WorldWideScience

Sample records for case studies decommissioning

  1. Knowledge Management Aspects of Decommissioning. Case Study

    International Nuclear Information System (INIS)

    Pironkov, Lyubomir

    2017-01-01

    Kozloduy NPP: Units 5&6, type VVER-1000 - in operation. SE RAW SD “Decommissioning of units 1-4” (type VVER-440); SD “Radioactive Waste – Kozloduy”; SD “National Repository for Radioactive Waste“; SD “Permanent Repository for Radioactive Waste – Novi Han”. Decommissioning Strategy: Strategy Target: “Brown Field”. Initial Version: Safe enclosure – completing by 2050. Updated Version: Continuous dismantling of equipment; Completing the process of Decommissioning of Units 1-4 by 2030. Major Phases: 1.Pre-decommissioning activities; 2.Facility shutdown activities; 3.Procurement of equipment; 4.Dismantling activities; 5.Treatment of RAM and RAW and delivery for disposal; 6.Site management and support; 7.Project management and engineering; 8.Management of SNF and activated materials

  2. Los Alamos National Laboratory case studies on decommissioning of research reactors and a small nuclear facility

    International Nuclear Information System (INIS)

    Salazar, M.D.

    1998-01-01

    Approximately 200 contaminated surplus structures require decommissioning at Los Alamos National Laboratory. During the last 10 years, 50 of these structures have undergone decommissioning. These facilities vary from experimental research reactors to process/research facilities contaminated with plutonium-enriched uranium, tritium, and high explosives. Three case studies are presented: (1) a filter building contaminated with transuranic radionuclides; (2) a historical water boiler that operated with a uranyl-nitrate solution; and (3) the ultra-high-temperature reactor experiment, which used enriched uranium as fuel

  3. Los Alamos National Laboratory case studies on decommissioning of research reactors and a small nuclear facility

    Energy Technology Data Exchange (ETDEWEB)

    Salazar, M.D.

    1998-12-01

    Approximately 200 contaminated surplus structures require decommissioning at Los Alamos National Laboratory. During the last 10 years, 50 of these structures have undergone decommissioning. These facilities vary from experimental research reactors to process/research facilities contaminated with plutonium-enriched uranium, tritium, and high explosives. Three case studies are presented: (1) a filter building contaminated with transuranic radionuclides; (2) a historical water boiler that operated with a uranyl-nitrate solution; and (3) the ultra-high-temperature reactor experiment, which used enriched uranium as fuel.

  4. Feasibility studies for decommissioning

    International Nuclear Information System (INIS)

    Hladky, E.

    2000-01-01

    In this presentation author deals with planning of decommission of the NPPs A1, V1 and V2 Bohunice and Mochovce. It was concluded that: Used model for decommissioning parameters assessment has been suitable for elaboration of initial decommissioning plans (feasibility studies); Basic assessment of main decommissioning parameters and basic comparison of various decommissioning options have been possible; Improvement of the model and corresponding software is desirable and works on software improvement began one year ago; V1-NPP initial decommissioning plan should be actualized, because initial decommissioning plan does not correspond by its content and structure to requirements of Act No. 130/98 and Nuclear Regulatory Authority Degree No. 246/99; Strategy of radioactive wastes treatment and conditioning together with technical provisions at Jaslovske Bohunice site was changed in comparison with the assumptions in 1991-92; Considered V1 NPP decommissioning options are necessary to be re-evaluated in accordance with latest development of knowledge and approaches to NPP decommissioning in the world; Specific unit costs are substantially and differentially changed in comparison with the assumptions in 1991-92; Necessity to take into account technical changes resulted from V1 NPP reconstruction. (author)

  5. Study on decommissioning

    International Nuclear Information System (INIS)

    2012-01-01

    This project consists of researches on (1) establishment of review plan on application of decommissioning, (2) establishment of specific method to confirm decommissioning completion, of decommissioning and (3) establishment of radioactive waste management guideline during dismantling and (4) development of the regulatory system on decommissioning in response to Fukushima Daiichi NPP accident. About researches on establishment of review plan on application of decommissioning. 'Planning of the Commercial Power Reactor Decommissioning:2001' which was published by Atomic Energy Society of Japan, was evaluated whether it suited the requirement for the decommissioning stipulated in the law, and the draft evaluation report was prepared. About researches on establishment of specific method to confirm decommissioning completion, technical information of practical procedures on the confirmation in U.S.A. were organized based on MARSSIM (Multi-Agency Radiation Survey and Site Investigation Manual, NUREG-1575) and applicability of MARSSIM on the confirmation in Japan was examined. Exposed doses for public during decommissioning period were estimated to study dose criterion of the confirmation. Radioactive concentrations in the soil of Tokai and Hamaoka NPP caused by the Fukushima Daiichi NPP accident were also investigated. About researches on establishment of radioactive waste management guideline during dismantling, one concrete core was sampled in biological shield of the Tokai NPP and radioactive concentrations were investigated. About researches on development of the regulatory system on decommissioning in response to Fukushima Daiichi NPP accident, present status of Three Mile Island Unit 2 and Chernobyl NPP Unit 4 were investigated. Present status of regulatory systems for decommissioning in foreign countries taken in consideration of the accident was also researched. (author)

  6. The Study on Domestic and Foreign Cases for Decommissioning of DPRK Nuclear Facilities

    International Nuclear Information System (INIS)

    Baek, Ye Ji; Hhu, Joo Youn; Lee, Jung Hyun; Hwang, Yong Soo

    2016-01-01

    This study was able to analyze domestic and foreign cases, and collect data on the approximate amount of waste and time required time; however, data on applied technology, input manpower, required cost, and waste disposal method was insufficient. DPRK activities such as nuclear weapon development or nuclear testing not only threaten our country's security but also have an adverse effect on nuclear nonproliferation and security in the international society. Therefore, denuclearization of the DPRK is prior task that is essential to peace on the Korean Peninsula. The fundamental purpose of denuclearization of the DPRK is to safely decommission facilities related to developing nuclear weapons and to depose related radioactive waste and nuclear materials. Understanding descriptive references and physical properties of the facility and its purpose important for decommissioning nuclear facilities. Although it was impossible to collect data on DPRK nuclear facilities to perform complete decommissioning, we were able to understand the process used at DPRK nuclear facilities with open source data. This study has been conducted to establish overall measures for decommissioning DPRK nuclear facilities. DPRK nuclear facilities in this study include a IRT- 2000 type nuclear research reactor, a 5 MWe graphite moderated reactor, nuclear fuel fabrication facility, and a nuclear fuel reprocessing facility, which are considered as facilities that produce or manufacture nuclear materials needed for nuclear weapons or related to such activities.

  7. The Study on Domestic and Foreign Cases for Decommissioning of DPRK Nuclear Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Baek, Ye Ji; Hhu, Joo Youn; Lee, Jung Hyun; Hwang, Yong Soo [Korea Institute of Nuclear Non-proliferation and Control, Daejeon (Korea, Republic of)

    2016-05-15

    This study was able to analyze domestic and foreign cases, and collect data on the approximate amount of waste and time required time; however, data on applied technology, input manpower, required cost, and waste disposal method was insufficient. DPRK activities such as nuclear weapon development or nuclear testing not only threaten our country's security but also have an adverse effect on nuclear nonproliferation and security in the international society. Therefore, denuclearization of the DPRK is prior task that is essential to peace on the Korean Peninsula. The fundamental purpose of denuclearization of the DPRK is to safely decommission facilities related to developing nuclear weapons and to depose related radioactive waste and nuclear materials. Understanding descriptive references and physical properties of the facility and its purpose important for decommissioning nuclear facilities. Although it was impossible to collect data on DPRK nuclear facilities to perform complete decommissioning, we were able to understand the process used at DPRK nuclear facilities with open source data. This study has been conducted to establish overall measures for decommissioning DPRK nuclear facilities. DPRK nuclear facilities in this study include a IRT- 2000 type nuclear research reactor, a 5 MWe graphite moderated reactor, nuclear fuel fabrication facility, and a nuclear fuel reprocessing facility, which are considered as facilities that produce or manufacture nuclear materials needed for nuclear weapons or related to such activities.

  8. Case Study to Apply Work Difficulty Factors to Decommissioning Cost Estimates

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Jung, Hyejin; Oh, Jaeyoung; Kim, Younggook [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    This article is prepared as a guideline regarding how to apply the work difficult factor (WDF) when it comes to the estimates of the decommissioning costs. Although several cases of the decommissioning cost estimates have been made for a few commercial nuclear power plants, the different technical, site-specific economic assumptions used make it difficult to interpret those cost estimates and compare them with that of Kori-1. In addition, it is clear that we are supposed to experience difficulties being created in the process of the Kori-1 and the virtual inaccessibility to the limited areas at the pre-decommissioning stage. Estimating decommissioning costs is one of the most crucial processes since it encompasses all the spectrum of decommissioning activities from the planning to the last evaluation on whether the decommissioning has successfully been proceeded from the safety and economic perspectives. Here I suggested the activity dependent costs is only related to WDFs of the incumbent plant planning or undergone to be decommissioned since as a matter of fact, estimating WDFs is the core process to articulately scrutinize the practical costs to apply to Kori-1 project.

  9. Study on decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-08-15

    This study examines the status of maintenance of the decommissioning-related regulations to which the maintenance is still insufficient. The contents in 2012 are as follows. First, we examined site release criteria through reports by international organizations, by overseas countries where nuclear sites have been released, and the environment standards in Japan. Then we also examined the standards of decommissioning completion confirmation (in other words, site release criteria). The study results will be utilized to document standards. Second, we assessed the present Japanese decommissioning regulatory system based on safety requirements of IAEA, and identified improvements. Then we prepared an improvement plan benefiting from the regulatory experiences in foreign countries. The study results will be utilized to document standards. Third, the Fukushima Daiichi NPS, which experienced serious core accident in March, 2011, has become a Specified Nuclear Facilities according to the new nuclear regulation, and the examination of the implementation plan is performed of the Nuclear Regulation Authority. As Units 1 to 4 at the Fukushima Daiichi NPS are planned to be decommissioned, we investigated regulatory requirements in foreign countries which experienced severe accidents. (author)

  10. INL - NNL an International Technology Collaboration Case Study - Advanced Fogging Technologies for Decommissioning - 13463

    International Nuclear Information System (INIS)

    Banford, Anthony; Edwards, Jeremy; Demmer, Rick; Rankin, Richard; Hastings, Jeremy

    2013-01-01

    International collaboration and partnerships have become a reality as markets continue to globalize. This is the case in nuclear sector where over recent years partnerships commonly form to bid for capital projects internationally in the increasingly contractorized world and international consortia regularly bid and lead Management and Operations (M and O) / Parent Body Organization (PBO) site management contracts. International collaboration can also benefit research and technology development. The Idaho National Laboratory (INL) and the UK National Nuclear Laboratory (NNL) are internationally recognized organizations delivering leading science and technology development programmes both nationally and internationally. The Laboratories are actively collaborating in several areas with benefits to both the laboratories and their customers. Recent collaborations have focused on fuel cycle separations, systems engineering supporting waste management and decommissioning, the use of misting for decontamination and in-situ waste characterisation. This paper focuses on a case study illustrating how integration of two technologies developed on different sides of the Atlantic are being integrated through international collaboration to address real decommissioning challenges using fogging technology. (authors)

  11. INL - NNL an International Technology Collaboration Case Study - Advanced Fogging Technologies for Decommissioning - 13463

    Energy Technology Data Exchange (ETDEWEB)

    Banford, Anthony; Edwards, Jeremy [National Nuclear Laboratory, 5th Floor Chadwick House, Birchwood Park, Warrington WA3 6AE(United Kingdom); Demmer, Rick; Rankin, Richard [Idaho National Laboratory, Idaho Falls, ID 83401(United States); Hastings, Jeremy [National Nuclear Laboratory, Central Laboratory Sellafield, Seascale, Cumbria CA20 1PG (United Kingdom)

    2013-07-01

    International collaboration and partnerships have become a reality as markets continue to globalize. This is the case in nuclear sector where over recent years partnerships commonly form to bid for capital projects internationally in the increasingly contractorized world and international consortia regularly bid and lead Management and Operations (M and O) / Parent Body Organization (PBO) site management contracts. International collaboration can also benefit research and technology development. The Idaho National Laboratory (INL) and the UK National Nuclear Laboratory (NNL) are internationally recognized organizations delivering leading science and technology development programmes both nationally and internationally. The Laboratories are actively collaborating in several areas with benefits to both the laboratories and their customers. Recent collaborations have focused on fuel cycle separations, systems engineering supporting waste management and decommissioning, the use of misting for decontamination and in-situ waste characterisation. This paper focuses on a case study illustrating how integration of two technologies developed on different sides of the Atlantic are being integrated through international collaboration to address real decommissioning challenges using fogging technology. (authors)

  12. Summary of case studies presented at the WPDD topical session on stakeholder involvement in decommissioning projects - november 14, 2005

    International Nuclear Information System (INIS)

    Metcalfe, Doug

    2006-01-01

    Full text of publication follows: Two case studies were presented on experiences with stakeholder involvement in decommissioning projects. The first paper described the development of the United Kingdom Atomic Energy Authority's (UKAEA) stakeholder involvement activities for the Dounreay Nuclear Reactor Test Establishment. The second paper presented the US Nuclear Regulatory Commission regulatory process for decommissioning that includes opportunities for public involvement. The presentation contrasted the stakeholder involvement for two commercial US nuclear power plants (NPPs) that completed decommissioning in 2005, the Trojan NPP and the Maine Yankee NPP. The two case studies highlighted the importance of involving stakeholders in decommissioning projects, and provide important lessons learned. The Dounreay case study demonstrated the UKAEA's determination and commitment to continuously improve its stakeholder engagement program. In 2002, the UKAEA set out to broaden its stakeholder program by improving both public understanding and participation. With regard to public understanding, the UKAEA committed to keep the public informed on decommissioning developments, and ensure that communication was in an understandable form. To improve participation, the UKAEA actively worked to identify and engage stakeholders. The UKAEA then made efforts to involve stakeholders in decision-making activities, including the use of stakeholder panels to discuss and consider options for specific aspects of the Dounreay decommissioning and site restoration plan. In 2004, the UKAEA commissioned an independent review of its stakeholder involvement program to assess the program's effectiveness and benchmark it against best practices. The program was found to be useful, and positive feedback was provided on the use of stakeholder panels and the UKAEA's determination to deliver a broad based and effective stakeholder strategy. Recommendations to UKAEA included involving stakeholders

  13. Decommissioning Study of Oskarshamn NPP

    International Nuclear Information System (INIS)

    Larsson, Helena; Anunti, Aake; Edelborg, Mathias

    2013-06-01

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for Oskarshamn NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding

  14. Decommissioning study of Forsmark NPP

    International Nuclear Information System (INIS)

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias

    2013-06-01

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding

  15. Decommissioning Study of Oskarshamn NPP

    Energy Technology Data Exchange (ETDEWEB)

    Larsson, Helena; Anunti, Aake; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for Oskarshamn NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  16. Decommissioning study of Forsmark NPP

    Energy Technology Data Exchange (ETDEWEB)

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  17. Direction for the Estimation of Required Resources for Nuclear Power Plant Decommissioning based on BIM via Case Study

    Energy Technology Data Exchange (ETDEWEB)

    Jung, Insu [Korea Institute of Construction Technology, Goyang (Korea, Republic of); Kim, Woojung [KHNP-Central Research Institute, Daejeon (Korea, Republic of)

    2014-05-15

    Ways to estimate decommissioning of required resources in the past have imposed great uncertainty since they analyze required resources at the construction stage, analyzing and consulting decommissioning required resources of overseas nuclear power plants. As demands on efficient management and use of complicated construction information increased these days, demands on the introduction of Building Information Modeling (herein after referred to as BIM) technology has increased. In the area of quotation, considerable effects are expected as to the accuracy and reliability predicting construction costs through the characteristics that can automatically estimate quantities by using attribute information of BIM model. BIM-based estimation and quotation of required resources is more accurate than the existing 2D-based quotations and have many advantages such as reviews over constructability and interference. It can be desirable to estimate decommissioning required resources in nuclear power plants using BIM as well as using tools that are compatible with usual international/industrial standards. As we looked into the cases where required resources were estimated, using BIM in Korea and abroad, they dealt with estimation of required resources, estimation of construction cost and process management at large. In each area, methodologies, classification systems, BIM, and realization tests have been used variably. Nonetheless, several problems have been reported, and among them, it is noticeable that although BIM standard classification system exists, no case was found that has used standard classification system. This means that no interlink among OBS (Object Breakdown Structure), WBS (Work Breakdown Structure) and CBS (Cost Breakdown Structure) was possible. Thus, for nuclear power plant decommissioning, decommissioning method and process, etc. shall be defined clearly in the stage of decommissioning strategy establishment, so that classification systems must be set up

  18. Direction for the Estimation of Required Resources for Nuclear Power Plant Decommissioning based on BIM via Case Study

    International Nuclear Information System (INIS)

    Jung, Insu; Kim, Woojung

    2014-01-01

    Ways to estimate decommissioning of required resources in the past have imposed great uncertainty since they analyze required resources at the construction stage, analyzing and consulting decommissioning required resources of overseas nuclear power plants. As demands on efficient management and use of complicated construction information increased these days, demands on the introduction of Building Information Modeling (herein after referred to as BIM) technology has increased. In the area of quotation, considerable effects are expected as to the accuracy and reliability predicting construction costs through the characteristics that can automatically estimate quantities by using attribute information of BIM model. BIM-based estimation and quotation of required resources is more accurate than the existing 2D-based quotations and have many advantages such as reviews over constructability and interference. It can be desirable to estimate decommissioning required resources in nuclear power plants using BIM as well as using tools that are compatible with usual international/industrial standards. As we looked into the cases where required resources were estimated, using BIM in Korea and abroad, they dealt with estimation of required resources, estimation of construction cost and process management at large. In each area, methodologies, classification systems, BIM, and realization tests have been used variably. Nonetheless, several problems have been reported, and among them, it is noticeable that although BIM standard classification system exists, no case was found that has used standard classification system. This means that no interlink among OBS (Object Breakdown Structure), WBS (Work Breakdown Structure) and CBS (Cost Breakdown Structure) was possible. Thus, for nuclear power plant decommissioning, decommissioning method and process, etc. shall be defined clearly in the stage of decommissioning strategy establishment, so that classification systems must be set up

  19. Preliminary nuclear decommissioning cost study

    International Nuclear Information System (INIS)

    Sissingh, R.A.P.

    1981-04-01

    The decommissioning of a nuclear power plant may involve one or more of three possible options: storage with surveillance (SWS), restricted site release (RSR), and unrestricted site use(USU). This preliminary study concentrates on the logistical, technical and cost aspects of decommissioning a multi-unit CANDU generating station using Pickering GS as the reference design. The procedure chosen for evaluation is: i) removal of the fuel and heavy water followed by decontamination prior to placing the station in SWS for thiry years; ii) complete dismantlement to achieve a USU state. The combination of SWS and USU with an interim period of surveillance allows for radioactive decay and hence less occupational exposure in achieving USU. The study excludes the conventional side of the station, assumes waste disposal repositories are available 1600 km away from the station, and uses only presently available technologies. The dismantlement of all systems except the reactor core can be accomplished using Ontario Hydro's current operating, maintenance and construction procedures. The total decommissioning period is spread out over approximately 40 years, with major activities concentrated in the first and last five years. The estimated dose would be approximately 1800 rem. Overall Pickering GS A costs would be $162,000,000 (1980 Canadian dollars)

  20. Concrete release protocol case studies for decommissioning work at the Idaho National Engineering and Environmental Laboratory

    International Nuclear Information System (INIS)

    Kamboj, S.; Arnish, J.; Chen, S-Y; Parker, F. L.; Phillips, A. M.; Tripp, J. L.; Meservey, R. H.

    2000-01-01

    in 1996 was used in the analysis; therefore, because of radioactive decay, the resultant doses to receptors (now or later) would be less than the values reported in this analysis. For the generic case study, costs associated with Alternatives A and C were shown to be much smaller than for Alternative E. For the INEEL-specific case, in general, costs were much higher for Alternatives A and C than for Alternative E because of on-site disposal with zero disposal cost

  1. Detritiation studies for JET decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Perevezentsev, A.N.; Bell, A.C.; Williams, J.; Brennan, P.D. [EURATOM/UKAEA Fussion Association, Culham Science Centre, Abingdon (United Kingdom)

    2007-07-01

    JET is the world largest tokamak and has the capacity of operating with a tritium plasma. Three experimental campaigns, the Preliminary Tritium Experiment (0.1g T{sub 2}) in 1991, the Trace Tritium Experiment (5g T{sub 2}) in 2005, and the large experiment, the Deuterium-Tritium Experiment (DTE1) (100g T{sub 2}) in 1997, were carried out at JET with tritium plasmas. In DTE1 about 35 grams of tritium were fed directly into the vacuum vessel, with about 30% of this tritium being retained inside the vessel. In several years time JET will cease experimental operations and enter a decommissioning phase. In preparation for this the United Kingdom Atomic Energy Authority, the JET Operator, has been carrying out studies of various detritiation techniques. The materials which have been the subject of these studies include solid materials, such as various metals (Inconel 600 and 625, stainless steel 316L, beryllium, 'oxygen-free' copper, aluminium bronze), carbon fibre composite tiles, 'carbon' flakes and dust present in the vacuum vessel and also soft housekeeping materials. Liquid materials include organic liquids, such as vacuum oils and scintillation cocktails, and water. Detritiation of gas streams was also investigated. The purpose of the studies was to select and experimentally prove primary and auxiliary technologies for in-situ detritiation of in-vessel components and ex-situ detritiation of components removed from the vessel. The targets of ex-vessel detritiation were a reduction of the tritium inventory in and the rate of tritium out-gassing from the materials, and conversion, if possible, of intermediate level waste to low level waste and a reduction in volume of waste for disposal. The results of experimental trials and their potential application are presented. (orig.)

  2. Study on the decommissioning of research reactor

    Energy Technology Data Exchange (ETDEWEB)

    Suh, Doo Hwan; Jun, Kwan Sik; Choi, Yoon Dong; Lee, Tae Yung; Kwon, Sang Woon; Lee, Jong Il [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    1995-01-01

    Currently, KAERI operates TRIGA Mark-II and TRIGA Mark-III research reactors as a general purpose research and training facility. As these are, however, situated at Seoul office site of KAERI which is scheduled to be transferred to KEPCO as well as 30 MW HANARO research reactor which is expected to reach the first criticality in 1995 is under construction at head site of KAERI, decommissioning of TRIGA reactors has become an important topic. The objective of this study is to prepare and present TRIGA facility decontamination and decommissioning plan. Estimation of the radioactive inventory in TRIGA research reactor was carried out by the use of computational method. In addition, summarized in particular were the methodologies associated with decontamination, segmenting processes for activated metallic components, disposition of wastes. Particular consideration in this study was focused available technology applicable to decommissioning of TRIGA research reactor. State-of-the-art summaries of the available technology for decommissioning presented here will serve a useful document for preparations for decommissioning in the future. 6 figs, 41 tabs, 30 refs. (Author).

  3. Decommissioning and decontamination (burial ground stabilization) studies

    International Nuclear Information System (INIS)

    Cline, J.F.

    1980-01-01

    The decommissioning and decontamination of retired Hanford facilities and the future use of surrounding landscapes require isolation of contaminated wastes from the biosphere. Burial ground stabilization studies were conducted to determine the effectiveness of physical barriers for isolating contaminated wastes in shallow-land burial sites from plants and animals. This study was undertaken to determine the effectiveness of using a layer of loose rock between the waste and the surface soil covering to prevent both plant root and animal penetrations

  4. A Human Factors Study on an Information Visualization System for Nuclear Power Plants Decommissioning Engineering

    Energy Technology Data Exchange (ETDEWEB)

    Yang, Chih Wei; Yang, Li Chen [Institute of Nuclear Energy Research, Atomic Energy Council, Longtan (China)

    2014-08-15

    Most nuclear power plants (NPPs) in the world have an operating life of up to 40 years. The utility should prepare a comprehensive decommissioning plan with purpose to document and to display how decommissioning activities can be safely performed. In the past, most studies related to NPPs decommissioning planning put emphasis on technical issues, little attention have been given to human factors in decommissioning activities. In fact, human factors are a critical factor to successful NPPs decommissioning. NPPs decommissioning will face potential risks. These risks include not only dismantling and moving large equipment but also treating with the radioactive materials. Using information visualization system, such as virtual reality (VR) technology, for staff training can improve decommissioning work safety and economy. Therefore, this study presents a study using VR to solve real world problems in the nuclear plant decommissioning. Then appropriate cases for introducing VR systems are summarized and future prospects are given. This study assesses availability and performance of the work training system by using heuristic evaluation and actual experiment. In the result, block type of radiation visibility was found relatively better both in performance and person's preference than other types. The results presented in this paper illustrate the VR applications a NPP decommissioning perspective.

  5. A Human Factors Study on an Information Visualization System for Nuclear Power Plants Decommissioning Engineering

    International Nuclear Information System (INIS)

    Yang, Chih Wei; Yang, Li Chen

    2014-01-01

    Most nuclear power plants (NPPs) in the world have an operating life of up to 40 years. The utility should prepare a comprehensive decommissioning plan with purpose to document and to display how decommissioning activities can be safely performed. In the past, most studies related to NPPs decommissioning planning put emphasis on technical issues, little attention have been given to human factors in decommissioning activities. In fact, human factors are a critical factor to successful NPPs decommissioning. NPPs decommissioning will face potential risks. These risks include not only dismantling and moving large equipment but also treating with the radioactive materials. Using information visualization system, such as virtual reality (VR) technology, for staff training can improve decommissioning work safety and economy. Therefore, this study presents a study using VR to solve real world problems in the nuclear plant decommissioning. Then appropriate cases for introducing VR systems are summarized and future prospects are given. This study assesses availability and performance of the work training system by using heuristic evaluation and actual experiment. In the result, block type of radiation visibility was found relatively better both in performance and person's preference than other types. The results presented in this paper illustrate the VR applications a NPP decommissioning perspective

  6. A study on the optimization of plant life extension and decommissioning for the improvement of economy in nuclear power plant

    Energy Technology Data Exchange (ETDEWEB)

    Shin, Jae In; Jung, K. J.; Chung, U. S.; Baik, S. T.; Park, S. K.; Lee, D. G.; Kim, H. R.; Park, B. Y

    2000-01-01

    Fundamentals on the plan, the national policy, the safety securities for the life extension of the nuclear power plant was established from the domestic/abroad documents and case studies in relation with the life extension and decommissioning of the nuclear power plant. Concerning the decommissioning of the nuclear power plant, the management according to decommissioning stages was analyzed by the investigation of the domestic/abroad standard of the decommissioning (decontamination. dismantling) technology and regulation. Moreover, the study on the cost estimation method has been carried out for the decommissioning of the nuclear power plant. (author)

  7. Some studies related to decommissioning of nuclear reactors

    International Nuclear Information System (INIS)

    Bergman, C.; Menon, S.

    1990-02-01

    Decommissioning of large nuclear reactors has not yet taken place in the Nordic countries. Small nuclear installations, however, have been dismantled. This NKA-programme has dealt with some interesting and important factors which have to be analysed before a large scale decommissioning programme starts. Prior to decommissioning, knowledge is required regarding the nuclide inventory in various parts of the reactor. Measurements were performed in regions close to the reactor tank and the biological shield. These experimental data are used to verify theoretical calculations. All radioactive waste generated during decommissioning will have to be tansported to a repository. Studies show that in all the Nordic countries there are adequate transport systems with which decommissioning waste can be transported. Another requirement for orderly decommissioning planning is that sufficient information about the plant and its operation history must be available. It appears that if properly handled and sorted, all such information can be extracted from existing documentation. (authors)

  8. Envisioning Communications with Future Stakeholders - A Case Study Using the In-Situ Decommissioning of P-Reactor

    International Nuclear Information System (INIS)

    Antonucci, D.L.

    2009-01-01

    This paper will explore opportunities to expand the CAB's public outreach by the incorporation of technologies typically used in social networks and distance learning. Envisioning opportunities to engage next generation CAB members in public involvement will be delineated by retracing the decision process used with the in-situ decommissioning of P-Reactor at the Savannah River Site (SRS). This paper will discuss existing opportunities to enable another group of stakeholders to take part in the environmental policy decision making process regarding the inclusion of some very long lived radioactive constituents. The aim of the paper will be to locate places in the current process where alternate or parallel informational dissemination pathways could exist. These alternatives will incorporate the next generation's expectation for instantaneous information and universal ownership of hand-held communication devices. The goal of this paper is to use the present framework of CAB communications and add the components of virtual networking and distance learning in hopes of bridging the generational technology gap and extending the dialog to future stakeholders. (authors)

  9. The decommissioning of a research reactor in the USA: A case study from planning to site release

    International Nuclear Information System (INIS)

    Boing, L.E.

    1997-01-01

    Argonne National Laboratory (ANL) has completed the D ampersand D of the Experimental Boiling Water Reactor (EBWR). The project consisted of the decontamination and/or packaging as radioactive waste the reactor vessel and internals, contaminated piping systems, miscellaneous tanks, pumps, and associated equipment. The dismantling process involved the removal and size reduction of equipment and associated plumbing, ductwork, drain lines, etc. Size reduction of reactor vessel internals was performed in the fuel pool. All radioactive and mixed waste was packaged and manifested. A thorough survey of the facility was performed after the removal of contaminated and activated material. Non-radioactive waste was disposed of in the ANL landfill or recycled as appropriate. The EBWR D ampersand D project was divided into four phases. Phases I and II were completed by ANL personnel, while Phases III and IV were done by a contractor under ANL management. The final survey was performed by the contractor, while the verification survey was performed by ANL. The project lasted 118 months. Phase I was initiated in April 1986 and the final report was issued February 1996. The duration of the project was driven by the availability of funding for decommissioning. Total exposure to project personnel was 208.7 person-mSv (20.87 person-rem), with no personnel exceeding the EBWR project dose limit of 15 mSv (1.5 rem)

  10. SRP decontamination and decommissioning scoping study

    International Nuclear Information System (INIS)

    Martin, W.P.

    1986-06-01

    Of the approximately 3000 site facilities, 496 were judged to be radioactively contaminated thereby requiring Decontamination and Decommissioning (D and D) after shutdown. To enable projection of D and D timing for each of the 496 facilities, a plant shutdown schedule was developed. A 5-year ''cool-down'' period was added to the highly contaminated facilities to allow radioactive decay resulting in a reduction of cost, waste volume, and radiation exposure. D and D of all facilities is projected to be completed in FY 2045. Since essentially all of the plant facilities are scheduled to operate past FY 2000, only seventy-four of the 496 facilities are projected to be decommissioned prior to FY 2000. These facilities include currently excessed facilities and those scheduled for shutdown in the near future - seepage basins, HWCTR, R-Reactor, high level waste tanks, etc. The type of D and D chosen is the factor having the most significant effect on D and D costs and waste volumes. The two types of final D and D are Entombment and Dismantlement. Dismantlement can increase costs and waste volumes by a factor of 2 to 100 compared to Entombment. This point should be kept in mind when reviewing this scoping study as approximately 75% of the projects are estimated based upon the less costly Entombment option. The D and D estimates for the 496 facilities are summarized by plant area in Table 3 and by custodian group (Program/General Department) in Table 4. The total estimated D and D cost in constant FY 1986 dollars is approximately $800,000,000, with total solid waste volumes of 5,000,000 and 170,000 cubic feet, for low level waste (LLW) and transuranic waste (TRU), respectively. A 6% annual escalation factor increases the total project costs of 800,000,000, FY 1986 dollars to 7 billion dollars. 27 refs

  11. Study for reducing radioactive solid waste at ITER decommissioning period

    Energy Technology Data Exchange (ETDEWEB)

    Sato, Shinichi; Araki, Masanori; Ohmori, Junji; Ohno, Isamu; Sato, Satoshi; Yamauchi, Michinori; Nishitani, Takeo [Japan Atomic Energy Research Inst., Naka, Ibaraki (Japan). Naka Fusion Research Establishment

    2002-11-01

    It is one of the foremost goals for ITER to demonstrate the attractiveness with regard to safety and environmental potential. This implies that the radioactive materials and waste at decommissioning phase should carefully be treated with prescribed regulations. As possible activities during the Coordinated Technical Activity (CTA), the authors have performed a feasibility study for searching the possibility of effective reduction in the activated level as reasonably achievable as possible by taking account of minimum material changes while keeping original design concept and structure. Major induced activation in ITER comes from activated nickel and cobalt so that it is effective for the major structural components to minimize their material contents. Employing less Ni and Co steel in place of high-Ni austenitic stainless steel for blanket shield block, vacuum vessel shield material and TF coil casing has been considered as one of the effective plans to reduce the activated materials at the decommissioning phase. In this study, two less-Ni austenitic stainless steels are evaluated; one is high-Mn austenitic stainless steel JK2 which is developing for jacket material of ITER CS coil and the other is SS204L/ASTM-XM-11 which is also high-Mn steel specified in the popular standards such as American Society of Testing and Material (ASTM). Based on the material changes, activation analyses have been performed to investigate the possibility of reducing radioactive wastes. As a most impressive result, at 40 years after the termination some of main components such as a TF coil casing will reach to the clearance level which is specified by IAEA, and most components will be categorized into extremely low level waste except for limited components. These results will give the appropriate short decommissioning period that is assumed to start at 100 years after the termination in the original design. (author)

  12. Case study for a fit-to-purpose regulatory framework: the history and reasons for the evolution-in the French regulation regarding decommissioning

    International Nuclear Information System (INIS)

    Averous, J.; Chapalain, E.

    2005-01-01

    Full text: This paper exposes the regulatory approach for the safety of decommissioning in France, from an historical perspective. The first regulatory framework concerning decommissioning was introduced in the end of the 1980's and considered decommissioning as successive important modifications of the facility, which lead to multiple successive licenses. The first feedback from actual decommissioning projects lead the nuclear safety authority to reconsider the regulatory approach of decommissioning. The new approach privileges an integrated approach to the decommissioning projects, with an initial decommissioning license authorizing the complete project, and puts more weight on the responsibility of the licensee, fostering the organization of internal safety commissions which are allowed to authorize minor operations that do not put into question the global facility safety demonstration. This new regulatory approach was implemented in 2003 and new corresponding licensing procedures are already under way. It is thought that the new regulatory framework for decommissioning that has been introduced in 2003 will allow to regulate in a far more efficient way the decommissioning projects to come, while guarantying a high safety level, adapting the regulatory burden to the actual hazards, and allowing the licensee for the needed flexibility. Taking advantage of this new framework, licensees have already filed many decommissioning license applications, and decommissioning project licensing is currently one of the main tasks of the nuclear safety authority in France. Many such licenses, for all types of nuclear facilities, will be granted in the next few years. (authors)

  13. Nuclear decommissioning trusts: A case for convertible bonds

    International Nuclear Information System (INIS)

    Nichols, R.W.

    1992-01-01

    Asset-liability management is studied with special emphasis on application of the author's findings to the management of nuclear decommissioning trusts (NDTs). The trust themselves are investment vehicles established to accumulate and build funds to be used to defray future decommissioning costs. Decommissioning, in turn, is the process of dismantling the shell of a nuclear reactor and the surrounding concrete structures, followed by disposal of the radioactive material, the objective being to return the site to a greenfield state i.e. the site is freed up for unrestricted use. Unfortunately, the assets of NDTs are not so easily managed. The liability that the trusts have been established to fund is a highly uncertain moving target for which little historical data is available. This study first develops a framework for selecting portfolios when the investment objective is to invest against a future liability. The challenge then is to build an investment strategy around an uncertain liability, in the presence of taxes and miscellaneous portfolio constraints. The study then explores the viability of convertible bonds for liability-driven investment strategies because of the hybrid debt/equity nature of these instruments

  14. Topical Session on the Decommissioning and Dismantling Safety Case

    International Nuclear Information System (INIS)

    2002-01-01

    Set up by the Radioactive Waste Management Committee (RWMC), the WPDD brings together senior representatives of national organisations who have a broad overview of Decommissioning and Dismantling (D and D) issues through their work as regulators, implementers, R and D experts or policy makers. These include representatives from regulatory authorities, industrial decommissioners from the NEA Cooperative Programme on Exchange of Scientific and Technical Information on Nuclear Installation Decommissioning Projects (CPD), and cross-representation from the NEA Committee on Nuclear Regulatory Activities, the Committee on Radiation Protection and Public Health, and the RWMC. The EC is a member of the WPDD and the IAEA also participates. This ensures co-ordination amongst activities in these international programmes. Participation from civil society organisations is considered on a case by case basis, and has already taken place through the active involvement of the Group of Municipalities with Nuclear Installations at the first meeting of the WPDD At its second meeting, in Paris, 5-7 December 2001, the WPDD held two topical sessions on the D and D Safety Case and on the Management of Materials from D and D, respectively. This report documents the topical session on the safety case. The topical session was meant to provide an exchange of information and experience on the following issues: What topics should be included in a safety case? Of what should it consist? Is there sufficient and complete guidance nationally and internationally? How do practices differ internationally? Main boundary condition to this session was that it would deal with plants where spent fuel has been removed. Also the topical sessions was kept at a level that makes the most of the varied constituency of the WPDD. Namely, interface issues are important, and issue-identification and discussion was the immediate goal. There was less interest in examining areas where variability amongst national

  15. A study on the optimization of plant life extension and decommissioning for the improvement of economy in nuclear power plant

    Energy Technology Data Exchange (ETDEWEB)

    Shin, Jae In; Jung, K. J.; Chung, U. S.; Baik, S. T.; Park, S. K.; Lee, D. G.; Kim, H. R.; Park, B. Y

    2001-01-01

    Fundamental concepts on the life extension of the nuclear power plant and decommissioning optimization were established from the domestic abroad information and case analyses. Concerning the decommissioning of the nuclear power plant, the management according to decommissioning stages was analyzed by the investigation of the standard of the decommissioning(decontamination dismantling) regulation. Moreover, basics were set for the decommissioning of domestic nuclear power plants and research reactors from the analyses on the decommissioning technology and precedence.

  16. Safety case methodology for decommissioning of research reactors. Assessment of the long term impact of a flooding scenario

    International Nuclear Information System (INIS)

    Vladescu, G.; Banciu, O.

    1999-01-01

    The paper contains the assessment methodology of a Safety Case fuel decommissioning of research reactors, taking into account the international approach principles. The paper also includes the assessment of a flooding scenario for a decommissioned research reactor (stage 1 of decommissioning). The scenario presents the flooding of reactor basement, radionuclide migration through environment and long term radiological impact for public. (authors)

  17. Costs of Decommissioning Nuclear Power Plants

    International Nuclear Information System (INIS)

    Neri, Emilio; French, Amanda; Urso, Maria Elena; Deffrennes, Marc; Rothwell, Geoffrey; ); Rehak, Ivan; Weber, Inge; ); Carroll, Simon; Daniska, Vladislav

    2016-01-01

    While refurbishments for the long-term operation of nuclear power plants and for the lifetime extension of such plants have been widely pursued in recent years, the number of plants to be decommissioned is nonetheless expected to increase in future, particularly in the United States and Europe. It is thus important to understand the costs of decommissioning so as to develop coherent and cost-effective strategies, realistic cost estimates based on decommissioning plans from the outset of operations and mechanisms to ensure that future decommissioning expenses can be adequately covered. This study presents the results of an NEA review of the costs of decommissioning nuclear power plants and of overall funding practices adopted across NEA member countries. The study is based on the results of this NEA questionnaire, on actual decommissioning costs or estimates, and on plans for the establishment and management of decommissioning funds. Case studies are included to provide insight into decommissioning practices in a number of countries. (authors)

  18. Study on scenario evaluation methodology for decommissioning nuclear facilities using fuzzy logic

    International Nuclear Information System (INIS)

    Matsuhashi, Kazuya; Yanagihara, Satoshi

    2015-01-01

    Since there are many scenarios of the process from start to completion of a decommissioning project, it is important to study scenarios of decommissioning by evaluating such properties as safety, cost, and technology. An optimum scenario with the highest feasibility in accordance with the facility and environmental conditions should be selected on the basis of the results of the study. For analyzing a scenario of decommissioning, we prepared structured work packages by using the work breakdown structures (WBS) method together with qualitative evaluation of the technologies being applied to work packages located at the bottom (the third level) of the WBS. A calculation model was constructed to evaluate the feasibility of a scenario where fuzzy logic is applied to derive a score of technology performance and TOPSIS is applied for getting a feasibility grade of the scenario from technical performance scoring. As a case study, the model was applied to the debris removal scenario of Fukushima Daiichi Nuclear Power Plant to confirm its applicability. Two scenarios, underwater and in-air debris removal cases, were characterized by extracting the work packages with the lowest feasibility and by obtaining total average scores of the scenarios. It is confirmed that the methodology developed is useful for the scenario evaluation of decommissioning nuclear facilities. (author)

  19. Decommissioning nuclear power plants: a case for external funding

    International Nuclear Information System (INIS)

    Hendren, C.B.

    1987-01-01

    In deciding how to finance the decommissioning of nuclear power plants, there are five basic criteria for choosing between internal and external funding methods: (1) the desire for financial assurance, (2) the cost of the assurance, (3) the degree of equity in the recovery program, (4) the program's ability to respond to changes, and (5) the program's adaptability to different utilities. To fulfill its obligations to protect long-term public interests, the Missouri Public Service Commission decided it had to assure, to the maximum extent possible, that sufficient decommissioning funds were available when needed. For this reason, it chose the external funding method. In an external fund, the money currently collected from ratepayers to cover decommissioning costs is placed in an independent trust fund comprised of low-risk investments. The funds and the interest they accrue are available to the utility only at the time of decommissioning (and only for that purpose), thus assuring a certain amount of money will be on-hand to cover decommissioning costs as they arise. Such a fund may prove critical to the financial well-being of the utility, particularly if one considers that the utility would need additional generating facilities to replace the capacity lost through the retirement of its nuclear plant. 3 references

  20. Workshop on decommissioning

    International Nuclear Information System (INIS)

    Broden, K.

    2005-12-01

    A Nordic workshop on decommissioning of nuclear facilities was held at Risoe in Denmark September 13-15, 2005. The workshop was arranged by NKS in cooperation with the company Danish Decommissioning, DD, responsible for decommissioning of nuclear facilities at Risoe. Oral presentations were made within the following areas: International and national recommendations and requirements concerning decommissioning of nuclear facilities Authority experiences of decommissioning cases Decommissioning of nuclear facilities in Denmark Decommissioning of nuclear facilities in Sweden Plans for decommissioning of nuclear facilities in Norway Plans for decommissioning of nuclear facilities in Finland Decommissioning of nuclear facilities in German and the UK Decommissioning of nuclear facilities in the former Soviet Union Results from research and development A list with proposals for future work within NKS has been prepared based on results from group-work and discussions. The list contains strategic, economical and political issues, technical issues and issues regarding competence and communication. (au)

  1. A study on the decommissioning methods of nuclear facilities of North Korea

    International Nuclear Information System (INIS)

    Chung, U. S.; Park, J. H.; Park, S. K.; Hong, S. B.; Lee, G. W.

    2012-02-01

    For Korea, it is essential to participate in the decommissioning of North Korean nuclear facilities for Pu-based weapon program and to lead the project for the protection of the environments from the possible spread of nuclear contamination. Before, the studies for the verification of the North Korea nuclear facilities and for the technical preparation of the decommissioning of north Korea were conducted but the depth of the studies was not reached to the evaluation of the decommissioning project by the documentation of a decommissioning plan to the provision of the technical information to the policy decision makers. It is very helpful for understanding the characteristics of the decommissioning projects to formulate a possible dismantling scenario and to make a decommissioning plan. The cost and the periods estimated on the base of this scenario is more exact and the analysis for the selection of different policies will be possible

  2. Decommissioning of a nuclear facility: the Brazilian case

    International Nuclear Information System (INIS)

    Menezes, Regina M.; Deppe, Alzira L.; Nunes, Marcos E.C.; Cardoso, Eliezer M.; Nouailhetas, Y.; Mouco, Charles; Ferreira, Paulo R.; Matta, Luiz E.da

    1996-01-01

    The first decommissioning process of a nuclear facility in Brazil, has being taken place in Usina de Santo Amaro (USAM), located in Sao Paulo whose physical and chemical milling activities of the monazitic sands were interrupted in June 1992. Nowadays, materials and equipment generated from Minerals Physical Treatment and Rare Earths Separation Sectors, classified as low level radiation areas, are in final phase of dismantling, monitoring and release to the internal backyard of the facility or segregation in controlled areas. This decommissioning phase is considered as pilot for the verification of procedures, follow up of pieces and application of suitable radioprotection measures for the future dismantling of the Chemical Treatment of Monazite Sector, which will involve higher risks regarding radioprotection and safety aspects. The criteria of discharge of areas and equipment established by CNEN are conservative enough to assure that the contamination is not released to the environment. CNEN's activities conducted at the surveillance of works involving the dismantling and decontamination of materials and equipment verifying that they are in accordance with the requirements established by the Brazilian Commission of Nuclear Energy. (author)

  3. Innovative Integration of Decommissioning and Deactivation Program with Soil-Groundwater Clean Up Program Has Positive Results on Budget and Schedule: A Case Study

    International Nuclear Information System (INIS)

    Schappell, B; Rucker, G

    2007-01-01

    An innovative approach to integrate the activities of a decommissioning and deactivation program (D and D) with a soil-groundwater clean up program has had significant positive results saving both money and time at the Department of Energy's Savannah River Site. The accomplishments that have been achieved by the combining the two programs have been remarkable including significant cost savings, economies of scale for sampling and document generation, and alignment of common objectives. Because of the coordination of both activities area-wide ''end states'' can be formulated and be consistent with the customers' cleanup goals and federal regulations. This coordinates and aligns both the environmental clean up and D and D objectives because each must be addressed simultaneously and comprehensively. In this respect, resources from both organizations can be pooled to take advantage of the strengths of each. The new approach allows more efficient use of lean financial resources and optimizes workforce activities to attain the common objectives while being more cost effective, more protective of the environment, and optimizing the use existing resources

  4. Decommissioning of a RCRA Treatment, Storage, and Disposal Facility: A case study of the 216-A-29 ditch at the Hanford Site

    International Nuclear Information System (INIS)

    Smith, D.L.; Hayward, W.M.

    1991-09-01

    The 216-A-29 ditch is located in the central portion of the Hanford Site with Operable Unit 200-PO-5. The ditch is classified under the Resource Conservation and Recovery Act of 1976 as a Treatment, Storage, and Disposal (TSD) Facility and as such, is to be removed from service in support of the Hanford Federal Facility Agreement and Consent Order Tri-Party Agreement (Ecology et al. 1989) Milestone M-17-10, which states ''cease all liquid discharges to hazardous land disposal units unless such units have been clean closed in accordance with the Resource Conservation and Recovery Act of 1976''. The 216-A-29 ditch is one stream feeding the 216-B-3 Pond system, and its removal from service was necessary to support the closure strategy for the 216-B-3 Pond system. Interim stabilization of the 216-A-29 ditch is the first step required to comply with the Tri-Party Agreement (Ecology et al. 1989) and the eventual decommissioning of the entire B Pond system. Interim stabilization was required to maintain the 216-A-29 ditch in a stable configuration until closure actions have been determined and initiated. 4 refs., 3 figs

  5. Study on archive management for nuclear facility decommissioning projects

    International Nuclear Information System (INIS)

    Huang Ling; Gong Jing; Luo Ning; Liao Bing; Zhou Hao

    2011-01-01

    This paper introduces the main features and status of the archive management for nuclear facility decommissioning projects, and explores and discusses the countermeasures in its archive management. Taking the practice of the archive management system of a reactor decommissioning project as an example, the paper illustrates the establishment of archive management system for the nuclear facility decommissioning projects. The results show that the development of a systematic archive management principle and system for nuclear decommissioning projects and the construction of project archives for the whole process from the design to the decommissioning by digitalized archive management system are one effective route to improve the complete, accurate and systematic archiving of project documents, to promote the standardization and effectiveness of the archive management and to ensure the traceability of the nuclear facility decommissioning projects. (authors)

  6. Nuclear decommissioning planning, execution and international experience

    CERN Document Server

    2012-01-01

    A title that critically reviews the decommissioning and decontamination processes and technologies available for rehabilitating sites used for nuclear power generation and civilian nuclear facilities, from fundamental issues and best practices, to procedures and technology, and onto decommissioning and decontamination case studies.$bOnce a nuclear installation has reached the end of its safe and economical operational lifetime, the need for its decommissioning arises. Different strategies can be employed for nuclear decommissioning, based on the evaluation of particular hazards and their attendant risks, as well as on the analysis of costs of clean-up and waste management. This allows for decommissioning either soon after permanent shutdown, or perhaps a long time later, the latter course allowing for radioactivity levels to drop in any activated or contaminated components. It is crucial for clear processes and best practices to be applied in decommissioning such installations and sites, particular where any ...

  7. Decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    1975-01-01

    Present concepts on stages of, designing for and costs of decommissioning, together with criteria for site release, are described. Recent operations and studies and assessments in progress are summarized. Wastes from decommissioning are characterized

  8. TWRS privatization: Phase I monitoring well engineering study and decommissioning plan

    Energy Technology Data Exchange (ETDEWEB)

    Williams, B.A.

    1996-09-11

    This engineering study evaluates all well owners and users, the status or intended use of each well, regulatory programs, and any future well needs or special purpose use for wells within the TWRS Privatization Phase I demonstration area. Based on the evaluation, the study recommends retaining 11 of the 21 total wells within the demonstration area and decommissioning four wells prior to construction activities per the Well Decommissioning Plan (WHC-SD-EN-AP-161, Rev. 0, Appendix I). Six wells were previously decommissioned.

  9. Towards a safety case for the use of laser cutting in nuclear decommissioning

    International Nuclear Information System (INIS)

    Hilton, P.A.

    2014-01-01

    Some of the requirements in nuclear decommissioning include size reduction of contaminated containers, pipework and other structures manufactured from stainless and other steels. Size reduction is generally performed using mechanical saws or shears, with drawbacks of quick wear, significant applied force, difficult remote operation and addition to contaminated waste mass. The use of lasers for cutting within the context of nuclear decommissioning has been recently demonstrated by TWI and others. In this paper, aspects of drawing together a safety case for using laser beams for cutting in a nuclear decommissioning cell are discussed, via analysis of relevant purpose designed experimental data. Data presented includes assessment of the use of different focal length lenses and the power densities anticipated at distances of up to 3 m from the focal point, as well as beam effects on material behind the cutting zone. An assessment of anticipated material damage from stray beams or unintended exposure to laser light of surrounding items is also presented. Finally materials for effective screening against stray beams during the cutting process have been tested for effectiveness. (authors)

  10. Preliminary study on recycling of metallic waste from decommissioning of nuclear power plant for cask

    International Nuclear Information System (INIS)

    Ohe, Koichiro; Kato, Osamu; Saegusa, Toshiari

    1999-01-01

    Preliminary study was made on technology required to recycle of metallic waste from decommissioning for spent fuel storage cask and on quantity of the cask which can be produced by the metallic waste. The technical and institutional issues for the recycling were studied. The metallic waste from decommissioning may be technically used to a certain degree for manufacturing the casks. However, there were some technical issues to be solved. For example, the manufacturing factories should be established. The radioactive waste from the factories with radiation control should be handled and treated carefully. Quality of the cask should be properly controlled. The 'Clearance Levels' which allows to recycle decommissioning waste have been hardly enacted in Japan. Technical and economic evaluation on recycling of metallic waste from decommissioning for spent fuel storage cask should be conducted again after progress in recycling of radioactive waste of which radioactivity is below the 'Clearance Levels' in Japan. (author)

  11. Decommissioning standards

    International Nuclear Information System (INIS)

    Crofford, W.N.

    1980-01-01

    EPA has agreed to establish a series of environmental standards for the safe disposal of radioactive waste through participation in the Interagency Review Group on Nuclear Waste Management (IRG). One of the standards required under the IRG is the standard for decommissioning of radioactive contaminated sites, facilities, and materials. This standard is to be proposed by December 1980 and promulgated by December 1981. Several considerations are important in establishing these standards. This study includes discussions of some of these considerations and attempts to evaluate their relative importance. Items covered include: the form of the standards, timing for decommissioning, occupational radiation protection, costs and financial provisions. 4 refs

  12. Simulation studies for quantification of solid waste during decommissioning of nuclear reactors

    International Nuclear Information System (INIS)

    Sobhan Babu, K.; Gopalakrishnan, R.K.; Gupta, P.C.

    2007-01-01

    Decommissioning is the final phase in the lifecycle of a nuclear installation and in the area of occupational radiation protection, decommissioning constitute a challenge mainly due to the huge and complex radioactive waste generation. In the context of management and disposal of waste and reuse/recycle of usable materials during decommissioning of reactors, clearance levels for relevant radionuclides are of vital importance. During the process of decommissioning radionuclide-specific clearance levels allow the release of a major quantity of materials to the environment, without regulatory considerations. These levels may also be used to declare the usable materials for reuse or recycle. Assessment of activity concentration in huge quantities of material, for the purpose of clearance, is a challenge in decommissioning process. This paper describes the simulation studies being carried out for the design of a monitoring system for the estimation of activity concentration of the decommissioned materials, especially rubbles/concrete, using mathematical models. Several designs were studied using simulation and it was observed that for the estimation of very low levels of activity concentration, to satisfy the conditions of unrestricted releases, detection system using the principle of Emission Computed Tomography (ECT) is the best suitable method. (author)

  13. A study of a decommissioning activities classification structure for decommissioning of the project management of a nuclear power plant

    International Nuclear Information System (INIS)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Song, Chan Ho; Ha, Jei Hyun; Moon, Jei kwon

    2015-01-01

    Decommissioning activities and requirements that was established in the planning stage should be organized systematically in the course of dismantling the NPP. The work breakdown structure is essential to ensuring that all the project scope is identified, estimated and executed. The project manager needs to ensure that a WBS is established early in the project and maintained throughout the project life cycle. A project management system is ongoing under the circumstance of having no experience dismantling the NPP. The system related to the NPP decommissioning should have technical criteria as well as regulatory requirements in the full scale of decommissioning stage. In the dismantling stage, decommissioning plan document should include the results of radiation/radioactivity characterization, evaluation of the amount of dismantled waste, calculation of the expose dose rate, evaluation of decommissioning cost and schedule after shutdown

  14. A study of a decommissioning activities classification structure for decommissioning of the project management of a nuclear power plant

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Song, Chan Ho; Ha, Jei Hyun; Moon, Jei kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    Decommissioning activities and requirements that was established in the planning stage should be organized systematically in the course of dismantling the NPP. The work breakdown structure is essential to ensuring that all the project scope is identified, estimated and executed. The project manager needs to ensure that a WBS is established early in the project and maintained throughout the project life cycle. A project management system is ongoing under the circumstance of having no experience dismantling the NPP. The system related to the NPP decommissioning should have technical criteria as well as regulatory requirements in the full scale of decommissioning stage. In the dismantling stage, decommissioning plan document should include the results of radiation/radioactivity characterization, evaluation of the amount of dismantled waste, calculation of the expose dose rate, evaluation of decommissioning cost and schedule after shutdown.

  15. Decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Lunning, W.H.

    1977-01-01

    Collaborative studies are in progress in the U.K. between the U.K.A.E.A., the Generating Boards and other outside bodies, to identify the development issues and practical aspects of decommissioning redundant nuclear facilities. The various types of U.K.A.E.A. experimental reactors (D.F.R., W.A.G.R , S.G.H.W.R.) in support of the nuclear power development programme, together with the currently operating commercial 26 Magnox reactors in 11 stations, totalling some 5 GW will be retired before the end of the century and attention is focussed on these. The actual timing of withdrawal from service will be dictated by development programme requirements in the case of experimental reactors and by commercial and technical considerations in the case of electricity production reactors. Decommissioning studies have so far been confined to technical appraisals including the sequence logic of achieving specific objectives and are based on the generally accepted three stage progression. Stage 1, which is essentially a defuelling and coolant removal operation, is an interim phase. Stage 2 is a storage situation, the duration of which will be influenced by environmental pressures or economic factors including the re-use of existing sites. Stage 3, which implies removal of all active and non-active waste material and returning the site to general use, must be the ultimate objective. The engineering features and the radioactive inventory of the system must be assessed in detail to avoid personnel or environmental hazards during Stage 2. These factors will also influence decisions on the degree of Stage 2 decommissioning and its duration, bearing in mind that for Stage 3 activation may govern the waste disposal route and the associated radiation man-rem exposure during dismantling. Ideally, planning for decommissioning should be considered at the design stage of the facility. An objective of present studies is to identify features which would assist decommissioning of future systems

  16. A study on the applicability for primary system decontamination through analysis on NPP decommission technology and international experience

    Energy Technology Data Exchange (ETDEWEB)

    Song, Jong Soon; Jung, Min Young; Lee, Sang Heon [Chosun University, Gwangju (Korea, Republic of)

    2016-03-15

    Decontamination is one of the most important technologies for the decommissioning of NPP. The purpose of decontamination is to reduce the Risk of exposure of the decommissioning workers, and to recycle parts of the plant components. Currently, there is a lack of data on the efficiency of the decontamination technologies for decommissioning. In most cases, the local radiation level can be lowered below a regulatory limitation by decontamination. Therefore, more efficient decontamination technology must be continuously developed. This work describes the practical experiences in the United States and the European countries for NPP decommissioning using these decontamination technologies. When the decommissioning of domestic nuclear power plant is planned and implemented, this work will be helpful as a reference of previous cases.

  17. Training for decommissioning

    International Nuclear Information System (INIS)

    Dietzold, A.

    2009-01-01

    Plants entering decommissioning face many challenges One of the most important is the challenge of training for decommissioning This is important because: The facility operators and management have spent many years successfully operating the facility; The facility management arrangements are geared to operation; Decommissioning will include non-nuclear specialists and other stakeholders; Other skills are needed to decommission successfully. UKAEA has decommissioned many facilities at its sites in Dounreay, Windscale, Harwell and Winfrith in the UK. We have faced all of the challenges previously described and have developed many training methods for ensuring the challenges are met safely and effectively. We have developed courses for specialised skills such as safety cases which can be deployed to support any decommissioning. (author)

  18. Comparative analysis of the Oskarshamn 3 and Barsebaeck site decommissioning studies

    International Nuclear Information System (INIS)

    Hansson, Bertil; Joensson, Lars-Olof

    2009-01-01

    Several projects concerning the decommissioning of different types of nuclear facilities have shown that technical methods and equipment are available today for safe dismantling of nuclear facilities of any type or size. However, comparison of individual cost estimates for specific facilities exhibit relatively large variations, and several studies have tried to identify the reasons for these variations. Analysis has shown that decommissioning cost estimates vary depending on a number of factors, including: the boundary conditions and strategy chosen; the cost items taken into account; the origin of the cost estimate; the methodology applied; the political-administrative framework; and the way contingencies are included. In this study, a comparison has been made between two decommissioning studies in the same country, with more or less same decommissioning schedule and with similar overall ideas on cost estimates. However, the two studies had from the start a different focus and different objectives. One study is intended as a reference study for all BWRs in Sweden, while the other focuses on a full site decommissioning. Furthermore, one of the studies is based on direct dismantling and the other on deferred dismantling. A great deal of work therefore had to be devoted in the present study to giving the studies comparable structures and boundary conditions using the OECD/NEA cost estimate structure. The boundary conditions in each of the studies have been thoroughly evaluated qualitatively and quantitatively, and the differences have been explained. In the end, values have been set in the quantitative analysis to verify that the studies could be compared, within the accuracy of what is defined in the industry as a 'budgetary estimate'. Differences still exist relating to what has been included in the studies and to the decommissioning plans and the resulting inventory from site characterization. Such differences must be accepted as long as it is clear what is

  19. Comparative analysis of the Oskarshamn 3 and Barsebaeck site decommissioning studies

    Energy Technology Data Exchange (ETDEWEB)

    Hansson, Bertil (Bewon, Loeddekoepinge (Sweden)); Joensson, Lars-Olof (Barsebaeck Kraft AB, Loeddekoepinge (Sweden))

    2009-01-15

    Several projects concerning the decommissioning of different types of nuclear facilities have shown that technical methods and equipment are available today for safe dismantling of nuclear facilities of any type or size. However, comparison of individual cost estimates for specific facilities exhibit relatively large variations, and several studies have tried to identify the reasons for these variations. Analysis has shown that decommissioning cost estimates vary depending on a number of factors, including: the boundary conditions and strategy chosen; the cost items taken into account; the origin of the cost estimate; the methodology applied; the political-administrative framework; and the way contingencies are included. In this study, a comparison has been made between two decommissioning studies in the same country, with more or less same decommissioning schedule and with similar overall ideas on cost estimates. However, the two studies had from the start a different focus and different objectives. One study is intended as a reference study for all BWRs in Sweden, while the other focuses on a full site decommissioning. Furthermore, one of the studies is based on direct dismantling and the other on deferred dismantling. A great deal of work therefore had to be devoted in the present study to giving the studies comparable structures and boundary conditions using the OECD/NEA cost estimate structure. The boundary conditions in each of the studies have been thoroughly evaluated qualitatively and quantitatively, and the differences have been explained. In the end, values have been set in the quantitative analysis to verify that the studies could be compared, within the accuracy of what is defined in the industry as a 'budgetary estimate'. Differences still exist relating to what has been included in the studies and to the decommissioning plans and the resulting inventory from site characterization. Such differences must be accepted as long as it is clear

  20. In-core power sharing and fuel requirement study for a decommissioning Boiling Water Reactor using the linear reactivity model

    International Nuclear Information System (INIS)

    Chen, Chung-Yuan; Tung, Wu-Hsiung; Yaur, Shung-Jung; Kuo, Weng-Sheng

    2014-01-01

    Highlights: • Linear reactivity model (LRM) was modified and applied to Boiling Water Reactor. • The power sharing and fuel requirement study of the last cycle and two cycles before decommissioning was implemented. • The loading pattern design concept for the cycles before decommissioning is carried out. - Abstract: A study of in-core power sharing and fuel requirement for a decommissioning BWR (Boiling Water Reactor) was carried out using the linear reactivity model (LRM). The power sharing of each fuel batch was taken as an independent variable, and the related parameters were set and modified to simulate actual cases. Optimizations of the last cycle and two cycles before decommissioning were both implemented; in the last-one-cycle optimization, a single cycle optimization was carried out with different upper limits of fuel batch power, whereas, in the two-cycle optimization, two cycles were optimized with different cycle lengths, along with two different optimization approaches which are the simultaneous optimization of two cycles (MO) and two successive single-cycle optimizations (SO). The results of the last-one-cycle optimization show that it is better to increase the fresh fuel power and decrease the thrice-burnt fuel power as much as possible. It also shows that relaxing the power limit is good to the fresh fuel requirement which will be reduced under lower power limit. On the other hand, the results of the last-two-cycle (cycle N-1 and N) optimization show that the MO is better than SO, and the power of fresh fuel batch should be decreased in cycle N-1 to save its energy for the next cycle. The results of the single-cycle optimization are found to be the same as that in cycle N of the multi-cycle optimization. Besides that, under the same total energy requirement of two cycles, a long-short distribution of cycle length design can save more fresh fuel

  1. Decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    Harmon, K.M.; Jenkins, C.E.; Waite, D.A.; Brooksbank, R.E.; Lunis, B.C.; Nemec, J.F.

    1976-01-01

    This paper describes the currently accepted alternatives for decommissioning retired light water reactor fuel cycle facilities and the current state of decommissioning technology. Three alternatives are recognized: Protective Storage; Entombment; and Dismantling. Application of these alternatives to the following types of facilities is briefly described: light water reactors; fuel reprocessing plants, and mixed oxide fuel fabrication plants. Brief descriptions are given of decommissioning operations and results at a number of sites, and recent studies of the future decommissioning of prototype fuel cycle facilities are reviewed. An overview is provided of the types of operations performed and tools used in common decontamination and decommissioning techniques and needs for improved technology are suggested. Planning for decommissioning a nuclear facility is dependent upon the maximum permitted levels of residual radioactive contamination. Proposed guides and recently developed methodology for development of site release criteria are reviewed. 21 fig, 32 references

  2. Research reactor back-end options - decommissioning: a necessary consideration

    International Nuclear Information System (INIS)

    England, M.R.; Parry, D.R.; Smith, C.

    1998-01-01

    Decommissioning is a challenge, which all radioactive site licensees eventually need to face and research reactors are no exception. BNFL has completed numerous major decommissioning projects at its own operational sites and has undertaken similar works at customers' sites including the decommissioning of the Universities Research Reactor (URR), Risley and the ICI TRIGA 1-Mk I Reactor at Billingham. Based on the execution of such projects BNFL has gained an understanding of the variety of customer requirements and the effectiveness of specific decommissioning techniques for research reactors. This paper addresses factors to be considered when reviewing the way forward following shut down and how these affect the final decisions for fuel management and the extent of decommissioning. Case studies are described from BNFL's recent experience decommissioning both the URR and ICI TRIGA reactors. (author)

  3. Workshop on decommissioning; Seminarium om avveckling

    Energy Technology Data Exchange (ETDEWEB)

    Broden, K. (ed.)

    2005-12-15

    A Nordic workshop on decommissioning of nuclear facilities was held at Risoe in Denmark September 13-15, 2005. The workshop was arranged by NKS in cooperation with the company Danish Decommissioning, DD, responsible for decommissioning of nuclear facilities at Risoe. Oral presentations were made within the following areas: International and national recommendations and requirements concerning decommissioning of nuclear facilities Authority experiences of decommissioning cases Decommissioning of nuclear facilities in Denmark Decommissioning of nuclear facilities in Sweden Plans for decommissioning of nuclear facilities in Norway Plans for decommissioning of nuclear facilities in Finland Decommissioning of nuclear facilities in German and the UK Decommissioning of nuclear facilities in the former Soviet Union Results from research and development A list with proposals for future work within NKS has been prepared based on results from group-work and discussions. The list contains strategic, economical and political issues, technical issues and issues regarding competence and communication. (au)

  4. Guide for International Peer Reviews of Decommissioning Cost Studies for Nuclear Facilities

    International Nuclear Information System (INIS)

    LaGuardia, Thomas S.; Pescatore, Claudio; )

    2014-01-01

    Peer reviews are a standard co-operative OECD working tool that offer member countries a framework to compare experiences and examine best practices in a host of areas. The OECD Nuclear Energy Agency (NEA) has developed a proven methodology for conducting peer reviews in radioactive waste management and nuclear R and D. Using this methodology, the NEA Radioactive Waste Management Committee's Working Party on Decommissioning and Dismantling (WPDD) developed the present guide as a framework for decommissioning cost reviewers and reviewees to prepare for and conduct international peer reviews of decommissioning cost estimate studies for nuclear facilities. It includes checklists that will help national programmes or relevant organisations to assess and improve decommissioning cost estimate practices in the future. This guide will act as the NEA reference for conducting such international peer reviews. The remainder of this guide is divided into eight chapters. Chapter 2 describes gathering the cost estimate study and underpinning documents, reviewing the study and writing a final report. Chapter 3 provides a detailed checklist approach for the review of the cost study report. Chapter 4 provides checklists to assist in reviewing benchmarked information. Chapter 5 provides comments on the approach and recommendations for use of this guide. Chapters 6 and 7 provide the background material used in developing this guide and Chapter 8 provides a list of the abbreviations and acronyms used in this guide

  5. Study on the Operating Strategy of HVAC Systems for Nuclear Decommissioning Plant

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Sung-hwan; Han, Sung-heum; Lee, Jae-gon [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    According as Kori nuclear power plant unit 1 was determined to be defueled in 2017, various studies on nuclear plant decommissioning have been performed. In nuclear decommissioning plant, HVAC systems with large fan and electric coil have to be operated for long periods of time to support various types of work from defueled phase to final dismantling phase. So, in view of safety and utility costs, their overall operating strategy need to be established prior to defueled phase. This study presents HVAC system operating strategy at each decommissioning phase, that is, defueled plant operating phase, SSCs(systems, structures, components) decontamination and dismantling phases. In defueled plant operating phase, all fuel assemblies in reactor vessel are transferred to spent fuel pool(SFP) permanently. In defueled plant operation phase, reduction of the operating system trains is more practicable than the introduction of new HVAC components with reduced capacity. And, based on the result of the accident analyses for this phase, HVAC design bases such as MCR habitability requirement can be mitigated. According to these results, associated SSCs also can be downgraded. In similar approach, at each phase of plant decommissioning, proper inside design conditions and operating strategies should be re-established.

  6. Technical survey of decommissioning of commercial power reactors

    International Nuclear Information System (INIS)

    Nakamura, Masahide

    2003-01-01

    The technical survey of decommissioning of commercial power reactors had been carried out from 1982 to 2003. The investigation items are scenarios, procedures, simplification and recycling. On the scenarios, the case studies on the decommissioning steps (1983 to 1984), evaluation of the prior conditions of case studies (1994 to 1998), evaluation of rationalization of the scenarios of decommissioning steps (1999 to 2001) and evaluation of the effects of investigation of clearance level (1999 to 2002) are described. Procedures (1985 to 1996) and simplification (1985 to 1987) of decommissioning are investigated. On the recycling, survey on recycle of waste produced by the decommissioning step (1985 to 1993) and recycle of demolition waste (1997 to 2002) are reported. Recycle of radioactive waste has to be controlled under lows. (S.Y.)

  7. The development of the strategy and plan for the decommissioning and abandonment of 36'' offshore oil export pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Richard J. [PIMS of London Ltd, London, (United Kingdom); Galvez Reyes, Marco Antonio [PEMEX Refinacion, Veracruz, (Mexico)

    2010-07-01

    The decommissioning and abandonment of platforms and pipelines are big challenges for the pipeline industry. This paper presents a review of the decommissioning and abandonment processes based on a study case, the Rabon Grande pipeline system. First, the applicable international codes, standards and regulations associated with the decommissioning of pipelines are discussed. Next, this paper presents a review of the decommissioning and abandonment options and considerations available for the study case. The Rabon Grande pipeline system, which was shut down and isolated in 1990 pending decommissioning, is used as an example of applying decommissioning and abandonment best practice and establishing a realistic scope of work. A decommissioning plan is developed in light of these previous studies, followed by an environmental impact assessment. It is found that contrary to what was done in the case of the Rabon Grande pipeline, when a pipeline is to be shutdown, the best practice methodology is to temporally or fully decommission the system as soon as possible.

  8. Guidelines of Decommissioning Schedule Establishment

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Jae Yong; Yun, Taesik; Kim, Younggook; Kim, Hee-Geun [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning has recently become an issue highlighted in Korea due to the Permanent Shutdown (PS) of Kori-1 plant. Since Korea Hydro and Nuclear Power (KHNP) Company decided the PS of Kori-1 instead of further continued operation, Kori-1 will be the first decommissioning plant of the commercial reactors in Korea. Korean regulatory authority demands Initial Decommissioning Plan (IDP) for all the plants in operation and under construction. In addition, decommissioning should be considered for the completion of the life cycle of NPPs. To date, Korea has no experience regarding decommissioning of the commercial reactor and a lot of uncertainties will be expected due to its site-specific factors. However, optimized decommissioning process schedule must be indispensable in the safety and economic efficiency of the project. Differed from USA, Korea has no experience and know-hows of the operation and site management for decommissioning. Hence, in Korea, establishment of decommissioning schedule has to give more weight to safety than precedent cases. More economical and rational schedule will be composed by collecting and analyzing the experience data and site-specific data and information as the decommissioning progresses. In a long-range outlook, KHNP having capability of NPP decommissioning will try to decommissioning business in Korea and foreign countries.

  9. Decommissioning Handbook

    International Nuclear Information System (INIS)

    Cusack, J.G.; Dalfonso, P.H.; Lenyk, R.G.

    1994-01-01

    The Decommissioning Handbook provides technical guidance on conducting decommissioning projects. Information presented ranges from planning logic, regulations affecting decommissioning, technology discussion, health and safety requirements, an developing a cost estimate. The major focus of the handbook are the technologies -- decontamination technologies, waste treatment, dismantling/segmenting/demolition, and remote operations. Over 90 technologies are discussed in the handbook providing descriptions, applications, and advantages/disadvantages. The handbook was prepared to provide a compendium of available or potentially available technologies in order to aid the planner in meeting the specific needs of each decommissioning project. Other subjects presented in the Decommissioning Handbook include the decommissioning plan, characterization, final project configuration based planning, environmental protection, and packaging/transportation. These discussions are presented to complement the technologies presented in the handbook

  10. Current studies on the decommissioning materials recycling at Japan Atomic Energy Research Institute

    International Nuclear Information System (INIS)

    Fujiki, K.; Nakamura, H.

    1993-01-01

    Rational treatment of a large volume of solid wastes resulting from the reactor dismantling is a key to success to carry out the decommissioning smoothly. From this viewpoint, the Japan Atomic Energy Research Institute (JAERI) has been conducting development of the recycling technology for metal waste and an investigation study on the rational recycling system for the dismantling wastes recycling. With respect to the development of the recycling technology, series of melting tests using non-contaminated metals, metal waste dismantled from JPDR or imitated waste using radioisotopes have been conducted. The basic characteristics of the radionuclides transport behavior during the melting have been understood. In the investigation study on the rational recycling system, a scenario of recycling the wastes was developed based on the amount of waste arising from decommissioning nuclear power plants, and necessary processing facilities were examined, and safety and economy of the process were evaluated

  11. The Canadian Nuclear Safety Commission regulatory process for decommissioning a uranium mining facility

    International Nuclear Information System (INIS)

    Scissons, K.; Schryer, D.M.; Goulden, W.; Natomagan, C.

    2002-01-01

    The Canadian Nuclear Safety Commission (CNSC) regulates uranium mining in Canada. The CNSC regulatory process requires that a licence applicant plan for and commit to future decommissioning before irrevocable decisions are made, and throughout the life of a uranium mine. These requirements include conceptual decommissioning plans and the provision of financial assurances to ensure the availability of funds for decommissioning activities. When an application for decommissioning is submitted to the CNSC, an environmental assessment is required prior to initiating the licensing process. A case study is presented for COGEMA Resources Inc. (COGEMA), who is entering the decommissioning phase with the CNSC for the Cluff Lake uranium mine. As part of the licensing process, CNSC multidisciplinary staff assesses the decommissioning plan, associated costs, and the environmental assessment. When the CNSC is satisfied that all of its requirements are met, a decommissioning licence may be issued. (author)

  12. Decommissioning Handbook

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    The Decommissioning Handbook is a technical guide for the decommissioning of nuclear facilities. The decommissioning of a nuclear facility involves the removal of the radioactive and, for practical reasons, hazardous materials to enable the facility to be released and not represent a further risk to human health and the environment. This handbook identifies and technologies and techniques that will accomplish these objectives. The emphasis in this handbook is on characterization; waste treatment; decontamination; dismantling, segmenting, demolition; and remote technologies. Other aspects that are discussed in some detail include the regulations governing decommissioning, worker and environmental protection, and packaging and transportation of the waste materials. The handbook describes in general terms the overall decommissioning project, including planning, cost estimating, and operating practices that would ease preparation of the Decommissioning Plan and the decommissioning itself. The reader is referred to other documents for more detailed information. This Decommissioning Handbook has been prepared by Enserch Environmental Corporation for the US Department of Energy and is a complete restructuring of the original handbook developed in 1980 by Nuclear Energy Services. The significant changes between the two documents are the addition of current and the deletion of obsolete technologies and the addition of chapters on project planning and the Decommissioning Plan, regulatory requirements, characterization, remote technology, and packaging and transportation of the waste materials.

  13. Technical support to the social cost study of Ignalina NPP decommissioning

    International Nuclear Information System (INIS)

    Vitkiene, E.

    2001-01-01

    Description of Phare project on assessment of social cost related with decommissioning of unit 1 of Ignalina NPP is presented. This is the first project of social guarantees in Visaginas financed by European Commission Project will develop pilot studies aimed at encouraging small and medium size business in Visaginas, creating new jobs, employment of young people. The project will also consult about the activities of the said projects, inform the community about the things being done to mitigate social impact

  14. Study on the financing mechanism and management for decommissioning of nuclear installations in Malaysia

    International Nuclear Information System (INIS)

    Saleh, Lydia Ilaiza; Ryong, Kim Tae

    2015-01-01

    The whole cycle of the decommissioning process development of repository requires the relevant bodies to have a financial system to ensure that it has sufficient funds for its whole life cycle (over periods of many decades). Therefore, the financing mechanism and management system shall respect the following status: the national position, institutional and legislative environment, technical capabilities, the waste origin, ownership, characteristics and inventories. The main objective of the studies is to focus on the cost considerations, alternative funding managements and mechanisms, technical and non-technical factors that may affect the repository life-cycle costs. As a conclusion, the outcomes of this paper is to make a good recommendation and could be applied to the national planners, regulatory body, engineers, or the managers, to form a financial management plan for the decommissioning of the Nuclear Installation

  15. Study on the financing mechanism and management for decommissioning of nuclear installations in Malaysia

    Energy Technology Data Exchange (ETDEWEB)

    Saleh, Lydia Ilaiza, E-mail: lydiailaiza@gmail.com; Ryong, Kim Tae [KEPCO International Nuclear Graduate School (KINGS) 658-91 Haemaji-ro, Seosaeng-myeon, Ulju-gun, Ulsan 689-882 (Korea, Republic of)

    2015-04-29

    The whole cycle of the decommissioning process development of repository requires the relevant bodies to have a financial system to ensure that it has sufficient funds for its whole life cycle (over periods of many decades). Therefore, the financing mechanism and management system shall respect the following status: the national position, institutional and legislative environment, technical capabilities, the waste origin, ownership, characteristics and inventories. The main objective of the studies is to focus on the cost considerations, alternative funding managements and mechanisms, technical and non-technical factors that may affect the repository life-cycle costs. As a conclusion, the outcomes of this paper is to make a good recommendation and could be applied to the national planners, regulatory body, engineers, or the managers, to form a financial management plan for the decommissioning of the Nuclear Installation.

  16. Investigations on the decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Goertz, R.; Bastek, H.; Doerge, W.; Kruschel, K.P.

    1985-01-01

    The study discusses and evaluates safety and licensing related aspects associated with the decommissioning of nuclear power plants. Important decommissioning projects and experiences with relevance to decommissioning are analyzed. Recent developments in the field of decommissioning techniques with the potential of reducing the occupational dose to decommissioning workers are described and their range of application is discussed. The radiological consequences of the recycling of scrap metal arising during decommissioning are assessed. The results may be used to evaluate present licensing practices and may be useful for future licensing procedures. Finally the environmental impact of radionuclide release via air and water pathways associated with decommissioning activities is estimated. (orig.) [de

  17. Safety Assessment for Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-06-15

    In the past few decades, international guidance has been developed on methods for assessing the safety of predisposal and disposal facilities for radioactive waste. More recently, it has been recognized that there is also a need for specific guidance on safety assessment in the context of decommissioning nuclear facilities. The importance of safety during decommissioning was highlighted at the International Conference on Safe Decommissioning for Nuclear Activities held in Berlin in 2002 and at the First Review Meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management in 2003. At its June 2004 meeting, the Board of Governors of the IAEA approved the International Action Plan on Decommissioning of Nuclear Facilities (GOV/2004/40), which called on the IAEA to: ''establish a forum for the sharing and exchange of national information and experience on the application of safety assessment in the context of decommissioning and provide a means to convey this information to other interested parties, also drawing on the work of other international organizations in this area''. In response, in November 2004, the IAEA launched the international project Evaluation and Demonstration of Safety for Decommissioning of Facilities Using Radioactive Material (DeSa) with the following objectives: -To develop a harmonized approach to safety assessment and to define the elements of safety assessment for decommissioning, including the application of a graded approach; -To investigate the practical applicability of the methodology and performance of safety assessments for the decommissioning of various types of facility through a selected number of test cases; -To investigate approaches for the review of safety assessments for decommissioning activities and the development of a regulatory approach for reviewing safety assessments for decommissioning activities and as a basis for regulatory decision making; -To provide a forum

  18. Irradiated graphite studies prior to decommissioning of G1, G2 and G3 reactors

    International Nuclear Information System (INIS)

    Bonal, J.P.; Vistoli, J.Ph.; Combes, C.

    2005-01-01

    G1 (46 MW th ), G2 (250 MW th ) and G3 (250 MW th ) are the first French plutonium production reactors owned by CEA (Commissariat a l'Energie Atomique). They started to be operated in 1956 (G1), 1959 (G2) and 1960 (G3); their final shutdown occurred in 1968, 1980 and 1984 respectively. Each reactor used about 1200 tons of graphite as moderator, moreover in G2 and G3, a 95 tons graphite wall is used to shield the rear side concrete from neutron irradiation. G1 is an air cooled reactor operated at a graphite temperature ranging from 30 C to 230 C; G2 and G3 are CO 2 cooled reactors and during operation the graphite temperature is higher (140 C to 400 C). These reactors are now partly decommissioned, but the graphite stacks are still inside the reactors. The graphite core radioactivity has decreased enough so that a full decommissioning stage may be considered. Conceming this decommissioning, the studies reported here are: (i) stored energy in graphite, (ii) graphite radioactivity measurements, (iii) leaching of radionuclide ( 14 C, 36 Cl, 63 Ni, 60 Co, 3 H) from graphite, (iv) chlorine diffusion through graphite. (authors)

  19. Establishment the code for prediction of waste volume on NPP decommissioning

    International Nuclear Information System (INIS)

    Cho, W. H.; Park, S. K.; Choi, Y. D.; Kim, I. S.; Moon, J. K.

    2013-01-01

    -2 and developed DEMOS(DEcommissioning MOdeling System) and DEPES(DEcommissioning Process Establish System) using these data. These systems may be able to help to establish decommissioning strategy of nuclear power plant. We tried to apply research reactor data to OPR-1000 which is commercial nuclear power plant. But code for research reactor was not consistent when applying to nuclear power plant. The decommissioning activity of nuclear power plant is basically performed by the unit facility or room. In order to apply research reactor data, each WBS code is needed to apply to the object of each facility. This means that one FAC code may have several WBS codes. However, current codes in DECOMMIS are hard to map WBS code to FAC code one by one, and are specialized to research reactor. So it is difficult to apply to nuclear power plant directly. In order to solve this problem, the common code that can be adapted to commercial nuclear power plant as well as to research reactor is required. It may be inferred from the mapping data in the case of mismatching, or it can be applied with some modifications in the case of similar facility. In this paper, the establishment method of the code which uses the research reactor data in decommissioning project of nuclear power plant was studied. Method for prediction of the decommissioning waste volume was discussed on the basis of the domestic nuclear power plant, OPR-1000. Decommissioning experience is very important to apply to the estimation of decommissioning waste volume. So method for the estimation of decommissioning waste volume using common code that link OPR-1000 and KRR-2 was suggested. This research result will be helpful to reliable estimation of decommissioning waste volume and further estimation of the decommissioning cost and establishment of decommissioning strategies

  20. A nationwide modelling approach to decommissioning - 16182

    International Nuclear Information System (INIS)

    Kelly, Bernard; Lowe, Andy; Mort, Paul

    2009-01-01

    In this paper we describe a proposed UK national approach to modelling decommissioning. For the first time, we shall have an insight into optimizing the safety and efficiency of a national decommissioning strategy. To do this we use the General Case Integrated Waste Algorithm (GIA), a universal model of decommissioning nuclear plant, power plant, waste arisings and the associated knowledge capture. The model scales from individual items of plant through cells, groups of cells, buildings, whole sites and then on up to a national scale. We describe the national vision for GIA which can be broken down into three levels: 1) the capture of the chronological order of activities that an experienced decommissioner would use to decommission any nuclear facility anywhere in the world - this is Level 1 of GIA; 2) the construction of an Operational Research (OR) model based on Level 1 to allow rapid what if scenarios to be tested quickly (Level 2); 3) the construction of a state of the art knowledge capture capability that allows future generations to learn from our current decommissioning experience (Level 3). We show the progress to date in developing GIA in levels 1 and 2. As part of level 1, GIA has assisted in the development of an IMechE professional decommissioning qualification. Furthermore, we describe GIA as the basis of a UK-Owned database of decommissioning norms for such things as costs, productivity, durations etc. From level 2, we report on a pilot study that has successfully tested the basic principles for the OR numerical simulation of the algorithm. We then highlight the advantages of applying the OR modelling approach nationally. In essence, a series of 'what if...' scenarios can be tested that will improve the safety and efficiency of decommissioning. (authors)

  1. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Anon.

    1987-01-01

    The paper on nuclear decommissioning was presented by Dr H. Lawton to a meeting of the British Nuclear Energy Society and Institution of Nuclear Engineers, 1986. The decommissioning work currently being undertaken on the Windscale advanced gas cooled reactor (WAGR) is briefly described, along with projects in other countries, development work associated with the WAGR operation and costs. (U.K.)

  2. A study on the influence of the regulatory requirements of a nuclear facility during decommissioning activities

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Park, Kook Nam; Hong, Yun Jeong; Park, Jang Jin; Choi, Jong Won [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    The preliminary decommissioning plan should be written with various chapters such as a radiological characterization, a decommissioning strategy and methods, a design for decommissioning usability, a safety evaluation, decontamination and dismantling activities, radioactive waste management, an environmental effect evaluation, and fire protection. The process requirements of the decommissioning project and the technical requirements and technical criteria should comply with regulatory requirements when dismantling of a nuclear facility. The requirements related to safety in the dismantling of a nuclear facility refer to the IAEA safety serious. The present paper indicates that a decommissioning design and plan, dismantling activities, and a decommissioning project will be influenced by the decommissioning regulatory requirements when dismantling of a nuclear facility. We hereby paved the way to find the effect of the regulatory requirements on the decommissioning of a whole area from the decommissioning strategy to the radioactive waste treatment when dismantling a nuclear facility. The decommissioning requirements have a unique feature in terms of a horizontal relationship as well as a vertical relationship from the regulation requirements to the decommissioning technical requirements. The decommissioning requirements management will be conducted through research that can recognize a multiple relationship in the next stage.

  3. Summary of feasibility studies on in situ disposal as a decommissioning option for nuclear facilities

    International Nuclear Information System (INIS)

    Helbrecht, R.A.

    2002-01-01

    A scoping study was conducted over the period 1998-2000 to consider the feasibility of in situ disposal as a decommissioning option for AECL's Nuclear Power Demonstration Reactor located at Rolphton, Ontario. The results of a detailed assessment are summarized and the study concludes that in situ disposal appears feasible. Additional work required to confirm the results is also identified. A second in situ component, contaminated Winnipeg River sediments at AECL's Whiteshell Laboratory located in Manitoba, was also evaluated. That study concluded that in situ abandonment would have no adverse impact on aquatic life, humans and the environment. A summary of the study is presented as an appendix to the report. (author)

  4. Recordkeeping in the decommissioning process

    International Nuclear Information System (INIS)

    Boing, L. E.

    2000-01-01

    In the US, there are two sets of key decommissioning records clearly identified -- those that are essential for planning the D and D of a facility and then those that are the result of the decommissioning process itself. In some cases, the regulatory authorities require and in others advise the licensees of the records that may be useful or which are required to be kept from the decommissioning. In the remainder of the paper, the author attempts to highlight some important aspects of decommissioning recordkeeping

  5. Joint U.S./Russian Study on the Development of a Preliminary Cost Estimate of the SAFSTOR Decommissioning Alternative for the Leningrad Nuclear Power Plant Unit #1

    Energy Technology Data Exchange (ETDEWEB)

    SM Garrett

    1998-09-28

    The objectives of the two joint Russian/U.S. Leningrad Nuclear Power Plant (NPP) Unit #1 studies were the development of a safe, technically feasible, economically acceptable decom missioning strategy, and the preliminary cost evaluation of the developed strategy. The first study, resulting in the decommissioning strategy, was performed in 1996 and 1997. The preliminary cost estimation study, described in this report, was performed in 1997 and 1998. The decommissioning strategy study included the analyses of three basic RBM.K decommission- ing alternatives, refined for the Leningrad NPP Unit #1. The analyses included analysis of the requirements for the planning and preparation as well as the decommissioning phases.

  6. Reactor decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1984-01-01

    A pioneering project on the decommissioning of the Windscale Advanced Gas-cooled Reactor, by the UKAEA, is described. Reactor data; policy; waste management; remote handling equipment; development; and recording and timescales, are all briefly discussed. (U.K.)

  7. Study on the Development of Methodology for Cost Calculations and Financial Planning of Decommissioning Operations

    International Nuclear Information System (INIS)

    2001-12-01

    The following study deals with the development of methodology for cost calculations and financial planning of decommissioning operations. It has been carried out by EDF / FRAMATOME / VUJE / SCK-CEN in the frame of the contract B7-032/2000/291058/MAR/C2 awarded by the European Commission. This study consists of 4 parts. The first task objective is to develop a reliable and transparent methodology for cost assessment and financial planning sufficient precise but without long and in depth investigations and studies. This methodology mainly contains: Calculation methods and algorithms for the elaboration of costs items making up the whole decommissioning cost. Estimated or standard values for the parameters and for the cost factors to be used in the above-mentioned algorithms Financial mechanism to be applied as to establish a financial planning. The second part task is the provision of standard values for the different parameters and costs factors described in the above-mentioned algorithms. This provision of data is based on the own various experience acquired by the members of the working team and on existing international references (databases, publications and reports). As decommissioning operations are spreading over several dozens of years, the scope of this task the description of the financial mechanisms to be applied to the different cost items as to establish a complete financial cost. It takes into account the financial schedule issued in task 1. The scope of this task consists in bringing together in a guideline all the information collected before: algorithms, data and financial mechanisms. (A.L.B.)

  8. Nuclear decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Lawton, H.

    1987-02-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the UK, good progress has been made with the WAGR and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level.

  9. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1987-01-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the UK, good progress has been made with the WAGR and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level. (author)

  10. How it is possible to build a national system for decommissioning waste management without site nor waste liberation: the case of France

    International Nuclear Information System (INIS)

    Averous, Jeremie; Chapalain, Estelle

    2003-01-01

    Past experience in decommissioning in France has shown that a national system has to be put in place to deal with decommissioning, waste elimination and site cleaning up activities in order to allow a consistent, safe, transparent and industrially applicable management of these matters. A system founded on successive lines of defence has been put into enforcement, which does not involve any site nor waste liberation, as it is considered that the criteria associated are always prone to discussion and contradiction. This system is based on the following concepts: - 'nuclear waste', waste prone to have been contaminated or activated, is segregated from 'conventional waste' using a system involving successive lines of defence, and hence, building a very high level of confidence that no 'nuclear waste' will be eliminated without control in conventional waste eliminators or recycling facilities; - 'nuclear waste' is eliminated in dedicated facilities or repositories, or in conventional facilities under the condition of a special authorization based on a radiological impact study and a public inquiry; - a global safety evaluation of the nuclear site is conducted after decommissioning in order to define possible use restrictions. In all cases, minimum restrictions will be put into enforcement in urbanization plans to ensure sufficient precaution when planning future uses of the ground or the building. This paper describes this global system in detail and shows that its inherent consistency allows it to be easily applicable by operators while achieving a high level of safety and confidence. It is now widely accepted by stakeholders. The French Nuclear Safety Authority is now working to apply this methodology more widely to other nuclear practices like the waste management from medical, research and industrial activities, or from past or remediation activities. (authors)

  11. Guideline to Estimate Decommissioning Costs

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Kim, Younggook; Oh, Jaeyoung [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    The primary objective of this work is to provide guidelines to estimate the decommissioning cost as well as the stakeholders with plausible information to understand the decommissioning activities in a reasonable manner, which eventually contribute to acquiring the public acceptance for the nuclear power industry. Although several cases of the decommissioning cost estimate have been made for a few commercial nuclear power plants, the different technical, site-specific and economic assumptions used make it difficult to interpret those cost estimates and compare them with that of a relevant plant. Trustworthy cost estimates are crucial to plan a safe and economic decommissioning project. The typical approach is to break down the decommissioning project into a series of discrete and measurable work activities. Although plant specific differences derived from the economic and technical assumptions make a licensee difficult to estimate reliable decommissioning costs, estimating decommissioning costs is the most crucial processes since it encompasses all the spectrum of activities from the planning to the final evaluation on whether a decommissioning project has successfully been preceded from the perspective of safety and economic points. Hence, it is clear that tenacious efforts should be needed to successfully perform the decommissioning project.

  12. Joint US/Russian study on the development of a decommissioning strategy plan for RBMK-1000 unit No. 1 at the Leningrad Nuclear Power Plant

    International Nuclear Information System (INIS)

    1997-12-01

    The objective of this joint U.S./Russian study was to develop a safe, technically feasible, economically acceptable strategy for decommissioning Leningrad Nuclear Power Plant (LNPP) Unit No. 1 as a representative first-generation RBMK-1000 reactor. The ultimate goal in developing the decommissioning strategy was to select the most suitable decommissioning alternative and end state, taking into account the socioeconomic conditions, the regulatory environment, and decommissioning experience in Russia. This study was performed by a group of Russian and American experts led by Kurchatov Institute for the Russian efforts and by the Pacific Northwest National Laboratory for the U.S. efforts and for the overall project

  13. Basic Research about Calculation of the Decommissioning Unit Cost based on The KRR-2 Decommissioning Project

    International Nuclear Information System (INIS)

    Song, Chan-Ho; Park, Hee-Seong; Ha, Jea-Hyun; Jin, Hyung-Gon; Park, Seung-Kook

    2015-01-01

    The KAERI be used to calculate the decommissioning cost and manage the data of decommissioning activity experience through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). Some country such as Japan and The United States have the information for decommissioning experience of the NPP and publish reports on decommissioning cost analysis. These reports as valuable data be used to compare with the decommissioning unit cost. In particular, need a method to estimate the decommissioning cost of the NPP because there is no decommissioning experience of NPP in case of Korea. makes possible to predict the more precise prediction about the decommissioning unit cost. But still, there are many differences on calculation for the decommissioning unit cost in domestic and foreign country. Typically, it is difficult to compare with data because published not detailed reports. Therefore, field of estimation for decommissioning cost have to use a unified framework in order to the decommissioning cost be provided to exact of the decommissioning cost

  14. Basic Research about Calculation of the Decommissioning Unit Cost based on The KRR-2 Decommissioning Project

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Hee-Seong; Ha, Jea-Hyun; Jin, Hyung-Gon; Park, Seung-Kook [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    The KAERI be used to calculate the decommissioning cost and manage the data of decommissioning activity experience through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). Some country such as Japan and The United States have the information for decommissioning experience of the NPP and publish reports on decommissioning cost analysis. These reports as valuable data be used to compare with the decommissioning unit cost. In particular, need a method to estimate the decommissioning cost of the NPP because there is no decommissioning experience of NPP in case of Korea. makes possible to predict the more precise prediction about the decommissioning unit cost. But still, there are many differences on calculation for the decommissioning unit cost in domestic and foreign country. Typically, it is difficult to compare with data because published not detailed reports. Therefore, field of estimation for decommissioning cost have to use a unified framework in order to the decommissioning cost be provided to exact of the decommissioning cost.

  15. Decommissioning project feedback experience in the Japan Atomic Energy Research Institut

    International Nuclear Information System (INIS)

    Yanagihara, S.; Tachibana, M.; Miyajima, K.

    2003-01-01

    Since starting the research and development program for peaceful use of nuclear energy in 1950's, various research and demonstration facilities have been constructed in research organizations, universities and commercial sectors in Japan. Some of the nuclear facilities constructed in the early stage of research and development have been retired to be decommissioned because of completion of the initial objectives in the Japan Atomic Energy Research Institute (JAERI). On the other hand, since the first commercial operation of nuclear power plant (1968), the number of nuclear power plants has increased up to 52 plants operating as of August 2003 in Japan. The shear of nuclear energy accounts approximately for 35% of electricity generation in total at present time. However, several nuclear power plants have been operated for more than 25 years and two nuclear power plants are expected to be finally shutdown by 2010 to be eventually decommissioned. The Tokai Power Station, the oldest Japanese nuclear power plant operated by the Japan Atomic Power Company, was permanently shutdown from March 1998 and it is in decommissioning stage at this time. The Fugen, which is advanced thermal reactor operated by the Japan Nuclear Cycle Development Institute (JNC), was finally shutdown on March, 2003 after 25 years operation to be decommissioned. In addition, relating to planned unification between JAERI and JNC in 2005, the studies have been in progress on decommissioning and radioactive waste treatment and disposal; the cost was estimated to be 10 to 30 billion Japanese yens per year during 80 years for decommissioning of nearly 200 nuclear facilities. Decommissioning of nuclear facilities is thus getting to be one of important issues in Japan. Decommissioning of nuclear facilities might be possible using conventional and/or partially improved technology. However, reviewing project feedback experience on decommissioning and decontamination might contribute to solve various issues

  16. The technological study on the decommissioning of nuclear facility, etc. in the Tokai Research Establishment

    International Nuclear Information System (INIS)

    Tomii, Hiroyuki; Matsuo, Kiyoshi; Shiraishi, Kunio; Kato, Rokuro; Watabe, Kozou; Higashiyama, Yutaka; Nagane, Satoru

    2005-03-01

    Since JPDR is dismantled and is removed, in Tokai Research Establishment, Japan Atomic Energy Research Institute, the dismantling of nuclear facility which finished the mission, etc. is advanced. At present, nuclear facility as a dismantling object count the approximately 20 facilities, and decommissioning plan of these facilities becomes an important problem, when the decommissioning countermeasure is considered. However, decommissioning techniques in proportion to various nuclear facility, etc. are clearly, and it has not been determined. In this report, the technical consideration on decommissioning techniques of nuclear facility promoted on the basis of this experience in future, while until now decommissioning experience and technical knowledge are arranged, etc. was added in order to appropriately and surely carry out decommissioning techniques and legal procedures, etc. (author)

  17. Decommissioning handbook

    Energy Technology Data Exchange (ETDEWEB)

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained.

  18. Decommissioning handbook

    International Nuclear Information System (INIS)

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained

  19. Research on decommissioning of nuclear facilities 2. Study on optimum scenario using the AHP (Joint research)

    International Nuclear Information System (INIS)

    Shibahara, Yuji; Morishita, Yoshitsugu; Ishigami, Tsutomu; Yanagihara, Satoshi; Arita, Yuji

    2013-01-01

    To implement a decommissioning project reasonably, it is necessary and important to calculate project management data beforehand as well as to select an optimum dismantling scenario among various scenarios postulated. Little study on the subject of selecting an optimum scenario has been carried out, and it is one of the most important issues in terms of decision making. In FY 2009, Japan Atomic Energy Agency and University of Fukui launched the joint research of a decision making method which is important to determine a decommissioning plan. The purpose of this research is to formulate a methodology for selecting an optimum dismantling scenario among various scenarios postulated based on calculated results of project management data for FUGEN. Project management data for several dismantling scenarios postulated at FUGEN were evaluated based on actual dismantling work for feedwater heater at FUGEN, and an optimum scenario was discussed using the AHP, one of Multi-Criteria Decision Analysis Methods. This report describes the results of the joint research in FY 2010. (author)

  20. Modelling of nuclear power plant decommissioning financing.

    Science.gov (United States)

    Bemš, J; Knápek, J; Králík, T; Hejhal, M; Kubančák, J; Vašíček, J

    2015-06-01

    Costs related to the decommissioning of nuclear power plants create a significant financial burden for nuclear power plant operators. This article discusses the various methodologies employed by selected European countries for financing of the liabilities related to the nuclear power plant decommissioning. The article also presents methodology of allocation of future decommissioning costs to the running costs of nuclear power plant in the form of fee imposed on each megawatt hour generated. The application of the methodology is presented in the form of a case study on a new nuclear power plant with installed capacity 1000 MW. © The Author 2015. Published by Oxford University Press. All rights reserved. For Permissions, please email: journals.permissions@oup.com.

  1. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1987-01-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the United Kingdom, good progress has been made with the Windscale Advanced Gas-cooled Reactor and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level. (author)

  2. ORNL decontamination and decommissioning program

    International Nuclear Information System (INIS)

    Bell, J.P.

    1980-01-01

    A program has been initiated at ORNL to decontaminate and decommission surplus or abandoned nuclear facilities. Program planning and technical studies have been performed by UCC-ND Engineering. A feasibility study for decommissioning the Metal Recovery Facility, a fuel reprocessing pilot plant, has been completed

  3. Waste management considerations in nuclear facility decommissioning

    International Nuclear Information System (INIS)

    Elder, H.K.; Murphy, E.S.

    1981-01-01

    Decommissioning of nuclear facilities involves the management of significant quantities of radioactive waste. This paper summarizes information on volumes of waste requiring disposal and waste management costs developed in a series of decommissioning studies performed for the U.S. Nuclear Regulatory Commission by the Pacific Northwest Laboratory. These studies indicate that waste management is an important cost factor in the decommissioning of nuclear facilities. Alternatives for managing decommissioning wastes are defined and recommendations are made for improvements in waste management practices

  4. Development of decommissioning system engineering technology

    International Nuclear Information System (INIS)

    Lee, K. W.; Kim, S. K.; Seo, B. K.

    2012-02-01

    In the decommissioning planning stage, it is important to select the optimized decommissioning process considering the cost and safety. Especially the selection of the optimized decommissioning process is necessary because it affects to improve worker's safety and decommissioning work efficiency. The decommissioning process evaluation technology can provide the optimized decommissioning process as constructing various decommissioning scenarios and it can help to prevent the potential accidents as delivering the exact work procedures to workers and to help workers to perform decommissioning work skillfully. It's necessary to measure the radioactive contamination in the highly contaminated facilities such as hot-cells or glove-boxes to be decommissioned for decommissioning planning. These facilities are very high radiation level, so it is difficult to approach. In this case the detector system is preferable to separate the sensor and electronics, which have to locate in the facility outside to avoid the electric noise and worker's radiation exposure. In this project, we developed the remote detection system for radiation measurement and signal transmission in the high radiation area. In order to minimize worker's exposure when decommissioning highly activated nuclear facilities, it is necessary to develop the remote handling tool to perform the dismantling work remotely. Especially, since cutting, measuring, and decontamination works should be performed remotely in the highly activated area, the remote handling tool for conducting these works should be developed. Therefore, the multi-purpose dismantling machine that can measuring dose, facility cutting, and remote handling for maintenance and decommissioning of highly activated facility should be needed

  5. Decommissioning: a problem or a challenge?

    Directory of Open Access Journals (Sweden)

    Mele Irena

    2004-01-01

    Full Text Available With the ageing of nuclear facilities or the reduced interest in their further operation, a new set of problems, related to the decommissioning of these facilities, has come into forefront. In many cases it turns out that the preparations for decommissioning have come too late, and that financial resources for covering decommissioning activities have not been provided. To avoid such problems, future liailities should be thoroughly estimated in drawing up the decommissioning and waste management programme for each nuclear facility in time, and financial provisions for implementing such programme should be provided. In this paper a presentation of current decommissioning experience in Slovenia is given. The main problems and difficulties in decommissioning of the Žirovski Vrh Uranium Mine are exposed and the lesson learned from this case is presented. The preparation of the decommissioning programme for the Nuclear Power Plant Krško is also described, and the situation at the TRIGA research reactor is briefly discussed.

  6. Assessment of foreign decommissioning technology with potential application to US decommissioning needs

    International Nuclear Information System (INIS)

    Allen, R.P.; Konzek, G.J.; Schneider, K.J.; Smith, R.I.

    1987-09-01

    This study was conducted by the Pacific Northwest Laboratory (PNL) for the US Department of Energy (DOE) to identify and technically assess foreign decommissioning technology developments that may represent significant improvements over decommissioning technology currently available or under development in the United States. Technology need areas for nuclear power reactor decommissioning operations were identified and prioritized using the results of past light water reactor (LWR) decommissioning studies to quantitatively evaluate the potential for reducing cost and decommissioning worker radiation dose for each major decommissioning activity. Based on these identified needs, current foreign decommissioning technologies of potential interest to the US were identified through personal contacts and the collection and review of an extensive body of decommissioning literature. These technologies were then assessed qualitatively to evaluate their uniqueness, potential for a significant reduction in decommissioning costs and/or worker radiation dose, development status, and other factors affecting their value and applicability to US needs

  7. Planning activities for ANPP decommissioning

    International Nuclear Information System (INIS)

    Ghazaryan, K.G.

    2002-01-01

    suggested solution was a choice of SAFSTOR as a viable decommissioning option. Spent fuel management is not considered part of decommissioning; however it can strongly affect the decommissioning strategy. Currently the spent nuclear fuel is being stored on site in pools and in a newly constructed NUHOMS storage facility built by FRAMATOME under license of USA Transnuclear West Company. The facility includes 11 horizontal storage modules (HSM). Each HSM has a capacity of 56 non-failed fuel assemblies. A capacity of the existing dry storage facility is not sufficient to accommodate all spent fuel generated during plant operation. However, the NUHOMS concept is modular and it is possible to increase the storage capacity. The facility is designed for 50 years storage of spent nuclear fuel. In any case, these studies should be considered as an informative basis only. Much more additional information should be collected and the detailed characterization survey, i.e. the comprehensive engineering and radiological survey, conducted to have sufficient data for all further planning activities. (author)

  8. Decommissioning planning of Swedish nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Hedin, Gunnar; Bergh, Niklas [Westinghouse Electric Sweden AB, Vaesteraes (Sweden)

    2013-07-01

    The technologies required for the decommissioning work are for the most part readily proven. Taken into account that there will be many more years before the studied reactor units will undergo decommissioning, the techniques could even be called conventional at that time. This will help bring the decommissioning projects to a successful closure. A national waste fund is already established in Sweden to finance amongst others all dismantling and decommissioning work. This will assure that funding for the decommissioning projects is at hand when needed. All necessary plant data are readily available and this will, combined with a reliable management system, expedite the decommissioning projects considerably. Final repositories for both long- and short-lived LILW respectively is planned and will be constructed and dimensioned to receive the decommissioning waste from the Swedish NPP:s. Since the strategy is set and well thought-through, this will help facilitate a smooth disposal of the radioactive decommissioning waste. (orig.)

  9. TEM study of radiation induced defects in baffle-former-barrel assembly from decommissioned NPP Greifswald

    International Nuclear Information System (INIS)

    Srba, O.; Michalicka, J.; Keilova, E.; Kocik, K.

    2013-06-01

    A complex transmission electron microscopy (TEM) study of reactor vessel internal (RVI) materials from the baffle-former-barrel assembly from NPP Greifswald (VVER 440), Unit 1 decommissioned after 15 service cycles has been undertaken. All parts of the baffle-former-barrel assembly are made from Ti-stabilized austenitic stainless steel 08Ch18N10T. The materials were exposed to different dose of neutron radiation (2.4 - 11.4 dpa) at temperatures 267 - 398 deg. C depending on position in the core. Three types of radiation induced defects were identified and quantified, namely: dislocations, cavities (voids) and fine-scaled precipitated particles of Ni-Si rich phases. Black-dot type defects were observed too. Operation conditions are around ≅ 300 deg. C that is why we have observed defect typical for both low and high regions of irradiation temperatures. (authors)

  10. Decommissioning in western Europe

    International Nuclear Information System (INIS)

    Lundqvist, K.

    1999-12-01

    This report gives an overview of the situation in Western Europe. The original aim was to focus on organisational and human issues with regard to nuclear reactor decommissioning, but very few articles were found. This is in sharp contrast to the substantial literature on technical issues. While most of the reports on decommissioning have a technical focus, several provide information on regulatory issues, strategies and 'state of the art'. The importance of the human and organizational perspective is however discovered, when reading between the lines of the technical publications, and especially when project managers summarize lessons learned. The results are to a large extent based on studies of articles and reports, mainly collected from the INIS database. Decommissioning of nuclear facilities started already in the sixties, but then mainly research and experimental facilities were concerned. Until now about 70 reactors have been shutdown world-wide. Over the years there have been plenty of conferences for exchanging experiences mostly about technical matters. Waste Management is a big issue. In the 2000s there will be a wave of decommissioning when an increasing amount of reactors will reach the end of their calculated lifetime (40 years, a figure now being challenged by both life-extension and pre-shutdown projects). Several reactors have been shut-down for economical reasons. Shutdown and decommissioning is however not identical. A long period of time can sometimes pass before an owner decides to decommission and dismantle a facility. The conditions will also differ depending on the strategy, 'immediate dismantling' or 'safe enclosure'. If immediate dismantling is chosen the site can reach 'green-field status' in less than ten years. 'Safe enclosure', however, seems to be the most common strategy. There are several pathways, but in general a safe store is constructed, enabling the active parts to remain in safe and waterproof conditions for a longer period of

  11. Summary of comments received at workshop on use of a Site Specific Advisory Board (SSAB) to facilitate public participation in decommissioning cases

    International Nuclear Information System (INIS)

    Caplin, J.; Padge, G.; Smith, D.; Wiblin, C.

    1995-06-01

    The Nuclear Regulatory Commission (NRC) is conducting an enhanced participatory rulemaking to establish radiological criteria for the decommissioning of NRC-licensed facilities. As part of this rulemaking, On August 20, 1994 the NRC published a proposed rule for public comment. Paragraph 20.1406(b) of the proposed rule would require that the licensee convene a Site Specific Advisory Board (SSAB) if the licensee proposed release of the site for restricted use after decommissioning. To encourage comment the NRC held a workshop on the subject of $SABs on December 6, 7, and 8, 1994. This report summarizes the 567 comments categorized from the transcript of the workshop. The commenters at the workshop generally supported public participation in decommissioning cases. Many participants favored promulgating requirements in the NRC's rules. Some industry participants favored relying on voluntary exchanges between the public and the licensees. Many participants indicated that a SSAB or something functionally equivalent is needed in controversial decommissioning cases, but that some lesser undertaking can achieve meaningful public participation in other cases. No analysis or response to the comments is included in this report

  12. Progress of JPDR decommissioning project

    International Nuclear Information System (INIS)

    Kiyota, M.; Yanagihara, S.

    1995-01-01

    The Japan Power Demonstration Reactor (JPDR) decommissioning project is progressively achieving its final goal; the project will be finished by March 1996 to release the JPDR's site into unrestricted use in a green field condition. The new techniques which developed or improved in R and D, the first phase of this program, have been successfully applied to the actual dismantling activities. Some decommissioning wastes have been managed as the first case of onsite shallow land burial based on the new regulatory frame of radioactive waste management. The experiences and the data obtained from the JPDR dismantling activities are expected to contribute to future decommissioning of commercial nuclear power plants. (author)

  13. Decommissioning of nuclear power stations

    International Nuclear Information System (INIS)

    Gregory, A.R.

    1988-01-01

    In the United Kingdom the Electricity Boards, the United Kingdom Atomic Energy Authority (UKAEA) and BNFL cooperate on all matters relating to the decommissioning of nuclear plant. The Central Electricity Generating Board's (CEGB) policy endorses the continuing need for nuclear power, the principle of reusing existing sites where possible and the building up of sufficient funds during the operating life of a nuclear power station to meet the cost of its complete clearance in the future. The safety of the plant is the responsibility of the licensee even in the decommissioning phase. The CEGB has carried out decommissioning studies on Magnox stations in general and Bradwell and Berkeley in particular. It has also been involved in the UKAEA Windscale AGR decommissioning programme. The options as to which stage to decommission to are considered. Methods, costs and waste management are also considered. (U.K.)

  14. Importance of funding in decommissioning cost estimates

    International Nuclear Information System (INIS)

    Mingst, B.C.

    1987-01-01

    Decommissioning cost estimates have been made by several study groups for the decommissioning of pressurized-water and boiling-water nuclear power stations. The results of these studies are comparable when corrected for inflation and the differences in contingency factors applied by the study groups. The estimated dismantling costs differ far less than a factor of 2 in all cases, despite the design differences found in the plants that were studied. An analysis of the different methods available for funding the dismantling of these facilities shows the much stronger effect that the choice of funding methods has on the net cost of decommissioning. The total cost of dismantling may vary more than a factor of 4 from one funding method to another, assuming current or recent historical inflation rates. The funding methods evaluated include sinking funds, deposits, negative-salvage value depreciation, and insurance. These funding methods are taken from the NRC's Notice of Proposed Rulemaking description of acceptable funding methods. The funding analysis for this study was performed using the DECOST-86 computer code. The evaluation of funding options for a nuclear facility, and the appropriate choice of the funding method best for that facility, are found to be more important than detailed engineering studies in determining the net cost of decommissioning during the early portions of the plant's operating lifetime

  15. Experiences in teaching decommissioning - 16179

    International Nuclear Information System (INIS)

    Catlow, Fred

    2009-01-01

    The paper describes the experience gained by the author in teaching decommissioning in the Highlands of Scotland. Initially when asked to teach the subject of decommissioning to students sitting for a BSc degree in 'Electrical or Mechanical Engineering with Decommissioning Studies', the author was taken aback, not having previously taught degree students and there was no precedent since there was no previous material or examples to build on. It was just as difficult for the students since whilst some had progressed from completing HND studies, the majority were employed at the Dounreay site and were mature students with families who were availing themselves of the opportunity for career advancement (CPD). Some of the students were from the UKAEA and its contractors whilst others were from Rolls-Royce working at Vulcan, the Royal Navy's establishment for testing nuclear reactors for submarines. A number of the students had not been in a formal learning environment for many years. The College which had originally been funded by the UKAEA and the nuclear industry in the 1950's was anxious to break into the new field of Decommissioning and were keen to promote these courses in order to support the work progressing on site. Many families in Thurso, and in Caithness, have a long tradition of working in the nuclear industry and it was thought at the time that expertise in nuclear decommissioning could be developed and indeed exported elsewhere. In addition the courses being promoted by the College would attract students from other parts so that a centre of excellence could be established. In parallel with formal teaching, online courses were also developed to extend the reach of the College. The material was developed as a mixture of power point presentations and formal notes and was obtained from existing literature, web searches and interactive discussions with people in the industry as well as case studies obtained from actual situations. Assignments were set and

  16. 1982 international decommissioning symposium

    International Nuclear Information System (INIS)

    Mickelson, S.

    1982-01-01

    Sixty-four papers were presented at the following sessions: policy, regulations, and standards; management of decommissioning wastes; decommissioning experience; decommissioning tooling and techniques; radiological concerns; and planning and engineering

  17. A study on the application of standards for clearance of metal waste generated during the decommissioning of NPP by using the RESRAD-RECYCLE

    Energy Technology Data Exchange (ETDEWEB)

    Song, Jong Soon; Kim, Dong Min; Lee, Sang Heon [Chosun University, Gwangju (Korea, Republic of)

    2016-12-15

    The metal waste generated during nuclear power plant decommissioning constitutes a large proportion of the total radioactive waste. This study investigates the current status of domestic and international regulatory requirements for clearance and the clearance experience of domestic institutions. The RESRAD-RECYCLE code was used for analyzing the clearance of the metal wastes generated during actual nuclear power plant decommissioning, and assessment of the exposure dose of twenty-six scenarios was carried out. The evaluation results will be useful in preliminary analysis of clearance and recycling during nuclear power plant decommissioning. As a next step, the effects of reducing disposal costs by clearance can be studied.

  18. Decommissioning - The worldwide challenge

    International Nuclear Information System (INIS)

    McKeown, John

    2002-01-01

    Full text: Whatever the future may hold for nuclear power, there are closed or ageing nuclear facilities in many countries around the world. While these may be in safe care and maintenance at present, a sustainable long term solution is required. Facilities need to be decommissioned, contaminated land remediated, and wastes conditioned for safe storage or disposal. Practical nuclear site restoration has been demonstrated internationally. This experience has revealed generic challenges in dealing with old, often experimental, facilities. These include: Facilities not designed for ease of decommissioning; Records of plant construction and operation, and of the materials utilised and wastes produced, not to modern standards; Fuels and wastes stored for long periods in less than optimal conditions, leading to deterioration and handling problems; The historic use of experimental fuels and materials, giving rise to unique waste streams requiring unique waste management solutions; The application of modern safety and environmental standards to plant which dates from the 1940s, 50s and 60s, requiring investment before decommissioning can even commence. These problems can be tackled, as examples from UKAEA's own programme will illustrate. But two fundamental issues must be recognised and considered. First, the costs of decommissioning older facilities are very high, and may place a heavy burden on national budgets, despite using best efforts to control them. We can limit these costs by learning from one another's experience and sharing the development of new techniques and technologies. UKAEA has already initiated a programme of international collaboration, and hopes that other IAEA countries will be encouraged to follow suit. But whilst the costs of decommissioning may be high, the process normally meets with public acceptance. This is seldom the case for long term waste storage or disposal. Until waste management routes are available - either nationally or internationally

  19. Decommissioning of Brennilis NPP

    International Nuclear Information System (INIS)

    Baize, Jean-Marc

    1998-01-01

    This EDF press communique give information related to the decommissioning of the Brennilis NPP. The following five items are developed in this report: 1. the level-2 decommissioning operations at the Brennilis NPP; 2. the Brennilis NPP, a pilot operation from the commissioning up to the decommissioning; 3. history of the Brennilis NPP decommissioning; 4. the types of radioactive wastes generated by the Brennilis NPP decommissioning; 5. the Brennilis NPP - a yard management as a function of the wastes. The document contains also seven appendices addressing the following subjects: 1. the share of decommissioning assigned to EDF and the decommissioning steps; 2. the EDF installations in course of decommissioning; 3. the CEA decommissioned installations or in course of decommissioning; 4. regulations; 5. costs; 6. waste management - principles; 7. data on the decommissioning yard

  20. Ringhals Site Study 2013 - An assessment of the decommissioning cost for the Ringhals site

    Energy Technology Data Exchange (ETDEWEB)

    Hansson, Tommy [Ringhals AB, Ringhals (Sweden); Norberg, Thomas [Solvina AB, Goeteborg (Sweden); Knutsson, Andreas; Fors, Patrik; Sandebert, Camilla [Vattenfall AB, Stockholm (Sweden)

    2013-03-15

    This report presents the decommissioning cost for the Ringhals site as of 2013. The objective has been to make a best estimate of the costs within the uncertainties of a budgetary estimate. To achieve this, the decommissioning costs have been assessed with support from TLG Services Inc., utilizing their knowledge and experience from U.S. decommissioning projects incorporated in their cost estimation platform DECCER. The 2013 estimate has included the development of a Ringhals-specific cost estimation method that allows for successive improvement in the future. In-house experiences have been included and the method is based on the present decommissioning strategy according to Ringhals decommissioning plan. Two basic approaches have been used in the cost assessment; a bottom up approach to develop unit cost factors (UCF) for recurrent work; and a specific analogy approach for cost estimating special items. The basic, activity-dependent, costs have been complemented by period-dependent costs, derived, among other things, from SKB's newly developed reference planning and organizational model for a Swedish decommissioning project. Furthermore, collateral costs based on the experiences of Barsebaeck have been included. As a final point, all costs have been adjusted for industrial standard contingencies, as suggested by TLG, to achieve a best estimate. In order to make the cost intelligible a comprehensive description of the assumptions, boundary conditions and general basis of the estimate is included in this report. All costs have been reported both according to the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations published by OECD/NEA and according to the SKB developed EEF structure. Furthermore, common costs have been isolated to a theoretical unit 0 to make the cost for respective unit even more comparable on a national and international scale. The calculations show that the total cost for the decommissioning of the Ringhals

  1. Ringhals Site Study 2013 - An assessment of the decommissioning cost for the Ringhals site

    International Nuclear Information System (INIS)

    Hansson, Tommy; Norberg, Thomas; Knutsson, Andreas; Fors, Patrik; Sandebert, Camilla

    2013-03-01

    This report presents the decommissioning cost for the Ringhals site as of 2013. The objective has been to make a best estimate of the costs within the uncertainties of a budgetary estimate. To achieve this, the decommissioning costs have been assessed with support from TLG Services Inc., utilizing their knowledge and experience from U.S. decommissioning projects incorporated in their cost estimation platform DECCER. The 2013 estimate has included the development of a Ringhals-specific cost estimation method that allows for successive improvement in the future. In-house experiences have been included and the method is based on the present decommissioning strategy according to Ringhals decommissioning plan. Two basic approaches have been used in the cost assessment; a bottom up approach to develop unit cost factors (UCF) for recurrent work; and a specific analogy approach for cost estimating special items. The basic, activity-dependent, costs have been complemented by period-dependent costs, derived, among other things, from SKB's newly developed reference planning and organizational model for a Swedish decommissioning project. Furthermore, collateral costs based on the experiences of Barsebaeck have been included. As a final point, all costs have been adjusted for industrial standard contingencies, as suggested by TLG, to achieve a best estimate. In order to make the cost intelligible a comprehensive description of the assumptions, boundary conditions and general basis of the estimate is included in this report. All costs have been reported both according to the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations published by OECD/NEA and according to the SKB developed EEF structure. Furthermore, common costs have been isolated to a theoretical unit 0 to make the cost for respective unit even more comparable on a national and international scale. The calculations show that the total cost for the decommissioning of the Ringhals site is

  2. Policy and systems analysis for nuclear installation decommissioning

    International Nuclear Information System (INIS)

    Gu Jiande

    1995-01-01

    On the basis of introducing into principal concept for nuclear installation decommissioning, form policy, sciences point of view, the author analyses present problems in the policy, the administrative and programme for decommissioning work in China. According to the physical process of decommissioning, the author studied engineering economics, derived method and formulas to estimate decommissioning cost. It is pointed out that basing on optimization principle for radiation protection and analysing cost-benefit for decommissioning engineering, the corresponding policy decision can be made

  3. A study of implementing In-Cycle-Shuffle strategy to a decommissioning boiling water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Chen, Chung-Yuan, E-mail: tuckjason@iner.gov.tw; Tung, Wu-Hsiung; Yaur, Shyun-Jung

    2017-06-15

    Highlights: • A loading pattern strategy ICS (In-Cycle-Shuffle) was implemented to the last cycle of the boiling water reactor. • The best power sharing distribution and ICS timing was found. • A new parameter “Burnup sharing” is presented to evaluate ICS strategy. - Abstract: In this paper, a loading pattern strategy In-Cycle-Shuffle (ICS) is implemented to the last cycle of the boiling water reactor (BWR) before decommissioning to save the fuel cycle cost. This method needs a core shutdown during the operation of a cycle to change the loading pattern to gain more reactivity. The reactivity model is used to model the ICS strategy in order to find out the best ICS timing and the optimum power sharing distribution before ICS and after ICS. Several parameters of reactivity model are modified and the effect of burnable poison, gadolinium (Gd), is considered in this research. Three cases are presented and it is found that the best ICS timing is at about two-thirds of total cycle length no matter the poisoning effect of Gd is considered or not. According to the optimum power sharing distribution result, it is suggested to decrease the once burnt power and increase the thrice burnt fuel power as much as possible before ICS. After ICS, it is suggested to increase the positive reactivity fuel power and decrease the thrice burnt fuel power as much as possible. A new parameter “Burnup sharing” is presented to evaluate the special case whose EOC power weighting factor and the burnup accumulation factor in the reactivity model are quite different.

  4. A study of implementing In-Cycle-Shuffle strategy to a decommissioning boiling water reactor

    International Nuclear Information System (INIS)

    Chen, Chung-Yuan; Tung, Wu-Hsiung; Yaur, Shyun-Jung

    2017-01-01

    Highlights: • A loading pattern strategy ICS (In-Cycle-Shuffle) was implemented to the last cycle of the boiling water reactor. • The best power sharing distribution and ICS timing was found. • A new parameter “Burnup sharing” is presented to evaluate ICS strategy. - Abstract: In this paper, a loading pattern strategy In-Cycle-Shuffle (ICS) is implemented to the last cycle of the boiling water reactor (BWR) before decommissioning to save the fuel cycle cost. This method needs a core shutdown during the operation of a cycle to change the loading pattern to gain more reactivity. The reactivity model is used to model the ICS strategy in order to find out the best ICS timing and the optimum power sharing distribution before ICS and after ICS. Several parameters of reactivity model are modified and the effect of burnable poison, gadolinium (Gd), is considered in this research. Three cases are presented and it is found that the best ICS timing is at about two-thirds of total cycle length no matter the poisoning effect of Gd is considered or not. According to the optimum power sharing distribution result, it is suggested to decrease the once burnt power and increase the thrice burnt fuel power as much as possible before ICS. After ICS, it is suggested to increase the positive reactivity fuel power and decrease the thrice burnt fuel power as much as possible. A new parameter “Burnup sharing” is presented to evaluate the special case whose EOC power weighting factor and the burnup accumulation factor in the reactivity model are quite different.

  5. The decommissioning of nuclear power stations

    International Nuclear Information System (INIS)

    Barker, F.

    1992-01-01

    This report has been commissioned by the National Steering Committee of Nuclear Free Local Authorities to provide: a comprehensive introduction to the technical, social, political, environmental and economic dimensions to nuclear power station decommissioning; an independent analysis of Nuclear Electric's recent change of decommissioning strategy; the case for wider public involvement in decision making about decommissioning; and a preliminary assessment of the potential mechanisms for achieving that essential wider public involvement

  6. Decommissioning strategy and schedule for a multiple reactor nuclear power plant site

    Energy Technology Data Exchange (ETDEWEB)

    Monteiro, Deiglys Borges; Moreira, Joao M.L.; Maiorino, Jose Rubens, E-mail: deiglys.monteiro@ufabc.edu.br, E-mail: joao.moreira@ufabc.edu.br, E-mail: joserubens.maiorino@ufabc.edu.br [Universidade Federal do ABC (CECS/UFABC), Santo Andre, SP (Brazil). Centro de Engenharia, Modelagem e Ciencias Aplicadas

    2015-07-01

    The decommissioning is an important part of every Nuclear Power Plant life cycle gaining importance when there are more than one plant at the same site due to interactions that can arise from the operational ones and a decommissioning plant. In order to prevent undesirable problems, a suitable strategy and a very rigorous schedule should implemented and carried. In this way, decommissioning tasks such as fully decontamination and dismantling of activated and contaminated systems, rooms and structures could be delayed, posing as an interesting option to multiple reactor sites. The present work aims to purpose a strategy and a schedule for the decommissioning of a multiple reactor site highlighting the benefits of delay operational tasks and constructs some auxiliary services in the site during the stand by period of the shutdown plants. As a case study, will be presented a three-reactor site which the decommissioning process actually is in planning stage and that should start in the next decade. (author)

  7. Decommissioning strategy and schedule for a multiple reactor nuclear power plant site

    International Nuclear Information System (INIS)

    Monteiro, Deiglys Borges; Moreira, Joao M.L.; Maiorino, Jose Rubens

    2015-01-01

    The decommissioning is an important part of every Nuclear Power Plant life cycle gaining importance when there are more than one plant at the same site due to interactions that can arise from the operational ones and a decommissioning plant. In order to prevent undesirable problems, a suitable strategy and a very rigorous schedule should implemented and carried. In this way, decommissioning tasks such as fully decontamination and dismantling of activated and contaminated systems, rooms and structures could be delayed, posing as an interesting option to multiple reactor sites. The present work aims to purpose a strategy and a schedule for the decommissioning of a multiple reactor site highlighting the benefits of delay operational tasks and constructs some auxiliary services in the site during the stand by period of the shutdown plants. As a case study, will be presented a three-reactor site which the decommissioning process actually is in planning stage and that should start in the next decade. (author)

  8. An Applied Study on the Decontamination and Decommissioning of the Map Tube Facility 317 Area Argonne National Laboratory, Chicago

    Energy Technology Data Exchange (ETDEWEB)

    Varley, Geoff; Rusch, Chris [NAC International, Henley-on-Thames (United Kingdom)

    2005-01-01

    less. Unlike the MTF, AT has some storage vaults in addition to storage tubes. Based on available descriptions of the nature of the wastes stored in AT and the MTF, in general terms the range of wastes appears to be somewhat similar. In the case of the MTF it was determined that radioactive sludge was present at the bottom of the tubes, resulting from water ingress and corrosion of both storage containers and their contents. In the case of AT it is not known exactly what the condition of the tubes is but it is recognised that leakage/contamination in the lower parts of the tubes is likely to have occurred. This is an important consideration in the planning of the AT decommissioning program and the related cost estimate, principally because of the potential consequence of different approaches and specific techniques chosen to implement decommissioning. The AT decommissioning cost estimate report is not entirely clear in detail regarding the specific methodology to be adopted. In addition there are a number of important uncertainties concerning the extent of radioactive contamination. Depending on what the reality turns out to be, the decommissioning methodology could be affected and the quantities of wastes in various categories also could vary. In any event, the AT cost estimate report is unclear regarding waste volumes in a number of respects. The AT cost estimate is presented in a similar fashion to several other recent decommissioning cost estimates prepared by Westinghouse for SVAFO, using an approach and presentation format that suffers somewhat from: - Not always being clear, - Not always being unambiguous and easy to understand and, - Lack of detail and clear substantiation of assumptions in some important areas. Setting these concerns aside, the available information has been evaluated and compared with the Argonne MTF decommissioning costs and other selected NAC derived decommissioning cost benchmarks. In summary the conclusions for the AT decommissioning cost

  9. An Applied Study on the Decontamination and Decommissioning of the Map Tube Facility 317 Area Argonne National Laboratory, Chicago

    International Nuclear Information System (INIS)

    Varley, Geoff; Rusch, Chris

    2005-01-01

    less. Unlike the MTF, AT has some storage vaults in addition to storage tubes. Based on available descriptions of the nature of the wastes stored in AT and the MTF, in general terms the range of wastes appears to be somewhat similar. In the case of the MTF it was determined that radioactive sludge was present at the bottom of the tubes, resulting from water ingress and corrosion of both storage containers and their contents. In the case of AT it is not known exactly what the condition of the tubes is but it is recognised that leakage/contamination in the lower parts of the tubes is likely to have occurred. This is an important consideration in the planning of the AT decommissioning program and the related cost estimate, principally because of the potential consequence of different approaches and specific techniques chosen to implement decommissioning. The AT decommissioning cost estimate report is not entirely clear in detail regarding the specific methodology to be adopted. In addition there are a number of important uncertainties concerning the extent of radioactive contamination. Depending on what the reality turns out to be, the decommissioning methodology could be affected and the quantities of wastes in various categories also could vary. In any event, the AT cost estimate report is unclear regarding waste volumes in a number of respects. The AT cost estimate is presented in a similar fashion to several other recent decommissioning cost estimates prepared by Westinghouse for SVAFO, using an approach and presentation format that suffers somewhat from: - Not always being clear, - Not always being unambiguous and easy to understand and, - Lack of detail and clear substantiation of assumptions in some important areas. Setting these concerns aside, the available information has been evaluated and compared with the Argonne MTF decommissioning costs and other selected NAC derived decommissioning cost benchmarks. In summary the conclusions for the AT decommissioning cost

  10. Decommissioning of offshore installations

    Energy Technology Data Exchange (ETDEWEB)

    Oeen, Sigrun; Iversen, Per Erik; Stokke, Reidunn; Nielsen, Frantz; Henriksen, Thor; Natvig, Henning; Dretvik, Oeystein; Martinsen, Finn; Bakke, Gunnstein

    2010-07-01

    New legislation on the handling and storage of radioactive substances came into force 1 January 2011. This version of the report is updated to reflect this new regulation and will therefore in some chapters differ from the Norwegian version (see NEI-NO--1660). The Ministry of the Environment commissioned the Climate and Pollution Agency to examine the environmental impacts associated with the decommissioning of offshore installations (demolition and recycling). This has involved an assessment of the volumes and types of waste material and of decommissioning capacity in Norway now and in the future. This report also presents proposals for measures and instruments to address environmental and other concerns that arise in connection with the decommissioning of offshore installations. At present, Norway has four decommissioning facilities for offshore installations, three of which are currently involved in decommissioning projects. Waste treatment plants of this kind are required to hold permits under the Pollution Control Act. The permit system allows the pollution control authority to tailor the requirements in a specific permit by evaluating conditions and limits for releases of pollutants on a case-to-case basis, and the Act also provides for requirements to be tightened up in line with the development of best available techniques (BAT). The environmental risks posed by decommissioning facilities are much the same as those from process industries and other waste treatment plants that are regulated by means of individual permits. Strict requirements are intended to ensure that environmental and health concerns are taken into account. The review of the four Norwegian decommissioning facilities in connection with this report shows that the degree to which requirements need to be tightened up varies from one facility to another. The permit for the Vats yard is newest and contains the strictest conditions. The Climate and Pollution Agency recommends a number of measures

  11. On tentative decommissioning cost analysis with specific authentic cost calculations with the application of the Omega code on a case linked to the Intermediate storage facility for spent fuel in Sweden

    Energy Technology Data Exchange (ETDEWEB)

    Vasko, Marek; Daniska, Vladimir; Ondra, Frantisek; Bezak, Peter; Kristofova, Kristina; Tatransky, Peter; Zachar, Matej [DECOM Slovakia, spol. s.r.o., J. Bottu 2, SK-917 01 Trnava (Slovakia); Lindskog, Staffan [Swedish Nuclear Power Inspectorate, Stockholm (Sweden)

    2007-03-15

    The presented report is focused on tentative calculations of basic decommissioning parameters such as costs, manpower and exposure of personnel for activities of older nuclear facility decommissioning in Sweden represented by Intermediate storage facility for spent fuel in Studsvik, by means of calculation code OMEGA. This report continuously follows up two previous projects, which described methodology of cost estimates of decommissioning with an emphasis to derive cost functions for alpha contaminated material and implementation of the advanced decommissioning costing methodology for Intermediate Storage facility for Spent Fuel in Studsvik. The main purpose of the presented study is to demonstrate the trial application of the advanced costing methodology using OMEGA code for Intermediate Storage Facility for Spent Fuel in Studsvik. Basic work packages presented in report are as follows: 1. Analysis and validation input data on Intermediate Storage Facility for Spent Fuel and assemble a database suitable for standardised decommissioning cost calculations including radiological parameters, 2. Proposal of range of decommissioning calculations and define an extent of decommissioning activities, 3. Defining waste management scenarios for particular material waste streams from Intermediate Storage Facility for Spent Fuel, 4. Developing standardised cost calculation structure applied for Intermediate Storage Facility for Spent Fuel decommissioning calculation and 5. Performing tentative decommissioning calculations for Intermediate Storage Facility for Spent Fuel by OMEGA code. Calculated parameters of decommissioning are presented in structure according to Proposed Standardized List of Items for Costing Purposes. All parameters are documented and summed up in both table and graphic forms in text and Annexes. The presented report documents availability and applicability of methodology for evaluation of costs and other parameters of decommissioning in a form implemented

  12. On tentative decommissioning cost analysis with specific authentic cost calculations with the application of the Omega code on a case linked to the Intermediate storage facility for spent fuel in Sweden

    International Nuclear Information System (INIS)

    Vasko, Marek; Daniska, Vladimir; Ondra, Frantisek; Bezak, Peter; Kristofova, Kristina; Tatransky, Peter; Zachar, Matej; Lindskog, Staffan

    2007-03-01

    The presented report is focused on tentative calculations of basic decommissioning parameters such as costs, manpower and exposure of personnel for activities of older nuclear facility decommissioning in Sweden represented by Intermediate storage facility for spent fuel in Studsvik, by means of calculation code OMEGA. This report continuously follows up two previous projects, which described methodology of cost estimates of decommissioning with an emphasis to derive cost functions for alpha contaminated material and implementation of the advanced decommissioning costing methodology for Intermediate Storage facility for Spent Fuel in Studsvik. The main purpose of the presented study is to demonstrate the trial application of the advanced costing methodology using OMEGA code for Intermediate Storage Facility for Spent Fuel in Studsvik. Basic work packages presented in report are as follows: 1. Analysis and validation input data on Intermediate Storage Facility for Spent Fuel and assemble a database suitable for standardised decommissioning cost calculations including radiological parameters, 2. Proposal of range of decommissioning calculations and define an extent of decommissioning activities, 3. Defining waste management scenarios for particular material waste streams from Intermediate Storage Facility for Spent Fuel, 4. Developing standardised cost calculation structure applied for Intermediate Storage Facility for Spent Fuel decommissioning calculation and 5. Performing tentative decommissioning calculations for Intermediate Storage Facility for Spent Fuel by OMEGA code. Calculated parameters of decommissioning are presented in structure according to Proposed Standardized List of Items for Costing Purposes. All parameters are documented and summed up in both table and graphic forms in text and Annexes. The presented report documents availability and applicability of methodology for evaluation of costs and other parameters of decommissioning in a form implemented

  13. A study on people's awareness about the restarting and decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Goto, Manabu; Sakai, Yukimi

    2015-01-01

    In this study, we conducted two questionnaire surveys targeting a total of 918 respondents living in the cities of Kyoto, Osaka and Kobe, in order to elucidate people's awareness of three things: 1) restart of nuclear power plants; 2) extension of the operation period of aging plants; and 3) decommissioning. The results are as follows: 1) People who think that electrical power companies voluntarily take higher safety measures trust the power companies and do not oppose the restart of the nuclear power plants, as compared to people who think that power companies only meet the requirements set by the nuclear regulatory agency. 2) When people were given information about aging measures and conforming to new regulatory standards, their anxiety toward the operation of aging plants was reduced. 3) People thought that decommissioning work was important for society. However, a small number of people thought it was a job worthwhile doing. (author)

  14. A study on Prediction of Radioactive Source-term from the Decommissioning of Domestic NPPs by using CRUDTRAN Code

    Energy Technology Data Exchange (ETDEWEB)

    Song, Jong Soon; Lee, Sang Heon; Cho, Hoon Jo [Department of Nuclear Engineering Chosun University, Gwangju (Korea, Republic of)

    2016-10-15

    For the study, the behavior mechanism of corrosion products in the primary system of the Kori no.1 was analyzed, and the volume of activated corrosion products in the primary system was assessed based on domestic plant data with the CRUDTRAN code used to predict the volume. It is expected that the study would be utilized in predicting radiation exposure of workers performing maintenance and repairs in high radiation areas and in selecting the process of decontaminations and decommissioning in the primary system. It is also expected that in the future it would be used as the baseline data to estimate the volume of radioactive wastes when decommissioning a nuclear plant in the future, which would be an important criterion in setting the level of radioactive wastes used to compute the quantity of radioactive wastes. The results of prediction of the radioactive nuclide inventory in the primary system performed in this study would be used as baseline data for the estimation of the volume of radioactive wastes when decommissioning NPPs in the future. It is also expected that the data would be important criteria used to classify the level of radioactive wastes to calculate the volume. In addition, it is expected that the data would be utilized in reducing radiation exposure of workers in charge of system maintenance and repairing in high radiation zones and also predicting the selection of decontaminations and decommissioning processes in the primary systems. In future researches, it is planned to conduct the source term assessment against other NPP types such as CANDU and OPR-1000, in addition to the Westinghouse type nuclear plants.

  15. Study into the applicabilities of lasers for the dismantling of decommissioned nuclear power plant

    International Nuclear Information System (INIS)

    Haferkamp, H.; Bach, F.W.; Vinke, T.; Kinzel, A.; Mack, N.; Kuboschek, M.; Grobe, K.

    1989-01-01

    The project was intended to screen current laser technology for potential applications of laser beams in the dismantling of decommissioned nuclear power plant. As with CO 2 , Nd-YAG, or excimer lasers, developments clearly proceed towards higher output power. The market survey shows the CO 2 -laser to be the most efficient at present, with a great number of laser units available on the market in the range up to 5 kW, and some in the range up to 15 kW. The CO 2 -laser has exclusively been used so far for cutting work in steel plates thicker than 10 mm. Characteristic conditions of application include the high output power of more than 2 kW, long beam lengths, oxygen supply at strongly increased working pressure, sometimes from external sources. The maximum cutting work achieved in the laboratory was 110 mm in structural steel, 90 mm in austenitic steel, and 160 mm in concrete, all under conditions of easy access to the material. It remains to be examined whether steel cutting work at constrained positions will allow separation of wall thicknesses of more than 10 mm. Laser beam cutting under water is feasible in principle but has not been much studied yet. There also are only few sampling results of measurements of dust and aerosol quantities resulting from laser beam cutting work. (orig.) [de

  16. Ethics of nuclear decommissioning

    International Nuclear Information System (INIS)

    Surrey, John

    1992-01-01

    What to do with the numerous reactors that reach the end of their operating lives over the next 30 years involves ethical issues of an intergenerational kind. This essay examines various nuclear decommissioning options in the light of the ethical issues. Prompt dismantlement seems preferable to other options involving postponed dismantlement, entombment of some kind or doing nothing. It would avoid bequeathing future generations with the disamenity of entombed reactors or responsibility for dismantling other disused reactors. The choice of option also depends on the health risks through time and whether a sufficient decommissioning fund exists to avoid handing down debt and constrained choice. There is a strong case for supporting research and development from public funds to develop the technology and reduce both the health risks and the costs, especially if dismantlement is left to a future generation. (author)

  17. Decommissioning of Ukrainian NPPs

    International Nuclear Information System (INIS)

    Skripov, A.E.

    2002-01-01

    The decision about the development of 'Decommissioning Concept of Ukrainian NPPs' being on commercial operational stage was approved by NAEK 'Energoatom' Board of Administration by way of the decommissioning activity effective planning. The Concept will be the branch document, containing common approaches formulations on problem decisions according to the units decommissioning with generated resources, and RAW and SNF management strategy during decommissioning

  18. Needs for European decommissioning academy (EDA)

    International Nuclear Information System (INIS)

    Slugen, Vladimir

    2014-01-01

    According to analyses presented at EC meeting focused on decommissioning organized at 11.9.2012 in Brussels, it was stated that at least 500 new international experts for decommissioning will be needed in Europe up to 2025, which means about 35 per year. Having in mind the actual EHRO-N report from 2013 focused on operation of nuclear facilities and an assumption that the ratio between nuclear experts, nuclearized and nuclear aware people is comparable also for decommissioning, as well as the fact that the special study branch for decommissioning in the European countries almost does not exist, this European Decommissioning Academy (EDA) could be helpful in the over-bridging this gap. The main goal is - from about 74% of nuclearized experts (graduated at different technical Universities and increased their nuclear knowledge and skills mostly via on-job training and often in the area of NPP operation) to create nuclear experts for decommissioning via our post-gradual coursed organized in two semester study at our Academy, which will include the lessons, practical exercises in our laboratories, on-site training at NPP V-1 in Jaslovske Bohunice, Slovakia as well as 3 days technical tour to JAVYS (Slovakia), UJV Rez (Czech Rep.) and PURAM (Hungary), respectively. Beside the exams in selected topics (courses), the final thesis written under supervision of recognized experts will be the precondition for graduation and certification of the participants. For the first run of the EDA scheduled on 2014 we would like to focus on VVER decommissioning issues because this reactor type is the most distributed design in the world and many of these units are actually in decommissioning process or will be decommissioned in the near future in Europe. The growing decommissioning market creates a potential for new activities, with highly skilled jobs in an innovative field, involving high-level technologies. A clear global positioning of the EU will stimulate the export of know-how to

  19. CCA retention and its effects on the bonding performance of decommissioned treated wood: a preliminary study

    Science.gov (United States)

    Cheng Piao; Todd F. Shupe; Mark Gibson; Chung Y. Hse

    2009-01-01

    Chromated copper arsenate (CCA) continues to be widely used as a wood preservative for industrial uses in the U.S. Disposal of treated wood is a potential long-term environmental liability. Current practices for disposing of decommissioned preservative-treated wood include landfilling and incineration, which are increasingly impractical due to environmental...

  20. Considerations about the European Decommissioning Academy (EDA)

    International Nuclear Information System (INIS)

    Slugen, V.; Hinca, R.

    2014-01-01

    According to analyses presented at EC meeting focused on decommissioning organized at 11.9.2012 in Brussels, it was stated that at least 500 new international experts for decommissioning will be needed in Europe up to 2025, which means about 35 per year.Having in mind the actual EHRO-N report from 2013 focused on operation of nuclear facilities and an assumption that the ratio between nuclear experts, nuclearized and nuclear aware people is comparable also for decommissioning (16:74:10), as well as the fact that the special study branch for decommissioning in the European countries almost does not exist, this European Decommissioning Academy (EDA) could be helpful in the overbridging this gap.For the first run of the EDA scheduled on 2014 we would like to focus on VVER decommissioning issues because this reactor type is the most distributed design in the world and many of these units are actually in decommissioning process or will be decommissioned in the near future in Europe.A graduate of the European Decommissioning Academy (EDA) should have at least bachelor level from technical or natural science Universities or Colleges and at least one year working experiences in the area of NPP decommissioning or nuclear power engineering. This study creates prerequisites for acquiring and completion of professional and specialized knowledge in the subjects which are described. (authors)

  1. A model study of cost estimates of decontamination and decommissioning with an emphasis to derive cost functions for alpha contaminated material using OMEGA code

    Energy Technology Data Exchange (ETDEWEB)

    Kristofova, Kristina; Daniska, Vladimir; Ondra, Frantisek; Rehak, Ivan; Vasko, Marek [DECOM SLOVAKIA spol. s.r.o., Trnava (Slovakia)

    2004-12-01

    The presented study is focused on model decommissioning cost calculations for primary circuit of A-1 nuclear power plant in Jaslovske Bohunice. In addition, the survey of advanced decommissioning costing is included together with impact analyses of contamination on particular decommissioning parameters. OMEGA code decommissioning cost calculations for primary circuit of A-1 NPP presented in the study are performed and evaluated under the following conditions: different contamination level of inner and outer surfaces; different waste management scenarios; application and non-application of pre-dismantling decontamination; different start of decommissioning: 2004, 2010, 2020, 2030, 2040; radionuclide composition of primary circuit contamination in A-1 NPP with occurrence of alpha radionuclides and fission products as a consequence of operational accident with damaged fuel cladding; radionuclide composition of primary circuit contamination in V-2 NPP in Jaslovske Bohunice as a representative NPP with an operation without accidents and therefore neither non-alpha contaminants nor fission products are included. The results of all the above mentioned conditions impacts on calculated costs, manpower, exposure and distribution of materials arisen from decommissioning are evaluated in detail within the calculation sensitivity analysis.

  2. A model study of cost estimates of decontamination and decommissioning with an emphasis to derive cost functions for alpha-contaminated material using OMEGA code

    International Nuclear Information System (INIS)

    Kristofova, Kristina; Daniska, Vladimir; Ondra, Frantisek; Rehak, Ivan; Vasko, Marek

    2004-12-01

    The presented study is focused on model decommissioning cost calculations for primary circuit of A-1 nuclear power plant in Jaslovske Bohunice. In addition, the survey of advanced decommissioning costing is included together with impact analyses of contamination on particular decommissioning parameters. OMEGA code decommissioning cost calculations for primary circuit of A-1 NPP presented in the study are performed and evaluated under the following conditions: different contamination level of inner and outer surfaces; different waste management scenarios; application and non-application of pre-dismantling decontamination; different start of decommissioning: 2004, 2010, 2020, 2030, 2040; radionuclide composition of primary circuit contamination in A-1 NPP with occurrence of alpha radionuclides and fission products as a consequence of operational accident with damaged fuel cladding; radionuclide composition of primary circuit contamination in V-2 NPP in Jaslovske Bohunice as a representative NPP with an operation without accidents and therefore neither non-alpha contaminants nor fission products are included. The results of all the above mentioned conditions impacts on calculated costs, manpower, exposure and distribution of materials arisen from decommissioning are evaluated in detail within the calculation sensitivity analysis

  3. Decommissioning and demolition 1992

    International Nuclear Information System (INIS)

    Whyte, I.L.

    1992-01-01

    The decommissioning and demolition of structures offshore, onshore and in nuclear works involves new technologies and industries in demolition and removal. The aim of the conference was to provide a forum to keep up to date with technological developments, to publicise new techniques and to share and discuss present and future plans. A particular feature was the multi-disciplinary approach to promote and encourage communication between different sectors of this difficult field of operations. The conference emphasised not only technical issues but also legislative, management and health and safety aspects. Papers were presented by practising engineers, contractors and research workers involved in offshore structures, buildings, power stations, contaminated sites, nuclear plant and includes specialist techniques of cutting, lifting, explosives, ground treatment and decontamination. Many valuable case histories and records based on practical experience were reported. The volume provides a reference source on the state-of-the-art in decommissioning and demolition. The ten papers relevant to the decommissioning and demolition of nuclear facilities are indexed separately. (Author)

  4. Comments on the feasibility studies concerning the decommissioning options LAW retrieval, relocation and backfilling for the Asse facility with respect to the applicability of the BfS evaluation criteria

    International Nuclear Information System (INIS)

    Alt, Stefan; Kallenbach-Herbert, Beate; Neles, Julia

    2009-01-01

    The comments on the feasibility studies cover the decommissioning options LAW retrieval, relocation and backfilling for the Asse facility with respect to the applicability of the BfS evaluation criteria. The respective BfS criteria include the evaluation with respect to the safety during the operational phase, the environmental impacts in case of an uncontrollable brine intrusion; the preliminary long-term safety assessment; the feasibility; and the time required.

  5. Lessons learned from the decommissioning process affected by an accident during operation. The case of A1 NPP in Slovakia

    International Nuclear Information System (INIS)

    Daniska, Vladimir; Timulak, Jan; Pekar, Anton; Niznansky, Vojtech; Konecny, Ladislav

    2007-01-01

    Decommissioning of NPP's with standard shutdown is currently well known process. The A1 NPP in Slovakia was shutdown in 1977 after the accident in the core which caused the damage of the fuel and contamination of systems. Long period from 1977 to 2008 was needed to manage issues resulting from affecting the systems and structures of A1 NPP and the environment by the accident. Management of the damaged spent fuel, decontamination of the primary circuit and other processes generated large amounts of alpha bearing waste, mostly liquid, having sludge phases with specific physical-chemical and radiological properties. Up to 1994, the approach for eliminating the consequences of the accident was based on safety priorities. The systematic approach, which includes also the rehabilitation of the affected environment, was implemented in the period 1994-2008. The process includes also establishing of the decommissioning infrastructure, legislative and funding system with the aim to implement the standard decommissioning procedures after 2008. However, the specific aspects, especially the level and radio-nuclide composition of contamination of systems and structures will remain. For final decommissioning 2008-2033, the approach was selected which foresees four licensed phases. This approach enables proper planning and performing of individual decommissioning phases. (authors)

  6. On Cost Estimate for Decommissioning of one Isotope Central

    International Nuclear Information System (INIS)

    Marek Vasko et al

    2010-08-01

    The main scope of this study has been to calculate the future cost for decommission and dismantling the Isotope central at the Studsvik site using the OMEGA CODE. Detailed empirical information is used in the study for 'bench-marking' purposes, in such cases when there is a need to supplement and correct field data from the industry. In the present study, data has been retrieved and organized such that the estimated costs for decommissioning of the Isotope Central become transparent and reliable. This approach gives a preliminary qualitative indication about the accuracy of the cost estimate delivered by the industry

  7. On Cost Estimate for Decommissioning of one Isotope Central

    Energy Technology Data Exchange (ETDEWEB)

    Marek Vasko et al

    2010-08-15

    The main scope of this study has been to calculate the future cost for decommission and dismantling the Isotope central at the Studsvik site using the OMEGA CODE. Detailed empirical information is used in the study for 'bench-marking' purposes, in such cases when there is a need to supplement and correct field data from the industry. In the present study, data has been retrieved and organized such that the estimated costs for decommissioning of the Isotope Central become transparent and reliable. This approach gives a preliminary qualitative indication about the accuracy of the cost estimate delivered by the industry

  8. Study concerning decommissioning of nuclear facilities overseen by the IAEA in the United States and major European countries

    International Nuclear Information System (INIS)

    Hirashima, Shikazoh

    1983-01-01

    The purpose of this investigation was to know generally on the activities of decommissioning nuclear facilities in the IAEA, and to compare the regulation and finance concerning reactor decommissioning in European countries and the United States together with the decommissioning policy and the status of research and development. Recently also in Japan, attention has been paid to reactor decommissioning after the termination of operation, and the report by the Decommissioning Countermeasures Committee was published in March, 1981. In the IAEA, the investigation of Reactor decommissioning has been performed since 1973, and the meetings of the technical committee in 1975 and 1977, the international symposium in 1978, and the publication of ''Various factors concerning the decommissioning of inland nuclear facilities'' in 1980 were held. The regulation and finance concerning the decommissioning have been performed differently in each country, and the features of the main policy of decommissioning are indicated. In foreign countries, the measures of account for the decommissioning expenses have been already taken. In Japan, it is desirable to establish the technical standard for the decommissioning including legislation and finance. (Kako, I.)

  9. Evaluating decommissioning costs for nuclear power plants

    International Nuclear Information System (INIS)

    MacDonald, R.R.

    1980-01-01

    An overview is presented of the economic aspects of decommissioning of large nuclear power plants in an attempt to put the subject in proper perspective. This is accomplished by first surveying the work that has been done to date in evaluating the requirements for decommissioning. A review is presented of the current concepts of decommissioning and a discussion of a few of the uncertainties involved. This study identifies the key factors to be considered in the econmic evaluation of decommissioning alternatives and highlights areas in which further study appears to be desirable. 12 refs

  10. Development of an integrated cost model for nuclear plant decommissioning

    International Nuclear Information System (INIS)

    Amos, G.; Roy, R.

    2003-01-01

    A need for an integrated cost estimating tool for nuclear decommissioning and associated waste processing and storage facilities for Intermediate Level Waste (ILW) was defined during the authors recent MSc studies. In order to close the defined gap a prototype tool was developed using logically derived CER's and cost driver variables. The challenge in developing this was to be able to produce a model that could produce realistic cost estimates from the limited levels of historic cost data that was available for analysis. The model is an excel based tool supported by 3 point risk estimating output and is suitable for producing estimates for strategic or optional cost estimates (±30%) early in the conceptual stage of a decommissioning project. The model was validated using minimal numbers of case studies supported by expert opinion discussion. The model provides an enhanced approach for integrated decommissioning estimates which will be produced concurrently with strategic options analysis on a nuclear site

  11. Investigation Study on Gamma Ray Imaging Technology for Nuclear Power Plant Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Sang Guk; Jeong, Woo Tae [Machinery and Materials Laboratory, Korea Hydro and Nuclear Power Co., Daejeon (Korea, Republic of)

    2014-10-15

    The gamma ray imaging system provides an estimated dose-rate of the source at 30 cm above. The gamma detector is a terbium activated glass scintillator. The system is capable of producing a color two dimensional image of a radiation field superimposed on a black and white visual image. The system used in US power plants consists of a portable sensor head that contains both gamma ray and visual imaging systems and a portable control computer. The gamma ray imaging system has been successfully used as an ALARA tool for identifying source terms and determining the adequacy of existing shielding. Because the control system can be positioned away from the camera, the radiation exposure to personnel can be reduced without extensive shielding requirements. The gamma ray imaging system has been used to date in the decommissioning of Maine Yankee, Big Rock point,Trojan, San Onofre1, and Millstone 1. The equipment has also been used at normal refueling outages at a number of commercial nuclear power plants and at several Department of Energy Decommissioning sites. This paper is intended to review the applicability of gamma ray imaging system as decommissioning tool. In order to review the actual applicability, we are going to introduce applications for US power plants.

  12. Decommissioning Trawsfynydd - How public consultation shaped the strategy

    Energy Technology Data Exchange (ETDEWEB)

    Kay, Martin J [Nuclear Electric plc. (United Kingdom)

    1995-07-01

    This case study discusses the ned of consulting the public when decommissioning a nuclear power plants. When Trawsfynydd power station in North Wales shutdown in July 1993, Nuclear Electric's strategy for decommissioning its stations was not clearly defined. The company had altered its corporate policy on decommissioning fro he strategy referred to as the 'Reference Case' which had been approved by the Government, to the preferred 'Deferred Safestore' strategy, which was waiting Government approval. Deferred Safestore is preferred as it simplifies the engineering work involved by capitalising an the basic strength and integrity of the reactor building. It minimises thd radiation exposure to workers and radioactivity released to the environment, reduces the amount of radioactive waste produced and significantly cuts the total decommissioning cost. The closure and the decommissioning of Trawsfynydd power station was a sensitive issue as: The station lies within a National Park of outstanding beauty. The economic circumstances in the area are such that employment opportunities are very limited. At a crucial time when the company was approaching a Government review which would decide its future, Nuclear Electric could not afford to lose any credibility. A public consultation programme was launched in the vicinity of the power station To gauge the reactions of the public and elected local government bodies to a series of decommissioning options. Nuclear Electric presented three main options with details on the employment opportunities, the costs, and the lorry loads of material involved with each. The people were identified on whom decommissioning Trawsfynydd power station is likely to have an environmental or socioeconomic impact. As a result of the polls the Nuclear Electric received feedback in two ways. Formal feedback from the local councils Independent analysis of the completed questionnaires. The company was wholly committed to a meaningful consultation. Before

  13. Decommissioning Trawsfynydd - How public consultation shaped the strategy

    International Nuclear Information System (INIS)

    Kay, Martin J.

    1995-01-01

    This case study discusses the ned of consulting the public when decommissioning a nuclear power plants. When Trawsfynydd power station in North Wales shutdown in July 1993, Nuclear Electric's strategy for decommissioning its stations was not clearly defined. The company had altered its corporate policy on decommissioning fro he strategy referred to as the 'Reference Case' which had been approved by the Government, to the preferred 'Deferred Safestore' strategy, which was waiting Government approval. Deferred Safestore is preferred as it simplifies the engineering work involved by capitalising an the basic strength and integrity of the reactor building. It minimises thd radiation exposure to workers and radioactivity released to the environment, reduces the amount of radioactive waste produced and significantly cuts the total decommissioning cost. The closure and the decommissioning of Trawsfynydd power station was a sensitive issue as: The station lies within a National Park of outstanding beauty. The economic circumstances in the area are such that employment opportunities are very limited. At a crucial time when the company was approaching a Government review which would decide its future, Nuclear Electric could not afford to lose any credibility. A public consultation programme was launched in the vicinity of the power station To gauge the reactions of the public and elected local government bodies to a series of decommissioning options. Nuclear Electric presented three main options with details on the employment opportunities, the costs, and the lorry loads of material involved with each. The people were identified on whom decommissioning Trawsfynydd power station is likely to have an environmental or socioeconomic impact. As a result of the polls the Nuclear Electric received feedback in two ways. Formal feedback from the local councils Independent analysis of the completed questionnaires. The company was wholly committed to a meaningful consultation. Before

  14. Utility planning for decommissioning

    International Nuclear Information System (INIS)

    Williams, D.H.

    1982-01-01

    Though the biggest impact on a utility of nuclear power plant decommissioning may occur many years from now, procrastination of efforts to be prepared for that time is unwarranted. Foresight put into action through planning can significantly affect that impact. Financial planning can assure the recovery of decommissioning costs in a manner equitable to customers. Decision-making planning can minimize adverse affects of current decisions on later decommissioning impacts and prepare a utility to be equipped to make later decommissioning decisions. Technological knowledge base planning can support all other planning aspects for decommissioning and prepare a utility for decommissioning decisions. Informed project planning can ward off potentially significant pitfalls during decommissioning and optimize the effectiveness of the actual decommissioning efforts

  15. CASE STUDY

    African Journals Online (AJOL)

    2011-06-02

    Jun 2, 2011 ... immunosuppression associated with HIV/AIDS puts them at a higher risk of developing oesophageal cancer. 47. CASE STUDY. A 49-year-old man was diagnosed as HIV infected, with a CD4 count of 60 cells/µl. He was started on an antiretroviral treatment regimen comprising zidovudine, lamivudine and ...

  16. Decommissioning and decontamination

    International Nuclear Information System (INIS)

    Dadoumont, J.; Cantrel, E.; Valenduc, P.; Noynaert, L.

    2009-01-01

    The SCK-CEN has built a large know-how in decommissioning and decontamination, thanks to its BR3 decommissioning project. In 2007, the decommissioning activities at BR3 have been continued according to the strategy. This article discusses main realisations the following domains: decommissioning of the neutron shield tank and installation of new ventilation for the controlled area, dismantling of the former one and characterization of the stack

  17. Optimizing decommissioning and waste management

    International Nuclear Information System (INIS)

    McKeown, J.

    2000-01-01

    UKAEA has clarified its future purpose. It is a nuclear environmental restoration business. Its proud history of being at the forefront of nuclear research now provides decommissioning challenges of unique breadth. The methods employed, and in some cases developed, by UKAEA to assist in the optimization of its overall work programme are identified. (author)

  18. Cost estimation for decommissioning of research reactors

    International Nuclear Information System (INIS)

    Grossi, Pablo Andrade; Tello, Cledola Cassia Oliveira de; Segabinaze, Roberto de Oliveira; Daniska, Vladimir

    2013-01-01

    In the case of research reactors, the limited data that is available tends to provide only overall decommissioning costs, without any breakdown of the main cost elements. In order to address this subject, it is important to collect and analyse all available data of decommissioning costs for the research reactors. The IAEA has started the DACCORD Project focused on data analysis and costing of research reactors decommissioning. Data collection is organized in accordance with the International Structure for Decommissioning Costing (ISDC), developed jointly by the IAEA, the OECD Nuclear Energy Agency and the European Commission. The specific aims of the project include the development of representative and comparative data and datasets for preliminary costing for decommissioning. This paper will focus on presenting a technique to consider several representative input data in accordance with the ISDC structure and using the CERREX (Cost Estimation for Research Reactors in Excel) software developed by IAEA. (author)

  19. Studies on decommissioning of TRIGA reactors and site restoration technologies in the Republic of Korea

    International Nuclear Information System (INIS)

    Oh, Won-Zin; Kim, Gye-Nam; Won, Hui-Jun

    2002-01-01

    Research and development on research reactor decommissioning and environmental restoration has been carried out at KAERI since 1997 to prepare for the decommissioning of KAERI's two TRIGA-type research reactors, which had been shut down since 1995. A 3-D graphic model of the TRIGA research reactor was built using IGRIP. The dismantling process was simulated in the graphic environment to verify the feasibility of individual operations before the execution of the remote dismantling process. An under-water wall-climbing robot, moving by propeller injection, and identifying its coordinates by using a laser sensor, was developed and tested in the TRIGA reactor pool by measuring a radioactive contamination map of the reactor surface. Using MODFLOW and TRIGA site geological data, a computer simulation of the underground migration of residual radionuclides, after the TRIGA reactor decommissioning, was carried out. It was found that the underground migration rate was very slow such that, when radionuclide decay and dilution are considered, the residual radionuclides will not have a significant environmental impact. The soil decontamination R and D, using soil washing, solvent flushing and electro-decontamination technologies, was carried out to determine the best method for decontaminating the soil waste accumulated in KAERI. The decontamination results indicated that, using the soil washing method, more than 80% of the soil wastes could be decontaminated well enough to discharge them to the environment. It was also determined that the control of solution pH and temperature in the soil washing process is important for the reduction of decontamination waste. Further decontamination, using an electro-kinetic decontamination method, was considered necessary for the residual soil waste, which consisted mainly of fine soil particles. (author)

  20. Preliminary study of the environmental radiological assessment for the Garigliano nuclear power plant decommissioning

    International Nuclear Information System (INIS)

    Esposito, A.M.; Sabbarese, C.; Sirignano, C.; Visciano, L.; D'Onofrio, A.D.; Lubritto, C.; Terrasi, F.

    2002-01-01

    In the last few years many nuclear installations in the world have been stopped either because they reached the end of production lifetime, or for operation problems or, like in Italy, for political decisions. This stop started the decommissioning procedure. It consists in the dismantling of the nuclear installation with appropriate controls and limitations of environmental and radiological impact which arises from these operations. The evaluation of risk and the actions needed for the population safeguard are generally inspired to the recommendations of the International Commission on Radiological Protection (ICRP), but each country faces the problem with different evaluation methodologies and calculations. That is due to different laws and environmental, social and economical context where nuclear installations are located. For this, the decommissioning operations must be separately evaluated for each nuclear installation. In this paper, we present the work carried out so far about the decommissioning of the Nuclear Power Plant of Garigliano (Caserta, Italy), which is managed by SoGIN (Societa di Gestione degli Impianti Nucleari). This Nuclear Power Plant began its activity in 1964 by using a boiling water reactor with a production of 160 MW electric power. In 1979 this nuclear installation was stopped for maintenance and operation has not been resumed until the referendum in 1986, after which all Italian nuclear plants were stopped. Now, the Nuclear Power Plant of Garigliano has the reactor isolated respect to the remaining part and all components and pipes have been drained and sealed. The underground tanks of radioactive wastes have been evacuated and decontaminated. The radioactive wastes have been completely conditioned with cementification in drums suitable to prevent outside release

  1. National waste terminal storage repository in a bedded salt formation for spent unreprocessed fuel. Special study No. 1. Twenty-five-year retrievability, decommissioning cost estimate

    International Nuclear Information System (INIS)

    1978-11-01

    This estimate covers decommissioning costs of facilities for the receipt, handling, and storage in bedded salt of canistered spent fuel assemblies from both BWR and PWR commercial power plants. The estimate includes all decommissioning costs for a repository, based on 25-year retrievability, constructed in accordance with the design shown in Conceptual Design Report (CDR), as modified by Special Study No. 1 (KE Report No. 78-60-RE) and decommissioned in accordance with the program outlined in the Conceptual Design Description Report, KE Report No. 78-58-R. Costs for Operating Contractor personnel on the site at this time are included in this report and not in the Operating Cost Estimate (KE Report 78-63-RE). The operating cost estimates end with the completion of storage room backfilling. The three major elements of decommissioning are: demolition of surface facilities, backfilling of main entries and airways, and shaft liner removal and shaft plugging. EDIT, ECON, and DELOX computer programs and a chart of accounts were furnished by UCC-ND under direction of the Government and the line item-capital-cost estimate was prepared according to the prescribed format. The decommissioning cost estimate referenced herein is in the same format as its companion line item-capital-cost estimate KE Report 78-62-RE

  2. Measuring and reporting on decommissioning progress

    International Nuclear Information System (INIS)

    Lange, B.A.

    2006-01-01

    One of the challenges facing AECL, as well as other organizations charged with the responsibility of decommissioning nuclear facilities, is the means by which to measure and report on decommissioning progress to various audiences which, in some cases, may only have a peripheral knowledge or understanding of the complexities associated with the decommissioning process. The reporting and measurement of decommissioning progress is important for a number of reasons, i.e., It provides a vehicle by which to effectively communicate the nature of the decommissioning process; It ensures that stakeholders and shareholders are provided with a transparent and understandable means for assessing value for money; It provides a means by which to integrate the planning, measurement, and operational aspects of decommissioning One underlying reason behind the challenge of reporting decommissioning progress lies in the fact that decommissioning programs are generally executed over periods of time that far exceed those generally associated with typical design and build projects. For example, a decommissioning program could take decades to complete in which case progress on the order of a few percent in any one year might be typical. However, such progress may appear low compared to that seen with more typical projects that can be completed in a matter of years. As a consequence, AECL undertook to develop a system by which to measure decommissioning progress in a straightforward, meaningful, and understandable fashion. The system is not rigorously objective, and there are subjective aspects that are necessitated by the need to keep the system readily understandable. It is also important to note that while the system is simple in concept, there is, nonetheless, significant effort involved in generating and updating the parameters used as input, and in the actual calculations. (author)

  3. Criteria for decommissioning

    International Nuclear Information System (INIS)

    Ricci, P.F.

    1988-01-01

    In this paper the authors describe three risk acceptability criteria as parts of a strategy to clean up decommissioned facilities, related to both the status quo and to a variety of alternative technical clean-up options. The acceptability of risk is a consideration that must enter into any decision to establish when a site is properly decommissioned. To do so, both the corporate and public aspects of the acceptability issue must be considered. The reasons for discussion the acceptability of risk are to: Legitimize the process for making cleanup decisions; Determine who is at risk, who benefits, and who bears the costs of site cleanup, for each specific cleanup option, including the do nothing option; Establish those factors that, taken as a whole, determine measures of acceptability; Determine chemical-specific aggregate and individual risk levels; and Establish levels for cleanup. The choice of these reasons is pragmatic. The method consistent with these factors is risk-risk-effectiveness: the level of cleanup must be consistent with the foreseeable use of the site and budget constraints. Natural background contamination is the level below which further cleanup is generally inefficient. Case-by-case departures from natural background are to be considered depending on demonstrated risk. For example, a hot spot is obviously a prima facie exception, but should be rebuttable. Rebuttability means that, through consensus, the ''hot spot'' is shown not to be associated with exposure

  4. Large transport packages for decommissioning waste

    International Nuclear Information System (INIS)

    Price, M.S.T.

    1988-03-01

    The main tasks performed during the period related to the influence of manufacture, transport and disposal on the design of such packages. It is deduced that decommissioning wastes will be transported under the IAEA Transport Regulations under either the Type B or Low Specific Activity (LSA) categories. If the LSA packages are self-shielded, reinforced concrete is the preferred material of construction. But the high cost of disposal implies that there is a strong reason to investigate the use of returnable shields for LSA packages and in such cases they are likely to be made of ferrous metal. Economic considerations favour the use of spheroidal graphite cast iron for this purpose. Transport operating hazards have been investigated using a mixture of desk studies, routes surveys and operations data from the railway organisations. Reference routes were chosen in the Federal Republic of Germany, France and the United Kingdom. This work has led to a description of ten accident scenarios and an evaluation of the associated accident probabilities. The effect of disposal on design of packages has been assessed in terms of the radiological impact of decommissioning wastes, an in addition corrosion and gas evolution have been examined. The inventory of radionuclides in a decommissioning waste package has low environmental impact. If metal clad reinforced concrete packages are to be used, the amount of gas evolution is such that a vent would need to be included in the design. Similar unclad packages would be sufficiently permeable to gases to prevent a pressure build-up. (author)

  5. Economic aspects of decommissioning

    International Nuclear Information System (INIS)

    Jenne, C.

    1988-01-01

    Two viewpoints on decommissioning are quoted; the first suggests that decommissioning can be viewed as a technical detail that is of limited relevance whereas the second suggests that decommissioning is a key financial issue. Both are specifically relevant to United Kingdom nuclear power stations. This paper attempts to reconcile the two views. It suggests that decommissioning does raise some important issues for regulation and financing of a privatised industry but, despite this, the economics of nuclear do remain insensitive. The paper begins by examining the significance of decommissioning costs in a number of contexts, including nuclear unit generating costs and financing requirements. It then addresses the degree of uncertainty in the decommissioning cost estimates. With privatisation on the horizon, the paper considers the significance of decommissioning and the associated uncertainty for the investor; this last section considers regulatory issues raised in relation to funding, accounting policy and electricity pricing. (author)

  6. Study on the evaluation of decontamination and decommissioning technologies and their demands in Korea

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Won Zin; Lee, K. W.; Jung, C. H.; Choi, W. K.; Won, H. J.; Kim, G. N.; Jung, K. J.; Chung, U. S.; Lee, D. G.; Kim, C. J.; Kim, S. H.; Chung, J. M.; Kwon, S. O. [Korea Atomic Energy Research Institute, Taejeon (Korea)

    2001-03-01

    D and D market demand, the current status of the technology, technology items applicable to the domestic market and the future prospect of technologies not self-developed in Korea were evaluated. In the evaluation of D and D market demand and the current status of the technology, 1) the market demand was investigated on the D and D objects such as the research reactors, the nuclear power plants and the nuclear fuel cycle development facilities from 2001 to 2010, and 2) the technology demand for decommissioning of the nuclear power plants from 2001 to 2030 were investigated. In the evaluation of the technology items applicable to the domestic market, 1) the analysis of the technologies derived from the technology requirements on D and D objects and their related similar technologies was performed, and 2) the technology items applicable to the domestic market were derived from the evaluation of the suitability on the domestic technology requirements. The promising technologies applicable to the domestic market were derived from the integrated evaluation of the technological factors(innovation, internationally competitive power and the difficulty of the technology development), economical factors (domestic demand and substitution effect of foreign currency) and domestically applicable factors (applicability on the industry and a ripple effect). The background of the technology development such as business applicability and the technology demonstration effect through the integrated management of the decommissioning of TRIGA reactor and the uranium conversion facility was also analyzed. 10 refs., 9 figs., 28 tabs. (Author)

  7. Estimated long lived isotope activities in ET-RR-1 reactor structural materials for decommissioning study

    International Nuclear Information System (INIS)

    Ashoub, N.; Saleh, H.

    1995-01-01

    The first Egyptian research reactor, ET-RR-1 is tank type with light water as a moderator, coolant and reflector. Its nominal power is 2MWt and the average thermal neutron flux is 10 13 n/cm 2 sec -1 . Its criticality was on the fall of 1961. The reactor went through several modifications and updating and is still utilized for experimental research. A plan for decommissioning of ET-RR-1 reactor should include estimation of radioactivity in structural materials. The inventory will help in assessing the radiological consequences of decommissioning. This paper presents a conservative calculation to estimate the activity of the long lived isotopes which can be produced by neutron activation. The materials which are presented in significant quantities in the reactor structural materials are aluminum, cast iron, graphite, ordinary and iron shot concrete. The radioactivity of each component is dependent not only upon the major elements, but also on the concentration of the trace elements. The main radioactive inventory are expected to be from 60 Co and 55 Fe which are presented in aluminium as trace elements and in large quantities in other construction materials. (author)

  8. Technical and cost aspects of radioactive wastes from decommissioning

    International Nuclear Information System (INIS)

    Claes, J.; Menon, S.

    2001-01-01

    The OECD Nuclear Energy Agency's Co-operative Programme on Decommissioning was established in 1985 to share the experience and information emerging from on-going decommissioning projects within member countries. The main aim of the programme is to gather and collate such data, which can then provide the basis for planning the future industrial phase of decommissioning of commercial nuclear plants. Starting with 10 decommissioning projects in 1985, today the programme has 35 participating projects from 12 countries. Apart from exchanging valuable information, task groups have been set up for in-depth analysis and studies of areas of common interest, among which are the recycling of material from decommissioning projects and decommissioning costs. This paper will describe the structure and mode of operation of the programme. Some of the results of the work in the task groups will be presented, with particular emphasis on the management of materials from decommissioning and on decommissioning costs. (author)

  9. The IAEA Safety Regime for Decommissioning

    International Nuclear Information System (INIS)

    Bell, M.J.

    2002-01-01

    Full text of publication follows: The International Atomic Energy Agency is developing an international framework for decommissioning of nuclear facilities that consists of the Joint Convention on the Safety of Spent Fuel Management and the Safety of Radioactive Waste Management, and a hierarchy of Safety Standards applicable to decommissioning. The Joint Convention entered into force on 18 June 2001 and as of December 2001 had been ratified by 27 IAEA Member States. The Joint Convention contains a number of articles dealing with planning for, financing, staffing and record keeping for decommissioning. The Joint Convention requires Contracting Parties to apply the same operational radiation protection criteria, discharge limits and criteria for controlling unplanned releases during decommissioning that are applied during operations. The IAEA has issued Safety Requirements document and three Safety Guides applicable to decommissioning of facilities. The Safety Requirements document, WS-R-2, Pre-disposal Management of Radioactive Waste, including Decommissioning, contains requirements applicable to regulatory control, planning and funding, management of radioactive waste, quality assurance, and environmental and safety assessment of the decommissioning process. The three Safety Guides are WS-G-2.1, Decommissioning of Nuclear Power Plants and Research Reactors, WS-G-2.2, Decommissioning of Medical, Industrial and Research Facilities, an WS-G-2.4, Decommissioning of Nuclear Fuel Cycle Facilities. They contain guidance on how to meet the requirements of WS-R-2 applicable to decommissioning of specific types of facilities. These Standards contain only general requirements and guidance relative to safety assessment and do not contain details regarding the content of the safety case. More detailed guidance will be published in future Safety Reports currently in preparation within the Waste Safety Section of the IAEA. Because much material arising during the decommissioning

  10. A state-of-the art on decommissioning of nuclear facilities in Japan

    International Nuclear Information System (INIS)

    Park, Seung Kook; Kim, Hee Reyoung; Chung, Un Soo; Jung, Ki Jung

    2002-05-01

    While proceeding the KRR-1 and 2 decommissioning project, we are carried out study for the state of the art on decommissioning of nuclear facilities in Japan. Also, we are studied for the research reactors and commercial power plant that has the object of decommissioning, and for the government and the organization related on decommissioning operation. We are investigated for decommissioning activities of nuclear facilities achieved by JAERI, and collected the information and data for decommissioning techniques and computational system through the JPDR(Japan Power Demonstration Reactor) decommissioning activities. Such techniques are applying for Tokai Power Station began the decommissioning project from last year, and for Fugen Nuclear Power Station to be planned the decommissioning from 2003. Recent techniques for decommissioning was acquired by direct contact. The status of the treatment for decommissioning waste and the disposal facility for the very low-level radioactive concrete wastes was grasped

  11. Financial aspects of decommissioning (key aspects of decommissioning costing)

    International Nuclear Information System (INIS)

    Danska, V.

    2009-01-01

    In this presentation the following aspects of NPPs decommissioning are discussed: Requirements and purpose of decommissioning costing; Decommissioning costing methodologies; Standardised decommissioning cost structure; Input data for cost estimate process; Waste management in cost estimate process; Grading aspects in cost estimating; Cost control in decommissioning projects; Summary of the cost estimation process; Conclusions and recommendations.

  12. Integrated approach to planning the remediation of sites undergoing decommissioning

    International Nuclear Information System (INIS)

    2009-01-01

    Responding to the needs of Member States, the IAEA has launched an environmental remediation guidance initiative dealing with the issues of radioactive contamination world wide. Its aim is to collate and disseminate information concerning the key issues affecting environmental remediation of contaminated sites. This IAEA initiative includes the development of documents that report on remediation technologies available, best practices, and information and guidance concerning (a) Strategy development for environmental remediation; (b) Characterization and remediation of contaminated sites and contaminated groundwater; (c) Management of waste and residues from mining and milling of uranium and thorium; (d) Decommissioning of buildings; (e) A database for contaminated sites. The subject of this present report concerns the integration of decommissioning and remediation activities at sites undergoing decommissioning and this fits within the first category of guidance documentation (strategy development). This document addresses key strategic planning issues. It is intended to provide practical advice and complement other reports that focus on decommissioning and remediation at nuclear facilities. The document is designed to encourage site remediation activities that take advantage of synergies with decommissioning in order to reduce the duplication of effort by various parties and minimize adverse impacts on human health, the environment, and costs through the transfer of experience and knowledge. To achieve this objective, the document is designed to help Member States gain perspective by summarizing available information about synergies between decommissioning and remediation, strategic planning and project management and planning tools and techniques to support decision making and remediation. Case studies are also presented as to give concrete examples of the theoretical elements elaborated in the documents. This publication investigates the potential synergies

  13. Casing study

    Energy Technology Data Exchange (ETDEWEB)

    Roche, P.

    2000-12-01

    An unorthodox method of casing drilling used by Tesco Corporation at a gas well in Wyoming to drill deeper using casings as drillpipe is discussed. The process involves either rotating the casing as drill string or using a downhole mud motor to rotate the bit. In this instance, the surface hole and the production hole were casing-drilled to a record 8,312 feet by rotating the casing. The 8 1/2-inch surface hole was drilled with 7-inch casing to 1,200 feet using a Tesco underreamer and a polycrystalline pilot bit; drilling and cementing was completed in 12 1/2 hours. The 6 1/4-inch production hole was drilled with 4 1/2-inch casing and the bottomhole assembly was retrieved after 191 hours rotating. This case was the first in which the entire well was casing-drilled from surface to TD. Penetration rate compared favorably with conventional methods: 12 1/2 hours for casing-drilling to 18.9 hours for conventional drilling, despite the fact that the casing-drilling technology is still in its infancy. It is suggested that casing-drilling has the potential to eliminate the need for the drillpipe entirely. If these expectations were to be realised, casing-drilling could be one of the most radical drilling changes in the history of the oil and gas industry. 1 photo.

  14. A database structure for radiological optimization analyses of decommissioning operations

    International Nuclear Information System (INIS)

    Zeevaert, T.; Van de Walle, B.

    1995-09-01

    The structure of a database for decommissioning experiences is described. Radiological optimization is a major radiation protection principle in practices and interventions, involving radiological protection factors, economic costs, social factors. An important lack of knowledge with respect to these factors exists in the domain of the decommissioning of nuclear power plants, due to the low number of decommissioning operations already performed. Moreover, decommissioning takes place only once for a installation. Tasks, techniques, and procedures are in most cases rather specific, limiting the use of past experiences in the radiological optimization analyses of new decommissioning operations. Therefore, it is important that relevant data or information be acquired from decommissioning experiences. These data have to be stored in a database in a way they can be used efficiently in ALARA analyses of future decommissioning activities

  15. A study on source term assessment and waste disposal requirement of decontamination and decommissioning for the TRIGA research reactor

    Energy Technology Data Exchange (ETDEWEB)

    Whang, Joo Ho; Lee, Kyung JIn; Lee, Jae Min; Choi, Gyu Seup; Shin, Byoung Sun [Kyunghee Univ., Seoul (Korea, Republic of)

    1999-08-15

    The objective and necessity of the project : TRIGA is the first nuclear facility that decide to decommission and decontamination in our nation. As we estimate the expected life of nuclear power generation at 30 or 40 years, the decommissioning business should be conducted around 2010, and the development of regulatory technique supporting it should be developed previously. From a view of decommissioning and decontamination, the research reactor is just small in scale but it include all decommissioning and decontamination conditions. So, the rules by regulatory authority with decommissioning will be a guide for nuclear power plant in the future. The basis of regulatory technique required when decommissioning the research reactor are the radiological safety security and the data for it. The source term is very important condition not only for security of worker but for evaluating how we dispose the waste is appropriate for conducting the middle store and the procedure after it when the final disposal is considered. The content and the scope in this report contain the procedure of conducting the assessment of the source term which is most important in understanding the general concept of the decommissioning procedure of the decommissioning and decontamination of TRIGA research reactor. That is, the sampling and measuring method is presented as how to measure the volume of the radioactivity of the nuclear facilities. And also, the criterion of classifying the waste occurred in other countries and the site release criteria which is the final step of decommissioning and decontamination presented through MARSSIM. Finally, the program to be applicable through comparing the methods of our nation and other countries ones is presented as plan for disposal of the waste in the decommissioning.

  16. Nuclear power plant decommissioning

    International Nuclear Information System (INIS)

    Yaziz Yunus

    1986-01-01

    A number of issues have to be taken into account before the introduction of any nuclear power plant in any country. These issues include reactor safety (site and operational), waste disposal and, lastly, the decommissioning of the reactor inself. Because of the radioactive nature of the components, nuclear power plants require a different approach to decommission compared to other plants. Until recently, issues on reactor safety and waste disposal were the main topics discussed. As for reactor decommissioning, the debates have been academic until now. Although reactors have operated for 25 years, decommissioning of retired reactors has simply not been fully planned. But the Shippingport Atomic Power Plant in Pennysylvania, the first large scale power reactor to be retired, is now being decommissioned. The work has rekindled the debate in the light of reality. Outside the United States, decommissioning is also being confronted on a new plane. (author)

  17. The cost of decommissioning uranium mill tailings

    International Nuclear Information System (INIS)

    Lush, D.L.; Lendrum, C.; Hostovsky, C.; Eedy, W.; Ashbrook, A.

    1986-04-01

    This report identifies several key operations that are commonly carried out during decommissioning of tailings areas in the Canadian environment. These operations are unit costed for a generic site to provide a base reference case. The unit costs have also been scaled to the quantities required for the decommissioning of four Canadian sites and these scaled quantities compared with site-specific engineering cost estimates and actual costs incurred in carrying out the decommissioning activities. Variances in costing are discussed. The report also recommends a generic monitoring regime upon which both short- and longer-term environmental monitoring costs are calculated. Although every site must be addressed as a site-specific case, and monitoring programs must be tailored to fit a specific site, it would appear that for the conventional decommissioning and monitoring practices that have been employed to date, costs can be reasonably estimated when site-specific conditions are taken into account

  18. CASE STUDY

    African Journals Online (AJOL)

    HIV infection has several oral manifestations, including oral candidiasis and oral hairy leucoplakia. Occasionally unusual presentations requiring rigorous investigations are seen, and in these cases the diagnosis sometimes remains a dilemma owing to limited investigation facilities.1-3 We present the case of a patient who.

  19. Decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Schneider, K.J.

    1979-01-01

    The Symposium was jointly sponsored by OECD/NEA and IAEA and was attended by more than 225 participants from 26 countries. Forty one papers were presented in eight sessions which covered the following topics: national and international policies and planning; engineering considerations relevant to decommissioning; radiological release considerations and waste classifications; decommissioning experience; and decontamination and remote operations. In addition, a panel of decommissioning experts discussed questions from the participants

  20. Preparatory activities of the Fugen decommissioning

    International Nuclear Information System (INIS)

    Iguchi, Y.; Tajiri, T.; Kiyota, S.

    2004-01-01

    The Advanced Thermal Reactor Fugen is a 165 MWe, heavy water moderated, light-water cooled, pressure-tube type reactor. In February 1998, the Atomic Energy Commission of Japan introduced a new policy that development and research of decommissioning of Fugen should be promoted in order to carry out the decommissioning smoothly after the shutdown. The Fugen reactor was shut down definitely in March 2003, and Fugen has been preparing for the project, including necessary development of technologies. The development of decommissioning for Fugen is divided into two areas. One area is the development of unique technology for dismantling special components such as the reactor core and the heavy water system. Another area is the improvement and enhancement of existing technologies. Especially the former area requires effort and comprises development of the reactor dismantlement, tritium decontamination of heavy water system and engineering support systems. The activities are as follows: the density and amount of radioactive nuclides in all equipment or concrete including the reactor core need to be evaluated for the decommissioning. To prepare for decommissioning, analysis, measurement and evaluation of the neutron flux density have been executed during reactor operation. Special dismantling process is necessary for the heavy water system and the reactor that are unique to Fugen. Some studies and tests are going on for the safe dismantling based on existing technologies and their combination. Systems engineering approach is necessary in order to optimize the work load, exposure dose, waste mass and cost by selecting appropriate dismantling process at the planning stage of the decommissioning. For this reason, in order to make a decommissioning plan efficiently, we have been developing an Engineering Support System for decommissioning by adopting new information technologies such as three-dimensional computer-aided design system and virtual reality system. Moreover, the

  1. Decommissioning of NPP A-1

    International Nuclear Information System (INIS)

    Anon

    2009-01-01

    In this presentation the Operation history of A1 NPP, Project 'Decommissioning of A1 NPP' - I stage, Project 'Decommissioning of A1 NPP ' - II stage and Next stages of Project 'Decommissioning of A1 NPP ' are discussed.

  2. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP KRSKO. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and the results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economical aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling all activities necessary for the decommissioning of the NPP KRSKO are presented. (author)

  3. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP Krsko. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for a decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill the decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economic aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling of all activities necessary for the decommissioning of the NPP Krsko are presented. (author)

  4. Management of Decommissioning on a Multi-Facility Site

    International Nuclear Information System (INIS)

    Laraia, Michele; McIntyre, Peter; Visagie, Abrie

    2008-01-01

    The management of the decommissioning of multi-facility sites may be inadequate or inappropriate if based on approaches and strategies developed for sites consisting of only a single facility. The varied nature of activities undertaken, their interfaces and their interdependencies are likely to complicate the management of decommissioning. These issues can be exacerbated where some facilities are entering the decommissioning phase while others are still operational or even new facilities are being built. Multi-facility sites are not uncommon worldwide but perhaps insufficient attention has been paid to optimizing the overall site decommissioning in the context of the entire life cycle of facilities. Decommissioning management arrangements need to be established taking a view across the whole site. A site-wide decommissioning management system is required. This should include a project evaluation and approval process and specific arrangements to manage identified interfaces and interdependencies. A group should be created to manage decommissioning across the site, ensuring adequate and consistent practices in accordance with the management system. Decommissioning management should be aimed at the entire life cycle of facilities. In the case of multi facility sites, the process becomes more complex and decommissioning management arrangements need to be established with a view to the whole site. A site decommissioning management system, a group that is responsible for decommissioning on site, a site project evaluation and approval process and specific arrangements to manage the identified interfaces are key areas of a site decommissioning management structure that need to be addressed to ensure adequate and consistent decommissioning practices. A decommissioning strategy based on single facilities in a sequential manner is deemed inadequate

  5. Decommissioning of nuclear facilities. Feasibility, needs and costs

    International Nuclear Information System (INIS)

    1986-01-01

    Reactor decommissioning activities generally are considered to begin after operations have ceased and the fuel has been removed from the reactor, although in some countries the activities may be started while the fuel is still at the reactor site. The three principal alternatives for decommissioning are described. The factors to be considered in selecting the decommissioning strategy, i.e. a stage or a combination of stages that comprise the total decommissioning programme, are reviewed. One presents a discussion of the feasibility of decommissioning techniques available for use on the larger reactors and fuel cycle facilities. The numbers and types of facilities to be decommissioned and the resultant waste volumes generated for disposal will then be projected. Finally, the costs of decommissioning these facilities, the effect of these costs on electricity generating costs, and alternative methods of financing decommissioning are discussed. The discussion of decommissioning draws on various countries' studies and experience in this area. Specific details about current activities and policies in NEA Member Countries are given in the short country specific Annexes. The nuclear facilities that are addressed in this study include reactors, fuel fabrication facilities, reprocessing facilities, associated radioactive waste storage facilities, enrichment facilities and other directly related fuel cycle support facilities. The present study focuses on the technical feasibility, needs, and costs of decommissioning the larger commercial facilities in the OECD member countries that are coming into service up to the year 2000. It is intended to inform the public and to assist in planning for the decommissioning of these facilities

  6. case study

    African Journals Online (AJOL)

    Elton

    particularly in patients who commence ART with low CD4 counts and established opportunistic infections. IRIS results from a pathological inflammatory response to pre-existing infective, host or other antigens, alive or dead, causing clinical deterioration in HIV-infected patients after initiating ART.1 A case definition for IRIS ...

  7. CASE STUDY

    African Journals Online (AJOL)

    2010-09-01

    Sep 1, 2010 ... of the two diseases surgery can be successful, recovery can be similar to that .... lymphocytes predominated in 68% of cases, and that there was an .... using ferritin is the fact that it acts as an acute-phase reactant and will be ...

  8. Decommissioning of the CANDU-PHW reactor

    International Nuclear Information System (INIS)

    Unsworth, G.N.

    1977-04-01

    This report contains the results of a study of various aspects of decommissioning of reactors. The study places in perspective the size of the job, the hazards involved, the cost and the environmental impact. The three internationally agreed ''stages'' of decommissioning, namely, mothballing, entombment, and dismantling are defined and discussed. The single unit 600 MW(e) CANDU is chosen as the type of reactor on which the discussion is focussed but the conclusions reached will provide a basis for judgement of the costs and problems associated with decommissioning reactors of other sizes and types. (author)

  9. Options for Steam Generator Decommissioning

    International Nuclear Information System (INIS)

    Krause, Gregor; Amcoff, Bjoern; Robinson, Joe

    2016-01-01

    Selecting the best option for decommissioning steam generators is a key consideration in preparing for decommissioning PWR nuclear power plants. Steam Generators represent a discrete waste stream of large, complex items that can lend themselves to a variety of options for handling, treatment, recycling and disposal. Studsvik has significant experience in processing full size Steam Generators at its metal recycling facility in Sweden, and this paper will introduce the Studsvik steam generator treatment concept and the results achieved to date across a number of projects. The paper will outline the important parameters needed at an early stage to assess options and to help consider the balance between off-site and on-site treatment solutions, and the role of prior decontamination techniques. The paper also outlines the use of feasibility studies and demonstration projects that have been used to help customers prepare for decommissioning. The paper discusses physical, radiological and operational history data, Pro and Contra factors for on- and off-site treatment, the role of chemical decontamination prior to treatment, planning for off-site shipments as well as Studsvik experience This paper has an original focus upon the coming challenges of steam generator decommissioning and potential external treatment capacity constraints in the medium term. It also focuses on the potential during operations or initial shut-down to develop robust plans for steam generator management. (authors)

  10. Safety in decommissioning of research reactors

    International Nuclear Information System (INIS)

    1986-01-01

    This Guide covers the technical and administrative considerations relevant to the nuclear aspects of safety in the decommissioning of reactors, as they apply to the reactor and the reactor site. While the treatment, transport and disposal of radioactive wastes arising from decommissioning are important considerations, these aspects are not specifically covered in this Guide. Likewise, other possible issues in decommissioning (e.g. land use and other environmental issues, industrial safety, financial assurance) which are not directly related to radiological safety are also not considered. Generally, decommissioning will be undertaken after planned final shutdown of the reactor. In some cases a reactor may have to be decommissioned following an unplanned or unexpected event of a series or damaging nature occurring during operation. In these cases special procedures for decommissioning may need to be developed, peculiar to the particular circumstances. This Guide could be used as a basis for the development of these procedures although specific consideration of the circumstances which create the need for them is beyond its scope

  11. Decommissioning of nuclear installations - regulations - financing - responsibility - insurance

    International Nuclear Information System (INIS)

    Hubert, E.H.; Andersson, C.; Deprimoz, J.; Mayoux, J.C.; Richard, M.; Sartorelli, C.; Nocera, F.

    1983-01-01

    This paper highlights three aspects of decommissioning of nuclear installations which relate, more or less directly, to legal options already applied or advocated. It reviews the regulatory conditions for decommissioning a nuclear installation and indicates legal provisions for financing decommissioning expenditures. It also describes the legal provisions to determine liabilities in case of nuclear damage and the assistance which insurers may provide to cover the consequences of such liabilities. (NEA) [fr

  12. Social effects of decommissioning Trawsfynydd Power Station

    International Nuclear Information System (INIS)

    Jones, H.

    2001-01-01

    The decision to close Trawsfynydd in 1993 had significant implications for the staff and local community. The site is situated within a National Park and local employment opportunities are limited. The staff and local communities were consulted regarding the issues arising from closure and decommissioning. This consultation influenced the decommissioning strategy for the site, with emphasis placed on the mitigation of the effects of closure. Subsequent studies have shown that the adopted strategies have served to limit the social and economic effects. The experience at Trawsfynydd has proved to be generally applicable at other decommissioning sites. (author)

  13. Stakeholder involvement in decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    2007-01-01

    Significant numbers of nuclear facilities will need to be decommissioned in the coming decades. In this context, NEA member countries are placing increasing emphasis on the involvement of stakeholders in the associated decision procedures. This study reviews decommissioning experience with a view to identifying stakeholder concerns and best practice in addressing them. The lessons learnt about the end of the facility life cycle can also contribute to better foresight in siting and building new facilities. This report will be of interest to all major players in the field of decommissioning, in particular policy makers, implementers, regulators and representatives of local host communities

  14. Decommissioning Unit Cost Data

    International Nuclear Information System (INIS)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-01-01

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for

  15. Case Study: Testing with Case Studies

    Science.gov (United States)

    Herreid, Clyde Freeman

    2015-01-01

    This column provides original articles on innovations in case study teaching, assessment of the method, as well as case studies with teaching notes. This month's issue discusses using case studies to test for knowledge or lessons learned.

  16. Decommissioning activities for Salaspils research reactor - 59055

    International Nuclear Information System (INIS)

    Abramenkovs, A.; Malnacs, J.

    2012-01-01

    In May 1995, the Latvian government decided to shut down the Salaspils Research Reactor (SRR). The reactor is out of operation since July 1998. A conceptual study for the decommissioning of SRR has been carried out by Noell-KRC-Energie- und Umwelttechnik GmbH at 1998-1999. The Latvian government decided to start the direct dismantling to 'green field' in October 26, 1999. The upgrade of decommissioning and dismantling plan was performed in 2003-2004 years, which change the main goal of decommissioning to the 'brown field'. The paper deals with the SRR decommissioning experience during 1999-2010. The main decommissioning stages are discussed including spent fuel and radioactive wastes management. The legal aspects and procedures for decommissioning of SRR are described in the paper. It was found, that the involvement of stakeholders at the early stages significantly promotes the decommissioning of nuclear facility. Radioactive waste management's main efforts were devoted to collecting and conditioning of 'historical' radioactive wastes from different storages outside and inside of reactor hall. All radioactive materials (more than 96 tons) were conditioned in concrete containers for disposal in the radioactive wastes repository 'Radons' at Baldone site. The dismantling of contaminated and activated components of SRR systems is discussed in paper. The cementation of dismantled radioactive wastes in concrete containers is discussed. Infrastructure of SRR, including personal protective and radiation measurement equipment, for decommissioning purposes was upgraded significantly. Additional attention was devoted to the free release measurement's technique. The certified laboratory was installed for supporting of all decommissioning activities. All non-radioactive equipments and materials outside of reactor buildings were released for clearance and dismantled for reusing or conventional disposing. Weakly contaminated materials from reactor hall were collected

  17. Atmospheric discharges from nuclear facilities during decommissioning: German experiences

    Energy Technology Data Exchange (ETDEWEB)

    Braun, H.; Goertz, R.; Weil, L.

    1997-08-01

    In Germany, a substantial amount of experience is available with planning, licensing and realization of decommissioning projects. In total, a number of 18 nuclear power plants including prototype facilities as well as 6 research reactors and 3 fuel cycle facilities have been shut down finally and are at different stages of decommissioning. Only recently the final {open_quotes}green field{close_quotes} stage of the Niederaichbach Nuclear Power Plant total dismantlement project has been achieved. From the regulatory point of view, a survey of the decommissioning experience in Germany is presented highlighting the aspects of production and retention of airborne radioactivity. Nuclear air cleaning technology, discharge limits prescribed in licences and actual discharges are presented. As compared to operation, the composition of the discharged radioactivity is different as well as the off-gas discharge rate. In practically all cases, there is no significant amount of short-lived radionuclides. The discussion further includes lessons learned, for example inadvertent discharges of radionuclides expected not to be in the plants inventory. It is demonstrated that, as for operation of nuclear power plants, the limits prescribed in the Ordinance on Radiological Protection can be met using existing air cleaning technology, Optimization of protection results in public exposures substantially below the limits. In the frame of the regulatory investigation programme a study has been conducted to assess the airborne radioactivity created during certain decommissioning activities like decontamination, segmentation and handling of contaminated or activated parts. The essential results of this study are presented, which are supposed to support planning for decommissioning, for LWRs, Co-60 and Cs-137 are expected to be the dominant radionuclides in airborne discharges. 18 refs., 2 figs., 1 tab.

  18. Decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Friske, A.; Thiele, D.

    1988-01-01

    The IAEA classification of decommissioning stages is outlined. The international development hitherto observed in decommissioning of nuclear reactors and nuclear power stations is presented. The dismantling, cutting and decontamination methods used in the decommissioning process are mentioned. The radioactive wastes from decommissioning are characterized, the state of the art of their treatment and disposal is given. The radiation burdens and the decommissioning cost in a decommissioning process are estimated. Finally, some evaluation of the trends in the decommissioning process of nuclear power plants is given. 54 refs. (author)

  19. Decommissioning and disposal costs in Switzerland

    International Nuclear Information System (INIS)

    Zurkinden, Auguste

    2003-01-01

    Introduction Goal: Secure sufficient financial resources. Question: How much money is needed? Mean: Concrete plans for decommissioning and waste disposal. - It is the task of the operators to elaborate these plans and to evaluate the corresponding costs - Plans and costs are to be reviewed by the authorities Decommissioning Plans and Costs - Comprise decommissioning, dismantling and management (including disposal) of the waste. - New studies 2001 for each Swiss nuclear power plant (KKB 2 x 380 MWe, KKM 370 MWe, KKG 1020 MWe, KKL 1180 MWe). - Studies performed by NIS (D). - Last developments taken into account (Niederaichbach, Gundremmingen, Kahl). Decommissioning: Results and Review Results: Total cost estimates decreasing (billion CHF) 1994 1998 2001 13.7 13.1 11.8 Lower costs for spent fuel conditioning and BE/HAA/LMA repository (Opalinus Clay) Split in 2025: 5.6 bil. CHF paid by NPP 6.2 billion CHF in Fund Review: Concentrates on disposal, ongoing

  20. UK reactor decommissioning strategy

    International Nuclear Information System (INIS)

    Woollam, P.B.

    2004-01-01

    With the cessation of electricity generation, nuclear power stations move into the next stage of the overall life cycle of the facility: decommissioning. Decommissioning is defined as the process whereby a nuclear facility, at the end of its economic life, is taken permanently out of service and its site made available for other purposes. This involves the implementation of a structured and safe programme for dismantling and clearing the site and making it available for alternative use in the future. In practical terms, 'decommissioning' means the systematic and progressive reduction of hazards to the point where the site could eventually be de-licensed. (author)

  1. Nuclear decommissioning and society

    International Nuclear Information System (INIS)

    Pasqualetti, M.J.

    1990-01-01

    Links between decommissioning in general, reactor decommissioning in particular, and the public are indexed. The established links are recognised and others, such as jobs, are discussed. Finally the links with policy, such as political geography, and wider issues of the environment and public concern over waste disposal are considered. Decommissioning is a relatively new field where public opinion must now be considered but it has implications both for existing nuclear power plants and those planned for the future, especially in their siting. This book looks especially at the situation in the United Kingdom. There are twelve papers, all indexed separately. (UK)

  2. Decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    Buck, S.

    1996-01-01

    Nuclear facilities present a number of problems at the end of their working lives. They require dismantling and removal but public and environmental protection remain a priority. The principles and strategies are outlined. Experience of decommissioning in France and the U.K. had touched every major stage of the fuel cycle by the early 1990's. Decommissioning projects attempt to restrict waste production and proliferation as waste treatment and disposal are costly. It is concluded that technical means exist to deal with present civil plant and costs are now predictable. Strategies for decommissioning and future financial provisions are important. (UK)

  3. European Decommissioning Academy

    International Nuclear Information System (INIS)

    Slugen, V. S.; Hornacek, M.

    2016-01-01

    Full text: Experiences from the first run of the European Decommissioning Academy (EDA) are reported in details. EDA was created at the Slovak University of Technology in Bratislava Slovakia, based on discussion and expressed needs declared at many international meetings including ECED2013. The first run successfully passed 15 participants during 7–26 June 2015. Academy was focused on decommissioning issues via lessons, practical exercises in laboratories, on-site training prepared at NPP V-1 in Jaslovské Bohunice, Slovakia as well as four day technical tour to other European decommissioning facilities in Switzerland and Italy. Detailed information can be found at http://kome.snus.sk/inpe/. (author

  4. The environmental risk between forgetting and managing the past: the case of the decommissioning of a uranium mine in France

    International Nuclear Information System (INIS)

    Bretesche, S.; Ponnet, M.

    2013-01-01

    This description of how a uranium mine (the Lucette mine) in western France was managed once it had been shut down draws attention to what was left behind. The article emphasizes how the mine became something common, ordinary, since the work conducted there during the nineties gradually erased evidence of the mining of uranium and was like a progressive return to a pristine state. But 3 events that happened after the decommissioning of the mine revealed to be strong memories of the past activity of the mine. First, some important land surface collapses happened which led to a zoning and a regular monitoring of the site. Secondly, red-colored water seepage appeared on the site and flowed into a nearby river. Analysis have shown the presence of radium, uranium and sodium chloride in the seeping. Thirdly, the tailings were being used by a construction enterprise to build and repair roads until the tailings were considered too radioactive to be used. The example of the Lucette mine provides a framework for broader questions about the effect of what is left behind in articulating past and present, and in the public construction of what is 'memorable' in environmental management

  5. Nuclear power plant decommissioning costs in perspective

    International Nuclear Information System (INIS)

    Rothwell, Geoffrey; Deffrennes, Marc; Weber, Inge

    2016-01-01

    At the international level, actual experience is limited in the completion of nuclear power plant decommissioning projects. Cost data for decommissioning projects are thus largely unavailable, with few examples of analyses or comparisons between estimates and actual costs at the project level. The Nuclear Energy Agency (NEA) initiated a project to address this knowledge gap and in early 2016 published the outcomes in the report on Costs of Decommissioning Nuclear Power Plants. The study reviews decommissioning costs and funding practices adopted by NEA member countries, based on the collection and analysis of survey data via a questionnaire. The work was carried out in co-operation with the International Atomic Energy Agency (IAEA) and the European Commission (EC). (authors)

  6. The decommissioning of Berkeley II

    International Nuclear Information System (INIS)

    Hannan, A.

    2002-01-01

    This paper describes the decommissioning progress at the Magnox site at Berkeley in Gloucestershire.Throughout the work at Berkeley the emphasis has been on conducting decommissioning safely. This has been reflected in the progress of decommissioning starting with removal of the fuel from site and thus much greater than 99% of the radioactive inventory. The major radioactive hazard is the Intermediate Level Waste in the form of fuel element debris (graphite struts and extraneous magnox components removed to increase the packing density of fuel elements in flasks going to Sellafield), miscellaneous activated components, sludges and resins. Approximately 1500 m 3 of such material exists and is stored in underground waste vaults on site. Work is underway to recover and encapsulate the waste in cement so rendering it 'passively safe'. All work on site is covered by a nuclear safety case which has a key objective of minimising the radiological exposures that could accrue to workers. Reflecting this an early decision has been taken to leave work on the Reactor Pressure Vessels themselves for several decades. Also important in protection of the workforce has been control of asbestos.Much material has been removed with redundant plant and equipment, but a programme of remediation in line with government legislation has been required to ensure personnel safety throughout the decommissioning period and into Care and Maintenance.In addition to health and safety matters the site approach to environmental issues has been consistent. Formally such standards as ISO 14001 have been adhered to and the appropriate certification maintained. At a working level the principles of reduce, reuse and recycle have been inculcated

  7. Decommissioning and Decontamination

    International Nuclear Information System (INIS)

    Massaut, V.

    2000-01-01

    The objectives of SCK-CEN's decommissioning and decontamination programme are (1) to develop, test and optimise the technologies and procedures for decommissioning and decontamination of nuclear installations in order to minimise the waste arising and the distributed dose; (2) to optimise the environmental impact; (3) to reduce the cost of the end-of-life of the installation; (4) to make these new techniques available to the industry; (5) to share skills and competences. The programme and achievements in 1999 are summarised

  8. Study on the state-of-the-arts technologies and policy trends for the decommissioning of nuclear installations and facilities

    International Nuclear Information System (INIS)

    Jeong, G. J.; Park, J. H.; Jeong, U. S. and others

    2005-12-01

    D and D project of the nuclear facilities is now the one of the biggest projects among the nuclear ones in the world. The nuclear facilities have their unique characteristics so making preparations about technical research in advance is very important in economic side and worker's protection side. Especially, because workers have a high possibility to contact radioactive material directly, an automation technology and shielding technology for worker's protection as well as a system development which can perform D and D work efficiently are necessary for D and D project. The waste reduction technology development, D and D equipment development, container development, and the study related the establishment of the level of the release regulation for radioactive waste are also important. The purpose of this research is to grasp of the national and internal D and D status for the nuclear facilities and to estimate them so we expect to prevent the possibility of a tremendous economical loss as the initiative of the nuclear D and D market is lost due to not understand the situation about the status of the related technologies. And we also expect to practical use the accumulated experience to decommissioning facilities in North

  9. Risk Management of Large Component in Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Nah, Kyung Ku; Kim, Tae Ryong [KEPCO International Nuclear Graduate School, Ulsan (Korea, Republic of)

    2014-10-15

    The need for energy, especially electric energy, has been dramatically increasing in Korea. Therefore, a rapid growth in nuclear power development has been achieved to have about 30% of electric power production. However, such a large nuclear power generation has been producing a significant amount of radioactive waste and other matters such as safety issue. In addition, owing to the severe accidents at the Fukushima in Japan, public concerns regarding NPP and radiation hazard have greatly increased. In Korea, the operation of KORI 1 has been scheduled to be faced with end of lifetime in several years and Wolsong 1 has been being under review for extending its life. This is the reason why the preparation of nuclear power plant decommissioning is significant in this time. Decommissioning is the final phase in the life-cycle of a nuclear facility and during decommissioning operation, one of the most important management in decommissioning is how to deal with the disused large component. Therefore, in this study, the risk in large component in decommissioning is to be identified and the key risk factor is to be analyzed from where can be prepared to handle decommissioning process safely and efficiently. Developing dedicated acceptance criteria for large components at disposal site was analyzed as a key factor. Acceptance criteria applied to deal with large components like what size of those should be and how to be taken care of during disposal process strongly affect other major works. For example, if the size of large component was not set up at disposal site, any dismantle work in decommissioning is not able to be conducted. Therefore, considering insufficient time left for decommissioning of some NPP, it is absolutely imperative that those criteria should be laid down.

  10. Risk Management of Large Component in Decommissioning

    International Nuclear Information System (INIS)

    Nah, Kyung Ku; Kim, Tae Ryong

    2014-01-01

    The need for energy, especially electric energy, has been dramatically increasing in Korea. Therefore, a rapid growth in nuclear power development has been achieved to have about 30% of electric power production. However, such a large nuclear power generation has been producing a significant amount of radioactive waste and other matters such as safety issue. In addition, owing to the severe accidents at the Fukushima in Japan, public concerns regarding NPP and radiation hazard have greatly increased. In Korea, the operation of KORI 1 has been scheduled to be faced with end of lifetime in several years and Wolsong 1 has been being under review for extending its life. This is the reason why the preparation of nuclear power plant decommissioning is significant in this time. Decommissioning is the final phase in the life-cycle of a nuclear facility and during decommissioning operation, one of the most important management in decommissioning is how to deal with the disused large component. Therefore, in this study, the risk in large component in decommissioning is to be identified and the key risk factor is to be analyzed from where can be prepared to handle decommissioning process safely and efficiently. Developing dedicated acceptance criteria for large components at disposal site was analyzed as a key factor. Acceptance criteria applied to deal with large components like what size of those should be and how to be taken care of during disposal process strongly affect other major works. For example, if the size of large component was not set up at disposal site, any dismantle work in decommissioning is not able to be conducted. Therefore, considering insufficient time left for decommissioning of some NPP, it is absolutely imperative that those criteria should be laid down

  11. Regulatory experience in nuclear power station decommissioning

    International Nuclear Information System (INIS)

    Ross, W.M.; Waters, R.E.; Taylor, F.E.; Burrows, P.I.

    1995-01-01

    In the UK, decommissioning on a licensed nuclear site is regulated and controlled by HM Nuclear Installations Inspectorate on behalf of the Health and Safety Executive. The same legislative framework used for operating nuclear power stations is also applied to decommissioning activities and provides a continuous but flexible safety regime until there is no danger from ionising radiations. The regulatory strategy is discussed, taking into account Government policy and international guidance for decommissioning and the implications of the recent white paper reviewing radioactive waste management policy. Although each site is treated on a case by case basis as regulatory experience is gained from decommissioning commercial nuclear power stations in the UK, generic issues have been identified and current regulatory thinking on them is indicated. Overall it is concluded that decommissioning is an evolving process where dismantling and waste disposal should be carried out as soon as reasonably practicable. Waste stored on site should, where it is practical and cost effective, be in a state of passive safety. (Author)

  12. JPDR decommissioning program

    International Nuclear Information System (INIS)

    Anon.

    1983-01-01

    As approved by the Japan Nuclear Safety Commission, the preparatory work for dismantling the Japan Power Demonstration Reactor of Japan Atomic Energy Research Institute has begun. As decided in the long term nuclear energy development and utilization program in June, 1982, by the Japan Atomic Energy Commission, the dismantling of the JPDR through its entire phase is the model case for the development of the dismantling technology and for the establishment of safety standard in the dismantling of shut-off nuclear power plants and their removal. The schedule of the JPDR dismantling is divided into two phases. In Phase 1, the development of dismantling techniques is made by the end of fiscal 1985, and in Phase 2, the full scale dismantling work is carried out by the end of fiscal 1989. The removal of the related facilities and the rearrangement of the evacuated land also are scheduled to be completed. During the first 10 days of April, 1983, the JPDR will be in the sealed up condition for the purpose of developing the dismantling techniques, and the nuclear fuel has been transferred to the spent fuel pool. The national policy on reactor decommissioning and the program for the technology development are reported. (Kako, I.)

  13. The decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Niel, J.Ch.; Rieu, J.; Lareynie, O.; Delrive, L.; Vallet, J.; Girard, A.; Duthe, M.; Lecomte, C.; Rozain, J.P.; Nokhamzon, J.G.; Davoust, M.; Eyraud, J.L.; Bernet, Ph.; Velon, M.; Gay, A.; Charles, Th.; Leschaeva, M.; Dutzer, M.; Maocec, Ch.; Gillet, G.; Brut, F.; Dieulot, M.; Thuillier, D.; Tournebize, F.; Fontaine, V.; Goursaud, V.; Birot, M.; Le Bourdonnec, Th.; Batandjieva, B.; Theis, St.; Walker, St.; Rosett, M.; Cameron, C.; Boyd, A.; Aguilar, M.; Brownell, H.; Manson, P.; Walthery, R.; Wan Laer, W.; Lewandowski, P.; Dorms, B.; Reusen, N.; Bardelay, J.; Damette, G.; Francois, P.; Eimer, M.; Tadjeddine, A.; Sene, M.; Sene, R.

    2008-01-01

    This file includes five parts: the first part is devoted to the strategies of the different operators and includes the following files: the decommissioning of nuclear facilities Asn point of view, decommissioning of secret nuclear facilities, decommissioning at the civil Cea strategy and programs, EDF de-construction strategy, Areva strategy for decommissioning of nuclear facilities; the second one concerns the stakes of dismantling and includes the articles as follow: complete cleanup of buildings structures in nuclear facilities, decommissioning of nuclear facilities and safety assessment, decommissioning wastes management issues, securing the financing of long-term decommissioning and waste management costs, organizational and human factors in decommissioning projects, training for the decommissioning professions: the example of the Grenoble University master degree; the third part is devoted to the management of dismantling work sites and includes the different articles as follow: decommissioning progress at S.I.C.N. plant, example of decommissioning work site in Cea Grenoble: Siloette reactor decommissioning, matters related to decommissioning sites, decommissioning of french nuclear installations: the viewpoint of a specialist company, specificities of inspections during decommissioning: the Asn inspector point of view; the fourth part is in relation with the international approach and includes as follow: IAEA role in establishing a global safety regime on decommissioning, towards harmonization of nuclear safety practices in Europe: W.E.N.R.A. and the decommissioning of nuclear facilities, EPA superfund program policy for decontamination and decommissioning, progress with remediation at Sellafield, progress and experiences from the decommissioning of the Eurochemic reprocessing plant in Belgium, activities of I.R.S.N. and its daughter company Risk-audit I.r.s.n./G.r.s. international in the field of decommissioning of nuclear facilities in eastern countries

  14. The study on the recycle condition for existence of the decommissioning waste in the nuclear power station

    International Nuclear Information System (INIS)

    Hironaga, Michihiko; Ozaki, Sachio; Hirai, Mitsuyuki; Sakamoto, Hiroyuki; Usui, Tatsuo; Simizu, Yasuo; Ogane, Daisuke

    2000-01-01

    To establish the technique of the recycle for concrete waste, this paper describes the recycle condition for existence of the decommissioning concrete waste in the nuclear power plant and considers the durability of cask yard concrete constructed at about twenty years ago. The authors examine the recycle system of concrete in the power plant. (author)

  15. CASE STUDY CRITIQUE; UPPER CLINCH CASE STUDY

    Science.gov (United States)

    Case study critique: Upper Clinch case study (from Research on Methods for Integrating Ecological Economics and Ecological Risk Assessment: A Trade-off Weighted Index Approach to Integrating Economics and Ecological Risk Assessment). This critique answers the questions: 1) does ...

  16. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    International Nuclear Information System (INIS)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J.

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process

  17. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    Energy Technology Data Exchange (ETDEWEB)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process.

  18. Subsidies to the decommissioning of the first uranium mining and processing plant in Brazil - the case of the mineral industrial complex in Pocos de Caldas, Minas Gerais State

    International Nuclear Information System (INIS)

    Fernandes, Horst Richard Sebastian Monken

    1997-01-01

    The closure of an uranium mining and milling facility has the potential to cause risks (radiological and non-radiological) to the human health and to the environment as a whole; these risks may be incurred in the short as well in the long terms. The present work took the mining and milling facility of Pocos de Caldas, Minas Gerais - as a study case. The following aspects were covered by the work: analysis of the impacts associated to the facility operation; assessment of the geological processes involved in the mobilization of radioactive and non-radioactive pollutants from the main sources of these pollutants in the environment - the waste rock piles and the tailings dam; quantification of the resulting impacts associated to the emission of pollutants into the environment in future scenarios and establishment of remedial actions taking into account the risk reduction and the association costs. The main aspects arising from the study were: the wastes in the tailings dam are stratified in relation to metal and radionuclide concentrations, with the exception of 210 Pb and 226 Ra. The stratification is caused by the oxidation of the residual pyrite in the tailings, and is also related to metal and radionuclide concentrations in seepage water being higher in the upper zone and lower in the deeper zones. Sulfate anion was the only pollutant present in the seepage water to be detected in the groundwater below the tailings dam. Mathematical simulations taking into account the rest of the potential pollutants indicated the probability of groundwater contamination after 800 years. Direct liquid effluent releases into superficial waters are associated with a dose of about 8.0 mSv/y (conservative scenario) and less than 0.62 mSv/y (non-conservative scenario). If houses are built over the tailings, doses as high as 40 mSv/y and 8.0 mSv/y are to expected due to the Rn exhalation and external gamma respectively. Finally, covering the tailings dam with a clay layer 1.0 m thick

  19. Evaluation of nuclear facility decommissioning projects. Project summary report, Elk River Reactor

    International Nuclear Information System (INIS)

    Miller, R.L.; Adams, J.A.

    1982-12-01

    This report summarizes information concerning the decommissioning of the Elk River Reactor. Decommissioning data from available documents were input into a computerized data-handling system in a manner that permits specific information to be readily retrieved. The information is in a form that assists the Nuclear Regulatory Commission in its assessment of decommissioning alternatives and ALARA methods for future decommissionings projects. Samples of computer reports are included in the report. Decommissioning of other reactors, including NRC reference decommissioning studies, will be described in similar reports

  20. Cost estimation for decommissioning: a review of current practice

    International Nuclear Information System (INIS)

    O'Sullivan, P.; Pescatore, C.

    2009-01-01

    boundary conditions; cost estimation methodologies; and experience gained during the process. Twelve countries provided responses and participated in the analysis: Belgium, Canada, France, Germany, Italy, Japan, the Netherlands, the Slovak Republic, Spain, Sweden, the United Kingdom and the United States. The final report documenting the study is nearing publication. Its main findings are reported in this article. There is no single cost assessment methodology that applies equally at all stages of a decommissioning project. This means that different cost assessment methodologies may need to be used as the project advances. Such methodologies should be continuously updated using cost data from actual decommissioning projects, thus improving the cost assessment, providing better control of uncertainties and contingencies for each major cost category, and facilitating the preparation of an annualized schedule of expenditures for each facility. In the future, risk management may benefit from an approach that uses a deterministic calculation (base case) that feeds into a probabilistic assessment of future costs. Such approaches may be used to gain a better understanding of potential cost and programme requirements. Attention should also be given early on to socio-economic factors, including impacts caused by loss of employment, to help in building public support and acceptance of a decommissioning project. Early meetings with stakeholders may be used to gain agreement on project boundary conditions, strategy, release criteria and measurement protocols, and waste containers used. In view of the very significant impacts that changes and increases in scope may have on cost estimates, it is important that these be identified and controlled immediately, and incorporated into the estimate so that the estimate may continue to provide a viable benchmarking resource. Characterisation is acknowledged to be an important part of cost estimating accuracy, as it affects system and structure

  1. Computer System Analysis for Decommissioning Management of Nuclear Reactor

    International Nuclear Information System (INIS)

    Nurokhim; Sumarbagiono

    2008-01-01

    Nuclear reactor decommissioning is a complex activity that should be planed and implemented carefully. A system based on computer need to be developed to support nuclear reactor decommissioning. Some computer systems have been studied for management of nuclear power reactor. Software system COSMARD and DEXUS that have been developed in Japan and IDMT in Italy used as models for analysis and discussion. Its can be concluded that a computer system for nuclear reactor decommissioning management is quite complex that involved some computer code for radioactive inventory database calculation, calculation module on the stages of decommissioning phase, and spatial data system development for virtual reality. (author)

  2. WPDD workshop on: 'safe, efficient, and cost-effective decommissioning'. Workshop Conclusions/Final Stocktaking

    International Nuclear Information System (INIS)

    2005-01-01

    On September 6-10, 2004 a workshop on 'Safe, Efficient, and Cost-Effective Decommissioning' was held in Rome (Italy) to enable international experts on decommissioning to compare and evaluate respective approaches and experiences in decommissioning nuclear power and fuel cycle facilities and to formulate proposals for future international cooperation in the decommissioning arena. The main messages emerging from the workshop are: - Decommissioning is a mature industrial process and many projects have been safely completed with support of local communities. Technical and scientific issues are well-understood and practical experience and associated lessons are being documented to guide future activities. Emphasis is being placed on effective planning with active programmes of community involvement. - Individual countries need to further develop integrated decommissioning and waste management strategies to ensure that long-term solutions will be available for all wastes generated from decommissioning. National systems are evolving to meet national needs, against a framework provided by the international organisations, and these seem increasingly to favour early dismantling regardless of the availability of waste disposal routes. - Realistic and streamlined regulatory programmes are being developed with feed back from industry experience and are placing more responsibility and accountability on licensees. - Accurate decommissioning waste cost calculation methods is needed. Waste volumes may vary from project to project even for similar installations. There though appears to be a strong case for accumulating data and benchmarking costs for similar plants and processes. Further work and experience exchange on cost comparisons between different strategies (for example clearance and recycling/reuse of materials versus direct surface disposal) would be valuable. - International clearance criteria have been established, with individual countries free to adopt them

  3. Decommissioning of nuclear facilities: Feasibility, needs and costs

    International Nuclear Information System (INIS)

    DeLaney, E.G.; Mickelson, J.R.

    1985-01-01

    The Nuclear Energy Agency's Working Group on Decommissioning is preparing a study entitled ''Decommissioning of Nuclear Facilities: Feasibility, Needs and Costs.'' The study addresses the economics, technical feasibility and waste management aspects of decommissioning larger commercial reactors and nuclear support facilities. Experience on decommissioning small reactors and fuel cycle facilities shows that current technology is generally adequate. Several major projects that are either underway or planned will demonstrate decommissioning of the larger and more complex facilities. This experience will provide a framework for planning and engineering the decommissioning of the larger commercial reactors and fuel cycle facilities. Several areas of technology development are desired for worker productivity improvement, occupational exposure reduction, and waste volume reduction. In order to assess and plan for the decommissioning of large commercial nuclear facilities, projections have been made of the capacity of these facilities that may be decommissioned in the future and the radioactive waste that would be produced from the decommissioning of these facilities. These projections through the year 2025 are based on current data and the OECD reactor capacity forecast through the year 2000. A 25-year operating lifetime for electrical power generation was assumed. The possibilities of plant lifetime extension and the deferral of plant dismantlement make this projection very conservative

  4. Technology, safety and costs of decommissioning a reference pressurized water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies on conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference pressurized water reactor (PWR) described in the earlier study; defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs; and completing a study of recent PWR steam generator replacements to determine realistic estimates for time, costs and doses associated with steam generator removal during decommissioning. This report presents the results of recent PNL studies to provide supporting information in four areas concerning decommissioning of the reference PWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; assessing the cost and dose impacts of recent steam generator replacements; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation

  5. Decommissioning strategy selection

    International Nuclear Information System (INIS)

    Warnecke, E.

    2005-01-01

    At the end of their useful life nuclear facilities have to be decommissioned. The strategy selection on how to decommission a facility is a highly important decision at the very beginning of decommissioning planning. Basically, a facility may be subject to (a) immediate dismantling; (b) deferred dismantling after a period of ''safe enclosure'' or (c) entombment where a facility is turned into a near surface disposal facility. The first two strategies are normally applied. The third one may be accepted in countries without significant nuclear activities and hence without disposal facilities for radioactive waste. A large number of factors has to be taken into account when a decision on the decommissioning strategy is being made. Many of the factors cannot be quantified. They may be qualitative or subject to public opinion which may change with time. At present, a trend can be observed towards immediate dismantling of nuclear facilities, mainly because it is associated with less uncertainty, less local impact, a better public acceptance, and the availability of operational expertise and know how. A detailed evaluation of the various factors relevant to strategy selection and a few examples showing the situation regarding decommissioning strategy in a number of selected countries are presented in the following article. (orig.)

  6. Financial aspects of decommissioning

    International Nuclear Information System (INIS)

    Chirica, T.; Havris, A.

    2003-01-01

    European Commission adopted recently two proposals of Directives designed to pave the way for a Community approach to the safety of nuclear power plants and the processing of radioactive waste. Nuclear safety cannot be guaranteed without making available adequate financial resources. With regard, in particular, to the decommissioning of nuclear facilities, the Directive defines the Community rules for the establishment, management and use of decommissioning funds allocated to a body with legal personality separate from that of the nuclear operator. In order to comply with the acquis communautaire, Romanian Government issued the Emergency Ordinance no. 11/2003 which set up the National Agency for Radioactive Waste (ANDRAD) and soon will be established the financial mechanism for raising the necessary funds. Societatea Nationala 'Nuclearelectrica' S.A. operates, through one of its branches, Cernavoda NPP Unit 1 and has to prepare its decommissioning strategy and to analyze the options to assure the financing for covering the future costs. The purpose of this paper is to clarify the financial systems' mechanisms to the satisfaction of the nuclear operator obligations, according to the disbursement schedule foreseen by decommissioning projects . The availability of cash to pay for all the decommissioning expenditure must be foreseen by setting up assets and establishing a suitable financing plan. The different practices of assets management shall be presented in this paper on the basis of the international experience. Some calculation samples shall be given as an illustration. (author)

  7. The NEA Co-Operative Programme on Decommissioning, the First Ten Years 1985-95

    International Nuclear Information System (INIS)

    1996-01-01

    The Nuclear Energy (NEA) Co-operative Programme on Decommissioning established the Task Group on Recycling and Reuse in 1992. The Task Group was charged with examining means for maximizing the recovery of valuable materials that partially comprise waste resulting from decommissioning activities. The Task Group also was to examine means for minimising the quantity of waste from such operations. Much of the Task Group's work has been concentrated on metal recycling and reuse. The Task Group's examination and report are the product of experts from seven countries and constitute a synthesis of surveys, analyses, and case studies. The report is intended to provide information and insights, as of the end of 1994, into the practicality and usefulness of release criteria from the perspective of organisations currently engaged in actual decommissioning activities

  8. Decommissioning funding: ethics, implementation, uncertainties

    International Nuclear Information System (INIS)

    2006-01-01

    This status report on Decommissioning Funding: Ethics, Implementation, Uncertainties also draws on the experience of the NEA Working Party on Decommissioning and Dismantling (WPDD). The report offers, in a concise form, an overview of relevant considerations on decommissioning funding mechanisms with regard to ethics, implementation and uncertainties. Underlying ethical principles found in international agreements are identified, and factors influencing the accumulation and management of funds for decommissioning nuclear facilities are discussed together with the main sources of uncertainties of funding systems. (authors)

  9. Decommissioning and environmental remediation: An overview

    International Nuclear Information System (INIS)

    Chatzis, Irena

    2016-01-01

    The objective in both decommissioning and environmental remediation is to lower levels of residual radioactivity enough that the sites may be used for any purpose, without restriction. In some cases, however, this may not be practical and restrictions may be placed on future land use. Following decommissioning, for example, some sites may be reused for non-nuclear industrial activities, but not for habitation. Some former uranium mining sites may be released for reuse as nature reserves or for other leisure activities. Both decommissioning and environmental remediation are major industrial projects in which the safety of the workforce, the local public and the environment must be ensured from both radiological and conventional hazards. Hence, an appropriate legal and regulatory framework, as well as proper training for personnel both in implementation and in regulatory oversight are among the necessary preconditions to ensure safety.

  10. Decommissioning and environmental remediation: An overview

    International Nuclear Information System (INIS)

    Chatzis, Irena

    2016-01-01

    The objective in both decommissioning and environmental remediation is to lower levels of residual radioactivity enough that the sites may be used for any purpose, without restriction. In some cases, however, this may not be practical and restrictions may be placed on future land use. Following decommissioning, for example, some sites may be reused for non-nuclear industrial activities, but not for habitation. Some former uranium mining sites may be released for reuse as nature reserves or for other leisure activities. Both decommissioning and environmental remediation are major industrial projects in which the safety of the workforce, the local public and the environment must be ensured from both radiological and conventional hazards. Hence, an appropriate legal and regulatory framework, as well as proper training for personnel both in implementation and in regulatory oversight are among the necessary preconditions to ensure safety

  11. Decommissioning costs of WWER-440 nuclear power plants. Interim report: Data collection and preliminary evaluations

    International Nuclear Information System (INIS)

    2002-11-01

    comparison of data. As a result, the cost figures were collected in a recommended structure and analysed. During progress of work, experts of participating Member States responded to a questionnaire, and explained the contents of individual cost items and cost groups during subsequent discussions. Comparison of cost estimates in the various decommissioning projects showed to be rather difficult, even with the support of the standardised list of items for costing purposes. In each country, the existing cost figures were many times allocated to different cost codes, and it was difficult to re-allocate costs that were grouped based on the individual costing methodologies. Verification of cost figures was sometimes executed while comparing with previous IAEA as well as OECD/NEA studies. The total costs for the immediate decommissioning option vary from 219 MUSD (Finland) to 1,370 MUSD (Germany). This large difference is mainly due to country and site specific conditions. In the case of Finland the possibility for on-site disposal of all dismantled material reduces the costs dramatically. In the case of the Greifswald project (Germany) major costs for post-operational and site support activities, as well as the construction of a large interim storage on the site are included. For the safe enclosure option the cost figures vary from 210 MUSD (Czech Republic) to 469 MUSD (Hungary). In this case the spread in the cost estimations is smaller, but still significant, the reason for this being the different scopes that are included. At this stage of cost estimating in the participating countries, overall comparisons seem to be premature and it is necessary to look at the detail of each cost item. Comparing the cost categories Labour Costs; Capital, Equipment and Material Costs; and Expenses has demonstrated that labour represents about 50 % of the total decommissioning costs. Comparing these results with former OECD/NEA cost studies shows quite good agreement. It may be concluded

  12. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The Shippingport Atomic Power Station was located on the Ohio River in Shippingport Borough (Beaver County), Pennsylvania, USA. The US Atomic Energy Commission (AEC) constructed the plant in the mid-1950s on a seven and half acre parcel of land leased from Duquesne Light Company (DLC). The purposes were to demonstrate and to develop Pressurized Water Recovery technology and to generate electricity. DLC operated the Shippingport plant under supervision of (the successor to AEC) the Department of Energy (DOE)-Naval Reactors (NR) until operations were terminated on October 1, 1982. NR concluded end-of-life testing and defueling in 1984 and transferred the Station's responsibility to DOE Richland Operations Office (RL), Surplus Facility Management Program Office (SFMPO5) on September 5, 1984. SFMPO subsequently established the Shippingport Station Decommissioning Project and selected General Electric (GE) as the Decommissioning Operations Contractor. This report is intended to provide an overview of the Shippingport Station Decommissioning Project

  13. Scheduling for decommissioning projects

    International Nuclear Information System (INIS)

    Podmajersky, O.E.

    1987-01-01

    This paper describes the Project Scheduling system being employed by the Decommissioning Operations Contractor at the Shippingport Station Decommissioning Project (SSDP). Results from the planning system show that the project continues to achieve its cost and schedule goals. An integrated cost and schedule control system (C/SCS) which uses the concept of earned value for measurement of performance was instituted in accordance with DOE orders. The schedule and cost variances generated by the C/SCS system are used to confirm management's assessment of project status. This paper describes the types of schedules and tools used on the SSDP project to plan and monitor the work, and identifies factors that are unique to a decommissioning project that make scheduling critical to the achievement of the project's goals. 1 fig

  14. Decommissioning: the final folly

    International Nuclear Information System (INIS)

    Dibdin, T.

    1990-01-01

    The Second International Seminar on Decommissioning of Nuclear Facilities held in London is reviewed. Various solutions to the reactor decommissioning, including isolating the reactor core, and turning the surrounding buildings into a theme park, are mentioned. The International Atomic Energy Agency identifies three decommissioning stages. Stage 1, defuelling; Stage 2 dismounting of non-radioactive plant with isolation of the nuclear island and Stage 3, return to a 'green field' site. The real debate is about waste management and timing of the stages - whether to defer Stage 3 for a century or so, or even whether to attempt Stage 3 at all. Cost estimation is also discussed. In the United Kingdom, the timing of completion of the deep repository for high level waste will affect the timing. (UK)

  15. Site decommissioning management plan

    International Nuclear Information System (INIS)

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff's strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites

  16. Decommissioning licensing procedure

    International Nuclear Information System (INIS)

    Perello, M.

    1979-01-01

    Decommissioning or closure of a nuclear power plant, defined as the fact that takes place from the moment that the plant stops producing for the purpose it was built, is causing preocupation. So this specialist meeting on Regulatory Review seems to be the right place for presenting and discusing the need of considering the decommissioning in the safety analysis report. The main goal of this paper related to the licensing procedure is to suggest the need of a new chapter in the Preliminary Safety Analysis Report (P.S.A.R.) dealing with the decommissioning of the nuclear power plant. Therefore, after a brief introduction the problem is exposed from the point of view of nuclear safety and finally a format of the new chapter is proposed. (author)

  17. Site decommissioning management plan

    Energy Technology Data Exchange (ETDEWEB)

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff`s strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites.

  18. IAEA Assistance on Decommissioning of Small Facilities with Limited Resources

    International Nuclear Information System (INIS)

    Batandjieva, B.; Warnecke, E.

    2008-01-01

    The number of facilities reaching their lifetime is increasing and drawing the attention of operators, regulators, public and other interested parties (potential users of the site after decommissioning) on the importance of adequate planning, funding and implementation of decommissioning activities in compliance with regulatory requirements and criteria. Specific attention is required for small facilities that have been used for research purposes and in most cases state owned by and dependent on state funding. With the current tendency for expansion of the nuclear industry such small facilities could become less of importance for the operators which can increase the probability that these facilities become abandoned, hazardous and imposing undue burden to future generations. This concern is more related to countries with limited human and financial resources at the operating organizations and the regulatory body. The International Atomic Energy Agency (IAEA) has been working on the; (i) establishment of internationally recognized safety standards on decommissioning and (ii) providing Member States with assistance on the application of these standards. The recent international conference on Lessons Learned from the Decommissioning of Nuclear Facilities and the Safe Termination of Practices (Athens, Greece, 2006) has demonstrated that the set of IAEA standards is almost complete and that the International Action Plan on Decommissioning (2004), that is addressing decommissioning of small facilities, is being successfully implemented. However the need for further assistance on decommissioning of small facilities in countries with limited resources was also recognized and the Agency is planning its future work in this field. The IAEA also addresses the needs of small nuclear countries that have only a limited number of nuclear facilities, e.g. a research reactor, in its R esearch Reactor Decommissioning Demonstration Project (R 2 D 2 P. The Philippine Research Reactor

  19. Preparation for Ignalina NPP decommissioning

    International Nuclear Information System (INIS)

    Medeliene, D.

    2004-01-01

    Latest developments of atomic energy in Lithuania, works done to prepare Ignalina NPP for final shutdown and decommissioning are described. Information on decommissioning program for Ignalina NPP unit 1, decommissioning method, stages and funding is presented. Other topics: radiation protection, radioactive waste management and disposal. Key facts related to nuclear energy in Lithuania are listed

  20. Decommissioning Challenges, strategy and programme development

    Energy Technology Data Exchange (ETDEWEB)

    Potier, J.M.; Laraie, M.; Dinner, P. [Waste Technology Section, Dept. of Nuclear Energy, International Atomic Energy Agency (IAEA), Vienna (Austria); Pescatore, C.; O' Sullivan [Organisation for Economic Co-Operation and Development, Nuclear Energy Agency, 75 - Paris (France); Dupuis, M.C. [Agence Nationale pour la Gestion des Dechets Radioactifs (ANDRA), 92 - Chatenay Malabry (France); Szilagyi, A.; Collazo, Y.; Negin, Ch. [U.S. Department of Energy, Washington, DC (United States)

    2008-11-15

    This document gathers 4 short articles. The first one presents the IAEA decommissioning activities. These activities include: -) the development and implementation of the international action on decommissioning, -) the provision of experts and equipment to assist member states, -) networking activities such as training or exchange of knowledge and experience. The second article presents the work program of the Nea (nuclear energy agency) in the field of decommissioning and reports on the lessons that have been learnt. Among these lessons we can quote: -) selecting a strategy for decommissioning and funding it adequately, -) regulating the decommissioning of nuclear activities, -) thinking of the future in terms of reusing materials, buildings and sites, -) involving local and regional actors in the decommissioning process from decision-making to dismantling work itself, and -) increasing transparency in decision-making in order to build trust. The third article presents the management of radioactive wastes in France. This management is based on the categorization of wastes in 6 categories according to both the activity level and the radioactive half-life T: 1) very low activity, 2) low activity and T < 31 years, 3) low activity and T > 31 years, 4) intermediate activity and T < 31 years, 5) intermediate activity and T > 31 years, and 6) high activity. For categories 1, 2, 3 and 5, the waste treatment process and the disposal places have been operating for a long time while for categories 4 and 6, the disposal places are still being studied: low-depth repository and deep geological repository respectively. The last article presents the action of the US Department of energy in decommissioning activities and environmental remediation, the example of the work done at the ancient nuclear site of Rocky Flats gives an idea of the magnitude and complexity of the operations made. (A.C.)

  1. Optimizing decommissioning strategies

    International Nuclear Information System (INIS)

    Passant, F.H.

    1993-01-01

    Many different approaches can be considered for achieving satisfactory decommissioning of nuclear installations. These can embrace several different engineering actions at several stages, with time variations between the stages. Multi-attribute analysis can be used to help in the decision making process and to establish the optimum strategy. It has been used in the Usa and the UK to help in selecting preferred sites for radioactive waste repositories, and also in UK to help with the choice of preferred sites for locating PWR stations, and in selecting optimum decommissioning strategies

  2. Vinca nuclear decommissioning program

    International Nuclear Information System (INIS)

    Pesic, M.; Subotic, K.; Sotic, O.; Plecas, I.; Ljubenov, V.; Peric, A.

    2002-01-01

    In this paper a preliminary program for the nuclear decommissioning in The Vinca Institute of Nuclear Sciences is presented. Proposed Projects and Activities, planned to be done in the next 10 years within the frames of the Program, should improve nuclear and radiation safety and should solve the main problems that have arisen in the previous period. Project of removal of irradiated spent nuclear fuel from the RA reactor, as a first step in all possible decommissioning strategies and the main activity in the first two-three years of the Program realization, is considered in more details. (author)

  3. Decommissioning nuclear installations

    International Nuclear Information System (INIS)

    Dadoumont, J.

    2010-01-01

    When a nuclear installation is permanently shut down, it is crucial to completely dismantle and decontaminate it on account of radiological safety. The expertise that SCK-CEN has built up in the decommissioning operation of its own BR3 reactor is now available nationally and internationally. Last year SCK-CEN played an important role in the newly started dismantling and decontamination of the MOX plant (Mixed Oxide) of Belgonucleaire in Dessel, and the decommissioning of the university research reactor Thetis in Ghent.

  4. Decommissioning of IFEC

    International Nuclear Information System (INIS)

    Ceccotti, G.; Sberze, L.

    1995-05-01

    The IFEC nuclear fuel fabrication plant operated in Italy for more then thirty years and has now been successfully decommissioned. The rules and regulations relating to Quality Assurance established during the fabrication of Cirene reactor fuel have been adhered to during the decommissioning phase. The use of personnel with large experience in the nuclear field has resulted in vast majority of cares of material and apparatus to be reutilized in conventional activities without the need of calling on the assistance of external firms. The whole decontamination process was successfully completed on time and in particular the quantity of contaminated wastes was kept to eminimun

  5. Platform decommissioning costs

    International Nuclear Information System (INIS)

    Rodger, David

    1998-01-01

    There are over 6500 platforms worldwide contributing to the offshore oil and gas production industry. In the North Sea there are around 500 platforms in place. There are many factors to be considered in planning for platform decommissioning and the evaluation of options for removal and disposal. The environmental impact, technical feasibility, safety and cost factors all have to be considered. This presentation considers what information is available about the overall decommissioning costs for the North Sea and the costs of different removal and disposal options for individual platforms. 2 figs., 1 tab

  6. The regulatory process for the decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    1990-01-01

    The objective of this publication is to provide general guidance to Member States for regulating the decommissioning of nuclear facilities within the established nuclear regulatory framework. The Guide should also be useful to those responsible for, or interested in, the decommissioning of nuclear facilities. The Guide describes in general terms the process to be used in regulating decommissioning and the considerations to be applied in the development of decommissioning regulations and guides. It also delineates the responsibilities of the regulatory body and the licensee in decommissioning. The provisions of this Guide are intended to apply to all facilities within the nuclear fuel cycle and larger industrial installations using long lived radionuclides. For smaller installations, however, less extensive planning and less complex regulatory control systems should be acceptable. The Guide deals primarily with decommissioning after planned shutdown. Most provisions, however, are also applicable to decommissioning after an abnormal event, once cleanup operations have been terminated. The decommissioning planning in this case must take account of the abnormal event. 28 refs, 1 fig

  7. A study on implementation plan of decontamination and decommissioning R and D and evaluation of KAERI soil decontamination process

    International Nuclear Information System (INIS)

    Oh, Won Zin; Lee, K. W.; Won, H. J.; Jung, C. H.; Choi, W. K.; Kim, G. N.

    2001-08-01

    A. Decontamination Technology Development of Uranium Conversion Facility. Understanding of uranium conversion facility and related decontamination technologies, and analysis of current status of decontamination technologies. Establishment of the objective and research items of the middle and long term R and D project. Discussion of the erformance plan and about the methodology for connection with the project of environmental restoration of uranium conversion facility B. Treatment Technology Development of Uranium Sludge Analysis of the domestic and overseas research development status. Suggestion of treatment methodology of uranium slurry and cooperative R and D among industries, universities and research institute. Establishment of the objective and research items of the middle and long term R and D project. Discussion about the performance plan and about the methodology for connection with the project of environmental restoration of uranium conversion facility C. Decommissioning Technology Development Analysis of the domestic and overseas research development status and the overview of decommissioning technologies. Establishment of the objective and research items of the middle and long term R and D project. Discussion about the performance plan and about the methodology for connection with the project of TRIGA decommissioning D. Evaluation of KAERI Soil Decontamination Technology. Evaluation of soil decontamination process and the liquid decontamination waste treatment technology. Performance of soil decontamination test using solvent flushing test equipment for evaluation of residual radioactivity after decontami- nation and modeling of the results

  8. A study on implementation plan of decontamination and decommissioning R and D and evaluation of KAERI soil decontamination process

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Won Zin; Lee, K. W.; Won, H. J.; Jung, C. H.; Choi, W. K.; Kim, G. N

    2001-08-01

    A. Decontamination Technology Development of Uranium Conversion Facility. Understanding of uranium conversion facility and related decontamination technologies, and analysis of current status of decontamination technologies. Establishment of the objective and research items of the middle and long term R and D project. Discussion of the erformance plan and about the methodology for connection with the project of environmental restoration of uranium conversion facility B. Treatment Technology Development of Uranium Sludge Analysis of the domestic and overseas research development status. Suggestion of treatment methodology of uranium slurry and cooperative R and D among industries, universities and research institute. Establishment of the objective and research items of the middle and long term R and D project. Discussion about the performance plan and about the methodology for connection with the project of environmental restoration of uranium conversion facility C. Decommissioning Technology Development Analysis of the domestic and overseas research development status and the overview of decommissioning technologies. Establishment of the objective and research items of the middle and long term R and D project. Discussion about the performance plan and about the methodology for connection with the project of TRIGA decommissioning D. Evaluation of KAERI Soil Decontamination Technology. Evaluation of soil decontamination process and the liquid decontamination waste treatment technology. Performance of soil decontamination test using solvent flushing test equipment for evaluation of residual radioactivity after decontami- nation and modeling of the results.

  9. Decommissioning Work Modeling System for Nuclear Facility Decommissioning Design

    International Nuclear Information System (INIS)

    Park, S. K.; Cho, W. H.; Choi, Y. D.; Moon, J. K.

    2012-01-01

    During the decommissioning activities of the KRR-1 and 2 (Korea Research Reactor 1 and 2) and UCP (Uranium Conversion Plant), all information and data, which generated from the decommissioning project, were record, input and managed at the DECOMMIS (DECOMMissioning Information management System). This system was developed for the inputting and management of the data and information of the man-power consumption, operation time of the dismantling equipment, the activities of the radiation control, dismantled waste management and Q/A activities. When a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste volume and estimating the cost of the decommissioning project. That is why, the DEFACS (DEcommissioning FAcility Characterization DB System) was established for the management of the facility characterization data. The DEWOCS (DEcommissioning WOrk-unit productivity Calculation System) was developed for the calculation of the workability on the decommissioning activities. The work-unit productivities are calculated through this system using the data from the two systems, DECOMMIS and DEFACS. This result, the factors of the decommissioning work-unit productivities, will be useful for the other nuclear facility decommissioning planning and engineering. For this, to set up the items and plan for the decommissioning of the new objective facility, the DEMOS (DEcommissioning work Modeling System) was developed. This system is for the evaluation the cost, man-power consumption of workers and project staffs and technology application time. The factor of the work-unit productivities from the DEWOCS and governmental labor cost DB and equipment rental fee DB were used for the calculation the result of the DEMOS. And also, for the total system, DES (Decommissioning Engineering System), which is now

  10. Information management for decommissioning projects

    International Nuclear Information System (INIS)

    LeClair, A.N.; Lemire, D.S.

    2011-01-01

    This paper explores the importance of records and information management for decommissioning projects. Key decommissioning information and elements of a sound information management strategy are identified. Various knowledge management strategies and tools are discussed as opportunities for leveraging decommissioning information. The paper also examines the implementation of Atomic Energy of Canada Limited's (AECL) strategy for the long term preservation of decommissioning information, and its initiatives in leveraging of information with the application of several knowledge management strategies and tools. The implementation of AECL's strategy illustrates common as well as unique information and knowledge management challenges and opportunities for decommissioning projects. (author)

  11. New projects related to decommissioning

    International Nuclear Information System (INIS)

    Benbow, R.

    2008-01-01

    The PMU has been established in support of the KNPP Decommissioning Department. All of the Infrastructure Projects associated with Decommissioning have been identified and are being managed through the EBRD Procurement Process. The status of the following projects is presented: Evaluation of the Radiological Inventory for Units 1 to 4; Supply of Size Reduction and Decontamination Workshops; Dismantling Tools and Equipment; Heat Generation Plant; Environmental Assessment for Decommissioning; Decay Storage Site for Transitional RAW ; Information Centres for Decommissioning; Storage Site for Conventional Waste from Decommissioning; Inventory, Treatment an Conditioning of Contaminated Soil; Concrete Core Sampling Analysis; Asbestos Removal Equipment; Demolition Equipment

  12. The emergence of sustainable practice within decommissioning - 16059

    International Nuclear Information System (INIS)

    Adamson, David William; Francis, Jonathan

    2009-01-01

    Despite the advance of sustainable practice and energy efficient techniques outside of the nuclear industry, at the start of the 21. Century there was a lack of published guidance aimed at their adoption at specifically nuclear facilities. Even with the establishment of the Nuclear Decommissioning Authority, there is very little guidance published on how to adopt sustainable practices during decommissioning. There have been instances where energy efficiency had affected design and operations decisions. Projects aimed at responsible housekeeping, switching off lights, and changes to the nuclear ventilation design philosophy illustrate a desire for action, but these activities were championed by interested and motivated employees. Sustainable practice had not at that time received a strategic lead that resulted in a management structure to enable a coordinated and concerted effort in sustainable practice. This paper traces the progress during the 20. and early 21. Centuries, whereby sustainable practice is now established within a much firmer foundation of case study, guidance and organisational structure; to embed sustainable practice within the United Kingdom's current decommissioning programme. It looks at the development of relevant literature and, through interviews with key managers and external stakeholders, demonstrates (i) the degree to which two essential guidance documents (the NiCOP and CIRIA SD:SPUR) are permeating the industry, (ii) how the current work of the Characterisation and Clearance Group has evolved to influence the decontamination and dismantling planning procedures and (iii) the transition from identifying 'free-release' materials to actually releasing them for re-use in the community. (authors)

  13. Decommissioning of nuclear power plants: policies, strategies and costs

    International Nuclear Information System (INIS)

    Lund, I.

    2004-01-01

    As many nuclear power plants will reach the end of their lifetime during the next 20 years or so, decommissioning is an increasingly important topic for governments, regulators and industries. From a governmental viewpoint, particularly in a deregulated market, one essential aspect is to ensure that money for the decommissioning of nuclear installations will be available at the time it is needed, and that no 'stranded' liabilities will be left to be financed by the taxpayers rather than by the electricity consumers. For this reason, there is governmental interest in understanding decommissioning costs, and in periodically reviewing decommissioning cost estimates from nuclear installation owners. Robust cost estimates are key elements in designing and implementing a coherent and comprehensive national decommissioning policy including the legal and regulatory bases for the collection, saving and use of decommissioning funds. From the industry viewpoint, it is essential to assess and monitor decommissioning costs in order to develop a coherent decommissioning strategy that reflects national policy and assures worker and public safety, whilst also being cost effective. For these reasons, nuclear power plant owners are interested in understanding decommissioning costs as best as possible and in identifying major cost drivers, whether they be policy, strategy or 'physical' in nature. National policy considerations will guide the development of national regulations that are relevant for decommissioning activities. Following these policies and regulations, industrial managers responsible for decommissioning activities will develop strategies which best suit their needs, while appropriately meeting all government requirements. Decommissioning costs will be determined by technical and economic conditions, as well as by the strategy adopted. Against this backdrop, the study analyses the relationships among decommissioning policy as developed by governments, decommissioning

  14. The NEA Co-operative Programme on Decommissioning. A Decade of Progress

    International Nuclear Information System (INIS)

    2006-01-01

    decommissioning techniques like dry abrasive blasting, cutting, removal of biological shielding and decontamination of concrete surfaces. Regarding the use of ventilated suits for workers in specific decommissioning activities, the information exchange in the CPD has helped push programmes to either improve the ventilated suits or to reduce the need for these systems. To address more general issues of common interest the CPD Technical Advisory Group established specific Task Groups. The Task Group on Decommissioning Costs developed, in co-operation with IAEA and EC, a standardised list of items for costing purposes, which allows for comparison of project costs. The Task Group on Recycling and Re-use put together case studies and provided information on the practicality and usefulness of the criteria under development for the release of slightly contaminated material from decommissioning, seen from the perspective of organisations engaged in actual decommissioning operations. Decontamination issues have been addressed by another Task Group that surveyed applied decommissioning techniques and characterised selected techniques in connection with decommissioning. Finally, the Task Group on Release Measurements studied collected relevant data from CPD projects and produced a report giving an overview on equipment and methods for and applications of release measurement. Looking back over the twenty years since the OECD-NEA established the CPD, the Programme has functioned as the main international forum for the exchange of technical and other information arising from nuclear decommissioning projects

  15. Lessons Learned for Decommissioning Planning

    International Nuclear Information System (INIS)

    Sohn, Wook; Kim, Young-gook; Kim, Hee-keun

    2015-01-01

    The purpose of this paper is to introduce the U.S. nuclear industrial's some key lessons learned especially for decommissioning planning based on which well informed decommissioning planning can be carried out. For a successful decommissioning, it is crucial to carry out a well-organized decommissioning planning before the decommissioning starts. This paper discussed four key factors which should be decided or considered carefully during the decommissioning planning period with introduction of related decommissioning lessons learned of U.S. nuclear industry. Those factors which have been discussed in this paper include the end state of a site, the overall decommissioning strategy, the management of the spent fuels, and the spent fuel pool island. Among them, the end state of a site should be decided first as it directs the whole decommissioning processes. Then, decisions on the overall decommissioning strategy (DECON vs. SAFSTOR) and the management of the spent fuels (wet vs. dry) should follow. Finally, the spent fuel pool island should be given due consideration because its implementation will result in much cost saving. Hopefully, the results of this paper would provide useful inputs to performing the decommissioning planing for the Kori unit 1

  16. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the decontamination of plant components and structures at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities in support of the shipment of radioactive wastes and the unconditional release of the site and structural materials. 1 ref., 16 figs., 4 tabs

  17. Challenges for decommissioning policies

    International Nuclear Information System (INIS)

    Riotte, H.

    2007-01-01

    In the coming years, OECD member countries will be increasingly faced with the need to make appropriate provisions, in terms of policy, finance and management, for all aspects of decommissioning. Decommissioning requires regulatory approval and oversight, the directions of which are guided by national policy. In several instances, governments have only recently begun to address their approaches to decommissioning policy and regulation in national legislation, and international overviews of such approaches, which may eventually lead to international harmonization, are only now beginning to emerge. In parallel, policy and regulation have been evolving and a broadened competence has developed in relevant regulatory authorities. The challenge lying ahead is to establish a framework that will allow for the growth of nuclear industrial activities in competitive, globalized markets, while maintaining and assuring the safety of decommissioning for the public and for workers. Within this context, institutional arrangements, stakeholder issues, costs and funding, waste management and policies for release from regulatory control, as well as the availability of technologies and skills, need to be reviewed. (author)

  18. Particle-accelerator decommissioning

    International Nuclear Information System (INIS)

    Opelka, J.H.; Mundis, R.L.; Marmer, G.J.; Peterson, J.M.; Siskind, B.; Kikta, M.J.

    1979-12-01

    Generic considerations involved in decommissioning particle accelerators are examined. There are presently several hundred accelerators operating in the United States that can produce material containing nonnegligible residual radioactivity. Residual radioactivity after final shutdown is generally short-lived induced activity and is localized in hot spots around the beam line. The decommissioning options addressed are mothballing, entombment, dismantlement with interim storage, and dismantlement with disposal. The recycle of components or entire accelerators following dismantlement is a definite possibility and has occurred in the past. Accelerator components can be recycled either immediately at accelerator shutdown or following a period of storage, depending on the nature of induced activation. Considerations of cost, radioactive waste, and radiological health are presented for four prototypic accelerators. Prototypes considered range from small accelerators having minimal amounts of radioactive mmaterial to a very large accelerator having massive components containing nonnegligible amounts of induced activation. Archival information on past decommissionings is presented, and recommendations concerning regulations and accelerator design that will aid in the decommissioning of an accelerator are given

  19. Decommissioning, mothballing and revamping

    International Nuclear Information System (INIS)

    Briggs, M.; Buck, S.; Smith, M.

    1997-01-01

    This guide, written to assist those concerned with the decommissioning of redundant facilities, is applicable to nuclear, chemical and power plants. Legal aspects and risk management is covered in the pre-project stage. Preparation for and execution of renovation, modification or mothballing of various plants is also covered. Dismantling operations and the necessary follow-up conclude the book. (UK)

  20. Decommissioning the WAGR

    Energy Technology Data Exchange (ETDEWEB)

    Lawton, H. (UKAEA Windscale Nuclear Power Development Labs.)

    1982-11-01

    The planned decommissioning of the Windscale Advanced Gas-cooled Reactor, which will take about ten years, is discussed with especial reference to the radioactive decay of the reactor components, the problems of disposal of the resulting radioactive waste, and the planning of the necessary engineering works.

  1. Decommissioning the WAGR

    International Nuclear Information System (INIS)

    Lawton, H.

    1982-01-01

    The planned decommissioning of the Windscale Advanced Gas-cooled Reactor, which will take about ten years, is discussed with especial reference to the radioactive decay of the reactor components, the problems of disposal of the resulting radioactive waste, and the planning of the necessary engineering works. (U.K.)

  2. Assessment methodology applicable to safe decommissioning of Romanian VVR-S research reactor

    International Nuclear Information System (INIS)

    Baniu, O.; Vladescu, G.; Vidican, D.; Penescu, M.

    2002-01-01

    The paper contains the results of research activity performed by CITON specialists regarding the assessment methodology intended to be applied to safe decommissioning of the research reactors, developed taking into account specific conditions of the Romanian VVR-S Research Reactor. The Romanian VVR-S Research Reactor is an old reactor (1957) and its Decommissioning Plan is under study. The main topics of paper are as follows: Safety approach of nuclear facilities decommissioning. Applicable safety principles; Main steps of the proposed assessment methodology; Generic content of Decommissioning Plan. Main decommissioning activities. Discussion about the proposed Decommissioning Plan for Romanian Research Reactor; Safety risks which may occur during decommissioning activities. Normal decommissioning operations. Fault conditions. Internal and external hazards; Typical development of a scenario. Features, Events and Processes List. Exposure pathways. Calculation methodology. (author)

  3. Economical aspect of the decommissioning for NPP

    International Nuclear Information System (INIS)

    Daryoko, M.

    1998-01-01

    The estimated, analysed and founding of the economical aspect at decommissioning of Nuclear Power Plant (NPP) have been studied. The data that have been obtained from literature, then the calculation and analysing have been done base to the future condition. The cost for NPP decommissioning depend on the internal factor such as type, capacity and safe storage time, and the external factor such as policy, manpower and the technology preparation. The successfulness of funding, depend on the rate of inflation, discount rate of interest and the currency fluctuation. For the internal factor, the influence of the type of the reactor (BWR or PWR) to the decommissioning cost is negligible, the big reactor capacity (±1100 MW), and the safe storage between 30 to 100 years are recommended, and for the external factor, specially Indonesia, to meet the future need the ratio of decommissioning cost and capital cost will be lower than in develop countries at the present (10%). The ratio between decommissioning fund and electricity generation cost relatively very low, are more less than 1.79 % for 30 years safe storage, and discount rate of interest 3%, or more less than 0.30 % for safe storage 30 years, and discount rate of interest 6%. (author)

  4. Management of safety and safety culture in regulatory work - The case of decommissioning of a Swedish plant

    International Nuclear Information System (INIS)

    Svensson, G.; Lekberg, A.

    2002-01-01

    The case of early closure of one of the units at a plant is one example of a situation where the regulator has to reflect on and choose its role in order to prevent an impairment of the safety culture at the plant. The strategy chosen by the Swedish Nuclear Power Inspectorate is presented and some conclusions are drawn. (author)

  5. Decommissioning strategy for reactor AM, Russian Federation

    International Nuclear Information System (INIS)

    Suvorov, A.P.; Mukhamadeev, R.I.

    2002-01-01

    This paper presents the results of studies into the various aspects of decommissioning the oldest Russian research reactor, the AM reactor. Experimental and calculation results of a study to determine the inventory of long lived radioactive materials at the AM reactor are presented, along with a comparison to comparable data for other similar reactors. An analysis, by calculation, of the decay time needed to allow manual dismantling of the reactor vessel and stack, without remote operated equipment, defined it as 90 years. The possibility of burning most of the irradiated graphite to decrease the amount of long lived radioactive wastes was confirmed. The problems associated with the dismantling of the reactor components, contaminated with radioactive corrosion products, were analyzed. A decommissioning strategy for reactor AM was formed which is deferred dismantling, placing most of the radiological areas into long term safe enclosure. An overall decommissioning plan for reactor AM is given. (author)

  6. Cost Estimation for Research Reactor Decommissioning

    International Nuclear Information System (INIS)

    2013-01-01

    Economic Co-operation and Development/Nuclear Energy Agency, and the European Commission as the general platform for decommissioning cost estimation purposes. Use of the ISDC based model facilitates the preliminary costing stages in the absence of decommissioning plans. For proper establishment of the costing case, the intended decommissioning strategy is used. The model should be flexible as to the extent and details of the inventory data. The impact of individual inventory items (working constraints) should be respected. Implementing the ISDC as the basis for the cost calculation structure ensures compatibility with the IAEA classification scheme for radioactive waste. The developed tool is intended for experts who are familiar with the facility, such as the former or actual operators of research reactors. A basic knowledge of decommissioning issues is recommended. (author)

  7. Decommissioning and material recycling. Radiation risk management issues

    International Nuclear Information System (INIS)

    Dodd, D.H.

    1996-09-01

    Once nuclear fuel cycle facilities have permanently stopped operations they have to be decommissioned. The decommissioning of a nuclear facility involves the surveillance and dismantling of the facility systems and buildings, the management of the materials resulting from the dismantling activities and the release of the site for further use. The management of radiation risks associated with these activities plays an important role in the decommissioning process. Existing legislation covers many aspects of the decommissioning process. However, in most countries with nuclear power programmes legislation with respect to decommissioning is incomplete. In particular this is true in the Netherlands, where government policy with respect to decommissioning is still in development. Therefore a study was performed to obtain an overview of the radiation risk management issues associated with decommissioning and the status of the relevant legislation. This report describes the results of that study. It is concluded that future work at the Netherlands Energy Research Foundation on decommissioning and radiation risk management issues should concentrate on surveillance and dismantling activities and on criteria for site release. (orig.)

  8. Project management case studies

    CERN Document Server

    Kerzner, Harold R

    2013-01-01

    A new edition of the most popular book of project management case studies, expanded to include more than 100 cases plus a ""super case"" on the Iridium Project Case studies are an important part of project management education and training. This Fourth Edition of Harold Kerzner''s Project Management Case Studies features a number of new cases covering value measurement in project management. Also included is the well-received ""super case,"" which covers all aspects of project management and may be used as a capstone for a course. This new edition:Contains 100-plus case studies drawn from re

  9. Case Study Research Methodology

    Directory of Open Access Journals (Sweden)

    Mark Widdowson

    2011-01-01

    Full Text Available Commenting on the lack of case studies published in modern psychotherapy publications, the author reviews the strengths of case study methodology and responds to common criticisms, before providing a summary of types of case studies including clinical, experimental and naturalistic. Suggestions are included for developing systematic case studies and brief descriptions are given of a range of research resources relating to outcome and process measures. Examples of a pragmatic case study design and a hermeneutic single-case efficacy design are given and the paper concludes with some ethical considerations and an exhortation to the TA community to engage more widely in case study research.

  10. Development of improved technology for decommissioning operations

    International Nuclear Information System (INIS)

    Allen, R.P.

    1982-07-01

    This paper describes the technology development activities conducted at Pacific Northwest Laboratory under US Department of Energy sponsorship to help ensure the availability of safe, cost-effective and environmentally sound decommissioning technology for radioactively contaminated facilities. These improved decommissioning technologies include techniques for the removal of contaminated concrete surfaces and coatings, adaptation of electropolishing and vibratory finishing decontamination techniques for field decommissioning applications, development of sensitive field instrumentation and methods for the monitoring of large surface areas, techniques for the field sectioning of contaminated components, improved contamination-stabilizing coatings and application methods, and development of a small solidification system for the field solidification of liquid waste. The results of cost/benefit studies for some of these technologies are also reported

  11. The Role of Stakeholders in the Decommissioning of Salaspils Research Reactor

    International Nuclear Information System (INIS)

    Abramenkovs, A.

    2009-01-01

    The paper describes the role of different stakeholders in the decommissioning of the Salaspils Research Reactor. Decommissioning was a large challenge for the Latvia, since the country in this moment had no decommissioning experience and necessary technologies for the implementation of the defined goals by the Government. In this case for facilitation of the decommissioning of Salaspils Research Reactor (SRR), the significant role plays the local and international stakeholders. The paper deals with information on the basic stages of decommissioning of SRR and the role of the wide spectrum of stakeholders in preparation, upgrade and implementation of the decommissioning plan. The role of governmental institutions in the decommissioning of Salaspils research reactor is discussed. It was shown, that local municipalities are very important stakeholders, which significantly influence the decommissioning of SRR. The Salaspils municipalities positive impact on the decommissioning processes are discussed. Basic problems with the Baldone municipality in context of radioactive wastes management are indicated. The role of international stakeholders in decommissioning of Salaspils research reactor is discussed. It was shown, that the support from International Atomic Energy Agency significantly promotes the decommissioning of SRR. The main issues were expert support for solution of different technical problems in radioactive wastes management, area monitoring, and verification of decommissioning plans, training of staff and technical expertise during whole process of decommissioning. It was shown, that technical and economical support from DOE, USA provides the possibility to solve the fuel problem during decommissioning of SRR, as well as, to increase the physical safety of SRR and repository 'Radons'. It was shown, that a proper coordination of all activities and using the services from stakeholders can significantly reduce the total project expenses. The cooperation between

  12. Structure and function design for nuclear facilities decommissioning information database

    International Nuclear Information System (INIS)

    Liu Yongkuo; Song Yi; Wu Xiaotian; Liu Zhen

    2014-01-01

    The decommissioning of nuclear facilities is a radioactive and high-risk project which has to consider the effect of radiation and nuclear waste disposal, so the information system of nuclear facilities decommissioning project must be established to ensure the safety of the project. In this study, by collecting the decommissioning activity data, the decommissioning database was established, and based on the database, the decommissioning information database (DID) was developed. The DID can perform some basic operations, such as input, delete, modification and query of the decommissioning information data, and in accordance with processing characteristics of various types of information data, it can also perform information management with different function models. On this basis, analysis of the different information data will be done. The system is helpful for enhancing the management capability of the decommissioning process and optimizing the arrangements of the project, it also can reduce radiation dose of the workers, so the system is quite necessary for safe decommissioning of nuclear facilities. (authors)

  13. Decommissioning project management unit started its activities

    International Nuclear Information System (INIS)

    Medeliene, D.

    2002-01-01

    The Decommissioning Project Management Unit team comprises western experts as well as experts from INPP Decommissioning Service who all work as a single team. The DPMU will develop the Final Decommissioning Plan and a more detailed Decommissioning Project, which will describe how the plant will be removed from service and safely decommissioned

  14. Decommissioning of NPP A1 - HWGCR type

    International Nuclear Information System (INIS)

    Burclova, J.

    1998-01-01

    Prototype nuclear power plant A-1 located at Jaslovske Bohunice, was a HWGCR with channel type reactor KS 150 (refuelling during operation) and capacity of 143 MWe. Single unit has been constructed with reactor hall building containing reactor vessel, heavy water system and equipment for spent fuel handling. Another compartment of main building contents coolant system piping, six steam generators and six turbo compressors, the turbine hall was equipped by three turbines. Unit also shares liquid radwaste treatment and storage buildings and ventilation systems including chimney. It started operation in 1972 and was shutdown in 1977 after primary coolant system integrity accident. In 1979 a final decision was made to decommission this plant. The absence of waste treatment technologies and repository and not sufficient storage capacity affected the planning and realization of decommissioning for NPP A-1. The decommissioning policy for the first stage is for lack of regulations based on 'case by case' strategy. For these reasons and for not existence of Decommissioning Found until 1995 the preferred decommissioning option is based on differed decommissioning with safe enclosure of confinement. Transfer of undamaged spent fuel cooled in organic coolant to Russia was finished in 1990. It was necessary to develop new technology for the damaged fuel preparation for transport. The barriers check-up and dismantling of secondary circuit and cooling towers was performed during 1989/90. The complex plan for the first phase of A-1 decommissioning - the status with treated operational radwaste, removed contamination and restored treated waste and spent fuel (in case of interruption of transfer to Russia) was developed in 1993-1994. Under this project bituminization of all liquid operational radwaste (concentrates) was performed during 1995/96, vitrification of inorganic spent fuel coolant started at 1996, decontamination of spent fuel pool coolant occurs (under AEA Technology

  15. The Impact of Severe Nuclear Accidents on National Decision for Nuclear Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Suh, Young A; Hornibrook, Carol; Yim, Man Sung [KAIST, Daejeon (Korea, Republic of)

    2016-05-15

    Many researchers have tried to identify the impact of severe nuclear accidents on a country's or international nuclear energy policy [2-3]. However, there is little research on the influence of nuclear accidents and historical events on a country's decision to permanently shutdown an NPP versus international nuclear decommissioning trends. To demonstrate the correlation between a nuclear severe accident and the impact on world nuclear decommissioning, this research reviewed case studies of individual historical events, such as the St. Lucens, TMI, Chernobyl, Fukushima accidents and the series of events leading up to the collapse of the Soviet Union. For validation of the results of these case studies, a statistical analysis was conducted using the R code. This will be useful in explaining how international and national decommissioning strategies are affected by shutdown reasons, i.e. world historical events. The number of permanently shutdown NPPs was selected as an indicator because any relationship between the number of permanently In conclusion, nuclear severe accidents and historical events have an impact on the number of international NPPs that shutdown permanently and cancelled NPP construction. This directly impacts international nuclear decommissioning policy and nuclear energy policy trends. The number of permanently shutdown NPPs was selected as an indicator because any relationship between the number of permanently.

  16. The Impact of Severe Nuclear Accidents on National Decision for Nuclear Decommissioning

    International Nuclear Information System (INIS)

    Suh, Young A; Hornibrook, Carol; Yim, Man Sung

    2016-01-01

    Many researchers have tried to identify the impact of severe nuclear accidents on a country's or international nuclear energy policy [2-3]. However, there is little research on the influence of nuclear accidents and historical events on a country's decision to permanently shutdown an NPP versus international nuclear decommissioning trends. To demonstrate the correlation between a nuclear severe accident and the impact on world nuclear decommissioning, this research reviewed case studies of individual historical events, such as the St. Lucens, TMI, Chernobyl, Fukushima accidents and the series of events leading up to the collapse of the Soviet Union. For validation of the results of these case studies, a statistical analysis was conducted using the R code. This will be useful in explaining how international and national decommissioning strategies are affected by shutdown reasons, i.e. world historical events. The number of permanently shutdown NPPs was selected as an indicator because any relationship between the number of permanently In conclusion, nuclear severe accidents and historical events have an impact on the number of international NPPs that shutdown permanently and cancelled NPP construction. This directly impacts international nuclear decommissioning policy and nuclear energy policy trends. The number of permanently shutdown NPPs was selected as an indicator because any relationship between the number of permanently

  17. Technology, safety and costs of decommissioning a refernce boiling water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies of conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference boiling water reactor (BWR) described in the earlier study; and defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs. This report presents the results of recent PNL studies to provide supporting information in three areas concerning decommissioning of the reference BWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation

  18. Guidelines for estimating nuclear power plant decommissioning costs

    International Nuclear Information System (INIS)

    LaGuardia, T.S.; Williams, D.H.

    1989-01-01

    The objectives of the study were: (1) To develop guidelines to facilitate estimating the cost of nuclear power plant decommissioning alternatives on a plant-specific basis and to facilitate comparing estimates made by others. The guidelines are expressed in a form that could be readily adapted by technical specialists from individual utilities or by other uses. (2) To enhance the industry's credibility with decision-makes at the state and federal levels during rate/regulatory processes involving decommissioning costs. This is accomplished by providing a detailed, systematic breakdown of how decommissioning cost estimates are prepared. (3) To increase the validity, realism, and accuracy of site-specific decommissioning cost estimates. This is accomplished by pulling together the experiences and practices of several nuclear utilities and consultants in conducting past decommissioning cost estimates

  19. Decommissioning and equipment replacement of nuclear power plants under uncertainty

    International Nuclear Information System (INIS)

    Takashima, Ryuta; Naito, Yuta; Kimura, Hiroshi; Madarame, Haruki

    2007-01-01

    This study examines the optimal timing for the decommissioning and equipment replacement of nuclear power plants. We consider that the firm has two options of decommissioning and equipment replacement, and determines to exercise these options under electricity price uncertainty. This problem is formulated as two optimal stopping problems. The solution of this model provides the value of the nuclear power plant and the threshold values for decommissioning and replacement. The dependence of decommissioning and replacement strategies on uncertainty and each cost is shown. In order to investigate the probability of events for decommissioning and replacement, Monte Carlo calculations are performed. We also show the probability distribution and the conditional expected time for each event. (author)

  20. Towards Greater Harmonisation of Decommissioning Cost Estimates

    International Nuclear Information System (INIS)

    O'Sullivan, Patrick; ); Laraia, Michele; ); LaGuardia, Thomas S.

    2010-01-01

    The NEA Decommissioning Cost Estimation Group (DCEG), in collaboration with the IAEA Waste Technology Section and the EC Directorate-General for Energy and Transport, has recently studied cost estimation practices in 12 countries - Belgium, Canada, France, Germany, Italy, Japan, the Netherlands, Slovakia, Spain, Sweden, the United Kingdom and the United States. Its findings are to be published in an OECD/NEA report entitled Cost Estimation for Decommissioning: An International Overview of Cost Elements, Estimation Practices and Reporting Requirements. This booklet highlights the findings contained in the full report. (authors)

  1. INTERNATIONAL DECOMMISSIONING SYMPOSIUM 2000

    Energy Technology Data Exchange (ETDEWEB)

    M.A. Ebadian, Ph.D.

    2001-01-01

    The purpose of IDS 2000 was to deliver a world-class conference on applicable global environmental issues. The objective of this conference was to publicize environmental progress of individual countries, to provide a forum for technology developer and problem-holder interaction, to facilitate environmental and technology discussions between the commercial and financial communities, and to accommodate information and education exchange between governments, industries, universities, and scientists. The scope of this project included the planning and execution of an international conference on the decommissioning of nuclear facilities, and the providing of a business forum for vendors and participants sufficient to attract service providers, technology developers, and the business and financial communities. These groups, when working together with attendees from regulatory organizations and government decision-maker groups, provide an opportunity to more effectively and efficiently expedite the decommissioning projects.

  2. Decommissioning a nuclear reactor

    International Nuclear Information System (INIS)

    Montoya, G.M.

    1991-01-01

    The process of decommissioning a facility such as a nuclear reactor or reprocessing plant presents many waste management options and concerns. Waste minimization is a primary consideration, along with protecting a personnel and the environment. Waste management is complicated in that both radioactive and chemical hazardous wastes must be dealt with. This paper presents the general decommissioning approach of a recent project at Los Alamos. Included are the following technical objectives: site characterization work that provided a thorough physical, chemical, and radiological assessment of the contamination at the site; demonstration of the safe and cost-effective dismantlement of a highly contaminated and activated nuclear-fuelded reactor; and techniques used in minimizing radioactive and hazardous waste. 12 figs

  3. The decommissioning and redevelopment of NECSA site

    International Nuclear Information System (INIS)

    Visagie, A.L.; Fourie, E.

    2008-01-01

    Full text: The South African nuclear programme started in 1948 and was focussed on research and development in the nuclear field. In the early 70s a uranium conversion plant and a uranium enrichment plant were constructed on the NECSA site. The enriched uranium was used for military purposes, as fuel for the research reactor SAFARI-1 at Necsa. A semi-commercial uranium enrichment plant and a fuel manufacturing plant were commissioned in the 80's to supply fuel for the nuclear power plant at Koeberg near Cape Town. Currently the research reactor is utilized for the generation of radioactive isotopes for industrial and medical applications. Various other research projects were initiated and buildings constructed on the Necsa site to accommodate the different projects. The uranium conversion and enrichment projects were terminated in the early 90's, and many buildings on the Necsa site became redundant. An initial decommissioning strategy was to return the Necsa site to green fields. This endpoint of decommissioning has changed dramatically with the nuclear renaissance to include redevelopment and reuse options. In the case of a multi-facility nuclear site, such as the Necsa site, it is vital to develop a total site redevelopment plan rather than to decommission and allocate individual facilities for isolated reuse demands. A holistic approach should be assured by considering current and projected future redevelopment demands in the development of a redevelopment and reuse plan. It is important not to allow the redevelopment and reuse of a single facility on a multi-facility site based on short- term financial gain. With the recent increase in demand for nuclear facilities the redevelopment and reuse of nuclear facilities for non-nuclear applications should generally not be considered due to the inherent advantages associated with an existing licensed site. The initial decommissioning plan did not consider the Necsa site as a whole. Decommissioning costs, and the

  4. Offshore decommissioning issues: Deductibility and transferability

    International Nuclear Information System (INIS)

    Parente, Virginia; Ferreira, Doneivan; Moutinho dos Santos, Edmilson; Luczynski, Estanislau

    2006-01-01

    Dealing with the decommissioning of petroleum installations is a relatively new challenge to most producer countries. It is natural to expect that industry's experience in building platforms is much greater than the one of dismantling them. Even if manifold and varied efforts are underway towards establishing international 'best practices' standards in this sector, countries still enjoy rather extensive discretionary power as they practice a particular national style in the regulation of decommissioning activities in their state's jurisdiction. The present paper offers a broad panorama of this discussion, concentrating mainly on two controversial aspects. The first one analyses the ex-ante deductibility of decommissioning costs as they constitute an ex-post expense. The second discussion refers to the assignment of decommissioning responsibility in the case of transfer of exploration and production rights to new lessees during the project's life. Finally the paper applies concepts commonly used in project financing as well as structures generally used in organising pension funds to develop insights into these discussions

  5. Offshore decommissioning issues: deductibility and transferability

    Energy Technology Data Exchange (ETDEWEB)

    Parente, V.; Santos, M. dos [University of Sao Paulo (Brazil). Instituto de Electrotecnica; Ferreira, D. [State University of Campinas (Brazil). Dept. of Geology and Natural Resources; Luczynski, E. [Grupo de Estudos e Pesquisas Economico-Energeticas, Belem (Brazil)

    2006-10-15

    Dealing with the decommissioning of petroleum installations is a relatively new challenge to most producer countries. It is natural to expect that industry's experience in building platforms is much greater than the one of dismantling them. Even if manifold and varied efforts are underway towards establishing international ''best practices'' standards in this sector, countries still enjoy rather extensive discretionary power as they practice a particular national style in the regulation of decommissioning activities in their state's jurisdiction. The present paper offers a broad panorama of this discussion, concentrating mainly on two controversial aspects. The first one analyses the ex-ante deductibility of decommissioning costs as they constitute an ex-post expense. The second discussion refers to the assignment of decommissioning responsibility in the case of transfer of exploration and production rights to new lessees during the project's life. Finally the paper applies concepts commonly used in project financing as well as structures generally used in organising pension funds to develop insights into these discussions. (author)

  6. BN-350 nuclear power plant. Regulatory aspects of decommissioning

    International Nuclear Information System (INIS)

    Shiganakov, S.; Zhantikin, T.; Kim, A.

    2002-01-01

    regulations valid in the Republic of Kazakhstan and to IAEA recommendations. In a case of absence of the regulatory documentation BN-350 decommissioning works shall be performed in accordance with the standards existing for operational facilities after they have been approved by KAEC. (author)

  7. Decommissioning Facility Characterization DB System

    International Nuclear Information System (INIS)

    Park, S. K.; Ji, Y. H.; Park, J. H.; Chung, U. S.

    2010-01-01

    Basically, when a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste and estimating the cost of the decommissioning project. In this paper, it is presented a computer system for the characterization of nuclear facilities, called DEFACS (DEcommissioning FAcility Characterization DB System). This system consists of four main parts: a management coding system for grouping items, a data input system, a data processing system and a data output system. All data is processed in a simplified and formatted manner in order to provide useful information to the decommissioning planner. For the hardware, PC grade computers running Oracle software on Microsoft Windows OS were selected. The characterization data results for the nuclear facility under decommissioning will be utilized for the work-unit productivity calculation system and decommissioning engineering system as basic sources of information

  8. Decommissioning Facility Characterization DB System

    Energy Technology Data Exchange (ETDEWEB)

    Park, S. K.; Ji, Y. H.; Park, J. H.; Chung, U. S. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2010-10-15

    Basically, when a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste and estimating the cost of the decommissioning project. In this paper, it is presented a computer system for the characterization of nuclear facilities, called DEFACS (DEcommissioning FAcility Characterization DB System). This system consists of four main parts: a management coding system for grouping items, a data input system, a data processing system and a data output system. All data is processed in a simplified and formatted manner in order to provide useful information to the decommissioning planner. For the hardware, PC grade computers running Oracle software on Microsoft Windows OS were selected. The characterization data results for the nuclear facility under decommissioning will be utilized for the work-unit productivity calculation system and decommissioning engineering system as basic sources of information

  9. Fort St. Vrain decommissioning project

    International Nuclear Information System (INIS)

    Fisher, M.

    1998-01-01

    Public Service Company of Colorado (PSCo), owner of the Fort St. Vrain nuclear generating station, achieved its final decommissioning goal on August 5, 1997 when the Nuclear Regulatory Commission terminated the Part 50 reactor license. PSCo pioneered and completed the world's first successful decommissioning of a commercial nuclear power plant after many years of operation. In August 1989, PSCo decided to permanently shutdown the reactor and proceed with its decommissioning. The decision to proceed with early dismantlement as the appropriate decommissioning method proved wise for all stake holders - present and future - by mitigating potential environmental impacts and reducing financial risks to company shareholders, customers, employees, neighboring communities and regulators. We believe that PSCo's decommissioning process set an exemplary standard for the world's nuclear industry and provided leadership, innovation, advancement and distinguished contributions to other decommissioning efforts throughout the world. (author)

  10. Decommissioning of nuclear power facilities

    International Nuclear Information System (INIS)

    Nosovskij, A.V.; Vasil'chenko, V.N.; Klyuchnikov, A.A.; Yashchenko, Ya.V.

    2005-01-01

    This is the first manual in Ukraine giving the complete review of the decommissioning process of the nuclear power facilities including the issues of the planning, design documentation development, advanced technology description. On the base of the international and domestic experience, the issues on the radwaste management, the decontamination methods, the equipment dismantling, the remote technology application, and also the costs estimate at decommissioning are considered. The special attention to the personnel safety provision, population and environment at decommissioning process is paid

  11. Decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Vollradt, J.

    1977-01-01

    A survey of the main questions of decommissioning of nuclear power plants will be given in the sight of German utilities (VDEW-Working group 'Stillegung'). The main topics are: 1) Definitions of decommissioning, entombment, removal and combinations of such alternatives; 2) Radioactive inventory (build up and decay); 3) Experience up to now; 4) Possibilities to dismantle are given by possibility to repair nuclear power plants; 5) Estimated costs, waste, occupational radiation dose; 6) German concept of decommissioning. (orig./HK) [de

  12. When a plant shuts down: The psychology of decommissioning

    International Nuclear Information System (INIS)

    Schulz, J.; Crawford, A.C.

    1993-01-01

    Within the next decade, 10 to 25 nuclear plants in the United States may be taken off line. Many will have reached the end of their 40-year life cycles, but others will be retired because the cost of operating them has begun to outweigh their economic benefit. Such was the case at Fort St. Vrain, the first decommissioning of a US commercial plant under new Nuclear Regulatory Commission (NRC) regulations. Two major problems associated with decommissioning plants have been obvious: (1) the technical challenges and costs of decommissioning, and (2) the cost of maintaining and finally decommissioning a plant after a safe storage (SAFSTOR) period of approximately 60 years. What has received little attention is the challenge that affects not only the people who make a plant work, but the quality of the solutions to these problems: how to maintain effective organizational performance during the process of downsizing and decommissioning and/or SAFSTOR. The quality of technical solutions for closing a plant, as well as how successfully the decommissioning process is held within or below budget, will depend largely on how effectively the nuclear organization functions as a social unit. Technical and people issues are bound together. The difficulty is how to operate a plant effectively when plant personnel have no sense of long-term security. As the nuclear power industry matures and the pace for closing operating plants accelerates, the time has come to prepare for the widespread decommissioning of plants. The industry would be well served by conducting a selective, industry-wide evaluation of plants to assess its overall readiness for the decommissioning process. A decommissioning is not likely to be trouble free, but with a healthy appreciation for the human side of the process, it will undoubtedly go more smoothly than if approached as a matter of dismantling a machine

  13. Technology, safety, and costs of decommissioning a reference large irradiator and reference sealed sources

    Energy Technology Data Exchange (ETDEWEB)

    Haffner, D.R.; Villelgas, A.J. [Pacific Northwest Lab., Richland, WA (United States)

    1996-01-01

    This report contains the results of a study sponsored by the US Nuclear Regulatory Commission (NRC) to examine the decommissioning of large radioactive irradiators and their respective facilities, and a broad spectrum of sealed radioactive sources and their respective devices. Conceptual decommissioning activities are identified, and the technology, safety, and costs (in early 1993 dollars) associated with decommissioning the reference large irradiator and sealed source facilities are evaluated. The study provides bases and background data for possible future NRC rulemaking regarding decommissioning, for evaluation of the reasonableness of planned decommissioning actions, and for determining if adequate funds are reserved by the licensees for decommissioning of their large irradiator or sealed source facilities. Another purpose of this study is to provide background and information to assist licensees in planning and carrying out the decommissioning of their sealed radioactive sources and respective facilities.

  14. Economic Evaluation of Decommissioning Cost of Nuclear Power Plant in the National Electricity Plan in Korea

    International Nuclear Information System (INIS)

    Lee, Man Ki; Nam, Ji Hee

    2008-01-01

    Decommissioning cost of a nuclear power plant includes the costs related with dismantling a nuclear power plant, disposal of a spent fuel and of a low/medium radioactive waste. The decommissioning cost is different from the other expenditures in that it is occurred after the reactor finishes its commercial operation. In this respect, the electricity act was enforced to secure provisions for decommissioning a nuclear power plant during its commercial operation. The purpose of this study is to provide economic evaluation and economic cost for a decommissioning when the cost of a decommissioning is provided as one of input to the national electricity plan. Therefore, this study does not deal with whether the estimated amount of a decommissioning cost is just or not. This study focuses how to transfer the estimated decommissioning cost given in the electricity act to the economic cost, which can be used in the national electricity plan

  15. Technology, safety, and costs of decommissioning a reference large irradiator and reference sealed sources

    International Nuclear Information System (INIS)

    Haffner, D.R.; Villelgas, A.J.

    1996-01-01

    This report contains the results of a study sponsored by the US Nuclear Regulatory Commission (NRC) to examine the decommissioning of large radioactive irradiators and their respective facilities, and a broad spectrum of sealed radioactive sources and their respective devices. Conceptual decommissioning activities are identified, and the technology, safety, and costs (in early 1993 dollars) associated with decommissioning the reference large irradiator and sealed source facilities are evaluated. The study provides bases and background data for possible future NRC rulemaking regarding decommissioning, for evaluation of the reasonableness of planned decommissioning actions, and for determining if adequate funds are reserved by the licensees for decommissioning of their large irradiator or sealed source facilities. Another purpose of this study is to provide background and information to assist licensees in planning and carrying out the decommissioning of their sealed radioactive sources and respective facilities

  16. Decommissioning of Salaspils nuclear reactor

    International Nuclear Information System (INIS)

    Abramenkovs, A.; Malnachs, J.; Popelis, A.

    2002-01-01

    In May 1995, the Latvian Government decided to shut down the Research Reactor Salaspils (SRR) and to dispense with nuclear energy in future. The reactor has been out of operation since July 1998. A conceptual study for the decommissioning of SRR has been carried out by Noell-KRC-Energie- und Umwelttechnik GmbH from 1998-1999. he Latvian Government decided on 26 October 1999 to start the direct dismantling to 'green field' in 2001. The results of decommissioning and dismantling performed in 1999-2001 are presented and discussed. The main efforts were devoted to collecting and conditioning 'historical' radioactive waste from different storages outside and inside the reactor hall. All radioactive material more than 20 tons were conditioned in concrete containers for disposal in the radioactive waste depository 'Radons' in the Baldone site. Personal protective and radiation measurement equipment was upgraded significantly. All non-radioactive equipment and material outside the reactor buildings were free-released and dismantled for reuse or conventional disposal. Weakly contaminated material from the reactor hall was collected and removed for free-release measurements. The technology of dismantling of the reactor's systems, i.e. second cooling circuit, zero power reactors and equipment, is discussed in the paper. (author)

  17. The decommissioning of a small nuclear reactor

    International Nuclear Information System (INIS)

    Neset, K.; Christensen, G.C.; Lundby, J.E.; Roenneberg, G.A.

    1990-02-01

    The JEEP II reactor at Kjeller, Norway has been used as a model for a study of the decommissioning of a small research reactor. A radiological survey is given and a plan for volume reducing, packaging, certifying, classifying and shipping of the radioactive waste is described. 23 refs., 4 figs

  18. Radiological characterization and challenges at decommissioning sites

    International Nuclear Information System (INIS)

    Moore, Scott

    2002-01-01

    Scott Moore described the dose-based radiological characterisation process used in the USA, and four current characterisation issues faced there. His paper emphasized the importance of characterisation to control decommissioning hazards and costs: The License Termination Rule (LTR), Subpart E to 10 CFR Part 20, provides the dose-based criteria that the U.S. Nuclear Regulatory Commission (NRC) uses as the basis for regulating cleanup at material and reactor sites. The LTR permits the release of sites for unrestricted use, if the radioactivity that is distinguishable from background results in a total effective dose equivalent to an average member of a critical group that does not exceed 0.25 milli-Sievert per year (mSv/yr) (25 milli-rem/year) and the residual radioactivity has been reduced to levels that are as low as reasonably achievable. Additionally, the LTR establishes criteria for license termination with restrictions on future land use, which allow for a dose to the critical group of 0.25 mSv/yr (25 milli-rem/year) with restrictions in place, and 1 mSv/yr (100 milli-rem/year) if the restrictions fail. In certain circumstances as outlined in Subpart E, a dose as high as 5 mSv/yr (500 milli-rem/year) is permitted if restrictions fail. Following issuance of the dose-based LTR in 1997, NRC staff developed the Standard Review Plan for Decommissioning Plans (NUREG-1727). NUREG-1727 is a guidance document that describes the methods that NRC has determined are acceptable for implementing the LTR and other decommissioning regulations. While NUREG-1727 is focused on the review of decommissioning plans for nuclear material sites, it provides general guidance that in many cases is applicable to reactor sites (e.g., review criteria for dose-modeling and radiological surveys). In addition to NUREG-1727, staff developed the Standard Review Plan for Evaluating Nuclear Power Reactor License Termination Plans (NUREG-1700) as specific guidance for reactor decommissioning. NUREG

  19. International Good Practice on Practical Implementation of Characterisation in Decommissioning. Radiological Characterization in Decommissioning of Nuclear Facilities: International Good Practice on Practical Implementation

    International Nuclear Information System (INIS)

    Larsson, A.; Empdage, M.; Weber, I.; )

    2017-01-01

    Within the Nuclear Energy Agency (NEA), the Working Party on Decommissioning and Dismantling (WPDD) operates under the umbrella of the Radioactive Waste Management Committee (RWMC). The WPDD provides a focus for the analysis of decommissioning policy, strategy and regulation, including the related issues of waste management, release of buildings and sites from regulatory control and associated cost estimation and funding. WPDD also convenes task groups comprised of experts from the NEA member countries to review related topics such as characterisation techniques which support decommissioning and associated waste management. The Task Group on Radiological Characterisation and Decommissioning was established in 2011 to identify and present characterisation good practice at different stages of decommissioning and to identify areas that could, or should, be developed further through international cooperation and coordination. By the end of 2016 two phases of work will be complete. The first phase developed strategic guidance for decision makers on the selection and tailoring of strategies for radiological characterisation, which gives an overview of good practice for radiological characterisation at different phases of the life cycle of a nuclear installation. The second phase has focused on strategies for practical implementation of radiological characterisation from a waste and materials end-state perspective. This paper provides a summary of the phase 2 findings, covering: -) a major international survey (questionnaire) to elicit the views of characterisation experts regarding good practice; -) Learning drawn from recent international case studies; -) The collation and analysis of regulations, standards and guidance documents; -) Learning distilled from an international conference on characterisation co-organised by the task group; and -) Overall conclusions regarding characterisation good practice, recommendations and identified areas for further international

  20. Conceptual data modeling on the KRR-1 and 2 decommissioning database

    International Nuclear Information System (INIS)

    Park, Hee Seoung; Park, Seung Kook; Lee, Kune Woo; Park, Jin Ho

    2002-01-01

    A study of the conceptual data modeling to realize the decommissioning database on the KRR-1 and 2 was carried out. In this study, the current state of the abroad decommissioning databased was investigated to make a reference of the database. A scope of the construction of decommissioning database has been set up based on user requirements. Then, a theory of the database construction was established and a scheme on the decommissioning information was classified. The facility information, work information, radioactive waste information, and radiological information dealing with the decommissioning database were extracted through interviews with an expert group and also decided upon the system configuration of the decommissioning database. A code which is composed of 17 bit was produced considering the construction, scheme and information. The results of the conceptual data modeling and the classification scheme will be used as basic data to create a prototype design of the decommissioning database

  1. Study on the design and manufacturing requirements of container for low level radioactive solid waste form KRR decommissioning

    International Nuclear Information System (INIS)

    Lee, D. K.; Kim, H. R.; Park, S. K.; Jung, K. H.; Jung, W. S.; Jung, K. J.

    2000-01-01

    The design requirement and manufacturing criteria have been proposed on the container for the storage and transportation of low level radioactive solid waste from decommissioning of KRR 1 and 2. The structure analysis was carried out based on the design criteria, and the safety of the container was assessed. The ISO container with its capacity of 4m 3 was selected for the radioactive solid waste storage. The proposed container was satisfied the criteria of ISO 1496/1 and the packaging standard of atomic energy act. manufacturing and test standards of IAEA were also applied to the container. Stress distribution and deformation were analyzed under given condition using ANSYS code, and the maximum stress was verified to be within yield stress without any structural deformation. From the results of lifting tests, it was verified that the container was safe

  2. 451 Case studies Cardiac

    African Journals Online (AJOL)

    Marinda

    Case Studies. 29 ... A case of a 26-year-old ASA I physical status male undergoing septoplasty had an abrupt ... myocardial infarction, severe hypertensive crisis, cerebral .... or no formal management is required in an ASA I patient.8 One.

  3. Options for Enhancing Education, Training and Knowledge Management for Decommissioning

    International Nuclear Information System (INIS)

    Roberts, John

    2017-01-01

    UK Nuclear Sites: Decommissioning: 26 Magnox Reactors, 2 Fast Reactors; Operational: 14 AGRs, 1 PWR; 9.6 GWe Total Capacity. Nuclear Technology Education Consortium (NTEC) Decommissioning Modules: N04 Decommissioning, Radioactive Waste and Environmental Management; N07 Nuclear Safety Case Development; N08 Particle & Colloid Engineering in the Nuclear Industry; N09 Policy, Regulation & Licensing; N10 Processing, Storage & Disposal of Nuclear Waste; N31 Management of the Decommissioning Process; N01 Reactor Physics, Criticality & Design; N02 Nuclear Fuel Cycle; N03 Radiation & Radiological Protection; N06 Reactor Materials & Lifetime Behaviour; N11 Radiation Shielding; N12 Reactor Thermal Hydraulics; N13 Criticality Safety Management; N23 Environmental Impact Assessment; N32 Experimental Reactor Physics

  4. Decommissioning of the ICI TRIGA Mark I reactor

    International Nuclear Information System (INIS)

    Parry, D.R.; England, M.R.; Ward, A.; Green, D.

    2000-01-01

    This paper considers the fuel removal, transportation and subsequent decommissioning of the ICI TRIGA Mark I Reactor at Billingham, UK. BNFL Waste Management and Decommissioning carried out this work on behalf of ICI. The decommissioning methodology was considered in the four stages to be described, namely Preparatory Works, Reactor Defueling, Intermediate Level Waste Removal and Low Level Waste Removal. This paper describes the principal methodologies involved in the defueling of the reactor and subsequent decommissioning operations, highlighting in particular the design and safety case methodologies used in order to achieve a solution which was completed without incident or accident and resulted in a cumulative radiation dose to personnel of only 1.57 mSv. (author)

  5. Plan for reevaluation of NRC policy on decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    1978-03-01

    Recognizing that the current generation of large commercial reactors and supporting nuclear facilities would substantially increase future decommissioning needs, the NRC staff began an in-depth review and re-evaluation of NRC's regulatory approach to decommissioning in 1975. Major technical studies on decommissioning have been initiated at Battelle Pacific Northwest Laboratory in order to provide a firm information base on the engineering methodology, radiation risks, and estimated costs of decommissioning light water reactors and associated fuel cycle facilities. The Nuclear Regulatory Commission is now considering development of a more explicit overall policy for nuclear facility decommissioning and amending its regulations in 10 CFR Parts 30, 40, 50, and 70 to include more specific guidance on decommissioning criteria for production and utilization facility licensees and byproduct, source, and special nuclear material licensees. The report sets forth in detail the NRC staff plan for the development of an overall NRC policy on decommissioning of nuclear facilities

  6. Operational experience of decommissioning techniques for research reactors in the United Kingdom

    International Nuclear Information System (INIS)

    England, M.R.; McCool, T.M.

    2002-01-01

    In previous co-ordinated research projects (CRP) conducted by the IAEA no distinction was made between decommissioning activities carried out at nuclear power plants, research reactors or nuclear fuel cycle facilities. As experience was gained and technology advanced it became clear that decommissioning of research reactors had certain specific characteristics which needed a dedicated approach. It was within this context that a CRP on Decommissioning Techniques for Research Reactors was launched and conducted by the IAEA from 1997 to 2001. This paper considers the experience gained from the decommissioning of two research reactors during the course of the CRP namely: (a) the ICI Triga Mk I reactor at Billingham UK which was largely complete by the end of the research project and (b) the Argonaut 100 reactor at the Scottish Universities Research and Reactor centre at East Kilbride in Scotland which is currently is the early stages of dismantling/site operations. It is the intention of this paper with reference to the two case studies outlined above to compare the actual implementation of these works against the original proposals and identify areas that were found to be problematical and/or identify any lessons learnt. (author)

  7. BNFL decommissioning strategy and techniques

    International Nuclear Information System (INIS)

    Taylor, D.

    2002-01-01

    This paper provides an overview of the range of reactor decommissioning projects being managed by BNFL, both on its own sites and for other client organizations in the UK and abroad. It also describes the decommissioning strategies and techniques that have been developed by BNFL and adopted in order to carry out this work

  8. Regulations and financing for decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Kumakura, Osamu

    1981-01-01

    The purpose of this report is to survey the French legislation concerning the decommissioning of nuclear facilities and the method of financing for it. There is no clause in French regulations, which states any specific criterion or licensing procedure for the proper decommissioning. The legal problems in this domain are treated within the general regulation system on atomic energy. The decommissioning of nuclear facilities is carried out in accordance with the licensing procedure for constructing nuclear facilities or the permission procedure for operating them, according to the ''Decree on nuclear installations, 1963''. The works for the final shut-down and decommissioning are regarded as the modification to the safety report or the general operation instructions, and new permit is required. In the case that the radioactivity of substances after decommissioning is above the criteria of the Decree, 1963, the new license is required. In the case of below the criteria, the facilities are governed by the ''Act on installations classified for environmental protection, 1976''. The ''Decree on general radiation protection, 1966'', the ''Decree on radiation protection of workers in nuclear installations, 1975'', the ''Ministerial order on transport of dangerous materials, 1945'', and two ministerial orders on radioactive effluent discharge, 1974, are applied to the decommissioning works. (Kako, I.)

  9. An Applied Study of Implementation of the Advanced Decommissioning Costing Methodology for Intermediate Storage Facility for Spent Fuel in Studsvik, Sweden with special emphasis to the application of the Omega code

    Energy Technology Data Exchange (ETDEWEB)

    Kristofova, Kristina; Vasko, Marek; Daniska, Vladimir; Ondra, Frantisek; Bezak, Peter [DECOM Slovakia, spol. s.r.o., J. Bottu 2, SK-917 01 Trnava (Slovakia); Lindskog, Staffan [Swedish Nuclear Power Inspectorate, Stockholm (Sweden)

    2007-01-15

    The presented study is focused on an analysis of decommissioning costs for the Intermediate Storage Facility for Spent Fuel (FA) facility in Studsvik prepared by SVAFO and a proposal of the advanced decommissioning costing methodology application. Therefore, this applied study concentrates particularly in the following areas: 1. Analysis of FA facility cost estimates prepared by SVAFO including description of FA facility in Studsvik, summarised input data, applied cost estimates methodology and summarised results from SVAFO study. 2. Discussion of results of the SVAFO analysis, proposals for enhanced cost estimating methodology and upgraded structure of inputs/outputs for decommissioning study for FA facility. 3. Review of costing methodologies with the special emphasis on the advanced costing methodology and cost calculation code OMEGA. 4. Discussion on implementation of the advanced costing methodology for FA facility in Studsvik together with: - identification of areas of implementation; - analyses of local decommissioning infrastructure; - adaptation of the data for the calculation database; - inventory database; and - implementation of the style of work with the computer code OMEGA.

  10. An Applied Study of Implementation of the Advanced Decommissioning Costing Methodology for Intermediate Storage Facility for Spent Fuel in Studsvik, Sweden with special emphasis to the application of the Omega code

    International Nuclear Information System (INIS)

    Kristofova, Kristina; Vasko, Marek; Daniska, Vladimir; Ondra, Frantisek; Bezak, Peter; Lindskog, Staffan

    2007-01-01

    The presented study is focused on an analysis of decommissioning costs for the Intermediate Storage Facility for Spent Fuel (FA) facility in Studsvik prepared by SVAFO and a proposal of the advanced decommissioning costing methodology application. Therefore, this applied study concentrates particularly in the following areas: 1. Analysis of FA facility cost estimates prepared by SVAFO including description of FA facility in Studsvik, summarised input data, applied cost estimates methodology and summarised results from SVAFO study. 2. Discussion of results of the SVAFO analysis, proposals for enhanced cost estimating methodology and upgraded structure of inputs/outputs for decommissioning study for FA facility. 3. Review of costing methodologies with the special emphasis on the advanced costing methodology and cost calculation code OMEGA. 4. Discussion on implementation of the advanced costing methodology for FA facility in Studsvik together with: - identification of areas of implementation; - analyses of local decommissioning infrastructure; - adaptation of the data for the calculation database; - inventory database; and - implementation of the style of work with the computer code OMEGA

  11. Decommissioning policy in Sweden

    International Nuclear Information System (INIS)

    Bergman, C.; Boge, R.; Snihs, J.O.

    1987-01-01

    In Sweden the nuclear power program is, according to a parliamentary decision, limited to twelve power producing reactors. The last reactor shall be taken out of service no later than the year 2010. As a result of the Chernobyl accident the program for taking the reactors out of service will be accelerated. This report is the first approach by the Swedish authorities to formulate a decommissioning policy. It is not the final policy document but it discusses the principal questions from the special Swedish viewpoint. (orig.)

  12. Decommissioning policy in Sweden

    International Nuclear Information System (INIS)

    Bergman, C.; Boge, R.; Snihs, J.O.

    1987-01-01

    In Sweden the nuclear power program is, according to a parliamentary decision, limited to twelve power producing reactors. The last reactor shall be taken out of service no later than the year 2010. As a result of the Chernobyl accident the program for taking the reactors out of service will be accelerated. The first approach by the Swedish authorities to formulate a decommissioning policy is discussed. It is not the final policy document but it discusses the principal questions from the special Swedish viewpoint

  13. Environmental assessment after decommissioning at the North Sea- Froey oil production site: a field study with biomarkers in fish and invertebrates

    Energy Technology Data Exchange (ETDEWEB)

    Pinturier, Laurence; Beyer, Jonny; Moltu, Ulf; Plisson, Saune Stephan; Berland, Harald; Sundt, Rolf; Bjoernstad, Anne; Sanni, Steinar

    2006-03-15

    sediment environmental survey carried in 2003 indicating that sediment fauna disturbance were limited to the immediate vicinity of the field centre (less than 250 m). It was the first time that biological effects parameters were used to assess the environmental condition of an oil field after decommissioning. This survey demonstrates the feasibility of such study and its potential for assessing the condition of benthic community living in the water and at the surface sediment. (Author)

  14. Procedures and Practices - Challenges for Decommissioning Management and Teamwork

    Energy Technology Data Exchange (ETDEWEB)

    Rindahl, G., E-mail: grete.rindahl@hrp.no [Institute for Energy Technology, Halden (Norway)

    2013-08-15

    The mental and practical approach to a decommissioning project is often not the same at all levels of an organization. Studies indicate that the early establishment of a decommissioning mindset throughout an organization is an important and frequently overlooked process. It is not enough to establish procedures, if practices and mental approaches are overlooked; and for decommissioning projects that are more often than not dominated by one of a kind problem solving, procedure design is challenging, and new requirements are put on communication. Our research considers stakeholder involvement in these processes in the wider sense of the term; however the main stakeholders in focus are regulators and the work force that will perform or lead the tasks related to decommissioning. Issues here treated include: Decommissioning mindset and the manifestation of mindset issues in decommissioning projects, including challenges and prospective solutions; trust building and trust breaking factors in communication and collaboration relevant to transition and decommissioning; new technologies for collaboration and communication and how these may impair or empower participants - experiences from several domains. This paper is based on work done in collaboration with the OECD NEA Halden Reactor Project. (author)

  15. Optimal policies for aggregate recycling from decommissioned forest roads.

    Science.gov (United States)

    Thompson, Matthew; Sessions, John

    2008-08-01

    To mitigate the adverse environmental impact of forest roads, especially degradation of endangered salmonid habitat, many public and private land managers in the western United States are actively decommissioning roads where practical and affordable. Road decommissioning is associated with reduced long-term environmental impact. When decommissioning a road, it may be possible to recover some aggregate (crushed rock) from the road surface. Aggregate is used on many low volume forest roads to reduce wheel stresses transferred to the subgrade, reduce erosion, reduce maintenance costs, and improve driver comfort. Previous studies have demonstrated the potential for aggregate to be recovered and used elsewhere on the road network, at a reduced cost compared to purchasing aggregate from a quarry. This article investigates the potential for aggregate recycling to provide an economic incentive to decommission additional roads by reducing transport distance and aggregate procurement costs for other actively used roads. Decommissioning additional roads may, in turn, result in improved aquatic habitat. We present real-world examples of aggregate recycling and discuss the advantages of doing so. Further, we present mixed integer formulations to determine optimal levels of aggregate recycling under economic and environmental objectives. Tested on an example road network, incorporation of aggregate recycling demonstrates substantial cost-savings relative to a baseline scenario without recycling, increasing the likelihood of road decommissioning and reduced habitat degradation. We find that aggregate recycling can result in up to 24% in cost savings (economic objective) and up to 890% in additional length of roads decommissioned (environmental objective).

  16. Decommissioning Funding: Ethics, Implementation, Uncertainties

    International Nuclear Information System (INIS)

    2007-01-01

    This status report on decommissioning funding: ethics, implementation, uncertainties is based on a review of recent literature and materials presented at NEA meetings in 2003 and 2004, and particularly at a topical session organised in November 2004 on funding issues associated with the decommissioning of nuclear power facilities. The report also draws on the experience of the NEA Working Party on Decommissioning and Dismantling (WPDD). This report offers, in a concise form, an overview of relevant considerations on decommissioning funding mechanisms with regard to ethics, implementation and uncertainties. Underlying ethical principles found in international agreements are identified, and factors influencing the accumulation and management of funds for decommissioning nuclear facilities are discussed together with the main sources of uncertainties of funding systems

  17. Remote Decommissioning Experiences at Sellafield

    International Nuclear Information System (INIS)

    Brownridge, M.

    2006-01-01

    British Nuclear Group has demonstrated through delivery of significant decommissioning projects the ability to effectively deploy innovative remote decommissioning technologies and deliver cost effective solutions. This has been achieved through deployment and development of off-the-shelf technologies and design of bespoke equipment. For example, the worlds first fully remotely operated Brokk was successfully deployed to enable fully remote dismantling, packaging and export of waste during the decommissioning of a pilot reprocessing facility. British Nuclear Group has also successfully implemented remote decommissioning systems to enable the decommissioning of significant challenges, including dismantling of a Caesium Extraction Facility, Windscale Pile Chimney and retrieval of Plutonium Contaminated Material (PCM) from storage cells. The challenge for the future is to continue to innovate through utilization of the supply chain and deploy off-the-shelf technologies which have been demonstrated in other industry sectors, thus reducing implementation schedules, cost and maintenance. (authors)

  18. Organization and management for decommissioning of large nuclear facilities

    International Nuclear Information System (INIS)

    2000-01-01

    organizational aspects of decommissioning and describes factors relevant to the planning and management of a decommissioning project. It identifies the general issues to be addressed and provides an overview of organizational activities necessary to manage a decommissioning project in a safe, timely and cost effective manner. There are a number of facilities that present special cases and include those which have undergone a major accident as well as uranium mines and mills and radioactive waste repositories. These facilities are not dealt with in this report. This report is structured as follows. Section 1 contains background information, objectives and scope of the document. In Section 2 considerations important for decommissioning management are discussed which could affect the organization. Section 3 deals with the management for active phases of decommissioning and provides a discussion on the organization of the decommissioning management team. Section 4 gives an overview of the decommissioning planning and approval process. Section 5 provides information on quality assurance issues relevant to decommissioning. Management of decommissioning wastes is briefly discussed in Section 6. Responsibilities and qualifications of the decommissioning management team are dealt with in Section 7. Conclusions and recommendations are given in Section 8. The report is supplemented with references, Appendix I giving details on recent experience on data management, a glossary, and national annexes, some of which indicate how the principles set out in the main report are to be utilized in different countries, and some of which are real examples of arrangements used in decommissioning projects. A list of drafting and reviewing bodies is also included

  19. Nuclear reactor decommissioning: an analysis of the regulatory environments

    International Nuclear Information System (INIS)

    Cantor, R.

    1984-04-01

    The purpose of this study is to highlight some of the current and likely regulations that will significantly affect the costs, technical alternatives and financing schemes for reactor decommissioning encountered by electric utilities and their customers. The paper includes a general review of the decommissioning literature, as well as information on specific regulations at the federal, state, and utility levels. Available estimated costs for the decommissioning of individual reactors are also presented. Finally, classification of the specific policies into common trends and practices among the various regulatory bodies is used to examine more general regulatory environments and their potential financial implications

  20. A study on safety concept and criteria of site release of nuclear installation proposed by international organizations and adopted in decommissioning practices

    International Nuclear Information System (INIS)

    Enokido, Yuji; Miyasaka, Yasuhiko; Ishikawa, Hironori

    2008-01-01

    Regulatory systems and safety criteria of site release of nuclear installation proposed by international organizations such as IAEA and applied in decommissioning in domestic and foreign countries have been studied, in order to avail them to deliberate the relevant domestic regulation and guides. In addition, the applicability of the proposal and practices to domestic legislation have been discussed. Regarding the national safety criteria, the annual individual dose constraint is optimized between 10 μSv and 300 μSv after recommendation and/or guides of IAEA etc. Unconditional release should be achieved, but the conditional and/or partial site release are possible under the same safety criteria to make the selection flexible for licensees. (author)

  1. Shippingport Station Decommissioning Project Start of Physical Decommissioning

    International Nuclear Information System (INIS)

    Crimi, F. P.

    1987-01-01

    The Shippingport Atomic Power Station consists of the nuclear steam supply system and associated radioactive waste processing systems, which are owned by the United States Department of Energy, and the turbine-generator and balance of plant, which is owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania on seven acres of land leased by DOE from Duquesne Light Company. The Shippingport Station Decommissioning Project is being performed under contract to the DOE by the General Electric Company and its integrated subcontractor, Morrison-Knudsen Company. as the Decommissioning Operations Contractor. This paper describes the current status of the physical decommissioning work, which started September 1985. The preparations required to start a major decommissioning work effort in a safe and cost effective manner are discussed including the development and implementation of a cost/schedule control system. The detailed plan required to ensure that people, property, and procedures are ready in sufficient time to support the start of physical decommissioning is also discussed. The total estimated cost of the Shippingport Station Decommissioning Project should be $98.3 M, with the Project scheduled for completion in April 1990. As the decommissioning of the first commercial-scale nuclear power plant, the Shippingport Project is expected to set the standard for safe, cost-effective demolition of nuclear plants

  2. Funding Decommissioning - UK Experience

    International Nuclear Information System (INIS)

    MacKerron, Gordon

    2006-01-01

    'Funding' started with CEGB and SSEB (state-owned electric utilities) in 1976 using the internal un-segregated fund route (i.e unfunded). This continued until privatisation of electricity industry (excluding nuclear) in 1990. Assets bought with the internal un-segregated fund were mostly transferred into non-nuclear private utilities. New state-owned Nuclear Electric (England and Wales) was given a 'Fossil Fuel Levy', a consumer charge of 10% on retail bills, amounting to c. BP 1 bn. annually. This allowed Nuclear Electric to trade legally (A reserve of BP 2.5 bn. was available from Government if company ran out of money). By 1996 the newer nuclear stations (AGRS plus PWR) were privatised as British Energy. British Energy started an external segregated fund, the Nuclear Decommissioning Fund, with a starting endowment of c. BP 225 m. - and BE made annual contributions of British Pound 16 m. into the Fund. Assumptions were that BE had 70 to accumulate cash and could get a 3.5% average annual real return. Older stations (Magnox) were left in private sector and went to BNFL in 1997. Magnox inherited the surplus cash in BE - mostly unspent Fossil Fuel Levy receipts - of c. BP 2.6 bn. Government gave an 'Undertaking' to pay BP 3.8 bn. (escalating at 4.5% real annually) for Magnox liabilities, should Magnox Electric run out of cash. BNFL inherited the BP 2.6 bn. and by 2000 had a 'Nuclear Liabilities Investment Portfolio' of c. BP 4 bn. This was a quasi-segregated internal fund for liabilities in general. [Note: overall UK nuclear liabilities in civilian sector were running at c. BP 48 bn. by now]. BE started profitable and paid BP 100 m. annually in dividends to private investors for several years. BE ran into severe financial problems after 2001 and Government organised restructuring aid, now approved by European Commission. Terms include: - BE now to contribute BP 20 m. a year into an expanded Nuclear Liabilities Fund; - A bond issue of BP 275 m. to go to Fund; - 65

  3. Development of decontamination, decommissioning and environmental restoration technology

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Byung Jik; Kwon, H S; Kim, G N. and others

    1999-03-01

    Through the project of 'Development of decontamination, decommissioning and environmental restoration technology', the followings were studied. 1. Development of decontamination and repair technology for nuclear fuel cycle facilities 2. Development of dismantling technology 3. Development of environmental restoration technology. (author)

  4. DECOST: computer routine for decommissioning cost and funding analysis

    International Nuclear Information System (INIS)

    Mingst, B.C.

    1979-12-01

    One of the major controversies surrounding the decommissioning of nuclear facilities is the lack of financial information on just what the eventual costs will be. The Nuclear Regulatory Commission has studies underway to analyze the costs of decommissioning of nuclear fuel cycle facilities and some other similar studies have also been done by other groups. These studies all deal only with the final cost outlays needed to finance decommissioning in an unchangeable set of circumstances. Funding methods and planning to reduce the costs and financial risks are usually not attempted. The DECOST program package is intended to fill this void and allow wide-ranging study of the various options available when planning for the decommissioning of nuclear facilities

  5. [Case and studies].

    Science.gov (United States)

    Schubert, András

    2015-11-15

    Case studies and case reports form an important and ever growing part of scientific and scholarly literature. The paper deals with the share and citation rate of these publication types on different fields of research. In general, evidence seems to support the opinion that an excessive number of such publications may negatively influence the impact factor of the journal. In the literature of scientometrics, case studies (at least the presence of the term "case study" in the titles of the papers) have a moderate share, but their citation rate is practically equal to that of other publication types.

  6. The Financing of Decommissioning - A View on Legal Aspects in Germany

    International Nuclear Information System (INIS)

    Paul, M.

    2006-01-01

    Nuclear power plants and other nuclear facilities such as nuclear research facilities will be gradually decommissioned. In all cases of decommissioning, no matter what type of nuclear facility is concerned, it must be ensured that adequate financial means for carrying out the decommissioning process will be available when they are needed. This paper analyses whether the necessary measures have been taken in Germany, by describing the legislative framework of decommissioning and the German system for financing the decommissioning process. The author comes to the conclusion that so far, the German system for financing the decommissioning of nuclear facilities has been successful and that currently there is no reason to doubt the amount or the security of the operators' provisions. Eventually there will be a need for modifications to the German system in order to secure the availability of financial provisions in future. (authors)

  7. Decommissioning Operations at the Cadarache Nuclear Research Center

    International Nuclear Information System (INIS)

    Gouhier, E.

    2008-01-01

    Among the different activities of the CEA research center of Cadarache, located in the south of France, one of the most important involves decommissioning. As old facilities close, decommissioning activity increases. This presentation will give an overview of the existing organization and the different ongoing decommissioning and cleanup operations on the site. We shall also present some of the new facilities under construction the purpose of which is to replace the decommissioned ones. Cadarache research center was created on October 14, 1959. Today, the activities of the research center are shared out among several technological R and D platforms, essentially devoted to nuclear energy (fission and fusion) Acting as a support to these R and D activities, the center of Cadarache has a platform of services which groups the auxiliary services required by the nuclear facilities and those necessary to the management of nuclear materials, waste, nuclear facility releases and decommissioning. Many old facilities have shut down in recent years (replaced by new facilities) and a whole decommissioning program is now underway involving the dismantling of nuclear reactors (Rapsodie, Harmonie), processing facilities (ATUE uranium treatment facility, LECA UO 2 facility) as well as waste treatment and storage facilities (INB37, INB 56. In conclusion: other dismantling and cleanup operations that are now underway in Cadarache include the following: - Waste treatment and storage facilities, - Historical VLLW and HLW storage facility, - Fissile material storage building, - Historical spent fuel storage facility. Thanks to the project organization: - Costs and risks on these projects can be reduced. - Engineers and technicians can easily move from one project to another. In some cases, when a new facility is under construction for the purpose of replacing a decommissioned one, some of the project team can integrate the new facility as members of the operation team. Today

  8. Implementation of the II. Stage decommissioning of A1 NPP

    International Nuclear Information System (INIS)

    Ficher, T.

    2015-01-01

    Presentation is focused on the implementation of the II. stage decommissioning of A1 NPP. Introductory part focuses on brief characteristics of the power plant with a history of operation, basic technical parameters and actions that were made after operation. The next section describes the basic schedule for decommissioning, structure of management and implementation of the II. stage decommissioning of the A1 NPP and objectives of the individual stages. The last and largest part of the presentation is devoted to detailed description of the II. stage decommissioning of the A1 NPP, its individual tasks and verbal and visual description of the activities that were performed. Presented is decommissioning of the technology and construction of external objects NPP A1 including storage tanks for liquid RAW, next are presented activities carried out in the Main Production Unit - decommissioning of non-operating technologies in various places/rooms, management of waste arising from these activities, treatment of case of A1 long-term spent fuel storage and long-term spent fuel storage. The subsequent section is devoted to the management and handling of contaminated soil, concrete and construction waste, including management of VLLW. (authors)

  9. Evaluation of Nuclear Facility Decommissioning Projects program

    International Nuclear Information System (INIS)

    Baumann, B.L.

    1983-01-01

    The objective of the Evaluation of Nuclear Facility Decommissioning Projects (ENFDP) program is to provide the NRC licensing staff with data which will allow an assessment of radiation exposure during decommissioning and the implementation of ALARA techniques. The data will also provide information to determine the funding level necessary to ensure timely and safe decommissioning operations. Actual decommissioning costs, methods and radiation exposures are compared with those estimated by the Battelle-PNL and ORNL NUREGs on decommissioning. Exposure reduction techniques applied to decommissioning activities to meet ALARA objectives are described. The lessons learned concerning various decommissioning methods are evaluated

  10. The decommissioning information management system

    International Nuclear Information System (INIS)

    Park, Seung-Kook; Moon, Jei-Kwon

    2015-01-01

    At the Korea Atomic Energy Research Institute (KAERI), the Korea Research Reactor (KRR-2) and one uranium conversion plant (UCP) were decommissioned. A project was launched in 1997, for the decommissioning of KRR-2 reactor with the goal of completion by 2008. Another project for the decommissioning of the UCP was launched in 2001. The physical dismantling works were started in August 2003 and the entire project was completed by the end of 2010. KAERI has developed a computer information system, named DECOMMIS, for an information management with an increased effectiveness for decommissioning projects and for record keeping for the future decommissioning projects. This decommissioning information system consists of three sub-systems; code management system, data input system (DDIS) and data processing and output system (DDPS). Through the DDIS, the data can be directly inputted at sites to minimize the time gap between the dismantling activities and the evaluation of the data by the project staff. The DDPS provides useful information to the staff for more effective project management and this information includes several fields, such as project progress management, man power management, waste management, and radiation dose control of workers and so on. The DECOMMIS was applied to the decommissioning projects of the KRR-2 and the UCP, and was utilized to give information to the staff for making decisions regarding the progress of projects. It is also to prepare the reference data for the R and D program which is for the development of the decommissioning engineering system tools and to maintain the decommissioning data for the next projects. In this paper, the overall system will be explained and the several examples of its utilization, focused on waste management and manpower control, will be introduced. (author)

  11. Nuclear installations: decommissioning and dismantling

    International Nuclear Information System (INIS)

    Anon.

    1995-01-01

    This document is a compilation of seven talks given during the 1995 EUROFORUM conference about decommissioning and dismantling of Nuclear installations in the European Community. The first two papers give a detailed description of the legal, financial and regulatory framework of decommissioning and dismantling of nuclear facilities in the European Union and a review of the currently available decommissioning techniques for inventory, disassembly, decontamination, remote operations and management of wastes. Other papers describe some legal and technical aspects of reactor and plants dismantling in UK, Germany, Spain and France. (J.S.)

  12. Approaches to estimating decommissioning costs

    International Nuclear Information System (INIS)

    Smith, R.I.

    1990-07-01

    The chronological development of methodology for estimating the cost of nuclear reactor power station decommissioning is traced from the mid-1970s through 1990. Three techniques for developing decommissioning cost estimates are described. The two viable techniques are compared by examining estimates developed for the same nuclear power station using both methods. The comparison shows that the differences between the estimates are due largely to differing assumptions regarding the size of the utility and operating contractor overhead staffs. It is concluded that the two methods provide bounding estimates on a range of manageable costs, and provide reasonable bases for the utility rate adjustments necessary to pay for future decommissioning costs. 6 refs

  13. Calculating Program for Decommissioning Work Productivity based on Decommissioning Activity Experience Data

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Seung-Kook; Park, Hee-Seong; Moon, Jei-kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-10-15

    KAERI is performing research to calculate a coefficient for decommissioning work unit productivity to calculate the estimated time decommissioning work and estimated cost based on decommissioning activity experience data for KRR-2. KAERI used to calculate the decommissioning cost and manage decommissioning activity experience data through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). In particular, KAERI used to based data for calculating the decommissioning cost with the form of a code work breakdown structure (WBS) based on decommissioning activity experience data for KRR-2.. Defined WBS code used to each system for calculate decommissioning cost. In this paper, we developed a program that can calculate the decommissioning cost using the decommissioning experience of KRR-2, UCP, and other countries through the mapping of a similar target facility between NPP and KRR-2. This paper is organized as follows. Chapter 2 discusses the decommissioning work productivity calculation method, and the mapping method of the decommissioning target facility will be described in the calculating program for decommissioning work productivity. At KAERI, research on various decommissioning methodologies of domestic NPPs will be conducted in the near future. In particular, It is difficult to determine the cost of decommissioning because such as NPP facility have the number of variables, such as the material of the target facility decommissioning, size, radiographic conditions exist.

  14. Calculating Program for Decommissioning Work Productivity based on Decommissioning Activity Experience Data

    International Nuclear Information System (INIS)

    Song, Chan-Ho; Park, Seung-Kook; Park, Hee-Seong; Moon, Jei-kwon

    2014-01-01

    KAERI is performing research to calculate a coefficient for decommissioning work unit productivity to calculate the estimated time decommissioning work and estimated cost based on decommissioning activity experience data for KRR-2. KAERI used to calculate the decommissioning cost and manage decommissioning activity experience data through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). In particular, KAERI used to based data for calculating the decommissioning cost with the form of a code work breakdown structure (WBS) based on decommissioning activity experience data for KRR-2.. Defined WBS code used to each system for calculate decommissioning cost. In this paper, we developed a program that can calculate the decommissioning cost using the decommissioning experience of KRR-2, UCP, and other countries through the mapping of a similar target facility between NPP and KRR-2. This paper is organized as follows. Chapter 2 discusses the decommissioning work productivity calculation method, and the mapping method of the decommissioning target facility will be described in the calculating program for decommissioning work productivity. At KAERI, research on various decommissioning methodologies of domestic NPPs will be conducted in the near future. In particular, It is difficult to determine the cost of decommissioning because such as NPP facility have the number of variables, such as the material of the target facility decommissioning, size, radiographic conditions exist

  15. Decommissioning of multiple-reactor stations: facilitation by sequential decommissioning

    International Nuclear Information System (INIS)

    Moore, E.B.; Smith, R.I.; Wittenbrock, N.G.

    1982-01-01

    Reductions in cost and radiation dose can be achieved for decommissionings at multiple reactor stations because of factors not necessarily present at a single reactor station: reactors of similar design, the opportunity for sequential decommissioning, a site dedicated to nuclear power generation, and the option of either interim or permanent low-level radioactive waste storage facilities onsite. The cost and radiation dose reductions occur because comprehensive decommissioning planning need only be done once, because the labor force is stable and need only be trained once, because there is less handling of radioactive wastes, and because central stores, equipment, and facilities may be used. The cost and radiation dose reductions are sensitive to the number and types of reactors on the site, and to the alternatives selected for decommissioning. 3 tables

  16. Decommissioning a phosphoric acid production plant: a radiological protection case study

    Energy Technology Data Exchange (ETDEWEB)

    Stamatis, V.; Seferlis, S. [Greek Atomic Energy Commission (GAEC), P.O. Box 60092, 15310 Ag. Paraskevi (Greece); Kamenopoulou, V., E-mail: vkamenop@eeae.g [Greek Atomic Energy Commission (GAEC), P.O. Box 60092, 15310 Ag. Paraskevi (Greece); Potiriadis, C.; Koukouliou, V.; Kehagia, K. [Greek Atomic Energy Commission (GAEC), P.O. Box 60092, 15310 Ag. Paraskevi (Greece); Dagli, C. [Protypos Company, Geraniou 30, 105 52 Athens (Greece); Georgiadis, S. [Environmental Protection Engineering S.A., Dervenakion 24, 185 45 Piraeus (Greece); Camarinopoulos, L. [Greek Atomic Energy Commission (GAEC), P.O. Box 60092, 15310 Ag. Paraskevi (Greece)

    2010-12-15

    During a preliminary survey at the area of an abandoned fertilizer plant, increased levels of radioactivity were measured at places, buildings, constructions and materials. The extent of the contamination was determined and the affected areas were characterized as controlled areas. After the quantitative and qualitative determination of the contaminated materials, the decontamination was planned and performed step by step: the contaminated materials were categorized according to their physical characteristics (scrap metals, plastic pipes, scales and residues, building materials, etc) and according to their level of radioactivity. Depending on the material type, different decontamination and disposal options were proposed; the most appropriate technique was chosen taking into account apart from technical issues, the legal framework, radiation protection issues, the opinion of the local authorities involved as well as the owner's wish. After taking away the biggest amount of the contaminated materials, an iterative process consisting of surveys and decontamination actions was performed in order to remove the residual traces of contamination from the area. During the final survey, no residual surface contamination was detected; some sparsely distributed low level contaminated materials deeply immersed into the soil were found and removed.

  17. Decommissioning a phosphoric acid production plant: a radiological protection case study

    International Nuclear Information System (INIS)

    Stamatis, V.; Seferlis, S.; Kamenopoulou, V.; Potiriadis, C.; Koukouliou, V.; Kehagia, K.; Dagli, C.; Georgiadis, S.; Camarinopoulos, L.

    2010-01-01

    During a preliminary survey at the area of an abandoned fertilizer plant, increased levels of radioactivity were measured at places, buildings, constructions and materials. The extent of the contamination was determined and the affected areas were characterized as controlled areas. After the quantitative and qualitative determination of the contaminated materials, the decontamination was planned and performed step by step: the contaminated materials were categorized according to their physical characteristics (scrap metals, plastic pipes, scales and residues, building materials, etc) and according to their level of radioactivity. Depending on the material type, different decontamination and disposal options were proposed; the most appropriate technique was chosen taking into account apart from technical issues, the legal framework, radiation protection issues, the opinion of the local authorities involved as well as the owner's wish. After taking away the biggest amount of the contaminated materials, an iterative process consisting of surveys and decontamination actions was performed in order to remove the residual traces of contamination from the area. During the final survey, no residual surface contamination was detected; some sparsely distributed low level contaminated materials deeply immersed into the soil were found and removed.

  18. Decommissioning Cost Assessment

    International Nuclear Information System (INIS)

    Labor, Bea

    2012-03-01

    The future costs for dismantling, decommissioning and handling of associated radioactive waste of nuclear installations represents substantial liabilities. It is the generations that benefits from the use of nuclear installations that shall carry the financial burden. Nuclear waste programmes have occasionally encountered set-backs related to the trust from society. This has resulted in delayed, redirected or halted activities, which has the common denominator of costs increases. In modern democratic countries, information sharing, knowledge transfer and open communication about costs for the management of radioactive waste are prerequisites for the task to develop modern methods for public participation and thus to develop well-founded and justified confidence for further development of nuclear energy. Nuclear and radiation safety Authorities have a clear role to provide unbiased information on any health, safety, financial and environmental related issues. This task requires a good understanding of the values and opinion of the public, and especially those of the younger generation

  19. Decommissioning. Success with preparation

    International Nuclear Information System (INIS)

    Klasen, Joerg; Schulz, Rolf; Wilhelm, Oliver

    2017-01-01

    The decommissioning of a nuclear power plant poses a significant challenge for the operating company. The business model is turned upside down and a working culture developed for power operation has to be adapted while necessary know- how for the upcoming tasks has to be built up. The trauma for the employees induced by the final plant shut-down has to be considered and respected. The change of working culture in the enterprise has to be managed and the organization has to be prepared for the future. Here the methods of Change-Management offer a systematic and effective approach. Confidence in the employee's competencies is one of the key success factors for the change into the future.

  20. Decontamination & decommissioning focus area

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-08-01

    In January 1994, the US Department of Energy Office of Environmental Management (DOE EM) formally introduced its new approach to managing DOE`s environmental research and technology development activities. The goal of the new approach is to conduct research and development in critical areas of interest to DOE, utilizing the best talent in the Department and in the national science community. To facilitate this solutions-oriented approach, the Office of Science and Technology (EM-50, formerly the Office of Technology Development) formed five Focus AReas to stimulate the required basic research, development, and demonstration efforts to seek new, innovative cleanup methods. In February 1995, EM-50 selected the DOE Morgantown Energy Technology Center (METC) to lead implementation of one of these Focus Areas: the Decontamination and Decommissioning (D & D) Focus Area.

  1. IAEA/CRP for decommissioning techniques for research reactors

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Won Zin; Won, H. J.; Kim, K. N.; Lee, K. W.; Jung, C. H

    2001-03-01

    The following were studied through the project entitled 'IAEA/CRP for decommissioning techniques for research reactors 1. Decontamination technology development for TRIGA radioactive soil waste - Electrokinetic soil decontamination experimental results and its mathematical simulation 2. The 2nd IAEA/CRP for decommissioning techniques for research reactors - Meeting results and program 3. Hosting the 2001 IAEA/RCA D and D training course for research reactors and small nuclear facilities.

  2. IAEA/CRP for decommissioning techniques for research reactors

    International Nuclear Information System (INIS)

    Oh, Won Zin; Won, H. J.; Kim, K. N.; Lee, K. W.; Jung, C. H.

    2001-03-01

    The following were studied through the project entitled 'IAEA/CRP for decommissioning techniques for research reactors 1. Decontamination technology development for TRIGA radioactive soil waste - Electrokinetic soil decontamination experimental results and its mathematical simulation 2. The 2nd IAEA/CRP for decommissioning techniques for research reactors - Meeting results and program 3. Hosting the 2001 IAEA/RCA D and D training course for research reactors and small nuclear facilities

  3. FIR 1 TRIGA activity inventories for decommissioning planning

    International Nuclear Information System (INIS)

    Raety, Antti; Kotiluoto, Petri

    2016-01-01

    The objective of the study has been to estimate the residual activity in the decommissioning waste of TRIGA Mark II type research reactor FiR 1 in Finland. Neutron flux distributions were calculated with Monte Carlo code MCNP. These were used in ORIGEN-S point-depletion code to calculate the neutron induced activity of materials at different time points by modelling the irradiation history and radioactive decay. The knowledge of radioactive inventory of irradiated materials is important in the planning of the decommissioning activities and is essential for predicting the radiological impact to personnel and environment. Decommissioning waste consists mainly of ordinary concrete, aluminium, steel and graphite parts. Results include uncertainties due to assumptions on material compositions and possible diffusion of gaseous nuclides. Comparison to activity inventory estimates of two other decommissioned research reactors is also presented. (authors)

  4. Construction times and the decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Erramuspe, H.J.

    1988-01-01

    The construction and the decommissioning periods of nuclear power plants (NPP), are studied, due to their importance in the generation costs. With reference to the construction periods of these plants, a review is made of the situation and technical improvements made in different countries, with the purpose of shortening them. In regard to the decommissioning of NPP, the present and future situations are reviewed in connection with different stages of decommissioning and their related problems, as the residual radioactivity of different components, and the size of the final wastes to be disposed of. The possibilities of plant life extensions are also revised in connection with these problems. Finally, the expected decommissioning costs are analyzed. (Author) [es

  5. Scheme of database structure on decommissioning of the research reactor

    International Nuclear Information System (INIS)

    Park, H. S.; Park, S. K.; Kim, H. R.; Lee, D. K.; Jung, K. J.

    2001-01-01

    ISP (Information Strategy Planning), which is the first step of the whole database development, has been studied to manage effectively information and data related to the decommissioning activities of the Korea Research Reactor 1 and 2 (KRR-1 and 2). Since Korea has not acquired the technology of the decommissioning database management system, some record management system (RMS) of large nuclear facilities of national experience such as in the U.S.A, Japan, Belgium, and Russian were reviewed. In order to construct the database structure of the whole decommissioning activities such as the working information, radioactive waste treatment, and radiological surveying and analysis has been extracted from the whole dismantling process. These information and data will be used as the basic data to analyzed the matrix to find the entity relationship diagram and will contribute to the establishment of a business system design and the development of a decommissioning database system as well

  6. Alternatives evaluation and decommissioning study on shielded transfer tanks at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    DeVore, J.R.; Hinton, R.R.

    1994-08-01

    The shielded transfer tanks (STTs) are five obsolete cylindrical shipping casks which were used to transport high specific activity radioactive solutions by rail during the 1960s and early 1970s. The STTs are currently stored at the Oak Ridge National Laboratory under a shed roof. This report is an evaluation to determine the preferred alternative for the final disposition of the five STTs. The decommissioning alternatives assessed include: (1) the no action alternative to leave the STTs in their present location with continued surveillance and maintenance; (2) solidification of contents within the tanks and holding the STTs in long term retrievable storage; (3) sale of one or more of the used STTs to private industry for use at their treatment facility with the remaining STTs processed as in Alternative 4; and (4) removal of tank contents for de-watering/retrievable storage, limited decontamination to meet acceptance criteria, smelting the STTs to recycle the metal through the DOE contaminated scrap metal program, and returning the shielding lead to the ORNL lead recovery program because the smelting contractor cannot reprocess the lead. To completely evaluate the alternatives for the disposition of the STTs, the contents of the tanks must be characterized. Shielding and handling requirements, risk considerations, and waste acceptance criteria all require that the radioactive inventory and free liquids residual in the STTs be known. Because characterization of the STT contents in the field was not input into a computer model to predict the probable inventory and amount of free liquid. The four alternatives considered were subjected to a numerical scoring procedure. Alternative 4, smelting the STTs to recycle the metal after removal/de-watering of the tank contents, had the highest score and is, therefore, recommended as the preferred alternative. However, if a buyer for one or more STT could be found, it is recommended that Alternative 3 be reconsidered

  7. Building confidence in decommissioning in France: Towards a safe, industrially applicable, coherent national system without site or waste liberation

    International Nuclear Information System (INIS)

    Averous, J.; Chapalain, E.

    2002-01-01

    The rate of decommissioning in France is accelerating, as the first generation of power reactors will be actively decommissioned in the next few years. Experience has been gathered from past decommissioning activities and some current pilot decommissioning operations. This experience has shown that a national system has to be put in place to deal with decommissioning, waste elimination and site cleaning up activities in order to allow a consistent, safe, transparent and industrially applicable management of these matters. A system founded on successive lines of defence has been put into enforcement, which does not involve any site nor waste liberation, as it is considered that the criteria associated are always prone to discussion and contradiction. This system is based on the following concepts : 'nuclear waste', waste prone to have been contaminated or activated, is segregated from 'conventional waste' using a system involving successive lines of defence, and hence, building a very high level of confidence that no 'nuclear waste' will be eliminated without control in conventional waste eliminators or recycling facilities ; 'nuclear waste' is eliminated in dedicated facilities or repositories, or in conventional facilities under the condition of a special authorisation based on a radiological impact study and a public inquiry ; a global safety evaluation of the nuclear site is conducted after decommissioning in order to define possible use restrictions. In all cases, minimum restrictions will be put into enforcement in urbanisation plans to ensure sufficient precaution when planning future uses of the ground or the building. This paper describes this global system in detail and shows that its inherent consistency allows it to be easily applicable by operators while achieving a high level of safety and confidence. (author)

  8. On Decommissioning Costs of the Ranstad Site

    Energy Technology Data Exchange (ETDEWEB)

    Varley, Geoff (NAC International (United Kingdom))

    2010-08-15

    The main objective of this study has been to extend the review of the future cost to decommission and dismantling the industrial area at the site of the old uranium mine at Ranstad in Sweden. The feedback of experience and actual costs from a decommissioning project in the United Kingdom (A26 in Springfields) has been used to help in the assessment of the reasonableness of the estimated costs for decommissioning of the old uranium mine in Ranstad. A quantitative (albeit subjective) statement about the accuracy of the Ranstad cost estimate has been developed. Also, the factors relevant to the allocation of costs between the Swedish state and the current owners of the old uranium mine site have been evaluated and presented. The study has developed the following main conclusions: - The importance of thorough characterization/radiological mapping to the selection of the optimum decommissioning approach (technique) has been reinforced very strongly. - Thorough characterization has the related consequence of being able to better define the costs of decommissioning, in terms of equipment needed, labour hours required and, importantly, the volumes of different categories of waste requiring different routes (and associated different unit costs) for ultimate disposition. - Uncertainties in the Ranstad decommissioning cost estimate nevertheless remain, in particular relating to the viability of the proposed approach to dismantling and decontaminating the acid proof bricks that line the pools in the Large Leaching Hall; a method that is acknowledged to be not proven. The outcome could have an impact on actual dismantling and decontamination costs, as well as on the costs of ultimate waste disposition. The KB2010 cost estimate report does not offer an alternative in the event that the base plan proves to be unfeasible. - On balance it would appear that the continued presence of RMA at the Ranstad site ultimately will provide a net cost benefit to the program. The extra costs

  9. On Decommissioning Costs of the Ranstad Site

    International Nuclear Information System (INIS)

    Varley, Geoff

    2010-08-01

    The main objective of this study has been to extend the review of the future cost to decommission and dismantling the industrial area at the site of the old uranium mine at Ranstad in Sweden. The feedback of experience and actual costs from a decommissioning project in the United Kingdom (A26 in Springfields) has been used to help in the assessment of the reasonableness of the estimated costs for decommissioning of the old uranium mine in Ranstad. A quantitative (albeit subjective) statement about the accuracy of the Ranstad cost estimate has been developed. Also, the factors relevant to the allocation of costs between the Swedish state and the current owners of the old uranium mine site have been evaluated and presented. The study has developed the following main conclusions: - The importance of thorough characterization/radiological mapping to the selection of the optimum decommissioning approach (technique) has been reinforced very strongly. - Thorough characterization has the related consequence of being able to better define the costs of decommissioning, in terms of equipment needed, labour hours required and, importantly, the volumes of different categories of waste requiring different routes (and associated different unit costs) for ultimate disposition. - Uncertainties in the Ranstad decommissioning cost estimate nevertheless remain, in particular relating to the viability of the proposed approach to dismantling and decontaminating the acid proof bricks that line the pools in the Large Leaching Hall; a method that is acknowledged to be not proven. The outcome could have an impact on actual dismantling and decontamination costs, as well as on the costs of ultimate waste disposition. The KB2010 cost estimate report does not offer an alternative in the event that the base plan proves to be unfeasible. - On balance it would appear that the continued presence of RMA at the Ranstad site ultimately will provide a net cost benefit to the program. The extra costs

  10. An analysis of decommissioning costs

    International Nuclear Information System (INIS)

    Teunckens, L.; Loeschhorn, U.; Yanagihara, S.; Wren, G.; Menon, S.

    1992-01-01

    Within the OECD/NEA Cooperative Programme on Decommissioning a Task Group was set up early in 1989 to identify the reasons for the large variations in decommissioning cost estimates. The Task Group gathered cost data from 12 of the 14 projects in the Programme to form the basis of their analysis. They included reactors being decommissioned to various stages as well as fuel cycle facilities. The projects were divided into groups of projects with similar characteristics ('models') to facilitate the analysis of the cost distribution in each group of projects and the cost data was progressively refined by a dialogue between the Task Group and the project managers. A comparative analysis was then performed and project specific discrepancies were identified. The Task Group's report is summarized on the results of the comparative analysis as well as the lessons learnt by the Task Group in the acquisition and analysis of cost data from international decommissioning projects. (author) 5 tabs

  11. Trojan Decommissioning Project Cost Performance

    International Nuclear Information System (INIS)

    Michael B. Lackey

    2000-01-01

    The Trojan nuclear plant (Trojan) was an 1160-MW(electric) four-loop pressurized water reactor located in Rainier, Oregon. The plant was permanently shut down in 1993 after ∼17 yr of commercial operation. The early plant closure was an economic decision. The key factors in the closure analysis were escalation of inspection and repair costs associated with steam generator tube cracking and the projected availability of inexpensive replacement power in the Pacific Northwest region of the United States. Since the plant closure, Portland General Electric (PGE) has been actively engaged in decommissioning. The Trojan Decommissioning Project currently has a forecast at completion of $429.7 million (all costs are in millions of 1997 dollars, unless otherwise noted). The cost performance of the Trojan Decommissioning Project to date is addressed, as well as the tools that are in place to provide cost control through completion of decommissioning

  12. Septic Systems Case Studies

    Science.gov (United States)

    A collection of septic systems case studies to help community planners, elected officials, health department staff, state officials, and interested citizens explore alternatives for managing their decentralized wastewater treatment systems.

  13. HYDROGEOLOGIC CASE STUDIES

    Science.gov (United States)

    Hydrogeology is the foundation of subsurface site characterization for evaluations of monitored natural attenuation (MNA). Three case studies are presented. Examples of the potentially detrimental effects of drilling additives on ground-water samples from monitoring wells are d...

  14. A Psychobiographical Case Study

    African Journals Online (AJOL)

    man, and cancer fighter. This psychobiographical case study entailed a psychosocial-historical ... does not draw more attention as a research method, as this approach has .... of the applied Levinsonian theory to the life of Jobs against the ...

  15. Qualitative Case Study Guidelines

    Science.gov (United States)

    2013-11-01

    Introduction to Sociological Methods. 2nd ed. New York, McGraw-Hill 14. Denzin , N. K. and Lincoln , Y. S. (2011) The SAGE Handbook of Qualitative...The Art of Science. In: Denzin , N. K. and Lincoln , Y. S. (eds.) Handbook of Qualitative Research. Thousand Oaks, Sage 19. GAO (1990) Case Study...Rinehart & Winston 39. Stake, R. E. (1994) Case Studies. In: Denzin , N. K. and Lincoln , Y. S. (eds.) Handbook of Qualitative Research. Thousand Oaks, Sage

  16. General principles of nuclear safety management related to research reactor decommissioning

    International Nuclear Information System (INIS)

    Banciu, Ortenzia; Vladescu, Gabriela

    2003-01-01

    The paper contents the general principles applicable to the decommissioning of research reactors to ensure a proper nuclear safety management, during both decommissioning activities and post decommissioning period. The main objective of decommissioning is to ensure the protection of workers, population and environment against all radiological and non-radiological hazards that could result after a reactor shutdown and dismantling. In the same time, it is necessary, by some proper provisions, to limit the effect of decommissioning for the future generation, according to the new Romanian, IAEA and EU Norms and Regulations. Assurance of nuclear safety during decommissioning process involves, in the first step, to establish of some safety principles and requirements to be taken into account during whole process. In the same time, it is necessary to perform a series of analyses to ensure that the whole process is conducted in a planned and safe manner. The general principles proposed for a proper management of safety during research reactor decommissioning are as follows: - Set-up of all operations included in a Decommissioning Plan; - Set-up and qualitative evaluation of safety problems, which could appear during normal decommissioning process, both radiological and nonradiological risks for workers and public; - Set-up of accident list related to decommissioning process the events that could appear both due to some abnormal working conditions and to some on-site and off-site events like fires, explosions, flooding, earthquake, etc.); - Development and qualitative/ quantitative evaluation of scenarios for each incidents; - Development (and evaluation) of safety indicator system. The safety indicators are the most important tools used to assess the level of nuclear safety during decommissioning process, to discover the weak points and to establish safety measures. The paper contains also, a safety case evaluation (description of facility according to the decommissioning

  17. Preliminary decommissioning plan of the reactor IPEN-MB01

    International Nuclear Information System (INIS)

    Vivas, Ary de Souza

    2014-01-01

    Around the world, many nuclear plants were built and need to be turned off at a certain time because they are close to their recommended time of use is approximately 50 years. So the IAEA (International Atomic Energy Agency), seeks to guide and recommend a set of guidelines for the conduct of activities of nuclear facilities, with special attention to countries that do not have a framework regulatory Legal that sustain the activities of decommissioning. Brazil, so far, does not have a specific standard to guide the steps of the guidelines regarding decommissioning research reactors. However, in March 2011 a study committee was formed with the main task facing the issues of decommissioning of nuclear installations in Brazil, culminating in Resolution 133 of November 8, 2012, a standard project that treat about the Decommissioning of nucleoelectric plants. O Instituto de Pesquisas Energeticas e Nucleares (IPEN) has two research reactors one being the reactor IPEN/MB-01. The purpose of this master dissertation is to develop a preliminary plan for decommissioning this research reactor, considering the technical documentation of the facility (RAS-Safety Analysis Report), the existing standards of CNEN (National Nuclear Energy Commission), as well as IAEA recommendations. In terms of procedures for decommissioning research reactors, this work was based on what is most modern in experiences, strategies and lessons learned performed and documented in IAEA publications covering techniques and technologies for decommissioning. Considering these technical knowledge and due to the peculiarities of the facility, was selected to immediate dismantling strategy, which corresponds to the start of decommissioning activities once the installation is switched off, dividing it into work sectors. As a resource for monitoring and project management of reactor decommissioning and maintenance of records, we developed a database using Microsoft Access 2007, which contain all the items and

  18. Human resource development for decommissioning

    International Nuclear Information System (INIS)

    Yanagihara, Satoshi

    2016-01-01

    This paper summarized the features of decommissioning work and the methods how to develop human resources. The general flow of decommissioning includes the following steps: (1) evaluation of facility characteristics, (2) planning, (3) decontamination and disassembly of equipment and structures contaminated with radioactivity, (4) radioactivity measurement, (5) treatment and disposal of radioactive waste, and (6) release from legal restrictions (termination of decommissioning). For this purpose, techniques in various fields are required. In the evaluation of facility characteristics, radiation measurement and calculation of activation amount in the core part are required. In decontamination and dismantling, cutting technology (mechanical cutting, thermal cutting, etc.), decontamination technology, and remote control technology are required. In the nuclear power education in the past, the fields related to design, construction, operation, and maintenance among the plant life cycle were the main parts. Much attention was not payed to decommissioning and the treatment/disposal of radioactive waste in the second half of life cycle. As university education, Hokkaido University and Fukui University have lectures on decommissioning. Furthermore, the education and research for students are proceeding at seven universities, with a focus on common reactors including those of Fukushima Daiichi Power Station. It is a key for promoting decommissioning, to incorporate project management, risk analysis, cost evaluation, and decision making into education, and to foster human resources heading toward challenging problems including social problems. (A.O.)

  19. An outsider's view of decommissioning

    International Nuclear Information System (INIS)

    Wilkie, T.

    1996-01-01

    The decommissioning of nuclear facilities is not just a technical or even a financial issue. Presenting decommissioning as a technically difficult task overcome by superhuman effort on the part of the industry will not gain much credit amongst sophisticated consumers who now require that any complex technology will work and work safely. Any engineering problems are surmountable given the money to find the solution. Some of the financial aspects of decommissioning are worrying, however, given their open-ended nature. The cost of waste disposal is one of these. Despite a lapse of fifty years since the start-up of its first reactor, the United Kingdom is unlikely to have available a repository for the disposal of intermediate level waste until about 2020. Waste disposal is a large consideration in decommissioning and the industry's forecasts of cost in this area lack credibility in the light of a poor track record in financial prediction. Financial engineering in the form of the segregated fund set up in March 1996 to cover the decommissioning of nuclear power stations in the United Kingdom is likely to provide only short term reassurance in the light of doubts about a credible future for nuclear power. This lack of confidence over the wider problems of nuclear power creates particular problems for decommissioning which go beyond technical difficulties and complicate financial considerations. (UK)

  20. Decommissioning challenges - an industrial reality

    International Nuclear Information System (INIS)

    Moore, H.; Mort, P.; Hutton, E.

    2008-01-01

    Sellafield Limited has undergone many transformations in previous years. The Nuclear Decommissioning Authority (NDA) has managed the site from April 2005, and a new Parent Body Organisation (PBO) is soon to be announced. In addition, it is an exciting time for the nuclear industry following the announcement of the UK government support new reactor builds. Should the site be selected for new build, the impact on Sellafield, its decommissioning program and economic impact on the local area can only be speculated at the current time. Every past, present and future decommissioning project at the Sellafield Limited site offers complex challenges, as each facility is unique. Specialist skills and experience must be engaged at pre-planned phases to result in a safe, efficient and successful decommissioning project. This paper provides an overview of a small selection of decommissioning projects, including examples of stakeholder engagement, plant and equipment dismantling using remote handling equipment and the application of innovative techniques and technologies. In addition, the final section provides a summary upon how future technologies required by the decommissioning projects are being assessed and developed. (authors)

  1. Brazilian nuclear power plants decommissioning plan for a multiple reactor site

    Energy Technology Data Exchange (ETDEWEB)

    Monteiro, Deiglys B.; Moreira, Joao M.L.; Maiorino, Jose R., E-mail: deiglys.monteiro@ufabc.edu.br, E-mail: joao.moreira@ufabc.edu.br, E-mail: joserubens.maiorino@ufabc.edu.br [Universidade Federal do ABC (CECS/UFABC), Santo Andre, SP (Brazil). Centro de Engenharia, Modelagem e Ciencias Aplicadas. Programa de Pos-Graduacao em Energia e Engenharia da Energia

    2015-07-01

    Actually, Brazil has two operating Nuclear Power Plants and a third one under construction, all at Central Nuclear Almirante Alvaro Alberto - CNAAA. To comply with regulatory aspects the power plants operator, Eletronuclear, must present to Brazilian Nuclear Regulatory Agency, CNEN, a decommissioning plan. Brazilian experience with decommissioning is limited because none of any nuclear reactor at the country was decommissioned. In literature, decommissioning process is well described despite few nuclear power reactors have been decommissioned around the world. Some different approach is desirable for multiple reactors sites, case of CNAAA site. During the decommissioning, a great amount of wastes will be produced and have to be properly managed. Particularly, the construction of Auxiliary Services on the site could be a good choice due to the possibility of reducing costs. The present work intends to present to the Eletronuclear some aspects of the decommissioning concept and decommissioning management, storage and disposal de wastes, based on the available literature, regulatory standards of CNEN and international experience as well as to suggest some solutions to be implemented at CNAAA site before starts the decommissioning project in order to maximize the benefits. (author)

  2. Brazilian nuclear power plants decommissioning plan for a multiple reactor site

    International Nuclear Information System (INIS)

    Monteiro, Deiglys B.; Moreira, Joao M.L.; Maiorino, Jose R.

    2015-01-01

    Actually, Brazil has two operating Nuclear Power Plants and a third one under construction, all at Central Nuclear Almirante Alvaro Alberto - CNAAA. To comply with regulatory aspects the power plants operator, Eletronuclear, must present to Brazilian Nuclear Regulatory Agency, CNEN, a decommissioning plan. Brazilian experience with decommissioning is limited because none of any nuclear reactor at the country was decommissioned. In literature, decommissioning process is well described despite few nuclear power reactors have been decommissioned around the world. Some different approach is desirable for multiple reactors sites, case of CNAAA site. During the decommissioning, a great amount of wastes will be produced and have to be properly managed. Particularly, the construction of Auxiliary Services on the site could be a good choice due to the possibility of reducing costs. The present work intends to present to the Eletronuclear some aspects of the decommissioning concept and decommissioning management, storage and disposal de wastes, based on the available literature, regulatory standards of CNEN and international experience as well as to suggest some solutions to be implemented at CNAAA site before starts the decommissioning project in order to maximize the benefits. (author)

  3. Money Related Decommissioning and Funding Decision Making

    International Nuclear Information System (INIS)

    Goodman, Lynne S.

    2008-01-01

    'Money makes the world go round', as the song says. It definitely influences decommissioning decision-making and financial assurance for future decommissioning. This paper will address two money-related decommissioning topics. The first is the evaluation of whether to continue or to halt decommissioning activities at Fermi 1. The second is maintaining adequacy of financial assurance for future decommissioning of operating plants. Decommissioning costs considerable money and costs are often higher than originally estimated. If costs increase significantly and decommissioning is not well funded, decommissioning activities may be deferred. Several decommissioning projects have been deferred when decision-makers determined future spending is preferable than current spending, or when costs have risen significantly. Decommissioning activity timing is being reevaluated for the Fermi 1 project. Assumptions for waste cost-escalation significantly impact the decision being made this year on the Fermi 1 decommissioning project. They also have a major impact on the estimated costs for decommissioning currently operating plants. Adequately funding full decommissioning during plant operation will ensure that the users who receive the benefit pay the full price of the nuclear-generated electricity. Funding throughout operation also will better ensure that money is available following shutdown to allow decommissioning to be conducted without need for additional funds

  4. Revised Analyses of Decommissioning Reference Non-Fuel-Cycle Facilities

    International Nuclear Information System (INIS)

    Bierschbach, M.C.; Haffner, D.R.; Schneider, K.J.; Short, S.M.

    2002-01-01

    Cost information is developed for the conceptual decommissioning of non-fuel-cycle nuclear facilities that represent a significant decommissioning task in terms of decontamination and disposal activities. This study is a re-evaluation of the original study (NUREG/CR-1754 and NUREG/CR-1754, Addendum 1). The reference facilities examined in this study are the same as in the original study and include: a laboratory for the manufacture of 3 H-labeled compounds; a laboratory for the manufacture of 14 C-labeled compounds; a laboratory for the manufacture of 123 I-labeled compounds; a laboratory for the manufacture of 137 Cs sealed sources; a laboratory for the manufacture of 241 Am sealed sources; and an institutional user laboratory. In addition to the laboratories, three reference sites that require some decommissioning effort were also examined. These sites are: (1) a site with a contaminated drain line and hold-up tank; (2) a site with a contaminated ground surface; and (3) a tailings pile containing uranium and thorium residues. Decommissioning of these reference facilities and sites can be accomplished using techniques and equipment that are in common industrial use. Essentially the same technology assumed in the original study is used in this study. For the reference laboratory-type facilities, the study approach is to first evaluate the decommissioning of individual components (e.g., fume hoods, glove boxes, and building surfaces) that are common to many laboratory facilities. The information obtained from analyzing the individual components of each facility are then used to determine the cost, manpower requirements and dose information for the decommissioning of the entire facility. DECON, the objective of the 1988 Rulemaking for materials facilities, is the decommissioning alternative evaluated for the reference laboratories because it results in the release of the facility for restricted or unrestricted use as soon as possible. For a facility, DECON requires

  5. Revised Analyses of Decommissioning Reference Non-Fuel-Cycle Facilities

    Energy Technology Data Exchange (ETDEWEB)

    MC Bierschbach; DR Haffner; KJ Schneider; SM Short

    2002-12-01

    Cost information is developed for the conceptual decommissioning of non-fuel-cycle nuclear facilities that represent a significant decommissioning task in terms of decontamination and disposal activities. This study is a re-evaluation of the original study (NUREG/CR-1754 and NUREG/CR-1754, Addendum 1). The reference facilities examined in this study are the same as in the original study and include: a laboratory for the manufacture of {sup 3}H-labeled compounds; a laboratory for the manufacture of {sup 14}C-labeled compounds; a laboratory for the manufacture of {sup 123}I-labeled compounds; a laboratory for the manufacture of {sup 137}Cs sealed sources; a laboratory for the manufacture of {sup 241}Am sealed sources; and an institutional user laboratory. In addition to the laboratories, three reference sites that require some decommissioning effort were also examined. These sites are: (1) a site with a contaminated drain line and hold-up tank; (2) a site with a contaminated ground surface; and (3) a tailings pile containing uranium and thorium residues. Decommissioning of these reference facilities and sites can be accomplished using techniques and equipment that are in common industrial use. Essentially the same technology assumed in the original study is used in this study. For the reference laboratory-type facilities, the study approach is to first evaluate the decommissioning of individual components (e.g., fume hoods, glove boxes, and building surfaces) that are common to many laboratory facilities. The information obtained from analyzing the individual components of each facility are then used to determine the cost, manpower requirements and dose information for the decommissioning of the entire facility. DECON, the objective of the 1988 Rulemaking for materials facilities, is the decommissioning alternative evaluated for the reference laboratories because it results in the release of the facility for restricted or unrestricted use as soon as possible. For a

  6. Decommissioning analyzis of a university cyclotron

    International Nuclear Information System (INIS)

    Eggermont, G.X.; Buls, N.; Hermanne, A.

    1996-01-01

    In the widespread use of some medical nuclear facilities, such as cyclotrons for isotope production, Life cycle analyzis, including decommissioning, was not taken into account. The structural materials of an accelerator and the concrete shielding of the bunker are activated by neutrons. This could yield a considerable volume of nuclear waste and needs radiation protection concern for occupational workers and the environment during some decennia. At the university of Brussels (WB) a prospective radiation protection and waste analyzis is being made for the later decommissioning of their cyclotron. Only few similar studies have been published. In Belgium future nuclear dismantling operations will be submitted to a radiation protection authorization procedure. Meanwhile the nuclear waste authorities insist on dismantling planning, including financial provisioning. An optimization exercise was made at the VUB-cyclotron, taking into account international trends to clearance levels for low level nuclear waste. Conceptual prevention opportunities e.g. selective material choice could be identified for future accelerator constructions. (author)

  7. Beneficial Re-use of Decommissioned Former Nuclear Facilities

    International Nuclear Information System (INIS)

    Boing, L.E.

    1997-01-01

    With the decision to decommission a nuclear facility, it is necessary to evaluate whether to fully demolish a facility or to re-use the facility in some capacity. This evaluation is often primarily driven by both the past mission of the site and the facility and the site's perceived future mission. In the case where the facility to be decommissioned is located within a large research or industrial complex and represents a significant resource to the site's future mission, it may be a perfect candidate to be re-used in some fashion. However, if the site is a rather remote older facility with little chance of being modified to today's standards for its re-use, the chances for its re-use will be substantially reduced. In this presentation, some specific cases of former nuclear facilities being decommissioned and re-used will be reviewed and some factors required to be considered in making this decision will be reviewed

  8. Current status of Chernobyl NPP decommissioning

    International Nuclear Information System (INIS)

    2009-01-01

    Strategy of Chernobyl NPP decommissioning with the decommissioning license 2002-2064 is presented. The main activities at the stage of ChNPP units shutdown (2002 - 2012) are: units maintenance in safe state; decommissioning infrastructure construction; unloading of SNF – main activity determining the stage duration; systems and elements final shutdown; decommissioning life-support systems reconstruction; Comprehensive engineering and radiation survey (CERS); dismantling of the reactor facilities external equipment; removal of RAW from units; decommissioning documentation development. The decommissioning activities main results are presented

  9. NPP Decommissioning: the concept; state of activities

    International Nuclear Information System (INIS)

    Nemytov, S.; Zimin, V.

    2001-01-01

    The main principles of NPP decommissioning concept in Russia are given. The conditions with fulfillment of works on NPP unit pre-decommissioning and decommissioning including: development of the normative documentation, creation of special fund for financing NPP decommissioning activities, deriving the Gosatomnadzor license for decommissioning of shut down NPP units, development of the equipment and technologies for waste and spent fuel management are presented. The decommissioning cost and labour intensity of one WWER-440 unit are shown. The practical works, executed on shut down units at Beloyarsk NPP (Unit1 and 2) and Novo Voronezh NPP (Unit 1 and 2) are outlined

  10. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Appendices. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Appendices are presented concerning the evaluations of decommissioning financing alternatives; reference site description; reference BWR facility description; radiation dose rate and concrete surface contamination data; radionuclide inventories; public radiation dose models and calculated maximum annual doses; decommissioning methods; generic decommissioning information; immediate dismantlement details; passive safe storage, continuing care, and deferred dismantlement details; entombment details; demolition and site restoration details; cost estimating bases; public radiological safety assessment details; and details of alternate study bases.

  11. Recycling and Reuse of Materials Arising from the Decommissioning of Nuclear Facilities. A Report by the NEA Co-operative Program on Decommissioning

    International Nuclear Information System (INIS)

    Ooms, Bart; Verwaest, Isi; Legee, Frederic; Nokhamzon, Jean-Guy; Pieraccini, Michel; Poncet, Philippe; Franzen, Nicole; Vignaroli, Tiziano; Herschend, Bjoern; Benest, Terry; Loudon, David; Favret, Derek; Weber, Inge; )

    2017-01-01

    Large quantities of materials arising from the decommissioning of nuclear facilities are non-radioactive per se. An additional, significant share of materials is of very low-level or low-level radioactivity and can, after having undergone treatment and a clearance process, be recycled and reused in a restricted or unrestricted way. Recycle and reuse options today provide valuable solutions to minimise radioactive waste from decommissioning and at the same time maximise the recovery of valuable materials. The NEA Co-operative Programme on Decommissioning (CPD) prepared this overview on the various approaches being undertaken by international and national organisations for the management of slightly contaminated material resulting from activities in the nuclear sector. The report draws on CPD member organisations' experiences and practices related to recycling and reuse, which were gathered through an international survey. It provides information on improvements and changes in technologies, methodologies and regulations since the 1996 report on this subject, with the conclusions and recommendations taking into account 20 years of additional experience that will be useful for current and future practitioners. Case studies are provided to illustrate significant points of interest, for example in relation to scrap metals, concrete and soil

  12. The use of managing agencies in decommissioning

    International Nuclear Information System (INIS)

    Nelson, R.L.

    1994-01-01

    On 1 April 1994 UKAEA Government Division was formed and one of its main responsibilities is the safe and cost effective management of the facilities which have already closed and the fuel reprocessing and radioactive waste management plant required to assist in the current programme of decommissioning. UKAEA Government Division, working on behalf of DTI, is intended to be a lean and efficient programme management and procurement organisation. Rather than build up its own project management capability it intends to use external resources for this function, obtained in future by competitive tendering. For each major facility undergoing decommissioning a Managing Agency has been, or will be, appointed to act on behalf of UKAEA Government Division. The responsibilities of each Managing Agency will be to assist in the definition of tasks, the commissioning of option studies and safety studies, the specification of individual contracts, management of the tendering processes and the subsequent management of the Implementation Contractors carrying out the decommissioning work, including the associated safety and training responsibilities. Teams involved in Managing Agency work require skills in project management, relevant technical issues, contract and safety management. (author)

  13. Radiological characterisation and decommissioning in Denmark

    International Nuclear Information System (INIS)

    Nellemenn, Thomas

    2012-01-01

    alpha emitters will be incorporated into the inventory calculations. Due to the variable nature of the systems being decommissioned, the sampling procedures are based on ad hoc principles. The number of samples needed is determined by the conventional characterisation of the systems. For systems where conventional knowledge is limited, more samples are generally needed earlier in the decommissioning process. Otherwise sampling can take place prior to the packing of the containers for the interim storage facility. In this case less sampling is needed as few representative samples for each material from each system in the container are sufficient. (author)

  14. Decommissioning of the Salaspils Research Reactor

    Directory of Open Access Journals (Sweden)

    Abramenkovs Andris

    2011-01-01

    Full Text Available In May 1995, the Latvian government decided to shut down the Salaspils Research Reactor and to dispense with nuclear energy in the future. The reactor has been out of operation since July 1998. A conceptual study on the decommissioning of the Salaspils Research Reactor was drawn up by Noell-KRC-Energie- und Umwelttechnik GmbH in 1998-1999. On October 26th, 1999, the Latvian government decided to start the direct dismantling to “green-field” in 2001. The upgrading of the decommissioning and dismantling plan was carried out from 2003-2004, resulting in a change of the primary goal of decommissioning. Collecting and conditioning of “historical” radioactive wastes from different storages outside and inside the reactor hall became the primary goal. All radioactive materials (more than 96 tons were conditioned for disposal in concrete containers at the radioactive wastes depository “Radons” at the Baldone site. Protective and radiation measurement equipment of the personnel was upgraded significantly. All non-radioactive equipment and materials outside the reactor buildings were released for clearance and dismantled for reuse or conventional disposal. Contaminated materials from the reactor hall were collected and removed for clearance measurements on a weekly basis.

  15. Governments' role in decommissioning nuclear power facilities

    International Nuclear Information System (INIS)

    Guindon, S.; Wendling, R.D.; Gordelier, S.; Soederberg, O.; Averous, J.; Orlando, D.

    2005-01-01

    Many nuclear power plants will reach the end of their operating lives over the next 20 years; some may be life-extended, others may not. This development will precipitate enhanced industrial and regulatory activities in the area of decommissioning. We are also witnessing in many countries a significant shift in the role of government itself: new pressures on governments, such as enhanced attention on environmental impact/mitigation and strategies to implement market-oriented approaches in a variety of sectors, including the energy sector are driving the public policy agenda. The paper will examine the range of policy issues, drawing from recent NEA studies on decommissioning policies and the recent NEA study on Government and Nuclear Energy and, strategies and costs, and other current trends and developments in the nuclear industry and in the nuclear policy fields. The paper will reflect on issues to be addressed during the conference and draw conclusions on the appropriate role of government in this area. Decommissioning policy is very specific and focused: it is not a high level policy/political issue in most instances and rarely gets the same attention as the issue surrounding the future of nuclear energy itself and public concerns regarding safety, waste and economics. One reason why decommissioning does not get the same attention as for example disposal of spent nuclear fuel might be the fact that technology is available for decommissioning, while technology for disposal of spent nuclear fuel is under development. High profile or not, it will remain an important issue for governments and industry alike particularly because of the cost and long lead times involved. In some instances, governments are the owners of the facilities to be decommissioned. In addition, decommissioning factors into issues surrounding the economics of nuclear energy and the sustainability of the nuclear option. Based on results of the Tarragona Seminar (Spain, September 2-4, 2003) and

  16. Objectivist case study research

    DEFF Research Database (Denmark)

    Ridder, Hanne Mette Ochsner; Fachner, Jörg

    2016-01-01

    be achieved through the use of objectivist case study research. The strength of the case study design is that it allows for uncovering or suggesting causal relationships in real-life settings through an intensive and rich collection of data. According to Hilliard (1993), the opposite applies for extensive......In order to comprehend the impact of music therapy or music therapy processes, a researcher might look for an approach where the topic under investigation can be understood within a broader context. This calls for a rich inclusion of data and consequently a limited number of participants and may...... designs, in which a small amount of data is gathered on a large number of subjects. With the richness of data, the intensive design is ―the primary pragmatic reason for engaging in single-case or small N research‖ (p. 374) and for working from an idiographic rather than a nomothetic perspective....

  17. Long-reach manipulators for decommissioning

    International Nuclear Information System (INIS)

    Webster, D.A.; Challinor, S.F.

    1993-01-01

    A survey of redundant facilities at Sellafield has identified that in many cases the conventional means of deploying remote handling equipment are not appropriate and that novel means must be employed. However, decommissioning is not a value adding activity and so expensive one off designs must be avoided. The paper will describe BNFL's approach to the synthesis from proprietary parts of a manipulator which can lift 3 te at a horizontal reach of over 5 metres and yet can still perform the dextrous manipulation necessary to remove small items. It will also cover the development of the manipulator control systems and the adaption of commercial handtools to be manipulator friendly. (author)

  18. Decommissioning and dismantling policy in Spain

    International Nuclear Information System (INIS)

    Landa, J.

    2004-01-01

    Decommissioning and dismantling nuclear installations is an increasingly important topic for governments, regulators, industries and civil society. There are many aspects that have to be carefully considered and planned, in many cases well in advance when they really need to be implemented. In my speech I am going to focus on policy-making considerations. Firstly I will go briefly over the current Spanish strategy on D and D, discussing the know-how we have gained from past experience. Then I will review the challenges that we will have to face in the near future, suggesting possible alternatives and approaches. I will finish talking a little bit about the international scene. (author)

  19. Decommissioning of small medical, industrial and research facilities

    International Nuclear Information System (INIS)

    2003-01-01

    of complexity, safety risk and radiological inventory. The key objective of this report is to provide information, experience and assistance on what is appropriate and sufficient for policy makers, regulators and operators of small facilities. It is intended to promote timely and cost effective decommissioning and waste management at the end of the life of a facility so as to render such a facility harmless. No statements in the report are intended to be prescriptive. There is significant documentation on the decommissioning of large nuclear facilities but the more modest requirements of small facilities have received little attention. If users of small facilities only have available to them published information for large, complex facilities, then there may be a tendency to overreact and engage in elaborate or unnecessary studies and activities. They also may shy away from important issues and do too little, either because they are not trained or advised properly or they do not have a decommissioning plan or adequate human and financial resources. They also are often unaware of the requirements, both legal and technical, of decommissioning and waste management. Some decades ago, when the first large power and demonstration reactors started to be shut down, there were many unknowns and uncertainties on how to proceed. There is now a significant experience database on common problems, which has been shared by the international nuclear power industry. This is not necessarily the case for small facilities, however, and this report is intended to encourage the interchange of information and experience. It is intended in this report to cover all aspects of decommissioning small facilities in which radioactive material and radiation sources are produced, received, used and/or stored. Power reactors, prototype and demonstration reactors, larger research reactors, fuel processing and reprocessing plants and their associated large nuclear chemical facilities, and all forms of

  20. The curious accountancy of decommissioning

    International Nuclear Information System (INIS)

    Anon.

    1990-01-01

    Financial provision for the decommissioning and waste management of the United Kingdom Magnox and AGR reactor is discussed. In the last set of accounts prior to privatisation a decommissioning provision of Pound 8.34 bn was indicated whereas previous figures had only shown Pound 2.88. It is suggested that the increase was only achieved on paper, without real financial provision. Estimates of decommissioning costs for the Magnox stations have increased greatly. Cost estimates for AGR decommissioning have still to be released but it is expected that the post-privatisation owners of the nuclear power industry, Nuclear Electric, will have to find Pound 6-7 bn to dismantle its own reactors. Much of this it hopes to put off for over 100 years. The South of Scotland Electicity Board has made much more realistic provision for its own Magnox and two AGR stations. Reprocessing costs for AGR reactor fuel is uncertain and high reprocessing and decommissioning costs will mean increases in the price of nuclear electricity. (UK)

  1. Case Studies - Cervical Cancer

    Centers for Disease Control (CDC) Podcasts

    Dr. Alan Waxman, a professor of obstetrics and gynecology at the University of New Mexico and chair of the American College of Obstetricians and Gynecologists (ACOG) committee for the underserved, talks about several case studies for cervical cancer screening and management.

  2. Nuclear forensics case studies

    International Nuclear Information System (INIS)

    Fedchenko, Vitaly

    2016-01-01

    The objective of this presentation is to share three case studies from the Institute of Transuranium Elements (ITU) which describe the application of nuclear forensics to events where nuclear and other radioactive material was found to be out of regulatory control

  3. SCA12 case study

    Indian Academy of Sciences (India)

    Home; Journals; Journal of Genetics; Volume 88; Issue 1. Utilizing linkage disequilibrium information from Indian Genome Variation Database for mapping mutations: SCA12 case study. Samira Bahl Ikhlak Ahmed The Indian Genome Variation Consortium Mitali Mukerji. Research Article Volume 88 Issue 1 April 2009 pp 55- ...

  4. national Case study

    African Journals Online (AJOL)

    This national case study reports on the development of a national network, ... system under the new policy), tends to be limited by content on problems and ... 20 credit programme; and within two Post Graduate Certificate of Education contexts, ...... descriptive with an issues focus (empirical) towards awareness production to.

  5. The study of the container types used for transport and final disposal of the radioactive wastes resulting from decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Postelnicu, C.

    1998-01-01

    The purpose of the present paper is to select from a variety of package forms and capacities some containers which will be used for transport and disposal of the radioactive wastes resulting from decommissioning of nuclear facilities into the National Repository for Radioactive Waste - Baita, Bihor county. Taken into account the possibilities of railway and / or road transport and waste disposal in our country, detailed container classification was given in order to use them for radioactive waste transport and final disposal from decommissioning of IFIN-HH Research Reactor. (author)

  6. State of decommissioning process in Romania

    International Nuclear Information System (INIS)

    Ciuculescu, C.

    2002-01-01

    In Romania, there are several installations that arrived at the decommissioning stage. These installations are: VVR-S research reactor, Sub critical Assembly HELEN, and Zero Power Reactor (RP-0). In this paper, the methods the Romanian Regulatory Body is developing the legal framework for decommissioning process of nuclear installations are described. There is a draft of decommissioning norms for research reactors. This regulation provides each stage of decommissioning and requirements for decommissioning plan. Also, CNCAN has evaluated and made requirements for completion of a VVR-S research reactor decommissioning plan submitted by IFIN-HH. Further, the reasons for which the decommissioning plan was rejected and requirements that the owner of VVR-S research reactor must fulfil in order to receive decommissioning licence are presented. (author)

  7. MRI case studies

    International Nuclear Information System (INIS)

    Huggett, S.; Barber, J.

    1989-01-01

    Three case studies are presented to show the value of magnetic resonance imaging used in conjunction with other imaging techniques. In each case MRI proved a vital diagnostic tool and superior to CT in showing firstly the haematoma in a patient with aphasia and right-sided weakness, secondly the size of the disc herniation in a patient with severe leg and ankle pains and thirdly the existence of a metastatic lesion in a patient with a previous history of breast cancer. 11 figs

  8. Decommissioning Plan for European Spallation Source

    Directory of Open Access Journals (Sweden)

    Ene Daniela

    2017-01-01

    Full Text Available This paper is a survey of the European Spallation Source initial decommissioning plan developed in compliance with Swedish Regulatory Authority requirements. The report outlines the decommissioning strategy selected and the baseline plan for decommissioning. Types and quantities of radioactive waste estimated to be generated at the final shut-down of the facility are further provided. The paper ends up with the analysis of the key elements of the decommissioning plan and the recommendations to the ESS management team..

  9. The Italian decommissioning industry

    International Nuclear Information System (INIS)

    Adinolfi, R.

    2005-01-01

    Full text: Italy's step out from nuclear activities in 1987 deeply affected an industry that, in the previous years, had managed to grow up in quality and technology levels to meet the nuclear standards. Only a few companies were able to partially retain their skills through activities abroad. The decommissioning program represents a new challenge for the Italian industry at large and will require a consistent effort to properly qualify the potential suppliers. On the other side, a program with such implications in terms of investments and so depending from social aspects cannot be effectively implemented without a significant involvement of the local industry. Essential conditions for the success are a reliable program, as well as a careful supply management scheme, which must facilitate aggregation of skills spread among different subjects. 'Human Resources: Maintaining a Nuclear Culture in Italy' Bruno Panella Politecnico di Torino, Giuseppe Forasassi, Universita di Pisa, Inter-University Consortium for the Nuclear Technological Research (CIRTEN). After a brief history of the nuclear engineering education in Italy within the international and national nuclear energy scenario, the present situation, with reference to the Italian universities, is shown. In order to maintain a nuclear culture in Italy the solution, exploited with different peculiarities in each University, is to carry out high quality research activities in reciprocal collaboration (mostly within the CIRTEN inter university Consortium) as well as with the Industry and research Organisations and to collaborate actively in establishing a stable network and a synergy of teaching activities in Europe in the field of Nuclear Engineering Education. The aim is to maintain at a high level and as updated as possible the Italian educational offer in nuclear engineering and also to attract the best students for the enrolment. (author)

  10. Business operations and decommissioning strategy for imperial college London research reactor 'Consort' - A financial risk management approach

    International Nuclear Information System (INIS)

    Franklin, S.J.; Gardner, D.; Mumford, J.; Lea, R.; Knight, J.

    2005-01-01

    Imperial College London (IC) operates commercially a 100 kW research reactor, and as site licensee is responsible for funding both operations and eventual decommissioning. With long lead times ahead urgent decisions on the future business options have had to be made in 2004/5 including choices on whether to move to early decommissioning, recognising the high costs entailed, or to pursue continuing operations involving life extension measures such as refuelling. To develop a coherent overall approach strategy a financial risk driven programme was initiated to help define a robust transparent business and termination case for the reactor. This study was carried out in collaboration with a UK firm of financial risk experts, PURE Risk Management Ltd (PURE), working within a dedicated IC London reactor project team. This work evaluated immediate closure options due to financial constraints or life limiting failures, and options for continuing operation extending to 2028. Decommissioning and clean up were reviewed. Bespoke financial models created single value cost outputs and ranges of probabilistic net present values (NPV) for decommissioning costs and financial provisions to meet those costs at various levels of risk acceptance and regulatory compliance. (author)

  11. Global solutions through simulation for better decommissioning

    International Nuclear Information System (INIS)

    Scoto Di Suoccio, Ines; Testard, Vincent

    2016-01-01

    be tried, analyzed and compared on all output parameters in a total accordance with the ALARA/ALARP approach. Then, contingencies can be prevented by testing an infinite number of situations whatever the uncertainties are, and this enables to determine the best scenario strategy for each set of data. Simulations also allow people to test not only access issues into some environment but also radiological access. By testing different dosimetric configurations or hot spot location, simulation allows you to test them and so reduce risks. For a specific environment, when many scenarios have been developed and tested, sensitivity studies are really important to choose the optimal decommissioning strategy. Sensitivity studies can be done with simulation tools by comparing results of scenarios directly into the software. This comparison helps to choose the optimal scenario according to which output data is considered as key determinant. Simulation offers a very good return on investment in the sense that many scenarios are quick to do, they can be copied and the user can change one input data to observe instantaneously the impacts of this change on results. Doing different simulations permit to quantify risks, reduce hazard and therefore reduce costs. Finally, simulation tools enable to collect output data of decommissioning projects during realization, comparing them in real time to the studies assessments. This improve the feedback acquisition, very important in the decommissioning field in which we do not have a lot of experience. Current experiences of studies using DEMplus on different kind of projects show several benefits either on the entry data consolidation, the scenario optimization and the risks studies. The ALARA/ALARP approach is fully developed by simulating a large set of strategies, using a cost-benefits analysis on many criteria. A unique software that deals with all types of entry data in order to compute results is clearly a powerful tool as a decision

  12. Radiation safety for decommissioning projects

    International Nuclear Information System (INIS)

    Ross, A.C.

    1999-01-01

    Decommissioning of redundant nuclear facilities is a growth area in the UK at the present time. NUKEM Nuclear Limited is a leading-edge nuclear decommissioning and waste management contractor (with its own in-house health physics and safety department), working for a variety of clients throughout the UK nuclear industry. NUKEM Nuclear is part of the prestigious, international NUKEM group, a world-class organization specializing in nuclear engineering and utilities technologies. NUKEM Nuclear is involved in a number of large, complex decommissioning projects, both in its own right and as part of consortia. This paper explores the challenges presented by such projects and the interfaces of contractor, client and subcontractors from the point of view of a radiation protection adviser. (author)

  13. Platform decommissioning. Environmental challenges and practical solutions

    International Nuclear Information System (INIS)

    Kvalvik, Inge

    1998-01-01

    The publication gives a short introduction of platform decommissioning, followed by an overview of what to be decommissioned and removed. This will be followed by some of the vital technologies and methods within decommissioning, abandonment of wells, removal and handling of remains that is reuse and scrapping. A final presentation with a view of current research and developments is given. 3 figs

  14. 77 FR 41107 - Decommissioning Planning During Operations

    Science.gov (United States)

    2012-07-12

    ..., 40, 50, 70, and 72 [NRC-2011-0162] Decommissioning Planning During Operations AGENCY: Nuclear... (DG) 4014, ``Decommissioning Planning During Operations.'' This guide describes a method that the NRC staff considers acceptable for use in complying with the NRC's Decommissioning Planning Rule. The NRC...

  15. 76 FR 77431 - Decommissioning Planning During Operations

    Science.gov (United States)

    2011-12-13

    ... (DG) DG-4014, ``Decommissioning Planning During Operations.'' This guide describes a method that the.... The draft regulatory guide entitled, ``Decommissioning Planning During Operations,'' is temporarily..., 40, 50, 70, and 72 RIN 3150-AI55 [NRC-2011-0286; NRC-2008-0030] Decommissioning Planning During...

  16. 78 FR 663 - Decommissioning Planning During Operations

    Science.gov (United States)

    2013-01-04

    ...] Decommissioning Planning During Operations AGENCY: Nuclear Regulatory Commission. ACTION: Regulatory guide..., ``Decommissioning Planning During Operations.'' The guide describes a method that the NRC staff considers acceptable for use by holders of licenses in complying with the NRC's Decommissioning Planning Rule (DPR) (76 FR...

  17. Decommissioning experience at UKAEA Winfrith

    International Nuclear Information System (INIS)

    Miller, K.

    2008-01-01

    The Winfrith Site was used for development of nuclear reactors, particularly the 100 MW(e) Steam Generating Heavy Water Reactor (SGHWR) and the 30 MW gas-cooled DRAGON reactor. Following the closure of the SGHWR reactor in 1990 the site has run down nuclear operations by removing from site most of the high level hazards from both reactors and then commencing the decommissioning of major items of plant and other site facilities. After the SGHWR was shut down, UKAEA prepared a decommissioning programme for this plant comprising a multistage process, each to be subjected to a competitive tendering operation. The recently completed Stage 1 decommissioning contract, awarded to Nuvia in 2005, involved decommissioning and removal of all the ancillary plant and equipment in the secondary containment and non-containment areas of the plant. The decommissioning processes involved with these large and heavy plant items will be described with some emphasis of the establishment of multiple work-fronts for the production, recovery, treatment and disposal of mainly tritium contaminated waste arising from its contact with the direct cycle reactor coolant. The means of size reduction of a variety of large, heavy and complex items of plant made from a range of materials will also be described with some emphasis on the control of fumes during hot cutting operations. Over the past 18 years Nuvia has gained vast experience with decommissioning operations on redundant nuclear plant and facilities on the Winfrith Site and has been extremely successful in meeting its contractual obligations in a safe and efficient manner. The final section of the paper will dwell upon the key issues that have made a difference in achieving these objectives for the benefit of others involved in similar operations. (author)

  18. The Practice of Cost Estimation for Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    Davidova, Ivana; Desecures, Sylvain; Lexow, Thomas; Buonarroti, Stefano; Marini, Giuseppe; Pescatore, Claudio; Rehak, Ivan; Weber, Inge; ); Daniska, Vladimir; Linan, Jorge Borque; Caroll, Simon; Hedberg, Bjoern; De La Gardie, Fredrik; Haenggi, Hannes; Laguardia, Thomas S.; Ridpath, Andy

    2015-01-01

    Decommissioning of both commercial and R and D nuclear facilities is expected to increase significantly in the coming years, and the largest of such industrial decommissioning projects could command considerable budgets. Several approaches are currently being used for decommissioning cost estimations, with an international culture developing in the field. The present cost estimation practice guide was prepared in order to offer international actors specific guidance in preparing quality cost and schedule estimates to support detailed budgeting for the preparation of decommissioning plans, for the securing of funds and for decommissioning implementation. This guide is based on current practices and standards in a number of NEA member countries and aims to help consolidate the practice and process of decommissioning cost estimation so as to make it more widely understood. It offers a useful reference for the practitioner and for training programmes. The remainder of report is divided into the following chapters: - Chapter 2 covers the purpose and nature of decommissioning cost estimates, approaches to cost estimation and the major elements of a cost estimate. - Chapter 3 examines the development of the integrated schedule of the activity-dependent work scope and the determination of the project critical path. - Chapter 4 describes the attributes of a quality assurance programme applicable to cost estimation and the use and cautions of benchmarking the estimate from other estimates or actual costs. - Chapter 5 describes the pyramidal structure of the report, and the scope and content that should be included in the cost study report to ensure consistency and transparency in the estimate underpinnings. - Chapter 6 provides some observations, conclusions and recommendations on the use of this guide

  19. Shippingport: A relevant decommissioning project

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    Because of Shippingport's low electrical power rating (72 MWe), there has been some misunderstanding on the relevancy of the Shippingport Station Decommissioning Project (SSDP) to a modern 1175 MWe commercial pressurized water reactor (PWR) power station. This paper provides a comparison of the major components of the reactor plant of the 72 MWe Shippingport Atomic Power Station and an 1175 MWe nuclear plant and the relevancy of the Shippingport decommissioning as a demonstration project for the nuclear industry. For the purpose of this comparison, Portland General Electric Company's 1175 MWe Trojan Nuclear Plant at Rainier, Oregon, has been used as the reference nuclear power plant. 2 refs., 2 figs., 1 tab

  20. Decommissioning: guiding principles and best practices for involving local stakeholders

    International Nuclear Information System (INIS)

    Keyes, D.

    2005-01-01

    Full text: A wide range of nuclear facilities covering the entire nuclear fuel cycle have been constructed and operated for many years worldwide. For communities where the facilities are located, concerns about safety and environmental contamination are paramount. Working together with elected officials, local community leaders and the public at large during the earliest planning stages will help alleviate concerns about facility operation and ultimate disposition, and will result in better decisions about facility design, location, construction, operation and, ultimately, decommissioning. Such comprehensive community involvement has been the exception rather than the norm. Now that older facilities are being considered for decommissioning, efforts to involve local stakeholders and alleviate their concerns face major challenges. This is particularly true where some residual radioactive contamination will remain onsite and future use of the site may need to be restricted. Plans for stakeholder involvement at the decommissioning stage should be carefully designed and provide for honest, authentic and meaningful involvement of all stakeholders affected by decommissioning decisions. A set of principles and best practices is proposed to help guide the design and implementation of effective community involvement programs. The principles and best practices are drawn from the experiences of public involvement practitioners in a variety of environmental contamination applications. Successful community involvement is the result of a carefully crafted set of coordinated activities conducted over the long term. Ideally, facility decommissioning is simply the end stage of the involvement process, or the beginning of a site stewardship process in those cases where decommissioning does not produce an uncontaminated site. In either case, decommissioning will not be a new, unexpected event, and stakeholders could be involved just as they have been over the life of the facility. In

  1. Study of fundamental safety-related aspects in connection with the decommissioning of nuclear installations. Pt. 2. Safety considerations and emissions

    International Nuclear Information System (INIS)

    John, T.; Thierfeldt, S.

    1993-01-01

    The procedures used so far for the examination of selected decommissioning projects in expert opinions on safety, in particular of nuclear power plants, were screened, with special emphasis on the examination of safety considerations, i.e. analysis of possible accidents. Generic examinations on safety in connection with the decommissioning of nuclear installations were used to assess safety considerations. Different approaches were taken with regard to the selection of analysed accidents and determination of parameters defining activity release and assumptions in safety opinions. Therefore it seems to be appropriate to establish a scenario to be used for nuclear power plant accident analyses, which covers the range of radiologically relevant accidents during decommissioning activities. Although it might be controversially discussed, because of specific plant designs (test and prototype reactors as well as first power reactors), to establish such a radiologically covering accident scenario for older nuclear power plants, it seems to be no problem for modern light water reactors. The radiologically most relevant possible accident in a decommissioned nuclear power plant is fire in the plant. Parameter values and assumptions are suggested which determine the source term in the event of a fire in the plant. Inspite of a conservative determination of parameter values and assumptions, an environmental dose commitment of less than 50 mSv is to be expected for the resulting source term. (orig.) [de

  2. Case study - Czechoslovakia

    International Nuclear Information System (INIS)

    Kovar, P.

    1986-01-01

    In the lecture Case Study - Czechoslovakia with the sub-title 'Unified System of Personnel Preparation for Nuclear Programme in Czechoslovakia' the actual status and the current experience of NPP personnel training and preparation in Czechoslovakia are introduced. The above mentioned training system is presented and demonstrated by the story of a proxy person who is going to become shift engineer in a nuclear power plant in Czechoslovakia. (orig./HP)

  3. Case Studies - Cervical Cancer

    Centers for Disease Control (CDC) Podcasts

    2010-10-15

    Dr. Alan Waxman, a professor of obstetrics and gynecology at the University of New Mexico and chair of the American College of Obstetricians and Gynecologists (ACOG) committee for the underserved, talks about several case studies for cervical cancer screening and management.  Created: 10/15/2010 by National Center for Chronic Disease Prevention and Health Promotion (NCCDPHP), Division of Cancer Prevention and Control (DCPC).   Date Released: 6/9/2010.

  4. Main elements in favour of an immediate decommissioning

    International Nuclear Information System (INIS)

    Cregut, A.

    1985-01-01

    After a presentation of the elements to be taken into consideration when undertaking a comparative study of the diverse possible solutions for the future of a shut down nuclear reactor, this outlines the advantages of simultaneously decommissioning and conducting final shut down operations. It is clarified that in a real situation the benefits of demonstration and judgement on the technical solutions adopted are arguments in favour of this approach but that this is only true for the first case. The advantages of this approach in a systematic manner are then developed. In conclusion, the advantages associated with this approach are theoretically beyond question and it should not be rejected a priori. However, if it is a question of taken a decision on the future of a nuclear installation, it is necessary to quantify and compare the advantages and disadvantages of other approaches in order to make the best choice

  5. Decontamination and Decommissioning at Small Nuclear Facilities: Facilitating the Submission of Decommissioning Funding Plans

    International Nuclear Information System (INIS)

    Minor, D.A.; Grumbles, A.

    2009-01-01

    This paper describes the efforts of the Washington State Department of Health to ensure that small nuclear facilities have the tools each needs to submit Decommissioning Funding Plans. These Plans are required by both the U.S. Nuclear Regulatory Commission (NRC) and in some states - in the case of Washington state, the Washington State Department of Health is the regulator of radioactive materials. Unfortunately, the guidance documents provided by the U.S. NRC pertain to large nuclear facilities, such as nuclear fuel fabrication plants, not the small nuclear laboratory nor small nuclear laundry that may also be required to submit such Plans. These small facilities are required to submit Decommissioning Funding Plans by dint of their nuclear materials inventory, but have only a small staff, such as a Radiation Safety Officer and few authorized users. The Washington State Department of Health and Attenuation Environmental Company have been working on certain tools, such as templates and spreadsheets, that are intended to assist these small nuclear facilities prepare compliant Decommissioning Funding Plans with a minimum of experience and effort. (authors)

  6. Estimating of funding levels for decommissioning

    International Nuclear Information System (INIS)

    Sieving, K.W.

    1985-01-01

    In order to meet its public service obligations, an electric utility must attain the following objectives: Recognize future power requirements early, and take appropriate actions to satisfy them; Construct new generating, transmission and distribution facilities in a timely and economical manner; Operate its facilities safely, and maintain them without decreasing the quality and reliability of service. In the case of a nuclear electric generating station, the third objective includes the obligation to decommission the station following shutdown at the end of its useful life and to dispose of residual radioactivity in accordance with Nuclear Regulatory Commission guidelines, as a part of the process of terminating the NRC license. In the case of an investor-owned electric utility, the third objective includes the additional duty to estimate the cost of decommissioning for ratemaking purposes, since the funds required for this future event must be collected over the life of the generating station from the consumers who enjoy the benefits of its output. This article deals with these issues

  7. Decommissioning and abandonment of offshore installations

    International Nuclear Information System (INIS)

    Side, J.C.

    1992-01-01

    To the onlooker surprising little thought was given at the project planning stage to the fate of offshore facilities once their production lifetimes had come to an end. Throughout the 1970s at least, international law required the complete removal of all structures and installations one disused or abandoned. Fishermen's organisations were led to believe that such installations would be entirely removed yet many of the designs of these show that removal was not much in the minds of the engineers or project management during the design stages. Changes in the text of the United Nations' Convention on the Law of the Sea and (by their widespread legal adoption) in customary international law may now permit partial removal of installations subject to important safeguards for navigation, the environment and other users of the sea. Of the North Sea states at least one has adopted policies that will minimise the cost associated with offshore decommissioning and abandonment and both the UK and Norway are adopting legislation which will provide for a case by case approach to the decommissioning and abandonment of offshore facilities and allow partial removal options. There has thus been a recent and significant change in approach to the abandonment of offshore oil and gas installations. This chapter reviews the development of abandonment laws and policies, outlines the available removal options, and provides a consideration of the environmental and fishery implications of these for the North Sea. (Author)

  8. Decommissioning in British Nuclear Fuels plc

    International Nuclear Information System (INIS)

    Colquhoun, A.

    1988-01-01

    Decommissioning projects at the BNFL Sellafield site have been selected taking the following into account; the need to gain experience in preparation for the decommissioning of the Magnox reactors and for the post Magnox stage; the need to develop larger scale projects; the need to be cost effective and to foster long term safety. The balance between prompt or delayed decommissioning has to consider operator dose uptake and radioactive waste management. The ten year plan for decommissioning at Sellafield is described briefly. Currently decommissioning is of the fuel pond and decanning plant, the Windscale Pile Chimneys, the coprecipitation plant and the uranium recovery plant. (author)

  9. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    Pasquini, L.A.

    1986-01-01

    The purpose of the Shippingport Station Decommissioning Project (SSDP) is to place the Shippingport Atomic Power Station in a long-term radiologically safe condition following defueling of the reactor, to perform decommissioning in such a manner as to demonstrate to the nuclear industry the application of decommissioning procedures to a large scale nuclear power plant, and to provide useful planning data for future decommissioning projects. This paper describes the Technology Transfer Program for collecting and archiving the decommissioning data base and its availability to the nuclear industry

  10. Civil engineering design for decommissioning of nuclear installations

    International Nuclear Information System (INIS)

    Paton, A.A.; Benwell, P.; Irwin, T.F.; Hunter, I.

    1984-01-01

    This report describes the work carried out by Taylor Woodrow Construction Limited (TWC) in a study aimed at identifying features which may be incorporated at the design stage of future nuclear power plants to facilitate their eventual decommissioning and, in so doing, promote economic and radiological benefits at teh decommissioning stage. For the purposes of this study, decommissioning of a nuclear facility means those measures taken at the end of the facility's operating life to remove it from the site and restore the site to green field conditions, and, while so doing, ensure the continued protection of the public from any residual radioactivity or other potential hazards present in or emanating from the facility. The overall decommissioning process involves eventual dismantling and demolition and may also include, where possible and appropriate, the intermediate steps of renewal and refurbishing. The work has been carried out in a number of sequential stages consisting principally of a literature review, identification of problems likely to arise in decommissioning, generation of possible solutions to the problems, first assessment of the feasibility of these solutions, closer investigation of promising solutions and, finally, preparation of conclusions and recommendations. (author)

  11. On-site disposal as a decommissioning strategy

    International Nuclear Information System (INIS)

    1999-11-01

    On-site disposal is not a novel decommissioning strategy in the history of the nuclear industry. Several projects based on this strategy have been implemented. Moreover, a number of studies and proposals have explored variations within the strategy, ranging from in situ disposal of entire facilities or portions thereof to disposal within the site boundary of major components such as the reactor pressure vessel or steam generators. Regardless of these initiatives, and despite a significant potential for dose, radioactive waste and cost reduction, on-site disposal has often been disregarded as a viable decommissioning strategy, generally as the result of environmental and other public concerns. Little attention has been given to on-site disposal in previous IAEA publications in the field of decommissioning. The objective of this report is to establish an awareness of technical factors that may or may not favour the adoption of on-site disposal as a decommissioning strategy. In addition, this report presents an overview of relevant national experiences, studies and proposals. The expected end result is to show that, subject to safety and environmental protection assessment, on-site disposal can be a viable decommissioning option and should be taken into consideration in decision making

  12. Environmental Problems Associated With Decommissioning The Chernobyl Nuclear Power Plant Cooling Pond

    International Nuclear Information System (INIS)

    Farfan, E. B.; Jannik, G. T.; Marra, J. C.; Oskolkov, B. Ya.; Bondarkov, M. D.; Gaschak, S. P.; Maksymenko, A. M.; Maksymenko, V. M.; Martynenko, V. I.

    2009-01-01

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning

  13. Decommissioning: A critical component of the design for uranium tailings management facilities

    International Nuclear Information System (INIS)

    Clifton, W.A.; Barsi, R.G.; Misfeldt, G.A.

    2000-01-01

    Uranium was discovered in the Beaverlodge area of northern Saskatchewan in 1934 with the first major mill beginning operation in 1953. Little attention was paid to tailings quality or tailings management practices. With the onset of the modem uranium operations beginning in the late 1970's, it was repeatedly evident, that the public had significant concerns, particularly with respect to tailings management, that must be addressed if the developments were to be allowed to proceed. Primary considerations related to environmental protection, public safety and an assurance of the ongoing sustainable development of the region. Integrating the decommissioning of a mine/mill site into development planning from the very outset has proven to be a critical component that has contributed to the ongoing success of the Saskatchewan uranium operations. This paper will provide a case study of the evolution of the uranium tailings management technology utilized in Saskatchewan. It documents the evolution of tailings management processes and the characteristics of tailings produced by successive mines in northern Saskatchewan. It also discusses the evolution of technologies applied to management of uranium mill tailings and demonstrates how progressively increasing levels of environmental protection have been achieved during the last 47 years of uranium mill operation. The paper also shows that the planned and progressive decommissioning of an operational site is the key to: Minimizing environmental impacts; Satisfying public and regulatory concerns; Minimizing operational and decommissioning costs; Minimizing corporate liability; and Shifting public resistance to public support. (author)

  14. Decommissioning: A critical component of the design for uranium tailings management facilities

    International Nuclear Information System (INIS)

    Clifton, A.W.; Barsi, R.G.; Misfeldt, G.A.

    2002-01-01

    Uranium was discovered in the Beaverlodge area of northern Saskatchewan in 1934 with the first major mill beginning operation in 1953. Little attention was paid to tailings quality or tailings management practices. With the onset of the modern uranium operations beginning in the late 1970's, it was repeatedly evident, that the public had significant concerns, particularly with respect to tailings management, that must be addressed if the developments were to be allowed to proceed. Primary considerations related to environmental protection, public safety and an assurance of the ongoing sustainable development of the region. Integrating the decommissioning of a mine/mill site into development planning from the very outset has proven to be a critical component that has contributed to the ongoing success of the Saskatchewan uranium operations. This paper will provide a case study of the evolution of the uranium tailings management technology utilized in Saskatchewan. It documents the evolution of tailings management processes and the characteristics of tailings produced by successive mines in northern Saskatchewan. It also discusses the evolution of technologies applied to management of uranium mill tailings and demonstrates how progressively increasing levels of environmental protection have been achieved during the last 47 years of uranium mill operation. The paper also shows that the planned and progressive decommissioning of an operational site is the key to: Minimizing environmental impacts; Satisfying public and regulatory concerns; Minimizing operational and decommissioning costs; Minimizing corporate liability; and Shifting public resistance to public support. (author)

  15. Environmental Problems Associated With Decommissioning The Chernobyl Nuclear Power Plant Cooling Pond

    Energy Technology Data Exchange (ETDEWEB)

    Farfan, E. B.; Jannik, G. T.; Marra, J. C.; Oskolkov, B. Ya.; Bondarkov, M. D.; Gaschak, S. P.; Maksymenko, A. M.; Maksymenko, V. M.; Martynenko, V. I.

    2009-11-09

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  16. ENVIRONMENTAL PROBLEMS ASSOCIATED WITH DECOMMISSIONING THE CHERNOBYL NUCLEAR POWER PLANT COOLING POND

    Energy Technology Data Exchange (ETDEWEB)

    Farfan, E.

    2009-09-30

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  17. 76 FR 35511 - Decommissioning Planning

    Science.gov (United States)

    2011-06-17

    ... licensees to conduct their operations to minimize the introduction of residual radioactivity into the site... account and line of credit as approved financial assurance mechanisms, and modify other financial... additional information on the costs of decommissioning and spent fuel management. DATES: The final rule is...

  18. A Decommissioning Information Management System

    Energy Technology Data Exchange (ETDEWEB)

    Park, S. K.; Hong, S. B.; Chung, U. S.; Park, J. H. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2007-07-01

    In 1996, it was determined that research reactors, the KRR-1 and the KRR-2, would be shut down and dismantled. A project for the decommissioning of these reactors was launched in January 1997 with the goal of a completion by 2008. The total budget of the project was 19.4 million US dollars, including the cost for the waste disposal and for the technology development. The work scopes during the decommissioning project were the dismantling of all the facilities and the removal of all the radioactive materials from the reactor site. After the removal of the entire radioactivity, the site and buildings will be released for an unconditional use. A separate project for the decommissioning of the uranium conversion plant was initiated in 2001. The plant was constructed for the development of the fuel manufacturing technologies and the localization of nuclear fuels in Korea. It was shut downed in 1993 and finally it was concluded in 2000 that the plant would be decommissioned. The project will be completed by 2008 and the total budget was 9.2 million US dollars. During this project, all vessels and equipment will be dismantled and the building surface will be decontaminated to be utilized as general laboratories.

  19. Case Study - Alpha

    Directory of Open Access Journals (Sweden)

    Stephen Leybourne

    2016-11-01

    Full Text Available This case study was developed from an actual scenario by Dr. Steve Leybourne of Boston University.  The case documents the historical evolution of an organization, and has been used successfully in courses dealing with organizational and cultural change, and the utilization of ‘soft skills’ in project-based management. This is a short case, ideal for classroom use and discussion.  The issues are easily accessible to students, and there is a single wide ranging question that allows for the inclusion of many issues surrounding strategic decision-making, and behavioural and cultural change. Alpha was one of the earlier companies in the USA to invest in large, edge-of-town superstores, with plentiful free vehicle parking, selling food and related household products. Alpha was created in the 1950s as a subsidiary of a major publicly quoted retail group.  It started business by opening a string of very large discount stores in converted industrial and warehouse premises in the south of the United States. In the early days shoppers were offered a limited range of very competitively priced products. When Alpha went public in 1981 it was the fourth largest food retailer in the US, selling an ever-widening range of food and non-food products.  Its success continued to be based on high volume, low margins and good value for money, under the slogan of ‘Alpha Price.’

  20. A Comparative Perspective on Reactor Decommissioning

    International Nuclear Information System (INIS)

    Devgun, J.S.; Zelmer, R.

    2006-01-01

    A comparative perspective on decommissioning, based on facts and figures as well as the national policies, is useful in identifying mutually beneficial 'lessons learned' from various decommissioning programs. In this paper we provide such a perspective on the US and European approaches based on a review of the programmatic experience and the decommissioning projects. The European countries selected for comparison, UK, France, and Germany, have nuclear power programs comparable in size and vintage to the US program but have distinctly different policies at the federal level. The national decommissioning scene has a lot to do with how national nuclear energy policies are shaped. Substantial experience exists in all decommissioning programs and the technology is in a mature state. Substantial cost savings can result from sharing of decommissioning information, technologies and approaches among various programs. However, the Achilles' heel for the decommissioning industry remains the lack of appropriate disposal facilities for the nuclear wastes. (authors)

  1. AECL's waste management and decommissioning program

    International Nuclear Information System (INIS)

    Kupferschmidt, W.C.H.

    2006-01-01

    Full text: Canada has developed significant expertise in radioactive waste management since the mid 1940s, when the Canadian nuclear program commenced activities at Chalk River Laboratories (CRL). Atomic Energy of Canada Limited (AECL), created as a Federal Crown Corporation in 1952, continues to manage wastes from these early days, as well as other radioactive wastes produced by Canadian hospitals, universities, industry, and operational wastes from AECL's current programs. AECL is also carrying out decommissioning of nuclear facilities and installations in Canada, predominantly at its own sites in Ontario (CRL, and the Douglas Point and Nuclear Power Demonstration prototype reactors), Manitoba (Whiteshell Laboratories) and Quebec (Gentilly-1 prototype reactor). At the CRL site, several major waste management enabling facilities are being developed to facilitate both the near- and long-term management of radioactive wastes. For example, the Liquid Waste Transfer and Storage Project is underway to recover and process highly radioactive liquid wastes, currently stored in underground tanks that, in some cases, date back to the initial operations of the site. This project will stabilize the wastes and place them in modern, monitored storage for subsequent solidification and disposal. Another initiative, the Fuel Packaging and Storage Project, has been initiated to recover and condition degraded used fuel that is currently stored in below-ground standpipes. The fuel will be then be stored in new facilities based on an adaptation of AECL's proven MACSTOR TM * dry storage system, originally designed for intermediate-term above-ground storage of used CANDU fuel bundles. Other commercial-based development work is underway to improve the storage density of the MACSTOR TM design, and to extend its application to interim storage of used LWR fuels as well as to the storage of intermediate-level radioactive waste arising from upcoming reactor refurbishment activities in Canada

  2. Strategic aspects on waste management in decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Rannemalm, T.; Eliasson, S.; Larsson, A.; Lidar, P.; Bergh, N.; Hedin, G.

    2017-01-01

    A team composed of experts from the facility owner OKG, Westinghouse and Studsvik (today Cyclife Sweden and Studsvik Consulting) was asked to develop a basis for decision on an overall strategy for the management of the material and waste arising from the decommissioning of two BWR NPPs at the Oskarshamn site in Sweden. To be able to provide a good basis for decision the full waste management chain from generation to disposition, i.e. clearance or disposal had to be assessed, categorised, quantified and analysed with regards to costs, environmental impact and risks. A systematic approach was applied taking benefit of the decommissioning studies made previously for the two facilities, the decommissioning concepts developed by Ndcon (the partnership in decommissioning between Studsvik and Westinghouse) and the combined knowledge and experience in the project team. In total 4 different waste management concepts were compared individually and in combinations. The four concepts evaluated were based on: direct disposal in the national geological repository; treatment of the waste for volume reduction and where applicable clearance in an external waste treatment facility; decontamination and clearance in an on-site waste treatment facility; direct disposal in a near surface repository at the NPP site. It was important to be able to compare the different options in a quantifiable way. Therefore the project team set up a matrix with parameters for the different options gained from the utility, the national waste management company, external vendors and the experience of the team. In this way a quantitative analysis could be done with the four different waste management options. In addition to the quantitative analysis the team summarised decades of experience in radioactive waste management and decommissioning recommendations and risk analyses. Special attention was given to risk mitigation and redundancy in the waste management chain. The development of an overall waste

  3. NOx trade. Case studies

    International Nuclear Information System (INIS)

    Jantzen, J.

    2002-01-01

    Some of the questions with respect to the trade of nitrogen oxides that businesses in the Netherlands have to deal with are dealt with: should a business buy or sell rights for NOx emission; which measures must be taken to reduce NOx emission; how much must be invested; and how to deal with uncertainties with regard to prices. Simulations were carried out with the MOSES model to find the answers to those questions. Results of some case studies are presented, focusing on the chemical sector in the Netherlands. Finally, the financial (dis)advantages of NOx trade and the related uncertainties for a single enterprise are discussed [nl

  4. OBSESSIONS: CASE REPORT STUDY

    Directory of Open Access Journals (Sweden)

    Miloš Židanik

    2004-01-01

    Full Text Available Background. Obsessions are one of the most refractory psychiatric disorders. The therapeutic guidelines include a psychopharmacotherapy and the use of behavioural and supportive psychotherapy.Methods. This case report study presents a patient with a homicide obsessions at the forefront and narcissistic personality disorder in background. The use of analytical oriented psychotherapy, which helped to resolve axis-1 symptoms, is described.Conclusions. In the therapy of patients it is important to have the knowledge about the national therapeutic guidelines and critical distance toward them as well. Which therapy to use should be decided by the individual patient’s needs.

  5. FAMS DECOMMISSIONING END-STATE ALTERNATIVE EVALUATION

    International Nuclear Information System (INIS)

    Grimm, B; Stephen Chostner, S; Brenda Green, B

    2006-01-01

    Nuclear Material Management (NMM) completed a comprehensive study at the request of the Department of Energy Savannah River Operations Office (DOE-SR) in 2004 (Reference 11.1). The study evaluated the feasibility of removal and/or mitigation of the Pu-238 source term in the F-Area Material Storage (FAMS) facility during on-going material storage operations. The study recommended different options to remove and/or mitigate the Pu-238 source term depending on its location within the facility. During April 2005, the Department of Energy (DOE) sent a letter of direction (LOD) to Washington Savannah River Company (WSRC) directing WSRC to implement a new program direction that would enable an accelerated shutdown and decommissioning of FAMS (Reference 11.2). Further direction in the LOD stated that effective December 1, 2006 the facility will be transitioned to begin deactivation and decommissioning (D and D) activities. To implement the LOD, Site D and D (SDD) and DOE agreed the planning end-state would be demolition of the FAMS structure to the building slab. SDD developed the D and D strategy, preliminary cost and schedule, and issued the deactivation project plan in December 2005 (Reference 11.3). Due to concerns and questions regarding the FAMS planning end-state and in support of the project's Critical Decision 1, an alternative study was performed to evaluate the various decommissioning end-states and the methods by which those end-states are achieved. This report documents the results of the alternative evaluation which was performed in a structured decision-making process as outlined in the E7 Manual, Procedure 2.15, ''Alternative Studies'' (Reference 11.4)

  6. Identification and evaluation of facilitation techniques for decommissioning light water power reactors

    International Nuclear Information System (INIS)

    LaGuardia, T.S.; Risley, J.F.

    1986-06-01

    This report describes a study sponsored by the US Nuclear Regulatory Commission to identify practical techniques to facilitate the decommissioning of nuclear power generating facilities. The objective of these ''facilitation techniques'' is to reduce the radioactive exposures and/or volumes of waste generated during the decommissioning process. The report presents the possible facilitation techniques identified during the study and discusses the corresponding facilitation of the decommissioning process. Techniques are categorized by their applicability of being implemented during the three stages of power reactor life: design/construction, operation, or decommissioning. Detailed cost-benefit analyses were performed for each technique to determine the anticipated exposure and/or radioactive waste reduction; the estimated costs for implementing each technique were then calculated. Finally, these techniques were ranked by their effectiveness in facilitating the decommissioning process. This study is a part of the Nuclear Regulatory Commission's evaluation of decommissioning policy and its modification of regulations pertaining to the decommissioning process. The findings can be used by the utilities in the planning and establishment of activities to ensure that all objectives of decommissioning will be achieved

  7. Nuclear decommissioning in Italy

    International Nuclear Information System (INIS)

    Tripputi, I.

    2005-01-01

    in the oil market, both in terms of barrel cost and in terms of security of supplies, and the severe black-outs that have plagued also Italy (the major one in September 2003 lasting in some areas for about 24 hours), have started a widespread discussion about energy alternatives and strategic energy plans. In this frame an increasing number of politicians and scientists are calling for a reconsideration of nuclear energy as a viable option also for Italy in a new energy mix. It is clear that public acceptance of nuclear energy is strictly connected not only to the demonstration of high safety standards of future plants, but also to the solution of radioactive waste disposal and of plant decommissioning. This is the link that could make the SOGIN mission even more strategic for the country

  8. National policies and regulations for decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    1993-07-01

    This report, though produced as a follow-up to Safety Series No. 105, The Regulatory Process for the Decommissioning of Nuclear Facilities, is not primarily intended as guidance. Rather, its objective is to provide an overview of national decommissioning policies and regulatory practices as part of the background knowledge which is an essential precondition for good decision making. It discusses the reasons for the similarities and differences in national approach using specific examples but without giving preference to any particular scheme; it aims rather to provide factual, general information on the choices that have been or are being made, and why. As many Member States are in a transient situation between the case-by-case approach to decommissioning and the establishment of national policies, strategies and regulations, this seems the right moment to assess existing national practices worldwide and that is the purpose for which the document is issued at this time. The information gathered in this report is based on submissions by Member States which have developed or are in the process of developing decommissioning oriented policies and regulations. 29 refs

  9. Ecological and political issues surrounding decommissioning of offshore oil facilities in the Southern California Bight

    Science.gov (United States)

    Schroeder, Donna M.; Love, Milton S.

    2004-01-01

    To aid legislators, resource managers, and the general public, this paper summarizes and clarifies some of the issues and options that the federal government and the state of California face in decommissioning offshore oil and gas production platforms, particularly as these relate to platform ecology. Both local marine ecology and political climate play a role in decommissioning offshore oil production platforms. Compared to the relatively supportive political climate in the Gulf of Mexico for “rigs-to-reefs” programs, conflicting social values among stakeholders in Southern California increases the need for understanding ecological impacts of various decommissioning alternatives (which range from total removal to allowing some or all of platform structure to remain in the ocean). Additional scientific needs in the decommissioning process include further assessment of platform habitat quality, estimation of regional impacts of decommissioning alternatives to marine populations, and determination of biological effects of any residual contaminants. The principal management need is a ranking of environmental priorities (e.g. species-of-interest and marine habitats). Because considerable numbers of economically important species reside near oil platforms, National Oceanic and Atmospheric Administration Fisheries should consider the consequences of decommissioning alternatives in their overall management plans. Management strategies could include designating reefed platforms as marine protected areas. The overarching conclusion from both ecological and political perspectives is that decommissioning decisions should be made on a case-by-case basis.

  10. Proven approaches to organise a large decommissioning project, including the management of local stakeholder interests

    International Nuclear Information System (INIS)

    Rodriguez, A.

    2005-01-01

    Full text: Spanish experience holds a relatively important position in the field of the decommissioning of nuclear and radioactive facilities. Decommissioning projects of uranium concentrate mill facilities are near completion; some old uranium mine sites have already been restored; several projects for the dismantling of various small research nuclear reactors and a few pilot plants are at various phases of the dismantling process, with some already completed. The most notable Spanish project in this field is undoubtedly the decommissioning of the Vandellos 1 nuclear power plant that is currently ready to enter a safe enclosure, or dormancy, period. The management of radioactive wastes in Spain is undertaken by 'Empresa Nacional de Residuos Radioactivos, S.A.' (ENRESA), the Spanish national radioactive waste company, constituted in 1984. ENRESA operates as a management company, whose role is to develop radioactive waste management programmes in accordance with the policy and strategy approved by the Spanish Government. Its responsibilities include the decommissioning and dismantling of nuclear installations. Decommissioning and dismantling nuclear installations is an increasingly important topic for governments, regulators, industries and civil society. There are many aspects that have to be carefully considered, planned and organised in many cases well in advance of when they really need to be implemented. The goal of this paper is describe proven approaches relevant to organizing and managing large decommissioning projects, in particular in the case of Vandellos-1 NPP decommissioning. (author)

  11. Technology, safety and costs of decommissioning nuclear reactors at multiple-reactor stations

    International Nuclear Information System (INIS)

    Wittenbrock, N.G.

    1982-01-01

    Safety and cost information is developed for the conceptual decommissioning of large (1175-MWe) pressurized water reactors (PWR) and large (1155-MWe) boiling water reactors (BWR) at multiple-reactor stations. Three decommissioning alternatives are studied: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). Safety and costs of decommissioning are estimated by determining the impact of probable features of multiple-reactor-station operation that are considered to be unavailable at a single-reactor station, and applying these estimated impacts to the decommissioning costs and radiation doses estimated in previous PWR and BWR decommissioning studies. The multiple-reactor-station features analyzed are: the use of interim onsite nuclear waste storage with later removal to an offsite waste disposal facility, the use of permanent onsite nuclear waste disposal, the dedication of the site to nuclear power generation, and the provision of centralized services

  12. Allocation of Decommissioning and Waste Liabilities

    International Nuclear Information System (INIS)

    Varley, Geoff

    2011-11-01

    The work demonstrates that there are a number of methods available for cost allocation, the pros and cons of which are examined. The study investigates potential proportional and incremental methods in some depth. A recommendation in principle to use the latter methodology is given. It is concluded that a 'fair assumption' is that the potential allocation of costs for 'the RMA Leaching Hall' probably is small, in relation to the total costs, and estimated to be not more than about 175 kSEK, plus any costs associated with decommissioning/ disposal of a number of small pieces of equipment added by the current operator

  13. Decontamination and decommissioning techniques for research reactors

    International Nuclear Information System (INIS)

    Oh, Won Zin; Won, H. J.; Jung, C. H.; Choi, W. K.; Kim, G. N.; Lee, K. W.

    2002-05-01

    Evaluation of soil decontamination process and the liquid decontamination waste treatment technology are investigation of organic acid as a decontamination agent, investigation of the liquid waste purification process and identification of recycling the decontamination agents. Participation on IAEA CRP meeting are preparation of IAEA technical report on 'studies on decommissioning of TRIGA reactors and site restoration technologies' and exchange the research result, technology, experience and safety regulation of the research reactor D and D of USA, Great Britain, Canada, Belgium, Italy, India and so forth

  14. Recovery of decommissioning and spent fuel charges

    International Nuclear Information System (INIS)

    Bermanis, G.

    1982-01-01

    The licensing and financial aspects of NPP decommissioning, deactivation and dismantling of radioactive equipment in the USA are considered. Data on the costs of spent fuel transport and conservation are given. The state of the problem development in other countries is briefly described. It is pointed out that the technical aspect of the problem is much better studied than that of license-financial problem. At the same time in contrast to TPP NPP use is connected with considerable expenses after the end of a power plant sevice time

  15. Nuclear Decommissioning R and D: a successful history that goes on. Evolution of R and D for nuclear decommissioning

    International Nuclear Information System (INIS)

    Laraia, Michele; )

    2017-01-01

    certain installations and individual systems, structures and components, and related techniques, have been published in the 1990's and 2000's. These reports include, among others, the achievements of several Coordinated Research Projects in a row where 10-15 organizations active in nuclear decommissioning shared a common theme and periodically reported on their progress at Research Coordination Meetings. While the writer does not expect significant breakthroughs in decommissioning technology in the foreseeable future, a new impetus to R and D has been given by the Fukushima accident. Due to the complexity of Fukushima circumstances, this is one case where the available technology may not be equal to the challenges that lie ahead and significant technological progress is needed to move on. It is possible that innovative technologies stemming from Fukushima will boost a staggering change in decommissioning. For example, a fleet of robots could carry out decommissioning instead of humans: but we are not yet there. (author)

  16. Research reactor decommissioning experience - concrete removal and disposal -

    International Nuclear Information System (INIS)

    Manning, Mark R.; Gardner, Frederick W.

    1990-01-01

    Removal and disposal of neutron activated concrete from biological shields is the most significant operational task associated with research reactor decommissioning. During the period of 1985 thru 1989 Chem-Nuclear Systems, Inc. was the prime contractor for complete dismantlement and decommissioning of the Northrop TRIGA Mark F, the Virginia Tech Argonaut, and the Michigan State University TRIGA Mark I Reactor Facilities. This paper discusses operational requirements, methods employed, and results of the concrete removal, packaging, transport and disposal operations for these (3) research reactor decommissioning projects. Methods employed for each are compared. Disposal of concrete above and below regulatory release limits for unrestricted use are discussed. This study concludes that activated reactor biological shield concrete can be safely removed and buried under current regulations

  17. Basic Research on Selecting ISDC Activity for Decommissioning Costing in KRR-2 Decommissioning Project Experience Data

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Hee-Seong; Jin, Hyung-Gon; Park, Seung-Kook [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    KAERI is performing research for calculation of expected time of a decommissioning work and evaluation of decommissioning cost and this research calculate a decommissioning work unit productivity based on the experience data of decommissioning activity for KRR-2. The KAERI be used to calculate the decommissioning cost and manage the experience data from the decommissioning activity through the Decommissioning Information Management System (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), and Decommissioning Work-unit Productivity Calculation System (DEWOCS). In this paper, the methodology was presented how select the ISDC activities in dismantling work procedures of a 'removal of radioactive concrete'. The reason to select the 'removal of radioactive concrete' is main key activity and generates the amount of radioactive waste. This data will take advantage of the cost estimation after the code for the selected items derived ISDC. There are various efforts for decommissioning costing in each country. In particular, OECD/NEA recommends decommissioning cost estimation using the ISDC and IAEA provides for Cost Estimation for Research Reactors in Excel (CERREX) program that anyone is easy to use the cost evaluation from a limited decommissioning experience in domestic. In the future, for the decommissioning cost evaluation, the ISDC will be used more widely in a strong position. This paper has described a method for selecting the ISDC item from the actual dismantling work procedures.

  18. An Applied Study on the Decontamination and Decommissioning of Hot Cell Facilities in the United States and Comparison with the Studsvik Facility for Solid and Liquid Waste

    International Nuclear Information System (INIS)

    Varley, Geoff; Rusch, Chris

    2006-07-01

    This report presents the plans, processes and results of the decontamination and decommissioning of the Hot Cell Facility in Building 23 at the General Atomics Torrey Pines Mesa Facility (HCF) and compares the program and cost of decommissioning HCF with the Swedish cost estimate for decontamination and decommissioning of the HM hot cell and wastes treatment facility at Studsvik in Sweden. The HCF had three main hot cells and was licensed to: Receive, handle and ship radioactive materials; Remotely handle, examine and store irradiated fuel materials; Extract tritium (engineering scale); Support new reactor production development; Develop, fabricate and inspect UO 2 - BeO fuel materials. The HM facility in Studsvik was constructed to handle and package medium-active solid and liquid wastes, prior to disposal. Central to the facility is a conventional hot cell including three work stations, serviced by master slave manipulators. Other parts of the facility include holding tanks for liquid wastes and slurries, a centrifuge room, as well as an encapsulation station where drummed wastes can be encapsulated in cement, offices, laboratories and workshops and so on, as well as building and cell ventilation systems. Decontamination and decommissioning of the HCF took place during 1993 through 2001. The objective was to obtain regulatory release of the site so that it could be used on an unrestricted basis. Based on data from extensive hazardous and radiological materials characterization, GA evaluated four decommissioning options and selected dismantling as the only option that would satisfy the decommissioning objective. The decontamination and decommissioning scope included the following actions. 1. Remove the legacy waste that consisted of radioactive wastes stored at the HCF consisting of 21,434 kg of irradiated fuel material (IFM) that was owned by the US DoE and store the waste in temporary storage set up at the GA site. 2. Actual Decontamination and Dismantlement

  19. An Applied Study on the Decontamination and Decommissioning of Hot Cell Facilities in the United States and Comparison with the Studsvik Facility for Solid and Liquid Waste

    Energy Technology Data Exchange (ETDEWEB)

    Varley, Geoff; Rusch, Chris [NAC International, Atlanta, GA (United States)

    2006-07-15

    This report presents the plans, processes and results of the decontamination and decommissioning of the Hot Cell Facility in Building 23 at the General Atomics Torrey Pines Mesa Facility (HCF) and compares the program and cost of decommissioning HCF with the Swedish cost estimate for decontamination and decommissioning of the HM hot cell and wastes treatment facility at Studsvik in Sweden. The HCF had three main hot cells and was licensed to: Receive, handle and ship radioactive materials; Remotely handle, examine and store irradiated fuel materials; Extract tritium (engineering scale); Support new reactor production development; Develop, fabricate and inspect UO{sub 2} - BeO fuel materials. The HM facility in Studsvik was constructed to handle and package medium-active solid and liquid wastes, prior to disposal. Central to the facility is a conventional hot cell including three work stations, serviced by master slave manipulators. Other parts of the facility include holding tanks for liquid wastes and slurries, a centrifuge room, as well as an encapsulation station where drummed wastes can be encapsulated in cement, offices, laboratories and workshops and so on, as well as building and cell ventilation systems. Decontamination and decommissioning of the HCF took place during 1993 through 2001. The objective was to obtain regulatory release of the site so that it could be used on an unrestricted basis. Based on data from extensive hazardous and radiological materials characterization, GA evaluated four decommissioning options and selected dismantling as the only option that would satisfy the decommissioning objective. The decontamination and decommissioning scope included the following actions. 1. Remove the legacy waste that consisted of radioactive wastes stored at the HCF consisting of 21,434 kg of irradiated fuel material (IFM) that was owned by the US DoE and store the waste in temporary storage set up at the GA site. 2. Actual Decontamination and

  20. Feedback from the decommissioning of two accelerators

    International Nuclear Information System (INIS)

    Aubert, M-C; Damoy, F.; Joly, J-M

    2003-01-01

    Saclay Linear Accelerator (ALS) and Saturne synchrotron, both well known as international research instruments, have definitively stopped operating in 1990 and 1997 respectively. The French Atomic Energy Commission (CEA) has decided proceeding with the appropriate actions in order to dismantle these two nuclear installations (NIs) known as INB 43 (ALS) and INB 48 (Saturne). The SDA (Accelerator Decommissioning Division) was created to be in charge of the dismantling procedure of the above NIs under the following conditions: - to maintain within the team a few employees from the previous exploitation of two NIs, in order not to loose the details and history of accelerator operation; - to import the necessary skills for a good management of dismantling operation such as waste management, ANDRA rules, project AMEC34omelt.com. Learn more about GeoMelt ats-gssr410nuclear safety, radiation protection, ALARA concepts, etc. Presently the dismantling operations are well under way at INB 43 and nearly finished at INB 48. The project organisation established by SDA has allowed meeting both the schedule and cost requirements of the decommissioning. At the beginning, major decommissioning safety characteristics of large research instruments will be presented and dismantling aspects in particular. Afterwards, the organization of both projects will be detailed, emphasizing their statutory aspects (e.g., safety documents, zoning, traceability, etc.) and technical difficulties. Waste characterisation as well as the choice of evacuation paths for each category of the waste will then be described in detail for both accelerators. A number of difficulties met during these procedures will be analysed and proposals will be made in order to improve the statutory framework in particular, both on technical and nuclear safety aspects. The application of the above experience to the dismantling of two fuel cycle installations, namely the research nuclear reactors, is presently under study

  1. Status of the support researches for the regulation of nuclear facilities decommissioning in Japan

    International Nuclear Information System (INIS)

    Masuda, Yusuke; Iguchi, Yukihiro; Kawasaki, Satoru; Kato, Masami

    2011-01-01

    In Japan, 4 nuclear power stations are under decommissioning and some nuclear fuel cycle facilities are expected to be decommissioned in the future. On the other hand, the safety regulation of decommissioning of nuclear facilities was changed by amending act in 2005. An approval system after review process of decommissioning plan was adopted and applied to the power stations above. In this situation, based on the experiences of the new regulatory system, the system should be well established and moreover, it should be improved and enhanced in the future. Nuclear Industry and Safety Agency (NISA) is in charge of regulation of commercial nuclear facilities in Japan and decommissioning of them is included. Japan Nuclear Energy Safety Organization (JNES) is in charge of technical supports for NISA as a TSO (Technical Support Organization) also in this field. As for decommissioning, based on regulatory needs, JNES has been continuing research activities from October 2003, when JNES has been established. Considering the 'Prioritized Nuclear Safety Research Plan (August 2009)' of the Nuclear Safety Commission of Japan and the situation of operators facilities, 'Regulatory Support Research Plan between FY 2010-2014' was established in November 2009, which shows the present regulatory needs and a research program. This program consists of researches for 1. review process of decommissioning plan of power reactors, 2. review process of decommissioning plan of nuclear fuel cycle facilities, 3. termination of license at the end of decommissioning and 4. management of decommissioning waste. For the item 1, JNES studied safety assessment methods of dismantling, e.g. obtaining data and analysis of behavior of dust diffusion and risk assessment during decommissioning, which are useful findings for the review process. For the item 2, safety requirements for the decommissioning of nuclear fuel cycle facilities was compiled, which will be used in the future review. For the item 3

  2. Study on the identification of the national research and development needs for nuclear decontamination and decommissioning in Korea

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Hwa Sup; Song, Ki Dong; Oh, Won Zin; Oh, Keun Bae; Jung, Ki jung; Yang, Mang Ho; Kim, Cheol Jung; Lee, Han Myung; Kwack, Kim Ku; Moon, Kee Hwan; Choi, Wan Kyu; Kim, Hyun Jun; Jung, Jong Hun; Kim, Seung Su; Lee, Yong Bum; Cheong, Hwan Sam; Cheong, Un Soo; Lim, Chae Young; Park, Seong Kuk [Korea Atomic Energy Research Institute, Taejeon (Korea)

    2000-03-01

    The major contents in this study are as follows: This study investigated and analyzed the current status of foreign and domestic D and D technology. For the domestic technology, the contents of and output from the projects for D and D technology development conducted so far in Korea were investigated and analyzed. For the foreign technology, the status of current D and D technology and D and D projects in the U.S., European countries, Japan, and others were investigated. Especially, some investigation and discussion on technical cooperation were made by visiting the Republic of Ukraine and France. This study discuss the appropriateness of establishing a national strategy for D and D technology development with viewpoints of technical capability, timing, and social and economic acceptability. Based on the discussion, this study set up three alternative strategies and then, suggested 'stepwise D and D technology development strategy' as the most desirable alternative in Korea. The final goal for the strategy and the intermediate goals for each stage were established. Then, attempts were made to suggest appropriate projects to be conducted in order to achieve those goals and their prioritie. 2 figs., 9 tabs. (Author)

  3. Needs for R and D and innovations to address challenges of nuclear facility decommissioning after its normal shutdown versus advanced approaches required for Fukushima Daiichi NPS decommissioning. Needs and emergency technologies for decommissioning

    International Nuclear Information System (INIS)

    Laurent, G.

    2017-01-01

    Taking into account several attempts to address variety of needs for R and D related to the decommissioning challenges such as: - Characterisation and survey prior to dismantling, - Technologies for dismantling, - Decontamination and on-site remediation, - Material and waste management, - Site characterisation and environmental monitoring. This presentation will give an update of approaches in several countries for R and D to aim at more efficient and effective decommissioning and, above all, to reduce current labour intensive needs to implement this kind of work. The evidence of the particular needs to coordinate efforts both for 'normal decommissioning' and accident cases like Fukushima Daiichi will be offered by demonstrating that, for a large part, that needs might be considered as similar. Some examples of particular interest will be given and it will be emphasized the need to adapt existing and/or new technologies from 'non-nuclear' areas to use them for nuclear decommissioning. The global interest to evaluate and to coordinate R and D efforts will be demonstrated. Consequently there might be a large international interest to increase the consensus where R and D can be better directed. The more comprehensive coordination should support improvement of the overview of future decommissioning needs to implement the decommissioning activities more effectively in terms of time and finance, not compromising safety. (author)

  4. Roadmap and performance carried out during Ciemat site decommissioning

    International Nuclear Information System (INIS)

    Quinones, Javier; Diaz Diaz, Jose Luis

    2005-01-01

    Ciemat (Research Centre for Energy, Environment and Technology) located in the heart of the Ciudad Universitaria of Madrid, occupies a property of 20 Ha. Since its creation in 1951 as JEN, and in 1986 renowned as Ciemat, it has involved on R and D projects in the field of Energy and Environment, i.e., Nuclear Fission, Nuclear Fusion, Fossils Fuels, Renewable Energy. As a consequence of the R and D projects developed between 1951 - 1986 on Nuclear Fission field (fuel design, fabrication, characterization on irradiated fuels, safety studies, etc) and to the diversification of the goals as well, it is necessary to Decommissioning and Dismantling (D and D) from nuclear facilities (nuclear reactor, Hot Cells, Irradiation facility), buildings and soils. Preparations for D and D included a staged shutdown of operations, planning documentation and licensing for decommissioning. As a prerequisite to Ciemat application for a decommissioning license and nuclear environmental assessment was carried out according to Spanish Nuclear Council (CSN) and approval of the site decommissioning project was obtained in 2000 and valid until December 31, 2006. Since 2001 - 2003 is underway and focussed on the radiological characterization of the site (divided in pieces of ground), when each piece of ground is characterized a planning for D and D is presented to CSN in order to obtain a license for actuation. Nowadays several pieces of ground are decontaminated and modifications have been done in order to achieve a safe state of storage-with-surveillance. Later phases have planned waste management improvements for selected wastes already on temporally storage, eventually followed by final decommissioning of facilities and buildings and cleaning of contaminants from soils and removal of waste from the site. This paper describes the planning, nuclear and environment assessment and descriptions of decommissioning activities currently underway at Ciemat. (Author)

  5. Technology, safety, and costs of decommissioning reference nuclear research and test reactors: sensitivity of decommissioning radiation exposure and costs to selected parameters

    International Nuclear Information System (INIS)

    Konzek, G.J.

    1983-07-01

    Additional analyses of decommissioning at the reference research and test (R and T) reactors and analyses of five recent reactor decommissionings are made that examine some parameters not covered in the initial study report (NUREG/CR-1756). The parameters examined for decommissioning are: (1) the effect on costs and radiation exposure of plant size and/or type; (2) the effects on costs of increasing disposal charges and of unavailability of waste disposal capacity at licensed waste disposal facilities; and (3) the costs of and the available alternatives for the disposal of nuclear R and T reactor fuel assemblies

  6. Decommissioning of Salaspils Research Reactor

    International Nuclear Information System (INIS)

    Abramenkovs, A.; Popelis, A.; Abramenkova, G

    2008-01-01

    The Salaspils Research Reactor (SRR) is out of operation since July 1998 and the decommissioning of SRR was started in 1999 according to the decision of the Government of Latvia. The main decommissioning activities up to 2006 were connected with collecting and conditioning of historical radioactive wastes from different storages outside and inside of reactor hall. The total amount of dismantled materials was about 700 tons, more than 77 tons were conditioned in concrete containers for disposal in repository. The radioactive wastes management technology is discussed in the paper. It was found, that additional efforts must be spent for immobilization of radionuclides in cemented matrix to be comply with the wastes acceptance criteria. The investigations of mechanical stability of water-cement matrix are described and discussed in the paper

  7. Nuclear power plants life extension and decommissioning its economic aspects

    International Nuclear Information System (INIS)

    Watanabe, Yoshiaki

    1994-06-01

    In USA where the development of nuclear power was started early, the life of nuclear power plants expires successively around the turn of century, and the serious hindrance to electric power supply is feared. Therefore, the research for extending 40 year approved period of operation is in progress. By the extension of life of nuclear power plants, huge cost reduction is estimated as compared with the construction of new plants. However, due to the rise of the cost for the life extension, there were the cases of forced decommissioning. In this book, the present state of the life extension of nuclear power stations, the economical assessment and analysis of the life extension by DOE, the economical assessment by MIDAS method of Electric Power Research Institute, the economical assessment by cost-benefit method of Northern States Power Co., the assessment of the long term operation possibility of nuclear power stations, the economical assessment system for the life extension in Japan, the present state of the decommissioning of nuclear power stations and that in USA, Canada and Europe, the assessment of the decommissioning cost by OECD/NEA, and the decommissioning cost for thermal power stations are described. (K.I.)

  8. Worldwide Overview of Lessons Learned from Decommissioning Projects

    International Nuclear Information System (INIS)

    Laraia, Michele

    2008-01-01

    With an increasing number of radioactive facilities and reactors now reaching the end of their useful life and being taken out of service, there is a growing emphasis worldwide on the safe and efficient decommissioning of such plants. There is a wealth of experience already gained in decommissioning projects for all kinds of nuclear facilities. It is now possible to compare and discuss progress and accomplishments worldwide. In particular, rather than on the factual descriptions of projects, technologies and case histories, it is important to focus on lessons learned: in this way, the return of experience is felt to effectively contribute to progress. Key issues - inevitably based on a subjective ranking - are presented in this paper. Through the exchange of lessons learned, it is possible to achieve full awareness of the need for resources for and constraints of safe and cost-effective decommissioning. What remains now is the identification of specific, remaining issues that may hinder or delay the smooth progress of decommissioning. To this end, lessons learned provide the necessary background information; this paper tries to make extensive use of practical experience gained by the international community

  9. EPRI Guidance for Transition from Operations to Decommissioning

    International Nuclear Information System (INIS)

    McGrath, Richard; Reid, Richard; Snyder, Michael

    2016-01-01

    A wide range of key activities are necessary after permanent shutdown of a nuclear power plant before active dismantlement of the plant can begin. This period is typically referred to as the transition period. In some cases these activities are prescribed by regulation and in others they may be more practically driven or even optional. In either case, planning for transition activities should optimally take place prior to final shutdown. Additionally, execution of some transition period activities, such as filing required regulatory submittals, may be performed prior to plant shut down. In addition to general transition period activities such as defueling, management of operational wastes, fulfilling regulatory requirements and changes to plant technical specifications, there are a number of optional activities that may have a long-range impact on future decommissioning activities. This includes activities such as the timing of staff reductions and performance of chemical decontamination. EPRI is nearing completion of a project to develop guidance for transitioning a nuclear power plant to decommissioning. This project includes the following elements: - A review of required and recommended transition period activities. For countries where a clear regulatory framework exists, this includes country-specific requirements; - A review of pending regulatory activities in the US and other countries where there is currently no clear regulatory framework for transitioning to decommissioning; - A summary of activities that have been performed during the transition period for past and current decommissioning sites, as well as current sites that are actively planning decommissioning activities; and - Guidance for development of a transition plan for changing from an operational to decommissioning status. Informed planning of the transition period activities will provide immediate benefits in reducing costs and minimizing the duration of the transition period, as well as longer

  10. Project No. 8 - Final decommissioning plan

    International Nuclear Information System (INIS)

    2000-01-01

    Ignalina NPP should prepare the final Ignalina NPP unit 1 decommissioning plan by march 31, 2002. This plan should include the following : description of Ignalina NPP and the Ignalina NPP boundary that could be influenced by decommissioning process; decommissioning strategy selected and a logical substantiation for this selection; description of the decommissioning actions suggested and a time schedule for the actions to be performed; conceptual safety and environmental impact assessment covering ionizing radiation and other man and environment impact; description of the environmental monitoring program proposed during decommissioning process; description of the waste management proposed; assessment of decommissioning expenses including waste management, accumulated funds and other sources. Estimated project cost - 0.75 M EURO

  11. Fort St. Vrain defueling ampersand decommissioning considerations

    International Nuclear Information System (INIS)

    Warembourg, D.

    1994-01-01

    Fort St. Vrain Nuclear Generating Station (FSV) is one of the first commercial reactors to be decommissioned under NRC's decommissioning rule. The defueling and decommissioning of this 330 MWe High Temperature Gas Cooled Reactor (HTGR) has involved many challenges for Public Service Company of Colorado (PSC) including defueling to an Independent Spent Fuel Storage Installation (ISFSI), establishing decommissioning funding, obtaining regulatory approvals, arranging for waste disposal, and managing a large fixed price decommissioning contract. In 1990, a team comprised of the Westinghouse Corporation and Morrison Knudsen Corporation, with the Scientific Ecology Group as a major subcontractor, was contracted by PSC to perform the decommissioning under a fixed price contract. Physical work activities began in August 1992. Currently, physical dismantlement activities are about 45% complete, the project is on schedule, and is within budget

  12. IDMT, Integrated Decommissioning Management Tools

    International Nuclear Information System (INIS)

    Alemberti, A.; Castagna, P.; Marsiletti, M.; Orlandi, S.; Perasso, L.; Susco, M.

    2005-01-01

    Nuclear Power Plant decommissioning requires a number of demolition activities related to civil works and systems as well as the construction of temporary facilities used for treatment and conditioning of the dismantled parts. The presence of a radiological, potentially hazardous, environment due to the specific configuration and history of the plant require a professional, expert and qualified approach approved by the national safety authority. Dismantling activities must be designed, planned and analysed in detail during an evaluation phase taking into account different scenarios generated by possible dismantling sequences and specific waste treatments to be implemented. The optimisation process of the activities becomes very challenging taking into account the requirement of the minimisation of the radiological impact on exposed workers and people during normal and accident conditions. While remote operated equipment, waste treatment and conditioning facilities may be designed taking into account this primary goal also a centralised management system and corresponding software tools have to be designed and operated in order to guarantee the fulfilment of the imposed limits as well as the traceability of wastes. Ansaldo Nuclear Division has been strongly involved in the development of a qualified and certified software environment to manage the most critical activities of a decommissioning project. The IDMT system (Integrated Decommissioning Management Tools) provide a set of stand alone user friendly applications able to work in an integrated configuration to guarantee waste identification, traceability during treatment and conditioning process as well as location and identification at the Final Repository site. Additionally, the system can be used to identify, analyse and compare different specific operating scenarios to be optimised in term of both economical and radiological considerations. The paper provides an overview of the different phases of

  13. Goiania incident case study

    International Nuclear Information System (INIS)

    Petterson, J.S.

    1988-06-01

    The reasons for wanting to document this case study and present the findings are simple. According to USDOE technical risk assessments (and our own initial work on the Hanford socioeconomic study), the likelihood of a major accident involving exposure to radioactive materials in the process of site characterization, construction, operation, and closure of a high-level waste repository is extremely remote. Most would agree, however, that there is a relatively high probability that a minor accident involving radiological contamination will occur sometime during the lifetime of the repository -- for example, during transport, at an MRS site or at the permanent site itself during repacking and deposition. Thus, one of the major concerns of the Yucca Mountain Socioeconomic Study is the potential impact of a relatively minor radiation-related accident. A large number of potential impact of a relatively minor radiation-related accident. A large number of potential accident scenarios have been under consideration (such as a transportation or other surface accident which results in a significant decline in tourism, the number of conventions, or the selection of Nevada as a retirement residence). The results of the work in Goiania make it clear, however, that such a significant shift in established social patterns and trends is not likely to occur as a direct outcome of a single nuclear-related accident (even, perhaps, a relatively major one), but rather, are likely to occur as a result of the enduring social interpretations of such an accident -- that is, as a result of the process of understanding, communicating, and socially sustaining a particular set of associations with respect to the initial incident

  14. FMCT verification: Case studies

    International Nuclear Information System (INIS)

    Hui Zhang

    2001-01-01

    Full text: How to manage the trade-off between the need for transparency and the concern about the disclosure of sensitive information would be a key issue during the negotiations of FMCT verification provision. This paper will explore the general concerns on FMCT verification; and demonstrate what verification measures might be applied to those reprocessing and enrichment plants. A primary goal of an FMCT will be to have the five declared nuclear weapon states and the three that operate unsafeguarded nuclear facilities become parties. One focus in negotiating the FMCT will be verification. Appropriate verification measures should be applied in each case. Most importantly, FMCT verification would focus, in the first instance, on these states' fissile material production facilities. After the FMCT enters into force, all these facilities should be declared. Some would continue operating to produce civil nuclear power or to produce fissile material for non- explosive military uses. The verification measures necessary for these operating facilities would be essentially IAEA safeguards, as currently being applied to non-nuclear weapon states under the NPT. However, some production facilities would be declared and shut down. Thus, one important task of the FMCT verifications will be to confirm the status of these closed facilities. As case studies, this paper will focus on the verification of those shutdown facilities. The FMCT verification system for former military facilities would have to differ in some ways from traditional IAEA safeguards. For example, there could be concerns about the potential loss of sensitive information at these facilities or at collocated facilities. Eventually, some safeguards measures such as environmental sampling might be seen as too intrusive. Thus, effective but less intrusive verification measures may be needed. Some sensitive nuclear facilities would be subject for the first time to international inspections, which could raise concerns

  15. Decommissioning program of JRR-2

    International Nuclear Information System (INIS)

    Kishimoto, Katsumi; Banba, Masao; Arigane, Kenji

    1999-01-01

    Japan Research Reactor No.2(JRR-2), heavy water moderated and cooled tank type research reactor with maximum thermal power of 10 MW, was used over 36 years, and was permanently shut down in December, 1996. Afterward, dismantling report was submitted to the STA, and dismantling was begun in 1997. Decommissioning of JRR-2 is planned in 11 years from 1997 to 2007, and the program is divided into 4 phases. Phase 1 had already been ended, phase 2 is being executed at present. Reactor body will be removed in phase 4 by one piece removal or caisson techniques. On reactor building, it is planned to use effectively as a hot experimental facilities after decommissioning ends. How to treat heavy water and primary cooling system contaminated by tritium becomes an important problem to lead decommissioning to success because JRR-2 is heavy water reactor. On heavy water, transportation to foreign country is planned in phase 2. On primary cooling system, it is planned to remove and dispose the majority in phase 3, and tritium decontamination with technique established by the proof test is planned before them. As a preparation for them, various investigation and examination are being advanced at present. (author)

  16. Decommissioning: a United Kingdom perspective

    International Nuclear Information System (INIS)

    Haworth, A.; Reed, D.L.; Bleeze, A.

    1995-01-01

    The paper considers the United Kingdom legislative framework relevant to decommissioning of facilities on nuclear licensed sites. It describes the various legislative bodies involved in regulating this activity and the inspectorate concerned. The licensing regime is described in some detail highlighting the UK arrangements whereby a license is granted for the site upon which nuclear facilities are planned or exist. The license remains in place throughout the life of the plant on the site: from initial planning through to the end of decommissioning. A site (of part of) is not de-licensed until it can be stated that there has ceased to be any danger from ionising radiations from anything on the site (or appropriate part of the site). The final part of the paper considers the changes arising from the commercialization of the nuclear power industry in UK and the restatement of the Nuclear Installation Inspectorate's policy on decommissioning which has arisen as a result of a review made in response to these changes. (author)

  17. Planning For Armenian NPP Decommissioning

    International Nuclear Information System (INIS)

    Ghazaryan, K.; Atoyan, V.; Pyuskyulyan, K.

    2008-01-01

    Armenian Nuclear Power Plant (ANPP) is situated in Ararat valley near the Metzamor town, approximately 30 km west of Yerevan. The plant consists of two units of WWER-440 Model V-270 that is seismically upgraded version of standard V-230 design. The two units were put in commercial operation in 1976 and 1980 respectively. An earthquake in northern Armenia occurred in December 1988. Although both plants continued to operate after the earthquake, the USSR Council of Ministers ordered the shutdown of both plants for safety reasons. Unit 1 was shutdown in February 1989; Unit 2 was shutdown in March 1989. Shortly after Armenia became an independent republic, the ''energy crisis'' began, leaving the country with virtually no power for five years. The Armenian Government ordered the restart of Unit 2 ANPP. Unit 2 was restarted in November 1995. Unit 1 remains in a long-term shutdown mode. Currently nuclear share in total electricity generation is about 45%. The design life of Unit 2 expires in 2016. As with many older reactors throughout the world the decommissioning issues had not been considered for ANPP at the design stage. The planning activities for ANPP decommissioning were started in 2002 taking into account the IAEA recommendations that early planning will facilitate future decommissioning activities, and the complexity of preparatory and D and D activities as well. (author)

  18. Experience of TTR-1 decommissioning

    International Nuclear Information System (INIS)

    Kato, Hiroaki; Nobuoka, Yoshishige; Yoshimura, Yukio; Homma, Hitoshi; Nakai, Masaru

    2005-01-01

    Toshiba Training Reactor-1 (TTR-1) was planned for improvement of technical level from the standpoint of nuclear reactor manufacturer, training of a nuclear engineer, and research of nuclear physics, radiochemistry, radiation shielding and others. TTR-1 was permitted for construction in May 1960, attained at the first criticality in March 1962 and has continued to operate over 40 years. TTR-1 was permanently shut down in March 2001, accomplishing the planned target. From the initial criticality to the shut down, total operating time amounts to 15,300 hours and 31 MWds. Decommissioning plan was submitted to the Ministry of Education, Culture, Sports, Science and Technology on August 8, 2001 and dismantling work was started. The spent fuel was transported outside the laboratory, and the first phase and the second phase dismantling work were completed at the end of February 2004. Some of the reactor equipments continue maintaining their performance, and waste materials generated from dismantling work are under the state of managed storage, until disposal of the dismantling radioactive waste becomes clear, when the third phase of dismantling work will be started. At the end of the third phase work, all the TTR-1 equipments are dismantled and all waste materials are removed from TTR-1, then decommissioning of TTR-1 is completed. The outline of the decommissioning plan, the actually performed dismantling work, and spent fuel transportation work is briefly described. (author)

  19. Decommissioning of naval nuclear ships

    International Nuclear Information System (INIS)

    Oelgaard, P.L.

    1993-10-01

    During the next decade the two major nuclear powers will each have to decommission more than 100 naval nuclear vessels, in particular submarines. The problems connected with this task is considered in this report. Firstly the size of the task is considered, i.e. the number of nuclear vessels that has to be decommissioned. Secondly the reactors of these vessels, their fuel elements, their power level, the number of reactors per vessel and the amount of radioactivity to be handled are discussed. Thirdly the decommissioning procedures, i.e. The removal of fuel from the vessels, the temporary storage of the reactor fuel near the base, and the cleaning and disposal of the reactor and the primary circuit components are reviewed. Finally alternative uses of the newer submarines are briefly considered. It should be emphasizes that much of the detailed information on which this report is based, may be of dubious nature, and that may to some extent affect the validity of the conclusions of the report. (au)

  20. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1988-01-01

    US Department of Energy (DOE) Shippingport Station Decommissioning Project (SSDP) decommissioned, decontaminated, and dismantled the world's first, nuclear fueled, commercial size, electric power plant. SSDP programmatic goal direction for technology transfer is documentation of project management and operations experience. Objective is to provide future nuclear facility decommissioning projects with pertinent SSDP performance data for project assessment, planning, and operational implementation. This paper presents a working definition for technology transfer. Direction is provided for access and availability for SSDP technology acquisition

  1. Decommissioning high-level waste surface facilities

    International Nuclear Information System (INIS)

    1978-04-01

    The protective storage, entombment and dismantlement options of decommissioning a High-Level Waste Surface Facility (HLWSF) was investigated. A reference conceptual design for the facility was developed based on the designs of similar facilities. State-of-the-art decommissioning technologies were identified. Program plans and cost estimates for decommissioning the reference conceptual designs were developed. Good engineering design concepts were on the basis of this work identified

  2. Shippingport Station Decommissioning Project: overview and justification

    International Nuclear Information System (INIS)

    Coffman, F.E.

    1984-01-01

    The purpose of this booklet is to brief the reader on the Shippingport Station Decommissioning Project and to summarize the benefits of funding the project in FY 1984. Background information on the station and the decommissioning project is provided in this section of the booklet; the need for a reactor decommissining demonstration is discussed in the next section; and a summary of how the Shippingport Station Decommissioning Project (SSDP) provides the needed demonstration is provided in the final section

  3. Technology, safety and costs of decommissioning a Reference Boiling Water Reactor Power Station. Main report. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWe.

  4. Planning and management for reactor decommissioning

    International Nuclear Information System (INIS)

    Miyasaka, Yasuhiko

    2001-01-01

    This report describes decommissioning strategy, planning process, regulation, management and organization, radiological characterization and safety. Planning is used to identify, define and organize the requirements for decommissioning including decommissioning options, items to be accomplished (objective, scope), to solve problems of how it is to be accomplished (methods, means and procedures), questions of who will execute it (resources, organization and responsibilities, interfacing), and time when it will be executed (schedule for meeting the objectives). A plan is highly dependent on the quality of the management team assembled to carry it out. Radiological characterization involves a survey of existing data, calculation, in situ measurements and/or sampling and analyses. Using this databases decommissioning planner may assess options, considering: decontamination processes, dismantling procedures, tools required, radiological protection of workers and public/environment, waste classification, and resulting costs. Comparison and optimization of these factors will lead to selection of a decommissioning strategy, i.e. typically, immediate or deferred dismantling. The planning and implementation of decommissioning for nuclear reactors should be referred both recent dismantling techniques and many decommissioning experiences. The technical lessons learned from many projects will help in the planning for future decommissioning projects. And systematic planning and management are essential to successful completion of a decommissioning project. (author)

  5. The waste management implications of decommissioning

    International Nuclear Information System (INIS)

    Passant, F.H.

    1988-01-01

    Decommissioning policy can only be framed in the light of radioactive waste management policy. What can be done with the waste materials, how and when, will determine the overall decommissioning plans and costs. In this paper the waste management options and their costs are reviewed for the decommissioning of the Central Electricity Generating Boards civil nuclear power stations. The paper concentrates on the decommissioning of Magnox stations, although comparative information on waste volumes and costs are given for the AGR programme and a typical PWR. (author)

  6. Prospective needs for decommissioning commercial nuclear facilities

    International Nuclear Information System (INIS)

    Stevens, G.H.; Yasui, M.; Laraia, M.

    1992-01-01

    The answers to the questions: How many reactors will face the end of their operating lifetime over the next few decades? To what extent are the issues of decommissioning urgent? The answers will lead us to those issues that should be tackled now in order to complete smoothly the decommissioning of commercial nuclear power plants. The prospective needs for decommissioning of nuclear power plants are illustrated from the viewpoint of reactor age, and some of the issues to be tackled, in particular by governments, in this century are discussed, to prepare for the future decommissioning activities. (author) 18 refs.; 2 figs.; 2 tabs

  7. Human resource development for management of decommissioning

    International Nuclear Information System (INIS)

    Tanaka, Kenichi

    2017-01-01

    This paper described the contents of 'Human resource development for the planning and implementation of safe and reasonable nuclear power plant decommissioning' as the nuclear human resource development project by the Ministry of Education, Culture, Sports, Science and Technology. The decommissioning of a nuclear power plant takes 30 to 40 years for its implementation, costing tens of billions of yen. As the period of decommissioning is almost the same as the operation period, it is necessary to provide a systematic and continuous supply of engineers who understand the essence of the decommissioning project. The engineers required here should have project management ability to take charge of preparation, implementation, and termination of decommissioning, and have the ability to perform not only technology, but also factor management, cost management, and the like. As the preconditions of these abilities, it is important to develop human resources who possess qualities that can oversee decommissioning in the future. The contents of human resource education are as follows; (1) desk training (teaching materials: facilities of nuclear power plants, management of nuclear fuels, related laws, decommissioning work, decontamination, dismantling, disposal of waste, etc.), (2) field training (simulators, inspection of power station under decommissioning, etc.), (3) practical training (radiation inventory evaluation, and safety assessment), and (4) inspection of overseas decommissioning, etc. (A.O.)

  8. Status of the Fort St. Vrain decommissioning

    International Nuclear Information System (INIS)

    Fisher, M.J.

    1990-01-01

    Fort St. Vrain is a high temperature gas cooled reactor. It has been shut down as a result of financial and technical difficulties. Fort St. Vrain has been planning for defueling and decommissioning for at least three years. The preliminary decommissioning plan, in accordance with the NRC's final rule, has been submitted and is being reviewed by the NRC. The basis of the preliminary decommissioning plan has been SAFSTOR. Public Service Company, who is the owner and operator of FSV, is scheduled to submit a proposed decommissioning plan to the NRC in the fourth quarter of 1990. PSC has gone out for bid on the decontamination and dismantlement of FSV. This paper includes the defueling schedule, the independent spent fuel storage installation status, the probability of shipping fuel to DOE, the status of the preliminary decommissioning plan submittal, the issuance of a possession only license and what are the results of obtaining this license amendment, preliminary decommissioning activities allowed prior to the approval of a proposed decommissioning plan, the preparation of a proposed decommissioning plan and the status of our decision to proceed with SAFSTOR or DECON as identified in the NRC's final decommissioning rule

  9. Decommissioning Technology Development for Nuclear Research Facilities

    International Nuclear Information System (INIS)

    Lee, K. W.; Kang, Y. A.; Kim, G. H.

    2007-06-01

    It is predicted that the decommissioning of a nuclear power plant would happen in Korea since 2020 but the need of partial decommissioning and decontamination for periodic inspection and life extension still has been on an increasing trend and its domestic market has gradually been extended. Therefore, in this project we developed following several essential technologies as a decommissioning R and D. The measurement technology for in-pipe radioactive contamination was developed for measuring alpha/beta/gamma emitting nuclides simultaneously inside a in-pipe and it was tested into the liquid waste transfer pipe in KRR-2. And the digital mock-up system for KRR-1 and 2 was developed for choosing the best scenarios among several scenarios on the basis of various decommissioning information(schedule, waste volume, cost, etc.) that are from the DMU and the methodology of decommissioning cost estimation was also developed for estimating a research reactor's decommissioning cost and the DMU and the decommissioning cost estimation system were incorporated into the decommissioning information integrated management system. Finally the treatment and management technology of the irradiated graphites that happened after decommissioning KRR-2 was developed in order to treat and manage the irradiated graphites safely

  10. Financing the Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    2016-01-01

    Decommissioning of both commercial and R and D nuclear facilities is expected to increase significantly in the coming years, and the largest of such industrial decommissioning projects could command considerable budgets. It is important to understand the costs of decommissioning projects in order to develop realistic cost estimates as early as possible based on preliminary decommissioning plans, but also to develop funding mechanisms to ensure that future decommissioning expenses can be adequately covered. Sound financial provisions need to be accumulated early on to reduce the potential risk for residual, unfunded liabilities and the burden on future generations, while ensuring environmental protection. Decommissioning planning can be subject to considerable uncertainties, particularly in relation to potential changes in financial markets, in energy policies or in the conditions and requirements for decommissioning individual nuclear installations, and such uncertainties need to be reflected in regularly updated cost estimates. This booklet offers a useful overview of the relevant aspects of financing the decommissioning of nuclear facilities. It provides information on cost estimation for decommissioning, as well as details about funding mechanisms and the management of funds based on current practice in NEA member countries. (authors)

  11. Decommissioning Technology Development for Nuclear Research Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Lee, K. W.; Kang, Y. A.; Kim, G. H. (and others)

    2007-06-15

    It is predicted that the decommissioning of a nuclear power plant would happen in Korea since 2020 but the need of partial decommissioning and decontamination for periodic inspection and life extension still has been on an increasing trend and its domestic market has gradually been extended. Therefore, in this project we developed following several essential technologies as a decommissioning R and D. The measurement technology for in-pipe radioactive contamination was developed for measuring alpha/beta/gamma emitting nuclides simultaneously inside a in-pipe and it was tested into the liquid waste transfer pipe in KRR-2. And the digital mock-up system for KRR-1 and 2 was developed for choosing the best scenarios among several scenarios on the basis of various decommissioning information(schedule, waste volume, cost, etc.) that are from the DMU and the methodology of decommissioning cost estimation was also developed for estimating a research reactor's decommissioning cost and the DMU and the decommissioning cost estimation system were incorporated into the decommissioning information integrated management system. Finally the treatment and management technology of the irradiated graphites that happened after decommissioning KRR-2 was developed in order to treat and manage the irradiated graphites safely.

  12. European Decommissioning Academy (EDA). Ready to start

    International Nuclear Information System (INIS)

    Slugen, Vladimir

    2015-01-01

    According to analyses presented at EC meeting focused on decommissioning organized at 11 September 2012 in Brussels, it was stated that at least 2,000 new international experts for decommissioning will be needed in Europe up to 2025, which means about 150 each year. The article describes the European Decommissioning Academy (EDA) which is prepared for the first term in June 2015 in Slovakia. The main goal is a creation of new nuclear experts generation for decommissioning via the Academy, which will include lessons, practical exercises in laboratories as well as 2 days on-site training at NPP V-1 in Jaslovske Bohunice (Slovakia). Four days technical tour via most interesting European decommissioning facilities in Switzerland and Italy are planned as well. After the final exam, there is the option to continue in knowledge collection via participation at the 2nd Eastern and Central European Decommissioning (ECED) conference in Trnava (Slovakia). We would like to focus on VVER decommissioning issues because this reactor type is the most distributed design in the world and many of these units are actually in decommissioning process or will be decommissioned in the near future.

  13. Final report on case studies

    DEFF Research Database (Denmark)

    Ljungberg, Daniel; McKelvey, Maureen; Lassen, Astrid Heidemann

    2012-01-01

    Case study as a research design means investigating a single or multiple instance(s) or setting(s) (i.e. a case) and its entire context to explain a phenomenon and its processes. This is achieved through detailed understanding, usually comprised of multiple sources of information. In this way, case...... studies attempt to provide as a complete an understanding of a (complex) phenomenon as possible. Within the AEGIS project, survey and case study research are complementary. They are complementary in the sense that the former can provide more generalizable evidence on a phenomenon in terms of cross......-sectional data, while the latter can provide more in-depth (qualitative) understanding on specific issues. In systematically examining the case studies, however, this report goes beyond a typical single case study. Here we provide a synthesis of 86 case studies. Multiple case studies, following similar focus...

  14. 425 Case study

    African Journals Online (AJOL)

    Marinda

    Anaesthesia management of acute aortic dissection type B in ... of a severe, constant abdominal and chest pain radiating to the ... Continuous spinal anaesthesia was induced ... these cases surgical intervention is critical.1,2 Type B of AAD is.

  15. Activation analysis of dual-purpose metal cask after the end of design lifetime for decommission

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Tae Man; Ku, Ji Young; Dho Ho Seog; Cho, Chun Hyung [Korea Radioactive Waste Agency, Daejeon (Korea, Republic of); Ko, Jae Hun [Korea Nuclear Engineering and Service Co., Daejeon (Korea, Republic of)

    2016-12-15

    The Korea Radioactive Waste Agency (KORAD) has developed a dual-purpose metal cask for the dry storage of spent nuclear fuel that has been generated by domestic light-water reactors. The metal cask was designed in compliance with international and domestic technology standards, and safety was the most important consideration in developing the design. It was designed to maintain its integrity for 50 years in terms of major safety factors. The metal cask ensures the minimization of waste generated by maintenance activities during the storage period as well as the safe management of the waste. An activation evaluation of the main body, which includes internal and external components of metal casks whose design lifetime has expired, provides quantitative data on their radioactive inventory. The radioactive inventory of the main body and the components of the metal cask were calculated by applying the MCNP5·ORIGEN-2 evaluation system and by considering each component's chemical composition, neutron flux distribution, and reaction rate, as well as the duration of neutron irradiation during the storage period. The evaluation results revealed that 10 years after the end of the cask's design life, {sup 60}Co had greater radioactivity than other nuclides among the metal materials. In the case of the neutron shield, nuclides that emit high-energy gamma rays such as {sup 28}Al and {sup 24}Na had greater radioactivity immediately after the design lifetime. However, their radioactivity level became negligible after six months due to their short half-life. The surface exposure dose rates of the canister and the main body of the metal cask from which the spent nuclear fuel had been removed with expiration of the design lifetime were determined to be at very low levels, and the radiation exposure doses to which radiation workers were subjected during the decommissioning process appeared to be at insignificant levels. The evaluations of this study strongly suggest that

  16. Nuclear facility decommissioning and site remedial actions

    International Nuclear Information System (INIS)

    Owen, P.T.; Knox, N.P.; Ferguson, S.D.; Fielden, J.M.; Schumann, P.L.

    1989-09-01

    The 576 abstracted references on nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the tenth in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types--technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions--have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Program, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Uranium Mill Tailings Management, (7) Technical Measurements Center, and (8) General Remedial Action Program Studies. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication description. Indexes are provided for author, corporate affiliation, title work, publication description, geographic location, subject category, and keywords

  17. Nuclear facility decommissioning and site remedial actions

    Energy Technology Data Exchange (ETDEWEB)

    Owen, P.T.; Knox, N.P.; Ferguson, S.D.; Fielden, J.M.; Schumann, P.L.

    1989-09-01

    The 576 abstracted references on nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the tenth in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types--technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions--have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Program, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Uranium Mill Tailings Management, (7) Technical Measurements Center, and (8) General Remedial Action Program Studies. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication description. Indexes are provided for author, corporate affiliation, title work, publication description, geographic location, subject category, and keywords.

  18. Evaluation of the I. Stage of decommissioning and implementation of the II. Stage of decommissioning of NPP V1

    International Nuclear Information System (INIS)

    Hrasnova, E.

    2015-01-01

    In this paper author deals with following aspects: 1. Introduction of company Nuclear and Decommissioning Company, plc; 2. Evaluation of the I. stage of decommissioning and implementation of the II. Stage of decommissioning of NPP V1; (author)

  19. Status of ANSI standards on decommissioning of nuclear reprocessing facilities

    International Nuclear Information System (INIS)

    Graham, H.B.

    1975-01-01

    A definition of decommissioning is given, and the preparation of ANSI Standard, ''General Design Criteria for Nuclear Reprocessing Facilities'' (N101.3) is discussed. A Eurochemic report, entitled ''The Shutdown of Reprocessing Facilities--Results of Preliminary Studies on the Installations Belonging to Eurochemic,'' was used in the preparation of this standard. (U.S.)

  20. Development of decontamination, decommissioning and environmental restoration technology

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Byung Jik; Kwon, H. S.; Kim, G. N. and others

    1999-03-01

    Through the project of 'Development of decontamination, decommissioning and environmental restoration technology', the followings were studied. 1. Development of decontamination and repair technology for nuclear fuel cycle facilities 2. Development of dismantling technology 3. Development of environmental restoration technology. (author)

  1. New safety experiments in decommissioned superheated steam reactor at Karlstein

    International Nuclear Information System (INIS)

    Koerting, K.

    1986-01-01

    This article gives a concise summary of the Status Report of the Superheated Steam Reactor Safety Program (PHDR) Project, held at KfK on Dec. 5, 1985. The results discussed dealt with fire experiments, shock tests simulating airplane crashes, temperature shocks in the reactor pressure vessel, studies of crack detection in pressure vessels and blasting experiments associated with nuclear plant decommissioning

  2. Development of decontamination, decommissioning and environmental restoration technology

    International Nuclear Information System (INIS)

    Lee, Byung Jik; Kwon, H. S.; Kim, G. N. and others

    1999-03-01

    Through the project of D evelopment of decontamination, decommissioning and environmental restoration technology , the followings were studied. 1. Development of decontamination and repair technology for nuclear fuel cycle facilities 2. Development of dismantling technology 3. Development of environmental restoration technology. (author)

  3. In-house developed methodologies and tools for decommissioning projects

    International Nuclear Information System (INIS)

    Detilleux, Michel; Centner, Baudouin

    2007-01-01

    The paper describes different methodologies and tools developed in-house by Tractebel Engineering to facilitate the engineering works to be carried out especially in the frame of decommissioning projects. Three examples of tools with their corresponding results are presented: - The LLWAA-DECOM code, a software developed for the radiological characterization of contaminated systems and equipment. The code constitutes a specific module of more general software that was originally developed to characterize radioactive waste streams in order to be able to declare the radiological inventory of critical nuclides, in particular difficult-to-measure radionuclides, to the Authorities. In the case of LLWAA-DECOM, deposited activities inside contaminated equipment (piping, tanks, heat exchangers...) and scaling factors between nuclides, at any given time of the decommissioning time schedule, are calculated on the basis of physical characteristics of the systems and of operational parameters of the nuclear power plant. This methodology was applied to assess decommissioning costs of Belgian NPPs, to characterize the primary system of Trino NPP in Italy, to characterize the equipment of miscellaneous circuits of Ignalina NPP and of Kozloduy unit 1 and, to calculate remaining dose rates around equipment in the frame of the preparation of decommissioning activities; - The VISIMODELLER tool, a user friendly CAD interface developed to ease the introduction of lay-out areas in a software named VISIPLAN. VISIPLAN is a 3D dose rate assessment tool for ALARA work planning, developed by the Belgian Nuclear Research Centre SCK.CEN. Both softwares were used for projects such as the steam generators replacements in Belgian NPPs or the preparation of the decommissioning of units 1 and 2 of Kozloduy NPP; - The DBS software, a software developed to manage the different kinds of activities that are part of the general time schedule of a decommissioning project. For each activity, when relevant

  4. Technology, safety and costs of decommissioning a reference boiling water reactor power station: Comparison of two decommissioning cost estimates developed for the same commercial nuclear reactor power station

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1990-12-01

    This study presents the results of a comparison of a previous decommissioning cost study by Pacific Northwest Laboratory (PNL) and a recent decommissioning cost study of TLG Engineering, Inc., for the same commercial nuclear power reactor station. The purpose of this comparative analysis on the same plant is to determine the reasons why subsequent estimates for similar plants by others were significantly higher in cost and external occupational radiation exposure (ORE) than the PNL study. The primary purpose of the original study by PNL (NUREG/CR-0672) was to provide information on the available technology, the safety considerations, and the probable costs and ORE for the decommissioning of a large boiling water reactor (BWR) power station at the end of its operating life. This information was intended for use as background data and bases in the modification of existing regulations and in the development of new regulations pertaining to decommissioning activities. It was also intended for use by utilities in planning for the decommissioning of their nuclear power stations. The TLG study, initiated in 1987 and completed in 1989, was for the same plant, Washington Public Supply System's Unit 2 (WNP-2), that PNL used as its reference plant in its 1980 decommissioning study. Areas of agreement and disagreement are identified, and reasons for the areas of disagreement are discussed. 31 refs., 3 figs., 22 tabs

  5. Criteria, standards and policies regarding decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Detilleux, E.; Lennemann, W.L.

    1977-01-01

    At the end of this century, there will probably be around 2500 operating nuclear power reactors, along with all the other nuclear fuel cycle facilities supporting their operation. Eventually these facilities, one by one, will be shut down and it will be necessary to dispose of them as with any redundant industrial facility or plant. Some parts of a nuclear fuel cycle facility can be dismantled by conventional methods, but those parts which have become contaminated with radioactive nuclear products or induced radioactivity must be subject to rigid controls and restrictions and handled by special dismantling and disposal procedures. In many cases, the resulting quantity of radioactive waste is likely to be relatively large and dismantling quite costly. Decommissioning nuclear facilities is a multifaceted problem involving planners, design engineers, operators, waste managers and regulatory authorities. Preparation for decommissioning should begin as early as site selection and plant design. The corner stone for the preparation of a decommissioning programme is the definition of its extent, meeting the requirements for public and environmental protection during the period that the radioactive material is of concern. The paper discusses the decontamination and decommissioning experience at the Eurochemic fuel reprocessing plant, the implications and the knowledge gained from this experience. It includes the results of technical reviews made by the Nuclear Energy Agency of OECD and the International Atomic Energy Agency regarding decommissioning nuclear facilities. The paper notes the special planning that should be arranged between those responsible for the nuclear facility and competent public authorities who should jointly make a realistic determination of the eventual disposition of the nuclear facility, even before it is built. Recommendations cover the responsibilities of nuclear plant entrepreneurs, designers, operators, and public and regulatory authorities

  6. Radiological and economic impact of decommissioning charged particle accelerators

    International Nuclear Information System (INIS)

    Sonck, M.; Buls, N.; Hermanne, A.; Eggermont, G.

    2000-01-01

    To evaluate the real radiological and economic consequences of future dismantling of particle accelerators, only insufficient information was available in literature or even at the individual accelerator facilities themselves. DGXI of the European Commission hence launched a project with focus on gathering quantitative and scientifically sound data on the number of accelerators in the EU, on the status of activation of the different facilities, on the awareness of the possible problems at dismantling and on cost evacuations for full scale decommissioning. The project was granted to the VUB with subcontracts to NIRAS/ONDRAF, MAN and CEA-Saclay. With the replies received to an extensive questionnaire, a database was set up with the necessary data for evaluating the decommissioning problems to be expected at the different facilities. From this database three accelerators were chosen as reference cases (VUB medium energy cyclotron, IRMM 200 MeV electron linear accelerator and the 6 GeV proton synchrotron Saturne in Saclay). Extensive sampling of their concrete shieldings (more than 200 drill cores) and metal parts of accelerator and infrastructure, followed by accurate γ-spectrometric analysis and custom designed 3D interpolation, yield data on the 3D distribution of the activity in the different rooms of the installations. In addition to the γ-spectrometric analysis, an analysis of the tritium content of the concrete was performed by measuring the water liberated from heating ground concrete samples. These specific activity distributions allow evaluation of both immediate and deferred decommissioning costs using different scenarios (different clearance levels, different waste management prices, different labor costs and different decommissioning techniques) based on real situations in France, Germany and Great Britain. Several important conclusions and recommendations with respect to decommissioning both existing and future accelerator facilities will be presented

  7. Study on a new calibration methods of in-situ HPGe γ spectrometers used for non-destructive analyzing radioactivity in nuclear facilities decommissioning

    International Nuclear Information System (INIS)

    Xiao Xuefu; Song Lijun; Wang Yulai; Wen Fuping; Liao Haitao; Ban Ying; Xia Yihua; Li Ruixiang; Li Hang; Tu Xingmin

    2007-06-01

    A new calibration technique, which is the Monte Carlo modeling technique, of in-situ HPGe γ spectrometers used for non-destructive analyzing radioactivity in nuclear facilities decommissioning, is presented. A series of assay for some stainless steel pipes and tanks in some nuclear facilities/laboratories of CIAE are taken on site with the in-situ HPGe γ spectrometer. At the same time, some examples are taken and analyzed in laboratories. The relative bias/variation between the values of activity measured by in-situ HPGe γ spectrometers on site and that analyzed in laboratory is less than ±45.0%. (authors)

  8. Level 3 decommissioning of Triton - Nereide research reactor

    International Nuclear Information System (INIS)

    Lopes, E.; Pillette-Cousin, L.

    2002-01-01

    The French Atomic Energy Commission Center located at Fontenay-Aux-Roses has launched an extensive programme of site cleanup and decommissioning of nuclear facilities. This programme includes the level 3 decommissioning of the Triton and Nereide piles. These pool type research reactors were constructed in the late 1950's, primarily for R and D activities related to neutron physics studies, radiological shielding experiments and radioelement production. As of 1982, a level 2 decommissioning was achieved and over the the last twenty years, no activities were carried out in the facility. During 2001, there has been extensive investigation work carried out to acquire a better knowledge of the radiological status of the facility, in order to set up dismantling scenarios and to reduce the volume of generated radioactive waste. Indeed, one of the first and main operations to be carried out for dismantling Triton and Nereide piles is waste zoning, by using the facility layout, operating conditions and history, as well as the present radiological inventory. The paper describes the investigations and studies carried out to implement waste zoning. The paper also describes the preliminary dismantling operations undertaken on equipment and studies conducted to optimize the dismantling and cleanup of the facility. Finally, the paper presents the outline of the preferred dismantling and decommissioning options and the progress of the work to date. (author)

  9. Principles of record keeping for decommissioning purposes

    International Nuclear Information System (INIS)

    Laraia, M.

    2003-01-01

    At the siting and conceptual design stage of a nuclear facility the first records pertaining to that facility are produced and stored. Subsequent phases in the facility's life cycle (detailed design, construction, commissioning, operation and shutdown) will include the production and retention of a large variety of records. Design, as-built drawings and operational records are essential for safe and efficient operation of any nuclear facility. This set of records is constantly updated and augmented during operation. Records from all phases of a nuclear facility are important for planning its decommissioning. Although not all of these records need to be included explicitly in the decommissioning plan itself, the process of initial, ongoing and final planning utilizes pertinent records for, and ultimately achieves, safe and cost effective decommissioning. When a nuclear facility is shutdown for decommissioning, current operating experience may be lost. Therefore, one important element of planning is to identify, secure and store appropriate operational records to support decommissioning. This process is preferably initiated during the design and construction phase and continues throughout operation including shutdown. Part of the records inventory from operation will become records for decommissioning and it is cost effective to identify these records before final facility shutdown. Experience shows that lack of attention to record keeping may result in an undue waste of time, other resources and additional costs. The newly established Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management recognizes the importance of keeping decommissioning-related records. In addition, the systematic management of records is an essential part of quality assurance and is often a licence condition. A good comprehensive decommissioning records management system (RMS) is one specific application of the broader concepts of 'Protection

  10. Research in decommissioning techniques for nuclear fuel cycle facilities in JNC. 7. JWTF decommissioning techniques

    International Nuclear Information System (INIS)

    Ogawa, Ryuichiro; Ishijima, Noboru

    1999-02-01

    Decommissioning techniques such as radiation measuring and monitoring, decontamination, dismantling and remote handling in the world were surveyed to upgrading technical know-how database for decommissioning of Joyo Waste Treatment Facility (JWTF). As the result, five literatures for measuring and monitoring techniques, 14 for decontamination and 22 for dismantling feasible for JWTF decommissioning were obtained and were summarized in tables. On the basis of the research, practical applicability of those techniques to decommissioning of JWTF was evaluated. This report contains brief surveyed summaries related to JWTF decommissioning. (H. Itami)

  11. Costing for decommissioning: Continuing NEA engagement

    International Nuclear Information System (INIS)

    Gillogly, Mari; Weber, Inge; ); Siemann, Michael; )

    2017-01-01

    On 20-21 September 2016, the International Conference on Financing of Decommissioning of nuclear power plants was held in Stockholm, Sweden. The conference focused on the exchange and sharing of information on current and emerging issues in the financing of nuclear power plant decommissioning and the underlying costs of decommissioning. It aimed at providing a good picture of the variety of financing systems in place to cover the costs of decommissioning of nuclear facilities. As an increasing number of nuclear reactors are expected to be permanently shut-down and enter into the decommissioning phase, the conference highlighted challenges for financing and delivering these decommissioning activities and explored the ways in which they were being addressed. This also included consideration of the implications of potentially under-funded or uncertain decommissioning liabilities. The insights gained in the course of the conference informed future development of work on these issues. The conference addressed a variety of issues from a range of perspectives under three main themes: financing systems - the variety of financing systems in place to provide the financial resources needed for decommissioning, including the arrangements for collecting and developing financial resources during operation and drawing down the assets during decommissioning activities, as well as oversight and reporting issues; decommissioning costing - understanding the cost estimates, quality and interpretation issues in decommissioning costing, the challenges of assurance, comparisons of estimates and actual costs, exploring ways to remedy the current lack of comparable actual cost data, possible benchmarking, etc.; [financial] risk management - effective management of financial assets, risk management strategies, the changing of markets and investment strategies for financial assets, balancing the rates of return and the reduction of risk, implications of the major changes in the energy and

  12. Cost estimation of the decommissioning of nuclear fuel cycle plants

    International Nuclear Information System (INIS)

    Barbe, A.; Pech, R.

    1991-01-01

    Most studies conducted to date on the cost of decommissioning nuclear facilities pertain to reactors. Few such studies have been performed on the cost of decommissioning nuclear fuel cycle plants, particularly spent fuel reprocessing plants. Present operators of these plants nevertheless need to assess such costs, at least in order to include the related expenses in their short-, medium- or long-term projections. They also need to determine now, for example, suitable production costs that the plant owners will have to propose to their customers. Unlike nuclear reactors for which a series effect is involved (PWRs, BWRs, etc.) and where radioactivity is relatively concentrated, industrial-scale reprocessing plants are large, complex installations for which decommissioning is a long and costly operation that requires a special approach. Faced with this problem, Cogema, the owner and operator of the La Hague and Marcoule reprocessing plants in France, called on SGN to assess the total decommissioning costs for its plants. This assessment led SGN to development by SGN engineers of a novel methodology and a computerized calculation model described below. The resulting methodology and model are applicable to other complex nuclear facilities besides reprocessing plants, such as laboratories and nuclear auxiliaries of reactor cores. (author)

  13. Development of Cost Estimation Methodology of Decommissioning for PWR

    International Nuclear Information System (INIS)

    Lee, Sang Il; Yoo, Yeon Jae; Lim, Yong Kyu; Chang, Hyeon Sik; Song, Geun Ho

    2013-01-01

    The permanent closure of nuclear power plant should be conducted with the strict laws and the profound planning including the cost and schedule estimation because the plant is very contaminated with the radioactivity. In Korea, there are two types of the nuclear power plant. One is the pressurized light water reactor (PWR) and the other is the pressurized heavy water reactor (PHWR) called as CANDU reactor. Also, the 50% of the operating nuclear power plant in Korea is the PWRs which were originally designed by CE (Combustion Engineering). There have been experiences about the decommissioning of Westinghouse type PWR, but are few experiences on that of CE type PWR. Therefore, the purpose of this paper is to develop the cost estimation methodology and evaluate technical level of decommissioning for the application to CE type PWR based on the system engineering technology. The aim of present study is to develop the cost estimation methodology of decommissioning for application to PWR. Through the study, the following conclusions are obtained: · Based on the system engineering, the decommissioning work can be classified as Set, Subset, Task, Subtask and Work cost units. · The Set and Task structure are grouped as 29 Sets and 15 Task s, respectively. · The final result shows the cost and project schedule for the project control and risk management. · The present results are preliminary and should be refined and improved based on the modeling and cost data reflecting available technology and current costs like labor and waste data

  14. Decommissioning and environmental restoration of nuclear facilities in China

    International Nuclear Information System (INIS)

    Pan Ziqiang

    2000-01-01

    In the beginning of the 1980s, the Scientific and Technological Commission (STC) began the study on the environmental impact of the nuclear industry in China. At the end of the 1980s, the STC initiated the study on the decommissioning of nuclear facilities and environmental restoration. In 1989 the STC completed the project entitled ''Radiological and Environmental Quality Assessment of the Nuclear Industry in China Over the Past Thirty Years''. The status of the environmental pollution of various nuclear facility sites was subsequently analysed. In 1994, the decommissioning and environmental restoration of the first research and manufacture complex for nuclear weapons was completed. The complex is now accessible to the public without restriction and the site has become a town. Some nuclear related facilities, such as uranium mines, are currently being decommissioned. Although uranium mining and milling has a more serious impact on the environment, the technology for decommissioning and environmental restoration in mining and milling installations is not much more complicated than that used for reactor and reprocessing facilities: much has been achieved in the area of mining and milling. (author)

  15. Decommissioning of NPPs with spent nuclear fuel present - efforts to amend the German regulatory framework to cope with this situation

    International Nuclear Information System (INIS)

    Brendebach, Boris; Rehs, Bernd

    2016-01-01

    The authorization to operate an installation for the fission of nuclear fuel for the commercial production of electricity was withdrawn for the seven oldest NPPs and NPP Kruemmel in Germany on August 6, 2011 after the events at Japanese Nuclear Power Plant (NPP) Fukushima Daiichi in March 2011. In the meantime, all these NPPs applied for decommissioning. One aspect reflected in the applications for these NPPs is the possibility that spent nuclear fuel elements or fuel rods will still be present in the cooling ponds at least during the first stage of decommissioning, i.a. due to limited availability of spent fuel casks. Although considerable decommissioning experiences are available in Germany, the approach 'decommissioning with fuel elements present' has been the exceptional case so far. The paper highlights the efforts undertaken to strengthen the regulatory framework with respect to decommissioning in Germany taking into account this changed approach. The paper presents a short introduction to the legal and regulatory requirements for decommissioning in Germany. Afterwards, the updates to the Decommissioning Guide, which includes proposals for an appropriate procedure for the decommissioning, safe enclosure and dismantling of facilities or parts thereof as defined in item 7 of the German Atomic Energy Act in respect of the application of the technical rules for planning and preparation of decommissioning measures as well as for licensing and supervision, are highlighted. In addition, the amendments to the Guidelines for the Decommissioning of Nuclear Facilities of the Nuclear Waste Management Commission (ESK), which is complementary to the Decommissioning Guide in a technical sense, are reported as well. (authors)

  16. Decommissioning engineering systems for nuclear facilities and knowledge inheritance for decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Tachibana, Mitsuo

    2016-01-01

    Information on construction, operation and maintenance of a nuclear facility is essential in order to plan and implement the decommissioning of the nuclear facility. A decommissioning engineering system collects these information efficiently, retrieves necessary information rapidly, and support to plan the reasonable decommissioning as well as the systematic implementation of dismantling activities. Then, knowledge of workers involved facility operation and dismantling activities is important because decommissioning of nuclear facility will be carried out for a long period. Knowledge inheritance for decommissioning has been carried out in various organizations. This report describes an outline of and experiences in applying decommissioning engineering systems in JAEA and activities related to knowledge inheritance for decommissioning in some organizations. (author)

  17. The Research Status for Decommissioning and Radioactive Waste Minimization of HTR-PM

    International Nuclear Information System (INIS)

    Li Wenqian; Li Hong; Cao Jianzhu; Tong Jiejuan

    2014-01-01

    Decommissioning of the high-temperature gas-cooled reactor-pebble bed module (HTR-PM) as a part of the nuclear power plant, is very important during the early design stage of the construction, and it is under study and research currently. This article gives a thorough description of the current decommissioning study status of HTR-PM. Since HTR-PM has its features such as adopting a large amount of graphite, the waste inventory and characterization will be quite different from other type of reactors, new researches should be carried out and good lessons of practices and experiences should be learned from international other reactors, especially the AVR. Based on the new international regulations and Chinese laws, a comprehensive decommissioning program should be proposed to guarantee the HTR-PM will succeed in every stage of the decommissioning, such as defueling, decontamination, dismantling, demolition, waste classification and disposal, etc. In the meantime, the minimization of the radioactive waste should be taken into account during the whole process - before construction, during operation and after shut down. In this article, the decommissioning strategy and program conception of HTR-PM will be introduced, the radiation protection consideration during the decommissioning activities will be discussed, and the research on the activation problem of the decommissioning graphite will be introduced. (author)

  18. Technology and costs for decommissioning of Swedish nuclear power plants