WorldWideScience

Sample records for demolition sites closure

  1. 200 West Area Ash Pit Demolition Site closure plan. Revision 1

    International Nuclear Information System (INIS)

    Ruck, F.R.

    1994-01-01

    The Ash Pit Demolition Site had two known demolition events, the first occurred in November of 1984, and the second occurred in June of 1986. These demolition events were a form of thermal treatment for discarded explosive chemical products. Because the Ash Pit Demolition Site will no longer be used for this thermal activity, the site will be closed. Closure will be conducted pursuant to the requirements of the Washington State Department of Ecology (Ecology) ''Dangerous Waste Regulations'', Washington Administrative Code (WAC) 173-303-610 and 40 Code of Federal Regulations (CFR) 270.1. The 200 West Area Ash Pit Demolition Site Closure Plan consists of a Part A, Form 3, Dangerous Waste Permit Application (Revision 4) and a closure plan. An explanation of the Part A, Form 3, submitted with this closure plan is provided at the beginning of the Part A Section. The closure plan consists of nine chapters and five appendices. This closure plan presents a description of the Ash,Pit Demolition Site, the history of the waste treated, and the approach that will be followed to close the Ash Pit Demolition Site. Because there were no radioactively contaminated chemicals involved in the demolitions, the information on radionuclides is provided for ''information only''. Remediation of any radioactive contamination is not within the scope of this closure plan. Only dangerous constituents derived from Ash Pit Demolition Site operations will be addressed in this closure plan in accordance with WAC 173-303-610(2)(b)(i)

  2. 200 West Ash Pit Demolition Site closure plan

    International Nuclear Information System (INIS)

    1992-11-01

    The Hanford Facility is owned by the US Government and operated by the US Department of Energy, Richland Field Office. Dangerous waste and mixed waste (containing both radioactive and dangerous components) are managed and produced on the Hanford Facility. Westinghouse Hanford Company is a major contractor to the US Department of Energy, Richland Field Office and serves as cooperator of the 200 West Ash Pit Demolition Site, the unit addressed in this closure plan. The 200 West Ash Pit Demolition Site Closure Plan consists of a Part A Permit Application (Revision 3) and a closure plan. An explanation of the Part A Permit Application revision is provided at the beginning of the Part A section. The closure plan consists of nine chapters and three appendices. This 200 West Ash Pit Demolition Site Closure Plan submittal contains information current as of October 15, 1992

  3. 218-E-8 Borrow Pit Demolition Site closure plan. Revision 1

    International Nuclear Information System (INIS)

    Ruck, F.R.

    1994-01-01

    The 218-E-8 Demolition Site was the site of a single demolition event in November of 1984. This demolition event was a form of thermal treatment for discarded explosive chemical products. Because the 218-E-8 Demolition Site will no longer be used for this thermal activity, the site will be closed. Closure will be conducted pursuant to the requirements of the Washington State Department of Ecology (Ecology) ''Dangerous Waste Regulations,'' Washington Administrative Code (WAC) 173-303-610 and 40 Code of Federal Regulations (CFR) 270.1. The 218-E-8 Borrow Pit Demolition Site Closure Plan consists of a Hanford Facility Dangerous Waste Part A Permit Application, Form 3, Revision 4, and a closure plan. An explanation of the Part A Form 3, submitted with this closure plan is provided at the beginning of the Part A Section. The closure plan consists of nine chapters and five appendices. This closure plan presents a description of the 218-E-8 Demolition Site, the history of the waste treated, and the approach that will be followed to close the 218-E-8 Demolition Site. Because there were no radioactively contaminated chemicals involved in t he demolitions at the 218-E-8 Borrow Pit site, the information on radionuclides is provided for ''information only.'' Remediation of any radioactive contamination is not within the scope of this closure plan. Only dangerous constituents derived from 218-E-8 Demolition Site operations will be addressed in this closure plan in accordance with WAC 173-303-610(2)(b)(i)

  4. Hanford Patrol Academy demolition sites closure plan

    Energy Technology Data Exchange (ETDEWEB)

    1993-09-30

    The Hanford Site is owned by the U.S. Government and operated by the U.S. Department of Energy, Richland Operations Office. Westinghouse Hanford Company is a major contractor to the U.S. Department of Energy, Richland Operations Office and serves as co-operator of the Hanford Patrol Academy Demolition Sites, the unit addressed in this paper. This document consists of a Hanford Facility Dangerous Waste Part A Permit Application, Form 3 (Revision 4), and a closure plan for the site. An explanation of the Part A Form 3 submitted with this closure plan is provided at the beginning of the Part A section. This Hanford Patrol Academy Demolition Sites Closure Plan submittal contains information current as of December 15, 1994.

  5. Hanford Patrol Academy Demolition Sites Closure Plan

    International Nuclear Information System (INIS)

    1992-11-01

    From 1975 to 1991 the Hanford Patrol Academy Demolition Sites (HPADS) were used for demolition events. These demolition events were a form of thermal treatment for spent or abandoned chemical waste. Because the HPADS will no longer be used for this thermal activity, the sites will be closed. Closure will be conducted pursuant to the requirements of the Washington State Department of Ecology (Ecology) Dangerous Waste Regulations, Washington Administrative Code (WAC) 173-303-610 and 40 CFR 270.1. Closure also will satisfy closure requirements of WAC 173-303-680 and for the thermal treatment closure requirements of 40 CFR 265.381. This closure plan presents a description of the HPADS, the history of the waste treated, and the approach that will be followed to close the HPADS. Because dangerous waste does not include the source, special nuclear, and by-product material components of mixed waste, radionuclides are not within the scope of WAC 173-303 or of this closure plan. The information on radionuclides is provided only for general knowledge where appropriate. Only dangerous constituents derived from HPADS operations will be addressed in this closure plan in accordance with WAC 173-303-610(2)(b)(i). The HPADS are actually two distinct soil closure areas within the Hanford Patrol Academy training area

  6. 218 E-8 Borrow Pit Demolition Site clean closure soil evaluation report

    International Nuclear Information System (INIS)

    Korematsu-Olund, D.M.

    1995-01-01

    This report summarizes the sampling activities undertaken and the analytical results obtained in a soil sampling and analyses study performed for the 218 E-8 Borrow Pit Demolition Site (218 E-8 Demolition Site). The 218 E-8 Demolition Site is identified as a Resource Conservation and Recovery Act (RCRA) treatment unit that will be closed in accordance with the applicable laws and regulations. The site was used for the thermal treatment of discarded explosive chemical products. No constituents of concern were found in concentrations indicating contamination of the soil by 218 E-8 Demolition Site activities

  7. Bat Surveys of Retired Facilitiies Scheduled for Demolition by Washington Closure Hanford

    Energy Technology Data Exchange (ETDEWEB)

    Gano, K. A.; Lucas, J. G.; Lindsey, C. T.

    2011-06-30

    This project was conducted to evaluate buildings and facilities remaining in the Washington Closure Hanford (WCH) deactivation, decontamination, decommissioning, and demolition schedule for bat roost sites. The project began in spring of 2009 and was concluded in spring of 2011. A total of 196 buildings and facilities were evaluated for the presence of bat roosting sites. The schedule for the project was prioritized to accommodate the demolition schedule. As the surveys were completed, the results were provided to the project managers to facilitate planning and project completion. The surveys took place in the 300 Area, 400 Area, 100-H, 100-D, 100-N, and 100-B/C Area. This report is the culmination of all the bat surveys and summarizes the findings by area and includes recommended mitigation actions where bat roosts were found.

  8. Environmental impacts of manufactured gas plant demolition: examples from site remediation experience

    Energy Technology Data Exchange (ETDEWEB)

    Unites, D. [Atlantic Environmental Services, Inc., Colchester, CT (United States)

    1995-12-31

    Inappropriate demolition of manufactured gas plant (MGP) sites may leave a continuing legacy in the environmental record. Much of the contamination encountered at former gas plants originated from on-site disposal or from spills and leaks during operations. However, some of the greatest potential for continual release comes from inappropriately decommissioned vessels and tanks. These structures contained liquids such as tars, oils, water, and other fluids associated with by-product removal or the gas stream purification process. Inorganic `solids` constitute another, although generally minor, source of contaminants during demolition. These contaminants include: cyanide- and sulfide-containing purifier materials; asbestos from roofing, pipe lagging, etc.; mercury from controls and manometers; and lead from painted surfaces. Normal elements of decommissioning and dismantling include: purging the piping system with inert gas; removal and sale of liquids having commercial value; disposal or abandonment of non-saleable liquids; scrapping and dismantling of above-grade metal vessels; abandonment of below-grade vessels; and demolition of above-grade buildings. Depending on the time from the cessation of operations to the demolition, some steps may have been omitted. Appropriate demolition would also take into account removal and disposal of asbestos, cyanide, lead, and mercury-containing materials prior to razing structures. By employing precautions during demolition, widespread contamination can be avoided and subsequent reuse of the site can be facilitated.

  9. Addendum to the Closure Report for Corrective Action Unit 113: Area 25 R-MAD Facility, Nevada National Security Site, Nevada

    International Nuclear Information System (INIS)

    2011-01-01

    This addendum to the Closure Report for Corrective Action Unit 113: Area 25, Reactor Maintenance, Assembly, and Disassembly Facility, Building 3110, Nevada Test Site, Nevada, DOE/NV--891-VOL I-Rev. 1, dated July 2003, provides details of demolition, waste disposal, and use restriction (UR) modification for Corrective Action Unit 113, Area 25 R-MAD Facility. Demolition was completed on July 15, 2010, when the last of the building debris was disposed. Final field activities were concluded on August 30, 2010, after all equipment was demobilized and UR signs were posted. This work was funded by the American Recovery and Reinvestment Act.

  10. Y-12 Construction/Demolition Landfill VII: Permit application: Part 1 and 2

    International Nuclear Information System (INIS)

    1992-04-01

    The United States Department of Energy (DOE) has three major operating facilities on the DOE Oak Ridge Reservation (ORR) at Oak Ridge, Tennessee: the Y-12 Plant, the K-25 Site, and the Oak Ridge National Laboratory (ORNL). Operations associated with the DOE energy research and production facilities at Oak Ridge result in the production of several types of waste materials. Disposal of solid waste (as defined in the Solid Waste Processing and Disposal Rules for Tennessee) in disposal facilities operated by the Y-12 Plant is the responsibility of Y-12 Waste Management Division (MWD). The WMD is proposing to develop a facility that will include two new disposal units: one for construction/demolition waste and spoil and one for industrial solid waste. This manual describes the closure and post-closure plans for the construction/demolition waste and spoil disposal unit. This disposal unit is referred to as the Y-12 Construction/Demolition Landfill VII (CD-VII) and is to be operated by the Y-12 Plant for the DOE. This will be a Tennessee Department of Environment and Conservation/Division of Solid Waste Management (TDEC/DSWM) Class IV disposal unit

  11. Lessons Learned from the On-Site Disposal Facility at Fernald Closure Project

    International Nuclear Information System (INIS)

    Kumthekar, U.A.; Chiou, J.D.

    2006-01-01

    The On-Site Disposal Facility (OSDF) at the U.S. Department of Energy's (DOE) Fernald Closure Project near Cincinnati, Ohio is an engineered above-grade waste disposal facility being constructed to permanently store low level radioactive waste (LLRW) and treated mixed LLRW generated during Decommissioning and Demolition (D and D) and soil remediation performed in order to achieve the final land use goal at the site. The OSDF is engineered to store 2.93 million cubic yards of waste derived from the remediation activities. The OSDF is intended to isolate its LLRW from the environment for at least 200 years and for up to 1,000 years to the extent practicable and achievable. Construction of the OSDF started in 1997 and waste placement activities will complete by the middle of April 2006 with the final cover (cap) placement over the last open cell by the end of Spring 2006. An on-site disposal alternative is considered critical to the success of many large-scale DOE remediation projects throughout the United States. However, for various reasons this cost effective alternative is not readily available in many cases. Over the last ten years Fluor Fernald Inc. has cumulated many valuable lessons learned through the complex engineering, construction, operation, and closure processes of the OSDF. Also in the last several years representatives from other DOE sites, State agencies, as well as foreign government agencies have visited the Fernald site to look for proven experiences and practices, which may be adapted for their sites. This paper present a summary of the major issues and lessons leaned at the Fernald site related to engineering, construction, operation, and closure processes for the disposal of remediation waste. The purpose of this paper is to share lessons learned and to benefit other projects considering or operating similar on-site disposal facilities from our successful experiences. (authors)

  12. 76 FR 5365 - Environmental Management Site-Specific Advisory Board, Nevada

    Science.gov (United States)

    2011-01-31

    ... Industrial Sites and Soils Committees of the Environmental Management Site-Specific Advisory Board (EM SSAB... sites at the Nevada National Security Site including decontamination, closure, re-use and/or demolition. Purpose of the Soils Committee: The purpose of the Committee is to focus on issues related to soil...

  13. 75 FR 71677 - Environmental Management Site-Specific Advisory Board, Nevada

    Science.gov (United States)

    2010-11-24

    ... Industrial Sites and Soils Committees of the Environmental Management Site-Specific Advisory Board (EM SSAB... sites at the Nevada Test Site including decontamination, closure, re-use and/or demolition. Purpose of the Soils Committee: The purpose of the Committee is to focus on issues related to soil contamination...

  14. Nuclear Rocket Facility Decommissioning Project: Controlled Explosive Demolition of Neutron-Activated Shield Wall

    International Nuclear Information System (INIS)

    Michael R, Kruzic

    2008-01-01

    Located in Area 25 of the Nevada Test Site (NTS), the Test Cell A (TCA) Facility (Figure 1) was used in the early to mid-1960s for testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program, to further space travel. Nuclear rocket testing resulted in the activation of materials around the reactors and the release of fission products and fuel particles. The TCA facility, known as Corrective Action Unit 115, was decontaminated and decommissioned (D and D) from December 2004 to July 2005 using the Streamlined Approach for Environmental Restoration (SAFER) process, under the Federal Facility Agreement and Consent Order. The SAFER process allows environmental remediation and facility closure activities (i.e., decommissioning) to occur simultaneously, provided technical decisions are made by an experienced decision maker within the site conceptual site model. Facility closure involved a seven-step decommissioning strategy. First, preliminary investigation activities were performed, including review of process knowledge documentation, targeted facility radiological and hazardous material surveys, concrete core drilling and analysis, shield wall radiological characterization, and discrete sampling, which proved to be very useful and cost-effective in subsequent decommissioning planning and execution and worker safety. Second, site setup and mobilization of equipment and personnel were completed. Third, early removal of hazardous materials, including asbestos, lead, cadmium, and oil, was performed ensuring worker safety during more invasive demolition activities. Process piping was to be verified void of contents. Electrical systems were de-energized and other systems were rendered free of residual energy. Fourth, areas of high radiological contamination were decontaminated using multiple methods. Contamination levels varied across the facility. Fixed beta/gamma contamination levels ranged up to 2 million disintegrations per minute (dpm)/100

  15. Nuclear Rocket Facility Decommissioning Project: Controlled Explosive Demolition of Neutron-Activated Shield Wall

    Energy Technology Data Exchange (ETDEWEB)

    Michael R. Kruzic

    2008-06-01

    Located in Area 25 of the Nevada Test Site (NTS), the Test Cell A (TCA) Facility (Figure 1) was used in the early to mid-1960s for testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program, to further space travel. Nuclear rocket testing resulted in the activation of materials around the reactors and the release of fission products and fuel particles. The TCA facility, known as Corrective Action Unit 115, was decontaminated and decommissioned (D&D) from December 2004 to July 2005 using the Streamlined Approach for Environmental Restoration (SAFER) process, under the Federal Facility Agreement and Consent Order. The SAFER process allows environmental remediation and facility closure activities (i.e., decommissioning) to occur simultaneously, provided technical decisions are made by an experienced decision maker within the site conceptual site model. Facility closure involved a seven-step decommissioning strategy. First, preliminary investigation activities were performed, including review of process knowledge documentation, targeted facility radiological and hazardous material surveys, concrete core drilling and analysis, shield wall radiological characterization, and discrete sampling, which proved to be very useful and cost-effective in subsequent decommissioning planning and execution and worker safety. Second, site setup and mobilization of equipment and personnel were completed. Third, early removal of hazardous materials, including asbestos, lead, cadmium, and oil, was performed ensuring worker safety during more invasive demolition activities. Process piping was to be verified void of contents. Electrical systems were de-energized and other systems were rendered free of residual energy. Fourth, areas of high radiological contamination were decontaminated using multiple methods. Contamination levels varied across the facility. Fixed beta/gamma contamination levels ranged up to 2 million disintegrations per minute (dpm)/100

  16. 75 FR 64718 - Environmental Management Site-Specific Advisory Board, Nevada

    Science.gov (United States)

    2010-10-20

    ... Test Site including decontamination, closure, re-use and/or demolition. Purpose of the Soils Committee: The purpose of the Committee is to focus on issues related to soil contamination at the Nevada Test... Industrial Sites and Soils Committees of the Environmental Management Site-Specific Advisory Board (EM SSAB...

  17. Nevada Test Site closure program

    International Nuclear Information System (INIS)

    Shenk, D.P.

    1994-08-01

    This report is a summary of the history, design and development, procurement, fabrication, installation and operation of the closures used as containment devices on underground nuclear tests at the Nevada Test Site. It also addresses the closure program mothball and start-up procedures. The Closure Program Document Index and equipment inventories, included as appendices, serve as location directories for future document reference and equipment use

  18. Decommissioning and demolition 1992

    International Nuclear Information System (INIS)

    Whyte, I.L.

    1992-01-01

    The decommissioning and demolition of structures offshore, onshore and in nuclear works involves new technologies and industries in demolition and removal. The aim of the conference was to provide a forum to keep up to date with technological developments, to publicise new techniques and to share and discuss present and future plans. A particular feature was the multi-disciplinary approach to promote and encourage communication between different sectors of this difficult field of operations. The conference emphasised not only technical issues but also legislative, management and health and safety aspects. Papers were presented by practising engineers, contractors and research workers involved in offshore structures, buildings, power stations, contaminated sites, nuclear plant and includes specialist techniques of cutting, lifting, explosives, ground treatment and decontamination. Many valuable case histories and records based on practical experience were reported. The volume provides a reference source on the state-of-the-art in decommissioning and demolition. The ten papers relevant to the decommissioning and demolition of nuclear facilities are indexed separately. (Author)

  19. Single-site neural tube closure in human embryos revisited.

    Science.gov (United States)

    de Bakker, Bernadette S; Driessen, Stan; Boukens, Bastiaan J D; van den Hoff, Maurice J B; Oostra, Roelof-Jan

    2017-10-01

    Since the multi-site closure theory was first proposed in 1991 as explanation for the preferential localizations of neural tube defects, the closure of the neural tube has been debated. Although the multi-site closure theory is much cited in clinical literature, single-site closure is most apparent in literature concerning embryology. Inspired by Victor Hamburgers (1900-2001) statement that "our real teacher has been and still is the embryo, who is, incidentally, the only teacher who is always right", we decided to critically review both theories of neural tube closure. To verify the theories of closure, we studied serial histological sections of 10 mouse embryos between 8.5 and 9.5 days of gestation and 18 human embryos of the Carnegie collection between Carnegie stage 9 (19-21 days) and 13 (28-32 days). Neural tube closure was histologically defined by the neuroepithelial remodeling of the two adjoining neural fold tips in the midline. We did not observe multiple fusion sites in neither mouse nor human embryos. A meta-analysis of case reports on neural tube defects showed that defects can occur at any level of the neural axis. Our data indicate that the human neural tube fuses at a single site and, therefore, we propose to reinstate the single-site closure theory for neural tube closure. We showed that neural tube defects are not restricted to a specific location, thereby refuting the reasoning underlying the multi-site closure theory. Clin. Anat. 30:988-999, 2017. © 2017 Wiley Periodicals, Inc. © 2017 Wiley Periodicals, Inc.

  20. Closure Strategy Nevada Test Site Area 5 Radioactive Waste Management Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Management

    2007-03-01

    This paper presents an overview of the strategy for closure of part of the Area 5 Radioactive Waste Management Site (RWMS) at the Nevada Test Site (NTS), which is about 65 miles northwest of Las Vegas, Nevada (Figure 1). The Area 5 RWMS is in the northern part of Frenchman Flat, approximately 14 miles north of Mercury. The Area 5 RWMS encompasses 732 acres subdivided into quadrants, and is bounded by a 1,000-foot (ft)-wide buffer zone. The northwest and southwest quadrants have not been developed. The northeast and southeast quadrants have been used for disposal of unclassified low-level radioactive waste (LLW) and indefinite storage of classified materials. This paper focuses on closure of the 38 waste disposal and classified material storage units within the southeast quadrant of the Area 5 RWMS, called the ''92-Acre Area''. The U.S Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) is currently planning to close the 92-Acre Area by 2011. Closure planning for this site must take into account the regulatory requirements for a diversity of waste streams, disposal and storage configurations, disposal history, and site conditions. For ease of discussion, the 92-Acre Area has been subdivided into six closure units defined by waste type, location, and similarity in regulatory requirements. Each of the closure units contains one or more waste disposal units; waste disposal units are also called waste disposal cells. The paper provides a brief background of the Area 5 RWMS, identifies key closure issues for the 92-Acre Area, recommends actions to address the issues, and provides the National Security Technologies, LLC (NSTec), schedule for closure.

  1. Site Closure Strategy Model for Creosote Site

    International Nuclear Information System (INIS)

    Coll, F.R.; Gray, D.R.

    2009-01-01

    In conjunction with RCRA site corrective action at an active wood preserving facility, a risk-based site closure strategy was developed and incorporated the performance of a dense non-aqueous phase liquid (DNAPL) source recovery remedy, a monitored natural attenuation (MNA) remedy for dissolved phase groundwater, and institutional controls. Innovative creosote DNAPL source recovery has been undertaken at the Site since 1998. Pooled creosote DNAPL is present 90 feet below ground within a transmissive sand and gravel aquifer with a saturated thickness of approximately 80 feet. The creosote DNAPL source is situated on the property boundary of the site and has generated a 1/2 mile off-site dissolved phase plume, creating significant NAPL management and remedial technology verification issues. To date, over 120,000 gallons of creosote DNAPL have been recovered from the subsurface utilizing a modified circulation well technology. A mass discharge flux protocol was developed to serve as a major performance metrics for the continuation of source removal efforts and to support the application of monitored natural attenuation as an associated remedial technology for groundwater. The mass removal success has supported the MNA remedy for dissolved phase groundwater and the associated development of institutional controls. The enacted site management strategy outlines the current and future risk management activities for the Site and represents an appropriate site closure strategy for the Site. (authors)

  2. The Office of Site Closure: Progress in the Face of Challenges

    International Nuclear Information System (INIS)

    Fiore, J. J.; Murphie, W. E.; Meador, S. W.

    2002-01-01

    The Office of Site Closure (OSC) was formed in November 1999 when the Department of Energy's (DOE's) Office of Environmental Management (EM) reorganized to focus specifically on site cleanup and closure. OSC's objective is to achieve safe and cost-effective cleanups and closures that are protective of our workers, the public, and the environment, now and in the future. Since its inception, OSC has focused on implementing a culture of safe closure, with emphasis in three primary areas: complete our responsibility for the Closure Sites Rocky Flats, Mound, Fernald, Ashtabula, and Weldon Spring; complete our responsibility for cleanup at sites where the DOE mission has been completed (examples include Battelle King Avenue and Battelle West Jefferson in Columbus, and General Atomics) or where other Departmental organizations have an ongoing mission (examples include the Brookhaven, Livermore, or Los Alamos National Laboratories, and the Nevada Test Site); and create a framework a nd develop specific business closure tools that will help sites close, such as guidance for and decisions on post-contract benefit liabilities, records retention, and Federal employee incentives for site closure. This paper discusses OSC's 2001 progress in achieving site cleanups, moving towards site closure, and developing specific business closure tools to support site closure. It describes the tools used to achieve progress towards cleanup and closure, such as the application of new technologies, changes in contracting approaches, and the development of agreements between sites and with host states. The paper also identifies upcoming challenges and explores options for how Headquarters and the sites can work together to address these challenges. Finally, it articulates OSC's new focus on oversight of Field Offices to ensure they have the systems in place to oversee contractor activities resulting in site cleanups and closures

  3. Closure Report for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2009-07-31

    Corrective Action Unit (CAU) 139 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Waste Disposal Sites' and consists of the following seven Corrective Action Sites (CASs), located in Areas 3, 4, 6, and 9 of the Nevada Test Site: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Closure activities were conducted from December 2008 to April 2009 according to the FFACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 139 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007b). The corrective action alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls. Closure activities are summarized. CAU 139, 'Waste Disposal Sites,' consists of seven CASs in Areas 3, 4, 6, and 9 of the NTS. The closure alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls. This CR provides a summary of completed closure activities, documentation of waste disposal, and confirmation that remediation goals were met. The following site closure activities were performed at CAU 139 as documented in this CR: (1) At CAS 03-35-01, Burn Pit, soil and debris were removed and disposed as LLW, and debris was removed and disposed as sanitary waste. (2) At CAS 04-08-02, Waste Disposal Site, an administrative UR was implemented. No postings or post-closure monitoring are required. (3) At CAS 04-99-01, Contaminated Surface Debris, soil and debris were removed and disposed as LLW, and debris was removed and disposed as sanitary waste. (4) At CAS 06-19-02, Waste Disposal Site/Burn Pit, no work was performed. (5) At CAS 06-19-03, Waste Disposal Trenches, a native soil cover was installed

  4. Closure Report for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2009-01-01

    Corrective Action Unit (CAU) 139 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Waste Disposal Sites' and consists of the following seven Corrective Action Sites (CASs), located in Areas 3, 4, 6, and 9 of the Nevada Test Site: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Closure activities were conducted from December 2008 to April 2009 according to the FFACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 139 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007b). The corrective action alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls. Closure activities are summarized. CAU 139, 'Waste Disposal Sites,' consists of seven CASs in Areas 3, 4, 6, and 9 of the NTS. The closure alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls. This CR provides a summary of completed closure activities, documentation of waste disposal, and confirmation that remediation goals were met. The following site closure activities were performed at CAU 139 as documented in this CR: (1) At CAS 03-35-01, Burn Pit, soil and debris were removed and disposed as LLW, and debris was removed and disposed as sanitary waste. (2) At CAS 04-08-02, Waste Disposal Site, an administrative UR was implemented. No postings or post-closure monitoring are required. (3) At CAS 04-99-01, Contaminated Surface Debris, soil and debris were removed and disposed as LLW, and debris was removed and disposed as sanitary waste. (4) At CAS 06-19-02, Waste Disposal Site/Burn Pit, no work was performed. (5) At CAS 06-19-03, Waste Disposal Trenches, a native soil cover was installed, and a UR was

  5. Closure Plan for the Area 5 Radioactive Waste Management Site at the Nevada Test Site

    International Nuclear Information System (INIS)

    NSTec Environmental Management

    2008-01-01

    The Area 5 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec), for the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the preliminary closure plan for the Area 5 RWMS at the NTS that was presented in the Integrated Closure and Monitoring Plan (DOE, 2005a). The major updates to the plan include a new closure schedule, updated closure inventory, updated site and facility characterization data, the Title II engineering cover design, and the closure process for the 92-Acre Area of the RWMS. The format and content of this site-specific plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). This interim closure plan meets closure and post-closure monitoring requirements of the order DOE O 435.1, manual DOE M 435.1-1, Title 40 Code of Federal Regulations (CFR) Part 191, 40 CFR 265, Nevada Administrative Code (NAC) 444.743, and Resource Conservation and Recovery Act (RCRA) requirements as incorporated into NAC 444.8632. The Area 5 RWMS accepts primarily packaged low-level waste (LLW), low-level mixed waste (LLMW), and asbestiform low-level waste (ALLW) for disposal in excavated disposal cells

  6. Closure Plan for the Area 5 Radioactive Waste Management Site at the Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Management

    2008-09-01

    The Area 5 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec), for the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the preliminary closure plan for the Area 5 RWMS at the NTS that was presented in the Integrated Closure and Monitoring Plan (DOE, 2005a). The major updates to the plan include a new closure schedule, updated closure inventory, updated site and facility characterization data, the Title II engineering cover design, and the closure process for the 92-Acre Area of the RWMS. The format and content of this site-specific plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). This interim closure plan meets closure and post-closure monitoring requirements of the order DOE O 435.1, manual DOE M 435.1-1, Title 40 Code of Federal Regulations (CFR) Part 191, 40 CFR 265, Nevada Administrative Code (NAC) 444.743, and Resource Conservation and Recovery Act (RCRA) requirements as incorporated into NAC 444.8632. The Area 5 RWMS accepts primarily packaged low-level waste (LLW), low-level mixed waste (LLMW), and asbestiform low-level waste (ALLW) for disposal in excavated disposal cells.

  7. Corrective Action Plan for CAU No. 95: Area 15 EPA Farm Laboratory Building, Decontamination and Demolition Closure Activities - Nevada Test Site. Rev. 0

    International Nuclear Information System (INIS)

    Olson, A.L.; Nacht, S.J.

    1997-11-01

    This Corrective Action Plan (CAP) provides the selected corrective action alternative and proposes the closure implementation methodology for the Environmental Protection Agency (EPA) Farm Laboratory Building 15-06 located in Area 15 of the Nevada Test Site (NTS), Nye County, Nevada. The facility is part of the Environmental Restoration Project managed by the U.S. Department of Energy/Nevada Operations Office (DOE/NV) under the Decontamination and Decommissioning (D ampersand D) Subproject which serves to manage and dispose of surplus facilities at the NTS in a manner that will protect personnel, the public, and the environment. It is identified as Corrective Action Unit (CAU) 95 in Appendix III of the Federal Facilities Agreement and Consent Order (FFACO). In July 1997, the DOE/NV verbally requested approval from the Nevada Division of Environmental Protection (NDEP) for the closure schedule to be accelerated. Currently, field activities are anticipated to be completed by September 30, 1997. In order to meet this new schedule NDEP has agreed to review this document as expeditiously as possible. Comments will be addressed in the Closure Report after field activities have been completed, unless significant issues require resolution during closure activities

  8. Corrective Action Plan for CAU No. 95: Area 15 EPA Farm Laboratory Building, Decontamination and Demolition Closure Activities - Nevada Test Site. Rev. 0

    Energy Technology Data Exchange (ETDEWEB)

    Olson, A.L.; Nacht, S.J.

    1997-11-01

    This Corrective Action Plan (CAP) provides the selected corrective action alternative and proposes the closure implementation methodology for the Environmental Protection Agency (EPA) Farm Laboratory Building 15-06 located in Area 15 of the Nevada Test Site (NTS), Nye County, Nevada. The facility is part of the Environmental Restoration Project managed by the U.S. Department of Energy/Nevada Operations Office (DOE/NV) under the Decontamination and Decommissioning (D&D) Subproject which serves to manage and dispose of surplus facilities at the NTS in a manner that will protect personnel, the public, and the environment. It is identified as Corrective Action Unit (CAU) 95 in Appendix III of the Federal Facilities Agreement and Consent Order (FFACO). In July 1997, the DOE/NV verbally requested approval from the Nevada Division of Environmental Protection (NDEP) for the closure schedule to be accelerated. Currently, field activities are anticipated to be completed by September 30, 1997. In order to meet this new schedule NDEP has agreed to review this document as expeditiously as possible. Comments will be addressed in the Closure Report after field activities have been completed, unless significant issues require resolution during closure activities.

  9. Closure Report for Corrective Action Unit 537: Waste Sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 537 is identified in the ''Federal Facility Agreement and Consent Order'' (FFACO) of 1996 as Waste Sites. CAU 537 is located in Areas 3 and 19 of the Nevada Test Site, approximately 65 miles northwest of Las Vegas, Nevada, and consists of the following two Corrective Action Sites (CASs): CAS 03-23-06, Bucket; Yellow Tagged Bags; and CAS 19-19-01, Trash Pit. CAU 537 closure activities were conducted in April 2007 according to the FFACO and Revision 3 of the Sectored Clean-up Work Plan for Housekeeping Category Waste Sites (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2003). At CAS 03-23-06, closure activities included removal and disposal of a 15-foot (ft) by 15-ft by 8-ft tall wooden shed containing wood and metal debris and a 5-gallon plastic bucket containing deteriorated plastic bags with yellow radioactive contamination tape. The debris was transported to the Area 9 U10c Landfill for disposal after being screened for radiological contamination according to the ''NV/YMP Radiological Control Manual'' (NNSA/NSO, 2004). At CAS 19-19-01, closure activities included segregation, removal, and disposal of non-friable, non-regulated asbestos-containing material (ACM) and construction debris. The ACM was determined to be non-friable by waste characterization samples collected prior to closure activities. The ACM was removed and double-bagged by licensed, trained asbestos workers and transported to the Area 9 U10c Landfill for disposal. Construction debris was transported in end-dump trucks to the Area 9 U10c Landfill for disposal. Closure activities generated sanitary waste/construction debris and ACM. Waste generated during closure activities was appropriately managed and disposed. Waste characterization sample results are included as Appendix A of this report, and waste disposition documentation is included as Appendix B of this report. Copies of the Sectored Housekeeping Site Closure

  10. Guidance for closure of existing DOE LLW disposal sites

    International Nuclear Information System (INIS)

    Blanchfield, L.

    1987-01-01

    During FY 1986, a closure guidance document was developed. The purpose of this document is to provide guidance in support of DOE Order 5820.2 to site operating contractors for the stabilization and closure of existing low-level waste (LLW) shallow land disposal sites at US Department of Energy (DOE) facilities. Guidance is provided to aid operators in placing existing LLW sites in a closed conditions, i.e., a condition in which a nonoperational site meets postclosure performance requirements and can be shown, within a high degree of confidence, to perform as anticipated in the future, under the most cost-effective maintenance approach. Guidance is based on the philosophy that closure should be planned and performed using a systems approach. Plans for FY 1987 call for revision of the document to incorporate more information on closure of LLW sites also containing radioactive mixed waste and/or transuranic waste. 4 references, 3 figures, 2 tables

  11. Evaluation of a novel trocar-site closure and comparison with a standard Carter-Thomason closure device.

    Science.gov (United States)

    del Junco, Michael; Okhunov, Zhamshid; Juncal, Samuel; Yoon, Renai; Landman, Jaime

    2014-07-01

    The aim of this study was to evaluate and compare a novel trocars-site closure device, the WECK EFx™ Endo Fascial Closure System (EFx) with the Carter-Thomason CloseSure System® (CT) for the closure of laparoscopic trocar site defects created by a 12-mm dilating trocar. We created standardized laparoscopic trocars-site abdominal wall defects in cadaver models using a standard 12-mm laparoscopic dilating trocar. Trocar defects were closed in a randomized fashion using one of the two closure systems. We recorded time and number of attempts needed for complete defect closure. In addition, we recorded the ability to maintain pneumoperitoneum, endoscopic visualization, safety, security, and facility based on the surgeon's subjective evaluations. We compared outcomes for the EFx and CT closure systems. We created 72 standardized laparoscopic trocars-site abdominal wall defects. The mean time needed for complete defect closure was 98.53 seconds (±28.9) for the EFx compared with 133.61 seconds (±54.61) for the CT (Psafety were 2.92 for EFx vs 2.19 for CT (Pvs 1.83 for EFx and CT, respectively (Pvs 2.33 for CT (P=0.022). No significant difference was observed between the EFx and the CT systems for endoscopic visualization (2.28 vs 2.50, P=0.080). In this in vitro cadaver trial, the EFx was superior in terms of time needed to complete defect closure, safety, and facility. CT was superior in terms of maintenance of pneumoperitoneum. Both systems were equal in the number of attempts needed to complete the defect closure and endoscopic visualization.

  12. Closure report for CAU No. 450: Historical UST release sites, Nevada Test Site. Volume 1

    International Nuclear Information System (INIS)

    1997-09-01

    This report addresses the closure of 11 historical underground storage tank (UST) release sites within various areas of the Nevada Test Site (NTS). The closure of each hydrocarbon release has not been documented, therefore, this report addresses the remedial activities completed for each release site. The hydrocarbon release associated with each tank site within CAU 450 was remediated by excavating the impacted soil. Clean closure of the release was verified through soil sample analysis by an off-site laboratory. All release closure activities were completed following standard environmental and regulatory guidelines. Based upon site observations during the remedial activities and the soil sample analytical results, which indicated that soil concentrations were below the Nevada Administrative code (NAC) Action Level of 100 mg/kg, it is anticipated that each of the release CASs be closed without further action

  13. Supporting Fernald Site Closure with Integrated Health and Safety Plans as Documented Safety Analyses

    International Nuclear Information System (INIS)

    Kohler, S.; Brown, T.; Fisk, P.; Krach, F.; Klein, B.

    2004-01-01

    At the Fernald Closure Project (FCP) near Cincinnati, Ohio, environmental restoration activities are supported by Documented Safety Analyses (DSAs) that combine the required project-specific Health and Safety Plans, Safety Basis Requirements (SBRs), and Process Requirements (PRs) into single Integrated Health and Safety Plans (I-HASPs). These integrated DSAs employ Integrated Safety Management methodology in support of simplified restoration and remediation activities that, so far, have resulted in the decontamination and demolition (D and D) of over 200 structures, including eight major nuclear production plants. There is one of twelve nuclear facilities still remaining (Silos containing uranium ore residues) with its own safety basis documentation. This paper presents the status of the FCP's safety basis documentation program, illustrating that all of the former nuclear facilities and activities have now replaced. Basis of Interim Operations (BIOs) with I-HASPs as their safety basis during the closure process

  14. Development of an arid site closure plan

    International Nuclear Information System (INIS)

    Nyhan, J.W.; Barnes, F.J.

    1987-01-01

    This document describes the development of a prototype plan for the effective closure and stabilization of an arid low-level waste disposal site. This plan will provide demonstrated closure techniques for a trench in a disposal site at Los Alamos. The accuracy of modeling soil water storage by two hydrologic models, CREAMS and HELP, was tested by comparing simulation results with field measurements of soil moisture in eight experimental landfill cover systems having a range of well-defined soil profiles and vegetative covers. Regression analysis showed that CREAMS generally represented soil moisture more accurately than HELP simulations. Precautions for determining parameter values for model input and for interpreting simulation results are discussed. A specific example is presented showing how the field-validated hydrologic models can be used to develop a final prototype closure plan. 15 refs., 13 figs., 3 tabs

  15. A Sandia National Laboratories decontamination and demolition success story

    International Nuclear Information System (INIS)

    Miller, D.R.; Barber, D.S.; Lipka, G.

    1994-01-01

    Sandia National Laboratories/New Mexico (SNL/NM) has established a formal facility assessment, decontamination and demolition oversight process with the goal of ensuring that excess or contaminated facilities are managed in a cost-effective manner that is protective of human health and the environment. The decontamination and demolition process is designed so that all disciplines are consulted and have input from the initiation of a project. The committee consists of all essential Environmental, Safety and Health (ES and H) and Facilities disciplines. The interdisciplinary-team approach has provided a mechanism that verifies adequate building and site assessment activities are conducted. This approach ensures that wastes generated during decontamination and demolition activities are handled and disposed according to Department of Energy (DOE), Federal, state, and local requirements. Because of the comprehensive nature of the SNL decontamination and demolition process, the strategy can be followed for demolition, renovation and new construction projects, regardless of funding source. An overview of the SNL/NM decontamination and demolition process is presented through a case study which demonstrates the practical importance of the formal process

  16. Construction and demolition waste indicators.

    Science.gov (United States)

    Mália, Miguel; de Brito, Jorge; Pinheiro, Manuel Duarte; Bravo, Miguel

    2013-03-01

    The construction industry is one of the biggest and most active sectors of the European Union (EU), consuming more raw materials and energy than any other economic activity. Furthermore, construction waste is the commonest waste produced in the EU. Current EU legislation sets out to implement construction and demolition waste (CDW) prevention and recycling measures. However it lacks tools to accelerate the development of a sector as bound by tradition as the building industry. The main objective of the present study was to determine indicators to estimate the amount of CDW generated on site both globally and by waste stream. CDW generation was estimated for six specific sectors: new residential construction, new non-residential construction, residential demolition, non-residential demolition, residential refurbishment, and non-residential refurbishment. The data needed to develop the indicators was collected through an exhaustive survey of previous international studies. The indicators determined suggest that the average composition of waste generated on site is mostly concrete and ceramic materials. Specifically for new residential and new non-residential construction the production of concrete waste in buildings with a reinforced concrete structure lies between 17.8 and 32.9 kg m(-2) and between 18.3 and 40.1 kg m(-2), respectively. For the residential and non-residential demolition sectors the production of this waste stream in buildings with a reinforced concrete structure varies from 492 to 840 kg m(-2) and from 401 to 768 kg/m(-2), respectively. For the residential and non-residential refurbishment sectors the production of concrete waste in buildings lies between 18.9 and 45.9 kg/m(-2) and between 18.9 and 191.2 kg/m(-2), respectively.

  17. Green Residential Demolitions: Case Study of Vacant Land Reuse in Storm Water Management in Cleveland

    Science.gov (United States)

    The demolition process impacts how vacant land might be reused for storm water management. For five residential demolition sites (Cleveland, Ohio), an enhanced green demolition process was observed in 2012, and soil physical and hydrologic characteristics were measured predemolit...

  18. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    International Nuclear Information System (INIS)

    JOHNSTON GA

    2008-01-01

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D and D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D and D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D and D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and Liability Act of 1980

  19. Characterizing the environmental impact of metals in construction and demolition waste.

    Science.gov (United States)

    Yu, Danfeng; Duan, Huabo; Song, Qingbin; Li, Xiaoyue; Zhang, Hao; Zhang, Hui; Liu, Yicheng; Shen, Weijun; Wang, Jinben

    2018-05-01

    Large quantities of construction and demolition (C&D) waste are generated in China every year, but their potential environmental impacts on the surrounding areas are rarely assessed. This study focuses on metals contained in C&D waste, characterizing the metal concentrations and their related environmental risks. C&D waste samples were collected in Shenzhen City, China, from building demolition sites, renovation areas undergoing refurbishment, landfill sites, and recycling companies (all located in Shenzhen city) that produce recycled aggregate, in order to identify pollution levels of the metals As, Cd, Cr, Cu, Pb, Ni, and Zn. The results showed that (1) the metal concentrations in most demolition and renovation waste samples were below the soil environmental quality standard for agricultural purposes (SQ-Agr.) in China; (2) Cd, Cu, and Zn led to relatively higher environmental risks than other metals, especially for Zn (DM5 tile sample, 360 mg/kg; R4 tile sample, 281 mg/kg); (3) non-inert C&D waste such as wall insulation and foamed plastic had high concentrations of As and Cd, so that these materials required special attention for sound waste management; and (4) C&D waste collected from landfill sites had higher concentrations of Cd and Cu than did waste collected from demolition and refurbishment sites.

  20. Closure Report for Corrective Action Unit 536: Area 3 Release Site, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 536 is located in Area 3 of the Nevada Test Site. CAU 536 is listed in the Federal Facility Agreement and Consent Order of 1996 as Area 3 Release Site, and comprises a single Corrective Action Site (CAS): (sm b ullet) CAS 03-44-02, Steam Jenny Discharge The Nevada Division of Environmental Protection (NDEP)-approved corrective action alternative for CAS 03-44-02 is clean closure. Closure activities included removing and disposing of total petroleum hydrocarbon (TPH)- and polyaromatic hydrocarbon (PAH)-impacted soil, soil impacted with plutonium (Pu)-239, and concrete pad debris. CAU 536 was closed in accordance with the NDEP-approved CAU 536 Corrective Action Plan (CAP), with minor deviations as approved by NDEP. The closure activities specified in the CAP were based on the recommendations presented in the CAU 536 Corrective Action Decision Document (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2004). This Closure Report documents CAU 536 closure activities. During closure activities, approximately 1,000 cubic yards (yd3) of hydrocarbon waste in the form of TPH- and PAH-impacted soil and debris, approximately 8 yd3 of Pu-239-impacted soil, and approximately 100 yd3 of concrete debris were generated, managed, and disposed of appropriately. Additionally, a previously uncharacterized, buried drum was excavated, removed, and disposed of as hydrocarbon waste as a best management practice. Waste minimization techniques, such as the utilization of laboratory analysis to characterize and classify waste streams, were employed during the performance of closure

  1. Cost effectiveness of risk-based closures at UST sites

    International Nuclear Information System (INIS)

    Scruton, K.M.; Baker, J.N.

    1995-01-01

    Risk-based closures have been achieved at Underground Storage Tank (UST) sites throughout the country for a major transportation company. The risk-based closures were cost-effective because a streamlined risk-based approach was used instead of the generic baseline risk assessment approach. USEPA has recently provided guidance encouraging the use of risk-based methodology for achieving closure at UST sites. The risk-based approach used in achieving the site closures involved an identification of potential human and ecological receptors and exposure pathways, and a comparison of maximum onsite chemical concentrations to applicable or relevant and appropriate requirements (ARARs). The ARARs used in the evaluation included Federal and/or State Maximum Contaminant Levels (MCLs) for groundwater and risk-based screening levels for soils. If the maximum concentrations were above the screening levels, a baseline risk assessment was recommended. In several instances, however, the risk-based approach resulted in a regulatory agency acceptance of a ''no further action'' alternative at UST sites which did not pose a significant threat to human health and the environment. The cost of the streamlined risk-based approach is approximately $3,500, while a baseline risk assessment for the same UST site could cost up to $10,000 or more. The use of the streamlined risk-based approach has proven to be successful for achieving a ''no further action'' outcome for the client at a reasonable cost

  2. CLOSING IN ON CLOSURE PERSPECTIVES FROM HANFORD and FERNALD AN UPDATE

    International Nuclear Information System (INIS)

    CONNELL, J.D.

    2004-01-01

    In World War II, the arms dramatically changed from machine guns and incendiary bombs to nuclear weapons. Hanford and Fernald, two government-run sites, were part of the infrastructure established for producing the fissile material for making these weapons, as well as building a nuclear arsenal to deter future aggression by other nations. This paper compares and contrasts, from a communications point of view, these two Department of Energy (DOE) closure sites, each with Fluor as a prime contractor. The major differences between the two sites--Hanford in Washington state and Fernald in Ohio--includes the following: size of the site and the workforce, timing of closure, definition of end state, DOE oversight, proximity to population centers, readiness of local population for closure, and dependence of the local economy on the site's budget. All of these elements affect how the sites' communication professionals provide information even though the objectives are the same: build public acceptance and support for DOE's mission to accelerate cleanup, interface with stakeholders to help ensure that issues are addressed and goals are met, help workers literally work themselves out of jobs--faster, and prepare the ''host'' communities to deal with the void left when the sites are closed and the government contractors are gone. The 12-months between January 04 and January 05 have seen dramatic transformations at both sites, as Fernald is now just about a year away from closure and FLuor's work at Hanford has made the transition from operations to deactivation and demolition. While Fernald continues to clean out silos of waste and ship it off site, Hanford is dealing with recent state legislation that has the potential to significantly impact the progress of cleanup. These changes have even further accentuated the differences in the content, distribution, and impact of communications

  3. Closure report for housekeeping category, Corrective Action Unit 348, Nevada Test Site

    International Nuclear Information System (INIS)

    1998-01-01

    This Closure Report summarizes the corrective actions which were completed at twelve Corrective Action Sites within Corrective Action Unit 348 at the Nevada Test Site. Current site descriptions, observations and identification of wastes removed are included on FFACO Corrective Action Site housekeeping closure verification forms

  4. Closure report for housekeeping category, Corrective Action Unit 347, Nevada Test Site

    International Nuclear Information System (INIS)

    1998-01-01

    This Closure Report summarizes the corrective actions which were completed at the Corrective Action Sites within Corrective Action Unit 347 at the Nevada Test Site. Current site descriptions, observations and identification of wastes removed are included on FFACO Corrective Action Site housekeeping closure verification forms

  5. Accelerating cleanup. Paths to closure Hanford Site

    International Nuclear Information System (INIS)

    Edwards, C.

    1998-01-01

    This document was previously referred to as the Draft 2006 Plan. As part of the DOE's national strategy, the Richland Operations Office's Paths to Closure summarizes an integrated path forward for environmental cleanup at the Hanford Site. The Hanford Site underwent a concerted effort between 1994 and 1996 to accelerate the cleanup of the Site. These efforts are reflected in the current Site Baseline. This document describes the current Site Baseline and suggests strategies for further improvements in scope, schedule and cost. The Environmental Management program decided to change the name of the draft strategy and the document describing it in response to a series of stakeholder concerns, including the practicality of achieving widespread cleanup by 2006. Also, EM was concerned that calling the document a plan could be misconstrued to be a proposal by DOE or a decision-making document. The change in name, however, does not diminish the 2006 vision. To that end, Paths to Closure retains a focus on 2006, which serves as a point in time around which objectives and goals are established

  6. Weldon Spring Site Remedial Action Project approach to building dismantlement and demolition

    Energy Technology Data Exchange (ETDEWEB)

    Spittler, F.J.

    1996-01-01

    When remediation began at the Weldon Spring Site Remedial Action Project (WSSRAP), there were 41 buildings on site. Twenty-nine of these buildings were ancillary structures and were not used for processing radioactive material. Most of these have been torn down. The remaining 12 buildings were used for uranium and thorium processing or were major support structures, such as the laboratory. Two of the buildings were major processing operations occurred were successfully demolished in February of this year. Demolition of all structures will be complete in September of this year. To give an understanding of the magnitude of the work, the following is a description of the physical characteristics of the green salt building. This building was used to convert brown oxide (UO3) to green salt (UF4), which is the last intermediate step in purifying the mostly yellow cake feed material into uranium metal.

  7. Weldon Spring Site Remedial Action Project approach to building dismantlement and demolition

    International Nuclear Information System (INIS)

    Spittler, F.J.

    1996-01-01

    When remediation began at the Weldon Spring Site Remedial Action Project (WSSRAP), there were 41 buildings on site. Twenty-nine of these buildings were ancillary structures and were not used for processing radioactive material. Most of these have been torn down. The remaining 12 buildings were used for uranium and thorium processing or were major support structures, such as the laboratory. Two of the buildings were major processing operations occurred were successfully demolished in February of this year. Demolition of all structures will be complete in September of this year. To give an understanding of the magnitude of the work, the following is a description of the physical characteristics of the green salt building. This building was used to convert brown oxide (UO3) to green salt (UF4), which is the last intermediate step in purifying the mostly yellow cake feed material into uranium metal

  8. Construction and Demolition Waste Characteristics in Tanzania ...

    African Journals Online (AJOL)

    The construction industry generates a lot of construction and demolition (C&D) waste which puts some challenges to its management. For example, currently, in many towns in Tanzania, there are no landfill sites for solid waste disposal; and as a consequence open air dumping sites are used. Dumping C&D waste puts ...

  9. Infiltration experiment for closure cap evaluation at the Savannah River Site

    International Nuclear Information System (INIS)

    Roddy, N.S.; Cook, J.R.

    1990-01-01

    This document discusses several large waste disposal facilities at the Savannah River Site which are being closed. These facilities include two seepage basins and the low-level waste disposal facility. The key element of the closures is the construction of a cap system to limit the infiltration of water which might reach the disposed waste. Cap designs have been modeled using the Hydrologic Evaluation of Landfill Performance (HELP) computer code. This code was developed by the US Army Corps of Engineers for the Environmental Protection Agency to model the effects of various cap and liner designs on the water balance at landfills. A field experiment has been set up which will allow the results of the HELP Code to be verified at the Savannah River Site (SRS) by measuring the actual water balance created by closure cap configurations which will be used in waste site closures at SRS. Two of the caps will be similar to those used for the planned closure activities. Each one has a specific closure arrangement. Once operational, the experiment will be evaluated for a five-year period

  10. Closure Report for Corrective Action Unit 547: Miscellaneous Contaminated Waste Sites, Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2012-07-17

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 547, Miscellaneous Contaminated Waste Sites, and provides documentation supporting the completed corrective actions and confirmation that closure objectives for CAU 547 were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; the U.S. Department of Energy (DOE), Environmental Management; the U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996 as amended). CAU 547 consists of the following three Corrective Action Sites (CASs), located in Areas 2, 3, and 9 of the Nevada National Security Site: (1) CAS 02-37-02, Gas Sampling Assembly; (2) CAS 03-99-19, Gas Sampling Assembly; AND (3) CAS 09-99-06, Gas Sampling Assembly Closure activities began in August 2011 and were completed in June 2012. Activities were conducted according to the Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for CAU 547 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2011). The recommended corrective action for the three CASs in CAU 547 was closure in place with administrative controls. The following closure activities were performed: (1) Open holes were filled with concrete; (2) Steel casings were placed over vertical expansion joints and filled with cement; (3) Engineered soil covers were constructed over piping and exposed sections of the gas sampling system components; (4) Fencing, monuments, Jersey barriers, radiological postings, and use restriction (UR) warning signs were installed around the perimeters of the sites; (5) Housekeeping debris was picked up from around the sites and disposed; and (6) Radiological surveys were performed to confirm final radiological postings. UR documentation is included in Appendix D. The post-closure plan was presented in detail in the CADD/CAP for CAU 547 and is included as

  11. Closure Report for Corrective Action Unit 547: Miscellaneous Contaminated Waste Sites, Nevada National Security Site, Nevada

    International Nuclear Information System (INIS)

    2012-01-01

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 547, Miscellaneous Contaminated Waste Sites, and provides documentation supporting the completed corrective actions and confirmation that closure objectives for CAU 547 were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; the U.S. Department of Energy (DOE), Environmental Management; the U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996 as amended). CAU 547 consists of the following three Corrective Action Sites (CASs), located in Areas 2, 3, and 9 of the Nevada National Security Site: (1) CAS 02-37-02, Gas Sampling Assembly; (2) CAS 03-99-19, Gas Sampling Assembly; AND (3) CAS 09-99-06, Gas Sampling Assembly Closure activities began in August 2011 and were completed in June 2012. Activities were conducted according to the Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for CAU 547 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2011). The recommended corrective action for the three CASs in CAU 547 was closure in place with administrative controls. The following closure activities were performed: (1) Open holes were filled with concrete; (2) Steel casings were placed over vertical expansion joints and filled with cement; (3) Engineered soil covers were constructed over piping and exposed sections of the gas sampling system components; (4) Fencing, monuments, Jersey barriers, radiological postings, and use restriction (UR) warning signs were installed around the perimeters of the sites; (5) Housekeeping debris was picked up from around the sites and disposed; and (6) Radiological surveys were performed to confirm final radiological postings. UR documentation is included in Appendix D. The post-closure plan was presented in detail in the CADD/CAP for CAU 547 and is included as

  12. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    Energy Technology Data Exchange (ETDEWEB)

    JOHNSTON GA

    2008-01-15

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D&D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D&D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D&D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and

  13. Quality assurance and demolition: 2006 symposium

    International Nuclear Information System (INIS)

    Thierfeldt, S.

    2006-01-01

    The '2006 Symposium: Quality Assurance and Demolition' jointly organized by compra GmbH and Brenk Systemplanung GmbH this year again focused on quality assurance and the demolition of nuclear facilities as its main topics. The papers presented ranged from issues of clearance and disposal to demolition technologies and status reports about specific demolition projects. The sixteen presentations at the '2006 Symposium: Quality Assurance and Demolition' offered an interesting and very topical cross section of decommissioning and demolition of nuclear facilities in Germany. In 2007, the conference about similar main topics will again be held at the Schloss Bensberg Grand Hotel. (orig.)

  14. Incorporating Sustainability into Site Closure - A Field Example

    Science.gov (United States)

    Austrins, L. M.; West, J.

    2013-12-01

    Long term management of former chemical production facilities can be a costly and time consuming element of site closure, however, implementation of creative measures to introduce sustainability and reduce the need for onsite presence can be successfully incorporated into the site closure process. A case study demonstrating this involves a facility located in Sarnia, Ontario, which was an active multi chemical production facility from the 1940s, until it was decommissioned and sold between 2005 and 2010. The facility consisted of 322 acres of production areas. Several elements which allowed for reduced onsite presence and lower management costs were incorporated into the site decommissioning plan, including; phased remediation planning, and selection of sustainable components as part of remediation, surface water management, and groundwater management. The sustainability and management modifications were successfully negotiated and approved by the local regulatory agency. Due to the size and complexity of the site, a holistic approach for the facility was needed and included the development of a comprehensive decision matrix. Each remediation alternative incorporated sustainable practices. Ex-situ remediation consisted of excavation of contaminated subsurface medium and consolidation at a 4.7 acre onsite soil treatment area designed specifically for the site closure process. In-situ remediation consisted of injection of amendment into the native soils using hydraulic fracture and injection. When the plant was an active operating facility, groundwater management required active pumping and groundwater treatment through a series of carbon treatment units. Active pumping has been replaced by passive hydraulic control through the use of tree plantations.

  15. Closure Plan for the Area 3 Radioactive Waste Management Site at the Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Management

    2007-09-01

    The Area 3 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec) for the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the interim closure plan for the Area 3 RWMS, which was presented in the Integrated Closure and Monitoring Plan (ICMP) (DOE, 2005). The format and content of this plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). The major updates to the plan include a new closure date, updated closure inventory, the new institutional control policy, and the Title II engineering cover design. The plan identifies the assumptions and regulatory requirements, describes the disposal sites and the physical environment in which they are located, presents the design of the closure cover, and defines the approach and schedule for both closing and monitoring the site. The Area 3 RWMS accepts low-level waste (LLW) from across the DOE Complex in compliance with the NTS Waste Acceptance Criteria (NNSA/NSO, 2006). The Area 3 RWMS accepts both packaged and unpackaged unclassified bulk LLW for disposal in subsidence craters that resulted from deep underground tests of nuclear devices in the early 1960s. The Area 3 RWMS covers 48 hectares (119 acres) and comprises seven subsidence craters--U-3ax, U-3bl, U-3ah, U-3at, U-3bh, U-3az, and U-3bg. The area between craters U-3ax and U-3bl was excavated to form one large disposal unit (U-3ax/bl); the area between craters U-3ah and U-3at was also excavated to form another large disposal unit (U-3ah/at). Waste unit U-3ax/bl is closed; waste units U-3ah/at and U-3bh are active; and the remaining craters, although currently undeveloped, are available for disposal of waste if required. This plan specifically addresses the closure of the U-3ah/at and the U-3bh LLW units. A final closure

  16. Closure Plan for the Area 3 Radioactive Waste Management Site at the Nevada Test Site

    International Nuclear Information System (INIS)

    NSTec Environmental Management

    2007-01-01

    The Area 3 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec) for the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the interim closure plan for the Area 3 RWMS, which was presented in the Integrated Closure and Monitoring Plan (ICMP) (DOE, 2005). The format and content of this plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). The major updates to the plan include a new closure date, updated closure inventory, the new institutional control policy, and the Title II engineering cover design. The plan identifies the assumptions and regulatory requirements, describes the disposal sites and the physical environment in which they are located, presents the design of the closure cover, and defines the approach and schedule for both closing and monitoring the site. The Area 3 RWMS accepts low-level waste (LLW) from across the DOE Complex in compliance with the NTS Waste Acceptance Criteria (NNSA/NSO, 2006). The Area 3 RWMS accepts both packaged and unpackaged unclassified bulk LLW for disposal in subsidence craters that resulted from deep underground tests of nuclear devices in the early 1960s. The Area 3 RWMS covers 48 hectares (119 acres) and comprises seven subsidence craters--U-3ax, U-3bl, U-3ah, U-3at, U-3bh, U-3az, and U-3bg. The area between craters U-3ax and U-3bl was excavated to form one large disposal unit (U-3ax/bl); the area between craters U-3ah and U-3at was also excavated to form another large disposal unit (U-3ah/at). Waste unit U-3ax/bl is closed; waste units U-3ah/at and U-3bh are active; and the remaining craters, although currently undeveloped, are available for disposal of waste if required. This plan specifically addresses the closure of the U-3ah/at and the U-3bh LLW units. A final closure

  17. PROJECT EXPERIENCE REPORT DEMOLITION OF HANFORDS 233-S PLUTONIUM CONCENTRATION FACILITY

    International Nuclear Information System (INIS)

    BERLIN, G.T.; ORGILL, T.K.

    2004-01-01

    This report provides a summary of the preparation, operations, innovative work practices, and lessons learned associated with demolition of the 2334 Plutonium Concentration Facility. This project represented the first open-air demolition of a highly-contaminated plutonium facility at the Hanford Site. This project may also represent the first plutonium facility in the US. Department of Energy (DOE) complex to have been demolished without first decontaminating surfaces to near ''free release'' standards. Demolition of plutonium contaminated structures, if not properly managed, can subject cleanup personnel and the environment to significant risk. However, with proper sequencing and innovative use of commercially available equipment, materials, and services, this project demonstrated that a plutonium processing facility can be demolished while avoiding the need to perform extensive decontamination or to construct large enclosures. This project utilized an excavator with concrete shears, diamond circular saws, water misting and fogging equipment, commercially available fixatives and dust suppressants, conventional mobile crane and rigging services, and near real-time modeling of meteorological and radiological conditions. Following a significant amount of preparation, actual demolition of the 233-S Facility began in October 2003 and was completed in late April 2004. The knowledge and experience gained on this project are important to the Hanford Site as additional plutonium processing facilities are scheduled for demolition in the near future. Other sites throughout the DOE Complex may also be faced with similar challenges. Numerous innovations and effective work practices were implemented on this project. Accordingly, a series of ''Lessons Learned and Innovative Practices Fact Sheets'' were developed and are included as an appendix to this report. This collection of fact sheets is not intended to capture every innovative work practice and lesson learned, but rather

  18. PROJECT EXPERIENCE REPORT DEMOLITION OF HANFORDS 233-S PLUTONIUM CONCENTRATION FACILITY

    International Nuclear Information System (INIS)

    BERLIN, G.T.

    2004-01-01

    This report provides a summary of the preparation, operations, innovative work practices, and lessons learned associated with demolition of the 2334 Plutonium Concentration Facility. This project represented the first open-air demolition of a highly-contaminated plutonium facility at the Hanford Site. This project may also represent the first plutonium facility in the US. Department of Energy (DOE) complex to have been demolished without first decontaminating surfaces to near ''free release'' standards. Demolition of plutonium contaminated structures, if not properly managed, can subject cleanup personnel and the environment to significant risk. However, with proper sequencing and innovative use of commercially available equipment, materials, and services, this project demonstrated that a plutonium processing facility can be demolished while avoiding the need to perform extensive decontamination or to construct large enclosures. This project utilized an excavator with concrete shears, diamond circular saws, water misting and fogging equipment, commercially available fixatives and dust suppressants, conventional mobile crane and rigging services, and near real-time modeling of meteorological and radiological conditions. Following a significant amount of preparation, actual demolition of the 2333 Facility began in October 2003 and was completed in late April 2004. The knowledge and experience gained on this project are important to the Hanford Site as additional plutonium processing facilities are scheduled for demolition in the near future. Other sites throughout the DOE Complex may also be faced with similar challenges. Numerous innovations and effective work practices were implemented on this project. Accordingly, a series of ''Lessons Learned and Innovative Practices Fact Sheets'' were developed and are included as an appendix to this report. This collection of fact sheets is not intended to capture every innovative work practice and lesson learned, but rather to

  19. The Effects of Data Collection Method and Monitoring of Workers’ Behavior on the Generation of Demolition Waste

    Directory of Open Access Journals (Sweden)

    Gi-Wook Cha

    2017-10-01

    Full Text Available The roles of both the data collection method (including proper classification and the behavior of workers on the generation of demolition waste (DW are important. By analyzing the effect of the data collection method used to estimate DW, and by investigating how workers’ behavior can affect the total amount of DW generated during an actual demolition process, it was possible to identify strategies that could improve the prediction of DW. Therefore, this study surveyed demolition waste generation rates (DWGRs for different types of building by conducting on-site surveys immediately before demolition in order to collect adequate and reliable data. In addition, the effects of DW management strategies and of monitoring the behavior of workers on the actual generation of DW were analyzed. The results showed that when monitoring was implemented, the estimates of DW obtained from the DWGRs that were surveyed immediately before demolition and the actual quantities of DW reported by the demolition contractors had an error rate of 0.63% when the results were compared. Therefore, this study has shown that the proper data collection method (i.e., data were collected immediately before demolition applied in this paper and monitoring on the demolition site have a significant impact on waste generation.

  20. Drilling-and-blasting method of demolition

    Directory of Open Access Journals (Sweden)

    Sinitsyn Denis

    2018-01-01

    Full Text Available This article analyzes the experience and gives the examples of dismantling and demolition of the construction structures of the buildings and facilities using the drilling-and-blasting method. The drilling-and-blasting method is widely used in construction and reconstruction. The demolition means may be classified according to impact on a material of structures to be demolished and to forces application, where, by virtue of an impact energy type, we choose the blasting method. This method is used during the complete demolition or fragmentation of concrete, reinforced concrete, masonry structures, of old buildings and facilities demolition to their base or in the intended direction. Blasting method may be used as well during the steel and reinforced concrete structures demolition to the smaller easy-to-move parts. Reviewed are the organizational-process activities, which are performed during the various structures dismantling. Given are the areas of application for the various methods of structures demolition. Given is the example of demolition of “Sevemaya” boiler house brick chimney at the territory of Murmansk DSK using the blast in confined spaces of the operating company. Subject of research: methods of construction structures demolition in alarm situations and acts of God. Objects: determination of the most efficient demolition methods in the present conditions of construction operations development. Materials and methods: the developed activities on the construction structures dismantling are given. Results: the most efficient methods and ways of construction structures demolition are defined. Conclusions: it is required for improvement of methods and ways of the structures drilling-and-blasting demolition.

  1. Closure Report for Corrective Action Unit 107: Low Impact Soil Sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2009-01-01

    Corrective Action Unit (CAU) 107 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Low Impact Soil Sites' and consists of the following 15 Corrective Action Sites (CASs), located in Areas 1, 2, 3, 4, 5, 9, 10, and 18 of the Nevada Test Site: CAS 01-23-02, Atmospheric Test Site - High Alt; CAS 02-23-02, Contaminated Areas (2); CAS 02-23-03, Contaminated Berm; CAS 02-23-10, Gourd-Amber Contamination Area; CAS 02-23-11, Sappho Contamination Area; CAS 02-23-12, Scuttle Contamination Area; CAS 03-23-24, Seaweed B Contamination Area; CAS 03-23-27, Adze Contamination Area; CAS 03-23-28, Manzanas Contamination Area; CAS 03-23-29, Truchas-Chamisal Contamination Area; CAS 04-23-02, Atmospheric Test Site T4-a; CAS 05-23-06, Atmospheric Test Site; CAS 09-23-06, Mound of Contaminated Soil; CAS 10-23-04, Atmospheric Test Site M-10; and CAS 18-23-02, U-18d Crater (Sulky). Closure activities were conducted from February through April 2009 according to the FFACO (1996; as amended February 2008) and Revision 1 of the Streamlined Approach for Environmental Restoration Plan for CAU 107 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2009). The corrective action alternatives included No Further Action and Closure in Place with Administrative Controls. Closure activities are summarized.

  2. Closure report for housekeeping category, Corrective Action Unit 349, Area 12, Nevada Test Site

    International Nuclear Information System (INIS)

    1998-01-01

    This Closure Report summarizes the corrective actions which were completed at the Corrective Action Sites within Corrective Action Unit 349 Area 12 at the Nevada Test Site. Current site descriptions, observations and identification of wastes removed are included on FFACO Corrective Action Site housekeeping closure verification forms

  3. Closure report for housekeeping category, Corrective Action Unit 349, Area 12, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-01-01

    This Closure Report summarizes the corrective actions which were completed at the Corrective Action Sites within Corrective Action Unit 349 Area 12 at the Nevada Test Site. Current site descriptions, observations and identification of wastes removed are included on FFACO Corrective Action Site housekeeping closure verification forms.

  4. Application of Updated Construction and Demolition Waste Reduction Policy to Army Projects

    Science.gov (United States)

    2015-12-01

    recovering materials for reuse and recycling from demolition, new construction, and renovation and repurposing projects. In its efforts to improve the...Building contents; reuse and recycling potential (including the follow- ing specific materials, products and components that are potentially re- usable...conventional demolition. Implement deconstruction wherever markets or on-site reuse opportunities exist or are anticipated.  Page 24, 3-7 REDUCE

  5. Corrective Action Decision Document/Closure Report for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick

    2013-09-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 105: Area 2 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada. CAU 105 comprises the following five corrective action sites (CASs): -02-23-04 Atmospheric Test Site - Whitney Closure In Place -02-23-05 Atmospheric Test Site T-2A Closure In Place -02-23-06 Atmospheric Test Site T-2B Clean Closure -02-23-08 Atmospheric Test Site T-2 Closure In Place -02-23-09 Atmospheric Test Site - Turk Closure In Place The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 105 based on the implementation of the corrective actions. Corrective action investigation (CAI) activities were performed from October 22, 2012, through May 23, 2013, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites; and in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices.

  6. Closure Report for Corrective Action Unit 573: Alpha Contaminated Sites Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick [Navarro, Las Vegas, NV (United States)

    2017-03-01

    This Closure Report (CR) presents information supporting the closure of Corrective Action Unit (CAU) 573: Alpha Contaminated Sites, Nevada National Security Site, Nevada. CAU 573 comprises the two corrective action sites (CASs): 05-23-02-GMX Alpha Contaminated Are-Closure in Place and 05-45-01-Atmospheric Test Site - Hamilton- Clean Closure. The purpose of this CR is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 573 based on the implementation of the corrective actions. Corrective action activities were performed at Hamilton from May 25 through June 30, 2016; and at GMX from May 25 to October 27, 2016, as set forth in the Corrective Action Decision Document (CADD)/Corrective Action Plan (CAP) for Corrective Action Unit 573: Alpha Contaminated Sites; and in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices. Verification sample results were evaluated against data quality objective criteria developed by stakeholders that included representatives from the Nevada Division of Environmental Protection and the DOE, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) during the corrective action alternative (CAA) meeting held on November 24, 2015. Radiological doses exceeding the final action level were assumed to be present within the high contamination areas associated with CAS 05-23-02, thus requiring corrective action. It was also assumed that radionuclides were present at levels that require corrective action within the soil/debris pile associated with CAS 05-45-01. During the CAU 573 CAA meeting, the CAA of closure in place with a use restriction (UR) was selected by the stakeholders as the preferred corrective action of the high contamination areas at CAS 05-23-02 (GMX), which contain high levels of removable contamination; and the CAA of clean closure was selected by the

  7. Streamlined approach for environmental restoration closure report for Corrective Action Unit 452: Historical underground storage tank release sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1998-04-01

    This report addresses the site characterization of three historical underground storage tank (UST) petroleum hydrocarbon release sites identified as 25-3101-1, 25-3102-3, and 25-3152-1. The sites are located within the Nevada Test Site in Area 25 at Buildings 3101, 3102, and 3152. The characterization was completed to support administrative closure of the sites. Characterization was completed using drilling equipment to delineate the extent of hydrocarbon impact. Clean closure had been previously attempted at each of these sites using backhoe equipment without success due to adjacent structures, buried utilities, or depth restrictions associated with each site. Although the depth and extent of hydrocarbon impact was determined to be too extensive for clean closure, it was verified through drilling that the sites should be closed through an administrative closure. The Nevada Administrative Code ''A Through K'' evaluation completed for each site supports that there is no significant risk to human health or the environment from the impacted soils remaining at each site

  8. OPEN AIR DEMOLITION OF FACILITIES HIGHLY CONTAMINATED WITH PLUTONIUM

    International Nuclear Information System (INIS)

    LLOYD, E.R.

    2007-01-01

    The demolition of highly contaminated plutonium buildings usually is a long and expensive process that involves decontaminating the building to near free- release standards and then using conventional methods to remove the structure. It doesn't, however, have to be that way. Fluor has torn down buildings highly contaminated with plutonium without excessive decontamination. By removing the select source term and fixing the remaining contamination on the walls, ceilings, floors, and equipment surfaces; open-air demolition is not only feasible, but it can be done cheaper, better (safer), and faster. Open-air demolition techniques were used to demolish two highly contaminated buildings to slab-on-grade. These facilities on the Department of Energy's Hanford Site were located in, or very near, compounds of operating nuclear facilities that housed hundreds of people working on a daily basis. To keep the facilities operating and the personnel safe, the projects had to be creative in demolishing the structures. Several key techniques were used to control contamination and keep it within the confines of the demolition area: spraying fixatives before demolition; applying fixative and misting with a fine spray of water as the buildings were being taken down; and demolishing the buildings in a controlled and methodical manner. In addition, detailed air-dispersion modeling was done to establish necessary building and meteorological conditions and to confirm the adequacy of the proposed methods. Both demolition projects were accomplished without any spread of contamination outside the modest buffer areas established for contamination control. Furthermore, personnel exposure to radiological and physical hazards was significantly reduced by using heavy equipment rather than ''hands on'' techniques

  9. The End of the Line, Preparing the Main Plant Process Building for Demolition at the West Valley Demonstration Project

    International Nuclear Information System (INIS)

    Rowell, L.E.; Kurasch, D.H.; Hackett, M.; Gorsuch, G.; Sullivan, D.W.

    2009-01-01

    The West Valley Demonstration Project (WVDP) Act of 1980 authorized the Department of Energy to conduct a high-level radioactive waste management demonstration project at the site of the former Spent Fuel Reprocessing Plant in West Valley, New York to demonstrate solidification techniques to prepare high-level liquid waste for disposal. The reprocessing facility at this site was the only commercial NRC-licensed spent fuel reprocessing plant to have operated in the United States. The spent fuel reprocessing operations ended in 1972 and DoE's cleanup operations have been underway since 1982. High-level waste solidification was safely concluded in 2002 and follow-on activities at the site have been concentrated on facility decontamination and waste management and off-site disposal. Among the features that remain at the WVDP site is the highly-contaminated Main Plant Process Building (MPPB). The five-story reinforced concrete structure, which was formerly used to reprocess irradiated nuclear fuel, contains residual levels of contamination in some areas that prohibit safe human entry. DoE's long-range plans for the site include demolition of the MPPB. Current site contractor, West Valley Environmental Services LLC (WVES), while actively working to dismantle equipment and decontaminate areas inside the MPPB, has developed a conceptual two-phase plan for demolishing the structure that provides a cost-effective, lower-dose alternative to conventional demolition techniques. This paper discusses the current condition of the MPPB and the demolition-ready preparations conducted in the facility thus far. This paper also introduces the concept of a two-part surgical demolition plan that has been proposed and is being evaluated as a safe method of demolishing the structure. The practical applications that support feasibility for the demolition approach are being demonstrated through current work applications in the MPPB. The Inside-Out Demolition proposal for the MPPB is a safe

  10. Proceedings of the eighth annual DOE low-level waste management forum: Technical Session 2, Site closure

    International Nuclear Information System (INIS)

    1987-02-01

    This volume on site closure or site stabilization and closure, centers on a number of major issues which have been identified by the contractor community as requiring resolution before the topic of site stabilization and closure can be laid to rest. All papers, seven total, in this volume have been processed for inclusion in the Energy Data Base. (AT)

  11. Characterization Report Operational Closure Covers for the Area 5 Radioactive Waste Management Site at the Nevada Test Site

    International Nuclear Information System (INIS)

    Bechtel Nevada Geotechnical Sciences

    2005-01-01

    Bechtel Nevada (BN) manages two low-level Radioactive Waste Management Sites (RWMSs) at the Nevada Test Site (NTS) for the U.S. Department of Energy (DOE) National Nuclear Security Administration Nevada Site Office (NNSA/NSO). The Area 3 RWMS is located in south-central Yucca Flat and the Area 5 RWMS is located about 15 miles south, in north-central Frenchman Flat. Though located in two separate topographically closed basins, they are similar in climate and hydrogeologic setting. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste, while the Area 3 RWMS uses subsidence craters formed from underground testing of nuclear weapons for the disposal of packaged and unpackaged bulk waste. Over the next several decades, most waste disposal units at both the Area 3 and Area 5 RWMSs are anticipated to be closed. Closure of the Area 3 and Area 5 RWMSs will proceed through three phases: operational closure, final closure, and institutional control. Many waste disposal units at the Area 5RWMS are operationally closed and final closure has been placed on one unit at the Area 3 RWMS (U-3ax/bl). Because of the similarities between the two sites (e.g., type of wastes, environmental factors, operational closure cover designs, etc.), many characterization studies and data collected at the Area 3 RWMS are relevant and applicable to the Area 5 RWMS. For this reason, data and closure strategies from the Area 3 RWMS are referred to as applicable. This document is an interim Characterization Report - Operational Closure Covers, for the Area 5 RWMS. The report briefly describes the Area 5 RWMS and the physical environment where it is located, identifies the regulatory requirements, reviews the approach and schedule for closing, summarizes the monitoring programs, summarizes characterization studies and results, and then presents conclusions and recommendations

  12. Maxey Flats low-level waste disposal site closure activities

    International Nuclear Information System (INIS)

    Haight, C.P.; Mills, D.; Razor, J.E.

    1987-01-01

    The Maxey Flats Radioactive Waste Disposal Facility in Fleming County, Kentucky is in the process of being closed. The facility opened for commercial business in the spring of 1963 and received approximately 4.75 million cubic feet of radioactive waste by the time it was closed in December of 1977. During fourteen years of operation approximately 2.5 million curies of by-product material, 240,000 kilograms of source material, and 430 kilograms of special nuclear material were disposed. The Commonwealth purchased the lease hold estate and rights in May 1978 from the operating company. This action was taken to stabilize the facility and prepare it for closure consisting of passive care and monitoring. To prepare the site for closure, a number of remedial activities had to be performed. The remediation activities implemented have included erosion control, surface drainage modifications, installation of a temporary plastic surface cover, leachate removal, analysis, treatment and evaporation, US DOE funded evaporator concentrates solidification project and their on-site disposal in an improved disposal trench with enhanced cover for use in a humid environment situated in a fractured geology, performance evaluation of a grout injection demonstration, USGS subsurface geologic investigation, development of conceptual closure designs, and finally being added to the US EPA National Priority List for remediation and closure under Superfund. 13 references, 3 figures

  13. Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 116: Area 25 Test Cell C Facility, Nevada Test Site, Nevada, Revision 1

    International Nuclear Information System (INIS)

    2008-01-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan identifies the activities required for the closure of Corrective Action Unit (CAU) 116, Area 25 Test Cell C Facility. The Test Cell C (TCC) Facility is located in Area 25 of the Nevada Test Site (NTS) approximately 25 miles northwest of Mercury, Nevada (Figure 1). CAU 116 is currently listed in Appendix III of the Federal Facility Agreement and Consent Order (FFACO) of 1996 (as amended February 2008) and consists of two Corrective Action Sites (CASs): (1) CAS 25-23-20, Nuclear Furnace Piping; and (2) CAS 25-41-05, Test Cell C Facility. CAS 25-41-05 is described in the FFACO as the TCC Facility but actually includes Building 3210 and attached concrete shield wall only. CAU 116 will be closed by demolishing Building 3210, the attached concrete shield wall, and the nuclear furnace piping. In addition, as a best management practice (BMP), Building 3211 (moveable shed) will be demolished due to its close proximity to Building 3210. This will aid in demolition and disposal operations. Radiological surveys will be performed on the demolition debris to determine the proper disposal pathway. As much of the demolition debris as space allows will be placed into the Building 3210 basement structure. After filling to capacity with demolition debris, the basement structure will be mounded or capped and closed with administrative controls. Prior to beginning demolition activities and according to an approved Sampling and Analysis Plan (SAP), representative sampling of surface areas that are known, suspected, or have the potential to contain hazardous constituents such as lead or polychlorinated biphenyls (PCBs) will be performed throughout all buildings and structures. Sections 2.3.2, 4.2.2.2, 4.2.2.3, 4.3, and 6.2.6.1 address the methodologies employed that assure the solid debris placed in the basement structure will not contain contaminants of concern (COCs) above hazardous waste levels. The anticipated post-closure

  14. Simplifying documentation while approaching site closure: integrated health and safety plans as documented safety analysis

    International Nuclear Information System (INIS)

    Brown, Tulanda

    2003-01-01

    At the Fernald Closure Project (FCP) near Cincinnati, Ohio, environmental restoration activities are supported by Documented Safety Analyses (DSAs) that combine the required project-specific Health and Safety Plans, Safety Basis Requirements (SBRs), and Process Requirements (PRs) into single Integrated Health and Safety Plans (I-HASPs). By isolating any remediation activities that deal with Enriched Restricted Materials, the SBRs and PRs assure that the hazard categories of former nuclear facilities undergoing remediation remain less than Nuclear. These integrated DSAs employ Integrated Safety Management methodology in support of simplified restoration and remediation activities that, so far, have resulted in the decontamination and demolition (D and D) of over 150 structures, including six major nuclear production plants. This paper presents the FCP method for maintaining safety basis documentation, using the D and D I-HASP as an example

  15. Post-Closure Strategy for Use-Restricted Sites on the Nevada National Security Site, Nevada Test and Training Range, and Tonopah Test Range, Nevada

    International Nuclear Information System (INIS)

    Silvas, A. J.

    2014-01-01

    The purpose of this Post-Closure Strategy is to provide a consistent methodology for continual evaluation of post-closure requirements for use-restricted areas on the Nevada National Security Site (NNSS), Nevada Test and Training Range (NTTR), and Tonopah Test Range (TTR) to consolidate, modify, or streamline the program. In addition, this document stipulates the creation of a single consolidated Post-Closure Plan that will detail the current post-closure requirements for all active use restrictions (URs) and outlines its implementation and subsequent revision. This strategy will ensure effective management and control of the post-closure sites. There are currently over 200 URs located on the NNSS, NTTR, and TTR. Post-closure requirements were initially established in the Closure Report for each site. In some cases, changes to the post-closure requirements have been implemented through addenda, errata sheets, records of technical change, or letters. Post-closure requirements have been collected from these multiple sources and consolidated into several formats, such as summaries and databases. This structure increases the possibility of inconsistencies and uncertainty. As more URs are established and the post-closure program is expanded, the need for a comprehensive approach for managing the program will increase. Not only should the current requirements be obtainable from a single source that supersedes all previous requirements, but the strategy for modifying the requirements should be standardized. This will enable more effective management of the program into the future. This strategy document and the subsequent comprehensive plan are to be implemented under the assumption that the NNSS and outlying sites will be under the purview of the U.S. Department of Energy, National Nuclear Security Administration for the foreseeable future. This strategy was also developed assuming that regulatory control of the sites remains static. The comprehensive plan is not

  16. How the Lean Management System is Working on a Closure Project - 13242

    Energy Technology Data Exchange (ETDEWEB)

    Mowery, Carol [Washington Closure Hanford, 2620 Fermi, Richland, Washington, 99354 (United States)

    2013-07-01

    Washington Closure Hanford, LLC (WCH) manages the River Corridor Closure Project (RCCP), a 10-year contract, in which WCH will clean up 220 mi{sup 2} of contaminated land at the Hanford Site in Richland, Washington. Strategic planning sessions in 2009 identified key performance areas that were essential to closure and in which focused change could result in dramatic performance improvement. Lean Management Systems (Lean) was selected as the methodology to achieve the desired results. The Lean Process is built upon the fundamentals of the power of respect for people and the practice of continuous process improvement. Lean uses week-long, focused sessions that teach a selected team the techniques to recognize waste within their own work processes, propose potential solutions, and then conduct experiments during the week to test their solutions. In 2011, the Lean process was implemented in the Waste Operations organization. From there it was expanded to closure documents, field remediation, and decommissioning and demolition. WCH identified the following Lean focus areas: 1) closure document processes that required extensive internal preparation, and lengthy external review and approval cycles; 2) allocation of limited transportation and waste disposal resources to meet aggressive remediation schedules; 3) effective start-of-the-day routines in field operations; 4) improved excavation and load-out processes; and 5) approaches to strengthen safety culture and support disciplined operations. Since the introduction of Lean, RCCP has realized many successes and also gained some unexpected benefits. (authors)

  17. How the Lean Management System is Working on a Closure Project - 13242

    International Nuclear Information System (INIS)

    Mowery, Carol

    2013-01-01

    Washington Closure Hanford, LLC (WCH) manages the River Corridor Closure Project (RCCP), a 10-year contract, in which WCH will clean up 220 mi 2 of contaminated land at the Hanford Site in Richland, Washington. Strategic planning sessions in 2009 identified key performance areas that were essential to closure and in which focused change could result in dramatic performance improvement. Lean Management Systems (Lean) was selected as the methodology to achieve the desired results. The Lean Process is built upon the fundamentals of the power of respect for people and the practice of continuous process improvement. Lean uses week-long, focused sessions that teach a selected team the techniques to recognize waste within their own work processes, propose potential solutions, and then conduct experiments during the week to test their solutions. In 2011, the Lean process was implemented in the Waste Operations organization. From there it was expanded to closure documents, field remediation, and decommissioning and demolition. WCH identified the following Lean focus areas: 1) closure document processes that required extensive internal preparation, and lengthy external review and approval cycles; 2) allocation of limited transportation and waste disposal resources to meet aggressive remediation schedules; 3) effective start-of-the-day routines in field operations; 4) improved excavation and load-out processes; and 5) approaches to strengthen safety culture and support disciplined operations. Since the introduction of Lean, RCCP has realized many successes and also gained some unexpected benefits. (authors)

  18. DEMOLITION OF HANFORD'S 232-Z WASTE INCINERATION FACILITY

    International Nuclear Information System (INIS)

    LLOYD, E.R.

    2006-01-01

    The 232-Z Plutonium Incinerator Facility was a small, highly alpha-contaminated, building situated between three active buildings located in an operating nuclear complex. Approximately 500 personnel worked within 250 meters (800 ft) of the structure and expectations were that the project would neither impact plant operations nor result in any restrictions when demolition was complete. Precision demolition and tight controls best describe the project. The team used standard open-air demolition techniques to take the facility to slab-on-grade. Several techniques were key to controlling contamination and confining it to the demolition area: spraying fixatives before demolition began; using misting systems, frequently applying fixatives, and using a methodical demolition sequence and debris load-out process. Detailed air modeling was done before demolition to determine necessary facility source-term levels, establish radiological boundaries, and confirm the adequacy of the proposed demolition approach. By only removing the major source term in equipment, HEPA filters, gloveboxes, and the like, and leaving fixed contamination on the walls, ceilings and floors, the project showed considerable savings and reduced worker hazards and exposure. The ability to perform this demolition safely and without the spread of contamination provides confidence that similar operations can be performed successfully. By removing the major source terms, fixing the remaining contamination in the building, and using controlled demolition and contamination control techniques, similar structures can be demolished cost effectively and safely

  19. CLOSURE REPORT FOR CORRECTIVE ACTION UNIT 528: POLYCHLORINATED BIPHENYLS CONTAMINATION NEVADA TEST SITE, NEVADA

    Energy Technology Data Exchange (ETDEWEB)

    BECHTEL NEVADA

    2006-09-01

    This Closure Report (CR) describes the closure activities performed at CAU 528, Polychlorinated Biphenyls Contamination, as presented in the Nevada Division of Environmental Protection (NDEP)-approved Corrective Action Plan (CAP) (US. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSAINSO], 2005). The approved closure alternative was closure in place with administrative controls. This CR provides a summary of the completed closure activities, documentation of waste disposal, and analytical data to confirm that the remediation goals were met.

  20. Data Quality Objectives Summary Report for the Demolition of the 116-D and 116-DR Stacks

    International Nuclear Information System (INIS)

    Adler, J. G.

    1999-01-01

    This data quality objective (DQO) summary report has been developed to support demolition and disposal of the 116-D and 116-DR stacks in the 100-D Area of the Hanford Site. This project-specific summary was developed to meet the requirements in BHI-EE-01, Environmental Investigations Procedures, Procedure 1.2, ''Data Quality Objectives,'' using a simplified DQO process. The pathway for disposal of the 116-D and 116-DR stacks is the Environmental Restoration Disposal Facility (ERDF), which requires the development of a waste profile. A combination of process knowledge, history, and existing analogous data will be used to build a waste profile to dispose of the stack and plenum debris in the ERDF. Additional sample data are not necessary for waste designation. This report also addresses the Resources, Conservation, and Recovery Act of 1976 treatment, storage, and disposal closure requirements associated with the 116-DR stack

  1. Closure Report for Corrective Action Unit 107: Low Impact Soil Sites, Nevada Test Site, Nevada with ROTC-1

    International Nuclear Information System (INIS)

    Matthews, Patrick

    2009-01-01

    CAU 107, ''Low Impact Soil Sites'', consists of 15 CASs in Areas 1, 2, 3, 4, 5, 9, 10, and 18 of the NTS. The closure alternatives included No Further Action and Closure in Place with Administrative Controls. This CR provides a summary of completed closure activities. ROTC Justification: The FFACO UR as published in the Closure Report for Corrective Action Unit 107: Low Impact Soil Sites, Nevada Test Site, Nevada (NNSA/NSO, 2009) states that the UR for CAS 18-23-02, U-18d Crater (Sulky), was implemented for assumed radioactive contamination that could cause a dose greater that 25 millirems per year. This document further clarifies that this was based on particulate releases of radionuclides identified in Radiological Effluents Released from U.S. Continental Tests, 1961 through 1992 (DOE/NV, 1996). The radionuclides listed in this document are krypton (Kr)-85, Kr-85m, Kr-87, Kr-88, rubidium (Rb)-87, strontium (Sr)-89, Sr-91, yttrium (Y)-91, iodine (I)-131, I-132, I-133, I-134, I-135, xeon (Xe)-133, Xe-135, Xe-138, cesium (Cs)-135, Cs-138, barium (Ba)-139, and Ba-140.

  2. Corrective Action Decision Document/Closure Report for Corrective Action Unit 567: Miscellaneous Soil Sites - Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick [Navarro-Intera, LLC (N-I), Las Vegas, NV (United States)

    2014-12-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 567: Miscellaneous Soil Sites, Nevada National Security Site, Nevada. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 567 based on the implementation of the corrective actions. The corrective actions implemented at CAU 567 were developed based on an evaluation of analytical data from the CAI, the assumed presence of COCs at specific locations, and the detailed and comparative analysis of the CAAs. The CAAs were selected on technical merit focusing on performance, reliability, feasibility, safety, and cost. The implemented corrective actions meet all requirements for the technical components evaluated. The CAAs meet all applicable federal and state regulations for closure of the site. Based on the implementation of these corrective actions, the DOE, National Nuclear Security Administration Nevada Field Office provides the following recommendations: • No further corrective actions are necessary for CAU 567. • The Nevada Division of Environmental Protection issue a Notice of Completion to the DOE, National Nuclear Security Administration Nevada Field Office for closure of CAU 567. • CAU 567 be moved from Appendix III to Appendix IV of the FFACO.

  3. INTEC CPP-603 Basin Water Treatment System Closure: Process Design

    Energy Technology Data Exchange (ETDEWEB)

    Kimmitt, Raymond Rodney; Faultersack, Wendell Gale; Foster, Jonathan Kay; Berry, Stephen Michael

    2002-09-01

    This document describes the engineering activities that have been completed in support of the closure plan for the Idaho Nuclear Technology and Engineering Center (INTEC) CPP-603 Basin Water Treatment System. This effort includes detailed assessments of methods and equipment for performing work in four areas: 1. A cold (nonradioactive) mockup system for testing equipment and procedures for vessel cleanout and vessel demolition. 2. Cleanout of process vessels to meet standards identified in the closure plan. 3. Dismantlement and removal of vessels, should it not be possible to clean them to required standards in the closure plan. 4. Cleanout or removal of pipelines and pumps associated with the CPP-603 basin water treatment system. Cleanout standards for the pipes will be the same as those used for the process vessels.

  4. Wound management with vacuum assisted closure in surgical site infection after ankle surgery.

    Science.gov (United States)

    Zhou, Zhen-Yu; Liu, Ya-Ke; Chen, Hong-Lin; Liu, Fan

    2015-05-01

    The aim of this study was to compare the efficacy of vacuum assisted closure (VAC) with standard moist wound care (SMWC) in surgical site infection after ankle surgery. A prospective cohort was performed among patients with surgical site infection after ankle surgery between 2012 and 2013. The follow-up period was three month, and the efficacy end point was complete wound closure rate. Ninety-four patients were analyzed, with 61 patients in the VAC group and 33 in the SMWC group. The complete wound closure rate in the VAC group was higher than that in the SMWC group at 3 month follow up (90.2% Vs. 72.7%, p = 0.028). The median time to complete wound closure was 31 days (95% CI 20.2-41.8) for VAC, and 63 days (95% CI 46.9-79.1) for SMWC (χ(2) = 4.023, p = 0.045). In the superficial infection subgroup, the median times to complete wound closure were 20 days (95% CI 14.2-35.1) in the VAC group and 42 days (95% CI 35.4-69.4) in SMWC group (χ(2) = 4.331, p = 0.041). In the deep subgroup, the median times to complete wound closure were 46 days (95% CI 28.2-65.9) in the VAC group and 75 days (95% CI 43.2-79.6) in SMWC group (χ(2) = 6.475, p = 0.026). Our result showed that vacuum assisted closure was more effective than standard moist wound care in surgical site infection after ankle surgery. Copyright © 2015 IJS Publishing Group Limited. Published by Elsevier Ltd. All rights reserved.

  5. Environmental analysis of closure options for waste sites at the Savannah River Plant

    International Nuclear Information System (INIS)

    Gordon, D.E.; King, C.M.; Looney, B.B.; Stephenson, D.E.; Johnson, W.F.

    1987-01-01

    Previously acceptable waste management practices (e.g., the use of unlined seepage basins) for discarding of wastes from nuclear materials production has resulted in occasional cases of groundwater contamination beneath some disposal sites, mainly in water-table aquifers. Groundwater contaminants include volatile organic compounds, heavy metals, radionuclides, and other chemicals. The closure of active and inactive waste sites that have received hazardous and/or low-level radioactive materials at the Savannah River Plant (SRP) is planned as part of an overall program to protect groundwater quality. DOE developed and submitted to Congress a groundwater protection plan for SRP. This initial plan and subsequent revisions provide the basis for closure of SRP waste sites to comply with applicable groundwater protection requirements. An environmental analysis of the closure options for the criteria waste sites that have received hazardous and/or low-level radioactive wastes was conducted to provide technical support. The several parts of this environmental analysis include description of geohydrologic conditions; determination of waste inventories; definition of closure options; modeling of environmental pathways; assessment of risk; and analysis of project costs. Each of these components of the overall analysis is described in turn in the following paragraphs. Production operations at SRP have generated a variety of solid, hazardous, and low-level radioactive waste materials. Several locations onplant have been used as waste disposal sites for solid and liquid wastes. Seventy-six individual waste sites at 45 distinct geographical locations on SRP have received hazardous, low-level radioactive, or mixed wastes. These waste sites can be categorized into 26 groupings according to the function of the waste disposed. 15 refs., 6 figs., 5 tabs

  6. Closure Report for Corrective Action Unit 366: Area 11 Plutonium Valley Dispersion Sites, Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2013-12-31

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 366, Area 11 Plutonium Valley Dispersion Sites, and provides documentation supporting the completed corrective actions and confirmation that closure objectives for CAU 366 were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; the U.S. Department of Energy (DOE), Environmental Management; the U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996 as amended).

  7. Applying Lean Concepts to Waste Site Closure - 13137

    International Nuclear Information System (INIS)

    Proctor, M.L.

    2013-01-01

    Washington Closure Hanford (WCH) was selected by the U.S. Department of Energy, Richland Operations Office to manage the River Corridor Closure Project, a 10-year contract in which WCH will clean up 220 mi 2 of contaminated land at the Hanford Site in Richland, Washington. In the summer of 2011, with Tri-Party (DOE-RL, Environmental Protection Agency and Washington State Department of Ecology) Agreement Milestones due at the end of the calendar year, standard work practices were challenged in regards to closure documentation development. The Lean process, a concept that maximizes customer value while minimizing waste, was introduced to WCH's Sample Design and Cleanup Verification organization with the intention of eliminating waste and maximizing efficiencies. The outcome of implementing Lean processes and concepts was impressive. It was determined that the number of non-value added steps far outnumbered the value added steps. Internal processing time, document size, and review times were all reduced significantly; relationships with the customer and the regulators were also improved; and collaborative working relationships with the Tri Parties have been strengthened by working together on Lean initiatives. (authors)

  8. Applying Lean Concepts to Waste Site Closure - 13137

    Energy Technology Data Exchange (ETDEWEB)

    Proctor, M.L. [Washington Closure Hanford, 2620 Fermi, Richland, Washington 99354 (United States)

    2013-07-01

    Washington Closure Hanford (WCH) was selected by the U.S. Department of Energy, Richland Operations Office to manage the River Corridor Closure Project, a 10-year contract in which WCH will clean up 220 mi{sup 2} of contaminated land at the Hanford Site in Richland, Washington. In the summer of 2011, with Tri-Party (DOE-RL, Environmental Protection Agency and Washington State Department of Ecology) Agreement Milestones due at the end of the calendar year, standard work practices were challenged in regards to closure documentation development. The Lean process, a concept that maximizes customer value while minimizing waste, was introduced to WCH's Sample Design and Cleanup Verification organization with the intention of eliminating waste and maximizing efficiencies. The outcome of implementing Lean processes and concepts was impressive. It was determined that the number of non-value added steps far outnumbered the value added steps. Internal processing time, document size, and review times were all reduced significantly; relationships with the customer and the regulators were also improved; and collaborative working relationships with the Tri Parties have been strengthened by working together on Lean initiatives. (authors)

  9. Amchitka Mud Pit Sites 2006 Post-Closure Monitoring and Inspection Report, Amchitka Island, Alaska, Rev. No.: 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick

    2006-09-01

    In 2001, the U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA/NSO) remediated six areas associated with Amchitka mud pit release sites located on Amchitka Island, Alaska. This included the construction of seven closure caps. To ensure the integrity and effectiveness of remedial action, the mud pit sites are to be inspected every five years as part of DOE's long-term monitoring and surveillance program. In August of 2006, the closure caps were inspected in accordance with the ''Post-Closure Monitoring and Inspection Plan for Amchitka Island Mud Pit Release Sites'' (Rev. 0, November 2005). This post-closure monitoring report provides the 2006 cap inspection results.

  10. Corrective Action Decision Document/Closure Report for Corrective Action Unit 370: T-4 Atmospheric Test Site, Nevada Test Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Patrick Matthews

    2009-05-01

    This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit (CAU) 370, T-4 Atmospheric Test Site, located in Area 4 at the Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 370 is comprised of Corrective Action Site (CAS) 04-23-01, Atmospheric Test Site T-4. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 370 due to the implementation of the corrective action of closure in place with administrative controls. To achieve this, corrective action investigation (CAI) activities were performed from June 25, 2008, through April 2, 2009, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 370: T-4 Atmospheric Test Site and Record of Technical Change No. 1.

  11. Impact of liability and site closure and long-term care issues on future siting efforts

    International Nuclear Information System (INIS)

    Carlin, E.M.; Hana, S.L.A.

    1988-01-01

    Washington's research in the area of financial responsibility for liability and cleanup for radioactive materials licensees and low-level radioactive waste permittees is offered to assist unsited states and regions in their planning and development of new low-level waste disposal capacity. The state considered the need for third party bodily injury and property damage financial responsibility and determined that the USDOT requirements comprehensively cover transport of wastes. In regard to licensees' facilities, it is the state's opinion that an adequate technical basis for third party requirements has not yet been developed. Also considered was the need for financial assurance for cleanup, which is covered for transportation, but generally not available for facilities. Three options are examined to provide such coverage, and the economic impact on licensees assessed. Finally, the current low-level waste disposal site operator's insurance coverage is analyzed and deficiencies are identified. Washington is also conducting research into site closure and perpetual care and maintenance requirements for the commercial low-level radioactive waste disposal facility located on the Hanford reservation near Richland, Washington. This research includes a site assessment and identification and formulation of site-specific design elements for closure and long-term care

  12. Quality assurance and demolition: 2008 symposium

    International Nuclear Information System (INIS)

    Schartmann, F.; Thierfeldt, S.

    2008-01-01

    The 'Quality Assurance and Demolition Symposium, which has become a tradition established jointly by Applus RTD Deutschland GmbH (formerly compra GmbH) and Brenk Systemplanung GmbH, Aachen, was held also in 2008 with the focus on quality assurance and the demolition of nuclear facilities. The conference began with a series of lectures on knowledge and document management in general, and the use of document management systems in the nuclear field in particular. The evening lecture was presented by Axel Weis (Karlsruhe Research Center) on 'Competence Preservation in Nuclear Technology'. The 24 technical papers presented on the next 2 days of the symposium dealt with non-destructive materials testing and with special problems of radiation protection, demolition, and waste management. In 2009, the meeting will cover similar main topics and will again be held in an interesting environment, perhaps in combination with a tour of a demolition project. (orig.)

  13. Closure Report for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2008-01-01

    This Closure Report (CR) documents closure activities for Corrective Action Unit (CAU) 543, Liquid Disposal Units, according to the Federal Facility Agreement and Consent Order (FFACO, 1996) and the Corrective Action Plan (CAP) for CAU 543 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2007). CAU 543 is located at the Nevada Test Site (NTS), Nevada (Figure 1), and consists of the following seven Corrective Action Sites (CASs): CAS 06-07-01, Decon Pad; CAS 15-01-03, Aboveground Storage Tank; CAS 15-04-01, Septic Tank; CAS 15-05-01, Leachfield; CAS 15-08-01, Liquid Manure Tank; CAS 15-23-01, Underground Radioactive Material Area; CAS 15-23-03, Contaminated Sump, Piping; and CAS 06-07-01 is located at the Decontamination Facility in Area 6, adjacent to Yucca Lake. The remaining CASs are located at the former U.S. Environmental Protection Agency (EPA) Farm in Area 15. The purpose of this CR is to provide a summary of the completed closure activities, to document waste disposal, and to present analytical data confirming that the remediation goals were met. The closure alternatives consisted of closure in place for two of the CASs, and no further action with implementation of best management practices (BMPs) for the remaining five CASs.

  14. Comparison of primary and delayed primary closure in dirty abdominal wounds in terms of frequency of surgical site infection

    International Nuclear Information System (INIS)

    Aziz, O.B.A.; Ahmed, N.; Butt, M.W.U.D.; Saleem, M.R.

    2013-01-01

    Objective: Objective of this study was to compare primary and delayed primary wound closure for dirty abdominal wounds in terms of frequency of surgical site infection. Study Design: Randomized Controlled Trial. Place and Duration of Study: Combined Military Hospital, Multan. From 16 Sep 2010 to 15 Mar 2011. Patients and Methods: A total of 110 patients were randomly divided into two groups of 55 patients each using random numbers table. Abdominal wounds of one group were closed primarily and of other group were subjected to delayed primary wound closure. The wounds were then checked for surgical site infection for seven post operative days. Results: A higher frequency of surgical site infection was observed in primary closure group (27.3%) as compared to delayed primary closure group (9.1%) which was statistically significant (p=0.013). Conclusion: Delayed primary closure is superior to primary closure in dirty abdominal wounds in terms of frequency of surgical site infection. (author)

  15. Integrated Closure and Monitoring Plan for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    S. E. Rawlinson

    2001-09-01

    Bechtel Nevada (BN) manages two low-level Radioactive Waste Management Sites (RWMSs) (one site is in Area 3 and the other is in Area 5) at the Nevada Test Site (NTS) for the U.S. Department of Energy's (DOE's) National Nuclear Security Administration Nevada Operations Office (NNSA/NV). The current DOE Order governing management of radioactive waste is 435.1. Associated with DOE Order 435.1 is a Manual (DOE M 435.1-1) and Guidance (DOE G 435.1-1). The Manual and Guidance specify that preliminary closure and monitoring plans for a low-level waste (LLW) management facility be developed and initially submitted with the Performance Assessment (PA) and Composite Analysis (CA) for that facility. The Manual and Guidance, and the Disposal Authorization Statement (DAS) issued for the Area 3 RWMS further specify that the preliminary closure and monitoring plans be updated within one year following issuance of a DAS. This Integrated Closure and Monitoring Plan (ICMP) fulfills both requirements. Additional updates will be conducted every third year hereafter. This document is an integrated plan for closing and monitoring both RWMSs, and is based on guidance issued in 1999 by the DOE for developing closure plans. The plan does not follow the format suggested by the DOE guidance in order to better accommodate differences between the two RWMSs, especially in terms of operations and site characteristics. The modification reduces redundancy and provides a smoother progression of the discussion. The closure and monitoring plans were integrated because much of the information that would be included in individual plans is the same, and integration provides efficient presentation and program management. The ICMP identifies the regulatory requirements, describes the disposal sites and the physical environment where they are located, and defines the approach and schedule for both closing and monitoring the sites.

  16. Construction quality assurance closure report, Lawrence Livermore National Laboratory Site 300, Pits 1 and 7

    International Nuclear Information System (INIS)

    1993-02-01

    This document presents the Final Construction Quality Assurance (CQA) report for the closure cover system of two mixed, low-level radioactive and hazardous waste landfills (pits) at Site 300. Site 300, operated by the Lawrence Livermore National Laboratory (LLNL), is located in the Altamont Hills, approximately 15 miles southeast of Livermore, California. The purpose of this report is to document the CQA program established to assure that construction is completed in accordance with the design intent and the approved Closure and Post Closure Plans dated May 1989 and revised January 1990 (EPA ID Number: CA 2890090002). Inclusive within the Closure and Post Closure Plan were the CQA Plan and the Technical Specifications for the final cover system. This report contains a complete narrative with photographic documentation of the construction activities and progress, problems encountered and solutions utilized, and third party testing and monitoring results, thus establishing the verification of compliance with the Quality Assurance Plan for the project

  17. Handling construction waste of building demolition

    Directory of Open Access Journals (Sweden)

    Vondráčková Terezie

    2018-01-01

    Full Text Available Some building defects lead to their demolition. What about construction and demolition waste? According to the Waste Act 185/2001 Coll. and its amendment 223/2015 Coll., which comes into force on January 1, 2017, the production of waste has to be reduced because, as already stated in the amendment to Act No. 229/2014 Coll., the ban on landfilling of waste will apply from 2024 onwards. The main goals of waste management can thus be considered: Preventing or minimizing waste; Waste handling to be used as a secondary raw material - recycling, composting, combustion and the remaining waste to be dumped. Company AZS 98 s. r. o. was established, among other activities, also for the purpose of recycling construction and demolition waste. It operates 12 recycling centers throughout the Czech Republic and therefore we have selected it for a demonstration of the handling of construction and demolition waste in addressing the defects of the buildings.

  18. Sustainable Management of Construction and Demolition Materials

    Science.gov (United States)

    This web page discusses how to sustainably manage construction and demolition materials, Information covers, what they are, and how builders, construction crews, demolition teams,and deign practitioners can divert C&D from landfills.

  19. Construction quality assurance for Pit 6 landfill closure, Lawrence Livermore National Laboratory, Site 300

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-10-30

    Golder Construction Services, Inc. (GCS), under contract to the Regents of the University of California, Lawrence Livermore National Laboratory (LLNL), provided the construction quality assurance (CQA) observation and testing during the construction of the Site 300, Pit 6 landfill closure cover. The cap construction was performed as a CERCLA non-time-critical removal action from June 2 to August 29, 1997. the project site is located 18 miles east of Livermore on Tesla Road and approximately 10 miles southwest of Tracy on Corral Hollow Road in San Joaquin County, California. This report certifies that the LLNL, Site 300, Pit 6, Landfill Closure was constructed in accordance with the construction specifications and design drawings. This report documents construction activities and CQA monitoring and testing for construction of the Pit 6 Landfill Closure. Golder Associates, Inc. of Oakland, California was the design engineering firm responsible for preparation of the drawings and specifications. CQA services were provided by GCS, of Roseville, California, under supervision of a California registered civil Engineer.

  20. Facility Closure Report for T-Tunnel (U12T), Area 12, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2008-01-01

    This Facility Closure Report (FCR) has been prepared to document the actions taken to permanently close the remaining accessible areas of U12t-Tunnel (T-Tunnel) in Area 12 of the Nevada Test Site (NTS). The closure of T-Tunnel was a prerequisite to transfer facility ownership from the Defense Threat Reduction Agency (DTRA) to the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). Closure of the facility was accomplished with the cooperation and concurrence of both NNSA/NSO and the Nevada Division of Environmental Protection (NDEP). The purpose of this FCR is to document that the closure of T-Tunnel complied with the closure requirements specified in the Facility Closure Plan for N- and T-Tunnels Area 12, Nevada Test Site (Appendix D) and that the facility is ready for transfer to NNSA/NSO. The Facility Closure Plan (FCP) is provided in Appendix D. T-Tunnel is located approximately 42 miles north of Mercury in Area 12 of the NTS (Figure 1). Between 1970 and 1987, T-Tunnel was used for six Nuclear Weapons Effects Tests (NWETs). The tunnel was excavated horizontally into the volcanic tuffs of Rainier Mesa. The T-Tunnel complex consists of a main access drift with two NWET containment structures, a Gas Seal Plug (GSP), and a Gas Seal Door (GSD) (Figure 2). The T-Tunnel complex was mothballed in 1993 to preserve the tunnel for resumption of testing, should it happen in the future, to stop the discharge of tunnel effluent, and to prevent unauthorized access. This was accomplished by sealing the main drift GSD

  1. Program for closure of an inactive radioactive waste disposal site at the Savannah River Plant

    International Nuclear Information System (INIS)

    Cook, J.R.

    1987-01-01

    The 643-G Radioactive Waste Disposal Facility was operated at the Savannah River Plant from 1952 through 1974, and has been inactive since that time. The actions leading to closure of 643-G will involve a combination of activities consisting of limited waste removal, stabilization, capping, and monitoring. The overall effect of these closure actions will be to place the 643-G site in a physically and chemically stable state which will remain stable over a long period of time. During a one-hundred year institutional control period surveillance and monitoring of the site will be carried out to verify that the performance of the system is acceptable, and access of the general public to the site will be restricted. The program described in this paper is a recommendation; the actual closure plan will be negotiated with regulatory authorities. 2 figs., 1 tab

  2. Middlesex FUSRAP Site - A Path to Site-Wide Closure - 13416

    Energy Technology Data Exchange (ETDEWEB)

    Miller, David M. [ECC, 110 Fieldcrest Ave, Ste 31, Edison, NJ, 08837 (United States); Edge, Helen [US Army Corps of Engineers - NYD, 26 Federal Plaza, Room 1811, New York, NY, 10278 (United States)

    2013-07-01

    The road-map to obtaining closure of the Middlesex Sampling Plant FUSRAP site in Middlesex, New Jersey (NJ) has required a multi-faceted approach, following the CERCLA Process. Since 1998, the US ACE, ECC, and other contractors have completed much of the work required for regulatory acceptance of site closure with unrestricted use. To date, three buildings have been decontaminated, demolished, and disposed of. Two interim storage piles have been removed and disposed of, followed by the additional removal and disposal of over 87,000 tons of radiologically and chemically-impacted subsurface soils by the summer of 2008. The US ACE received a determination from the EPA for the soils Operable Unit, (OU)-1, in September 2010 that the remedial excavations were acceptable, and meet the criteria for unrestricted use as required by the 2004 Record of Decision (ROD) for OU-1. Following the completion of OU-1, the project delivery team performed additional field investigation of the final Operable Unit for Middlesex, OU-2, Groundwater. As of December 2012, the project delivery team has completed a Supplemental Remedial Investigation, which will be followed with a streamlined Feasibility Study, Proposed Plan, and ROD. Several years of historical groundwater data was available from previous investigations and the FUSRAP Environmental Surveillance Program. Historical data indicated sporadic detections of Volatile Organic Compounds (VOCs), primarily trichloroethylene (TCE), carbon tetrachloride (CT), and methyl tert-butyl ether (MTBE), with no apparent trend or pattern indicating extent or source of the VOC impact. In 2008, the project delivery team initiated efforts to re-assess the Conceptual Site Model (CSM) for groundwater. The bedrock was re-evaluated as a leaky multi-unit aquifer, and a plan was developed for additional investigations for adequate bedrock characterization and delineation of groundwater contaminated primarily by CT, TCE, and tetrachloroethene (PCE). The

  3. Closure Report for Corrective Action Unit 562: Waste Systems, Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2012-08-15

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 562, Waste Systems, and provides documentation supporting the completed corrective actions and confirmation that closure objectives for CAU 562 were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; the U.S. Department of Energy (DOE), Environmental Management; the U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996 as amended). CAU 562 consists of the following 13 Corrective Action Sites (CASs), located in Areas 2, 23, and 25 of the Nevada National Security Site: · CAS 02-26-11, Lead Shot · CAS 02-44-02, Paint Spills and French Drain · CAS 02-59-01, Septic System · CAS 02-60-01, Concrete Drain · CAS 02-60-02, French Drain · CAS 02-60-03, Steam Cleaning Drain · CAS 02-60-04, French Drain · CAS 02-60-05, French Drain · CAS 02-60-06, French Drain · CAS 02-60-07, French Drain · CAS 23-60-01, Mud Trap Drain and Outfall · CAS 23-99-06, Grease Trap · CAS 25-60-04, Building 3123 Outfalls Closure activities began in October 2011 and were completed in April 2012. Activities were conducted according to the Corrective Action Plan for CAU 562 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2011). The corrective actions included No Further Action and Clean Closure. Closure activities generated sanitary waste and hazardous waste. Some wastes exceeded land disposal limits and required offsite treatment prior to disposal. Other wastes met land disposal restrictions and were disposed in appropriate onsite or offsite landfills. NNSA/NSO requests the following: · A Notice of Completion from the Nevada Division of Environmental Protection to NNSA/NSO for closure of CAU 562 · The transfer of CAU 562 from Appendix III to Appendix IV, Closed Corrective Action Units, of the FFACO

  4. Closure report for CAU No. 450: Historical UST release sites, Nevada Test Site. Volume 2

    International Nuclear Information System (INIS)

    1997-09-01

    This report addresses the closure of 11 historical underground storage tank release sites within various areas of the Nevada Test Site. This report contains remedial verification of the soil sample analytical results for the following: Area 11 Tweezer facility; Area 12 boiler house; Area 12 service station; Area 23 bypass yard; Area 23 service station; Area 25 power house; Area 25 tech. services building; Area 25 tech. operations building; Area 26 power house; and Area 27 boiler house

  5. 26 CFR 1.280B-1 - Demolition of structures.

    Science.gov (United States)

    2010-04-01

    ... 26 Internal Revenue 3 2010-04-01 2010-04-01 false Demolition of structures. 1.280B-1 Section 1... (CONTINUED) INCOME TAXES Items Not Deductible § 1.280B-1 Demolition of structures. (a) In general. Section 280B provides that, in the case of the demolition of any structure, no deduction otherwise allowable...

  6. K-25 Structural Separation and Demolition

    International Nuclear Information System (INIS)

    Cater, Frank

    2008-01-01

    The K-25 building is a former gaseous diffusion plant, built in 1944-1945 as part of the United States Manhattan Project. The structure was the largest structure under one roof, surpassed only by the Pentagon. Together the three wings represent about 17.8 hectare (44 acres) under roof and are generally about 18.3 meters (60 ft.) high on the outside face and approximately 12.2 meters (40 ft.) high on the inside face. The entire structure was built in the shape of a 'U', with a lateral distance of approximately one mile. It was constructed in individual building units with each unit connected using expansion joint-type connection. A single unit is approximately 24.4 meters (80 ft.) across and 122 meters (400 ft.) deep. The northern structure is connected to the eastern and western structures at the upper level floors. The four-level, U-shaped building is a steel-frame structure with corrugated cement-asbestos siding. The cell level is an elevated concrete structure supported by reinforced concrete columns located in the basement, or vault area. The vault area can be accessed at grade level from the outside perimeter. Inside the courtyard, the grade level has been raised to provide entry to the second or cell floor level. An engineering evaluation of the structure was performed to determine the condition of the structure and possibility of unplanned collapse of any portion of the structure. The evaluation included physical inspections, calculations for wind, pre-demolition loads, and evaluation of failure modes. The results of the evaluation have provided guidance for the demolition plan and the development of criteria for protection of personnel performing pre-demolition activities. Challenges include degradation of the structure that necessitated repair, dealing with changes in the code revisions from both the American Concrete Institute (ACI) and the American Institute of Steel Construction (AISC), access to areas of the structure that were not necessarily designed

  7. Optimization of the Area 5 Radioactive Waste Management Site Closure Cover

    Energy Technology Data Exchange (ETDEWEB)

    Shott, Greg; Yucel, Vefa

    2009-04-01

    The U.S. Department of Energy Manual DOE M 435.1-1, “Radioactive Waste Management Manual,” requires that performance assessments demonstrate that releases of radionuclides to the environment are as low as reasonably achievable (ALARA). Quantitative cost benefit analysis of radiation protection options is one component of the ALARA process. This report summarizes a quantitative cost benefit analysis of closure cover thickness for the Area 5 Radioactive Waste Management Site (RWMS) on the Nevada Test Site. The optimum cover thickness that maintains doses ALARA is shown to be the thickness with the minimum total closure cost. Total closure cost is the sum of cover construction cost and the health detriment cost. Cover construction cost is estimated based on detailed cost estimates for closure of the 92-acre Low-Level Waste Management Unit (LLWMU). The health detriment cost is calculated as the product of collective dose and a constant monetary value of health detriment in units of dollars per unit collective dose. Collective dose is the sum of all individual doses in an exposed population and has units of person-sievert (Sv). Five discrete cover thickness options ranging from 2.5 to 4.5 meters (m) (8.2 to 15 feet [ft]) are evaluated. The optimization was subject to the constraints that (1) options must meet all applicable regulatory requirements and that (2) individual doses be a small fraction of background radiation dose. Total closure cost is found to be a monotonically increasing function of cover thickness for the 92-ac LLWMU, the Northern Expansion Area, and the entire Area 5 RWMS. The cover construction cost is orders of magnitude greater than the health detriment cost. Two-thousand Latin hypercube sampling realizations of the relationship between total closure cost and cover thickness are generated. In every realization, the optimum cover thickness is 2.5 m (8.2 ft) for the 92-ac Low-Level Waste Management Unit, the Northern Expansion Area, and the entire

  8. Optimization of the Area 5 Radioactive Waste Management Site Closure Cover

    International Nuclear Information System (INIS)

    Shott, Greg; Yucel, Vefa

    2009-01-01

    The U.S. Department of Energy Manual DOE M 435.1-1, 'Radioactive Waste Management Manual,' requires that performance assessments demonstrate that releases of radionuclides to the environment are as low as reasonably achievable (ALARA). Quantitative cost benefit analysis of radiation protection options is one component of the ALARA process. This report summarizes a quantitative cost benefit analysis of closure cover thickness for the Area 5 Radioactive Waste Management Site (RWMS) on the Nevada Test Site. The optimum cover thickness that maintains doses ALARA is shown to be the thickness with the minimum total closure cost. Total closure cost is the sum of cover construction cost and the health detriment cost. Cover construction cost is estimated based on detailed cost estimates for closure of the 92-acre Low-Level Waste Management Unit (LLWMU). The health detriment cost is calculated as the product of collective dose and a constant monetary value of health detriment in units of dollars per unit collective dose. Collective dose is the sum of all individual doses in an exposed population and has units of person-sievert (Sv). Five discrete cover thickness options ranging from 2.5 to 4.5 meters (m) (8.2 to 15 feet (ft)) are evaluated. The optimization was subject to the constraints that (1) options must meet all applicable regulatory requirements and that (2) individual doses be a small fraction of background radiation dose. Total closure cost is found to be a monotonically increasing function of cover thickness for the 92-ac LLWMU, the Northern Expansion Area, and the entire Area 5 RWMS. The cover construction cost is orders of magnitude greater than the health detriment cost. Two-thousand Latin hypercube sampling realizations of the relationship between total closure cost and cover thickness are generated. In every realization, the optimum cover thickness is 2.5 m (8.2 ft) for the 92-ac Low-Level Waste Management Unit, the Northern Expansion Area, and the entire Area

  9. HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-03-01

    This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered

  10. HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered.

  11. Distribution of materials in construction and demolition waste in Portugal.

    Science.gov (United States)

    Coelho, André; de Brito, Jorge

    2011-08-01

    It may not be enough simply to know the global volume of construction and demolition waste (CDW) generated in a certain region or country if one wants to estimate, for instance, the revenue accruing from separating several types of materials from the input entering a given CDW recycling plant. A more detailed determination of the distribution of the materials within the generated CDW is needed and the present paper addresses this issue, distinguishing different buildings and types of operation (new construction, retrofitting and demolition). This has been achieved by measuring the materials from buildings of different ages within the Portuguese building stock, and by using direct data from demolition/retrofitting sites and new construction average values reported in the literature. An attempt to establish a benchmark with other countries is also presented. This knowledge may also benefit industry management, especially that related to CDW recycling, helping to optimize procedures, equipment size and operation and even industrial plant spatial distribution. In an extremely competitive market, where as in Portugal low-tech and high environmental impact procedures remain the norm in the construction industry (in particular, the construction waste industry), the introduction of a successful recycling industry is only possible with highly optimized processes and based on a knowledge-based approach to problems.

  12. Site-Wide Integrated Water Monitoring - Defining and Implementing Sampling Objectives to Support Site Closure - 13060

    International Nuclear Information System (INIS)

    Wilborn, Bill; Knapp, Kathryn; Farnham, Irene; Marutzky, Sam

    2013-01-01

    The Underground Test Area (UGTA) activity is responsible for assessing and evaluating the effects of the underground nuclear weapons tests on groundwater at the Nevada National Security Site (NNSS), formerly the Nevada Test Site (NTS), and implementing a corrective action closure strategy. The UGTA strategy is based on a combination of characterization, modeling studies, monitoring, and institutional controls (i.e., monitored natural attenuation). The closure strategy verifies through appropriate monitoring activities that contaminants of concern do not exceed the SDWA at the regulatory boundary and that adequate institutional controls are established and administered to ensure protection of the public. Other programs conducted at the NNSS supporting the environmental mission include the Routine Radiological Environmental Monitoring Program (RREMP), Waste Management, and the Infrastructure Program. Given the current programmatic and operational demands for various water-monitoring activities at the same locations, and the ever-increasing resource challenges, cooperative and collaborative approaches to conducting the work are necessary. For this reason, an integrated sampling plan is being developed by the UGTA activity to define sampling and analysis objectives, reduce duplication, eliminate unnecessary activities, and minimize costs. The sampling plan will ensure the right data sets are developed to support closure and efficient transition to long-term monitoring. The plan will include an integrated reporting mechanism for communicating results and integrating process improvements within the UGTA activity as well as between other U.S. Department of Energy (DOE) Programs. (authors)

  13. Closure Report for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2010-01-01

    Corrective Action Unit (CAU) 563 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Septic Systems' and consists of the following four Corrective Action Sites (CASs), located in Areas 3 and 12 of the Nevada Test Site: (1) CAS 03-04-02, Area 3 Subdock Septic Tank; (2) CAS 03-59-05, Area 3 Subdock Cesspool; (3) CAS 12-59-01, Drilling/Welding Shop Septic Tanks; and (4) CAS 12-60-01, Drilling/Welding Shop Outfalls Closure activities were conducted from September to November 2009 in accordance with the FFACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 563. The corrective action alternatives included No Further Action and Clean Closure.

  14. Closure Report for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-02-28

    Corrective Action Unit (CAU) 563 is identified in the Federal Facility Agreement and Consent Order (FFACO) as “Septic Systems” and consists of the following four Corrective Action Sites (CASs), located in Areas 3 and 12 of the Nevada Test Site: · CAS 03-04-02, Area 3 Subdock Septic Tank · CAS 03-59-05, Area 3 Subdock Cesspool · CAS 12-59-01, Drilling/Welding Shop Septic Tanks · CAS 12-60-01, Drilling/Welding Shop Outfalls Closure activities were conducted from September to November 2009 in accordance with the FFACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 563. The corrective action alternatives included No Further Action and Clean Closure.

  15. Large-Scale Residential Demolition

    Science.gov (United States)

    The EPA provides resources for handling residential demolitions or renovations. This includes planning, handling harmful materials, recycling, funding, compliance assistance, good practices and regulations.

  16. Facility Closure Report for Tunnel U16a, Area 16, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2009-01-01

    U16a is not listed in the Federal Facility Agreement and Consent Order. The closure of U16a was sponsored by the Defense Threat Reduction Agency (DTRA) and performed with the cooperation of the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office and the Nevada Division of Environmental Protection. This report documents closure of this site as identified in the DTRA Fiscal Year 2008 Statement of Work, Task 6.3. Closure activities included: (1) Removing and disposing of a shack and its contents; (2) Disposing of debris from within the shack and in the vicinity of the tunnel entrance; (3) Verifying that the tunnel is empty; (4) Welding screened covers over tunnel vent holes to limit access and allow ventilation; and (5) Constructing a full-tunnel cross-section fibercrete bulkhead to prevent access to the tunnel Field activities were conducted from July to August 2008.

  17. Progressively safer, cheaper demolition of Fernald

    International Nuclear Information System (INIS)

    Nichols, Robert; Pennington, Norman

    2000-01-01

    , which uses gasoline instead of acetylene gas, and a vacuum system for asbestos removal of wall insulation. These new methods proved effective and beneficial. Fluor Fernald has integrated demolition activities with waste disposal requirements to enhance overall efficiency. The relatively straight steel configurations required for recycling, and waste acceptance criteria that dictate waste sizes are typically included in the subcontract specifications The progressive improvements by Fluor Fernald have led to cost savings and schedule acceleration without increased risk to workers or the environment. When Fluor Fernald came to the site in 1992, the remediation baseline reflected a completion schedule of 2020 and a cost of $7.2 billion. The current projection is 2008 and $4.2 billion

  18. Closure report for CAU 93: Area 6 steam cleaning effluent ponds, Nevada Test Site. Volume 1

    International Nuclear Information System (INIS)

    1997-12-01

    The Steam Cleaning Effluent Ponds (SCEP) waste unit is located in Area 6 at the Nevada Test Site. The SCEPs are evaporation basins formerly used for the disposal of untreated liquid effluent discharged from steam cleaning activities associated with Buildings 6-623 and 6-800. This closure report documents the strategy and analytical results that support the clean closure or closure in place of each of the components within CAU 93. In addition, the report documents all deviations from the approved closure plan and provides rationale for all deviations

  19. M-area basin closure-Savannah River Site

    International Nuclear Information System (INIS)

    McMullin, S.R.; Horvath, J.G.

    1991-01-01

    M-Area, on the Savannah River Site, processes raw materials and manufactures fuel and target rods for reactor use. Effluent from these processes were discharged into the M-Area settling basin and Lost Lake, a natural wetland. The closure of this basin began in 1988 and included the removal and stabilization of basin fluids, excavation of all contaminated soils from affected areas and Lost Lake, and placement of all materials in the bottom of the emptied basin. These materials were covered with a RCRA style cap, employing redundant barriers of kaolin clay and geosynthetic material. Restoration of excavated uplands and wetlands is currently underway

  20. THE EFFECT OF VESSEL SUPPLY ON SHIP-DEMOLITION PRICES

    Directory of Open Access Journals (Sweden)

    Nikos Kagkarakis

    2017-02-01

    Full Text Available The ship-demolition is one of the four main markets that form the shipping industry and plays an important role on the seaborne trade, as it mitigates imbalances between supply and demand for transportation services by adjusting the merchant fleet supply. The aim of this study is to examine whether the factors that determine the supply of vessels for demolition are capable of affecting materially the ship-demolition price formation. The availability of ships for demolition is primarily a function of the fleet’s age and the conditions on the freight and secondhand markets. The analysis is conducted on the crude tanker and the bulk carrier segments and the vector autoregressive model methodology is employed, whereby the effect of both the supply and the demand factors on the ship-demolition prices is examined. The results indicate that the supply side has limited effect on the price formation in the industry, which is driven by the demand for the steel-scrap commodity.

  1. Closure Report for Corrective Action Unit 516: Septic Systems and Discharge Points, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 516 is located in Areas 3, 6, and 22 of the Nevada Test Site. CAU 516 is listed in the Federal Facility Agreement and Consent Order of 1996 as Septic Systems and Discharge Points, and is comprised of six Corrective Action Sites (CASs): (sm b ullet) CAS 03-59-01, Bldg 3C-36 Septic System (sm b ullet) CAS 03-59-02, Bldg 3C-45 Septic System (sm b ullet) CAS 06-51-01, Sump and Piping (sm b ullet) CAS 06-51-02, Clay Pipe and Debris (sm b ullet) CAS 06-51-03, Clean Out Box and Piping (sm b ullet) CAS 22-19-04, Vehicle Decontamination Area The Nevada Division of Environmental Protection (NDEP)-approved corrective action alternative for CASs 06-51-02 and 22-19-04 is no further action. The NDEP-approved corrective action alternative for CASs 03-59-01, 03-59-02, 06-51-01, and 06-51-03 is clean closure. Closure activities included removing and disposing of total petroleum hydrocarbon (TPH)-impacted septic tank contents, septic tanks, distribution/clean out boxes, and piping. CAU 516 was closed in accordance with the NDEP-approved CAU 516 Corrective Action Plan (CAP). The closure activities specified in the CAP were based on the recommendations presented in the CAU 516 Corrective Action Decision Document (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2004). This Closure Report documents CAU 516 closure activities. During closure activities, approximately 186 tons of hydrocarbon waste in the form of TPH-impacted soil and debris, as well as 89 tons of construction debris, were generated and managed and disposed of appropriately. Waste minimization techniques, such as field screening of soil samples and the utilization of laboratory analysis to characterize and classify waste streams, were employed during the performance of closure work

  2. Construction and demolition waste generation rates for high-rise buildings in Malaysia.

    Science.gov (United States)

    Mah, Chooi Mei; Fujiwara, Takeshi; Ho, Chin Siong

    2016-12-01

    Construction and demolition waste continues to sharply increase in step with the economic growth of less developed countries. Though the construction industry is large, it is composed of small firms with individual waste management practices, often leading to the deleterious environmental outcomes. Quantifying construction and demolition waste generation allows policy makers and stakeholders to understand the true internal and external costs of construction, providing a necessary foundation for waste management planning that may overcome deleterious environmental outcomes and may be both economically and environmentally optimal. This study offers a theoretical method for estimating the construction and demolition project waste generation rate by utilising available data, including waste disposal truck size and number, and waste volume and composition. This method is proposed as a less burdensome and more broadly applicable alternative, in contrast to waste estimation by on-site hand sorting and weighing. The developed method is applied to 11 projects across Malaysia as the case study. This study quantifies waste generation rate and illustrates the construction method in influencing the waste generation rate, estimating that the conventional construction method has a waste generation rate of 9.88 t 100 m -2 , the mixed-construction method has a waste generation rate of 3.29 t 100 m -2 , and demolition projects have a waste generation rate of 104.28 t 100 m -2 . © The Author(s) 2016.

  3. Buffer, backfill and closure process report for the safety assessment SR-Site

    International Nuclear Information System (INIS)

    Sellin, Patrik

    2010-11-01

    This report gives an account of how processes in buffer, deposition tunnel backfill and the closure important for the long-term evolution of a KBS-3 repository for spent nuclear fuel, will be documented in the safety assessment SR-Site

  4. Buffer, backfill and closure process report for the safety assessment SR-Site

    Energy Technology Data Exchange (ETDEWEB)

    Sellin, Patrik (ed.)

    2010-11-15

    This report gives an account of how processes in buffer, deposition tunnel backfill and the closure important for the long-term evolution of a KBS-3 repository for spent nuclear fuel, will be documented in the safety assessment SR-Site

  5. Closure Report for Corrective Action Unit 356: Mud Pits and Disposal Sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2002-01-01

    This Closure Report (CR) has been prepared for Corrective Action Unit (CAU) 356, Mud Pits and Disposal Sites, in accordance with the Federal Facility Agreement and Consent Order. This CAU is located in Areas 3 and 20 of the Nevada Test Site (NTS) approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 356 consists of seven Corrective Action Sites (CASs): 03-04-01, Area 3 Change House Septic System; 03-09-01, Mud Pit Spill Over; 03-09-03, Mud Pit; 03-09-04, Mud Pit; 03-09-05, Mud Pit; 20-16-01, Landfill; and 20-22-21, Drums. This CR identifies and rationalizes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office's (NNSA/NV's) recommendation that no further corrective action and closure in place is deemed necessary for CAU 356. This recommendation is based on the results of field investigation/closure activities conducted November 20, 2001, through January 3, 2002, and March 11 to 14, 2002. These activities were conducted in accordance with the Streamlined Approach for Environmental Restoration Plan (SAFER) for CAU 356. For CASs 03-09-01, 03-09-03, 20-16-01, and 22-20-21, analytes detected in soil during the corrective action investigation were evaluated against Preliminary Action Levels (PALs) and it was determined that no Contaminants of Concern (COCs) were present. Therefore, no further action is necessary for the soil at these CASs. For CASs 03-04-01, 03-09-04, and 03-09-05, analytes detected in soil during the corrective action investigation were evaluated against PALs and identifies total petroleum hydrocarbons (TPHs) and radionuclides (i.e., americium-241 and/or plutonium 239/240) as COCs. The nature, extent, and concentration of the TPH and radionuclide COCs were bounded by sampling and shown to be relatively immobile. Therefore, closure in place is recommended for these CASs in CAU 356. Further, use restrictions are not required at this CAU beyond the NTS use restrictions identified in

  6. Closure Report for Corrective Action Unit 465: Hydronuclear Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Mark Burmeister and Patrick Matthews

    2012-11-01

    The corrective action sites (CASs) within CAU 465 are located within Areas 6 and 27 of the NNSS. CAU 465 comprises the following CASs: • 00-23-01, Hydronuclear Experiment, located in Area 27 of the NNSS and known as the Charlie site. • 00-23-02, Hydronuclear Experiment, located in Area 27 of the NNSS and known as the Dog site. • 00-23-03, Hydronuclear Experiment, located in Area 27 of the NNSS and known as the Charlie Prime and Anja sites. • 06-99-01, Hydronuclear, located in Area 6 of the NNSS and known as the Trailer 13 site. The purpose of this CR is to provide documentation supporting the completed corrective actions and provide data confirming that the closure objectives for CASs within CAU 465 were met. From September 2011 through July 2012, closure activities were performed as set forth in the Streamlined Approach for Environmental Restoration Plan for CAU 465: Hydronuclear, Nevada National Security Site, Nevada.

  7. Integrated Closure and Monitoring Plan for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site

    International Nuclear Information System (INIS)

    Bechtel Nevada

    2005-01-01

    This document is an integrated plan for closing and monitoring two low-level radioactive waste disposal sites at the Nevada Test Site. This document is an integrated plan for closing and monitoring two low-level radioactive waste disposal sites at the Nevada Test Site (NTS). The Area 3 and Area 5 Radioactive Waste Management Sites (RWMSs) are managed and operated by Bechtel Nevada (BN) for the U.S. Department of Energy's (DOE's) National Nuclear Security Administration Nevada Site Office (NNSA/NSO). The Integrated Closure and Monitoring Plan (ICMP) for these sites is based on guidance for developing closure plans issued by the DOE (DOE, 1999a). The plan does not closely follow the format suggested by the DOE guidance to better accommodate differences between the two RWMSs, especially in terms of operations and site characteristics. The modification reduces redundancy and provides a smoother progression of the discussion. Further, much of the information that would be included in the individual plans is the same, and integration provides efficient presentation. A cross-walk between the contents of the ICMP and the DOE guidance is given in Appendix A. Closure and monitoring were integrated because monitoring measures the degree to which the operational and closed disposal facilities are meeting performance objectives specified in the manual to DOE Order O 435.1. Department of Energy Order 435.1 governs management of radioactive waste, and associated with it are Manual DOE M 435.1-1 and Guidance DOE G 435.1-1. The performance objectives are intended to ensure protection of workers, the public, and the environment from radiological exposure associated with the RWMSs now and in the future

  8. Corrective Action Decision Document/Closure Report for Corrective Action Unit 383: Area E-Tunnel Sites, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document/Closure Report (CADD/CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 383, Area 12 E-Tunnel Sites, which is the joint responsibility of DTRA and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense. Corrective Action Unit 383 is comprised of three Corrective Action Sites (CASs) and two adjacent areas: • CAS 12-06-06, Muckpile • CAS 12-25-02, Oil Spill • CAS 12-28-02, Radioactive Material • Drainage below the Muckpile • Ponds 1, 2, and 3 The purpose of this CADD/CR is to provide justification and documentation to support the recommendation for closure with no further corrective action, by placing use restrictions at the three CASs and two adjacent areas of CAU 383.

  9. CLOSURE REPORT FOR CORRECTIVE ACTION UNIT 115: AREA 25 TEST CELL A FACILITY, NEVADA TEST SITE, NEVADA

    International Nuclear Information System (INIS)

    2006-01-01

    This Closure Report (CR) describes the activities performed to close CAU 115, Area 25 Test Cell A Facility, as presented in the NDEP-approved SAFER Plan (NNSA/NSO, 2004). The SAFER Plan includes a summary of the site history, process knowledge, and closure standards. This CR provides a summary of the completed closure activities, documentation of waste disposal, and analytical and radiological data to confirm that the remediation goals were met and to document final site conditions. The approved closure alternative as presented in the SAFER Plan for CAU 115 (NNSA/NSO, 2004) was clean closure; however, closure in place was implemented under a Record of Technical Change (ROTC) to the SAFER Plan when radiological surveys indicated that the concrete reactor pad was radiologically activated and could not be decontaminated to meet free release levels. The ROTC is included as Appendix G of this report. The objectives of closure were to remove any trapped residual liquids and gases, dispose regulated and hazardous waste, decontaminate removable radiological contamination, demolish and dispose aboveground structures, remove the dewar as a best management practice (BMP), and characterize and restrict access to all remaining radiological contamination. Radiological contaminants of concern (COCs) included cobalt-60, cesium-137, strontium-90, uranium-234/235/236/238, and plutonium-239/240. Additional COCs included Resource Conservation and Recovery Act (RCRA) metals, polychlorinated biphenyls (PCBs), and asbestos

  10. Closure Report for Corrective Action Unit 566: EMAD Compound, Nevada National Security Site, Nevada with ROTC-1, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Mark Krauss

    2011-06-01

    This Closure Report (CR) presents information supporting the closure of Corrective Action Unit (CAU) 566: EMAD Compound, Nevada National Security Site, Nevada. Corrective Action Unit 566 comprises Corrective Action Site (CAS) 25-99-20, EMAD Compound, located within Area 25 of the Nevada National Security Site. The purpose of this CR is to provide documentation supporting the completed corrective actions and provide data confirming that the closure objectives for CAU 566 were met. To achieve this, the following actions were performed: • Review the current site conditions, including the concentration and extent of contamination. • Implement any corrective actions necessary to protect human health and the environment. • Properly dispose of corrective action and investigation wastes. • Document Notice of Completion and closure of CAU 566 issued by the Nevada Division of Environmental Protection. From October 2010 through May 2011, closure activities were performed as set forth in the Streamlined Approach for Environmental Restoration Plan for CAU 566: EMAD Compound, Nevada National Security Site, Nevada. The purposes of the activities as defined during the data quality objectives process were as follows: • Determine whether contaminants of concern (COCs) are present. • If COCs are present, determine their nature and extent, implement appropriate corrective actions, and properly dispose of wastes. Analytes detected during the closure activities were evaluated against final action levels (FALs) to determine COCs for CAU 566. Assessment of the data from collected soil samples, and from radiological and visual surveys of the site, indicates the FALs were exceeded for polychlorinated biphenyls (PCBs), semivolatile organic compounds (SVOCs), and radioactivity. Corrective actions were implemented to remove the following: • Radiologically contaminated soil assumed greater than FAL at two locations • Radiologically contaminated soil assumed greater than FAL with

  11. Closure Report for Corrective Action Unit 300: Surface Release Areas Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2007-07-01

    Corrective Action Unit (CAU) 300 is located in Areas 23, 25, and 26 of the Nevada Test Site, which is located approximately 65 miles northwest of Las Vegas, Nevada. CAU 300 is listed in the Federal Facility Agreement and Consent Order of 1996 as Surface Release Areas and is comprised of the following seven Corrective Action Sites (CASs), which are associated with the identified Building (Bldg): {sm_bullet} CAS 23-21-03, Bldg 750 Surface Discharge {sm_bullet} CAS 23-25-02, Bldg 750 Outfall {sm_bullet} CAS 23-25-03, Bldg 751 Outfall {sm_bullet} CAS 25-60-01, Bldg 3113A Outfall {sm_bullet} CAS 25-60-02, Bldg 3901 Outfall {sm_bullet} CAS 25-62-01, Bldg 3124 Contaminated Soil {sm_bullet} CAS 26-60-01, Bldg 2105 Outfall and Decon Pad The Nevada Division of Environmental Protection (NDEP)-approved corrective action alternative for CASs 23-21-03, 23-25-02, and 23-25-03 is no further action. As a best management practice, approximately 48 feet of metal piping was removed from CAS 23-25-02 and disposed of as sanitary waste. The NDEP-approved corrective action alternative for CASs 25-60-01, 25-60-02, 25-62-01, and 26-60-01, is clean closure. Closure activities for these CASs included removing and disposing of soil impacted with total petroleum hydrocarbons-diesel range organics (TPH-DRO), polychlorinated biphenyls (PCBs), semivolatile organic compounds (SVOCs), and cesium (Cs)-137, concrete impacted with TPH-DRO, and associated piping impacted with TPH-DRO. CAU 300 was closed in accordance with the NDEP-approved CAU 300 Corrective Action Plan (CAP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006). The closure activities specified in the CAP were based on the recommendations presented in the CAU 300 Corrective Action Decision Document (NNSA/NSO, 2005). This Closure Report documents CAU 300 closure activities. During closure activities, approximately 40 cubic yards (yd3) of low-level waste consisting of TPH-DRO-, PCB

  12. Management of construction and demolition wastes as secondary building resources

    Science.gov (United States)

    Manukhina, Lyubov; Ivanova, Irina

    2017-10-01

    The article analyzes the methods of management of construction and demolition wastes. The authors developed suggestions for improving the management system of the turnover of construction and demolition wastes. Today the issue of improving the management of construction and demolition wastes is of the same importance as problems of protecting the life-support field from pollution and of preserving biological and land resources. The authors educed the prospective directions and methods for improving the management of the turnover processes for construction and demolition wastes, including the evaluation of potential of wastes as secondary raw materials and the formation of a centralized waste management system.

  13. Ecologic assessment of closure options for Savannah River Plant waste sites: Task 38, AX-681812

    International Nuclear Information System (INIS)

    1987-01-01

    Ecologic assessment of closure options is one of several analyses being documented in the EIDs (along with analysis of relative potential health risks, accident risks, and costs). This information will serve as a basis for choosing the best option for closing a particular waste facility. This report presents the methodology adopted for SRP waste site ecological assessment, and the results of its application. The results of the ecologic assessment indicated that no impacts are expected for any of the closure options at eleven sites. Significant ecologic impacts are possible at the eight waste sites or groups of waste sites including the Radioactive Waste Burial Grounds, Old TNX Seepage Basin, CMP Pits, F-Area Seepage Basins, H-Area Seepage Basins, SRL Seepage Basins, R-Reactor Seepage Basins, and L-Area Oil and Chemical Basin. 104 refs., 22 figs., 241 tabs

  14. Closure plan for Corrective Action Unit 109: U-2bu subsidence crater, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1999-03-01

    The U-2bu subsidence crater, Corrective Action Unit 109, will be closed in accordance with the Resource Conservation and Recovery Act, the Nevada Division of Environmental Protection operational permit, and the Federal Facility Agreement and Consent Order. The U-2bu subsidence crater is located in Area 2 of the Nevada Test Site. It was created in 1971 by an underground nuclear test with the name Miniata. The crater has a diameter of 288 meters (944 feet) and an approximate depth of 35 meters (115 feet). Based on the results of the analyses reported in the site characterization report, the only constituents of concern in the U-2bu subsidence crater include leachable lead and total petroleum hydrocarbons. Closure activities will include the excavation and disposal of impacted soil from the top of the crater. Upon completion of excavation, verification samples will be collected to show that the leachable lead has been removed to concentrations below the regulatory action level. After sample results show that the lead has been removed, the excavated area will be backfilled and a soil flood diversion berm will be constructed as a best management practice. An independent registered professional engineer will certify the site was closed following the approved Closure Plan. Post-closure care is not warranted for this site because closure activities will involve removal of the Resource Conservation and Recovery Act constituents of concern

  15. Closure plan for Corrective Action Unit 109: U-2bu subsidence crater, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-03-01

    The U-2bu subsidence crater, Corrective Action Unit 109, will be closed in accordance with the Resource Conservation and Recovery Act, the Nevada Division of Environmental Protection operational permit, and the Federal Facility Agreement and Consent Order. The U-2bu subsidence crater is located in Area 2 of the Nevada Test Site. It was created in 1971 by an underground nuclear test with the name Miniata. The crater has a diameter of 288 meters (944 feet) and an approximate depth of 35 meters (115 feet). Based on the results of the analyses reported in the site characterization report, the only constituents of concern in the U-2bu subsidence crater include leachable lead and total petroleum hydrocarbons. Closure activities will include the excavation and disposal of impacted soil from the top of the crater. Upon completion of excavation, verification samples will be collected to show that the leachable lead has been removed to concentrations below the regulatory action level. After sample results show that the lead has been removed, the excavated area will be backfilled and a soil flood diversion berm will be constructed as a best management practice. An independent registered professional engineer will certify the site was closed following the approved Closure Plan. Post-closure care is not warranted for this site because closure activities will involve removal of the Resource Conservation and Recovery Act constituents of concern.

  16. Site closure and perpetual care of a low-level radioactive waste disposal facility in semi-arid climate

    International Nuclear Information System (INIS)

    Singh, P.N.; Breeden, K.H.; Hana, S.L.A.

    1988-01-01

    A study has been performed on site closure and perpetual care and maintenance requirements for the commercially operated low-level radioactive waste (LLRW) disposal facility, referred to as the Richland Facility, on the Hanford Reservation near Richland, Washington. The study included a site assessment and identification and formulation of site specific design elements for closure and perpetual care and maintenance. This paper summarizes the observations, findings and conclusions resulting from Phase I of this study. Three release mechanisms and four destructive processes are considered in the conceptual closure design process. The release mechanisms considered include subsurface liquid movement, biological transport of wastes to the surface and subsurface gas movement. The destructive processes considered are wind erosion, biological penetration or damage of cover, vegetation destroying processes and subsidence and seismic activity. The closure design elements were developed with several key principles in mind. The primary goals were to prevent intrusion into, or exposure of, the waste; to prevent or minimize release from the trenches; to provide early warning of any release that should occur; and to provide definitive information as to whether or not any observed environmental contamination actually originated from the facility

  17. AREA COMPLETION STRATEGIES AT SAVANNAH RIVER SITE: CHARACTERIZATION FOR CLOSURE AND BEYOND

    International Nuclear Information System (INIS)

    Bagwell, L; Mark Amidon, M; Sadika Baladi, S

    2007-01-01

    During the first four decades of its 56 year existence, the Savannah River Site (SRS) was a key supplier of nuclear material for national defense. During the 1990s, the site's primary missions became waste site closure, environmental restoration, and deactivation and decommissioning (D and D) of remnant cold war apparatus. Since 1989, with the approval of State and Federal regulatory agencies and with the participation of interested stakeholders, SRS has implemented a final remedy for a majority of the more than 500 individual waste sites at the former nuclear materials complex. These waste sites range from small, inert rubble pits to large, heavy industrial areas and radioactive waste disposal grounds. The closure and final remediation of these waste sites mark significant progress toward achieving SRS's overarching goal of reducing or eliminating future environmental damage and human health threats. However, larger challenges remain. For example, what are appropriate and achievable end-states for decommissioned nuclear facilities? What environmental and human health risks are associated with these end-states? To answer these questions within the strictures of smaller budgets and accelerated schedules, SRS is implementing an ''area completion'' strategy that: (1) unites several discrete waste units into one conceptual model, (2) integrates historically disparate environmental characterization and D and D activities, (3) reduces the number of required regulatory documents, and (4) in some cases, compresses schedules for achieving a stakeholder-approved end-state

  18. AREA COMPLETION STRATEGIES AT SAVANNAH RIVER SITE: CHARACTERIZATION FOR CLOSURE AND BEYOND

    Energy Technology Data Exchange (ETDEWEB)

    Bagwell, L; Mark Amidon, M; Sadika Baladi, S

    2007-06-11

    During the first four decades of its 56 year existence, the Savannah River Site (SRS) was a key supplier of nuclear material for national defense. During the 1990s, the site's primary missions became waste site closure, environmental restoration, and deactivation and decommissioning (D&D) of remnant cold war apparatus. Since 1989, with the approval of State and Federal regulatory agencies and with the participation of interested stakeholders, SRS has implemented a final remedy for a majority of the more than 500 individual waste sites at the former nuclear materials complex. These waste sites range from small, inert rubble pits to large, heavy industrial areas and radioactive waste disposal grounds. The closure and final remediation of these waste sites mark significant progress toward achieving SRS's overarching goal of reducing or eliminating future environmental damage and human health threats. However, larger challenges remain. For example, what are appropriate and achievable end-states for decommissioned nuclear facilities? What environmental and human health risks are associated with these end-states? To answer these questions within the strictures of smaller budgets and accelerated schedules, SRS is implementing an ''area completion'' strategy that: (1) unites several discrete waste units into one conceptual model, (2) integrates historically disparate environmental characterization and D&D activities, (3) reduces the number of required regulatory documents, and (4) in some cases, compresses schedules for achieving a stakeholder-approved end-state.

  19. A data-driven analysis of energy balance closure across FLUXNET research sites: The role of landscape scale heterogeneity

    DEFF Research Database (Denmark)

    Stoy, Paul C.; Mauder, Matthias; Foken, Thomas

    2013-01-01

    approached 1. These results suggest that landscape-level heterogeneity in vegetation and topography cannot be ignored as a contributor to incomplete energy balance closure at the flux network level, although net radiation measurements, biological energy assimilation, unmeasured storage terms......The energy balance at most surface-atmosphere flux research sites remains unclosed. The mechanisms underlying the discrepancy between measured energy inputs and outputs across the global FLUXNET tower network are still under debate. Recent reviews have identified exchange processes and turbulent...... motions at large spatial and temporal scales in heterogeneous landscapes as the primary cause of the lack of energy balance closure at some intensively-researched sites, while unmeasured storage terms cannot be ruled out as a dominant contributor to the lack of energy balance closure at many other sites...

  20. Estimation of construction and demolition waste using waste generation rates in Chennai, India.

    Science.gov (United States)

    Ram, V G; Kalidindi, Satyanarayana N

    2017-06-01

    A large amount of construction and demolition waste is being generated owing to rapid urbanisation in Indian cities. A reliable estimate of construction and demolition waste generation is essential to create awareness about this stream of solid waste among the government bodies in India. However, the required data to estimate construction and demolition waste generation in India are unavailable or not explicitly documented. This study proposed an approach to estimate construction and demolition waste generation using waste generation rates and demonstrated it by estimating construction and demolition waste generation in Chennai city. The demolition waste generation rates of primary materials were determined through regression analysis using waste generation data from 45 case studies. Materials, such as wood, electrical wires, doors, windows and reinforcement steel, were found to be salvaged and sold on the secondary market. Concrete and masonry debris were dumped in either landfills or unauthorised places. The total quantity of construction and demolition debris generated in Chennai city in 2013 was estimated to be 1.14 million tonnes. The proportion of masonry debris was found to be 76% of the total quantity of demolition debris. Construction and demolition debris forms about 36% of the total solid waste generated in Chennai city. A gross underestimation of construction and demolition waste generation in some earlier studies in India has also been shown. The methodology proposed could be utilised by government bodies, policymakers and researchers to generate reliable estimates of construction and demolition waste in other developing countries facing similar challenges of limited data availability.

  1. Chronic lower respiratory diseases among demolition and cement workers

    DEFF Research Database (Denmark)

    Mølgaard, Ellen Fischer; Hannerz, Harald; Tüchsen, Finn

    2013-01-01

    To estimate standardised hospitalisation ratios (SHR) for chronic lower respiratory diseases among demolition and cement workers in Denmark, 1995-2009.......To estimate standardised hospitalisation ratios (SHR) for chronic lower respiratory diseases among demolition and cement workers in Denmark, 1995-2009....

  2. Corrective Action Decision Document/Closure Report for Corrective Action Unit 190: Contaminated Waste Sites, Nevada Test Site, Nevada, Revision 0

    International Nuclear Information System (INIS)

    Alfred Wickline

    2008-01-01

    This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit (CAU) 190, Contaminated Waste Sites, Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; U.S. Department of Energy, Environmental Management; U.S. Department of Defense; and DOE, Legacy Management (1996, as amended January 2007). Corrective Action Unit 190 is comprised of the following four corrective action sites (CASs): (1) 11-02-01, Underground Centrifuge; (2) 11-02-02, Drain Lines and Outfall; (3) 11-59-01, Tweezer Facility Septic System; (4) 14-23-01, LTU-6 Test Area The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation for closure of CAU 190 with no further corrective action. To achieve this, corrective action investigation (CAI) activities were performed from March 21 through June 26, 2007. All CAI activities were conducted as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 190: Contaminated Waste Sites, Nevada Test Site, Nevada (NNSA/NSO, 2006). The purpose of the CAI was to fulfill the following data needs as defined during the data quality objective process: (1) Determine whether contaminants of concern (COCs) are present. (2) If COCs are present, determine their nature and extent. (3) Provide sufficient information and data to complete appropriate corrective actions. The CAU 190 dataset from the investigation results was evaluated based on the data quality indicator parameters. This evaluation demonstrated the quality and acceptability of the dataset for use in fulfilling the data quality objective data needs

  3. Stripping demolition of concrete by applying electric current through reinforcing bars

    International Nuclear Information System (INIS)

    Nakagawa, Wahei; Kumegawa, Sadatsune

    1995-01-01

    The presence of reinforcing bars in reinforced concrete structures is an obstruction hindering the smooth progress of demolition works. The electric heating method is, on the other hand, a demolition technique of unique concept since it adopts the bars to help the demolition of reinforced concrete structures. This technique has the following advantages for demolition: 1) the more densely a structure is reinforced with bars, the greater is the effect of the electric heating, 2) demolition after heating produces little dust, and 3) electric heating of reinforcing bars causes no damage to the portions of concrete not subjected to electric current. The present paper describes the procedures and results of a series of experiments we conducted to verify the efficiency of the electric heating method. In this method, a low-voltage high-current is run through reinforcing bars existing in a concrete structure, inducing intense heat in the bars which in its turn brings about cracks in the surrounding concrete mass, facilitating secondary demolition by hammer picks or other means. The experiments were performed on full-scale biological shield wall mock-ups of a BWR and a small nuclear reactor. The experiments revealed that these excellent features of the electric heating method are worth utilizing in stripping demolition of radioactivated regions of biological shield walls in nuclear power plants. The electric heating method is currently being adopted and shows effective results in partial demolition works in diaphragm wall shafts where starting/arriving holes are to be fixed for shield machines without damaging surrounding portions. (author)

  4. Overview of the closure approach for the Hanford Site single-shell tank farm

    International Nuclear Information System (INIS)

    Smith, E.H.

    1991-09-01

    The disposal of chemical and radioactive waste stored within the single-shell tanks (SST) represents one of the most significant waste management problems at the Hanford Site. A comprehensive program has been established to obtain analytical data regarding the chemical and radiological constituents within these tanks. This information will be used to support the development of a supplemental environmental impact statement (SEIS) and ultimately to aid in the selection of a final disposal option. This paper discusses some of the technical options and major regulatory issues associated with SST waste retrieval and in situ waste treatment and disposal. Certain closure options and treatment technologies will require further development before they can be implemented or accepted as being useful. In addition, continued negotiations with the regulatory authorities will be required to determine the preferred closure option and the regulatory pathway to accommodate such closure

  5. 76 FR 35006 - Recovery Policy RP9523.4, Demolition of Private Structures

    Science.gov (United States)

    2011-06-15

    ...] Recovery Policy RP9523.4, Demolition of Private Structures AGENCY: Federal Emergency Management Agency, DHS... (FEMA) is accepting comments on Recovery Policy RP9523.4, Demolition of Private Structures. DATES... guidance in determining the eligibility of demolition of private structures under the provisions of the...

  6. Closure Report for Corrective Action Unit 300: Surface Release Areas Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 300 is located in Areas 23, 25, and 26 of the Nevada Test Site, which is located approximately 65 miles northwest of Las Vegas, Nevada. CAU 300 is listed in the Federal Facility Agreement and Consent Order of 1996 as Surface Release Areas and is comprised of the following seven Corrective Action Sites (CASs), which are associated with the identified Building (Bldg): (sm b ullet) CAS 23-21-03, Bldg 750 Surface Discharge (sm b ullet) CAS 23-25-02, Bldg 750 Outfall (sm b ullet) CAS 23-25-03, Bldg 751 Outfall (sm b ullet) CAS 25-60-01, Bldg 3113A Outfall (sm b ullet) CAS 25-60-02, Bldg 3901 Outfall (sm b ullet) CAS 25-62-01, Bldg 3124 Contaminated Soil (sm b ullet) CAS 26-60-01, Bldg 2105 Outfall and Decon Pad The Nevada Division of Environmental Protection (NDEP)-approved corrective action alternative for CASs 23-21-03, 23-25-02, and 23-25-03 is no further action. As a best management practice, approximately 48 feet of metal piping was removed from CAS 23-25-02 and disposed of as sanitary waste. The NDEP-approved corrective action alternative for CASs 25-60-01, 25-60-02, 25-62-01, and 26-60-01, is clean closure. Closure activities for these CASs included removing and disposing of soil impacted with total petroleum hydrocarbons-diesel range organics (TPH-DRO), polychlorinated biphenyls (PCBs), semivolatile organic compounds (SVOCs), and cesium (Cs)-137, concrete impacted with TPH-DRO, and associated piping impacted with TPH-DRO. CAU 300 was closed in accordance with the NDEP-approved CAU 300 Corrective Action Plan (CAP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006). The closure activities specified in the CAP were based on the recommendations presented in the CAU 300 Corrective Action Decision Document (NNSA/NSO, 2005). This Closure Report documents CAU 300 closure activities. During closure activities, approximately 40 cubic yards (yd3) of low-level waste consisting of TPH

  7. Closure Report for Corrective Action Unit 568: Area 3 Plutonium Dispersion Sites Nevada National Security Site, Nevada, Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick [Navarro, Las Vegas, NV (United States)

    2017-06-01

    The purpose of this CR is to provide documentation and justification that no further corrective action is needed for the closure of CAU 568 based on the implementation of corrective actions. This includes a description of closure activities that were performed and an evaluation of the verification data. The CAP (NNSA/NFO, 2016a) and ROTC-1 (NNSA/NFO, 2016c) provide information relating to the selection of CAAs and the reasoning behind their selection. The CADD (NNSA/NFO, 2015) identifies the release sites that require additional corrective action and presents information supporting the selection of CAAs.

  8. Closure Report for Corrective Action Unit 151: Septic Systems and Discharge Area, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2008-01-01

    Corrective Action Unit (CAU) 151 is identified in the Federal Facility Agreement and Consent Order (FFACO) as Septic Systems and Discharge Area. CAU 151 consists of the following eight Corrective Action Sites (CASs), located in Areas 2, 12, and 18 of the Nevada Test Site, approximately 65 miles northwest of Las Vegas, Nevada: (1) CAS 02-05-01, UE-2ce Pond; (2) CAS 12-03-01, Sewage Lagoons (6); (3) CAS 12-04-01, Septic Tanks; (4) CAS 12-04-02, Septic Tanks; (5) CAS 12-04-03, Septic Tank; (6) CAS 12-47-01, Wastewater Pond; (7) CAS 18-03-01, Sewage Lagoon; and (8) CAS 18-99-09, Sewer Line (Exposed). CAU 151 closure activities were conducted according to the FFACO (FFACO, 1996; as amended February 2008) and the Corrective Action Plan for CAU 151 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007) from October 2007 to January 2008. The corrective action alternatives included no further action, clean closure, and closure in place with administrative controls. CAU 151 closure activities are summarized in Table 1. Closure activities generated liquid remediation waste, sanitary waste, hydrocarbon waste, and mixed waste. Waste generated was appropriately managed and disposed. Waste that is currently staged onsite is being appropriately managed and will be disposed under approved waste profiles in permitted landfills. Waste minimization activities included waste characterization sampling and segregation of waste streams. Some waste exceeded land disposal restriction limits and required offsite treatment prior to disposal. Other waste meeting land disposal restrictions was disposed of in appropriate onsite or offsite landfills. Waste disposition documentation is included as Appendix C

  9. Closure Report for Corrective Action Unit 151: Septic Systems and Discharge Area, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2008-04-01

    Corrective Action Unit (CAU) 151 is identified in the Federal Facility Agreement and Consent Order (FFACO) as Septic Systems and Discharge Area. CAU 151 consists of the following eight Corrective Action Sites (CASs), located in Areas 2, 12, and 18 of the Nevada Test Site, approximately 65 miles northwest of Las Vegas, Nevada: (1) CAS 02-05-01, UE-2ce Pond; (2) CAS 12-03-01, Sewage Lagoons (6); (3) CAS 12-04-01, Septic Tanks; (4) CAS 12-04-02, Septic Tanks; (5) CAS 12-04-03, Septic Tank; (6) CAS 12-47-01, Wastewater Pond; (7) CAS 18-03-01, Sewage Lagoon; and (8) CAS 18-99-09, Sewer Line (Exposed). CAU 151 closure activities were conducted according to the FFACO (FFACO, 1996; as amended February 2008) and the Corrective Action Plan for CAU 151 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007) from October 2007 to January 2008. The corrective action alternatives included no further action, clean closure, and closure in place with administrative controls. CAU 151 closure activities are summarized in Table 1. Closure activities generated liquid remediation waste, sanitary waste, hydrocarbon waste, and mixed waste. Waste generated was appropriately managed and disposed. Waste that is currently staged onsite is being appropriately managed and will be disposed under approved waste profiles in permitted landfills. Waste minimization activities included waste characterization sampling and segregation of waste streams. Some waste exceeded land disposal restriction limits and required offsite treatment prior to disposal. Other waste meeting land disposal restrictions was disposed of in appropriate onsite or offsite landfills. Waste disposition documentation is included as Appendix C.

  10. Concrete characterization for the 300 Area Solvent Evaporator Closure Site

    International Nuclear Information System (INIS)

    Prignano, A.L.

    1995-01-01

    This report summarizes the sampling activities undertaken and the analytical results obtained in a concrete sampling and analyses study performed for the 300 Area Solvent Evaporator (300 ASE) closure site. The 300 ASE is identified as a Resource Conservation and Recovery Act (RCRA) treatment, storage, or disposal (TSD) unit that will be closed in accordance with the applicable laws and regulations. No constituents of concern were found in concentrations indicating contamination of the concrete by 300 ASE operations

  11. Closure Report for Corrective Action Unit 481: Area 12 T-Tunnel Conditional Release Storage Yard, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2008-01-01

    Corrective Action Unit (CAU) 481 is identified in the Federal Facility Agreement and Consent Order (FFACO) as Area 12 T-Tunnel Conditional Release Storage Yard. CAU 481 is located in Area 12 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. This CAU consists of one Corrective Action Site (CAS), CAS 12-42-05, Housekeeping Waste. CAU 481 closure activities were conducted by the Defense Threat Reduction Agency from August 2007 through July 2008 according to the FFACO and Revision 3 of the Sectored Clean-up Work Plan for Housekeeping Category Waste Sites. Closure activities included removal and disposal of construction debris and low-level waste. Drained fluids, steel, and lead was recycled as appropriate. Waste generated during closure activities was appropriately managed and disposed.

  12. Development of closure criteria for inactive radioactive waste disposal sites at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Kocher, D.C.

    1989-01-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, specifies that cleanup of inactive waste disposal sites at Department of Energy (DOE) facilities shall at least attain legally applicable or relevant and appropriate requirements (ARARs) for cleanup or control of environmental contamination. This paper discusses potential ARARs for cleanup of inactive radioactive waste disposal sites and proposes a set of closure criteria for such sites at Oak Ridge National Laboratory (ORNL). The most important potential ARARs include Federal standards for radiation protection of the public, radioactivity in drinking water, and near-surface land disposal of radioactive wastes. On the basis of these standards, we propose that cleanup and closure of inactive radioactive waste disposal sites at ORNL shall achieve (1) limits on annual effective dose equivalent for off-site individuals and inadvertent intruders that conform to the DOE's performance objectives for new low-level waste disposal facilities and (2) to the extent reasonably achievable, limits on radionuclide concentrations in ground water and surface waters in accordance with Federal drinking water standards and ground-water protection requirements

  13. Cleanups In My Community (CIMC) - Base Realignment and Closure (BRAC) Superfund Sites, National Layer

    Data.gov (United States)

    U.S. Environmental Protection Agency — This data layer provides access to Base Realignment and Closure (BRAC) Superfund Sites as part of the CIMC web service. EPA works with DoD to facilitate the reuse...

  14. A RCRA clean closure of a unique site - Kerr Hollow quarry at the Y-12 Plant

    International Nuclear Information System (INIS)

    Stone, J.E.; Yemington, C.

    1991-01-01

    An abandoned rock quarry, Kerr Hollow Quarry (KHQ), near the DOE Oak Ridge Y-12 Plant, Oak Ridge, Tennessee, was used from 1951-1988 as a site to treat RCRA wastes which were reactive, corrosive, or ignitable and which posed major concerns for personnel safety. The wastes were generated from operations at the Y-12 Plant and Oak Ridge National Laboratory and were previously treated by allowing the wastes to react with the water in KHQ. When closure of the site was required by the RCRA regulations, a closure method was selected to allow for clean closure of the quarry without treatment or removal of the water in KHQ. The method proposed to and approved by the Tennessee Department of Health and Environment (TDHE) was one of surveying the containers in the quarry by a submersible Remotely Operated Vehicle (ROV) using sonar and visually inspecting the containers by camera to confirm that all containers are breached and empty. Any container found intact would be breached to allow the contents to react with water and form non-hazardous residue. The progress of this unique type of closure is presented along with a summary of the problems encountered, planning activities, equipment utilized and other information about the closure. All work was done with remotely operated equipment. This work is being performed by Sonsub, Inc. This closure project showed the practicality and cost benefits of telerobotic systems for work on hazardous waste sites. In addition to the intangible benefit of reduced exposure of workers, insurance costs are much lower and efficiency is higher. Daily start-up time is reduced since there is no need to don protective suits or other gear. Productivity is higher since personnel work only in clean areas where they are not hampered by protective gear. Cleanup time at shift end is minimized since the remote equipment does not leave the hazardous area and personnel need not go through decontamination

  15. Closure Report for Corrective Action Unit 116: Area 25 Test Cell C Facility, Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2011-09-29

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 116, Area 25 Test Cell C Facility. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; the U.S. Department of Energy (DOE), Environmental Management; the U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996 [as amended March 2010]). CAU 116 consists of the following two Corrective Action Sites (CASs), located in Area 25 of the Nevada National Security Site: (1) CAS 25-23-20, Nuclear Furnace Piping and (2) CAS 25-41-05, Test Cell C Facility. CAS 25-41-05 consisted of Building 3210 and the attached concrete shield wall. CAS 25-23-20 consisted of the nuclear furnace piping and tanks. Closure activities began in January 2007 and were completed in August 2011. Activities were conducted according to Revision 1 of the Streamlined Approach for Environmental Restoration Plan for CAU 116 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2008). This CR provides documentation supporting the completed corrective actions and provides data confirming that closure objectives for CAU 116 were met. Site characterization data and process knowledge indicated that surface areas were radiologically contaminated above release limits and that regulated and/or hazardous wastes were present in the facility.

  16. Postwar City: Importance of Recycling Construction and Demolition Waste

    Science.gov (United States)

    Al-Qaraghuli, Hanan; Alsayed, Yaman; Almoghazy, Ali

    2017-10-01

    Wars and armed conflicts have heavy tolls on the built environment when they take place in cities. It is not only restricted to the actually fighting which destroys or damages buildings and infrastructure, but the damage and destruction inflicts its impacts way beyond the cessation of military actions. They can even have another impact through physical segregation of city quarters through walls and checkpoints that complicates, or even terminates, mobility of citizens, goods, and services in the post-war scenario. The accumulation of debris in the streets often impedes the processes of rescue, distribution of aid and services, and other forms of city life as well. Also, the amount of effort and energy needed to remove those residual materials to their final dumping sites divert a lot of urgently needed resources. In this paper, the components of construction and demolition waste found in post-war cities are to be discussed, relating each one to its origins and potential reuses. Then the issues related to the management of construction waste and demolition debris resulting from military actions are to be discussed. First, an outlook is to be given on the historical example of Berlin and how the city was severely damaged during World War II, and how the reconstruction of the city was aided in part by the reuse of demolition debris. Then two more recent examples will be given, the cities of Baghdad in Iraq, and Homs in Syria. In Baghdad, though major military actions have ceased but not all rubble is cleared out, some security structures in the form of concrete walls separate the cities into quarters and impede city life and lie around as poorly allocated resource needed for reconstruction. While in the case of Homs, and the wider Syrian context, major military operations are still raging, making more pressure on the resources needed for reconstruction. This recycling of demolition debris can bring economic and social stability through the conservation of resources

  17. Closure Report for Corrective Action Unit 254: Area 25, R-MAD Decontamination Facility, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    G. N. Doyle

    2002-02-01

    Corrective Action Unit (CAU) 254 is located in Area 25 of the Nevada Test Site (NTS), approximately 100 kilometers (km) (62 miles) northwest of Las Vegas, Nevada. The site is located within the Reactor Maintenance, Assembly and Disassembly (R-MAD) compound and consists of Building 3126, two outdoor decontamination pads, and surrounding areas within an existing fenced area measuring approximately 50 x 37 meters (160 x 120 feet). The site was used from the early 1960s to the early 1970s as part of the Nuclear Rocket Development Station program to decontaminate test-car hardware and tooling. The site was reactivated in the early 1980s to decontaminate a radiologically contaminated military tank. This Closure Report (CR) describes the closure activities performed to allow un-restricted release of the R-MAD Decontamination Facility.

  18. Corrective Action Decision Document/Closure Report for Corrective Action Unit 570: Area 9 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick [Navarro-Intera, LLC (N-I), Las Vegas, NV (United States)

    2013-11-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 570: Area 9 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada. This complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. The purpose of the CADD/CR is to provide justification and documentation supporting the recommendation that no further corrective action is needed.

  19. Closure Report for Corrective Action Unit 124, Storage Tanks, Nevada Test Site, Nevada with Errata Sheet, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Alfred Wickline

    2008-01-01

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 124, Storage Tanks, Nevada Test Site (NTS), Nevada. This report complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996; as amended January 2007). This CR provides documentation and justification for the closure of CAU 124 without further corrective action. This justification is based on process knowledge and the results of the investigative activities conducted in accordance with the Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 124: Storage Tanks, Nevada Test Site, Nevada (NNSA/NSO, 2007). The SAFER Plan provides information relating to site history as well as the scope and planning of the investigation. Therefore, this information will not be repeated in this CR.

  20. CLOSURE REPORT FOR CORRECTIVE ACTION UNIT 165: AREA 25 AND 26 DRY WELL AND WASH DOWN AREAS, NEVADA TEST SITE, NEVADA

    International Nuclear Information System (INIS)

    BECHTEL NEVADA

    2005-01-01

    This Closure Report (CR) documents the closure activities for Corrective Action Unit (CAU) 165, Area 25 and 26 Dry Well and Washdown Areas, according to the Federal Facility Agreement and Consent Order (FFACO) of 1996. CAU 165 consists of 8 Corrective Action Sites (CASs) located in Areas 25 and 26 of the Nevada Test Site (NTS). The NTS is located approximately 105 kilometers (65 miles) northwest of Las Vegas, nevada. Site closure activities were performed according to the Nevada Division of Environmental Protection (NDEP)-approved Corrective Action Plan (CAP) for CAU 165. CAU 165 consists of the following CASs: (1) CAS 25-07-06, Train Decontamination Area; (2) CAS 25-07-07, Vehicle Washdown; (3) CAS 25-20-01, Lab Drain Dry Well; (4) CAS 25-47-01, Reservoir and French Drain; (5) CAS 25-51-02, Drywell; (6) CAS 25-59-01, Septic System; (7) CAS 26-07-01, Vehicle Washdown Station; and (8) CAS 26-59-01, Septic System. CAU 165, Area 25 and 26 Dry Well and Washdown Areas, consists of eight CASs located in Areas 25 and 26 of the NTS. The approved closure alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls

  1. CLOSURE REPORT FOR CORRECTIVE ACTION UNIT165: AREA 25 AND 26 DRY WELL AND WASH DOWN AREAS, NEVADA TEST SITE, NEVADA

    Energy Technology Data Exchange (ETDEWEB)

    BECHTEL NEVADA

    2005-12-01

    This Closure Report (CR) documents the closure activities for Corrective Action Unit (CAU) 165, Area 25 and 26 Dry Well and Washdown Areas, according to the Federal Facility Agreement and Consent Order (FFACO) of 1996. CAU 165 consists of 8 Corrective Action Sites (CASs) located in Areas 25 and 26 of the Nevada Test Site (NTS). The NTS is located approximately 105 kilometers (65 miles) northwest of Las Vegas, nevada. Site closure activities were performed according to the Nevada Division of Environmental Protection (NDEP)-approved Corrective Action Plan (CAP) for CAU 165. CAU 165 consists of the following CASs: (1) CAS 25-07-06, Train Decontamination Area; (2) CAS 25-07-07, Vehicle Washdown; (3) CAS 25-20-01, Lab Drain Dry Well; (4) CAS 25-47-01, Reservoir and French Drain; (5) CAS 25-51-02, Drywell; (6) CAS 25-59-01, Septic System; (7) CAS 26-07-01, Vehicle Washdown Station; and (8) CAS 26-59-01, Septic System. CAU 165, Area 25 and 26 Dry Well and Washdown Areas, consists of eight CASs located in Areas 25 and 26 of the NTS. The approved closure alternatives included No Further Action, Clean Closure, and Closure in Place with Administrative Controls.

  2. Demolition of one of the old barracks

    CERN Multimedia

    2002-01-01

    Many people at CERN will no doubt remember having rented accommodation in the four barracks-type huts near Entrance A. The rates were certainly rock bottom but it was hardly the Ritz! Put up at the end of the 1950s, they were abandoned in favour of the Saint-Genis-Pouilly hostel and the Meyrin site hostels. As they no longer meet current safety standards, they will all ultimately have to be demolished. One of them, situated immediately below the HV power line, has just been demolished at the request of the Swiss electricity company Energie Ouest Suisse. With its demolition, a little piece of CERN's social history has gone for ever.

  3. Mercury-Containing Devices and Demolition

    Science.gov (United States)

    Some items inside residential buildings contain mercury, which poses a persistent and toxic human health and environmental threat. These materials should be carefully salvaged for proper recycling to prevent mercury contamination prior to demolition.

  4. Closure Report for Corrective Action Unit 574: Neptune, Nevada National Security Site, Nevada

    International Nuclear Information System (INIS)

    2012-01-01

    Corrective Action Unit (CAU) 574 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Neptune' and consists of the following two Corrective Action Sites (CASs), located in Area 12 of the Nevada National Security Site: (1) CAS 12-23-10, U12c.03 Crater (Neptune); and (2) CAS 12-45-01, U12e.05 Crater (Blanca). This Closure Report presents information supporting closure of CAU 574 according to the FFACO (FFACO, 1996 [as amended March 2010]) and the Streamlined Approach for Environmental Restoration Plan for CAU 574 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2011). The following activities were performed to support closure of CAU 574: (1) In situ external dose rate measurements were collected using thermoluminescent dosimeters at CAS 12-45-01, U12e.05 Crater (Blanca). (2) Total effective dose rates were determined at both sites by summing the internal and external dose rate components. (3) A use restriction (UR) was implemented at CAS 12-23-10, U12c.03 Crater (Neptune). Areas that exceed the final action level (FAL) of 25 millirems per year (mrem/yr) based on the Occasional Use Area exposure scenario are within the existing use restricted area for CAU 551. The 25-mrem/yr FAL is not exceeded outside the existing CAU 551 UR for any of the exposure scenarios (Industrial Area, Remote Work Area, and Occasional Use Area). Therefore, the existing UR for CAU 551 is sufficient to bound contamination that exceeds the FAL. (4) An administrative UR was implemented at CAS 12-45-01, U12e.05 Crater (Blanca) as a best management practice (BMP). The 25-mrem/yr FAL was not exceeded for the Remote Work Area or Occasional Use Area exposure scenarios; therefore, a UR is not required. However, because the 25-mrem/yr FAL was exceeded for the Industrial Area exposure scenario, an administrative UR was established as a BMP. UR documentation is included as Appendix B. The UR at CAS 12-23-10, U12c.03 Crater (Neptune

  5. Closure Report for Corrective Action Unit 118: Area 27 Super Kukla Facility, Nevada Test Site, Nevada, Revision 0

    International Nuclear Information System (INIS)

    Mark Burmeister

    2007-01-01

    This CR provides documentation and justification for the closure of CAU 118 without further corrective action. This justification is based on process knowledge and the results of the investigative and closure activities conducted in accordance with the CAU 118 SAFER Plan: Streamlined Approach for Environmental Restoration (SAFER) Plan for CAU 118: Area 27 Super Kukla Facility, Nevada Test Site, Nevada (NNSA/NSO, 2006). The SAFER Plan provides information relating to site history as well as the scope and planning of the investigation. This CR also provides the analytical and radiological survey data to confirm that the remediation goals were met as specified in the CAU 118 SAFER Plan (NNSA/NSO, 2006). The Nevada Division of Environmental Protection (NDEP) approved the CAU 118 SAFER Plan (Murphy, 2006), which recommends closure in place with use restrictions (URs)

  6. Closure Report for Corrective Action Unit 224: Decon Pad and Septic Systems, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 224 is located in Areas 02, 03, 05, 06, 11, and 23 of the Nevada Test Site, which is situated approximately 65 miles northwest of Las Vegas, Nevada. CAU 224 is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 as Decon Pad and Septic Systems and is comprised of the following nine Corrective Action Sites (CASs): CAS 02-04-01, Septic Tank (Buried); CAS 03-05-01, Leachfield; CAS 05-04-01, Septic Tanks (4)/Discharge Area; CAS 06-03-01, Sewage Lagoons (3); CAS 06-05-01, Leachfield; CAS 06-17-04, Decon Pad and Wastewater Catch; CAS 06-23-01, Decon Pad Discharge Piping; CAS 11-04-01, Sewage Lagoon; and CAS 23-05-02, Leachfield. The Nevada Division of Environmental Protection (NDEP)-approved corrective action alternative for CASs 02-04-01, 03-05-01, 06-03-01, 11-04-01, and 23-05-02 is no further action. As a best management practice, the septic tanks and distribution box were removed from CASs 02-04-01 and 11-04-01 and disposed of as hydrocarbon waste. The NDEP-approved correction action alternative for CASs 05-04-01, 06-05-01, 06-17-04, and 06-23-01 is clean closure. Closure activities for these CASs included removing and disposing of radiologically and pesticide-impacted soil and debris. CAU 224 was closed in accordance with the NDEP-approved CAU 224 Corrective Action Plan (CAP). The closure activities specified in the CAP were based on the recommendations presented in the CAU 224 Corrective Action Decision Document (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2005). This Closure Report documents CAU 224 closure activities. During closure activities, approximately 60 cubic yards (yd3) of mixed waste in the form of soil and debris; approximately 70 yd 3 of sanitary waste in the form of soil, liquid from septic tanks, and concrete debris; approximately 10 yd 3 of hazardous waste in the form of pesticide-impacted soil; approximately 0.5 yd 3 of universal waste in the form of

  7. The Mixed Waste Management Facility closure and expansion at the Savannah River Site

    International Nuclear Information System (INIS)

    Bittner, M.F.; Frye-O'Bryant, R.C.

    1992-01-01

    Process wastes containing radioactive and hazardous constituents have been generated throughout the operational history of the Savannah River Site. Solid wastes containing low level radionuclides were buried in Low Level Radioactive Disposal Facility (LLRWDF). Until 1986, waste containing lead and cadmium was disposed of in the Mixed Waste Management Facility (MWMF) portion of LLRWDF. Between 1986 and 1990, waste containing F-listed hazardous rags were buried. Current Resource Conservation and Recovery Act (RCRA) regulations prohibit the disposal of these hazardous wastes at nonpermitted facilities. This paper describes the closure activities for the MWMF, completed in 1990 and plans proposed for the expansion of this closure to include the LLRWDF suspect solvent rag trenches

  8. Technology Assessment of Dust Suppression Techniques Applied During Structural Demolition. Topical Report August1, 1995 - October 30, 1996

    International Nuclear Information System (INIS)

    Boudreaux, J.F.; Ebadian, M.A.; Williams, P.T.; Dua, S.K.

    1998-01-01

    Hanford, Fernald, Savannah River, and other sites are currently reviewing technologies that can be implemented to demolish buildings in a cost-effective manner. In order to demolish a structure properly and, at the same time, minimize the amount of dust generated from a given technology, an evaluation must be conducted to choose the most appropriate dust suppression technology given site-specific conditions. Thus, the purpose of this research, which was carried out at the Hemispheric Center for Environmental Technology (HCET) at Florida International University, was to conduct an experimental study of dust aerosol abatement (dust suppression) methods as applied to nuclear D and D. This experimental study targeted the problem of dust suppression during the demolition of nuclear facilities. The resulting data were employed to assist in the development of mathematical correlations that can be applied to predict dust generation during structural demolition

  9. Assessment of different construction and demolition waste management approaches

    Directory of Open Access Journals (Sweden)

    Manal S. Abdelhamid

    2014-12-01

    Full Text Available The waste generated from construction and demolition sites is considered one of the most irritating problems in Egypt. In the last 10 years some effort has been made toward solving this problem, the most outstanding is the newly issued Egyptian rating system “Green Pyramids Rating System”. It emphasizes on waste management and particularly “site provision and environment” which contributes to 75% of the management category score. However the traditional practice which is limited to dumping all the generated waste is still dominating. The absence of sustainable practices in construction sector in Egypt led to the lack in financial and environmental data. From strategic perspective, the research aims at developing a detailed procedure to evaluate two construction and demolition waste management approaches by means of Decision Matrix technique. A detailed study is introduced for the two approaches; for each approach a flow chart is developed to demonstrate its lifecycle, as well as the cost break down structure and the different stakeholders’ roles. A penetration discussion of the pros and cons for each approach was developed accordingly and came out with sixteen influencing attributes for both approaches. The previous steps paved the ground to construct a Decision Matrix to decide on one of the approaches from a strategic environmentally oriented perspective. The study relied on the detailed and deep demonstration of the two approaches to justify the assigned weight for attributes and scores for corresponding approach. From a strategic perspective, the decision came out in favor of the more environmentally friendly approach.

  10. Occupancy estimation and the closure assumption

    Science.gov (United States)

    Rota, Christopher T.; Fletcher, Robert J.; Dorazio, Robert M.; Betts, Matthew G.

    2009-01-01

    1. Recent advances in occupancy estimation that adjust for imperfect detection have provided substantial improvements over traditional approaches and are receiving considerable use in applied ecology. To estimate and adjust for detectability, occupancy modelling requires multiple surveys at a site and requires the assumption of 'closure' between surveys, i.e. no changes in occupancy between surveys. Violations of this assumption could bias parameter estimates; however, little work has assessed model sensitivity to violations of this assumption or how commonly such violations occur in nature. 2. We apply a modelling procedure that can test for closure to two avian point-count data sets in Montana and New Hampshire, USA, that exemplify time-scales at which closure is often assumed. These data sets illustrate different sampling designs that allow testing for closure but are currently rarely employed in field investigations. Using a simulation study, we then evaluate the sensitivity of parameter estimates to changes in site occupancy and evaluate a power analysis developed for sampling designs that is aimed at limiting the likelihood of closure. 3. Application of our approach to point-count data indicates that habitats may frequently be open to changes in site occupancy at time-scales typical of many occupancy investigations, with 71% and 100% of species investigated in Montana and New Hampshire respectively, showing violation of closure across time periods of 3 weeks and 8 days respectively. 4. Simulations suggest that models assuming closure are sensitive to changes in occupancy. Power analyses further suggest that the modelling procedure we apply can effectively test for closure. 5. Synthesis and applications. Our demonstration that sites may be open to changes in site occupancy over time-scales typical of many occupancy investigations, combined with the sensitivity of models to violations of the closure assumption, highlights the importance of properly addressing

  11. Closure Report for Corrective Action Unit 553: Areas 19, 20 Mud Pits and Cellars, Nevada Test Site, Nevada, Revision 0

    International Nuclear Information System (INIS)

    Al Wickline

    2007-01-01

    This Closure Report (CR) presents information supporting the closure of Corrective Action Unit (CAU) 553: Areas 19, 20 Mud Pits and Cellars, Nevada Test Site, Nevada. This CR complies with the requirements of the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. The corrective action sites (CASs) within CAU 553 are located within Areas 19 and 20 of the Nevada Test Site. Corrective Action Unit 553 is comprised of the following CASs: 19-99-01, Mud Spill 19-99-11, Mud Spill 20-09-09, Mud Spill 20-99-03, Mud Spill. The purpose of this CR is to provide documentation supporting the completed corrective actions and provide data confirming that the closure objectives for CASs within CAU 553 were met. To achieve this, the following actions were or will be performed: Review the current site conditions including the concentration and extent of contamination. Implement any corrective actions necessary to protect human health and the environment. Properly dispose of corrective action and investigation wastes. Document the Notice of Completion and closure of CAU 553 to be issued by Nevada Division of Environmental Protection

  12. Radioactive waste disposal sites: Two successful closures at Tinker Air Force Base

    International Nuclear Information System (INIS)

    McKenzie, G.; Mohatt, J.V.; Kowall, S.J.; Jarvis, M.F.

    1993-06-01

    This article describes remediation and closure of two radioactive waste disposal sites at Tinker Air Force Base, Oklahoma, making them exemption regulatory control. The approach consisted of careful exhumation and assessment of soils in sites expected to be contaminated based on historical documentation, word of mouth, and geophysical surveys; removal of buried objects that had gamma radiation exposure levels above background; and confirmation that the soil containing residual radium-226 was below an activity level equal to no more than a 10 mrem/yr annual dose equivalent. In addition, 4464 kg of chemically contaminated excavated soils were removed for disposal. After remediation, the sites met standards for unrestricted use. These sites were two of the first three Air Force radioactive disposal sites to be closed and were the first to be closed under Draft NUREG/CR-5512

  13. Demolition wastes recycling; Reciclado de residuos de construccion y demolicion

    Energy Technology Data Exchange (ETDEWEB)

    Aguilar, A.; Monge, G. [INGURU Constructore, S.A. (Spain)

    1995-06-01

    This paper wants to show the up-to-date situation of demolition wastes from an international point of view. On the one hand it describes the different type of demolition wastes; on the other hand it explains the kind of treatment that is more adequate to each one. (Author)

  14. Closure Report for Corrective Action Unit 356: Mud Pits and Disposal Sites, Nevada Test Site, Nevada with Errata Sheet

    Energy Technology Data Exchange (ETDEWEB)

    NNSA/NV

    2002-11-12

    This Closure Report (CR) has been prepared for Corrective Action Unit (CAU) 356, Mud Pits and Disposal Sites, in accordance with the Federal Facility Agreement and Consent Order. This CAU is located in Areas 3 and 20 of the Nevada Test Site (NTS) approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 356 consists of seven Corrective Action Sites (CASs): 03-04-01, Area 3 Change House Septic System; 03-09-01, Mud Pit Spill Over; 03-09-03, Mud Pit; 03-09-04, Mud Pit; 03-09-05, Mud Pit; 20-16-01, Landfill; and 20-22-21, Drums. This CR identifies and rationalizes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office's (NNSA/NV's) recommendation that no further corrective action and closure in place is deemed necessary for CAU 356. This recommendation is based on the results of field investigation/closure activities conducted November 20, 2001, through January 3, 2002, and March 11 to 14, 2002. These activities were conducted in accordance with the Streamlined Approach for Environmental Restoration Plan (SAFER) for CAU 356. For CASs 03-09-01, 03-09-03, 20-16-01, and 22-20-21, analytes detected in soil during the corrective action investigation were evaluated against Preliminary Action Levels (PALs) and it was determined that no Contaminants of Concern (COCs) were present. Therefore, no further action is necessary for the soil at these CASs. For CASs 03-04-01, 03-09-04, and 03-09-05, analytes detected in soil during the corrective action investigation were evaluated against PALs and identifies total petroleum hydrocarbons (TPHs) and radionuclides (i.e., americium-241 and/or plutonium 239/240) as COCs. The nature, extent, and concentration of the TPH and radionuclide COCs were bounded by sampling and shown to be relatively immobile. Therefore, closure in place is recommended for these CASs in CAU 356. Further, use restrictions are not required at this CAU beyond the NTS use restrictions

  15. Post-Closure Inspection Report for Corrective Action Unit 90: Area 2 Bitcutter Containment, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    Corrective Action Unit (CAU) 90, Area 2 Bitcutter Containment, is identified in the ''Federal Facility Agreement and Consent Order'' of 1996. The post-closure requirements for CAU 90 are described in Section VII.B.8.b of the Nevada Test Site ''Resource Conservation and Recovery Act'' Permit for a Hazardous Waste Management Facility Number NEV HW0021, dated November 2005. Post-closure activities consist of the following: Semiannual inspections of the site using inspection checklists; Photographic documentation; Field note documentation; and Preparation and submittal of an annual Post-Closure Inspection Report. This annual report covers the period of July 2006 to June 2007 and consists of a summary of the results of the inspections, copies of the inspection checklists and field notes, maintenance and repair records (if any), photographs, and conclusions and recommendations. The inspection checklists are provided in Appendix A, a copy of the field notes is provided in Appendix B, and copies of photographs taken during the inspections are provided in Appendix C

  16. 22 CFR 121.11 - Military demolition blocks and blasting caps.

    Science.gov (United States)

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false Military demolition blocks and blasting caps... blasting caps. Military demolition blocks and blasting caps referred to in Category IV(a) do not include the following articles: (a) Electric squibs. (b) No. 6 and No. 8 blasting caps, including electric...

  17. Housekeeping Closure Report for Corrective Action Unit 463: Areas 2, 3, 9, and 25 Housekeeping Waste Sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1999-01-01

    The Federal Facility Agreement and Consent Order was entered into by the State of Nevada, U.S. Department of Energy, and U.S. Department of Defense to identify sites of potential historical contamination and implement corrective actions based on public health and environmental considerations. The facilities subject to this agreement include the Nevada Test Site (NTS), parts of the Tonopah Test Range, parts of the Nellis Air Force Range, the Central Nevada Test Area, and the Project Shoal Area. Corrective Action Sites (CASs) are areas potentially requiring corrective actions and may include solid waste management units, individual disposal, or release sites. Based on geography, technical similarity, agency responsibility, or other appropriate reasons, CASs are grouped together into Corrective Action Units (CAUs) for the purposes of determining corrective actions. This report contains the Closure Verification Forms for cleanup activities that were performed at 13 CASs within CAU 463 on the NTS. The Housekeeping Closure Verification Form for each CAS provides the location, directions to the site, general description, and photographs of the site before and after cleanup activities. Housekeeping activities at these sites included removal of debris (e.g., wooden pallets, metal, glass, and trash) and other material. In addition, these forms confirm prior removal of other contaminated materials such as metal drums or buckets, transformers, lead bricks, batteries, and gas cylinders. Based on these activities, no further action is required at these CASs

  18. Closure Report for Corrective Action Unit 330: Areas 6, 22, and 23 Tanks and Spill Sites, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    A. T. Urbon

    2003-07-01

    This Closure Report (CR) documents the activities performed to close Corrective Action Unit (CAU) 330: Areas 6, 22, and 23 Tanks and Spill Sites, in accordance with the Federal Facility Agreement and Consent Order (FFACO of 1996), and the Nevada Division of Environmental Protection (NDEP)-approved Streamlined Approach for Environmental Restoration (SAFER) Plan for CAU 330: Areas 6, 22, and 23 Tanks and Spill Sites, Nevada Test Site (NTS), Nevada (U.S. Department of Energy, National Nuclear Security Administration Nevada Operation Office [NNSA/NV], 2001). CAU 330 consists of the following four Corrective Action Sites (CASs): 06-02-04, 22-99-06, 23-01-02, and 23-25-05 (Figure 1).

  19. Corrective Action Decision Document/Closure Report for Corrective Action Unit 569: Area 3 Yucca Flat Atmospheric Test Sites Nevada National Security Site, Nevada with ROTC 1, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Sloop, Christy

    2013-04-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 569: Area 3 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada. CAU 569 comprises the following nine corrective action sites (CASs): • 03-23-09, T-3 Contamination Area • 03-23-10, T-3A Contamination Area • 03-23-11, T-3B Contamination Area • 03-23-12, T-3S Contamination Area • 03-23-13, T-3T Contamination Area • 03-23-14, T-3V Contamination Area • 03-23-15, S-3G Contamination Area • 03-23-16, S-3H Contamination Area • 03-23-21, Pike Contamination Area The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 569 based on the implementation of the corrective actions listed in Table ES-2.

  20. Tools for Closure Project and Contract Management: Development of the Rocky Flats Integrated Closure Project Baseline

    International Nuclear Information System (INIS)

    Gelles, C. M.; Sheppard, F. R.

    2002-01-01

    This paper details the development of the Rocky Flats Integrated Closure Project Baseline - an innovative project management effort undertaken to ensure proactive management of the Rocky Flats Closure Contract in support of the Department's goal for achieving the safe closure of the Rocky Flats Environmental Technology Site (RFETS) in December 2006. The accelerated closure of RFETS is one of the most prominent projects within the Department of Energy (DOE) Environmental Management program. As the first major former weapons plant to be remediated and closed, it is a first-of-kind effort requiring the resolution of multiple complex technical and institutional challenges. Most significantly, the closure of RFETS is dependent upon the shipment of all special nuclear material and wastes to other DOE sites. The Department is actively working to strengthen project management across programs, and there is increasing external interest in this progress. The development of the Rocky Flats Integrated Closure Project Baseline represents a groundbreaking and cooperative effort to formalize the management of such a complex project across multiple sites and organizations. It is original in both scope and process, however it provides a useful precedent for the other ongoing project management efforts within the Environmental Management program

  1. Post-Closure Inspection Report for Corrective Action Unit 90: Area 2 Bitcutter Containment, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2008-01-01

    Corrective Action Unit (CAU) 90, Area 2 Bitcutter Containment, is identified in the Federal Facility Agreement and Consent Order of 1996, as amended February 2008. The post-closure requirements for CAU 90 are described in Section VII.B.8.b of the Nevada Test Site Resource Conservation and Recovery Act Permit for a Hazardous Waste Management Facility Number NEV HW0021, dated November 2005. Post-closure activities consist of the following: (1) Semiannual inspections of the site using inspection checklists; (2) Photographic documentation; (3) Field note documentation; and (4) Preparation and submittal of an annual Post-Closure Inspection Report. This annual report covers the period of July 2007 to June 2008 and consists of a summary of the results of the inspections, copies of the inspection checklists and field notes, maintenance and repair records (if any), photographs, and conclusions and recommendations. The inspection checklists are provided in Appendix A, a copy of the field notes is provided in Appendix B, and copies of photographs taken during the inspections are provided in Appendix C

  2. Closure End States for Facilities, Waste Sites, and Subsurface Contamination - 12543

    Energy Technology Data Exchange (ETDEWEB)

    Gerdes, Kurt; Chamberlain, Grover; Whitehurst, Latrincy; Marble, Justin [Office of Groundwater and Soil Remediation, U.S. Department of Energy, Washington, DC 20585 (United States); Wellman, Dawn [Pacific Northwest National Laboratory, Richland, Washington 99352 (United States); Deeb, Rula; Hawley, Elisabeth [ARCADIS U.S., Inc., Emeryville, CA 94608 (United States)

    2012-07-01

    The United States (U.S.) Department of Energy (DOE) manages the largest groundwater and soil cleanup effort in the world. DOE's Office of Environmental Management (EM) has made significant progress in its restoration efforts at sites such as Fernald and Rocky Flats. However, remaining sites, such as Savannah River Site, Oak Ridge Site, Hanford Site, Los Alamos, Paducah Gaseous Diffusion Plant, Portsmouth Gaseous Diffusion Plant, and West Valley Demonstration Project possess the most complex challenges ever encountered by the technical community and represent a challenge that will face DOE for the next decade. Closure of the remaining 18 sites in the DOE EM Program requires remediation of 75 million cubic yards of contaminated soil and 1.7 trillion gallons of contaminated groundwater, deactivation and decommissioning (D and D) of over 3000 contaminated facilities and thousands of miles of contaminated piping, removal and disposition of millions of cubic yards of legacy materials, treatment of millions of gallons of high level tank waste and disposition of hundreds of contaminated tanks. The financial obligation required to remediate this volume of contaminated environment is estimated to cost more than 7% of the to-go life-cycle cost. Critical in meeting this goal within the current life-cycle cost projections is defining technically achievable end states that formally acknowledge that remedial goals will not be achieved for a long time and that residual contamination will be managed in the interim in ways that are protective of human health and environment. Formally acknowledging the long timeframe needed for remediation can be a basis for establishing common expectations for remedy performance, thereby minimizing the risk of re-evaluating the selected remedy at a later time. Once the expectations for long-term management are in place, remedial efforts can be directed towards near-term objectives (e.g., reducing the risk of exposure to residual contamination

  3. Streamlined approach for environmental restoration closure report for Corrective Action Unit 464: Historical underground storage tank release sites, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-04-01

    This report addresses the site characterization of two historical underground storage tank petroleum hydrocarbon release sites identified by Corrective Action Site (CAS) Numbers 02-02-03 and 09-02-01. The sites are located at the Nevada Test Site in Areas 2 and 9 and are concrete bunker complexes (Bunker 2-300, and 9-300). Characterization was completed using drilling equipment to delineate the extent of petroleum hydrocarbons at release site 2-300-1 (CAS 02-02-03). Based on site observations, the low hydrocarbon concentrations detected, and the delineation of the vertical and lateral extent of subsurface hydrocarbons, an ``A through K`` evaluation was completed to support a request for an Administrative Closure of the site.

  4. Streamlined approach for environmental restoration closure report for Corrective Action Unit 464: Historical underground storage tank release sites, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1998-04-01

    This report addresses the site characterization of two historical underground storage tank petroleum hydrocarbon release sites identified by Corrective Action Site (CAS) Numbers 02-02-03 and 09-02-01. The sites are located at the Nevada Test Site in Areas 2 and 9 and are concrete bunker complexes (Bunker 2-300, and 9-300). Characterization was completed using drilling equipment to delineate the extent of petroleum hydrocarbons at release site 2-300-1 (CAS 02-02-03). Based on site observations, the low hydrocarbon concentrations detected, and the delineation of the vertical and lateral extent of subsurface hydrocarbons, an ''A through K'' evaluation was completed to support a request for an Administrative Closure of the site

  5. Remaining Sites Verification Package for the 126-B-3, 184-B Coal Pit Dumping Area, Waste Site Reclassification Form 2005-028

    Energy Technology Data Exchange (ETDEWEB)

    L. M. Dittmer

    2006-08-07

    The 126-B-3 waste site is the former coal storage pit for the 184-B Powerhouse. During demolition operations in the 1970s, the site was used for disposal of demolition debris from 100-B/C Area facilities. The site has been remediated by removing debris and contaminated soils. The results of verification sampling demonstrated that residual contaminant concentrations do not preclude any future uses and allow for unrestricted use of shallow zone soils. The results also showed that residual contaminant concentrations are protective of groundwater and the Columbia River.

  6. Final closure plan for the high-explosives open burn treatment facility at Lawrence Livermore National Laboratory Experimental Test Site 300

    Energy Technology Data Exchange (ETDEWEB)

    Mathews, S.

    1997-04-01

    This document addresses the interim status closure of the HE Open Bum Treatment Facility, as detailed by Title 22, Division 4.5, Chapter 15, Article 7 of the Califonia Code of Regulations (CCR) and by Title 40, Code of Federal Regulations (CFR) Part 265, Subpart G, ``Closure and Post Closure.`` The Closure Plan (Chapter 1) and the Post- Closure Plan (Chapter 2) address the concept of long-term hazard elimination. The Closure Plan provides for capping and grading the HE Open Bum Treatment Facility and revegetating the immediate area in accordance with applicable requirements. The Closure Plan also reflects careful consideration of site location and topography, geologic and hydrologic factors, climate, cover characteristics, type and amount of wastes, and the potential for contaminant migration. The Post-Closure Plan is designed to allow LLNL to monitor the movement, if any, of pollutants from the treatment area. In addition, quarterly inspections will ensure that all surfaces of the closed facility, including the cover and diversion ditches, remain in good repair, thus precluding the potential for contaminant migration.

  7. Closure requirements

    International Nuclear Information System (INIS)

    Hutchinson, I.P.G.; Ellison, R.D.

    1992-01-01

    Closure of a waste management unit can be either permanent or temporary. Permanent closure may be due to: economic factors which make it uneconomical to mine the remaining minerals; depletion of mineral resources; physical site constraints that preclude further mining and beneficiation; environmental, regulatory or other requirements that make it uneconomical to continue to develop the resources. Temporary closure can occur for a period of several months to several years, and may be caused by factors such as: periods of high rainfall or snowfall which prevent mining and waste disposal; economic circumstances which temporarily make it uneconomical to mine the target mineral; labor problems requiring a cessation of operations for a period of time; construction activities that are required to upgrade project components such as the process facilities and waste management units; and mine or process plant failures that require extensive repairs. Permanent closure of a mine waste management unit involves the provision of durable surface containment features to protect the waters of the State in the long-term. Temporary closure may involve activities that range from ongoing maintenance of the existing facilities to the installation of several permanent closure features in order to reduce ongoing maintenance. This paper deals with the permanent closure features

  8. Femoral Artery Stenosis Following Percutaneous Closure Using a Starclose Closure Device

    International Nuclear Information System (INIS)

    Bent, Clare Louise; Kyriakides, Constantinos; Matson, Matthew

    2008-01-01

    Starclose (Abbott Vascular Devices, Redwood City, CA) is a new arterial closure device that seals a femoral puncture site with an extravascular star-shaped nitinol clip. The clip projects small tines into the arterial wall which fold inward, causing the arterial wall to pucker, producing a purse-string-like seal closing the puncture site. The case history is that of a 76-year-old female patient who underwent day-case percutaneous diagnostic coronary angiography. A Starclose femoral artery closure device was used to achieve hemostasis with subsequent femoral artery stenosis.

  9. Decommissioning and demolition in the European Union. Current status

    International Nuclear Information System (INIS)

    Blohm-Hieber, Ute

    2009-01-01

    The European Commission pursues the environmental and energy policy goals of limiting global warming to a maximum of 2 C and, therefore, reducing CO 2 emissions by at least 20%. Nuclear power, with its present 30% contribution to the Community's electricity supply and the low CO 2 emissions of the entire fuel cycle, makes an important contribution to an energy mix matching the 3 factors of competitiveness, security of supply, and sustainability. The decision to use nuclear power plants in their respective countries for electricity production is left to each member state. As of mid-2008, 146 nuclear power plants were in operation in the European Union, while 74 had been shut down permanently. Two nuclear power plants had been demolished completely, showing that the European Community is just at the beginning of the learning curve in this field. The importance of nuclear power plant decommissioning and demolition will increase in the future as replacement capacity in nuclear power generation will become necessary. The European Commission's activities in decommissioning and demolition date from the 1990s: The provisions about environmental impact assessment and the recommendations to apply Article 37 (potential impacts on water, soil and air) of the Euratom Treaty demand a description of decommissioning and demolition of nuclear power plants. In a ruling of 2002, the European Court of Justice assigns to the Community the required competences in the fields of nuclear safety and, consequently, also decommissioning and demolition. The financial provisions necessary for these activities are covered in the Electricity Directive within the framework of the rules for a common single market in 2003. After a first status report, the Commission published recommendations about financing decommissioning and demolition in 2006. (orig.)

  10. Feasibility study for the United Nuclear Corporation Disposal Site at the Oak Ridge Y-12 plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1991-02-01

    In July 1990, the US Environmental Protection Agency (EPA) directed the Department of Energy Oak Ridge Operations to comply with Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements for the remediation of the United Nuclear Corporation (UNC) Disposal Site located at the Y-12 Plant, Oak Ridge, Tennessee. EPA, Waste Management Branch, had approved a closure plan in December 1989 for the UNC Disposal Site. This feasibility study (FS) is a fully satisfy the National Oil and Hazardous Substances Contingency Plan (NCP) requirements for support of the selection of a remedial response for closure of the UNC Disposal Site. For two years the UNC Disposal Site accepted and disposed of waste from the decommissioning of a UNC uranium recovery facility in Wood River Junction, Rhode Island. Between June 1982 and November 1984, the UNC Disposal Site received 11,000 55-gal drums of sludge fixed in cement, 18,000 drums of contaminated soil, and 288 wooden boxes of contaminated building and process demolition materials. The FS assembles a wide range of remedial technologies so the most appropriate actions could be selected to remediate potential contamination to below MCLs and/or to below the maximum level of acceptable risk. Technologies were evaluated based on technical effectiveness, ease of implementation, and costs. Applicable technologies were then selected for alternative development. 33 refs., 9 figs., 27 tabs

  11. [Vacuum-assisted closure as a treatment modality for surgical site infection in cardiac surgery].

    Science.gov (United States)

    Simek, M; Nemec, P; Zálesák, B; Hájek, R; Kaláb, M; Fluger, I; Kolár, M; Jecmínková, L; Gráfová, P

    2007-08-01

    The vacuum-asssited closure has represented an encouraging treatment modality in treatment of surgical site infection in cardiac surgery, providing superior results compared with conventional treatment strategies, particularly in the treatment of deep sternal wound infection. From November 2004 to January 2007, 40 patients, undergoing VAC therapy (VAC system, KCI, Austria, Hartmann-Rico Inc., Czech Republic) for surgical site infection following cardiac surgery, were prospectively evaluated. Four patients (10%) were treated for extensive leg-wound infection, 10 (25%) were treated for superficial sternal wound infection and 26 (65%) for deep sternal wound infection. The median age was 69.9 +/- 9.7 years and the median BMI was 33.2 +/- 5.0 kg/m2. Twenty-three patients (57%) were women and diabetes was present in 22 patients (55%). The VAC was employed after the previous failure of the conventional treatment strategy in 7 patients (18%). Thirty-eight patients (95%) were successfully healed. Two patients (5%) died, both of deep sternal infetion consequences. The overall length of hospitalization was 36.4 +/- 22.6 days. The median number of dressing changes was 4.6 +/- 1.8. The median VAC treatment time until surgical closure was 9.7 +/- 3.9 days. The VAC therapy was solely used as a bridge to the definite wound closure. Four patients (10%) with a chronic fistula were re-admitted with the range of 1 to 12 months after the VAC therapy. The VAC therapy is a safe and reliable option in the treatment of surgical site infection in the field of cardiac surgery. The VAC therapy can be considered as an effective adjunct to convetional treatment modalities for the therapy of extensive and life-threatening wound infection following cardiac surgery, particurlarly in the group of high-risk patients.

  12. Forecasting of construction and demolition waste in Brazil.

    Science.gov (United States)

    Paz, Diogo Hf; Lafayette, Kalinny Pv

    2016-08-01

    The objective of this article is to develop a computerised tool (software) that facilitates the analysis of strategies for waste management on construction sites through the use of indicators of construction and demolition waste generation. The development involved the following steps: knowledge acquisition, structuring the system, coding and system evaluation. The step of knowledge acquisition aims to provide subsidies for the representation of them through models. In the step of structuring the system, it was presented the structuring and formalisation of knowledge for the development of the system, and has two stages: the construction of the conceptual model and the subsequent instantiation of the model. The coding system aims to implement (code) the conceptual model developed in a model played by computer (digital). The results showed that the system is very useful and applicable in construction sites, helping to improve the quality of waste management, and creating a database that will support new research. © The Author(s) 2016.

  13. ICPP tank farm closure study. Volume 2: Engineering design files

    International Nuclear Information System (INIS)

    1998-02-01

    Volume 2 contains the following topical sections: Tank farm heel flushing/pH adjustment; Grouting experiments for immobilization of tank farm heel; Savannah River high level waste tank 20 closure; Tank farm closure information; Clean closure of tank farm; Remediation issues; Remote demolition techniques; Decision concerning EIS for debris treatment facility; CERCLA/RCRA issues; Area of contamination determination; Containment building of debris treatment facility; Double containment issues; Characterization costs; Packaging and disposal options for the waste resulting from the total removal of the tank farm; Take-off calculations for the total removal of soils and structures at the tank farm; Vessel off-gas systems; Jet-grouted polymer and subsurface walls; Exposure calculations for total removal of tank farm; Recommended instrumentation during retrieval operations; High level waste tank concrete encasement evaluation; Recommended heavy equipment and sizing equipment for total removal activities; Tank buoyancy constraints; Grout and concrete formulas for tank heel solidification; Tank heel pH requirements; Tank cooling water; Evaluation of conservatism of vehicle loading on vaults; Typical vault dimensions and approximately tank and vault void volumes; Radiological concerns for temporary vessel off-gas system; Flushing calculations for tank heels; Grout lift depth analysis; Decontamination solution for waste transfer piping; Grout lift determination for filling tank and vault voids; sprung structure vendor data; Grout flow properties through a 2--4 inch pipe; Tank farm load limitations; NRC low level waste grout; Project data sheet calculations; Dose rates for tank farm closure tasks; Exposure and shielding calculations for grout lines; TFF radionuclide release rates; Documentation of the clean closure of a system with listed waste discharge; and Documentation of the ORNL method of radionuclide concentrations in tanks

  14. ICPP tank farm closure study. Volume 2: Engineering design files

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-02-01

    Volume 2 contains the following topical sections: Tank farm heel flushing/pH adjustment; Grouting experiments for immobilization of tank farm heel; Savannah River high level waste tank 20 closure; Tank farm closure information; Clean closure of tank farm; Remediation issues; Remote demolition techniques; Decision concerning EIS for debris treatment facility; CERCLA/RCRA issues; Area of contamination determination; Containment building of debris treatment facility; Double containment issues; Characterization costs; Packaging and disposal options for the waste resulting from the total removal of the tank farm; Take-off calculations for the total removal of soils and structures at the tank farm; Vessel off-gas systems; Jet-grouted polymer and subsurface walls; Exposure calculations for total removal of tank farm; Recommended instrumentation during retrieval operations; High level waste tank concrete encasement evaluation; Recommended heavy equipment and sizing equipment for total removal activities; Tank buoyancy constraints; Grout and concrete formulas for tank heel solidification; Tank heel pH requirements; Tank cooling water; Evaluation of conservatism of vehicle loading on vaults; Typical vault dimensions and approximately tank and vault void volumes; Radiological concerns for temporary vessel off-gas system; Flushing calculations for tank heels; Grout lift depth analysis; Decontamination solution for waste transfer piping; Grout lift determination for filling tank and vault voids; sprung structure vendor data; Grout flow properties through a 2--4 inch pipe; Tank farm load limitations; NRC low level waste grout; Project data sheet calculations; Dose rates for tank farm closure tasks; Exposure and shielding calculations for grout lines; TFF radionuclide release rates; Documentation of the clean closure of a system with listed waste discharge; and Documentation of the ORNL method of radionuclide concentrations in tanks.

  15. Roles of Historical Photography in Waste Site Characterization, Closure, and Remediation

    International Nuclear Information System (INIS)

    Mackey, H.

    1998-07-01

    Over 40,000 frames of vertical historical photography from 1938 to 1996 and over 10,000 frames of oblique photography from 1981 to 1991 of the 777-square kilometer Savannah River Site in south central South Carolina were reviewed, cataloged, and referenced utilizing ARCView and associated ArcInfo tools. This allows environmental reviews of over 400 potential waste units on the SRS to be conducted in a rapid fashion to support preparation of work plans, characterization, risk assessments, and closure of the waste units in a more cost effective manner

  16. Mixed Waste Management Facility closure at the Savannah River Site

    International Nuclear Information System (INIS)

    Bittner, M.F.

    1991-08-01

    The Mixed Waste Management Facility of the Savannah River Plant received hazardous and solid low level radioactive wastes from 1972 until 1986. Because this facility did not have a permit to receive hazardous wastes, a Resource Conservation and Recovery Act closure was performed between 1987 and 1990. This closure consisted of dynamic compaction of the waste trenches and placement of a 3-foot clay cap, a 2-foot soil cover, and a vegetative layer. Operations of the waste disposal facility, tests performed to complete the closure design, and the construction of the closure cap are discussed herein

  17. Closure Report for Corrective Action Unit 166: Storage Yards and Contaminated Materials, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2009-08-01

    Corrective Action Unit (CAU) 166 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Storage Yards and Contaminated Materials' and consists of the following seven Corrective Action Sites (CASs), located in Areas 2, 3, 5, and 18 of the Nevada Test Site: CAS 02-42-01, Condo Release Storage Yd - North; CAS 02-42-02, Condo Release Storage Yd - South; CAS 02-99-10, D-38 Storage Area; CAS 03-42-01, Conditional Release Storage Yard; CAS 05-19-02, Contaminated Soil and Drum; CAS 18-01-01, Aboveground Storage Tank; and CAS 18-99-03, Wax Piles/Oil Stain. Closure activities were conducted from March to July 2009 according to the FF ACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 166 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007b). The corrective action alternatives included No Further Action and Clean Closure. Closure activities are summarized. CAU 166, Storage Yards and Contaminated Materials, consists of seven CASs in Areas 2, 3, 5, and 18 of the NTS. The closure alternatives included No Further Action and Clean Closure. This CR provides a summary of completed closure activities, documentation of waste disposal, and confirmation that remediation goals were met. The following site closure activities were performed at CAU 166 as documented in this CR: (1) At CAS 02-99-10, D-38 Storage Area, approximately 40 gal of lead shot were removed and are currently pending treatment and disposal as MW, and approximately 50 small pieces of DU were removed and disposed as LLW. (2) At CAS 03-42-01, Conditional Release Storage Yard, approximately 7.5 yd{sup 3} of soil impacted with lead and Am-241 were removed and disposed as LLW. As a BMP, approximately 22 ft{sup 3} of asbestos tile were removed from a portable building and disposed as ALLW, approximately 55 gal of oil were drained from accumulators and are currently pending disposal as HW, the portable building was removed and

  18. Closure Report for Corrective Action Unit 166: Storage Yards and Contaminated Materials, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2009-01-01

    Corrective Action Unit (CAU) 166 is identified in the Federal Facility Agreement and Consent Order (FFACO) as 'Storage Yards and Contaminated Materials' and consists of the following seven Corrective Action Sites (CASs), located in Areas 2, 3, 5, and 18 of the Nevada Test Site: CAS 02-42-01, Condo Release Storage Yd - North; CAS 02-42-02, Condo Release Storage Yd - South; CAS 02-99-10, D-38 Storage Area; CAS 03-42-01, Conditional Release Storage Yard; CAS 05-19-02, Contaminated Soil and Drum; CAS 18-01-01, Aboveground Storage Tank; and CAS 18-99-03, Wax Piles/Oil Stain. Closure activities were conducted from March to July 2009 according to the FF ACO (1996, as amended February 2008) and the Corrective Action Plan for CAU 166 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, 2007b). The corrective action alternatives included No Further Action and Clean Closure. Closure activities are summarized. CAU 166, Storage Yards and Contaminated Materials, consists of seven CASs in Areas 2, 3, 5, and 18 of the NTS. The closure alternatives included No Further Action and Clean Closure. This CR provides a summary of completed closure activities, documentation of waste disposal, and confirmation that remediation goals were met. The following site closure activities were performed at CAU 166 as documented in this CR: (1) At CAS 02-99-10, D-38 Storage Area, approximately 40 gal of lead shot were removed and are currently pending treatment and disposal as MW, and approximately 50 small pieces of DU were removed and disposed as LLW. (2) At CAS 03-42-01, Conditional Release Storage Yard, approximately 7.5 yd 3 of soil impacted with lead and Am-241 were removed and disposed as LLW. As a BMP, approximately 22 ft 3 of asbestos tile were removed from a portable building and disposed as ALLW, approximately 55 gal of oil were drained from accumulators and are currently pending disposal as HW, the portable building was removed and disposed as LLW, and

  19. Choosing a sustainable demolition waste management strategy using multicriteria decision analysis

    International Nuclear Information System (INIS)

    Roussat, Nicolas; Dujet, Christiane; Mehu, Jacques

    2009-01-01

    This paper presents an application of the ELECTRE III decision-aid method in the context of choosing a sustainable demolition waste management strategy for a case study in the city of Lyon, France. This choice of waste management strategy takes into consideration the sustainable development objectives, i.e. economic aspects, environmental consequences, and social issues. Nine alternatives for demolition waste management were compared with the aid of eight criteria, taking into account energy consumption, depletion of abiotic resources, global warming, dispersion of dangerous substances in the environment, economic activity, employment, and quality of life of the local population. The case study concerned the demolition of 25 buildings of an old military camp. Each alternative was illustrated with different waste treatments, such as material recovery, recycling, landfilling, and energy recovery. The recommended solution for sustainable demolition waste management for the case study is a selective deconstruction of each building with local material recovery in road engineering of inert wastes, local energy recovery of wood wastes, and specific treatments for hazardous wastes

  20. Closure Report for Corrective Action Unit 539: Areas 25 and 26 Railroad Tracks Nevada National Security Site, Nevada, Revision 0

    International Nuclear Information System (INIS)

    Kauss, Mark

    2011-01-01

    This Closure Report (CR) presents information supporting the closure of Corrective Action Unit (CAU) 539: Areas 25 and 26 Railroad Tracks, Nevada National Security Site, Nevada. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. The corrective action sites (CASs) within CAU 539 are located within Areas 25 and 26 of the Nevada National Security Site. Corrective Action Unit 539 comprises the following CASs: (1) 25-99-21, Area 25 Railroad Tracks; and (2) 26-99-05, Area 26 Railroad Tracks The purpose of this CR is to provide documentation supporting the completed corrective actions and provide data confirming that the closure objectives for CASs within CAU 539 were met. To achieve this, the following actions were performed: (1) Reviewed documentation on historical and current site conditions, including the concentration and extent of contamination; (2) Conducted radiological walkover surveys of railroad tracks in both Areas 25 and 26; (3) Collected ballast and soil samples and calculated internal dose estimates for radiological releases; (4) Collected in situ thermoluminescent dosimeter measurements and calculated external dose estimates for radiological releases; (5) Removed lead bricks as potential source material (PSM) and collected verification samples; (6) Implemented corrective actions as necessary to protect human health and the environment; (7) Properly disposed of corrective action and investigation wastes; and (8) Implemented an FFACO use restriction (UR) for radiological contamination at CAS 25-99-21. The approved UR form and map are provided in Appendix F and will be filed in the DOE, National Nuclear Security Administration Nevada Site Office (NNSA/NSO), Facility Information Management System; the FFACO database; and the NNSA/NSO CAU/CAS files. From

  1. The effect of an engineered closure cap on radon gas transport from a shallow land burial site

    International Nuclear Information System (INIS)

    Lindstrom, F.T.; Cawlfield, D.E.; Donahue, M.E.; Emer, D.F.; Shott, G.J.

    1992-01-01

    US Department of Energy (DOE) Order 5820.2A requires performance assessment of all new and existing low level radioactive waste disposal sites. An integral part of performance assessment is estimating the fluxes of radioactive gases such as radon-220 and radon-222. Mathematical models, which in themselves point out data needs and therefore drive site characterization, provide a logical means of performing the required flux estimations. The effects of an engineered closure cap on radon gas transport in a very dry alluvial soil in the southwestern desert are considered in detail in this paper. Our model (Lindstrom, et al. 1992 a ampersand b and Cawlfield et al. 1992 a ampersand b) was constructed in a site specific fashion because the existing mathematical models of noble gas transport from the spatial point of origin in the low level waste repository through the surrounding soil and closure cap with subsequent release to the atmosphere are few in numbers (Nazaroff, 1992)

  2. Remaining Sites Verification Package for the 126-B-3, 184-B Coal Pit Dumping Area. Attachment to Waste Site Reclassification Form 2005-028

    International Nuclear Information System (INIS)

    Dittmer, L.M.

    2006-01-01

    The 126-B-3 waste site is the former coal storage pit for the 184-B Powerhouse. During demolition operations in the 1970s, the site was used for disposal of demolition debris from 100-B/C Area facilities. The site has been remediated by removing debris and contaminated soils. The results of verification sampling demonstrated that residual contaminant concentrations do not preclude any future uses and allow for unrestricted use of shallow zone soils. The results also showed that residual contaminant concentrations are protective of groundwater and the Columbia River

  3. Recycling the construction and demolition waste to produce polymer concrete

    Science.gov (United States)

    Hamza, Mohammad T.; Hameed, Awham M., Dr.

    2018-05-01

    The sustainable management for solid wastes of the construction and demolition waste stimulates searching for safety applications for these wastes. The aim of this research is recycling of construction and demolition waste with some different types of polymeric resins to be used in manufacturing process of polymer mortar or polymer concrete, and studying their mechanical and physical properties, and also Specify how the values of compressive strength and the density are affected via the different parameters. In this research two types of construction and demolition waste were used as aggregates replacement (i.e. waste cement/concrete debris, and the waste blocks) while the two types of polymer resins (i.e. Unsaturated polyester and Epoxy) as cement replacements. The used weight percentages of the resins were changed within (1°, 20, 25 and 30) % to manufacture this polymer concrete.

  4. Corrective Action Decision Document/Closure Report for Corrective Action Unit 137: Waste Disposal Sites, Nevada Test Site, Nevada (Revision 0) with ROTC 1 and 2

    Energy Technology Data Exchange (ETDEWEB)

    Krauss, Mark J

    2007-03-01

    The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation for closure of CAU 137 with no further corrective action. To achieve this, corrective action investigation (CAI) activities were performed from February 28 through August 17, 2006, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 137: Waste Disposal Sites. The purpose of the CAI was to fulfill the following data needs as defined during the data quality objective process: • Determine whether contaminants of concern (COCs) are present. • If COCs are present, determine their nature and extent. • Provide sufficient information and data to complete appropriate corrective actions. ROTC-1: Downgrade FFACO UR at CAU 137, CAS 07-23-02, Radioactive Waste Disposal Site to an Administrative UR. ROTC-2: Downgrade FFACO UR at CAU 137, CAS 01-08-01, Waste Disposal Site to an Administrative UR.

  5. Influence of construction and demolition waste management on the environmental impact of buildings

    International Nuclear Information System (INIS)

    Coelho, André; Brito, Jorge de

    2012-01-01

    Highlights: ► Environmental impacts of different demolition practices. ► “Top-down” approach to the Life Cycle Analysis methodology. ► Results based on real buildings measurements and demolition contractor activities. ► Not every type of selective demolition brings about environmental benefits. - Abstract: The purpose of this study is to quantify comparable environmental impacts within a Life Cycle Analysis (LCA) perspective, for buildings in which the first (Materials) and last (End of Life) life cycle stages are adjusted to several waste/material management options. Unlike most LCAs, the approach is “top-down” rather than “bottom-up”, which usually involves large amounts of data and the use of specific software applications. This approach is considered appropriate for a limited but expedient LCA designed to compare the environmental impacts of different life cycle options. Present results, based on real buildings measurements and demolition contractor activities, show that shallow, superficial, selective demolition may not result in reduced environmental impacts. Calculations actually show an increase (generally less than 5%) in most impact categories for the Materials and End of Life stages because of extra transportation needs. However, core material separation in demolition operations and its recycling and/or reuse does bring environmental benefits. A reduction of around 77% has been estimated in the climate change impact category, 57% in acidification potential and 81% in the summer smog impact (for the life cycle stages referred).

  6. Streamlined Approach for Environmental Restoration Closure Report for Corrective Action Unit 120: Areas 5 and 6 Aboveground Storage Tanks, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Allison Urban

    1999-06-01

    This Closure Report provides documentation for the closure of Corrective Action Unit 120. CAU 120 consists of two Corrective Action Sites located in Areas 5 and 6 of the Nevada Test Site. CAS 05-01-01 is located in Area 5 and consists of three 45,800-liter aboveground storage tanks, piping, and debris associated with Well RNM-1. CAS 06-01-01 in Area 6 consists of two aboveground storage tanks and two tanker trailers All the CAU 120 items have been used to convey or contain radiologically contaminated fluid from post-nuclear event activities at the NTS> Closure of this CAU was completed by collecting samples to identify the appropriate method of disposal for tanks, piping, debris, and tankers in each CAS. Placing low-level radioactive waste into the appropriate containers and disposing of waste in the Area 5 Radioactive Waste Management Site, the Area 9 10C Landfill, and the Area 3 Radioactive Waste Management Site.

  7. Streamlined Approach for Environmental Restoration Closure Report for Corrective Action Unit 120: Areas 5 and 6 Aboveground Storage Tanks, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Allison Urban

    1999-01-01

    This Closure Report provides documentation for the closure of Corrective Action Unit 120. CAU 120 consists of two Corrective Action Sites located in Areas 5 and 6 of the Nevada Test Site. CAS 05-01-01 is located in Area 5 and consists of three 45,800-liter aboveground storage tanks, piping, and debris associated with Well RNM-1. CAS 06-01-01 in Area 6 consists of two aboveground storage tanks and two tanker trailers All the CAU 120 items have been used to convey or contain radiologically contaminated fluid from post-nuclear event activities at the NTS> Closure of this CAU was completed by collecting samples to identify the appropriate method of disposal for tanks, piping, debris, and tankers in each CAS. Placing low-level radioactive waste into the appropriate containers and disposing of waste in the Area 5 Radioactive Waste Management Site, the Area 9 10C Landfill, and the Area 3 Radioactive Waste Management Site

  8. Area Completion Strategies at Savannah River Site: Characterization for Closure and Beyond

    International Nuclear Information System (INIS)

    Bagwell, Laura; O'Quinn, Sadika; Amidon, Mark

    2008-01-01

    During the first four decades of its 56 year existence, the Savannah River Site (SRS) was a key supplier of nuclear material for national defense. During the 1990's, the site's primary missions became waste site closure, environmental restoration, and deactivation and decommissioning (D and D) of remnant cold war apparatus. Since 1989, with the approval of State and Federal regulatory agencies and with the participation of interested stakeholders, SRS has implemented a final remedy for a majority of the more than 500 individual waste sites at the former nuclear materials complex. These waste sites range from small, inert rubble pits to large, heavy industrial areas and radioactive waste disposal grounds. The closure and final remediation of these waste sites mark significant progress toward achieving SRS's overarching goal of reducing or eliminating future environmental damage and human health threats. However, larger challenges remain. For example, what are appropriate and achievable end-states for decommissioned nuclear facilities? What environmental and human health risks are associated with these end-states? To answer these questions within the strictures of smaller budgets and accelerated schedules, SRS is implementing an 'area completion' strategy that: - unites several discrete waste units into one conceptual model, - integrates historically disparate environmental characterization and D and D activities - reduces the number of required regulatory documents, - and, in some cases, compresses schedules for achieving a stakeholder-approved end-state. The area completion approaches being implemented at SRS reflect an evolution of the traditional RCRA/ CERCLA remedial process. Area completion strategies: - group waste units and/or D and D facilities together for characterization, remediation, and possible reuse; - identify data needs and integrate data collection activities for D and D, characterization, and remediation; - identify problems that require action

  9. OPERATIONAL LIMITATIONS FOR DEMOLITION OF A HIGHLY ALPHA CONTAMINATED BUILDING MODLES VERSUS MEASURED AIR & SURFACE ACTIVITY CONCENTRATIONS

    Energy Technology Data Exchange (ETDEWEB)

    LLOYD, E.R.

    2006-11-02

    The demolition of a facility historically used for processing and handling transuranic materials is considered. Residual alpha emitting radionuclide contamination poses an exposure hazard if released to the local environment during the demolition. The process of planning for the demolition of this highly alpha contaminated building, 232-Z, included a predemolition modeling analysis of potential exposures. Estimated emission rates were used as input to an air dispersion model to estimate frequencies of occurrence of peak air and surface exposures. Postdemolition modeling was also conducted, based on the actual demolition schedule and conditions. The modeling results indicated that downwind deposition is the main operational limitation for demolition of a highly alpha-contaminated building. During the demolition of 232-Z, airborne radiation and surface contamination were monitored. The resultant non-detect monitoring results indicate a significant level of conservatism in the modeled results. This comparison supports the use of more realistic assumption in the estimating emission rates. The resultant reduction in modeled levels of potential exposures has significant implications in terms of the projected costs of demolition of such structures.

  10. Consideration of post-closure controls for a near surface low level waste disposal site

    International Nuclear Information System (INIS)

    Clegg, R.; Pinner, A.; Smith, A.; Quartermaine, J.

    1997-01-01

    There is currently an ongoing programme of disposal of low level radioactive wastes by British Nuclear Fuels plc (BNFL) at Drigg, Cumbria, and this programme is likely to continue through the first few decades of the 21st century. Although control of the site is anticipated for a period of about 100 years post-closure, eventually restrictions on access will lapse. Thereafter, the possibility of human actions leading to exposure to, and/or exhumation of, the wastes exists and has to be addressed in post-closure radiological performance assessments. Potential modes of intrusion into the Drigg site have been studied using a suite of computer codes developed specifically for this purpose. Required inputs to these codes include information on possible future uses of the site and the various human actions associated with those uses. This information was obtained from a group of experts using formal elicitation procedures. Although the most likely site uses, notably those involving agricultural activities, are unlikely to result in intrusion into the wastes, others, such a urban development, do have the potential to result in such intrusion. In these circumstances, it seemed appropriate to give consideration to the degree to which documentary records and markers could protect the Drigg site against intrusive activities. Overall, it is concluded that provided that a variety of documentary records are established, ranging from local council archives to mass produced maps, then memory of the site can realistically be assumed whilst civilization continues to exist. However, if this first line of defence fails, markers constitute a second warning system. Finally, assessment calculations can be used to demonstrate that, even if these two lines of defence fail, risks from intrusion and radiation doses contingent upon intrusive events having occurred would not be unacceptably large. (author). 10 refs, 1 fig., 1 tab

  11. Test program for closure activities at a mixed waste disposal site at the Savannah River Plant

    International Nuclear Information System (INIS)

    Cook, J.R.; Harley, J.P. Jr.

    1988-01-01

    A 58-acre site at the Savannah River Plant which was used for disposal of low-level radioactive waste and quantities of the hazardous materials lead, cadmium, scintillation fluid, and oil will be the first large waste site at the Savannah River Plant to be permanently closed. The actions leading to closure of the facility will include surface stabilization and capping of the site. Test programs have been conducted to evaluate the effectiveness of dynamic compaction as a stabilization technique and the feasibility of using locally derived clay as a capping material

  12. Closure Plan for Corrective Action Unit 109: U-2bu Subsidence Crater Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Shannon Parsons

    1999-03-01

    The U-2bu subsidence crater, Corrective Action Unit 109, will be closed in accordance with the Resource Conservation and Recovery Act, the Nevada Division of Environmental Protection operational permit, and the Federal Facilities Agreement and Consent Order. The U-2bu subsidence crater is located in Area 2 of the Nevada Test Site. It was created in 1971 by an underground nuclear test with the name Miniata. The crater has a diameter of 288 meters (944 feet) and an approximate depth of 35 meters (115 feet). The subsidence crater was used as a land disposal unit for radioactive and hazardous waste from 1973 to 1988. Site disposal history is supported by memorandums, letters, and personnel who worked at the Nevada Test Site at the time of active disposal. Closure activities will include the excavation and disposal of impacted soil form the tip of the crater. Upon completion of excavation, verification samples will be collected to show that lead has been removed to concentrations be low regulatory action level. The area will then be backfilled and a soil flood diversion berm will be constructed, and certified by an independent professional engineer as to having followed the approved Closure Plan.

  13. Closure Strategy for a Waste Disposal Facility with Multiple Waste Types and Regulatory Drivers at the Nevada Test Site - 8422

    International Nuclear Information System (INIS)

    D Wieland; V Yucel; L Desotell; G Shott; J Wrapp

    2008-01-01

    The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) plans to close the waste and classified material storage cells in the southeast quadrant of the Area 5 Radioactive Waste Management Site (RWMS), informally known as the '92-Acre Area', by 2011. The 25 shallow trenches and pits and the 13 Greater Confinement Disposal (GCD) borings contain various waste streams including low-level waste (LLW), low-level mixed waste (LLMW), transuranic (TRU), mixed transuranic (MTRU), and high specific activity LLW. The cells are managed under several regulatory and permit programs by the U.S. Department of Energy (DOE) and the Nevada Division of Environmental Protection (NDEP). Although the specific closure requirements for each cell vary, 37 closely spaced cells will be closed under a single integrated monolayer evapotranspirative (ET) final cover. One cell will be closed under a separate cover concurrently. The site setting and climate constrain transport pathways and are factors in the technical approach to closure and performance assessment. Successful implementation of the integrated closure plan requires excellent communication and coordination between NNSA/NSO and the regulators

  14. Demolition of the FRJ-1 research reactor (MERLIN)

    International Nuclear Information System (INIS)

    Stahn, B.; Matela, K.; Zehbe, C.; Poeppinghaus, J.; Cremer, J.

    2003-01-01

    FRJ-2 (MERLIN), the swimming pool reactor cooled and moderated by light water, was built at the then Juelich Nuclear Research Establishment (KFA) between 1958 and 1962. In the period between 1964 and 1985, it was used for. The reactor was decommissioned in 1985. Since 1996, most of the demolition work has been carried out under the leadership of a project team. The complete secondary cooling system was removed by late 1998. After the cooling loops and experimental installations had been taken out, the reactor vessel internals were removed in 2000 after the water had been drained from the reactor vessel. After the competent authority had granted a license, demolition of the reactor block, the central part of the research reactor, was begun in October 2001. In a first step, the reactor operating floor and the reactor attachment structures were removed by the GNS/SNT consortium charged with overall planning and execution of the job. This phase gave rise to approx. The reactor block proper is dismantled in a number of steps. A variety of proven cutting techniques are used for this purpose. Demolition of the reactor block is to be completed in the first half of 2003. (orig.) [de

  15. Streamlined approach for environmental restoration work plan for Corrective Action Unit 126: Closure of aboveground storage tanks, Nevada Test Site, Nevada. Revision 1

    International Nuclear Information System (INIS)

    1998-07-01

    This plan addresses the closure of several aboveground storage tanks in Area 25 of the Nevada Test Site. The unit is currently identified as Corrective Action Unit 126 in the Federal Facility Agreement and Consent Order and is listed as having six Corrective Action Sites. This plan addresses the Streamlined Approach for Environmental Restoration closure for five of the six sites. Four of the CASs are located at the Engine Test Stand complex and one is located in the Central Support Area. The sites consist of aboveground tanks, two of which were used to store diesel fuel and one stored Nalcool (an antifreeze mixture). The remaining tanks were used as part of a water demineralization process and stored either sulfuric acid or sodium hydroxide, and one was used as a charcoal adsorption furnace. Closure will be completed by removal of the associated piping, tank supports and tanks using a front end loader, backhoe, and/or crane. When possible, the tanks will be salvaged as scrap metal. The piping that is not removed will be sealed using a cement grout

  16. Corrective Action Decision Document/Closure Report for Corrective Action Unit 500: Test Cell A Septic System, Nevada Test Site, Nevada, Rev. 0

    International Nuclear Information System (INIS)

    2000-01-01

    This Corrective Action Decision Document/Closure Report (CADD/CR) has been prepared for Corrective Action Unit (CAU) 500: Test Cell A Septic System, in accordance with the Federal Facility Agreement and Consent Order. Located in Area 25 at the Nevada Test Site in Nevada, CAU 500 is comprised of one Corrective Action Site, CAS 25-04-05. This CADD/CR identifies and rationalizes the U.S. Department of Energy, Nevada Operations Office's (DOE/NV's) recommendation that no corrective action is deemed necessary for CAU 500. The Corrective Action Decision Document and Closure Report have been combined into one report based on sample data collected during the field investigation performed between February and May 1999, which showed no evidence of soil contamination at this site. The clean closure justification for CAU 500 is based on these results. Analytes detected were evaluated against preliminary action levels (PALs) to determine contaminants of concern (COCs) for CAU 500, and it was determined that the PALs were not exceeded for total volatile organic compounds, total semivolatile organic compounds, total petroleum hydrocarbons, polychlorinated biphenyls, total Resource Conservation and Recovery Act metals, gamma-emitting radionuclides, isotopic uranium, and strontium-90 for any of the soil samples collected. COCs were identified only within the septic tank and distribution box at the CAU. No COCs were identified outside these two areas; therefore, no corrective action was necessary for the soil. Closure activities were performed to address the COCs identified within the septic tank and distribution box. The DOE/NV recommended that neither corrective action nor a corrective action plan was required at CAU 500. Further, no use restrictions were required to be placed on CAU 500, and the septic tank and distribution box have been closed in accordance with all applicable state and federal regulations for closure of the site

  17. Pilot-based assessment of the economics of recycling construction demolition waste.

    Science.gov (United States)

    Srour, Issam M; Chehab, Ghassan R; El-Fadel, Mutasem; Tamraz, Sandy

    2013-11-01

    The significant amount of waste generated from construction demolition has become a chronic problem in many developing countries. Using data obtained from demolition contractors and various other sources, this paper proposes a framework for proper handling of construction demolition waste (CDW) to serve as a decision support tool in countries suffering from the lack of national CDW management guidelines. The framework is then demonstrated through a case study in the city of Beirut, Lebanon, and a sensitivity analysis is carried out to examine the economic feasibility of developing a recycling facility. The analysis showed that in order for a facility to be feasible, a gate fee should be charged in the presence of a market for recycled aggregates. The results confirm the significance of instigating and implementing legislation to control illegal dumping, constructing, and managing engineered landfills, and establishing markets for recycled CDW.

  18. Title I conceptual design for Pit 6 landfill closure at Lawrence Livermore National Laboratory Site 300

    International Nuclear Information System (INIS)

    MacDonnell, B.A.; Obenauf, K.S.

    1996-08-01

    The objective of this design project is to evaluate and prepare design and construction documents for a closure cover cap for the Pit 6 Landfill located at Lawrence Livermore National Laboratory Site 300. This submittal constitutes the Title I Design (Conceptual Design) for the closure cover of the Pit 6 Landfill. A Title I Design is generally 30 percent of the design effort. Title H Design takes the design to 100 percent complete. Comments and edits to this Title I Design will be addressed in the Title II design submittal. Contents of this report are as follows: project background; design issues and engineering approach; design drawings; calculation packages; construction specifications outline; and construction quality assurance plan outline

  19. Tank closure reducing grout

    International Nuclear Information System (INIS)

    Caldwell, T.B.

    1997-01-01

    A reducing grout has been developed for closing high level waste tanks at the Savannah River Site in Aiken, South Carolina. The grout has a low redox potential, which minimizes the mobility of Sr 90 , the radionuclide with the highest dose potential after closure. The grout also has a high pH which reduces the solubility of the plutonium isotopes. The grout has a high compressive strength and low permeability, which enhances its ability to limit the migration of contaminants after closure. The grout was designed and tested by Construction Technology Laboratories, Inc. Placement methods were developed by the Savannah River Site personnel

  20. Closure Report for Corrective Action Unit 340: NTS Pesticide Release Sites Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    C. M. Obi

    2000-05-01

    The purpose of this report is to provide documentation of the completed corrective action and to provide data confirming the corrective action. The corrective action was performed in accordance with the approved Corrective Action Plan (CAP) (U.S. Department of Energy [DOE], 1999) and consisted of clean closure by excavation and disposal. The Area 15 Quonset Hut 15-11 was formerly used for storage of farm supplies including pesticides, herbicides, and fertilizers. The Area 23 Quonset Hut 800 was formerly used to clean pesticide and herbicide equipment. Steam-cleaning rinsate and sink drainage occasionally overflowed a sump into adjoining drainage ditches. One ditch flows south and is referred to as the quonset hut ditch. The other ditch flows southeast and is referred to as the inner drainage ditch. The Area 23 Skid Huts were formerly used for storing and mixing pesticide and herbicide solutions. Excess solutions were released directly to the ground near the skid huts. The skid huts were moved to a nearby location prior to the site characterization performed in 1998 and reported in the Corrective Action Decision Document (CADD) (DOE, 1998). The vicinity and site plans of the Area 23 sites are shown in Figures 2 and 3, respectively.

  1. An Estimation of Construction and Demolition Debris in Seoul, Korea: Waste Amount, Type, and Estimating Model.

    Science.gov (United States)

    Seo, Seongwon; Hwang, Yongwoo

    1999-08-01

    Construction and demolition (C&D) debris is generated at the site of various construction activities. However, the amount of the debris is usually so large that it is necessary to estimate the amount of C&D debris as accurately as possible for effective waste management and control in urban areas. In this paper, an effective estimation method using a statistical model was proposed. The estimation process was composed of five steps: estimation of the life span of buildings; estimation of the floor area of buildings to be constructed and demolished; calculation of individual intensity units of C&D debris; and estimation of the future C&D debris production. This method was also applied in the city of Seoul as an actual case, and the estimated amount of C&D debris in Seoul in 2021 was approximately 24 million tons. Of this total amount, 98% was generated by demolition, and the main components of debris were concrete and brick.

  2. Considerations for closure of low-level radioactive waste engineered disposal facilities

    International Nuclear Information System (INIS)

    1992-01-01

    Proper stabilization and closure of low-level radioactive waste disposal facilities require detailed planning during the early stages of facility development. This report provides considerations for host States, compact regions, and unaffiliated States on stabilization and closure of engineered low-level radioactive waste and mixed waste disposal facilities. A time line for planning closure activities, which identifies closure considerations to be addressed during various stages of a facility's development, is presented. Current Federal regulatory requirements and guidance for closure and post-closure are outlined. Significant differences between host State and Federal closure requirements are identified. Design features used as stabilization measures that support closure, such as waste forms and containers, backfill materials, engineered barrier systems, and site drainage systems, are described. These design features are identified and evaluated in terms of how they promote long-term site stability by minimizing water infiltration, controlling subsidence and surface erosion, and deterring intrusion. Design and construction features critical to successful closure are presented for covers and site drainage. General considerations for stabilization and closure operations are introduced. The role of performance and environmental monitoring during closure is described

  3. Closure Report for Corrective Action Unit 262: Area 25 Septic Systems and Underground Discharge Point, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Tobiason, D. S.

    2003-01-01

    This Closure Report (CR) documents the activities undertaken to close Corrective Action Unit (CAU) 262: Area 25 Septic Systems and Underground Discharge Point, in accordance with the Federal Facility Agreement and Consent Order (FFACO) of 1996. Site closure was performed in accordance with the Nevada Division of Environmental Protection (NDEP)-approved Corrective Action Plan (CAP) for CAU 262 (U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office [NNSA/NV, 2002a]). CAU 262 is located at the Nevada Test Site (NTS) approximately 105 kilometers (65 miles) northwest of Las Vegas, Nevada. CAU 262 consists of the following nine Corrective Action Sites (CASs) located in Area 25 of the NTS: CAS 25-02-06, Underground Storage tank CAS 25-04-06, Septic Systems A and B CAS 25-04-07, Septic System CAS 25-05-03, Leachfield CAS 25-05-05, Leachfield CAS 25-05-06, Leachfield CAS 25-05-08, Radioactive Leachfield CAS 25-05-12, Leachfield CAS 25-51-01, Dry Well

  4. Recycling of construction and demolition waste in Kuwait

    International Nuclear Information System (INIS)

    Kartam, N.; Al-Mutairi, N.; Al-Ghusain, I.; Al-Humoud, J.

    2002-01-01

    'Full text:' There is an increasing pressure on the construction industry to reduce costs and improve our environment. The fact is that both of these goals can be achieved at the same time. Although construction and demolition (C and D) constitutes a major type of waste in terms of volume and weight, its management and recycling efforts have not seen the light in Kuwait. The goal of this research project is to study methods leading to the minimization of the total C and D waste that is landfilled in Kuwait. This can be achieved by applying the waste management hierarchy in order of importance: 1) reduce, 2) re-use, 3) recycle, 4) incineration (energy recovery), and 5) safe disposal. This paper presents the current C and D waste disposal system in Kuwait and identifies potential problems to the environment, people and economy. Then, it investigates the recycling option to manage and control this major type of waste in an economically efficient and environmentally safe manner. There are significant volumes of potentially valuable and recoverable resources being wasted in the construction industry, and these figures are continuously growing as we are starting the new millennium. C and D waste constitutes 15%-30% of all solid waste entering landfills in various countries [Bossink 1995]; and thus it is a major type of waste. An estimated 2-3 million ton of construction and demolition waste are being only disposed of in Kuwait's landfill sites each year despite the limited available land (Industrial Investment Company, 1990). C and D waste is a target because it is both heavy and bulky, and therefore undesirable for disposal in engineered, lined landfills because of the space it consumes. On the other hand, many C and D materials have high potential for recovery and use. Recovering C and D waste can help communities reach their recycling goals, preserve valuable space in their local landfills, and create better opportunities for handling other kind of waste. Therefore

  5. Regulatory Closure Options for the Residue in the Hanford Site Single-Shell Tanks

    Energy Technology Data Exchange (ETDEWEB)

    Cochran, J.R. Shyr, L.J.

    1998-10-05

    Liquid, mixed, high-level radioactive waste (HLW) has been stored in 149 single-shell tanks (SSTS) located in tank farms on the U.S. Department of Energy's (DOE's) Hanford Site. The DOE is developing technologies to retrieve as much remaining HLW as technically possible prior to physically closing the tank farms. In support of the Hanford Tanks Initiative, Sandia National Laboratories has addressed the requirements for the regulatory closure of the radioactive component of any SST residue that may remain after physical closure. There is significant uncertainty about the end state of each of the 149 SSTS; that is, the nature and amount of wastes remaining in the SSTS after retrieval is uncertain. As a means of proceeding in the face of these uncertainties, this report links possible end-states with associated closure options. Requirements for disposal of HLW and low-level radioactive waste (LLW) are reviewed in detail. Incidental waste, which is radioactive waste produced incidental to the further processing of HLW, is then discussed. If the low activity waste (LAW) fraction from the further processing of HLW is determined to be incidental waste, then DOE can dispose of that incidental waste onsite without a license from the U.S. Nuclear Regulatory Commissions (NRC). The NRC has proposed three Incidental Waste Criteria for determining if a LAW fraction is incidental waste. One of the three Criteria is that the LAW fraction should not exceed the NRC's Class C limits.

  6. Regulatory Closure Options for the Residue in the Hanford Site Single-Shell Tanks

    International Nuclear Information System (INIS)

    Cochran, J.R.; Shyr, L.J.

    1998-01-01

    Liquid, mixed, high-level radioactive waste (HLW) has been stored in 149 single-shell tanks (SSTS) located in tank farms on the U.S. Department of Energy's (DOE's) Hanford Site. The DOE is developing technologies to retrieve as much remaining HLW as technically possible prior to physically closing the tank farms. In support of the Hanford Tanks Initiative, Sandia National Laboratories has addressed the requirements for the regulatory closure of the radioactive component of any SST residue that may remain after physical closure. There is significant uncertainty about the end state of each of the 149 SSTS; that is, the nature and amount of wastes remaining in the SSTS after retrieval is uncertain. As a means of proceeding in the face of these uncertainties, this report links possible end-states with associated closure options. Requirements for disposal of HLW and low-level radioactive waste (LLW) are reviewed in detail. Incidental waste, which is radioactive waste produced incidental to the further processing of HLW, is then discussed. If the low activity waste (LAW) fraction from the further processing of HLW is determined to be incidental waste, then DOE can dispose of that incidental waste onsite without a license from the U.S. Nuclear Regulatory Commissions (NRC). The NRC has proposed three Incidental Waste Criteria for determining if a LAW fraction is incidental waste. One of the three Criteria is that the LAW fraction should not exceed the NRC's Class C limits

  7. Recycled construction and demolition concrete waste as aggregate for structural concrete

    Directory of Open Access Journals (Sweden)

    Ashraf M. Wagih

    2013-12-01

    Full Text Available In major Egyptian cities there is a surge in construction and demolition waste (CDW quantities causing an adverse effect on the environment. The use of such waste as recycled aggregate in concrete can be useful for both environmental and economical aspects in the construction industry. This study discusses the possibility to replace natural coarse aggregate (NA with recycled concrete aggregate (RCA in structural concrete. An investigation into the properties of RCA is made using crushing and grading of concrete rubble collected from different demolition sites and landfill locations around Cairo. Aggregates used in the study were: natural sand, dolomite and crushed concretes obtained from different sources. A total of 50 concrete mixes forming eight groups were cast. Groups were designed to study the effect of recycled coarse aggregates quality/content, cement dosage, use of superplasticizer and silica fume. Tests were carried out for: compressive strength, splitting strength and elastic modulus. The results showed that the concrete rubble could be transformed into useful recycled aggregate and used in concrete production with properties suitable for most structural concrete applications in Egypt. A significant reduction in the properties of recycled aggregate concrete (RAC made of 100% RCA was seen when compared to natural aggregate concrete (NAC, while the properties of RAC made of a blend of 75% NA and 25% RCA showed no significant change in concrete properties.

  8. Underground Test Area (UGTA) Closure Report for Corrective Action Unit 98: Frenchman Flat Nevada National Security Site, Nevada, Revision 1 ROTC-1

    International Nuclear Information System (INIS)

    Farnham, Irene

    2016-01-01

    This Closure Report (CR) has been prepared for Corrective Action Unit (CAU) 98, Frenchman Flat, Nevada National Security Site (NNSS), Nevada. The Frenchman Flat CAU was the site of 10 underground nuclear tests, some of which have impacted groundwater near the tests. This work was performed as part of the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) Underground Test Area (UGTA) Activity in accordance with the Federal Facility Agreement and Consent Order (FFACO). This CR describes the selected corrective action to be implemented during closure to protect human health and the environment from the impacted groundwater

  9. Underground Test Area (UGTA) Closure Report for Corrective Action Unit 98: Frenchman Flat Nevada National Security Site, Nevada, Revision 1 ROTC-1

    Energy Technology Data Exchange (ETDEWEB)

    Farnham, Irene [Navarro-Intera, LLC (N-I), Las Vegas, NV (United States)

    2016-08-01

    This Closure Report (CR) has been prepared for Corrective Action Unit (CAU) 98, Frenchman Flat, Nevada National Security Site (NNSS), Nevada. The Frenchman Flat CAU was the site of 10 underground nuclear tests, some of which have impacted groundwater near the tests. This work was performed as part of the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) Underground Test Area (UGTA) Activity in accordance with the Federal Facility Agreement and Consent Order (FFACO). This CR describes the selected corrective action to be implemented during closure to protect human health and the environment from the impacted groundwater

  10. Concrete decontamination and demolition methods

    International Nuclear Information System (INIS)

    LaGuardia, T.S.

    1980-01-01

    The US Department of Energy (DOE), Division of Environmental Control Technology, requested Nuclear Energy Services to prepare a handbook for the decontamination and decommissioning (D and D) of DOE-owned and commercially-owned radioactive facilities. the objective of the handbook is to provide the nuclear industry with guidance on the state-of-the-art methods and equipment available for decommissioning and to provide the means to estimate decommissioning costs and environmental impact. The methods available for concrete decontamination and demolition are summarized to provide an overview of some of the state-of-the-art techniques to be discussed at this workshop. The pertinent information on each method will include the selection factors such as the rate of performance in terms of concrete removal per unit time (cubic yards per day), manpower required by craft, unit cost (dollars per cubic yard) and the advantages and disadvantages. The methods included in this overview are those that have been routinely used in nuclear and nonnuclear applications or demonstrated in field tests. These methods include controlled blasting, wrecking ball or slab, backhoe mounted ram, flame torch, thermic lance, rock splitter, demolition compound, sawing, core stitch drilling, explosive cutting, paving breaker and power chisel, drill and spall, scarifying, water cannon and grinding

  11. Deployment of an Alternative Closure Cover and Monitoring System at the Mixed Waste Disposal Unit U-3ax/bl at the Nevada Test Site

    International Nuclear Information System (INIS)

    Levitt, D.G.; Fitzmaurice, T.M.

    2001-01-01

    In October 2000, final closure was initiated of U-3ax/bl, a mixed waste disposal unit at the Nevada Test Site (NTS). The application of approximately 30 cm of topsoil, composed of compacted native alluvium onto an operational cover, seeding of the topsoil, installation of soil water content sensors within the cover, and deployment of a drainage lysimeter facility immediately adjacent to the disposal unit initiated closure. This closure is unique in that it required the involvement of several U.S. Department of Energy (DOE) Environmental Management (EM) groups: Waste Management (WM), Environmental Restoration (ER), and Technology Development (TD). Initial site characterization of the disposal unit was conducted by WM. Regulatory approval for closure of the disposal unit was obtained by ER, closure of the disposal unit was conducted by ER, and deployment of the drainage lysimeter facility was conducted by WM and ER, with funding provided by the Accelerated Site Technology Deployment ( ASTD) program, administered under TD. In addition, this closure is unique in that a monolayer closure cover, also known as an evapotranspiration (ET) cover, consisting of native alluvium, received regulatory approval instead of a traditional Resource Conservation and Recovery Act (RCRA) multi-layered cover. Recent studies indicate that in the arid southwestern United States, monolayer covers may be more effective at isolating waste than layered covers because of the tendency of clay layers to desiccate and crack, and subsequently develop preferential pathways. The lysimeter facility deployed immediately adjacent to the closure cover consists of eight drainage lysimeters with three surface treatments: two were left bare; two were revegetated with native species; two were allowed to revegetate with invader species; and two are reserved for future studies. The lysimeters are constructed such that any drainage through the bottoms of the lysimeters can be measured. Sensors installed in the

  12. Closure of a mixed waste landfill: Lessons learned

    International Nuclear Information System (INIS)

    Phifer, M.A.

    1990-01-01

    Much experience has been gained during the closure of the Mixed Waste Management Facility (MWMF) at the Savannah River Site (SRS) and many lessons were learned. This knowledge was applied to other closures at SRS yielding decreased costs, schedule enhancement, and increased overall project efficiency. The next major area of experience to be gained at SRS in the field of waste site closures will be in the upkeep, maintenance, and monitoring of clay caps. Further test programs will be required to address these requirements

  13. Construction and Demolition Waste

    DEFF Research Database (Denmark)

    Christensen, Thomas Højlund; Andersen, L.

    2011-01-01

    Construction and demolition waste (C&D waste) is the waste generated during the building, repair, remodeling or removal of constructions. The constructions can be roads, residential housing and nonresidential buildings. C&D waste has traditionally been considered without any environmental problems...... should be managed accordingly. Another reason is that it has been documented that a large fraction of C&D waste (about 90 %) can be easily recycled and thus can conserve landfill capacity. C&D waste may conveniently be divided into three subcategories: Buildings, roads and excavations. This chapter...

  14. Closure Report for Corrective Action Unit 539: Areas 25 and 26 Railroad Tracks Nevada National Security Site, Nevada with ROTC-1, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Mark Kauss

    2011-06-01

    This Closure Report (CR) presents information supporting the closure of Corrective Action Unit (CAU) 539: Areas 25 and 26 Railroad Tracks, Nevada National Security Site, Nevada. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. The corrective action sites (CASs) within CAU 539 are located within Areas 25 and 26 of the Nevada National Security Site. Corrective Action Unit 539 comprises the following CASs: • 25-99-21, Area 25 Railroad Tracks • 26-99-05, Area 26 Railroad Tracks The purpose of this CR is to provide documentation supporting the completed corrective actions and provide data confirming that the closure objectives for CASs within CAU 539 were met. To achieve this, the following actions were performed: • Reviewed documentation on historical and current site conditions, including the concentration and extent of contamination. • Conducted radiological walkover surveys of railroad tracks in both Areas 25 and 26. • Collected ballast and soil samples and calculated internal dose estimates for radiological releases. • Collected in situ thermoluminescent dosimeter measurements and calculated external dose estimates for radiological releases. • Removed lead bricks as potential source material (PSM) and collected verification samples. • Implemented corrective actions as necessary to protect human health and the environment. • Properly disposed of corrective action and investigation wastes. • Implemented an FFACO use restriction (UR) for radiological contamination at CAS 25-99-21. The approved UR form and map are provided in Appendix F and will be filed in the DOE, National Nuclear Security Administration Nevada Site Office (NNSA/NSO), Facility Information Management System; the FFACO database; and the NNSA/NSO CAU/CAS files. From November 29

  15. Distally based sural neuro-fasciocutaneous perforator flap for foot and ankle reconstruction: Surgical modifications for flap pedicle and donor site closure without skin graft.

    Science.gov (United States)

    Chi, Zhenglin; Chen, Yiheng; Chu, Tinggang; Gao, Weiyang; Li, Zhijie; Yan, Hede; Song, Yonghuan

    2018-02-01

    The conventional procedure of the sural neuro-fasciocutaneous flap enables the supply of blood and venous drainage by increasing the width of the adipofascial tissue and preserving tiny venous return routes. Moreover, skin graft is a common method for donor site closure, which may lead to some complications and influence the aesthetic appearance. We report modifications for a distally based sural neuro-fasciocutaneous perforator flap and a relaying flap for donor site closure without skin graft. Twelve patients undergoing the modified flap for foot and ankle reconstruction were included in this study between 2014 and 2016. A peroneal-based perforator, a superficial vein, and the vascular axis of the sural nerve were included in the pedicle. A Z-shape skin incision was performed to explore the perforator vessels and a relaying island perforator flap was used to close the donor site. All flaps survived completely without necrosis. The area of the flaps ranged from 16 × 8 cm to 30 × 15 cm. The diameter width of the pedicle ranged from 1.0 to 2.0 cm. A relaying perforator island flap was used in 10 cases for donor site closure and no skin graft was performed. There were no serious donor site complications. All patients were satisfied with the aesthetic outcome postoperatively at the final follow-up. The distally based sural neuro-fasciocutaneous perforator flap is considered a reliable method for foot and ankle reconstruction. The modification for flap pedicle and donor site closure method without skin graft should be recommended. Copyright © 2017. Published by Elsevier Ltd.

  16. High Flux Isotopes Reactor (HFIR) Cooling Towers Demolition Waste Management

    Energy Technology Data Exchange (ETDEWEB)

    Pudelek, R. E.; Gilbert, W. C.

    2002-02-26

    This paper describes the results of a joint initiative between Oak Ridge National Laboratory, operated by UT-Battelle, and Bechtel Jacobs Company, LLC (BJC) to characterize, package, transport, treat, and dispose of demolition waste from the High Flux Isotope Reactor (HFIR), Cooling Tower. The demolition and removal of waste from the site was the first critical step in the planned HFIR beryllium reflector replacement outage scheduled. The outage was scheduled to last a maximum of six months. Demolition and removal of the waste was critical because a new tower was to be constructed over the old concrete water basin. A detailed sampling and analysis plan was developed to characterize the hazardous and radiological constituents of the components of the Cooling Tower. Analyses were performed for Resource Conservation and Recovery Act (RCRA) heavy metals and semi-volatile constituents as defined by 40 CFR 261 and radiological parameters including gross alpha, gross beta, gross gamma, alpha-emitting isotopes and beta-emitting isotopes. Analysis of metals and semi-volatile constituents indicated no exceedances of regulatory limits. Analysis of radionuclides identified uranium and thorium and associated daughters. In addition 60Co, 99Tc, 226Rm, and 228Rm were identified. Most of the tower materials were determined to be low level radioactive waste. A small quantity was determined not to be radioactive, or could be decontaminated. The tower was dismantled October 2000 to January 2001 using a detailed step-by-step process to aid waste segregation and container loading. The volume of waste as packaged for treatment was approximately 1982 cubic meters (70,000 cubic feet). This volume was comprised of plastic ({approx}47%), wood ({approx}38%) and asbestos transite ({approx}14%). The remaining {approx}1% consisted of the fire protection piping (contaminated with lead-based paint) and incidental metal from conduit, nails and braces/supports, and sludge from the basin. The waste

  17. Role of organic aerosols in CCN activation and closure over a rural background site in Western Ghats, India

    Science.gov (United States)

    Singla, V.; Mukherjee, S.; Safai, P. D.; Meena, G. S.; Dani, K. K.; Pandithurai, G.

    2017-06-01

    The cloud condensation nuclei (CCN) closure study was performed to exemplify the effect of aerosol chemical composition on the CCN activity of aerosols at Mahabaleshwar, a high altitude background site in the Western Ghats, India. For this, collocated aerosol, CCN, Elemental Carbon (EC), Organic Carbon (OC), sub-micron aerosol chemical speciation for the period from 3rd June to 19th June 2015 was used. The chemical composition of non-refractory particulate matter (theory on the basis of measured aerosol particle number size distribution, size independent NR-PM1 chemical composition and calculated hygroscopicity. The CCN closure study was evaluated for 3 scenarios, B-I (all soluble inorganics), B-IO (all soluble organics and inorganics) and B-IOOA (all soluble inorganic and soluble oxygenated organic aerosol, OOA). OOA component was derived from the positive matrix factorization (PMF) analysis of organic aerosol mass spectra. Considering the bulk composition as internal mixture, CCN closure study was underestimated by 16-39% for B-I and overestimated by 47-62% for B-IO. The CCN closure result was appreciably improved for B-IOOA where the knowledge of OOA fraction was introduced and uncertainty reduced to within 8-10%.

  18. Innovative probabilistic risk assessment applications: barrier impairments and fracture toughness. 2. Demolition Debris and Tornado Missile Hazard During Decommissioning

    International Nuclear Information System (INIS)

    Calhoun, David; Shepherd, Stephen

    2001-01-01

    During their operating lives, nuclear power plants typically maintain a high level of control over the amount of debris that is allowed to accumulate at the plant site. Although primarily intended to reduce the potential for fire damage, some plants also rely on these controls to limit the damage that could be caused during a tornado from missiles generated from loose debris. Demolition work associated with power plant decommissioning inevitably increases the quantity of debris. When bulk commodities such as piping and electrical distribution components are demolished, they are subject to various staging, handling, and storage processes before they can be released from the site. The demolition of plant structures dramatically increases the quantity of loose steel and concrete debris. For the foreseeable future, all plants that undertake decommissioning will have spent-fuel assemblies present on the plant site during the demolition project whether the spent fuel remains stored in a spent-fuel pool or is transferred to an independent spent-fuel storage installation (ISFSI). Under present regulations, protection from tornado missiles would be required for both types of spent-fuel storage. In addition, a small proportion of decommissioning plants will have operating units in close proximity. Licensing commitments for tornado missile protection may mandate controls on the production or storage of demolition debris. This paper presents a case study of the San Onofre Nuclear Generating Station (Fig. 1). Tornado missile protection licensing commitments from three types of facilities will be in force during the decommissioning of San Onofre Unit 1 (Unit 1): 1. Unit 1, under a possession-only license; 2. an ISFSI that will eventually store spent fuel from Unit 1; 3. San Onofre Operating Unit 2 (Unit 2) and San Onofre Operating Unit 3 (Unit 3). Together, these three facilities illustrate the range of impacts that licensing commitments designed for tornado protection may

  19. Preliminary post-closure safety assessment of repository concepts for low level radioactive waste at the Bruce Site, Ontario

    International Nuclear Information System (INIS)

    Little, R.H.; Penfold, J.S.S.; Egan, M.J.; Leung, H.

    2005-01-01

    The preliminary post-closure safety assessment of permanent repository concepts for low-level radioactive waste (LLW) at the Ontario Power Generation (OPG) Bruce Site is described. The study considered the disposal of both short and long-lived LLW. Four geotechnically feasible repository concepts were considered (two near-surface and two deep repositories). An approach consistent with best international practice was used to provide a reasoned and comprehensive analysis of post-closure impacts of the repository concepts. The results demonstrated that the deep repository concepts in shale and in limestone, and the surface repository concept on sand should meet radiological protection criteria. For the surface repository concept on glacial till, it appears that increased engineering such as grouting of waste and voids should be considered to meet the relevant dose constraint. Should the project to develop a permanent repository for LLW proceed, it is expected that this preliminary safety assessment would need to be updated to take account of future site-specific investigations and design updates. (author)

  20. Remediation and demolition of coke by-products plants

    Energy Technology Data Exchange (ETDEWEB)

    Stiffler, M A; Gould, W C

    1992-08-01

    The programme undertaken by ICF Kaiser Engineers and LTV Steel Co. to clean up and demolish four closed coking plants is described, including PCB removal, asbestos abatement, pipe removal and cleaning, tank cleaning, demolition and soil bioremediation. Costs are discussed.

  1. CIRSE Vascular Closure Device Registry

    International Nuclear Information System (INIS)

    Reekers, Jim A.; Müller-Hülsbeck, Stefan; Libicher, Martin; Atar, Eli; Trentmann, Jens; Goffette, Pierre; Borggrefe, Jan; Zeleňák, Kamil; Hooijboer, Pieter; Belli, Anna-Maria

    2011-01-01

    Purpose: Vascular closure devices are routinely used after many vascular interventional radiology procedures. However, there have been no major multicenter studies to assess the safety and effectiveness of the routine use of closure devices in interventional radiology. Methods: The CIRSE registry of closure devices with an anchor and a plug started in January 2009 and ended in August 2009. A total of 1,107 patients were included in the registry. Results: Deployment success was 97.2%. Deployment failure specified to access type was 8.8% [95% confidence interval (95% CI) 5.0–14.5] for antegrade access and 1.8% (95% CI 1.1–2.9) for retrograde access (P = 0.001). There was no difference in deployment failure related to local PVD at the access site. Calcification was a reason for deployment failure in only 5.9 cm, and two vessel occlusions. Conclusion: The conclusion of this registry of closure devices with an anchor and a plug is that the use of this device in interventional radiology procedures is safe, with a low incidence of serious access site complications. There seems to be no difference in complications between antegrade and retrograde access and other parameters.

  2. Environmental and economical feasibility of selective demolition project; Viabilidad ambiental y economica de un proyecto de demolicion selectiva: hacia una optima gestion de los RCD

    Energy Technology Data Exchange (ETDEWEB)

    Vegas, I.

    2004-07-01

    Selective demolition practices have not yet become popular in our country. Unlike conventional demolition practices, selective demolition helps to increase the amount of components to be reused or materials to be recycled. Thus, the percentage of demolition waste deposited in landfills can be reduced, and the production of recycled materials with optimum quality is fostered. Taking the case study of selective demolition carried out in the municipally of Lasarte-Oria (Basque Country-Spain) as its basis, this paper presents an economic and environmental analysis of the same. Likewise, the economic costs deriving from selective demolition are compared with analogous costs from conventional demolition with an aim to establishing the ideal frame supporting economically feasible selective demolition. (Author)

  3. GIS-based planning system for managing the flow of construction and demolition waste in Brazil.

    Science.gov (United States)

    Paz, Diogo Henrique Fernandes da; Lafayette, Kalinny Patrícia Vaz; Sobral, Maria do Carmo

    2018-05-01

    The objective of this article was to plan a network for municipal management of construction and demolition waste in Brazil with the assistance of a geographic information system, using the city of Recife as a case study. The methodology was carried out in three stages. The first was to map the illegal construction and demolition of waste disposal points across Recife and classify the waste according to its recyclability. In sequence, a method for indicating suitable areas for installation of voluntary delivery points, for small waste generators, are presented. Finally, a method for indicating suitable areas for the installation of trans-shipment and waste sorting areas, developed for large generators, is presented. The results show that a geographic information system is an essential tool in the planning of municipal construction and demolition waste management, in order to facilitate the spatial analysis and control the generation, sorting, collection, transportation, and final destination of construction and demolition waste, increasing the rate of recovery and recycling of materials.

  4. Closure report for CAU 93: Area 6 steam cleaning effluent ponds, Nevada Test Site. Volume 2

    International Nuclear Information System (INIS)

    1997-11-01

    The Steam Cleaning Effluent Ponds (SCEP) waste unit is located in Area 6 at the Nevada Test Site. The SCEPs are evaporation basins formerly used for the disposal of untreated liquid effluent discharged from steam cleaning activities associated with Buildings 6-623 and 6-800. This report contains Appendix B which provides all of the laboratory summary data sheets for the Area 6 SCEPs closure activities

  5. Closure report for CAU 93: Area 6 steam cleaning effluent ponds, Nevada Test Site. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-11-01

    The Steam Cleaning Effluent Ponds (SCEP) waste unit is located in Area 6 at the Nevada Test Site. The SCEPs are evaporation basins formerly used for the disposal of untreated liquid effluent discharged from steam cleaning activities associated with Buildings 6-623 and 6-800. This report contains Appendix B which provides all of the laboratory summary data sheets for the Area 6 SCEPs closure activities.

  6. Comparing over-the-scope clip versus endoloop and clips (KING closure) for access site closure: a randomized experimental study

    Czech Academy of Sciences Publication Activity Database

    Martínek, J.; Ryska, O.; Tučková, I.; Filípková, T.; Doležel, R.; Juhás, Štefan; Motlík, Jan; Zavoral, M.; Ryska, M.

    2013-01-01

    Roč. 27, č. 4 (2013), s. 1203-1210 ISSN 0930-2794 R&D Projects: GA MZd NS9994 Institutional research plan: CEZ:AV0Z50450515 Keywords : NOTES * gastrotomy closure * rectotomy closure Subject RIV: FJ - Surgery incl. Transplants Impact factor: 3.313, year: 2013

  7. POST-CLOSURE INSPECTION REPORT FOR CORRECTIVE ACTION UNIT 92: AREA 6 DECON POND FACILITY, NEVADA TEST SITE, NEVADA FOR CALENDAR YEAR 2005

    International Nuclear Information System (INIS)

    2006-01-01

    This Post-Closure Inspection Report provides an analysis and summary of inspections for Corrective Action Unit (CAU) 92, Area 6 Decon Pond Facility, Nevada Test Site, Nevada. CAU 92 was closed in accordance with the Resource Conservation and Recovery Act (RCRA) Part B Operational Permit (Nevada Division of Environmental Protection (NDEP), 1995) and the Federal Facility Agreement and Consent Order of 1996. Closure activities were completed on February 16, 1999, and the Closure Report (U.S. Department of Energy, Nevada Operations Office, 1999) was approved and a Notice of Completion issued by the NDEP on May 11, 1999. CAU 92 consists of two Corrective Action Sites (CASs): CAS 06-04-01, Decon Pad Oil/Water Separator; and CAS 06-05-02, Decontamination Pond (RCRA). Both CASs have use restrictions; however, only CAS 06-05-02 requires post-closure inspections. Visual inspections of the cover and fencing at CAS 06-05-02 are performed quarterly. Additional inspections are conducted if precipitation occurs in excess of 1.28 centimeters (cm) (0.50 inches [in]) in a 24-hour period. This report covers calendar year 2005. Quarterly site inspections were performed in March, June, September, and December of 2005. All observations indicated the continued integrity of the unit. No issues or concerns were noted, and no corrective actions were necessary. Copies of the inspection checklists and field notes completed during each inspection are included in Appendix A. Five additional inspections were performed after precipitation events that exceeded 1.28 cm (0.50 in) within a 24-hour period during 2005. No significant changes in site conditions were noted during these inspections, and no corrective actions were necessary. Copies of the inspection checklists and field notes completed during each inspection are included in Appendix A. Precipitation records for 2005 are included in Appendix C

  8. Quantities of arsenic-treated wood in demolition debris generated by Hurricane Katrina.

    Science.gov (United States)

    Dubey, Brajesh; Solo-Gabriele, Helena M; Townsendt, Timothy G

    2007-03-01

    The disaster debris from Hurricane Katrina is one of the largest in terms of volume and economic loss in American history. One of the major components of the demolition debris is wood waste of which a significant proportion is treated with preservatives, including preservatives containing arsenic. As a result of the large scale destruction of treated wood structures such as electrical poles, fences, decks, and homes a considerable amount of treated wood and consequently arsenic will be disposed as disaster debris. In this study an effort was made to estimate the quantity of arsenic disposed through demolition debris generated in the Louisiana and Mississippi area through Hurricane Katrina. Of the 72 million cubic meters of disaster debris generated, roughly 12 million cubic meters were in the form of construction and demolition wood resulting in an estimated 1740 metric tons of arsenic disposed. Management of disaster debris should consider the relatively large quantities of arsenic associated with pressure-treated wood.

  9. Stripping demolition of reinforced concrete by electric heating method

    International Nuclear Information System (INIS)

    Nakagawa, Wahei; Nishita, Kiwamu; Kasai, Yoshio

    1993-01-01

    The present paper describes the procedures and results of a series of experiments the authors conducted to verify the efficiency of the electric heating method, previously proposed for so-called stripping demolition by applying electric current through reinforcing bars. In this method, a low voltage high current is run from one end to the other of a reinforcing bar or bars existing in a concrete structure, inducing intense heat in the bar(s) which in its turn brings about cracks in the surrounding concrete mass, facilitating secondary demolition by hammer picks or other means. The experiments were performed on full-scale biological shield wall mock-ups of a BWR and a small reactor. The results of the experiments are summarized as follows. (1) When electric current is applied through reinforcing bars, the bond between concrete and bars is loosened, and cracks start from one bar and progress toward other bars. Under appropriate conditions, the cracks in concrete run from the contact surface at one bar all the way to its the contact surface on another bar. (2) Cracks appear and grow only between two electrodes between which current is applied, not extending out of the area thus defined. (3) The concrete in the region closer to a current-bearing bar is intensely heated, whereas the concrete far from the bars remains nearly unheated. (4) Concrete walls after electric heating of bars disintegrates, if demolished with hammers, with the covering concrete are removed from the remaining portion of the structure together with heated bars, in shapes of flakes. (5) The reinforced concrete collapses in massive pieces of concrete, without generating much dust as is the case with the demolition of a concrete structure not heated by electricity. Results of the experiments show that the electric heating method is worth applying also to the demolition of nuclear power plants where concrete in the radioactivated surface region of shield walls needs to be stripped off in flakes

  10. Does demolition or refurbishment of old and inefficient homes help to increase our environmental, social and economic viability?

    International Nuclear Information System (INIS)

    Power, Anne

    2008-01-01

    The issue of whether to demolish or refurbish older housing has been debated for over a century. It has been an active policy area since the late 1880s, when the Government first authorised the statutory demolition of insanitary slums. In the 1960s, revulsion at the scale of 'demolition blight' and new building caused a rethink, leading to a major reinvestment in inner city neighbourhoods of older housing. In the past 5 years, debate on demolition and new building has been intensified by the Government's Sustainable Communities Plan of 2003, with its proposals for large-scale clearance and building. Environmental arguments about renovating the existing stock have gained increasing prominence as people have sought to defend their communities from demolition. The evidence on whether demolition would reduce the amount of greenhouse gases we emit into the atmosphere is unclear and disputed. This paper summarises the evidence and arguments, and attempts to clarify the most realistic, achievable route to major reductions in energy use in homes

  11. Asbestos exposure among construction workers during demolition of old houses in Tehran, Iran.

    Science.gov (United States)

    Kakooei, Hossein; Normohammadi, Mohhammad

    2014-01-01

    Air quality in demolition practices has seldom been evaluated in Iran. Accordingly, we evaluated asbestos exposure among Tehran construction workers during the demolition of old houses. To identify possible sources of asbestos exposure, including thermal insulations, chimney pipes and cement sheets, were all sampled. This study also were taken the personal air samples to evaluate any asbestos exposure during the demolition. The asbestos fibers found in the samples were analyzed by phase-contrast optical microscopy (PCM), scanning electron microscopy (SEM) equipped with an energy dispersive X-ray analysis, and polarized light microscopy (PLM) methods. Personal monitoring of asbestos fiber levels indicated a range from 0.01 to 0.15 PCM f/ml (0.02-0.42 SEM f/ml). The geometric mean concentrations were 0.07 PCM f/ml (0.20 SEM f/ml), which is considerably higher than the threshold limit value (TLV) proposed by American Conference of Governmental Industrial Hygienist (ACGIH), which is 0.1 f/ml. The analysis showed a presence in the bulk samples only chrysotile asbestos and an absence of the other type asbestos. Therefore, it might be expected that workers who worked in the demolition of old houses will suffer from negative effects of exposing to the asbestos fibers.

  12. Detailed design report for an operational phase panel-closure system

    International Nuclear Information System (INIS)

    1996-01-01

    Under contract to Westinghouse Electric Corporation (Westinghouse), Waste Isolation Division (WID), IT Corporation has prepared a detailed design of a panel-closure system for the Waste Isolation Pilot Plant (WIPP). Preparation of this detailed design of an operational-phase closure system is required to support a Resource Conservation and Recovery Act (RCRA) Part B permit application and a non-migration variance petition. This report describes the detailed design for a panel-closure system specific to the WIPP site. The recommended panel-closure system will adequately isolate the waste-emplacement panels for at least 35 years. This report provides detailed design and material engineering specifications for the construction, emplacement, and interface-grouting associated with a panel-closure system at the WIPP repository, which would ensure that an effective panel-closure system is in place for at least 35 years. The panel-closure system provides assurance that the limit for the migration of volatile organic compounds (VOC) will be met at the point of compliance, the WIPP site boundary. This assurance is obtained through the inherent flexibility of the panel-closure system

  13. Nevada test site underground storage tank number 12-13-1: Nevada division of emergency management case number H931130E corrective action unit 450. Closure report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-01-01

    The project site was identified as an abandoned Underground Storage Tank (UST) to be closed under the Department of Energy/Nevada Operations Office (DOE/NV) Environmental Restoration Division (ERD) Program during Fiscal Year 1993. The United States Environmental Protection Agency (EPA) requires that before permanent closure is completed an assessment of the site must take place. The Nevada Division of Environmental Protection (NDEP) requires assessment and corrective actions for a petroleum substance in the soil which exceeds 100 milligrams per kilogram (mg/kg). Subsequent to the tank removal, a hydrocarbon release was identified at the site. The release was reported to the NDEP by DOE/NV on November 30, 1993. Nevada Division of Environmental Management (NDEM) Case Number H931130E was assigned. This final closure report documents the assessment and corrective actions taken for the hydrocarbon release identified at the site. The Notification of Closure, EPA Form 7530-1 dated March 22, 1994, is provided in Appendix A. A 45-day report documenting the notification for a hydrocarbon release was submitted to NDEP on April 6, 1994.

  14. Closure certification report: TA-35 TSL-125 surface impoundment

    International Nuclear Information System (INIS)

    1991-01-01

    This closure report documents closure activities for the TA-35 TSL-125 surface impoundment and associated structures at Los Alamos National Laboratory (the Laboratory). Prior to formal approval of the closure plan, the decision was made to proceed with closure activities to prevent any further releases from the site following informal discussions with New Mexico Environment Department (NMED) personnel. The closure plan is a revision of the previously submitted draft dated July 1988. Clean closure of the TSL-125 site was accomplished through: Removal and proper disposal of all wastes contained within the surface impoundment system; Decontamination and/or removal and proper disposal of the surface impoundment, its associated structures, and contaminated soil underlying the impoundment area; Sampling and analysis of soil to determine the presence and concentrations of any hazardous constituents remaining in the soil at the TSL-125 site; and Demonstration through a risk assessment that any constituents remaining in the soil at the TSL-125 site pose no threat to human health and the environment. All remaining soil concentrations of hazardous constituents were below health-based action levels. Analytical results indicated that benzidine, n-nitrosodimethylamine, and n-nitrosodi-n-propylamine were not detected at or above their limits of quantitation and beryllium was not present at or above its laboratory detection limit. However, the limits of quantitation and detection for these constituents were greater than their calculated health-based action levels. To demonstrate that these constituents were not present, historical data was researched and it was determined that the constituents were not utilized at the Building 125 site. 4 refs., 8 figs., 1 tab

  15. Application of micro blasting technique to demolition of biological shield wall of reactor building

    International Nuclear Information System (INIS)

    Kontani, Osamu

    2016-01-01

    Although heavily reinforced concrete structures in nuclear facilities could be dismantled effectively with the controlled blasting technique, the noises and vibrations caused by blasting were matters of concern. Recently, in the building replacement at urban areas, there are increasing cases of demolition of large reinforced concrete members below ground. Instead of applying heavy weight breakers, the micro blasting technique that enables to lower noises and vibrations has developed and applied to demolition work of large reinforced concrete members in urban areas. In this report, the features of the micro blasting technique is reviewed by comparing with existing controlled blasting technique and its applicability to demolition work of nuclear facilities is investigated. The results of those study find that it is confirmed that the micro blasting technique could be applicable to large reinforced concrete structures in nuclear facilities because of the low levels of noises and vibrations. However, it is recommended to perform mock-up tests to confirm the demolition efficiency and levels of the noises and vibrations since the rebar used in nuclear facilities is larger in diameters and in rebar ratio compared with ordinary reinforced concrete structures. (author)

  16. STATUS OF MECHANICAL SLUDGE REMOVAL AND COOLING COILS CLOSURE AT THE SAVANNAH RIVER SITE - F TANK FARM CLOSURE PORJECT -9225

    International Nuclear Information System (INIS)

    Jolly, R.

    2009-01-01

    The Savannah River Site F-Tank Farm Closure project has successfully performed Mechanical Sludge Removal using the Waste on Wheels (WOW) system within two of its storage tanks. The Waste on Wheels (WOW) system is designed to be relatively mobile with the ability for many components to be redeployed to multiple tanks. It is primarily comprised of Submersible Mixer Pumps (SMPs), Submersible Transfer Pumps (STPs), and a mobile control room with a control panel and variable speed drives. These tanks, designated as Tank 6 and Tank 5 respectively, are Type I waste tanks located in F-Tank Farm (FTF) with a capacity of 2839 cubic meters (750,000 gallons) each. In addition, Type I tanks have 34 vertically oriented cooling coils and two horizontal cooling coil circuits along the tank floor. DOE intends to remove from service and operationally close Tank 5 and Tank 6 and other HLW tanks that do not meet current containment standards. After obtaining regulatory approval, the tanks and cooling coils will be isolated and filled with grout for long term stabilization. Mechanical Sludge Removal of the remaining sludge waste within Tank 6 removed ∼ 75% of the original 25,000 gallons in August 2007. Utilizing lessons learned from Tank 6, Tank 5 Mechanical Sludge Removal completed removal of ∼ 90% of the original 125 cubic meters (33,000 gallons) of sludge material in May 2008. The successful removal of sludge material meets the requirement of approximately 19 to 28 cubic meters (5,000 to 7,500 gallons) remaining prior to the Chemical Cleaning process. The Chemical Cleaning Process will utilize 8 wt% oxalic acid to dissolve the remaining sludge heel. The flow sheet for Chemical Cleaning planned a 20:1 volume ratio of acid to sludge for the first strike with mixing provided by the submersible mixer pumps. The subsequent strikes will utilize a 13:1 volume ratio of acid to sludge with no mixing. The results of the Chemical Cleaning Process are detailed in the 'Status of Chemical

  17. STATUS OF MECHANICAL SLUDGE REMOVAL AND COOLING COILS CLOSURE AT THE SAVANNAH RIVER SITE - F TANK FARM CLOSURE PROJECT - 9225

    Energy Technology Data Exchange (ETDEWEB)

    Jolly, R

    2009-01-06

    The Savannah River Site F-Tank Farm Closure project has successfully performed Mechanical Sludge Removal using the Waste on Wheels (WOW) system within two of its storage tanks. The Waste on Wheels (WOW) system is designed to be relatively mobile with the ability for many components to be redeployed to multiple tanks. It is primarily comprised of Submersible Mixer Pumps (SMPs), Submersible Transfer Pumps (STPs), and a mobile control room with a control panel and variable speed drives. These tanks, designated as Tank 6 and Tank 5 respectively, are Type I waste tanks located in F-Tank Farm (FTF) with a capacity of 2839 cubic meters (750,000 gallons) each. In addition, Type I tanks have 34 vertically oriented cooling coils and two horizontal cooling coil circuits along the tank floor. DOE intends to remove from service and operationally close Tank 5 and Tank 6 and other HLW tanks that do not meet current containment standards. After obtaining regulatory approval, the tanks and cooling coils will be isolated and filled with grout for long term stabilization. Mechanical Sludge Removal of the remaining sludge waste within Tank 6 removed {approx} 75% of the original 25,000 gallons in August 2007. Utilizing lessons learned from Tank 6, Tank 5 Mechanical Sludge Removal completed removal of {approx} 90% of the original 125 cubic meters (33,000 gallons) of sludge material in May 2008. The successful removal of sludge material meets the requirement of approximately 19 to 28 cubic meters (5,000 to 7,500 gallons) remaining prior to the Chemical Cleaning process. The Chemical Cleaning Process will utilize 8 wt% oxalic acid to dissolve the remaining sludge heel. The flow sheet for Chemical Cleaning planned a 20:1 volume ratio of acid to sludge for the first strike with mixing provided by the submersible mixer pumps. The subsequent strikes will utilize a 13:1 volume ratio of acid to sludge with no mixing. The results of the Chemical Cleaning Process are detailed in the &apos

  18. Corrective Action Decision Document/Closure Report for Corrective Action Unit 477: Area 12 N-Tunnel Muckpile, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 477, N-Tunnel Muckpile. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Corrective Action Unit 477 is comprised of one Corrective Action Site (CAS): • 12-06-03, Muckpile The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure with no further action, by placing use restrictions on CAU 477.

  19. Corrective Action Decision Document/Closure Report for Corrective Action Unit 476: Area 12 T-Tunnel Muckpile, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 476, Area 12 T-Tunnel Muckpile. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Corrective Action Unit 476 is comprised of one Corrective Action Site (CAS): • 12-06-02, Muckpile The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 476.

  20. Permanent Closure of the TAN-664 Underground Storage Tank

    Energy Technology Data Exchange (ETDEWEB)

    Bradley K. Griffith

    2011-12-01

    This closure package documents the site assessment and permanent closure of the TAN-664 gasoline underground storage tank in accordance with the regulatory requirements established in 40 CFR 280.71, 'Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks: Out-of-Service UST Systems and Closure.'

  1. Strategy of Construction and Demolition Waste Management after Chemical Industry Facilities Removal

    Science.gov (United States)

    Tashkinova, I. N.; Batrakova, G. M.; Vaisman, Ya I.

    2017-06-01

    Mixed waste products are generated in the process of irrelevant industrial projects’ removal if conventional techniques of their demolition and dismantling are applied. In Russia the number of unused chemical industry facilities including structures with high rate of wear is growing. In removing industrial buildings and production shops it is used conventional techniques of demolition and dismantling in the process of which mixed waste products are generated. The presence of hazardous chemicals in these wastes makes difficulties for their use and leads to the increasing volume of unutilized residues. In the process of chemical industry facilities’ removal this fact takes on special significance as a high level of hazardous chemicals in the waste composition demands for the realization of unprofitable measures aimed at ensuring environmental and industrial safety. The proposed strategy of managing waste originated from the demolition and dismantling of chemical industry facilities is based on the methodology of industrial metabolism which allows identifying separate material flows of recycled, harmful and ballast components, performing separate collection of components during removal and taking necessary preventive measures. This strategy has been tested on the aniline synthesis plant being in the process of removal. As a result, a flow of 10 wt. %, subjected to decontamination, was isolated from the total volume of construction and demolition waste (C&D waste). The considered approach allowed using the resource potential of more than 80wt. % of waste and minimizing the disposed waste volume.

  2. Construction, Maintenance and Demolition of Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Smet, Camiel de [Hilti Corporation, P.O. Box 333, FL-9494 Schaan (Liechtenstein)

    2008-07-01

    Hilti is your reliable partner in nuclear power plant construction, maintenance and demolition worldwide. Professional advice and innovative solutions for virtually every phase of construction and supply technologically leading products and systems to increase your productivity and help to create and maintain safe and lasting plants is offered. The solutions for nuclear power plants construction, maintenance and demolition have been employed with great success in many different countries on a wide variety of projects due in no small way to their worldwide availability. An unbroken, international exchange of experience upholds a permanent innovation process. This assures our customers that they always receive products on the very latest technological standard. This paper is not intended to cover all topics related to nuclear power plants. The idea is more to give a kind of an overview. The paper covers briefly the following topics: safety (corrosion and fire), fastenings, measuring and finally decommissioning of nuclear power plants. (author)

  3. Towards a more professional demolition and dismantling industry

    International Nuclear Information System (INIS)

    1988-01-01

    The work of the National Economic Development Office Demolition and Dismantling Group in four areas which are crucial to the economic performance of the demolition and dismantling industry and its safety record is considered. The first concerns the availability and accessibility of information about unconventional structures and details are given of the sort of information often kept for different types of structure. Secondly, the need is stressed for guidelines for the client, particularly on the risks involved and the choice of a competent contractor. Thirdly, basic credentials which it is important for contractors to set out in order to establish a good reputation for the industry are set out. Finally, the particular case of nuclear power station decommissioning is considered with reference to the size of the market, the pioneering knowledge to be gained from the decommissioning of the Windscale Advanced Gas-cooled Reactor, private sector involvement and the special techniques required. (U.K.)

  4. Construction, Maintenance and Demolition of Nuclear Power Plants

    International Nuclear Information System (INIS)

    Smet, Camiel de

    2008-01-01

    Hilti is your reliable partner in nuclear power plant construction, maintenance and demolition worldwide. Professional advice and innovative solutions for virtually every phase of construction and supply technologically leading products and systems to increase your productivity and help to create and maintain safe and lasting plants is offered. The solutions for nuclear power plants construction, maintenance and demolition have been employed with great success in many different countries on a wide variety of projects due in no small way to their worldwide availability. An unbroken, international exchange of experience upholds a permanent innovation process. This assures our customers that they always receive products on the very latest technological standard. This paper is not intended to cover all topics related to nuclear power plants. The idea is more to give a kind of an overview. The paper covers briefly the following topics: safety (corrosion and fire), fastenings, measuring and finally decommissioning of nuclear power plants. (author)

  5. 304 Concretion facility closure plan

    International Nuclear Information System (INIS)

    1990-04-01

    The Hanford Site, located northwest of Richland, Washington, houses reactors, chemical-separation systems, and related facilities used for the production of special nuclear materials. The 300 Area of the Hanford Site contains reactor fuel manufacturing facilities and several research and development laboratories. Recyclable scrap uranium Zircaloy-2 and copper silicon alloy, uranium-titanium alloy, beryllium/Zircaloy-2 alloy, and Zircaloy-2 chips and fines were secured in concrete billets in the 304 Concretion Facility, located in the 300 Area. The beryllium/Zircaloy-2 alloy and Zircaloy-2 chips and fines are designated as low-level radioactive mixed waste (LLRMW) with the characteristic of ignitability. The concretion process reduced the ignitability of the fines and chips for safe storage and shipment. This process has been discontinued and the 304 Concretion Facility is now undergoing closure as defined in the Resource Conservation and Recovery Act of 1976 (RCRA). This closure plan presents a description of the facility, the history of materials and wastes managed, and the procedures that will be followed to close the 304 Concretion Facility (304 Facility). Clean closure of the 304 Facility is the proposed method for closure of the facility. Justification for this proposal is presented. 15 refs., 22 figs., 4 tabs

  6. CIRSE Vascular Closure Device Registry

    Science.gov (United States)

    Müller-Hülsbeck, Stefan; Libicher, Martin; Atar, Eli; Trentmann, Jens; Goffette, Pierre; Borggrefe, Jan; Zeleňák, Kamil; Hooijboer, Pieter; Belli, Anna-Maria

    2010-01-01

    Purpose Vascular closure devices are routinely used after many vascular interventional radiology procedures. However, there have been no major multicenter studies to assess the safety and effectiveness of the routine use of closure devices in interventional radiology. Methods The CIRSE registry of closure devices with an anchor and a plug started in January 2009 and ended in August 2009. A total of 1,107 patients were included in the registry. Results Deployment success was 97.2%. Deployment failure specified to access type was 8.8% [95% confidence interval (95% CI) 5.0–14.5] for antegrade access and 1.8% (95% CI 1.1–2.9) for retrograde access (P = 0.001). There was no difference in deployment failure related to local PVD at the access site. Calcification was a reason for deployment failure in only 5.9 cm, and two vessel occlusions. Conclusion The conclusion of this registry of closure devices with an anchor and a plug is that the use of this device in interventional radiology procedures is safe, with a low incidence of serious access site complications. There seems to be no difference in complications between antegrade and retrograde access and other parameters. PMID:20981425

  7. Mitigation of Hexavalent Chromium in Storm Water Resulting from Demolition of Large Concrete Structure at the East Tennessee Technology Park - 12286

    Energy Technology Data Exchange (ETDEWEB)

    Britto, Ronnie; Brown, Bridget; Hale, Timothy B.; Hensley, Janice L.; Johnson, Robert T.; Patel, Madhu [Tetra Tech, Inc. (United States); Emery, Jerry A. [Energy Solutions, Inc. (United States); Gaston, Clyde [LATA-SHARP Remediation Services - LSRS (United States); Queen, David C. [U.S. DOE-ORO (United States)

    2012-07-01

    American Recovery and Reinvestment Act (ARRA) funding was provided to supplement the environmental management program at several DOE sites, including the East Tennessee Technology Park (ETTP) in Oak Ridge, Tennessee. Demolition of the ETTP K-33 Building, the largest building to be demolished to date in Oak Ridge, was awarded to LSRS in FY-2010 under the ARRA program. The K-33 building was an 82 foot tall 2-story structure covering approximately 32 acres. Once this massive building was brought down to the ground, the debris was segregated and consolidated into piles of concrete rubble and steel across the remaining pad. The process of demolishing the building, tracking across concrete debris with heavy equipment, and stockpiling the concrete rubble caused it to become pulverized. During and after storm events, hexavalent chromium leached from the residual cement present in the large quantities of concrete. Storm water control measures were present to preclude migration of contaminants off-site, but these control measures were not designed to control hexavalent chromium dissolved in storm water from reaching nearby receiving water. The following was implemented to mitigate hexavalent chromium in storm water: - Steel wool was distributed around K-33 site catch basins and in water pools as an initial step in addressing hexavalent chromium. - Since the piles of concrete were too massive and unsafe to tarp, they were placed into windrows in an effort to reduce total surface area. - A Hach colorimetric field meter was acquired by the K-33 project to provide realtime results of hexavalent chromium in site surface water. - Three hexavalent chromium treatment systems were installed at three separate catch basins that receive integrated storm water flow from the K-33 site. Sodium bisulfite is being used as a reducing agent for the immobilization of hexavalent chromium while also assisting in lowering pH. Concentrations initially were 310 - 474 ppb of hexavalent chromium in

  8. Wound infection following stoma takedown: primary skin closure versus subcuticular purse-string suture.

    Science.gov (United States)

    Marquez, Thao T; Christoforidis, Dimitrios; Abraham, Anasooya; Madoff, Robert D; Rothenberger, David A

    2010-12-01

    Stoma closure has been associated with a high rate of surgical site infection (SSI) and the ideal stoma-site skin closure technique is still debated. The aim of this study was to compare the rate of SSI following primary skin closure (PC) versus a skin-approximating, subcuticular purse-string closure (APS). All consecutive patients undergoing stoma closure between 2002 and 2007 by two surgeons at a single tertiary-care institution were retrospectively assessed. Patients who had a new stoma created at the same site or those without wound closure were excluded. The end point was SSI, determined according to current CDC guidelines, at the stoma closure site and/or the midline laparotomy incision. There were 61 patients in the PC group (surgeon A: 58 of 61) and 17 in the APS group (surgeon B: 16 of 17). The two groups were similar in baseline and intraoperative characteristics, except that patients in the PC group were more often diagnosed with benign disease (p = 0.0156) and more often had a stapled anastomosis (p = 0.002). The overall SSI rate was 14 of 78 (18%). All SSIs occurred in the PC group (14 of 61 vs. 0 of 17, p = 0.03). Our study suggests that a skin-approximating closure with a subcuticular purse-string of the stoma site leads to less SSI than a primary closure. Randomized studies are needed to confirm our findings and assess additional end points such as healing time, cost, and patient satisfaction.

  9. A BIM-based system for demolition and renovation waste estimation and planning.

    Science.gov (United States)

    Cheng, Jack C P; Ma, Lauren Y H

    2013-06-01

    Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C&D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D&R) works and the growing amount of D&R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D&R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results could provide alerts to contractors ahead of time at project planning stage. This paper also presents an example scenario with a 47-floor residential building in Hong Kong to demonstrate our D&R waste estimation and planning system. As the BIM technology has been increasingly adopted in the architectural, engineering and construction industry

  10. Use of demolition residues construction in soil-lime bricks

    International Nuclear Information System (INIS)

    Figueiredo, S.S.; Silva, C.G.; Silva, I.A.; Neves, G.A.

    2011-01-01

    Besides being responsible for several environmental damage caused by its residues, the construction industry is also considered the greatest natural resources consumer. When finely ground, such residues can exhibit cementing properties, which may replace part of the lime used in the manufacture of soil-lime bricks. This study aimed to verify the viability of using demolition residues (DR) in soil-lime bricks without structural function. For this, test specimens were prepared using mixes in a 1:10 ratio of lime:soil and embedding residue in partial replacement of lime in the proportions of 25%, 50% and 75%. The test specimens were submitted to curing periods of 28 and 52 days, then it was determined the compression strength. The results showed that when embedded on moderate percentages, demolition residues construction can be used in the production of soil-lime bricks. (author)

  11. Closure report for CAU 339: Area 12 Fleet Operations steam-cleaning discharge area, Nevada Test Site

    International Nuclear Information System (INIS)

    1997-12-01

    This Closure Report (CR) provides documentation of the completed corrective action at the Area 12 Fleet Operations site located in the southeast portion of the Area 12 Camp at the Nevada Test Site (NTS). Field work was performed in July 1997 as outlined in the Corrective Action Plan (CAP). The CAP was approved by the Nevada Division of Environmental Protection (NDEP) in June 1997. This site is identified in the Federal Facility Agreement and Consent Order (FFACO) as Corrective Action Site (CAS) Number 12-19-01 and is the only CAS in Corrective Action Unit (CAU) 339. The former Area 12 Fleet Operations Building 12-16 functioned as a maintenance facility for light- and heavy-duty vehicles from approximately 1965 to January 1993. Services performed at the site included steam-cleaning, tire service, and preventative maintenance on vehicles and equipment. Past activities impacted the former steam-cleaning discharge area with volatile organic compounds (VOCs) and total petroleum hydrocarbons (TPH) as oil

  12. Assessing metal contamination from construction and demolition (C&D) waste used to infill wetlands: using Deroceras reticulatum (Mollusca: Gastropoda).

    Science.gov (United States)

    Staunton, John A; Mc Donnell, Rory J; Gormally, Michael J; Williams, Chris D; Henry, Tiernan; Morrison, Liam

    2014-11-01

    Large quantities of construction and demolition waste (C&D) are produced globally every year, with little known about potential environmental impacts. In the present study, the slug, Deroceras reticulatum (Mollusca: Gastropoda) was used as the first biomonitor of metals (Ag, As, Ba, Cd, Co, Cr, Cu, Mn, Mo, Ni, Pb, Sb, Se, Ti, Tl, V and Zn) on wetlands post infilling with construction and demolition (C&D) waste. The bioaccumulation of As, Ba, Cd, Co, Sb, Se and Tl were found to be significantly elevated in slugs collected on C&D waste when compared to unimproved pastures (control sites), while Mo, Se and Sr had significantly higher concentrations in slugs collected on C&D waste when compared to known contaminated sites (mining locations), indicating the potential hazardous nature of C&D waste to biota. Identifying exact sources for these metals within the waste can be problematic, due to its heterogenic nature. Biomonitors are a useful tool for future monitoring and impact studies, facilitating policy makers and regulations in other countries regarding C&D waste infill. In addition, improving separation of C&D waste to allow increased reuse and recycling is likely to be effective in reducing the volume of waste being used as infill, subsequently decreasing potential metal contamination.

  13. Closure Report for Corrective Action Unit 135: Areas 25 Underground Storage Tanks, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    D. H. Cox

    2001-06-01

    Corrective Action Unit (CAU) 135, Area 25 Underground Storage Tanks, was closed in accordance with the approved Corrective Action Plan (DOE/NV, 2000). CAU 135 consists of three Corrective Action Sites (CAS). Two of these CAS's were identified in the Corrective Action Investigation Data Quality Objective meeting as being improperly identified as underground storage tanks. CAS 25-02-03 identified as the Deluge Valve Pit was actually an underground electrical vault and CAS 25-02-10 identified as an Underground Storage Tank was actually a former above ground storage tank filled with demineralized water. Both of these CAS's are recommended for a no further action closure. CAS 25-02-01 the Underground Storage Tanks commonly referred to as the Engine Maintenance Assembly and Disassembly Waste Holdup Tanks and Vault was closed by decontaminating the vault structure and conducting a radiological verification survey to document compliance with the Nevada Test Site unrestricted use release criteria. The Area 25 Underground Storage Tanks, (CAS 25-02-01), referred to as the Engine Maintenance, Assembly, and Disassembly (E-MAD) Waste Holdup Tanks and Vault, were used to receive liquid waste from all of the radioactive and cell service area drains at the E-MAD Facility. Based on the results of the Corrective Action Investigation conducted in June 1999, discussed in ''The Corrective Action Investigation Plan for Corrective Action Unit 135: Area 25 Underground Storage Tanks, Nevada Test Site, Nevada'' (DOE/NV, 199a), one sample from the radiological survey of the concrete vault interior exceeded radionuclide preliminary action levels. The analytes from the sediment samples exceeded the preliminary action levels for polychlorinated biphenyls, Resource Conservation and Recovery Act metals, total petroleum hydrocarbons as diesel-range organics, and radionuclides. The CAU 135 closure activities consisted of scabbling radiological ''hot spots

  14. Energy savings from housing: Ineffective renovation subsidies vs efficient demolition and reconstruction incentives

    International Nuclear Information System (INIS)

    Dubois, Maarten; Allacker, Karen

    2015-01-01

    Energy savings in the housing sector are key to reduce global greenhouse gas emissions. Policies to incentivize energy savings are however disparate between countries. Taking into account environmental aspects and consumer surplus, the paper uses a stylized economic model to assess the effectiveness and efficiency of three economic instruments: subsidies for renovation, subsidies for demolition and reconstruction projects and subsidies for building new houses on virgin land. The assessment also relates to differentiated value added taxes and other financial incentives such as green loans. In a counter-intuitive way, the model highlights that subsidies for renovations with minor energy gains worsen the overall energy consumption of housing due to the inducement of lock-ins with energy inefficient houses. Structural changes are needed in the use of policy instruments. First, commonly applied support schemes for renovations with minor energy savings should be abolished. Second, scarce public resources should incentivize deep renovation and demolition and reconstruction. Finally, taxes should apply on the use of virgin land to persuade households with a high willingness to pay for a new house, to invest in demolition and reconstruction. - Highlights: • Renovation subsidies worsen overall energy consumption of housing. • Renovation induces a lock-in with energy inefficient houses. • Renovation subsidies should be abolished or structurally reformed. • Policy should incentivize demolition and reconstruction projects. • Building on virgin land should be taxed.

  15. Corrective Action Decision Document/Closure Report for Corrective Action Unit 551: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No.: 1

    Energy Technology Data Exchange (ETDEWEB)

    Wickline, Alfred

    2006-11-01

    This Corrective Action Decision Document (CADD)/Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 551, Area 12 Muckpiles, Nevada Test Site (NTS), Nevada. The corrective actions proposed in this document are in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada, U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 551 is comprised of the four Corrective Action Sites (CASs) that are shown on Figure 1-2 and listed below: CAS 12-01-09, Aboveground Storage Tank and Stain; CAS 12-06-05, U-12b Muckpile; CAS 12-06-07, Muckpile; and CAS 12-06-08, Muckpile. A detailed discussion of the history of this CAU is presented in the ''Corrective Action Investigation Plan (CAIP) for Corrective Action Unit 551: Area 12 Muckpiles'' (NNSA/NSO, 2004). This CADD/CR provides justification for the closure of CAU 551 in place with administrative controls. This justification is based upon process knowledge and the results of the investigative activities conducted in accordance with the CAIP (NNSA/NSO, 2004). The CAIP provides information relating to the history, planning, and scope of the investigation; therefore, this information will not be repeated in the CADD/CR. Corrective Action Unit 551, Area 12 Muckpiles, consists of four inactive sites located in the southwestern portion of Area 12. The four CAU 551 sites consist of three muckpiles, and an aboveground storage tank (AST) and stain. The CAU 551 sites were all used during underground nuclear testing at the B-, C-, D- and F-Tunnels in the late 1950s and early 1960s and have mostly remained inactive since that period.

  16. Corrective Action Decision Document/Closure Report for Corrective Action Unit 551: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No.: 1

    International Nuclear Information System (INIS)

    Wickline, Alfred

    2006-01-01

    This Corrective Action Decision Document (CADD)/Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 551, Area 12 Muckpiles, Nevada Test Site (NTS), Nevada. The corrective actions proposed in this document are in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada, U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 551 is comprised of the four Corrective Action Sites (CASs) that are shown on Figure 1-2 and listed below: CAS 12-01-09, Aboveground Storage Tank and Stain; CAS 12-06-05, U-12b Muckpile; CAS 12-06-07, Muckpile; and CAS 12-06-08, Muckpile. A detailed discussion of the history of this CAU is presented in the ''Corrective Action Investigation Plan (CAIP) for Corrective Action Unit 551: Area 12 Muckpiles'' (NNSA/NSO, 2004). This CADD/CR provides justification for the closure of CAU 551 in place with administrative controls. This justification is based upon process knowledge and the results of the investigative activities conducted in accordance with the CAIP (NNSA/NSO, 2004). The CAIP provides information relating to the history, planning, and scope of the investigation; therefore, this information will not be repeated in the CADD/CR. Corrective Action Unit 551, Area 12 Muckpiles, consists of four inactive sites located in the southwestern portion of Area 12. The four CAU 551 sites consist of three muckpiles, and an aboveground storage tank (AST) and stain. The CAU 551 sites were all used during underground nuclear testing at the B-, C-, D- and F-Tunnels in the late 1950s and early 1960s and have mostly remained inactive since that period

  17. Performance Assessment/Composite Analysis Modeling to Support a Holistic Strategy for the Closure of F Area, a Large Nuclear Complex at the Savannah River Site

    International Nuclear Information System (INIS)

    COOK, JAMES

    2004-01-01

    A performance-based approach is being used at the Savannah River Site to close the F area Complex. F Area consists of a number of large industrial facilities including plutonium separations, uranium fuel fabrication, tanks for storing high level waste and a number of smaller operations. A major part of the overall closure strategy is the use of techniques derived from the Performance Assessment and Composite Analysis requirements for low level waste disposal at DOE sites. This process will provide a means of demonstrating the basis for deactivation, decommissioning and closure decisions to management, stakeholders and regulators

  18. Ambivalence in Place Attachment : The Lived Experiences of Residents in Declining Neighbourhoods Facing Demolition in Shenyang, China

    NARCIS (Netherlands)

    Li, X.; Kleinhans, R.J.; van Ham, M.

    This paper investigates the place attachment of residents in declining neighbourhoods that are facing demolition in Shenyang, China. Through in-depth interviews with homeowners living in danwei communities, or urban villages, at the pre-demolition phase, this paper reveals the strong connection

  19. Cleanups In My Community (CIMC) - Base Realignment and Closure (BRAC) Superfund Sites, National Layer

    Science.gov (United States)

    This data layer provides access to Base Realignment and Closure (BRAC) Superfund Sites as part of the CIMC web service. EPA works with DoD to facilitate the reuse and redevelopment of BRAC federal properties. When the BRAC program began in the early 1990s, EPA worked with DoD and the states to identify uncontaminated areas and these parcels were immediately made available for reuse. Since then EPA has worked with DoD to clean up the contaminated portions of bases. These are usually parcels that were training ranges, landfills, maintenance facilities and other past waste-disposal areas. Superfund is a program administered by the EPA to locate, investigate, and clean up worst hazardous waste sites throughout the United States. EPA administers the Superfund program in cooperation with individual states and tribal governments. These sites include abandoned warehouses, manufacturing facilities, processing plants, and landfills - the key word here being abandoned.This data layer shows Superfund Sites that are located at BRAC Federal Facilities. Additional Superfund sites and other BRAC sites (those that are not Superfund sites) are included in other data layers as part of this web service.BRAC Superfund Sites shown in this web service are derived from the epa.gov website and include links to the relevant web pages within the attribute table. Data about BRAC Superfund Sites are located on their own EPA web pages, and CIMC links to those pages. The CIMC web service

  20. Responding To Changes in the Decommissioning Plans for Demolition of a Former Active Handling Building at The United Kingdom Atomic Energy Establishment Winfrith

    International Nuclear Information System (INIS)

    Brown, N.; Parkinson, S.J.; Cornell, R.M.; Staples, A.T.

    2006-01-01

    The full decommissioning of the former Active Handling Building A59 at Winfrith in Dorset is being carried out by RWE NUKEM Limited under contract from the site owners and nuclear site licence holder, United Kingdom Atomic Energy Authority (UKAEA). Following recent government changes, the United Kingdom's Nuclear Decommissioning Authority (NDA) has now set up contracts with UKAEA for delivery of the site clean-up programme. The building contains two heavily shielded suites of caves originally used to carry out remote examination of irradiated nuclear fuel elements together with other supporting facilities. The original intention was to demolish the caves ahead of the building but after detailed consideration it was concluded that demolition of the building in advance of the caves was more operationally effective. As a result, the original decommissioning plan had to be reworked to reflect these changes. The paper briefly explains how this situation arose and the means by which the problems experienced were overcome by a complete revision to the decommissioning programme. The updated plan has been adopted by UKAEA and work is now proceeding apace to clear the building of redundant items, to complete decontamination of all remaining areas and facilities and to carry out detailed radiological surveys to confirm that the building structure is clean and ready for demolition. Both cave lines have been completely decontaminated to low residual levels of activity and are essentially ready for controlled demolition. This paper describes some of the significant tasks undertaken during the past year with particular reference to the decommissioning techniques that gave the greatest success and the limitations of others originally considered. Some of these processes were aimed at minimising the volume of low level waste (LLW) generated by using standard off-the-shelf equipment to remove contamination from ∼5 Ton concrete blocks recovered from both cave line structures. A

  1. Does Disposing of Construction and Demolition Debris in Unlined Landfills Impact Groundwater Quality? Evidence from 91 Landfill Sites in Florida.

    Science.gov (United States)

    Powell, Jon T; Jain, Pradeep; Smith, Justin; Townsend, Timothy G; Tolaymat, Thabet M

    2015-08-04

    More than 1,500 construction and demolition debris (CDD) landfills operate in the United States (U.S.), and U.S. federal regulations do not require containment features such as low-permeability liners and leachate collection systems for these facilities. Here we evaluate groundwater quality from samples collected in groundwater monitoring networks at 91 unlined, permitted CDD landfills in Florida, U.S. A total of 460,504 groundwater sample results were analyzed, with a median of 10 years of quarterly or semiannual monitoring data per site including more than 400 different chemical constituents. Downgradient concentrations of total dissolved solids, sulfate, chloride, iron, ammonia-nitrogen, and aluminum were greater than upgradient concentrations (p < 0.05). At downgradient wells where sulfate concentrations were greater than 150 mg/L (approximately 10% of the maximum dissolved sulfate concentration in water, which suggests the presence of leachate from the landfill), iron and arsenic were detected in 91% and 43% of samples, with median concentrations of 1,900 μg/L and 11 μg/L, respectively. These results show that although health-based standards can be exceeded at unlined CDD landfills, the magnitude of detected chemical concentrations is generally small and reflective of leached minerals from components (wood, concrete, and gypsum drywall) that comprise the bulk of discarded CDD by mass.

  2. Corrective Action Decision Document/Closure Report for Corrective Action Unit 478: Area 12 T-Tunnel Ponds, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 478, Area 12 T-Tunnel Ponds. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 478 is comprised of one corrective action site (CAS): • 12-23-01, Ponds (5) RAD Area The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 478.

  3. Corrective Action Decision Document/Closure Report for Corrective Action Unit 559: T Tunnel Compressor/Blower Pad, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 559, T-Tunnel Compressor/Blower Pad. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Corrective Action Unit 559 is comprised of one Corrective Action Site (CAS): • 12-25-13, Oil Stained Soil and Concrete The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 559.

  4. Project Management Approach to Transition of the Miamisburg Closure Project From Environmental Cleanup to Post-Closure Operations

    International Nuclear Information System (INIS)

    Carpenter, C.P.; Marks, M.L.; Smiley, S.L.; Gallaher, D.M.; Williams, K.D.

    2006-01-01

    The U.S. Department of Energy (DOE) used a project management approach to transition the Miamisburg Closure Project from cleanup by the Office of Environmental Management (EM) to post-closure operations by the Office of Legacy Management (LM). Two primary DOE orders were used to guide the site transition: DOE Order 430.1B, Real Property Asset Management, for assessment and disposition of real property assets and DOE Order 413.3, Program and Project Management for Acquisition of Capital Assets, for project closeout of environmental cleanup activities and project transition of post-closure activities. To effectively manage these multiple policy requirements, DOE chose to manage the Miamisburg Closure Project as a project under a cross-member transitional team using representatives from four principal organizations: DOE-LM, the LM contractor S.M. Stoller Corporation, DOE-EM, and the EM contractor CH2M Hill Mound Inc. The mission of LM is to manage the Department's post-transition responsibilities and long-term care of legacy liabilities and to ensure the future protection of human health and the environment for cleanup sites after the EM has completed its cleanup activities. (authors)

  5. Post-Closure Inspection Report for Corrective Action Unit 92: Area 6 Decon Pond Facility, Nevada Test Site, Nevada, for Calendar Year 2006

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    This Post-Closure Inspection Report provides an analysis and summary of inspections for Corrective Action Unit (CAU) 92, Area 6 Decon Pond Facility. CAU 92 was closed according to the ''Resource Conservation and Recovery Act'' (RCRA) Part B Operational Permit (Nevada Division of Environmental Protection [NDEP], 1995) and the ''Federal Facility Agreement and Consent Order'' (FFACO) of 1996 (FFACO, 1996). Closure activities were completed on February 16, 1999, and the Closure Report (U.S. Department of Energy, Nevada Operations Office, 1999) was approved and a Notice of Completion issued by NDEP on May 11, 1999. CAU 92 consists of two Corrective Action Sites (CASs), CAS 06-04-01, Decon Pad Oil/Water Separator; and CAS 06-05-02, Decontamination Pond (RCRA). Both CASs have use restrictions; however, only CAS 06-05-02 requires post-closure inspections. Visual inspections of the cover and fencing at CAS 06-05-02 are performed quarterly. Additional inspections are conducted if precipitation occurs in excess of 1.28 centimeters (cm) (0.50 inches [in.]) in a 24-hour period. This report covers calendar year 2006. Quarterly site inspections were performed in March, June, September, and December of 2006. All observations indicated the continued integrity of the unit. No issues or concerns were noted, and no corrective actions were necessary. Copies of the inspection checklists and field notes completed during each inspection are included in Appendix A of this report, and photographs taken during the site inspections are included in Appendix B of this report. One additional inspection was performed after a precipitation event that exceeded 1.28 cm (0.50 in.) within a 24-hour period during 2006. No significant changes in site conditions were noted during this inspection, and no corrective actions were necessary. A copy of the inspection checklist and field notes completed during this additional inspection is included in Appendix A of this report. Precipitation records for 2006

  6. 48 CFR 52.249-3 - Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).

    Science.gov (United States)

    2010-10-01

    ... Convenience of the Government (Dismantling, Demolition, or Removal of Improvements). 52.249-3 Section 52.249-3... Convenience of the Government (Dismantling, Demolition, or Removal of Improvements). As prescribed in 49.502(b)(2), insert the following clause: Termination for Convenience of the Government (Dismantling...

  7. Demolition of Building 12, an old plutonium filter facility

    International Nuclear Information System (INIS)

    Christensen, E.L.; Garde, R.; Valentine, A.M.

    1975-01-01

    This report discusses the decommissioning and disposal of a plutonium-contaminated air filter facility that provided ventilation for the main plutonium processing plant at Los Alamos from 1945 until 1973. The health physics, waste management, and environmental aspects of the demolition are also discussed

  8. Housekeeping Closure Report for Corrective Action Unit 119: Storage Tanks, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2000-01-01

    The Federal Facility Agreement and Consent Order was entered into by the State of Nevada, US Department of Energy, and US Department of Defense to identify sites of potential historical contamination and implement corrective actions based on public health and environmental considerations. The facilities subject to this agreement include the Nevada Test Site (NTS), parts of the Tonopah Test Range, parts to the Nellis Air Force Range, the Central Nevada Test Area, and the Project Shoal Area. Corrective Action Sites (CASs) are areas potentially requiring corrective actions and may include solid waste management units, individual disposal, or release sites. Based on geography, technical similarity, agency responsibility, or other appropriate reasons, CASs are grouped together into Corrective Action Units (CAUs) for the purpose of determining appropriate corrective actions. This report contains the Closure Verification Forms for cleanup activities that were performed at 19 CASs with in CAU 119 on the NTS. The form for each CAS provides the location, directions to the site, general description, and photographs of the site before and after cleanup activities. Activities included verification of the prior removal of both aboveground and underground gas/oil storage tanks, gas sampling tanks, pressure fuel tanks, tank stands, trailers, debris, and other material. Based on these former activities, no further action is required at these CASs

  9. A standardized perioperative surgical site infection care process among children with stoma closure: a before-after study.

    Science.gov (United States)

    Porras-Hernandez, Juan; Bracho-Blanchet, Eduardo; Tovilla-Mercado, Jose; Vilar-Compte, Diana; Nieto-Zermeño, Jaime; Davila-Perez, Roberto; Teyssier-Morales, Gustavo; Lule-Dominguez, Martha

    2008-10-01

    We report on the effectiveness of a standardized perioperative care process for lowering surgical site infection (SSI) rates among children with stoma closure at a tertiary-care public pediatric teaching hospital in Mexico City. All consecutive children with stoma closure operated on between November 2003 and October 2005 were prospectively followed for 30 days postoperatively. We conducted a before-after study to evaluate standardized perioperative bowel- and abdominal-wall care process results on SSI rates. Seventy-one patients were operated on, and all completed follow-up. SSI rates declined from 42.8% (12/28) before to 13.9% (6/43) after the standardization procedure (relative risk (RR) = 3.1; 95% confidence interval (CI) = 1.3-7.2; p = 0.006). SSI independently associated risk factors comprised peristomal skin inflammation >3 mm (odds ratio (OR) = 9.6; 95% CI = 1.8-49.6; p = 0.007) and intraoperative complications (OR = 13.3; 95% CI = 1.4-127.2; p = 0.02). Being operated on during the after-study period was shown to be a protective factor against SSI (OR = 0.2; 95% CI = 0.4-0.97; p = 0.04). Standardization was able to reduce SSI rates threefold in children with stoma closure in a short period of time.

  10. Post-Closure Report for Closed Resource Conservation and Recovery Act Corrective Action Units, Nevada National Security Site, Nevada, for Fiscal Year 2014

    Energy Technology Data Exchange (ETDEWEB)

    Silvas, Alissa J. [Nevada Field Office, Las Vegas, NV (United States)

    2015-01-01

    This report serves as the combined annual report for post-closure activities for several Corrective Action Units (CAUs). The locations of the sites are shown in Figure 1. This report covers fiscal year 2014 (October 2013–September 2014). The post-closure requirements for these sites are described in Resource Conservation and Recovery Act Permit Number NEV HW0101 and summarized in each CAU-specific section in Section 1.0 of this report. The results of the inspections, a summary of maintenance activities, and an evaluation of monitoring data are presented in this report. Site inspections are conducted semiannually at CAUs 90 and 91 and quarterly at CAUs 92, 110, 111, and 112. Additional inspections are conducted at CAU 92 if precipitation occurs in excess of 0.50 inches (in.) in a 24-hour period and at CAU 111 if precipitation occurs in excess of 1.0 in. in a 24-hour period. Inspections include an evaluation of the condition of the units, including covers, fences, signs, gates, and locks. In addition to visual inspections, soil moisture monitoring, vegetation evaluations, and subsidence surveys are conducted at CAU 110. At CAU 111, soil moisture monitoring, vegetation evaluations, subsidence surveys, direct radiation monitoring, air monitoring, radon flux monitoring, and groundwater monitoring are conducted. The results of the vegetation surveys and an analysis of the soil moisture monitoring data at CAU 110 are presented in this report. Results of additional monitoring at CAU 111 are documented annually in the Nevada National Security Site Waste Management Monitoring Report Area 3 and Area 5 Radioactive Waste Management Sites and in the Nevada National Security Site Data Report: Groundwater Monitoring Program Area 5 Radioactive Waste Management Site, which will be prepared in approximately June 2015. All required inspections, maintenance, and monitoring were conducted in accordance with the post-closure requirements of the permit. It is recommended to continue

  11. CRITICAL ASSUMPTIONS IN THE F-TANK FARM CLOSURE OPERATIONAL DOCUMENTATION REGARDING WASTE TANK INTERNAL CONFIGURATIONS

    Energy Technology Data Exchange (ETDEWEB)

    Hommel, S.; Fountain, D.

    2012-03-28

    The intent of this document is to provide clarification of critical assumptions regarding the internal configurations of liquid waste tanks at operational closure, with respect to F-Tank Farm (FTF) closure documentation. For the purposes of this document, FTF closure documentation includes: (1) Performance Assessment for the F-Tank Farm at the Savannah River Site (hereafter referred to as the FTF PA) (SRS-REG-2007-00002), (2) Basis for Section 3116 Determination for Closure of F-Tank Farm at the Savannah River Site (DOE/SRS-WD-2012-001), (3) Tier 1 Closure Plan for the F-Area Waste Tank Systems at the Savannah River Site (SRR-CWDA-2010-00147), (4) F-Tank Farm Tanks 18 and 19 DOE Manual 435.1-1 Tier 2 Closure Plan Savannah River Site (SRR-CWDA-2011-00015), (5) Industrial Wastewater Closure Module for the Liquid Waste Tanks 18 and 19 (SRRCWDA-2010-00003), and (6) Tank 18/Tank 19 Special Analysis for the Performance Assessment for the F-Tank Farm at the Savannah River Site (hereafter referred to as the Tank 18/Tank 19 Special Analysis) (SRR-CWDA-2010-00124). Note that the first three FTF closure documents listed apply to the entire FTF, whereas the last three FTF closure documents listed are specific to Tanks 18 and 19. These two waste tanks are expected to be the first two tanks to be grouted and operationally closed under the current suite of FTF closure documents and many of the assumptions and approaches that apply to these two tanks are also applicable to the other FTF waste tanks and operational closure processes.

  12. Closure Report for Corrective Action Unit 145: Wells and Storage Holes, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2008-01-01

    The purpose of this Closure Report is to provide a summary of the completed closure activities, to document waste disposal, and to present information confirming that the remediation goals were met. The closure alternatives consisted of closure in place with administrative controls for one CAS, and no further action with implementation of best management practices (BMPs) for the remaining five CASs

  13. Repository Closure and Sealing Approach

    International Nuclear Information System (INIS)

    A.T. Watkins

    2000-01-01

    The scope of this analysis will be to develop the conceptual design of the closure seals and their locations in the Subsurface Facilities. The design will be based on the recently established program requirements for transitioning to the Site Recommendation (SR) design as outlined by ''Approach to Implementing the Site Recommendation Baseline'' (Stroupe 2000) and the ''Monitored Geologic Repository Project Description Document'' (CRWMS M andO 1999b). The objective of this analysis will be to assist in providing a description for the Subsurface Facilities System Description Document, Section 2 and finally to document any conclusions reached in order to contribute and provide support to the SR. This analysis is at a conceptual level and is considered adequate to support the SR design. The final closure barriers and seals for the ventilation shafts, and the north and south ramps will require these openings to be permanently sealed to limit excessive air and water inflows and prevent human intrusion. The major tasks identified with closure in this analysis are: (1) Developing the overall subsurface seal layout and identifying design and operational interfaces for the Subsurface Facilities. (2) Summarizing the general site conditions and general rock characteristic with respect to seal location and describing the seal selected. (3) Identify seal construction materials, methodology of construction and strategic locations including design of the seal and plugs. (4) Discussing methods to prevent human intrusion

  14. Modeling end-of-life pathways of construction and demolition debris in the United States (poster for LCM 2017)

    Science.gov (United States)

    In 2013, the United States generated 530 million tons of construction and demolition debris (CDD), 90% of which was related to demolition. Despite this major contribution to national waste streams, Life Cycle Assessment (LCA) studies and product declarations of buildings and buil...

  15. Quantum demolition filtering and optimal control of unstable systems.

    Science.gov (United States)

    Belavkin, V P

    2012-11-28

    A brief account of the quantum information dynamics and dynamical programming methods for optimal control of quantum unstable systems is given to both open loop and feedback control schemes corresponding respectively to deterministic and stochastic semi-Markov dynamics of stable or unstable systems. For the quantum feedback control scheme, we exploit the separation theorem of filtering and control aspects as in the usual case of quantum stable systems with non-demolition observation. This allows us to start with the Belavkin quantum filtering equation generalized to demolition observations and derive the generalized Hamilton-Jacobi-Bellman equation using standard arguments of classical control theory. This is equivalent to a Hamilton-Jacobi equation with an extra linear dissipative term if the control is restricted to Hamiltonian terms in the filtering equation. An unstable controlled qubit is considered as an example throughout the development of the formalism. Finally, we discuss optimum observation strategies to obtain a pure quantum qubit state from a mixed one.

  16. The FRJ-1 (MERLIN) research reactor: its main activity inventory has been removed by successful demolition of the reactor block

    International Nuclear Information System (INIS)

    Stahn, B.; Printz, R.; Matela, K.; Zehbe, C.; Poeppinghaus, J.; Cremer, J.

    2004-01-01

    The FRJ-1 (MERLIN) research reactor was decommissioned in 1985 after twenty-three years of operation. Demolition of the plant was begun in 1996. The article contains a survey of the demolition steps carried out so far within the framework of three partial permits. The main activity is the demolition of the reactor core structures as a precondition for subsequent measures to ensure clearance measurements of the building. The core structures are demolished which were exposed to high neutron fluxes during reactor operation and now show the highest activity and dose rate levels, except for the core internals. For demolition and disassembly of the metal structures in this part of the plant, the tools specially designed and made include a remotely operated sawing system and a pipe cutting system for internal segmentation of the beam lines. The universal demolition tool for use also above and beyond the concrete structures has been found to be a remotely controlled electrohydraulic demolition shovel. Spreading contamination in the course of the demolition work was avoided. One major reason for this success was the fact that no major airborne contamination existed at any time as a consequence of the quality of the material demolished and also of the consistent use of technical tools. While the reactor block was being demolished, an application for clearance measurement of the reactor hall and subsequent release from the scope of the Atomic Energy Act was filed as early as in mid-2003. The fourth partial permit covering these activities is expected to be issued in the spring of 2004. (orig.)

  17. Modified Brokk Demolition Machine with Remote Operator Console. Innovative Technology Summary Report

    International Nuclear Information System (INIS)

    2001-01-01

    The Low-Cost D and D System modifies a commercially available BROKK demolition system for remote viewing and long tether remote operation that provides a portable facility camera pod and interfaces with the Compact Remote Operator Console (TMS Tech ID 2180) to extend the applicability of the BROKK system to projects that require removal of the operator from the work area due to exposure to radiological, chemical, or industrial hazards. The modified BROKK has been integrated with the Compact Remote Operator Console to provide a true remotely operated low-cost D and D system applicable to a wide range of small D and D demolition tasks across the DOE complex

  18. Closure Report for Corrective Action Unit 240: Area 25 Vehicle Washdown Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Gustafason, D.L.

    2001-01-01

    The Area 25 Vehicle Washdown, Corrective Action Unit (CAU) 240, was clean-closed following the approved Corrective Action Decision Document closure alternative and in accordance with the Federal Facility Agreement and Consent Order (FFACO, 1996). The CAU consists of thee Corrective Action Sites (CASs): 25-07-01 - Vehicle Washdown Area (Propellant Pad); 25-07-02 - Vehicle Washdown Area (F and J Roads Pad); and 25-07-03 - Vehicle Washdown Station (RADSAFE Pad). Characterization activities indicated that only CAS 25-07-02 (F and J Roads Pad) contained constituents of concern (COCs) above action levels and required remediation. The COCs detected were Total Petroleum Hydrocarbons (TPH) as diesel, cesium-137, and strontium-90. The F and J Roads Pad may have been used for the decontamination of vehicles and possibly disassembled engine and reactor parts from Test Cell C. Activities occurred there during the 1960s through early 1970s. The F and J Roads Pad consisted of a 9- by 5-meter (m) (30- by 15-foot [ft]) concrete pad and a 14- by 13-m (46-by 43-ft) gravel sump. The clean-closure corrective action consisted of excavation, disposal, verification sampling, backfilling, and regrading. Closure activities began on August 21, 2000, and ended on September 19, 2000. Waste disposal activities were completed on December 12, 2000. A total of 172 cubic meters (223 cubic yards) of impacted soil was excavated and disposed. The concrete pad was also removed and disposed. Verification samples were collected from the bottom and sidewalls of the excavation and analyzed for TPH diesel and 20-minute gamma spectroscopy. The sample results indicated that all impacted soil above remediation standards was removed. The closure was completed following the approved Corrective Action Plan. All impacted waste was disposed in the Area 6 Hydrocarbon Landfill. All non-impacted debris was disposed in the Area 9 Construction Landfill and the Area 23 Sanitary Landfill

  19. Stomal Closure: Strategies to Prevent Incisional Hernia

    Science.gov (United States)

    Harries, Rhiannon L.; Torkington, Jared

    2018-01-01

    Incisional hernias following ostomy reversal occur frequently. Incisional hernias at the site of a previous stoma closure can cause significant morbidity, impaired quality of life, lead to life-threatening hernia incarceration or strangulation and result in a significant financial burden on health care systems Despite this, the evidence base on the subject is limited. Many recognised risk factors for the development of incisional hernia following ostomy reversal are related to patient factors such as age, malignancy, diabetes, COPD, hypertension and obesity, and are not easily correctable. There is a limited amount of evidence to suggest that prophylactic mesh reinforcement may be of benefit to reduce the post stoma closure incisional hernia rate but a further large scale randomised controlled trial is due to report in the near future. There appears to be weak evidence to suggest that surgeons should favour circular, or “purse-string” closure of the skin following stoma closure in order to reduce the risk of SSI, which in turn may reduce incisional hernia formation. There remains the need for further evidence in relation to suture technique, skin closure techniques, mechanical bowel preparation and oral antibiotic prescription focusing on incisional hernia development as an outcome measure. Within this review, we discuss in detail the evidence base for the risk factors for the development of, and the strategies to prevent ostomy reversal site incisional hernias. PMID:29670882

  20. Stomal Closure: Strategies to Prevent Incisional Hernia

    Directory of Open Access Journals (Sweden)

    Rhiannon L. Harries

    2018-04-01

    Full Text Available Incisional hernias following ostomy reversal occur frequently. Incisional hernias at the site of a previous stoma closure can cause significant morbidity, impaired quality of life, lead to life-threatening hernia incarceration or strangulation and result in a significant financial burden on health care systems Despite this, the evidence base on the subject is limited. Many recognised risk factors for the development of incisional hernia following ostomy reversal are related to patient factors such as age, malignancy, diabetes, COPD, hypertension and obesity, and are not easily correctable. There is a limited amount of evidence to suggest that prophylactic mesh reinforcement may be of benefit to reduce the post stoma closure incisional hernia rate but a further large scale randomised controlled trial is due to report in the near future. There appears to be weak evidence to suggest that surgeons should favour circular, or “purse-string” closure of the skin following stoma closure in order to reduce the risk of SSI, which in turn may reduce incisional hernia formation. There remains the need for further evidence in relation to suture technique, skin closure techniques, mechanical bowel preparation and oral antibiotic prescription focusing on incisional hernia development as an outcome measure. Within this review, we discuss in detail the evidence base for the risk factors for the development of, and the strategies to prevent ostomy reversal site incisional hernias.

  1. Demolition Range Noise Abatement Technique Demonstration and Evaluation for the McAlester Army Ammunition Plant; TOPICAL

    International Nuclear Information System (INIS)

    CALDERONE, JAMES J.; GARBIN H, DOUGLAS

    2001-01-01

    Public concern regarding the effects of noise generated by the detonation of excess and obsolete explosive munitions at U.S. Army demolition ranges is a continuing issue for the Army's demilitarization and disposal groups. Recent concerns of citizens living near the McAlester Army Ammunition Plant (MCAAP) in Oklahoma have lead the U.S. Army Defense Ammunition Center (DAC) to conduct a demonstration and evaluation of noise abatement techniques that could be applied to the MCAAP demolition range. With the support of the DAC, MCAAP, and Sandia National Laboratories (SNL), three types of noise abatement techniques were applied: aqueous foams, overburden (using combinations of sand beds and dirt coverings), and rubber or steel blast mats. Eight test configurations were studied and twenty-four experiments were conducted on the MCAAP demolition range in July of 2000. Instrumentation and data acquisition systems were fielded for the collection of near-field blast pressures, far-field acoustic pressures, plant boundary seismic signals, and demolition range meteorological conditions. The resulting data has been analyzed and reported, and a ranking of each technique's effects has been provided to the DAC

  2. Streamlined approach for environmental restoration closure report for Corrective Action Unit No. 456: Underground storage tank release site 23-111-1, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1998-04-01

    The underground storage tank (UST) release site 23-111-1 is located in Mercury, Nevada. The site is in Area 23 of the Nevada Test Site, (NTS) located on the north side of Building 111. The tank associated with the release was closed in place using cement grout on September 6, 1990. The tank was not closed by removal due to numerous active underground utilities, a high-voltage transformer pad, and overhead power lines. Soil samples collected below the tank bottom at the time of tank closure activities exceeded the Nevada Administrative Code Action Level of 100 milligrams per kilogram (mg/kg) for petroleum hydrocarbons. Maximum concentrations detected were 119 mg/kg. Two passive venting wells were subsequently installed at the tank ends to monitor the progress of biodegradation at the site. Quarterly air sampling from the wells was completed for approximately one year, but was discontinued since data indicated that considerable biodegradation was not occurring at the site

  3. A refined safety analysis approach for closure of the Hanford Site flammable gas unreviewed safety question

    International Nuclear Information System (INIS)

    Bratzel, D.R.

    1997-01-01

    Following a 1990 investigation into flammable gas generation, retention, and release mechanisms within the Hanford Site high-level waste tanks, personnel concluded that the existing Authorization Basis documentation did not adequately evaluate flammable gas hazards. This declaration was based primarily on the fact that personnel did not adequately consider hydrogen and nitrous oxide evolution within the material in certain waste tanks and subsequent hypothetical ignition in the development of safety documentation for the waste tanks. The US Department of Energy-Headquarters subsequently declared an Unreviewed Safety Question (USQ). Although work scope has been focused on closure of the USQ since 1990, the DOE has yet to close the USQ because of considerable uncertainty regarding essential technical parameters and associated risk. The DOE recently approved a Basis for Interim Operation to revise the Authorization Basis for managing the tank farms, however, the USQ remains open. The two fundamental requirements for closure of the flammable gas USQ are as follows: development of a defensible technical basis for existing controls; development of a process to assess the adequacy of controls as the waste tank mission progresses

  4. Corrective Action Decision Document/Closure Report for Corrective Action Unit 266: Area 25 Building 3124 Leachfield, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NNSA/NV

    2000-02-17

    This Corrective Action Decision Document/Closure Report (CADD/CR) was prepared for Corrective Action Unit (CAU) 266, Area 25 Building 3124 Leachfield, in accordance with the Federal Facility Agreement and Consent Order. Located in Area 25 at the Nevada Test Site in Nevada, CAU 266 includes Corrective Action Site (CAS) 25-05-09. The Corrective Action Decision Document and Closure Report were combined into one report because sample data collected during the corrective action investigation (CAI) indicated that contaminants of concern (COCs) were either not present in the soil, or present at concentrations not requiring corrective action. This CADD/CR identifies and rationalizes the U.S. Department of Energy, Nevada Operations Office's recommendation that no corrective action was necessary for CAU 266. From February through May 1999, CAI activities were performed as set forth in the related Corrective Action Investigation Plan. Analytes detected during the three-stage CAI of CAU 266 were evaluated against preliminary action levels (PALs) to determine COCs, and the analysis of the data generated from soil collection activities indicated the PALs were not exceeded for total volatile/semivolatile organic compounds, total petroleum hydrocarbons, polychlorinated biphenyls, total Resource Conservation and Recovery Act metals, gamma-emitting radionuclides, isotopic uranium/plutonium, and strontium-90 for any of the samples. However, COCs were identified in samples from within the septic tank and distribution box; and the isotopic americium concentrations in the two soil samples did exceed PALs. Closure activities were performed at the site to address the COCs identified in the septic tank and distribution box. Further, no use restrictions were required to be placed on CAU 266 because the CAI revealed soil contamination to be less than the 100 millirems per year limit established by DOE Order 5400.5.

  5. Corrective Action Decision Document/Closure Report for Corrective Action Unit 266: Area 25 Building 3124 Leachfield, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    2000-01-01

    This Corrective Action Decision Document/Closure Report (CADD/CR) was prepared for Corrective Action Unit (CAU) 266, Area 25 Building 3124 Leachfield, in accordance with the Federal Facility Agreement and Consent Order. Located in Area 25 at the Nevada Test Site in Nevada, CAU 266 includes Corrective Action Site (CAS) 25-05-09. The Corrective Action Decision Document and Closure Report were combined into one report because sample data collected during the corrective action investigation (CAI) indicated that contaminants of concern (COCs) were either not present in the soil, or present at concentrations not requiring corrective action. This CADD/CR identifies and rationalizes the U.S. Department of Energy, Nevada Operations Office's recommendation that no corrective action was necessary for CAU 266. From February through May 1999, CAI activities were performed as set forth in the related Corrective Action Investigation Plan. Analytes detected during the three-stage CAI of CAU 266 were evaluated against preliminary action levels (PALs) to determine COCs, and the analysis of the data generated from soil collection activities indicated the PALs were not exceeded for total volatile/semivolatile organic compounds, total petroleum hydrocarbons, polychlorinated biphenyls, total Resource Conservation and Recovery Act metals, gamma-emitting radionuclides, isotopic uranium/plutonium, and strontium-90 for any of the samples. However, COCs were identified in samples from within the septic tank and distribution box; and the isotopic americium concentrations in the two soil samples did exceed PALs. Closure activities were performed at the site to address the COCs identified in the septic tank and distribution box. Further, no use restrictions were required to be placed on CAU 266 because the CAI revealed soil contamination to be less than the 100 millirems per year limit established by DOE Order 5400.5

  6. Environmental Impacts Assessment of Recycling of Construction and Demolition Waste

    DEFF Research Database (Denmark)

    Butera, Stefania

    .e. soil and stones, concrete, asphalt and masonry, and as such it has the potential to be used as aggregate in the construction sector. A typical application is in an unbound state as filler in road structures. This practice offers evident benefits in terms of resource savings, however it might lead......Construction and demolition waste (C&DW) is waste derived from the construction, demolition and renovation of buildings and civil infrastructure. With 900 million tons generated every year in Europe, it is the largest waste stream on the continent. C&DW is mainly constituted of mineral fractions, i...... be evaluated critically.Owing to its high toxicity and significant mobility, especially at high pH levels, Cr(VI) is one of the elements of concern found in C&DW leachates. Its fate in the sub-soil below road applications was assessed experimentally, and its vertical migration was then predicted through...

  7. Interim status of closure/post-closure plan for 183-H solar evaporation basins

    International Nuclear Information System (INIS)

    1988-03-01

    This report describes a plan for decommissioning several solar evaporation basins on the Hanford reservation. The document describes procedures for sampling during decommissioning and a plan for certification of the resulting completed landfill. Additional plans deal with the training, security of the site, and post-closure monitoring

  8. Development of a prototype plan for the effective closure of a waste disposal site in Los Alamos, New Mexico

    International Nuclear Information System (INIS)

    Nyhan, J.; Barnes, F.

    1989-02-01

    The purpose of this study was to develop a prototype plan for the effective closure and stabilization of a semiarid low-level waste disposal site. This prototype plan will provide demonstrated closure techniques for a trench in a disposal site at Los Alamos based on previous shallow land burial (SLB) field research both at the Los Alamos Experimental Engineered Test Facility (EETF), and at a waste disposal area at Los Alamos. The accuracy of modeling soil water storage by two hydrologic models was tested by comparing simulation results with field measurements of soil moisture in eight experimental landfill cover systems at Waste Disposal Area B having a range of well-defined soil profiles and vegetative covers. Regression analysis showed that one of the two models tested represented soil moisture more accurately than the second model. The accuracy of modeling all of the parameters of the water balance equation was then evaluated using field data from the Integrated Systems Demonstration plots at the EETF. Optimized parameters were developed for one model to describe observed values of deep percolation, evapotranspiration, and runoff from the field plots containing an SLB trench cap configuration

  9. A change in strategy for a CERCLA Removal Action Demolition Project in progress results in overall project enhancements

    International Nuclear Information System (INIS)

    Albertin, M.; Nichols, R.M.; Edwards, D.T.

    1995-01-01

    This paper discusses changes made in a demolition project at the Fernald Environmental Management Project (FEMP), a site on the National Priorities list (NPL), owned by the Department of Energy. The project, to demolish fourteen uranium ore silos and their structure, was based on a Removal Action Work Plan, submitted and approved by the United States Environmental Protection Agency (USEPA), that integrated Comprehensive Environmental Response Compensation and Liability Act (CERCLA) requirements to remove the source of contamination and threat to public health and the environment. After the demolition contractor defaulted at 30% complete, completion of the project by the USEPA deadline was threatened. The recovery plan included re-evaluation of project documents in addition to the schedule. It was determined that re-interpretation of the removal action criteria, including design and Removal Action Work Plan, would eliminate road-blocks, and optimize resources, resulting in project completion by the original deadline even after lost-time in mobilizing another contractor. This presentation will discuss the open-quotes lessons learnedclose quotes by the project team and illustrate how simplification of construction methods resulted in enhancements to the environmental controls, improved material handing, and created a safer work environment

  10. Does demolition or refurbishment of old and inefficient homes help to increase our environmental, social and economic viability?

    Energy Technology Data Exchange (ETDEWEB)

    Power, Anne [London School of Economics, Houghton Street, London WC2A 2AE (United Kingdom); Sustainable Development Commission, Room 101, 55 Whitehall, c/o 3-8 Whitehall Place, London SW1A 2HH (United Kingdom)

    2008-12-15

    The issue of whether to demolish or refurbish older housing has been debated for over a century. It has been an active policy area since the late 1880s, when the Government first authorised the statutory demolition of insanitary slums. In the 1960s, revulsion at the scale of 'demolition blight' and new building caused a rethink, leading to a major reinvestment in inner city neighbourhoods of older housing. In the past 5 years, debate on demolition and new building has been intensified by the Government's Sustainable Communities Plan of 2003, with its proposals for large-scale clearance and building. Environmental arguments about renovating the existing stock have gained increasing prominence as people have sought to defend their communities from demolition. The evidence on whether demolition would reduce the amount of greenhouse gases we emit into the atmosphere is unclear and disputed. This paper summarises the evidence and arguments, and attempts to clarify the most realistic, achievable route to major reductions in energy use in homes. The arguments that apply to housing also apply to most other buildings and therefore to the overall built environment, which accounts for half of all carbon emissions. Three main sources of evidence have helped in the development of this paper, but there are many other studies we draw on in the discussion.

  11. Permanent Closure of MFC Biodiesel Underground Storage Tank 99ANL00013

    Energy Technology Data Exchange (ETDEWEB)

    Kerry L. Nisson

    2012-10-01

    This closure package documents the site assessment and permanent closure of the Materials and Fuels Complex biodiesel underground storage tank 99ANL00013 in accordance with the regulatory requirements established in 40 CFR 280.71, “Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks: Out-of-Service UST Systems and Closure.”

  12. A BIM-based system for demolition and renovation waste estimation and planning

    International Nuclear Information System (INIS)

    Cheng, Jack C.P.; Ma, Lauren Y.H.

    2013-01-01

    Highlights: ► We developed a waste estimation system leveraging the BIM technology. ► The system can calculate waste disposal charging fee and pick-up truck demand. ► We presented an example scenario demonstrating this system. ► Automatic, time-saving and wide applicability are the features of the system. - Abstract: Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C and D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D and R) works and the growing amount of D and R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D and R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results

  13. A BIM-based system for demolition and renovation waste estimation and planning

    Energy Technology Data Exchange (ETDEWEB)

    Cheng, Jack C.P., E-mail: cejcheng@ust.hk [Department of Civil and Environmental Engineering, The Hong Kong University of Science and Technology (Hong Kong); Ma, Lauren Y.H., E-mail: yingzi@ust.hk [Department of Civil and Environmental Engineering, The Hong Kong University of Science and Technology (Hong Kong)

    2013-06-15

    Highlights: ► We developed a waste estimation system leveraging the BIM technology. ► The system can calculate waste disposal charging fee and pick-up truck demand. ► We presented an example scenario demonstrating this system. ► Automatic, time-saving and wide applicability are the features of the system. - Abstract: Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C and D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D and R) works and the growing amount of D and R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D and R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results

  14. Citizen Contributions to the Closure of High-Level Waste (HLW) Tanks 18 and 19 at the Department of Energy's (DOE) Savannah River Site (SRS) - 13448

    Energy Technology Data Exchange (ETDEWEB)

    Lawless, W.F. [Paine College, Departments of Math and Psychology, 1235 15th Street, Augusta, GA 30901 (United States)

    2013-07-01

    Citizen involvement in DOE's decision-making for the environmental cleanup from DOE's management of its nuclear wastes across the DOE complex has had a positive effect on the cleanup of its SRS site, characterized by an acceleration of cleanup not only for the Transuranic wastes at SRS, but also for DOE's first two closures of HLW tanks, both of which occurred at SRS. The Citizens around SRS had pushed successfully for the closures of Tanks 17 and 20 in 1997, becoming the first closures of HLW tanks under regulatory guidance in the USA. However, since then, HLW tank closures ceased due to a lawsuit, the application of new tank clean-up technology, interagency squabbling between DOE and NRC over tank closure criteria, and finally and almost fatally, from budget pressures. Despite an agreement with its regulators for the closure of Tanks 18 and 19 by the end of calendar year 2012, the outlook in Fall 2011 to close these two tanks had dimmed. It was at this point that the citizens around SRS became reengaged with tank closures, helping DOE to reach its agreed upon milestone. (authors)

  15. Influence of construction and demolition waste management on the environmental impact of buildings.

    Science.gov (United States)

    Coelho, André; de Brito, Jorge

    2012-03-01

    The purpose of this study is to quantify comparable environmental impacts within a Life Cycle Analysis (LCA) perspective, for buildings in which the first (Materials) and last (End of Life) life cycle stages are adjusted to several waste/material management options. Unlike most LCAs, the approach is "top-down" rather than "bottom-up", which usually involves large amounts of data and the use of specific software applications. This approach is considered appropriate for a limited but expedient LCA designed to compare the environmental impacts of different life cycle options. Present results, based on real buildings measurements and demolition contractor activities, show that shallow, superficial, selective demolition may not result in reduced environmental impacts. Calculations actually show an increase (generally less than 5%) in most impact categories for the Materials and End of Life stages because of extra transportation needs. However, core material separation in demolition operations and its recycling and/or reuse does bring environmental benefits. A reduction of around 77% has been estimated in the climate change impact category, 57% in acidification potential and 81% in the summer smog impact (for the life cycle stages referred). Copyright © 2011 Elsevier Ltd. All rights reserved.

  16. Remaining Sites Verification Package for 132-DR-1, 1608-DR Effluent Pumping Station. Attachment to Waste Site Reclassification Form 2005-035

    International Nuclear Information System (INIS)

    Carlson, R.A.

    2005-01-01

    Radiological characterization, decommissioning and demolition of the 132-DR-1 site, 1608-DR Effluent Pumping Station was performed in 1987. The current site conditions achieve the remedial action objectives and the corresponding remedial action goals established in the Remaining Sites ROD. Residual concentrations support future land uses that can be represented by a rural-residential scenario and pose no threat to groundwater or the Columbia River based on RESRAD modeling

  17. Closure Report for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2012-02-21

    This Closure Report (CR) presents information supporting closure of the 92-Acre Area, which includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' This CR provides documentation supporting the completed corrective actions and confirmation that the closure objectives were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) (FFACO, 1996 [as amended March 2010]). Closure activities began in January 2011 and were completed in January 2012. Closure activities were conducted according to Revision 1 of the Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for the 92-Acre Area and CAU 111 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2010). The following closure activities were performed: (1) Construct an engineered evapotranspiration cover over the boreholes, trenches, and pits in the 92-Acre Area; (2) Install use restriction (UR) warning signs, concrete monuments, and subsidence survey monuments; and (3) Establish vegetation on the covers. UR documentation is included as Appendix C of this report. The post-closure plan is presented in detail in Revision 1 of the CADD/CAP for the 92-Acre Area and CAU 111, and the requirements are summarized in Section 5.2 of this document. When the next request for modification of Resource Conservation and Recovery Act Permit NEV HW0101 is submitted to the Nevada Division of Environmental Protection (NDEP), the requirements for post-closure monitoring of the 92-Acre Area will be included. NNSA/NSO requests the following: (1) A Notice of Completion from NDEP to NNSA/NSO for closure of CAU 111; and (2) The transfer of CAU 111 from Appendix III to Appendix IV, Closed Corrective Action Units, of the FFACO.

  18. Closure Report for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada

    International Nuclear Information System (INIS)

    2012-01-01

    This Closure Report (CR) presents information supporting closure of the 92-Acre Area, which includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' This CR provides documentation supporting the completed corrective actions and confirmation that the closure objectives were met. This CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) (FFACO, 1996 (as amended March 2010)). Closure activities began in January 2011 and were completed in January 2012. Closure activities were conducted according to Revision 1 of the Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for the 92-Acre Area and CAU 111 (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO), 2010). The following closure activities were performed: (1) Construct an engineered evapotranspiration cover over the boreholes, trenches, and pits in the 92-Acre Area; (2) Install use restriction (UR) warning signs, concrete monuments, and subsidence survey monuments; and (3) Establish vegetation on the covers. UR documentation is included as Appendix C of this report. The post-closure plan is presented in detail in Revision 1 of the CADD/CAP for the 92-Acre Area and CAU 111, and the requirements are summarized in Section 5.2 of this document. When the next request for modification of Resource Conservation and Recovery Act Permit NEV HW0101 is submitted to the Nevada Division of Environmental Protection (NDEP), the requirements for post-closure monitoring of the 92-Acre Area will be included. NNSA/NSO requests the following: (1) A Notice of Completion from NDEP to NNSA/NSO for closure of CAU 111; and (2) The transfer of CAU 111 from Appendix III to Appendix IV, Closed Corrective Action Units, of the FFACO.

  19. Quantifying construction and demolition waste: an analytical review.

    Science.gov (United States)

    Wu, Zezhou; Yu, Ann T W; Shen, Liyin; Liu, Guiwen

    2014-09-01

    Quantifying construction and demolition (C&D) waste generation is regarded as a prerequisite for the implementation of successful waste management. In literature, various methods have been employed to quantify the C&D waste generation at both regional and project levels. However, an integrated review that systemically describes and analyses all the existing methods has yet to be conducted. To bridge this research gap, an analytical review is conducted. Fifty-seven papers are retrieved based on a set of rigorous procedures. The characteristics of the selected papers are classified according to the following criteria - waste generation activity, estimation level and quantification methodology. Six categories of existing C&D waste quantification methodologies are identified, including site visit method, waste generation rate method, lifetime analysis method, classification system accumulation method, variables modelling method and other particular methods. A critical comparison of the identified methods is given according to their characteristics and implementation constraints. Moreover, a decision tree is proposed for aiding the selection of the most appropriate quantification method in different scenarios. Based on the analytical review, limitations of previous studies and recommendations of potential future research directions are further suggested. Copyright © 2014 Elsevier Ltd. All rights reserved.

  20. 304 Concretion Facility Closure Plan

    International Nuclear Information System (INIS)

    1991-10-01

    The Hanford Site, located northwest of Richland, Washington, houses reactors, chemical-separation systems, and related facilities used for the production of special nuclear materials. The 300 Area of the Hanford Site contains reactor fuel manufacturing facilities and several research and development laboratories. Recyclable scrap uranium with Zircaloy-2 and copper silicon allo , uranium-titanium alloy, beryllium/Zircaloy-2 alloy, and Zircaloy-2 chips and fines were secured in concrete billets (7.5-gal containers) in the 304 Concretion Facility (304 Facility), located in the 300 Area. The beryllium/Zircaloy-2 alloy and Zircaloy-2 chips and fines are designated as low-level radioactive mixed waste (LLRMW) with the characteristic of ignitability. The concretion process reduced the ignitability of the fines and chips for safe storage and shipment. This process has been discontinued and the 304 Concretion Facility is now undergoing closure as defined in the Resource Conservation and Recovery Act of 1976 (RCRA) and the Washington Administrative Code (WAC) Dangerous Waste Regulations, WAC 173-303-040 (Ecology 1991). This closure plan presents a description of the facility, the history of materials and wastes managed, and the procedures that will be followed to close the 304 Facility. The strategy for closure of the 304 Facility is presented in Section 6.0

  1. Progress report on decommissioning activities at the Fernald Environmental Management Project (FEMP) site

    International Nuclear Information System (INIS)

    1998-01-01

    The Fernald Environmental Management Project (FEMP), is located about 18 miles northwest of Cincinnati, Ohio. Between 1953 and 1989, the facility, then called the Feed Material Production Center or FMPC, produced uranium metal products used in the eventual production of weapons grade material for use by other US Department of Energy (DOE) sites. In 1989, FMPC's production was suspended by the federal government in order to focus resources on environmental restoration versus defense production. In 1992, Fluor Daniel Fernald assumed responsibility for managing all cleanup activities at the FEMP under contract to the DOE. In 1990, as part of the remediation effort, the site was divided into five operable units based on physical proximity of contaminated areas, similar amounts of types of contamination, or the potential for a similar technology to be used in cleanup activities. This report continues the outline of the decontamination and decommissioning (D and D) activities at the FEMP site Operable Unit 3 (OU3) and provides an update on the status of the decommissioning activities. OU3, the Facilities Closure and Demolition Project, involves the remediation of more than 200 uranium processing facilities. The mission of the project is to remove nuclear materials stored in these buildings, then perform the clean out of the buildings and equipment, and decontaminate and dismantle the facilities

  2. Concrete block production from construction and demolition waste in Tanzania

    NARCIS (Netherlands)

    Sabai, M.M.; Cox, M.G.D.M.; Mato, R.R.A.M.; Egmond - de Wilde De Ligny, van E.L.C.; Lichtenberg, J.J.N.

    2013-01-01

    In Tanzania, construction and demolition (C&D) waste is not recycled and knowledge on how it can be recycled especially into valuable products like building materials are still limited. This study aimed at investigating the possibility of recycling the C&D waste (mainly cementitious rubble) into

  3. The River Corridor Closure Contract How Washington Closure Hanford is Closing A Unique Department of Energy Project - 12425

    Energy Technology Data Exchange (ETDEWEB)

    Feist, E.T. [Washington Closure Hanford, 2620 Fermi Avenue, Richland, WA 99354 (United States)

    2012-07-01

    Cleanup of the Hanford River Corridor has been one of Hanford Site's top priorities since the early 1990's. This urgency is due to the proximity of hundreds of waste sites to the Columbia River and the groundwater that continues to threaten the Columbia River. In April 2005, the U.S. Department of Energy, Richland Operations Office (DOE-RL) awarded the Hanford River Corridor Closure Contract (RCCC), a cost-plus incentive-fee closure contract with a 2015 end date and first of its kind at Hanford Site, to Washington Closure Hanford (WCH), a limited-liability company owned by URS, Bechtel National, and CH2M HILL. WCH is a single-purpose company whose goal is to safely, compliantly, and efficiently accelerate cleanup in the Hanford River Corridor and reduce or eliminate future obligations to DOE-RL for maintaining long-term stewardship over the site. Accelerated performance of the work-scope while keeping a perspective on contract completion presents challenges that require proactive strategies to support the remaining work-scope through the end of the RCCC. This paper outlines the processes to address the challenges of completing work-scope while planning for contract termination. WCH is responsible for cleanup of the River Corridor 569.8 km{sup 2} (220 mi{sup 2}) of the 1,517.7 km{sup 2} (586 mi{sup 2}) Hanford Site's footprint reduction. At the end of calendar year 2011, WCH's closure implementation is well underway. Fieldwork is complete in three of the largest areas within the RCCC scope (Segments 1, 2, and 3), approximately 44.5% of the River Corridor (Figure 3). Working together, DOE-RL and WCH are in the process of completing the 'paper work' that will document the completion of the work-scope and allow DOE-RL to relieve WCH of contractual responsibilities and transition the completed areas to the Long-Term Stewardship Program, pending final action RODs. Within the next 4 years, WCH will continue to complete cleanup of the River

  4. Creation and demolition of illegal structures in Nigerian cities ...

    African Journals Online (AJOL)

    The paper examined the issue of demolition of illegal structures in Benin City. The study revealed that the poor economic condition of the country forced many landlords in the city to restructure and convert their houses into mixed uses in order to make a living. In the process many illegal structures sprang up as many ...

  5. Positive Catch & Economic Benefits of Periodic Octopus Fishery Closures: Do Effective, Narrowly Targeted Actions ‘Catalyze’ Broader Management?

    Science.gov (United States)

    Oliver, Thomas A.; Oleson, Kirsten L. L.; Ratsimbazafy, Hajanaina; Raberinary, Daniel; Benbow, Sophie; Harris, Alasdair

    2015-01-01

    Overview Eight years of octopus fishery records from southwest Madagascar reveal significant positive impacts from 36 periodic closures on: (a) fishery catches and (b) village fishery income, such that (c) economic benefits from increased landings outweigh costs of foregone catch. Closures covered ~20% of a village’s fished area and lasted 2-7 months. Fishery Catches from Each Closed Site Octopus landings and catch per unit effort (CPUE) significantly increased in the 30 days following a closure’s reopening, relative to the 30 days before a closure (landings: +718%, poctopus fishery income doubled in the 30 days after a closure, relative to 30 days before (+132%, p<0.001, n = 28). Control villages not implementing a closure showed no increase in income after “no ban” closures and modest increases after “ban” closures. Villages did not show a significant decline in income during closure events. Net Economic Benefits from Each Closed Site Landings in closure sites generated more revenue than simulated landings assuming continued open-access fishing at that site (27/36 show positive net earnings; mean +$305/closure; mean +57.7% monthly). Benefits accrued faster than local fishers’ time preferences during 17-27 of the 36 closures. High reported rates of illegal fishing during closures correlated with poor economic performance. Broader Co-Management We discuss the implications of our findings for broader co-management arrangements, particularly for catalyzing more comprehensive management. PMID:26083862

  6. Closure Report for Corrective Action Unit 127: Areas 25 and 26 Storage Tanks, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2008-02-01

    CAU 127, Areas 25 and 26 Storage Tanks, consists of twelve CASs located in Areas 25 and 26 of the NTS. The closure alternatives included no further action, clean closure, and closure in place with administrative controls. The purpose of this Closure Report is to provide a summary of the completed closure activities, documentation of waste disposal, and analytical data to confirm that the remediation goals were met.

  7. Corrective Action Decision Document/Closure Report for Corrective Action Unit 504: 16a-Tunnel Muckpile, Nevada Test Site

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 504, 16a-Tunnel Muckpile. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. Corrective Action Unit 504 is comprised of four Corrective Action Sites (CASs): • 16-06-01, Muckpile • 16-23-01, Contaminated Burial Pit • 16-23-02, Contaminated Area • 16-99-01, Concrete Construction Waste Corrective Action Site 16-23-01 is not a burial pit; it is part of CAS 16-06-01. Therefore, there is not a separate data analysis and assessment for CAS 16-23-01; it is included as part of the assessment for CAS 16-06-01. In addition to these CASs, the channel between CAS 16-23-02 (Contaminated Area) and Mid Valley Road was investigated with walk-over radiological surveys and soil sampling using hand tools. The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 504. A CADD was originally submitted for CAU 504 and approved by the Nevada Division of Environmental Protection (NDEP). However, following an agreement between NDEP, DTRA, and the DOE, National Nuclear Security Administration Nevada Site Office to change to a risk-based approach for assessing the corrective action investigation (CAI) data, NDEP agreed that the CAU could be re-evaluated using the risk-based approach and a CADD/CR prepared to close the site.

  8. Socket sclerosis--an obstacle for orthodontic space closure?

    Science.gov (United States)

    Baumgaertel, Sebastian

    2009-07-01

    Socket sclerosis is a rare reaction to tooth extraction resulting in high-density bone in the center of the alveolar process, where, under normal circumstances, cancellous bone is to be expected. In an adult orthodontic patient, routine extractions of the mandibular first permanent bicuspids were performed, resulting in socket sclerosis and unsuccessful orthodontic space closure. Orthodontic mini-implants were inserted to augment anchorage and aid in space closure. In the presence of socket sclerosis, conventional orthodontic mechanics failed to close the extraction spaces. However, with absolute anchorage in place, space closure occurred at a nearly normal rate. After treatment, no signs of socket sclerosis were discernible on the periapical radiographs. Socket sclerosis can be an obstacle for orthodontic space closure if traditional mechanics are employed. However, mini-implant-reinforced anchorage can lead to successful space closure, resulting in complete resolution of the sclerotic sites.

  9. Closure Report for Corrective Action Units 530, 531, 532, 533, 534, 535: NTS Mud Pits, Nevada Test Site, Nevada, Rev. No.: 0

    Energy Technology Data Exchange (ETDEWEB)

    Alfred Wickline

    2006-07-01

    This Closure Report (CR) presents information supporting the recommendation of no further action for the following six Corrective Action Units (CAUs): (1) CAU 530 - LANL Preshot Mud Pits; (2) CAU 531 - LANL Postshot Mud Pits; (3) CAU 532 - LLNL Preshot Mud Pits; (4) CAU 533 - LLNL Postshot Mud Pits; (5) CAU 534 - Exploratory/Instrumentation Mud Pits; and (6) CAU 535 - Mud Pits/Disposal Areas. This CR complies with the requirements of the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. CAUs 530-535 are located in Areas 1-10, 14, 17, 19, and 20 of the Nevada Test Site and are comprised of 268 Corrective Action Sites (CASs) listed in Table 1-1. The purpose of this CR is to validate the risk-based closure strategy presented in the ''Mud Pit Risk-Based Closure Strategy Report'' (RBCSR) (NNSA/NSO, 2004) and the CAUs 530-535 SAFER Plan (NNSA/NSO, 2005b). This strategy uses 52 CASs as a statistical representation of CAUs 530-535 to confirm the proposed closure alternative, no further action, is sufficient to protect human health and the environment. This was accomplished with the following activities: A field investigation following a probabilistic sampling design to collect data that were used in a non-carcinogenic risk assessment for human receptors; Visual habitat surveys to confirm the lack of habitat for threatened and endangered species; Disposal of debris and waste generated during field activities; and Document Notice of Completion and closure of CAUs 530-535 issued by Nevada Division of Environmental Protection. The field investigation and site visits were conducted between August 31, 2005 and February 21, 2006. As stated in the RBCSR and Streamlined Approach for Environmental Restoration (SAFER) Plan, total petroleum hydrocarbons-diesel-range organics (TPH-DRO) was the only contaminant of potential

  10. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2009

    International Nuclear Information System (INIS)

    2010-01-01

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2009 and includes inspection and repair activities completed at the following seven CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 407: Roller Coaster RadSafe Area (TTR); (3) CAU 424: Area 3 Landfill Complexes (TTR); (4) CAU 426: Cactus Spring Waste Trenches (TTR); (5) CAU 453: Area 9 UXO Landfill (TTR); (6) CAU 484: Surface Debris, Waste Sites, and Burn Area (TTR); and (7) CAU 487: Thunderwell Site (TTR). The annual post-closure inspections were conducted May 5-6, 2009. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2009, and the vegetation monitoring report is included in Attachment F. Maintenance was performed at CAU 453. Animal burrows observed during the annual inspection were backfilled, and a depression was restored to grade on June 25, 2009. Post-closure site inspections should continue as scheduled. Vegetation survey inspections have been conducted annually at CAUs 400, 404, 407, and 426. Discontinuation of vegetation surveys is recommended at the CAU 400 Bomblet Pit and CAU 426, which have been successfully revegetated. Discontinuation of vegetation surveys is also recommended at CAU 404, which has been changed to an administrative closure with no inspections

  11. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2009

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-05-28

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2009 and includes inspection and repair activities completed at the following seven CAUs: · CAU 400: Bomblet Pit and Five Points Landfill (TTR) · CAU 407: Roller Coaster RadSafe Area (TTR) · CAU 424: Area 3 Landfill Complexes (TTR) · CAU 426: Cactus Spring Waste Trenches (TTR) · CAU 453: Area 9 UXO Landfill (TTR) · CAU 484: Surface Debris, Waste Sites, and Burn Area (TTR) · CAU 487: Thunderwell Site (TTR) The annual post-closure inspections were conducted May 5–6, 2009. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2009, and the vegetation monitoring report is included in Attachment F. Maintenance was performed at CAU 453. Animal burrows observed during the annual inspection were backfilled, and a depression was restored to grade on June 25, 2009. Post-closure site inspections should continue as scheduled. Vegetation survey inspections have been conducted annually at CAUs 400, 404, 407, and 426. Discontinuation of vegetation surveys is recommended at the CAU 400 Bomblet Pit and CAU 426, which have been successfully revegetated. Discontinuation of vegetation surveys is also recommended at CAU 404, which has been changed to an administrative closure with no inspections required. Vegetation

  12. Corrective Action Decision Document/Closure Report for Corrective Action Unit 545: Dumps, Waste Disposal Sites, and Buried Radioactive Materials Nevada Test Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Alfred Wickline

    2008-04-01

    This Corrective Action Decision Document (CADD)/Closure Report (CR) has been prepared for Corrective Action Unit (CAU) 545, Dumps, Waste Disposal Sites, and Buried Radioactive Materials, in Areas 2, 3, 9, and 20 of the Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management (1996, as amended February 2008). Corrective Action Unit 545 is comprised of the following eight Corrective Action Sites (CASs): • 02-09-01, Mud Disposal Area • 03-08-03, Mud Disposal Site • 03-17-01, Waste Consolidation Site 3B • 03-23-02, Waste Disposal Site • 03-23-05, Europium Disposal Site • 03-99-14, Radioactive Material Disposal Area • 09-23-02, U-9y Drilling Mud Disposal Crater • 20-19-01, Waste Disposal Site While all eight CASs are addressed in this CADD/CR, sufficient information was available for the following three CASs; therefore, a field investigation was not conducted at these sites: • For CAS 03-08-03, though the potential for subsidence of the craters was judged to be extremely unlikely, the data quality objective (DQO) meeting participants agreed that sufficient information existed about disposal and releases at the site and that a corrective action of close in place with a use restriction is recommended. Sampling in the craters was not considered necessary. • For CAS 03-23-02, there were no potential releases of hazardous or radioactive contaminants identified. Therefore, the Corrective Action Investigation Plan for CAU 545 concluded that: “Sufficient information exists to conclude that this CAS does not exist as originally identified. Therefore, there is no environmental concern associated with CAS 03-23-02.” This CAS is closed with no further action. • For CAS 03-23-05, existing information about the two buried sources and lead pig was considered to be

  13. Post-Closure Inspection and Monitoring Report for Corrective Action Unit 110: Area 3 WMD U-3ax/bl Crater, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Bechtel Nevada

    2006-08-01

    This Post-Closure Inspection and Monitoring Report provides the results and inspections and monitoring for Corrective Action Unit 110: Area 3 Waste Management Division U-3ax/bl Crater, Nevada Test Site, Nevada. This report includes an analysis and summary of the site inpsections, repairs and maintenance, meteorological information, and soil moisture monitoring data obtained at Corrective Action Unit 110, for the annual period July 2005 thrugh June 2006.

  14. Development of closure criteria for inactive radioactive waste-disposal sites at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Kocher, D.C.

    1990-01-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) specifies that the U.S. Department of Energy shall comply with the procedural and substantive requirements of CERCLA regarding cleanup of inactive waste-disposal sites. Remedial actions require a level of control for hazardous substances that at least attains legally applicable or relevant and appropriate requirements (ARAR). This requirement may be waived if compliance with ARAR results in greater risk to human health and the environment than alternatives or is technically impractical. It will review potential ARAR for cleanup of inactive radioactive waste-disposal sites and propose a set of closure criteria for such sites at Oak Ridge National Laboratory. Important potential ARAR include federal standards for radiation protection of the public, radioactivity in drinking water, and near-surface land disposal of radioactive wastes. Proposed criteria for cleanup of inactive radioactive waste-disposal sites are: (1) a limit of 0.25 mSv on annual effective dose equivalent for offsite individuals; (2) limits of 1 mSv for continuous exposures and 5 mSv for occasional exposures on annual effective dose equivalent for inadvertent intruders, following loss of institutional controls over disposal sites; and (3) limits on concentrations of radionuclides in potable ground and surface waters in accordance with federal drinking-water standards, to the extent reasonably achievable

  15. CLOSURE REPORT FOR CORRECTIVE ACTION UNIT 390: AREAS 9, 10, AND 12 SPILL SITES, NEVADA TEST SITE, NEVADA

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-10-01

    Corrective Action Unit (CAU) 390 consists four Corrective Action Sites (CASs) located in Areas 9, 10, and 12 of the Nevada Test Site. The closure activities performed at the CASs include: (1) CAS 09-99-03, Wax, Paraffin: 2 cubic yards of drilling polymer was removed on June 20,2005, and transported to the Area 9 Landfill for disposal. (2) CAS 10-99-01, Epoxy Tar Spill: 2 cubic feet of asphalt waste was removed on June 20,2005, and transported to the Area 9 Landfill for disposal. (3) CAS 10-99-03, Tar Spills: 3 cubic yards of deteriorated asphalt waste was removed on June 20,2005, and transported to the Area 9 Landfill for disposal. (4) CAS 12-25-03, Oil Stains (2); Container: Approximately 16 ounces of used oil were removed from ventilation equipment on June 28,2005, and recycled. One CAS 10-22-19, Drums, Stains, was originally part of CAU 390 but was transferred out of CAU 390 and into CAU 550, Drums, Batteries, and Lead Materials. The transfer was approved by the Nevada Division of Environmental Protection on August 19,2005, and a copy of the approval letter is included in Appendix D of this report.

  16. Use of rubble from building demolition in mortars.

    Science.gov (United States)

    Corinaldesi, V; Giuggiolini, M; Moriconi, G

    2002-01-01

    Because of increasing waste production and public concerns about the environment, it is desirable to recycle materials from building demolition. If suitably selected, ground, cleaned and sieved in appropriate industrial crushing plants, these materials can be profitably used in concrete. Nevertheless, the presence of masonry instead of concrete rubble is particularly detrimental to the mechanical performance and durability of recycled-aggregate concrete and the same negative effect is detectable when natural sand is replaced by fine recycled aggregate fraction. An alternative use of both masonry rubble and fine recycled material fraction could be in mortars. These could contain either recycled instead of natural sand or powder obtained by bricks crushing as partial cement substitution. In particular, attention is focused on the modification that takes place when either polypropylene or stainless steel fibers are added to these mortars. Polypropylene fibers are added in order to reduce shrinkage of mortars, stainless steel fibers for improving their flexural strength. The combined use of polypropylene fibers and fine recycled material from building demolition could allow the preparation of mortars showing good performance, in particular when coupled with bricks. Furthermore, the combined use of stainless steel fibers and mortars containing brick powder seems to be an effective way to guarantee a high flexural strength.

  17. Closure Report for Corrective Action Unit 357: Mud Pits and Waste Dump, Nevada Test Site, Nevada, Rev. No.: 0

    Energy Technology Data Exchange (ETDEWEB)

    Laura A. Pastor

    2005-04-01

    This Closure Report (CR) presents information supporting closure of Corrective Action Unit (CAU) 357: Mud Pits and Waste Dump, Nevada Test Site (NTS), Nevada. The CR complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada, U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). Corrective Action Unit 357 is comprised of 14 Corrective Action Sites (CASs) located in Areas 1, 4, 7, 8, 10, and 25 of the NTS (Figure 1-1). The NTS is located approximately 65 miles (mi) northwest of Las Vegas, Nevada. Corrective Action Unit 357 consists of 11 CASs that are mud pits located in Areas 7, 8, and 10. The mud pits were associated with drilling activities conducted on the NTS in support of the underground nuclear weapons testing. The remaining three CASs are boxes and pipes associated with Building 1-31.2el, lead bricks, and a waste dump. These CAS are located in Areas 1, 4, and 25, respectively. The following CASs are shown on Figure 1-1: CAS 07-09-02, Mud Pit; CAS 07-09-03, Mud Pit; CAS 07-09-04, Mud Pit; CAS 07-09-05, Mud Pit; CAS 08-09-01, Mud Pit; CAS 08-09-02, Mud Pit; CAS 08-09-03, Mud Pit; CAS 10-09-02, Mud Pit; CAS 10-09-04, Mud Pit; CAS 10-09-05, Mud Pit; CAS 10-09-06, Mud Pit, Stains, Material; CAS 01-99-01, Boxes, Pipes; CAS 04-26-03, Lead Bricks; and CAS 25-15-01, Waste Dump. The purpose of the corrective action activities was to obtain analytical data that supports the closure of CAU 357. Environmental samples were collected during the investigation to determine whether contaminants exist and if detected, their extent. The investigation and sampling strategy was designed to target locations and media most likely to be contaminated (biased sampling). A general site conceptual model was developed for each CAS to support and guide the investigation as outlined in the Streamlined Approach for Environmental Restoration (SAFER) Plan (NNSA/NSO, 2003b). This CR

  18. 2727-S Nonradioactive Dangerous Waste Storage Facility Closure Plan

    International Nuclear Information System (INIS)

    Wilczek, T.A.; Laws, J.R.; Izatt, R.D.

    1992-01-01

    This closure plan describes the activities for final closure of the 2727-S Nonradioactive Dangerous Waste Storage (NRDWS) Facility at the Hanford Site. The 2727-S NRDWS Facility provided container storage for nonradioactive dangerous and extremely hazardous wastes generated in the research and development laboratories, process operations, and maintenance and transportation functions throughout the Hanford Site. Storage operations began at the 2727-S NRDWS Facility March 14, 1983, and continued until December 30, 1986, when the last shipment of materials from the facility took place. These storage operations have been moved to the new 616 NRDWS Facility, which is an interim status unit located between the 200 East and 200 West Areas of the Hanford Site

  19. Post-Closure Inspection Report for the Tonopah Test Range, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2006 and includes inspection and repair activities completed at the following nine CAUs: CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 404: Roller Coaster Lagoons and Trench (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 426: Cactus Spring Waste Trenches (TTR); CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR). Post-closure inspections were conducted on May 9, 2006, May 31, 2006, and November 15, 2006. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2006, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 400, CAU 407, CAU 426, CAU 453, and CAU 487 in 2006. During the May inspection of CAU 400, it was identified that the east and west sections of chickenwire fencing beyond the standard fencing were damaged; they were repaired in June 2006. Also in June 2006, the southeast corner fence post and one warning sign at CAU 407 were reinforced and reattached, the perimeter fencing adjacent to the gate at CAU 426 was tightened, and large animal

  20. Post-Closure Inspection Report for the Tonopah Test Range, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2007-06-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2006 and includes inspection and repair activities completed at the following nine CAUs: CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 404: Roller Coaster Lagoons and Trench (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 426: Cactus Spring Waste Trenches (TTR); CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR). Post-closure inspections were conducted on May 9, 2006, May 31, 2006, and November 15, 2006. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2006, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 400, CAU 407, CAU 426, CAU 453, and CAU 487 in 2006. During the May inspection of CAU 400, it was identified that the east and west sections of chickenwire fencing beyond the standard fencing were damaged; they were repaired in June 2006. Also in June 2006, the southeast corner fence post and one warning sign at CAU 407 were reinforced and reattached, the perimeter fencing adjacent to the gate at CAU 426 was tightened, and large animal

  1. Post-Closure Inspection and Monitoring Report for Corrective Action Unit 342: Area 23 Mercury Fire Training Pit, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2006-01-01

    This report provides a summary and analysis of visual site inspections and soil gas sampling results for Corrective Action Unit (CAU) 342, Area 23 Mercury Fire Training Pit. CAU 342 is identified in the Federal Facility Agreement and Consent Order of 1996 and consists of Corrective Action Site 23-56-01, Former Mercury Fire Training Pit. This report covers calendar years 2004 and 2005. Visual site inspections were conducted on May 20 and November 14, 2004, and May 17 and November 15, 2005. No significant findings were observed during these inspections. The site was in good condition, and no repair activities were required. Soil gas samples were collected on November 29, 2005, for analysis of volatile organic compounds (VOCs) and semivolatile organic compounds (SVOCs), and samples were collected on December 1, 2005, for analysis of base gases. Base gas concentrations in the monitoring well show a high concentration of carbon dioxide and a low concentration of oxygen, which is an indication of biodegradation of total petroleum hydrocarbons (TPH) in the soil. Results for VOCs and SVOCs are unchanged, with VOCs below or near laboratory method detection limits and no SVOCs detected above laboratory method detection limits. Post-closure monitoring was required for six years after closure of the site. Therefore, since 2005 was the sixth year of monitoring, the effectiveness of natural attenuation of the TPH-impacted soil by biodegradation was evaluated. The base gas concentrations indicate that biodegradation of TPH in the soil is occurring; therefore, it is recommended that monitoring be discontinued. Visual site inspections should continue to be performed biannually to ensure that the signs are in place and readable and that the use restriction has been maintained. The results of the site inspections will be documented in a letter report and submitted annually

  2. Closure Report for Corrective Action Unit 143: Area 25 Contaminated Waste Dumps, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Tobiason, D. S.

    2002-01-01

    This Closure Report (CR) has been prepared for the Area 25 Contaminated Waste Dumps (CWD), Corrective Action Unit (CAU) 143 in accordance with the Federal Facility Agreement and Consent Order [FFACO] (FFACO, 1996) and the Nevada Division of Environmental Protection (NDEP)-approved Corrective Action Plan (CAP) for CAU 143: Area 25, Contaminated Waste Dumps, Nevada Test Site, Nevada. CAU 143 consists of two Corrective Action Sites (CASs): 25-23-09 CWD No.1, and 25-23-03 CWD No.2. The Area 25 CWDs are historic disposal units within the Area 25 Reactor Maintenance, Assembly, and Disassembly (R-MAD), and Engine Maintenance, Assembly, and Disassembly (E-MAD) compounds located on the Nevada Test Site (NTS). The R-MAD and E-MAD facilities originally supported a portion of the Nuclear Rocket Development Station in Area 25 of the NTS. CWD No.1 CAS 25-23-09 received solid radioactive waste from the R-MAD Compound (East Trestle and West Trench Berms) and 25-23-03 CWD No.2 received solid radioactive waste from the E-MAD Compound (E-MAD Trench)

  3. Coal and wood fuel for electricity production: An environmentally sound solution for waste and demolition wood

    Energy Technology Data Exchange (ETDEWEB)

    Penninks, F.W.M. [EPON, Zwolle (Netherlands)

    1997-12-31

    Waste wood from primary wood processing and demolition presents both a problem and a potential. If disposed in landfills, it consumes large volumes and decays, producing CH{sub 4}, CO{sub 2} and other greenhouse gases. As an energy source used in a coal fired power plant it reduces the consumption of fossil fuels reducing the greenhouse effect significantly. Additional advantages are a reduction of the ash volume and the SO{sub 2} and NO{sub x} emissions. The waste wood requires collection, storage, processing and burning. This paper describes a unique project which is carried out in the Netherlands at EPON`s Gelderland Power Plant (635 MW{sub e}) where 60 000 tonnes of waste and demolition wood will be used annually. Special emphasis is given to the processing of the powdered wood fuel. Therefore, most waste and demolition wood can be converted from an environmental liability to an environmental and economic asset. (author)

  4. Coal and wood fuel for electricity production: An environmentally sound solution for waste and demolition wood

    Energy Technology Data Exchange (ETDEWEB)

    Penninks, F W.M. [EPON, Zwolle (Netherlands)

    1998-12-31

    Waste wood from primary wood processing and demolition presents both a problem and a potential. If disposed in landfills, it consumes large volumes and decays, producing CH{sub 4}, CO{sub 2} and other greenhouse gases. As an energy source used in a coal fired power plant it reduces the consumption of fossil fuels reducing the greenhouse effect significantly. Additional advantages are a reduction of the ash volume and the SO{sub 2} and NO{sub x} emissions. The waste wood requires collection, storage, processing and burning. This paper describes a unique project which is carried out in the Netherlands at EPON`s Gelderland Power Plant (635 MW{sub e}) where 60 000 tonnes of waste and demolition wood will be used annually. Special emphasis is given to the processing of the powdered wood fuel. Therefore, most waste and demolition wood can be converted from an environmental liability to an environmental and economic asset. (author)

  5. Streamlined approach for environmental restoration closure report for Corrective Action Unit 120: Areas 5 and 6 aboveground storage tanks, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-06-01

    This Closure Report provides documentation for the closure of Corrective Action Unit (CAU) 120 of the Federal Facilities Agreement and Consent Order (FFACO). CAU 120 consists of two Corrective Action Sites (CASs) located in Areas 5 and 6 of the Nevada Test Site (NTS), which are approximately 130 kilometers (80 miles) northwest of Las Vegas, Nevada. CAS 05-01-01 is located in Area 5 and consists of three 45,800-liter (12,100-gallon) aboveground storage tanks (ASTs), piping, and debris associated with Well RNM-1. CAS 06-01-01 consists of two ASTs and two tanker trailers (all portable) that were originally located at the Area 6 Cp-50 Hot Park and which had been moved to the Area 6 Waste Handling Facility. All of the items in CAU 120 have been used to contain or convey radiologically contaminated fluid that was generated during post-nuclear event activities at the NTS.

  6. Streamlined approach for environmental restoration closure report for Corrective Action Unit 120: Areas 5 and 6 aboveground storage tanks Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    1999-06-01

    This Closure Report provides documentation for the closure of Corrective Action Unit (CAU) 120 of the Federal Facilities Agreement and Consent Order (FFACO). CAU 120 consists of two Corrective Action Sites (CASs) located in Areas 5 and 6 of the Nevada Test Site (NTS), which are approximately 130 kilometers (80 miles) northwest of Las Vegas, Nevada. CAS 05-01-01 is located in Area 5 and consists of three 45,800-liter (12,100-gallon) aboveground storage tanks (ASTs), piping, and debris associated with Well RNM-1. CAS 06-01-01 consists of two ASTs and two tanker trailers (all portable) that were originally located at the Area 6 Cp-50 Hot Park and which had been moved to the Area 6 Waste Handling Facility. All of the items in CAU 120 have been used to contain or convey radiologically contaminated fluid that was generated during post-nuclear event activities at the NTS

  7. Fracture analysis of cement treated demolition waste using a lattice model

    NARCIS (Netherlands)

    Xuan, D.; Schlangen, H.E.J.G.; Molenaar, A.A.A.; Houben, L.J.M.

    2013-01-01

    Fracture properties of cement treated demolition waste were investigated using a lattice model. In practice the investigated material is applied as a cement treated road base/subbase course. The granular aggregates used in this material were crushed recycled concrete and masonry. This results in six

  8. Comparison of fasciotomy wound closures using traditional dressing changes and the vacuum-assisted closure device.

    Science.gov (United States)

    Zannis, John; Angobaldo, Jeff; Marks, Malcolm; DeFranzo, Anthony; David, Lisa; Molnar, Joseph; Argenta, Louis

    2009-04-01

    Fasciotomy wounds can be a major contributor to length of stay for patients as well as a difficult reconstructive challenge. Once the compartment pressure has been relieved and stabilized, the wound should be closed as quickly and early as possible to avoid later complications. Skin grafting can lead to morbidity and scarring at both the donor and fasciotomy site. Primary closure results in a more functional and esthetic outcome with less morbidity for the patient, but can often be difficult to achieve secondary to edema, skin retraction, and skin edge necrosis. Our objective was to examine fasciotomy wound outcomes, including time to definitive closure, comparing traditional wet-to-dry dressings, and the vacuum-assisted closure (VAC) device. This retrospective chart review included a consecutive series of patients over a 10-year period. This series included 458 patients who underwent 804 fasciotomies. Of these fasciotomy wounds, 438 received exclusively VAC. dressings, 270 received only normal saline wet-to-dry dressings, and 96 were treated with a combination of both. Of the sample, 408 patients were treated with exclusively VAC therapy or wet-to-dry dressings and 50 patients were treated with a combination of both. In comparing all wounds, there was a statistically significant higher rate of primary closure using the VAC versus traditional wet-to-dry dressings (P lower extremities and P extremities). The time to primary closure of wounds was shorter in the VAC. group in comparison with the non-VAC group. This study has shown that the use of the VAC for fasciotomy wound closure results in a higher rate of primary closure versus traditional wet-to-dry dressings. In addition, the time to primary closure of wounds or time to skin grafting is shorter when the VAC was employed. The VAC used in the described settings decreases hospitalization time, allows for earlier rehabilitation, and ultimately leads to increased patient satisfaction.

  9. Corrective Action Decision Document/Closure Report for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick

    2014-01-01

    The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 105 based on the implementation of the corrective actions. Corrective action investigation (CAI) activities were performed from October 22, 2012, through May 23, 2013, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites; and in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices.

  10. IDENTIFICATION OF DOE'S POST-CLOSURE MONITORING NEEDS AND REQUIREMENTS

    Energy Technology Data Exchange (ETDEWEB)

    M.A. Ebadian, Ph.D.

    1999-01-01

    The 2006 plan sets an ambitious agenda for the U.S. Department of Energy (DOE), Office of Environmental Management (EM) and the remediation of sites contaminated by decades of nuclear weapons production activities. The plan's primary objective is to reduce overall clean up costs by first eliminating the environmental problems that are most expensive to control and safely maintain. In the context of the 2006 Plan, closure refers to the completion of area or facility specific cleanup projects. The cleanup levels are determined by the planned future use of the site or facility. Use restrictions are still undecided for most sites but are highly probable to exclude residential or agricultural activities. Most of the land will be remediated to ''industrial use'' levels with access restrictions and some areas will be closed-off through containment. Portions of the site will be reserved for waste disposal, either as a waste repository or the in-situ immobilization of contaminated soil and groundwater, and land use will be restricted to waste disposal only. The land used for waste disposal will require monitoring and maintenance activities after closure. Most of the land used for industrial use may also require such postclosure activities. The required postclosure monitoring and maintenance activities will be imposed by regulators and stakeholders. Regulators will not approve closure plans without clearly defined monitoring methods using approved technologies. Therefore, among all other more costly and labor-intensive closure-related activities, inadequate planning for monitoring and lack of appropriate monitoring technologies can prevent closure. The purpose of this project is to determine, document, and track the current and evolving postclosure monitoring requirements at DOE-EM sites. This information will aid CMST-CP in guiding its postclosure technology development and deployment efforts.

  11. Hexone Storage and Treatment Facility closure plan

    International Nuclear Information System (INIS)

    1992-11-01

    The HSTF is a storage and treatment unit subject to the requirements for the storage and treatment of dangerous waste. Closure is being conducted under interim status and will be completed pursuant to the requirements of Washington State Department of Ecology (Ecology) Dangerous Waste Regulations, Washington Administrative Code (WAC) 173-303-610 and WAC 173-303-640. Because dangerous waste does not include the source, special nuclear, and by-product material components of mixed waste, radionuclides are not within the scope of WAC 173-303 or of this closure plan. The information on radionuclides is provided only for general knowledge where appropriate. The known hazardous/dangerous waste remaining at the site before commencing other closure activities consists of the still vessels, a tarry sludge in the storage tanks, and residual contamination in equipment, piping, filters, etc. The treatment and removal of waste at the HSTF are closure activities as defined in the Resource Conservation and Recovery Act (RCRA) of 1976 and WAC 173-303

  12. HWMA/RCRA Closure Plan for the TRA Fluorinel Dissolution Process Mockup and Gamma Facilities Waste System

    International Nuclear Information System (INIS)

    K. Winterholler

    2007-01-01

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act closure plan was developed for the Test Reactor Area Fluorinel Dissolution Process Mockup and Gamma Facilities Waste System, located in Building TRA-641 at the Reactor Technology Complex (RTC), Idaho National Laboratory Site, to meet a further milestone established under the Voluntary Consent Order SITE-TANK-005 Action Plan for Tank System TRA-009. The tank system to be closed is identified as VCO-SITE-TANK-005 Tank System TRA-009. This closure plan presents the closure performance standards and methods for achieving those standards

  13. The decommissioning and demolition of four suites of high active chemical analysis cells at DNPDE

    International Nuclear Information System (INIS)

    Black, R.M.; Spence, B.W.; Stewart, C.W.

    1987-11-01

    The decommissioning and demolition of four laboratory suites of high active cells at DNPDE is described. All four suites had suffered drain leaks of high active liquor into underfloor ducts; the options available at the time and current policy for dealing with the resultant activity deposits are given. The decommissioning procedures are detailed to provide information for future similar exercises. Features to ease demolition of such facilities and to eliminate the possibility of long term activity deposition from drain leaks are highlighted for incorporation in future designs. The waste arisings and radiation doses received during the work are tabulated. (author)

  14. POST-CLOSURE INSPECTION REPORT FOR CORRECTIVE ACTION UNIT 92: AREA 6 DECON PAD FACILITY, NEVADA. TEST SITE NEVADA, FOR THE PERIOD JANUARY 2004 - DECEMBER 2004

    International Nuclear Information System (INIS)

    BECHTEL NEVADA

    2005-01-01

    This Post-Closure Inspection Report provides an analysis and summary of inspections for Corrective Action Unit (CAU) 92, Area 6 Decon Pond Facility, Nevada Test Site, Nevada. CAU 92 was closed in accordance with the Resource Conservation and Recovery Act (RCRA) Part B Operational Permit (Nevada Division of Environmental Protection, 1995) and the Federal Facility Agreement and Consent Order of 1996 on May 11, 1999. CAU 92 consists of two Corrective Action Sites (CASs): CAS 06-04-01, Decon Pad oil/Water Separator; and CAS 06-05-02, Decontamination Pond (RCRA). Both CASs have use restrictions; however, only CAS 06-05-02, Decontamination Pond (RCRA), requires post-closure inspections. CAS 06-04-01, Decon Pad Oil/Water Separator, is located inside the fence at the Building 6-605 compound. This report covers the annual period January 2004 through December 2004

  15. Demolition, construction and excavation wastes in Copenhagen. Los residuos de demolicion, construccion y excavacion en Copenhague

    Energy Technology Data Exchange (ETDEWEB)

    Hahn, N.J.; Lauridsen, P.S.

    1994-01-01

    Demolition Waste, Construction Waste and Excavation Waste will in a modern society represent a major part of the total amount of the industrial wastes. Implementation of the Regulation for Industrial Waste in Copenhagen has resulted insignificant changes in the transportation and processing of this type of waste was typically disposed of as mixed waste on landfill sites and open dumps. Today most of this waste is sorted at the source (see figure 1) and recycled namely as secondary raw materials. This change in the disposal of construction waste etc, is due to two main factors: implementation of the regulation of commercial wastes and a significant raise in the (governmental) waste tax on specially landfilling activities. (Author)

  16. Downcycling versus recycling of construction and demolition waste: Combining LCA and LCC to support sustainable policy making.

    Science.gov (United States)

    Di Maria, Andrea; Eyckmans, Johan; Van Acker, Karel

    2018-05-01

    Urgent solutions are needed in Europe to deal with construction and demolition waste (CDW). EU policy has contributed to significantly reducing the amount of CDW going to landfill, but most of the effort has been put in downcycling practices. Therefore, further policies are needed to stimulate high-quality recycling of CDW. The present paper presents a combined life cycle assessment (LCA) and life cycle costing (LCC) methodologies to analyse the environmental and the economic drivers in four alternative CDW end-of-life scenarios in the region of Flanders, in Belgium. The four analysed alternatives are (i) landfilling, (ii) downcycling, (iii) advanced recycling and (iv) recycling after selective demolition. LCA results show that landiflling is the scenario having the highest environmental impacts in terms of person equivalent (PE), followed by downcycling and recycling (-36%) and recycling after selective demolition (-59%). The decrease in environmental impacts is mostly due to the avoided landfilling of CDW and the recovery of materials from selective demolition. LCC results indicate that landfilling is the scenario bearing the highest total economic costs. This is due to the high landfill tax in Flanders. The recycling after selective demolition bears the second highest cost. The increase of high-quality CDW recycling can significantly reduce the overall environmental impact of the system. Implementing a high landfill tax, increasing the gate fee to the recycling plant, and boosting the sales price of recycled aggregates are the most effective drivers to facilitate a transition towards a more sustainable CDW management system. The paper demonstrates that the combined LCA and LCC results can highlight the environmental and economic drivers in CDW management. The results of the combined analysis can help policymakers to promote the aspects contributing to sustainability and to limit the ones creating a barrier. Copyright © 2018 Elsevier Ltd. All rights reserved.

  17. Construction and Demolition Debris 2014 US Final Disposition Estimates Using the CDDPath Method

    Data.gov (United States)

    U.S. Environmental Protection Agency — Estimates of the final amount and final disposition of materials generated in the Construction and Demolition waste stream measured in total mass of each material....

  18. The Effect of Platelet-Rich Fibrin, Calcium Sulfate Hemihydrate, Platelet-Rich Plasma and Resorbable Collagen on Soft Tissue Closure of Extraction Sites

    Directory of Open Access Journals (Sweden)

    Lisa M. Yerke

    2017-05-01

    Full Text Available Rapid and complete soft tissue healing after tooth extraction minimizes surgical complications and facilitates subsequent implant placement. We used four treatment methods and assessed changes in soft tissue socket closure following tooth extraction in humans. The effects of platelet-rich fibrin-calcium sulfate hemihydrate (PRF-CSH, platelet-rich plasma-calcium sulfate hemihydrate (PRP-CSH, a resorbable collagen dressing (RCD, and no grafting material were compared in a randomized, controlled pilot study with a blinded parallel design (N = 23. Patients with a hopeless tooth scheduled for extraction were randomly assigned to one of the four treatment groups. Socket measurements were obtained immediately after extraction and treatment, as well as after 21 days. There was a significant decrease in the total epithelialized external surface area of the extraction sockets in each group at all time points. However, there were no significant differences in soft tissue closure (p > 0.05 at any time point and PRF-CSH or PRP-CSH did not provide any additional benefit to enhance the soft tissue closure of extraction sockets compared with either RCD or sites without graft.

  19. An integrated approach for the management of demolition waste in Cyprus.

    Science.gov (United States)

    Kourmpanis, Basilis; Papadopoulos, Achilleas; Moustakas, Konstantinos; Kourmoussis, Fotis; Stylianou, Marinos; Loizidou, Maria

    2008-12-01

    This study investigated the generation and management of demolition waste (DW) in Cyprus. A methodology has been developed and applied for the estimation of the quantities of the waste stream under examination, since quantitative primary data were not available. The existing situation relating to the practices applied for the management of DW was investigated and assessed. Furthermore, a multi-criteria analysis method (PROMETHEE II) was developed and applied in order to examine alternative systems that could be implemented for the management of the DW in the country. In particular, nine management systems (scenarios) were examined, evaluated and ranked according to their efficiency using seventeen individual criteria, divided into four groups (social-legislative, environmental, economic and technical). The ranking of the alternative waste management scenarios indicated that the optimum management system for possible implementation in the island included complete selective demolition procedures and transfer of mixed recyclable materials to the recycling centre and non-recyclable material to landfill.

  20. Nuclear Rocket Test Facility Decommissioning Including Controlled Explosive Demolition of a Neutron-Activated Shield Wall

    International Nuclear Information System (INIS)

    Michael Kruzic

    2007-01-01

    Located in Area 25 of the Nevada Test Site, the Test Cell A Facility was used in the 1960s for the testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program. The facility was decontaminated and decommissioned (D and D) in 2005 using the Streamlined Approach For Environmental Restoration (SAFER) process, under the Federal Facilities Agreement and Consent Order (FFACO). Utilities and process piping were verified void of contents, hazardous materials were removed, concrete with removable contamination decontaminated, large sections mechanically demolished, and the remaining five-foot, five-inch thick radiologically-activated reinforced concrete shield wall demolished using open-air controlled explosive demolition (CED). CED of the shield wall was closely monitored and resulted in no radiological exposure or atmospheric release

  1. Regulatory Framework for Salt Waste Disposal and Tank Closure at the Savannah River Site - 13663

    Energy Technology Data Exchange (ETDEWEB)

    Thomas, Steve; Dickert, Ginger [Savannah River Remediation LLC, Savannah River Site, Aiken, SC 29808 (United States)

    2013-07-01

    The end of the Cold War has left a legacy of approximately 37 million gallons of radioactive waste in the aging waste tanks at the Department of Energy's Savannah River Site (SRS). A robust program is in place to remove waste from these tanks, treat the waste to separate into a relatively small volume of high-level waste and a large volume of low-level waste, and to actively dispose of the low-level waste on-site and close the waste tanks and associated ancillary structures. To support performance-based, risk-informed decision making and to ensure compliance with all regulatory requirements, the U.S. Department of Energy (DOE) and its current and past contractors have worked closely with the South Carolina Department of Health and Environmental Control (SCDHEC), the U.S. Environmental Protection Agency (EPA) and the Nuclear Regulatory Commission (NRC) to develop and implement a framework for on-site low-level waste disposal and closure of the SRS waste tanks. The Atomic Energy Act of 1954, as amended, provides DOE the authority to manage defense-related radioactive waste. DOE Order 435.1 and its associated manual and guidance documents detail this radioactive waste management process. The DOE also has a requirement to consult with the NRC in determining that waste that formerly was classified as high-level waste can be safely managed as either low-level waste or transuranic waste. Once DOE makes a determination, NRC then has a responsibility to monitor DOE's actions in coordination with SCDHEC to ensure compliance with the Title 10 Code of Federal Regulations Part 61 (10CFR61), Subpart C performance objectives. The management of hazardous waste substances or components at SRS is regulated by SCDHEC and the EPA. The foundation for the interactions between DOE, SCDHEC and EPA is the SRS Federal Facility Agreement (FFA). Managing this array of requirements and successfully interacting with regulators, consultants and stakeholders is a challenging task but

  2. 3718-F Alkali Metal Treatment and Storage Facility Closure Plan

    International Nuclear Information System (INIS)

    1992-11-01

    The Hanford Site, located northwest of the city of Richland, Washington, houses reactors, chemical-separation systems, and related facilities used for the production of special nuclear materials, as well as for activities associated with nuclear energy development. The 300 Area of the Hanford Site contains reactor fuel manufacturing facilities and several research and development laboratories. The 3718-F Alkali Metal Treatment and Storage Facility (3718-F Facility), located in the 300 Area, was used to store and treat alkali metal wastes. Therefore, it is subject to the regulatory requirements for the storage and treatment of dangerous wastes. Closure will be conducted pursuant to the requirements of the Washington Administrative Code (WAC) 173-303-610 (Ecology 1989) and 40 CFR 270.1. Closure also will satisfy the thermal treatment facility closure requirements of 40 CFR 265.381. This closure plan presents a description of the 3718-F Facility, the history of wastes managed, and the approach that will be followed to close the facility. Only hazardous constituents derived from 3718-F Facility operations will be addressed

  3. The role of the California Base Closure Environmental Committee's (CBCEC) Radioactive and Mixed Waste Process Action Team (RMWPAT) in expediting site restoration and reuse

    International Nuclear Information System (INIS)

    Laudon, L.S.

    1994-01-01

    The Base Realignment and Closure Act (BRAC) mandated the closing and transfer of Department of Defense (DoD) properties within specific timeframes. Due to requirements of federal and state laws, closing bases must be environmentally remediated to alleviate threats to human health and the environment upon transfer. Certain barriers such as legislative, regulatory, administrative, and technical issues, have been identified which threaten the timely restoration and transfer of these BRAC properties. The state of California, faced with the scheduled closure or realignment of 26 military bases, recognized the need to establish a base closure environmental committee to address issues affecting the timely cleanup and reuse of DoD properties and promote accelerated restoration. Accordingly, the California Base Closure Environmental Committee (CBCEC) was formed by executive order of Governor Pete Wilson. One of the barriers identified by the CBCEC is the potential contamination of DoD facilities with radioactive materials. As a result of the difficulties encountered in assessing the nature and extent of radioactive contamination at DoD sites in California, the CBCEC formed the Radioactive and Mixed Waste Process Action Team (RMWPAT). The RMWPAT was tasked with ''demystifying'' and working to address issues associated with radioactive contamination

  4. Decontamination Study for Mixed Waste Storage Tanks RCRA Closure

    International Nuclear Information System (INIS)

    Leaphart, D.M.; Reed, S.R.; Rankin, W.N.

    1995-01-01

    The Savannah River Site (SRS) plans to close six underground tanks storing mixed waste under RCRA regulations. In support of this closure effort, a study was performed to determine the optimal method of decontaminating these tanks to meet the closure requirements. Items consaidered in the evaluation of the decontamination methods included effectiveness, compatibility with existing waste residues, possible cleaning solution disposal methods, and cost

  5. Periodic Closures as Adaptive Coral Reef Management in the Indo-Pacific

    Directory of Open Access Journals (Sweden)

    Josh Cinner

    2006-06-01

    Full Text Available This study explores the social, economic, and ecological context within which communities in Papua New Guinea and Indonesia use adaptive coral reef management. We tested whether periodic closures had positive effects on reef resources, and found that both the biomass and the average size of fishes commonly caught in Indo-Pacific subsistence fisheries were greater inside areas subject to periodic closures compared to sites with year-round open access. Surprisingly, both long-lived and short-lived species benefited from periodic closures. Our study sites were remote communities that shared many socioeconomic characteristics; these may be crucial to the effectiveness of adaptive management of reef resources through periodic closures. Some of these factors include exclusive tenure over marine resources, a body of traditional ecological knowledge that allows for the rapid assessment of resource conditions, social customs that facilitate compliance with closures, relatively small human populations, negligible migration, and a relatively low dependence on fisheries. This dynamic adaptive management system, in which communities manage their resources among multiple social and ecological baselines, contrasts with western fisheries management practices, centered on maintaining exploited populations at stable levels in which net production is maximized.

  6. The vacuum-assisted closure (V.A.C®) system for surgical site infection with involved vascular grafts.

    Science.gov (United States)

    Saziye, Karaca; Afksendiyos, Kalangos

    2015-04-01

    In vascular surgery, surgical site infection is the most common postoperative morbidity, occurring in 5-10% of vascular patients. The optimal management of surgical site infection with involved lower limb vascular grafts remains controversial. We present our 6-year results of using the V.A.C.® system in surgical site infection with involved vascular grafts. A retrospective 6-year review of patient who underwent a VAC® therapy for postoperative surgical site infection in lower limb with involved vascular grafts in our department between January 2006 and December 2011. V.A.C therapy was used in 40 patients. All patients underwent surgical wound revision with VAC® therapy and antibiotics. The mean time of use of the V.A.C. system was 14.2 days. After mean of 12 days in 34 of 40 patients, in whom the use of VAC® therapy resulted in delayed primary closure or healing by secondary intention. The mean postoperative follow-up time was 61.67 months, during which 3 patients died. We showed that the V.A.C.® system is valuable for managing specifically surgical site infection with involved vascular grafts. Using the V.A.C.® system, reoperation rates are reduced; 85% of patients avoided graft replacement. © The Author(s) 2014 Reprints and permissions: sagepub.co.uk/journalsPermissions.nav.

  7. Positive Catch & Economic Benefits of Periodic Octopus Fishery Closures: Do Effective, Narrowly Targeted Actions 'Catalyze' Broader Management?

    Science.gov (United States)

    Oliver, Thomas A; Oleson, Kirsten L L; Ratsimbazafy, Hajanaina; Raberinary, Daniel; Benbow, Sophie; Harris, Alasdair

    2015-01-01

    Eight years of octopus fishery records from southwest Madagascar reveal significant positive impacts from 36 periodic closures on: (a) fishery catches and (b) village fishery income, such that (c) economic benefits from increased landings outweigh costs of foregone catch. Closures covered ~20% of a village's fished area and lasted 2-7 months. Octopus landings and catch per unit effort (CPUE) significantly increased in the 30 days following a closure's reopening, relative to the 30 days before a closure (landings: +718%, poctopus fishery income doubled in the 30 days after a closure, relative to 30 days before (+132%, p<0.001, n = 28). Control villages not implementing a closure showed no increase in income after "no ban" closures and modest increases after "ban" closures. Villages did not show a significant decline in income during closure events. Landings in closure sites generated more revenue than simulated landings assuming continued open-access fishing at that site (27/36 show positive net earnings; mean +$305/closure; mean +57.7% monthly). Benefits accrued faster than local fishers' time preferences during 17-27 of the 36 closures. High reported rates of illegal fishing during closures correlated with poor economic performance. We discuss the implications of our findings for broader co-management arrangements, particularly for catalyzing more comprehensive management.

  8. Design, production and initial state of the closure

    International Nuclear Information System (INIS)

    2010-12-01

    The report is included in a set of Production reports, presenting how the KBS-3 repository is designed, produced and inspected. The production reports are included in the safety report for the KBS-3 repository and repository facility. The report provides input on the initial state of the closure and plugs in underground openings other than deposition tunnels for the assessment of the long-term safety, SR-Site. The initial state refers to the properties of the engineered barriers once they have been finally placed in the KBS-3 repository and will not be further handled within the repository facility. In addition, the report provides some input to the operational safety report, SR-Operation, on how the closure and plugs shall be handled and installed. The report presents the design premises and reference designs of the closure and plugs and verifies their conformity to the design premises. It also briefly deals with the production of the closure and plugs. Finally, the initial state of the closure and plugs and their conformity to the reference designs and design premises are presented

  9. Design, production and initial state of the closure

    Energy Technology Data Exchange (ETDEWEB)

    2010-12-15

    The report is included in a set of Production reports, presenting how the KBS-3 repository is designed, produced and inspected. The production reports are included in the safety report for the KBS-3 repository and repository facility. The report provides input on the initial state of the closure and plugs in underground openings other than deposition tunnels for the assessment of the long-term safety, SR-Site. The initial state refers to the properties of the engineered barriers once they have been finally placed in the KBS-3 repository and will not be further handled within the repository facility. In addition, the report provides some input to the operational safety report, SR-Operation, on how the closure and plugs shall be handled and installed. The report presents the design premises and reference designs of the closure and plugs and verifies their conformity to the design premises. It also briefly deals with the production of the closure and plugs. Finally, the initial state of the closure and plugs and their conformity to the reference designs and design premises are presented

  10. Effect of Co-Composting Cattle Manure with Construction and Demolition Waste on the Archaeal, Bacterial, and Fungal Microbiota, and on Antimicrobial Resistance Determinants.

    Science.gov (United States)

    Holman, Devin B; Hao, Xiying; Topp, Edward; Yang, Hee Eun; Alexander, Trevor W

    2016-01-01

    Agricultural operations generate large quantities of manure which must be eliminated in a manner that is consistent with public health guidelines. Meanwhile, construction and demolition waste makes up about 25% of total solid municipal waste. Co-composting of manure with construction and demolition waste offers a potential means to make manure safe for soil amendment and also divert construction and demolition waste from municipal landfills. Therefore, the archaeal, bacterial, and fungal microbiota of two different types of composted cattle manure and one co-composted with construction and demolition waste, were assessed over a 99-day composting period. The microbiota of the three compost mixtures did not differ, but significant changes over time and by sampling depth were observed. Bacillus and Halocella, however, were more relatively abundant in composted manure from cattle fed dried distillers' grains and solubles. Proteobacteria and Bacteroidetes were enriched at day 0 and Firmicutes at day 99. The fungal genus Kernia was the most relatively abundant overall and was enriched at day 0. The concentration of 12 antimicrobial resistance determinants in the compost mixtures was also determined, and 10 of these determinants decreased significantly from days 0 to 99. The addition of construction and demolition waste did not affect the persistence of antimicrobial resistance genes or community structure of the compost microbiota and therefore co-composting construction and demolition waste with cattle manure offers a safe, viable way to divert this waste from landfills.

  11. Effect of Co-Composting Cattle Manure with Construction and Demolition Waste on the Archaeal, Bacterial, and Fungal Microbiota, and on Antimicrobial Resistance Determinants

    Science.gov (United States)

    Holman, Devin B.; Hao, Xiying; Topp, Edward; Yang, Hee Eun; Alexander, Trevor W.

    2016-01-01

    Agricultural operations generate large quantities of manure which must be eliminated in a manner that is consistent with public health guidelines. Meanwhile, construction and demolition waste makes up about 25% of total solid municipal waste. Co-composting of manure with construction and demolition waste offers a potential means to make manure safe for soil amendment and also divert construction and demolition waste from municipal landfills. Therefore, the archaeal, bacterial, and fungal microbiota of two different types of composted cattle manure and one co-composted with construction and demolition waste, were assessed over a 99-day composting period. The microbiota of the three compost mixtures did not differ, but significant changes over time and by sampling depth were observed. Bacillus and Halocella, however, were more relatively abundant in composted manure from cattle fed dried distillers’ grains and solubles. Proteobacteria and Bacteroidetes were enriched at day 0 and Firmicutes at day 99. The fungal genus Kernia was the most relatively abundant overall and was enriched at day 0. The concentration of 12 antimicrobial resistance determinants in the compost mixtures was also determined, and 10 of these determinants decreased significantly from days 0 to 99. The addition of construction and demolition waste did not affect the persistence of antimicrobial resistance genes or community structure of the compost microbiota and therefore co-composting construction and demolition waste with cattle manure offers a safe, viable way to divert this waste from landfills. PMID:27300323

  12. Life cycle assessment and life cycle costing for demolition waste management

    NARCIS (Netherlands)

    Hu, M.; Miranda-Xicotencat, B.; Ita-Nagy, D.; Prado, V.; Guinée, J.B.; van Roekel, E; Huismans, R.; Rens, F.; Lotfi, Somayeh; Di Maio, F.; Di Maio, F.; Lotfi, S.; Bakker, M.; Hu, M.; Vahidi, A.

    2017-01-01

    Ninety five percent of the construction and demolition waste is recycled in the Netherlands. Most of it is used for low value applications such as road base materials; the use of secondary material in buildings is still less than 3%7. In order to recover waste for higher value applications,

  13. Portland blended cements: demolition ceramic waste management

    International Nuclear Information System (INIS)

    Trezza, M.A.; Zito, S.; Tironi, A.; Irassar, E.F.; Rahhal, V.F.

    2017-01-01

    Demolition ceramic wastes (DCWs) were investigated in order to determine their potential use as supplementary cementitious materials in Portland Blended Cements (PBCs). For this purpose, three ceramic wastes were investigated. After characterization of the materials used, the effect of ceramic waste replacement (8, 24 and 40% by mass) was analyzed. Pozzolanic activity, hydration progress, workability and compressive strength were determined at 2, 7 and 28 days. The results showed that the ground wastes behave as filler at an early age, but as hydration progresses, the pozzolanic activity of ceramic waste contributes to the strength requirement. [es

  14. Corrective Action Decision Document/Closure Report for Corrective Action Unit 511: Waste Dumps (Piles and Debris) Nevada Test Site, Nevada, Rev. No.: 0

    Energy Technology Data Exchange (ETDEWEB)

    Pastor, Laura

    2005-12-01

    This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit (CAU) 511, Waste Dumps (Piles & Debris). The CAU is comprised of nine corrective action sites (CASs) located in Areas 3, 4, 6, 7, 18, and 19 of the Nevada Test Site, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (1996). Corrective Action Unit 511 is comprised of nine CASs: (1) 03-08-02, Waste Dump (Piles & Debris); (2) 03-99-11, Waste Dump (Piles); (3) 03-99-12, Waste Dump (Piles & Debris); (4) 04-99-04, Contaminated Trench/Berm; (5) 06-16-01, Waste Dump (Piles & Debris); (6) 06-17-02, Scattered Ordnance/Automatic Weapons Range; (7) 07-08-01, Contaminated Mound; (8) 18-99-10, Ammunition Dump; and (9) 19-19-03, Waste Dump (Piles & Debris). The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation for closure of CAU 511 with no further corrective action. To achieve this, corrective action investigation (CAI) and closure activities were performed from January 2005 through August 2005, as set forth in the ''Corrective Action Investigation Plan for Corrective Action Unit 511: Waste Dumps (Piles & Debris)'' (NNSA/NSO, 2004) and Record of Technical Change No. 1. The purpose of the CAI was to fulfill the following data needs as defined during the data quality objective process: (1) Determine whether contaminants of concern (COCs) are present. (2) If COCs are present, determine their nature and extent. (3) Provide sufficient information and data to complete appropriate corrective actions. The CAU 511 dataset from the investigation results was evaluated based on the data quality indicator parameters. This evaluation demonstrated the quality and acceptability of the dataset for use in fulfilling the data quality objective data needs. Analytes detected during the CAI were evaluated against appropriate preliminary

  15. Patient Satisfaction After Femoral Arterial Access Site Closure Using the ExoSeal® Vascular Closure Device Compared to Manual Compression: A Prospective Intra-individual Comparative Study

    International Nuclear Information System (INIS)

    Pieper, Claus Christian; Thomas, Daniel; Nadal, Jennifer; Willinek, Winfried A.; Schild, Hans Heinz; Meyer, Carsten

    2016-01-01

    PurposeTo intra-individually compare discomfort levels and patient satisfaction after arterial access closure using the ExoSeal ® vascular closure device (VCD) and manual compression (MC) in a prospective study design.MethodsPatients undergoing two planned interventions from 07/2013 to 09/2014 could participate in the study. Access closure was performed with an ExoSeal ® -VCD in one and MC in the other intervention. Patients were clinically and sonographically examined and were given questionnaires 1 day after intervention [groin- and back-pain during bedrest (100-point visual analog scale; 0: no pain); comfortability of bedrest (10-point Likert scale, 1: comfortable), satisfaction with closure (10-point Likert scale, 1: very satisfied)]. Results were analyzed in a cross-over design.Results48 patients (29 male, median age 62.5 (32–88) years) were included. An ExoSeal ® -VCD was used first in 25 cases. As four of these subsequently refused MC as second intervention, data from 44 patients could be analyzed. All closures were technically successful (successful device deployment) without major complications. Groin- and back-pain after VCD-use/MC was 0 (0–15) vs. 10 (0–80) and 0 (0–75) vs. 25 (0–90), respectively (p < 0.0001). Bedrest after VCD-use was more comfortable than after MC [1 (range 1–7) vs. 6 (2–10); p < 0.0001]. Satisfaction with the closure procedure and with the intervention in general was higher after VCD-use compared to MC [1 (1–3) vs. 5 (2–10) and 1 (1–2) vs. 2 (1–4), respectively; p < 0.0001].ConclusionIntra-individual comparison showed pain levels and discomfort to be significantly lower after ExoSeal ® use compared to MC. VCD closure was associated with higher satisfaction both with the closure itself and with the intervention in general

  16. Identifying areas under potential risk of illegal construction and demolition waste dumping using GIS tools.

    Science.gov (United States)

    Seror, Nissim; Portnov, Boris A

    2018-05-01

    Construction and demolition (C&D) waste, dumped illegally in ravines and open areas, contaminates soil and can cause underground water pollution and forests fires. Yet, effective monitoring of illegal C&D waste dumping and enforcing legislation against the offenders are often a difficult task due to the large size of geographic areas that need to be monitored, and limited human and financial resources available to environmental law enforcement agencies. In this study, we use Geographic Information System (GIS) tools and geo-statistical modelling to identify the areas under potentially elevated risk of illegal C&D waste dumping in the Haifa district of Israel. As our analysis shows, locational factors, significantly associated with the accumulated amount of waste in the existing illegal C&D waste sites, include: distance to the nearest main road, depth of the ravine present at the site (pwaste dumping for future monitoring. As we suggest, the proposed approach may be useful for environmental law enforcement authorities, by helping them to focus on specific sites for inspection, save resources, and act against the offenders more efficiently. Copyright © 2018 Elsevier Ltd. All rights reserved.

  17. Closure Report Central Nevada Test Area Subsurface Corrective Action Unit 443 January 2016

    Energy Technology Data Exchange (ETDEWEB)

    Findlay, Rick [US Department of Energy, Washington, DC (United States). Office of Legacy Management

    2015-11-01

    The U.S. Department of Energy (DOE) Office of Legacy Management (LM) prepared this Closure Report for the subsurface Corrective Action Unit (CAU) 443 at the Central Nevada Test Area (CNTA), Nevada, Site. CNTA was the site of a 0.2- to 1-megaton underground nuclear test in 1968. Responsibility for the site’s environmental restoration was transferred from the DOE, National Nuclear Security Administration, Nevada Field Office to LM on October 1, 2006. The environmental restoration process and corrective action strategy for CAU 443 are conducted in accordance with the Federal Facility Agreement and Consent Order (FFACO 1996, as amended 2011) and all applicable Nevada Division of Environmental Protection (NDEP) policies and regulations. This Closure Report provides justification for closure of CAU 443 and provides a summary of completed closure activities; describes the selected corrective action alternative; provides an implementation plan for long-term monitoring with well network maintenance and approaches/policies for institutional controls (ICs); and presents the contaminant, compliance, and use-restriction boundaries for the site.

  18. Corrective Action Decision Document/Closure Report for Corrective Action Unit 232: Area 25 Sewage Lagoons, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    US Department of Energy Nevada Operations Office

    1999-01-01

    This Corrective Action Decision Document/Closure Report (CADD/CR) has been prepared for Corrective Action Unit (CAU) 232, Area 25 Sewage Lagoons, in accordance with the Federal Facility Agreement and Consent Order. Located at the Nevada Test Site in Nevada, approximately 65 miles northwest of Las Vegas, CAU 232 is comprised of Corrective Action Site 25-03-01, Sewage Lagoon. This CADD/CR identifies and rationalizes the U.S. Department of Energy, Nevada Operations Office's (DOE/NV's) recommendation that no corrective action is deemed necessary for CAU 232. The Corrective Action Decision Document and Closure Report have been combined into one report because sample data collected during the July 1999 corrective action investigation (CAI) activities disclosed no evidence of contamination at the site. Contaminants of potential concern (COPCs) addressed during the CAI included total volatile organic compounds, total semivolatile organic compounds, total Resource Conservation and Recovery Act metals, total pesticides, total herbicides, total petroleum hydrocarbons (gasoline and diesel/oil range), polychlorinated biphenyls, isotopic uranium, isotopic plutonium, strontium-90, and gamma-emitting radionuclides. The data confirmed that none of the COPCs identified exceeded preliminary action levels outlined in the CAIP; therefore, no corrective actions were necessary for CAU 232. After the CAI, best management practice activities were completed and included installation of a fence and signs to limit access to the lagoons, cementing Manhole No. 2 and the diverter box, and closing off influent and effluent ends of the sewage lagoon piping. As a result of the CAI, the DOE/NV recommended that: (1) no further actions were required; (2) no Corrective Action Plan would be required; and (3) no use restrictions were required to be placed on the CAU

  19. Assessment of leaching from Construction & Demolition Waste concrete

    DEFF Research Database (Denmark)

    Butera, Stefania; Christensen, Thomas Højlund; Astrup, Thomas

    2012-01-01

    Construction and demolition waste features two very important properties when considering its management options: the large amounts, and the low environmental hazardousness. Therefore, concrete waste can be recycled relatively easily: most common end-of-life option is utilization as unbound...... approaches exist, often implying unrealistic or not relevant conditions if compared to real life utilization scenarios. A modified version of the CEN/TS 14405 column percolation test has been implemented on four crushed concrete samples, with the purpose of analysing the release of chromium, one...

  20. Dehomed: the impacts of house demolitions on the well-being of women from the unrecognized Bedouin-Arab villages in the Negev/Israel.

    Science.gov (United States)

    Gottlieb, Nora; Feder-Bubis, Paula

    2014-09-01

    Thirty-five Bedouin-Arab villages in South Israel are regarded illegal settlements by the state. Consequently, the residents׳ homes are subject to demolition. Based on 12 semi-structured multiple-participant interviews, this paper examines the house demolitions׳ impacts on women, in the context of gendered constructions of social roles and space. It highlights that the marginalized position of Arab-Bedouin women - as women in a patriarchal community, as members of a minority within Israeli society, and as residents of an "invisible" settlement - contributes to the devastating effects of the house demolitions. In particular, the study׳s results show that the house demolitions inflict severe personal and collective trauma, amplified by women׳s primary role as mothers. Paradoxically, the very same role also becomes a source of resilience and political resistance, as women act to defend a sense of home and restore family life in the face of state violence. Copyright © 2014 Elsevier Ltd. All rights reserved.

  1. Composite three-layer closure of oral antral communication with 10 months follow-up-a case study.

    Science.gov (United States)

    Weinstock, Robert J; Nikoyan, Levon; Dym, Harry

    2014-02-01

    We propose a 3-layer composite closure technique for an oral antral communication (OAC) while avoiding secondary donor site morbidity. A patient had developed a 1-cm OAC after extraction of right maxillary first molar. The patient subsequently developed acute maxillary sinusitis. The patient was taken to the operating room, and a Caldwell-Luc procedure was performed. The bony window from the Caldwell-Luc was "press fit" over the bony OAC defect. Soft tissue closure was then achieved with a buccal fat pad flap and a buccal mucosal advancement flap. The patient was examined on postoperative day 5 and 1, 2, 3, 6, and 10 months postoperatively. The acute sinusitis had resolved. The soft tissue closure was successful. The bone graft remained intact, prevented sinus pneumatization, and restored continuity to the floor of the maxillary sinus. The presented technique for 3-layer closure of OACs allows for the stability of a double-layer closure of OAC with the added benefit of bone grafting from single operative site, achieving stable oral antral closure, bone grafting, and the avoidance of secondary donor site morbidity. Copyright © 2014 American Association of Oral and Maxillofacial Surgeons. Published by Elsevier Inc. All rights reserved.

  2. AX Tank Farm tank removal study

    International Nuclear Information System (INIS)

    SKELLY, W.A.

    1998-01-01

    This report considers the feasibility of exposing, demolishing, and removing underground storage tanks from the 241-AX Tank Farm at the Hanford Site. For the study, it was assumed that the tanks would each contain 360 ft 3 of residual waste (corresponding to the one percent residual Inventory target cited in the Tri-Party Agreement) at the time of demolition. The 241-AX Tank Farm is being employed as a ''strawman'' in engineering studies evaluating clean and landfill closure options for Hanford single-shell tank farms. The report is one of several reports being prepared for use by the Hanford Tanks Initiative Project to explore potential closure options and to develop retrieval performance evaluation criteria for tank farms

  3. Significant skin-tightening by closure of fractional ablative laser holes.

    Science.gov (United States)

    Russe, Elisabeth; Purschke, Martin; Limpiangkanan, Wikunda; Farinelli, William A; Wang, Ying; Doukas, Apostolos G; Sakamoto, Fernanda H; Wechselberger, Gottfried; Anderson, Richard Rox

    2018-01-01

    Ablative fractional laser treatment uses thousands of very small laser beam wounds to damage a fraction of the skin, which stimulates tissue remodeling. Each open micro-wound heals without scarring, but the amount of skin tightening achieved is limited. This animal study was performed to test the hypothesis that immediate temporary closure of fractional laser wounds could increase skin tightening after fractional ablative laser treatment. Four adult swine were used for the study; 98 square test sites (3 × 3 cm) were tattooed on the abdomen and flanks of each pig. An ablative fractional Erbium:YAG laser (Sciton Profile, Sciton Inc, Palo Alto, CA) was used to treat the test areas. A laser micro-spot fluence of 375 J/cm 2 was delivered in 150-250 microseconds pulses, resulting in an array of ablation channels extending 1.5 mm deep into the skin, with a spot size of 250 µm, with 10% treatment density. Immediately following laser exposure the resulting holes were closed using a stretched elastic adhesive dressing, which, when applied, recoiled and compressed the diameter of the ablation holes. The compressive dressings were removed after 7 days. This procedure was compared to removing the same amount of skin (10%) mechanically by specially designed 19 gauge coring needles, as well as to the same laser and coring methods without compression closure. Area and shape of test sites were measured by digital photography before and 28 days after treatment. Data analysis included compensation for animal growth, as measured by increase in the area of the untreated control sites. All treated and control sites healed within a week, without scarring evident at 28 days. Laser treatment combined with compressive wound closure caused significant shrinkage at 28 days compared with untreated control sites. The treated skin area was reduced by 11.5% (P = 0.0001). Needle coring with wound closure produced similar, significant shrinkage (8%, P < 0.0021), whereas laser

  4. Economic evaluation of closure CAP barrier materials Volume I and Volume II

    International Nuclear Information System (INIS)

    Serrato, M.G.; Bhutani, J.S.; Mead, S.M.

    1993-09-01

    This study prepared by the Site Geotechnical Services (SGS) and Environmental Restoration (ER) departments of the WSRC evaluates a generic closure cover system for a hazardous waste site, using 10 different surface areas, ranging from 0.1 acre to 80 acres, and 12 barrier materials. This study presents a revision to the previous study (Rev. 0) published in June 1993, under the same title. The objective of this study was to revise the previous study by incorporating four additional site sizes into the evaluation process and identifying the most cost-effective barrier material for a given closure cover system at the SRS

  5. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2007

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2008-01-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2007 and includes inspection and repair activities completed at the following nine CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 404: Roller Coaster Lagoons and Trench (TTR); (3) CAU 407: Roller Coaster RadSafe Area (TTR); (4) CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); (5) CAU 424: Area 3 Landfill Complexes (TTR); (6) CAU 426: Cactus Spring Waste Trenches (TTR); (7) CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); (8) CAU 453: Area 9 UXO Landfill (TTR); and (9) CAU 487: Thunderwell Site (TTR). In a letter from the Nevada Division of Environmental Protection (NDEP) dated December 5, 2006, NDEP concurred with the request to reduce the frequency of post-closure inspections of CAUs at TTR to an annual frequency. This letter is included in Attachment B. Post-closure inspections were conducted on May 15-16, 2007. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in May 2007, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 453. Animal burrows observed during the annual inspection at CAU 453 were backfilled on August 1, 2007. At this time, the TTR post-closure site inspections should continue as

  6. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2007

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2008-06-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2007 and includes inspection and repair activities completed at the following nine CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 404: Roller Coaster Lagoons and Trench (TTR); (3) CAU 407: Roller Coaster RadSafe Area (TTR); (4) CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); (5) CAU 424: Area 3 Landfill Complexes (TTR); (6) CAU 426: Cactus Spring Waste Trenches (TTR); (7) CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); (8) CAU 453: Area 9 UXO Landfill (TTR); and (9) CAU 487: Thunderwell Site (TTR). In a letter from the Nevada Division of Environmental Protection (NDEP) dated December 5, 2006, NDEP concurred with the request to reduce the frequency of post-closure inspections of CAUs at TTR to an annual frequency. This letter is included in Attachment B. Post-closure inspections were conducted on May 15-16, 2007. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in May 2007, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 453. Animal burrows observed during the annual inspection at CAU 453 were backfilled on August 1, 2007. At this time, the TTR post-closure site inspections should continue as

  7. Vacuum-assisted closure versus closure without vacuum assistance for preventing surgical site infections and infections of chronic wounds: a meta-analysis of randomized controlled trials.

    Science.gov (United States)

    Tansarli, Giannoula S; Vardakas, Konstantinos Z; Stratoulias, Constantinos; Peppas, George; Kapaskelis, Anastasios; Falagas, Matthew E

    2014-08-01

    We sought to examine whether vacuum-assisted closure (VAC) is associated with fewer surgical site infections (SSIs) or infections of chronic wounds than other management procedures for surgical wounds. The PubMed and Scopus databases were searched systematically. Randomized controlled trials (RCTs) comparing the development of SSIs or infections of chronic wounds between patients treated with VAC for acute or chronic wounds and those whose wounds were treated without VAC were considered eligible for inclusion in the study. Eight RCTs met the inclusion criteria for the study. Four of the studies included chronic or diabetic lower extremity wounds and four included fractures. In three of four studies reporting on fractures, the wounds were not closed post-operatively, whereas in one study primary closure of the wound was performed. With regard to wounds left open after the stabilization of fractures, patients whose wounds were treated with VAC developed fewer SSIs than those whose wounds were treated without VAC ([367 patients (196 with VAC; 171 without VAC) relative risk [RR], 0.47; 95% CI 0.28-0.81]). On the contrary, no difference in the development of SSIs occurred among patients with chronic or diabetic lower-extremity wounds treated with VAC and those whose wounds were treated without VAC ([638 patients (320 with VAC; 318 without VAC) RR 1.67; 95% CI: 0.71-3.94]). The available evidence suggests that the development of infections in wounds treated with VAC depends on the type of wound being treated.

  8. Environmental Assessment for the Closure of the High-Level Waste Tanks in F- & H-Areas at the Savannah River Site

    Energy Technology Data Exchange (ETDEWEB)

    N/A

    1996-07-31

    This Environmental Assessment (EA) has been prepared by the Department of Energy (DOE) to assess the potential environmental impacts associated with the closure of 51 high-level radioactive waste tanks and tank farm ancillary equipment (including transfer lines, evaporators, filters, pumps, etc) at the Savannah River Site (SRS) located near Aiken, South Carolina. The waste tanks are located in the F- and H-Areas of SRS and vary in capacity from 2,839,059 liters (750,000 gallons) to 4,921,035 liters (1,300,000 gallons). These in-ground tanks are surrounded by soil to provide shielding. The F- and H-Area High-Level Waste Tanks are operated under the authority of Industrial Wastewater Permits No.17,424-IW; No.14520, and No.14338 issued by the South Carolina Department of Health and Environmental Control (SCDHEC). In accordance with the Permit requirements, DOE has prepared a Closure Plan (DOE, 1996) and submitted it to SCDHEC for approval. The Closure Plan identifies all applicable or relevant and appropriate regulations, statutes, and DOE Orders for closing systems operated under the Industrial Wastewater Permits. When approved by SCDHEC, the Closure Plan will present the regulatory process for closing all of the F- and H-Area High Level Waste Tanks. The Closure Plan establishes performance objectives or criteria to be met prior to closing any tank, group of tanks, or ancillary tank farm equipment. The proposed action is to remove the residual wastes from the tanks and to fill the tanks with a material to prevent future collapse and bind up residual waste, to lower human health risks, and to increase safety in and around the tanks. If required, an engineered cap consisting of clay, backfill (soil), and vegetation as the final layer to prevent erosion would be applied over the tanks. The selection of tank system closure method will be evaluated against the following Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) criteria described in 40

  9. Corrective Action Decision Document/Closure Report for Corrective Action Unit 550: Smoky Contamination Area Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick K. [Navarro-Intera, LLC (N-I), Las Vegas, NV (United States)

    2015-02-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 550: Smoky Contamination Area, Nevada National Security Site, Nevada. CAU 550 includes 19 corrective action sites (CASs), which consist of one weapons-related atmospheric test (Smoky), three safety experiments (Ceres, Oberon, Titania), and 15 debris sites (Table ES-1). The CASs were sorted into the following study groups based on release potential and technical similarities: • Study Group 1, Atmospheric Test • Study Group 2, Safety Experiments • Study Group 3, Washes • Study Group 4, Debris The purpose of this document is to provide justification and documentation supporting the conclusion that no further corrective action is needed for CAU 550 based on implementation of the corrective actions listed in Table ES-1. Corrective action investigation (CAI) activities were performed between August 2012 and October 2013 as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 550: Smoky Contamination Area; and in accordance with the Soils Activity Quality Assurance Plan. The approach for the CAI was to investigate and make data quality objective (DQO) decisions based on the types of releases present. The purpose of the CAI was to fulfill data needs as defined during the DQO process. The CAU 550 dataset of investigation results was evaluated based on a data quality assessment. This assessment demonstrated the dataset is complete and acceptable for use in fulfilling the DQO data needs.

  10. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part III

    International Nuclear Information System (INIS)

    2011-01-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  11. Presentation of safety after closure of the repository for spent nuclear fuel. Main report of the project SR-Site. Part I

    International Nuclear Information System (INIS)

    2011-01-01

    The purpose of the safety assessment SR-Site is to investigate whether a safe repository for spent nuclear fuel by KBS-3 type can be constructed at Forsmark in Oesthammar in Sweden. The location of the Forsmark has been selected based on results of several surveys from surface conditions at depth in Forsmark and in Laxemar in Oskarshamn. The choice of location is not justified in SR-Site Report, but in other attachments to SKB's permit applications. SR-Site Report is an important part of SKB's permit applications to construct and operate a repository for spent nuclear fuel at Forsmark in Oesthammar. The purpose of the report in the applications is to show that a repository at Forsmark is safe after closure

  12. Proceedings of the tenth annual DOE low-level waste management conference: Session 6: Closure and decommissioning

    International Nuclear Information System (INIS)

    1988-12-01

    This document contains eight papers on various aspects of low-level radioactive waste management. Topics include: site closure; ground cover; alternate cap designs; performance monitoring of waste trenches; closure options for a mixed waste site; and guidance for environmental monitoring. Individual papers were processed separately for the data base

  13. Final Environmental Assessment for solid waste disposal, Nevada Test Site, Nye County, Nevada

    International Nuclear Information System (INIS)

    1995-08-01

    New solid waste regulations require that the existing Nevada Test Site (NTS) municipal landfills, which receive less than 20 tons of waste per day, be permitted or closed by October 9, 1995. In order to be permitted, the existing landfills must meet specific location, groundwater monitoring, design, operation, and closure requirements. The issuance of these regulations has resulted in the need of the Department of Energy (DOE) to provide a practical, cost-effective, environmentally sound means of solid waste disposal at the NTS that is in compliance with all applicable federal, state, and local regulations. The current landfills in Areas 9 and 23 on the Nevada Test Site do not meet design requirements specified in new state and federal regulations. The DOE Nevada Operations Office prepared an environmental assessment (EA) to evaluate the potential impacts of the proposal to modify the Area 23 landfill to comply with the new regulations and to close the Area 9 landfill and reopen it as Construction and Demolition debris landfill. Based on information and analyses presented in the EA, DOE has determined that the proposed action would not constitute a major federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act. Therefore, an environmental impact statement (EIS) is not required. This report contains the Environmental Assessment, as well as the Finding of No Significant Impact (FONSI)

  14. Recycling of rubble from building demolition for low-shrinkage concretes.

    Science.gov (United States)

    Corinaldesi, Valeria; Moriconi, Giacomo

    2010-04-01

    In this project concrete mixtures were prepared that were characterized by low ductility due to desiccation by using debris from building demolition, which after a suitable treatment was used as aggregate for partial replacement of natural aggregates. The recycled aggregate used came from a recycling plant, in which rubble from building demolition was selected, crushed, cleaned, sieved, and graded. Such aggregates are known to be more porous as indicated by the Saturated Surface Dry (SSD) moisture content. The recycled concrete used as aggregates were added to the concrete mixture in order to study their influence on the fresh and hardened concrete properties. They were added either after water pre-soaking or in dry condition, in order to evaluate the influence of moisture in aggregates on the performance of concrete containing recycled aggregate. In particular, the effect of internal curing, due to the use of such aggregates, was studied. Concrete behavior due to desiccation under dehydration was studied by means of both drying shrinkage test and German angle test, through which shrinkage under the restrained condition of early age concrete can be evaluated. Copyright 2009 Elsevier Ltd. All rights reserved.

  15. Development and Implementation of the Waste Management Information System to Support Hanford's River Corridor Cleanup

    Energy Technology Data Exchange (ETDEWEB)

    Nolan, L M [Washington Closure Hanford, LLC, 3070 George Washington Way, Richland, WA 99354 (United States)

    2006-07-01

    This paper describes the development of a Waste Information Management System (WMIS) to support the waste designation, transportation, and disposal processes used by Washington Closure Hanford, LLC to support cleanup of the Columbia River Corridor. This waste, primarily consisting of remediated burial sites and building demolition debris, is disposed at the Environmental Restoration Disposal Facility (ERDF), which is located in the center of the Hanford Site (an approximately 1460 square kilometers site). WMIS uses a combination of bar-code scanning, hand-held computers, and strategic employment of a radio frequency identification (RFID) tag system to track each waste shipment from waste generation to disposal. (authors)

  16. Corrective Action Decision Document/Closure Report for Corrective Action Unit 367: Area 10 Sedan, Ess and Uncle Unit Craters Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Patrick Matthews

    2011-06-01

    Corrective Action Unit 367 comprises four corrective action sites (CASs): • 10-09-03, Mud Pit • 10-45-01, U-10h Crater (Sedan) • 10-45-02, Ess Crater Site • 10-45-03, Uncle Crater Site The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation of the corrective actions and site closure activities implemented at CAU 367. A corrective action of closure in place with use restrictions was completed at each of the three crater CASs (10-45-01, 10-45-02, and 10-45-03); corrective actions were not required at CAS 10-09-03. In addition, a limited soil removal corrective action was conducted at the location of a potential source material release. Based on completion of these correction actions, no additional corrective action is required at CAU 367, and site closure is considered complete. Corrective action investigation (CAI) activities were performed from February 2010 through March 2011, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 367: Area 10 Sedan, Ess and Uncle Unit Craters, Nevada Test Site, Nevada. The approach for the CAI was divided into two facets: investigation of the primary release of radionuclides, and investigation of non-test or other releases (e.g., migration in washes and potential source material). Based on the proximity of the Uncle, Ess, and Sedan craters, the impact of the Sedan test on the fallout deposited from the two earlier tests, and aerial radiological surveys, the CAU 367 investigation was designed to study the releases from the three crater CASs as one combined release (primary release). Corrective Action Site 10-09-03, Mud Pit, consists of two mud pits identified at CAU 367. The mud pits are considered non-test releases or other releases and were investigated independent of the three crater CASs. The purpose of the CAI was to fulfill data needs as defined during the data quality objective (DQO) process. The CAU 367 dataset of

  17. An estimation framework for building information modeling (BIM)-based demolition waste by type.

    Science.gov (United States)

    Kim, Young-Chan; Hong, Won-Hwa; Park, Jae-Woo; Cha, Gi-Wook

    2017-12-01

    Most existing studies on demolition waste (DW) quantification do not have an official standard to estimate the amount and type of DW. Therefore, there are limitations in the existing literature for estimating DW with a consistent classification system. Building information modeling (BIM) is a technology that can generate and manage all the information required during the life cycle of a building, from design to demolition. Nevertheless, there has been a lack of research regarding its application to the demolition stage of a building. For an effective waste management plan, the estimation of the type and volume of DW should begin from the building design stage. However, the lack of tools hinders an early estimation. This study proposes a BIM-based framework that estimates DW in the early design stages, to achieve an effective and streamlined planning, processing, and management. Specifically, the input of construction materials in the Korean construction classification system and those in the BIM library were matched. Based on this matching integration, the estimates of DW by type were calculated by applying the weight/unit volume factors and the rates of DW volume change. To verify the framework, its operation was demonstrated by means of an actual BIM modeling and by comparing its results with those available in the literature. This study is expected to contribute not only to the estimation of DW at the building level, but also to the automated estimation of DW at the district level.

  18. LLNL/YMP Waste Container Fabrication and Closure Project

    International Nuclear Information System (INIS)

    1990-10-01

    The Department of Energy's Office of Civilian Radioactive Waste Management (OCRWM) Program is studying Yucca Mountain, Nevada as a suitable site for the first US high-level nuclear waste repository. Lawrence Livermore National Laboratory (LLNL) has the responsibility for designing and developing the waste package for the permanent storage of high-level nuclear waste. This report is a summary of the technical activities for the LLNL/YMP Nuclear Waste Disposal Container Fabrication and Closure Development Project. Candidate welding closure processes were identified in the Phase 1 report. This report discusses Phase 2. Phase 2 of this effort involved laboratory studies to determine the optimum fabrication and closure processes. Because of budget limitations, LLNL narrowed the materials for evaluation in Phase 2 from the original six to four: Alloy 825, CDA 715, CDA 102 (or CDA 122) and CDA 952. Phase 2 studies focused on evaluation of candidate material in conjunction with fabrication and closure processes

  19. Construction and demolition waste as a source of PVC for recycling.

    Science.gov (United States)

    Prestes, Sabrina Moretto Darbello; Mancini, Sandro Donnini; Rodolfo, Antonio; Keiroglo, Raquel Carramillo

    2012-02-01

    Construction and demolition waste can contain considerable amounts of polyvinyl chloride (PVC). This paper describes a study of the recycling of PVC pipes collected from such waste materials. In a sorting facility for the specific disposal of construction and demolition waste, PVC was found to represent one-third of the plastics separated by workers. Pipes were sorted carefully to preclude any possible contamination by poly(ethylene terephthalate) (PET) found in the waste. The material was ground into two distinct particle sizes (final mesh of 12.7 and 8 mm), washed, dried and recycled. The average formulation of the pipes was determined based on ash content tests and used in the fabrication of a similar compound made mainly of virgin PVC. Samples of recycled pipes and of compound based on virgin material were subjected to tensile and impact tests and provided very similar results. These results are a good indication of the application potential of the recycled material and of the fact that longer grinding to obtain finer particles is not necessarily beneficial.

  20. Percutaneous Transcatheter PDA Device Closure in Infancy

    International Nuclear Information System (INIS)

    Ullah, M.; Sultan, M.; Akhtar, K.; Sadiq, N.; Akbar, H.

    2014-01-01

    Objective: To evaluate the results and complications associated with transcatheter closure of patent ductus arteriosus (PDA) in infants. Study Design: Quasi-experimental study. Place and Duration of Study: Paediatric Cardiology Department of Armed Forces Institute of Cardiology / National Institute of Heart Diseases (AFIC/NIHD), Rawalpindi, from December 2010 to June 2012. Methodology: Infants undergoing transcatheter device closure of PDA were included. All patients were evaluated by experienced Paediatric Cardiologists with 2-D echocardiography and Doppler before the procedure. Success of closure and complications were recorded. Results: The age of patients varied from 05 - 12 months and 31 (56.4%) were females. Out of the 55 infants, 3 (5.4%) were not offered device closure after aortogram (two large tubular type ducts and one tiny duct, considered unsuitable for device closure); while in 50 (96.1%) patients out of remaining 52, the duct was successfully closed with transcatheter PDA device or coil. In one infant, device deployment resulted in acquired coarctation, necessitating device retrieval by Snare followed by surgical duct interruption and another patient had non-fatal cardiac arrest during device deployment leading to abandonment of procedure and subsequent successful surgical interruption. Local vascular complications occurred in 12 (21.8%) of cases and all were satisfactorily treated. Conclusion: Transcatheter device closure of PDA in infants was an effective procedure in the majority of cases; however, here were considerable number of local access site vascular complications. (author)

  1. Corrective Action Decision Document/Closure Report for Corrective Action Unit 371: Johnnie Boy Crater and Pin Stripe Nevada Test Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Patrick Matthews

    2010-07-01

    This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit 371, Johnnie Boy Crater and Pin Stripe, located within Areas 11 and 18 at the Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit (CAU) 371 comprises two corrective action sites (CASs): • 11-23-05, Pin Stripe Contamination Area • 18-45-01, U-18j-2 Crater (Johnnie Boy) The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 371 based on the implementation of corrective actions. The corrective action of closure in place with administrative controls was implemented at both CASs. Corrective action investigation (CAI) activities were performed from January 8, 2009, through February 16, 2010, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 371: Johnnie Boy Crater and Pin Stripe. The approach for the CAI was divided into two facets: investigation of the primary release of radionuclides and investigation of other releases (migration in washes and chemical releases). The purpose of the CAI was to fulfill data needs as defined during the data quality objective (DQO) process. The CAU 371 dataset of investigation results was evaluated based on the data quality indicator parameters. This evaluation demonstrated the dataset is acceptable for use in fulfilling the DQO data needs. Analytes detected during the CAI were evaluated against final action levels (FALs) established in this document. Radiological doses exceeding the FAL of 25 millirem per year were not found to be present in the surface soil. However, it was assumed that radionuclides are present in subsurface media within the Johnnie Boy crater and the fissure at Pin Stripe. Due to the assumption of radiological dose exceeding the FAL, corrective actions were undertaken

  2. Site Development, Operations, and Closure Plan Topical Report 5 An Assessment of Geologic Carbon Sequestration Options in the Illinois Basin. Phase III

    Energy Technology Data Exchange (ETDEWEB)

    Finley, Robert [Univ. of Illinois, Champaign, IL (United States); Payne, William [Schlumberger Carbon Services, Houston, TX (United States); Kirksey, Jim [Univ. of Illinois, Champaign, IL (United States)

    2015-06-01

    The Midwest Geological Sequestration Consortium (MGSC) has partnered with Archer Daniels Midland Company (ADM) and Schlumberger Carbon Services to conduct a large-volume, saline reservoir storage project at ADM’s agricultural products processing complex in Decatur, Illinois. The Development Phase project, named the Illinois Basin Decatur Project (IBDP) involves the injection of 1 million tonnes of carbon dioxide (CO2) into a deep saline formation of the Illinois Basin over a three-year period. This report focuses on objectives, execution, and lessons learned/unanticipated results from the site development (relating specifically to surface equipment), operations, and the site closure plan.

  3. Silica dust control in small-scale building/structure demolition operations using good work practice guidance

    International Nuclear Information System (INIS)

    Muianga, C V; Rice, C H; Succop, P

    2009-01-01

    Work practices can influence exposure, especially in small-scale operations conducted by mobile work crews. This study evaluated the use of information on good work practice in control guidance sheets adapted from UK Silica Essentials guidance sheets by trained workers and supervisors employed in small-scale concrete and masonry demolition operations. A one-page employee silica task-based control guidance sheet for each of four demolition tasks and multiple-page silica control guidance for supervisors were developed. Interactive, hands-on worker training on these task-based good work practice controls was developed. Training was presented to 26 participants from two demolition crews. Feedback on the training and task-based good work practice control guidance sheets was elicited. Observations of work practices were made before and after training. Participants indicated gains in knowledge and checklists were used to document skill attainment. The quality of the training and usefulness of the material/skills was rated high by trainees. Increased use of water to suppress dust and wet cleaning methods on the job were documented following the training. Additional follow-up after training is required to determine long-term impact on sustained changes in work practices, and to evaluate the need for refresher training.

  4. Silica dust control in small-scale building/structure demolition operations using good work practice guidance

    Science.gov (United States)

    Muianga, C. V.; Rice, C. H.; Succop, P.

    2009-02-01

    Work practices can influence exposure, especially in small-scale operations conducted by mobile work crews. This study evaluated the use of information on good work practice in control guidance sheets adapted from UK Silica Essentials guidance sheets by trained workers and supervisors employed in small-scale concrete and masonry demolition operations. A one-page employee silica task-based control guidance sheet for each of four demolition tasks and multiple-page silica control guidance for supervisors were developed. Interactive, hands-on worker training on these task-based good work practice controls was developed. Training was presented to 26 participants from two demolition crews. Feedback on the training and task-based good work practice control guidance sheets was elicited. Observations of work practices were made before and after training. Participants indicated gains in knowledge and checklists were used to document skill attainment. The quality of the training and usefulness of the material/skills was rated high by trainees. Increased use of water to suppress dust and wet cleaning methods on the job were documented following the training. Additional follow-up after training is required to determine long-term impact on sustained changes in work practices, and to evaluate the need for refresher training.

  5. Patient Satisfaction After Femoral Arterial Access Site Closure Using the ExoSeal{sup ®} Vascular Closure Device Compared to Manual Compression: A Prospective Intra-individual Comparative Study

    Energy Technology Data Exchange (ETDEWEB)

    Pieper, Claus Christian, E-mail: claus.christian.pieper@ukb.uni-bonn.de; Thomas, Daniel, E-mail: daniel.thomas@ukb.uni-bonn.de [University of Bonn, Department of Radiology (Germany); Nadal, Jennifer, E-mail: jennifer.nadal@ukb.uni-bonn.de [University of Bonn, Institute for Medical Biometry, Informatics and Epidemiology (Germany); Willinek, Winfried A., E-mail: w.willinek@bk-trier.de; Schild, Hans Heinz, E-mail: hans.schild@ukb.uni-bonn.de; Meyer, Carsten, E-mail: carsten.meyer@ukb.uni-bonn.de [University of Bonn, Department of Radiology (Germany)

    2016-01-15

    PurposeTo intra-individually compare discomfort levels and patient satisfaction after arterial access closure using the ExoSeal{sup ®} vascular closure device (VCD) and manual compression (MC) in a prospective study design.MethodsPatients undergoing two planned interventions from 07/2013 to 09/2014 could participate in the study. Access closure was performed with an ExoSeal{sup ®}-VCD in one and MC in the other intervention. Patients were clinically and sonographically examined and were given questionnaires 1 day after intervention [groin- and back-pain during bedrest (100-point visual analog scale; 0: no pain); comfortability of bedrest (10-point Likert scale, 1: comfortable), satisfaction with closure (10-point Likert scale, 1: very satisfied)]. Results were analyzed in a cross-over design.Results48 patients (29 male, median age 62.5 (32–88) years) were included. An ExoSeal{sup ®}-VCD was used first in 25 cases. As four of these subsequently refused MC as second intervention, data from 44 patients could be analyzed. All closures were technically successful (successful device deployment) without major complications. Groin- and back-pain after VCD-use/MC was 0 (0–15) vs. 10 (0–80) and 0 (0–75) vs. 25 (0–90), respectively (p < 0.0001). Bedrest after VCD-use was more comfortable than after MC [1 (range 1–7) vs. 6 (2–10); p < 0.0001]. Satisfaction with the closure procedure and with the intervention in general was higher after VCD-use compared to MC [1 (1–3) vs. 5 (2–10) and 1 (1–2) vs. 2 (1–4), respectively; p < 0.0001].ConclusionIntra-individual comparison showed pain levels and discomfort to be significantly lower after ExoSeal{sup ®} use compared to MC. VCD closure was associated with higher satisfaction both with the closure itself and with the intervention in general.

  6. 2727-S Nonradioactive Dangerous Waste Storage Facility clean closure evaluation report

    International Nuclear Information System (INIS)

    Luke, S.N.

    1994-01-01

    This report presents the analytical results of 2727-S NRDWS facility closure verification soil sampling and compares these results to clean closure criteria. The results of this comparison will determine if clean closure of the unit is regulatorily achievable. This report also serves to notify regulators that concentrations of some analytes at the site exceed sitewide background threshold levels (DOE-RL 1993b) and/or the limits of quantitation (LOQ). This report also presents a Model Toxics Control Act Cleanup (MTCA) (WAC 173-340) regulation health-based closure standard under which the unit can clean close in lieu of closure to background levels or LOQ in accordance with WAC 173-303-610. The health-based clean closure standard will be closure to MTCA Method B residential cleanup levels. This report reconciles all analyte concentrations reported above background or LOQ to this health-based cleanup standard. Regulator acceptance of the findings presented in this report will qualify the TSD unit for clean closure in accordance with WAC 173-303-610 without further TSD unit soil sampling, or soil removal and/or decontamination. Nondetected analytes require no further evaluation

  7. Infering and Calibrating Triadic Closure in a Dynamic Network

    Science.gov (United States)

    Mantzaris, Alexander V.; Higham, Desmond J.

    In the social sciences, the hypothesis of triadic closure contends that new links in a social contact network arise preferentially between those who currently share neighbours. Here, in a proof-of-principle study, we show how to calibrate a recently proposed evolving network model to time-dependent connectivity data. The probabilistic edge birth rate in the model contains a triadic closure term, so we are also able to assess statistically the evidence for this effect. The approach is shown to work on data generated synthetically from the model. We then apply this methodology to some real, large-scale data that records the build up of connections in a business-related social networking site, and find evidence for triadic closure.

  8. HWMA/RCRA Closure Plan for the Fluorinel Dissolution Process Makeup and Cooling and Heating Systems Voluntary Consent Order SITE-TANK-005 Action Plan Tank Systems INTEC-066, INTEC-067, INTEC-068, and INTEC-072

    International Nuclear Information System (INIS)

    M.E. Davis

    2007-01-01

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act closure plan for the fluorinel dissolution process makeup and cooling and heating systems located in the Fluorinel Dissolution Process and Fuel Storage Facility (CPP-666), Idaho Nuclear Technology and Engineering Center, Idaho National Laboratory Site, was developed to meet milestones established under the Voluntary Consent Order. The systems to be closed include waste piping associated with the fluorinel dissolution process makeup systems. This closure plan presents the closure performance standards and methods of achieving those standards

  9. HWMA/RCRA Closure Plan for the Fluorinel Dissolution Process Makeup and Cooling and Heating Systems Voluntary Consent Order SITE-TANK-005 Action Plan Tank Systems INTEC-066, INTEC-067, INTEC-068, and INTEC-072

    Energy Technology Data Exchange (ETDEWEB)

    M.E. Davis

    2007-05-01

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act closure plan for the fluorinel dissolution process makeup and cooling and heating systems located in the Fluorinel Dissolution Process and Fuel Storage Facility (CPP-666), Idaho Nuclear Technology and Engineering Center, Idaho National Laboratory Site, was developed to meet milestones established under the Voluntary Consent Order. The systems to be closed include waste piping associated with the fluorinel dissolution process makeup systems. This closure plan presents the closure performance standards and methods of achieving those standards.

  10. Radiation protection of the workers, public and the environment during / after uranium site restoration and clean-up of additional contaminated areas

    International Nuclear Information System (INIS)

    Aurelian, F.; Georgescu, D.; Popescu, M.

    2006-01-01

    closure, decommissioning and rehabilitation workings time, it is presented for the working staff the calculation of the supplementary effective doses, which it is exposed to, related to the working type, as it follows: - at the radioactive material relocation: 1.01 mSv/year; - at the stepping, leveling and encapsulation workings: 2.77 mSv/year; - at the underground equipment decommissioning: 1.12 mSv/year; - at the building demolition and underground equipment decommissioning the supplementary effective dose is: 0.5 mSv/year. After site remediation and clean-up of contaminated areas the limits stipulated by the Romanian Nuclear Authority are respected, as it follows: - the ecological restored surface areas and dumps fulfilled the conditions according to which specific activity is less or equal to 0.2 Bq/g and the gamma rate dose is less or equal to 0.3 v/h; - the hydrographic network waters conform to dose values stipulated by the Romanian Nuclear Authority. The calculated supplementary effective doses for the workers did not exceed the value of 20 mSv/year and the ones calculated for the population after the remediation are not exceeding 1 mSv/year. (authors)

  11. Final vegetative cover for closed waste sites

    International Nuclear Information System (INIS)

    Cook, J.R.; Salvo, S.K.

    1993-01-01

    Low-level, hazardous, and mixed waste disposal sites normally require some form of plant material to prevent erosion of the final closure cap. Waste disposal sites are closed and capped in a complex scientific manner to minimize water infiltration and percolation into and through the waste material. Turf type grasses are currently being used as an interim vegetative cover for most sites. This coverage allows for required monitoring of the closure cap for settlement and maintenance activities. The purpose of this five year study was to evaluate plant materials for use on wastes sites after the post-closure care period that are quickly and easily established and economically maintained, retard water infiltration, provide maximum year-round evapotranspiration, are ecologically acceptable and do not harm the closure cap. The results of the study suggest that two species of bamboo (Phyllostachys (P.) bissetii and P. rubromarginata) can be utilized to provide long lived, low maintenance, climax vegetation for the waste sites after surveillance and maintenance requirements have ceased

  12. Mixture optimization of cement treated demolition waste with recycled masonry and concrete

    NARCIS (Netherlands)

    Xuan, D.X.; Houben, L.J.M.; Molenaar, A.A.A.; Shui, Z.H,

    2011-01-01

    Due to environmental reasons and the shortage of natural resources, it is greatly valuable to recycle construction and demolition waste (CDW) as much as possible. One of effective ways to reuse more CDW is to produce a cemented road base material. The recycled CDW however is a mix of recycled

  13. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Science.gov (United States)

    2010-04-01

    ... modifications is cost-effective to return the public housing project or portion of the project to useful life... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false Specific criteria for HUD approval of demolition requests. 970.15 Section 970.15 Housing and Urban Development Regulations Relating to...

  14. Trends in demolition planning and in the cutting techniques employed; Trends bei der Rueckbauplanung und den verwendeten Schneidverfahren

    Energy Technology Data Exchange (ETDEWEB)

    Brueggemann, Pascal [NUKEM Technologies GmbH, Alzenau (Germany)

    2009-08-15

    The past couple of years have seen the continuous further development of cutting techniques employed in demolishing nuclear facilities. This trend is continuing. After mostly mechanical cutting techniques had been used initially, there has been a tendency in the past few years to make increasing use of thermal cutting. Reasons for this preference are the reduced space requirement and the advantages this technique offers in remote handling because of the low weight and the small dimensions of the cutting heads, and the high flexibility in materials to be cut. This results in greater planning reliability in calculating quotations and performing the demolition work. The emissions generated by these techniques are manageable reliably at low additional expense for the required extraction and filter systems. Thermal cutting is likely to achieve wide use in dismantling and demolition of nuclear plant components also in the future. Advanced developments in computer hardware and software allow more and more detailed planning of demolition work. While, in the past, CAD had been applied only to generate two-dimensional drawings, current 3D applications allow animated representations of entire demolition scenes with high accuracy in detail. In this way, potential problems associated with handling large components or using manipulators for cutting can be detected and solved much more easily in the preparatory phase. Although current CAD use can be no substitute for mockup tests, it does help to enhance clearly reliability in planning prior to running mockup tests. (orig.)

  15. Environmental Assessment for the Closure of the High-Level Waste Tanks in F- and H-Areas at the Savannah River Site

    International Nuclear Information System (INIS)

    1996-01-01

    This Environmental Assessment (EA) has been prepared by the Department of Energy (DOE) to assess the potential environmental impacts associated with the closure of 51 high-level radioactive waste tanks and tank farm ancillary equipment (including transfer lines, evaporators, filters, pumps, etc) at the Savannah River Site (SRS) located near Aiken, South Carolina. The waste tanks are located in the F- and H-Areas of SRS and vary in capacity from 2,839,059 liters (750,000 gallons) to 4,921,035 liters (1,300,000 gallons). These in-ground tanks are surrounded by soil to provide shielding. The F- and H-Area High-Level Waste Tanks are operated under the authority of Industrial Wastewater Permits No.17,424-IW; No.14520, and No.14338 issued by the South Carolina Department of Health and Environmental Control (SCDHEC). In accordance with the Permit requirements, DOE has prepared a Closure Plan (DOE, 1996) and submitted it to SCDHEC for approval. The Closure Plan identifies all applicable or relevant and appropriate regulations, statutes, and DOE Orders for closing systems operated under the Industrial Wastewater Permits. When approved by SCDHEC, the Closure Plan will present the regulatory process for closing all of the F- and H-Area High Level Waste Tanks. The Closure Plan establishes performance objectives or criteria to be met prior to closing any tank, group of tanks, or ancillary tank farm equipment. The proposed action is to remove the residual wastes from the tanks and to fill the tanks with a material to prevent future collapse and bind up residual waste, to lower human health risks, and to increase safety in and around the tanks. If required, an engineered cap consisting of clay, backfill (soil), and vegetation as the final layer to prevent erosion would be applied over the tanks. The selection of tank system closure method will be evaluated against the following Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) criteria described in 40

  16. Reduced sulfur compounds in gas from construction and demolition debris landfills.

    Science.gov (United States)

    Lee, Sue; Xu, Qiyong; Booth, Matthew; Townsend, Timothy G; Chadik, Paul; Bitton, Gabriel

    2006-01-01

    The biological conversion of sulfate from disposed gypsum drywall to hydrogen sulfide (H(2)S) in the anaerobic environment of a landfill results in odor problems and possible health concerns at many disposal facilities. To examine the extent and magnitude of such emissions, landfill gas samples from wells, soil vapor samples from the interface of the waste and cover soil, and ambient air samples, were collected from 10 construction and demolition (C&D) debris landfills in Florida and analyzed for H(2)S and other reduced sulfur compounds (RSC). H(2)S was detected in the well gas and soil vapor at all 10 sites. The concentrations in the ambient air above the surface of the landfill were much lower than those observed in the soil vapor, and no direct correlation was observed between the two sampling locations. Methyl mercaptan and carbonyl sulfide were the most frequently observed other RSC, though they occurred at smaller concentrations than H(2)S. This research confirmed the presence of H(2)S at C&D debris landfills. High concentrations of H(2)S may be a concern for employees working on the landfill site. These results indicate that workers should use proper personal protection at C&D debris landfills when involved in excavation, landfill gas collection, or confined spaces. The results indicate that H(2)S is sufficiently diluted in the atmosphere to not commonly pose acute health impacts for these landfill workers in normal working conditions. H(2)S concentrations were extremely variable with measurements occurring over a very large range (from less than 3 ppbv to 12,000 ppmv in the soil vapor and from less than 3 ppbv to 50 ppmv in ambient air). Possible reasons for the large intra- and inter-site variability observed include waste and soil heterogeneities, impact of weather conditions, and different site management practices.

  17. 3718-F Alkali Metal Treatment and Storage Facility Closure Plan. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    None

    1992-11-01

    The Hanford Site, located northwest of the city of Richland, Washington, houses reactors, chemical-separation systems, and related facilities used for the production of special nuclear materials, as well as for activities associated with nuclear energy development. The 300 Area of the Hanford Site contains reactor fuel manufacturing facilities and several research and development laboratories. The 3718-F Alkali Metal Treatment and Storage Facility (3718-F Facility), located in the 300 Area, was used to store and treat alkali metal wastes. Therefore, it is subject to the regulatory requirements for the storage and treatment of dangerous wastes. Closure will be conducted pursuant to the requirements of the Washington Administrative Code (WAC) 173-303-610 (Ecology 1989) and 40 CFR 270.1. Closure also will satisfy the thermal treatment facility closure requirements of 40 CFR 265.381. This closure plan presents a description of the 3718-F Facility, the history of wastes managed, and the approach that will be followed to close the facility. Only hazardous constituents derived from 3718-F Facility operations will be addressed.

  18. Single-shell tank closure work plan. Revision A

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-06-01

    In January 1994, the Hanford Federal Facility Agreement and Conset Order (Tri-Party Agreement) was amended to reflect a revised strategy for remediation of radioactive waste in underground storage tanks. These amendments include milestones for closure of the single-shell tank (SST) operable units, to be initiated by March 2012 and completed by September 2024. This SST-CWP has been prepared to address the principal topical areas identified in Tri-Party Agreement Milestone M-45-06 (i.e., regulatory pathway, operable unit characterization, waste retrieval, technology development, and a strategy for achieving closure). Chapter 2.0 of this SST-CWP provides a brief description of the environmental setting, SST System, the origin and characteristics of SST waste, and ancillary equipment that will be remediated as part of SST operable unit closure. Appendix 2A provides a description of the hydrogeology of the Hanford Site, including information on the unsaturated sediments (vadose zone) beneath the 200 Areas Plateau. Chapter 3.0 provides a discussion of the laws and regulations applicable to closure of the SST farm operable units. Chapter 4.0 provides a summary description of the ongoing characterization activities that best align with the proposed regulatory pathway for closure. Chapter 5.0 describes aspects of the SST waste retrieval program, including retrieval strategy, technology, and sequence, potential tank leakage during retrieval, and considerations of deployment of subsurface barriers. Chapter 6.0 outlines a proposed strategy for closure. Chapter 7.0 provides a summary of the programs underway or planned to develop technologies to support closure. Ca. 325 refs.

  19. Single-shell tank closure work plan. Revision A

    International Nuclear Information System (INIS)

    1995-06-01

    In January 1994, the Hanford Federal Facility Agreement and Conset Order (Tri-Party Agreement) was amended to reflect a revised strategy for remediation of radioactive waste in underground storage tanks. These amendments include milestones for closure of the single-shell tank (SST) operable units, to be initiated by March 2012 and completed by September 2024. This SST-CWP has been prepared to address the principal topical areas identified in Tri-Party Agreement Milestone M-45-06 (i.e., regulatory pathway, operable unit characterization, waste retrieval, technology development, and a strategy for achieving closure). Chapter 2.0 of this SST-CWP provides a brief description of the environmental setting, SST System, the origin and characteristics of SST waste, and ancillary equipment that will be remediated as part of SST operable unit closure. Appendix 2A provides a description of the hydrogeology of the Hanford Site, including information on the unsaturated sediments (vadose zone) beneath the 200 Areas Plateau. Chapter 3.0 provides a discussion of the laws and regulations applicable to closure of the SST farm operable units. Chapter 4.0 provides a summary description of the ongoing characterization activities that best align with the proposed regulatory pathway for closure. Chapter 5.0 describes aspects of the SST waste retrieval program, including retrieval strategy, technology, and sequence, potential tank leakage during retrieval, and considerations of deployment of subsurface barriers. Chapter 6.0 outlines a proposed strategy for closure. Chapter 7.0 provides a summary of the programs underway or planned to develop technologies to support closure. Ca. 325 refs

  20. Overview regarding construction and demolition waste in Spain.

    Science.gov (United States)

    Rodríguez-Robles, Desirée; García-González, Julia; Juan-Valdés, Andrés; Morán-Del Pozo, Julia M; Guerra-Romero, M Ignacio

    2015-01-01

    The construction sector comprises a number of activities that may result in environmental impacts of considerable magnitude, waste generation being one of the major negative effects of this industry due to the large streams generated. Proper knowledge of the environmental problem caused by the sector is of great importance in order to achieve an effective waste management. Thus, this paper analyse the Spanish situation regarding construction and demolition waste (CDW) compared with other European Union countries; which sets out the current figures of the CDW scenario (legislation, generation, composition, treatment and market) as well as the difficulties encountered when handling this residue.

  1. Sustainable closure of construction materials quarries in Cuba

    Directory of Open Access Journals (Sweden)

    Julio Montero-Matos

    2017-10-01

    Full Text Available The inclusion of effective mine closure plans in the exploitation project is the way to compensate for the harmful effect of this activity. Based on a diagnosis carried out in 11 sites in operation, belonging to the company Canteras, a methodology was designed with a systemic and integral approach that consists of five stages and allows the execution of quarry closures in a sustainable manner. The Delphi method was applied to select the criteria that directly affect the sustainable closure of quarries in such a way that it considers the essential postulates of the Cuban Economic Model (MEC. The proposed methodology represents a contribution to the planning and design of the mining closure in Cuban non-metallic deposits to guarantee the reduction of the environmental impacts caused during its operation and the reduction, to the lesser extent possible, of negative socio-economic effects for the workers and the community located in the area of influence of the quarries. Currently applied in the quarry of San José, in Mayabeque province.

  2. Corrective Action Decision Document/Closure Report for Corrective Action Unit 106: Area 5, 11 Frenchman Flat Atmospheric Sites, Nevada National Security Site, Nevada

    International Nuclear Information System (INIS)

    Matthews, Patrick; Peterson, Dawn

    2011-01-01

    Corrective Action Unit 106 comprises four corrective action sites (CASs): (1) 05-20-02, Evaporation Pond; (2) 05-23-05, Atmospheric Test Site - Able; (3) 05-45-04, 306 GZ Rad Contaminated Area; (4) 05-45-05, 307 GZ Rad Contaminated Area. The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 106 based on the implementation of corrective actions. The corrective action of clean closure was implemented at CASs 05-45-04 and 05-45-05, while no corrective action was necessary at CASs 05-20-02 and 05-23-05. Corrective action investigation (CAI) activities were performed from October 20, 2010, through June 1, 2011, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 106: Areas 5, 11 Frenchman Flat Atmospheric Sites. The approach for the CAI was divided into two facets: investigation of the primary release of radionuclides, and investigation of other releases (mechanical displacement and chemical releases). The purpose of the CAI was to fulfill data needs as defined during the data quality objective (DQO) process. The CAU 106 dataset of investigation results was evaluated based on a data quality assessment. This assessment demonstrated the dataset is complete and acceptable for use in fulfilling the DQO data needs. Investigation results were evaluated against final action levels (FALs) established in this document. A radiological dose FAL of 25 millirem per year was established based on the Industrial Area exposure scenario (2,250 hours of annual exposure). The only radiological dose exceeding the FAL was at CAS 05-45-05 and was associated with potential source material (PSM). It is also assumed that additional PSM in the form of depleted uranium (DU) and DU-contaminated debris at CASs 05-45-04 and 05-45-05 exceed the FAL. Therefore, corrective actions were undertaken at these CASs that consisted of removing PSM and collecting verification

  3. Site operations

    International Nuclear Information System (INIS)

    House, W.B.; Ebenhack, D.G.

    1989-01-01

    This chapter is a discussion of the management and operations practices used at the Barnwell Waste Management Facility in Barnwell, SC. The following topics are discussed: (1) Waste receiving and inspection, including manifest and certificates of compliance, radiological surveys, disposition of nonconforming items, and decontamination and disposition of secondary waste streams; (2) Waste disposal, including Title 10 CFR 61 requirements, disposal area evaluations, shipment offloading, container emplacement, and radiation protection; (3) Trench closure, including trench backfilling, trench capping, and permanent markers; (4) Site maintenance and stabilization, including trench maintenance, surface water management, and site closure activities; (5) Site monitoring programs, including operational monitoring, and environmental monitoring program; (6) Personnel training and qualifications, including basic training program, safety training program, special skills training, and physical qualifications; (7) Records management, including waste records, personnel training records, personnel dosimetry records, site monitoring records, trench qualification and construction records, and site drawings and stabilization records; (8) Site security; (9) Emergency response plans; and (10) Quality assurance

  4. Rash with DERMABOND PRINEO Skin Closure System Use in Bilateral Reduction Mammoplasty: A Case Series.

    Science.gov (United States)

    Knackstedt, R W; Dixon, J A; O'Neill, P J; Herrera, F A

    2015-01-01

    Background. Bilateral reduction mammoplasty is a common plastic surgery procedure that can be complicated by unfavorable scar formation along incision sites. Surgical adhesives can be utilized as an alternative or as an adjunct to conventional suture closures to help achieve good wound tension and provide an adequate barrier with excellent cosmesis. The recently introduced DERMABOND PRINEO Skin Closure System Skin Closure System combines the skin adhesive 2-octyl cyanoacrylate with a self-adhering polyester-based mesh. Proposed benefits of wound closure with DERMABOND PRINEO Skin Closure System, used with or without sutures, include its watertight seal, easy removal, microbial barrier, even distribution of tension, and reduction in wound closure time. Although allergic reactions to 2-octyl cyanoacrylate have been reported, few allergic reactions to DERMABOND PRINEO Skin Closure System have been noted in the literature. This case series describes three patients who experienced an allergic reaction to DERMABOND PRINEO Skin Closure System after undergoing elective bilateral reduction mammoplasties at our institution to further explore this topic. Methods. Retrospective chart review of bilateral reduction mammoplasty patients who received DERMABOND PRINEO Skin Closure System dressing at our institution was performed. Results. Three patients were identified as having a rash in reaction to DERMABOND PRINEO Skin Closure System after bilateral reduction mammoplasty. All three patients required systemic steroid treatment to resolve the rash. One patient was identified as having a prior adhesive reaction. Conclusions. DERMABOND PRINEO Skin Closure System has demonstrated its efficacy in optimizing scar healing and appearance. However, as we demonstrate these three allergic reactions to DERMABOND PRINEO Skin Closure System, caution must be utilized in its usage, namely, in patients with a prior adhesive allergy and in sites where moisture or friction may be apparent.

  5. Rash with DERMABOND PRINEO Skin Closure System Use in Bilateral Reduction Mammoplasty: A Case Series

    Directory of Open Access Journals (Sweden)

    R. W. Knackstedt

    2015-01-01

    Full Text Available Background. Bilateral reduction mammoplasty is a common plastic surgery procedure that can be complicated by unfavorable scar formation along incision sites. Surgical adhesives can be utilized as an alternative or as an adjunct to conventional suture closures to help achieve good wound tension and provide an adequate barrier with excellent cosmesis. The recently introduced DERMABOND PRINEO Skin Closure System Skin Closure System combines the skin adhesive 2-octyl cyanoacrylate with a self-adhering polyester-based mesh. Proposed benefits of wound closure with DERMABOND PRINEO Skin Closure System, used with or without sutures, include its watertight seal, easy removal, microbial barrier, even distribution of tension, and reduction in wound closure time. Although allergic reactions to 2-octyl cyanoacrylate have been reported, few allergic reactions to DERMABOND PRINEO Skin Closure System have been noted in the literature. This case series describes three patients who experienced an allergic reaction to DERMABOND PRINEO Skin Closure System after undergoing elective bilateral reduction mammoplasties at our institution to further explore this topic. Methods. Retrospective chart review of bilateral reduction mammoplasty patients who received DERMABOND PRINEO Skin Closure System dressing at our institution was performed. Results. Three patients were identified as having a rash in reaction to DERMABOND PRINEO Skin Closure System after bilateral reduction mammoplasty. All three patients required systemic steroid treatment to resolve the rash. One patient was identified as having a prior adhesive reaction. Conclusions. DERMABOND PRINEO Skin Closure System has demonstrated its efficacy in optimizing scar healing and appearance. However, as we demonstrate these three allergic reactions to DERMABOND PRINEO Skin Closure System, caution must be utilized in its usage, namely, in patients with a prior adhesive allergy and in sites where moisture or friction may

  6. Chemical sulphate removal for treatment of construction and demolition debris leachate.

    Science.gov (United States)

    Kijjanapanich, Pimluck; Annachhatre, Ajit P; Esposito, Giovanni; Lens, Piet N L

    2014-08-01

    Construction and demolition debris (CDD) is a product of construction, renovation or demolition activities. It has a high gypsum content (52.4% of total gypsum), concentrated in the CDD sand (CDDS) fraction. To comply with the posed limit of the maximum amount of sulphate present in building sand, excess sulphate needs to be removed. In order to enable reuse of CDDS, a novel treatment process is developed based on washing of the CDDS to remove most of the gypsum, and subsequent sulphate removal from the sulphate-rich CDDS leachate. This study aims to assess chemical techniques, i.e. precipitation and adsorption, for sulphate removal from the CDDS leachate. Good sulphate removal efficiencies (up to 99.9%) from the CDDS leachate can be achieved by precipitation with barium chloride (BaCl2) and lead(II) nitrate (Pb(NO3)2). Precipitation with calcium chloride (CaCl2), calcium carbonate (CaCO3) and calcium oxide (CaO) gave less efficient sulphate removal. Adsorption of sulphate to aluminium oxide (Al2O3) yielded a 50% sulphate removal efficiency, whereas iron oxide-coated sand as adsorbent gave only poor (10%) sulphate removal efficiencies.

  7. Closure Plan for Corrective Action Unit 110: Area 3 RWMS U-3ax/bl Disposal Unit, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Fitzmaurice, T. M.

    2000-01-01

    This Closure Plan has been prepared for the Area 3 RWMS U-3ax/bl Disposal Unit Corrective Action Unit 110 in accordance with the Federal Facility and Consent Order (Nevada Division of Environmental Protection [NDEP] et al., 1996). The U-3ax/bl is a historic disposal unit within the Area 3 Radioactive Waste Management Site located on the Nevada Test Site (NTS). The unit, which was formed by excavating the area between two subsidence craters (U-3ax and U-3bl), was operationally closed in 1987. The U-3ax/bl disposal unit is scheduled for permanent closure under the Resource Conservation and Recovery Act as a hazardous waste landfill. Existing records indicate that, from July 1968 to December 1987, U-3ax/bl received 2.3 x 10 5 cubic meters (8.12 x 10 6 cubic feet) of waste. NTS nuclear device testing generated approximately 95 percent of the total volume disposed of in U-3ax/bl, the majority of which came from the Waste Consolidation Project (80 percent of the total volume) (Elletson and Johnejack, 1995). Area 3 is located in Yucca Flat, within the northeast quadrant of the NTS. The Yucca Flat watershed is a structurally closed basin encompassing an area of approximately 780 square kilometers (300 square miles). The structural geomorphology of Yucca Flat is typical of the Basin and Range Physiographic Province. Yucca Flat lies in one of the most arid regions of the country. Water balance calculations for Area 3 indicate that it is continuously in a state of moisture deficit. The U-3ax/bl Disposal Unit will be closed in place by installing a Resource Conservation and Recovery Act equivalent cover. Following cover construction a fence will be installed around the cover to prevent accidental damage to the cover. Post-closure monitoring will consist of site inspections to determine the condition of the engineered cover and cover performance monitoring using Time-Domain Reflectometry arrays to monitor moisture migration in the cover. Any identified maintenance and repair

  8. Closure Plan for Corrective Action Unit 110: Area 3 RWMS U-3ax/bl Disposal Unit, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    T. M. Fitzmaurice

    2000-08-01

    This Closure Plan has been prepared for the Area 3 RWMS U-3ax/bl Disposal Unit Corrective Action Unit 110 in accordance with the Federal Facility and Consent Order (Nevada Division of Environmental Protection [NDEP] et al., 1996). The U-3ax/bl is a historic disposal unit within the Area 3 Radioactive Waste Management Site located on the Nevada Test Site (NTS). The unit, which was formed by excavating the area between two subsidence craters (U-3ax and U-3bl), was operationally closed in 1987. The U-3ax/bl disposal unit is scheduled for permanent closure under the Resource Conservation and Recovery Act as a hazardous waste landfill. Existing records indicate that, from July 1968 to December 1987, U-3ax/bl received 2.3 x 10{sup 5} cubic meters (8.12 x 10{sup 6} cubic feet) of waste. NTS nuclear device testing generated approximately 95 percent of the total volume disposed of in U-3ax/bl, the majority of which came from the Waste Consolidation Project (80 percent of the total volume) (Elletson and Johnejack, 1995). Area 3 is located in Yucca Flat, within the northeast quadrant of the NTS. The Yucca Flat watershed is a structurally closed basin encompassing an area of approximately 780 square kilometers (300 square miles). The structural geomorphology of Yucca Flat is typical of the Basin and Range Physiographic Province. Yucca Flat lies in one of the most arid regions of the country. Water balance calculations for Area 3 indicate that it is continuously in a state of moisture deficit. The U-3ax/bl Disposal Unit will be closed in place by installing a Resource Conservation and Recovery Act equivalent cover. Following cover construction a fence will be installed around the cover to prevent accidental damage to the cover. Post-closure monitoring will consist of site inspections to determine the condition of the engineered cover and cover performance monitoring using Time-Domain Reflectometry arrays to monitor moisture migration in the cover. Any identified maintenance and

  9. A closure study of aerosol optical properties at a regional background mountainous site in Eastern China

    International Nuclear Information System (INIS)

    Yuan, Liang; Yin, Yan; Xiao, Hui; Yu, Xingna; Hao, Jian; Chen, Kui

    2016-01-01

    There is a large uncertainty in evaluating the radiative forcing from aerosol–radiation and aerosol–cloud interactions due to the limited knowledge on aerosol properties. In-situ measurements of aerosol physical and chemical properties were carried out in 2012 at Mt. Huang (the Yellow Mountain), a continental background mountainous site in eastern China. An aerosol optical closure study was performed to verify the model outputs by using the measured aerosol optical properties, in which a spherical Mie model with assumptions of external and core–shell mixtures on the basis of a two-component optical aerosol model and high size-segregated element carbon (EC) ratio was applied. Although the spherical Mie model would underestimate the real scattering with increasing particle diameters, excellent agreement between the calculated and measured values was achieved with correlation coefficients above 0.98. Sensitivity experiments showed that the EC ratio had a negligible effect on the calculated scattering coefficient, but largely influenced the calculated absorption coefficient. The high size-segregated EC ratio averaged over the study period in the closure was enough to reconstruct the aerosol absorption coefficient in the Mie model, indicating EC size resolution was more important than time resolution in retrieving the absorption coefficient in the model. The uncertainties of calculated scattering and absorption coefficients due to the uncertainties of measurements and model assumptions yielded by a Monte Carlo simulation were ± 6% and ± 14% for external mixture and ± 9% and ± 31% for core–shell mixture, respectively. This study provided an insight into the inherent relationship between aerosol optical properties and physicochemical characteristics in eastern China, which could supplement the database of aerosol optical properties for background sites in eastern China and provide a method for regions with similar climate. - Highlights: • A spherical Mie

  10. A closure study of aerosol optical properties at a regional background mountainous site in Eastern China

    Energy Technology Data Exchange (ETDEWEB)

    Yuan, Liang [Collaborative Innovation Center on Forecast and Evaluation of Meteorological Disasters, Nanjing University of Information Science & Technology, Nanjing 210044 (China); Key Laboratory for Aerosol–Cloud–Precipitation of China Meteorological Administration, School of Atmospheric Physics, Nanjing University of Information Science and Technology, Nanjing 210044 (China); Yin, Yan, E-mail: yinyan@nuist.edu.cn [Collaborative Innovation Center on Forecast and Evaluation of Meteorological Disasters, Nanjing University of Information Science & Technology, Nanjing 210044 (China); Key Laboratory for Aerosol–Cloud–Precipitation of China Meteorological Administration, School of Atmospheric Physics, Nanjing University of Information Science and Technology, Nanjing 210044 (China); Xiao, Hui [Key Laboratory for Aerosol–Cloud–Precipitation of China Meteorological Administration, School of Atmospheric Physics, Nanjing University of Information Science and Technology, Nanjing 210044 (China); Yu, Xingna [Collaborative Innovation Center on Forecast and Evaluation of Meteorological Disasters, Nanjing University of Information Science & Technology, Nanjing 210044 (China); Key Laboratory for Aerosol–Cloud–Precipitation of China Meteorological Administration, School of Atmospheric Physics, Nanjing University of Information Science and Technology, Nanjing 210044 (China); Hao, Jian; Chen, Kui [Key Laboratory for Aerosol–Cloud–Precipitation of China Meteorological Administration, School of Atmospheric Physics, Nanjing University of Information Science and Technology, Nanjing 210044 (China); and others

    2016-04-15

    There is a large uncertainty in evaluating the radiative forcing from aerosol–radiation and aerosol–cloud interactions due to the limited knowledge on aerosol properties. In-situ measurements of aerosol physical and chemical properties were carried out in 2012 at Mt. Huang (the Yellow Mountain), a continental background mountainous site in eastern China. An aerosol optical closure study was performed to verify the model outputs by using the measured aerosol optical properties, in which a spherical Mie model with assumptions of external and core–shell mixtures on the basis of a two-component optical aerosol model and high size-segregated element carbon (EC) ratio was applied. Although the spherical Mie model would underestimate the real scattering with increasing particle diameters, excellent agreement between the calculated and measured values was achieved with correlation coefficients above 0.98. Sensitivity experiments showed that the EC ratio had a negligible effect on the calculated scattering coefficient, but largely influenced the calculated absorption coefficient. The high size-segregated EC ratio averaged over the study period in the closure was enough to reconstruct the aerosol absorption coefficient in the Mie model, indicating EC size resolution was more important than time resolution in retrieving the absorption coefficient in the model. The uncertainties of calculated scattering and absorption coefficients due to the uncertainties of measurements and model assumptions yielded by a Monte Carlo simulation were ± 6% and ± 14% for external mixture and ± 9% and ± 31% for core–shell mixture, respectively. This study provided an insight into the inherent relationship between aerosol optical properties and physicochemical characteristics in eastern China, which could supplement the database of aerosol optical properties for background sites in eastern China and provide a method for regions with similar climate. - Highlights: • A spherical Mie

  11. Security option file - After closure (DOS-AF)

    International Nuclear Information System (INIS)

    2016-01-01

    A first volume presents the context and scope of the Cigeo project, and the scope of this document. It proposes a general presentation of Cigeo, the regulatory framework and standards. It describes the different aspects and components of the security strategy: principles, security functions after closure, objectives of protection, global approach. It proposes a security assessment: objectives, consistency with international practices, assessment steps, scenarios, scenario quantitative assessment. The next part addresses security management. The second volume contains a description of the storage system: site characteristics, types of stored parcels, the future of the installation after its closure. The third volume proposes a security assessment. It addresses the management of risks and uncertainties, describes a scenario of normal evolution and also scenarios of altered evolutions, scenarios of unintentional human intrusion, and what-if type scenarios. The fourth volume reports lessons at the current stage of the project, and gives an overview of important activities from storage design to storage closure

  12. The impact of public hospital closure on medical and residency education: implications and recommendations.

    Science.gov (United States)

    Walker, Kara Odom; Calmes, Daphne; Hanna, Nancy; Baker, Richard

    2008-12-01

    Challenges around safety-net hospital closure have impacted medical student and resident exposure to urban public healthcare sites that may influence their future practice choices. To assess the impact of the closure of a public safety-net teaching hospital for the clinical medical education of Charles Drew University medical students and residents. Retrospective cohort study of medical students' and residents' and clinical placement into safety-net experiences after the closure of the primary teaching hospital. The hospital closure impacted both medical student and residency training experiences. Only 71% (17/24) of medical student rotations and 13% (23/180) of residents were maintained at public safety-net clinical sittings. The closure of the public safety-net hospital resulted in the loss of 36% of residency training spots sponsored by historically black medical schools in the United States and an even larger negative impact on the number of physicians training in underserved urban areas of Los Angeles County. While the medical educational program changes undertaken in the wake of hospital closure have negatively affected the immediate clinical educational experiences of medical students and residents, it remains to be seen whether the training site location changes will alter their long-term preferences in specialty choice and practice location.

  13. Fernald - Developing and Executing an Accelerated Closure Plan

    International Nuclear Information System (INIS)

    Nixon, D.A.

    2006-01-01

    In November 2000 the Department of Energy (DOE) and Fluor Fernald entered into a closure contract that incited Fluor Fernald to reduce the cost and schedule of the Fernald site cleanup. The contract established a target schedule and target cost and how Fluor Fernald performs against these targets determines the amount of fee the company earns. In response to these new challenges, Fluor Fernald developed a 13-part strategy to safely accelerate work and more efficiently utilize the available funding. Implementation of this strategy required a dramatic culture change at Fernald - from a 'government job mind set' to an entrepreneurial/commercial model. Fluor Fernald's strategy and culture change has proved to be successful as the company is on track to close the site ahead of the target schedule at a total project cost less than the target cost. The elements of Fluor Fernald's strategy and the lessons learned during implementation provide valuable information that could be utilized by other DOE sites that will be undergoing closure over the next decade. (authors)

  14. Tonopah Test Range Environmental Restoration Corrective Action Sites

    International Nuclear Information System (INIS)

    Ronald B. Jackson

    2007-01-01

    Corrective Action Sites (CASs) and Corrective Action Units (CAUs) at the Tonopah Test Range (TTR) may be placed into three categories: Clean Closure/No Further Action, Closure in Place, or Closure in Progress

  15. Closure of the Radial Forearm Free Flap Donor Site Using the Combined Local Triangular Full-Thickness Skin Graft.

    Science.gov (United States)

    Moreno-Sánchez, Manuel; González-García, Raúl; Ruiz-Laza, Luis; Manzano Solo de Zaldívar, Damián; Moreno-García, Carlos; Monje, Florencio

    2016-01-01

    Traditional donor-site closure has been associated with serious esthetic and functional morbidity. The purpose of this study was to assess morbidity in esthetics and function and measure the postoperative complications of the radial forearm free flap (RFFF) donor site after using combined local triangular full-thickness skin grafting. This prospective study of patients who underwent reconstruction of head and neck defects using an RFFF was conducted from July 2008 through December 2014. The donor site was repaired with a combined local triangular full-thickness skin graft. Quality of the scar, color match, tendon exposure, presence of necrosis, dehiscence of the suture, and presence of dysesthesia were recorded and analyzed using SPSS 21.0 software. One hundred consecutive patients (71 male and 29 female) underwent RFFF harvesting. RFFF donor-site defects ranged from 15 to 70 cm2; partial skin graft loss occurred in 7% of patients. Five patients (5%) had small dehiscences of the forearm skin graft, and 2 cases (2%) presented tendon exposure. In all cases, these sites healed secondarily by conservative management, with no final impairment of function. Esthetic results were considered excellent in 87%, good in 11%, and suboptimal in 2% of the cases. The combined local triangular full-thickness skin graft is a reliable method for closing RFFF donor-site defects because it obviates a second surgical site, it provides excellent color match and pliability, and it can be used for covering large defects of the donor site. Copyright © 2016 American Association of Oral and Maxillofacial Surgeons. Published by Elsevier Inc. All rights reserved.

  16. Surplus Facilities and Resource Conservation and Recovery Act Closure program plan, fiscal year 1992

    International Nuclear Information System (INIS)

    Hughes, M.C.; Wahlen, R.K.; Winship, R.A.

    1991-10-01

    The Surplus Facilities and Resource Conservation and Recovery Act Closure program is responsible to US Department of Energy Field Office, Richland for the safe, cost-effective surveillance, maintenance, and decommissioning of surplus facilities at the Hanford Site. The Surplus Facilities and Resource Conservation and Recovery Act Closure program is also responsible to US Department of Energy Field Office, Richland for the program management of specific Resource Conservation and Recovery Act closures at the Hanford Site. This program plan addresses only the surplus facilities. The criteria used to evaluate each factor relative to decommissioning are based on the guidelines presented by the US Department of Energy Field Office, Richland, Environmental Restoration Division. The guidelines are consistent with the Westinghouse Hanford Company commitment to decommission Hanford Site retired facilities in the safest and most cost-effective way achievable. This document outlines the plan for managing these facilities until disposal

  17. Closure report for CAU No. 416: Project Shoal Area

    International Nuclear Information System (INIS)

    1998-01-01

    This Closure Report provides the documentation for closure of the US Department of Energy/Nevada Operations Office (DOE/NV) Project Shoal Area (PSA) Surface Corrective Action Unit (CAU) 416. CAU 416 consists of a mud pit, muckpile, and housekeeping site. The PSA is located approximately 48.3 kilometers (30 miles) southeast of Fallon, Nevada. The mud pit was the result of drilling activities at the PSA in 1963. Investigation activities completed in 1996 determined drilling mud in the mud pit was impacted with petroleum hydrocarbons in excess of the State of Nevada 100 milligram per kilogram (mg/kg). The muckpile consists of broken granite from emplacement shaft and drift (tunnel) mining activities at the PSA in 1963. The housekeeping site consisted of approximately 20 used, empty, rusted, steel 0.9 liter (1 quart) oil cans

  18. Closure Report for Corrective Action Unit 110: Areas 3 RWMS U-3ax/bl Disposal Unit, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    J. L. Smith

    2001-08-01

    This Closure Report (CR) has been prepared for the Area 3 Radioactive Waste Management Site (RWMS) U-3ax/bl Disposal Unit Corrective Action Unit (CAU) 110 in accordance with the reissued (November 2000) Resource Conservation and Recovery Act (RCRA) Part B operational permit NEV HW009 (Nevada Division of Environmental Protection [NDEP], 2000) and the Federal Facility and Consent Order (FFACO) (NDEP et al., 1996). CAU 110 consists of one Corrective Action Site 03-23-04, described as the U-3ax/bl Subsidence Crater. Certifications of closure are located in Appendix A. The U-3ax/bl is a historic disposal unit within the Area 3 RWMS located on the Nevada Test Site (NTS). The unit, which was formed by excavating the area between two subsidence craters (U-3ax and U-3bl), was operationally closed in 1987. The U-3ax/bl disposal unit was closed under the RCRA, as a hazardous waste landfill. Existing records indicate that, from July 1968 to December 1987, U-3ax/bl received 2.3 x 10{sup 5} cubic meters (m{sup 3}) (8.12 x 10{sup 6} cubic feet [ft{sup 3}]) of waste. NTS atmospheric nuclear device testing generated approximately 95% of the total waste volume disposed of in U-3ax/bl; 80% of the total volume was generated from the Waste Consolidation Project. Area 3 is located in Yucca Flat, within the northeast quadrant of the NTS. The Yucca Flat watershed is a structurally closed basin encompassing an area of approximately 780 square kilometers (300 square miles). The structural geomorphology of Yucca Flat is typical of the Basin and Range Physiographic Province. Yucca Flat lies in one of the most arid regions of the country. Water balance calculations for Area 3 indicate that it is normally in a state of moisture deficit.

  19. Quantum non-demolition phonon counter with a hybrid optomechnical system

    Science.gov (United States)

    Song, Qiao; Zhang, KeYe; Dong, Ying; Zhang, WeiPing

    2018-05-01

    A phonon counting scheme based on the control of polaritons in an optomechanical system is proposed. This approach permits us to measure the number of phonons in a quantum non-demolition (QND) manner for arbitrary modes not limited by the frequency matching condition as in usual photon-phonon scattering detections. The performance on phonon number transfer and quantum state transfer of the counter are analyzed and simulated numerically by taking into account all relevant sources of noise.

  20. Understanding the basis of space closure in Orthodontics for a more efficient orthodontic treatment.

    Science.gov (United States)

    Ribeiro, Gerson Luiz Ulema; Jacob, Helder B

    2016-01-01

    Space closure is one of the most challenging processes in Orthodontics and requires a solid comprehension of biomechanics in order to avoid undesirable side effects. Understanding the biomechanical basis of space closure better enables clinicians to determine anchorage and treatment options. In spite of the variety of appliance designs, space closure can be performed by means of friction or frictionless mechanics, and each technique has its advantages and disadvantages. Friction mechanics or sliding mechanics is attractive because of its simplicity; the space site is closed by means of elastics or coil springs to provide force, and the brackets slide on the orthodontic archwire. On the other hand, frictionless mechanics uses loop bends to generate force to close the space site, allowing differential moments in the active and reactive units, leading to a less or more anchorage control, depending on the situation. This article will discuss various theoretical aspects and methods of space closure based on biomechanical concepts.

  1. Understanding the basis of space closure in Orthodontics for a more efficient orthodontic treatment

    Directory of Open Access Journals (Sweden)

    Gerson Luiz Ulema Ribeiro

    2016-04-01

    Full Text Available ABSTRACT Introduction: Space closure is one of the most challenging processes in Orthodontics and requires a solid comprehension of biomechanics in order to avoid undesirable side effects. Understanding the biomechanical basis of space closure better enables clinicians to determine anchorage and treatment options. In spite of the variety of appliance designs, space closure can be performed by means of friction or frictionless mechanics, and each technique has its advantages and disadvantages. Friction mechanics or sliding mechanics is attractive because of its simplicity; the space site is closed by means of elastics or coil springs to provide force, and the brackets slide on the orthodontic archwire. On the other hand, frictionless mechanics uses loop bends to generate force to close the space site, allowing differential moments in the active and reactive units, leading to a less or more anchorage control, depending on the situation. Objective: This article will discuss various theoretical aspects and methods of space closure based on biomechanical concepts.

  2. Regional neural tube closure defined by the Grainy head-like transcription factors.

    Science.gov (United States)

    Rifat, Yeliz; Parekh, Vishwas; Wilanowski, Tomasz; Hislop, Nikki R; Auden, Alana; Ting, Stephen B; Cunningham, John M; Jane, Stephen M

    2010-09-15

    Primary neurulation in mammals has been defined by distinct anatomical closure sites, at the hindbrain/cervical spine (closure 1), forebrain/midbrain boundary (closure 2), and rostral end of the forebrain (closure 3). Zones of neurulation have also been characterized by morphologic differences in neural fold elevation, with non-neural ectoderm-induced formation of paired dorso-lateral hinge points (DLHP) essential for neural tube closure in the cranial and lower spinal cord regions, and notochord-induced bending at the median hinge point (MHP) sufficient for closure in the upper spinal region. Here we identify a unifying molecular basis for these observations based on the function of the non-neural ectoderm-specific Grainy head-like genes in mice. Using a gene-targeting approach we show that deletion of Grhl2 results in failed closure 3, with mutants exhibiting a split-face malformation and exencephaly, associated with failure of neuro-epithelial folding at the DLHP. Loss of Grhl3 alone defines a distinct lower spinal closure defect, also with defective DLHP formation. The two genes contribute equally to closure 2, where only Grhl gene dosage is limiting. Combined deletion of Grhl2 and Grhl3 induces severe rostral and caudal neural tube defects, but DLHP-independent closure 1 proceeds normally in the upper spinal region. These findings provide a molecular basis for non-neural ectoderm mediated formation of the DLHP that is critical for complete neuraxis closure. (c) 2010 Elsevier Inc. All rights reserved.

  3. United Kingdom. Development plan for the eventual closure of the UK Drigg nuclear surface low level waste disposal facility

    International Nuclear Information System (INIS)

    2001-01-01

    The Drigg site, owned and operated by BNFL, is the UK's principal site for the disposal of low level radioactive waste. The site has operated since 1959 and receives wastes from a wide range of sources including nuclear power stations, nuclear fuel cycle facilities, isotope manufacturing sites, universities, general industry and cleanup of historically contaminated sites. Disposals until the late 1980s were solely by tipping essentially loose wastes into excavated trenches. More recently, trench disposals have been phased out in preference to emplacement of containerised, conditioned wastes in concrete vaults. The standardised wasteform consists of high force compacted (or non-compactable) waste immobilised within 20 m 3 steel overpack containers by the addition of cementitious grout. Larger items of wastes are grouted directly, in situ in the vault. The disposal trenches have been completed with an interim cap, as will the vaults when filled. It is currently estimated that sufficient capacity remains at Drigg for disposals to continue until at least 2050. Post-operations it is planned that the site will enter a phase including shut down of operational facilities, emplacement of long term site closure features including a final closure cap and then to an institutional management phase. Planning has therefore been carried out as to the strategy for eventual closure of the site. This closure strategy is also underpinned by an engineering evaluation studies programme to develop and evaluate appropriate closure measures including assessment of the long term performance of such measures. This appendix summarizes some of this work

  4. Use of a Collagen-Based Device for Closure of Low Brachial Artery Punctures

    International Nuclear Information System (INIS)

    Belenky, A.; Aranovich, D.; Greif, F.; Bachar, G.; Bartal, G.; Atar, E.

    2007-01-01

    Purpose. To report our experience with the Angioseal vascular closure device for hemostasis of distal brachial artery puncture. Methods. Between September 2003 and August 2005, 64 Angioseal vascular closure devices were inserted in 64 patients (40 men, 24 women; mean age 65 years) immediately after diagnostic or therapeutic arterial angiographies performed through a 5 Fr to 7 Fr sheath via the distal brachial artery. Ultrasound examination of the brachial artery preceded the angiography in all cases and only arteries wider than 4 mm were closed by the Angioseal. In cases of a sonographically evident thin subcutaneous space of the cubital fossa, tissue tumescence, using 1% Lidocaine, was performed prior to the arterial closure. Results. The deployment success rate was 100%. No major complications were encountered; only 2 patients developed puncture site hematoma, and these were followed conservatively. Conclusions. Closure of low brachial artery punctures with the Angioseal is simple and safe. No additional manual compression is required. We recommend its use after brachial artery access interventions, through appropriately wide arteries, to improve early patient ambulation and potentially reduce possible puncture site complications

  5. 2010 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    Energy Technology Data Exchange (ETDEWEB)

    C. T. Lindsey, A. L. Johnson

    2010-09-30

    This report documents eh status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with CERLA cleanup of National Priorities List waste sites at Hanford. This report contains vegetation monitoring data that were collected in the spring and summer of 2010 from the River Corridor Closure Contract’s revegetation and mitigation areas on the Hanford Site.

  6. Morphologic features of puncture sites after exoseal vascular closure device implantation: Changes on follow-up computed tomography

    International Nuclear Information System (INIS)

    Ryu, Hwa Seong; Jang, Joo Yeon; Kim, Tae Un; Lee, Jun Woo; Park, Jung Hwan; Choo, Ki Seok; Cho, Mong; Yoon, Ki Tae; Hong, Young Ki; Jeon, Ung Bae

    2017-01-01

    The study aimed to evaluate the morphologic changes in transarterial chemoembolization (TACE) puncture sites implanted with an ExoSeal vascular closure device (VCD) using follow-up computed tomography (CT). 16 patients who used ExoSeal VCD after TACE were enrolled. Using CT images, the diameters and anterior wall thicknesses of the puncture sites in the common femoral artery (CFA) were compared with those of the contralateral CFA before TACE, at 1 month after every TACE session, and at the final follow-up period. The rates of complications were also evaluated. There were no puncture- or VCD-related complications. Follow-up CT images of the CFA's of patients who used ExoSeal VCDs showed eccentric vascular wall thickening with soft-tissue densities considered to be hemostatic plugs. Final follow-up CT images (mean, 616 days; range, 95–1106 days) revealed partial or complete resorption of the hemostatic plugs. The CFA puncture site diameters did not differ statistically from those of the contralateral CFA on the final follow-up CT (p > 0.05), regardless of the number of VCDs used. Follow-up CT images of patients who used ExoSeal VCDs showed no significant vascular stenosis or significant vessel wall thickening

  7. Morphologic features of puncture sites after exoseal vascular closure device implantation: Changes on follow-up computed tomography

    Energy Technology Data Exchange (ETDEWEB)

    Ryu, Hwa Seong; Jang, Joo Yeon; Kim, Tae Un; Lee, Jun Woo; Park, Jung Hwan; Choo, Ki Seok; Cho, Mong; Yoon, Ki Tae; Hong, Young Ki; Jeon, Ung Bae [Pusan National University Yangsan Hospital, Yangsan (Korea, Republic of)

    2017-05-15

    The study aimed to evaluate the morphologic changes in transarterial chemoembolization (TACE) puncture sites implanted with an ExoSeal vascular closure device (VCD) using follow-up computed tomography (CT). 16 patients who used ExoSeal VCD after TACE were enrolled. Using CT images, the diameters and anterior wall thicknesses of the puncture sites in the common femoral artery (CFA) were compared with those of the contralateral CFA before TACE, at 1 month after every TACE session, and at the final follow-up period. The rates of complications were also evaluated. There were no puncture- or VCD-related complications. Follow-up CT images of the CFA's of patients who used ExoSeal VCDs showed eccentric vascular wall thickening with soft-tissue densities considered to be hemostatic plugs. Final follow-up CT images (mean, 616 days; range, 95–1106 days) revealed partial or complete resorption of the hemostatic plugs. The CFA puncture site diameters did not differ statistically from those of the contralateral CFA on the final follow-up CT (p > 0.05), regardless of the number of VCDs used. Follow-up CT images of patients who used ExoSeal VCDs showed no significant vascular stenosis or significant vessel wall thickening.

  8. Post-Closure Inspection Report for Corrective Action Unit 453: Area 9 UXO Landfill Tonopah Test Range, Nevada, Calendar Year 2000; TOPICAL

    International Nuclear Information System (INIS)

    K. B. Campbell

    2001-01-01

    Post-closure monitoring requirements for the Area 9 Unexploded Ordnance Landfill (Corrective Action Unit[CAU] 453) (Figure 1) are described in Closure Report for Corrective Action Unit 453: Area 9 UXO Landfill, Tonopah Test Range, Nevada, report number DOE/NV-284. The Closure Report (CR) was submitted to the Nevada Division of Environmental Protection (NDEP) on August 5,1999. The CR (containing the Post-Closure Monitoring Plan) was approved by the NDEP on September 10,1999. Post-closure monitoring at CAU 453 consists of the following: (1) Site inspections done twice a year to evaluate the condition of the unit; (2) Verification that the site is secure; (3) Notice of any subsidence or deficiencies that may compromise the integrity of the unit; (4) Remedy of any deficiencies within 90 days of discovery; and (5) Preparation and submittal of an annual report. Site inspections were conducted on June 20, 2000 and November 21, 2000. Both site inspections were conducted after NDEP approval of the CR, and in accordance with the Post-Closure Monitoring Plan in the NDEP-approved CR. This report includes copies of the inspection checklists, photographs, recommendations, and conclusions. The Post-Closure Inspection Checklists are found in Attachment A, a copy of the field notes is found in Attachment B, and inspection photographs are found in Attachment C

  9. Risk and Performance Analyses Supporting Closure of WMA C at the Hanford Site in Southeast Washington

    International Nuclear Information System (INIS)

    Eberlein, Susan J.; Bergeron, Marcel P.; Kemp, Christopher J.; Hildebrand, R. Douglas; Aly, Alaa; Kozak, Matthew; Mehta, Sunil; Connelly, Michael

    2013-01-01

    The Office of River Protection under the U.S. Department of Energy (DOE) is pursuing closure of the Single-Shell Tank (SST) Waste Management Area (WMA) C as stipulated by the Hanford Federal Facility Agreement and Consent Order (HFFACO) under federal requirements and work tasks will be done under the State-approved closure plans and permits. An initial step in meeting the regulatory requirements is to develop a baseline risk assessment representing current conditions based on available characterization data and information collected at the WMA C location. The baseline risk assessment will be supporting a Resource Conservation and Recovery Act of 1976 (RCRA) Field Investigation (RFI)/Corrective Measures Study (CMS) for WMA closure and RCRA corrective action. Complying with the HFFACO conditions also involves developing a long-term closure Performance Assessment (PA) that evaluates human health and environmental impacts resulting from radionuclide inventories in residual wastes remaining in WMA C tanks and ancillary equipment. This PA is being developed to meet the requirements necessary for closure authorization under DOE Order 435.1 and Washington State Hazardous Waste Management Act. To meet the HFFACO conditions, the long-term closure risk analysis will include an evaluation of human health and environmental impacts from hazardous chemical inventories along with other performance Comprehensive Environmental Response, Compensation, and Liability Act Appropriate and Applicable Requirements (CERCLA ARARs) in residual wastes left in WMA C facilities after retrieval and removal. This closure risk analysis is needed to needed to comply with the requirements for permitted closure. Progress to date in developing a baseline risk assessment of WMA C has involved aspects of an evaluation of soil characterization and groundwater monitoring data collected as a part of the RFI/CMS and RCRA monitoring. Developing the long-term performance assessment aspects has involved the

  10. Risk and Performance Analyses Supporting Closure of WMA C at the Hanford Site in Southeast Washington

    Energy Technology Data Exchange (ETDEWEB)

    Eberlein, Susan J.; Bergeron, Marcel P.; Kemp, Christopher J.

    2013-11-11

    The Office of River Protection under the U.S. Department of Energy (DOE) is pursuing closure of the Single-Shell Tank (SST) Waste Management Area (WMA) C as stipulated by the Hanford Federal Facility Agreement and Consent Order (HFFACO) under federal requirements and work tasks will be done under the State-approved closure plans and permits. An initial step in meeting the regulatory requirements is to develop a baseline risk assessment representing current conditions based on available characterization data and information collected at the WMA C location. The baseline risk assessment will be supporting a Resource Conservation and Recovery Act of 1976 (RCRA) Field Investigation (RFI)/Corrective Measures Study (CMS) for WMA closure and RCRA corrective action. Complying with the HFFACO conditions also involves developing a long-term closure Performance Assessment (PA) that evaluates human health and environmental impacts resulting from radionuclide inventories in residual wastes remaining in WMA C tanks and ancillary equipment. This PA is being developed to meet the requirements necessary for closure authorization under DOE Order 435.1 and Washington State Hazardous Waste Management Act. To meet the HFFACO conditions, the long-term closure risk analysis will include an evaluation of human health and environmental impacts from hazardous chemical inventories along with other performance Comprehensive Environmental Response, Compensation, and Liability Act Appropriate and Applicable Requirements (CERCLA ARARs) in residual wastes left in WMA C facilities after retrieval and removal. This closure risk analysis is needed to needed to comply with the requirements for permitted closure. Progress to date in developing a baseline risk assessment of WMA C has involved aspects of an evaluation of soil characterization and groundwater monitoring data collected as a part of the RFI/CMS and RCRA monitoring. Developing the long-term performance assessment aspects has involved the

  11. RCRA closure of eight land-based units at the Y-12 plant

    International Nuclear Information System (INIS)

    Stone, J.E.; Welch, S.H.

    1988-01-01

    Eight land-based hazardous waste management units at the Oak Ridge Y-12 Plant are being closed under an integrated multi-year program. Closure plans for the units have been submitted and are in various stages of revision and regulatory review. These units will be closed by various combinations of methods, including liquid removal and treatment, sludge stabilization, contaminated sludge and/or soil removal, and capping. The closure of these sites will be funded by a new Department of Energy budget category, the Environmental Restoration Budget Category (ERBC), which is intended to provide greater flexibility in the response to closure and remedial activities. A major project, Closure and Post-Closure Activities (CAPCA), has been identified for ERBC funding to close and remediate the land units in accordance with RCRA requirements. Establishing the scope of this program has required the development of risk assessments and the preparation of an integrated schedule

  12. RCRA closures at Rocky Flats Plant: A programmatic perspective and case study

    International Nuclear Information System (INIS)

    Ogg, Randy T.; Peterman, Bruce D.

    1992-01-01

    The Interagency Agreement (IAG) integrates a unique mechanism for remediating hazardous waste sites at the Rocky Flats Plant (RFP), which include utilizing RCRA and CERCLA technical/regulatory processes. Pursuant to the IAG signed by the Department of Energy (DOE), Environmental Protection Agency (EPA), and the Colorado Department of Health (CDH) on January 22, 1991, sixteen operable units (OUs) were defined for characterization and remediation at RFP. Of the sixteen OUs, six are classified as Resource Conservation and Recovery Act (RCRA) closure units. The six RCRA interim status closure units are: Solar Evaporation Ponds-OU 4, Present LandfUl-OU 7, Original Process Waste Lines-OU 9, Other Outside Closures-OU 10, West Spray Field-OU II, and Inside Building Closures-OU 15. The IAG will function as a technical/regulatory mechanism for managing/complying with all aspects of the RCRA interim status closure units at RFP. (author)

  13. Programmatic agreement among the USDOE/RL Operations Office, the Advisory Council on Historic Preservation, and the WA State Historic Preservation Office for the maintenance, deactivation, alteration and demolition of the built environment on the Hanford Site, Washington

    International Nuclear Information System (INIS)

    Lloyd, D.W.

    1997-01-01

    This Programmatic Agreement (PA) addresses the built environment (i.e., buildings and structures) constructed during the Manhattan Project and Cold War Era periods of Hanford's operational history. As such it encompasses the years 1943 through 1990. The identification, evaluation, and treatment of buildings and historic archeological remains on the Hanford Site predating 1943 will be accomplished through Sections 800.4 through 800.6 of the Council's regulations. This PA will be in effect from the date of signature until September 30, 2000. Completion of the Sitewide Treatment Plan established under this PA satisfies all Section 106 requirements for identification, evaluation, and treatment necessary for all undertakings, up to and including demolition which may affect Manhattan Project and Cold War Era properties. This PA may be extended if the Sitewide Treatment Plan has not been completed by the end of FY 2000. Identification, evaluation, and treatment of properties constructed on the Hanford Site after 1990 will be handled pursuant to the regulations in effect at the time such properties are eligible for review

  14. Brownfields Recover Your Resources - Reduce, Reuse, and Recycle Construction and Demolition Materials at Land Revitalization Projects

    Science.gov (United States)

    This document provides background information on how the sustainable reuse of brownfield properties includes efforts to reduce the environmental impact by reusing and recycling materials generated during building construction, demolition, or renovation.

  15. Accelerated Clean-up of the United States Department of Energy, Mound Nuclear Weapons Facility in Miamisburg, Ohio

    International Nuclear Information System (INIS)

    Lehew, J.G.; Bradford, J.D.; Cabbil, C.C.

    2006-01-01

    CH2M HILL is executing a performance-based contract with the United States Department of Energy to accelerate the safe closure of the nuclear facilities at the former Mound plant in Miamisburg, Ohio. The contract started in January 2003 with a target completion date of March 31, 2006. Our accelerated baseline targets completion of the project 2 years ahead of the previous baseline schedule, by spring 2006, and for $200 million less than previous estimates. This unique decommissioning and remediation project is located within the City of Miamisburg proper and is designed for transfer of the property to the Miamisburg Mound Community Improvement Corporation for industrial reuse. The project is being performed with the Miamisburg Mound Community Improvement Corporation and their tenants co-located on the site creating significant logistical, safety and stakeholder challenges. The project is also being performed in conjunction with the United States Department of Energy, United States Environmental Protection Agency, and the Ohio Environmental Protection Agency under the Mound 2000 regulatory cleanup process. The project is currently over 95% complete. To achieve cleanup and closure of the Mound site, CH2M HILL's scope includes: - Demolition of 64 nuclear, radiological and commercial facilities - Preparation for Transfer of 9 facilities (including a Category 2 nuclear facility) to the Miamisburg Mound Community Improvement Corporation for industrial reuse - Removal of all above ground utility structures and components, and preparation for transfer of 9 utility systems to Miamisburg Mound Community Improvement Corporation - Investigation, remediation, closure, and documentation of all known Potential Release Sites contaminated with radiological and chemical contamination (73 identified in original contract) - Storage, characterization, processing, packaging and shipment of all waste and excess nuclear materials - Preparation for Transfer of the 306 acre site to the

  16. Road Closures

    Data.gov (United States)

    Montgomery County of Maryland — This is an up to date map of current road closures in Montgomery County.This dataset is updated every few minutes from the Department of Transportation road closure...

  17. An Initial Evaluation of Characterization and Closure Options for Underground Pipelines within a Hanford Site Single-Shell Tank Farm - 13210

    Energy Technology Data Exchange (ETDEWEB)

    Badden, Janet W.; Connelly, Michael P. [Washington River Protection Services, P.O. Box 850, Richland, Washington, 99352 (United States); Seeley, Paul N. [Cenibark International, Inc., 104318 Nicole Drive, Kennewick, Washington, 99338-7596 (United States); Hendrickson, Michelle L. [Washington State Department of Ecology, 3100 Port of Benton Blvd, Richland, Washington, 99354 (United States)

    2013-07-01

    The Hanford Site includes 149 single-shell tanks, organized in 12 'tank farms,' with contents managed as high-level mixed waste. The Hanford Federal Facility Agreement and Consent Order requires that one tank farm, the Waste Management Area C, be closed by June 30, 2019. A challenge to this project is the disposition and closure of Waste Management Area C underground pipelines. Waste Management Area C contains nearly seven miles of pipelines and 200 separate pipe segments. The pipelines were taken out of service decades ago and contain unknown volumes and concentrations of tank waste residuals from past operations. To understand the scope of activities that may be required for these pipelines, an evaluation was performed. The purpose of the evaluation was to identify what, if any, characterization methods and/or closure actions may be implemented at Waste Management Area C for closure of Waste Management Area C by 2019. Physical and analytical data do not exist for Waste Management Area C pipeline waste residuals. To develop estimates of residual volumes and inventories of contamination, an extensive search of available information on pipelines was conducted. The search included evaluating historical operation and occurrence records, physical attributes, schematics and drawings, and contaminant inventories associated with the process history of plutonium separations facilities and waste separations and stabilization operations. Scoping analyses of impacts to human health and the environment using three separate methodologies were then developed based on the waste residual estimates. All analyses resulted in preliminary assessments, indicating that pipeline waste residuals presented a comparably low long-term impact to groundwater with respect to soil, tank and other ancillary equipment residuals, but exceeded Washington State cleanup requirement values. In addition to performing the impact analyses, the assessment evaluated available sampling technologies

  18. An Initial Evaluation Of Characterization And Closure Options For Underground Pipelines Within A Hanford Site Single-Shell Tank Farm-13210

    International Nuclear Information System (INIS)

    Badden, Janet W.; Connelly, Michael P.; Seeley, Paul N.; Hendrickson, Michelle L.

    2013-01-01

    The Hanford Site includes 149 single-shell tanks, organized in 12 'tank farms,' with contents managed as high-level mixed waste. The Hanford Federal Facility Agreement and Consent Order requires that one tank farm, the Waste Management Area C, be closed by June 30, 2019. A challenge to this project is the disposition and closure of Waste Management Area C underground pipelines. Waste Management Area C contains nearly seven miles of pipelines and 200 separate pipe segments. The pipelines were taken out of service decades ago and contain unknown volumes and concentrations of tank waste residuals from past operations. To understand the scope of activities that may be required for these pipelines, an evaluation was performed. The purpose of the evaluation was to identify what, if any, characterization methods and/or closure actions may be implemented at Waste Management Area C for closure of Waste Management Area C by 2019. Physical and analytical data do not exist for Waste Management Area C pipeline waste residuals. To develop estimates of residual volumes and inventories of contamination, an extensive search of available information on pipelines was conducted. The search included evaluating historical operation and occurrence records, physical attributes, schematics and drawings, and contaminant inventories associated with the process history of plutonium separations facilities and waste separations and stabilization operations. Scoping analyses of impacts to human health and the environment using three separate methodologies were then developed based on the waste residual estimates. All analyses resulted in preliminary assessments, indicating that pipeline waste residuals presented a comparably low long-term impact to groundwater with respect to soil, tank and other ancillary equipment residuals, but exceeded Washington State cleanup requirement values. In addition to performing the impact analyses, the assessment evaluated available sampling technologies and

  19. Rash with DERMABOND PRINEO Skin Closure System Use in Bilateral Reduction Mammoplasty: A Case Series

    OpenAIRE

    R. W. Knackstedt; J. A. Dixon; P. J. O’Neill; F. A. Herrera

    2015-01-01

    Background. Bilateral reduction mammoplasty is a common plastic surgery procedure that can be complicated by unfavorable scar formation along incision sites. Surgical adhesives can be utilized as an alternative or as an adjunct to conventional suture closures to help achieve good wound tension and provide an adequate barrier with excellent cosmesis. The recently introduced DERMABOND PRINEO Skin Closure System Skin Closure System combines the skin adhesive 2-octyl cyanoacrylate with a self-ad...

  20. Closure Report for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada

    International Nuclear Information System (INIS)

    Campbell, K.B.

    2001-11-01

    This Closure Report provides the documentation for closure of the Central Nevada Test Area (CNTA) surface Corrective Action Unit (CAU) 417. The CNTA is located in Hot Creek Valley in Nye County, Nevada, approximately 22.5 kilometers (14 miles) west of U.S. State Highway 6 near the Moores Station historical site, and approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. A nuclear device for Project Faultless was detonated approximately 975 meters (3,200 feet) below ground surface on January 19, 1968, in emplacement boring UC-1 (Department of Energy, Nevada Operation Office [DOE/NV], 1997). CAU 417 consists of 34 Corrective Action Sites (CASs). Site closure was completed using a Nevada Department of Environmental Protection (NDEP) approved Corrective Action Plan (CAP) (DOE/NV, 2000) which was based on the recommendations presented in the NDEP-approved Corrective Action Decision Document (DOE/NV, 1999). Closure of CAU 417 was completed in two phases. Phase I field activities were completed with NDEP concurrence during 1999 as outlined in the Phase I Work Plan, Appendix A of the CAP (DOE/NV, 2000), and as summarized in Section 2.1.2 of this document

  1. HEAVY METALS IN RECOVERED FINES FOR CONSTRUCTION AND DEMOLITION DEBRIS RECYCLING FACILITIES IN FLORIDA

    Science.gov (United States)

    A major product recovered from the processing and recycling of construction and demolition (C&D) debris is screened soil, also referred to as fines. A proposed reuse option for C&D debris fines is fill material, typically in construction projects as a substitute for natural soil....

  2. 78 FR 40705 - Takes of Marine Mammals Incidental to Specified Activities; Demolition and Construction...

    Science.gov (United States)

    2013-07-08

    ... (Zalophus californianus), and northern elephant seals (Mirounga angustirostris) incidental to demolition and... activities by the general public. Over the last three years (2010 through 2012), an average of 1,556,184..., but because of basic year-round working condition needs for the lifeguards and the demand for...

  3. Primary Angle Closure and Sequence Variants within MicroRNA Binding Sites of Genes Involved in Eye Development.

    Directory of Open Access Journals (Sweden)

    Haihong Shi

    Full Text Available The formation of primary angle closure (PAC and primary angle closure glaucoma (PACG is regulated by a tissue remodeling pathway that plays a critical role in eye development. MicroRNAs (miRNAs are powerful gene expression regulators and may exert their effects on tissue remodeling genes. This study investigated the associations between gene variants (single-nucleotide polymorphism, SNP in miRNA binding sites in the 3'-UTR region of genes involved in eye development and PAC.The sample consisted of 232 PAC subjects and 306 controls obtained from a population-based cohort in the Funing District of Jiangsu, China. The markers include 9 SNPs in the COL11A1, PCMTD1, ZNRF3, MTHFR, and ALPPL2 genes respectively. SNP genotyping was performed with a TaqMan-MGB probe using an RT-PCR system.Of the 9 SNPs studied, the frequency of the minor A allele of COL11A1 rs1031820 was higher in the PAC group than in the control group in allele analysis (p = 0.047. The genotype analysis indicated that MTHFR rs1537514 is marginally associated with PAC (p = 0.014. The CC genotype of rs1537514 was present solely in the PAC group. However, the differences lost significance after Bonferroni correction.Our study reveals a possible association of COL11A1 and MTHFR with PAC in the Han Chinese population. These results will contribute to an improved understanding of the genetic basis of PACG.

  4. 300 Area waste acid treatment system closure plan. Revision 1

    International Nuclear Information System (INIS)

    1996-03-01

    This section provides a description of the Hanford Site, identifies the proposed method of 300 Area Waste Acid Treatment System (WATS) closure, and briefly summarizes the contents of each chapter of this plan

  5. 300 Area waste acid treatment system closure plan. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This section provides a description of the Hanford Site, identifies the proposed method of 300 Area Waste Acid Treatment System (WATS) closure, and briefly summarizes the contents of each chapter of this plan.

  6. Closure Report for Corrective Action Unit 426: Cactus Spring Waste Trenches, Tonopah Test Range, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Dave Madsen

    1998-08-01

    This Closure Report provides the documentation for closure of the Cactus Spring Waste Trenches Corrective Action Unit (CAU) 426. The site is located on the Tonopah Test Range, approximately 225 kilometers northwest of Las Vegas, NV. CAU 426 consists of one corrective action site (CAS) which is comprised of four waste trenches. The trenches were excavated to receive solid waste generated in support of Operation Roller Coaster, primary the Double Tracks Test in 1963, and were subsequently backfilled. The Double Tracks Test involved use of live animals to assess the biological hazards associated with the nonnuclear detonation of plutonium-bearing devices. The Nevada Division of Environmental Protection approved Corrective Action Plan (CAP)which proposed ''capping'' methodology. The closure activities were completed in accordance with the approved CAP and consisted of constructing an engineered cover in the area of the trenches, constructing/planting a vegetative cover, installing a perimeter fence and signs, implementing restrictions on future use, and preparing a Post-Closure Monitoring Plan.

  7. Interferometric Imaging Directly with Closure Phases and Closure Amplitudes

    Science.gov (United States)

    Chael, Andrew A.; Johnson, Michael D.; Bouman, Katherine L.; Blackburn, Lindy L.; Akiyama, Kazunori; Narayan, Ramesh

    2018-04-01

    Interferometric imaging now achieves angular resolutions as fine as ∼10 μas, probing scales that are inaccessible to single telescopes. Traditional synthesis imaging methods require calibrated visibilities; however, interferometric calibration is challenging, especially at high frequencies. Nevertheless, most studies present only a single image of their data after a process of “self-calibration,” an iterative procedure where the initial image and calibration assumptions can significantly influence the final image. We present a method for efficient interferometric imaging directly using only closure amplitudes and closure phases, which are immune to station-based calibration errors. Closure-only imaging provides results that are as noncommittal as possible and allows for reconstructing an image independently from separate amplitude and phase self-calibration. While closure-only imaging eliminates some image information (e.g., the total image flux density and the image centroid), this information can be recovered through a small number of additional constraints. We demonstrate that closure-only imaging can produce high-fidelity results, even for sparse arrays such as the Event Horizon Telescope, and that the resulting images are independent of the level of systematic amplitude error. We apply closure imaging to VLBA and ALMA data and show that it is capable of matching or exceeding the performance of traditional self-calibration and CLEAN for these data sets.

  8. Remaining Sites Verification Package for the 120-F-1 Glass Dump Waste Site. Attachment to Waste Site Reclassification Form 2008-028

    International Nuclear Information System (INIS)

    Capron, J.M.

    2008-01-01

    The 120-F-1 waste site consisted of two dumping areas located 660 m southeast of the 105-F Reactor containing laboratory equipment and bottles, demolition debris, light bulbs and tubes, small batteries, small drums, and pesticide contaminated soil. It is probable that 108-F was the source of the debris but the material may have come from other locations within the 100-F Area. In accordance with this evaluation, the verification sampling results support a reclassification of this site to Interim Closed Out. The results of verification sampling show that residual contaminant concentrations do not preclude any future uses and allow for unrestricted use of shallow zone soils. The results also demonstrate that residual contaminant concentrations are protective of groundwater and the Columbia River

  9. Remedial action selection report Maybell, Colorado, site. Final report

    International Nuclear Information System (INIS)

    1996-12-01

    The Maybell uranium mill tailings site is 25 miles (mi) (40 kilometers [km]) west of the town of Craig, Colorado, in Moffat County, in the northwestern part of the state. The unincorporated town of Maybell is 5 road mi (8 km) southwest of the site. The site is 2.5 mi (4 km) northeast of the Yampa River on relatively flat terrain broken by low, flat-topped mesas. U.S. Highway 40 runs east-west 2 mi (3.2 km) south of the site. The designated site covers approximately 110 acres (ac) (45 hectares [ha]) and consists of a concave-shaped tailings pile and rubble from the demolition of the mill buildings buried in the former mill area. The site is situated between Johnson Wash to the east and Rob Pit Mine to the west. Numerous reclaimed and unreclaimed mines are in the immediate vicinity. Aerial photographs (included at the end of this executive summary) show evidence of mining activity around the Maybell site. Contaminated materials at the Maybell processing site include the tailings pile, which has an average depth of 20 feet (ft) (6 meters [ml]) and contains 2.8 million cubic yards (yd 3 ) (2.1 million cubic meters [m 3 ]) of tailings. The former mill processing area is on the north side of the site and contains 20,000 yd 3 (15,000 m 3 ) of contaminated demolition debris. Off-pile contamination is present and includes areas adjacent to the tailings pile, as well as contamination dispersed by wind and surface water flow. The volume of off-pile contamination to be placed in the disposal cell is 550,000 yd 3 (420,000 m 3 ). The total volume of contaminated materials to be disposed of as part of the remedial action is estimated to be 3.37 million yd 3 (2.58 million m 3 )

  10. Closure Report for Corrective Action Unit 261: Area 25 Test Cell A Leachfield System, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    T. M. Fitzmaurice

    2001-04-01

    The purpose of this Closure Report (CR) is to provide documentation of the completed corrective action at the Test Cell A Leachfield System and to provide data confirming the corrective action. The Test Cell A Leachfield System is identified in the Federal Facility Agreement and Consent Order (FFACO) of 1996 as Corrective Action Unit (CAU) 261. Remediation of CAU 261 is required under the FFACO (1996). CAU 261 is located in Area 25 of the Nevada Test Site (NTS) which is approximately 140 kilometers (87 miles) northwest of Las Vegas, Nevada (Figure 1). CAU 261 consists of two Corrective Action Sites (CASS): CAS 25-05-01, Leachfield; and CAS 25-05-07, Acid Waste Leach Pit (AWLP) (Figures 2 and 3). Test Cell A was operated during the 1960s and 1970s to support the Nuclear Rocket Development Station. Various operations within Building 3124 at Test Cell A resulted in liquid waste releases to the Leachfield and the AWLP. The following existing site conditions were reported in the Corrective Action Decision Document (CADD) (U.S. Department of Energy, Nevada Operations Office [DOE/NV], 1999): Soil in the leachfield was found to exceed the Nevada Division of Environmental Protection (NDEP) Action Level for petroleum hydrocarbons, the U.S. Environmental Protection Agency (EPA) preliminary remediation goals for semi volatile organic compounds, and background concentrations for strontium-90; Soil below the sewer pipe and approximately 4.5 meters (m) (15 feet [ft]) downstream of the initial outfall was found to exceed background concentrations for cesium-137 and strontium-90; Sludge in the leachfield septic tank was found to exceed the NDEP Action Level for petroleum hydrocarbons and to contain americium-241, cesium-137, uranium-234, uranium-238, potassium-40, and strontium-90; No constituents of concern (COC) were identified at the AWLP. The NDEP-approved CADD (DOWNV, 1999) recommended Corrective Action Alternative 2, ''Closure of the Septic Tank and Distribution Box

  11. 77 FR 70684 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Science.gov (United States)

    2012-11-27

    ... environmental risk to health or risk to safety that may disproportionately affect children. 10. Indian Tribal... the Cline Avenue bridge in East Chicago, IN. The Captain of the Port, Sector Lake Michigan, has determined that this demolition project will pose a significant risk to public safety and property. Such...

  12. 2011 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    Energy Technology Data Exchange (ETDEWEB)

    West, W. J.; Lucas, J. G.; Gano, K. A.

    2011-11-14

    This report documents the status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 cleanup of National Priorities List waste sites at Hanford. This report contains the vegetation monitoring data that was collected in the spring and summer of 2011 from the River Corridor Closure Contractor’s revegetation and mitigation areas on the Hanford Site.

  13. Gentrification in black and white: the racial impact of public housing demolition in American cities.

    Science.gov (United States)

    Goetz, Edward

    2011-01-01

    The gentrification that has transformed high-poverty neighbourhoods in US cities since the mid 1990s has been characterised by high levels of state reinvestment. Prominent among public-sector interventions has been the demolition of public housing and in some cases multimillion dollar redevelopment efforts. In this paper, the racial dimension of state-supported gentrification in large US cities is examined by looking at the direct and indirect displacement induced by public housing transformation. The data show a clear tendency towards the demolition of public housing projects with disproportionately high African American occupancy. The pattern of indirect displacement is more varied; public housing transformation has produced a number of paths of neighbourhood change. The most common, however, involve significant reductions in poverty, sometimes associated with Black to White racial turnover and sometimes not. The findings underscore the central importance of race in understanding the dynamics of gentrification in US cities.

  14. Total and respirable dust exposures among carpenters and demolition workers during indoor work in Denmark

    DEFF Research Database (Denmark)

    Kirkeskov, Lilli; Hanskov, Dorte Jessing Agerby; Brauer, Charlotte

    2016-01-01

    BACKGROUND: Within the construction industry the risk of lung disorders depends on the specific professions probably due to variations in the levels of dust exposure, and with dust levels depending on the work task and job function. We do not know the extent of exposure in the different professions...... was 3.90 (95 % confidence interval 1.13-13.5) mg/m(3). Dust exposure varied depending on work task for both professions. The dustiest work occurred during demolition, especially when it was done manually. Only few workers used personal respiratory protection and only while performing the dustiest work...... or the variation between the different work tasks. The purpose of this study was therefore to assess if there were differences in dust exposure between carpenters and demolition workers who were expected to have low and high dust exposure, respectively. METHODS: Through interviews of key persons...

  15. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Slick Rock, Colorado

    International Nuclear Information System (INIS)

    1993-07-01

    The Slick Rock uranium mill tailings sites are located near the small town of Slick Rock, in San Miguel County, Colorado. There are two designated UMTRA sites at Slick Rock, the Union Carbide (UC) site and the North Continent (NC) site. Both sites are adjacent to the Dolores River. The UC site is approximately 1 mile (mi) [2 kilometers (km)] downstream of the NC site. Contaminated materials cover an estimated 55 acres (ac) [22 hectares (ha)] at the UC site and 12 ac (4.9 ha) at the NC site. The sites contain former mill building concrete foundations, tailings piles, demolition debris, and areas contaminated by windblown and waterborne radioactive materials. The total estimated volume of contaminated materials is approximately 620, 000 cubic yards (yd 3 ) [470,000 cubic meters (m 3 )]. In addition to the contamination at the two processing site areas, four vicinity properties were contaminated. Contamination associated with the UC and NC sites has leached into groundwater

  16. Quantifying construction and demolition waste: An analytical review

    International Nuclear Information System (INIS)

    Wu, Zezhou; Yu, Ann T.W.; Shen, Liyin; Liu, Guiwen

    2014-01-01

    Highlights: • Prevailing C and D waste quantification methodologies are identified and compared. • One specific methodology cannot fulfill all waste quantification scenarios. • A relevance tree for appropriate quantification methodology selection is proposed. • More attentions should be paid to civil and infrastructural works. • Classified information is suggested for making an effective waste management plan. - Abstract: Quantifying construction and demolition (C and D) waste generation is regarded as a prerequisite for the implementation of successful waste management. In literature, various methods have been employed to quantify the C and D waste generation at both regional and project levels. However, an integrated review that systemically describes and analyses all the existing methods has yet to be conducted. To bridge this research gap, an analytical review is conducted. Fifty-seven papers are retrieved based on a set of rigorous procedures. The characteristics of the selected papers are classified according to the following criteria - waste generation activity, estimation level and quantification methodology. Six categories of existing C and D waste quantification methodologies are identified, including site visit method, waste generation rate method, lifetime analysis method, classification system accumulation method, variables modelling method and other particular methods. A critical comparison of the identified methods is given according to their characteristics and implementation constraints. Moreover, a decision tree is proposed for aiding the selection of the most appropriate quantification method in different scenarios. Based on the analytical review, limitations of previous studies and recommendations of potential future research directions are further suggested

  17. Quality and quantity of construction and demolition waste in Tehran.

    Science.gov (United States)

    Asgari, Alireza; Ghorbanian, Tahereh; Yousefi, Nader; Dadashzadeh, Dariush; Khalili, Fatemeh; Bagheri, Amin; Raei, Mehdi; Mahvi, Amir Hossein

    2017-01-01

    In recent years the generation rate of construction and demolition waste (C&D) has significantly augmented. The aim of this study was to assessed the quality and quantity of construction and demolition waste in Tehran (capital of Iran). Questionnaire methods were used for estimating the amount of generated C&D wastes national statistical data and typical waste generation data. In order to defining the composition of C&D waste, trucks were randomly selected and their wastes were separated and weighted. According to obtained results, about 82,646,051 m 3 of C&D waste (average 16,529,210 m 3 per year) were generated during 2011 to 2016 which only about 26% of them has been recycled. Mixing sand and cement, concrete, broken bricks and soil have the highest amount of the composition of C&D waste in Tehran that was 30, 19, 18 and 11%, respectively. Based on the results, about 2,784,158 t of the waste will generate in 2025 and this is approximately 122% higher than wastes generate in 2016. Based on MAPSA's data, 360 teams of personnel cruise and control the illegal disposals, but due to the expansion of Tehran this number of teams is inadequate and can't be effective in controlling the situation. In general, the overall condition of C&D waste management in Tehran seems undesirable and needs to be updated based on the experience of successful countries in this field.

  18. Integrating scientific results for a post-closure safety demonstration

    International Nuclear Information System (INIS)

    Taylor, E.C.; Ramspott, L.D.; Sinnock, S.; Sprecher, W.M.

    1994-01-01

    The U.S. Department of Energy (DOE) is developing a nuclear waste management system that will accept high-level radioactive waste, transport it, store it, and ultimately emplace it in a deep geologic repository. The key activity now is determining whether Yucca Mountain, Nevada is suitable as a site for the repository. If so, the crucial technological advance will be the demonstration that disposal of nuclear waste will be safe for thousands of years after closure. Recent regulatory, legal, and scientific developments imply that the safety demonstration must be simple. The scientific developments taken together support a simple set of hypotheses that constitute a post-closure safety argument for a repository at Yucca Mountain. If the understanding of Yucca Mountain hydrology presented in the Site Characterization Plan proves correct, then these hypotheses might be confirmed by combining results of Surface-Based Testing with early testing results in the Exploratory Studies Facility

  19. 77 FR 63732 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Science.gov (United States)

    2012-10-17

    ..., Protection of Children from Environmental Health Risks and Safety Risks. This rule is not an economically significant rule and does not create an environmental risk to health or risk to safety that may.... The Captain of the Port, Sector Lake Michigan, has determined that this demolition project will pose a...

  20. Cultural Resource Assessment of the Test Area North Demolition Landfill at the Idaho National Engineering and Environmental Laboratory

    Energy Technology Data Exchange (ETDEWEB)

    Brenda R. Pace

    2003-07-01

    The proposed new demolition landfill at Test Area North on the Idaho National Engineering and Environmental Laboratory (INEEL) will support ongoing demolition and decontamination within the facilities on the north end of the INEEL. In June of 2003, the INEEL Cultural Resource Management Office conducted archival searches, field surveys, and coordination with the Shoshone-Bannock Tribes to identify all cultural resources that might be adversely affected by the project and to provide recommendations to protect those listed or eligible for listing on the National Register of Historic Places. These investigations showed that landfill construction and operation would affect two significant cultural resources. This report outlines protective measures to ensure that these effects are not adverse.

  1. Cultural Resource Assessment of the Test Area North Demolition Landfill at the Idaho National Engineering and Environmental Laboratory

    International Nuclear Information System (INIS)

    Brenda R. Pace

    2003-01-01

    The proposed new demolition landfill at Test Area North on the Idaho National Engineering and Environmental Laboratory (INEEL) will support ongoing demolition and decontamination within the facilities on the north end of the INEEL. In June of 2003, the INEEL Cultural Resource Management Office conducted archival searches, field surveys, and coordination with the Shoshone-Bannock Tribes to identify all cultural resources that might be adversely affected by the project and to provide recommendations to protect those listed or eligible for listing on the National Register of Historic Places. These investigations showed that landfill construction and operation would affect two significant cultural resources. This report outlines protective measures to ensure that these effects are not adverse

  2. Characterization Report for the 92-Acre Area of the Area 5 Radioactive Waste Management Site, Nevada Test Site, Nevada

    International Nuclear Information System (INIS)

    Bechtel Nevada; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2006-01-01

    The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office manages two low-level Radioactive Waste Management Sites at the Nevada Test Site. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste. This report summarizes characterization and monitoring work pertinent to the 92-Acre Area in the southeast part of the Area 5 Radioactive Waste Management Sites. The decades of characterization and assessment work at the Area 5 RWMS indicate that the access controls, waste operation practices, site design, final cover design, site setting, and arid natural environment contribute to a containment system that meets regulatory requirements and performance objectives for the short- and long-term protection of the environment and public. The available characterization and Performance Assessment information is adequate to support design of the final cover and development of closure plans. No further characterization is warranted to demonstrate regulatory compliance. U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office is proceeding with the development of closure plans for the six closure units of the 92-Acre Area

  3. Characterization Report for the 92-Acre Area of the Area 5 Radioactive Waste Management Site, Nevada Test Site, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    Bechtel Nevada; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2006-06-01

    The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office manages two low-level Radioactive Waste Management Sites at the Nevada Test Site. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste. This report summarizes characterization and monitoring work pertinent to the 92-Acre Area in the southeast part of the Area 5 Radioactive Waste Management Sites. The decades of characterization and assessment work at the Area 5 RWMS indicate that the access controls, waste operation practices, site design, final cover design, site setting, and arid natural environment contribute to a containment system that meets regulatory requirements and performance objectives for the short- and long-term protection of the environment and public. The available characterization and Performance Assessment information is adequate to support design of the final cover and development of closure plans. No further characterization is warranted to demonstrate regulatory compliance. U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office is proceeding with the development of closure plans for the six closure units of the 92-Acre Area.

  4. Closure The Definitive Guide

    CERN Document Server

    Bolin, Michael

    2010-01-01

    If you're ready to use Closure to build rich web applications with JavaScript, this hands-on guide has precisely what you need to learn this suite of tools in depth. Closure makes it easy for experienced JavaScript developers to write and maintain large and complex codebases -- as Google has demonstrated by using Closure with Gmail, Google Docs, and Google Maps. Author and Closure contributor Michael Bolin has included numerous code examples and best practices, as well as valuable information not available publicly until now. You'll learn all about Closure's Library, Compiler, Templates, tes

  5. Properties of Concrete Paving Blocks and Hollow Tiles with Recycled Aggregate from Construction and Demolition Wastes.

    Science.gov (United States)

    Rodríguez, Carlos; Miñano, Isabel; Aguilar, Miguel Ángel; Ortega, José Marcos; Parra, Carlos; Sánchez, Isidro

    2017-11-30

    In recent years there has been an increasing tendency to recycle the wastes generated by building companies in the construction industry, demolition wastes being the most important in terms of volume. The aim of this work is to study the possibility of using recycled aggregates from construction and demolition wastes in the preparation of precast non-structural concretes. To that purpose, two different percentages (15% and 30%) of natural aggregates were substituted by recycled aggregates in the manufacture of paving blocks and hollow tiles. Dosages used by the company have not been changed by the introduction of recycled aggregate. Precast elements have been tested by means of compressive and flexural strength, water absorption, density, abrasion, and slipping resistance. The results obtained show the possibility of using these wastes at an industrial scale, satisfying the requirements of the Spanish standards for these elements.

  6. Uranium ISR Mine Closure — General Concepts and Model-Based Simulation of Natural Attenuation for South-Australian Mine Sites

    Energy Technology Data Exchange (ETDEWEB)

    Jeuken, B.; Märten, H.; Woods, P., E-mail: horst.maerten@heathgate.com.au [Heathgate Resources Pty. Ltd. (Heathgate), Adelaide (Australia); Kalka, H.; Nicolai, J. [Umwelt- und Ingenieurtechnik GmbH Dresden (UIT), Dresden (Germany)

    2014-05-15

    Heathgate has demonstrated the effect of natural attenuation (NA) in post in-situ recovery (ISR) aquifer regions during the operation of the Beverley mine since 2001. Enhanced natural attenuation (ENA) has been considered as the key component of the mine closure concept for the new Beverley Four Mile (BFM) project, complemented by an extensive monitoring program. Data from batch and column tests for BFM core samples was used to calibrate a reactive transport model, whose application in conjunction with the hydrological modelling of the BFM aquifer has shown that NA will result in the restoration of the aquifer in time. ENA within a staged mine development program under the site-specific circumstances is discussed. (author)

  7. Geopolymerisation of silt generated from construction and demolition waste washing plants.

    Science.gov (United States)

    Lampris, C; Lupo, R; Cheeseman, C R

    2009-01-01

    Recycling plants that size, sort and wash construction and demolition waste can produce high quality aggregate. However, they also produce up to 80ton per hour of filter cake waste containing fine (waste and normally landfilled. This research investigated the potential to form geopolymers containing silt, which would allow this problematic waste to be beneficially reused as aggregate. This would significantly improve the economic viability of recycling plants that wash wastes. Silt filter cakes have been collected from a number of aggregate washing plants operating in the UK. These were found to contain similar aluminosilicate crystalline phases. Geopolymer samples were produced using silt and silt mixed with either metakaolin or pulverised fuel ash (PFA). Silt geopolymers cured at room temperature had average 7-day compressive strengths of 18.7MPa, while partial substitution of silt by metakaolin or PFA increased average compressive strengths to 30.5 and 21.9MPa, respectively. Curing specimens for 24h at 105 degrees C resulted in a compressive strength of 39.7MPa and microstructural analysis confirmed the formation of dense materials. These strengths are in excess of those required for materials to be used as aggregate, particularly in unbound applications. The implications of this research for the management of waste silt at construction and demolition waste washing plants are discussed.

  8. Corporate strategy and viable future land use: Planning for closure from the outset of mining

    International Nuclear Information System (INIS)

    Warhurst, A.

    2000-01-01

    This paper provides an overview of the environmental impact of mining on viable future land use and underlines the imperative of improved environmental management and closure planning. It argues that pollution prevention, through planning for closure, can lead to cost-effective strategies for sustainable minerals development and viable future land use. This seems to be most true for greenfield sites since, generally, the earlier closure planning and pollution prevention is built into a project, the more cost-effective and environmentally benign closure will be. Further, for greenfield sites, pollution prevention techniques can be employed from the outset, at the stages of exploration and mine development, and then monitored and improved through the operation stage to closure, and can be kept in place to manage future land use. The paper discusses how global changes in the industry, following the liberalisation of investment regimes, and mergers and strategic alliances between key firms, has, by virtue of the diffusion of new technology, led to further opportunities to prevent pollution and optimise future land use through planning for closure from the outset. The objectives and components of closure plans are also reviewed as the paper draws on case studies to highlight some of the possible constraints and challenges to pollution prevention that may be faced at the level of both public policy and corporate strategy. The article concludes by suggesting a forward-looking approach to integrated environmental management and viable future land-use planning based on a dynamic model for environmental management. (author)

  9. Acoustic and vibrational tests of effects induced on building by the demolition of the 'Ponte del Barco' Firenze - Toscana

    International Nuclear Information System (INIS)

    Stragapede, Francesco; Biannucci, Roberto; Pascini, Lando Umberto; Leonasi, Giovanni

    2016-01-01

    For demolition of Ponte del Barco, the Torrente Mugnone overpass at the Parco delle Cascine of Firenze, were checked up entities in the field of energy and vibrational noise produced during activities on sensitive lens, considering the building located near the structure being demolished. The vibrations to the building have been checked with reference to noise thresholds of disturbance to the person (UNI 9614) and resentment/damage to the building (UNI 9 9 16). Evaluation of transient vibration actions on the building were examined during the demolition of the structure, carried out using excavator CAT 320 D LN equipped with concrete crusher, and handling stages of demolition material using excavator ZAX 2 40 Hitachi equipped with a shovel. The tests were conducted with Symphonie type level meter (class 1 REF. EN60651/94 and EN60804/9 4) and oriented velocimeters n. 4 recording stations using GEOBOX of Sara Electr. Instr. The noise level was compared with the acoustic limits of the area and the intensity of vibration induced on sensitive building was related to thresholds of disturbance to the person and damage to structures, ensuring that in the course of the demolition operations were the conditions of security of operators in the area and the absence of damage to the buildings. Based on the findings from the analysis, the acoustic activity of demolition of the Bridge in Florence took place within the acoustic limits of exemption of localization activities (class IV – area of intense human activity). The exceeded the thresholds of vibrational disturbance to the person was checked, in reference UNI 9614; the exceeded the thresholds for structural damage was not checked, in reference to UNI 9916. The attendance of the necessary staff for testing acoustic and vibrational did not affect any sensitive subject even in the presence of the excess of noise and vibration thresholds of disturbance to the person.

  10. An empirical investigation of construction and demolition waste generation rates in Shenzhen city, South China

    International Nuclear Information System (INIS)

    Lu Weisheng; Yuan Hongping; Li Jingru; Hao, Jane J.L.; Mi Xuming; Ding Zhikun

    2011-01-01

    The construction and demolition waste generation rates (C and D WGRs) is an important factor in decision-making and management of material waste in any construction site. The present study investigated WGRs by conducting on-site waste sorting and weighing in four ongoing construction projects in Shenzhen city of South China. The results revealed that WGRs ranged from 3.275 to 8.791 kg/m 2 and miscellaneous waste, timber for formwork and falsework, and concrete were the three largest components amongst the generated waste. Based on the WGRs derived from the research, the paper also discussed the main causes of waste in the construction industry and attempted to connect waste generation with specific construction practices. It was recommended that measures mainly including performing waste sorting at source, employing skilful workers, uploading and storing materials properly, promoting waste management capacity, replacing current timber formwork with metal formwork and launching an incentive reward program to encourage waste reduction could be potential solutions to reducing current WGRs in Shenzhen. Although these results were derived from a relatively small sample and so cannot justifiably be generalized, they do however add to the body of knowledge that is currently available for understanding the status of the art of C and D waste management in China.

  11. Post-Closure Inspection Report for Corrective Action Unit 404: Roller Coaster Sewage Lagoons and North Disposal Trench Tonopah Test Range, Nevada, Calendar Year 2000

    Energy Technology Data Exchange (ETDEWEB)

    K. B. Campbell

    2001-06-01

    Post-closure monitoring requirements for the Roller Coaster Sewage Lagoons and North Disposal Trench (Corrective Action Unit [CAW 404]) (Figure 1) are described in Closure Report for Corrective Action Unit 404, Roller Coaster Sewage Lagoons and North Disposal Trench, Tonopah Test Range, Nevada, report number DOE/NV--187. The Closure Report (CR) was submitted to the Nevada Division of Environmental Protection (NDEP) on September 11, 1998. Permeability results of soils adjacent to the engineered cover and a request for closure of CAU 404 were transmitted to the NDEP on April 29, 1999. The CR (containing the Post-Closure Monitoring Plan) was approved by the NDEP on May 18, 1999. Post-closure monitoring at CAU 404 consists of the following: (1) Site inspections done twice a year to evaluate the condition of the unit; (2) Verification that the site is secure; (3) Notice of any subsidence or deficiencies that may compromise the integrity of the unit; (4) Remedy of any deficiencies within 90 days of discovery; and (5) Preparation and submittal of an annual report. Site inspections were conducted on June 19, 2000, and November 21, 2000. The site inspections were conducted after completion of the revegetation activities (October 30, 1997) and NDEP approval of the CR (May 18, 1999). All site inspections were conducted in accordance with the Post-Closure Monitoring Plan in the NDEP-approved CR. This report includes copies of inspection checklists, photographs, recommendations, and conclusions. The Post-Closure Inspection Checklists are found in Attachment A, a copy of the field notes is found in Attachment B, and copies of the inspection photographs are found in Attachment C.

  12. 78 FR 29648 - Regulated Navigation Area; Waldo-Hancock Bridge Demolition, Penobscot River, Between Prospect and...

    Science.gov (United States)

    2013-05-21

    ... 1625-AA11 Regulated Navigation Area; Waldo-Hancock Bridge Demolition, Penobscot River, Between Prospect... River between Prospect and Verona, ME, under and surrounding the Waldo- Hancock Bridge in order to... Prospect and Verona, ME. (a) Location. The following area is a Regulated Navigation Area (RNA): All...

  13. Decommissioning and demolition of the Greifswald nuclear power station

    International Nuclear Information System (INIS)

    Sterner, H.; Leushacke, D.; Rittscher, D.

    1995-01-01

    The unexpected decision to decommission the plants in Greifswald makes the management and disposal of fuels and plant waste a major issue to be solved as a precondition for decommissioning and dismantling. The decisive point in waste management is the existence of an interim store or repository of sufficient capacity to accept both the nuclear fuel and the plant waste and the considerable volumes of radioactive residues arising in dismantling. Current major activities include planning for decommissioning and demolition, and drafting of the licensing documents; removal of the fuel elements from the reactor units; construction of the northern interim store for fuel elements and residues. (orig./HP)

  14. Estimating construction and demolition debris generation using a materials flow analysis approach.

    Science.gov (United States)

    Cochran, K M; Townsend, T G

    2010-11-01

    The magnitude and composition of a region's construction and demolition (C&D) debris should be understood when developing rules, policies and strategies for managing this segment of the solid waste stream. In the US, several national estimates have been conducted using a weight-per-construction-area approximation; national estimates using alternative procedures such as those used for other segments of the solid waste stream have not been reported for C&D debris. This paper presents an evaluation of a materials flow analysis (MFA) approach for estimating C&D debris generation and composition for a large region (the US). The consumption of construction materials in the US and typical waste factors used for construction materials purchasing were used to estimate the mass of solid waste generated as a result of construction activities. Debris from demolition activities was predicted from various historical construction materials consumption data and estimates of average service lives of the materials. The MFA approach estimated that approximately 610-78 × 10(6)Mg of C&D debris was generated in 2002. This predicted mass exceeds previous estimates using other C&D debris predictive methodologies and reflects the large waste stream that exists. Copyright © 2010 Elsevier Ltd. All rights reserved.

  15. Final closure of a low level waste disposal facility

    International Nuclear Information System (INIS)

    Potier, J.M.

    1995-01-01

    The low-level radioactive waste disposal facility operated by the Agence Nationale pour la Gestion des Dechets Radioactifs near La Hague, France was opened in 1969 and is scheduled for final closure in 1996. The last waste package was received in June 1994. The total volume of disposed waste is approximately 525,000 m 3 . The site closure consists of covering the disposal structures with a multi-layer impervious cap system to prevent rainwater from infiltrating the waste isolation system. A monitoring system has been set up to verify the compliance of infiltration rates with hydraulic performance objectives (less than 10 liters per square meter and per year)

  16. RCRA land unit closures at the Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Welch, S.H.; Kelly, B.A.; Delozier, M.F.P.; Manrod, W.E.

    1987-01-01

    Eight land-based hazardous waste management units at the Y-12 Plant are being closed under an integrated multi-year program. Closure plans for the units have been submitted and are in various stages of revision and regulatory review. These units will be closed by various combinations of methods, including liquid removal and treatment, sludge stabilization, contaminated sludge and/or soil removal, and capping. The closure of these sites will be funded by a new Department of Energy budget category, the Environmental Restoration Budget Category (ERBC), which is intended to provide greater flexibility in the response to closure and remedial activities. A major project, Closure and Post-Closure Activities (CAPCA), has been identified for ERBC funding to close and remediate the land units in accordance with RCRA requirements. Establishing the scope of this program has required the development of a detailed set of assumptions and a confirmation program for each assumption. Other significant activities in the CAPCA program include the development of risk assessments and the preparation of an integrated schedule

  17. Demolition to Green-Field conditions of the FRJ-1 (MERLIN) research reactor. Successes and hurdles in the demolition of a research reactor of the megawatt class; Der Rueckbau des Forschungsreaktors FRJ-1 (MERLIN) bis zur 'Gruenen Wiese'. Erfolge und Huerden beim Rueckbau eines Forschungsreaktors der Megawatt-Klasse

    Energy Technology Data Exchange (ETDEWEB)

    Stahn, Burkhard; Printz, Rudolf; Matela, Karel; Zehbe, Carsten; Stauch, Bernhard; Zander, Iven [Forschungszentrum Juelich GmbH, Juelich (Germany)

    2010-02-15

    The Juelich-1 Research Reactor (FRJ-1), also referred to as MERLIN (Medium Energy Research Light Water Moderated Industrial Nuclear Reactor), was a light-water moderated and cooled swimming pool reactor of British design. The cornerstone in the erection of the reactor building was laid on June 11, 1958. Reactor operation was started on February 23, 1962. The plant was last run at a thermal power of 10 MW and shut down for good in 1985 after 23 years of operation. After the fuel elements had been removed and most of the experimental installations dismantled, some first steps towards demolition were taken in 1995. Demolition on a large scale began in 1996. September 8, 2008 was a special day: On the area of the former reactor hall, an oak tree was planted as a symbol of the 'green field' and of the original oak wood which had to make way for the construction of reactors in Juelich. An oak tree now stands in the place of the reactor unit. Was that all? It was not, for there were ancillary systems, operations, utility and hygiene buildings which had to be pulled down. Decontamination and clearance measurements were completed. The application for clearance was prepared and completed. Conventional demolition was started in 2009. After completion of that step, the last chapter about demolition of the FRJ-1 research reactor has been written, and the book can be closed. (orig.)

  18. Impact of Different Standard Type A7A Drum Closure-Ring Practices on Gasket Contraction and Bolt Closure Distance– 15621

    Energy Technology Data Exchange (ETDEWEB)

    Ketusky, Edward [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Blanton, Paul [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Bobbitt, John H. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL)

    2015-03-11

    The Department of Energy, the Savannah River National Laboratory, several manufacturers of specification drums, and the United States Department of Transportation (DOT) are collaborating in the development of a guidance document for DOE contractors and vendors who wish to qualify containers to DOT 7A Type A requirements. Currently, the effort is focused on DOT 7A Type A 208-liter (55-gallons) drums with a standard 12-gauge bolted closure ring. The U.S. requirements, contained in Title 49, Part 178.350 “Specification 7A; general packaging, Type A specifies a competent authority review of the packaging is not required for the transport of (Class 7) radioactive material containing less than Type A quantities of radioactive material. For Type AF drums, a 4 ft. regulatory free drop must be performed, such that the drum “suffers maximum damage.” Although the actual orientation is not defined by the specification, recent studies suggest that maximum damage would result from a shallow angle top impact, where kinetic energy is transferred to the lid, ultimately causing heavy damage to the lid, or even worse, causing the lid to come off. Since each vendor develops closure recommendations/procedures for the drums they manufacture, key parameters applied to drums during closing vary based on vendor. As part of the initial phase of the collaboration, the impact of the closure variants on the ability of the drum to suffer maximum damage is investigated. Specifically, closure testing is performed varying: 1) the amount of torque applied to the closure ring bolt; and, 2) stress relief protocol, including: a) weight of hammer; and, b) orientation that the hammer hits the closure ring. After closure, the amount of drum lid gasket contraction and the distance that the closure bolt moves through the closure ring is measured.

  19. Field test of a post-closure radiation monitor

    International Nuclear Information System (INIS)

    Reed, S.; Christy, C.E.; Heath, R.E.

    1995-01-01

    The DOE is conducting remedial actions at many sites contaminated with radioactive materials. After closure of these sites, long-term subsurface monitoring is typically required by law. This monitoring is generally labor intensive and expensive using conventional sampling and analysis techniques. The U.S. Department of Energy's Morgantown Energy Technology Center (METC) has contracted with Babcock and Wilcox to develop a Long-Term Post-Closure Radiation Monitoring System (LPRMS) to reduce these monitoring costs. A prototype LPRMS probe was built, and B ampersand W and FERMCO field tested this monitoring probe at the Fernald Environmental Management Project in the fall of 1994 with funding from the DOE's Office of Technology Development (EM-50) through METC. The system was used to measure soil and water with known uranium contamination levels, both in drums and in situ at depths up to 3 meters. For comparison purposes, measurements were also performed using a more conventional survey probe with a sodium iodide scintillator directly butt-coupled to detection electronics. This paper presents a description and the results of the field tests. The results were used to characterize the lower detection limits, precision and bias of the system, which allowed the DOE to judge the monitoring system's ability to meet its long-term post-closure radiation monitoring needs. Based on the test results, the monitoring system has been redesigned for fabrication and testing in a potential Phase III of this program. If the DOE feels that this system can meet its needs and chooses to continue into Phase III of this program, this redesigned full scale prototype system will be built and tested for a period of approximately a year. Such a system can be used at a variety of radioactively contaminated sites

  20. Immobilization of calcium sulfate contained in demolition waste

    International Nuclear Information System (INIS)

    Ambroise, J.; Pera, J.

    2008-01-01

    This paper presents the results of a laboratory study undertaken to examine the treatment of demolition waste containing calcium sulfate by means of calcium sulfoaluminate clinker (CSA). The quantity of CSA necessary to entirely consume calcium sulfate was determined. Using infrared spectrometry analysis and X-ray diffraction, it was shown that calcium sulfate was entirely consumed when the ratio between CSA and calcium sulfate was 4. Standard sand was polluted by 4% calcium sulfate. Two solutions were investigated: ·either global treatment of sand by CSA, ·or immobilization of calcium sulfate by CSA, followed by the introduction of this milled mixture in standard sand. Regardless of the type of treatment, swelling was almost stabilized after 28 days of immersion in water