  1. Isar-2 nuclear power station twenty-five years

    International Nuclear Information System (INIS)

    Fischer, Erwin; Luginger, Markus

    2013-01-01

    The Isar-2 nuclear power station (KKI 2) began commercial power operation on April 9, 1988. In these past 25 years the plant generated a total of approx. 285 billion kWh of electricity. The annual electricity production of KKI 2 of approx. 12 billion kWh corresponds to a share of approx. 15 % in the cumulated Bavarian electricity production. This amount of electricity, theoretically, could supply some 3 million three person households, or meet two thirds of the electricity requirement of the Bavarian industry, for one year. In its 25 years of power operation the Isar-2 nuclear power plant has recorded the highest annual gross electricity production of all nuclear power plants in the world nine times so far. A plant performance as impressive as this necessitates a plant availability far above the average. This, in turn, is based on short revision times and faultfree plant operation. However, high plant safety and availability must not be taken for granted, but are the result of responsible, safety-minded plant operation combined with continuous plant optimization and permanent execution of comprehensive checks, inspections, and maintenance measures. Besides plant technology also organization and administration were permanently advanced and adapted to changing requirements so as to safeguard reliable, safe, and non-polluting plant operation.

  2. Emergency planning of the city of Munich with reference to nuclear facilities, especially the nuclear power stations Isar I and II, resp. the reactor in Garching

    International Nuclear Information System (INIS)

    1990-01-01

    During the hearing of Munich's city council of 13.7.1990 thirteen experts were heard on the following subjects: Hazard potential of Isar reactors and FRM reactor and appropriate radioactive waste transports; responsibilities in emergency planning. Some of the experts cannot visualize a major accident and propose not to cater for it. Shelters and evacuation are not planned for Munich, both solutions not being realizable for all inhabitants. Nuclear phaseout is seen by some as a measure of prevention. (HSCH) [de

  3. Distributed MIMO-ISAR Sub-image Fusion Method

    Directory of Open Access Journals (Sweden)

    Gu Wenkun

    2017-02-01

    Full Text Available The fast fluctuation associated with maneuvering a target’s radar cross-section often affects the imaging performance stability of traditional monostatic Inverse Synthetic Aperture Radar (ISAR. To address this problem, in this study, we propose an imaging method based on the fusion of sub-images of frequencydiversity-distributed multiple Input-Multiple Output-Inverse Synthetic Aperture Radar (MIMO-ISAR. First, we establish the analytic expression of a two-dimensional ISAR sub-image acquired by different channels of distributed MIMO-ISAR. Then, we derive the distance and azimuth distortion factors of the image acquired by the different channels. By compensating for the distortion of the ISAR image, we ultimately realize distributed MIMO-ISAR fusion imaging. Simulations verify the validity of this imaging method using distributed MIMO-ISAR.

  4. Decontamination of the reactor pressure vessel and further internals and auxiliary systems in the German boiling water reactor Isar-1; Dekontamination des RDB inkl. der Einbauten wie Dampftrockner und Wasserabscheider sowie der angeschlossenen Hilfssysteme im deutschen Siedewasserreaktor ISAR 1

    Energy Technology Data Exchange (ETDEWEB)

    Fischer, Michael; Sempere Belda, Luis; Basu, Ashim; Topf, Christian [AREVA GmbH, Erlangen (Germany). Abt. Chemistry Services; Erbacher, Thomas; Hiermer, Thomas; Schnurr, Bernhard; Appeldorn, Thomas van [E.ON Kernkraft GmbH, Kernkraftwerk ISAR, Essenbach (Germany). Abt. Maschinentechnik; Volkmann, Christian [ESG Engineering Services GmbH, Greifswald (Germany)

    2015-12-15

    The German nuclear power plant ISAR 1 (KKI 1), a 878 MWe boiling water reactor of KWU design, was shut down on March 17{sup th}, 2011. With the objective to minimize the plants activity inventory accompanied by the reduction of contact dose rates of systems and components the project 'decontamination of the RPV incl. steam dryer and water separator and the connected auxiliary systems' was implemented in the first quarter of 2015. One major focus within the project was the specific in-situ decontamination of the steam dryer.

  5. Ship dynamics for maritime ISAR imaging.

    Energy Technology Data Exchange (ETDEWEB)

    Doerry, Armin Walter

    2008-02-01

    Demand is increasing for imaging ships at sea. Conventional SAR fails because the ships are usually in motion, both with a forward velocity, and other linear and angular motions that accompany sea travel. Because the target itself is moving, this becomes an Inverse- SAR, or ISAR problem. Developing useful ISAR techniques and algorithms is considerably aided by first understanding the nature and characteristics of ship motion. Consequently, a brief study of some principles of naval architecture sheds useful light on this problem. We attempt to do so here. Ship motions are analyzed for their impact on range-Doppler imaging using Inverse Synthetic Aperture Radar (ISAR). A framework for analysis is developed, and limitations of simple ISAR systems are discussed.

  6. Target Identification Using Harmonic Wavelet Based ISAR Imaging

    Science.gov (United States)

    Shreyamsha Kumar, B. K.; Prabhakar, B.; Suryanarayana, K.; Thilagavathi, V.; Rajagopal, R.

    2006-12-01

    A new approach has been proposed to reduce the computations involved in the ISAR imaging, which uses harmonic wavelet-(HW) based time-frequency representation (TFR). Since the HW-based TFR falls into a category of nonparametric time-frequency (T-F) analysis tool, it is computationally efficient compared to parametric T-F analysis tools such as adaptive joint time-frequency transform (AJTFT), adaptive wavelet transform (AWT), and evolutionary AWT (EAWT). Further, the performance of the proposed method of ISAR imaging is compared with the ISAR imaging by other nonparametric T-F analysis tools such as short-time Fourier transform (STFT) and Choi-Williams distribution (CWD). In the ISAR imaging, the use of HW-based TFR provides similar/better results with significant (92%) computational advantage compared to that obtained by CWD. The ISAR images thus obtained are identified using a neural network-based classification scheme with feature set invariant to translation, rotation, and scaling.

  7. Measures to assess and to assure the integrity of RPV-internals at Isar, Unit 1 Nuclear Power Plant

    International Nuclear Information System (INIS)

    Erve, M.; Bouecke, R.; Leibold, F.; Marschke, D.; Senski, G.; Maier, V.

    1998-01-01

    As visual examinations carried out in autumn 1994 detected cracks in a German BWR plant due to intergranular stress corrosion cracking in several core shroud components manufactured from 1.4550 steel, precautionary examinations and assessments were performed for all other plants. In accordance with these analyses, it can be stated for Isar, Unit 1 that the heat treatment to which the components in question were subjected in the course of manufacture cannot have caused sensitization of the material, and that crack formation due to the damage mechanism primarily identified in the reactor pressure vessel internals at Wuergassen Nuclear Power Station need not be feared. Although the material and corrosion-chemical assessments performed to date did not give any indications for the other crack formation mechanisms that are theoretically relevant for reactor pressure vessel internals (IGSCC due to weld sensitization, IASCC), visual examinations with a limited scope will be carried out with the independent expert's agreement during the scheduled inservice inspections. The fluid-dynamic and structure-mechanical analyses showed that the individual components are subjected only to low loadings, even in the event of accidents, and that the safety objectives shutdown and residual heat removal can be fulfilled even in the case of large postulated cracks. The fracture-mechanics analyses indicated critical through-wall crack lengths which, however, can be promptly and reliably detected during random inservice inspections even when assuming stress corrosion cracking and irradiation-induced low-toughness material conditions. In addition, both the VGB and the Isar, Unit 1 licensee are pursuing further prophylactic measures such as alternative water chemistry modes and an appropriate repair and replacement concept. (author)

  8. ISAR imaging using the instantaneous range instantaneous Doppler method

    CSIR Research Space (South Africa)

    Wazna, TM

    2015-10-01

    Full Text Available In Inverse Synthetic Aperture Radar (ISAR) imaging, the Range Instantaneous Doppler (RID) method is used to compensate for the nonuniform rotational motion of the target that degrades the Doppler resolution of the ISAR image. The Instantaneous Range...

  9. Coherent Multistatic ISAR Imaging

    NARCIS (Netherlands)

    Dorp, Ph. van; Otten, M.P.G.; Verzeilberg, J.M.M.

    2012-01-01

    This paper presents methods for Coherent Multistatic Radar Imaging for Non Cooperative Target Recognition (NCTR) with a network of radar sensors. Coherent Multistatic Radar Imaging is based on an extension of existing monostatic ISAR algorithms to the multistatic environment. The paper describes the

  10. Geometric shapes inversion method of space targets by ISAR image segmentation

    Science.gov (United States)

    Huo, Chao-ying; Xing, Xiao-yu; Yin, Hong-cheng; Li, Chen-guang; Zeng, Xiang-yun; Xu, Gao-gui

    2017-11-01

    The geometric shape of target is an effective characteristic in the process of space targets recognition. This paper proposed a method of shape inversion of space target based on components segmentation from ISAR image. The Radon transformation, Hough transformation, K-means clustering, triangulation will be introduced into ISAR image processing. Firstly, we use Radon transformation and edge detection to extract space target's main body spindle and solar panel spindle from ISAR image. Then the targets' main body, solar panel, rectangular and circular antenna are segmented from ISAR image based on image detection theory. Finally, the sizes of every structural component are computed. The effectiveness of this method is verified using typical targets' simulation data.

  11. `Mountain Hut` promotion programme of Isar Amperwerke - interim project report; Foerderprogramm Berghuetten der Isar-Amperwerke - Projektstatus

    Energy Technology Data Exchange (ETDEWEB)

    Pfeiffer, G.; Reiner, H. [Isar-Amperwerke AG, Abt. ETK, Muenchen (Germany)

    1997-12-31

    The purpose of the ``Mountain Hut`` promotion programme is to accelerate the conversion of mountain hut power supply systems to renewables. Under this programme, which exclusively promotes the installation of renewable energy systems (hydropower, solar energy, wind power, biomass), Isar Amperwerke contributes up to a maximum of 50% of the investment costs. The present article briefly reports on four projects that have already been realised. (HW) [Deutsch] Mit dem Foerderprogramm `Berghuetten` soll die Stromversorgung von Berghuetten staerker auf erneuerbare Energietraeger umgestellt werden. Die Zuschussrate der Isar-Amper-Werke betraegt dabei maximal 50%, wobei nur regenerative Energien (Wasserkraft, Solarenergie, Windkraft und Biomasse) gefoerdert werden. Der vorliegende Beitrag gibt einen Ueberblick ueber vier schon realisierte Projekte. (HW)

  12. Towards Inverse Synthetic Aperture Radar (ISAR) for small sea vessels

    CSIR Research Space (South Africa)

    Abdul Gaffar, MY

    2006-12-01

    Full Text Available Aperture Radar (ISAR) for Small Sea Vessels M.Y. Abdul Gaffar Council for Scientific and Industrial Research University of Cape Town Slide 2 © CSIR 2006 www.csir.co.za What is ISAR? • Technique that produces cross range...

  13. Resolution and Micro-Doppler Effect in Bi-ISAR System (in English

    Directory of Open Access Journals (Sweden)

    Deng Dong-hu

    2013-06-01

    Full Text Available Compared to the monostatic radar, bistatic radar has many special characteristics because of its spatial complexity. Bistatic Inverse Synthetic Aperture Radar (Bi-ISAR can be employed as a radar imaging tool for obtaining non-cooperative target images. In this study, we first analyze the range and azimuth resolution of a Bi-ISAR system. To analyze this azimuth resolution and its spatial-variety characteristic, a definition called con-Doppler bandwidth is introduced, which helps overcome the difficulty of the target’s viewing angle diversity calculation. Then, a detailed investigation is conducted to study the micro-Doppler effect caused by the vibration and the rotation of the target in the Bi-ISAR system. By comparing the difference in the micro-Doppler effect between the Bi-ISAR system and the Mono-ISAR system, we modify the extended Hough transform to extract the real micro-motion features of the targets. Finally, we provide some simulation results to validate the theoretical derivation and to illustrate the effectiveness of the proposed method.

  14. Technology, safety and costs of decommissioning nuclear reactors at multiple-reactor stations

    International Nuclear Information System (INIS)

    Wittenbrock, N.G.

    1982-01-01

    Safety and cost information is developed for the conceptual decommissioning of large (1175-MWe) pressurized water reactors (PWR) and large (1155-MWe) boiling water reactors (BWR) at multiple-reactor stations. Three decommissioning alternatives are studied: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). Safety and costs of decommissioning are estimated by determining the impact of probable features of multiple-reactor-station operation that are considered to be unavailable at a single-reactor station, and applying these estimated impacts to the decommissioning costs and radiation doses estimated in previous PWR and BWR decommissioning studies. The multiple-reactor-station features analyzed are: the use of interim onsite nuclear waste storage with later removal to an offsite waste disposal facility, the use of permanent onsite nuclear waste disposal, the dedication of the site to nuclear power generation, and the provision of centralized services

  15. Performance limits for maritime Inverse Synthetic Aperture Radar (ISAR)

    Energy Technology Data Exchange (ETDEWEB)

    Doerry, Armin Walter [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2013-11-01

    The performance of an Inverse Synthetic Aperture Radar (ISAR) system depends on a variety of factors, many which are interdependent in some manner. In this report we specifically examine ISAR as applied to maritime targets (e.g. ships). It is often difficult to get your arms around the problem of ascertaining achievable performance limits, and yet those limits exist and are dictated by physics. This report identifies and explores those limits, and how they depend on hardware system parameters and environmental conditions. Ultimately, this leads to a characterization of parameters that offer optimum performance for the overall ISAR system. While the information herein is not new to the literature, its collection into a single report hopes to offer some value in reducing the seek time.

  16. ISAR Imaging of Maneuvering Targets Based on the Modified Discrete Polynomial-Phase Transform

    Directory of Open Access Journals (Sweden)

    Yong Wang

    2015-09-01

    Full Text Available Inverse synthetic aperture radar (ISAR imaging of a maneuvering target is a challenging task in the field of radar signal processing. The azimuth echo can be characterized as a multi-component polynomial phase signal (PPS after the translational compensation, and the high quality ISAR images can be obtained by the parameters estimation of it combined with the Range-Instantaneous-Doppler (RID technique. In this paper, a novel parameters estimation algorithm of the multi-component PPS with order three (cubic phase signal-CPS based on the modified discrete polynomial-phase transform (MDPT is proposed, and the corresponding new ISAR imaging algorithm is presented consequently. This algorithm is efficient and accurate to generate a focused ISAR image, and the results of real data demonstrate the effectiveness of it.

  17. The NPP Isar comprehensive Aging Management Program

    International Nuclear Information System (INIS)

    Zander, Andre; Ertl, Stefan

    2012-01-01

    The majority of System, Structure and Components (SSC) in a nuclear power plants are designed to experience a service life, which is far above the intended design life. In most cases, only a small percentage of SSCs are subject to significant aging effects, which may affect the integrity or the function of the component. The process of aging management (AM) has the objective to monitor and control degradation effects which may compromise safety functions of the plant. And furthermore, to ensure, that testing and maintenance programs sufficiently provide preventive measures to control degradation effects. Safety-related aspects and the targeted high availability of the power plant as well as the requirements stipulated by German regulatory authorities prompted the operator of NPP ISAR to introduce an aging surveillance program. The NPP Isar as well as the German NPPs has to be following in the scope of aging management the KTA 1403 guideline. The NPP Isar surveillance program based on the KTA 1403 guideline covers the following aspects: - Scoping and screening of safety relevant Systems, Structures and Components (SSC); - Identification of possible degradation mechanisms for safety relevant SSC; - Ensure, that testing and maintenance programs sufficiently provide preventive measures to control degradation effects; - Transferability check of industry experience (internal and external events); - Annual preparation of an AM status report. (author)

  18. Sensitivity of Attitude Determination on the Model Assumed for ISAR Radar Mappings

    Science.gov (United States)

    Lemmens, S.; Krag, H.

    2013-09-01

    Inverse synthetic aperture radars (ISAR) are valuable instrumentations for assessing the state of a large object in low Earth orbit. The images generated by these radars can reach a sufficient quality to be used during launch support or contingency operations, e.g. for confirming the deployment of structures, determining the structural integrity, or analysing the dynamic behaviour of an object. However, the direct interpretation of ISAR images can be a demanding task due to the nature of the range-Doppler space in which these images are produced. Recently, a tool has been developed by the European Space Agency's Space Debris Office to generate radar mappings of a target in orbit. Such mappings are a 3D-model based simulation of how an ideal ISAR image would be generated by a ground based radar under given processing conditions. These radar mappings can be used to support a data interpretation process. E.g. by processing predefined attitude scenarios during an observation sequence and comparing them with actual observations, one can detect non-nominal behaviour. Vice versa, one can also estimate the attitude states of the target by fitting the radar mappings to the observations. It has been demonstrated for the latter use case that a coarse approximation of the target through an 3D-model is already sufficient to derive the attitude information from the generated mappings. The level of detail required for the 3D-model is determined by the process of generating ISAR images, which is based on the theory of scattering bodies. Therefore, a complex surface can return an intrinsically noisy ISAR image. E.g. when many instruments on a satellite are visible to the observer, the ISAR image can suffer from multipath reflections. In this paper, we will further analyse the sensitivity of the attitude fitting algorithms to variations in the dimensions and the level of detail of the underlying 3D model. Moreover, we investigate the ability to estimate the orientations of different

  19. Using image quality measures and features to choose good images for classification of ISAR imagery

    CSIR Research Space (South Africa)

    Steyn, JM

    2014-10-01

    Full Text Available the quality measures and to determine the minimum dwell-time for ISAR image formation. Keywords—ISAR (inverse synthetic aperture radar), Dwell-time, Quality Measure, Image Contrast, Image Entropy, SNR (signal-to-noise ratio), Maritime Vessels ...

  20. Adaptive ISAR Imaging of Maneuvering Targets Based on a Modified Fourier Transform.

    Science.gov (United States)

    Wang, Binbin; Xu, Shiyou; Wu, Wenzhen; Hu, Pengjiang; Chen, Zengping

    2018-04-27

    Focusing on the inverse synthetic aperture radar (ISAR) imaging of maneuvering targets, this paper presents a new imaging method which works well when the target's maneuvering is not too severe. After translational motion compensation, we describe the equivalent rotation of maneuvering targets by two variables-the relative chirp rate of the linear frequency modulated (LFM) signal and the Doppler focus shift. The first variable indicates the target's motion status, and the second one represents the possible residual error of the translational motion compensation. With them, a modified Fourier transform matrix is constructed and then used for cross-range compression. Consequently, the imaging of maneuvering is converted into a two-dimensional parameter optimization problem in which a stable and clear ISAR image is guaranteed. A gradient descent optimization scheme is employed to obtain the accurate relative chirp rate and Doppler focus shift. Moreover, we designed an efficient and robust initialization process for the gradient descent method, thus, the well-focused ISAR images of maneuvering targets can be achieved adaptively. Human intervention is not needed, and it is quite convenient for practical ISAR imaging systems. Compared to precedent imaging methods, the new method achieves better imaging quality under reasonable computational cost. Simulation results are provided to validate the effectiveness and advantages of the proposed method.

  1. Eco-audit at the site of the nuclear power plants Isar 1 and Isar 2

    International Nuclear Information System (INIS)

    Brosche, D.

    2000-01-01

    The voluntary eco-audits for the nuclear power plants Isar 1 and 2 were the first ones for a nuclear power plant in Germany under the Council Eco Regulation of the European Commission and have shown that the environmental protection is actively practiced in accordance with the environmental policy of Bayernwerk AG. With the early integration of all partners and a careful planning, such audits can be performed efficiently and at a reasonable expenditure. (orig.) [de

  2. Energy balance and efficiency of power stations with a pulsed Tokamak reactor

    International Nuclear Information System (INIS)

    Davenport, P.A.; Mitchell, J.T.D.; Darvas, J.; Foerster, S.; Sack, B.

    1976-06-01

    The energy balance of a fusion power station based on the TOKAMAK concept is examined with the aid of a model comprising three distinct elements: the reactor, the energy converter and the reactor operation equipment. The efficiency of each element is expressed in terms of the various energy flows and the product of these efficiencies gives the net station efficiency. The analysis takes account of pulsed operation and has general applicability. Numerical values for the net station efficiency are derived from detailed estimates of the energy flows for a TOKAMAK reactor and its auxiliary equipment operating with advanced energy converters. The derivation of these estimates is given in eleven appendices. The calculated station efficiencies span ranges similar to those quoted for the current generation of fission reactors, though lower than those predicted for HTGR and LMFBR stations. Credible parameter domains for pulsed TOKAMAK operation are firmly delineated and factors inimical to improved performance are indicated. It is concluded that the net thermal efficiency of a TOKAMAK reactor power station based on present designs and using advanced thermal converters will be approximately 0.3 and is unlikely to exceed 0.33. (orig.) [de

  3. A time domain phase-gradient based ISAR autofocus algorithm

    CSIR Research Space (South Africa)

    Nel, W

    2011-10-01

    Full Text Available . Results on simulated and measured data show that the algorithm performs well. Unlike many other ISAR autofocus techniques, the algorithm does not make use of several computationally intensive iterations between the data and image domains as part...

  4. Decommissioning of multiple-reactor stations: facilitation by sequential decommissioning

    International Nuclear Information System (INIS)

    Moore, E.B.; Smith, R.I.; Wittenbrock, N.G.

    1982-01-01

    Reductions in cost and radiation dose can be achieved for decommissionings at multiple reactor stations because of factors not necessarily present at a single reactor station: reactors of similar design, the opportunity for sequential decommissioning, a site dedicated to nuclear power generation, and the option of either interim or permanent low-level radioactive waste storage facilities onsite. The cost and radiation dose reductions occur because comprehensive decommissioning planning need only be done once, because the labor force is stable and need only be trained once, because there is less handling of radioactive wastes, and because central stores, equipment, and facilities may be used. The cost and radiation dose reductions are sensitive to the number and types of reactors on the site, and to the alternatives selected for decommissioning. 3 tables

  5. Quality measures for HRR alignment based ISAR imaging algorithms

    CSIR Research Space (South Africa)

    Janse van Rensburg, V

    2013-05-01

    Full Text Available Some Inverse Synthetic Aperture Radar (ISAR) algorithms form the image in a two-step process of range alignment and phase conjugation. This paper discusses a comprehensive set of measures used to quantify the quality of range alignment, with the aim...

  6. ISAR Imaging of Ship Targets Based on an Integrated Cubic Phase Bilinear Autocorrelation Function

    Directory of Open Access Journals (Sweden)

    Jibin Zheng

    2017-03-01

    Full Text Available For inverse synthetic aperture radar (ISAR imaging of a ship target moving with ocean waves, the image constructed with the standard range-Doppler (RD technique is blurred and the range-instantaneous-Doppler (RID technique has to be used to improve the image quality. In this paper, azimuth echoes in a range cell of the ship target are modeled as noisy multicomponent cubic phase signals (CPSs after the motion compensation and a RID ISAR imaging algorithm is proposed based on the integrated cubic phase bilinear autocorrelation function (ICPBAF. The ICPBAF is bilinear and based on the two-dimensionally coherent energy accumulation. Compared to five other estimation algorithms, the ICPBAF can acquire higher cross term suppression and anti-noise performance with a reasonable computational cost. Through simulations and analyses with the synthetic model and real radar data, we verify the effectiveness of the ICPBAF and corresponding RID ISAR imaging algorithm.

  7. Distributed ISAR Subimage Fusion of Nonuniform Rotating Target Based on Matching Fourier Transform.

    Science.gov (United States)

    Li, Yuanyuan; Fu, Yaowen; Zhang, Wenpeng

    2018-06-04

    In real applications, the image quality of the conventional monostatic Inverse Synthetic Aperture Radar (ISAR) for the maneuvering target is subject to the strong fluctuation of Radar Cross Section (RCS), as the target aspect varies enormously. Meanwhile, the maneuvering target introduces nonuniform rotation after translation motion compensation which degrades the imaging performance of the conventional Fourier Transform (FT)-based method in the cross-range dimension. In this paper, a method which combines the distributed ISAR technique and the Matching Fourier Transform (MFT) is proposed to overcome these problems. Firstly, according to the characteristics of the distributed ISAR, the multiple channel echoes of the nonuniform rotation target from different observation angles can be acquired. Then, by applying the MFT to the echo of each channel, the defocused problem of nonuniform rotation target which is inevitable by using the FT-based imaging method can be avoided. Finally, after preprocessing, scaling and rotation of all subimages, the noncoherent fusion image containing all the RCS information in all channels can be obtained. The accumulation coefficients of all subimages are calculated adaptively according to the their image qualities. Simulation and experimental data are used to validate the effectiveness of the proposed approach, and fusion image with improved recognizability can be obtained. Therefore, by using the distributed ISAR technique and MFT, subimages of high-maneuvering target from different observation angles can be obtained. Meanwhile, by employing the adaptive subimage fusion method, the RCS fluctuation can be alleviated and more recognizable final image can be obtained.

  8. Station blackout with reactor coolant pump seal leakage

    International Nuclear Information System (INIS)

    Evinay, A.

    1993-01-01

    The U.S. Nuclear Regulatory Commission (NRC) amended its regulations in 10CFR50 with the addition of a new section, 50.63, open-quotes Loss of All Alternating Current Power.close quotes The objective of these requirements is to ensure that all nuclear plants have the capability to withstand a station blackout (SBO) and maintain adequate reactor core cooling and containment integrity for a specified period of time. The NRC also issued Regulatory Guide (RG) 1.155, open-quotes Station Blackout,close quotes to provide guidance for meeting the requirements of 10CFR50.63. Concurrent with RG-1.155, the Nuclear Utility Management and Resources Council (NUMARC) has developed NUMARC 87-00 to address SBO-coping duration and capabilities at light water reactors. Licensees are required to submit a topical report based on NUMARC 87-00 guidelines, to demonstrate compliance with the SBO rule. One of the key compliance criteria is the ability of the plant to maintain adequate reactor coolant system (RCS) inventory to ensure core cooling for the required coping duration, assuming a leak rate of 25 gal/min per reactor coolant pump (RCP) seal in addition to technical specification (TS) leak rate

  9. Quaternion-based transformation for extraction of image-generating Doppler for ISAR

    CSIR Research Space (South Africa)

    Abdul Gaffar, MY

    2008-10-01

    Full Text Available contributing motion that is useful to the ISAR imaging process; the contributing motion consists of the Doppler generating axis and the effective angle of rotation. This letter presents a quaternion-based transformation that converts measured attitude...

  10. A Novel Adaptive Joint Time Frequency Algorithm by the Neural Network for the ISAR Rotational Compensation

    Directory of Open Access Journals (Sweden)

    Zisheng Wang

    2018-02-01

    Full Text Available We propose a novel adaptive joint time frequency algorithm combined with the neural network (AJTF-NN to focus the distorted inverse synthetic aperture radar (ISAR image. In this paper, a coefficient estimator based on the artificial neural network (ANN is firstly developed to solve the time-consuming rotational motion compensation (RMC polynomial phase coefficient estimation problem. The training method, the cost function and the structure of ANN are comprehensively discussed. In addition, we originally propose a method to generate training dataset sourcing from the ISAR signal models with randomly chosen motion characteristics. Then, prediction results of the ANN estimator is used to directly compensate the ISAR image, or to provide a more accurate initial searching range to the AJTF for possible low-performance scenarios. Finally, some simulation models including the ideal point scatterers and a realistic Airbus A380 are employed to comprehensively investigate properties of the AJTF-NN, such as the stability and the efficiency under different signal-to-noise ratios (SNRs. Results show that the proposed method is much faster than other prevalent improved searching methods, the acceleration ratio are even up to 424 times without the deterioration of compensated image quality. Therefore, the proposed method is potential to the real-time application in the RMC problem of the ISAR imaging.

  11. Station blackout core damage frequency in an advanced nuclear reactor

    International Nuclear Information System (INIS)

    Carvalho, Luiz Sergio de

    2004-01-01

    Even though nuclear reactors are provided with protection systems so that they can be automatically shut down in the event of a station blackout, the consequences of this event can be severe. This is because many safety systems that are needed for removing residual heat from the core and for maintaining containment integrity, in the majority of the nuclear power plants, are AC dependent. In order to minimize core damage frequency, advanced reactor concepts are being developed with safety systems that use natural forces. This work shows an improvement in the safety of a small nuclear power reactor provided by a passive core residual heat removal system. Station blackout core melt frequencies, with and without this system, are both calculated. The results are also compared with available data in the literature. (author)

  12. Advances in commercial heavy water reactor power stations

    International Nuclear Information System (INIS)

    Brooks, G.L.

    1987-01-01

    Generating stations employing heavy water reactors have now firmly established an enviable record for reliable, economic electricity generation. Their designers recognize, however, that further improvements are both possible and necessary to ensure that this reactor type remains attractively competitive with alternative nuclear power systems and with fossil-fuelled generation plants. This paper outlines planned development thrusts in a number of important areas, viz., capital cost reduction, advanced fuel cycles, safety, capacity factor, life extension, load following, operator aida, and personnel radiation exposure. (author)

  13. Investigation of 3-D RCS Image formation of ships using ISAR

    CSIR Research Space (South Africa)

    Lord, RT

    2006-05-01

    Full Text Available Conventional Inverse Synthetic Aperture Radar (ISAR) utilises the rotational motion of a target such as a ship or an aircraft to obtain a 2-D image of the target’s radar cross section (RCS) profile from a coherent radar system. This concept can...

  14. Application of radon transforms and time-frequency representations to ISAR imagery

    NARCIS (Netherlands)

    Steeghs, T.P.H.; Gelsema, S.J.

    2003-01-01

    The use of ISAR imagery for Automatic Target Recognition is seriously hampered by the difficulty of target motion compensation. Phase perturbations that result from target maneuvers during the processing interval need to be corrected for. In a previous paper, we demonstrated the use of the local

  15. Culham conceptual Tokamak reactor MkII. Conceptual layout of buildings for a twin reactor power station

    International Nuclear Information System (INIS)

    Guthrie, J.A.S.; Harding, N.H.

    1981-01-01

    This paper discusses the conceptual design of the nuclear complex of a 2400 MWe twin fusion reactor power station utilising common services and a single containment building. The design is based upon environmental and maintenance logistical requirements, the provision of adequate storage, workshop and construction facilities and the constraints imposed by the geometry of the main and auxiliary reactor coolant systems. (author)

  16. A Parasitic Array Receiver for ISAR Imaging of Ship Targets Using a Coastal Radar

    Directory of Open Access Journals (Sweden)

    Fabrizio Santi

    2016-01-01

    Full Text Available The detection and identification of ship targets navigating in coastal areas are essential in order to prevent maritime accidents and to take countermeasures against illegal activities. Usually, coastal radar systems are employed for the detection of vessels, whereas noncooperative ship targets as well as ships not equipped with AIS transponders can be identified by means of dedicated active radar imaging system by means of ISAR processing. In this work, we define a parasitic array receiver for ISAR imaging purposes based on the signal transmitted by an opportunistic coastal radar over its successive scans. In order to obtain the proper cross-range resolution, the physical aperture provided by the array is combined with the synthetic aperture provided by the target motion. By properly designing the array of passive devices, the system is able to correctly observe the signal reflected from the ships over successive scans of the coastal radar. Specifically, the upper bounded interelement spacing provides a correct angular sampling accordingly to the Nyquist theorem and the lower bounded number of elements of the array ensures the continuity of the observation during multiple scans. An ad hoc focusing technique has been then proposed to provide the ISAR images of the ships. Simulated analysis proved the effectiveness of the proposed system to provide top-view images of ship targets suitable for ATR procedures.

  17. Tracking of Range and Azimuth for Continuous Imaging of Marine Target in Monopulse ISAR with Wideband Echoes

    Directory of Open Access Journals (Sweden)

    Junhao Xie

    2016-01-01

    Full Text Available Real-time tracking of maneuvering targets is the prerequisite for continuous imaging of moving targets in inverse synthetic aperture radar (ISAR. In this paper, the range and azimuth tracking (RAT method with wideband radar echoes is first presented for a mechanical scanning monopulse ISAR, which is regarded as the simplest phased array unit due to the two antenna feeds. To relieve the estimation fluctuation and poor robustness of the RAT method with a single snapshot, a modified range and azimuth tracking approach based on centroid algorithm (RATCA with forgotten factor and multiple echoes is then proposed. The performances of different forgotten factors are investigated. Both theoretical analysis and experimental results demonstrate that RATCA is superior to RAT method. Particularly, when target echo is missing occasionally, RAT method fails while RATCA still keeps good performance. The potential of continuous imaging with shipborne ISAR is verified by experimental results. With minor modification, the method proposed in this paper can be potentially applied in the phased array radar.

  18. Nuclear power station with nuclear reactor accommodated largely secure against catastrophes

    International Nuclear Information System (INIS)

    Rosen, O.

    1987-01-01

    If the nuclear reactor is installed underground near the power station unit, then danger to the environment due to radiation contamination can be largely or nearly completely prevented by a covering of constant thickness or by a covering which can be installed by a catastrophic accident. The extinguishing of a burning reactor is also relatively simple for a reactor accommodated in a pit. The above-mentioned measures can be used individually or combined. (orig./HP) [de

  19. Reactor coolant pump shaft seal stability during station blackout

    International Nuclear Information System (INIS)

    Rhodes, D.B.; Hill, R.C.; Wensel, R.G.

    1987-05-01

    Results are presented from an investigation into the behavior of Reactor Coolant Pump shaft seals during a potential station blackout (loss of all ac power) at a nuclear power plant. The investigation assumes loss of cooling to the seals and focuses on the effect of high temperature on polymer seals located in the shaft seal assemblies, and the identification of parameters having the most influence on overall hydraulic seal performance. Predicted seal failure thresholds are presented for a range of station blackout conditions and shaft seal geometries

  20. Reactor coolant pump shaft seal stability during station blackout

    Energy Technology Data Exchange (ETDEWEB)

    Rhodes, D B; Hill, R C; Wensel, R G

    1987-05-01

    Results are presented from an investigation into the behavior of Reactor Coolant Pump shaft seals during a potential station blackout (loss of all ac power) at a nuclear power plant. The investigation assumes loss of cooling to the seals and focuses on the effect of high temperature on polymer seals located in the shaft seal assemblies, and the identification of parameters having the most influence on overall hydraulic seal performance. Predicted seal failure thresholds are presented for a range of station blackout conditions and shaft seal geometries.

  1. A signature correlation study of ground target VHF/UHF ISAR imagery

    Science.gov (United States)

    Gatesman, Andrew J.; Beaudoin, Christopher J.; Giles, Robert H.; Kersey, William T.; Waldman, Jerry; Carter, Steve; Nixon, William E.

    2003-09-01

    VV and HH-polarized radar signatures of several ground targets were acquired in the VHF/UHF band (171-342 MHz) by using 1/35th scale models and an indoor radar range operating from 6 to 12 GHz. Data were processed into medianized radar cross sections as well as focused, ISAR imagery. Measurement validation was confirmed by comparing the radar cross section of a test object with a method of moments radar cross section prediction code. The signatures of several vehicles from three vehicle classes (tanks, trunks, and TELs) were measured and a signature cross-correlation study was performed. The VHF/UHF band is currently being exploited for its foliage penetration ability, however, the coarse image resolution which results from the relatively long radar wavelengths suggests a more challenging target recognition problem. One of the study's goals was to determine the amount of unique signature content in VHF/UHF ISAR imagery of military ground vehicles. Open-field signatures are compared with each other as well as with simplified shapes of similar size. Signatures were also acquired on one vehicle in a variety of configurations to determine the impact of monitor target variations on the signature content at these frequencies.

  2. Examination policy concerning the additional installation of No. 3 and No. 4 reactors in Takahama Nuclear Power Station and No. 3 and No. 4 reactors in Fukushima No. 2 Nuclear Power Station

    International Nuclear Information System (INIS)

    1980-01-01

    The Nuclear Safety Commission decided the annual examination policy on the modification of reactor installation in Takahama Nuclear Power Station to construct No. 3 and No. 4 reactors inquired under date of November 26, 1979, by the Minister of International Trade and Industry, so that the examination results of the accident in Three Mile Island nuclear power station are reflected to the examination for the purpose of improving reactor safety. The examination results of the accident in Three Mile Island power station are being investigated by the Committee on Examination of Reactor Safety, based on the policy shown in ''On the second report of the special committee examining the accident in a nuclear power station in the U.S.'' determined by the Nuclear Safety Commission under date of September 13, 1979. Though the Committee will further clarify the past guideline about the items concerning the criteria, design and operation management, the Committee decided the tentative policy to reflect it to safety examination. Further, a table is attached, in which 52 items to be reflected to the security measures are classified from the viewpoint of necessity to reflect them to the final examination. This table includes 13 items of criteria and examination, 7 items related to design, 10 items related to operation management, 10 antidisaster items, and 12 items related to safety research. (Wakatsuki, Y.)

  3. Remerschen nuclear power station with BBR pressurized water reactor

    International Nuclear Information System (INIS)

    Hoffmann, J.P.

    1975-01-01

    On the basis of many decades of successful cooperation in the electricity supply sector with the German RWE utility, the Grand Duchy of Luxemburg and RWE jointly founded Societe Luxembourgeoise d'Energie Nucleaire S.A. (SENU) in 1974 in which each of the partners holds a fifty percent interest. SENU is responsible for planning, building and operating this nuclear power station. Following an international invitation for bids on the delivery and turnkey construction of a nuclear power station, the consortium of the German companies of Brown, Boveri and Cie. AG (BBC), Babcock - Brown Boveri Reaktor GmbH (BBR) and Hochtief AG (HT) received a letter of intent for the purchase of a 1,300 MW nuclear power station equipped with a pressurized water reactor. The 1,300 MW station of Remerschen will be largely identical with the Muelheim-Kaerlich plant under construction by the same consortium near Coblence on the River Rhine since early 1975. According to present scheduling, the Remerschen nuclear power station could start operation in 1981. (orig.) [de

  4. Development of the fuel-cycle costs in nuclear power stations with light-water reactors

    International Nuclear Information System (INIS)

    Brosch, R.; Moraw, G.; Musil, G.; Schneeberger, M.

    1976-01-01

    The authors investigate the fuel-cycle costs in nuclear power stations with light-water reactors in the Federal Republic of Germany in the years 1966 to 1976. They determine the effect of the price development for the individual components of the nuclear fuel cycle on the fuel-cycle costs averaged over the whole power station life. Here account is taken also of inflation rates and the change in the DM/US $ parity. In addition they give the percentage apportionment of the fuel-cycle costs. The authors show that real fuel-cycle costs for nuclear power stations with light-water reactors in the Federal Republic of Germany have risen by 11% between 1966 and 1976. This contradicts the often repeated reproach that fuel costs in nuclear power stations are rising very steeply and are no longer competitive. (orig.) [de

  5. Reactor Vessel and Reactor Vessel Internals Segmentation at Zion Nuclear Power Station - 13230

    Energy Technology Data Exchange (ETDEWEB)

    Cooke, Conrad; Spann, Holger [Siempelkamp Nuclear Services: 5229 Sunset Blvd., (Suite M), West Columbia, SC, 29169 (United States)

    2013-07-01

    Zion Nuclear Power Station (ZNPS) is a dual-unit Pressurized Water Reactor (PWR) nuclear power plant located on the Lake Michigan shoreline, in the city of Zion, Illinois approximately 64 km (40 miles) north of Chicago, Illinois and 67 km (42 miles) south of Milwaukee, Wisconsin. Each PWR is of the Westinghouse design and had a generation capacity of 1040 MW. Exelon Corporation operated both reactors with the first unit starting production of power in 1973 and the second unit coming on line in 1974. The operation of both reactors ceased in 1996/1997. In 2010 the Nuclear Regulatory Commission approved the transfer of Exelon Corporation's license to ZionSolutions, the Long Term Stewardship subsidiary of EnergySolutions responsible for the decommissioning of ZNPS. In October 2010, ZionSolutions awarded Siempelkamp Nuclear Services, Inc. (SNS) the contract to plan, segment, remove, and package both reactor vessels and their respective internals. This presentation discusses the tools employed by SNS to remove and segment the Reactor Vessel Internals (RVI) and Reactor Vessels (RV) and conveys the recent progress. SNS's mechanical segmentation tooling includes the C-HORCE (Circumferential Hydraulically Operated Cutting Equipment), BMT (Bolt Milling Tool), FaST (Former Attachment Severing Tool) and the VRS (Volume Reduction Station). Thermal segmentation of the reactor vessels will be accomplished using an Oxygen- Propane cutting system. The tools for internals segmentation were designed by SNS using their experience from other successful reactor and large component decommissioning and demolition (D and D) projects in the US. All of the designs allow for the mechanical segmentation of the internals remotely in the water-filled reactor cavities. The C-HORCE is designed to saw seven circumferential cuts through the Core Barrel and Thermal Shield walls with individual thicknesses up to 100 mm (4 inches). The BMT is designed to remove the bolts that fasten the Baffle

  6. Pressurized-water-reactor station blackout

    International Nuclear Information System (INIS)

    Dobbe, C.A.

    1983-01-01

    The purpose of the Severe Accident Sequence Analysis (SASA) Program was to investigate accident scenarios beyond the design basis. The primary objective of SASA was to analyze nuclear plant transients that could lead to partial or total core melt and evaluate potential mitigating actions. The following summarizes the pressurized water reactor (PWR) SASA effort at the Idaho National Engineering Laboratory (INEL). The INEL is presently evaluating Unresolved Safety Issue A-44 - Station Blackout from initiation of the transient to core uncovery. The balance of the analysis from core uncovery until fission product release is being performed at Sandia National Laboratory (SNL). The current analyses involve the Bellefonte Nuclear Steam Supply System (NSSS), a Babcock and Wilcox (B and W) 205 Fuel Assembly (205-FA) raised loop design to be operated by the Tennessee Valley Authority

  7. Station Blackout Analysis of HTGR-Type Experimental Power Reactor

    Science.gov (United States)

    Syarip; Zuhdi, Aliq; Falah, Sabilul

    2018-01-01

    The National Nuclear Energy Agency of Indonesia has decided to build an experimental power reactor of high-temperature gas-cooled reactor (HTGR) type located at Puspiptek Complex. The purpose of this project is to demonstrate a small modular nuclear power plant that can be operated safely. One of the reactor safety characteristics is the reliability of the reactor to the station blackout (SBO) event. The event was observed due to relatively high disturbance frequency of electricity network in Indonesia. The PCTRAN-HTR functional simulator code was used to observe fuel and coolant temperature, and coolant pressure during the SBO event. The reactor simulated at 10 MW for 7200 s then the SBO occurred for 1-3 minutes. The analysis result shows that the reactor power decreases automatically as the temperature increase during SBO accident without operator’s active action. The fuel temperature increased by 36.57 °C every minute during SBO and the power decreased by 0.069 MW every °C fuel temperature rise at the condition of anticipated transient without reactor scram. Whilst, the maximum coolant (helium) temperature and pressure are 1004 °C and 9.2 MPa respectively. The maximum fuel temperature is 1282 °C, this value still far below the fuel temperature limiting condition i.e. 1600 °C, its mean that the HTGR has a very good inherent safety system.

  8. The decommissioning of commercial magnox gas cooled reactor power stations in the United Kingdom

    International Nuclear Information System (INIS)

    Holt, G.

    1998-01-01

    There are nine commercial Magnox gas-cooled reactor power stations in the United Kingdom. Three of these stations have been shutdown and are being decommissioning, and plans have also been prepared for the eventual decommissioning of the remaining operational stations. The preferred strategy for the decommissioning of the Magnox power stations has been identified as 'Safestore' in which the decommissioning activities are carried out in a number of steps separated by quiescent periods of care and maintenance. The final clearance of the site could be deferred for up to 135 years following station shutdown so as to obtain maximum benefit from radioactive decay. The first step in the decommissioning strategy is to defuel the reactors and transport all spent and new fuel off the site. This work has been completed at all three shutdown stations. Decommissioning work is continuing on the three sites and has involved activities such as dismantling, decontamination, recycling and disposal of some plant and structures, and the preparation of others for retention on the site for a period of care and maintenance. Significant experience has been gained in the practical application of decommissioning, with successful technologies and processes being identified for a wide range of activities. For example, large and small metallic and concrete structures, some with complex geometries, have been successfully decontaminated. Also, the reactors have been prepared for a long period of care and maintenance, with instrumentation and sampling systems having been installed to monitor their continuing integrity. All of this work has been done under careful safety, technical, and financial control. (author)

  9. French experience in operating pressurized water reactor power stations. Ten years' operation of the Ardennes power station

    International Nuclear Information System (INIS)

    Teste du Bailler, A.; Vedrinne, J.F.

    1978-01-01

    In the paper the experience gained over ten years' operation of the Ardennes (Chooz) nuclear power station is summarized from the point of view of monitoring and control equipment. The reactor was the first pressurized water reactor to be installed in France; it is operated jointly by France and Belgium. The equipment, which in many cases consists of prototypes, was developed for industrial use and with the experience that has now been gained it is possible to evaluate its qualities and defects, the constraints which it imposes and the action that has to be taken in the future. (author)

  10. Selecting suitable coherent processing time window lengths for ground-based ISAR imaging of cooperative sea vessels

    CSIR Research Space (South Africa)

    Abdul Gaffar, MY

    2009-09-01

    Full Text Available CPTWLs are needed for larger vessels in order to obtain ISAR images with the desired cross-range resolution. The effectiveness of the CPTWLs, suggested by the MACS algorithm, is shown using measured radar data. The suggested CPTWLs may also be used...

  11. Cooling of nuclear power stations with high temperature reactors and helium turbine cycles

    International Nuclear Information System (INIS)

    Foerster, S.; Hewing, G.

    1977-01-01

    On nuclear power stations with high temperature reactors and helium turbine cycles (HTR-single circuits) the residual heat from the energy conversion process in the primary and intermediate coolers is removed from cycled gas, helium. Water, which is circulated for safety reasons through a closed circuit, is used for cooling. The primary and intermediate coolers as well as other cooling equipment of the power plant are installed within the reactor building. The heat from the helium turbine cycle is removed to the environment most effectively by natural draught cooling towers. In this way a net plant efficiency of about 40% is attainable. The low quantities of residual heat thereby produced and the high (in comparison with power stations with steam turbine cycles) cooling agent pressure and cooling water reheat pressure in the circulating coolers enable an economically favourable design of the overall 'cold end' to be expected. In the so-called unit range it is possible to make do with one or two cooling towers. Known techniques and existing operating experience can be used for these dry cooling towers. After-heat removal reactor shutdown is effected by a separate, redundant cooling system with forced air dry coolers. The heat from the cooling process at such locations in the power station is removed to the environment either by a forced air dry cooling installation or by a wet cooling system. (orig.) [de

  12. A charge regulating system for turbo-generator gas-cooled high-temperature reactor power stations

    International Nuclear Information System (INIS)

    Braytenbah, A.S.; Jaegtnes, K.O.

    1975-01-01

    The invention relates to a regulating system for gas-cooled high-temperature reactors power stations (helium coolant), equipped with several steam-boilers, each of which deriving heat from a corresponding cooling-gas flow circulating in the reactor, so as to feed superheated steam into a main common steam-manifold and re-superheated steam into a re-superheated hot common manifold [fr

  13. System Definition Document: Reactor Data Necessary for Modeling Plutonium Disposition in Catawba Nuclear Station Units 1 and 2

    International Nuclear Information System (INIS)

    Ellis, R.J.

    2000-01-01

    The US Department of Energy (USDOE) has contracted with Duke Engineering and Services, Cogema, Inc., and Stone and Webster (DCS) to provide mixed-oxide (MOX) fuel fabrication and reactor irradiation services in support of USDOE's mission to dispose of surplus weapons-grade plutonium. The nuclear station units currently identified as mission reactors for this project are Catawba Units 1 and 2 and McGuire Units 1 and 2. This report is specific to Catawba Nuclear Station Units 1 and 2, but the details and materials for the McGuire reactors are very similar. The purpose of this document is to present a complete set of data about the reactor materials and components to be used in modeling the Catawba reactors to predict reactor physics parameters for the Catawba site. Except where noted, Duke Power Company or DCS documents are the sources of these data. These data are being used with the ORNL computer code models of the DCS Catawba (and McGuire) pressurized-water reactors

  14. Focusing ISAR Images using Fast Adaptive Time-Frequency and 3D Motion Detection on Simulated and Experimental Radar Data

    National Research Council Canada - National Science Library

    Brinkman, Wade

    2005-01-01

    ...) and the Particle Swarm Optimization (PSO) algorithm were designed to rapidly traverse the solution space in order to find the parameters that would bring the ISAR image into focus in the cross-range...

  15. Installation of the Light-Water Breeder Reactor at the Shippingport Atomic Power Station (LWBR Development Program)

    International Nuclear Information System (INIS)

    Massimino, R.J.; Williams, D.A.

    1983-05-01

    This report summarizes the refueling operations performed to install a Light Water Breeder Reactor (LWBR) core into the existing pressurized water reactor vessel at the Shippingport Atomic Power Station. Detailed descriptions of the major installation operations (e.g., primary system preconditioning, fuel installation, pressure boundary seal welding) are included as appendices to this report; these operations are of technical interest to any reactor servicing operation, whether the reactor is a breeder or a conventional light water non-breeder core

  16. Installation of the Light-Water Breeder Reactor at the Shippingport Atomic Power Station (LWBR Development Program)

    Energy Technology Data Exchange (ETDEWEB)

    Massimino, R.J.; Williams, D.A.

    1983-05-01

    This report summarizes the refueling operations performed to install a Light Water Breeder Reactor (LWBR) core into the existing pressurized water reactor vessel at the Shippingport Atomic Power Station. Detailed descriptions of the major installation operations (e.g., primary system preconditioning, fuel installation, pressure boundary seal welding) are included as appendices to this report; these operations are of technical interest to any reactor servicing operation, whether the reactor is a breeder or a conventional light water non-breeder core.

  17. Testing time for Siemens/KWU's PRINS/PRISCA at Isar II and Emsland

    International Nuclear Information System (INIS)

    Aleite, W.

    1988-01-01

    The culmination of work started in the early 1970s, the first PRINS/PRISCA process information system has recently been through commissioning tests at the new Isar II and Emsland convoy PWRS. PRINS/PRISCA is a human factor orientated, fully redundant, distributed, real time computer system with full graphic capabilities and standardized pictorial symbols. It also features elements of artificial intelligence and an innovative presentation of information, using banks of up to eight screens. KWU reports that reactions from operators have been increasingly positive. (author)

  18. Investigating the effect of a targets time-varying doppler generating axis of rotation on isar image distortion

    CSIR Research Space (South Africa)

    Abdul Gaffar, MY

    2007-10-01

    Full Text Available , contributes to ISAR image blurring. Quaternion algebra is used to aid the characterisation of a time-varying Doppler generating axis of rotation on the migration through cross-range cells. Real motion data of a sailing yacht is used to examine the effects of 3...

  19. Design of a redundant meteorological station for a BWR reactor

    International Nuclear Information System (INIS)

    Ramirez S, R.; Celis del Angel, L.; Bucio, F.; Rivero, T.; Palacios, J.

    2008-01-01

    In this work the design of a meteorological station for a reactor type BWR is proposed. Two independent channels of data acquisition that allow him to have a bigger readiness is exposed. It is incorporate sensors without mobile parts to measure speed, wind direction and pluvial precipitation. It also counts, with sensors of global solar radiation, net radiation, barometric pressure, relative humidity and ambient temperature; with them they are possible to be calculated, moreover, other variables as temperature differential, dew point and atmospheric stability. The sensors are placed on a tower to different heights and send their information (each second) to a local registration system, the one which in turn, it remits the data to the monitoring office so that a computer is linked with the system, display and management the information in real time and automatic way. The redundant structure allows that in the event of maintenance the data acquisition is not interrupted, even if the information is transferred to another place. In all the station sections it is used protocols of standard communication to allow that a great quantity of devices can be connected without major problem. The above-mentioned would allow to the operators in the control room to have reliable information during the whole time of the reactor operation. (Author)

  20. Thermohydraulic and safety analysis on China advanced research reactor under station blackout accident

    International Nuclear Information System (INIS)

    Tian Wenxi; Qiu Suizheng; Su Guanghui; Jia Dounan; Liu Xingmin; Zhang Jianwei

    2007-01-01

    A thermohydraulic and safety analysis code-TSACC has been developed using Fortran90 language to evaluate the transient thermohydraulic behavior of the China advanced research reactor (CARR) under station blackout accident (SBA). For the development of TSACC, a series of corresponding mathematical and physical models were applied. Point reactor neutron kinetics model was adopted for solving the reactor power. All possible flow and heat transfer conditions under station blackout accident were considered and the optional correlations were supplied. The usual finite difference method was abandoned and the integral technique was adopted to evaluate the temperature field of the plate type fuel elements. A new simple and convenient equation was proposed for the resolution of the transient behaviors of the main pump instead of the complicated four-quadrant model. Gear method and Adams method were adopted alternately for a better solution to the stiff differential equations describing the dynamic behavior of the CARR. The computational result of TSACC showed the adequacy of the safety margin of CARR under SBA. For the purpose of Verification and Validation (V and V), the simulated results of TSACC were compared with those of RELAP5/MOD3 and a good agreement was obtained. The adoption of modular programming techniques enables TASCC to be applied to other reactors by easily modifying the corresponding function modules

  1. Technology, safety and costs of decommissioning a reference boiling water reactor power station: Comparison of two decommissioning cost estimates developed for the same commercial nuclear reactor power station

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1990-12-01

    This study presents the results of a comparison of a previous decommissioning cost study by Pacific Northwest Laboratory (PNL) and a recent decommissioning cost study of TLG Engineering, Inc., for the same commercial nuclear power reactor station. The purpose of this comparative analysis on the same plant is to determine the reasons why subsequent estimates for similar plants by others were significantly higher in cost and external occupational radiation exposure (ORE) than the PNL study. The primary purpose of the original study by PNL (NUREG/CR-0672) was to provide information on the available technology, the safety considerations, and the probable costs and ORE for the decommissioning of a large boiling water reactor (BWR) power station at the end of its operating life. This information was intended for use as background data and bases in the modification of existing regulations and in the development of new regulations pertaining to decommissioning activities. It was also intended for use by utilities in planning for the decommissioning of their nuclear power stations. The TLG study, initiated in 1987 and completed in 1989, was for the same plant, Washington Public Supply System's Unit 2 (WNP-2), that PNL used as its reference plant in its 1980 decommissioning study. Areas of agreement and disagreement are identified, and reasons for the areas of disagreement are discussed. 31 refs., 3 figs., 22 tabs

  2. Reactor coolant pump shaft seal behavior during station blackout

    International Nuclear Information System (INIS)

    Kittmer, C.A.; Wensel, R.G.; Rhodes, D.B.; Metcalfe, R.; Cotnam, B.M.; Gentili, H.; Mings, W.J.

    1985-04-01

    A testing program designed to provide fundamental information pertaining to the behavior of reactor coolant pump (RCP) shaft seals during a postulated nuclear power plant station blackout has been completed. One seal assembly, utilizing both hydrodynamic and hydrostatic types of seals, was modeled and tested. Extrusion tests were conducted to determine if seal materials could withstand predicted temperatures and pressures. A taper-face seal model was tested for seal stability under conditions when leaking water flashes to steam across the seal face. Test information was then used as the basis for a station blackout analysis. Test results indicate a potential problem with an elastomer material used for O-rings by a pump vendor; that vendor is considering a change in material specification. Test results also indicate a need for further research on the generic issue of RCP seal integrity and its possible consideration for designation as an unresolved safety issue

  3. Future plans for the design and construction of fast reactor power stations in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Kempken, M.; Koehler, M.; Wolff, M.

    1978-01-01

    Some important design features of future fast reactors in the Federal Republic of Germany (FRG) are presented, in particular for the demonstration plant SNR 2 which is to follow the prototype SNR 300, presently under construction in Kalkar. The SNR 2 conceptual design will be based on the SNR 300 design as far as possible. Programmes for the introduction of fast breeder reactor power stations on the part of the governments, the utilities and suppliers are based on broad international co-operation. The FRG is a country which imports a high proportion of its primary energy and it has rather small resources of natural uranium. The natural uranium realistically available to the FRG will allow nuclear energy to play a substantial role in the long-term energy supply only if present uranium utilization based on LWRs is supplemented and replaced by breeder reactor utilization later. To maintain this option, efforts towards the development, design and construction of fast breeder reactors have to be intensively continued in the FRG. The construction of the first large power station with a fast breeder reactor, SNR 2, will, according to present planning, start in the middle of the 80s. Operation can be expected to start at the beginning of the 90s. The present fast breeder programme in the FRG promises to develop reactors, reprocessing and fuel manufacturing plants to such a degree that by the end of this century the introduction of a substantial number of fast reactor power stations will be possible. (author)

  4. Aging management program of the reactor building concrete at Point Lepreau Generating Station

    Science.gov (United States)

    Aldea, C.-M.; Shenton, B.; Demerchant, M. M.; Gendron, T.

    2011-04-01

    In order for New Brunswick Power Nuclear (NBPN) to control the risks of degradation of the concrete reactor building at the Point Lepreau Generating Station (PLGS) the development of an aging management plan (AMP) was initiated. The intention of this plan was to determine the requirements for specific structural components of concrete of the reactor building that require regular inspection and maintenance to ensure the safe and reliable operation of the plant. The document is currently in draft form and presents an integrated methodology for the application of an AMP for the concrete of the reactor building. The current AMP addresses the reactor building structure and various components, such as joint sealant and liners that are integral to the structure. It does not include internal components housed within the structure. This paper provides background information regarding the document developed and the strategy developed to manage potential degradation of the concrete of the reactor building, as well as specific programs and preventive and corrective maintenance activities initiated.

  5. Training courses for the staff of the nuclear power station KRSKO conducted at the TRIGA reactor center in Ljubljana

    International Nuclear Information System (INIS)

    Pregl, G.; Najzer, M.

    1976-01-01

    The training program for the Nuclear Power Station Krsko was divided into two modules: fundamentals of nuclear engineering and specialized training according to duties that candidates are supposed to take at the power station. Basic training was organized at the TRIGA Reactor Center in Ljubljana in two different versions. The first version intended for plant operators and all engineers lasted for six months and included about 500 hours of classroom lessons and seminars and 31 laboratory experiments. The educational program was conventional. The following topics were covered: nuclear and atomic physics, reactor theory, reactor dynamics, reactor instrumentation and control, heat transfer in nuclear power plants, nuclear power plant systems, reactor materials, reactor safety, and radiation protection. Until now, two groups, consisting of 37 candidates altogether, have attended this basic course. Plans have been made to conduct two additional courses of about 20 students each for technicians other than operators. The program of this second version will be reduced, with the emphasis on reactor core physics and radiation protection. Classroom lessons will be strongly supported by laboratory experiments. (author)

  6. Long-term prognostic value of risk scores after drug-eluting stent implantation for unprotected left main coronary artery: A pooled analysis of the ISAR-LEFT-MAIN and ISAR-LEFT-MAIN 2 randomized clinical trials.

    Science.gov (United States)

    Xhepa, Erion; Tada, Tomohisa; Kufner, Sebastian; Ndrepepa, Gjin; Byrne, Robert A; Kreutzer, Johanna; Ibrahim, Tareq; Tiroch, Klaus; Valgimigli, Marco; Tölg, Ralf; Cassese, Salvatore; Fusaro, Massimiliano; Schunkert, Heribert; Laugwitz, Karl L; Mehilli, Julinda; Kastrati, Adnan

    2017-01-01

    To evaluate the long-term prognostic value of risk scores in the setting of drug-eluting stent (DES) implantation for uLMCA. Data on the prognostic value of novel risk scores developed to select the most appropriate revascularization strategy in patients undergoing DES implantation for uLMCA disease are relatively limited. The study represents a patient-level pooled analysis of the ISAR-LEFT-MAIN (607 patients randomized to paclitaxel-eluting or sirolimus-eluting stents) and the ISAR-LEFT-MAIN-2 (650 patients randomized to everolimus-eluting or zotarolimus-eluting stents) randomized trials. The Syntax Score (SxScore) as well the Syntax Score II (SS-II), the EuroSCORE and the Global Risk Classification (GRC) were calculated. The primary outcome was all-cause mortality. At a mean follow-up of 3 years there were 160 deaths (12.7%). The death-incidence was significantly higher in the upper tertiles than in the intermediate or lower ones for all risk scores (log-rank test P risk scores were able to stratify the mortality risk at long-term follow-up. EuroSCORE was the only risk score that significantly improved the discriminatory power of a multivariable model to predict long-term mortality. © 2016 Wiley Periodicals, Inc. © 2016 Wiley Periodicals, Inc.

  7. Nuclear power plant Isar. Actualized environmental statement 2012 on the consolidated environmental statement 2010

    International Nuclear Information System (INIS)

    2012-01-01

    The actualized environmental statement 2012 for the NPP Isar covers the following issues: Direct environmental aspects: heat dissipation to the environment, water management, radioactive matter release onto the environment, environmental monitoring, waste management, operational materials supply, radioactive materials transport, safety of the nuclear facilities, remote monitoring and information system, environmental protection, communication; indirect environmental aspects; core indicators according EMAS III, development of the environmental targets and programs, reference to the valid environmental regulations, declaration of the environmental consultant.

  8. The construction of a PWR power station reactor building liner

    International Nuclear Information System (INIS)

    Skirving, N.; Goulding, J.S.; Gibson, J.A.

    1991-01-01

    Cleveland Bridge and Engineering Co Ltd (CBE) are constructing the Reactor Building Liner Plate containment of the Sizewell 'B' Power Station for Nuclear Electric Ltd. This has entailed extensive offsite prefabrication of components and their subsequent erection at Sizewell. It has been necessary to engineer temporary supporting mechanisms to enable manufacture and erection to proceed, yet also to withstand wet concrete forces during the progressive construction. The Reactor Building Liner Plate is a safety related system and as such, in addition to strict compliance with the ASME code, the Quality Assurance (QA) requirements of BS 5882 are applicable. A dedicated Project Team was established by CBE to control and direct the work. Equally important as satisfying the rigorous Q.A. requirements has been the need to meet programme and budget. This paper details CBE execution of the Project. (author)

  9. Use of Genetic Algorithms for Contrast and Entropy Optimization in ISAR Autofocusing

    Directory of Open Access Journals (Sweden)

    Martorella Marco

    2006-01-01

    Full Text Available Image contrast maximization and entropy minimization are two commonly used techniques for ISAR image autofocusing. When the signal phase history due to the target radial motion has to be approximated with high order polynomial models, classic optimization techniques fail when attempting to either maximize the image contrast or minimize the image entropy. In this paper a solution of this problem is proposed by using genetic algorithms. The performances of the new algorithms that make use of genetic algorithms overcome the problem with previous implementations based on deterministic approaches. Tests on real data of airplanes and ships confirm the insight.

  10. Relap5 Analysis of Processes in Reactor Cooling Circuit and Reactor Cavity in Case of Station Blackout in RBMK-1500

    International Nuclear Information System (INIS)

    Kaliatka, A.

    2007-01-01

    Ignalina NPP is equipped with channel-type boiling-water graphite-moderated reactor RBMK-1500. Results of the level-1 probabilistic safety assessment of the Ignalina NPP have shown that in topography of the risk, the transients with failure of long-term core cooling other than LOCA are the main contributors to the core damage frequency. The total loss of off-site power with a failure to start any diesel generator, that is station blackout, is the event which could lead to the loss of long-term core cooling. Such accident could lead to multiple ruptures of fuel channels with severe consequences and should be analyzed in order to estimate the timing of the key events and the possibilities for accident management. This paper presents the results of the analysis of station blackout at Ignalina NPP. Analysis was performed using thermal-hydraulic state-of-the-art RELAP5/MOD3.2 code. The response of reactor cooling system and the processes in the reactor cavity and its venting system in case of a few fuel-channel ruptures due to overheating were demonstrated. The possible measures for prevention of the development of this beyond design basis accident (BDBA) to a severe accident are discussed

  11. Alteration in reactor installations (Unit 1 and 2 reactor facilities) in the Hamaoka Nuclear Power Station of The Chubu Electric Power Co., Inc. (report)

    International Nuclear Information System (INIS)

    1982-01-01

    A report by the Nuclear Safety Commission to the Ministry of International Trade and Industry concerning the alteration in Unit 1 and 2 reactor facilities in the Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc., was presented. The technical capabilities for the alteration of reactor facilities in Chubu Electric Power Co., Inc., were confirmed to be adequate. The safety of the reactor facilities after the alteration was confirmed to be adequate. The items of examination made for the confirmation of the safety are as follows: reactor core design (nuclear design, mechanical design, mixed reactor core), the analysis of abnormal transients in operation, the analysis of various accidents, the analysis of credible accidents for site evaluation. (Mori, K.)

  12. The ring-stiffened shell of the ISAR II nuclear power plant natural-draught cooling tower

    International Nuclear Information System (INIS)

    Form, J.

    1986-01-01

    The natural-draught cooling tower of the ISAR II nuclear power plant is one of the largest in the world. The bid specifications provided for an unstiffened cooling tower shell. For the execution, however, it was decided to adopt a shell with three additional stiffening rings. The present contribution deals with the static and dynamic calculations of the execution and, in particular, with the working technique employed for the construction of the rings. (author)

  13. Aging management program of the reactor building concrete at Point Lepreau Generating Station

    Directory of Open Access Journals (Sweden)

    Gendron T.

    2011-04-01

    Full Text Available In order for New Brunswick Power Nuclear (NBPN to control the risks of degradation of the concrete reactor building at the Point Lepreau Generating Station (PLGS the development of an aging management plan (AMP was initiated. The intention of this plan was to determine the requirements for specific structural components of concrete of the reactor building that require regular inspection and maintenance to ensure the safe and reliable operation of the plant. The document is currently in draft form and presents an integrated methodology for the application of an AMP for the concrete of the reactor building. The current AMP addresses the reactor building structure and various components, such as joint sealant and liners that are integral to the structure. It does not include internal components housed within the structure. This paper provides background information regarding the document developed and the strategy developed to manage potential degradation of the concrete of the reactor building, as well as specific programs and preventive and corrective maintenance activities initiated.

  14. Culham Conceptual Tokamak Mark II. Design study of the layout of a twin-reactor fusion power station

    International Nuclear Information System (INIS)

    Guthrie, J.A.S.; Harding, N.H.

    1981-07-01

    This report describes the building layout and outline design for the nuclear complex of a fusion reactor power station incorporating two Culham Conceptual Tokamak Reactors Mk.II. The design incorporates equipment for steam generation, process services for the fusion reactors and all facilities for routine and non-routine servicing of the nuclear complex. The design includes provision of temporary facilities for on site construction of the major reactor components and shows that these facilities may be used for disassembly of the reactors either for major repair and/or decommissioning. Preliminary estimates are included, which indicate the cost benefits to be obtained from incorporating two reactors in one nuclear complex and from increased wall loading. (author)

  15. Uncertainty and sensitivity analysis for the simulation of a station blackout scenario in the Jules Horowitz Reactor

    International Nuclear Information System (INIS)

    Ghione, Alberto; Noel, Brigitte; Vinai, Paolo; Demazière, Christophe

    2017-01-01

    Highlights: • A station blackout scenario in the Jules Horowitz Reactor is analyzed using CATHARE. • Input and model uncertainties relevant to the transient, are considered. • A statistical methodology for the propagation of the uncertainties is applied. • No safety criteria are exceeded and sufficiently large safety margins are estimated. • The most influential uncertainties are determined with a sensitivity analysis. - Abstract: An uncertainty and sensitivity analysis for the simulation of a station blackout scenario in the Jules Horowitz Reactor (JHR) is presented. The JHR is a new material testing reactor under construction at CEA on the Cadarache site, France. The thermal-hydraulic system code CATHARE is applied to investigate the response of the reactor system to the scenario. The uncertainty and sensitivity study was based on a statistical methodology for code uncertainty propagation, and the ‘Uncertainty and Sensitivity’ platform URANIE was used. Accordingly, the input uncertainties relevant to the transient, were identified, quantified, and propagated to the code output. The results show that the safety criteria are not exceeded and sufficiently large safety margins exist. In addition, the most influential input uncertainties on the safety parameters were found by making use of a sensitivity analysis.

  16. Maintenance experience on reactor recirculation pumps at Tarapur Atomic Power Station

    International Nuclear Information System (INIS)

    Singh, A.K.

    1995-01-01

    Reactor recirculation pumps at Tarapur Atomic Power Station (TAPS) are vertical, single stage centrifugal pumps having mechanical shaft seals and are driven by vertical mounted 3.3 kV, 3 phase, 1500 h.p. electric motors. During these years of operation TAPS has gained enough experience and expertise on the maintenance of reactor recirculation pumps which are dealt in this article. Failure of mechanical shaft seals, damage on pump carbon bearings, motor winding insulation failures and motor shaft damage have been the main areas of concern on recirculation pump. A detailed procedure step by step with component sketches has helped in eliminating errors during shaft seal assembly and installation. Pressure breakdown devices in seal assembly were rebuilt. Additional coolant water injection for shaft seal cooling was provided. These measures have helped in extending the reactor recirculation pump seal life. Pump bearing problems were mainly due to failure of anti-rotation pins and dowel pins of bearing assembly. These pins were redesigned and strengthened. Motor stator winding insulation failures were detected. Stator winding replacement program has been taken up on regular basis to avoid winding insulation failure due to aging. 3 refs., 2 tabs., 7 figs

  17. Alteration in reactor installation (addition of Unit 2) in Shimane Nuclear Power Station, Chugoku Electric Power Co., Inc. (inquiry)

    International Nuclear Information System (INIS)

    1983-01-01

    An inquiry was made by the Ministry of International Trade and Industry to Nuclear Safety Commission on the addition of Unit 2 in Shimane Nuclear Power Station of The Chugoku Electric Power Co., Inc., concerning the technical capability of Chugoku Electric Power Co., Inc., and the plant safety. The NSC requested the Committee on Examination of Reactor Safety to make a deliberation on this subject. Both the technical capability and the safety of Unit 1 were already confirmed by MITI. Unit 2 to be newly added in the Shimane Nuclear Power Station is a BWR power plant with electric output of 820 MW. The examination made by MITI is described: the technical capability of Chugoku Electric Power Co., Inc., the safety of Unit 2 about its siting, reactor proper, reactor cooling system, radioactive waste management, etc. (J.P.N.)

  18. Technical limits on performance reserves and life expectancy in nuclear power stations with light water reactors

    International Nuclear Information System (INIS)

    Wanner, R.; Brosi, S.; Duijvestijn, G.

    1990-01-01

    The safety margin (i.e. the difference between the loads equipment can take and those actually imposed on components) in a reactor pressure vessel is a major factor in the life expectancy of a nuclear power station. This safety margin is reduced considerably by reductions in the toughness of equipment caused by neutron irradiation and growth of cracks. Once the minimum safety margin is infringed, the nuclear power station is at the end of its working life. 13 figs., 11 refs

  19. Synthetic range profiling, ISAR imaging of sea vessels and feature extraction, using a multimode radar to classify targets: initial results from field trials

    CSIR Research Space (South Africa)

    Abdul Gaffar, MY

    2011-04-01

    Full Text Available tanazi@kacst.edu.sa, aazamil@kacst.edu.sa Abstract?This paper describes the design and working principles of an experimental multimode radar with a stepped-frequency Synthetic Range Profiling (SRP) and Inverse Synthetic Aperture Radar (ISAR...

  20. Station Blackout Analysis for a 3-Loop Westinghouse PWR Reactor Using Trace

    International Nuclear Information System (INIS)

    El-Sahlamy, N.M.

    2017-01-01

    One of the main concerns in the area of severe accidents in nuclear reactors is that of station blackout (SBO). The loss of offsite electrical power concurrent with the unavailability of the onsite emergency alternating current (AC) power system can result in loss of decay heat removal capability, leading to a potential core damage which may lead to undesirable consequences to the public and the environment. To cope with an SBO, nuclear reactors are provided with protection systems that automatically shut down the reactor, and with safety systems to remove the core residual heat. This paper provides a best estimate assessment of the SBO scenario in a 3-loop Westinghouse PWR reactor. The evaluation is performed using TRACE, a best estimate computer code for thermal-hydraulic calculations. Two sets of scenarios for SBO analyses are discussed in the current work. The first scenario is the short term SBO where it is assumed that in addition to the loss of AC power, there is no DC power; i.e., no batteries are available. In the second scenario, a long term SBO is considered. For this scenario, DC batteries are available for four hours. The aim of the current SBO analyses for the 3-loop pressurized water reactor presented in this paper is to focus on the effect of the availability of a DC power source to delay the time to core uncovers and heatup

  1. Development of remote decontamination technologies improving internal environment of reactor buildings at Fukushima Daiichi Nuclear Power Station

    International Nuclear Information System (INIS)

    Hotta, Koji; Hayashi, Hirotada; Sakai, Hitoshi

    2016-01-01

    The reactor buildings at the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Co., Inc., which was seriously damaged by the Great East Japan Earthquake of March 11, 2011, have been highly contaminated by radioactive materials. To safely and efficiently advance the processes related to the forthcoming decommissioning of the reactors, it is necessary to improve the hazardous environment inside the reactor buildings. During the more than four years that have elapsed since the Great East Japan Earthquake, Toshiba has been implementing various measures to reduce the ambient dose rates inside the reactor buildings through decontamination work and participation in a national project for the development of remote decontamination technologies for reactor buildings. A variety of vehicles and technologies to support decontamination work have been developed through these activities, and are significantly contributing to improvement of the environment inside the reactor buildings. (author)

  2. A feasibility assessment of nuclear reactor power system concepts for the NASA Growth Space Station

    Science.gov (United States)

    Bloomfield, H. S.; Heller, J. A.

    1986-01-01

    A preliminary feasibility assessment of the integration of reactor power system concepts with a projected growth Space Station architecture was conducted to address a variety of installation, operational, disposition and safety issues. A previous NASA sponsored study, which showed the advantages of Space Station - attached concepts, served as the basis for this study. A study methodology was defined and implemented to assess compatible combinations of reactor power installation concepts, disposal destinations, and propulsion methods. Three installation concepts that met a set of integration criteria were characterized from a configuration and operational viewpoint, with end-of-life disposal mass identified. Disposal destinations that met current aerospace nuclear safety criteria were identified and characterized from an operational and energy requirements viewpoint, with delta-V energy requirement as a key parameter. Chemical propulsion methods that met current and near-term application criteria were identified and payload mass and delta-V capabilities were characterized. These capabilities were matched against concept disposal mass and destination delta-V requirements to provide a feasibility of each combination.

  3. A feasibility assessment of nuclear reactor power system concepts for the NASA growth Space Station

    International Nuclear Information System (INIS)

    Bloomfield, H.S.; Heller, J.A.

    1986-01-01

    A preliminary feasibility assessment of the integration of reactor power system concepts with a projected growth space station architecture was conducted to address a variety of installation, operational, disposition and safety issues. A previous NASA sponsored study, which showed the advantages of space station related concepts, served as the basis for this study. A study methodology was defined and implemented to assess compatible combinations of reactor power installation concepts, disposal destinations, and propulsion methods. Three installation concepts that met a set of integration criteria were characterized from a configuration and operational viewpoint, with end-of-life disposal mass identified. Disposal destinations that met current aerospace nuclear safety criteria were identified and characterized from an operational and energy requirements viewpoint, with delta-V energy requirement as a key parameter. Chemical propulsion methods that met current and near-term application criteria were identified and payload mass and delta-V capabilities were characterized. These capabilities were matched against concept disposal mass and destination delta-V requirements to provide a feasibility of each combination

  4. Multipurpose epithermal neutron beam on new research station at MARIA research reactor in Swierk-Poland

    Energy Technology Data Exchange (ETDEWEB)

    Gryzinski, M.A.; Maciak, M. [National Centre for Nuclear Research, Andrzeja Soltana 7, 05-400 Otwock-Swierk (Poland)

    2015-07-01

    planned to create fully equipped complex facility possible to perform various experiments on the intensive neutron beam. Epithermal neutron beam enables development across the full spectrum of materials research for example shielding concrete tests or electronic devices construction improvement. Due to recent reports on the construction of the accelerator for the Boron Neutron Capture Therapy (BNCT) it has the opportunity to become useful and successful method in the fight against brain and other types of cancers not treated with well known medical methods. In Europe there is no such epithermal neutron source which could be used throughout the year for training and research for scientist working on BNCT what makes the stand unique in Europe. Also our research group which specializes in mixed radiation dosimetry around nuclear and medical facilities would be able to carry out research on new detectors and methods of measurements for radiological protection and in-beam (therapeutic) dosimetry. Another group of scientists from National Centre for Nuclear Research, where MARIA research reactor is located, is involved in research of gamma detector systems. There is an idea to develop Prompt-gamma Single Photon Emission Computed Tomography (Pg- SPECT). This method could be used as imaging system for compounds emitting gamma rays after nuclear reaction with thermal neutrons e.g. for boron concentration in BNCT. Inside the room, where H2 channel is located, there is another horizontal channel - H1 which is also unused. Simultaneously with the construction of the H2 stand it will be possible to create special pneumatic horizontal mail inside the H1 channel for irradiation material samples in the vicinity of the core i.e. in the distal part of the H1 channel. It might expand the scope of research at the planned neutron station. Secondly it is planned to equip both stands with moveable positioning system, video system and facilities to perform animal experiments (anaesthesia, vital

  5. Reactor Safety Commission Code of Practice for Pressurized Water Reactors

    International Nuclear Information System (INIS)

    1990-01-01

    The Reactor Safety Commission of the Federal German Republic has summarized in the form of Official Guidelines the safety requirements which, in the Commission's view, have to be met in the design, construction and operation of a nuclear power station equipped with a pressurized water reactor. The Third Edition of the RSK Guidelines for pressurized water reactors dated 14.10.81. is a revised and expanded version of the Second Edition dated 24.1.79. The Reactor Safety Commission will with effect from October 1981 use these Guidelines in consultations on the siting of and safety concept for the installation approval of future pressurized water reactors and will assess these nuclear power stations during their erection in the light of these Guidelines. They have not however been immediately conceived for the adaptation of existing nuclear power stations, whether under construction or in operation. The scope of application of these Guidelines to such nuclear power stations will have to be examined for each individual case. The main aim of the Guidelines is to simplify the consultation process within the reactor Safety Commission and to provide early advice on the safety requirements considered necessary by the Commission. (author)

  6. Light Water Reactor Sustainability Program: Analysis of Pressurized Water Reactor Station Blackout caused by external flooding using the RISMC toolkit

    International Nuclear Information System (INIS)

    2014-01-01

    The existing fleet of nuclear power plants is in the process of extending its lifetime and increasing the power generated from these plants via power uprates. In order to evaluate the impacts of these two factors on the safety of the plant, the Risk Informed Safety Margin Characterization project aims to provide insights to decision makers through a series of simulations of the plant dynamics for different initial conditions (e.g., probabilistic analysis and uncertainty quantification). This paper focuses on the impacts of power uprate on the safety margin of a boiling water reactor for a flooding induced station black-out event. Analysis is performed by using a combination of thermal-hydraulic codes and a stochastic analysis tool currently under development at the Idaho National Laboratory, i.e. RAVEN. We employed both classical statistical tools, i.e. Monte-Carlo, and more advanced machine learning based algorithms to perform uncertainty quantification in order to quantify changes in system performance and limitations as a consequence of power uprate. Results obtained give a detailed investigation of the issues associated with a plant power uprate including the effects of station black-out accident scenarios. We were able to quantify how the timing of specific events was impacted by a higher nominal reactor core power. Such safety insights can provide useful information to the decision makers to perform risk informed margins management.

  7. Purification and solidification of reactor wastes at a Canadian nuclear generating station

    International Nuclear Information System (INIS)

    Buckley, L.P.; Burt, D.A.

    1981-06-01

    Chalk River Nuclear Laboratories are developing methods to condition power reactor wastes and to immobilize their radionuclides. Evaporation alone and combined with bituminization has been an important part of the program. After testing at the laboratories a 0.5 m 2 wiped-film evaporator was sent to the Douglas Point Nuclear Generating Station (220 MWe) to demonstrate its suitability to handle typical reactor liquid wastes. Two specific tasks undertaken with the wiped-film evaporator were successfully completed. The first was purification of contaminated heavy water which had leaked from the moderator circuit. The heavy water is normally recovered, cleaned by filters and ion-exchange resin and then upgraded by electrolysis. Cleaning the heavy water with the wiped-film evaporator produced better quality water for upgrading than had been achieved by any previous method and at much lower operating cost. The second task was to concentrate and immobilize a decontamination waste. The waste was generated from the decontamination of pump bowls used in the primary heat transport circuit. The simultaneous addition of the liquid waste and bitumen emulsion to the wiped-film evaporator produced a solid containing 30 wt% waste solids in a bitumen matrix. The volume reduction achieved was 16:1 based on the volumes of initial liquid waste and the final product generated. The quantity sent to storage was 20 times less than had the waste been immobilized in a cement matrix. The successful demonstration has resulted in a proposal to install a wiped-film evaporator at the station to clean heavy water and immobilize decontamination wastes. (author)

  8. Purification and solidification of reactor wastes at a Canadian nuclear generating station

    International Nuclear Information System (INIS)

    Buckley, L.P.; Burt, D.A.

    1981-01-01

    The study aimed at development and demonstration of volume reduction and solidification of CANDU reactor wastes has been underway at Chalk River Nuclear Laboratories in the Province of Ontario, Canada. The study comprises membrane separation processes, evaporator appraisal and immobilization of concentrated wastes in bitumen. This paper discusses the development work with a wiped-film evaporator and the successful completion of demonstration tests at Douglas Point Nuclear Generating Station. Heavy water from the moderator system was purified and wastes arising from pump bowl decontamination were immobilized in bitumen with the wiped-film evaporator that was used in the development tests at Chalk River

  9. Reactor costs and maintenance, with reference to the Culham Mark II conceptual tokamak reactor design

    International Nuclear Information System (INIS)

    Hancox, R.; Mitchell, J.T.D.

    1977-01-01

    Published designs of tokamak reactors have proposed conceptual solutions for most of the technological problems encountered. Two areas which remain uncertain, however, are the capital cost of the reactor and the practicability of reactor maintenance. A cost estimate for the Culham Conceptual Tokamak Reactor (Mk I) is presented. The capital cost of a power station incorporating this reactor would be significantly higher than that of an equivalent fast breeder fission power station, mainly because of the low power density of the fusion reactor which affects both the reactor and building costs. To reduce the fusion station capital costs a new conceptual design is proposed (Mk II) which incorporates a shaped plasma cross-section to give a higher plasma pressure ratio, βsub(t) approximately 0.1. Since the higher power density implies more severe radiation damage of the blanket structure, the question of reactor maintenance assumes greater importance. With the proposed scheme for regular replacement of the blanket, a fusion power station availability around 0.9 should be achievable. (author)

  10. Reactor costs and maintenance, with reference to the Culham Mark II conceptual Tokamak reactor design

    International Nuclear Information System (INIS)

    Hancox, R.; Mitchell, J.T.D.

    1976-01-01

    Published designs of tokamak reactors have proposed conceptual solutions for most of the technological problems encountered. Two areas which remain uncertain, however, are capital cost of the reactor and the practicability of reactor maintenance. A cost estimate for the Culham Conceptual Tokamak Reactor (Mk I) is presented. The capital cost of a power station incorporating this reactor would be significantly higher than that of an equivalent fast breeder fission power station, due mainly to the low power density of the fusion reactor which affects both the reactor and building costs. In order to reduce the fusion station capital costs a new conceptual design is proposed (Mk II) which incorporates a shaped plasma cross-section to give a higher plasma pressure ratio, βsub(t) approximately 0.1. Since the higher power density implies more severe radiation damage of the blanket structure, the question of reactor maintenance assumes greater importance. With the proposed scheme for regular replacement of the blanket, a fusion power station availability around 0.9 should be achievable. (orig.) [de

  11. UMA ANÁLISE CRÍTICA ENTRE OS CURRÍCULOS DOS CURSOS DE CIÊNCIAS CONTÁBEIS NOS PAÍSES DO MERCOSUL E O PROPOSTO PELA ONU/UNCTAD/ISAR

    Directory of Open Access Journals (Sweden)

    Giovanna Tonetto Segantini

    2013-07-01

    Full Text Available A harmonização das normas contábeis tornou-se uma necessidade dos usuários externos e in-ternos da informação contábil, uma vez que passaram a atuar em diversos mercados e a prestar contas aos usuários com necessidades variadas, pois o mercado cada vez mais globalizado exige profissionais preparados para atuar dentro e fora do seu país. Visando isso, a ONU/UNCTAD/ISAR desenvolveu um Currículo Mundial para servir de referência para os cursos de Ciências Contábeis, buscando prover conhecimentos internacionais de normas contábeis independentemente do país responsável pela formação do profissional. Assim, o objetivo geral do artigo foi analisar e comparar a adequação dos currículos dos cursos de ciências contá-beis de quatro universidades do MERCOSUL, sendo uma de cada país, com o currículo proposto pela ONU/UNCTAD/ISAR. As universidades selecionadas foram: Facultad de Ciencias Econômicas de la Universidad de Buenos Aires (Argentina; Faculdade de Economia, Administração e Con-tabilidade da Universidade de São Paulo (Brasil; Universidad Nacional de Asunción (Paraguai; e Facultad de Ciências Econômicas y de Administración de la Universidad de la República (Uruguai, e suas matrizes curriculares foram comparadas com o Currículo Mundial proposto pela ONU/UNCTAD/ISAR. Os resultados indicam que a similaridade entre os currículos das quatro universidades selecionadas com o proposto pela ONU/UNCTAD/ISAR é alta, existindo, em mé-dia, 76,71% de semelhança entre as matérias dos currículos. Por ser apenas uma recomendação, as universidades pesquisadas demonstraram possuir certa flexibilidade na elaboração de seus currículos.

  12. Tests of a new CCD-camera based neutron radiography detector system at the reactor stations in Munich and Vienna

    Energy Technology Data Exchange (ETDEWEB)

    Lehmann, E; Pleinert, H [Paul Scherrer Inst. (PSI), Villigen (Switzerland); Schillinger, B [Technische Univ. Muenchen (Germany); Koerner, S [Atominstitut der Oesterreichischen Universitaeten, Vienna (Austria)

    1997-09-01

    The performance of the new neutron radiography detector designed at PSI with a cooled high sensitive CCD-camera was investigated under real neutronic conditions at three beam ports of two reactor stations. Different converter screens were applied for which the sensitivity and the modulation transfer function (MTF) could be obtained. The results are very encouraging concerning the utilization of this detector system as standard tool at the radiography stations at the spallation source SINQ. (author) 3 figs., 5 refs.

  13. Supervised Self-Organizing Classification of Superresolution ISAR Images: An Anechoic Chamber Experiment

    Directory of Open Access Journals (Sweden)

    Radoi Emanuel

    2006-01-01

    Full Text Available The problem of the automatic classification of superresolution ISAR images is addressed in the paper. We describe an anechoic chamber experiment involving ten-scale-reduced aircraft models. The radar images of these targets are reconstructed using MUSIC-2D (multiple signal classification method coupled with two additional processing steps: phase unwrapping and symmetry enhancement. A feature vector is then proposed including Fourier descriptors and moment invariants, which are calculated from the target shape and the scattering center distribution extracted from each reconstructed image. The classification is finally performed by a new self-organizing neural network called SART (supervised ART, which is compared to two standard classifiers, MLP (multilayer perceptron and fuzzy KNN ( nearest neighbors. While the classification accuracy is similar, SART is shown to outperform the two other classifiers in terms of training speed and classification speed, especially for large databases. It is also easier to use since it does not require any input parameter related to its structure.

  14. Joint Processing of Envelope Alignment and Phase Compensation for Isar Imaging

    Science.gov (United States)

    Chen, Tao; Jin, Guanghu; Dong, Zhen

    2018-04-01

    Range envelope alignment and phase compensation are spilt into two isolated parts in the classical methods of translational motion compensation in Inverse Synthetic Aperture Radar (ISAR) imaging. In classic method of the rotating object imaging, the two reference points of the envelope alignment and the Phase Difference (PD) estimation are probably not the same point, making it difficult to uncouple the coupling term by conducting the correction of Migration Through Resolution Cell (MTRC). In this paper, an improved approach of joint processing which chooses certain scattering point as the sole reference point is proposed to perform with utilizing the Prominent Point Processing (PPP) method. With this end in view, we firstly get the initial image using classical methods from which a certain scattering point can be chose. The envelope alignment and phase compensation using the selected scattering point as the same reference point are subsequently conducted. The keystone transform is thus smoothly applied to further improve imaging quality. Both simulation experiments and real data processing are provided to demonstrate the performance of the proposed method compared with classical method.

  15. Nuclear Power Station Kalkar, 300 MWe Prototype Nuclear Power Plant with Fast Sodium Cooled Reactor (SNR-300), Plant description

    International Nuclear Information System (INIS)

    1984-06-01

    The nuclear power station Kalkar (SNR-300) is a prototype with a sodium cooled fast reactor and a thermal power of 762 MW. The present plant description has been made available in parallel to the licensing procedure for the reactor plant and its core Mark-Ia as supplementary information for the public. The report gives a detailed description of the whole plant including the prevention measures against the impact of external and plant internal events. The radioactive materials within the reactor cooling system and the irradiation protection and surveillance measures are outlined. Finally, the operation of the plant is described with the start-up procedures, power operation, shutdown phases with decay heat removal and handling procedures

  16. Model engineering for piping layout of boiling water reactor nuclear station

    International Nuclear Information System (INIS)

    Tsukada, Koji; Uchiyama, Masayuki; Wada, Takanao; Jibu, Noboru.

    1977-01-01

    A nuclear power station is made up of a wide variety of equipment, piping, ventilation ducts, conduits, and cable trays, etc. Even if equipment arrangement and piping layout are carefully planned on drawings, troubles such as interference often occur at field installation. Accordingly, it is thought very useful to make thorough examinations with plastic three-dimensional models in addition to drawings in reducing troubles at field, shortening the construction period, and improving economics. Examination with plastic models offers the following features: (1) It permits visual three-dimensional examination. (2) Group thinking and examination is possible. (3) Troubles due to failure to understand complicated drawings can be reduced drastically. Manufacturing a 1/20 scale model of the reactor building of the Tokai No. 2 Power Station of the Japan Atomic Power Co., Hitachi has performed model engineering-solution of interference troubles related to equipment and piping, securing of work space for in-service inspection (ISI), carry-in/installation of various equipment and piping, and determination of the piping route of which only the starting and terminating points were given under the complicated ambient conditions. Success with this procedure has confirmed that model engineering is an effective technique for future plant engineering. (auth.)

  17. How to handle station black outs

    Energy Technology Data Exchange (ETDEWEB)

    Reisch, Frigyes [Swedish Nuclear Power Inspectorate, S-10252 Stockholm (Sweden)

    1986-02-15

    Station black out is defined as the loss of ail high voltage alternating current at a nuclear power site. An international study was made to survey the practices in the different countries. The best way to handle station black out is to avoid it therefore briefly the normal off site and emergency on site power supplies are discussed. The ways in use to enhance nuclear power plants using Boiling Water Reactors or Pressurized Water Reactors to cope with a station black out are discussed in some detail. (author)

  18. How to handle station black outs

    International Nuclear Information System (INIS)

    Reisch, Frigyes

    1986-01-01

    Station black out is defined as the loss of ail high voltage alternating current at a nuclear power site. An international study was made to survey the practices in the different countries. The best way to handle station black out is to avoid it therefore briefly the normal off site and emergency on site power supplies are discussed. The ways in use to enhance nuclear power plants using Boiling Water Reactors or Pressurized Water Reactors to cope with a station black out are discussed in some detail. (author)

  19. Development and construction of nuclear power and nuclear heating stations in the USSR

    International Nuclear Information System (INIS)

    Schmidt, G.; Kirmse, B.

    1983-01-01

    The state-of-the-art of nuclear power technology in the USSR is reviewed by presenting characteristic data on design and construction. The review takes into consideration the following types of facilities: Nuclear power stations with 1000 MWe pressurized water reactors, with 1000 MWe pressure tube boiling water reactors, and with 600 MWe fast breeder reactors; nuclear heating power stations with 1000 MWe reactors and nuclear heating stations with 500 MWth boiling water reactors

  20. State-space model predictive control method for core power control in pressurized water reactor nuclear power stations

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Guo Xu; Wu, Jie; Zeng, Bifan; Wu, Wangqiang; Ma, Xiao Qian [School of Electric Power, South China University of Technology, Guangzhou (China); Xu, Zhibin [Electric Power Research Institute of Guangdong Power Grid Corporation, Guangzhou (China)

    2017-02-15

    A well-performed core power control to track load changes is crucial in pressurized water reactor (PWR) nuclear power stations. It is challenging to keep the core power stable at the desired value within acceptable error bands for the safety demands of the PWR due to the sensitivity of nuclear reactors. In this paper, a state-space model predictive control (MPC) method was applied to the control of the core power. The model for core power control was based on mathematical models of the reactor core, the MPC model, and quadratic programming (QP). The mathematical models of the reactor core were based on neutron dynamic models, thermal hydraulic models, and reactivity models. The MPC model was presented in state-space model form, and QP was introduced for optimization solution under system constraints. Simulations of the proposed state-space MPC control system in PWR were designed for control performance analysis, and the simulation results manifest the effectiveness and the good performance of the proposed control method for core power control.

  1. TEPCO plans to construct Higashidori Nuclear Power Station

    International Nuclear Information System (INIS)

    Tsuruta, Atsushi

    2008-01-01

    In 2006, TEPCO submitted to the government plans for the construction of Higashidori Nuclear Power Station. The application was filed 41 years after the project approved by the Higashidori Village Assembly. This nuclear power station will be the first new nuclear power plant constructed by TEPCO since the construction of Units No.6 and 7 at the Kashiwazaki Kariwa Nuclear Power Station 18 years ago. Higashidori Nuclear Power Station is to be constructed at a completely new site, which will become the fourth TEPCO nuclear power station. Higashidori Nuclear Power Station Unit No.1 will be TEPCO's 18th nuclear reactor. Unit No.1 will be an advanced boiling water reactor (ABWR), a reactor-type with a proven track record. It will be TEPCO's third ABWR. Alongside incorporating the latest technology, in Higashidori Nuclear Power Station Unit No.1, the most important requirement is for TEPCO to reflect in the new unit information and experience acquired from the operation of other reactors (information and experience acquired through the experience of operating TEPCO's 17 units at Fukushima Daiichi Nuclear Power Station, Fukushima Daini Nuclear Power Station and Kashiwazaki Kashiwa Nuclear Power Station in addition to information on non-conformities at nuclear power stations in Japan and around the world). Higashidori Nuclear Power Station is located in Higashidori-Village (Aomori Prefecture) and the selected site includes a rich natural environment. From an environmental perspective, we will implement the construction with due consideration for the land and sea environment, aiming to ensure that the plant can co-exist with its natural surroundings. The construction plans are currently being reviewed by the Nuclear and Industrial Safety Agency. We are committed to making progress in the project for the start of construction and subsequent commercial operation. (author)

  2. Economic simplified boiling water reactor (ESBWR) response to an extended station blackout/ loss of all AC power

    International Nuclear Information System (INIS)

    Barrett, A.J.; Marquino, W.

    2013-01-01

    U.S. federal regulations require light water cooled nuclear power plants to cope with Station Blackout for a predetermined amount of time based on design factors for the plant. U.S. regulations define Station Blackout (SBO) as a loss of the offsite electric power system concurrent with turbine trip and unavailability of the onsite emergency AC power system. According to U.S. regulations, typically the coping period for an SBO is 4 hours and can be as long as 16 hours for currently operating BWR plants. Being able to cope with an SBO and loss of all AC power is required by international regulators as well. The U.S. licensing basis for the ESBWR is a coping period of 72 hours for an SBO based on U.S. NRC requirements for passive safety plants. In the event of an extended SBO (viz., greater than 72 hours), the ESBWR response shows that the design is able to cope with the event for at least 7 days without AC electrical power or operator action. ESBWR is a Generation III+ reactor design with an array of passive safety systems. The ESBWR primary success path for mitigation of an SBO event is the Isolation Condenser System (ICS). The ICS is a passive, closed loop, safety system that initiates automatically on a loss of power. Upon Station Blackout or loss of all AC power, the ICS begins removing decay heat from the Reactor Pressure Vessel (RPV) by (i) condensing the steam into water in heat exchangers located in pools of water above the containment, and (ii) transferring the decay heat to the atmosphere. The condensed water is then returned by gravity to cool the reactor again. The ICS alone is capable of maintaining the ESBWR in a safe shutdown condition after an SBO for an extended period. The fuel remains covered throughout the SBO event. The ICS is able to remove decay heat from the RPV for at least 7 days and maintains the reactor in a safe shutdown condition. The water level in the RPV remains well above the top of active fuel for the duration of the SBO event

  3. Floating nuclear heat. And power station 'Pevec' with KLT-40S type reactor plant for remote regions of Russia

    International Nuclear Information System (INIS)

    Veshnyakov, K.B.; Kiryushin, A.I.; Panov, Yu.K.; Polunichev, V.I.

    2000-01-01

    Floating small nuclear power plants power for local energy systems of littoral regions of Russia, located far from central energy system, open a new line in nuclear power development. Designing a floating power unit of a lead nuclear heat and power generating station for port Pevec at the Chuckchee national district is currently nearing completion. Most labor-intensive components are being manufactured. The co-generation NPP Pevec is to be created on the basis of a floating power unit with KLT-40S type reactor plant. KLT-40S reactor plant is based on similar propulsion plants, verified at operation of Russia's nuclear-powered civil ships, evolutionary improved by elimination of 'weak points' revealed during its prototypes operation or on the basis of safety analysis. KLT-40S reactor plant uses the most wide-spread and developed in the world practice PWR-type reactor. KLT-40S meets contemporary national and international requirements imposed to future reactor plants. The NHPS description, its main technical-economic data, environmental safety indices, basic characteristics of KLT-40S reactor plant are presented. Prospects of small NPPs utilization outside Russia, particularly as an energy source for sea water desalination, are considered. (author)

  4. Comparison of oxide- and metal-core behavior during CRBRP [Clinch River Breeder Reactor Plant] station blackout

    International Nuclear Information System (INIS)

    Polkinghorne, S.T.; Atkinson, S.A.

    1986-01-01

    A resurrected concept that could significantly improve the inherently safe response of Liquid-Metal cooled Reactors (LMRs) during severe undercooling transients is the use of metallic fuel. Analytical studies have been reported on for the transient behavior of metal-fuel cores in innovative, inherently safe LMR designs. This paper reports on an analysis done, instead, for the Clinch River Breeder Reactor Plant (CRBRP) design with the only innovative change being the incorporation of a metal-fuel core. The SSC-L code was used to simulate a protected station blackout accident in the CRBRP with a 943 MWt Integral Fast Reactor (IFR) metal-fuel core. The results, compared with those for the oxide-fueled CRBRP, show that the margin to boiling is greater for the IFR core. However, the cooldown transient is more severe due to the faster thermal response time of metallic fuel. Some additional calculations to assess possible LMR design improvements (reduced primary system pressure losses, extended flow coastdown) are also discussed. 8 refs., 13 figs., 2 tabs

  5. Research on spatial-variant property of bistatic ISAR imaging plane of space target

    International Nuclear Information System (INIS)

    Guo Bao-Feng; Wang Jun-Ling; Gao Mei-Guo

    2015-01-01

    The imaging plane of inverse synthetic aperture radar (ISAR) is the projection plane of the target. When taking an image using the range-Doppler theory, the imaging plane may have a spatial-variant property, which causes the change of scatter’s projection position and results in migration through resolution cells. In this study, we focus on the spatial-variant property of the imaging plane of a three-axis-stabilized space target. The innovative contributions are as follows. 1) The target motion model in orbit is provided based on a two-body model. 2) The instantaneous imaging plane is determined by the method of vector analysis. 3) Three Euler angles are introduced to describe the spatial-variant property of the imaging plane, and the image quality is analyzed. The simulation results confirm the analysis of the spatial-variant property. The research in this study is significant for the selection of the imaging segment, and provides the evidence for the following data processing and compensation algorithm. (paper)

  6. Probabilistic safety analysis for fire events for the NPP Isar 2

    International Nuclear Information System (INIS)

    Schmaltz, H.; Hristodulidis, A.

    2007-01-01

    The 'Probabilistic Safety Analysis for Fire Events' (Fire-PSA KKI2) for the NPP Isar 2 was performed in addition to the PSA for full power operation and considers all possible events which can be initiated due to a fire. The aim of the plant specific Fire-PSA was to perform a quantitative assessment of fire events during full power operation, which is state of the art. Based on simplistic assumptions referring to the fire induced failures, the influence of system- and component-failures on the frequency of the core damage states was analysed. The Fire-PSA considers events, which will result due to fire-induced failures of equipment on the one hand in a SCRAM and on the other hand in events, which will not have direct operational effects but because of the fire-induced failure of safety related installations the plant will be shut down as a precautionary measure. These events are considered because they may have a not negligible influence on the frequency of core damage states in case of failures during the plant shut down because of the reduced redundancy of safety related systems. (orig.)

  7. Materials Test Station

    Data.gov (United States)

    Federal Laboratory Consortium — When completed, the Materials Test Station at the Los Alamos Neutron Science Center will meet mission need. MTS will provide the only fast-reactor-like irradiation...

  8. Uma Análise Crítica Entre os Currículos dos Cursos de Ciências Contábeis nos Países do Mercosul e o Proposto Pela ONU/UNCTAD/ISAR

    Directory of Open Access Journals (Sweden)

    Giovanna Tonetto Segantini

    2013-07-01

    Full Text Available A harmonização das normas contábeis tornou-se uma necessidade dos usuários externos e internos da informação contábil, uma vez que passaram a atuar em diversos mercados e a prestar contas aos usuários com necessidades variadas, pois o mercado cada vez mais globalizado exige profissionais preparados para atuar dentro e fora do seu país. Visando isso, a ONU/UNCTAD/ISAR desenvolveu um Currículo Mundial para servir de referência para os cursos de Ciências Contábeis, buscando prover conhecimentos internacionais de normas contábeis independentemente do país responsável pela formação do profissional. Assim, o objetivo geral do artigo foi analisar e comparar a adequação dos currículos dos cursos de ciências contábeis de quatro universidades do MERCOSUL, sendo uma de cada país, com o currículo proposto pela ONU/UNCTAD/ISAR. As universidades selecionadas foram: Facultad de Ciencias Econômicas de la Universidad de Buenos Aires (Argentina; Faculdade de Economia, Administração e Contabilidade da Universidade de São Paulo (Brasil; Universidad Nacional de Asunción (Paraguai; e Facultad de Ciências Econômicas y de Administración de la Universidad de la República (Uruguai, e suas matrizes curriculares foram comparadas com o Currículo Mundial proposto pela ONU/UNCTAD/ISAR. Os resultados indicam que a similaridade entre os currículos das quatro universidades selecionadas com o proposto pela ONU/UNCTAD/ISAR é alta, existindo, em média, 76,71% de semelhança entre as matérias dos currículos. Por ser apenas uma recomendação, as universidades pesquisadas demonstraram possuir certa flexibilidade na elaboração de seus currículos.

  9. Confirmatory Survey Results for the Reactor Building Dome Upper Structural Surfaces, Rancho Saco Nuclear Generating Station, Herald, California

    International Nuclear Information System (INIS)

    Wade C. Adams

    2006-01-01

    Results from a confirmatory survey of the upper structural surfaces of the Reactor Building Dome at the Rancho Seco Nuclear Generating Station (RSNGS) performed by the Oak Ridge Institute for Science and Education for the NRC. Also includes results of interlaboratory comparison analyses on several archived soil samples that would be provided by RSNGS personnel. The confirmatory surveys were performed on June 7 and 8, 2006

  10. Experience with reactor power cutback system at Palo Verde nuclear generating station

    International Nuclear Information System (INIS)

    Chari, D.R.; Rec, J.R.; Simoni, L.P.; Eimar, R.L.; Sowers, G.W.

    1987-01-01

    Palo Verde Nuclear Generating Station (PVNGS) is a three unit site which illustrates System 80 nuclear steam supply system (NSSS) design. The System 80 NSSS is the Combustion Engineering (C-E) standard design rated at 3817 Mwth. PVNGS Units 1 and 2 achieved commercial operation on February 13, 1986 and September 22, 1986, respectively, while Unit 3 has a forecast date for commercial operation in the third quarter of 1987. The System 80 design incorporates a reactor power cutback system (RPCS) feature which reduces plant trips caused by two common initiating events: loss of load/turbine trip (LOL) and loss of one main feedwater pump (LOMFWP). The key design objective of the RPCS is to improve overall plant availability and performance, while minimizing challenges to the plant safety system

  11. Socio-economic impacts of nuclear generating stations: Arkansas Nuclear One Station case study

    International Nuclear Information System (INIS)

    Pijawka, K.D.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Arkansas Nuclear One nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  12. The Paks Nuclear Power Station

    International Nuclear Information System (INIS)

    Erdosi, N.; Szabo, L.

    1978-01-01

    As the first stage in the construction of the Paks Nuclear Power Station, two units of 440 MW(e) each will be built. They are operated with two coolant loops each. The reactor units are VVER 440 type water-moderated PWR type heterogeneous power reactors designed in the Soviet Union and manufactured in Czechoslovakia. Each unit operates two Soviet-made K-220-44 steam turbines and Hungarian-made generators of an effective output of 220 MW. The output of the transformer units - also of Hungarian made - is 270 MVA. The radiation protection system of the nuclear power station is described. Protection against system failures is accomplished by specially designed equipment and security measures especially within the primary circuit. Some data on the power station under construction are given. (R.P.)

  13. Technology, safety and costs of decommissioning a Reference Boiling Water Reactor Power Station. Main report. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWe.

  14. Technology, safety, and costs of decommissioning a reference pressurized water reactor power station

    International Nuclear Information System (INIS)

    Smith, R.I.; Konzek, G.J.; Kennedy, W.E. Jr.

    1978-05-01

    Safety and cost information was developed for the conceptual decommissioning of a large [1175 MW(e)] pressurized water reactor (PWR) power station. Two approaches to decommissioning, Immediate Dismantlement and Safe Storage with Deferred Dismantlement, were studied to obtain comparisons between costs, occupational radiation doses, potential radiation dose to the public, and other safety impacts. Immediate Dismantlement was estimated to require about six years to complete, including two years of planning and preparation prior to final reactor shutdown, at a cost of $42 million, and accumulated occupational radiation dose, excluding transport operations, of about 1200 man-rem. Preparations for Safe Storage were estimated to require about three years to complete, including 1 1 / 2 years for planning and preparation prior to final reactor shutdown, at a cost of $13 million and an accumulated occupational radiation dose of about 420 man-rem. The cost of continuing care during the Safe Storage period was estimated to be about $80 thousand annually. Accumulated occupational radiation dose during the Safe Storage period was estimated to range from about 10 man-rem for the first 10 years to about 14 man-rem after 30 years or more. The cost of decommissioning by Safe Storage with Deferred Dismantlement was estimated to be slightly higher than Immediate Dismantlement. Cost reductions resulting from reduced volumes of radioactive material for disposal, due to the decay of the radioactive containments during the deferment period, are offset by the accumulated costs of surveillance and maintenance during the Safe Storage period

  15. Applicability of AWJ technique for dismantling reactor of the Fukushima Daiichi Nuclear Power Station. Cutting test of imitation of fuel debris and optimization of the cutting condition

    International Nuclear Information System (INIS)

    Maruyama, Shin-ichiro; Watatani, Satoshi

    2016-01-01

    Based on findings during recovery works that followed the accident at Three Mile Island Station 2, it is assumed that the reactor internals at the Fukushima Daiichi Nuclear Power Station (1F) have complex geometries intermixed with melted fuel and confined in limited spaces. Accordingly, abrasive water jet (AWJ) cutting method is considered to be a promising technique that can be safely and reasonably used for cutting and removing reactor internals. The authors conducted tests to examine the possibility of application and to solve the problems of this technique. In the tests imitation of fuel debris and optimization of the cutting condition is used. The test result made the measures for some of the associated issues clear, and demonstrated that AWJ cutting method is assumed as one of the promising techniques for removing reactor internals. (author)

  16. Electricity supplies in a French nuclear power station

    International Nuclear Information System (INIS)

    2011-01-01

    As the operation of a nuclear power station requires a power supply system enabling this operation as well as the installation safety, this document describes how such systems are designed in the different French nuclear power stations to meet the requirements during a normal operation (when the station produces electricity) or when it is stopped, but also to ensure power supply to equipment ensuring safety functions during an incident or an accident occurring on the installation. More precisely, these safety functions are provided by two independent systems in the French nuclear power stations. Their operation is briefly described. Two different types of nuclear reactors are addressed: pressurised water reactors (PWR) of second generation, EPR (or PWR of third generation)

  17. Vibration monitoring of large vertical pumps via a remote satellite station

    International Nuclear Information System (INIS)

    Cook, S.A.; Crowe, R.D.; Roblyer, S.P.; Toffer, H.

    1985-01-01

    The Hanford N Reactor is operated by UNC Nuclear Industries for the Department of Energy for the production of special isotopes and electric energy. The reactor has a unique design in which the equipment such as pumps, turbines, generators and diesel engines are located in separate buildings. This equipment arrangement has led to the conclusion that the most cost-effective implementation of a dedicated vibration monitoring system would be to install a computerized network system in lieu of a single analyzing station. In this approach, semi-autonomous micro processor based data collection stations referred to as satellite stations are located near each concentration of machinery to be monitored. The satellite stations provide near continuous monitoring of the machinery. They are linked to a minicomputer using voice grade telephone circuits and hardware and software specifically designed for network communications. The communications link between the satellite stations and the minicomputer permits data and programs to be transmitted between the units. This paper will describe the satellite station associated with large vertical pumps vibration monitoring. The reactor has four of these pumps to supply tertiary cooling to reactor systems. 4 figs

  18. Chernobyl reactor accident. A documentation submitted by the Deutsche Welle radio station. Der Fall Tschernobyl. Eine Dokumentation der Deutschen Welle

    Energy Technology Data Exchange (ETDEWEB)

    1986-01-01

    The documentation abstracted contains a complete survey of the broadcasts transmitted by the Russian wire service of the Deutsche Welle radio station between April 28 and May 15, 1986 on the occasion of the Chernobyl reactor accident. Access is given to extracts of the remarkable eastern and western echoes on the broadcasts of the Deutsche Welle.

  19. Comparison of wastewater plant of Nova Pampulha, with an UASB reactor, with another ten brazilian stations; Comparacion de la EDAR de Nova Pampulha, dotada de reactor UASB, con otras diez plantas brasilenas

    Energy Technology Data Exchange (ETDEWEB)

    Barrosa Correa, S. M. B.; Ruiz, E.; Romero, F.

    2004-07-01

    This work is based on data of the wastewater plant of Nova Pampulha with an UASB reactor. The objective of this research was focussed in the comparison of this plant with another ten brazilian stations provided with different depuration techniques. Firstly the graphical comparison of average operational data suggest analogies between influents (less suspended solids in the Nova Pampulha), effluent (more suspended solids and bacteria in the same station) and alimentation's (smaller for suspended solids and bacteria in Nova Pampulha, where there is also an increase in alkalinity). Cluster analysis, made with percentages of elimination of constituents in the eleven stations and shown as dendrograms, was chosen as the second comparative method. A third comparison was affected by multiple linear regression for obtaiming mathematical models from the eliminations of constituents, with statistical significance at level of the 95% confidence, using as possible independent variables the flows and the concentrations of influents. The explanations of the variances of data by the calculated equations is in the range 46 to 91%. As a general conclusion, it can be said that a well operated UASB reactor may be a satisfactory technique for wastewater treatment and well adapted to climatological Brazilian conditions. (Author) 14 refs.

  20. Light-water nuclear reactors

    International Nuclear Information System (INIS)

    Drevon, G.

    1983-01-01

    This work gives basic information on light-water reactors which is advanced enough for the reader to become familiar with the essential objectives and aspects of their design, their operation and their insertion in the industrial, economic and human environment. In view of the capital role of electric energy in the modern economy a significant place is given to electron-nuclear power stations, particularly those of the type adopted for the French programme. The work includes sixteen chapters. The first chapter relates the history and presents the various applications of light water reactors. The second refers to the general elementary knowledge of reactor physics. The third chapter deals with the high power light-water nuclear power station and thereby introduces the ensuing chapters which, up to and including chapter 13, are devoted to the components and the various aspects of the operation of power stations, in particular safety and the relationship with the environment. Chapter 14 provides information on the reactors adapted to applications other than the generation of electricity on an industrial scale. Chapter 15 shows the extent of the industrial effort devoted to light-water reactors and chapter 16 indicates the paths along which the present work is preparing the future of these reactors. The various chapters have been written to allow for separate consultation. An index of the main technical terms and a bibliography complete the work [fr

  1. Graphite-water steam-generating reactor in the USSR

    Energy Technology Data Exchange (ETDEWEB)

    Dollezhal, N A [AN SSSR, Moscow

    1981-10-01

    One of the types of power reactor used in the USSR is the graphite-water steam-generating reactor RBMK. This produces saturated steam at a pressure of 7MPa. Reactors giving 1GWe each have been installed at the Leningrad, Kursk, Chernobyl and other power stations. Further stations using reactors of this type are being built. A description is given of the fuel element design, and of the layout of the plant. The main characteristics of RBMK reactors using fuel of rated and higher enrichment are listed.

  2. The prototype fast reactor

    International Nuclear Information System (INIS)

    Broomfield, A.M.

    1985-01-01

    The paper concerns the Prototype Fast Reactor (PFR), which is a liquid metal cooled fast reactor power station, situated at Dounreay, Scotland. The principal design features of a Fast Reactor and the PFR are given, along with key points of operating history, and health and safety features. The role of the PFR in the development programme for commercial reactors is discussed. (U.K.)

  3. Light Water Reactor Sustainability Program: Analysis of Pressurized Water Reactor Station Blackout Caused by External Flooding Using the RISMC Toolkit

    Energy Technology Data Exchange (ETDEWEB)

    Smith, Curtis [Idaho National Lab. (INL), Idaho Falls, ID (United States); Mandelli, Diego [Idaho National Lab. (INL), Idaho Falls, ID (United States); Prescott, Steven [Idaho National Lab. (INL), Idaho Falls, ID (United States); Alfonsi, Andrea [Idaho National Lab. (INL), Idaho Falls, ID (United States); Rabiti, Cristian [Idaho National Lab. (INL), Idaho Falls, ID (United States); Cogliati, Joshua [Idaho National Lab. (INL), Idaho Falls, ID (United States); Kinoshita, Robert [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-08-01

    The existing fleet of nuclear power plants is in the process of extending its lifetime and increasing the power generated from these plants via power uprates. In order to evaluate the impact of these factors on the safety of the plant, the Risk Informed Safety Margin Characterization (RISMC) project aims to provide insight to decision makers through a series of simulations of the plant dynamics for different initial conditions (e.g., probabilistic analysis and uncertainty quantification). This report focuses, in particular, on the application of a RISMC detailed demonstration case study for an emergent issue using the RAVEN and RELAP-7 tools. This case study looks at the impact of a couple of challenges to a hypothetical pressurized water reactor, including: (1) a power uprate, (2) a potential loss of off-site power followed by the possible loss of all diesel generators (i.e., a station black-out event), (3) and earthquake induces station-blackout, and (4) a potential earthquake induced tsunami flood. The analysis is performed by using a set of codes: a thermal-hydraulic code (RELAP-7), a flooding simulation tool (NEUTRINO) and a stochastic analysis tool (RAVEN) – these are currently under development at the Idaho National Laboratory.

  4. Operating experience at Scottish Nuclear's power stations

    International Nuclear Information System (INIS)

    Blackburn, P.

    1991-01-01

    A brief history is presented of the design and operation of the four Scottish nuclear power stations currently run by Scottish Nuclear, namely Hunterston 'A' and 'B' and the Torness reactors. A design flaw in the Magnox reactor at Hunterston 'A' led to it being operated at lower than optimal temperature and hence producing less power. For Hunterston 'B' reactor the Advanced Gas Cooled design prototype was used. Operating setbacks and successes are noted. The design chosen for Torness embraced all the good points of Hunterston 'B' but sought to eliminate its faults. After 26 years of successful operation Hunterston 'A' is now being decommissioned, while the other three stations continue to generate electricity successfully. (UK)

  5. Technology, safety and costs of decommissioning a reference pressurized water reactor power station. Classification of decommissioning wastes. Addendum 3

    International Nuclear Information System (INIS)

    Murphy, E.S.

    1984-09-01

    The radioactive wastes expected to result from decommissioning of the reference pressurized water reactor power station are reviewed and classified in accordance with 10 CFR 61. The 17,885 cubic meters of waste from DECON are classified as follows: Class A, 98.0%; Class B, 1.2%; Class C, 0.1%. About 0.7% (133 cubic meters) of the waste would be generally unacceptable for disposal using near-surface disposal methods

  6. Experience in surveillance of the prestress of concrete reactor vessels in Wylfa nuclear power station

    International Nuclear Information System (INIS)

    Dawson, P.; Paton, A.A.; Walsh, S.R.

    1989-01-01

    This paper describes experience gained in the in-service surveillance of the prestressing system for the prestressed concrete reactor vessels (PCRVs) at Wylfa nuclear power station. The paper gives details of results for the prestressing system obtained from the statutory in-service inspection program of the PCRVs. The program includes a detailed examination of a selection of prestressing tendon anchorages, anchorage load checks using a lift-off technique on a one percent sample of tendons and corrosion inspection of samples of prestressing strand and determination of their mechanical properties. The results obtained from the above in-service inspections have shown that the prestressing system continues to function within its design limits

  7. Advanced gas-cooled reactors (AGR)

    Energy Technology Data Exchange (ETDEWEB)

    Yeomans, R. M. [South of Scotland Electricity Board, Hunterston Power Station, West Kilbride, Ayshire, UK

    1981-01-15

    The paper describes the advanced gas-cooled reactor system, Hunterston ''B'' power station, which is a development of the earlier natural uranium Magnox type reactor. Data of construction, capital cost, operating performance, reactor safety and also the list of future developments are given.

  8. On the troubles happened in nuclear power stations, 1995

    International Nuclear Information System (INIS)

    1996-01-01

    The troubles which happened at the nuclear power stations of Japan in the fiscal year of 1995 are described in this report. The number of troubles in those power stations reported from the corporations of electric industry to Nuclear Safety Commission according to The Law for Regulation of Nuclear Fertile Material, Nuclear Fuel Material and Reactors and Utility Industry Law were 14 in the year and so, the number per reactor was 0.3. The details of the trouble cases were as follows; one and nine cases for automatic and manual shutdowns in operation, respectively and 4 cases found during a down-time of the reactor. But, there was no influence on the environment surrounding those nuclear power stations by the radioactive materials in either of the cases. (M.N.)

  9. Steam turbines for PWR stations

    International Nuclear Information System (INIS)

    Muscroft, J.

    1989-01-01

    The thermodynamic cycle requirements and mechanical design features applying to modern GEC 3000 rev/min steam turbines for pressurised water reactor power stations are reviewed. The most recent developments include machines of 630 MW and 985 MW output which are currently under construction. The importance of service experience with nuclear wet steam turbines associated with a variety of types of water cooled reactor and its relevance to the design of modern 3000 rev/min turbines for pressurised water reactor applications is emphasised. (author)

  10. Determination of neutron energy spectrum at a pneumatic rabbit station of a typical swimming pool type material test research reactor

    International Nuclear Information System (INIS)

    Malkawi, S.R.; Ahmad, N.

    2002-01-01

    The method of multiple foil activation was used to measure the neutron energy spectrum, experimentally, at a rabbit station of Pakistan Research Reactor-1 (PARR-1), which is a typical swimming pool type material test research reactor. The computer codes MSITER and SANDBP were used to adjust the spectrum. The pre-information required by the adjustment codes was obtained by modelling the core and its surroundings in three-dimensions by using the one dimensional transport theory code WIMS-D/4 and the multidimensional finite difference diffusion theory code CITATION. The input spectrum covariance information required by MSITER code was also calculated from the CITATION output. A comparison between calculated and adjusted spectra shows a good agreement

  11. Prototype moving-ring reactor

    International Nuclear Information System (INIS)

    Smith, A.C. Jr.; Ashworth, C.P.; Abreu, K.E.

    1982-01-01

    We have completed a design of the Prototype Moving-Ring Reactor. The fusion fuel is confined in current-carrying rings of magnetically-field-reversed plasma (Compact Toroids). The plasma rings, formed by a coaxial plasma gun, undergo adiabatic magnetic compression to ignition temperature while they are being injected into the reactor's burner section. The cylindrical burner chamber is divided into three burn stations. Separator coils and a slight axial guide field gradient are used to shuttle the ignited toroids rapidly from one burn station to the next, pausing for 1/3 of the total burn time at each station. D-T- 3 He ice pellets refuel the rings at a rate which maintains constant radiated power

  12. Design and verification of computer-based reactor control system modification at Bruce-A candu nuclear generating station

    International Nuclear Information System (INIS)

    Basu, S.; Webb, N.

    1995-01-01

    The Reactor Control System at Bruce-A Nuclear Generating Station is going through some design modifications, which involve a rigorous design process including independent verification and validation. The design modification includes changes to the control logic, alarms and annunciation, hardware and software. The design (and verification) process includes design plan, design requirements, hardware and software specifications, hardware and software design, testing, technical review, safety evaluation, reliability analysis, failure mode and effect analysis, environmental qualification, seismic qualification, software quality assurance, system validation, documentation update, configuration management, and final acceptance. (7 figs.)

  13. Pumps for nuclear power stations

    International Nuclear Information System (INIS)

    Ogura, Shiro

    1979-01-01

    16 nuclear power plants are in commercial operation in Japan, and nuclear power generation holds the most important position among various substitute energies. Hereafter also, it is expected that the construction of nuclear power stations will continue because other advantageous energy sources are not found. In this paper, the outline of the pumps used for BWR plants is described. Nuclear power stations tend to be large scale to reduce the construction cost per unit power output, therefore the pumps used are those of large capacity. The conditions to be taken in consideration are high temperature, high pressure, radioactive fluids, high reliability, hydrodynamic performances, aseismatic design, relevant laws and regulations, and quality assurance. Pumps are used for reactor recirculation system, control rod driving hydraulic system, boric acid solution injecting system, reactor coolant purifying system, fuel pool cooling and purifying system, residual heat removing system, low pressure and high pressure core spraying systems, and reactor isolation cooling system, for condensate, feed water, drain and circulating water systems of turbines, for fresh water, sea water, make-up water and fire fighting services, and for radioactive waste treating system. The problems of the pumps used for nuclear power stations are described, for example, the requirement of high reliability, the measures to radioactivity and the aseismatic design. (Kako, I.)

  14. Care management at Ikata Power Station

    International Nuclear Information System (INIS)

    Sakai, Koji

    1982-01-01

    For operating nuclear power stations safely and economically, it is necessary to control nuclear fuel itself and reactor cores. Nuclear fuel must be controlled consistently in view of quantitative balance and operational method over the whole nuclear fuel cycle of uranium ore, fabrication, burning in reactors and reprocessing, based on the plan of using fuel in electric power companies. The control of the burning in reactors is called core management, and it is important because the users of fuel execute it. For dealing with such core management works, Shikoku Electric Power Co., Inc., has developed the computer code system for grasping the state of fuel exchange and the burning condition in reactors and used it since 1972. The outline of the core management in Ikata Power Station is reported in this paper centering around computing works. The core management works are divided into those at the time of regular inspection and those in operation. In the regular inspection, fuel inspection, fuel exchange and reactor physics test are performed. In operation, the burning condition of fuel is grasped. The technical computations corresponding to these works are explained, and the examples of computations are shown. (Kako, I.)

  15. Nuclear power station achievement 1968-1980

    International Nuclear Information System (INIS)

    Howles, L.R.

    This report reviews and gives an analysis of the achievement of operating nuclear power stations in the Western world on three relevant bases: (1) both annual and cumulative achievement of all nuclear power stations at a particular time; (2) cumulative achievement of all nuclear power stations at the end of the first and subsequent years of their lives to show trends with age; (3) achievement based on refuelling period considerations. Nowhere in the report are any operating details ignored, omitted or eliminated in the method of analysis. Summarising the results of the reviews shows: an improvement with time from initial electricity generation on all bases; that initially, larger sizes of reactor/turbine operate less well than smaller sizes (except for PHWR's); that after an initial number of years, the largest size units operate as well as the intermediate and smaller sizes, or better in the PHWR case; that a 75 per cent cumulative load factor achievement in the middle years of a reactor/turbines life can be expected on the refuelling period considerations base; that at June 1980, 35 nuclear power stations achieved an annual load factor over 75 per cent; that the above achievement was possible despite the repercussions following the Three Mile Island 'accident' and the shutdowns in the USA for piping system seismic adequacy checks required by the Nuclear Regulatory Commission for five nuclear power stations; and that even when reactors/turbines are reaching towards the end of their design life, there is no rapid deterioration in their achievements. (author)

  16. Forced vibration tests on the reactor building of a nuclear power station, 1

    International Nuclear Information System (INIS)

    Takeda, Toshikazu; Tsunoda, Tomohiko; Wakamatsu, Kunio; Kaneko, Masataka; Nakamura, Mitsuru; Kunoh, Toshio; Murahashi, Hisahiro

    1988-01-01

    Tsuruga Unit No.2 Nuclear Power Station of the Japan Atomic Power Company is the first PWR-type 4-loop plant constructed in Japan with a prestressed concrete containment vessel (PCCV). This report describes forced vibration tests carried out on the reactor building of this plant. The following were obtained as results: (1) The results of the forced vibration tests corresponded well on the whole with design values. (2) The vibration characteristics of the PCCV observed in the tests after prestressing are no different from the ones before prestressing. This shows that the vibration properties of the PCCV are practically independent of prestressing loads. (3) A seismic response analysis of the design basis earthquake was made on the design model reflecting the test results. The seismic safety of the plant was confirmed by this analysis. (author)

  17. Micro-motion Recognition of Spatial Cone Target Based on ISAR Image Sequences

    Directory of Open Access Journals (Sweden)

    Changyong Shu

    2016-04-01

    Full Text Available The accurate micro-motions recognition of spatial cone target is the foundation of the characteristic parameter acquisition. For this reason, a micro-motion recognition method based on the distinguishing characteristics extracted from the Inverse Synthetic Aperture Radar (ISAR sequences is proposed in this paper. The projection trajectory formula of cone node strong scattering source and cone bottom slip-type strong scattering sources, which are located on the spatial cone target, are deduced under three micro-motion types including nutation, precession, and spinning, and the correctness is verified by the electromagnetic simulation. By comparison, differences are found among the projection of the scattering sources with different micro-motions, the coordinate information of the scattering sources in the Inverse Synthetic Aperture Radar sequences is extracted by the CLEAN algorithm, and the spinning is recognized by setting the threshold value of Doppler. The double observation points Interacting Multiple Model Kalman Filter is used to separate the scattering sources projection of the nutation target or precession target, and the cross point number of each scattering source’s projection track is used to classify the nutation or precession. Finally, the electromagnetic simulation data are used to verify the effectiveness of the micro-motion recognition method.

  18. Nuclear district heating. 1. Process heat reactors and transmission and distribution networks

    International Nuclear Information System (INIS)

    Caizergues, R.

    1979-01-01

    Three kinds of production station are considered: joint electricity and heat-producing stations, heat-producing stations with CAS reactors and heat-producing stations with Thermos reactors. The thermal energy supply possibilities of these stations, the cost price of this energy and the cost price per therm produced by the district heating source and conveyed to the user are studied [fr

  19. Advanced gas cooled reactors - Designing for safety

    International Nuclear Information System (INIS)

    Keen, Barry A.

    1990-01-01

    The Advanced Gas-Cooled Reactor Power Stations recently completed at Heysham in Lancashire, England, and Torness in East Lothian, Scotland represent the current stage of development of the commercial AGR. Each power station has two reactor turbo-generator units designed for a total station output of 2x660 MW(e) gross although powers in excess of this have been achieved and it is currently intended to uprate this as far as possible. The design of both stations has been based on the successful operating AGRs at Hinkley Point and Hunterston which have now been in-service for almost 15 years, although minor changes were made to meet new safety requirements and to make improvements suggested by operating experience. The construction of these new AGRs has been to programme and within budget. Full commercial load for the first reactor at Torness was achieved in August 1988 with the other three reactors following over the subsequent 15 months. This paper summarises the safety principles and guidelines for the design of the reactors and discusses how some of the main features of the safety case meet these safety requirements. The paper also summarises the design problems which arose during the construction period and explains how these problems were solved with the minimum delay to programme

  20. Advanced gas cooled reactors - Designing for safety

    Energy Technology Data Exchange (ETDEWEB)

    Keen, Barry A [Engineering Development Unit, NNC Limited, Booths Hall, Knutsford, Cheshire (United Kingdom)

    1990-07-01

    The Advanced Gas-Cooled Reactor Power Stations recently completed at Heysham in Lancashire, England, and Torness in East Lothian, Scotland represent the current stage of development of the commercial AGR. Each power station has two reactor turbo-generator units designed for a total station output of 2x660 MW(e) gross although powers in excess of this have been achieved and it is currently intended to uprate this as far as possible. The design of both stations has been based on the successful operating AGRs at Hinkley Point and Hunterston which have now been in-service for almost 15 years, although minor changes were made to meet new safety requirements and to make improvements suggested by operating experience. The construction of these new AGRs has been to programme and within budget. Full commercial load for the first reactor at Torness was achieved in August 1988 with the other three reactors following over the subsequent 15 months. This paper summarises the safety principles and guidelines for the design of the reactors and discusses how some of the main features of the safety case meet these safety requirements. The paper also summarises the design problems which arose during the construction period and explains how these problems were solved with the minimum delay to programme.

  1. Study on vibration characteristics and fault diagnosis method of oil-immersed flat wave reactor in Arctic area converter station

    Science.gov (United States)

    Lai, Wenqing; Wang, Yuandong; Li, Wenpeng; Sun, Guang; Qu, Guomin; Cui, Shigang; Li, Mengke; Wang, Yongqiang

    2017-10-01

    Based on long term vibration monitoring of the No.2 oil-immersed fat wave reactor in the ±500kV converter station in East Mongolia, the vibration signals in normal state and in core loose fault state were saved. Through the time-frequency analysis of the signals, the vibration characteristics of the core loose fault were obtained, and a fault diagnosis method based on the dual tree complex wavelet (DT-CWT) and support vector machine (SVM) was proposed. The vibration signals were analyzed by DT-CWT, and the energy entropy of the vibration signals were taken as the feature vector; the support vector machine was used to train and test the feature vector, and the accurate identification of the core loose fault of the flat wave reactor was realized. Through the identification of many groups of normal and core loose fault state vibration signals, the diagnostic accuracy of the result reached 97.36%. The effectiveness and accuracy of the method in the fault diagnosis of the flat wave reactor core is verified.

  2. Socio-economic impacts of nuclear generating stations

    International Nuclear Information System (INIS)

    Weisiger, M.L.; Pijawka, K.D.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the St. Lucie nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  3. BN800: The advanced sodium cooled fast reactor plant based on close fuel cycle

    International Nuclear Information System (INIS)

    Wu Xingman

    2011-01-01

    As one of the advanced countries with actually fastest reactor technology, Russia has always taken a leading role in the forefront of the development of fast reactor technology. After successful operation of BN600 fast reactor nuclear power station with a capacity of six hundred thousand kilowatts of electric power for nearly 30 years, and after a few decades of several design optimization improved and completed on its basis, it is finally decided to build Unit 4 of Beloyarsk nuclear power station (BN800 fast reactor power station). The BN800 fast reactor nuclear power station is considered to be the project of the world's most advanced fast reactor nuclear power being put into implementation. The fast reactor technology in China has been developed for decades. With the Chinese pilot fast reactor to be put into operation soon, the Chinese model fast reactor power station has been put on the agenda. Meanwhile, the closed fuel cycle development strategy with fast reactor as key aspect has given rise to the concern of experts and decision-making level in relevant areas. Based on the experiences accumulated in many years in dealing the Sino-Russian cooperation in fast reactor technology, with reference to the latest Russian published and authoritative literatures regarding BN800 fast reactor nuclear power station, the author compiled this article into a comprehensive introduction for reference by leaders and experts dealing in the related fields of nuclear fuel cycle strategy and fast reactor technology development researches, etc. (authors)

  4. Extended Station Blackout Analyses of an APR1400 with MARS-KS

    International Nuclear Information System (INIS)

    Kim, WoongBae; Jang, HyungWook; Oh, Seungjong; Lee, Sangyong

    2016-01-01

    The Fukushima Dai-ichi nuclear power plant accident shows that natural disasters such as earthquakes and the subsequent tsunamis can cause station blackout for several days. The electricity required for essential systems during a station blackout is provided from the emergency backup batteries installed at the nuclear power plant. In South Korea, in the event of an extended station blackout, the life of these emergency backup batteries has recently been extended from 8 hours to 24 hours at Shin-Kori 5, 6 and APR1400 for design certification. For a battery life of 24 hours, available safety means system, equipment and procedures are studied and analyzed in their ability to cope with an extended station blackout. A sensitivity study of reactor coolant pump seal leakage is performed to verify how different seal leakages could affect the system. For simulating of extended station blackout scenarios, the best estimate MARS-KS was used. In this paper, an APR1400 RELAP5 input deck was developed for station blackout scenario to analyze operation strategy by manually depressurizing the reactor coolant system through the steam generator's secondary side. Additionally, a sensitivity study was performed on reactor coolant pump seal leakage

  5. Extended Station Blackout Analyses of an APR1400 with MARS-KS

    Energy Technology Data Exchange (ETDEWEB)

    Kim, WoongBae; Jang, HyungWook; Oh, Seungjong; Lee, Sangyong [KEPCO International Nuclear Graduate School, Ulsan (Korea, Republic of)

    2016-10-15

    The Fukushima Dai-ichi nuclear power plant accident shows that natural disasters such as earthquakes and the subsequent tsunamis can cause station blackout for several days. The electricity required for essential systems during a station blackout is provided from the emergency backup batteries installed at the nuclear power plant. In South Korea, in the event of an extended station blackout, the life of these emergency backup batteries has recently been extended from 8 hours to 24 hours at Shin-Kori 5, 6 and APR1400 for design certification. For a battery life of 24 hours, available safety means system, equipment and procedures are studied and analyzed in their ability to cope with an extended station blackout. A sensitivity study of reactor coolant pump seal leakage is performed to verify how different seal leakages could affect the system. For simulating of extended station blackout scenarios, the best estimate MARS-KS was used. In this paper, an APR1400 RELAP5 input deck was developed for station blackout scenario to analyze operation strategy by manually depressurizing the reactor coolant system through the steam generator's secondary side. Additionally, a sensitivity study was performed on reactor coolant pump seal leakage.

  6. CANDU reactor experience: fuel performance

    International Nuclear Information System (INIS)

    Truant, P.T.; Hastings, I.J.

    1985-07-01

    Ontario Hydro has more than 126 reactor-years experience in operating CANDU reactors. Fuel performance has been excellent with 47 000 channel fuelling operations successfully completed and 99.9 percent of the more than 380 000 bundles irradiated operating as designed. Fuel performance limits and fuel defects have had a negligible effect on station safety, reliability, the environment and cost. The actual incapability charged to fuel is less than 0.1 percent over the stations' lifetimes, and more recently has been zero

  7. International breeder reactor development

    International Nuclear Information System (INIS)

    Traube, K.

    1976-01-01

    For more than a decade, sodium cooled breeder reactors have now been in the focus of advanced nuclear power development in the major industrialized countries. In the sixties, a total of seven small experimental nuclear power stations were commissioned. Two of these have been shut down in the meantime, the others continue to work satisfactorily, their main purpose being the development of fuel elements. The years 1972-1974 saw the commissioning of the prototype power stations in the 300 MWe power category in France, the United Kingdom and the Soviet Union. Presently, other experimental reactors are under construction in the Federal Republic of Germany, Italy, Japan, the United States, plus another Soviet 600 MWe prototype reactor and the SNR 300 DeBeNeLux prototype at Kalkar. A comparison of the technological features either implemented or planned in the prototype and experimental power plants and of their fuel elements reveals a remarkable similarity in the basic concepts pursued in different countries. The two types of breeder reactors, viz. the loop and the pool types, show a closer resemblance to each other than do pressurized and boilling water reactors. The growing awareness of administrative problems emerging in the approaching phase of the introduction of large breeder power stations in a number of European countries has recently led to a streamlining effort in the structure of industries and to tentative steps towards international cooperation on a broad basis. (orig.) [de

  8. Reactor control system. PWR

    International Nuclear Information System (INIS)

    2009-01-01

    At present, 23 units of PWR type reactors have been operated in Japan since the start of Mihama Unit 1 operation in 1970 and various improvements have been made to upgrade operability of power stations as well as reliability and safety of power plants. As the share of nuclear power increases, further improvements of operating performance such as load following capability will be requested for power stations with more reliable and safer operation. This article outlined the reactor control system of PWR type reactors and described the control performance of power plants realized with those systems. The PWR control system is characterized that the turbine power is automatic or manually controlled with request of the electric power system and then the nuclear power is followingly controlled with the change of core reactivity. The system mainly consists of reactor automatic control system (control rod control system), pressurizer pressure control system, pressurizer water level control system, steam generator water level control system and turbine bypass control system. (T. Tanaka)

  9. Nuclear reactor types

    International Nuclear Information System (INIS)

    Jones, P.M.S.

    1987-01-01

    The characteristics of different reactor types designed to exploit controlled fission reactions are explained. Reactors vary from low power research devices to high power devices especially designed to produce heat, either for direct use or to produce steam to drive turbines to generate electricity or propel ships. A general outline of basic reactors (thermal and fast) is given and then the different designs considered. The first are gas cooled, including the Magnox reactors (a list of UK Magnox stations and reactor performance is given), advanced gas cooled reactors (a list of UK AGRs is given) and the high temperature reactor. Light water cooled reactors (pressurized water [PWR] and boiling water [BWR] reactors) are considered next. Heavy water reactors are explained and listed. The pressurized heavy water reactors (including CANDU type reactors), boiling light water, steam generating heavy water reactors and gas cooled heavy water reactors all come into this category. Fast reactors (liquid metal fast breeder reactors and gas cooled fast reactors) and then water-cooled graphite-moderated reactors (RBMK) (the type at Chernobyl-4) are discussed. (U.K.)

  10. High-temperature and breeder reactors - economic nuclear reactors of the future

    International Nuclear Information System (INIS)

    Djalilzadeh, A.M.

    1977-01-01

    The thesis begins with a review of the theory of nuclear fission and sections on the basic technology of nuclear reactors and the development of the first generation of gas-cooled reactors applied to electricity generation. It then deals in some detail with currently available and suggested types of high temperature reactor and with some related subsidiary issues such as the coupling of different reactor systems and various schemes for combining nuclear reactors with chemical processes (hydrogenation, hydrogen production, etc.), going on to discuss breeder reactors and their application. Further sections deal with questions of cost, comparison of nuclear with coal- and oil-fired stations, system analysis of reactor systems and the effect of nuclear generation on electricity supply. (C.J.O.G.)

  11. Socioeconomic impacts of nuclear generating stations: Arkansas Nuclear One station case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Pijawka, K.D.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Arkansas Nuclear One nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  12. Gas-cooled reactors

    International Nuclear Information System (INIS)

    Schulten, R.; Trauger, D.B.

    1976-01-01

    Experience to date with operation of high-temperature gas-cooled reactors has been quite favorable. Despite problems in completion of construction and startup, three high-temperature gas-cooled reactor (HTGR) units have operated well. The Windscale Advanced Gas-Cooled Reactor (AGR) in the United Kingdom has had an excellent operating history, and initial operation of commercial AGRs shows them to be satisfactory. The latter reactors provide direct experience in scale-up from the Windscale experiment to fullscale commercial units. The Colorado Fort St. Vrain 330-MWe prototype helium-cooled HTGR is now in the approach-to-power phase while the 300-MWe Pebble Bed THTR prototype in the Federal Republic of Germany is scheduled for completion of construction by late 1978. THTR will be the first nuclear power plant which uses a dry cooling tower. Fuel reprocessing and refabrication have been developed in the laboratory and are now entering a pilot-plant scale development. Several commercial HTGR power station orders were placed in the U.S. prior to 1975 with similar plans for stations in the FRG. However, the combined effects of inflation, reduced electric power demand, regulatory uncertainties, and pricing problems led to cancellation of the 12 reactors which were in various stages of planning, design, and licensing

  13. Comparative analysis of station blackout accident progression in typical PWR, BWR, and PHWR

    International Nuclear Information System (INIS)

    Park, Soo Young; Ahn, Kwang Il

    2012-01-01

    Since the crisis at the Fukushima plants, severe accident progression during a station blackout accident in nuclear power plants is recognized as a very important area for accident management and emergency planning. The purpose of this study is to investigate the comparative characteristics of anticipated severe accident progression among the three typical types of nuclear reactors. A station blackout scenario, where all off-site power is lost and the diesel generators fail, is simulated as an initiating event of a severe accident sequence. In this study a comparative analysis was performed for typical pressurized water reactor (PWR), boiling water reactor (BWR), and pressurized heavy water reactor (PHWR). The study includes the summarization of design differences that would impact severe accident progressions, thermal hydraulic/severe accident phenomenological analysis during a station blackout initiated-severe accident; and an investigation of the core damage process, both within the reactor vessel before it fails and in the containment afterwards, and the resultant impact on the containment.

  14. Extended station blackout analyses of an APR1400 with MARS-KS

    Directory of Open Access Journals (Sweden)

    Kim Woongbae

    2016-01-01

    Full Text Available The Fukushima Daiichi nuclear power plant accident shows that natural disasters such as earthquakes and the subsequent tsunamis can cause station blackout for several days. The electric energy required for essential systems during a station blackout is provided from emergency backup batteries installed at the nuclear power plant. In South Korea, in the event of an extended station blackout, the life of these emergency backup batteries has recently been extended from 8 hours to 24 hours at Shin-Kori 5, 6, and APR1400 for design certification. For a battery life of 24 hours, available safety means system, equipment and procedures are studied and analyzed in their ability to cope with an extended station blackout. A sensitivity study of reactor coolant pump seal leakage is performed to verify how different seal leakages could affect the system. For simulating extended station blackout scenarios, the best estimate MARS-KS computer code was used. In this paper, an APR1400 RELAP5 input deck was developed for station blackout scenario to analyze operation strategy by manually depressurizing the reactor coolant system through the steam generator's secondary side. Additionally, a sensitivity study on reactor coolant pump seal leakage was carried out.

  15. Shippingport Station Decommissioning Project: overview and justification

    International Nuclear Information System (INIS)

    Coffman, F.E.

    1984-01-01

    The purpose of this booklet is to brief the reader on the Shippingport Station Decommissioning Project and to summarize the benefits of funding the project in FY 1984. Background information on the station and the decommissioning project is provided in this section of the booklet; the need for a reactor decommissining demonstration is discussed in the next section; and a summary of how the Shippingport Station Decommissioning Project (SSDP) provides the needed demonstration is provided in the final section

  16. Pressurised water reactor operation

    International Nuclear Information System (INIS)

    Birnie, S.; Lamonby, J.K.

    1987-01-01

    The operation of a pressurized water reactor (PWR) is described with respect to the procedure for a unit start-up. The systems details and numerical data are for a four loop PWR station of the design proposed for Sizewell-'B', United Kingdom. A description is given of: the initial conditions, filling the reactor coolant system (RCS), heat-up and pressurisation of the RCS, secondary system preparations, reactor start-up, and reactivity control at power. (UK)

  17. Reactor safety in Eastern Europe

    International Nuclear Information System (INIS)

    1995-02-01

    The papers presented to the GRS colloquium refer to the cooperative activities for reactor accident analysis and modification of the GRS computer codes for their application to reactors of the Russian design types of WWER or RBMK. Another topic is the safety of RBMK reactors in particular, and the current status of investigations and studies addressing the containment of unit 4 of the Chernobyl reactor station. All papers are indexed separately in report GRS--117. (HP)

  18. Some novel on-power refuelling features of CANDU stations

    International Nuclear Information System (INIS)

    Erwin, D.; Pendlebury, B.; Watson, J.F.; Welch, A.C.

    1976-01-01

    Part A of the paper describes the reasons for, and advantages resulting from, the use of flow assisted refuelling in the CANDU type nuclear reactors at the Pickering Generating Station. A separate fuel handling system is used for each reactor unit, as distinct from the system employed at the Bruce Generating station, where the fuel handling system is shared among several units. Part B of the paper describes some of the advantages of the shared concept with particular emphasis on the availability of the fuel handling system. (author)

  19. Technical evaluation report on the monitoring of electric power to the reactor-protection system for the Pilgrim Nuclear Power Station

    International Nuclear Information System (INIS)

    Selan, J.C.

    1982-01-01

    This report documents the technical evaluation of the monitoring of electric power to the reactor protection system (RPS) at the Pilgrim Nuclear Power Station. The evaluation is to determine if the proposed design modification will protect the RPS from abnormal voltage and frequency conditions which could be supplied from the power supplies and will meet certain requirements set forth by the Nuclear Regulatory Commission. The proposed design modifications will protect the RPS from sustained abnormal voltage and frequency conditions from the supplying sources

  20. Development of an automated system of nuclear materials accounting for nuclear power stations with water-cooled, water-moderated reactors

    International Nuclear Information System (INIS)

    Babaev, N.S.

    1981-06-01

    The results of work carried out under IAEA Contract No. 2336/RB are described (subject: an automated system of nuclear materials accounting for nuclear power stations with water-cooled, water-moderated (VVER) reactors). The basic principles of an accounting system for this type of nuclear power plant are outlined. The general structure and individual units of the information computer program used to achieve automated accounting are described and instructions are given on the use of the program. A detailed example of its application (on a simulated nuclear power plant) is examined

  1. Advanced CANDU reactors

    International Nuclear Information System (INIS)

    Dunn, J.T.; Finlay, R.B.; Olmstead, R.A.

    1988-12-01

    AECL has undertaken the design and development of a series of advanced CANDU reactors in the 700-1150 MW(e) size range. These advanced reactor designs are the product of ongoing generic research and development programs on CANDU technology and design studies for advanced CANDU reactors. The prime objective is to create a series of advanced CANDU reactors which are cost competitive with coal-fired plants in the market for large electricity generating stations. Specific plant designs in the advanced CANDU series will be ready for project commitment in the early 1990s and will be capable of further development to remain competitive well into the next century

  2. UK experience of safety requirements for thermal reactor stations

    International Nuclear Information System (INIS)

    Matthews, R.R.; Dale, G.C.; Tweedy, J.N.

    1977-01-01

    The paper summarises the development of safety requirements since the first of the Generating Boards' Magnox reactors commenced operation in 1962 and includes A.G.R. safety together with the preparation of S.G.H.W.R. design safety criteria. It outlines the basic principles originally adopted and shows how safety assessment is a continuing process throughout the life of a reactor. Some description is given of the continuous effort over the years to obtain increased safety margins for existing and new reactors, taking into account the construction and operating experience, experimental information, and more sophisticated computer-aided design techniques which have become available. The main safeguards against risks arising from the Generating Boards' reactors are the achievement of high standards of design, construction and operation, in conjunction with comprehensive fault analyses to ensure that adequate protective equipment is provided. The most important analyses refer to faults which can lead to excessive fuel element temperatures arising from an increase in power or a reduction in cooling capacity. They include the possibility of unintended control rod withdrawal at power or at start-up, coolant flow failure, pressure circuit failure, loss of boiler feed water, and failure of electric power. The paper reviews the protective equipment, and the policy for reactor safety assessments which include application of maximum credible accident philosophy and later the limited use of reliability and probability methods. Some of the Generating Boards' reactors are now more than half way through their planned working lives and during this time safety protective equipment has occasionally been brought into operation, often for spurious reasons. The general performance, of safety equipment is reviewed particularly for incidents such as main turbo-alternator trip, circulator failure, fuel element failures and other similar events, and some problems which have given rise to

  3. Reactor safety in Eastern Europe. Proceedings

    International Nuclear Information System (INIS)

    1995-02-01

    The papers presented to the GRS colloquium refer to the cooperative activities for reactor accident analysis and modification of the GRS computer codes for their application to reactors of the Russian design types of WWER or RBMK. Another topic is the safety of RBMK reactors in particular, and the current status of investigations and studies addressing the containment of unit 4 of the Chernobyl reactor station. (HP) [de

  4. Radiological survey of the area surrounding the National Reactor Testing Station, Idaho Falls, Idaho. Date of survey: 1 and 2 February 1972

    International Nuclear Information System (INIS)

    1974-01-01

    The Aerial Radiological Measuring System (ARMS) was used to survey the National Reactor Testing Station (NRTS) during February 1972. The purpose of the survey was primarily to identify the presence of Ru-106 and Rh-106 in a release from the Chemical Processing Plant at NRTS. Additionally, the gamma-ray terrestrial exposure rate levels were mapped and the distribution of any man-made isotopes was located and defined

  5. Early Site Permit Demonstration Program: Station design alternatives report

    International Nuclear Information System (INIS)

    1993-03-01

    This report provides the results of investigating the basis for including Station Design Alternatives (SDAs) in the regulatory guidance given for nuclear plant environmental reports (ERs), explains approaches or processes for evaluating SDAs at the early site permit (ESP) stage, and applies one of the processes to each of the ten systems or subsystems considered as SDAS. The key objective o this report s to demonstrate an adequate examination of alternatives can be performed without the extensive development f design data. The report discusses the Composite Suitability Approach and the Established Cutoff Approach in evaluating station design alternatives and selects one of these approaches to evaluate alternatives for each of the plant or station that were considered. Four types of ALWRs have been considered due to the availability of extensive plant data: System 80+, AP600, Advanced Boiling Reactor (ABWR), and Simplified Boiling Water Reactor (SBWR). This report demonstrates the feasibility of evaluating station design alternatives when reactor design detail has not been determined, quantitatively compares the potential ental impacts of alternatives, and focuses the ultimate selection of a alternative on cost and applicant-specific factors. The range of alternatives system is deliberately limited to a reasonable number to demonstrate the or to the three most commonly used at operating plants

  6. Sizewell B Power Station control dosimetry system

    International Nuclear Information System (INIS)

    Renn, G.

    1995-01-01

    Sizewell B Power Station is the first Pressurized Water Reactor (PWR) built in the UK for commercial electricity production. An effective control dosimetry system is a crucial tool, in allowing the station to assess its radiological performance against targets. This paper gives an overview of the control dosimetry system at Sizewell B and describes early operating experience with the system. (UK)

  7. Fire safety in nuclear power stations

    International Nuclear Information System (INIS)

    Kench, R.L.

    1988-01-01

    This is the first of a three-part report on the fire hazards in nuclear power stations and some of the precautions necessary. This part lists the United Kingdom reactors, outlines how they work, the fuels used, the use of moderators and coolants and the control systems. Although the risk of fire is no higher than in fossil-fuel stations the consequences can be more serious. The radioactive materials used mean that there is biological shielding round the core, limitations on waste emissions allowed and limited access to some zones. Reliable shut-down systems are needed. Care in the use of water to fight fires must be exercised -it can act as a moderator and cause an otherwise safe core to go critical. The Wigner effect in graphite moderated reactors is explained. Fires in graphite can be extinguished by carbon dioxide. Argon, chlorine and sodium silicate can also be effective. In sodium cooled reactors fires can be allowed to burn themselves out, or TEC and argon could be used to extinguish the flame. (UK)

  8. The siting of UK nuclear reactors.

    Science.gov (United States)

    Grimston, Malcolm; Nuttall, William J; Vaughan, Geoff

    2014-06-01

    Choosing a suitable site for a nuclear power station requires the consideration and balancing of several factors. Some 'physical' site characteristics, such as the local climate and the potential for seismic activity, will be generic to all reactors designs, while others, such as the availability of cooling water, the area of land required and geological conditions capable of sustaining the weight of the reactor and other buildings will to an extent be dependent on the particular design of reactor chosen (or alternatively the reactor design chosen may to an extent be dependent on the characteristics of an available site). However, one particularly interesting tension is a human and demographic one. On the one hand it is beneficial to place nuclear stations close to centres of population, to reduce transmission losses and other costs (including to the local environment) of transporting electricity over large distances from generator to consumer. On the other it is advantageous to place nuclear stations some distance away from such population centres in order to minimise the potential human consequences of a major release of radioactive materials in the (extremely unlikely) event of a major nuclear accident, not only in terms of direct exposure but also concerning the management of emergency planning, notably evacuation.This paper considers the emergence of policies aimed at managing this tension in the UK. In the first phase of nuclear development (roughly speaking 1945-1965) there was a highly cautious attitude, with installations being placed in remote rural locations with very low population density. The second phase (1965-1985) saw a more relaxed approach, allowing the development of AGR nuclear power stations (which with concrete pressure vessels were regarded as significantly safer) closer to population centres (in 'semi-urban' locations, notably at Hartlepool and Heysham). In the third phase (1985-2005) there was very little new nuclear development, Sizewell

  9. Conceptual design of a moving-ring reactor

    International Nuclear Information System (INIS)

    Smith, A.C.; Carlson, G.A.; Ashworth, C.P.

    1986-01-01

    A design of a prototype moving-ring reactor was completed, and a development plan for a pilot reactor is outlined. The fusion fuel is confined in current-carrying rings of magnetically field-reversed plasma (''compact toroids''). The plasma rings, formed by a coaxial plasma gun, undergo adiabatic magnetic compression to ignition temperature while they are being injected into the reactor's burner section. The cylindrical burner chamber is divided into three ''burn stations.'' Separator coils and a slight axial guide field gradient are used to shuttle the ignited toroids rapidly from one burn station to the next, pausing for one-third of the total burn time at each station. Deuterium-tritium- 3 He ice pellets refuel the rings at a rate that maintains constant radiated power. The fusion power per ring is approx. =105.5 MW. The burn time to reach a fusion energy gain of Q = 30 is 5.9 s

  10. Occupational radiation exposures at Canadian CANDU nuclear power stations

    International Nuclear Information System (INIS)

    LeSurf, J.E.; Taylor, G.F.

    1982-09-01

    In Canada, methods to reduce the radiation exposure to workers at nuclear power reactors have been studied and implemented since the early days of the CANDU reactor program. Close collaboration between the designers, the operators, and the manufacturers has reduced the total exposure at each station, the dose requirement to operate and maintain each successive station compared with earlier stations, and the average annual exposure per worker. Specific methods developed to achieve dose reduction include water chemistry; corrosion resistant materials; low cobalt materials; decontamination; hot filtration, improved equipment reliability, maintainability, and accessibility; improved shielding design and location; planning of work for low exposure; improved operating and maintenance procedures; removal of tritium from D 2 O systems and work environments; improved protective clothing; on-power refuelling; worker awareness and training; and many other small improvements. The 1981 occupational dose productivity factors for Pickering A and Bruce A nuclear generating stations were respectively 0.43 and 0.2 rem/MW(e).a

  11. Operation of the UK Magnox Stations in a competitive market

    International Nuclear Information System (INIS)

    Corrigan, A.

    2000-01-01

    In 1955 the UK Government announced the first major civil nuclear power plant construction programme based on the Magnox design of reactor. This was followed in 1956 with the commencement of operation of Calder Hall, the world's first nuclear power station. The initial programme was for the construction of 1 500-2 000 MW of plant but, with the success of the early stations, this was increased to 5 000 MW by 1960. In total 11 Magnox nuclear power stations were commissioned in the UK over the period 1956 to 1971, comprising a total of 26 reactors (see Table 1). At present 20 of the reactors remain in operation, with an average life of 37 years. Output from the stations has been steady for many years and they have been regarded as the workhorses of the electricity generation industry in the UK. In 1990 the electricity supply and distribution system was deregulated and a market system introduced which has led to a reduction in the sale price of electricity. In addition to this it has been necessary to invest in the plants to maintain safety levels and operational reliability. The plant's can only continue in operation provided they remain safe and economic. This paper will review recent experience with the life management of the Magnox stations. (author)

  12. A STRONGLY COUPLED REACTOR CORE ISOLATION COOLING SYSTEM MODEL FOR EXTENDED STATION BLACK-OUT ANALYSES

    Energy Technology Data Exchange (ETDEWEB)

    Zhao, Haihua [Idaho National Laboratory; Zhang, Hongbin [Idaho National Laboratory; Zou, Ling [Idaho National Laboratory; Martineau, Richard Charles [Idaho National Laboratory

    2015-03-01

    The reactor core isolation cooling (RCIC) system in a boiling water reactor (BWR) provides makeup cooling water to the reactor pressure vessel (RPV) when the main steam lines are isolated and the normal supply of water to the reactor vessel is lost. The RCIC system operates independently of AC power, service air, or external cooling water systems. The only required external energy source is from the battery to maintain the logic circuits to control the opening and/or closure of valves in the RCIC systems in order to control the RPV water level by shutting down the RCIC pump to avoid overfilling the RPV and flooding the steam line to the RCIC turbine. It is generally considered in almost all the existing station black-out accidents (SBO) analyses that loss of the DC power would result in overfilling the steam line and allowing liquid water to flow into the RCIC turbine, where it is assumed that the turbine would then be disabled. This behavior, however, was not observed in the Fukushima Daiichi accidents, where the Unit 2 RCIC functioned without DC power for nearly three days. Therefore, more detailed mechanistic models for RCIC system components are needed to understand the extended SBO for BWRs. As part of the effort to develop the next generation reactor system safety analysis code RELAP-7, we have developed a strongly coupled RCIC system model, which consists of a turbine model, a pump model, a check valve model, a wet well model, and their coupling models. Unlike the traditional SBO simulations where mass flow rates are typically given in the input file through time dependent functions, the real mass flow rates through the turbine and the pump loops in our model are dynamically calculated according to conservation laws and turbine/pump operation curves. A simplified SBO demonstration RELAP-7 model with this RCIC model has been successfully developed. The demonstration model includes the major components for the primary system of a BWR, as well as the safety

  13. Valve maintainability in CANDU-PHW nuclear generating stations

    International Nuclear Information System (INIS)

    Pothier, N.E.; Crago, W.A.

    1977-09-01

    Design, application, layout and administrative factors which affect valve maintainability in CANDU-PHW power reactors are identified and discussed. Some of these are illustrated by examples based on prototype reactor operation experience. Valve maintainability improvements resulting from laboratory development and maintainability analysis, have been incorporated in commercial CANDU-PHW nuclear generating stations. These, also, are discussed and illustrated. (author)

  14. Bradwell Nuclear Power Station

    International Nuclear Information System (INIS)

    1987-01-01

    When built, the Magnox reactors were expected to have operating lifetimes of 20-25 years. In order to satisfy the licensing authorities of their continued safety, long term safety reviews (LTSRs) are being carried out as the reactors reach 20 years of operation. This is the Nuclear Installations Inspectorate's (NII) summary report on Bradwell nuclear power station. The objectives of the LTSR are stated. A description of the plant is followed by an explanation of the statutory position on licensing. The responsibilities of the Central Electricity Generating Board (CEGB) and the NII are defined. From the examination of the CEGB's LTSR it is concluded that this generally confirms the validity of the existing safety case for present operation. However, some recommendations are made as to work required for reactor operation up to 1992. A summary of the NII findings is presented. This includes the reactor pressure circuit integrity, effects of ageing and in-service wear and radiation doses. (U.K.)

  15. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The Shippingport Atomic Power Station was located on the Ohio River in Shippingport Borough (Beaver County), Pennsylvania, USA. The US Atomic Energy Commission (AEC) constructed the plant in the mid-1950s on a seven and half acre parcel of land leased from Duquesne Light Company (DLC). The purposes were to demonstrate and to develop Pressurized Water Recovery technology and to generate electricity. DLC operated the Shippingport plant under supervision of (the successor to AEC) the Department of Energy (DOE)-Naval Reactors (NR) until operations were terminated on October 1, 1982. NR concluded end-of-life testing and defueling in 1984 and transferred the Station's responsibility to DOE Richland Operations Office (RL), Surplus Facility Management Program Office (SFMPO5) on September 5, 1984. SFMPO subsequently established the Shippingport Station Decommissioning Project and selected General Electric (GE) as the Decommissioning Operations Contractor. This report is intended to provide an overview of the Shippingport Station Decommissioning Project

  16. Lunar base thermoelectric power station study

    Science.gov (United States)

    Determan, William; Frye, Patrick; Mondt, Jack; Fleurial, Jean-Pierre; Johnson, Ken; Stapfer, G.; Brooks, Michael D.; Heshmatpour, Ben

    2006-01-01

    Under NASA's Project Prometheus, the Nuclear Systems Program, the Jet Propulsion Laboratory, Pratt & Whitney Rocketdyne, and Teledyne Energy Systems have teamed with a number of universities, under the Segmented Thermoelectric Multicouple Converter (STMC) program, to develop the next generation of advanced thermoelectric converters for space reactor power systems. Work on the STMC converter assembly has progressed to the point where the lower temperature stage of the segmented multicouple converter assembly is ready for laboratory testing and the upper stage materials have been identified and their properties are being characterized. One aspect of the program involves mission application studies to help define the potential benefits from the use of these STMC technologies for designated NASA missions such as the lunar base power station where kilowatts of power are required to maintain a permanent manned presence on the surface of the moon. A modular 50 kWe thermoelectric power station concept was developed to address a specific set of requirements developed for this mission. Previous lunar lander concepts had proposed the use of lunar regolith as in-situ radiation shielding material for a reactor power station with a one kilometer exclusion zone radius to minimize astronaut radiation dose rate levels. In the present concept, we will examine the benefits and requirements for a hermetically-sealed reactor thermoelectric power station module suspended within a man-made lunar surface cavity. The concept appears to maximize the shielding capabilities of the lunar regolith while minimizing its handling requirements. Both thermal and nuclear radiation levels from operation of the station, at its 100-m exclusion zone radius, were evaluated and found to be acceptable. Site preparation activities are reviewed and well as transport issues for this concept. The goal of the study was to review the entire life cycle of the unit to assess its technical problems and technology

  17. Performance assessment of Point Lepreau Generating Station

    International Nuclear Information System (INIS)

    Alikhan, S.

    1991-01-01

    The Point Lepreau Generating Station, a 680 MWe CANDU unit, is located about 40 km southwest of the city of Saint John, New Brunswick, Canada. It was declared in-service on 1 February, 1983 and, since then, has demonstrated an average cross capacity factor of over 93% up to the end of 1990. This paper compared the performance of the station with other sister CANDU units and the Light Water Reactors world-wide using the following ten performance indicators, as applicable: - gross capacity factor; - fuel burn-up; - heavy water upkeep; - unplanned reactor trips while critical; - forced outage rate; - fuel handling performance; - derived emission of radioactive effluents to environment; - personnel radiation dose; - industrial safety; - low-level solid radioactive wastes. The paper examines various areas of station activities including management and organization, operations and maintenance, technical support, fuel handling and health physics in order to highlight some of the 'good practices' which are believed to have made a significant contribution towards achieving the demonstrated performance of Point Lepreau G.S. In addition, several areas of potential improvement are discussed in order to maintain and enhance, where practicable, the safety, reliability and economic performance of the station. In this context, a careful review of the operating experiences, both in-house and at other stations, and a judicious application of lessons learned plays a significant role. (author)

  18. Performance assessment of Point Lepreau Generating Station

    Energy Technology Data Exchange (ETDEWEB)

    Alikhan, S [Point Lepreau Generating Station, Lepreau, NB (Canada)

    1991-04-01

    The Point Lepreau Generating Station, a 680 MWe CANDU unit, is located about 40 km southwest of the city of Saint John, New Brunswick, Canada. It was declared in-service on 1 February, 1983 and, since then, has demonstrated an average cross capacity factor of over 93% up to the end of 1990. This paper compared the performance of the station with other sister CANDU units and the Light Water Reactors world-wide using the following ten performance indicators, as applicable: - gross capacity factor; - fuel burn-up; - heavy water upkeep; - unplanned reactor trips while critical; - forced outage rate; - fuel handling performance; - derived emission of radioactive effluents to environment; - personnel radiation dose; - industrial safety; - low-level solid radioactive wastes. The paper examines various areas of station activities including management and organization, operations and maintenance, technical support, fuel handling and health physics in order to highlight some of the 'good practices' which are believed to have made a significant contribution towards achieving the demonstrated performance of Point Lepreau G.S. In addition, several areas of potential improvement are discussed in order to maintain and enhance, where practicable, the safety, reliability and economic performance of the station. In this context, a careful review of the operating experiences, both in-house and at other stations, and a judicious application of lessons learned plays a significant role. (author)

  19. Station black out concurrent with PORV failure using a Generic Pressurized Water Reactor simulator

    International Nuclear Information System (INIS)

    Zubair, Muhammad; Ababneh, Ahmad; Ishag, Ahmed

    2017-01-01

    Highlights: •SBO accident simulation by using a GPWR simulator. •Normal SBO, and SBO with additional failure of Pilot Operated Relief Valve. •The research results will provide help in future for better understanding of accidents in APR 1400 reactors. -- Abstract: Station Black Out (SBO) is an accident situation that refers to the total loss of offsite power, along with the unavailability of onsite power, which results from the failure of all Diesel Generators (DG). Probabilistic Safety Assessment (PSA) spans a number of methods that include modeling of event-trees and simulation of accidents scenarios, aimed to quantify risk and ensure safety in nuclear power plants. PSA also deals with prediction of future accidents and calculation of failure probabilities that has been done in this study. A SBO accident was simulated using a Generic Pressurized Water Reactor (GPWR) simulator from KEYMASTER™. The accident scenario consists of two stages; the first stage belongs to normal SBO, in second stage SBO accident with additional failure of Pilot Operated Relief Valve (PORV) opens and it stuck open has been considered for the pressurizer. A comparison of the two stages was made by plotting variables on the same graph. The research has been carried out to analyze the hot and cold leg temperatures, Steam Generator (SG) pressure, SG Narrow Range (NR) level, SG water-level-percentage (PCT), Pressurizer pressure, Fuel Temperature, and containment pressure. Simulation results suggest that failure in closing PORV has negligible impact on hot and cold leg temperatures, results in an overall less pressure in SGs, but higher pressure in the pressurizer. Additionally, containment pressure did not exceed the maximum approved pressure of 8.7 kg/cm 2 , but was approaching the Advanced Pressurized Water Reactor’s (APR-1400) design pressure of 4.218 kg/cm 2 . Finally, nuclear fuel temperature exceeded Probabilistic Risk Assessment (PRA) limit of 726.7 °C for both scenarios. The

  20. Energy analysis of nuclear power stations

    International Nuclear Information System (INIS)

    Lindhout, A.H.

    1975-01-01

    A study based on a 1000MWe light water reactor power station was carried out to determine the total energy input and output of the power station. The calculations took into account the mining and processing of the ore, enrichment of the uranium, treatment of used nuclear fuel, investment in land, buildings, machinery, and transport. 144 tons of natural uranium produce 6100 million kWh (electric) and 340 million kWh (thermal) per annum. (J.S.)

  1. Underground nuclear power station using self-regulating heat-pipe controlled reactors

    International Nuclear Information System (INIS)

    Hampel, V.E.

    1989-01-01

    The author presents a nuclear reactor for generating electricity disposed underground at the bottom of a vertical hole that can be drilled using conventional drilling technology. The primary coolant of the reactor core is the working fluid in a plurality of thermodynamically coupled heat pipes emplaced in the hole between the heat source at the bottom of the hole and heat exchange means near the surface of the earth. Additionally, the primary coolant (consisting of the working fluid in the heat pipes in the reactor core) moderates neutrons and regulates their reactivity, thus keeping the power of the reactor substantially constant. At the end of its useful life, the reactor core may be abandoned in place. Isolation from the atmosphere in case of accident or for abandonment is provided by the operation of explosive closures and mechanical valves emplaced along the hole. This invention combines technology developed and tested for small, highly efficient, space-based nuclear electric power plants with the technology of fast-acting closure mechanisms developed and used for underground testing of nuclear weapons. This invention provides a nuclear power installation which is safe from the worst conceivable reactor accident, namely, the explosion of a nuclear weapon near the ground surface of a nuclear power reactor

  2. Underground nuclear power station using self-regulating heat-pipe controlled reactors

    Science.gov (United States)

    Hampel, Viktor E.

    1989-01-01

    A nuclear reactor for generating electricity is disposed underground at the bottom of a vertical hole that can be drilled using conventional drilling technology. The primary coolant of the reactor core is the working fluid in a plurality of thermodynamically coupled heat pipes emplaced in the hole between the heat source at the bottom of the hole and heat exchange means near the surface of the earth. Additionally, the primary coolant (consisting of the working flud in the heat pipes in the reactor core) moderates neutrons and regulates their reactivity, thus keeping the power of the reactor substantially constant. At the end of its useful life, the reactor core may be abandoned in place. Isolation from the atmosphere in case of accident or for abandonment is provided by the operation of explosive closures and mechanical valves emplaced along the hole. This invention combines technology developed and tested for small, highly efficient, space-based nuclear electric power plants with the technology of fast-acting closure mechanisms developed and used for underground testing of nuclear weapons. This invention provides a nuclear power installation which is safe from the worst conceivable reactor accident, namely, the explosion of a nuclear weapon near the ground surface of a nuclear power reactor.

  3. Shippingport Station Decommissioning Project (SSDP). A progress report

    International Nuclear Information System (INIS)

    Mullee, G.R.; Usher, J.M.

    1986-01-01

    The Shippingport Atomic Power Station was shutdown in October, 1982 by the Plant Operator, Duquesne Light Company, for decommissioning by the US Department of Energy. The planning for decommissioning was completed in September, 1983. In September, 1984 operational responsibility for the station was transferred to the DOE's Decommissioning Operations Contractor - the General Electric Company (assisted by an integrated subcontractor, MK Ferguson Company). Significant accomplishments to date include the completion of all prerequisites for decommissioning, the removal of asbestos from plant systems, loading of irradiated reactor components into the reactor vessel for shipment, the commencement of electrical deactivations and the commencement of piping/component removal. Decontamination and waste processing are progressing in support of the project schedule. The reactor vessel will be shipped as one piece on a barge for burial at Hanford, Washington. The final release of the site is scheduled for April, 1990. A technology transfer program is being utilized to disseminate information about the project

  4. Valves and fittings for nuclear power stations

    International Nuclear Information System (INIS)

    1976-01-01

    The standard specifies technical requirements for valves and pipe fittings in nuclear power stations with PWR type reactors. Details of appropriate materials, welding, surface treatment for corrosion protection, painting, and complementary supply are given

  5. Siting technology of underground nuclear power station

    International Nuclear Information System (INIS)

    Motojima, M.; Hibino, S.

    1989-01-01

    For the site of a nuclear power station, it may be possible to select a seaside mountain area, if the condition is suitable to excavate large rock caverns in which a reactor and other equipments are installed. As the case study on the siting technology for an underground nuclear power station, the following example was investigated. The site is a seaside steep mountain area, and almost all the equipments are installed in plural tunnel type caverns. The depth from the ground surface to the top of the reactor cavern is about 150 m, and the thickness of the rock pillar between the reactor cavern of 33 m W x 82 mH x 79 mD and the neighboring turbine cavern is 60 m. In this paper, the stability of rock caverns in this example, evaluated by numerical analysis, is described. The numerical analysis was carried out on the central cross section of the reactor cavern, taking the turbine cavern, geostress, the mechanical properties of rock mass and the process of excavation works in consideration. By the analysis, the underground caverns in this example were evaluated as stable, if the rock quality is equivalent to C H class or better according to the CRIEPI rock classification. (K.I.)

  6. Integrity of Magnox reactor steel pressure vessels

    International Nuclear Information System (INIS)

    Flewitt, P.E.J.; Williams, G.H.; Wright, M.B.

    1992-01-01

    The background to the safety assessment of the steel reactor pressure vessels for Magnox power stations is reviewed. The evolved philosophy adopted for the 1991 safety cases prepared for the continued operation of four Magnox power stations operated by Nuclear Electric plc is described, together with different aspects of the multi-legged integrity argument. The main revisions to the materials mechanical property data are addressed together with the assessment methodology adopted and their implications for the overall integrity argument formulated for the continued safe operation of these reactor pressure vessels. (author)

  7. Power station impacts: socio-economic impact assessment

    International Nuclear Information System (INIS)

    Glasson, John; Elson, Martin; Barrett, Brendan; Wee, D. Van der

    1987-01-01

    The aim of this study is to assess the local social and economic impacts of a proposed nuclear power station development at Hinkley Point in Somerset. The proposed development, Hinkley Point C, would be an addition to the existing Hinkley Point A Magnox station, commissioned in 1965, and the Hinkley Point B Advanced Gas Cooled Reactor (AGR) station, commissioned in 1976. It is hoped that the study will be of assistance to the CEGB, the Somerset County and District Councils and other agencies in their studies of the proposed development. In addition, the study seeks to apply and further develop the methodology and results from previous studies by the Power Station Impacts (PSI) team for predicting the social and economic effects of proposed power station developments on their localities. (author)

  8. Shippingport station decommissioning project irradiated components transfer: Topical report

    International Nuclear Information System (INIS)

    1988-01-01

    This topical report is a synopsis of the transfer of irradiated components into the Shippingport Reactor Pressure Vessel (RPV) performed at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities for the decommissioning of a nuclear power reactor to be removed in one piece

  9. SILOETTE, a training centre for reactor physics at the Nuclear Research Centre of Grenoble

    International Nuclear Information System (INIS)

    Destot, M.

    1983-10-01

    The Reactor Department of Grenoble has created, based on Siloette, an activity of training in reactor physics, wich is running since 1975 to meet the important needs generated by the development of electronuclear power stations. Its essential goal is to provide an initiation to the basic physical phenomena which determine the operation of the reactors. For that purpose, a rather comprehensive program of practical works on reactor (SILOETTE) and on nuclear power station simulators (PWR, UNGG) is proposed besides lectures and conferences, general and specialized teaching on the reactor operation principle, kinetics, dynamics and thermics

  10. Point Lepreau generating station

    International Nuclear Information System (INIS)

    Ganong, G.H.D.; Strang, A.E.; Gunter, G.E.; Thompson, T.S.

    Point Lepreau-1 reactor is a 600 MWe generating station expected to be in service by October 1979. New Brunswick is suffering a 'catch up' phenomenon in load growth and needs to decrease dependence on foreign oil. The site is on salt water and extensive study has gone into corrosion control. Project management, financing and scheduling have unique aspects. (E.C.B.)

  11. Training and teaching with SILOETTE reactor and associated simulators at the Nuclear Research Centre of Grenoble

    International Nuclear Information System (INIS)

    Destot, M.

    1983-10-01

    Thanks to its three reactors SILOE (35 MW), MELUSINE (8 MW) and SILOETTE (100 KW), the Reactor Department of the Nuclear Research Centre of Grenoble has gained a considerable experience in the operation and utilization of research and material testing reactors. Inside of this general framework, the Reactor Department of Grenoble has built up a training and teaching centre that has been permanently active since 1975, with the aim of satisfying the considerable needs arising from the development of electro-nuclear power stations. The course is mainly intended for engineers and technicians who will be responsible for running power stations. A thorough series of practical exercices, carried out in the SILOETTE training reactor and in a PWR or in a Gas Cooled Reactor Simulator, desmonstrates the application of the theorical courses and familiarises the trainees with the behaviour of reactors and power stations

  12. Reactor handbook. 2. rev. ed.

    International Nuclear Information System (INIS)

    Lederer, B.J.; Wildberg, D.W.

    1992-01-01

    On the basis of the guidelines on expert knowledge, the book discusses the subjects of atomic physics, heat transfer, nuclear power plants, reactor materials, radiation protection, reactor safety, reactor instrumentation, and reactor operation, with special regard to nuclear power plants with LWR-type reactors. The book is intended for shift personnel, especially gang bosses, reactor operators, and control station operators: for this reason a practical and rather popular style has been chosen. However, the book will also be a manual for other operating personnel, personnel of producer companies, expert organisations, authorities, and students. It can be used as a textbook for staff training, a manual for the practice, and as accompanying book for teaching at nuclear engineering schools. (orig.) With 173 figs [de

  13. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 1. Main report. Technical report, September 1977-October 1979

    International Nuclear Information System (INIS)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE

  14. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 1. Main report. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE.

  15. Conceptual design of a moving-ring reactor

    International Nuclear Information System (INIS)

    Smith, A.C. Jr.; Ashworth, C.P.; Abreu, K.E.

    1983-01-01

    A design of a prototype Moving-Ring Reactor has been completed. The fusion fuel is confined in current-carrying rings of magnetically field-reversed plasma (''compact toroids''). The plasma rings, formed by a coaxial plasma gun, undergo adiabatic magnetic compression to ignition temperature while they are being injected into the reactor's burner section. The cylindrical burner chamber is divided into three ''burn stations''. Separator coils and a slight axial guide-field gradient are used to shuttle the ignited toroids rapidly from one burn station to the next, pausing for one third of the total burn time at each station. D-T- 3 He ice pellets refuel the rings at a rate which maintains constant radiated power. The first wall and tritium breeding blanket designs make credible use of helium cooling, SiC and Li 2 O to minimize structural radioactivity. ''Hands-on'' maintenance is possible on all reactor components outside the blanket. The first wall and blanket are designed to shut the reactor down passively in the event of a loss-of-coolant or loss-of-flow accident. Helium removes heat from the first wall, blanket and shield, and is used in a closed-cycle gas turbine to produce electricity. Energy residing in the plasma ring at the end of the burn is recovered via magnetic expansion. Electrostatic direct conversion is not used in this design. The reactor produces a constant net power of 99 MW(e). (author)

  16. Station blackout at nuclear power plants: Radiological implications for nuclear war

    International Nuclear Information System (INIS)

    Shapiro, C.S.

    1986-12-01

    Recent work on station blackout is reviewed its radiological implications for a nuclear war scenario is explored. The major conclusion is that the effects of radiation from many nuclear weapon detonations in a nuclear war would swamp those from possible reactor accidents that result from station blackout

  17. Technological status of reactor coolant pumps in generation III+ pressurized nuclear reactors

    Energy Technology Data Exchange (ETDEWEB)

    Brecht, Bernhard; Bross, Stephan [KSB Aktiengesellschaft, Frankenthal (Germany)

    2016-05-15

    KSB has been developing and producing pumps for thermal power plants for nearly 90 years. Consequently, KSB also started to develop and manufacture pumps for all kinds of nuclear power plants from the very beginning of the civil use of nuclear energy. This is especially true for reactor coolant pumps for pressurized water reactors. For the generation of advanced evolutionary reactors (Generation III+ reactors), KSB developed an advanced shaft seal system which is also able to fulfill the requirements of station blackout conditions. The tests in the KSB test rigs, which were successfully completed in December 2015, proved the full functionality of the new design. For generation III+ passive plant reactors KSB developed a new reactor coolant pump type called RUV, which is based on the experience of classic reactor coolant pumps and reactor internal pumps. It is a very compact, hermetically sealed vertical pump-motor unit with a wet winding motor. A full scale prototype successfully passed the 1st stage qualification test program in October 2015.

  18. The fast breeder reactor

    International Nuclear Information System (INIS)

    Davis, D.A.; Baker, M.A.W.; Hall, R.S.

    1990-01-01

    Following submission of written evidence, the Energy Committee members asked questions of three witnesses from the Central Electricity Generating Board and Nuclear Electric (which will be the government owned company running nuclear power stations after privatisation). Both questions and answers are reported verbatim. The points raised include where the responsibility for the future fast reactor programme should lie, with government only or with private enterprise or both and the viability of fast breeder reactors in the future. The case for the fast reactor was stated as essentially strategic not economic. This raised the issue of nuclear cost which has both a construction and a decommissioning element. There was considerable discussion as to the cost of building a European Fast reactor and the cost of the electricity it would generate compared with PWR type reactors. The likely demand for fast reactors will not arrive for 20-30 years and the need to build a fast reactor now is questioned. (UK)

  19. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 2. Appendices. Technical report, September 1977-October 1979

    International Nuclear Information System (INIS)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE. This volume contains the appendices

  20. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 2. Appendices. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE. This volume contains the appendices.

  1. Socio-economic impacts of nuclear generating stations: Diablo Canyon case study

    International Nuclear Information System (INIS)

    Pijawka, K.D.; Yaquinto, G.

    1982-07-01

    This report documents a case study of the socioeconomic impacts of the construction and operation of the Diablo Canyon nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  2. Economical dismantling of nuclear power stations

    International Nuclear Information System (INIS)

    Mallok, J.; Andermann, H.

    1999-01-01

    The dismantling of nuclear power stations requires a high degree of security and economic efficiency due to the strong contamination of components and the close spatial conditions. In order to protect involved staff from radiation, modern remote-controlled technology is applied in sectors with heavy radioactive contamination such as reactor pressure vessels. The article shows, that the dismantling of reactor pressure vessels using a remote-controlled milling machine developed by the Siemens subsidiary Mechanik Center Erlangen GmbH, can be done in a secure and efficient way. (orig.) [de

  3. Anticorrosional protection in nuclear power station objects

    International Nuclear Information System (INIS)

    Czarnocki, A.; Kwiatkowski, A.

    1976-01-01

    The distribution and qualities of chemical protection and demands concerning preparation of the bottom for protecting coats in nuclear power station objects are discussed. The solutions of protections applied abroad and in the objects of ''MARIA'' reactor are presented. (author)

  4. Socio-economic impacts of nuclear generating stations: Oconee case study

    International Nuclear Information System (INIS)

    Flynn, J.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Oconee nuclear power stations. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  5. Socio-economic impacts of nuclear generating stations: Surry case study

    International Nuclear Information System (INIS)

    Flynn, J.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Surry nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  6. The utility of different reactor types for the research

    International Nuclear Information System (INIS)

    Stiennon, G.

    1983-01-01

    The report presents a general view of the use of the different belgian research reactor i.e. venus reactor, BR-1 reactor, BR-2 reactor and BR-3 reactor. Particular attention is given to the programmes which is in the interest of international collaboration. In order to reach an efficient utilization of such reactors they require a specialized personnel groups to deal with the irradiation devices and radioactive materials and post irradiation examinations, creating a complete material testing station. (A.J.)

  7. Contamination awareness at the Dresden Nuclear Power Station

    International Nuclear Information System (INIS)

    Pagel, D.J.; Rath, W.C.

    1986-01-01

    Dresden Nuclear Power Station, which is located ∼ 60 miles southwest of Chicago near Morris, Illinois, has been generating electricity since 1960. Owned by Commonwealth Edison, Dresden was the nation's first privately financed nuclear station. On its site are three boiling water reactors (BWRs). Due to the contamination potential inherent with a reactor, a contamination trending program was created at the station. Studies had indicated a rise in contamination events during refueling outages. Further increases were due to specific work projects such as hydrolyzing operations. The investigations suggested that contract personnel also increased the number of events. In 1983, a contamination awareness program was created. The 1984 contamination awareness program was comprised of the following: (1) a statistical review in which trended contamination events were discussed. (2) A demonstration of protective clothing removal by an individual making various mistakes. (3) Scenarios were developed for use in mock work areas. (4) Upper management involvement. Because of the 1984 program, favorable attention has been focused on Dresden from the US Nuclear Regulatory Commission and the Institute of Nuclear Power Operations

  8. Petri nets and fault diagnosis in nuclear reactors

    International Nuclear Information System (INIS)

    Jalel, N.A.; Nicholson, H.

    1990-11-01

    The possibility of applying Petri nets (Pns) as a modelling tool to represent any fault or accident that might occur in the Loss Of Fluid Test (LOFT) reactor, small scale pressurised water reactor, is discussed and analysed. Pns are developed to assist the nuclear reactor operator in identifying any fault or alarm that might arise in the power station. (author)

  9. An underground nuclear power station using self-regulating heat-pipe controlled reactors

    Science.gov (United States)

    Hampel, V.E.

    1988-05-17

    A nuclear reactor for generating electricity is disposed underground at the bottom of a vertical hole that can be drilled using conventional drilling technology. The primary coolant of the reactor core is the working fluid in a plurality of thermodynamically coupled heat pipes emplaced in the hole between the heat source at the bottom of the hole and heat exchange means near the surface of the earth. Additionally, the primary coolant (consisting of the working fluid in the heat pipes in the reactor core) moderates neutrons and regulates their reactivity, thus keeping the power of the reactor substantially constant. At the end of its useful life, the reactor core may be abandoned in place. Isolation from the atmosphere in case of accident or for abandonment is provided by the operation of explosive closures and mechanical valves emplaced along the hole. This invention combines technology developed and tested for small, highly efficient, space-based nuclear electric power plants with the technology of fast- acting closure mechanisms developed and used for underground testing of nuclear weapons. This invention provides a nuclear power installation which is safe from the worst conceivable reactor accident, namely, the explosion of a nuclear weapon near the ground surface of a nuclear power reactor. 5 figs.

  10. Algological studies on the site of the Fessenheim nuclear power station

    International Nuclear Information System (INIS)

    Pierre, J.F.

    1980-01-01

    Systematic study of the algal flora at five stations situated on both sides of the nuclear power station at Fessenheim (department of Haut-Rhin, France). The analysis of the diatomaceae populations in 1977 and 1978, i.e. before and after the start of the reactors, does not indicate, in the composition and abundance of algae, any modifications susceptible to be directly connected to the implantation of the nuclear power station [fr

  11. Safety aspects of nuclear power stations

    International Nuclear Information System (INIS)

    Binner, W.

    1980-01-01

    Psychological aspects of the fear of nuclear power are discussed, cancer deaths due to a nuclear accident are predicted and the need for nuclear accident prevention is stressed. A simplified analysis of the safety precautions in a generalised nuclear power station is offered, with reference to loss-of-coolant incidents, and developments in reactor design for fail-safe modes are explained. The importance of learning from the Three Mile Island incident is noted and failure statistics are presented. Tasks to be undertaken at the Austrian Zwentendorf nuclear power station are listed, including improved quality control and acoustic detectors. Precautions against earthquakes are also discussed and it is stated that safe operation of the Zwentendorf station will be achieved. (G.M.E.)

  12. Medium-size high-temperature gas-cooled reactor

    International Nuclear Information System (INIS)

    Peinado, C.O.; Koutz, S.L.

    1980-08-01

    This report summarizes high-temperature gas-cooled reactor (HTGR) experience for the 40-MW(e) Peach Bottom Nuclear Generating Station of Philadelphia Electric Company and the 330-MW(e) Fort St. Vrain Nuclear Generating Station of the Public Service Company of Colorado. Both reactors are graphite moderated and helium cooled, operating at approx. 760 0 C (1400 0 F) and using the uranium/thorium fuel cycle. The plants have demonstrated the inherent safety characteristics, the low activation of components, and the high efficiency associated with the HTGR concept. This experience has been translated into the conceptual design of a medium-sized 1170-MW(t) HTGR for generation of 450 MW of electric power. The concept incorporates inherent HTGR safety characteristics [a multiply redundant prestressed concrete reactor vessel (PCRV), a graphite core, and an inert single-phase coolant] and engineered safety features

  13. Reactor types for the future

    International Nuclear Information System (INIS)

    Hall, A.C.

    1990-01-01

    The factors impacting a utility's choice of reactor for commercial exploitation are discussed. Concepts available in time frames of 5, 10 and 20 years are considered. It is concluded that future programmes are likely to be based on a relatively small number of largely pre-licensed turnkey station designs. The near future is likely to be dominated by light water reactors. The Westinghouse AP600 design is briefly described. (author)

  14. Reactor types for the future

    Energy Technology Data Exchange (ETDEWEB)

    Hall, A C [PWR Power Projects Ltd., Knutsford, Cheshire (United Kingdom)

    1990-06-01

    The factors impacting a utility's choice of reactor for commercial exploitation are discussed. Concepts available in time frames of 5, 10 and 20 years are considered. It is concluded that future programmes are likely to be based on a relatively small number of largely pre-licensed turnkey station designs. The near future is likely to be dominated by light water reactors. The Westinghouse AP600 design is briefly described. (author)

  15. MRP-227 Reactor vessel internals inspection planning and initial results at the Oconee nuclear station unit 2

    International Nuclear Information System (INIS)

    Davidsaver, S.B.; Fyfitch, S.; Whitaker, D.E.; Doss, R.L.

    2015-01-01

    The U.S. PWR industry has pro-actively developed generic inspection requirements and standards for reactor vessel (RV) internals. The Electric Power Research Institute (EPRI) Pressurized Water Reactor (PWR) Materials Reliability Program (MRP) has issued MRP-227-A and MRP-228 with mandatory and needed requirements based on the Nuclear Energy Institute (NEI) document NEI 03-08. The inspection and evaluation guidelines contained in MRP-227-A consider eight age-related degradation mechanisms: stress corrosion cracking (SCC), irradiation-assisted stress corrosion cracking (IASCC), wear, fatigue, thermal aging embrittlement, irradiation embrittlement, void swelling and irradiation growth, and thermal and irradiation-enhanced stress relaxation or irradiation-enhanced creep. This paper will discuss the decision planning efforts required for implementing the MRP-227-A and MRP-228 requirements and the results of these initial inspections at the Oconee Nuclear power station (ONS) units. Duke Energy and AREVA overcame a significant technology and NDE challenge by successfully completing the first-of-a-kind MRP-227-A scope requirements at ONS-1 in one outage below the estimated dose and with zero safety issues or events. This performance was repeated at ONS-2 a year later. The remote NDE tooling and processes developed to examine the MRP-227-A scope for ONS-1 and ONS-2 are transferable to other PWRs

  16. Implementation of multiple measures to improve reactor recirculation pump sealing performance in nuclear boiling water reactor service

    Energy Technology Data Exchange (ETDEWEB)

    Loenhout, Gerard van [Flowserve B.V., Etten-Leur (Netherlands). Nuclear Services and Solutions Engineering; Hurni, Juerg

    2015-05-15

    A modern reactor recirculation pump circulates a large volume of high temperature, very pure water from the reactor pressure vessel back to the core by feeding into multiple stationary jet pumps inside the vessel. Together with the jet pumps, they allow station operators to vary coolant flow and variable pump speed provides the best and most stable reactor power control. A crucial technical problem with a recirculation pump, such as a mechanical seal indicating loss of sealing pressure, may result in a power station having to shut down for repair. This article describes the sudden increase in stray current phenomenon leading to rapid and severe deterioration of the mechanical end face shaft seal in a reactor recirculation pump. This occurred after the installation of a variable frequency converter replacing the original motor-generator set. This article will also discuss the 2,500 hour laboratory test results conducted under reactor recirculation pump sealing conditions using a newly developed seal face technology recently implemented to overcome challenges when sealing neutral, ultra-pure water. In addition, the article will describe the elaborate shaft grounding arrangement and the preliminary measurement results achieved in order to eliminate potential damages to both pump and mechanical seal.

  17. Nuclear generating station and heavy water plant cost estimates for strategy studies

    International Nuclear Information System (INIS)

    Archinoff, G.H.

    1979-07-01

    Nuclear generating station capital, operating and maintenance costs are basic input data for strategy analyses of alternate nuclear fuel cycles. This report presents estimates of these costs for natural uranium CANDU stations, CANDU stations operating on advanced fuel cycles, and liquid metal fast breeder reactors. Cost estimates for heavy water plants are also presented. The results show that station capital costs for advanced fuel cycles are not expected to be significantly greater than those for natural uranium stations. LMFBR capital costs are expected to be 25-30 percent greater than for CANDU's. (auth)

  18. Research to sustain cases for Magnox-reactor steel pressure vessels

    International Nuclear Information System (INIS)

    Graham, W.J.

    1997-01-01

    Britain's Magnox Electric plc owns and operates six power stations, each of which has twin gas-cooled reactors of the Magnox-fuel type. The older group of four power stations has steel pressure-circuits. The reactor cores are housed within spherical, steel vessels. This article describes some of the research which is undertaken to sustain the safety cases for these steel vessels which have now been in operation for just over 30 years. (author) 2 figs., 4 refs

  19. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    Pasquini, L.A.

    1986-01-01

    The purpose of the Shippingport Station Decommissioning Project (SSDP) is to place the Shippingport Atomic Power Station in a long-term radiologically safe condition following defueling of the reactor, to perform decommissioning in such a manner as to demonstrate to the nuclear industry the application of decommissioning procedures to a large scale nuclear power plant, and to provide useful planning data for future decommissioning projects. This paper describes the Technology Transfer Program for collecting and archiving the decommissioning data base and its availability to the nuclear industry

  20. Ten-yearly report on operations at the Garigliano nuclear power station

    International Nuclear Information System (INIS)

    1977-01-01

    This document is the final report on operation of the Garigliano Nuclear Power Station as required under the participation contract between Enel and Euratom and refers to the first ten years of commercial operation (1 May 1964-31 December 1973) of the power station. In the decade in question the Garigliano Power Station has assumed an important position in the world spectrum of nuclear energy since it was the first thermal-power reactor in the world to have irradiated considerable quantities of plutonium as a fuel in its own core for the production of energy. An experimental programme on this was started in 1966 with theoretical study of plutonium recycling and was followed by the charging of the Garigliano reactor with some mixed oxide elements (PuO 2 -UO 2 ) in 1968 and 1970. The excellent performance of these prototype elements, which among other things were examined in detail at the end of each radiation cycle, prompted Enel to decide in favour of the use of entire batches of recycled fuel elements of the PuO 2 -UO 2 type in the reactor from 1975 onwards

  1. Dynamic behaviour of CANDU reactor

    International Nuclear Information System (INIS)

    Subramanian, M.G.; Srikantiah, G.; Pai, M.A.

    1976-01-01

    Understanding of the dynamic behaviour of a reactor system in a power station is essential for evolving control stragies as well as design modifications. The dynamic behaviour of Rajasthan Atomic Power Station is studied. Mathematical models for the reactor, the steam generator and the steam drum with the natural circulation loop are developed from physical principles like conservation of mass, momentum and energy. Each of these models is then simulated on a digital computer to obtain the characteristics during transients. The models are then combined to yield a dynamic mathematical model of the system comprising the reactor, the steam generator and the steam drum and this results in a nonlinear model. Using this model, responses of the system for various disturbances like step change in the area of the steam valve, step change in the temperature of feed water are obtained and are discussed. These models could be used to devise new control laws using optimal control theory or to evaluate the performance of existing control schemes. (author)

  2. Study of sources, dose contribution and control measures of Argon-41 at Kaiga Generating Station

    International Nuclear Information System (INIS)

    Venkata Ramana, K.; Shrikrishna, U.V.; Manojkumar, M.; Ramesh, R.; Madhan, V.; Varadhan, R.S.

    2001-01-01

    Air is used as a medium for cooling calandria vault and thermal shield systems in the earlier Pressurised Heavy Water Reactors (Rajasthan Atomic Power Station and Madras Atomic Power Station) in India. This leads to production of significant quantity of 41 Ar in calandria vault and thermal shield cooling systems due to neutron activation of 40 Ar present in air (∼1% v/v). The presence of 41 Ar in reactor building contributes significant external doses to plant personnel during reactor operation and the release of this radionuclide to the environment result in dose to the public in the vicinity of the plants. An attempt is made to eliminate Argon-41 production in Indian standard Pressurised Heavy Water Reactors (Narora Atomic Power Station, Kakrapar Atomic Power Station, Kaiga Generating Station -1 and 2 and Rajasthan Atomic Power Station-3 and 4), by filling the calandria vault with demineralized water and providing a separate Annulus Gas Monitoring System (AGMS) for detecting leaks from calandria tube or pressure tube using Carbon dioxide as a medium. However, 41 Ar is produced in the Annulus Gas Monitoring System, Primary Heat Transport cover gas system and moderator cover gas system due to ingress of air into the systems during operational transients or due to trace quantity of air present as an impurity in the gases used for the above systems. A study was conducted to identify and quantify the sources of 41 Ar in the work areas. This report brings out the sources of 41 Ar, reasons for 41 Ar production and the results of the measures incorporated to reduce the presence of 41 Ar in the above systems. (author)

  3. Developments in gaseous core reactor technology

    International Nuclear Information System (INIS)

    Diaz, N.J.; Dugan, E.T.

    1979-01-01

    An effort to characterize the most promising concepts for large, central-station electrical generation was done under the auspices of the Nonproliferation Alternative Systems Assessment Program (NASAP). The two leading candidates were identified from this effort: The Mixed-Flow Gaseous Core Reactor (MFGCR) and the Heterogeneous Gas Core Reactor (HGCR). Key advantages over other nuclear concepts are weighed against the disadvantages of an unproven technology and the cost-time for deployment to make a sound decision on RandD support for these promising reactor alternatives. 38 refs

  4. Fire protection devices in the controlled region of GKN nuclear power station

    International Nuclear Information System (INIS)

    Bernhardt, S.; Grauf, E.

    1976-01-01

    In the GKN nuclear power station ('Neckar reactor'), an 805 MW PWR reactor whose start-up is scheduled for the near future, fire protection measures have been realized that go far beyond those realized in other German nuclear power stations until now. One of the main reasons is that the authorities have been sensibilized by a fire in the refuelling cavity during construction and by the Browns Ferry fire and are therefore extremely thorough in their examination. Further subsections have been added to the fire prevention sections in order to provide better quenching devices for potential fire sites. (orig./AK) [de

  5. (Shippingport Atomic Power Station). Quarterly operating report, third quarter 1979

    Energy Technology Data Exchange (ETDEWEB)

    Jones, T. D.

    1979-01-01

    At the beginning of the third quarter of 1979, the Shippingport Atomic Power Station remained shutdown to complete repairs of the turbine generator hydrogen circulation fan following discovery of a rubbing noise on May 24, 1979. The Station was in a cooldown condition at approximately 180/sup 0/F and 300 psig with a steam bubble in the pressurizer and the reactor coolant pumps in slow speed. The reactor plant cooldown heat exchanger was in service to maintain coolant temperature. The 1A, 1B, 1C, and 1D reactor coolant loops and the 1AC and 1BD purification loops remained in service. All expended PWR Core 2 fuel elements have previously been shipped off-site. The remaining irradiated PWR Core 2 core barrel and miscellaneous refueling tools were in storage under shielding water in the deep pit of the Fuel Handling Building. The LWBR Core has generated 12,111.00 EFPH from startup through the end of the quarter.

  6. Socio-economic impacts of nuclear generating stations: Calvert Cliffs case study

    International Nuclear Information System (INIS)

    Flynn, J.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Calvert Cliffs nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  7. Socio-economic impacts of nuclear generating stations: Rancho Seco case study

    International Nuclear Information System (INIS)

    Bergmann, P.A.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Rancho Seco nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  8. Socio-economic impacts of nuclear generating stations: Peach Bottom case study

    International Nuclear Information System (INIS)

    Pijawka, K.D.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Peach Bottom nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  9. Release of low-contaminated reactor wastes for unrestricted use

    International Nuclear Information System (INIS)

    Carleson, G.

    1982-01-01

    A generic methodology has been used to evaluate the dose contributions to an individual and to the population of five categories of low-contaminated reactor wastes produced according to the Swedish program and released for unrestricted handling and use. A reference quantity with a surface dose rate below a predetermined level is followed along the whole commercial pathway from the reactor station to the final product consumer and/or a municipal waste station. Dose contributions are calculated for each step in a normal pathway under maximally unfavourable conditions. (Auth.)

  10. Weigh Station and Grid Plate Testing

    International Nuclear Information System (INIS)

    PAJUNEN, A.L.

    2000-01-01

    The purpose of this test is to verify that the Shortened Fuel Canister Hook with Certified Scale (i.e. Weigh Station) can be used to weigh an empty canister from the Canister Well and the empty Primary Cleaning Machine (PCM) Strainer Basket from the process table. Drawing H-1-84835, ''Canister Handling Hook for Fuel Retrieval System Process Table,'' provides details of the Shortened Fuel Canister Hook. It is also necessary to verify that the grid plate can be lifted and tilted over a canister in the canister well. This testing shall be performed before N Reactor fuel is processed through the FRS in Phase 3. The Phase 3 Test will repeatedly weigh fuel and scrap canisters and the PCM strainer basket containing N Reactor fuel (Pajunen, et. al, 2000). Advance testing of this weigh station will ensure that accurate fuel weight data can be recorded in the Phase 3 Test. This document satisfies the requirements EN-6-031-00, ''Testing Process'' for a test plan, test specification and test procedure

  11. Principles of nuclear power station control

    International Nuclear Information System (INIS)

    Knowles, J.B.

    1975-12-01

    This memorandum represents lecture notes first distributed as part of a UKAEA introductory course on Reactor Technology held during November 1975. A nuclear power station is only one element of a dispersed interconnected arrangement of other nuclear and fossil-fired units which together constitute the national 'grid'. Thus the control of any one station must relate to the objectives of the grid network as a whole. A precise control of the supply frequency of the grid is achieved by regulating the output power of individual stations, and it is necessary for each station to be stable when operating in isolation with a variable load. As regards individual stations, several special control problems concerned with individual plant items are discussed, such as: controlled reactivity insertions, temperature reactivity time constants and flow instability. A simplified analysis establishes a fundamental relationship between the stored thermal energy of a boiler unit (a function of mechanical construction) and the flexibility of the heat source (nuclear or fossil-fired) if the station is to cope satisfactorily with demands arising from unscheduled losses of other generating sets or transmission capacity. Two basic control schemes for power station operation are described known as 'coupled' and 'decoupled control'. Each of the control modes has its own merits, which depend on the proposed station operating strategy (base load or load following) and the nature of the heat source. (U.K.)

  12. Description of the advanced gas cooled type of reactor (AGR)

    Energy Technology Data Exchange (ETDEWEB)

    Nonboel, E. [Risoe National Lab., Roskilde (Denmark)

    1996-11-01

    The present report comprises a technical description of the Advanced Gas cooled Reactor (AGR), a reactor type which has only been built in Great Britain. 14 AGR reactors have been built, located at 6 different sites and each station is supplied with twin-reactors. The Torness AGR plant on the Lothian coastline of Scotland, 60 km east of Edinburgh, has been chosen as the reference plant and is described in some detail. Data on the other 6 stations, Dungeness B, Hinkely Point B, Hunterston G, Hartlepool, Heysham I and Heysham II, are given only in tables with a summary of design data. Where specific data for Torness AGR has not been available, corresponding data from other AGR plans has been used, primarily from Heysham II, which belongs to the same generation of AGR reactors. The information presented is based on the open literature. The report is written as a part of the NKS/RAK-2 subproject 3: `Reactors in Nordic Surroundings`, which comprises a description of nuclear power plants neighbouring the Nordic countries. (au) 11 refs.

  13. Description of the advanced gas cooled type of reactor (AGR)

    International Nuclear Information System (INIS)

    Nonboel, E.

    1996-11-01

    The present report comprises a technical description of the Advanced Gas cooled Reactor (AGR), a reactor type which has only been built in Great Britain. 14 AGR reactors have been built, located at 6 different sites and each station is supplied with twin-reactors. The Torness AGR plant on the Lothian coastline of Scotland, 60 km east of Edinburgh, has been chosen as the reference plant and is described in some detail. Data on the other 6 stations, Dungeness B, Hinkely Point B, Hunterston G, Hartlepool, Heysham I and Heysham II, are given only in tables with a summary of design data. Where specific data for Torness AGR has not been available, corresponding data from other AGR plans has been used, primarily from Heysham II, which belongs to the same generation of AGR reactors. The information presented is based on the open literature. The report is written as a part of the NKS/RAK-2 subproject 3: 'Reactors in Nordic Surroundings', which comprises a description of nuclear power plants neighbouring the Nordic countries. (au) 11 refs

  14. Reactor shutdown: nuclear power plant performance

    International Nuclear Information System (INIS)

    Anon.

    1982-01-01

    The article essentially looks at the performance of nine of Sweden's nuclear reactors. A table lists the percentage of time for the first three quarters of 1981 that the reactors were operating, and the number of hours out of service for planned or other reasons. In particular, one station - Ringhals 3 - was out of action because of a damaged tube in the associated steam generator. The same fault occurred with another reactor - Ringhals 4 - before this was brought into service. The reasons for the failure and its importance are briefly discussed. (G.P.)

  15. Dragon project reference design assessment study for a 528 MW (E) thorium cycle high temperature gas cooled reactor

    International Nuclear Information System (INIS)

    Hosegood, S.B.

    1967-05-01

    The report presents an assessment of the feasibility, safety and cost of a large nuclear power station employing a high temperature gas-cooled reactor. A thermal output 1250 MW was chosen for the study, resulting in a net electrical output of 528.34 MW from a single reactor station, or 1056.7 MW from a twin reactor station. A reference design has been developed and is described. The reactor uses a U-235/Th-232/U-233 fuel cycle, on a feed and breed basis. It is believed that such a reactor could be built at an early date, requiring only a relatively modest development programme. Building costs are estimated to be Pound46.66/kW for a single unit station and Pound42.6/kW for a twin station, with power generation costs of 1.67p/kWh and 1.50p/kWh respectively. Optimisation studies have not been carried out and it should be possible to improve on the costs. The design has been made as flexible as possible to allow units of smaller or larger outputs to be designed with a minimum of change. (U.K.)

  16. Next generation light water reactors

    International Nuclear Information System (INIS)

    Omoto, Akira

    1992-01-01

    In the countries where the new order of nuclear reactors has ceased, the development of the light water reactors of new type has been discussed, aiming at the revival of nuclear power. Also in Japan, since it is expected that light water reactors continue to be the main power reactor for long period, the technology of light water reactors of next generation has been discussed. For the development of nuclear power, extremely long lead time is required. The light water reactors of next generation now in consideration will continue to be operated till the middle of the next century, therefore, they must take in advance sufficiently the needs of the age. The improvement of the way men and the facilities should be, the simple design, the flexibility to the trend of fuel cycle and so on are required for the light water reactors of next generation. The trend of the development of next generation light water reactors is discussed. The construction of an ABWR was started in September, 1991, as No. 6 plant in Kashiwazaki Kariwa Power Station. (K.I.)

  17. SOLASE: a conceptual laser fusion reactor design

    International Nuclear Information System (INIS)

    Conn, R.W.; Abdel-Khalik, S.I.; Moses, G.A.

    1977-12-01

    The SOLASE conceptual laser fusion reactor has been designed to elucidate the technological problems posed by inertial confinement fusion reactors. This report contains a detailed description of all aspects of the study including the physics of pellet implosion and burn, optics and target illumination, last mirror design, laser system analysis, cavity design, pellet fabrication and delivery, vacuum system requirements, blanket design, thermal hydraulics, tritium analysis, neutronics calculations, radiation effects, stress analysis, shield design, reactor and plant building layout, maintenance procedures, and power cycle design. The reactor is designed as a 1000 MW/sub e/ unit for central station electric power generation

  18. Improvements in operational safety performance of the Magnox power stations

    Energy Technology Data Exchange (ETDEWEB)

    Marchese, C.J. [BNFL Magnox Generation, Berkeley (United Kingdom)

    2000-10-01

    In the 43 years since commencement of operation of Calder Hall, the first Magnox power station, there remain eight Magnox stations and 20 reactors still in operation, owned by BNFL Magnox Generation. This paper describes how the operational safety performance of these stations has significantly improved over the last ten years. This has been achieved against a background of commercial competition introduced by privatization and despite the fact that the Magnox base design belongs to the past. Finally, the company's future plans for continued improvements in operational safety performance are discussed. (author)

  19. Remote controlled ultrasonic pre-service and in-service inspections of reactor pressure vessels

    International Nuclear Information System (INIS)

    Mueller, G.

    1990-01-01

    The first mechanised in-service inspection of the reactor pressure vessel on unit one of Eskom's Koeberg nuclear power station has been carried out. Since 1968 a whole range of manipulators to carry out remote controlled ultrasonic inspections of nuclear power station equipment has been developed. The inspection of a reactor pressure vessel using a central mast manipulator is described. 3 figs., 1 ill

  20. The World's Reactors no. 70 - Forsmark 3, BWR-75

    International Nuclear Information System (INIS)

    Anon.

    1976-01-01

    A large pull-out wall chart is presented showing a coloured cut-away diagram of the Forsmark 3 station. It is accompanied by 2 small sketches one showing the layout of station buildings and the other the inside of the reactor vessel. Parameters are listed. (U.K.)

  1. Application of a steam injector for passive emergency core cooling during a station blackout

    International Nuclear Information System (INIS)

    Heinze, D.; Behnke, L.; Schulenberg, T.

    2012-01-01

    One of the basic protection targets of reactor safety is the safe heat removal during normal operation but also following shut-down. Since the reactor accident in Fukushima an optimization of the plant robustness in case of beyond-design accident is performed. Special attention is given to the increase of time available for starting appropriate measures for emergency core cooling in case of a station blackout. The state-of the art in engineering and research is presented. Investigations on the applicability of a steam injector for passive emergency core cooling during a station blackout in BWR-type reactors have progressed, experiments on dynamic behavior of the injector are described. A precise design with respect to the thermal hydraulic boundary conditions has been performed.

  2. Development of Reactor Protection System (RPS) in Reactor Digital Instrumentation and Control System (ReDICS)

    International Nuclear Information System (INIS)

    Mohd Khairulezwan Abdul Manan; Mohd Sabri Minhat; Ridzuan Abdul Mutalib

    2013-01-01

    RTP Research Reactor are in the process upgraded from analogue control console system to a digital control console system . Upgrade process requires a statistical study to improve safety during reactor operation. RPS was developed to meet the needs of operational safety and at the same time comply with the guidelines set by the IAEA. RPS is in analog and hardware with industry standard interfaced with digital DAC (Data Acquisition and Control) and OWS (Operator Work Station). (author)

  3. A Review of the UK Fast Reactor Programme: March 1980

    International Nuclear Information System (INIS)

    Smith, R.D.

    1980-01-01

    Towards the end of 1979 the Government announced a new programme of thermal reactor stations to be built over ten years (totalling 15GW), in addition to the two AGR stations at Torness and Heysham 'B' which had been approved by the previous Government. The first station of the new programme will be based on a Westinghouse PWR, subject to safety clearance and the outcome of a public inquiry, and it is envisaged that the remaining stations of the programme would be split between PWRs and AGRs. The AEA Chairman wrote formally to the Secretary of State for Energy in December 1979, putting forward on behalf of the Electricity Supply Authorities, NNC, BNFL and the AEA a recommended strategy for building the Commercial Demonstration Fast Reactor (CDFR), subject to normal licensing procedure and to public inquiry, so as to ensure that the key options for introducing commercial fast reactors, when required, should remain open. A Government statement is expected during the next few months. Meanwhile the level of effort on fast reactor research and development in the UK has been maintained, the fast reactor remaining the largest of the UKAEA's reactor development projects with expenditure totalling somewhat over £80M per annum. The main feature of the UK fast reactor programme has continued to be the operation of PFR (Sections 2 and 7) which is yielding a wealth of experience and of information relevant to the design of commercial fast reactors. Bum-up of standard driver fuel has reached 6-7% by heavy atoms, while specially enriched lead fuel pins have reached 11 % without failure. An extensive programme of work in the reactor and its associated steam plant was completed in March 1980 and the reactor then started its fifth power run. The fuel reprocessing plant at DNE is being commissioned and has reprocessed some of the spent fuel remaining from the DFR. It will start soon on reprocessing fuel discharged from the PFR. During the year improvements to the design of the future

  4. Monitoring the Microgravity Environment Quality On-Board the International Space Station Using Soft Computing Techniques

    Science.gov (United States)

    Jules, Kenol; Lin, Paul P.

    2001-01-01

    This paper presents an artificial intelligence monitoring system developed by the NASA Glenn Principal Investigator Microgravity Services project to help the principal investigator teams identify the primary vibratory disturbance sources that are active, at any moment in time, on-board the International Space Station, which might impact the microgravity environment their experiments are exposed to. From the Principal Investigator Microgravity Services' web site, the principal investigator teams can monitor via a graphical display, in near real time, which event(s) is/are on, such as crew activities, pumps, fans, centrifuges, compressor, crew exercise, platform structural modes, etc., and decide whether or not to run their experiments based on the acceleration environment associated with a specific event. This monitoring system is focused primarily on detecting the vibratory disturbance sources, but could be used as well to detect some of the transient disturbance sources, depending on the events duration. The system has built-in capability to detect both known and unknown vibratory disturbance sources. Several soft computing techniques such as Kohonen's Self-Organizing Feature Map, Learning Vector Quantization, Back-Propagation Neural Networks, and Fuzzy Logic were used to design the system.

  5. Integrity of pressurized water electronuclear reactor vessels. The case of French reactors

    International Nuclear Information System (INIS)

    2012-01-01

    This document aims at identifying elements related to design, manufacturing and control during operation of reactor vessels of the French electronuclear fleet, and more precisely as far as vessel ferrule is concerned. It briefly describes the typical design and elements of most of French PWR vessels with respect to the reactor type (900 MWe, 1300 MWe, 1450 MWe, EPR). It recalls some measures regarding design (for embrittlement assessment) and manufacturing processes (forging operations for shell fabrication, coatings). It discusses the different manufacturing defects which have been noticed (under the coatings, due to hydrogen, and intergranular loss of cohesion due to re-heating). It more particularly comments defects noticed on a Belgium power station reactor in Doel, defects due to hydrogen and some other defects noticed in the French reactor fleet. It presents the different types of control which are performed on vessel shells during operation

  6. AECB staff annual assessment of the Bruce B Nuclear Generating Station for the year 1996

    International Nuclear Information System (INIS)

    1997-06-01

    The Atomic Energy Control Board is the independent federal agency that controls all nuclear activities in Canada. A major use of nuclear energy in Canada is electricity production. The AECB assesses every station's performance against legal requirements, including the conditions in the operating licence. Each station is inspected and all aspects of the station's operation and management is reviewed. This report is the AECB staff assessment of reactor safety at the Bruce Nuclear Generating Station B for 1996. It was concluded that Ontario Hydro operated Bruce B safely in 1996. Although the Bruce B plant is safe,it was noted that the number of outages and the number of secondary and tertiary equipment failures during reactor unit upsets increased. Ontario Hydro needs to pay special attention to prevent such a decrease in the safety performance at Bruce B

  7. Socio-economic impacts of nuclear generating stations: D. C. Cook case study

    International Nuclear Information System (INIS)

    Branch, K.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the D. C. Cook nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  8. Socio-economic impacts of nuclear generating stations: Three Mile Island case study

    International Nuclear Information System (INIS)

    Flynn, C.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Three Mile Island nuclear power stations. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  9. Public relations activities of the Service Hall for Kashiwazaki-Kariwa Nuclear Power Station

    International Nuclear Information System (INIS)

    Kono, T.

    1998-01-01

    This article includes information of the Service Hall for Kashiwazaki-Kariwa Nuclear Power Station. About 30% of the total electricity production in Japan is due to 16 power stations and 52 reactors. The service hall is a kind of atomic power pavilion for public relations. In Japan, each nuclear power station has such a pavilion, which acts a a center of public relations activities for the atomic power. (S. Grainger)

  10. Gas reactor and associated nuclear experience in the UK relevant to high temperature reactor engineering

    International Nuclear Information System (INIS)

    Beech, D.J.; May, R.

    2000-01-01

    In the UK, the NNC played a leading role in the design and build of all of the UK's commercial magnox reactors and advanced gas-cooled reactors (AGRs). It was also involved in the DRAGON project and was responsible for producing designs for large scale HTRs and other gas reactor designs employing helium and carbon dioxide coolants. This paper addresses the gas reactor experience and its relevance to the current HTR designs under development which use helium as the coolant, through the consideration of a representative sample of the issues addressed in the UK by the NNC in support of the AGR and other reactor programmes. Modern HTR designs provide unique engineering challenges. The success of the AGR design, reflected in the extended lifetimes agreed upon by the licensing authorities at many stations, indicates that these challenges can be successfully overcome. The UK experience is unique and provides substantial support to future gas reactor and high temperature engineering studies. (authors)

  11. Digital control system of advanced reactor

    International Nuclear Information System (INIS)

    Peng Huaqing; Zhang Rui; Liu Lixin

    2001-01-01

    This article produced the Digital Control System For Advanced Reactor made by NPIC. This system uses Siemens SIMATIC PCS 7 process control system and includes five control system: reactor power control system, pressurizer level control system, pressurizer pressure control system, steam generator water level control system and dump control system. This system uses three automatic station to realize the function of five control system. Because the safety requisition of reactor is very strict, the system is redundant. The system configuration uses CFC and SCL. the human-machine interface is configured by Wincc. Finally the system passed the test of simulation by using RETRAN 02 to simulate the control object. The research solved the key technology of digital control system of reactor and will be very helpful for the nationalization of digital reactor control system

  12. Analysis of a station blackout transient at the Kori units 3/4

    International Nuclear Information System (INIS)

    Bang, Young Seok; Kim, Hho Jung

    1992-01-01

    A transient analysis of station blackout accident is performed to evaluate the plant specific capability to cope with the accident at the Kori Units 3/4. The RELAP5/MOD3/5m5 code and full three loop modelling scheme are used in the calculation. The leak flow from reactor coolant system due to a failure of reactor coolant pump seal following the accident is assumed to be 25 gpm and the turbine driven aux feedwater unavailable. As a result, it is found that no core uncovery occurs in the plant until 7100 sec following a station blackout, the steam generator has a decay heat removal capability until 3100 sec, and the natural circulation over the reactor coolant loop until the complete loop seal voiding are observed. And the Nuclear Plant Analyzer is used and found to be effective in improving the phenomenological understanding on the accident

  13. Station power supply by residual steam of Fugen

    Energy Technology Data Exchange (ETDEWEB)

    Kamiya, Y.; Kato, H.; Hattori, S. (Power Reactor and Nuclear Fuel Development Corp., Tokyo (Japan))

    1981-09-01

    In the advanced thermal reactor ''Fugen'', when the sudden decrease of load more than 40% occurs due to the failure of power system, the turbine regulating valve is rapidly shut, and the reactor is brought to scrum. However, the operation of turbo-generators is continued with the residual steam in the reactor, and the power for inside the station is supplied for 30 sec by the limiting timer, then the power-generating plant is automatically stopped. The reasons why such design was adopted are to reduce manual operation at the time of emergency, to continue water supply for cooling the reactor and to maintain the water level in the steam drum, and to reduce steam release from the safety valve and the turbine bypass valve. The output-load unbalance relay prevents the everspeed of the turbo-generator when load decreased suddenly, but when the failure of power system is such that recovers automatically in course of time, it does not work. The calculation for estimating the dynamic characteristics at the time of the sole operation within the station is carried out by the analysis code FATRAC. The input conditions for the calculation and the results are reported. Also the dynamic characteristics were actually tested to confirm the set value of the limiting timer and the safe working of turbine and generator trips. The estimated and tested results were almost in agreement.

  14. Pellet bed reactor for multi-modal space power

    International Nuclear Information System (INIS)

    Buden, D.; Williams, K.; Mast, P.; Mims, J.

    1987-01-01

    A review of forthcoming space power needs for both civil and military missions indicates that power requirements will be in the tens of megawatts. The electrical power requirements are envisioned to be twofold: long-duration lower power levels will be needed for station keeping, communications, and/or surveillance; short-duration higher power levels will be required for pulsed power devices. These power characteristics led to the proposal of a multi-modal space power reactor using a pellet bed design. Characteristics desired for such a multimegawatt reactor power source are standby, alert, and pulsed power modes; high-thermal output heat source (approximately 1000 MWt peak power); long lifetime station keeping power (10 to 30 years); high temperature output (1500 K to 1800 K); rapid-burst power transition; high reliability (above 95 percent); and stringent safety standards compliance. The proposed pellet bed reactor is designed to satisfy these characteristics

  15. Training of engineers for nuclear power station operation

    International Nuclear Information System (INIS)

    Myerscough, P.B.

    1980-01-01

    The requirements for staffing and training of a nuclear electric utility are described. Current training facilities at the Central Electricity Generating Board are applicable to gas-cooled technology with the possibility of the introduction of a thermal water system and fast reactors in the future. The CEGB training centres provide for the initial training of operational staff, revision training of experienced operational staff, and training of non-operational staff from the stations and supporting departments. Details are given of the content of the training courses which also provide simulation facilities of the basic dynamics of the CEGB stations. Further developments in simulation will include dynamics of the boiler and turbine plants in Magnox stations. The flexibility of the AGR simulations will enable the training exercises to be adjusted to meet changing operating patterns for each AGR station. (U.K.)

  16. Pneumatic transport systems for TRIGA reactors

    International Nuclear Information System (INIS)

    Bolton, John A.

    1970-01-01

    Main parameters and advantages of pneumatically operated systems, primarily those operated by gas pressure are discussed. The special irradiation ends for the TRIGA reactor are described. To give some idea of the complexity of some modern systems, the author presents the large system currently operating at the National Bureau of Standards in Washington. In this system, 13 stations are located throughout the radiochemistry laboratories and three irradiation ends are located in the reactor, which is a 14-megawatt unit. The system incorporates practically every fail-safe device possible, including ball valves located on all capsule lines entering the reactor area, designed to close automatically in the event of a reactor scram, and at that time capsules within the reactor would be diverted by means of switches located on the inside of the reactor wall. The whole system is under final control of a permission control panel located in the reactor control room. Many other safety accessories of the system are described

  17. Reactor Neutrino Oscillations: KamLAND and KASKA

    International Nuclear Information System (INIS)

    Suekane, F.

    2006-01-01

    Nuclear reactors generate a huge number of low energy ν-bar e 's. The reactor neutrinos have been used to study properties of neutrinos since its discovery a half century ago. Recently, KamLAND group finally discovered reactor neutrino oscillation with average baseline 180 km. According to the 3 flavor scheme of standard theory and measured oscillation parameters so far, the reactor neutrino is expected to perform another type of small oscillation at a baseline 1.8 km. KASKA experiment is a project to detect this small oscillation and to measure the last neutrino mixing angle θ 13 by using the world most powerful reactor complex, Kashiwazaki-Kariwa nuclear power station. In this proceedings, phenomena of neutrino oscillation and the two reactor oscillation experiments, KamLAND and KASKA, are introduced

  18. Accident Analysis of Chinese CPR1000 in Response to Station Blackout

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Juyoul [FNC Technology Co., Yongin (Korea, Republic of); Cilliers, Anthonie [North-West University, Potchefstroom (South Africa)

    2016-10-15

    Stress tests required evaluation of the consequences of loss of safety functions from any initiating event (e.g., earthquake or flooding) causing loss of electrical power, including station blackout (SBO). The SBO scenario involves a loss of offsite power, failure of the redundant emergency diesel generators, failure of alternate current (AC) power restoration and the eventual degradation of the reactor coolant pump (RCP) seals resulting in a long term loss of coolant. Using PCTRAN/CPR1000, this study analyses the station blackout on a Chinese CPR1000 which is the most representative type reactor in terms of number of reactors, operating period, power capacity and geological distance from Korean Peninsula. Both the physical effects of the accidents as well as the releases of radioisotopes are calculated and discussed. Station blackout simulation was conducted in this study. The resulting effects seen are consistent with other stress test station blackout tests used utilizing licensed simulation codes. An exact comparison is however not possible as the plants on which the simulations was done vary greatly and the limitations of availability to Chinese FSAR. PCTRAN/CPR1000 is an extremely useful simulation package that provides engineers and scientists very accurate feedback to how a nuclear power plant would react as a whole under various plant conditions. It is able to do this extremely fast as well. As a training tool PCTRAN/CPR1000 provides hands-on experience with many of the primary plant operations and develops an intuitive understanding of the plant.

  19. Ten year report on the operation of the Latina nuclear power station 1964-1973

    International Nuclear Information System (INIS)

    1976-07-01

    The final report on the operation of the Latina nuclear power station, required under the terms of the contract of participation between ENEL and EURATOM is presented. It covers the first ten years of commercial operation (1 January 1964-31 December 1973) of this power station. Latina uses a British Magnox-type gas-graphite natural uranium reactor with a design thermal capacity of 724 MW. The rated electrical output of the three main turbogenerators was originally 210 MW (3x70), but was reduced to 160 MW in 1971. Construction began in November 1958 and was completed when the reactor first reached criticality in December 1962, the station being connected to the Italian electricity network for the first time in May 1963. The gross rated output of 210 MWe was reached in December 1963 and commercial operation began on 1 January 1964, by which date, however, the power station had already fed 295.5 million kWh into the network

  20. Implementation of multiple measures to improve reactor recirculation pump sealing performance in nuclear boiling water reactor service

    Energy Technology Data Exchange (ETDEWEB)

    Loenhout, Gerard van [Flowserve B.V., Etten-Leur (Netherlands). Nuclear Services and Solutions Engineering; Hurni, Juerg

    2014-07-01

    A modern reactor recirculation pump circulates a large volume of high temperature, very pure water from the reactor pressure vessel back to the core. A crucial technical problem with a recirculation pump, such as a mechanical seal indicating loss of sealing pressure, may result in a power station having to shut down for repair. The paper describes the sudden increase in stray current phenomenon leading to rapid and severe deterioration of the mechanical end face shaft seal in a reactor recirculation pump. This occurred after the installation of a variable frequency converter replacing the original motorgenerator set.

  1. Implementation of multiple measures to improve reactor recirculation pump sealing performance in nuclear boiling water reactor service

    International Nuclear Information System (INIS)

    Loenhout, Gerard van; Hurni, Juerg

    2014-01-01

    A modern reactor recirculation pump circulates a large volume of high temperature, very pure water from the reactor pressure vessel back to the core. A crucial technical problem with a recirculation pump, such as a mechanical seal indicating loss of sealing pressure, may result in a power station having to shut down for repair. The paper describes the sudden increase in stray current phenomenon leading to rapid and severe deterioration of the mechanical end face shaft seal in a reactor recirculation pump. This occurred after the installation of a variable frequency converter replacing the original motorgenerator set.

  2. Snubber reduction program at the Byron Station, Unit 1

    International Nuclear Information System (INIS)

    Arterburn, J.; Bakhtiari, S.

    1987-01-01

    Commonwealth Edison Company's (CECo's) Byron Station, unit 1, was originally designed with approximately 1200 snubbers supporting the plant's large- and small-bore piping systems. This relatively large number of snubbers is attributed to excessive conservatism in nuclear piping codes and regulations effective during the original piping design. A recent pilot program at CECo's LaSalle County Station, a boiling water reactor plant, demonstrated that a 50% or greater reduction in total snubber population is achievable in plants of this design vintage. Based on the successful results of the pilot program, CECo initiated a full scale snubber reduction program at Byron, a pressurized water reactor plant of the same vintage at the LaSalle County Station. The benefits from a reduced snubber population are described. To realize the maximum potential benefits, all snubbers in the plant were prioritized in order of desirability for removal. The priority designations are discussed. The major results from phase 1 of the Byron program are summarized. The NRC inspection of the project addressed a variety of issues and is discussed. The conclusions that can be drawn from the phase 1 program are summarized

  3. Radioactivity monitoring by the official monitoring stations in North-Rhine Westphalia and the Juelich Nuclear Research Centre after the Chernobyl reactor accident

    International Nuclear Information System (INIS)

    1986-01-01

    This official report presents a governmental declaration of the prime minister of NRW, Mr. Rau, concerning the reactor accident at Chernobyl, and a joint declaration of ministers of NRW, concerning the impact of the accident on the Land NRW. These statements are completed by six official reports on radioactivity measurements carried out by the official monitoring stations of the Land and by the KFA Juelich. These reports inform about methods, scope, and results of the measuring campaigns accomplished by the Zentralstelle fuer Sicherheitstechnik (ZFS), the public materials testing office (MPA), the Chemisches Untersuchungsamt, the Landesamt fuer Wasser und Abfall, and the KFA Juelich. (DG) [de

  4. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Harrison, J.R.

    1982-11-01

    An overview is given of the Safety Case for the Sizewell B nuclear power station as presented in the Pre-Construction Safety Report. Information which has been made available since its publication is included. Safety is considered for normal operation of the reactor and under fault conditions. Faults considered are those due to external hazards such as earthquakes, extreme weather conditions and aircraft crashes, internal hazards such as fire and missiles and reactor faults. Reactor fault studies described include transient analyses of pressurised faults and of loss-of-coolant accidents and the evaluation of the radiological consequences of design basis faults. (U.K.)

  5. Risk of loss power for ATWT in Daya Bay and Ling'ao nuclear power stations

    International Nuclear Information System (INIS)

    Guo Cheng

    2010-01-01

    In order to analyze the differences between the Anticipated Transient Without Reactor Trip (ATWT) and other reactor protection methods, this paper analyzes in detail the realizing means of ATWT and the effect of lost of power supply on the units based on Daya Bay and Ling'ao Nuclear Power Stations by system wiring diagram. Based on the comprehensive analysis,this paper proposes the sequence for powering when recovering the power source after ATWT power supply (LCC/LNE) loss for Daya Bay and Ling'ao Nuclear Power Stations. (authors)

  6. Safety aspects of designs for future light water reactors (evolutionary reactors)

    International Nuclear Information System (INIS)

    1993-07-01

    The main purpose of this document is to describe the major innovations of proposed designs of future light water reactors, to describe specific safety characteristics and safety analysis methodologies, and to give a general overview of the most important safety aspects related to future reactors. The reactors considered in this report are limited to those intended for fixed station electrical power production, excluding most revolutionary concepts. More in depth discussion is devoted to those designs that are in a more advanced state of completion and have been more extensively described and analysed in the open literature. Other designs will be briefly described, as evidence of the large spectrum of new proposals. Some designs are similar; others implement unique features and require specific discussion (not all aspects of designs with unique features are fully discussed in this document). 131 refs, 22 figs

  7. Process for extracting residual heat and device for the ultimate absorption of heat for nuclear reactors

    International Nuclear Information System (INIS)

    Bernard, Lawrence Jr.

    1980-01-01

    This invention concerns a 'heat sink' or device for the ultimate absorption of heat for electric power stations using the most widespread thermal neutron nuclear reactors, namely 'light water' reactors such as boiling or pressurized water reactors. The residual heat given off by these reactors can be safely extracted with this method by using dry cooling. However, the invention does not concern the problems arising from the cooling of the steam used for actuating the steam turbine nor the cooling of the steam exhausted by the turbine or coming from it, but it does concern the 'safety' part of the nuclear power station in which the residual heat discharged in the reactor is controlled and dissipated [fr

  8. Development of upgraded full-core 3D diffusion models for the Pickering stations

    Energy Technology Data Exchange (ETDEWEB)

    Arsenault, B., E-mail: benoit.arsenault@amecfw.com [AMEC Foster Wheeler, Toronto, ON (Canada); Catovic, Z., E-mail: zlatko.catovic@opg.com [Ontario Power Generation, Pickering, ON (Canada); Shaula, S., E-mail: sergiy.shaula@amecfw.com [AMEC Foster Wheeler, Toronto, ON (Canada); Buchan, P.D., E-mail: david.buchan@opg.com [Ontario Power Generation, Pickering, ON (Canada)

    2015-07-01

    This paper describes a methodology used to model Pickering reactors with the Reactor Physics toolset currently in use at OPG stations, which includes the Reactor Physics Industry Standard Toolset (RFSP-IST/WIMS-IST/DRAGON-IST) and the fuel management code SORO. Detailed geometries were modeled in DRAGON-IST with devices and structures that extended into the reflector region and incremental properties were calculated for reactivity devices, guide tubes and structural materials based on the engineering drawings. Simulations and comparisons with measurements performed showed improved predictive capabilities of the new reactor physics models. (author)

  9. Development of upgraded full-core 3D diffusion models for the Pickering stations

    International Nuclear Information System (INIS)

    Arsenault, B.; Catovic, Z.; Shaula, S.; Buchan, P.D.

    2015-01-01

    This paper describes a methodology used to model Pickering reactors with the Reactor Physics toolset currently in use at OPG stations, which includes the Reactor Physics Industry Standard Toolset (RFSP-IST/WIMS-IST/DRAGON-IST) and the fuel management code SORO. Detailed geometries were modeled in DRAGON-IST with devices and structures that extended into the reflector region and incremental properties were calculated for reactivity devices, guide tubes and structural materials based on the engineering drawings. Simulations and comparisons with measurements performed showed improved predictive capabilities of the new reactor physics models. (author)

  10. Periodic reviews of structural integrity of gas-cooled reactors

    International Nuclear Information System (INIS)

    Banks, P.J.; Stokoe, T.Y.; Thomas, D.L.

    1995-01-01

    Nuclear Electric operates 12 gas-cooled reactor power stations which have been in service for between 5 and 30 years. Periodically, comprehensive reviews of the safety cases are carried out for each station. The approach followed in these reviews in respect of structural integrity is outlined with the use of illustrative examples. (author)

  11. Upgrading of fire protection arrangements at Magnox power stations in the United Kingdom

    International Nuclear Information System (INIS)

    Zhu, L.H.

    1998-01-01

    The methodology used in conducting fire hazard assessments at Magnox Reactor power stations operated by Magnox Electric plc is described. The assessments use a deterministic approach. This includes the identification of essential plant and the associated supporting systems required for the safe trip, shutdown and post-trip cooling of the reactor, assessment of the location of the essential plant and the vulnerability of these plant in the presence of a fire, assessment of essential functions against the effects of a fire and identification of improvements to the fire protection arrangements. Practical aspects of fire protection engineering on operating power stations are discussed and examples of improvements in protection described. (author)

  12. Socio-economic impacts of nuclear generating stations: Crystal River Unit 3 case study

    International Nuclear Information System (INIS)

    Bergmann, P.A.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Crystal River Unit 3 nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  13. The fast reactor and energy supply

    International Nuclear Information System (INIS)

    1979-01-01

    The progress made with fast reactor development in many countries is summarised showing that the aim is to provide to the nation concerned an ability to instal fast reactor power stations at the end of this century or early in the next one. Accepting the importance of fast reactors as a potential independent source of energy, problems concerning economics, industrial capability, technical factors, public acceptibility and in particular plutonium management, are discussed. It is concluded that although fast reactors have reached a comparatively advanced stage of development, a number of factors make it likely that their introduction for electricity generation will be a gradual process. Nevertheless it is necessary to complete demonstration and development phases in good time. (U.K.)

  14. Operating Experience at the Aagesta Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Sandstroem, S [ed.

    1966-09-15

    Sweden's first nuclear power reactor Agesta, achieved criticality on July 17, 1963. Full power (65 MW{sub t}) was attained on March 20, 1964. Aagesta is a heavy water cooled and moderated pressure vessel reactor used for production of electricity as well as for district heating. The design, assembly and construction etc, of the reactor was described in detail in a staff report by AB Atomenergi, 'The Aagesta Nuclear Power Station' edited by B McHugh, which was published in September, 1964. In the book experiences from the commissioning and the first operation of the reactor were reported as well as findings from the extensive reactor physics studies made during this period. The report now presented is written by members of the operating team at Aagesta since its start. It reflects in general the experiences up to the end of 1965. The Aagesta Log, however, covers the period up to the normal summer stop 1966. The reactor has hitherto produced 506,000 MWh power of which 48,700 MWh have been electric power. In July 1965 the responsibility for the reactor operation was taken over by the Swedish State Power Board from AB Atomenergi, which company had started the reactor and operated it until the summer break 1965.

  15. Operating Experience at the Aagesta Nuclear Power Station

    International Nuclear Information System (INIS)

    Sandstroem, S.

    1966-09-01

    Sweden's first nuclear power reactor Agesta, achieved criticality on July 17, 1963. Full power (65 MW t ) was attained on March 20, 1964. Aagesta is a heavy water cooled and moderated pressure vessel reactor used for production of electricity as well as for district heating. The design, assembly and construction etc, of the reactor was described in detail in a staff report by AB Atomenergi, 'The Aagesta Nuclear Power Station' edited by B McHugh, which was published in September, 1964. In the book experiences from the commissioning and the first operation of the reactor were reported as well as findings from the extensive reactor physics studies made during this period. The report now presented is written by members of the operating team at Aagesta since its start. It reflects in general the experiences up to the end of 1965. The Aagesta Log, however, covers the period up to the normal summer stop 1966. The reactor has hitherto produced 506,000 MWh power of which 48,700 MWh have been electric power. In July 1965 the responsibility for the reactor operation was taken over by the Swedish State Power Board from AB Atomenergi, which company had started the reactor and operated it until the summer break 1965

  16. Operating Experience at the Aagesta Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Sandstroem, S. (ed.)

    1966-09-15

    Sweden's first nuclear power reactor Agesta, achieved criticality on July 17, 1963. Full power (65 MW{sub t}) was attained on March 20, 1964. Aagesta is a heavy water cooled and moderated pressure vessel reactor used for production of electricity as well as for district heating. The design, assembly and construction etc, of the reactor was described in detail in a staff report by AB Atomenergi, 'The Aagesta Nuclear Power Station' edited by B McHugh, which was published in September, 1964. In the book experiences from the commissioning and the first operation of the reactor were reported as well as findings from the extensive reactor physics studies made during this period. The report now presented is written by members of the operating team at Aagesta since its start. It reflects in general the experiences up to the end of 1965. The Aagesta Log, however, covers the period up to the normal summer stop 1966. The reactor has hitherto produced 506,000 MWh power of which 48,700 MWh have been electric power. In July 1965 the responsibility for the reactor operation was taken over by the Swedish State Power Board from AB Atomenergi, which company had started the reactor and operated it until the summer break 1965.

  17. Operational experience of the Marcoule reactors

    International Nuclear Information System (INIS)

    Conte, F.

    1963-01-01

    The results obtaining from three years operation of the reactors G-2, G-3 have made it possible to accumulate a considerable amount of operational experience of these reactors. The main original points: - the pre-stressed concrete casing - the possibility of loading while under power - automatic temperature control have been perfectly justified by the results of operation. The author confirms the importance of these original solutions and draws conclusions concerning the study of future nuclear power stations. (author) [fr

  18. Reactor safety training for decision making

    International Nuclear Information System (INIS)

    Scott, C.K.

    2003-01-01

    The purpose of this paper is to describe an approach to reactor safety training for technical staff working at an operating station. The concept being developed is that, when the engineer becomes a registered professional engineer, they have sufficient reactor safety knowledge to perform independent technical work without compromising the safety of the plant. This goal would be achieved with a focused training program while working as an engineer-in-training (four years in NB). (author)

  19. Activity transport in nuclear generating stations

    International Nuclear Information System (INIS)

    Mitchell, A.B.

    1975-01-01

    The objective of this paper is to give a basic understanding of the operational limitations caused by radiation fields in the present design of CANDU-PHW reactors. A simple model of activity transport is described, and the significance of various radioisotopes identified. The impact which radiation fields have at the Divisional, Station Manager and Operation levels, is outlined in the context of typical work situations. (author)

  20. Method of operating a nuclear reactor

    International Nuclear Information System (INIS)

    Spurgin, A.J.; Schaefer, W.F.

    1978-01-01

    A method of controlling a nuclear power generting station in the event of a malfunction of particular operating components is described. Upon identification of a malfunction, preselected groups of control rods are fully inserted sequentially until a predetermined power level is approached. Additional control rods are then selectively inserted to quickly bring the reactor to a second given power level to be compatible with safe operation of the system with the malfunctioning component. At the time the thermal power output of the reactor is being reduced, the turbine is operated at a rate consistent with the output of the reactor. In the event of a malfunction, the power generating system is operated in a turbine following reactor mode, with the reactor power rapidly reduced, in a controlled manner, to a safe level compatible with the type of malfunction experienced

  1. Light Water Reactor Sustainability Constellation Pilot Project FY11 Summary Report

    International Nuclear Information System (INIS)

    Johansen, R.

    2011-01-01

    Summary report for Fiscal Year 2011 activities associated with the Constellation Pilot Project. The project is a joint effor between Constellation Nuclear Energy Group (CENG), EPRI, and the DOE Light Water Reactor Sustainability Program. The project utilizes two CENG reactor stations: R.E. Ginna and Nine Point Unit 1. Included in the report are activities associate with reactor internals and concrete containments.

  2. Light Water Reactor Sustainability Program Support and Modeling for the Boiling Water Reactor Station Black Out Case Study Using RELAP and RAVEN

    Energy Technology Data Exchange (ETDEWEB)

    Mandelli, Diego [Idaho National Lab. (INL), Idaho Falls, ID (United States); Smith, Curtis [Idaho National Lab. (INL), Idaho Falls, ID (United States); Riley, Thomas [Idaho National Lab. (INL), Idaho Falls, ID (United States); Schroeder, John [Idaho National Lab. (INL), Idaho Falls, ID (United States); Rabiti, Cristian [Idaho National Lab. (INL), Idaho Falls, ID (United States); Alfonsi, Aldrea [Idaho National Lab. (INL), Idaho Falls, ID (United States); Nielsen, Joe [Idaho National Lab. (INL), Idaho Falls, ID (United States); Maljovec, Dan [Idaho National Lab. (INL), Idaho Falls, ID (United States); Wang, Bie [Idaho National Lab. (INL), Idaho Falls, ID (United States); Pascucci, Valerio [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2013-09-01

    The existing fleet of nuclear power plants is in the process of extending its lifetime and increasing the power generated. In order to evaluate the impact of these two factors on the safety of the plant, the Risk Informed Safety Margin Characterization (RISMC) project aims to provide insight to decision makers through a series of simulations of the plant dynamics for different initial conditions (e.g., probabilistic analysis and uncertainty quantification). This report focuses, in particular, on the impact of power uprate on the safety of a boiled water reactor system. The case study considered is a loss of off-site power followed by the loss of diesel generators, i.e., a station black out (SBO) event. Analysis is performed by using a thermo-hydraulic code, i.e. RELAP-5, and a stochastic analysis tool currently under development at INL, i.e. RAVEN. Starting from the event tree models contained in SAPHIRE, we built the input file for RELAP-5 that models in great detail system dynamics under SBO conditions. We also interfaced RAVEN with RELAP-5 so that it would be possible to run multiple RELAP-5 simulation runs by changing specific keywords of the input file. We both employed classical statistical tools, i.e. Monte-Carlo, and more advanced machine learning based algorithms to perform uncertainty quantification in order to quantify changes in system performance and limitations as a consequence of power uprate. We also employed advanced data analysis and visualization tools that helped us to correlate simulation outcome such as maximum core temperature with a set of input uncertain parameters. Results obtained gave a detailed overview of the issues associated to power uprate for a SBO accident scenario. We were able to quantify how timing of safety related events were impacted by a higher reactor core power. Such insights can provide useful material to the decision makers to perform risk-infomed safety margins management.

  3. Service hall in Number 1 Fukushima Nuclear Power Station, Tokyo Electric Power Company, Inc

    International Nuclear Information System (INIS)

    Tawara, Shigesuke

    1979-01-01

    There are six BWR type nuclear power plants in the Number 1 Fukushima Nuclear Power Station, Tokyo Electric Power Company, Inc. The service hall of the station is located near the entrance of the station. In the center of this service hall, there is the model of a nuclear reactor of full scale. This mock-up shows the core region in the reactor pressure vessel for the number one plant. The diameter and the thickness of the pressure vessel are about 5 m and 16 cm, respectively. The fuel assemblies and control rods are set just like the actual reactor, and the start-up operation of the reactor is shown colorfully and dynamically by pushing a button. When the control rods are pulled out, the boiling of water is demonstrated. The 1/50 scale model of the sixth plant with the power generating capacity of 1100 MWe is set, and this model is linked to the mock-up of reactor written above. The operations of a recirculating loop, a turbine and a condenser are shown by switching on and off lamps. The other exhibitions are shielding concrete wall, ECCS model, and many kinds of panels and models. This service hall is incorporated in the course of study and observation of civics. The good environmental effects to fishes and shells are explained in this service hall. Official buildings and schools are built near the service hall utilizing the tax and grant concerning power generation. This service hall contributes to give much freedom from anxiety to the public by the tour. (Nakai, Y.)

  4. Rate of generation of tritium during the operation of Tsuruga Power Station Unit No. 2

    International Nuclear Information System (INIS)

    Funamoto, Hisao; Yoshinari, Masaharu; Fukuda, Masayuki; Makino, Shinichi; Watari, Tuneo

    1994-01-01

    Total amount of 3 H activity in primary coolant due to the operation of Tsuruga Power Station Unit No. 2 was estimated. The 3 H inventory was measured for samples from the spent fuel pool, primary coolant and miscellaneous tanks. From the result of the measurement and the data of environmental release of 3 H, the rate of generation of 3 H in the reactor was found to be 25 TBq/GWa. Since Tsuruga Power Station Unit No. 2 is a PWR type reactor, we presume that most of the 3 H in primary coolant is formed by 10 B(n, 2α) 3 H reaction. It is necessary to release about 23 TBq/GWa of 3 H to maintain the station inventory at the present level. (author)

  5. Potential of remote multiplexing systems in reducing cabling cost and complexity in nuclear power stations

    International Nuclear Information System (INIS)

    Stirling, A.J.; L'Archeveque, J.V.R.

    1977-03-01

    Control and instrumentation cabling accounts for nearly 1% of the capital cost of a CANDU generating station. This study of cabling requirements, methods and costs for nuclear reactors, shows that efficient design and scale economies make CANDU wiring costs (per field point) among the lowest for comparable applications. Although attractive in other reactors, commercially available remote multiplexing systems are not, as yet, cost effective for general use in CANDU stations. The report, with its comprehensive tabulation of remote multiplexing equipment, and analysis of cabling procedures describes an approach for re-evaluating the tradeoff between remote multiplexing and conventional wiring as conditions change. (author)

  6. Monitoring for shaft cracks on reactor recirculation pumps

    International Nuclear Information System (INIS)

    Kowal, M.G.; O'Brien, J.T. Jr.

    1989-01-01

    The article discusses the vibration characteristics associated with a boiling water reactor (BWR) recirculation pump. It also describes the application of diagnostic techniques and shaft crack theory to an on-line diagnostic monitoring system for reactor recirculation pumps employed at Philadelphia Electric Company's Peach Bottom Atomic Power Station. Specific emphasis is placed on the unique monitoring techniques associated with these variable speed vertical pumps

  7. SOLASE: a conceptual laser fusion reactor design

    International Nuclear Information System (INIS)

    Conn, R.W.; Abdel-Khalik, S.I.; Moses, G.A.

    1977-12-01

    The SOLASE conceptual laser fusion reactor has been designed to elucidate the technological problems posed by inertial confinement fusion ractors. This report contains a detailed description of all aspects of the study including the physics of pellet implosion and burn, optics and target illumination, last mirror design, laser system analysis, cavity design, pellet fabrication and delivery, vacuum system requirements, blanket design, thermal hydraulics, tritium analysis, neutronics calculations, radiation effects, stress analysis, shield design, reactor and plant building layout, maintenance procedures, and power cycle design. The reactor is designed as a 1000 MW/sub e/ unit for central station electric power generation

  8. Site of the First Spanish Nuclear Power Stations; Los Emplazamientos de las Primeras Centrales Nucleares Espanolas

    Energy Technology Data Exchange (ETDEWEB)

    Pascual, F.; Alonso, A.; Norena, S.; Sevilla, A. [Junta de Energia Nuclear, Madrid (Spain)

    1967-09-15

    The authors analyse and describe the sites of three Spanish nuclear power stations: the Zorita station (153 M W (e )) with a pressurized water reactor and single containment; the Santa Marfa de Garofia station (380 MW (e)), with a boiling water reactor and containment by steam condensation; and the Vandellos station (480 MW(e)), with a graphite-moderated gas-cooled reactor and integrated design of the EDF-4 type. The first two are located in the interior of the country and the third on the Mediterranean coast. The paper discusses the normal criteria and the safety considerations governing the choice of site, and points out the influence of Spanish orography on the transport of heavy equipment and hence its repercussions on the selection of power station sites. Reference is made to the experience acquired in transporting equipment for the Z-orita plant, and an analysis of the practical difficulties encountered in applying particular safety standards to the sites of stations of different types and designs is included. As the type of reactor and its containment system affect the practical value of applying particular standards which, moreover, have to be adapted to the special features of each country, safety standards for assessing power station sites should be applied in an appropriate and flexible manner. The paper describes the geological and meteorological features of the three sites and summarizes the studies carried out in these fields. It refers particularly to the hydrological studies carried out at Zorita and Santa Maria de Garofia and describes the weather stations set up at both sites, the diffusion experiments with neutcal-buoyancy balloons at Santa Maria de Garofia, and the results of these investigations. (author) [Spanish] Se analizan y describen los emplazamientos de tres centrales nucleares espanolas: la central de Zorita, de 153 MW(e), con reactor de agua a presion y sistema de contencion simple; la central de Santa Maria de Garofia, de 380 MW

  9. The Chernobyl reactor accident

    International Nuclear Information System (INIS)

    1986-01-01

    The documentation abstracted contains a complete survey of the broadcasts transmitted by the Russian wire service of the Deutsche Welle radio station between April 28 and Mai 15, 1986 on the occasion of the Chernobyl reactor accident. Access is given to extracts of the remarkable eastern and western echoes on the broadcasts of the Deutsche Welle. (HP) [de

  10. The training and research reactor of the Zittau Technical College

    International Nuclear Information System (INIS)

    Ackermann, G.; Hampel, R.; Konschak, K.

    1979-01-01

    The light-water moderated training and research reactor of the Zittau Technical College, which has been put into operation 1 July 1979, is described. Having a power of 10 MW, it is provided for education of students and advanced training of nuclear power plant staff members. High inherent nuclear safety and economy of operation are achieved by appropriate design of the reactor core and the use of fresh fuel elements provided for the 10-MW research reactor at the Rossendorf Central Institute for Nucleear Research for one year on a loan basis. Further characteristics of the reactor are easy accessibility of the core interior for in-core studies, sufficient external experimental channels, and a control and protection system meeting the requirements of teaching operation. The installed technological and dosimetric devices not only ensure reliable operation of the reactor, but also extend the potentialities of experimental work and education that is reported in detail. The principles on which the training programs are based are explained in the light of some examples. The training reactor is assumed to serve for providing basic knowledge about processes in nuclear power stations with pressurized water reactors. Where the behaviour of a nuclear power station cannot sufficiently be demonstrated by the training reactor, a reasonable completion of practical training at special simulation models and experimental facilities of the Technical College and at the nuclear power plant simulator of the Rheinsberg nuclear power plant school has been conceived. (author)

  11. Reactor coolant pump transportation incident

    International Nuclear Information System (INIS)

    Noce, D.

    1992-01-01

    This paper reports on an incident, which occurred on August 27, 1991, in which a Reactor Coolant Pump motor en route from Surry Power Station to Westinghouse repair facilities struck the overpass at the junction of Interstate 64 and Jefferson Avenue in Newport News, Virginia. The transport container that housed the reactor coolant pump motor failed to clear the overpass. The force of the impact dislodged the container and motor from the truck bed, and it landed on the acceleration land and road shoulder. Upon impact, the container broke open and exposed the reactor coolant pump motor. Incidental radioactively contaminated water that remained in the motor coolers drained onto the road, contaminating the aggregate as well as the underlying gravel

  12. Ontario Hydro Pickering Generating Station fuel handling system performance

    International Nuclear Information System (INIS)

    Underhill, H.J.

    1986-01-01

    The report briefly describes the Pickering Nuclear Generating Station (PNGS) on-power fuel handling system and refuelling cycle. Lifetime performance parameters of the fuelling system are presented, including station incapability charged to the fuel handling system, cost of operating and maintenance, dose expenditure, events causing system unavailability, maintenance and refuelling strategy. It is concluded that the 'CANDU' on-power fuelling system, by consistently contributing less than 1% to the PNGS incapability, has been credited with a 6 to 20% increase in reactor capacity factor, compared to off-power fuelling schemes. (author)

  13. The main safety problems encountered at Creys-Malville power station

    International Nuclear Information System (INIS)

    Saitcevsky, Boris

    1980-01-01

    The 1200 MW. Creys-Malville nuclear power station, situated on the upper Rhone river, in the Isere department, is the largest unit in construction of the fast neutrons sodium-cooled reactor channel. Realized within a European framework, this power station of a specific character, requires special safety dispositions, owing to the utilization of sodium. Safety rests on a thorough preventive system, particularly at the level of the sodium circuits, the shut-down system and the devices for the evacuation of residual power [fr

  14. Socio-economic impacts of nuclear generating stations: Nine Mile Point and Fitzpatrick case study

    International Nuclear Information System (INIS)

    Branch, K.; Cochran, R.; Meale, R.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Nine Mile Point and Fitzpatrick nuclear power stations. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of the construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  15. Core power distribution measurement and data processing in Daya Bay Nuclear Power Station

    International Nuclear Information System (INIS)

    Zhang Hong

    1997-01-01

    For the first time in China, Daya Bay Nuclear Power Station applied the advanced technology of worldwide commercial pressurized reactors to the in-core detectors, the leading excore six-chamber instrumentation for precise axial power distribution, and the related data processing. Described in this article are the neutron flux measurement in Daya Bay Nuclear Power Station, and the detailed data processing

  16. Overall strategy of Creys Malville power station dismantling

    International Nuclear Information System (INIS)

    Alphonse, P.

    2002-01-01

    The power station was stopped by a government decision following the elections in 1997. This shutdown was then made official by a letter dated April 1998 and the decree of December 1998. This was a non-technical shutdown and as such had not been envisaged; there has been no early warning. Current dismantling strategy: The studies leading to shutdown and then dismantling were engaged in 1998 based on a scenario with a status corresponding to IAEA level 2 until 2046. In 2001, EDF management made the decision to dismantle all the first generation power stations and Creys Malville between now and 2025. It should be noted that the presence of strongly irradiated stellite in the Creys Malville reactor would still require remote systems for working in the reactor block after 2046. The sequence of operations dictated by the dismantling strategy is as follows: eliminate the risks as soon as possible and in particular the risk related to the sodium, 3300 tonnes of which is kept in liquid form in the reactor vessel; dismantle the most active parts which are too radioactive to be sent to the existing or planned storage centres. This may lead to on-site storage to allow decay to occur before sending to a storage centre; planning of the work interventions in order to limit the costs

  17. Ten years of KRB Gundremmingen demonstration power station

    International Nuclear Information System (INIS)

    Facius, H. von; Ettemeyer, R.

    1976-01-01

    In August 1976 the first large nuclear power station in the Federal Republic, the KRB Gundremmingen plant with a net power of 237 MWe, has been in operation ten years. The construction of KRB as a demonstration plant was a major step forward on the way to the economic utilization of nuclear power for German utilities. Design and operation of the plant have decisively influenced the further development of the technology of light water reactors in the Federal Republic. Unlike the Kahl Experimental Nuclear Power Station (VAK), which was a test facility designed to generate experience and to train personnel, the decision to build KRB from the outset was conditional upon the fulfillment of economic criteria. Here are some of the aspects in which KRB has greatly influenced the development of nuclear power station technology: first application of internal steam-water separation instead of a steam drum with a water content of the steam of less than 1%; construction of a reactor buildung with all the necessary safety factors; solution of the corrosion and erosion problems linked with the use of a saturated steam turbine; special measures taken to prevent the turbine from speeding up due to post-evaporation effects after shutdown. Detailed comments are devoted to the subjects of availability, causes of failure and repair work. (orig.) [de

  18. Management of radioactive wastes at power reactor sites in India

    International Nuclear Information System (INIS)

    Amalraj, R.V.; Balu, K.

    Indian nuclear power programme, at the present stage, is based on natural uranium fuelled heavy water moderated CANDU type reactors except for the first nuclear power station consisting of two units of enriched uranium fuelled, light water moderated, BWR type of reactors. Some of the salient aspects of radioactive waste management at power reactor sites in India are discussed. Brief reviews are presented on treatment of wastes, their disposal and environmental aspects. Indian experience in power reactor waste management is also summarised identifying some of the areas needing further work. (auth.)

  19. Loviisa Power Station - final disposal of reactor waste

    International Nuclear Information System (INIS)

    Vaajasaari, Marja

    1987-01-01

    This report is based on the earlier published results of research into the properties and function of the candidate backfill materials. The results of the backfill material research, and the sealing concepts presented in the literature have been evaluatedand applied to sealing the Loviisa Reactor Waste Repository taking into consideration the local rock and groundwater conditions. It is emphasised that the applicability of the presented backfill materials and plugs to repository sealing must still be carefully evaluated on the basis of detailed studies and the local environment. 24 refs

  20. Development of the Arctic radionuclide monitoring station

    International Nuclear Information System (INIS)

    King, S.E.; Phillips, G.W.; Aakenes, U.R.

    1996-01-01

    In recent years, the world has learned about the dumping of nuclear reactors and other waste into the Arctic seas by the former Soviet Union. Most of the information on the present levels of radioactivity in the region has been obtained by oceanographic expeditions conducted during the brief Arctic summers. Year-round monitoring of the movement of radio-activity during dynamic seasonal and episodic chances is hampered by the difficulties caused by sea ice, logistics and communication constraints associated with deployment and maintenance of monitoring equipment in this remote region. We have designed an autonomous station to measure the benthic gamma-ray emitting radioactivity for periods of at least one year. The station is capable of detecting a 30 Bq/m 3 increase in the 137 Cs activity in a 24 hour period. After a year-long deployment, the station releases its anchor and rises to the surface to transmit the accumulated spectra and oceanographic data via an Argos satellite link. The design and performance characteristics of the prototype station will be discussed

  1. Development of the Arctic radionuclide monitoring station

    Science.gov (United States)

    King, S. E.; Aakenes, U. R.; McCoy, K.; Phillips, G. W.

    1997-06-01

    The world has learned about the dumping of nuclear reactors and other waste into the Arctic seas by the former Soviet Union. Most of the information on the present levels of radioactivity in the region has been obtained by oceanographic expeditions conducted during the brief Arctic summers. Year-round monitoring of the movement of radioactivity during dynamic seasonal and episodic changes is hampered by the difficulties caused by sea ice, logistics and communication constraints associated with deployment and maintenance of monitoring equipment in this remote region. The authors have designed an autonomous station to measure the benthic gamma-ray emitting radioactivity for periods of at least one year. The station is capable of detecting a 30 Bq/m/sup 3/ increase in the /sup 137/Cs activity in a 24 hour period. After a year-long deployment, the station releases its anchor and rises to the surface to transmit the accumulated spectra and oceanographic data via an Argos satellite link. The design and performance characteristics of the prototype station are discussed.

  2. Advanced materials: The key to attractive magnetic fusion power reactors

    International Nuclear Information System (INIS)

    Bloom, E.E.

    1992-01-01

    Fusion is one of the most attractive central station power sources from the viewpoint of potential safety and environmental impact characteristics. Studies also indicate that fusion can be economically competitive with other options such as fission reactors and fossil-fired power stations. However, to achieve this triad of characteristics we must develop advanced materials with properties tailored for performance in the various fusion reactor systems. This paper discusses the desired characteristics of materials and the status of materials technology in four critical areas: (1) structural material for the first wail and blanket (FWB), (2) plasma-facing materials, (3) materials for superconducting magnets, and (4) ceramics for electrical and structural applications

  3. Advanced materials - the key to attractive magnetic fusion power reactors

    International Nuclear Information System (INIS)

    Bloom, E.E.

    1992-01-01

    Fusion is one of the most attractive central station power sources from the viewpoint of potential safety and environmental impact characteristics. Studies also indicate that fusion can be economically competitive with other options such as fission reactors and fossil-fired power stations. However, to achieve this triad of characteristics we must develop advanced materials with properties tailored for performance in the various fusion reactor systems. This paper discusses the desired characteristics of materials and the status of materials technology in four critical areas: (1) structural materials for the first wall and blanket (FWB), (2) plasmafacing materials, (3) materials for superconducting magnets, and (4) ceramics for electrical and structural applications. (author)

  4. Shippingport Station decommissioning project overview

    International Nuclear Information System (INIS)

    Schreiber, J.J.

    1985-01-01

    The U.S. Department of Energy is in the process of decommissioning the Shippingport Atomic Power Station located on the Ohio River, 30 miles northwest of Pittsburgh, Pennsylvania. The Shippingport Station is the first commercial size nuclear power plant to undergo decommissioning in the United Staes. The plant is located on approximately 7 acres of land owned by the Duquesne Light Company (DLC) and leased to the U.S. Government. DLC operates two nuclear power plants, Beaver Valley 1 and 2, located immediately adjacent to the site and the Bruce Mansfield coal-fired power plant is also within the immediate area. The Station was shutdown in October, 1982. Defueling operations began in 1983 and were completed by September, 1984. The Shippingport Station consists of a 275' x 60' fuel handling building containing the reactor containment chamber, the service building, the turbine building, the radioactive waste processing building, the administration building and other smaller support buildings. The Station has four coolant loops and most of the containment structures are located below grade. Structures owned by the U.S. Government including the fuel handling building, service building, contaminated equipment room, the boiler chambers, the radioactive waste processing building and the decontamination and laydown buildings will be dismantled and removed to 3 feet below grade. The area will then be filled with clean soil and graded. The turbine building, testing and training building and the administration building are owned by DLC and will remain

  5. Flow and pressure profiles for the primary heat transport system of Rajasthan Atomic Power Station for the operation with few isolated reactor channels near the end shield cracks

    Energy Technology Data Exchange (ETDEWEB)

    Gaikwad, A J; Chaki, S K; Sehgal, R L; Venkat Raj, V [Reactor Safety Division, Bhabha Atomic Research Centre, Mumbai (India)

    1994-06-01

    The RAPS (Rajasthan Atomic Power Station) unit-1 is now operating at reduced power due to the removal of fifteen fuel channels for repair of south end shield cracks. The power level is restricted to 50% of the full power capacity as a precautionary measure. The relative difference that operation at 50% power and higher power would make to the end shield structure is being currently analysed with a view to operate this reactor at higher power levels. As a prerequisite, a detailed thermal hydraulic analysis is essential to assess the effect of reactor operation with isolated channels on the primary heat transport (PHT) system pressure, flow, temperature. The adequacy of the existing trip set points for the plant operation under this mode is also required to be assessed. In the present study, analysis of the PHT system has been carried out to determine the flow and pressure profiles for the RAPS heat transport system for operation of the reactor with isolated channels. (author). 5 refs., 1 fig., 1 tab.

  6. Reactor core and passive safety systems descriptions of a next generation pressure tube reactor - mechanical aspects

    Energy Technology Data Exchange (ETDEWEB)

    Yetisir, M.; Gaudet, M.; Rhodes, D.; Hamilton, H.; Pencer, J. [Atomic Energy of Canada Limited, Chalk River, ON (Canada)

    2014-07-01

    Canada has been developing a channel-type supercritical water-cooled nuclear reactor concept, often called the Canadian SCWR. The objective of this reactor concept is to meet the technology goals of the Generation IV International Forum (GIF) for the next generation nuclear reactor development, which include enhanced safety features (inherent safe operation and deploying passive safety features), improved resource utilization, sustainable fuel cycle, and greater proliferation resistance than Generation III nuclear reactors. The Canadian SCWR core concept consists of a high-pressure inlet plenum, a separate low-pressure heavy water moderator contained in a calandria vessel, and 336 pressure tubes surrounded by the moderator. The reactor uses supercritical water as a coolant, and a direct steam power cycle to generate electricity. The reactor concept incorporates advanced safety features such as passive core cooling, long-term decay heat rejection to the environment and fuel melt prevention via passive moderator cooling. These features significantly reduce core damage frequency relative to existing nuclear reactors. This paper presents a description of the design concepts for the Canadian SCWR core, reactor building layout and the plant layout. Passive safety concepts are also described that address containment and core cooling following a loss-of coolant accident, as well as long term reactor heat removal at station blackout conditions. (author)

  7. Steam turbines for nuclear power stations in Czechoslovakia and their use for district heating

    International Nuclear Information System (INIS)

    Drahy, J.

    1989-01-01

    The first generation of nuclear power stations in Czechoslavakia is equipped with 440 MW e pressurized water reactors. Each reactor supplies two 220 MW, 3000 rpm condensing type turbosets operating with saturated steam. After the completion of heating water piping systems, all of the 24 units of 220 MW in Czechoslovak nuclear power stations will be operated as dual purpose units, delivering both electricity and heat. At the present time, second-generation nuclear power stations, with 1000 MW e PWRs, are being built. Each such plant is equipped with one 1000 MW full-speed saturated steam turbine. The turbine is so designed as to permit the extraction of steam corresponding to the following quantities of heat: 893 MJ/s with three-stage water heating (150/60 0 C); and 570 MJ/s with two-stage water heating (120/60 0 C). The steam is taken from uncontrolled steam extraction points. (author)

  8. Damage of reactor recirculation pump of No.3 plant in Fukushima No.2 Nuclear Power Station, Tokyo Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1990-01-01

    No.3 plant in Fukushima No.2 Nuclear Power Station is a BWR plant with the rated output of 1100 MW, and as for the damage of its reactor recirculation pump, the investigation of the cause and the examination of countermeasures are advanced by the special committee. It is presumed that the submerged bearing ring of this pump caused the fatigue fracture due to the insufficient penetration in the fillet-welded part. The ring broke into pieces, and the main disk of the impeller was broken by the wear due to the pieces. Further, the damage of washers and the falling-off of bolts occurred. The metallic particles generated by wear were about 30 kg, and it is presumed that several kg of them adhered to fuel. Hereafter, the investigation of the cause will be continued, and the countermeasures for preventing the recurrence are examined. On January 1, 1989, the vibration of the pump increased, and the alarm was issued. However, the operation was continued carefully. On January 6, the vibration increased again, and on January 7, the reactor was stopped. The third regular inspection was begun on the same day, and the damage of the pump was found. (K.I.)

  9. Annexes to the lecture on reactor protection system including engineered features actuation system

    International Nuclear Information System (INIS)

    Palmaers, W.

    1982-01-01

    The present paper deals with the fundamentals for a reactor protection system and discusses the following topics: - System lay-out - Analog measured data acquisition - Analog measured data processing - Limit value generation and logical gating - Procesing of the reactor protection actuation signals - Decoupling of the reactor protection system - Mechanical lay-out - Monitoring system and - Emergency control station. (orig./RW)

  10. HTGR type reactors for the heat market

    International Nuclear Information System (INIS)

    Oesterwind, D.

    1981-01-01

    Information about the standard of development of the HTGR type reactor are followed by an assessment of its utilization on the heat market. The utilization of HTGR type reactors is considered suitable for the production of synthesis gas, district heat, and industrial process heat. A comparison with a pit coal power station shows the economy of the HTGR. Finally, some aspects of introducing new technologies into the market, i.e. small plants in particular are investigated. (UA) [de

  11. Dismantling the nuclear research reactor Thetis

    Energy Technology Data Exchange (ETDEWEB)

    Michiels, P. [Belgoprocess, 2480 Dessel (Belgium)

    2013-07-01

    The research reactor Thetis, in service since 1967 and stopped in 2003, is part of the laboratories of the institution of nuclear science of the University of Ghent. The reactor, of the pool-type, was used as a neutron-source for the production of radio-isotopes and for activation analyses. The reactor is situated in a water pool with inner diameter of 3 m. and a depth of 7.5 m. The reactor core is situated 5.3 m under water level. Besides the reactor, the pool contains pneumatic loops, handling tools, graphite blocks for neutron moderation and other experimental equipment. The building houses storage rooms for fissile material and sources, a pneumatic circuit for transportation of samples, primary and secondary cooling circuits, water cleaning resin circuits, a ventilation system and other necessary devices. Because of the experimental character of the reactor, laboratories with glove boxes and other tools were needed and are included in the dismantling program. The building is in 3 levels with a crawl-space. The ground-floor contains the ventilation installation, the purification circuits with tanks, cooling circuits and pneumatic transport system. On the first floor, around the reactor hall, the control-room, visiting area, end-station for pneumatic transport, waste-storage room, fuel storage room and the labs are located. The second floor contains a few laboratories and end stations of the two high speed transfer tubes. The lowest level of the pool is situated under ground level. The reactor has been operated at a power of 150 kW and had a max operating power of 250 kW. Belgoprocess has been selected to decommission the reactor, the labs, storage halls and associated circuits to free release the building for conventional reuse and for the removal of all its internals as legal defined. Besides the dose-rate risk and contamination risk, there is also an asbestos risk of contamination. During construction of the installation, asbestos-containing materials were

  12. Development of Research Reactor Simulator and Its Application to Dynamic Test-bed

    International Nuclear Information System (INIS)

    Kwon, Kee Choon; Park, Jae Chang; Lee, Seung Wook; Bang, Dane; Bae, Sung Won

    2014-01-01

    We developed HANARO and the Jordan Research and Training Reactor (JRTR) real-time simulator for operating staff training. The main purpose of this simulator is operator training, but we modified this simulator as a dynamic test-bed to test the reactor regulating system in HANARO or JRTR before installation. The simulator configuration is divided into hardware and software. The simulator hardware consists of a host computer, 6 operator stations, a network switch, and a large display panel. The simulator software is divided into three major parts: a mathematical modeling module, which executes the plant dynamic modeling program in real-time, an instructor station module that manages user instructions, and a human machine interface (HMI) module. The developed research reactors are installed in the Korea Atomic Energy Research Institute nuclear training center for reactor operator training. To use the simulator as a dynamic test-bed, the reactor regulating system modeling software of the simulator was replaced by a hardware controller and the simulator and target controller were interfaced with a hard-wired and network-based interface

  13. Development of Research Reactor Simulator and Its Application to Dynamic Test-bed

    Energy Technology Data Exchange (ETDEWEB)

    Kwon, Kee Choon; Park, Jae Chang; Lee, Seung Wook; Bang, Dane; Bae, Sung Won [KAERI, Daejeon (Korea, Republic of)

    2014-08-15

    We developed HANARO and the Jordan Research and Training Reactor (JRTR) real-time simulator for operating staff training. The main purpose of this simulator is operator training, but we modified this simulator as a dynamic test-bed to test the reactor regulating system in HANARO or JRTR before installation. The simulator configuration is divided into hardware and software. The simulator hardware consists of a host computer, 6 operator stations, a network switch, and a large display panel. The simulator software is divided into three major parts: a mathematical modeling module, which executes the plant dynamic modeling program in real-time, an instructor station module that manages user instructions, and a human machine interface (HMI) module. The developed research reactors are installed in the Korea Atomic Energy Research Institute nuclear training center for reactor operator training. To use the simulator as a dynamic test-bed, the reactor regulating system modeling software of the simulator was replaced by a hardware controller and the simulator and target controller were interfaced with a hard-wired and network-based interface.

  14. Confirmation test on the dynamic interaction between a model reactor-building foundation and ground in the Sendai Nuclear Power Station

    International Nuclear Information System (INIS)

    Umezu, Hideo; Kisaki, Noboru; Shiota, Mutsumi

    1982-01-01

    On the site of unit 2 (planned) in the Sendai Nuclear Power Station, a model reactor-building foundation of reinforced concrete with diameter of 12 m and height of 5 m was installed. With a vibration generator, its forced vibration tests were carried out in October to December, 1980. Valuable data were able to be obtained on the dynamic interaction between the model foundation and the ground, and also the outlook for the application of theories in hard base rock was obtained. (1) The resonance frequency of the model foundation in horizontal vibration was 35 Hz in both NS and EW directions. (2) Remarkable difference was not observed in the horizontal vibration behavior between NS and EW directions, so that there is not anisotropy in the ground. (3) The model foundation was deformed nearly as a rigid body. (J.P.N.)

  15. SA silent on talk of a second nuclear station

    International Nuclear Information System (INIS)

    Waddacor, M.

    1983-01-01

    Local nuclear energy officials have either denied or will not comment on recent European reports suggesting South Africa plans to construct a second nuclear power station. The probability of South Africa building a second nuclear power plant is discussed. The recent sabotage at the Koeberg-1 reactor is also mentioned

  16. Technical evaluation report on the monitoring of electric power to the reactor protection system for the Nine Mile Point Nuclear Station, Unit 1 (Docket No. 50-220)

    International Nuclear Information System (INIS)

    Selan, J.C.

    1984-01-01

    This report documents the technical evaluation of the monitoring of electric power to the reactor protection system (RPS) at the Nine Mile Point Nuclear Station, Unit 1. The evaluation is to determine if the proposed design modification will protect the RPS from abnormal voltage and frequency conditions which could be supplied from the power supplies and will meet certain requirements set forth by the Nuclear Regulatory Commission. The proposed design modifications will protect the RPS from sustained abnormal voltage and frequency conditions from the supplying sources

  17. Measurement station for interim inspections of Lightbridge metallic fuel rods at the Halden Boiling Water Reactor

    Science.gov (United States)

    Hartmann, C.; Totemeier, A.; Holcombe, S.; Liverud, J.; Limi, M.; Hansen, J. E.; Navestad, E. AB(; )

    2018-01-01

    Lightbridge Corporation has developed a new Uranium-Zirconium based metallic fuel. The fuel rods aremanufactured via a co-extrusion process, and are characterized by their multi-lobed (cruciform-shaped) cross section. The fuel rods are also helically-twisted in the axial direction. Two experimental fuel assemblies, each containing four Lightbridge fuel rods, are scheduled to be irradiated in the Halden Boiling Water Reactor (HBWR) starting in 2018. In addition to on-line monitoring of fuel rod elongation and critical assembly conditions (e.g. power, flow rates, coolant temperatures, etc.) during the irradiation, several key parameters of the fuel will be measured out-of-core during interim inspections. An inspection measurement station for use in the irradiated fuel handling compartment at the HBWR has therefore been developed for this purpose. The multi-lobed cladding cross section combined with the spiral shape of the Lightbridge metallic fuel rods requires a high-precision guiding system to ensure good position repeatability combined with low-friction guiding. The measurement station is equipped with a combination of instruments and equipment supplied from third-party vendors and instruments and equipment developed at Institute for Energy Technology (IFE). Two sets of floating linear voltage differential transformer (LVDT) pairs are used to measure swelling and diameter changes between the lobes and the valleys over the length of the fuel rods. Eddy current probes are used to measure the thickness of oxide layers in the valleys and on the lobe tips and also to detect possible surface cracks/pores. The measurement station also accommodates gamma scans. Additionally, an eddy-current probe has been developed at IFE specifically to detect potential gaps or discontinuities in the bonding layer between the metallic fuel and the Zirconium alloy cladding. Potential gaps in the bonding layer will be hidden behind a 0.5-1.0 mm thick cladding wall. It has therefore been

  18. A review of the Italian fast reactor programme

    International Nuclear Information System (INIS)

    Pierantoni, F.; Tavoni, R.

    1984-01-01

    This review sums up the Italian situation in the field of the fast reactors on the eve of the fifth five year plan (1985-1989), in which the country undertakes to implement an important activity of research and development in the context of a greater European collaboration. Italian participation in the development of European nuclear power stations together with the completion of the PEC plant which will be used to develop a fuel element with the necessary economic and safety characteristics, remain the two principal goals of the Italian fast reactor programme. In 1983 the sum assigned by ENEA for fast reactors was about 220 billion lire of which 145 billion was for the PEC reactor

  19. Status of fast breeder reactor development in Germany

    International Nuclear Information System (INIS)

    Hueber, R.; Kathol, W.; Kempken, M.

    1991-01-01

    The KNK, the sodium cooled compact reactor is an experimental nuclear power plant of 20 MW electric power. Since 1977, it has been operated with fast reactor cores as KNK II. The KNK II/3 core was designed. The core fabrication has been largely completed. In 1990, the KNK II plant achieved a time availability of 56%. On January 8, 1991 KNK II was shut down for inspection. Since pre-nuclear commissioning was completed the Kalkar Nuclear Power Station SNR 300 has been operated in a mode similar to that of a power station. In March 1991 the financing partners decided not to prolong the standby phase because they do not think that the last construction permit and the operation permit will be issued within a definite period of time. The partners were convinced that the lack of progress in the licensing procedure was not caused by basic safety deficiencies of the project but by the way the licensing procedure was executed. The German fast breeder programme is now concentrated on contributions to the European Fast Reactor. (author)

  20. The Steam Generating Heavy Water Reactor

    International Nuclear Information System (INIS)

    Middleton, J.E.

    1975-01-01

    An account is given of the SGHWR, the prototype of which was built by the United Kingdom Atomic Energy Authority at Winfrith, under the following headings: Introduction; origin of the SGHWR concept; conceptual design (choice of reactor type, steam cycle, reactor coolant system, nuclear behaviour, fuel design, core design, and protective, auxiliary and containment systems); operation and control (integrity of core cooling, reactivity control, power trimming, long term reactivity control, xenon override, load following, power shaping, spatial stability control, void coefficient); protective systems (breached coolant circuit trip, intact coolant circuits trip, power set-back trip); dynamic characteristics; reactor control; station control (decoupled control system, coupled control system, rate of response); Winfrith prototype (design and safety philosophy, conceptual features and parameters, reactor coolant system, protective systems, emergency core cooling, core structure, fuel design, vented containment). (U.K.)

  1. Wet steam turbines for CANDU-Reactors

    International Nuclear Information System (INIS)

    Westmacott, C.H.L.

    1977-01-01

    The technical characteristics of 4 wet steam turbine aggregates used in the Pickering nuclear power station are reported on along with operational experience. So far, the general experience was positive. Furthermore, plans are mentioned to use this type of turbines in other CANDU reactors. (UA) [de

  2. AECB staff annual assessment of the Pickering A and B Nuclear Generating Stations for the year 1996

    International Nuclear Information System (INIS)

    1997-06-01

    The Atomic Energy Control Board is the independent federal agency that controls all nuclear activities in Canada. A major use of nuclear energy in Canada is electricity production. The AECB assesses every station's performance against legal requirements, including the conditions in the operating licence. Each station is inspected and all aspects of the station's operation and management is reviewed. This report is the AECB staff assessment of reactor safety at the Pickering A and B Generating Stations for 1996. PNGS-A and PNGS-B operated safely during 1996. Although the risk to the workers and the public is low, major safety related changes are necessary at the stations and the sustainability of those changes needs to be demonstrated. Improvement is needed by Ontario Hydro in meeting the time limits for reporting reportable events. Ontario Hydro's follow up to events and causal factor analyses continue to need improvements. Improvements are needed to operational safety and reactor maintenance at both A and B. There are signs of improvement through Ontario Hydro's plan for recovery, and in station management changes. There also appears to be commitment to safety expressed at the highest level of the utility

  3. Capital cost: gas cooled fast reactor plant

    International Nuclear Information System (INIS)

    1977-09-01

    The results of an investment cost study for a 900 MW(e) GCFR central station power plant are presented. The capital cost estimate arrived at is based on 1976 prices and a conceptual design only, not a mature reactor design

  4. The decommissioning of nuclear power stations. France and the American experience

    International Nuclear Information System (INIS)

    Tonnac, Alain de; Perves, Jean-Pierre

    2013-01-01

    After having noticed that many electronuclear reactors have already been stopped, and that some research reactors have just been dismantled in Grenoble by the CEA, and evoked the main involved actors (ASN, IRSN, ANDRA), some characteristics of the French situation are outlined: the strategy adopted by EDF for a fast dismantling process, the long legal delays for stopping, dismantling and downgrading of sites, the absence of waste radioactivity release thresholds, and the responsibility of operators for dismantling operations. The main steps of a station dismantling are indicated and discussed: end of exploitation; steps of deconstruction (evacuation of big components, elimination of building radioactivity, building destruction, site partial or total reconversion). The French authorization process is briefly commented. Then, the American experience and situation is commented in terms of number of concerned sites, of site situation, but also in terms of organisation and selected technologies. Critical steps are outlined as well as improvements obtained in terms of exposure, of waste volumes, of effluent filtration capacities, and of cutting methods. The next part proposes an overview of the situation or steps of decommissioning in France for different sites: the Chooz PWR, the fleet of first generation reactors, graphite gas reactors, the Brennilis power station and Super Phenix in Creys Malville. Costs and delays are briefly evoked for the USA as well as for France

  5. Thermalydraulic processes in the reactor coolant system of a BWR under severe accident conditions

    International Nuclear Information System (INIS)

    Hodge, S.A.

    1990-01-01

    Boiling water reactors (BWRs) incorporate many unique structural features that make their expected response under severe accident conditions very different from that predicted in the case of pressurized water reactor accident sequences. Automatic main steam isolation valve (MIV) closure as the vessel water level approaches the top of the core would cause reactor vessel isolation while automatic recirculation pump trip would limit the in-vessel flows to those characteristic of natural circulation (as disturbed by vessel relief valve actuation). This paper provides a discussion of the BWR control blade, channel box, core plate, control rod guide tube, and reactor vessel safety relief valve (SRV) configuration and the effects of these structural components upon thermal hydraulic processes within the reactor vessel under severe accident conditions. The dominant BWR severe accident sequences as determined by probabilistic risk assessment are described and the expected timing of events for the unmitigated short-term station blackout severe accident sequence at the Peach Bottom atomic power station is presented

  6. Regulatory aspects of nuclear reactor decommissioning

    International Nuclear Information System (INIS)

    Ross, W.M.

    1990-01-01

    The paper discusses the regulatory aspects of decommissioning commercial nuclear power stations in the UK. The way in which the relevant legislation has been used for the first time in dealing with the early stages of decommissioning commercial nuclear reactor is described. International requirements and how they infit with the UK system are also covered. The discussion focusses on the changes which have been required, under the Nuclear Site Licence, to ensure that the licensee carries out of work of reactor decommissioning in a safe and controlled manner. (Author)

  7. Shippingport operations with the Light Water Breeder Reactor core. (LWBR Development Program)

    International Nuclear Information System (INIS)

    Budd, W.A.

    1986-03-01

    This report describes the operation of the Shippingport Atomic Power Station during the LWBR (Light Water Breeder Reactor) Core lifetime. It also summarizes the plant-oriented operations during the period preceding LWBR startup, which include the defueling of The Pressurized Water Reactor Core 2 (PWR-2) and the installation of the LWBR Core, and the operations associated with the defueling of LWBR. The intent of this report is to examine LWBR experience in retrospect and present pertinent and significant aspects of LWBR operations that relate primarily to the nuclear portion of the Station. The nonnuclear portion of the Station is discussed only as it relates to overall plant operation or to unusual problems which result from the use of conventional equipment in radioactive environments. 30 refs., 69 figs., 27 tabs

  8. Hinkley Point 'C' power station public inquiry: statement of case

    International Nuclear Information System (INIS)

    1988-08-01

    This Statement of Case contains full particulars of the case which the Central Electricity Generating Board (CEGB) proposes to put forward at the Hinkley Point ''C'' Inquiry. It relates to the planning application made by the CEGB for the construction of a 1200 MW Pressurized Water Reactor (PWR) power station at Hinkley Point in the United Kingdom, adjacent to an existing nuclear power station. The inquiry will consider economic, safety, environmental and planning matters relevant to the application and the implications for agriculture and local amenities of re-aligning two power transmission lines. The Statement contains submissions on the following matters: Topic 1 The Requirement for the Station; Topic 2 Safety and Design, including Radioactive Discharges; Topic 3 The On-Site Management of Radioactive Waste and Decommissioning of the Station; Topic 4 Emergency Arrangements; Topic 5 Local and Environmental Issues. (author)

  9. Lifetime management of Magnox power stations

    International Nuclear Information System (INIS)

    Smitton, C.

    1998-01-01

    Magnox Electric, which is, a subsidiary of BNFL, operates six nuclear power plants that have an average age of about 33 years. The procedures developed to maintain the plants and ensure nuclear safety in longer-term operation are reviewed. The technical limit on station lifetimes is expected to be determined by the effect of ageing on major reactor structures where replacement is impractical. Examination of the effect of ageing confirms that the stations are capable of operating to a life of at least 40 years. The economic factors affecting operation are reviewed, recognising the need to sell electricity in a competitive market. Recently Magnox Electric and BNFL have merged and all plant supporting Magnox operations are now within a single integrated company that will provide further opportunities for improved efficiency. (author)

  10. Method for supervising and controlling the charging and discharging operations of fuel in a nuclear reactor and apparatus for applying this method

    International Nuclear Information System (INIS)

    Plumier, M.

    1985-01-01

    Method is described for supervising and controlling the charging and discharging operations, in nuclear fuel element assemblies, of a core of a reactor, of a reactor pond and of a decontamination pond, by means of a charging machine equipped with a telescopic mast the end of which is provided with a gripping head with grippers, serving the reactor and the reactor pond in which there is arranged a buffer storage rack, a fixed depositing station and a mobile depositing station, and by means of a charging machine equipped with a telescopic mast the end of which is provided with a gripping head with grippers, serving the decontamination pond containing storage racks, and by means of a transfer device providing communication between the reactor pond and the decontamination pond, characterised in that the initial position in each assembly in the core of the reactor, in the storage racks and possibly in the buffer rack is recorded, in that the position of the charging machine and/or of the handling machine and/or of the transfer device and/or of the mobile depositing station is recorded, likewise the identification of the assembly at the time of each taking up of an assembly and/or at the time of each placing of an assembly in the core of the reactor, in the buffer rack in the transfer basket, in the storage rack, in the fixed depositing station and in the mobile depositing station, in that the command and control signals for each manipulation required of the charging machine, of the handling machine, of the transfer device and of any other mobile station are compared with the recorded signals of a preestablished charging sequence. 5 refs., 4 figs

  11. Human-factor operating concept for Borssele Nuclear Power Station

    International Nuclear Information System (INIS)

    Wieman, J.L.

    1995-01-01

    The safety level in the operation of a reactor is determined basically by human beings. The Borssele Nuclear Power Station has carried out measures for improving the man-machine interface through training and operating instructions for the shift personnel. The retrofitting of control technology relevant to safety engineering should avoid operating instructions which can cause potential failures. A safety study has shown that the remaining risk following all retrofitting measures remains dependent to the extent of 80% on human factors and that human factors as a whole have a positive effect on reactor safety. (orig.) [de

  12. Socioeconomic impacts of nuclear generating stations: Oconee case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Flynn, J.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Oconee nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  13. Socioeconomic impacts of nuclear generating stations: Surry case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Flynn, J.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Surry nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  14. Operational and reliability experience with reactor instrumentation

    International Nuclear Information System (INIS)

    Dixon, F.; Gow, R.S.

    1978-01-01

    In the last 15 years the CEGB has experienced progressive plant development, integration and changes in operating regime through nine nuclear (gas-cooled reactor) power stations with corresponding instrumentation advances leading towards more refined centralized control. Operation and reliability experience with reactor instrumentation is reported in this paper with reference to the progressive changes related to the early magnox, late magnox and AGR periods. Data on instrumentation reliability in terms of reactor forced outages are presented and show that the instrumentation contributions to loss of generating plant availability are small. Reactor safety circuits, neutron flux and temperature measurements, gas analysis and vibration monitoring are discussed. In reviewing the reactor instrumentation the emphasis is on reporting recent experience, particularly on AGR equipment, but overall performance and changes to magnox equipment are included so that some appreciation can be obtained of instrumentation requirements with respect to plant lifetimes. (author)

  15. Modular high-temperature reactor launched (and wallchart)

    International Nuclear Information System (INIS)

    Steinwarz, W.

    1987-01-01

    In view of the need for a technically unsophisticated, safe and economic reactor system, the KWU group has integrated the experience gained from German light-water reactor engineering and from successful operation of the German AVR experimental high-temperature reactor into the development of the High-Temperature Reactor (HTR)-module. The main components are illustrated and explained and technical data for the HTR-module is given. Safety is also considered. This includes graphs of core heat-up temperature for pebble-bed HTR and a graph of the temperature load of the fuel elements. The operation, control and applications are considered. The latter includes use in combined heat and power generation and community heating. Feasibility studies have shown that the HTR-module is cheaper, comparatively, than coal-fired power stations. (U.K.)

  16. Present status of research reactor and future prospects

    International Nuclear Information System (INIS)

    Nakajima, Ken

    2013-01-01

    Research reactors have been playing an important role in the research and development of the various fields, such as physics, chemistry, biology, engineering, agriculture, medicine, etc. as well as human resource development. However, the most of them are older than 40 years, and the ageing management is an important issue. In Japan, only two research reactors are operational after the Great East Japan Earthquake in 2011. JAEA's reactors suffered from the quake and they are under inspections. Kyoto University Research Reactor, one of the operational reactors, has been widely used for research and human resource development, and the additional safety measures against the station blackout were installed. Besides the affect of the quake, the disposal or treatment of spent fuel becomes an inevitable problem for research reactors. The way of spent fuel disposal or treatment should be determined with the nation-wide and/or international coalition. (author)

  17. Trade study for kWe class space reactors

    Science.gov (United States)

    Bost, Donald S.

    Recent interest by NASA and other government agencies in space reactor power systems with power levels in the 1 to 100 kWe range has prompted a review of earlier space reactor programs, as well as the ongoing SP-100 program, to identify a system that will best fulfill their needs. The candidate reactor types that were reviewed are listed. They are categorized according to the method of heat removal. The five types are: conduction cooled, heat pipe cooled, liquid metal cooled, in-core thermionic and gas cooled. The UZrH moderated reactor coupled with an organic Rankine cycle power conversion system provides an attractive system for multikilowatt, long lived missions. The reactor requires a minimum development because a similar reactor has already flown and the ORC is being developed for use in the Dynamic Isotope Power System (DIPS) and on the Space Station.

  18. Training of power station staff

    International Nuclear Information System (INIS)

    Dusserre, J.

    1993-01-01

    ELECTRICITE DE FRANCE currently operates 51 generating stations with 900 and 1300 MW Pressurized Water Reactors while, only 15 years ago, France possessed only a very small number of such stations. It was therefore vital to set up a major training organization to produce staff capable of starting, controlling and maintaining these facilities with a constant eye to improving quality and safety. Operator and maintenance staff training is based on highly-structured training plans designed to match both the post to be filled and the qualifications possessed by the person who is to fill it. It was essential to set up suitable high-performance training resources to handle this fast growth in staff. These resources are constantly being developed and allow EDF to make steady progress in a large number of areas, varying from the effects of human factors to the procedures to be followed during an accident

  19. Experiences of operation for Ikata Nuclear Power Station

    International Nuclear Information System (INIS)

    Kashimoto, Shigeyuki

    1979-01-01

    No. 1 plant in the Ikata Nuclear Power Station, Shikoku Electric Power Co., Inc., is a two-loop PWR unit with electric output of 566 MW, and it began the commercial operation on September 30, 1977, as the first nuclear power station in Shikoku. It is the 13th LWR and 7th PWR in Japan. The period of construction was 52 months since it had been started in June, 1973. During the period, it became the object of the first administrative litigation to seek the cancellation of permission to install the reactor, and it was subjected to the influence of the violent economical variation due to the oil shock, but it was completed as scheduled. After the start of operation, it continued the satisfactory operation, and generated about 2.35 billion KWh for 4300 operation hours. It achieved the rate of utilization of 96.7%. Since March 28, 1978, the first periodical inspection was carried out, and abnormality was not found in the reactor, the steam generator and the fuel at all. The period of inspection was 79 days and shorter than expected. The commercial operation was started again on June 14. The outline of the Ikata Nuclear Power Station, its state of operation, and the periodical inspection are reported. Very good results were able to be reported on the operation for one year, thanks to the valuable experiences offered by other electric power companies. (Kako, I.)

  20. The ESKOM pebble bed modular reactor

    International Nuclear Information System (INIS)

    Gittus, J.H.

    1999-01-01

    An audit has been made of the design, construction, safety, economics and marketability of the ESKOM pebble bed modular reactor (PBMR). In this paper that audit is briefly summarized. The principal conclusions of the audit are as follows. The design is sound. It is a logical development of the designs proposed for other, modern, high-temperature gas-cooled reactors. More than 80% of the cost of constructing and commissioning a series of PBMRs would be spent in South Africa. The PBMR is much safer than existing nuclear power reactors and for many practical purposes it may be treated as a conventional chemical plant. The PBMR is economically competitive with thermal power stations. There is a substantial global market for the PBMR. (author)

  1. Darlington Station outage - a maintenance perspective

    International Nuclear Information System (INIS)

    Plourde, J.; Marczak, J.; Stone, M.; Myers, R.; Sutton, K.

    1997-01-01

    Ontario Hydro's Darlington Nuclear Generating Station (4x881MW(e)net) has carried out its first station outage since full commercial operation. The outage presented challenges to the organization in terms of outage planning, support, management, and safe execution within the constraints of schedule, budget and resources. This paper will focus on the success of the outage maintenance program, identifying the major work programs - a vacuum structure and containment outage, an emergency service water system outage, an emergency coolant injection system outage, intake channel inspections, low pressure service water inspections, and significant outage maintenance work on each of the four reactor units. Planning for the outage was initiated early in anticipation of this important milestone in the station's life. Detailed safety reviews - nuclear, radiation, and conventional - were conducted in support of the planned maintenance program. System lineup and work protection were provided by the Station Operator work group. Work protection permitry was initiated well in advance of the outage. Station maintenance staff resources were bolstered in support of the outage to ensure program execution could be maintained within the schedule. Training programs were in place to ensure that expectations were clear and that high standards would be maintained. Materials management issues in support of maintenance activities were given high priority to ensure no delays to the planned work. Station management review and monitoring in preparation for and during the outage ensured that staff priorities remained focused. Lessons learned from the outage execution are being formalized in maintenance procedures and outage management procedures, and shared with the nuclear community. (author)

  2. Shippingport Station Decommissioning Project: Contaminated concrete removal: Topical report

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the removal of contaminated concrete from the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the decontamination activities in support of site release in the decommissioning of a nuclear power reactor. 4 refs., 8 figs., 2 tabs

  3. Distributed computer control system for reactor optimization

    International Nuclear Information System (INIS)

    Williams, A.H.

    1983-01-01

    At the Oldbury power station a prototype distributed computer control system has been installed. This system is designed to support research and development into improved reactor temperature control methods. This work will lead to the development and demonstration of new optimal control systems for improvement of plant efficiency and increase of generated output. The system can collect plant data from special test instrumentation connected to dedicated scanners and from the station's existing data processing system. The system can also, via distributed microprocessor-based interface units, make adjustments to the desired reactor channel gas exit temperatures. The existing control equipment will then adjust the height of control rods to maintain operation at these temperatures. The design of the distributed system is based on extensive experience with distributed systems for direct digital control, operator display and plant monitoring. The paper describes various aspects of this system, with particular emphasis on: (1) the hierarchal system structure; (2) the modular construction of the system to facilitate installation, commissioning and testing, and to reduce maintenance to module replacement; (3) the integration of the system into the station's existing data processing system; (4) distributed microprocessor-based interfaces to the reactor controls, with extensive security facilities implemented by hardware and software; (5) data transfer using point-to-point and bussed data links; (6) man-machine communication based on VDUs with computer input push-buttons and touch-sensitive screens; and (7) the use of a software system supporting a high-level engineer-orientated programming language, at all levels in the system, together with comprehensive data link management

  4. Treatment of opinions, etc. in the public hearing on the alteration of reactor installation (addition of Unit 2) in the Shimane Nuclear Power Station of The Chugoku Electric Power Company, Inc

    International Nuclear Information System (INIS)

    1983-01-01

    The Nuclear Safety Commission has acknowledged the governmental policy, and further decided on the treatment of the opinions expressed by the local people in the public hearing held in May, 1983, in Shimane Prefecture on the addition of Unit 2 to the Shimane Nuclear Power Station, Chugoku Electric Power Co., Inc. The NSC has directed the Committee on Examination of Reactor Safety to take into consideration the opinions in its later examination. The opinions expressed by the local people in the form of question are given as follows: siting conditions (earthquake, ground, weather, etc.), the safety design for reactor installation (general aspect, aseismatic design, core design, ECCS, the teaching of TMI accident, etc.), radioactive wastes, radiation exposure, site evaluation. (Mori, K.)

  5. Diagnosis of electric equipment at the Dalat Nuclear Research Reactor

    International Nuclear Information System (INIS)

    Nguyen Truong Sinh

    1999-01-01

    The Dalat Nuclear Research Reactor (DNRR) is a pool type of its kind in the world: Soviet-designed core and control system harmoniously integrated into the left-over infrastructure of the former American-made TRIGA MARK II reactor, which includes the reactor tank and shielding, graphite reflector, beam tubes and thermal column. The reactor is mainly used for radioisotope and radiopharmaceutical production, elemental analysis using neutron activation techniques, neutron beam exploitation, silicon doping, and reactor physics experimentation. For safe operation of the reactor maintenance work has been carried out for the reactor control and instrumentation, reactor cooling, ventilation, radiomonitoring, mechanical, normal electric supply systems as well as emergency electric diesel generators and the water treatment station. Technical management of the reactor includes periodical maintenance as required by technical specifications, training, re-training and control of knowledge for reactor staff. During recent years, periodic preventive maintenance (PPM) has been carried out for the electric machines of the technological systems. (author)

  6. Maintenance of reactor recirculation pumps [Paper No.: II-1

    International Nuclear Information System (INIS)

    Ansari, M.A.; Bhat, K.P.

    1981-01-01

    At Tarapur Atomic Power Station (TAPS), two reactor recirculation pumps are provided, one each for the two reactor units. The performance of pumps has been uniformly good; however, leakage through the cartridge type, two stage, mechanical seals which are installed on these pumps was encountered on few occasions. The paper describes the leakage problems, identification of certain design deficiencies and rectification carried out at TAPS for overcoming these problems. (author)

  7. Study on examples of safety culture enhancing activities at U.S. Nuclear Power Stations

    International Nuclear Information System (INIS)

    Ichiki, Kuniyasu

    2010-01-01

    After the wake of the incident of reactor vessel head degradation at Davis Basse in 2002, the NRC, the regulatory body in the U.S., included extraction of safety culture (SC) related elements from every failure into its inspection scheme of Reactor Oversight Process, since July 2006. The idea of SC itself was established some time ago, though, there are very few similar examples of such evaluation so far. This study is an attempt of making analyses on various activities with regard to SC in the U.S., to gain useful knowledge for considering the way to improve station's SC in Japan. Despite the fact that the numbers of inspection findings at stations are generally seen as unchanged, it is obvious that there are substantial difference in the number of the NRC's findings by each station. This appears to show that the condition of SC may largely different by stations. At several stations which accepted our investigation, those staff have made serious efforts to correct their area for improvements which were pointed out by the NRC. Such examples include improving management of their Corrective Action Program and establishing various measures to enable transmitting employee's concerns. It is thought that such activities aim to achieve efficient transfer of vital information among the station. This kind of activities should help every station solve various deficiencies in equipment, and also remove any obstacles in its communication. Their effort seem to result in not only the decrease in number of trouble but also much enhancement of mutual trust among the station, which would contribute to the great advance in their SC. (author)

  8. Intrinsically Safe and Economical Reactor (ISER)

    International Nuclear Information System (INIS)

    Wakabayashi, Hiroaki; Asahi, Yoshiro

    1991-01-01

    The Intrinsically Safe and Economical Reactor (ISER) is designed based on the principle of a process inherent ultimate safe reactor, PIUS, a so-called inherently safe reactor (ISR). ISER has been developed joingly by the members of the Kanagawa Institute of Technology, the University of Tokyo, the Japan Atomic Energy Research Institute (JAERI) and several industrial firms in Japan. This paper describes the requirements for the next generation of power reactor, the safety design philosphy of ISR and ISER, the controllability of ISER and the results of analyses of some of the design-based accidents (DBA) of ISER, namely station blackout, accidents in which the pressurizer relief valve becomes jammed and stuck in open position and tube breaks in the steam generator. It is concluded that the ISER can ensure a wide range of contraollabitily and fuel integrity for all the analysed DBAs. (orig.)

  9. Safety issues at the defense production reactors

    International Nuclear Information System (INIS)

    1987-01-01

    The United States produces plutonium and tritium for use in nuclear weapons at the defense production reactors endash the N Reactor in Washington and the Savannah River reactors in South Carolina. This report reaches general conclusions about the management of those reactors and highlights a number of safety and technical issues that should be resolved. The report provides an assessment of the safety management, safety review, and safety methodology employed by the Department of Energy and the private contractors who operate the reactors for the federal government. The report is necessarily based on a limited review of the defense production reactors. It does not address whether any of the reactors are ''safe,'' because such an analysis would involve a determination of acceptable risk endash a matter of obvious importance, but one that was beyond the purview of the committee. It also does not address whether the safety of the production reactors is comparable to that of commercial nuclear power stations, because even this narrower question extended beyond the charge to the committee and would have involved detailed analyses that the committee could not undertake

  10. Status and development programme of the fast breeder reactor system in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Daeunert, U.; Kessler, G.

    1977-01-01

    The Federal Republic of Germany depends on imports of raw materials for energy purposes, and special importance is therefore given to nuclear energy for reasons of energy policy. Against the background of a nuclear power station capacity amounting to 24,000MW(e) in 1976 (power stations being either on order, under construction or actually in operation), the fast breeder reactor (FBR) is outstandingly significant in the Federal Republic for the economic use both of the uranium and the plutonium accumulating in light-water reactors (LWRs). Work in this sector started in the FRG in 1960. Important stages in development were: the initial activities on the plutonium critical SNEAK at Karlsruhe; successful operation of the KNK 20-MW(e) experimental reactor (sodium-cooled) with the KNK II (plutonium core) follow-up stage; costruction of the 300-MW(e) FBR prototype nuclear power station at Kalkar; and initial planning carried out for a 1300-MW(e) FBR demonstration nuclear power station. A viable infrastructure for safety assessment must go hand in hand with the development of new reactor systems. Prototype reactors in the FRG are therefore already subjected to the same strict licensing procedures under nuclear legislation as are commercial nuclear power stations. Several years' practical experience have shown that this was the right approach. It was recognized in the FRG early on that major long-term technological projects could no longer be implemented by unaided single nations. The SNR-300 FBR prototype project combines the efforts of the governments, power supply companies, reactor manufacturers and nuclear research centres of the FRG, Belgium and the Netherlands. The agreement signed in 1971 by the Rheinisch-Westfaelische Elektrizitaetswerke AG (FRG), Ente Nazionale per l'Energia Elettrica (Italy) and Electricite de France (France) power supply companies on the joint construction of the Super-Phenix and SNR-2 FBR demonstration nuclear power stations, and the German

  11. Chernobyl reactor transient simulation study

    International Nuclear Information System (INIS)

    Gaber, F.A.; El Messiry, A.M.

    1988-01-01

    This paper deals with the Chernobyl nuclear power station transient simulation study. The Chernobyl (RBMK) reactor is a graphite moderated pressure tube type reactor. It is cooled by circulating light water that boils in the upper parts of vertical pressure tubes to produce steam. At equilibrium fuel irradiation, the RBMK reactor has a positive void reactivity coefficient. However, the fuel temperature coefficient is negative and the net effect of a power change depends upon the power level. Under normal operating conditions the net effect (power coefficient) is negative at full power and becomes positive under certain transient conditions. A series of dynamic performance transient analysis for RBMK reactor, pressurized water reactor (PWR) and fast breeder reactor (FBR) have been performed using digital simulator codes, the purpose of this transient study is to show that an accident of Chernobyl's severity does not occur in PWR or FBR nuclear power reactors. This appears from the study of the inherent, stability of RBMK, PWR and FBR under certain transient conditions. This inherent stability is related to the effect of the feed back reactivity. The power distribution stability in the graphite RBMK reactor is difficult to maintain throughout its entire life, so the reactor has an inherent instability. PWR has larger negative temperature coefficient of reactivity, therefore, the PWR by itself has a large amount of natural stability, so PWR is inherently safe. FBR has positive sodium expansion coefficient, therefore it has insufficient stability it has been concluded that PWR has safe operation than FBR and RBMK reactors

  12. The risks of nuclear energy technology. Safety concepts of light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Raskob, Wolfgang; Landman, Claudia; Paesler-Sauer, Juergen [Karlsruher Institut fuer Technologie (KIT), Eggenstein-Leopoldshafen (Germany). Inst. fuer Kern- und Energietechnk (IKET); Kessler, Guenter; Veser, Anke; Schlueter, Franz-Hermann

    2014-11-01

    Analyses the risks of nuclear power stations. Discusses the security concept of reactors. Analyzes possible crash of air planes on a reactor containment. Presents measures against the spread of radioactivity after a severe accident. Written in engaging style for professionals and policy makers. The book analyses the risks of nuclear power stations. The security concept of reactors is explained. Measures against the spread of radioactivity after a severe accident, accidents of core melting and a possible crash of an air plane on a reactor containment are discussed. The book covers three scientific subjects of the safety concepts of Light Water Reactors: - A first part describes the basic safety design concepts of operating German Pressurized Water Reactors and Boiling Water Reactors including accident management measures introduced after the reactor accidents of Three Mile Island and Chernobyl. These safety concepts are also compared with the experiences of the Fukushima accidents. In addition, the safety design concepts of the future modern European Pressurized Water Reactor (EPR) and of the future modern Boiling Water Reactor SWR-1000 (KERENA) are presented. These are based on new safety research results of the past decades. - In a second, part the possible crash of military or heavy commercial air planes on a reactor containment is analyzed. It is shown that reactor containments can be designed to resist to such an airplane crash. - In a third part, an online decision system is presented. It allows to analyze the distribution of radioactivity in the atmosphere and to the environment after a severe reactor accident. It provides data for decisions to be taken by authorities for the minimization of radiobiological effects to the population. This book appeals to readers who have an interest in save living conditions and some understanding for physics or engineering.

  13. Aseismic design of the Heysham II Nuclear Power Station

    International Nuclear Information System (INIS)

    Day, J.W.

    1983-01-01

    A brief description of the seismic criteria established for use with the Steam Generating Heavy Water Reactor (SCHWR) and taken for the Heysham II Project is given. The qualification strategy adopted for Heysham II is described, and a brief overview is given of some of the more important design changes required for seismic purposes on that station

  14. Feasibility and usefulness of reconstructing obsolete power blocks of VVER-440 reactors

    International Nuclear Information System (INIS)

    Kirichenko, A.M.; Krushenik, S.D.; Sigal, M.V.; Kustov, V.P.

    1993-01-01

    At the present time, in Russia and in the East European countries there are atomic power stations with first-generation VVER-440 reactors built according to specification which no longer satisfy the more rigorous modern safety standards. Among these power stations are, in particular, the Novovoronezh and the Armenian Atomic Power Station and two blocks of the Kola Atomic Power Station. The search for technical solutions for modernizing these power blocks is complicated because two conditions which are hard to reconcile must be fulfilled: an acceptable safety level must be obtained and the rebuilding must be economically justifiable (particularly since the time of operation of a power block until its standard service life is over is short). Research work undertaken in the All-Union Scientific Research Institute of Atomic Power Stations has shown that one way of overcoming these difficulties may involve changing the operating conditions of the reactor assembly to a less demanding mode of operation. This solution implies an economically justified minimum of structural improvements, provides the required safety level, and prolongs the service life of the power block. The reduction of the thermal power, and consequently, the necessary transfer of a power block to another option

  15. Summary of commissioning of Hamaoka Nuclear Power Station Unit No.5

    International Nuclear Information System (INIS)

    Wakunaga, T.; Sekine, Y.; Yamada, K.; Nakamura, Y.; Kawahara, M.

    2006-01-01

    The Hamaoka Nuclear Power Station Unit No.5 was put into commercial operation in January 2005, which is the 1380 MWe advanced boiling water reactor (ABWR) incorporating design improvements and latest technologies of safer operation, reliability and maintenance. For example, S-FMCRD (Sealless Fine-Motion Control Rod Drive) was equipped to eliminate the use of seal housing by adopting a magnetic coupling and also ASD (Adjustable Speed Drive- the multiple drive power supply to reactor internal pumps) that can drive two or three Recirculation Internal Pumps with a large-capacity inverter. The reactor start-up tests were performed about for eleven months from February 2004 to confirm the plant's required performance including design change points. (T. Tanaka)

  16. International working group on gas-cooled reactors. Summary report

    Energy Technology Data Exchange (ETDEWEB)

    1981-01-15

    The purpose of the meeting was to provide a forum for exchange of information on safety and licensing aspects for gas-cooled reactors in order to provide comprehensive review of the present status and of directions for future applications and development. Contributions were made concerning the operating experience of the Fort St. Vrain (FSV) HTGR Power Plant in the United States of America, the experimental power station Arbeitsgemeinschaft Versuchsreaktor (AVR) in the Federal Republic of Germany, and the CO/sub 2/-cooled reactors in the United Kingdom such as Hunterson B and Hinkley Point B. The experience gained at each of these reactors has proved the high safety potential of Gas-cooled Reactor Power Plants.

  17. Economic aspects of electricity and industrial heat generating reactors

    International Nuclear Information System (INIS)

    Gaussens, J.; Moulle, N.; Dutheil, F.

    1964-01-01

    The economic advantage of electricity-generating nuclear stations decreases when their size decreases. However, when a counter-pressure turbine is joined on to a reactor and the residual heat can be properly used, it can be shown that fairly low capacity nuclear equipment may compete with conventional equipment under certain realistic enough conditions. The aim of this paper is to define these special conditions under which nuclear energy can be profitable. They are connected with the location and the general economic environment of the station, the pattern of the electricity and heat demands it must meet, the level of fuel and specific capital costs, nuclear and conventional. These conditions entail certain technical and economic specifications for the reactors used in this way otherwise they are unlikely to be competitive. In addition, these results are referred to the potential steam and electricity market, which leads us to examine certain uses for the heat generated by double purpose power stations; for example, to supply combined industrial plants, various types of town heating and for removal of salt from sea water. (authors) [fr

  18. Socioeconomic impacts of nuclear generating stations: Peach Bottom case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Pijawka, K.D.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Peach Bottom nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  19. Socioeconomic impacts of nuclear generating stations: St. lucie case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Weisiger, M.L.; Pijawka, K.D.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the St. Lucie nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study are during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  20. Socioeconomic impacts of nuclear generating stations: Rancho Seco case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Bergmann, P.A.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Rancho Seco nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  1. Basic safety principles of KLT-40C reactor plants

    International Nuclear Information System (INIS)

    Beliaev, V.; Polunichev, V.

    2000-01-01

    The KLT-40 NSSS has been developed for a floating power block of a nuclear heat and power station on the basis of ice-breaker-type NSSS (Nuclear Steam Supply System) with application of shipbuilding technologies. Basic reactor plant components are pressurised water reactor, once-through coil-type steam generator, primary coolant pump, emergency protection rod drive mechanisms of compensate group-electromechanical type. Basic RP components are incorporated in a compact steam generating block which is arranged within metal-water shielding tank's caissons. Domestic regulatory documents on safety were used for the NSSS design. IAEA recommendations were also taken into account. Implementation of basic safety principles adopted presently for nuclear power allowed application of the KLT-40C plant for a floating power unit of a nuclear co-generation station. (author)

  2. Nuclear power stations in August: information and commentary

    International Nuclear Information System (INIS)

    Rogozhin, Yu.

    1989-01-01

    A summary of events at nuclear power stations in the USSR in August 1989 is given. There were 44 nuclear power units in service which had 9 unplanned shutdowns and 13 unsanctioned power reductions. Gosatomenergonadzor SSSR is also responsible for all research and marine reactors. It is reported that there are currently (1989) six nuclear vessels in the USSR and no major accidents or damage to nuclear steam-generating units on these were reported. On-site inspectors maintain a constant presence at nuclear power stations to supervise operation and make sure safety requirements are enforced. Glasnost is opening up previously forbidden areas to the public to enable it to obtain information to allow objective assessment to be made. (author)

  3. Innovations in PHWR design, integration of nuclear power stations into power systems and role of small size nuclear power plants in a developing country

    International Nuclear Information System (INIS)

    Mehta, S.K.; Kakodkar, A.; Balakrishnan, M.R.; Ray, R.N.; Murthy, L.G.K.; Chamany, B.F.; Kati, S.L.

    1977-01-01

    PHWR concept of thermal reactors has been considered with a view to exploiting the limited resources of natural uranium and keeping in mind the projected nuclear power programme covering fast breeder reactors. Experience in engineering of current PHWR units in India, gradual build up of necessary infrastructure and operational experience with one unit, have helped in building up design and technological capability in the country. The R and D facilities have been so planned that additional data required for the design of bigger reactor units (i.e.500/600 MWe) could be generated with minimal augmentation. Satisfactory operation of a nuclear power station demands certain prerequisites from the connected power system. The grid should have load patterns suitable for base load operation of these stations, should be stiff so far as voltage and frequency fluctuations are concerned and should have high reliability. A typical power grid in this country is characterised by heavy loads during peak hours and very light loads during night. Regional grids are of small size and the few interconnections existing between the regional grids consist of weak tie lines. Amongst all types of the power stations, it is the nuclear system which undergoes maximum strain and economic penalty while operating when connected to such a power system. Consistent with the above, phase installation of small-size power reactor units of about 200 MWe capacity may facilitate setting up of larger unit sizes at a later date. The effect of any possible reduction in the capital cost of a larger unit power station will enable the power station to partially meet the demand of the more productive types of loads. This paper deals with some of the major design changes that are being incorporated in the PHWR type power reactors currently being set up and the research and development back-up required for the purpose. Since the unit sizes of the power reactors presently contemplated are small compared to nuclear

  4. Water electrolysis plants for hydrogen and oxygen production. Shipped to Tsuruga Power Station Unit No.1, and Tokai No.2 power station, the Japan Atomic Power Co

    International Nuclear Information System (INIS)

    Ueno, Syuichi; Sato, Takao; Ishikawa, Nobuhide

    1997-01-01

    Ebara's water electrolysis plants have been shipped to Tsuruga Power Station Unit No.1, (H 2 generation rate: 11 Nm 3 /h), and Tokai No.2 Power Station (H 2 generation rate: 36 Nm 3 /h), Japan Atomic Power Co. An outcome of a business agreement between Nissho Iwai Corporation and Norsk Hydro Electrolysers (Norway), this was the first time that such water electrolysis plants were equipped in Japanese boiling water reactor power stations. Each plant included an electrolyser (for generating hydrogen and oxygen), an electric power supply, a gas compression system, a dehumidifier system, an instrumentation and control system, and an auxiliary system. The plant has been operating almost continuously, with excellent feedback, since March 1997. (author)

  5. Development situation about the Canadian CANDU Nuclear Power Generating Stations

    Energy Technology Data Exchange (ETDEWEB)

    Jeon, Yu Mi; Kim, Yong Hee; Park, Joo Hwan

    2009-07-15

    The CANDU reactor is the most versatile commercial power reactor in the world. The acronym 'CANDU', a registered trademark of Atomic Energy of Canada Limited, stands for 'CANada Deuterium Uranium'. CANDU uses heavy water as moderator and uranium (originally, natural uranium) as fuel. All current power reactors in Canada are of the CANDU type. Canada exports CANDU type reactor in abroad. CANDU type is used as the nuclear power plants to produce electrical. Today, there are 41 CANDU reactors in use around the world, and the design has continuously evolved to maintain into unique technology and performance. The CANDU-6 power reactor offers a combination of proven, superior and state-of-the-art technology. CANDU-6 was designed specifically for electricity production, unlike other major reactor types. One of its characteristics is a very high operating and fuel efficiency. Canada Nuclear Power Generating Stations were succeeded in a commercial reactor of which the successful application of heavy water reactor, natural uranium method and that on-power fuelling could be achieved. It was achieved through the joint development of a major project by strong support of the federal government, public utilities and private enterprises. The potential for customization to any country's needs, with competitive development and within any level of domestic industrial infrastructure, gives CANDU technology strategic importance in the 21st century.

  6. Development situation about the Canadian CANDU Nuclear Power Generating Stations

    International Nuclear Information System (INIS)

    Jeon, Yu Mi; Kim, Yong Hee; Park, Joo Hwan

    2009-07-01

    The CANDU reactor is the most versatile commercial power reactor in the world. The acronym 'CANDU', a registered trademark of Atomic Energy of Canada Limited, stands for 'CANada Deuterium Uranium'. CANDU uses heavy water as moderator and uranium (originally, natural uranium) as fuel. All current power reactors in Canada are of the CANDU type. Canada exports CANDU type reactor in abroad. CANDU type is used as the nuclear power plants to produce electrical. Today, there are 41 CANDU reactors in use around the world, and the design has continuously evolved to maintain into unique technology and performance. The CANDU-6 power reactor offers a combination of proven, superior and state-of-the-art technology. CANDU-6 was designed specifically for electricity production, unlike other major reactor types. One of its characteristics is a very high operating and fuel efficiency. Canada Nuclear Power Generating Stations were succeeded in a commercial reactor of which the successful application of heavy water reactor, natural uranium method and that on-power fuelling could be achieved. It was achieved through the joint development of a major project by strong support of the federal government, public utilities and private enterprises. The potential for customization to any country's needs, with competitive development and within any level of domestic industrial infrastructure, gives CANDU technology strategic importance in the 21st century

  7. The operating reliability of the reactor coolant pump

    International Nuclear Information System (INIS)

    Grancy, W.

    1996-01-01

    There is a strong tendency among operating companies and manufacturers of nuclear power stations to further increase safety and operating availability of the plant and of its components. This applies also and particularly to reactor coolant pumps for the primary circuit of nuclear power stations of the type PWR. For 3 decades, ANDRITZ has developed and built such pumps and has attached great importance to the design of the complete pump rotor and of its essential surrounding elements, such as bearing and shaft seal. Apart from questions connected with design functioning of the pump there is one question of top priority: the operating reliability of the reactor coolant pump. The pump rotor (together with the rotor of the drive motor) is the only component within the primary system that permanently rotates at high speed during operation of the reactor plant. Many questions concerning design and configuration of such components cannot be answered purely theoretically, or they can only be answered partly. Therefore comprehensive development work and testing was necessary to increase the operating reliability of the pump rotor itself and of its surrounding elements. This contribution describes the current status of development and, as a focal point, discusses shaft sealing solutions elaborated so far. In this connection also a sealing system will be presented which aims for the first time at using a two-stage mechanical seal in reactor coolant pumps

  8. Slow clean-up for fast reactor

    Science.gov (United States)

    Banks, Michael

    2008-05-01

    The year 2300 is so distant that one may be forgiven for thinking of it only in terms of science fiction. But this is the year that workers at the Dounreay power station in Northern Scotland - the UK's only centre for research into "fast" nuclear reactors - term as the "end point" by which time the site will be completely clear of radioactive material. More than 180 facilities - including the iconic dome that housed the Dounreay Fast Reactor (DFR) - were built at at the site since it opened in 1959, with almost 50 having been used to handle radioactive material.

  9. Liquid metal cooled fast breeder nuclear reactors

    International Nuclear Information System (INIS)

    Barnes, S.

    1976-01-01

    Reference is made to liquid metal cooled fast breeder reactors of the 'pool' kind. In this type of reactor the irradiated fuel is lowered into a transfer rotor for removal to storage facilities, this rotor normally having provision for the temporary storage of 20 irradiated fuel assemblies, each within a stainless steel bucket. For insertion or withdrawal of a fuel assembly the rotor is rotated to bring the fuel assembly to a loading or discharging station. The irradiated fuel assembly is withdrawn from the rotor within its bucket and the total weight is approximately 1000 kg, which is lifted about 27 m. In the event of malfunction the combination falls back into the rotor with considerable force. In order to prevent damage to the rotor fracture pins are provided, and to prevent damage to the reactor vessel and other parts of the reactor structure deformable energy absorbing devices are provided. After a malfunction the fractured pins and the energy absorbing devices must be replaced by remote control means operated from outside the reactor vault - a complex operation. The object of the arrangement described is to provide improved energy absorbing means for fuel assemblies falling into a fuel transfer rotor. The fuel assemblies are supported in the rotor by elastic means during transfer to storage and a hydraulic dash pot is provided in at least one position below the rotor for absorbing the energy of a falling fuel assembly. It is preferable to provide dash pots immediately below a receiving station for irradiated fuel assemblies and immediately below a discharge station. Each bucket is carried in a container that is elastically supported in the transfer rotor on a helical coil compression spring, so that, in the event of a malfunction the container and bucket are returned to their normal operating position after the force of the falling load has been absorbed by the dash pot. The transfer rotor may also be provided with recoil springs to absorb the recoil energy

  10. Occupational analysis for the Angra-1 reactor

    International Nuclear Information System (INIS)

    Moraes, A.

    1991-01-01

    Due to several modifications which were imposed to its time schedule during construction, the Angra-1 reactor did not enter to the grid in 1982 as it was initially foreseen. These modifications occurred due to an unforeseen scenario that was verified in steam generators (serie D-3, Westinghouse) of power stations with similar configurations which had been installed in other countries such as Ringhals-3 (Sweden), Almaraz-1 (Spain) and McGuine-1 (USA). So, among the main events that occurred in the Angra-1 reactor, which were of interest from the point of view of radiation protection, it could be pointed out the personnel monitoring, and the occupational exposure measurements at different reactor power, during the reactor fueling and during modification and tests performed at the steam generators and at ducts of the primary coolant circuit. (author)

  11. AECB staff annual assessment of the Point Lepreau Nuclear Generating Station

    International Nuclear Information System (INIS)

    1997-06-01

    The Atomic Energy Control Board is the independent federal agency that controls all nuclear activities in Canada. A major use of nuclear energy in Canada is electricity production. The AECB assesses every station's performance against legal requirements, including the conditions in the operating licence. Each station is inspected and all aspects of the station's operation and management is reviewed. This report is the AECB staff assessment of reactor safety at the Point Lepreau Generating Station in 1996. Point Lepreau operated safely but the worsening trends in NB Power's safety performance leads to the conclusion that urgent action is required. NB Power is required to report formally to the AECB on progress with measures to improve safety management every six months. Further licensing action will be taken on NB Power if it fails to make the improvements

  12. The Heysham 2 and Torness nuclear power station projects

    International Nuclear Information System (INIS)

    Cameron, P.J.

    1989-01-01

    At the beginning of the design of the Heysham 2 and Torness Nuclear Power Stations in the UK, it was agreed that the Hinkley Point B/Hunterston B Advanced Gas Cooled reactor design would be repeated. However, the Hinkley Point B/Hunterston B designs dated from 1964, and inevitably safety requirements had escalated in the intervening years. Furthermore, operating experience gained from Hinkley Point B/Hunterston B showed that it was desirable to make changes to particular features. Design changes were therefore included where it was considered essential to improve performance, to improve safety and to improve engineering. The resulting station designs are described. (author)

  13. Nuclear power reactors in the world. April 1990 ed.

    International Nuclear Information System (INIS)

    1990-01-01

    This is the tenth edition of Reference Data Series No. 2, Nuclear Power Reactors in the World, which is published once per year, to present the most recent reactor data available to the Agency. It contains the following summarized information: General information as of the end of 1989 on power reactors operating or under construction, and shut down; Performance data on reactors operating in the Agency's Member States, as reported to the IAEA. The information is collected by the Agency by circulating questionnaires to the Member States through the designated national correspondents. The replies are used to maintain computerized files on general and design data of, and operating experience with, power reactors. The Agency's power reactor information system (PRIS) comprising the above files provides all the information and data previously published in the Agency's Power Reactors in Member States and currently published in the Agency's Operating Experience with Nuclear Power Stations in Member States

  14. Nuclear power reactors in the world. Apr 1991 ed.

    International Nuclear Information System (INIS)

    1991-01-01

    This is the eleventh edition of Reference Data Series No. 2, Nuclear Power Reactors in the World, which is published once per year, to present the most recent reactor data available to the Agency. It contains the following summarized information: General information as of the end of 1990, on power reactors operating or under construction, and shut down; performance data on reactors operating in the Agency's Member States, as reported to the IAEA. This information is collected by the Agency by circulating questionnaires to the Member States through the designated national correspondents. The replies are used to maintain computerized files on general and design data of, and operating experience with, power reactors. The Agency's Power Reactor Information System (PRIS) comprising the above files provides all the information and data previously published in the Agency's Power Reactors in Member States and currently published in the Agency's Operating Experience with Nuclear Power Stations in Member States. 5 figs, 19 tabs

  15. Nuclear power reactors in the world. April 2005 ed

    International Nuclear Information System (INIS)

    2005-01-01

    This is the twenty-fifth edition of Reference Data Series No. 2, Nuclear Power Reactors in the World, which is published once per year, to present the most recent reactor data available to the Agency. It contains the following summarized information: - General information as of the end of 2004 on power reactors operating or under construction, and shut down; - Performance data on reactors operating in the Agency's Member States, as reported to the IAEA. The information is collected by the Agency by circulating questionnaires to Member States through the designated national correspondents. The replies are used to maintain computerized files on general and design data of, and operating experience with, power reactors. The Agency's Power Reactor Information System (PRIS) comprising the above files provides all the information and data previously published in the Agency's Power Reactors in Member States and currently published in the Agency's Operating Experience with Nuclear Power Stations in Member States and available at the Internet address http://www.iaea.org/programmes/a2

  16. 76 FR 72007 - ZionSolutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Exemption From Certain Security...

    Science.gov (United States)

    2011-11-21

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-295 and 50-304; NRC-2011-0244] ZionSolutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Exemption From Certain Security Requirements 1.0 Background Zion Nuclear Power Station (ZNPS or Zion), Unit 1, is a Westinghouse 3250 MWt Pressurized Water Reactor...

  17. Lippe-Ems GmbH nuclear power stations. Annual report 1992

    International Nuclear Information System (INIS)

    1993-01-01

    The Nuclear power company Lippe-Ems GmbH (KLE) runs the Emsland Nuclear Power Station (KKE) in Lingen (Ems) with a 1300 MW pressurized Water reactor. Partners of KLE are VEW and Elektromark. This 1992 annual report reveals numerous financial data of the operator (balance sheet, profit and loss account.) (orig./UA) [de

  18. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Wright, J.K.

    1982-11-01

    A description is given of the CEGB's current assessment of the potential contribution to electricity generation of those methods considered to be the most significant alternatives to conventional power stations or thermal nuclear reactors for generating electricity. The state of development of the technology, the timescale on which it could be developed, its ability to generate electricity reliably and the cost of generating electricity are some of the matters considered. The following topics are covered: potential developments in coal fired generating plant; combined heat and power generation; energy storage; electricity generation from renewable energy sources; fast reactors and fusion. (U.K.)

  19. Monitoring the Microgravity Environment Quality On-board the International Space Station Using Soft Computing Techniques. Part 2; Preliminary System Performance Results

    Science.gov (United States)

    Jules, Kenol; Lin, Paul P.; Weiss, Daniel S.

    2002-01-01

    This paper presents the preliminary performance results of the artificial intelligence monitoring system in full operational mode using near real time acceleration data downlinked from the International Space Station. Preliminary microgravity environment characterization analysis result for the International Space Station (Increment-2), using the monitoring system is presented. Also, comparison between the system predicted performance based on ground test data for the US laboratory "Destiny" module and actual on-orbit performance, using measured acceleration data from the U.S. laboratory module of the International Space Station is presented. Finally, preliminary on-orbit disturbance magnitude levels are presented for the Experiment of Physics of Colloids in Space, which are compared with on ground test data. The ground test data for the Experiment of Physics of Colloids in Space were acquired from the Microgravity Emission Laboratory, located at the NASA Glenn Research Center, Cleveland, Ohio. The artificial intelligence was developed by the NASA Glenn Principal Investigator Microgravity Services Project to help the principal investigator teams identify the primary vibratory disturbance sources that are active, at any moment of time, on-board the International Space Station, which might impact the microgravity environment their experiments are exposed to. From the Principal Investigator Microgravity Services' web site, the principal investigator teams can monitor via a dynamic graphical display, implemented in Java, in near real time, which event(s) is/are on, such as crew activities, pumps, fans, centrifuges, compressor, crew exercise, structural modes, etc., and decide whether or not to run their experiments, whenever that is an option, based on the acceleration magnitude and frequency sensitivity associated with that experiment. This monitoring system detects primarily the vibratory disturbance sources. The system has built-in capability to detect both known

  20. Certifying the decommissioned Shippingport reactor vessel for transport

    International Nuclear Information System (INIS)

    Towell, R.H.

    1990-01-01

    The decommissioned Shippingport reactor pressure vessel with its concentric neutron shield tank was shipped to Hanford, WA as part of the effort to restore the Shippingport Station to its original condition. The metal walls of the reactor vessel had become radioactive from neutron bombardment while the reactor was operating so it had to be shipped under the regulations for transporting radioactive material. Because of the large amount of radioactivity in the walls, 16,467 Curies, and because the potentially dispersible corrosion layer on the inner walls of both tanks was also radioactive, the Shippingport reactor vessel was transported under the most stringent of the regulations, those for a type B package. Compliance with the packaging regulations was confirmed via independent analysis by the staff of the Department of Energy certifying official and the Shippingport reactor vessel was shipped under DOE Certificate of Compliance USA/9515/B(U)

  1. Handling of views and opinions by staters and others in a public hearing on alteration in reactor installation (addition of Unit 2) in the Sendai Nuclear Power Station of Kyushu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1981-01-01

    A public hearing on the addition of Unit 2 in the Sendai Nuclear Power Station, Kyushu Electric Power Co., Inc., was held on July 17, 1980, in Sendai City, Kagoshima Prefecture. The views and opinions by the local staters and those by the notification of statement were expressed concerning its nuclear safety. The handling of these views and opinions by the Nuclear Safety Commission is explained. The most important in this action is the instruction by the NSC to the Committee on Examination of Reactor Safety to reflect the results of the public hearing to the reactor safety examination of the Unit 2 installation by the CERS. The views and opinions expressed in this connection are summarized as follows: the sitting conditions, the safety design of the reactor plant, and the release of radioactive materials, involving such aspects as earthquakes, accidents and radioactive waste management. (J.P.N.)

  2. Characterization of alternative electric generation technologies for the SPS comparative assessment: volume 2, central-station technologies

    International Nuclear Information System (INIS)

    1980-08-01

    The SPS Concept Development and Evaluation Program includes a comparative assessment. An early first step in the assessment process is the selection and characterization of alternative technologies. This document describes the cost and performance (i.e., technical and environmental) characteristics of six central station energy alternatives: (1) conventional coal-fired powerplant; (2) conventional light water reactor (LWR); (3) combined cycle powerplant with low-Btu gasifiers; (4) liquid metal fast breeder reactor (LMFBR); (5) photovoltaic system without storage; and (6) fusion reactor

  3. Exchange of pressurizer safeguarding system at Biblis nuclear power station

    International Nuclear Information System (INIS)

    Weber, D.; Hofbeck, W.

    1991-01-01

    Valves and piping of the pressurizer safeguarding system are exchanged and reset in such a way that they are suitable not only for discharging steam, but also for discharging a water-steam mixture and hot pressurized water; for the emergency measure of primary depressurization by hand (bleed) in the event of failure of the entire feedwater supply and station black-out, and in the event of operational transients with supposed failure of the reactor scram (ATWS). To achieve this, in addition to the requirements of the pressurizer discharging station, changes have to be made to the valve drive to dominate the water loads. During the 1990 inspection this exchange of the pressurizer discharging station was performed at the Biblis A unit as the first German plant. (orig.) [de

  4. CNSS plant concept, capital cost, and multi-unit station economics

    Energy Technology Data Exchange (ETDEWEB)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system.

  5. CNSS plant concept, capital cost, and multi-unit station economics

    International Nuclear Information System (INIS)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system

  6. Flux distribution measurements in the Bruce A unit 1 reactor

    International Nuclear Information System (INIS)

    Okazaki, A.; Kettner, D.A.; Mohindra, V.K.

    1977-07-01

    Flux distribution measurements were made by copper wire activation during low power commissioning of the unit 1 reactor of the Bruce A generating station. The distribution was measured along one diameter near the axial and horizontal midplanes of the reactor core. The activity distribution along the copper wire was measured by wire scanners with NaI detectors. The experiments were made for five configurations of reactivity control mechanisms. (author)

  7. Technical specifications: Seabrook Station, Unit 1 (Docket No. 50-443)

    International Nuclear Information System (INIS)

    1990-03-01

    The Seabrook Station, Unit 1 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public

  8. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Whittle, J.

    1982-11-01

    The non-destructive testing of components for the proposed Sizewell B nuclear power station is discussed. Issues considered include: non-destructive testing techniques available; inspection of ferritic steel components during fabrication; reliability of the ultrasonic inspection of ferritic structures; inspection of components of austenitic steel; in-service inspection of the reactor coolant system. (U.K.)

  9. Socioeconomic impacts of nuclear generating stations: Three Mile Island case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Flynn, C.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Three Mile Island nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  10. Socioeconomic impacts of nuclear generating stations - Diablo Canyon case study. Technical report for 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Pijawka, K.D.; Yaquinto, G.

    1982-07-01

    This report documents a case study of the socioeconomic impacts of the construction and operation of the Diablo Canyon nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlemeent patterns and housing, local government and public services, social structure, and public response in the study during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  11. Socioeconomic impacts of nuclear generating stations: D. C. Cook case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Branch, K.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the D. C. Cook nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  12. Technical feasibility of an Integral Fast Reactor (IFR) as a future option for fast reactor cycles. Integrate a small metal-fueled fast reactor and pyroprocessing facilities

    International Nuclear Information System (INIS)

    Tanaka, Nobuo

    2017-01-01

    Integral Fast Reactor that integrated fast reactor and pyrorocessing facilities developed by Argonne National Laboratory in the U.S. is an excellent nuclear fuel cycle system for passive safety, nuclear non-proliferation, and reduction in radioactive waste. In addition, this system can be considered as a technology applicable to the treatment of the fuel debris caused by the Fukushima Daiichi Nuclear Power Station accident. This study assessed the time required for debris processing, safety of the facilities, and construction cost when using this technology, and examined technological possibility including future technological issues. In a small metal-fueled reactor, it is important to design the core that achieves both of reduction in combustion reactivity and reduction in coolant reactivity. In system design, calorimetric analysis, structure soundness assessment, seismic feasibility establishment study, etc. are important. Regarding safety, research and testing are necessary on the capabilities of passive reactor shutdown and reactor core cooling as well as measures for avoiding re-criticality, even when emergency stop has failed. In dry reprocessing system, studies on electrolytic reduction and electrolytic refining process for treating the debris with compositions different from those of normal fuel are necessary. (A.O.)

  13. Sizewell B: consent application for Britain's first PWR power station

    International Nuclear Information System (INIS)

    1981-02-01

    The Central Electricity Generating Board has applied to the Secretary of State for Energy for consent and for other necessary permissions to construct a nuclear power station of about 1200 MW output capacity based on the pressurised water reactor (PWR) system on the Board's existing site at Sizewell (near Leiston) in Suffolk to be known as Sizewell B. Application has also been made to the Health and Safety Executive to extend the existing nuclear site licence to permit the use of the site for a pressurised water reactor. The Secretary of State for Energy has already stated that a Public Inquiry will be held into the application and this is expected to take place in 1982. The Board is making these applications now to give ample time for public discussion and consultation. Construction of the station could not begin until the outcome of the Public Inquiry is known and the necessary consents, nuclear licence and clearances have been given. The text of the application is presented. Some background information is given. (author)

  14. Development of research reactor simulator and its application to dynamic test-bed

    International Nuclear Information System (INIS)

    Kwon, Kee-Choon; Baang, Dane; Park, Jae-Chang; Lee, Seung-Wook; Bae, Sung Won

    2014-01-01

    We developed a real-time simulator for 'High-flux Advanced Neutron Application ReactOr (HANARO), and the Jordan Research and Training Reactor (JRTR). The main purpose of this simulator is operator training, but we modified this simulator into a dynamic test-bed (DTB) to test the functions and dynamic control performance of reactor regulating system (RRS) in HANARO or JRTR before installation. The simulator hardware consists of a host computer, 6 operator stations, a network switch, and a large display panel. The software includes a mathematical model that implements plant dynamics in real-time, an instructor station module that manages user instructions, and a human machine interface module. The developed research reactor simulators are installed in the Korea Atomic Energy Research Institute nuclear training center for reactor operator training. To use the simulator as a dynamic test-bed, the reactor regulating system modeling software of the simulator was replaced by actual RRS cabinet, and was interfaced using a hard-wired and network-based interface. RRS cabinet generates control signals for reactor power control based on the various feedback signals from DTB, and the DTB runs plant dynamics based on the RRS control signals. Thus the Hardware-In-the-Loop Simulation between RRS and the emulated plant (DTB) has been implemented and tested in this configuration. The test result shows that the developed DTB and actual RRS cabinet works together simultaneously resulting in quite good dynamic control performances. (author)

  15. Fuel Summary Report: Shippingport Light Water Breeder Reactor

    International Nuclear Information System (INIS)

    Illum, D.B.; Olson, G.L.; McCardell, R.K.

    1999-01-01

    The Shippingport Light Water Breeder Reactor (LWBR) was a small water cooled, U-233/Th-232 cycle breeder reactor developed by the Pittsburgh Naval Reactors to improve utilization of the nation's nuclear fuel resources in light water reactors. The LWBR was operated at Shippingport Atomic Power Station (APS), which was a Department of Energy (DOE) (formerly Atomic Energy Commission)-owned reactor plant. Shippingport APS was the first large-scale, central-station nuclear power plant in the United States and the first plant of such size in the world operated solely to produce electric power. The Shippingport LWBR was operated successfully from 1977 to 1982 at the APS. During the five years of operation, the LWBR generated more than 29,000 effective full power hours (EFPH) of energy. After final shutdown, the 39 core modules of the LWBR were shipped to the Expended Core Facility (ECF) at Naval Reactors Facility at the Idaho National Engineering and Environmental Laboratory (INEEL). At ECF, 12 of the 39 modules were dismantled and about 1000 of more than 17,000 rods were removed from the modules of proof-of-breeding and fuel performance testing. Some of the removed rods were kept at ECF, some were sent to Argonne National Laboratory-West (ANL-W) in Idaho and some to ANL-East in Chicago for a variety of physical, chemical and radiological examinations. All rods and rod sections remaining after the experiments were shipped back to ECF, where modules and loose rods were repackaged in liners for dry storage. In a series of shipments, the liners were transported from ECF to Idaho Nuclear Technology Engineering Center (INTEC), formerly the Idaho Chemical Processing Plant (ICPP). The 47 liners containing the fully-rodded and partially-derodded core modules, the loose rods, and the rod scraps, are now stored in underground dry wells at CPP-749

  16. Operating experience of Fugen Nuclear Power Station

    International Nuclear Information System (INIS)

    Ohteru, Shigeru; Kaneko, Jun; Kawahara, Toshio; Matsumoto, Mitsuo

    1987-01-01

    The prototype ATR 'Fugen' developed as one of the national project has verified the performance and reliability of the advanced thermal reactor system through the operation for about eight years since 1979, and the elucidation of the characteristics in plutonium utilization and the development and verification of the tuilizing techniques have been advanced. Besides, the operational results and the achievement of the technical development are successively reflected to the design of a demonstration reactor. In this paper, the outline of Fugan and the operational results are reported. The ATR Fugen Power Station is that of the prototype reactor of heavy water moderated, boiling light water cooled, pressure tube type, having the electric output of 165 MW. It started the full scale operation on March 20, 1979, and as of January, 1987, the total generated electric power reached about 7 billion kWh, the time of power generation was about 43,000 h, and the average capacity factor was 60.6 %. Plutonium utilization techniques, the flow characteristics and the dynamic plant characteristics of a pressure tube type reactor, the operational characteristics of a heavy water system and the techniques of handling heavy water containing tritium, and the operational reliability and maintainability of the machinery and equipment installed have been studied. (Kako, I.)

  17. Trends in the capital costs of CANDU generating stations

    International Nuclear Information System (INIS)

    Yu, A.M.

    1982-09-01

    This paper consolidates the actual cost experience gained by Atomic Energy of Canada Limited, Ontario Hydro, and other Canadian electric utlities in the planning, design and construction of CANDU-PHWR (CANada Deuterium Uranium-Pressurized Heavy Water Reactor) generating stations over the past 30 years. For each of the major CANDU-PHWR generating stations in operation and under construction in Canada, an analysis is made to trace the evolution of the capital cost estimates. Major technical, economic and other parameters that affect the cost trends of CANDU-PHWR generating stations are identified and their impacts assessed. An analysis of the real cost of CANDU generating stations is made by eliminating interest during construction and escalation, and the effects of planned deferment of in-service dates. An historical trend in the increase in the real cost of CANDU power plants is established. Based on the cost experience gained in the design and construction of CANDU-PHWR units in Canada, as well as on the assessment of parameters that influence the costs of such projects, the future costs of CANDU-PHWRs are presented

  18. Studies on components for a molten salt reactor

    International Nuclear Information System (INIS)

    Nejedly, M.; Matal, O.

    2003-01-01

    The aim is contribute to a design of selected components of molten salt reactors with fuel in the molten fluoride salt matrix. Molten salt reactors (MSRs) permit the utilization of plutonium and minor actinides as new nuclear fuel from a traditional nuclear power station with production of electric energy. Results of preliminary feasibility studies of an intermediate heat exchanger, a small power molten salt pump and a modular conception of a steam generator for a demonstration unit of the MSR (30 MW) are summarized. (author)

  19. Life extension of CANDU reactor cores

    International Nuclear Information System (INIS)

    Millard, J.; Kerker, J.; Albert, M.

    2011-01-01

    Candu Energy (formerly AECL), in partnership with station operators, has developed a robust methodology for demonstrating the fitness of reactor core structures, and associated reactivity control devices, as an essential element in conducting a station life extension project. The ageing of reactors is affected by ageing mechanisms impacted by operational history and design related factors such as materials, chemistries and stress distributions. The methodology of this life extension work is based on the IAEA TECDOC 1197; which documents practices for ageing management in CANDU reactors. This paper uses the work in Bruce Units 1 and 2, conducted from 2007 through to 2011, to explain the methodology. The work started with analysis of historical operational conditions and identification of the forms of degradation that could have occurred. The assessment and related inspections considered the safety and pressure boundary significance of each item, as well as its failure modes and margins. It then moved through both general and local inspection, focused mainly inside the calandria vessel once the calandria tubes were removed. The inspection found the bulk of the hardware to be in good condition, with a small number of remediation opportunities. In the course of that remediation some foreign material was sampled and removed. The minor remediation was successful and the work was completed through formal documentation of the fitness for extended life. It has been demonstrated through these analyses and visual inspections that the reactor structures and components inspected are free of indications and active degradation mechanisms that would prevent the safe and reliable operation of Bruce A Units 1 and 2 through its next 25 years of life. (author)

  20. Remote tritium-in-air sampling in reactor building at NAPS

    International Nuclear Information System (INIS)

    Mitra, S.R.; Lal Chand

    2000-01-01

    Tritium-in-air activity is an important parameter in PHW reactors from the point of view of internal exposure and heavy water escape from the system. The sampling technique in vogue in PHWRs, for measurement of tritium-in-air activity, requires collection of on the spot sample from different areas using a portable sampler. This sampler uses the bubbler method of sampling. As the areas of sampling are numerous, this technique is time consuming, laborious and can lead to significant internal exposure in areas where tritium-in-air activity is high. This technique is also error prone due to the heavy workload involved. A new scheme, in which the sampling of all the areas of reactor building is done through a sampling station, has been introduced for the first time in NAPS. This sampling station facilitates collection of samples from all the areas of reactor building, remotely and simultaneously at one place thereby reducing time, labour, exposure and error. This paper gives the details of the sampling system installed at NAPS. (author)

  1. High system-safety level of nuclear power stations

    International Nuclear Information System (INIS)

    Lutz, H.R.

    1976-01-01

    A bluntly worded disquisition contrasting the incidence of death and harm to persons in the chemical industry with the low hazards in nuclear power stations. Quotes conclusions from a U.S. accident study that the risk from 100 large power stations is 100 times smaller than from chlorine manufacture and transport. The enclosure of a reactor in a safety container, the well understood effects of radioactivity on man, and the ease of measuring leakage well below safe limits, are safety features which he considers were not matched in the products and plant of the Seveso factory which suffered disaster. Questions the usefulness of warnings about nuclear dangers when chemical dangers are much greater and road dangers very much greater still. (R.W.S.)

  2. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Baker, J.W.

    1982-11-01

    The case for Sizewell B in terms of the CEGB's overall duties, policies and objectives is presented. The discussion concentrates on the rationale of the CEGB's wish to proceed with Sizewell B and the implications which an eventual decision to proceed with a Pressurised Water Reactor at Sizewell could have for future power station orders. (U.K.)

  3. Operating Experience with Power Reactors. Proceedings of the Conference on Operating Experience with Power Reactors. Vol. I

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1963-10-15

    At the beginning of 1963 nuclear power plants produced some 3 500 000kW of electrical power to different distribution grids around the world. Much significant operating experience has been gained with these power reactors, but this experience is often not collected in such a way as to make it easily available. The International Atomic Energy Agency convened a Conference on Operating Experience with Power Reactors in Vienna from 4-8 June 1963 which was attended by 240 participants representing 27 of the Agency's Member States and six international organizations. At the Conference, 42 papers giving detailed experience with more than 20 nuclear power stations were discussed. Although similar meetings on a national or regional scale have been held earlier in various countries, this is the first arranged by the Agency on a world-wide basis. Some of the detailed material may have been given earlier but for the most part it represents new and recently acquired experience, and for the first time it has been possible to compile in one place such extensive material on the operating experience with power reactors. The Conference discussed the experience gained both generally in the context of national and international nuclear power development programmes, and more specifically in the detailed operating experience with different power reactor stations. In addition, various plant components, fuel cycles, staffing of nuclear plants and licensing of such staff were treated. It is hoped that these Proceedings will be of interest not only to nuclear plant designers and operators who daily encounter problems similar to those discussed by the Conference, but also to those guiding the planning and implementation of power development programmes.

  4. Operating Experience with Power Reactors. Proceedings of the Conference on Operating Experience with Power Reactors. Vol. II

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1963-10-15

    At the beginning of 1963 nuclear power plants produced some 3 500 000 kW of electrical power to different distribution grids around the world. Much significant operating experience has been gained with these power reactors, but this experience is often not collected in such a way as to make it easily available. The International Atomic Energy Agency convened a Conference on Operating Experience with Power Reactors in Vienna from 4 -8 June 1963 which was attended by 240 participants representing 27 of the Agency's Member States and six international organizations. At the Conference, 42 papers giving detailed experience with more than 20 nuclear power stations were discussed. Although similar meetings on a national or regional scale have been held earlier in various countries, this is the first arranged by the Agency on a world-wide basis. Some of the detailed material may have been given earlier but for the most part it represents new and recently acquired experience, and for the first time it has been possible to compile in one place such extensive material on the operating experience with power reactors. The Conference discussed the experience gained both generally in the context of national and international nuclear power development programmes, and more specifically in the detailed operating experience with different power reactor stations. In addition, various plant components, fuel cycles, staffing of nuclear plants and licensing of such staff were treated. It is hoped that these Proceedings will be of interest not only to nuclear , plant designers and operators who daily encounter problems similar to those discussed by the Conference, but also to those guiding the planning and implementation of power development programmes.

  5. Nuclear power station with a water-cooled reactor pressure vessel

    International Nuclear Information System (INIS)

    Hoffmann, R.; Brunner, G.; Jost, N.

    1987-01-01

    Nuclear radiation produces radiolysis gases, which are undesirable for corrosion and oxyhydrogen gas reasons. To limit the proportion of this radiolysis gas, the invention provides that catalytic surfaces should be introduced into the primary circuit, to produce recombination of hydrogen and oxygen. These surfaces can be accommodated in the upper part of the reactor pressure vessel. The live steam screen can also have a catalytic surface. (orig./HP) [de

  6. Capital cost: pressurized water reactor plant. Commercial electric power cost studies

    Energy Technology Data Exchange (ETDEWEB)

    1977-06-01

    The investment cost study for the 1139 MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume contains the drawings, equipment list and site description.

  7. Capital cost: pressurized water reactor plant. Commercial electric power cost studies

    International Nuclear Information System (INIS)

    1977-06-01

    The investment cost study for the 1139 MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume contains the drawings, equipment list and site description

  8. Socioeconomic impacts of nuclear generating stations: Crystal River Unit 3 case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Bergmann, P.A.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Crystal River Unit 3 nuclear power station. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  9. Choice of thermal reactor systems: a report

    Energy Technology Data Exchange (ETDEWEB)

    1977-09-01

    This is a report by the UK National Nuclear Corporation published by the UK Secretary of State for Energy (Mr. Benn) on 29th July 1977. It is concerned with the advantages and disadvantages of three thermal reactor systems -the AGR (advanced gas cooled reactor), the PWR (pressurised water reactor), and the SGHWR (steam generating heavy water reactor). The object was to help in the future choice of a thermal system for the UK to cover the next 25 years. The matter of export potential is also considered. A programme of four stations of 1100 to 1300 MW each over six years starting from 1979 was assumed. It is emphasised that a decision must be taken now both about reactor systems and actual orders. Headings are as follows: Extract from conclusions reached; Summary of main features of assessment; General conclusions regarding the following - safety, security of the investment, operational characteristics, development and launching requirements, effect on industry, and capital and generation costs. It is stated that in order to make an overall judgement on reactor choice the technical, commercial and social issues involved must be weighed in conjunction with cost differentials.

  10. Consideration of the opinions and others in the public hearing on the alteration in reactor installation (addition of Unit 2) in the Tsuruga Power Station of the Japan Atomic Power Company

    International Nuclear Information System (INIS)

    1982-01-01

    A public hearing was held in Tsuruga City, Fukui Prefecture, on the alteration in reactor installation, i.e., the addition of Unit 2 in the Tsuruga Power Station, JAPC, on November 20, 1980, by the Nuclear Safety Commission. The opinions and others stated by the local people were taken into consideration in the governmental examinations on the installation, etc. The considerations of such opinions principally in the examinations by NSC are explained in the form of questions (i.e. opinion, etc.) and answers (i.e. consideration) as follows: site conditions (site, earthquakes, ground, meteorology, siting situation, etc.), the safety design of the reactor facilities (overall plant, aseismic design, the teaching by the TMI accident in U.S., ECCS, pre-stressed concrete containment vessel, radioactive waste release, etc.), radioactive waste management, radiation exposure relation, the technical capabilities of personnel (operation, etc.). (J.P.N.)

  11. Computer functions in overall plant control of candu generating stations

    International Nuclear Information System (INIS)

    Chou, Q.B.; Stokes, H.W.

    1976-01-01

    System Planning Specifications form the basic requirements for the performance of the plant including its response to abnormal situations. The rules for the computer control programs are devised from these, taking into account limitations imposed by the reactor, heat transport and turbine-generator systems. The paper outlines these specifications and the limitations imposed by the major items of plant equipment. It describes the functions of each of the main programs, their interactions and the control modes used in the existing Ontario Hydro's nuclear station or proposed for future stations. Some simulation results showing the performance of the overall unit control system and plans for future studies are discussed. (orig.) [de

  12. Characteristics of outage radiation fields around various reactor components

    International Nuclear Information System (INIS)

    Verzilov, Y.; Husain, A.; Corbin, G.

    2008-01-01

    Full text: Activity monitoring surveys, consisting of gamma spectroscopy and dose rate measurements, of various CANDU station components such as the reactor face, feeder cabinet, steam generators and moderator heat exchangers are often performed during shutdown in order to trend the transport of activity around the primary heat transport and moderator systems. Recently, the increased dose expenditure for work such as feeder inspection and replacement in the reactor vault has also spurred interest in improved characterization of the reactor face fields to facilitate better ALARA decision making and hence a reduction in future dose expenditures. At present, planning for reactor face work is hampered by insufficient understanding of the relative contribution of the various components to the overall dose. In addition to the increased dose expenditure for work at the reactor face, maintenance work associated with horizontal flux detectors and liquid injection systems has also resulted in elevated dose expenditures. For instance at Darlington, radiation fields in the vicinity of horizontal flux detectors (HFD) and Liquid Injection Shutdown System (LISS) nozzle bellows are trending upwards with present contact fields being in the range 16-70 rem/h and working distance fields being in the range 100-500 mrem/h. This paper presents findings based on work currently being funded by the CANDU Owners Group. Measurements were performed at Ontario Power Generation's Pickering and Darlington nuclear stations. Specifically, the following are addressed: Characteristics of Reactor Vault Fields; Characteristics of Steam Generator Fields; Characteristics of Moderator Heat Exchanger Fields. Measurements in the reactor vault were performed at the reactor face, along the length of end fittings, along the length of feeders, at the bleed condenser and at the HFD and LISS nozzle bellows. Steam generator fields were characterized at various elevations above the tube sheet, with and without the

  13. Control of operational transients in power reactors - Methodology

    International Nuclear Information System (INIS)

    Vukovic, D.

    1983-01-01

    By introducing the nuclear power stations in the electric power system, questions of their possibilities to satisfy system's demand arise. Control of operational transients (temperature and Xe 135 ) in power reactors by determining the optimal control rod strategy is given. Ti optimize the Xe 135 transients, the Pantryagin theorem of optimal processes is applied. For solving three dimensional, two-group diffusion equations the heterogeneous Feinberg-Galanin method with axial flux harmonics is adopted. An application of this formalism to three-dimensional, finite cylindrical pressurised water reactor radially reflected is presented. (author)

  14. Dose management programmes at Kaiga Generating Station

    International Nuclear Information System (INIS)

    Vijayan, P.; Prabhakaran, V.; Managavi, Sadashiv B.; Danannavar, Veerendra; Biju, P.; Manoj Kumar, M.; Shrikrishna, U.V.

    2001-01-01

    Kaiga Generating Station (KGS) has two units of pressurized heavy water reactors of 220 MWe each capacity. KGS-2 started power generation since 1999 and KGS-1 since 2000. Several programmes such as assessment of radioactive condition, training on radiological safety aspects, job planning in radioactive areas, etc. are conducted periodically to implement an effective dose control programmes in KGS. These efforts are briefly discussed in this report. Facilities and techniques to implement ALARA programs are also highlighted in this report. (author)

  15. Front against the Temelin nuclear power station

    International Nuclear Information System (INIS)

    Anon.

    1990-01-01

    Though the main concern of the author is the Czechoslovakian Temelin power station, the main target of his attacks are the Austrian proponents of nuclear energy i.e. the Reactor Safty Commission and the Austrian Chancellor. The newly opened possibility of anti-nuclear propaganda in the CSFR, by Greenpeace and the author's organisation is welcomed. The number of signatures collected against Temelin is given as 350.000. 815 signatures come from Japan: a facsimile of some Japanese signatures is presented

  16. History of measures taken to reduce radiation exposure at Hamaoka Nuclear Power Station

    International Nuclear Information System (INIS)

    Kondou, Masashi; Takagi, Nobuyuki; Yabushita, Kazuo; Dekijima, Makoto

    2009-01-01

    Hamaoka Nuclear Power Station currently has five reactors, Units 1 to 5. Units 1 and 2 halted commercial operation in January 2009 and are now being prepared for decommissioning. Units 3 to 5 are operating at the rated thermal output with the gross electrical output of 3504 MWe. Hamaoka Nuclear Power Station has been operating for about 30 years since Unit 1 started up in 1976. Various measures have been taken to control water chemistry: for controlling SCC in the core internals and structural materials, hydrogen injection and noble metal injection were implemented; and to reduce radiation exposure for workers, condensate filter demineralizers were added, hollow fiber filters and pleated filters were installed in the condensate cleanup system, and zinc injection was performed. This paper describes measures taken at Hamaoka to reduce exposure in terms of water chemistry and techniques to monitor ion impurities in the reactor water. (author)

  17. To question of NPP power reactor choice for Kazakhstan

    International Nuclear Information System (INIS)

    Batyrbekov, G.A.; Makhanov, Y.M.; Reznikova, R.A.; Sidorenco, A.V.

    2004-01-01

    Full text: The requirements to NPP power reactors that will be under construction in Kazakhstan are proved and given in the report. A comparative analysis of the most advanced projects of power reactors with light and heavy water under pressure of large, medium and low power is carried out. Different reactors have been considered as follows: 1. Reactors with high-power (700 MW(el) and up) such as EPR, French - German reactor; CANDU-9, Canadian heavy-water reactor; System 80+, developed by ABB Combustion Engineering company, USA; KNGR, Korean reactor of the next generation; APWR, Japanese advanced reactor; WWER-1000 (V-392) - development of Atomenergoproect /Gydropress, Russian Federation; EP 1000, European passive reactor. 2. Reactors with medium power (300 MW (el) - 700 MW (el): AP-600, passive PWR of the Westinghouse company; CANDU-6, Canadian heavy-water reactor; AC-600, Chinese passive PWR; WWER-640, Russian passive reactor; MS-600 Japanese reactor of Mitsubishi Company; KSNP-600, South Korean reactor. 3. Reactors with low power (a few MW(el)- 300 MW(el)): IRIS, reactor of IV generation, developed by the International Corporation of 13 organizations from 7 countries, SMART, South Korean integrated reactor; CAREM, Argentina integrated reactor; MRX, Japanese integrated reactor; 'UNITERM', Russian NPP with integrated reactor, development of NIKIET; AHEC-80, Russian NPP, developed by OKBM. A comparison of the projects of the above-mentioned power reactors was carried out with respect to 15 criteria of nuclear, radiating, ecological safety and economic competitiveness, developed especially for this case. Data on a condition and prospects of power production and power consumption, stations and networks in Kazakhstan necessary for the choice of projects of NPP reactors for Kazakhstan are given. According to the data a balance of power production and power consumption as a whole in the country was received at the level of 59 milliard kw/h. However, strong dis balance

  18. To question of NPP power reactor choice for Kazakhstan

    International Nuclear Information System (INIS)

    Batyrbekov, G.A.; Makhanov, Y.M.; Reznikova, R.A.; Sidorenco, A.V.

    2004-01-01

    The requirements to NPP power reactors that will be under construction in Kazakhstan are proved and given in the report. A comparative analysis of the most advanced projects of power reactors with light and heavy water under pressure of large, medium and low power is carried out. Different reactors have been considered as follows: 1. Reactors with high-power (700 MW(el) and up) such as EPR, French - German reactor; CANDU-9, Canadian heavy-water reactor; System 80+, developed by ABB Combustion Engineering company, USA; KNGR, Korean reactor of the next generation; APWR, Japanese advanced reactor; WWER-1000 (V-392) - development of Atomenergoproect /Gydropress, Russian Federation; EP 1000, European passive reactor. 2. Reactors with medium power (300 MW (el) - 700 MW (el): AP-600, passive PWR of the Westinghouse company; CANDU-6, Canadian heavy-water reactor; AC-600, Chinese passive PWR; WWER-640, Russian passive reactor; MS-600 Japanese reactor of Mitsubishi Company; KSNP-600, South Korean reactor. 3. Reactors with low power (a few MW(el)- 300 MW(el)): IRIS, reactor of IV generation, developed by the International Corporation of 13 organizations from 7 countries, SMART, South Korean integrated reactor; CAREM, Argentina integrated reactor; MRX, Japanese integrated reactor; 'UNITERM', Russian NPP with integrated reactor, development of NIKIET; AHEC-80, Russian NPP, developed by OKBM. A comparison of the projects of the above-mentioned power reactors was carried out with respect to 15 criteria of nuclear, radiating, ecological safety and economic competitiveness, developed especially for this case. Data on a condition and prospects of power production and power consumption, stations and networks in Kazakhstan necessary for the choice of projects of NPP reactors for Kazakhstan are given. According to the data a balance of power production and power consumption as a whole in the country was received at the level of 59 milliard kw/h. However, strong dis balance in the

  19. The effects of the nuclear disaster at Fukushima Daiichi Nuclear Power Station on local governments

    International Nuclear Information System (INIS)

    Nakamura, Makoto; Dake, Kinji

    2012-01-01

    All Japan council of local governments with atomic power stations consisted of 24 reactor site and 6 neighboring local governments to solve reactor site related problems. Nuclear disaster at Fukushima Daiichi Nuclear Power Station affected member local governments to be forced in severe conditions such as 'removal of administrative function' or 'refuge over a wide district beyond local government area', not imagined before. The council set up working group for thirteen local governments themselves to investigate this disaster and find safety and prevention of disaster measures to be deployed in nuclear administration, which published report in March 2012. This article described outline of investigation and derived problems and direction of their solution. Main items were related with communication, resident evacuation, prevention of disaster system, and management of refuge site. (T. Tanaka)

  20. The training and assessment of operations engineers at Hinkley Point 'B' nuclear power station

    International Nuclear Information System (INIS)

    Walsey, B.A.; Howard, J.D.

    1986-01-01

    The Nuclear Power Training Centre at Oldbury-on-Severn was established to provide a common training of staff at all nuclear power stations operated by the Central Electricity Generating Board, following the ''Standard Specification for the Nuclear Training of Staff at CEGB Nuclear Power Stations''. The paper deals with the following aspects of AGR Stations: The Legislation applicable to these stations. The current training requirements for Operations Staff. The development of training for operations staff at Hinkley Point 'B' including training for career progression within the Operations Department. A detailed explanation of the training package developed for Reactor Desk Drivers at Hinkley 'B'. Revision training of Operations staff to ensure that they continue to run the plant in a safe and commercially viable manner. The training of Shift Operations Engineers for their duties under the Station Emergency Plan. (author)

  1. Analysis of thermal fatigue events in light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Okuda, Yasunori [Institute of Nuclear Safety System Inc., Seika, Kyoto (Japan)

    2000-09-01

    Thermal fatigue events, which may cause shutdown of nuclear power stations by wall-through-crack of pipes of RCRB (Reactor Coolant Pressure Boundary), are reported by licensees in foreign countries as well as in Japan. In this paper, thermal fatigue events reported in anomalies reports of light water reactors inside and outside of Japan are investigated. As a result, it is clarified that the thermal fatigue events can be classified in seven patterns by their characteristics, and the trend of the occurrence of the events in PWRs (Pressurized Water Reactors) has stronger co-relation to operation hours than that in BWRs (Boiling Water Reactors). Also, it is concluded that precise identification of locations where thermal fatigue occurs and its monitoring are important to prevent the thermal fatigue events by aging or miss modification. (author)

  2. Job-related doses in light water reactors

    International Nuclear Information System (INIS)

    Schnuer, K.

    1993-01-01

    The Treaty of 1957 establishing the European Atomic Energy Community, (EURATOM) was an essential prerequisite for the development of a strong nuclear industry in Europe. Among other things the Treaty provides that the Community shall lay down Basic Safety Standards for the protection of the health of workers and the general public against the dangers arising from ionizing radiation and ensure that they are applied. Following adoption of the Council Directive of 1980, the European Commission defined the basic principles of Justification, Optimization and Limitation to be applied in order to ensure the greatest possible protection of workers and the general public. Subsequently the Commission took initiatives in order to find ways of implementing these three basic principles in practical radiation protection. In 1980 the Commission in close collaboration with the leading nuclear power station operators, set up its own system of 'occupational radiation dose statistics from light water reactors operating in Western Europe'. This was designed for PWRs and BWRs, and the Commission benefited from the experience of neighbouring non-EC countries such as Sweden, Finland, Switzerland and Spain (not yet a member) operating nuclear power stations made by different manufacturers. The paper provides some general information on developments and trends in collective and individual doses to workers in nuclear power stations, based on a unique European databank of approximately 1000 operating reactor years. 9 figs

  3. Status and programme of development of the fast breeder reactor systems in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Daeunert, U.; Kessler, G.

    1977-01-01

    Owing to the dependence of the Federal Republic of Germany on imports of raw materials for energy purposes, special importance is given to nuclear energy for reasons of energy policy. Against the background of a nuclear power station capacity amounting to 24,000 MWe in 1976 (power stations being either on order, under construction or actually in operation), the Fast Breeder Reactor (FBR) has quite outstanding significance in this country where the economical utilization both of uranium and of the plutonium accumulating in light water reactors is concerned. Work in this sector started in the Federal Republic of Germany in 1960. Milestones on the path of development were the initial activities on the plutonium critical SNEAK at Karlsruhe, the successful operation of the KNK 20 MWe experimental reactor (sodium-cooling) with the KNK II (plutonium core) follow-up stage, the construction of the 300 MWe FBR prototype nuclear power station at Kalkar, as well as the initial planning work carried out in connection with a 1,300 MWe FBR demonstration nuclear power station. The provision of a viable infrastructure for safety assessment must go hand in hand with the development of new reactor systems. For this reason, prototype reactors in the Federal Republic of Germany are already subjected to the same strict licensing procedures under nuclear legislation as are commercial nuclear power stations. After several years' practical experience, it is becoming evident that this approach was the right one to take. Already early on, it was recognized in the Federal Republic of Germany that the execution of long-term technological major projects were increasingly exceeding the capacities of unaided development by single nations. The SNR 300 FBR prototype project combines the efforts of the governments, power supply companies, reactor manufacturers and nuclear research centres of the Federal Republic of Germany and of the Kingdoms of both Belgium and the Netherlands. The Agreement signed

  4. Development of Reactor TRIGA PUSPATI Simulator for Education and Training

    International Nuclear Information System (INIS)

    Mohd Sabri Minhat; Zarina Masood; Muhammad Rawi Mohamed Zin

    2016-01-01

    The real-time simulator for Reactor TRIGA PUSPATI (RTP) which is under development. The main purpose of this simulator is operator training and a dynamic test bed (DTB) to test and validate the control logics in reactor regulating system (RRS) of RTP. The simulator configuration is divided into hardware and software. The simulator hardware consists of a host computer, operator station, a network switch, control rod drive mechanism and a large display panel. The RTP hardwired panel is replicated similar to real console. The software includes a mathematical model includes reactor kinetics and thermal-hydraulics that implements plant dynamics in real-time using LabVIEW, an instructor station module work as host computer that manages user instructions, and a human machine interface module as a graphical user interface which is used in the real RTP plant. The developed TRIGA reactor simulators are installed in the Malaysian Nuclear Agency nuclear training center for reactor operator training. To use the simulator as a dynamic test-bed, the reactor regulating system modeling software of the simulator was replaced by actual RRS cabinet which is consist of Programmable Logic Controller (PLC) S7-1500, and was interfaced using a hard-wired and network-based interface. RRS cabinet generates control signals for reactor power control based on the various feedback signals from DTB such as neutron detector signal and control rod positions, and the DTB runs plant dynamics based on the RRS control signals. Thus the Hardware-In-the-Loop Simulation between RRS and the emulated plant (DTB) has been implemented and tested in this configuration. Normal and abnormal case test have been emulated for this project. In conclusion, the functions and the control performance of the developed RTP dynamic test bed simulator have been tested showing reasonable and acceptable results. (author)

  5. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Smedley, G.P.

    1982-11-01

    A description is given of the role of Lloyd's Register of Shipping as Independent Inspection Agency for the primary circuit of the PWR for the proposed Sizewell B power station. Topics discussed include: Lloyd's Register of Shipping and its functions; the Independent Inspection Agency and its functions; fabrication of the reactor pressure vessel; inspection on site at Sizewell. (U.K.)

  6. Outage performance improvement by state of the art reactor stud tensioning

    International Nuclear Information System (INIS)

    Oehler, Horst Werner; Vervliet, Herman

    2006-01-01

    Actual methods of reactor closing, i.e. cover to vessel sealing, is based on the creation of an equal load to the sealing circumference by tensioning all reactor studs with an equal force. This method ensures leak tightness through equal compression of the reactor seal in normal circumstances and is largely applied for all types of reactors throughout many generations and designs of nuclear power stations. The tension generated in each reactor stud is controlled indirectly by measuring the reactor stud elongation while under stress. Most studs are designed to measure this elongation easily by conventional or more advanced systems (from individual clock gauge to integrated digital transmission to a computer screen). It is this elongation value, prescribed by the reactor vessel/cover manufacturer which must be respected and demonstrated during all reactor closing operations, weather they take place for initial hydro testing, refuelling operations or periodical hydraulic tests of the primary circuit. Closing (and re-opening) of reactor vessels has become a routine operation as it is required for fuel reloading of the reactor core. This operation is performed on all PWR and BWR type of reactors with a large variety of tooling. As most of the utilities have implemented maintenance optimisation programs, the refuelling outage is reduced to a sequence of activities that allow quick and efficient refuelling of the core. The performance and efficiency of instrumentation and tooling deployed during these essential activities are of the utmost importance to minimise the critical path of the refuelling outage. Today, in support of outage performance, many utilities have invested in new and refurbished tooling to allow quick and efficient opening and closing of the reactor vessel. The features and properties of the most performing multi stud tensioning machines currently in service in nuclear power stations world wide (Africa, Europe, Asia and USA) are presented in the paper

  7. The advanced neutron source - A world-class research reactor facility

    International Nuclear Information System (INIS)

    Thompson, P.B.; Meek, W.E.

    1993-01-01

    The advanced neutron source (ANS) is a new facility being designed at the Oak Ridge National Laboratory that is based on a heavy-water-moderated reactor and extensive experiment and user-support facilities. The primary purpose of the ANS is to provide world-class facilities for neutron scattering research, isotope production, and materials irradiation in the United States. The neutrons provided by the reactor will be thermalized to produce sources of hot, thermal, cold, very cold, and ultracold neutrons usable at the experiment stations. Beams of cold neutrons will be directed into a large guide hall using neutron guide technology, greatly enhancing the number of research stations possible in the project. Fundamental and nuclear physics, materials analysis, and other research pro- grams will share the neutron beam facilities. Sufficient laboratory and office space will be provided to create an effective user-oriented environment

  8. Contaminated concrete scabbling at the Shippingport station decommissioning project

    International Nuclear Information System (INIS)

    Bauer, R.G.

    1989-01-01

    The Shippingport atomic power station was the first commercial nuclear power plant in the United States, joining the Duquesne Light Company (DLC) grid in December 1957. The Shippingport station was shut down in October 1982 and defueled in preparation for dismantling. On September 6, 1984, the Shippingport Station Decommissioning Project (SSDP) office of the US Department of Energy (DOE) assumed responsibility for the site. At turnover, there were several areas in the plant where radioactive contamination was entrained in concrete surfaces. The removal of contaminated concrete at SSDP was an important part of the decontamination to meet site release criteria, which is a major consideration in the decommissioning of nuclear power reactors. The highlights of this activity include: (1) development and application of remote scabbling tools, which effectively removed the contaminated concrete surfaces, and (2) use of scabblers minimized the removal of noncontaminated concrete by removing shallow layers of the surface and contributed to waste control, since the waste form enabled good packaging efficiency

  9. Some aspects affecting fast reactor steam generator integrity considered from a utility viewpoint

    Energy Technology Data Exchange (ETDEWEB)

    Bolt, P R

    1975-07-01

    The important conditions affecting fast reactor steam generator integrity are discussed. In addition to the need for high integrity levels when the steam generator is first delivered to the power station site, the equally important aspect of demonstrating retention of continued high levels of integrity throughout the operating life of the station is described. The functional and related conditions that are believed important to the selection of a design type which can offer adequately high levels of integrity are given. Some of the data needs of a utility concerned with fast reactor S.G.U. design assessment are described, particular emphasis being given to areas believed to have a significant effect on steam generator reliability and integrity. (author)

  10. Socioeconomic impacts of nuclear generating stations: Nine Mile Point and Fitzpatrick case study. Technical report 1 Oct 78-4 Jan 82

    International Nuclear Information System (INIS)

    Branch, K.; Cochran, R.; Meale, R.

    1982-07-01

    The report documents a case study of the socioeconomic impacts of the construction and operation of the Nine Mile Point and Fitzpatrick nuclear power stations. It is part of a major post-licensing study of the socioeconomic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period, 1980-81. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socioeconomic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  11. The action of the project coordinator with respect to reactor safety

    International Nuclear Information System (INIS)

    Leclercq, Jacques

    1981-01-01

    Before describing the various actions of the project coordinator (EDF) entrusted with the building of nuclear power stations, with respect to reactor safety in France, the definition of reactor safety and the various participants are mentioned first. These participants are: the Government Departments and the Experts involved (the Department of Nuclear Safety of the 'Institut de Protection et de Surete Nucleaire' forming the first technical support) and the applicant, namely the EDF. The reactor safety actions of the project coordinator are defined as from the following components: 1 - The targets laid down with respect to safety, the final objective being the protection of workers and the public against the potential dangers of the installations, principally against radiation. 2 - The safety methodology at the design stage of the power station: 'barrier' method, defence method in depth at three levels, lines of assurance method, and probabilistic method. 3 - Safety actions at the construction stage within the context of an assurance of quality programe. 4 - Safety at the trials, commissioning and operating stage, with the backing of the 'Groupe Operationnel de Demarrage (G.O.D.)' and the 'Commission d'Essais sur Site (C.E.S.)'. An initial balance sheet of the reactor safety actions for the PWR units built by the EDF is presented [fr

  12. Effect of parameter variation of reactor coolant pump on loss of coolant accident consequence

    International Nuclear Information System (INIS)

    Dang Gaojian; Huang Daishun; Gao Yingxian; He Xiaoqiang

    2015-01-01

    In this paper, the analyses were carried out on Ling'ao nuclear power station phase II to study the consequence of the loss of coolant accident when the homologous characteristic curves and free volumes of the reactor coolant pump changed. Two different pumps used in the analysis were 100D (employed on Ling'ao nuclear power station phase II) and ANDRITZ. The thermal characteristics in the large break LOCA accident were analyzed using CATHRE GB and CONPATE4, and the reactor coolant system hydraulics load during blow-clown phase of LOCA accident was analyzed using ATHIS and FORCET. The calculated results show that the homologous characteristic curves have great effect on the thermal characteristics of reactor core during the reflood phase of the large break LOCA accident. The maximum cladding surface temperatures are quite different when the pump's homologous characteristic curves change. On the other hand, the pump's free volume changing results in the variation of the LOCA rarefaction wave propagation, and therefore, the reactor coolant system hydraulic load in LOCA accident would be different. (authors)

  13. Using harmonical analysis for experimental verification of reactor dynamics

    International Nuclear Information System (INIS)

    Hrstka, V.

    1974-01-01

    The questions are discussed of the accuracy of the method of static programming when applied to digital harmonic analysis, with regard to the variation of the mean value of the analyzed signals, and to the use of symmetrical trapezoidal periodical signals. The evaluation is made of the suitability of the above-mentioned method in determining the frequency characteristic of the SR-OA reactor. The results obtained were applied to planning the start-up experiments of the KS-150 reactor at the A-1 nuclear power station. (author)

  14. Demonstration of fully coupled simplified extended station black-out accident simulation with RELAP-7

    Energy Technology Data Exchange (ETDEWEB)

    Zhao, Haihua [Idaho National Lab. (INL), Idaho Falls, ID (United States); Zhang, Hongbin [Idaho National Lab. (INL), Idaho Falls, ID (United States); Zou, Ling [Idaho National Lab. (INL), Idaho Falls, ID (United States); Anders, David [Idaho National Lab. (INL), Idaho Falls, ID (United States); Martineau, Richard [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-10-01

    The RELAP-7 code is the next generation nuclear reactor system safety analysis code being developed at the Idaho National Laboratory (INL). The RELAP-7 code develop-ment effort started in October of 2011 and by the end of the second development year, a number of physical components with simplified two phase flow capability have been de-veloped to support the simplified boiling water reactor (BWR) extended station blackout (SBO) analyses. The demonstration case includes the major components for the primary system of a BWR, as well as the safety system components for the safety relief valve (SRV), the reactor core isolation cooling (RCIC) system, and the wet well. Three scenar-ios for the SBO simulations have been considered. Since RELAP-7 is not a severe acci-dent analysis code, the simulation stops when fuel clad temperature reaches damage point. Scenario I represents an extreme station blackout accident without any external cooling and cooling water injection. The system pressure is controlled by automatically releasing steam through SRVs. Scenario II includes the RCIC system but without SRV. The RCIC system is fully coupled with the reactor primary system and all the major components are dynamically simulated. The third scenario includes both the RCIC system and the SRV to provide a more realistic simulation. This paper will describe the major models and dis-cuss the results for the three scenarios. The RELAP-7 simulations for the three simplified SBO scenarios show the importance of dynamically simulating the SRVs, the RCIC sys-tem, and the wet well system to the reactor safety during extended SBO accidents.

  15. Technical Specifications, Seabrook Station, Unit 1 (Docket No. 50-443). Appendix ''A'' to License No. NPF-56

    International Nuclear Information System (INIS)

    1986-10-01

    This report provides specifications for the Seabrook Station Unit 1 reactor concerning: safety limits and limiting safety settings; limiting conditions for operation and surveillance requirements; design features; and administrative controls

  16. Internal exposure profile of occupational workers of a BWR type atomic power station

    International Nuclear Information System (INIS)

    Hegde, A.G.; Bhat, I.S.

    1979-01-01

    The internal exposure profile of major radionuclides, for Tarapur Atomic Power Station (India) occupational staff for the last 9 years (1970-1978) of station operation, is presented. This power station has two boiling water reactor units. The occupational staff were monitored for internal exposure with the whole body counter. It has been observed that 60 Co, 134 Cs and 137 Cs are major contaminants. The highest yearly average of internal exposure was less than 1% of maximum permissible body burden recommended by ICRP. Depending on the nature of exposures the power station employees were classified under four different groups, (i) maintenance, (ii) operations, (iii) techanical and (iv) non-technical. This study revealed that maintenance group had highest incidence of internal exposure among these. It is also observed that contribution of 60 Co is maximum in the exposure of this group. (B.G.W.)

  17. AECB staff annual assessment of the Pickering A and B Nuclear Generating Stations for the year 1994

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-06-01

    The Pickering Nuclear Generating Station (PNGS) is located on the north shore of Lake Ontario, about 32 km east of downtown Toronto. It consists of two stations, PNGS-A and PNGS-B. Each station contains four reactor units. PNGS-A consists of Units 1 to 4, while PNGS-B consists of Units 5 to 8. Each unit can generate about 540 megawatts of electricity. All eight units are located within a single enclosure. Ontario Hydro`s Pickering Nuclear Division has assigned one Station Director with authority over both stations, but each station has its own organization. AECB issue a separate operating licence for each station. This report presents the Atomic Energy Control Board staff assessment of the Pickering stations` safety performance in 1994 and other aspects that they consider to have significant impact on nuclear safety. AECB based their conclusions on their observations, audits, inspections and review of information that Ontario Hydro submits to them as required by the station Operating Licences. 11 tabs., 8 figs.

  18. AECB staff annual assessment of the Pickering A and B Nuclear Generating Stations for the year 1994

    International Nuclear Information System (INIS)

    1995-06-01

    The Pickering Nuclear Generating Station (PNGS) is located on the north shore of Lake Ontario, about 32 km east of downtown Toronto. It consists of two stations, PNGS-A and PNGS-B. Each station contains four reactor units. PNGS-A consists of Units 1 to 4, while PNGS-B consists of Units 5 to 8. Each unit can generate about 540 megawatts of electricity. All eight units are located within a single enclosure. Ontario Hydro's Pickering Nuclear Division has assigned one Station Director with authority over both stations, but each station has its own organization. AECB issue a separate operating licence for each station. This report presents the Atomic Energy Control Board staff assessment of the Pickering stations' safety performance in 1994 and other aspects that they consider to have significant impact on nuclear safety. AECB based their conclusions on their observations, audits, inspections and review of information that Ontario Hydro submits to them as required by the station Operating Licences. 11 tabs., 8 figs

  19. Health physics in fusion reactor design

    International Nuclear Information System (INIS)

    Wong, K.Y.; Dinner, P.J.

    1984-06-01

    Experience in the control of tritium exposures to workers and the public gained through the design and operation of Ontario Hydro's nuclear stations has been applied to fusion projects and to design studies on emerging fusion reactor concepts. Ontario Hydro performance in occupational tritium exposure control and environmental impact is reviewed. Application of tritium control technologies and dose management methodology during facility design is highlighted

  20. The economics of Magnox reactors

    International Nuclear Information System (INIS)

    Watts, P.E.

    1982-01-01

    The CEGB regularly publishes figures for generation costs per kilowatt hour (kWh) at Magnox and several coal and oil stations. These have been criticized by Select Committees and most recently by Professor Jeffery for being expressed in historic cost accounting terms rather than in constant price terms. How the economic performance of Magnox reactors can best be judged is discussed. Headings are: post audit of past investment; future investment choice; inflation corrected assets. (author)

  1. Reference ZrH reactor power system for NASA space station post-operational reentry analysis

    International Nuclear Information System (INIS)

    Elliott, R.D.

    1970-01-01

    The flight dynamic and heating of a spent ZrH reactor power system returning from orbit at the end of its useful life are analyzed. The results of this analysis indicate that the reactor with a large portion of the lithium shield still surrounding it will impact the earth at a velocity of from 660 to 820 ft/sec, depending upon whether it tumbles or becomes stabilized during the latter part of its trajectory. (U.S.)

  2. Reactivity requirements and safety systems for heavy water reactors

    International Nuclear Information System (INIS)

    Kati, S.L.; Rustagi, R.S.

    1977-01-01

    The natural uranium fuelled pressurised heavy water reactors are currently being installed in India. In the design of nuclear reactors, adequate attention has to be given to the safety systems. In recent years, several design modifications having bearing on safety, in the reactor processes, protective and containment systems have been made. These have resulted either from new trends in safety and reliability standards or as a result of feed-back from operating reactors of this type. The significant areas of modifications that have been introduced in the design of Indian PHWR's are: sophisticated theoretical modelling of reactor accidents, reactivity control, two independent fast acting systems, full double containment and improved post-accident depressurisation and building clean-up. This paper brings out the evolution of design of safety systems for heavy water reactors. A short review of safety systems which have been used in different heavy water reactors, of varying sizes, has been made. In particular, the safety systems selected for the latest 235 MWe twin reactor unit station in Narora, in Northern India, have been discussed in detail. Research and Development efforts made in this connection are discussed. The experience of design and operation of the systems in Rajasthan and Kalpakkam reactors has also been outlined

  3. AECB staff annual assessment of the Bruce A Nuclear Generating Station for the year 1996

    International Nuclear Information System (INIS)

    1997-06-01

    The Atomic Energy Control Board is the independent federal agency that controls all nuclear activities in Canada. A major use of nuclear energy in Canada is electricity production. The AECB assesses every station's performance against legal requirements, including the conditions in the operating licence. Each station is inspected and all aspects of the station's operation and management is reviewed. This report is the AECB staff assessment of reactor safety at the Bruce Nuclear Generating Station A for 1996. Ontario Hydro operated Bruce A safely in 1996, maintaining the risk to workers and the public at an acceptably low level. Special safety system performance at Bruce A was adequate. Availability targets were all met. Improvement is needed to reduce the number of operating licence non-compliances

  4. Axial power deviation control strategy and computer simulation for Daya Bay Nuclear Power Station

    International Nuclear Information System (INIS)

    Liao Yehong; Zhou Xiaoling, Xiao Min

    2004-01-01

    Daya Bay Nuclear Power Station has very tight operation diagram especially at its right side. Therefore the successful control of axial power deviation for PWR is crucial to nuclear safety. After analyzing various core characters' effect on axial power distribution, several axial power deviation control strategies has been proposed to comply with different power varying operation scenario. Application and computer simulation of the strategies has shown that our prediction of axial power deviation evolution are comparable to the measurement values, and that our control strategies are effective. Engineering experience shows that the application of our methodology can predict accurately the transient of axial power deviation, and therefore has become a useful tool for reactor operation and safety control. This paper presents the axial power control characteristics, reactor operation strategy research, computer simulation, and comparison to measurement results in Daya Bay Nuclear Power Station. (author)

  5. Proceedings of the workshop on future control station designs and human performance issues in nuclear power plants

    International Nuclear Information System (INIS)

    2007-01-01

    The nuclear community is currently at a stage where new reactors are being built, advanced reactors are being planned, and existing reactors are undergoing various forms of modernization of their control stations. Nuclear power plants are characterised by a high degree of complexity, where efficient and safe performance is dependent on both a sound technical design and effective teamwork and work practices. Team interactions have long traditions in current nuclear power plants. The way people operate and maintain the plants may need to accommodate technical advances associated with control station modernization and advanced plant control stations. The nuclear community likely to see the introduction of new designs, new tools to support the staff, changes to staffing types and levels, concepts of operation for new reactors that are different from current reactors, e.g., multi-unit control, possible remote operation, distributed decision making, and cooperation across distances. Based on recent experience, there is limited knowledge about human performance issues with regard to upgraded control rooms. However, even less knowledge exists regarding operation and maintenance of control stations for future and more advanced reactor designs. In order to explore these issues, the CSNI Special Experts' Group on Human and Organisational Factors (SEGHOF), now the Working Group on Human and Organizational Factors (WGHOF), and the Halden Reactor Project (HRP) hosted a joint workshop which provided an international forum for utilities, vendors, research bodies and regulators to discuss human performance issues related to control stations for future nuclear power plant designs and for modified control rooms for existing plants. The Norwegian petroleum industry also shared their experiences, especially with integrated and distributed operations among off-shore and on-shore control centres. There were 74 participants from 20 countries at the workshop. Twenty-two papers were

  6. The reactor and cold neutron research facility at NIST

    Energy Technology Data Exchange (ETDEWEB)

    Prask, H J; Rowe, J M [Reactor Radiation Division, National Institute of Standards and Technology, Gaithersburg, MD (United States)

    1992-07-01

    The NIST Reactor (NBSR) is a 20 MW research reactor located at the Gaithersburg, MD site, and has been in operation since 1969. It services 26 thermal neutron facilities which are used for materials science, chemical analysis, nondestructive evaluation, neutron standards work, and irradiations. In 1987 the Department of Commerce and NIST began development of the CNRF - a $30M National Facility for cold neutron research -which will provide fifteen new experimental stations with capabilities currently unavailable in this country. As of May 1992, four of the planned seven guides and a cold port were installed, eight cold neutron experimental stations were operational, and the Call for Proposals for the second cycle of formally-reviewed guest-researcher experiments had been sent out. Some details of the performance of instrumentation are described, along with the proposed design of the new hydrogen cold source which will replace the present D{sub 2}O/H{sub 2}O ice cold source. (author)

  7. The reactor and cold neutron research facility at NIST

    International Nuclear Information System (INIS)

    Prask, H.J.; Rowe, J.M.

    1992-01-01

    The NIST Reactor (NBSR) is a 20 MW research reactor located at the Gaithersburg, MD site, and has been in operation since 1969. It services 26 thermal neutron facilities which are used for materials science, chemical analysis, nondestructive evaluation, neutron standards work, and irradiations. In 1987 the Department of Commerce and NIST began development of the CNRF - a $30M National Facility for cold neutron research -which will provide fifteen new experimental stations with capabilities currently unavailable in this country. As of May 1992, four of the planned seven guides and a cold port were installed, eight cold neutron experimental stations were operational, and the Call for Proposals for the second cycle of formally-reviewed guest-researcher experiments had been sent out. Some details of the performance of instrumentation are described, along with the proposed design of the new hydrogen cold source which will replace the present D 2 O/H 2 O ice cold source. (author)

  8. Methods of selection and training of personnel for the Rajasthan atomic power station

    International Nuclear Information System (INIS)

    Sarma, M.S.R.; Wagadarikar, V.K.

    1975-01-01

    Personnel selected to work in a nuclear electric generating station rarely have the necessary knowledge and experience in all the related fields. A station can be operated and maintained and at the same time radiation doses absorbed by station personnel can be kept to a minimum only if the operating personnel are familiar with, and can be used for, all phases of station operation and the maintainers have more than one skill or trade. More technical knowledge and more diversified skills, in addition to those required in other industries, are needed because of the nature of the nuclear reactor and the associated radiation environment and high automation. A training programme has been developed at the Nuclear Training Centre (NTC) near the Rajasthan Atomic Power Station (RAPS), Kota, India, to cater to the needs of the operation and maintenance personnel for nuclear power stations including the Madras Atomic Power Station. This programme has been in operation for the last five years. The paper describes the method of recruitment/selection of various categories of personnel and the method of training them to meet the job requirements. (author)

  9. Identification of hospitalized elderly patients at risk for adverse in-hospital outcomes in a university orthopedics and trauma surgery environment.

    Directory of Open Access Journals (Sweden)

    Janine Gronewold

    Full Text Available As a consequence of demographic changes, hospitals are confronted with increasing numbers of elderly patients, who are at high risk of adverse events during hospitalization. Geriatric risk screening followed by comprehensive geriatric assessment (CGA and treatment has been requested by geriatric societies and task forces to identify patients at risk. Since empirical evidence on factors predisposing to adverse hospital events is scarce, we now prospectively evaluated implications of geriatric risk screening followed by CGA in a university hospital department of orthopedics and trauma surgery.Three hundred and eighty-one patients ≥75 years admitted to the Department of Orthopedics and Trauma Surgery of the University Hospital Essen received Identification of Seniors at Risk (ISAR Screening followed by CGA via a geriatric liaison service in case of positive screening results. Associations between ISAR, CGA, comorbid risk factors and diseases, length of hospital stay, number of nursing and physiotherapy hours, and falls during hospital stay were analyzed.Of 381 ISAR screenings, 327 (85.8% were positive, confirming a high percentage of patients at risk of adverse events. Of these, 300 CGAs revealed 82.7% abnormal results, indicating activities of daily living impairment combined with cognitive, emotional or mobility disturbances. Abnormal CGA resulted in a longer hospital stay (14.0±10.3 days in ISAR+/CGA abnormal compared with 7.6±7.0 days in ISAR+/CGA normal and 8.1±5.4 days in ISAR-, both p<0.001, increased nursing hours (3.4±1.1 hours/day in ISAR+/CGA abnormal compared with 2.5±1.0 hours/day in ISAR+/CGA normal and 2.2±0.8 hours/day in ISAR-, both p<0.001, and increased falls (7.3% in ISAR+/CGA abnormal, 0% in ISAR+/CGA normal, 1.9% in ISAR-. Physiotherapy hours were only significantly increased in ISAR+/CGA abnormal (3.0±2.7 hours compared with in ISAR+/CGA normal (1.6±1.4 hours, p<0.001 whereas the comparison with ISAR- (2.4±2

  10. Hinkley Point 'C' power station public inquiry: outline statement of case

    International Nuclear Information System (INIS)

    1988-05-01

    This outline statement relates to the public inquiry to be held into the planning application by the Central Electricity Generating Board (CEGB) to construct a 1200 MW Pressurized Water Reactor (PWR) power station at Hinkley Point (Hinkley Point ''C'') in the United Kingdom, adjacent to an existing nuclear power station. The inquiry will consider economic, safety, environmental and planning matters relevant to the application and the implications for agriculture and local amenities of the re-aligning of two 400 kV overhead transmission lines. The outline statement contains submissions on: policy contest and approach; the requirement for Hinkley Point ''C''; design and safety; local issues. (UK)

  11. Man-machine interface systems for the Sizewell B Nuclear Power Station

    International Nuclear Information System (INIS)

    Boettcher, D.B.

    2004-01-01

    Sizewell B is the first nuclear power station to be built in the United Kingdom using the Pressurised Water Reactor or PWR system. The design is based on stations operating in the United States, but many changes and new features have been introduced to bring it up to date, and to meet United Kingdom practice and regulatory requirements. The Man-Machine Interfaces (MMIs) in the control rooms have been newly designed from first principles, with special attention paid to human factors and the role of the operators. The instrumentation and control (1 and C) systems which interface the MMIs to the process plant, and automate the operation of the station, use advanced technology to achieve high performance and availability. This paper describes the development of the control rooms and 1 and C systems, explaining the thinking that lay behind the principal decisions. (author)

  12. Nuclear Power Reactor simulator - based training program

    International Nuclear Information System (INIS)

    Abdelwahab, S.A.S.

    2009-01-01

    nuclear power stations will continue playing a major role as an energy source for electric generation and heat production in the world. in this paper, a nuclear power reactor simulator- based training program will be presented . this program is designed to aid in training of the reactor operators about the principles of operation of the plant. also it could help the researchers and the designers to analyze and to estimate the performance of the nuclear reactors and facilitate further studies for selection of the proper controller and its optimization process as it is difficult and time consuming to do all experiments in the real nuclear environment.this program is written in MATLAB code as MATLAB software provides sophisticated tools comparable to those in other software such as visual basic for the creation of graphical user interface (GUI). moreover MATLAB is available for all major operating systems. the used SIMULINK reactor model for the nuclear reactor can be used to model different types by adopting appropriate parameters. the model of each component of the reactor is based on physical laws rather than the use of look up tables or curve fitting.this simulation based training program will improve acquisition and retention knowledge also trainee will learn faster and will have better attitude

  13. Completely automated nuclear reactors for long-term operation

    International Nuclear Information System (INIS)

    Teller, E.; Ishikawa, M.; Wood, L.

    1996-01-01

    The authors discuss new types of nuclear fission reactors optimized for the generation of high-temperature heat for exceedingly safe, economic, and long-duration electricity production in large, long-lived central power stations. These reactors are quite different in design, implementation and operation from conventional light-water-cooled and -moderated reactors (LWRs) currently in widespread use, which were scaled-up from submarine nuclear propulsion reactors. They feature an inexpensive initial fuel loading which lasts the entire 30-year design life of the power-plant. The reactor contains a core comprised of a nuclear ignitor and a nuclear burn-wave propagating region comprised of natural thorium or uranium, a pressure shell for coolant transport purposes, and automatic emergency heat-dumping means to obviate concerns regarding loss-of-coolant accidents during the plant's operational and post-operational life. These reactors are proposed to be situated in suitable environments at ∼100 meter depths underground, and their operation is completely automatic, with no moving parts and no human access during or after its operational lifetime, in order to avoid both error and misuse. The power plant's heat engine and electrical generator subsystems are located above-ground

  14. Aspects of safety and of functional construction and configuration in planning and designing nuclear heating stations

    International Nuclear Information System (INIS)

    Adam, E.; Mueller, R.; Boettger, M.; Kremtz, U.

    1982-01-01

    The present studies are based on the design of a technological project of a nuclear heating station with a unit power of 250 MW. Essentially, this nuclear heating station is a three-circuit plant, the primary coolant circuit being based on natural circulation through the reactor vessel with integrated heat exchangers. Starting from the social objective and the derived development structure of the territory, the siting problems in integrating the nuclear heating stations have to be solved. On the basis of the resulting dimensions of the containment the technical and economical specifications of different versions of containment design are evaluated. (author)

  15. CEGB nuclear power stations basic emergency plan

    International Nuclear Information System (INIS)

    1978-03-01

    The introduction states that this is a typical emergency plan for a nuclear power station employing about 500 people, having two reactors and a total electrical output of 500 Megawatts in an intensively farmed rural area. The document has the following headings: definitions ('site incident', etc); functions of the site emergency organization; conditions for taking emergency action; persons empowered to declare or cancel a site incident or an emergency; emergency actions by staff; control centres; communication; collaboration with other bodies; warnings; transport; house rules; public information centre. (U.K.)

  16. The Osiris reactor. Descriptive report - Volume 1 - text

    International Nuclear Information System (INIS)

    1969-05-01

    Osiris is a pool type reactor with a 70 MW thermal power. Its main purpose is to irradiate under high flows of neutrons the materials of which future nuclear power stations are made. This report proposes a description of this pool reactor. A first part describes the functional aspects and general characteristics of all installations which are in principle definitely defined (premises, irradiation and experimentation equipment, water circuits, power supply, venting, controls). The second part addresses elements which are likely to be changed, and more particularly the reactor core: fuel elements and controls (uranium and boron load in different fuel element generations, experimental locations within the core), neutron transport aspects (calculation and experiment), and thermal aspects (power generation and removal) of the pile). The third part addresses the operation: operation cycles, stops, exploitation organisation [fr

  17. Procedures for permission of installation of nuclear power stations

    International Nuclear Information System (INIS)

    Narita, Yoriaki

    1980-01-01

    The locations of atomic power stations are first selected by electric power enterprises in consultation with the Ministry of International Trade and Industry or under the guidance of authorities concerned. The surveys of the climate, topography, water and plants in the planned sites and the influences of nuclear power generation to the surrounding areas are made by the enterprisers under the administrative guidance of the MITI. Secondly, the basic project shall be submitted to and decided by the Power Resource Development Council headed by the Prime Minister (Article 10, the Power Resource Development Law). The Council shall, if necessary, call for the attendance of the governors of prefectures concerned and hear their opinions (Article 11, the Law). As the third and most complicated phase, various procedures include; (a) permission of the changes of electrical facilities under the Electricity Enterprises Act; (b) authorization of the installation of reactors under the Nuclear Reactor Regulation Law; (c) permission or authorization under other regulations including the Agricultural Land Act, etc.; (d) additional procedures related to the indemnification to fishery and so forth. Finally the reactors are to be operated after receiving the certificates of the Minister of ITI on the inspections of construction works, nuclear fuel materials used for the reactors and welding processes of reactor containment vessels, boilers, turbines, etc. (Okada, K.)

  18. Hinkley Point 'C' power station public inquiry: proof of evidence on landscape and architecture

    International Nuclear Information System (INIS)

    Lisney, A.; Owen, I.D.

    1988-09-01

    A public inquiry has been set up to examine the planning application made by the Central Electricity Generating Board (CEGB) for the construction of a 1200 MW Pressurized Water Reactor power station at Hinkley Point (Hinkley Point ''C'') in the United Kingdom, adjacent to an existing nuclear power station. The CEGB evidence to the Inquiry includes an assessment of the effect, in visual terms, that the additional power station will have on the surrounding landscape and landscaping proposals for the proposed construction, including reinstatement of land used for temporary works. In addition, the architectural objectives for the new buildings are presented, primarily aiming at the best possible appearance from relatively short distances and medium and long range. (UK)

  19. Applied research into direct numerical control of A-1 reactor temperature

    International Nuclear Information System (INIS)

    Karpeta, C.; Volf, K.

    1974-01-01

    Partial results of research efforts aimed at applying modern control theory in the control of the reactor of the A-1 nuclear power station are presented. A mathematical model of the process dynamics was developed. Some parameters of the model were determined using the results of an experimentally performed reactor scram. The optimal stochastic discrete regulator was determined and closed-loop transients were studied. The possibilities of implementing control routines were investigated using the RPP-16 computer. (author)

  20. When reactors reach old age

    International Nuclear Information System (INIS)

    Fischetti, M.

    1986-01-01

    While the battle over whether to build new nuclear plants has quieted in recent times, a second struggle is shaping up in the United States as reactors approach a new stage of life: retirement. Four decades into the nuclear power age, questions of how best to dismantle and dispose of a nuclear power plant remain largely unanswered. The debates have been mainly academic until now - although reactors have operated for 25 years, decommissioning retired reactors has simply not been fully planned in this country. But the Shippingport Atomic Power Station in Pennsylvania, the first large-scale power reactor to be retired, is now being decommissioned. The work has rekindled the debates in the light of reality. Outside the United States, decommissioning is also being confronted on a new plane. Virtually all groups involved in decommissioning a reactor in the United States - the utility, the Nuclear Regulatory Commission, the U.S. Department of Energy, the U.S. Environmental Protection Agency, state public service commissions, and citizen organizations - agree that for the most part the technology to dismantle and dispose of a reactor safely is available. They disagree, however, on which technical option is the safest or cheapest and on who should pay for dismantlement. And there are further complications: Which regulations must be complied with. How much radiation exposure for workers and the public is acceptable. Even with answers to these questions, uncertainty about where to dispose of the radioactive waste and about how much residual radiation can be left at a former reactor site plagues the architects of decommissioning. This article discusses these questions

  1. Application of heat pipes in nuclear reactors for passive heat removal

    Energy Technology Data Exchange (ETDEWEB)

    Haque, Z.; Yetisir, M., E-mail: haquez@aecl.ca [Atomic Energy of Canada Limited, Chalk River, Ontario (Canada)

    2013-07-01

    This paper introduces a number of potential heat pipe applications in passive (i.e., not requiring external power) nuclear reactor heat removal. Heat pipes are particularly suitable for small reactors as the demand for heat removal is significantly less than commercial nuclear power plants, and passive and reliable heat removal is required. The use of heat pipes has been proposed in many small reactor designs for passive heat removal from the reactor core. This paper presents the application of heat pipes in AECL's Nuclear Battery design, a small reactor concept developed by AECL. Other potential applications of heat pipes include transferring excess heat from containment to the atmosphere by integrating low-temperature heat pipes into the containment building (to ensure long-term cooling following a station blackout), and passively cooling spent fuel bays. (author)

  2. (Shippingport Atomic Power Station). Quarterly operating report, third quarter 1980

    Energy Technology Data Exchange (ETDEWEB)

    Zagorski, J. F.

    1980-01-01

    At the beginning of the third quarter of 1980, the Shippingport Atomic Power Station was operating with the 1A, 1B, 1C, and 1D reactor coolant loops and the 1AC and 1BD purification loops in service. During the quarter, the Station was operated for Duquesne Light Company System grid including base load and swing load operation. Twelve (12) planned swing load operations were performed on the LWBR Core this quarter to complete the LWBR operating plan of fifty (50) during this operating phase. The Station was shutdown on September 12 for the Fall 1980 Shutdown and remained in this mode through the end of the quarter. The LWBR Core has generated 18,297.98 EFPH from start-up through the end of the quarter. There were no radioactive liquid discharges from the Radioactive Waste Processing System to the river this quarter. The radioactive liquid waste effluent line to the river remained blanked off to prevent inadvertent radioactive liquid waste discharges. During the quarter, approximately 0.001 curies of Xe 133 activity were released from the station. The radioactivity released from Shippingport Station is far too small to have any measurable effect on the general background environmental radioactivity outside the plant.

  3. Considerations of the opinions and others in the public hearing on the alteration in reactor installation (addition of Unit 3) in the Hamaoka Nuclear Power Station of the Chubu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1982-01-01

    A public hearing was held in Hamaoka Town, Shizuoka Prefecture, on the alteration in reactor installation, i.e., the addition of Unit 3 in the Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc., on March 19, 1981, by the Nuclear Safety Commission. The opinions and others stated by the local people were taken into consideration in the governmental examinations on the installation, etc. The considerations of such opinions principally in the examinations by NSC are explained in the form of questions (i.e. opinion, etc.) and answers (i.e. considerations) as follows: site conditions (earthquakes, ground, hydraulic features, etc.), the safety design of the reactor facilities (overall plant, aseismic design, the control of inflammable gas concentration, radioactive waste treatment, the reflection of accident experiences, etc.), radioactive waste management, radiation exposure relation, the technical capabilities of personnel (operation, etc.). (J.P.N.)

  4. Full scale reactor safety experiments performed in the Marviken Power Station Sweden

    International Nuclear Information System (INIS)

    Thoren, H.G.; Ericson, L.

    1977-01-01

    Since 1972 experiments oriented towards increasing the understanding of reactor safety processes have been performed at the Marviken Power Station. This was originally built as a direct cycle BHWR but was never taken into nuclear operation. In addition to Sweden, the countries represented in these experiments are Denmark, the Federal Republic of Germany, Finland, Norway, the United States, the Netherlands, France and Japan. The first series of sixteen experiments included studies of the response of the PS-containment to simulated ruptures in the pipe systems that are connected to the pressure vessel. These tests were completed in 1973 and also included experimental studies of iodine transport, containment leakage, the behaviour of auxiliary components under accident conditions and pressure fluctuations in the wetwell water pool. One of the more essential findings of the tests was that the containment performance was in accordance with the pre-test calculations. A second series of eight blowdown tests was begun in February 1976. The main purpose of these tests is to provide additional information as to the characteristics of the pressure oscillations inside the containment and primarily in the wetwell water pool under different conditions. These oscillations were observed in the first series of blowdowns but only low frequencies could then be detected due to limitations in the measurement system. The measurement system was therefore substantially extended for this second series of experiments. A summary of the results from these two sets of blowdown tests are given in the paper. In 1976 preparations for a new test program were initiated. The objective of these tests is to improve the understanding of critical flow in the low quality and subcooled flow regions through short length, large diameter pipes. Extensive modifications of the test facility will be necessary in order to allow a discharge flow through openings which are up to 500 mm in diameter. Advanced plans

  5. Nuclear reactor system for ABWR

    International Nuclear Information System (INIS)

    Miyano, Hiroshi; Kitagawa, Koji

    1997-01-01

    Various tests and measurements were performed during the pre-operational test run of Unit No. 6 of The Tokyo Electric Power Co., Inc.'s Kashiwazaki-Kariwa Nuclear Power Station, the first advanced boiling water reactor (ABWR) unit in the world, and the design and performance adequacy of the ABWR were confirmed. The realization of the ABWR in Japan took about 20 years. It was decided that technologies for the reactor internal pump (RIP) and the fine-motion control rod drive (FMCRD), which had been applied in Europe, would be incorporated in the ABWR aiming at simplification of its structure and operation. These main components were evaluated, modified and verified in consideration of the unique Japanese environment, such as seismic conditions, through a joint study program with Japanese utilities as well as an improvement and standardization program in cooperation with the government. In addition to incorporating RIP and FMCRD technologies, the ABWR also has improved features in terms of the design of the reactor pressure vessel and internals, as well as automated servicing equipment for the RIP, FMCRD, and primary containment vessel. (author)

  6. Capital cost: pressurized water reactor plant. Commerical electric power cost studies

    International Nuclear Information System (INIS)

    1977-06-01

    The investment cost study for the 1139-MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume includes in addition to the foreword and summary, the plant description and the detailed cost estimate

  7. Annual progress report for 1982 of Theoretical Reactor Physics Section

    International Nuclear Information System (INIS)

    Rastogi, B.P.; Kumar, Vinod

    1983-01-01

    The progress of work done in the Theoretical Reactor Physics Section of the Bhabha Atomic Research Centre, Bombay, during the calendar year 1982 is reported in the form of write-ups and summaries. The main thrust of the work has been to master the neutronic design technology of four different types of nuclear reactor types, namely, pressurized heavy water reactors, boiling light water reactors, pressurized light water reactors and fast breeder reactors. The development work for the neutronic analysis, fuel design, and fuel management of the BWR type reactors of the Tarapur Atomic Power Station has been completed. A new reactor simulator system for PHWR design analysis and core follow-up was completed. Three dimensional static analysis codes based on nodal and finite element methods for the design work of larger size (500-750 MWe) reactors have been developed. Space link kinetics codes in one, two and three dimensions for above-mentioned reactor systems have been written and validated. Fast reactor core disruptive analysis codes have been developed. In the course of R and D work concerning various types of reactor projects, investigations were also carried in the allied areas of Monte Carlo techniques, integral transform methods, path integral methods, high spin states in heavy nuclei and a hydrodynamics model for a laser driven fusion system. (M.G.B.)

  8. MELCOR simulation of long-term station blackout at Peach Bottom

    International Nuclear Information System (INIS)

    Madni, I.K.

    1990-01-01

    This paper presents the results from MELCOR (Version 1.8BC) calculations of the Long-Term Station Blackout Accident Sequence, with failure to depressurize the reactor vessel, at the Peach Bottom (BWR Mark I) plant, and presents comparisons with Source Term Code Package (STCP) calculations of the same sequence. This sequence assumes that batteries are available for six hours following loss of all power to the plant. Following battery failure, the reactor coolant system (RCS) inventory is boiled off through the relief valves by continued decay heat generation. This leads to core uncovery, heatup, clad oxidation, core degradation, relocation, and, eventually, vessel failure at high pressure. STCP has calculated the transient out to 13.5 hours after core uncovery. The results include the timing of key events, pressure and temperature response in the reactor vessel and containment, hydrogen production, and the release of source terms to the environment. 12 refs., 23 figs., 3 tabs

  9. Allowable Residual Contamination Levels in soil for decommissioning the Shippingport Atomic Power Station site

    International Nuclear Information System (INIS)

    Kennedy, W.E. Jr.; Napier, B.A.; Soldat, J.K.

    1983-09-01

    As part of decommissioning the Shippingport Atomic Power Station, a fundamental concern is the determination of Allowable Residual Contamination Levels (ARCL) for radionuclides in the soil at the site. The ARCL method described in this report is based on a scenario/exposure-pathway analysis and compliance with an annual dose limit for unrestricted use of the land after decommissioning. In addition to naturally occurring radionuclides and fallout from weapons testing, soil contamination could potentially come from five other sources. These include operation of the Shippingport Station as a pressurized water reactor, operations of the Shippingport Station as a light-water breeder, operation of the nearby Beaver Valley reactors, releases during decommissioning, and operation of other nearby industries, including the Bruce-Mansfield coal-fired power plants. ARCL values are presented for 29 individual radionculides and a worksheet is provided so that ARCL values can be determined for any mixture of the individual radionuclides for any annual dose limit selected. In addition, a worksheet is provided for calculating present time soil concentration value that will decay to the ARCL values after any selected period of time, such as would occur during a period of restricted access. The ARCL results are presented for both unconfined (surface) and confined (subsurface) soil contamination. The ARCL method and results described in this report provide a flexible means of determining unrestricted-use site release conditions after decommissioning the Shippingport Atomic Power Station

  10. The development of the breeder reactor program of the German Federal Republic

    International Nuclear Information System (INIS)

    Haunschild, H.H.

    1984-01-01

    This article recapitulates the stages of the program which is in hand in the German Federal Republic concerning breeder reactors with fast neutrons. In particular, it describes in detail the causes for the delays in the construction of the demonstration reactor SRN 300 (Kalkar) for which the commissioning has now been fixed for 1987. It emphasizes the importance of the collaboration which exists in Europe for the establishment of the projects and the construction of fast neutron power stations, including the SNR 2 reactor; the construction of the latter could begin in the German Federal Republic at the end of the Eighties [fr

  11. The development of criteria for the design of insulation for nuclear reactors

    International Nuclear Information System (INIS)

    Furber, B.N.; Hopkins, I.H.G.; Stuart, R.A.

    1976-01-01

    In 1960 when the early design studies for the Oldbury Power Station were being carried out the use of insulation in a reactor environment was quite novel. No manufacturer had previous experience of this particular application of insulation. The paper describes the work carried out to establish the design criteria for Magnox and subsequent Advanced Gas Cooled Reactors (AGR) and indicates some of the new problems of the High Temperature Reactor (HTR). Unless otherwise stated the work was carried out by The Nuclear Power Group Ltd. (TNPG) and the conclusions express the present thinking of that Company. (author)

  12. Future plans for the design and construction of fast reactor power stations in Italy

    International Nuclear Information System (INIS)

    Castelli, G.; Ghilardotti, G.

    1978-01-01

    Studies related to fast reactor technology have been pursued in Italy for a long time and this country is now deeply engaged in the demonstration and marketing phases, in accordance with the outlines of the Italian national energy plan. In the paper the following topics are examined: current possibilities for introducing fast reactors in Italy; the main social and political constraints concerning their introduction; the necessary industrial and organizational structures (in the broadest meaning) existing or foreseen; the national programme pertaining to activities towards achieving this goal. (author)

  13. Operating experience with nuclear power stations in Member States in 1997

    International Nuclear Information System (INIS)

    1998-12-01

    This report is twenty-ninth in the IAEA series of annual reports on operating experience with nuclear power stations in Member States. The report is a direct output from the Agency's Power Reactor Information System (PRIS), whose database contains all operating experience data published in Agency's operating experience annual reports published since 1971 and basic information on power reactors, including design data. According to the information available to the Agency at the end of 1997, there were 437 nuclear power reactors having a total capacity of 351795 MW(e). During 1997 three new reactors having total capacity of 3555 MW(e) were connected to the grid in France and the Republic of Korea. There were 36 nuclear power plants under construction in the world. Load, operation and availability factors are used as the basic performance factors. In addition to annual performance data and outage information, the report contains a historical summary of performance and outages during the lifetime of individual plants and five figures illustrating worldwide performance and statistical data

  14. Fuel development for reactors of new generation in Ukraine

    International Nuclear Information System (INIS)

    Odeychuk, N.P.

    2006-01-01

    Full text: On the background of critical situation in traditional power engineering due to deficiency of organic fuel, physical and moral ageing of the of thermal power stations equipment and their harmful influence on the ecology of environment, the nuclear engineering works stably enough and, by keeping all safety measures, is the most non-polluting energy source. In Ukraine the atomic engineering became one of main sources of energy production and is the important factor of guarantee the power engineering independence of the state. The main center on development of the components of nuclear reactors active zones is the National scientific center K harkov institute of Physics and Technology . The significant place in institutes' investigations was occupied with works on creation the constructional materials and nuclear fuel for heavy water reactors E-circumflexS-150, OR-1000, OR-2000, light water reactors WWER-1000 and RBMK-1500, high-temperature gas cooled reactors ABTU and HTGR, gas reactors on fast neutrons BGR and BRGD, and also the reactor - converter ROMASHKA and other special reactors of special assignment. Radiation tests and post-irradiation research confirm intended material-study, technological and design decisions and fuel elements capacity work on the whole. Nevertheless, by the present conditions, it is necessary to pay special attention to development of the new, safe guaranteed nuclear energy sources. In Ukraine proceed works on research and development of new safe nuclear reactors: basing the underground nuclear thermal power stations; development the reactors with managed chain reaction of nucleus division in an active zone with the help of an external source of neutrons; power thermonuclear installations; high-temperature helium reactors which are especially actual now from the point of view of the hydrogen production; the advanced pressure water reactors, heavy water reactors. In the paper also discussed the state of works in Ukraine on fuel

  15. Reactivity monitoring for safety purposes on the UK prototype fast reactor

    International Nuclear Information System (INIS)

    Lord, D.J.; Wilkes, D.J.

    1987-01-01

    The small size and high rating of the liquid metal cooled fast breeder reactor (LMFBR) make the provision of safety related instrumentation for individual subassemblies both difficult and expensive. Global monitoring of the core is thus very attractive. Reactivity monitoring is an important part of such global monitoring. Reactivity monitoring on a short timescale (a few seconds) is used on the UK Prototype Fast Reactor (PFR) as a trip parameter and long-term reactivity monitoring is being developed as a means of providing early warning of slowly developing faults. Results are presented from PFR to demonstrate the capabilities of reactivity monitoring in an operational fast reactor power station. (author)

  16. Decontamination of the Douglas Point reactor, May 1983

    International Nuclear Information System (INIS)

    Lesurf, J.E.; Stepaniak, R.; Broad, L.G.; Barber, W.G.

    1983-01-01

    The Douglas Point reactor primary heat transport system including the fuel, was successfully decontaminated by the CAN-DECON process in 1975. A second decontamination, also using the CAN-DECON process, was successfully performed in May 1983. This paper outlines the need for the decontamination, the process used, the results obtained, and the benefits to the station maintenance and operation

  17. Spallation radiation damage and the radiation damage facility at the LAMPF A-6 target station

    Energy Technology Data Exchange (ETDEWEB)

    Wechsler, M.S.; Sommer, W.F. (Los Alamos National Lab., NM (USA))

    1984-05-01

    A redesign of the Clinton P. Anderson Los Alamos Meson Physics Facility (LAMPF) A-6 Target Station is underway that will permit materials irradiations to be conducted in the proton beam and in the spallation neutron environment under more controlled conditions than has been possible heretofore. The protons of energy near 800 MeV and beam current approaching one mA are able to produce radiation damage rates (displacement production rates) as high as can be achieved in fission reactors, and the damage is uniform over macroscopic dimensions. The spallation neutrons have a degraded fission spectrum energy distribution, with the important admixture of a high energy tail up to 800 MeV. Irradiations in these radiation environments can be used to address important problems in the development of materials for fusion reactors. The redesign of the A-6 Target Station is described and plans for its use are discussed.

  18. Radiation protection considerations in space station missions

    International Nuclear Information System (INIS)

    Peddicord, K.L.; Bolch, W.E.

    1991-01-01

    The National Aeronautics and Space Administration (NASA) is currently studying the degree to which the baseline design of space station Freedom (SSF) would permit its evolution to a transportation node for lunar or Mars expeditions. To accomplish NASA's more ambitious exploration goals, nuclear-powered vehicles could be used in SSF's vicinity. This enhanced radiation environment around SSF could necessitate additional crew shielding to maintain cumulative doses below recommended limits. This paper presents analysis of radiation doses received upon the return and subsequent unloading of Mars vehicles utilizing either nuclear electric propulsion (NEP) or nuclear thermal rocket (NTR) propulsion systems. No inherent shielding by the vehicle structure or space station is assumed; consequently, the only operational parameters available to control radiation doses are the source-to-target distance and the reactor shutdown time prior to the exposure period. For the operations planning, estimated doses are shown with respect to recommended dose limits and doses due solely to the natural space environment in low Earth orbit

  19. Development of Advanced Monitoring System with Reactor Neutrino Detection Technique for Verification of Reactor Operations

    International Nuclear Information System (INIS)

    Furuta, H.; Tadokoro, H.; Imura, A.; Furuta, Y.; Suekane, F.

    2010-01-01

    Recently, technique of Gadolinium-loaded liquid scintillator (Gd-LS) for reactor neutrino oscillation experiments has attracted attention as a monitor of reactor operation and ''nuclear Gain (GA)'' for IAEA safeguards. When the thermal operation power is known, it is, in principle, possible to non-destructively measure the ratio of Pu/U in reactor fuel under operation from the reactor neutrino flux. An experimental program led by Lawrence Livermore National Laboratory and Sandia National Laboratories in USA has already demonstrated feasibility of the reactor monitoring by neutrinos at San Onofre Nuclear Power Station, and the Pu monitoring by neutrino detection is recognized as a candidate of novel technology to detect undeclared operation of reactor. However, further R and D studies of detector design and materials are still necessary to realize compact and mobile detector for practical use of neutrino detector. Considering the neutrino interaction cross-section and compact detector size, the detector must be set at a short distance (a few tens of meters) from reactor core to accumulate enough statistics for monitoring. In addition, although previous reactor neutrino experiments were performed at underground to reduce cosmic ray muon background, feasibility of the measurement at ground level is required for the monitor considering limited access to the reactor site. Therefore, the detector must be designed to be able to reduce external backgrounds extremely without huge shields at ground level, eg. cosmic ray muons and fast neutrons. We constructed a 0.76 ton Gd-LS detector, and carried out a reactor neutrino measurement at the experimental fast reactor JOYO in 2007. The neutrino detector was set up at 24.3m away from the reactor core at the ground level, and we understood the property of the main background; the cosmic-ray induced fast neutron, well. Based on the experience, we are constructing a new detector for the next experiment. The detector is a Gd

  20. Principles, design and fuel performance characteristics of gas cooled thermal reactors

    International Nuclear Information System (INIS)

    Boocock, P.M.; Eaton, J.R.P.

    1989-01-01

    Reactor output and availability are closely related to fuel design and performance and the SSEB, in collaboration with the Central Electricity Generating Board have followed a policy of continuous analysis and improvement. The position reached is set out and some views on further improvements, are given. The strategy of increasing fuel burn-up on Hunterston A power station has brought significant dividends in the form of major benefits in fuel cycle cost and station availability. Significant improvements in output and availability at Hunterston B have resulted from increasing the fuel cycle burn-up, from 18 GWd/t U to 21 GWd/t U and introducing on-load refuelling. Additional benefits are soon to be obtained by further extending the burn-up to 24 GWd/t U. Further reduction of typically Pound 2-7 million/year in fuel cycle costs over the remaining life of the stations would be made by extending the burn-up to 30 GWd/t U at Hunterston B and Torness. There would be additional savings of about Pound 4 million/year in replacement fuel costs if the reactors continued to be refuelled at 30% power at Hunterston B and 40% power at Torness. (author)

  1. A Review of Past Reactor Progress in the UK, April 1975

    International Nuclear Information System (INIS)

    Smith, R.D.

    1975-01-01

    The fast reactor project in the UK is continuing at approximately the same scale of effort as last year, with great attention being paid to overcoming the difficulties being met in raising PFR to full power. Organisational arrangements for nuclear power in the UK during the year have been dominated by two interlinked issues, firstly the choice of thermal reactor system for the next stage of the British nuclear power programme, and secondly the consolidation of the British nuclear design and construction industry. On the former, widespread discussion on the merits of alternative thermal systems culminated in the announcement by the Secretary of State for Energy on 10 July 1974 that the British electricity boards would adopt the SGHWR for their next nuclear power station orders. The initial ordering programme was set at 4000 KW(E) over the next four years, with the prospect of extending the programme in the later 1970s given satisfactory initial experience of construction. Consent has now been given by the Department of Energy to the CEGB for an SGHWR station at Sizewell in Suffolk (adjacent to an existing Magnox station) and to the SSEB for one at Torness Point in East Lothian

  2. Cooling methods of station blackout scenario for LWR plants

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-08-15

    The objective of this study is to analyze the cooling method of station blackout scenario for both the BWR and PWR plants by RELAP5 code and to check the validity of the cooling method proposed by the utilities. In the BWR plant cooling scenario, the Reactor Core Isolation Cooling System (RCIC), which is operated with high pressure steam from the reactor, injects cooling water into the reactor to keep the core water level. The steam generated in the core is released into the suppression pool at containment vessel to condense. To restrict the containment vessel pressure rising, the ventilation from the wet-well is operated. The scenario is analyzed by RELAP5 code. In the PWR plant scenario, the primary pressure is decreased by the turbine-driven auxiliary feed water system operated with secondary side steam of the steam generators (SGs). And the core cooling is kept by the natural circulation flow at the primary loop. From the RELAP5 code analysis, it was shown that the primary system cooling was practicable by using the turbine-driven auxiliary feed water system. (author)

  3. Cooling methods of station blackout scenario for LWR plants

    International Nuclear Information System (INIS)

    2012-01-01

    The objective of this study is to analyze the cooling method of station blackout scenario for both the BWR and PWR plants by RELAP5 code and to check the validity of the cooling method proposed by the utilities. In the BWR plant cooling scenario, the Reactor Core Isolation Cooling System (RCIC), which is operated with high pressure steam from the reactor, injects cooling water into the reactor to keep the core water level. The steam generated in the core is released into the suppression pool at containment vessel to condense. To restrict the containment vessel pressure rising, the ventilation from the wet-well is operated. The scenario is analyzed by RELAP5 and CONTEMPT-LT code. In the PWR plant scenario, the primary pressure is decreased by the turbine-driven auxiliary feed water system operated with secondary side steam of the steam generators (SGs). And the core cooling is kept by the natural circulation flow at the primary loop. The analytical method of un-uniform flow behavior among the SG U-tubes, which affects the natural circulation flow rate, is developed. (author)

  4. Present status of maintenance in nuclear power stations

    International Nuclear Information System (INIS)

    Fueki, Kensuke

    1982-01-01

    For nuclear power stations, the improvement of the rate of facility utilization is indispensable. As its means, the shortening of regular inspection period, the adoption of long term cycle operation, the shortening of plant shutdown period by the improvement of the reliability of installed equipment and so on are conceivable. In this paper, the maintenance techniques in nuclear power stations which constitute the basis of reliability improvement are explained. In nuclear power stations, the use of nuclear fuel, accordingly the existence of radioactivity are the remarkable features. At the time of an accident, the nuclear reaction in a reactor must be stopped, and the excessive heat must be removed. The radioactivity in nuclear fuel must not be released outside. The regular inspection of once a year is provided by the law, and routine tests are performed during normal operation. The check-up by operators also is a part of the safety measures. For the early detection of abnormality, the diagnosis system is developed, and the maintenance techniques during operation are examined for being taken into the safety test and standard. The improvement of reliability is attempted by the redundancy of systems. The activity of quality assurance, the organization for the maintenance of nuclear power stations and maintenance works, and the measures to raise the rate of operation are reported. (Kako, I.)

  5. Cobalt-60 control in Ontario Hydro reactors

    International Nuclear Information System (INIS)

    Lacy, C.S.

    1988-01-01

    This paper discusses the impact of specifying reduced Cobalt-59 in the primary heat transport circuit materials of construction on the radiation fields developed around the primary circuit. An eight-fold reduction in steam generator radiation fields due to Cobalt-60 has been observed for two identical sets of reactors, one with and one without Cobalt-59 control. The comparison is between eight reactors at the Pickering Nuclear Generating Station (PNGS). Units 5 to 8 (PNGS-B) are identical to Units 1 to 4 (PNGS-A) except that PNGS-B has reduced impurity Cobalt-59 in the alloys of construction and a reduced use of stellite. The effects of chemistry control are also discussed

  6. k{sub 0}-INAA method at the pneumatic station of the IEA-R1 nuclear research reactor. Application to geological samples

    Energy Technology Data Exchange (ETDEWEB)

    Mariano, Davi B.; Figueiredo, Ana Maria G.; Semmler, Renato, E-mail: davimariano@usp.br, E-mail: anamaria@ipen.br, E-mail: rsemmler@ipen.br [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil)

    2011-07-01

    There is a significant number of analytically important elements, when geological samples are concerned, whose activation products are short-lived (seconds to minutes) or medium-lived radioisotopes (minutes to hours). As part of the process of implementation of the k{sub 0}-INAA standardization method at the Neutron Activation Laboratory (LAN-IPEN), Sao Paulo, Brazil, this study presents the results obtained for the analysis of short and medium-lived nuclides in geological samples by k{sub 0}-INAA using the program k{sub 0}-IAEA, provided by The International Atomic Energy Agency (IAEA). The elements Al, Dy, Eu, Na, K, Mn, Mg, Sr, V and Ti were determined with respect to gold ({sup 197}Au) using the pneumatic station facility of the IEA-R1 5 MW swimming pool nuclear research reactor, Sao Paulo. Characterization of the pneumatic station was carried out by using the -bare triple-monitor- method with {sup 197}Au-{sup 96}Zr-{sup 94}Zr. The Certified Reference Material IRMM-530R Al-0,1% Au alloy, high purity zirconium, Ni and Lu comparators were irradiated. The efficiency curves of the gamma-ray spectrometer used were determined by measuring calibrated radioactive sources at the usually utilized counting geometries. The method was validated by analyzing the reference materials basalt BE-N (IWG-GIT), basalt JB- 1 (GSJ), andesite AGV-1 (USGS), granite GS-N (IWG-GIT), SOIL-7 (IAEA) and sediment Buffalo River Sediment (NIST-BRS-8704), which represent different geological matrices. The concentration results obtained agreed with certified, reference and recommended values, showing relative errors less than 10% for most elements. (author)

  7. HTGR Metallic Reactor Internals Core Shell Cutting & Machining Antideformation Technique Study

    International Nuclear Information System (INIS)

    Xing Huiping; Xue Song

    2014-01-01

    The reactor shell assembly of HTGR nuclear power station demonstration project metallic reactor internals is key components of reactor, remains with high-precision large component with large-sized thin-walled straight cylinder-shaped structure, and is the first manufacture in China. As compared with other reactor shell, it has a larger ID (Φ5360mm), a longer length (19000mm), a smaller wall thickness (40mm) and a higher precision requirement. During the process of manufacture, the deformation due to cutting & machining will directly affect the final result of manufacture, the control of structural deformation and cutting deformation shall be throughout total manufacture process of such assembly. To realize the control of entire core shell assembly geometry, the key is to innovate and make breakthroughs on anti-deformation technique and then provide reliable technological foundations for the manufacture of HTGR metallic reactor internals. (author)

  8. Possibilities of optimizing non-nuclear simulation of pressurized water reactor transients

    International Nuclear Information System (INIS)

    Silva Filho, E.

    1985-01-01

    The GKSS-Forschungszentrum Geesthacht GmbH has instituted the concept of a scaled test facility (volume scale factor of 1/100) of a typical PWR of the 1 300 MWe class for the purpose of studying small breaks Loss-of-Coolant Accidents (LOCA) and transients. Having in mind the goal of an optimization of this concept has been choosen a station blackout with and without reactor shutdown and a small break LOCA in a primary loop piping to investigate the thermohydraulic behaviour of the test facility in comparison to the reactor plant. The computer code RELAP 5/MOD 1 has been utilized to compare the test facility behaviour with the reactor plant one. Recommendations are given for minimization of distortions between test facility and reactor plant. (orig./HP) [de

  9. Neutron radiography (NRAD) reactor 64-element core upgrade

    Energy Technology Data Exchange (ETDEWEB)

    Bess, John D. [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-03-01

    The neutron radiography (NRAD) reactor is a 250 kW TRIGA (registered) (Training, Research, Isotopes, General Atomics) Mark II , tank-type research reactor currently located in the basement, below the main hot cell, of the Hot Fuel Examination Facility (HFEF) at the Idaho National Laboratory (INL). It is equipped with two beam tubes with separate radiography stations for the performance of neutron radiography irradiation on small test components. The interim critical configuration developed during the core upgrade, which contains only 62 fuel elements, has been evaluated as an acceptable benchmark experiment. The final 64-fuel-element operational core configuration of the NRAD LEU TRIGA reactor has also been evaluated as an acceptable benchmark experiment. Calculated eigenvalues differ significantly (approximately ±1%) from the benchmark eigenvalue and have demonstrated sensitivity to the thermal scattering treatment of hydrogen in the U-Er-Zr-H fuel.

  10. Comparison of control systems applied to the handling of radioactive reactor components

    International Nuclear Information System (INIS)

    Robinson, C.; Harris, E.G.; Dyer, P.C.; Williams, J.G.B.

    1985-01-01

    The first generation of nuclear power stations have individual reactors each incorporating complete facilities for servicing components and refuelling. In the later designs, each power station has two reactors which are connected by a central block. This central block contains one set of facilities to service both reactors, but to improve the station capability, some of these are to be replicated. The central block incorporates a hoist well which was used during construction for the accessing of complete components. On completion of this work, the physical size of the hoist well is such as to permit the incorporation of additional facilities if these are shown to be operationally and economically desirable. Since a number of years of power operation has elapsed, the advantages of back-fitting to existing fuel-handling facilities has been illustrated. Since the mechanical arrangements and operating procedures are substantially similar for both the original and new handling facilities, the paper will illustrate the control systems provided for each. The configuration of the system is arranged to have two channels of control which complies with the current standard requirements in the United Kingdom. These requirements are more stringent than when the existing facility was designed and constructed, as described in the relevant sections of the paper. The new system has been designed and is being manufactured to comply with the Central Electricity Generating Board standard for nuclear fuel route interlock and control systems. (author)

  11. The energy gap and the fast reactor

    International Nuclear Information System (INIS)

    Hill, J.

    1977-01-01

    The background to the development of fast reactors is summarized. In Britain, the results of the many experiments performed, the operation of the Dounreay Fast Reactor for the past 18 years and the first year's operation of the larger Prototype Fast Reactor have all been very encouraging, in that they demonstrated that the performance corresponded well with predictions, breeding is possible, and the system is exceptionally stable in operation. The next step in fast reactor engineering is to build a full-scale fast reactor power station. There would seem to be little reason to expect more trouble than could reasonably be expected in constructing any large project of this general nature. However, from an engineering point of view continuity of experience is required. If a decision to build a commercial fast reactor were taken today there would be a 14-year gap between strating this and the start of the Prototype Fast Reactor. This is already much too long. From an environmental standpoint we have to demonstrate that we can manufacture and reprocess fast reacctor fuel for a substantial programme in a way that does not lead to pollution of the environment, and that plutonium-containing fuel can be transported in the quantities required in safety and in a way that does not attract terrorists or require a private army to ensure its security. Finally, we have to find a way to allow many countries to obtain the energy they need from fast reactors, without leading to the proliferation of nuclear weapons or weapons capability. (author)

  12. Modular Stellarator Fusion Reactor concept

    International Nuclear Information System (INIS)

    Miller, R.L.; Krakowski, R.A.

    1981-08-01

    A preliminary conceptual study is made of the Modular Stellarator Reactor (MSR). A steady-state ignited, DT-fueled, magnetic fusion reactor is proposed for use as a central electric-power station. The MSR concept combines the physics of the classic stellarator confinement topology with an innovative, modular-coil design. Parametric tradeoff calculations are described, leading to the selection of an interim design point for a 4-GWt plant based on Alcator transport scaling and an average beta value of 0.04 in an l = 2 system with a plasma aspect ratio of 11. The physics basis of the design point is described together with supporting magnetics, coil-force, and stress computations. The approach and results presented herein will be modified in the course of ongoing work to form a firmer basis for a detailed conceptual design of the MSR

  13. Standard concerning the design of nuclear power stations in earthquake-prone districts

    International Nuclear Information System (INIS)

    Kirillov, A.P.; Anbriashivili, Y.K.; Suvilova, A.V.

    1980-01-01

    The measures of security assurance against the effect of radioactive contamination has become more and more complex due to the construction of nuclear power stations of diverse types. The aseismatic measures for the nuclear power stations built in the districts where earthquakes of different intensity occur are important problems. All main machinery and equipments and emergency systems in power stations must be protected from earthquakes, and this makes the solution of problems difficult. At present in USSR, the provisional standard concerning the design of atomic energy facilities built in earthquake-prone districts is completed. The basic philosophy of the standard is to decide the general requirements as the conditions for the design of nuclear power stations built in earthquake-prone districts. The lowest earthquake activity in the construction districts is considered as magnitude 4, and in the districts where earthquake activity is magnitude 9 or more, the construction of nuclear power stations is prohibited. Two levels of earthquake action are specified for the design: design earthquake and the largest design earthquake. The construction sites of nuclear power stations must be 15 to 150 km distant from the potential sources of earthquakes. Nuclear power stations are regarded as the aseismatically guaranteed type when the safety of reactors is secured under the application of the standard. The buildings and installations are classified into three classes regarding the aseismatic properties. (Kako, I.)

  14. Technical water system of the Reactor - Design description, operation regime and manipulation

    International Nuclear Information System (INIS)

    Badrljica, R.

    1984-05-01

    Technical water, reactor secondary coolant system is made of four parts: pumping station on the Danube; sedimentation facility in the village Vinca; coolant, heat exchangers and other elements within the RA reactor building; leading outer pipes and the stream Mlaka. All the four parts are connected to form a functional entirety, and each of them connected to cooling heat exchangers forms a partial functional system which enable the whole system to fulfill its fundamental task [sr

  15. Research and development activities for reactor decommissioning. Developing technology of Fuji Electric Co., Ltd

    International Nuclear Information System (INIS)

    Shirakawa, Masahiro; Takaya, Jyunichi; Mizukoshi, Seiji; Hosoda, Hiroshi; Tomizuka, Chiaki; Funaguchi, Susumu; Ito, Katsuhito

    1997-01-01

    Fuji Electric Co., Ltd. is conducting decommissioning R and D for commercial reactor, especially for gas cooled reactor since the construction of the Tokai-1 power station of JAPCO, in the field of system engineering, residual radioactivity evaluation, dismantling of core internals, remote handling, treatment and disposal of radioactive waste, and radioactivity measurement. These R and D have been performed mainly under contract of JAPCO and JAERI. This paper gives a summary of the present status and future plan concerning technical development for decommissioning of nuclear reactor by Fuji Electric Co., Ltd. (author)

  16. The present status of the fast breeder reactor industrialization in western Europe

    International Nuclear Information System (INIS)

    Dievoet, J.P. van

    1987-01-01

    The development of the liquid metal fast breeder reactor in Europe started in the mid-fifties, after the successful operation of EBR-1 at ARCO, Idaho, in 1951. A more and more integrated development among the countries of the European Community culminated in 1986 with the beginning to power of the 1200 MWe SUPERPHENIX plant at Creys-Malville, France. The road is now open towards the full industrialization of the liquid metal fast breeder reactor at the moment, in 2005, when the first European thermal neutron power reactor station will have to be decommissioned and replaced. The European programme aims at providing the utilities at that time with a clear choice between thermal neutron reactors and fast breeder reactors, both economical but very different in their use of the limited natural resource that uranium is. (author)

  17. IRSN-ANCCLI partnership. IRSN-ANCCLI seminar on decennial inspections of 900 MWe reactors - November 2010

    International Nuclear Information System (INIS)

    Rollinger, Francois; Delalonde, Jean-Claude; Hubert, F.; Paulmaz, X.; Tindillere, M.; Lheureux, Y.; Junker, R.; Sene, M.

    2010-11-01

    This seminar addressed the commitment of local information commissions (CLI) in the analysis and follow-up of the third decennial inspections of the French 900 MWe nuclear reactors. A first session addressed topics directly related to these inspections. Contributions proposed under the form of Power Point presentations by experts and representatives of the IRSN, EDF and CLIs addressed the following issues: safety re-examination of EDF 900 MWe reactors at the occasion of the third decennial inspection, activities of the IRSN related to skill management in nuclear power stations, implementation of the third decennial inspection of the unit 1 of the Fessenheim nuclear power station, the issue of follow-up by a local information commission after a decennial inspection. A second session addressed topics not related to decennial inspections and were proposed by Gravelines and Dampierre local information commissions: analysis of significant safety events, issues of skill management in nuclear power stations

  18. Structural design of nuclear reactor machinery and equipment

    International Nuclear Information System (INIS)

    Hara, Hideki

    1992-01-01

    Since the machinery, equipment and piping which compose nuclear power station facilities are diverse, when those are designed, consideration is given sufficiently to the objective of use and the importance of the object machinery and equipment so that those can maintain the soundness over the design life. In this report, on the contents and the design standard in the design techniques for nuclear reactor machinery and equipment, the way of thinking is shown, taking an example of reactor pressure vessel which is stipulated as the vessel kind 1 in the 'Technical standard of structures and others regarding nuclear facilities for electric power generation', Notice No. 501 of the Ministry of International Trade and Industry. The reactor pressure vessel of 1350 MWe improved type BWR (ABWR) is used under the condition of 87.9 kg/cm 2 and 302 degC, and the inside diameter is about 7.2 m, the inside height is about 21 m, and the wall thickness is about 170 mm. The design standard for reactor pressure vessels and its way of thinking, breakdown prevention design and the design techniques for reactor pressure vessels are described. (K.I.)

  19. Status of control assembly materials in Indian water reactors

    International Nuclear Information System (INIS)

    Date, V.G.; Kulkarni, P.G.

    2000-01-01

    India's present operating water cooled power reactors comprise boiling water reactors of Tarapur Atomic Power Station (TAPS) and pressurized heavy water reactors (PHWRs) at Kota (RAPS), Kalpakkam (MAPS), Narora (NAPS) and Kakrapara (KAPS). Boiling water reactors of TAPS use boron carbide control blades for control of power as well as for shut down (scram). PHWRs use boron steel and cobalt absorber rods for power control and Cd sandwiched shut off rods (primary shut down system) and liquid poison rods (secondary shut down system) for shut down. In TAPS, Gadolinium rods (burnable poison rods) are also incorporated in fuel assembly for flux flattening. Boron carbide control blades and Gadolinium rods for TAPS, cobalt absorber rods and shut down assemblies for PHWRs are fabricated indigenously. Considerable development work was carried out for evolving material specifications, component and assembly drawings, and fabrication processes. Details of various control and shut off assemblies being fabricated currently are highlighted in the paper. (author)

  20. Cable condition monitoring in a pressurized water reactor environment

    International Nuclear Information System (INIS)

    Al-Hussaini, T.J.

    1988-01-01

    Oconee Nuclear Station is the first nuclear plant designed, engineered and constructed by Duke Power Company. Even though the accelerated aging method was available to determine the life expectancy of the cable used in the reactor building, no natural aging data was available at that time. In order to be able to verify the condition of the reactor building cable over the life of the plant, an on-going cable monitoring plan was instituted. Various types of cable were selected to be monitored, and they were installed in cable life evaluation circuits in the reactor building. At five year intervals over the life of the plant, cable samples would be removed from these cable life evaluation circuits and tested to determine the effects of the reactor building environment on the integrity of the cable. A review of the cable life evaluation circuits and the results of the evaluation program to date is presented