  1. Preliminary site description Forsmark area - version 1.1

    2004-03-01

    This report presents the interim version (model version 1.1) of the preliminary Site Descriptive Model for Forsmark. The basis for this interim version is quality-assured, geoscientific and ecological field data from Forsmark that were available in the SKB databases SICADA and GIS at April 30, 2003 as well as version 0 of the Site Descriptive Model. The new data acquired during the initial site investigation phase to the date of data freeze 1.1 constitute the basis for the updating of version 0 to version 1.1. These data originate from surface investigations on the candidate area with its regional environment and from drilling and investigations in boreholes. The surface-based data sets were rather extensive whereas the data sets from boreholes were limited to information from one 1,000 m deep cored borehole (KFM01A) and eight 150 to 200 m deep percussion-drilled boreholes in the Forsmark candidate area. Discipline specific models are developed for a selected regional and local model volume and these are then integrated into a site description. The current methodologies for developing the discipline specific models and the integration of these are documented in methodology reports or strategy reports. In the present work, the guidelines given in those reports were followed to the extent possible with the data and information available at the time for data freeze for model version 1.1. Compared with version 0 there are considerable additional features in the version 1.1, especially in the geological description and in the description of the near surface. The geological models of lithology and deformation zones are based on borehole information and much higher resolution surface data. The existence of highly fractured sub-horizontal zones has been verified and these are now part of the model of the deformation zones. A discrete fracture network (DFN) model has also been developed. The rock mechanics model is based on strength information from SFR and an empirical

  2. Preliminary site description Forsmark area - version 1.1

    NONE

    2004-03-01

    This report presents the interim version (model version 1.1) of the preliminary Site Descriptive Model for Forsmark. The basis for this interim version is quality-assured, geoscientific and ecological field data from Forsmark that were available in the SKB databases SICADA and GIS at April 30, 2003 as well as version 0 of the Site Descriptive Model. The new data acquired during the initial site investigation phase to the date of data freeze 1.1 constitute the basis for the updating of version 0 to version 1.1. These data originate from surface investigations on the candidate area with its regional environment and from drilling and investigations in boreholes. The surface-based data sets were rather extensive whereas the data sets from boreholes were limited to information from one 1,000 m deep cored borehole (KFM01A) and eight 150 to 200 m deep percussion-drilled boreholes in the Forsmark candidate area. Discipline specific models are developed for a selected regional and local model volume and these are then integrated into a site description. The current methodologies for developing the discipline specific models and the integration of these are documented in methodology reports or strategy reports. In the present work, the guidelines given in those reports were followed to the extent possible with the data and information available at the time for data freeze for model version 1.1. Compared with version 0 there are considerable additional features in the version 1.1, especially in the geological description and in the description of the near surface. The geological models of lithology and deformation zones are based on borehole information and much higher resolution surface data. The existence of highly fractured sub-horizontal zones has been verified and these are now part of the model of the deformation zones. A discrete fracture network (DFN) model has also been developed. The rock mechanics model is based on strength information from SFR and an empirical

  3. Preliminary site description Forsmark area - version 1.2

    Skagius, Kristina [ed.

    2005-06-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterisation at two different locations, the Forsmark and Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. An integrated component in the characterisation work is the development of a site descriptive model that constitutes a description of the site and its regional setting, covering the current state of the geosphere and the biosphere as well as those ongoing natural processes that affect their long-term evolution. The present report documents the site descriptive modelling activities (version 1.2) for the Forsmark area. The overall objectives of the version 1.2 site descriptive modelling are to produce and document an integrated description of the site and its regional environments based on the site-specific data available from the initial site investigations and to give recommendations on continued investigations. The modelling work is based on primary data, i.e. quality-assured, geoscientific and ecological field data available in the SKB databases SICADA and GIS, available July 31, 2004. The work has been conducted by a project group and associated discipline-specific working groups. The members of the project group represent the disciplines of geology, rock mechanics, thermal properties, hydrogeology, hydrogeochemistry, transport properties and surface ecosystems (including overburden, surface hydrogeochemistry and hydrology). In addition, some group members have specific qualifications of importance in this type of project e.g. expertise in RVS (Rock Visualisation System) modelling, GIS-modelling and in statistical data analysis. The overall strategy to achieve a site description is to develop discipline-specific models by interpretation and analyses of the primary data. The different discipline-specific models are then integrated into a site description. Methodologies for developing the discipline-specific models are documented in

  4. Preliminary site description Forsmark area - version 1.2

    Skagius, Kristina

    2005-06-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterisation at two different locations, the Forsmark and Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. An integrated component in the characterisation work is the development of a site descriptive model that constitutes a description of the site and its regional setting, covering the current state of the geosphere and the biosphere as well as those ongoing natural processes that affect their long-term evolution. The present report documents the site descriptive modelling activities (version 1.2) for the Forsmark area. The overall objectives of the version 1.2 site descriptive modelling are to produce and document an integrated description of the site and its regional environments based on the site-specific data available from the initial site investigations and to give recommendations on continued investigations. The modelling work is based on primary data, i.e. quality-assured, geoscientific and ecological field data available in the SKB databases SICADA and GIS, available July 31, 2004. The work has been conducted by a project group and associated discipline-specific working groups. The members of the project group represent the disciplines of geology, rock mechanics, thermal properties, hydrogeology, hydrogeochemistry, transport properties and surface ecosystems (including overburden, surface hydrogeochemistry and hydrology). In addition, some group members have specific qualifications of importance in this type of project e.g. expertise in RVS (Rock Visualisation System) modelling, GIS-modelling and in statistical data analysis. The overall strategy to achieve a site description is to develop discipline-specific models by interpretation and analyses of the primary data. The different discipline-specific models are then integrated into a site description. Methodologies for developing the discipline-specific models are documented in

  5. Description of surface systems. Preliminary site description. Forsmark area Version 1.2

    Lindborg, Tobias [ed.

    2005-06-01

    Swedish Nuclear Fuel and Waste Management Co (SKB) started site investigations for a deep repository for spent nuclear fuel in 2002 at two different sites in Sweden, Forsmark and Oskarshamn. The investigations should provide necessary information for a license application aimed at starting underground exploration. For this reason, ecosystem data need to be interpreted and assessed into site descriptive models, which in turn are used for safety assessment studies and for environmental impact assessment. Descriptions of the surface system are also needed for further planning of the site investigations. This report describes the surface ecosystems of the Forsmark site (e.g. hydrology, Quaternary deposits, chemistry, vegetation, animals and the human land use). The ecosystem description is an integration of the site and its regional setting, covering the current state of the biosphere as well as the ongoing natural processes affecting the longterm development. Improving the descriptions is important during both the initial and the complete site investigation phase. Before starting of the initial phase in Forsmark, version 0 of the site descriptive model was developed. The results of the initial site investigation phase is compiled into a preliminary site description of Forsmark (version 1.2) in June 2005. This report provides the major input and background to the biosphere description, in the 1.2 version of the Forsmark site description. The basis for this interim version is quality-assured field data from the Forsmark sub area and regional area, available in the SKB SICADA, and GIS data bases as of July 31th 2004 as well as version 1.1 of the Site Descriptive Model. To achieve an ecosystem site description there is a need to develop discipline-specific models by interpreting and analysing primary data. The different discipline-specific models are then integrated into a system describing interactions and flows and stocks of matter between and within functional units in

  6. Description of surface systems. Preliminary site description. Forsmark area Version 1.2

    Lindborg, Tobias

    2005-06-01

    Swedish Nuclear Fuel and Waste Management Co (SKB) started site investigations for a deep repository for spent nuclear fuel in 2002 at two different sites in Sweden, Forsmark and Oskarshamn. The investigations should provide necessary information for a license application aimed at starting underground exploration. For this reason, ecosystem data need to be interpreted and assessed into site descriptive models, which in turn are used for safety assessment studies and for environmental impact assessment. Descriptions of the surface system are also needed for further planning of the site investigations. This report describes the surface ecosystems of the Forsmark site (e.g. hydrology, Quaternary deposits, chemistry, vegetation, animals and the human land use). The ecosystem description is an integration of the site and its regional setting, covering the current state of the biosphere as well as the ongoing natural processes affecting the longterm development. Improving the descriptions is important during both the initial and the complete site investigation phase. Before starting of the initial phase in Forsmark, version 0 of the site descriptive model was developed. The results of the initial site investigation phase is compiled into a preliminary site description of Forsmark (version 1.2) in June 2005. This report provides the major input and background to the biosphere description, in the 1.2 version of the Forsmark site description. The basis for this interim version is quality-assured field data from the Forsmark sub area and regional area, available in the SKB SICADA, and GIS data bases as of July 31th 2004 as well as version 1.1 of the Site Descriptive Model. To achieve an ecosystem site description there is a need to develop discipline-specific models by interpreting and analysing primary data. The different discipline-specific models are then integrated into a system describing interactions and flows and stocks of matter between and within functional units in

  7. Evaluation of the state of stress at the Forsmark site. Preliminary site investigation Forsmark area - version 1.2

    Sjoeberg, Jonny; Lindfors, Ulf; Perman, Fredrik; Ask, Daniel [SwedPower AB, Stockholm (Sweden)

    2005-09-15

    This report presents an evaluation of the state of stress at the Forsmark site, based on all conducted stress measurements to date at the site, indirect stress estimates, geological and tectonic description of the site, and regional stress data from nearby locations. The work included (i) compilation of measurement results from Forsmark, as well as from nearby (regional) sites/locations, (ii) analysis of confidence intervals for each group of measurement, (iii) assessment of the stress state for the Forsmark site accounting for geological/tectonic evolution at the site, (iv) assessment of stress state for selected nearby (regional) sites/locations, and (v) comparison and combined interpretation of similarities and/or differences in stress state from a regional perspective. The combined assessment of the local (site-scale) and regional stress data for Forsmark showed that the major stress is orientated sub-horizontally and trending NW-SE; however, with significant local variation. A thrust faulting ({sigma}H > {sigma}h > {sigma}v) or possibly strike-slip faulting ({sigma}H > {sigma}v > {sigma}h) stress regime is evident at the Forsmark site. The maximum horizontal stress tends to be higher at the site compared to nearby sites and regional conditions. The site and regional data indicate that the vertical stress seems to be solely due to the overburden pressure. The lack of solid core discing for large portions of the boreholes at Forsmark was used to estimate an upper limit of the maximum horizontal stress magnitude. However, such an estimation is highly uncertain due to e.g. partly unknown mechanism for core discing failure, and unknown effects of the simplifying assumptions made in the analysis. The possible effects of shallow-dipping deformation zones on the stress state, could not be verified from the currently available data. However, the possibility of different stress regimes above and below deformation zones must be considered in future work. Slightly lower

  8. Evaluation of the state of stress at the Forsmark site. Preliminary site investigation Forsmark area - version 1.2

    Sjoeberg, Jonny; Lindfors, Ulf; Perman, Fredrik; Ask, Daniel

    2005-09-01

    This report presents an evaluation of the state of stress at the Forsmark site, based on all conducted stress measurements to date at the site, indirect stress estimates, geological and tectonic description of the site, and regional stress data from nearby locations. The work included (i) compilation of measurement results from Forsmark, as well as from nearby (regional) sites/locations, (ii) analysis of confidence intervals for each group of measurement, (iii) assessment of the stress state for the Forsmark site accounting for geological/tectonic evolution at the site, (iv) assessment of stress state for selected nearby (regional) sites/locations, and (v) comparison and combined interpretation of similarities and/or differences in stress state from a regional perspective. The combined assessment of the local (site-scale) and regional stress data for Forsmark showed that the major stress is orientated sub-horizontally and trending NW-SE; however, with significant local variation. A thrust faulting (σH > σh > σv) or possibly strike-slip faulting (σH > σv > σh) stress regime is evident at the Forsmark site. The maximum horizontal stress tends to be higher at the site compared to nearby sites and regional conditions. The site and regional data indicate that the vertical stress seems to be solely due to the overburden pressure. The lack of solid core discing for large portions of the boreholes at Forsmark was used to estimate an upper limit of the maximum horizontal stress magnitude. However, such an estimation is highly uncertain due to e.g. partly unknown mechanism for core discing failure, and unknown effects of the simplifying assumptions made in the analysis. The possible effects of shallow-dipping deformation zones on the stress state, could not be verified from the currently available data. However, the possibility of different stress regimes above and below deformation zones must be considered in future work. Slightly lower horizontal stress was found in

  9. Regional hydrogeological simulations for Forsmark - numerical modelling using CONNECTFLOW. Preliminary site description Forsmark area - version 1.2

    Hartley, Lee; Cox, Ian; Hunter, Fiona; Jackson, Peter; Joyce, Steve; Swift, Ben [Serco Assurance, Risley (United Kingdom); Gylling, Bjoern; Marsic, Niko [Kemakta Konsult AB, Stockholm (Sweden)

    2005-05-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) carries out site investigations in two different candidate areas in Sweden with the objective of describing the in-situ conditions for a bedrock repository for spent nuclear fuel. The site characterisation work is divided into two phases, an initial site investigation phase (IPLU) and a complete site investigation phase (KPLU). The results of IPLU are used as a basis for deciding on a subsequent KPLU phase. On the basis of the KPLU investigations a decision is made as to whether detailed characterisation will be performed (including sinking of a shaft). An integrated component in the site characterisation work is the development of site descriptive models. These comprise basic models in three dimensions with an accompanying text description. Central in the modelling work is the geological model, which provides the geometrical context in terms of a model of deformation zones and the rock mass between the zones. Using the geological and geometrical description models as a basis, descriptive models for other geo-disciplines (hydrogeology, hydro-geochemistry, rock mechanics, thermal properties and transport properties) will be developed. Great care is taken to arrive at a general consistency in the description of the various models and assessment of uncertainty and possible needs of alternative models. Here, a numerical model is developed on a regional-scale (hundreds of square kilometres) to understand the zone of influence for groundwater flow that affects the Forsmark area. Transport calculations are then performed by particle tracking from a local-scale release area (a few square kilometres) to identify potential discharge areas for the site and using greater grid resolution. The main objective of this study is to support the development of a preliminary Site Description of the Forsmark area on a regional-scale based on the available data of 30 June 2004 and the previous Site Description. A more specific

  10. Preliminary assessment of potential underground stability (wedge and spalling) at Forsmark, Simpevarp and Laxemar sites

    Martin, Derek [Univ. of Alberta, Edmonton (Canada). Geotechnical Engineering

    2005-12-15

    In SKB's Underground Design Premises the objective in the early design phase is to estimate if there is sufficient space for the repository at a site. One of the conditions that could limit the space available is stability of the underground openings, i.e., deposition tunnels and deposition boreholes. The purpose of this report is to provide a preliminary assessment of the potential for wedge instability and spalling that may be encountered at the Forsmark, Simpevarp and Laxemar sites based on information from the site investigations program up to July 30, 2004. The rock mass spalling strength was defined using the in-situ results from SKB's Aespoe Pillar Stability Experiment and AECL's Mine-by Experiment. These experiments suggest that the rock mass spalling strength for crystalline rocks can be estimated as 0.57 of the mean laboratory uniaxial compressive strength. A probability-based methodology utilizing this in-situ rock mass spalling strength has been developed for assessing the risk for spalling in a repository at the Forsmark, Simpevarp and Laxemar sites. The in-situ stresses and the uniaxial compressive strength data from these sites were used as the bases for the analyses. Preliminary findings from all sites suggest that, generally, the risk for spalling increases as the depth of the repository increases, simply because the stress magnitudes increase with depth. The depth at which the risk for spalling is significant, depends on the individual sites which are discussed below. The greatest uncertainty in the spalling analyses for Forsmark is related to the uncertainty in the horizontal stress magnitudes and associated stress gradients with depth. The confidence in these analyses can only be increased by increasing the confidence in the stress and geology model for the site. From the analyses completed it appears that spalling in the deposition tunnels can be controlled by orienting the tunnels approximately parallel to the maximum horizontal

  11. Regional hydrogeological simulations for Forsmark - numerical modelling using DarcyTools. Preliminary site description Forsmark area version 1.2

    Follin, Sven; Stigsson, Martin; Svensson, Urban

    2005-12-01

    A numerical model is developed on a regional-scale (hundreds of square kilometres) to study the zone of influence for variable-density groundwater flow that affects the Forsmark area. Transport calculations are performed by particle tracking from a local-scale release area (a few square kilometres) to test the sensitivity to different hydrogeological uncertainties and the need for far-field realism. The main objectives of the regional flow modelling were to achieve the following: I. Palaeo-hydrogeological understanding: An improved understanding of the palaeohydrogeological conditions is necessary in order to gain credibility for the site descriptive model in general and the hydrogeological description in particular. This requires modelling of the groundwater flow from the last glaciation up to present-day with comparisons against measured TDS and other hydro-geochemical measures. II. Simulation of flow paths: The simulation and visualisation of flow paths from a tentative repository area is a means for describing the role of the current understanding of the modelled hydrogeological conditions in the target volume, i.e. the conditions of primary interest for Safety Assessment. Of particular interest here is demonstration of the need for detailed far-field realism in the numerical simulations. The motivation for a particular model size (and resolution) and set of boundary conditions for a realistic description of the recharge and discharge connected to the flow at repository depth is an essential part of the groundwater flow path simulations. The numerical modelling was performed by two separate modelling teams, the ConnectFlow Team and the DarcyTools Team. The work presented in this report was based on the computer code DarcyTools developed by Computer-aided Fluid Engineering. DarcyTools is a kind of equivalent porous media (EPM) flow code specifically designed to treat flow and salt transport in sparsely fractured crystalline rock intersected by transmissive

  12. Regional hydrogeological simulations for Forsmark - numerical modelling using DarcyTools. Preliminary site description Forsmark area version 1.2

    NONE

    2005-12-15

    A numerical model is developed on a regional-scale (hundreds of square kilometres) to study the zone of influence for variable-density groundwater flow that affects the Forsmark area. Transport calculations are performed by particle tracking from a local-scale release area (a few square kilometres) to test the sensitivity to different hydrogeological uncertainties and the need for far-field realism. The main objectives of the regional flow modelling were to achieve the following: I. Palaeo-hydrogeological understanding: An improved understanding of the palaeohydrogeological conditions is necessary in order to gain credibility for the site descriptive model in general and the hydrogeological description in particular. This requires modelling of the groundwater flow from the last glaciation up to present-day with comparisons against measured TDS and other hydro-geochemical measures. II. Simulation of flow paths: The simulation and visualisation of flow paths from a tentative repository area is a means for describing the role of the current understanding of the modelled hydrogeological conditions in the target volume, i.e. the conditions of primary interest for Safety Assessment. Of particular interest here is demonstration of the need for detailed far-field realism in the numerical simulations. The motivation for a particular model size (and resolution) and set of boundary conditions for a realistic description of the recharge and discharge connected to the flow at repository depth is an essential part of the groundwater flow path simulations. The numerical modelling was performed by two separate modelling teams, the ConnectFlow Team and the DarcyTools Team. The work presented in this report was based on the computer code DarcyTools developed by Computer-aided Fluid Engineering. DarcyTools is a kind of equivalent porous media (EPM) flow code specifically designed to treat flow and salt transport in sparsely fractured crystalline rock intersected by transmissive

  13. Hydrogeochemical evaluation. Preliminary site description Forsmark area - version 1.2

    Laaksoharju, Marcus

    2005-03-01

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Forsmark and Laxemar-Simpevarp, on the eastern coast of Sweden to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 which represents the second evaluation of the available Forsmark groundwater analytical data collected up to June, 2004. The Hydrochemical Analytical Group (HAG) had access to data where a total of 1,131 water samples had been collected from the surface and sub-surface environment; 252 samples were collected from drilled boreholes. The deepest fracture groundwater samples with sufficient analytical data reflected depths down to 1 km. Most of the waters sampled (66%) lacked crucial analytical information that restricted the evaluation. Model version 1.2 focuses on geochemical and mixing processes affecting the groundwater composition in the uppermost part of the bedrock, down to repository levels, and eventually extending to 1,000 m depth. The complex groundwater evolution and patterns at Forsmark are a result of many factors such as: a) the present-day topography and proximity to the Baltic Sea, b) past changes in hydrogeology related to glaciation/deglaciation, land uplift and repeated marine/lake water regressions/ transgressions, and c) organic or inorganic alteration of the groundwater composition caused by microbial processes or water/rock interactions. The sampled groundwaters reflect to various degrees processes relating to modern or ancient water/rock interactions and mixing. The groundwater flow regimes at Forsmark are considered local and extend down to depths of around 600 m depending on hydraulic conditions. Close to the Baltic Sea coastline where topographical variation is even less, groundwater flow penetration to depth will subsequently be less marked and such areas will tend to be characterised by groundwater

  14. Hydrogeochemical evaluation. Preliminary site description Forsmark area - version 1.2

    Laaksoharju, Marcus (ed.) [Geopoint AB, Stockholm (Sweden)

    2005-03-15

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Forsmark and Laxemar-Simpevarp, on the eastern coast of Sweden to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 which represents the second evaluation of the available Forsmark groundwater analytical data collected up to June, 2004. The Hydrochemical Analytical Group (HAG) had access to data where a total of 1,131 water samples had been collected from the surface and sub-surface environment; 252 samples were collected from drilled boreholes. The deepest fracture groundwater samples with sufficient analytical data reflected depths down to 1 km. Most of the waters sampled (66%) lacked crucial analytical information that restricted the evaluation. Model version 1.2 focuses on geochemical and mixing processes affecting the groundwater composition in the uppermost part of the bedrock, down to repository levels, and eventually extending to 1,000 m depth. The complex groundwater evolution and patterns at Forsmark are a result of many factors such as: a) the present-day topography and proximity to the Baltic Sea, b) past changes in hydrogeology related to glaciation/deglaciation, land uplift and repeated marine/lake water regressions/ transgressions, and c) organic or inorganic alteration of the groundwater composition caused by microbial processes or water/rock interactions. The sampled groundwaters reflect to various degrees processes relating to modern or ancient water/rock interactions and mixing. The groundwater flow regimes at Forsmark are considered local and extend down to depths of around 600 m depending on hydraulic conditions. Close to the Baltic Sea coastline where topographical variation is even less, groundwater flow penetration to depth will subsequently be less marked and such areas will tend to be characterised by

  15. Preliminary safety evaluation for the Forsmark area. Based on data and site descriptions after the initial site investigation stage

    Andersson, Johan

    2005-08-01

    The main objectives of this Preliminary Safety Evaluation (PSE) of the Forsmark area have been to determine, with limited efforts, whether the feasibility study's judgement of the suitability of the candidate area with respect to long-term safety holds up in the light of the actual site investigation data; to provide feedback to continued site investigations and site-specific repository design and to identify site-specific scenarios and geoscientific issues for further analyses. The PSE focuses on comparing the attained knowledge of the sites with the suitability criteria as set out by SKB. The PSE does not aim at comparing sites and does not assess compliance with safety and radiation protection criteria. The evaluation shows that, even considering remaining uncertainties, the Forsmark area meets all stated safety requirements and preferences. Consequently, from a safety point of view, there is no reason not to continue the Site Investigations of the Forsmark area. There are still uncertainties to resolve and the safety would eventually need to be verified through a full safety assessment. Nevertheless, this Preliminary Safety Evaluation demonstrates that it is likely that a safe repository for spent nuclear fuel of the KBS-3 type could be constructed at the site. The following feedback is provided to the site investigations and the associated site modelling: Reducing the uncertainty on the deformation zone geometry inside the target area would be needed to more firmly define locations of the suitable deposition volumes. There is substantial uncertainty in the Discrete Fracture Network model. Further reduction of the uncertainties, if needed, would probably only be possible from the underground, detailed investigation phase. Efforts need also be spent on improving the DFN-modelling. There are assumptions made in current models that could be challenged and there seems to be room for better use of the borehole information. It is particularly important to provide

  16. Preliminary safety evaluation for the Forsmark area. Based on data and site descriptions after the initial site investigation stage

    Andersson, Johan [JA Streamflow AB, Aelvsjoe (Sweden)

    2005-08-01

    The main objectives of this Preliminary Safety Evaluation (PSE) of the Forsmark area have been to determine, with limited efforts, whether the feasibility study's judgement of the suitability of the candidate area with respect to long-term safety holds up in the light of the actual site investigation data; to provide feedback to continued site investigations and site-specific repository design and to identify site-specific scenarios and geoscientific issues for further analyses. The PSE focuses on comparing the attained knowledge of the sites with the suitability criteria as set out by SKB. The PSE does not aim at comparing sites and does not assess compliance with safety and radiation protection criteria. The evaluation shows that, even considering remaining uncertainties, the Forsmark area meets all stated safety requirements and preferences. Consequently, from a safety point of view, there is no reason not to continue the Site Investigations of the Forsmark area. There are still uncertainties to resolve and the safety would eventually need to be verified through a full safety assessment. Nevertheless, this Preliminary Safety Evaluation demonstrates that it is likely that a safe repository for spent nuclear fuel of the KBS-3 type could be constructed at the site. The following feedback is provided to the site investigations and the associated site modelling: Reducing the uncertainty on the deformation zone geometry inside the target area would be needed to more firmly define locations of the suitable deposition volumes. There is substantial uncertainty in the Discrete Fracture Network model. Further reduction of the uncertainties, if needed, would probably only be possible from the underground, detailed investigation phase. Efforts need also be spent on improving the DFN-modelling. There are assumptions made in current models that could be challenged and there seems to be room for better use of the borehole information. It is particularly important to

  17. Thermal modelling. Preliminary site description. Forsmark area - version 1.2

    Sundberg, Jan; Back, Paer-Erik; Bengtsson, Anna; Laendell, Maerta [Geo Innova AB, Linkoeping (Sweden)

    2005-08-01

    This report presents the thermal site descriptive model for the Forsmark area, version 1.2. The main objective of this report is to present the thermal modelling work where data has been identified, quality controlled, evaluated and summarised in order to make an upscaling to lithological domain level possible. The thermal conductivity at canister scale has been modelled for two different lithological domains (RFM029 and RFM012, both dominated by granite to granodiorite (101057)). A main modelling approach has been used to determine the mean value of the thermal conductivity. Two alternative/complementary approaches have been used to evaluate the spatial variability of the thermal conductivity at domain level. The thermal modelling approaches are based on the lithological model for the Forsmark area, version 1.2 together with rock type models constituted from measured and calculated (from mineral composition) thermal conductivities. Results indicate that the mean of thermal conductivity is expected to exhibit a small variation between the different domains, 3.46 W/(mxK) for RFM012 to 3.55 W/(mxK) for RFM029. The spatial distribution of the thermal conductivity does not follow a simple model. Lower and upper 95% confidence limits are based on the modelling results, but have been rounded of to only two significant figures. Consequently, the lower limit is 2.9 W/(mxK), while the upper is 3.8 W/(mxK). This is applicable to both the investigated domains. The temperature dependence is rather small with a decrease in thermal conductivity of 10.0% per 100 deg C increase in temperature for the dominating rock type. There are a number of important uncertainties associated with these results. One of the uncertainties considers the representative scale for the canister. Another important uncertainty is the methodological uncertainties associated with the upscaling of thermal conductivity from cm-scale to canister scale. In addition, the representativeness of rock samples is

  18. Bedrock hydrogeology Forsmark. Site descriptive modelling, SDM-Site Forsmark

    Follin, Sven (SF GeoLogic AB, Taeby (Sweden))

    2008-12-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) has conducted site investigations at two different locations, the Forsmark and Laxemar-Simpevarp areas, with the objective of siting a final repository for spent nuclear fuel according to the KBS-3 concept. Site characterisation should provide all data required for an integrated evaluation of the suitability of the investigated site and an important component in the characterisation work is the development of a hydrogeological model. The hydrogeological model is used by repository engineering to design the underground facility and to develop a repository layout adapted to the site. It also provides input to the safety assessment. Another important use of the hydrogeological model is in the environmental impact assessment. This report presents the understanding of the hydrogeological conditions of the bedrock at Forsmark reached following the completion of the surface-based investigations and provides a summary of the bedrock hydrogeological model and the underlying data supporting its development. It constitutes the main reference on bedrock hydrogeology for the site descriptive model concluding the surface-based investigations at Forsmark, SDM-site, and is intended to describe the hydraulic properties and hydrogeological conditions of the bedrock at the site and to give the information essential for demonstrating understanding

  19. Rock mechanics site descriptive model-theoretical approach. Preliminary site description Forsmark area - version 1.2

    Fredriksson, Anders; Olofsson, Isabelle [Golder Associates AB, Uppsala (Sweden)

    2005-12-15

    The present report summarises the theoretical approach to estimate the mechanical properties of the rock mass in relation to the Preliminary Site Descriptive Modelling, version 1.2 Forsmark. The theoretical approach is based on a discrete fracture network (DFN) description of the fracture system in the rock mass and on the results of mechanical testing of intact rock and on rock fractures. To estimate the mechanical properties of the rock mass a load test on a rock block with fractures is simulated with the numerical code 3DEC. The location and size of the fractures are given by DFN-realisations. The rock block was loaded in plain strain condition. From the calculated relationship between stresses and deformations the mechanical properties of the rock mass were determined. The influence of the geometrical properties of the fracture system on the mechanical properties of the rock mass was analysed by loading 20 blocks based on different DFN-realisations. The material properties of the intact rock and the fractures were kept constant. The properties are set equal to the mean value of each measured material property. The influence of the variation of the properties of the intact rock and variation of the mechanical properties of the fractures are estimated by analysing numerical load tests on one specific block (one DFN-realisation) with combinations of properties for intact rock and fractures. Each parameter varies from its lowest values to its highest values while the rest of the parameters are held constant, equal to the mean value. The resulting distribution was expressed as a variation around the value determined with mean values on all parameters. To estimate the resulting distribution of the mechanical properties of the rock mass a Monte-Carlo simulation was performed by generating values from the two distributions independent of each other. The two values were added and the statistical properties of the resulting distribution were determined.

  20. Rock mechanics site descriptive model-theoretical approach. Preliminary site description Forsmark area - version 1.2

    Fredriksson, Anders; Olofsson, Isabelle

    2005-12-01

    The present report summarises the theoretical approach to estimate the mechanical properties of the rock mass in relation to the Preliminary Site Descriptive Modelling, version 1.2 Forsmark. The theoretical approach is based on a discrete fracture network (DFN) description of the fracture system in the rock mass and on the results of mechanical testing of intact rock and on rock fractures. To estimate the mechanical properties of the rock mass a load test on a rock block with fractures is simulated with the numerical code 3DEC. The location and size of the fractures are given by DFN-realisations. The rock block was loaded in plain strain condition. From the calculated relationship between stresses and deformations the mechanical properties of the rock mass were determined. The influence of the geometrical properties of the fracture system on the mechanical properties of the rock mass was analysed by loading 20 blocks based on different DFN-realisations. The material properties of the intact rock and the fractures were kept constant. The properties are set equal to the mean value of each measured material property. The influence of the variation of the properties of the intact rock and variation of the mechanical properties of the fractures are estimated by analysing numerical load tests on one specific block (one DFN-realisation) with combinations of properties for intact rock and fractures. Each parameter varies from its lowest values to its highest values while the rest of the parameters are held constant, equal to the mean value. The resulting distribution was expressed as a variation around the value determined with mean values on all parameters. To estimate the resulting distribution of the mechanical properties of the rock mass a Monte-Carlo simulation was performed by generating values from the two distributions independent of each other. The two values were added and the statistical properties of the resulting distribution were determined

  1. Statistical model of fractures and deformations zones for Forsmark. Preliminary site description Forsmark area - version 1.2

    La Pointe, Paul R. [Golder Associate Inc., Redmond, WA (United States); Olofsson, Isabelle; Hermanson, Jan [Golder Associates AB, Uppsala (Sweden)

    2005-04-01

    different high and low fracture intensity intervals in order to capture the variation of this parameter in the model volume. The fracture intensity P32 has been derived by means of simulations for each rock domain and each fracture type, and is expressed as a mean value, and if possible standard deviation and span. The uncertainty in the model has been quantified: for the different geometrical parameters by providing ranges of variations and studying relevant distribution models, by conducting sensitivity analysis on some input data: the effect of truncation of lineaments at the border of the regional model volume and the impact of truncation in outcrop mapping. An alternative conceptual model is under study which is based on the identified deterministic deformation zones, and not on lineaments. An important issue using this model is the bias of information and the limited amount of structures. The current DFN model still contains significant uncertainties which need to be resolved in order to be able to produce a final site DFN model. Three main issues are listed below: The definition of the subhorizontal fracture set in terms of geological processes and tectonics. The size distribution is a critical issue for the hydrogeology of the site. The variation of the fracture intensity by rock domain has been identified but the variation pattern and the spatial distribution within an individual domain are still sufficiently unpredictable that the fracture network permeability structure within a rock domain is uncertain from a conceptual perspective, not just a data uncertainty perspective. Moreover, many rock domains have not yet been sampled by boreholes or outcrops, and thus their fracture properties remain highly uncertain. Validation of the DFN models will require resolution of these two issues, and may also require the drilling of highly inclined or horizontal boreholes. Near-vertical boreholes and the mapping protocol to only map fracture traces in outcrop greater than 0

  2. Statistical model of fractures and deformations zones for Forsmark. Preliminary site description Forsmark area - version 1.2

    La Pointe, Paul R.; Olofsson, Isabelle; Hermanson, Jan

    2005-04-01

    different high and low fracture intensity intervals in order to capture the variation of this parameter in the model volume. The fracture intensity P32 has been derived by means of simulations for each rock domain and each fracture type, and is expressed as a mean value, and if possible standard deviation and span. The uncertainty in the model has been quantified: for the different geometrical parameters by providing ranges of variations and studying relevant distribution models, by conducting sensitivity analysis on some input data: the effect of truncation of lineaments at the border of the regional model volume and the impact of truncation in outcrop mapping. An alternative conceptual model is under study which is based on the identified deterministic deformation zones, and not on lineaments. An important issue using this model is the bias of information and the limited amount of structures. The current DFN model still contains significant uncertainties which need to be resolved in order to be able to produce a final site DFN model. Three main issues are listed below: The definition of the subhorizontal fracture set in terms of geological processes and tectonics. The size distribution is a critical issue for the hydrogeology of the site. The variation of the fracture intensity by rock domain has been identified but the variation pattern and the spatial distribution within an individual domain are still sufficiently unpredictable that the fracture network permeability structure within a rock domain is uncertain from a conceptual perspective, not just a data uncertainty perspective. Moreover, many rock domains have not yet been sampled by boreholes or outcrops, and thus their fracture properties remain highly uncertain. Validation of the DFN models will require resolution of these two issues, and may also require the drilling of highly inclined or horizontal boreholes. Near-vertical boreholes and the mapping protocol to only map fracture traces in outcrop greater than 0

  3. Surface system Forsmark. Site descriptive modelling SDM-Site Forsmark

    Lindborg, Tobias

    2008-12-01

    SKB has undertaken site characterization of two different areas, Forsmark and Laxemar-Simpevarp, in order to find a suitable location for a geological repository for spent nuclear fuel. This report focuses on the site descriptive modelling of the surface system at Forsmark. The characterization of the surface system at the site was primarily made by identifying and describing important properties in different parts of the surface system, properties concerning e.g. hydrology and climate, Quaternary deposits and soils, hydrochemistry, vegetation, ecosystem functions, but also current and historical land use. The report presents available input data, methodology for data evaluation and modelling, and resulting models for each of the different disciplines. Results from the modelling of the surface system are also integrated with results from modelling of the deep bedrock system. The Forsmark site is located within the municipality of Oesthammar, about 120 km north of Stockholm. The investigated area is located along the shoreline of Oeregrundsgrepen, a funnel-shaped bay of the Baltic Sea. The area is characterized by small-scale topographic variations and is almost entirely located at altitudes lower than 20 metres above sea level. The Quaternary deposits in the area are dominated by till, characterized by a rich content of calcite which was transported by the glacier ice to the area from the sedimentary bedrock of Gaevlebukten about 100 km north of Forsmark. As a result, the surface waters and shallow groundwater at Forsmark are characterized by high pH values and high concentrations of certain major constituents, especially calcium and bicarbonate. The annual precipitation and runoff are 560 and 150 mm, respectively. The lakes are small and shallow, with mean and maximum depths ranging from approximately 0.1 to 1 m and 0.4 to 2 m. Sea water flows into the most low-lying lakes during events giving rise to very high sea levels. Wetlands are frequent and cover 25 to 35

  4. Surface system Forsmark. Site descriptive modelling SDM-Site Forsmark

    Lindborg, Tobias [ed.

    2008-12-15

    SKB has undertaken site characterization of two different areas, Forsmark and Laxemar-Simpevarp, in order to find a suitable location for a geological repository for spent nuclear fuel. This report focuses on the site descriptive modelling of the surface system at Forsmark. The characterization of the surface system at the site was primarily made by identifying and describing important properties in different parts of the surface system, properties concerning e.g. hydrology and climate, Quaternary deposits and soils, hydrochemistry, vegetation, ecosystem functions, but also current and historical land use. The report presents available input data, methodology for data evaluation and modelling, and resulting models for each of the different disciplines. Results from the modelling of the surface system are also integrated with results from modelling of the deep bedrock system. The Forsmark site is located within the municipality of Oesthammar, about 120 km north of Stockholm. The investigated area is located along the shoreline of Oeregrundsgrepen, a funnel-shaped bay of the Baltic Sea. The area is characterized by small-scale topographic variations and is almost entirely located at altitudes lower than 20 metres above sea level. The Quaternary deposits in the area are dominated by till, characterized by a rich content of calcite which was transported by the glacier ice to the area from the sedimentary bedrock of Gaevlebukten about 100 km north of Forsmark. As a result, the surface waters and shallow groundwater at Forsmark are characterized by high pH values and high concentrations of certain major constituents, especially calcium and bicarbonate. The annual precipitation and runoff are 560 and 150 mm, respectively. The lakes are small and shallow, with mean and maximum depths ranging from approximately 0.1 to 1 m and 0.4 to 2 m. Sea water flows into the most low-lying lakes during events giving rise to very high sea levels. Wetlands are frequent and cover 25 to 35

  5. Site description of Forsmark at completion of the site investigation phase. SDM-Site Forsmark

    2008-12-15

    north-western part of the candidate area lacks hydraulically conductive, gently dipping fracture zones at potential repository depth and was selected as the target area for the complete site investigation work, following the initial investigations at the site. Prior to the presentation of the SDM-Site report, three versions of a site descriptive model have been completed for the Forsmark area and presented for peer review. The last version, referred to as version 1.2, was a preliminary site description that concluded the initial site investigation work and was presented in 2005. This preliminary site description formed the basis for a preliminary safety evaluation (PSE) of the Forsmark area, a preliminary repository layout (step D1), and the first evaluation of the long-term safety of this layout for KBS-3 repositories in the context of the SR-Can project. The final site descriptive model, SDM-Site, builds on a coordinated geological model in 3D, into which other discipline-specific models have been integrated without any major conflicting interpretations. In particular, the thermal properties of the bedrock at the site have been coupled to identified rock domains in the geological model and an integrated model that links the current stress regime, the hydrogeology and the chemistry of the groundwater to fracture domains and fracture zones in the geological model has evolved. These mutually consistent results demonstrate that a fundamental understanding of the current state of conditions and the on-going processes in the Forsmark area, from the surface down to potential repository depth, has been achieved. In addition, the properties of the area can be explained in the context of an understanding of the past evolution, throughout a long period of geological history. This integrated understanding of the area is presented in chapter 11 of this report and this chapter serves as an executive summary. A systematic assessment of the confidence in the model, including

  6. Site description of Forsmark at completion of the site investigation phase. SDM-Site Forsmark

    2008-12-01

    north-western part of the candidate area lacks hydraulically conductive, gently dipping fracture zones at potential repository depth and was selected as the target area for the complete site investigation work, following the initial investigations at the site. Prior to the presentation of the SDM-Site report, three versions of a site descriptive model have been completed for the Forsmark area and presented for peer review. The last version, referred to as version 1.2, was a preliminary site description that concluded the initial site investigation work and was presented in 2005. This preliminary site description formed the basis for a preliminary safety evaluation (PSE) of the Forsmark area, a preliminary repository layout (step D1), and the first evaluation of the long-term safety of this layout for KBS-3 repositories in the context of the SR-Can project. The final site descriptive model, SDM-Site, builds on a coordinated geological model in 3D, into which other discipline-specific models have been integrated without any major conflicting interpretations. In particular, the thermal properties of the bedrock at the site have been coupled to identified rock domains in the geological model and an integrated model that links the current stress regime, the hydrogeology and the chemistry of the groundwater to fracture domains and fracture zones in the geological model has evolved. These mutually consistent results demonstrate that a fundamental understanding of the current state of conditions and the on-going processes in the Forsmark area, from the surface down to potential repository depth, has been achieved. In addition, the properties of the area can be explained in the context of an understanding of the past evolution, throughout a long period of geological history. This integrated understanding of the area is presented in chapter 11 of this report and this chapter serves as an executive summary. A systematic assessment of the confidence in the model, including

  7. Bedrock hydrogeochemistry Forsmark. Site descriptive modelling SDM-Site Forsmark

    Laaksoharju, Marcus [Geopoint AB, Sollentuna (Sweden); Smellie, John [Conterra AB, Partille (Sweden); Tullborg, Eva-Lena [Terralogica, Graabo (Sweden); Gimeno, Maria [Univ. of Zaragoza, Zaragoza (Spain); Hallbeck, Lotta [Microbial Analytics, Goeteborg (Sweden); Molinero, Jorge [Amphos XXI Consulting S.L., Barcelona (Spain); Waber, Nick [Univ. of Bern, Bern (Switzerland)

    2008-12-15

    The overall objectives of the hydrogeochemical site description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site, and to use this understanding to develop models that address the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and porewater and their evolution with time. The specific aims of the hydrogeochemical work were: To document the hydrogeochemistry at the Forsmark site with focus on the development of conceptual models to describe and visualise the site. To provide relevant parameter values to be used for safety assessment calculations. To provide the hydrogeochemical basis for the modelling work by other teams, in particular hydrogeology. To take account of the feedback from the SR-Can safety assessment work that bears relevance to the hydrogeochemical modelling work. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. In this report, the groundwaters have been interpreted in relation to their origin, evolution and composition, which require close integration with geological, climatological and hydrogeological information. Past climate changes are one of the major driving forces for long-term hydrogeochemical changes (hundreds to thousands of years) and are, therefore, of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the Fennoscandian crystalline bedrock. In contrast, redox buffer capacity of the bedrock will minimise the effects on changes in alkalinity and redox at repository depths, therefore limiting the variations in pH and Eh significantly, regardless of major changes in groundwater composition. There is

  8. Bedrock hydrogeochemistry Forsmark. Site descriptive modelling SDM-Site Forsmark

    Laaksoharju, Marcus; Smellie, John; Tullborg, Eva-Lena; Gimeno, Maria; Hallbeck, Lotta; Molinero, Jorge; Waber, Nick

    2008-12-01

    The overall objectives of the hydrogeochemical site description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site, and to use this understanding to develop models that address the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and porewater and their evolution with time. The specific aims of the hydrogeochemical work were: To document the hydrogeochemistry at the Forsmark site with focus on the development of conceptual models to describe and visualise the site. To provide relevant parameter values to be used for safety assessment calculations. To provide the hydrogeochemical basis for the modelling work by other teams, in particular hydrogeology. To take account of the feedback from the SR-Can safety assessment work that bears relevance to the hydrogeochemical modelling work. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. In this report, the groundwaters have been interpreted in relation to their origin, evolution and composition, which require close integration with geological, climatological and hydrogeological information. Past climate changes are one of the major driving forces for long-term hydrogeochemical changes (hundreds to thousands of years) and are, therefore, of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the Fennoscandian crystalline bedrock. In contrast, redox buffer capacity of the bedrock will minimise the effects on changes in alkalinity and redox at repository depths, therefore limiting the variations in pH and Eh significantly, regardless of major changes in groundwater composition. There is

  9. Fracture mineralogy of the Forsmark site. SDM-Site Forsmark

    Sandstroem, Bjoern (Dept. of Earth Sciences, Univ. of Goeteborg (Sweden)); Tullborg, Eva-Lena (Terralogica AB, Graabo (Sweden)); Smellie, John (Conterra AB, Luleaa (Sweden)); MacKenzie, Angus B. (SUERC, Scottish Enterprise Technology Park, East Kilbride (United Kingdom)); Suksi, Juhani (Dept. of Chemistry, Univ. of Helsinki, Helsinki (Finland))

    2008-08-15

    Detailed investigations of the fracture mineralogy and altered wall rock have been carried out as part of the site characterisation programme between 2003 and 2007 at Forsmark. The results have been published in a number of P-reports and in contributions to scientific journals. This report summarises and evaluates the data obtained during the detailed fracture mineralogical studies. The report includes descriptions of the identified fracture minerals and their chemical composition. A sequence of fracture mineralisations has been distinguished and provides information of the low to moderate temperature (brittle) geological and hydrogeological evolution at the site. Special focus has been paid to the chemical and stable isotopic composition of calcite to obtain palaeohydrogeological information. Chemical analyses of bulk fracture filling material have been carried out to identify possible sinks for certain elements and also to reveal the presence of minor phases rich in certain elements which have not been possible to detect by X-ray diffraction (XRD). Statistical analysis of the mineralogy in fractures outside deformation zones (i.e. within fracture domains FFM01, FFM02, FFM03 and FFM06) have been carried out concerning variation of fracture mineral distribution at depth and in different fracture domains. Uranium contents and uranium-series isotopes have been analysed on fracture coating material from hydraulically conductive fractures. Such analyses are also available from the groundwaters and the results are combined in order to reveal recent (< 1 Ma) removal/deposition of uranium in the fracture system. The redox conditions in the fracture system have been evaluated based on mineralogical and chemical indicators as well as Moessbauer analyses

  10. Description of climate, surface hydrology, and near-surface hydrogeology. Preliminary site description. Forsmark area - version 1.2

    Johansson, Per-Olof; Werner, Kent; Bosson, Emma; Berglund, Sten; Juston, John

    2005-06-01

    chloride content has been found below Lake Bolundsfjaerden, Lake Eckarfjaerden and Lake Gaellsbotraesket. The relations between the sea water level and the water levels in Lake Norra Bassaengen, Lake Bolundsfjaerden and Lake Lillfjaerden show that inflow of sea water can occur during periods of high sea water levels. The results from the hydrological GIS modelling support the assumptions and conclusions in the descriptive model. The flow model is highly sensitive to the topography, as this is the only parameter determining the flow pattern. Consequently, the simulated locations of recharge and discharge areas are strongly influenced by the local topography. In addition, the flat topography implies that small errors in the topographical model (the Digital Elevation Model, DEM) may have large effects on the modelled flow pattern. Ditches, diverted water courses and other human impacts on the system are important in some parts of the model area. These and other types of ''man-made structures'' are not fully considered in the DEM. The water balance for the Forsmark area, as calculated with the MIKE SHE modelling tool, agrees with the presented conceptual and descriptive models of the flow system. The transient model simulations for the selected reference year (1988) result in an annual total runoff of 226 mm and a total actual evapotranspiration of 441 mm. These values, which are average values for the considered model area, are considered to be reasonable for the Forsmark area. At present, however, they cannot be tested against site-specific measurements. The MIKE SHE model produces a shallow groundwater table, which approximately agrees with the groundwater level measurements within the area, and with the overall conceptualisation of the system. However, no detailed model calibration has been performed. The modelling results show that most of the groundwater flow occurs in the Quaternary deposits. The results also illustrate the importance of the fracture zones for the

  11. Description of climate, surface hydrology, and near-surface hydrogeology. Preliminary site description. Forsmark area - version 1.2

    Johansson, Per-Olof [Artesia Grundvattenkonsult AB, Stockholm (Sweden); Werner, Kent [SWECO VIAK AB/Golder Associates AB, Stockholm (Sweden); Bosson, Emma; Berglund, Sten [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Juston, John [DBE Sweden, Uppsala (Sweden)

    2005-06-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is conducting site investigations at two different locations, the Forsmark and Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. The results from the investigations at the sites are used as a basic input to the development of Site Descriptive Models (SDM). The SDM shall summarise the current state of knowledge of the site, and provide parameters and models to be used in further analyses within Safety Assessment, Repository Design and Environmental Impact Assessment. The present report is a background report describing the meteorological conditions and the modelling of surface hydrology and near-surface hydrogeology in support of the Forsmark version 1.2 SDM based on the data available in the Forsmark 1.2 'data freeze' (July 31, 2004). The groundwater is very shallow, with groundwater levels within one meter below ground as an annual mean for almost all groundwater monitoring wells. Also, the annual groundwater level amplitude is less than 1.5 m for most wells. The shallow groundwater levels mean that there is a strong interaction between evapotranspiration, soil moisture and groundwater. In the modelling, surface water and near-surface groundwater divides are assumed to coincide. The small-scale topography implies that many local, shallow groundwater flow systems are formed in the Quaternary deposits, overlaying more large-scale flow systems associated with groundwater flows at greater depths. Groundwater level time series from wells in till and bedrock within the same areas show a considerably higher groundwater level in the till than in the bedrock. The observed differences in levels are not fully consistent with the good hydraulic contact between overburden and bedrock indicated by the hydraulic tests in the Quaternary deposits. However, the relatively lower groundwater levels in the bedrock may be caused by the horizontal to sub-horizontal highly

  12. Forsmark - site descriptive model version 0

    2002-10-01

    During 2002, the Swedish Nuclear Fuel and Waste Management Company (SKB) is starting investigations at two potential sites for a deep repository in the Precambrian basement of the Fennoscandian Shield. The present report concerns one of those sites, Forsmark, which lies in the municipality of Oesthammar, on the east coast of Sweden, about 150 kilometres north of Stockholm. The site description should present all collected data and interpreted parameters of importance for the overall scientific understanding of the site, for the technical design and environmental impact assessment of the deep repository, and for the assessment of long-term safety. The site description will have two main components: a written synthesis of the site, summarising the current state of knowledge, as documented in the databases containing the primary data from the site investigations, and one or several site descriptive models, in which the collected information is interpreted and presented in a form which can be used in numerical models for rock engineering, environmental impact and long-term safety assessments. The site descriptive models are devised and stepwise updated as the site investigations proceed. The point of departure for this process is the regional site descriptive model, version 0, which is the subject of the present report. Version 0 is developed out of the information available at the start of the site investigation. This information, with the exception of data from tunnels and drill holes at the sites of the Forsmark nuclear reactors and the underground low-middle active radioactive waste storage facility, SFR, is mainly 2D in nature (surface data), and is general and regional, rather than site-specific, in content. For this reason, the Forsmark site descriptive model, version 0, as detailed in the present report, has been developed at a regional scale. It covers a rectangular area, 15 km in a southwest-northeast and 11 km in a northwest-southeast direction, around the

  13. Forsmark - site descriptive model version 0

    NONE

    2002-10-01

    During 2002, the Swedish Nuclear Fuel and Waste Management Company (SKB) is starting investigations at two potential sites for a deep repository in the Precambrian basement of the Fennoscandian Shield. The present report concerns one of those sites, Forsmark, which lies in the municipality of Oesthammar, on the east coast of Sweden, about 150 kilometres north of Stockholm. The site description should present all collected data and interpreted parameters of importance for the overall scientific understanding of the site, for the technical design and environmental impact assessment of the deep repository, and for the assessment of long-term safety. The site description will have two main components: a written synthesis of the site, summarising the current state of knowledge, as documented in the databases containing the primary data from the site investigations, and one or several site descriptive models, in which the collected information is interpreted and presented in a form which can be used in numerical models for rock engineering, environmental impact and long-term safety assessments. The site descriptive models are devised and stepwise updated as the site investigations proceed. The point of departure for this process is the regional site descriptive model, version 0, which is the subject of the present report. Version 0 is developed out of the information available at the start of the site investigation. This information, with the exception of data from tunnels and drill holes at the sites of the Forsmark nuclear reactors and the underground low-middle active radioactive waste storage facility, SFR, is mainly 2D in nature (surface data), and is general and regional, rather than site-specific, in content. For this reason, the Forsmark site descriptive model, version 0, as detailed in the present report, has been developed at a regional scale. It covers a rectangular area, 15 km in a southwest-northeast and 11 km in a northwest-southeast direction, around the

  14. Forsmark site investigation. Interpretation of topographic lineaments 2002

    Isaksson, Hans

    2003-04-01

    SKB performs site investigations for localization of a deep repository for high level radioactive waste. The site investigations are performed in two municipalities; Oesthammar and Oskarshamn. The Forsmark investigation area is situated in Oesthammar, close to the Forsmark nuclear power plant. The purpose of interpretation of lineaments from topographic data is to identify linear features (lineaments), which may correspond to deformation zones in the bedrock. The data will be combined with interpretations of lineaments from airborne geophysical data in order to produce an integrated lineament interpretation for the Forsmark area. This integrated interpretation will be combined with geological data in order to establish a bedrock geological map of the Forsmark area. The area for the lineament interpretation is the same as that selected for the bedrock mapping activities during 2002, i.e. the land area around Forsmark

  15. Human population and activities in Forsmark. Site description

    Miliander, Sofia; Punakivi, Mari; Kylaekorpi, Lasse; Rydgren, Bernt [SwedPower AB, Stockholm (Sweden)

    2004-12-01

    The Swedish Nuclear Fuel and Waste Management Co (SKB) is in the process of selecting a safe and environmentally acceptable location for a deep repository of radioactive waste. Two alternative locations are under investigation. These are Forsmark, Oesthammars kommun (kommun = municipality) and Simpevarp/Laxemar, Oskarshamns kommun. SKB has expressed the importance of describing the humans and their activities in these areas and therefore has this synthesis concerning the human population in Forsmark been produced.The description is a statistical synthesis, mainly based upon statistical data from SCB (Statistics Sweden) that has been collected, processed and analysed. The statistical data has not been verified through site inspections and interviews. When using statistical data, it is advisable to note that the data becomes more unreliable if the areas are small, with small populations.The data in this description is essential for future evaluations of the impact on the environment and its human population (Environmental Impact Assessments). The data is also important when modelling the potential flows of radio nuclides and calculating the risk of exposure in future safety assessments.The actual area for the study is in this report called 'the Forsmark area', an area of 19.5 km{sup 2} near Forsmark nuclear power plant. The land use in the Forsmark area differs notably from the land use in Uppsala laen (laen = county). Only 0.04% of the total area is developed (built-up) compared to 4.9% in Uppsala laen and only 4% is agricultural land compared to 25% in the county. Furthermore, there are far more forest, wetlands and water areas in the Forsmark area. The forest area represents as much as 72.5% of the total area.The Forsmark area is uninhabited, and its surroundings are very sparsely populated. In 2002, the population density in Forsmark was 1.8 inhabitants per square kilometre, which was 24 times lower than in Uppsala laen. The population density in the

  16. Human population and activities in Forsmark. Site description

    Miliander, Sofia; Punakivi, Mari; Kylaekorpi, Lasse; Rydgren, Bernt

    2004-12-01

    The Swedish Nuclear Fuel and Waste Management Co (SKB) is in the process of selecting a safe and environmentally acceptable location for a deep repository of radioactive waste. Two alternative locations are under investigation. These are Forsmark, Oesthammars kommun (kommun = municipality) and Simpevarp/Laxemar, Oskarshamns kommun. SKB has expressed the importance of describing the humans and their activities in these areas and therefore has this synthesis concerning the human population in Forsmark been produced.The description is a statistical synthesis, mainly based upon statistical data from SCB (Statistics Sweden) that has been collected, processed and analysed. The statistical data has not been verified through site inspections and interviews. When using statistical data, it is advisable to note that the data becomes more unreliable if the areas are small, with small populations.The data in this description is essential for future evaluations of the impact on the environment and its human population (Environmental Impact Assessments). The data is also important when modelling the potential flows of radio nuclides and calculating the risk of exposure in future safety assessments.The actual area for the study is in this report called 'the Forsmark area', an area of 19.5 km 2 near Forsmark nuclear power plant. The land use in the Forsmark area differs notably from the land use in Uppsala laen (laen = county). Only 0.04% of the total area is developed (built-up) compared to 4.9% in Uppsala laen and only 4% is agricultural land compared to 25% in the county. Furthermore, there are far more forest, wetlands and water areas in the Forsmark area. The forest area represents as much as 72.5% of the total area.The Forsmark area is uninhabited, and its surroundings are very sparsely populated. In 2002, the population density in Forsmark was 1.8 inhabitants per square kilometre, which was 24 times lower than in Uppsala laen. The population density in the parish has been

  17. Validation of coastal oceanographic models at Forsmark. Site descriptive modelling SDM-Site Forsmark

    Engqvist, Anders (A och I Engqvist Konsult HB, Vaxholm (SE)); Andrejev, Oleg (Finnish Inst. of Marine Research, Helsinki (FI))

    2008-01-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterisation at two different locations, the Forsmark and the Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. The characterisation work is divided into an initial site investigation phase and a complete site investigation phase. In this context, the water exchange of the coastal zone is one link of the chain of possible nuclide transport mechanisms that must be assessed in the site description of potential repository areas. For the purpose of validating the pair of nested 3D-models employed to simulate the water exchange in the near-shore coastal zone in the Forsmark area, an encompassing measurement program entailing six stations has been performed. The design of this program was to first assess to what degree the forcing of the fine resolution (FR) model of the Forsmark study area at its interfacial boundary to the coarse resolution (CR) model of the entire Baltic was reproduced. In addition to this scrutiny it is of particular interest how the time-varying density-determining properties, salinity and temperature, at the borders are propagated into the FR-domain, since this corresponds to the most efficient mode of water exchange. An important part of the validation process has been to carefully evaluate which measurement data that can be considered reliable. The result was that several periods of foremost near-surface salinity data had to be discarded due to growth of algae on the conductivity sensors. Lack of thorough absolute calibration of the salinity meters also necessitates dismissal of measurement data. Relative the assessed data that can be accepted as adequate, the outcome of the validation can be summarized in five points: (i) The surface-most salinity of the CR-model drifts downward a little less than one practical salinity unit (psu) per year, requiring that the ensuing correlation analysis be subdivided into periods of a

  18. Validation of coastal oceanographic models at Forsmark. Site descriptive modelling SDM-Site Forsmark

    Engqvist, Anders; Andrejev, Oleg

    2008-01-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterisation at two different locations, the Forsmark and the Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. The characterisation work is divided into an initial site investigation phase and a complete site investigation phase. In this context, the water exchange of the coastal zone is one link of the chain of possible nuclide transport mechanisms that must be assessed in the site description of potential repository areas. For the purpose of validating the pair of nested 3D-models employed to simulate the water exchange in the near-shore coastal zone in the Forsmark area, an encompassing measurement program entailing six stations has been performed. The design of this program was to first assess to what degree the forcing of the fine resolution (FR) model of the Forsmark study area at its interfacial boundary to the coarse resolution (CR) model of the entire Baltic was reproduced. In addition to this scrutiny it is of particular interest how the time-varying density-determining properties, salinity and temperature, at the borders are propagated into the FR-domain, since this corresponds to the most efficient mode of water exchange. An important part of the validation process has been to carefully evaluate which measurement data that can be considered reliable. The result was that several periods of foremost near-surface salinity data had to be discarded due to growth of algae on the conductivity sensors. Lack of thorough absolute calibration of the salinity meters also necessitates dismissal of measurement data. Relative the assessed data that can be accepted as adequate, the outcome of the validation can be summarized in five points: (i) The surface-most salinity of the CR-model drifts downward a little less than one practical salinity unit (psu) per year, requiring that the ensuing correlation analysis be subdivided into periods of a

  19. Execution programme for the initial site investigations at Forsmark

    2002-05-01

    In the feasibility studies that were completed in 2001, eight sites were identified as potentially suitable for hosting a repository. All the identified sites meet the safety requirements with respect to bedrock conditions that could be checked at that time. The feasibility studies have revealed good potential when it comes to the technical and environmental aspects as well. Based on an integrated evaluation SKB proposed to start site investigations with test drillings at three sites; Forsmark, Simpevarp and Tierp. Site investigations have started at Forsmark and Simpevarp. The municipal council of Tierp voted no to a site investigation in April 2002. The site investigations are divided into two main phases; initial and complete investigations. Initial site investigations are performed to identify the site within a specified area that is deemed to be most suitable for a deep repository and to determine whether the feasibility study's judgement of the suitability of the area holds up in the light of borehole data from repository depth. The initial site investigations are expected to take 1.5-2 years. If the assessment shows that the site has good potential to host a repository, complete site investigations will follow for an expected duration of 3.5-4 years. The purpose of the complete site investigations is to gather all information required to select one of the sites as the main alternative and to apply for a permit for construction of the deep repository at that site. A general programme in which the results from feasibility studies are summarized, the candidate sites presented and the framework of programme for the site investigation phase presented has been published. The general programme, and main references to the programme, specifies which data are required in order to design the repository and carry out a safety assessment, how the investigations should be carried out in order to provide these data, criteria with which the site must comply, as well as

  20. Execution programme for the initial site investigations at Forsmark

    NONE

    2002-05-01

    In the feasibility studies that were completed in 2001, eight sites were identified as potentially suitable for hosting a repository. All the identified sites meet the safety requirements with respect to bedrock conditions that could be checked at that time. The feasibility studies have revealed good potential when it comes to the technical and environmental aspects as well. Based on an integrated evaluation SKB proposed to start site investigations with test drillings at three sites; Forsmark, Simpevarp and Tierp. Site investigations have started at Forsmark and Simpevarp. The municipal council of Tierp voted no to a site investigation in April 2002. The site investigations are divided into two main phases; initial and complete investigations. Initial site investigations are performed to identify the site within a specified area that is deemed to be most suitable for a deep repository and to determine whether the feasibility study's judgement of the suitability of the area holds up in the light of borehole data from repository depth. The initial site investigations are expected to take 1.5-2 years. If the assessment shows that the site has good potential to host a repository, complete site investigations will follow for an expected duration of 3.5-4 years. The purpose of the complete site investigations is to gather all information required to select one of the sites as the main alternative and to apply for a permit for construction of the deep repository at that site. A general programme in which the results from feasibility studies are summarized, the candidate sites presented and the framework of programme for the site investigation phase presented has been published. The general programme, and main references to the programme, specifies which data are required in order to design the repository and carry out a safety assessment, how the investigations should be carried out in order to provide these data, criteria with which the site must comply, as well as

  1. Confidence assessment. Site descriptive modelling SDM-Site Forsmark

    2008-09-01

    The objective of this report is to assess the confidence that can be placed in the Forsmark site descriptive model, based on the information available at the conclusion of the surface-based investigations (SDM-Site Forsmark). In this exploration, an overriding question is whether remaining uncertainties are significant for repository engineering design or long-term safety assessment and could successfully be further reduced by more surface based investigations or more usefully by explorations underground made during construction of the repository. The confidence in the Forsmark site descriptive model, based on the data available at the conclusion of the surface-based site investigations, have been assessed by exploring: Confidence in the site characterisation data base; Key remaining issues and their handling; Handling of alternative models; Consistency between disciplines; and, Main reasons for confidence and lack of confidence in the model. It is generally found that the key aspects of importance for safety assessment and repository engineering of the Forsmark site descriptive model are associated with a high degree of confidence. Because of the robust geological model that describes the site, the overall confidence in Forsmark site descriptive model is judged to be high. While some aspects have lower confidence this lack of confidence is handled by providing wider uncertainty ranges, bounding estimates and/or alternative models. Most, but not all, of the low confidence aspects have little impact on repository engineering design or for long-term safety. Poor precision in the measured data are judged to have limited impact on uncertainties on the site descriptive model, with the exceptions of inaccuracy in determining the position of some boreholes at depth in 3-D space, as well as the poor precision of the orientation of BIPS images in some boreholes, and the poor precision of stress data determined by overcoring at the locations where the pre

  2. Rock Mechanics Forsmark. Site descriptive modelling Forsmark stage 2.2

    Glamheden, Rune; Fredriksson, Anders (Golder Associates AB (SE)); Roeshoff, Kennert; Karlsson, Johan (Berg Bygg Konsult AB (SE)); Hakami, Hossein (Itasca Geomekanik AB (SE)); Christiansson, Rolf (Swedish Nuclear Fuel and Waste Management Co., Stockholm (SE))

    2007-12-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterisation at two different locations, Forsmark and Laxemar/Simpevarp, with the objective of siting a geological repository for spent nuclear fuel. The characterisation of a site is an integrated work carried out by several disciplines including geology, rock mechanics, thermal properties, hydrogeology, hydrogeochemistry and surface systems. This report presents the rock mechanics model of the Forsmark site up to stage 2.2. The scope of work has included compilation and analysis of primary data of intact rock and fractures, estimation of the rock mass mechanical properties and estimation of the in situ state of stress at the Forsmark site. The laboratory results on intact rock and fractures in the target volume demonstrate a good quality rock mass that is strong, stiff and relatively homogeneous. The homogeneity is also supported by the lithological and the hydrogeological models. The properties of the rock mass have been initially estimated by two separate modelling approaches, one empirical and one theoretical. An overall final estimate of the rock mass properties were achieved by integrating the results from the two models via a process termed 'Harmonization'. Both the tensile tests, carried out perpendicular and parallel to the foliation, and the theoretical analyses of the rock mass properties in directions parallel and perpendicular to the major principal stress, result in parameter values almost independent of direction. This indicates that the rock mass in the target volume is isotropic. The rock mass quality in the target volume appears to be of high and uniform quality. Those portions with reduced rock mass quality that do exist are mainly related to sections with increased fracture frequency. Such sections are associated with deformation zones according to the geological description. The results of adjacent rock domains and fracture domains of the target

  3. Forsmark site investigation. Bedrock geology - overview and excursion guide

    Stephens, Michael B. (Geological Survey of Sweden, Uppsala (Sweden))

    2010-09-15

    Bearing in mind the significance of the bedrock data from the ground surface for the geological 3D modelling work, SKB decided to present excursion guides that serve in the demonstration of the bedrock geology at the ground surface in both the Forsmark (this guide) and Laxemar-Simpevarp areas. An excursion guide is also available for the Olkiluoto area in south-western Finland, which has been selected for the construction of a repository for the disposal of highly radioactive, spent nuclear fuel in Finland. The current excursion guide presents the bedrock geology and describes in detail the character of the bedrock at ten representative outcrops or outcrop areas at the ground surface in the site investigation area at Forsmark. All localities are located within or immediately adjacent to the proposed repository volume selected by SKB

  4. Forsmark site investigation. Bedrock geology - overview and excursion guide

    Stephens, Michael B.

    2010-09-01

    Bearing in mind the significance of the bedrock data from the ground surface for the geological 3D modelling work, SKB decided to present excursion guides that serve in the demonstration of the bedrock geology at the ground surface in both the Forsmark (this guide) and Laxemar-Simpevarp areas. An excursion guide is also available for the Olkiluoto area in south-western Finland, which has been selected for the construction of a repository for the disposal of highly radioactive, spent nuclear fuel in Finland. The current excursion guide presents the bedrock geology and describes in detail the character of the bedrock at ten representative outcrops or outcrop areas at the ground surface in the site investigation area at Forsmark. All localities are located within or immediately adjacent to the proposed repository volume selected by SKB

  5. Forsmark site investigation. A deformation analysis of the Forsmark GPS monitoring network from 2005 to 2009

    Gustafson, Lars; Ljungberg, Annika (Caliterra AB (Sweden))

    2010-10-15

    The objective of the study is to identify possible movements in the bedrock within and outside the candidate area at Forsmark. Seven physically stable stations were built in the Forsmark area in the autumn of 2005. Stations were established within a ten-kilometer radius. The stations were placed in three different areas separated by regional deformation zones: NE of the Singoe zone, within the candidate area, and SW of the Forsmark zone. Data have been collected in eighteen campaigns, each with a duration of about five days, from November 2005 to December 2009. Stations consist of a stainless steel rod fixed in the bedrock on which the GPS antenna mounts. Each station has dedicated GPS equipment only used at the specific site. Sets consist of a GPS receiver collecting raw GPS data and a choke ring antenna linked to the receiver using a coaxial cable. The receivers and antennas are dual frequency high precision geodetic grade. During each campaign the GPS receiver saves a reading every second for the duration of the five days campaign. The antennas remain mounted on the stations during the entire project, whereas all other equipment is in place at the station only during the campaigns. The measurements were related to the SWEPOS network stations Lovoe, Uppsala and Maartsbo that are defined as stations with stable fundaments by the National Land Survey of Sweden (Lantmaeteriet). This report deals with altogether 18 campaigns. The first 13 campaigns were performed during the period November 2005 to August 2008. However, the number of campaigns has been extended by adding a fourth year to the project. Optimization of the data processing depends on the properties of the entire data set comprising a period of four years. We divided the data into periods of 24 hours with each period processed as a separate session in the Bernese post processing software, after which we analyzed the residuals to conclude that data are of the expected quality. The entire data set from four

  6. Safety-related site characteristics - a relative comparison of the Forsmark reference areas

    Winberg, Anders

    2010-12-01

    SKB has over the years from 2002 to 2008 conducted site investigations in Forsmark and Laxemar, with associated site modeling, design and safety analysis. In mid-2009 Forsmark was selected on the basis of analysis made as site for a future repository for spent nuclear fuel. Based on defined safety-related geoscientific location factors data from Forsmark are compared in relative terms with data from a number of locations in Sweden, previously studied by SKB. The factors compared include: the rock's composition and structures, future climate evolution, rock mechanical conditions, earthquakes, groundwater flow, groundwater composition, delay of solutes, and the ability to characterize and describe the location. Past comparisons of these properties for the selected sites show that none of these sites collectively show any significant benefit over Forsmark site for a repository. This does not preclude that there may be places on the basis of an overall assessment of geoscientific location factors could be equivalent to Forsmark

  7. Landscape Forsmark - data, methodology and results for SR-Site

    Lindborg, Tobias

    2010-12-01

    This report presents an integrated description of the landscape at the Forsmark site during the succession from present conditions to the far future. It was produced as a part of the biosphere modelling within the SR-Site safety assessment. The report gives a description of input data, methodology and resulting models used to support the current understanding of the landscape used in SR-Site. It is intended to describe the properties and conditions at the site and to give information essential for demonstrating understanding. The report relies heavily on a number of discipline-specific background reports concerning details of the data analyses and modelling. Long-term landscape development in the Forsmark area is dependent on two main and partly interdependent factors, i.e. climate variations and shoreline displacement. These two factors in combination strongly affect a number of processes, which in turn determine the development of ecosystems. Some examples of such processes are erosion and sedimentation, groundwater recharge and discharge, soil formation, primary production and decomposition of organic matter. The biosphere at the site during the next 1,000 years is assumed to be quite similar to the present situation. The most important changes are the natural infilling of lakes and a slight withdrawal of the sea with its effects on the near-shore areas and the shallow coastal basins. The climate during the rest of the temperate period may vary considerably, with both warmer and colder periods. The main effect of temperature changes will be on the vegetation period. Changed temperatures may give rise to drier or wetter climate and to changed snow cover and frost characteristics, and this can in turn affect the dominant vegetation and mire build-up. The description of the Forsmark ecosystem succession during a glacial cycle is one of the main features of the SR-Site biosphere modelling. The future areas potentially affected by deep groundwater discharge are

  8. Landscape Forsmark - data, methodology and results for SR-Site

    Lindborg, Tobias [ed.; Svensk Kaernbraenslehantering AB (Sweden)

    2010-12-15

    This report presents an integrated description of the landscape at the Forsmark site during the succession from present conditions to the far future. It was produced as a part of the biosphere modelling within the SR-Site safety assessment. The report gives a description of input data, methodology and resulting models used to support the current understanding of the landscape used in SR-Site. It is intended to describe the properties and conditions at the site and to give information essential for demonstrating understanding. The report relies heavily on a number of discipline-specific background reports concerning details of the data analyses and modelling. Long-term landscape development in the Forsmark area is dependent on two main and partly interdependent factors, i.e. climate variations and shoreline displacement. These two factors in combination strongly affect a number of processes, which in turn determine the development of ecosystems. Some examples of such processes are erosion and sedimentation, groundwater recharge and discharge, soil formation, primary production and decomposition of organic matter. The biosphere at the site during the next 1,000 years is assumed to be quite similar to the present situation. The most important changes are the natural infilling of lakes and a slight withdrawal of the sea with its effects on the near-shore areas and the shallow coastal basins. The climate during the rest of the temperate period may vary considerably, with both warmer and colder periods. The main effect of temperature changes will be on the vegetation period. Changed temperatures may give rise to drier or wetter climate and to changed snow cover and frost characteristics, and this can in turn affect the dominant vegetation and mire build-up. The description of the Forsmark ecosystem succession during a glacial cycle is one of the main features of the SR-Site biosphere modelling. The future areas potentially affected by deep groundwater discharge are

  9. Safety-related site characteristics - a relative comparison of the Forsmark reference areas; Saekerhetsrelaterade platsegenskaper - en relativ jaemfoerelse av Forsmark med referensomraaden

    Winberg, Anders (Conterra AB, Uppsala (Sweden))

    2010-12-15

    SKB has over the years from 2002 to 2008 conducted site investigations in Forsmark and Laxemar, with associated site modeling, design and safety analysis. In mid-2009 Forsmark was selected on the basis of analysis made as site for a future repository for spent nuclear fuel. Based on defined safety-related geoscientific location factors data from Forsmark are compared in relative terms with data from a number of locations in Sweden, previously studied by SKB. The factors compared include: the rock's composition and structures, future climate evolution, rock mechanical conditions, earthquakes, groundwater flow, groundwater composition, delay of solutes, and the ability to characterize and describe the location. Past comparisons of these properties for the selected sites show that none of these sites collectively show any significant benefit over Forsmark site for a repository. This does not preclude that there may be places on the basis of an overall assessment of geoscientific location factors could be equivalent to Forsmark

  10. SR-Site - hydrogeochemical evolution of the Forsmark site

    Salas, Joaquin; Molinero, Jorge; Juarez, Iker; Gimeno, Maria Jose; Auque, Luis; Gomez, Javier

    2010-12-01

    The present work has involved the development of a methodology in order to simulate the evolution of the groundwater composition within the candidate repository site of the Forsmark area. A series of climate periods is expected to be probable after the repository closure (temperate, periglacial and glacial) and, eventually, the area could be submerged under seawaters or under a lake of glacial melt waters. These environmental conditions will affect groundwater flow and composition around of the candidate repository volume. The present report summarizes the results obtained by the calculations which reproduce the hydrogeochemical evolution in the Forsmark area, and within the candidate repository volume. The hydrogeochemical evolution of groundwaters is one of the key factors affecting the chemical stability of the buffer and the canister. In this way, the main objective of the hydrogeochemical simulations is to assay the evolution of a series of safety assessment factors, such as salinity, redox potential, pH, and concentrations of iron, sulphide and potassium, among others. Using ConnectFlow, previous hydrological calculations have provided the transport of (1) the fractions of selected reference waters (Deep Saline, Old Meteoric, Glacial, Littorina and Altered Meteoric groundwaters), or (2) salinities, depending on the working team (Serco or Terrasolve). The results of the regional-scale groundwater flow modelling for each specific climate period are used as input of the geochemical models. Groundwater compositions have been modelled using PHREEQC, through mixing and chemical reactions between the waters obtained from the hydrogeological models and the reactive fracture-filling minerals. Both models (hydrological and geochemical) are not fully coupled, and it allows a description of the geochemical heterogeneity, which otherwise would be hard to attain. The stage of the open repository has been non-numerically analysed. Aspects as salinity, redox conditions

  11. SR-Site - hydrogeochemical evolution of the Forsmark site

    Salas, Joaquin; Molinero, Jorge; Juarez, Iker (Amphos 21 (Spain)); Gimeno, Maria Jose; Auque, Luis; Gomez, Javier (Univ. of Zaragoza (Spain))

    2010-12-15

    The present work has involved the development of a methodology in order to simulate the evolution of the groundwater composition within the candidate repository site of the Forsmark area. A series of climate periods is expected to be probable after the repository closure (temperate, periglacial and glacial) and, eventually, the area could be submerged under seawaters or under a lake of glacial melt waters. These environmental conditions will affect groundwater flow and composition around of the candidate repository volume. The present report summarizes the results obtained by the calculations which reproduce the hydrogeochemical evolution in the Forsmark area, and within the candidate repository volume. The hydrogeochemical evolution of groundwaters is one of the key factors affecting the chemical stability of the buffer and the canister. In this way, the main objective of the hydrogeochemical simulations is to assay the evolution of a series of safety assessment factors, such as salinity, redox potential, pH, and concentrations of iron, sulphide and potassium, among others. Using ConnectFlow, previous hydrological calculations have provided the transport of (1) the fractions of selected reference waters (Deep Saline, Old Meteoric, Glacial, Littorina and Altered Meteoric groundwaters), or (2) salinities, depending on the working team (Serco or Terrasolve). The results of the regional-scale groundwater flow modelling for each specific climate period are used as input of the geochemical models. Groundwater compositions have been modelled using PHREEQC, through mixing and chemical reactions between the waters obtained from the hydrogeological models and the reactive fracture-filling minerals. Both models (hydrological and geochemical) are not fully coupled, and it allows a description of the geochemical heterogeneity, which otherwise would be hard to attain. The stage of the open repository has been non-numerically analysed. Aspects as salinity, redox conditions

  12. Site investigation SFR. Vegetation in streams in the Forsmark area

    Andersson, Eva; Aquilonius, Karin; Sivars Becker, Lena; Borgiel, Mikael

    2011-09-01

    The streams in the model area of Forsmark have previously been thoroughly investigated regarding water chemistry, hydrology, bottom substrate, flooding, percentage coverage of macrophytes and fish migration. Retention of radionuclides in a stream ecosystem is assumed to occur by sorption to sediments or by uptake of radionuclides by macrophytes and it is therefore of interest to know the biomass and production of macrophytes in the streams included in a safety assessment. The general aim of this study was to examine the relation between biomass and the percentage cover of vegetation in streams in the Forsmark area. In this study streams within and nearby the candidate area in Forsmark was investigated. The somewhat larger streams Forsmarksaan and Olandsaan nearby the candidate area, are assumed to be more similar to future streams developing in Forsmark due to landrise, than the smaller streams present in the candidate area today. In total 22 vegetation samples were gathered in order to estimate the biomass at the sites. Percentage coverage of macrophytes, and dominating species were noted and the above ground macrophytes were sampled for biomass analysis. In the smaller streams, the biomass varied between 6 and almost 358 g dry weight per square metre. In the larger streams, the dry biomass varied between 0 and 247 g dry weight per square meter. There were no significant difference between macrophyte biomass in smaller and the larger stream. In total 13 macrophyte species were found. The biomass dry weight at 100% covering degree varied depending on macrophyte species. Although this was a rather small study, it is evident that the biomasses do vary a wide range between sampling squares in the area. However, although it may be difficult to use this data set to estimate the biomass in a specific square meter in the stream section, the relation between biomass weight and covering degree is sufficient to be used when fitting biomass to macrophyte coverage for entire

  13. Site investigation SFR. Vegetation in streams in the Forsmark area

    Andersson, Eva (Svensk Nuclear Fuel and Waste Management Co. (Sweden)); Aquilonius, Karin; Sivars Becker, Lena (Studsvik Nuclear AB (Sweden)); Borgiel, Mikael (Sveriges Vattenekologer AB (Sweden))

    2011-09-15

    The streams in the model area of Forsmark have previously been thoroughly investigated regarding water chemistry, hydrology, bottom substrate, flooding, percentage coverage of macrophytes and fish migration. Retention of radionuclides in a stream ecosystem is assumed to occur by sorption to sediments or by uptake of radionuclides by macrophytes and it is therefore of interest to know the biomass and production of macrophytes in the streams included in a safety assessment. The general aim of this study was to examine the relation between biomass and the percentage cover of vegetation in streams in the Forsmark area. In this study streams within and nearby the candidate area in Forsmark was investigated. The somewhat larger streams Forsmarksaan and Olandsaan nearby the candidate area, are assumed to be more similar to future streams developing in Forsmark due to landrise, than the smaller streams present in the candidate area today. In total 22 vegetation samples were gathered in order to estimate the biomass at the sites. Percentage coverage of macrophytes, and dominating species were noted and the above ground macrophytes were sampled for biomass analysis. In the smaller streams, the biomass varied between 6 and almost 358 g dry weight per square metre. In the larger streams, the dry biomass varied between 0 and 247 g dry weight per square meter. There were no significant difference between macrophyte biomass in smaller and the larger stream. In total 13 macrophyte species were found. The biomass dry weight at 100% covering degree varied depending on macrophyte species. Although this was a rather small study, it is evident that the biomasses do vary a wide range between sampling squares in the area. However, although it may be difficult to use this data set to estimate the biomass in a specific square meter in the stream section, the relation between biomass weight and covering degree is sufficient to be used when fitting biomass to macrophyte coverage for entire

  14. Forsmark site investigation. Reflection seismic studies in the Forsmark area, 2004: Stage 2

    Juhlin, Christopher; Palm, Hans [Uppsala Univ. (Sweden). Dept. of Earth Sciences

    2005-06-15

    Reflection seismic data were acquired in the Fall of 2004 in the Forsmark area, located about 140 km north of Stockholm, Sweden. The Forsmark area has been targeted by SKB as a possible storage site for spent nuclear fuel. About 25 km of high resolution (nominal source and receiver spacing of maximum 10 m and a minimum of 160 active channels) seismic data were acquired along 10 profiles, varying in length from about 1 km to over 4 km. Three of these profiles are extensions of profiles that were acquired in 2002 (Stage 1). While the 2002 Stage 1 profiles were geared towards acquiring data from within the relatively undeformed lens, the current study focused on acquiring data from the boundaries of the lens. Data acquisition was also concentrated towards the western part of the candidate area. Data were acquired using a combination of the same explosive source as in Stage 1 (1575 g of explosives) and the VIBSIST mechanical source consisting of an industrial hammer mounted on a tractor. Earlier tests in Laxemar had shown that the VIBSIST source gives comparable data to the explosive source and is less expensive. It can also be used in areas where explosives are prohibited, such as close to the nuclear power plant. At present, the source cannot be used in the terrain, therefore an explosive component is still required. About 80% of the 2100 source points were activated using the VIBSIST system. Stacked sections from the new profiles are generally consistent with the Stage 1 results. Reflections from the prominent south dipping A1 reflector can be observed on most profiles, however, it is not clear if it can be traced all the way to the surface. Neither is it clearly observed below the power plant, suggesting its lateral extent is limited to the west. Instead, a gently east dipping reflector (B8) is interpreted below the power plant. Reflections consistent with the A2 reflector are also found on two profiles, but cannot be traced very far to the south, suggesting that

  15. Discrete-Feature Model Implementation of SDM-Site Forsmark

    Geier, Joel

    2010-03-01

    A discrete-feature model (DFM) was implemented for the Forsmark repository site based on the final site descriptive model from surface based investigations. The discrete-feature conceptual model represents deformation zones, individual fractures, and other water-conducting features around a repository as discrete conductors surrounded by a rock matrix which, in the present study, is treated as impermeable. This approximation is reasonable for sites in crystalline rock which has very low permeability, apart from that which results from macroscopic fracturing. Models are constructed based on the geological and hydrogeological description of the sites and engineering designs. Hydraulic heads and flows through the network of water-conducting features are calculated by the finite-element method, and are used in turn to simulate migration of non-reacting solute by a particle-tracking method, in order to estimate the properties of pathways by which radionuclides could be released to the biosphere. Stochastic simulation is used to evaluate portions of the model that can only be characterized in statistical terms, since many water-conducting features within the model volume cannot be characterized deterministically. Chapter 2 describes the methodology by which discrete features are derived to represent water-conducting features around the hypothetical repository at Forsmark (including both natural features and features that result from the disturbance of excavation), and then assembled to produce a discrete-feature network model for numerical simulation of flow and transport. Chapter 3 describes how site-specific data and repository design are adapted to produce the discrete-feature model. Chapter 4 presents results of the calculations. These include utilization factors for deposition tunnels based on the emplacement criteria that have been set forth by the implementers, flow distributions to the deposition holes, and calculated properties of discharge paths as well as

  16. Discrete-Feature Model Implementation of SDM-Site Forsmark

    Geier, Joel (Clearwater Hardrock Consulting, Corvallis, OR (United States))

    2010-03-15

    A discrete-feature model (DFM) was implemented for the Forsmark repository site based on the final site descriptive model from surface based investigations. The discrete-feature conceptual model represents deformation zones, individual fractures, and other water-conducting features around a repository as discrete conductors surrounded by a rock matrix which, in the present study, is treated as impermeable. This approximation is reasonable for sites in crystalline rock which has very low permeability, apart from that which results from macroscopic fracturing. Models are constructed based on the geological and hydrogeological description of the sites and engineering designs. Hydraulic heads and flows through the network of water-conducting features are calculated by the finite-element method, and are used in turn to simulate migration of non-reacting solute by a particle-tracking method, in order to estimate the properties of pathways by which radionuclides could be released to the biosphere. Stochastic simulation is used to evaluate portions of the model that can only be characterized in statistical terms, since many water-conducting features within the model volume cannot be characterized deterministically. Chapter 2 describes the methodology by which discrete features are derived to represent water-conducting features around the hypothetical repository at Forsmark (including both natural features and features that result from the disturbance of excavation), and then assembled to produce a discrete-feature network model for numerical simulation of flow and transport. Chapter 3 describes how site-specific data and repository design are adapted to produce the discrete-feature model. Chapter 4 presents results of the calculations. These include utilization factors for deposition tunnels based on the emplacement criteria that have been set forth by the implementers, flow distributions to the deposition holes, and calculated properties of discharge paths as well as

  17. Encapsulation plant at Forsmark

    Nystroem, Anders

    2007-08-01

    SKB has already carried out a preliminary study of an encapsulation plant detached from Clab (Central interim storage for spent fuels). This stand-alone encapsulation plant was named FRINK and its assumed siting was the above-ground portion of the final repository, irrespective of the repository's location. The report previously presented was produced in cooperation with BNFL Engineering Ltd in Manchester and the fuel reception technical solution was examined by Gesellschaft fuer Nuklear-Service mbH (GNS) in Hannover and by Societe Generale pour les Techniques Nouvelles (SGN) in Paris. This report is an update of the earlier preliminary study report and is based on the assumption that the encapsulation plant and also the final repository will be sited in the Forsmark area. SKB's main alternative for siting the encapsulation plant is next to Clab. Planning of this facility is ongoing and technical solutions from the planning work have been incorporated in this report. An encapsulation plant placed in proximity to any final repository in Forsmark forms part of the alternative presentation in the application for permission to construct and operate an installation at Clab. The main technical difference between the planned encapsulation plant at Clab and an encapsulation plant at a final repository at Forsmark is how the fuel is managed and prepared before actual encapsulation. Fuel reception at the encapsulation plant in Forsmark would be dry, i.e. there would be no water-filled pools at the facility. Clab is used for verificatory fuel measurements, sorting and drying of the fuel before transport to Forsmark. This means that Clab will require a measure of rebuilding and supplementary equipment. In purely technical terms, the prospects for building an encapsulation plant sited at Forsmark are good. A description of the advantages and drawbacks of siting the encapsulation plant at Clab as opposed to any final repository at Forsmark is presented in a separate report

  18. Encapsulation plant at Forsmark

    Nystroem, Anders

    2007-08-15

    SKB has already carried out a preliminary study of an encapsulation plant detached from Clab (Central interim storage for spent fuels). This stand-alone encapsulation plant was named FRINK and its assumed siting was the above-ground portion of the final repository, irrespective of the repository's location. The report previously presented was produced in cooperation with BNFL Engineering Ltd in Manchester and the fuel reception technical solution was examined by Gesellschaft fuer Nuklear-Service mbH (GNS) in Hannover and by Societe Generale pour les Techniques Nouvelles (SGN) in Paris. This report is an update of the earlier preliminary study report and is based on the assumption that the encapsulation plant and also the final repository will be sited in the Forsmark area. SKB's main alternative for siting the encapsulation plant is next to Clab. Planning of this facility is ongoing and technical solutions from the planning work have been incorporated in this report. An encapsulation plant placed in proximity to any final repository in Forsmark forms part of the alternative presentation in the application for permission to construct and operate an installation at Clab. The main technical difference between the planned encapsulation plant at Clab and an encapsulation plant at a final repository at Forsmark is how the fuel is managed and prepared before actual encapsulation. Fuel reception at the encapsulation plant in Forsmark would be dry, i.e. there would be no water-filled pools at the facility. Clab is used for verificatory fuel measurements, sorting and drying of the fuel before transport to Forsmark. This means that Clab will require a measure of rebuilding and supplementary equipment. In purely technical terms, the prospects for building an encapsulation plant sited at Forsmark are good. A description of the advantages and drawbacks of siting the encapsulation plant at Clab as opposed to any final repository at Forsmark is presented in a separate

  19. Soils and site types in the Forsmark area

    Lundin, Lars; Lode, Elve; Stendahl, Johan; Melkerud, Per-Arne; Bjoerkvald, Louise; Thorstensson, Anna

    2004-01-01

    Investigations to give prerequisites for long-term storage of nuclear waste are made by the Swedish Nuclear Fuel and Waste Management Company (SKB AB). Ecosystem functions are crucial in this management. The range of the scope is wide including bedrock, regolith, hydrosphere and biosphere. The interface between deep geological formations and surface systems is then considered very important. This would be the top of the regolith, where soils are developed. Special attention has been paid to these layers with fairly comprehensive investigations. Field investigations were made for one of the candidate areas, the Forsmark area, in 2002 by the Department of Forest Soils, Swedish University of Agricultural Sciences. In these ecosystem functions, the upper part of the regolith is one crucial component and the focus in the investigations was on the upper metre of the soil. Variables determined include vegetation, hydrology, soil parent material, textural composition, soil type and physical and chemical properties of relevant soil layers. Methods used in the investigation coincide with those of the Swedish Forest Soil Inventory, which provide possibilities to compare properties in the Forsmark area with those of total Sweden and regions of the country. Soil properties were determined thoroughly on eight site types in two replicates to provide statistical significance. However, this meant that the investigation did not have a total spatial coverage. Instead, the spatial distribution of soils in the area was determined from a GIS based on the inventory made and information on vegetation types, distribution of Quaternary deposits and a hydrological index. From this GIS, distributions were compared with other parts of the country. The geographical location of the Forsmark area (N 60 deg 22 min; E 18 deg 13 min) is on the northeast coast of central Sweden bordering to the Bothnian Sea. The area is low-lying, reaching only up to 15 m above the sea, which means that the soils are

  20. Geological evolution, palaeoclimate and historical development of the Forsmark and Laxemar-Simpevarp areas. Site descriptive modelling SDM-Site

    Soederbaeck, Bjoern [ed.

    2008-06-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterization at two different locations, the Forsmark and Laxemar-Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. The site investigations started in 2002 and were completed in 2007. The analysis and modelling of data from the site investigations, which have taken place during and after these investigations, provide a foundation for the development of an integrated, multidisciplinary site descriptive model (SDM) for each of the two sites. A site descriptive model constitutes a description of the site and its regional setting, covering the current state of the geosphere and the biosphere, as well as those natural processes that affect or have affected their long-term development. Hitherto, a number of reports presenting preliminary site descriptive models for Forsmark and Laxemar-Simpevarp have been published. In these reports, the evolutionary and historical aspects of the site were included in a separate chapter. The present report comprises a further elaboration of the evolutionary and historical information included in the preliminary SDM reports, but presented here in a separate, supplementary report to the final site description, SDM-Site. The report is common to the two investigated areas, and the overall objective is to describe the long-term geological evolution, the palaeoclimate, and the post-glacial development of ecosystems and of the human population at the two sites. The report largely consists of a synthesis of information derived from the scientific literature and other sources not related to the site investigations. However, considerable information from the site investigations that has contributed to our understanding of the past development at each site is also included. This unique synthesis of both published information in a regional perspective and new site-specific information breaks new ground in our understanding

  1. Geological evolution, palaeoclimate and historical development of the Forsmark and Laxemar-Simpevarp areas. Site descriptive modelling SDM-Site

    Soederbaeck, Bjoern

    2008-06-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterization at two different locations, the Forsmark and Laxemar-Simpevarp areas, with the objective of siting a geological repository for spent nuclear fuel. The site investigations started in 2002 and were completed in 2007. The analysis and modelling of data from the site investigations, which have taken place during and after these investigations, provide a foundation for the development of an integrated, multidisciplinary site descriptive model (SDM) for each of the two sites. A site descriptive model constitutes a description of the site and its regional setting, covering the current state of the geosphere and the biosphere, as well as those natural processes that affect or have affected their long-term development. Hitherto, a number of reports presenting preliminary site descriptive models for Forsmark and Laxemar-Simpevarp have been published. In these reports, the evolutionary and historical aspects of the site were included in a separate chapter. The present report comprises a further elaboration of the evolutionary and historical information included in the preliminary SDM reports, but presented here in a separate, supplementary report to the final site description, SDM-Site. The report is common to the two investigated areas, and the overall objective is to describe the long-term geological evolution, the palaeoclimate, and the post-glacial development of ecosystems and of the human population at the two sites. The report largely consists of a synthesis of information derived from the scientific literature and other sources not related to the site investigations. However, considerable information from the site investigations that has contributed to our understanding of the past development at each site is also included. This unique synthesis of both published information in a regional perspective and new site-specific information breaks new ground in our understanding

  2. Description of surface hydrology and near-surface hydrogeology at Forsmark. Site descriptive modelling SDM. Site Forsmark

    Johansson, Per-Olof

    2008-12-01

    This report describes the modelling of the surface hydrology and near-surface hydrogeology that was performed for the final site descriptive model of Forsmark produced in the site investigation stage, SDM-Site Forsmark. The comprehensive investigation and monitoring programme forms a strong basis for the developed conceptual and descriptive model of the hydrological and near-surface hydrological system of the site investigation area. However, there are some remaining uncertainties regarding the interaction of deep and near-surface groundwater and surface water of importance for the understanding of the system: The groundwaters in till below Lake Eckarfjaerden, Lake Gaellbotraesket, Lake Fiskarfjaerden and Lake Bolundsfjaerden have high salinities. The hydrological and hydrochemical interpretations indicate that these waters are relict waters of mainly marine origin. From the perspective of the overall water balance, the water below the central parts of the lakes can be considered as stagnant. However, according to the hydrochemical interpretation, these waters also contain weak signatures of deep saline water. Rough chloride budget calculations for the Gaellbotraesket depression also raise the question of a possible upward flow of deep groundwater. No absolute conclusion can be drawn from the existing data analyses regarding the key question of whether there is a small ongoing upward flow of deep saline water. However, Lake Bolundsfjaerden is an exception where the clear downward flow gradient from the till to the bedrock excludes the possibility of an active deep saline source. The available data indicate that there are no discharge areas for flow systems involving deep bedrock groundwater in the northern part of the tectonic lens, where the repository is planned to be located (the so-called 'target area'). However, it can not be excluded that such discharge areas exist. Data indicate that the prevailing downward vertical flow gradients from the QD to the bedrock

  3. Description of surface hydrology and near-surface hydrogeology at Forsmark. Site descriptive modelling SDM. Site Forsmark

    Johansson, Per-Olof (Artesia Grundvattenkonsult AB, Taeby (Sweden))

    2008-12-15

    This report describes the modelling of the surface hydrology and near-surface hydrogeology that was performed for the final site descriptive model of Forsmark produced in the site investigation stage, SDM-Site Forsmark. The comprehensive investigation and monitoring programme forms a strong basis for the developed conceptual and descriptive model of the hydrological and near-surface hydrological system of the site investigation area. However, there are some remaining uncertainties regarding the interaction of deep and near-surface groundwater and surface water of importance for the understanding of the system: The groundwaters in till below Lake Eckarfjaerden, Lake Gaellbotraesket, Lake Fiskarfjaerden and Lake Bolundsfjaerden have high salinities. The hydrological and hydrochemical interpretations indicate that these waters are relict waters of mainly marine origin. From the perspective of the overall water balance, the water below the central parts of the lakes can be considered as stagnant. However, according to the hydrochemical interpretation, these waters also contain weak signatures of deep saline water. Rough chloride budget calculations for the Gaellbotraesket depression also raise the question of a possible upward flow of deep groundwater. No absolute conclusion can be drawn from the existing data analyses regarding the key question of whether there is a small ongoing upward flow of deep saline water. However, Lake Bolundsfjaerden is an exception where the clear downward flow gradient from the till to the bedrock excludes the possibility of an active deep saline source. The available data indicate that there are no discharge areas for flow systems involving deep bedrock groundwater in the northern part of the tectonic lens, where the repository is planned to be located (the so-called 'target area'). However, it can not be excluded that such discharge areas exist. Data indicate that the prevailing downward vertical flow gradients from the QD to

  4. Numerical modelling of surface hydrology and near-surface hydrogeology at Forsmark. Site descriptive modelling SDM. Site Forsmark

    Bosson, Emma (Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)); Gustafsson, Lars-Goeran; Sassner, Mona (DHI Sverige AB, Stockholm (Sweden))

    2008-09-15

    SKB is currently performing site investigations at two potential sites for a final repository for spent nuclear fuel. This report presents results of water flow and solute transport modelling of the Forsmark site. The modelling reported in this document focused on the near-surface groundwater, i.e. groundwater in Quaternary deposits and shallow rock, and surface water systems, and was performed using the MIKE SHE tool. The most recent site data used in the modelling were delivered in the Forsmark 2.3 dataset, which had its 'data freeze' on March 31, 2007. The present modelling is performed in support of the final version of the Forsmark site description that is produced during the site investigation phase. In this work, the hydrological modelling system MIKE SHE has been used to describe near-surface groundwater flow and the contact between groundwater and surface water at the Forsmark site. The surface water system at Forsmark is described with the one-dimensional 'channel flow' modelling tool MIKE 11, which is fully and dynamically integrated with MIKE SHE. The MIKE SHE model was updated with data from the F2.3 data freeze. The main updates concerned the geological description of the saturated zone and the time series data on water levels and surface water discharges. The time series data used as input data and for calibration and validation was extended until the Forsmark 2.3 data freeze (March 31, 2007). The present work can be subdivided into the following four parts: 1. Update of the numerical flow model. 2. Sensitivity analysis and calibration of the model parameters. 3. Validation of the calibrated model, followed by evaluation and identification of discrepancies between measurements and model results. 4. Additional sensitivity analysis and calibration in order to resolve the problems identified in point three above. The main actions taken during the calibration can be summarised as follows: 1. The potential evapotranspiration was

  5. Soils and site types in the Forsmark area

    Lundin, Lars; Lode, Elve; Stendahl, Johan; Melkerud, Per-Arne; Bjoerkvald, Louise; Thorstensson, Anna [Swedish Univ. of Agricultural Sciences, Uppsala (Sweden). Dept. of Forest Soils

    2004-01-01

    Investigations to give prerequisites for long-term storage of nuclear waste are made by the Swedish Nuclear Fuel and Waste Management Company (SKB AB). Ecosystem functions are crucial in this management. The range of the scope is wide including bedrock, regolith, hydrosphere and biosphere. The interface between deep geological formations and surface systems is then considered very important. This would be the top of the regolith, where soils are developed. Special attention has been paid to these layers with fairly comprehensive investigations. Field investigations were made for one of the candidate areas, the Forsmark area, in 2002 by the Department of Forest Soils, Swedish University of Agricultural Sciences. In these ecosystem functions, the upper part of the regolith is one crucial component and the focus in the investigations was on the upper metre of the soil. Variables determined include vegetation, hydrology, soil parent material, textural composition, soil type and physical and chemical properties of relevant soil layers. Methods used in the investigation coincide with those of the Swedish Forest Soil Inventory, which provide possibilities to compare properties in the Forsmark area with those of total Sweden and regions of the country. Soil properties were determined thoroughly on eight site types in two replicates to provide statistical significance. However, this meant that the investigation did not have a total spatial coverage. Instead, the spatial distribution of soils in the area was determined from a GIS based on the inventory made and information on vegetation types, distribution of Quaternary deposits and a hydrological index. From this GIS, distributions were compared with other parts of the country. The geographical location of the Forsmark area (N 60 deg 22 min; E 18 deg 13 min) is on the northeast coast of central Sweden bordering to the Bothnian Sea. The area is low-lying, reaching only up to 15 m above the sea, which means that the soils are

  6. SR-Site - sulphide content in the groundwater at Forsmark

    Tullborg, E-L (Terralogica (Sweden)); Smellie, J (Conterra (Sweden)); Nilsson, A-Ch (Geosigma (Sweden)); Gimeno, M J; Auque, LF (Univ. of Zaragoza (Spain)); Bruchert, V (Stockholms Universitet (Sweden)); Molinero, J (Amphos21 (Spain))

    2010-12-15

    Sulphide concentrations in groundwater play a key role in the long-term reliability of the metal canisters containing the radioactive waste within a disposal facility for nuclear waste. This is because sulphide in the groundwaters circulating in the vicinity of the deposition tunnels can react with copper in the canisters causing corrosion and therefore reducing their expected lifetime; in a worst case scenario erosion of the bentonite buffer material will expose the canister more rapidly to the fracture groundwater.Sulphide in the groundwater is predominantly microbially produced and thereby controlled by the content of oxidised sulphur sources, organics (carbon sources), reductants (mainly Fe(II), DOC, H{sub 2} and CH{sub 4}), and also flow and mixing of different groundwater types. In addition, achieved saturation in respect to amorphous Fe-monosulphide will control the possible maximum values and will also limit the Fe2+ and S2- values in the groundwater. The aim of this report is to assess realistic, representative and reliable sulphide groundwater concentrations at present conditions in Forsmark and also to evaluate possible changes during different climatic conditions covering the repository operation period (some tens to hundreds of years), post closure conditions (some thousand of years) and the proceeding temperate period (some tens of thousands of years) which may be extended due to enhanced greenhouse effects etc. It is expected that this period will be followed by the onset of the next glaciation during which periglacial (permafrost), glacial and postglacial conditions may succeed each other. To achieve these aims, an evaluation is performed of all the sulphide-related data reported from the Forsmark site investigations /Laaksoharju et al. 2008/ and later monitoring campaigns, all of which are stored in the Sicada database. This evaluation shows that values from the Complete Chemical Characterisation (CCC) sampling are usually lower than those measured

  7. SR-Site - sulphide content in the groundwater at Forsmark

    Tullborg, E-L; Smellie, J; Nilsson, A-Ch; Gimeno, M J; Auque, LF; Bruchert, V; Molinero, J

    2010-12-01

    Sulphide concentrations in groundwater play a key role in the long-term reliability of the metal canisters containing the radioactive waste within a disposal facility for nuclear waste. This is because sulphide in the groundwaters circulating in the vicinity of the deposition tunnels can react with copper in the canisters causing corrosion and therefore reducing their expected lifetime; in a worst case scenario erosion of the bentonite buffer material will expose the canister more rapidly to the fracture groundwater.Sulphide in the groundwater is predominantly microbially produced and thereby controlled by the content of oxidised sulphur sources, organics (carbon sources), reductants (mainly Fe(II), DOC, H 2 and CH 4 ), and also flow and mixing of different groundwater types. In addition, achieved saturation in respect to amorphous Fe-monosulphide will control the possible maximum values and will also limit the Fe 2+ and S 2- values in the groundwater. The aim of this report is to assess realistic, representative and reliable sulphide groundwater concentrations at present conditions in Forsmark and also to evaluate possible changes during different climatic conditions covering the repository operation period (some tens to hundreds of years), post closure conditions (some thousand of years) and the proceeding temperate period (some tens of thousands of years) which may be extended due to enhanced greenhouse effects etc. It is expected that this period will be followed by the onset of the next glaciation during which periglacial (permafrost), glacial and postglacial conditions may succeed each other. To achieve these aims, an evaluation is performed of all the sulphide-related data reported from the Forsmark site investigations /Laaksoharju et al. 2008/ and later monitoring campaigns, all of which are stored in the Sicada database. This evaluation shows that values from the Complete Chemical Characterisation (CCC) sampling are usually lower than those measured during

  8. Site description of the SFR area at Forsmark at completion of the site investigation phase. SDM-PSU Forsmark

    NONE

    2013-05-15

    The site descriptive model (SDM) presented in this report is an integrated model for bedrock geology, rock mechanics, bedrock hydrogeology and bedrock hydrogeochemistry of the site investigated in the SFR extension project (PSU). A description of the surface system is also included in the report. However, the surface system is not integrated with the other disciplines as new data regarding the surface system will not be available until after the completion of SDM-PSU. It is noted that SDM-PSU does not include all disciplines handled in SDM-Site Forsmark (SKB 2008b), the focus is to produce a site description that meets the needs of the SFR extension project. The overall objective of the SFR extension project is to have the application for the extension ready by 2013. This report presents an integrated site model incorporating the historic data acquired from the investigations for and construction of the existing SFR facility (1980-1986), as well as from the recent investigations for the planned extension of SFR (2008-2009). It also provides a summary of the abundant underlying data and the discipline-specific models that support the integrated site model. The description relies heavily on background reports concerning detailed data analyses and modelling in the different disciplines. It is noteworthy that the investigations conducted during the SFR extension project were guided by the choice of site prior to the investigations, which was based on the experience gained during the construction of the existing SFR facility.

  9. Site description of the SFR area at Forsmark at completion of the site investigation phase. SDM-PSU Forsmark

    2013-05-01

    The site descriptive model (SDM) presented in this report is an integrated model for bedrock geology, rock mechanics, bedrock hydrogeology and bedrock hydrogeochemistry of the site investigated in the SFR extension project (PSU). A description of the surface system is also included in the report. However, the surface system is not integrated with the other disciplines as new data regarding the surface system will not be available until after the completion of SDM-PSU. It is noted that SDM-PSU does not include all disciplines handled in SDM-Site Forsmark (SKB 2008b), the focus is to produce a site description that meets the needs of the SFR extension project. The overall objective of the SFR extension project is to have the application for the extension ready by 2013. This report presents an integrated site model incorporating the historic data acquired from the investigations for and construction of the existing SFR facility (1980-1986), as well as from the recent investigations for the planned extension of SFR (2008-2009). It also provides a summary of the abundant underlying data and the discipline-specific models that support the integrated site model. The description relies heavily on background reports concerning detailed data analyses and modelling in the different disciplines. It is noteworthy that the investigations conducted during the SFR extension project were guided by the choice of site prior to the investigations, which was based on the experience gained during the construction of the existing SFR facility

  10. Validation of the marine vegetation model in Forsmark. SFR-Site Forsmark

    Aquilonius, Karin (Studsvik Nuclear AB (Sweden)); Qvarfordt, Susanne; Borgiel, Micke (Sveriges Vattenekologer AB (Sweden))

    2011-04-15

    A regression model implemented in GIS of the marine vegetation in Forsmark were developed by SKB /Aquilonius 2010/ based on field investigations and video surveys /Fredriksson 2005/ and from correlations of field data and physical properties /Carlen et al. 2007/. The marine vegetation model describes distribution and biomasses of the marine vegetation and is used as input data in the dose modeling within the safety assessments performed by the SKB. In this study the predictive performance of the vegetation model in the less examined parts of the marine area in Forsmark is evaluated. In general, the vegetation model works very well in predicting absence of biomass, except for Red algae. In total and for Fucus sp., the model also predicts the observed biomass fairly well. However, for phanerogams, Chara sp., filamentous algae and red algae the vegetation model works less well in predicting biomass

  11. Validation of the marine vegetation model in Forsmark. SFR-Site Forsmark

    Aquilonius, Karin; Qvarfordt, Susanne; Borgiel, Micke

    2011-04-01

    A regression model implemented in GIS of the marine vegetation in Forsmark were developed by SKB /Aquilonius 2010/ based on field investigations and video surveys /Fredriksson 2005/ and from correlations of field data and physical properties /Carlen et al. 2007/. The marine vegetation model describes distribution and biomasses of the marine vegetation and is used as input data in the dose modeling within the safety assessments performed by the SKB. In this study the predictive performance of the vegetation model in the less examined parts of the marine area in Forsmark is evaluated. In general, the vegetation model works very well in predicting absence of biomass, except for Red algae. In total and for Fucus sp., the model also predicts the observed biomass fairly well. However, for phanerogams, Chara sp., filamentous algae and red algae the vegetation model works less well in predicting biomass

  12. Background complementary hydrogeochemical studies. SDM-Site Forsmark

    Kalinowski, Birgitta E. (ed.)

    2008-08-15

    The overall objectives of the hydrogeochemical description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site and to develop models that fulfil the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and pore water and their evolution with time. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. Past climate changes are one of the major driving forces for hydrogeochemical changes and therefore of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the crystalline bedrock of the Fennoscandian Shield. Understanding current undisturbed hydrochemical conditions at the proposed repository site is important when predicting future changes in groundwater chemistry. The causes of copper corrosion and/or bentonite degradation are of particular interest as they may jeopardise the long-term integrity of the planned SKB repository system. Thus, the following variables are considered for the hydrogeochemical site descriptive modelling: pH, Eh, sulphur species, iron, manganese, uranium, carbonate, phosphate, nitrogen species, total dissolved solids (TDS), isotopes, colloids, fulvic and humic acids and microorganisms. In addition, dissolved gases (e.g. carbon dioxide, methane and hydrogen) are of interest because of their likely participation in microbial reactions. In this series of reports, the final hydrogeochemical evaluation work of the site investigation at the Forsmark site, is presented. The work was conducted by SKB's hydrogeochemical project group, ChemNet, which consists of independent consultants and university researchers with expertise

  13. Advanced on-site conceptual simulator for Forsmark 3

    Johansson, G.; Sjoestrand, K.

    1984-01-01

    On-site conceptual simulators have been extensively used at Swedish nuclear power plants. Despite having access to identical replica simulators, both the Swedish State Power Board and the Swedish private power industry have ordered conceptual simulators during 1982. The motivation has been that a complete training programme requires access to both a replica and a conceptual simulator. The replica simulator is perfect for training in control room behaviour but less appropriate for ensuring deeper process understanding. On the other hand, the conceptual simulator is not well suited for getting the personnel acquainted with the control room but is perfect for extending their knowledge of the plant processes. In order to give a realistic description of these processes, the conceptual simulator model must be fairly advanced. The Forsmark 3 conceptual simulator simulates the entire primary system, including the details of the steam and feedwater systems. Considerable attention has also been devoted to the presentation of calculated variables. For example, all the variables in the data base (approx. 6600) can be presented on colour-graphic CRTs as functions of time. (author)

  14. Numerical modelling of solute transport at Forsmark with MIKE SHE. Site descriptive modelling SDM-Site Forsmark

    Gustafsson, Lars-Goeran; Sassner, Mona (DHI Sverige AB, Stockholm (Sweden)); Bosson, Emma (Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden))

    2008-12-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is performing site investigations at two different locations in Sweden, referred to as the Forsmark and Laxemar areas, with the objective of siting a final repository for high-level radioactive waste. Data from the site investigations are used in a variety of modelling activities. This report presents model development and results of numerical transport modelling based on the numerical flow modelling of surface water and near-surface groundwater at the Forsmark site. The numerical modelling was performed using the modelling tool MIKE SHE and is based on the site data and conceptual model of the Forsmark areas. This report presents solute transport applications based on both particle tracking simulations and advection-dispersion calculations. The MIKE SHE model is the basis for the transport modelling presented in this report. Simulation cases relevant for the transport from a deep geological repository have been studied, but also the pattern of near surface recharge and discharge areas. When the main part of the modelling work presented in this report was carried out, the flow modelling of the Forsmark site was not finalised. Thus, the focus of this work is to describe the sensitivity to different transport parameters, and not to point out specific areas as discharge areas from a future repository (this is to be done later, within the framework of the safety assessment). In the last chapter, however, results based on simulations with the re-calibrated MIKE SHE flow model are presented. The results from the MIKE SHE water movement calculations were used by cycling the calculated transient flow field for a selected one-year period as many times as needed to achieve the desired simulation period. The solute source was located either in the bedrock or on top of the model. In total, 15 different transport simulation cases were studied. Five of the simulations were particle tracking simulations, whereas the rest

  15. Numerical modelling of solute transport at Forsmark with MIKE SHE. Site descriptive modelling SDM-Site Forsmark

    Gustafsson, Lars-Goeran; Sassner, Mona; Bosson, Emma

    2008-12-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is performing site investigations at two different locations in Sweden, referred to as the Forsmark and Laxemar areas, with the objective of siting a final repository for high-level radioactive waste. Data from the site investigations are used in a variety of modelling activities. This report presents model development and results of numerical transport modelling based on the numerical flow modelling of surface water and near-surface groundwater at the Forsmark site. The numerical modelling was performed using the modelling tool MIKE SHE and is based on the site data and conceptual model of the Forsmark areas. This report presents solute transport applications based on both particle tracking simulations and advection-dispersion calculations. The MIKE SHE model is the basis for the transport modelling presented in this report. Simulation cases relevant for the transport from a deep geological repository have been studied, but also the pattern of near surface recharge and discharge areas. When the main part of the modelling work presented in this report was carried out, the flow modelling of the Forsmark site was not finalised. Thus, the focus of this work is to describe the sensitivity to different transport parameters, and not to point out specific areas as discharge areas from a future repository (this is to be done later, within the framework of the safety assessment). In the last chapter, however, results based on simulations with the re-calibrated MIKE SHE flow model are presented. The results from the MIKE SHE water movement calculations were used by cycling the calculated transient flow field for a selected one-year period as many times as needed to achieve the desired simulation period. The solute source was located either in the bedrock or on top of the model. In total, 15 different transport simulation cases were studied. Five of the simulations were particle tracking simulations, whereas the rest

  16. Forsmark site investigation. Programme for further investigations of geosphere and biosphere

    NONE

    2005-01-01

    of the geological and ecological conditions in the area has largely been completed. In order to investigate the bedrock at depth, five deep (1,000 m) and two shallower cored boreholes have been drilled and documented. Drilling of a sixth deep cored borehole is under way. 19 percussion boreholes have been drilled, partly to supply core drilling with flushing water and partly to investigate the bedrock. A comprehensive, preliminary site description (version 1.1) has been published. The work of compiling all information from the initial site investigation is under way and will result in version 1.2 of the site description. The consultation process for a possible deep repository in Forsmark has been established in accordance with the provisions of the Environmental Code. An active information and communication programme has been established for ongoing dialogue with nearby residents, the public, Oesthammar Municipality, neighbouring municipalities and other local stakeholders.

  17. Forsmark site investigation. Programme for further investigations of geosphere and biosphere

    2005-01-01

    geological and ecological conditions in the area has largely been completed. In order to investigate the bedrock at depth, five deep (1,000 m) and two shallower cored boreholes have been drilled and documented. Drilling of a sixth deep cored borehole is under way. 19 percussion boreholes have been drilled, partly to supply core drilling with flushing water and partly to investigate the bedrock. A comprehensive, preliminary site description (version 1.1) has been published. The work of compiling all information from the initial site investigation is under way and will result in version 1.2 of the site description. The consultation process for a possible deep repository in Forsmark has been established in accordance with the provisions of the Environmental Code. An active information and communication programme has been established for ongoing dialogue with nearby residents, the public, Oesthammar Municipality, neighbouring municipalities and other local stakeholders

  18. Mapping of reed in shallow bays. SFR-Site Forsmark

    Stroemgren, Maarten; Lindgren, Fredrik (Umeaa Univ. (Sweden))

    2011-03-15

    The regolith-lake development model (RLDM) describes the development of shallow bays to lakes and the infilling of lakes in the Forsmark area during an interglacial. The sensitivity analysis has shown the need for an update of the infill procedure in the RLDM. Data from the mapping of reed in shallow bays in the Forsmark area will be used to improve the infill procedure of an updated RLDM. The field work was performed in August 26-31, 2010. The mapping of reed was done in 124 points. In these points, coordinates and water depth were mapped using an echo sounder and a DGPS. Quaternary deposits and the thickness of soft sediments were mapped using an earth probe. Measurement points were delivered in ESRI shape format with coordinates in RT90 2.5 gon W and altitudes in the RHB70 system for storage in SKB's GIS data base

  19. Rock types and ductile structures on a rock domain basis, and fracture orientation and mineralogy on a deformation zone basis. Preliminary site description. Forsmark area - version 1.2

    Stephens, Michael [Geological Survey of Sweden, Uppsala (Sweden); Forssberg, Ola [Golder Associates AB, Uppsala (Sweden)

    2006-09-15

    This report presents the results of the analysis of base geological data in order to establish the dominant rock type, the subordinate rock types and the orientation of ductile mineral fabrics within each rock domain included in the regional geological model, version 1.2. An assessment of the degree of homogeneity of each domain is also provided. The analytical work has utilised the presentation of data in the form of histograms and stereographic projections. Fisher means and K values or best-fit great circles and corresponding pole values have been calculated for the ductile structural data. These values have been used in the geometric modelling of rock domains in the regional model, version 1.2. Furthermore, all analytical results have been used in the assignment of properties to rock domains in this model. A second analytical component reported here addresses the orientation and mineralogy of fractures in the deterministic deformation zones that are included in the regional geological model, version 1.2. The analytical work has once again utilised the presentation of data in the form of histograms and stereographic projections. Fisher means and K values are presented for the orientation of fracture sets in the deterministic deformation zones that have been identified with the help of new borehole data. The frequencies of occurrence of different minerals along the fractures in these deformation zones as well as the orientation of fractures in the zones, along which different minerals occur, are also presented. The results of the analyses have been used in the establishment of a conceptual structural model for the Forsmark site and in the assignment of properties to deterministic deformation zones in model version 1.2.

  20. The marine ecosystems at Forsmark and Laxemar-Simpevarp. SR-Site Biosphere

    Aquilonius, Karin

    2010-12-01

    The overall objective of this report is to provide a thorough description of the marine ecosystems at the sites Forsmark and Laxemar-Simpevarp, to identify processes in these ecosystems of importance to transfer and accumulation of radionuclides and, finally based on this knowledge, develop parameters to be used for the marine ecosystem in the safety analysis SR-Site. The report includes a thorough description of the major components in the marine ecosystems in Forsmark and Laxemar-Simpevarp, and covers the following areas: chemical and physical characteristics, climate and meteorology, morphology and regolith, biota in the marine ecosystem, human impact, water exchange and historical evolution at the sites. The site specific characteristics are compared with marine data from the Baltic region. Marine ecosystem modeling and mass balances calculations for carbon and a number of other elements were carried out to further improve the understanding of the marine ecosystems. Important processes for the safety assessment are identified, described and evaluated according to a systematic method. The derivation of marine ecosystem parameters and the resulting parameters is presented. The last chapter of the report aims at summarizing the knowledge of the marine ecosystems at the two areas. In comparison with the Gulf of Bothnia and the Baltic Proper, salinity is somewhat lower in Forsmark and Laxemar-Simpevarp respectively. The nitrogen and phosphorus levels at the two sites are low to moderately high compared with environmental monitoring data for corresponding areas in the Baltic Sea. In Forsmark, nitrogen seems to be the limiting nutrient during the summer months. In Laxemar-Simpevarp, nitrogen seems to be the limiting nutrient in the outer areas and phosphorus in the inner bays. This coincides with the general conditions in the Bothnian Sea (Forsmark) and the Baltic Proper (Laxemar-Simpevarp). The annual mean water temperature in Forsmark is slightly higher than the

  1. The marine ecosystems at Forsmark and Laxemar-Simpevarp. SR-Site Biosphere

    Aquilonius, Karin [ed.; Studsvik Nuclear AB (Sweden)

    2010-12-15

    The overall objective of this report is to provide a thorough description of the marine ecosystems at the sites Forsmark and Laxemar-Simpevarp, to identify processes in these ecosystems of importance to transfer and accumulation of radionuclides and, finally based on this knowledge, develop parameters to be used for the marine ecosystem in the safety analysis SR-Site. The report includes a thorough description of the major components in the marine ecosystems in Forsmark and Laxemar-Simpevarp, and covers the following areas: chemical and physical characteristics, climate and meteorology, morphology and regolith, biota in the marine ecosystem, human impact, water exchange and historical evolution at the sites. The site specific characteristics are compared with marine data from the Baltic region. Marine ecosystem modeling and mass balances calculations for carbon and a number of other elements were carried out to further improve the understanding of the marine ecosystems. Important processes for the safety assessment are identified, described and evaluated according to a systematic method. The derivation of marine ecosystem parameters and the resulting parameters is presented. The last chapter of the report aims at summarizing the knowledge of the marine ecosystems at the two areas. In comparison with the Gulf of Bothnia and the Baltic Proper, salinity is somewhat lower in Forsmark and Laxemar-Simpevarp respectively. The nitrogen and phosphorus levels at the two sites are low to moderately high compared with environmental monitoring data for corresponding areas in the Baltic Sea. In Forsmark, nitrogen seems to be the limiting nutrient during the summer months. In Laxemar-Simpevarp, nitrogen seems to be the limiting nutrient in the outer areas and phosphorus in the inner bays. This coincides with the general conditions in the Bothnian Sea (Forsmark) and the Baltic Proper (Laxemar-Simpevarp). The annual mean water temperature in Forsmark is slightly higher than the

  2. Hydrochemistry in surface water and shallow groundwater. Site descriptive modelling SDM-Site Forsmark

    Troejbom, Mats (Mopelikan, Norrtaelje (SE)); Soederbaeck, Bjoern (Swedish Nuclear Fuel and Waste Management Co., Stockholm (SE)); Johansson, Per-Olof (Artesia Grundvattenkonsult AB, Taeby (SE))

    2007-10-15

    With a mathematical/statistical approach, a large number of visualisations and models reflect the hydrochemistry in the Forsmark area, with the intention to give an understanding of important processes and factors that affect the hydrochemistry in the surface systems. In order to widen the perspective, all data from the Forsmark 2.2 stage including observations from different levels of the bedrock, as well as hydrological measurements and characterisations of the Quaternary deposits, have been included in the analyses. The purpose of this report is to give a general understanding of the site and to explain observed overall patterns as well as anomalies, and, ultimately, to present a conceptual model that explains the present hydrochemistry in the surface system in the light of the past. The report may also function as a basis for further evaluation and testing of scenarios, and may be regarded as an intermediate step between raw data compilations from the vast SICADA database and specialised expert models. The flat topography and the recent withdrawal of the Baltic Sea due to the isostatic land-uplift are two important factors determining the hydrochemistry in the Forsmark area. Marine remnants in the Quaternary deposits, as well as modern sea water intrusions, are therefore strongly influencing the hydrochemistry, especially in areas at low altitude close to the coast. Large-scale marine gradients in the surface system are consistent with the conceptual model that describes the hydrochemical evolution in a paleo-hydrologic perspective. The Forsmark area is covered by glacial remnants, mostly in the form of a till layer, which was deposited during the Weichselian glaciation and deglaciation. When the ice cover retreated about 11,000 years ago, these deposits were exposed on the sea floor. This till layer is characterized by a rich content of calcite, originating from the sedimentary bedrock of Gaevlebukten about 100 km north of Forsmark. The dissolution of this

  3. Hydrochemistry in surface water and shallow groundwater. Site descriptive modelling SDM-Site Forsmark

    Troejbom, Mats; Soederbaeck, Bjoern; Johansson, Per-Olof

    2007-10-01

    With a mathematical/statistical approach, a large number of visualisations and models reflect the hydrochemistry in the Forsmark area, with the intention to give an understanding of important processes and factors that affect the hydrochemistry in the surface systems. In order to widen the perspective, all data from the Forsmark 2.2 stage including observations from different levels of the bedrock, as well as hydrological measurements and characterisations of the Quaternary deposits, have been included in the analyses. The purpose of this report is to give a general understanding of the site and to explain observed overall patterns as well as anomalies, and, ultimately, to present a conceptual model that explains the present hydrochemistry in the surface system in the light of the past. The report may also function as a basis for further evaluation and testing of scenarios, and may be regarded as an intermediate step between raw data compilations from the vast SICADA database and specialised expert models. The flat topography and the recent withdrawal of the Baltic Sea due to the isostatic land-uplift are two important factors determining the hydrochemistry in the Forsmark area. Marine remnants in the Quaternary deposits, as well as modern sea water intrusions, are therefore strongly influencing the hydrochemistry, especially in areas at low altitude close to the coast. Large-scale marine gradients in the surface system are consistent with the conceptual model that describes the hydrochemical evolution in a paleo-hydrologic perspective. The Forsmark area is covered by glacial remnants, mostly in the form of a till layer, which was deposited during the Weichselian glaciation and deglaciation. When the ice cover retreated about 11,000 years ago, these deposits were exposed on the sea floor. This till layer is characterized by a rich content of calcite, originating from the sedimentary bedrock of Gaevlebukten about 100 km north of Forsmark. The dissolution of this

  4. Summary of discrete fracture network modelling as applied to hydrogeology of the Forsmark and Laxemar sites

    Hartley, Lee; Roberts, David

    2013-04-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is responsible for the development of a deep geological repository for spent nuclear fuel. The permitting of such a repository is informed by assessment studies to estimate the risks of the disposal method. One of the potential risks involves the transport of radionuclides in groundwater from defective canisters in the repository to the accessible environment. The Swedish programme for geological disposal of spent nuclear fuel has involved undertaking detailed surface-based site characterisation studies at two different sites, Forsmark and Laxemar-Simpevarp. A key component of the hydrogeological modelling of these two sites has been the development of Discrete Fracture Network (DFN) concepts of groundwater flow through the fractures in the crystalline rocks present. A discrete fracture network model represents some of the characteristics of fractures explicitly, such as their, orientation, intensity, size, spatial distribution, shape and transmissivity. This report summarises how the discrete fracture network methodology has been applied to model groundwater flow and transport at Forsmark and Laxemar. The account has involved summarising reports previously published by SKB between 2001 and 2011. The report describes the conceptual framework and assumptions used in interpreting site data, and in particular how data has been used to calibrate the various parameters that define the discrete fracture network representation of bedrock hydrogeology against borehole geologic and hydraulic data. Steps taken to confirm whether the developed discrete fracture network models provide a description of regional-scale groundwater flow and solute transport consistent with wider hydraulic tests hydrochemical data from Forsmark and Laxemar are discussed. It illustrates the use of derived hydrogeological DFN models in the simulations of the temperate period hydrogeology that provided input to radionuclide transport

  5. Summary of discrete fracture network modelling as applied to hydrogeology of the Forsmark and Laxemar sites

    Hartley, Lee; Roberts, David

    2013-04-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is responsible for the development of a deep geological repository for spent nuclear fuel. The permitting of such a repository is informed by assessment studies to estimate the risks of the disposal method. One of the potential risks involves the transport of radionuclides in groundwater from defective canisters in the repository to the accessible environment. The Swedish programme for geological disposal of spent nuclear fuel has involved undertaking detailed surface-based site characterisation studies at two different sites, Forsmark and Laxemar-Simpevarp. A key component of the hydrogeological modelling of these two sites has been the development of Discrete Fracture Network (DFN) concepts of groundwater flow through the fractures in the crystalline rocks present. A discrete fracture network model represents some of the characteristics of fractures explicitly, such as their, orientation, intensity, size, spatial distribution, shape and transmissivity. This report summarises how the discrete fracture network methodology has been applied to model groundwater flow and transport at Forsmark and Laxemar. The account has involved summarising reports previously published by SKB between 2001 and 2011. The report describes the conceptual framework and assumptions used in interpreting site data, and in particular how data has been used to calibrate the various parameters that define the discrete fracture network representation of bedrock hydrogeology against borehole geologic and hydraulic data. Steps taken to confirm whether the developed discrete fracture network models provide a description of regional-scale groundwater flow and solute transport consistent with wider hydraulic tests hydrochemical data from Forsmark and Laxemar are discussed. It illustrates the use of derived hydrogeological DFN models in the simulations of the temperate period hydrogeology that provided input to radionuclide transport

  6. Forsmark site investigation. Detailed ground magnetic survey and lineament interpretation in the Forsmark area, 2006-2007

    Isaksson, Hans; Thunehed, Hans; Pitkaenen, Timo; Keisu, Mikael

    2007-12-01

    The report presents detailed ground magnetic measurements carried out on an 11.1 km 2 area in the Forsmark site investigation area. The main objective of this activity is to determine a detailed ground magnetic representation of the bedrock. The results from previous surveys were encouraging and have led to a broad geophysical programme for investigation of lineaments at Forsmark. This report comprises the results from the second and final phase of the extended survey programme and a compilation and summary of all phases in the programme. On ground and on lake ice, a grid with parallel lines was staked. Measurements of the magnetic total field were carried out along profiles, perpendicular to the staked lines, with a profile spacing of 10 m and a station spacing of 5 m. Measurements on the ice-covered sea bays were carried out by a two man crew. One crew member walked along the survey lines, carrying a RTK-GPS guiding the other crew member who measured the magnetic total field. No seaborne survey was carried out in the final phase. Previously, using a high accuracy RTK-GPS unit for boat navigation gave a seaborne survey grid of on average 10 m line spacing and 2-3 m station spacing. In total 427,238 magnetic survey stations have been measured and an area of 4.7 km 2 has been surveyed from boat. The magnetic pattern in the survey area can be divided into six main areas with different magnetic character. Along the southwest margin of the survey area the magnetic pattern is intensely banded with rapidly changing low and highly magnetic bands striking southeast-northwest, which to the northeast changes to a gentler, banded pattern of low to moderate magnetic intensity. To the northeast, at the SFR office and along the coastline to the southeast, the pattern is again intensely banded with, southeast-northwest trending, rapidly changing low and highly magnetic bands. These two banded structures probably forms fold limbs of a common fold with a northwest oriented fold

  7. Forsmark site investigation. Detailed ground magnetic survey and lineament interpretation in the Forsmark area, 2006-2007

    Isaksson, Hans; Thunehed, Hans; Pitkaenen, Timo; Keisu, Mikael (GeoVista AB, Luleaa (SE))

    2007-12-15

    The report presents detailed ground magnetic measurements carried out on an 11.1 km2 area in the Forsmark site investigation area. The main objective of this activity is to determine a detailed ground magnetic representation of the bedrock. The results from previous surveys were encouraging and have led to a broad geophysical programme for investigation of lineaments at Forsmark. This report comprises the results from the second and final phase of the extended survey programme and a compilation and summary of all phases in the programme. On ground and on lake ice, a grid with parallel lines was staked. Measurements of the magnetic total field were carried out along profiles, perpendicular to the staked lines, with a profile spacing of 10 m and a station spacing of 5 m. Measurements on the ice-covered sea bays were carried out by a two man crew. One crew member walked along the survey lines, carrying a RTK-GPS guiding the other crew member who measured the magnetic total field. No seaborne survey was carried out in the final phase. Previously, using a high accuracy RTK-GPS unit for boat navigation gave a seaborne survey grid of on average 10 m line spacing and 2-3 m station spacing. In total 427,238 magnetic survey stations have been measured and an area of 4.7 km2 has been surveyed from boat. The magnetic pattern in the survey area can be divided into six main areas with different magnetic character. Along the southwest margin of the survey area the magnetic pattern is intensely banded with rapidly changing low and highly magnetic bands striking southeast-northwest, which to the northeast changes to a gentler, banded pattern of low to moderate magnetic intensity. To the northeast, at the SFR office and along the coastline to the southeast, the pattern is again intensely banded with, southeast-northwest trending, rapidly changing low and highly magnetic bands. These two banded structures probably forms fold limbs of a common fold with a northwest oriented fold axis

  8. Displacement along extensive deformation zones at the two SKB sites: Forsmark and Laxemar

    Beckholmen, Monica; Tiren, Sven A.

    2010-12-01

    The Fennoscandian shield, a part of the East European Craton, is distinguished by the exposed bedrock which is mainly composed of Precambrian metamorphic and igneous rocks. Large parts of the ground surface closely coincides with a late Precambrian denudation surface; the sub-Cambrian peneplain. Palaeozoic and younger sediments were deposited on the peneplain but these sediments have been removed from most areas that now form the mainland of Sweden and Finland and there are just a few remnants left. In the Baltic Sea, located in large-scale depressions on the boundary of in the Fennoscandian Shield/ in the East European Craton/, the Precambrian bedrock is still in large parts covered by Palaeozoic sediments. The Palaeozoic sedimentary rocks, as they are well bedded, may form a memory of the late Palaeozoic and younger tectonic events in the underlying basement rocks. Such data are used here to complement the structural observations made at sites located on the mainland, giving information on displacement along faults. Significant for the Baltic Sea are faults oriented in N-S that appear as segments, displaced relative to each other. Other structures are oriented in E-W, NE-SW and NW-SE. The SKB Forsmark site is located in a relatively flat coastal area within the sub-Cambrian peneplain. The sea area at the Forsmark site has a more accentuated relief than what is found on the mainland, for example, a furrow along the western side of the N-S oriented island Graesoe northeast of Forsmark (below 30m b.s.l. and locally more than 50m lower than Graesoe) and the deep between Aaland and Sweden (301m b.s.l.) about 100km east-southeast of Forsmark. In the Forsmark-site area two sets of structures interfere: a WNWESE trending set with relatively straight faults along the north coast of Uppland and a NNW-SSE to N-S trending set, slightly curved, along the (north)east coast of Uppland. The Forsmark site is located in an elevated WNW trending lath-shaped rock block outlined by

  9. Displacement along extensive deformation zones at the two SKB sites: Forsmark and Laxemar

    Beckholmen, Monica; Tiren, Sven A. (GEOSIGMA AB (Sweden))

    2010-12-15

    The Fennoscandian shield, a part of the East European Craton, is distinguished by the exposed bedrock which is mainly composed of Precambrian metamorphic and igneous rocks. Large parts of the ground surface closely coincides with a late Precambrian denudation surface; the sub-Cambrian peneplain. Palaeozoic and younger sediments were deposited on the peneplain but these sediments have been removed from most areas that now form the mainland of Sweden and Finland and there are just a few remnants left. In the Baltic Sea, located in large-scale depressions on the boundary of in the Fennoscandian Shield/ in the East European Craton/, the Precambrian bedrock is still in large parts covered by Palaeozoic sediments. The Palaeozoic sedimentary rocks, as they are well bedded, may form a memory of the late Palaeozoic and younger tectonic events in the underlying basement rocks. Such data are used here to complement the structural observations made at sites located on the mainland, giving information on displacement along faults. Significant for the Baltic Sea are faults oriented in N-S that appear as segments, displaced relative to each other. Other structures are oriented in E-W, NE-SW and NW-SE. The SKB Forsmark site is located in a relatively flat coastal area within the sub-Cambrian peneplain. The sea area at the Forsmark site has a more accentuated relief than what is found on the mainland, for example, a furrow along the western side of the N-S oriented island Graesoe northeast of Forsmark (below 30m b.s.l. and locally more than 50m lower than Graesoe) and the deep between Aaland and Sweden (301m b.s.l.) about 100km east-southeast of Forsmark. In the Forsmark-site area two sets of structures interfere: a WNWESE trending set with relatively straight faults along the north coast of Uppland and a NNW-SSE to N-S trending set, slightly curved, along the (north)east coast of Uppland. The Forsmark site is located in an elevated WNW trending lath-shaped rock block outlined by

  10. The terrestrial ecosystems at Forsmark and Laxemar-Simpevarp. SR-Site Biosphere

    Loefgren, Anders [ed.; EcoAnalytica, Haegersten (Sweden)

    2010-12-15

    The ecosystem is in most cases the link between radionuclides released from a repository and the exposure of humans and other biota to them. This report describes the terrestrial ecosystems in the Forsmark and Laxemar-Simpevarp areas by summarizing and performing cross-disciplinary analyses of data from a large number of reports produced during the site investigations, Figure 1-2. The report describes the terrestrial landscape, divided here into the three main categories: forests, wetlands and agriculture land, by identifying properties that are important for element accumulation and transport

  11. The terrestrial ecosystems at Forsmark and Laxemar-Simpevarp. SR-Site Biosphere

    Loefgren, Anders

    2010-12-01

    The ecosystem is in most cases the link between radionuclides released from a repository and the exposure of humans and other biota to them. This report describes the terrestrial ecosystems in the Forsmark and Laxemar-Simpevarp areas by summarizing and performing cross-disciplinary analyses of data from a large number of reports produced during the site investigations, Figure 1-2. The report describes the terrestrial landscape, divided here into the three main categories: forests, wetlands and agriculture land, by identifying properties that are important for element accumulation and transport

  12. Modelling of present and future hydrology and solute transport at Forsmark. SR-Site Biosphere

    Bosson, Emma; Sassner, Mona; Sabel, Ulrika; Gustafsson, Lars-Goeran

    2010-10-01

    Radioactive waste from nuclear power plants in Sweden is managed by the Swedish Nuclear Fuel and Waste Management Co, SKB. SKB has performed site investigations at two different locations in Sweden, referred to as the Forsmark and Laxemar-Simpevarp areas, with the objective of siting a final repository for high-level radioactive waste. In 2009 a decision was made to focus on the Forsmark site. This decision was based on a large amount of empirical evidence suggesting Forsmark to be more suitable for a geological repository /SKB 2010b/. This report presents model results of numerical flow and transport modelling of surface water and near-surface groundwater at the Forsmark site for present and future conditions. Both temperate and periglacial climates have been simulated. Also different locations of the shoreline have been applied to the model, as well as different models of vegetation and Quaternary deposits. The modelling was performed using the modelling tool MIKE SHE and was based on the SDM-Site Forsmark MIKE SHE model (presented by Bosson et al. in SKB report R-08-09). The present work is a part of the biosphere modelling performed for the SR-Site safety assessment. The Forsmark area has a flat, small-scale topography. The study area is almost entirely below 20 m.a.s.l. (metres above sea level). There is a strong correlation between the topography of the ground surface and the ground water level in the Quaternary deposits (QD); thus, the surface water divides and the groundwater divides for the QD can be assumed to coincide. No major water courses flow through the catchment. Small brooks, which often dry out in the summer, connect the different sub-catchments with each other. The main lakes in the area, Lake Bolundsfjaerden, Lake Fiskarfjaerden, Lake Gaellsbotraesket and Lake Eckarfjaerden, all have sizes of less than one km2. The lakes are in general shallow. Approximately 70% of the catchment areas are covered by forest. Agricultural land is only present in

  13. Modelling of present and future hydrology and solute transport at Forsmark. SR-Site Biosphere

    Bosson, Emma (Swedish Nuclear Fuel and Waste Management Co., Stocholm (Sweden)); Sassner, Mona; Sabel, Ulrika; Gustafsson, Lars-Goeran (DHI Sverige AB (Sweden))

    2010-10-15

    Radioactive waste from nuclear power plants in Sweden is managed by the Swedish Nuclear Fuel and Waste Management Co, SKB. SKB has performed site investigations at two different locations in Sweden, referred to as the Forsmark and Laxemar-Simpevarp areas, with the objective of siting a final repository for high-level radioactive waste. In 2009 a decision was made to focus on the Forsmark site. This decision was based on a large amount of empirical evidence suggesting Forsmark to be more suitable for a geological repository /SKB 2010b/. This report presents model results of numerical flow and transport modelling of surface water and near-surface groundwater at the Forsmark site for present and future conditions. Both temperate and periglacial climates have been simulated. Also different locations of the shoreline have been applied to the model, as well as different models of vegetation and Quaternary deposits. The modelling was performed using the modelling tool MIKE SHE and was based on the SDM-Site Forsmark MIKE SHE model (presented by Bosson et al. in SKB report R-08-09). The present work is a part of the biosphere modelling performed for the SR-Site safety assessment. The Forsmark area has a flat, small-scale topography. The study area is almost entirely below 20 m.a.s.l. (metres above sea level). There is a strong correlation between the topography of the ground surface and the ground water level in the Quaternary deposits (QD); thus, the surface water divides and the groundwater divides for the QD can be assumed to coincide. No major water courses flow through the catchment. Small brooks, which often dry out in the summer, connect the different sub-catchments with each other. The main lakes in the area, Lake Bolundsfjaerden, Lake Fiskarfjaerden, Lake Gaellsbotraesket and Lake Eckarfjaerden, all have sizes of less than one km2. The lakes are in general shallow. Approximately 70% of the catchment areas are covered by forest. Agricultural land is only present in

  14. Forsmark site investigation. Searching for evidence of late- or postglacial faulting in the Forsmark region. Results from 2002-2004

    Lagerbaeck, Robert; Sundh, Martin; Svedlund, Jan-Olov; Johansson, Helena [Geological Survey of Sweden, Uppsala (Sweden)

    2005-10-15

    The study was designed to determine whether any major late- or postglacial faulting occurred in the proposed repository area at Forsmark or in its vicinity. 'Major faulting' in this context is defined as dislocations in the order of several metres along faults several kilometres long. Faults of such dimensions may, if conditions are favourable, be detected by means of interpreting aerial photographs. Furthermore, they would have generated high magnitude earthquakes that could produce characteristic distortions in waterlogged sandy or silty sediments. Interpretation of aerial photographs was carried out in a relatively large area in northeast Uppland, with the purpose of looking for morphologically conspicuous lineaments, i.e. late- or postglacial fault candidates. A number of fairly prominent but short escarpments and crevasses were noted, but when later field-checked these candidates for young fault movement proved to be more or less strongly glacially eroded, i.e. formed prior to the last deglaciation. In order to search for seismically induced distortions, all gravel and sand pits being worked in the investigation area were visited and some fifty machine-dug trenches were excavated, mainly in sandy-silty glaciofluvial deposits along eskers. Contorted and folded sequences of glacial clay were encountered at many of the localities, but the disturbances were generally interpreted as caused by sliding. A seismic origin for the sliding cannot be excluded, but no conclusive evidence of this was found. As no distortions attributable to seismically induced liquefaction were noted in any of the trenches excavated along the Boerstil esker, to the southeast of Forsmark, it is concluded that no major (>M7) earthquakes occurred in the Forsmark area after the disappearance of the last inland ice sheet. An erosional unconformity accompanied by a laterally persistent layer of coarse-grained sediments was found in most of the investigated trenches and it is concluded

  15. Forsmark site investigation. Searching for evidence of late- or postglacial faulting in the Forsmark region. Results from 2002-2004

    Lagerbaeck, Robert; Sundh, Martin; Svedlund, Jan-Olov; Johansson, Helena

    2005-10-01

    The study was designed to determine whether any major late- or postglacial faulting occurred in the proposed repository area at Forsmark or in its vicinity. 'Major faulting' in this context is defined as dislocations in the order of several metres along faults several kilometres long. Faults of such dimensions may, if conditions are favourable, be detected by means of interpreting aerial photographs. Furthermore, they would have generated high magnitude earthquakes that could produce characteristic distortions in waterlogged sandy or silty sediments. Interpretation of aerial photographs was carried out in a relatively large area in northeast Uppland, with the purpose of looking for morphologically conspicuous lineaments, i.e. late- or postglacial fault candidates. A number of fairly prominent but short escarpments and crevasses were noted, but when later field-checked these candidates for young fault movement proved to be more or less strongly glacially eroded, i.e. formed prior to the last deglaciation. In order to search for seismically induced distortions, all gravel and sand pits being worked in the investigation area were visited and some fifty machine-dug trenches were excavated, mainly in sandy-silty glaciofluvial deposits along eskers. Contorted and folded sequences of glacial clay were encountered at many of the localities, but the disturbances were generally interpreted as caused by sliding. A seismic origin for the sliding cannot be excluded, but no conclusive evidence of this was found. As no distortions attributable to seismically induced liquefaction were noted in any of the trenches excavated along the Boerstil esker, to the southeast of Forsmark, it is concluded that no major (>M7) earthquakes occurred in the Forsmark area after the disappearance of the last inland ice sheet. An erosional unconformity accompanied by a laterally persistent layer of coarse-grained sediments was found in most of the investigated trenches and it is concluded that strong

  16. Hydraulic effects of unsealed boreholes. Numerical groundwater flow modelling of the Forsmark and Laxemar sites

    Bockgaard, Niclas

    2011-06-01

    The objective of the work was to investigate hydraulic effects of open and poorly sealed boreholes on groundwater flow conditions through simulations using a numerical groundwater model. Specifically, the boreholes KFM07A, KFM09A, and KFM09B in Forsmark and the boreholes KLX04, KLX06, and KLX10 in Laxemar were studied. The criteria for the selection of these boreholes were that the boreholes should represent typical conditions of the site, the borehole length should exceed 500 m, and that several major fractured zones should be intersected. The boreholes KFM07A and KLX06, respectively, were selected as reference boreholes for more detailed studies of different sealing schemes. The model setup of the Forsmark model followed the Forsmark 2.2 regional-scale conceptual hydrogeological model. The model domain was approximately 15 km (north-south) x 10 km (west- east) x 1.2 km (depth). The 131 deformation zones and three layers of superficial horizontal sheet joint were modelled deterministically. A stochastic discrete fracture network (DFN) representing fractures and minor deformation zones were also generated between the deterministic deformation zones inside central model volume. The side lengths of the square fractures were from 1,000 m down to 10 m. In order to resolve the details of flow in to and out from the borehole, a more detailed DFN was generated in a zone around the borehole KFM07A, where fractures down to a side length of 0.5 m were considered. The model setup of the Laxemar model followed the SDM-Site Laxemar (Laxemar 2.3) regional scale conceptual hydrogeological model. The model domain was approximately 12 km (north-south) x 20 km (west-east) x 2.1 km (depth). A number of 71 deformation zones were modelled deterministically, and one realization of a stochastic DFN, the so-called hydrogeological DFN model base case, was imported to the model. Similar to the Forsmark case, a more detailed DFN was also generated around the reference borehole KLX06. The

  17. Hydraulic effects of unsealed boreholes. Numerical groundwater flow modelling of the Forsmark and Laxemar sites

    Bockgaard, Niclas [Golder Associates AB, Stockholm (Sweden)

    2011-06-15

    The objective of the work was to investigate hydraulic effects of open and poorly sealed boreholes on groundwater flow conditions through simulations using a numerical groundwater model. Specifically, the boreholes KFM07A, KFM09A, and KFM09B in Forsmark and the boreholes KLX04, KLX06, and KLX10 in Laxemar were studied. The criteria for the selection of these boreholes were that the boreholes should represent typical conditions of the site, the borehole length should exceed 500 m, and that several major fractured zones should be intersected. The boreholes KFM07A and KLX06, respectively, were selected as reference boreholes for more detailed studies of different sealing schemes. The model setup of the Forsmark model followed the Forsmark 2.2 regional-scale conceptual hydrogeological model. The model domain was approximately 15 km (north-south) x 10 km (west- east) x 1.2 km (depth). The 131 deformation zones and three layers of superficial horizontal sheet joint were modelled deterministically. A stochastic discrete fracture network (DFN) representing fractures and minor deformation zones were also generated between the deterministic deformation zones inside central model volume. The side lengths of the square fractures were from 1,000 m down to 10 m. In order to resolve the details of flow in to and out from the borehole, a more detailed DFN was generated in a zone around the borehole KFM07A, where fractures down to a side length of 0.5 m were considered. The model setup of the Laxemar model followed the SDM-Site Laxemar (Laxemar 2.3) regional scale conceptual hydrogeological model. The model domain was approximately 12 km (north-south) x 20 km (west-east) x 2.1 km (depth). A number of 71 deformation zones were modelled deterministically, and one realization of a stochastic DFN, the so-called hydrogeological DFN model base case, was imported to the model. Similar to the Forsmark case, a more detailed DFN was also generated around the reference borehole KLX06. The

  18. Forsmark site investigation. Programme for long-term observations of geosphere and biosphere after completed site investigations

    NONE

    2007-06-15

    The site investigation at Forsmark was terminated the last of June, 2007. Hundreds of investigations have been conducted during a period of more than five years. Monitoring of a number of geoscientific parameters and biological objects has been one important part of the site investigation programme. Monitoring is defined as recurrent measurements of the same parameters/objects, so that time series are generated. Long-term monitoring of for example weather parameters, surface water discharge in brooks, and the groundwater head in a large number of boreholes has been conducted during the site investigations. Furthermore, repeated sampling of precipitation, surface water and groundwater in soil and rock for hydrochemical analyses has been carried out, and the groundwater flow in isolated borehole sections has been measured several times. Besides, some biological objects, for example rare bird species, have been invented each year of the site investigation. The measured parameters and the invented objects are characterized by a certain degree of time dependent variability, which is also site-specific. The aim of the monitoring is primarily to establish the 'undisturbed' conditions, the so called 'baseline'. If a deep repository is sited at Forsmark, many site-specific conditions will change, due to natural causes as well as to the construction works. Knowledge about the undisturbed conditions strengthens the ability to reveal and quantify such changes and to distinguish natural changes from those caused by the human activities. Another object of monitoring is to, by the study of the variability pattern of the monitored parameters, elevate the knowledge about the underlying, often complex causes governing the variations. In this way the description of site-specific conditions may be more precise and the prospects of modelling important processes are improved. After completion of the site investigations, a period of about two years will follow, when

  19. Forsmark site investigation. Programme for long-term observations of geosphere and biosphere after completed site investigations

    2007-06-01

    The site investigation at Forsmark was terminated the last of June, 2007. Hundreds of investigations have been conducted during a period of more than five years. Monitoring of a number of geoscientific parameters and biological objects has been one important part of the site investigation programme. Monitoring is defined as recurrent measurements of the same parameters/objects, so that time series are generated. Long-term monitoring of for example weather parameters, surface water discharge in brooks, and the groundwater head in a large number of boreholes has been conducted during the site investigations. Furthermore, repeated sampling of precipitation, surface water and groundwater in soil and rock for hydrochemical analyses has been carried out, and the groundwater flow in isolated borehole sections has been measured several times. Besides, some biological objects, for example rare bird species, have been invented each year of the site investigation. The measured parameters and the invented objects are characterized by a certain degree of time dependent variability, which is also site-specific. The aim of the monitoring is primarily to establish the 'undisturbed' conditions, the so called 'baseline'. If a deep repository is sited at Forsmark, many site-specific conditions will change, due to natural causes as well as to the construction works. Knowledge about the undisturbed conditions strengthens the ability to reveal and quantify such changes and to distinguish natural changes from those caused by the human activities. Another object of monitoring is to, by the study of the variability pattern of the monitored parameters, elevate the knowledge about the underlying, often complex causes governing the variations. In this way the description of site-specific conditions may be more precise and the prospects of modelling important processes are improved. After completion of the site investigations, a period of about two years will follow, when the investigation

  20. Water-rock interaction modelling and uncertainties of mixing modelling. SDM-Site Forsmark

    Gimeno, Maria J.; Auque, Luis F.; Gomez, Javier B.; Acero, Patricia (Univ. of Zaragoza, Zaragoza (Spain))

    2008-08-15

    The overall objectives of the hydrogeochemical description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site and to develop models that fulfil the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and pore water and their evolution with time. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. Past climate changes are one of the major driving forces for hydrogeochemical changes and therefore of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the crystalline bedrock of the Fennoscandian Shield. Understanding current undisturbed hydrochemical conditions at the proposed repository site is important when predicting future changes in groundwater chemistry. The causes behind of copper corrosion and/or bentonite degradation are of particular interest as they may jeopardise the long-term integrity of the planned SKB repository system. Thus, the following variables are considered for the hydrogeochemical site descriptive modelling: pH, Eh, sulphur species, iron, manganese, carbonate, phosphate, nitrogen species, total dissolved solids (TDS), isotopes, colloids, fulvic and humic acids and microorganisms. In addition, dissolved gases (e.g. carbon dioxide, methane and hydrogen) are of interest because of their likely participation in microbial reactions. In this series of reports, the final hydrogeochemical evaluation work of the site investigation at the Forsmark site, is presented. The work was conducted by SKB's hydrogeochemical project group, ChemNet, which consists of independent consultants and university researchers with expertise

  1. Water-rock interaction modelling and uncertainties of mixing modelling. SDM-Site Forsmark

    Gimeno, Maria J.; Auque, Luis F.; Gomez, Javier B.; Acero, Patricia

    2008-08-01

    The overall objectives of the hydrogeochemical description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site and to develop models that fulfil the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and pore water and their evolution with time. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. Past climate changes are one of the major driving forces for hydrogeochemical changes and therefore of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the crystalline bedrock of the Fennoscandian Shield. Understanding current undisturbed hydrochemical conditions at the proposed repository site is important when predicting future changes in groundwater chemistry. The causes behind of copper corrosion and/or bentonite degradation are of particular interest as they may jeopardise the long-term integrity of the planned SKB repository system. Thus, the following variables are considered for the hydrogeochemical site descriptive modelling: pH, Eh, sulphur species, iron, manganese, carbonate, phosphate, nitrogen species, total dissolved solids (TDS), isotopes, colloids, fulvic and humic acids and microorganisms. In addition, dissolved gases (e.g. carbon dioxide, methane and hydrogen) are of interest because of their likely participation in microbial reactions. In this series of reports, the final hydrogeochemical evaluation work of the site investigation at the Forsmark site, is presented. The work was conducted by SKB's hydrogeochemical project group, ChemNet, which consists of independent consultants and university researchers with expertise in

  2. Forsmark site investigation. Hydrochemical investigations in four calciferous lakes in the Forsmark area. Results from the second year of a complementary investigation in the Forsmark area

    Qvarfordt, Susanne; Borgiel, Micke; Berg, Cecilia

    2011-12-01

    The present report documents the results from the second year of hydrochemical investigations in four small, calciferous lakes in the Forsmark area in order to study the lake water compositions. The construction of a permanent storage facility for used nuclear fuel may result in a lowering of the ground water level and also lake surface water levels. Restoration of habitats by adding water may be an option to reduce possible negative consequences induced by a lower water level on biodiversity and valuable species. Thus, knowledge of the water composition is needed. This report presents the results from six sampling occasions during January to December 2010. The results from the sampling of the four lakes includes field measurements of redox potential (ORP), pH, dissolved oxygen, electrical conductivity, salinity, depth, atmospheric pressure, turbidity, chlorophyll and water temperature, as well as chemical analyses of major constituents and nutrient salts. The four investigated small lakes are well buffered with high alkalinity, high pH and high calcium concentrations. This is in accordance with results from the ongoing monitoring programme of lakes and streams in the area and with the results from the previous sampling period (2008-2009). The results show both seasonal and inter-annual variation in the analysed parameters. This can be explained by seasonal changes and annual differences in temperature, ice-cover, precipitation etc and lake specific parameters such as lake size and drainage area. The variation highlights the importance of both year round sampling and continued sampling for several years when discussing the water composition

  3. Forsmark site investigation. Hydrochemical investigations in four calciferous lakes in the Forsmark area. Results from the second year of a complementary investigation in the Forsmark area

    Qvarfordt, Susanne; Borgiel, Micke [Sveriges Vattenekologer AB, Vingaaker (Sweden); Berg, Cecilia [Geosigma AB, Uppsala (Sweden)

    2011-12-15

    The present report documents the results from the second year of hydrochemical investigations in four small, calciferous lakes in the Forsmark area in order to study the lake water compositions. The construction of a permanent storage facility for used nuclear fuel may result in a lowering of the ground water level and also lake surface water levels. Restoration of habitats by adding water may be an option to reduce possible negative consequences induced by a lower water level on biodiversity and valuable species. Thus, knowledge of the water composition is needed. This report presents the results from six sampling occasions during January to December 2010. The results from the sampling of the four lakes includes field measurements of redox potential (ORP), pH, dissolved oxygen, electrical conductivity, salinity, depth, atmospheric pressure, turbidity, chlorophyll and water temperature, as well as chemical analyses of major constituents and nutrient salts. The four investigated small lakes are well buffered with high alkalinity, high pH and high calcium concentrations. This is in accordance with results from the ongoing monitoring programme of lakes and streams in the area and with the results from the previous sampling period (2008-2009). The results show both seasonal and inter-annual variation in the analysed parameters. This can be explained by seasonal changes and annual differences in temperature, ice-cover, precipitation etc and lake specific parameters such as lake size and drainage area. The variation highlights the importance of both year round sampling and continued sampling for several years when discussing the water composition.

  4. Statistics of modelled conductive fractures based on Laxemar and Forsmark. Site descriptive model data

    Stigsson, Martin

    2009-12-15

    The objectives of this report is to investigate the frequency of fractures assumed to be water conductive, i.e. open or partly open and directly or indirectly connected to a source. Also the distribution of total transmissivity in 100 m and 20 m horizontal sections and 8 m vertical sections is calculated. The report is only intended to serve as input to the SER, Site Engineering Report, at Laxemar and Forsmark. The input data for the analyses is taken, as is, from the Discrete Fracture Network sections in published reports. No evaluation that the model parameters are appropriate for the task or sensitivity analysis is performed. The tunnels and deposition holes are modelled as scanlines which is a very coarse approximation, but it may give some rough estimation of the frequency of the water bearing features, especially for the larger ones, and the total transmissivity in a section

  5. Statistics of modelled conductive fractures based on Laxemar and Forsmark. Site descriptive model data

    Stigsson, Martin

    2009-12-01

    The objectives of this report is to investigate the frequency of fractures assumed to be water conductive, i.e. open or partly open and directly or indirectly connected to a source. Also the distribution of total transmissivity in 100 m and 20 m horizontal sections and 8 m vertical sections is calculated. The report is only intended to serve as input to the SER, Site Engineering Report, at Laxemar and Forsmark. The input data for the analyses is taken, as is, from the Discrete Fracture Network sections in published reports. No evaluation that the model parameters are appropriate for the task or sensitivity analysis is performed. The tunnels and deposition holes are modelled as scanlines which is a very coarse approximation, but it may give some rough estimation of the frequency of the water bearing features, especially for the larger ones, and the total transmissivity in a section

  6. Hydrogeochemical evaluation of the Forsmark site, model version 1.1

    Laaksoharju, Marcus (ed.) [GeoPoint AB, Sollentuna (Sweden); Gimeno, Maria; Auque, Luis; Gomez, Javier [Univ. of Zaragoza (Spain). Dept. of Earth Sciences; Smellie, John [Conterra AB, Uppsala (Sweden); Tullborg, Eva-Lena [Terralogica AB, Graabo (Sweden); Gurban, Ioana [3D-Terra, Montreal (Canada)

    2004-01-01

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Forsmark and Simpevarp, on the eastern coast of Sweden to determine their geological, geochemical and hydrogeological characteristics. Present work completed has resulted in model version 1.1 which represents the first evaluation of the available Forsmark groundwater analytical data collected up to May 1, 2003 (i.e. the first 'data freeze'). The HAG group had access to a total of 456 water samples collected mostly from the surface and sub-surface environment (e.g. soil pipes in the overburden, streams and lakes); only a few samples were collected from drilled boreholes. The deepest samples reflected depths down to 200 m. Furthermore, most of the waters sampled (74%) lacked crucial analytical information that restricted the evaluation. Consequently, model version 1.1 focussed on the processes taking place in the uppermost part of the bedrock rather than at repository levels. The complex groundwater evolution and patterns at Forsmark are a result of many factors such as: a) the flat topography and closeness to the Baltic Sea resulting in relative small hydrogeological driving forces which can preserve old water types from being flushed out, b) the changes in hydrogeology related to glaciation/deglaciation and land uplift, c) repeated marine/lake water regressions/transgressions, and d) organic or inorganic alteration of the groundwater caused by microbial processes or water/rock interactions. The sampled groundwaters reflect to various degrees modern or ancient water/rock interactions and mixing processes. Based on the general geochemical character and the apparent age two major water types occur in Forsmark: fresh-meteoric waters with a bicarbonate imprint and low residence times (tritium values above detection limit), and brackish-marine waters with Cl contents up to 6,000 mg/L and longer residence times (tritium

  7. Forsmark site characterisation - Borehole KFM22 and KFM23: Derivation of porewater data by diffusion experiments

    Waber, H. N. [Rock Water Interaction, University of Bern, Bern (Switzerland); Smellie, J. A. T. [Conterra AB, Partille (Sweden)

    2012-04-15

    Within the Detum Project (Detailed Investigations in Forsmark) a 'Methodology comparison for porewater extraction and characterisation techniques' was initiated. This has centred on two shallow boreholes drilled at Soederviken within the northern part of the Forsmark characterisation site. The comparison includes different methodologies to characterise the chemical and isotopic composition of porewater residing in the connected pore space of the rock matrix. The present report describes the chemical and isotopic information of the porewater obtained by out-diffusion experiments and the diffusive isotope equilibration technique applied to originally water saturated drillcore samples. In addition, petrophysical data and solute transport properties of the rock matrix, all necessary for porewater characterisation, have also been elaborated. Specially conditioned drillcore samples were obtained from depths of less than 100 m from boreholes KFM22 and KFM23. Porewater has been extracted successfully from seven samples by laboratory out-diffusion and diffusive isotope exchange methods. The methodology to extract and analyse the porewater is outlined and the analytical data are tabulated. The data are critically reviewed for potential experimental artefacts and their significance with respect to in situ conditions. The connected pore space in the core material representing borehole KFM22 and KFM23 was measured on different types of originally saturated drillcore samples using gravimetric and isotope mass balance methods. Out-diffusion experiments were performed on kg-sized drillcore samples to derive the in situ concentration of the chemically conservative compounds chloride and bromide. The attainment of equilibrium conditions in the out-diffusion experiments was monitored by the concentration change of chloride and bromide as a function of time. The water isotope composition of porewater was determined by the diffusive isotope equilibration technique and by

  8. Explorative analysis of major components and isotopes. SDM-Site Forsmark

    Smellie, John (Conterra AB (Sweden)); Tullborg, Eva-Lena (Terralogica AB (Sweden)); Nilsson, Ann-Chatrin (Geosigma AB (Sweden)); Sandstroem, Bjoern (Goeteborg Univ. (Sweden)); Waber, Niklaus (Univ. of Bern (Switzerland)); Gimeno, Maria (Univ. of Zaragoza (Spain)); Gascoyne, Mel (GGP Inc. (United Kingdom))

    2008-09-15

    The overall objectives of the hydrogeochemical description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site and to develop models that fulfil the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and pore water and their evolution with time. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. Past climate events are the major driving force for hydrogeochemical changes and therefore are of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the crystalline bedrock of the Fennoscandian Shield. Understanding current undisturbed hydrochemical conditions at the proposed repository site is important when predicting future changes in groundwater chemistry. The causes behind copper corrosion and/or bentonite degradation are of particular interest as they may jeopardise the long-term integrity of the planned SKB repository system. Thus, the following variables are considered for the hydrogeochemical site descriptive modelling: pH, Eh, sulphur species, iron, manganese, carbonate, phosphate, nitrogen species, total dissolved solids (TDS), isotopes, colloids, fulvic and humic acids and microorganisms. In addition, dissolved gases (e.g. carbon dioxide, methane and hydrogen) are of interest because of their likely participation in microbial reactions. In this series of reports, the final hydrogeochemical evaluation work of the site investigation at the Forsmark site, is presented. The work was conducted by SKB's hydrogeochemical project group, ChemNet, which consists of independent consultants and university researchers with expertise in

  9. Comparison of site descriptive models for Olkiluoto, Finland and Forsmark, Sweden

    Geier, J.; Bath, A.; Stephansson, O.; Luukkonen, A.

    2012-08-15

    The proposed high-level radioactive waste repository sites at Olkiluoto and Forsmark share broadly similar geologic histories and regional settings. Despite differences in lithology, rock strength and patterns of brittle deformation, the sites show similarities in terms of hydrogeochemistry and hydrogeology. These similarities reflect a dominating influence of saline and brackish water intrusion during inundation by the postglacial Littorina Sea and Baltic Sea, followed by exposure to meteoric waters following postglacial uplift and transition to a Baltic coastal setting. Both sites also contain deep bedrock saline groundwater, though this is more evident at Olkiluoto than at Forsmark. A comparative study of site descriptive models for the two sites identifies the following key differences that could potentially impact safety of a repository: (1) Redox controls, buffering and biogeochemistry at proposed repository depths; (2) Salinity gradients at and below proposed repository depths; (3) Methane concentrations at and below proposed repository depths; (4) Depths to which glacial water and Littorina water penetrated; (5) Cation hydrogeochemistry and water-rock reaction; (6) Pore water compositions in rock matrix; (7) Rock fabric, secondary minerals and alteration with respect to radionuclide retention; (8) Brittle deformation fabric differences on multiple scales that affect vertical hydraulic conductivity; (9) Differences in apparent frequency of encountering water-conducting networks at proposed repository depths; (10) Shallow bedrock hydraulic properties; (11) Unique intrusive or dissolution features; (12) Connectivity of site-scale models to regional-scale features; (13) Mesoproterozoic rocks in vicinity and possibilities for human-intrusion scenarios; (14) Rock stresses and bedrock strength and deformability at proposed repository depths; (15) Thermal anisotropy. These differences are all potentially significant to safety functions, but none are so severe that

  10. Explorative analysis of major components and isotopes. SDM-Site Forsmark

    Smellie, John; Tullborg, Eva-Lena; Nilsson, Ann-Chatrin; Sandstroem, Bjoern; Waber, Niklaus; Gimeno, Maria; Gascoyne, Mel

    2008-09-01

    The overall objectives of the hydrogeochemical description for Forsmark are to establish a detailed understanding of the hydrogeochemical conditions at the site and to develop models that fulfil the needs identified by the safety assessment groups during the site investigation phase. Issues of concern to safety assessment are radionuclide transport and technical barrier behaviour, both of which are dependent on the chemistry of groundwater and pore water and their evolution with time. The work has involved the development of descriptive and mathematical models for groundwaters in relation to rock domains, fracture domains and deformation zones. Past climate events are the major driving force for hydrogeochemical changes and therefore are of fundamental importance for understanding the palaeohydrogeological, palaeohydrogeochemical and present evolution of groundwater in the crystalline bedrock of the Fennoscandian Shield. Understanding current undisturbed hydrochemical conditions at the proposed repository site is important when predicting future changes in groundwater chemistry. The causes behind copper corrosion and/or bentonite degradation are of particular interest as they may jeopardise the long-term integrity of the planned SKB repository system. Thus, the following variables are considered for the hydrogeochemical site descriptive modelling: pH, Eh, sulphur species, iron, manganese, carbonate, phosphate, nitrogen species, total dissolved solids (TDS), isotopes, colloids, fulvic and humic acids and microorganisms. In addition, dissolved gases (e.g. carbon dioxide, methane and hydrogen) are of interest because of their likely participation in microbial reactions. In this series of reports, the final hydrogeochemical evaluation work of the site investigation at the Forsmark site, is presented. The work was conducted by SKB's hydrogeochemical project group, ChemNet, which consists of independent consultants and university researchers with expertise in

  11. The terrestrial ecosystems at Forsmark and Laxemar-Simpevarp. Site descriptive modelling SDM site

    Loefgren, Anders [EcoAnalytica, Haegersten (Sweden); ed.

    2008-12-15

    This report describes the terrestrial ecosystems in the Forsmark and Laxemar-Simpevarp areas by summarizing ecological data and data from disciplines such as hydrology, quaternary geology and chemistry. The description therefore includes a number of different processes that drive element fluxes in the ecosystems, such as net primary production, heterotrophic respiration, transpiration, and horizontal transport from land to streams and lakes. Moreover, the human appropriation of the landscape is described with regard to land use and potential and actual utilization of food resources both today and in a historical perspective

  12. The limnic ecosystems at Forsmark and Laxemar-Simpevarp. Site descriptive modelling SDM-Site

    Norden, Sara; Soederbaeck, Bjoern [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Andersson, Eva [SWECO, Stockholm (Sweden)

    2008-11-15

    The overall objective of this report is to provide a thorough description of the limnic ecosystems at both Forsmark and Laxemar-Simpevarp. This information may be used in the Safety Assessment and as a basis for the Environmental Impact Assessment. Three aims were set up for the report: 1) to characterize and describe the limnic ecosystems today and in the past in the Forsmark and Laxemar-Simpevarp areas and compare these ecosystems with limnic ecosystems in other areas; 2) to evaluate and visualize major pools, fluxes and sinks of elements within the limnic ecosystems; and finally 3) to describe human impact on the limnic ecosystems. The report includes a thorough description of the lakes and streams in Forsmark and Laxemar-Simpevarp and covers the following areas: catchment area characteristics, hydrology, climate, sediment characteristics, physical characteristics of streams, habitat distribution in lakes, biotic components, water chemistry, comparisons with other lakes and streams in the region, and a historical description. Ecosystem models for carbon and mass balances for a number of elements have been calculated to further improve the understanding of the lake ecosystems. Important processes for the safety assessment are described and evaluated in the report. The Forsmark regional model area contains more than 20 permanent lakes and pools. All lakes are small and shallow, and are characterized as oligotrophic hardwater lakes. Calcareous soils in the area give rise to high calcium concentrations in the surface water, which in turn leads to high pH and low nutrient concentrations in water as phosphorus often co-precipitates with calcium. The shallow depths and moderate water colour permit photosynthesis in the entire benthic habitat of the lakes, and the bottoms are covered by dense stands of the macroalgae Chara sp. Moreover, many of the lakes also have a thick microbial mat (>10 cm), consisting of cyanobacteria and diatoms, in the benthic habitat. Fish in

  13. The limnic ecosystems at Forsmark and Laxemar-Simpevarp. Site descriptive modelling SDM-Site

    Norden, Sara; Soederbaeck, Bjoern; Andersson, Eva

    2008-11-01

    The overall objective of this report is to provide a thorough description of the limnic ecosystems at both Forsmark and Laxemar-Simpevarp. This information may be used in the Safety Assessment and as a basis for the Environmental Impact Assessment. Three aims were set up for the report: 1) to characterize and describe the limnic ecosystems today and in the past in the Forsmark and Laxemar-Simpevarp areas and compare these ecosystems with limnic ecosystems in other areas; 2) to evaluate and visualize major pools, fluxes and sinks of elements within the limnic ecosystems; and finally 3) to describe human impact on the limnic ecosystems. The report includes a thorough description of the lakes and streams in Forsmark and Laxemar-Simpevarp and covers the following areas: catchment area characteristics, hydrology, climate, sediment characteristics, physical characteristics of streams, habitat distribution in lakes, biotic components, water chemistry, comparisons with other lakes and streams in the region, and a historical description. Ecosystem models for carbon and mass balances for a number of elements have been calculated to further improve the understanding of the lake ecosystems. Important processes for the safety assessment are described and evaluated in the report. The Forsmark regional model area contains more than 20 permanent lakes and pools. All lakes are small and shallow, and are characterized as oligotrophic hardwater lakes. Calcareous soils in the area give rise to high calcium concentrations in the surface water, which in turn leads to high pH and low nutrient concentrations in water as phosphorus often co-precipitates with calcium. The shallow depths and moderate water colour permit photosynthesis in the entire benthic habitat of the lakes, and the bottoms are covered by dense stands of the macroalgae Chara sp. Moreover, many of the lakes also have a thick microbial mat (>10 cm), consisting of cyanobacteria and diatoms, in the benthic habitat. Fish in

  14. The terrestrial ecosystems at Forsmark and Laxemar-Simpevarp. Site descriptive modelling SDM site

    Loefgren, Anders

    2008-12-01

    This report describes the terrestrial ecosystems in the Forsmark and Laxemar-Simpevarp areas by summarizing ecological data and data from disciplines such as hydrology, quaternary geology and chemistry. The description therefore includes a number of different processes that drive element fluxes in the ecosystems, such as net primary production, heterotrophic respiration, transpiration, and horizontal transport from land to streams and lakes. Moreover, the human appropriation of the landscape is described with regard to land use and potential and actual utilization of food resources both today and in a historical perspective

  15. Updated strategy and test of new concepts for groundwater flow modelling in Forsmark in preparation of site descriptive modelling stage 2.2

    Follin, Sven [SF GeoLogic AB (Sweden); Johansson, Per-Olof [Artesia Grundvattenkonsult AB (Sweden); Leven, Jakob [Geosigma AB (Sweden); Hartley, Lee; Holton, David; McCarthy, Rachel; Roberts, David [Serco Assurance (United Kingdom)

    2007-01-15

    As part of the preliminary Site Descriptive Modelling (SDM version 1.2) for the Initial Site Investigation (ISI) stage at Forsmark, Simpevarp and Laxemar, a methodology was developed for constructing hydrogeological models of the crystalline bedrock. The methodology achieved reasonable success given the restricted amounts and types of data available at the time. Notwithstanding, several issues of concern have surfaced following the reviews of the preliminary site descriptions of the three sites. Possible solutions to parts of the problems have been discussed internally for a longer time and an integrated view and strategy forward has been formulated. The 'new strategy' is not a complete shift in methodology, however, but a refocusing on and clarification of the key aspects that the hydrogeological SDM needs to accomplish. In broad terms the basic principle of the 'new strategy' suggested is to develop an overall conceptual model that first establishes the major flowing deformation zones, and then gradually approaches determination of the hydraulic properties of the bedrock outside these zones in the potential repository volume. On each scale, the focus of the description should be on features/structures of significance on that scale. Clearly, a detailed (although statistical) description of the repository and canister deposition hole scale is the end goal, but this approach (which also is more the traditional approach in hydrogeology) is judged to provide a much better motivated overall geometrical description. Furthermore, the 'new strategy' puts more emphasis on field testing (e.g. interference tests) and data analyses and less on numerical simulation and calibration. That is, before extensive (and costly) simulations and model calibrations are made it needs to be clearly understood what could be the potential gains of carrying them out. This report presents the conceptual model development for Forsmark in preparation of the site

  16. A coupled regolith-lake development model applied to the Forsmark site

    Brydsten, Lars; Stroemgren, Maarten (Umeaa Univ., Umeaa (Sweden))

    2010-11-15

    The Quaternary geology at the Forsmark site has been characterized using both a map of Quaternary deposits and a regolith depth model (RDM) that show the stratigraphy and thickness of different deposits. Regolith refers to all the unconsolidated deposits overlying the bedrock. The surface geology and regolith depth are important parameters for hydrogeological and geochemical modelling and for the overall understanding of the area. The safety assessment analysis should focus on processes involved during a period of 120,000 years, which includes a full glacial cycle; however, the investigations within the site description model do not cover the temporal change of the regolith, a limitation that does not fulfil the requirements for the safety assessment. To this end, this study constructs a model that can predict the surface geology, stratigraphy, and thickness of different strata at any time during a glacial cycle and applies this model to the Forsmark site. The Weichselian ice sheet covered the study area until around 9500 BC. The deglaciation revealed a marine landscape with bedrock, till and glacial clay. For the safety assessment, the most important unconsolidated strata are clay or silt: these small grains can bind nuclear elements more easily than coarser sediment particles. Thick layers of clay can be found where post-glacial clay settled on top of glacial clay, especially where the middle-aged erosion of postglacial clay is missing and where there is an uninterrupted sequence of accumulation of finegrained particles. Such areas could be found in deep marine basins that later become lakes when raised into a supra-marine position. The coupled regolith-lake development model (RLDM) predicts the course of events described above during an interglacial, especially the dynamics of the clay and silt particles. The RLDM is divided into two modules: a marine module that predicts the sediment dynamics caused by wind waves and a lake module that predicts the lake infill

  17. A coupled regolith-lake development model applied to the Forsmark site

    Brydsten, Lars; Stroemgren, Maarten

    2010-11-01

    The Quaternary geology at the Forsmark site has been characterized using both a map of Quaternary deposits and a regolith depth model (RDM) that show the stratigraphy and thickness of different deposits. Regolith refers to all the unconsolidated deposits overlying the bedrock. The surface geology and regolith depth are important parameters for hydrogeological and geochemical modelling and for the overall understanding of the area. The safety assessment analysis should focus on processes involved during a period of 120,000 years, which includes a full glacial cycle; however, the investigations within the site description model do not cover the temporal change of the regolith, a limitation that does not fulfil the requirements for the safety assessment. To this end, this study constructs a model that can predict the surface geology, stratigraphy, and thickness of different strata at any time during a glacial cycle and applies this model to the Forsmark site. The Weichselian ice sheet covered the study area until around 9500 BC. The deglaciation revealed a marine landscape with bedrock, till and glacial clay. For the safety assessment, the most important unconsolidated strata are clay or silt: these small grains can bind nuclear elements more easily than coarser sediment particles. Thick layers of clay can be found where post-glacial clay settled on top of glacial clay, especially where the middle-aged erosion of postglacial clay is missing and where there is an uninterrupted sequence of accumulation of finegrained particles. Such areas could be found in deep marine basins that later become lakes when raised into a supra-marine position. The coupled regolith-lake development model (RLDM) predicts the course of events described above during an interglacial, especially the dynamics of the clay and silt particles. The RLDM is divided into two modules: a marine module that predicts the sediment dynamics caused by wind waves and a lake module that predicts the lake infill

  18. Chemical conditions in present and future ecosystems in Forsmark - implications for selected radionuclides in the safety assessment SR-Site

    Troejbom, Mats; Grolander, Sara

    2010-12-01

    This report is a background report for the biosphere analysis of the SR-Site Safety Assessment. This work aims to describe the future development of the chemical conditions at Forsmark, based on the present chemical conditions at landscape level taking landscape development and climate cases into consideration. The results presented contribute to the overall understanding of the present and future chemistry in the Forsmark area, and specifically, to the understanding of the behaviour of some selected radionuclides in the surface system. The future development of the chemistry at the site is qualitatively discussed with focus on the interglacial within the next 10,000 years. The effects on the chemical environment of future climate cases as Global Warming and cold permafrost climates are also briefly discussed. The work is presented in two independent parts describing background radionuclide activities in the Forsmark area and the distribution and behaviour of a large number of stable elements in the landscape. In a concluding section, implications of the future chemical environment of a selection of radionuclides important in the Safety Assessment are discussed based on the knowledge of stable elements. The broad range of elements studied show that there are general and expected patterns for the distribution and behaviour in the landscape of different groups of elements. Mass balances reveal major sources and sinks, pool estimations show where elements are accumulated in the landscape and estimations of time-scales give indications of the potential future development. This general knowledge is transferred to radionuclides not measured in order to estimate their behaviour and distribution in the landscape. It could be concluded that the future development of the chemical environment in the Forsmark area might affect element specific parameters used in de radionuclide model in different directions depending on element. The alternative climate cases, Global Warming

  19. Chemical conditions in present and future ecosystems in Forsmark - implications for selected radionuclides in the safety assessment SR-Site

    Troejbom, Mats (Mats Troejbom Konsult AB (Sweden)); Grolander, Sara (Facilia AB (Sweden))

    2010-12-15

    This report is a background report for the biosphere analysis of the SR-Site Safety Assessment. This work aims to describe the future development of the chemical conditions at Forsmark, based on the present chemical conditions at landscape level taking landscape development and climate cases into consideration. The results presented contribute to the overall understanding of the present and future chemistry in the Forsmark area, and specifically, to the understanding of the behaviour of some selected radionuclides in the surface system. The future development of the chemistry at the site is qualitatively discussed with focus on the interglacial within the next 10,000 years. The effects on the chemical environment of future climate cases as Global Warming and cold permafrost climates are also briefly discussed. The work is presented in two independent parts describing background radionuclide activities in the Forsmark area and the distribution and behaviour of a large number of stable elements in the landscape. In a concluding section, implications of the future chemical environment of a selection of radionuclides important in the Safety Assessment are discussed based on the knowledge of stable elements. The broad range of elements studied show that there are general and expected patterns for the distribution and behaviour in the landscape of different groups of elements. Mass balances reveal major sources and sinks, pool estimations show where elements are accumulated in the landscape and estimations of time-scales give indications of the potential future development. This general knowledge is transferred to radionuclides not measured in order to estimate their behaviour and distribution in the landscape. It could be concluded that the future development of the chemical environment in the Forsmark area might affect element specific parameters used in de radionuclide model in different directions depending on element. The alternative climate cases, Global Warming

  20. Forsmark site investigation. Investigation of marine and lacustrine sediment in lakes. Field data 2003

    Hedenstroem, Anna [SGU, Uppsala (Sweden)

    2003-04-01

    The aim of this activity is to describe the aerial and stratigraphical distribution of marine and lacustrine sediment i.e. sediment overlaying the glacial till and/or bedrock surface, in lakes in the Forsmark area. The investigation is carried out within areas where mapping of unconsolidated Quaternary deposits is presently carried out. Since small and shallow lakes cover a large part of the region, this work will give important information on the distribution and stratigraphy of sedimentary deposits not included in the regular mapping of unconsolidated Quaternary deposits within the site investigation programme. Samples were also collected for laboratory analyses of grain size distribution, mineralogical composition as well as the total content of C, N and S and calcium carbonate. The analyses will be carried out on selected samples of representative sedimentary units in order to characterise the chemical and physical properties of the unconsolidated deposits. The analytical data will be useful for the hydrogeological modelling and for models of the Quaternary evolution of the area. The mineralogical analyses of clay may provide information on the origin of the clay particles. One stratigraphic sequence from Lake Eckarfjaerden will be stored for later analyses, e.g. pollen analysis. This report includes field data from spring 2003. Together, the field data and the forthcoming results from the laboratory analyses will form the basis for construction of stratigraphical profiles to be presented in a following report in the fall 2003.

  1. Forsmark site investigation. Investigation of marine and lacustrine sediment in lakes. Field data 2003

    Hedenstroem, Anna

    2003-04-01

    The aim of this activity is to describe the aerial and stratigraphical distribution of marine and lacustrine sediment i.e. sediment overlaying the glacial till and/or bedrock surface, in lakes in the Forsmark area. The investigation is carried out within areas where mapping of unconsolidated Quaternary deposits is presently carried out. Since small and shallow lakes cover a large part of the region, this work will give important information on the distribution and stratigraphy of sedimentary deposits not included in the regular mapping of unconsolidated Quaternary deposits within the site investigation programme. Samples were also collected for laboratory analyses of grain size distribution, mineralogical composition as well as the total content of C, N and S and calcium carbonate. The analyses will be carried out on selected samples of representative sedimentary units in order to characterise the chemical and physical properties of the unconsolidated deposits. The analytical data will be useful for the hydrogeological modelling and for models of the Quaternary evolution of the area. The mineralogical analyses of clay may provide information on the origin of the clay particles. One stratigraphic sequence from Lake Eckarfjaerden will be stored for later analyses, e.g. pollen analysis. This report includes field data from spring 2003. Together, the field data and the forthcoming results from the laboratory analyses will form the basis for construction of stratigraphical profiles to be presented in a following report in the fall 2003

  2. Chemistry data from surface ecosystems in Forsmark and Laxemar-Simpevarp. Site specific data used for estimation of CR and Kd values in SR-Site

    Troejbom, Mats; Norden, Sara

    2010-11-01

    This report is a background report for the biosphere analysis of the SR-Site Safety Assessment. This work aims to compile information from the Forsmark and Laxemar-Simpevarp sites in order to select and provide relevant site data for parameter sed in the Radionuclide Dose Model. This report contains an overview of all available chemistry data from the surface ecosystems at Forsmark and Laxemar-Simpevarp areas, comprising hydrochemistry of shallow groundwater, porewater, lake water, stream water and sea water as well as the chemical composition of the regolith and biota of the terrestrial, limnic and marine ecosystems. Detailed references to data reports are tabulated and all sampling points are shown in a large number of maps in Chapter 2. An explorative analysis in Chapter 3 is the basis for the final selection of site data described in Chapter 4

  3. Site investigation SFR. Reprocessing of reflection seismic profiles 5b and 8, Forsmark

    Juhlin, Christopher; Zhang, Fengjiao (Uppsala Univ., Dept. of Earth Sciences (Sweden))

    2010-12-15

    Reflection seismic profiles 5b and 8 in the northern Forsmark area have been reprocessed with the aim of improving the images in the uppermost 500 metres in the SFR area. The main conclusion is that a new reflection (B10) has been identified that may extend below the SFR site. This reflection was not clearly observed in the previous processing. The reflection strikes approximately N25E and dips at about 35 degrees to the southeast. This orientation is similar to the set B group identified earlier /Juhlin and Palm 2005/. Note that the dip of the reflection is uncertain. On shot gathers it appears to dip at a slightly shallower angle while on the stacked sections it appears to dip at a greater angle. This discrepancy is probably due to the crooked nature of the profiles. However, reflections are clearly observed in shot gathers and its presence below SFR is highly probable. Two new reflections were also identified further north along profile 5b (A11 and A12). These dip to the south-southeast, but would be found at a depth of 1-2 km below SFR if they extend to below the site. There are also signs of a 3rd reflection with similar orientation to the set A group identified earlier, A13, but its existence is very speculative. This reflector would intersect the surface within the SFR area. South of the Singoe deformation zone on profile 5b, another new reflection has been found, N1. The orientation of this reflection is speculative since it is not clearly seen on profile 8. It has been modelled as dipping to the north at about 35 degrees and projects to the surface south of the main SFR area. In addition, the orientation of reflection B7 has been revised as has the lateral extent of A1. Most importantly, A1 is now interpreted not to extend to the surface and not cross the Singoe deformation zone

  4. Mechanical modelling of the Singoe deformation zone. Site descriptive modelling Forsmark stage 2.1

    Glamheden, Rune; Maersk Hansen, Lars; Fredriksson, Anders; Bergkvist, Lars; Markstroem, Ingemar; Elfstroem, Mats [Golder Associates AB (Sweden)

    2007-02-15

    This project aims at demonstrating the theoretical approach developed by SKB for determination of mechanical properties of large deformation zones, in particular the Singoe deformation zone. Up to now, only bedrock and minor deformation zones have been characterized by means of this methodology, which has been modified for this project. The Singoe deformation zone is taken as a reference object to get a more comprehensive picture of the structure, which could be incorporated in a future version of the SDM of Forsmark. Furthermore, the Singoe Zone has been chosen because of available data from four tunnels. Scope of work has included compilation and analysis of geological information from site investigations and documentation of existing tunnels. Results have been analyzed and demonstrated by means of RVS-visualization. Numerical modelling has been used to obtain mechanical properties. Numerical modelling has also been carried out in order to verify the results by comparison of calculated and measured deformations. Compilation of various structures in the four tunnels coincides largely with a magnetic anomaly and also with the estimated width. Based on the study it is clear that the Singoe deformation zone has a heterogeneous nature. The number of fracture zones associated with the deformation zone varies on either side of the zone, as does the transition zone between host rock and the Singoe zone. The overall impression from the study is that the results demonstrate that the methodology used for simulating of equivalent mechanical properties is an applicable and adequate method, also in case of large deformation zones. Typical rock mechanical parameters of the Singoe deformations that can be used in the regional stress model considering the zone to be a single fracture are: 200 MPa/m in normal stiffness, 10-15 MPa/m in shear stiffness, 0.4 MPa in cohesion and 31.5 degrees in friction angle.

  5. Mechanical modelling of the Singoe deformation zone. Site descriptive modelling Forsmark stage 2.1

    Glamheden, Rune; Maersk Hansen, Lars; Fredriksson, Anders; Bergkvist, Lars; Markstroem, Ingemar; Elfstroem, Mats

    2007-02-01

    This project aims at demonstrating the theoretical approach developed by SKB for determination of mechanical properties of large deformation zones, in particular the Singoe deformation zone. Up to now, only bedrock and minor deformation zones have been characterized by means of this methodology, which has been modified for this project. The Singoe deformation zone is taken as a reference object to get a more comprehensive picture of the structure, which could be incorporated in a future version of the SDM of Forsmark. Furthermore, the Singoe Zone has been chosen because of available data from four tunnels. Scope of work has included compilation and analysis of geological information from site investigations and documentation of existing tunnels. Results have been analyzed and demonstrated by means of RVS-visualization. Numerical modelling has been used to obtain mechanical properties. Numerical modelling has also been carried out in order to verify the results by comparison of calculated and measured deformations. Compilation of various structures in the four tunnels coincides largely with a magnetic anomaly and also with the estimated width. Based on the study it is clear that the Singoe deformation zone has a heterogeneous nature. The number of fracture zones associated with the deformation zone varies on either side of the zone, as does the transition zone between host rock and the Singoe zone. The overall impression from the study is that the results demonstrate that the methodology used for simulating of equivalent mechanical properties is an applicable and adequate method, also in case of large deformation zones. Typical rock mechanical parameters of the Singoe deformations that can be used in the regional stress model considering the zone to be a single fracture are: 200 MPa/m in normal stiffness, 10-15 MPa/m in shear stiffness, 0.4 MPa in cohesion and 31.5 degrees in friction angle

  6. A preliminary carbon budget for two oligotrophic hardwater lakes in the Forsmark area, Sweden

    Nilsson, Eva [Uppsala Univ. (Sweden). Dept. of Limnology

    2001-06-01

    The Swedish Nuclear Fuel and Waste Management Co (SKB) is responsible for management and disposal of Swedish radioactive waste. The company is planning to construct repositories that will keep radioactive waste away from humans for hundreds of thousands of years. In a safety assessment of the repositories hypothetical releases are used to evaluate the robustness of the repositories. It is important to know how the radioactive nuclides would react if they were released and by which way they could enter the living biota. SFR are responsible for the disposal of low radioactive waste and close to the nuclear plant in Forsmark there is a storage for low radioactive waste. At the moment this storage is located in the bedrock far below the sea level but due to land-rise in the area it will in the future be located above sea level. Hence, it is of importance to know how the surface ecosystems in the area are functioning. A carbon budget for the aquatic ecosystem above SFR in Oeresundsgrepen exist, but it is also important to have a carbon budget for the surface systems in the Forsmark area since SFR in the future will be situated above sea level. Carbon budgets can be used to get a picture of how an ecosystem functions. The carbon flow shows how carbon is transported through a food web from lower trophic levels, e.g. plants and bacteria to higher trophic levels such as fish. Oligotrophic hardwater lakes are the most important lakes in the Forsmark area. This report aims to give a picture of a potential flow of carbon through the ecosystem in two oligotrophic hard-water lakes, Lake Haellefjaerd and Lake Eckarfjaerden. Macrophyte, mainly Chara, were calculated to make up the largest part of the biomass and production in both lakes. Benthic bacteria and microphytobenthos (benthic photosynthesising microorganisms) were other large contributors to the production. Benthic bacteria were found responsible for a major part of respiration and, hence, consumption of carbon in the

  7. A preliminary carbon budget for two oligotrophic hardwater lakes in the Forsmark area, Sweden

    Nilsson, Eva

    2001-06-01

    The Swedish Nuclear Fuel and Waste Management Co (SKB) is responsible for management and disposal of Swedish radioactive waste. The company is planning to construct repositories that will keep radioactive waste away from humans for hundreds of thousands of years. In a safety assessment of the repositories hypothetical releases are used to evaluate the robustness of the repositories. It is important to know how the radioactive nuclides would react if they were released and by which way they could enter the living biota. SFR are responsible for the disposal of low radioactive waste and close to the nuclear plant in Forsmark there is a storage for low radioactive waste. At the moment this storage is located in the bedrock far below the sea level but due to land-rise in the area it will in the future be located above sea level. Hence, it is of importance to know how the surface ecosystems in the area are functioning. A carbon budget for the aquatic ecosystem above SFR in Oeresundsgrepen exist, but it is also important to have a carbon budget for the surface systems in the Forsmark area since SFR in the future will be situated above sea level. Carbon budgets can be used to get a picture of how an ecosystem functions. The carbon flow shows how carbon is transported through a food web from lower trophic levels, e.g. plants and bacteria to higher trophic levels such as fish. Oligotrophic hardwater lakes are the most important lakes in the Forsmark area. This report aims to give a picture of a potential flow of carbon through the ecosystem in two oligotrophic hard-water lakes, Lake Haellefjaerd and Lake Eckarfjaerden. Macrophyte, mainly Chara, were calculated to make up the largest part of the biomass and production in both lakes. Benthic bacteria and microphytobenthos (benthic photosynthesising microorganisms) were other large contributors to the production. Benthic bacteria were found responsible for a major part of respiration and, hence, consumption of carbon in the

  8. Chemical characteristics of surface waters in the Forsmark area. Evaluation of data from lakes, streams and coastal sites

    Sonesten, Lars

    2005-06-01

    This report is an evaluation of the chemical composition of surface water in lakes, streams, and at coastal sampling sites in the Forsmark area. The aim with this study is to characterise the surface water systems in the area, and the further aim with this characterisation is to be used as input material to the safety analyses and environmental impact assessments for the potential deep repository of used nuclear fuels. The data used consist of water chemical composition of lakes, streams and coastal sites from the period March 2002 - April 2004. The sampling has been performed predominantly on a monthly basis. The emphasis of the assessment has been on surface waters (0.5 m), as the water depth at all sampling locations is limited, and thereby the water systems are rarely stratified for prolonged periods. The characterisations have been restricted to the most commonly measured chemical parameters.The assessment has been divided into three parts: Comparisons within and between the lakes, streams, and coastal sites, respectively; Temporal and spatial variation, predominantly within lakes and stream sites; and Relationships between the various chemical parameters. Beside comparisons between the sampling sites within the Forsmark area, comparisons have also been made with regional and national data from the latest Swedish National Survey (2000). The analyses of temporal and spatial variation have been concentrated on the freshwater systems in the Norra Bassaengen catchment area. This catchment area is the most comprehensively investigated, and it also includes the Bolundsfjaerden sub-catchment, which is the area where the continued site investigations will be concentrated. The relationships among the sampling sites, the catchment areas, as well as the chemical parameters investigated, were examined by applying PCA analyses on the lake and stream data. In general, the freshwater systems in the Forsmark area are characterised by small and shallow oligotrophic hardwater

  9. Chemical characteristics of surface waters in the Forsmark area. Evaluation of data from lakes, streams and coastal sites

    Sonesten, Lars [Swedish Univ. of Agricultural Sciences, Uppsala (Sweden). Dept. of Environmental Assessment

    2005-06-01

    This report is an evaluation of the chemical composition of surface water in lakes, streams, and at coastal sampling sites in the Forsmark area. The aim with this study is to characterise the surface water systems in the area, and the further aim with this characterisation is to be used as input material to the safety analyses and environmental impact assessments for the potential deep repository of used nuclear fuels. The data used consist of water chemical composition of lakes, streams and coastal sites from the period March 2002 - April 2004. The sampling has been performed predominantly on a monthly basis. The emphasis of the assessment has been on surface waters (0.5 m), as the water depth at all sampling locations is limited, and thereby the water systems are rarely stratified for prolonged periods. The characterisations have been restricted to the most commonly measured chemical parameters.The assessment has been divided into three parts: Comparisons within and between the lakes, streams, and coastal sites, respectively; Temporal and spatial variation, predominantly within lakes and stream sites; and Relationships between the various chemical parameters. Beside comparisons between the sampling sites within the Forsmark area, comparisons have also been made with regional and national data from the latest Swedish National Survey (2000). The analyses of temporal and spatial variation have been concentrated on the freshwater systems in the Norra Bassaengen catchment area. This catchment area is the most comprehensively investigated, and it also includes the Bolundsfjaerden sub-catchment, which is the area where the continued site investigations will be concentrated. The relationships among the sampling sites, the catchment areas, as well as the chemical parameters investigated, were examined by applying PCA analyses on the lake and stream data. In general, the freshwater systems in the Forsmark area are characterised by small and shallow oligotrophic hardwater

  10. Statistical analysis of results from the quantitative mapping of fracture minerals in Forsmark. Site descriptive modelling - complementary studies

    Loefgren, Martin (Niressa AB, Norsborg (Sweden)); Sidborn, Magnus (Kemakta Konsult AB, Stockholm (Sweden))

    2010-12-15

    Within the Forsmark site investigation campaign, quantitative mapping of different fracture minerals has been performed. This has been done by studying fracture surfaces of drill core sections from many different boreholes at the Forsmark site /Eklund and Mattsson 2009/. The drill core mapping was focused on the rock in the vicinity of flow anomalies detected by the Posiva Flow Log (PFL). The quantitative mapping was performed only on open fractures. The fracture minerals that were mapped are calcite, chlorite, clay minerals (as a group), hematite, and pyrite. In this present report, data from the quantitative mineral mapping campaign are refined, sorted into different data subsets, and analysed by parametric and non-parametric statistical methods. The data subsets are associated with 21 different rock volumes, representing different elevations, rock domains, fracture domains, and groups of deformation zones. In total 2,071 fractures were mapped at the site, and the most frequent mineral was calcite. Its amount could be quantitatively estimated in 32% of the mapped fractures. Of the other minerals, chlorite was quantitatively estimated in 24%, clay minerals in 11%, pyrite in 10%, and hematite in 0.4% of the mapped fractures. For fractures where the averaged fracture mineral thickness, d{sub mean} [mm], and visible coverage, C{sub vis} [%], could be quantitatively estimated, the following arithmetic means were found: calcite = 0.11 mm and 18%, chlorite = 0.22 mm and 38%, clay minerals = 0.14 mm and 40%, pyrite = 2.3 mum and 0.5%, hematite = 19 mum and 14%. These quantities are based on visual inspection of fracture surfaces and do not include the contribution from non-consolidated fracture fillings. It is shown that there is significant spatial variability of d{sub mean} and C{sub vis} within the examined rock volumes. Furthermore, the non-parametric analyses indicate that there are differences in d{sub mean} and C{sub vis} between the different rock volumes. Even

  11. Rock thermal property measurements with the Posiva TERO56 drill hole device in the forsmark study site

    Kukkonen, I.; Suppala, I.; Korpisalo, A.

    2007-10-01

    Thermal properties were measured in situ in Forsmark at the SKB study site constructed for large-scale thermal conductivity investigations in an outcrop of anisotropic granite. The Posiva TERO56 drill hole tool was used for in situ measurements in four 20 m deep boreholes KFM90C, D, E and F located within very short distances of each other (less than 2.3 m). Measurements were done at depths of 10-18 m in water-filled holes. The bedrock is granite with thin amphibolite and pegmatite layers and thin felsic veins. The measurement principle of the TERO56 logging device is based on conduction of heat from a cylindrical source placed in a borehole and the thermal parameter values are calculated with a least squares inversion algorithm. Measurements in Forsmark consisted typically of 6 hours heating time followed by 10 hours cooling time, but in one measurement the heating time was reduced to of 2 h 45 min and the cooling time to 5 hours. Average thermal conductivity values range from 3.37 to 3.91 W m -1 K -1 with standard deviations between 0.01 and 0.04 W m -1 K -1 . The result is plausible considering the quite homogeneous target geology and short distances between different experiment stations. Diffusivity values, however, vary much more, and averages range from 0.68 to 2.08 A 10 -6 m 2 s -1 with standard deviations ranging from 0.04 to 0.09 A 10 -6 m 2 s -1 . Variations may be attributed to small flow effects or time-dependent temperature trends related to thermal equilibration of the probe. (orig.)

  12. Mineralogy, geochemistry, porosity and redox properties of rocks from Forsmark. Compilation of data from the regional model volume for SR-Site

    Sandstroem, Bjoern (WSP Sverige AB, Stockholm (Sweden)); Stephens, Michael B. (Geological Survey of Sweden, Uppsala (Sweden))

    2009-11-15

    This report is a compilation of the data acquired during the Forsmark site investigation programme on the mineralogy, geochemistry, redox properties and porosity of different rock types at Forsmark. The aim is to provide a final summary of the available data for use during the SR-Site modelling work. Data presented in this report represent the regional model volume and have previously been published in various SKB reports. The data have been extracted from the SKB database Sicada and are presented as calculated median values, data range and lower/upper quartile. The representativity of all samples used for the calculations have been evaluated and data from samples where there is insufficient control on the rock type have been omitted. Rock samples affected by alteration have been omitted from the unaltered samples and are presented separately based on type of alteration (e.g. oxidised or albitized rock)

  13. Forsmark 1

    Fredell, J.; Henriksson, T.

    1981-12-01

    ASEA-ATOM carried out an experiment in Forsmark 1 in 1978, in conjunction with discharge test, by means of the safety/relief valves. The tests have been carried out for the case of single valve actuation (SVA), multiple valve actuations (MVA) and consecutive valve actuations (CVA). During MVA tests, up to 12 valves have been used. One of the aims of the experiment was to confirm the operation of the new design of mitigator of the discharge pipes and another was to survey the pressure oscillations in the pool and the vibratory behaviour of the structures and components. The results of these measurements are presented in a number of reports. This report contains an abstract of the results of the measurements presented in these reports. This report also describes the theoretical background and comparisons between test and theoretical results. It is clear that very good agreement has been established between earlier steam discharge experiments, using a mitigator of the type fitted in Forsmark 1, and this experiment. This is based on the fact the amplitude, frequency and distribution of the pressure oscillations in the condensation pool are basically equal to the values predicted by calculations based on the earlier experiments. The low maximum acceleration amplitudes predicted by the beam type structural model have been confirmed, but the frequency content of the response is not very well represented by this type of model. The shell-beam finite element model of the structure gives better agreement with the measured frequency. (author)

  14. Conceptual and numerical modelling of radionuclide transport in near-surface systems at Forsmark. SR-Site Biosphere

    Pique, Angels; Grandia, Fidel; Sena, Clara; Arcos, David; Molinero, Jorge; Duro, Lara; Bruno, Jordi

    2010-11-01

    In the framework of the SR-Site safety assessment, a conceptual and numerical modelling of radionuclide reactive transport in near-surface systems (including till and clay systems) at Forsmark has been carried out. The objective was to evaluate the retention capacity of the near-surface systems, composed of Quaternary deposits, which would be the last natural barrier for an eventual radionuclide release from the deep repository prior to reaching the biosphere. The studied radionuclides are 14 C, 129 I, 36 Cl, 94 Nb, 59 Ni, 93 Mo, 79 Se, 99 Tc, 230 Th, 90 Sr, 226 Ra, 135 Cs and U. Conceptual description and numerical simulations of radionuclide reactive transport show that cation exchange and surface complexation on illite are active processes for the retention of several radionuclides (U, Th, Ni, Cs, Sr, Ra). Surface complexation on iron hydroxide is an active process in the till system, able to effectively retain U and Ni. Another retention process of importance is the incorporation of the radionuclides into mineral phases, either by the precipitation of pure phases or solid solutions. Quantitative modelling has been useful to illustrate the incorporation of C and Sr in the carbonate solid solution in the considered model domains (till and clay), as well as the precipitation of uraninite in the clay sediments and the precipitation of native selenium and radiobarite in the till. Other mineral phases that could, a priori, retain U, Se, Nb and Tc do not precipitate in the simulations, either due to the pH-Eh conditions and/or because the dissolved concentration of the element is not high enough under the considered simulation conditions. It is important to keep in mind that changes in these parameters and in the boundary conditions could modify the predicted behaviour of these elements. The radionuclides that are most significantly retarded are Th, Ni and Cs, mainly through sorption onto illite. Therefore, if the amount of illite (or available sorption sites

  15. Conceptual and numerical modelling of radionuclide transport in near-surface systems at Forsmark. SR-Site Biosphere

    Pique, Angels; Grandia, Fidel; Sena, Clara; Arcos, David; Molinero, Jorge; Duro, Lara; Bruno, Jordi (Amphos21 Consulting S.L., Barcelona (Spain))

    2010-11-15

    In the framework of the SR-Site safety assessment, a conceptual and numerical modelling of radionuclide reactive transport in near-surface systems (including till and clay systems) at Forsmark has been carried out. The objective was to evaluate the retention capacity of the near-surface systems, composed of Quaternary deposits, which would be the last natural barrier for an eventual radionuclide release from the deep repository prior to reaching the biosphere. The studied radionuclides are 14C, 129I, 36Cl, 94Nb, 59Ni, 93Mo, 79Se, 99Tc, 230Th, 90Sr, 226Ra, 135Cs and U. Conceptual description and numerical simulations of radionuclide reactive transport show that cation exchange and surface complexation on illite are active processes for the retention of several radionuclides (U, Th, Ni, Cs, Sr, Ra). Surface complexation on iron hydroxide is an active process in the till system, able to effectively retain U and Ni. Another retention process of importance is the incorporation of the radionuclides into mineral phases, either by the precipitation of pure phases or solid solutions. Quantitative modelling has been useful to illustrate the incorporation of C and Sr in the carbonate solid solution in the considered model domains (till and clay), as well as the precipitation of uraninite in the clay sediments and the precipitation of native selenium and radiobarite in the till. Other mineral phases that could, a priori, retain U, Se, Nb and Tc do not precipitate in the simulations, either due to the pH-Eh conditions and/or because the dissolved concentration of the element is not high enough under the considered simulation conditions. It is important to keep in mind that changes in these parameters and in the boundary conditions could modify the predicted behaviour of these elements. The radionuclides that are most significantly retarded are Th, Ni and Cs, mainly through sorption onto illite. Therefore, if the amount of illite (or available sorption sites) decreases, the

  16. Rock-block configuration in Uppland and the Aalands-hav basin, the regional surroundings of the SKB site in Forsmark, Sea and land areas, eastern Sweden

    Beckholmen, Monica; Tiren, Sven A. (GEOSIGMA AB (Sweden))

    2010-12-15

    The Forsmark SKB site lies at the west-northwest trending shoreline in northern Uppland, sheltered from the sea by one of the larger islands in the Uppland archipelago, Graesoe. To assess the structures around Forsmark also in the sea area, the bottom structures of the Aalands-hav basin were investigated by means of depth readings from sea charts. Two rock-block maps with rock blocks at different scales were constructed and analysed for their top surface elevation. The topography in Uppland is more broken in the sea area east and northeast of Forsmark than it is on land. The major structure in the Aalands-hav basin is a westnorth- westerly line that passes southwest of Aaland, with a very steep gradient from the Aaland archipelago down to an exceptionally low sea-floor valley. On its southern side it rises in steps to a low flat basin divided into a deeper western half and a somewhat shallower eastern half. The deep west-north-westerly zone can be traced on-land past Oeregrund and Forsmark. West of Oeregrund however, the main trough swings into a north-northwesterly direction, just west of Graesoe. The southern border south of Oeregrund and Forsmark, shows a major drop in elevation northern side down. Forsmark thus lies on a ribbon with lower ground on both its southern and northern boundaries. This west-north-westerly belt is cut in two by a major north-south lineament that cuts through the archipelago between Aaland and Graesoe with a very deep canyon. This structure was seismically active in June 2006. The southern part of this line constitutes the western border of the low basin and has a steep gradient on its western side up to the Uppland mainland. The deep basin is filled with Jotnian metasediments. South of this basin, the Uppland mainland continues under water towards the east. South of Aaland an east-north-easterly ridge separates the low basin to the north from an east-west trending trough which is the eastern continuation of a major onland structure

  17. Rock-block configuration in Uppland and the Aalands-hav basin, the regional surroundings of the SKB site in Forsmark, Sea and land areas, eastern Sweden

    Beckholmen, Monica; Tiren, Sven A.

    2010-12-01

    The Forsmark SKB site lies at the west-northwest trending shoreline in northern Uppland, sheltered from the sea by one of the larger islands in the Uppland archipelago, Graesoe. To assess the structures around Forsmark also in the sea area, the bottom structures of the Aalands-hav basin were investigated by means of depth readings from sea charts. Two rock-block maps with rock blocks at different scales were constructed and analysed for their top surface elevation. The topography in Uppland is more broken in the sea area east and northeast of Forsmark than it is on land. The major structure in the Aalands-hav basin is a westnorth- westerly line that passes southwest of Aaland, with a very steep gradient from the Aaland archipelago down to an exceptionally low sea-floor valley. On its southern side it rises in steps to a low flat basin divided into a deeper western half and a somewhat shallower eastern half. The deep west-north-westerly zone can be traced on-land past Oeregrund and Forsmark. West of Oeregrund however, the main trough swings into a north-northwesterly direction, just west of Graesoe. The southern border south of Oeregrund and Forsmark, shows a major drop in elevation northern side down. Forsmark thus lies on a ribbon with lower ground on both its southern and northern boundaries. This west-north-westerly belt is cut in two by a major north-south lineament that cuts through the archipelago between Aaland and Graesoe with a very deep canyon. This structure was seismically active in June 2006. The southern part of this line constitutes the western border of the low basin and has a steep gradient on its western side up to the Uppland mainland. The deep basin is filled with Jotnian metasediments. South of this basin, the Uppland mainland continues under water towards the east. South of Aaland an east-north-easterly ridge separates the low basin to the north from an east-west trending trough which is the eastern continuation of a major onland structure

  18. SR-Site: Oxygen ingress in the rock at Forsmark during a glacial cycle

    Sidborn, Magnus (Kemakta Konsult AB (Sweden)); Sandstroem, Bjoern (WSP Sverige AB (Sweden)); Tullborg, Eva-Lena (Terralogica AB (Sweden)); Salas, Joaquin; Maia, Flavia; Delos, Anne; Molinero, Jorge (Amphos21 (Spain)); Hallbeck, Lotta; Pedersen, Karsten (Microbial Analytics Sweden AB (Sweden))

    2010-11-15

    The aim of this report is to assess the possibility for oxygen to be transported by glacial melt-water to canister positions in a final repository for spent nuclear fuel at the proposed location in Forsmark. The approach for this assessment is to combine reactive transport modelling with geological observations of present and historical indications of oxygen ingress. For safety assessment purposes a cautious approach in the modelling is required when estimating the extent of oxygen ingress. In this report, a cautious approach has been applied both in the conceptualisation of the problem and in the choice of input parameters used in the models. Oxygen consuming processes are only neglected in the modelling if they are expected to further decrease the extent of oxygen ingress. Several oxygen consuming processes have been identified, each of which may play an important role in the scavenging of oxygen along recharge flow paths in the rock. These processes include biological pathways with degradation of organic material of ground surface origin, and biotically mediated reactions with reduced rock minerals and with various materials expected to be present in the backfilled repository volume. In the absence of microbes most of these reactions may also follow abiotic pathways. Present day observations show that degradation of organic material is the most powerful oxygen scavenging process. At Forsmark, oxygen is generally depleted within a few metres under present day temperate conditions. Although biological activity is likely to exist also during different phases of a glaciation, large uncertainties exist regarding e.g. the population growth dynamics, the biotic reaction rates and the availability of organic material under the highly varying conditions expected. Microbial activity and degradation of organic material is therefore pessimistically neglected in the calculations in this report. In the absence of organic material, ferrous iron present in minerals in the rock

  19. SR-Site: Oxygen ingress in the rock at Forsmark during a glacial cycle

    Sidborn, Magnus; Sandstroem, Bjoern; Tullborg, Eva-Lena; Salas, Joaquin; Maia, Flavia; Delos, Anne; Molinero, Jorge; Hallbeck, Lotta; Pedersen, Karsten

    2010-11-01

    The aim of this report is to assess the possibility for oxygen to be transported by glacial melt-water to canister positions in a final repository for spent nuclear fuel at the proposed location in Forsmark. The approach for this assessment is to combine reactive transport modelling with geological observations of present and historical indications of oxygen ingress. For safety assessment purposes a cautious approach in the modelling is required when estimating the extent of oxygen ingress. In this report, a cautious approach has been applied both in the conceptualisation of the problem and in the choice of input parameters used in the models. Oxygen consuming processes are only neglected in the modelling if they are expected to further decrease the extent of oxygen ingress. Several oxygen consuming processes have been identified, each of which may play an important role in the scavenging of oxygen along recharge flow paths in the rock. These processes include biological pathways with degradation of organic material of ground surface origin, and biotically mediated reactions with reduced rock minerals and with various materials expected to be present in the backfilled repository volume. In the absence of microbes most of these reactions may also follow abiotic pathways. Present day observations show that degradation of organic material is the most powerful oxygen scavenging process. At Forsmark, oxygen is generally depleted within a few metres under present day temperate conditions. Although biological activity is likely to exist also during different phases of a glaciation, large uncertainties exist regarding e.g. the population growth dynamics, the biotic reaction rates and the availability of organic material under the highly varying conditions expected. Microbial activity and degradation of organic material is therefore pessimistically neglected in the calculations in this report. In the absence of organic material, ferrous iron present in minerals in the rock

  20. Preliminary Site Suitability Evaluation

    J. L. King

    2001-01-01

    Commercial electric power generation, nuclear weapons production, the operation of naval reactors, and research and development activities produce spent nuclear fuel and high-level radioactive waste. Spent nuclear fuel and high-level radioactive waste have been accumulating at commercial reactor sites and storage facilities across the country since 1957. Spent nuclear fuel and high-level radioactive waste have been accumulating at sites now managed by U.S. Department of Energy (DOE) since the mid-1940s. The DOE has the statutory obligation to dispose of these wastes. The U.S. has studied methods for the safe storage and disposal of radioactive waste for more than 40 years. Many organizations and government agencies have participated in these studies. In the 1950s, the U.S. Atomic Energy Commission requested the National Academy of Sciences to evaluate options for land disposal of radioactive waste. The U.S. Atomic Energy Commission and its successor agencies, the Energy Research and Development Administration and the DOE, continued to analyze radioactive waste management options throughout the 1960s and 1970s. In 1979, an Interagency Review Group that included representatives of 14 federal government entities provided findings and recommendations to the President. After analyzing a range of options, disposal in a geologic repository emerged as the preferred long-term environmental solution. This consensus is reflected in the Nuclear Waste Policy Act of 1982 (NWPA). The NWPA and related statutes established the framework for addressing the issues of radioactive waste disposal and designated the roles and responsibilities of the federal government and the owners and generators of the waste

  1. Forsmark site investigation. Hydrochemical monitoring of groundwaters and surface waters. Results from water sampling in the Forsmark area, January-December 2009

    Nilsson, Ann-Chatrin (ed.); Berg, Cecilia; Harrstroem, Johan; Joensson, Stig; Thur, Pernilla (Geosigma AB (Sweden)); Borgiel, Micke; Qvarfordt, Susanne (Sveriges Vattenekologer AB (Sweden))

    2010-09-15

    The fifth year (2009) of hydrochemical monitoring of groundwaters, surface waters and precipitation in Forsmark is documented in the report. The hydrochemical monitoring programme 2009 included water sampling from: - percussion- and core boreholes equipped with installations for long-term pressure monitoring, tracer tests and water sampling in packed off borehole sections, sampling and analysis performed twice (spring and autumn), - near surface groundwaters (sampling four times a year), - private wells (once per year in October), - surface waters (eleven sampling occasions per year). Due to the somewhat different performance of the hydrogeochemical monitoring of the deep groundwaters during the autumn 2009 compared to previous years, some new findings and knowledge were obtained: 1) Removal of water volumes corresponding to three to five times the volume of the borehole section (the routine procedure) is seldom enough to obtain a complete exchange of the water present in the borehole section when the pumping starts. 2) It is likely that the elevated sulphide concentrations observed in the monitoring programme /1/ is due to contamination from initial water present in the borehole sections when the pumping starts. This water may have a very high sulphide concentration. Dirty water in tubes and in stand pipes may also contribute to the enhanced sulphide concentration. 3) Plug flow calculations will be introduced in the future as a new routine procedure to estimate the water volumes to be removed, in order to exchange the section water volume, prior to groundwater sampling in delimited borehole sections. During the autumn sampling, sample series of five samples per sampling location were collected during continuous pumping in thirteen selected borehole sections. Furthermore, special efforts were put on cleaning of stand pipes and exchange of water prior to sampling. The analytical protocol was rather extensive and included sulphide and uranium analyses for each sample

  2. Forsmark site investigation. Hydrochemical monitoring of groundwaters and surface waters. Results from water sampling in the Forsmark area, January-December 2009

    Nilsson, Ann-Chatrin; Borgiel, Micke; Qvarfordt, Susanne

    2010-09-01

    The fifth year (2009) of hydrochemical monitoring of groundwaters, surface waters and precipitation in Forsmark is documented in the report. The hydrochemical monitoring programme 2009 included water sampling from: - percussion- and core boreholes equipped with installations for long-term pressure monitoring, tracer tests and water sampling in packed off borehole sections, sampling and analysis performed twice (spring and autumn), - near surface groundwaters (sampling four times a year), - private wells (once per year in October), - surface waters (eleven sampling occasions per year). Due to the somewhat different performance of the hydrogeochemical monitoring of the deep groundwaters during the autumn 2009 compared to previous years, some new findings and knowledge were obtained: 1) Removal of water volumes corresponding to three to five times the volume of the borehole section (the routine procedure) is seldom enough to obtain a complete exchange of the water present in the borehole section when the pumping starts. 2) It is likely that the elevated sulphide concentrations observed in the monitoring programme /1/ is due to contamination from initial water present in the borehole sections when the pumping starts. This water may have a very high sulphide concentration. Dirty water in tubes and in stand pipes may also contribute to the enhanced sulphide concentration. 3) Plug flow calculations will be introduced in the future as a new routine procedure to estimate the water volumes to be removed, in order to exchange the section water volume, prior to groundwater sampling in delimited borehole sections. During the autumn sampling, sample series of five samples per sampling location were collected during continuous pumping in thirteen selected borehole sections. Furthermore, special efforts were put on cleaning of stand pipes and exchange of water prior to sampling. The analytical protocol was rather extensive and included sulphide and uranium analyses for each sample

  3. Chemistry data from surface ecosystems in Forsmark and Laxemar-Simpevarp. Site specific data used for estimation of CR and K{sub d} values in SR-Site

    Troejbom, Mats [Mats Troejbom Konsult AB (Sweden); Norden, Sara [Svensk Kaernbraenslehantering AB (Sweden)

    2010-11-15

    This report is a background report for the biosphere analysis of the SR-Site Safety Assessment. This work aims to compile information from the Forsmark and Laxemar-Simpevarp sites in order to select and provide relevant site data for parameter sed in the Radionuclide Dose Model. This report contains an overview of all available chemistry data from the surface ecosystems at Forsmark and Laxemar-Simpevarp areas, comprising hydrochemistry of shallow groundwater, porewater, lake water, stream water and sea water as well as the chemical composition of the regolith and biota of the terrestrial, limnic and marine ecosystems. Detailed references to data reports are tabulated and all sampling points are shown in a large number of maps in Chapter 2. An explorative analysis in Chapter 3 is the basis for the final selection of site data described in Chapter 4

  4. Monitoring Forsmark - Bird monitoring in Forsmark 2012

    Green, Martin [Dept of Biology, Lund Univ., Lund (Sweden)

    2013-03-15

    This report summarizes the monitoring of selected listed (Swedish Red List and/or the EU Birds directive) breeding birds in Forsmark 2002 - 2012. Monitoring of eleven listed species was conducted in the regional model area, including the candidate area in 2012 in the same way as in earlier years. The results from 2012 generally follow patterns recorded in earlier years. 2012 was in general a better bird year compared to 2010 and 2011 and most species (82%) showed increasing or stable numbers from 2011 to 2012. Only two species (18%) decreased in numbers between the last two years. All in all, six species (55 %, black-throated diver, honey buzzard, black grouse, ural owl, wryneck and red-backed shrike) show no significant trends since the start of the bird monitoring (2002/2003/2004 depending on species). During this period three species (27 %, white-tailed eagle, osprey and lesser spotted woodpecker) have increased in numbers while just two (18 %, capercaillie and hazelhen) have decreased. A new pair of black-throated divers was discovered in 2012 and seven resident pairs were registered. Breeding success was very good, the second best during the study period. Population development follows the national pattern, but breeding success seems to be better in Forsmark than in the country as a whole. Honey buzzards and ospreys occurred in good numbers, and breeding success for ospreys was good. No signs of successful breedings of honey buzzards were recorded, but this may mean little as no detailed monitoring of breeding success is made for this species. The white-tailed eagles had their best breeding year since the start of the SKB bird monitoring, meaning that during the last two years local breeding success has been back at the level recorded before the site investigations started. The three grouse species (black grouse, capercaillie and hazelhen) again showed somewhat varying patterns between the last two years as well as in the long run. The black grouse increased

  5. Growth dynamics of fine roots in a coniferous fern forest site close to Forsmark in the central part of Sweden

    Persson, Hans; Stadenberg, Ingela

    2007-12-01

    The seasonal growth dynamics of live and dead roots for trees and the field layer species (g/m 2 , varying diameter fractions) and live/dead ratios were analysed at a fresh/moist coniferous fern forest site close to the nuclear power plant at Forsmark in the central eastern parts of Sweden. The changes in depth distribution of fine roots were observed at depth intervals of the top humus horizon down to 40 cm in the mineral soil profile. The bulk of living fine roots of trees ( 2 . The total quantity of fine roots (live + dead) amounted to 543, 434, 314 and 546 g/m 2 . Considerable quantities of fine roots (< 1 mm in diameter) were attributed to field-layer species (about 18% of the total biomass during the whole period of investigation). The turnover rate (the rate of construction of new roots) for tree fine roots < 1 mm in diameter amounted to at least the size of the average fine-root biomass. Our methods of estimating fine-root production and mortality, involved periodic measurements of live and dead dry weight of the fine roots from sequential core samples of the forest soil. The collected data give a proper and instant measure of the spatial and temporal distribution of fine roots in the undisturbed soil-profile. Data from other fine-root investigations suggest turnover rates in agreement with our present findings. Differences between root growth and turnover should be expected between trees of different age, tree species and different forest sites, but also between different years. Substantial variations in fine-root biomass, necromass and live/dead ratios are found in different forest sites. Correct methods for estimating the amount of live and dead fine-roots in the soil at regular time intervals are essential for any calculation of fine-root turnover. Definition of root vitality differs in literature, making it difficult to compare results from different root investigators. Our investigation clarifies the importance of using distinct morphological criteria

  6. A comparison of two independent interpretations of lineaments from geophysical and topographic data at the Forsmark site

    Johansson, Rune

    2005-03-01

    In the development of site descriptions, uncertainties in the modelling work are given much attention. One aspect of this is the development of alternative models. Given the importance of the lineaments for the continued deformation zone modelling, it has been regarded important to carry out an alternative, independent lineament interpretation at the Forsmark site. The objective of the work presented in this report was to compare the primary and alternative interpretations, which have been provided by two independent groups of geoscientists. A primary interpretation has been carried out by GeoVista AB and an alternative interpretation (within the central part of the site investigation area) by the Geological Survey of Finland (GTK). Based on the results of this comparative study, further evaluation of the inferred lineaments and the need for supplementary information are discussed. When the two sets of inferred lineaments are compared, it must be remembered that the two groups have performed the interpretation work under different conditions. GeoVista AB has a profound knowledge of the geological setting, as opposed to GTK which has been provided only with some basic geological information. The different conditions might very well have affected some of the expert judgements involved in the interpretation process. However, the comparison of the two independent lineament interpretations has revealed that the results are, in principle, reproducible. Nevertheless, there are discrepancies that are judged to be significant and have to be considered during the further assessment of lineaments. The attributes assigned to the inferred lineaments provide an excellent tool for displaying the characteristics of an individual lineament. However, the use of a single attribute or a combination of attributes as a stand-alone criterion for the assessment can be seriously misleading. Whether a lineament represents a deformation zone or not must instead be concluded on the basis of

  7. Modelling of soil depth and lake sediments. An application of the GeoEditor at the Forsmark site

    Vikstroem, Maria

    2005-02-01

    This report aims at describing the modelled soil depth according to three layers with different hydrogeological properties at the Forsmark site, based on available data from boreholes, observation points, seismic data and radar profiles. For the lakes in the area, the sediment has been modelled according to six layers of the most common deposits in the area. The peat layer at Stenroesmossen has also been visualized. The program used in the modelling of soil depths is the GeoEditor, which is an ArcView3.3-extension. The input data used in the model consist of 1,532 points based on seismic measurements, 31 profiles of interpreted ground penetrating radar data, 119 boreholes and 472 observation points. The western and south eastern part of the area has a low data density. In the southern parts the data density with respect to estimated bedrock elevation is low. Observation points in this area are generally not very deep and do not describe the actual bedrock elevation. They do, however, describe the minimum soil depth at each location. A detailed topographical DEM, bathymetry and map of Quaternary deposits were also used. The model is based on a three-layer-principle where each layer is assumed to have similar hydrological characteristics. The uppermost layer, Z1, is characterized by the impact from surface processes, roots and biological activity. The bottom layer, Z3, is characterized by contact with the bedrock. The middle layer, Z2, is assumed to have different hydraulic qualities than Z1 and Z3. The lake sediments have been modelled according to six classes of typical deposits. The modelled soil depths show a relatively high bedrock elevation and thus small total soil depth in the major part of the area. The median soil depth has been calculated to 1.9 m, based on model results in areas with higher data density. The maximum modelled soil depth is about 13 m, just north of Lake Stocksjoen. Generally, the sediment layers in the lakes of the area consists of a

  8. District heating from Forsmark

    1980-11-01

    The district heating system of Greater Stockholm must be based on other energy sources than oil. Two alternatives are assessed, namely heat from Forsmark or a coal fueled plant in the region of Stockholm. Forsmark 3 can produce both electricity and heat from the year 1988 on. The capacity can be increased by coal fueled blocks. For low electricity use, 115 TWh in the year 1990, the Forsmark alternative will be profitable. The alternative will be profitable. The alternative with a fossile fuelled plant will be profitable when planning for high consumption of electricity, 125 TWh. The Forsmark alternative means high investments and the introduction of new techniques. (G.B.)

  9. Site descriptive modelling Forsmark, stage 2.2. A fracture domain concept as a basis for the statistical modelling of fractures and minor deformation zones, and interdisciplinary coordination

    Olofsson, Isabelle; Simeonov, Assen [Swedish Nuclear Fuel and Waste Manageme nt Co., Stockholm (Sweden); Stephens, Michael [Geological Survey of Sweden (SGU), U ppsala (Sweden); Follin, Sven [SF GeoLogic AB, Taeby (Sweden); Nilsson, Ann-Chatrin [G eosigma AB, Uppsala (Sweden); Roeshoff, Kennert; Lindberg, Ulrika; Lanaro, Flavio [Bergbygg konsult AB, Haesselby (Sweden); Fredriksson, Anders; Persson, Lars [Golder Associat es AB (Sweden)

    2007-04-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is undertaking site characterization at two different locations, Forsmark and Simpevarp/Laxemar, with the objective of siting a final waste repository at depth for spent nuclear fuel. The programme is built upon the development of site descriptive models after each data freeze. This report describes the first attempt to define fracture domains for the Forsmark site modelling in stage 2.2. Already during model version 1.2 at Forsmark, significant spatial variability in the fracture pattern was observed. The variability appeared to be so significant that it provoked the need for a subdivision of the model volume for the treatment of geological and hydrogeological data into sub-volumes. Subsequent analyses of data collected up to data freeze 2.1 led to a better understanding of the site and a concept for the definition of fracture domains based on geological characteristics matured. The main objectives of this report are to identify and describe fracture domains at the site on the basis of geological data and to compile hydrogeological, hydrogeochemical and rock mechanics data within each fracture domain and address the implications of this integration activity. On the basis of borehole data, six fracture domains (FFM01-FFM06) have been recognized inside and immediately around the candidate volume. Three of these domains (FFM01, FFM02 and FFM06) lie inside the target volume for a potential repository in the northwestern part of the candidate area, and need to be addressed in the geological DFN modelling work. The hydrogeological data support the subdivision of the bedrock into fracture domains FFM01, FFM02 and FFM03. Few or no data are available for the other three domains. The hydrogeochemical data also support the subdivision into fracture domains FFM01 and FFM02. Since few data are available from the bedrock between deformation zones inside FFM03, there is little information on the hydrogeochemical

  10. Forsmark site investigation. Monitoring of brook water levels, electrical conductivities, temperatures and discharges January-December 2009

    Johansson, Per-Olof (Artesia Grundvattenkonsult (Sweden)); Juston, John (Juston Konsult (Sweden))

    2011-03-15

    This document reports the monitoring of water levels, electrical conductivities, temperatures and discharges at four brook discharge gauging stations, and the monitoring of water electrical conductivity at the outlet of Lake Bolundsfjaerden in the Forsmark area. The report presents data from 1 January through 31 December 2009 and is a continuation of reporting from Johansson and Juston (2007, 2009), which covered the periods from 1 April 2004 through 31 March 2007 and 1 April 2007 through 31 December 2008, respectively. Long-throated flumes equipped with automatically recording devices were used for the discharge measurements. Every c. 14 days the water depths at the upstream edge of the flumes were measured manually by a ruler as a check. Electrical conductivity and temperature were automatically recorded and these parameters were also measured manually every c. 14 days with the site investigation field devices. SKB's Hydro Monitoring System (HMS) was used to collect and store all data. From HMS quality assured data were transferred to SKB's primary database Sicada. Measurements of levels, electrical conductivities and temperatures were made every 10 minutes (every 30 minutes for electrical conductivity at the outlet of Lake Bolundsfjaerden). For the calculation of discharge, quality assured water level data from the flumes were used. The calculation procedure included consolidation of the time series to hourly averages, screening of data for removal of short-term spikes, noise and other data that were judged erroneous. After the calculations were performed, the results were delivered to Sicada. The amplitudes of water level variations during this reporting period were 0.26-0.33 m at the four stations. The mean electrical conductivities varied between 26 and 41 mS/m at the four discharge stations. The electrical conductivity at the outlet of Lake Bolundsfjaerden varied between 53 and 188 mS/m during the period with the higher values at the end of the

  11. Forsmark site investigation. Monitoring of brook water levels, electrical conductivities, temperatures and discharges January-December 2010

    Johansson, Per-Olof (Artesia Grundvattenkonsult (Sweden)); Juston, John (Juston Konsult (Sweden))

    2011-06-15

    This document reports the monitoring of water levels, electrical conductivities, temperatures and discharges at four brook discharge gauging stations, and the monitoring of water electrical conductivity at the outlet of Lake Bolundsfjaerden in the Forsmark area. The report presents data from 1 January through 31 December 2010 and is a continuation of reporting from Johansson and Juston (2007, 2009, 2011), which covered the periods from 1 April 2004 through 31 March 2007, 1 April 2007 through 31 December 2008, and 1 January through 31 December 2009, respectively. Long-throated flumes equipped with automatically recording devices were used for the discharge measurements. Every c. 14 days the water depths at the upstream edge of the flumes were measured manually by a ruler as a check. Electrical conductivity and temperature were automatically recorded and these parameters were also measured manually every c. 14 days with the site investigation field devices. SKB's Hydro Monitoring System (HMS) was used to collect and store all data. From HMS quality assured data were transferred to SKB's primary database Sicada. Measurements of levels, electrical conductivities and temperatures were made every 10 minutes (every 30 minutes for electrical conductivity at the outlet of Lake Bolundsfjaerden). For the calculation of discharge, quality assured water level data from the flumes were used. The calculation procedure included consolidation of the time series to hourly averages, screening of data for removal of short-term spikes, noise and other data that were judged erroneous. After the calculations were performed, the results were delivered to Sicada. The amplitudes of water level variations during this reporting period were 0.41-0.55 m and the mean electrical conductivities varied between 23 and 39 mS/m at the four discharge stations. However, due to mal-function of measuring devices for electrical conductivity, data were missing for relatively long time periods. Due

  12. Present status and an appreciation of the consequences for recreation and outdoor leisure activities from siting a nuclear waste repository at Forsmark; Nulaegesanalys samt bedoemning av konsekvenser foer rekreation och friluftsliv av ett slutfoervar i Forsmark

    Ottosson, Pia [Atrax Energi AB, Stockholm (Sweden)

    2007-07-15

    This report describes how the area around Forsmark is used with respect to recreation and outdoor life. It also describes the impact of the final repository on recreation and outdoor life if it is located in Forsmark. The studied area is situated in the parish of Forsmark in the municipality of Oesthammar. Forsmark nuclear power plant and the final repository for radioactive operational waste, SFR, are situated within the area and there are both houses and holiday houses. The area is used for leisure pursuit by inhabitants and employees at FKA and SKB, but also by a number of different associations and by tourists. Statistical data shows that the parish of Forsmark is sparsely populated. The area was previously dominated by one big landowner and the land surrounding the nuclear power plant was inaccessible to the general public during that period. The outdoor life is therefore less widespread here than along other parts of the east coast. The value of the area does not lie in paths and trails, bike tracks and bathing places, but in the unspoiled countryside, the wildlife and the bird life. Recreation such as hunting and fishing is very popular in the area. The construction of a final repository will increase traffic and hence increase noise and motion in the area. This will mainly impact the enjoyment value for the people spending time in the area. No other significant consequences are expected as the final repository will be mainly situated within the existing industrial complex and hence the character of the area should remain unchanged.

  13. Growth dynamics of fine roots in a coniferous fern forest site close to Forsmark in the central part of Sweden

    Persson, Hans; Stadenberg, Ingela (SLU, Dept. of Ecology and Environmental Research, Uppsala (Sweden))

    2007-12-15

    The seasonal growth dynamics of live and dead roots for trees and the field layer species (g/m2, varying diameter fractions) and live/dead ratios were analysed at a fresh/moist coniferous fern forest site close to the nuclear power plant at Forsmark in the central eastern parts of Sweden. The changes in depth distribution of fine roots were observed at depth intervals of the top humus horizon down to 40 cm in the mineral soil profile. The bulk of living fine roots of trees (< 1 mm in diameter) were found in the mineral soil horizon the total profile down to 40 cm of the mineral soil, where 89, 82, 83 and 89% of the total amount in the whole profile were found. The upper 2.5 cm part of the humus layer contained 83, 81, 100 and 100% of all roots of the humus layer on the four different sampling occasions. High amounts of living fine roots were found in the upper 10 cm of the mineral soil horizon viz. 84, 76, 91 and 69% of the total mineral soil layer. Consequently, both the top soil horizons of the humus and the mineral soil layers were heavily penetrated by living fine roots. The highest proportion of living fine roots was found in the top 2.5 cm of the humus layer. Accordingly, the live/dead ratio of fine roots (< 1 mm in diameter) decreased from the top of the humus layer to the lower part of mineral soil horizon from 8.0-0.3, 0.8-0.2, 4.4-0.4 and 3.3-0.7 (g g-1) for the four sampling occasions, respectively. We concluded that the decrease in the live/ dead ratio was related to decreased vitality with depth of the fine roots in the soil profile. The highest live/dead ratio was found in the upper 2.5 cm of the humus layer for both the tree and field-layer species. This distribution pattern was most evident for tree fine roots < 1 mm in diameter. The mean fine-root biomass (live tissue < 1 mm in diameter) of tree species for the total profile varied on the four sampling occasions between 317, 113, 139 and 248 g m-2. The related fine root necromass (dead tissue

  14. Large-Scale Groundwater Flow with Free Water Surface Based on Data from SKB's Site Investigation in the Forsmark Area

    Woerman, Anders; Sjoegren, Bjoern; Marklund, Lars

    2004-12-01

    This report describes a data-base that covers entire Sweden with regard to various geographical parameters with implications to simulation of groundwater circulation on a regional and continental scale. The data-base include topography, stream network properties, and-use and water chemistry for limited areas. Furthermore, the report describes a computational (finite difference) code that solves the continuum equation for laminar, stationary and isotropic groundwater flow. The formulation accounts for a free groundwater surface except where the groundwater recharge into the stream network and lake bottoms. The theoretical background of the model is provided and the codes are described. The report also contain a simple user manual in a Matlab environment and provides and example calculation for the Forsmark area, Uppland, Sweden.

  15. Preliminary Hydrogeochemical Site Description SFR (version 0.2)

    Nilsson, Ann-Chatrin (Geosigma AB, Uppaala (Sweden)); Tullborg, Eva-Lena (Terralogica AB, Graabo (Sweden)); Smellie, John (Conterra AB, Partille (Sweden))

    2010-05-15

    The final repository for low and intermediate level radioactive operational waste, SFR, located about 150 km north of Stockholm, is to undergo a future extension. The present on-going project, scheduled from 2007 to 2011, is to define and characterise a suitable bedrock volume for the extended repository. This will include the drilling and geoscientific evaluation of seven core-drilled and four percussion boreholes as well as subsequent interpretation and modelling based on the obtained results in order to provide the necessary information for safety assessment and repository design. This report presents a preliminary hydrogeochemical site description for the SFR site and should be considered as an early progress report rather than a complete hydrochemical site descriptive model. The completed hydrogeochemical field investigations have yielded chemical data from a total of 12 borehole sections in five boreholes and additional data from the entire length of two open boreholes in connection with hydraulic tests. These data, together with data from a total of 18 early boreholes in the present SFR tunnel system, were used in the interpretation work. The main part of the data consisted of basic groundwater analyses including major ions and isotopes. Some sporadic gas, microbe and measured redox data are available, but these are either not treated in this report, or are only briefly discussed. This was due to time constraints since special care is needed when interpreting few data of varying quality. The groundwaters in the SFR dataset cover a maximum depth down to about .400 masl and represent a relatively limited salinity range (1,500 to 5,500 mg/L chloride). However, the delta18O values show a wide variation (-1.55 to -0.75% V-SMOW) similar to that reported from the Forsmark site investigations. At the SFR, marine indicators such as Mg/Cl, K/Cl and Br/Cl also show relatively large variations considering the limited salinity range. From very few measured Eh values, and

  16. Preliminary Hydrogeochemical Site Description SFR (version 0.2)

    Nilsson, Ann-Chatrin; Tullborg, Eva-Lena; Smellie, John

    2010-05-01

    The final repository for low and intermediate level radioactive operational waste, SFR, located about 150 km north of Stockholm, is to undergo a future extension. The present on-going project, scheduled from 2007 to 2011, is to define and characterise a suitable bedrock volume for the extended repository. This will include the drilling and geoscientific evaluation of seven core-drilled and four percussion boreholes as well as subsequent interpretation and modelling based on the obtained results in order to provide the necessary information for safety assessment and repository design. This report presents a preliminary hydrogeochemical site description for the SFR site and should be considered as an early progress report rather than a complete hydrochemical site descriptive model. The completed hydrogeochemical field investigations have yielded chemical data from a total of 12 borehole sections in five boreholes and additional data from the entire length of two open boreholes in connection with hydraulic tests. These data, together with data from a total of 18 early boreholes in the present SFR tunnel system, were used in the interpretation work. The main part of the data consisted of basic groundwater analyses including major ions and isotopes. Some sporadic gas, microbe and measured redox data are available, but these are either not treated in this report, or are only briefly discussed. This was due to time constraints since special care is needed when interpreting few data of varying quality. The groundwaters in the SFR dataset cover a maximum depth down to about .400 masl and represent a relatively limited salinity range (1,500 to 5,500 mg/L chloride). However, the δ 18 O values show a wide variation (-1.55 to -0.75% V-SMOW) similar to that reported from the Forsmark site investigations. At the SFR, marine indicators such as Mg/Cl, K/Cl and Br/Cl also show relatively large variations considering the limited salinity range. From very few measured Eh values, and

  17. Long-term safety for the final repository for spent nuclear fuel at Forsmark. Main report of the SR-Site project

    2011-03-15

    The central conclusion of the safety assessment SR-Site is that a KBS-3 repository that fulfils long-term safety requirements can be built at the Forsmark site. This conclusion is reached because the favourable properties of the Forsmark site ensure the required long-term durability of the barriers of the KBS-3 repository. In particular, the copper canisters with their cast iron inserts have been demonstrated to provide a sufficient resistance to the mechanical and chemical loads to which they may be subjected in the repository environment. The conclusion is underpinned by: - The reliance of the KBS-3 repository on i) a geological environment that exhibits long-term stability with respect to properties of importance for long-term safety, i.e. mechanical stability, low groundwater flow rates at repository depth and the absence of high concentrations of detrimental components in the groundwater, and ii) the choice of naturally occurring materials (copper and bentonite clay) for the engineered barriers that are sufficiently durable in the repository environment to provide the barrier longevity required for safety. - The understanding, through decades of research at SKB and in international collaboration, of the phenomena that affect long-term safety, resulting in a mature knowledge base for the safety assessment. - The understanding of the characteristics of the site through several years of surface-based investigations of the conditions at depth and of scientific interpretation of the data emerging from the investigations, resulting in a mature model of the site, adequate for use in the safety assessment. - The detailed specifications of the engineered parts of the repository and the demonstration of how components fulfilling the specifications are to be produced in a quality assured manner, thereby providing a quality assured initial state for the safety assessment. The detailed analyses demonstrate that canister failures in a one million year perspective are rare

  18. Long-term safety for the final repository for spent nuclear fuel at Forsmark. Main report of the SR-Site project

    2011-03-01

    The central conclusion of the safety assessment SR-Site is that a KBS-3 repository that fulfils long-term safety requirements can be built at the Forsmark site. This conclusion is reached because the favourable properties of the Forsmark site ensure the required long-term durability of the barriers of the KBS-3 repository. In particular, the copper canisters with their cast iron inserts have been demonstrated to provide a sufficient resistance to the mechanical and chemical loads to which they may be subjected in the repository environment. The conclusion is underpinned by: - The reliance of the KBS-3 repository on i) a geological environment that exhibits long-term stability with respect to properties of importance for long-term safety, i.e. mechanical stability, low groundwater flow rates at repository depth and the absence of high concentrations of detrimental components in the groundwater, and ii) the choice of naturally occurring materials (copper and bentonite clay) for the engineered barriers that are sufficiently durable in the repository environment to provide the barrier longevity required for safety. - The understanding, through decades of research at SKB and in international collaboration, of the phenomena that affect long-term safety, resulting in a mature knowledge base for the safety assessment. - The understanding of the characteristics of the site through several years of surface-based investigations of the conditions at depth and of scientific interpretation of the data emerging from the investigations, resulting in a mature model of the site, adequate for use in the safety assessment. - The detailed specifications of the engineered parts of the repository and the demonstration of how components fulfilling the specifications are to be produced in a quality assured manner, thereby providing a quality assured initial state for the safety assessment. The detailed analyses demonstrate that canister failures in a one million year perspective are rare

  19. Monitoring Forsmark. Meteorological monitoring at Forsmark, January-December 2010

    Andersson, Cari; Jones, Joergen (Swedish Meteorological and Hydrological Institute (SMHI), Norrkoeping (Sweden))

    2011-01-15

    In the Forsmark area, SKB's meteorological monitoring started in 2003 at the sites Storskaeret and Hoegmasten. However, since July 1, 2007 measurements are only performed at Hoegmasten. Measured and calculated parameters at Hoegmasten are precipitation and corrected precipitation, air temperature, barometric pressure, wind speed and direction, air humidity, global radiation and potential evapotranspiration. The Swedish Meteorological and Hydrological Institute, SMHI, has been responsible for planning and design, as well as for the operation of the stations used for meteorological monitoring. In general, the quality of the meteorological measurements during the period concerned, starting January 1, 2010, and ending December 31, 2010, has shown to be good

  20. Rock-block characterization on regional to local scales for two SKB sites in Forsmark - Uppland and Laxemar - eastern Smaaland, south-eastern Sweden

    Beckholmen, Monica; Tiren, Sven A.

    2010-11-01

    Digital elevation data in 500m, 50m and 10m grids were used for rock-block interpretations at regional, semi-regional and local scales of areas around the two SKB sites, Forsmark and Laxemar, objects for the site-investigation programme. Both areas are interpreted to be close to the surface of the sub- Cambrian peneplain and varying altitude and attitude may testify to blockfaulting in the distorted peneplain. Topographic breaks and changes in the gradient also reveal possible zones of weakness that may conduct water. Rock blocks were constructed for Uppland at 1:750 000, northern Uppland at 1:450 000 and the local Forsmark area at 1:150 000, three sets were constructed for eastern Smaaland at 1:500 000, and one for the semi-regional area at 1:250 000 and one for the local Laxemar area at 1:75 000. The orientation of rock-block boundaries and the size of the rock blocks were treated statistically. The rock blocks/polygons were analysed for their mean, minimum and maximum elevation and the range. The values were displayed by maps. The topography in especially eastern Smaaland is dominated by a clear gradient, the land rising from the sea in the east. Efforts were therefore made to remove an estimated gradient to assess the residual features and the same analyses were then made for mean, maximum, minimum and range values. In many cases the results were enhanced and the two types of presentations are complementary to each other. The rock-block interpretations were compared to bedrock and general correlation between major structures where identified. However, the distribution of rocks on a regional map often demonstrates the plastic deformation in a wider zone. Earthquake epicentres were combined with the rock-block maps and assuming that interpreted rock-block boundaries are fairly steep, there is good agreement between the location of epicentres and rock-block boundaries. In some cases it can be seen how seismic disturbance migrated along a structure. Many

  1. Rock-block characterization on regional to local scales for two SKB sites in Forsmark - Uppland and Laxemar - eastern Smaaland, south-eastern Sweden

    Beckholmen, Monica; Tiren, Sven A. (GEOSIGMA AB (Sweden))

    2010-11-15

    Digital elevation data in 500m, 50m and 10m grids were used for rock-block interpretations at regional, semi-regional and local scales of areas around the two SKB sites, Forsmark and Laxemar, objects for the site-investigation programme. Both areas are interpreted to be close to the surface of the sub- Cambrian peneplain and varying altitude and attitude may testify to blockfaulting in the distorted peneplain. Topographic breaks and changes in the gradient also reveal possible zones of weakness that may conduct water. Rock blocks were constructed for Uppland at 1:750 000, northern Uppland at 1:450 000 and the local Forsmark area at 1:150 000, three sets were constructed for eastern Smaaland at 1:500 000, and one for the semi-regional area at 1:250 000 and one for the local Laxemar area at 1:75 000. The orientation of rock-block boundaries and the size of the rock blocks were treated statistically. The rock blocks/polygons were analysed for their mean, minimum and maximum elevation and the range. The values were displayed by maps. The topography in especially eastern Smaaland is dominated by a clear gradient, the land rising from the sea in the east. Efforts were therefore made to remove an estimated gradient to assess the residual features and the same analyses were then made for mean, maximum, minimum and range values. In many cases the results were enhanced and the two types of presentations are complementary to each other. The rock-block interpretations were compared to bedrock and general correlation between major structures where identified. However, the distribution of rocks on a regional map often demonstrates the plastic deformation in a wider zone. Earthquake epicentres were combined with the rock-block maps and assuming that interpreted rock-block boundaries are fairly steep, there is good agreement between the location of epicentres and rock-block boundaries. In some cases it can be seen how seismic disturbance migrated along a structure. Many

  2. Preliminary Site Characterization Report, Rulsion Site, Colorado

    NONE

    1996-08-01

    This report is a summary of environmental information gathered during a review of the documents pertaining to Project Rulison and interviews with personnel who worked on the project. Project Rulison was part of Operation Plowshare (a program designed to explore peaceful uses for nuclear devices). The project consisted of detonating a 43-kiloton nuclear device on September 10, 1969, in western Colorado to stimulate natural gas production. Following the detonation, a reentry well was drilled and several gas production tests were conducted. The reentry well was shut-in after the last gas production test and was held in standby condition until the general cleanup was undertaken in 1972. A final cleanup was conducted after the emplacement and testing wells were plugged in 1976. However, some surface radiologic contamination resulted from decontamination of the drilling equipment and fallout from the gas flaring during drilling operations. With the exception of the drilling effluent pond, all surface contamination at the Rulison Site was removed during the cleanup operations. All mudpits and other excavations were backfilled, and both upper and lower drilling pads were leveled and dressed. This report provides information regarding known or suspected areas of contamination, previous cleanup activities, analytical results, a review of the regulatory status, the site`s physical environment, and future recommendations for Project Ruhson. Based on this research, several potential areas of contamination have been identified. These include the drilling effluent pond and mudpits used during drilling operations. In addition, contamination could migrate in the gas horizon.

  3. THM-issues in repository rock. Thermal, mechanical, thermo-mechanical and hydro-mechanical evolution of the rock at the Forsmark and Laxemar sites

    Hoekmark, Harald; Loennqvist, Margareta; Faelth, Billy (Clay Technology AB, Lund (Sweden))

    2010-05-15

    The present report addresses aspects of the Thermo-Hydro-Mechanical (THM) evolution of the repository host rock that are of potential importance to the SR-Site safety assessment of a KBS-3 type spent nuclear fuel repository. The report covers the evolution of rock temperatures, rock stresses, pore pressures and fracture transmissivities during the excavation and operational phase, the temperate phase and a glacial cycle on different scales. The glacial cycle is assumed to include a period of pre-glacial permafrost with lowered temperatures and with increased pore pressures in the rock beneath the impermeable permafrost layer. The report also addresses the question of the peak temperature reached during the early temperate phase in the bentonite buffer surrounding the spent fuel canisters. The main text is devoted exclusively to the projected THM evolution of the rock at the Forsmark site in central Sweden. The focus is on the potential for stress-induced failures, i.e. spalling, in the walls of the deposition holes and on changes in the transmissivity of fractures and deformation zones. All analyses are conducted by a combination of numerical tools (3DEC) and analytical solutions. All phases are treated separately and independently of each other, although in reality construction will overlap with heat generation because of the step-by-step excavation/deposition approach with some 50 years between deposition of the first and last canisters. It is demonstrated here that the thermal and thermo-mechanical evolution of the near-field will be independent of heat generated by canisters that were deposited in the past, provided that deposition is made in an orderly fashion, deposition area by deposition area. Peak temperatures and near-field stresses can, consequently, be calculated as if all canisters were deposited simultaneously. The canister and tunnel spacing is specified such that the peak buffer temperature will not exceed 100 deg C in any deposition hole, i.e. not

  4. Preliminary site characterization - final report

    Clark, D.; Smith, L.B.

    1993-12-01

    This report summarizes the ecological unit reconnaissance conducted at the F-Area Burning/Rubble Pit(s) RCRA/CERCLA Unit (F-Area BRP) on August 30 and 31, 1993 as part of the RFI/RI baseline risk assessment for the waste unit The baseline risk assessment will assess the potential endangerment to human health and the environment associated with the unit and will be used to evaluate remediation criteria, if needed. The information presented in this report will be used in subsequent stages of the ecological risk assessment to refine the conceptual site model, assist in the selection of contaminants of concern, identify potential ecological receptors, and evaluate trophic relationships and other exposure pathways. The unit reconnaissance survey was conducted in accordance with Specification No. E-18272, Rev. 1 dated August 5, 1993, and the Draft {open_quotes}Ecological Risk Assessment Program Plan for Evaluation of Waste Sites on the Savannah River Site{close_quotes}. The objectives of the site reconnaissance were to: Assess the general characteristics of on-unit biological communities including mammals, birds, reptiles, amphibians, and any aquatic communities present. Determine the location, extent, and characteristics of on-unit ecological resources, such as forested areas and wetlands, that could serve as important wildlife habitat or provide other ecological functions. Identify any overt effects of contamination on biological communities. The field investigations included mapping and describing all wetland and terrestrial habitats; recording wildlife observations of birds, mammals, and reptiles; and investigating ecological resources in nearby downgradient and downstream areas which could be affected by mobile contaminants or future remedial actions. In preparation for the field investigation, existing unit information including aerial photographs and reports were reviewed to help identify and describe ecological resources at the waste unit.

  5. Preliminary site characterization - final report

    Clark, D.; Smith, L.B.

    1993-12-01

    This report summarizes the ecological unit reconnaissance conducted at the F-Area Burning/Rubble Pit(s) RCRA/CERCLA Unit (F-Area BRP) on August 30 and 31, 1993 as part of the RFI/RI baseline risk assessment for the waste unit The baseline risk assessment will assess the potential endangerment to human health and the environment associated with the unit and will be used to evaluate remediation criteria, if needed. The information presented in this report will be used in subsequent stages of the ecological risk assessment to refine the conceptual site model, assist in the selection of contaminants of concern, identify potential ecological receptors, and evaluate trophic relationships and other exposure pathways. The unit reconnaissance survey was conducted in accordance with Specification No. E-18272, Rev. 1 dated August 5, 1993, and the Draft open-quotes Ecological Risk Assessment Program Plan for Evaluation of Waste Sites on the Savannah River Siteclose quotes. The objectives of the site reconnaissance were to: Assess the general characteristics of on-unit biological communities including mammals, birds, reptiles, amphibians, and any aquatic communities present. Determine the location, extent, and characteristics of on-unit ecological resources, such as forested areas and wetlands, that could serve as important wildlife habitat or provide other ecological functions. Identify any overt effects of contamination on biological communities. The field investigations included mapping and describing all wetland and terrestrial habitats; recording wildlife observations of birds, mammals, and reptiles; and investigating ecological resources in nearby downgradient and downstream areas which could be affected by mobile contaminants or future remedial actions. In preparation for the field investigation, existing unit information including aerial photographs and reports were reviewed to help identify and describe ecological resources at the waste unit

  6. Forsmark site investigation. Assessment of the validity of the rock domain model, version 1.2, based on the modelling of gravity and petrophysical data

    Isaksson, Hans; Stephens, Michael B.

    2007-11-01

    This document reports the results gained by the geophysical modelling of rock domains based on gravity and petrophysical data, which is one of the activities performed within the site investigation work at Forsmark. The main objective with this activity is to assess the validity of the geological rock domain model version 1.2, and to identify discrepancies in the model that may indicate a need for revision of the model or a need for additional investigations. The verification is carried out by comparing the calculated gravity model response, which takes account of the geological model, with a local gravity anomaly that represents the measured data. The model response is obtained from the three-dimensional geometry and the petrophysical data provided for each rock domain in the geological model. Due to model boundary conditions, the study is carried out in a smaller area within the regional model area. Gravity model responses are calculated in three stages; an initial model, a base model and a refined base model. The refined base model is preferred and is used for comparison purposes. In general, there is a good agreement between the refined base model that makes use of the rock domain model, version 1.2 and the measured gravity data, not least where it concerns the depth extension of the critical rock domain RFM029. The most significant discrepancy occurs in the area extending from the SFR office to the SFR underground facility and further to the northwest. It is speculated that this discrepancy is caused by a combination of an overestimation of the volume of gabbro (RFM016) that plunges towards the southeast in the rock domain model, and an underestimation of the volume of occurrence of pegmatite and pegmatitic granite that are known to be present and occur as larger bodies around SFR. Other discrepancies are noted in rock domain RFM022, which is considered to be overestimated in the rock domain model, version 1.2, and in rock domain RFM017, where the gravity

  7. Present status and an appreciation of the consequences for recreation and outdoor leisure activities from siting a nuclear waste repository at Forsmark

    Ottosson, Pia

    2007-07-01

    This report describes how the area around Forsmark is used with respect to recreation and outdoor life. It also describes the impact of the final repository on recreation and outdoor life if it is located in Forsmark. The studied area is situated in the parish of Forsmark in the municipality of Oesthammar. Forsmark nuclear power plant and the final repository for radioactive operational waste, SFR, are situated within the area and there are both houses and holiday houses. The area is used for leisure pursuit by inhabitants and employees at FKA and SKB, but also by a number of different associations and by tourists. Statistical data shows that the parish of Forsmark is sparsely populated. The area was previously dominated by one big landowner and the land surrounding the nuclear power plant was inaccessible to the general public during that period. The outdoor life is therefore less widespread here than along other parts of the east coast. The value of the area does not lie in paths and trails, bike tracks and bathing places, but in the unspoiled countryside, the wildlife and the bird life. Recreation such as hunting and fishing is very popular in the area. The construction of a final repository will increase traffic and hence increase noise and motion in the area. This will mainly impact the enjoyment value for the people spending time in the area. No other significant consequences are expected as the final repository will be mainly situated within the existing industrial complex and hence the character of the area should remain unchanged

  8. Hydrochemical patterns of a small lake and a stream in an uplifting area proposed as a repository site for spent nuclear fuel, Forsmark, Sweden

    Rönnback, Pernilla; Åström, Mats

    2007-10-01

    SummaryThe overall aim of this study was to increase the understanding of the chemical dynamics of small catchments. The focus was on a small oligotropic lake and its major inflow stream in an uplifting area in eastern Sweden (Forsmark) proposed as a repository site for spent nuclear fuel. The hydrochemical sampling campaign lasted for nearly 4 years with sample collection monthly to semi-monthly, and continuous flow measurements carried out over the last 20 months. All this was done as part of the Swedish Nuclear Fuel and Waste Management Company's (SKBs) Site Investigation Programme. The major findings were: (1) as a result of the calcareous overburden caused by redistributed Paleozoic deposits, pH and the Ca and HCO3- concentrations were relatively high in both the stream and lake throughout the period, (2) limnic primary production resulted in decreased concentrations of Ca, HCO3-, NH4+, NO3- and Si, and increased pH and concentrations of chlorophyll a, O 2, DON, POC, PON and POP in the lake in summer, while in other seasons (in winter in particular) when the production was minimal or non-existent the concentrations in the lake and the inflow stream were similar, (3) intrusion of brackish-water resulted in moderately to strongly increased concentrations of Cl -, Na, Mg, Br -, SO42-, K and Sr in the lake: the ratio versus Cl - were for Na and Br - always similar to those in sea water, for Mg and SO42- similar to those in sea water at elevated Cl - concentrations (>3 mM), while K and Sr always occurred in relative excess as compared to sea water, (4) high U concentrations in both the stream and the lake was derived most likely from reduced U-minerals in the overburden and was predicted to be carried to >90% in the form of calcium uranyl carbonate, in a model in which colloidal Fe and Al oxyhydroxides were not considered, (5) the rare earth elements (REEs) had similar concentrations and fractionation patterns in the stream and lake, unlike those found in the

  9. Monitoring Forsmark-Bird monitoring in Forsmark 2012

    Green, Martin

    2013-03-01

    This report summarizes the monitoring of selected listed (Swedish Red List and/or the EU Birds directive) breeding birds in Forsmark 2002 - 2012. Monitoring of eleven listed species was conducted in the regional model area, including the candidate area in 2012 in the same way as in earlier years. The results from 2012 generally follow patterns recorded in earlier years. 2012 was in general a better bird year compared to 2010 and 2011 and most species (82%) showed increasing or stable numbers from 2011 to 2012. Only two species (18%) decreased in numbers between the last two years. All in all, six species (55 %, black-throated diver, honey buzzard, black grouse, ural owl, wryneck and red-backed shrike) show no significant trends since the start of the bird monitoring (2002/2003/2004 depending on species). During this period three species (27 %, white-tailed eagle, osprey and lesser spotted woodpecker) have increased in numbers while just two (18 %, capercaillie and hazelhen) have decreased. A new pair of black-throated divers was discovered in 2012 and seven resident pairs were registered. Breeding success was very good, the second best during the study period. Population development follows the national pattern, but breeding success seems to be better in Forsmark than in the country as a whole. Honey buzzards and ospreys occurred in good numbers, and breeding success for ospreys was good. No signs of successful breedings of honey buzzards were recorded, but this may mean little as no detailed monitoring of breeding success is made for this species. The white-tailed eagles had their best breeding year since the start of the SKB bird monitoring, meaning that during the last two years local breeding success has been back at the level recorded before the site investigations started. The three grouse species (black grouse, capercaillie and hazelhen) again showed somewhat varying patterns between the last two years as well as in the long run. The black grouse increased

  10. Monitoring Forsmark. Bird monitoring in Forsmark 2010

    Green, Martin (Dept. of Animal Ecology, Lund Univ. (Sweden))

    2010-12-15

    This report summarizes the monitoring of selected listed (Swedish Red List and/or the EU Birds Directive) breeding birds in Forsmark 2002-2010. Monitoring of eleven listed species was conducted in the regional model area, including the candidate area in 2010 in the same way as in earlier years. The results from the monitoring in 2010 differed somewhat from results gathered in earlier years. Most monitored species have increased in local numbers during the study years, and from most years continued increases have been reported. Between 2009 and 2010 most species (seven, 64% of the monitored ones) instead decreased in numbers. Only one species (honey buzzard) increased in numbers between the years and in this case this was probably more a result of small moves by certain pairs so that they this year had parts reaching into the regional model area, while in 2009 their territories were outside of this. No dramatic changes in bird numbers were however recorded and all the studied species show stable or increasing local populations over the study period. Number of Black-throated diver pairs was normal and breeding success was good this year. The breeding success of divers has improved considerably over the studied period and the patterns recorded in Forsmark closely follow recorded patterns at the national level. Honey buzzards and ospreys occurred in good numbers, above the average for the whole period, and breeding success was better than in 2009. Even if breeding success of honey buzzards is not monitored in any detail, there were still signs of at least a few successful breedings in the area this year. Breeding success of ospreys was below average, but still within the normal variation for most years. The local white-tailed eagles had a poor breeding season and no young at all were produced within the study area. All three grouse species (black grouse, capercaillie and hazelhen) decreased in numbers between 2009 and 2010. Note however that the large amounts of snow

  11. Monitoring Forsmark. Bird monitoring in Forsmark 2010

    Green, Martin

    2010-12-01

    This report summarizes the monitoring of selected listed (Swedish Red List and/or the EU Birds Directive) breeding birds in Forsmark 2002-2010. Monitoring of eleven listed species was conducted in the regional model area, including the candidate area in 2010 in the same way as in earlier years. The results from the monitoring in 2010 differed somewhat from results gathered in earlier years. Most monitored species have increased in local numbers during the study years, and from most years continued increases have been reported. Between 2009 and 2010 most species (seven, 64% of the monitored ones) instead decreased in numbers. Only one species (honey buzzard) increased in numbers between the years and in this case this was probably more a result of small moves by certain pairs so that they this year had parts reaching into the regional model area, while in 2009 their territories were outside of this. No dramatic changes in bird numbers were however recorded and all the studied species show stable or increasing local populations over the study period. Number of Black-throated diver pairs was normal and breeding success was good this year. The breeding success of divers has improved considerably over the studied period and the patterns recorded in Forsmark closely follow recorded patterns at the national level. Honey buzzards and ospreys occurred in good numbers, above the average for the whole period, and breeding success was better than in 2009. Even if breeding success of honey buzzards is not monitored in any detail, there were still signs of at least a few successful breedings in the area this year. Breeding success of ospreys was below average, but still within the normal variation for most years. The local white-tailed eagles had a poor breeding season and no young at all were produced within the study area. All three grouse species (black grouse, capercaillie and hazelhen) decreased in numbers between 2009 and 2010. Note however that the large amounts of snow

  12. Preliminary safety analysis of the Gorleben site

    Bracke, G.; Fischer-Appelt, K.

    2014-01-01

    The safety requirements governing the final disposal of heat-generating radioactive waste in Germany were implemented by the Federal Ministry of Environment, Natural Conservation and Nuclear Safety (BMU) in 2010. The Ministry considers as a fundamental objective the protection of man and the environment against the hazards of radioactive waste. Unreasonable burdens and obligation for future generations shall be avoided. The main safety principles are concentration and inclusion of radioactive and other pollutants in a containment-providing rock zone. Any release of radioactive nuclides may increase the risk for men and the environment only negligibly compared to natural radiation exposure. No intervention or maintenance work shall be necessary in the post-closure phase. Retrieval/recovery of the waste shall be possible up to 500 years after closure. The Gorleben salt dome has been discussed since the 1970's as a possible repository site for heat-generating radioactive waste in Germany. The objective of the project preliminary safety analysis of the Gorleben site (VSG) was to assess if repository concepts at the Gorleben site or other sites with a comparable geology could comply with these requirements based on currently available knowledge (Fischer-Appelt, 2013; Bracke, 2013). In addition to this it was assessed if methodological approaches can be used for a future site selection procedure and which technological and conceptual considerations can be transferred to other geological situations. The objective included the compilation and review of the available exploration data of the Gorleben site and on disposal in salt rock, the development of repository designs, and the identification of the needs for future R and D work and further site investigations. (authors)

  13. Work at Forsmark since ASSET 1996

    Loewenhielm, G; Andersson, O [Forsmark Kraftgrupp AB, Oesthammar (Sweden)

    1997-10-01

    The following directions of work at Forsmark since ASSET 1996 are briefly described: peer review follow-up; work related to peer review, Forsmark 2 mini-ASSET; MTO(man-technology-organization)-analysis method, concept development, combination of MTO and ASSET methods; Forsmark INES manual.

  14. Organizational development at Forsmark NPP

    Metzen, H.

    2001-01-01

    Forsmark is a three unit BWR site with a total capacity of 3200 MW. Units 1 and two are identical and went into commercial operation in 1980 and 1981. Unit 3 is of a later design with an output of 1200 MW and has been operating since 1985. The average availability for the site has been over 90% for the last 10 years, and the total busbar cost has been competitive. A consistent management strategy has been used to achieve the good results. Several organizational modifications have been made during the years to adapt the organization to changing internal and external conditions. An overall goal regarding staffing has been to keep the number of employees at the same level as in 1985 when Unit 3 went into commercial operation. During the time period from 1975, when the operational organization was formed, until today, the focus for the organization has changed several times. During the commissioning period the focus was on training and establishing routines and procedures. During the first years of operation development of maintenance programs and taking over activities from the supplier dominated. Next area in focus was increasing availability and making the outages more efficient. Several minor modifications to the plant were made to support maintenance activities. More focus on cost reduction and increasing the production through technical modifications were next. After 15 years of operation the need for replacement of components to ensure reliable operation was evident. A program for major modifications was developed, aiming at 40 years lifetime. Deregulation of the Nordic Electricity Market now calls for further reductions in production costs. (author)

  15. Geology - Background complementary studies. Forsmark modelling stage 2.2

    Stephens, Michael B. [Geological Survey of Sweden, Uppsala (Sweden); Skagius, Kristina [Kemakta Konsult AB, Stockholm (Sweden)] (eds.)

    2007-09-15

    During Forsmark model stage 2.2, seven complementary geophysical and geological studies were initiated by the geological modelling team, in direct connection with and as a background support to the deterministic modelling of deformation zones. One of these studies involved a field control on the character of two low magnetic lineaments with NNE and NE trends inside the target volume. The interpretation of these lineaments formed one of the late deliveries to SKB that took place after the data freeze for model stage 2.2 and during the initial stage of the modelling work. Six studies involved a revised processing and analysis of reflection seismic, refraction seismic and selected oriented borehole radar data, all of which had been presented earlier in connection with the site investigation programme. A prime aim of all these studies was to provide a better understanding of the geological significance of indirect geophysical data to the geological modelling team. Such essential interpretative work was lacking in the material acquired in connection with the site investigation programme. The results of these background complementary studies are published together in this report. The titles and authors of the seven background complementary studies are presented below. Summaries of the results of each study, with a focus on the implications for the geological modelling of deformation zones, are presented in the master geological report, SKB-R--07-45. The sections in the master report, where reference is made to each background complementary study and where the summaries are placed, are also provided. The individual reports are listed in the order that they are referred to in the master geological report and as they appear in this report. 1. Scan line fracture mapping and magnetic susceptibility measurements across two low magnetic lineaments with NNE and NE trend, Forsmark. Jesper Petersson, Ulf B. Andersson and Johan Berglund. 2. Integrated interpretation of surface and

  16. Geology - Background complementary studies. Forsmark modelling stage 2.2

    Stephens, Michael B.; Skagius, Kristina

    2007-09-01

    During Forsmark model stage 2.2, seven complementary geophysical and geological studies were initiated by the geological modelling team, in direct connection with and as a background support to the deterministic modelling of deformation zones. One of these studies involved a field control on the character of two low magnetic lineaments with NNE and NE trends inside the target volume. The interpretation of these lineaments formed one of the late deliveries to SKB that took place after the data freeze for model stage 2.2 and during the initial stage of the modelling work. Six studies involved a revised processing and analysis of reflection seismic, refraction seismic and selected oriented borehole radar data, all of which had been presented earlier in connection with the site investigation programme. A prime aim of all these studies was to provide a better understanding of the geological significance of indirect geophysical data to the geological modelling team. Such essential interpretative work was lacking in the material acquired in connection with the site investigation programme. The results of these background complementary studies are published together in this report. The titles and authors of the seven background complementary studies are presented below. Summaries of the results of each study, with a focus on the implications for the geological modelling of deformation zones, are presented in the master geological report, SKB-R--07-45. The sections in the master report, where reference is made to each background complementary study and where the summaries are placed, are also provided. The individual reports are listed in the order that they are referred to in the master geological report and as they appear in this report. 1. Scan line fracture mapping and magnetic susceptibility measurements across two low magnetic lineaments with NNE and NE trend, Forsmark. Jesper Petersson, Ulf B. Andersson and Johan Berglund. 2. Integrated interpretation of surface and

  17. Bioturbation in different ecosystems at Forsmark and Oskarshamn

    Persson, Tryggve; Lenoir, Lisette; Taylor, Astrid [Dept. of Ecology and Environmental Research, Swedish University or Agricultural Sciences, Uppsala (Sweden)

    2007-01-15

    The Swedish Nuclear Fuel and Waste Management Co (SKB) carries out extensive investigations on factors that can affect long-term storage of nuclear waste. Earthworms consume organic soil materials and when doing so they transport and mix mineral soil particles as well as litter and humus materials. Ants do not consume soil materials, but they collect and mix mineral soil particles and litter materials to construct their nests. This process of material displacement by earthworms and ants is called bioturbation and can be a mechanism for the redistribution (vertical and horizontal) of radionuclides within the soil profile. The aim of the present study was to determine the quantitative impact of earthworms and ants on bioturbation of soil in different ecosystems at Forsmark and Oskarshamn. Earthworms were sampled at four 20x20 cm{sup 2} sub-plots at each site and were determined, dried and weighed in the laboratory. Gut passage time and faeces production were determined in a laboratory experiment at constant temperature. Temperature dependence of earthworm growth was studied at 3, 6, 10 and 20 deg C, and it was assumed that defecation mirrored growth as regards temperature dependence. Ant species composition, ant nest density and nest volume were investigated in the field by using pitfall traps and a transect method to enumerate ant nests. Dry weights of ant nests were determined after weighing in the laboratory. Earthworm abundances and biomasses were high in moist/wet alder forests and deciduous woodlands and low in pine and pine/spruce forests at both Forsmark and Oskarshamn. In mesic spruce forests, high estimates of abundance/biomass of earthworms were found at Forsmark but low at Oskarshamn, whereas grazed pastures had high estimates at Oskarshamn and ungrazed abandoned fields had relatively low estimates at Forsmark. High pH at Forsmark and low pH at Oskarshamn as well as high groundwater tables at some of the Forsmark sites can explain the difference between

  18. Bioturbation in different ecosystems at Forsmark and Oskarshamn

    Persson, Tryggve; Lenoir, Lisette; Taylor, Astrid

    2007-01-01

    The Swedish Nuclear Fuel and Waste Management Co (SKB) carries out extensive investigations on factors that can affect long-term storage of nuclear waste. Earthworms consume organic soil materials and when doing so they transport and mix mineral soil particles as well as litter and humus materials. Ants do not consume soil materials, but they collect and mix mineral soil particles and litter materials to construct their nests. This process of material displacement by earthworms and ants is called bioturbation and can be a mechanism for the redistribution (vertical and horizontal) of radionuclides within the soil profile. The aim of the present study was to determine the quantitative impact of earthworms and ants on bioturbation of soil in different ecosystems at Forsmark and Oskarshamn. Earthworms were sampled at four 20x20 cm 2 sub-plots at each site and were determined, dried and weighed in the laboratory. Gut passage time and faeces production were determined in a laboratory experiment at constant temperature. Temperature dependence of earthworm growth was studied at 3, 6, 10 and 20 deg C, and it was assumed that defecation mirrored growth as regards temperature dependence. Ant species composition, ant nest density and nest volume were investigated in the field by using pitfall traps and a transect method to enumerate ant nests. Dry weights of ant nests were determined after weighing in the laboratory. Earthworm abundances and biomasses were high in moist/wet alder forests and deciduous woodlands and low in pine and pine/spruce forests at both Forsmark and Oskarshamn. In mesic spruce forests, high estimates of abundance/biomass of earthworms were found at Forsmark but low at Oskarshamn, whereas grazed pastures had high estimates at Oskarshamn and ungrazed abandoned fields had relatively low estimates at Forsmark. High pH at Forsmark and low pH at Oskarshamn as well as high groundwater tables at some of the Forsmark sites can explain the difference between

  19. Geology Forsmark. Site descriptive modelling Forsmark - stage 2.2

    Stephens, Michael B. [Geological Survey of Sweden, Uppsala (Sweden); Fox, Aaron; La Pointe, Paul [Golder Associates Inc (United States); Simeonov, Assen [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Isaksson, Hans [GeoVista AB, Luleaa (Sweden); Hermanson, Jan; Oehman, Johan [Golder Associates AB, Stockholm (Sweden)

    2007-10-15

    The geological work during stage 2.2 has involved the development of deterministic models for rock domains (RFM) and deformation zones (ZFM), the identification and deterministic modelling of fracture domains (FFM) inside the candidate volume, i.e. the parts of rock domains that are not affected by deformation zones, and the development of statistical models for fractures and minor deformation zones (geological discrete fracture network modelling or geological DFN modelling). The geological DFN model addresses brittle structures at a scale of less than 1 km, which is the lower cut-off in the deterministic modelling of deformation zones. In order to take account of variability in data resolution, deterministic models for rock domains and deformation zones are presented in both regional and local model volumes, while the geological DFN model is valid within specific fracture domains inside the north-western part of the candidate volume, including the target volume. The geological modelling work has evaluated and made use of: A revised bedrock geological map at the ground surface. Geological and geophysical data from 21 cored boreholes and 33 percussion boreholes. Detailed mapping of fractures and rock units along nine excavations or large surface outcrops. Data bearing on the characterisation (including kinematics) of deformation zones. Complementary geochronological and other rock and fracture analytical data. Lineaments identified on the basis of airborne and high-resolution ground magnetic data. A reprocessing of both surface and borehole reflection seismic data. Seismic refraction data. The outputs of the deterministic modelling work are geometric models in RVS format and detailed property tables for rock domains and deformation zones, and a description of fracture domains. The outputs of the geological DFN modelling process are recommended parameters or statistical distributions that describe fracture set orientations, radius sizes, volumetric intensities, spatial correlations and models, and other parameters (lithology and scaling corrections, termination matrices) that are necessary to build stochastic models. Primarily due to the establishment of additional fixed point intersections for rock domain boundaries at depth, adjustments have been made to earlier regional and local rock domain models. These adjustments are only minor in character. Compared with the earlier stage 2.1 model, adjustments in the regional deformation zone model are also, in general, highly limited in character. More important differences, which also affect the local model for deformation zones, concern zones ZFMA2, ZFMF1 and ZFMA8 in the gently dipping set. Significant changes in the modelling of deformation zones also concern the steeply dipping zones with surface trace lengths between 1 and 3 km in the local model volume. A totally revised geological DFN model is presented compared with the latest model (version 1.2). In particular, conceptually distinct alternatives are presented for fracture size modelling.

  20. Geology Forsmark. Site descriptive modelling Forsmark - stage 2.2

    Stephens, Michael B.; Fox, Aaron; La Pointe, Paul; Simeonov, Assen; Isaksson, Hans; Hermanson, Jan; Oehman, Johan

    2007-10-01

    The geological work during stage 2.2 has involved the development of deterministic models for rock domains (RFM) and deformation zones (ZFM), the identification and deterministic modelling of fracture domains (FFM) inside the candidate volume, i.e. the parts of rock domains that are not affected by deformation zones, and the development of statistical models for fractures and minor deformation zones (geological discrete fracture network modelling or geological DFN modelling). The geological DFN model addresses brittle structures at a scale of less than 1 km, which is the lower cut-off in the deterministic modelling of deformation zones. In order to take account of variability in data resolution, deterministic models for rock domains and deformation zones are presented in both regional and local model volumes, while the geological DFN model is valid within specific fracture domains inside the north-western part of the candidate volume, including the target volume. The geological modelling work has evaluated and made use of: A revised bedrock geological map at the ground surface. Geological and geophysical data from 21 cored boreholes and 33 percussion boreholes. Detailed mapping of fractures and rock units along nine excavations or large surface outcrops. Data bearing on the characterisation (including kinematics) of deformation zones. Complementary geochronological and other rock and fracture analytical data. Lineaments identified on the basis of airborne and high-resolution ground magnetic data. A reprocessing of both surface and borehole reflection seismic data. Seismic refraction data. The outputs of the deterministic modelling work are geometric models in RVS format and detailed property tables for rock domains and deformation zones, and a description of fracture domains. The outputs of the geological DFN modelling process are recommended parameters or statistical distributions that describe fracture set orientations, radius sizes, volumetric intensities, spatial correlations and models, and other parameters (lithology and scaling corrections, termination matrices) that are necessary to build stochastic models. Primarily due to the establishment of additional fixed point intersections for rock domain boundaries at depth, adjustments have been made to earlier regional and local rock domain models. These adjustments are only minor in character. Compared with the earlier stage 2.1 model, adjustments in the regional deformation zone model are also, in general, highly limited in character. More important differences, which also affect the local model for deformation zones, concern zones ZFMA2, ZFMF1 and ZFMA8 in the gently dipping set. Significant changes in the modelling of deformation zones also concern the steeply dipping zones with surface trace lengths between 1 and 3 km in the local model volume. A totally revised geological DFN model is presented compared with the latest model (version 1.2). In particular, conceptually distinct alternatives are presented for fracture size modelling

  1. Inventory of mammals at Forsmark and Haallnaes

    Truve, Johan

    2012-08-01

    A selection of terrestrial mammals was surveyed in the SKB site investigation areas near Forsmark and Haallnaes between January and April 2012. The methods that were used include snow tracking along line transects, snow tracking along water, aerial survey and fecal pellet counts. The same species were found in 2012 as in previous surveys performed in 2002, 2003 and 2007. Some species show a large variation in density between years and it is difficult to draw any conclusions about their long term development. Several carnivores, i.e. lynx, fox and otter show a positive growth rate in both areas. The wild boar population is also growing whilst moose density remains fairly stable and roe deer are becoming less numerous

  2. Reactor safety study applied to the Forsmark 3 Power Plant

    Ericsson, G.; Tiren, L.I.

    1978-01-01

    A reactor safety study of the Forsmark 3 BWR power plant has been carried out for the purpose of calculating core melt probabilities using WASH-1400 methods. A sensitivity analysis shows that the calculated core melt probability is changed by approximately a factor of 10 depending on assumptions made with respect to the probability of human error. The importance of the availability of off-site power and the influence of common cause failure is also discussed. (author)

  3. Monitoring Forsmark. Moose age composition, reproduction and antler development in Forsmark; Monitoring Forsmark. Aelgstammens aalderssammansaettning reproduktion och hornutveckling i Forsmark

    Cederlund, Goeran; Broman, Emil (Svensk Naturfoervaltning AB (Sweden))

    2011-05-15

    The moose (Alces alces) is an important game species in Forsmark, as well as in Sweden in general. Hunting on moose is subject to strict local regulations and restrictions within a management program. Such restrictions will have considerable effects on demography. This has led to a moose population in Forsmark with biased sex ratio with fewer adult males than females and a generally low average age. High hunting pressure on males has caused a low survival rate and the chance to survive more than five years is just a few percent. Restrictions in hunting pressure on females have caused a generally higher survival rate and a higher average age compared to males. Sex differences in body mass are normal compared to other populations in southern Sweden. Mean body mass of culled calves is an important measure of quality of the population, since it reflects the available food resources in the management area. Body mass among calves in Forsmark is generally low, indicating a deteriorated food resource due to either ambient population density and/or hampered food production in the forest. The average reproduction rate is normal compared to other populations in this part of Sweden. However, one year old females (yearlings) have a fairly low production of eggs per female (ovulation rate). As the yearlings constitute a considerable part of the population in Forsmark, their lowered ovulation rate will affect the rate of recruitment of calves to the local population. The moose population seems to have been subject to considerable variation in density during the last decade, which is probably a joint effect of changes in demography (hunting), changes in food resources due to forestry management and by food competition from other browsers in the area. Local managers believe that the population has reached such a low level (although not verified by surveys) that the number of moose has to be increased. It is vital to stress the importance of keeping up collection of data from the

  4. Preliminary siting characterization Salt Disposition Facility - Site B

    Wyatt, D.

    2000-01-01

    A siting and reconnaissance geotechnical program has been completed in S-Area at the Savannah River Site in South Carolina. This program investigated the subsurface conditions for the area known as ''Salt Disposition Facility (SDF), Site B'' located northeast of H-Area and within the S-Area. Data acquired from the Site B investigation includes both field exploration and laboratory test data

  5. OSU TOMF Program Site Selection and Preliminary Concept Design Report

    Spadling, Steve [Oklahoma State Univ., Stillwater, OK (United States)

    2012-05-10

    The purpose of this report is to confirm the programmatic requirements for the new facilities, identify the most appropriate project site, and develop preliminary site and building concepts that successfully address the overall project goals and site issues. These new facilities will be designed to accommodate the staff, drivers and maintenance requirements for the future mixed fleet of passenger vehicles, Transit Style Buses and School Buses.

  6. Preliminary environmental site assessments in New York City

    Lundy, P.; Gasson, D.R.; Longendyke, S.T.

    1991-01-01

    Preliminary Environmental Site Assessments are often performed prior to real estate transactions or refinancing. These assessments are typically performed for real estate buyers, sellers and lending institutions. Undertaking a Preliminary Environmental Site Assessment in New York City can often be quite complex and time-consuming. This is due, in part, to the age and density of buildings in the city as well as the myriad of regulatory agencies with jurisdiction over environmental issues. This paper will discuss how environmental assessments are performed with a special emphasis on building in New York City. In includes hazardous wastes management for Radon, PCB's and asbestos

  7. Quantifying in situ stress magnitudes and orientations for Forsmark. Forsmark stage 2.2

    Martin, C. Derek

    2007-11-01

    Stephansson et al. concluded that in the Fennoscandia shield: (1) there is a large horizontal stress component in the uppermost 1,000 m of bedrock, and (2) the maximum and minimum horizontal stresses exceed the vertical stress assuming the vertical stress is estimated from the weight of the overburden. Several stress campaigns involving both overcoring and hydraulic fracturing, including the hydraulic testing of pre-existing fractures (HTPF), have been carried out at Forsmark to establish the in situ stress state. The results from the initial campaigns were summarised by Sjoeberg et al. which formed the bases for the stresses provided in the Site Descriptive Model version 1.2. Since then additional stress measurement campaigns have been completed. The results from these stress measurement campaigns support the conclusions from Stephansson et al. In addition to these in situ stress measurements the following additional studies were undertaken to aid in assessing the stress state at Forsmark. 1. A detailed televiewer survey of approximately 6,900 m of borehole walls to depths of 1,000 m was carried out to assess borehole wall damage, i.e. borehole breakouts. 2. Evaluation of nonlinear strains in laboratory samples to depths of approximately 800 m to assess if stress magnitudes were sufficient to create stress-induced microcracking. 3. Assessment of the magnitudes required to cause core disking and survey of core disking observed at Forsmark. The magnitudes and orientations from the stress measurement campaigns were analysed to establish the most likely stress magnitudes and orientations for Design Step D2 within the Target Area of the Complete Site Investigations. The maximum and minimum horizontal stress components are essentially the same as the maximum and intermediate principal stresses, σ1 and σ2, respectively. The minimum principal stress (σ3) is synonymous with the vertical stress. The most likely range in values to be used in the design is also shown. The

  8. Quantifying in situ stress magnitudes and orientations for Forsmark. Forsmark stage 2.2

    Martin, C. Derek (Univ. of Alberta (Canada))

    2007-11-15

    Stephansson et al. concluded that in the Fennoscandia shield: (1) there is a large horizontal stress component in the uppermost 1,000 m of bedrock, and (2) the maximum and minimum horizontal stresses exceed the vertical stress assuming the vertical stress is estimated from the weight of the overburden. Several stress campaigns involving both overcoring and hydraulic fracturing, including the hydraulic testing of pre-existing fractures (HTPF), have been carried out at Forsmark to establish the in situ stress state. The results from the initial campaigns were summarised by Sjoeberg et al. which formed the bases for the stresses provided in the Site Descriptive Model version 1.2. Since then additional stress measurement campaigns have been completed. The results from these stress measurement campaigns support the conclusions from Stephansson et al. In addition to these in situ stress measurements the following additional studies were undertaken to aid in assessing the stress state at Forsmark. 1. A detailed televiewer survey of approximately 6,900 m of borehole walls to depths of 1,000 m was carried out to assess borehole wall damage, i.e. borehole breakouts. 2. Evaluation of nonlinear strains in laboratory samples to depths of approximately 800 m to assess if stress magnitudes were sufficient to create stress-induced microcracking. 3. Assessment of the magnitudes required to cause core disking and survey of core disking observed at Forsmark. The magnitudes and orientations from the stress measurement campaigns were analysed to establish the most likely stress magnitudes and orientations for Design Step D2 within the Target Area of the Complete Site Investigations. The maximum and minimum horizontal stress components are essentially the same as the maximum and intermediate principal stresses, sigma1 and sigma2, respectively. The minimum principal stress (sigma3) is synonymous with the vertical stress. The most likely range in values to be used in the design is also

  9. Inventory of mammals at Forsmark and Haallnaes; Inventering av daeggdjur i Forsmark och Haallnaes

    Truve, Johan [Svensk Naturfoervaltning AB, Goeteborg (Sweden)

    2012-08-15

    A selection of terrestrial mammals was surveyed in the SKB site investigation areas near Forsmark and Haallnaes between January and April 2012. The methods that were used include snow tracking along line transects, snow tracking along water, aerial survey and fecal pellet counts. The same species were found in 2012 as in previous surveys performed in 2002, 2003 and 2007. Some species show a large variation in density between years and it is difficult to draw any conclusions about their long term development. Several carnivores, i.e. lynx, fox and otter show a positive growth rate in both areas. The wild boar population is also growing whilst moose density remains fairly stable and roe deer are becoming less numerous.

  10. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites

    Maheras, Steven J.; Best, Ralph E.; Ross, Steven B.; Buxton, Kenneth A.; England, Jeffery L.; McConnell, Paul E.

    2013-09-30

    This report fulfills the M2 milestone M2FT-13PN0912022, “Stranded Sites De-Inventorying Report.” In January 2013, the U.S. Department of Energy (DOE) issued the Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste (DOE 2013). Among the elements contained in this strategy is an initial focus on accepting used nuclear fuel from shutdown reactor sites. This focus is consistent with the recommendations of the Blue Ribbon Commission on America’s Nuclear Future, which identified removal of stranded used nuclear fuel at shutdown sites as a priority so that these sites may be completely decommissioned and put to other beneficial uses (BRC 2012). Shutdown sites are defined as those commercial nuclear power reactor sites where the nuclear power reactors have been shut down and the site has been decommissioned or is undergoing decommissioning. In this report, a preliminary evaluation of removing used nuclear fuel from 12 shutdown sites was conducted. The shutdown sites were Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, Zion, Crystal River, Kewaunee, and San Onofre. These sites have no other operating nuclear power reactors at their sites and have also notified the U.S. Nuclear Regulatory Commission that their reactors have permanently ceased power operations and that nuclear fuel has been permanently removed from their reactor vessels. Shutdown reactors at sites having other operating reactors are not included in this evaluation.

  11. Hydrogeological DFN modelling using structural and hydraulic data from KLX04. Preliminary site description Laxemar subarea - version 1.2

    Follin, Sven [SF GeoLogic AB, Taeby (Sweden); Stigsson, Martin [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Svensson, Urban [Computer-aided Fluid Engineering AB, Norrkoeping (Sweden)

    2006-04-15

    SKB is conducting site investigations for a high-level nuclear waste repository in fractured crystalline rocks at two coastal areas in Sweden. The two candidate areas are named Forsmark and Simpevarp. The site characterisation work is divided into two phases, an initial site investigation phase (ISI) and a complete site investigation phase (CSI). The results of the ISI phase are used as a basis for deciding on the subsequent CSI phase. On the basis of the CSI investigations a decision is made as to whether detailed characterisation will be performed (including sinking of a shaft). An integrated component in the site characterisation work is the development of site descriptive models. These comprise basic models in three dimensions with an accompanying text description. Central in the modelling work is the geological model which provides the geometrical context in terms of a model of deformation zones and the less fractured rock mass between the zones. Using the geological and geometrical description models as a basis, descriptive models for other disciplines (surface ecosystems, hydrogeology, hydrogeochemistry, rock mechanics, thermal properties and transport properties) will be developed. Great care is taken to arrive at a general consistency in the description of the various models and assessment of uncertainty and possible needs of alternative models. The main objective of this study is to support the development of a hydrogeological DFN model (Discrete Fracture Network) for the Preliminary Site Description of the Laxemar area on a regional-scale (SDM version L1.2). A more specific objective of this study is to assess the propagation of uncertainties in the geological DFN modelling reported for L1.2 into the groundwater flow modelling. An improved understanding is necessary in order to gain credibility for the Site Description in general and the hydrogeological description in particular. The latter will serve as a basis for describing the present

  12. Hydrogeological DFN modelling using structural and hydraulic data from KLX04. Preliminary site description Laxemar subarea - version 1.2

    Follin, Sven; Stigsson, Martin; Svensson, Urban

    2006-04-01

    SKB is conducting site investigations for a high-level nuclear waste repository in fractured crystalline rocks at two coastal areas in Sweden. The two candidate areas are named Forsmark and Simpevarp. The site characterisation work is divided into two phases, an initial site investigation phase (ISI) and a complete site investigation phase (CSI). The results of the ISI phase are used as a basis for deciding on the subsequent CSI phase. On the basis of the CSI investigations a decision is made as to whether detailed characterisation will be performed (including sinking of a shaft). An integrated component in the site characterisation work is the development of site descriptive models. These comprise basic models in three dimensions with an accompanying text description. Central in the modelling work is the geological model which provides the geometrical context in terms of a model of deformation zones and the less fractured rock mass between the zones. Using the geological and geometrical description models as a basis, descriptive models for other disciplines (surface ecosystems, hydrogeology, hydrogeochemistry, rock mechanics, thermal properties and transport properties) will be developed. Great care is taken to arrive at a general consistency in the description of the various models and assessment of uncertainty and possible needs of alternative models. The main objective of this study is to support the development of a hydrogeological DFN model (Discrete Fracture Network) for the Preliminary Site Description of the Laxemar area on a regional-scale (SDM version L1.2). A more specific objective of this study is to assess the propagation of uncertainties in the geological DFN modelling reported for L1.2 into the groundwater flow modelling. An improved understanding is necessary in order to gain credibility for the Site Description in general and the hydrogeological description in particular. The latter will serve as a basis for describing the present

  13. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites

    Maheras, Steven J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Best, Ralph E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Ross, Steven B. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Buxton, Kenneth A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); England, Jeffery L. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); McConnell, Paul E. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Massaro, Lawrence M. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Jensen, Philip J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2015-09-30

    A preliminary evaluation of removing spent nuclear fuel (SNF) from 13 shutdown nuclear power reactor sites was conducted. At these shutdown sites the nuclear power reactors have been permanently shut down and the sites have been decommissioned or are undergoing decommissioning. The shutdown sites were Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, Zion, Crystal River, Kewaunee, San Onofre, and Vermont Yankee. The evaluation was divided into four components: (1) characterization of the SNF and greater-than-Class C low-level radioactive waste (GTCC waste) inventory, (2) a description of the on-site infrastructure and conditions relevant to transportation of SNF and GTCC waste, (3) an evaluation of the near-site transportation infrastructure and experience relevant to shipping transportation casks containing SNF and GTCC waste, including identification of gaps in information, and (4) an evaluation of the actions necessary to prepare for and remove SNF and GTCC waste. Every site was found to have at least one off-site transportation mode option for removing its SNF and GTCC waste; some have multiple options. Experience removing large components during reactor decommissioning provided an important source of information used to identify the transportation mode options for the sites. Especially important in conducting the evaluation were site visits, through which information was obtained that would not have been available otherwise. Extensive photographs taken during the site visits proved to be particularly useful in documenting the current conditions at or near the sites. It is expected that additional site visits will be conducted to add to the information presented in the evaluation.

  14. Environmental Survey preliminary report, Hanford Site, Richland, Washington

    1987-08-01

    This report presents the preliminary findings from the first phase of the Environmental Survey of the United States Department of Energy (DOE) Hanford Site, conducted August 18 through September 5, 1986. The Survey is being conducted by an interdisciplinary team of environmental specialists, led and managed by the Office of Environment, Safety and Health's Office of Environmental Audit. Individual team components are being supplied by a private contractor. The objective of the Survey is to identify environmental problems and areas of environmental risk associated with the Hanford Site. The Survey covers all environmental media and all areas of environmental regulation. It is being performed in accordance with the DOE Environmental Survey Manual. This phase of the Survey involves the review of existing site environmental data, observations of the operations carried on at the Hanford Site, and interviews with site personnel. The Survey team developed a Sampling and Analysis Plan to assist in further assessing certain of the environmental problems identified during its on-site activities. The Sampling and Analysis Plan will be executed by a DOE National Laboratory or a support contractor. When completed, the results will be incorporated into the Environmental Survey Interim Report for the Hanford Site. The Interim Report will reflect the final determinations of the Hanford Site Survey. 44 refs., 88 figs., 74 tabs.

  15. Environmental Survey preliminary report, Hanford Site, Richland, Washington

    1987-08-01

    This report presents the preliminary findings from the first phase of the Environmental Survey of the United States Department of Energy (DOE) Hanford Site, conducted August 18 through September 5, 1986. The Survey is being conducted by an interdisciplinary team of environmental specialists, led and managed by the Office of Environment, Safety and Health's Office of Environmental Audit. Individual team components are being supplied by a private contractor. The objective of the Survey is to identify environmental problems and areas of environmental risk associated with the Hanford Site. The Survey covers all environmental media and all areas of environmental regulation. It is being performed in accordance with the DOE Environmental Survey Manual. This phase of the Survey involves the review of existing site environmental data, observations of the operations carried on at the Hanford Site, and interviews with site personnel. The Survey team developed a Sampling and Analysis Plan to assist in further assessing certain of the environmental problems identified during its on-site activities. The Sampling and Analysis Plan will be executed by a DOE National Laboratory or a support contractor. When completed, the results will be incorporated into the Environmental Survey Interim Report for the Hanford Site. The Interim Report will reflect the final determinations of the Hanford Site Survey. 44 refs., 88 figs., 74 tabs

  16. Forsmark NPP I and C modernization strategy

    Hallen, J.; Rydahl, I.; Kloow, L.

    2003-01-01

    By the year 2000, the Forsmark NPP was halfway through the planned plant life. As early as 1995, Forsmark realized that the old analog I and C equipment would need to be replaced before 2005. At the Forsmark NPP they had strength of a vision of an integrated modernization and a strategy to reach the vision. Without vision and strategy, the plant could end up with a fragmented plant I and C-architecture that is not cost-effective or operable. This paper will address several questions that led to the current modernization program in Forsmark, the more important questions are: What would happen if the modernization would be postponed? Which main requirements were to be achieved by means of the modernization strategy? The goal of a completed plant modernization program is a totally integrated system solution and what factors were considered during the modernization? How to gain acceptance from the operational staff in designing Control Room and Soft Control Displays? What are the important roles for the staff and organization to reach the end goal? What has been the experience to date and what are the lessons learned? Thanks to the long term co-operation between Forsmark and Westinghouse the modernization has been very successful for both parties. (orig.)

  17. Spatial modelling of marine organisms in Forsmark and Oskarshamn. Including calculation of physical predictor variables

    Carlen, Ida; Nikolopoulos, Anna; Isaeus, Martin (AquaBiota Water Research, Stockholm (SE))

    2007-06-15

    GIS grids (maps) of marine parameters were created using point data from previous site investigations in the Forsmark and Oskarshamn areas. The proportion of global radiation reaching the sea bottom in Forsmark and Oskarshamn was calculated in ArcView, using Secchi depth measurements and the digital elevation models for the respective area. The number of days per year when the incoming light exceeds 5 MJ/m2 at the bottom was then calculated using the result of the previous calculations together with measured global radiation. Existing modelled grid-point data on bottom and pelagic temperature for Forsmark were interpolated to create surface covering grids. Bottom and pelagic temperature grids for Oskarshamn were calculated using point measurements to achieve yearly averages for a few points and then using regressions with existing grids to create new maps. Phytoplankton primary production in Forsmark was calculated using point measurements of chlorophyll and irradiance, and a regression with a modelled grid of Secchi depth. Distribution of biomass of macrophyte communities in Forsmark and Oskarshamn was calculated using spatial modelling in GRASP, based on field data from previous surveys. Physical parameters such as those described above were used as predictor variables. Distribution of biomass of different functional groups of fish in Forsmark was calculated using spatial modelling based on previous surveys and with predictor variables such as physical parameters and results from macrophyte modelling. All results are presented as maps in the report. The quality of the modelled predictions varies as a consequence of the quality and amount of the input data, the ecology and knowledge of the predicted phenomena, and by the modelling technique used. A substantial part of the variation is not described by the models, which should be expected for biological modelling. Therefore, the resulting grids should be used with caution and with this uncertainty kept in mind. All

  18. Spatial modelling of marine organisms in Forsmark and Oskarshamn. Including calculation of physical predictor variables

    Carlen, Ida; Nikolopoulos, Anna; Isaeus, Martin

    2007-06-01

    GIS grids (maps) of marine parameters were created using point data from previous site investigations in the Forsmark and Oskarshamn areas. The proportion of global radiation reaching the sea bottom in Forsmark and Oskarshamn was calculated in ArcView, using Secchi depth measurements and the digital elevation models for the respective area. The number of days per year when the incoming light exceeds 5 MJ/m2 at the bottom was then calculated using the result of the previous calculations together with measured global radiation. Existing modelled grid-point data on bottom and pelagic temperature for Forsmark were interpolated to create surface covering grids. Bottom and pelagic temperature grids for Oskarshamn were calculated using point measurements to achieve yearly averages for a few points and then using regressions with existing grids to create new maps. Phytoplankton primary production in Forsmark was calculated using point measurements of chlorophyll and irradiance, and a regression with a modelled grid of Secchi depth. Distribution of biomass of macrophyte communities in Forsmark and Oskarshamn was calculated using spatial modelling in GRASP, based on field data from previous surveys. Physical parameters such as those described above were used as predictor variables. Distribution of biomass of different functional groups of fish in Forsmark was calculated using spatial modelling based on previous surveys and with predictor variables such as physical parameters and results from macrophyte modelling. All results are presented as maps in the report. The quality of the modelled predictions varies as a consequence of the quality and amount of the input data, the ecology and knowledge of the predicted phenomena, and by the modelling technique used. A substantial part of the variation is not described by the models, which should be expected for biological modelling. Therefore, the resulting grids should be used with caution and with this uncertainty kept in mind. All

  19. Final repository for spent nuclear fuel. Underground design Forsmark, Layout D1

    Brantberger, Martin; Zetterqvist, Anders; Arnbjerg-Nielsen, Torben; Olsson, Tommy; Outters, Nils; Syrjaenen, Pauli

    2006-04-01

    This report comprises the design step D1 related to the underground design for a deep repository located at the Forsmark site. The design is based on the Site Descriptive Model Forsmark v1.2. All studies have been focussed at an area southeast of the Forsmark nuclear plant, which has been considered to be the most promising area for hosting the repository. SKB has developed guidelines for the design of the repository, which further describes the methodology applied for the studies. From these guidelines the following basic objectives for the design step D1 are summarized: to determine whether the final repository can be accommodated within the studied site; to identify site-specific facility critical issues; to test and evaluate the design methodology; to provide feedback to: the design organisation regarding additional studies that needs to be done; the site investigation and modelling organization regarding further investigations required; and the safety assessment team. The possible locations for a tentative deep repository are analysed in Chapter 3 of the report. The most promising area for the repository (denoted 'priority site') has been defined by SKB to be located southeast of the Forsmark nuclear plant and northwest of the gently dipping deformation zone ZFMNE00A2. Regarding the repository depth, present knowledge acquired from the site investigations indicates that it is possible to locate the repository at all stipulated depths according to SKB, that is between 400 m and 700 m depth. The preliminary assessment made in Chapter 3 clearly demonstrates that the repository can be accommodated within the 'priority site'. The potential to accommodate the repository is essentially the same for both 400 m and 500 m depths. The design of the deposition areas is reported in Chapter 4, which includes the design of layout features for all tunnels and deposition holes, orientation of tunnels, calculation of anticipated loss of deposition holes due to the applied

  20. Final repository for spent nuclear fuel. Underground design Forsmark, Layout D1

    Brantberger, Martin; Zetterqvist, Anders [Ramboell Sweden AB, Stockholm (Sweden); Arnbjerg-Nielsen, Torben [Ramboell Denmark A/S, Virum (Denmark); Olsson, Tommy [IandT Olsson AB, Uppsala (Sweden); Outters, Nils [Golder Associates AB, Uppsala (Sweden); Syrjaenen, Pauli [Gridpoint Oy, Helsinki (Sweden)

    2006-04-15

    This report comprises the design step D1 related to the underground design for a deep repository located at the Forsmark site. The design is based on the Site Descriptive Model Forsmark v1.2. All studies have been focussed at an area southeast of the Forsmark nuclear plant, which has been considered to be the most promising area for hosting the repository. SKB has developed guidelines for the design of the repository, which further describes the methodology applied for the studies. From these guidelines the following basic objectives for the design step D1 are summarized: to determine whether the final repository can be accommodated within the studied site; to identify site-specific facility critical issues; to test and evaluate the design methodology; to provide feedback to: the design organisation regarding additional studies that needs to be done; the site investigation and modelling organization regarding further investigations required; and the safety assessment team. The possible locations for a tentative deep repository are analysed in Chapter 3 of the report. The most promising area for the repository (denoted 'priority site') has been defined by SKB to be located southeast of the Forsmark nuclear plant and northwest of the gently dipping deformation zone ZFMNE00A2. Regarding the repository depth, present knowledge acquired from the site investigations indicates that it is possible to locate the repository at all stipulated depths according to SKB, that is between 400 m and 700 m depth. The preliminary assessment made in Chapter 3 clearly demonstrates that the repository can be accommodated within the 'priority site'. The potential to accommodate the repository is essentially the same for both 400 m and 500 m depths. The design of the deposition areas is reported in Chapter 4, which includes the design of layout features for all tunnels and deposition holes, orientation of tunnels, calculation of anticipated loss of deposition holes due

  1. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites

    Maheras, Steven J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Best, Ralph E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Ross, Steven B. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Buxton, Kenneth A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); England, Jeffery L. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); McConnell, Paul E. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Massaro, Lawrence M. [Fermi Research Alliance (FRA), Batavia, IL (United States); Jensen, Philip J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2016-09-30

    A preliminary evaluation of removing spent nuclear fuel (SNF) from 13 shutdown nuclear power plant sites was performed. At these shutdown sites the nuclear power reactors have been permanently shut down and the sites have been decommissioned or are undergoing decommissioning. The shutdown sites were Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, Zion, Crystal River, Kewaunee, San Onofre, and Vermont Yankee. The evaluation was divided into four components: Characterization of the SNF and greater-than-Class C low-level radioactive waste (GTCC waste) inventory A description of the on-site infrastructure at the shutdown sites An evaluation of the near-site transportation infrastructure and transportation experience at the shutdown sites An evaluation of the actions necessary to prepare for and remove SNF and GTCC waste. The primary sources for the inventory of SNF and GTCC waste were the U.S. Department of Energy (DOE) spent nuclear fuel inventory database, industry publications such as StoreFUEL, and government sources such as the U.S. Nuclear Regulatory Commission. The primary sources for information on the conditions of on-site infrastructure and near-site transportation infrastructure and experience included information collected during site visits, information provided by managers at the shutdown sites, Facility Interface Data Sheets compiled for DOE in 2005, Services Planning Documents prepared for DOE in 1993 and 1994, industry publications such as Radwaste Solutions, and Google Earth. State staff, State Regional Group representatives, a Tribal representative, and a Federal Railroad Administration representative have participated in nine of the shutdown site visits. Every shutdown site was found to have at least one off-site transportation mode option for removing its SNF and GTCC waste; some have multiple options. Experience removing large components during reactor decommissioning provided an

  2. Decommissioning study of Forsmark NPP

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias

    2013-06-01

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding

  3. Decommissioning study of Forsmark NPP

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  4. Description of the Northwest hazardous waste site data base and preliminary analysis of site characteristics

    Woodruff, D.L.; Hartz, K.E.; Triplett, M.B.

    1988-08-01

    The Northwest Hazardous Waste RD and D Center (the Center) conducts research, development, and demonstration (RD and D) activities for hazardous and radioactive mixed-waste technologies applicable to remediating sites in the states of Idaho, Montana, Oregon, and Washington. To properly set priorities for these RD and D activities and to target development efforts it is necessary to understand the nature of the sites requiring remediation. A data base of hazardous waste site characteristics has been constructed to facilitate this analysis. The data base used data from EPA's Region X Comprehensive Environmental Response, Compensation, and Liability Information System (CERCLIS) and from Preliminary Assessment/Site Investigation (PA/SI) forms for sites in Montana. The Center's data base focuses on two sets of sites--those on the National Priorities List (NPL) and other sites that are denoted as ''active'' CERCLIS sites. Active CERCLIS sites are those sites that are undergoing active investigation and analysis. The data base contains information for each site covering site identification and location, type of industry associated with the site, waste categories present (e.g., heavy metals, pesticides, etc.), methods of disposal (e.g., tanks, drums, land, etc.), waste forms (e.g., liquid, solid, etc.), and hazard targets (e.g., surface water, groundwater, etc.). As part of this analysis, the Northwest region was divided into three geographic subregions to identify differences in disposal site characteristics within the Northwest. 2 refs., 18 figs., 5 tabs

  5. Reflection seismic studies in the Forsmark area - stage 1

    Juhlin, Christopher; Bergman Bjoern; Palm, Hans [Uppsala Univ. (Sweden). Dept. of Earth Sciences

    2002-10-01

    Reflection seismic data were acquired in the Spring of 2002 in the Forsmark area, located about 70 km northeast of Uppsala, Sweden. The Forsmark area has been targeted by SKB as a possible storage site for high level radioactive waste. About 16 km of high resolution seismic data were acquired along five separate profiles varying in length from 2 to 5 km. Non-final source and receiver spacing was 10 m with 100 active channels when recording data from a dynamite source (15-75 g). The profiles were located within a relatively undeformed lens of bedrock that trends in the NW-SE direction. The lens is surrounded by highly deformed rock on all sides. In conjunction with the reflection component of the study, all shots were also recorded on up to eleven 3-component fixed Orion seismographs. These recordings provided long offset data from which a velocity model of the uppermost 400 m of bedrock could be derived. Results from the study show that the bedrock has been well imaged down to depths of at least 3 km. The upper 1000 m of bedrock is much more reflective in the southeastern portion of the lens compared to the northwestern part close to the Forsmark reactors. This is interpreted as the bedrock being more homogeneous in the northwest. However, a major reflective zone (the A1 reflector) is interpreted to dip to the S-SE below this homogeneous bedrock. In the southeastern portion of the lens the orientation of the reflectors is well determined where the profiles cross one another. The general strike of the major reflectors is NE-SW with dips of 20-35 degrees to the southeast.

  6. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites

    Maheras, Steven J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Best, Ralph E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Ross, Steven B. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Buxton, Kenneth A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); England, Jeffery L. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); McConnell, Paul E. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Massaro, Lawrence M. [Federal Railroad Administration (FRA) (United States); Jensen, Philip J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2014-10-01

    This report presents a preliminary evaluation of removing used nuclear fuel (UNF) from 12 shutdown nuclear power plant sites. At these shutdown sites the nuclear power reactors have been permanently shut down and the sites have been decommissioned or are undergoing decommissioning. The shutdown sites are Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, Zion, Crystal River, Kewaunee, and San Onofre. The evaluation was divided into four components: characterization of the UNF and greater-than-Class C low-level radioactive waste (GTCC waste) inventory; a description of the on-site infrastructure and conditions relevant to transportation of UNF and GTCC waste; an evaluation of the near-site transportation infrastructure and experience relevant to shipping transportation casks containing UNF and GTCC waste, including identification of gaps in information; and, an evaluation of the actions necessary to prepare for and remove UNF and GTCC waste. The primary sources for the inventory of UNF and GTCC waste are the U.S. Department of Energy (DOE) RW-859 used nuclear fuel inventory database, industry sources such as StoreFUEL and SpentFUEL, and government sources such as the U.S. Nuclear Regulatory Commission. The primary sources for information on the conditions of site and near-site transportation infrastructure and experience included observations and information collected during visits to the Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, and Zion sites; information provided by managers at the shutdown sites; Facility Interface Data Sheets compiled for DOE in 2005; Services Planning Documents prepared for DOE in 1993 and 1994; industry publications such as Radwaste Solutions; and Google Earth. State and Regional Group representatives, a Tribal representative, and a Federal Railroad Administration representative participated in six of the shutdown site

  7. Discrete fracture network for the Forsmark site

    Darcel, C. [Itasca Consultants, Ecully (France); Davy, P.; Bour, O.; Dreuzy, J.R. de [Geosciences, Rennes (France)

    2006-08-15

    In this report, we aim at defining a self-consistent method for analyzing the fracture patterns from boreholes, outcrops and lineaments. The objective was both to point out some variations in the fracture network parameters, and to define the global scaling fracture models that can encompass all the constraints brought by the different datasets. Although a full description of the DFN model variability is obviously fundamental for the future, we have put emphasis on the determination of mean parameters. The main parameters of the disc-shaped DFN model are the fracture size, orientations and spatial density distribution. The scaling model is defined as an extrapolation of existing i) observations at specific scales and ii) local fitting models to the whole range of scales. The range of possible models is restricted to the power-law scaling models. During the project we have put emphasize on the definition of the theory and methodology necessary to assess a sound comparison between data taken at different scales, with different techniques. Both 'local' and 'global' models have been investigated. Local models are linked exactly to the dataset they represent. Then, the global DFN models arise from the association of local models, different scales and different sample support shapes. Discrepancies between local and global model illustrate the variability associated to the DFN models. We define two possible Global Scaling Models (GSM). The first one is consistent with the scaling measured in the outcrops (Model A). Its scaling exponent is a{sub 3d}=3.5 (eq. to k{sub r}=2.5); it overestimates the fracture densities observed in the lineament maps. The second one assumes that both lineaments and outcrops belong to the same distribution model (Model B), which entails a scaling exponent a{sub 3d}=3.9 (eq. to k{sub r}=2.9). Both models have been tested by looking for the best consistency in the fracture density-dip relationships, between boreholes data at depth (based on boreholes KFM02A, KFM05A, HFM04 and HFM05) and outcrop DFN models. The main conclusions drawn from the consistency analysis are the following: There exists an important sub horizontal fracturing that occurs close to surface, which makes outcrop fracturing different, in term of density, from the fracturing observed in deep geological units from boreholes. The difference between surface and deep units does not exist for fractures dipping more than 30-40 deg. The rock units are remarkably consistent with outcrops for dips larger than 30-40 deg, and for Model A (a{sub 3d}=3.5). Model B tends to predict larger fracture densities in outcrops than in rock units defined in boreholes (in the dip range of 30-40 deg). There is no equivalence, in the outcrops, of the Deformation Zones, identified at depth. The best-fitting model is defined for l{sub min} (the smallest fracture diameter consistent with the power law model; l{sub min}=2r{sub 0} with r{sub 0} the location parameter) smaller than the borehole diameter. With this method, it is not possible to say more about l{sub min}. Models that consider larger values of l{sub min} do not ensure the consistency between outcrops and boreholes. The shear zones, as well as the lineaments, may belong to a different global scaling model than rock units. Further investigations and more data are necessary to characterize this additional GSM. Along the project, the issue of DFN model and of the fracture definition consistency across scales is often raised. It should be further investigated, together with a more complete description of the model variability.

  8. Discrete fracture network for the Forsmark site

    Darcel, C.; Davy, P.; Bour, O.; Dreuzy, J.R. de

    2006-08-01

    In this report, we aim at defining a self-consistent method for analyzing the fracture patterns from boreholes, outcrops and lineaments. The objective was both to point out some variations in the fracture network parameters, and to define the global scaling fracture models that can encompass all the constraints brought by the different datasets. Although a full description of the DFN model variability is obviously fundamental for the future, we have put emphasis on the determination of mean parameters. The main parameters of the disc-shaped DFN model are the fracture size, orientations and spatial density distribution. The scaling model is defined as an extrapolation of existing i) observations at specific scales and ii) local fitting models to the whole range of scales. The range of possible models is restricted to the power-law scaling models. During the project we have put emphasize on the definition of the theory and methodology necessary to assess a sound comparison between data taken at different scales, with different techniques. Both 'local' and 'global' models have been investigated. Local models are linked exactly to the dataset they represent. Then, the global DFN models arise from the association of local models, different scales and different sample support shapes. Discrepancies between local and global model illustrate the variability associated to the DFN models. We define two possible Global Scaling Models (GSM). The first one is consistent with the scaling measured in the outcrops (Model A). Its scaling exponent is a 3d =3.5 (eq. to k r =2.5); it overestimates the fracture densities observed in the lineament maps. The second one assumes that both lineaments and outcrops belong to the same distribution model (Model B), which entails a scaling exponent a 3d =3.9 (eq. to k r =2.9). Both models have been tested by looking for the best consistency in the fracture density-dip relationships, between boreholes data at depth (based on boreholes KFM02A, KFM05A, HFM04 and HFM05) and outcrop DFN models. The main conclusions drawn from the consistency analysis are the following: There exists an important sub horizontal fracturing that occurs close to surface, which makes outcrop fracturing different, in term of density, from the fracturing observed in deep geological units from boreholes. The difference between surface and deep units does not exist for fractures dipping more than 30-40 deg. The rock units are remarkably consistent with outcrops for dips larger than 30-40 deg, and for Model A (a 3d =3.5). Model B tends to predict larger fracture densities in outcrops than in rock units defined in boreholes (in the dip range of 30-40 deg). There is no equivalence, in the outcrops, of the Deformation Zones, identified at depth. The best-fitting model is defined for l min (the smallest fracture diameter consistent with the power law model; l min =2r 0 with r 0 the location parameter) smaller than the borehole diameter. With this method, it is not possible to say more about l min . Models that consider larger values of l min do not ensure the consistency between outcrops and boreholes. The shear zones, as well as the lineaments, may belong to a different global scaling model than rock units. Further investigations and more data are necessary to characterize this additional GSM. Along the project, the issue of DFN model and of the fracture definition consistency across scales is often raised. It should be further investigated, together with a more complete description of the model variability

  9. New Reactor Siting in Finland, Hanhikivi Site in Pyhaejoki - STUK preliminary safety assessment

    Nevalainen, Janne

    2013-01-01

    STUK has performed a preliminary assessment of the Decision-in-Principle on the Fennovoima application. A variety of factors must be considered in the selection of a site, including effects of the site on the plant design and the effects of the plant on the site environment. These include external hazards, both natural and human-induced. Since this is a new site, an extensive siting process is followed, that can include an EIA. A site survey is performed to identify candidate sites, after investigating a large region and rejecting unsuitable sites. The remaining sites are then screened and compared on the basis of safety and other considerations to select one or more preferred sites. Natural hazards include geology, seismology, hydrology and meteorology. Offshore ice will be a particular hazard for this plant, since the site is on average only 1.5 m above sea level. The design basis earthquake corresponds to a return frequency of 100,000 years, with 50 % confidence. The existing sites in southern Finland used a design peak ground acceleration of 0.1 g with the ground response spectrum maximum at 10 Hz. The candidate sites in northern Finland will require a peak ground acceleration of 0.2 g with the ground response spectrum maximum at 25 Hz

  10. Hydrogeological conceptual model development and numerical modelling using CONNECTFLOW, Forsmark modelling stage 2.3

    Follin, Sven (SF GeoLogic AB, Taeby (Sweden)); Hartley, Lee; Jackson, Peter; Roberts, David (Serco TAP (United Kingdom)); Marsic, Niko (Kemakta Konsult AB, Stockholm (Sweden))

    2008-05-15

    Three versions of a site descriptive model (SDM) have been completed for the Forsmark area. Version 0 established the state of knowledge prior to the start of the site investigation programme. Version 1.1 was essentially a training exercise and was completed during 2004. Version 1.2 was a preliminary site description and concluded the initial site investigation work (ISI) in June 2005. Three modelling stages are planned for the complete site investigation work (CSI). These are labelled stage 2.1, 2.2 and 2.3, respectively. An important component of each of these stages is to address and continuously try to resolve discipline-specific uncertainties of importance for repository engineering and safety assessment. Stage 2.1 included an updated geological model for Forsmark and aimed to provide a feedback from the modelling working group to the site investigation team to enable completion of the site investigation work. Stage 2.2 described the conceptual understanding and the numerical modelling of the bedrock hydrogeology in the Forsmark area based on data freeze 2.2. The present report describes the modelling based on data freeze 2.3, which is the final data freeze in Forsmark. In comparison, data freeze 2.3 is considerably smaller than data freeze 2.2. Therefore, stage 2.3 deals primarily with model confirmation and uncertainty analysis, e.g. verification of important hypotheses made in stage 2.2 and the role of parameter uncertainty in the numerical modelling. On the whole, the work reported here constitutes an addendum to the work reported in stage 2.2. Two changes were made to the CONNECTFLOW code in stage 2.3. These serve to: 1) improve the representation of the hydraulic properties of the regolith, and 2) improve the conditioning of transmissivity of the deformation zones against single-hole hydraulic tests. The changes to the modelling of the regolith were made to improve the consistency with models made with the MIKE SHE code, which involved the introduction

  11. Site Characterization and Preliminary Performance Assessment Calculation Applied To JAEA-Horonobe URL Site of Japan

    Lim, Doo Hyun; Hatanaka, Koichiro; Ishii, Eiichi

    2010-01-01

    JAEA-Horonobe Underground Research Laboratory (URL) is designed for research and development on high-level radioactive waste (HLW) repository in sedimentary rock. For a potential HLW repository, understanding and implementing fracturing and faulting system, with data from the site characterization, into the performance assessment is essential because fracture and fault will be the major conductors or barriers for the groundwater flow and radionuclide release. The objectives are i) quantitative derivation of characteristics and correlation of fracturing/faulting system with geologic and geophysics data obtained from the site characterization, and ii) preliminary performance assessment calculation with characterized site information

  12. Site Characterization and Preliminary Performance Assessment Calculation Applied To JAEA-Horonobe URL Site of Japan

    Lim, Doo Hyun [NE Union Hill Road, Suite 200, WA 98052 (United States); Hatanaka, Koichiro; Ishii, Eiichi [Japan Atomic Energy Agency, Hokkaido (Japan)

    2010-10-15

    JAEA-Horonobe Underground Research Laboratory (URL) is designed for research and development on high-level radioactive waste (HLW) repository in sedimentary rock. For a potential HLW repository, understanding and implementing fracturing and faulting system, with data from the site characterization, into the performance assessment is essential because fracture and fault will be the major conductors or barriers for the groundwater flow and radionuclide release. The objectives are i) quantitative derivation of characteristics and correlation of fracturing/faulting system with geologic and geophysics data obtained from the site characterization, and ii) preliminary performance assessment calculation with characterized site information

  13. Uncertainty aspects of the digital elevation model for the Forsmark area

    Stroemgren, Maarten; Brydsten, Lars (Umeaa Univ., Umeaa (Sweden))

    2009-10-15

    A digital elevation model (DEM) describes the terrain relief. A proper DEM is an important data source for many of the different site description models conducted in the Forsmark region. Input data for the Forsmark DEM is elevation data for both land and sea areas of different origin and quality. No statistical analysis of the error in the Forsmark DEM is so far carried out. However, the Forsmark DEM is part of the quality assessment of the regolith depth model for the Forsmark area since it represents the upper surface of the regolith depth model. The aim of this project was to calculate the errors in different areas in the Forsmark DEM and present them in terms of general descriptive statistics. Measurements have confirmed the knowledge that the 0.25-metre DEM produced from the laser scanning measurements in the Laxemar-Simpevarp area is of very high quality. The 0.25-metre DEM was used to calculate the errors of the 10 and 50-metre DEMs, and the errors for different sea shoreline sources. These error distributions were placed randomly among points for the same data sources in the Forsmark area and used for correction of the original elevation levels. Using the corrected input data for the 10 and 50-metre DEMs and for the sea shoreline, a new DEM was produced. All other input data remained unchanged. The error for the Forsmark DEM was calculated for areas within the data sources corrected from the 0.25-metre DEM. The 0.25-metre DEM from the Laxemar-Simpevarp area was also used for a calculation of how density of input data points used in interpolation affects quality in a 20-metre DEM. Part of the input data was removed in the sea area, new DEMs were produced and compared to the existing Forsmark DEM within the areas of the removed data, to get a measure of the error in these areas of the DEM. In areas of input data for the sea shoreline, the quality of the Forsmark DEM is high. The errors within the SKB 10-metre DEM are slightly less than within the extension

  14. Uncertainty aspects of the digital elevation model for the Forsmark area

    Stroemgren, Maarten; Brydsten, Lars

    2009-10-01

    A digital elevation model (DEM) describes the terrain relief. A proper DEM is an important data source for many of the different site description models conducted in the Forsmark region. Input data for the Forsmark DEM is elevation data for both land and sea areas of different origin and quality. No statistical analysis of the error in the Forsmark DEM is so far carried out. However, the Forsmark DEM is part of the quality assessment of the regolith depth model for the Forsmark area since it represents the upper surface of the regolith depth model. The aim of this project was to calculate the errors in different areas in the Forsmark DEM and present them in terms of general descriptive statistics. Measurements have confirmed the knowledge that the 0.25-metre DEM produced from the laser scanning measurements in the Laxemar-Simpevarp area is of very high quality. The 0.25-metre DEM was used to calculate the errors of the 10 and 50-metre DEMs, and the errors for different sea shoreline sources. These error distributions were placed randomly among points for the same data sources in the Forsmark area and used for correction of the original elevation levels. Using the corrected input data for the 10 and 50-metre DEMs and for the sea shoreline, a new DEM was produced. All other input data remained unchanged. The error for the Forsmark DEM was calculated for areas within the data sources corrected from the 0.25-metre DEM. The 0.25-metre DEM from the Laxemar-Simpevarp area was also used for a calculation of how density of input data points used in interpolation affects quality in a 20-metre DEM. Part of the input data was removed in the sea area, new DEMs were produced and compared to the existing Forsmark DEM within the areas of the removed data, to get a measure of the error in these areas of the DEM. In areas of input data for the sea shoreline, the quality of the Forsmark DEM is high. The errors within the SKB 10-metre DEM are slightly less than within the extension

  15. Preliminary evaluation of the seismic hazard at Cernavoda NPP site

    Mingiuc, C.; Serban, V.; Androne, M.

    2001-01-01

    The probabilistic seismic hazard analysis (PSHA) is a methodology by which one evaluates the probability of exceeding different parameters of the ground motions (the maximum ground acceleration - PGA and the ground response spectrum - SA) as effect of the seismic action, on a given site at a future time moment. Due to the large uncertainties in the geological, geophysical, seismological input data, as well as, in the models utilised, various interpretation schemes are applied in the PSHA analyses. This interpretation schemes lead to opinion discrepancies among specialists which finally lead to disagreements in estimating the values of the seismic design for a given site. In order to re-evaluate the methodology and to improve the PSHA result stability, U.S. Nuclear Regulatory Commission (NRC), U.S. Department of Energy (DOE) and Electric Power Research Institute (EPRI) sponsored a project for defining methodological guides of performing PSHA analyses. The project was implemented by a panel of 7 experts, the Senior Seismic Hazard Analysis Committee - SSHAC. This paper presents a preliminary evaluation of the seismic hazard for the Cernavoda NPP site by application of the methodology mentioned, by taking into account the possible sources which could affect the site (the Vrancea focus, Galati - Tulcea fault, Sabla - Dulovo fault and local earthquakes)

  16. Environmental Survey preliminary report, Nevada Test Site, Mercury, Nevada

    1988-04-01

    This report presents the preliminary findings from the first phase of the Environmental Survey of the United States Department of Energy (DOE) Nevada Test Site (NTS), conducted June 22 through July 10, 1987. The Survey is being conducted by a multidisciplinary team of environmental specialists led and managed by the Office of Environment, Safety and Health's Office of Environmental Audit. Individual team members are outside experts being supplied by a private contractor. The objective of the Survey is to identify environmental problems and areas of environmental risk associated with the NTS. The Survey covers all environment media and all areas of environmental regulation. It is being performed in accordance with the DOE Environmental Survey Manual. This phase of the Survey involves the review of existing site environmental data, observations of the operations and activities performed at the NTS, and interviews with site personnel. The Survey team developed a Sampling and Analysis Plan to assist in further assessing certain environmental problems identified during its on-site activities. The Sampling and Analysis Plan is being executed by the Battelle Columbus Division under contract with DOE. When completed, the results will be incorporated into the NTS Environmental Survey Interim Report. The Interim Report will reflect the final determinations of the NTS Survey. 165 refs., 42 figs., 52 tabs

  17. Environmental Survey preliminary report, Nevada Test Site, Mercury, Nevada

    1988-04-01

    This report presents the preliminary findings from the first phase of the Environmental Survey of the United States Department of Energy (DOE) Nevada Test Site (NTS), conducted June 22 through July 10, 1987. The Survey is being conducted by a multidisciplinary team of environmental specialists led and managed by the Office of Environment, Safety and Health's Office of Environmental Audit. Individual team members are outside experts being supplied by a private contractor. The objective of the Survey is to identify environmental problems and areas of environmental risk associated with the NTS. The Survey covers all environment media and all areas of environmental regulation. It is being performed in accordance with the DOE Environmental Survey Manual. This phase of the Survey involves the review of existing site environmental data, observations of the operations and activities performed at the NTS, and interviews with site personnel. The Survey team developed a Sampling and Analysis Plan to assist in further assessing certain environmental problems identified during its on-site activities. The Sampling and Analysis Plan is being executed by the Battelle Columbus Division under contract with DOE. When completed, the results will be incorporated into the NTS Environmental Survey Interim Report. The Interim Report will reflect the final determinations of the NTS Survey. 165 refs., 42 figs., 52 tabs.

  18. Preliminary site design for the SP-100 ground engineering test

    Cox, C.M.; Miller, W.C.; Mahaffey, M.K.

    1986-04-01

    In November, 1985, Hanford was selected by the Department of Energy (DOE) as the preferred site for a full-scale test of the integrated nuclear subsystem for SP-100. The Hanford Engineering Development Laboratory, operated by Westinghouse Hanford Company, was assigned as the lead contractor for the Test Site. The nuclear subsystem, which includes the reactor and its primary heat transport system, will be provided by the System Developer, another contractor to be selected by DOE in late FY-1986. In addition to reactor operations, test site responsibilities include preparation of the facility plus design, procurement and installation of a vacuum chamber to house the reactor, a secondary heat transport system to dispose of the reactor heat, a facility control system, and postirradiation examination. At the conclusion of the test program, waste disposal and facility decommissioning are required. The test site must also prepare appropriate environmental and safety evaluations. This paper summarizes the preliminary design requirements, the status of design, and plans to achieve full power operation of the test reactor in September, 1990

  19. Man-machine communication at Forsmark 3

    Hultquist, Goeran; Norberg, Soeren

    1984-01-01

    The design of Forsmark 3 began in 1976 and the control room layout and equipment were discussed right from the start. Susequent evolution and events in other nuclear power plants have, however, radically changed the direction of the development of the man-machine functions. (author)

  20. Epilithic algal assemblages in the Forsmark Biotest basin

    Snoeijs, P.

    1987-04-01

    The Forsmark Biotest Basin is an artificial offshore brackish lake, through which the cooling water is led from the Forsmark Nuclear Power Station on the Swedish east coast. The Biotest Basin differs from the Bothnian Sea surrounding it by a temperature elevation of up to 10 degrees C, no ice cover in winter, and an artificial, fast current. At 11 sites in- and outside the basin, benthic algal assemblages on stones in the hydrolittoral belt were sampled every third week during one year. Cover abundances were estimated for all algae occurring on the stones, but for diatoms only when they formed blooms. The results of the vegetation analyses are given. Diversity indices and dominance-diversity curves were computed for each site on the basis of pooled data for the cold season and for the rest of the year. The algae included both unicellular and multicellular forms. In total 88 taxa were distinguished in the species lists: 29 Cyanophyta, 7 Rhodophyta, 1 Chrysophyceae, 9 Fucophyceae, 17 Diatomophyceae and 25 Chlorophyta. In terms of percentage cover-abundance, blue-green and green algae increased with temperature, while red and brown algae and diatoms decreased with temperature in the interval between the minimum (0 degrees C) and the maximum (25.7 degrees C) water temperatures that were measured during the investigation period. Melosira spp. and Nitzschia filiformis proved to be the diatoms most favoured by the cooling water discharge. Lower diversity and greater dominance of one or a few species over the other was caused by thermal discharge at sites with fast-flowing water, but the opposite occurred at sites with quiescent water, mainly due to a greater number and higher abundances of blue-green algal species and thread-like green algae at the latter sites. This report also gives some notes on taxonomy of the encountered species.

  1. Water activities in Forsmark. Ecological field inventory and classification of biodiversity values and description of forest production land; Vattenverksamhet i Forsmark. Ekologisk faeltinventering och naturvaerdesklassificering samt beskrivning av skogsproduktionsmark

    Hamren, Ulrika; Collinder, Per [Ekologigruppen AB (Sweden)

    2010-12-15

    In 2009, the Swedish Nuclear Fuel and Waste Management Co (SKB) chose Forsmark in the Municipality of Oesthammar as site for the final repository for spent nuclear fuel. This report describes nature values and forestry areas in Forsmark, and provides part of the background material for description of consequences due to groundwater diversion during construction and operation of the repository. The report describes results of map studies and comprehensive field investigations, in terms of geographical delineations, descriptions of characteristics and classifications of nature values for groundwater dependent or groundwater favoured nature objects in Forsmark. The nature objects are located in an investigation area, which contains the area that according to numerical flow modelling could be affected by groundwater-table drawdown due to groundwater diversion

  2. The limnic ecosystems at Forsmark and Laxemar-Simpevarp

    Andersson, Eva

    2010-12-01

    The overall objective of this report is to describe the limnic ecosystems at Forsmark and Laxemar- Simpevarp, identify important processes in a radionuclide perspective and provide a description of the radionuclide model for the biosphere used in SR-Site. The report includes a thorough description of the lakes and streams in Forsmark and Laxemar- Simpevarp and covers the following areas: catchment area characteristics, hydrology, climate, sediment characteristics, physical characteristics of streams, habitat distribution in lakes, biotic components (biomass as well as production), water chemistry, and comparison with other lakes and streams in the region, and a historical description. Ecosystem models for carbon and mass balances for a number of elements have been calculated to further improve the understanding of the lake ecosystems. Important processes for the safety assessment are described and evaluated in the report. A separate chapter is included to specifically describe how and where these processes are included in the radionuclide model. The radionuclide model is described and parameterisation and guidance to parameter calculation is provided. The last chapter of the report provides a summary of the knowledge of the limnic systems at the two areas. The Forsmark regional model area contains more than 25 permanent lakes and pools. All lakes are small and shallow, and are characterized as oligotrophic hardwater lakes. Calcareous soils in the area give rise to high calcium concentrations in the surface water, which in turn leads to high pH and low nutrient concentrations in water as phosphorus often co-precipitates with calcium. The shallow depths and moderate water colour permit photosynthesis in the entire benthic habitat of the lakes, and the bottoms are covered by dense stands of the macroalgae Chara sp. Moreover, many of the lakes also have a thick microbial mat (>10 cm), consisting of cyanobacteria and diatoms, in the benthic habitat. Fish in the lakes

  3. The limnic ecosystems at Forsmark and Laxemar-Simpevarp

    Andersson, Eva

    2010-12-15

    The overall objective of this report is to describe the limnic ecosystems at Forsmark and Laxemar- Simpevarp, identify important processes in a radionuclide perspective and provide a description of the radionuclide model for the biosphere used in SR-Site. The report includes a thorough description of the lakes and streams in Forsmark and Laxemar- Simpevarp and covers the following areas: catchment area characteristics, hydrology, climate, sediment characteristics, physical characteristics of streams, habitat distribution in lakes, biotic components (biomass as well as production), water chemistry, and comparison with other lakes and streams in the region, and a historical description. Ecosystem models for carbon and mass balances for a number of elements have been calculated to further improve the understanding of the lake ecosystems. Important processes for the safety assessment are described and evaluated in the report. A separate chapter is included to specifically describe how and where these processes are included in the radionuclide model. The radionuclide model is described and parameterisation and guidance to parameter calculation is provided. The last chapter of the report provides a summary of the knowledge of the limnic systems at the two areas. The Forsmark regional model area contains more than 25 permanent lakes and pools. All lakes are small and shallow, and are characterized as oligotrophic hardwater lakes. Calcareous soils in the area give rise to high calcium concentrations in the surface water, which in turn leads to high pH and low nutrient concentrations in water as phosphorus often co-precipitates with calcium. The shallow depths and moderate water colour permit photosynthesis in the entire benthic habitat of the lakes, and the bottoms are covered by dense stands of the macroalgae Chara sp. Moreover, many of the lakes also have a thick microbial mat (>10 cm), consisting of cyanobacteria and diatoms, in the benthic habitat. Fish in the lakes

  4. Water activities in Forsmark. Ecological field inventory and classification of biodiversity values and description of forest production land

    Hamren, Ulrika; Collinder, Per

    2010-12-01

    In 2009, the Swedish Nuclear Fuel and Waste Management Co (SKB) chose Forsmark in the Municipality of Oesthammar as site for the final repository for spent nuclear fuel. This report describes nature values and forestry areas in Forsmark, and provides part of the background material for description of consequences due to groundwater diversion during construction and operation of the repository. The report describes results of map studies and comprehensive field investigations, in terms of geographical delineations, descriptions of characteristics and classifications of nature values for groundwater dependent or groundwater favoured nature objects in Forsmark. The nature objects are located in an investigation area, which contains the area that according to numerical flow modelling could be affected by groundwater-table drawdown due to groundwater diversion

  5. Groundwater flow modelling of periods with temperate climate conditions - Forsmark

    Joyce, Steven; Simpson, Trevor; Hartley, Lee; Applegate, David; Hoek, Jaap; Jackson, Peter; Swan, David (Serco Technical Consulting Services (United Kingdom)); Marsic, Niko (Kemakta Konsult AB (Sweden)); Follin, Sven (SF GeoLogic AB (Sweden))

    2010-11-15

    As a part of the license application for a final repository for spent nuclear fuel at Forsmark, the Swedish Nuclear Fuel and Waste Management Company (SKB) has undertaken a series of groundwater flow modelling studies. These represent time periods with different climate conditions and the simulations carried out contribute to the overall evaluation of the repository design and long-term radiological safety. This report concerns the modelling of a repository at the Forsmark site during temperate conditions; i.e. from post-closure and throughout the temperate period up until the receding shoreline leaves the modelling domain at around 12,000 AD. The collation and implementation of onsite hydrogeological and hydrogeochemical data from previous reports are used in the construction of a hydrogeological base case (reference case conceptualisation) and then in an examination of various areas of uncertainty within the current understanding by a series of model variants. The hydrogeological base case models at three different scales, 'repository', 'site' and 'regional', make use of continuous porous medium (CPM), equivalent continuous porous medium (ECPM) and discrete fracture network (DFN) models. The use of hydrogeological models allow for the investigation of the groundwater flow from a deep disposal facility to the biosphere and for the calculation of performance measures that will provide an input to the site performance assessment. The focus of the study described in this report has been to perform numerical simulations of the hydrogeological system from post-closure and throughout the temperate period. Besides providing quantitative results for the immediate temperate period following post-closure, these results are also intended to give a qualitative indication of the evolution of the groundwater system during future temperate periods within an ongoing cycle of glacial/inter-glacial events

  6. Market led: Forsmark looks to 2000

    Anon.

    1994-01-01

    The Forsmark nuclear power plant in Sweden includes three BWR reactors totalling 3200 MWe. From a design level of 70% the average capability factor has been increased to 90%. This has been achieved by a market-orientated approach with efficient outages and a total production cost identified with each unit in order to show how each stands in relation to the market price level and to outside competition. Forsmark's performance, as indicated by capacity factors, refuelling outage length and electricity production costs is better than most. Strategic planning is important and a refurbishment programme up to 2000 is planned to renew the electricity generators, replace the process computers and upgrade the preheater systems. (UK)

  7. Macrofauna on rocky substrates in the Forsmark biotest basin. March 1984 - March 1985

    Snoeijs, P.; Mo, K.

    1987-09-01

    The Forsmark biotest basin, situated on the Swedish east coast, is an artificial offshore brackish lake, through which the cooling water is channelled from the Forsmark nuclear power plant to the Bothnian Sea. The biotest basin is up to 10 0 C warmer than the sea surrounding it, and has no ice cover in winter. There is an artificial, fast current in a large part of the basin. Macrofauna on stones in the hydrolittoral belt was sampled at 11 sites in- and outside the basin every third week during one year. The numbers of individuals per m 2 for each taxon were counted. Diversity indices and dominance-diversity curves were computed for each site on the basis of pooled data for the cold season, and for the rest of the year. In total 66 taxa were distinguished in the species lists, of which 3 are sessile, the rest free-living. (orig./DG)

  8. Radon as a groundwater tracer in Forsmark and Laxemar

    Grolander, Sara

    2009-10-01

    Radon concentrations were measured in different water types in Forsmark and Laxemar during the site investigation and within this study. From these measurements it can be concluded that large differences between surface water, near surface groundwater and deep groundwater can be found in both Laxemar and Forsmark. The differences in radon concentrations between different water types are used in this study to detect interactions between surface water, near surface water and deep groundwater. From the radon measurements it can also be concluded that radon concentration in deep groundwater varies largely with depth. These variations with depth are probably caused by groundwater flow in conductive fracture zones in the bedrock. The focus of this study has been the radon concentration of near surface groundwater and the interaction between near surface groundwater and deep groundwater. Radon measurements have been done using the RAD-7 radon detector within this study. It could be concluded that RAD-7 is a good technique for radon measurements and also easy to use in field. The radon concentrations measured in near surface groundwater in Laxemar within this study were low and homogenous. The variation in radon concentration has been analyses and compared to other parameters. Since the hypothesis of this study has been that there are differences in radon concentrations between recharging and discharging groundwater, the most important parameter to consider is the recharge/discharge field classification of the wells. No correlation between the recharge/discharge classifications of wells and the radon concentrations were found. The lack of correlation between groundwater flow patterns and radon concentration means that it is not possible to detect flow patterns in near surface groundwater using radon as a tracer in the Laxemar area. The lack of correlation can be caused by the fact that there are just a few wells located in areas classified as recharge area. It can also be

  9. Permanent scatterer InSAR processing: Forsmark

    Dehls, John F.

    2006-04-01

    It has been speculated that slow, aseismic movement may be occurring along some of the fracture zones crosscutting the Forsmark area. The purpose of this study is to determine if it is possible to measure such movement using dInSAR. Differential SAR Interferometry (DInSAR) is a technique that compares the phases of multiple radar images of an area to measure surface change. The method has the potential to detect millimetric surface deformation along the sensor - target line-of-sight. Differences in phase between two images are easily viewed by combining, or interfering, the two phase-images. In the resulting image, the waves will either reinforce or cancel one another, depending upon the relative phases. The resulting image is called an interferogram and contains concentric bands of colour, or fringes, that are related to topography and/or surface deformation. New algorithms use many images acquired over a long time period to determine the movement history of individual objects, referred to as permanent scatterers. In the current project, standard PSInSAR processing was performed on 40 ERS-1 and ERS-2 scenes. The total area processed is approximately 1,500 km 2 . Slightly less than 20,000 permanent scatterers were identified.The highest densities were obtained along the coast and on the islands, where natural outcrops are more abundant. Two main classes of objects act as permanent scatterers in this area. The first are natural reflectors, such as rocks. The second are man-made reflectors, such as parts of buildings. Numerous local movements were found in the study area, relating to building subsidence, or compaction of anthropogenic fill. The dataset was divided into three groups for analysis, based upon the location of regional lineaments provided by SKB. Both statistical and geostatistical techniques were used. The median velocity of the three blocks did not differ by more than 0.2 mm/yr. This is not considered significant, given the possible magnitude of errors

  10. Permanent scatterer InSAR processing: Forsmark

    Dehls, John F [Geological Survey of Norway, Trondheim (Norway)

    2006-04-15

    It has been speculated that slow, aseismic movement may be occurring along some of the fracture zones crosscutting the Forsmark area. The purpose of this study is to determine if it is possible to measure such movement using dInSAR. Differential SAR Interferometry (DInSAR) is a technique that compares the phases of multiple radar images of an area to measure surface change. The method has the potential to detect millimetric surface deformation along the sensor - target line-of-sight. Differences in phase between two images are easily viewed by combining, or interfering, the two phase-images. In the resulting image, the waves will either reinforce or cancel one another, depending upon the relative phases. The resulting image is called an interferogram and contains concentric bands of colour, or fringes, that are related to topography and/or surface deformation. New algorithms use many images acquired over a long time period to determine the movement history of individual objects, referred to as permanent scatterers. In the current project, standard PSInSAR processing was performed on 40 ERS-1 and ERS-2 scenes. The total area processed is approximately 1,500 km{sup 2}. Slightly less than 20,000 permanent scatterers were identified.The highest densities were obtained along the coast and on the islands, where natural outcrops are more abundant. Two main classes of objects act as permanent scatterers in this area. The first are natural reflectors, such as rocks. The second are man-made reflectors, such as parts of buildings. Numerous local movements were found in the study area, relating to building subsidence, or compaction of anthropogenic fill. The dataset was divided into three groups for analysis, based upon the location of regional lineaments provided by SKB. Both statistical and geostatistical techniques were used. The median velocity of the three blocks did not differ by more than 0.2 mm/yr. This is not considered significant, given the possible magnitude of

  11. Application of the Drilling Impact Study (DIS) to Forsmark groundwaters

    Gascoyne, Mel; Gurban, Ioana

    2008-01-01

    Characterisation of a geological formation as a repository for nuclear fuel waste requires deep drilling into the bedrock to gain an understanding of the geological structure, rock types, groundwater flow and the chemical composition of groundwater and the adjacent rock. The methods of characterisation from a hydrogeochemical point of view, might be affected by the various drilling activities and techniques for determining groundwater composition have been employed so that the composition can be corrected for these activities. SKB has developed and supported the Drilling Impact Study (DIS) project in which a tracer is used as an indicator of contamination to attempt to correct the groundwater composition for dilution or contamination by surface waters. The project began about five years ago with the intention of developing a routine method for determining the extent of contamination of borehole groundwater by drilling water. The main objectives of this work were: 1. Determine the extent of drilling water contamination in permeable zones in a test borehole on the Forsmark site. 2. Correct measured chemical compositions of the groundwaters based on contamination results. 3. Provide a workable methodology for routine correction of groundwater composition. 4. Apply the modified DIS model to suitable borehole zones at the Forsmark site in a systematic fashion 5. Determine uncertainties in DIS modelling. A memorandum was prepared by describing the characteristics of borehole KFM06 and its drilling history. Estimates were made of the amount of drilling water in permeable zones in the borehole and the various approaches to applying results of DIS were described and recommendations made, with an example calculation

  12. Preliminary site characterization at Beishan northwest China-A potential site for China's high-level radioactive waste repository

    Wang Ju; Su Rui; Xue Weiming; Zheng Hualing

    2004-01-01

    Chinese nuclear power plants,radioactive waste and radioactive waste disposal are introduced. Beishan region (Gansu province,Northwest China)for high-level radioactive waste repository and preliminary site characterization are also introduced. (Zhang chao)

  13. Preliminary site description. Simpevarp area - version 1.1

    Winberg, Anders

    2004-08-01

    Site characterisation in the Oskarshamn area is currently conducted at two adjoining localities, the Simpevarp and Laxemar subareas. This report presents the interim version (model version Simpevarp 1.1 of S1.1 for short) of the preliminary Site Descriptive Model for the Simpevarp subarea. The basis for this interim version is quality-assured, geoscientific and ecological field data from the Simpevarp subarea (and in part from the Laxemar area) available in the SKB SICADA and GIS data bases as of July 1, 2003 as well as version 0 of the Site Descriptive Model. The new data collected during the initial site investigation phase up till the date of data freeze S1.1 constitute the basis for the update of version 0 to version S1.1. These data include results from surface investigations in the subarea with its regional environment and from drillings and investigations in boreholes. The surface-based data sets were, in a relative sense, extensive compared with data sets from boreholes, were the information largely was limited to information from one c. 1,000 m deep cored borehole (KSH01A), two existing cored boreholes and three c. 200 m deep percussion-drilled boreholes. Discipline-specific models are developed for the selected regional and local model volumes and these models are subsequently integrated into a unified site description. The current methodologies for developing discipline-specific models and their integration are documented in methodology/ strategy reports. In the present work, the procedures and guidelines given in those reports were followed to the extent possible given the data and information available at the time of data freeze for model version S1.1. Compared with version 0 there are considerable additional features in the version S1.1, especially in the geological description and in the description of the near surface. The geological models of lithology and deformation zones are based on borehole information and surface data of much higher

  14. Subsidence analysis Forsmark nuclear power plant - unit 1; Saettningsanalys Forsmarks kaernkraftverk - aggregat 1

    Bono, Nancy; Fredriksson, Anders; Maersk Hansen, Lars (Golder Associates AB (Sweden))

    2010-12-15

    On behalf of SKB, Golder Associates Ltd carried out a risk analysis of subsidence during Forsmark nuclear power plant in the construction of the final repository for spent nuclear fuel near and below existing reactors. Specifically, the effect of horizontal cracks have been studied.

  15. Modelling of Fracture Initiation, Propagation and Creep of a KBS-3V and KBS-3H Repository in Sparsely Fractured Rock with Application to the Design at Forsmark Candidate Site

    Backers, Tobias; Stephansson, Ove

    2008-01-01

    The stability issues of deposition holes of a repository layout according to the KBS-3 concept in the sparsely fractured Forsmark granites are analysed with the emphasis on fracture mechanics. At the start of the project the rock mass is viewed as a continuum. In a second step explicit fracture networks are introduced and included in the numerical rock fracture models. The software Fracod2D was used for the rock fracture mechanics analysis. Assuming deposition holes located in a continuous, homogeneous elastic rock mass and The presented stress state of the rock mass the following results were obtained: For single KBS-3H deposition holes oriented in the direction of the minimum horizontal stress, Sh, bore hole breakouts are introduced for all depth levels. For KBS-3H holes which are oriented in direction of SH, no significant fracturing can be expected. In case of vertical deposition holes according to KBS-3V an increased risk of fracturing at greater depth levels (> 500m) is evident. At shallow depth levels ( 5MPa gives a favourable situation about spalling for the KBS-3H and KBS-3V layouts. To prevent spalling, it is important to build up a swelling pressure soon after excavation, so that the enhanced stresses in the surrounding of the deposition ii holes are reduced. This has a positive impact on other excavation activities and also on time-dependent fracturing. After excavation and filling of the deposition holes with subsequent increase of swelling pressure, the temperature will increase in the vicinity of the excavation. For the range of swelling pressures predicted for the KBS-3 concept, i.e. 5.5MPa to 7.2MPa, no significant fracturing for the KBS-3H concept with the axis parallel SH at depths below about 600m was discovered. The results from other layouts bare the risk of partly significant fracturing. About 60ka from closing the repository an ice cover of approximately 3km is expected over Forsmark. This dead load increases the in-situ stresses and

  16. Preliminary site description: Groundwater flow simulations. Simpevarp area (version 1.1) modelled with CONNECTFLOW

    Hartley, Lee; Worth, David; Gylling, Bjoern; Marsic, Niko; Holmen, Johan

    2004-08-01

    The main objective of this study is to assess the role of known and unknown hydrogeological conditions for the present-day distribution of saline groundwater at the Simpevarp and Laxemar sites. An improved understanding of the paleo-hydrogeology is necessary in order to gain credibility for the Site Descriptive Model in general and the Site Hydrogeological Description in particular. This is to serve as a basis for describing the present hydrogeological conditions as well as predictions of future hydrogeological conditions. This objective implies a testing of: geometrical alternatives in the structural geology and bedrock fracturing, variants in the initial and boundary conditions, and parameter uncertainties (i.e. uncertainties in the hydraulic property assignment). This testing is necessary in order to evaluate the impact on the groundwater flow field of the specified components and to promote proposals of further investigations of the hydrogeological conditions at the site. The general methodology for modelling transient salt transport and groundwater flow using CONNECTFLOW that was developed for Forsmark has been applied successfully also for Simpevarp. Because of time constraints only a key set of variants were performed that focussed on the influences of DFN model parameters, the kinematic porosity, and the initial condition. Salinity data in deep boreholes available at the time of the project was too limited to allow a good calibration exercise. However, the model predictions are compared with the available data from KLX01 and KLX02 below. Once more salinity data is available it may be possible to draw more definite conclusions based on the differences between variants. At the moment though the differences should just be used understand the sensitivity of the models to various input parameters

  17. Preliminary site description. Simpevarp area - version 1.1

    Winberg, Anders [ed.

    2004-08-01

    Site characterisation in the Oskarshamn area is currently conducted at two adjoining localities, the Simpevarp and Laxemar subareas. This report presents the interim version (model version Simpevarp 1.1 of S1.1 for short) of the preliminary Site Descriptive Model for the Simpevarp subarea. The basis for this interim version is quality-assured, geoscientific and ecological field data from the Simpevarp subarea (and in part from the Laxemar area) available in the SKB SICADA and GIS data bases as of July 1, 2003 as well as version 0 of the Site Descriptive Model. The new data collected during the initial site investigation phase up till the date of data freeze S1.1 constitute the basis for the update of version 0 to version S1.1. These data include results from surface investigations in the subarea with its regional environment and from drillings and investigations in boreholes. The surface-based data sets were, in a relative sense, extensive compared with data sets from boreholes, were the information largely was limited to information from one c. 1,000 m deep cored borehole (KSH01A), two existing cored boreholes and three c. 200 m deep percussion-drilled boreholes. Discipline-specific models are developed for the selected regional and local model volumes and these models are subsequently integrated into a unified site description. The current methodologies for developing discipline-specific models and their integration are documented in methodology/ strategy reports. In the present work, the procedures and guidelines given in those reports were followed to the extent possible given the data and information available at the time of data freeze for model version S1.1. Compared with version 0 there are considerable additional features in the version S1.1, especially in the geological description and in the description of the near surface. The geological models of lithology and deformation zones are based on borehole information and surface data of much higher

  18. Radon as a groundwater tracer in Forsmark and Laxemar

    Grolander, Sara

    2009-10-15

    Radon concentrations were measured in different water types in Forsmark and Laxemar during the site investigation and within this study. From these measurements it can be concluded that large differences between surface water, near surface groundwater and deep groundwater can be found in both Laxemar and Forsmark. The differences in radon concentrations between different water types are used in this study to detect interactions between surface water, near surface water and deep groundwater. From the radon measurements it can also be concluded that radon concentration in deep groundwater varies largely with depth. These variations with depth are probably caused by groundwater flow in conductive fracture zones in the bedrock. The focus of this study has been the radon concentration of near surface groundwater and the interaction between near surface groundwater and deep groundwater. Radon measurements have been done using the RAD-7 radon detector within this study. It could be concluded that RAD-7 is a good technique for radon measurements and also easy to use in field. The radon concentrations measured in near surface groundwater in Laxemar within this study were low and homogenous. The variation in radon concentration has been analyses and compared to other parameters. Since the hypothesis of this study has been that there are differences in radon concentrations between recharging and discharging groundwater, the most important parameter to consider is the recharge/discharge field classification of the wells. No correlation between the recharge/discharge classifications of wells and the radon concentrations were found. The lack of correlation between groundwater flow patterns and radon concentration means that it is not possible to detect flow patterns in near surface groundwater using radon as a tracer in the Laxemar area. The lack of correlation can be caused by the fact that there are just a few wells located in areas classified as recharge area. It can also be

  19. Operative meteorological data base in Forsmark

    Appelgren, A.; Hallberg, B.; Nordlinder, S.

    1990-01-01

    This report describes how data collected during a field measurement campaign were analysed and compiled to create a data base for operative use. The data base gives information about the wind and the atmospheric stability at five locations around the Forsmark nuclear power plant. In the measurement campaign, sodar systems and a 100 m high tower at Forsmark were used. Temperature, wind speed and wind direction were measured by sensors on the tower, while wind speed and direction, and the standard deviation of the vertical wind, were monitored by the sodar systems. This gave meteorological data from several heights. At Forsmark, the temperature difference and the wind speed from the tower were used to determine the atmospheric stability. At the sodar locations, the stability was deduced by employing a scheme which considered the season, the time of day, the wind direction and the wind speed. To create the operative data base, the wind speeds and wind directions, respectively, from two locations at the time were correlated. A code for graphical and numerical presentation of the data from the data base was developed. A special system of warnings was included, featuring notification about phenomena such as sea breeze, warnings about large variation in the wind conditions within the area, and warnings for situations in which the meteorological conditions make the results from the atmospheric dispersion calculations uncertain. This feature was implemented to alert the user to the fact that ordinary dispersion and dose calculations, using meteorological data from a single point, might give erroneous results. The operative data base and the presentation code were integrated with the dispersion and dose calculation code AIRPAC/EMMA, which is to be used in case of increased releases from nuclear power plants. The possibility to use the data from the operative data base in the dispersion calculations was investigated. It was found that a modification of AIRPAC/EMMA, in such a

  20. Preliminary site description Simpevarp subarea - version 1.2

    Winberg, Anders [ed.

    2005-04-01

    The objectives of the version 1.2 site descriptive modelling (SDM) of the Simpevarp subarea are to produce and document an integrated description of the site and its regional environments based on the site-specific data available from the initial site investigations and to give recommendations on continued investigations on a continuous basis. The modelling work is based on primary data available at the time of the data freeze for Simpevarp 1.2, April 1, 2004. The local scale model area (24 km{sup 2}) for the Simpevarp 1.2 modelling encompasses both the Simpevarp and Laxemar subareas. The local model area is located in the centre of a regional scale model area (273 km{sup 2}). Surface ecosystem models in terms of pools and fluxes of carbon have been developed for the terrestrial (e.g. plants and animals) and limnic (e.g. algae and fish) systems using the Lake Frisksjoen drainage area. Furthermore, a first marine ecosystem model has been developed for the Basin Borholmsfjaerden. Three principal lithological domains have been defined in the subarea, an A domain that is dominated by the Aevroe granite, a domain B that is dominated by the fine-grained dioritoid, a C domain that is characterised by a mixture of of Aevroe granite and quartz monzodiorite. A fourth domain is made up a few scattered domains of diorite to gabbro. In total, 22 deformation zones with high confidence of occurrence have been interpreted in the local scale model area. The understanding of the interpreted deformation zones of the Simpevarp subarea is considered adequate to make a preliminary assessment of available storage volumes for a deep repository. High rock stresses do not appear to be a major concern for the Simpevarp subarea. The magnitude of the maximum principal stress at 500 m in the Simpevarp subarea is estimated at 10-22 MPa. The analysis of the thermal conductivity has developed considerably since Simpevarp 1.1. In terms of interpreted mean values for the identified lithological

  1. Preliminary site description Simpevarp subarea - version 1.2

    Winberg, Anders

    2005-04-01

    The objectives of the version 1.2 site descriptive modelling (SDM) of the Simpevarp subarea are to produce and document an integrated description of the site and its regional environments based on the site-specific data available from the initial site investigations and to give recommendations on continued investigations on a continuous basis. The modelling work is based on primary data available at the time of the data freeze for Simpevarp 1.2, April 1, 2004. The local scale model area (24 km 2 ) for the Simpevarp 1.2 modelling encompasses both the Simpevarp and Laxemar subareas. The local model area is located in the centre of a regional scale model area (273 km 2 ). Surface ecosystem models in terms of pools and fluxes of carbon have been developed for the terrestrial (e.g. plants and animals) and limnic (e.g. algae and fish) systems using the Lake Frisksjoen drainage area. Furthermore, a first marine ecosystem model has been developed for the Basin Borholmsfjaerden. Three principal lithological domains have been defined in the subarea, an A domain that is dominated by the Aevroe granite, a domain B that is dominated by the fine-grained dioritoid, a C domain that is characterised by a mixture of of Aevroe granite and quartz monzodiorite. A fourth domain is made up a few scattered domains of diorite to gabbro. In total, 22 deformation zones with high confidence of occurrence have been interpreted in the local scale model area. The understanding of the interpreted deformation zones of the Simpevarp subarea is considered adequate to make a preliminary assessment of available storage volumes for a deep repository. High rock stresses do not appear to be a major concern for the Simpevarp subarea. The magnitude of the maximum principal stress at 500 m in the Simpevarp subarea is estimated at 10-22 MPa. The analysis of the thermal conductivity has developed considerably since Simpevarp 1.1. In terms of interpreted mean values for the identified lithological domains, the

  2. Site study plan for Deep Hydronest Test Wells, Deaf Smith County Site, Texas: Preliminary draft

    1987-05-01

    Wells called Deep Hydronest Wells will be installed at six locations at the Deaf Smith County Site to characterize hydraulic parameters in the geologic column between the top of the San Andres Formation and the base of Pennsylvanian System. Three hydronests will be drilled during early stages of site characterization to provide data for performance assessment modeling. Four wells are proposed for each of these 3 nests. Results of drilling, testing, and preliminary modeling will direct drilling and testing activities at the last 3 nests. Two wells are proposed at each of the last 3 nests for a total of 18 wells. The Salt Repository Project (SRP) Networks specify the schedule under which this program will operate. Drilling and hydrologic testing of the first Deep Hydronest will begin early in the Surface Investigation Program. Drilling and testing of the first three Deep Hydronests will require about 18 months. After 12 months of evaluating and analyzing data from the first three hydronests, the remaining three hydronests will be drilled during a 12-month period. The Technical Field Services Contractor is responsible for conducting the field program. Samples and data will be handled and reported in accordance with established SRP procedures. A quality assurance program will be used to assure that activities affecting quality are performed correctly and that the appropriate documentation is maintained. 36 refs., 20 figs., 6 tabs

  3. Investigation of BWR stability in Forsmark 2

    Oguma, R.; Reisch, F.; Bergdahl, B.G.; Lorenzen, J.; Aakerhielm, F.; Kellner, S.

    1988-01-01

    A series of noise measurements have been conducted at the Forsmark-2 reactor during its start-up operation after the revision in 1987. The main purpose was to investigate the BWR stability problem based on noise analysis, i.e. the problem of resonant power oscillation with frequency of about 0.5 Hz, which tends to arise at high power and low core flow condition. The noise analysis was performed to estimate the noise source which gives rise to the power oscillation, to evaluate the stability condition of the Forsmark-2 reactor in terms of the decay ratio (DR), as well as to investigate a safety related problem in connection with the BWR stability. The results indicate that the power oscillation is due to dynamic coupling between the neutron kinetics and thermal-hydraulics via void reactivity feedback. The DR reached as high as ≅ 0.7 at 63% of the rated power and 4100 kg/s of the total core flow. An investigation was made for the noise recording which represents a strong pressure oscillation with a peak frequency at 0.33 Hz. The result suggests that such pressure oscillation, if the peak frequency coincided with that of the resonant power oscillation, might become a cause of scram. The present noise analysis indicates the importance of a BWR on-line surveillance system with functions like stability condition monitoring and control system diagnosis. (orig.)

  4. Final disposal Forsmark, Simpevarp and Laxemar. Inflow of ground water and influence on hydrogeologic and hydrologic conditions; Slutfoervar Forsmark, Simpevarp och Laxemar. Inlaeckage av grundvatten samt paaverkan paa hydrogeologiska och hydrologiska foerhaallanden

    Werner, Kent [Golder Associates AB, Stockholm (Sweden)

    2006-10-15

    This report summarizes the description of the natural (uninfluenced) hydrogeological and hydrological conditions at the possible final repository locations Forsmark, Simpevarp and Laxemar. For each site, the description is based on SKB's site descriptions version 1.2. The report provides assessments of the inflow and the effects on the surroundings (groundwater drawdown and the associated area of influence) due to construction, operation, and closing of a repository for spent nuclear fuel at the above locations. The assessment of the effects of the repository on its surroundings is primarily based on calculation results from two numerical flow models, DarcyTools and MOUSESHE (for Simpevarp, only DarcyTools has been used). The basis for the modelling is SKB's site descriptions version 1.2, which will be updated in the form of new versions. Moreover, the models are based on a preliminary layout of the repository at each location. Hence, the flow models will be developed further when the site descriptions are updated. The results may also be affected by changes of the repository layout. The modelling projects have been performed in the same order as they are presented in the report (Forsmark, Simpevarp and Laxemar). Some aspects of the numerical models, and the coupling between them, have been developed and improved during the course of work. Examples on major differences between the models include the technique to simulate grouting in DarcyTools, and the possibility to visualize modelling results from this model, for instance on other types of background maps. The results show a small inflow and a small area of influence for a repository at Forsmark. The upper parts of the repository (c 100 m depth and upwards) give the largest contribution to the inflow and the area of influence. This indicates that the effects on the surroundings from the deep and the near surface parts of the repository can be analysed separately. For a repository at Simpevarp and

  5. A Preliminary Case Study for Rectenna Sites in Indonesia

    Purwanto, Y.; Collins, P.

    2004-12-01

    Electricity power generation using alternative energy sources in Indonesia has become an important policy. Until now, the contribution from alternative energy sources (especially from renewable energy sources) is very small, only about 1% of the total energy supply. It is expected that in the next 10 years this contribution will be raised to 20%. The development of renewable energy sources is primarily performed in remote areas, that are poor in infrastructure facilities. This is considered to be a good policy since there are many such remote areas in Indonesia that need development programs. The existence of Solar Power Satellite system will open a new horizon in alternative energy supply, including Indonesia, because of its higher efficiency compared to conventional terrestrial solar cells, with almost no influence from either climate or solar position. Like other countries in the world, Indonesia, although one of the largest mineral energy producers in the world (i.e. oil, coal, and natural gas), still gives attention to energy diversification programs, including solar energy utilization. SPS, being based on solar energy, could be a good choice. The Indonesian archipelago consists of thousands of islands (more than 13,000) and is the equatorial country with the longest equatorial extent (more than 5000 km). This condition is very good for energy reception from the SPS 2000 pilot plant since the energy transmitting system (spacetenna) will orbit above the equator. Along the equator there could be placed more than four receiving stations (rectenna), especially in remote areas. Thus, it is very important to consider the involvement of Indonesia in SPS energy reception research. This paper describes a preliminary study of the development possibilities in SPS energy reception in Indonesia. To define the rectenna sites and physical development aspect, this study considers some major aspects: environmental, technical, social, and economic aspects. Environmental aspects

  6. Geoscientific long-term prognosis. Preliminary safety analysis for the site Gorleben

    Mrugalla, Sabine

    2011-07-01

    The preliminary safety analysis of the site Gorleben includes the following chapters: (1) Introduction; (2) Aim and content of the geoscientific long-term prognosis for the site Gorleben; (3) Boundary conditions at the site Gorleben: climate; geomorphology; overlying rocks and adjoining rocks; hydrogeology; salt deposit Gorleben. (4) Probable future geological developments at the site Gorleben: supraregional developments with effects on the site Gorleben; glacial period developments; developments of the geomorphology, overlying and adjoining rocks; future developments of the hydrological systems at the site Gorleben; future saliniferous specific developments of the salt deposit Gorleben. (5) Commentary on the unlikely or excludable developments of the site Gorleben.

  7. Forsmark site investigation. Microorganisms in groundwater from boreholes KFM10A, KFM11A and KFM08D - numbers, viability, and metabolic diversity. Results from five sections 298.0-305.1 m and 478.0-487.5 m in KFM10A, 447.5-454.6 m in KFM11A, and 669.7-676.8 m and 828.4-835.5 m in KFM08D

    Pedersen, Karsten (Microbial Analytics Sweden AB, Goeteborg (SE))

    2007-09-15

    Microorganisms and their characteristic features were investigated while geochemically characterizing the groundwater, as part of the site investigation programme at Forsmark. The investigation consists of determining the total numbers of microorganisms, the concentration of adenosine-tri-phosphate (ATP), and the number of culturable heterotrophic aerobic bacteria (CHAB); also included is a method for determining the numbers of organisms belonging to different physiological groups, the most probable number (MPN) method. This investigation covered eight different groups, namely, nitrate-, iron-, manganese-, and sulphate-reducing bacteria, auto- and heterotrophic acetogens, and auto- and heterotrophic methanogens. The reproducibility of the MPN method was tested using groundwater from a depth of 450 m at the Aspo Hard Rock Laboratory and was found to be excellent. Samples were taken from boreholes KFM10A at 298.305 m and 478.487 m, KFM11A at 447.454 m, and KFM08D at 669.676 m and 828.835 m; the sampling dates were 2006-11-28, 2006-10-31, 2007-03-13, 2007-06-19, and 2007-05-02, respectively. The total number of cells (TNC) found in KFM10A groundwater was the highest so far found in a total of 19 analysed sections in the Forsmark area. In contrast, KFM08D-828 m and KFM11A-447 m had among the lowest numbers of cells found thus far. A large amount of ATP per cell indicates large, active cells. The average of all previous ATP/TNC ratios (n approx = 100) in deep groundwater was determined to be 0.43. The analysed groundwater samples from KFM10A-478 m and KFM08D-669 m had ATP/TNC ratios exceeding the overall average of 0.43 for deep groundwater. This suggests that the microorganisms in these groundwaters possessed viability and activity levels above the average for deep groundwater microorganisms. The ratios between the CHAB and NRB numbers found here suggest that there was no surface water contamination. The percentages of TNC culturable using the MPN method were in the 1

  8. Forsmark site investigation. Microorganisms in groundwater from boreholes KFM10A, KFM11A and KFM08D - numbers, viability, and metabolic diversity. Results from five sections 298.0-305.1 m and 478.0-487.5 m in KFM10A, 447.5-454.6 m in KFM11A, and 669.7-676.8 m and 828.4-835.5 m in KFM08D

    Pedersen, Karsten

    2007-09-01

    Microorganisms and their characteristic features were investigated while geochemically characterizing the groundwater, as part of the site investigation programme at Forsmark. The investigation consists of determining the total numbers of microorganisms, the concentration of adenosine-tri-phosphate (ATP), and the number of culturable heterotrophic aerobic bacteria (CHAB); also included is a method for determining the numbers of organisms belonging to different physiological groups, the most probable number (MPN) method. This investigation covered eight different groups, namely, nitrate-, iron-, manganese-, and sulphate-reducing bacteria, auto- and heterotrophic acetogens, and auto- and heterotrophic methanogens. The reproducibility of the MPN method was tested using groundwater from a depth of 450 m at the Aspo Hard Rock Laboratory and was found to be excellent. Samples were taken from boreholes KFM10A at 298.305 m and 478.487 m, KFM11A at 447.454 m, and KFM08D at 669.676 m and 828.835 m; the sampling dates were 2006-11-28, 2006-10-31, 2007-03-13, 2007-06-19, and 2007-05-02, respectively. The total number of cells (TNC) found in KFM10A groundwater was the highest so far found in a total of 19 analysed sections in the Forsmark area. In contrast, KFM08D-828 m and KFM11A-447 m had among the lowest numbers of cells found thus far. A large amount of ATP per cell indicates large, active cells. The average of all previous ATP/TNC ratios (n ≅ 100) in deep groundwater was determined to be 0.43. The analysed groundwater samples from KFM10A-478 m and KFM08D-669 m had ATP/TNC ratios exceeding the overall average of 0.43 for deep groundwater. This suggests that the microorganisms in these groundwaters possessed viability and activity levels above the average for deep groundwater microorganisms. The ratios between the CHAB and NRB numbers found here suggest that there was no surface water contamination. The percentages of TNC culturable using the MPN method were in the 1

  9. Monitoring Forsmark. Moose age composition, reproduction and antler development in Forsmark

    Cederlund, Goeran; Broman, Emil

    2011-05-01

    The moose (Alces alces) is an important game species in Forsmark, as well as in Sweden in general. Hunting on moose is subject to strict local regulations and restrictions within a management program. Such restrictions will have considerable effects on demography. This has led to a moose population in Forsmark with biased sex ratio with fewer adult males than females and a generally low average age. High hunting pressure on males has caused a low survival rate and the chance to survive more than five years is just a few percent. Restrictions in hunting pressure on females have caused a generally higher survival rate and a higher average age compared to males. Sex differences in body mass are normal compared to other populations in southern Sweden. Mean body mass of culled calves is an important measure of quality of the population, since it reflects the available food resources in the management area. Body mass among calves in Forsmark is generally low, indicating a deteriorated food resource due to either ambient population density and/or hampered food production in the forest. The average reproduction rate is normal compared to other populations in this part of Sweden. However, one year old females (yearlings) have a fairly low production of eggs per female (ovulation rate). As the yearlings constitute a considerable part of the population in Forsmark, their lowered ovulation rate will affect the rate of recruitment of calves to the local population. The moose population seems to have been subject to considerable variation in density during the last decade, which is probably a joint effect of changes in demography (hunting), changes in food resources due to forestry management and by food competition from other browsers in the area. Local managers believe that the population has reached such a low level (although not verified by surveys) that the number of moose has to be increased. It is vital to stress the importance of keeping up collection of data from the

  10. The potential for ore and industrial minerals in the Forsmark area

    Lindroos, Hardy [MIRAB Mineral Resurser AB, Uppsala (Sweden); Isaksson, Hans; Thunehed, Hans [GeoVista AB, Luleaa (Sweden)

    2004-03-01

    A survey has been made of existing information concerning the potential for ore and industrial minerals in and near the candidate area for a deep repository in Forsmark. A deep repository for spent nuclear fuel should not be located in a rock type or an area where mineral extraction might be considered in the future, since this would make it impossible to exploit this natural resource. Avoiding such areas reduces the risk that people in the future will come into contact with the deep repository through mineral prospecting or mining activities. The survey has made use of all the geoscientific information that was compiled in the more regional investigations in Oesthammar Municipality in 1996-97. In cooperation with the Geological Survey of Sweden (SGU), a new, more detailed mineral resources map has been prepared. The map shows areas with an ore potential that may be unsuitable or unfavourable for siting of a deep repository. The results of the recently completed geophysical helicopter surveys of the Forsmark area are presented in a special chapter. The judgement of the area's ore potential is in part based on the geophysical evaluation of these measurements. Furthermore, the survey obtained information from ongoing deep drillings from the site investigation in Forsmark. In order to better be able to judge the ore potential, the survey has initiated a geochemical investigation of activated soil samples, plus an ore geology sampling of a section in the deep borehole KFM02A, where a hydrothermally altered zone was detected in 2003.The first results from these samplings are presented in the report, which also discusses prospecting efforts in the area as well as relevant Swedish mining legislation. Some suggestions are made for further ore geology investigations. The mineral resources map shows that there is an elongate northwest-southeast zone south and southwest of the candidate area which has a potential for skarn iron ore, and possibly for copper and zinc

  11. The potential for ore and industrial minerals in the Forsmark area

    Lindroos, Hardy; Isaksson, Hans; Thunehed, Hans

    2004-03-01

    A survey has been made of existing information concerning the potential for ore and industrial minerals in and near the candidate area for a deep repository in Forsmark. A deep repository for spent nuclear fuel should not be located in a rock type or an area where mineral extraction might be considered in the future, since this would make it impossible to exploit this natural resource. Avoiding such areas reduces the risk that people in the future will come into contact with the deep repository through mineral prospecting or mining activities. The survey has made use of all the geoscientific information that was compiled in the more regional investigations in Oesthammar Municipality in 1996-97. In cooperation with the Geological Survey of Sweden (SGU), a new, more detailed mineral resources map has been prepared. The map shows areas with an ore potential that may be unsuitable or unfavourable for siting of a deep repository. The results of the recently completed geophysical helicopter surveys of the Forsmark area are presented in a special chapter. The judgement of the area's ore potential is in part based on the geophysical evaluation of these measurements. Furthermore, the survey obtained information from ongoing deep drillings from the site investigation in Forsmark. In order to better be able to judge the ore potential, the survey has initiated a geochemical investigation of activated soil samples, plus an ore geology sampling of a section in the deep borehole KFM02A, where a hydrothermally altered zone was detected in 2003.The first results from these samplings are presented in the report, which also discusses prospecting efforts in the area as well as relevant Swedish mining legislation. Some suggestions are made for further ore geology investigations. The mineral resources map shows that there is an elongate northwest-southeast zone south and southwest of the candidate area which has a potential for skarn iron ore, and possibly for copper and zinc, although

  12. Results from Marine geological investigations outside Forsmark

    Nyberg, Johan; Elhammer, Anders; Sohlenius, Gustav; Kjellin, Bernt; Nordgren, Paer (Geological Survey of Sweden (Sweden))

    2011-08-15

    A detailed marine geological survey was conducted in a 10 km2 large area outside Forsmark comprising hydro acoustic, 100 m spacing between survey lines, and groundtruthing. These data, together with reanalyzed survey data retrieved in 2002 from the same area, were used to produce maps of seabed and underlying bedrock surface morphology as well as horizontal and vertical extension of sediments. An esker is discovered running approximately in a north northwesterly-south southeasterly direction in the area, which may be causing submarine groundwater discharge. Pockmarks, which are caused by sediment gas of thermogenic and/or microbial origin, are detected in the area. In addition to the original commissioned survey, bedrock surface and seabed morphology as well as horizontal and vertical extension of sediments in a larger adjacent area were reanalyzed and produced from survey lines retrieved during a commission by SKB in 2002 and during SGUs regular mapping program in 2002, 2008 and 2009

  13. Results from Marine geological investigations outside Forsmark

    Nyberg, Johan; Elhammer, Anders; Sohlenius, Gustav; Kjellin, Bernt; Nordgren, Paer

    2011-08-01

    A detailed marine geological survey was conducted in a 10 km 2 large area outside Forsmark comprising hydro acoustic, 100 m spacing between survey lines, and groundtruthing. These data, together with reanalyzed survey data retrieved in 2002 from the same area, were used to produce maps of seabed and underlying bedrock surface morphology as well as horizontal and vertical extension of sediments. An esker is discovered running approximately in a north northwesterly-south southeasterly direction in the area, which may be causing submarine groundwater discharge. Pockmarks, which are caused by sediment gas of thermogenic and/or microbial origin, are detected in the area. In addition to the original commissioned survey, bedrock surface and seabed morphology as well as horizontal and vertical extension of sediments in a larger adjacent area were reanalyzed and produced from survey lines retrieved during a commission by SKB in 2002 and during SGUs regular mapping program in 2002, 2008 and 2009

  14. Quality control of GPS deformation data from Forsmark and analysis of crustal deformation in the local scale

    Ekman, Lennart; Ekman, Mats

    2013-03-01

    A network comprising seven GPS stations was established at Forsmark, Sweden, within about 10 km radius from the centre of the investigation area for a final repository for spent nuclear fuel with the purpose of monitoring slow rock motion. During the period November 2005 to December 2009, GPS data were collected in eighteen intermittent measurement campaigns, each with a duration of between three and seven days. As shown in Gustafson and Ljungberg (2010), the data expose a considerable scatter, indicating a non-linear variability of the GPS baseline velocities. However, the commission narrated in Gustafson and Ljungberg (2010) was restricted to account only for the field performance of the GPS measurement campaign and to present the resulting measurement data per se, merely supplemented with a linear regression solution for the baseline motions. The preliminary interpretation of GPS data in Gustafson and Ljungberg (2010) was in the present report followed by a closer examination where the non-linear variability is modelled as sinusoidal. Evidence for sinusoidal variations were also found in resulting data from GPS measurements at the Aespoe/Laxemar area at Oskarshamn (Sjoeberg et al. 2004), as well as in GPS data from several sites in western, middle and north-eastern Finland (Ollikainen et al. 2004, Ahola et al. 2008, Poutanen et al. 2010). We here postulate that the baseline velocities are characterized by a long-term linear drift superposed by a non-linear sinusoidal motion. This was modelled in two steps. Initially an Auto Regressive (AR) model was applied and the linear trends between the GPS stations were estimated. In a second step, an Auto Regressive Moving Average (ARMA) model was estimated for (almost) all baselines. The residuals between the original data and the one-step predictor for the ARMA model were then used to estimate new linear trends for the baselines. Our analysis of the Forsmark GPS data indicates relative motions more than 10 times slower

  15. Quality control of GPS deformation data from Forsmark and analysis of crustal deformation in the local scale

    Ekman, Lennart; Ekman, Mats [LE Geokonsult AB, Baelinge (Sweden)

    2013-03-15

    A network comprising seven GPS stations was established at Forsmark, Sweden, within about 10 km radius from the centre of the investigation area for a final repository for spent nuclear fuel with the purpose of monitoring slow rock motion. During the period November 2005 to December 2009, GPS data were collected in eighteen intermittent measurement campaigns, each with a duration of between three and seven days. As shown in Gustafson and Ljungberg (2010), the data expose a considerable scatter, indicating a non-linear variability of the GPS baseline velocities. However, the commission narrated in Gustafson and Ljungberg (2010) was restricted to account only for the field performance of the GPS measurement campaign and to present the resulting measurement data per se, merely supplemented with a linear regression solution for the baseline motions. The preliminary interpretation of GPS data in Gustafson and Ljungberg (2010) was in the present report followed by a closer examination where the non-linear variability is modelled as sinusoidal. Evidence for sinusoidal variations were also found in resulting data from GPS measurements at the Aespoe/Laxemar area at Oskarshamn (Sjoeberg et al. 2004), as well as in GPS data from several sites in western, middle and north-eastern Finland (Ollikainen et al. 2004, Ahola et al. 2008, Poutanen et al. 2010). We here postulate that the baseline velocities are characterized by a long-term linear drift superposed by a non-linear sinusoidal motion. This was modelled in two steps. Initially an Auto Regressive (AR) model was applied and the linear trends between the GPS stations were estimated. In a second step, an Auto Regressive Moving Average (ARMA) model was estimated for (almost) all baselines. The residuals between the original data and the one-step predictor for the ARMA model were then used to estimate new linear trends for the baselines. Our analysis of the Forsmark GPS data indicates relative motions more than 10 times slower

  16. Regional hydrogeological simulations. Numerical modelling using ConnectFlow. Preliminary site description Simpevarp sub area - version 1.2

    Hartley, Lee; Hoch, Andrew; Hunter, Fiona; Jackson, Peter [Serco Assurance, Risley (United Kingdom); Marsic, Niko [Kemakta Konsult, Stockholm (Sweden)

    2005-02-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) carries out site investigations in two different candidate areas in Sweden with the objective of describing the in situ conditions for a bedrock repository for spent nuclear fuel. The two candidate areas are named Forsmark and Simpevarp. The site characterisation work is divided into two phases, an initial site investigation phase (IPLU) and a complete site investigation phase (KPLU). The results of IPLU are used as a basis for deciding on a subsequent KPLU phase. On the basis of the KPLU investigations a decision is made as to whether detailed characterisation will be performed (including sinking of a shaft).An integrated component in the site characterisation work is the development of site descriptive models. These comprise basic models in three dimensions with an accompanying text description. Central in the modelling work is the geological model which provides the geometrical context in terms of a model of deformation zones and the rock mass between the zones. Using the geological and geometrical description models as a basis, descriptive models for other geo-disciplines (hydrogeology, hydro-geochemistry, rock mechanics, thermal properties and transport properties) will be developed. Great care is taken to arrive at a general consistency in the description of the various models and assessment of uncertainty and possible needs of alternative models.Here, a numerical model is developed on a regional-scale (hundreds of square kilometres) to understand the zone of influence for groundwater flow that effects the Simpevarp area. Transport calculations are then performed by particle tracking from a local-scale release area (tens of square kilometres) to identify potential discharge areas for the site. The transport from the two site-scale release areas (a few square kilometres) at the Simpevarp site and the Laxemar site are also considered more specifically and using greater grid resolution.The main

  17. Removal of groundwater from final repository in Forsmark. Description of consequences for nature values and forest production; Bortledande av grundvatten fraan slutfoervarsanlaeggningen i Forsmark. Beskrivning av konsekvenser foer naturvaerden och skogsproduktion

    Hamren, Ulrika; Collinder, Per; Allmer, Johan (Ekologigruppen AB (Sweden))

    2010-11-15

    The Swedish Nuclear Fuel and Waste Management Co (SKB) has chosen Forsmark in the Municipality of Oesthammar as site for the final repository for spent nuclear fuel. This report describes consequences for nature values and forestry due to groundwater diversion during construction and operation of the repository. The report concerns nature values that depend on, or are favoured by, a groundwater table close to or above the ground surface

  18. Site characterization and validation. Stage 2 - Preliminary predictions

    Olsson, O.; Black, J.H.; Gale, J.E.; Holmes, D.C.

    1989-05-01

    The Site Characterization and Validation (SCV) project is designed to assess how well we can characterize a volume of rock prior to using it as a repository. The programme of work focuses on the validation of the techniques used in site characterization. The SCV project contains 5 stages of work arranged in two 'cycles' of data-gathering, prediction, and validation. The first stage of work has included drilling of 6 boreholes (N2, N3, N4, W1, W2 and V3) and measurements of geology, fracture characteristics, stess, single borehole geophysical logging, radar, seismics and hydrogeology. The rock at the SCV site is granite with small lithological variations. Based essentially on radar and seismic results 5 'fracture zones' have been identified, named GA, GB, GC, GH and GI. They all extend acroos the entire SCV site. They aer basically in in two groups (GA, GB, GC and GH, GI). The first group are aligned N40 degree E with a dip of 35 degree to the south. The second group are aligned approximately N10 degree W dipping 60 degree E. From the stochastic analysis of the joint data it was possible to identify three main fracture orientation clusters. The orientation of two of these clusters agree roughly with orientation of the main features. Cluster B has roughly the same orientation as GH and GI, while features GA, GB and GC have an orientation similar to the more loosely defined cluster C. The orientation of the third cluster (A) is northwest with a dip to northeast. It is found that 94% of all measured hydraulic transmissivity is accounted for by 4% of the tested rock, not all of this 'concentrated' transmissivity is with the major features defined by geophysics. When the hydraulic connections across the site are examied they show that there are several welldefined zones which permit rapid transmission of hydraulic signals. These are essentially from the northeast to the southwest. (66 figs., 21 tabs., 33 refs.)

  19. Preliminary interpretation of thermal data from the Nevada Test Site

    Sass, J.H.; Lachenbruch, A.H.

    1982-01-01

    Analysis of data from 60 wells in and around the Nevada Test Site, including 16 in the Yucca Mountain area, indicates a thermal regime characterized by large vertical and lateral gradients in heat flow. Estimates of heat flow indicate considerable variation on both regional and local scales. The variations are attributable primarily to hydrologic processes involving interbasin flow with a vertical component of (seepage) velocity (volume flux) of a few mm/yr. Apart from indicating a general downward movement of water at a few mm/yr, the reults from Yucca Mountain are as yet inconclusive. The purpose of the study was to determine the suitability of the area for proposed repository sites

  20. Electrical Dynamic Simulation Activities in Forsmark NPP

    Lamell, Per

    2015-01-01

    The original power system analysis was done in the seventies in former ASEA AB software. For approximate twenty years no major new studies was done because of limited numbers of renewal projects. In the end of the nineties the plant started to update the selectivity planning and study of the loading of the safety bus-bars. The simulation and start of the development of simulation models was done in a tool named Simpow. Simpow was also an ASEA/ABB AB software developed from the program used in the seventies. To continue to work with Simpow was a decision made after doing an extensive review of on the marked available commercially software. Also at that time we start to do our first attempt building electrical simulation models of unit 1 and 2 according to the original documentation. The development of models for the unit 1, 2 and 3 became more intensive some years after the millennium. Partly because of event July 25, 2006 and also because of the renewal of unit 1 and 2 and had subsequently been initiated for unit 3 also. Today we have initiated a conversion of our models to a new program called PowerFactory. That due to the withdrawal of support and development on SIMPOW a couple of years ago. To development relevance, accuracy and detail, models are an important issue for FKA (Forsmark Kraftgrupp AB). The model is initially created according to the plant documentation and also including requested information from the original supplier. Continued development and updates of the model is done according to the data received from the contractors via the demands according to requirements in our technical documents on different electrical components in renewal projects. The development of the model is driven by known weaknesses, depending of the type of studies and necessary data related to events. An important part that will be described is to have a verified simulation tool and validated models. An example is that the models have been validated by making start and

  1. Variable-density groundwater flow simulations and particle tracking. Numerical modelling using DarcyTools. Preliminary site description of the Simpevarp area, version 1.1

    Follin, Sven [SF GeoLogic AB, Stockholm (Sweden); Stigsson, Martin; Berglund, Sten [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Svensson, Urban [Computer-aided Fluid Engineering AB, Norrkoeping (Sweden)

    2004-12-01

    SKB is conducting site investigations for a high-level nuclear waste repository in fractured crystalline rocks at two coastal areas in Sweden, Forsmark and Simpevarp. The investigations started in 2002 and have been planned since the late 1990s. The work presented here investigates the possibility of using hydrogeochemical measurements in deep boreholes to reduce parameter uncertainty in a regional modelling of groundwater flow in fractured rock. The work was conducted with the aim of improving the palaeohydrogeological understanding of the Simpevarp area and to give recommendations to the preparations of the next version of the Preliminary Site Description (1.2). The study is based on a large number of numerical simulations of transient variable density groundwater flow through a strongly heterogeneous and anisotropic medium. The simulations were conducted with the computer code DarcyTools, the development of which has been funded by SKB. DarcyTools is a flexible porous media code specifically designed to treat groundwater flow and salt transport in sparsely fractured crystalline rock and it is noted that some of the features presented in this report are still under development or subjected to testing and verification. The simulations reveal the sensitivity of the results to different hydrogeological modelling assumptions, e.g. the sensitivity to the initial groundwater conditions at 10,000 BC, the size of the model domain and boundary conditions, and the hydraulic properties of deterministically and stochastically modelled deformation zones. The outcome of these simulations was compared with measured salinities and calculated relative proportions of different water types (mixing proportions) from measurements in two deep core drilled boreholes in the Laxemar subarea. In addition to the flow simulations, the statistics of flow related transport parameters were calculated for particle flowpaths from repository depth to ground surface for two subareas within the

  2. Variable-density groundwater flow simulations and particle tracking. Numerical modelling using DarcyTools. Preliminary site description of the Simpevarp area, version 1.1

    Follin, Sven; Stigsson, Martin; Berglund, Sten; Svensson, Urban

    2004-12-01

    SKB is conducting site investigations for a high-level nuclear waste repository in fractured crystalline rocks at two coastal areas in Sweden, Forsmark and Simpevarp. The investigations started in 2002 and have been planned since the late 1990s. The work presented here investigates the possibility of using hydrogeochemical measurements in deep boreholes to reduce parameter uncertainty in a regional modelling of groundwater flow in fractured rock. The work was conducted with the aim of improving the palaeohydrogeological understanding of the Simpevarp area and to give recommendations to the preparations of the next version of the Preliminary Site Description (1.2). The study is based on a large number of numerical simulations of transient variable density groundwater flow through a strongly heterogeneous and anisotropic medium. The simulations were conducted with the computer code DarcyTools, the development of which has been funded by SKB. DarcyTools is a flexible porous media code specifically designed to treat groundwater flow and salt transport in sparsely fractured crystalline rock and it is noted that some of the features presented in this report are still under development or subjected to testing and verification. The simulations reveal the sensitivity of the results to different hydrogeological modelling assumptions, e.g. the sensitivity to the initial groundwater conditions at 10,000 BC, the size of the model domain and boundary conditions, and the hydraulic properties of deterministically and stochastically modelled deformation zones. The outcome of these simulations was compared with measured salinities and calculated relative proportions of different water types (mixing proportions) from measurements in two deep core drilled boreholes in the Laxemar subarea. In addition to the flow simulations, the statistics of flow related transport parameters were calculated for particle flowpaths from repository depth to ground surface for two subareas within the

  3. Preliminary Safety Analysis of the Gorleben Site: Geological Database - 13300

    Weber, Jan Richard; Mrugalla, Sabine; Dresbach, Christian; Hammer, Joerg

    2013-01-01

    The Gorleben salt dome is 4 km wide and nearly 15 km long. It is composed of different salt rock types of the Zechstein (Upper Permian) series and extends to the Zechstein basis in a depth of more than 3 km. In the course of the salt dome formation the salt was moved several kilometers. During the uplift of the salt the initially plane-bedded strata of the Zechstein series were extensively folded. In this process anhydrite as a competent layer was broken to isolated blocks. In the core of the salt dome the Hauptsalz, which is characterized by a particularly high creeping capacity, forms a homogeneous halite body with a volume of several cubic kilometres. The Hauptsalz contains gaseous and liquid hydrocarbons in separated zones of decimeter to meter dimensions. The overall hydrocarbon content is far below 0.01 %. At the flanks the salt dome consists of salt rocks with lower creeping capacities. Brine reservoirs with fluid volumes in the range of liters to hundreds of cubic meters exist in certain regions of this part of the salt dome. The water content of the Hauptsalz is below 0.02 %. Interconnected pores do not exist in the salt rock outside of fluid bearing or fractured areas, i.e. the salt rock is impermeable. The exploration of the Gorleben site as a potential site for a HLW-repository started in 1979 and is still in progress. To date no scientific findings contest the suitability of the site for a safe HLW-repository. (authors)

  4. Construction experiences from underground works at Forsmark. Compilation Report

    Carlsson, Anders [Vattenfall Power Consultant AB, Stockholm (Sweden); Christiansson, Rolf [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)

    2007-02-15

    The main objective with this report, the Construction Experience Compilation Report (CECR), is to compile experiences from the underground works carried out at Forsmark, primarily construction experiences from the tunnelling of the two cooling water tunnels of the Forsmark nuclear power units 1, 2 and 3, and from the underground excavations of the undersea repository for low and intermediate reactor waste, SFR. In addition, a brief account is given of the operational experience of the SFR on primarily rock support solutions. The authors of this report have separately participated throughout the entire construction periods of the Forsmark units and the SFR in the capacity of engineering geologists performing geotechnical mapping of the underground excavations and acted as advisors on tunnel support; Anders Carlsson participated in the construction works of the cooling water tunnels and the open cut excavations for Forsmark 1, 2 and 3 (geotechnical mapping) and the Forsmark 3 tunnel (advise on tunnel support). Rolf Christiansson participated in the underground works for the SFR (geotechnical mapping, principal investigator for various measurements and advise on tunnel support and grouting). The report is to a great extent based on earlier published material as presented in the list of references. But it stands to reason that, during the course of the work with this report, unpublished notes, diaries, drawings, photos and personal recollections of the two authors have been utilised in order to obtain such a complete compilation of the construction experiences as possible.

  5. Construction experiences from underground works at Forsmark. Compilation Report

    Carlsson, Anders; Christiansson, Rolf

    2007-02-01

    The main objective with this report, the Construction Experience Compilation Report (CECR), is to compile experiences from the underground works carried out at Forsmark, primarily construction experiences from the tunnelling of the two cooling water tunnels of the Forsmark nuclear power units 1, 2 and 3, and from the underground excavations of the undersea repository for low and intermediate reactor waste, SFR. In addition, a brief account is given of the operational experience of the SFR on primarily rock support solutions. The authors of this report have separately participated throughout the entire construction periods of the Forsmark units and the SFR in the capacity of engineering geologists performing geotechnical mapping of the underground excavations and acted as advisors on tunnel support; Anders Carlsson participated in the construction works of the cooling water tunnels and the open cut excavations for Forsmark 1, 2 and 3 (geotechnical mapping) and the Forsmark 3 tunnel (advise on tunnel support). Rolf Christiansson participated in the underground works for the SFR (geotechnical mapping, principal investigator for various measurements and advise on tunnel support and grouting). The report is to a great extent based on earlier published material as presented in the list of references. But it stands to reason that, during the course of the work with this report, unpublished notes, diaries, drawings, photos and personal recollections of the two authors have been utilised in order to obtain such a complete compilation of the construction experiences as possible

  6. Modelling of temperature in deep boreholes and evaluation of geothermal heat flow at Forsmark and Laxemar

    Sundberg, Jan; Back, Paer-Erik; Laendell, Maerta; Sundberg, Anders (GEO INNOVA AB, Linkoeping (Sweden))

    2009-06-15

    This report presents modelling of temperature and temperature gradients in boreholes in Laxemar and Forsmark and fitting to measured temperature data. The modelling is performed with an analytical expression including thermal conductivity, thermal diffusivity, heat flow, internal heat generation and climate events in the past. As a result of the fitting procedure it is also possible to evaluate local heat flow values for the two sites. However, since there is no independent evaluation of the heat flow, uncertainties in for example thermal conductivity, diffusivity and the palaeoclimate temperature curve are transferred into uncertainties in the heat flow. Both for Forsmark and Laxemar, reasonably good fits were achieved between models and data on borehole temperatures. However, none of the general models achieved a fit within the 95% confidence intervals of the measurements. This was achieved in some cases for the additional optimised models. Several of the model parameters are uncertain. A good model fit does not automatically imply that 'correct' values have been used for these parameters. Similar model fits can be expected with different sets of parameter values. The palaeoclimatically corrected surface mean heat flow at Forsmark and Laxemar is suggested to be 61 and 56 mW/m2 respectively. If all uncertainties are combined, including data uncertainties, the total uncertainty in the heat flow determination is judged to be within +12% to -14% for both sites. The corrections for palaeoclimate are quite large and verify the need of site-specific climate descriptions. Estimations of the current ground surface temperature have been made by extrapolations from measured temperature logging. The mean extrapolated ground surface temperature in Forsmark and Laxemar is estimated to 6.5 deg and 7.3 deg C respectively. This is approximately 1.7 deg C higher for Forsmark, and 1.6 deg C higher for Laxemar compared to data in the report SKB-TR-06-23. Comparison with

  7. Modelling of temperature in deep boreholes and evaluation of geothermal heat flow at Forsmark and Laxemar

    Sundberg, Jan; Back, Paer-Erik; Laendell, Maerta; Sundberg, Anders

    2009-05-01

    This report presents modelling of temperature and temperature gradients in boreholes in Laxemar and Forsmark and fitting to measured temperature data. The modelling is performed with an analytical expression including thermal conductivity, thermal diffusivity, heat flow, internal heat generation and climate events in the past. As a result of the fitting procedure it is also possible to evaluate local heat flow values for the two sites. However, since there is no independent evaluation of the heat flow, uncertainties in for example thermal conductivity, diffusivity and the palaeoclimate temperature curve are transferred into uncertainties in the heat flow. Both for Forsmark and Laxemar, reasonably good fits were achieved between models and data on borehole temperatures. However, none of the general models achieved a fit within the 95% confidence intervals of the measurements. This was achieved in some cases for the additional optimised models. Several of the model parameters are uncertain. A good model fit does not automatically imply that 'correct' values have been used for these parameters. Similar model fits can be expected with different sets of parameter values. The palaeoclimatically corrected surface mean heat flow at Forsmark and Laxemar is suggested to be 61 and 56 mW/m 2 respectively. If all uncertainties are combined, including data uncertainties, the total uncertainty in the heat flow determination is judged to be within +12% to -14% for both sites. The corrections for palaeoclimate are quite large and verify the need of site-specific climate descriptions. Estimations of the current ground surface temperature have been made by extrapolations from measured temperature logging. The mean extrapolated ground surface temperature in Forsmark and Laxemar is estimated to 6.5 deg and 7.3 deg C respectively. This is approximately 1.7 deg C higher for Forsmark, and 1.6 deg C higher for Laxemar compared to data in the report SKB-TR-06-23. Comparison with air

  8. Towards understanding household-level forest reliance in Cambodia - study sites, methods, and preliminary findings

    Ra, Koy; Pichdara, Lonn; Dararath, Yem

    There is growing international interest in the role of forests in poverty prevention and reduction. In consequence, this broad area of investigation has been subject to increased research; one major international research project is that facilitated by the Poverty Environment Network (PEN). This ......). This project covers a large number of sites in 26 countries throughout the tropics. The present report contains contextual details, methodological information and preliminary findings for the PEN sites in Cambodia....

  9. Chemical Analysis of the Moon at the Surveyor VII Landing Site: Preliminary Results.

    Turkevich, A L; Franzgrote, E J; Patterson, J H

    1968-10-04

    The alpha-scattering experiment aboard Surveyor VII has provided a chemical analysis of the moon in the area of the crater Tycho. The preliminary results indicate a chemical composition similar to that already found at two mare sites, but with a lower concentration of elements of the iron group (titanium through copper).

  10. Safety improvement plant modifications at Forsmark 3, 1986-1995

    Kjellander, M. [Kaernkraftsaekerhet och utbildning, Nykoeping (Sweden)

    1998-10-01

    All important plant modifications implemented in safety-related equipment or software at Forsmark 3 are compiled in this report. The report covers the period from the start of commercial operation in 1985 up to and including 1995. The plant modifications, which were carried out by different suppliers during the guarantee period, are not included in the report since they have not been administered by the Forsmark organisation. The report contains references to relevant modification notices and to files and file divider numbers. These data refer to the Safety Department central archives. The report is based on Forsmark 3 Technical Specifications (STF) which means that Chapter 3 is divided into the same sections as in the STF. Modifications, which cannot be directly attributed to any specific STF chapter, and major modifications are described separately

  11. BWR-stability investigation at Forsmark 1

    Bergdahl, B.G.; Reisch, F.; Oguma, R.; Lorenzen, J.; Aakerhielm, F.

    1988-01-01

    A series of noise measurements have been conducted at Forsmark 1 during start-up operation after the revision summer '87. The main purpose was to investigate BWR-stability problems, i.e. resonant power oscillations of 0.5 Hz around 65% power and 4100 kg/s core flow, which tend to arise at high power and low core flow conditions. The analysis was performed to estimate the noise source which gives rise to the oscillation, to evaluate the measure of stability, i.e. the Decay Ratio (Dr) as well as to investigate other safety related problems. The result indicates that the oscillation is due to the dynamic coupling between the neutron kinetics and thermal hydraulics via void reactivity feedback. The Dr ranged between values of 0.7 and > 0.9, instead of expected 0.6 (Dr=1 is defined as instability). These high values imply that the core cannot suppress oscillations fast enough and a small perturbation can cause scram. Further it was found that the entire core is oscillating in phase (LPRM's) with varying strength where any connection to the consequences of different fuel (8x8, 9x9) being present simultaneously cannot be excluded. This report elucidates the importance of an on-line BWR-stability surveillance system with functions like stability condition monitoring and control system diagnosis. (orig.)

  12. Elemental composition of a deep sediment core from Lake Stocksjoen in the Forsmark area

    Stroemgren, Maarten [Umeaa Univ. (Sweden). Dept. of Ecology and Environmental Sciences; Brunberg, Anna-Kristina [Uppsala Univ. (Sweden). Dept. of Ecology and Evolution/Limnology

    2006-10-15

    A deep sediment core was taken from Lake Stocksjoen, situated within the Forsmark site investigation area. The 55 cm long sediment core, representing the entire history of the lake (approx 430 years) was sliced in 5 cm portions and analysed for various chemical elements, using ICP-MS technique. In total, 54 different elements - classified as main elements, heavy metals and trace elements - were analysed. In general terms, three different patterns of stratigraphy were derived from all the analysed elements. Calcium, manganese, lead and mercury occurred in highest concentrations in the upper sediments (<30 cm depth). Phosphorus, zinc, cadmium, antimony, tin and strontium occurred in more even proportions throughout the sediment core. All the other elements were substantially reduced in the upper parts (<30 cm) compared to the deeper parts of the sediment core. Metals that are considered as airborne pollutants were found in low or moderate concentrations. This is in concert with other investigations of pollutants that have been performed in the Forsmark area. The sediment of Lake Stocksjoen is highly organic, and has been so during the entire history of the lake. Much of the organic Material seems to be refractory and less susceptible for mineralisation and respiration during the prevailing environmental conditions. This corresponds well with the characteristic gelatinous cyanophycee gyttja found in the lower parts of the sediment core. Although speculative, the pronounced changes in elemental composition of the sediment at 30 cm depth may correspond to the final isolation of the lake from the Baltic Sea, which occurred approximately 230 years ago. The deeper parts (below 30 cm depth) thus may represent the time period with regular intrusions of brackish water into the lake basin. One important factor governing the environmental conditions and the resulting elemental composition of the sediment is the unusually thick 'microbial mat', which is characteristic

  13. Hydrogeochemical evaluation. Preliminary site description Laxemar subarea - version 1.2

    Laaksoharju, Marcus

    2006-04-01

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Simpevarp and Forsmark, on the eastern coast of Sweden to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 for Laxemar subarea which represents the third evaluation of the available Simpevarp area groundwater analytical data collected up to November, 2004. Model version 1.2 focusses on improving the methodology and tools used for evaluating the hydrochemistry combined with a sensitivity and uncertainty analysis of the available data. The major goal has been to consolidate groundwater geochemical understanding and the models used at the site. The complex groundwater evolution and patterns at Simpevarp are a result of many factors such as: a) the present-day topography and proximity to the Baltic Sea, b) past changes in hydrogeology related to glaciation/deglaciation, land uplift and repeated marine/lake water regressions/transgressions, and c) organic or inorganic alteration of the groundwater composition caused by microbial processes or water/rock interactions. The sampled groundwaters reflect to various degrees processes relating to modern or ancient water/rock interactions and mixing. The groundwater flow regimes at Laxemar/Simpevarp are considered local and extend down to depths of around 600-1,000 m depending on local topography. Close to the Baltic Sea coastline where topographical variation is small, groundwater flow penetration to depth will subsequently be less marked. In contrast, the Laxemar subarea is characterised by higher topography resulting in a much more dynamic groundwater circulation which appears to extend to 1,000 m depth in the vicinity of borehole KLX02. The marked differences in the groundwater flow regimes between the Laxemar and Simpevarp are reflected in the groundwater chemistry where four major hydrochemical

  14. Hydrogeochemical evaluation. Preliminary site description Laxemar subarea - version 1.2

    Laaksoharju, Marcus (ed.) [Geopoint AB, Stockholm (Sweden)

    2006-04-15

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Simpevarp and Forsmark, on the eastern coast of Sweden to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 for Laxemar subarea which represents the third evaluation of the available Simpevarp area groundwater analytical data collected up to November, 2004. Model version 1.2 focusses on improving the methodology and tools used for evaluating the hydrochemistry combined with a sensitivity and uncertainty analysis of the available data. The major goal has been to consolidate groundwater geochemical understanding and the models used at the site. The complex groundwater evolution and patterns at Simpevarp are a result of many factors such as: a) the present-day topography and proximity to the Baltic Sea, b) past changes in hydrogeology related to glaciation/deglaciation, land uplift and repeated marine/lake water regressions/transgressions, and c) organic or inorganic alteration of the groundwater composition caused by microbial processes or water/rock interactions. The sampled groundwaters reflect to various degrees processes relating to modern or ancient water/rock interactions and mixing. The groundwater flow regimes at Laxemar/Simpevarp are considered local and extend down to depths of around 600-1,000 m depending on local topography. Close to the Baltic Sea coastline where topographical variation is small, groundwater flow penetration to depth will subsequently be less marked. In contrast, the Laxemar subarea is characterised by higher topography resulting in a much more dynamic groundwater circulation which appears to extend to 1,000 m depth in the vicinity of borehole KLX02. The marked differences in the groundwater flow regimes between the Laxemar and Simpevarp are reflected in the groundwater chemistry where four major

  15. Preliminary Hazard Classification for the Remediation of the 100-B/C Area Remaining Sites (Confirmatory Sampling Effort)

    Routt, T.M.

    2000-01-01

    This document provides the preliminary hazard classification for the sampling and characterization activities to be conducted at the 100-B/C confirmatory sampling effort sites in support of remedial design and eventual remediation of these sites

  16. Preliminary siting activities for new waste handling facilities at the Idaho National Engineering Laboratory

    Taylor, D.D.; Hoskinson, R.L.; Kingsford, C.O.; Ball, L.W.

    1994-09-01

    The Idaho Waste Processing Facility, the Mixed and Low-Level Waste Treatment Facility, and the Mixed and Low-Level Waste Disposal Facility are new waste treatment, storage, and disposal facilities that have been proposed at the Idaho National Engineering Laboratory (INEL). A prime consideration in planning for such facilities is the selection of a site. Since spring of 1992, waste management personnel at the INEL have been involved in activities directed to this end. These activities have resulted in the (a) identification of generic siting criteria, considered applicable to either treatment or disposal facilities for the purpose of preliminary site evaluations and comparisons, (b) selection of six candidate locations for siting,and (c) site-specific characterization of candidate sites relative to selected siting criteria. This report describes the information gathered in the above three categories for the six candidate sites. However, a single, preferred site has not yet been identified. Such a determination requires an overall, composite ranking of the candidate sites, which accounts for the fact that the sites under consideration have different advantages and disadvantages, that no single site is superior to all the others in all the siting criteria, and that the criteria should be assigned different weighing factors depending on whether a site is to host a treatment or a disposal facility. Stakeholder input should now be solicited to help guide the final selection. This input will include (a) siting issues not already identified in the siting, work to date, and (b) relative importances of the individual siting criteria. Final site selection will not be completed until stakeholder input (from the State of Idaho, regulatory agencies, the public, etc.) in the above areas has been obtained and a strategy has been developed to make a composite ranking of all candidate sites that accounts for all the siting criteria.

  17. Preliminary siting activities for new waste handling facilities at the Idaho National Engineering Laboratory

    Taylor, D.D.; Hoskinson, R.L.; Kingsford, C.O.; Ball, L.W.

    1994-09-01

    The Idaho Waste Processing Facility, the Mixed and Low-Level Waste Treatment Facility, and the Mixed and Low-Level Waste Disposal Facility are new waste treatment, storage, and disposal facilities that have been proposed at the Idaho National Engineering Laboratory (INEL). A prime consideration in planning for such facilities is the selection of a site. Since spring of 1992, waste management personnel at the INEL have been involved in activities directed to this end. These activities have resulted in the (a) identification of generic siting criteria, considered applicable to either treatment or disposal facilities for the purpose of preliminary site evaluations and comparisons, (b) selection of six candidate locations for siting,and (c) site-specific characterization of candidate sites relative to selected siting criteria. This report describes the information gathered in the above three categories for the six candidate sites. However, a single, preferred site has not yet been identified. Such a determination requires an overall, composite ranking of the candidate sites, which accounts for the fact that the sites under consideration have different advantages and disadvantages, that no single site is superior to all the others in all the siting criteria, and that the criteria should be assigned different weighing factors depending on whether a site is to host a treatment or a disposal facility. Stakeholder input should now be solicited to help guide the final selection. This input will include (a) siting issues not already identified in the siting, work to date, and (b) relative importances of the individual siting criteria. Final site selection will not be completed until stakeholder input (from the State of Idaho, regulatory agencies, the public, etc.) in the above areas has been obtained and a strategy has been developed to make a composite ranking of all candidate sites that accounts for all the siting criteria

  18. Hydrogeochemical evaluation for Simpevarp model version 1.2. Preliminary site description of the Simpevarp area

    Laaksoharju, Marcus

    2004-12-01

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Simpevarp and Forsmark, to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 which represents the second evaluation of the available Simpevarp groundwater analytical data collected up to April, 2004. The deepest fracture groundwater samples with sufficient analytical data reflected depths down to 1.7 km. Model version 1.2 focusses on geochemical and mixing processes affecting the groundwater composition in the uppermost part of the bedrock, down to repository levels, and eventually extending to 1000 m depth. The groundwater flow regimes at Laxemar/Simpevarp are considered local and extend down to depths of around 600-1000 m depending on local topography. The marked differences in the groundwater flow regimes between Laxemar and Simpevarp are reflected in the groundwater chemistry where four major hydrochemical groups of groundwaters (types A-D) have been identified: TYPE A: This type comprises dilute groundwaters ( 3 type present at shallow ( 300 m) levels at Simpevarp, and at even greater depths (approx. 1200 m) at Laxemar. At Simpevarp the groundwaters are mainly Na-Ca-Cl with increasingly enhanced Br and SO 4 with depth. At Laxemar they are mainly Ca-Na-Cl also with increasing enhancements of Br and SO 4 with depth. Main reactions involve ion exchange (Ca). At both sites a glacial component and a deep saline component are present. At Simpevarp the saline component may be potentially non marine and/or non-marine/old Littorina marine in origin; at Laxemar it is more likely to be non-marine in origin. TYPE D: This type comprises reducing highly saline groundwaters (> 20 000 mg/L Cl; to a maximum of ∼70 g/L TDS) and only has been identified at Laxemar at depths exceeding 1200 m. It is mainly Ca-Na-Cl with higher Br but lower SO 4 compared

  19. A safety assessment approach using coupled NEAR3D and CHAN3D - Forsmark

    Liu, Longcheng; Moreno, Luis; Neretnieks, Ivars (Dept. of Chemical Engineering and Technology, Royal Inst. of Technology, Stockholm (Sweden)); Gylling, Bjoern (Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden))

    2010-12-15

    Safety assessment calculations for the Forsmark site were performed using a new code, which couples the far-field code CHAN3D and the near-field code NEAR3D. In addition, the package has a Graphical User Interface (GUI) and a code that governs the simulations (Coupling). The simulations were performed for 90 different canister locations, which were randomly chosen. Deterministic data were used for tunnels, deposition holes, and shafts. The background fractures were stochastically generated in two HRD realizations. The F-ratio and the water travel time distributions were used to study the performance of the simulations. Near-field calculations were not performed for the Forsmark site using the new coded presented in the prevailing report. However, the obtained results in this study are compared with the results from the Task 2 model of the ConnectFlow report /Joyce et al. 2010/. Although the results cannot be compared directly, a reasonably good agreement is obtained for the F-ratio

  20. Preliminary site requirements and considerations for a monitored retrievable storage facility

    1991-08-01

    This report presents preliminary requirements and considerations for siting monitored retrievable storage (MRS) facility. It purpose is to provide guidance for assessing the technical suitability of potential sites for the facility. It has been reviewed by the NRC staff, which stated that this document is suitable for ''guidance in making preliminary determinations concerning MRS site suitability.'' The MRS facility will be licensed by the US Nuclear Regulatory Commission. It will receive spent fuel from commercial nuclear power plants and provide a limited amount of storage for this spent fuel. When a geologic repository starts operations, the MRS facility will also stage spent-fuel shipments to the repository. By law, storage at the MRS facility is to be temporary, with permanent disposal provided in a geologic repository to be developed by the DOE

  1. A preliminary analysis of the risk of transporting nuclear waste to potential candidate commercial repository sites

    Madsen, M.M.

    1984-01-01

    In accordance with the provisions of the Nuclear Waste Policy Act of 1982, environmental assessments for potential candidate sites are required to provide a basis for selection of the first site for disposal of commercial radioactive waste in deep geologic repositories. A preliminary analysis of the impacts of transportation for each of the five potential sites will be described. Transportation was assumed to be entirely by truck or entirely by rail in order to obtain bounding impacts. This paper presents both radiological and nonradiological risks for the once-through fuel cycle

  2. Preliminary investigation on determination of radionuclide distribution in field tracing test site

    Tanaka, Tadao; Mukai, Masayuki; Takebe, Shinichi; Guo Zede; Li Shushen; Kamiyama, Hideo.

    1993-12-01

    Field tracing tests for radionuclide migration have been conducted by using 3 H, 60 Co, 85 Sr and 134 Cs, in the natural unsaturated loess zone at field test site of China Institute for Radiation Protection. It is necessary to obtain confidable distribution data of the radionuclides in the test site, in order to evaluate exactly the migration behavior of the radionuclides in situ. An available method to determine the distribution was proposed on the basis of preliminary discussing results on sampling method of soils from the test site and analytical method of radioactivity in the soils. (author)

  3. Complementary modelling of radionuclide retention in the near-surface system at Forsmark. Development of a reactive transport model using Forsmark 1.2 data

    Sena, Clara; Grandia, Fidel; Arcos, David; Molinero, Jorge; Duro, Lara (Amphos XXI Consulting S.L., Barcelona (Spain))

    2008-10-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is conducting a comprehensive geoscientific characterization of two alternative sites to allocate a deep geological repository of high level nuclear waste. The Site Characterization Program also includes the near-surface systems, which are expected to constitute the last geological barrier between the repository system and the earth's surface. The evaluation of the retention capacity of the near surface systems is, therefore, very relevant for the site characterization program. From the geological point of view, near-surface systems in the Forsmark area consist of Quaternary deposits that overlay a granitic bedrock. Glacial till is the most abundant outcropping Quaternary deposit (approx75% of surface extension) and the remainder is made up of clayey materials (glacial and post-glacial clays). These types of near-surface sediments show distinctive hydraulic and geochemical features. The main reactive mineral in the till deposits, for the time scale considered in this work, is calcium carbonate (calcite). This mineral is found along with clay minerals (e.g. illite) and Fe(III) hydroxides. In contrast, glacial and post-glacial clays are basically composed of illite with minor amounts of calcium carbonate, and containing organic matter-rich levels (gyttja) which can promote reducing conditions in the system. The assessment of the migration behaviour of selected long-lived radionuclides through the near-surface system of Forsmark was developed in an earlier work, that focused on the evaluation of the capacity of the Quaternary deposits for radionuclide retention. The work reported here is an improvement of the geochemical conceptual and numerical model already presented, based on data available in the Site Descriptive Model v 1.2 (Forsmark). Regarding the geochemical variability of the Quaternary deposits present at Forsmark and its implications on radionuclide mobility through the near-surface systems, a

  4. Indirect estimations and spatial variation in leaf area index of coniferous, deciduous and mixed forest stands in Forsmark and Laxemar

    Tagesson, Torbern

    2006-12-01

    Two sites in Sweden are investigated for a potential deep repository of the nuclear waste, the Laxemar investigation area (57 deg 5 min N, 16 deg 7 min E) and the Forsmark investigation area (60 deg 4 min N, 18 deg 2 min E). In the characterisation of these sites, development of site descriptive models is an important part. Leaves are the main surface were an exchange of matter and energy between the atmosphere and the biosphere takes place, and leaf area index (LAI) of the vegetation cover is an important variable correlated to a number of ecophysiological parameters and hereby an important parameter in ecosystem models. In the investigation areas, LAI of boreal and temperate ecosystems were therefore estimated indirectly through optical measurements using the LAI-2000 (LI-COR, Cambridge UK) and TRAC (Tracing Radiation and Architecture of Canopies). On average, measured maximum LAI was 3.40 in Laxemar and 3.43 in Forsmark; minimum LAI was 1.65 in Laxemar and 1.97 in Forsmark. Forest inventory data showed that LAI is positively correlated with basal area, stand height, stand volume and breast height tree diameter. For the coniferous stands, there was also a linearly negative relationship with age. In the Laxemar investigation area, there were no significant relationships for LAI with a satellite derived kNN (kNearest Neighbor) data set with stand height, stand volume and stand age. The kNN data set can therefore not be used to extrapolate measured LAI over the Laxemar investigation area. There were significant relationships between LAI and the normalized difference vegetation index (NDVI) for coniferous, deciduous and mixed forest stands in the Laxemar investigation area. A NDVI image could be used to extrapolate LAI over the entire investigation area. For the Forsmark investigation area, effective LAI for all stands were correlated to NDVI and this relationship could then be used for extrapolation. The effective LAI image was afterwards corrected for average

  5. Indirect estimations and spatial variation in leaf area index of coniferous, deciduous and mixed forest stands in Forsmark and Laxemar

    Tagesson, Torbern [Dept. of Physical Geography and Ecosystem Analysis, Lund Univ., Lund (Sweden)

    2006-12-15

    Two sites in Sweden are investigated for a potential deep repository of the nuclear waste, the Laxemar investigation area (57 deg 5 min N, 16 deg 7 min E) and the Forsmark investigation area (60 deg 4 min N, 18 deg 2 min E). In the characterisation of these sites, development of site descriptive models is an important part. Leaves are the main surface were an exchange of matter and energy between the atmosphere and the biosphere takes place, and leaf area index (LAI) of the vegetation cover is an important variable correlated to a number of ecophysiological parameters and hereby an important parameter in ecosystem models. In the investigation areas, LAI of boreal and temperate ecosystems were therefore estimated indirectly through optical measurements using the LAI-2000 (LI-COR, Cambridge UK) and TRAC (Tracing Radiation and Architecture of Canopies). On average, measured maximum LAI was 3.40 in Laxemar and 3.43 in Forsmark; minimum LAI was 1.65 in Laxemar and 1.97 in Forsmark. Forest inventory data showed that LAI is positively correlated with basal area, stand height, stand volume and breast height tree diameter. For the coniferous stands, there was also a linearly negative relationship with age. In the Laxemar investigation area, there were no significant relationships for LAI with a satellite derived kNN (kNearest Neighbor) data set with stand height, stand volume and stand age. The kNN data set can therefore not be used to extrapolate measured LAI over the Laxemar investigation area. There were significant relationships between LAI and the normalized difference vegetation index (NDVI) for coniferous, deciduous and mixed forest stands in the Laxemar investigation area. A NDVI image could be used to extrapolate LAI over the entire investigation area. For the Forsmark investigation area, effective LAI for all stands were correlated to NDVI and this relationship could then be used for extrapolation. The effective LAI image was afterwards corrected for average

  6. Preliminary safety evaluation for the Laxemar subarea. Based on data and site descriptions after the initial site investigation stage

    Andersson, Johan [JA Streamflow AB, Aelvsjoe (Sweden)

    2006-03-15

    The main objectives of this Preliminary Safety Evaluation (PSE) of the Laxemar subarea have been to determine, with limited efforts, whether the feasibility study's judgement of the suitability of the candidate area with respect to long-term safety holds up in the light of the actual site investigation data; to provide feedback to continued site investigations and site-specific repository design and to identify site-specific scenarios and geoscientific issues for further analyses. The PSE focuses on comparing the attained knowledge of the sites with the suitability criteria as set out by SKB in 2000. These criteria both concern properties of the site judged to be necessary for safety and engineering (requirements) and properties judged to be beneficial (preferences). The findings are then evaluated in order to provide feedback to continued investigations and design work. The PSE does not aim at comparing sites and does not assess compliance with safety and radiation protection criteria. The latter is eventually done in coming Safety Assessments. This preliminary safety evaluation shows that, according to existing data, the Laxemar subarea meets all safety requirements. The evaluation also shows that the Laxemar subarea meets most of the safety preferences, but for some aspects of the site description further reduction of the uncertainties would enhance the safety case. Despite the stated concerns, there is no reason, from a safety point of view, not to continue the Site Investigations at the Laxemar subarea. There are uncertainties to resolve and the safety would eventually need to be verified through a proper safety assessment. Only some of the uncertainties noted in the Site Descriptive Model have safety implications and need further resolution for this reason. Furthermore, uncertainties may need resolving for other reasons, such as giving an adequate assurance of site understanding or assisting in optimising design. Notably, there are questions about the

  7. Preliminary safety evaluation for the Laxemar subarea. Based on data and site descriptions after the initial site investigation stage

    Andersson, Johan

    2006-03-01

    The main objectives of this Preliminary Safety Evaluation (PSE) of the Laxemar subarea have been to determine, with limited efforts, whether the feasibility study's judgement of the suitability of the candidate area with respect to long-term safety holds up in the light of the actual site investigation data; to provide feedback to continued site investigations and site-specific repository design and to identify site-specific scenarios and geoscientific issues for further analyses. The PSE focuses on comparing the attained knowledge of the sites with the suitability criteria as set out by SKB in 2000. These criteria both concern properties of the site judged to be necessary for safety and engineering (requirements) and properties judged to be beneficial (preferences). The findings are then evaluated in order to provide feedback to continued investigations and design work. The PSE does not aim at comparing sites and does not assess compliance with safety and radiation protection criteria. The latter is eventually done in coming Safety Assessments. This preliminary safety evaluation shows that, according to existing data, the Laxemar subarea meets all safety requirements. The evaluation also shows that the Laxemar subarea meets most of the safety preferences, but for some aspects of the site description further reduction of the uncertainties would enhance the safety case. Despite the stated concerns, there is no reason, from a safety point of view, not to continue the Site Investigations at the Laxemar subarea. There are uncertainties to resolve and the safety would eventually need to be verified through a proper safety assessment. Only some of the uncertainties noted in the Site Descriptive Model have safety implications and need further resolution for this reason. Furthermore, uncertainties may need resolving for other reasons, such as giving an adequate assurance of site understanding or assisting in optimising design. Notably, there are questions about the

  8. Radionuclide transport report for the safety assessment SR-Site

    2010-12-15

    This document compiles radionuclide transport calculations of a KBS-3 repository for the safety assessment SR-Site. The SR-Site assessment supports the licence application for a final repository at Forsmark, Sweden

  9. Statistical geological discrete fracture network model. Forsmark modelling stage 2.2

    Fox, Aaron; La Pointe, Paul; Simeonov, Assen; Hermanson, Jan; Oehman, Johan

    2007-11-01

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is performing site characterization at two different locations, Forsmark and Laxemar, in order to locate a site for a final geologic repository for spent nuclear fuel. The program is built upon the development of Site Descriptive Models (SDMs) at specific timed data freezes. Each SDM is formed from discipline-specific reports from across the scientific spectrum. This report describes the methods, analyses, and conclusions of the geological modeling team with respect to a geological and statistical model of fractures and minor deformation zones (henceforth referred to as the geological DFN), version 2.2, at the Forsmark site. The geological DFN builds upon the work of other geological modelers, including the deformation zone (DZ), rock domain (RD), and fracture domain (FD) models. The geological DFN is a statistical model for stochastically simulating rock fractures and minor deformation zones as a scale of less than 1,000 m (the lower cut-off of the DZ models). The geological DFN is valid within four specific fracture domains inside the local model region, and encompassing the candidate volume at Forsmark: FFM01, FFM02, FFM03, and FFM06. The models are build using data from detailed surface outcrop maps and the cored borehole record at Forsmark. The conceptual model for the Forsmark 2.2 geological revolves around the concept of orientation sets; for each fracture domain, other model parameters such as size and intensity are tied to the orientation sets. Two classes of orientation sets were described; Global sets, which are encountered everywhere in the model region, and Local sets, which represent highly localized stress environments. Orientation sets were described in terms of their general cardinal direction (NE, NW, etc). Two alternatives are presented for fracture size modeling: - the tectonic continuum approach (TCM, TCMF) described by coupled size-intensity scaling following power law distributions

  10. Statistical geological discrete fracture network model. Forsmark modelling stage 2.2

    Fox, Aaron; La Pointe, Paul [Golder Associates Inc (United States); Simeonov, Assen [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Hermanson, Jan; Oehman, Johan [Golder Associates AB, Stockholm (Sweden)

    2007-11-15

    The Swedish Nuclear Fuel and Waste Management Company (SKB) is performing site characterization at two different locations, Forsmark and Laxemar, in order to locate a site for a final geologic repository for spent nuclear fuel. The program is built upon the development of Site Descriptive Models (SDMs) at specific timed data freezes. Each SDM is formed from discipline-specific reports from across the scientific spectrum. This report describes the methods, analyses, and conclusions of the geological modeling team with respect to a geological and statistical model of fractures and minor deformation zones (henceforth referred to as the geological DFN), version 2.2, at the Forsmark site. The geological DFN builds upon the work of other geological modelers, including the deformation zone (DZ), rock domain (RD), and fracture domain (FD) models. The geological DFN is a statistical model for stochastically simulating rock fractures and minor deformation zones as a scale of less than 1,000 m (the lower cut-off of the DZ models). The geological DFN is valid within four specific fracture domains inside the local model region, and encompassing the candidate volume at Forsmark: FFM01, FFM02, FFM03, and FFM06. The models are build using data from detailed surface outcrop maps and the cored borehole record at Forsmark. The conceptual model for the Forsmark 2.2 geological revolves around the concept of orientation sets; for each fracture domain, other model parameters such as size and intensity are tied to the orientation sets. Two classes of orientation sets were described; Global sets, which are encountered everywhere in the model region, and Local sets, which represent highly localized stress environments. Orientation sets were described in terms of their general cardinal direction (NE, NW, etc). Two alternatives are presented for fracture size modeling: - the tectonic continuum approach (TCM, TCMF) described by coupled size-intensity scaling following power law distributions

  11. Site study plan for cultural resources, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Cultural Resources Site Study Plan describes a field program to identify and evaluate the archaeological, historical, and Native American Indian resources of the site on local and regional perspectives; monitor and manage discovered cultural resources; and establish a worker education program. The archaeological field program consists of three pedestrian surveys: Survey 1 includes two EDBH seismic survey lines and the area within the exploratory shaft facility (ESF); Survey 2 includes the remainder of the site plus a 1/4 to 3/4-mi border area; and Survey 3 includes an assortment of offsite areas. The historical studies will identify and evaluate known and discovered historical sites and structures and the Native American Indian will identify and evaluate cultural and religious concerns expressed by Indian tribal groups. Prehistoric and historic sites will be evaluated to determine if they meet eligibility criteria for listing on the National Register of Historic Places. This site study plan describes the need for each study; its design and design rationale; analysis, management, and use of data; schedule of field activities; organization of field personnel and sample management; and quality assurance requirements. The cultural resource studies will provide data for satisfying the Programmatic Agreement, engineering design needs, and SRP requirements for permits and approvals, and for minimizing effects to any cultural properties discovered during site characterization. 75 refs., 10 figs., 2 tabs

  12. The World's Reactors no. 70 - Forsmark 3, BWR-75

    Anon.

    1976-01-01

    A large pull-out wall chart is presented showing a coloured cut-away diagram of the Forsmark 3 station. It is accompanied by 2 small sketches one showing the layout of station buildings and the other the inside of the reactor vessel. Parameters are listed. (U.K.)

  13. Subsidence analysis Forsmark nuclear power plant - unit 1

    Bono, Nancy; Fredriksson, Anders; Maersk Hansen, Lars

    2010-12-01

    On behalf of SKB, Golder Associates Ltd carried out a risk analysis of subsidence during Forsmark nuclear power plant in the construction of the final repository for spent nuclear fuel near and below existing reactors. Specifically, the effect of horizontal cracks have been studied

  14. Site study plan for Transportation, Deaf Smith County Site, Texas: Preliminary draft

    1987-06-01

    This site study plan describes transportation field studies to be conducted during the characterization of the Deaf Smith County, Texas, site for the US Department of Energy's Salt Repository Project. The studies are needed to identify and assess potential project impacts to transportation infrastructure and systems in the project vicinity and along potential transportation routes to the site across the State of Texas. The studies are also needed to locate and design project transportation facilities, and to evaluate and design impact mitigation. After identifying the transportation information requirements needed to comply with Federal, State, and local regulations and repository program requirements, the site study plan describes the study design and rationale, the field data collection procedures and equipment, the data analysis methods and application of results, the data management strategy, the schedule of field activities, the management of the study, and the study's quality assurance program. The field data collection activities are organized into programs for the characterization of site vicinity rail corridors and highway corridors, characterization of alternative statewide transportation routes, monitoring of site characterization effects on transportation, characterization of aircraft overflight patterns and hazardous material transportation patterns, and assessment of emergency response preparedness along alternative statewide transportation routes. 34 refs., 10 figs., 2 tabs

  15. Long Term Sorption Diffusion Experiment (LTDE-SD). Supporting laboratory program - Sorption diffusion experiments and rock material characterisation. With supplement of adsorption studies on intact rock samples from the Forsmark and Laxemar site investigations

    Widestrand, Henrik; Byegaard, Johan; Selnert, Eva; Skaalberg, Mats; Hoeglund, Susanne; Gustafsson, Erik (Geosigma AB, Uppsala (Sweden))

    2010-12-15

    The LTDE-SD experiment, (Long Term Sorption Diffusion Experiment) aims at increasing the scientific knowledge of sorption and diffusion under in situ conditions and to provide data for performance and safety assessment calculations. In this report, performance and results of laboratory sorption and diffusion experiments and porosity investigations using site-specific crushed and intact rock materials are presented, including a geological and mineralogical characterization of the samples. A synthetic groundwater and a part of the radionuclide tracer cocktail that was used for the in situ experiment were used also in the laboratory experiments. 13 radionuclide tracers were analysed in the laboratory experiments. The method descriptions from SKB Site Investigations were applied in order to enable comparisons with Site Investigations data. The water saturation porosity of 10 unaltered matrix rock samples from KA3065A02 and A03 is 0.26 +- 0.08% and two fracture material samples show porosities of 2.4% and 5.2% respectively. 14C-methylmethacrylate impregnation (the PMMA-method) show that the unaltered rock matrix porosity is relatively homogeneous with grain boundary porosity, while the porosity of fracture samples is heterogeneous and have increased porosity up to more than 10% in some parts. Through-diffusion experiments using tritiated water (H3HO) give a matrix diffusivity in the range from 2.7centre dot10-14 to 6.5centre dot10-14 m2/s in four samples from KA3065A02 and A03. The results of the porosity and diffusion measurements are coherent in ranges with earlier LTDE-SD measurements and are also in line with the SKB Site Investigations results. In the batch sorption experiments using crushed rock material, two matrix rock samples of Aevroe granodiorite, one red-stained altered Aevroe granodiorite sample and two chlorite-calcite dominated fracture samples were analysed for three different size fractions as a function of time up to 186 days contact time. The

  16. Preliminary Evaluation of Removing Used Nuclear Fuel From Nine Shutdown Sites

    Maheras, Steven J.; Best, Ralph; Ross, Steven B.; Buxton, Kenneth A.; England, Jeffery L.; McConnell, Paul

    2013-04-30

    The Blue Ribbon Commission on America’s Nuclear Future identified removal of stranded used nuclear fuel at shutdown sites as a priority so that these sites may be completely decommissioned and put to other beneficial uses. In this report, a preliminary evaluation of removing used nuclear fuel from nine shutdown sites was conducted. The shutdown sites included Maine Yankee, Yankee Rowe, Connecticut Yankee, Humboldt Bay, Big Rock Point, Rancho Seco, Trojan, La Crosse, and Zion. At these sites a total of 7649 used nuclear fuel assemblies and a total of 2813.2 metric tons heavy metal (MTHM) of used nuclear fuel are contained in 248 storage canisters. In addition, 11 canisters containing greater-than-Class C (GTCC) low-level radioactive waste are stored at these sites. The evaluation was divided in four components: • characterization of the used nuclear fuel and GTCC low-level radioactive waste inventory at the shutdown sites • an evaluation of the onsite transportation conditions at the shutdown sites • an evaluation of the near-site transportation infrastructure and experience relevant to the shipping of transportation casks containing used nuclear fuel from the shutdown sites • an evaluation of the actions necessary to prepare for and remove used nuclear fuel and GTCC low-level radioactive waste from the shutdown sites. Using these evaluations the authors developed time sequences of activities and time durations for removing the used nuclear fuel and GTCC low-level radioactive waste from a single shutdown site, from three shutdown sites located close to each other, and from all nine shutdown sites.

  17. Preliminary Geological Survey on the Proposed Sites for the New Research Reactor

    Lim, In Cheol; Ha, J. J.; Oh, K. B.

    2010-12-01

    · Performing the preliminary geological survey on the proposed sites for the new research reactor through the technical service · Ordering a technical service from The Geological Society of Korea · Contents of the geological survey - Confirmation of active fault - Confirmation of a large-scale fracture zone or weak zone - Confirmation of inappropriate items related to the underground water - Confirmation of historical seismicity and instrumental earthquakes data · Synthesized analysis and holding a report meeting · Results of the geological survey - Confirmation of the geological characteristics of the sites and drawing the requirements for the precise geological survey in the future

  18. Site Study Plan for land use, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Land Use Site Study Plan describes a field program consisting of characterization of the site; seismic survey rights-of-way and transportation and utility corridors, the vicinity, the region, future land use, and monitoring land-use change. Aerial photography will be used to characterize the site, seismic rows and transportation and utility corridors, and the vicinity. The resulting land-use maps and overlays will then be verified in the field. Interviews with farm managers and local experts will provide additional information. A Geographic Information System (GIS) and satellite imagery will be used to characterize the region, monitor land-use change, and provide information to assist with the future land use study. The site study plan describes the study design and rationale, the filed data collection procedures and equipment, the data analysis methods and application of results, the data management strategy, the schedule of field activities, the personnel requirements and management of the study, and the study's quality assurance program. The directives and requirements that drive these studies are derived from the Salt Repository Project Requirements Document. 51 refs; 6 figs; 3 tabs

  19. Site Study Plan for Aesthetics, Deaf Smith County Site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Aesthetic Site Study Plan describes a field program consisting of identification of the visually affected area; determination of scenic quality, visual sensitivity, and visual management classes of the site and vicinity; and analysis of the level of visual contrast that would be created by the project. Field ratings of scenic quality, visual sensitivity, and visual contrast will be supplemented by a public perception survey designed to incorporate the views of the public. This plan describes the need for the study, the study design, data management and use, schedule for proposed activities, and quality assurance program. This study will provide data needed to satisfy requirements contained in, or derived from, SRPO Requirement Document (SRP-RD). 35 refs., 6 figs., 2 tabs

  20. Site Study Plan for salt, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Salt Site Study Plan (SSP) describes a program for characterizing the existing salt environment in the site vicinity. A step-by-step approach is described which proceeds from published data and planned theoretical studies, to planned laboratory studies, and finally to planned field studies, to provide the necessary data to meet program requirements contained in the Salt Repository Project - Requirements Document (SRP-RD). The plan also draws on the results of other SSP's for certain data; for example, soil salinity data are to be provided under the Soils SSP. The salt studies consist of evaluation of control and mitigation measures, salt monitoring studies, emission factors development, air models development and validation, and risk assessment. For each study, its design and design rationale; analysis, management, and use of data; schedule of activities; organization of personnel and sample management; and quality assurance requirements are described. 90 refs., 9 figs., 7 tabs

  1. Site Study Plan for Acoustics, Deaf Smith County Site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Acoustics site study plan describes a field program which characterizes existing sound levels, determines the area's sound propagation characteristics, and monitors the project-related sound emissions. The plan describes for each study: the need for the study, study design, data management and use, schedule, and quality assurance requirements. These studies will provide data needed to satisfy requirements contained in, or derived from, the Salt Repository Requirements Document. 37 refs., 9 figs., 3 tabs

  2. Preliminary safety evaluation, based on initial site investigation data. Planning document

    Hedin, Allan

    2002-12-01

    This report is a planning document for the preliminary safety evaluations (PSE) to be carried out at the end of the initial stage of SKBs ongoing site investigations for a deep repository for spent nuclear fuel. The main purposes of the evaluations are to determine whether earlier judgements of the suitability of the candidate area for a deep repository with respect to long-term safety holds up in the light of borehole data and to provide feed-back to continued site investigations and site specific repository design. The preliminary safety evaluations will be carried out by a safety assessment group, based on a site model, being part of a site description, provided by a site modelling group and a repository layout within that model suggested by a repository engineering group. The site model contains the geometric features of the site as well as properties of the host rock. Several alternative interpretations of the site data will likely be suggested. Also the biosphere is included in the site model. A first task for the PSE will be to compare the rock properties described in the site model to previously established criteria for a suitable host rock. This report gives an example of such a comparison. In order to provide more detailed feedback, a number of thermal, hydrological, mechanical and chemical analyses of the site will also be included in the evaluation. The selection of analyses is derived from the set of geosphere and biosphere analyses preliminarily planned for the comprehensive safety assessment named SR-SITE, which will be based on a complete site investigation. The selection is dictated primarily by the expected feedback to continued site investigations and by the availability of data after the PSE. The repository engineering group will consider several safety related factors in suggesting a repository layout: Thermal calculations will be made to determine a minimum distance between canisters avoiding canister surface temperatures above 100 deg C

  3. Site 300 hazardous-waste-assessment project. Interim report: December 1981. Preliminary site reconnaissance and project work plan

    Raber, E.; Helm, D.; Carpenter, D.; Peifer, D.; Sweeney, J.

    1982-01-01

    This document was prepared to outline the scope and objectives of the Hazardous Waste Assessment Project (HWAP) at Site 300. This project was initiated in October, 1981, to investigate the existing solid waste landfills in an effort to satisfy regulatory guidelines and assess the potential for ground-water contamination. This involves a site-specific investigation (utilizing geology, hydrology, geophysics and geochemistry) with the goal of developing an effective ground-water quality monitoring network. Initial site reconnaissance work has begun and we report the results, to date, of our geologic hydrogeologic studies. All known solid waste disposal locations are underlain by rocks of either the Late Miocene Neroly Formation or the Cierbo Formation, both of which are dominantly sandstones interbedded with shale and claystone. The existence of a regional confined (artesian) aquifer, as well as a regional water-table aquifer is postulated for Site 300. Preliminary analysis has led to an understanding of directions and depths of regional ground-water flow

  4. Site study plan for ecology, Deaf Smith County Site, Texas: Environmental Field Program: Preliminary Draft

    1987-06-01

    The Ecology Site Study Plan describes a field program consisting of studies which include surveys for endangered, threatened, and candidate species; vegetation characterization, including mapping and cover typing, plant succession, wetlands description, and preexisting stresses; and wildlife community characterization, including availability and quality of habitats and descriptions of mammal, bird, reptile, amphibian, and invertebrate populations. The plan for each study describes the need for the study, study design, data management and use, schedule and personnel requirements, and quality assurance. These studies will provide data needed to satisfy requirements contained in, or derived from, the Salt Repository Project Requirements Document (SRP-RD). 83 refs., 3 tabs

  5. Site study plan for exploratory shaft monitoring wells, Deaf Smith County Site, Texas: Preliminary Draft

    1988-01-01

    As part of site characterization studies, two exploratory shafts will be constructed at the Deaf Smith County site, Texas. Twelve wells at five locations have been proposed to monitor potential impacts of shaft construction on water-bearing zones in the Ogallala Formation and the Dockum Group. In addition, tests have been proposed to determine the hydraulic properties of the water-bearing zones for use in design and construction of the shafts. Samples of the Blackwater Draw Formation, Ogallala Formation, and Dockum Group will be obtained during construction of these wells. Visual indentification, laboratory testing, and in situ testing will yield data necessary for Exploratory Shaft Facility design and construction. This activity provides the earliest data on the Blackwater Drew Formation, Ogallala Formation, and Dockum Group near the exploratory shaft locations. Drilling and hydrologic testing are scheduled prior to other subsurface activity at the Exploratory Shaft Facility to establish ground-water baseline conditions. The Technical Field Services Contractor is responsible for conducting the field program of drilling and testing. Samples and data will be handled and reported in accordance with established Salt Repository Project procedures. A quality assurance program will be utilized to assure that activities affecting quality are performed correctly and that the appropriate documentation is maintained. 45 refs., 11 figs., 4 tabs

  6. Input and turnover of forest tree litter in the Forsmark and Oskarshamn areas

    Mjoefors, Kristina; Johansson, Maj-Britt; Nilsson, Aake [Dept. of Forest Soi ls, Swedish Univ. of Agricultural Sciences (Sweden); Hyvoenen, Riitta [Dept. of Eco logy, Swedish Univ. of Agricultural Sciences (Sweden)

    2007-04-15

    The site investigations reported here were conducted to provide data for the comprehensive descriptive ecosystem model that is being constructed. This report provides estimates of annual inputs of aboveground litter from trees (dry mass and amounts of C and N), litter decomposition rates and changes in organic and inorganic components in litter during decomposition. The study in the Forsmark area comprised two Norway spruce (Picea abies (L.) Karst) stands (sites F1 and F3), and a mixed stand of Norway spruce and alder (Alnus glutinosa (L.) Gaertn.) (site F2). The study in the Oskarshamn area comprised one common oak stand (Quercus robur L.) (site O1), one Scots pine stand (Pinus silvestris L.) (site O2) and one Norway spruce stand (site O3). In the Forsmark area, the aboveground litterfall from trees was of similar magnitude at sites F1 and F2, but considerably lower at site F3. At the former sites the average annual litterfall amounted to 195 and 231 gdw/m{sup 2} respectively, whereas the latter site received only 136 gdw/m{sup 2}. There was also a large variation in annual litterfall between stands in the Oskarshamn area. The spruce stand at site O3 exhibited the highest litterfall (almost 400 gdw/m{sup 2}), followed by the oak stand at site O1 (with almost 300 gdw/m{sup 2}), whereas the pine stand at site O2 had the lowest (less than 150 gdw/m{sup 2}). The proportion of needles/leaves in the total litterfall varied between 65% and 75% for the stands. The amount of carbon (C) returned in aboveground litterfall amounted to between 60 and 110 gdw/m{sup 2}/yr at the forest sites within the Forsmark area. The corresponding range for the sites in the Oskarshamn area was 70 to 190 gdw/m{sup 2}/yr. At sites O1 and O2 in Oskarshamn, about 3.6 gdw/m{sup 2}/yr of nitrogen (N) were returned annually to the forest floor by the aboveground litterfall. This was over four times the N amount deposited in the Scots pine stand in the same area (about 0.8 gdw/m{sup 2}/yr). At the

  7. Input and turnover of forest tree litter in the Forsmark and Oskarshamn areas

    Mjoefors, Kristina; Johansson, Maj-Britt; Nilsson, Aake; Hyvoenen, Riitta

    2007-04-01

    The site investigations reported here were conducted to provide data for the comprehensive descriptive ecosystem model that is being constructed. This report provides estimates of annual inputs of aboveground litter from trees (dry mass and amounts of C and N), litter decomposition rates and changes in organic and inorganic components in litter during decomposition. The study in the Forsmark area comprised two Norway spruce (Picea abies (L.) Karst) stands (sites F1 and F3), and a mixed stand of Norway spruce and alder (Alnus glutinosa (L.) Gaertn.) (site F2). The study in the Oskarshamn area comprised one common oak stand (Quercus robur L.) (site O1), one Scots pine stand (Pinus silvestris L.) (site O2) and one Norway spruce stand (site O3). In the Forsmark area, the aboveground litterfall from trees was of similar magnitude at sites F1 and F2, but considerably lower at site F3. At the former sites the average annual litterfall amounted to 195 and 231 gdw/m 2 respectively, whereas the latter site received only 136 gdw/m 2 . There was also a large variation in annual litterfall between stands in the Oskarshamn area. The spruce stand at site O3 exhibited the highest litterfall (almost 400 gdw/m 2 ), followed by the oak stand at site O1 (with almost 300 gdw/m 2 ), whereas the pine stand at site O2 had the lowest (less than 150 gdw/m 2 ). The proportion of needles/leaves in the total litterfall varied between 65% and 75% for the stands. The amount of carbon (C) returned in aboveground litterfall amounted to between 60 and 110 gdw/m 2 /yr at the forest sites within the Forsmark area. The corresponding range for the sites in the Oskarshamn area was 70 to 190 gdw/m 2 /yr. At sites O1 and O2 in Oskarshamn, about 3.6 gdw/m 2 /yr of nitrogen (N) were returned annually to the forest floor by the aboveground litterfall. This was over four times the N amount deposited in the Scots pine stand in the same area (about 0.8 gdw/m 2 /yr). At the Forsmark sites, the N return in

  8. Hydrogeochemical evaluation for Simpevarp model version 1.2. Preliminary site description of the Simpevarp area

    Laaksoharju, Marcus (ed.) [Geopoint AB, Stockholm (Sweden)

    2004-12-01

    Siting studies for SKB's programme of deep geological disposal of nuclear fuel waste currently involves the investigation of two locations, Simpevarp and Forsmark, to determine their geological, hydrogeochemical and hydrogeological characteristics. Present work completed has resulted in Model version 1.2 which represents the second evaluation of the available Simpevarp groundwater analytical data collected up to April, 2004. The deepest fracture groundwater samples with sufficient analytical data reflected depths down to 1.7 km. Model version 1.2 focusses on geochemical and mixing processes affecting the groundwater composition in the uppermost part of the bedrock, down to repository levels, and eventually extending to 1000 m depth. The groundwater flow regimes at Laxemar/Simpevarp are considered local and extend down to depths of around 600-1000 m depending on local topography. The marked differences in the groundwater flow regimes between Laxemar and Simpevarp are reflected in the groundwater chemistry where four major hydrochemical groups of groundwaters (types A-D) have been identified: TYPE A: This type comprises dilute groundwaters (< 1000 mg/L Cl; 0.5-2.0 g/L TDS) of Na-HCO{sub 3} type present at shallow (<200 m) depths at Simpevarp, but at greater depths (0-900 m) at Laxemar. At both localities the groundwaters are marginally oxidising close to the surface, but otherwise reducing. Main reactions involve weathering, ion exchange (Ca, Mg), surface complexation, and dissolution of calcite. Redox reactions include precipitation of Fe-oxyhydroxides and some microbially mediated reactions (SRB). Meteoric recharge water is mainly present at Laxemar whilst at Simpevarp potential mixing of recharge meteoric water and a modern sea component is observed. Localised mixing of meteoric water with deeper saline groundwaters is indicated at both Laxemar and Simpevarp. TYPE B: This type comprises brackish groundwaters (1000-6000 mg/L Cl; 5-10 g/L TDS) present at

  9. CATE 2016 Indonesia: normalized radial graded filtering, site-to-site image registration, and preliminary results

    Jensen, L.; Kovac, S. A.; Hare, H. S.; Mitchell, A. M.; McKay, M. A.; Bosh, R.; Watson, Z.; Penn, M.

    2016-12-01

    An area of the solar corona from 1 out to approximately 2.5 solar radii is currently poorly sampled in astronomy. This is largely due to difficulties inherent in observing the sun from space and from the ground. Specifically focusing on ground based observations, the main problem is scattered light in the Earth's atmosphere and in the telescopes themselves. A total solar eclipse solves this problem by blocking the light from the photosphere of the sun before it enters the atmosphere, reducing the scattered light in the atmosphere by a factor of 10,000. However, using a total solar eclipse introduces another challenge due to the small window of time it provides. At any given location in 2017, the totality will last for only about 2.5 minutes and such a small data set limits the studies that can be done on the inner corona. The Citizen Continental-America Telescopic Eclipse Experiment plans to overcome this issue by taking advantage of America's infrastructure and using 60 identical telescopes to collect continuous data of the solar eclipse as the shadow travels from Oregon to South Carolina. By splicing these data together 90 minutes of one-of-a-kind data can be collected, revealing the dynamics of the inner corona as never seen before. For the 2016 Indonesian total solar eclipse the CATE project collected data using 5 sites along the eclipse path. These data were then used to develop processing programs to use on future data. These processes included site-to-site image registration as well as normalized radial graded filtering of the images. Programs were also developed to begin performing studies on the data including overlapping CATE and LASCO space telescope data for a total coronal image as well as thread tracing routines to quantify direction in the coronal filaments. This work was made possible through the National Solar Observatory Research Experiences for Undergraduates (REU) Program, which is funded by the National Science Foundation (NSF). The NSO

  10. Site Study Plan for soils, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Soils Site Study Plan describes a field program consisting of a soil characterization survey, impact monitoring of soils, predisturbance soil salinity survey, and a reclamation suitability study. This information will be used to plan for soil stripping, stockpiling, and replacement; reclamation of soils; determining predisturbance chemical and physical characteristics of the soils; including salinity levels; and monitoring for changes in chemical and physical characteristics of the soil. The SSP describes for each study the need for the study, the study design, data management and use, schedule of proposed activities, and the quality assurance program. These studies will provide data needed to satisfy requirements contained in, or derived from, the Salt Repository Project Requirements Document. 75 refs., 10 figs., 5 tabs

  11. Preliminary site characterization radiological monitoring plan for the Nevada Nuclear Waste Storage Investigations Project, Yucca Mountain Site

    1987-03-01

    The activities described in this plan occur in the early phases of site characterization. This document presents the Preliminary Site Characterization Radiological Monitoring Plan (PSCRMP) for collecting and evaluating data in support of the NNWSI Project. The PSCRMP defines and identifies control procedures for the monitoring activities. The PSCRMP activity will utilize integrating radon monitoring devices, a continuous radon monitor, and a particulate air sampler. These instruments will be used to establish the baseline radioactivity and/or radioactivity released due to early site characterization activities. The sections that follow provide a general project description, the specifics of the monitoring program, and the practices that will be employed to ensure the validity of the collected data by integrating quality assurance into all activities. Section 2 of this document describes the regulatory base of this document. Section 3 describes the site characterization activities which may lead to release of radioactivity. Section 4 provides a description of the potential sources of radioactivity that site characterization could generate. Section 5 summarizes the sampling and monitoring methodology, which will be used to monitor the potential sources of radioactivity. The network of sampling and monitoring equipment is described in Section 6, and Section 7 summarizes the systems operation activities. The data reporting activities are described in Section 8. Finally, a description of the Quality Assurance (QA) and Quality Control (QC) activities is provided in Section 9. Appendix A contains a summary of the procedures to be used in this program, and Appendix B contains technical specification on equipment and services. 20 refs., 11 figs., 2 tabs

  12. Preliminary risk assessment of Power Plant Plomin site contaminated by radioactive slag and ash

    Skanata, D.; Sinka, D.; Lokner, V.; Schaller, A.

    1996-01-01

    There is a certain number of radioactively contaminated sites in the Republic of Croatia, one of them being known as Power Plant Plomin site, which contains radioactive slag and ash. Due to a relatively high quantity of the deposited material, as well as relatively high population density of the neighbouring area, it is very important to assess the impact of the site on human health and environment. Using RESRAD computer code and PATHRAE method a preliminary assessment of doses and radiation risks for the workers who spend most of their working day at the pile has been performed. PATHRAE method has also been used for the assessment of radiation risks for the neighbouring population. The assessment is preliminary in its character due to the lack of input data. On the basis of assessment results, recommendations are being given comprising measurements to be taken with a view to coming up with the final risk assessment, as well as protective measures which should be undertaken in the meantime. (author)

  13. Thermal properties. Site descriptive modelling Forsmark - stage 2.2

    Back, Paer-Erik; Wrafter, John; Sundberg, Jan; Rosen, L ars

    2007-09-01

    The lithological data acquired from boreholes and mapping of the rock surface need to be reclassified into thermal rock classes, TRCs. The main reason is to simplify the simulations. The lithological data are used to construct models of the transition between different TRCs, thus describing the spatial statistical structure of each TRC. The result is a set of transition probability models that are used in the simulation of TRCs. The intermediate result of this first stochastic simulation is a number of realisations of the geology, each one equally probable. Based on the thermal data, a spatial statistical thermal model is constructed for each TRC. It consists of a statistical distribution and a variogram for each TRC. These are used in the stochastic simulation of thermal conductivity and the result is a number of equally probable realisations of thermal conductivity for the domain. In the next step, the realisations of TRCs (lithology) and thermal conductivity are merged, i.e. each realisation of geology is filled with simulated thermal conductivity values. The result is a set of realisations of thermal conductivity that considers both the difference in thermal properties between different TRCs, and the variability within each TRC. If the result is desired in a scale different from the simulation scale, i.e. the canister scale, upscaling of the realisations can be performed. The result is a set of equally probable realisations of thermal properties. The presented methodology was applied to rock domain RFM029 and RFM045. The main results are sets of realisations of thermal properties that can be used for further processing, most importantly for statistical analysis and numerical temperature simulations for the design of repository layout (distances between deposition holes). The main conclusions of the thermal modelling are: The choice of scale has a profound influence on the distribution of thermal conductivity values. The variance decreases and the lower tail percentiles increase significantly as the scale of observation increases from 1 m to 5 m. Best estimates of the 0.1 percentile of thermal conductivity are: Domain RFM029: 2.30 W/(m*K) for the 1 m scale and 2.87 W/(m*K) for the 5 m scale. omain RFM045: 2.25 W/(m*K) for the 1 m scale and 2.33 W/(m*K) for the 5 m scale. The discretisation error of amphibolite is believed to be the largest uncertainty for the 1 m scale for domain RFM029. This error results in conservative estimates (believed to be too low) of the lower percentiles. For other cases, the uncertainties associated with the spatial structure of TRCs (lithology) and the spatial statistical thermal models of each TRC are believed to be the most important ones. Low-conductive rocks, mainly amphibolite and the tonalitic varieties of granodiorite to tonalite are decisive for the lower tail of the thermal conductivity distribution of a domain. The shape of the tail is therefore mainly determined by how these rock types are modelled. One of the most important uncertainties for the result for domain RFM045 is how amphibolite was modelled. Based on relatively limited data, the typical lengths of amphibolite rock bodies are modelled as being significantly longer than in domain RFM029. This may have resulted in a too heavy lower tail of the distribution of thermal conductivity for domain RFM045. In conclusion, the resulting thermal models are judged to represent the modelled rock domains, but may overemphasise the importance of the low-conductive amphibolite

  14. Thermal properties. Site descriptive modelling Forsmark - stage 2.2

    Back, Paer-Erik; Wrafter, John; Sundberg, Jan [Geo Innova AB (Sweden); Rosen, L ars [Sweco Viak AB (Sweden)

    2007-09-15

    The lithological data acquired from boreholes and mapping of the rock surface need to be reclassified into thermal rock classes, TRCs. The main reason is to simplify the simulations. The lithological data are used to construct models of the transition between different TRCs, thus describing the spatial statistical structure of each TRC. The result is a set of transition probability models that are used in the simulation of TRCs. The intermediate result of this first stochastic simulation is a number of realisations of the geology, each one equally probable. Based on the thermal data, a spatial statistical thermal model is constructed for each TRC. It consists of a statistical distribution and a variogram for each TRC. These are used in the stochastic simulation of thermal conductivity and the result is a number of equally probable realisations of thermal conductivity for the domain. In the next step, the realisations of TRCs (lithology) and thermal conductivity are merged, i.e. each realisation of geology is filled with simulated thermal conductivity values. The result is a set of realisations of thermal conductivity that considers both the difference in thermal properties between different TRCs, and the variability within each TRC. If the result is desired in a scale different from the simulation scale, i.e. the canister scale, upscaling of the realisations can be performed. The result is a set of equally probable realisations of thermal properties. The presented methodology was applied to rock domain RFM029 and RFM045. The main results are sets of realisations of thermal properties that can be used for further processing, most importantly for statistical analysis and numerical temperature simulations for the design of repository layout (distances between deposition holes). The main conclusions of the thermal modelling are: The choice of scale has a profound influence on the distribution of thermal conductivity values. The variance decreases and the lower tail percentiles increase significantly as the scale of observation increases from 1 m to 5 m. Best estimates of the 0.1 percentile of thermal conductivity are: Domain RFM029: 2.30 W/(m*K) for the 1 m scale and 2.87 W/(m*K) for the 5 m scale. omain RFM045: 2.25 W/(m*K) for the 1 m scale and 2.33 W/(m*K) for the 5 m scale. The discretisation error of amphibolite is believed to be the largest uncertainty for the 1 m scale for domain RFM029. This error results in conservative estimates (believed to be too low) of the lower percentiles. For other cases, the uncertainties associated with the spatial structure of TRCs (lithology) and the spatial statistical thermal models of each TRC are believed to be the most important ones. Low-conductive rocks, mainly amphibolite and the tonalitic varieties of granodiorite to tonalite are decisive for the lower tail of the thermal conductivity distribution of a domain. The shape of the tail is therefore mainly determined by how these rock types are modelled. One of the most important uncertainties for the result for domain RFM045 is how amphibolite was modelled. Based on relatively limited data, the typical lengths of amphibolite rock bodies are modelled as being significantly longer than in domain RFM029. This may have resulted in a too heavy lower tail of the distribution of thermal conductivity for domain RFM045. In conclusion, the resulting thermal models are judged to represent the modelled rock domains, but may overemphasise the importance of the low-conductive amphibolite.

  15. Lessons from the Forsmark 1 event in Sweden

    Jorle, A.

    2007-01-01

    A short circuit at a switchyard broke some of the safety chains in the reactor safety system and created a difficult situation in the control room at the Forsmark 1 power plant in Sweden. After a scram two of four diesel generators failed to deliver power but the reactor could safely be controlled through remaining two systems and power could be distributed from external grid after 22 minutes. Surveillance systems in the control room also failed and the situation at the reactor was unclear. Analysis shows that there was never a risk to the public and no damage on the core. The incident exposed unknown weakness in the power supply systems of the reactor. Also it was found that maintenance had failed and some components were not properly installed. The regulator identified the problem as a serious failure but did not at once realize the public impact. The licensee was late in its decision making and did only publish local press releases that did not fully expose the nature of the incident. After some days an independent expert claimed that a core melt was a close possibility. He was widely quoted and created a media impact many European countries. In the light of the incident problems with safety culture was identified at the plant and additional findings showed problems in the management system of Forsmark. Growing media interest culminated in January when a critical internal report from staff members in Forsmark was made public. Some lessons learnt: - Media activity followed well-known patterns. - The regulator was an important source for media. - Regulator not fired upon until January, after a long autumn filled with negative reporting on Forsmark. - The plant was not proactive in its communication which created a problem for the regulator. (author)

  16. Groundwater flow modelling of the excavation and operational phases - Forsmark

    Svensson, Urban; Follin, Sven

    2010-07-01

    As a part of the license application for a final repository for spent nuclear fuel at Forsmark, the Swedish Nuclear Fuel and Waste Management Company (SKB) has undertaken a series of groundwater flow modelling studies. These represent time periods with different climate conditions and the simulations carried out contribute to the overall evaluation of the repository design and long-term radiological safety. The modelling study reported here presents calculated inflow rates, drawdown of the groundwater table and upconing of deep saline water for different levels of grouting efficiency during the excavation and operational phases of a final repository at Forsmark. The inflow calculations are accompanied by a sensitivity study, which among other matters handles the impact of parameter heterogeneity, different deposition hole rejection criteria, and the SFR facility (the repository for short-lived radioactive waste located approximately 1 km to the north of the investigated candidate area for a final repository at Forsmark). The report also presents tentative modelling results for the duration of the saturation phase, which starts once the used parts of the repository are being backfilled

  17. Environmental monitoring at the Forsmark nuclear power plant

    Sandstroem, O.

    1991-01-01

    The use of cooling water at such large power plants as Forsmark creates a considerable hazard for fish in the intake area, as they may be transported into the plant and killed. Several millions of Baltic herring and three-spined stickleback are lost each year at the intake screens. A release of cooling water to an open sea area is generally considered as a minor environmental problem, a presumption so far not contradicated by the results from the monitoring studies at Forsmark. In the Biotest basin, however, where the exposure to heat is maximal, a long series of effects ultimately changing populations of plants, benthic animals and fish have been documented. One important conclusion after ten years of studies in a heated Biotest basin, is that ecosystem stability seems to need very long time to be established, if it ever will. The monitoring of radioactivity controls the quality of the fish as food but is also directed to select special species accumulating these elements, bladder wrack etc. At Forsmark only small amounts of radionuclides from the plant so far have been detected in the marine environment. (KAE)

  18. Groundwater flow modelling of the excavation and operational phases - Forsmark

    Svensson, Urban (Computer-aided Fluid Engineering AB, Lyckeby (Sweden)); Follin, Sven (SF GeoLogic AB, Taeby (Sweden))

    2010-07-15

    As a part of the license application for a final repository for spent nuclear fuel at Forsmark, the Swedish Nuclear Fuel and Waste Management Company (SKB) has undertaken a series of groundwater flow modelling studies. These represent time periods with different climate conditions and the simulations carried out contribute to the overall evaluation of the repository design and long-term radiological safety. The modelling study reported here presents calculated inflow rates, drawdown of the groundwater table and upconing of deep saline water for different levels of grouting efficiency during the excavation and operational phases of a final repository at Forsmark. The inflow calculations are accompanied by a sensitivity study, which among other matters handles the impact of parameter heterogeneity, different deposition hole rejection criteria, and the SFR facility (the repository for short-lived radioactive waste located approximately 1 km to the north of the investigated candidate area for a final repository at Forsmark). The report also presents tentative modelling results for the duration of the saturation phase, which starts once the used parts of the repository are being backfilled.

  19. Repository for spent nuclear fuel. Plant description layout D - Forsmark

    2010-07-01

    This document describes the final repository for spent nuclear fuel, SFK, which is located at Forsmark, in Oesthammar. The bedrock at the site is part of a so-called tectonic lens, in which the rock composition is relatively homogeneous and less deformed than outside the lens. The bedrock consists mainly of granite with high quartz content and good thermal conductivity. The central parts above ground are grouped in an operations area, located at the Soederviken on the south side of the intake duct for cooling water for nuclear power plant. Operating area is divided into an internal, secured portion, where the canisters of fuel are handled and there are links to the underground part, and a outer part, where the buffer, backfill and sealing used in the repository's barriers are produced. The above-ground part of the plant and also include storage of excavated rock, ventilation stations, and supplies of bentonite. The underground portion consists of a central area and a storage area. Caverns of the central area contain features for the underground operation. It communicates with the internal operating range above ground via a spiral ramp and several shafts. The ramp used to transport capsules of spent fuel and other heavy or bulky transport. The shafts are used to transport rock, buffer, backfill and staff, as well as for ventilation. The largest part of the space below ground is the repository where the canisters with the spent fuel are disposed. The capsules are deposited in vertical holes in the tunnels. When the deposit in a tunnel is complete, the tunnel is re-filled. The two main activities underground is rock work and disposal work, which are conducted separately from each other. Rock works covers all steps required to excavate tunnels and drill deposition holes, as well as to make temporary installations in the tunnels. To the landfill works count, besides the deposit of the capsule, the placement of the bentonite buffer in the deposition hole and backfilling

  20. Investigation of discrete-fracture network conceptual model uncertainty at Forsmark

    Geier, Joel

    2011-04-01

    In the present work a discrete fracture model has been further developed and implemented using the latest SKB site investigation data. The model can be used for analysing the fracture network and to model flow through the rock in Forsmark. The aim has been to study uncertainties in the hydrological discrete fracture network (DFN) for the repository model. More specifically the objective has been to study to which extent available data limits uncertainties in the DFN model and how data that can be obtained in future underground work can further limit these uncertainties. Moreover, the effects on deposition hole utilisation and placement have been investigated as well as the effects on the flow to deposition holes

  1. Mineralogy and geochemistry of rocks and fracture fillings from Forsmark and Oskarshamn: Compilation of data for SR-Can

    Drake, Henrik; Sandstroem, Bjoern [Isochron GeoConsulting HB, Goeteborg (Sweden); Tullborg, Eva-Lena [Terralogica AB, Graabo (Sweden)

    2006-11-15

    This report is a compilation of the so far available data for the safety assessment SR-Can carried out by SKB. The data consists of mineralogy, geochemistry, porosity, density and redox properties for both dominating rock types and fracture fillings at the Forsmark and Oskarshamn candidate areas. In addition to the compilation of existing information, the aim has been to identify missing data and to clarify some conception of e.g. deformation zones. The objective of the report is to present the available data requested for the modelling of the chemical stability of the two sites. The report includes no interpretation of the data.

  2. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part I; Redovisning av saekerhet efter foerslutning av slutfoervaret foer anvaent kaernbraensle. Huvudrapport fraan projekt SR-Site. Del I

    2011-07-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  3. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part II; Redovisning av saekerhet efter foerslutning av slutfoervaret foer anvaent kaernbraensle. Huvudrapport fraan projekt SR-Site. Del II

    2011-07-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  4. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part III; Redovisning av saekerhet efter foerslutning av slutfoervaret foer anvaent kaernbraensle. Huvudrapport fraan projekt SR-Site. Del III

    2011-07-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  5. A Preliminary Assessment of Daily Weather Conditions in Nuclear Site for Development of Effective Emergency Plan

    Han, Seok Jung; Ahn, Kwang Il

    2012-01-01

    A radiological emergency preparedness for nuclear sites is recognized as an important measure against anticipated severe accidents with environmental releases of radioactive materials. While there are many individual means in the emergency preparedness for nuclear accidents, one of most important means is to make a decision of evacuation or shelter of the public residents with the emergency plan zone (EPZ) of a nuclear site. In order to prepare an effective strategy for the evacuation as a basis of the emergency preparedness, it may need the understanding of atmospheric dispersion characteristics of radiation releases to the environment, mainly depending upon the weather conditions of a radiation releases location, i.e., a nuclear site. As a preliminary study for the development of an effective emergency plan, the basic features of the weather conditions of a specific site were investigated. A main interest of this study is to identify whether or not the site weather conditions have specific features helpful for a decision making of evacuation of the public residents

  6. The accumulation of a platelet protein, thrombospondin, at the site of arterial thrombus formation: Preliminary report

    Perlman, S.B.; Hammes, R.J.; Besozzi, M.C.; Folts, J.D.; Mosher, D.F.

    1987-01-01

    There are many methods available for the detection of thrombosis, none of which are noninvasive, rapid and accurate. Thrombosponding is a platelet protein that is present in the developing thrombus and may be an effective substance to use for imaging thrombosis. Vascular stenosis and thrombosis were produced in coronary, carotid and femoral arteries in eleven adult mongrel dogs. 131 I labeled thrombosponding was administered to each animal to determine whether the radiotracer accumulated at the site of thrombus formation. The radioactivity per gram of vessels with thrombi was significantly different from the control vessels or whole blood (p=0.0037 and p=0.015, respectively, paired t-test). This preliminary work suggests that iodinated thrombosponding accumulates at the site of thrombus formation. Labeled thrombosponding may be a rapid, safe and accurate method of detecting arterial thrombosis. (orig.)

  7. Repository for spent nuclear fuel. Plant description layout D - Forsmark; Slutfoervarsanlaeggning foer anvaent kaernbraensle. Anlaeggningsbeskrivning layout D - Forsmark

    2010-07-15

    This document describes the final repository for spent nuclear fuel, SFK, which is located at Forsmark, in Oesthammar. The bedrock at the site is part of a so-called tectonic lens, in which the rock composition is relatively homogeneous and less deformed than outside the lens. The bedrock consists mainly of granite with high quartz content and good thermal conductivity. The central parts above ground are grouped in an operations area, located at the Soederviken on the south side of the intake duct for cooling water for nuclear power plant. Operating area is divided into an internal, secured portion, where the canisters of fuel are handled and there are links to the underground part, and a outer part, where the buffer, backfill and sealing used in the repository's barriers are produced. The above-ground part of the plant and also include storage of excavated rock, ventilation stations, and supplies of bentonite. The underground portion consists of a central area and a storage area. Caverns of the central area contain features for the underground operation. It communicates with the internal operating range above ground via a spiral ramp and several shafts. The ramp used to transport capsules of spent fuel and other heavy or bulky transport. The shafts are used to transport rock, buffer, backfill and staff, as well as for ventilation. The largest part of the space below ground is the repository where the canisters with the spent fuel are disposed. The capsules are deposited in vertical holes in the tunnels. When the deposit in a tunnel is complete, the tunnel is re-filled. The two main activities underground is rock work and disposal work, which are conducted separately from each other. Rock works covers all steps required to excavate tunnels and drill deposition holes, as well as to make temporary installations in the tunnels. To the landfill works count, besides the deposit of the capsule, the placement of the bentonite buffer in the deposition hole and

  8. Preliminary safety evaluation for the Simpevarp subarea. Based on data and site descriptions after the initial site investigation stage

    2005-04-01

    The main objectives of this Preliminary safety evaluation (PSE) of the Simpevarp subarea are: to determine, whether the feasibility study's judgement of the suitability of the candidate area with respect to long-term safety holds up in the light of the site investigation data; to provide feedback to continued site investigations and site-specific repository design and to identify site specific scenarios and geoscientific issues for further analyses. The PSE focuses on comparing the attained knowledge of the sites with the suitability criteria as set out by SKB in the report SKB-TR--00-12. These criteria both concern properties of the site judged to be necessary for safety and engineering (requirements) and properties judged to be beneficial (preferences). The findings are then evaluated in order to provide feedback to continued investigations and design work. The PSE does not aim at comparing sites and does not assess compliance with safety and radiation protection criteria. The evaluation shows that even considering remaining uncertainties, the Simpevarp subarea meets all safety requirements and most of the safety preferences. Consequently, from a safety point of view, there is no reason not to continue the Site Investigations of the Simpevarp subarea. There are still uncertainties to resolve and the safety would eventually need to be verified through a full safety assessment. Still, this Preliminary Safety Evaluation demonstrates that it is likely that a safe repository for spent nuclear fuel of the KBS-3 type could be constructed at the site. The following feedback is provided to the site investigations and the associated site modelling: Reducing the uncertainty on the deformation zone geometry within the Simpevarp subarea would allow for a more specified layout, although the sensitivity analysis shows that the space needed is rather robust with respect to uncertainties in the zones. There is substantial uncertainty in the discrete fracture network (DFN) model

  9. Bedrock geology Forsmark. Modelling stage 2.3. Description of the bedrock geological map at the ground surface

    Stephens, Michael B.; Bergman, Torbjoern (Geological Survey of Sweden, Uppsala (Sweden)); Isaksson, Hans (GeoVista AB, Luleaa (Sweden)); Petersson, Jesper (SwedPower AB, Stockholm (Sweden))

    2008-12-15

    A description of the bedrock geological map of the ground surface at the Forsmark site is presented here. This map is essentially a 2D model for the distribution of different types of rock unit on this surface. Besides showing the distribution of these rock units, the bedrock geological map also displays the distribution of some deformation zones that intersect the ground surface. It also presents information bearing on the position and form of outcrops, the location and projection of boreholes drilled during the site investigation programme, subordinate rock types, the occurrence of abandoned mines or exploration prospects, measurements of ductile structures in outcrops, inferred form lines, key minerals, and the occurrence of mylonite and cataclastic rock. Bedrock data from outcrops and excavations, airborne and ground magnetic data and information from the uppermost part of boreholes have all been used in the construction of the geological map. The description has also made use of complementary analytical data bearing on the composition and age of the rocks as well gamma-ray spectrometry and gravity data. Uncertainty in the position of the boundaries between rock units over the mapped area are addressed in a qualitative manner. Four model versions of the bedrock geological map have been delivered to SKB's GIS database (bedrock geological map, Forsmark, versions 1.1, 1.2, 2.2 and 2.3) at different times during the site investigation programme. The Forsmark area is situated along the coast of the Baltic Sea in northern Uppland, Sweden, in a region where the overall level of ductile strain in the bedrock is high. This high-strain region extends several tens of kilometres across the WNW-ENE to NW-SE strike of the rocks in this part of the Fennoscandian Shield. At Forsmark, the coastal region is composed partly of high-strain belts, which formed under amphibolite-facies metamorphic conditions, and partly of tectonic lenses, where the bedrock is also affected by

  10. Bedrock geology Forsmark. Modelling stage 2.3. Description of the bedrock geological map at the ground surface

    Stephens, Michael B.; Bergman, Torbjoern; Isaksson, Hans; Petersson, Jesper

    2008-12-01

    A description of the bedrock geological map of the ground surface at the Forsmark site is presented here. This map is essentially a 2D model for the distribution of different types of rock unit on this surface. Besides showing the distribution of these rock units, the bedrock geological map also displays the distribution of some deformation zones that intersect the ground surface. It also presents information bearing on the position and form of outcrops, the location and projection of boreholes drilled during the site investigation programme, subordinate rock types, the occurrence of abandoned mines or exploration prospects, measurements of ductile structures in outcrops, inferred form lines, key minerals, and the occurrence of mylonite and cataclastic rock. Bedrock data from outcrops and excavations, airborne and ground magnetic data and information from the uppermost part of boreholes have all been used in the construction of the geological map. The description has also made use of complementary analytical data bearing on the composition and age of the rocks as well gamma-ray spectrometry and gravity data. Uncertainty in the position of the boundaries between rock units over the mapped area are addressed in a qualitative manner. Four model versions of the bedrock geological map have been delivered to SKB's GIS database (bedrock geological map, Forsmark, versions 1.1, 1.2, 2.2 and 2.3) at different times during the site investigation programme. The Forsmark area is situated along the coast of the Baltic Sea in northern Uppland, Sweden, in a region where the overall level of ductile strain in the bedrock is high. This high-strain region extends several tens of kilometres across the WNW-ENE to NW-SE strike of the rocks in this part of the Fennoscandian Shield. At Forsmark, the coastal region is composed partly of high-strain belts, which formed under amphibolite-facies metamorphic conditions, and partly of tectonic lenses, where the bedrock is also affected by

  11. Preliminary results from comparisons of redundant tiltmeters at three sites in central california

    Mortensen, C.E.; Johnston, M.J.S.

    1979-01-01

    The U.S. Geological Survey has been operating a network of shallow-borehole tiltmeters in central California since June 1973. At six sites redundant instruments have been installed as a check on data coherency. These include the Sage Ranch, Tres Pinos, New Idria, Aromas, Bear Valley and San Juan Bautista tiltmeter sites. Preliminary results from the comparison of redundant data from the Aromas, Bear Valley and San Juan Bautista sites for periods of eight, three and seven months respectively, suggest that short period tilt signals in the range 5 min < T < 3-5 h and ranging in amplitude from 5 ?? 10-8 to 10-6 rad, but not including step offsets, show excellent agreement on closely spaced instruments. Agreement is not as good in this period range for instruments at San Juan Bautista with a separation of 200 m. Signals of interest observed in this period range include coseismic tilts, teleseisms and tilts associated with creep events. Tilt signals in the period range 3-5 h < T < 2- 5 weeks are not always coherent at all three of the redundant tilt sites studied. Tilt signals in this period range have amplitudes up to 5 ?? 10-6 rad and wavelengths down to at least the instrument separation at the closely spaced sites (~several meters). Regarding longerterm coherency, the instruments at San Juan Bautista with 200-m spacing, agree within 0.5 ??rad for the N-S component and 0.7 jurad for the E-W component for a period of two months. The closely spaced redundant instruments at Aromas agree within 2 ??rad for the N-S component and 1 ??rad for the E-W component for the eight-month period of operation. Data from the three sites have been checked for effects of temperature, atmospheric pressure and rainfall. The latter appears to be critically site dependent. The worst case tilts for 1 inch of rainfall can be more than 1 jurad with a duration of a few days to a week. Typical rain-induced tilts are less than 0.3 ??rad for 1 inch of rain. The two instruments at the Sage Ranch

  12. Preliminary constitutive properties for salt and nonsalt rocks from four potential repository sites

    Pfeifle, T.W.; Mellegard, K.D.; Senseny, P.E.

    1983-07-01

    Results are presented from laboratory strength and creep tests performed on salt and nonsalt specimens from the Richton Dome in Mississippi, the Vacherie Dome in Louisiana, the Permian Basin in Texas, and the Paradox Basin in Utah. The constititive properties obtained for salt are the elastic moduli and the failure envelope at 24 0 C and parameter values for the exponential-time creep law. Some additional data are presented to indicate how the elastic moduli and strength change with temperature. The nonsalt constitutive properties reported are the elastic moduli, the unconfined compressive strength and the tensile strength at 24 0 C. The properties given in this report will be used in subsequent numerical simulations that will provide information to assist in the screening and selection of site locations for a nuclear waste repository and to assist in the repository design at the selected site. The matrix of tests performed is the minimum effort required to obtain these constitutive properties. The preliminary values obtained will be supplemented by additional testing for sites that are selected for further investigation

  13. Preliminary report on the utilization of the Fermilab site for a future accelerator

    1996-10-01

    This report is a preliminary assessment of the utility of the Fermilab site for future accelerator projects. It responds to a request from the Director to evaluate how the Fermilab site and infrastructure may be relevant to future accelerator projects in the U.S. The SSC experience suggests that any major new project will have to be based on the existing infrastructure at one of the National Laboratories. This work presents only the technical issues and the benefits of the Fermilab site and infrastructure. The projects treated are: (1) A really large hadron collider based on the ''Pipetron'' vision of low-field (2 Tesla) magnets in a small diameter tunnel. Another option, not treated in detail, is a hadron collider using high field magnets. (2) Muon Colliders with 250 GeV and 2 TeV per beam. (3) A linear electron collider with 250 to 500 GeV per beam. The infrastructure of the state of Illinois - geology, hydrology, power and surface water- seems remarkably well suited to any of these projects. The geology of most of Illinois, including Fermilab, contains a dolomite layer that: has low seismic activity, is at an appropriate depth to provide radiation protection, is essentially impervious to water movement and thus satisfies hydrology requirements. There is adequate electrical power - both locally and statewide. We first give brief overviews of the Fermilab and Illinois infrastructure - geology, hydrology, power, and water - and then a summary of each project. On the basis of what we have learned, we feel that Fermilab must be considered seriously as a site for any of these projects. Beyond this point, however site-specific plans will need to be developed for each of the projects

  14. Design principle of TVO's final repository and preliminary adaptation to site specific conditions

    Salo, J-P.; Reikkola, R.

    1995-01-01

    Teollisuuden Voima Oy (TVO) is responsible for the management of spent fuel produced by the Olkiluoto power plant. TVO's current programme of spent fuel management is based on the guidelines and time schedule set by the Finnish Government. TVO has studied a final disposal concept in which the spent fuel bundles are encapsulated in copper canisters and emplaced in Finnish bedrock. According to the plan the final repository for spent fuel will be in operation by 2020. TVO's updated technical plans for the disposal of spent fuel together with a performance analysis (TVO-92) were submitted to the authorities in 1992. The paper describes the design principle of TVO's final repository and preliminary adaptation of the repository to site specific conditions. (author). 10 refs., 5 figs

  15. Regional hydrogeological simulations using CONECTFLOW. Preliminary site description. Laxemar sub area - version 1.2

    Hartley, Lee; Hunter, Fiona; Jackson, Peter; McCarthy, Rachel [Serco Assurance, Risley (United Kingdom); Gylling, Bjoern; Marsic, Niko [Kemakta Konsult AB, Stockholm (Sweden)

    2006-04-15

    The main objective of this study is to support the development of a preliminary Site Description of the Laxemar subarea on a regional-scale based on the available data of November 2004 (Data Freeze L1.2). A more specific objective of this study is to assess the role of both known and less quantified hydrogeological conditions in determining the present-day distribution of saline groundwater in the Laxemar subarea on a regional-scale. An improved understanding of the palaeo-hydrogeology is necessary in order to gain credibility for the Site Description in general and the hydrogeological description in particular. This is to serve as a basis for describing the present hydrogeological conditions on a local-scale, as well as predictions of future hydrogeological conditions. Another objective is to assess the flow-paths from the local-scale model domain, based on the present-day flow conditions, to assess the distribution of discharge and recharge areas connected to the flow at the approximate repository depth to inform the Preliminary Safety Evaluation. Significant new features incorporated in the modelling include: a depth variation in hydraulic properties within the deformation zones; a dependence on rock domain and depth in the rock mass properties in regional-scale models; a more detailed model of the overburden in terms of a layered system of spatially variable thickness made up of several different types of Quaternary deposits has been implemented; and several variants on the position of the watertable have been tried. The motivation for introducing a dependence on rock domain was guided by the hydrogeological interpretation with the aim of honouring the observed differences in hydraulic properties measured at the boreholes.

  16. Regional hydrogeological simulations using CONECTFLOW. Preliminary site description. Laxemar sub area - version 1.2

    Hartley, Lee; Hunter, Fiona; Jackson, Peter; McCarthy, Rachel; Gylling, Bjoern; Marsic, Niko

    2006-04-01

    The main objective of this study is to support the development of a preliminary Site Description of the Laxemar subarea on a regional-scale based on the available data of November 2004 (Data Freeze L1.2). A more specific objective of this study is to assess the role of both known and less quantified hydrogeological conditions in determining the present-day distribution of saline groundwater in the Laxemar subarea on a regional-scale. An improved understanding of the palaeo-hydrogeology is necessary in order to gain credibility for the Site Description in general and the hydrogeological description in particular. This is to serve as a basis for describing the present hydrogeological conditions on a local-scale, as well as predictions of future hydrogeological conditions. Another objective is to assess the flow-paths from the local-scale model domain, based on the present-day flow conditions, to assess the distribution of discharge and recharge areas connected to the flow at the approximate repository depth to inform the Preliminary Safety Evaluation. Significant new features incorporated in the modelling include: a depth variation in hydraulic properties within the deformation zones; a dependence on rock domain and depth in the rock mass properties in regional-scale models; a more detailed model of the overburden in terms of a layered system of spatially variable thickness made up of several different types of Quaternary deposits has been implemented; and several variants on the position of the watertable have been tried. The motivation for introducing a dependence on rock domain was guided by the hydrogeological interpretation with the aim of honouring the observed differences in hydraulic properties measured at the boreholes

  17. Quantitative assessment of radionuclide retention in the near-surface system at Forsmark. Development of a reactive transport model using Forsmark 1.2 data

    Grandia, Fidel; Sena, Clara; Arcos, David; Molinero, Jorge; Duro, Lara; Bruno, Jordi

    2007-12-01

    The main objective of this work is to assess the migration behaviour of selected long-lived radionuclides through the near-surface system of Forsmark, with special focus on the evaluation of the capacity of the Quaternary deposits and sediments for radionuclide retention. The work reported here is based on data and information from Forsmark Site Descriptive Model version 1.2. From the geological point of view, the near-surface systems in the Forsmark area consist of Quaternary deposits and sediments that overlay the granitic bedrock. Glacial till is the more abundant outcropping Quaternary deposit and the remainder is made of clayey deposits. These types of near-surface sediments show distinctive hydraulic and geochemical features. The main reactive mineral in the till deposits, for the time horizons considered in this work, is calcium carbonate together with minor amounts of clay minerals (e.g. illite). The till deposits forms aquifers with relatively high hydraulic conductivities. In contrast, glacial and post-glacial clays are basically composed of illite with low to very low amounts of calcium carbonate, and containing organic matter-rich layers (gyttja), which can promote reducing conditions in the porewaters. All these clays exhibits relatively low hydraulic conductivity values. Five radionuclides have been selected for conceptualization and qualitative evaluation of retention process: U as an actinide, Se as a redox-sensitive radionuclide, Cs as a monovalent cation, Sr as a divalent cation, and I as an anion radionuclide. Overall, radionuclide retention capacity in the surface systems at Forsmark can be provided by sorption on charged surfaces of clays and oxyhydroxides, co-precipitation with sulphates, sulphides, oxyhydroxides and carbonates, and sorption on organic matter. Two-dimensional coupled hydrogeological and reactive solute transport models have been developed to simulate the geochemical behaviour of U, Cs and Sr. These three radionuclides have

  18. Soil carbon effluxes in ecosystems of Forsmark and Laxemar

    Tagesson, Torbern (Dept. of Physical Geography and Ecosystem Analysis, Lund Univ. (Sweden))

    2007-12-15

    Soil carbon effluxes were estimated in a number of ecosystems in Laxemar and Forsmark investigations areas. It was done in a young Scots pine (Pinus sylvestris) stand, a wet deciduous stand, a poor fen and an agricultural field in the Laxemar investigation area in south-eastern Sweden (57 deg 5 min N, 16 deg 7 min E) and in a pasture, two Norway spruce (Picea abies) stands, a deciduous forest, a mire, a wet deciduous forest and a clear-cut in the Forsmark investigation area (60 deg 4 min N, 18 deg 2 min E). It was measured with the closed chamber technique in 2005 and 2006. Soil temperature at 10 cm depth, air temperature and photosynthetically active radiation (PAR) were also measured. Exponential regressions with soil respiration against air and soil temperature were used to estimate annual soil respiration. A hyperbolic curve with Gross Primary Production (GPP) against PAR was used for modelling GPP for the growing season in the poor fen and the agricultural area of Laxemar. The exponential regressions with soil respiration against air and soil temperature explained on average 33.6% and 44.0% of the variation, respectively. GPP of the ground vegetation were reducing soil carbon effluxes, in all stands but one of the spruce stands, the deciduous forest, the mire and the wet deciduous forest of Forsmark. The significant (all but spruce 2 in Forsmark) curves with GPP against PAR explained on average 22.7% of the variation in GPP. The cubic regressions with GPP against air temperature were only significant for the poor fen and the agricultural field in Laxemar and it explained on average 34.8% of the variation in GPP for these ecosystems. The exponential regressions with air and soil temperature against soil respiration could be used to temporally extrapolate the occasional field measurements. The hyperbolic curve with GPP against PAR could also be used for temporal extrapolation of GPP for the ecosystems without a tree layer, i.e. the poor fen and the agricultural

  19. Soil carbon effluxes in ecosystems of Forsmark and Laxemar

    Tagesson, Torbern

    2007-12-01

    Soil carbon effluxes were estimated in a number of ecosystems in Laxemar and Forsmark investigations areas. It was done in a young Scots pine (Pinus sylvestris) stand, a wet deciduous stand, a poor fen and an agricultural field in the Laxemar investigation area in south-eastern Sweden (57 deg 5 min N, 16 deg 7 min E) and in a pasture, two Norway spruce (Picea abies) stands, a deciduous forest, a mire, a wet deciduous forest and a clear-cut in the Forsmark investigation area (60 deg 4 min N, 18 deg 2 min E). It was measured with the closed chamber technique in 2005 and 2006. Soil temperature at 10 cm depth, air temperature and photosynthetically active radiation (PAR) were also measured. Exponential regressions with soil respiration against air and soil temperature were used to estimate annual soil respiration. A hyperbolic curve with Gross Primary Production (GPP) against PAR was used for modelling GPP for the growing season in the poor fen and the agricultural area of Laxemar. The exponential regressions with soil respiration against air and soil temperature explained on average 33.6% and 44.0% of the variation, respectively. GPP of the ground vegetation were reducing soil carbon effluxes, in all stands but one of the spruce stands, the deciduous forest, the mire and the wet deciduous forest of Forsmark. The significant (all but spruce 2 in Forsmark) curves with GPP against PAR explained on average 22.7% of the variation in GPP. The cubic regressions with GPP against air temperature were only significant for the poor fen and the agricultural field in Laxemar and it explained on average 34.8% of the variation in GPP for these ecosystems. The exponential regressions with air and soil temperature against soil respiration could be used to temporally extrapolate the occasional field measurements. The hyperbolic curve with GPP against PAR could also be used for temporal extrapolation of GPP for the ecosystems without a tree layer, i.e. the poor fen and the agricultural

  20. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part III

    2011-01-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  1. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part I

    2011-01-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  2. Long-term safety for KBS-3 repositories at Forsmark and Laxemar - a first evaluation. Main Report of the SR-Can project

    Hedin, Allan

    2006-10-01

    This document is the main report from the safety assessment project SR-Can. The SR-Can project is a preparatory stage for the SR-Site assessment, the report that will be used in support of SKB's application for a final repository. The purposes of the safety assessment SR-Can are the following: 1. To make a first assessment of the safety of potential KBS-3 repositories at Forsmark and Laxemar to dispose of canisters as specified in the application for the encapsulation plant. 2. To provide feedback to design development, to SKB's RandD programme, to further site investigations and to future safety assessment projects. 3. To foster a dialogue with the authorities that oversee SKB's activities, i.e. the Swedish Nuclear Power Inspectorate, SKI, and the Swedish Radiation Protection Authority, SSI, regarding interpretation of applicable regulations, as a preparation for the SR-Site project. The assessment relates to the KBS-3 disposal concept in which copper canisters with a cast iron insert containing spent nuclear fuel are surrounded by bentonite clay and deposited at approximately 500 m depth in saturated, granitic rock. Preliminary data from the Forsmark and Laxemar sites, presently being investigated by SKB as candidates for a KBS-3 repository are used in the assessment. An important aim of this report is to demonstrate the proper handling of requirements placed on the safety assessment in applicable regulations. Therefore, regulations issued by the Swedish Nuclear Power Inspectorate and the Swedish Radiation Protection Institute are reproduced in an Appendix where references are given to sections in the main text where the handling of the different requirements is discussed. The principal acceptance criterion requires that 'the annual risk of harmful effects after closure does not exceed 10 -6 for a representative individual in the group exposed to the greatest risk'. 'Harmful effects' refer to cancer and hereditary effects. The risk limit corresponds to an

  3. Long-term safety for KBS-3 repositories at Forsmark and Laxemar - a first evaluation. Main Report of the SR-Can project

    Hedin, Allan (ed.)

    2006-10-15

    This document is the main report from the safety assessment project SR-Can. The SR-Can project is a preparatory stage for the SR-Site assessment, the report that will be used in support of SKB's application for a final repository. The purposes of the safety assessment SR-Can are the following: 1. To make a first assessment of the safety of potential KBS-3 repositories at Forsmark and Laxemar to dispose of canisters as specified in the application for the encapsulation plant. 2. To provide feedback to design development, to SKB's RandD programme, to further site investigations and to future safety assessment projects. 3. To foster a dialogue with the authorities that oversee SKB's activities, i.e. the Swedish Nuclear Power Inspectorate, SKI, and the Swedish Radiation Protection Authority, SSI, regarding interpretation of applicable regulations, as a preparation for the SR-Site project. The assessment relates to the KBS-3 disposal concept in which copper canisters with a cast iron insert containing spent nuclear fuel are surrounded by bentonite clay and deposited at approximately 500 m depth in saturated, granitic rock. Preliminary data from the Forsmark and Laxemar sites, presently being investigated by SKB as candidates for a KBS-3 repository are used in the assessment. An important aim of this report is to demonstrate the proper handling of requirements placed on the safety assessment in applicable regulations. Therefore, regulations issued by the Swedish Nuclear Power Inspectorate and the Swedish Radiation Protection Institute are reproduced in an Appendix where references are given to sections in the main text where the handling of the different requirements is discussed. The principal acceptance criterion requires that 'the annual risk of harmful effects after closure does not exceed 10{sup -6} for a representative individual in the group exposed to the greatest risk'. 'Harmful effects' refer to cancer and hereditary effects

  4. Inventory of vegetation and benthos in newly laid and natural ponds in Forsmark 2012; Inventering av vegetation och bottenfauna i nyanlagda och naturliga goelar i Forsmark 2012

    Qvarfordt, Susanne; Wallin, Anders; Borgiel, Micke [Sveriges Vattenekologer AB, Vingaaker (Sweden)

    2013-01-15

    SKB plans to build a repository for the spent nuclear fuel. The repository is planned to be built in Forsmark and constitutes installations above and below ground. The building and operation of the construction will involve activities that might affect the nature in the area. The impact means, among other things, that a small water body, which today is a reproduction site for the red listed pool frog (Rana lessonae), will disappear. The lost locality for the pool frog has been compensated by creating four new ponds in the Forsmark area. This study is part of the follow-up of these new habitats. The aim is to describe the plant and animal communities in the ponds, and follow the succession, i.e. the development of the habitats. The study also includes two natural ponds that will serve as reference objects. The survey of vegetation and invertebrate fauna in the ponds was conducted in October 2012. The results show that the new ponds had low coverage of submersed vegetation and the species composition in the plant communities differed between the ponds. The reference ponds also had different plant communities, both in terms of species composition and coverage. This indicates that the species composition of the plant communities in the new ponds will likely depend on physical factors specific to the respective pond, but that higher vegetation coverage can be expected over time in all new ponds. The reference ponds had similar animal communities that differed from the animal communities in the new ponds. The similar species composition in the reference ponds, despite the variety of plant communities, suggests that similar animal communities are likely to develop in the new ponds, even if the plant communities continues to be different. Water chemical sampling has also been conducted in the ponds during 2012. A comparison of the inorganic environment (with regard to analysed ions) showed that the reference ponds had relatively similar ion compositions with little

  5. Risk of surgical site infection in paediatric herniotomies without any prophylactic antibiotics: A preliminary experience

    Dhananjay Vaze

    2014-01-01

    Full Text Available Background: Different studies underline the use of pre-operative antibiotic prophylaxis in clean surgeries like herniotomy and inguinal orchiopexy. But, the meta-analyses do not recommend nor discard the use of prophylactic pre-operative antibiotics. The scarcity of controlled clinical trials in paediatric population further vitiates the matter. This study assessed the difference in the rate of early post-operative wound infection cases in children who received single dose of pre-operative antibiotics and children who did not receive antibiotics after inguinal herniotomy and orchiopexy. Materials and Methods: This randomised prospective study was conducted in Paediatric Surgery department of PGIMER Chandigarh. Out of 251 patients, 112 patients were randomised to the case group and 139 were ascribed to the control group. The patients in control group were given a standard regimen of single dose of intravenous antibiotic at the time of induction followed by 3-4 days of oral antibiotic. Case group patients underwent the surgical procedure in similar manner with no antibiotic either at the time of induction or post-operatively. Results: The incidence of surgical site infection in case group was 3.73 % and that in control group was 2.22%. The observed difference in the incidence of surgical site infection was statistically insignificant (P value = 0.7027. The overall infection rate in case and control group was 2.89%. Conclusions: Our preliminary experience suggests that there is no statistically significant difference in the proportion of early post-operative wound infection between the patients who received single dose of pre-operative antibiotics and the patients who received no antibiotics after inguinal herniotomy and orchiopexy. The risk of surgical site infection in paediatric heriotomies does not increase even if the child′s weight is less than his/her expected weight for age.

  6. Preliminary evaluation of 30 potential granitic rock sites for a radioactive waste storage facility in southern Nevada

    Boardman, C.R.; Knutson, C.F.

    1978-02-15

    Results of preliminary study are presented which was performed under subtask 2.7 of the NTS Terminal Waste Storage Program Plan for 1978. Subtask 2.7 examines the feasibility of locating a nuclear waste repository in a granitic stock or pluton in southern Nevada near the Nevada Test Site (NTS). It is assumed for the purposes of this study that such a repository cannot be located at NTS. This assumption may or may not be correct. This preliminary report does not identify a particular site as being a suitable location for a repository. Nor does it absolutely eliminate a particular site from further consideration. It does, however, answer the basic question of probable suitability of some of the sites and present a systematic method for site evaluation. Since the findings of this initial study have been favorable, it will be followed by more exhaustive and detailed studies of the original 30 sites and perhaps others. In future studies some of the evaluation criteria used in the preliminary study may be modified or eliminated, and new criteria may be introduced.

  7. Preliminary evaluation of 30 potential granitic rock sites for a radioactive waste storage facility in southern Nevada

    Boardman, C.R.; Knutson, C.F.

    1978-01-01

    Results of preliminary study are presented which was performed under subtask 2.7 of the NTS Terminal Waste Storage Program Plan for 1978. Subtask 2.7 examines the feasibility of locating a nuclear waste repository in a granitic stock or pluton in southern Nevada near the Nevada Test Site (NTS). It is assumed for the purposes of this study that such a repository cannot be located at NTS. This assumption may or may not be correct. This preliminary report does not identify a particular site as being a suitable location for a repository. Nor does it absolutely eliminate a particular site from further consideration. It does, however, answer the basic question of probable suitability of some of the sites and present a systematic method for site evaluation. Since the findings of this initial study have been favorable, it will be followed by more exhaustive and detailed studies of the original 30 sites and perhaps others. In future studies some of the evaluation criteria used in the preliminary study may be modified or eliminated, and new criteria may be introduced

  8. Greenland Analogue Project - Hydraulic properties of deformation zones and fracture domains at Forsmark, Laxemar and Olkiluoto for usage together with Geomodel version 1

    Follin, Sven; Stigsson, Martin; Rhen, Ingvar; Engstroem, Jon; Klint, Knut Erik

    2011-05-01

    The database of the GAP site is under development. In order to meet the data needs of the different modelling teams working with groundwater flow modelling it has been decided to compile trial data sets comprising structural-hydraulic properties suitable for flow modelling on different scales. The properties provided in this report are based on data and groundwater flow modelling studies conducted for three sites located in the Fennoscandian Shield, two of which are studied by SKB, Forsmark and Laxemar, and one by Posiva, Olkiluoto. The provided hydraulic properties provided here are simplified to facilitate a readily usage together with the GAP Geomodel version 1

  9. Greenland Analogue Project - Hydraulic properties of deformation zones and fracture domains at Forsmark, Laxemar and Olkiluoto for usage together with Geomodel version 1

    Follin, Sven (SF GeoLogic AB (Sweden)); Stigsson, Martin (Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)); Rhen, Ingvar (Sweco Environment AB (Sweden)); Engstroem, Jon (Geologian tutkimuskeskus (Finland)); Klint, Knut Erik (De Nationale Geologiske Undersoegelser for Danmark og Groenland (Denmark))

    2011-05-15

    The database of the GAP site is under development. In order to meet the data needs of the different modelling teams working with groundwater flow modelling it has been decided to compile trial data sets comprising structural-hydraulic properties suitable for flow modelling on different scales. The properties provided in this report are based on data and groundwater flow modelling studies conducted for three sites located in the Fennoscandian Shield, two of which are studied by SKB, Forsmark and Laxemar, and one by Posiva, Olkiluoto. The provided hydraulic properties provided here are simplified to facilitate a readily usage together with the GAP Geomodel version 1.

  10. Drift design methodology and preliminary application for the Yucca Mountain Site Characterization Project

    Hardy, M.P.; Bauer, S.J.

    1991-12-01

    Excavation stability in an underground nuclear waste repository is required during construction, emplacement, retrieval (if required), and closure phases to ensure worker health and safety, and to prevent development of potential pathways for radionuclide migration in the post-closure period. Stable excavations are developed by appropriate excavation procedures, design of the room shape, design and installation of rock support reinforcement systems, and implementation of appropriate monitoring and maintenance programs. In addition to the loads imposed by the in situ stress field, the repository drifts will be impacted by thermal loads developed after waste emplacement and, periodically, by seismic loads from naturally occurring earthquakes and underground nuclear events. A priori evaluation of stability is required for design of the ground support system, to confirm that the thermal loads are reasonable, and to support the license application process. In this report, a design methodology for assessing drift stability is presented. This is based on site conditions, together with empirical and analytical methods. Analytical numerical methods are emphasized at this time because empirical data are unavailable for excavations in welded tuff either at elevated temperatures or under seismic loads. The analytical methodology incorporates analysis of rock masses that are systematically jointed, randomly jointed, and sparsely jointed. In situ thermal and seismic loads are considered. Methods of evaluating the analytical results and estimating ground support requirements for all the full range of expected ground conditions are outlines. The results of a preliminary application of the methodology using the limited available data are presented. 26 figs., 55 tabs

  11. Water-quality monitoring at the Hoe Creek test site: review and preliminary conclusions

    Wang, F T; Mead, S W; Stuermer, D H

    1982-05-20

    It has been shown that underground coal gasification (UCG) may introduce a broad range of residual gasification products into the groundwater of a coal aquifer. Sorption of many contaminants by the coal itself is an important factor in restricting the migration of these contaminants in the ground water. However, field studies, conducted at Lawrence Livermore National Laboratory's Hoe Creek site, have shown that sorption of organic compounds by coal is not as effective as expected, perhaps because the coal surface area is limited. Furthermore, if severe roof collapse has taken place during gasification, non-coal aquifers located above the gasified coal seam may be interconnected with the coal aquifer, and contaminants may enter these non-coal aquifers, in which sorption is even less effective. The Hoe Creek II and III experiments have provided opportunities to study the contamination of a sand aquifer located above a gasified coal seam in a hydrological recharge area. Preliminary results indicate that the water in the overlying sand aquifer is much less contaminated with organic compounds than the water in the gasified coal aquifer. In conducting these field investigations, valuable lessons ere learned concerning groundwater monitoring. A suggested monitoring strategy is discussed.

  12. Dry-run of site investigation planning using the manual for preliminary investigation in Japan

    Akamura, Shigeki; Miwa, Tadashi; Tanaka, Tatsuya; Shiratsuchi, Hiroshi; Horio, Atsushi

    2011-01-01

    A stepwise site selection process has been adopted for geological disposal of HLW in Japan. Literature surveys, followed by preliminary investigations (PI) and, finally, detailed investigations in underground facilities will be carried out in the successive selection stages. In the PI stage, surface-based investigations such as borehole surveys and geophysical prospecting will be implemented. In order to conduct the PI appropriately and efficiently within a restricted timeframe and budget, planning and management of PI are very important. NUMO therefore compiled existing knowledge and experience in the planning and managing of investigations in the form of manuals to be used to improve and maintain internal expertise. The first editions of the two manuals were prepared on the basis of experience overseas, and then they were revised by taking technological environment, laws and regulation in Japan into consideration. This paper introduces the procedure of PI planning using manual as well as the results of the dry-run, with the Yokosuka area as a hypothetical PI area, where the monstraction study is under way. Based on the dry-run, applicability of the manual is checked and, at the same time, further revisions are made to improve the content. (author)

  13. Effect of corrosive marine atmosphere on construction materials in Tanzania: Exposure sites and preliminary results

    Mmari, A.G.; Uiso, C.B.S.; Makundi, I.N.; Potgieter-Vermaak, S.S.; Potgieter, J.H.; Van Grieken, R.

    2007-01-01

    Air pollution studies in Africa are limited and the influence of ambient air quality on buildings and constructions have not been investigated in the larger part of Sub-Saharan Africa. The increasing burden of emission from industry, traffic and coal power plants on ambient air pollution in Sub-Saharan Africa necessitated reviewing previous and current studies. In South Africa a 20-year exposure program, focusing on the effect of ambient exposure on various metals and alloys, showed that the amount of rainfall, relative humidity, atmospheric pollution, wind speed, solar radiation and structural design are some of the factors controlling atmospheric corrosion. Tanzania, being among the Sub-Saharan African countries and partly bordered by Indian ocean, the main source of marine atmosphere, experiences corrosive degradation on metal roofing and cementitious materials. This paper describes the exposure site set-up and will report on some preliminary results of air quality and its relation with the meteorological conditions, as well as surface changes observed, for the year one of exposure. These will thereafter be compared to the completed European and Asian studies, as reported by CLRTAP and RAPIDC respectively. (author)

  14. Groundwater chemical changes at SFR in Forsmark

    Laaksoharju, Marcus [GeoPoint AB, Sollentuna (Sweden); Gurban, Ioana [3DTerra (Sweden)

    2003-01-01

    The examination of the groundwater sampled at the SFR tunnel system indicated that the groundwater consist mainly of a Na-Cl to Na-Ca-Cl type of water. Most of the samples fall within the Cl range of 2500-5500 mg/l having a neutral pH (6.6-7.7 units). The water is reducing and despite the fact that the tunnel acts like a hydraulic sink constantly withdrawing water out from the rock into the tunnel the groundwater changes are moderate with time. Most of the sampling points in the SFR tunnel system are located under the Sea and M3 calculations indicated that most of the sampling points have a change of water types from an older marine water type affected by glacial melt water to an more modern marine water type such as Baltic Sea water which has been modified by possibly microbial sulphate reduction and ion exchange. Mass balance calculations indicated that the waters seem to be in equilibrium with the fracture filling mineral such as calcite. The quality of the aluminium data made the modelling with the major rock forming aluminium silicates such as feldspars and clay minerals uncertain and was therefore not reported. The conclusion is that the groundwater evolution and patterns at SFR are a result of many factors such as: 1. the changes in hydrogeology related to glaciation/deglaciation and land uplift, 2. repeated Sea/lake water regressions/transgressions 3. the closeness to Baltic Sea resulting in relative small hydrogeological driving forces which could preserve old water types from being flushed out, 4. organic or inorganic alteration of the groundwater caused by microbial processes or in situ water/rock interactions 5. tunnel construction which changed the flow system The modelled present-day groundwater conditions of the SFR site consist of a mixture in varying degrees of different water types. The data indicate that all the groundwater at SFR is strongly affected by Sea water of different origin and ages. The meteoric (0- 1000 B.P) portion is located close

  15. Quantitative assessment of radionuclide retention in the near-surface system at Forsmark. Development of a reactive transport model using Forsmark 1.2 data

    Grandia, Fidel; Sena, Clara; Arcos, David; Molinero, Jorge; Duro, Lara; Bruno, Jordi (Amphos XXI Consulting S.L., Barcelona (Spain))

    2007-12-15

    The main objective of this work is to assess the migration behaviour of selected long-lived radionuclides through the near-surface system of Forsmark, with special focus on the evaluation of the capacity of the Quaternary deposits and sediments for radionuclide retention. The work reported here is based on data and information from Forsmark Site Descriptive Model version 1.2. From the geological point of view, the near-surface systems in the Forsmark area consist of Quaternary deposits and sediments that overlay the granitic bedrock. Glacial till is the more abundant outcropping Quaternary deposit and the remainder is made of clayey deposits. These types of near-surface sediments show distinctive hydraulic and geochemical features. The main reactive mineral in the till deposits, for the time horizons considered in this work, is calcium carbonate together with minor amounts of clay minerals (e.g. illite). The till deposits forms aquifers with relatively high hydraulic conductivities. In contrast, glacial and post-glacial clays are basically composed of illite with low to very low amounts of calcium carbonate, and containing organic matter-rich layers (gyttja), which can promote reducing conditions in the porewaters. All these clays exhibits relatively low hydraulic conductivity values. Five radionuclides have been selected for conceptualization and qualitative evaluation of retention process: U as an actinide, Se as a redox-sensitive radionuclide, Cs as a monovalent cation, Sr as a divalent cation, and I as an anion radionuclide. Overall, radionuclide retention capacity in the surface systems at Forsmark can be provided by sorption on charged surfaces of clays and oxyhydroxides, co-precipitation with sulphates, sulphides, oxyhydroxides and carbonates, and sorption on organic matter. Two-dimensional coupled hydrogeological and reactive solute transport models have been developed to simulate the geochemical behaviour of U, Cs and Sr. These three radionuclides have

  16. Preventive maintenance at the Forsmark Nuclear Power Plant

    Danielsson, H.

    1985-01-01

    The maintenance system at the Forsmark Nuclear Power Plant began in 1975, and was drawn up in co-operation with other power stations within the control of the Swedish State Power Board. Preventive maintenance (PM) is part of the system and has been in operation since 1978. Great efforts have been made to build up the system and to gather input data. Since 1981, the system has been in continuous use; follow-ups and system and quality improvements in database contents have been carried out. Great effort has also been devoted to maintaining a high quality of database contents and to the interplay between the different PM measures. We believe that PM plays an important role in the safety and economic operation of the power station and that it is essential that interest in PM should exist at all levels of the power company. (author)

  17. Inventory of vegetation and benthos in newly laid and natural ponds in Forsmark 2012

    Qvarfordt, Susanne; Wallin, Anders; Borgiel, Micke

    2013-01-01

    SKB plans to build a repository for the spent nuclear fuel. The repository is planned to be built in Forsmark and constitutes installations above and below ground. The building and operation of the construction will involve activities that might affect the nature in the area. The impact means, among other things, that a small water body, which today is a reproduction site for the red listed pool frog (Rana lessonae), will disappear. The lost locality for the pool frog has been compensated by creating four new ponds in the Forsmark area. This study is part of the follow-up of these new habitats. The aim is to describe the plant and animal communities in the ponds, and follow the succession, i.e. the development of the habitats. The study also includes two natural ponds that will serve as reference objects. The survey of vegetation and invertebrate fauna in the ponds was conducted in October 2012. The results show that the new ponds had low coverage of submersed vegetation and the species composition in the plant communities differed between the ponds. The reference ponds also had different plant communities, both in terms of species composition and coverage. This indicates that the species composition of the plant communities in the new ponds will likely depend on physical factors specific to the respective pond, but that higher vegetation coverage can be expected over time in all new ponds. The reference ponds had similar animal communities that differed from the animal communities in the new ponds. The similar species composition in the reference ponds, despite the variety of plant communities, suggests that similar animal communities are likely to develop in the new ponds, even if the plant communities continues to be different. Water chemical sampling has also been conducted in the ponds during 2012. A comparison of the inorganic environment (with regard to analysed ions) showed that the reference ponds had relatively similar ion compositions with little

  18. Preliminary recommendations on the design of the characterization program for the Hanford Site single-shell tanks: A system analysis

    Buck, J.W.; Peffers, M.S.; Hwang, S.T.

    1991-11-01

    The work described in this volume was conducted by Pacific Northwest Laboratory to provide preliminary recommendations on data quality objectives (DQOs) to support the Waste Characterization Plan (WCP) and closure decisions for the Hanford Site single-shell tanks (SSTs). The WCP describes the first of a two-phase characterization program that will obtain information to assess and implement disposal options for SSTs. This work was performed for the Westinghouse Hanford Company (WHC), the current operating contractor on the Hanford Site. The preliminary DQOs contained in this volume deal with the analysis of SST wastes in support of the WCP and final closure decisions. These DQOs include information on significant contributors and detection limit goals (DLGs) for SST analytes based on public health risk

  19. Stress variations during a glacial cycle at 500 m depth in Forsmark and Oskarshamn: Earth model effects

    Lund, Bjoern [Uppsala Univ. (Sweden). Dept. of Earth Sciences

    2006-06-15

    This study has considered the response to a glaciation of Earth models of increasingly complex structure in elastic parameters and viscosity. The models are one-dimensional in the sense that they vary only in the depth direction, i.e. there are only uniform, horizontal layers in the models. I find that as the complexity of the models increase, and the properties of the uppermost kilometer of the Earth become less affected by average properties from deeper down, the flexural stresses at 500 m depth decrease, as expected. A lower Young's modulus, lower compressibility and lower density in the uppermost layer all act to lower the stresses. However, the three properties act differently on the resulting response. Introducing layering in Young's modulus generally decreases the stresses all along a profile through the ice model. Going from incompressible to compressible models affect the stresses outside the ice edge significantly more than the stresses under the ice sheet. Introducing layering in density conversely affect the stresses under the ice sheet more than those outside the ice edge. The combined effects of the most complex models tested here show that the glacially induced horizontal stresses at 500 m depth decrease to levels very similar in magnitude to the loading stress. There are, however, temporal variations in these horizontal stresses that do not follow the loading stress and which induce tensional or compressional horizontal stresses that persist when no ice is present.As is well known, changes in viscosity structure has a very large effect on the Earth response. Viscosity affect both the magnitudes of the induced stresses and the temporal behavior of the stress evolution. This is confirmed in the current study.The glacially induced stresses for some of the models have been used in combination with the current background stress field at Forsmark and Oskarshamn, as estimated in SKB's site models, to evaluate fault stability throughout a

  20. Stress variations during a glacial cycle at 500 m depth in Forsmark and Oskarshamn: Earth model effects

    Lund, Bjoern

    2006-06-01

    This study has considered the response to a glaciation of Earth models of increasingly complex structure in elastic parameters and viscosity. The models are one-dimensional in the sense that they vary only in the depth direction, i.e. there are only uniform, horizontal layers in the models. I find that as the complexity of the models increase, and the properties of the uppermost kilometer of the Earth become less affected by average properties from deeper down, the flexural stresses at 500 m depth decrease, as expected. A lower Young's modulus, lower compressibility and lower density in the uppermost layer all act to lower the stresses. However, the three properties act differently on the resulting response. Introducing layering in Young's modulus generally decreases the stresses all along a profile through the ice model. Going from incompressible to compressible models affect the stresses outside the ice edge significantly more than the stresses under the ice sheet. Introducing layering in density conversely affect the stresses under the ice sheet more than those outside the ice edge. The combined effects of the most complex models tested here show that the glacially induced horizontal stresses at 500 m depth decrease to levels very similar in magnitude to the loading stress. There are, however, temporal variations in these horizontal stresses that do not follow the loading stress and which induce tensional or compressional horizontal stresses that persist when no ice is present.As is well known, changes in viscosity structure has a very large effect on the Earth response. Viscosity affect both the magnitudes of the induced stresses and the temporal behavior of the stress evolution. This is confirmed in the current study.The glacially induced stresses for some of the models have been used in combination with the current background stress field at Forsmark and Oskarshamn, as estimated in SKB's site models, to evaluate fault stability throughout a glacial cycle. The

  1. Sediment dynamics in the coastal areas of Forsmark and Laxemar during an interglacial

    Brydsten, Lars

    2009-06-01

    been evaluated within the project. It is based on a digital elevation model (DEM) covering the Baltic Sea and its surroundings (negative values for the sea and positive values for the land) that have also been evaluated within the project. The DEM is based on elevation data from many different sources that is merged into a common coordinate system and a common height system. These irregularly spaced data have been used to interpolate a regular DEM. For each time step, this DEM has been corrected to those circumstances prevalent at that date using shore displacement equations for about 80 places around the Baltic Sea. This correction accounts for the special conditions that existed during periods when the Baltic Sea was a lake. The bathymetry of the high-resolution model domains at Forsmark and Laxemar are based on existing 20 m resolution DEMs. The change in bathymetry over time for these areas is calculated using the shore displacement equations for three sites close to each model site, a strategy that makes it possible to investigate the tilt of the landscape. This factor has some significance early and late in the modelled period. It is impossible to run the model for all combinations of wind directions and wind speeds at each time step due to time reason, so only wind directions from long fetches and two critical wind speeds are simulated. The two critical wind speeds are expected to show changes in the extensions of three sea bottom types: 1) erosion bottoms where the resuspension frequency is so high that a particle is settled for maximum of one month, 2) accumulation bottoms where resuspension is not occurring, and 3) transport bottoms where a particle can be settled for one month to 500 years. The higher wind speed is chosen so that it possibly occurs at least at one occasion each 500 years with a wind direction approximately parallel with the longest fetch and with duration enough to make the fetch the only limiting factor for the wave generation. The lower

  2. Artificially regenerating longleaf pine on wet sites: preliminary analysis of effects of site preparation treatments on early survival and growth

    Benjamin O. Knapp; G. Geoff Wang; Joan L. Walker

    2010-01-01

    Our study, conducted over two years on poorly drained, sandy sites in Onslow County, NC, compared the effects of eight common site preparation treatments on early survival and growth of planted longleaf pine seedlings. Through two growing seasons, we found survival to be similar across all treatments (p = 0.8806), but root collar diameter was greatest with combinations...

  3. Solid/liquid partition coefficients (Kd) for selected soils and sediments at Forsmark and Laxemar-Simpevarp

    Sheppard, Steve; Long, Jeff; Sanipelli, Barb [ECOMatters Inc., Pinawa (Canada); Sohlenius, Gustav [Geological Survey of Sweden (SGU), Uppsala (Sweden)

    2009-03-15

    Soil and sediment solid/liquid partition coefficients (Kd) are used to indicate the relative mobility of radionuclides and elements of concern from nuclear fuel waste, as well as from other sources. The Kd data are inherently extremely variable, but also vary systematically with key environmental attributes. For soil Kd, the key variables are pH, clay content and organic carbon content. For sediment Kd, water type (freshwater versus marine) and sediment type (benthic versus suspended) are important. This report summarized Kd data for soils and sediments computed from indigenous stable element concentrations measured at the Forsmark and Laxemar-Simpevarp sites. These were then compared to several literature sources of Kd data for Ce, Cl, Co, Cr, Cs, Fe, Ho, I, La, Mn, Mo, Nb, Nd, Ni, Np, Pa, Pb, Pu, Ra, Sb, Se, Sm, Sn, Sr, Tc, Th, Tm, U and Yb. The Kd data computed from indigenous stable element concentrations may be especially relevant for assessment of long-lived radionuclides from deep disposal of waste, because the long time frame for the potential releases is more consistent with the steady state measured using indigenous stable elements. For almost every one of these elements in soils, a statistically meaningful regression equation was developed to allow estimation of Kd for any soil given a modest amount of information about the soil. Nonetheless, the median residual geometric standard deviation (GSD) was 4.3-fold, implying confidence bounds of about 18-fold above and below the best estimate Kd. For sediment, the values are categorised simply by water type and sediment type. The median GSD for sediment Kd as measured at the Forsmark and Laxemar-Simpevarp sites was 2.5-fold, but the median GSD among literature values was as high as 8.6-fold. Clearly, there remains considerable uncertainty in Kd values, and it is important to account for this in assessment applications

  4. Solid/liquid partition coefficients (Kd) for selected soils and sediments at Forsmark and Laxemar-Simpevarp

    Sheppard, Steve; Long, Jeff; Sanipelli, Barb; Sohlenius, Gustav

    2009-03-01

    Soil and sediment solid/liquid partition coefficients (Kd) are used to indicate the relative mobility of radionuclides and elements of concern from nuclear fuel waste, as well as from other sources. The Kd data are inherently extremely variable, but also vary systematically with key environmental attributes. For soil Kd, the key variables are pH, clay content and organic carbon content. For sediment Kd, water type (freshwater versus marine) and sediment type (benthic versus suspended) are important. This report summarized Kd data for soils and sediments computed from indigenous stable element concentrations measured at the Forsmark and Laxemar-Simpevarp sites. These were then compared to several literature sources of Kd data for Ce, Cl, Co, Cr, Cs, Fe, Ho, I, La, Mn, Mo, Nb, Nd, Ni, Np, Pa, Pb, Pu, Ra, Sb, Se, Sm, Sn, Sr, Tc, Th, Tm, U and Yb. The Kd data computed from indigenous stable element concentrations may be especially relevant for assessment of long-lived radionuclides from deep disposal of waste, because the long time frame for the potential releases is more consistent with the steady state measured using indigenous stable elements. For almost every one of these elements in soils, a statistically meaningful regression equation was developed to allow estimation of Kd for any soil given a modest amount of information about the soil. Nonetheless, the median residual geometric standard deviation (GSD) was 4.3-fold, implying confidence bounds of about 18-fold above and below the best estimate Kd. For sediment, the values are categorised simply by water type and sediment type. The median GSD for sediment Kd as measured at the Forsmark and Laxemar-Simpevarp sites was 2.5-fold, but the median GSD among literature values was as high as 8.6-fold. Clearly, there remains considerable uncertainty in Kd values, and it is important to account for this in assessment applications

  5. Results of the preliminary radiological survey at the former Diamond Magnesium Company site, Luckey, Ohio (DML001)

    Foley, R.D.; Crutcher, J.W.

    1990-02-01

    As part of the Formerly Utilized Sites Remedial Action Program, the US Department of Energy (DOE) is implementing a radiological survey program to determine the radiological conditions at sites that were used by the department's predecessor agencies. One such site is the former Diamond Magnesium Company facility in Luckey, Ohio. The preliminary radiological survey discussed in this report was conducted at the request of DOE by members of the Measurement Applications and Development group of Oak Ridge National Laboratory in December 1988. The former Diamond Magnesium Company site in Luckey, Ohio, was used as a magnesium reduction plant during World War 2. It was closed in 1945 and reopened in 1949 as a beryllium production facility, operated by Brush Wellman for the US Atomic Energy Commission. The preliminary radiological survey included: a surface gamma scan of part of the property outdoors, collection of surface and subsurface soil samples, and collection of water samples. Laboratory analysis of soil samples showed concentrations of 226 Ra in excess of applicable DOE guidelines. A follow-up, detailed survey is recommended. 9 refs., 10 figs., 4 tabs

  6. Revising the security organisation at Forsmark NPP - A case study from the point of view of the operator and the regulatory and supervisory authority

    Roeden, B.; Strandberg, L.; Isaksson, S.

    2001-01-01

    Forsmark Nuclear Power Plant consists of three reactor-units. Each unit has separate shift crews and separate control rooms for operation of the plant. During 1996, Forsmarks Kraftgrupp AB (FKA) decided to change the organisation of Security at the site in Forsmark, Sweden. Reasons for changing the Organisation Experiences pointed out that it was necessary to have a Security supervisor present at site 24 hours per day. Experiences were basically gained from occasions when malfunctions in the technical security systems occurred. Another experience was that the procedures describing counter measures to different malfunctions in the technical security systems, did not meet the same high requirements, that would be expected in comparison with the Standard Operational and Emergency Operational Procedures, which are used for operation of the Nuclear Power Plant. It was decided to integrate the Security guards in the shift crew, one guard for each reactor unit and shift. Some of the regular Field Operators in the shift-crews for operating the plant were educated to competent Security Guards. The Shift Supervisor on each reactor unit became in charge for one Security Guard. One of the units also became in charge of the Security Central and the Security Guard operating the technical security systems. During incidents the supervisor from the fire brigade takes the responsibility for the security. He also has additionally two Security Guards at disposal from the fire brigade. In case of a major incident, this arrangement let the Shift Supervisors proceed taking the necessary counter measures concerning the process in the power plant. The attitude to new duties among the regular Field Operators educated to Security Guards were not positive, this problem affected also the attitude among the Shift supervisors. It was difficult to bring the different reactor units to work in the same direction and at the same time, generally speaking. The procedures and standards at each unit

  7. Hydrogeological characterisation and modelling of deformation zones and fracture domains, Forsmark modelling stage 2.2

    Follin, Sven (SF GeoLogic AB, Taeby (SE)); Leven, Jakob (Swedish Nuclear Fuel and Waste Management Co., Stockholm (SE)); Hartley, Lee; Jackson, Peter; Joyce, Steve; Roberts, David; Swift, Ben (Serco Assurance, Harwell (GB))

    2007-09-15

    The work reported here collates the structural-hydraulic information gathered in 21 cored boreholes and 32 percussion-drilled boreholes belonging to Forsmark site description, modelling stage 2.2. The analyses carried out provide the hydrogeological input descriptions of the bedrock in Forsmark needed by the end users Repository Engineering, Safety Assessment and Environmental Impact Assessment; that is, hydraulic properties of deformation zones and fracture domains. The same information is also needed for constructing 3D groundwater flow models of the Forsmark site and surrounding area. The analyses carried out render the following conceptual model regarding the observed heterogeneity in deformation zone transmissivity: We find the geological division of the deterministically modelled deformation zones into eight categories (sets) useful from a hydrogeological point of view. Seven of the eight categories are steeply dipping, WNW, NW, NNW, NNE, NE, ENE and EW, and on is gently dipping, G. All deformation zones, regardless of orientation (strike and dip), are subjected to a substantial decrease in transmissivity with depth. The data gathered suggest a contrast of c. 20,000 times for the uppermost one kilometre of bedrock, i.e. more than four orders of magnitude. The hydraulic properties below this depth are not investigated. The lateral heterogeneity is also substantial but more irregular in its appearance. For instance, for a given elevation and deformation zone category (orientation), the spatial variability in transmissivity within a particular deformation zone appears to be as large as the variability between all deformation zones. This suggests that the lateral correlation length is shorter than the shortest distance between two adjacent observation points and shorter than the category spacing. The observation that the mean transmissivity of the gently-dipping deformation zones is c. one to two orders of magnitude greater than the mean transmissivities of all

  8. Site study plan for regional hydrologic sampling and monitoring: Preliminary draft

    Dutton, A.R.

    1987-01-01

    The purpose of the Regional Hydrologic Studies Plan is to describe those field activities required for completion of the objectives of hydrologic activities. Many of these activities are regional in scope and are designed to provide a framework for understanding the hydrologic setting of the site and the hydrologic processes that influence site characteristics. Site Study Plans (SSPs) define activates at and in the immediate vicinity of the site. The activities specified in the Regional Hydrologic Studies Plan are performed beyond the confines of the site because the hydrologic systems extend beyond the site boundaries, because pertinent data that bear on site suitability are available outside of the site, and because natural analogues exist outside of the site that allow analysis of processes that are expected to operate within the site. 15 refs., 5 figs., 1 tab

  9. 75 FR 984 - Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA and RCRA Sites

    2010-01-07

    ...The Environmental Protection Agency (EPA or the Agency) is announcing a 50-day public comment period for draft recommended interim preliminary remediation goals (PRGs) developed in the Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) Sites. EPA's Office of Solid Waste and Emergency and Emergency Response (OSWER) has developed the draft recommended interim PRGs for dioxin in soil. These draft recommended interim PRGs were calculated using existing, peer- reviewed toxicity values and current EPA equations and default exposure assumptions. This Federal Register notice is intended to provide an opportunity for public comment on the draft recommended interim PRGs. EPA will consider any public comments submitted in accordance with this notice and may revise the draft recommended interim PRGs thereafter.

  10. Lessons learned from the preliminary performance assessment exercise for the Vienne site strategies for investigating the granodiorite confinement capability

    Lebon, P.

    1999-01-01

    One of the three sites under study by ANDRA is located on the Poitou shoal in the Vienne Department. The granitic basement rock is overlain by a 160 m thick layer of Jurassic sediments containing two seasonally pumped aquifers. The preliminary hydrogeological model of the granitic basement assumed that regional flow is SE-NW, and circulates in the hecto-metric fractures, and that groundwater flow velocity is very low. A preliminary performance assessment exercise focusing on the geological barrier was carried out based on these assumptions and a disposal concept where radwaste is stored in separate granodiorite 'blocks' delimited by the water-bearing fractures. As regards of the granodioritic blocks, the programme goals include analysing of detailed structure, obtaining uncontaminated samples of interstitial ground water in order to determine its physicochemical properties and evaluating transport and retention parameters. (author)

  11. Effect of ionizing radiation on radionuclide speciation: Preliminary results from site-specific experiments in a basaltic system

    Reed, D.T.; Burnell, J.R.

    1986-01-01

    Rockwell Hanford Operations, under contract to the Department of Energy, is investigating the suitability of the Hanford site in the state of Washington as a high level nuclear waste repository. An important consideration in these investigations is the effect of ionizing radiation on the speciation of radionuclides in the groundwater after the high-level-waste container has been breached and there is direct contact between the groundwater and the waste form (controlled released period). The effect of ionizing radiation on radionuclide speciation depends on the radiation environment and site-specific chemistry near the waste container. With respect to these two aspects, the following results will be presented: a definition of the radiation environment during the controlled release period; preliminary site-specific experimental results: (1) basaltic systems spiked with radionuclides; (2) spent fuel-groundwater-basalt experiments

  12. Uptake of elements by fungi in the Forsmark area

    Johanson, Karl J.; Nikolova, Ivanka; Taylor, Andy F.S. [Swedish Univ. of Agricultural Sciences, Uppsala (Sweden). Dept. of Forest Mycology and Pathology; Vinichuk, Mykhaylo M. [Swedish Univ. of Agricultural Sciences, Uppsala (Sweden). Dept. of Soil Sciences

    2004-10-01

    Samples were collected in a forest ecosystem close to the Nuclear Power Plant at Forsmark, Sweden. The soil was fractioned in bulk soil, rhizosphere, soil-root interface and fungal mycelium. At the same sampling sites, fruit bodies of fungi were also collected. The concentration (mg/kg dw of soil) of K, Rb, Cs, P, Ca, Cr, Mn, Co, Ni, Cu, Zn, As, Sr, Cd, I, Hg, Pb, Ra, Th and U, were analysed in the various fractions using microspectrometry. The concentration of the stable potassium, rubidium and cesium in forest soil as well as in fungal compartment is discussed first and than the other 17 elements is discussed. Compared to bulk soil, rhizosphere was enriched with K, Rb and Cs by a factor 1.3, 1.7 and 1.5, and soil-root interface by factor 5.4, 2.6 and 1.0. Concentration of K, Rb and Cs was much higher in mycelium compared to bulk soil, indicating accumulation of these elements within fungi. The concentration ratios (CR) defined as mg/kg dw in mycelium divided by mg/kg dw in soil were found to be 4.5, 5.1 and 2.4 for K, Rb and Cs respectively. For fruit bodies of fungi, these ratios were about one order of magnitude higher than that for mycelium: 65, 3. 75.8 and 18.6 for K, Rb and Cs, respectively. In mycelium, only weak correlations were found between K and Rb uptake (r=0.33) and between K and Cs uptake (r=0.48). The concentrations of the elements in fruit bodies of fungi were species-dependent. Generally, fungi seemed to take up Rb more efficiently than K. Highest Cs concentrations were found in fruit bodies of Sarcodon imbricatus (25.1 mg/kg). Sarcodon imbricatus was found to accumulate K, Cs and especially Rb to greatest extent, followed by Cortinarius sp., and Suillus variegatus. Litter decomposing fungi Hypholoma capnoides and Collybia peronata showed relatively weak ability to accumulate K, Rb as well as Cs, compared to the mycorrhizal species. No correlation was found between concentration of K, Rb and Cs in fruit bodies of fungi and soil pH as well as

  13. Uptake of elements by fungi in the Forsmark area

    Johanson, Karl J.; Nikolova, Ivanka; Taylor, Andy F.S.; Vinichuk, Mykhaylo M.

    2004-10-01

    Samples were collected in a forest ecosystem close to the Nuclear Power Plant at Forsmark, Sweden. The soil was fractioned in bulk soil, rhizosphere, soil-root interface and fungal mycelium. At the same sampling sites, fruit bodies of fungi were also collected. The concentration (mg/kg dw of soil) of K, Rb, Cs, P, Ca, Cr, Mn, Co, Ni, Cu, Zn, As, Sr, Cd, I, Hg, Pb, Ra, Th and U, were analysed in the various fractions using microspectrometry. The concentration of the stable potassium, rubidium and cesium in forest soil as well as in fungal compartment is discussed first and than the other 17 elements is discussed. Compared to bulk soil, rhizosphere was enriched with K, Rb and Cs by a factor 1.3, 1.7 and 1.5, and soil-root interface by factor 5.4, 2.6 and 1.0. Concentration of K, Rb and Cs was much higher in mycelium compared to bulk soil, indicating accumulation of these elements within fungi. The concentration ratios (CR) defined as mg/kg dw in mycelium divided by mg/kg dw in soil were found to be 4.5, 5.1 and 2.4 for K, Rb and Cs respectively. For fruit bodies of fungi, these ratios were about one order of magnitude higher than that for mycelium: 65, 3. 75.8 and 18.6 for K, Rb and Cs, respectively. In mycelium, only weak correlations were found between K and Rb uptake (r=0.33) and between K and Cs uptake (r=0.48). The concentrations of the elements in fruit bodies of fungi were species-dependent. Generally, fungi seemed to take up Rb more efficiently than K. Highest Cs concentrations were found in fruit bodies of Sarcodon imbricatus (25.1 mg/kg). Sarcodon imbricatus was found to accumulate K, Cs and especially Rb to greatest extent, followed by Cortinarius sp., and Suillus variegatus. Litter decomposing fungi Hypholoma capnoides and Collybia peronata showed relatively weak ability to accumulate K, Rb as well as Cs, compared to the mycorrhizal species. No correlation was found between concentration of K, Rb and Cs in fruit bodies of fungi and soil pH as well as

  14. Chemical Analysis of the Moon at the Surveyor VI Landing Site: Preliminary Results.

    Turkevich, A L; Patterson, J H; Franzgrote, E J

    1968-06-07

    The alpha-scattering experiment aboard soft-landing Surveyor VI has provided a chemical analysis of the surface of the moon in Sinus Medii. The preliminary results indicate that, within experimental errors, the composition is the same as that found by Surveyor V in Mare Tranquillitatis. This finding suggests that large portions of the lunar maria resemble basalt in composition.

  15. Transforming Pinus pinaster forest to recreation site: preliminary effects on LAI, some forest floor, and soil properties.

    Öztürk, Melih; Bolat, İlyas

    2014-04-01

    This study investigates the effects of forest transformation into recreation site. A fragment of a Pinus pinaster plantation forest was transferred to a recreation site in the city of Bartın located close to the Black Sea coast of northwestern Turkey. During the transformation, some of the trees were selectively removed from the forest to generate more open spaces for the recreationists. As a result, Leaf Area Index (LAI) decreased by 0.20 (about 11%). Additionally, roads and pathways were introduced into the site together with some recreational equipment sealing parts of the soil surface. Consequently, forest environment was altered with a semi-natural landscape within the recreation site. The purpose of this study is to assess the effects of forest transformation into recreation site particularly in terms of the LAI parameter, forest floor, and soil properties. Preliminary monitoring results indicate that forest floor biomass is reduced by 26% in the recreation site compared to the control site. Soil temperature is increased by 15% in the recreation site where selective removal of trees expanded the gaps allowing more light transmission. On the other hand, the soil bulk density which is an indicator of soil compaction is unexpectedly slightly lower in the recreation site. Organic carbon (C(org)) and total nitrogen (N(total)) together with the other physical and chemical parameter values indicate that forest floor and soil have not been exposed to much disturbance. However, subsequent removal of trees that would threaten the vegetation, forest floor, and soil should not be allowed. The activities of the recreationists are to be concentrated on the paved spaces rather than soil surfaces. Furthermore, long-term monitoring and management is necessary for both the observation and conservation of the site.

  16. Site study plan for utilities and solid waste, Deaf Smith County Site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    This site plan describes utilities and solid waste studies to be conducted during the characterization of the Deaf Smith County, Texas, site for the US Department of Energy's Salt Repository Project. After utilities and solid waste information needs derived from Federal, State, and local statutes and regulations and the project specifications are briefly described, the site study plan describes the study design and rationale, the field data collection procedures and equipment, and data analysis methods and application of results, the data management strategy, the schedule of field activities, the management of the study, and the study's quality assurance program. The field data collection activities are organized into programs to characterize electrical power, natural gas, communication, water, wastewater sludge, nonradiological solid waste, nonradiological hazardous waste, and low-level radiological waste. These programs include details for the collection of project needs, identification of utilities and solid waste disposal contractor capabilities, and verification of the obtained data. Utilities and solid waste field activities will begin approximately at the time of site access. Utilities and solid waste characterization will be completed within the first year of activity. 29 refs., 6 figs., 2 tabs

  17. Site Study Plan for meteorology/air quality, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Meteorological/Air Quality Site Study Plan describes a field program consisting of continuous measurements of surface (10-meter) wind speed and direction, temperature, humidity, dew point, pressure, and sensible heat flux (vertical). Air quality measurements will be limited to suspended particulate matter. After the first year of measurements, a 60-meter tower will be added to incorporate measurements needed for later modeling and dose calculations; these will include upper level winds, vertical temperature structure, and vertical wind speed. All of these measurements will be made at a site located within the 9-mi 2 site area but remote from the ESF. A second site, located near and downwind from the ESF, will monitor only particulate matter. The SSP describes the need for each study; its design and design rationale; analysis, management, and use of data, schedule of field activities, organization of field personnel and sample management, and quality assurance requirements. These studies will provide data needed to satisfy requirements contained in, or derived from the Salt Repository Project Requirements Document. 38 refs., 8 figs., 3 tabs

  18. Preliminary screening analysis of the off-site environment downstream of the US Department of Energy Oak Ridge Reservation

    Blaylock, B.G.; Hoffman, F.O.; Frank, M.L.

    1990-01-01

    Operations and waste disposal activities at the Y-12 Plant, the Oak Ridge National Laboratory (ORNL), and the Oak Ridge Gaseous Diffusion Plant (ORGDP), located on the US Department of Energy (DOE) Oak Ridge Reservation (ORR) in eastern Tennessee, have introduced airborne, liquid, and solid wastes into the surrounding environment. Some of these wastes may affect off-site areas by entering local streams that ultimately drain into the Clinch River. Previously reported concentrations of radionuclides, metals, and organic compounds in water, sediment, and biota of the Clinch River and Watts Bar Reservoir suggest the presence of contaminants of possible concern to the protection of human health and the environment. A preliminary screening was conducted of contaminants in the off-site surface water environments downstream of the DOE ORR. This screening analysis represents part of a scoping phase of the Clinch River Resource Conservation and Recovery Facilities Investigation (CRRFI). The purpose of this preliminary screening analysis is to use existing data on off-site contaminant concentrations to identify and prioritize potential contaminants of concern for further evaluation and investigation. The primary objective of this screening analysis is to ensure that CRRFI sampling and analysis efforts focus on those contaminants that may possibly contribute to human health or environmental risk. 8 refs., 3 figs., 6 tabs

  19. The Forsmark biotest basin. An instrument for environmental research. Experiences of large cooling water discharges in Sweden (1969-1993) and research perspectives for the future

    Snoeijs, P.

    1994-01-01

    This report presents the Biotest basin at Forsmark (Sweden) as an instrument for experimental environmental research, and indicates possibilities for its future use. the basin consists of a 1 km 2 artificial enclosure in the Baltic Sea that receives cooling water discharge from the Forsmark nuclear power plant. Cooling water discharge was initiated in 1980, and since then the basin has been serving as the main Swedish instrument for field studies on the effects of enhanced temperature and low-dose radioactivity on aquatic ecosystems. Environmental effects of large cooling water discharges from power plants to the sea have been studied at other sites in Sweden too, and for the sake of completeness of background information this report provides a survey and an extensive bibliography of all previous research on cooling water discharges in Sweden during the last 25 years. The aim of scientific research in the Biotest basin is to provide an independent academically-based assessment of the effects of the discharges of heat to the aquatic environment and of the pathways of pollutants through the ecosystems. Until now the research has mainly been describing the ecological effects of the cooling water flow through the basin under normal operation of the power plant. In the future it will be possible to manipulate the basin for large field experiments. An important perspective for the future is that of climatic change; the Forsmark Biotest basin provides excellent conditions for field studies on possible biological effects. This includes e.g. temperature effects on basic biological processes (growth, metabolism, reproduction etc.), population genetics, and combination effects of heat and toxic substances. 60 refs, 3 figs, 6 tabs

  20. Preliminary site investigation for LL and IL radwaste disposal for Qinshan NPP

    Huang Yawen; Chen Zhangru

    1993-01-01

    With the purpose of selecting a disposal site for the low- and intermediate-level radwastes arising from Qinshan NPP, site investigations were carried out in several districts of Zhejiang Province. Investigation objectives included the circumstances of geology, hydrogeology, environmental ecology, and social economy. On the basis of collected data, five possible sites were recommended for policy-making reference and further investigation

  1. Mammals in the areas adjacent to Forsmark and Oskarshamn. Population density, ecological data and carbon budget

    Truve, Johan; Cederlund, Goeran [Svensk Naturfoervaltning AB, Ramsberg (Sweden)

    2005-06-01

    The Swedish Nuclear Fuel and Waste Management Co is in the process of selecting a safe and environmentally acceptable location for the deep-level repository of radioactive waste. SKB has expressed the importance of monitoring mammal species that are of interest both in biodiversity issues and for local hunting and recreational purposes. Two of the major goals are to: 1) monitor dynamics of population density over several years; 2) obtain information that is essential for modelling of energy/carbon flows in the biosphere and ultimately calculations of the risks of exposure to radionuclides. This report contributes to the major goals by presenting: Results from surveys of mammal abundance in the study sites near Forsmark and Oskarshamn, and a comparison with data from other surveys. A summary of traits associated to demography, resource selection and spatial distribution. A model framework that can be used to model the future development of populations. A plausible future scenario for mammal species. Mammal contribution to fluxes of energy and material in the ecosystem. Estimated harvest rates of mammals in the study sites. General conclusions that can be drawn from the survey are that population densities of the most common species are in the same range as many other populations. Lynx, wild boar, red deer and fallow deer are expanding in the areas. Marine mammals have not been surveyed but at least grey seals are important top consumers in the coastal ecosystem. Red listed species resident in the areas are Lynx, Otter, Whiskered bat, Natterer's bat, Nathusius' pipistrelle and Harbour seal. Annual production of the mammal species that were surveyed was 40-50 mg carbon/m2 and year. Hunters harvest nearly half of the production each year. Future developments for the populations are briefly discussed and a model framework that can be used to make better quantitative predictions is presented.

  2. Mammals in the areas adjacent to Forsmark and Oskarshamn. Population density, ecological data and carbon budget

    Truve, Johan; Cederlund, Goeran [Svensk Naturfoervaltning AB, Ramsberg (Sweden)

    2005-06-01

    The Swedish Nuclear Fuel and Waste Management Co is in the process of selecting a safe and environmentally acceptable location for the deep-level repository of radioactive waste. SKB has expressed the importance of monitoring mammal species that are of interest both in biodiversity issues and for local hunting and recreational purposes. Two of the major goals are to: 1) monitor dynamics of population density over several years; 2) obtain information that is essential for modelling of energy/carbon flows in the biosphere and ultimately calculations of the risks of exposure to radionuclides. This report contributes to the major goals by presenting: Results from surveys of mammal abundance in the study sites near Forsmark and Oskarshamn, and a comparison with data from other surveys. A summary of traits associated to demography, resource selection and spatial distribution. A model framework that can be used to model the future development of populations. A plausible future scenario for mammal species. Mammal contribution to fluxes of energy and material in the ecosystem. Estimated harvest rates of mammals in the study sites. General conclusions that can be drawn from the survey are that population densities of the most common species are in the same range as many other populations. Lynx, wild boar, red deer and fallow deer are expanding in the areas. Marine mammals have not been surveyed but at least grey seals are important top consumers in the coastal ecosystem. Red listed species resident in the areas are Lynx, Otter, Whiskered bat, Natterer's bat, Nathusius' pipistrelle and Harbour seal. Annual production of the mammal species that were surveyed was 40-50 mg carbon/m2 and year. Hunters harvest nearly half of the production each year. Future developments for the populations are briefly discussed and a model framework that can be used to make better quantitative predictions is presented.

  3. Mammals in the areas adjacent to Forsmark and Oskarshamn. Population density, ecological data and carbon budget

    Truve, Johan; Cederlund, Goeran

    2005-06-01

    The Swedish Nuclear Fuel and Waste Management Co is in the process of selecting a safe and environmentally acceptable location for the deep-level repository of radioactive waste. SKB has expressed the importance of monitoring mammal species that are of interest both in biodiversity issues and for local hunting and recreational purposes. Two of the major goals are to: 1) monitor dynamics of population density over several years; 2) obtain information that is essential for modelling of energy/carbon flows in the biosphere and ultimately calculations of the risks of exposure to radionuclides. This report contributes to the major goals by presenting: Results from surveys of mammal abundance in the study sites near Forsmark and Oskarshamn, and a comparison with data from other surveys. A summary of traits associated to demography, resource selection and spatial distribution. A model framework that can be used to model the future development of populations. A plausible future scenario for mammal species. Mammal contribution to fluxes of energy and material in the ecosystem. Estimated harvest rates of mammals in the study sites. General conclusions that can be drawn from the survey are that population densities of the most common species are in the same range as many other populations. Lynx, wild boar, red deer and fallow deer are expanding in the areas. Marine mammals have not been surveyed but at least grey seals are important top consumers in the coastal ecosystem. Red listed species resident in the areas are Lynx, Otter, Whiskered bat, Natterer's bat, Nathusius' pipistrelle and Harbour seal. Annual production of the mammal species that were surveyed was 40-50 mg carbon/m2 and year. Hunters harvest nearly half of the production each year. Future developments for the populations are briefly discussed and a model framework that can be used to make better quantitative predictions is presented

  4. TRANSIT: model for providing generic transportation input for preliminary siting analysis

    McNair, G.W.; Cashwell, J.W.

    1985-02-01

    To assist the US Department of Energy's efforts in potential facility site screening in the nuclear waste management program, a computerized model, TRANSIT, is being developed. Utilizing existing data on the location and inventory characteristics of spent nuclear fuel at reactor sites, TRANSIT derives isopleths of transportation mileage, costs, risks and fleet requirements for shipments to storage sites and/or repository sites. This technique provides a graphic, first-order method for use by the Department in future site screening efforts. 2 refs

  5. Chemical characteristics of surface systems in the Forsmark area. Visualisation and statistical evaluation of data from surface water, precipitation, shallow groundwater, and regolith

    NONE

    2006-02-15

    The Swedish Nuclear Fuel and Waste management Co (SKB) initiated site investigations for a deep repository for spent nuclear fuel at two different sites in Sweden, Forsmark and Oskarshamn, in 2002. This report evaluates the results from chemical investigations of the surface system in the Forsmark area during the period November 2002 - March 2005. The evaluation includes data from surface waters (lakes, streams and the sea), precipitation, shallow groundwater and regolith (till, soil, peat, sediments and biota) in the area. Results from surface waters are not presented in this report since these were treated in a recently published report. The main focus of the study is to visualize the vast amount of data collected hitherto in the site investigations, and to give a chemical characterisation of the investigated media at the site. The results will be used to support the site descriptive models, which in turn are used for safety assessment studies and for the environmental impact assessment. The data used consist of water chemical composition in lakes, streams, coastal sites, and in precipitation, predominantly sampled on a monthly basis, and in groundwater from soil tubes and wells, sampled up to four times per year. Moreover, regolith data includes information on the chemical composition of till, soil, sediment and vegetation samples from the area. The characterisations include all measured chemical parameters, i.e. major and minor constituents, trace elements, nutrients, isotopes and radio nuclides, as well as field measured parameters. The evaluation of data from each medium has been divided into the following parts: Characterisation of individual sampling sites, and comparisons within and among sampling sites as well as comparisons with local, regional and national reference data; Analysis of time trends and seasonal variation (for shallow groundwater); Exploration of relationships among the various chemical parameters. For all investigated parameters, the

  6. Chemical characteristics of surface systems in the Forsmark area. Visualisation and statistical evaluation of data from shallow groundwater, precipitation, and regolith

    Troejbom, Mats; Soederbaeck, Bjoern

    2006-02-01

    The Swedish Nuclear Fuel and Waste management Co (SKB) initiated site investigations for a deep repository for spent nuclear fuel at two different sites in Sweden, Forsmark and Oskarshamn, in 2002. This report evaluates the results from chemical investigations of the surface system in the Forsmark area during the period November 2002 - March 2005. The evaluation includes data from surface waters (lakes, streams and the sea), precipitation, shallow groundwater and regolith (till, soil, peat, sediments and biota) in the area. Results from surface waters are not presented in this report since these were treated in a recently published report. The main focus of the study is to visualize the vast amount of data collected hitherto in the site investigations, and to give a chemical characterisation of the investigated media at the site. The results will be used to support the site descriptive models, which in turn are used for safety assessment studies and for the environmental impact assessment. The data used consist of water chemical composition in lakes, streams, coastal sites, and in precipitation, predominantly sampled on a monthly basis, and in groundwater from soil tubes and wells, sampled up to four times per year. Moreover, regolith data includes information on the chemical composition of till, soil, sediment and vegetation samples from the area. The characterisations include all measured chemical parameters, i.e. major and minor constituents, trace elements, nutrients, isotopes and radio nuclides, as well as field measured parameters. The evaluation of data from each medium has been divided into the following parts: Characterisation of individual sampling sites, and comparisons within and among sampling sites as well as comparisons with local, regional and national reference data; Analysis of time trends and seasonal variation (for shallow groundwater); Exploration of relationships among the various chemical parameters. For all investigated parameters, the

  7. Preliminary studies on trace element contamination in dumping sites of municipal wastes in India and Vietnam

    Agusa, T.; Kunito, T.; Nakashima, E.; Minh, T. B.; Tanabe, S.; Subramanian, A.; Viet, P. H.

    2003-05-01

    The disposal of wastes in dumping sites has increasingly caused concem about adverse health effects on the populations living nearby. However, no investigation has been conducted yet on contamination in dumping sites of municipal wastes in Asian developing countries. In this study, concentrations of 11 trace elements (V, Cr, Mn, Co, Cu, Zn, Mo, Ag, Cd, Sb and Pb) were detennined in scalp hair from the population living nearby and in soil from dumping sites and control sites of India and Vietnam. Soil samples in dumping site in India showed significantly higher concentrations of some trace elements than soils in control site, whereas this trend was not notable in Vietnam. This is probably due to the fact that the wastes were covered with the soil in the dumping site of Vietnam. Cadmium concentrations in some hair samples of people living near dumping site in India and Vietnam exceeded the level associated with learning disorder in children. Levels of most of the trace elements in hair were significantly higher in dumping site than those in control site in India and Vietnam, suggesting direct or indirect exposure to those elements from dumping wastes. To our knowledge, this is the first study of trace element contamination in dumping sites in India and Vietnam.

  8. Updated model for radionuclide transport in the near-surface till at Forsmark - Implementation of decay chains and sensitivity analyses

    Pique, Angels; Pekala, Marek; Molinero, Jorge; Duro, Lara; Trinchero, Paolo; Vries, Luis Manuel de

    2013-02-01

    The Forsmark area has been proposed for potential siting of a deep underground (geological) repository for radioactive waste in Sweden. Safety assessment of the repository requires radionuclide transport from the disposal depth to recipients at the surface to be studied quantitatively. The near-surface quaternary deposits at Forsmark are considered a pathway for potential discharge of radioactivity from the underground facility to the biosphere, thus radionuclide transport in this system has been extensively investigated over the last years. The most recent work of Pique and co-workers (reported in SKB report R-10-30) demonstrated that in case of release of radioactivity the near-surface sedimentary system at Forsmark would act as an important geochemical barrier, retarding the transport of reactive radionuclides through a combination of retention processes. In this report the conceptual model of radionuclide transport in the quaternary till at Forsmark has been updated, by considering recent revisions regarding the near-surface lithology. In addition, the impact of important conceptual assumptions made in the model has been evaluated through a series of deterministic and probabilistic (Monte Carlo) sensitivity calculations. The sensitivity study focused on the following effects: 1. Radioactive decay of 135 Cs, 59 Ni, 230 Th and 226 Ra and effects on their transport. 2. Variability in key geochemical parameters, such as the composition of the deep groundwater, availability of sorbing materials in the till, and mineral equilibria. 3. Variability in hydraulic parameters, such as the definition of hydraulic boundaries, and values of hydraulic conductivity, dispersivity and the deep groundwater inflow rate. The overarching conclusion from this study is that the current implementation of the model is robust (the model is largely insensitive to variations in the parameters within the studied ranges) and conservative (the Base Case calculations have a tendency to

  9. Updated model for radionuclide transport in the near-surface till at Forsmark - Implementation of decay chains and sensitivity analyses

    Pique, Angels; Pekala, Marek; Molinero, Jorge; Duro, Lara; Trinchero, Paolo; Vries, Luis Manuel de [Amphos 21 Consulting S.L., Barcelona (Spain)

    2013-02-15

    The Forsmark area has been proposed for potential siting of a deep underground (geological) repository for radioactive waste in Sweden. Safety assessment of the repository requires radionuclide transport from the disposal depth to recipients at the surface to be studied quantitatively. The near-surface quaternary deposits at Forsmark are considered a pathway for potential discharge of radioactivity from the underground facility to the biosphere, thus radionuclide transport in this system has been extensively investigated over the last years. The most recent work of Pique and co-workers (reported in SKB report R-10-30) demonstrated that in case of release of radioactivity the near-surface sedimentary system at Forsmark would act as an important geochemical barrier, retarding the transport of reactive radionuclides through a combination of retention processes. In this report the conceptual model of radionuclide transport in the quaternary till at Forsmark has been updated, by considering recent revisions regarding the near-surface lithology. In addition, the impact of important conceptual assumptions made in the model has been evaluated through a series of deterministic and probabilistic (Monte Carlo) sensitivity calculations. The sensitivity study focused on the following effects: 1. Radioactive decay of {sup 135}Cs, {sup 59}Ni, {sup 230}Th and {sup 226}Ra and effects on their transport. 2. Variability in key geochemical parameters, such as the composition of the deep groundwater, availability of sorbing materials in the till, and mineral equilibria. 3. Variability in hydraulic parameters, such as the definition of hydraulic boundaries, and values of hydraulic conductivity, dispersivity and the deep groundwater inflow rate. The overarching conclusion from this study is that the current implementation of the model is robust (the model is largely insensitive to variations in the parameters within the studied ranges) and conservative (the Base Case calculations have a

  10. A study on landscape and the historical geography of two areas - Oskarshamn and Forsmark

    Jansson, Ulf; Berg, Johan; Bjoerklund, Annika

    2004-06-01

    The aim of this project is to investigate the land-use; the settlement and the way people have used and affected the landscape in two areas, Forsmark and Simpevarp. This preliminary report aim mainly at describing the sources and methods used in the project. Some analyses are undertaken, but a more complete interpretation will take place in the final report of Phase two. This is a project that forms a part of the environmental impact assessment work that is done for examining potential locations for a plant for a deep repository for spent nuclear fuel. Both areas are located on the East Coast of Sweden. A number of scientific studies are carried out in this project. Fields that are included studies for the EIA and the safety assessment include geology, quaternary geology, limnology, biology and other natural sciences that focus on vegetation and the terrestrial as well as the aquatic environment.The study that is carried out at the Department of Human geography at Stockholm university is basically a study of the historical land-use, the changes in settlement and how people have been working and using the landscape over the last centuries.The methods used include historical maps, cadastral material and in a later phase interviews and fieldwork. In the first phase that ends the summer 2004 the bulk of the historical material is probed and analysed. A big effort is put into the creation of GIS-data sets that can be used for further analyses. The work during spring 2004 resulted in this preliminary report that deal with historical land-use, population, settlement from medieval times to the present and both detailed and general descriptions and investigations of the historical geography of the areas.Both the investigated areas are located by the Baltic, but are very different both physically, especially with the land upheaval in the north, and historically with a different land-use system, ownership structure and distribution of settlement. The results of this study

  11. A study on landscape and the historical geography of two areas - Oskarshamn and Forsmark

    Jansson, Ulf; Berg, Johan; Bjoerklund, Annika [Stockholm Univ. (Sweden). Dept. of Human Geography

    2004-06-01

    The aim of this project is to investigate the land-use; the settlement and the way people have used and affected the landscape in two areas, Forsmark and Simpevarp. This preliminary report aim mainly at describing the sources and methods used in the project. Some analyses are undertaken, but a more complete interpretation will take place in the final report of Phase two. This is a project that forms a part of the environmental impact assessment work that is done for examining potential locations for a plant for a deep repository for spent nuclear fuel. Both areas are located on the East Coast of Sweden. A number of scientific studies are carried out in this project. Fields that are included studies for the EIA and the safety assessment include geology, quaternary geology, limnology, biology and other natural sciences that focus on vegetation and the terrestrial as well as the aquatic environment.The study that is carried out at the Department of Human geography at Stockholm university is basically a study of the historical land-use, the changes in settlement and how people have been working and using the landscape over the last centuries.The methods used include historical maps, cadastral material and in a later phase interviews and fieldwork. In the first phase that ends the summer 2004 the bulk of the historical material is probed and analysed. A big effort is put into the creation of GIS-data sets that can be used for further analyses. The work during spring 2004 resulted in this preliminary report that deal with historical land-use, population, settlement from medieval times to the present and both detailed and general descriptions and investigations of the historical geography of the areas.Both the investigated areas are located by the Baltic, but are very different both physically, especially with the land upheaval in the north, and historically with a different land-use system, ownership structure and distribution of settlement. The results of this study

  12. Geoscientific long-term prognosis. Preliminary safety analysis for the site Gorleben; Geowissenschaftliche Langzeitprognose. Bericht zum Arbeitspaket 2. Vorlaeufige Sicherheitsanalyse fuer den Standort Gorleben

    Mrugalla, Sabine [Bundesanstalt fuer Geowissenschaften und Rohstoffe, Hannover (Germany)

    2011-07-15

    The preliminary safety analysis of the site Gorleben includes the following chapters: (1) Introduction; (2) Aim and content of the geoscientific long-term prognosis for the site Gorleben; (3) Boundary conditions at the site Gorleben: climate; geomorphology; overlying rocks and adjoining rocks; hydrogeology; salt deposit Gorleben. (4) Probable future geological developments at the site Gorleben: supraregional developments with effects on the site Gorleben; glacial period developments; developments of the geomorphology, overlying and adjoining rocks; future developments of the hydrological systems at the site Gorleben; future saliniferous specific developments of the salt deposit Gorleben. (5) Commentary on the unlikely or excludable developments of the site Gorleben.

  13. Site Study Plan for background environmental radioactivity, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-06-01

    The Background Environmental Radioactivity Site Study Plan describes a field program consisting of an initial radiological survey and a radiological sampling program. The field program includes measurement of direct radiation and collection and analysis of background radioactivity samples of air, precipitation, soil, water, milk, pasture grass, food crops, meat, poultry, game, and eggs. The plan describes for each study: the need for the study, the study design, data management and use, schedule of proposed activities, and quality assurance requirements. These studies will provide data needed to satisfy requirements contained in, or derived from, the Salt Repository Project (SRP) Requirements Document. 50 refs., 11 figs., 7 tabs

  14. Technical procedures for implementation of acoustics site studies, Deaf Smith County site, Texas: Environmental Field Program: Preliminary draft

    1987-09-01

    The purpose and scope of the technical procedure for processing data from the tethered meteorological system are covered. Definitions, interfaces, and concurrent data needs are also addressed. This technical procedure describes how to control, organize, verify, and archive tethered meteorological system data. These data will be received at the processing location from the field measurement location and are part of the characterization of the Deaf Smith County Site, Texas for the salt repository program. These measurements will be made in support of the sound propagation study and are a result of environmental data requirements for acoustics. 6 refs., 15 figs., 5 tabs

  15. Vegetation mapping with satellite data of the Forsmark and Tierp regions

    Boresjoe-Bronge, Laine; Wester, Kjell [SwedPower, Stockholm (Sweden)

    2002-04-01

    SKB (Swedish Nuclear Fuel and Waste Management Co) performs a siting program for deep repository of spent nuclear fuel that includes survey of three potential sites. The SKB siting process has now reached the site investigation phase. There are several fields of investigations performed in this phase. One of them is description of the surface ecosystems. The surface ecosystems are mapped both on a regional (50-100 km{sup 2} ) and a local level (1 km{sup 2} ). Two inventory methods are used, remote sensing (satellite data/aerial photographs) for the regional level, and field inventory for the detailed level. As a part of the surface ecosystem characterisation on the regional level vegetation mapping using satellite data has been performed over the three potential deep depository sites, Forsmark, Tierp and Oskarshamn. The user requirements for the vegetation mapping of the potential sites are the following: Dominated species in the tree layer, shrub layer, field layer and ground layer shall be described both on regional and local level; Dominated species in all layers shall be quantified regarding share and percentage of ground cover, or absence of cover (vegetation free ground); The regional and the local inventory shall have identical or comparable classification systems; The classification system and the method used shall make it possible to scale the results from local to regional level and vice versa; The produced layers shall be presented in digital form and make it possible to model biomass and turnover of organic matter (carbon, nutrients, water); The produced information shall in a first phase be of use for planning and for making nature and environmental considerations. Data sources used in the study include geo-referenced SPOT4 XI data (20 m ground resolution), geo-referenced Landsat TM data (30 m ground resolution), soil type data, topographic map data and colour infrared aerial photographs. The production of vegetation layers has been carried out in two

  16. Vegetation mapping with satellite data of the Forsmark and Tierp regions

    Boresjoe-Bronge, Laine; Wester, Kjell

    2002-04-01

    SKB (Swedish Nuclear Fuel and Waste Management Co) performs a siting program for deep repository of spent nuclear fuel that includes survey of three potential sites. The SKB siting process has now reached the site investigation phase. There are several fields of investigations performed in this phase. One of them is description of the surface ecosystems. The surface ecosystems are mapped both on a regional (50-100 km 2 ) and a local level (1 km 2 ). Two inventory methods are used, remote sensing (satellite data/aerial photographs) for the regional level, and field inventory for the detailed level. As a part of the surface ecosystem characterisation on the regional level vegetation mapping using satellite data has been performed over the three potential deep depository sites, Forsmark, Tierp and Oskarshamn. The user requirements for the vegetation mapping of the potential sites are the following: Dominated species in the tree layer, shrub layer, field layer and ground layer shall be described both on regional and local level; Dominated species in all layers shall be quantified regarding share and percentage of ground cover, or absence of cover (vegetation free ground); The regional and the local inventory shall have identical or comparable classification systems; The classification system and the method used shall make it possible to scale the results from local to regional level and vice versa; The produced layers shall be presented in digital form and make it possible to model biomass and turnover of organic matter (carbon, nutrients, water); The produced information shall in a first phase be of use for planning and for making nature and environmental considerations. Data sources used in the study include geo-referenced SPOT4 XI data (20 m ground resolution), geo-referenced Landsat TM data (30 m ground resolution), soil type data, topographic map data and colour infrared aerial photographs. The production of vegetation layers has been carried out in two steps. In

  17. Preliminary research on groundwater flow characteristics of the low- and Intermediate-level radioactive waste disposal site

    Koh, Young Kwon; Bae, Dae Seok; Kim, Geon Young; Ryu, Ji Hoon; Park, Kyung Woo; Ji, Sung Hoon; Kim, Kyung Su

    2009-08-01

    Preliminary site survey and candidate survey complements the purpose of the current site selection and disposal place selected for the study because of hydraulic to the geological survey done for the general idea was brought in the field of geochemistry survey was made. Therefore, this report hydraulic - the underlying structure of the model deterministic deformation zone model to focus on the configuration kept, according to data survey by hydraulic and hydraulic rock star pitcher trying to figure out the scope of the structure factors were hydraulic. Groundwater and related land place shares characteristics of the existing data and complementary research and laboratory research performed on the basis of geochemical data, based on the following major finding were present

  18. Preliminary Information on the Vertebrate Fauna (Animalia: Vertebrata of the NATURA2000 Site “Rice Fields Tsalapitsa” (Bulgaria

    Ivayla L. Klimentova

    2011-12-01

    Full Text Available The study was carried out by tree visits in different areas of the Natura 2000 site “Rice Fields Tsalapitsa” BG 0002086 (West of Plovdiv city, near village of Tsalapitsa. Our preliminary research showed that in the area vertebrates with high conservation status occurred included in the Bulgarian Bidiversity Act, Appendix II and III, Appendix II of the Bern convention, Natura 2000 species list, the Bonn convention, Appendix II, the Convention of the International Trade of Endangered Species, and the list of the International Union for Conservation of the Nature. This information will help in future preparation of the management plan of the Natura 2000 site and showed the need of studies focused on such areas which will help undertaking adequate measures for their proper way of conservation.

  19. Preliminary post-closure safety assessment of repository concepts for low level radioactive waste at the Bruce Site, Ontario

    Little, R.H.; Penfold, J.S.S.; Egan, M.J.; Leung, H.

    2005-01-01

    The preliminary post-closure safety assessment of permanent repository concepts for low-level radioactive waste (LLW) at the Ontario Power Generation (OPG) Bruce Site is described. The study considered the disposal of both short and long-lived LLW. Four geotechnically feasible repository concepts were considered (two near-surface and two deep repositories). An approach consistent with best international practice was used to provide a reasoned and comprehensive analysis of post-closure impacts of the repository concepts. The results demonstrated that the deep repository concepts in shale and in limestone, and the surface repository concept on sand should meet radiological protection criteria. For the surface repository concept on glacial till, it appears that increased engineering such as grouting of waste and voids should be considered to meet the relevant dose constraint. Should the project to develop a permanent repository for LLW proceed, it is expected that this preliminary safety assessment would need to be updated to take account of future site-specific investigations and design updates. (author)

  20. Vegetation in the Forsmark biotest basin, 1974-1986

    Renstroem, S.; Svensson, Roger; Wigren-Svensson, M.

    1990-05-01

    Since 1980, Forsmark Power Plants has discharged large amount of cooling water into the Biotest basin. In 1974, before the dam was constructed, and 1980 to 1986, the macrophytic algae and higher vegetation inside and around the basin has been investigated. The observed changes are mainly caused by the increased water temperature causing lack of ice cover during the winter, the embankment reducing the exposition, the heavy water stream through the basin and the reduced light transmission in the water. The macroscopic vegetation in the Biotest basin was originally distributed all over the lake, but is now mainly found in more shallow water. The deepest part, a passage from the input of the cooling water to the output, totally lack vegetation. The reason for this is a combination of the heavy stream, raised temperature and reduced light transmission. The total biomass of macroscopic vegetation in the basin has been reduced from c. 70 metric ton in 1980 to c. 27 ton in 1982 and 1986. Among the most important species, the production of Chara spp. and Potamogeton pectinatus have been strongly reduced, while Cladophora glomerata and Vaucheria sp. have increased. Especially for Vaucheria, the raised temperature has been of vital importance. Among other species, Tolypella nidifica first increased, but has now totally disappeared. Zannichellia palustris was the only phanerogam which increased all the time. It is Z. palustris var. major which stands for the increase, while Z. palustris var. repens has disappeared from the basin. The shore vegetation, mainly reeds, has expanded conspicuously. From 1974 to 1980, the shore vegetation was favoured by the reduced exposition caused by the embankment. Since then, the raised temperature and absence of ice cover have resulted in an accelerating expansion of mainly Phragmites communis. Scirpus tabernaemontani and S. maritimus were first increasing, but do not seem to be able to compete with Phragmites in the long run. (au)

  1. Frictional sliding in layered rock model: Preliminary experiments. Yucca Mountain Site Characterization Project

    Perry, K.E. Jr.; Buescher, B.J.; Anderson, D.; Epstein, J.S.

    1995-09-01

    An important aspect of determining the suitability of Yucca Mountain as a possible nuclear waste repository requires understanding the mechanical behavior of jointed rock-masses. To this end we have studied the frictional sliding between simulated rock joints in the laboratory using the technique of phase shifting moire interferometry. The models were made from stacks of Lexan plates and contained a central hole to induce slip between the plates when the models were loaded in compression. These preliminary results confirm the feasibility of the approach and show a clear evolution of slip as function of load

  2. Documentation of Hanford Site independent review of the Hanford Waste Vitrification Plant Preliminary Safety Analysis Report

    Herborn, D.I.

    1991-10-01

    The requirements for Westinghouse Hanford independent review of the Preliminary Safety Analysis Report (PSAR) are contained in Section 1.0, Subsection 4.3 of WCH-CM-4-46. Specifically, this manual requires the following: (1) Formal functional reviews of the HWVP PSAR by the future operating organization (HWVP Operations), and the independent review organizations (HWVP and Environmental Safety Assurance, Environmental Assurance, and Quality Assurance); and (2) Review and approval of the HWVP PSAR by the Tank Waste Disposal (TWD) Subcouncil of the Safety and Environmental Advisory Council (SEAC), which provides independent advice to the Westinghouse Hanford President and executives on matters of safety and environmental protection. 7 refs

  3. Groundwater flow modelling of periods with periglacial and glacial climate conditions - Forsmark

    Vidstrand, Patrik (TerraSolve AB, Floda (Sweden)); Follin, Sven (SF GeoLogic AB, Taeby (Sweden)); Zugec, Nada (Bergab, Stockholm (Sweden))

    2010-12-15

    As a part of the license application for a final repository for spent nuclear fuel at Forsmark, the Swedish Nuclear Fuel and Waste Management Company (SKB) has undertaken a series of groundwater flow modelling studies. These represent time periods with different hydraulic conditions and the simulations carried out contribute to the overall evaluation of the repository design and long-term radiological safety. The groundwater flow modelling study reported here comprises a coupled thermal-hydraulic-chemical (T-H-C) analysis of periods with periglacial and glacial climate conditions. Hydraulic-mechanical (H-M) issues are also handled but no coupled flow modelling is done. The objective of the report is to provide bounding hydrogeological estimates at different stages during glaciation and deglaciation of a glacial cycle for subsequent use in safety assessment applications within SKB's project SR-Site. Three cases with different climate conditions are analysed here: (i) Temperate case, (ii) Glacial case without permafrost, and (iii) Glacial case with permafrost. The glacial periods are transient and encompass approximately 19,000 years. The simulation results comprise residual fluid pressures, Darcy fluxes, and water salinities, as well as advective transport performance measures obtained by particle tracking such as flow path lengths, travel times and flow-related transport resistances. The modelling is accompanied by a sensitivity study that addresses the impact of the following matters: the direction of the ice sheet advance, the speed of the ice sheet margin, the bedrock hydraulic and transport properties, the temperature at the ice-subsurface interface close to the ice sheet margin, and the initial hydrochemical conditions.

  4. Groundwater flow modelling of periods with periglacial and glacial climate conditions - Forsmark

    Vidstrand, Patrik; Follin, Sven; Zugec, Nada

    2010-12-01

    As a part of the license application for a final repository for spent nuclear fuel at Forsmark, the Swedish Nuclear Fuel and Waste Management Company (SKB) has undertaken a series of groundwater flow modelling studies. These represent time periods with different hydraulic conditions and the simulations carried out contribute to the overall evaluation of the repository design