  1. Maintenance implementation plan for the Plutonium Finishing Plant. Revision 3

    International Nuclear Information System (INIS)

    Meldrom, C.A.

    1996-03-01

    This document outlines the Maintenance Implementation Plan (MIP) for the Plutonium Finishing Plant (PFP) located at the Hanford site at Richland, Washington. This MIP describes the PFP maintenance program relative to DOE order 4330.4B. The MIP defines the key actions needed to meet the guidelines of the Order to produce a cost-effective and efficient maintenance program. A previous report identified the presence of significant quantities of Pu-bearing materials within PFP that pose risks to workers. PFP's current mission is to develop, install and operate processes which will mitigate these risks. The PFP Maintenance strategy is to equip the facility with systems and equipment able to sustain scheduled PFP operations. The current operating run is scheduled to last seven years. Activities following the stabilization operation will involve an Environmental Impact Statement (EIS) to determine future plant activities. This strategy includes long-term maintenance of the facility for safe occupancy and material storage. The PFP maintenance staff used the graded approach to dictate the priorities of the improvement and upgrade actions identified in Chapter 2 of this document. The MIP documents PFP compliance to the DOE 4330.4B Order. Chapter 2 of the MIP follows the format of the Order in addressing the eighteen elements. As this revision is a total rewrite, no sidebars are included to highlight changes

  2. Plutonium Finishing Plant

    Data.gov (United States)

    Federal Laboratory Consortium — The Plutonium Finishing Plant, also known as PFP, represented the end of the line (the final procedure) associated with plutonium production at Hanford.PFP was also...

  3. Plutonium finishing plant dangerous waste training plan

    International Nuclear Information System (INIS)

    ENTROP, G.E.

    1999-01-01

    This training plan describes general requirements, worker categories, and provides course descriptions for operation of the Plutonium Finish Plant (PFP) waste generation facilities, permitted treatment, storage and disposal (TSD) units, and the 90-Day Accumulation Areas

  4. Plutonium Finishing Plant (PFP) hazards assessment

    International Nuclear Information System (INIS)

    Campbell, L.R.

    1998-01-01

    This report documents the hazards assessment for the Plutonium Finishing Plant (PFP) located on the US Department of Energy (DOE) Hanford Site. This hazards assessment was conducted to provide the emergency planning technical basis for the PFP. DOE Orders require an emergency planning hazards assessment for each facility that has the potential to reach or exceed the lowest level emergency classification

  5. Plutonium Finishing Plant safety evaluation report

    International Nuclear Information System (INIS)

    1995-01-01

    The Plutonium Finishing Plant (PFP) previously known as the Plutonium Process and Storage Facility, or Z-Plant, was built and put into operation in 1949. Since 1949 PFP has been used for various processing missions, including plutonium purification, oxide production, metal production, parts fabrication, plutonium recovery, and the recovery of americium (Am-241). The PFP has also been used for receipt and large scale storage of plutonium scrap and product materials. The PFP Final Safety Analysis Report (FSAR) was prepared by WHC to document the hazards associated with the facility, present safety analyses of potential accident scenarios, and demonstrate the adequacy of safety class structures, systems, and components (SSCs) and operational safety requirements (OSRs) necessary to eliminate, control, or mitigate the identified hazards. Documented in this Safety Evaluation Report (SER) is DOE's independent review and evaluation of the PFP FSAR and the basis for approval of the PFP FSAR. The evaluation is presented in a format that parallels the format of the PFP FSAR. As an aid to the reactor, a list of acronyms has been included at the beginning of this report. The DOE review concluded that the risks associated with conducting plutonium handling, processing, and storage operations within PFP facilities, as described in the PFP FSAR, are acceptable, since the accident safety analyses associated with these activities meet the WHC risk acceptance guidelines and DOE safety goals in SEN-35-91

  6. Plutonium finishing plant safety systems and equipment list

    International Nuclear Information System (INIS)

    Bergquist, G.G.

    1995-01-01

    The Safety Equipment List (SEL) supports Analysis Report (FSAR), WHC-SD-CP-SAR-021 and the Plutonium Finishing Plant Operational Safety Requirements (OSRs), WHC-SD-CP-OSR-010. The SEL is a breakdown and classification of all Safety Class 1, 2, and 3 equipment, components, or system at the Plutonium Finishing Plant complex

  7. Neutron Measurements At Hanford's Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    Conrady, Matthew M.; Berg, Randal K.; Scherpelz, Robert I.; Rathbone, Bruce A.

    2009-01-01

    The Pacific Northwest National Laboratory (PNNL) conducted neutron measurements at Hanford's Plutonium Finishing Plant (PFP). The measurements were performed to evaluate the performance of the Hanford Standard Dosimeter (HSD) and the 8816 TLD component of the Hanford Combination Neutron Dosimeter (HCND) in the neutron fields responsible for worker neutron exposures. For this study, TEPC detectors and multisphere spectrometers were used to measure neutron dose equivalent rate, and multispheres were used to measure average neutron energy. Water-filled phantoms holding Hanford dosimeters were positioned at each measurement location. The phantoms were positioned in the same location where a multisphere measurement was taken and TEPCs were also positioned there. Plant survey meters were also used to measure neutron dose rates at all locations. Three measurement locations were chose near the HC-9B glovebox in room 228A of Building 234-5. The multisphere spectrometers measured average neutron energies in the range of 337 to 555 keV at these locations. Personal dose equivalent, Hp(10)n, as measured by the multisphere and TEPC, ranged from 2.7 to 9.7 mrem/h in the three locations. Effective dose assuming a rotational geometry (EROT) was substantially lower than Hp(10), ranging from 1.3 to 3.6 mrem/h. These values were lower than the reported values from dosimeters exposed on a rotating phantom. Effective dose assuming an AP geometry (EAP) was also substantially lower than Hp(10), ranging from 2.3 to 6.5 mrem/h. These values were lower than the reported values from the dosimeters on slab phantoms. Since the effective dose values were lower than reported values from dosimeters, the dosimeters were shown to be conservative estimates of the protection quantities.

  8. Nuclear Power Plants. Revised.

    Science.gov (United States)

    Lyerly, Ray L.; Mitchell, Walter, III

    This publication is one of a series of information booklets for the general public published by the United States Atomic Energy Commission. Among the topics discussed are: Why Use Nuclear Power?; From Atoms to Electricity; Reactor Types; Typical Plant Design Features; The Cost of Nuclear Power; Plants in the United States; Developments in Foreign…

  9. Plutonium vulnerability issues at Hanford's Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    Feldt, E.; Templeton, D.W.; Tholen, E.

    1995-01-01

    The Plutonium Finishing Plant (PFP) at the Hanford, Washington Site was operated to produce plutonium (Pu) metal and oxide for national defense purposes. Due to the production requirements and methods utilized to meet national needs and the abrupt shutdown of the plant in the late 1980s, the plant was left in a condition that poses a risk of radiation exposure to plant workers, of accidental radioactive material release to the environment, and of radiation exposure to the public. In early 1994, an Environmental Impact Statement (EIS) to determine the best methods for cleaning out and stabilizing Pu materials in the PFP was started. While the EIS is being prepared, a number of immediate actions have been completed or are underway to significantly reduce the greatest hazards in the PFP. Recently, increased attention his been paid to Pu risks at Department of Energy (DOE) facilities resulting in the Department-wide Plutonium Vulnerability Assessment and a recommendation by the Defense Nuclear Facilities Safety Board (DNFSB) for DOE to develop integrated plans for managing its nuclear materials

  10. Plutonium Finishing Plant. Interim plutonium stabilization engineering study

    Energy Technology Data Exchange (ETDEWEB)

    Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J. [Pacific Northwest Lab., Richland, WA (United States); Nass, R. [Nuclear Fuel Services, Inc. (United States)

    1995-08-01

    This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage.

  11. Plutonium Finishing Plant Transition Project mission analysis report

    International Nuclear Information System (INIS)

    Courson, D.B.

    1994-01-01

    This report defines the mission for the Plutonium Finishing Plant Transition Project (PFPTP) using a systems engineering approach. This mission analysis will be the basis for the functional analysis which will further define and break down the mission statement into all of the detailed functions required to accomplish the mission. The functional analysis is then used to develop requirements, allocate those requirements to functions, and eventually be used to design the system. This report: presents the problem which will be addressed, defines PFP Transition Project, defines the overall mission statement, describes the existing, initial conditions, defines the desired, final conditions, identifies the mission boundaries and external interfaces, identifies the resources required to carry out the mission, describes the uncertainties and risks, and discusses the measures which will be used to determine success

  12. Plutonium Finishing Plant. Interim plutonium stabilization engineering study

    International Nuclear Information System (INIS)

    Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J.; Nass, R.

    1995-08-01

    This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage

  13. Fire hazard analysis for Plutonium Finishing Plant complex

    International Nuclear Information System (INIS)

    MCKINNIS, D.L.

    1999-01-01

    A fire hazards analysis (FHA) was performed for the Plutonium Finishing Plant (PFP) Complex at the Department of Energy (DOE) Hanford site. The scope of the FHA focuses on the nuclear facilities/structures in the Complex. The analysis was conducted in accordance with RLID 5480.7, [DOE Directive RLID 5480.7, 1/17/94] and DOE Order 5480.7A, ''Fire Protection'' [DOE Order 5480.7A, 2/17/93] and addresses each of the sixteen principle elements outlined in paragraph 9.a(3) of the Order. The elements are addressed in terms of the fire protection objectives stated in paragraph 4 of DOE 5480.7A. In addition, the FHA also complies with WHC-CM-4-41, Fire Protection Program Manual, Section 3.4 [1994] and WHC-SD-GN-FHA-30001, Rev. 0 [WHC, 1994]. Objectives of the FHA are to determine: (1) the fire hazards that expose the PFP facilities, or that are inherent in the building operations, (2) the adequacy of the fire safety features currently located in the PFP Complex, and (3) the degree of compliance of the facility with specific fire safety provisions in DOE orders, related engineering codes, and standards

  14. Fire hazard analysis for Plutonium Finishing Plant complex

    Energy Technology Data Exchange (ETDEWEB)

    MCKINNIS, D.L.

    1999-02-23

    A fire hazards analysis (FHA) was performed for the Plutonium Finishing Plant (PFP) Complex at the Department of Energy (DOE) Hanford site. The scope of the FHA focuses on the nuclear facilities/structures in the Complex. The analysis was conducted in accordance with RLID 5480.7, [DOE Directive RLID 5480.7, 1/17/94] and DOE Order 5480.7A, ''Fire Protection'' [DOE Order 5480.7A, 2/17/93] and addresses each of the sixteen principle elements outlined in paragraph 9.a(3) of the Order. The elements are addressed in terms of the fire protection objectives stated in paragraph 4 of DOE 5480.7A. In addition, the FHA also complies with WHC-CM-4-41, Fire Protection Program Manual, Section 3.4 [1994] and WHC-SD-GN-FHA-30001, Rev. 0 [WHC, 1994]. Objectives of the FHA are to determine: (1) the fire hazards that expose the PFP facilities, or that are inherent in the building operations, (2) the adequacy of the fire safety features currently located in the PFP Complex, and (3) the degree of compliance of the facility with specific fire safety provisions in DOE orders, related engineering codes, and standards.

  15. Environmental-friendly wool fabric finishing by some water plant extracts

    Directory of Open Access Journals (Sweden)

    Šmelcerović Miodrag

    2007-01-01

    Full Text Available In this article, environmental-friendly finishing of wool fabric were processed with several water extract plants, such as hibiscus, St. John's wort, and marigold. The plant extracts have good basis in the commercial dyeing of wool, for garment and carpet industry. At the same time, the environmental-friendly finishing by water extracts plants shows very good fastness of the antimicrobial properties and coloration of wool fabric. From an ecological viewpoint, the substitution of chemical dyes with "natural products" may represent not only a strategy to reduce risk and pollutants but also an opportunity for new markets and new businesses, which can expend involving of ecology in trade policy.

  16. Estimation and characterization of decontamination and decommissioning solid waste expected from the Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    Millar, J.S.; Pottmeyer, J.A.; Stratton, T.J.

    1995-01-01

    Purpose of the study was to estimate the amounts of equipment and other materials that are candidates for removal and subsequent processing in a solid waste facility when the Hanford Plutonium Finishing Plant is decontaminated and decommissioned. (Building structure and soil are not covered.) Results indicate that ∼5,500 m 3 of solid waste is expected to result from the decontamination and decommissioning of the Pu Finishing Plant. The breakdown of the volumes and percentages of waste by category is 1% dangerous solid waste, 71% low-level waste, 21% transuranic waste, 7% transuranic mixed waste

  17. Revised inspection program for nuclear power plants

    International Nuclear Information System (INIS)

    1978-01-01

    The United States Nuclear Regulatory Commission (NRC) regulates nuclear power plants to assure adequate protection of the public and the environment from the dangers associated with nuclear materials. NRC fulfills this responsibility through comprehensive safety reviews of nuclear facilities, licensing of organizations that use nuclear materials, and continuing inspection. The NRC inspection program is currently conducted from the five regional offices in or near Philadelphia, Atlanta, Chicago, Dallas and San Francisco. Inspectors travel from the regional offices to nuclear power plants in various phases of construction, test and operation in order to conduct inspections. However, in June 1977 the Commission approved a revision to the inspection program that will include stationing inspectors at selected plants under construction and at all plants in operation. In addition, the revised program provides for appraising the performance of licensees on a national basis and involves more direct measurement and observation by NRC inspectors of work and tests in progress. The program also includes enhanced career management consisting of improved training and career development for inspectors and other professionals. The report was requested in the Conference Report on the NRC Authorization for Appropriations for Fiscal Year 1978. The report provides a discussion of the basis for both the current and revised inspection programs, describes these programs, and shows how the NRC inspection force will be trained and utilized. In addition, the report includes a discussion of the actions that will be taken to assure the objectivity of inspectors

  18. A Study on Salt Attack Protection of Structural and Finishing Materials in Power Plant Structures

    Energy Technology Data Exchange (ETDEWEB)

    Kim, W B; Kweon, K J; Suh, Y P; Nah, H S; Lee, K J; Park, D S; Jo, Y K [Korea Electric Power Research Institute, Taejeon (Korea, Republic of)

    1998-12-31

    This is a final report written by both KEPRI and KICT as a co-operative research titled {sup A} study on Salt Protection of Structural and Finishings in Power Plant Structures{sup .} This study presented the methods to prevent the chloride-induced corrosion of power plant structures through collection and analysis of research datum relating to design, construction and maintenance for the prevention of structural and finishing materials, thru material performance tests for anti-corrosion under many kinds of chloride-induced corrosion environments. As a result, this study proposed the guidelines for design, construction and maintenance of power plant structures due to chloride-induced corrosion. (author). 257 refs., 111 figs., 86 tabs.

  19. A Study on Salt Attack Protection of Structural and Finishing Materials in Power Plant Structures

    Energy Technology Data Exchange (ETDEWEB)

    Kim, W.B.; Kweon, K.J.; Suh, Y.P.; Nah, H.S.; Lee, K.J.; Park, D.S.; Jo, Y.K. [Korea Electric Power Research Institute, Taejeon (Korea, Republic of)

    1997-12-31

    This is a final report written by both KEPRI and KICT as a co-operative research titled {sup A} study on Salt Protection of Structural and Finishings in Power Plant Structures{sup .} This study presented the methods to prevent the chloride-induced corrosion of power plant structures through collection and analysis of research datum relating to design, construction and maintenance for the prevention of structural and finishing materials, thru material performance tests for anti-corrosion under many kinds of chloride-induced corrosion environments. As a result, this study proposed the guidelines for design, construction and maintenance of power plant structures due to chloride-induced corrosion. (author). 257 refs., 111 figs., 86 tabs.

  20. Project Plan For Remove Special Nuclear Material (SNM) from Plutonium Finishing Plant (PFP) Project

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove SNM Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617. This project plan is the top-level definitive project management document for the PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baseline to manage the execution of the Remove SNM Materials project. Any deviation to the document must be authorized through the appropriate change control process. The Remove SNM Materials project provides the necessary support and controls required for DOE-HQ, DOE-RL, BWHC, and other DOE Complex Contractors the path forward to negotiate shipped/receiver agreements, schedule shipments, and transfer material out of PFP to enable final deactivation

  1. Project plan remove special nuclear material from PFP project plutonium finishing plant; TOPICAL

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617,Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  2. Project plan remove special nuclear material from PFP project plutonium finishing plant

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  3. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  4. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    International Nuclear Information System (INIS)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment

  5. Plutonium Finishing Plant (PFP) Safety Class and Safety Significant Commercial Grade Items (CGI) Critical Characteristic

    International Nuclear Information System (INIS)

    THOMAS, R.J.

    2000-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for use in the Plutonium Finishing Plant as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics of any one item

  6. Project Management Plan to Maintain Safe and Compliant Conditions at the Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    COX, G.J.

    1999-01-01

    This Project Management Plan presents the overall plan, description, mission, and workscope for the Plutonium Finishing Plant (PFP) maintain safe and compliant conditions project at PFP. This plan presents the overall description, mission, work scope, and planning for the Plutonium Finishing Plant (PFP) Maintain Safe and Compliant Conditions Project at PFP. This project includes all tasks required to maintain the safety boundary for the PFP Complex, except for the 2736-2 Vault Complex and the 234-52 vaults and vault-type rooms. The intent of this plan is to describe how this project will be managed and integrated with the stabilization, and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines that will manage the execution of this project. It describes the organizational approach and roles/responsibilities implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action

  7. Plutonium Finishing Plant (PFP) Waste Composition and High Efficiency Particulate Air Filter Loading

    Energy Technology Data Exchange (ETDEWEB)

    ZIMMERMAN, B.D.

    2000-12-11

    This analysis evaluates the effect of the Plutonium Finishing Plant (PFP) waste isotopic composition on Tank Farms Final Safety Analysis Report (FSAR) accidents involving high-efficiency particulate air (HEPA) filter failure in Double-Contained Receiver Tanks (DCRTs). The HEPA Filter Failure--Exposure to High Temperature or Pressure, and Steam Intrusion From Interfacing Systems accidents are considered. The analysis concludes that dose consequences based on the PFP waste isotopic composition are bounded by previous FSAR analyses. This supports USQD TF-00-0768.

  8. Sludge stabilization at the Plutonium Finishing Plant, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1994-10-01

    This Environmental Assessment evaluates the proposed action to operate two laboratory-size muffle furnaces in glovebox HC-21C, located in the Plutonium Finishing Plant (PFP), Hanford Site, Richland, Washington. The muffle furnaces would be used to stabilize chemically reactive sludges that contain approximately 25 kilograms (55 pounds) of plutonium by heating to approximately 500 to 1000 degrees C (900 to 1800 degrees F). The resulting stable powder, mostly plutonium oxide with impurities, would be stored in the PFP vaults. The presence of chemically reactive plutonium-bearing sludges in the process gloveboxes poses a risk to workers from radiation exposure and limits the availability of storage space for future plant cleanup. Therefore, there is a need to stabilize the material into a form suitable for long-term storage. This proposed action would be an interim action, which would take place prior to completion of an Environmental Impact Statement for the PFP which would evaluate stabilization of all plutonium-bearing materials and cleanout of the facility. However, only 10 percent of the total quantity of plutonium in reactive materials is in the sludges, so this action will not limit the choice of reasonable alternatives or prejudice the Record of Decision of the Plutonium Finishing Plant Environmental Impact Statement

  9. Characterization of past and present solid waste streams from the plutonium finishing plant

    Energy Technology Data Exchange (ETDEWEB)

    Duncan, D.R.; Mayancsik, B.A. [Westinghouse Hanford Co., Richland, WA (United States); Pottmeyer, J.A.; Vejvoda, E.J.; Reddick, J.A.; Sheldon, K.M.; Weyns, M.I. [Los Alamos Technical Associates, Kennewick, WA (United States)

    1993-02-01

    During the next two decades the transuranic (TRU) wastes now stored in the burial trenches and storage facilities at the Hanford Site are to be retrieved, processed at the Waste Receiving and Processing (WRAP) Facility, and shipped to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, New Mexico for final disposal. Over 50% of the TRU waste to be retrieved for shipment to the WIPP has been generated at the Plutonium Finishing Plant (PFP), also known as the Plutonium Processing and Storage Facility and Z Plant. The purpose of this report is to characterize the radioactive solid wastes generated by the PFP since its construction in 1947 using process knowledge, existing records, and history-obtained from interviews. The PFP is currently operated by Westinghouse Hanford Company (WHC) for the US Department of Energy (DOE).

  10. Characterization of past and present solid waste streams from the plutonium finishing plant

    International Nuclear Information System (INIS)

    Duncan, D.R.; Mayancsik, B.A.; Pottmeyer, J.A.; Vejvoda, E.J.; Reddick, J.A.; Sheldon, K.M.; Weyns, M.I.

    1993-02-01

    During the next two decades the transuranic (TRU) wastes now stored in the burial trenches and storage facilities at the Hanford Site are to be retrieved, processed at the Waste Receiving and Processing (WRAP) Facility, and shipped to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, New Mexico for final disposal. Over 50% of the TRU waste to be retrieved for shipment to the WIPP has been generated at the Plutonium Finishing Plant (PFP), also known as the Plutonium Processing and Storage Facility and Z Plant. The purpose of this report is to characterize the radioactive solid wastes generated by the PFP since its construction in 1947 using process knowledge, existing records, and history-obtained from interviews. The PFP is currently operated by Westinghouse Hanford Company (WHC) for the US Department of Energy (DOE)

  11. Current situation of the project finishing of the building of 3 and 4 block of the nuclear power plant Mochovce

    International Nuclear Information System (INIS)

    Niznan, S.

    2005-01-01

    In the contribution there is the basic information mentioned about history of building and the current situation at the finishing of the building of 3 and 4 block of the Nuclear Power Plant Mochovce with the use of project digitization. Further on the contribution shows what kinds of supporting material has been elaborated, what kind of decisions have been issued to the finishing of the building, way of financing and also the assumption of investment return under the defined conditions. An orientation time schedule of the finishing of the building and the crucial steps for its security are presented in the conclusion

  12. Plutonium Finishing Plant Treatment and Storage Unit Dangerous Waste Training Plan

    International Nuclear Information System (INIS)

    ENTROP, G.E.

    2000-01-01

    The training program for personnel performing waste management duties pertaining to the Plutonium Finishing Plant (PFP) Treatment and Storage Unit is governed by the general requirements established in the Plutonium Finishing Plant Dangerous Waste Training Plan (PFP DWTP). The PFP Treatment and Storage Unit DWTP presented below incorporates all of the components of the PFP DWTP by reference. The discussion presented in this document identifies aspects of the training program specific to the PFP Treatment and Storage Unit. The training program includes specifications for personnel instruction through both classroom and on-the-job training. Training is developed specific to waste management duties. Hanford Facility personnel directly involved with the PFP Treatment and Storage Unit will receive training to container management practices, spill response, and emergency response. These will include, for example, training in the cementation process and training pertaining to applicable elements of WAC 173-303-330(1)(d). Applicable elements from WAC 173-303-330(1)(d) for the PFP Treatment and Storage Unit include: procedures for inspecting, repairing, and replacing facility emergency and monitoring equipment; communications and alarm systems; response to fires or explosions; and shutdown of operations

  13. ASSESSING CHEMICAL HAZARDS AT THE PLUTONIUM FINISHING PLANT FOR PLANNING FUTURE DECONTAMINATION AND DECOMMISSIONING

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; KLOS, D.B.; MINETT, M.J.

    2007-01-01

    This paper documents the fiscal year (FY) 2006 assessment to evaluate potential chemical and radiological hazards associated with vessels and piping in the former plutonium process areas at Hanford's Plutonium Finishing Plant (PFP). Evaluations by PFP engineers as design authorities for specific systems and other subject-matter experts were conducted to identify the chemical hazards associated with transitioning the process areas for the long-term layup of PFP before its eventual final decontamination and decommissioning (D and D). D and D activities in the main process facilities were suspended in September 2005 for a period of between 5 and 10 years. A previous assessment conducted in FY 2003 found that certain activities to mitigate chemical hazards could be deferred safely until the D and D of PFP, which had been scheduled to result in a slab-on-grade condition by 2009. As a result of necessary planning changes, however, D and D activities at PFP will be delayed until after the 2009 time frame. Given the extended project and plant life, it was determined that a review of the plant chemical hazards should be conducted. This review to determine the extended life impact of chemicals is called the ''Plutonium Finishing Plant Chemical Hazards Assessment, FY 2006''. This FY 2006 assessment addresses potential chemical and radiological hazard areas identified by facility personnel and subject-matter experts who reevaluated all the chemical systems (items) from the FY 2003 assessment. This paper provides the results of the FY 2006 chemical hazards assessment and describes the methodology used to assign a hazard ranking to the items reviewed

  14. PLUTONIUM FINISHING PLANT (PFP) SUB-GRADE EE/CA EVALUATION OF ALTERNATIVES: A NEW MODEL

    International Nuclear Information System (INIS)

    HOPKINS, A.M.

    2007-01-01

    An engineering evaluation/cost analysis (EE/CA) was performed at the Hanford Site's Plutonium Finishing Plant (PFP). The purpose of the EVCA was to identify the sub-grade items to be evaluated; determine the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) hazardous substances through process history and available data; evaluate these hazards; and as necessary, identify the available alternatives to reduce the risk associated with the contaminants. The sub-grade EWCA considered four alternatives for an interim removal action: (1) No Action; (2) Surveillance and Maintenance (S and M); (3) Stabilize and Leave in Place (Stabilization); and (4) Remove, Treat and Dispose (RTD). Each alternative was evaluated against the CERCLA criteria for effectiveness, implementability, and cost

  15. Total Measurement Uncertainty for the Plutonium Finishing Plant (PFP) Segmented Gamma Scan Assay System

    CERN Document Server

    Fazzari, D M

    2001-01-01

    This report presents the results of an evaluation of the Total Measurement Uncertainty (TMU) for the Canberra manufactured Segmented Gamma Scanner Assay System (SGSAS) as employed at the Hanford Plutonium Finishing Plant (PFP). In this document, TMU embodies the combined uncertainties due to all of the individual random and systematic sources of measurement uncertainty. It includes uncertainties arising from corrections and factors applied to the analysis of transuranic waste to compensate for inhomogeneities and interferences from the waste matrix and radioactive components. These include uncertainty components for any assumptions contained in the calibration of the system or computation of the data. Uncertainties are propagated at 1 sigma. The final total measurement uncertainty value is reported at the 95% confidence level. The SGSAS is a gamma assay system that is used to assay plutonium and uranium waste. The SGSAS system can be used in a stand-alone mode to perform the NDA characterization of a containe...

  16. The chemistry of tributyl phosphate at elevated temperatures in the Plutonium Finishing Plant Process Vessels

    International Nuclear Information System (INIS)

    Barney, G.S.; Cooper, T.D.

    1994-01-01

    Potentially violent chemical reactions of the tributyl phosphate solvent used by the Plutonium Finishing Plant at the Hanford Site were investigated. There is a small probability that a significant quantity of this solvent could be accidental transferred to heated process vessels and react there with nitric acid or plutonium nitrate also present in the solvent extraction process. The results of laboratory studies of the reactions show that exothermic oxidation of tributyl phosphate by either nitric acid or actinide nitrates is slow at temperatures expected in the heated vessels. Less than four percent of the tributyl phosphate will be oxidized in these vented vessels at temperatures between 125 degrees C and 250 degrees C because the oxidant will be lost from the vessels by vaporization or decomposition before the tributyl phosphate can be extensively oxidized. The net amounts of heat generated by oxidation with concentrated nitric acid and with thorium nitrate (a stand-in for plutonium nitrate) were determined to be about -150 and -220 joules per gram of tributyl phosphate initially present, respectively. This is not enough heat to cause violent reactions in the vessels. Pyrolysis of the tributyl phosphate occurred in these mixtures at temperatures of 110 degrees C to 270 degrees C and produced mainly 1-butene gas, water, and pyrophosphoric acid. Butene gas generation is slow at expected process vessel temperatures, but the rate is faster at higher temperatures. At 252 degrees C the rate of butene gas generated was 0.33 g butene/min/g of tributyl phosphate present. The measured heat absorbed by the pyrolysis reaction was 228 J/g of tributyl phosphate initially present (or 14.5 kcal/mole of tributyl phosphate). Release of flammable butene gas into process areas where it could ignite appears to be the most serious safety consideration for the Plutonium Finishing Plant

  17. The chemistry of tributyl phosphate at elevated temperatures in the Plutonium Finishing Plant Process Vessels

    Energy Technology Data Exchange (ETDEWEB)

    Barney, G.S.; Cooper, T.D.

    1994-06-01

    Potentially violent chemical reactions of the tributyl phosphate solvent used by the Plutonium Finishing Plant at the Hanford Site were investigated. There is a small probability that a significant quantity of this solvent could be accidental transferred to heated process vessels and react there with nitric acid or plutonium nitrate also present in the solvent extraction process. The results of laboratory studies of the reactions show that exothermic oxidation of tributyl phosphate by either nitric acid or actinide nitrates is slow at temperatures expected in the heated vessels. Less than four percent of the tributyl phosphate will be oxidized in these vented vessels at temperatures between 125{degrees}C and 250{degrees}C because the oxidant will be lost from the vessels by vaporization or decomposition before the tributyl phosphate can be extensively oxidized. The net amounts of heat generated by oxidation with concentrated nitric acid and with thorium nitrate (a stand-in for plutonium nitrate) were determined to be about -150 and -220 joules per gram of tributyl phosphate initially present, respectively. This is not enough heat to cause violent reactions in the vessels. Pyrolysis of the tributyl phosphate occurred in these mixtures at temperatures of 110{degrees}C to 270{degrees}C and produced mainly 1-butene gas, water, and pyrophosphoric acid. Butene gas generation is slow at expected process vessel temperatures, but the rate is faster at higher temperatures. At 252{degrees}C the rate of butene gas generated was 0.33 g butene/min/g of tributyl phosphate present. The measured heat absorbed by the pyrolysis reaction was 228 J/g of tributyl phosphate initially present (or 14.5 kcal/mole of tributyl phosphate). Release of flammable butene gas into process areas where it could ignite appears to be the most serious safety consideration for the Plutonium Finishing Plant.

  18. History and stabilization of the Plutonium Finishing Plant (PFP) complex, Hanford Site

    Energy Technology Data Exchange (ETDEWEB)

    Gerber, M.S., Fluor Daniel Hanford

    1997-02-18

    The 231-Z Isolation Building or Plutonium Metallurgy Building is located in the Hanford Site`s 200 West Area, approximately 300 yards north of the Plutonium Finishing Plant (PFP) (234-5 Building). When the Hanford Engineer Works (HEW) built it in 1944 to contain the final step for processing plutonium, it was called the Isolation Building. At that time, HEW used a bismuth phosphate radiochemical separations process to make `AT solution,` which was then dried and shipped to Los Alamos, New Mexico. (AT solution is a code name used during World War II for the final HEW product.) The process was carried out first in T Plant and the 224-T Bulk Reduction Building and B Plant and the 224-B Bulk Reduction Building. The 224-T and -B processes produced a concentrated plutonium nitrate stream, which then was sent in 8-gallon batches to the 231-Z Building for final purification. In the 231-Z Building, the plutonium nitrate solution underwent peroxide `strikes` (additions of hydrogen peroxide to further separate the plutonium from its carrier solutions), to form the AT solution. The AT solution was dried and shipped to the Los Alamos Site, where it was made into metallic plutonium and then into weapons hemispheres.` The 231-Z Building began `hot` operations (operations using radioactive materials) with regular runs of plutonium nitrate on January 16, 1945.

  19. Treatment of Wastewater from Electroplating, Metal Finishing and Printed Circuit Board Manufacturing. Operation of Wastewater Treatment Plants Volume 4.

    Science.gov (United States)

    California State Univ., Sacramento. Dept. of Civil Engineering.

    One of four manuals dealing with the operation of wastewater plants, this document was designed to address the treatment of wastewater from electroplating, metal finishing, and printed circuit board manufacturing. It emphasizes how to operate and maintain facilities which neutralize acidic and basic waters; treat waters containing metals; destroy…

  20. Definition and means of maintaining the emergency notification and evacuation system portion of the plutonium finishing plant safety envelope

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    The Emergency Evacuation and Notification System provides information to the Plutonium Finishing Plant (PFP) Building Emergency Director to assist in determining appropriate emergency response, notifies personnel of the required response, and assists in their response. The report identifies the equipment in the Safety Envelope (SE) for this System and the Administrative, Maintenance, and Surveillance Procedures used to maintain the SE Equipment

  1. Definition and means of maintaining the emergency notification and evacuation system portion of the plutonium finishing plant safety envelope; TOPICAL

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    The Emergency Evacuation and Notification System provides information to the Plutonium Finishing Plant (PFP) Building Emergency Director to assist in determining appropriate emergency response, notifies personnel of the required response, and assists in their response. The report identifies the equipment in the Safety Envelope (SE) for this System and the Administrative, Maintenance, and Surveillance Procedures used to maintain the SE Equipment

  2. Plutonium Finishing Plant (PFP) Treatment and Storage Unit Waste Analysis Plan

    International Nuclear Information System (INIS)

    PRIGNANO, A.L.

    2000-01-01

    The purpose of this waste analysis plan (WAP) is to document waste analysis activities associated with the Plutonium Finishing Plant Treatment and Storage Unit (PFP Treatment and Storage Unit) to comply with Washington Administrative Code (WAC) 173-303-300(1), (2), (4)(a) and (5). The PFP Treatment and Storage Unit is an interim status container management unit for plutonium bearing mixed waste radiologically managed as transuranic (TRU) waste. TRU mixed (TRUM) waste managed at the PFP Treatment and Storage Unit is destined for the Waste Isolation Pilot Plant (WIPP) and therefore is not subject to land disposal restrictions [WAC 173-303-140 and 40 CFR 268]. The PFP Treatment and Storage Unit is located in the 200 West Area of the Hanford Facility, Richland Washington (Figure 1). Because dangerous waste does not include source, special nuclear, and by-product material components of mixed waste, radionuclides are not within the scope of this documentation. The information on radionuclides is provided only for general knowledge

  3. Medicinal plants and finished marketed herbal products used in the treatment of malaria in the Ashanti region, Ghana.

    Science.gov (United States)

    Komlaga, Gustav; Agyare, Christian; Dickson, Rita Akosua; Mensah, Merlin Lincoln Kwao; Annan, Kofi; Loiseau, Philippe M; Champy, Pierre

    2015-08-22

    Ethnobotanical survey was performed to document medicinal plants employed in the management of malaria in the Bosomtwe and Sekyere East Districts of the Ashanti Region (Ghana), in comparison with the plant ingredients in herbal antimalarial remedies registered by the Ghana Food and Drug Administration. Two hundred and three (203) herbalists from 33 communities within the two districts were interviewed on medicinal plants they use to manage malaria. A literature search was made to determine already documented plants. In addition, 23 finished marketed herbal products indicated for the management of malaria were identified and their labels examined to find out which of the plants mentioned in our survey were listed as ingredients and whether these products are in anyway regulated. Ninety-eight (98) species of plants were cited for the management of malaria. In comparison with literature citations, 12 (12.2%) species were reported for the management of malaria for the first time and 20 (20.4%) others for the first time in Ghana. Twenty-three (23) finished marketed herbal antimalarial products examined contained aerial or underground parts of 29 of the plants cited in our survey as ingredients. Twenty-two (22) of these products have been registered by the Ghana Food and Drugs Authority, four (4) of which were included in the recommended herbal medicine list for treating malaria in Ghana. This study provides new additions to the inventory of medicinal plants used for the management of malaria and reports the commercial availability and regulation of finished marketed labelled herbal products intended for the treatment of malaria in Ghana. Copyright © 2015 Elsevier Ireland Ltd. All rights reserved.

  4. Plutonium Finishing Plant (PFP) Final Safety Analysis Report (FSAR) [SEC 1 THRU 11

    Energy Technology Data Exchange (ETDEWEB)

    ULLAH, M K

    2001-02-26

    The Plutonium Finishing Plant (PFP) is located on the US Department of Energy (DOE) Hanford Site in south central Washington State. The DOE Richland Operations (DOE-RL) Project Hanford Management Contract (PHMC) is with Fluor Hanford Inc. (FH). Westinghouse Safety Management Systems (WSMS) provides management support to the PFP facility. Since 1991, the mission of the PFP has changed from plutonium material processing to preparation for decontamination and decommissioning (D and D). The PFP is in transition between its previous mission and the proposed D and D mission. The objective of the transition is to place the facility into a stable state for long-term storage of plutonium materials before final disposition of the facility. Accordingly, this update of the Final Safety Analysis Report (FSAR) reflects the current status of the buildings, equipment, and operations during this transition. The primary product of the PFP was plutonium metal in the form of 2.2-kg, cylindrical ingots called buttoms. Plutonium nitrate was one of several chemical compounds containing plutonium that were produced as an intermediate processing product. Plutonium recovery was performed at the Plutonium Reclamation Facility (PRF) and plutonium conversion (from a nitrate form to a metal form) was performed at the Remote Mechanical C (RMC) Line as the primary processes. Plutonium oxide was also produced at the Remote Mechanical A (RMA) Line. Plutonium processed at the PFP contained both weapons-grade and fuels-grade plutonium materials. The capability existed to process both weapons-grade and fuels-grade material through the PRF and only weapons-grade material through the RMC Line although fuels-grade material was processed through the line before 1984. Amounts of these materials exist in storage throughout the facility in various residual forms left from previous years of operations.

  5. DEACTIVATION AND DECOMMISSIONING ENVIRONMENTAL STRATEGY FOR THE PLUTONIUM FINISHING PLANT COMPLEX, HANFORD NUCLEAR RESERVATION

    International Nuclear Information System (INIS)

    Hopkins, A.M.; Heineman, R.; Norton, S.; Miller, M.; Oates, L.

    2003-01-01

    Maintaining compliance with environmental regulatory requirements is a significant priority in successful completion of the Plutonium Finishing Plant (PFP) Nuclear Material Stabilization (NMS) Project. To ensure regulatory compliance throughout the deactivation and decommissioning of the PFP complex, an environmental regulatory strategy was developed. The overall goal of this strategy is to comply with all applicable environmental laws and regulations and/or compliance agreements during PFP stabilization, deactivation, and eventual dismantlement. Significant environmental drivers for the PFP Nuclear Material Stabilization Project include the Tri-Party Agreement; the Resource Conservation and Recovery Act of 1976 (RCRA); the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA); the National Environmental Policy Act of 1969 (NEPA); the National Historic Preservation Act (NHPA); the Clean Air Act (CAA), and the Clean Water Act (CWA). Recent TPA negotiation s with Ecology and EPA have resulted in milestones that support the use of CERCLA as the primary statutory framework for decommissioning PFP. Milestones have been negotiated to support the preparation of Engineering Evaluations/Cost Analyses for decommissioning major PFP buildings. Specifically, CERCLA EE/CA(s) are anticipated for the following scopes of work: Settling Tank 241-Z-361, the 232-Z Incinerator, , the process facilities (eg, 234-5Z, 242, 236) and the process facility support buildings. These CERCLA EE/CA(s) are for the purpose of analyzing the appropriateness of the slab-on-grade endpoint Additionally, agreement was reached on performing an evaluation of actions necessary to address below-grade structures or other structures remaining after completion of the decommissioning of PFP. Remaining CERCLA actions will be integrated with other Central Plateau activities at the Hanford site

  6. Calculation note - Consequences of a fire in the sorting and repackaging glovebox in room 636 of bldg 2736-ZB - Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    JOHNSON, L.E.

    1999-01-01

    This Calculation Note provides a conservative estimate of the grams of plutonium released from Building 2736-ZB of the Plutonium Finishing Plant as a result of a fire within Glovebox 636, without consideration of mitigation

  7. The Integrated Safety Management System Verification Enhancement Review of the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    BRIGGS, C.R.

    2000-01-01

    The primary purpose of the verification enhancement review was for the DOE Richland Operations Office (RL) to verify contractor readiness for the independent DOE Integrated Safety Management System Verification (ISMSV) on the Plutonium Finishing Plant (PFP). Secondary objectives included: (1) to reinforce the engagement of management and to gauge management commitment and accountability; (2) to evaluate the ''value added'' benefit of direct public involvement; (3) to evaluate the ''value added'' benefit of direct worker involvement; (4) to evaluate the ''value added'' benefit of the panel-to-panel review approach; and, (5) to evaluate the utility of the review's methodology/adaptability to periodic assessments of ISM status. The review was conducted on December 6-8, 1999, and involved the conduct of two-hour interviews with five separate panels of individuals with various management and operations responsibilities related to PFP. A semi-structured interview process was employed by a team of five ''reviewers'' who directed open-ended questions to the panels which focused on: (1) evidence of management commitment, accountability, and involvement; and, (2) consideration and demonstration of stakeholder (including worker) information and involvement opportunities. The purpose of a panel-to-panel dialogue approach was to better spotlight: (1) areas of mutual reinforcement and alignment that could serve as good examples of the management commitment and accountability aspects of ISMS implementation, and, (2) areas of potential discrepancy that could provide opportunities for improvement. In summary, the Review Team found major strengths to include: (1) the use of multi-disciplinary project work teams to plan and do work; (2) the availability and broad usage of multiple tools to help with planning and integrating work; (3) senior management presence and accessibility; (4) the institutionalization of worker involvement; (5) encouragement of self-reporting and self

  8. Plan for the Startup of HA-21I Furnace Operations at the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    WILLIS, H.T.

    2000-01-01

    Achievement of Thermal Stabilization mission elements require the installation and startup of three additional muffle furnaces for the thermal stabilization of plutonium and plutonium bearing materials at the Plutonium Finishing Plant (PFP). The release to operate these additional furnaces will require an Activity Based Startup Review. The conduct of the Activity Based Startup Review (ABSR) was approved by Fluor Daniel Hanford on October 15, 1999. This plan has been developed with the objective of identifying those activities needed to guide the controlled startup of five furnaces from authorization to unrestricted operations by adding the HA-211 furnaces in an orderly and safe manner after the approval to Startup has been given. The Startup Plan provides a phased approach that bridges the activities between the completion of the Activity Based Startup Review authorizing the use of the three additional furnaces and the unrestricted operation of the five thermal stabilization muffle furnaces. The four phases are: (1) the initiation of five furnace operations using three empty (simulated full) boat charges from HA-211 and two full charges from HC-21C; (2) three furnace operations (one full charge from HA-211 and two full charges from HC-21C); (3) four furnace operations (two full charges from HA-211 and two full charges from HC-21C); and (4) integrated five furnace operations and unrestricted operations. Phase 1 of the Plan will be considered as the cold runs. This Plan also provides management oversight and administrative controls that are to be implemented until unrestricted operations are authorized. It also provides a formal review process for ensuring that all preparations needed for full five furnace operations are completed and formally reviewed prior to proceeding to the increased activity levels associated with five furnace operations. Specific objectives include: (1) To ensure that activities are conducted in a safe manner. (2) To provide supplemental

  9. Preliminary safety analysis report for project 89-GEB-610 Plutonium Finishing Plant instrumentation upgrade. Revision 1

    International Nuclear Information System (INIS)

    Huber, T.E.

    1995-01-01

    This document consists of an analysis of the MICON system upgrade. This project shall install a Micon Co. distributed process monitor and control system with Sparc Sun workstation operator interfaces. The Sparc workstations are housed in consoles custom designed to human factors specifications. The distributed control system (DCS) shall have the installed capacity to monitor and control all related instruments and equipment presently connected to the panels in the PFP Power Control Room 321A as listed in the input/output list. This also includes all devices monitored and controlled by the 2736-ZB Allen Bradley programmable logic controller. The system has since assumed the control and monitoring responsibilities for Projects B- 680H ''Low Level Waste Treatment Facility'' and C-031H ''PFP Liquid Effluent Facilities''. Part of the new en's change area in Building 234-5ZA, Room 712, has been remodeled to house two consoles and one supervisor console. Local control units containing the microprocontrollers and the input/output interface circuit boards shall be wired to the instrumentation and controlled equipment. These units communicate with the Sparc workstations via a redundant data communications highway and shall be strategic, throughout the PFP facility. The DCS has already been purchased from Micon Co., located in Houston Texas, presently on site

  10. Standard technical specifications: Babcock and Wilcox Plants. Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for Babcock ampersand Wilcox Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4--3.9 of the improved STS

  11. Pilot-industrial plant for radiation-chemical finishing of textiles

    International Nuclear Information System (INIS)

    Burov, V.K.; Vanyushkin, B.M.; Voskoboev, A.E.

    1976-01-01

    A pilot technological radiational-chemical line for liquid-phase radiational-chemical finish of fabrics is described, which is being mounted at the Glukhov cotton group of enterprises now. It is designed primarily for the anti-microbe finish of cotton fabrics by grafting copper polyacrylate. The technological scheme is built on the principle of direct (combined) irradiation of the fabric impregnated by a monomer solution. Graft of the monomer to the fabric is performed by the radiational method. As source of radiation, an electron accelerator with the beam power of 0.4-0.7 Mev and with a biological protection has been employed. Depending on the thickness of the material irradiated and irradiation conditions, the fabric drive mechanism permits to change a number of irradiated fabric layers from 1 to 9 and by this to utilize in the most complete manner the energy of the accelerated electron beam. The nominal width of the irradiated material is 1000 m, the transportation velocity can vary in the range from 10 through 100 m/min. The radiational-chemical method of fabric finish is economical, highly productive and easily controllable

  12. MODIFICATION OF RECIPES USED IN THE BLEACHING SECTION OF THE FINISHING PLANT OF THE TEXTILE UNIT "DESEMBARCO DEL GRANMA”

    Directory of Open Access Journals (Sweden)

    Isabel Cabrera Estada

    2017-07-01

    Full Text Available The Textile Basic Unit (BU “Desembarco del Granma” of Villa Clara is one of the most important textile industries in Cuba, it is responsible for the provision of a wide variety of fabrics, threads and surgical gauze to various sectors of the country. In the finishing plant of the BU "Desembarco del Granma" a production that meets the parameters set is achieved, but this requires the use of large volumes of costly chemicals and with negative impacts on the environment. To solve this problem an investigation was carried out to evaluate the modification of some of the recipes used in the bleaching section of the finishing plant of the BU "Desembarco del Granma". The results obtained were processed with the Statgraphics software. When the caustic soda is decreased from 60g/L to 40g/L, and it is analyzed the capillarity of warp, it was confirmed that there is no significant difference between the average of the two samples, for a 95,0 % of confidence level; but there were differences between the variances; when analyzing the fabric capillarity it was found that there is no significant difference between the average and the variance of the two samples for a 95,0 % of confidence level. With such modification it is saved 241,4 $/day, by concept of decrease of soda used. The hydrogen peroxide cannot be reduced because it affects the white degree of the fabric.

  13. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    Energy Technology Data Exchange (ETDEWEB)

    JOHNSTON GA

    2008-01-15

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D&D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D&D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D&D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and

  14. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    International Nuclear Information System (INIS)

    JOHNSTON GA

    2008-01-01

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D and D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D and D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D and D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and Liability Act of 1980

  15. 78 FR 17708 - Endangered and Threatened Wildlife and Plants; Draft Revised Supplement to the Grizzly Bear...

    Science.gov (United States)

    2013-03-22

    ...] Endangered and Threatened Wildlife and Plants; Draft Revised Supplement to the Grizzly Bear Recovery Plan... Revised Supplement to the Grizzly Bear Recovery Plan. Specifically, this supplement proposes to revise the demographic recovery criteria for the Yellowstone Ecosystem. In the lower 48 States, Grizzly bears (Ursus...

  16. Salmonella enterica prevalence in finishing pigs at slaughter plants in Northern Italy

    Directory of Open Access Journals (Sweden)

    Irene Alpigiani

    2014-04-01

    Full Text Available Finishing pigs carrying Salmonella enterica are believed to be the main source of carcass contamination at the beginning of slaughtering. The aim of this study was to assess the S. enterica carrier status of finishing pigs at herd level by sampling pooled faeces on farm and mesenteric lymph nodes at slaughter in the North East of Italy. Environmental faecal samples belonging to 30 batches of pigs were collected on farm. At slaughter, mesenteric lymph nodes were collected from five randomly selected pigs per batch. S. enterica was isolated from 16 lymph nodes out of 150 (10.6% and from seven out of 30 (23.3% faecal samples. Four batches (13.3% were positive to S. enterica both in lymph nodes and in faeces. The number of batches positive to S. enterica either in lymph nodes or in faeces was 13 out of 30 (43.3%. The most prevalent serovars from lymph nodes were S. Derby (25.0% and S. Typhimurium monophasic variant 1, 4,[5],12:i:- (18.6%, which were also isolated from faecal material (14.3 and 42.8% respectively. Contaminated faecal material or lymph nodes could be a primary source of carcass contamination at slaughter during evisceration. S. enterica contamination is widespread on pig farms and carrier pigs pass undetected the inspection visits at slaughter, entering the food chain. Therefore, in order to control S. enterica in pigs, the need to quantify possible risk factors at slaughter and develop effective management strategies on farm is of paramount importance to ensure food safety.

  17. AN APPROACH TO CHARACTERIZING and EVALUATING ALTERNATIVES FOR THE DECOMMISSIONING OF SUB-GRADE STRUCTURES AT THE PLUTONIUM FINISHING PLANT

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; KLOS, D.B.

    2007-01-01

    In 2002, the Richland Operations Office (RL) of the US Department of Energy (DOE), the US Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) developed milestones for transitioning the Plutonium Finishing Plant (PFP) facility to a clean slab-on-grade configuration. These milestones required developing an engineering evaluation/cost analysis (EF/CA) for the facility's sub-grade structures and installations as part of a series of evaluations intended to provide for the transition of the facility to a clean slab-on-grade configuration. In addition to supporting decisions for interim actions, the analyses of sub-grade structures and installations performed through this EE/CA will contribute to the remedial investigation feasibility study(ies) and subsequently to the final records of decision for the relevant operable units responsible for site closure in the 200 West Area of the Hanford Site

  18. Storage for the Fast Flux Test Facility unirradiated fuel in the Plutonium Finishing Plant Complex, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-01-01

    This Environmental Assessment evaluates the proposed action to relocate and store unirradiated Fast Flux Test Facility fuel in the Plutonium Finishing Plant Complex on the Hanford Site, Richland, Washington. The US Department of Energy has decided to cease fuel fabrication activities in the 308 Building in the 300 Area. This decision was based on a safety concern over the ability of the fuel fabrication portion of the 308 Building to withstand a seismic event. The proposed action to relocate and store the fuel is based on the savings that could be realized by consolidating security costs associated with storage of the fuel. While the 308 Building belowgrade fuel storage areas are not at jeopardy by a seismic event, the US Department of Energy is proposing to cease storage operations along with the related fabrication operations. The US Department of Energy proposes to remove the unirradiated fuel pins and fuel assemblies from the 308 Building and store them in Room 192A, within the 234-5Z Building, a part of the Plutonium Finishing Plant Complex, located in the 200 West Area. Minor modifications to Room 192A would be required to accommodate placement of the fuel. The US Department of Energy estimates that removing all of the fuel from the 308 Building would save $6.5 million annually in security expenditures for the Fast Flux Test Facility. Environmental impacts of construction, relocation, and operation of the proposed action and alternatives were evaluated. This evaluation concluded that the proposed action would have no significant impacts on the human environment

  19. Revised concept for the Waste Isolation Pilot Plant

    International Nuclear Information System (INIS)

    Dennis, A.W.; Milloy, J.A.; Scully, L.W.; Shefelbine, H.C.; Stinebaugh, R.E.; Wowak, W.E.

    1978-07-01

    The quantities of remotely handled wastes that must be handled at the Waste Isolation Pilot Plant have been reduced from 250 x 10 3 ft 3 /y to 10 x 10 3 ft 3 /y; the capital cost of the facility will be reduced from 534 to 428 million dollars. Changes in the facility design due to the reduction in the amount of remote-handled waste are discussed. If DOE should exercise its option to construct a high-level waste repository concurrently with the construction of the revised design, with both facilities receiving waste in 1985, the combined cost would be about 580 million dollars. However, it is unlikely that significant quantities of high-level waste in a form suitable for geologic disposal would be available until after 1990. (13 figures, 5 tables)

  20. Application of preliminary risk analysis at marble finishing plants in Recife's metropolitan area.

    Science.gov (United States)

    de Melo Neto, Rútilo P; Kohlman Rabbani, Emilia R

    2012-01-01

    The finishing of marble occurs in quarries all over Brazil, being the most significant dimension of the ornamental stone sector, with 7,000 businesses. Recife's Metropolitan Area (RMR) contains approximately 106 marble quarries, 25 of them unionized. The study focused on the application of Preliminary Risk Analysis, conducted at two unionized quarries: M1, a small business; and the second, M2, considered a micro enterprise. In this analysis both the administrative and the productive sectors were evaluated. The fieldwork was done in the month of December 2010. The study revealed that the two quarries carried moderate risks in the administrative sector, mainly due to ergonomic factors, and that in the productive sectors the risks were high, specifically because of excess noise, dust material, and precarious electrical installations. Using the results of the qualitative analysis as a base, the need for quantitative study presents itself in order to determine the most adequate modes of protection to be of assistance in the management of these risks, guaranteeing the safety and health of the worker and consequently the improvement in productivity in this sector.

  1. Revised

    DEFF Research Database (Denmark)

    Johannsen, Vivian Kvist; Nord-Larsen, Thomas; Riis-Nielsen, Torben

    This report is a revised analysis of the Danish data on CO2 emissions from forest, afforestation and deforestation for the period 1990 - 2008 and a prognosis for the period until 2020. Revision have included measurements from 2009 in the estimations. The report is funded by the Ministry of Climate...

  2. Improving Efficiency with 3-D Imaging: Technology Essential in Removing Plutonium Processing Equipment from Plutonium Finishing Plant Gloveboxes

    International Nuclear Information System (INIS)

    Crow, Stephen H.; Kyle, Richard N.; Minette, Michael J.

    2008-01-01

    The Plutonium Finishing Plant at Hanford, Washington began operations in 1949 to process plutonium and plutonium products. Its primary mission was to produce plutonium metal, fabricate weapons parts, and stabilize reactive materials. These operations, and subsequent activities, were performed in remote production lines, consisting primarily of hundreds of gloveboxes. Over the years these gloveboxes and processes have been continuously modified. The plant is currently inactive and Fluor Hanford has been tasked to clean out contaminated equipment and gloveboxes from the facility so it can be demolished in the near future. Approximately 100 gloveboxes at PFP have been cleaned out in the past four years and about 90 gloveboxes remain to be cleaned out. Because specific commitment dates for this work have been established with the State of Washington and other entities, it is important to adopt work practices that increase the safety and speed of this effort. The most recent work practice to be adopted by Fluor Hanford D and D workers is the use of 3-D models to improve the efficiency of cleaning out radioactive gloveboxes at the plant. The use of 3-D models has significantly improved the work planning process by providing workers with a clear image of glovebox construction and composition, which is then used to determine cleanout methods and work sequences. The 3-D visual products enhance safety by enabling workers to more easily identify hazards and implement controls. In addition, the ability to identify and target the removal of radiological materials early in the D and D process provides substantial dose reduction for the workers

  3. 78 FR 29774 - Endangered and Threatened Wildlife and Plants; Draft Revised Supplement to the Grizzly Bear...

    Science.gov (United States)

    2013-05-21

    ...] Endangered and Threatened Wildlife and Plants; Draft Revised Supplement to the Grizzly Bear Recovery Plan... extending the public comment period for a Draft Revised Supplement to the Grizzly Bear Recovery Plan in the... to the Grizzly Bear Recovery Plan is available at http://www.fws.gov/mountain-prairie/species/mammals...

  4. 77 FR 76065 - Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for Kendall Warm...

    Science.gov (United States)

    2012-12-26

    ...] Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for Kendall Warm Springs Dace... revised recovery plan for the Kendall Warm Springs dace (Rhinichthys osculus thermalis). This species is... recovery plan. The Kendall Warm Springs dace (Rhinichthys osculus thermalis), found only in one location in...

  5. 78 FR 9409 - Endangered and Threatened Wildlife and Plants; Draft Revised Indiana Bat Summer Survey Guidelines

    Science.gov (United States)

    2013-02-08

    ...-FF03E00000] Endangered and Threatened Wildlife and Plants; Draft Revised Indiana Bat Summer Survey Guidelines... documents related to the draft revised summer survey guidelines for the Indiana bat (Myotis sodalis) for an... U.S. mail address; Email: indiana_bat@fws.gov ; or Fax: 812-334-4273. Include ``Indiana Bat Summer...

  6. Full Focus Needed on Finishing Hanford's Waste Treatment Plant - 12196

    Energy Technology Data Exchange (ETDEWEB)

    Dahl, Suzanne; Biyani, Rabindra; Holmes, Erika [Washington State Department of Ecology, Richland, WA 99354 (United States)

    2012-07-01

    The United States Department of Energy's (US DOE's) Hanford Nuclear Site has 177 underground waste storage tanks located 19 to 24 km (12 to 15 miles) from the Columbia River in south-central Washington State. Hanford's tanks now hold about 212,000 cu m (56 million gallons) of highly radioactive and chemically hazardous waste. Sixty-seven tanks have leaked an estimated 3,785 cu m (1 million gallons) of this waste into the surrounding soil. Further releases to soil, groundwater, and the Columbia River are the inevitable result of the tanks continuing to age. The risk from this waste is recognized as a threat to the Northwest by both State and Federal governments. US DOE and Bechtel National, Inc., are building the Waste Treatment and Immobilization Plant (WTP) to treat and vitrify (immobilize in glass) the waste from Hanford's tanks. As is usual for any groundbreaking project, problems have arisen that must be resolved as they occur if treatment is to take place as specified in the court-enforceable Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) and the Consent Decree, entered into by US DOE, the U.S. Environmental Protection Agency, and the Washington State Department of Ecology (Ecology). At times, US DOE's approach to solving these critical issues seems to have caused undue wastes of time, energy, and, ultimately, public funds. Upon reviewing the history of Hanford's tank waste treatment project, Ecology hopes that constructive criticism of past failures and praise of successes will inspire US DOE to consider changing practices, be more transparent with regulatory agencies and the public, and take a 'lean production' approach to successfully completing this project. All three Tri-Party Agreement agencies share the goal of completing WTP on time, ensuring it is operational and in compliance with safety standards. To do this, Ecology believes US DOE should: - Maintain focus on the primary goal of

  7. Radioactive Air Emissions Notice of Construction for the Magnesium Hydroxide Precipitation Process at the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    JANSKY, M.T.

    1999-01-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions and Defense Waste (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A.'' Appendix A (WAC 246-247-1 10) lists the requirements that must be addressed. Additionally, the following description, attachments and references are provided to the US Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40, Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem per year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI), and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also will constitute EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2) will be provided at a later date. This NOC covers the activities associated with the Construction and operation activities involving the magnesium hydroxide precipitation process of plutonium solutions within the Plutonium Finishing Plant (PFP)

  8. 76 FR 9079 - Revision of Distilled Spirits Plant Regulations

    Science.gov (United States)

    2011-02-16

    ... materials. This term does not apply to wine and beer, which generally are products of fermentation alone... category, TTB should create category-specific regulations, similar to the regulations for vinegar plants and alcohol fuel plants. TTB Response: TTB notes that vinegar plants and alcohol fuel plants differ...

  9. 75 FR 37358 - Endangered and Threatened Wildlife and Plants; Revised Critical Habitat for the Arroyo Toad

    Science.gov (United States)

    2010-06-29

    ...-0069] [92210-0-0009-B4] RIN 1018-AV89 Endangered and Threatened Wildlife and Plants; Revised Critical...; (2) revegetation of riparian areas; (3) removal of invasive plants such as arundo (Arundo donax) and tamarisk (Tamarix sp.); (4) protecting wetlands from urban runoff by establishing a revegetated upland...

  10. Assessment of the Plutonium Finishing Plant Criticality Alarm System U.S. Department of Energy Richland Operations Office

    International Nuclear Information System (INIS)

    NIRIDER, L.T.

    2002-01-01

    At the request of the Assistant Manager for Safety and Engineering, the U.S. Department of Energy Richland Operations Office (RL) Engineering Support Division, performed an oversight review of the Plutonium Finishing Plant (PFP) nuclear Criticality Alarm System (CAS). The review was conducted to satisfy requirements and agreements associated with Defense Nuclear Facility Safety Board (DNFSB) Recommendation 2000-2, ''Vital Safety Systems.'' The PFP is managed by Fluor Hanford, Inc. for RL. The field assessment and staff interviews were conducted August 12 through August 19,2002. This was a limited scope assessment that consisted of a review of the nuclear CAS operations, maintenance, and compliance with National Consensus Standards Requirements. The main purpose of the assessment was to determine the adequacy of the existing alarm system and its associated infrastructure to support the PFP facility mission through the remaining facility lifetime. The Review Plan was modeled upon Criteria and Review Approach Documents (CRAD) developed for DNFSB Recommendation 2000-2 reviews conducted across the Hanford Site. Concerns regarding component degradation and failure, increasing numbers of occurrence reports associated with the alarm system, and reliability issues were addressed. Additionally, RL performed a review of the engineering aspects of the CAS including the functions of design authorities and aspects of systems engineering. However, the focus of the assessment was on operations, maintenance, and reliability of the CAS, associated procurement practices, adequacy of safety and engineering policies and procedures, safety documentation, and fundamental engineering practices including training, qualification, and systems engineering. This assessment revealed that the PFP CAS and its associated infrastructure, administrative procedures, and conduct of operations are generally effective. There are no imminent criticality safety issues associated with the operation of the

  11. 78 FR 71676 - NUREG-1482, Revision 2, “Guidelines for Inservice Testing at Nuclear Power Plants, Final Report”

    Science.gov (United States)

    2013-11-29

    ... Testing at Nuclear Power Plants, Final Report'' AGENCY: Nuclear Regulatory Commission. ACTION: Notice of... entitled: NUREG-1482, Revision 2, ``Guidelines for Inservice Testing at Nuclear Power Plants,'' and... Restraints (Snubbers) at Nuclear Power Plants.'' In the previous Revisions 0 and 1 of NUREG-1482, the NRC...

  12. Sensitivity Studies on Revised PSA Model of KHNP Nuclear Power Plants

    International Nuclear Information System (INIS)

    Lee, Hyun-Gyo; Hwang, Seok-Won; Shin, Tae-Young

    2016-01-01

    Korea also performed safety revaluation for all nuclear power plants led by Korean regulatory and elicited 49 improvement factor for plants. One of those factors is Severe Accident Management Guidelines (SAMG) development, KHNP decided to develop Low Power and Shutdown(LPSD) Probabilistic Safety Assessment (PSA) models and upgrade full power PSA models of all operating plants for enhancement of guideline quality. In this paper we discuss about the effectiveness of post Fukushima equipment and improvements of each plant based on the results of revised full power PSA and newly developed LPSD PSA. Through sensitivity analysis based on revised PSA models we confirmed that the facilities installed or planned to installation as follow-up measures of Fukushima accident helped to enhance the safety of nuclear power plants. These results will provide various technical insights to scheduled studies which evaluate effectiveness of Fukushima post action items and develop accident management guideline. Also it will contribute to improve nuclear power plants safety

  13. Sensitivity Studies on Revised PSA Model of KHNP Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Hyun-Gyo; Hwang, Seok-Won; Shin, Tae-Young [KHNP, Daejeon (Korea, Republic of)

    2016-10-15

    Korea also performed safety revaluation for all nuclear power plants led by Korean regulatory and elicited 49 improvement factor for plants. One of those factors is Severe Accident Management Guidelines (SAMG) development, KHNP decided to develop Low Power and Shutdown(LPSD) Probabilistic Safety Assessment (PSA) models and upgrade full power PSA models of all operating plants for enhancement of guideline quality. In this paper we discuss about the effectiveness of post Fukushima equipment and improvements of each plant based on the results of revised full power PSA and newly developed LPSD PSA. Through sensitivity analysis based on revised PSA models we confirmed that the facilities installed or planned to installation as follow-up measures of Fukushima accident helped to enhance the safety of nuclear power plants. These results will provide various technical insights to scheduled studies which evaluate effectiveness of Fukushima post action items and develop accident management guideline. Also it will contribute to improve nuclear power plants safety.

  14. THE DEACTIVATION, DECONTAMINATION AND DECOMMISSIONING OF THE PLUTONIUM FINISHING PLANT, A FORMER PLUTONIUM PROCESSING FACILITY AT DOE'S HANFORD SITE

    International Nuclear Information System (INIS)

    CHARBONEAU, S.L.

    2006-01-01

    The Plutonium Finishing Plant (PFP) was constructed as part of the Manhattan Project during World War II. The Manhattan Project was developed to usher in the use of nuclear weapons to end the war. The primary mission of the PFP was to provide plutonium used as special nuclear material (SNM) for fabrication of nuclear devices for the war effort. Subsequent to the end of World War II, the PFP's mission expanded to support the Cold War effort through plutonium production during the nuclear arms race and later the processing of fuel grade mixed plutonium-uranium oxide to support DOE's breeder reactor program. In October 1990, at the close of the production mission for PFP, a shutdown order was prepared by the Department of Energy (DOE) in Washington,; DC--and issued to the Richland DOE field office. Subsequent to the shutdown order, a team from the Defense Nuclear Facilities Safety Board (DNFSB) analyzed the hazards at PFP associated with the continued storage of certain forms of plutonium solutions and solids. The assessment identified many discrete actions that were required to stabilize the different plutonium forms into stable form and repackage the material in high integrity containers. These actions were technically complicated and completed as part of the PFP nuclear material stabilization project between 1995 and early 2005. The completion of the stabilization project was a necessary first step in deactivating PFP. During stabilization, DOE entered into negotiations with the U.S. Environmental Protection Agency (EPA) and the State of Washington and established milestones for the Deactivation and Decommissioning (DandD) of the PFP. The DOE and its contractor, Fluor Hanford (Fluor), have made great progress in deactivating, decontaminating and decommissioning the PFP at the Hanford Site as detailed in this paper. Background information covering the PFP DandD effort includes descriptions of negotiations with the State of Washington concerning consent

  15. Flow-accelerated corrosion in power plants. Revision 1

    International Nuclear Information System (INIS)

    Chexal, B.; Horowitz, J.; Dooley, B.

    1998-07-01

    Flow-Accelerated Corrosion (FAC) is a phenomenon that results in metal loss from piping, vessels, and equipment made of carbon steel. FAC occurs only under certain conditions of flow, chemistry, geometry, and material. Unfortunately, those conditions are common in much of the high-energy piping in nuclear and fossil-fueled power plants. Undetected, FAC will cause leaks and ruptures. Consequently, FAC has become a major issue, particularly for nuclear plants. Although major failures are rare, the consequences can be severe. In 1986, four men in the area of an FAC-induced pipe rupture were killed. Fossil plants too, are subject to FAC. In 1995, a failure at a fossil-fired plant caused two fatalities. In addition to concerns about personnel safety, FAC failures can pose challenges to plant safety. Regulatory agencies have therefore required nuclear utilities to institute formal programs to address FAC. Finally, a major FAC failure (like the one that happened in 1997 at a US nuclear power plant) can force a plant to shutdown and purchase replacement power at a price approaching a million dollars per day depending upon the MWe rating of the plant. A great deal of time and money has been spent to develop the technology to predict, detect, and mitigate FAC in order to prevent catastrophic failures. Over time, substantial progress has been made towards understanding and preventing FAC. The results of these efforts include dozens of papers, reports, calculations, and manuals, as well as computer programs and other tools. This book is written to provide a detailed treatment of the entire subject in a single document. Any complex issue requires balancing know-how, the risk of decision making, and a pragmatic engineering solution. This book addresses these by carrying out the necessary R and D and engineering along with plant knowledge to cover all quadrants of Chexal's four quadrant known-unknown diagram, as seen in Figure i

  16. Selective application of revised source terms to operating nuclear power plants

    International Nuclear Information System (INIS)

    Moon, Joo Hyun; Song, Jae Hyuk; Lee, Young Wook; Ko, Hyun Seok; Kang, Chang Sun

    2001-01-01

    More than 30 years later since 1962 when TID-14844 was promulgated, there has been big change of the US NRC's regulatory position in using accident source terms for radiological assessment following a design basis accident (DBA). To replace the instantaneous source terms of TID-14844, the time-dependent source terms of NUREG-1465 was published in 1995. In the meantime, the radiological acceptance criteria for reactor site evaluation in 10 CFR Part 100 were also revised. In particular, the concept of total effective dose equivalent has been incorporated in accordance with the radiation protection standards set forth in revised 10 CFR Part 20. Subsequently, the publication of Regulatory Guide 1.183 and the revision of Standard Review Plan 15.0.1 followed in 2000, which provided the licensee of operating nuclear power reactor with the acceptable guidance of applying the revised source term. The guidance allowed the holder of an operating license issued prior to January 10, 1997 to voluntarily revise the accident source terms used in the radiological consequence analyses of DBA. Regarding to its type of application, there suggested full and selective applications, Whether it is full or selective, based upon the scope and nature of associated plant modifications being proposed, the actual application of the revised source terms to an operating plant is expected to give a large impact on its facility design basis. Considering scope and cost of the analyses required for licensing, selective application is seemed to be more appealing to an licensee of the operating plant rather than full application. In this paper, hence, the selective application methodology is reviewed and is actally applied to the assessment of offsite radiological consequence following a LOCA at Ulchin Unit 3 and 4, in order to identify and analyze the potential impacts due to application of revised source terms and to assess the considerations taken in each application prior to its actual

  17. 76 FR 64372 - Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan, First Revision, for...

    Science.gov (United States)

    2011-10-18

    ... INFORMATION: Background Recovery of endangered or threatened animals and plants to the point where they are... through the present day, such that both species remain in danger of extinction. Habitat loss, resulting in... mortality resulting from entrainment in water management structures were cited as causes for declines in...

  18. 75 FR 56131 - Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for the Northern...

    Science.gov (United States)

    2010-09-15

    ... on the MOCA network recommended in the 2008 Recovery Plan and will instead use the model results to... DEPARTMENT OF THE INTERIOR Fish and Wildlife Service [FWS-R1-ES-2010-N184; 10120-1113-0000-C2] Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for the Northern Spotted Owl...

  19. 78 FR 63100 - Endangered and Threatened Wildlife and Plants; Revised Critical Habitat for the Comal Springs...

    Science.gov (United States)

    2013-10-23

    ...-0082; 4500030114] RIN 1018-AY20 Endangered and Threatened Wildlife and Plants; Revised Critical Habitat... Comal and Hays Counties, Texas. DATES: This rule is effective on November 22, 2013. ADDRESSES: This... hearing. We held a public hearing on May 17, 2013, in San Marcos, Texas. We also contacted appropriate...

  20. Monitoring well plugging and abandonment plan, Y-12 Plant, Oak Ridge, Tennessee (revised)

    International Nuclear Information System (INIS)

    1997-05-01

    Plugging and abandonment (P ampersand A) of defunct groundwater monitoring wells is a primary element of the Oak Ridge Y-12 Plant Groundwater Protection Program (GWPP) (AJA Technical Services, Inc. 1996). This document is the revised groundwater monitoring well P ampersand A plan for the U.S. Department of Energy (DOE) Y-12 Plant located in Oak Ridge, Tennessee. This plan describes the systematic approach employed by Y-12 Plant GWPP to identify wells that require P ampersand A, the technical methods employed to perform P ampersand A activities, and administrative requirements. Original documentation for Y-12 Plant GWPP groundwater monitoring well P ampersand A was provided in HSW, Inc. (1991). The original revision of the plan specified that a comprehensive monitoring well P ampersand A was provided in HSW, Inc. (1991). The original revision of the plan specified that a comprehensive monitoring well P ampersand A schedule be maintained. Wells are added to this list by issuance of both a P ampersand A request and a P ampersand A addendum to the schedule. The current Updated Subsurface Data Base includes a single mechanism to track the status of monitoring wells. In addition, rapid growth of the groundwater monitoring network and new regulatory requirements have resulted in constant changes to the status of wells. As a result, a streamlined mechanism to identify and track monitoring wells scheduled for P ampersand A has been developed and the plan revised to formalize the new business practices

  1. Maintenance implementation plan for T Plant. Revision 2

    International Nuclear Information System (INIS)

    Ayers, W.S.

    1995-05-01

    This document is a Maintenance Implementation Plan (MIP) for the T Plant Facility complex located in the 200 West Area of the Hanford Reservation in Washington state. This plan has been developed to provide a disciplined approach to maintenance functions and to describe how the T Plant facility will implement and comply with the regulations according to US DOE order 4330.4B, entitled Maintenance Management Program, Chapter 2.0 open-quotes Nuclear Facilitiesclose quotes. Physical structures, systems, processes, as well as all associated equipment specifically assigned to these groups are included in the MIP

  2. Development of the methodology for application of revised source term to operating nuclear power plants in Korea

    International Nuclear Information System (INIS)

    Kang, M.S.; Kang, P.; Kang, C.S.; Moon, J.H.

    2004-01-01

    Considering the current trend in applying the revised source term proposed by NUREG-1465 to the nuclear power plants in the U.S., it is expected that the revised source term will be applied to the Korean operating nuclear power plants in the near future, even though the exact time can not be estimated. To meet the future technical demands, it is necessary to prepare the technical system including the related regulatory requirements in advance. In this research, therefore, it is intended to develop the methodology to apply the revised source term to operating nuclear power plants in Korea. Several principles were established to develop the application methodologies. First, it is not necessary to modify the existing regulations about source term (i.e., any back-fitting to operating nuclear plants is not necessary). Second, if the pertinent margin of safety is guaranteed, the revised source term suggested by NUREG-1465 may be useful to full application. Finally, a part of revised source term could be selected to application based on the technical feasibility. As the results of this research, several methodologies to apply the revised source term to the Korean operating nuclear power plants have been developed, which include: 1) the selective (or limited) application to use only some of all the characteristics of the revised source term, such as release timing of fission products and chemical form of radio-iodine and 2) the full application to use all the characteristics of the revised source term. The developed methodologies are actually applied to Ulchin 9 and 4 units and their application feasibilities are reviewed. The results of this research are used as either a manual in establishing the plan and the procedure for applying the revised source term to the domestic nuclear plant from the utility's viewpoint; or a technical basis of revising the related regulations from the regulatory body's viewpoint. The application of revised source term to operating nuclear

  3. B Plant Complex waste management training plan. Revision 1

    International Nuclear Information System (INIS)

    Beam, T.G.

    1994-01-01

    This training program is designed to comply with all applicable federal, state and US Department of Energy-Richland Operations Office training requirements. The training program complies with requirements contained within WAC 173-303-330 for the development of a written dangerous waste training program. The training program is designed to prepare personnel to manage and maintain waste treatment, storage and disposal (TSD) units, as well as generator units, in a safe, effective, efficient and environmentally sound manner. In addition to preparing employees to manage and maintain TSD and generator units under normal conditions, the training program ensures that employees are prepared to respond in a prompt and effective manner should an emergency occur. The training plan also identifies specific individuals holding key waste management positions at B Plant Complex

  4. B Plant Complex pollution prevention plan. Revision 1

    International Nuclear Information System (INIS)

    Beam, T.G.

    1994-01-01

    The US Department of Energy (DOE) has directed Westinghouse Hanford Company (WHC) to develop an effective strategy to minimize the generation of hazardous, radioactive, and mixed wastes at Hanford in compliance with state and federal regulations. WHC has formalized a pollution prevention program composed of management policies, management requirements and procedures. This plan addresses pollution prevention for B Plant Complex. A pollution prevention team is in place and has been assigned responsibility for implementing the plan. This plan includes actions and goals for reducing volume and toxicity of waste generated, as well as a basis for evaluation of progress. Descriptions of waste streams, current specific goals, general pollution prevention methods, and specific accomplishments are in the appendices of this plan

  5. Monitoring well inspection and maintenance plan Y-12 Plant, Oak Ridge, Tennessee (revised)

    International Nuclear Information System (INIS)

    1996-09-01

    Inspection and maintenance of groundwater monitoring wells is a primary element of the Oak Ridge Y-12 Plant Groundwater Protection Program (GWPP). This document is the revised groundwater monitoring well inspection and maintenance plan for the U.S. Department of Energy (DOE) Y-12 Plant in Oak Ridge, Tennessee. The plan provides a systematic program for: (1) inspecting the physical condition of monitoring wells at the Y-12 Plant and (2) identifying maintenance needs that will extend the life of each well and ensure that representative groundwater quality samples and hydrologic data are collected from the wells. Original documentation for the Y-12 Plant GWPP monitoring well inspection and maintenance program was provided in HSW, Inc. 1991a. The original revision of the plan specified that only a Monitoring Well Inspection/Maintenance Summary need be updated and reissued each year. Rapid growth of the monitoring well network and changing regulatory requirements have resulted in constant changes to the status of wells (active or inactive) listed on the Monitoring Well Inspection/Maintenance Summary. As a result, a new mechanism to track the status of monitoring wells has been developed and the plan revised to formalize the new business practices. These changes are detailed in Sections 2.4 and 2.5

  6. Standard technical specifications, Westinghouse Plants: Bases (Sections 3.4--3.9). Volume 3, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This NUREG contains the improved Standard Technical Specifications (STS) for Westinghouse plants. Revision 1 incorporates the cumulative changes to Revision 0, which was published in September 1992. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, specifically the Westinghouse Owners Group (WOG), NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993 (58 FR 39132). Licensees are encouraged to upgrade their technical specifications consistent with those criteria and conforming, to the extent practical and consistent with the licensing basis for the facility, to Revision 1 to the improved STS. The Commission continues to place the highest priority on requests for complete conversions to the improved STS. Licensees adopting portions of the improved STS to existing technical specifications should adopt all related requirements, as applicable, to achieve a high degree of standardization and consistency

  7. Standard technical specifications, Westinghouse Plants: Bases (Sections 2.0--3.3). Volume 2, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This NUREG contains the improved Standard Technical Specifications (STS) for Westinghouse plants. Revision 1 incorporates the cumulative changes to Revision 0, which was published in September 1992. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, specifically the Westinghouse Owners Group (WOG), NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993 (58 FR 39132). Licensees are encouraged to upgrade their technical specifications consistent with those criteria and conforming, to the extent practical and consistent with the licensing basis for the facility, to Revision 1 to the improved STS. The Commission continues to place the highest priority on requests for complete conversions to the improved STS. Licensees adopting portions of the improved STS to existing technical specifications should adopt all related requirements, as applicable, to achieve a high degree of standardization and consistency

  8. CONTAMINATED PROCESS EQUIPMENT REMOVAL FOR THE DECOMMISSIONG AND DECONTAMINATION OF THE 232-Z CONTAMINATED WASTE RECOVERY PROCESS FACILITY AT THE PLUTONIUM FINISHING PLANT

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; MINETTE, M.J.; KLOS, D.B.

    2007-01-01

    This paper describes the unique challenges encountered and subsequent resolutions to accomplish the deactivation and decontamination of a plutonium ash contaminated building. The 232-Z Contaminated Waste Recovery Process Facility at the Plutonium Finishing Plant was used to recover plutonium from process wastes such as rags, gloves, containers and other items by incinerating the items and dissolving the resulting ash. The incineration process resulted in a light-weight plutonium ash residue that was highly mobile in air. This light-weight ash coated the incinerator's process equipment, which included gloveboxes, blowers, filters, furnaces, ducts, and filter boxes. Significant airborne contamination (over 1 million derived air concentration hours [DAC]) was found in the scrubber cell of the facility. Over 1300 grams of plutonium held up in the process equipment and attached to the walls had to be removed, packaged and disposed. This ash had to be removed before demolition of the building could take place

  9. Revision of AESJ standard 'the code of implemnetation of periodic safety review of nuclear power plants'

    International Nuclear Information System (INIS)

    Hirano, Masashi; Narumiya, Yoshiyuki

    2010-01-01

    The Periodic Safety Review (PSR) was launched in June 1992, when the Agency for Natural Resources and Energy issued a notification that required licensees to conduct comprehensive review on the safety of each existing nuclear power plant (NPP) once approximately every ten years based on the latest technical findings for the purpose of improving the safety of the NPP. In 2006, the Standard Committee of the Atomic Energy Society of Japan established the first version of 'The Standard of Implementation for Periodic Safety Review of Nuclear Power Plants: 2006'. Taking into account developments in safety regulation of PSR after the issuance of the first version, the Standard Committee has revised the Standard. This paper summarizes background on PSR, such developments are major contents of the Standard as well as the focal points of the revision. (author)

  10. Knowledge and abilities catalog for nuclear power plant operators: Boiling water reactors, Revision 1

    International Nuclear Information System (INIS)

    1995-08-01

    The Knowledge and Abilities Catalog for Nuclear Power Plant Operators: Boiling-Water Reactors (BWRs) (NUREG-1123, Revision 1) provides the basis for the development of content-valid licensing examinations for reactor operators (ROs) and senior reactor operators (SROs). The examinations developed using the BWR Catalog along with the Operator Licensing Examiner Standards (NUREG-1021) and the Examiner's Handbook for Developing Operator Licensing Written Examinations (NUREG/BR-0122), will cover the topics listed under Title 10, Code of Federal Regulations, Part 55 (10 CFR 55). The BWR Catalog contains approximately 7,000 knowledge and ability (K/A) statements for ROs and SROs at BWRs. The catalog is organized into six major sections: Organization of the Catalog, Generic Knowledge and Ability Statements, Plant Systems grouped by Safety Functions, Emergency and Abnormal Plant Evolutions, Components, and Theory. Revision 1 to the BWR Catalog represents a modification in form and content of the original catalog. The K/As were linked to their applicable 10 CFR 55 item numbers. SRO level K/As were identified by 10 CFR 55.43 item numbers. The plant-wide generic and system generic K/As were combined in one section with approximately one hundred new K/As. Component Cooling Water and Instrument Air Systems were added to the Systems Section. Finally, High Containment Hydrogen Concentration and Plant Fire On Site evolutions added to the Emergency and Abnormal Plant Evolutions section

  11. Supplementation with plant extracts (carvacrol, cinnamaldehyde and capsaicin): its effects on acid-base status and productive performance in growing/finishing bull calves.

    Science.gov (United States)

    Hernández, Joaquín; Benedito, José Luís; Vázquez, Patricia; Pereira, Victor; Méndez, Jesús; Sotillo, Juan; Castillo, Cristina

    2009-01-01

    This study investigated the in vivo effects of a commercial blend of plant extracts (carvacrol, cinnamaldehyde and capsaicin) on blood acid-base balance and serum lactate levels in a 148-day feedlot experimentwith 24 double-muscled Belgian Blue bull calves. Animals were allotted randomly to one of two experimental groups: 1) a control group (C, no supplementation; n = 10), and 2) a group receiving dietary supplementation with a combination of plant extracts (PE, 100 mg per kg DM of concentrate; n = 14). All animals received a high-grain ration, typical of diets fed commercially to feedlot cattle in Spain, consisting mainly of barley plus other components in proportions depending on the production phase. Production data (weight, DMI, ADG and feed-to-gain ratio) were recorded, and venous blood pH, pCO2, HCO3(-), Base Excess -BE- and serum L-lactate were determined. Apparently, beneficial effects of supplementation on production parameters were observed in both growing and finishing periods, though statistically significant effects were only observed in the finishing period. As regards blood parameters, no significant effects of supplementation (or the supplementation x time interaction) were observed, except for an effect on blood pH in the growing period, when supplemented animals showed significantly higher values than controls. A beneficial supplementation x time interactive effect was observed on serum L-lactate levels: from the first week of the study until the end, supplemented animals showed significantly lower levels than controls. These in vivo results support the utility of this dietary supplement in feedlot cattle receiving a barley-based high-grain diet.

  12. 77 FR 46157 - Endangered and Threatened Wildlife and Plants; Revising the Special Rule for the Utah Prairie Dog

    Science.gov (United States)

    2012-08-02

    ... Utah Prairie Dog; Final Rule #0;#0;Federal Register / Vol. 77 , No. 149 / Thursday, August 2, 2012...-AW02 Endangered and Threatened Wildlife and Plants; Revising the Special Rule for the Utah Prairie Dog... special regulations for the conservation of the Utah prairie dog. We are revising our special regulations...

  13. Review of revised Japanese seismic guidelines for Nuclear Power Plant design

    International Nuclear Information System (INIS)

    Kato, M.

    1987-01-01

    Development of aseismic design for nuclear power plants in Japan has evolved roughly in three stages. The first phase, which continued by 1978, was a period progressive development when design for each siteplant has referred to designs of predecessor plants and have added the latest knowledge and experience in that time. The second phase from issuance of 'Regulatory Guide for Aseismic Design of Nuclear Power Reactor Facilities' (1978, revised in 1981), or 1978 to 1986, was a period when the application of customary conservative design method was continued, while standardization of the aseismic design technology have been proceded. It is in this phase when new knowledge was accumulated by aseismic proof studies. The third phase represents a transient period to rational design when the conservative aseismic design technology has been reviewed due to the new knowledge and revision of the above JEAG guideline has progressed for incorporation in design, and ont the other hand by-laws of the Ministry of International Trade and Industry are being provided. In this report a review is given of aseismic design and its guideline after the second phase onward and an overview of the revised JEAG - Recent Aseismic Design Method - and the by-laws including rationalization of aseismic design technology

  14. Standard technical specifications General Electric plants, BWR/6. Volume 1, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for General Electric BWR/6 Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4--3.10 of the improved STS

  15. Standard technical specifications: General Electric plants, BWR/4. Volume 1, Revision 1: Specifications

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for General Electric BWR/4 Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4--3.10 of the improved STS

  16. Standard technical specifications: Combustion engineering plants. Volume 1, Revision 1: Specifications

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for Combustion Engineering Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4--3.9 of the improved STS

  17. Water bath and air bath calorimeter qualification for measuring 3013 containers of plutonium oxide at the Hanford Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    WELSH, T.L.

    2003-01-01

    The purpose of this paper is to present qualification data generated from water and air-bath calorimeters measuring radioactive decay heat from plutonium oxide in DOE STD-3013-2000 (3013) containers at the Hanford Plutonium Finishing Plant (PFP). Published data concerning air and water bath calorimeters and especially 3013-qualified calorimeters is minimal at best. This paper will address the data from the measurement/qualification test plan, the heat standards used, and the calorimeter precision and accuracy results. The 3013 package is physically larger than earlier plutonium oxide storage containers, thereby necessitating a larger measurement chamber. To accommodate the measurements of the 3013 containers at PFP, Los Alamos National Laboratory (LANL) supplied a water bath dual-chambered unit and the Savannah River Technology Center (SRTC) provided two air-bath calorimeters. Both types of Calorimeters were installed in the analytical laboratory at PFP. The larger 3013 containers presented a new set of potential measurement problems: longer counting times, heat conductivity through a much larger container mass and wall thickness, and larger amounts of copper shot to assist sample thermal conductivity. These potential problems were addressed and included in the measurement/qualification test plan

  18. Finishing of wood

    Science.gov (United States)

    R. Sam Williams

    1999-01-01

    The primary function of any wood finish (paint, varnish, and stain, for example) is to protect the wood surface, help maintain a certain appearance, and provide a cleanable surface. Although wood can be used both outdoors and indoors without finishing, unfinished wood surfaces exposed to the weather change color, are roughened by photodegradation and surface checking,...

  19. New technical knowledge to be implemented to the revision of rules on pipe wall thinning management for PWR plants

    International Nuclear Information System (INIS)

    Hirai, Junya; Nakamura, Takao; Amano, Yoichi

    2013-01-01

    Rules for PWR plant pipe wall thinning management were formulated by the Japan Society of Mechanical Engineers in 2006. Since then thinning management of Japanese PWR plants has been carried out based on this rule. Pipe wall thinning phenomena to be dealt with in this rule have been identified in many piping components of power plants. New technical knowledge has been accumulated since the issuance of 2006 edition. We have formulated these knowledge and information about the thinning phenomena in PWR power plants. Given the history of application of this rule, we have to make our best effort to carry out a study of latest technical knowledge and implement them to the revision of rule and improve pipe wall thinning management. This paper summarizes the new technical knowledge and basis to be implemented to the revision of rules on pipe wall thinning management for PWR plants in Japan. (author)

  20. Revising scenario map for plant management via interaction of stakeholders' intentions and constraints

    International Nuclear Information System (INIS)

    Ohsawa, Yukio; Taya, Sayuri

    2013-01-01

    The purpose of this study is to put knowledge of plant safety together and make a map that will help to understand a system of plant and notice new links among components. This map, called the scenario map, can be used for aiding the chance discoveries - decision of various stakeholders of the system based on their awareness of latent dynamics underlying observed events. The trustworthiness of their analysis will be also reinforced by linking relevant data to the nodes and lines in the graph. In order to have stakeholders be aware of information missed in available data, we invented a method of workshop and moved forward with a rough map of plant safety. The first phase attempts to externalize differences in the bodies of knowledge of each participant. In the second, introducing Tsugo Roulette (TR) – the core component of this paper -, latent dynamics where physical and social causalities emerge is externalized. Then participants revise the scenario map based on their thoughts by the second phase, to finally evaluate the utility of nodes and lines in the graph. In accordance with each phase, participants in the workshop could exchange their tsugoes - views of intentions and constraints - and realize new links or nodes to be evaluated highly by experts in the corresponding domain. (author)

  1. Standard technical specifications combustion engineering plants: Bases (Sections 2.0--3.3). Volume 2, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for General Electric BWR/6 Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes

  2. Standard Review Plan for the review of safety analysis reports for nuclear power plants, Revision No. 7 to Section 9

    International Nuclear Information System (INIS)

    1978-03-01

    Revision No. 1 to Section 9 of the Standard Review Plan incorporates changes that have been developed since the original issuance in September 1975, many of which are editorial in nature, to reflect current staff practice in the review of safety analysis reports for nuclear power plants

  3. 77 FR 24975 - Endangered and Threatened Wildlife and Plants; Revised Recovery Plan for the Utah Prairie Dog

    Science.gov (United States)

    2012-04-26

    ...-FF06E00000] Endangered and Threatened Wildlife and Plants; Revised Recovery Plan for the Utah Prairie Dog... Utah prairie dog (Cynomys parvidens). This species is federally listed as threatened under the... recovery plan for the Utah prairie dog. The Service and other Federal agencies also will take these...

  4. 75 FR 57055 - Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for Utah Prairie Dog

    Science.gov (United States)

    2010-09-17

    ...] Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for Utah Prairie Dog AGENCY: Fish... recovery plan for the Utah prairie dog (Cynomys parvidens). This species is federally listed as threatened... and peer reviewers in an appendix to the approved recovery plan. The Utah prairie dog (Cynomys...

  5. Revision of by-laws about effluents of EdF's nuclear power plants

    International Nuclear Information System (INIS)

    2002-01-01

    In France, in application of the clean water law from January 3, 1992 and since the decree 95-540 from May 4, 1995, each basic nuclear facility receives a single permission which covers both its water takes and its radioactive and non-radioactive effluents. This decree, initially dedicated to new facilities has been enlarged to all existing installations for which the prefectorial by-laws have reached their date-line. Thus, up to now, five inter-ministerial by-laws have renewed the permissions of water takes and effluents evacuation of the power plants of Saint-Laurent-des-Eaux (Loir-et-Cher), Flamanville (Manche), Paluel (Seine-Maritime), Belleville (Cher) and Saint-Alban (Isere). These by-laws foresee an important abatement of the effluents and concern more particularly the tritium, 14 C, the iodine isotopes and also some other non-radioactive chemical compounds. This document is a compilation of all revised by-laws about effluents and concerning the nuclear power plants listed above. (J.S.)

  6. The Creative Application of Science, Technology and Work Force Innovations to the Decontamination and Decommissioning of the Plutonium Finishing Plant at the Hanford Nuclear Reservation

    International Nuclear Information System (INIS)

    Charboneau, S.; Klos, B.; Heineman, R.; Skeels, B.; Hopkins, A.

    2006-01-01

    The Plutonium Finishing Plant (PFP) consists of a number of process and support buildings for handling plutonium. Building construction began in the late 1940's to meet national priorities and became operational in 1950 producing refined plutonium salts and metal for the United States nuclear weapons program The primary mission of the PFP was to provide plutonium used as special nuclear material for fabrication into a nuclear device for the war effort. Subsequent to the end of World War II, the PFP's mission expanded to support the Cold War effort through plutonium production during the nuclear arms race. PFP has now completed its mission and is fully engaged in deactivation, decontamination and decommissioning (D and D). At this time the PFP buildings are planned to be reduced to ground level (slab-on-grade) and the site remediated to satisfy national, Department of Energy (DOE) and Washington state requirements. The D and D of a highly contaminated plutonium processing facility presents a plethora of challenges. PFP personnel approached the D and D mission with a can-do attitude. They went into D and D knowing they were facing a lot of challenges and unknowns. There were concerns about the configuration control associated with drawings of these old process facilities. There were unknowns regarding the location of electrical lines and the condition and contents of process piping containing chemical residues such as strong acids and caustics. The gloveboxes were highly contaminated with plutonium and chemical residues. Most of the glovebox windows were opaque with splashed process chemicals that coated the windows or etched them, reducing visibility to near zero. Visibility into the glovebox was a serious worker concern. Additionally, all the gloves in the gloveboxes were degraded and unusable. Replacing gloves in gloveboxes was necessary to even begin glovebox clean-out. The sheer volume of breathing air needed was also an issue. These and other challenges and PFP

  7. Unit 1 and Unit 2 Nuclear Power Plant Mochovce construction finishing from primary contractor of technological part. Skoda Praha a. s. point of view

    International Nuclear Information System (INIS)

    Horky, F.

    2000-01-01

    In this paper the history of delivery of technological part for NPP V-1 Mochovce as well as of reconstruction and safety improvements by the Skoda Praha a.s. is presented. Primary contractor of technological part Skoda Praha together with its final suppliers proved ability to realize under hard conditions such a complicated work what was indisputedly Units 1 and 2 finishing. Company proved capability to conform itself flexibly in the course of work to requirements of customer for realization of safety measures which means that Units 1 and 2 fully satisfy international standards. By fulfilment of primary contractor of technology obligations and above all by takeover of complex responsibility for both Units putting in operation including responsibility for 'past' Skoda Praha put away one of basic problems which occurred in decision making to whom will be assigned construction finishing contract. These facts fully qualify Skoda Praha to be selected for possible Units 3 and 4 construction finishing as one of chief construction finishing participant

  8. Nuclear fuel reprocessing deactivation plan for the Idaho Chemical Processing Plant, Revision 1

    International Nuclear Information System (INIS)

    Patterson, M.W.

    1994-10-01

    The decision was announced on April 28, 1992 to cease all United States Department of Energy (DOE) reprocessing of nuclear fuels. This decision leads to the deactivation of all fuels dissolution, solvent extraction, krypton gas recovery operations, and product denitration at the Idaho Chemical Processing Plant (ICPP). The reprocessing facilities will be converted to a safe and stable shutdown condition awaiting future alternate uses or decontamination and decommissioning (D ampersand D). This ICPP Deactivation Plan includes the scope of work, schedule, costs, and associated staffing levels necessary to achieve a safe and orderly deactivation of reprocessing activities and the Waste Calcining Facility (WCF). Deactivation activities primarily involve shutdown of operating systems and buildings, fissile and hazardous material removal, and related activities. A minimum required level of continued surveillance and maintenance is planned for each facility/process system to ensure necessary environmental, health, and safety margins are maintained and to support ongoing operations for ICPP facilities that are not being deactivated. Management of the ICPP was transferred from Westinghouse Idaho Nuclear Company, Inc. (WINCO) to Lockheed Idaho Technologies Company (LITCO) on October 1, 1994 as part of the INEL consolidated contract. This revision of the deactivation plan (formerly the Nuclear Fuel Reprocessing Phaseout Plan for the ICPP) is being published during the consolidation of the INEL site-wide contract and the information presented here is current as of October 31, 1994. LITCO has adopted the existing plans for the deactivation of ICPP reprocessing facilities and the plans developed under WINCO are still being actively pursued, although the change in management may result in changes which have not yet been identified. Accordingly, the contents of this plan are subject to revision

  9. Standard technical specifications - Babcock and Wilcox Plants: Bases (Sections 2.0-3.3). Volume 2, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This NUREG contains the improved Standard Technical Specifications (STS) for Babcock and Wilcox (B ampersand W) plants. Revision 1 incorporates the cumulative changes to Revision 0, which was published in September 1992. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, specifically the B ampersand W Owners Group (BWOG), NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993 (58 FR 39132). Licensees are encouraged to upgrade their technical specifications consistent with those criteria and conforming, to the extent practical and consistent with the licensing basis for the facility, to Revision 1 to the improved STS. The Commission continues to place the highest priority on requests for complete conversions to the improved STS. Licensees adopting portions of the improved STS to existing technical specifications should adopt all related requirements, as applicable, to achieve a high degree of standardization and consistency

  10. Chemical and Radiochemical Composition of Thermally Stabilized Plutonium Oxide from the Plutonium Finishing Plant Considered as Alternate Feedstock for the Mixed Oxide Fuel Fabrication Facility

    International Nuclear Information System (INIS)

    Tingey, Joel M.; Jones, Susan A.

    2005-01-01

    Eighteen plutonium oxide samples originating from the Plutonium Finishing Plant (PFP) on the Hanford Site were analyzed to provide additional data on the suitability of PFP thermally stabilized plutonium oxides and Rocky Flats oxides as alternate feedstock to the Mixed Oxide Fuel Fabrication Facility (MFFF). Radiochemical and chemical analyses were performed on fusions, acid leaches, and water leaches of these 18 samples. The results from these destructive analyses were compared with nondestructive analyses (NDA) performed at PFP and the acceptance criteria for the alternate feedstock. The plutonium oxide materials considered as alternate feedstock at Hanford originated from several different sources including Rocky Flats oxide, scrap from the Remote Mechanical C-Line (RMC) and the Plutonium Reclamation Facility (PRF), and materials from other plutonium conversion processes at Hanford. These materials were received at PFP as metals, oxides, and solutions. All of the material considered as alternate feedstock was converted to PuO2 and thermally stabilized by heating the PuO2 powder at 950 C in an oxidizing environment. The two samples from solutions were converted to PuO2 by precipitation with Mg(OH)2. The 18 plutonium oxide samples were grouped into four categories based on their origin. The Rocky Flats oxide was divided into two categories, low- and high-chloride Rocky Flats oxides. The other two categories were PRF/RMC scrap oxides, which included scrap from both process lines and oxides produced from solutions. The two solution samples came from samples that were being tested at Pacific Northwest National Laboratory because all of the plutonium oxide from solutions at PFP had already been processed and placed in 3013 containers. These samples originated at the PFP and are from plutonium nitrate product and double-pass filtrate solutions after they had been thermally stabilized. The other 16 samples originated from thermal stabilization batches before canning at

  11. Wall Finishes; Carpentry: 901895.

    Science.gov (United States)

    Dade County Public Schools, Miami, FL.

    The course outline is designed to provide instruction in selecting, preparing, and installing wall finishing materials. Prerequisites for the course include mastery of building construction plans, foundations and walls, and basic mathematics. Intended for use in grades 11 and 12, the course contains five blocks of study totaling 135 hours of…

  12. Technical specifications: Callaway Plant, Unit No. 1 (Docket No. STN 50-483). Appendix A to License No. NPF-30. Revision 1

    International Nuclear Information System (INIS)

    1984-10-01

    Revised specifications are presented concerning limiting safety system settings for control systems, power distribution, instrumentation, coolant system, emergency core cooling system, containment systems, plant systems, electrical systems, refueling operations, radioactive effluents, and radiation environmental monitoring

  13. Finishing with invisalign.

    Science.gov (United States)

    Duong, Trang; Kuo, Eric

    2006-01-01

    Finishing in orthodontics can be challenging and can involve use of various techniques and armamentarium. This article reports a study that evaluates a procedure for using a thicker Aligner at the end of treatment to aide in finishing and also to determine if this would reduce the need for additional "case refinement" Aligners at the end of treatment. Align Technology has developed the Invisalign System, which is a series of clear plastic appliances ("aligners") that move the patient's teeth in small increments from their original state to a final, treated state. The Invisalign System uses a computer as a tool to assist in creating a series of sequential movements to assure light and consistent forces on the patient's teeth.

  14. Standard Technical Specifications General Electric plants, BWR/4:Bases (Sections 3.4-3.10). Volume 3, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for General Electric BWR/4 Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the specifications for all chapters and sections of the improved STS. Volume 2 contains he Bases for Chapters 2.0 and 3.0, and Sections 3.1-3.3 of the improved STS. This document, Volume 3, contains the Bases for Sections 3.4-3.10 of the improved STS

  15. Standard technical specifications: Combustion engineering plants. Volume 3, Revision 1: Bases (Sections 3.4--3.9)

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for Combustion Engineering Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS Volume 3 contains the Bases for Sections 3.4--3.9 of the improved STS

  16. Standard technical specifications: Babcock and Wilcox plants. Volume 3, Revision 1: Bases (Sections 3.4--3.9)

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry to produce improved Standard Technical Specifications (STS), Revision 1 for Babcock and Wilcox Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved STS or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume 1 contains the Specifications for all chapters and sections of the improved STS. Volume 2 contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1--3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4--3.9 of the improved STS

  17. Standard Technical Specifications General Electric plants, BWR/4: Bases (Sections 2.0-3.3). Volume 2, Revision 1

    International Nuclear Information System (INIS)

    1995-04-01

    This report documents the results of the combined effort of the NRC and the industry produce improved Standard Technical Specifications (STS), Revision 1 for General Electric BWR/4 Plants. The changes reflected in Revision 1 resulted from the experience gained from license amendment applications to convert to these improved ST or to adopt partial improvements to existing technical specifications. This NUREG is the result of extensive public technical meetings and discussions between the Nuclear Regulatory Commission (NRC) staff and various nuclear power plant licensees, Nuclear Steam Supply System (NSSS) Owners Groups, NSSS vendors, and the Nuclear Energy Institute (NEI). The improved STS were developed based on the criteria in the Final Commission Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 22, 1993. The improved STS will be used as the basis for individual nuclear power plant licensees to develop improved plant-specific technical specifications. This report contains three volumes. Volume I contains the Specifications for all chapters and sections of the improved STS. This document, Volume 2, contains the Bases for Chapters 2.0 and 3.0, and Sections 3.1-3.3 of the improved STS. Volume 3 contains the Bases for Sections 3.4-3.10 of the improved STS

  18. Revision of by-laws about effluents of EdF's nuclear power plants; Revision des arretes de rejets des centrales nucleaires d'EDF

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-07-01

    In France, in application of the clean water law from January 3, 1992 and since the decree 95-540 from May 4, 1995, each basic nuclear facility receives a single permission which covers both its water takes and its radioactive and non-radioactive effluents. This decree, initially dedicated to new facilities has been enlarged to all existing installations for which the prefectorial by-laws have reached their date-line. Thus, up to now, five inter-ministerial by-laws have renewed the permissions of water takes and effluents evacuation of the power plants of Saint-Laurent-des-Eaux (Loir-et-Cher), Flamanville (Manche), Paluel (Seine-Maritime), Belleville (Cher) and Saint-Alban (Isere). These by-laws foresee an important abatement of the effluents and concern more particularly the tritium, {sup 14}C, the iodine isotopes and also some other non-radioactive chemical compounds. This document is a compilation of all revised by-laws about effluents and concerning the nuclear power plants listed above. (J.S.)

  19. Print Finishing: From Manual to Automated Print Finishing

    Directory of Open Access Journals (Sweden)

    Gareth Ward

    2004-12-01

    Full Text Available Meeting the demand for faster turnrounds and shorter print runs goes beyond making the printing press easier to set up and change. There is little point in producing plates and then sheets from a press if the post press area does not change to keep abreast of developments in prepress and the print room. The greatest impact is going to come from JDF, the end to end production data format which is finding wide spread acceptance in print areas. To date finishing equipment manufacturers are not as well represented within the CIP4 organisation as prepress and press vendors, but the major manufacturers are members. All are working to the goal of complete connectivity.The idea of JDF is that if the format of a print product like a magazine is known during the creation phases, the information can be used to preset machinery that is going to be used to produce it, so avoiding input errors and saving manufacturing time.A second aspect to JDF is that information about performance and progress is gathered and can be retrieved from a central point or made available to a customer. Production scheduling and costing becomes more accurate and customer relationships are deepened. However JDF to its fullest extent is not yet in use in connecting the finishing area to the rest of the printing plant. Around the world different companies are testing the idea of JDF to connect saddle stitchers, guillotines and binders with frantic work underway to be able to show results soon.

  20. Next Generation Nuclear Plant Materials Research and Development Program Plan, Revision 3

    International Nuclear Information System (INIS)

    G.O. Hayner; R.L. Bratton; R.E. Mizia; W.E. Windes; W.R. Corwin; T.D. Burchell; C.E. Duty; Y. Katoh; J.W. Klett; T.E. McGreevy; R.K. Nanstad; W. Ren; P.L. Rittenhouse; L.L. Snead; R.W. Swindeman; D.F. Wlson

    2006-01-01

    This is the 2006 update (Revision 3) of the NGNP Materials Research and Development Program Plan. This law established that the U.S Department of Energy (DOE) Secretary of Energy shall establish a ''Next Generation Nuclear Plant'' (NGNP) project. The NGNP project named in the Act was given the following attributes and guiding principles to manage its development: (1) The NGNP consists of research, development, design (R and DD), construction, and operation of a prototype reactor to generate electricity and hydrogen; (2) The project shall be managed by the DOE Office of Nuclear Energy; (3) The Idaho National Laboratory (INL) shall be the lead DOE laboratory for the NGNP; (4) The INL shall establish collaborations with selected institutions of higher education, other research institutes and international researchers; (5) The INL shall organize an industrial consortium of partners for cost-shared R and DD, construction; (6) The project shall be sited at the INL; (7) The project shall be licensed by the Nuclear Regulatory Commission (NRC) and by July, 2008 the NRC and DOE shall jointly submit a licensing strategy to Congress; (8) The project shall be organized to maximize technical interchange with the nuclear power industry, nuclear power plant construction firms, the chemical process industry and to seek international cooperation, participation and contributions; (9) The Nuclear Energy Research Advisory Committee (NERAC) shall review all program plans for the NGNP; (10) Phase 1 of the project (selection of hydrogen production technology, conduct R and DD and initial design activities) shall be completed no later than September 30, 2011; (11) Phase 2 of the project (continue R and DD, develop final design, apply for a license, construct and start operations) shall be completed by September 30, 2021; and (12) Provision for authorization of appropriations was made. As a result of the direction provided, the INL and the DOE issued an NGNP Preliminary Project Management

  1. 78 FR 35719 - Endangered and Threatened Wildlife and Plants; Proposed Revision To the Nonessential Experimental...

    Science.gov (United States)

    2013-06-13

    ... governing the Mexican wolf nonessential experimental population designation. Background Our approach in this... private activities within or adjacent to the experimental population area. Furthermore, as set forth in 50...; Proposed Revision To the Nonessential Experimental Population of the Mexican Wolf AGENCY: Fish and Wildlife...

  2. Quality provision within the preparation of the finishing of the building of 3. and 4. block of the Nuclear Power Plant Mochovce

    International Nuclear Information System (INIS)

    Kompan, L.

    2007-01-01

    The contribution defines within the mentioned project the basic documentation of quality management system, relation between the launching programme, phase programmes and quality plans, relations between documentation of quality provision and documentation of the project quality provision. Moreover it describes the organisation structure of the plant Slovak Power Plants MO34 and the organisation scheme of the project team and principles of communication between teams on the working level

  3. 78 FR 37281 - Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses

    Science.gov (United States)

    2013-06-20

    ... factors: (1) License renewal will involve nuclear power plants for which the environmental impacts of...) Changes in the environment around nuclear power plants are gradual and predictable. The 1996 GEIS improved... environmental impacts that may occur from renewing commercial nuclear power plant operating licenses; (2...

  4. 78 FR 46255 - Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses; Correction

    Science.gov (United States)

    2013-07-31

    ... Environmental Review for Renewal of Nuclear Power Plant Operating Licenses; Correction AGENCY: Nuclear... nuclear power plant. Compliance with the provisions of the rule is required by June 20, 2014. This... environmental effect of renewing the operating license of a nuclear power plant. This document is necessary to...

  5. Provision of NDA instrumentation for the control of operations on plutonium finishing and waste plants at the Sellafield nuclear fuel reprocessing facility

    International Nuclear Information System (INIS)

    Whitehouse, K.R.; Orr, C.H.

    1995-01-01

    On BNFL's Sellafield site a significant number of major plants are involved in the handling, processing and storage of plutonium in various forms including nitrate, oxide and mixed oxide (MOX). Other plants in operation or under construction treat and prepare for storage, plutonium bearing wastes in the form of plutonium contaminated materials -- PCM (transuranic waste -- TRU) or low level waste. Concurrently, a number of old plutonium handling plants are being decommissioned. The safety and cost effectiveness of these widely varying operations has been ensured by the development and installation of a wide range of special radiometric instrumentation. These systems based on a range of neutron counting and high resolution gamma spectrometric techniques -- singly or in combination -- enable BNFL to maintain a detailed and comprehensive picture of the disposition of plutonium within each plant and across the site. This paper describes an overview of the range of plant and paper prove waste measurement systems in this context, highlighting the specific roles of the Plutonium Inventory Measurement System (PIMS) for real time accountancy and the Decommissioning In-Situ Plutonium Inventory Monitor (DISPIM) for material control during decommissioning

  6. Guidelines for Electromagnetic Interference Testing of Power Plant Equipment: Revision 3 to TR-102323

    Energy Technology Data Exchange (ETDEWEB)

    J. Cunningham and J. Shank

    2004-11-01

    To continue meeting safety and reliability requirements while controlling costs, operators of nuclear power plants must be able to replace and upgrade equipment in a cost-effective manner. One issue that has been problematic for new plant equipment and especially for digital instrumentation and control (I&C) systems in recent years is electromagnetic compatibility (EMC). The EMC issue usually involves testing to show that critical equipment will not be adversely affected by electromagnetic interference (EMI) in the plant environment. This guide will help nuclear plant engineers address EMC issues and qualification testing in a consistent, comprehensive manner.

  7. Guidelines for Electromagnetic Interference Testing of Power Plant Equipment: Revision 3 to TR-102323

    International Nuclear Information System (INIS)

    Cunningham, J.; Shank, J.

    2004-01-01

    To continue meeting safety and reliability requirements while controlling costs, operators of nuclear power plants must be able to replace and upgrade equipment in a cost-effective manner. One issue that has been problematic for new plant equipment and especially for digital instrumentation and control (I and C) systems in recent years is electromagnetic compatibility (EMC). The EMC issue usually involves testing to show that critical equipment will not be adversely affected by electromagnetic interference (EMI) in the plant environment. This guide will help nuclear plant engineers address EMC issues and qualification testing in a consistent, comprehensive manner

  8. New technical knowledge to be implemented to the revision of rules on pipe wall thinning management for PWR Plants. 2006 edition

    International Nuclear Information System (INIS)

    Hirai, Junya; Amano, Yoichi; Nakamura, Takao

    2013-01-01

    Rules for PWR plant pipe wall thinning management were formulated by the Japan Society of Mechanical Engineers in 2006. Since then thinning management of Japanese PWR plants has been carried out based on this rule. Pipe wall thinning phenomena to be dealt with in this rule have been identified in many piping components of power plants. New technical knowledge has been accumulated since the issuance of 2006 edition. We have formulated these knowledge and information about the thinning phenomena in PWR power plants. Given the history of application of this rule, we have to make our best effort to carry out a study of latest technical knowledge and implement them to the revision of rule and improve pipe wall thinning management. This paper summarizes the new technical knowledge and basis to be implemented to the revision of rules on pipe wall thinning management for PWR plants in Japan. (author)

  9. Maintenance implementation plan for the B Plant/WESF. Revision 4

    International Nuclear Information System (INIS)

    Tritt, S.E.; Lueck, B.H.

    1996-01-01

    This Maintenance Implementation Plan (MIP) has been developed for maintenance functions associated with the B Plant/WESF (Waste Encapsulation Storage Facility) complex. The objective of this plan is to provide baseline information for establishing and identifying WHC conformance programs and policies applicable to implementation of DOE order 4330.4B guidelines. In addition, this maintenance plan identifies the actions necessary to develop a cost-effective and efficient maintenance program at B Plant/WESF. The B Plant WESF facility complex consists of three main facilities and several support structures located in the 200 East Area of the Hanford site. B Plant is a transition facility that is required to ensure safe storage and management of WESF (operating facility) cesium and strontium capsules. B Plant/WESF also contains substantial radiological inventory from previous campaigns. There are no production activities at B Plant, but several of its operating systems are required to accomplish the current B Plant/WESF mission. B Plant/WESF are each considered a nuclear facility due to the storage of cesium and strontium capsules at WESF and the large radiological inventory from past processing

  10. Health effects models for nuclear power plant accident consequence analysis. Part 1, Introduction, integration, and summary: Revision 2

    Energy Technology Data Exchange (ETDEWEB)

    Evans, J.S. [Harvard School of Public Health, Boston, MA (United States); Abrahmson, S. [Wisconsin Univ., Madison, WI (United States); Bender, M.A. [Brookhaven National Lab., Upton, NY (United States); Boecker, B.B.; Scott, B.R. [Inhalation Toxicology Research Inst., Albuquerque, NM (United States); Gilbert, E.S. [Battelle Pacific Northwest Lab., Richland, WA (United States)

    1993-10-01

    This report is a revision of NUREG/CR-4214, Rev. 1, Part 1 (1990), Health Effects Models for Nuclear Power Plant Accident Consequence Analysis. This revision has been made to incorporate changes to the Health Effects Models recommended in two addenda to the NUREG/CR-4214, Rev. 1, Part 11, 1989 report. The first of these addenda provided recommended changes to the health effects models for low-LET radiations based on recent reports from UNSCEAR, ICRP and NAS/NRC (BEIR V). The second addendum presented changes needed to incorporate alpha-emitting radionuclides into the accident exposure source term. As in the earlier version of this report, models are provided for early and continuing effects, cancers and thyroid nodules, and genetic effects. Weibull dose-response functions are recommended for evaluating the risks of early and continuing health effects. Three potentially lethal early effects -- the hematopoietic, pulmonary, and gastrointestinal syndromes are considered. Linear and linear-quadratic models are recommended for estimating the risks of seven types of cancer in adults - leukemia, bone, lung, breast, gastrointestinal, thyroid, and ``other``. For most cancers, both incidence and mortality are addressed. Five classes of genetic diseases -- dominant, x-linked, aneuploidy, unbalanced translocations, and multifactorial diseases are also considered. Data are provided that should enable analysts to consider the timing and severity of each type of health risk.

  11. Review about corrosion of superheaters tubes in biomass plants; Revision sobre la corrosion de tubos sobrecalentadores en plantas de biomasa

    Energy Technology Data Exchange (ETDEWEB)

    Berlanga-Labari, C.; Fernandez-Carrasquilla, J.

    2006-07-01

    The design of new biomass-fired power plants with increased steam temperature raises concerns of high-temperature corrosion. The high potassium and chlorine contents in many biomass, specially in wheat straw, are potentially harmful elements with regard to corrosion. Chlorine may cause accelerated corrosion resulting in increased oxidation, metal wastage, internal attack, void formations and loose non-adherent scales. The most severe corrosion problems in biomass-fired systems are expected to occur due to Cl-rich deposits formed on superheater tubes. In the first part of this revision the corrosion mechanism proposed are described in function of the conditions and compounds involved. The second part is focused on the behaviour of the materials tested so far in the boiler and in the laboratory. First the traditional commercial alloys are studied and secondly the new alloys and the coasting. (Author). 102 refs.

  12. Qualification of nuclear power plant inspection, examination, and testing personnel. Revision 1, September 1980

    International Nuclear Information System (INIS)

    Anon.

    1981-01-01

    Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to 10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities, requires that the quality assurance program provide for indoctrination and training of personnel performing activities affecting quality as necessary to ensure that quality assurance personnel achieve and maintain suitable proficiency. This guide describes a method acceptable to the NRC staff for complying with the Commission's regulations with regard to qualification of inspection, examination, and testing personnel for all types of nuclear power plants

  13. Conversion of finished leather waste incorporated with plant fibers into value added consumer products - An effort to minimize solid waste in Ethiopia.

    Science.gov (United States)

    Teklay, A; Gebeyehu, G; Getachew, T; Yaynshet, T; Sastry, T P

    2017-10-01

    Presently, the leftovers from leather product industries are discarded as waste in Ethiopia. The objective of the present study was therefore, to prepare composite sheets by incorporating various plant fibers like enset (Ensete ventricosum), hibiscus (Hibiscus cannabinus), jute (Corchorus trilocularis L.), palm (Phoenix dactylifera) and sisal (Agave sisal) in various proportions into the leather waste. Resin binder (RB) and natural rubber latex (NRL) were used as binding agents for the preparation of the composite sheets. The composite sheets prepared were characterized for their physicochemical properties (tensile strength, elongation at break, stitch tear strength, water absorption, water desorption and flexing strength). Composite sheets prepared using RB having 10% hibiscus, 20% palm and 40% sisal fibers showed better mechanical properties than their respective controls. In composite sheets prepared using NRL having 30% jute fiber exhibited better mechanical properties than its control. Most of the plant fibers used in this study played a role in increasing the performance of the sheets. However, as seen from the results, the contribution of these plant fibers on performance of the composite sheets prepared is dependent on the ratio used and the nature of binder. The SEM studies have exhibited the composite nature of the sheets and FTIR studies have shown the functional groups of collagen protein, cellulose and binders. The prepared sheets were used as raw materials for preparation of items like stiff hand bags, ladies' purse, keychain, chappal upper, wallet, wall cover, mouse pad and other interior decorating products. By preparing such value added products, we can reduce solid waste; minimize environmental pollution and thereby securing environmental sustainability. Copyright © 2017 Elsevier Ltd. All rights reserved.

  14. Automation in tube finishing bay

    International Nuclear Information System (INIS)

    Bhatnagar, Prateek; Satyadev, B.; Raghuraman, S.; Syama Sundara Rao, B.

    1997-01-01

    Automation concept in tube finishing bay, introduced after the final pass annealing of PHWR tubes resulted in integration of number of sub-systems in synchronisation with each other to produce final cut fuel tubes of specified length, tube finish etc. The tube finishing bay which was physically segregated into four distinct areas: 1. tube spreader and stacking area, 2. I.D. sand blasting area, 3. end conditioning, wad blowing, end capping and O.D. wet grinding area, 4. tube inspection, tube cutting and stacking area has been studied

  15. Stormwater Pollution Prevention Plan TA-60 Asphalt Batch Plant Revision 2: January 2017

    Energy Technology Data Exchange (ETDEWEB)

    Sandoval, Leonard Frank [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2017-02-01

    The Stormwater Pollution Prevention Team (PPT) is applicable to operations at the Technical Area (TA)- 60 Asphalt Batch Plant (ABP) located on Eniwetok Drive/Sigma Mesa, in Los Alamos County, New Mexico at Los Alamos National Laboratory (LANL).

  16. Waste Isolation Pilot Plant No-migration variance petition. Addendum: Volume 7, Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    1990-03-01

    This report describes various aspects of the Waste Isolation Pilot Plant (WIPP) including design data, waste characterization, dissolution features, ground water hydrology, natural resources, monitoring, general geology, and the gas generation/test program.

  17. Bioconversion of plant biomass to ethanol. Annual report and revised research plan, January 1977--January 1978

    Energy Technology Data Exchange (ETDEWEB)

    Brooks, R.E.; Bellamy, W.D.; Su, T.M.

    1978-03-23

    The objective of this research is to demonstrate on a laboratory scale the technical feasibility of the direct microbial conversion of pretreated wood to ethanol. During the first year of this contract, we investigated the feasibility of biologically delignifying wood with C. pruinosum and directly fermenting the pretreated wood to ethanol with a mixed culture. Bench-top fermentations of a thermophilic bacillus growing on glucose and of a mixed culture of thermophilic sporocytophaga (US) and a thermophilic bacillus growing on microcrystalline and amorphous cellulose were evaluated for growth and ethanol production. In the mixed culture fermentation of amorphous and microcrystalline cellulose, the specific rate of substrate depletion was calculated to be 0.087 hr/sup -1/ and 0.0346 hr/sup -1/, respectively. However, defining the growth requirements of C. pruinosum and sporocytophaga (US) proved more difficult than originally anticipated. In order to achieve the program objectives within the contract period, a revised research plan was developed based upon chemical pretreatment and the direct fermentation of pretreated hardwood to ethanol. In place of the biological delignification pretreatment step, we have substituted a chemically supplemented steam pretreatment step to partially delignify wood and to enhance its accessibility to microbial utilization. Clostridium thermocellum, which ferments cellulose directly to ethanol and acetic acid, has replaced the mixed culture fermentation stage for ethanol production. Research on the production of ethanol from xylose by the thermophilic bacillus ZB-B2 is retained as one means of utilizing the hemicellulose fraction of hardwood. Work on the genetic improvement of the ethanol yields of both cultures by suppressing acetic acid production is also retained. The rationale, experimental approach, and economic considerations of this revised research plan are also presented.

  18. W-007H B Plant Process Condensate Treatment Facility. Revision 3

    International Nuclear Information System (INIS)

    Rippy, G.L.

    1995-01-01

    B Plant Process Condensate (BCP) liquid effluent stream is the condensed vapors originating from the operation of the B Plant low-level liquid waste concentration system. In the past, the BCP stream was discharged into the soil column under a compliance plan which expired January 1, 1987. Currently, the BCP stream is inactive, awaiting restart of the E-23-3 Concentrator. B Plant Steam Condensate (BCS) liquid effluent stream is the spent steam condensate used to supply heat to the E-23-3 Concentrator. The tube bundles in the E-23-3 Concentrator discharge to the BCS. In the past, the BCS stream was discharged into the soil column. Currently, the BCS stream is inactive. This project shall provide liquid effluent systems (BCP/BCS/BCE) capable of operating for a minimum of 20 years, which does not include the anticipated decontamination and decommissioning (D and D) period

  19. W-007H B Plant Process Condensate Treatment Facility. Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    Rippy, G.L.

    1995-01-20

    B Plant Process Condensate (BCP) liquid effluent stream is the condensed vapors originating from the operation of the B Plant low-level liquid waste concentration system. In the past, the BCP stream was discharged into the soil column under a compliance plan which expired January 1, 1987. Currently, the BCP stream is inactive, awaiting restart of the E-23-3 Concentrator. B Plant Steam Condensate (BCS) liquid effluent stream is the spent steam condensate used to supply heat to the E-23-3 Concentrator. The tube bundles in the E-23-3 Concentrator discharge to the BCS. In the past, the BCS stream was discharged into the soil column. Currently, the BCS stream is inactive. This project shall provide liquid effluent systems (BCP/BCS/BCE) capable of operating for a minimum of 20 years, which does not include the anticipated decontamination and decommissioning (D and D) period.

  20. B Plant Complex generator dangerous waste storage areas inspection plan: Revision 1

    International Nuclear Information System (INIS)

    Beam, T.G.

    1994-01-01

    This document contains the inspection plan for the <90 day dangerous/mixed waste storage areas and satellite accumulation areas at B Plant Complex. This inspection plan is designed to comply with all applicable federal, state and US Department of Energy-Richland Operations Office training requirements. In particular, the requirements of WAC 173-303 ''Dangerous Waste Regulations'' are met by this inspection plan. This inspection plan is designed to provide B Plant Complex with the records and documentation showing that the waste storage and handling program is in compliance with applicable regulations. The plan also includes the requirements for becoming a qualified inspector of waste storage areas and the responsibilities of various individuals and groups at B Plant Complex

  1. Reliability programs for nuclear power plants. Regulatory standard S-98 revision 1

    International Nuclear Information System (INIS)

    2005-07-01

    The purpose of this regulatory standard is to help assure, in accordance with the purpose of the Nuclear Safety and Control Act (NSCA), that a licensee who constructs or operates a nuclear power plant (NPP) develops and implements a reliability program that assures that the systems important to safety at the plant can and will meet their defined design and performance specifications at acceptable levels of reliability throughout the lifetime of the facility. This regulatory standard describes the requirements of a reliability program for a nuclear power plant. The licensee shall implement the requirements described in this regulatory standard when a condition of a licence or other legally enforceable instrument so requires.(author)

  2. Knowledge and abilities catalog for nuclear power plant operators: Pressurized water reactors. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-08-01

    This document provides the basis for the development of content-valid licensing examinations for reactor operators and senior reactor operators. The examinations developed using the PWR catalog will cover those topics listed under Title 10, (ode of Federal Regulations Part 55. The PWR catalog contains approximately 5100 knowledge and ability (K/A) statements for reactor operators and senior reactor operators. The catalog is organized into six major sections: Catalog Organization; Generic Knowledge and Abilities; Plant Systems; Emergency and Abnormal Plant Evolutions; Components and Theory.

  3. Knowledge and abilities catalog for nuclear power plant operators: Pressurized water reactors. Revision 1

    International Nuclear Information System (INIS)

    1995-08-01

    This document provides the basis for the development of content-valid licensing examinations for reactor operators and senior reactor operators. The examinations developed using the PWR catalog will cover those topics listed under Title 10, (ode of Federal Regulations Part 55. The PWR catalog contains approximately 5100 knowledge and ability (K/A) statements for reactor operators and senior reactor operators. The catalog is organized into six major sections: Catalog Organization; Generic Knowledge and Abilities; Plant Systems; Emergency and Abnormal Plant Evolutions; Components and Theory

  4. 75 FR 16404 - Endangered and Threatened Wildlife and Plants; Proposed Revised Designation of Critical Habitat...

    Science.gov (United States)

    2010-04-01

    ... soil surface near A. jaegerianus plants (Fahnestock 1999, p. 3). The topography where A. jaegerianus... mining, recreational off-highway vehicle use, military maneuvers on Army lands at the NTC and its future... determined, by referring to digital raster graphic maps, the topography is either too steep or the elevation...

  5. Operation of Wastewater Treatment Plants. Volume 1. A Field Study Training Program. Third Edition. Revised.

    Science.gov (United States)

    California State Univ., Sacramento. Dept. of Civil Engineering.

    The purpose of this wastewater treatment field study training program is to: (1) develop new qualified wastewater treatment plant operators; (2) expand the abilities of existing operators, permitting better service both to employers and public; and (3) prepare operators for civil service and certification examinations (examinations administered by…

  6. Water Treatment Plant Operation Volume 2. A Field Study Training Program. Revised.

    Science.gov (United States)

    California State Univ., Sacramento. School of Engineering.

    The purpose of this water treatment field study training program is to: (1) develop new qualified water treatment plant operators; (2) expand the abilities of existing operators, permitting better service both to employers and public; and (3) prepare operators for civil service and certification examinations (examinations administered by…

  7. Revising and Updating the Plant Science Components of the Connecticut Vocational Agriculture Curriculum.

    Science.gov (United States)

    Connecticut Univ., Storrs. Dept. of Educational Leadership.

    This curriculum guide provides the plant science components of the vocational agriculture curriculum for Regional Vocational Agriculture Centers. The curriculum is divided into exploratory units for students in the 9th and 10th grades and specialized units for students in grades 11 and 12. The five exploratory units are: agricultural pest control;…

  8. Technical assessment of compliance with work place air sampling requirements at T Plant. Revision No. 1

    International Nuclear Information System (INIS)

    Hackworth, M.F.

    1995-01-01

    The US DOE requires its contractors to conduct air sampling to detect and evaluate airborne radioactive material in the workplace. Hanford Reservation T Plant compliance with workplace air sampling requirements has been assessed. Requirements, basis for determining compliance and recommendations are included

  9. 77 FR 23007 - Endangered and Threatened Wildlife and Plants; Designation of Revised Critical Habitat for Allium...

    Science.gov (United States)

    2012-04-17

    ... sometimes produce flower buds. In addition to sexual reproduction through seed production, A. munzii plants... estimated about 27,000 A. c. var. notatior individuals occupied about 145 acres (ac) (59 hectares (ha)) of..., p. 15). Approximately 84,000 of these individuals were found on 236.5 ac (95.7 ha) along the San...

  10. 76 FR 29107 - Endangered and Threatened Wildlife and Plants; Final Revised Designation of Critical Habitat for...

    Science.gov (United States)

    2011-05-19

    ..., Anthidium dammersi, is a solitary bee that nests in the ground, likely in close proximity to A. jaegerianus plants. Ground-nesting bees are highly sensitive to activities that may compact soil, as the nests may be... preserving our world as a museum. Our Response: We recognize that the natural world is one of change...

  11. Revision of nuclear power plants safety systems' routine testing assigned periodicity during the design extension period

    International Nuclear Information System (INIS)

    Skalozubov, V.I.; Kozlov, Yi.L.; Chulkyin, O.O.

    2017-01-01

    When nuclear power plants safety systems thermal equipment operation extending, a necessary requirement shall rely on revising the scheduled equipment tests frequency to optimize those tests schedule taking into account the equipment remained lifespan. On the one hand, there exists a need for tests frequency increase to detect ''hidden'' failures, and on the another, frequent tests cause a premature wear of the equipment. Proposed is an original method for optimizing the frequency of NPPs safety systems thermal engineering equipment testing. Essential in the proposed method is the optimization criterion chosen: index of security system failure probability non-exceedance during the beyond-design operating period as referred to the failure probability expected considering the equipment residual resource during the design operating period. The developed method implementation when applied to NPPs safety systems operated beyond the design service life at nuclear power plants with WWER-1000 series reactors, allowed to establish that the optimal tests frequency makes half the designed one when the equipment service life is extended by five years and three times less that the designed frequency when subject lifespan extended by 10 years.

  12. Waste Isolation Pilot Plant No-Migration Variance Petition. Revision 1, Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Hunt, Arlen

    1990-03-01

    The purpose of the WIPP No-Migration Variance Petition is to demonstrate, according to the requirements of RCRA {section}3004(d) and 40 CFR {section}268.6, that to a reasonable degree of certainty, there will be no migration of hazardous constituents from the facility for as long as the wastes remain hazardous. The DOE submitted the petition to the EPA in March 1989. Upon completion of its initial review, the EPA provided to DOE a Notice of Deficiencies (NOD). DOE responded to the EPA`s NOD and met with the EPA`s reviewers of the petition several times during 1989. In August 1989, EPA requested that DOE submit significant additional information addressing a variety of topics including: waste characterization, ground water hydrology, geology and dissolution features, monitoring programs, the gas generation test program, and other aspects of the project. This additional information was provided to EPA in January 1990 when DOE submitted Revision 1 of the Addendum to the petition. For clarity and ease of review, this document includes all of these submittals, and the information has been updated where appropriate. This document is divided into the following sections: Introduction, 1.0: Facility Description, 2.0: Waste Description, 3.0; Site Characterization, 4.0; Environmental Impact Analysis, 5.0; Prediction and Assessment of Infrequent Events, 6.0; and References, 7.0.

  13. 2003 Kansas City Plant Annual Illness and Injury Surveillance Report, Revised September 2007

    Energy Technology Data Exchange (ETDEWEB)

    U.S. Department of Energy, Office of Health, Safety and Security, Office of Illness and Injury Prevention Programs

    2007-10-04

    Annual Illness and Injury Surveillance Program report for 2003 for the Kansas City Plant. The U.S. Department of Energy’s (DOE) commitment to assuring the health and safety of its workers includes the conduct of epidemiologic surveillance activities that provide an early warning system for health problems among workers. The IISP monitors illnesses and health conditions that result in an absence of workdays, occupational injuries and illnesses, and disabilities and deaths among current workers.

  14. 2003 Pantex Plant Annual Illness and Injury Surveillance Report, Revised September 2007

    Energy Technology Data Exchange (ETDEWEB)

    U.S. Department of Energy, Office of Health, Safety and Security, Office of Illness and Injury Prevention Programs

    2007-10-05

    Annual Illness and Injury Surveillance Program report for 2003 for the Pantex Plant. DOE is commited to assuring the health and safety of its workers. This includes the conduct of epidemiologic surveillance activities that provide an early warning system for health problems among workers. The IISP monitors illnesses and health conditions that result in an absence of workdays, occupational injuries and illnesses, and disabilities and deaths among current workers.

  15. A revised list of alien plants for the Kruger National Park

    Directory of Open Access Journals (Sweden)

    L.C. Foxcroft

    2003-12-01

    Full Text Available Alien plants recorded in the Kruger National Park are listed, providing an update of species that have been recorded since the last published list in 1988. The serious consequences that invasive alien plants pose are widely recognised internationally and are regarded as the greatest threat to the Kruger National Park. It is extremely important to maintain an updated list of species to use as a reference and from which to monitor changes in the influx of invasive species. The list contains the invasive status of the plants, current impact, habitat types, biological control status and status according to the Conservation of Agricultural Resources Act (CARA, Act 43 of 1983, as amended in March 2001. The list comprises 370 species, of which 121 are invaders and two are transformer weeds, which may cause considerable damage and alterations to the indigenous biodiversity. A total of 91 species listed herein are also listed in the CARA regulations or are proposed additions to the CARA regulations.

  16. Acceptable knowledge document for INEEL stored transuranic waste - Rocky Flats Plant waste. Revision 2

    International Nuclear Information System (INIS)

    1998-01-01

    This document and supporting documentation provide a consistent, defensible, and auditable record of acceptable knowledge for waste generated at the Rocky Flats Plant which is currently in the accessible storage inventory at the Idaho National Engineering and Environmental Laboratory. The inventory consists of transuranic (TRU) waste generated from 1972 through 1989. Regulations authorize waste generators and treatment, storage, and disposal facilities to use acceptable knowledge in appropriate circumstances to make hazardous waste determinations. Acceptable knowledge includes information relating to plant history, process operations, and waste management, in addition to waste-specific data generated prior to the effective date of the RCRA regulations. This document is organized to provide the reader a comprehensive presentation of the TRU waste inventory ranging from descriptions of the historical plant operations that generated and managed the waste to specific information about the composition of each waste group. Section 2 lists the requirements that dictate and direct TRU waste characterization and authorize the use of the acceptable knowledge approach. In addition to defining the TRU waste inventory, Section 3 summarizes the historical operations, waste management, characterization, and certification activities associated with the inventory. Sections 5.0 through 26.0 describe the waste groups in the inventory including waste generation, waste packaging, and waste characterization. This document includes an expanded discussion for each waste group of potential radionuclide contaminants, in addition to other physical properties and interferences that could potentially impact radioassay systems

  17. Next Generation Nuclear Plant Materials Research and Development Program Plan, Revision 4

    Energy Technology Data Exchange (ETDEWEB)

    G.O. Hayner; R.L. Bratton; R.E. Mizia; W.E. Windes; W.R. Corwin; T.D. Burchell; C.E. Duty; Y. Katoh; J.W. Klett; T.E. McGreevy; R.K. Nanstad; W. Ren; P.L. Rittenhouse; L.L. Snead; R.W. Swindeman; D.F. Wlson

    2007-09-01

    DOE has selected the High Temperature Gas-cooled Reactor (HTGR) design for the Next Generation Nuclear Plant (NGNP) Project. The NGNP will demonstrate the use of nuclear power for electricity and hydrogen production. It will have an outlet gas temperature in the range of 950°C and a plant design service life of 60 years. The reactor design will be a graphite moderated, helium-cooled, prismatic or pebble-bed reactor and use low-enriched uranium, TRISO-coated fuel. The plant size, reactor thermal power, and core configuration will ensure passive decay heat removal without fuel damage or radioactive material releases during accidents. The NGNP Materials Research and Development (R&D) Program is responsible for performing R&D on likely NGNP materials in support of the NGNP design, licensing, and construction activities. Some of the general and administrative aspects of the R&D Plan include: • Expand American Society of Mechanical Engineers (ASME) Codes and American Society for Testing and Materials (ASTM) Standards in support of the NGNP Materials R&D Program. • Define and develop inspection needs and the procedures for those inspections. • Support selected university materials related R&D activities that would be of direct benefit to the NGNP Project. • Support international materials related collaboration activities through the DOE sponsored Generation IV International Forum (GIF) Materials and Components (M&C) Project Management Board (PMB). • Support document review activities through the Materials Review Committee (MRC) or other suitable forum.

  18. Acceptable knowledge document for INEEL stored transuranic waste -- Rocky Flats Plant waste. Revision 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-01-23

    This document and supporting documentation provide a consistent, defensible, and auditable record of acceptable knowledge for waste generated at the Rocky Flats Plant which is currently in the accessible storage inventory at the Idaho National Engineering and Environmental Laboratory. The inventory consists of transuranic (TRU) waste generated from 1972 through 1989. Regulations authorize waste generators and treatment, storage, and disposal facilities to use acceptable knowledge in appropriate circumstances to make hazardous waste determinations. Acceptable knowledge includes information relating to plant history, process operations, and waste management, in addition to waste-specific data generated prior to the effective date of the RCRA regulations. This document is organized to provide the reader a comprehensive presentation of the TRU waste inventory ranging from descriptions of the historical plant operations that generated and managed the waste to specific information about the composition of each waste group. Section 2 lists the requirements that dictate and direct TRU waste characterization and authorize the use of the acceptable knowledge approach. In addition to defining the TRU waste inventory, Section 3 summarizes the historical operations, waste management, characterization, and certification activities associated with the inventory. Sections 5.0 through 26.0 describe the waste groups in the inventory including waste generation, waste packaging, and waste characterization. This document includes an expanded discussion for each waste group of potential radionuclide contaminants, in addition to other physical properties and interferences that could potentially impact radioassay systems.

  19. Sampling and analysis plan for Mount Plant D ampersand D soils packages, Revision 1

    International Nuclear Information System (INIS)

    1991-02-01

    There are currently 682 containers of soils in storage at Mound Plant, generated between April 1 and October 31, 1990 as a result of excavation of soils containing plutonium-238 at two ongoing Decontamination and Decommissioning (D ampersand D) Program sites. These areas are known as Area 14, the waste transfer system (WTS) hillside, and Area 17, the Special Metallurgical (SM) Building area. The soils from these areas are part of Mound Plant waste stream number AMDM-000000010, Contaminated Soil, and are proposed for shipment to the Nevada Test Site (NTS) for disposal as low-level radioactive waste. The sealed waste packages, constructed of either wood or metal, are currently being stored in Building 31 and at other locations throughout the Mound facility. At a meeting in Las Vegas, Nevada on October, 26, 1990, DOE Nevada Operations Office (DOE-NV) and NTS representatives requested that the Mound Plant D ampersand D soils proposed for shipment to NTS be sampled for Toxicity Characteristic Leaching Procedure (TCLP) constituents. On December 14, 1990, DOE-NV also requested that additional analyses be performed on the soils from one of the soils boxes for polychlorinated biphenyls (PCBs), particle size distribution, and free liquids. The purpose of this plan is to document the proposed sampling and analyses of the packages of D ampersand D soils produced prior to October 31, 1990. In order to provide a thorough description of the soils excavated from the WTS and SM areas, sections 1.1 and 1.2 provide historical Information concerning the D ampersand D soils, including waste stream evaluations and past sampling data

  20. Aqueous sample from B-Plant, Tank 9-1. Revision 1

    International Nuclear Information System (INIS)

    Bell, K.E.

    1995-01-01

    Eight liquid samples were received from B-Plant Tank 9-1 in four lots of two samples each, for inorganic and organic analysis. This is the final report for the sampling and analysis effort; included are summary tables of the analytical and quality control data as well as all raw data. The analyses include pH, OH, inductively coupled plasma spectrography, ion chromatograph, total organic carbon, total inorganic carbon, and differential scanning calorimetry. Included are copies of the chain of custody and request for special analysis forms

  1. Toxicological benchmarks for screening potential contaminants of concern for effects on terrestrial plants: 1994 revision

    International Nuclear Information System (INIS)

    Will, M.E.; Suter, G.W. II.

    1994-09-01

    One of the initial stages in ecological risk assessment for hazardous waste sites is screening contaminants to determine which of them are worthy of further consideration as contaminants of potential concern. This process is termed contaminant screening. It is performed by comparing measured ambient concentrations of chemicals to benchmark concentrations. Currently, no standard benchmark concentrations exist for assessing contaminants in soil with respect to their toxicity to plants. This report presents a standard method for deriving benchmarks for this purpose (phytotoxicity benchmarks), a set of data concerning effects of chemicals in soil or soil solution on plants, and a set of phytotoxicity benchmarks for 38 chemicals potentially associated with United States Department of Energy (DOE) sites. In addition, background information on the phytotoxicity and occurrence of the chemicals in soils is presented, and literature describing the experiments from which data were drawn for benchmark derivation is reviewed. Chemicals that are found in soil at concentrations exceeding both the phytotoxicity benchmark and the background concentration for the soil type should be considered contaminants of potential concern

  2. Toxicological benchmarks for screening potential contaminants of concern for effects on terrestrial plants: 1994 revision

    Energy Technology Data Exchange (ETDEWEB)

    Will, M.E.; Suter, G.W. II

    1994-09-01

    One of the initial stages in ecological risk assessment for hazardous waste sites is screening contaminants to determine which of them are worthy of further consideration as contaminants of potential concern. This process is termed contaminant screening. It is performed by comparing measured ambient concentrations of chemicals to benchmark concentrations. Currently, no standard benchmark concentrations exist for assessing contaminants in soil with respect to their toxicity to plants. This report presents a standard method for deriving benchmarks for this purpose (phytotoxicity benchmarks), a set of data concerning effects of chemicals in soil or soil solution on plants, and a set of phytotoxicity benchmarks for 38 chemicals potentially associated with United States Department of Energy (DOE) sites. In addition, background information on the phytotoxicity and occurrence of the chemicals in soils is presented, and literature describing the experiments from which data were drawn for benchmark derivation is reviewed. Chemicals that are found in soil at concentrations exceeding both the phytotoxicity benchmark and the background concentration for the soil type should be considered contaminants of potential concern.

  3. San Diego Multiple Species Conservation Program (MSCP) Rare Plant Monitoring Review and Revision

    Science.gov (United States)

    McEachern, Kathryn; Pavlik, Bruce M.; Rebman, Jon; Sutter, Rob

    2007-01-01

    Introduction The San Diego Multiple Species Conservation Program (MSCP) was developed for the conservation of plants and animals in the south part of San Diego County, under the California Natural Community Conservation Planning Act of 1991 (California Department of Fish and Game) and the Federal Endangered Species Act of 1973, as amended (16 U.S. Code 1531-1544.) The Program is on the leading edge of conservation, as it seeks to both guide development and conserve at-risk species with the oversight of both State and Federal agencies. Lands were identified for inclusion in the MSCP based on their value as habitat for at-risk plants or plant communities (Natural Community Conservation Planning, 2005). Since its inception in the mid-1990s the Program has protected over 100,000 acres, involving 15 jurisdictions and the U.S. Fish and Wildlife Service (USFWS) and California Department of Fish and Game (CDFG) in the conservation of 87 taxa. Surveys for covered species have been conducted, and management and monitoring have been implemented at some high priority sites. Each jurisdiction or agency manages and monitors their conservation areas independently, while collaborating regionally for long-term protection. The San Diego MSCP is on the forefront of conservation, in one of the most rapidly growing urban areas of the country. The planning effort that developed the MSCP was state-of-the-art, using expert knowledge, spatial habitat modeling, and principles of preserve design to identify and prioritize areas for protection. Land acquisition and protection are ahead of schedule for most jurisdictions. Surveys have verified the locations of many rare plant populations known from earlier collections, and they provide general information on population size and health useful for further conservation planning. Management plans have been written or are in development for most MSCP parcels under jurisdictional control. Several agencies are developing databases for implementation

  4. Data quality objectives summary report in support of Hanford Generating Plant. Revision 1

    International Nuclear Information System (INIS)

    Miller, M.S.; Marske, S.G.

    1996-09-01

    The Hanford Generating Plant (HGP) consists of two 430 MW low-pressure turbine generators and is owned by the Washington Public Power Supply System (WPPSS). Steam from the N Reactor powered the HGP turbines before passing through the turbine condenser, where waste heat was transferred to the cooling water. The DOE-RL requested that Environmental Restoration Contractor (ERC) generate a sampling and analysis plan to assist in the assessment of decontamination and decommissioning (D and D) and remediation of the HGP and 11 associated Solid Waste Management Units (SWMUs). This report summarizes the results of the Data Quality Objectives planning process as applied to HGP. The characterization data will be used to better estimate the cost for D and D and remediation. These costs will be utilized in an agreement between the Department of Energy-Richland Office (DOE-RL) and the WPSS. The agreement will define which organization will perform D and D of the HGP building, external support buildings, and remediation of buildings and soils surrounding the facility. The sampling and analysis design is presented in Section 7 with Tables 7-1 and 7-3 summarizing the design, number, location, analytes, and analytical methods to be used. The purpose of the sampling is to provide the nature and depth of contaminants. In locations where it was difficult to make assumptions related to extent, the design allows for limited characterization related to extent of contamination

  5. Options for the disposition of current inventory of Rocky Flats Plant residues. Revision 1

    International Nuclear Information System (INIS)

    Chang, L.

    1994-01-01

    With the end of the Cold War, much concern has been directed towards the accumulation of special nuclear material resulting from the dismantlement of a large number of nuclear weapons. This concern has opened up a debate over the final disposition of the large inventory of weapons-capable plutonium. Technologies for the conversion of plutonium into acceptable forms will need to be assessed and evaluated. Candidate strategies for interim and final disposition include a variety of immobilization techniques (vitrification in glass, ceramic, or metal), conversion to reactor fuel, or direct discard as waste. The selected disposition strategy will be chosen based upon a range of decision metrics such as expected conversion costs, equipment requirements, and waste generation. To this end, a systems analysis approach is necessary for the evaluation and comparison of the different disposition strategies. Current data on inventory of plutonium, such as that at the Rocky Flats Plant (RFP), may be useful for the evaluation and selection of candidate disposition technologies. A preliminary analysis of the residues of scrap at Rocky Flats was performed to establish a foundation for comparison of candidate strategies. About 3 metric tons of plutonium and 270 metric tons of other wastes remain in the inventory at Rocky Flats. Estimates on the equipment, facility, manpower, and cost requirements to process this inventory over a proposed 10-year cleanup campaign will provide a benchmark for comparison and assessment of proposed disposition technologies

  6. CAPSULE REPORT - MANAGING CYANIDE IN METAL FINISHING

    Science.gov (United States)

    The purpose of this document is to provide guidance to surface finishing manufacturers, metal finishing decision maker and regulators on management practices and control technologies for managing cyanide in the workplace. This information can benefit key industry stakeholder gro...

  7. 27 CFR 25.231 - Finished beer.

    Science.gov (United States)

    2010-04-01

    ... 27 Alcohol, Tobacco Products and Firearms 1 2010-04-01 2010-04-01 false Finished beer. 25.231... OF THE TREASURY LIQUORS BEER Beer Purchased From Another Brewer § 25.231 Finished beer. (a) A brewer may obtain beer in barrels and kegs, finished and ready for sale from another brewer. The purchasing...

  8. Proposals for a revision and amendment of the 'Guide for the examination of control room personnel of nuclear power plants, technical and expert knowledge required'

    International Nuclear Information System (INIS)

    Frisch, W.; Kersting, E.; Meissner, R.; Mester, W.; Richter, H.; Weber, J.P.

    1983-01-01

    a) Proposals are presented for amending the Guide in section 5 and 6 (Table I and II) and in the Annex (Examples of problems and answers), relating to three special subjects, namely: Thermohydraulics; Methods and procedures of analyzing the current operational state of a plant in case of incidents, malfunction failure indication; Plant operational performance and behaviour in cases exceeding design limits (especially analysis and counter-measures in case of reactor core damage, general behaviour in critical situations). b) Revision of all examples of problems to be put in examinations, and of the answers, as given in the Annex. Revision with regard to correctness and balanced distribution of difficulty of problems to be put in the various subject fields, and with regard to correctness of answers. This revision shall include an examination of the problems for their suitability to show the candidate's efficiency in diagnosis, prognosis and appropriate action. c) Proposals for amending and improving the Guide, resulting from an evaluation of the results and the experience gained in previous examinations. (orig.) [de

  9. Revision of documents guide to obtain the renovation of licence of the nuclear power plant of Laguna Verde, Units I and II

    International Nuclear Information System (INIS)

    Jarvio C, G.; Fernandez S, G.

    2008-01-01

    Unquestionably the renovation of license of the nuclear power plants , it this converting in a promising option to be able to gather in sure, reliable form and economic those requests about future energy in the countries with facilities of this type. This work it analyzes four documents guide and their application for the determination of the renovation of it licenses in nuclear plants that will serve of base for their aplication in the Nuclear Power Plant of Laguna Verde Units I and 2. The four documents in question are: the one Inform Generic of Learned Lessons on the Aging (NUREG - 1801), the Standard Revision Plan for the Renovation of License (NUREG - 1800), the Regulatory Guide for Renovation of License (GR-1.188), and the NEI 95-10, developed by the Institute of Nuclear Energy that is an Industrial Guide to Implement the Requirements of the 1OCFR Part 54-the Rule of Renovation of It licenses. (Author)

  10. 75 FR 15723 - Endangered and Threatened Wildlife and Plants; Draft Revised Recovery Plan for the Mariana Fruit...

    Science.gov (United States)

    2010-03-30

    ... Wildlife Service, announce the availability of the Draft Revised Recovery Plan for the Mariana Fruit Bat or... and assistance of a Recovery Team appointed by the U.S. Fish and Wildlife Service. Section 4(f) of the... life history and ecology, this recovery plan focuses on the first 10 years of the recovery process. As...

  11. 76 FR 38575 - Endangered and Threatened Wildlife and Plants; Revised Recovery Plan for the Northern Spotted Owl...

    Science.gov (United States)

    2011-07-01

    ... document availability: revised recovery plan. SUMMARY: We, the U.S. Fish and Wildlife Service, announce the... concluded that the integrity of the agency decisionmaking process for the spotted owl recovery plan was... DEPARTMENT OF THE INTERIOR Fish and Wildlife Service 50 CFR Part 17 [FWS-R1-ES-2011-N020; 10120...

  12. 76 FR 31906 - Endangered and Threatened Wildlife and Plants; Revising the Special Rule for the Utah Prairie Dog

    Science.gov (United States)

    2011-06-02

    ... Special Rule for the Utah Prairie Dog AGENCY: Fish and Wildlife Service, Interior. ACTION: Proposed rule... prairie dog. We are proposing to revise the existing limits on take, and we also propose a new incidental... dogs see: http://www.fws.gov/mountain-prairie/species/mammals/UTprairiedog or http://ecos.fws.gov...

  13. 76 FR 53482 - Endangered and Threatened Wildlife and Plants; Notice of Availability of a Revised Recovery Plan...

    Science.gov (United States)

    2011-08-26

    ... and revised the recovery plan accordingly. The desert tortoise is a large, herbivorous reptile that... tortoise populations. Disease and increased incidence of fire in the Mojave Desert have also been... tortoises, there are few data available to evaluate or quantify the effects of threats on desert tortoise...

  14. Surface finishing and levelling of thermomechanically hardened rolled steel

    International Nuclear Information System (INIS)

    Grosval'd, V.G.; Bashchenko, A.P.; Grishkov, A.I.; Gutnik, M.V.; Kanevskij, B.L.; Nikozov, A.I.; Sedov, N.D.; Prosin, K.A.; Safonov, L.I.

    1975-01-01

    The finishing of high-strength merchant shapes from alloy steel was tried out under industrial conditions with the equipment of metallurgical plants. After thermomechanical hardening in the production line of the rolling mill, 30KhGSN2A and 40Kh1NVA steel rounds 32 and 31 mm in diameter were straightened on a two-roller straightening machine designed by the All-Union Scientific Research Institute for Metallurgical Machinery (VNII Metmash). This made possible subsequent turning and grinding of the rods. The conditions of straightening, turning and grinding have been worked so as to obtain thermomechanically strengthened and ground rolled products approximating the gauged and ground metal in shape geometry and surface finish. It is shown that the labour-consuming operation of turning can be eliminated by reducing the machining pass of the rolled product, and this lowers the labour required for the finishing operations by 75%. After grinding with 40- and 25-grain abrasive wheels, high strength rolled shapes were obtained with a diameter of 30-0.20 mm and a surface finish of class 6-5 satisfying the technical specifications. (author)

  15. 76 FR 52355 - NUREG-1482, Revision 2, “Guidelines for Inservice Testing at Nuclear Power Plants, Draft Report...

    Science.gov (United States)

    2011-08-22

    ... Testing at Nuclear Power Plants, Draft Report for Comment'' AGENCY: Nuclear Regulatory Commission. ACTION... Testing at Nuclear Power Plants, Draft Report for Comment,'' and subtitled ``Inservice Testing of Pumps... Examination and Testing of Dynamic Restraints (Snubbers) at Nuclear Power Plants'' is available electronically...

  16. Feasibility Study for Co-Locating and Integrating Ethanol Production Plants from Corn Starch and Lignocellulosic Feedstocks (Revised)

    Energy Technology Data Exchange (ETDEWEB)

    Wallace, R.; Ibsen, K.; McAloon, A.; Yee, W.

    2005-01-01

    Analysis of the feasibility of co-locating corn-grain-to-ethanol and lignocellulosic ethanol plants and potential savings from combining utilities, ethanol purification, product processing, and fermentation. Although none of the scenarios identified could produce ethanol at lower cost than a straight grain ethanol plant, several were lower cost than a straight cellulosic ethanol plant.

  17. Status of the revision of the 88/609 directive on the reduction of air pollutant emissions from large burning plants; Le point sur la revision de la Directive 88/609 relative a la reduction des emissions polluantes dans l`atmosphere, en provenance des grandes installations de combustion (GIC)

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-12-31

    The present European 88/609 directive, which applies to burning plants with a capacity of more than 50 MW (i.e. mainly power plant boilers and industrial energy production plants), is presented; different emission level limits are fixed for new and old plants, for the three main air pollutants (sulfur dioxide, nitrogen oxides and dust). Results on emission pollution levels in 1990, following the 1988 directive are presented. Several revisions drafts have been studied, which included gas turbines, and the end of the separation between old and new plants

  18. 7 CFR 29.2518 - Finish.

    Science.gov (United States)

    2010-01-01

    ...-Cured Tobacco (u.s. Types 22, 23, and Foreign Type 96) § 29.2518 Finish. The reflectance factor in color perception. Finish indicates the sheen or shine of the surface of a tobacco leaf. (See chart, § 29.2601.) ...

  19. Finishability of CCA pressure-treated wood

    Science.gov (United States)

    Alan Ross; Richard Carlson; William Feist; Steven Bussjaeger

    2000-01-01

    Thus, a need arose for the development of surface finishes for CCA-treated wood that could address the special requirements of this substrate and provide protection against the ravages of water, sunlight, mildew, and other aspects of weathering and wear. Initially, this need was not addressed, most wood preserving companies had little expertise in surface finishes and...

  20. Project C-018H, 242-A Evaporator/PUREX Plant Process Condensate Treatment Facility, functional design criteria. Revision 3

    International Nuclear Information System (INIS)

    Sullivan, N.

    1995-01-01

    This document provides the Functional Design Criteria (FDC) for Project C-018H, the 242-A Evaporator and Plutonium-Uranium Extraction (PUREX) Plant Condensate Treatment Facility (Also referred to as the 200 Area Effluent Treatment Facility [ETF]). The project will provide the facilities to treat and dispose of the 242-A Evaporator process condensate (PC), the Plutonium-Uranium Extraction (PUREX) Plant process condensate (PDD), and the PUREX Plant ammonia scrubber distillate (ASD)

  1. 75 FR 1574 - Endangered and Threatened Wildlife and Plants; 12-month Finding on a Petition To Revise Critical...

    Science.gov (United States)

    2010-01-12

    ... been scheduled for, or are in the process of developing, minimum flow regulations. Those requirements... can be eliminated due to plant obsolescence, environmental permitting requirements, economic pressures...

  2. FON: From Start to Finish

    Science.gov (United States)

    Pakuliak, L. K.; Andruk, V. M.; Golovnia, V. V.; Shatokhina, S. V.; Yizhakevych, O. M.; Ivanov, G. A.; Yatsenko, A. I.; Sergeeva, T. P.

    Almost 40-year history of FON project ended with the creation of the whole northern sky catalog of objects down to B ≤ 16.5m. The idea of 4-fold overlapping of the northern sky with 6 wide-field astrographs has not been realized in full. For historical reasons it has been transformed into the 2-fold overlapping observational program of MAO NAS of Ukraine, resulted in three versions of the multimillion catalog of positions, proper motions, and B-magnitudes of stars. The first version of 1.2 million stars had been finished before the 2000s and is based on the AC object list. The measurements of plates were made by automatic measuring complex PARSEC, specially developed for massive photographic reviews. As the input list was limited by AC objects, the most part of stars on the FON plates remained unmeasured. Principles of workflow organization of such works formed the basis for the further development of the project using the latest IT-technologies. For the creation of the second and the third versions of the catalog, the list of objects was obtained as a result of total digitizing of plates and their image processing. The final third version contains 19.5 million stars and galaxies with the maximum possible for the photographic astrometry accuracy. The collection of plates, obtained in other observatories - participants of the project, are partially safe and can be used for the same astrometric tasks.

  3. Revising Translations

    DEFF Research Database (Denmark)

    Rasmussen, Kirsten Wølch; Schjoldager, Anne

    2011-01-01

    The paper explains the theoretical background and findings of an empirical study of revision policies, using Denmark as a case in point. After an overview of important definitions, types and parameters, the paper explains the methods and data gathered from a questionnaire survey and an interview...... survey. Results clearly show that most translation companies regard both unilingual and comparative revisions as essential components of professional quality assurance. Data indicate that revision is rarely fully comparative, as the preferred procedure seems to be a unilingual revision followed by a more...... or less comparative rereading. Though questionnaire data seem to indicate that translation companies use linguistic correctness and presentation as the only revision parameters, interview data reveal that textual and communicative aspects are also considered. Generally speaking, revision is not carried...

  4. Outfall 51 air stripping feasibility study for the Reduction of Mercury in Plant Effluent (RMPE) Project. Revision 1

    International Nuclear Information System (INIS)

    1997-01-01

    Within the US Department of Energy's Oak Ridge Y-12 Plant there are a number of industrial wastewater discharge points or outfalls that empty into East Fork Poplar Creek (EFPC). EFPC originates within and runs continuously throughout the plant site and subsequently flows out the east end of the Y-12 Plant into the City of Oak Ridge. Mercury is present in outfall discharges due to contact of water with the soils surrounding past mercury-use buildings. As a result, the Reduction of Mercury in Plant Effluent (RMPE) Project was developed to achieve and maintain environmental compliance with regards to mercury, and, in particular with the National Pollutant Discharge Elimination System permit for the Y-12 Plant. To achieve a reduction in mercury loading to EFPC, a number of options have already been studied and implemented as part of the RMPE project. With the successful implementation of these options, Outfall 51 remains as a significant contributor to mercury load to EFPC. The primary purpose of this project is to determine the feasibility of removing mercury from contaminated spring water using air stripping. In order to accomplish this goal, a number of different areas were addressed. A pilot-scale unit was tested in the field using actual mercury-contaminated source water. Properties which impact the mercury removal via air stripping were reviewed to determine their effect. Also, enhanced testing was performed to improve removal efficiencies. Finally, the variable outfall flow was studied to size appropriate processing equipment for full-scale treatment

  5. The Adolescent Who Does Not Finish Anything.

    Science.gov (United States)

    Breiner, Sander J.

    1985-01-01

    Practical information for therapists who deal with adolescents who do not finish tasks is presented. The relationship of task incompletion to neurosis, psychosis, depression, homosexuality, and drug abuse is described, and techniques and guidelines for treatment are provided. (Author)

  6. Surface Finish after Laser Metal Deposition

    Science.gov (United States)

    Rombouts, M.; Maes, G.; Hendrix, W.; Delarbre, E.; Motmans, F.

    Laser metal deposition (LMD) is an additive manufacturing technology for the fabrication of metal parts through layerwise deposition and laser induced melting of metal powder. The poor surface finish presents a major limitation in LMD. This study focuses on the effects of surface inclination angle and strategies to improve the surface finish of LMD components. A substantial improvement in surface quality of both the side and top surfaces has been obtained by laser remelting after powder deposition.

  7. Radiological and chemical characterization report for the planned Quarry Construction Staging Area and Water Treatment Plant: Revision 1

    International Nuclear Information System (INIS)

    1989-03-01

    The Quarry Construction Staging Area and Water Treatment Plant (QCSA) will be used in the support of the bulk waste removal of the Weldon Spring Quarry. Radiological and chemical characterization was performed on a 12 acre site where the QCSA will be constructed. The characterization revealed approximately .5 acres of radiologically contaminated land. No chemical contamination was found. 8 refs., 5 figs., 7 tabs

  8. Resource Conservation and Recovery Act, Part B permit application [for the Waste Isolation Pilot Plant (WIPP)]. Volume 1, Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    1993-03-01

    This volume includes the following chapters: Waste Isolation Pilot Plant RCRA A permit application; facility description; waste analysis plan; groundwater monitoring; procedures to prevent hazards; RCRA contingency plan; personnel training; corrective action for solid waste management units; and other Federal laws.

  9. 10-MWe solar-thermal central-receiver pilot plant: collector subsystem foundation construction. Revision No. 1

    Energy Technology Data Exchange (ETDEWEB)

    1979-12-18

    Bid documents are provided for the construction of the collector subsystem foundation of the Barstow Solar Pilot Plant, including invitation to bid, bid form, representations and certifications, construction contract, and labor standards provisions of the Davis-Bacon Act. Instructions to bidders, general provisions and general conditions are included. Technical specifications are provided for the construction. (LEW)

  10. Resource Conservation and Recovery Act, Part B Permit Application [for the Waste Isolation Pilot Plant (WIPP)]. Volume 5, Chapter D, Appendix D1 (conclusion), Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    Cook, Neville G.W.; Heuze, Francois E.; Miller, Hamish D.S.; Thoms, Robert L.

    1993-03-01

    The reference design for the underground facilities at the Waste Isolation Pilot Plant was developed using the best criteria available at initiation of the detailed design effort. These design criteria are contained in the US Department of Energy document titled Design Criteria, Waste Isolation Pilot Plant (WIPP). Revised Mission Concept-IIA (RMC-IIA), Rev. 4, dated February 1984. The validation process described in the Design Validation Final Report has resulted in validation of the reference design of the underground openings based on these criteria. Future changes may necessitate modification of the Design Criteria document and/or the reference design. Validation of the reference design as presented in this report permits the consideration of future design or design criteria modifications necessitated by these changes or by experience gained at the WIPP. Any future modifications to the design criteria and/or the reference design will be governed by a DOE Standard Operation Procedure (SOP) covering underground design changes. This procedure will explain the process to be followed in describing, evaluating and approving the change.

  11. Carbon allocation, source-sink relations and plant growth: do we need to revise our carbon centric concepts?

    Science.gov (United States)

    Körner, Christian

    2014-05-01

    Since the discovery that plants 'eat air' 215 years ago, carbon supply was considered the largely unquestioned top driver of plant growth. The ease at which CO2 uptake (C source activity) can be measured, and the elegant algorithms that describe the responses of photosynthesis to light, temperature and CO2 concentration, explain why carbon driven growth and productivity became the starting point of all process based vegetation models. Most of these models, nowadays adopt other environmental drivers, such as nutrient availability, as modulating co-controls, but the carbon priority is retained. Yet, if we believe in the basic rules of stoichometry of all life, there is an inevitable need of 25-30 elements other then carbon, oxygen and hydrogen to build a healthy plant body. Plants compete for most of these elements, and their availability (except for N) is finite per unit land area. Hence, by pure plausibility, it is a highly unlikely situation that carbon plays the rate limiting role of growth under natural conditions, except in deep shade or on exceptionally fertile soils. Furthermore, water shortage and low temperature, both act directly upon tissue formation (meristems) long before photosynthetic limitations come into play. Hence, plants will incorporate C only to the extent other environmental drivers permit. In the case of nutrients and mature ecosystems, this sink control of plant growth may be masked in the short term by a tight, almost closed nutrient cycle or by widening the C to other element ratio. Because source and sink activity must match in the long term, it is not possible to identify the hierarchy of growth controls without manipulating the environment. Dry matter allocation to C rich structures and reserves may provide some stoichimetric leeway or periodic escapes from the more fundamental, long-term environmental controls of growth and productivity. I will explain why carbon centric explanations of growth are limited or arrive at plausible answers

  12. Finishing procedures action on mechanical characteristics of pressed ceramics

    Directory of Open Access Journals (Sweden)

    Mohamed Abdel Moniem Ahmed

    2018-06-01

    Conclusions& significance: Grinding & finishing procedures of pressed ceramics showed significant effect Of drill speed and polishing technique over flexural strength, As Grinding with no finishing and polishing procedure showed lowest flexural Strength values followed by finishing and polishing procedure followed by finishing and polishing with polishing paste procedure.

  13. An atomic-scale and high efficiency finishing method of zirconia ceramics by using magnetorheological finishing

    Science.gov (United States)

    Luo, Hu; Guo, Meijian; Yin, Shaohui; Chen, Fengjun; Huang, Shuai; Lu, Ange; Guo, Yuanfan

    2018-06-01

    Zirconia ceramics is a valuable crucial material for fabricating functional components applied in aerospace, biology, precision machinery, military industry and other fields. However, the properties of its high brittleness and high hardness could seriously reduce its finishing efficiency and surface quality by conventional processing technology. In this work, we present a high efficiency and high-quality finishing process by using magnetorheological finishing (MRF), which employs the permanent magnetic yoke with straight air gap as excitation unit. The sub-nanoscale surface roughness and damage free surface can be obtained after magnetorheological finishing. The XRD results and SEM morphologies confirmed that the mechanical shear removal with ductile modes are the dominant material removal mechanism for the magnetorheological finishing of zirconia ceramic. With the developed experimental apparatus, the effects of workpiece speed, trough speed and work gap on material removal rate and surface roughness were systematically investigated. Zirconia ceramics finished to ultra-smooth surface with surface roughness less than Ra 1 nm was repeatedly achieved during the parametric experiments. Additionally, the highest material removal rate exceeded 1 mg/min when using diamond as an abrasive particle. Magnetorheological finishing promises to be an adaptable and efficient method for zirconia ceramics finishing.

  14. Glazed Tiles as Floor Finish in Nigeria

    Directory of Open Access Journals (Sweden)

    Toyin Emmanuel AKINDE

    2013-09-01

    Full Text Available Tile is no doubt rich in antiquity; its primordial  show, came as mosaic with primary prospect in sacred floor finish before its oblivion, courtesy of, later consciousness towards wall finish in banquets, kitchens, toilets, restaurants and even bars. Today, its renaissance as floor finish is apparent in private and public architectural structures with prevalence in residential, recreational, commercial, governmental and other spaces. In Nigeria, the use of glazed tiles as floor finish became apparent, supposedly in mid-twentieth century; and has since, witnessed ever increasing demands from all sundry; a development that is nascent and has necessitated its mass  production locally with pockets of firms in the country. The latter however, is a resultant response to taste cum glazed tiles affordability, whose divergent sophistication in design, colour, size and shape is believed preferred to terrazzo, carpet and floor flex tile. Accessible as glazed tile and production is, in recent times; its dearth of a holistic literature in Nigeria is obvious. In the light of the latter, this paper examine glazed tiles as floor finish in Nigeria, its advent, usage, production, challenge, benefit and prospect with the hope of opening further frontier in discipline specifics.

  15. Demonstration of acid and water recovery systems: Applicability and operational challenges in Indian metal finishing SMEs.

    Science.gov (United States)

    Balakrishnan, M; Batra, R; Batra, V S; Chandramouli, G; Choudhury, D; Hälbig, T; Ivashechkin, P; Jain, J; Mandava, K; Mense, N; Nehra, V; Rögener, F; Sartor, M; Singh, V; Srinivasan, M R; Tewari, P K

    2018-07-01

    Diffusion dialysis, acid retardation and nanofiltration plants were acquired from Europe and demonstrated in several Indian metal finishing companies over a three year period. These companies are primarily small and medium enterprises (SMEs). Free acid recovery rate from spent pickling baths using diffusion dialysis and retardation was in the range of 78-86% and 30-70% respectively. With nanofiltration, 80% recovery rate of rinse water was obtained. The demonstrations created awareness among the metal finishing companies to reuse resources (acid/water) from the effluent streams. However, lack of efficient oil separators, reliable chemical analysis and trained personnel as well as high investment cost limit the application of these technologies. Local manufacturing, plant customization and centralized treatment are likely to encourage the uptake of such technologies in the Indian metal finishing sector. Copyright © 2018 Elsevier Ltd. All rights reserved.

  16. Finishing of the cold mass assembly

    CERN Multimedia

    Patrice Loïez

    2001-01-01

    Photo 1 Technicians are putting in order the instrumentation wires. The prototype magnets were equipped with numerous sensors to monitor key parameters during the performance tests at cold conditions. Photo 2 The cold mass assembly is resting on special supports in order to allow the finishing operations. Technicians are putting in order the instrumentation wires. The prototype magnets were equipped with numerous sensors to monitor key parameters during the performance tests at cold conditions. Photo 3 View of the lyre-side end of the active part assembly. The extremity of the shrinking cylinder has been bevelled in view of welding the end cover. Photo 4 General view of the finishing station showing the special supporting structures (blue and yellow structures) needed for the geometric measurements and for the alignment operations. One can also see the light building surrounding the finishing station, which purpose is to isolate the laser measuring machines from disturbances. Photo 5 The extremity of the shri...

  17. Establishing Trailer Ventilation (Boarding) Requirements for Finishing Pigs during Transport.

    Science.gov (United States)

    McGlone, John; Sapkota, Avi; Johnson, Anna; Kephart, Rebecca

    2014-08-19

    Specifically, this study aimed to establish the effects on mortality and morbidity of boarding levels (amount of side-wall trailer ventilation) for finishing pigs in mild weather (8.80 ± 0.30 °C, 71.70% ± 1.12% humidity). Pigs from commercial finishing sites were transported in 302 pot-bellied trailers to commercial processing plants. Measures collected at the processing plant were rates of dead on arrival (DOA), non-ambulatory, non-injured (NANI), non-ambulatory, injured (NAI), and total dead and down (D&D). Boarding levels (% that side walls were closed off with inserted boards) were divided into 3 bins: low, medium, and high, and outside temperature was divided into 4 bins 15 °C. Average rates of DOA, NANI, NAI, and D&D were approximately 0.30%, 0.12%, 0.04%, and 0.46%, respectively. The D&D was highest when boarding level was low with temperatures boarding level (medium and high boarding) in the temperature range of 5.10 °C to 23.30 °C did not affect pig losses.

  18. Manpower development for safe operation of nuclear power plant. China. Revision of final safety analysis report. Activity: 5.1.3-Task-08. Technical report

    International Nuclear Information System (INIS)

    Almeida, C.; Elias, D.

    1994-01-01

    The objectives of this mission included providing assistance for the revision of the FSAR including: national practices, administrative procedures, required staffing level, other resources, planning, scheduling, content, and organization of the revision. Activities included several days of lectures regarding worldwide practices including the United States and Commonwealth Edison Company (ComEd), interaction with Chinese counterparts re. their FSAR and Technical Specification revision and two visits to the Qin Shan NPP

  19. A Revised Similarity Law in Botanic Describes the Genesis of the Vulnerability Curve Shape in Vascular Plants

    Science.gov (United States)

    Mrad, A.; Domec, J. C.; Huang, C. W.; Katul, G. G.

    2017-12-01

    Xylem tissues are specialized in offering the least possible resistance to water flow. However, this is not guaranteed when ascending sap reaches large negative pressures during periods of water stress when embolism within the xylem occurs, an inevitable step toward potential drought-induced mortality. Ongoing research into changing forest patterns and plant survival due to droughts rarely dispute the significance of Vulnerability Curves (VCs), plots that feature loss in relative conductance with declining liquid pressure (ψ). While Earth-Systems models routinely employ various VC functions, the theoretical underpinnings describing their shape remains lacking. VCs are the outcome of microscopic phenomena describing embolism formation, bubble-scale xylem properties allowing embolism spread, and hydraulic processes that dictate the water potential along the flow path. The work here explores how the upscaled version of these gives rise to popular mathematical shapes used to describe VC measurements: The Logistic and Weibull exceedance equations. Each of these two captures a distinct type of embolism spread: The Logistic VC arises when the probability that embolized vessels interact with intact ones describe embolism spread as water pressure decreases (labeled as a similarity law in botanic [1]). The Weibull VC arises when the aforementioned description includes the effects of ψ explicitly. Variability in xylem properties along the flow path is explored analytically using novel approaches borrowed from `super-statistics' and numerical simulations. The numerical simulations intend to single out which xylem network property is significant in describing the VC shape. The model results corroborate previous research (experimental and 3-dimensional high-resolution simulations) on the effect of vessel size and network topology. It is shown that (i) initial embolism locations alter air-seeding pressure and VC slope; (ii) redundancy and size variations decrease bubble

  20. Revision of Viable Environmental Monitoring in a Development Pilot Plant Based on Quality Risk Assessment: A Case Study.

    Science.gov (United States)

    Ziegler, Ildikó; Borbély-Jakab, Judit; Sugó, Lilla; Kovács, Réka J

    2017-01-01

    In this case study, the principles of quality risk management were applied to review sampling points and monitoring frequencies in the hormonal tableting unit of a formulation development pilot plant. In the cleanroom area, premises of different functions are located. Therefore a general method was established for risk evaluation based on the Hazard Analysis and Critical Control Points (HACCP) method to evaluate these premises (i.e., production area itself and ancillary clean areas) from the point of view of microbial load and state in order to observe whether the existing monitoring program met the emerged advanced monitoring practice. LAY ABSTRACT: In pharmaceutical production, cleanrooms are needed for the manufacturing of final dosage forms of drugs-intended for human or veterinary use-in order to protect the patient's weakened body from further infections. Cleanrooms are premises with a controlled level of contamination that is specified by the number of particles per cubic meter at a specified particle size or number of microorganisms (i.e. microbial count) per surface area. To ensure a low microbial count over time, microorganisms are detected and counted by environmental monitoring methods regularly. It is reasonable to find the easily infected places by risk analysis to make sure the obtained results really represent the state of the whole room. This paper presents a risk analysis method for the optimization of environmental monitoring and verification of the suitability of the method. © PDA, Inc. 2017.

  1. Pneumonia outbreaks in calves and finishers.

    Science.gov (United States)

    2016-03-19

    Pneumonia in calves and finishers. Ovarian tumour in a calf . Abortion associated with bovine herpesvirus 1 in a suckler herd. Parasitic gastroenteritis causing illthrift and death in sheep. Outbreaks of acute fasciolosis in sheep. These are among matters discussed in the disease surveillance report for December 2015 from SAC Consulting: Veterinary Services (SAC C VS). British Veterinary Association.

  2. Processing and finishing of granite surfaces

    OpenAIRE

    Klich, J. (Jiří); Hlaváček, P. (Petr); Ščučka, J. (Jiří); Sitek, L. (Libor); Foldyna, J. (Josef); Georgiovská, L. (Lucie); Souček, K. (Kamil); Staš, L. (Lubomír); Bortolussi, A.

    2013-01-01

    The article deals with granite surface processing and finishing by various methods including bush hammering, flaming, polishing, continuous and pulsating water jetting. Both optical and CT X-ray methods are used for analysis of surface and subsurface areas of tested samples. Advantages of pulsating water jetting compared to other techniques are discussed.

  3. Explosion hazards of aluminum finishing operations

    NARCIS (Netherlands)

    Taveau, J.R.; Hochgreb, Simone; Lemkowitz, S.M.; Roekaerts, D.J.E.M.

    2018-01-01

    Metal dust deflagrations have become increasingly common in recent years. They are also more devastating than deflagrations involving organic materials, owing to metals' higher heat of combustion, rate of pressure rise, explosion pressure and flame temperature. Aluminum finishing operations offer

  4. Explosion hazards of aluminum finishing operations

    NARCIS (Netherlands)

    Taveau, J.; Hochgreb, S.; Lemkowitz, S.M.; Roekaerts, D.J.E.M.

    2018-01-01

    Metal dust deflagrations have become increasingly common in recent years. They are also more devastating than deflagrations involving organic materials, owing to metals' higher heat of combustion, rate of pressure rise, explosion pressure and flame temperature. Aluminum finishing operations offer a

  5. On the improving of finishing works

    International Nuclear Information System (INIS)

    Arzamaskov, V.N.; Bondarenko, I.Ya.; Pogozhev, I.M.

    1986-01-01

    Problems of the improvement of finishing works performed during the construction of power installations are considered. Recommendations on the improvement of the quality of these works, increase of labour productivity and decrease of a manual labour share on their implementation are given

  6. Corrosion protection and finishing of automobiles

    International Nuclear Information System (INIS)

    Sheikh, S.T.

    2005-01-01

    finishing of automobiles is an important aspect. There have been considerable reductions of weight in automobiles by the use of composites components replacing heavy metallic components. Fenders previously based on metal have been replaced with plastic and painted with the same colour shade as of the metallic body, this has eps for proper adhesion of the paints on the plastic fender to avoid chipping off the paint form it. This paper discusses the necessary processes required for finishing of an automobile along with the corrosion protection measures. Automobiles contains a variety of engineering materials, engine main body fuel tanks connecting rods heat radiators and other mechanical parts are made from different types of engineering alloys having varying chemical compositions. Other parts like dashboard, front panel and other are made from composites. The main body made from cold roll ed steel having various contours 'c' it due to the different designs is the potential site for corrosion attack, The main body is exposed to the hostile environment through out its life period. An automobile is given a particular finish with a view to counter the hostile environments as they are not limited for plying in a limiting conditions and are taken to different weather conditions in one day thus facing severe stresses and strain. Thus it is essential that an automobile before rolling 'out of the assembly line should properly corrosion resistant and aesthetically pleasant also. Finishing for automobiles being very specialized, the main requirement being maximum durability with minimum numbers of coats baked, at the fastest possible schedule. High gloss and range of good eye catching colours being important to increase sales appeal. In the near past the car finishes were based on alkyd-amino resins baking materials and force drying lacquers, which have excellent appearance originally and maintain it on aging. The finishing system for the synthetic baking type may consist of

  7. Economics of finishing Tanzania Shorthorn Zebu cattle in feedlot and optimum finishing period

    DEFF Research Database (Denmark)

    Asimwe, L.; Kimambo, A E; Laswai, G. H.

    2016-01-01

    finishing for TSZ cattle. The biological data collected from the two experiments were used as basis for deriving the economic scenarios. The range of days steers were kept in feedlot was set at 0, 25, 50, 75 and 100 days. The dietary metabolisable energy intake (MEI) levels used in the study were 55 MJ......Economic potential of finishing Tanzania Shorthorn Zebu (TSZ) cattle in feedlot was analysed using data obtained from two feedlot experiments carried out at Kongwa ranch in Tanzania. The experiments were performed to evaluate the effects of feeding agro-processing by products and length of feedlot...... length of 25 days, higher profit per animal carcass was realized with long stays (100 days, 238,000 TSh.) than short stays (25 days, 37,600 TSh.). It was concluded that the high feeding level is the most profitable irrespective of meat price and finishing length. The optimum finishing length is between...

  8. Experimental investigation on shore hardness of barrel-finished ...

    Indian Academy of Sciences (India)

    Rupinder Singh

    2017-08-02

    Aug 2, 2017 ... Barrel finishing (BF) process is widely used to improve the surface finish and dimensional features of metallic and ... plastic-based waste can be easily recycled. However .... The pattern prepared with solid density has a dense.

  9. Sequence finishing and mapping of Drosophila melanogasterheterochromatin

    Energy Technology Data Exchange (ETDEWEB)

    Hoskins, Roger A.; Carlson, Joseph W.; Kennedy, Cameron; Acevedo,David; Evans-Holm, Martha; Frise, Erwin; Wan, Kenneth H.; Park, Soo; Mendez-Lago, Maria; Rossi, Fabrizio; Villasante, Alfredo; Dimitri,Patrizio; Karpen, Gary H.; Celniker, Susan E.

    2007-06-15

    Genome sequences for most metazoans are incomplete due tothe presence of repeated DNA in the pericentromeric heterochromatin. Theheterochromatic regions of D. melanogaster contain 20 Mb of sequenceamenable to mapping, sequence assembly and finishing. Here we describethe generation of 15 Mb of finished or improved heterochromatic sequenceusing available clone resources and assembly and mapping methods. We alsoconstructed a BAC-based physical map that spans approximately 13 Mb ofthe pericentromeric heterochromatin, and a cytogenetic map that positionsapproximately 11 Mb of BAC contigs and sequence scaffolds in specificchromosomal locations. The integrated sequence assembly and maps greatlyimprove our understanding of the structure and composition of this poorlyunderstood fraction of a metazoan genome and provide a framework forfunctional analyses.

  10. Clear exterior finishes : finding the balance between aesthetics and durability

    Science.gov (United States)

    Tom Daniel; Marc S. Hirsch; Ken McClelland; Alan S. Ross; R. Sam Williams

    2004-01-01

    Consumers can easily be confused by the abundance of choices to make when selecting a clear wood finish. There are many types of clear finishes with different characteristics and product claims. This article is designed to help consumers sort out the different finishes and effectively choose which product would be best for their purpose. First, we cover the causes and...

  11. Lathe Attachment Finishes Inner Surface of Tubes

    Science.gov (United States)

    Lancki, A. J.

    1982-01-01

    Extremely smooth finishes are machined on inside surfaces of tubes by new attachment for a lathe. The relatively inexpensive accessory, called a "microhone," holds a honing stone against workpiece by rigid tangs instead of springs as in conventional honing tools. Inner rod permits adjustment of microhoning stone, while outer tube supports assembly. Outer tube is held between split blocks on lathe toolpost. Microhoning can be done with either microhone or workpiece moving and other member stationary.

  12. Nearly Finished Genomes Produced Using Gel Microdroplet Culturing (Seventh Annual Sequencing, Finishing, Analysis in the Future (SFAF) Meeting 2012)

    Energy Technology Data Exchange (ETDEWEB)

    Fitzsimmons, Michael

    2012-06-01

    Michael Fitzsimmons from Los Alamos National Laboratory gives a talk titled "Nearly Finished Genomes Produced Using Gel Microdroplet Culturing" at the 7th Annual Sequencing, Finishing, Analysis in the Future (SFAF) Meeting held in June, 2012 in Santa Fe, NM.

  13. Revision of documents guide to obtain the renovation of licence of the nuclear power plant of Laguna Verde, Units I and II; Revision de documentos guia para obtener la renovacion de licencia de la Central Nuclear Laguna Verde Unidades 1 and 2

    Energy Technology Data Exchange (ETDEWEB)

    Jarvio C, G. [ININ 52750 La Marquesa, Estado de Mexico (Mexico); Fernandez S, G. [CFE, Gerencia de Centrales Nucleoelectricas, Subgerencia de Ingenieria, Carretera Veracruz-Medellin s/n (Km. 7.5), Dos Bocas, 54270 Veracruz (Mexico)]. e-mail: giarvio@yahoo.com.mx

    2008-07-01

    Unquestionably the renovation of license of the nuclear power plants , it this converting in a promising option to be able to gather in sure, reliable form and economic those requests about future energy in the countries with facilities of this type. This work it analyzes four documents guide and their application for the determination of the renovation of it licenses in nuclear plants that will serve of base for their aplication in the Nuclear Power Plant of Laguna Verde Units I and 2. The four documents in question are: the one Inform Generic of Learned Lessons on the Aging (NUREG - 1801), the Standard Revision Plan for the Renovation of License (NUREG - 1800), the Regulatory Guide for Renovation of License (GR-1.188), and the NEI 95-10, developed by the Institute of Nuclear Energy that is an Industrial Guide to Implement the Requirements of the 1OCFR Part 54-the Rule of Renovation of It licenses. (Author)

  14. Population dynamics of swine influenza virus in farrow-to-finish and specialised finishing herds in the Netherlands

    NARCIS (Netherlands)

    Loeffen, W.L.A.; Hunneman, W.A.; Quak, J.; Verheijden, J.H.M.; Stegeman, J.A.

    2009-01-01

    Influenza virus infections with subtypes H1N1, H3N2 and H1N2 are very common in domestic pigs in Europe. Data on possible differences of population dynamics in finishing pigs in farrow-to-finish herds and in specialised finishing herds are, however, scarce. The presence of sows and weaned piglets on

  15. Best of both worlds : clear exterior finishes : in search of finishes that protect wood without hiding its natural beauty

    Science.gov (United States)

    Tom Daniels; Marc Hirsch; Ken McClelland; Alan Ross; Sam Williams

    2000-01-01

    In recent years, a number of clear wood finishes have been developed that protect wood while accentuating its natural beauty. The focus of this publication is on those finishes having little visible pigment. In some cases, the pigments are included but are finely ground to create a coating that is transparent to visible light. Most natural clear wood finishes are...

  16. Revision of species of Minerisporites, Azolla and associated plant microfossils from deposits of the Upper Palaeocene and Palaeocene/Eocene transition in the Netherlands, Belgium and the USA.

    Science.gov (United States)

    Batten, D J.; Collinson, M E.

    2001-05-01

    Species of the megaspore genus Minerisporites Potonié, megaspore apparatuses of species of the water fern Azolla Lamarck, and some associated organic-walled microfossils recovered from deposits of the Upper Palaeocene and Palaeocene/Eocene transition in the southern part of the Netherlands and neighbouring Belgium are redescribed on the basis of an examination of specimens under scanning and transmission electron microscopes. Originally studied about 40 years ago by S.J. Dijkstra, the re-examination has enabled emended diagnoses to be produced for six taxa: Minerisporites glossoferus (Dijkstra) Tschudy, M. mirabilis (Miner) Potonié, M. mirabilissimus (Dijkstra) Potonié, Azolla schopfii Dijkstra, A. teschiana Florschütz, and A. velus (Dijkstra) Jain and Hall. In addition, a revised description is provided for massulae of Salvinia Séguier that were originally thought to be megaspores and, hence, named by Dijkstra as Triletes? exiguus. The gross morphology and construction of the exospore of the species of Minerisporites are similar, but nevertheless sufficiently distinct for them to be maintained as separate taxa. Monolete microspores are preserved in hollows in the reticulate surface of some of the specimens of M. mirabilissimus. This is consistent with the presumed isoetalean affinity of Minerisporites. An apparent stratigraphic morphocline from M. glossoferus to M. mirabilis, suggested previously, is confirmed following our reassessment of their characteristics. The species of Azolla are all multi-floated, but they differ from each other in several ways, in particular with respect to the ultrastructure of the megaspore wall. They are also distinct from all other species that have been considered in sufficient detail for satisfactory comparisons to be made. The massulae of A. teschiana are described for the first time. The floats in A. velus are attached to the proximal part of the megaspore only by suprafilosal hairs. There are no maniculae. It is argued that

  17. New and revised standards for coke production

    Energy Technology Data Exchange (ETDEWEB)

    G.A. Kotsyuba; M.I. Alpatov; Y.G. Shapoval [Giprokoks, the State Institute for the Design of Coke-Industry Enterprises, Kharkov (Ukraine)

    2009-07-15

    The need for new and revised standards for coke production in Ukraine and Russia is outlined. Such standards should address improvements in plant operation, working conditions, environmental protection, energy conservation, fire and explosion safety, and economic indices.

  18. FFTF operations procedures preparation guide. Revision 2

    International Nuclear Information System (INIS)

    1976-12-01

    The Guide is intended to provide guidelines for the initial preparation of FFTF Operating Procedures. The Procedures Preparation Guide was developed from the plan presented and approved in the FFTF Reactor Plant Procedures Plan, PC-1, Revision 3

  19. Facility Effluent Monitoring Plan for the Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    FRAZIER, T.P.

    1999-01-01

    A facility effluent monitoring plan is required by the U. S. Department of Energy in DOE Order 5400.1 for any operations that involve hazardous materials and radioactive substances that could impact employee or public safety or the environment. This facility effluent monitoring plan assesses effluent monitoring systems and evaluates whether these systems are adequate to ensure the public health and safety as specified in applicable federal, state, and local requirements. To ensure the long-range integrity of the effluent monitoring systems, an update to this facility effluent monitoring plan is required whenever a new process or operation introduces new hazardous materials or significant radioactive materials. This document is reviewed annually even if there are no operational changes, and is updated, at a minimum, every 3 years

  20. Plutonium Finishing Plant transition project function analysis report

    International Nuclear Information System (INIS)

    Lund, D.P.

    1995-09-01

    The document contains the functions, function definitions, function interfaces, function interface definitions, Input Computer Automated Manufacturing Definition (IDEFO) diagrams, and function hierarchy charts that describe what needs to be performed to deactivate PFP and to continue safe storage, treatment and disposition of Plutonium and High Enriched Uranium

  1. Acceptance test report, plutonium finishing plant life safety upgrade

    International Nuclear Information System (INIS)

    Hodge, S.G.

    1994-01-01

    This acceptance Test Procedure (ATP) has been prepared to demonstrate that modifications to the Fir Protection systems function as required by project criteria. The ATP will test the Fire Alarm Control Panels, Flow Alarm Pressure Switch, Heat Detectors, Smoke Detectors, Flow Switches, Manual Pull Stations, and Gong/Door By Pass Switches

  2. Thecomposition of semi finished inventories at a solid board plant

    NARCIS (Netherlands)

    Wanders, Henrico L.T.; Gaalman, Gerard J.C.; Sierksma, Gerard

    2001-01-01

    A solid board factory produces rectangular sheets of cardboard in two different formats, namely large formats and small formats. The production process consists of two stages separated by an inventory point. In the first stage a cardboard machine produces the large formats. In the second stage a

  3. Plutonium Finishing Plant (PFP) HVAC System Component Index; FINAL

    International Nuclear Information System (INIS)

    DICK, J.D.

    1999-01-01

    This document identities the components, design media, procedures and defines the critical characteristics of Commercial Grade Items necessary to ensure the HVAC system provides these functions. This document lists safety class (SC) and safety significant (SS) components for the Heating Ventilation Air Conditioning (HVAC) and specifies the critical characteristics for Commercial Grade Items (CGI), as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics for any one item

  4. [Experimental analysis of finishing lines in ceramometal restorations].

    Science.gov (United States)

    Gascón, F; Gil, J A; Fons, A; Badal, R

    1990-11-01

    The preparation is the first step of any tooth reconstruction. The biological integration of the protesis is depending on the marginal adaptation (finish line of the preparation), occlusal adaptation (occlusal reduction), longevity of the restoration (retention and luting) and esthetics. The effect the two finish line of the preparation is studied using experimental design. In porcelain-fused-to-metal the finish line of the preparation in chanfer is superior at the beveled shoulder, because proportioning better marginal adaptation.

  5. Occurrence of neonicotinoid insecticides in finished drinking water and fate during drinking water treatment

    Science.gov (United States)

    Klarich, Kathryn L.; Pflug, Nicholas C.; DeWald, Eden M.; Hladik, Michelle L.; Kolpin, Dana W.; Cwiertny, David M.; LeFevre, Gergory H.

    2017-01-01

    Neonicotinoid insecticides are widespread in surface waters across the agriculturally-intensive Midwestern US. We report for the first time the presence of three neonicotinoids in finished drinking water and demonstrate their general persistence during conventional water treatment. Periodic tap water grab samples were collected at the University of Iowa over seven weeks in 2016 (May-July) after maize/soy planting. Clothianidin, imidacloprid, and thiamethoxam were ubiquitously detected in finished water samples and ranged from 0.24-57.3 ng/L. Samples collected along the University of Iowa treatment train indicate no apparent removal of clothianidin and imidacloprid, with modest thiamethoxam removal (~50%). In contrast, the concentrations of all neonicotinoids were substantially lower in the Iowa City treatment facility finished water using granular activated carbon (GAC) filtration. Batch experiments investigated potential losses. Thiamethoxam losses are due to base-catalyzed hydrolysis at high pH conditions during lime softening. GAC rapidly and nearly completely removed all three neonicotinoids. Clothianidin is susceptible to reaction with free chlorine and may undergo at least partial transformation during chlorination. Our work provides new insights into the persistence of neonicotinoids and their potential for transformation during water treatment and distribution, while also identifying GAC as an effective management tool to lower neonicotinoid concentrations in finished drinking water.

  6. Wire Finishing Mill Rolling Bearing Fault Diagnosis Based on Feature Extraction and BP Neural Network

    Directory of Open Access Journals (Sweden)

    Hong-Yu LIU

    2014-10-01

    Full Text Available Rolling bearing is main part of rotary machine. It is frail section of rotary machine. Its running status affects entire mechanical equipment system performance directly. Vibration acceleration signals of the third finishing mill of Anshan Steel and Iron Group wire plant were collected in this paper. Fourier analysis, power spectrum analysis and wavelet transform were made on collected signals. Frequency domain feature extraction and wavelet transform feature extraction were made on collected signals. BP neural network fault diagnosis model was adopted. Frequency domain feature values and wavelet transform feature values were treated as neural network input values. Various typical fault models were treated as neural network output values. Corresponding relations between feature vector and fault omen were utilized. BP neural network model of typical wire plant finishing mill rolling bearing fault was constructed by training many groups sample data. After inputting sample needed to be diagnosed, wire plant finishing mill rolling bearing fault can be diagnosed. This research has important practical significance on enhancing rolling bearing fault diagnosis precision, repairing rolling bearing duly, decreasing stop time, enhancing equipment running efficiency and enhancing economic benefits.

  7. Finishing of the cold mass assembly

    CERN Multimedia

    Maximilien Brice

    2001-01-01

    Photo 1 Zoom of the lyre-side end of the active part assembly. The extremity of the shrinking cylinder has been bevelled in view of welding the end cover. Photo 2 General view of the finishing station showing the special supporting structures (blue and yellow structures) needed for the geometric measurements and for the alignment operations. Photo 3 Zoom of the lyre-side end of the active part assembly. One can also see the auxiliary bus bars needed to power the corrector magnets that are installed in the dipole cold mass assembly. Photo 4 Technicians are putting in order the instrumentation wires. The prototype magnets were equipped with numerous sensors to monitor key parameters during the performance tests at cold conditions.

  8. Finishing of precision generated metal optical components

    International Nuclear Information System (INIS)

    Baker, P.C.; Sonderman, J.B.

    1975-08-01

    Diamond turning and precision generation of aspheric metal surfaces has promoted a change in lapping techniques due to the extremely close figure tolerances and surface finishes that have been achieved. Special tooling, diamond abrasive, silicon oil and special techniques used to polish the unusual aspheric figures are described. The studies include small flat diamond turned samples of copper, electroplated copper, electroplated silver, electroplated nickel and silver as well as large aspheres such as an f/0.75, 35 cm dia copper ellipse. Results from cleaning studies on flat samples using ultrasonics and vapor degreasers are also summarized. Interferograms of wavefront distortion and analysis of focal volume are included as well as 10.6 μm reflectivity and a summary of laser damage experiments. (TFD)

  9. Finishing of the cold mass assembly

    CERN Multimedia

    Maximilien Brice

    2001-01-01

    Photo 1 The connection-side end of the active part assembly. This view shows the electrical connections between the poles and the curved bus ended with flanges for the connection with the protection diode. Photo 2 The connection-side end of the active part assembly. This view shows the electrical connections between the poles, the auxiliary bus bars and the instrumentation wires. Photo 3 Lyre-side end of the active part assembly. One can see the mechanical support of the corretor magnets that are to be installed around the cold bore tubes. Photo 4 General view of the finishing station showing the special supporting structures (blue and yellow structures) needed for the geometric measurements and for the alignment operations. Around the magnet, there are datum points (on the tripodes) needed to build up the coordinates system for the measurements.

  10. Figure and finish of grazing incidence mirrors

    International Nuclear Information System (INIS)

    Takacs, P.Z.; Church, E.L.

    1989-08-01

    Great improvement has been made in the past several years in the quality of optical components used in synchrotron radiation (SR) beamlines. Most of this progress has been the result of vastly improved metrology techniques and instrumentation permitting rapid and accurate measurement of the surface finish and figure on grazing incidence optics. A significant theoretical effort has linked the actual performance of components used as x-ray wavelengths to their topological properties as measured by surface profiling instruments. Next-generation advanced light sources will require optical components and systems to have sub-arc second surface figure tolerances. This paper will explore the consequences of these requirements in terms of manufacturing tolerances to see if the present manufacturing state-of-the-art is capable of producing the required surfaces. 15 refs., 14 figs., 2 tabs

  11. Revised licensee event report system

    International Nuclear Information System (INIS)

    Mays, G.T.; Poore, W.P.

    1985-01-01

    Licensee Event Reports (LERs) provide the basis for evaluating and assessing operating experience information from nuclear power plants. The reporting requirements for submitting LERs to the Nuclear Regulatory Commission have been revised. Effective Jan. 1, 1984, all events were to be submitted in accordance with 10 CFR 50.73 of the Code of Federal Regulations. Report NUREG-1022, Licensee Event Report System-Description of System and Guidelines for Reporting, describes the guidelines on reportability of events. This article summarizes the reporting requirements as presented in NUREG-1022, high-lights differences in data reported between the revised and previous LER systems, and presents results from a preliminary assessment of LERs submitted under the revised LER reporting system

  12. Addendum to the post-closure permit application for the Bear Creek Hydrogeologic Regime at the Y-12 Plant: Walk-in pits. Revision 2

    International Nuclear Information System (INIS)

    1995-04-01

    The revised Closure Plan was initially intended to apply to A Area, C-West, B Area, and the Walk-In Pits (WIPs) of the Bear Creek Burial Grounds (BCBG). However, a strategy was developed to include the B Area [a solid waste management unit (SWMU)] with the WIPs so that both areas would be closed under one cap. The plan was presented to the State of Tennessee on March 8, 1990, and the Department of Energy was requested to review other unique alternatives to close the site. Therefore, in November 1992, the Closure Plan for B Area and the WIPs was prepared separately from that of the other sites associated with the BCBG and was presented in a RCRA Closure Plan. The Closure Plan revision issued April 1993 was intended to reflect the placement of the Kerr Hollow Quarry debris at the WIPs, revise the closure data, and acknowledge that the disposition of a monitoring well within the closure site could not be verified. A Post-Closure Permit Application (PCPA) was to include the WIPs; however, at the time of submittal, closure of the WIPs had not been certified. This addendum contains information on the WIPs to accompany the BCBG PCPA. The purpose of this document is to supplement the information provided in the BCBG PCPA. This document is not intended to be a stand-alone document. Only additional information regarding the WIPs is included in the sections of this document, which correspond to sections of the PCPA submitted in June 1994

  13. Enhancing Surface Finish of Additively Manufactured Titanium and Cobalt Chrome Elements Using Laser Based Finishing

    Science.gov (United States)

    Gora, Wojciech S.; Tian, Yingtao; Cabo, Aldara Pan; Ardron, Marcus; Maier, Robert R. J.; Prangnell, Philip; Weston, Nicholas J.; Hand, Duncan P.

    Additive manufacturing (AM) offers the possibility of creating a complex free form object as a single element, which is not possible using traditional mechanical machining. Unfortunately the typically rough surface finish of additively manufactured parts is unsuitable for many applications. As a result AM parts must be post-processed; typically mechanically machined and/or and polished using either chemical or mechanical techniques (both of which have their limitations). Laser based polishing is based on remelting of a very thin surface layer and it offers potential as a highly repeatable, higher speed process capable of selective area polishing, and without any waste problems (no abrasives or liquids). In this paper an in-depth investigation of CW laser polishing of titanium and cobalt chrome AM elements is presented. The impact of different scanning strategies, laser parameters and initial surface condition on the achieved surface finish is evaluated.

  14. 9 CFR 318.309 - Finished product inspection.

    Science.gov (United States)

    2010-01-01

    ... Section 318.309 Animals and Animal Products FOOD SAFETY AND INSPECTION SERVICE, DEPARTMENT OF AGRICULTURE AGENCY ORGANIZATION AND TERMINOLOGY; MANDATORY MEAT AND POULTRY PRODUCTS INSPECTION AND VOLUNTARY... Canning and Canned Products § 318.309 Finished product inspection. (a) Finished product inspections must...

  15. Population dynamics of swine influenza virus in finishing pigs

    NARCIS (Netherlands)

    Loeffen, W.L.A.

    2008-01-01

    Influenza virus infections in swine were first noticed in the US in 1918, during the human pandemic of the Spanish flu. In Europe, seroprevalences for the three most common swine influenza strains at the moment, H1N1, H3N2 and H1N2, range from 20-80% in finishing pigs at the end of the finishing

  16. Assessment of the Nutrient Contents of Finished Broiler Starter and ...

    African Journals Online (AJOL)

    The study was conducted to assess and compare the proximate composition and amino acid profile of six (6) finished broiler starter and finisher diets with recommendations of National Research Council (NRC) nutrient requirements table for the different physiological age growth stage. Four samples of each feed type were ...

  17. Performance and cost implication of finisher turkeys fed varying ...

    African Journals Online (AJOL)

    A 28-day experiment was conducted to determine the effect of feeding varying levels of rice milling waste as a substitute on maize on the performance, nutrient utilization and the economics implication on finisher turkeys. Five turkey finisher diets were formulated by substituting maize with rice milling waste at 0%, 25%, 50%, ...

  18. 16 CFR 1509.8 - Construction and finishing.

    Science.gov (United States)

    2010-01-01

    ... REGULATIONS REQUIREMENTS FOR NON-FULL-SIZE BABY CRIBS § 1509.8 Construction and finishing. (a) All wood surfaces of non-full-size baby cribs shall be smooth and free from splinters. (b) All wood parts of non... 16 Commercial Practices 2 2010-01-01 2010-01-01 false Construction and finishing. 1509.8 Section...

  19. 16 CFR 1508.7 - Construction and finishing.

    Science.gov (United States)

    2010-01-01

    ... REGULATIONS REQUIREMENTS FOR FULL-SIZE BABY CRIBS § 1508.7 Construction and finishing. (a) All wood surfaces shall be smooth and free from splinters. (b) All wood parts shall be free from splits, cracks, or other... 16 Commercial Practices 2 2010-01-01 2010-01-01 false Construction and finishing. 1508.7 Section...

  20. Effect of Hoodia gordonii leaf meal supplementation at finisher stage ...

    African Journals Online (AJOL)

    A nutritional experiment was conducted to determine the effect of Hoodia gordonii leaf meal supplementation at finisher stage (30 to 42 days old) on productivity, carcass characteristics and meat sensory attributes of Ross 308 broiler chickens. The chickens were fed a finisher diet supplemented with 0 (H0), 200 (H200), 300 ...

  1. Signs of revision in Don Quixote, Part II

    Directory of Open Access Journals (Sweden)

    Gonzalo Pontón

    2016-11-01

    Full Text Available This article provides new evidences in favour of the hypothesis that Cervantes, after finishing Don Quixote, Part II, partially revised the original, introducing some significant changes and additions, mainly in the last chapters. The analysis of some narrative inconsistencies, that cannot be interpreted as mere mistakes but as significant textual traces, reveals a process of re-elaboration –a process that affects at least four sections of the novel. Most of the evidence gathered here suggests that this revision is closely linked to Avellaneda’s continuation, in the sense that Cervantes tried to challenge the apocriphal Quixote making last-time interventions in his own text.

  2. Philippines revises power plans

    Energy Technology Data Exchange (ETDEWEB)

    Hayes, D.

    1988-02-01

    Following an unexpected surge in electricity demand the Philippines has revised its medium term power development programme. The sharp increase in electricity consumption follows three years of slack demand due to civil disturbances before the end of the Macros administration and the election of Corazon Aquino as President in 1986. Originally, the Aquino government's medium term power development plans called for about 500MW of generating capacity to be installed between 1986 and 1992. The three proposed plants were scheduled for commissioning in 1991 and 1992. However, a spurt in power demand growth during the past nine months has caused concern among industrialists that power shortages could occur by the end of the decade. So additional capacity will be installed to prevent an anticipated shortfall in electricity supplies by the early 1990s.

  3. United States Department of Energy's reactor core protection evaluation methodology for fires at RBMK and VVER nuclear power plants. Revision 1

    International Nuclear Information System (INIS)

    1997-06-01

    This document provides operators of Soviet-designed RBMK (graphite moderated light water boiling water reactor) and VVER (pressurized light water reactor) nuclear power plants with a systematic Methodology to qualitatively evaluate plant response to fires and to identify remedies to protect the reactor core from fire-initiated damage

  4. Protein requirements of finishing paca (Cuniculus paca).

    Science.gov (United States)

    Nogueira-Filho, Sérgio Luiz Gama; Bastos, Ivanise da Hora; Mendes, Alcester; Nogueira, Selene Siqueira da Cunha

    2016-06-01

    We conducted a nitrogen balance digestion trial to determine the crude protein requirements of paca (Cuniculus paca) during the last growth phase. In a 4 × 4 Latin square design, four young captive male pacas, aged 5 months, were fed four isoenergetic diets containing four different levels of nitrogen (N) (11.3, 16.6, 21.4, and 26.6 g N/kg of dry matter). After 15 days of adaptation, we collected all feces and urine for five consecutive days. By regression analysis between N intake and N in feces and urine, the metabolic fecal nitrogen (MFN = 4.2 g/kg of dry matter intake) and daily endogenous urinary N (EUN = 91.6 mg/kg(0.75)) were determined. Likewise, by regression analyses between nitrogen intake and nitrogen retention [NR = N intake-(fecal N + urine N)], we estimated the daily requirement of 280.5 mg N/kg(0.75). Therefore, a minimum of 55 g crude protein per kilogram dry matter and 13 MJ/kg of digestible energy are required by finishing paca on unrestricted diets. Such values are similar to those of other wild frugivores and below those of growing rabbits. The data confirm that farmers overfeed protein, and similar growth can be more economically achieved on lower protein diets.

  5. Finishing of the cold mass assembly

    CERN Multimedia

    Maximilien Brice

    2001-01-01

    Photo 1 General view of the finishing station showing the special supporting structures (blue and yellow structures) needed for the geometric measurements and for the alignment operations. Around the magnet, there are datum points (on the tripodes) needed to build up the coordinates system for the measurements. Photo 2 The corrector magnets that are sextupoles are prepared for a plug-in fixation on their mechanical support. Photo 3 A corretor magnet has been installed on the left cold bore tube. The second one is waiting on the table for installation. Photo 4 The mechanical mole holding the corner cube reflector of the 3-D measuring machine is introduced in the cold bore tube (the right one on the picture). This will allow to pick up the X-Y-Z coordinates of the centre of the cold bore tube on its entire length. Photo 5 This picture shows the driving system that is completely computer controlled to pull the mechanical mole inside the cold bore tube. Photo 6 This picture shows details of the driving system...

  6. Hanford Waste Vitrification Plant Quality Assurance Program description for high-level waste form development and qualification. Revision 3, Part 2

    Energy Technology Data Exchange (ETDEWEB)

    1993-08-01

    The Hanford Waste Vitrification Plant Project has been established to convert the high-level radioactive waste associated with nuclear defense production at the Hanford Site into a waste form suitable for disposal in a deep geologic repository. The Hanford Waste Vitrification Plant will mix processed radioactive waste with borosilicate material, then heat the mixture to its melting point (vitrification) to forin a glass-like substance that traps the radionuclides in the glass matrix upon cooling. The Hanford Waste Vitrification Plant Quality Assurance Program has been established to support the mission of the Hanford Waste Vitrification Plant. This Quality Assurance Program Description has been written to document the Hanford Waste Vitrification Plant Quality Assurance Program.

  7. PFP MICON maintenance manual. Revision 1

    International Nuclear Information System (INIS)

    Silvan, G.R.

    1995-01-01

    This manual covers the use of maintenance displays, maintenance procedures, system alarms and common system failures. This manual is intended to supplement the MICON maintenance training not replace it. It also assumes that the user is familiar with the normal operation of the MICON A/S system. The MICON system is a distributed control computer and, among other things, controls the HVAC system for the Plutonium Finishing Plant

  8. Development of production-integrated methods of reducing environmental pollution by reducing energy and materials consumption in a textile finishing plant. Final report; Entwicklung produktionsintegrierter Verfahren zur Reduzierung von Umweltbelastungen durch Minimierung der Energie- und Stoffstrommassenstroeme am Beispiel eines Textilveredlungsbetriebes. Schlussbericht

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-11-01

    The textile finishing industry is an industry with high consumption of energy, materials (dyes, finishing agents, chemicals), and water, and with a complex technology. The industry is forced to reduce organic water pollutants as well as the consumption of energy and water. This research project is to provide the fundamentals for further research. [German] Die mittelstaendisch strukturierte Textilveredlungsindustrie ist hinsichtlich ihres Energie- und Hilfsstoffbedarfs (Farbstoffe, Textilhilfsmittel, Chemikalien), des Bedarfs an Wasser als Loesemittel bzw. Medium fuer den Stofftransfer und der vorgegebenen Prozesstechnik zunehmend gezwungen, produktionsintegrierte Konzepte zur Reduzierung gewaesserrelevanter organischer Stoffe als auch des spezifischen Energie- und Wasserbedarfs zu entwickeln. Das geplante Forschungsvorhaben soll Grundlagen fuer produktionsintegrierte Massnahmen bzw. Verfahren schaffen, die zukunftsweisend - mit ausgepraegt oekonomischen Wirkungen - weitere Fortschritte bei Entlastung der Umweltkompartimente Wasser und Boden generieren. In diesem Sinne kommen anstelle der bislang ueberwiegend angewandten additiven Technologien nur Verfahren in Frage, die sich auf spezifisch belastete Abwasserteilstroeme konzentrieren, deren Behandlungsfaehigkeit vor dem Hintergrund der erwarteten Inhaltsstoffe untersucht werden soll. (orig.)

  9. 40 CFR 425.90 - Applicability; description of the retan-wet finish-splits subcategory.

    Science.gov (United States)

    2010-07-01

    ... PROTECTION AGENCY (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS LEATHER TANNING AND FINISHING POINT SOURCE... resulting from any tannery which processes previously unhaired and tanned splits into finished leather by...

  10. Transition projects, Fiscal Year 1996: Multi-Year Program Plan (MYPP) for WBS 1.31, 7.1, and 6.13. Revision 1, Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Cartmell, D.B.

    1995-09-01

    Based on US Department of Energy (DOE), Richland Operations Office (RL) review, specific areas of Westinghouse Hanford Company (WHC), Transition Projects ``Draft`` Multi-Year Program Plan (MYPP) were revised in preparation for the RL approval ceremony on September 26, 1995. These changes were reviewed with the appropriate RL Project Manager. The changes have been incorporated to the MYPP electronic file, and hard copies replacing the ``Draft`` MYPP will be distributed after the formal signing. In addition to the comments received, a summary level schedule and outyear estimates for the K Basin deactivation beginning in FY 2001 have been included. The K Basin outyear waste data is nearing completion this week and will be incorporated. This exclusion was discussed with Mr. N.D. Moorer, RL, Facility Transition Program Support/Integration. The attached MYPP scope/schedule reflects the Integrated Target Case submitted in the April 1995 Activity Data Sheets (ADS) with the exception of B Plant and the Plutonium Finishing Plant (PFP). The 8 Plant assumption in FY 1997 reflects the planning case in the FY 1997 ADS with a shortfall of $5 million. PFP assumptions have been revised from the FY 1997 ADS based on the direction provided this past summer by DOE-Headquarters. This includes the acceleration of the polycube stabilization back to its originally planned completion date. Although the overall program repricing in FY 1996 allowed the scheduled acceleration to fall with the funding allocation, the FY 1997 total reflects a shortfall of $6 million.

  11. Transition projects, Fiscal Year 1996: Multi-Year Program Plan (MYPP) for WBS 1.31, 7.1, and 6.13. Revision 1, Volume 1

    International Nuclear Information System (INIS)

    Cartmell, D.B.

    1995-09-01

    Based on US Department of Energy (DOE), Richland Operations Office (RL) review, specific areas of Westinghouse Hanford Company (WHC), Transition Projects ''Draft'' Multi-Year Program Plan (MYPP) were revised in preparation for the RL approval ceremony on September 26, 1995. These changes were reviewed with the appropriate RL Project Manager. The changes have been incorporated to the MYPP electronic file, and hard copies replacing the ''Draft'' MYPP will be distributed after the formal signing. In addition to the comments received, a summary level schedule and outyear estimates for the K Basin deactivation beginning in FY 2001 have been included. The K Basin outyear waste data is nearing completion this week and will be incorporated. This exclusion was discussed with Mr. N.D. Moorer, RL, Facility Transition Program Support/Integration. The attached MYPP scope/schedule reflects the Integrated Target Case submitted in the April 1995 Activity Data Sheets (ADS) with the exception of B Plant and the Plutonium Finishing Plant (PFP). The 8 Plant assumption in FY 1997 reflects the planning case in the FY 1997 ADS with a shortfall of $5 million. PFP assumptions have been revised from the FY 1997 ADS based on the direction provided this past summer by DOE-Headquarters. This includes the acceleration of the polycube stabilization back to its originally planned completion date. Although the overall program repricing in FY 1996 allowed the scheduled acceleration to fall with the funding allocation, the FY 1997 total reflects a shortfall of $6 million

  12. Loosening After Acetabular Revision

    DEFF Research Database (Denmark)

    Beckmann, Nicholas A.; Weiss, Stefan; Klotz, Matthias C.M.

    2014-01-01

    The best method of revision acetabular arthroplasty remains unclear. Consequently, we reviewed the literature on the treatment of revision acetabular arthroplasty using revision rings (1541 cases; mean follow-up (FU) 5.7 years) and Trabecular Metal, or TM, implants (1959 cases; mean FU 3.7 years...

  13. Implementing Cleaner Printed Wiring Board Technologies: Surface Finishes

    Science.gov (United States)

    This document describes the problems, solutions, and time and effort involved in implementing alternative surface finish technologies, and this guide is produced as part of the DfE Printed Wiring Board Project

  14. Portable flooring protects finished surfaces, is easily moved

    Science.gov (United States)

    Carmody, R. J.

    1964-01-01

    To protect curved, finished surface and provide support for workmen, portable flooring has been made from rigid plastic foam blocks, faced with aluminum strips. Held together by nylon webbing, the flooring can be rolled up for easy carrying.

  15. Relevance of microbial finished product testing in food safety management

    DEFF Research Database (Denmark)

    Zwietering, Marcel H.; Jacxsens, Liesbeth; Membré, Jeanne Marie

    2016-01-01

    Management of microbiological food safety is largely based on good design of processes, products and procedures. Finished product testing may be considered as a control measure at the end of the production process. However, testing gives only very limited information on the safety status of a food......-active way by implementing an effective food safety management system. For verification activities in a food safety management system, finished product testing may however be useful. For three cases studies; canned food, chocolate and cooked ham, the relevance of testing both of finished products....... If a hazardous organism is found it means something, but absence in a limited number of samples is no guarantee of safety of a whole production batch. Finished product testing is often too little and too late. Therefore most attention should be focussed on management and control of the hazards in a more pro...

  16. Effect of Moringa oleifera leaf meal on finisher pig growth ...

    African Journals Online (AJOL)

    Effect of Moringa oleifera leaf meal on finisher pig growth performance, meat ... pig growth performance, meat quality, shelf life and fatty acid composition of pork ... negative effect on feed conversion efficiency, carcass and meat quality traits, ...

  17. Polishing Metal Mirrors to 0,025 Micron Surface Finish

    DEFF Research Database (Denmark)

    Pedersen, P. E.

    1978-01-01

    A research program undertaken by the Danish Atomic Energy Commission required the fabrication of metal mirrors measuring 1 m long by 53 mm wide, which had to be finished to extremely tight tolerances on thickness, plane-parallelism and surface characteristics. Progressively finer diamond compound...... are employed to achieve a high gloss finish on the metal mirrors, which are used in polarized neutron experiments. This article describes the fabrication techniques developed at the Commission's Ris phi Central Workshop....

  18. Health effects models for nuclear power plant accident consequence analysis. Modification of models resulting from addition of effects of exposure to alpha-emitting radionuclides: Revision 1, Part 2, Scientific bases for health effects models, Addendum 2

    Energy Technology Data Exchange (ETDEWEB)

    Abrahamson, S. [Wisconsin Univ., Madison, WI (United States); Bender, M.A. [Brookhaven National Lab., Upton, NY (United States); Boecker, B.B.; Scott, B.R. [Lovelace Biomedical and Environmental Research Inst., Albuquerque, NM (United States). Inhalation Toxicology Research Inst.; Gilbert, E.S. [Pacific Northwest Lab., Richland, WA (United States)

    1993-05-01

    The Nuclear Regulatory Commission (NRC) has sponsored several studies to identify and quantify, through the use of models, the potential health effects of accidental releases of radionuclides from nuclear power plants. The Reactor Safety Study provided the basis for most of the earlier estimates related to these health effects. Subsequent efforts by NRC-supported groups resulted in improved health effects models that were published in the report entitled {open_quotes}Health Effects Models for Nuclear Power Plant Consequence Analysis{close_quotes}, NUREG/CR-4214, 1985 and revised further in the 1989 report NUREG/CR-4214, Rev. 1, Part 2. The health effects models presented in the 1989 NUREG/CR-4214 report were developed for exposure to low-linear energy transfer (LET) (beta and gamma) radiation based on the best scientific information available at that time. Since the 1989 report was published, two addenda to that report have been prepared to (1) incorporate other scientific information related to low-LET health effects models and (2) extend the models to consider the possible health consequences of the addition of alpha-emitting radionuclides to the exposure source term. The first addendum report, entitled {open_quotes}Health Effects Models for Nuclear Power Plant Accident Consequence Analysis, Modifications of Models Resulting from Recent Reports on Health Effects of Ionizing Radiation, Low LET Radiation, Part 2: Scientific Bases for Health Effects Models,{close_quotes} was published in 1991 as NUREG/CR-4214, Rev. 1, Part 2, Addendum 1. This second addendum addresses the possibility that some fraction of the accident source term from an operating nuclear power plant comprises alpha-emitting radionuclides. Consideration of chronic high-LET exposure from alpha radiation as well as acute and chronic exposure to low-LET beta and gamma radiations is a reasonable extension of the health effects model.

  19. Prediction method of long-term reliability in improving residual stresses by means of surface finishing

    International Nuclear Information System (INIS)

    Sera, Takehiko; Hirano, Shinro; Chigusa, Naoki; Okano, Shigetaka; Saida, Kazuyoshi; Mochizuki, Masahito; Nishimoto, Kazutoshi

    2012-01-01

    Surface finishing methods, such as Water Jet Peening (WJP), have been applied to welds in some major components of nuclear power plants as a counter measure to Primary Water Stress Corrosion Cracking (PWSCC). In addition, the methods of surface finishing (buffing treatment) is being standardized, and thus the buffing treatment has been also recognized as the well-established method of improving stress. On the other hand, the long-term stability of peening techniques has been confirmed by accelerated test. However, the effectiveness of stress improvement by surface treatment is limited to thin layers and the effect of complicated residual stress distribution in the weld metal beneath the surface is not strictly taken into account for long-term stability. This paper, therefore, describes the accelerated tests, which confirmed that the long-term stability of the layer subjected to buffing treatment was equal to that subjected to WJP. The long-term reliability of very thin stress improved layer was also confirmed through a trial evaluation by thermal elastic-plastic creep analysis, even if the effect of complicated residual stress distribution in the weld metal was excessively taken into account. Considering the above findings, an approach is proposed for constructing the prediction method of the long-term reliability of stress improvement by surface finishing. (author)

  20. An introduction to the mechanics of performance assessment using examples of calculations done for the Waste Isolation Pilot Plant between 1990 and 1992. Revision

    Energy Technology Data Exchange (ETDEWEB)

    Rechard, R.P.

    1996-06-01

    This document provides an overview of the processes used to access the performance of the Waste Isolation Pilot Plant (WIPP). The quantitative metrics used in the performance-assessment (PA) process are those put forward in the Environmental Protection Agency`s Environmental Standards for the Management and Disposal of Spent Nuclear Fuel, HIgh-LEvel and transuranic radioactive Wastes (40 CFR 191).

  1. Cost analysis of revisions to 10 CFR Part 50, Appendix J, leak tests for primary and secondary containments of light-water-cooled nuclear power plants

    International Nuclear Information System (INIS)

    Sciacca, F.; Nelson, W.; Simpkins, B.; Riordan, B.; Godfrey, P.; Cohen, S.; Beal, S.; Goldin, D.

    1985-09-01

    The report examines the differences between the existing and proposed Appendix J and identifies eleven substantive areas where quantifiable impacts will likely result. The analysis indicated that there are four areas of change which tend to dominate all others in terms of cost impacts. The applicable paragraph numbers from Draft E2 of the Appendix J revision and the nature of the change follows: III.A(4) and III.A(6) - Test Pressure and Testing at Reduced Pressure No Longer Allowed; III.A(7)(b)(i) Acceptance Criteria 1.0 L/sub a/ Acceptable ''As Found'' Leakage; III.A(8)(2) Retesting Following Failure of ''As Found'' Type A Test - Corrective Action Plan, and III.A(8)(b)(ii) Option To Do More Frequent Type B and C Testing Rather Than More Type A Penalty Tests. The best estimate is that the proposed Appendix J would result in a cost savings ranging from about $100 million to $160 million, and increase routing occupational exposure on the order of 10,000 person-rem. These estimates capture the total impact to industry and the NRC over the assumed operating life of all existing and planned future power reactors. All dollar impacts projected to occur in future years have been present worthed at discount rates ranging from 5% to 10%

  2. ASSET guidelines. Revised 1991 Edition

    International Nuclear Information System (INIS)

    1991-12-01

    The present publication is an updated version of the IAEA Assessment of Safety Significant Events Team (ASSET) Guidelines, IAEA-TECDOC-573, published in 1990. Sections 5 and 6 include revised definitions and investigation guidelines for identification of both direct and root causes. These revisions were recommended by a Consultants Meeting held in Vienna on 3-7 December 1990. This guidance is not intended to infringe an expert's prerogative to investigate additional items. Its main purpose is to provide a basic structure and ensure consistency in the assessments. Use of the ASSET guidelines should also facilitate comparison between the observations made in different nuclear power plants and harmonize the reporting of generic ASSET results. The guidelines should always be used with a critical attitude and a view to possible improvements

  3. Prediction of manure nitrogen and carbon output from grower-finisher pigs

    DEFF Research Database (Denmark)

    Vu Thi Khanh, Van; Prapaspongsa, Trakarn; Poulsen, Hanne Damgaard

    2009-01-01

    Intensive pig production may be a hazard to the environment due to plant nutrient leakage and losses. To facilitate efficient and sustainable manure management and reduce oversupplying of crops with nutrients, there is a need for precise assessment of nutrient content in manure and manure excretion....... This study has developed algorithms for predicting the amount of excreta and manure content of nitrogen (N) and carbon (C). Data compiled from 285 digestibility and N balance experiments with growing-finishing pigs diets fed diets varying widely in chemical composition were used to establish algorithms...

  4. American National Standard administrative controls and quality assurance for the operational phase of nuclear power plants, revision of N18.7-1972

    International Nuclear Information System (INIS)

    Anon.

    1976-01-01

    This Standard provides requirements and recommendations for an administrative controls and quality assurance program necessary to provide assurance that operational phase activities at nuclear power plants are carried out without undue risk to the health and safety of the public. The requirements of this Standard apply to all activities affecting the safety-related functions of nuclear power plant structures, systems, and components. It is not intended to apply to test mobile and experimental reactors nor reactors not subject to U. S. Nuclear Regulatory Commission licensing. However, applicable sections of this Standard should be used as they apply to related activities. Activities included are: design changes, purchasing, fabricating, handling, shipping, storing, cleaning, erecting, installing, inspecting, testing, operating, maintaining, repairing, refueling and modifying

  5. IPEEE review of external events of the Asco I nuclear plant; Revision del IPEEE de sucesos externos de la Central Nuclear Asco I

    Energy Technology Data Exchange (ETDEWEB)

    Aleman, A.; Canadell, F.; Beltran, F.; Pifarre, D.; Hernandez, H.; Gasca, C.

    2012-07-01

    During the risk analysis update of Asco PP (2010), it has been carried out a review of the vulnerabilities against severe accidents caused by external events (individual Plant Examination of external Events, IPEEE). The assessment has included analysis of accidents in industrial and military facilities nearby and transportation accidents (i.e., rail, road and aircraft impact) release of hazardous materials on site, external flooding, turbine missiles and strong winds. (Author)

  6. Orthodontic treatment outcomes obtained by application of a finishing protocol

    Directory of Open Access Journals (Sweden)

    Alvaro Carvajal-Flórez

    2016-04-01

    Full Text Available ABSTRACT Objective: To evaluate the results of a finishing protocol implemented in patients treated in the Orthodontics graduate program at Universidad de Antioquia. Evaluation was carried out by means of the criteria set by the Objective Grading System (OGS of the American Board of Orthodontics (ABO. Methods: Cast models and panoramic radiographs of 34 patients were evaluated. The intervention group (IG consisted of 17 patients (19.88 ± 4.4 years old treated under a finishing protocol. This protocol included training in finishing, application of a finishing guide, brackets repositioning and patient's follow-up. Results of the IG were compared to a control group of 17 patients (21.88 ± 7.0 years old selected by stratified randomization without finishing intervention (CG. Results: The scores for both CG and IG were 38.00 ± 9.0 and 31.41 ± 9.6 (p = 0.048, respectively. The score improved significantly in the IG group, mainly regarding marginal ridges (CG: 5.59 ± 2.2; IG: 3.65 ± 1.8 (p = 0.009 and root angulation (CG: 7.59 ± 2.8; IG: 4.88 ± 2.6 (p = 0.007. Criteria that did not improve, but had the highest scores were: alignment (CG: 6.35 ± 2.7; IG: 6.82 ± 2.8 (p = 0.62 and buccolingual inclination (CG: 3.6 ± 5.88; IG: 5.29 ± 3.9 (p = 0.65. Conclusions: Standardization and implementation of a finishing protocol contributed to improve clinical performance in the Orthodontics graduate program, as expressed by occlusal outcomes. Greater emphasis should be given on the finishing phase to achieve lower scores in the ABO grading system.

  7. W. R. Grace: Plant Uses Six Sigma Methodology and Traditional Heat Balance Analysis to Identify Energy Conservation Opportunities at Curtis Bay Works (Revised)

    Energy Technology Data Exchange (ETDEWEB)

    2003-12-01

    The plant-wide energy assessment at W. R. Grace's Curtis Bay Works helped identify four projects with combined potential savings of $840,000 per year. A separate, unique project that would partner W. R. Grace with the City of Baltimore to recover and use landfill gas (methane) to cogenerate steam and electricity was also identified during the assessment. If implemented, the project would recover gas from the landfill to replace 40% of the electricity and 65% of the fuel currently required to produce steam at Curtis Bay Works. Annual savings are estimated at $900,000 to $1.2 million.

  8. Flexibility of production systems and prepare-finish time

    Directory of Open Access Journals (Sweden)

    Vukićević Milan R.

    2006-01-01

    Full Text Available One of the specificities of the large-serial and mass production is the almost neglected percentage of prepare-finish time in the production cycle. In the conditions of today dominant discontinuous production, it becomes a significant element of the production cycle. The eastern (Japan doctrine of increasing the flexibility of the production systems, is based inter alia also on the extreme reduction of the prepare-finish time. For this reason, the aim of this study was to identify the types and percentages of individual jobs within the group of prepare-finish jobs. The sample consisted of 3 (three production systems for the production of joinery, with the discontinuous production system. The research shows that the percentage of time of the jobs installation of work instruments, regulation of processing regime, and removal of work instruments is extremely long and that it ranges between 11.83% and 18.93% of the shift time. The reasons of the high percentage of these jobs are the wide range of products and the absence of the rationalisation of prepare-finish jobs. Within the efforts to minimize the effects of disruption and to increase the flexibility of the production systems, the rationalisation of prepare-finish jobs is the unavoidable condition.

  9. Legume finishing provides beef with positive human dietary fatty acid ratios and consumer preference comparable with grain-finished beef.

    Science.gov (United States)

    Chail, A; Legako, J F; Pitcher, L R; Griggs, T C; Ward, R E; Martini, S; MacAdam, J W

    2016-05-01

    Consumer liking, proximate composition, pH, Warner-Bratzler shear force, fatty acid composition, and volatile compounds were determined from the LM (longissimus thoracis) of cattle ( = 6 per diet) finished on conventional feedlot (USUGrain), legume, and grass forage diets. Forage diets included a condensed tannin-containing perennial legume, birdsfoot trefoil (; USUBFT), and a grass, meadow brome ( Rehmann; USUGrass). Moreover, representative retail forage (USDA Certified Organic Grass-fed [OrgGrass]) and conventional beef (USDA Choice, Grain-fed; ChGrain) were investigated ( = 6 per retail type). The ChGrain had the greatest ( 0.05) to that of both USUGrain and USUGrass. Both grain-finished beef treatments were rated greater ( Consumer liking of USUBFT beef tenderness, fattiness, and overall liking were comparable ( > 0.05) with that of USUGrain and ChGrain. Flavor liking was rated greatest ( 0.05) to those of ChGrain, USUGrass, and OrgGrass. Cumulative SFA and MUFA concentrations were greatest ( 0.05) to those of USUGrain and USUGrass. Each forage-finished beef treatment, USUGrass, OrgGrass, and USUBFT, had lower ( < 0.001) ratios of -6:-3 fatty acids. Hexanal was the most numerically abundant volatile compound. The concentration of hexanal increased with increasing concentrations of total PUFA. Among all the lipid degradation products (aldehydes, alcohols, furans, carboxylic acids, and ketones) measured in this study, there was an overall trend toward greater quantities in grain-finished products, lower quantities in USUGrass and OrgGrass, and intermediate quantities in USUBFT. This trend was in agreement with IMF content, fatty acid concentrations, and sensory attributes. These results suggest an opportunity for a birdsfoot trefoil finishing program, which results in beef comparable in sensory quality with grain-finished beef but with reduced -6 and SFA, similar to grass-finished beef.

  10. Introduction of 'Physicochemical and manufacturing basis for uranium concentrates production from wastes of hydrometallurgical plants and technical waters (Second edition, revised)'

    International Nuclear Information System (INIS)

    Khakimov, N.; Nazarov, Kh.M.; Mirsaidov, I.U.

    2012-01-01

    The uranium deposits of Tajikistan played an immensely significant role in the practical solution of a radioactive raw materials problem which appeared during the post-World War II years in the USSR. The pioneer in this field became complex №6 (currently known as 'Vostokredmet'). The first soviet uranium was produced from the ores extracted from the republic's deposits. For 50 years (1945-1995 y.) , uranium bearing raw materials from all over the former USSR were delivered to Tajikistan, and uranium oxide was produced, which was later delivered back to Russia for further production of enriched uranium. The total volume of uranium produced in Tajikistan plants was approximately 100 thousands tons. In Soghd region, during that period, more than 55 million tons of uranium waste was accumulated. The total activity of the waste, according to different calculations, is approximately 240-285 TBq. The total amount of waste in dumps and tailings piles is estimated to be more than 170 million tons, most of which are located in the neighborhoods of hydrometallurgical plants and heap leaching locations. Uranium industry wastes in Northern Tajikistan have become attractive for different investors and commercial companies, from secondary reprocessing of mines and tailings' point of view, since the uranium price is increasing. In this regard, research on developing uranium extraction methods from wastes is broadening. The study of the possibility and economic reasonability of reprocessing former year's dumps requires comprehensive examination, and relates not only to uranium extraction but to safe extraction of dumps from tailings as well.

  11. Stormwater Pollution Prevention Plan for the TA-03-22 Power and Steam Plant, Los Alamos National Laboratory, Revision 3, January 2018

    Energy Technology Data Exchange (ETDEWEB)

    Burgin, Jillian Elizabeth [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2018-02-01

    This Storm Water Pollution Prevention Plan (SWPPP) was developed in accordance with the provisions of the Clean Water Act (33 U.S.C. §§1251 et seq., as amended), and the Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activity (U.S. EPA, June 2015) issued by the U.S. Environmental Protection Agency (EPA) for the National Pollutant Discharge Elimination System (NPDES) and using the industry specific permit requirements for Sector O-Steam Electric Generating Facilities as a guide. This SWPPP applies to discharges of stormwater from the operational areas of the TA-03-22 Power and Steam Plant at Los Alamos National Laboratory. Los Alamos National Laboratory (also referred to as LANL or the “Laboratory”) is owned by the Department of Energy (DOE), and is operated by Los Alamos National Security, LLC (LANS). Throughout this document, the term “facility” refers to the TA-03-22 Power and Steam Plant and associated areas. The current permit expires at midnight on June 4, 2020.

  12. Approaches for in silico finishing of microbial genome sequences

    Directory of Open Access Journals (Sweden)

    Frederico Schmitt Kremer

    Full Text Available Abstract The introduction of next-generation sequencing (NGS had a significant effect on the availability of genomic information, leading to an increase in the number of sequenced genomes from a large spectrum of organisms. Unfortunately, due to the limitations implied by the short-read sequencing platforms, most of these newly sequenced genomes remained as “drafts”, incomplete representations of the whole genetic content. The previous genome sequencing studies indicated that finishing a genome sequenced by NGS, even bacteria, may require additional sequencing to fill the gaps, making the entire process very expensive. As such, several in silico approaches have been developed to optimize the genome assemblies and facilitate the finishing process. The present review aims to explore some free (open source, in many cases tools that are available to facilitate genome finishing.

  13. Approaches for in silico finishing of microbial genome sequences.

    Science.gov (United States)

    Kremer, Frederico Schmitt; McBride, Alan John Alexander; Pinto, Luciano da Silva

    The introduction of next-generation sequencing (NGS) had a significant effect on the availability of genomic information, leading to an increase in the number of sequenced genomes from a large spectrum of organisms. Unfortunately, due to the limitations implied by the short-read sequencing platforms, most of these newly sequenced genomes remained as "drafts", incomplete representations of the whole genetic content. The previous genome sequencing studies indicated that finishing a genome sequenced by NGS, even bacteria, may require additional sequencing to fill the gaps, making the entire process very expensive. As such, several in silico approaches have been developed to optimize the genome assemblies and facilitate the finishing process. The present review aims to explore some free (open source, in many cases) tools that are available to facilitate genome finishing.

  14. Bonding of radioactive contamination. IV. Effect of surface finish

    International Nuclear Information System (INIS)

    Rankin, W.N.

    1983-01-01

    The mechanisms by which radioactive contamination would be bonded to a DWPF canister are being investigated. Previous investigations in this series have examined the effects of temperature, oxidation before contamination, and atmosphere composition control on the bonding of contamination. This memorandum describes the results of tests to determine the effect of special surface finishes on the bonding of contamination to waste glass canisters. Surface pretreatments which produce smoother canister surfaces actually cause radioactive contamination to be more tightly bonded to the metal surface than on an untreated surface. Based on the results of these tests it is recommended that the canister surface finish be specified as having a bright cold rolled mill finish equivalent to ASTM No. 2B. 7 references, 3 figures, 3 tables

  15. Tool steel quality and surface finishing of plastic molds

    Directory of Open Access Journals (Sweden)

    Rafael Agnelli Mesquita

    2010-01-01

    Full Text Available Plastic industry is today in a constant growth, demanding several products from other segments, which includes the plastic molds, mainly used in the injection molding process. Considering all the requirements of plastic molds, the surface finishing is of special interest, as the injected plastic part is able to reproduce any details (and also defects from the mold surface. Therefore, several aspects on mold finishing are important, mainly related to manufacturing conditions - machining, grinding, polishing and texturing, and also related to the tool steel quality, in relation to microstructure homogeneity and non-metallic inclusions (cleanliness. The present paper is then focused on this interrelationship between steel quality and manufacturing process, which are both related to the final quality of plastic mold surfaces. Examples are discussed in terms of surface finishing of plastic molds and the properties or the microstructure of mold steels.

  16. TRU [transuranic] waste certification compliance requirements for acceptance of newly generated contact-handled wastes to be shipped to the Waste Isolation Pilot Plant: Revision 2

    International Nuclear Information System (INIS)

    1989-01-01

    Compliance requirements are presented for certifying that unclassified, newly generated (NG), contact-handled (CH) transuranic (TRU) solid wastes from defense programs meet the Waste Isolation Pilot Plant (WIPP) Waste Acceptance Criteria (WAC). Where appropriate, transportation and interim storage requirements are incorporated; however, interim storage sites may have additional requirements consistent with these requirements. All applicable Department of Energy (DOE) orders must continue to be met. The compliance requirements for stored or buried waste are not addressed in this document. The compliance requirements are divided into four sections, primarily determined by the general feature that the requirements address. These sections are General Requirements, Waste Container Requirements, Waste Form Requirements, and Waste Package Requirements. The waste package is the combination of waste container and waste. 10 refs., 1 fig

  17. Resource Conservation and Recovery Act, Part B permit application [for the Waste Isolation Pilot Plant (WIPP)]. Volume 4, Revision 1.0

    Energy Technology Data Exchange (ETDEWEB)

    1991-12-31

    The US Department of Energy is currently constructing the Waste Isolation Pilot near Carlsbad, New Mexico. The full-scale pilot plant will demonstrate the feasibility of the safe disposal of defense-related nuclear waste in a bedded salt formation at a depth of 2160 feet below the surface. WIPP will provide for the permanent storage of 25,000 cu ft of remote-handled (RH) transuranic waste and 6,000,000 cu ft of contact-handled (CH) transuranic waste. This paper covers the major mechanical/structural design considerations for the waste hoist and its hoist tower structure. The design of the hoist system and safety features incorporates state-of-the-art technology developed in the hoist and mining industry to ensure safe operation for transporting nuclear waste underground. Also included are design specifications for VOC-10 monitoring system.

  18. Analytical methods for the characterization of surface finishing in bricks

    International Nuclear Information System (INIS)

    Nardini, I.; Zendri, E.; Biscontin, G.; Brunetin, A.

    2006-01-01

    The recent restoration works of Santo Stefano Church Facade (XV century) in Venice have shown traces variously saved of different kind of surface finishes. These finishes were found on the brick's surface both in the masonry and in the decorative elements. Different brick's surface and decorative tile samples were investigated using several techniques: optical microscopy, scanning electron-microscopy, thermal analysis, infrared spectroscopy and reflectance Fourier transform infrared microspectroscopy. The evaluation of the reached results was used to understand the decorative techniques and to recognize the material employed

  19. New trends for PWB surface finishes in mobile phone applications

    DEFF Research Database (Denmark)

    Nielsen, Claus Würtz; Ambat, Rajan; Rasmussen, Anette Alsted

    2005-01-01

    Immersion Ni/Au has been the overall dominant surface finish on PWB's for the last 10 years. During the last 5 years Mobile Phones have been extremely popular and spread all over the world in different climate zones in very high volumes. At the same time the Mobile Phone terminal for many people...... use of Imm. Ni/Au unnecessary in the near future. The end result is higher reliability with less expensive and simpler processes. This paper will discuss the various considerations for choice of surface finish and results from the extensive feasibility studies performed by Nokia Mobile Phones...

  20. Persistence of antimicrobial resistance genes from sows to finisher pigs

    DEFF Research Database (Denmark)

    Birkegård, Anna Camilla; Halasa, Tariq; Folkesson, Anders

    2018-01-01

    Antimicrobial resistance in pigs has been under scrutiny for many years. However, many questions remain unanswered, including whether the initial antimicrobial resistance level of a pig will influence the antimicrobial resistance found at slaughter. Faecal samples from finishers pigs from 681 farms...... and from sows from 82 farms were collected, and levels of seven antimicrobial resistance genes, ermB, ermF, sulI, sulII, tet(M), tet(O), and tet(W), were quantified by high-capacity qPCR. There were 40 pairs of observations where the finishers were born in the farms of the sows. The objective of this study...

  1. EPRI PWR primary water chemistry guidelines revision

    International Nuclear Information System (INIS)

    McElrath, Joel; Fruzzetti, Keith

    2014-01-01

    EPRI periodically updates the PWR Primary Water Chemistry Guidelines as new information becomes available and as required by NEI 97-06 (Steam Generator Program Guidelines) and NEI 03-08 (Guideline for the Management of Materials Issues). The last revision of the PWR water chemistry guidelines identified an optimum primary water chemistry program based on then-current understanding of research and field information. This new revision provides further details with regard to primary water stress corrosion cracking (PWSCC), fuel integrity, and shutdown dose rates. A committee of industry experts, including utility specialists, nuclear steam supply system (NSSS) and fuel vendor representatives, Institute of Nuclear Power Operations (INPO) representatives, consultants, and EPRI staff collaborated in reviewing the available data on primary water chemistry, reactor water coolant system materials issues, fuel integrity and performance issues, and radiation dose rate issues. From the data, the committee updated the water chemistry guidelines that all PWR nuclear plants should adopt. The committee revised guidance with regard to optimization to reflect industry experience gained since the publication of Revision 6. Among the changes, the technical information regarding the impact of zinc injection on PWSCC initiation and dose rate reduction has been updated to reflect the current level of knowledge within the industry. Similarly, industry experience with elevated lithium concentrations with regard to fuel performance and radiation dose rates has been updated to reflect data collected to date. Recognizing that each nuclear plant owner has a unique set of design, operating, and corporate concerns, the guidelines committee has retained a method for plant-specific optimization. Revision 7 of the Pressurized Water Reactor Primary Water Chemistry Guidelines provides guidance for PWR primary systems of all manufacture and design. The guidelines continue to emphasize plant

  2. Finishing and upgrading of heavy water

    International Nuclear Information System (INIS)

    Butler, J.P.; Hammerli, M.

    1981-01-01

    This invention provides a process and apparatus for deuterium enrichment as a final stage in a heavy water plant, for continuous on-line enrichment of the heavy water in moderator and heat transfer systems in heavy water nuclear reactors, and for enrichment of hevy water that has been downgraded with natural water during the course of operating a heavy water nuclear reactor. The method comprises contacting partially-enriched heavy water feed in a catalyst column with hydrogen gas (essentially D 2 ) orginating in an electrolysis cell so as to enrich the feed water with deuterium extracted from the electrolytic hydrogen gas and passing the deuterium-enriched water to the electrolysis cell. The apparatus comprises a catalyst isotope exchange column with hydrogen gas and liquid water passing through in countercurrent isotope exchange, an electrolysis cell, a dehumidifer-scrubber; and means for passing the liquid water enriched in deuterium from the catalyst column through the dehumidifer-scrubber to the electrolysis cell, for passing the hydrogen gas evolved in the cathode side of the cell through the dehumidifier-scrubber to the catalyst column, for passing the hydrogen gas from the catalyst column to an output, for introducing an input water feed to the upper portion of the catalyst column, and for taking a product enriched in deuterium from the system. (LL)

  3. Bibliocable. Revised Edition.

    Science.gov (United States)

    Cable Television Information Center, Washington, DC.

    This selective, annotated bibliography is a revision of the original published in 1972 (ED 071 402). Some 104 books, articles, and reports included here deal with access, applications, franchising, regulation, technology, and other aspects of cable television. The listings are of two types in each category. First are revisions of the original…

  4. Site suitability report in the matter of Clinch River Breeder Reactor Plant. Docket No. 50-537. Revision to March 4, 1977 report

    International Nuclear Information System (INIS)

    1982-06-01

    In March 1977, the Office of Nuclear Reactor Regulation issued its Site Suitability Report (SSR) for the proposed Clinch River Breeder Plant (CRBRP). That SSR documents the result of the staff's evaluation of the suitability of the proposed CRBRP site for a facility of the general size and type as the CRBRP from the standpoint of radiological health and safety considerations. The staff concluded in that SSR that the proposed CRBRP site is suitable for such a facility. Since the SSR was issued, several modifications have been made to the CRBRP design, additional data related to the site and its environs have been collected, and the Fast Flux Test Facility, a technological precursor to the CRBRP, has been completed and has commenced operation. In addition, new emergency planning requirements have been promulgated by the staff. This report is an update of the March 1977 SSR that reflects these matters and discusses them in terms of the previous staff conclusion regarding the suitability of the proposed CRBRP site

  5. Resource Conservation and Recovery Act, Part B Permit Application [for the Waste Isolation Pilot Plant (WIPP)]. Volume 4, Chapter D, Appendix D1 (beginning), Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    Lappin, A. R.

    1993-03-01

    The Waste Isolation Pilot Plant (WIPP), which is designed for receipt, handling, storage, and permanent isolation of defense-generated transuranic wastes, is being excavated at a depth of approximately 655 m in bedded halites of the Permian Salado Formation of southeastern New Mexico. Site-characterization activities at the present WIPP site began in 1976. Full construction of the facility began in 1983, after completion of ``Site and Preliminary Design Validation`` (SPDV) activities and reporting. Site-characterization activities since 1983 have had the objectives of updating or refining the overall conceptual model of the geologic, hydrologic, and structural behavior of the WIPP site and providing data adequate for use in WIPP performance assessment. This report has four main objectives: 1. Summarize the results of WIPP site-characterization studies carried out since the spring of 1983 as a result of specific agreements between the US Department of Energy and the State of New Mexico. 2. Summarize the results and status of site-characterization and facility-characterization studies carried out since 1983, but not specifically included in mandated agreements. 3. Compile the results of WIPP site-characterization studies into an internally consistent conceptual model for the geologic, hydrologic, geochemical, and structural behavior of the WIPP site. This model includes some consideration of the effects of the WIPP facility and shafts on the local characteristics of the Salado and Rustler Formations. 4. Discuss the present limitations and/or uncertainties in the conceptual geologic model of the WIPP site and facility. The objectives of this report are limited in scope, and do not include determination of whether or not the WIPP Project will comply with repository-performance criteria developed by the US Environmental Protection Agency (40CFR191).

  6. Implementation of the Resource Disincentive in 40 CFR part 191.14 (e) at the Waste Isolation Pilot Plant. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    1993-06-01

    In 1986, the US Department of Energy (DOE) Waste Isolation Pilot Plant (WIPP) Project Office (WPO) (DOE-WPO) prepared a strategy for complying with the Environmental Protection Agency`s (EPA`s) Standards for the management of transuranic (TRU) waste. Section 3.2.2.2 of the DOE`s report addressed compliance with the Assurance Requirements found in 40 CFR {section} 191.14. One of the Assurance Requirements addresses the selection of repository sites that contain recoverable natural resources. This report documents that the site selection process for the WIPP facility did indeed comply with the natural resource disincentive requirement in 40 CFR {section} 191,14(e) at the time selected and therefore complies with the standard at this time. Thus, it shall be shown that it is reasonably certain that the WIPP site provides better overall protection than practical alternatives that were available when the site was selected. It is important to point out here, and it will be discussed later in the report, that the resource disincentive requirement is a preliminary siting criterion that requires further evaluation of sites that have resources (i.e, hydrocarbons, minerals and groundwater) in the vicinity or on the site. This further evaluation requires that for sites that do have resources, a qualitative determination must be made that the site will provide better overall protection than practical alternatives. The purpose of this report is not to provide a quantitative evaluation for selection of the WIPP site. A further discussion on the difference between the qualitative analysis required under 40 CFR {section} 191.14(e) and the quantitative analysis under other sections of 40 CFR 191 is provided in {section}2.1 of this report.

  7. Revised Earthquake Catalog and Relocated Hypocenters Near Fluid Injection Wells and the Waste Isolation Pilot Plant (WIPP) in Southeastern New Mexico

    Science.gov (United States)

    Edel, S.; Bilek, S. L.; Garcia, K.

    2014-12-01

    Induced seismicity is a class of crustal earthquakes resulting from human activities such as surface and underground mining, impoundment of reservoirs, withdrawal of fluids and gas from the subsurface, and injection of fluids into underground cavities. Within the Permian basin in southeastern New Mexico lies an active area of oil and gas production, as well as the Waste Isolation Pilot Plant (WIPP), a geologic nuclear waste repository located just east of Carlsbad, NM. Small magnitude earthquakes have been recognized in the area for many years, recorded by a network of short period vertical component seismometers operated by New Mexico Tech. However, for robust comparisons between the seismicity patterns and the injection well locations and rates, improved locations and a more complete catalog over time are necessary. We present results of earthquake relocations for this area by using data from the 3-component broadband EarthScope Flexible Array SIEDCAR experiment that operated in the area between 2008-2011. Relocated event locations tighten into a small cluster of ~38 km2, approximately 10 km from the nearest injection wells. The majority of events occurred at 10-12 km depth, given depth residuals of 1.7-3.6 km. We also present a newly developed more complete catalog of events from this area by using a waveform cross-correlation algorithm and the relocated events as templates. This allows us to detect smaller magnitude events that were previously undetected with the short period network data. The updated earthquake catalog is compared with geologic maps and cross sections to identify possible fault locations. The catalog is also compared with available well data on fluid injection and production. Our preliminary results suggest no obvious connection between seismic moment release, fluid injection, or production given the available monthly industry data. We do see evidence in the geologic and well data of previously unidentified faults in the area.

  8. Performance Of Growing Pigs And Finisher Broilers Housed Together

    African Journals Online (AJOL)

    Growth performance and cost of feeding young growing pigs and finisher broilers under integrated broiler/pig production system were investigated. Four young growing pigs (the control) were housed in pen A and fed 4% of their body weight as commercial growers feed. Another 4 were housed in pen B with broilers in ...

  9. Serum biochemical indices of Finisher Broiler Chickens fed diets ...

    African Journals Online (AJOL)

    A 4 week feeding trial was conducted using 180 five-week old Hubbard broiler chickens to determine the effect of feeding variously processed roselle(Hibiscus sabdariffa) seeds on serum biochemical indices with a view to determining the potential of roselle seed as an alternative to soybeans. Five broiler finisher diets were ...

  10. Effect of finishing system on carcass characteristics and composition ...

    African Journals Online (AJOL)

    Effect of finishing system on carcass characteristics and composition of Mubende goats and their Boer goat crossbreds. ... Dissectible lean and fat percentages varied in an ascending order of 66%, 72%, 72.6% and 8%, 14% and 16.5% for T1, T2 and T3, respectively. A reverse trend was observed for bone percentages with ...

  11. Comparison of triticale cultivars with maize grain for finishing lambs ...

    African Journals Online (AJOL)

    Comparison of triticale cultivars with maize grain for finishing lambs. TS Brand, GD van der Merwe. Abstract. No Abstract. Full Text: EMAIL FREE FULL TEXT EMAIL FREE FULL TEXT · DOWNLOAD FULL TEXT DOWNLOAD FULL TEXT · AJOL African Journals Online. HOW TO USE AJOL... for Researchers · for Librarians ...

  12. 78 FR 23591 - Certain Prepregs, Laminates, and Finished Circuit Boards

    Science.gov (United States)

    2013-04-19

    ... INTERNATIONAL TRADE COMMISSION [Investigation No. 337-TA-659 (Enforcement)] Certain Prepregs... United States after importation of certain prepregs, laminates, and finished circuit boards that infringe... prepregs and laminates that are the subject of the investigation or that otherwise infringe, induce, and/or...

  13. Carpentry and Finishing Procedures. Building Maintenance. Module II. Instructor's Guide.

    Science.gov (United States)

    Hawk, Sam; Brunk, Art

    This curriculum guide, keyed to the building maintenance competency profile developed by industry and education professionals, provides three units on carpentry and finishing procedures. The first unit, Exterior Carpentry, contains the following lessons: carpentry safety procedures, ladder and scaffolding safety, door installation/repair,…

  14. Response of finishing broiler chickens to diets containing rumen ...

    African Journals Online (AJOL)

    One hundred and fifty Arbor acres broiler chickens aged four weeks were used in determining the effect of fermented rice husk meal diets on the performance and nutrient digestibility of finisher broiler chickens. They were allotted into five dietary treatments containing 0, 5, 10, 15 and 20 % rumen liquor fermented rice husk ...

  15. Performance and nutrient utilization of cockerel finishers fed graded ...

    African Journals Online (AJOL)

    RMW) on performance and nutrient utilization of cockerel finishers. One hundred and fifty 9-week old Black Harco cockerels were raised on five experimental diets where RMW replaced maize at graded levels and designated diet 1 (0% RMW); diet ...

  16. Response of finishing broiler chickens to supplemental Neem ...

    African Journals Online (AJOL)

    An eight weeks feeding trial was conducted to investigate the effects of feeding diets containing Neem Leaf Meal (NLM), Garlic Meal (GM) and their combinations (NLM +GM) on oocyst count, bacteria count and gut morphology of finishing broiler chickens. A total of 180 day-old Cobb broiler chickens were divided into twelve ...

  17. A survey of grass-finished beef producers in Pennsylvania

    Science.gov (United States)

    To meet our goal of quantifying the environmental impacts of grass-finished beef production, data on production practices in Pennsylvania were collected at the farm level via visits and online surveys. Twenty-three responses represented a total of 1,055 animals on 2,155 acres of land. Farms were rel...

  18. Effect of Moringa oleifera leaf meal on finisher pig growth ...

    African Journals Online (AJOL)

    Felistus

    2014-12-12

    Dec 12, 2014 ... (FCR) of finisher pigs, physico-chemical meat quality, fatty acid (FA) composition and shelf life of pork was .... 5.2 mg manganese; 2.6 mg copper; 0.05 mg selenium. ... indicating redness (red-green spectrum) and b*, indicating ...

  19. Relevance of microbial finished product testing in food safety management

    NARCIS (Netherlands)

    Zwietering, M.H.; Jacxsens, L.; Membre, J.M.; Nauta, M.; Peterz, M.

    2016-01-01

    Management of microbiological food safety is largely based on good design of processes, products and procedures. Finished product testing may be considered as a control measure at the end of the production process. However, testing gives only very limited information on the safety status of a food.

  20. Fungal biodegradation of plantain peel for broiler finisher feeding: In ...

    African Journals Online (AJOL)

    ... protein, cholesterol and glucose were significantly (P<0.05) affected by the treatments. Fungal biodegradation of PPL using A.niger has the potential of enhancing feed intake, nutrient digestibility and the body weight gain of broiler finisher. Keywords: Aspergillus niger, biodegradation, nutrient enhancement and broilers.

  1. A preliminary study on growth response of broiler finishers fed ...

    African Journals Online (AJOL)

    A preliminary study on growth response of broiler finishers fed processed mottle Mucuna beans ( Mucuna pruriens var. utilis ) ... They were fed diets (20% CP, 13 MJME/kg) incorporating 0%, 5% and 10% processed mottle “Mucuna” beans. A completely randomized design was used. Feed and water were supplied and ...

  2. Finished Genome Sequence of Collimonas arenae Cal35

    NARCIS (Netherlands)

    Wu, Je-Jia; de Jager, Victor; Deng, Wen-ling; Leveau, Johan

    2015-01-01

    We announce the finished genome sequence of soil forest isolate Collimonas arenae Cal35, which comprises a 5.6-Mbp chromosome and 41-kb plasmid. The Cal35 genome is the second one published for the bacterial genus Collimonas and represents the first opportunity for high-resolution comparison of

  3. Investigation of Floor Surface Finishes for Optimal Slip Resistance Performance

    Directory of Open Access Journals (Sweden)

    In-Ju Kim

    2018-03-01

    Full Text Available Background: Increasing the slip resistance of floor surfaces would be desirable, but there is a lack of evidence on whether traction properties are linearly correlated with the topographic features of the floor surfaces or what scales of surface roughness are required to effectively control the slipperiness of floors. Objective: This study expands on earlier findings on the effects of floor surface finishes against slip resistance performance and determines the operative ranges of floor surface roughness for optimal slip resistance controls under different risk levels of walking environments. Methods: Dynamic friction tests were conducted among three shoes and nine floor specimens under wet and oily environments and compared with a soapy environment. Results: The test results showed the significant effects of floor surface roughness on slip resistance performance against all the lubricated environments. Compared with the floor-type effect, the shoe-type effect on slip resistance performance was insignificant against the highly polluted environments. The study outcomes also indicated that the oily environment required rougher surface finishes than the wet and soapy ones in their lower boundary ranges of floor surface roughness. Conclusion: The results of this study with previous findings confirm that floor surface finishes require different levels of surface coarseness for different types of environmental conditions to effectively manage slippery walking environments. Collected data on operative ranges of floor surface roughness seem to be a valuable tool to develop practical design information and standards for floor surface finishes to efficiently prevent pedestrian fall incidents. Keywords: floor surface finishes, operational levels of floor surface roughness, slip resistance, wet, soapy and oily environments

  4. Transport losses in finisher pigs: impact of transport distance and season of the year

    Directory of Open Access Journals (Sweden)

    Eva Voslarova

    2017-01-01

    Full Text Available Objective The death of animals during transport for slaughter is a major factor indicating the level of welfare in transported animals. The aim of this study was to assess mortality related to the commercial transport of finisher pigs for slaughter in the Czech Republic. Methods The inspectors of the State Veterinary Administration of the Czech Republic recorded the numbers of finisher pigs transported to processing plants in the Czech Republic for slaughter and the mortality in these pigs in relation to transport in the period from 2009 to 2014. Results Our results show that the likelihood of death losses in transported pigs increases with increasing transport distance. The transport-related mortality ranged from 0.049% in pigs transported for distances below 50 km to 0.145% in pigs transported for distances exceeding 300 km. The impact of external air temperature on the transport-related mortality found in our study clearly shows that current transport practices fail to ensure the welfare of pigs transported under other than moderate weather. Particularly cold temperatures below −2°C were associated with increased death losses in winter transport. Conclusion Despite a decreasing trend in the mortality of finisher pigs transported for slaughter in Europe, our study suggests that current transport conditions are not efficient at ensuring the welfare of pigs during transport for longer distances and the protection of pigs against the negative impact of extreme ambient temperatures. Further research should focus on developing practical guidelines to improve the welfare of pigs in transit accordingly.

  5. Proceedings of national executive management seminar on surface finishing by radiation curing technology: radiation curing for better finishing

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-12-31

    This book compiled the paper presented at this seminar. The papers discussed are 1. Incentives for investment in the manufacturing sector (in Malaysia) 2.Trends and prospect of surface finishing by radiation curing technology in Malaysia 3. Industrial application of radiation curing.

  6. Proceedings of national executive management seminar on surface finishing by radiation curing technology: radiation curing for better finishing

    International Nuclear Information System (INIS)

    1993-01-01

    This book compiled the paper presented at this seminar. The papers discussed are 1. Incentives for investment in the manufacturing sector (in Malaysia) 2.Trends and prospect of surface finishing by radiation curing technology in Malaysia 3. Industrial application of radiation curing

  7. Publishing and Revising Content

    Science.gov (United States)

    Editors and Webmasters can publish content without going through a workflow. Publishing times and dates can be set, and multiple pages can be published in bulk. Making an edit to published content created a revision.

  8. Letter of Map Revision

    Data.gov (United States)

    Earth Data Analysis Center, University of New Mexico — The National Flood Hazard Layer (NFHL) data incorporates all Digital Flood Insurance Rate Map(DFIRM) databases published by FEMA, and any Letters Of Map Revision...

  9. Activated sludge respirometry to assess solar detoxification of a metal finishing effluent

    Energy Technology Data Exchange (ETDEWEB)

    Santos-Juanes, L.; Amat, A.M. [Departamento de Ingenieria Textil y Papelera, Escuela Politecnica Superior de Alcoy, Universidad Politecnica de Valencia, Plaza Ferrandiz y Carbonell s/n, E-03801 Alcoy (Spain); Arques, A. [Departamento de Ingenieria Textil y Papelera, Escuela Politecnica Superior de Alcoy, Universidad Politecnica de Valencia, Plaza Ferrandiz y Carbonell s/n, E-03801 Alcoy (Spain)], E-mail: aarques@txp.upv.es; Bernabeu, A.; Silvestre, M.; Vicente, R. [Departamento de Ingenieria Textil y Papelera, Escuela Politecnica Superior de Alcoy, Universidad Politecnica de Valencia, Plaza Ferrandiz y Carbonell s/n, E-03801 Alcoy (Spain); Ano, E. [Departamento de Gestion e Innovacion, Area de producto y desarrollo sostenible, Asociacion de Investigacion de la Industria del Juguete, Conexas y Afines (AIJU), Avda. de la industria, 23, 03440 Ibi (Spain)], E-mail: m.ambiente@aiju.info

    2008-05-30

    Inhibition of the respiration of activated sludge has been tested as a convenient method to estimate toxicity of aqueous solutions containing copper and cyanide, such as metal finishing effluents; according to this method, an EC{sub 50} of 0.5 mg/l was determined for CN{sup -} and 3.0 mg/l for copper. Solar detoxification of cyanide-containing solutions was studied using TiO{sub 2}, but this process was unfavourable because of the inhibitory role that plays the copper ions present in real effluents on the oxidation of cyanide. On the other hand, the oxidative effect of hydrogen peroxide was greatly enhanced by Cu{sup 2+} and solar irradiation, as complete elimination of free and complexed cyanide could be accomplished, together with precipitation of copper, in experiments carried out at pilot plant scale with real metal finishing effluents. Under these conditions, total detoxification was achieved according to respirometric measurements although some remaining toxicity was determined by more sensitive Vibrio fischeri luminescent assay.

  10. Activated sludge respirometry to assess solar detoxification of a metal finishing effluent

    International Nuclear Information System (INIS)

    Santos-Juanes, L.; Amat, A.M.; Arques, A.; Bernabeu, A.; Silvestre, M.; Vicente, R.; Ano, E.

    2008-01-01

    Inhibition of the respiration of activated sludge has been tested as a convenient method to estimate toxicity of aqueous solutions containing copper and cyanide, such as metal finishing effluents; according to this method, an EC 50 of 0.5 mg/l was determined for CN - and 3.0 mg/l for copper. Solar detoxification of cyanide-containing solutions was studied using TiO 2 , but this process was unfavourable because of the inhibitory role that plays the copper ions present in real effluents on the oxidation of cyanide. On the other hand, the oxidative effect of hydrogen peroxide was greatly enhanced by Cu 2+ and solar irradiation, as complete elimination of free and complexed cyanide could be accomplished, together with precipitation of copper, in experiments carried out at pilot plant scale with real metal finishing effluents. Under these conditions, total detoxification was achieved according to respirometric measurements although some remaining toxicity was determined by more sensitive Vibrio fischeri luminescent assay

  11. The effects of stainless steel finish on Salmonella Typhimurium attachment, biofilm formation and sensitivity to chlorine.

    Science.gov (United States)

    Schlisselberg, Dov B; Yaron, Sima

    2013-08-01

    Bacterial colonization and biofilm formation on stainless steel (SS) surfaces can be sources for cross contamination in food processing facilities, possessing a great threat to public health and food quality. Here the aim was to demonstrate the influence of surface finish of AISI 316 SS on colonization, biofilm formation and susceptibility of Salmonella Typhimurium to disinfection. Initial attachment of S. Typhimurium on surfaces of SS was four times lower, when surface was polished by Bright-Alum (BA) or Electropolishing (EP), as compared to Mechanical Sanded (MS) or the untreated surface (NT). The correlation between roughness and initial bacterial attachment couldn't account on its own to explain differences seen. Biofilms with similar thickness (15-18 μm) were developed on all surfaces 1-day post inoculation, whereas EP was the least covered surface (23%). Following 5-days, biofilm thickness was lowest on EP and MS (30 μm) and highest on NT (62 μm) surfaces. An analysis of surface composition suggested a link between surface chemistry and biofilm development, where the higher concentrations of metal ions in EP and MS surfaces correlated with limited biofilm formation. Interestingly, disinfection of biofilms with chlorine was up to 130 times more effective on the EP surface (0.005% surviving) than on the other surfaces. Overall these results suggest that surface finish should be considered carefully in a food processing plant. Copyright © 2013 Elsevier Ltd. All rights reserved.

  12. 40 CFR 425.40 - Applicability; description of the retan-wet finish-sides subcategory.

    Science.gov (United States)

    2010-07-01

    ... PROTECTION AGENCY (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS LEATHER TANNING AND FINISHING POINT SOURCE... resulting from any tannery which processes previously tanned hides and skins (grain side only) into finished...

  13. Technology of magnetic abrasive finishing in machining of difficult-to-machine alloy complex surface

    Directory of Open Access Journals (Sweden)

    Fujian MA

    2016-10-01

    Full Text Available The technology of magnetic abrasive finishing is one of the important finishing technologies. Combining with low-frequency vibration and ultrasonic vibration, it can attain higher precision, quality and efficiency. The characteristics and the related current research of magnetic abrasive finishing, vibration assisted magnetic abrasive finishing and ultrasonic assisted magnetic abrasive finishing are introduced. According to the characteristics of the difficult-to-machine alloy's complex surface, the important problems for further study are presented to realize the finishing of complex surface with the technology of magnetic abrasive finishing, such as increasing the machining efficiency by enhancing the magnetic flux density of machining gap and compounding of magnetic energy and others, establishing of the control function during machining and the process planning method for magnetic abrasive finishing of complex surface under the space geometry restraint of complex surface on magnetic pole, etc.

  14. 40 CFR 425.20 - Applicability; description of the hair save, chrome tan, retan-wet finish subcategory.

    Science.gov (United States)

    2010-07-01

    ... ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS LEATHER TANNING AND FINISHING... cattle-like hides into finished leather by hair save unhairing, chrome tanning, and retan-wet finishing. ...

  15. 76 FR 79221 - Penske Logistics, LLC, Customer Service Department General Motors and Tier Finished Goods...

    Science.gov (United States)

    2011-12-21

    ..., Customer Service Department General Motors and Tier Finished Goods/Finished Goods Division; a Subsidiary of... Manpower El Paso, TX; Amended Certification Regarding Eligibility To Apply for Worker Adjustment Assistance... should read Penske Logistics, LLC, Customer Service Department, General Motors and Tier Finished Goods...

  16. 21 CFR 181.26 - Drying oils as components of finished resins.

    Science.gov (United States)

    2010-04-01

    ... 21 Food and Drugs 3 2010-04-01 2009-04-01 true Drying oils as components of finished resins. 181... Prior-Sanctioned Food Ingredients § 181.26 Drying oils as components of finished resins. Substances classified as drying oils, when migrating from food-packaging material (as components of finished resins...

  17. 40 CFR 63.1347 - Standards for raw and finish mills.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 11 2010-07-01 2010-07-01 true Standards for raw and finish mills. 63... and Operating Limits § 63.1347 Standards for raw and finish mills. The owner or operator of each new or existing raw mill or finish mill at a facility which is a major source subject to the provisions...

  18. 77 FR 12227 - Long Term 2 Enhanced Surface Water Treatment Rule: Uncovered Finished Water Reservoirs; Public...

    Science.gov (United States)

    2012-02-29

    ... Water Treatment Rule: Uncovered Finished Water Reservoirs; Public Meeting AGENCY: Environmental... review of the uncovered finished water reservoir requirement in the Long Term 2 Enhanced Surface Water... uncovered finished water reservoir requirement and the agency's Six Year Review process. EPA also plans to...

  19. The importance of surface finish to energy performance

    Directory of Open Access Journals (Sweden)

    Smith Geoff B.

    2017-01-01

    Full Text Available Power generation in solar energy systems, thermal control in buildings and mitigation of the Urban Heat Island problem, are all sensitive to directional response to incoming radiation. The radiation absorption and emission profile also plays a crucial role in each system's response and depends strongly on surface finish. This important sensitivity needs wider recognition in materials data sheets, system modeling, plus in materials and environmental engineering. The impact of surface roughness on thermal response of natural and man-made external environments is examined. Important examples will be given of the role of surface finish within each class. Total emittance links to the way surface finish influences directional emittance E(θ. Smooth surface thermal emittance on PV module covers, many solar absorbers, some roof paints, polished concrete, and glass windows can be up to 15% different from insulator results based on fully diffuse models of the same material. Widespread evidence indicates smooth metals and low-E solar absorber surfaces cool faster, and smooth insulators slower than previously thought. Matt paint is cooler than low sheen paint under the same solar heating impacts and normal concrete cooler than polished. Emittance for water is the prime environmental example of oblique impacts as it reflects strongly at oblique incidence, which leads to a significant drop in E(θ. Ripples or waves however raise water's average emittance. A surprise in this work was the high sensitivity of total E and its angular components to roughness in the depth range of 0.1–0.8 μm, which are well under ambient thermal IR wavelengths of 3–30 μm but common in metal finishing. Parallel energy flows such as evaporation and convective cooling vary if emittance varies. Thermal image analysis can provide insights into angular radiative effects.

  20. Response of finishing broiler chickens fed three energy/protein ...

    African Journals Online (AJOL)

    A feeding experiment was conducted to investigate the response of finishing broiler chicken to diets containing three metabolizable energy (ME)/crude protein (CP) combinations ( 3203.76 ME vs 19.90 %CP, 2884.15 ME vs 18.10%CP and 2566.42 ME vs 18.10 %CP) at fixed ME:CP ratio of 160:1. A total of 126 four weeks ...

  1. Effect of cleaning products on upholstery leather finishes

    OpenAIRE

    Lara López, Mercedes

    2003-01-01

    The main objective of the project is to investigate the effects of cleaning products on upholstery leather finishes. Focusing on products applicable to upholstery leather cleaning, non-typical leather cleaners (and possible contaminants) or ink removers, in order to find out their behaviour, understanding how they work and if they are suitable for their purpose. Moreover an initial investigation about mechanism of soiling is proposed, in order, in the future, to avoid the soiling or develop a...

  2. Hybrid machining processes perspectives on machining and finishing

    CERN Document Server

    Gupta, Kapil; Laubscher, R F

    2016-01-01

    This book describes various hybrid machining and finishing processes. It gives a critical review of the past work based on them as well as the current trends and research directions. For each hybrid machining process presented, the authors list the method of material removal, machining system, process variables and applications. This book provides a deep understanding of the need, application and mechanism of hybrid machining processes.

  3. Monitoring and control of fine abrasive finishing processes

    DEFF Research Database (Denmark)

    Lazarev, Ruslan

    In engineering, surfaces with specified functional properties are of high demand in various applications. Desired surface finish can be obtained using several methods. Abrasive finishing is one of the most important processes in the manufacturing of mould and dies tools. It is a principal method ...... was segmented using discretization methods. The applied methodology was proposed for implementation as an on-line system and is considered to be a part of the next generation of STRECON NanoRAP machine....... to remove unwanted material, obtain desired geometry, surface quality and surface functional properties. The automation and computerization of finishing processes involves utilisation of robots, specialized machines with several degrees of freedom, sensors and data acquisition systems. The focus...... of this work was to investigate foundations for process monitoring and control methods in application to semi-automated polishing machine based on the industrial robot. The monitoring system was built on NI data acquisition system with two sensors, acoustic emission sensor and accelerometer. Acquired sensory...

  4. Ageing of Dry Cement Mixes for Finishing Purposes

    Directory of Open Access Journals (Sweden)

    Bronius VEKTARIS

    2013-09-01

    Full Text Available Dry building mixes, stored in the air, absorb water vapor and CO2 gas and ageing because properties of binding materials, mostly Portland cement, deteriorate after its prehydration and carbonation. In this paper the ageing singularities of dry cement mixes for finishing purposes and additives for retarding this process has been determinated. Ordinary and quickly hardening Portland cements absorb H2O and CO2 more than white cement – about 70 % – 75 % and 30 % – 38 % per month of innitial mass, respectively. White cement is more resistant to prehydration and carbonation, because it contains less C3A, C4AF and alkali, characterized initial activity. Dry mixes with white cement, although slower, but still worse after stored. Influence of routine dry mortar mixes ingredients and additives (methyl cellulose, pigments, sand and lime on prehydration properties of the mixes for finishing purpose is not substantial. Significant positive influence comes from the addition of fatty acid salts (zinc stearate or sodium oleate. The dry cement mixes for finishing purpose has been recomended to hydrophobisate with one of these additives, adding about 1 % by weight of cement during preducing mixes. DOI: http://dx.doi.org/10.5755/j01.ms.19.3.5243

  5. Ageing of Dry Cement Mixes for Finishing Purposes

    Directory of Open Access Journals (Sweden)

    Bronius VEKTARIS

    2013-09-01

    Full Text Available Dry building mixes, stored in the air, absorb water vapor and CO2 gas and ageing because properties of binding materials, mostly Portland cement, deteriorate after its prehydration and carbonation. In this paper the ageing singularities of dry cement mixes for finishing purposes and additives for retarding this process has been determinated. Ordinary and quickly hardening Portland cements absorb H2O and CO2 more than white cement – about 70 % – 75 % and 30 % – 38 % per month of innitial mass, respectively. White cement is more resistant to prehydration and carbonation, because it contains less C3A, C4AF and alkali, characterized initial activity. Dry mixes with white cement, although slower, but still worse after stored. Influence of routine dry mortar mixes ingredients and additives (methyl cellulose, pigments, sand and lime on prehydration properties of the mixes for finishing purpose is not substantial. Significant positive influence comes from the addition of fatty acid salts (zinc stearate or sodium oleate. The dry cement mixes for finishing purpose has been recomended to hydrophobisate with one of these additives, adding about 1 % by weight of cement during preducing mixes. DOI: http://dx.doi.org/10.5755/j01.ms.19.3.5243

  6. Productive performance of Holstein calves finished in feedlot or pasture

    Directory of Open Access Journals (Sweden)

    ANA MARIA O. DIAS

    Full Text Available ABSTRACT The use of animals from dairy farms is an alternative to meat production since it provides an increment of total income for farmers. This study aims to evaluate the performance of Holstein calves finished in two feeding systems (feedlot or pasture. Forty-three animals with 58 days old and 57 kg were divided in two treatments: 23 animals finished in feedlot with corn silage plus concentrate based on corn and soybean meal (40:60; 20 animals kept in cultivated pastures according to the period of the year: Italian ryegrass (Lolium multiflorum and pearl millet (Pennisetum americanum with supplementation with the same feedlot-concentrate at 1% body weight. Animals were slaughtered with 200 kg. Dry matter and nutrient intake were determined, with the use of chromium oxide for estimating pasture intake. Feedlot animals had greater total intake and total digestible nutrients, resulting in higher average daily gain (0.949 vs 0.694 kg day-1. Crude protein intake, neutral detergent fiber and feed conversion did not show significant differences. Holstein calves have improved performance when finished in feedlot.

  7. Revised nonstochastic health effects models

    International Nuclear Information System (INIS)

    Yaniv, S.S.; Scott, B.R.

    1991-01-01

    In 1989, the U.S. Nuclear Regulatory Commission (NRC) published a revision of the 1985 report, Health Effects Models for Nuclear Power Plant Accident Consequence Analysis, NUREG/CR-4214, that included models for early occurring and continuing nonstochastic effects, cancers and thyroid nodules, and genetic effects. This paper discusses specific models for lethality from early occurring and continuing effects. For brevity, hematopoietic-syndrome lethality is called hematopoietic death; pulmonary-syndrome lethality is called pulmonary death; and gastrointestinal syndrome lethality is called gastrointestinal death. Two-parameter Weibull risk functions are recommended for estimating the risk of hematopoietic, pulmonary, or gastrointestinal death. The risks are obtained indirectly by using hazard functions; as a result, this type of approach has been called hazard-function modeling and the models generated are called hazard-function models. In the 1989 NUREG/CR-4214 report, changes were made in the parameter values for a number of effects, and the models used to estimate hematopoietic and pulmonary deaths were substantially revised. Upper and lower estimates of model parameters are provided for all early health effects models. In this paper, we discuss the 1989 models for hematopoietic and pulmonary deaths, highlighting the differences between the 1989 and 1985 models. In addition, we give the reasons for which the 1985 models were modified

  8. Plan for the Initiation of HA-211 Furnace Operations at the Plutonium Finishing Plan (PFP)

    International Nuclear Information System (INIS)

    WILLIS, H.T.

    2000-01-01

    This plan provides a phased approach authorizing the use of three additional muffle furnaces for thermal stabilization. Achievement of Thermal Stabilization mission elements require the installation and startup of three additional muffle furnaces for the thermal stabilization of plutonium and plutonium bearing materials at the Plutonium Finishing Plant (PFP). The release to operate these additional furnaces will require an Activity Based Startup Review. The conduct of the Activity Based Startup Review (ABSR) was approved by Fluor Daniel Hanford on October 15, 1999. This plan has been developed with the objective of identifying those activities needed to guide the controlled startup of five furnaces from authorization to unrestricted operations by adding the HA-211 furnaces in an orderly and safe manner after the approval to Startup has been given

  9. Acetabular Cup Revision.

    Science.gov (United States)

    Kim, Young-Ho

    2017-09-01

    The use of acetabular cup revision arthroplasty is on the rise as demands for total hip arthroplasty, improved life expectancies, and the need for individual activity increase. For an acetabular cup revision to be successful, the cup should gain stable fixation within the remaining supportive bone of the acetabulum. Since the patient's remaining supportive acetabular bone stock plays an important role in the success of revision, accurate classification of the degree of acetabular bone defect is necessary. The Paprosky classification system is most commonly used when determining the location and degree of acetabular bone loss. Common treatment options include: acetabular liner exchange, high hip center, oblong cup, trabecular metal cup with augment, bipolar cup, bulk structural graft, cemented cup, uncemented cup including jumbo cup, acetabular reinforcement device (cage), trabecular metal cup cage. The optimal treatment option is dependent upon the degree of the discontinuity, the amount of available bone stock and the likelihood of achieving stable fixation upon supportive host bone. To achieve successful acetabular cup revision, accurate evaluation of bone defect preoperatively and intraoperatively, proper choice of method of acetabular revision according to the evaluation of acetabular bone deficiency, proper technique to get primary stability of implant such as precise grafting technique, and stable fixation of implant are mandatory.

  10. Design Process Control for Improved Surface Finish of Metal Additive Manufactured Parts of Complex Build Geometry

    Directory of Open Access Journals (Sweden)

    Mikdam Jamal

    2017-12-01

    Full Text Available Metal additive manufacturing (AM is increasingly used to create complex 3D components at near net shape. However, the surface finish (SF of the metal AM part is uneven, with surface roughness being variable over the facets of the design. Standard post-processing methods such as grinding and linishing often meet with major challenges in finishing parts of complex shape. This paper reports on research that demonstrated that mass finishing (MF processes are able to deliver high-quality surface finishes (Ra and Sa on AM-generated parts of a relatively complex geometry (both internal features and external facets under select conditions. Four processes were studied in this work: stream finishing, high-energy (HE centrifuge, drag finishing and disc finishing. Optimisation of the drag finishing process was then studied using a structured design of experiments (DOE. The effects of a range of finishing parameters were evaluated and optimal parameters and conditions were determined. The study established that the proposed method can be successfully applied in drag finishing to optimise the surface roughness in an industrial application and that it is an economical way of obtaining the maximum amount of information in a short period of time with a small number of tests. The study has also provided an important step in helping understand the requirements of MF to deliver AM-generated parts to a target quality finish and cycle time.

  11. Effects of Fiber Finish on the Performance of Asphalt Binders and Mastics

    Directory of Open Access Journals (Sweden)

    Bradley J. Putman

    2011-01-01

    Full Text Available The objective of this study was to determine the effects of finishes applied to polyester fibers on the properties of asphalt binders and mastics. Asphalt binders were mixed with finishes that were extracted from the fibers, and mastics were also made with binder and fibers (with and without finish to isolate the effects of the finish. The results indicated that crude source plays a significant role in how the fiber finish affects the binders and mastics. Additionally different finishes had different effects on binder properties. The major finding of this study is that different polyester fibers, even from the same manufacturer, may not necessarily perform the same in an asphalt mixture. It is important to use fibers that are compatible with the particular asphalt binder that is being used because of the significance of the binder source on the interaction between the finish and the binder.

  12. Discussion on some issues for HAF003 revision

    International Nuclear Information System (INIS)

    Huang Chaoyun, Wang Xiaotao; Duan Hongwei; Tian Feng

    2013-01-01

    This paper describes some key issues which should be considered during the revision of safety code Quality Assurance for Nuclear Power Plant (HAF003), based on the comparatively analysis and research on the quality assurance practice for nuclear power. It covers about 24 issues including management responsibilities, independent assessment, design control and procurement control etc. and is expected to provide some reference and proposal for HAF003 revision activities organized by National Nuclear Safety Agency (NNSA). (authors)

  13. An interim UK response to revised risk estimates

    International Nuclear Information System (INIS)

    Beaver, P.F.; Bines, W.P.

    1992-01-01

    This paper describes the legal framework in place when the revised risk estimates were announced by the International Commission for Radiological Protection (ICRP) in 1987 and how an addition to that framework enabled the revised risk estimates to be taken into account when making decisions about radiation protection practice both at plant and individual worker level. It is suggested that this a may be an early example of the use of a constraint applied generically. (author)

  14. 76 FR 77025 - Office of New Reactors; Notice of Availability of the Final Staff Guidance Section 1.0, Revision...

    Science.gov (United States)

    2011-12-09

    ... the Final Staff Guidance Section 1.0, Revision 2 on Introduction and Interfaces AGENCY: Nuclear... Plants: LWR Edition,'' Section 1.0, Revision 2 on ``Introduction and Interfaces'' (Agencywide Documents Access and Management System (ADAMS) Accession No. ML112730393). The NRC staff issues revisions to SRP...

  15. Revision of Pachycentria (Melastomataceae)

    NARCIS (Netherlands)

    Clausing, Gudrun

    2000-01-01

    A revision of Pachycentria Blume, which includes the monotypic Pogonanthera Blume, is presented. Pachycentria comprises eight species and one subspecies. Two species, P. vogelkopensis and P. hanseniana, are newly described. The genus is distinguished from other genera in the Medinillinae by a small

  16. Revision of Oxandra (Annonaceae)

    NARCIS (Netherlands)

    Junikka, L.; Maas, P.J.M.; Maas-van de Kamer, H.; Westra, L.Y.Th.

    2016-01-01

    A taxonomic revision is given of the Neotropical genus Oxandra (Annonaceae). Within the genus 27 species are recognized, 4 of which are new to science. Most of the species are occurring in tropical South America, whereas a few (6) are found in Mexico and Central America and two in the West Indies

  17. Revision without ordinals

    NARCIS (Netherlands)

    Rivello, Edoardo

    2013-01-01

    We show that Herzberger’s and Gupta’s revision theories of truth can be recast in purely inductive terms, without any appeal neither to the transfinite ordinal numbers nor to the axiom of Choice. The result is presented in an abstract and general setting, emphasising both its validity for a wide

  18. Revising and editing for translators

    CERN Document Server

    Mossop, Brian

    2014-01-01

    Revising and Editing for Translators provides guidance and learning materials for translation students learning to edit texts written by others, and professional translators wishing to improve their self-revision ability or learning to revise the work of others. Editing is understood as making corrections and improvements to texts, with particular attention to tailoring them to the given readership. Revising is this same task applied to draft translations. The linguistic work of editors and revisers is related to the professional situations in which they work. Mossop offers in-depth coverage of a wide range of topics, including copyediting, style editing, structural editing, checking for consistency, revising procedures and principles, and translation quality assessment. This third edition provides extended coverage of computer aids for revisers, and of the different degrees of revision suited to different texts. The inclusion of suggested activities and exercises, numerous real-world examples, a proposed gra...

  19. EPRI BWR Water Chemistry Guidelines Revision

    International Nuclear Information System (INIS)

    Garcia, Susan E.; Giannelli, Joseph F.

    2014-01-01

    BWRVIP-190: BWR Water Chemistry Guidelines – 2008 Revision has been revised. The revision committee consisted of U.S. and non-U.S. utilities (members of the BWR Vessel and Internals Protection (BWRVIP) Mitigation Committee), reactor system manufacturers, fuel suppliers, and EPRI and industry experts. The revised document, BWRVIP-190 Revision 1, was completely reformatted into two volumes, with a simplified presentation of water chemistry control, diagnostic and good practice parameters in Volume 1 and the technical bases in Volume 2, to facilitate use. The revision was developed in parallel and in coordination with preparation of the Fuel Reliability Guidelines Revision 1: BWR Fuel Cladding Crud and Corrosion. Guidance is included for plants operating under normal water chemistry (NWC), moderate hydrogen water chemistry (HWC-M), and noble metal application (GE-Hitachi NobleChem™) plus hydrogen injection. Volume 1 includes significant changes to BWR feedwater and reactor water chemistry control parameters to provide increased assurance of intergranular stress corrosion cracking (IGSCC) mitigation of reactor materials and fuel reliability during all plant conditions, including cold shutdown (≤200°F (93°C)), startup/hot standby (>200°F (93°C) and ≤ 10%) and power operation (>10% power). Action Level values for chloride and sulfate have been tightened to minimize environmentally assisted cracking (EAC) of all wetted surfaces, including those not protected by hydrogen injection, with or without noble metals. Chemistry control guidance has been enhanced to minimize shutdown radiation fields by clarifying targets for depleted zinc oxide (DZO) injection while meeting requirements for fuel reliability. Improved tabular presentations of parameter values explicitly indicate levels at which actions are to be taken and required sampling frequencies. Volume 2 provides the technical bases for BWR water chemistry control for control of EAC, flow accelerated corrosion

  20. Closed cooling water chemistry guidelines revision

    International Nuclear Information System (INIS)

    McElrath, Joel; Breckenridge, Richard

    2014-01-01

    This second revision of the Closed Cooling Water Chemistry Guideline addresses the use of chemicals and monitoring methods to mitigate corrosion, fouling, and microbiological growth in the closed cooling-water (CCW) systems of nuclear and fossil-fueled power plants. This revision has been endorsed by the utility chemistry community and represents another step in developing a more proactive chemistry program to limit or control closed cooling system degradation with increased consideration of corporate resources and plant-specific design and operating concerns. These guidelines were developed using laboratory data, operating experience, and input from organizations and utilities within and outside of the United States of America. It is the intent of the Revision Committee that these guidelines are applicable to all nuclear and fossil-fueled generating stations around the world. A committee of industry experts—including utility specialists, Institute of Nuclear Power Operations representatives, water-treatment service-company representatives, consultants, a primary contractor, and EPRI staff—collaborated in reviewing available data on closed cooling-water system corrosion and microbiological issues. Recognizing that each plant owner has a unique set of design, operating, and corporate concerns, the Guidelines Committee developed a methodology for plant-specific optimization. The guideline provides the technical basis for a reasonable but conservative set of chemical treatment and monitoring programs. The use of operating ranges for the various treatment chemicals discussed in this guideline will allow a power plant to limit corrosion, fouling, and microbiological growth in CCW systems to acceptable levels. The guideline now includes closed cooling chemistry regimes proven successful in use in the international community. The guideline provides chemistry constraints for the use of phosphates control, as well as pure water with pH control. (author)

  1. Additive manufacturing of reflective optics: evaluating finishing methods

    Science.gov (United States)

    Leuteritz, G.; Lachmayer, R.

    2018-02-01

    Individually shaped light distributions become more and more important in lighting technologies and thus the importance of additively manufactured reflectors increases significantly. The vast field of applications ranges from automotive lighting to medical imaging and bolsters the statement. However, the surfaces of additively manufactured reflectors suffer from insufficient optical properties even when manufactured using optimized process parameters for the Selective Laser Melting (SLM) process. Therefore post-process treatments of reflectors are necessary in order to further enhance their optical quality. This work concentrates on the effectiveness of post-process procedures for reflective optics. Based on already optimized aluminum reflectors, which are manufactured with a SLM machine, the parts are differently machined after the SLM process. Selected finishing methods like laser polishing, sputtering or sand blasting are applied and their effects quantified and compared. The post-process procedures are investigated on their impact on surface roughness and reflectance as well as geometrical precision. For each finishing method a demonstrator will be created and compared to a fully milled sample and among themselves. Ultimately, guidelines are developed in order to figure out the optimal treatment of additively manufactured reflectors regarding their optical and geometrical properties. Simulations of the light distributions will be validated with the developed demonstrators.

  2. TECHNOLOGY FORMING PRICE DISTRIBUTION OF FINISHED GOODS OF LOGISTICS SYSTEM

    Directory of Open Access Journals (Sweden)

    Novikova T. V.

    2015-12-01

    Full Text Available Modern economics has developed a number of areas of the system for controlling the distribution of finished products. However, in domestic and foreign economic literature the mechanisms of logistics approach are not sufficient to provide higher sales of enterprise-producers, that have sales in remote areas. In this study, first, the importance of company-producers and end-users the methods of rational delivery of finished products is considered, and secondly, the approaches to defining the essence and content of the concept of «distribution» are given, in the third, the logistics processes of the distribution system ready products of a particular company-producer are described, fourthly, the technology of one price product delivery was developed and it was shown the economic efficiency (the possible results of the solution of the problem of distribution logistics of its application in the target company. The study showed that there is an opportunity, based on the development and implementation of technologies to reduce the final price of the goods, to develop the company and increase its competitiveness by minimizing costs and increasing return on investment. The results of research extend the knowledge of methodology of system logistics management in the enterprise.

  3. Sensory quality of beef from different finishing diets.

    Science.gov (United States)

    Resconi, V C; Campo, M M; Font i Furnols, M; Montossi, F; Sañudo, C

    2010-11-01

    Beef production under different local husbandry systems might have meat sensory quality implications for the marketing of these products abroad. In order to assess the effect of finishing diet systems on beef quality, a trained sensory taste panel assessed meat aged for 20 days from 80 Uruguayan Hereford steers that were finished on one of the following diets: T1=Pasture [4% of animal live weight (LW)], T2=Pasture [3% LW plus concentrate (0.6% LW)], T3=Pasture [3% LW plus concentrate (1.2% LW)], or T4=Concentrate plus hay ad libitum. Beef odour and flavour intensities decreased with an increase in the energy content of the diet. The meat from T2 had the lowest acid flavour and strange odours intensities. In general, steers fed only concentrate plus hay (T4) produced meat that had an inferior sensory quality because they had more pronounced off-flavours and was tougher. Copyright © 2010 The American Meat Science Association. Published by Elsevier Ltd. All rights reserved.

  4. Revision of Krsko NPP Quality Assurance Plan

    International Nuclear Information System (INIS)

    Biscan, R.; Fifnja, I.; Kavsek, D.

    2012-01-01

    International standards from nuclear power plant operation area are being frequently upgraded and revised in accordance with the continuous improvement philosophy. This philosophy applies also to the area of Quality Assurance, which has also undergone significant improvement since the early 1950s. Besides just nuclear industry, there are also other international quality standards that are being continuously developed and revised, bringing needs for upgrades also in the nuclear application. Since the beginning of Krsko NPP construction, the overall Quality Assurance program and its applicable procedures were in place to assure that all planned and systematic actions necessary to provide adequate confidence that an item or service will satisfy given requirements to quality, are in place. The overall requirements for quality as one of the major objectives for Krsko NPP operation are also set forth in the Updated Safety Analyses Report, the document that serves as a base for operating license. During more than 30 years of Krsko NPP operation, the quality requirements and related documents were revised and upgraded in several attempts. The latest revision 6 of QD-1, Quality Assurance Plan was issued during the year 2011. The bases for the revision were: Changes of the Slovenian regulatory requirements (ZVISJV, JV5, JV9?), Changes of Krsko NPP licensing documents (USAR section 13?), SNSA inspection requirements, Changes of international standards (IAEA, ISO?), Conclusions of first PSR, Implementation of ISO standards in Krsko NPP (ISO14001, ISO17025), Changes of plant procedures, etc. One of the most obvious changes was the enlargement of the QA Plan scope to cover interdisciplinary areas defined in the plant management program MD-1, such as Safety culture, Self-assessment, Human performance, Industrial Safety etc. The attachment of the QA Plan defining relationships between certain standards was also updated to provide matrix for better correlation of requirements of

  5. Revision 2 of the NPP Krsko Decommissioning Program Is Stalled

    International Nuclear Information System (INIS)

    Levanat, I.; Lokner, V.; Rapic, A.; Zeleznik, N.; Kralj, M.

    2012-01-01

    Revision 2 of the joint Slovenian-Croatian Program of NPP Krsko Decommissioning and SF andLILW Disposal was scheduled to be finished and formally approved by the end of 2009, in accordance with the bilateral Agreement on the NPP. Slightly behind the schedule, the Project team completed the entire document during spring of 2010, and in June 2010 drafted a proposal for a peer review of the Program by a dedicated IAEA expert mission. This procedure was agreed upon at the last session (May 2010) of the Intergovernmental Commission for implementation of the Agreement, when the Commission was acquainted with the five scenarios of the Revision 2 and with the estimates of their costs/financing. It was expected that the peer review would be performed soon, and that formal adoption of the Revision 2 would follow. Although in this process of approval some decisions remained to be made by the stakeholders, the Project team did select and recommend one scenario to be used for costing purposes, in order to ensure that most necessary corrections in Program financing would be timely adopted. However, the planned IAEA review was cancelled by the Advisory board, the body nominated by the Commission ''to supervise the activities and resolve the issues raised by the Project team''. By this cancellation, the process of Program revision was effectively stalled, because the Advisory board could not clearly define further course of action: differing views between the Slovenian and the Croatian part of the Advisory board appeared, in particular regarding the set of Program scenarios and regarding the appropriateness of the Revision 2 document for the IAEA review; nonetheless, the Advisory board sent to the Project team a compilation of requests to modify Revision 2 document. The Project team determined that some minor requests were easy to fulfill, but other modifications could only be carried out after changes in the boundary conditions (approved by the Commission), or changes in national

  6. Surface texture of resin-modified glass ionomer cements: effects of finishing/polishing time.

    Science.gov (United States)

    Yap, A U J; Ong, S B; Yap, W Y; Tan, W S; Yeo, J C

    2002-01-01

    This study compared the surface texture of resin-modified glass ionomer cements after immediate and delayed finishing with different finishing/polishing systems. Class V preparations were made on the buccal and lingual/palatal surfaces of 64 freshly extracted teeth. The cavities on each tooth were restored with Fuji II LC (GC) and Photac-Fil Quick (3M-ESPE) according to manufacturers' instructions. Immediately after light-polymerization, gross finishing was done with 8-fluted tungsten carbide burs. The teeth were then randomly divided into four groups of 16 teeth. Half of the teeth in each group were finished immediately, while the remaining half were finished after one-week storage in distilled water at 37 degrees C. The following finishing/polishing systems were employed: (a) Robot Carbides; (b) Super-Snap system; (c) OneGloss and (d) CompoSite Polishers. The mean surface roughness (microm; n=8) in vertical (RaV) and horizontal (RaH) axis was measured using a profilometer. Data was subjected to ANOVA/Scheffe's tests and Independent Samples t-test at significance level 0.05. Ra values were generally lower in both vertical and horizontal axis with delayed finishing/polishing. Although significant differences in RaV and RaH values were observed among several systems with immediate finishing/polishing, only one (Fuji II LC: RaH - Super-Snap < Robot Carbides) was observed with delayed finishing.

  7. Thermal Properties of Anionic Polyurethane Composition for Leather Finishing

    Directory of Open Access Journals (Sweden)

    Olga KOVTUNENKO

    2016-09-01

    Full Text Available Thermal properties of anionic polyurethane composition mixed with collagen product and hydrophilic sodium form of montmorillonite for use in the finishing of leather were studied by thermogravimetric method. The thermal indices of processes of thermal and thermo-oxidative destruction depending on the polyurethane composition were determined. The influence of anionic polyurethane composition on thermal behavior of chromium tanned gelatin films that imitate the leather were studied. APU composition with natural compounds increases their thermal stability both in air and in nitrogen atmosphere due to the formation of additional bonds between active groups of APU, protein and chrome tanning agent as the result of chemical reactions between organic and inorganic parts with the new structure formation.DOI: http://dx.doi.org/10.5755/j01.ms.22.3.10043

  8. Radon Exhalation from some Finishing Materials Frequently used in Syria

    International Nuclear Information System (INIS)

    Shweikani, R.; Raja, G.

    2011-01-01

    Building materials are one of the main radon sources in dwellings. Therefore, the determination of radon exhalation from these materials will help in prediction the existence of dwelling with potential radon risk. Ceramic tiles and marble samples were collected from Syrian local market. The correlation between radon exhalation from these materials and radium-226 content was studied. Results showed that there is no clear relation between radium content and radon exhalation rate, and the exhalation of radon did not exceed the permissible limits of American Environment Protection Agency (EPA). In addition, the additional annual dose from radon and gamma of the natural radioactivity in ceramic and marble when used as finishing materials in houses was also estimated and found to be not exceeding 20 μSv and 35 μSv from radon and gamma respectively. (author)

  9. Radon exhalation from some Finishing Materials frequently used in Syria

    International Nuclear Information System (INIS)

    Shweikani, R.; Raja, G.

    2009-02-01

    Building materials are one of the main radon sources in dwellings. Therefore, the determination of radon exhalation from these materials will help in prediction the existence of dwelling with potential radon risk. Ceramic tiles and marble samples were collected from Syrian local market. The correlation between radon exhalation from these materials and radium-226 content were studied. Results showed that there is no clear relation between radium content and radon exhalation rate, and the exhalation of radon did not exceed the permissible limits of American Environment Protection Agency (EPA). In addition, the additional annual dose from radon and gamma of the natural radioactivity in ceramic and marble when used as finishing materials in houses were also estimated and found to be not exceeding 20 μSv and μ35 Sv from radon and gamma respectively. (author)

  10. Risk factors for intestinal pathogens in Danish finishing pig herds

    DEFF Research Database (Denmark)

    Stege, H.; Jensen, Tim Kåre; Møller, Kristian

    2001-01-01

    The objective of this investigation was to identify risk factors for infection with the intestinal bacteria: Lawsonia intracellularis, Brachyspira hyodysenteriae, Serpulina intermedia, Brachyspira innocens, Brachyspira pilosicoli and swine-pathogenic Escherichia coli (serogroups O138, O139, O141....... intermedia, B. innocens, B. pilosicoli) (OR's = 0.43 and 0.06, respectively). 2. Home-mixed (and/or non-pelleted) feed was associated with reduced prevalences of L. intracellularis and weakly beta -haemolytic spirochetes (OR's = 0.6 and 0.4, respectively). 3. Providing straw to finishers was associated...... with a reduced prevalence of weakly beta -haemolytic spirochetes (OR = 0.28-0.32). 4. Not using antimicrobial growth promoters for piglets was associated with an increased prevalence of S. intermedia (OR = 11.11). 5. Rare occurrence of post-weaning diarrhoea (as opposed to common) was associated...

  11. Research on reducing the edge effect in magnetorheological finishing.

    Science.gov (United States)

    Hu, Hao; Dai, Yifan; Peng, Xiaoqiang; Wang, Jianmin

    2011-03-20

    The edge effect could not be avoided in most optical manufacturing methods based on the theory of computer controlled optical surfacing. The difference between the removal function at the workpiece edge and that inside it is also the primary cause for edge effect in magnetorheological finishing (MRF). The change of physical dimension and removal ratio of the removal function is investigated through experiments. The results demonstrate that the situation is different when MRF "spot" is at the leading edge or at the trailing edge. Two methods for reducing the edge effect are put into practice after analysis of the processing results. One is adopting a small removal function for dealing with the workpiece edge, and the other is utilizing the removal function compensation. The actual processing results show that these two ways are both effective on reducing the edge effect in MRF.

  12. Crude oil and finished fuel storage stability: An annotated review

    Energy Technology Data Exchange (ETDEWEB)

    Whisman, M.L.; Anderson, R.P.; Woodward, P.W.; Giles, H.N.

    1991-01-01

    A state-of-the-art review and assessment of storage effects on crude oil and product quality was undertaken through a literature search by computer accessing several data base sources. Pertinent citations from that literature search are tabulated for the years 1980 to the present. This 1990 revision supplements earlier reviews by Brinkman and others which covered stability publications through 1979 and an update in 1983 by Goetzinger and others that covered the period 1952--1982. For purposes of organization, citations are listed in the current revision chronologically starting with the earliest 1980 publications. The citations have also been divided according to primary subject matter. Consequently 11 sections appear including: alternate fuels, gasoline, distillate fuel, jet fuel, residual fuel, crude oil, biodegradation, analyses, reaction mechanisms, containment, and handling and storage. Each section contains a brief narrative followed by all the citations for that category.

  13. Nutritional plans of digestible lysine for growing-finishing gilts

    Directory of Open Access Journals (Sweden)

    Gabriel Cipriano Rocha

    2014-09-01

    Full Text Available This experiment was conducted to evaluate nutritional plans of digestible lysine (DLys for growing-finishing gilts. Eighty gilts with 63 days of age and an initial weight of 24.2±1.52 kg were distributed in a completely randomized block design, with five nutritional plans of DLys (9-8-7, 10-9-8, 11-10-9, 12-11-10, and 13-12-11 g/kg, from 63 to 103, 104 to 133, and 134 to 153 days of age, respectively and eight replicates. Pigs were housed in pairs and fed their respective diets ad libitum throughout the experimental period (90 days. To monitor the animal development along the experiment at 103 and 133 days, gilts were weighed and subjected to analysis of ultrasound for evaluation of loin depth (longissimus dorsi and backfat thickness. At the end of the experiment (153 days of age the animals were weighed, and after slaughter carcasses were evaluated individually using a typifying pistol to evaluate the percentage and the content of carcass meat, loin depth and backfat thickness. From 63 to 133 days, there was no effect of the nutritional plans on daily feed intake, performance, or backfat thickness; however the loin depth was greater in the gilts that received plans with high levels of DLys (12-11; 13-12 g/kg compared with the plan with the lowest level (8-7 g/kg. For the entire period (63 to 153 days, no influence of the nutritional plans was observed on the daily feed intake, performance variables, or carcass characteristics. A nutritional plan containing 9-8-7 g/kg of digestible lysine fed from 63 to 103, 104 to 133 and 134 to 153 days, respectively, meets the requirements for performance and carcass characteristics of growing-finishing gilts.

  14. Methods for implementing revisions to emergency operating procedures. Final report

    International Nuclear Information System (INIS)

    Myers, L.B.; Bell, A.J.

    1984-05-01

    In response to the Three Mile Island (TMI) accident, the US Nuclear Regulatory Commission (NRC) has published the TMI Action Plan. The TMI Action Plan Item I.C.1 called for the upgrading of Emergency Operating Procedures (EOPs) at nuclear power plants. The program developed from this Action Plan item has resulted in utility efforts to: (1) revise EOPs; (2) train personnel in the use of the EOPs; and (3) implement the revised EOPs. The NRC supported the study presented in this report to identify factors which influence the effectiveness of training and implementation of revised EOPs. The NRC's major concern was the possible effects of negative transfer of training. The report includes a summary of existing methods for implementing revisions to procedures based on interviews of plant personnel, a review of the training literature applicable to the effect of previously learned procedures on the learning of and performance with revised procedures (i.e., negative transfer) and recommendations of methods and schedules for implementing revised EOPs. While the study found that the concern over negative transfer of training was not as great as anticipated, several recommendations were made. These include: (1) overtraining of operators to reduce the effect of observed negative transfer; and (2) implementation of the revised EOPs as soon as possible after training to minimize the time operators must rely upon the old EOPs after having been trained on the revised EOPs. The results of the study should be useful both to the utilities and the NRC in the development and review of EOP implementation programs

  15. Analysis of Failure to Finish a Race in a Cohort of Thoroughbred Racehorses in New Zealand

    Directory of Open Access Journals (Sweden)

    Jasmine Tanner

    2016-05-01

    Full Text Available The objective was to describe the incidence of failure to finish a race in flat-racing Thoroughbreds in New Zealand as these are summary indicators of falls, injuries and poor performance. Retrospective data on six complete flat racing seasons (n = 188,615 race starts of all Thoroughbred flat race starts from 1 August 2005 to 31 July 2011 were obtained. The incidence of failure to finish events and binomial exact 95% confidence intervals were calculated per 1000 horse starts. The association between horse-, rider- and race-level variables with the outcomes failure to finish, pulled-up/fell and lost rider were examined with a mixed effects Poisson regression model. A total of 544 horses failed to finish in 188,615 race starts with an overall incidence of 2.88 per 1000 horse starts (95% CI 2.64–3.12. The incidence of failure to finish horses across each race year showed little variability. In the univariable analysis race distance, larger field size, season, and ratings bands showed association with failing to finish a race. The overall failure to finish outcome was associated with season, race distance and ratings bands (horse experience and success ranking criteria. In the multivariable analysis, race distance and ratings bands were associated with horses that pulled-up/fell; season, apprentice allowances and ratings bands were associated with the outcome lost rider. The failure to finish rate was lower than international figures for race day catastrophic injury. Racing and environmental variables were associated with failure to finish a race highlighting the multifactorial nature of race-day events. Further investigation of risk factors for failure to finish is required to better understand the reasons for a low failure to finish rate in Thoroughbred flat races in New Zealand.

  16. A European longitudinal study in Salmonella seronegative and seropositive-classified finishing pig herds

    DEFF Research Database (Denmark)

    Wong, Danilo Lo Fo; Dahl, J.; Wingstrand, Anne

    2004-01-01

    and was performed between October 1996 and May 1999. The Salmonella status of finishing pig herds was determined by an initial blood sampling of approximately 50 finishing pigs close to market weight per herd. The development of the Salmonella status of the selected herds was assessed at seven subsequent sampling...

  17. Fatty acid metabolism and deposition in subcutaneous adipose tissue of pasture and feedlot finished cattle

    Science.gov (United States)

    An experiment was conducted to evaluate the effects of pasture finishing versus high-concentrate finishing, over time, on fatty acid metabolism in Angus crossbred (n = 24) steers. Ruminal fluid, serum, and adipose tissue biopsies were obtained on d 0, 28, 84, and 140. Pasture forages and diet ingr...

  18. 40 CFR 63.5390 - How do I measure the HAP content of a finish?

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 12 2010-07-01 2010-07-01 true How do I measure the HAP content of a... Initial Compliance Requirements § 63.5390 How do I measure the HAP content of a finish? (a) To determine the HAP content of a finish, the reference method is EPA Method 311 of appendix A of 40 CFR part 63...

  19. 77 FR 61025 - Certain Prepregs, Laminates, and Finished Circuit Boards: Notice of Institution of Formal...

    Science.gov (United States)

    2012-10-05

    ... INTERNATIONAL TRADE COMMISSION [Inv. No. 337-TA-659] Certain Prepregs, Laminates, and Finished..., and the sale within the United States after importation of certain prepregs, laminates, and finished... for sale, and selling for importation into the United States prepregs and laminates that are the...

  20. "Miss! I'm Done!" Finishing Craft Assignments as a Situated Activity System in Preschool

    Science.gov (United States)

    Deunk, Marjolein; Berenst, Jan; de Glopper, Kees

    2010-01-01

    We describe the Situated Activity System of finishing craft assignments in preschool: the specific, routinized way that child and teacher jointly close the child's craft assignment, employing a specific discourse pattern. We analyzed the interactions of 14 Dutch children between 2.1 and 3.10 years old while they were finishing their craft…

  1. Effects of roughage inclusion and particle size on performance and rumination behavior of finishing beef steers

    Science.gov (United States)

    Roughage is mechanically processed to increase digestibility, and handling and mixing characteristics in finishing diets. Roughage is fed to promote rumen health and decrease digestive upset, but inclusion in finishing diets is limited due to the cost per unit of energy. Rumination behavior may be a...

  2. Surface morphology changes of acrylic resins during finishing and polishing phases

    Directory of Open Access Journals (Sweden)

    Glaucio Serra

    2013-12-01

    Full Text Available INTRODUCTION: The finishing and polishing phases are essential to improve smoothness and shining on the surface of acrylic resins used to make removable orthodontic appliances. A good surface finishing reduces roughness, which facilitates hygiene, prevents staining and provides greater comfort to the patients. OBJECTIVE: The aim of this paper was to analyze the changes on surface morphology of acrylic resins during finishing and polishing phases. METHODS: Thirty discs (10 mm in diameter and 5 mm in length were made with acrylic resin and randomly divided into ten groups. The control group did not receive any treatment while the other groups received gradual finishing and polishing. The last group received the entire finishing and polishing procedures. Surface morphology was qualitatively analyzed through scanning electron microscopy and quantitatively analyzed through a laser profilometer test. RESULTS: The acrylic resin surfaces without treatment showed bubbles which were not observed in the subsequent phases. Wearing out with multilaminated burs, finishing with wood sandpaper and finishing with water sandpaper resulted in surfaces with decreasing irregularities. The surfaces that were polished with pumice and with low abrasive liquids showed high superficial smoothness. CONCLUSION: Highly smooth acrylic resin surfaces can be obtained after mechanical finishing and polishing performed with multilaminated burs, wood sandpaper, water sandpaper, pumice and low abrasive liquids.

  3. DEVELOPMENT OF THE U.S. EPA'S METAL FINISHING FACILITY POLLUTION PREVENTION TOOL

    Science.gov (United States)

    Metal finishing processes are a type of chemical processes and can be modeled using Computer Aided Process Engineering (CAPE). Currently, the U.S. EPA is developing the Metal Finishing Facility Pollution Prevention Tool (MFFP2T), a pollution prevention software tool for the meta...

  4. Effects of time of change from broiler starter to broiler finisher diet on ...

    African Journals Online (AJOL)

    A study was conducted to determine the effect of time of change from broiler starter ration (BSR) to broiler finisher ration (BFR) on growth performance and economy of gain of meat- type chickens. Six hundred Abor Acres broiler chickens were used in an 8-week study in which same starter and finisher diets were fed but at ...

  5. Radiation protection planning and management during revision

    International Nuclear Information System (INIS)

    Gewehr, K.

    1984-01-01

    During the operation of nuclear power plants it is normally possible for the in-house personnel to take care of arising radiation protection problems. However, in the comparatively short revision phases, the duties of radiation protection become much more varied. Additional trained radiation protection crews are needed at short notice. This is also the time in which the largest contributions are made to the annual cumulated doses of the personnel. Recent guidelines and rules trying to reduce the radiation exposure of personnel concentrate on this very point. The article outlines the radiation protection activities performed by the service personnel in the course of a steam generator check. (orig.) [de

  6. Meat goat kids finished on alfalfa, red clover or orchardgrass pastures: carcass merit and meat quality.

    Science.gov (United States)

    Turner, K E; Cassida, K A; Zerby, H N

    2014-12-01

    This experiment was conducted in 2005-2007 to evaluate carcass and chevon (goat meat) quality parameters when meat-goat kids (n=72) were finished on alfalfa (Medicago sativa L; ALF); red clover (Trifolium pratense L.; RCG); or orchardgrass (Dactylis glomerata L.; OGR) pastures. Carcass conformation score was greater (P=0.08) when meat-goat kids were finished on ALF compared to OGR with RCG intermediate. Chevon meat samples from goats finished on the three pasture treatments did not differ in ash, intramuscular fat, or crude protein content or in concentrations of omega6 and omega3 fatty acids, or the omega6 to omega3 ratio. Goats finished on OGR had higher (Pmeat-goat kids finished on ALF, RCG, or ORG produced desirable carcass weights for most niche markets in the USA. Chevon is a low-fat meat option with high desirable fatty acids for human diets. Published by Elsevier Ltd.

  7. Occurrence of 1,4-dioxane in cosmetic raw materials and finished cosmetic products.

    Science.gov (United States)

    Black, R E; Hurley, F J; Havery, D C

    2001-01-01

    Surveys of cosmetic raw materials and finished products for the presence of the carcinogen 1,4-dioxane have been conducted by the U.S. Food and Drug Administration since 1979. Analytical methods are described for the determination of 1,4-dioxane in ethoxylated cosmetic raw materials and cosmetic finished products. 1,4-Dioxane was isolated by azeotropic atmospheric distillation and determined by gas chromatography using n-butanol as an internal standard. A solid-phase extraction procedure based on a previously published method for the determination of 1,4-dioxane in cosmetic finished products was also used. 1,4-Dioxane was found in ethoxylated raw materials at levels up to 1410 ppm, and at levels up to 279 ppm in cosmetic finished products. Levels of 1,4-dioxane in excess of 85 ppm in children's shampoos indicate that continued monitoring of raw materials and finished products is warranted.

  8. Comparison of gene expression and fatty acid profiles in concentrate and forage finished beef.

    Science.gov (United States)

    Buchanan, J W; Garmyn, A J; Hilton, G G; VanOverbeke, D L; Duan, Q; Beitz, D C; Mateescu, R G

    2013-01-01

    Fatty acid profiles and intramuscular expression of genes involved in fatty acid metabolism were characterized in concentrate- (CO) and forage- (FO) based finishing systems. Intramuscular samples from the adductor were taken at slaughter from 99 heifers finished on a CO diet and 58 heifers finished on a FO diet. Strip loins were obtained at fabrication to evaluate fatty acid profiles of LM muscle for all 157 heifers by using gas chromatography fatty acid methyl ester analysis. Composition was analyzed for differences by using the General Linear Model (GLM) procedure in SAS. Differences in fatty acid profile included a greater atherogenic index, greater percentage total MUFA, decreased omega-3 to omega-6 ratio, decreased percentage total PUFA, and decreased percentage omega-3 fatty acids in CO- compared with FO-finished heifers (P0.05). Upregulation was observed for PPARγ, fatty acid synthase (FASN), and fatty acid binding protein 4 (FABP4) in FO-finished compared with CO-finished heifers in both atherogenic index categories (P<0.05). Upregulation of diglyceride acyl transferase 2 (DGAT2) was observed in FO-finished heifers with a HAI (P<0.05). Expression of steroyl Co-A desaturase (SCD) was upregulated in CO-finished heifers with a LAI, and downregulated in FO-finished heifers with a HAI (P<0.05). Expression of adiponectin (ADIPOQ) was significantly downregulated in CO-finished heifers with a HAI compared with all other categories (P<0.05). The genes identified in this study which exhibit differential regulation in response to diet or in animals with extreme fatty acid profiles may provide genetic markers for selecting desirable fatty acid profiles in future selection programs.

  9. 78 FR 55118 - Seismic Instrumentation for Nuclear Power Plants

    Science.gov (United States)

    2013-09-09

    ... NUCLEAR REGULATORY COMMISSION [NRC-2013-0202] Seismic Instrumentation for Nuclear Power Plants... Reports for Nuclear Power Plants: LWR Edition,'' Section 3.7.4, ``Seismic Instrumentation.'' DATES: Submit... Nuclear Power Plants: LWR Edition'' (SRP, from the current Revision 2 to a new Revision 3). The proposed...

  10. Interface Control Document Between the Double Shell Tanks (DST) System and the Plutonium Finishing Plan (PFP)

    International Nuclear Information System (INIS)

    MAY, T.H.

    1999-01-01

    This document identifies the requirements and responsibilities for all parties to support waste transfer from the Plutonium Finishing Plant (PFP) facility to the Double-Shell Tank (DST) System of the River Protection Project (RPP). This Interface Control Document (ICD) will not attempt to control the physical portion of this interface because the physical equipment making up this interface, and any associated interface requirements, are already in place, operational and governed by existing operating specifications and other documentation. The PFP and DST Systems have a direct physical interface (the waste transfer pipeline) that travels between the 241-2 Building (TK-D5) and DST SY-102 via 244-TX double-contained receiver tank (DCRT). The purpose of the ICD process is to formalize working agreements between the RPP DST System and organization/companies internal and external to RPP. This ICD has been developed as part of the requirements basis for design of the DST System to support the Phase I Privatization effort

  11. Novel finishing concepts within BNFL'S advanced reprocessing programme

    Energy Technology Data Exchange (ETDEWEB)

    Hobbs, J.W.; Booth, R.; Lawson, S.; Parkes, P. [BNFL British Nuclear Fuels, Sellafield, Seascale, Cumbria, Research and Technology (United Kingdom)

    2000-07-01

    New methods of converting actinide nitrate solutions to oxide and fabricating the products from the reprocessing of high burn up and MOX fuels are necessary for the next generation of fuel cycle facilities in order to meet dose criteria and cost reduction targets. Options to support this include never fully separating the plutonium from the uranium and reducing decontamination factors. The product stream from such a reprocessing plant will require a finishing route capable of significant levels of automation and dose minimization. Casting of molten uranyl nitrate into pellets followed by de-nitration under vacuum has been investigated as a novel way of manufacturing oxide fuel pellets. Pellets were successfully cast over a range of temperatures and de-nitrated. Incorporation of uranium oxide into the melt was investigated to increase the density of the cast pellet. It has been demonstrated that it is possible to produce extrudates from powder and molten magnesium nitrate mixtures. Results of a preliminary study of the flow behaviour during extrusion of magnesium nitrate simulant loaded with alumina powder are also discussed. (authors)

  12. HEU/LEU-conversion of BER II successfully finished

    International Nuclear Information System (INIS)

    Haas, K.; Fischer, C.-O.; Krohn, H.

    2000-01-01

    The BER II (Berliner Experimental Reactor) research reactor is a swimming pool type reactor located in Berlin, Germany. The reactor operates with a thermal power of 10 MW and is primarily used to produce neutrons for neutron scattering experiments. The conversion from HEU- to LEU-fuel elements began in August, 1997. At the last RERTR Meeting 1999 in Budapest, Hungary, Hahn-Meitner-Institut (HMI) presented a 'Status Report' on the conversion of 10 HEU/LEU mixed cores. In February 2000, HMI finished the HEU/LEU-conversion. Hereby, the first pure LEU-standard-core went into operation. Our second LEU-core just ends its operation at the end of July. The third LEU-core will be built up in the beginning of August. The average burn-up rate was improved from 50 - 55% (HEU) to 60 - 65% (LEU). Therefore, only 14 elements/year are now used instead of 28/year. The following report describes our first steps in building pure LEU-cores from mixed HEU/LEU-cores, as well as our initial experience using the pure LEU-cores. (author)

  13. Finishing procedures in Orthodontics: dental dimensions and proportions (microesthetics

    Directory of Open Access Journals (Sweden)

    Roberto Carlos Bodart Brandão

    2013-10-01

    Full Text Available OBJECTIVE: The objective of the present article is to describe procedures that can be performed to achieve excellence in orthodontic treatment finishing. The content is limited to microesthetics, which comprises the concept of ideal dental dimensions and proportions (white esthetics and its correlation with the periodontium (pink esthetics. Standards of normality are described both in their real dimensions (dental height and width, and in those effectively perceived by the observer, the virtual dimensions. METHODS: The best scientific evidence was sought in the literature to support the clinical procedures that must guide the professional to obtain maximum esthetic quality on their treatments. Therefore, it is necessary to investigate what the other specialties in Dentistry expect from Orthodontics and, specially, what they have to offer. Clinical cases will be used to illustrate the dental movement that might maximize treatment outcome and to confront the ideal standards with the current state of the art. CONCLUSION: Treatment quality is directly related to the amount of procedures implemented by the orthodontist, associated with concepts and resources from Periodontics and Dental Prosthesis. Microesthetics cannot be seen in isolation, but rather as the key to establish a pleasant smile (miniesthetics in addition to a harmonious face (macroesthetics and a human being with high self-esteem (hyper-esthetics.

  14. Evaluation of different finish line designs in base metal alloys

    Directory of Open Access Journals (Sweden)

    Aghandeh R

    1999-06-01

    Full Text Available This investigation was performed according to the widespread application of base metal alloys"nand few articles published about the marginal integrity of restorations fabricated by these metals."nThree standard dies of a maxillary first premolar were prepared with a flat shoulder finish line in buccal"naspect and chamfer in palatal. One of them left with no change. On the buccal aspect of the second and"nthird dies 135?and 1607 bevel were added respectively"nUsing dual wax technique, nine wax patterns were formed on each die and casting procedure of selected"nnon precious alloy was performed by centrifugal method. Marginal gaps of each copping seated on dies"nwere measured by scanning electron microscope (SEM with X500 magnification. Measurements were"ndone on three areas of marked dies on buccal aspect. Measurement son palatal aspect was done on"nmarked midpalatal point as control."nResults and statistical analysis showed no significant difference among marginal gaps in lingual aspect."nBut on the buccal aspect there were statistically significant differences among the groups (P<0.001. Flat"nshoulder had the best marginal integrity (mean 4 micron. Shoulder with 160' bevel had the most marginal"ngap (mean 26.5 micron and shoulder with 1357 bevel was between two other groups (mean 15.7 micron.

  15. Classification and storage of wastewater from floor finish removal operations

    Energy Technology Data Exchange (ETDEWEB)

    Hunt, Charles E. [Univ. of San Francisco, CA (United States)

    1996-05-01

    This study evaluates the wastewater generated from hard surface floor finish removal operations at Lawrence Livermore Laboratory in order to determine if this wastewater is a hazardous waste, either by statistical evaluation, or other measurable regulatory guidelines established in California Regulations. This research also comparatively evaluates the 55 gallon drum and other portable tanks, all less than 1,000 gallons in size in order to determine which is most effective for the management of this waste stream at Lawrence Livermore Laboratory. The statistical methods in SW-846 were found to be scientifically questionable in their application to hazardous waste determination. In this statistical evaluation, the different data transformations discussed in the regulatory guidance document were applied along with the log transformation to the population of 18 samples from 55 gallon drums. Although this statistical evaluation proved awkward in its application, once the data is collected and organized on a spreadsheet this statistical analysis can be an effective tool which can aid the environmental manager in the hazardous waste classification process.

  16. Improvement of hydroforming processes using tailored semi-finished tubes

    Energy Technology Data Exchange (ETDEWEB)

    Goebel, R.; Chatti, S.; Homberg, W.; Kleiner, M.; Shankar, R. [Dortmund Univ. (Germany). Inst. of Forming Technology and Lightweight Construction

    2005-07-01

    The manufacturing of curved tubular workpieces with complex geometry by hydroforming is a well known process. The formability of workpieces is limited by the overall amount of expansion, which always has to start with the smallest perimeter. Especially workpieces with a high ratio between the smallest and widest diameter are critical with regard to their manufacture. To improve the capability the hydroforming process, a new concept using tailored semi-finished tubes with a variable cross-section has been developed. Instead of only expanding a tube with the smallest diameter, the diameter of a tube with middle-sized cross-section is reduced locally by a spinning process so that only the critical regions left have to be expanded. Due to the fact that usually the pre-form has to be bent to assure that it fits into the tool, an additional specialized tube-bending process has been developed to realize the bending of tubes with variable diameter. In this article, the investigation and optimization of this process chain is presented. The capabilities of the process have been improved regarding the behavior of the workpieces in the hydroforming process by manufacturing a complex structural part originating from automotive industry. (orig.)

  17. Draft revision of human factors guideline HF-010

    International Nuclear Information System (INIS)

    Lee, Hyun Chul; Lee, Yong Hee; Oh, In Seok; Lee, Jung Woon; Cha, Woo Chang; Lee, Dhong Ha

    2003-05-01

    The Application of Human Factors to the design of Man-Machine Interfaces System(MMIS) in the nuclear power plant is essential to the safety and productivity of the nuclear power plants, human factors standards and guidelines as well as human factors analysis methods and experiments are weightily used to the design application. A Korean engineering company has developed a human factors engineering guideline, so-call HF-010, and has used it for human factors design, however the revision of HF-010 is necessary owing to lack of the contents related to the advanced MMI(Man-Machine Interfaces). As the results of the reviews of HF-010, it is found out that the revision of Section 9. Computer Displays of HF-010 is urgent, thus the revision was drafted on the basis of integrated human factors design guidelines for VDT, human factors design guidelines for PMAS SPADES display, human factors design guidelines for PMAS alarm display, and human factors design guidelines for electronic displays developed by the surveillance and operation support project of KOICS. The draft revision of HF-010 Section 9 proposed in this report can be utilized for the human factors design of the advanced MMI, and the high practical usability of the draft can be kept up through the continuous revision according to the advancement of digital technology

  18. Revised Rules for Concrete Bridges

    DEFF Research Database (Denmark)

    Thoft-Christensen, Palle; Jensen, F. M.; Middleton, C.

    This paper is based on research performed for the Highway Agency, London, UK under the project DPU/9/44 "Revision of Bridge Assessment Rules Based on Whole Life Performance: Concrete Bridges" It contains details of a methodology which can be used to generate Whole Life (WL) reliability profiles....... These WL reliability profiles may be used to establish revised rules for Concrete Bridges....

  19. Emotion Processes in Knowledge Revision

    Science.gov (United States)

    Trevors, Gregory J.; Kendeou, Panayiota; Butterfuss, Reese

    2017-01-01

    In recent years, a number of insights have been gained into the cognitive processes that explain how individuals overcome misconceptions and revise their previously acquired incorrect knowledge. The current study complements this line of research by investigating the moment-by-moment emotion processes that occur during knowledge revision using a…

  20. SURFACE FINISHES ON STAINLESS STEEL REDUCE BACTERIAL ATTACHMENT AND EARLY BIOFILM FORMATION: SCANNING ELECTRON AND ATOMIC FORCE MICROSCOPY STUDY

    Science.gov (United States)

    Three common finishing treatments of stainless steel that are used for equipment during poultry processing were tested for resistance to bacterial contamination. Methods were developed to measure attached bacteria and to identify factors that make surface finishes susceptible or ...

  1. Revised SRAC code system

    International Nuclear Information System (INIS)

    Tsuchihashi, Keichiro; Ishiguro, Yukio; Kaneko, Kunio; Ido, Masaru.

    1986-09-01

    Since the publication of JAERI-1285 in 1983 for the preliminary version of the SRAC code system, a number of additions and modifications to the functions have been made to establish an overall neutronics code system. Major points are (1) addition of JENDL-2 version of data library, (2) a direct treatment of doubly heterogeneous effect on resonance absorption, (3) a generalized Dancoff factor, (4) a cell calculation based on the fixed boundary source problem, (5) the corresponding edit required for experimental analysis and reactor design, (6) a perturbation theory calculation for reactivity change, (7) an auxiliary code for core burnup and fuel management, etc. This report is a revision of the users manual which consists of the general description, input data requirements and their explanation, detailed information on usage, mathematics, contents of libraries and sample I/O. (author)

  2. Microcomputers and the Improvement of Revision Skills.

    Science.gov (United States)

    Balajthy, Ernest; And Others

    1987-01-01

    Discusses use of word processing software as an effective tool in writing and revision instruction, and describes the role of the teacher. Examples of exercises that encourage revision and of software designed to teach effective revision skills are reviewed. (MBR)

  3. Local public document room directory. Revision 7

    International Nuclear Information System (INIS)

    1998-04-01

    This directory (NUREG/BR-0088, Revision 7) lists local public document rooms (LPDRs) for commercial nuclear power plants with operating or possession-only licenses or under construction, plus the LPDRs for potential high-level radioactive waste repository sites, gaseous diffusion plants, certain fuel cycle facilities, certain low-level waste disposal facilities, and any temporary LPDRs established for the duration of licensing proceedings. In some instances, the LPDR libraries maintain document collections for more than one licensed facility. The library staff members listed are the persons most familiar with the LPDR collections. Reference librarians in the NRC Headquarters Public Document Room (PDR) are also available to assist the public in locating NRC documents

  4. Engineering drawing field verification program. Revision 3

    International Nuclear Information System (INIS)

    Ulk, P.F.

    1994-01-01

    Safe, efficient operation of waste tank farm facilities is dependent in part upon the availability of accurate, up-to-date plant drawings. Accurate plant drawings are also required in support of facility upgrades and future engineering remediation projects. This supporting document establishes the procedure for performing a visual field verification of engineering drawings, the degree of visual observation being performed and documenting the results. A copy of the drawing attesting to the degree of visual observation will be paginated into the released Engineering Change Notice (ECN) documenting the field verification for future retrieval and reference. All waste tank farm essential and support drawings within the scope of this program will be converted from manual to computer aided drafting (CAD) drawings. A permanent reference to the field verification status will be placed along the right border of the CAD-converted drawing, referencing the revision level, at which the visual verification was performed and documented

  5. Study on interfacial reaction between lead-free solders and alternative surface finishes

    International Nuclear Information System (INIS)

    Siti Rabiatul Aisha; Ourdjini, A.; Saliza Osman

    2007-01-01

    This study investigates the interfacial reactions occurring during reflow soldering between Sn-Ag-Cu lead-free solder and two surface finishes: electroless nickel/ immersion gold (ENIG) and immersion silver (IAg). The study focuses on interfacial reactions evolution and growth kinetics of intermetallic compounds (IMC) formed during soldering and isothermal ageing at 150 degree Celsius for up to 2000 hours. Optical and scanning electron microscopy were used to measure IMC thickness and examine the morphology of IMC respectively, whereas the IMC phases were identified by energy dispersive X-ray analysis (EDX). The results showed that the IMC formed on ENIG finish is thinner compared to that formed on IAg finish. For IAg surface finish, Cu 6 Sn 5 IMCs with scallop morphology are formed at the solder/ surface finish interface after reflow while a second IMC, Cu 3 Sn was formed between the copper and Cu 6 Sn 5 IMC after the isothermal ageing treatment. For ENIG surface finish both (Cu,Ni) 6 Sn 5 and (Ni,Cu) 3 Sn 4 are formed after soldering. Isothermal aging of the solder joints formed on ENIG finish was found to have a significant effect on the morphology of the intermetallics by transforming to more spherical and denser morphology in addition to increase i their thickness with increased ageing time. (author)

  6. Resource Conservation and Recovery Act, Part B permit application [of the Waste Isolation Pilot Plant (WIPP)]. Volume 11, Chapter D, Appendix D4--Chapter D, Appendix D17: Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    1993-03-01

    This volume contains appendices D4 through D17 which cover the following: Waste Isolation Pilot Plant site environmental report; ecological monitoring program at the Waste Isolation Pilot Plant; site characterization; regional and site geology and hydrology; general geology; dissolution features; ground water hydrology; typical carbon sorption bed efficiency; VOC monitoring plan for bin-room tests; chemical compatibility analysis of waste forms and container materials; probable maximum precipitation; WHIP supplementary roof support system room 1, panel 1; and corrosion risk assessment of the Waste Isolation Pilot Plant ``humid`` test bins.

  7. Design and Feasibility Testing of the truth FinishIt Tobacco Countermarketing Brand Equity Scale.

    Science.gov (United States)

    Evans, W Douglas; Rath, Jessica; Pitzer, Lindsay; Hair, Elizabeth C; Snider, Jeremy; Cantrell, Jennifer; Vallone, Donna

    2016-07-01

    The original truth campaign was a branded, national smoking prevention mass media effort focused on at-risk youth ages 12-17. Today the truth brand focuses on the goal of finishing tobacco (truth FinishIt). There have been significant changes in the tobacco control landscape, leading FinishIt to focus on 15- to 21-year-olds. The present article reports on formative research and media monitoring data collected to pilot test a new truth FinishIt brand equity scale. The goals of this study were to (a) content analyze truth FinishIt mass media ads, (b) assess truth's social media and followers' perceptions of truth's digital brand identity, and (c) develop and feasibility test a new version of the truth FinishIt brand equity scale using data from an existing Truth Initiative media monitoring study. Through factor analysis, we identified a brand equity scale, as in previous research, consisting of 4 main constructs: brand loyalty, leadership/satisfaction, personality, and awareness. Targeted truth attitudes and beliefs about social perceptions, acceptability, and industry-related beliefs were regressed on the higher order factor and each of the 4 individual brand equity factors. Ordinary least squares regression models generally showed associations in the expected directions (positive for anti-tobacco and negative for pro-tobacco) between targeted attitudes/beliefs and truth FinishIt brand equity. This study succeeded in developing and validating a new truth FinishIt brand equity scale. The scale may be a valuable metric for future campaign evaluation. Future studies should examine the effects of truth FinishIt brand equity on tobacco use behavioral outcomes over time.

  8. Efficacy of 2 finishing protocols in the quality of orthodontic treatment outcome.

    Science.gov (United States)

    Stock, Gregory J; McNamara, James A; Baccetti, Tiziano

    2011-11-01

    The objectives of this prospective clinical study were to evaluate the quality of treatment outcomes achieved with a complex orthodontic finishing protocol involving serpentine wires and a tooth positioner, and to compare it with the outcomes of a standard finishing protocol involving archwire bends used to detail the occlusion near the end of active treatment. The complex finishing protocol sample consisted of 34 consecutively treated patients; 1 week before debonding, their molar bands were removed, and serpentine wires were placed; this was followed by active wear of a tooth positioner for up to 1 month after debonding. The standard finishing protocol group consisted of 34 patients; their dental arches were detailed with archwire bends and vertical elastics. The objective grading system of the American Board of Orthodontics was used to quantify the quality of the finish at each time point. The Wilcoxon signed rank test was used to compare changes in the complex finishing protocol; the Mann-Whitney U test was used to compare changes between groups. The complex finishing protocol group experienced a clinically significant improvement in objective grading system scores after treatment with the positioner. Mild improvement in posterior space closure was noted after molar band removal, but no improvement in the occlusion was observed after placement of the serpentine wires. Patients managed with the complex finishing protocol also had a lower objective grading system score (14.7) at the end of active treatment than did patients undergoing the standard finishing protocol (23.0). Tooth positioners caused a clinically significant improvement in interocclusal contacts, interproximal contacts, and net objective grading system score; mild improvement in posterior band space was noted after molar band removal 1 week before debond. Copyright © 2011 American Association of Orthodontists. Published by Mosby, Inc. All rights reserved.

  9. Inclusion of Tarchonanthus camphoratus in finishing diets for lambs

    African Journals Online (AJOL)

    Die insluiting van 20, 30, 40 en 50% TarcJwnanthus camphoratus ... verlaging in die skynbare verteerbaarheid van droe material1 en .... minimum 0,8% fat. .... Determination of plant cell wall ... The effects of frequency of feeding on milk.

  10. 40 CFR 425.10 - Applicability; description of the hair pulp, chrome tan, retan-wet finishing subcategory.

    Science.gov (United States)

    2010-07-01

    ... ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS LEATHER TANNING AND FINISHING... addition to other unhairing and tanning operation, processes raw or cured cattle or cattle-like hides into finished leather by chemically dissolving the hide hair, chrome tanning, and retan-wet finishing. ...

  11. DEVELOPING A CAPE-OPEN COMPLIANT METAL FINISHING FACILITY POLLUTION PREVENTION TOOL (CO-MFFP2T)

    Science.gov (United States)

    The USEPA is developing a Computer Aided Process Engineering (CAPE) software tool for the metal finishing industry that helps users design efficient metal finishing processes that are less polluting to the environment. Metal finishing process lines can be simulated and evaluated...

  12. Wavelet theory and belt finishing process, influence of wavelet shape on the surface roughness parameter values

    International Nuclear Information System (INIS)

    Khawaja, Z; Mazeran, P-E; Bigerelle, M; Guillemot, G; Mansori, M El

    2011-01-01

    This article presents a multi-scale theory based on wavelet decomposition to characterize the evolution of roughness in relation with a finishing process or an observed surface property. To verify this approach in production conditions, analyses were developed for the finishing process of the hardened steel by abrasive belts. These conditions are described by seven parameters considered in the Tagushi experimental design. The main objective of this work is to identify the most relevant roughness parameter and characteristic length allowing to assess the influence of finishing process, and to test the relevance of the measurement scale. Results show that wavelet approach allows finding this scale.

  13. SEM Evaluation of Surrounding Enamel after Finishing of Composite Restorations- Preliminary Results

    Science.gov (United States)

    Iovan, G.; Stoleriu, S.; Solomon, S.; Ghiorghe, A.; Sandu, A. V.; Andrian, S.

    2017-06-01

    The purpose of this study was to analyze the surface characteristics of the enamel adjacent to composite resin after finishing the restoration with different diamond and tungsten carbide burs. The topography of enamel was observed by using a scanning electron microscope. Finishing with extra-/ultra-fine carbide burs, and extra-fine diamond burs resulted in smooth surfaces. In few areas some superficial scratches with no clinical relevance were observed. Deep grooves were observed on the surface of enamel when fine diamond burs were used. Finishing of composite restorations with coarse burs should be avoided when there is a high risk of touching and scratching adjacent enamel during the procedure.

  14. Study on waste waters of metal finishing industries around Lahore metropolitan area

    International Nuclear Information System (INIS)

    Khan, Izhar-ul-Haq; Mahmood, F.; Tufail, S.; Naeem, M.

    2002-01-01

    Study was undertaken on the waste water samples from metal finishing industries of Lahore metropolitan area for the evaluation of metallic impurities. The metal finishing industry was classified into three categories i. e. medium scale, small scale and cottage scale industry. About 93 wastewater samples were collected from various metal finishing industries around Lahore metropolitan area. In addition to toxic elements like cadmium, nickel and zinc the other parameters such as hydrogen ion concentration (pH), Electrical conductivity (EC) and Total Dissolved Salts (TDS) were also determined. (author)

  15. Interaction of dispersed polyvynil acetate with silicate in finishing materials

    Directory of Open Access Journals (Sweden)

    Runova, R. F.

    1996-12-01

    Full Text Available This article focuses on the processes of interaction between calcium silicate hydrates and dispersed polyvinyl acetate in tight films with the aim of developing compounds meant for restoration and finishing works. The basis of this development relies on the concept concerning the determining role of the crystal-chemical factor of the silicate phase in the formation of organic-mineral compounds of increased durability. The characteristics of dispersed calcium silicate hydrates are portrayed. The preparation conditions, accounting for the synthesis of the product of submicrocrystalline structure, conforming with the stoichiometry CaO∙SiO2 =0.8-2.0 have been determined. The interaction has been studied for compounds achieved by mixing ingredients in a rapid whirling mixer, and subjected to hardening at T=20+2 T. With the aid of XRD, DTA and Infra-Red Spectrometry methods the formation process of the sophisticated polymer silicate phase in the material was observed for a period of 90 days. The properties of the film were investigated and its high resistance against the influence of external factors was established. On this basis a conclusion concerning the quite high effectiveness of substituting portland cement with dispersed calcium silicate hydrate in polymer cement compounds has been made. White colour and other various special properties determine the suitability for repair and finishing works on facades of buildings.

    Este artículo está orientado a estudiar los procesos de interacción entre los silicatos cálcicos hidratados y el acetato de polivinilo disperso en capas impermeables, con el objeto de desarrollar compuestos destinados para la restauración. El fundamento de estos estudios es determinar el papel que los factores cristaloquímicos de las fases silicato tienen en la formación de compuestos órganominerales de elevada durabilidad. Se han descrito las características de los silicatos cálcicos hidratados

  16. Resource Conservation and Recovery Act, Part B Permit Application [for the Waste Isolation Pilot Plant (WIPP)]. Volume 2, Chapter C, Appendix C1--Chapter C, Appendix C3 (beginning), Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    1993-03-01

    This volume contains appendices for the following: Rocky Flats Plant and Idaho National Engineering Laboratory waste process information; TRUPACT-II content codes (TRUCON); TRUPACT-II chemical list; chemical compatibility analysis for Rocky Flats Plant waste forms; chemical compatibility analysis for waste forms across all sites; TRU mixed waste characterization database; hazardous constituents of Rocky Flats Transuranic waste; summary of waste components in TRU waste sampling program at INEL; TRU waste sampling program; and waste analysis data.

  17. A study on scar revision

    Directory of Open Access Journals (Sweden)

    Ashutosh Talwar

    2016-04-01

    Full Text Available Introduction: Scars are psychologically distressing for the patients and have an impact on the quality of life and self esteem of the patients. Scar revision is an aesthetic skill which is mastered by plastic surgeons and encroached now by dermatosurgeons. Scars on the face are aesthetically unacceptable and various techniques have been improvised for making a scar aesthetically acceptable. Various types of techniques are used for scar revision like W plasty, Z plasty and VY plasty. Aims: To see the efficacy of various scar revision techniques including Z plasty, VY plasty and W plasty in 30 patients with disfiguring scars. Methods: We selected twenty patients of disfiguring scars for the study. The scars from various causes including trauma and burns were included in our study. Various techniques of scar revision include Z plasty, W plasty and VY plasty were performed according to the type and site of scar. Results: Male: female was 1.5: 1. The scar revision surgery yielded excellent results with minimal complications including haematoma formation, secondary infection and delayed healing seen in 5% patients each. Regarding the efficacy of scar revision, excellent improvement was seen in 60% patients, moderate improvement was seen in 30% patients and mild improvement was seen in 10% patients. Conclusions: Dermatologists can employ a number of surgical scar revision techniques. While some are better suited to treat specific types of scars, they can be used in combination with each other or with adjunctive therapies to achieve optimal results.

  18. The Tiger Team Process in the Rebaselining of the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    BAILEY, R.W.

    2000-01-01

    This paper will describe the integrated, teaming approach and planning process utilized by the Tiger Team in the development of the IPMP. This paper will also serve to document the benefits derived from this implementation process

  19. Update on the Department of Energy's 1994 plutonium vulnerability assessment for the plutonium finishing plant

    International Nuclear Information System (INIS)

    HERZOG, K.R.

    1999-01-01

    A review of the environmental, safety, and health vulnerabilities associated with the continued storage of PFP's inventory of plutonium bearing materials and other SNM. This report re-evaluates the five vulnerabilities identified in 1994 at the PFP that are associated with SNM storage. This new evaluation took a more detailed look and applied a risk ranking process to help focus remediation efforts

  20. Plutonium Finishing Plant (PFP) Generalized Geometry Holdup Calculations and Total Measurement Uncertainty

    International Nuclear Information System (INIS)

    Keele, B.D.

    2005-01-01

    A collimated portable gamma-ray detector will be used to quantify the plutonium content of items that can be approximated as a point, line, or area geometry with respect to the detector. These items can include ducts, piping, glove boxes, isolated equipment inside of gloveboxes, and HEPA filters. The Generalized Geometry Holdup (GGH) model is used for the reduction of counting data. This document specifies the calculations to reduce counting data into contained plutonium and the associated total measurement uncertainty.

  1. Plutonium Finishing Plant (PFP) Criticality Alarm System Commercial Grade Item (CGI) Critical Characteristics

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for PFP's criticality alarm system as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics for any one item. PFP's Criticality Alarm System includes the nine criticality alarm system panels and their associated hardware. This includes all parts up to the first breaker in the electrical distribution system. Specific system boundaries and justifications are contained in HNF-SD-CP-SDD-003, ''Definition and Means of Maintaining the Criticality Detectors and Alarms Portion of the PFP Safety Envelope.'' The procurement requirements associated with the system necessitates procurement of some system equipment as Commercial Grade Items in accordance with HNF-PRO-268, ''Control of Purchased Items and Services.''

  2. ALARA Design Review for the Resumption of the Plutonium Finishing Plant (PFP) Cementation Process Project Activities

    CERN Document Server

    Dayley, L

    2000-01-01

    The requirements for the performance of radiological design reviews are codified in 10CFR835, Occupational Radiation Protection. The basic requirements for the performance of ALARA design reviews are presented in the Hanford Site Radiological Control Manual (HSRCM). The HSRCM has established trigger levels requiring radiological reviews of non-routine or complex work activities. These requirements are implemented in site procedures HNF-PRO-1622 and 1623. HNF-PRO-1622 Radiological Design Review Process requires that ''radiological design reviews [be performed] of new facilities and equipment and modifications of existing facilities and equipment''. In addition, HNF-PRO-1623 Radiological Work Planning Process requires a formal ALARA Review for planned activities that are estimated to exceed 1 person-rem total Dose Equivalent (DE). The purpose of this review is to validate that the original design for the PFP Cementation Process ensures that the principles of ALARA (As Low As Reasonably Achievable) were included...

  3. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex

  4. The composition of semi-finished inventories at a solid board plant

    NARCIS (Netherlands)

    Wanders, H.L.T.; Gaalman, G.J.C.; Sierksma, G.

    2004-01-01

    A solid board factory produces rectangular sheets of cardboard in two different formats, namely large formats and small formats. The production process consists of two stages separated by an inventory point. In the first stage, a cardboard machine produces the large formats. In the second stage a

  5. Integrated Safety Management System Phase I Verification for the Plutonium Finishing Plant (PFP) [VOL 1 & 2

    Energy Technology Data Exchange (ETDEWEB)

    SETH, S.S.

    2000-01-10

    U.S. Department of Energy (DOE) Policy 450.4, Safety Management System Policy commits to institutionalizing an Integrated Safety Management System (ISMS) throughout the DOE complex as a means of accomplishing its missions safely. DOE Acquisition Regulation 970.5204-2 requires that contractors manage and perform work in accordance with a documented safety management system.

  6. Facility Effluent Monitoring Plan for the Plutonium Finishing Plant (PFP); FINAL

    International Nuclear Information System (INIS)

    FRAZIER, T.P.

    1999-01-01

    A facility effluent monitoring plan is required by the U. S. Department of Energy in DOE Order 5400.1 for any operations that involve hazardous materials and radioactive substances that could impact employee or public safety or the environment. This facility effluent monitoring plan assesses effluent monitoring systems and evaluates whether these systems are adequate to ensure the public health and safety as specified in applicable federal, state, and local requirements. To ensure the long-range integrity of the effluent monitoring systems, an update to this facility effluent monitoring plan is required whenever a new process or operation introduces new hazardous materials or significant radioactive materials. This document is reviewed annually even if there are no operational changes, and is updated, at a minimum, every 3 years

  7. Basic Soils. Revision.

    Science.gov (United States)

    Montana State Univ., Bozeman. Dept. of Agricultural and Industrial Education.

    This curriculum guide is designed for use in teaching a course in basic soils that is intended for college freshmen. Addressed in the individual lessons of the unit are the following topics: the way in which soil is formed, the physical properties of soil, the chemical properties of soil, the biotic properties of soil, plant-soil-water…

  8. Concentration data for anthropogenic organic compounds in groundwater, surface water, and finished water of selected community water systems in the United States, 2002-10

    Science.gov (United States)

    Carter, Janet M.; Kingsbury, James A.; Hopple, Jessica A.; Delzer, Gregory C.

    2010-01-01

    The National Water-Quality Assessment Program of the U.S. Geological Survey began implementing Source Water-Quality Assessments (SWQAs) in 2001 that focus on characterizing the quality of source water and finished water of aquifers and major rivers used by some of the larger community water systems in the United States. As used in SWQA studies, source water is the raw (ambient) water collected at the supply well before water treatment (for groundwater) or the raw (ambient) water collected from the river near the intake (for surface water), and finished water is the water that has been treated and is ready to be delivered to consumers. Finished-water samples are collected before the water enters the distribution system. The primary objective of SWQAs is to determine the occurrence of more than 250 anthropogenic organic compounds in source water used by community water systems, many of which currently are unregulated in drinking water by the U.S. Environmental Protection Agency. A secondary objective is to understand recurrence patterns in source water and determine if these patterns also occur in finished water before distribution. SWQA studies were conducted in two phases for most studies completed by 2005, and in one phase for most studies completed since 2005. Analytical results are reported for a total of 295 different anthropogenic organic compounds monitored in source-water and finished-water samples collected during 2002-10. The 295 compounds were classified according to the following 13 primary use or source groups: (1) disinfection by-products; (2) fumigant-related compounds; (3) fungicides; (4) gasoline hydrocarbons, oxygenates, and oxygenate degradates; (5) herbicides and herbicide degradates; (6) insecticides and insecticide degradates; (7) manufacturing additives; (8) organic synthesis compounds; (9) pavement- and combustion-derived compounds; (10) personal-care and domestic-use products; (11) plant- or animal-derived biochemicals; (12) refrigerants and

  9. Fiber Finishes for Improving Galvanic Resistance of Imide-Based Composites

    National Research Council Canada - National Science Library

    Allred, R. E

    1998-01-01

    The objective of this program is the development and demonstration of galvanic corrosion resistant carbon/ BMI composites through the use of reactive finishes to form coatings that isolate the carbon...

  10. Radiation technology in finishing process improves health, safety and environment (HSE) in the furniture manufacturing industry

    International Nuclear Information System (INIS)

    Ahmad Shakri Mat Seman

    1999-01-01

    In furniture manufacturing, processes like cross cutting, molding, planning, shaping, turning, assembling and finishing are involved. The most significant types of negative impact of these processes are such as dust emission, noise, hazardous work, health risk, emission of organic solvent, toxic chemicals emission and chemical waste. In the finishing process, a number of negative effects that will cause health, safety and environmental (HSE) performance. This article highlights the environmental problems in the furniture finishing processes and how the radiation technology can reduce these negative impacts. The drawbacks that hamper the manufacturers from adopting this technology are also discussed. The objective of the paper is to create the awareness among the industrialist and consumers on the HSE hazardous in furniture finishing and steps can be taken to improve

  11. DESIGN OF FILL AND FINISH FACILITY FOR ACTIVE PHARMACEUTICAL INGREDIENTS (API

    Directory of Open Access Journals (Sweden)

    NUUR LAILA KHAIRUDDIN

    2016-08-01

    Full Text Available Fill and finish operations continue to be one of the most heavily outsourced activities in the biopharmaceutical manufacturing market today. There are a few aspects that need to be consider in outsource activities like logistic, storage condition, facility certification and audit as regulations and standards which the manufacturer should adhere. Risk would be greater and extra care should be taken when outsource from foreign fill and finish facility. Thus, the internal aseptic fill and finish facility with audit checklist will help to minimize the risk during logistic and storage and also minimize the cost for outsource fill and finish facility. The data collections are through survey and conceptual design with simulation as the execution part.

  12. Conservation of filtering in manufacturing systems with unreliable machines and finished goods buffers

    Directory of Open Access Journals (Sweden)

    Jingshan Li

    2006-01-01

    nature of manufacturing systems, this law offers a tool for selecting the smallest, that is, lean, finished goods buffering, which is necessary and sufficient to ensure the desired level ofcustomer demand satisfaction.

  13. The Affordable Pre-Finishing of Silicon Carbide for Optical Applications, Phase I

    Data.gov (United States)

    National Aeronautics and Space Administration — Creare proposes to develop a novel, laser-assisted, pre-finishing process for chemical vapor deposition (CVD) coated silicon-carbide ceramics. Our innovation will...

  14. Reliability of lead-free solder joints with different PCB surface finishes under thermal cycling

    Energy Technology Data Exchange (ETDEWEB)

    Xia Yanghua [State Key Laboratory of Functional Materials for Informatics, Shanghai Institute of Microsystem and Information Technology, Chinese Academy of Sciences, Shanghai 200050 (China)], E-mail: xia_yanghua@hotmail.com; Xie Xiaoming [State Key Laboratory of Functional Materials for Informatics, Shanghai Institute of Microsystem and Information Technology, Chinese Academy of Sciences, Shanghai 200050 (China)

    2008-04-24

    The reliability of lead-free electronic assemblies under thermal cycling was investigated. Thin small outline package (TSOP) devices with FeNi leads were reflow soldered on FR4 PCB (printed circuit board) with Sn3.0Ag0.5Cu (wt%) solder. The effects of different PCB finishes (organic solderability preservative (OSP) and electroless nickel immersion gold (ENIG)) were studied. The results show that OSP finish reveals better performance than its ENIG counterparts. The crack originates at the fringe of heel fillet in both cases. The propagation of crack in the ENIG case is along the device/solder interface, while in the case of OSP, the crack extends parallel to the solder/PCB interface. When the OSP finishes are employed, many Cu6Sn5 precipitates form inside the bulk solder and have a strengthening effect on the solder joint, resulting in better reliability performance as compared to those with ENIG finishes.

  15. Revision of ASCE 4

    International Nuclear Information System (INIS)

    Nelson, T.A.; Murray, R.C.; Short, S.A.

    1995-01-01

    The original version of ASCE Standard 4, ''Seismic Analysis of Safety-Related Nuclear Structures'' was published in September 1986. It is ASCE policy to update its standards on a five year interval and the Working Group on Seismic Analysis of Safety Related Nuclear Structures was reconvened to formulate the revisions. The goal in updating the standard is to make sure that it is still relevant and that it incorporates the state of the practice in seismic engineering or, in some cases, where it has been demonstrated that state-of-the-art improvements need to be made to standard practice; new improvements are included. The contents of the new standard cover the same areas as the original version, with some additions. The contents are as follows: Input - response spectra and time histories; modeling of structures; analysis of structures; soil-structure interaction; input for subsystem analysis; special structures - buried pipes and conduits, earth-retaining walls, above-ground vertical tanks, raceways, and base-isolated structures; and an appendix providing seismic probabilistic risk assessment and margin assessment

  16. Contact activation: a revision.

    Science.gov (United States)

    Schmaier, A H

    1997-07-01

    In conclusion, a revised view of the contact system has been presented. This system has little to do with the initiation of hemostasis. Like lupus anticoagulants, deficiencies of contact proteins give prolonged APTTs but may be risk factors for thrombosis. BK from kininogens is a potent modulator of vascular biology inducing vasodilation, tissue plasminogen activator release, and prostacyclin liberation. Kininogens, themselves, are selective inhibitors of alpha-thrombin-induced platelet activation preventing alpha-thrombin from cleaving the cloned thrombin receptor after arginine41. Kininogens' alpha-thrombin inhibitory activity exists in intact kininogens, BK, and all of BK's breakdown products. HK also is the pivotal protein for contact protein assembly on endothelium. It is the receptor for prekallikrein which when bound to HK becomes activated to kallikrein by an endothelial cell enzyme system independent of activated forms of plasma factor XII. Prekallikrein activation on endothelial cells results in kinetically favorable single chain urokinase and plasminogen activation. Thus the "physiologic, negatively charged surface" for contact system activation is really the assembly of these proteins on cell membranes and activation by membrane-associated enzymes.

  17. Revised accident source terms and control room habitability

    International Nuclear Information System (INIS)

    Lahti, G.P.; Hubner, R.S.; Johnson, W.J.; Schwartz, B.C.

    1993-01-01

    In April 1992, the NRC staff presented to the Commissioners the draft NUREG open-quotes Revised Accident Source Terms for Light-Water Nuclear Power Plants.close quotes This document is the culmination of more than ten years of NRC-sponsored research and represents the first change in the NRC's position on source terms since TID-14844 was issued in 1962. The purpose of this paper is to investigate the impact of the revised source terms on the current approach to analyzing control room habitability as required by 10 CFR 50. Sample calculations are presented that identify aspects of the model requiring clarification before the implementation of the revised source terms. 6 refs., 4 tabs

  18. Drivers of Finished-Goods Inventory in the U.S. Automobile Industry

    OpenAIRE

    Gérard P. Cachon; Marcelo Olivares

    2010-01-01

    Automobile manufacturers in the U.S. supply chain exhibit significant differences in their days of supply of finished vehicles (average inventory divided by average daily sales rate). For example, from 1995 to 2004, Toyota consistently carried approximately 30 fewer days of supply than General Motors. This suggests that Toyota's well-documented advantage in manufacturing efficiency, product design, and upstream supply chain management extends to their finished-goods inventory in their downstr...

  19. Effects of the truth FinishIt brand on tobacco outcomes

    OpenAIRE

    Evans, W. Douglas; Rath, Jessica M.; Hair, Elizabeth C.; Snider, Jeremy Williams; Pitzer, Lindsay; Greenberg, Marisa; Xiao, Haijun; Cantrell, Jennifer; Vallone, Donna

    2017-01-01

    Since 2000, the truth campaign has grown as a social marketing brand. Back then, truth employed branding to compete directly with the tobacco industry. In 2014, the launch of truth FinishIt reflected changes in the brand's strategy, the tobacco control environment, and youth/young adult behavior.Building on a previous validation study, the current study examined brand equity in truth FinishIt, as measured by validated multi-dimensional scales, and tobacco related attitudes, beliefs, and behav...

  20. DESIGN OF FILL AND FINISH FACILITY FOR ACTIVE PHARMACEUTICAL INGREDIENTS (API)

    OpenAIRE

    NUUR LAILA KHAIRUDDIN; NORLIZA ABD. RAHMAN; NUR SYAFIQAH KAMARUDIN

    2016-01-01

    Fill and finish operations continue to be one of the most heavily outsourced activities in the biopharmaceutical manufacturing market today. There are a few aspects that need to be consider in outsource activities like logistic, storage condition, facility certification and audit as regulations and standards which the manufacturer should adhere. Risk would be greater and extra care should be taken when outsource from foreign fill and finish facility. Thus, the internal aseptic fill and fin...

  1. Study on mycoflora of poultry feed ingredients and finished feed in Iran

    OpenAIRE

    Seyed Soheil Ghaemmaghami; Mehrdad Modirsaneii; Alireza Khosravi; Mehdi Razzaghi-Abyaneh

    2016-01-01

     Background and Objectives: Unhygienic poultry feedstuffs can lead to nutrient losses and detrimental effect on poultry production and public health. In the present study, mycobiota and colony-forming units per gram in ingredients and finish poultry feed was evaluated with special reference to potentially mycotoxigenic fungi.Materials and Methods: Eighty five samples of corn, soybean meal and poultry finished feed were collected from nine poultry feed factories located in three provinces i.e....

  2. Effects of finishing/polishing techniques on microleakage of resin-modified glass ilonomer cement restorations.

    Science.gov (United States)

    Yap, Adrian U J; Yap, W Y; Yeo, Egwin J C; Tan, Jane W S; Ong, Debbie S B

    2003-01-01

    This study investigated the effect of finishing/polishing techniques on the microleakage of resin-modified glass ionomer restorations. Class V preparations were made on the buccal and lingual/palatal surfaces of freshly extracted teeth. The cavities on each tooth were restored with Fuji II LC (FT [GC]) and Photac-Fil Quick (PF [3M-ESPE]) according to manufacturers' instructions. Immediately after light-polymerization, gross finishing was done with eight-fluted tungsten carbide burs. The teeth were then randomly divided into four groups and finishing/polishing was done with one of the following systems: (a) Robot Carbides (RC); (b) Super-Snap system (SS); (c) OneGloss (OG) and (d) CompoSite Polishers (CS). The sample size for each material-finishing/polishing system combination was eight. After finishing/polishing, the teeth were stored in distilled water at 37 degrees C for one week. The root apices were then sealed with acrylic and two coats of varnish was applied 1 mm beyond the restoration margins. The teeth were subsequently subjected to dye penetration testing (0.5% basic fuchsin), sectioned and scored. Data was analyzed using Kruskal-Wallis and Mann-Whitney U tests at a significance level of 0.05. Results of statistical analysis were as follows: Enamel margins: PF-OGfinishing/polishing technique, leakage at dentin margins was significantly greater than at enamel margins for FT. For PF, no significant difference in leakage scores was observed between dentin and enamel with the exception of finishing/polishing with OG. FT restorations had significantly less enamel and dentin leakage than PF restorations when treated with OG. The effect of finishing/polishing techniques on microleakage was both tissue and material dependent.

  3. Circumcision revision in male children

    Directory of Open Access Journals (Sweden)

    Mohammed A. Al-Ghazo

    2006-08-01

    Full Text Available OBJECTIVE: To determine indications for circumcision revision and to identify the specialty of the person who performed unsatisfactory primary circumcision. MATERIALS AND METHODS: The authors reviewed medical records of 52 cases that underwent circumcision revision over a 6-year period (1998 to 2004. Sleeve surgical technique was used for revision in patients with redundant foreskin or concealed penis, penoplasty for partial or complete degloving of the penis and meatotomy for external meatal stenosis. The mean age of children was 32 months (range 6 months to 9 years. RESULTS: Most of unsatisfactory primary circumcisions (86.7% were performed by laymen. All patients who underwent circumcision revision had good to excellent cosmetic results. CONCLUSION: Primary circumcision performed by laymen carry a high complication rate and serious complications may occur. A period of training and direct supervision by physicians is required before allowing laymen to perform circumcision independently.

  4. EPR first responders revision test

    International Nuclear Information System (INIS)

    2011-01-01

    In this revision test evaluates the acquired knowledge in case of radiological emergency confront. Actions to be taken in relation to people, equipment and the environment. Doses, radioactive sources, pollution

  5. Corporate Author Entries. Revision 5

    International Nuclear Information System (INIS)

    Hendricks, P.L.

    1986-05-01

    This reference authority has been created and is maintained to provide standard forms for recording the names of organizations consistently in bibliographic citations. This revision includes approximately 42,000 entries established since 1973

  6. Surface finish and subsurface damage in polycrystalline optical materials

    Science.gov (United States)

    Shafrir, Shai Negev

    We measure and describe surface microstructure and subsurface damage (SSD) induced by microgrinding of hard metals and hard ceramics used in optical applications. We examine grinding of ceramic materials with bonded abrasives, and, specifically, deterministic microgrinding (DMG). DMG, at fixed nominal infeed rate and with bound diamond abrasive tools, is the preferred technique for optical fabrication of ceramic materials. In DMG material removal is by microcracking. DMG provides cost effective high manufacturing rates, while attaining higher strength and performance, i.e., low level of subsurface damage (SSD). A wide range of heterogeneous materials of interest to the optics industry were studied in this work. These materials include: A binderless tungsten carbide, nonmagnetic Ni-based tungsten carbides, magnetic Co-based tungsten carbides, and, in addition, other hard optical ceramics, such as aluminum oxynitride (Al23O27N5/ALON), polycrystalline alumina (Al2O3/PCA), and chemical vapor deposited (CVD) silicon carbide (Si4C/SiC). These materials are all commercially available. We demonstrate that spots taken with magnetorheological finishing (MRF) platforms can be used for estimating SSD depth induced by the grinding process. Surface morphology was characterized using various microscopy techniques, such as: contact interferometer, noncontact white light interferometer, light microscopy, scanning electron microscopy (SEM), and atomic force microscopy (AFM). The evolution of surface roughness with the amount of material removed by the MRF process, as measured within the spot deepest point of penetration, can be divided into two stages. In the first stage the induced damaged layer and associated SSD from microgrinding are removed, reaching a low surface roughness value. In the second stage we observe interaction between the MRF process and the material's microstructure as MRF exposes the subsurface without introducing new damage. Line scans taken parallel to the MR

  7. Revised accident source terms for light-water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Soffer, L. [Nuclear Regulatory Commission, Washington, DC (United States)

    1995-02-01

    This paper presents revised accident source terms for light-water reactors incorporating the severe accident research insights gained in this area over the last 15 years. Current LWR reactor accident source terms used for licensing date from 1962 and are contained in Regulatory Guides 1.3 and 1.4. These specify that 100% of the core inventory of noble gases and 25% of the iodine fission products are assumed to be instantaneously available for release from the containment. The chemical form of the iodine fission products is also assumed to be predominantly elemental iodine. These assumptions have strongly affected present nuclear air cleaning requirements by emphasizing rapid actuation of spray systems and filtration systems optimized to retain elemental iodine. A proposed revision of reactor accident source terms and some im implications for nuclear air cleaning requirements was presented at the 22nd DOE/NRC Nuclear Air Cleaning Conference. A draft report was issued by the NRC for comment in July 1992. Extensive comments were received, with the most significant comments involving (a) release fractions for both volatile and non-volatile species in the early in-vessel release phase, (b) gap release fractions of the noble gases, iodine and cesium, and (c) the timing and duration for the release phases. The final source term report is expected to be issued in late 1994. Although the revised source terms are intended primarily for future plants, current nuclear power plants may request use of revised accident source term insights as well in licensing. This paper emphasizes additional information obtained since the 22nd Conference, including studies on fission product removal mechanisms, results obtained from improved severe accident code calculations and resolution of major comments, and their impact upon the revised accident source terms. Revised accident source terms for both BWRS and PWRS are presented.

  8. SEABEE Combat Handbook. Revision

    Science.gov (United States)

    1989-02-01

    broad with strong spines that give them the appearance of a horned steer. The seed within the horny structure may be roasted or boiled. (See fig. 16-8...cats, hedgehogs , porcupines, and value per pound than those derived from plants. badgers should be skinned and gutted before You can increase your...for the fractures and for shock. A fractured spine RELIEF OF PAIN must be immobilized before the victim is moved at all, if further injuries are to be

  9. Guidelines and workbook for of organization and administration of utilities seeking operating license for a nuclear power plant. Workbook for assessment of organization and management. Volume, 2, Revision 1

    International Nuclear Information System (INIS)

    Thurber, J.A.; Olson, J.; Osborn, R.N.; Sommers, P.; Widrig, R.D.

    1986-09-01

    This report is a partial response to the requirements of Item I.B.1.1 of the ''NRC Action Plan Developed as a Result of the TMI-2 Accident,'' NUREG-0660, and is designed to serve as a basis for replacing the earlier NUREG-0731, ''Guidelines for Utility Management Structure and Technical Resources.'' The Guidelines are intended to provide guidance to the user in preparing a written plan for a proposed nuclear organization and administration. The purpose of the Workbook is to guide the NRC reviewer through a systematic review and assessment of a proposed organization and administration. It is the NRC's intention to incorporate these Guidelines and Workbook into a future revision of the Standard Review Plan (SRP), NUREG-0800. However, at this time the report is being published so that the material may be used on a voluntary basis by industry to systematically prepare or evaluate their organization or administration plans. Use of the report by the NRC would not occur until after it has been incorporated in the SRP

  10. Guidelines and workbook for assessment of organization and administration of utilities seeking operating license for a nuclear power plant. Guidelines for utility organization and administration plan. Volume 1, Revision 1

    International Nuclear Information System (INIS)

    Thurber, J.A.; Olson, J.; Osborn, R.N.; Sommers, P.; Widrig, R.D.

    1986-09-01

    Volumes 1 and 2 of this report are a partial response to the requirements of Item I.B.1.1 of the ''NRC Action Plan Developed as a Result of the TMI-2 Accident,'' NUREG-0660, and are designed to serve as a basis for replacing the earlier NUREG-0731, ''Guidelines for Utility Management Structure and Technical Resources.'' These Guidelines are intended to provide guidance to the user in preparing a written plan for a proposed nuclear organization and administration. The purpose of the Workbook (Vol. 2) is to guide the NRC reviewer through a systematic review and assessment of a proposed organization and administration. It is the NRC's intention to incorporate these Guidelines and Workbook into a future revision of the Standard Review Plan (SRP), NUREG-0800. However, at this time the report is being published so that the material may be used on a voluntary basis by industry to systematically prepare or evaluate their organization or administration plans. Use of the report by the NRC would not occur until after it has been incorpoarted in the SRP

  11. Poultry offal ensiled with lactobacillus acidophilus for growing and finishing swine diets.

    Science.gov (United States)

    Tibbetts, G W; Seerley, R W; McCampbell, H C

    1987-01-01

    Poultry offal (heads, feet, viscera) from a broiler processing plant was ground and mixed with corn, dried molasses and a Lactobacillus acidophilus culture. Fermentation was shown to be effective in batch sizes of 3.8, 75.7 and 208.1 liters, as well as a 1,360-kg silo. It was generally complete at 72 h. In trial 1, rats were fed silage mixtures of 60:30:5:5, 45:45:5:5 and 30:60:5:5, offal, corn, molasses and inoculant, respectively. Rats did not gain as well when fed the silage diets (P less than .05) as when fed the basal diet; however, the ranking of silages was 45:45, 60:30 and 30:60, offal-to-corn ratio for rat daily gains and feed conversions. In trial 2, growing-finishing pigs were fed the 60:30:5:5 silage at rates of 0, 10, 20 and 30% of the diet. Average daily gains and feed-to-gain ratios were not affected by including offal silage at up to 20% of the diet, but 30% offal silage in diets resulted in depressed gains (P less than .05) and increased feed-to-gain ratios. Carcasses were not different among treatments for dressing percentage, length, average backfat and percentage of ham, loin, shoulder, lean cuts and primal cuts. Carcasses from pigs fed 20 and 30% offal silage had significantly darker and firmer loin-eyes than those from control fed pigs. Marbling was higher (P less than .05) in loin-eyes from pigs fed 30% offal silage as compared with those from pigs fed 0% offal silage.(ABSTRACT TRUNCATED AT 250 WORDS)

  12. Improved laboratory assays of Pu and U for SRP purification and finishing processes

    International Nuclear Information System (INIS)

    Holland, M.K.; Dorsett, R.S.

    1986-01-01

    Significant improvements have been made in routine assay techniques for uranium and plutonium as part of an effort to improve accountability at the Savannah River Plant (SRP). Emphasis was placed on input/output accountability points and key physical inventory tanks associated with purification and finishing processes. Improvements were made in existing assay methods; new methods were implemented; and the application of these methods was greatly expanded. Prior to assays, samples were validated via density measurements. Digital density meters precise to four, five, and six decimal places were used to meet specific requirements. Improved plutonium assay techniques are now in routine use: controlled-potential coulometry, ion-exchange coulometry, and Pu(III) diode-array spectrophotometry. A new state-of-the-art coulometer was fabricated and used to ensure maximum accuracy in verifying standards and in measuring plutonium in product streams. The diode-array spectrophotometer for Pu(III) measurements was modified with fiber optics to facilitate remote measurements; rapid, precise measurements made the technique ideally suited for high-throughput assays. For uranium assays, the isotope-dilution mass spectrometric (IDMS) method was converted to a gravimetric basis. The IDMS method and the existing Davies-Gray titration (gravimetric basis) have met accountability requirements for uranium. More recently, a Pu(VI) diode-array spectrophotometric method was used on a test basis to measure plutonium in shielded-cell input accountability samples. In addition, tests to measure uranium via diode-array spectrophotometry were initiated. This rapid, precise method will replace IDMS for certain key sample points

  13. Compositions of airborne plutonium-bearing particles from a plutonium finishing operation

    International Nuclear Information System (INIS)

    Sanders, S.M. Jr.

    1976-11-01

    The elemental composition of 111 plutonium-bearing particles was determined (using an electron microprobe) as part of a program to investigate the origin and behavior of the long-lived transuranic radionuclides released from fuel reprocessing facilities at the Savannah River Plant. These particles, collected from wet-cabinet and room-air exhausts from the plutonium finishing operation (JB-Line), were between 0.4 and 36 μm in diameter. Ninety-nine of the particles were found to be aggregates of various minerals and metals, six were quartz, and six were small (less than 2-μm-diameter) pieces of iron oxide. Collectively, these particles contained less minerals and more metals than natural dusts contain. The metallic constituents included elements normally not found in dusts, e.g., chromium, nickel, copper, and zinc. Concentrations of aluminum and iron exceeded those normally found in minerals. Elemental concentrations in individual particles covered a wide range: one 2-μm-diameter particle contained 97 percent NiO, a 9-μm-diameter particle contained 72 percent Cr 2 O 3 . Although the particles were selected because they produced plutonium fission tracks, the plutonium concentration was too low to be estimated by microprobe analysis in all but a 1-μm-diameter particle. This plutonium-bearing particle contained 73 percent PuO 2 by weight in combination with Fe 2 O 3 and mica; its activity was estimated at 0.17 pCi of 239 Pu

  14. Influence of way of finishing furniture segments on amount emissions VOCs

    Directory of Open Access Journals (Sweden)

    Petr Čech

    2010-01-01

    Full Text Available The study deals with the influence of way of finishing furniture segments on amount emissions VOCs (volatile organic compounds. The so-called Volatile Organic Compounds (VOC are among the largest pollution sources of both the internal and external environments.VOC is defined as emission of any organic compound or a mixture thereof, with the exception of methane, whereby the compound exerts the pressure of 0.01 kPa or more at the temperature of 20 °C (293.15 K and reaches the corresponding volatility under the specific conditions of its use and can undergo photochemical reactions with nitrogen oxides when exposed to solar radiation. The effects of VOC upon environment can be described by equation: VOC + NOx + UV radiation + heat = tropospheric ozone (O3In this work there were tested MDF (medium density fibreboard coated by resin impregnated paper was used for the furniture components’ production. Next were tested compressed wood, which was used as a second material of furniture components. These both chosen materials was covered by resin impregnated paper and than sequentially finished by regular coat of finish.An attention of this study is especially put on mentioned factors and on quantity of instant and long-term VOCs emissions emitted from furniture components.The amount of emissions from furniture components, in different phases of the preparation including the resin impregnated paper coating finish, was monitored within the time intervals of 24 hours and 720 hours starting after the time of the finish preparation.The MDF (medium density fibreboard coated by resin impregnated paper was used for the furniture components´ production.A compressed wood was used as a second material of furniture components. This alternative material was covered by resin impregnated paper and than sequentially finished by regular coat of finish.

  15. A Review of Criticality Accidents 2000 Revision

    Energy Technology Data Exchange (ETDEWEB)

    Thomas P. McLaughlin; Shean P. Monahan; Norman L. Pruvost; Vladimir V. Frolov; Boris G. Ryazanov; Victor I. Sviridov

    2000-05-01

    Criticality accidents and the characteristics of prompt power excursions are discussed. Sixty accidental power excursions are reviewed. Sufficient detail is provided to enable the reader to understand the physical situation, the chemistry and material flow, and when available the administrative setting leading up to the time of the accident. Information on the power history, energy release, consequences, and causes are also included when available. For those accidents that occurred in process plants, two new sections have been included in this revision. The first is an analysis and summary of the physical and neutronic features of the chain reacting systems. The second is a compilation of observations and lessons learned. Excursions associated with large power reactors are not included in this report.

  16. A Review of Criticality Accidents 2000 Revision

    International Nuclear Information System (INIS)

    McLaughlin, Thomas P.; Monahan, Shean P.; Pruvost, Norman L.; Frolov, Vladimir V.; Ryazanov, Boris G.; Sviridov, Victor I.

    2000-01-01

    Criticality accidents and the characteristics of prompt power excursions are discussed. Sixty accidental power excursions are reviewed. Sufficient detail is provided to enable the reader to understand the physical situation, the chemistry and material flow, and when available the administrative setting leading up to the time of the accident. Information on the power history, energy release, consequences, and causes are also included when available. For those accidents that occurred in process plants, two new sections have been included in this revision. The first is an analysis and summary of the physical and neutronic features of the chain reacting systems. The second is a compilation of observations and lessons learned. Excursions associated with large power reactors are not included in this report

  17. BWR normal water chemistry guidelines: 1986 revision

    International Nuclear Information System (INIS)

    1988-09-01

    Boiling water reactors (BWRs) have experienced stress corrosion cracking in the reactor cooling system piping resulting in adverse impacts on plant availability and personnel radiation exposure. The BWR Owners Group and EPRI have sponsored a major research and development program to provide remedies for this stress corrosion cracking problem. This work shows that the likelihood of cracking depends on the plant's water chemistry performance (environment) as well as on material condition and stress level. Plant experience and other research demonstrate that water quality also affects fuel performance and radiation field buildup in BWRs. This report,''BWR Normal Water Chemistry Guidelines: 1986 Revision,'' presents suggested generic water chemistry specifications, justifies the proposed water chemistry limits, suggests responses to out-of-specification water chemistry, discusses available chemical analysis methods as well as data management and surveillance schemes, and details the management philosophy required to successfully implement a water chemistry control program. An appendix contains recommendations for water quality of auxiliary systems. 73 refs., 20 figs., 9 tabs

  18. Concentration data for anthropogenic organic compounds in ground water, surface water, and finished water of selected community water systems in the United States, 2002-05

    Science.gov (United States)

    Carter, Janet M.; Delzer, Gregory C.; Kingsbury, James A.; Hopple, Jessica A.

    2007-01-01

    combustion-derived compounds; (10) personal care and domestic use products; (11) plant- or animal-derived biochemicals; (12) refrigerants and propellants; and (13) solvents. Source and finished water samples were collected during phase 2 and analyzed for constituents that were detected frequently during phase 1. This report presents concentration data for AOCs in ground water, surface water, and finished water of CWSs sampled for SWQA studies during 2002-05. Specifically, this report presents the analytical results of samples collected during phase 1 including (1) samples from 221 wells that were analyzed for 258 AOCs; (2) monthly samples from 9 surface-water sites that were analyzed for 258 AOCs during phase 1; and (3) samples from a subset of the wells and surface-water sites located in areas with substantial agricultural production that were analyzed for 3 additional pesticides and 16 pesticide degradates. Samples collected during phase 2 were analyzed for selected AOCs that were detected most frequently in source water during phase 1 sampling; analytical results for phase 2 are presented for (1) samples of source water and finished water from 94 wells; and (2) samples of source water and finished water samples that were collected monthly and during selected flow conditions at 8 surface-water sites. Results of quality-assurance/quality-control samples collected for SWQA studies during 2002-05 also are presented.

  19. Revision of the genus Diaphorocera Heyden, 1863 (Coleoptera, Meloidae, Cerocomini)

    OpenAIRE

    Turco, F.; Bologna, M.A.

    2007-01-01

    Diaphorocera, a Saharo-Sindian genus belonging to the tribe Cerocomini, is revised and a new synonymy is proposed. A cladistic classification is proposed as well, on a set of adult morphological characters. The available bionomical records, both original and from literature, concerning phenology, elevation, habitat preference, and host plants, are summarised. Adult morphology of all species is described and figured, the catalogue of localities with maps of distribution is reported, and a biog...

  20. Graphic Display Development Program. Volume II, Revision 0. Appendices

    International Nuclear Information System (INIS)

    1984-12-01

    The objective of this project is to demonstrate the feasibility and utility of developing a set of graphic displays to support symptom-based emergency operating procedures (EOPs). Development of generic graphic displays is based on Revision 3 of the symptomatic Emergency Procedure Guidelines (EPGs) prepared by the BWR Owners' Group (BWROG), and development of plant-specific graphic displays is based on a set of emergency operating procedures developed from these EPGs

  1. Cross-Cultural Consumer Acceptability and Purchase Intent of Forage-Finished Rib-Eye Steaks.

    Science.gov (United States)

    Torrico, Damir Dennis; Wardy, Wisdom; Pujols, Kairy Dharali; Carabante, Kennet Mariano; Jirangrat, Wannita; Scaglia, Guillermo; Janes, Marlene E; Prinyawiwatkul, Witoon

    2015-10-01

    Rib-eye steaks, from 3 forage-finished systems (S1, S2, and S3) and 1 commercial steak (C), either cooked by 1-sided-grilling or 2-sided-grilling, were evaluated for sensory acceptability [overall appearance (ORA) and overall appearance of fat (OAF) for raw steaks; overall appearance (OCA), overall beef aroma (OBA), overall beef flavor (OBF), juiciness, tenderness and overall liking (OL) for cooked steaks] and purchase intent by Hispanic, Asian and U.S. consumers. They also indicated preferred degree of doneness and cooking methods. Cross-cultural differences in preferences and consumer acceptability of rib-eye steaks were observed. Grilling was the most preferred cooking method. Hispanics and Asians preferred medium and/or medium well, while U.S. consumers preferred medium and/or medium rare. For cooked steaks, the population effect was significant for all sensory attributes; Asians generally scored lower than did Hispanics and U.S. consumers. C and S3 generally had higher scores for all sensory attributes across 3 populations. Purchase intent for all forage-finished steaks was higher for Hispanics and U.S. consumers compared to Asians (50.0% to 77.8% compared with 43.2% to 65.9%). Attributes influencing purchase intent of forage-finished steaks differed among populations: tenderness (odds ratio = 1.4) for Hispanics, OCA (odds ratio = 1.5) for Asians, and OBF (odds ratio = 1.3) for U.S. consumers. Overall, this study demonstrated that the type of forage-finished system and ethnic differences influenced sensory acceptability and purchase intent of forage-finished rib-eye steaks. Demand for forage-finished beef has increased worldwide due to its potential health benefits. Little is known regarding the cross-cultural effects on the consumer acceptance of forage-finished beef. We evaluated sensory acceptance and purchase intent of raw and cooked forage-finished rib-eye steaks using Hispanic, Asian, and U.S. (White and African American) populations. This study

  2. Research and development of methods and technologies for CO2 capture in fossil fuel power plants and storage in geological formations in the Czech Republic. Stage 5.4: Boiler with oxyfuel technology. Revision 0

    International Nuclear Information System (INIS)

    Dlouhy, Tomas

    2011-12-01

    This phase comprised a preliminary study of boiler design modification for the oxyfuel technology. The design was developed specifically for the Prunerov II power plant. It was defined as a reference boiler for combustion using air which was consequently modified for combustion with oxygen. Changes in the construction of boiler were designed and quantified using thermal conversion, which provided the necessary modification of the sizes of the fireplace and heating surfaces. An existing general mathematical model, modified for this specific task, was used for the thermal conversion calculations

  3. The evaluation outline to 'root cause analysis report (revision) of the event which the penetration hole generated by the main exhaust pipe duct of the reprocessing plant' reported by Japan Atomic Energy Agency

    International Nuclear Information System (INIS)

    2013-06-01

    JNES evaluated the report which JAEA presented in October 2012 at the Nuclear Regulation Authority on the root cause analysis regarding the penetration hole on the main exhaust pipe duct in the JAEA reprocessing plant. The evaluation of the root cause analysis was done based on the guideline of the Regulation Authority evaluating the root cause analysis carried out by the enterprise side and concluded that the evaluation extending as to JAEA's organizational system was effective as a countermeasure for a recurrence, the present report representing the outline of the evaluation. (S. Ohno)

  4. Flame retardant finishing of cotton fabric based on synergistic compounds containing boron and nitrogen.

    Science.gov (United States)

    Xie, Kongliang; Gao, Aiqin; Zhang, Yongsheng

    2013-10-15

    Boric acid and compound containing nitrogen, 2,4,6-tri[(2-hydroxy-3-trimethyl-ammonium)propyl]-1,3,5-triazine chloride (Tri-HTAC) were used to finish cotton fabric. The flame retardant properties of the finished cotton fabrics and the synergetic effects of boron and nitrogen elements were investigated and evaluated by limited oxygen index (LOI) method. The mechanism of cross-linking reaction among cotton fiber, Tri-HTAC, and boric acid was discussed by FTIR and element analysis. The thermal stability and surface morphology of the finished cotton fabrics were investigated by thermogravimetric analysis (TGA) and scanning electron microscope (SEM), respectively. The finishing system of the mixture containing boron and nitrogen showed excellent synergistic flame retardancy for cotton fabric. The cotton fabric finished with mixture system had excellent flame retardancy. The LOI value of the treated cotton fabric increased over 27.5. Tri-HTAC could form covalent bonds with cellulose fiber and boric acid. The flame retardant cotton fabric showed a slight decrease in tensile strength and whiteness. The surface morphology of flame retardant cotton fiber was smooth. Copyright © 2013 Elsevier Ltd. All rights reserved.

  5. Advantages of modern collapsible systems for exterior finishing of buildings in urban areas in Russia

    Directory of Open Access Journals (Sweden)

    Tolstova Kristina

    2017-01-01

    Full Text Available Traditionally, the method of finishing interior spaces, as well as exterior surfaces and architectural and structural elements of buildings and structures is widely used, when layers of building materials or finishing structures are applied in a strict sequence, allowing them to eventually form an unbroken whole - a “monolith”. This method of finishing, its technology and results not only depend significantly on the quality of the materials used and the mechanization of processes, but also require high qualification and specialization of construction workers. The execution of such a finish is more an art than a reproduced with a given level of quality of results by a technological process. An alternative to “monolith” is a variety of collapsible (they are also called “hinged” systems for finishing urban buildings, the elements of which are manufactured in the construction industry, requiring, as a rule, only installation and assembly in internal premises (the so-called “evroremont”, Or on the external surfaces of a building or structure.

  6. Meat quality of buffaloes finished in traditional or silvopastoral system in the Brazilian Eastern Amazon.

    Science.gov (United States)

    Joele, Maria Rsp; Lourenço, Lúcia Fh; Lourenço Júnior, José B; Araújo, Geisielly S; Budel, Juliana Cc; Garcia, Alexandre R

    2017-04-01

    The present study aimed to assess the physical, chemical and sensory characteristics of meat from buffaloes finished in a Traditional System (TS) or Traditional + Silvopastoral System (TSPS) with dietary supplementation. Crossbred Murrah × Mediterranean buffaloes were raised from weaning to slaughter in the TS (n = 15) or were raised in the traditional system and finished in the TSPS (n = 15). After finishing, animals were slaughtered and their carcasses refrigerated for 24 h. The right side of each half-carcass was cut between the 12th and 13th ribs and the Longissimus thoracis muscle was removed. The cranial part underwent analyses of pH, color, weight loss as a result of cooking, water holding capacity, texture and sensory characteristics, whereas the rest of the muscle underwent microbiological analyses and determination of the chemical composition, fatty acid profile and mineral content. No major difference between finishing systems was found (P > 0.05) in the physical analyses and chemical composition of meat. The percentage of myristic acid (C14:0) and the sum of polyunsaturated fatty acids differed between treatments. The TS meat had the best 'characteristic meat aroma'. Considering the quality of meat produced in the TS or TSPS, it is concluded that finishing buffaloes in the pasture still represents the best alternative. © 2016 Society of Chemical Industry. © 2016 Society of Chemical Industry.

  7. Surface roughness of microparticulated and nanoparticulated composites after finishing and polishing procedures

    Directory of Open Access Journals (Sweden)

    Rosemary Arai Sadami Shinkai

    Full Text Available Objective: To evaluated the surface roughness of one microparticulate resin composite Durafill (Heraeus Kulzer Weihrheim, Germany andfour nanoparticulate resins 4 Seasons (Ivoclar Vivadent, Schaan, Liechtenstein Esthet x (Dentsply, Milford, DE, USA, Point 4 and Supreme (3M-ESPE, Dental Products,St. Paul, MN, USA. Methods: After finishing with a diamond bur point (F, and polishing with silicone points of gray, green and pink color Politipit (Ivoclar Vivadent,Schaan, Liechtenstein, four stages of completion were performed, simulating one of finishing and three of polishing a resin restoration. Ten samples of each composite resin were measured for surface roughness with surface profilometer (Mitutoyo Corporation, Tokyo, Japan after each of finishing and polishing sequence.Results: The results showed that nanoparticulate and microparticulate resins presented a significant difference in the surface roughness values, in all finishing and polishing steps. Conclusion: Of the the nanoparticulate resins 4 Seasons (Ivoclar Vivadent, Schaan, Liechtenstein, Point 4 (Kerr CO, Orange, CA, USA, and also microparticulate Durafill (Heraeus Kulzer Weihrheim, Germany presented significantly lower surface roughness values after completing all the finishing and polishing stages.

  8. THE CONCEPTUAL APPARATUS OF THE TERM "FINISHED GOODS" AS AN OBJECT OF ACCOUNTING

    Directory of Open Access Journals (Sweden)

    A. Kasich

    2016-11-01

    Full Text Available The article studies scientific approaches to the definition of "finished goods"; properties and various characteristics of the finished goods, which, in the author’s opinion, affect to the term’s wording. identified generalized features of the concept and differences from the executed works and the rendered services. Described the features and the main differences the ways of production of finished goods in certain economy’s sectors and proved the necessity of taking into account the specific features during the approach to the concept of "finished goods" in various industries. Analyzed the common and distinctive features of international and national standards for the accounting of inventory, because in the conditions of globalization becomes important the necessity of their identity. investigated the components of enterprise accounting policies, such as evaluation of reserves and write-offs on trade, applied in different countries of the world, revealed a basic discrepancy, namely, the use of LiFO method, which is prohibited for use in Ukraine, which, however, is used almost in all the considered countries. On the basis of the conducted research the author’s definition of "finished goods".

  9. 78 FR 7738 - Notice of Request for Revision to and Extension of Approval of an Information Collection...

    Science.gov (United States)

    2013-02-04

    ... hour per response. Respondents: Growers, importers, and foreign national plant protection organizations... DEPARTMENT OF AGRICULTURE Animal and Plant Health Inspection Service [Docket No. APHIS-2012-0102... Brown Rot AGENCY: Animal and Plant Health Inspection Service, USDA. ACTION: Revision to and extension of...

  10. R.4. Innovative concept for plutonium finishing facility

    International Nuclear Information System (INIS)

    Bertolotti, G.; Laguerie, I.V. de; Richter, R.; Gillet, B.

    1998-01-01

    After complete shutdown of the units of the previous UP2 plant, the new R4 facility will ensure the purification of Plutonium of the UP2-800 plant for the whole range of fuel to be reprocessed in the years to come. This facility features four main units: - Purification of plutonium nitrate; - Conversion into plutonium oxide; - PuO 2 conditioning into cans; Acid recovery. An extensive R and D program resulted in significant innovations. From a technological aspect the centrifugal extractor and the sub-critical tube bundle tank contributed to the reduction of the building dimensions. The extensive use of on-line analyses enables a more efficient follow-up of the process while minimizing the effluent production. On the other hand, the organization of the building which consists in grouping the rooms presenting the same risk of dispersal of nuclear materials also contributed to reduce the active zone volume. This facility, as any other facilities on the LA HAGUE site, will be remotely operated. (author)

  11. Quantum interaction. Revised selected papers

    Energy Technology Data Exchange (ETDEWEB)

    Song, Dawei; Zhang, Peng; Wang, Lei [Aberdeen Univ. (United Kingdom). School of Computing; Melucci, Massimo [Padua Univ., Padova (Italy). Dept. of Information Engineering; Frommholz, Ingo [Bedfordshire Univ. (United Kingdom); Arafat, Sachi (eds.) [Glasgow Univ. (United Kingdom). School of Computing Science

    2011-07-01

    This book constitutes the thoroughly refereed post-conference proceedings of the 5th International Symposium on Quantum Interaction, QI 2011, held in Aberdeen, UK, in June 2011. The 26 revised full papers and 6 revised poster papers, presented together with 1 tutorial and 1 invited talk were carefully reviewed and selected from numerous submissions during two rounds of reviewing and improvement. The papers show the cross-disciplinary nature of quantum interaction covering topics such as computation, cognition, mechanics, social interaction, semantic space and information representation and retrieval. (orig.)

  12. HEDR modeling approach: Revision 1

    International Nuclear Information System (INIS)

    Shipler, D.B.; Napier, B.A.

    1994-05-01

    This report is a revision of the previous Hanford Environmental Dose Reconstruction (HEDR) Project modeling approach report. This revised report describes the methods used in performing scoping studies and estimating final radiation doses to real and representative individuals who lived in the vicinity of the Hanford Site. The scoping studies and dose estimates pertain to various environmental pathways during various periods of time. The original report discussed the concepts under consideration in 1991. The methods for estimating dose have been refined as understanding of existing data, the scope of pathways, and the magnitudes of dose estimates were evaluated through scoping studies

  13. Quantum interaction. Revised selected papers

    International Nuclear Information System (INIS)

    Song, Dawei; Zhang, Peng; Wang, Lei; Arafat, Sachi

    2011-01-01

    This book constitutes the thoroughly refereed post-conference proceedings of the 5th International Symposium on Quantum Interaction, QI 2011, held in Aberdeen, UK, in June 2011. The 26 revised full papers and 6 revised poster papers, presented together with 1 tutorial and 1 invited talk were carefully reviewed and selected from numerous submissions during two rounds of reviewing and improvement. The papers show the cross-disciplinary nature of quantum interaction covering topics such as computation, cognition, mechanics, social interaction, semantic space and information representation and retrieval. (orig.)

  14. Medical writing, revising and editing

    DEFF Research Database (Denmark)

    Pilegaard, Morten

    2006-01-01

    The globalization of science makes medical writing, editing and revision a rapidly growing field of linguistic study and practice. Medical science texts are written according to uniform, general guidelines and medical genres have become highly conventionalized in terms of structure and linguistic...... form. Medical editing often takes the form of peer review and mainly addresses issues of contents and overall validity. Medical revision incorporates the checking of the macrostructure and the microstructure of the text, its language and style and its suitability for the target reader or client...

  15. Revising Nabokov Revising”

    Directory of Open Access Journals (Sweden)

    Marie Bouchet

    2010-10-01

    Full Text Available Nabokov revised his works as he translated them and, on another plane, canon revisionism has been having its backlash and provoked other refracting waves. The purpose of the conference was to advance Nabokov studies through the discussion of how our view of Nabokov’s standing and his works today should be revised, especially after the publication of The Original of Laura. However the conference was not confined to just this theme, since “revising” is a word rich with implications. To borrow s...

  16. Revision of the ASME nuclear quality assurance standard and its historical background

    International Nuclear Information System (INIS)

    Suzuki, Tetsuya

    2009-01-01

    ASME NQA-1-2008 'Quality Assurance Requirements for Nuclear Facility Applications' will be endorsed by US NRC by the end of 2009. This standard will apply to design, construction and operation of nuclear power plants newly erected in USA. It is important to Japanese vendors developing nuclear business in USA. Historical background, significance of revision and main revised points of the ASME nuclear quality assurance standard are described in the present paper. (T. Tanaka)

  17. Failure of aseptic revision total knee arthroplasties.

    Science.gov (United States)

    Leta, Tesfaye H; Lygre, Stein Håkon L; Skredderstuen, Arne; Hallan, Geir; Furnes, Ove

    2015-02-01

    In Norway, the proportion of revision knee arthroplasties increased from 6.9% in 1994 to 8.5% in 2011. However, there is limited information on the epidemiology and causes of subsequent failure of revision knee arthroplasty. We therefore studied survival rate and determined the modes of failure of aseptic revision total knee arthroplasties. This study was based on 1,016 aseptic revision total knee arthroplasties reported to the Norwegian Arthroplasty Register between 1994 and 2011. Revisions done for infections were not included. Kaplan-Meier and Cox regression analyses were used to assess the survival rate and the relative risk of re-revision with all causes of re-revision as endpoint. 145 knees failed after revision total knee arthroplasty. Deep infection was the most frequent cause of re-revision (28%), followed by instability (26%), loose tibial component (17%), and pain (10%). The cumulative survival rate for revision total knee arthroplasties was 85% at 5 years, 78% at 10 years, and 71% at 15 years. Revision total knee arthroplasties with exchange of the femoral or tibial component exclusively had a higher risk of re-revision (RR = 1.7) than those with exchange of the whole prosthesis. The risk of re-revision was higher for men (RR = 2.0) and for patients aged less than 60 years (RR = 1.6). In terms of implant survival, revision of the whole implant was better than revision of 1 component only. Young age and male sex were risk factors for re-revision. Deep infection was the most frequent cause of failure of revision of aseptic total knee arthroplasties.

  18. Characterisation of the joining zone of serially arranged hybrid semi-finished components

    Science.gov (United States)

    Behrens, B.-A.; Chugreev, A.; Matthias, T.

    2018-05-01

    Forming of already joined semi-finished products is an innovative approach to manufacture components which are well-adapted to external loads. This approach results in an economically and ecologically improved production by the targeted use of high-quality materials in component areas, which undergo high stresses. One possible production method for hybrid semi-finished products is friction welding. This welding method allows for the production of hybrid semi-finished products made of aluminium and steel as well as steel and steel. In this paper, the thermomechanical tensile and shear stresses causing a failure of the joined zone are experimentally determined through tension tests. These tests are performed with specimens whose joint zones are aligned with different angles to the load direction.

  19. EFFECT OF ARTIFICIAL WEATHERING ON WOOD LAMINATES COLOR TREATED WITH TWO FINISHING PRODUCTS

    Directory of Open Access Journals (Sweden)

    Thais Jacob Mendes

    2016-03-01

    Full Text Available Weathering is one of the main reasons for the degradation of wood, especially its color. The application of finishes minimizes these effects. This study aimed to monitor the effect of artificial weathering on wood veneer of the species cumaru (Dipteryx odorata and pau marfim (Balfourodendron riedelianum with two finishes, the marine varnish and Cetol, with monitoring using a spectrophotometer. The samples were subjected to cycles of exposure to weathering for 20, 40, 52, 76, 124, 226, 430, 838 and 960 hours. The colorimetric parameters (L*, a*, b*, C and h* were measured before treatment, after application of the products and during the weathering time intervals. The application of finishes darkened veneer of cumaru wood and pau marfim in nature. However, in higher weathering times, both species returned to a lighter color, and even became lighter than the natural wood. The use of Cetol was more efficient, giving greater stability in the conservation of wood color of the species studied.

  20. Finishing of additively manufactured titanium alloy by shape adaptive grinding (SAG)

    Science.gov (United States)

    Beaucamp, Anthony T.; Namba, Yoshiharu; Charlton, Phillip; Jain, Samyak; Graziano, Arthur A.

    2015-06-01

    In recent years, rapid prototyping of titanium alloy components for medical and aeronautics application has become viable thanks to advances in technologies such as electron beam melting (EBM) and selective laser sintering (SLS). However, for many applications the high surface roughness generated by additive manufacturing techniques demands a post-finishing operation to improve the surface quality prior to usage. In this paper, the novel shape adaptive grinding process has been applied to finishing titanium alloy (Ti6Al4V) additively manufactured by EBM and SLS. It is shown that the micro-structured surface layer resulting from the melting process can be removed, and the surface can then be smoothed down to less than 10 nm Ra (starting from 4-5 μm Ra) using only three different diamond grit sizes. This paper also demonstrates application of the technology to freeform shapes, and documents the dimensional accuracy of finished artifacts.

  1. The association between disease and profitability in individual finishing boars at a test station

    DEFF Research Database (Denmark)

    Jensen, Tina Birk; Baadsgaard, Niels Peter; Houe, Hans

    2008-01-01

    Endemic diseases in finisher herds are considered to be costly for the pig producer. We investigated the effect of diseases on the profit margin using data from a Danish boar test station (n = 5777) collected from July 2002 to December 2004. Boars reaching a target slaughter weight of at least 80...... kg were included in the study. Oral and parenteral treatments were used as indicator of disease in the finishing period and, pathological lesions were used as indicator of disease at slaughter. Profit margin was calculated individually for each boar as the difference between the total revenue......: profit margin. The results showed that treatment in the finishing period had a negative effect on the profit margin. According to the least square means estimates, boars that were treated parenterally had a reduction in the profit margin of 2.24 €. This corresponded to a reduction in the profit margin...

  2. Finishing of additively manufactured titanium alloy by shape adaptive grinding (SAG)

    International Nuclear Information System (INIS)

    Beaucamp, Anthony T; Namba, Yoshiharu; Charlton, Phillip; Jain, Samyak; Graziano, Arthur A

    2015-01-01

    In recent years, rapid prototyping of titanium alloy components for medical and aeronautics application has become viable thanks to advances in technologies such as electron beam melting (EBM) and selective laser sintering (SLS). However, for many applications the high surface roughness generated by additive manufacturing techniques demands a post-finishing operation to improve the surface quality prior to usage. In this paper, the novel shape adaptive grinding process has been applied to finishing titanium alloy (Ti6Al4V) additively manufactured by EBM and SLS. It is shown that the micro-structured surface layer resulting from the melting process can be removed, and the surface can then be smoothed down to less than 10 nm Ra (starting from 4–5 μm Ra) using only three different diamond grit sizes. This paper also demonstrates application of the technology to freeform shapes, and documents the dimensional accuracy of finished artifacts. (paper)

  3. Improvements in Sand Mold/Core Technology: Effects on Casting Finish

    Energy Technology Data Exchange (ETDEWEB)

    Prof. John J. Lannutti; Prof. Carroll E. Mobley

    2005-08-30

    In this study, the development and impact of density gradients on metal castings were investigated using sand molds/cores from both industry and from in-house production. In spite of the size of the castings market, almost no quantitative information about density variation within the molds/cores themselves is available. In particular, a predictive understanding of how structure and binder content/chemistry/mixing contribute to the final surface finish of these products does not exist. In this program we attempted to bridge this gap by working directly with domestic companies in examining the issues of surface finish and thermal reclamation costs resulting from the use of sand molds/cores. We show that these can be substantially reduced by the development of an in-depth understanding of density variations that correlate to surface finish. Our experimental tools and our experience with them made us uniquely qualified to achieve technical progress.

  4. Surface Finish Effects Using Coating Method on 3D Printing (FDM) Parts

    Science.gov (United States)

    Haidiezul, AHM; Aiman, AF; Bakar, B.

    2018-03-01

    One of three-dimensional (3-D) printing economical processes is by using Fused Deposition Modelling (FDM). The 3-D printed object was built using layer-by-layer approach which caused “stair stepping” effects. This situation leads to uneven surface finish which mostly affect the objects appearance for product designers in presenting their models or prototypes. The objective of this paper is to examine the surface finish effects from the application of XTC-3D coating developed by Smooth-On, USA on the 3D printed parts. From the experimental works, this study shows the application of XTC-3D coating to the 3-D printed parts has improve the surface finish by reducing the gap between the layer

  5. Disassembly Properties of Cementitious Finish Joints Using an Induction Heating Method

    Science.gov (United States)

    Ahn, Jaecheol; Noguchi, Takafumi; Kitagaki, Ryoma

    2015-01-01

    Efficient maintenance and upgrading of a building during its lifecycle are difficult because a cementitious finish uses materials and parts with low disassembly properties. Additionally, the reuse and recycling processes during building demolition also present numerous problems from the perspective of environmental technology. In this study, an induction heating (IH) method was used to disassemble cementitious finish joints, which are widely used to join building members and materials. The IH rapidly and selectively heated and weakened these joints. The temperature elevation characteristics of the cementitious joint materials were measured as a function of several resistor types, including wire meshes and punching metals, which are usually used for cementitious finishing. The disassembly properties were evaluated through various tests using conductive resistors in cementitious joints such as mortar. When steel fiber, punching metal, and wire mesh were used as conductive resistors, the cementitious modifiers could be weakened within 30 s. Cementitious joints with conductive resistors also showed complete disassembly with little residual bond strength.

  6. Effects of surface finish and mechanical training on Ni-Ti sheets for elastocaloric cooling

    Directory of Open Access Journals (Sweden)

    Kurt Engelbrecht

    2016-06-01

    Full Text Available Elastocaloric cooling has emerged as a promising alternative to vapor compression in recent years. Although the technology has the potential to be more efficient than current technologies, there are many technical challenges that must be overcome to realize devices with high performance and acceptable durability. We study the effects of surface finish and training techniques on dog bone shaped polycrystalline samples of NiTi. The fatigue life of several samples with four different surface finishes was measured and it was shown that a smooth surface, especially at the edges, greatly improved fatigue life. The effects of training both on the structure of the materials and the thermal response to an applied strain was studied. The load profile for the first few cycles was shown to change the thermal response to strain, the structure of the material at failure while the final structure of the material was weakly influenced by the surface finish.

  7. Effects of Wet and Dry Finishing and Polishing on Surface Roughness and Microhardness of Composite Resins

    Science.gov (United States)

    Nasoohi, Negin; Hoorizad, Maryam

    2017-01-01

    Objectives: This study aimed to assess the effect of wet and dry finishing and polishing on microhardness and roughness of microhybrid and nanohybrid composites. Materials and Methods: Thirty samples were fabricated of each of the Polofil Supra and Aelite Aesthetic All-Purpose Body microhybrid and Grandio and Aelite Aesthetic Enamel nanohybrid composite resins. Each group (n=30) was divided into three subgroups of D, W and C (n=10). Finishing and polishing were performed dry in group D and under water coolant in group W. Group C served as the control group and did not receive finishing and polishing. Surface roughness of samples was measured by a profilometer and their hardness was measured by a Vickers hardness tester. Data were analyzed using two-way ANOVA (Pcomposites (Pcomposites (Pcomposites (Pcomposite resins. PMID:29104597

  8. Pending revisions to ANS 56.8-81 containment systems leakage testing requirements

    International Nuclear Information System (INIS)

    Brown, T.M.

    1986-01-01

    The US Nuclear Regulatory Commission is currently processing a revision to Appendix J of Part 50, Title 10 of the Code of Federal Regulations. The revised Appendix J will not reference any ANSI standard. Processed concurrently with the revised Appendix J is a draft Regulatory Guide which does endorse ANS Standard 56.8. The draft Regulatory Guide currently takes many exceptions to the Standard. Many of the exceptions are changes the Working Group had in process and the exceptions are to bring the draft Regulatory Guide in line with the future Standard. The Working Group has completed their revisions to the Standard and its appendices. These revisions have been submitted to the Nuclear Power Plants Standards Committee (NUPPSCO). The NUPPSCO comments have recently been addressed by the Working Group and the Working Group response has been sent to the NUPPSCO commentators. This paper will discuss the revisions made to the Standard, the significance of the revisions and future tasks or Standard revisions which the ANS 56.8 Working Group may address

  9. Physiology of woody plants

    CERN Document Server

    Hazewinkel, Michiel; Pallardy, Stephen G

    1996-01-01

    This completely revised classic volume is an up-to-date synthesis of the intensive research devoted to woody plants. Intended primarily as a text for students and a reference for researchers, this interdisciplinary book should be useful to a broad range of scientists from agroforesters, agronomists, and arborists to plant pathologists, ecophysiologists, and soil scientists. Anyone interested in plant physiology will find this text invaluable. Key Features * Includes supplementary chapter summaries and lists of general references * Provides a solid foundation of reference information * Thoroughly updated classic text/reference.

  10. Marketing Strategy Formulation for the Introduction of Eukula Strato German Wood Finishes in Local Market of Emerging Indian Economy

    Directory of Open Access Journals (Sweden)

    Suraj Kushe Shekhar

    2013-09-01

    Full Text Available Wood finishing relates to the process of embellishing or protecting the surface of the wood. The paper aimed at formulating a marketing strategy for introducing water borne German based Wood Finishes named Eukula Strato into local market of northern Kerala, India. Multiple cross sectional descriptive research with judgmental sampling technique elicited responses from Finishers, Furniture manufacturers and Interior designers. Findings revealed that Eukula Strato had a distinct advantage when compared to any other Wood Finish that was available in the local market. Findings and suggestions were reported as per 4P’s of marketing mix. Percentage analysis, Chi square analysis etc were used to interpret the results

  11. Comparison of two feeding finishing treatments on production and quality of organic beef

    Directory of Open Access Journals (Sweden)

    Giulio Cozzi

    Full Text Available The study compared growth and slaughter performance and meat quality of organic beef cattle finished with or without pasture grazing. One group of 10 Limousin heifers was finished under confined conditions and fed ad libitum a total mixed ration based on maize silage, hay and cereal grains. A second group of 10 Limousin heifers rotationally grazed two contiguous pasture plots of 1.5 ha each with a daily supplementation of a concentrate mix based on cereal grains and roasted soybeans. Heifers were slaughtered at commercial finishing and meat quality traits were assessed on Longissimus thoracis muscle. The grazing group, due to a lower average daily gain (0.74 vs. 0.95 kg/day; P<0.05, required a prolonged finishing period (172 vs. 155 days; P<0.05 than the confined animals. Meat samples from grazing cattle were less tender (shear force: 3.92 vs. 3.24 kg/cm2; P<0.05 and showed a lower lightness (L*: 33.0 vs. 35.8; P<0.001 and a higher redness (15.4 vs. 13.7; P<0.01 and yellowness (15.6 vs. 14.6; P<0.05. Fatty acid composition of the intramuscular fat was significantly affected by the finishing system. Grazing heifers had a higher content of polyunsaturated fatty acids (4.06 vs. 3.66% of total fatty acids; P<0.05, conjugated linoleic acids (0.16 vs. 0.10% of total fatty acids; P<0.01 and ω-3 (0.44 vs. 0.30% of total fatty acids; P<0.001 than confined animals. The detrimental effects of pasture grazing on growth performance and on some important meat quality traits explain the limited adoption of this finishing system in organic beef production.

  12. Influence of Finishing and Polishing Techniques and Abrasion on Transmittance and Roughness of Composite Resins.

    Science.gov (United States)

    Carneiro, Pma; Ramos, T M; de Azevedo, C S; de Lima, E; de Souza, Shj; Turbino, M L; Cesar, P F; Matos, A B

    The aim of this study was to evaluate the influence of finishing and polishing systems and toothbrush abrasion on transmittance (T) and surface roughness (Ra) of three composite resins (Filtek Z350 XT, Tetric N-Ceram, and IPS Empress Direct). Eighteen resin disks (10 mm diameter × 2 mm thick) finished by polyester strips had initial surface smoothness recorded, representing phase 1 (P1). Specimens were divided into three groups (n=6) according to the finishing/polishing instrument used (OneGloss, TopGloss, and Sof-Lex) to compose phase 2 samples (P2). Then specimens were subjected to 514 cycles of toothbrush simulation using a toothpaste slurry, with a constant load applied to soft bristles, and were then washed (phase 3=P3). After each phase, the specimens were examined by an optical profiler and spectrophotometer to measure Ra and T. Data were analyzed by analysis of variance, Tukey and Pearson tests. T values were statistically influenced by composite resin ( p=0.000) and phase of measurement ( p=0.000) factors, while the finishing/polishing system used ( p=0.741) did not affect T. On the other hand, Ra values were statistically affected by the factor finishing/polishing system ( p=0.000), but not by composite resin ( p=0.100) and phase of measurement ( p=0.451). Tetric N-Ceram and Empress Direct presented higher values of roughness when polished by OneGloss, while TopGloss and Sof-Lex showed a lower roughness. It can be concluded that composite resins transmitted more light after dental abrasion. Transmittance of composite resins was not modified by the distinct roughness created by finishing/polishing instruments.

  13. Surface texture of resin-modified glass ionomer cements: effects of finishing/polishing systems.

    Science.gov (United States)

    Yap, Adrian U J; Tan, W S; Yeo, J C; Yap, W Y; Ong, S B

    2002-01-01

    This study investigated the surface texture of two resin-modified glass ionomer cements (RMGICs) in the vertical and horizontal axis after treatment with different finishing/polishing systems. Class V preparations were made on the buccal and lingual/palatal surfaces of freshly extracted teeth. The cavities on each tooth were restored with Fuji II LC (GC) and Photac-Fil Quick (ESPE) according to manufacturers' instructions. Immediately after light-polymerization, gross finishing was done with 8-flute tungsten carbide burs. The teeth were then randomly divided into four groups and finished/polished with (a) Robot Carbides (RC); (b) Super-Snap system (SS); (c) OneGloss (OG) and (d) CompoSite Points (CS). The sample size for each material-finishing/polishing system combination was eight. The mean surface roughness (microm) in vertical (RaV) and horizontal (RaH) axis was measured using a profilometer. Data was subjected to ANOVA/Scheffe's tests and Independent Samples t-test at significance level 0.05. Mean RaV ranged from 0.59-1.31 and 0.83-1.52, while mean RaH ranged from 0.80-1.43 and 0.85-1.58 for Fuji II LC and Photac-Fil, respectively. Results of statistical analysis were as follows: Fuji II LC: RaV-RC, SSfinished with RC. The use of carbides (RC) and one-step rubber abrasive system (OG) for finishing/polishing of RMGICs is not recommended. Graded abrasive disk (SS) or two-step rubber abrasive (CS) systems should be used instead.

  14. 78 FR 67206 - Qualification Tests for Safety-Related Actuators in Nuclear Power Plants

    Science.gov (United States)

    2013-11-08

    ... Nuclear Power Plants AGENCY: Nuclear Regulatory Commission. ACTION: Revision to regulatory guide; issuance..., ``Qualification Tests for Safety-Related Actuators in Nuclear Power Plants.'' This RG is being revised to provide... Operators Installed Inside the Containment of Nuclear Power Plants,'' dated January 1974. ADDRESSES: Please...

  15. Multi-Parameter Analysis of Surface Finish in Electro-Discharge Machining of Tool Steels

    Directory of Open Access Journals (Sweden)

    Cornelia Victoria Anghel

    2006-10-01

    Full Text Available The paper presents a multi- parameter analysis of surface finish imparted to tool-steel plates by electro-discharge machining (EDM is presented. The interrelationship between surface texture parameters and process parameters is emphasized. An increased number of parameters is studied including amplitude, spacing, hybrid and fractal parameters,, as well. The correlation of these parameters with the machining conditions is investigated. Observed characteristics become more pronounced, when intensifying machining conditions. Close correlation exists between certain surface finish parameters and EDM input variables and single and multiple statistical regression models are developed.

  16. Control software development for magnetorheological finishing of large aperture optical elements

    International Nuclear Information System (INIS)

    Zheng Nan; Li Haibo; Yuan Zhigang; Zhong Bo

    2011-01-01

    Based on the mechanism of magnetorheological finishing, the dwell time function was solved by Jansson-Van Cit-tert algorithm to accomplish the kernel module design. Then the software modularization programming, modular testing and integration testing were conducted. A verification experiment was carried out on a crystal element with full aperture of 500 mm and the element's surface achieved rapid and efficient convergence after the software controlled magnetorheological finishing. It is proved that the software could control the whole polishing process accurately. (authors)

  17. THE INFLUENCE OF GLUTEN - FREE FLOURS ON THE QUALITY INDICATORS OF BISCUIT SEMI - FINISHED PRODUCTS

    Directory of Open Access Journals (Sweden)

    К. G. IORGACHOVA

    2016-12-01

    Full Text Available The article is devoted to the research of applicability of gluten-free flours from cereal crops and from by-products of cereal crop processing - ground crumbs sifted out in a process of flake production from rice, corn and millet during the production of biscuit semi-finished products. Taking into account that viscosity is an important technological characteristic of foam-like biscuit dough, as it determines foam strength and dispersed medium stability, the influence of gluten-free flours on the structural and rheological properties of biscuit dough was studied. It is determined that the substitution of wheat flour for cereal flours leads to viscosity reduction of the dough as a consequence of absence of gluten-forming proteins in them. A comparative analysis of changes in viscous properties of biscuit dough based on flour from flakes crumb while warming it up to 60°C with dough based on cereal flours and dough based on wheat flour was held. It is shown that the presence of partially gelatinized starch granules in flour from flake crumb, as a result of technological peculiarities of their extraction, promotes greater demonstration of thickening properties already at the initial stage of baking than in cereal flours. This leads to an increase of dough viscosity and formation of desired rheological characteristics, which provide the porous structure of finished products. To provide the high quality of gluten-free biscuit semi-finished products, the recipe composition of gluten-free biscuit semi-finished product, based on flour mixture from millet flakes crumb, corn and rice flour, was optimized by using the method of mathematical design of experiments.  The porosity indicator was chosen as the criteria for the evaluation of influence of proportion of gluten-free flours on the quality of biscuit semi-finished products. The response surfaces of dependency of biscuit porosity from mass ratio of recipe components in the composite mixture were

  18. Effects of finishing diet and pre-slaughter fasting time on meat quality in crossbred pigs

    Directory of Open Access Journals (Sweden)

    K. PARTANEN

    2008-12-01

    Full Text Available The effects of the carbohydrate composition of finishing diet (fed from 80 to 107 kg of body weight and the length of pre-slaughter fasting on pork quality were studied in a 2 × 2 factorial experiment with 80 crossbred pigs. The control finishing diet was based on barley and soybean meal, and the fibrous finishing diet was based on barley, barley fibre, faba beans, and rapeseed cake. These diets contained 465 and 362 g starch and 177 and 250 g dietary fibre per kg, respectively. The fasting times of 25 and 41 h were obtained by giving the pigs their last meal at different times. Longer fasting lowered the glycolytic potential of the longissimus lumborum muscle (P = 0.01, whereas the finishing diet had no effect. Different muscles responded differently to the treatments. Longer fasting increased the ultimate pH of the semimembranosus muscle (P = 0.02, but did not affect that of the longissimus lumborum and semispinalis capitis muscles. The finishing diets did not affect the ultimate pH of the investigated muscles. A diet × fasting time interaction was seen in the lightness of the semimembranosus muscle (P = 0.05. The fibrous diet resulted in darker meat than the control diet did in pigs that were fasted for 25 h (P < 0.05. Longer fasting darkened the meat colour in pigs fed the fibrous diet (P < 0.05 but not in those fed the control diet. The meat from the semispinalis capitis muscle was darker in pigs fed the fibrous than those fed the control diet (P = 0.04. The treatments did not affect the colour of the longissimus lumborum muscle. Longer fasting decreased drip loss from the meat of pigs fed the control diet (P < 0.05. The eating quality of the pork was not influenced by the finishing diets or the fasting time. The pigs also grew equally fast on both finishing diets. In conclusion, a moderate alteration in the carbohydrate composition of a finishing diet or longer pre-slaughter fasting can have some effects on pork quality in crossbred pigs

  19. IAQ performance of interior finishing products and the role of LCA

    CSIR Research Space (South Africa)

    Ampofo-Anti, N

    2010-01-01

    Full Text Available of interior finishing products to be more performance-oriented, where performance is defined in terms of the life cycle human health effects 4 . 3.0 LCA – the science-based tool Life Cycle Assessment (LCA) is a science-based tool which is designed... of interior finishing products and the role of LCA Naalamkai Ampofo-Anti, Senior Researcher, CSIR 1.0 Introduction The environmental rating and certification of products is a voluntary, market-based response by industry and business to the consumer’s...

  20. Digital Restoration from Start to Finish How to repair old and damaged photographs

    CERN Document Server

    Ctein,

    2010-01-01

    Digital Restoration: Start to Finish 2nd edition guides you step-by-step through the entire process of restoring old photographs and repairing new ones using Adobe Photoshop, Picture Window, and now Elements. Nothing is left out, from choosing the right hardware and software and getting the photographs into the computer, to getting the finished photo out of the computer and preserving it for posterity.  LEARN HOW TO: Scan faded and damaged prints or films Improve snapshots with Shadow/Highlight adjustment Correct uneven exposure Fix color and skin tones quickly with Curves, plug-ins, a

  1. Pengaruh Berbagai Jenis Bahan Litter terhadap Kualitas Litter Broiler Fase Finisher di Closed House

    OpenAIRE

    Tiwi Metasari; Dian Septinova; Veronica Wanniatie

    2014-01-01

    The aim of this research was to 1) determine the effect of the use of rice husk, wood shavings,rice straw as litter material on litter quality for broiler during the finisher phase in closed house, 2)determine the best type of litter material on litter quality for broiler during the finisher phase in closedhouse. The duration of the research was 26 days. The research was started from 15 April to 10 May2014 in the closed house owned by PT. Rama Jaya Lampung Krawang Sari Village, the District o...

  2. WOOD PROPERTIES AND EFFECT OF WOOD PROPERTIES ON THE WOOD FINISHING

    Directory of Open Access Journals (Sweden)

    Abdulkadir Malkoçoğlu

    2006-04-01

    Full Text Available Wood is basic raw material for furniture and joinery industries with wood structures. Wood is a biological material that has widely different properties depending on species, geographic area where the tree grew, the growth condition, size of the tree at harvest, sawing, and other manufacturing processes. Wood properties have been characterized within two groups as natural and manufacturing factors that effects finishing performance. Grow rate, density, knots, moisture content, extractives and juvenile wood are natural characteristics. Grain orientation, texture, drying and performance expectations are manufacturing characteristics. In this review, the effects of natural and manufacturing characteristics are discussed on the surface finishing performance of wood.

  3. Effects of surface finish and mechanical training on Ni-Ti sheets for elastocaloric cooling

    DEFF Research Database (Denmark)

    Engelbrecht, Kurt; Tusek, Jaka; Sanna, Simone

    2016-01-01

    Elastocaloric cooling has emerged as a promising alternative to vapor compression in recent years. Although the technology has the potential to be more efficient than current technologies, there are many technical challenges that must be overcome to realize devices with high performance...... and acceptable durability. We study the effects of surface finish and training techniques on dog bone shaped polycrystalline samples of NiTi. The fatigue life of several samples with four different surface finishes was measured and it was shown that a smooth surface, especially at the edges, greatly improved...

  4. The nuclear liability conventions revised

    International Nuclear Information System (INIS)

    Reyners, P.

    2004-01-01

    The signature on 12 February 2004 of the Protocols amending respectively the 1960 Paris Convention and the 1963 Brussels Supplementary Convention was the second step of the process of modernisation of the international nuclear liability regime after the adoption in September 1997 of a Protocol revising the 1963 Vienna Convention and of a new Convention on Supplementary Compensation for Nuclear Damage. The common objective of the new instruments is to provide more funds to compensate a larger number of potential victims in respect of a broader range of damage. Another goal of the revision exercise was to maintain the compatibility between the Paris and Vienna based systems, a commitment enshrined in the 1988 Joint Protocol, as well as to ascertain that Paris/Brussels countries could also become a Party to the Convention on Supplementary Compensation. However, while generally consistent vis a vis the Joint Protocol, the provisions of the Paris and Vienna Conventions, as revised, differ on some significant aspects. Another remaining issue is whether the improved international nuclear liability regime will succeed in attracting in the future a larger number of countries, particularly outside Europe, and will so become truly universal. Therefore, the need for international co-operation to address these issues, to facilitate the adoption of new implementing legislation and to ensure that this special regime keeps abreast of economic and technological developments, is in no way diminished after the revision of the Conventions.(author)

  5. Concise revision of the Sarcospermataceae

    NARCIS (Netherlands)

    Lam, H.J.; Royen, van P.

    1952-01-01

    After the senior writer, together with W. W. Varossieau, had published a revision of this monogeneric family (Blumea III, 1938—’39 and IV, 1941), some more material has been examined by us and, moreover, some new species have been described. Thanks to the courtesy of Prof. F. Gagnepain of Paris, and

  6. Guidelines for Curriculum Development. Revised.

    Science.gov (United States)

    Kistler, K.; And Others

    The curriculum development process explained in this booklet was first implemented at College of the Redwoods in May 1986 and then revised in June 1989. First, information on the college's Curriculum Committee is provided, indicating that the committee was formed to plan credit/non-credit courses; evaluate and approve additions, modifications, or…

  7. Revised Accounting for Business Combinations

    Science.gov (United States)

    Wilson, Arlette C.; Key, Kimberly

    2008-01-01

    The Financial Accounting Standards Board (FASB) has recently issued Statement of Financial Accounting Standards No. 141 (Revised 2007) Business Combinations. The object of this Statement is to improve the relevance, representational faithfulness, and comparability of reported information about a business combination and its effects. This Statement…

  8. How Adults Learn. Revised Edition.

    Science.gov (United States)

    Kidd, J. R.

    The book's emphasis is on learning during the years of adulthood and examines present-day practice of adult education for practitioners. This revised edition brings up to date advances in such areas of learning as controversial theory; the effects of environment; sensory processes; intellectual capacities; motivation and attitude; transactional…

  9. A revision of the Paronychiinae

    NARCIS (Netherlands)

    Chaudhri, Mohammad Nazeer

    1968-01-01

    This study was undertaken, in April 1964, at the suggestion of Prof. Dr. J. Lanjouw. The need for such a revision, was, however, stressed by the authors of the subtribe, viz. PAX et K. HOFFMANN, who, while delimiting these genera, remarked that the Systematics of both the (main) genera of this

  10. Diet History Questionnaire: Database Revision History

    Science.gov (United States)

    The following details all additions and revisions made to the DHQ nutrient and food database. This revision history is provided as a reference for investigators who may have performed analyses with a previous release of the database.

  11. [Revised practice guideline 'Anaemia in midwifery practice'

    NARCIS (Netherlands)

    Beentjes, M.; Jans, S.M.P.J.

    2012-01-01

    The practice guideline of the Royal Dutch Organization of Midwives 'Anaemia in primary care midwifery practice' published in 2000, has recently been revised. The revised guideline takes physiological haemodilution during pregnancy into consideration and provides gestation specific reference values

  12. Revised Human Health Risk Assessment on Chlorpyrifos

    Science.gov (United States)

    We have revised our human health risk assessment and drinking water exposure assessment for chlorpyrifos that supported our October 2015 proposal to revoke all food residue tolerances for chlorpyrifos. Learn about the revised analysis.

  13. 75 FR 60485 - NRC Enforcement Policy Revision

    Science.gov (United States)

    2010-09-30

    ... NUCLEAR REGULATORY COMMISSION [NRC-2008-0497] NRC Enforcement Policy Revision AGENCY: Nuclear Regulatory Commission. ACTION: Policy statement. SUMMARY: The Nuclear Regulatory Commission (NRC or Commission) is publishing a major revision to its Enforcement Policy (Enforcement Policy or Policy) to...

  14. Humeral windows in revision total elbow arthroplasty.

    Science.gov (United States)

    Peach, Chris A; Salama, Amir; Stanley, David

    2016-04-01

    The use of cortical windows for revision elbow arthroplasty has not previously been widely reported. Their use aids safe revision of a well fixed humeral prosthesis and can be used in the setting of dislocation, periprosthetic fracture or aseptic loosening of the ulnar component. We describe our technique and results of cortical windows in the distal humerus for revision elbow arthroplasty surgery.

  15. A taxonomic revision of the genus Podocarpus

    NARCIS (Netherlands)

    Laubenfels, de D.J.

    1985-01-01

    In connection with the forthcoming revision of the Coniferae for the Flora Malesiana, the author thought it necessary to revise the genus Podocarpus. Although this genus has a substantial representation in Malesia (30 species), the revision is too involved to be appropriate with the Flora Malesiana

  16. 24 CFR 968.225 - Budget revisions.

    Science.gov (United States)

    2010-04-01

    ... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false Budget revisions. 968.225 Section... Fewer Than 250 Units) § 968.225 Budget revisions. (a) A PHA shall not incur any modernization cost in excess of the total HUD-approved CIAP budget. A PHA shall submit a budget revision, in a form prescribed...

  17. 7 CFR 3015.115 - Budget revisions.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 15 2010-01-01 2010-01-01 false Budget revisions. 3015.115 Section 3015.115..., DEPARTMENT OF AGRICULTURE UNIFORM FEDERAL ASSISTANCE REGULATIONS Programmatic Changes and Budget Revisions § 3015.115 Budget revisions. (a) Nonconstruction projects. (1) Except as provided in paragraph (a)(2) of...

  18. 48 CFR 15.307 - Proposal revisions.

    Science.gov (United States)

    2010-10-01

    ... AND CONTRACT TYPES CONTRACTING BY NEGOTIATION Source Selection 15.307 Proposal revisions. (a) If an... allow proposal revisions to clarify and document understandings reached during negotiations. At the... submit a final proposal revision. The contracting officer is required to establish a common cut-off date...

  19. Resource Conservation and Recovery Act, Part B Permit Application [for the Waste Isolation Pilot Plant (WIPP)]. Chapter E, Appendix E1, Chapter L, Appendix L1: Volume 12, Revision 3

    Energy Technology Data Exchange (ETDEWEB)

    1993-01-01

    The Waste Isolation Pilot Plant (WIPP) Project was authorized by the US Department of Energy 5 (DOE) National Security and Military Applications of the Nuclear Energy Authorization Act of 1980 (Public Law 96-164). Its legislative mandate is to provide a research and development facility to demonstrate the safe disposal of radioactive waste resulting from national defense programs and activities. To fulfill this mandate, the WIPP facility has been designed to perform scientific investigations of the behavior of bedded salt as a repository medium and the interactions between the soft and radioactive wastes. In 1991, DOE proposed to initiate a experimental Test Phase designed to demonstrate the performance of the repository. The Test Phase activities involve experiments using transuranic (TRU) waste typical of the waste planned for future disposal at the WIPP facility. Much of this TRU waste is co-contaminated with chemical constituents which are defined as hazardous under HWMR-7, Pt. II, sec. 261. This waste is TRU mixed waste and is the subject of this application. Because geologic repositories, such as the WIPP facility, are defined under the Resource Conservation and Recovery Act (RCRA) as land disposal facilities, the groundwater monitoring requirements of HWMR-7, PLV, Subpart X, must be addressed. HWMR-7, Pt. V, Subpart X, must be addressed. This appendix demonstrates that groundwater monitoring is not needed in order to demonstrate compliance with the performance standards; therefore, HWMR-7, Pt.V, Subpart F, will not apply to the WIPP facility.

  20. Plutonium Finishing Plan (PFP) Treatment and Storage Unit Interim Status Closure Plan

    International Nuclear Information System (INIS)

    PRIGNANO, A.L.

    2000-01-01

    This document describes the planned activities and performance standards for closing the Plutonium Finishing Plant (PFP) Treatment and Storage Unit. The PFP Treatment and Storage Unit is located within the 234-52 Building in the 200 West Area of the Hanford Facility. Although this document is prepared based upon Title 40 Code of Federal Regulations (CFR), Part 265, Subpart G requirements, closure of the unit will comply with Washington Administrative Code (WAC) 173-303-610 regulations pursuant to Section 5.3 of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Action Plan (Ecology et al. 1996). Because the PFP Treatment and Storage Unit manages transuranic mixed (TRUM) waste, there are many controls placed on management of the waste. Based on the many controls placed on management of TRUM waste, releases of TRUM waste are not anticipated to occur in the PFP Treatment and Storage Unit. Because the intention is to clean close the PFP Treatment and Storage Unit, postclosure activities are not applicable to this closure plan. To clean close the unit, it will be demonstrated that dangerous waste has not been left onsite at levels above the closure performance standard for removal and decontamination. If it is determined that clean closure is not possible or is environmentally impractical, the closure plan will be modified to address required postclosure activities. The PFP Treatment and Storage Unit will be operated to immobilize and/or repackage plutonium-bearing waste in a glovebox process. The waste to be processed is in a solid physical state (chunks and coarse powder) and will be sealed into and out of the glovebox in closed containers. The containers of immobilized waste will be stored in the glovebox and in additional permitted storage locations at PFP. The waste will be managed to minimize the potential for spills outside the glovebox, and to preclude spills from reaching soil. Containment surfaces will be maintained to ensure