 19 September last year. Interconnection work is also ongoing on the replacement magnet for the faulty dipole removed from sector 1-2. Three separate teams are now working in the three sectors to install the new DN200 pressure release nozzles. In total 27 magnets have been completed so far, with 34 nozzles welded. A new study is also underway to include a similar pressure release system for both the stand-alone magnets (SAMs) and the triplet magnets. All about Chamonix At the public session of the LHCC (the LHC experiments committee) held Wednesday, 18 February Steve Myers, Director for Accelerators and Technology, reviewed the discussions on the LHC at the Chamonix workshop. He explained the scenarios being studied to implement the machine consolidation measures and resume operation. The ...

  9. LHC Report: plumbing new heights

    CERN Multimedia

    John Jowett for the LHC team

    2015-01-01

    Following the end of the arduous 2015 proton run on 4 November, the many teams working on the LHC and its injector complex are naturally entitled to a calmer period before the well-earned end-of-year break. But that is not the way things work.       The CCC team after stable heavy-ion beams are declared in the LHC. Instead, the subdued frenzy of setting up the accelerators for a physics run has started again, this time for heavy-ion beams, with a few additional twists of the time-pressure knob. In this year’s one-month run, the first week was devoted to colliding protons at 2.51 TeV per beam to provide reference data for the subsequent collisions of lead nuclei (the atomic number of lead is Z=82, compared to Z=1 for protons) at the unprecedented energy of 5.02 TeV in the centre of mass per nucleon pair. The chain of specialised heavy-ion injectors, comprising the ECR ion source, Linac3 and the LEIR ring, with its elaborate bunch-forming and c...

  10. Machine protection: availability for particle accelerators

    International Nuclear Information System (INIS)

    Apollonio, A.

    2015-01-01

    Machine availability is a key indicator for the performance of the next generation of particle accelerators. Availability requirements need to be carefully considered during the design phase to achieve challenging objectives in different fields, as e.g. particle physics and material science. For existing and future High-Power facilities, such as ESS (European Spallation Source) and HL-LHC (High-Luminosity LHC), operation with unprecedented beam power requires highly dependable Machine Protection Systems (MPS) to avoid any damage-induced downtime. Due to the high complexity of accelerator systems, finding the optimal balance between equipment safety and accelerator availability is challenging. The MPS architecture, as well as the choice of electronic components, have a large influence on the achievable level of availability. In this thesis novel methods to address the availability of accelerators and their protection systems are presented. Examples of studies related to dependable MPS architectures are given in the thesis, both for Linear accelerators (Linac4, ESS) and circular particle colliders (LHC and HL-LHC). A study of suitable architectures for interlock systems of future availability-critical facilities is presented. Different methods have been applied to assess the anticipated levels of accelerator availability. The thesis presents the prediction of the performance (integrated luminosity for a particle collider) of LHC and future LHC up- grades, based on a Monte Carlo model that allows reproducing a realistic timeline of LHC operation. This model does not only account for the contribution of MPS, but extends to all systems relevant for LHC operation. Results are extrapolated to LHC run 2, run 3 and HL-LHC to derive individual system requirements, based on the target integrated luminosity. (author)

  11. submitter LHC@Home: a BOINC-based volunteer computing infrastructure for physics studies at CERN

    CERN Document Server

    Barranco, Javier; Cameron, David; Crouch, Matthew; De Maria, Riccardo; Field, Laurence; Giovannozzi, Massimo; Hermes, Pascal; Høimyr, Nils; Kaltchev, Dobrin; Karastathis, Nikos; Luzzi, Cinzia; Maclean, Ewen; McIntosh, Eric; Mereghetti, Alessio; Molson, James; Nosochkov, Yuri; Pieloni, Tatiana; Reid, Ivan D; Rivkin, Lenny; Segal, Ben; Sjobak, Kyrre; Skands, Peter; Tambasco, Claudia; Van der Veken, Frederik; Zacharov, Igor

    2017-01-01

    The LHC@Home BOINC project has provided computing capacity for numerical simulations to researchers at CERN since 2004, and has since 2011 been expanded with a wider range of applications. The traditional CERN accelerator physics simulation code SixTrack enjoys continuing volunteers support, and thanks to virtualisation a number of applications from the LHC experiment collaborations and particle theory groups have joined the consolidated LHC@Home BOINC project. This paper addresses the challenges related to traditional and virtualized applications in the BOINC environment, and how volunteer computing has been integrated into the overall computing strategy of the laboratory through the consolidated LHC@Home service. Thanks to the computing power provided by volunteers joining LHC@Home, numerous accelerator beam physics studies have been carried out, yielding an improved understanding of charged particle dynamics in the CERN Large Hadron Collider (LHC) and its future upgrades. The main results are highlighted i...

  12. LHC@Home: a BOINC-based volunteer computing infrastructure for physics studies at CERN

    Science.gov (United States)

    Barranco, Javier; Cai, Yunhai; Cameron, David; Crouch, Matthew; Maria, Riccardo De; Field, Laurence; Giovannozzi, Massimo; Hermes, Pascal; Høimyr, Nils; Kaltchev, Dobrin; Karastathis, Nikos; Luzzi, Cinzia; Maclean, Ewen; McIntosh, Eric; Mereghetti, Alessio; Molson, James; Nosochkov, Yuri; Pieloni, Tatiana; Reid, Ivan D.; Rivkin, Lenny; Segal, Ben; Sjobak, Kyrre; Skands, Peter; Tambasco, Claudia; Veken, Frederik Van der; Zacharov, Igor

    2017-12-01

    The LHC@Home BOINC project has provided computing capacity for numerical simulations to researchers at CERN since 2004, and has since 2011 been expanded with a wider range of applications. The traditional CERN accelerator physics simulation code SixTrack enjoys continuing volunteers support, and thanks to virtualisation a number of applications from the LHC experiment collaborations and particle theory groups have joined the consolidated LHC@Home BOINC project. This paper addresses the challenges related to traditional and virtualized applications in the BOINC environment, and how volunteer computing has been integrated into the overall computing strategy of the laboratory through the consolidated LHC@Home service. Thanks to the computing power provided by volunteers joining LHC@Home, numerous accelerator beam physics studies have been carried out, yielding an improved understanding of charged particle dynamics in the CERN Large Hadron Collider (LHC) and its future upgrades. The main results are highlighted in this paper.

  13. CERN confirms LHC schedule

    CERN Document Server

    2003-01-01

    The CERN Council held its 125th session on 20 June. Highlights of the meeting included confirmation that the LHC is on schedule for a 2007 start-up, and the announcement of a new organizational structure in 2004.

  14. CERN recognises LHC suppliers

    CERN Multimedia

    2002-01-01

    CERN has just presented the first awards recognising LHC suppliers. The Russian institute BINP, the Belgian firm Cockerill-Sambre and the US company Wah-Chang are the recipients of the first 'Golden Hadrons'.

  15. LHC Luminosity Performance

    CERN Document Server

    AUTHOR|(CDS)2091107; Fuchsberger, Kajetan; Papotti, Giulia

    This thesis adresses several approaches with the common goal of assessing, understanding and improving the luminosity of the Large Hadron Collider (LHC). To better exploit existing margins for maximum luminosity while fulfilling the requirements of the LHC experiments, new techniques for luminosity levelling are studied and developed to an operational state, such as changing the crossing angle or $\\beta^*$ (beam size) at the interaction points with the beams in collisions. In 2017 LHC operation, the crossing angle reduction in collisions improved the integrated luminosity by $\\mathrm{\\sim} 2\\,\\mathrm{fb^{-1}}$ ($\\mathrm{\\sim} 4\\,\\mathrm{\\%}$ of the yearly production). For additional diagnostics, a new method for measuring beam sizes and orbits for each circulating bunch using the luminosity measurement during beam separation scans is shown. The results of these Emittance Scans improved the understanding of the LHC luminosity reach and of the orbit offsets introduced by beam-beam long-range effects.

  16. LHC: seven golden suppliers

    CERN Multimedia

    2005-01-01

    The fourth CERN Golden Hadron awards saw seven of the LHC's best suppliers receive recognition for the high quality of their work, compliance with delivery deadlines, flexibility and adaptability to the demanding working conditions of the project. The representatives of the seven companies which received awards during the Golden Hadron ceremony, standing with Lyn Evans, LHC Project Leader. 'The Golden Hadron awards are a symbol of our appreciation of not only the quality and timely delivery of components but also the collaborative and flexible way the firms have contributed to this very difficult project,' said Lyn Evans, head of the LHC project. The awards went to Kemppi-Kempower (Finland), Metso Powdermet (Finland), Transtechnik (Germany), Babcock Noell Nuclear (Germany), Iniziative Industriali (Italy), ZTS VVU Kosice (Slovakia), and Jehier (France). Babock Noell Nuclear (BNN) successfully produced one-third (416 cold dipole masses) of the LHC's superconducting dipole magnets, one of the most critical an...

  17. 27 Febuary 2012 - US DoE Associate Director of Science for High Energy Physics J. Siegrist visiting the LHC superconducting magnet test hall with adviser J.-P. Koutchouk and engineer M. Bajko; in CMS experimental cavern with Spokesperson J. Incadela;in ATLAS experimental cavern with Deputy Spokesperson A. Lankford; in ALICE experimental cavern with Spokesperson P. Giubellino; signing the guest book with Director for Accelerators and Technology S. Myers.

    CERN Multimedia

    Laurent Egli

    2012-01-01

    27 Febuary 2012 - US DoE Associate Director of Science for High Energy Physics J. Siegrist visiting the LHC superconducting magnet test hall with adviser J.-P. Koutchouk and engineer M. Bajko; in CMS experimental cavern with Spokesperson J. Incadela;in ATLAS experimental cavern with Deputy Spokesperson A. Lankford; in ALICE experimental cavern with Spokesperson P. Giubellino; signing the guest book with Director for Accelerators and Technology S. Myers.

  18. 8 October 2013 - Rolex Director- General G. Marini in the ATLAS Control Room with CERN Director-General R. Heuer and ATLAS Collaboration Senior Physicist C. Rembser; visiting the ATLAS experimental cavern at LHC Point 1. Were also present from the Directorate: S. Lettow, Director for Administration and General Infrastructure; from the ATLAS Collaboration: Technische Universitaet Dortmund (DE) J. Jentzsch and SLAC National Accelerator Laboratory (US) G. Piacquadio.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    8 October 2013 - Rolex Director- General G. Marini in the ATLAS Control Room with CERN Director-General R. Heuer and ATLAS Collaboration Senior Physicist C. Rembser; visiting the ATLAS experimental cavern at LHC Point 1. Were also present from the Directorate: S. Lettow, Director for Administration and General Infrastructure; from the ATLAS Collaboration: Technische Universitaet Dortmund (DE) J. Jentzsch and SLAC National Accelerator Laboratory (US) G. Piacquadio.

  19. LHC First Beam 2008

    CERN Multimedia

    Tuura, L

    2008-01-01

    The CMS Centre played a major part in the LHC First Beam Event on September 10th 2008: it was a central point for CMS, hosting journalists from all over the world and providing live link-ups to collaborating institutes as well as, of course, monitoring events as they happened at Point 5. It was also a venue for celebration as the beam completed circuits of the LHC in both directions, passing successfully through the detector (Courtesy of Lassi Tuura)

  20. submitter LHC experiments

    CERN Document Server

    Tanaka, Shuji

    2001-01-01

    Large Hadron Collider (LHC) is under construction at the CERN Laboratory in Switzerland. Four experiments (ATLAS, CMS, LHCb, ALICE) will try to study the new physics by LHC from 2006. Its goal to explore the fundamental nature of matter and the basic forces. The PDF file of the transparency is located on http://www-atlas.kek.jp/sub/documents/lepsymp-stanaka.pdf.

  1. Future of LHC

    CERN Document Server

    Dova, Maria-Teresa; The ATLAS collaboration

    2018-01-01

    The High-Luminosity LHC aims to provide a total integrated luminosity of 3000 fb-1 from p-p collisions at  14 TeV over the course of 10 years. The upgraded ATLAS detector must be able to cope well with increased occupancies and data rates. The large data samples at the High-Luminosity LHC will enable precise measurements of the Higgs boson and other Standard Model particles, as well as searches for new phenomena BSM.

  2. La cellule d'essais du LHC fonctionne avec succès pendant 24h

    CERN Multimedia

    CERN Press Office. Geneva

    1994-01-01

    On 6 and 7 December a string of powerful superconducting magnets for CERN's next particle accelerator the Large Hadron Collider (LHC) ran successfully at 8.36 Tesla for 24 hours. 8.36 Tesla is the magnetic field required to accelerate protons to the required energy for LHC and this result demonstrates that the key technical choices made for the construction of the LHC magnets were correct. The test magnets have shown that they can operate reliably under the same working conditions as the future accelerator.

  3. New magnet transport system for the LHC beam transfer lines

    CERN Multimedia

    Patrice Loïez

    2003-01-01

    The first of 700 magnets has been installed in one of the two transfer tunnels built to transfer the SPS beam into the LHC. The start of this first installation phase of the LHC transfer lines provides the opportunity to launch a new and highly original modular system for transporting and installing all kinds of magnets in very narrow tunnels. The system (pictured here in one of the tunnels) is based on very compact bogies, up to four of which can be coupled together to form a convoy. The wheels are fitted with individual motors enabling them to swivel through an angle of 90° and the convoy to move laterally. The lead vehicle is powered by an electric rail set into the roof of the tunnel. The system is backed up by electrical batteries that enable it to operate in the absence of an outside power source or in the event of power failure. Last but not least, for the long-distance transport of magnets, it can be optically guided by a line traced on the tunnel floor. The convoy moves through the particularly narr...

  4. LHC Report: astounding availability

    CERN Multimedia

    Andrea Apollonio for the LHC team

    2016-01-01

    The LHC is off to an excellent start in 2016, having already produced triple the luminosity of 2015. An important factor in the impressive performance so far this year is the unprecedented machine availability.   LHC integrated luminosity in 2011, 2012, 2015 and 2016 and the prediction of the 2016 performance foreseen at the start of the year. Following the 2015-2016 end of year shutdown, the LHC restarted beam operation in March 2016. Between the restart and the first technical stop (TS1) in June, the LHC's beam intensity was successively increased, achieving operation with 2040 bunches per beam. The technical stop on 7-8 June was shortened to maximise the time available for luminosity production for the LHC experiments before the summer conferences. Following the technical stop, operation resumed and quickly returned to the performance levels previously achieved. Since then, the LHC has been running steadily with up to 2076 bunches per beam. Since the technical stop, a...

  5. LHC detectors trigger/DAQ at LHC

    CERN Document Server

    Sphicas, Paris

    1998-01-01

    At its design luminosity, the LHC will deliver hundreds of millions of proton-proton interactions per second. Storage and computing limitations limit the number of physics events that can be recorded to about 100 per second. The selection will be carried out by the Trigger and data acquisition systems of the experiments. This lecture will review the requirements, architectures and various designs currently considered.

  6. QCD-instantons at LHC. Theoretical aspects; QCD-Instantonen am LHC. Theoretische Aspekte

    Energy Technology Data Exchange (ETDEWEB)

    Petermann, M.

    2007-06-15

    Instantons are nonperturbative, topologically nontrivial field configurations, which occur in every nonabelian gauge theory. They can be understood as tunneling processes between topologically distinct vacua. Although being a basic theoretical aspect of the Standard Model, a direct experimental verification of instanton processes is still lacking. In this thesis the general discovery potential for QCD-instantons at the LHC is studied in detail by means of instanton perturbation theory. In this context the close correspondence between the leading instanton induced processes at HERA and at LHC becomes important. Essential aspects and differences to deep inelastic scattering can already be revealed by studying the simplest process. Based on these results inclusive cross sections are calculated including the emission of final state gluons. Compared to deep inelastic scattering, a large enhancement of the cross section is found. (orig.)

  7. LHC Report: LHC smashes collision records

    CERN Multimedia

    Sarah Charley

    2016-01-01

    The Large Hadron Collider is now producing more than a billion proton-proton collisions per second.   The LHC is colliding protons at a faster rate than ever before: approximately 1 billion times per second. Since April 2016, the LHC has delivered more than 30 inverse femtobarns (fb-1) to both ATLAS and CMS. This means that around 2.4 quadrillion (2.4 million billion) collisions have been seen by each of the experiments this year. The inverse femtobarn is the unit of measurement for integrated luminosity, indicating the cumulative number of potential collisions. This compares with the total of 33.2 fb-1 produced between 2010 and 2015. The unprecedented performance this year is the result of both the incremental increases in collision rate and the sheer amount of time the LHC has been up and running. This comes after a slow start-up in 2015, when scientists and engineers still needed to learn how to operate the machine at a much higher energy. “With more energy, the machine is much more sen...

  8. LHC un defi technologique sans precedent

    CERN Document Server

    Baruch, J O

    2002-01-01

    This article presents the future LHC (large hadron collider) in simple terms and gives some details concerning radiation detectors and supra-conducting magnets. LHC will take the place of the LEP inside the 27 km long underground tunnel near Geneva and is scheduled to operate in 2007. 8 years after its official launching the LHC project has piled up 2 year delay and has exceeded its initial budget (2 milliard euros) by 18%. Technological challenges and design difficulties are the main causes of these shifts. The first challenge has been carried out successfully, it was the complete clearing out of the LEP installation. In order to release 14 TeV in each proton-proton collision, powerful magnetic fields (8,33 Tesla) are necessary. 1248 supra-conducting 15 m-long bipolar magnets have to be built. 30% of the worldwide production of niobium-titanium wires will be used each year for 5 years in the design of these coils. The global cryogenic system will be gigantic and will use 94 tons of helium. 4 radiation detect...

  9. High Precision Current Control for the LHC Main Power Converters

    CERN Document Server

    Thiesen, H; Hudson, G; King, Q; Montabonnet, V; Nisbet, D; Page, S

    2010-01-01

    Since restarting at the end of 2009, the LHC has reached a new energy record in March 2010 with the two 3.5 TeV beams. To achieve the performance required for the good functioning of the accelerator, the currents in the main circuits (Main Bends and Main Quadrupoles) must be controlled with a higher precision than ever previously requested for a particle accelerator at CERN: a few parts per million (ppm) of nominal current. This paper describes the different challenges that were overcome to achieve the required precision for the current control of the main circuits. Precision tests performed during the hardware commissioning of the LHC illustrate this paper.

  10. Commissioning of the 400 MHz LHC RF System

    CERN Document Server

    Ciapala, Edmond; Baudrenghien, P; Brunner, O; Butterworth, A; Linnecar, T; Maesen, P; Molendijk, J; Montesinos, E; Valuch, D; Weierud, F

    2008-01-01

    The installation of the 400 MHz superconducting RF system in LHC is finished and commissioning is under way. The final RF system comprises four cryo-modules each with four cavities in the LHC tunnel straight section round IP4. Also underground in an adjacent cavern shielded from the main tunnel are the sixteen 300 kW klystron RF power sources with their high voltage bunkers, two Faraday cages containing RF feedback and beam control electronics, and racks containing all the slow controls. The system and the experience gained during commissioning will be described. In particular, results from conditioning the cavities and their movable main power couplers and the setting up of the low level RF feedbacks will be presented.

  11. Recognition tunneling

    Czech Academy of Sciences Publication Activity Database

    Lindsay, S.; He, J.; Sankey, O.; Hapala, Prokop; Jelínek, Pavel; Zhang, P.; Chang, S.; Huang, S.

    2010-01-01

    Roč. 21, č. 26 (2010), 262001/1-262001/12 ISSN 0957-4484 R&D Projects: GA ČR GA202/09/0545 Institutional research plan: CEZ:AV0Z10100521 Keywords : STM * tunneling current * molecular electronics * DFT calculations Subject RIV: BM - Solid Matter Physics ; Magnetism Impact factor: 3.644, year: 2010

  12. Electronics for LHC experiments

    International Nuclear Information System (INIS)

    Bourgeois, Francois

    1995-01-01

    Full text: A major effort is being mounted to prepare the way handling the high interaction rates expected from CERN's new LHC proton-proton collider (see, for example, November, page 6). September saw the First Workshop on Electronics for LHC Experiments, organized by Lisbon's Particle Physics Instrumentation Laboratory (LIP) on behalf of CERN's LHC Electronics Review Board (LERB - March, page 2). Its purpose was not only for the LERB to have a thorough review of ongoing activities, but also to promote cross fertilization in the engineering community involved in electronics design for LHC experiments. The Workshop gathered 187 physicists and engineers from 20 countries including USA and Japan. The meeting comprised six sessions and 82 talks, with special focus on radiation-hard microelectronic processes, electronics for tracking, calorimetry and muon detectors, optoelectronics, trigger and data acquisition systems. Each topic was introduced by an invited speaker who reviewed the requirements set by the particular detector technology at LHC. At the end of each session, panel discussions were chaired by each invited speaker. Representatives from four major integrated circuit manufacturers covered advanced radiation hard processes. Two talks highlighted the importance of obsolescence and quality systems in the long-lived and demanding environment of LHC. The Workshop identified areas and encouraged efforts for rationalization and common developments within and between the different detector groups. As a result, it will also help ensure the reliability and the long term maintainability of installed equipment. The proceedings of the Workshop are available from LIP Lisbon*. The LERB Workshop on Electronics for LHC Experiments will become a regular event, with the second taking place in Hungary, by Lake Balaton, from 23-27 September 1996. The Hungarian institutes KFKIRMKI have taken up the challenge of being as successful as LIP Lisbon in the organization

  13. Strategy and issues for the LHC upgrades and fair, including longer-term prospects

    CERN Document Server

    Zimmermann, F

    2013-01-01

    This report discusses the time line, goals and key ingredients for the next ten years of LHC operation, including injector upgrade, for the following High Luminosity LHC (HL-LHC), and for the FAIR project. Results from pertinent EuCARD-WP4 workshops on optics, space charge, crab cavities, crystal collimation, and electron cloud are summarized in this context. A Large Hadron electron Collider, LHeC, would be an additional upgrade, further expanding the physics scope of the LHC, to eventually include both ep and γγ Higgs factories (LHeC-HF and SAPPHiRE). Results from relevant topical WP4 workshops are highlighted. The development of magnet and cable technology based on Nb$_{3}$Sn, and HTS, for the HL-LHC prepares the ground for a future higher-energy hadron collider, either in the LHC tunnel, “HELHC” (33 TeV c.m.), or in a new 80- or 100-km tunnel, “VHE-LHC” (100 TeV c.m.). A large new tunnel could also host an ultimate highest-precision e+e- Higgs factory collider, “TLEP,” exhibiting many synergi...

  14. LHC rap: a global phenomenon

    CERN Multimedia

    2008-01-01

    Do you think the LHC is super duper fly? Does it make you want to compose some slick rhymes and bust out some killer beats? It did for one CERN rapper, and the results have become a YouTube smash hit! Katie McAlpine will sing for the CMS party on 24 September, and for the ATLAS Fest on 4 October.The Large Hadron Rap, to give it its full name, is the brainchild of AlpineKat, AKA Katie McAlpine, who is currently working for ATLAS e-News and outreach. To date, the YouTube video rap has been viewed more than 2.5 million times, to say nothing of the media coverage. Featured in newspapers around the world, including the New York Times in the US, The Telegraph in the UK and Geneva’s very own Matin Bleu, the rap is officially a sensation! Katie wrote the inspired (and pretty accurate) physics lyrics during her commute on the number 56 bus between Geneva and CERN. After obtaining permission to film in the experiment caverns and tunnel,...

  15. Performance of the Protection System for Superconducting Circuits during LHC Operation

    OpenAIRE

    Denz, R; Charifoulline, Z; Dahlerup-Petersen, K; Schmidt, R; Siemko, A; Steckert, J

    2011-01-01

    The protection system for superconducting magnets and bus-bars is an essential part of the LHC machine protection and ensures the integrity of substantial elements of the accelerator. Due to the large amount of hardwired and software interlock channels the dependability of the system is a critical parameter for the successful operation of the LHC.

  16. Radiation protection issues after 20 years of LHC operation

    CERN Document Server

    Forkel-Wirth, D.; Roesler, S.; Theis, C.; Ulrici, L.; Vincke, H.; Vincke, Hz.

    2011-01-01

    Since November 2009, the LHC commissioning progresses very well, both with proton and lead beams. It will continue in 2011 and nominal LHC operation is expected to be attained in 2013. In parallel, plans for various LHC upgrades are under discussion, suggesting a High-Luminosity (HL) upgrade first and a High-Energy (HE) upgrade in a later state. Whereas the upgrade in luminosity would require the modification of only some few key accelerator components like the inner triplets, the upgrade in beam energy from 7 TeV to 16.5 TeV would require the exchange of all dipoles and of numerous other accelerator components. The paper gives an overview of the radiation protection issues related to the dismantling of LHC components prior to the installation of the HE-LHC components, i.e. after about 20 years of LHC operation. Two main topics will be discussed: (i) the exposure of workers to ionizing radiation during the dismantling of dipoles, inner triplets or collimators and experiments and (ii) the production, condition...

  17. Transverse emittance measurement and preservation at the LHC

    Energy Technology Data Exchange (ETDEWEB)

    Kuhn, Maria

    2016-06-20

    The Large Hadron Collider (LHC) at CERN is a high energy storage ring that provides proton and heavy ion collisions to study fundamental particle physics. The luminosity production is closely linked to emittance preservation in the accelerator. The transverse emittance is the phase space density of the beam and should be conserved when the particle beam is transformed through the accelerator. Perturbing effects, however, can lead to emittance increase and hence luminosity degradation. Measuring the emittance growth is a complex task with high intensity beams and changing energies. The machine optics and the transverse beam size have to be measured as accurately as possible. Beta function measurements with k-modulation are discussed. With this method the quadrupole focussing strength is varied and the resulting tune change is traced to determine the beta function at the quadrupole. A new k-modulation measurement tool was developed for the LHC. The fully automatic and online measurement system takes constraints of various systems such as tune measurement precision and powering limitations of the LHC superconducting circuits into account. With sinusoidal k-modulation record low beta function measurement uncertainties in the LHC have been reached. 2015 LHC beta function and β*, which is the beta function at the collision point, measurements with k-modulation will be presented. Wire scanners and synchrotron light monitors are presently used in the LHC to measure the transverse beam size. Accuracy and limitations of the LHC transverse profile monitors are discussed. During the 2012 LHC proton run it was found that wire scanner photomultiplier saturation added significant uncertainty on all measurements. A large discrepancy between emittances from wire scanners and luminosity was discovered but not solved. During Long Shutdown 1 the wire scanner system was upgraded with new photomultipliers. A thorough study of LHC wire scanner measurement precision in 2015 is presented

  18. Beam Loss Patterns at the LHC Collimators Measurements & Simulations

    CERN Document Server

    Böhlen, Till Tobias

    2008-01-01

    The Beam Loss Monitoring (BLM) system of the Large Hadron Collider (LHC) detects particle losses of circulating beams and initiates an emergency extraction of the beam in case that the BLM thresholds are exceeded. This protection is required as energy deposition in the accelerator equipment due to secondary shower particles can reach critical levels; causing damage to the beam-line components and quenches of superconducting magnets. Robust and movable beam line elements, so-called collimators, are the aperture limitations of the LHC. Consequently, they are exposed to the excess of lost beam particles and their showers. Proton loss patterns at LHC collimators have to be determined to interpret the signal of the BLM detectors and to set adequate BLM thresholds for the protection of collimators and other equipment in case of unacceptably increased loss rates. The first part of this work investigates the agreement of BLM detector measurements with simulations for an LHC-like collimation setup. The setup consists ...

  19. A Beam Quality Monitor for LHC Beams in the SPS

    CERN Document Server

    Papotti, G

    2008-01-01

    The SPS Beam Quality Monitor (BQM) system monitors the longitudinal parameters of the beam before extraction to the LHC to prevent losses and degradation of the LHC luminosity by the injection of low quality beams. It is implemented in two priority levels. At the highest level the SPS-LHC synchronization and global beam structure are verified. If the specifications are not met, the beam should be dumped in the SPS before extraction. On the second level, individual bunch position, length and stability are checked for beam quality assessment. Tolerances are adapted to the mode of operation and extraction to the LHC can also be inhibited. Beam parameters are accessed by acquiring bunch profiles with a longitudinal pick up and fast digital oscilloscope. The beam is monitored for instabilities during the acceleration cycle and thoroughly checked a few ms before extraction for a final decision on extraction interlock. Dedicated hardware and software components implementing fast algorithms are required. In this pape...

  20. Tunnel - history of

    International Nuclear Information System (INIS)

    1998-11-01

    This book introduces history of tunnel in ancient times, the middle ages and modern times, survey of tunnel and classification of bedrock like environment survey of position, survey of the ground, design of tunnel on basic thing of the design, and design of tunnel of bedrock, analysis of stability of tunnel and application of the data, construction of tunnel like lattice girder and steel fiber reinforced shot crete, and maintenance control and repair of tunnel.

  1. An improved scattering routine for collimation tracking studies at LHC

    CERN Document Server

    Tambasco, Claudia; Salvachua Ferrando, Maria Belen; Cavoto, Gianluca

    The present Master thesis work has been carried out at CERN in the framework of the LHC (Large Hadron Collider) Collimation project. The LHC accelerates proton beams up to 7 TeV colliding in the experiment detectors installed in four points of the accelerator ring. The LHC is built to store a energy of 360MJ for each beam. The energy deposition induced by local beam losses could quench the superconducting magnets located around the accelerator beam pipes. To prevent and keep under control dangerous beam losses, an efficient collimation system is required. In addition, the achievable LHC beam intensity is related to the beam loss rate and, consequently, to the cleaning efficiency of the collimation system. Collimation studies at LHC are carried out also by means of simulations by using SixTrack, a dedicated simulation tool that tracks a large numbers of particles for many turns around the ring. The SixTrack code includes a scattering routine to model proton interactions with the material of the collimators j...

  2. Tunneling beyond the Fermilab site

    International Nuclear Information System (INIS)

    Baker, S.; Elwyn, A.; Lach, J.; Read, A.

    1983-01-01

    An accelerator that crosses the Fermilab site boundary must have a minimum effect on the surrounding environment and the people residing in the area. Unobstructed public access should be allowed above the ring except in relatively few areas such as the injection, dump, and experimental regions. The accelerator should be a benign and unobtrusive neighbor not only when it is completed but also in the construction period. For these reasons underground tunneling for all or most of the ring seems attractive. In this note we look into some questions raised by tunneling beyond the Fermilab site. Most of our discussion is of general applicability. However, we will use as examples two specific ring configurations. The examples have not been optimized from the point of view of physics output or accelerator technology but are just specific examples which allow us to study questions of tunneling. One is a ring of 5 km radius (5 TeV) tangent to the Tevatron and entirely east of the Fox River and fed by a beam from the Tevatron which crosses under the river. We assume that each of these machines will have 100 beam fills per year and we scale the maximum intensities with the accelerator radii. Thus we assume that there will be 1.0 E14 protons in each beam of the 20 TeV machine and 2.5 E13 for the 5 TeV machine

  3. Energy Deposition and DPA in the Superconducting Links for the HILUMI LHC Project at the LHC Interaction Points

    CERN Document Server

    AUTHOR|(CDS)2092158; Broggi, Francesco; Santini, C; Ballarino, Amalia; Cerutti, Francesco; Esposito, Luigi Salvatore

    2015-01-01

    In the framework of the upgrade of the LHC machine, the powering of the LHC magnets foresees the removal of the power converters and distribution feedboxes from the tunnel and its location at the surface[1]. The Magnesium Diboride (MgB2) connecting lines in the tunnel will be exposed to the debris from 7+7 TeV p-p interaction. The Superconducting (SC) Links will arrive from the surface to the tunnel near the separation dipole, at about 80 m from the Interaction Point at IP1 and IP5. The Connection Box (where the cables of the SC Links are connected to the NbTi bus bar) will be close to the beam pipe. The debris and its effect on the MgB2 SC links in the connection box (energy deposition and displacement per atom) are presented. The effect of thermal neutrons on the Boron consumption and the contribution of the lithium nucleus and the alpha particle on the DPA are evaluated. The results are normalized to an integrated luminosity of 3000 fb-1, value that represents the LHC High Luminosity lifetime. The dose de...

  4. LHC physics results and prospects

    CERN Document Server

    Kono, Takanori; The ATLAS collaboration

    2018-01-01

    This talk presents the latest results from LHC Run-2 as of May 2018 which include Standard Model measurements, Higgs boson properties and beyond Standard Model search results. The prospects for future LHC runs are also shown.

  5. Commissioning of the LHC

    CERN Multimedia

    CERN. Geneva

    2007-01-01

    The LHC construction is now approaching the end and it is now time to prepare for commissioning with beam. The behavior of a proton storage ring is much different to that of LEP, which profited from strong radiation damping to keep the beam stable. Our last experience with a hadron collider at CERN goes back more than 15 years when the proton-antiproton collider last operated. Ppbar taught us a lot about the machine physics of bunched beam proton storage rings and was essential input for the design of the LHC. After a short presentation of where we stand today with machine installation and hardware commissioning, I will discuss the main machine physics issues that will have to be dealt with in the LHC.

  6. Electronics at LHC

    CERN Document Server

    Hall, Geoffrey

    1998-01-01

    An overview of the electronic readout systems planned for use in the CMS and ATLAS experiments at the LHC will be given, with an emphasis on the motivations for the designs adopted and major technologies to be employed, specially those which are specific to LHC. At its design luminosity, the LHC will deliver hundreds of millions of proton-proton interactions per second. Storage and computing limitations limit the number of physics events that can be recorded to about 100 per second. The selection will be carried out by the Trigger and data acquisition systems of the experiments. This lecture will review the requirements, architectures and various designs currently considered. Introduction. Structure of gauge theories. The QED and QCD examples. Chiral theories. The electroweak theory. Spontaneous symmetry breaking. The Higgs machanism.Gauge boson and fermion masses. Yukawa coupling. Charges current couplings. The Cabibbo-Kobayashi-Maskawa matrix and CP violation. neutral current couplings. the Clashow-Iliopoul...

  7. LHC bending magnet coil

    CERN Multimedia

    A short test version of coil of wire used for the LHC dipole magnets. The high magnetic fields needed for guiding particles around the Large Hadron Collider (LHC) ring are created by passing 12’500 amps of current through coils of superconducting wiring. At very low temperatures, superconductors have no electrical resistance and therefore no power loss. The LHC is the largest superconducting installation ever built. The magnetic field must also be extremely uniform. This means the current flowing in the coils has to be very precisely controlled. Indeed, nowhere before has such precision been achieved at such high currents. Magnet coils are made of copper-clad niobium–titanium cables — each wire in the cable consists of 9’000 niobium–titanium filaments ten times finer than a hair.

  8. Lectures on LHC physics

    CERN Document Server

    Plehn, Tilman

    2015-01-01

    With the discovery of the Higgs boson, the LHC experiments have closed the most important gap in our understanding of fundamental interactions, confirming that such interactions between elementary particles can be described by quantum field theory, more specifically by a renormalizable gauge theory. This theory is a priori valid for arbitrarily high energy scales and does not require an ultraviolet completion. Yet, when trying to apply the concrete knowledge of quantum field theory to actual LHC physics - in particular to the Higgs sector and certain regimes of QCD - one inevitably encounters an intricate maze of phenomenological know-how, common lore and other, often historically developed intuitions about what works and what doesn’t. These lectures cover three aspects to help understand LHC results in the Higgs sector and in searches for physics beyond the Standard Model: they discuss the many facets of Higgs physics, which is at the core of this significantly expanded second edition; then QCD, to the deg...

  9. UFOs in the LHC

    Energy Technology Data Exchange (ETDEWEB)

    Grob, Laura [CERN, Geneva (Switzerland); Technische Universitaet Darmstadt (Germany)

    2016-07-01

    In the Large Hadron Collider (LHC) localized and recurring beam losses have been observed, which usually persist for several hundred microseconds. With increasing beam energy these losses were found to pose a serious risk to the machine availability, as some of these events can cause quenches in the superconducting magnets. The current understanding is that these losses are caused by falling microparticles that interact with the proton beam. To describe these so-called UFOs (unidentified falling objects) and their dynamics, a model was developed starting from the approach that only gravitational and electrostatic forces act on a neutrally charged particle. However, the model's results cannot reproduce the actual data from the LHC's beam loss monitors (BLMs), which indicates a more complex UFO dynamic. Experimental studies and further analysis of the BLM data are planned to investigate the UFO dynamics in greater detail and to understand origins and release mechanisms for microparticles in the LHC beam pipe.

  10. Taiwan links up to world's 1st LHC Computing Grid Project

    CERN Multimedia

    2003-01-01

    Taiwan's Academia Sinica was linked up to the Large Hadron Collider (LHC) Computing Grid Project to work jointly with 12 other countries to construct the world's largest and most powerful particle accelerator

  11. 3 October 2013 - Ukrainian Vice Prime Minister Ukraine K. I. Gryschenko welcomed by CERN Director-General R. Heuer who introduces Head of International Relations R. Voss; Head of Technology Department F. Bordry; Deputy Head of International Relations E. Tsesmelis; Deputy Legal Counsel M. Wilbers; Adviser for Ukraine T. Kurtyka; Signing of the Agreement between Ukraine and CERN concerning the granting of the status of Associate Member at CERN; in the LHC tunnel at Point 5 and visiting CMS experimental area with CERN Team Leader A. Petrilli.

    CERN Multimedia

    Anna Pantelia

    2013-01-01

    3 October 2013 - Ukrainian Vice Prime Minister Ukraine K. I. Gryschenko welcomed by CERN Director-General R. Heuer who introduces Head of International Relations R. Voss; Head of Technology Department F. Bordry; Deputy Head of International Relations E. Tsesmelis; Deputy Legal Counsel M. Wilbers; Adviser for Ukraine T. Kurtyka; Signing of the Agreement between Ukraine and CERN concerning the granting of the status of Associate Member at CERN; in the LHC tunnel at Point 5 and visiting CMS experimental area with CERN Team Leader A. Petrilli.

  12. Superconducting magnets for particle large accelerators

    International Nuclear Information System (INIS)

    Kircher, F.

    1994-01-01

    The different accelerator types (linear, circular) and the advantages of using superconductivity in particle accelerator are first reviewed. Characteristics of some large superconducting accelerators (Tevatron, HERA, RHIC, LHC CERN) are presented. The design features related to accelerator magnets are reviewed: magnet reproducibility, stability, field homogeneity, etc. and the selected design characteristics are discussed: manufacturing method, winding, shielding, cryostat. CEA involvement in this domain mainly addressing quadrupoles, is presented together with the Large Hadron Collider (LHC) project at CERN. Characteristics and design of detector magnets are also described. 5 figs., 2 tabs

  13. Cryogenics will cool LHC

    International Nuclear Information System (INIS)

    Anon.

    2001-01-01

    Results of the investigation into the cryogenic regulating line (QRL) performed by the LHC laboratory are presented. It is projected that eight cryogenic units located in five places around the LHC ring will provide superconducting magnets by liquid helium through eight cryogenic regulating lines of 3.2 km each. All QRL zones remain to be independent. CERN uses three test units with the aim of the certification of chosen constructions and verification of their thermal and mechanical efficiency before starting full-scale production [ru

  14. LHC-ILC synergy

    CERN Document Server

    Godbole, Rohini M

    2006-01-01

    I will begin by making a few general comments on the synergy between the Large Hadron Collider (LHC) which will go in action in 2007 and the International Linear Collider (ILC) which is under planning. I will then focus on the synergy between the LHC and the PLC option at the ILC, which is expected to be realised in the later stages of the ILC program. In this I will cover the possible synergy in the Higgs sector (with and without CP violation), in the determination of the anomalous vector boson couplings and last but not the least, in the search for extra dimensions and radions.

  15. The LHC detector challenge

    CERN Document Server

    Virdee, Tejinder S

    2004-01-01

    The Large Hadron Collider (LHC) from CERN, scheduled to come online in 2007, is a multi-TeV proton-proton collider with vast detectors. Two of the more significant detectors for LHC are ATLAS and CMS. Currently, both detectors are more than 65% complete in terms of financial commitment, and the experiments are being assembled at an increasing pace. ATLAS is being built directly in its underground cavern, whereas CMS is being assembled above ground. When completed, both detectors will aid researchers in determining what lies at the high-energy frontier, in particular the mechanism by which particles attain mass. (Edited abstract).

  16. LHC beampipe interconnection

    CERN Document Server

    Particle beams circulate for around 10 hours in the Large Hadron Collider (LHC). During this time, the particles make four hundred million revolutions of the machine, travelling a distance equivalent to the diameter of the solar system. The beams must travel in a pipe which is emptied of air, to avoid collisions between the particles and air molecules (which are considerably bigger than protons). The beam pipes are pumped down to an air pressure similar to that on the surface of the moon. Much of the LHC runs at 1.9 degrees above absolute zero. When material is cooled, it contracts. The interconnections must absorb this contraction whilst maintaining electrical connectivity.

  17. Exotic highly ionising particles at the LHC

    CERN Document Server

    De Roeck, A; Mermod, P; Milstead, D; Sloan, T

    2012-01-01

    The experiments at the Large Hadron Collider (LHC) are able to discover or set limits on the production of exotic particles with TeV-scale masses possessing values of electric and/or magnetic charge such that they appear as highly ionising particles (HIPs). In this paper the sensitivity of the LHC experiments to HIP production is discussed in detail. It is shown that a number of different detection methods are required to investigate as fully as possible the charge-mass range. These include direct detection as the HIPs pass through detectors and, in the case of magnetically charged objects, the so-called induction method with which monopoles which stop in accelerator and detector material could be observed. The benefit of using complementary approaches to HIP detection is discussed.

  18. Scientific Opportunity: the Tevatron and the LHC

    CERN Multimedia

    2010-01-01

    The press makes much of the competition between CERN’s LHC and Fermilab’s Tevatron in the search for the Higgs boson. This competitive aspect is real, and probably adds spice to the scientific exploration, but for us such reporting often feels like spilling the entire pepper shaker over a fine meal. The media’s emphasis on competition obscures the more important substance of our long-standing collaboration in scientific discovery.   Our laboratories and our communities have worked together for decades. Europeans have contributed greatly to the Tevatron’s many successes, including the discovery of the top quark, the discovery of fast oscillations in the decay of strange B mesons and the many searches for new phenomena. Americans have contributed to many programs at CERN, notably the extraordinary precision measurements of LEP, and more recently construction of the LHC accelerator and detectors. Fermilab scientists played a vital role throughout 2009 in...

  19. The LHC and its electrotechnical challenges

    International Nuclear Information System (INIS)

    Bordry, F.

    2010-01-01

    After a brief presentation of the CERN, the European organization for nuclear research, this article presents the LHC, the Large Hadron Collider, the largest and most powerful particle accelerator in the world. The project somehow started in 1984 and relies on several technological challenges which are herein described: superconducting magnets (their characteristics and cryogenic operation), operation security with particularly high energies stored in magnets and beams, LHC electricity supply (electric circuits with high time constant, a required precision and reproducibility of the magnetic field during all the operation phases, importance of power converters). Then the author evokes the starting procedures, some serious damages which occurred, and the restart of the operation period with spectacular results in terms of beam energy. Future experiments and expected results are also evoked

  20. LHC Report: No beams but still busy

    CERN Multimedia

    Mike Lamont for the LHC Team

    2012-01-01

    The LHC finished with beams for 2011 on Wednesday 7 December after a pretty good year of operation. The cryogenics team has emptied the magnets of helium for the winter technical stop and a full maintenance programme has started. The LHC is running long operational years at present with only a few short technical stops during operation with beam. This leaves very little time for much-needed maintenance and upgrades. Thus, the hardware teams involved have to take full advantage of the time available during the winter stop.   The Engineering Department is planning and coordinating the maintenance and repair activities for the whole accelerator complex. The list of planned interventions is truly impressive! There is a lot of work that involves the essential technical infrastructure systems (electricity, cooling, ventilation). Cryogenics have established a full programme aimed at maintaining and improving their already good level of availability. Other systems undergoing maintenance include: vacu...

  1. LHC Report: No beams but still busy

    CERN Multimedia

    Mike Lamont for the LHC Team

    2011-01-01

    The LHC finished with beams for 2011 on Wednesday 7 December after a pretty good year of operation. The cryogenics team has emptied the magnets of helium for the winter technical stop and a full maintenance programme has started. The LHC is running long operational years at present with only a few short technical stops during operation with beam. This leaves very little time for much-needed maintenance and upgrades. Thus, the hardware teams involved have to take full advantage of the time available during the winter stop.   The Engineering Department is planning and coordinating the maintenance and repair activities for the whole accelerator complex. The list of planned interventions is truly impressive! There is a lot of work that involves the essential technical infrastructure systems (electricity, cooling, ventilation). Cryogenics have established a full programme aimed at maintaining and improving their already good level of availability. Other systems undergoing maintenance include: vacu...

  2. LHC Commissioning and First Operation

    OpenAIRE

    Myers, S

    2010-01-01

    A description is given of the repair of the LHC after the accident of September 2008. The LHC hardware and beam commissioning and initial operation are reviewed both in terms of beam and hardware performance. The implemented machine protection measures and their impact on LHC operation are presented.

  3. LHC challenges and upgrade options

    Energy Technology Data Exchange (ETDEWEB)

    Bruning, O [CERN AB/ABP, Y03600, 1211 Geneva 23 (Switzerland)], E-mail: Oliver.Bruning@cern.ch

    2008-05-15

    The presentation summarizes the key parameters of the LHC collider. Following a discussion of the main challenges for reaching the nominal machine performance the presentation identifies options for increasing the operation tolerances and the potential performance reach of the LHC by means of future hardware upgrades of the LHC and its injector complex.

  4. LHC challenges and upgrade options

    International Nuclear Information System (INIS)

    Bruning, O

    2008-01-01

    The presentation summarizes the key parameters of the LHC collider. Following a discussion of the main challenges for reaching the nominal machine performance the presentation identifies options for increasing the operation tolerances and the potential performance reach of the LHC by means of future hardware upgrades of the LHC and its injector complex

  5. Reliability of the Quench Protection System for the LHC Superconducting Elements

    OpenAIRE

    Vergara-Fernández, A; Rodríguez-Mateos, F

    2003-01-01

    The huge energy stored in the Large Hadron Collider (LHC) could potentially cause severe damage when the superconducting state disappears (quench) if precautions are not taken. Most of the superconducting elements in this accelerator require protection in case of resistive transition. The reliability of the Quench Protection System will have a very important impact on the overall LHC performance. Existing high energy accelerators were conceived as prototypes whose main objective was not the e...

  6. Magnetization and loss measurements on Nb$_{3}$Sn and NbTi strands for ITER and LHC

    CERN Document Server

    Foitl, M

    2001-01-01

    Recent developments in high energy physics have led to a demand for high magnetic fields which cannot be generated permanently by conventional magnets wound from Cu cables. The acceleration of protons in a ring accelerator up to particle energies of several TeVs or the magnetic confinement of fusion plasmas of sufficient pressure to generate approx 1 GW of fusion power, or even more, are only two examples. To reach beam to beam collision energies of several TeV for hadrons or heavy ions, accelerator magnets have to provide very high magnetic fields which can only be produced by superconducting magnets. In the case of the Large Hadron Collider (LHC), which is planned to be commissioned in the year 2005, the circumference of the beam line is given by the dimensions of the 27 Km Large Electron Positron (LEP) Collider tunnel. Consequently each superconducting arc dipole has to provide a field of 8.36 T to bend 7 TeV protons around the ring. Apart from the total magnitude of the bending field, which necessitates t...

  7. Magnetization and loss measurements on Nb3Sn and NbTi strands for ITER and LHC

    CERN Document Server

    Foitl, M

    2001-01-01

    Recent developments in high energy physics have led to a demand for high magnetic fields which cannot be generated permanently by conventional magnets wound from Cu cables. The acceleration of protons in a ring accelerator up to particle energies of several TeVs or the magnetic confinement of fusion plasmas of sufficient pressure to generate approx 1 GW of fusion power, or even more, are only two examples. To reach beam to beam collision energies of several TeV for hadrons or heavy ions, accelerator magnets have to provide very high magnetic fields which can only be produced by superconducting magnets. In the case of the Large Hadron Collider (LHC), which is planned to be commissioned in the year 2005, the circumference of the beam line is given by the dimensions of the 27 Km Large Electron Positron (LEP) Collider tunnel. Consequently each superconducting arc dipole has to provide a field of 8.36 T to bend 7 TeV protons around the ring. Apart from the total magnitude of the bending field, which necessitates t...

  8. LHC Report: Summer temperatures in the LHC

    CERN Multimedia

    Jan Uythoven for the LHC Team

    2012-01-01

    The LHC experiments have finished their data-taking period before the summer conferences. The machine has already delivered substantially more collisions to the experiments this year than in the whole of 2011. The LHC has now started a six-day Machine Development period, which will be followed by the second Technical Stop of the year.   The number of collisions delivered to the experiments is expressed in integrated luminosity. In 2011, the integrated luminosity delivered to both ATLAS and CMS was around 5.6 fb-1. On Monday 18 June, experiments finished taking data before the summer conferences and the integrated luminosity for 2012 so far is about 6.6 fb-1, well above the unofficial target of 5 fb-1. The LHC’s performance over the last week of running was so efficient that the injection kicker magnets – which heat up due to the circulating beam – did not have time to cool down between the subsequent fills. As the time constants for warming up and cooli...

  9. The BRAN luminosity detectors for the LHC

    Energy Technology Data Exchange (ETDEWEB)

    Matis, H.S.; Placidi, M.; Ratti, A.; Turner, W.C. [Lawrence Berkeley National Laboratory, Berkeley, CA 94720 (United States); Bravin, E. [CERN, 1211 Geneva 23 (Switzerland); Miyamoto, R. [European Spallation Source, ESS AB, P.O. Box 176, SE-221 00 Lund (Sweden)

    2017-03-11

    This paper describes the several phases which led, from the conceptual design, prototyping, construction and tests with beam, to the installation and operation of the BRAN (Beam RAte of Neutrals) relative luminosity monitors for the LHC. The detectors have been operating since 2009 to contribute, optimize and maintain the accelerator performance in the two high luminosity interaction regions (IR), the IR1 (ATLAS) and the IR5 (CMS). The devices are gas ionization chambers installed inside a neutral particle absorber 140 m away from the Interaction Points in IR1 and IR5 and monitor the energy deposited by electromagnetic showers produced by high-energy neutral particles from the collisions. The detectors have the capability to resolve the bunch-by-bunch luminosity at the 40 MHz bunch rate, as well as to survive the extreme level of radiation during the nominal LHC operation. The devices have operated since the early commissioning phase of the accelerator over a broad range of luminosities reaching 1.4×10{sup 34} cm{sup −2} s{sup −1} with a peak pileup of 45 events per bunch crossing. Even though the nominal design luminosity of the LHC has been exceeded, the BRAN is operating well. After describing how the BRAN can be used to monitor the luminosity of the collider, we discuss the technical choices that led to its construction and the different tests performed prior to the installation in two IRs of the LHC. Performance simulations are presented together with operational results obtained during p-p operations, including runs at 40 MHz bunch rate, Pb-Pb operations and p-Pb operations.

  10. Golden Jubilee Photos: Laying the Ground for the LHC

    CERN Multimedia

    2004-01-01

    In 1997, a prototype of the LHC dipole magnet, with the two beampipes running through the centre. Even before digging the LEP tunnel, in the early eighties CERN scientists began laying the plans for the second-generation collider to go in the tunnel. From the beginning, physicists had their eyes fixed on certain goals such as finding the Higgs boson and signs of supersymmetric particles. To reach the desired energies within the LEP tunnel, instead of LEP's electrons and positrons, the next collider would need to use more massive particles that radiate away less energy as they travel around the circular tunnel. Also, since the United States was planning the Superconducting Super Collider (SSC) with a circumference even larger than LEP's, CERN scientists conceived of their next collider as a "high-luminosity" machine that would excel at producing a high number of collisions. But since making a strong antiproton beam is laborious, this collider would have to smash together two proton beams. Thus the LHC project ...

  11. Mechanical Design of the LHC Standard Half-Cell

    Science.gov (United States)

    Poncet, A.; Brunet, J. C.; Cruikshank, P.; Genet, M.; Parma, V.; Rohmig, P.; Saban, R.; Tavian, L.; Veness, R.; Vlogaert, J.; Williams, L. R.

    1997-05-01

    The LHC Conceptual Design Report issued on 20th October 1995 (CERN/AC/95-05 (LHC) - nicknamed "Yellow Book") introduced significant changes to some fundamental features of the LHC standard half-cell, composed of one quadrupole, 3 dipoles and a set of corrector magnets. A separate cryogenic distribution line was introduced, which was previously inside the main cryostat. The dipole length has been increased from 10 to 15 m and independent powering of the focusing and defocusing quadrupole magnets was chosen. Individual quench protection diodes were introduced in magnets interconnects and many auxiliary bus bars were added to feed in series the various families of correcting superconducting magnets. The various highly intricate basic systems such as: cryostats and cryogenics feeders, superconducting magnets and their electrical feeding and protection, vacuum beam screen and its cooling, support and alignment devices have been redesigned, taking into account the very tight space available. These space constraints are given by the necessity to have maximum integral bending field strength for maximum LHC energy, and the existing LHC tunnel. Finally, cryogenic and vacuum sectorisation have been introduced to reduce downtimes and facilitate commissioning.

  12. ORBIT FEEDBACK CONTROL FOR THE LHC Prototyping at the SPS

    CERN Document Server

    Steinhagen, Ralph J

    2004-01-01

    The Large Hadron Collider (LHC) is the next generation proton collider that is presently built at CERN. The LHC will be installed in the former LEP (Large Electron Positron Collider) tunnel. The presence of a high intensity beam in an environment of cryogenic magnets requires an excellent control of particle losses from the beam. Eventually the performance of the LHC may be limited by the ability to control the beam losses. The performance of the LHC cleaning system depends critically on the beam position stability. Ground motion, field and alignment imperfections and beam manipulations may cause orbit movements. The role of the future LHC Orbit Feedback System is the minimisation of closed orbit perturbations by periodically measuring and steering the transverse beam position back to its reference position. This diploma thesis focuses on the design and prototyping of an orbit feedback system at the SPS. The design is based on a separation of the steering problem into space and time. While the correction in s...

  13. A slice through a prototype LHC bending magnet

    CERN Multimedia

    Laurent Guiraud

    1998-01-01

    This slice through a prototype LHC magnet clearly shows the superconducting cable in several blocks around the central hole – the beam pipe in which the LHC’s accelerated beams will travel. Magnet design is crucial to the LHC’s success and this sample is among the first to be built to the final cable configuration.

  14. CERN confident of LHC start-up in 2007

    CERN Document Server

    Vanden Broeck, Renilde

    2007-01-01

    "Delegates attending the 140th meeting of CERN Council today heard a confident report from the Laboratory about the scheduled start-up of the world's highest energy particle accelerator, the Large Hadron Collier (LHC) in 2007. (1/2 page)

  15. CERN confident of LHC start-up in 2007

    CERN Multimedia

    2006-01-01

    "Delegates attending the 140th meeting of CERN Council today heard a confident report from the Laboratory about the scheduled start-up of the world's highest energy particle accelerator, the Large Hadron Collider (LHC) in 2007." (1/2 page)

  16. LHC Operation: Past and Future (1/3)

    CERN Multimedia

    CERN. Geneva

    2013-01-01

    After a successful first running period, LHC is now well into a two year shutdown for extensive consolidation. A pedagogical overview of the machine, its operating principles, its systems and underlying accelerator physics is presented. Performance past and future is discussed. (These lectures will be presented in three parts.)

  17. Le collisionneur LHC dans la tourmente: retard important en perspective

    CERN Multimedia

    Sacco, Laurent

    2007-01-01

    Bad news for particle physicist community: LHC, the biggest protons collider in the world, will not probably work in 2007. Supports of the superconductive magnetic quadrupoles, intended to focus the beams of protons in the accelerator, have just broken during preliminary tests. (1,5page)

  18. LHC Starts the Search for Sparticles in April

    CERN Multimedia

    2008-01-01

    The long expected CERN Large Hadron Collider will become operational somewhere this spring, and physicists all around the world can hardly wait to see what new discoveries it will bring. For example, whether the LHC accelerating particles towards each other at speeds close to that of light are able to prove the supersymmetry theory or not.

  19. CERN: LHC magnets

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    With test magnets for CERN's LHC proton-proton collider regularly attaining field strengths which show that 10 Tesla is not forbidden territory, attention turns to why and where quenches happen. If 'training' can be reduced, superconducting magnets become easier to commission

  20. Fully transparent LHC

    CERN Multimedia

    2008-01-01

    Thanks to the first real signals received from the LHC while in operation before the incident, the experiments are now set to make the best use of the data they have collected. Report from the LHCC open session.The September open session of the LHCC (LHC Experiments Committee) came just a few days after the incident that occurred at the LHC. The packed auditorium was a testament to the huge interest raised by Lyn Evans’ talk about the status of the machine and the plans for the future. After being told that the actual consequences of the incident will be clear only once Sector 3-4 has been warmed up, the audience focussed on the reports from the experiments. For the first time, the reports showed performance results of the various detectors with particles coming from the machine and not just from cosmic rays or tests and simulations. "The first days of LHC beam exceeded all expectations and the experiments made extensive and rapid use of the data they collected", says ...

  1. Higgs physics at LHC

    OpenAIRE

    Unal, G

    2006-01-01

    This is a review of Higgs physics at LHC. The topics covered are the search of the Standard Model Higgs boson (with emphasis on the low mass region), the measurements of the Higgs boson properties (mass, width, spin, CP and couplings) and the Higgs sector of the MSSM.

  2. Higgs physics at LHC

    Indian Academy of Sciences (India)

    The large hadron collider (LHC) and its detectors, ATLAS and CMS, are being built to study TeV scale physics, and to fully understand the electroweak symmetry breaking mechanism. The Monte-Carlo simulation results for the standard model and minimal super symmetric standard model Higgs boson searches and ...

  3. Electronics for LHC Experiments

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2004-07-01

    This document gathers the abstracts of most presentations made at this workshop on electronics for the large hadron collider (LHC) experiments. The presentations were arranged into 6 sessions: 1) electronics for tracker, 2) trigger electronics, 3) detector control systems, 4) data acquisition, 5) electronics for calorimeters and electronics for muons, and 6) links, power systems, grounding and shielding, testing and quality assurance.

  4. CERN: LHC magnets

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    1992-08-15

    With test magnets for CERN's LHC proton-proton collider regularly attaining field strengths which show that 10 Tesla is not forbidden territory, attention turns to why and where quenches happen. If 'training' can be reduced, superconducting magnets become easier to commission.

  5. Electronics for LHC Experiments

    International Nuclear Information System (INIS)

    2004-01-01

    This document gathers the abstracts of most presentations made at this workshop on electronics for the large hadron collider (LHC) experiments. The presentations were arranged into 6 sessions: 1) electronics for tracker, 2) trigger electronics, 3) detector control systems, 4) data acquisition, 5) electronics for calorimeters and electronics for muons, and 6) links, power systems, grounding and shielding, testing and quality assurance

  6. ATLAS. LHC experiments

    International Nuclear Information System (INIS)

    Anon.

    1995-01-01

    In Greek mythology, Atlas was a Titan who had to hold up the heavens with his hands as a punishment for having taken part in a revolt against the Olympians. For LHC, the ATLAS detector will also have an onerous physics burden to bear, but this is seen as a golden opportunity rather than a punishment. The major physics goal of CERN's LHC proton-proton collider is the quest for the long-awaited£higgs' mechanism which drives the spontaneous symmetry breaking of the electroweak Standard Model picture. The large ATLAS collaboration proposes a large general-purpose detector to exploit the full discovery potential of LHC's proton collisions. LHC will provide proton-proton collision luminosities at the aweinspiring level of 1034 cm2 s~1, with initial running in at 1033. The ATLAS philosophy is to handle as many signatures as possible at all luminosity levels, with the initial running providing more complex possibilities. The ATLAS concept was first presented as a Letter of Intent to the LHC Committee in November 1992. Following initial presentations at the Evian meeting (Towards the LHC Experimental Programme') in March of that year, two ideas for generalpurpose detectors, the ASCOT and EAGLE schemes, merged, with Friedrich Dydak (MPI Munich) and Peter Jenni (CERN) as ATLAS cospokesmen. Since the initial Letter of Intent presentation, the ATLAS design has been optimized and developed, guided by physics performance studies and the LHC-oriented detector R&D programme (April/May, page 3). The overall detector concept is characterized by an inner superconducting solenoid (for inner tracking) and large superconducting air-core toroids outside the calorimetry. This solution avoids constraining the calorimetry while providing a high resolution, large acceptance and robust detector. The outer magnet will extend over a length of 26 metres, with an outer diameter of almost 20 metres. The total weight of the detector is 7,000 tonnes. Fitted with its end

  7. Off-momentum collimation and cleaning in the energy ramp in the LHC

    CERN Document Server

    Quaranta, Elena; Giulini Castiglioni Agosteo, Stefano Luigi Maria

    This Master thesis work has been carried out at CERN in the framework of the LHC (Large Hadron Collider) Collimation project. The LHC is a two-beam proton collider, built to handle a stored energy of 360MJ for each beam. Since the energy deposition from particle losses could quench the superconducting magnets, a system of collimators has been installed in two cleaning insertions in the ring and in the experimental areas. The achievable LHC beam intensity is directly coupled to the beam loss rate and, consequently, to the cleaning eciency of the collimation system. This study analyses the collimation cleaning performance in dierent scenarios inside the accelerator. First, simulations are performed of the transverse losses in the LHC collimation system during the acceleration process. The results are compared with data taken during a dedicated session at the LHC machine. Simulations are also performed to predict the collimation eciency during future operation at higher energy. Furthermore, an investigation of t...

  8. Carpal Tunnel Syndrome

    Science.gov (United States)

    ... a passing cramp? It could be carpal tunnel syndrome. The carpal tunnel is a narrow passageway of ... three times more likely to have carpal tunnel syndrome than men. Early diagnosis and treatment are important ...

  9. Physics and technical development of accelerators

    International Nuclear Information System (INIS)

    2000-03-01

    About 90 registered participants delivered more than 40 scientific papers. A great part of these presentations were of general interest about running projects such as CIME accelerator at Ganil, IPHI (high intensity proton injector), ESRF (European source of synchrotron radiation), LHC (large hadron collider), ELYSE accelerator at Orsay, AIRIX, and VIVITRON tandem accelerator. Other presentations highlighted the latest technological developments of accelerator components: superconducting cavities, power klystrons, high current injectors..

  10. Status of the Large Hadron Collider (LHC)

    International Nuclear Information System (INIS)

    Evans, Lyndon R.

    2004-01-01

    The Large Hadron Collider (LHC), due to be commissioned in 2007, will provide particle physics with the first laboratory tool to access the energy frontier above 1 TeV. In order to achieve this, protons must be accelerated and stored at 7 TeV, colliding with an unprecedented luminosity of 10 34 cm -2 s -1 The 8.3 Tesla guide field is obtained using conventional NbTi technology cooled to below the lambda point of helium. The machine is now well into its installation phase, with first beam injection foreseen for spring 2007. A brief status report is given and future prospects are discussed. (orig.)

  11. The short straight sections for the LHC

    International Nuclear Information System (INIS)

    Bergot, J.B.; Coussy, E.; Dambre, P.; Ollivier, Y.; Reynet, D.; Vincent, D.; Rohmig, P.

    1999-01-01

    In 1995 a close collaboration between CERN, CEA and CNRS has been established for the design, proto-typing and follow-up of industrial series production of a sub-assembly of the Large Hadron Collider (LHC). In this frame, the design office of IPN's Accelerator R and D group has in charge one of these contracts concerning the 386 Short Straight Sections (SSS) and particularly: - the cryostat design; - the study of procedures and tool assembly; - the construction of two prototypes during the year 1999; - the industrialization and the production follow-up for the series SSS. This collaboration will last until the year 2004. (authors)

  12. Commissioning the cryogenic system of the first LHC sector

    International Nuclear Information System (INIS)

    Millet, F.; Claudet, S.; Ferlin, G.; Perin, A.; Riddone, G.; Serio, L.; Soubiran, M.; Tavian, L.; CERN; Ronayette, L.; GHMFL, Grenoble; Rabehl, R.; Fermilab

    2007-01-01

    The LHC machine, composed of eight sectors with superconducting magnets and accelerating cavities, requires a complex cryogenic system providing high cooling capacities (18 kW equivalent at 4.5 K and 2.4 W at 1.8 K per sector produced in large cold boxes and distributed via 3.3-km cryogenic transfer lines). After individual reception tests of the cryogenic subsystems (cryogen storages, refrigerators, cryogenic transfer lines and distribution boxes) performed since 2000, the commissioning of the cryogenic system of the first LHC sector has been under way since November 2006. After a brief introduction to the LHC cryogenic system and its specificities, the commissioning is reported detailing the preparation phase (pressure and leak tests, circuit conditioning and flushing), the cool-down sequences including the handling of cryogenic fluids, the magnet powering phase and finally the warm-up. Preliminary conclusions on the commissioning of the first LHC sector will be drawn with the review of the critical points already solved or still pending. The last part of the paper reports on the first operational experience of the LHC cryogenic system in the perspective of the commissioning of the remaining LHC sectors and the beam injection test

  13. The dance of the LHC magnets

    CERN Multimedia

    2003-01-01

    The dance of the blue magnets has begun. On 25 April, the first superconducting dipole magnet for the LHC made the trip from Building SM18, where it had been tested and assembled, to the Prévessin site, where it is now being stored. The next few months will see many of these exceptional convoys - in more ways than one - bringing the magnets along the Route de l'Europe to Prévessin for storage before they are lowered into the tunnel. CERN's impressive overhead travelling crane loading the 15-metre-long magnet onto a lorry.The start of the 10-km-an-hour journey to the Prévessin site. Infinite care is taken with the loading, transportation and unloading of these precious magnets.

  14. Tunneling technologies for the collider ring tunnels

    International Nuclear Information System (INIS)

    Frobenius, P.

    1989-01-01

    The Texas site chosen for the Superconducting Super Collider has been studied, and it has been determined that proven, conventional technology and accepted engineering practice are suitable for constructing the collider tunnels. The Texas National Research Laboratory Commission report recommended that two types of tunneling machines be used for construction of the tunnels: a conventional hard rock tunnel boring machine (TBM) for the Austin chalk and a double shielded, rotary TBM for the Taylor marl. Since the tunneling machines usually set the pace for the project, efficient planning, operation, and coordination of the tunneling system components will be critical to the schedule and cost of the project. During design, tunneling rate prediction should be refined by focusing on the development of an effective tunneling system and evaluating its capacity to meet or exceed the required schedules. 8 refs., 13 figs

  15. Theoretical Modeling and Experimental Investigation of the Thermal Performance of the LHC Prototype Lattice Cryostats

    CERN Document Server

    Riddone, G

    1997-01-01

    This thesis presents the thermal performance of the LHC (Large Hadron Collider) prototype cryostats both in steady-state and in transient conditions. LHC will be built in the 27 km LEP tunnel and will provide proton-proton collisions. It will make use of superconducting magnets operating in static bath of superfluid helium at 1.9 K. The thesis is mainly divided in three parts. The first part cont ains three chapters which present a brief overview of the LHC project. Part 1-Chapter 1 gives a short introduction to the LHC design layout and performance. Part 1-Chapter 2 refers to LHC cryogenic s ystem and describes the general architecture of the cryogenic plants, the temperature levels and the heat loads. The 50 m long LHC prototype half-cell contains one twin-bore quadrupole and four twin-a perture dipoles. In Part 1-Chapter 3 the design and construction of the prototype dipole and quadrupole cryostats are presented. The LHC prototype cryostats have integrated cryogenic lines, while the final LHC cryostats hav...

  16. LHC Nobel Symposium Proceedings

    Science.gov (United States)

    Ekelöf, Tord

    2013-12-01

    In the summer of 2012, a great discovery emerged at the Large Hadron Collider (LHC) at CERN in Geneva. A plethora of new precision data had already by then been collected by the ATLAS and CMS experiments at LHC, providing further extensive support for the validity of the Standard Model of particle physics. But what now appeared was the first evidence for what was not only the last unverified prediction of the Standard Model, but also perhaps the most decisive one: the prediction made already in 1964 of a unique scalar boson required by the theory of François Englert and Peter Higgs on how fundamental particles acquire mass. At that moment in 2012, it seemed particularly appropriate to start planning a gathering of world experts in particle physics to take stock of the situation and try to answer the challenging question: what next? By May 2013, when the LHC Nobel Symposium was held at the Krusenberg Mansion outside Uppsala in Sweden, the first signs of a great discovery had already turned into fully convincing experimental evidence for the existence of a scalar boson of mass about 125 GeV, having properties compatible with the 50-year-old prediction. And in October 2013, the evidence was deemed so convincing that the Swedish Royal Academy of Sciences awarded the Nobel Prize in Physics to Englert and Higgs for their pioneering work. At the same time the search at the LHC for other particles, beyond those predicted by the Standard Model, with heavier masses up to—and in some cases beyond—1 TeV, had provided no positive result. The triumph of the Standard Model seems resounding, in particular because the mass of the discovered scalar boson is such that, when identified with the Higgs boson, the Standard Model is able to provide predictions at energies as high as the Planck mass, although at the price of accepting that the vacuum would be metastable. However, even if there were some feelings of triumph, the ambience at the LHC Nobel Symposium was more one of

  17. The Radiation Tolerant Electronics for the LHC Cryogenic Controls: Basic Design and First Operational Experience

    CERN Document Server

    Casas-Cubillos, J; Rodríguez-Ruiz, M A

    2008-01-01

    The LHC optics is based in the extensive use of superconducting magnets covering 23 km inside the tunnel. The associated cryogenic system for keeping the magnets in nominal conditions is hence distributed all around the 27 km LHC tunnel and the cryogenic instrumentation submitted to the LHC radiation environment is composed of about 18’000 sensors and actuators. Radiation Tolerant (RadTol) electronics was designed and procured in order to keep the signals integrity against electromagnetic interference and to reduce cabling costs required in case of sending the analog signals into the 30 radiation protected areas. This paper presents the basic design, the qualification of the main RadTol components and the first operational results.

  18. The LHC Physics Centre at CERN

    CERN Document Server

    CERN Bulletin

    2010-01-01

    As the LHC goes on line for its first exploration of the new high-energy frontier, CERN is also getting ready to enhance the support it provides for the analysis and interpretation of the emerging data.    The LHC Physics Centre at CERN (LPCC) has started up over the past couple of months, beginning with a series of initiatives ranging from Workshops to lectures for students. More details about the LPCC will be featured in a forthcoming Bulletin article. In the meantime, you can consult the LPCC web page, now available at http://cern.ch/lpcc. This offers the high energy physics community a portal to the LPCC's activities, as well as to useful resources, tools and information about the LHC physics programme, the progress of accelerator operations, relevant workshops and events around the world, and much more. The LPCC will shortly begin issuing a weekly bulletin of its own, distributed by e-mail. Members of the CERN physics community and subscribers to the CERN Bulletin will receive the ...

  19. LHC interaction region quadrupole cryostat design

    International Nuclear Information System (INIS)

    Nicol, T.H.; Darve, Ch.; Huang, Y.; Page, T.M.

    2002-01-01

    The cryostat of a Large Hadron Collider (LHC) Interaction Region (IR) quadrupole magnet consists of all components of the inner triplet except the magnet assembly itself. It serves to support the magnet accurately and reliably within the vacuum vessel, to house all required cryogenic piping, and to insulate the cold mass from heat radiated and conducted from the environment. It must function reliably during storage, shipping and handling, normal magnet operation, quenches, and seismic excitations, and must be able to be manufactured at low cost. The major components of the cryostat are the vacuum vessel, thermal shield, multi-layer insulation system, cryogenic piping, and suspension system. The overall design of a cryostat for superconducting accelerator magnets requires consideration of fluid flow, proper selection of materials for their thermal and structural performance at both ambient and operating temperature, and knowledge of the environment to which the magnets will be subjected over the course of their expected operating lifetime. This paper describes the current LHC IR inner triplet quadrupole magnet cryostats being designed and manufactured at Fermilab as part of the US-LHC collaboration, and includes discussions on the structural and thermal considerations involved in the development of each of the major systems

  20. The LHC's suppliers come up trumps

    CERN Multimedia

    2006-01-01

    Four of the LHC Project's most exceptional suppliers have just been honoured in the fifth Golden Hadron awards ceremony. For the first time, a CERN team was among the prize-winners. The CERN main workshop (Mechanical and Materials Engineering group, TS/MME) received the Golden Hadron Award at the prize-giving ceremony held at the Globe. From left to right, Saïd Atieh (TS/MME), Vincent Vuillemin (TS/MME group leader), Michel Caccioppoli (TS/MME), Lyn Evans (LHC Project Leader), Marc Polini (TS/MME-MS section leader), Jean-Luc Gayraud (Cegelec), Jean-Paul Bacher (TS/MME-AS section leader) and Paolo Ciriani (head of the TS Department). Flexible, responsive, committed... all fitting adjectives to describe the recipients of the fifth Golden Hadron awards. The prizes, designed to honour the LHC Project's best suppliers, were awarded to a total of four suppliers, including two that are involved in the final accelerator assembly work: proof, if it were needed, that the project has now entered its final phase. Drak...