  1. Designing a two-rank acceptance sampling plan for quality inspection of geospatial data products

    Science.gov (United States)

    Tong, Xiaohua; Wang, Zhenhua; Xie, Huan; Liang, Dan; Jiang, Zuoqin; Li, Jinchao; Li, Jun

    2011-10-01

    To address the disadvantages of classical sampling plans designed for traditional industrial products, we originally propose a two-rank acceptance sampling plan (TRASP) for the inspection of geospatial data outputs based on the acceptance quality level (AQL). The first rank sampling plan is to inspect the lot consisting of map sheets, and the second is to inspect the lot consisting of features in an individual map sheet. The TRASP design is formulated as an optimization problem with respect to sample size and acceptance number, which covers two lot size cases. The first case is for a small lot size with nonconformities being modeled by a hypergeometric distribution function, and the second is for a larger lot size with nonconformities being modeled by a Poisson distribution function. The proposed TRASP is illustrated through two empirical case studies. Our analysis demonstrates that: (1) the proposed TRASP provides a general approach for quality inspection of geospatial data outputs consisting of non-uniform items and (2) the proposed acceptance sampling plan based on TRASP performs better than other classical sampling plans. It overcomes the drawbacks of percent sampling, i.e., "strictness for large lot size, toleration for small lot size," and those of a national standard used specifically for industrial outputs, i.e., "lots with different sizes corresponding to the same sampling plan."

  2. Evaluation of sampling plans for in-service inspection of steam generator tubes

    International Nuclear Information System (INIS)

    Kurtz, R.J.; Heasler, P.G.; Baird, D.B.

    1994-02-01

    This report summarizes the results of three previous studies to evaluate and compare the effectiveness of sampling plans for steam generator tube inspections. An analytical evaluation and Monte Carlo simulation techniques were the methods used to evaluate sampling plan performance. To test the performance of candidate sampling plans under a variety of conditions, ranges of inspection system reliability were considered along with different distributions of tube degradation. Results from the eddy current reliability studies performed with the retired-from-service Surry 2A steam generator were utilized to guide the selection of appropriate probability of detection and flaw sizing models for use in the analysis. Different distributions of tube degradation were selected to span the range of conditions that might exist in operating steam generators. The principal means of evaluating sampling performance was to determine the effectiveness of the sampling plan for detecting and plugging defective tubes. A summary of key results from the eddy current reliability studies is presented. The analytical and Monte Carlo simulation analyses are discussed along with a synopsis of key results and conclusions

  3. Inspection planning

    International Nuclear Information System (INIS)

    Korosec, D.; Levstek, M.F.

    2001-01-01

    Slovenian Nuclear Safety Administration (SNSA) division of nuclear and radiological safety inspection has developed systematic approach to their inspections. To be efficient in their efforts regarding regular and other types of inspections, in past years, the inspection plan has been developed. It is yearly based and organized on a such systematic way, that all areas of nuclear safety important activities of the licensee are covered. The inspection plan assures appropriate preparation for conducting the inspections, allows the overview of the progress regarding the areas to be covered during the year. Depending on the licensee activities and nature of facility (nuclear power plant, research reactor, radioactive waste storage, others), the plan has different levels of intensity of inspections and also their frequency. One of the basic approaches of the plan is to cover all nuclear and radiological important activities on such way, that all regulatory requests are fulfilled. In addition, the inspection plan is a good tool to improve inspection effectiveness based on previous experience and allows to have the oversight of the current status of fulfillment of planned inspections. Future improvement of the plan is necessary in the light of newest achievements on this field in the nuclear world, that means, new types of inspections are planned and will be incorporated into plan in next year.(author)

  4. INSPECT: a package of computer programs for planning safeguards inspections

    International Nuclear Information System (INIS)

    Wincek, M.A.; Mullen, M.F.

    1979-04-01

    As part of the U.S. program to provide technical assistance to the International Atomic Energy Agency, a package of computer programs was developed for use in planning safeguards inspections of various types of nuclear facilities. The INSPECT software package is a set of five interactive FORTRAN programs which can be used to calculate the variance components of the MUF (Material Unaccounted For) statistic, the variance components of the D (difference) statistic, attribute and variables sampling plans, a measure of the effectiveness of the inspection, and a measurement of the cost of implementing the inspection plan. This report describes the programs and explains how to use them

  5. INSPECT: a package of computer programs for planning and evaluating safeguards inspections

    International Nuclear Information System (INIS)

    Mullen, M.F.

    1980-01-01

    As part of the US Program of Technical Assistance to IAEA Safeguards, PNL has developed a package of computer programs, called INSPECT, that can be used in planning and evaluating safeguards inspections of various types of nuclear facilities. The programs are based on the statistical methods described in Part F of the IAEA Safeguards Technical Manual and can be used to calculate the variance components of the MUF (Material Unaccounted For) statistic, the variance components of the D (difference) statistic, attribute and variables sampling plans, and a measure of the effectiveness of the inspection plan. The paper describes the programs, reviews a number of applications, and indicates areas for future work

  6. Statistical sampling plans

    International Nuclear Information System (INIS)

    Jaech, J.L.

    1984-01-01

    In auditing and in inspection, one selects a number of items by some set of procedures and performs measurements which are compared with the operator's values. This session considers the problem of how to select the samples to be measured, and what kinds of measurements to make. In the inspection situation, the ultimate aim is to independently verify the operator's material balance. The effectiveness of the sample plan in achieving this objective is briefly considered. The discussion focuses on the model plant

  7. Statistical methods for the planning of inspections

    International Nuclear Information System (INIS)

    Hough, C.G.; Beetle, T.M.

    1976-01-01

    Inspection plans are designed to detect diversions of M kilograms of nuclear material with a high degree of confidence. Attribute sample plans were first developed and applied at a zero-energy fast reactor in the United Kingdom in co-operation with the Agency. Battelle-Northwest in the United States of America proposed a variables sample plan based on decision theory. The Karlsruhe Research Center in the Federal Republic of Germany developed the strategic points concept and sample plans based on game theory considerations. All these approaches were combined into a common approach which is summarized in this report. (author)

  8. Inspection and test planning

    International Nuclear Information System (INIS)

    Miller, T.

    1980-01-01

    Purpose of Quality Plan - arrangement of all necessary tests or inspections as far as possible filted to certain components or systems. Subject of Quality Plan - precise determination of tests or inspections and - according to the actual safety significance - the certificates to be done. Disposition of Quality Plan - accommodation of tests to the actual state of fabrication. Application of Quality Plan - to any component or system that is regarded. Supervision of Employment - by authorized personnel of manufacturer, customer or authority providing exact employment of quality plan. Overservance of Instructions - certificates given by authorized personnel. (orig./RW)

  9. Quality assurance for IAEA inspection planning

    International Nuclear Information System (INIS)

    Markin, J.T.

    1986-01-01

    Under the provisions of the Treaty on Nonproliferation of Nuclear Weapons and other agreements with states, the International Atomic Energy Agency (IAEA) conducts inspections at nuclear facilities to confirm that their operation is consistent with the peaceful use of nuclear material. The Department of Safeguards at the IAEA is considering a quality assurance program for activities related to the planning of these facility inspections. In this report, we summarize recent work in writing standards for planning inspections at the types of facilities inspected by the IAEA. The standards specify the sequence of steps in planning inspections, which are: (1) administrative functions, such as arrangements for visas and travel, and communications with the state to confirm facility operating schedules and the state's acceptance of the assigned inspectors; (2) technical functions including a specification of the required inspection activities, determination of personnel and equipment resources, and a schedule for implementing the inspection activities at the facility; and (3) management functions, such as pre- and post-inspection briefings, where the planned and implemented inspection activities are reviewed

  10. Integrating design and production planning with knowledge-based inspection planning system

    International Nuclear Information System (INIS)

    Abbasi, Ghaleb Y.; Ketan, Hussein S.; Adil, Mazen B.

    2005-01-01

    In this paper an intelligent environment to integrate design and inspection earlier to the design stage. A hybrid knowledge-based approach integrating computer-aided design (CAD) and computer-aided inspection planning (CAIP) was developed, thereafter called computer-aided design and inspection planning (CADIP). CADIP was adopted for automated dimensional inspection planning. Critical functional features were screened based on certain attributes for part features for inspection planning application. Testing the model resulted in minimizing the number of probing vectors associated with the most important features in the inspected prismatic part, significant reduction in inspection costs and release of human labor. In totality, this tends to increase customer satisfaction as a final goal of the developed system. (author)

  11. Special nuclear material inventory sampling plans

    International Nuclear Information System (INIS)

    Vaccaro, H.; Goldman, A.

    1987-01-01

    Since their introduction in 1942, sampling inspection procedures have been common quality assurance practice. The U.S. Department of Energy (DOE) supports such sampling of special nuclear materials inventories. The DOE Order 5630.7 states, Operations Offices may develop and use statistically valid sampling plans appropriate for their site-specific needs. The benefits for nuclear facilities operations include reduced worker exposure and reduced work load. Improved procedures have been developed for obtaining statistically valid sampling plans that maximize these benefits. The double sampling concept is described and the resulting sample sizes for double sample plans are compared with other plans. An algorithm is given for finding optimal double sampling plans that assist in choosing the appropriate detection and false alarm probabilities for various sampling plans

  12. Standard Ship Test and Inspection Plan, Procedures and Database

    National Research Council Canada - National Science Library

    1999-01-01

    ... construction schedules and increased cost is the area of test and inspection. This project investigates existing rules and regulations for testing and inspection of commercial ships and identifies differences and similarities within the requirements. The results include comparison matrices, a standard test plan, a set of standard test procedures, and a sample test database developed for a typical commercial ship.

  13. Short-Run Contexts and Imperfect Testing for Continuous Sampling Plans

    Directory of Open Access Journals (Sweden)

    Mirella Rodriguez

    2018-04-01

    Full Text Available Continuous sampling plans are used to ensure a high level of quality for items produced in long-run contexts. The basic idea of these plans is to alternate between 100% inspection and a reduced rate of inspection frequency. Any inspected item that is found to be defective is replaced with a non-defective item. Because not all items are inspected, some defective items will escape to the customer. Analytical formulas have been developed that measure both the customer perceived quality and also the level of inspection effort. The analysis of continuous sampling plans does not apply to short-run contexts, where only a finite-size batch of items is to be produced. In this paper, a simulation algorithm is designed and implemented to analyze the customer perceived quality and the level of inspection effort for short-run contexts. A parameter representing the effectiveness of the test used during inspection is introduced to the analysis, and an analytical approximation is discussed. An application of the simulation algorithm that helped answer questions for the U.S. Navy is discussed.

  14. 7 CFR 75.21 - Grain sample inspection.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 3 2010-01-01 2010-01-01 false Grain sample inspection. 75.21 Section 75.21... AND CERTIFICATION OF QUALITY OF AGRICULTURAL AND VEGETABLE SEEDS Inspection § 75.21 Grain sample inspection. A sample inspection shall be performed by examining official grain samples received from FGIS to...

  15. Inspection logistics planning for multi-stage production systems with applications to semiconductor fabrication lines

    Science.gov (United States)

    Chen, Kyle Dakai

    Since the market for semiconductor products has become more lucrative and competitive, research into improving yields for semiconductor fabrication lines has lately received a tremendous amount of attention. One of the most critical tasks in achieving such yield improvements is to plan the in-line inspection sampling efficiently so that any potential yield problems can be detected early and eliminated quickly. We formulate a multi-stage inspection planning model based on configurations in actual semiconductor fabrication lines, specifically taking into account both the capacity constraint and the congestion effects at the inspection station. We propose a new mixed First-Come-First-Serve (FCFS) and Last-Come-First-Serve (LCFS) discipline for serving the inspection samples to expedite the detection of potential yield problems. Employing this mixed FCFS and LCFS discipline, we derive approximate expressions for the queueing delays in yield problem detection time and develop near-optimal algorithms to obtain the inspection logistics planning policies. We also investigate the queueing performance with this mixed type of service discipline under different assumptions and configurations. In addition, we conduct numerical tests and generate managerial insights based on input data from actual semiconductor fabrication lines. To the best of our knowledge, this research is novel in developing, for the first time in the literature, near-optimal results for inspection logistics planning in multi-stage production systems with congestion effects explicitly considered.

  16. Generic Reliability-Based Inspection Planning for Fatigue Sensitive Details

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Straub, Daniel; Faber, Michael Havbro

    2005-01-01

    of fatigue sensitive details in fixed offshore steel jacket platforms and FPSO ship structures. Inspection and maintenance activities are planned such that code based requirements to the safety of personnel and environment for the considered structure are fulfilled and at the same time such that the overall......The generic approach for planning of in-service NDT inspections is extended to cover the case where the fatigue load is modified during the design lifetime of the structure. Generic reliability-based inspection planning has been developed as a practical approach to perform inspection planning...... expected costs for design, inspections, repairs and failures are minimized. The method is based on the assumption of “no-finds” of cracks during inspections. Each fatigue sensitive detail is categorized according to their type of details (SN curves), FDF values, RSR values, inspection, repair and failure...

  17. Monitoring well inspection and maintenance plan Y-12 Plant, Oak Ridge, Tennessee (revised)

    International Nuclear Information System (INIS)

    1996-09-01

    Inspection and maintenance of groundwater monitoring wells is a primary element of the Oak Ridge Y-12 Plant Groundwater Protection Program (GWPP). This document is the revised groundwater monitoring well inspection and maintenance plan for the U.S. Department of Energy (DOE) Y-12 Plant in Oak Ridge, Tennessee. The plan provides a systematic program for: (1) inspecting the physical condition of monitoring wells at the Y-12 Plant and (2) identifying maintenance needs that will extend the life of each well and ensure that representative groundwater quality samples and hydrologic data are collected from the wells. Original documentation for the Y-12 Plant GWPP monitoring well inspection and maintenance program was provided in HSW, Inc. 1991a. The original revision of the plan specified that only a Monitoring Well Inspection/Maintenance Summary need be updated and reissued each year. Rapid growth of the monitoring well network and changing regulatory requirements have resulted in constant changes to the status of wells (active or inactive) listed on the Monitoring Well Inspection/Maintenance Summary. As a result, a new mechanism to track the status of monitoring wells has been developed and the plan revised to formalize the new business practices. These changes are detailed in Sections 2.4 and 2.5

  18. Evaluating Heuristics for Planning Effective and Efficient Inspections

    Science.gov (United States)

    Shull, Forrest J.; Seaman, Carolyn B.; Diep, Madeline M.; Feldmann, Raimund L.; Godfrey, Sara H.; Regardie, Myrna

    2010-01-01

    A significant body of knowledge concerning software inspection practice indicates that the value of inspections varies widely both within and across organizations. Inspection effectiveness and efficiency can be measured in numerous ways, and may be affected by a variety of factors such as Inspection planning, the type of software, the developing organization, and many others. In the early 1990's, NASA formulated heuristics for inspection planning based on best practices and early NASA inspection data. Over the intervening years, the body of data from NASA inspections has grown. This paper describes a multi-faceted exploratory analysis performed on this · data to elicit lessons learned in general about conducting inspections and to recommend improvements to the existing heuristics. The contributions of our results include support for modifying some of the original inspection heuristics (e.g. Increasing the recommended page rate), evidence that Inspection planners must choose between efficiency and effectiveness, as a good tradeoff between them may not exist, and Identification of small subsets of inspections for which new inspection heuristics are needed. Most Importantly, this work illustrates the value of collecting rich data on software Inspections, and using it to gain insight into, and Improve, inspection practice.

  19. Inspection of licensee activities in emergency planning

    International Nuclear Information System (INIS)

    Van Binnebeek, J.J.; Gutierrez Ruiz, Luis Miguel; Bouvrie, E. des; Aro, Ilari; Gil, J.; Balloffet, Yves; Forsberg, Staffan; Klonk, H.; Lang, Hans-Guenter; Fichtinger, G.; Warren, T.; Manzella, P.; Gallo, R.; Koizumi, Hiroyoshi; Johnson, M.; Pittermann, P.

    1998-01-01

    The CNRA believes that safety inspections are a major element in the regulatory authority's efforts to ensure the safe operation of nuclear facilities. Considering the importance of these issues, the Committee has established a special Working Group on Inspection Practices (WGIP). The purpose of WGIP, is to facilitate the exchange of information and experience related to regulatory safety inspections between CNRA Member countries Following discussions at several meetings on the topic of what is expected by the regulatory body regarding inspection criteria, WGIP proposed putting together a compilation of Member countries practices on regulatory inspection practices with respect to licensee emergency planning. CNRA approved this task and this report. Information was collected from a questionnaire which was issued in 1996. The report presents information on regulatory inspection activities with respect to emergency planning in NEA Member countries. The focus of the report is on the third section. It reviews the similarities and differences in inspection practices to evaluate compliance with the requirements over which the regulatory body (RB) has jurisdiction

  20. Steam Generator Inspection Planning Expert System

    International Nuclear Information System (INIS)

    Rzasa, P.

    1987-01-01

    Applying Artificial Intelligence technology to steam generator non-destructive examination (NDE) can help identify high risk locations in steam generators and can aid in preparing technical specification compliant eddy current test (ECT) programs. A steam Generator Inspection Planning Expert System has been developed which can assist NDE or utility personnel in planning ECT programs. This system represents and processes its information using an object oriented declarative knowledge base, heuristic rules, and symbolic information processing, three artificial intelligence based techniques incorporated in the design. The output of the system is an automated generation of ECT programs. Used in an outage inspection, this system significantly reduced planning time

  1. Reliability-Based Inspection Planning for Structural Systems

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard

    1993-01-01

    A general model for reliability-based optimal inspection and repair strategies for structural systems is described. The total expected costs in the design lifetime is minimized with the number of inspections, the inspection times and efforts as decision variables. The equivalence of this model...... with a preposterior analysis from statistical decision theory is discussed. It is described how information obtained by an inspection can be used in a repair decision. Stochastic models for inspection, measurement and repair actions are presented. The general model is applied for inspection and repair planning...

  2. Hanford site post-NPH building inspection plan

    International Nuclear Information System (INIS)

    Wagenblast, G.R. Westinghouse Hanford

    1996-01-01

    This plan establishes consistent post-NPH building inspection procedures and defines a procedure for prioritization of buildings for inspection to ensure the safety of facilities prior to reentry. Qualification of systems for restart of operation is not included. This plan takes advantage, where possible, of existing national procedures for post-NPH inspection of buildings, of existing structural design and evaluation documentation of Hanford facilities, and current and proposed seismic instrumentation located throughout the Hanford site. A list of buildings, prioritized according to current building safety function and building vulnerability (without regard for or information about a damaging natural forces event) is provided

  3. 29 CFR 1956.84 - Location of plan for inspection and copying.

    Science.gov (United States)

    2010-07-01

    ... 29 Labor 9 2010-07-01 2010-07-01 false Location of plan for inspection and copying. 1956.84... PLANS Illinois § 1956.84 Location of plan for inspection and copying. A copy of the plan may be inspected and copied during normal business hours at the following locations: Office of State Programs, U.S...

  4. 29 CFR 1956.64 - Location of plan for inspection and copying.

    Science.gov (United States)

    2010-07-01

    ... 29 Labor 9 2010-07-01 2010-07-01 false Location of plan for inspection and copying. 1956.64... PLANS New Jersey § 1956.64 Location of plan for inspection and copying. A copy of the plan may be inspected and copied during normal business hours at the following locations: Office of State Programs, U.S...

  5. Discussion of in-service inspection planning for nuclear power plants

    International Nuclear Information System (INIS)

    Aoki, Takayuki; Takagi, Toshiyuki

    2012-01-01

    For creating an inspection plan for industrial plants like nuclear power plants, it is necessary to have a well-grounded basis. Therefore, this paper proposes a method for determining the following three elements of such a plan: the equipment to be inspected, the inspection method to be adopted, and the timing of its implementation using a scientific approach. The key idea is to analyze the components of the plan by employing the understanding of cancer detection and diagnosis in medical science and also to take an approach of creating a plan based on the characteristic features of the component and its aging degradation mode, the performance of the inspection method, and the relationship between the two. Taking all the above into account, the factors to be considered and the best way for inspecting the plants are presented in this paper. (author)

  6. Comparison of API 510 pressure vessels inspection planning with API 581 risk-based inspection planning approaches

    International Nuclear Information System (INIS)

    Shishesaz, Mohammad Reza; Nazarnezhad Bajestani, Mohammad; Hashemi, Seyed Javad; Shekari, Elahe

    2013-01-01

    To ensure mechanical integrity, all pressure vessels shall be inspected at the intervals provided in inspection codes or based on a risk-based inspection (RBI) assessment. The RBI assessment may allow previously established inspection intervals to be extended. This paper describes the methodology, analysis and results of two RBI studies conducted on 293 pressure vessel components in two crude oil distillation units. Based on API RBI methodology in API 581 (2008), risk target concept was used for determining inspection dates. It was shown that when thinning is the major active damage, the RBI recommended intervals are as long as twice the API 510 intervals. This paper summarizes that, as a fundamental step in the risk calculation, RBI has a more defined methodology for evaluating equipment for multiple damage mechanisms and a more defined approach to specify the use of other inspection technologies beyond the traditional visual, ultrasonic, and radiography tests. -- Highlights: • RBI calculated inspection intervals are as long as twice of API 510 inspection code. • Two case studies verified the advantage of RBI in inspection planning. • RBI is a more reliable methodology when evaluating multiple damage mechanisms. • Damage factor calculations can be used for determining RSFa value in FFS assessments

  7. Risk Based Inspection Planning of Ageing Structures

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Ersdal, Gerhard

    2008-01-01

    . Different approaches for updating inspection plans for older installations are considered in order to achieve decreased inspection intervals as the structure are ageing. The most promising method consists in increasing the rate of defects / crack initiation at the end of the expected lifetime. Different...

  8. Safety and Inspection Planning of Older Installations

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Ersdal, G.

    2007-01-01

    A basic assumption often made in risk/reliability based inspection planning is that a Bayesian approach can be used. This implies that probabilities of failure can be updated in a consistent way when new information (from inspections and repairs) becomes available. The Bayesian approach and a no-...

  9. Safety and Inspection Planning of Older Installations

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Ersdal, G.

    2008-01-01

    A basic assumption often made in risk- and reliability-based inspection planning is that a Bayesian approach can be used. This implies that probabilities of failure can be updated in a consistent way when new information (from inspections and repairs) becomes available. The Bayesian approach and ...

  10. Optimal Risk-Based Inspection Planning for Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Rangel-Ramirez, Jose G.; Sørensen, John Dalsgaard

    2008-01-01

    , inspection and maintenance activities are developed. This paper considers aspects of inspection and maintenance planning of fatigue prone details in jacket and tripod types of wind turbine support structures. Based oil risk-based inspection planning methods used for oil & gas installations, a framework......Wind turbines for electricity production have increased significantly the last years both in production capability and size. This development is expected to continue also in the coining years. The Support structure for offshore wind turbines is typically a steel structure consisting of a tower...... for optimal inspection and maintenance planning of offshore wind turbines is presented. Special aspects for offshore wind turbines are considered: usually the wind loading are dominating the wave loading, wake effects in wind farms are important and the reliability level is typically significantly lower than...

  11. Statistical sampling techniques as applied to OSE inspections

    International Nuclear Information System (INIS)

    Davis, J.J.; Cote, R.W.

    1987-01-01

    The need has been recognized for statistically valid methods for gathering information during OSE inspections; and for interpretation of results, both from performance testing and from records reviews, interviews, etc. Battelle Columbus Division, under contract to DOE OSE has performed and is continuing to perform work in the area of statistical methodology for OSE inspections. This paper represents some of the sampling methodology currently being developed for use during OSE inspections. Topics include population definition, sample size requirements, level of confidence and practical logistical constraints associated with the conduct of an inspection based on random sampling. Sequential sampling schemes and sampling from finite populations are also discussed. The methods described are applicable to various data gathering activities, ranging from the sampling and examination of classified documents to the sampling of Protective Force security inspectors for skill testing

  12. Hanford Facility Resource Conservation and Recovery Act Permit General Inspection Plan

    International Nuclear Information System (INIS)

    Beagles, D.S.

    1995-02-01

    This inspection plan describes the activities that shall be conducted for a general inspection of the Hanford Facility. RCRA includes a requirement that general facility inspections be conducted of the 100, 200 East, 200 West, 300, 400, and 1100 areas and the banks of the Columbia River. This plan meets the RCRA requirements and also provides for scheduling of inspections and defines general and specific items to be noted during the inspections

  13. 7 CFR 42.141 - Obtaining Operating Characteristic (OC) curve information for skip lot sampling and inspection.

    Science.gov (United States)

    2010-01-01

    ... Department of Agriculture AGRICULTURAL MARKETING SERVICE (Standards, Inspections, Marketing Practices... sampling plan for normal condition of container inspection from Table I or Table I-A of § 42.109. (b) For a... procedures. For example, let's assume the lot size is 6,001 to 12,000 containers, and we use the single...

  14. Optimal inspection planning for onshore pipelines subject to external corrosion

    International Nuclear Information System (INIS)

    Gomes, Wellison J.S.; Beck, André T.; Haukaas, Terje

    2013-01-01

    Continuous operation of pipeline systems involves significant expenditures in inspection and maintenance activities. The cost-effective safety management of such systems involves allocating the optimal amount of resources to inspection and maintenance activities, in order to control risks (expected costs of failure). In this context, this article addresses the optimal inspection planning for onshore pipelines subject to external corrosion. The investigation addresses a challenging problem of practical relevance, and strives for using the best available models to describe random corrosion growth and the relevant limit state functions. A single pipeline segment is considered in this paper. Expected numbers of failures and repairs are evaluated by Monte Carlo sampling, and a novel procedure is employed to evaluate sensitivities of the objective function with respect to design parameters. This procedure is shown to be accurate and more efficient than finite differences. The optimum inspection interval is found for an example problem, and the robustness of this optimum to the assumed inspection and failure costs is investigated. It is shown that optimum total expected costs found herein are not highly sensitive to the assumed costs of inspection and failure. -- Highlights: • Inspection, repair and failure costs of pipeline systems considered. • Optimum inspection schedule (OIS) obtained by minimizing total expected life-cycle costs. • Robustness of OIS evaluated w.r.t. estimated costs of inspection and failure. • Accurate non-conservative models of corrosion growth employed

  15. Acceptance inspection plan 105KE Facility modifications for fuel retrieval subproject

    International Nuclear Information System (INIS)

    Shen, E.J.

    1998-01-01

    The acceptance inspection of construction by Fluor Daniel Hanford (FDH) is performed to provide assurance that fabrication, construction, and installation are in accordance with approved contract documents. Approved contract documents used to perform inspections may include specifications, drawings, and contractor submittals such as fabrication drawings, procedures, etc. The amount or degree of inspection activity is tailored to the project as determined by the project team so that the effort and cost expended are commensurate with the importance of the facility in terms of function and safety. Inspections are documented to provide verification of the acceptability of the work performed. This document identifies the inspections and documentation forms to be provided. It is prepared and implemented with the understanding that the construction contractor is fully responsible for compliance with contract documents and for the quality of work performed. Inspections performed are in accordance with approved procedures. The Manager of Acceptance Inspection is responsible for the implementation of this plan and assignment of personnel for the work. Inspections are conducted by personnel who are qualified and certified, to perform their assigned task. The Acceptance Inspection Plan is organized in the Construction Specification Institute (CSI) format to cross reference design specification sections with sections of the AI Plan. In each AI Plan section the applicable specification section subject will be identified followed by the appropriate inspection requirements. General surveillances will be listed when applicable. Acceptance Inspection Reports are provided to document inspections not documented on a test report (i.e., Soil Test Data, Concrete Test Report, NDE/Weld Record, Leak/Pressure Test Certification, Backflow Device Test Report, Nonconformance Report, Deficiency Report, and/or Contractors testing forms)

  16. Acceptance inspection plan 105KW Facility modifications for fuel retrieval subproject

    International Nuclear Information System (INIS)

    Shen, E.J.

    1998-01-01

    The acceptance inspection of construction by Fluor Daniel Hanford (FDH) is performed to provide assurance that fabrication, construction, and installation are in accordance with approved contract documents. Approved contract documents used to perform inspections may include specifications, drawings, and contractor submittals such as fabrication drawings, procedures, etc. The amount or degree of inspection activity is tailored to the project as determined by the project team so that the effort and cost expended are commensurate with the importance of the facility in terms of function and safety. Inspections are documented to provide verification of the acceptability of the work performed. This document identifies the inspections and documentation forms to be provided. It is prepared and implemented with the understanding that the construction contractor is fully responsible for compliance with contract documents and for the quality of.work performed. Inspections performed are in accordance with approved procedures. The Manager of Acceptance Inspection is responsible for the implementation of this plan and assignment of personnel for the work. Inspections are conducted by personnel who are qualified and certified to perform their assigned task. The Acceptance Inspection Plan is organized in the Construction Specification Institute (CSI) format to cross reference design specification sections with sections of the AI Plan. In each AI Plan section the applicable specification section subject will be identified followed by the appropriate inspection requirements. General surveillances will be listed when applicable. Acceptance Inspection Reports are provided to document inspections not documented on a test report (i.e., Soil Test Data, Concrete Test Report, NDE/Weld Record, Leak/Pressure Test Certification, Backflow Device Test Report, Nonconformance Report, Deficiency Report, and/or Contractors testing forms)

  17. B Plant Complex generator dangerous waste storage areas inspection plan: Revision 1

    International Nuclear Information System (INIS)

    Beam, T.G.

    1994-01-01

    This document contains the inspection plan for the <90 day dangerous/mixed waste storage areas and satellite accumulation areas at B Plant Complex. This inspection plan is designed to comply with all applicable federal, state and US Department of Energy-Richland Operations Office training requirements. In particular, the requirements of WAC 173-303 ''Dangerous Waste Regulations'' are met by this inspection plan. This inspection plan is designed to provide B Plant Complex with the records and documentation showing that the waste storage and handling program is in compliance with applicable regulations. The plan also includes the requirements for becoming a qualified inspector of waste storage areas and the responsibilities of various individuals and groups at B Plant Complex

  18. B Plant treatment, storage, and disposal (TSD) units inspection plan

    International Nuclear Information System (INIS)

    Beam, T.G.

    1996-01-01

    This inspection plan is written to meet the requirements of WAC 173-303 for operations of a TSD facility. Owners/operators of TSD facilities are required to inspection their facility and active waste management units to prevent and/or detect malfunctions, discharges and other conditions potentially hazardous to human health and the environment. A written plan detailing these inspection efforts must be maintained at the facility in accordance with Washington Administrative Code (WAC), Chapter 173-303, ''Dangerous Waste Regulations'' (WAC 173-303), a written inspection plan is required for the operation of a treatment, storage and disposal (TSD) facility and individual TSD units. B Plant is a permitted TSD facility currently operating under interim status with an approved Part A Permit. Various operational systems and locations within or under the control of B Plant have been permitted for waste management activities. Included are the following TSD units: Cell 4 Container Storage Area; B Plant Containment Building; Low Level Waste Tank System; Organic Waste Tank System; Neutralized Current Acid Waste (NCAW) Tank System; Low Level Waste Concentrator Tank System. This inspection plan complies with the requirements of WAC 173-303. It addresses both general TSD facility and TSD unit-specific inspection requirements. Sections on each of the TSD units provide a brief description of the system configuration and the permitted waste management activity, a summary of the inspection requirements, and details on the activities B Plant uses to maintain compliance with those requirements

  19. Trajectory planning of tokamak flexible in-vessel inspection robot

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Hesheng [Department of Automation, Shanghai Jiao Tong University, 200240 Shanghai (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China, 200240 Shanghai (China); Chen, Weidong, E-mail: wdchen@sjtu.edu.cn [Department of Automation, Shanghai Jiao Tong University, 200240 Shanghai (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China, 200240 Shanghai (China); Lai, Yinping; He, Tao [Department of Automation, Shanghai Jiao Tong University, 200240 Shanghai (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China, 200240 Shanghai (China)

    2015-10-15

    Highlights: • A tokamak flexible in-vessel inspection robot is designed. • Two trajectory planning methods are used to ensure the full coverage of the first wall scanning. • The method is tested on a simulated platform of EAST with the flexible in-vessel inspection robot. • Experimental results show the effectiveness of the proposed algorithm. - Abstract: Tokamak flexible in-vessel inspection robot is mainly designed to carry a camera for close observation of the first wall of the vacuum vessel, which is essential for the maintenance of the future tokamak reactor without breaking the working condition of the vacuum vessel. A tokamak flexible in-vessel inspection robot is designed. In order to improve efficiency of the remote maintenance, it is necessary to design a corresponding trajectory planning algorithm to complete the automatic full coverage scanning of the complex tokamak cavity. Two different trajectory planning methods, RS (rough scanning) and FS (fine scanning), according to different demands of the task, are used to ensure the full coverage of the first wall scanning. To quickly locate the damage position, the first trajectory planning method is targeted for quick and wide-ranging scan of the tokamak D-shaped section, and the second one is for careful observation. Furthermore, both of the two different trajectory planning methods can ensure the full coverage of the first wall scanning with an optimal end posture. The method is tested on a simulated platform of EAST (Experimental Advanced Superconducting Tokamak) with the flexible in-vessel inspection robot, and the results show the effectiveness of the proposed algorithm.

  20. Trajectory planning of tokamak flexible in-vessel inspection robot

    International Nuclear Information System (INIS)

    Wang, Hesheng; Chen, Weidong; Lai, Yinping; He, Tao

    2015-01-01

    Highlights: • A tokamak flexible in-vessel inspection robot is designed. • Two trajectory planning methods are used to ensure the full coverage of the first wall scanning. • The method is tested on a simulated platform of EAST with the flexible in-vessel inspection robot. • Experimental results show the effectiveness of the proposed algorithm. - Abstract: Tokamak flexible in-vessel inspection robot is mainly designed to carry a camera for close observation of the first wall of the vacuum vessel, which is essential for the maintenance of the future tokamak reactor without breaking the working condition of the vacuum vessel. A tokamak flexible in-vessel inspection robot is designed. In order to improve efficiency of the remote maintenance, it is necessary to design a corresponding trajectory planning algorithm to complete the automatic full coverage scanning of the complex tokamak cavity. Two different trajectory planning methods, RS (rough scanning) and FS (fine scanning), according to different demands of the task, are used to ensure the full coverage of the first wall scanning. To quickly locate the damage position, the first trajectory planning method is targeted for quick and wide-ranging scan of the tokamak D-shaped section, and the second one is for careful observation. Furthermore, both of the two different trajectory planning methods can ensure the full coverage of the first wall scanning with an optimal end posture. The method is tested on a simulated platform of EAST (Experimental Advanced Superconducting Tokamak) with the flexible in-vessel inspection robot, and the results show the effectiveness of the proposed algorithm.

  1. 29 CFR 1952.156 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... inspected and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.156 Section 1952.156..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS North Carolina § 1952...

  2. 29 CFR 1952.96 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... inspected and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.96 Section 1952.96..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS South Carolina § 1952...

  3. 29 CFR 1952.381 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... inspected and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.381 Section 1952.381..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Puerto Rico § 1952...

  4. Safety assessment plans for authorization and inspection of radiation sources

    International Nuclear Information System (INIS)

    2002-05-01

    The objective of this TECDOC is to enhance the efficacy, quality and efficiency of the whole regulatory process. It provides advice on good practice administrative procedures for the regulatory process for preparation of applications, granting of authorizations, inspection, and enforcement. It also provides information on the development and use of standard safety assessment plans for authorization and inspection. The plans are intended to be used in conjunction with more detailed advice related to specific practices. In this sense, this TECDOC provides advice on a systematic approach to evaluations of protection and safety while other IAEA Safety Guides assist the user to distinguish between the acceptable and the unacceptable. This TECDOC covers administrative advice to facilitate the regulatory process governing authorization and inspection. It also covers the use of standard assessment and inspection plans and provides simplified plans for the more common, well established uses of radiation sources in medicine and industry, i.e. sources for irradiation facilities, industrial radiography, well logging, industrial gauging, unsealed sources in industry, X ray diagnosis, nuclear medicine, teletherapy and brachytherapy

  5. Safety assessment plans for authorization and inspection of radiation sources

    International Nuclear Information System (INIS)

    1999-09-01

    The objective of this TECDOC is to enhance the efficacy, quality and efficiency of the whole regulatory process. It provides advice on good practice administrative procedures for the regulatory process for preparation of applications, granting of authorizations, inspection, and enforcement. It also provides information on the development and use of standard safety assessment plans for authorization and inspection. The plans are intended to be used in conjunction with more detailed advice related to specific practices. In this sense, this TECDOC provides advice on a systematic approach to evaluations of protection and safety while other IAEA Safety Guides assist the user to distinguish between the acceptable and the unacceptable. This TECDOC covers administrative advice to facilitate the regulatory process governing authorization and inspection. It also covers the use of standard assessment and inspection plans and provides simplified plans for the more common, well established uses of radiation sources in medicine and industry, i.e. sources for irradiation facilities, industrial radiography, well logging, industrial gauging, unsealed sources in industry, X ray diagnosis, nuclear medicine, teletherapy and brachytherapy

  6. Value of information-based inspection planning for offshore structures

    DEFF Research Database (Denmark)

    Irman, Arifian Agusta; Thöns, Sebastian; Leira, Bernt J.

    2017-01-01

    with each inspection strategy. A simplified and generic risk-based inspection planning utilizing pre- posterior Bayesian decision analysis had been proposed by Faber et al. [1] and Straub [2]. This paper provides considerations on the theoretical background and a Value of Information analysis......-based inspection planning. The paper will start out with a review of the state-of-art RBI planning procedure based on Bayesian decision theory and its application in offshore structure integrity management. An example of the Value of Information approach is illustrated and it is pointed to further research......Asset integrity and management is an important part of the oil and gas industry especially for existing offshore structures. With declining oil price, the production rate is an important factor to be maintained that makes integrity of the structures one of the main concerns. Reliability based...

  7. Reliability-based inspection planning of 20MW offshore wind turbine jacket

    DEFF Research Database (Denmark)

    Gintautas, Tomas; Sørensen, John Dalsgaard

    2018-01-01

    This paper presents the application of a risk and reliability based inspection planning framework (RBI) for the InnWind 20MW reference wind turbine jacket sub-structure. A detailed fracture mechanics based fatigue crack growth model is developed and used as basis to derive optimal inspection plans...

  8. Generic Inspection Planning for Steel Structures

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Faber, Michael H.

    2002-01-01

    This paper presents a simplified and practically applicable approach for risk based inspection planning of fatigue sensitive structural details in steel structures. The basic idea is that the fatigue sensitive details are categorized according to their Fatigue Design Factor (FDF) and SN curve. When...

  9. Benefits of Risk Based Inspection Planning for Offshore Structures

    DEFF Research Database (Denmark)

    Straub, D.M.; Goyet, J.; Sørensen, John Dalsgaard

    2006-01-01

    The economical benefits of applying risk-based inspection planning (RBI) for offshore structures subject to fatigue are evaluated based on experiences from past industrial projects. To this end, the factors influencing the cost of inspection, repair and failure of structures are discussed......, the financial benefit of RBI is assessed....

  10. Hanford Facility resource conservation and recovery act permit general inspection plan

    International Nuclear Information System (INIS)

    Beagles, D.B.

    1995-12-01

    The Hanford Facility Resource Conservation and Recovery Act Permit, General Inspection Requirements, includes a requirement that general facility inspections be conducted of the 100, 200 East, 200 West, 300, 400, and 1100 Areas and the banks of the Columbia River. This inspection plan describes the activities that shall be conducted for a general inspection of the Hanford Facility

  11. Double-shell tank ultrasonic inspection plan. Revision 1

    International Nuclear Information System (INIS)

    Pfluger, D.C.

    1994-01-01

    The waste tank systems managed by the Tank Waste Remediation System Division of Westinghouse Hanford Company includes 28 large underground double-shell tanks (DST) used for storing hazardous radioactive waste. The ultrasonic (UT) inspection of these tanks is part of their required integrity assessment (WAC 1993) as described in the tank systems integrity assessment program plan (IAPP) (Pfluger 1994a) submitted to the Ecology Department of the State of Washington. Because these tanks hold radioactive waste and are located underground examinations and inspections must be done remotely from the tank annuli with specially designed equipment. This document describes the UT inspection system (DSTI system), the qualification of the equipment and procedures, field inspection readiness, DST inspections, and post-inspection activities. Although some of the equipment required development, the UT inspection technology itself is the commercially proven and available projection image scanning technique (P-scan). The final design verification of the DSTI system will be a performance test in the Hanford DST annulus mockup that includes the demonstration of detecting and sizing corrosion-induced flaws

  12. Evaluation of sampling schemes for in-service inspection of steam generator tubing

    International Nuclear Information System (INIS)

    Hanlen, R.C.

    1990-03-01

    This report is a follow-on of work initially sponsored by the US Nuclear Regulatory Commission (Bowen et al. 1989). The work presented here is funded by EPRI and is jointly sponsored by the Electric Power Research Institute (EPRI) and the US Nuclear Regulatory Commission (NRC). The goal of this research was to evaluate fourteen sampling schemes or plans. The main criterion used for evaluating plan performance was the effectiveness for sampling, detecting and plugging defective tubes. The performance criterion was evaluated across several choices of distributions of degraded/defective tubes, probability of detection (POD) curves and eddy-current sizing models. Conclusions from this study are dependent upon the tube defect distributions, sample size, and expansion rules considered. As degraded/defective tubes form ''clusters'' (i.e., maps 6A, 8A and 13A), the smaller sample sizes provide a capability of detecting and sizing defective tubes that approaches 100% inspection. When there is little or no clustering (i.e., maps 1A, 20 and 21), sample efficiency is approximately equal to the initial sample size taken. Thee is an indication (though not statistically significant) that the systematic sampling plans are better than the random sampling plans for equivalent initial sample size. There was no indication of an effect due to modifying the threshold value for the second stage expansion. The lack of an indication is likely due to the specific tube flaw sizes considered for the six tube maps. 1 ref., 11 figs., 19 tabs

  13. 7 CFR 27.16 - Inspection; weighing; samples; supervision.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 2 2010-01-01 2010-01-01 false Inspection; weighing; samples; supervision. 27.16 Section 27.16 Agriculture Regulations of the Department of Agriculture AGRICULTURAL MARKETING SERVICE (Standards, Inspections, Marketing Practices), DEPARTMENT OF AGRICULTURE COMMODITY STANDARDS AND STANDARD CONTAINER REGULATIONS COTTON CLASSIFICATION...

  14. Image formation simulation for computer-aided inspection planning of machine vision systems

    Science.gov (United States)

    Irgenfried, Stephan; Bergmann, Stephan; Mohammadikaji, Mahsa; Beyerer, Jürgen; Dachsbacher, Carsten; Wörn, Heinz

    2017-06-01

    In this work, a simulation toolset for Computer Aided Inspection Planning (CAIP) of systems for automated optical inspection (AOI) is presented along with a versatile two-robot-setup for verification of simulation and system planning results. The toolset helps to narrow down the large design space of optical inspection systems in interaction with a system expert. The image formation taking place in optical inspection systems is simulated using GPU-based real time graphics and high quality off-line-rendering. The simulation pipeline allows a stepwise optimization of the system, from fast evaluation of surface patch visibility based on real time graphics up to evaluation of image processing results based on off-line global illumination calculation. A focus of this work is on the dependency of simulation quality on measuring, modeling and parameterizing the optical surface properties of the object to be inspected. The applicability to real world problems is demonstrated by taking the example of planning a 3D laser scanner application. Qualitative and quantitative comparison results of synthetic and real images are presented.

  15. INSPTRAX - The Inspection Targeting, Planning and Tracking Database

    Data.gov (United States)

    U.S. Environmental Protection Agency — The INSPTRAX System tracks Air, RCRA, and Water inspection targeting, planning and tracking information. It is used by the the Air, RCRA, and Water programs to input...

  16. Economic Design of Acceptance Sampling Plans in a Two-Stage Supply Chain

    Directory of Open Access Journals (Sweden)

    Lie-Fern Hsu

    2012-01-01

    Full Text Available Supply Chain Management, which is concerned with material and information flows between facilities and the final customers, has been considered the most popular operations strategy for improving organizational competitiveness nowadays. With the advanced development of computer technology, it is getting easier to derive an acceptance sampling plan satisfying both the producer's and consumer's quality and risk requirements. However, all the available QC tables and computer software determine the sampling plan on a noneconomic basis. In this paper, we design an economic model to determine the optimal sampling plan in a two-stage supply chain that minimizes the producer's and the consumer's total quality cost while satisfying both the producer's and consumer's quality and risk requirements. Numerical examples show that the optimal sampling plan is quite sensitive to the producer's product quality. The product's inspection, internal failure, and postsale failure costs also have an effect on the optimal sampling plan.

  17. Comparative Study on Urban Planning Inspection System in the UK and China

    Institute of Scientific and Technical Information of China (English)

    2012-01-01

    The urban-rural planning inspector system of China is hierarchical supervision over local governments from the Central Government in respect of town and country development. The comparative analysis on planning inspection system of the UK may provide experience in seeking solutions to the problems occurring in the system of China. The planning inspector system of China can be improved in six aspects such as establishing the legal status, setting up the planning inspection agency, completing the personnel management system, enhancing the legal binding force, building the internal and external supervision channel, supplementing the relieve function, and establishing the coordination mechanism of various internal supervisions.

  18. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2011

    Energy Technology Data Exchange (ETDEWEB)

    None

    2012-03-01

    This report summarizes the 2011 annual inspection, sampling, measurement, and maintenance activities performed at the Salmon, Mississippi, Site (Salmon site1). The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County, Mississippi (DOE 2007) specifies the submittal of an annual report of site activities with the results of sample analyses. The Salmon site consists of 1,470 acres. The site is located in Lamar County, Mississippi, approximately 10 miles west of Purvis, Mississippi, and about 21 miles southwest of Hattiesburg, Mississippi.

  19. 7 CFR 52.38c - Statistical sampling procedures for lot inspection of processed fruits and vegetables by attributes.

    Science.gov (United States)

    2010-01-01

    ... FRUITS AND VEGETABLES, PROCESSED PRODUCTS THEREOF, AND CERTAIN OTHER PROCESSED FOOD PRODUCTS 1... processed fruits and vegetables by attributes. 52.38c Section 52.38c Agriculture Regulations of the... inspection of processed fruits and vegetables by attributes. (a) General. Single sampling plans shall be used...

  20. Preliminary inspection of secondary cooling system piping for maintenance plan in JMTR

    International Nuclear Information System (INIS)

    Hanakawa, Hiroki; Hanawa, Yoshio; Izumo, Hironobu; Fukasaku, Akitomi; Nagao, Yoshiharu; Miyazawa, Masataka; Niimi, Motoji

    2008-01-01

    The JMTR is under the refurbishment and will start on FY 2011. The JMTR will operate for about 20 years from 2011. Before this JMTR operation, preliminary inspection of secondary cooling system piping was carried out in order to make a maintenance plan. As the results of this inspection, it was confirmed that the corrosion was reached by piping ingot, or decrease of piping thickness could hardly be observed. Therefore, it was confirmed that the strength or the functionality of the piping had been maintained by usual operation and maintenance. According to the results of this inspection, the basic date for maintenances are confirmed and it is clear to be able to make the maintenances plan in future. (author)

  1. 7 CFR 27.20 - Drawing and handling of samples of cotton; inspection of bales.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 2 2010-01-01 2010-01-01 false Drawing and handling of samples of cotton; inspection... Regulations Inspection and Samples § 27.20 Drawing and handling of samples of cotton; inspection of bales. One sample shall be drawn from the top side of each bale and one from the bottom side. Each such sample shall...

  2. 29 CFR 1952.356 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.356 Section 1952.356..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Arizona § 1952.356...

  3. 29 CFR 1952.206 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.206 Section 1952.206..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Minnesota § 1952.206...

  4. 29 CFR 1952.216 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.216 Section 1952.216..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Maryland § 1952.216...

  5. 29 CFR 1952.236 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.236 Section 1952.236..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Kentucky § 1952.236...

  6. 29 CFR 1952.296 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.296 Section 1952.296..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Nevada § 1952.296...

  7. 29 CFR 1952.226 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.226 Section 1952.226..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Tennessee § 1952.226...

  8. 29 CFR 1952.346 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.346 Section 1952.346..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Wyoming § 1952.346...

  9. 29 CFR 1952.266 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.266 Section 1952.266..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Michigan § 1952.266...

  10. 29 CFR 1952.315 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.315 Section 1952.315..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Hawaii § 1952.315...

  11. 29 CFR 1952.245 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.245 Section 1952.245..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Alaska § 1952.245...

  12. 29 CFR 1952.171 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.171 Section 1952.171..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS California § 1952.171...

  13. 29 CFR 1952.376 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.376 Section 1952.376..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Virginia § 1952.376...

  14. 29 CFR 1952.326 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.326 Section 1952.326..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Indiana § 1952.326...

  15. 29 CFR 1952.271 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.271 Section 1952.271..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Vermont § 1952.271...

  16. 29 CFR 1952.106 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.106 Section 1952.106..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Oregon § 1952.106...

  17. 29 CFR 1952.121 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.121 Section 1952.121..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Washington § 1952.121...

  18. Chain sampling plan (ChSP-1) for desired acceptable quality level (AQL) and limiting quality level (LQL)

    Science.gov (United States)

    Raju, C.; Vidya, R.

    2017-11-01

    Chain Sampling Plan is widely used whenever a small sample attributes plan is required to be used for situations involving destructive products coming out of continuous production process [1, 2]. This paper presents a procedure for the construction and selection of a ChSP-1 by attributes inspection based on membership functions [3]. A procedure using search technique is developed for obtaining the parameters of single sampling plan for a given set of AQL and LQL values. A sample of tables providing ChSP-1 plans for various combinations of AQL and LQL values are presented [4].

  19. 29 CFR 1952.366 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... and copied during normal business hours at the following locations: Office of State Programs... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.366 Section 1952.366..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS New Mexico § 1952.366...

  20. 29 CFR 1956.41 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... business hours at the following locations: Office of State programs, 2100 M Street NW, Room 149, Washington... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1956.41 Section 1956.41..., DEPARTMENT OF LABOR (CONTINUED) STATE PLANS FOR THE DEVELOPMENT AND ENFORCEMENT OF STATE STANDARDS APPLICABLE...

  1. 29 CFR 1952.116 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... copied during normal business hours at the following locations: Office of State Programs, Occupational... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.116 Section 1952.116..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Utah § 1952.116 Where...

  2. 29 CFR 1952.166 - Where the plan may be inspected.

    Science.gov (United States)

    2010-07-01

    ... copied during normal business hours at the following locations: Office of State Programs, Occupational... 29 Labor 9 2010-07-01 2010-07-01 false Where the plan may be inspected. 1952.166 Section 1952.166..., DEPARTMENT OF LABOR (CONTINUED) APPROVED STATE PLANS FOR ENFORCEMENT OF STATE STANDARDS Iowa § 1952.166 Where...

  3. Estimation of inspection effort

    International Nuclear Information System (INIS)

    Mullen, M.F.; Wincek, M.A.

    1979-06-01

    An overview of IAEA inspection activities is presented, and the problem of evaluating the effectiveness of an inspection is discussed. Two models are described - an effort model and an effectiveness model. The effort model breaks the IAEA's inspection effort into components; the amount of effort required for each component is estimated; and the total effort is determined by summing the effort for each component. The effectiveness model quantifies the effectiveness of inspections in terms of probabilities of detection and quantities of material to be detected, if diverted over a specific period. The method is applied to a 200 metric ton per year low-enriched uranium fuel fabrication facility. A description of the model plant is presented, a safeguards approach is outlined, and sampling plans are calculated. The required inspection effort is estimated and the results are compared to IAEA estimates. Some other applications of the method are discussed briefly. Examples are presented which demonstrate how the method might be useful in formulating guidelines for inspection planning and in establishing technical criteria for safeguards implementation

  4. Calculation of parameters for inspection planning and evaluation: mixed-oxide fuel fabrication facilities

    International Nuclear Information System (INIS)

    Reardon, P.T.; Mullen, M.F.

    1982-08-01

    As part of Task C.35 (Calculation of Parameters for Inspection Planning and Evaluation) of the US Program of Technical Assistance to IAEA Safeguards, Pacific Northwest Laboratory has performed some quantitative analyses of IAEA inspection activities for mixed-oxide fuel fabrication facilities. There were four distinct efforts involved in this task. These were as follows: show the effect on a material balance verification of using two variables measurement methods in some strata; perform additional calculations for the reference facility described in STR-89; modify the INSPECT computer programs to be used as an after-inspection analysis tool, as well as a preinspection planning tool; provide written comments and explantations of text and graphs of the first draft of STR-89, Safeguards Considerations for Mixed-Oxide Fuel Element Fabrication Facilities, by W. Bahm, T. Shea, and D. Tolchenkov, System Studies Section, IAEA

  5. Reliability-Based Planning of Inspection, Operation and Maintenance for Offshore Oil & Gas Structures and Wind Turbines

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard

    2011-01-01

    Reliability-based cost-optimal planning of inspection, maintenance and operation has many applications. In this paper applications for planning of inspections for oil & gas jacket structures and of operation and maintenance of offshore wind turbines are described and illustrated by examples....

  6. Generalized procedures for determining inspection sample sizes (related to quantitative measurements). Vol. 1: Detailed explanations

    International Nuclear Information System (INIS)

    Jaech, J.L.; Lemaire, R.J.

    1986-11-01

    Generalized procedures have been developed to determine sample sizes in connection with the planning of inspection activities. These procedures are based on different measurement methods. They are applied mainly to Bulk Handling Facilities and Physical Inventory Verifications. The present report attempts (i) to assign to appropriate statistical testers (viz. testers for gross, partial and small defects) the measurement methods to be used, and (ii) to associate the measurement uncertainties with the sample sizes required for verification. Working papers are also provided to assist in the application of the procedures. This volume contains the detailed explanations concerning the above mentioned procedures

  7. Prospects offered by the departmental plans inspection; Les perspectives offertes par la revision des plans departementaux

    Energy Technology Data Exchange (ETDEWEB)

    Thauvin, Ph.

    2000-07-01

    In the framework of the departmental plans inspection, a detailed document is presented on the domestic and industrial wastes management. These plans forecast an increase of the recycling facing the incineration, a mastership of the costs, a better application of the regulations and a campaign of public information. The indicators of control and the main points of these plans are discussed, supported by tables and definitions. (A.L.B.)

  8. Reliability-Based Design and Planning of Inspection and Monitoring of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Marquez-Dominguez, Sergio

    Maintaining and developing a sustainable wind industry is the main motivation of this PhD thesis entitled “Reliability-based design and planning of inspection and monitoring of offshore wind turbines”. In this thesis, statistical methods and probability theory are important mathematical tools used...... and offshore wind turbine foundations with the aim of improving the design, decreasing structural costs and increasing benefits. Recently, wind energy technology has started to adopt risk and reliability based inspection planning (RBI) as a methodology based on Bayesian decision theories together...

  9. Regulatory inspection activities related to inspection planning, plant maintenance and assessment of safety. Proceedings of an international workshop

    International Nuclear Information System (INIS)

    Van Binnebeek, J.J.; Aubrey, Richard; Grandame, Melvyn; Aro, Ilari; Balloffet, Yves; Klonk, Hartmut; Manzella, Pietro; Koizumi, Hiroyoshi; Bouvrie, E.C. des; Forsberg, Staffan; Lang, Hans-Guenter; Mehew, Robert; Warren, Thomas; Woodhouse, Paul; Gallo, Robert M.; Campbell, Rob; )

    1997-01-01

    The NEA Committee on Nuclear Regulatory Activities (CNRA) believes that an essential factor in ensuring the safety of nuclear installations is the continuing exchange and analysis of technical information and data. To facilitate this exchange the Committee has established Working Groups and Groups of Experts in specialised topics. CNRA believes that safety inspections are a major element in the regulatory authority's efforts to ensure the safe operation of nuclear facilities. Considering the importance of these issues, the Committee has established a special Working Group on Inspection Practices (WGIP). The purpose of WGIP, is to facilitate the exchange of information and experience related to regulatory safety inspections between CNRA Member countries. This was the 3. international workshop held by the WGIP on regulatory inspection activities. The focus of this workshop was on 3 main topics; Inspection Planning, Plant Maintenance and Assessment of Safety. This document presents the proceedings from the workshop, including: workshop programme, results and conclusions, papers and presentations and the list of participants. The main purpose of the Workshop is to provide a forum of exchange of information on the regulatory inspection activities

  10. Regulatory inspection activities related to inspection planning, plant maintenance and assessment of safety. Proceedings of an international workshop

    Energy Technology Data Exchange (ETDEWEB)

    Van Binnebeek, J. J. [AIB-Vincotte Nuclear - AVN, Avenue du Roi, 157, B-1060 Brussels (Belgium); Aubrey, Richard; Grandame, Melvyn [Atomic Energy Control Board - AECB, P.O. Box 1046, Station B, 280 Slater Street, Ottawa, Ontario K1P 5S9 (Canada); Aro, Ilari [Finnish Centre for Radiation and Nuclear Safety - STUK, P.O. Box 14, FIN-00881 Helsinki (Finland); Balloffet, Yves [DRIRE Rhone Alpes, 146, rue Pierre Corneille, 69426 Lyon CEDEX 03 (France); Klonk, Hartmut [Bundesamt fuer Strahlenschutz - BfS, Federal Office for Radiation Protection, Postbox 10 01 49, 38201 Salzgitter 1 (Germany); Manzella, Pietro [A.N.P.A., Via V. Brancati, 48, 1-00144 Roma EUR (Italy); Koizumi, Hiroyoshi [Tech. Stan. Dept. - JAPEIC, Shin-Toranomon Bldg., 1-5-11, Akasaka, Minato-ku, Tokyo 107 (Japan); Bouvrie, E.C. des [Ministry of Social Affairs and Employment, Nuclear Safety Dept. KFD, P.O. Box 90804, 2509 LV The Hague (Netherlands); Forsberg, Staffan [Swedish Nuclear Power Inspectorate - SKI, Klarabergsviadukten 90, S-10658 Stockholm (Sweden); Lang, Hans-Guenter [Section Plant Coordination and Inspection, Swiss Federal Nuclear Safety Inspectorate - HSK, CH-5232 Villigen-HSK (Switzerland); Mehew, Robert; Warren, Thomas; Woodhouse, Paul [Health and Safety Executive - NII, St. Peter' s House, Balliol Road, Bootle, Merseyside L20 3LZ (United Kingdom); Gallo, Robert M. [Special Inspection Branch, US Nuclear Regulatory Commission - US NRC, Mail Stop 0-9A1, Washington, DC 20555 (United States); Campbell, Rob [International Atomic Energy Agency - IAEA, P.O. Box 100, A-1400 Vienna (International Atomic Energy Agency (IAEA))

    1997-07-01

    The NEA Committee on Nuclear Regulatory Activities (CNRA) believes that an essential factor in ensuring the safety of nuclear installations is the continuing exchange and analysis of technical information and data. To facilitate this exchange the Committee has established Working Groups and Groups of Experts in specialised topics. CNRA believes that safety inspections are a major element in the regulatory authority's efforts to ensure the safe operation of nuclear facilities. Considering the importance of these issues, the Committee has established a special Working Group on Inspection Practices (WGIP). The purpose of WGIP, is to facilitate the exchange of information and experience related to regulatory safety inspections between CNRA Member countries. This was the 3. international workshop held by the WGIP on regulatory inspection activities. The focus of this workshop was on 3 main topics; Inspection Planning, Plant Maintenance and Assessment of Safety. This document presents the proceedings from the workshop, including: workshop programme, results and conclusions, papers and presentations and the list of participants. The main purpose of the Workshop is to provide a forum of exchange of information on the regulatory inspection activities.

  11. Activities for turbine maintenance: planning, implementation and evaluation of inspection results

    International Nuclear Information System (INIS)

    Azcue, J.; Sanchez, M. A.; Alvaro, M.

    2014-01-01

    The article will cover the most significant aspects of how Tecnatom carry out the turbine maintenance work, both from the point of view of the inspection itself as the pre-and post tasks associated. Thus, the issues that will be part of the article are the Manual Inspection Service (MISI) and the inspection database, ISI WEB. These tools are essential for planning field work and serve as a guide to run later turbine inspections in different plants. Following this introduction the inspection teams and the techniques used by Tecnatom will be described. finally, the article will contain a small mention about management studies of life and integrity analysis of the turbine that can be performed, as well as involvement in its safe operation that is derived from them. Ultimately, the intention is to provide a comprehensive approach to the issue in question, the turbine maintenance work, so that the reader can get an ideal of the whole process. (Author)

  12. Optimal, Generic Planning of Maintenance and Inspection of Steel Bridges

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Faber, Michael Havbro

    2002-01-01

    Fatigue damage is an important deterioration mechanism for steel bridges. This paper describes a simplified and generic approach for reliability and risk based inspection planning of fatigue sensitive structural details. Fatigue sensitive details are categorized according to their loading charact...

  13. An analysis of OSHA inspections assessing contaminant exposures in general medical and surgical hospitals.

    Science.gov (United States)

    Knight, Jordan L; Sleeth, Darrah K; Larson, Rodney R; Pahler, Leon F

    2013-04-01

    This study analyzed data from the Occupational Safety and Health Administration's (OSHA) Chemical Exposure Health Database to assess contaminant exposures in general medical and surgical hospitals. Seventy-five inspections conducted in these hospitals from 2005 through 2009 were identified. Five categories of inspections were conducted, the three most common being complaint-based, planned, and referral-based inspections. Complaint-based inspections comprised the majority of inspections-55 (73%) of the 75 conducted. The overall violation rate for all inspection types was 68%. This finding was compared to the violation rates of planned inspections (100%), referral-based inspections (83%), and complaint-based inspections (62%). Asbestos was the hazardous substance most commonly sampled and cited by OSHA in hospitals, with 127 samples collected during 24 inspections; 31% of the total 75 inspections resulting in one or more violations were due to asbestos. Copyright 2013, SLACK Incorporated.

  14. ANALYSING ACCEPTANCE SAMPLING PLANS BY MARKOV CHAINS

    Directory of Open Access Journals (Sweden)

    Mohammad Mirabi

    2012-01-01

    Full Text Available

    ENGLISH ABSTRACT: In this research, a Markov analysis of acceptance sampling plans in a single stage and in two stages is proposed, based on the quality of the items inspected. In a stage of this policy, if the number of defective items in a sample of inspected items is more than the upper threshold, the batch is rejected. However, the batch is accepted if the number of defective items is less than the lower threshold. Nonetheless, when the number of defective items falls between the upper and lower thresholds, the decision-making process continues to inspect the items and collect further samples. The primary objective is to determine the optimal values of the upper and lower thresholds using a Markov process to minimise the total cost associated with a batch acceptance policy. A solution method is presented, along with a numerical demonstration of the application of the proposed methodology.

    AFRIKAANSE OPSOMMING: In hierdie navorsing word ’n Markov-ontleding gedoen van aannamemonsternemingsplanne wat plaasvind in ’n enkele stap of in twee stappe na gelang van die kwaliteit van die items wat geïnspekteer word. Indien die eerste monster toon dat die aantal defektiewe items ’n boonste grens oorskry, word die lot afgekeur. Indien die eerste monster toon dat die aantal defektiewe items minder is as ’n onderste grens, word die lot aanvaar. Indien die eerste monster toon dat die aantal defektiewe items in die gebied tussen die boonste en onderste grense lê, word die besluitnemingsproses voortgesit en verdere monsters word geneem. Die primêre doel is om die optimale waardes van die booonste en onderste grense te bepaal deur gebruik te maak van ’n Markov-proses sodat die totale koste verbonde aan die proses geminimiseer kan word. ’n Oplossing word daarna voorgehou tesame met ’n numeriese voorbeeld van die toepassing van die voorgestelde oplossing.

  15. Typical IAEA inspection procedures for model plant

    International Nuclear Information System (INIS)

    Theis, W.

    1984-01-01

    This session briefly refers to the legal basis for IAEA inspections and to their objectives. It describes in detail the planning and performance of IAEA inspections, including the examination of records, the comparison of facility records with State reports, flow and inventory verifications, the design of statistical sampling plans, and Agency's independent verification measurements. In addition, the session addresses the principles of Material Balance and MUF evaluation, as well as the content and format of summary statements and related problems

  16. TMI-2 accident evaluation program sample acquisition and examination plan. Executive summary

    International Nuclear Information System (INIS)

    Russell, M.L.; McCardell, R.K.; Broughton, J.M.

    1985-12-01

    The purpose of the TMI-2 Accident Evaluation Program Sample Acquisition and Examination (TMI-2 AEP SA and E) program is to develop and implement a test and inspection plan that completes the current-condition characterization of (a) the TMI-2 equipment that may have been damaged by the core damage events and (b) the TMI-2 core fission product inventory. The characterization program includes both sample acquisitions and examinations and in-situ measurements. Fission product characterization involves locating the fission products as well as determining their chemical form and determining material association

  17. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2012

    Energy Technology Data Exchange (ETDEWEB)

    None

    2013-03-01

    This report summarizes the 2012 annual inspection, sampling, measurement, and maintenance activities performed at the Salmon, Mississippi, Site (Salmon site). The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County, Mississippi (DOE 2007) specifies the submittal of an annual report of site activities with the results of sample analyses. A revised plan is in preparation. The Long-Term Surveillance Plan for the Salmon, Mississippi, Site is intended for release in 2013. The Salmon site consists of 1,470 acres. The site is located in Lamar County, Mississippi, approximately 10 miles west of Purvis, Mississippi, and about 21 miles southwest of Hattiesburg, Mississippi The State of Mississippi owns the surface real estate subject to certain restrictions related to subsurface penetration. The State is the surface operator; the Mississippi Forestry Commission is its agent. The federal government owns the subsurface real estate (including minerals and some surface features), shares right-of-entry easements with the State, and retains rights related to subsurface monitoring. The U.S. Department of Energy (DOE) Office of Legacy Management (LM), a successor agency to the U.S. Atomic Energy Commission, is responsible for the long-term surveillance of the subsurface real estate

  18. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2012

    International Nuclear Information System (INIS)

    2013-01-01

    This report summarizes the 2012 annual inspection, sampling, measurement, and maintenance activities performed at the Salmon, Mississippi, Site (Salmon site). The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County, Mississippi (DOE 2007) specifies the submittal of an annual report of site activities with the results of sample analyses. A revised plan is in preparation. The Long-Term Surveillance Plan for the Salmon, Mississippi, Site is intended for release in 2013. The Salmon site consists of 1,470 acres. The site is located in Lamar County, Mississippi, approximately 10 miles west of Purvis, Mississippi, and about 21 miles southwest of Hattiesburg, Mississippi The State of Mississippi owns the surface real estate subject to certain restrictions related to subsurface penetration. The State is the surface operator; the Mississippi Forestry Commission is its agent. The federal government owns the subsurface real estate (including minerals and some surface features), shares right-of-entry easements with the State, and retains rights related to subsurface monitoring. The U.S. Department of Energy (DOE) Office of Legacy Management (LM), a successor agency to the U.S. Atomic Energy Commission, is responsible for the long-term surveillance of the subsurface real estate.

  19. Noncontact inspection laser system for characterization of piezoelectric samples

    International Nuclear Information System (INIS)

    Jimenez, F.J.; Frutos, J. de

    2004-01-01

    In this work measurements on a piezoelectric sample in dynamic behavior were taken, in particular, around the frequencies of resonance for the sample where the nonlineal effects are accentuated. Dimension changes in the sample need to be studied as that will allow a more reliable characterization of the piezoelectric samples. The goal of this research is to develop an inspection system able to obtain measurements, using a noncontact laser displacement transducer, also able to visualize, in three-dimensional graphic environment, the displacement that takes place in a piezoelectric sample surface. In resonant mode, the vibration mode of the sample is visualized

  20. Tank waste remediation system nuclear criticality safety inspection and assessment plan

    International Nuclear Information System (INIS)

    VAIL, T.S.

    1999-01-01

    This plan provides a management approved procedure for inspections and assessments of sufficient depth to validate that the Tank Waste Remediation System (TWRS) facility complies with the requirements of the Project Hanford criticality safety program, NHF-PRO-334, ''Criticality Safety General, Requirements''

  1. Analisis Kepatuhan Supervisor Terhadap Implementasi Program Occupational Health & Safety (Ohs) Planned Inspection Di PT. Ccai

    OpenAIRE

    Sarah, Dewi; Ekawati, Ekawati; Widjasena, Baju

    2015-01-01

    The Government has issued Regulation Legislation No. 50 Year 2012 on Health and Safety Management System (SMK3). CCAI is a company that has implemented SMK3. The application of the CCAI SMK3 supported by K3 program one of them is OHS Planned Inspection. This study aimed to analyze the implementation of Occupational Health & Safety (OHS) program Planned Inspection in CCAI. The subjects of this study amounted to five people as the main informants and 2 as an informant triangulation. The res...

  2. Risk-Based Inspection and Maintenance Planning Optimization of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Ramírez, José G. Rangel; Sørensen, John Dalsgaard

    2009-01-01

    A risk-based inspection planning (RBI) approach applied to offshore wind turbines (OWT) is presented, based on RBI methodology developed in the last decades in the oil and gas industry. In wind farm (IWF) and single-alone locations are considered using a code-established turbulence models including...

  3. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2010

    International Nuclear Information System (INIS)

    2011-01-01

    This report summarizes the annual inspection, sampling, measurement, and maintenance activities performed at the Salmon, Mississippi, Site in calendar year 2010. The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County Mississippi (DOE 2007) specifies the submittal of an annual report of site activities with the results of sample analyses. The Salmon, MS, Site is a federally owned site located in Lamar County, MS, approximately 12 miles west of Purvis, MS, and about 21 miles southwest of Hattiesburg, MS (Figure 1). The U.S. Department of Energy (DOE), a successor agency to the U.S. Atomic Energy Commission (AEC), is responsible for the long-term surveillance and maintenance of the 1,470-acre site. DOE's Office of Legacy Management (LM) is the operating agent for the surface and subsurface real estate.

  4. First fuel re-load of Angra-1 reactor - Inspection and hearing plan

    International Nuclear Information System (INIS)

    Pollis, W.; Alvarenga, M.A.B.; Meldonian, N.L.; Paiva, R.L.C. de; Pollis, R.

    1985-01-01

    The plan of inspection and hearing of the first fuel reload of Angra-1 nuclear reactor is detailed. It consists in five steps: receiving and storage of the fuel; reload preparation; activities during; post-reload activities, and preliminary activities. (M.I.)

  5. 7 CFR 27.10 - Supervision of cotton inspection, weighing, sampling; and other duties.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 2 2010-01-01 2010-01-01 false Supervision of cotton inspection, weighing, sampling; and other duties. 27.10 Section 27.10 Agriculture Regulations of the Department of Agriculture AGRICULTURAL MARKETING SERVICE (Standards, Inspections, Marketing Practices), DEPARTMENT OF AGRICULTURE COMMODITY STANDARDS AND STANDARD CONTAINER...

  6. Technology Assessment of the Inspection Readiness Plan in Chemical Weapons Convention Challenge Inspections

    National Research Council Canada - National Science Library

    Woodley, Anthony

    1998-01-01

    ...) Challenge Inspections. The CWC is an intrusive inspection. The Challenge Inspection allows for a team of international inspectors to inspect on very short notice a naval facility suspected of violating the CWC...

  7. Process Improvement to the Inspection Readiness Plan in Chemical Weapons Convention Challenge Inspections

    National Research Council Canada - National Science Library

    Triplett, William

    1997-01-01

    ...) Challenge Inspection. The CWC is an intensive inspection. The Challenge Inspection allows for a team of international inspectors to inspect a naval facility suspected of violating the CWC on very short notice...

  8. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2010

    Energy Technology Data Exchange (ETDEWEB)

    None

    2011-03-01

    This report summarizes the annual inspection, sampling, measurement, and maintenance activities performed at the Salmon, Mississippi, Site in calendar year 2010. The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County Mississippi (DOE 2007) specifies the submittal of an annual report of site activities with the results of sample analyses. The Salmon, MS, Site is a federally owned site located in Lamar County, MS, approximately 12 miles west of Purvis, MS, and about 21 miles southwest of Hattiesburg, MS (Figure 1). The U.S. Department of Energy (DOE), a successor agency to the U.S. Atomic Energy Commission (AEC), is responsible for the long-term surveillance and maintenance of the 1,470-acre site. DOE's Office of Legacy Management (LM) is the operating agent for the surface and subsurface real estate.

  9. Engineering Task Plan for the Ultrasonic Inspection of Hanford Double Shell Tanks (DST) FY2000

    International Nuclear Information System (INIS)

    JENSEN, C.E.

    2000-01-01

    This document facilitates the ultrasonic examination of Hanford double-shell tanks. Included are a plan for engineering activities (individual responsibilities), plan for performance demonstration testing, and a plan for field activities (tank inspection). Also included are a Statement of Work for contractor performance of the work and a protocol to be followed should tank flaws that exceed the acceptance criteria be discovered

  10. 76 FR 65165 - Importation of Plants for Planting; Risk-Based Sampling and Inspection Approach and Propagative...

    Science.gov (United States)

    2011-10-20

    ..., this 14th day of October 2011. Kevin Shea, Acting Administrator, Animal and Plant Health Inspection... DEPARTMENT OF AGRICULTURE Animal and Plant Health Inspection Service [Docket No. APHIS-2011-0092] Importation of Plants for Planting; Risk-Based Sampling and Inspection Approach and Propagative Monitoring and...

  11. Design and implementation of motion planning of inspection and maintenance robot for ITER-like vessel

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Hesheng; Lai, Yinping [Department of Automation, Shanghai Jiao Tong University, Shanghai 200240 (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China (China); Chen, Weidong, E-mail: wdchen@sjtu.edu.cn [Department of Automation, Shanghai Jiao Tong University, Shanghai 200240 (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China (China); Cao, Qixin [Institute of Robotics, Shanghai Jiao Tong University, Shanghai 200240 (China)

    2015-12-15

    Robot motion planning is a fundamental problem to ensure the robot executing the task without clashes, fast and accurately in a special environment. In this paper, a motion planning of a 12 DOFs remote handling robot used for inspecting the working state of the ITER-like vessel and maintaining key device components is proposed and implemented. Firstly, the forward and inverse kinematics are given by analytic method. The work space and posture space of this manipulator are both considered. Then the motion planning is divided into three stages: coming out of the cassette mover, moving along the in-vessel center line, and inspecting the D-shape section. Lastly, the result of experiments verified the performance of the motion design method. In addition, the task of unscrewing/screwing the screw demonstrated the feasibility of system in function.

  12. 26 CFR 301.6104(a)-2 - Public inspection of material relating to pension and other plans.

    Science.gov (United States)

    2010-04-01

    ... pension and other plans. 301.6104(a)-2 Section 301.6104(a)-2 Internal Revenue INTERNAL REVENUE SERVICE... and Returns Returns and Records § 301.6104(a)-2 Public inspection of material relating to pension and...— (i) A pension, profit-sharing, or stock bonus plan under section 401(a), (ii) An annuity plan under...

  13. Post-Closure Inspection, Sampling, and Maintenance Report for the Salmon, Mississippi, Site Calendar Year 2009

    Energy Technology Data Exchange (ETDEWEB)

    None

    2010-10-01

    This report summarizes the annual inspection, sampling, and maintenance activities performed on and near the Salmon, Mississippi, Site in calendar year 2009. The draft Long-Term Surveillance and Maintenance Plan for the Salmon Site, Lamar County, Mississippi (DOE 2007) specifies the submittal of an annual report of site activities and the results of sample analyses. This report complies with the annual report requirement. The Salmon, MS, Site is located in Lamar County, MS, approximately 12 miles west of Purvis, MS, and about 21 miles southwest of Hattiesburg, MS The site encompasses 1,470 acres and is not open to the general public. The U.S. Department of Energy (DOE), a successor agency to the U.S. Atomic Energy Commission (AEC), is responsible for the long-term surveillance and maintenance of the site. The DOE Office of Legacy Management (LM) was assigned responsibility for the site effective October 1, 2006

  14. RPII Inspection and Licensing Activities and Annual Inspection Programme for 2011

    International Nuclear Information System (INIS)

    2010-07-01

    The objective of this report is to provide an overview of inspection activities of the Radiological Protection Institute of Ireland, to examine the evolution in licensee numbers and to outline the rationale in developing annual inspection programmes. All inspection activities are now carried out within the framework of a quality management system including: inspection planning, the training of inspectors, the conduct of inspections as well as inspection follow up and review. The report also provides an overview of the main features of the quality system

  15. RPII Inspection and Licensing Activities and Annual Inspection Programme for 2013

    International Nuclear Information System (INIS)

    2013-04-01

    The objective of this report is to provide an overview of inspection activities of the Radiological Protection Institute of Ireland RPII, to examine the evolution in licensee numbers and to outline the rationale in developing annual inspection programmes. All inspection activities are now carried out within the framework of a quality management system including inspection planning, the training of inspectors, the conduct of inspections as well as post inspection follow up and review. This report also provides an overview of the main features of the quality system

  16. Specified assurance level sampling procedure

    International Nuclear Information System (INIS)

    Willner, O.

    1980-11-01

    In the nuclear industry design specifications for certain quality characteristics require that the final product be inspected by a sampling plan which can demonstrate product conformance to stated assurance levels. The Specified Assurance Level (SAL) Sampling Procedure has been developed to permit the direct selection of attribute sampling plans which can meet commonly used assurance levels. The SAL procedure contains sampling plans which yield the minimum sample size at stated assurance levels. The SAL procedure also provides sampling plans with acceptance numbers ranging from 0 to 10, thus, making available to the user a wide choice of plans all designed to comply with a stated assurance level

  17. Special nuclear material inventory sampling plans

    International Nuclear Information System (INIS)

    Vaccaro, H.S.; Goldman, A.S.

    1987-01-01

    This paper presents improved procedures for obtaining statistically valid sampling plans for nuclear facilities. The double sampling concept and methods for developing optimal double sampling plans are described. An algorithm is described that is satisfactory for finding optimal double sampling plans and choosing appropriate detection and false alarm probabilities

  18. IAEA Sampling Plan

    Energy Technology Data Exchange (ETDEWEB)

    Geist, William H. [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2017-09-15

    The objectives for this presentation are to describe the method that the IAEA uses to determine a sampling plan for nuclear material measurements; describe the terms detection probability and significant quantity; list the three nuclear materials measurement types; describe the sampling method applied to an item facility; and describe multiple method sampling.

  19. Methodology For Reduction Of Sampling On The Visual Inspection Of Developed And Etched Wafers

    Science.gov (United States)

    van de Ven, Jamie S.; Khorasani, Fred

    1989-07-01

    There is a lot of inspection in the manufacturing of semiconductor devices. Generally, the more important a manufacturing step, the higher is the level of inspection. In some cases 100% of the wafers are inspected after certain steps. Inspection is a non-value added and expensive activity. It requires an army of "inspectors," often times expensive equipment and becomes a "bottle neck" when the level of inspection is high. Although inspection helps identify quality problems, it hurts productivity. The new management, quality and productivity philosophies recommend against over inspection. [Point #3 in Dr. Deming's 14 Points for Management (1)] 100% inspection is quite unnecessary . Often the nature of a process allows us to reduce inspection drastically and still maintain a high level of confidence in quality. In section 2, we discuss such situations and show that some elementary probability theory allows us to determine sample sizes and measure the chances of catching a bad "lot" and accepting a good lot. In section 3, we provide an example and application of the theory, and make a few comments on money and time saved because of this work. Finally, in section 4, we draw some conclusions about the new quality and productivity philosophies and how applied statisticians and engineers should study every situation individually and avoid blindly using methods and tables given in books.

  20. A comparison of attribute sampling plans

    International Nuclear Information System (INIS)

    Lanning, B.M.

    1997-05-01

    This report describes, compares, and provides sample size selection criteria for the most common sampling plans for attribute data (i.e., data that is qualitative in nature such as Pass-Fail, Yes-No, Defect-Nondefect data). This report is being issued as a guide in prudently choosing the correct sampling plan to meet statistical plan objectives. The report discusses three types of sampling plans: AQL (Acceptable Quality Level expressed as a percent), RQL (Rejectable Quality Level as a percent), and the AQL/RQL plan which emphasizes both risks simultaneously. These plans are illustrated with six examples, one of which is an inventory of UF 6 cans whose weight must agree within 100 grams of its listed weight to be acceptable

  1. The Use of Explosion Aftershock Probabilities for Planning and Deployment of Seismic Aftershock Monitoring System for an On-site Inspection

    Science.gov (United States)

    Labak, P.; Ford, S. R.; Sweeney, J. J.; Smith, A. T.; Spivak, A.

    2011-12-01

    One of four elements of CTBT verification regime is On-site inspection (OSI). Since the sole purpose of an OSI shall be to clarify whether a nuclear weapon test explosion or any other nuclear explosion has been carried out, inspection activities can be conducted and techniques used in order to collect facts to support findings provided in inspection reports. Passive seismological monitoring, realized by the seismic aftershock monitoring (SAMS) is one of the treaty allowed techniques during an OSI. Effective planning and deployment of SAMS during the early stages of an OSI is required due to the nature of possible events recorded and due to the treaty related constrains on size of inspection area, size of inspection team and length of an inspection. A method, which may help in planning the SAMS deployment is presented. An estimate of aftershock activity due to a theoretical underground nuclear explosion is produced using a simple aftershock rate model (Ford and Walter, 2010). The model is developed with data from the Nevada Test Site and Semipalatinsk Test Site, which we take to represent soft- and hard-rock testing environments, respectively. Estimates of expected magnitude and number of aftershocks are calculated using the models for different testing and inspection scenarios. These estimates can help to plan the SAMS deployment for an OSI by giving a probabilistic assessment of potential aftershocks in the Inspection Area (IA). The aftershock assessment combined with an estimate of the background seismicity in the IA and an empirically-derived map of threshold magnitude for the SAMS network could aid the OSI team in reporting. We tested the hard-rock model to a scenario similar to the 2008 Integrated Field Exercise 2008 deployment in Kazakhstan and produce an estimate of possible recorded aftershock activity.

  2. Sampling inspection for the evaluation of time-dependent reliability of deteriorating systems under imperfect defect detection

    International Nuclear Information System (INIS)

    Kuniewski, Sebastian P.; Weide, Johannes A.M. van der; Noortwijk, Jan M. van

    2009-01-01

    The paper presents a sampling-inspection strategy for the evaluation of time-dependent reliability of deteriorating systems, where the deterioration is assumed to initiate at random times and at random locations. After initiation, defects are weakening the system's resistance. The system becomes unacceptable when at least one defect reaches a critical depth. The defects are assumed to initiate at random times modeled as event times of a non-homogeneous Poisson process (NHPP) and to develop according to a non-decreasing time-dependent gamma process. The intensity rate of the NHPP is assumed to be a combination of a known time-dependent shape function and an unknown proportionality constant. When sampling inspection (i.e. inspection of a selected subregion of the system) results in a number of defect initiations, Bayes' theorem can be used to update prior beliefs about the proportionality constant of the NHPP intensity rate to the posterior distribution. On the basis of a time- and space-dependent Poisson process for the defect initiation, an adaptive Bayesian model for sampling inspection is developed to determine the predictive probability distribution of the time to failure. A potential application is, for instance, the inspection of a large vessel or pipeline suffering pitting/localized corrosion in the oil industry. The possibility of imperfect defect detection is also incorporated in the model.

  3. Improved in-service inspection program for management of degradation in steam generator tubing

    International Nuclear Information System (INIS)

    Kurtz, R.; Heasler, P.; Muscara, J.

    1992-01-01

    This paper presents an overview of significant results from NRC-sponsored research on steam generator tube integrity and inspection. Burst test results are described along with empirical models to relate flaw geometry and size to tube burst pressure. Results of round robin examinations of a retired-from-service steam generator to determine eddy current inspection reliability are presented. An evaluation and comparison of various sampling plans for in-service inspection of steam generators is discussed. Finally, performance demonstration qualification efforts for eddy current inspection systems are described

  4. Comparison of sampling strategies for tobacco retailer inspections to maximize coverage in vulnerable areas and minimize cost.

    Science.gov (United States)

    Lee, Joseph G L; Shook-Sa, Bonnie E; Bowling, J Michael; Ribisl, Kurt M

    2017-06-23

    In the United States, tens of thousands of inspections of tobacco retailers are conducted each year. Various sampling choices can reduce travel costs, emphasize enforcement in areas with greater non-compliance, and allow for comparability between states and over time. We sought to develop a model sampling strategy for state tobacco retailer inspections. Using a 2014 list of 10,161 North Carolina tobacco retailers, we compared results from simple random sampling; stratified, clustered at the ZIP code sampling; and, stratified, clustered at the census tract sampling. We conducted a simulation of repeated sampling and compared approaches for their comparative level of precision, coverage, and retailer dispersion. While maintaining an adequate design effect and statistical precision appropriate for a public health enforcement program, both stratified, clustered ZIP- and tract-based approaches were feasible. Both ZIP and tract strategies yielded improvements over simple random sampling, with relative improvements, respectively, of average distance between retailers (reduced 5.0% and 1.9%), percent Black residents in sampled neighborhoods (increased 17.2% and 32.6%), percent Hispanic residents in sampled neighborhoods (reduced 2.2% and increased 18.3%), percentage of sampled retailers located near schools (increased 61.3% and 37.5%), and poverty rate in sampled neighborhoods (increased 14.0% and 38.2%). States can make retailer inspections more efficient and targeted with stratified, clustered sampling. Use of statistically appropriate sampling strategies like these should be considered by states, researchers, and the Food and Drug Administration to improve program impact and allow for comparisons over time and across states. The authors present a model tobacco retailer sampling strategy for promoting compliance and reducing costs that could be used by U.S. states and the Food and Drug Administration (FDA). The design is feasible to implement in North Carolina. Use of

  5. The time optimal trajectory planning with limitation of operating task for the Tokamak inspecting manipulator

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Hesheng; Lai, Yinping [Department of Automation,Shanghai Jiao Tong University, Shanghai (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China (China); Chen, Weidong, E-mail: wdchen@sjtu.edu.cn [Department of Automation,Shanghai Jiao Tong University, Shanghai (China); Key Laboratory of System Control and Information Processing, Ministry of Education of China (China)

    2016-12-15

    In this paper, a new optimization model of time optimal trajectory planning with limitation of operating task for the Tokamak inspecting manipulator is designed. The task of this manipulator is to inspect the components of Tokamak, the inspecting velocity of manipulator must be limited in the operating space in order to get the clear pictures. With the limitation of joint velocity, acceleration and jerk, this optimization model can not only get the minimum working time along a specific path, but also ensure the imaging quality of camera through the constraint of inspecting velocity. The upper bound of the scanning speed is not a constant but changes according to the observation distance of camera in real time. The relation between scanning velocity and observation distance is estimated by curve-fitting. Experiment has been carried out to verify the feasibility of optimization model, moreover, the Laplace image sharpness evaluation method is adopted to evaluate the quality of images obtained by the proposed method.

  6. The time optimal trajectory planning with limitation of operating task for the Tokamak inspecting manipulator

    International Nuclear Information System (INIS)

    Wang, Hesheng; Lai, Yinping; Chen, Weidong

    2016-01-01

    In this paper, a new optimization model of time optimal trajectory planning with limitation of operating task for the Tokamak inspecting manipulator is designed. The task of this manipulator is to inspect the components of Tokamak, the inspecting velocity of manipulator must be limited in the operating space in order to get the clear pictures. With the limitation of joint velocity, acceleration and jerk, this optimization model can not only get the minimum working time along a specific path, but also ensure the imaging quality of camera through the constraint of inspecting velocity. The upper bound of the scanning speed is not a constant but changes according to the observation distance of camera in real time. The relation between scanning velocity and observation distance is estimated by curve-fitting. Experiment has been carried out to verify the feasibility of optimization model, moreover, the Laplace image sharpness evaluation method is adopted to evaluate the quality of images obtained by the proposed method.

  7. Inspection maintenance and planning of shutdown in thermal electric generating plants

    International Nuclear Information System (INIS)

    Dezordi, W.L.; Correa, D.A.; Kina, M.

    1984-01-01

    The schedule shutdown of an industrial plant and, more specifically, of an electrical generating station, is becoming increasingly important. The major parameters to be taken into account for the planning of such a shutdown are basically of economic-financial nature such as costs of the related services (materials, equipment, manpower, etc), loss of revenue caused by the station's shutdown as well as by the station availability, and other requirements expected from it by the Load Dispatch and consumers. Improving the equipment's performances and the station's availability are the fundamental objectives to be strived for. The authors present in this paper, in an abridged form, the planning tools used for thermal electric generating plants shutdowns for inspections, maintenance and design changes implementation. (Author) [pt

  8. Feasibility of surface sampling in automated inspection of concrete aggregates during bulk transport on a conveyor

    NARCIS (Netherlands)

    Bakker, M.C.M.; Di Maio, F.; Lotfi, S.; Bakker, M.; Hu, M.; Vahidi, A.

    2017-01-01

    Automated optic inspection of concrete aggregates for pollutants (e.g. wood, plastics, gypsum and brick) is required to establish the suitability for reuse in new concrete products. Inspection is more efficient when directly sampling the materials on the conveyor belt instead of feeding them in a

  9. Technical evaluation report on the Third 10-year Interval Inservice Inspection Program Plan: Florida Power and Light Company, Turkey Point Nuclear Power Plant, Units 3 and 4 (Docket Numbers 50-250 and 50-251)

    International Nuclear Information System (INIS)

    Brown, B.W.; Feige, E.J.; Galbraith, S.G.; Porter, A.M.

    1995-02-01

    This report presents the results of the evaluation of the Turkey Point Nuclear Power Plant, Units 3 and 4, Third 10-Year Interval Inservice Inspection Program Plan, Revision 0, submitted September 9, 1993, including the requests for relief from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, requirements that the licensee has determined to be impractical. The Turkey Point Nuclear Power Plant, Units 3 and 4, Third 10-Year Interval Inservice Inspection Program Plan is evaluated in Section 2 of this report. The inservice inspection (ISI) program plan is evaluated for (a) compliance with the appropriate edition/addenda of Section XI, (b) acceptability of the examination sample, (c) correctness of the application of system or component examination exclusion criteria, and (d) compliance with ISI-related commitments identified during previous Nuclear Regulatory Commission (NRC) reviews. The requests for relief are evaluated in Section 3 of this report

  10. 40 CFR 141.802 - Coliform sampling plan.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 22 2010-07-01 2010-07-01 false Coliform sampling plan. 141.802... sampling plan. (a) Each air carrier under this subpart must develop a coliform sampling plan covering each... required actions, including repeat and follow-up sampling, corrective action, and notification of...

  11. A study on the representative sampling survey for the inspection of the clearance level for the radioisotope waste

    International Nuclear Information System (INIS)

    Hong Joo Ahn; Se Chul Sohn; Kwang Yong Jee; Ju Youl Kim; In Koo Lee

    2007-01-01

    Utilization facilities for radioisotope (RI) are increasing annually in South Korea, and the total number was 2,723, as of December 31, 2005. The inspection of a clearance level is a very important problem in order to ensure a social reliance for releasing radioactive materials to the environment. Korean regulations for such a clearance are described in Notice No. 2001-30 of the Ministry of Science and Technology (MOST) and Notice No. 2002-67 of the Ministry of Commerce, Industry and Energy (MOCIE). Most unsealed sources in RI waste drums at a storage facility are low-level beta-emitters with short half-lives, so it is impossible to measure their inventories by a nondestructive analysis. Furthermore, RI wastes generated from hospital, educational and research institutes and industry have a heterogeneous, multiple, irregular, and a small quantity of a waste stream. This study addresses a representative (master) sampling survey and analysis plan for RI wastes because a complete enumeration of waste drums is impossible and not desirable in terms of a cost and efficiency. The existing approaches to a representative sampling include a judgmental, simple random, stratified random, systematic grid, systematic random, composite, and adaptive sampling. A representative sampling plan may combine two or more of the above sampling approaches depending on the type and distribution of a waste stream. Stratified random sampling (constrained randomization) is proven to be adequate for a sampling design of a RI waste regarding a half-life, surface dose, undertaking time to a storage facility, and type of waste. The developed sampling protocol includes estimating the number of drums within a waste stream, estimating the number of samples, and a confirmation of the required number of samples. The statistical process control for a quality assurance plan includes control charts and an upper control limit (UCL) of 95% to determine whether a clearance level is met or not. (authors)

  12. Czech interim spent fuel storage facility: operation experience, inspections and future plans

    International Nuclear Information System (INIS)

    Fajman, V.; Bartak, L.; Coufal, J.; Brzobohaty, K.; Kuba, S.

    1999-01-01

    The paper describes the situation in the spent fuel management in the Czech Republic. The interim Spent Fuel Storage Facility (ISFSF) at Dukovany, which was commissioned in January 1997 and is using dual transport and storage CASTOR - 440/84 casks, is briefly described. The authors deal with their experience in operating and inspecting the ISFSF Dukovany. The structure of the basic safety document 'Limits and Conditions of Normal Operation' is also mentioned, including the experience of the performance. The inspection activities focused on permanent checking of the leak tightness of the CASTOR 440/84 casks, the maximum cask temperature and inspections monitoring both the neutron and gamma dose rate as well as the surface contamination. The results of the inspections are mentioned in the presentation as well. The operator's experience with re-opening partly loaded and already dried CASTOR-440/84 cask, after its transport from NPP Jaslovske Bohunice to the NPP Dukovany is also described. The paper introduces briefly the concept of future spent fuel storage both from the NPP Dukovany and the NPP Temelin, as prepared by the CEZ. The preparatory work for the Central Interim Spent Nuclear Fuel Storage Facility (CISFSF) in the Czech Republic and the information concerning the planned storage technology for this facility is discussed in the paper as well. The authors describe the site selection process and the preparatory steps concerning new spent fuel facility construction including the Environmental Impact Assessment studies. (author)

  13. A High-Speed Train Operation Plan Inspection Simulation Model

    Directory of Open Access Journals (Sweden)

    Yang Rui

    2018-01-01

    Full Text Available We developed a train operation simulation tool to inspect a train operation plan. In applying an improved Petri Net, the train was regarded as a token, and the line and station were regarded as places, respectively, in accordance with the high-speed train operation characteristics and network function. Location change and running information transfer of the high-speed train were realized by customizing a variety of transitions. The model was built based on the concept of component combination, considering the random disturbance in the process of train running. The simulation framework can be generated quickly and the system operation can be completed according to the different test requirements and the required network data. We tested the simulation tool when used for the real-world Wuhan to Guangzhou high-speed line. The results showed that the proposed model can be developed, the simulation results basically coincide with the objective reality, and it can not only test the feasibility of the high-speed train operation plan, but also be used as a support model to develop the simulation platform with more capabilities.

  14. Noble Gas Sampling and Detection Methods for On-Site Inspections in Support of CTBT

    International Nuclear Information System (INIS)

    Wieslander, J.S.E.

    2015-01-01

    The On-Site Inspections (OSI) constitutes the final verification measure under the CTBT, and are conducted to verify States Parties' compliance with the Comprehensive Nuclear-Test-Ban Treaty (CTBT). An on-site inspection is launched to establish whether or not a nuclear explosion has been carried out and during such an inspection, facts might also be gathered to identify a possible violator of the Treaty. The Treaty lists all activities and techniques that are permitted and one of these is the environmental sampling of noble gases (NG) in the air and underground, which can be deployed at any time during an OSI. The CTBT relevant isotopes are Xe-133, 133m, 131m, 135 and Ar-37. The samples are primarily to be analyzed on-site, although the treaty also allows off-site analysis in designated laboratories if necessary. Stringent procedures ensure the security, integrity and confidentiality of the samples throughout the sampling and analysis process — all taking place in the field. Over the past decade the techniques for NG sampling, processing and analysis of both atmospheric and subsoil NG samples have been developed further in order to fit to the conditions and requirements during an OSI. This has been a major international effort with a global set of collaborators. Especially during the past three years the efforts intensified in order to finalize the scientific and technical developments for the Integrated Field Exercise, November 2014 (IFE14). This presentation will provide an overview of the current status of the OSI NG sampling regime and the OSI NG Field Laboratory to be deployed in IFE14, together with more technical descriptions of methods and equipment as well as a short discussion on potential future developments and alternative applications as applicable. (author)

  15. Computational framework for risk-based planning of inspections, maintenance, and condition monitoring using discrete Bayesian networks

    DEFF Research Database (Denmark)

    Nielsen, Jannie Sønderkær; Sørensen, John Dalsgaard

    2018-01-01

    This paper presents a computational framework for risk-based planning of inspections and repairs for deteriorating components. Two distinct types of decision rules are used to model decisions: simple decision rules that depend on constants or observed variables (e.g. inspection outcome...... expecte d life-cycle costs. For advanced decision rules, simulations are performed to estimate the expected costs, and dBNs are used within the simulations for decision-making. Information from inspections and condition monitoring are included if available. An example in the paper demonstrates...... the framework and the implemented strategies and decision rules, including various types of condition-based maintenance. The strategies using advanced decision rules lead to reduced costs compared to the simple decision rules when condition monitoring is applied, and the value of condition monitoring...

  16. RPII Inspection and Licensing Activities and Annual Inspection Programme for 2012

    International Nuclear Information System (INIS)

    2012-04-01

    The purpose of this document is to promote transparency in the activities of the RPII. It explains aspects of the internal workings of the Regulation and Information Management Division of the Institute to aid understanding of the processes and decisions of that Division which may impact on licensees and other interested parties. The objective of the report is to provide an overview of inspection activities of the RPII, to examine the evolution in licensee numbers and to outline the rationale in developing annual inspection programmes. All inspection activities are now carried out within the framework of a quality management system including; inspection planning, the training of inspectors, the conduct of inspections, as well as post inspection follow up and review. This report also provides an overview of the main features of the quality system

  17. Statistical Sampling For In-Service Inspection Of Liquid Waste Tanks At The Savannah River Site

    International Nuclear Information System (INIS)

    Harris, S.

    2011-01-01

    Savannah River Remediation, LLC (SRR) is implementing a statistical sampling strategy for In-Service Inspection (ISI) of Liquid Waste (LW) Tanks at the United States Department of Energy's Savannah River Site (SRS) in Aiken, South Carolina. As a component of SRS's corrosion control program, the ISI program assesses tank wall structural integrity through the use of ultrasonic testing (UT). The statistical strategy for ISI is based on the random sampling of a number of vertically oriented unit areas, called strips, within each tank. The number of strips to inspect was determined so as to attain, over time, a high probability of observing at least one of the worst 5% in terms of pitting and corrosion across all tanks. The probability estimation to determine the number of strips to inspect was performed using the hypergeometric distribution. Statistical tolerance limits for pit depth and corrosion rates were calculated by fitting the lognormal distribution to the data. In addition to the strip sampling strategy, a single strip within each tank was identified to serve as the baseline for a longitudinal assessment of the tank safe operational life. The statistical sampling strategy enables the ISI program to develop individual profiles of LW tank wall structural integrity that collectively provide a high confidence in their safety and integrity over operational lifetimes.

  18. Waste classification sampling plan

    International Nuclear Information System (INIS)

    Landsman, S.D.

    1998-01-01

    The purpose of this sampling is to explain the method used to collect and analyze data necessary to verify and/or determine the radionuclide content of the B-Cell decontamination and decommissioning waste stream so that the correct waste classification for the waste stream can be made, and to collect samples for studies of decontamination methods that could be used to remove fixed contamination present on the waste. The scope of this plan is to establish the technical basis for collecting samples and compiling quantitative data on the radioactive constituents present in waste generated during deactivation activities in B-Cell. Sampling and radioisotopic analysis will be performed on the fixed layers of contamination present on structural material and internal surfaces of process piping and tanks. In addition, dose rate measurements on existing waste material will be performed to determine the fraction of dose rate attributable to both removable and fixed contamination. Samples will also be collected to support studies of decontamination methods that are effective in removing the fixed contamination present on the waste. Sampling performed under this plan will meet criteria established in BNF-2596, Data Quality Objectives for the B-Cell Waste Stream Classification Sampling, J. M. Barnett, May 1998

  19. Summary report for 1990 inservice inspection (ISI) of SRS 100-L reactor tank

    International Nuclear Information System (INIS)

    Morrison, J.M.; Loibl, M.W.

    1991-01-01

    The integrity of the SRS reactor tanks is a key factor affecting their suitability for continued service since, unlike the external piping system and components, the tanks are virtually irreplaceable. Cracking in various areas of the process water piping systems has occurred beginning in about 1960 as a result of several degradation mechanisms, chiefly intergranular stress corrosion cracking (IGSCC) and chloride-induced transgranular cracking. The primary objective of this inspection was to determine if the accessible welds and selected portions of base metal in the L Reactor tank wall contain any indications of IGSCC. This inspection included areas in and beyond the weld HAZ, extending out as far as two to three inches from the centerline of the welds, plus selected areas of base metal at the intersection of the main tank vertical and mid-girth welds. No evidence of such degradation was found in any of the areas examined. Further, additional inspections were conducted of areas that had been damaged and repaired during original fabrication, and on a sample of areas containing linear indications observed during the 1986 visual inspection of the tank. No evidence of IGSCC or other service induced degradation was detected in these areas, either. The inspection was initially planned to cover a minimum of 60% of the accessible welds, plus repair areas and a sample of the indications from the 1986 visual inspection. Direction was received from DOE while the inspection was in progress to expand the scope to cover 100% of the accessible weld areas, and the plan was adjusted accordingly. Initial setup of the tank, which prior to inspection contained Mark 60B target assemblies and nearly a full charge of Mark 22 fuel assemblies, began on October 15, 1990. The inspection was completed on April 12, 1991

  20. Development of in-service inspection plans for nuclear components at the Surry 1 nuclear power station

    International Nuclear Information System (INIS)

    Vo, T.V.; Simonen, F.A.; Doctor, S.R.; Smith, B.W.; Gore, B.F.

    1993-01-01

    As part of the nondestructive evaluation reliability program sponsored by the US Nuclear Regulatory Commission at Pacific Northwest Laboratory, a methodology has been developed for establishing in-service inspection priorities of nuclear power plant components. The method uses results of probabilistic risk assessment in conjunction with the techniques of failure modes and effects analysis to identify and prioritize the most risk-important systems and components for inspection at nuclear power plants. Surry nuclear power station unit 1 was selected for demonstrating the methodology. The specific systems selected for analysis were the reactor pressure vessel, the reactor coolant, the low pressure injection including the accumulators, and the auxiliary feedwater. The results provide a risk-based ranking of components that can be used to establish a prioritization of the components and a basis for developing improved in-service inspection plans at nuclear power plants

  1. Appendix F - Sample Contingency Plan

    Science.gov (United States)

    This sample Contingency Plan in Appendix F is intended to provide examples of contingency planning as a reference when a facility determines that the required secondary containment is impracticable, pursuant to 40 CFR §112.7(d).

  2. Minimum variance and variance of outgoing quality limit MDS-1(c1, c2) plans

    Science.gov (United States)

    Raju, C.; Vidya, R.

    2016-06-01

    In this article, the outgoing quality (OQ) and total inspection (TI) of multiple deferred state sampling plans MDS-1(c1,c2) are studied. It is assumed that the inspection is rejection rectification. Procedures for designing MDS-1(c1,c2) sampling plans with minimum variance of OQ and TI are developed. A procedure for obtaining a plan for a designated upper limit for the variance of the OQ (VOQL) is outlined.

  3. Tools for Inspecting and Sampling Waste in Underground Radioactive Storage Tanks with Small Access Riser Openings

    International Nuclear Information System (INIS)

    Nance, T.A.

    1998-01-01

    Underground storage tanks with 2 inches to 3 inches diameter access ports at the Department of Energy's Savannah River Site have been used to store radioactive solvents and sludge. In order to close these tanks, the contents of the tanks need to first be quantified in terms of volume and chemical and radioactive characteristics. To provide information on the volume of waste contained within the tanks, a small remote inspection system was needed. This inspection system was designed to provide lighting and provide pan and tilt capabilities in an inexpensive package with zoom abilities and color video. This system also needed to be utilized inside of a plastic tent built over the access port to contain any contamination exiting from the port. This system had to be build to travel into the small port opening, through the riser pipe, into the tank evacuated space, and out of the riser pipe and access port with no possibility of being caught and blocking the access riser. Long thin plates were found in many access riser pipes that blocked the inspection system from penetrating into the tank interiors. Retrieval tools to clear the plates from the tanks using developed sampling devices while providing safe containment for the samples. This paper will discuss the inspection systems, tools for clearing access pipes, and solvent sampling tools developed to evaluate the tank contents of the underground solvent storage tanks

  4. FUZZY ACCEPTANCE SAMPLING AND CHARACTERISTIC CURVES

    Directory of Open Access Journals (Sweden)

    Ebru Turano?lu

    2012-02-01

    Full Text Available Acceptance sampling is primarily used for the inspection of incoming or outgoing lots. Acceptance sampling refers to the application of specific sampling plans to a designated lot or sequence of lots. The parameters of acceptance sampling plans are sample sizes and acceptance numbers. In some cases, it may not be possible to define acceptance sampling parameters as crisp values. These parameters can be expressed by linguistic variables. The fuzzy set theory can be successfully used to cope with the vagueness in these linguistic expressions for acceptance sampling. In this paper, the main distributions of acceptance sampling plans are handled with fuzzy parameters and their acceptance probability functions are derived. Then the characteristic curves of acceptance sampling are examined under fuzziness. Illustrative examples are given.

  5. Calculation of parameters for inspection planning and evaluation: low enriched uranium conversion and fuel fabrication facilities

    International Nuclear Information System (INIS)

    Reardon, P.T.; Mullen, M.F.; Harms, N.L.

    1981-02-01

    As part of Task C.35 (Calculation of Parameters for Inspection Planning and Evaluation) of the US Program of Technical Assistance to IAEA Safeguards, Pacific Northwest Laboratory has performed some quantitative analyses of IAEA inspection activities at low-enriched uranium (LEU) conversion and fuel fabrication facilities. This report presents the results and conclusions of those analyses. Implementation of IAEA safeguards at LEU conversion and fuel fabrication facilities must take into account a variety of practical problems and constraints. One of the key concerns is the problem of flow verification, especially product verification. The objective of this report is to help put the problem of flow verification in perspective by presenting the results of some specific calculations of inspection effort and probability of detection for various product measurement strategies. In order to provide quantitative information about the advantages and disadvantages of the various strategies, eight specific cases were examined

  6. Hanford site transuranic waste sampling plan

    International Nuclear Information System (INIS)

    GREAGER, T.M.

    1999-01-01

    This sampling plan (SP) describes the selection of containers for sampling of homogeneous solids and soil/gravel and for visual examination of transuranic and mixed transuranic (collectively referred to as TRU) waste generated at the U.S. Department of Energy (DOE) Hanford Site. The activities described in this SP will be conducted under the Hanford Site TRU Waste Certification Program. This SP is designed to meet the requirements of the Transuranic Waste Characterization Quality Assurance Program Plan (CAO-94-1010) (DOE 1996a) (QAPP), site-specific implementation of which is described in the Hanford Site Transuranic Waste Characterization Program Quality Assurance Project Plan (HNF-2599) (Hanford 1998b) (QAPP). The QAPP defines the quality assurance (QA) requirements and protocols for TRU waste characterization activities at the Hanford Site. In addition, the QAPP identifies responsible organizations, describes required program activities, outlines sampling and analysis strategies, and identifies procedures for characterization activities. The QAPP identifies specific requirements for TRU waste sampling plans. Table 1-1 presents these requirements and indicates sections in this SP where these requirements are addressed

  7. Deployment Plan for Small Roving Annulus Inspection Vehicle

    International Nuclear Information System (INIS)

    Minichan, R.

    2002-01-01

    The Small Roving Annulus Inspection Vehicle (SRAIV) is a modified commercially available wall crawler designed to supplement the In-Service Inspection (ISI) of Savannah River Site (SRS) Waste tanks. The SRAIV provides an improved capability to achieve a more complete inspection of the tank walls than existing methods. The SRAIV will be deployed through annulus risers in the tank to gain access to tank walls requiring inspection. The SRAIV will be deployed using a manually operated deployment pole and will be coupled to the wall using permanent magnet wheels. Navigation will be performed from the remote console where pictorial views can be displayed from the on-board cameras. The unit will incorporate multiple UT transducers for traditional weld examination. In addition, a specially developed Tandem Synthetic Aperture Focusing Technique (TSAFT) UT scanning bridge can be attached to provide further investigation of the knuckle region while the vehicle remains on the vertical surface of the tank wall. In summary, the SRAIV will provide features that enhance and expand the capability of the SRS ISI program

  8. Planning and programming of pre-operational and in-service inspections

    International Nuclear Information System (INIS)

    Udaondo, M.S.

    1984-01-01

    After a brief mention of the actual scope of in-service inspection work, conclusions are presented that relate to the preparations for inspections, making use of experience acquired since 1972 at 11 nuclear power plants in Spain which have commissioned such studies from one particular organization, and analyses are given of the advantages to be gained therefrom. Three different aspects of preparations for inspections are considered: (a) man-hour estimates and the duration of in-service inspections; (b) the sequence of action during a pre-operational inspection (assuming a typical functional organization) from definition of the codes of practice and standards applicable up to the issue of the final report and the schedule for distribution of the annual work load to be invested in a typical project, as a result of combining the two previous estimates, and (c) the documentary aspect of preparations for an inspection during a scheduled outage, as related to the various documents to be drawn up and their contents. Reference is made to the general training to be given to the staff in charge of inspection activities so as to provide them with information on, and a perspective of, the in-service inspection jobs required. (author)

  9. 7 CFR 301.92-11 - Inspection and sampling protocols.

    Science.gov (United States)

    2010-01-01

    ... determinations of apparent pest freedom for such nurseries must occur at the time when the best expression of... associated articles and nearby plants. Inspectors must conduct inspections at times when the best expression... annually for symptoms of Phytophthora ramorum. Inspections and determinations of freedom from evidence of...

  10. A study on in-pipe inspection mobile robots, 3

    International Nuclear Information System (INIS)

    Fukuda, Toshio; Hosokai, Hidemi; Uemura, Masahiro.

    1990-01-01

    This paper deals with inspection path planning for in-pipe inspection mobile robots which have the capability of moving through complicated pipeline networks. It is imperative that the robot systems have an inspection path planning system for such networks for their reasonable and rational operation, controlled by themselves or by the operators. The planning mainly requires two projects: the selection of the place to put the robot in or out, and the generation of the paths in the networks. This system provides the for complicated problems with plural inspection points using a basic strategy of systematically producing patterns and dividing partial problems of simple searches based on rules. (author)

  11. Use of knowledge based systems for rational reliability analysis based inspection and maintenance planning for offshore structures

    International Nuclear Information System (INIS)

    Tang, M.X.; Dharmavasan, S.; Peers, S.M.C.

    1994-01-01

    The structural integrity of fixed offshore platforms is ensured by periodic inspections. In the past, decisions made as to when, where and how to inspect have been made by engineers using rules-of-thumb and general planning heuristics. It is now hoped that more rational inspection and maintenance scheduling may be carried out by applying recently developed techniques based on structural reliability methods. However, one of the problems associated with a theoretical approach is that it is not always possible to incorporate all the constraints that are present in a practical situation. These constraints modify the decisions made for analysis data input and the interpretation of the analysis results. Knowledge based systems provide a mean of encapsulating several different forms of information and knowledge within a computer system and hence can overcome this problem. In this paper, a prototype system being developed for integrating reliability based analysis with other constraints for inspection scheduling will be described. In addition, the scheduling model and the algorithms to carry out the scheduling will be explained. Furthermore, implementation details are also given

  12. 2016 Groundwater Monitoring and Inspection Report Gnome-Coach, New Mexico, Site January 2017

    Energy Technology Data Exchange (ETDEWEB)

    Kreie, Ken [USDOE Office of Legacy Management, Washington, DC (United States); Findlay, Rick [Navarro Research and Engineering, Inc., Oak Ridge, TN (United States)

    2017-01-01

    The Gnome-Coach, New Mexico, Site was the location of an underground nuclear test in 1961 and a groundwater tracer test in 1963. Residual contamination remaining in the subsurface from these events requires long-term oversight. The Long-Term Surveillance and Maintenance Plan for the site describes the U.S. Department of Energy Office of Legacy Management’s (LM’s) plan for monitoring groundwater (radiochemical sampling and hydraulic head measurements), inspecting the site, maintaining the site’s institutional controls, evaluating and reporting data, and documenting the site’s records and data management processes. Groundwater monitoring and site inspection activities are conducted annually. This report summarizes the results of these activities conducted during the October 2015 through September 2016 reporting period. The site inspection and annual sampling were conducted on January 27, 2016. At the time of the site inspection, the signs installed near the emplacement shaft, near well USGS-1, and around the perimeter of the site were observed as being in good condition, as were the roads, wellheads, and Project Gnome monument. No new groundwater extraction wells or oil and gas wells were installed during this reporting period on the site or in the sections that surround the site. One new application was received by the New Mexico Oil Conservation Division to install a salt water disposal well approximately 0.8 miles northeast of the Project Gnome monument. The proposed well has a planned completion depth of 15,500 feet below ground surface, but as of November 2016 a drill date has not been established.

  13. Boresonic inspection of power plant rotors

    International Nuclear Information System (INIS)

    Rennie, I.S.

    1990-01-01

    Continental Field Machining and NEI Parsons together are able to provide an on site machining and boresonic inspection service. NEI Parsons existing boresonic equipment is described together with a summary of results obtained during the inspection of eighty rotors. A computer controlled automatic inspection system, planned to be in operation early in 1990, is also described

  14. Northeast Inspection Services, Inc. boresonic inspection system evaluation

    International Nuclear Information System (INIS)

    Nottingham, L.D.; Sabourin, P.F.; Presson, J.H.

    1993-04-01

    Turbine rotor reliability and remaining life assessment are continuing concerns to electric utilities. Over the years, boresonic inspection and evaluation have served as primary components in rotor remaining life assessment. Beginning with an evaluation of TREES by EPRI in 1982, a series of reports that document the detection and sizing capabilities of several boresonic systems have been made available. These studies should provide utilities with a better understanding of system performance and lead to improved reliability when predicting rotor remaining life. In 1990, the procedures followed for evaluating rotor boresonic performance capabilities were changed to transfer a greater portion of the data analysis function to the participating vendor. This change from previous policy was instituted so that the evaluation results would better reflect the ''final answer'' that a vendor would provide in a real rotor inspection and also to reduce the cost of an evaluation. Among the first vendors to participate in the new performance demonstration was Northeast Inspection Services, Inc. (NISI). The tests reported herein were conducted by NISI personnel under the guidelines of the new plan. Details of the new evaluation plan are also presented. Rotor bore blocks containing surface-connected fatigue cracks, embedded glass beads, and embedded radial-axial oriented disks were used in the evaluation. Data were collected during twenty-five independent passes through the blocks. The evaluation consisted of statistical characterization of the detection capabilities, flaw sizing and location accuracy, and repeatability of the inspection system. The results of the evaluation are included in this report

  15. Appendix E - Sample Production Facility Plan

    Science.gov (United States)

    This sample Spill Prevention, Control and Countermeasure (SPCC) Plan in Appendix E is intended to provide examples and illustrations of how a production facility could address a variety of scenarios in its SPCC Plan.

  16. 7 CFR 27.89 - Expenses; inspection; sampling.

    Science.gov (United States)

    2010-01-01

    ... Agriculture Regulations of the Department of Agriculture AGRICULTURAL MARKETING SERVICE (Standards, Inspections, Marketing Practices), DEPARTMENT OF AGRICULTURE COMMODITY STANDARDS AND STANDARD CONTAINER REGULATIONS COTTON CLASSIFICATION UNDER COTTON FUTURES LEGISLATION Regulations Costs of Classification and...

  17. Supervision and inspection plans of plants activities

    International Nuclear Information System (INIS)

    Feijoo, J. P.

    2009-01-01

    Any idea of hierarchization between supervisor and supervised in inspection and supervision activities should necessarily be dismissed, and the independence of the supervisor when executing has tasks should be guaranteed. The inspection and supervision program enable the detection and resolution of materials and human problems alike. In addition, they are a solution to anticipate potential problems in the future, which results in a very significant reduction of industrial accidents and human errors, as well as better use and upkeep of equipment. With these programs we improve our management and our work, and without a doubt they help to strengthen the safety culture in Cofrentes Nuclear Power Plant. (Author)

  18. A portable solution to enable guided ultrasonic inspection

    International Nuclear Information System (INIS)

    Enenkel, Laurent; Buechler, Johannes; Poirier, Jerome; Jervis David

    2012-01-01

    This paper describes the development and application of an innovative ultrasonic (UT) inspection system, which is 100% guided and menu-driven to reduce human error and ensure both inspection accuracy and productivity in the reliable and accurate non-destructive testing (NDT) of shafts, tubes, pipes, and other components and structures. Set-up is menu-directed with the minimum of instrument-specific training, allowing the integral operating software to calculate all the ultrasonic parameters for each task according to the inspection procedure and create an easy-to-follow inspection plan, using either phased array or conventional UT. The operator then scans the work piece, with an encoded scanner, which ensures that the inspection plan is strictly followed. Inspection data is transmitted to a review station in the industry-accepted, non-proprietary DICONDE protocol, allowing advanced analysis tools, such as real time, volume corrected imaging, to allow easier and more reliable image interpretation. By using GEs Rhythm software platform, inspection data can be reviewed and shared, reports generated and inspection results archived for traceability, tracking or further analysis.

  19. Long-Term Ecological Monitoring Field Sampling Plan for 2007

    International Nuclear Information System (INIS)

    T. Haney R. VanHorn

    2007-01-01

    This field sampling plan describes the field investigations planned for the Long-Term Ecological Monitoring Project at the Idaho National Laboratory Site in 2007. This plan and the Quality Assurance Project Plan for Waste Area Groups 1, 2, 3, 4, 5, 6, 7, 10, and Removal Actions constitute the sampling and analysis plan supporting long-term ecological monitoring sampling in 2007. The data collected under this plan will become part of the long-term ecological monitoring data set that is being collected annually. The data will be used to determine the requirements for the subsequent long-term ecological monitoring. This plan guides the 2007 investigations, including sampling, quality assurance, quality control, analytical procedures, and data management. As such, this plan will help to ensure that the resulting monitoring data will be scientifically valid, defensible, and of known and acceptable quality

  20. Long-Term Ecological Monitoring Field Sampling Plan for 2007

    Energy Technology Data Exchange (ETDEWEB)

    T. Haney

    2007-07-31

    This field sampling plan describes the field investigations planned for the Long-Term Ecological Monitoring Project at the Idaho National Laboratory Site in 2007. This plan and the Quality Assurance Project Plan for Waste Area Groups 1, 2, 3, 4, 5, 6, 7, 10, and Removal Actions constitute the sampling and analysis plan supporting long-term ecological monitoring sampling in 2007. The data collected under this plan will become part of the long-term ecological monitoring data set that is being collected annually. The data will be used t determine the requirements for the subsequent long-term ecological monitoring. This plan guides the 2007 investigations, including sampling, quality assurance, quality control, analytical procedures, and data management. As such, this plan will help to ensure that the resulting monitoring data will be scientifically valid, defensible, and of known and acceptable quality.

  1. Trends of degradation in steam generator tubes of Krsko NPP before the last planned inspection

    International Nuclear Information System (INIS)

    Cizelj, L.; Dvorsek, T.; Androjna, F.

    1998-01-01

    Full-length inspection of all active tubes in both Krsko steam generators resulted in a huge amount of inspection records. A computerized database was developed by Reactor Engineering division to accelerate the management of about 200.000 records. The database was designed to support the development and decision related to the plugging criteria for damaged tubes and is utilized to gain as much experience concerning the degradation of SG tube as possible. In this paper, two prevailing group of data are statistically analyzed: the axial cracks in expansion transitions at the top of tube sheet (TTS) and Outside Diameter Stress Corrosion Cracking at tube support plates (TSP). Especially ODSCC caused a vast majority of repaired tubes (e.g., plugs and sleeves). The influence of plant startups involving oxidizing transient on the repair rates of tubes affected by ODSCC is analyzed in some detail. The results are promising and show excellent correlation in SG 2 and reasonable fit in SG 1. Predictions of maximum expected number of tubes repaired due to ODSCC at the last planned inspection is given as 67 in SG 1 and 400 in SG 2. (author)

  2. 33 CFR 164.80 - Tests, inspections, and voyage planning.

    Science.gov (United States)

    2010-07-01

    ... searchlights. (5) Terminal gear. Visual inspection of tackle; of connections of bridle and towing pendant, if.... (2) Terminal gear. Visual inspection of tackle; of connections of bridle and towing pendant, if... under-keel and vertical clearances (air-gaps) for all bridges, ports, and berthing areas; (v) Pre...

  3. Engineering Work Plan for Development of Sludge Pickup Adapter for Fuel Cleanliness Inspections

    International Nuclear Information System (INIS)

    PITNER, A.L.

    2000-01-01

    The plan for developing an adapter to suction up sludge into a calibrated tube for fuel cleanliness inspection activities is described. A primary assessment of fuel cleanliness to be performed after processing through the Primary Cleaning Machine is whether the volume of any remaining canister sludge in or on a fuel assembly exceeds the allowable 14 cm 3 limit. It is anticipated that a general visual inspection of the sludge inventory after fuel assembly separation will usually suffice in making this assessment, but occasions may arise where there is some question as to whether or not the observed quantity of sludge exceeds this limit. Therefore a quantitative method of collecting and measuring the sludge volume is needed for these borderline situations. It is proposed to develop an adapter that fits on the end of the secondary cleaning station vacuum wand that will suction the material from the sludge collection tray into a chamber marked with the limiting volume to permit a direct go/no-go assessment of the sludge quantity

  4. Study on the inspection item and inspection method of HTGR fuel

    International Nuclear Information System (INIS)

    Na, Sang Ho; Kim, Y. K.; Jeong, K. C.; Oh, S. C.; Cho, M. S.; Kim, Y. M.; Lee, Y. W.

    2006-01-01

    The type of HTGR(High Temperature Gas-cooled Reactor) fuel is different according to the reactor type. Generally the HTGR fuel has two types. One is a block type, which is manufactured in Japan or America. And the other is a pebble type, which is manufactured in China. Regardless of the fuel type, the fuel manufacturing process started from the coated particle, which is consisted of fuel kernel and the 4 coating layers. Korea has a plan to fabricate a HTGR fuel in near future. The appropriate quality inspection standards are requested to produce a sound and reliable coated particle for HTGR fuel. Therefore, the inspection items and the inspection methods of HTGR fuel between Japan and China, which countries have the manufacturing process, are investigated to establish a proper inspection standards of our product characteristics

  5. A survey on inspecting structures using robotic systems

    Directory of Open Access Journals (Sweden)

    Randa Almadhoun

    2016-11-01

    Full Text Available Advancements in robotics and autonomous systems are being deployed nowadays in many application domains such as search and rescue, industrial automation, domestic services and healthcare. These systems are developed to tackle tasks in some of the most challenging, labour intensive and dangerous environments. Inspecting structures (e.g. bridges, buildings, ships, wind turbines and aircrafts is considered a hard task for humans to perform and of critical importance since missing any details could affect the structure’s performance and integrity. Additionally, structure inspection is time and resource intensive and should be performed as efficiently and accurately as possible. Inspecting various structures has been reported in the literature using different robotic platforms to: inspect difficult to reach areas and detect various types of faults and anomalies. Typically, inspection missions involve performing three main tasks: coverage path planning, shape, model or surface reconstruction and the actual inspection of the structure. Coverage path planning ensures the generation of an optimized path that guarantees the complete coverage of the structure of interest in order to gather highly accurate information to be used for shape/model reconstruction. This article aims to provide an overview of the recent work and breakthroughs in the field of coverage path planning and model reconstruction, with focus on 3D reconstruction, for the purpose of robotic inspection.

  6. Inspection of Emergency Arrangements

    International Nuclear Information System (INIS)

    2013-01-01

    The Working Group on Inspection Practices (WGIP) was tasked by the NEA CNRA to examine and evaluate the extent to which emergency arrangements are inspected and to identify areas of importance for the development of good inspection practices. WGIP members shared their approaches to the inspection of emergency arrangements by the use of questionnaires, which were developed from the requirements set out in IAEA Safety Standards. Detailed responses to the questionnaires from WGIP member countries have been compiled and are presented in the appendix to this report. The following commendable practices have been drawn from the completed questionnaires and views provided by WGIP members: - RBs and their Inspectors have sufficient knowledge and information regarding operator's arrangements for the preparedness and response to nuclear emergencies, to enable authoritative advice to be given to the national coordinating authority, where necessary. - Inspectors check that the operator's response to a nuclear emergency is adequately integrated with relevant response organisations. - Inspectors pay attention to consider the integration of the operator's response to safety and security threats. - The efficiency of international relations is checked in depth during some exercises (e.g. early warning, assistance and technical information), especially for near-border facilities that could lead to an emergency response abroad. - RB inspection programmes consider the adequacy of arrangements for emergency preparedness and response to multi-unit accidents. - RBs assess the adequacy of arrangements to respond to accidents in other countries. - The RB's role is adequately documented and communicated to all agencies taking part in the response to a nuclear or radiological emergency. - Inspectors check that threat assessments for NPPs have been undertaken in accordance with national requirements and that up-to-date assessments have been used as the basis for developing emergency plans for

  7. Rail inspection of RCF defects

    Directory of Open Access Journals (Sweden)

    Z. Popović

    2013-10-01

    Full Text Available Rail defects due to rolling contact fatigue (RCF threaten the traffic safety around the world. That hazard is more distinct on railways without adequate maintenance strategy. Realization of interoperability of European railway network demands from every infrastructure manager to have a maintenance plan for the infrastructure subsystem. Besides that, this plan includes rail inspection and strategy against RCF defects. This paper emphasizes the importance of rail inspection and early detection of RCF because the most of RCF crack should be removed in rail grinding campaigns (preventive, cyclical and corrective activities during the whole rail service life.

  8. International cooperation in production inspections

    International Nuclear Information System (INIS)

    Limousin, S.

    2009-01-01

    Nuclear pressure equipment, like the reactor pressure vessel or steam generators, are manufactured in many countries all around the world. As only few reactors were built in the 90's, most of the nuclear safety authorities have lost part of their know how in component manufacturing oversight. For these two reasons, vendor inspection is a key area for international cooperation. On the one hand, ASN has bilateral relationships with several countries (USA, Finland, China...) to fulfill specific purposes. On the other hand, ASN participates in international groups like the MDEP ( Multinational Design Evaluation Program). A MDEP working group dedicated to vendor inspection cooperation enables exchanges of informations (inspection program plan, inspection findings...) among the regulators. Join inspections are organized. International cooperation could lead in the long term to an harmonization of regulatory practices. (author)

  9. Development and performance of inspection equipment for pressure tubes in Fugen

    International Nuclear Information System (INIS)

    Naruo, Kazuteru; Tanimoto, Ken-ichi; Ohta, Takeo; Nakamura, Takahisa; Imaizumi, Kiyoshi.

    1984-01-01

    The pressure tubes of Fugen are the important equipment as the many tubes compose the core, and since they are made of Zr-2.5% Nb alloy which has been used for the first time in Japan, they have become the object of monitoring (the follow-up investigation of the change of inside diameter, the presence of defects and so on) in addition to the in-service inspection. In this paper, on the inspection equipment for pressure tubes, that has been developed independently by the Power Reactor and Nuclear Fuel Development Corp. in order to carry out the ISI and monitoring, the course of development and the construction and the performance are reported, and the results of having used it for the fourth regular inspection of Fugen are described. The 10-year plan of the ISI and monitoring of pressure tubes is shown. The core of Fugen is composed of 224 pressure tubes, therefore, the inspection is carried out by sampling inspection. The monitoring is carried out on four tubes for the follow-up investigation and one tube that shows the severest operation history at the time of inspection. The equipment performs ultrasonic flaw detection, the measurement of inside diameter and the visual inspection of internal surface. (Kako, I.)

  10. Sampling pig farms at the abattoir in a cross-sectional study − Evaluation of a sampling method

    DEFF Research Database (Denmark)

    Birkegård, Anna Camilla; Hisham Beshara Halasa, Tariq; Toft, Nils

    2017-01-01

    slaughter pigs. It was not possible to visit farms within the designated timeframe. Therefore, it was decided to use convenience sampling at the abattoir. Our approach was carried out in three steps: 1) planning: using data from meat inspection to plan at which abattoirs and how many farms to sample; 2......A cross-sectional study design is relatively inexpensive, fast and easy to conduct when compared to other study designs. Careful planning is essential to obtaining a representative sample of the population, and the recommended approach is to use simple random sampling from an exhaustive list...... of units in the target population. This approach is rarely feasible in practice, and other sampling procedures must often be adopted. For example, when slaughter pigs are the target population, sampling the pigs on the slaughter line may be an alternative to on-site sampling at a list of farms. However...

  11. Nevada National Security Site Integrated Groundwater Sampling Plan, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Marutzky, Sam; Farnham, Irene

    2014-10-01

    The purpose of the Nevada National Security Site (NNSS) Integrated Sampling Plan (referred to herein as the Plan) is to provide a comprehensive, integrated approach for collecting and analyzing groundwater samples to meet the needs and objectives of the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office (NNSA/NFO) Underground Test Area (UGTA) Activity. Implementation of this Plan will provide high-quality data required by the UGTA Activity for ensuring public protection in an efficient and cost-effective manner. The Plan is designed to ensure compliance with the UGTA Quality Assurance Plan (QAP). The Plan’s scope comprises sample collection and analysis requirements relevant to assessing the extent of groundwater contamination from underground nuclear testing. This Plan identifies locations to be sampled by corrective action unit (CAU) and location type, sampling frequencies, sample collection methodologies, and the constituents to be analyzed. In addition, the Plan defines data collection criteria such as well-purging requirements, detection levels, and accuracy requirements; identifies reporting and data management requirements; and provides a process to ensure coordination between NNSS groundwater sampling programs for sampling of interest to UGTA. This Plan does not address compliance with requirements for wells that supply the NNSS public water system or wells involved in a permitted activity.

  12. Final Sampling and Analysis Plan for Background Sampling, Fort Sheridan, Illinois

    National Research Council Canada - National Science Library

    1995-01-01

    .... This Background Sampling and Analysis Plan (BSAP) is designed to address this issue through the collection of additional background samples at Fort Sheridan to support the statistical analysis and the Baseline Risk Assessment (BRA...

  13. Poolside fuel assembly inspection campaigns performed at Kernkraftwerk Leibstadt during summer 1997

    International Nuclear Information System (INIS)

    Zwicky, H.U.; Wiktor, C.G.; Schrire, D.

    1998-01-01

    In order to minimise fuel cycle costs, fuel assembly discharge burnup and average U-235 enrichment were increasing over past years in the Kernkraftwerk Leibstadt (KKL) plant. In parallel, high burnup verification programs were defined in collaboration with fuel suppliers. The aim of these programs is to demonstrate safe and reliable fuel performance up to the designed burnup limit and to identify any problems in due time. This is not only achieved by detailed poolside inspections of lead test assemblies, but also by hot cell post-irradiation examination of selected rods. In the frame of a hot cell examination campaign, enhanced localised corrosion in the vicinity of spacers on SVEA-96 fuel rods was identified in May 1997 as a potential problem. The average rod burnup of the investigated rods was around 50 MWd/kgU after 5 one year cycles of operation. As fuel operation up to six cycles is foreseen in KKLs fuel management plants, the risk of fuel failures caused by enhanced localised corrosion could not be excluded. An action plan was therefore developed in order to identify the root cause. Part of the action plan were two poolside inspection campaigns: 1. Visual inspection of 38 assemblies unloaded during refuelling outage 1996 after 5 cycles in operation. This campaign was performed in June 1997. It gave a broader data base to develop a concept for fuel management for the upcoming refuelling outage scheduled in August 1997. 2. Visual inspection, oxide layer thickness measurements, crud sampling and rod diameter measurements on 29 assemblies with different operation histories. This campaign was performed during the outage. A large portion of the inspected bundles was re-inserted for continued operation. The collected data confirmed that assumptions made for reload licensing and safety analyses were conservative. The inspection campaigns performed at KKL during summer 1997 by ABB Atom demonstrated that it is possible to address unexpected problems in a short time

  14. Evaluation and improvement in nondestructive examination (NDE) reliability for inservice inspection of light water reactors

    International Nuclear Information System (INIS)

    Doctor, S.R.; Andersen, E.S.; Bowey, R.E.; Diaz, A.A.; Good, M.S.; Heasler, P.G.; Hockey, R.L.; Simonen, F.A.; Spanner, J.C.; Taylor, T.T.; Vo, T.V.

    1991-01-01

    This program is intended to establish the effectiveness, reliability and adequacy of inservice inspection of reactor pressure vessels and primary piping systems and the impact of ISI reliability on system integrity. The objectives of the program include: (a) determine the effectiveness and reliability of ultrasonic inservice inspection (ISI) performed on commercial, light water reactor pressure vessels and piping; (b) recommend Code changes to the inspection procedures to improve the reliability of ISI; (c) using fracture mechanics analysis, determine the impact of NDE unreliability on system safety and determine the level of inspection reliability required to assure a suitably low failure probability; (d) evaluate the degree of reliability improvement which could be achieved using improved NDE techniques; and (e) based on importance of component to safety, material properties, service conditions, and NDE uncertainties, formulate improved inservice inspection criteria (including sampling plan, frequency, and reliability of inspection) for revisions to ASME Section XI and regulatory requirements needed to assure suitably low failure probabilities

  15. Sampling and analysis plan (SAP) for WESF drains and TK-100 sump

    International Nuclear Information System (INIS)

    Simmons, F.M.

    1998-01-01

    The intent of this project is to determine whether the Waste Encapsulation and Storage Facility (WESF) floor drain piping and the TK-100 sump are free from contamination. TK-100 is currently used as a catch tank to transfer low level liquid waste from WESF to Tank Farms via B Plant. This system is being modified as part of the WESF decoupling since B Plant is being deactivated. As a result of the 1,1,1-trichloroethane (TCA) discovery in TK-100, the associated WESF floor drains and the pit sump need to be sampled. Breakdown constituents have been reviewed and found to be non-hazardous. There are 29 floor drains that tie into a common header leading into the tank. To prevent high exposure during sampling of the drains, TK-100 will be removed into the B Plant canyon and a new tank will be placed in the pit before any floor drain samples are taken. The sump will be sampled prior to TK-100 removal. A sample of the sludge and any liquid in the sump will be taken and analyzed for TCA and polychlorinated biphenyl (PCB). After the sump has been sampled, the vault floor will be flushed. The flush will be transferred from the sump into TK-100. TK-100 will be moved into B Plant. The vault will then be cleaned of debris and visually inspected. If there is no visual indication of TCA or PCB staining, the vault will be painted and a new tank installed. If there is an indication of TCA or PCB from laboratory analysis or staining, further negotiations will be required to determine a path forward. A total of 8 sets of three 40ml samples will be required for all of the floor drains and sump. The sump set will include one 125ml solid sample. The only analysis required will be for TCA in liquids. PCBs will be checked in sump solids only. The Sampling and Analysis Plan (SAP) is written to provide direction for the sampling and analytical activities of the 29 WESF floor drains and the TK-100 sump. The intent of this plan is to define the responsibilities of the various organizations

  16. Fully Employing Software Inspections Data

    Science.gov (United States)

    Shull, Forrest; Feldmann, Raimund L.; Seaman, Carolyn; Regardie, Myrna; Godfrey, Sally

    2009-01-01

    Software inspections provide a proven approach to quality assurance for software products of all kinds, including requirements, design, code, test plans, among others. Common to all inspections is the aim of finding and fixing defects as early as possible, and thereby providing cost savings by minimizing the amount of rework necessary later in the lifecycle. Measurement data, such as the number and type of found defects and the effort spent by the inspection team, provide not only direct feedback about the software product to the project team but are also valuable for process improvement activities. In this paper, we discuss NASA's use of software inspections and the rich set of data that has resulted. In particular, we present results from analysis of inspection data that illustrate the benefits of fully utilizing that data for process improvement at several levels. Examining such data across multiple inspections or projects allows team members to monitor and trigger cross project improvements. Such improvements may focus on the software development processes of the whole organization as well as improvements to the applied inspection process itself.

  17. Integrated sampling and analysis plan for samples measuring >10 mrem/hour

    International Nuclear Information System (INIS)

    Haller, C.S.

    1992-03-01

    This integrated sampling and analysis plan was prepared to assist in planning and scheduling of Hanford Site sampling and analytical activities for all waste characterization samples that measure greater than 10 mrem/hour. This report also satisfies the requirements of the renegotiated Interim Milestone M-10-05 of the Hanford Federal Facility Agreement and Consent Order (the Tri-Party Agreement). For purposes of comparing the various analytical needs with the Hanford Site laboratory capabilities, the analytical requirements of the various programs were normalized by converting required laboratory effort for each type of sample to a common unit of work, the standard analytical equivalency unit (AEU). The AEU approximates the amount of laboratory resources required to perform an extensive suite of analyses on five core segments individually plus one additional suite of analyses on a composite sample derived from a mixture of the five core segments and prepare a validated RCRA-type data package

  18. A Novel Method of Autonomous Inspection for Transmission Line based on Cable Inspection Robot LiDAR Data

    Directory of Open Access Journals (Sweden)

    Xinyan Qin

    2018-02-01

    Full Text Available With the growth of the national economy, there is increasing demand for electricity, which forces transmission line corridors to become structurally complicated and extend to complex environments (e.g., mountains, forests. It is a great challenge to inspect transmission line in these regions. To address these difficulties, a novel method of autonomous inspection for transmission line is proposed based on cable inspection robot (CIR LiDAR data, which mainly includes two steps: preliminary inspection and autonomous inspection. In preliminary inspection, the position and orientation system (POS data is used for original point cloud dividing, ground point filtering, and structured partition. A hierarchical classification strategy is established to identify the classes and positions of the abnormal points. In autonomous inspection, CIR can autonomously reach the specified points through inspection planning. These inspection targets are imaged with PTZ (pan, tilt, zoom cameras by coordinate transformation. The feasibility and effectiveness of the proposed method are verified by test site experiments and actual line experiments, respectively. The proposed method greatly reduces manpower and improves inspection accuracy, providing a theoretical basis for intelligent inspection of transmission lines in the future.

  19. Inspection technologies -Development of national safeguards technology-

    International Nuclear Information System (INIS)

    Hong, J. S.; Kim, B. K.; Kwack, E. H.

    1996-12-01

    17 facility regulations prepared by nuclear facilities according to the Ministerial Notices were evaluated. Safeguards inspection activities under Safeguards are described. Safeguards inspection equipments and operation manuals to be used for national inspection are also described. Safeguards report are produced and submitted to MOST by using the computerized nuclear material accounting system at state level. National inspection support system are developed to produce the on-site information for domestic inspection. Planning and establishment of policy for nuclear control of nuclear materials, international cooperation for nuclear control, CTBT, strengthening of international safeguards system, and the supply of PWRs to North Korea are also described. (author). 43 tabs., 39 figs

  20. Group Acceptance Sampling Plan for Lifetime Data Using Generalized Pareto Distribution

    Directory of Open Access Journals (Sweden)

    Muhammad Aslam

    2010-02-01

    Full Text Available In this paper, a group acceptance sampling plan (GASP is introduced for the situations when lifetime of the items follows the generalized Pareto distribution. The design parameters such as minimum group size and acceptance number are determined when the consumer’s risk and the test termination time are specified. The proposed sampling plan is compared with the existing sampling plan. It is concluded that the proposed sampling plan performs better than the existing plan in terms of minimum sample size required to reach the same decision.

  1. Nuclear power plant pressure vessels. Inservice inspections

    International Nuclear Information System (INIS)

    1995-01-01

    The requirements for the planning and reporting of inservice inspections of nuclear power plant pressure vessels are presented. The guide specifically applies to inservice inspections of Safety class 1 and 2 nuclear power plant pressure vessels, piping, pumps and valves plus their supports and reactor pressure vessel internals by non- destructive examination methods (NDE). Inservice inspections according to the Pressure Vessel Degree (549/73) are discussed separately in the guide YVL 3.0. (4 refs.)

  2. 40 CFR 60.36e - Inspection guidelines.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 6 2010-07-01 2010-07-01 false Inspection guidelines. 60.36e Section...) STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES Emission Guidelines and Compliance Times for Hospital/Medical/Infectious Waste Incinerators § 60.36e Inspection guidelines. (a) For approval, a State plan shall...

  3. Surface water sampling and analysis plan for environmental monitoring in Waste Area Grouping 6 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Environmental Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    1994-06-01

    This Sampling and Analysis Plan addresses surface water monitoring, sampling, and analysis activities that will be conducted in support of the Environmental Monitoring Plan for Waste Area Grouping (WAG) 6. WAG 6 is a shallow-burial land disposal facility for low-level radioactive waste at the Oak Ridge National Laboratory, a research facility owned by the US Department of Energy and managed by Martin Marietta Energy Systems, Inc. Surface water monitoring will be conducted at nine sites within WAG 6. Activities to be conducted will include the installation, inspection, and maintenance of automatic flow-monitoring and sampling equipment and manual collection of various water and sediment samples. The samples will be analyzed for various organic, inorganic, and radiological parameters. The information derived from the surface water monitoring, sampling, and analysis will aid in evaluating risk associated with contaminants migrating off-WAG, and will be used in calculations to establish relationships between contaminant concentration (C) and flow (Q). The C-Q relationship will be used in calculating the cumulative risk associated with the off-WAG migration of contaminants.

  4. Surface water sampling and analysis plan for environmental monitoring in Waste Area Grouping 6 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Environmental Restoration Program

    International Nuclear Information System (INIS)

    1994-06-01

    This Sampling and Analysis Plan addresses surface water monitoring, sampling, and analysis activities that will be conducted in support of the Environmental Monitoring Plan for Waste Area Grouping (WAG) 6. WAG 6 is a shallow-burial land disposal facility for low-level radioactive waste at the Oak Ridge National Laboratory, a research facility owned by the US Department of Energy and managed by Martin Marietta Energy Systems, Inc. Surface water monitoring will be conducted at nine sites within WAG 6. Activities to be conducted will include the installation, inspection, and maintenance of automatic flow-monitoring and sampling equipment and manual collection of various water and sediment samples. The samples will be analyzed for various organic, inorganic, and radiological parameters. The information derived from the surface water monitoring, sampling, and analysis will aid in evaluating risk associated with contaminants migrating off-WAG, and will be used in calculations to establish relationships between contaminant concentration (C) and flow (Q). The C-Q relationship will be used in calculating the cumulative risk associated with the off-WAG migration of contaminants

  5. Advanced Approach of Reactor Pressure Vessel In-service Inspection

    International Nuclear Information System (INIS)

    Matokovic, A.; Picek, E.; Pajnic, M.

    2006-01-01

    The most important task of every utility operating a nuclear power plant is the continuously keeping of the desired safety and reliability level. This is achieved by the performance of numerous inspections of the components, equipment and system of the nuclear power plant in operation and in particular during the scheduled maintenance periods at re-fueling time. Periodic non-destructive in-service inspections provide most relevant criteria of the integrity of primary circuit pressure components. The task is to reliably detect defects and realistically size and characterize them. One of most important and the most extensive examination is a reactor pressure vessel in-service inspection. That inspection demand high standards of technology and quality and continual innovation in the field of non-destructive testing (NDT) advanced technology as well as regarding reactor pressure vessel tool and control systems. A remote underwater contact ultrasonic technique is employed for the examination of the defined sections (reactor welds), whence eddy current method is applied for clad surface examinations. Visual inspection is used for examination of the vessel inner surface. The movement of probes and data positioning are assured by using new reactor pressure vessel tool concept that is fully integrated with NDT systems. The successful performance is attributed thorough pre-outage planning, training and successful performance demonstration qualification of chosen NDT techniques on the specimens with artificial and/or real defects. Furthermore, use of advanced approach of inspection through implementation the state of the art examination equipment significantly reduced the inspection time, radiation exposure to examination personnel, shortening nuclear power plant outage and cutting the total inspection costs. The advanced approach as presented in this paper offer more flexibility of application (non-destructive tests, local grinding action as well as taking of boat samples

  6. Nevada National Security Site Integrated Groundwater Sampling Plan, Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    Farnham, Irene

    2018-03-01

    The purpose is to provide a comprehensive, integrated approach for collecting and analyzing groundwater samples to meet the needs and objectives of the DOE/EM Nevada Program’s UGTA Activity. Implementation of this Plan will provide high-quality data required by the UGTA Activity for ensuring public protection in an efficient and cost-effective manner. The Plan is designed to ensure compliance with the UGTA Quality Assurance Plan (QAP) (NNSA/NFO, 2015); Federal Facility Agreement and Consent Order (FFACO) (1996, as amended); and DOE Order 458.1, Radiation Protection of the Public and the Environment (DOE, 2013). The Plan’s scope comprises sample collection and analysis requirements relevant to assessing both the extent of groundwater contamination from underground nuclear testing and impact of testing on water quality in downgradient communities. This Plan identifies locations to be sampled by CAU and location type, sampling frequencies, sample collection methodologies, and the constituents to be analyzed. In addition, the Plan defines data collection criteria such as well purging, detection levels, and accuracy requirements/recommendations; identifies reporting and data management requirements; and provides a process to ensure coordination between NNSS groundwater sampling programs for sampling analytes of interest to UGTA. Information used in the Plan development—including the rationale for selection of wells, sampling frequency, and the analytical suite—is discussed under separate cover (N-I, 2014) and is not reproduced herein. This Plan does not address compliance for those wells involved in a permitted activity. Sampling and analysis requirements associated with these wells are described in their respective permits and are discussed in NNSS environmental reports (see Section 5.2). In addition, sampling for UGTA CAUs that are in the Closure Report (CR) stage are not included in this Plan. Sampling requirements for these CAUs are described in the CR

  7. 42 CFR 431.814 - Sampling plan and procedures.

    Science.gov (United States)

    2010-10-01

    ... reliability of the reduced sample. (4) The sample selection procedure. Systematic random sampling is... sampling, and yield estimates with the same or better precision than achieved in systematic random sampling... 42 Public Health 4 2010-10-01 2010-10-01 false Sampling plan and procedures. 431.814 Section 431...

  8. A novel derivation of a within-batch sampling plan based on a Poisson-gamma model characterising low microbial counts in foods.

    Science.gov (United States)

    Gonzales-Barron, Ursula; Zwietering, Marcel H; Butler, Francis

    2013-02-01

    This study proposes a novel step-wise methodology for the derivation of a sampling plan by variables for food production systems characterised by relatively low concentrations of the inspected microorganism. After representing the universe of contaminated batches by modelling the between-batch and within-batch variability in microbial counts, a tolerance criterion defining batch acceptability (i.e., up to a tolerance percentage of the food units having microbial concentrations lower or equal to a critical concentration) is established to delineate a limiting quality contour that separates satisfactory from unsatisfactory batches. The problem consists then of finding the optimum decision criterion - arithmetic mean of the analytical results (microbiological limit, m(L)) and the sample size (n) - that satisfies a pre-defined level of confidence measured on the samples' mean distributions from all possible true within-batch distributions. This is approached by obtaining decision landscape curves representing collectively the conditional and joint producer's and consumer's risks at different microbiological limits along with confidence intervals representing uncertainty due to the propagated between-batch variability. Whilst the method requires a number of risk management decisions to be made such as the objective of the sampling plan (GMP-based or risk-based), the modality of derivation, the tolerance criterion or level of safety, and the statistical level of confidence, the proposed method can be used when past monitoring data are available so as to produce statistically-sound dynamic sampling plans with optimised efficiency and discriminatory power. For the illustration of Enterobacteriaceae concentrations on Irish sheep carcasses, a sampling regime of n=10 and m(L)=17.5CFU/cm(2) is recommended to ensure that the producer has at least a 90% confidence of accepting a satisfactory batch whilst the consumer at least a 97.5% confidence that a batch will not be

  9. UMTRA project water sampling and analysis plan, Gunnison, Colorado

    International Nuclear Information System (INIS)

    1994-06-01

    This water sampling and analysis plan summarizes the results of previous water sampling activities and the plan for water sampling activities for calendar year 1994. A buffer zone monitoring plan is included as an appendix. The buffer zone monitoring plan is designed to protect the public from residual contamination that entered the ground water as a result of former milling operations. Surface remedial action at the Gunnison Uranium Mill Tailings Remedial Action Project site began in 1992; completion is expected in 1995. Ground water and surface water will be sampled semiannually in 1994 at the Gunnison processing site (GUN-01) and disposal site (GUN-08). Results of previous water sampling at the Gunnison processing site indicate that ground water in the alluvium is contaminated by the former uranium processing activities. Background ground water conditions have been established in the uppermost aquifer (Tertiary gravels) at the Gunnison disposal site. The monitor well locations provide a representative distribution of sampling points to characterize ground water quality and ground water flow conditions in the vicinity of the sites. The list of analytes has been modified with time to reflect constituents that are related to uranium processing activities and the parameters needed for geochemical evaluation. Water sampling will be conducted at least semiannually during and one year following the period of construction activities, to comply with the ground water protection strategy discussed in the remedial action plan (DOE, 1992a)

  10. Sample Lesson Plans. Management for Effective Teaching.

    Science.gov (United States)

    Fairfax County Public Schools, VA. Dept. of Instructional Services.

    This guide is part of the Management for Effective Teaching (MET) support kit, a pilot project developed by the Fairfax County (Virginia) Public Schools to assist elementary school teachers in planning, managaing, and implementing the county's curriculum, Program of Studies (POS). In this guide, a sample lesson plan of a teaching-learning activity…

  11. OSE inspection of materials control and accountability: Review

    International Nuclear Information System (INIS)

    Coady, K.J.

    1987-01-01

    As part of its task to confirm that Department of Energy (DOE) field offices provide levels of security and safeguards commensurate with defined threats, the DOE Office of Security Evaluations (OSE) conducts inspections of the nuclear materials control and accountability (MC and A) systems at DOE facilities throughout the United States. Inspections are based on the DOE Safeguards and Security Standards and Criteria, tailored to the specific aspects at and threats to each individual site. This paper reviews the process of inspecting MC and A systems during the planning, preinspection, and inspection/reporting phases

  12. Sample management implementation plan: Salt Repository Project

    International Nuclear Information System (INIS)

    1987-01-01

    The purpose of the Sample Management Implementation Plan is to define management controls and building requirements for handling materials collected during the site characterization of the Deaf Smith County, Texas, site. This work will be conducted for the US Department of Energy Salt Repository Project Office (SRPO). The plan provides for controls mandated by the US Nuclear Regulatory Commission and the US Environmental Protection Agency. Salt Repository Project (SRP) Sample Management will interface with program participants who request, collect, and test samples. SRP Sample Management will be responsible for the following: (1) preparing samples; (2) ensuring documentation control; (3) providing for uniform forms, labels, data formats, and transportation and storage requirements; and (4) identifying sample specifications to ensure sample quality. The SRP Sample Management Facility will be operated under a set of procedures that will impact numerous program participants. Requesters of samples will be responsible for definition of requirements in advance of collection. Sample requests for field activities will be approved by the SRPO, aided by an advisory group, the SRP Sample Allocation Committee. This document details the staffing, building, storage, and transportation requirements for establishing an SRP Sample Management Facility. Materials to be managed in the facility include rock core and rock discontinuities, soils, fluids, biota, air particulates, cultural artifacts, and crop and food stuffs. 39 refs., 3 figs., 11 tabs

  13. Information-Driven Inspections

    International Nuclear Information System (INIS)

    Laughter, Mark D.; Whitaker, J. Michael; Lockwood, Dunbar

    2010-01-01

    New uranium enrichment capacity is being built worldwide in response to perceived shortfalls in future supply. To meet increasing safeguards responsibilities with limited resources, the nonproliferation community is exploring next-generation concepts to increase the effectiveness and efficiency of safeguards, such as advanced technologies to enable unattended monitoring of nuclear material. These include attribute measurement technologies, data authentication tools, and transmission and security methods. However, there are several conceptual issues with how such data would be used to improve the ability of a safeguards inspectorate such as the International Atomic Energy Agency (IAEA) to reach better safeguards conclusions regarding the activities of a State. The IAEA is pursuing the implementation of information-driven safeguards, whereby all available sources of information are used to make the application of safeguards more effective and efficient. Data from continuous, unattended monitoring systems can be used to optimize on-site inspection scheduling and activities at declared facilities, resulting in fewer, better inspections. Such information-driven inspections are the logical evolution of inspection planning - making use of all available information to enhance scheduled and randomized inspections. Data collection and analysis approaches for unattended monitoring systems can be designed to protect sensitive information while enabling information-driven inspections. A number of such inspections within a predetermined range could reduce inspection frequency while providing an equal or greater level of deterrence against illicit activity, all while meeting operator and technology holder requirements and reducing inspector and operator burden. Three options for using unattended monitoring data to determine an information-driven inspection schedule are to (1) send all unattended monitoring data off-site, which will require advances in data analysis techniques to

  14. Strategic planning of developing automatic optical inspection (AOI) technologies in Taiwan

    International Nuclear Information System (INIS)

    Fan, K C; Hsu, C

    2005-01-01

    In most domestic hi-tech industries in Taiwan, the automatic optical inspection (AOI) equipment is mostly imported. In view of the required specifications, AOI consists of the integration of mechanical-electrical-optical-information technologies. In the past two decades, traditional industries have lost their competitiveness due to the low profit rate. It is possible to promote a new AOI industry in Taiwan through the integration of its strong background in mechatronic technology in positioning stages with the optical image processing techniques. The market requirements are huge not only in domestic need but also in global need. This is the main reason to promote the AOI research for the coming years in Taiwan. Focused industrial applications will be in IC, PCB, LCD, communication, and MEMS parts. This paper will analyze the domestic and global AOI equipment market, summarize the necessary fish bone technology diagrams, survey the actual industrial needs, and propose the strategic plan to be promoted in Taiwan

  15. Strategic planning of developing automatic optical inspection (AOI) technologies in Taiwan

    Science.gov (United States)

    Fan, K. C.; Hsu, C.

    2005-01-01

    In most domestic hi-tech industries in Taiwan, the automatic optical inspection (AOI) equipment is mostly imported. In view of the required specifications, AOI consists of the integration of mechanical-electrical-optical-information technologies. In the past two decades, traditional industries have lost their competitiveness due to the low profit rate. It is possible to promote a new AOI industry in Taiwan through the integration of its strong background in mechatronic technology in positioning stages with the optical image processing techniques. The market requirements are huge not only in domestic need but also in global need. This is the main reason to promote the AOI research for the coming years in Taiwan. Focused industrial applications will be in IC, PCB, LCD, communication, and MEMS parts. This paper will analyze the domestic and global AOI equipment market, summarize the necessary fish bone technology diagrams, survey the actual industrial needs, and propose the strategic plan to be promoted in Taiwan.

  16. Sea bed mapping and inspection

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2006-07-01

    The conference has 24 presentations on the topics: Sea bed mapping, inspection, positioning, hydrography, marine archaeology, remote operation vehicles and computerized simulation technologies, oil field activities and plans, technological experiences and problems. (tk)

  17. Simulation in Quality Management – An Approach to Improve Inspection Planning

    Directory of Open Access Journals (Sweden)

    H.-A. Crostack

    2005-01-01

    Full Text Available Production is a multi-step process involving many different articles produced in different jobs by various machining stations. Quality inspection has to be integrated in the production sequence in order to ensure the conformance of the products. The interactions between manufacturing processes and inspections are very complex since three aspects (quality, cost, and time should all be considered at the same time while determining the suitable inspection strategy. Therefore, a simulation approach was introduced to solve this problem.The simulator called QUINTE [the QUINTE simulator has been developed at the University of Dortmund in the course of two research projects funded by the German Federal Ministry of Economics and Labour (BMWA: Bundesministerium für Wirtschaft und Arbeit, the Arbeitsgemeinschaft industrieller Forschungsvereinigungen (AiF, Cologne/Germany and the Forschungsgemeinschaft Qualität, Frankfurt a.M./Germany] was developed to simulate the machining as well as the inspection. It can be used to investigate and evaluate the inspection strategies in manufacturing processes. The investigation into the application of QUINTE simulator in industry was carried out at two pilot companies. The results show the validity of this simulator. An attempt to run QUINTE in a user-friendly environment, i.e., the commercial simulation software – Arena® is also described in this paper.NOTATION: QUINTE Qualität in der Teilefertigung  (Quality in  the manufacturing process  

  18. Condition Indicators for Inspection Planning of Concrete Structures

    DEFF Research Database (Denmark)

    Faber, Michael Havbro; Sørensen, John Dalsgaard

    2002-01-01

    Based on previous work by the authors a Bayesian formulation of condition indicators is developed further whereby in conjunction with a systems modelling of concrete structures the experience and expertise of the inspection personnel may be fully utilized. It is shown how the predicted evolution ...

  19. Method of analyzing the shipping inspection water in nuclear fuels

    International Nuclear Information System (INIS)

    Ishikawa, Tatsuo; Izumoji, Yoshiaki.

    1984-01-01

    Purpose: To automatically perform radioactive-corrosion-products removing operation and thereby automatic analysis for shipping inspection water. Method: An radioactive-corrosion-product removing device has a column filled with a chelate resin layer. Shipping-inspection water as a specimen is injected from a sample-water inlet to the column, passes through the chelate resin layer, issues through the sample-water exit and is then stored once in a sample collector. The shipping inspection water sampled in the sampling collector is sent to an inspection port in an on-line or off-line manner and gamma-ray determination is made by a gamma-ray spectrum analyzer. (Horiuchi, T.)

  20. Automated reticle inspection data analysis for wafer fabs

    Science.gov (United States)

    Summers, Derek; Chen, Gong; Reese, Bryan; Hutchinson, Trent; Liesching, Marcus; Ying, Hai; Dover, Russell

    2009-04-01

    To minimize potential wafer yield loss due to mask defects, most wafer fabs implement some form of reticle inspection system to monitor photomask quality in high-volume wafer manufacturing environments. Traditionally, experienced operators review reticle defects found by an inspection tool and then manually classify each defect as 'pass, warn, or fail' based on its size and location. However, in the event reticle defects are suspected of causing repeating wafer defects on a completed wafer, potential defects on all associated reticles must be manually searched on a layer-by-layer basis in an effort to identify the reticle responsible for the wafer yield loss. This 'problem reticle' search process is a very tedious and time-consuming task and may cause extended manufacturing line-down situations. Often times, Process Engineers and other team members need to manually investigate several reticle inspection reports to determine if yield loss can be tied to a specific layer. Because of the very nature of this detailed work, calculation errors may occur resulting in an incorrect root cause analysis effort. These delays waste valuable resources that could be spent working on other more productive activities. This paper examines an automated software solution for converting KLA-Tencor reticle inspection defect maps into a format compatible with KLA-Tencor's Klarity Defect(R) data analysis database. The objective is to use the graphical charting capabilities of Klarity Defect to reveal a clearer understanding of defect trends for individual reticle layers or entire mask sets. Automated analysis features include reticle defect count trend analysis and potentially stacking reticle defect maps for signature analysis against wafer inspection defect data. Other possible benefits include optimizing reticle inspection sample plans in an effort to support "lean manufacturing" initiatives for wafer fabs.

  1. Dry Cask Storage Inspection and Monitoring. Interim Report.

    Energy Technology Data Exchange (ETDEWEB)

    Bakhtiari, Susan [Argonne National Lab. (ANL), Argonne, IL (United States); Elmer, Thomas W. [Argonne National Lab. (ANL), Argonne, IL (United States); Koehl, Eugene R. [Argonne National Lab. (ANL), Argonne, IL (United States); Wang, Ke [Argonne National Lab. (ANL), Argonne, IL (United States); Raptis, Apostolos C. [Argonne National Lab. (ANL), Argonne, IL (United States); Kunerth, Dennis C. [Idaho National Lab. (INL), Idaho Falls, ID (United States); Birk, Sandra M. [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-03-04

    Recently, the U.S. Nuclear Regulatory Commission (NRC) issued the guidance on the aging management of dry storage facilities that indicates the necessity to monitor the conditions of dry cask storage systems (DCSSs) over extended periods of time.1 Part of the justification of the aging management plans is the requirement for inspection and monitoring to verify whether continued monitoring, inspection or mitigation are necessary. To meet this challenge Argonne National Laboratory (ANL) in collaboration with Idaho National Laboratory (INL) is conducting scoping studies on current and emerging nondestructive evaluation/examination (NDE) and online monitoring (OLM) technologies for DCSS integrity assessments. The scope of work plan includes identification and verification of technologies for long-term online monitoring of DCSSs’ crucial physical parameters such as temperature, pressure, leakage and structural integrity in general. Modifications have been made to the current technologies to accommodate field inspections and monitoring. A summary of the scoping studies and experimental efforts conducted to date as well as plans for future activities is provided below.

  2. MRP-227 Reactor vessel internals inspection planning and initial results at the Oconee nuclear station unit 2

    International Nuclear Information System (INIS)

    Davidsaver, S.B.; Fyfitch, S.; Whitaker, D.E.; Doss, R.L.

    2015-01-01

    The U.S. PWR industry has pro-actively developed generic inspection requirements and standards for reactor vessel (RV) internals. The Electric Power Research Institute (EPRI) Pressurized Water Reactor (PWR) Materials Reliability Program (MRP) has issued MRP-227-A and MRP-228 with mandatory and needed requirements based on the Nuclear Energy Institute (NEI) document NEI 03-08. The inspection and evaluation guidelines contained in MRP-227-A consider eight age-related degradation mechanisms: stress corrosion cracking (SCC), irradiation-assisted stress corrosion cracking (IASCC), wear, fatigue, thermal aging embrittlement, irradiation embrittlement, void swelling and irradiation growth, and thermal and irradiation-enhanced stress relaxation or irradiation-enhanced creep. This paper will discuss the decision planning efforts required for implementing the MRP-227-A and MRP-228 requirements and the results of these initial inspections at the Oconee Nuclear power station (ONS) units. Duke Energy and AREVA overcame a significant technology and NDE challenge by successfully completing the first-of-a-kind MRP-227-A scope requirements at ONS-1 in one outage below the estimated dose and with zero safety issues or events. This performance was repeated at ONS-2 a year later. The remote NDE tooling and processes developed to examine the MRP-227-A scope for ONS-1 and ONS-2 are transferable to other PWRs

  3. Risk Based Inspection of Gas-Cooling Heat Exchanger

    Directory of Open Access Journals (Sweden)

    Dwi Priyanta

    2017-09-01

    Full Text Available On October 2013, Pertamina Hulu Energi Offshore North West Java (PHE – ONWJ platform personnel found 93 leaking tubes locations in the finfan coolers/ gas-cooling heat exchanger. After analysis had been performed, the crack in the tube strongly indicate that stress corrosion cracking was occurred by chloride. Chloride stress corrosion cracking (CLSCC is the cracking occurred by the combined influence of tensile stress and a corrosive environment. CLSCC is the one of the most common reasons why austenitic stainless steel pipework or tube and vessels deteriorate in the chemical processing, petrochemical industries and maritime industries. In this thesis purpose to determine the appropriate inspection planning for two main items (tubes and header box in the gas-cooling heat exchanger using risk based inspection (RBI method. The result, inspection of the tubes must be performed on July 6, 2024 and for the header box inspection must be performed on July 6, 2025. In the end, RBI method can be applicated to gas-cooling heat exchanger. Because, risk on the tubes can be reduced from 4.537 m2/year to 0.453 m2/year. And inspection planning for header box can be reduced from 4.528 m2/year to 0.563 m2/year.

  4. Sampling pig farms at the abattoir in a cross-sectional study - Evaluation of a sampling method.

    Science.gov (United States)

    Birkegård, Anna Camilla; Halasa, Tariq; Toft, Nils

    2017-09-15

    A cross-sectional study design is relatively inexpensive, fast and easy to conduct when compared to other study designs. Careful planning is essential to obtaining a representative sample of the population, and the recommended approach is to use simple random sampling from an exhaustive list of units in the target population. This approach is rarely feasible in practice, and other sampling procedures must often be adopted. For example, when slaughter pigs are the target population, sampling the pigs on the slaughter line may be an alternative to on-site sampling at a list of farms. However, it is difficult to sample a large number of farms from an exact predefined list, due to the logistics and workflow of an abattoir. Therefore, it is necessary to have a systematic sampling procedure and to evaluate the obtained sample with respect to the study objective. We propose a method for 1) planning, 2) conducting, and 3) evaluating the representativeness and reproducibility of a cross-sectional study when simple random sampling is not possible. We used an example of a cross-sectional study with the aim of quantifying the association of antimicrobial resistance and antimicrobial consumption in Danish slaughter pigs. It was not possible to visit farms within the designated timeframe. Therefore, it was decided to use convenience sampling at the abattoir. Our approach was carried out in three steps: 1) planning: using data from meat inspection to plan at which abattoirs and how many farms to sample; 2) conducting: sampling was carried out at five abattoirs; 3) evaluation: representativeness was evaluated by comparing sampled and non-sampled farms, and the reproducibility of the study was assessed through simulated sampling based on meat inspection data from the period where the actual data collection was carried out. In the cross-sectional study samples were taken from 681 Danish pig farms, during five weeks from February to March 2015. The evaluation showed that the sampling

  5. Gentilly 2 steam generators Spring 2000 outage: tubesheet waterlance cleaning and inspection; upper bundle inspection

    International Nuclear Information System (INIS)

    Akeroyd, J.K.; Plante, S.

    2000-01-01

    A review of the secondary side maintenance activities recently completed during the Gentilly 2 Annual Spring 2000 Maintenance Outage. Activities included: 1) Tubesheet intertube waterlance cleaning and visual inspection, 2) First tube support plate, in-bundle visual inspection of the hot leg, and 3) Upper bundle tube support plate visual inspection. A description of the waterlancing and inspection equipment and setup in the RB at Gentilly 2 is provided. Several innovative techniques were successfully employed and yielded savings in critical path duration, labour and personnel radiation dose. These included accessing the SG tubesheet region through one handhole only and sludge removal utilizing the SG blowdown system. Plant personnel judged tubesheet sludge removal successful. Before and after results of the cleaning process along with samples of the visual inspection results are provided. Inspection of the first support plate, which was a repeat of an inspection done in 1997, was conducted along with an in-bundle inspection of the upper tube supports. Results are presented along with a discussion of the implications for future steam generator maintenance. (author)

  6. Application of reliability techniques to prioritize BWR [boiling water reactor] recirculation loop welds for in-service inspection

    International Nuclear Information System (INIS)

    Holman, G.S.

    1989-12-01

    In January 1988 the US Nuclear Regulatory Commission issued Generic Letter 88-01 together with NUREG-0313, Revision 2, ''Technical Report on Material Selection and Processing Guidelines for BWR Coolant Pressure Boundary Piping,'' to implement NRC long-range plans for addressing the problem of stress corrosion cracking in boiling water reactor piping. NUREG-0313 presents guidelines for categorizing BWR pipe welds according to their SCC condition (e.g., presence of known cracks, implementation of measures for mitigating SCC) as well as recommended inspection schedules (e.g., percentage of welds inspected, inspection frequency) for each weld category. NUREG-0313 does not, however, specify individual welds to be inspected. To address this issue, the Lawrence Livermore National Laboratory developed two recommended inspection samples for welds in a typical BWR recirculation loop. Using a probabilistic fracture mechanics model, LLNL prioritized loop welds on the basis of estimated leak probabilities. The results of this evaluation indicate that riser welds and bypass welds should be given priority attention over other welds. Larger-diameter welds as a group can be considered of secondary importance compared to riser and bypass welds. A ''blind'' comparison between the probability-based inspection samples and data from actual field inspections indicated that the probabilistic analysis generally captured the welds which the field inspections identified as warranting repair or replacement. Discrepancies between the field data and the analytic results can likely be attributed to simplifying assumptions made in the analysis. The overall agreement between analysis and field experience suggests that reliability techniques -- when combined with historical experience -- represent a sound technical basis on which to define meaningful weld inspection programs. 13 refs., 8 figs., 5 tabs

  7. Space Shuttle Communications Coverage Analysis for Thermal Tile Inspection

    Science.gov (United States)

    Kroll, Quin D.; Hwu, Shian U.; Upanavage, Matthew; Boster, John P.; Chavez, Mark A.

    2009-01-01

    The space shuttle ultra-high frequency Space-to-Space Communication System has to provide adequate communication coverage for astronauts who are performing thermal tile inspection and repair on the underside of the space shuttle orbiter (SSO). Careful planning and quantitative assessment are necessary to ensure successful system operations and mission safety in this work environment. This study assesses communication systems performance for astronauts who are working in the underside, non-line-of-sight shadow region on the space shuttle. All of the space shuttle and International Space Station (ISS) transmitting antennas are blocked by the SSO structure. To ensure communication coverage at planned inspection worksites, the signal strength and link margin between the SSO/ISS antennas and the extravehicular activity astronauts, whose line-of-sight is blocked by vehicle structure, was analyzed. Investigations were performed using rigorous computational electromagnetic modeling techniques. Signal strength was obtained by computing the reflected and diffracted fields along the signal propagation paths between transmitting and receiving antennas. Radio frequency (RF) coverage was determined for thermal tile inspection and repair missions using the results of this computation. Analysis results from this paper are important in formulating the limits on reliable communication range and RF coverage at planned underside inspection and repair worksites.

  8. Feasible sampling plan for Bemisia tabaci control decision-making in watermelon fields.

    Science.gov (United States)

    Lima, Carlos Ho; Sarmento, Renato A; Pereira, Poliana S; Galdino, Tarcísio Vs; Santos, Fábio A; Silva, Joedna; Picanço, Marcelo C

    2017-11-01

    The silverleaf whitefly Bemisia tabaci is one of the most important pests of watermelon fields worldwide. Conventional sampling plans are the starting point for the generation of decision-making systems of integrated pest management programs. The aim of this study was to determine a conventional sampling plan for B. tabaci in watermelon fields. The optimal leaf for B. tabaci adult sampling was the 6 th most apical leaf. Direct counting was the best pest sampling technique. Crop pest densities fitted the negative binomial distribution and had a common aggregation parameter (K common ). The sampling plan consisted of evaluating 103 samples per plot. This sampling plan was conducted for 56 min, costing US$ 2.22 per sampling and with a 10% maximum evaluation error. The sampling plan determined in this study can be adopted by farmers because it enables the adequate evaluation of B. tabaci populations in watermelon fields (10% maximum evaluation error) and is a low-cost (US$ 2.22 per sampling), fast (56 min per sampling) and feasible (because it may be used in a standardized way throughout the crop cycle) technique. © 2017 Society of Chemical Industry. © 2017 Society of Chemical Industry.

  9. UMTRA project water sampling and analysis plan, Tuba City, Arizona

    International Nuclear Information System (INIS)

    1996-02-01

    Planned, routine ground water sampling activities at the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Tuba City, Arizona, are described in the following sections of this water sampling and analysis plan (WSAP). This plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the stations routinely monitored at the site. The ground water data are used for site characterization and risk assessment. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the U.S. Environmental Protection Agency (EPA) regulations in 40 CFR Part 192 (1994) and the final EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), and the most effective technical approach for the site

  10. Sample summary report for KOR1 pressure tube sample

    International Nuclear Information System (INIS)

    Lee, Hee Jong; Nam, Min Woo; Choi, Young Ha

    2006-01-01

    This summary report includes basically the following: - The FLAW CHARACTERIZATION TABLE of KOR1 sample and supporting documentation. - The CROSS REFERENCE TABLES for each investigator, which is the SAMPLE INSPECTION TABLE that cross reference to the FLAW CHARACTERIZATION TABLE. - Each Sample Inspection Report as Appendices

  11. Drone Mission Definition and Implementation for Automated Infrastructure Inspection Using Airborne Sensors.

    Science.gov (United States)

    Besada, Juan A; Bergesio, Luca; Campaña, Iván; Vaquero-Melchor, Diego; López-Araquistain, Jaime; Bernardos, Ana M; Casar, José R

    2018-04-11

    This paper describes a Mission Definition System and the automated flight process it enables to implement measurement plans for discrete infrastructure inspections using aerial platforms, and specifically multi-rotor drones. The mission definition aims at improving planning efficiency with respect to state-of-the-art waypoint-based techniques, using high-level mission definition primitives and linking them with realistic flight models to simulate the inspection in advance. It also provides flight scripts and measurement plans which can be executed by commercial drones. Its user interfaces facilitate mission definition, pre-flight 3D synthetic mission visualisation and flight evaluation. Results are delivered for a set of representative infrastructure inspection flights, showing the accuracy of the flight prediction tools in actual operations using automated flight control.

  12. Hydrogeologic investigations sampling plan: Revision 0

    International Nuclear Information System (INIS)

    1988-11-01

    The goal of this sampling plan is to identify and develop specific plans for those investigative actions necessary to: (1) characterize the hydrologic regime; (2) define the extent and impact of contamination; and (3) predict future contaminant migration for the Weldon Spring Site (WSS) and vicinity. The plan is part of the Weldon Spring Site Remedial Action Project (WSSRAP) sponsored by the US Department of Energy (DOE) and has been developed in accordance with US EPA Remedial Investigation (RI) and Data Quality Objective (DQO) guidelines. The plan consists of a sequence of activities including the evaluation of data, development of a conceptual model, identification of data uses and needs, and the design and implementation of a data collection program. Data will be obtained to: (1) confirm the presence or absence of contaminants; (2) define contaminant sources and modes of transport; (3) delineate extent of contaminant migration and predict future migration; and (4) provide information to support the evaluation and selection of remedial actions. 81 refs., 62 figs., 26 tabs

  13. UMTRA project water sampling and analysis plan, Maybell, Colorado

    International Nuclear Information System (INIS)

    1994-06-01

    This water sampling and analysis plan (WSAP) describes planned water sampling activities and provides the regulatory and technical basis for ground water sampling in 1994 at the US Department of Energy's (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Maybell, Colorado. The WSAP identifies and justifies sampling locations, analytical parameters, and sampling frequencies at the site. The ground water data will be used for site characterization and risk assessment. The regulatory basis for the ground water and surface water monitoring activities is derived from the EPA regulations in 40 CFR Part 192 (1993) and the proposed EPA standards of 1987 (52 FR 36000). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site. This WSAP also includes a summary and the results of water sampling activities from 1989 through 1992 (no sampling was performed in 1993)

  14. The Toggle Local Planner for sampling-based motion planning

    KAUST Repository

    Denny, Jory; Amato, Nancy M.

    2012-01-01

    Sampling-based solutions to the motion planning problem, such as the probabilistic roadmap method (PRM), have become commonplace in robotics applications. These solutions are the norm as the dimensionality of the planning space grows, i.e., d > 5

  15. Do OSHA Inspections Reduce Injuries? A Panel Analysis

    OpenAIRE

    Wayne B. Gray; John T. Scholz

    1991-01-01

    Using data on injuries and OSHA inspections for 6,842 large manufacturing plants between 1979 and 1985, we find evidence that OSHA inspections significantly reduce injuries. This effect comes exclusively from inspections that impose penalties, inspections which do not impose penalties appear to have no effect on injuries. Plants which are inspected (and penalized) in a given year experience a 22 percent decline in their injuries during the following few years. In our sample, total OSHA enforc...

  16. 7 CFR 868.61 - How to request appeal inspection service.

    Science.gov (United States)

    2010-01-01

    ... may be made with the Board of Appeals and Review or the field office that performed the appeal... application shall be made: (i) Before the rice has left the place where the inspection being appealed was... inspection be based on: (i) The file sample or (ii) a new sample. However, an appeal inspection shall be...

  17. Plant inspection tours with mobile data logging system

    International Nuclear Information System (INIS)

    Roesser, U.

    2006-01-01

    The MDE Mobile Data Logging System has been introduced in a number of German power plants for efficient logging, evaluation, and quality-assured documentation of data recorded on plant inspection tours by means of pocket PCs instead of slips of paper. It will be installed in other nuclear power plants in the near future. The MDE system is composed of the pocket PCs for logging data during plant inspection tours, the associated docking stations installed in the respective areas of application, one PC or, if necessary, several PCs with the appropriate user software, and the associated network links. To install the software in the power plant, lists of rooms and measurement stations as well as other positions on an inspection course are transmitted to the MDE system. When the system has been commissioned, inspection tours are planned in accordance with past experience and optimized in the computer. User experience is taken into account in program updates. New functions improve user comfort and ease of evaluation. Additions to the MDE software, and applications in other areas, are tentatively planned and will be implemented as the need arises. (orig.)

  18. Activities for turbine maintenance: planning, implementation and evaluation of inspection results; Actividades para el mantenimiento de la turbina: planificacion, ejecucion y evaluacion de resultados de las inspecciones

    Energy Technology Data Exchange (ETDEWEB)

    Azcue, J.; Sanchez, M. A.; Alvaro, M.

    2014-04-01

    The article will cover the most significant aspects of how Tecnatom carry out the turbine maintenance work, both from the point of view of the inspection itself as the pre-and post tasks associated. Thus, the issues that will be part of the article are the Manual Inspection Service (MISI) and the inspection database, ISI WEB. These tools are essential for planning field work and serve as a guide to run later turbine inspections in different plants. Following this introduction the inspection teams and the techniques used by Tecnatom will be described. finally, the article will contain a small mention about management studies of life and integrity analysis of the turbine that can be performed, as well as involvement in its safe operation that is derived from them. Ultimately, the intention is to provide a comprehensive approach to the issue in question, the turbine maintenance work, so that the reader can get an ideal of the whole process. (Author)

  19. Development of an automatic reactor inspection system

    International Nuclear Information System (INIS)

    Kim, Jae Hee; Eom, Heung Seop; Lee, Jae Cheol; Choi, Yoo Raek; Moon, Soon Seung

    2002-02-01

    Using recent technologies on a mobile robot computer science, we developed an automatic inspection system for weld lines of the reactor vessel. The ultrasonic inspection of the reactor pressure vessel is currently performed by commercialized robot manipulators. Since, however, the conventional fixed type robot manipulator is very huge, heavy and expensive, it needs long inspection time and is hard to handle and maintain. In order to resolve these problems, we developed a new automatic inspection system using a small mobile robot crawling on the vertical wall of the reactor vessel. According to our conceptual design, we developed the reactor inspection system including an underwater inspection robot, a laser position control subsystem, an ultrasonic data acquisition/analysis subsystem and a main control subsystem. We successfully carried out underwater experiments on the reactor vessel mockup, and real reactor ready for Ulchine nuclear power plant unit 6 at Dusan Heavy Industry in Korea. After this project, we have a plan to commercialize our inspection system. Using this system, we can expect much reduction of the inspection time, performance enhancement, automatic management of inspection history, etc. In the economic point of view, we can also expect import substitution more than 4 million dollars. The established essential technologies for intelligent control and automation are expected to be synthetically applied to the automation of similar systems in nuclear power plants

  20. UMTRA Project water sampling and analysis plan, Gunnison, Colorado: Revision 1

    International Nuclear Information System (INIS)

    1994-11-01

    This water sampling and analysis plan summarizes the results of previous water sampling activities and the plan for future water sampling activities, in accordance with the Guidance Document for Preparing Sampling and Analysis Plans for UMTRA Sites. A buffer zone monitoring plan for the Dos Rios Subdivision is included as an appendix. The buffer zone monitoring plan was developed to ensure continued protection to the public from residual contamination. The buffer zone is beyond the area depicted as contaminated ground water due to former milling operations. Surface remedial action at the Gunnison Uranium Mill Tailings Remedial Action Project site began in 1992; completion is expected in 1995. Ground water and surface water will be sampled semiannually at the Gunnison processing site and disposal site. Results of previous water sampling at the Gunnison processing site indicate that ground water in the alluvium is contaminated by the former uranium processing activities. Background ground water conditions have been established in the uppermost aquifer at the Gunnison disposal site. The monitor well locations provide a representative distribution of sampling points to characterize ground water quality and ground water flow conditions in the vicinity of the sites. The list of analytes has been modified with time to reflect constituents that are related to uranium processing activities and the parameters needed for geochemical evaluation

  1. Sample collection and sample analysis plan in support of the 105-C/190-C concrete and soil sampling activities

    International Nuclear Information System (INIS)

    Marske, S.G.

    1996-07-01

    This sampling and analysis plan describes the sample collection and sample analysis in support of the 105-C water tunnels and 190-C main pumphouse concrete and soil sampling activities. These analytical data will be used to identify the radiological contamination and presence of hazardous materials to support the decontamination and disposal activities

  2. An inspection standard of fuel for the high temperature engineering test reactor

    International Nuclear Information System (INIS)

    Kobayashi, Fumiaki; Shiozawa, Shusaku; Sawa, Kazuhiro; Sato, Sadao; Hayashi, Kimio; Fukuda, Kosaku; Kaneko, Mitsunobu; Sato, Tsutomu.

    1992-06-01

    The High Temperature Engineering Test Reactor (HTTR) uses the fuel comprising coated fuel particles. A general inspection standard for the coated particle fuel, however, has not been established in Japan. Therefore, it has been necessary to prescribe the inspection standard of the fuel for HTTR. Under these circumstances, a fuel inspection standard of HTTR has been established under cooperation of fuel specialists both inside and outside of JAERI on referring to the inspection methods adopted in USA, Germany and Japan for HTGR fuels. Since a large number of coated fuel particle samples is needed to inspect the HTTR fuel, the sampling inspection standard has also been established considering the inspection efficiency. This report presents the inspection and the sampling standards together with an explanation of these standards. These standards will be applied to the HTTR fuel acceptance tests. (author)

  3. UMTRA water sampling and analysis plan, Green River, Utah

    International Nuclear Information System (INIS)

    Papusch, R.

    1993-12-01

    The purpose of this water sampling and analysis plan (WSAP) is to provide a basis for groundwater and surface water sampling at the Green River Uranium Mill Tailing Remedial Action (UMTRA) Project site. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the monitoring locations

  4. Compatibility Grab Sampling and Analysis Plan for Fiscal Year 2001

    International Nuclear Information System (INIS)

    LAURICELLA, T.L.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for grab samples obtained to address waste compatibility

  5. Nitrate Waste Treatment Sampling and Analysis Plan

    Energy Technology Data Exchange (ETDEWEB)

    Vigil-Holterman, Luciana R. [Los Alamos National Laboratory; Martinez, Patrick Thomas [Los Alamos National Laboratory; Garcia, Terrence Kerwin [Los Alamos National Laboratory

    2017-07-05

    This plan is designed to outline the collection and analysis of nitrate salt-bearing waste samples required by the New Mexico Environment Department- Hazardous Waste Bureau in the Los Alamos National Laboratory (LANL) Hazardous Waste Facility Permit (Permit).

  6. Sampling plans for pest mites on physic nut.

    Science.gov (United States)

    Rosado, Jander F; Sarmento, Renato A; Pedro-Neto, Marçal; Galdino, Tarcísio V S; Marques, Renata V; Erasmo, Eduardo A L; Picanço, Marcelo C

    2014-08-01

    The starting point for generating a pest control decision-making system is a conventional sampling plan. Because the mites Polyphagotarsonemus latus and Tetranychus bastosi are among the most important pests of the physic nut (Jatropha curcas), in the present study, we aimed to establish sampling plans for these mite species on physic nut. Mite densities were monitored in 12 physic nut crops. Based on the obtained results, sampling of P. latus and T. bastosi should be performed by assessing the number of mites per cm(2) in 160 samples using a handheld 20× magnifying glass. The optimal sampling region for T. bastosi is the abaxial surface of the 4th most apical leaf on the branch of the middle third of the canopy. On the abaxial surface, T. bastosi should then be observed on the side parts of the middle portion of the leaf, near its edge. As for P. latus, the optimal sampling region is the abaxial surface of the 4th most apical leaf on the branch of the apical third of the canopy on the abaxial surface. Polyphagotarsonemus latus should then be assessed on the side parts of the leaf's petiole insertion. Each sampling procedure requires 4 h and costs US$ 7.31.

  7. Using Load Balancing to Scalably Parallelize Sampling-Based Motion Planning Algorithms

    KAUST Repository

    Fidel, Adam; Jacobs, Sam Ade; Sharma, Shishir; Amato, Nancy M.; Rauchwerger, Lawrence

    2014-01-01

    Motion planning, which is the problem of computing feasible paths in an environment for a movable object, has applications in many domains ranging from robotics, to intelligent CAD, to protein folding. The best methods for solving this PSPACE-hard problem are so-called sampling-based planners. Recent work introduced uniform spatial subdivision techniques for parallelizing sampling-based motion planning algorithms that scaled well. However, such methods are prone to load imbalance, as planning time depends on region characteristics and, for most problems, the heterogeneity of the sub problems increases as the number of processors increases. In this work, we introduce two techniques to address load imbalance in the parallelization of sampling-based motion planning algorithms: an adaptive work stealing approach and bulk-synchronous redistribution. We show that applying these techniques to representatives of the two major classes of parallel sampling-based motion planning algorithms, probabilistic roadmaps and rapidly-exploring random trees, results in a more scalable and load-balanced computation on more than 3,000 cores. © 2014 IEEE.

  8. Using Load Balancing to Scalably Parallelize Sampling-Based Motion Planning Algorithms

    KAUST Repository

    Fidel, Adam

    2014-05-01

    Motion planning, which is the problem of computing feasible paths in an environment for a movable object, has applications in many domains ranging from robotics, to intelligent CAD, to protein folding. The best methods for solving this PSPACE-hard problem are so-called sampling-based planners. Recent work introduced uniform spatial subdivision techniques for parallelizing sampling-based motion planning algorithms that scaled well. However, such methods are prone to load imbalance, as planning time depends on region characteristics and, for most problems, the heterogeneity of the sub problems increases as the number of processors increases. In this work, we introduce two techniques to address load imbalance in the parallelization of sampling-based motion planning algorithms: an adaptive work stealing approach and bulk-synchronous redistribution. We show that applying these techniques to representatives of the two major classes of parallel sampling-based motion planning algorithms, probabilistic roadmaps and rapidly-exploring random trees, results in a more scalable and load-balanced computation on more than 3,000 cores. © 2014 IEEE.

  9. Decontamination and inspection plan for Phase 3 closure of the 300 area waste acid treatment system

    International Nuclear Information System (INIS)

    LUKE, S.N.

    1999-01-01

    This decontamination and inspection plan (DIP) describes decontamination and verification activities in support of Phase 3 closure of the 300 Area Waste Acid Treatment System (WATS). Phase 3 is the third phase of three WATS closure phases. Phase 3 attains clean closure conditions for WATS portions of the 334 and 311 Tank Farms (TF) and the 333 and 303-F Buildings. This DIP also describes designation and management of waste and debris generated during Phase 3 closure activities. Information regarding Phase 1 and Phase 2 for decontamination and verification activities closure can be found in WHC-SD-ENV-AP-001 and HNF-1784, respectively. This DIP is provided as a supplement to the closure plan (DOE/RL-90-11). This DIP provides the documentation for Ecology concurrence with Phase 3 closure methods and activities. This DIP is intended to provide greater detail than is contained in the closure plan to satisfy Ecology Dangerous Waste Regulations, Washington Administrative Code (WAC) 173-303-610 requirement that closure documents describe the methods for removing, transporting, storing, and disposing of all dangerous waste at the unit. The decontamination and verification activities described in this DIP are based on the closure plan and on agreements reached between Ecology and the U.S. Department of Energy, Richland Operations Office (DOE-RL) during Phase 3 closure activity workshops and/or project manager meetings (PMMs)

  10. Enhancement of the reliability of automated ultrasonic inspections using tools of quantitative NDT

    International Nuclear Information System (INIS)

    Kappes, W.; Baehr, W.; Kroening, M.; Schmitz, V.

    1994-01-01

    To achieve reliable test results from automated ultrasonic inspection of safety related components, optimization and integral consideration of the various inspection stages - inspection planning, inspection performance and evaluation of results - are indispensable. For this purpose, a large potential of methods is available: advanced measurement techniques, mathematical-numerical modelling processes, artificial intelligence tools, data bases and CAD systems. The potential inherent in these methods to enhance inspection reliability is outlined by way of different applications. (orig.) [de

  11. UMTRA Project water sampling and analysis plan, Salt Lake City, Utah. Revision 1

    International Nuclear Information System (INIS)

    1995-06-01

    This water sampling and analysis plan describes planned, routine ground water sampling activities at the US Department of Energy Uranium Mill Tailings Remedial Action Project site in Salt Lake City, Utah. This plan identifies and justifies sampling locations, analytical parameters, detection limits, and sampling frequencies for routine monitoring of ground water, sediments, and surface waters at monitoring stations on the site

  12. Optimal Inspection Planning for Fatigue Damage of Offshore Structures

    DEFF Research Database (Denmark)

    Madsen, H.O.; Sørensen, John Dalsgaard; Olesen, R.

    1990-01-01

    A formulation of optimal design, inspection and maintenance against damage caused by fatigue crack growth is formulated. A stochastic model for fatigue crack growth based on linear elastic fracture mechanics Is applied. Failure is defined by crack growth beyond a critical crack size. The failure ...

  13. An inspection demonstration program/a quality system

    International Nuclear Information System (INIS)

    Cox, L.D.

    1995-01-01

    Mobil relies on tubular manufacturers to consistently supply OCTG which complies with all material requirements of API Specification 5CT. This paper details the Mobil Inspection Demonstration Program; Mobil's method for qualifying ultrasonic inspection systems for use during Mobil receiving inspections. Additionally, the basic fundamentals of the Mobil quality system and acceptance sampling are presented with an emphasis on tracking short-term and long-term supplier performance

  14. Massively parallel E-beam inspection: enabling next-generation patterned defect inspection for wafer and mask manufacturing

    Science.gov (United States)

    Malloy, Matt; Thiel, Brad; Bunday, Benjamin D.; Wurm, Stefan; Mukhtar, Maseeh; Quoi, Kathy; Kemen, Thomas; Zeidler, Dirk; Eberle, Anna Lena; Garbowski, Tomasz; Dellemann, Gregor; Peters, Jan Hendrik

    2015-03-01

    SEMATECH aims to identify and enable disruptive technologies to meet the ever-increasing demands of semiconductor high volume manufacturing (HVM). As such, a program was initiated in 2012 focused on high-speed e-beam defect inspection as a complement, and eventual successor, to bright field optical patterned defect inspection [1]. The primary goal is to enable a new technology to overcome the key gaps that are limiting modern day inspection in the fab; primarily, throughput and sensitivity to detect ultra-small critical defects. The program specifically targets revolutionary solutions based on massively parallel e-beam technologies, as opposed to incremental improvements to existing e-beam and optical inspection platforms. Wafer inspection is the primary target, but attention is also being paid to next generation mask inspection. During the first phase of the multi-year program multiple technologies were reviewed, a down-selection was made to the top candidates, and evaluations began on proof of concept systems. A champion technology has been selected and as of late 2014 the program has begun to move into the core technology maturation phase in order to enable eventual commercialization of an HVM system. Performance data from early proof of concept systems will be shown along with roadmaps to achieving HVM performance. SEMATECH's vision for moving from early-stage development to commercialization will be shown, including plans for development with industry leading technology providers.

  15. Tank 241-BY-105 rotary core sampling and analysis plan

    International Nuclear Information System (INIS)

    Sasaki, L.M.

    1995-01-01

    This Sampling and Analysis Plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for two rotary-mode core samples from tank 241-BY-105 (BY-105)

  16. Risk-based priorities for inspection of nuclear pressure boundary components at selected LWRs

    International Nuclear Information System (INIS)

    Vo, T.V.; Simonen, F.A.; Gore, B.F.; Doctor, S.R.; Smith, B.W.

    1990-01-01

    Data from existing probabilistic risk assessments for eight representative nuclear power plants were used to identify and prioritize the most relevant systems to plant safety. The objective of this paper is to assess current in-service inspection requirements for pressure boundary systems and components, and to develop recommendations for improvements. This study demonstrates the feasibility of using risk-based methods to develop plant-specific inspection plans. Results for the eight representative plants also indicate generic trends that suggest improvements in current inspection plans now based on priorities set in accordance with code definitions of Class 1, 2, and 3 systems

  17. Risk-based priorities for inspection of nuclear pressure boundary components at selected LWRs

    International Nuclear Information System (INIS)

    Vo, T.V.; Simonen, F.A.; Gore, B.F.; Doctor, S.R.; Smith, B.W.

    1990-03-01

    Data from existing probabilistic risk assessments for eight representative nuclear power plants were used to identify and prioritize the most relevant systems to plant safety. The objective was to assess current in-service inspection requirements for pressure boundary systems and components, and to develop recommendations for improvements. This study demonstrates the feasibility of using risk-based methods to develop plant-specific inspection plans. Results for the eight representative plants also indicate generic trends that suggest improvements in current inspection plans now based on priorities set in accordance with code definitions of Class 1, 2, and 3 systems. 2 refs., 4 figs., 5 tabs

  18. Study on In-Service Inspection Program and Inspection Technologies for Commercialized Sodium-Cooled Fast Reactor

    International Nuclear Information System (INIS)

    Masato Ando; Shigenobu Kubo; Yoshio Kamishima; Toru Iitsuka

    2006-01-01

    The objective of in-service inspection of a nuclear power plant is to confirm integrity of function of components necessary to safety, and satisfy the needs to protect plant investment and to achieve high plant ability. The sodium-cooled fast reactor, which is designed in the feasibility study on commercialized fast reactor cycle systems in Japan, has two characteristics related to in-service inspection. The first is that all sodium coolant boundary structures have double-wall system. Continuous monitoring of the sodium coolant boundary structures are adopted for inspection. The second characteristic is the steam generator with double-wall-tubes. Volumetric testing is adopted to make sure that one of the tubes can maintain the boundary function in case of the other tube failure. A rational in-service inspection concept was developed taking these features into account. The inspection technologies were developed to implement in-service inspection plan. The under-sodium viewing system consisted of multi ultrasonic scanning transducers, which was used for imaging under-sodium structures. The under-sodium viewing system was mounted on the under-sodium vehicle and delivered to core internals. The prototype of under-sodium viewing system and vehicle were fabricated and performance tests were carried out under water. The laboratory experiments of volumetric testing for double-wall-tubes of steam generator, such as ultrasonic testing and remote-field eddy current testing, were performed and technical feasibility was assessed. (authors)

  19. 105-DR Large Sodium Fire Facility decontamination, sampling, and analysis plan

    International Nuclear Information System (INIS)

    Knaus, Z.C.

    1995-01-01

    This is the decontamination, sampling, and analysis plan for the closure activities at the 105-DR Large Sodium Fire Facility at Hanford Reservation. This document supports the 105-DR Large Sodium Fire Facility Closure Plan, DOE-RL-90-25. The 105-DR LSFF, which operated from about 1972 to 1986, was a research laboratory that occupied the former ventilation supply room on the southwest side of the 105-DR Reactor facility in the 100-D Area of the Hanford Site. The LSFF was established to investigate fire fighting and safety associated with alkali metal fires in the liquid metal fast breeder reactor facilities. The decontamination, sampling, and analysis plan identifies the decontamination procedures, sampling locations, any special handling requirements, quality control samples, required chemical analysis, and data validation needed to meet the requirements of the 105-DR Large Sodium Fire Facility Closure Plan in compliance with the Resource Conservation and Recovery Act

  20. Reachable Distance Space: Efficient Sampling-Based Planning for Spatially Constrained Systems

    KAUST Repository

    Xinyu Tang,

    2010-01-25

    Motion planning for spatially constrained robots is difficult due to additional constraints placed on the robot, such as closure constraints for closed chains or requirements on end-effector placement for articulated linkages. It is usually computationally too expensive to apply sampling-based planners to these problems since it is difficult to generate valid configurations. We overcome this challenge by redefining the robot\\'s degrees of freedom and constraints into a new set of parameters, called reachable distance space (RD-space), in which all configurations lie in the set of constraint-satisfying subspaces. This enables us to directly sample the constrained subspaces with complexity linear in the number of the robot\\'s degrees of freedom. In addition to supporting efficient sampling of configurations, we show that the RD-space formulation naturally supports planning and, in particular, we design a local planner suitable for use by sampling-based planners. We demonstrate the effectiveness and efficiency of our approach for several systems including closed chain planning with multiple loops, restricted end-effector sampling, and on-line planning for drawing/sculpting. We can sample single-loop closed chain systems with 1,000 links in time comparable to open chain sampling, and we can generate samples for 1,000-link multi-loop systems of varying topologies in less than a second. © 2010 The Author(s).

  1. Sampling plans in attribute mode with multiple levels of precision

    International Nuclear Information System (INIS)

    Franklin, M.

    1986-01-01

    This paper describes a method for deriving sampling plans for nuclear material inventory verification. The method presented is different from the classical approach which envisages two levels of measurement precision corresponding to NDA and DA. In the classical approach the precisions of the two measurement methods are taken as fixed parameters. The new approach is based on multiple levels of measurement precision. The design of the sampling plan consists of choosing the number of measurement levels, the measurement precision to be used at each level and the sample size to be used at each level

  2. UMTRA Project water sampling and analysis plan, Grand Junction, Colorado. Revision 1, Version 6

    International Nuclear Information System (INIS)

    1995-09-01

    This water sampling and analysis plan describes the planned, routine ground water sampling activities at the Grand Junction US DOE Uranium Mill Tailings Remedial Action (UMTRA) Project site (GRJ-01) in Grand Junction, Colorado, and at the Cheney Disposal Site (GRJ-03) near Grand Junction. The plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequencies for the routine monitoring stations at the sites. Regulatory basis is in the US EPA regulations in 40 CFR Part 192 (1994) and EPA ground water quality standards of 1995 (60 FR 2854). This plan summarizes results of past water sampling activities, details water sampling activities planned for the next 2 years, and projects sampling activities for the next 5 years

  3. Sampling and Analysis Plan for PUREX canyon vessel flushing

    International Nuclear Information System (INIS)

    Villalobos, C.N.

    1995-01-01

    A sampling and analysis plan is necessary to provide direction for the sampling and analytical activities determined by the data quality objectives. This document defines the sampling and analysis necessary to support the deactivation of the Plutonium-Uranium Extraction (PUREX) facility vessels that are regulated pursuant to Washington Administrative Code 173-303

  4. UMTRA water sampling and analysis plan, Tuba City, Arizona

    International Nuclear Information System (INIS)

    1993-09-01

    The purpose of this document is to provide background, guidance, and justification for fiscal year (FY) 1994 water sampling activities for the uranium mil tailings site at Tuba City, Arizona. This sampling and analysis plan will form the basis for groundwater sampling and analysis work orders to be implemented in FY94

  5. Visual Sample Plan (VSP) Software: Designs and Data Analyses for Sampling Contaminated Buildings

    International Nuclear Information System (INIS)

    Pulsipher, Brent A.; Wilson, John E.; Gilbert, Richard O.; Nuffer, Lisa L.; Hassig, Nancy L.

    2005-01-01

    A new module of the Visual Sample Plan (VSP) software has been developed to provide sampling designs and data analyses for potentially contaminated buildings. An important application is assessing levels of contamination in buildings after a terrorist attack. This new module, funded by DHS through the Combating Terrorism Technology Support Office, Technical Support Working Group, was developed to provide a tailored, user-friendly and visually-orientated buildings module within the existing VSP software toolkit, the latest version of which can be downloaded from http://dqo.pnl.gov/vsp. In case of, or when planning against, a chemical, biological, or radionuclide release within a building, the VSP module can be used to quickly and easily develop and visualize technically defensible sampling schemes for walls, floors, ceilings, and other surfaces to statistically determine if contamination is present, its magnitude and extent throughout the building and if decontamination has been effective. This paper demonstrates the features of this new VSP buildings module, which include: the ability to import building floor plans or to easily draw, manipulate, and view rooms in several ways; being able to insert doors, windows and annotations into a room; 3-D graphic room views with surfaces labeled and floor plans that show building zones that have separate air handing units. The paper will also discuss the statistical design and data analysis options available in the buildings module. Design objectives supported include comparing an average to a threshold when the data distribution is normal or unknown, and comparing measurements to a threshold to detect hotspots or to insure most of the area is uncontaminated when the data distribution is normal or unknown

  6. Nonradioactive Dangerous Waste Landfill sampling and analysis plan and data quality objectives process summary report

    International Nuclear Information System (INIS)

    Smith, R.C.

    1997-08-01

    This sampling and analysis plan defines the sampling and analytical activities and associated procedures that will be used to support the Nonradioactive Dangerous Waste Landfill soil-gas investigation. This SAP consists of three sections: this introduction, the field sampling plan, and the quality assurance project plan. The field sampling plan defines the sampling and analytical methodologies to be performed

  7. Development of sample size allocation program using hypergeometric distribution

    International Nuclear Information System (INIS)

    Kim, Hyun Tae; Kwack, Eun Ho; Park, Wan Soo; Min, Kyung Soo; Park, Chan Sik

    1996-01-01

    The objective of this research is the development of sample allocation program using hypergeometric distribution with objected-oriented method. When IAEA(International Atomic Energy Agency) performs inspection, it simply applies a standard binomial distribution which describes sampling with replacement instead of a hypergeometric distribution which describes sampling without replacement in sample allocation to up to three verification methods. The objective of the IAEA inspection is the timely detection of diversion of significant quantities of nuclear material, therefore game theory is applied to its sampling plan. It is necessary to use hypergeometric distribution directly or approximate distribution to secure statistical accuracy. Improved binomial approximation developed by Mr. J. L. Jaech and correctly applied binomial approximation are more closer to hypergeometric distribution in sample size calculation than the simply applied binomial approximation of the IAEA. Object-oriented programs of 1. sample approximate-allocation with correctly applied standard binomial approximation, 2. sample approximate-allocation with improved binomial approximation, and 3. sample approximate-allocation with hypergeometric distribution were developed with Visual C ++ and corresponding programs were developed with EXCEL(using Visual Basic for Application). 8 tabs., 15 refs. (Author)

  8. GASVOL 18'' gas pipeline - risk based inspection study

    Energy Technology Data Exchange (ETDEWEB)

    Bjoernoey, Ola H.; Etterdal, Birger A. [Det Norske Veritas (DNV), Oslo (Norway); Guarize, Rosimar; Oliveira, Luiz F.S. [Det Norske Veritas (DNV) (Brazil); Faertes, Denise; Dias, Ricardo [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper describes a risk based approach and inspection planning as part of the Pipeline Integrity Management (PIM) system for the 95.5 km long 18'' GASVOL gas pipeline in the South eastern region of Brazil transporting circa 5 000 000 m3 dry gas per day. Pipeline systems can be subject to several degradation mechanisms and inspection and monitoring are used to ensure system integrity. Modern pipeline regulations and codes are normally based on a core safety or risk philosophy. The detailed design requirements presented in design codes are practical interpretations established so as to fulfill these core objectives. A given pipeline, designed, constructed and installed according to a pipeline code is therefore the realization of a structure, which, along its whole length, meets the applicable safety objectives of that code. The main objective of Pipeline Integrity Management (PIM) is to control and document the integrity of the pipeline for its whole service life, and to do this in a cost-effective manner. DNV has a specific approach to RBI planning, starting with an initial qualitative assessment where pipelines and damage type are ranked according to risk and potential risk reduction by an inspection and then carried forward to a quantitative detailed assessment where the level of complexity and accuracy can vary based on availability of information and owner needs. Detailed assessment requires significant effort in data gathering. The findings are dependent upon the accuracy of the inspection data, and on DNV's interpretation of the pipeline reference system and simplifications in the inspection data reported. The following specific failure mechanisms were investigated: internal corrosion, external corrosion, third party interference, landslides and black powder. RBI planning, in general words, is a 'living process'. In order to optimize future inspections, it is essential that the analyses utilize the most recent information regarding

  9. Background Information for the Nevada National Security Site Integrated Sampling Plan, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Farnham, Irene; Marutzky, Sam

    2014-12-01

    This document describes the process followed to develop the Nevada National Security Site (NNSS) Integrated Sampling Plan (referred to herein as the Plan). It provides the Plan’s purpose and objectives, and briefly describes the Underground Test Area (UGTA) Activity, including the conceptual model and regulatory requirements as they pertain to groundwater sampling. Background information on other NNSS groundwater monitoring programs—the Routine Radiological Environmental Monitoring Plan (RREMP) and Community Environmental Monitoring Program (CEMP)—and their integration with the Plan are presented. Descriptions of the evaluations, comments, and responses of two Sampling Plan topical committees are also included.

  10. 105-N Basin sediment disposition phase-one sampling and analysis plan

    International Nuclear Information System (INIS)

    1997-01-01

    The sampling and analysis plan (SAP) for Phase 1 of the 105-N Basin sediment disposition project defines the sampling and analytical activities that will be performed for the engineering assessment phase (phase 1) of the project. A separate SAP defines the sampling and analytical activities that will be performed for the characterization phase (Phase 2) of the 105-N sediment disposition project. The Phase-1 SAP is presented in the introduction (Section 1.0), in the field sampling plan (FSP) (Section 2.0), and in the quality assurance project plan (QAPjP) (Section 3.0). The FSP defines the sampling and analytical methodologies to be performed. The QAPjP provides information on the quality assurance/quality control (QA/QC) parameters related to the sampling and analytical methodologies. This SAP defines the strategy and the methods that will be used to sample and analyze the sediment on the floor of the 105-N Basin. The resulting data will be used to develop and evaluate engineering designs for collecting and removing sediment from the basin

  11. UMTRA Project water sampling and analysis plan, Durango, Colorado. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    Planned, routine ground water sampling activities at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Durango, Colorado, are described in this water sampling and analysis plan. The plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the routine monitoring stations at the site. The ground water data are used to characterize the site ground water compliance strategies and to monitor contaminants of potential concern identified in the baseline risk assessment (DOE, 1995a). Regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US EPA regulations in 40 CFR Part 192 (1994) and EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site

  12. Hanford Sampling Quality Management Plan (HSQMP)

    International Nuclear Information System (INIS)

    Hyatt, J.E.

    1995-01-01

    This document provides a management tool for evaluating and designing the appropriate elements of a field sampling program. This document provides discussion of the elements of a program and is to be used as a guidance document during the preparation of project and/or function specific documentation. This document does not specify how a sampling program shall be organized. The HSQMP is to be used as a companion document to the Hanford Analytical Services Quality Assurance Plan (HASQAP) DOE/RL-94-55. The generation of this document was enhanced by conducting baseline evaluations of current sampling organizations. Valuable input was received from members of field and Quality Assurance organizations. The HSQMP is expected to be a living document. Revisions will be made as regulations and or Hanford Site conditions warrant changes in the best management practices. Appendices included are: summary of the sampling and analysis work flow process, a user's guide to the Data Quality Objective process, and a self-assessment checklist

  13. Sampling and Analysis Plan for the 233-S Plutonium Concentration Facility

    International Nuclear Information System (INIS)

    Mihalic, M.A.

    1998-02-01

    This Sampling and Analysis Plan (SAP) provides the information and instructions to be used for sampling and analysis activities in the 233-S Plutonium Concentration Facility. The information and instructions herein are separated into three parts and address the Data Quality Objective (DQO) Summary Report, Quality Assurance Project Plan (QAP), and SAP

  14. Tank 241-AP-104 Grab Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    TEMPLETON, A.M.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AP-104. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AP-104 required to provide sample material to the Waste Treatment Contractor. Grab samples will be obtained from riser 001 to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives and ICD-23. The 222-S Laboratory will receive samples; composite the samples; perform chemical analyses on composite samples; and provide samples to the Waste Treatment Contractor and the Process Chemistry Laboratory. The Process Chemistry Laboratory at the 222-S Laboratory Complex will perform process tests to evaluate the behavior of the 241-AP-104 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. The Waste Treatment Contractor will perform process verification and waste form qualification tests. Requirements for analyses of samples originating in the L and H DQO process tests will be documented in the corresponding test plan (Person 2000) and are not within the scope of this SAP. This report provides the general methodology and procedures to be used in the preparation, retrieval, transport, analysis, and reporting of results from grab samples retrieved from tank 241-AP-104

  15. The SWAMI inspection robot: Fernald site requirements

    International Nuclear Information System (INIS)

    Hazen, F.B.

    1993-01-01

    The purpose of this document is to introduce and describe the Stored Waste Autonomous Mobile Inspector (SWAMI) robot project and to identify issues that will need to be addressed prior to its field demonstration at Fernald in mid-1995. SWAMI is a mobile robotic vehicle that will perform mandated weekly inspections of waste containers. Fernald has a large inventory of these containers and a need to protect workers from radiation hazards while enhancing the efficiency and effectiveness of the inspections. Fernald's role in this project is to supply the demonstration site and make all necessary preparations. This includes identification of the test areas and plans, and identification and compliance to Federal, State, DOE, and Site regulations on system safety and quality. In addition, Fernald will link SWAMI output images to off-line mass data storage, and also to an on-line ORACLE database. The authors shall initiate a dialog with State and Federal regulators towards the near term goal of acceptance of the SWAMI test plan and a longer term goal of acceptance of SWAMI as a supplement and improvement to present mandated RCRA inspections

  16. Inspection Qualification Centre in NPP 'Kozloduy'

    International Nuclear Information System (INIS)

    Mikhovski, M.

    2000-01-01

    In May 1999 according to the working plan of the IAEA project RER 4/020 and the decision of the NPP the Inspection Qualification Centre (IQC) has been established in order to provide examination services in the NPP. During year 1999 IVC (AEA Technology) in the framework of the DTI project provides consulting and technical assistance to the NPP, IQC, Bulgarian Academy of Sciences and Regulatory Authorities in setting up the IQC infrastructure. Now IQC work as an independent inspection body B type. The IQC activities for the period 1999-2000 are presented and further tasks are outlined

  17. 46 CFR 160.176-15 - Production tests and inspections.

    Science.gov (United States)

    2010-10-01

    ... known weight and winch, (B) a scale, winch, and fixed anchor, or (C) a tensile test machine that is... laboratory inspector tests and inspects the lot; (ii) Perform required testing of each incoming lot of... produced the components used in the lifejacket. (d) Samples. (1) Samples used in testing and inspections...

  18. Reliability Assessment and Reliability-Based Inspection and Maintenance of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Ramírez, José G. Rangel; Sørensen, John Dalsgaard

    2009-01-01

    Probabilistic methodologies represent an important tool to identify the suitable strategy to inspect and deal with the deterioration in structures such as offshore wind turbines (OWT). Reliability based methods such as Risk Based Inspection (RBI) planning may represent a proper methodology to opt...

  19. Supervision and inspection plans of plants activities; Plan de inspeccion y supervision de actividades en planta

    Energy Technology Data Exchange (ETDEWEB)

    Feijoo, J. P.

    2009-07-01

    Any idea of hierarchization between supervisor and supervised in inspection and supervision activities should necessarily be dismissed, and the independence of the supervisor when executing has tasks should be guaranteed. The inspection and supervision program enable the detection and resolution of materials and human problems alike. In addition, they are a solution to anticipate potential problems in the future, which results in a very significant reduction of industrial accidents and human errors, as well as better use and upkeep of equipment. With these programs we improve our management and our work, and without a doubt they help to strengthen the safety culture in Cofrentes Nuclear Power Plant. (Author)

  20. Reliability-based inspection of prestressed concrete containment structures

    International Nuclear Information System (INIS)

    Pandey, M.D.

    1996-03-01

    A study was undertaken to develop a reliability-based approach to the planning of inspection programs for prestressed concrete containment structures. The main function of the prestressing system is to ensure the leak integrity of the containment by maintaining a compressive state of stress under the tensile forces which arise in a hypothesized loss of coolant accident. Prestressing force losses (due to creep and shrinkage, stress relaxation or tendon corrosion) can lead to tensile stresses under accident pressure, resulting in loss of containment leak integrity due to concrete cracking and tensile yielding of the non-prestressed reinforcement. Therefore, the evaluation of prestressing inspection programs was based on their effectiveness in maintaining an acceptable reliability level with respect to a limit state representing yeilding of non-prestressed reinforcement. An annual target reliability of 10 -4 was used for this limit state. As specified in CSA-N287.7, the evaluation of prestressing systems for containment structures is based on the results of lift-off tests to determine the prestressing force. For unbonded systems the tests are carried out on a randomly selected sample from each tendon group in the structure. For bonded systems, the test is carried out on an unbonded test beam that matches the section geometry and material properties of the containment structure. It was found that flexural testing is useful in updating the probability of concrete cracking under accident pressure. For unbonded systems, the analysis indicated that the sample size recommended by the CSA Standard (4% of the tendon population) is adequate. The CSA recommendation for a five year inspection interval is conservative unless severe degradation of the prestressing system, characterized by a high prestressing loss rate (>3%) and a large coefficient of variation of the measured prestressing force (>15%), is observed

  1. Energy-Aware Path Planning for UAS Persistent Sampling and Surveillance

    Science.gov (United States)

    Shaw-Cortez, Wenceslao

    The focus of this work is to develop an energy-aware path planning algorithm that maximizes UAS endurance, while performing sampling and surveillance missions in a known, stationary wind environment. The energy-aware aspect is specifically tailored to extract energy from the wind to reduce thrust use, thereby increasing aircraft endurance. Wind energy extraction is performed by static soaring and dynamic soaring. Static soaring involves using upward wind currents to increase altitude and potential energy. Dynamic soaring involves taking advantage of wind gradients to exchange potential and kinetic energy. The path planning algorithm developed in this work uses optimization to combine these soaring trajectories with the overarching sampling and surveillance mission. The path planning algorithm uses a simplified aircraft model to tractably optimize soaring trajectories. This aircraft model is presented and along with the derivation of the equations of motion. A nonlinear program is used to create the soaring trajectories based on a given optimization problem. This optimization problem is defined using a heuristic decision tree, which defines appropriate problems given a sampling and surveillance mission and a wind model. Simulations are performed to assess the path planning algorithm. The results are used to identify properties of soaring trajectories as well as to determine what wind conditions support minimal thrust soaring. Additional results show how the path planning algorithm can be tuned between maximizing aircraft endurance and performing the sampling and surveillance mission. A means of trajectory stitching is demonstrated to show how the periodic soaring segments can be combined together to provide a full solution to an infinite/long horizon problem.

  2. Korean experience with steam turbine blade inspection

    International Nuclear Information System (INIS)

    Jung, Hyun Kyu; Park, D.Y.; Park, Hyung Jin; Chung, Min Hwa

    1990-01-01

    Several turbine blade accidents in Korea have emphasized the importance of their adequate periodic inspection. As a typical example, a broken blade was found in the Low Pressure (LP) turbine at the 950 MWe KORI unit 3 during the 1986 overhaul after one year commercial operation. Since then the Manufacturer and the Utility company (KEPCO) have been concerned about the need of blade root inspection. The ultrasonic testing was applied to detect cracks in the blade roots without removing the blades from rotor. Due to the complex geometry of the roots, the test results could not be evaluated easily. We feel that the currently applied UT technique seems to be less reliable and more effective method of inspection must be developed in the near future. This paper describes the following items: The causes and analysis of blade damage The inspection techniques and results The remedial action to be taken (Repair and Replacement) The future plan

  3. Test plan for core sampling drill bit temperature monitor

    International Nuclear Information System (INIS)

    Francis, P.M.

    1994-01-01

    At WHC, one of the functions of the Tank Waste Remediation System division is sampling waste tanks to characterize their contents. The push-mode core sampling truck is currently used to take samples of liquid and sludge. Sampling of tanks containing hard salt cake is to be performed with the rotary-mode core sampling system, consisting of the core sample truck, mobile exhauster unit, and ancillary subsystems. When drilling through the salt cake material, friction and heat can be generated in the drill bit. Based upon tank safety reviews, it has been determined that the drill bit temperature must not exceed 180 C, due to the potential reactivity of tank contents at this temperature. Consequently, a drill bit temperature limit of 150 C was established for operation of the core sample truck to have an adequate margin of safety. Unpredictable factors, such as localized heating, cause this buffer to be so great. The most desirable safeguard against exceeding this threshold is bit temperature monitoring . This document describes the recommended plan for testing the prototype of a drill bit temperature monitor developed for core sampling by Sandia National Labs. The device will be tested at their facilities. This test plan documents the tests that Westinghouse Hanford Company considers necessary for effective testing of the system

  4. Inspecting close maternal relatedness: Towards better mtDNA population samples in forensic databases.

    Science.gov (United States)

    Bodner, Martin; Irwin, Jodi A; Coble, Michael D; Parson, Walther

    2011-03-01

    Reliable data are crucial for all research fields applying mitochondrial DNA (mtDNA) as a genetic marker. Quality control measures have been introduced to ensure the highest standards in sequence data generation, validation and a posteriori inspection. A phylogenetic alignment strategy has been widely accepted as a prerequisite for data comparability and database searches, for forensic applications, for reconstructions of human migrations and for correct interpretation of mtDNA mutations in medical genetics. There is continuing effort to enhance the number of worldwide population samples in order to contribute to a better understanding of human mtDNA variation. This has often lead to the analysis of convenience samples collected for other purposes, which might not meet the quality requirement of random sampling for mtDNA data sets. Here, we introduce an additional quality control means that deals with one aspect of this limitation: by combining autosomal short tandem repeat (STR) marker with mtDNA information, it helps to avoid the bias introduced by related individuals included in the same (small) sample. By STR analysis of individuals sharing their mitochondrial haplotype, pedigree construction and subsequent software-assisted calculation of likelihood ratios based on the allele frequencies found in the population, closely maternally related individuals can be identified and excluded. We also discuss scenarios that allow related individuals in the same set. An ideal population sample would be representative for its population: this new approach represents another contribution towards this goal. Copyright © 2010 Elsevier Ireland Ltd. All rights reserved.

  5. Genesis Contingency Planning and Mishap Recovery: The Sample Curation View

    Science.gov (United States)

    Stansbery, E. K.; Allton, J. H.; Allen, C. C.; McNamara, K. M.; Calaway, M.; Rodriques, M. C.

    2007-01-01

    Planning for sample preservation and curation was part of mission design from the beginning. One of the scientific objectives for Genesis included collecting samples of three regimes of the solar wind in addition to collecting bulk solar wind during the mission. Collectors were fabricated in different thicknesses for each regime of the solar wind and attached to separate frames exposed to the solar wind during specific periods of solar activity associated with each regime. The original plan to determine the solar regime sampled for specific collectors was to identify to which frame the collector was attached. However, the collectors were dislodged during the hard landing making identification by frame attachment impossible. Because regimes were also identified by thickness of the collector, the regime sampled is identified by measuring fragment thickness. A variety of collector materials and thin films applied to substrates were selected and qualified for flight. This diversity provided elemental measurement in more than one material, mitigating effects of diffusion rates and/or radiation damage. It also mitigated against different material and substrate strengths resulting in differing effects of the hard landing. For example, silicon crystal substrates broke into smaller fragments than sapphire-based substrates and diamond surfaces were more resilient to flying debris damage than gold. The primary responsibility of the curation team for recovery was process documentation. Contingency planning for the recovery phase expanded this responsibility to include not only equipment to document, but also gather, contain and identify samples from the landing area and the recovered spacecraft. The team developed contingency plans for various scenarios as part of mission planning that included topographic maps to aid in site recovery and identification of different modes of transport and purge capability depending on damage. A clean tent, set-up at Utah Test & Training Range

  6. GIMIS - Integral Solution for the In-Service Inspection Management of Components in NPPs

    International Nuclear Information System (INIS)

    Borovic, Damir; Vukovic, Igor

    2014-01-01

    Performance of in-service testing and inspection of components and systems in nuclear power plants are required in order to maintain the nuclear power plant while in operation and to return the plant to service, following plant outages. GIMIS is comprehensive software that integrates all processes, functions and data related to planning, administrating and executing inspections on systems, structures and components in nuclear power plants. The software is designed as a web application developed using the Microsoft ASP.NET technology, database is a Microsoft SQL, and client is composed of JavaScript frameworks. It can be adapted to local language, regulations, and requirements according to the power plant needs. The application consists of seven interdependent modules, namely: components, equipment, personnel, requirements, inspection planning, inspection execution, and reports. GIMIS deals with component, equipment and personnel management (both internally employed and outsourced), also provides full component history including uploaded documentation, drawings, previous inspection results, and supports various types of requirements. It enables scheduling facilitation using component data and compliance requirements, offers generation of all inspection relevant documentation and reports, and covers the equipment management including calibration requirements, certification of equipment and allocation to specific inspections/outages, as well as personnel certifications and allocation to specific inspections/outages. The paper describes the content and functionality of the GIMIS application and provides information of its built-in capabilities and features. (authors)

  7. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2014

    Energy Technology Data Exchange (ETDEWEB)

    Silvas, A. J. [National Security Technologies, LLC, Las Vegas, NV (United States). Nevada Test Site; Lantow, Tiffany A. [National Security Technologies, LLC, Las Vegas, NV (United States). Nevada Test Site

    2015-03-25

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2014 and includes inspection and repair activities completed at the following CAUs; CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved Closure Reports and subsequent correspondence with the Nevada Division of Environmental Protection. The post-closure inspection plans and subsequent correspondence modifying the requirements for each CAU are included in Appendix B. The inspection checklists are included in Appendix C. Photographs taken during inspections are included in Appendix D. The annual post-closure inspections were conducted on May 28, 2014. Maintenance was required at CAU 407. Animal burrows were backfilled and erosion repairs were performed. Vegetation monitoring was performed at CAU 407 in June 2014. The vegetation monitoring report is included in Appendix E.

  8. CASTOR - Advanced System for VVER Steam Generator Inspection

    International Nuclear Information System (INIS)

    Mateljak, Petar

    2014-01-01

    From the safety point of view, steam generator is a very important component of a nuclear power plant. Only a thin tube wall prevents leakage of radioactive material from the primary side into the environment. Therefore, it is very important to perform inspections in order to detect pipe damage and apply appropriate corrective actions during outage. Application of the nondestructive examination (NDE) technique, that can locate degradation and measure its size and orientation, is an integral part of nuclear power plant maintenance. The steam generator inspection system is consisted of remotely controlled manipulator, testing instrument and software for data acquisition and analysis. Recently, the inspection systems have evolved to a much higher level of automation, efficiency and reliability resulting in a lower cost and shorter outage time. Electronic components have become smaller and deal with more complex algorithms. These systems are very fast, precise, reliable and easy to handle. The whole inspection, from the planning, examination, data analysis and final report, is now a highly automated process, which makes inspection much easier and more reliable. This paper presents the new generation of INETEC's VVER steam generator inspection system as ultimate solution for steam generator inspection and repair. (author)

  9. Tank 241-U-105 push mode core sampling and analysis plan

    International Nuclear Information System (INIS)

    Bell, K.E.

    1995-01-01

    This Sampling and Analysis Plan (SAP) will identify characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples and two push mode core samples from tank 241-U-105 (U-105)

  10. Sampling and analysis plan for the 100-D Ponds voluntary remediation project

    International Nuclear Information System (INIS)

    1996-08-01

    This Sampling and Analysis Plan (SAP) describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds Resource Conservation and Recovery Act (RCRA) treatment, storage, and/or disposal (TSD) unit. This SAP includes the Field Sampling Plan (FSP) presented in Section 2.0, and the Quality Assurance Project Plan (QAPjP) described in Section 3.0. The FSP defines the sampling and analytical methodologies to be performed, and the QAPjP provides or includes information on the requirements for precision, accuracy, representativeness, comparability, and completeness of the analytical data. This sampling and analysis plan was developed using the Environmental Protection Agency's Seven-Step Data Quality Objectives (DQO) Guidance (EPA, 1994). The purpose of the DQO meetings was (1) to identify the contaminants of concern and their cleanup levels under the Washington State Model Toxics Control Act (MTCA, WAC-173-340) Method B, and (2) to determine the number and locations of samples necessary to verify that the 100-D Ponds meet the cleanup criteria. The data collected will be used to support RCRA closure of this TSD unit

  11. Methodology for identifying and representing knowledge in the scope of CMM inspection resource selection

    Science.gov (United States)

    Martínez, S.; Barreiro, J.; Cuesta, E.; Álvarez, B. J.; González, D.

    2012-04-01

    This paper is focused on the task of elicitation and structuring of knowledge related to selection of inspection resources. The final goal is to obtain an informal model of knowledge oriented to the inspection planning in coordinate measuring machines. In the first tasks, where knowledge is captured, it is necessary to use tools that make easier the analysis and structuring of knowledge, so that rules of selection can be easily stated to configure the inspection resources. In order to store the knowledge a so-called Onto-Process ontology has been developed. This ontology may be of application to diverse processes in manufacturing engineering. This paper describes the decomposition of the ontology in terms of general units of knowledge and others more specific for selection of sensor assemblies in inspection planning with touch sensors.

  12. Comparisons of NDT Methods to Inspect Cork and Cork filled Epoxy Bands

    Science.gov (United States)

    Lingbloom, Mike

    2007-01-01

    Sheet cork and cork filled epoxy provide external insulation for the Reusable Solid Rocket Motor (RSRM) on the Nation's Space Transportation System (STS). Interest in the reliability of the external insulation bonds has increased since the Columbia incident. A non-destructive test (NDT) method that will provide the best inspection for these bonds has been under evaluation. Electronic Shearography has been selected as the primary NDT method for inspection of these bond lines in the RSRM production flow. ATK Launch Systems Group has purchased an electronic shearography system that includes a vacuum chamber that is used for evaluation of test parts and custom vacuum windows for inspection of full-scale motors. Although the electronic shearography technology has been selected as the primary method for inspection of the external bonds, other technologies that exist continue to be investigated. The NASA/Marshall Space Flight Center (MSFC) NDT department has inspected several samples for comparison with electronic shearography with various inspections systems in their laboratory. The systems that were evaluated are X-ray backscatter, terahertz imaging, and microwave imaging. The samples tested have some programmed flaws as well as some flaws that occurred naturally during the sample making process. These samples provide sufficient flaw variation for the evaluation of the different inspection systems. This paper will describe and compare the basic functionality, test method and test results including dissection for each inspection technology.

  13. Artist - analytical RT inspection simulation tool

    International Nuclear Information System (INIS)

    Bellon, C.; Jaenisch, G.R.

    2007-01-01

    The computer simulation of radiography is applicable for different purposes in NDT such as for the qualification of NDT systems, the prediction of its reliability, the optimization of system parameters, feasibility analysis, model-based data interpretation, education and training of NDT/NDE personnel, and others. Within the framework of the integrated project FilmFree the radiographic testing (RT) simulation software developed by BAM is being further developed to meet practical requirements for inspection planning in digital industrial radiology. It combines analytical modelling of the RT inspection process with the CAD-orientated object description applicable to various industrial sectors such as power generation, railways and others. (authors)

  14. Study of a risk-based piping inspection guideline system.

    Science.gov (United States)

    Tien, Shiaw-Wen; Hwang, Wen-Tsung; Tsai, Chih-Hung

    2007-02-01

    A risk-based inspection system and a piping inspection guideline model were developed in this study. The research procedure consists of two parts--the building of a risk-based inspection model for piping and the construction of a risk-based piping inspection guideline model. Field visits at the plant were conducted to develop the risk-based inspection and strategic analysis system. A knowledge-based model had been built in accordance with international standards and local government regulations, and the rational unified process was applied for reducing the discrepancy in the development of the models. The models had been designed to analyze damage factors, damage models, and potential damage positions of piping in the petrochemical plants. The purpose of this study was to provide inspection-related personnel with the optimal planning tools for piping inspections, hence, to enable effective predictions of potential piping risks and to enhance the better degree of safety in plant operations that the petrochemical industries can be expected to achieve. A risk analysis was conducted on the piping system of a petrochemical plant. The outcome indicated that most of the risks resulted from a small number of pipelines.

  15. Microbiological characteristics of poultry meats - Results of inspections carried out in the province of Milano, Italy

    Directory of Open Access Journals (Sweden)

    Guido Grilli

    2010-01-01

    Full Text Available Examinations were conducted in terms of microbiological quality/quantity (TMC, Coliforms, E. coli, S. aureus, Sulphate-reducing Clostridia, B. cereus, Salmonella spp. and Lysteria spp. and Campylobacter spp. on 240 poultry meat samples (chicken, turkey and quail acquired pursuant to the standards set by the Regional Plan of programming and coordination in the field of operations concerning official inspections of Lombardia animal origin and by a few private companies for self-inspection. The TMC was consistently low and in line with reports in the literature, as was the case with coliforms, E. coli, S. aureus, sulphatereducing Clostrides and B. cereus. In the case of Salmonella spp., only 5 samples tested positive: one for S. typhimurium and one for S. enteritidis (chicken; only one sample from turkey tested positive for S. blokley, and two out of five samples analysed from quail tested positive result for S. typhimurium. About 3% of the samples analyzed tested positive for Listeria monocitogenes, but they were within the legal limits. Research on Campylobacter thermophiles has involved only 50 samples, of which only 5 have tested positive. These results confirm the high quality of hygiene and cleanliness of poultry meat, in accordance with that reported in the national literature and with respect to EU norms.

  16. Description of double-shell tank selection criteria for inspection

    International Nuclear Information System (INIS)

    Schwenk, E.B.; Scott, K.V.

    1996-01-01

    Technical criteria for selecting double-shelf tanks's (DST's) for inspection are presented. Inspection of DST's is planned to non-destructively determine the general condition of their inner wall and bottom knuckle. Inspection of representative tanks will provide a basis for evaluating the integrity of all the DST's and provide a basis for estimating remaining life. The selection criteria recommended are tank age based on date-of-first fluid entry, waste temperature, corrosion inhibitor levels, deviations from normal behavior - involving sludge levels, hydrogen release and waste transfers - least waste depth fluctuation, tank steel type, other chemical species that could activate stress-corrosion cracking, and waste types

  17. Sampling and Analysis Plan for the 221-U Facility

    International Nuclear Information System (INIS)

    Rugg, J.E.

    1998-02-01

    This sampling and analysis plan (SAP) presents the rationale and strategy for the sampling and analysis activities proposed to be conducted to support the evaluation of alternatives for the final disposition of the 221-U Facility. This SAP will describe general sample locations and the minimum number of samples required. It will also identify the specific contaminants of potential concern (COPCs) and the required analysis. This SAP does not define the exact sample locations and equipment to be used in the field due to the nature of unknowns associated with the 221-U Facility

  18. Acceptance Sampling Plans Based on Truncated Life Tests for Sushila Distribution

    Directory of Open Access Journals (Sweden)

    Amer Ibrahim Al-Omari

    2018-03-01

    Full Text Available An acceptance sampling plan problem based on truncated life tests when the lifetime following a Sushila distribution is considered in this paper. For various acceptance numbers, confidence levels and values of the ratio between fixed experiment time and particular mean lifetime, the minimum sample sizes required to ascertain a specified mean life were found. The operating characteristic function values of the suggested sampling plans and the producer’s risk are presented. Some tables are provided and the results are illustrated by an example of a real data set.

  19. Merge Fuzzy Visual Servoing and GPS-Based Planning to Obtain a Proper Navigation Behavior for a Small Crop-Inspection Robot.

    Science.gov (United States)

    Bengochea-Guevara, José M; Conesa-Muñoz, Jesus; Andújar, Dionisio; Ribeiro, Angela

    2016-02-24

    The concept of precision agriculture, which proposes farming management adapted to crop variability, has emerged in recent years. To effectively implement precision agriculture, data must be gathered from the field in an automated manner at minimal cost. In this study, a small autonomous field inspection vehicle was developed to minimise the impact of the scouting on the crop and soil compaction. The proposed approach integrates a camera with a GPS receiver to obtain a set of basic behaviours required of an autonomous mobile robot to inspect a crop field with full coverage. A path planner considered the field contour and the crop type to determine the best inspection route. An image-processing method capable of extracting the central crop row under uncontrolled lighting conditions in real time from images acquired with a reflex camera positioned on the front of the robot was developed. Two fuzzy controllers were also designed and developed to achieve vision-guided navigation. A method for detecting the end of a crop row using camera-acquired images was developed. In addition, manoeuvres necessary for the robot to change rows were established. These manoeuvres enabled the robot to autonomously cover the entire crop by following a previously established plan and without stepping on the crop row, which is an essential behaviour for covering crops such as maize without damaging them.

  20. Risk-based inspection in the context of nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Soares, Wellington A.; Vasconcelos, Vanderley de; Rabello, Emerson G., E-mail: soaresw@cdtn.br, E-mail: vasconv@cdtn.br, E-mail: egr@cdtn.br [Centro de Desenvolvimento da Tecnologia Nuclear (CDTN/CNEN-MG), Belo Horizonte, MG (Brazil)

    2015-07-01

    Nuclear power plant owners have to consider several aspects like safety, availability, costs and radiation exposure during operation of nuclear power plants. They also need to demonstrate to regulatory bodies that risk assessment and inspection planning processes are being implemented in effective and appropriate manner. Risk-Based Inspection (RBI) is a methodology that, unlike time-based inspection, involves a quantitative assessment of both failure probability and consequence associated with each safety-related item. A correctly implemented RBI program classifies individual equipment by its risks and prioritizes inspection efforts based on this classification. While in traditional deterministic approach, the inspection frequencies are constant, in the RBI approach the inspection interval for each item depends on the risk level. Regularly, inspection intervals from RBI result in risk levels lower or equal than deterministic inspection intervals. According to the literature, RBI solutions improve integrity and reduce costs through a more effective inspection. Risk-Informed In-service Inspection (RI-ISI) is the equivalent term used in the nuclear area. Its use in nuclear power plants around world is briefly reviewed in this paper. Identification of practice methodologies for performing risk-based analyses presented in this paper can help both Brazilian nuclear power plant operator and regulatory body in evaluating the RI-ISI technique feasibility as a tool for optimizing inspections within nuclear plants. (author)

  1. Risk-based inspection in the context of nuclear power plants

    International Nuclear Information System (INIS)

    Soares, Wellington A.; Vasconcelos, Vanderley de; Rabello, Emerson G.

    2015-01-01

    Nuclear power plant owners have to consider several aspects like safety, availability, costs and radiation exposure during operation of nuclear power plants. They also need to demonstrate to regulatory bodies that risk assessment and inspection planning processes are being implemented in effective and appropriate manner. Risk-Based Inspection (RBI) is a methodology that, unlike time-based inspection, involves a quantitative assessment of both failure probability and consequence associated with each safety-related item. A correctly implemented RBI program classifies individual equipment by its risks and prioritizes inspection efforts based on this classification. While in traditional deterministic approach, the inspection frequencies are constant, in the RBI approach the inspection interval for each item depends on the risk level. Regularly, inspection intervals from RBI result in risk levels lower or equal than deterministic inspection intervals. According to the literature, RBI solutions improve integrity and reduce costs through a more effective inspection. Risk-Informed In-service Inspection (RI-ISI) is the equivalent term used in the nuclear area. Its use in nuclear power plants around world is briefly reviewed in this paper. Identification of practice methodologies for performing risk-based analyses presented in this paper can help both Brazilian nuclear power plant operator and regulatory body in evaluating the RI-ISI technique feasibility as a tool for optimizing inspections within nuclear plants. (author)

  2. Pressure vessel integrity and weld inspection procedure

    International Nuclear Information System (INIS)

    Solomon, K.A.; Okrent, D.; Kastenberg, W.E.

    1975-01-01

    The primary objective of this paper is to develop a simple methodology which, when coupled with existing observations on pressure vessel behavior, provides an inter-relation between pressure vessel integrity, and the parameters of the in-service inspection program, including inspection sample size, frequency and efficiency. A modified Markov process is employed and a computer code was written to obtain numerical results. The Markov process mathematically describes the following physical events. In a nuclear reactor pressure vessel weld, some defects may exist prior to the zeroth inspection (i.e., prior to vessel operation). During the zeroth inspection and repair processes, some of these defects are removed. During the first cycle of vessel operation, the existing defects may grow and some new defects may be generated. Those defects that are found at the first (and succeeding) inspection interval and warrant repair, are repaired. The above process continues through several operating cycles to the end of vessel life. During any inspection, only a portion of the welds may be inspected, and with less than perfect efficiency

  3. In situ sampling cart development engineering task plan

    International Nuclear Information System (INIS)

    DeFord, D.K.

    1995-01-01

    This Engineering Task Plan (ETP) supports the development for facility use of the next generation in situ sampling system for characterization of tank vapors. In situ sampling refers to placing sample collection devices (primarily sorbent tubes) directly into the tank headspace, then drawing tank gases through the collection devices to obtain samples. The current in situ sampling system is functional but was not designed to provide the accurate flow measurement required by today's data quality objectives (DQOs) for vapor characterization. The new system will incorporate modern instrumentation to achieve much tighter control. The next generation system will be referred to in this ETP as the New In Situ System (NISS) or New System. The report describes the current sampling system and the modifications that are required for more accuracy

  4. Sampling Plans for the Thrips Frankliniella schultzei (Thysanoptera: Thripidae) in Three Lettuce Varieties.

    Science.gov (United States)

    Silva, Alisson R; Rodrigues-Silva, Nilson; Pereira, Poliana S; Sarmento, Renato A; Costa, Thiago L; Galdino, Tarcísio V S; Picanço, Marcelo C

    2017-12-05

    The common blossom thrips, Frankliniella schultzei Trybom (Thysanoptera: Thripidae), is an important lettuce pest worldwide. Conventional sampling plans are the first step in implementing decision-making systems into integrated pest management programs. However, this tool is not available for F. schultzei infesting lettuce crops. Thus, the objective of this work was to develop a conventional sampling plan for F. schultzei in lettuce crops. Two sampling techniques (direct counting and leaf beating on a white plastic tray) were compared in crisphead, looseleaf, and Boston lettuce varieties before and during head formation. The frequency distributions of F. schultzei densities in lettuce crops were assessed, and the number of samples required to compose the sampling plan was determined. Leaf beating on a white plastic tray was the best sampling technique. F. schultzei densities obtained with this technique were fitted to the negative binomial distribution with a common aggregation parameter (common K = 0.3143). The developed sampling plan is composed of 91 samples per field and presents low errors in its estimates (up to 20%), fast execution time (up to 47 min), and low cost (up to US $1.67 per sampling area). This sampling plan can be used as a tool for integrated pest management in lettuce crops, assisting with reliable decision making in different lettuce varieties before and during head formation. © The Author(s) 2017. Published by Oxford University Press on behalf of Entomological Society of America. All rights reserved. For permissions, please e-mail: journals.permissions@oup.com.

  5. Group SkSP-R sampling plan for accelerated life tests

    Indian Academy of Sciences (India)

    Muhammad Aslam

    2017-09-15

    Sep 15, 2017 ... SkSP-R sampling; life test; Weibull distribution; producer's risk; ... designed a sampling plan under a time-truncated life test .... adjusted using an acceleration factor. ... where P is the probability of lot acceptance for a single.

  6. Fabrication, inspection, and test plan for the Advanced Test Reactor (ATR) Mixed-Oxide (MOX) fuel irradiation project

    International Nuclear Information System (INIS)

    Wachs, G.W.

    1997-11-01

    The Department of Energy (DOE) Fissile Materials Disposition Materials Disposition Program (FMDP) has announced that reactor irradiation of MOX fuel is one of the preferred alternatives for disposal of surplus weapons-usable plutonium (Pu). MOX fuel has been utilized domestically in test reactors and on an experimental basis in a number of Commercial Light Water Reactors (CLWRs). Most of this experience has been with Pu derived from spent low enriched uranium (LEU) fuel, known as reactor grade (RG) Pu. The MOX fuel test will be irradiated in the ATR to provide preliminary data to demonstrate that the unique properties of surplus weapons-derived or weapons-grade (WG) plutonium (Pu) do not compromise the applicability of this MOX experience base. In addition, the test will contribute experience with irradiation of gallium-containing fuel to the data base required for resolution of generic CLWR fuel design issues (ORNL/MD/LTR-76). This Fabrication, Inspection, and Test Plan (FITP) is a level 2 document as defined in the FMDP LWR MOX Fuel Irradiation Test Project Plan (ORNL/MD/LTR-78)

  7. Inspection of licensee - Maintenance programme and activities

    International Nuclear Information System (INIS)

    2013-01-01

    An effective maintenance programme is critical to sustained safe and reliable operation of nuclear power plants. The Working Group on Inspection Practices (WGIP) concluded that when a licensee has an effective maintenance programme, the overall operating safety of the plant is improved and the protection of public health and safety enhanced. All Regulatory Bodies (RB) consider maintenance to be an important area for oversight. Although a variety of inspection practices are being used; RB are actively monitoring licensee performance. Specifically the following conclusions were reached and commendable practices identified: - Maintenance oversight by regulators appears to be in a stable continuous improvement state. Most regulators are executing inspection oversight based on an existing regulatory framework. - The performance of a licensee's maintenance programme is recognized as important part of maintaining nuclear safety. The result of the maintenance program assessment is included in the overall performance assessment of a license. - Maintenance inspection activities are recognized as an important part of the regulatory oversight process. Inspection activities are based on the safety significance and nature of work being performed by the licensee. - The effectiveness of the maintenance inspection activities is recognized to rely on properly qualified inspectors; who are adequately supported by specialists. Training and qualification of inspectors should be based on how the RB reviews and inspects licensee maintenance programmes. - Reporting requirements are identified to provide information on the licensees maintenance programme, and to help guide inspection activities. - Performance Indicators are recognized as a useful tool for helping focus regulatory activities. Basic PI are identified and tracked by the RB, and use of PI by the licensee is monitored. - Inspections are designed to confirm that the licensee is planning and scheduling maintenance with due

  8. Post-Closure Inspection Report for the Tonopah Test Range, Nevada

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2007-01-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2006 and includes inspection and repair activities completed at the following nine CAUs: CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 404: Roller Coaster Lagoons and Trench (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 426: Cactus Spring Waste Trenches (TTR); CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR). Post-closure inspections were conducted on May 9, 2006, May 31, 2006, and November 15, 2006. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2006, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 400, CAU 407, CAU 426, CAU 453, and CAU 487 in 2006. During the May inspection of CAU 400, it was identified that the east and west sections of chickenwire fencing beyond the standard fencing were damaged; they were repaired in June 2006. Also in June 2006, the southeast corner fence post and one warning sign at CAU 407 were reinforced and reattached, the perimeter fencing adjacent to the gate at CAU 426 was tightened, and large animal

  9. Post-Closure Inspection Report for the Tonopah Test Range, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2007-06-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2006 and includes inspection and repair activities completed at the following nine CAUs: CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 404: Roller Coaster Lagoons and Trench (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 426: Cactus Spring Waste Trenches (TTR); CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR). Post-closure inspections were conducted on May 9, 2006, May 31, 2006, and November 15, 2006. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2006, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 400, CAU 407, CAU 426, CAU 453, and CAU 487 in 2006. During the May inspection of CAU 400, it was identified that the east and west sections of chickenwire fencing beyond the standard fencing were damaged; they were repaired in June 2006. Also in June 2006, the southeast corner fence post and one warning sign at CAU 407 were reinforced and reattached, the perimeter fencing adjacent to the gate at CAU 426 was tightened, and large animal

  10. An Internationally Coordinated Science Management Plan for Samples Returned from Mars

    Science.gov (United States)

    Haltigin, T.; Smith, C. L.

    2015-12-01

    Mars Sample Return (MSR) remains a high priority of the planetary exploration community. Such an effort will undoubtedly be too large for any individual agency to conduct itself, and thus will require extensive global cooperation. To help prepare for an eventual MSR campaign, the International Mars Exploration Working Group (IMEWG) chartered the international Mars Architecture for the Return of Samples (iMARS) Phase II working group in 2014, consisting of representatives from 17 countries and agencies. The overarching task of the team was to provide recommendations for progressing towards campaign implementation, including a proposed science management plan. Building upon the iMARS Phase I (2008) outcomes, the Phase II team proposed the development of an International MSR Science Institute as part of the campaign governance, centering its deliberations around four themes: Organization: including an organizational structure for the Institute that outlines roles and responsibilities of key members and describes sample return facility requirements; Management: presenting issues surrounding scientific leadership, defining guidelines and assumptions for Institute membership, and proposing a possible funding model; Operations & Data: outlining a science implementation plan that details the preliminary sample examination flow, sample allocation process, and data policies; and Curation: introducing a sample curation plan that comprises sample tracking and routing procedures, sample sterilization considerations, and long-term archiving recommendations. This work presents a summary of the group's activities, findings, and recommendations, highlighting the role of international coordination in managing the returned samples.

  11. Planning of the regulatory inspection activity during manufacturing, construction and operation of the Italian nuclear plants

    International Nuclear Information System (INIS)

    Messore, G.A.

    1977-01-01

    After a brief review of the provisions in force in Italy on the inspection of nuclear installations the paper deals with the main criteria which determine the general and annual inspection programmes for every nuclear installation and the procedures for recording the results of inspections. It also describes the classification of nuclear installations into different categories according to the degree of hazard presented by their respective activities and consequently, the selection of the minimum number of inspections to be conducted every year for each of these categories. (NEA) [fr

  12. Risk-Informed Decisions Optimization in Inspection and Maintenance

    International Nuclear Information System (INIS)

    Robertas Alzbutas

    2002-01-01

    partial case is used for the construction and research of the models related to inspections and maintenance planning of Ignalina Nuclear Power Plant (RBMK-1500) piping components. The discussed example is related to risk analysis and inspection program improvements for selected pipe systems. The new risk-informed inspection and maintenance program for selected pipe systems are compared with various alternatives. The usage of risk evaluations to optimize the selection of inspection locations, the inspection interval, and the changes in risk and cost due suggested modifications are demonstrated. The proposed integrated modeling methodic and general model of inspection process can be used as a base for other risk-informed models of inspection process control and risk monitors of complex dynamic systems. (authors)

  13. Waste Calcining Facility remote inspection report

    International Nuclear Information System (INIS)

    Patterson, M.W.; Ison, W.M.

    1994-08-01

    The purpose of the Waste Calcining Facility (WCF) remote inspections was to evaluate areas in the facility which are difficult to access due to high radiation fields. The areas inspected were the ventilation exhaust duct, waste hold cell, adsorber manifold cell, off-gas cell, calciner cell and calciner vessel. The WCF solidified acidic, high-level mixed waste generated during nuclear fuel reprocessing. Solidification was accomplished through high temperature oxidation and evaporation. Since its shutdown in 1981, the WCFs vessels, piping systems, pumps, off-gas blowers and process cells have remained contaminated. Access to the below-grade areas is limited due to contamination and high radiation fields. Each inspection technique was tested with a mock-up in a radiologically clean area before the equipment was taken to the WCF for the actual inspection. During the inspections, essential information was obtained regarding the cleanliness, structural integrity, in-leakage of ground water, indications of process leaks, indications of corrosion, radiation levels and the general condition of the cells and equipment. In general, the cells contain a great deal of dust and debris, as well as hand tools, piping and miscellaneous equipment. Although the building appears to be structurally sound, the paint is peeling to some degree in all of the cells. Cracking and spalling of the concrete walls is evident in every cell, although the east wall of the off-gas cell is the worst. The results of the completed inspections and lessons learned will be used to plan future activities for stabilization and deactivation of the facility. Remote clean-up of loose piping, hand tools, and miscellaneous debris can start immediately while information from the inspections is factored into the conceptual design for deactivating the facility

  14. Sampling plan to support HLW tank 16

    International Nuclear Information System (INIS)

    Rodwell, P.O.; Martin, B.

    1997-01-01

    Plans are to remove the residual waste from the annulus of High-Level Waste Tank 16, located in the H-Area Tank Farm, in 1998. The interior of the tank is virtually clean. In the late 1970's, the waste was removed from the interior of the tank by several campaigns of waste removal with slurry pumps, spray washing, and oxalic acid cleaning. The annulus of the tank at one time had several thousand gallons of waste salt, which had leaked from the tank interior. Some of this salt was removed by adding water to the annulus and circulating, but much of the salt remains in the annulus. In order to confirm the source term used for fate and transport modeling, samples of the tank interior and annulus will be obtained and analyzed. If the results of the analyses indicate that the data used for the initial modeling is bounding then no changes will be made to the model. However, if the results indicate that the source term is higher than that assumed in the initial modeling, thus not bounding, additional modeling will be performed. The purpose of this Plan is to outline the approach to sampling the annulus and interior of Tank 16 as a prerequisite to salt removal in the annulus and closure of the entire tank system. The sampling and analysis of this tank system must be robust to reasonably ensure the actual tank residual is within the bounds of analysis error

  15. Effective Hull IMMR plan

    Energy Technology Data Exchange (ETDEWEB)

    Franco, Mireille

    2010-07-01

    The objective of the Hull Inspection, Maintenance and Repair Plan is to ensure the total integrity of the Floating Production Unit. To be efficient, the Monitoring has to be part of the Hull Inspection, Monitoring, Maintenance and Repair Plan (IMMR). The IMMR Plan should be developed during the design and project phases and take into account the interfaces between the different systems and teams' tasks in operation. The IMMR is multidisciplinary and form part of the hand-over to ensure an efficient and early implementation. Implementation of such a complex plan requires: - Cross-functionality: take advantage of the synergies - Boldness: break the mould and think outside the box - Listening: be attentive, be available, - Mutual support: during good and bad times. This paper presents the way Total believe the Hull IMMR Plan shall be developed, implemented and followed up. (Author)

  16. 7 CFR 75.18 - Sampling.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 3 2010-01-01 2010-01-01 false Sampling. 75.18 Section 75.18 Agriculture Regulations of the Department of Agriculture (Continued) AGRICULTURAL MARKETING SERVICE (Standards, Inspections... CERTIFICATION OF QUALITY OF AGRICULTURAL AND VEGETABLE SEEDS Inspection § 75.18 Sampling. Sampling, when...

  17. Tank 241-AZ-102 Privatization Push Mode Core Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    TEMPLETON, A.M.

    1999-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AZ-102

  18. Tank 241-AZ-102 Privatization Push Mode Core Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    RASMUSSEN, J.H.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AZ-102

  19. ROBOTIC TANK INSPECTION END EFFECTOR

    International Nuclear Information System (INIS)

    Rachel Landry

    1999-01-01

    The objective of this contract between Oceaneering Space Systems (OSS) and the Department of Energy (DOE) was to provide a tool for the DOE to inspect the inside tank walls of underground radioactive waste storage tanks in their tank farms. Some of these tanks are suspected to have leaks, but the harsh nature of the environment within the tanks precludes human inspection of tank walls. As a result of these conditions only a few inspection methods can fulfill this task. Of the methods available, OSS chose to pursue Alternating Current Field Measurement (ACFM), because it does not require clean surfaces for inspection, nor any contact with the Surface being inspected, and introduces no extra by-products in the inspection process (no coupling fluids or residues are left behind). The tool produced by OSS is the Robotic Tank Inspection End Effector (RTIEE), which is initially deployed on the tip of the Light Duty Utility Arm (LDUA). The RTEE combines ACFM with a color video camera for both electromagnetic and visual inspection The complete package consists of an end effector, its corresponding electronics and software, and a user's manual to guide the operator through an inspection. The system has both coarse and fine inspection modes and allows the user to catalog defects and suspected areas of leakage in a database for further examination, which may lead to emptying the tank for repair, decommissioning, etc.. The following is an updated report to OSS document OSS-21100-7002, which was submitted in 1995. During the course of the contract, two related sub-tasks arose, the Wall and Coating Thickness Sensor and the Vacuum Scarifying and Sampling Tool Assembly. The first of these sub-tasks was intended to evaluate the corrosion and wall thinning of 55-gallon steel drums. The second was retrieved and characterized the waste material trapped inside the annulus region of the underground tanks on the DOE's tank farms. While these sub-tasks were derived from the original intent

  20. 46 CFR 153.812 - Inspection for Certificate of Inspection.

    Science.gov (United States)

    2010-10-01

    ... 46 Shipping 5 2010-10-01 2010-10-01 false Inspection for Certificate of Inspection. 153.812... CARGOES SHIPS CARRYING BULK LIQUID, LIQUEFIED GAS, OR COMPRESSED GAS HAZARDOUS MATERIALS Design and Equipment Testing and Inspection § 153.812 Inspection for Certificate of Inspection. The rules governing the...

  1. Inspection Methods for Physical Protection Project: annual report, March-December 1981

    International Nuclear Information System (INIS)

    Bowden, D.D.; Green, J.N.; Minichino, C.; Thatcher, R.M.; Tyler, G.C.

    1982-01-01

    The report details the current production status of the expanded replacement inspection procedures for physical protection of power reactors, for strategic special nuclear material fixed sites, and for transportation of special nuclear material. In addition to the expanded replacement procedures, the final production status is reported for the new series of inspection procedures for special nuclear material of moderate and low strategic significance at fixed sites, for personnel training and qualifications plan (Appendix B to 10 CFR 73), for safeguards contingency plan (Appendix C to 10 CFR 73), and for licensee implementing procedures evaluation. Other deliverables, trips, management meetings, training, and changes in personnel are discussed

  2. Abbreviated sampling and analysis plan for planning decontamination and decommissioning at Test Reactor Area (TRA) facilities

    International Nuclear Information System (INIS)

    1994-10-01

    The objective is to sample and analyze for the presence of gamma emitting isotopes and hazardous constituents within certain areas of the Test Reactor Area (TRA), prior to D and D activities. The TRA is composed of three major reactor facilities and three smaller reactors built in support of programs studying the performance of reactor materials and components under high neutron flux conditions. The Materials Testing Reactor (MTR) and Engineering Test Reactor (ETR) facilities are currently pending D/D. Work consists of pre-D and D sampling of designated TRA (primarily ETR) process areas. This report addresses only a limited subset of the samples which will eventually be required to characterize MTR and ETR and plan their D and D. Sampling which is addressed in this document is intended to support planned D and D work which is funded at the present time. Biased samples, based on process knowledge and plant configuration, are to be performed. The multiple process areas which may be potentially sampled will be initially characterized by obtaining data for upstream source areas which, based on facility configuration, would affect downstream and as yet unsampled, process areas. Sampling and analysis will be conducted to determine the level of gamma emitting isotopes and hazardous constituents present in designated areas within buildings TRA-612, 642, 643, 644, 645, 647, 648, 663; and in the soils surrounding Facility TRA-611. These data will be used to plan the D and D and help determine disposition of material by D and D personnel. Both MTR and ETR facilities will eventually be decommissioned by total dismantlement so that the area can be restored to its original condition

  3. 46 CFR 160.010-7 - Methods of sampling, inspections and tests.

    Science.gov (United States)

    2010-10-01

    ... laboratory must inspect the place of manufacture, observe the various operations involved in the construction... section. (g) Painter attachment strength test. The apparatus must be positioned with its painter attachment fitting at the lowest point of the apparatus, directly below the center of buoyancy. The apparatus...

  4. IP Sample Plan #5 | NCI Technology Transfer Center | TTC

    Science.gov (United States)

    A sample Intellectual Property Management Plan in the form of a legal agreement between a University and its collaborators which addresses data sharing, sharing of research tools and resources and intellectual property management.

  5. Waste analysis plan for confirmation or completion of Tank Farms backlog waste designation

    International Nuclear Information System (INIS)

    1993-08-01

    This waste analysis plan satisfies the requirements of Item 3 of Ecology Order 93NM-201 as amended per the Settlement Agreement. Item 3 states: ''Within forty (40) calendar days of receipt of this Order, the US Department of Energy Richland Operations (DOE-RL) and Westinghouse Hanford Company (WHC) shall provide Ecology with a plan for review and approval detailing the established criteria and procedures for waste inspection, segregation, sampling, designation, and repackaging of all containers reported in item number-sign 1. The report shall include sampling plan criteria for different contaminated media, i.e., soils, compactable waste, high-efficiency particular air (HEPA) filters, etc., and a schedule for completing the work within the time allowed under this Order.'' Item 3 was amended per the Settlement Agreement as follows: ''In addition to the waste inspection plans for the ''unknowns'' previously provided and currently being supplemented, DOE-RL and WHC shall provide a draft waste analysis plan for the containers reported in Item 1 of the Order to Ecology by July 12, 1993. A final, DOE-RL approved waste analysis plan shall be submitted to Ecology by September 1, 1993, for Ecology's written approval by September 15, 1993.'' Containers covered by the Order, Settlement Agreement, and this waste analysis plan consist of all those reported under Item 1 of the Order, less any containers that have been identified in unusual occurrences reported by Tank Farms. This waste analysis plan describes the procedures that will be undertaken to confirm or to complete designation of the solid waste identified in the Order

  6. Vision Based Autonomous Robotic Control for Advanced Inspection and Repair

    Science.gov (United States)

    Wehner, Walter S.

    2014-01-01

    The advanced inspection system is an autonomous control and analysis system that improves the inspection and remediation operations for ground and surface systems. It uses optical imaging technology with intelligent computer vision algorithms to analyze physical features of the real-world environment to make decisions and learn from experience. The advanced inspection system plans to control a robotic manipulator arm, an unmanned ground vehicle and cameras remotely, automatically and autonomously. There are many computer vision, image processing and machine learning techniques available as open source for using vision as a sensory feedback in decision-making and autonomous robotic movement. My responsibilities for the advanced inspection system are to create a software architecture that integrates and provides a framework for all the different subsystem components; identify open-source algorithms and techniques; and integrate robot hardware.

  7. Test plan for evaluating the performance of the in-tank fluidic sampling system

    International Nuclear Information System (INIS)

    BOGER, R.M.

    1999-01-01

    The PHMC will provide Low Activity Wastes (LAW) tank wastes for final treatment by a privatization contractor from double-shell feed tanks, 241-AP-102 and 241-AP-104, Concerns about the inability of the baseline ''grab'' sampling to provide large volume samples within time constraints has led to the development of a conceptual sampling system that would be deployed in a feed tank riser, This sampling system will provide large volume, representative samples without the environmental, radiation exposure, and sample volume impacts of the current base-line ''grab'' sampling method. This test plan identifies ''proof-of-principle'' cold tests for the conceptual sampling system using simulant materials. The need for additional testing was identified as a result of completing tests described in the revision test plan document, Revision 1 outlines tests that will evaluate the performance and ability to provide samples that are representative of a tanks' content within a 95 percent confidence interval, to recovery from plugging, to sample supernatant wastes with over 25 wt% solids content, and to evaluate the impact of sampling at different heights within the feed tank. The test plan also identifies operating parameters that will optimize the performance of the sampling system

  8. Tank 241-AZ-102 Privatization Push Mode Core Sampling and Analysis Plan; FINAL

    International Nuclear Information System (INIS)

    TEMPLETON, A.M.

    1999-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AZ-102. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AZ-102. Push mode core samples will be obtained from risers 15C and 24A to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples, composite the liquids and solids, perform chemical analyses, and provide subsamples to the Process Chemistry Laboratory. The Process Chemistry Laboratory will prepare test plans and perform process tests to evaluate the behavior of the 241-AZ-102 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. Requirements for analyses of samples originating in the process tests will be documented in the corresponding test plan

  9. Soil Sampling Plan for the transuranic storage area soil overburden and final report: Soil overburden sampling at the RWMC transuranic storage area

    International Nuclear Information System (INIS)

    Stanisich, S.N.

    1994-12-01

    This Soil Sampling Plan (SSP) has been developed to provide detailed procedural guidance for field sampling and chemical and radionuclide analysis of selected areas of soil covering waste stored at the Transuranic Storage Area (TSA) at the Idaho National Engineering Laboratory's (INEL) Radioactive Waste Management Complex (RWMC). The format and content of this SSP represents a complimentary hybrid of INEL Waste Management--Environmental Restoration Program, and Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) Remedial Investigation/Feasibility Study (RI/FS) sampling guidance documentation. This sampling plan also functions as a Quality Assurance Project Plan (QAPP). The QAPP as a controlling mechanism during sampling to ensure that all data collected are valid, reliabile, and defensible. This document outlines organization, objectives and quality assurance/quality control (QA/QC) activities to achieve the desired data quality goals. The QA/QC requirements for this project are outlined in the Data Collection Quality Assurance Plan (DCQAP) for the Buried Waste Program. The DCQAP is a program plan and does not outline the site specific requirements for the scope of work covered by this SSP

  10. [Legislation and inspection for the health and safety of workers. Efficacy and limits].

    Science.gov (United States)

    Tozzi, G A

    2009-01-01

    To provide information regarding Occupational Health and Safety (OHS) Inspections in Europe. The dynamics that are transforming regulatory subsystems and complementary inspection services are described. Simplification initiatives, the limits and difficulties of applying the different models of Health and Safety Management Systems are discussed. Examples are given on how to evaluate legislation and technical standards during planning and enforcement. Different approaches for studying characteristics, methodologies and efficacy in practice of OHS Inspection are provided. Targeted inspections need to respond to the needs of enterprises and workers. Impartiality must be guaranteed and workers' participation should be facilitated.

  11. Spatial distribution and sequential sampling plans for Tuta absoluta (Lepidoptera: Gelechiidae) in greenhouse tomato crops.

    Science.gov (United States)

    Cocco, Arturo; Serra, Giuseppe; Lentini, Andrea; Deliperi, Salvatore; Delrio, Gavino

    2015-09-01

    The within- and between-plant distribution of the tomato leafminer, Tuta absoluta (Meyrick), was investigated in order to define action thresholds based on leaf infestation and to propose enumerative and binomial sequential sampling plans for pest management applications in protected crops. The pest spatial distribution was aggregated between plants, and median leaves were the most suitable sample to evaluate the pest density. Action thresholds of 36 and 48%, 43 and 56% and 60 and 73% infested leaves, corresponding to economic thresholds of 1 and 3% damaged fruits, were defined for tomato cultivars with big, medium and small fruits respectively. Green's method was a more suitable enumerative sampling plan as it required a lower sampling effort. Binomial sampling plans needed lower average sample sizes than enumerative plans to make a treatment decision, with probabilities of error of sampling plan required 87 or 343 leaves to estimate the population density in extensive or intensive ecological studies respectively. Binomial plans would be more practical and efficient for control purposes, needing average sample sizes of 17, 20 and 14 leaves to take a pest management decision in order to avoid fruit damage higher than 1% in cultivars with big, medium and small fruits respectively. © 2014 Society of Chemical Industry.

  12. Nuclear fuel shipping inspection device

    International Nuclear Information System (INIS)

    Takahashi, Toshio; Hada, Koji.

    1988-01-01

    Purpose: To provide an nuclear fuel shipping inspection device having a high detection sensitivity and capable of obtaining highly reliable inspection results. Constitution: The present invention concerns a device for distinguishing a fuel assembly having failed fuel rods in LMFBR type reactors. Coolants in a fuel assembly to be inspected are collected by a sampling pipeway and transferred to a filter device. In the filter device, granular radioactive corrosion products (CP) in the coolants are captured, to reduce the background. The coolants, after being passed through the filter device, are transferred to an FP catching device and gamma-rays of iodine and cesium nuclides are measured in FP radiation measuring device. Subsequently, the coolants transferred to a degasing device to separate rare gas FP in the coolants from the liquid phase. In a case if rare gas fission products are detected by the radiation detector, it means that there is a failed fuel rod in the fuel assembly to be inspected. Since the CP and the soluble FP are separated and extracted for the radioactivity measurement, the reliability can be improved. (Kamimura, M.)

  13. Integration of design and inspection

    Science.gov (United States)

    Simmonds, William H.

    1990-08-01

    Developments in advanced computer integrated manufacturing technology, coupled with the emphasis on Total Quality Management, are exposing needs for new techniques to integrate all functions from design through to support of the delivered product. One critical functional area that must be integrated into design is that embracing the measurement, inspection and test activities necessary for validation of the delivered product. This area is being tackled by a collaborative project supported by the UK Government Department of Trade and Industry. The project is aimed at developing techniques for analysing validation needs and for planning validation methods. Within the project an experimental Computer Aided Validation Expert system (CAVE) is being constructed. This operates with a generalised model of the validation process and helps with all design stages: specification of product requirements; analysis of the assurance provided by a proposed design and method of manufacture; development of the inspection and test strategy; and analysis of feedback data. The kernel of the system is a knowledge base containing knowledge of the manufacturing process capabilities and of the available inspection and test facilities. The CAVE system is being integrated into a real life advanced computer integrated manufacturing facility for demonstration and evaluation.

  14. Visual Sample Plan (VSP) - FIELDS Integration

    Energy Technology Data Exchange (ETDEWEB)

    Pulsipher, Brent A.; Wilson, John E.; Gilbert, Richard O.; Hassig, Nancy L.; Carlson, Deborah K.; Bing-Canar, John; Cooper, Brian; Roth, Chuck

    2003-04-19

    Two software packages, VSP 2.1 and FIELDS 3.5, are being used by environmental scientists to plan the number and type of samples required to meet project objectives, display those samples on maps, query a database of past sample results, produce spatial models of the data, and analyze the data in order to arrive at defensible decisions. VSP 2.0 is an interactive tool to calculate optimal sample size and optimal sample location based on user goals, risk tolerance, and variability in the environment and in lab methods. FIELDS 3.0 is a set of tools to explore the sample results in a variety of ways to make defensible decisions with quantified levels of risk and uncertainty. However, FIELDS 3.0 has a small sample design module. VSP 2.0, on the other hand, has over 20 sampling goals, allowing the user to input site-specific assumptions such as non-normality of sample results, separate variability between field and laboratory measurements, make two-sample comparisons, perform confidence interval estimation, use sequential search sampling methods, and much more. Over 1,000 copies of VSP are in use today. FIELDS is used in nine of the ten U.S. EPA regions, by state regulatory agencies, and most recently by several international countries. Both software packages have been peer-reviewed, enjoy broad usage, and have been accepted by regulatory agencies as well as site project managers as key tools to help collect data and make environmental cleanup decisions. Recently, the two software packages were integrated, allowing the user to take advantage of the many design options of VSP, and the analysis and modeling options of FIELDS. The transition between the two is simple for the user – VSP can be called from within FIELDS, automatically passing a map to VSP and automatically retrieving sample locations and design information when the user returns to FIELDS. This paper will describe the integration, give a demonstration of the integrated package, and give users download

  15. In-field inspection support software: A status report on the Common Inspection On-site Software Package (CIOSP) project

    International Nuclear Information System (INIS)

    Novatchev, Dimitre; Titov, Pavel; Siradjov, Bakhtiiar; Vlad, Ioan; Xiao Jing

    2001-01-01

    Inspection (SNRI) plug-in is planned for this year. Extensive beta and field testing of the CIOSP software has been performed at several facilities in Japan and Indonesia. The feedback received has been reflected in the software and the system is ready to be accepted for inspection use. The significance of this work cannot be underestimated. It will allow facilities to be supported by a single automated tool thus streamlining and improving efficiency of inspection activities. In addition, support for new requirements can be delivered more rapidly. (author)

  16. On-Site Inspection RadioIsotopic Spectroscopy (Osiris) System Development

    Energy Technology Data Exchange (ETDEWEB)

    Caffrey, Gus J. [Idaho National Laboratory, Idaho Falls, ID (United States); Egger, Ann E. [Idaho National Laboratory, Idaho Falls, ID (United States); Krebs, Kenneth M. [Idaho National Laboratory, Idaho Falls, ID (United States); Milbrath, B. D. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Jordan, D. V. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Warren, G. A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Wilmer, N. G. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)

    2015-09-01

    We have designed and tested hardware and software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy—Osiris—software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,132I. A set of over 100 fission-product spectra was employed for Osiris testing. These spectra were measured, where possible, or generated by modeling. The synthetic test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, Osiris correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.The Osiris gamma-ray spectrometer is a mechanically-cooled, battery-powered ORTEC Transpec-100, chosen to avoid the need for liquid nitrogen during on-site inspections. The spectrometer was used successfully during the recent 2014 CTBT Integrated Field Exercise in Jordan. The spectrometer is controlled and the spectral data analyzed by a Panasonic Toughbook notebook computer. To date, software development has been the main focus of the Osiris project. In FY2016-17, we plan to modify the Osiris hardware, integrate the Osiris software and hardware, and conduct rigorous field tests to ensure that the Osiris system will function correctly during CTBT on-site inspections. The planned development will raise Osiris to technology readiness level TRL-8; transfer the Osiris technology to a commercial manufacturer, and demonstrate Osiris to potential CTBT on-site inspectors.

  17. On-Site Inspection RadioIsotopic Spectroscopy (Osiris) System Development

    International Nuclear Information System (INIS)

    Caffrey, Gus J.; Egger, Ann E.; Krebs, Kenneth M.; Milbrath, B. D.; Jordan, D. V.; Warren, G. A.; Wilmer, N. G.

    2015-01-01

    We have designed and tested hardware and software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy-Osiris-software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,132I. A set of over 100 fission-product spectra was employed for Osiris testing. These spectra were measured, where possible, or generated by modeling. The synthetic test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, Osiris correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.The Osiris gamma-ray spectrometer is a mechanically-cooled, battery-powered ORTEC Transpec-100, chosen to avoid the need for liquid nitrogen during on-site inspections. The spectrometer was used successfully during the recent 2014 CTBT Integrated Field Exercise in Jordan. The spectrometer is controlled and the spectral data analyzed by a Panasonic Toughbook notebook computer. To date, software development has been the main focus of the Osiris project. In FY2016-17, we plan to modify the Osiris hardware, integrate the Osiris software and hardware, and conduct rigorous field tests to ensure that the Osiris system will function correctly during CTBT on-site inspections. The planned development will raise Osiris to technology readiness level TRL-8; transfer the Osiris technology to a commercial manufacturer, and demonstrate Osiris to potential CTBT on-site inspectors.

  18. Sampling and Analysis Plan for U.S. Department of Energy Office of Legacy Management Sites

    International Nuclear Information System (INIS)

    2012-01-01

    This plan incorporates U.S. Department of Energy (DOE) Office of Legacy Management (LM) standard operating procedures (SOPs) into environmental monitoring activities and will be implemented at all sites managed by LM. This document provides detailed procedures for the field sampling teams so that samples are collected in a consistent and technically defensible manner. Site-specific plans (e.g., long-term surveillance and maintenance plans, environmental monitoring plans) document background information and establish the basis for sampling and monitoring activities. Information will be included in site-specific tabbed sections to this plan, which identify sample locations, sample frequencies, types of samples, field measurements, and associated analytes for each site. Additionally, within each tabbed section, program directives will be included, when developed, to establish additional site-specific requirements to modify or clarify requirements in this plan as they apply to the corresponding site. A flowchart detailing project tasks required to accomplish routine sampling is displayed in Figure 1. LM environmental procedures are contained in the Environmental Procedures Catalog (LMS/PRO/S04325), which incorporates American Society for Testing and Materials (ASTM), DOE, and U.S. Environmental Protection Agency (EPA) guidance. Specific procedures used for groundwater and surface water monitoring are included in Appendix A. If other environmental media are monitored, SOPs used for air, soil/sediment, and biota monitoring can be found in the site-specific tabbed sections in Appendix D or in site-specific documents. The procedures in the Environmental Procedures Catalog are intended as general guidance and require additional detail from planning documents in order to be complete; the following sections fulfill that function and specify additional procedural requirements to form SOPs. Routine revision of this Sampling and Analysis Plan will be conducted annually at the

  19. Sampling and Analysis Plan for U.S. Department of Energy Office of Legacy Management Sites

    Energy Technology Data Exchange (ETDEWEB)

    None

    2012-10-24

    This plan incorporates U.S. Department of Energy (DOE) Office of Legacy Management (LM) standard operating procedures (SOPs) into environmental monitoring activities and will be implemented at all sites managed by LM. This document provides detailed procedures for the field sampling teams so that samples are collected in a consistent and technically defensible manner. Site-specific plans (e.g., long-term surveillance and maintenance plans, environmental monitoring plans) document background information and establish the basis for sampling and monitoring activities. Information will be included in site-specific tabbed sections to this plan, which identify sample locations, sample frequencies, types of samples, field measurements, and associated analytes for each site. Additionally, within each tabbed section, program directives will be included, when developed, to establish additional site-specific requirements to modify or clarify requirements in this plan as they apply to the corresponding site. A flowchart detailing project tasks required to accomplish routine sampling is displayed in Figure 1. LM environmental procedures are contained in the Environmental Procedures Catalog (LMS/PRO/S04325), which incorporates American Society for Testing and Materials (ASTM), DOE, and U.S. Environmental Protection Agency (EPA) guidance. Specific procedures used for groundwater and surface water monitoring are included in Appendix A. If other environmental media are monitored, SOPs used for air, soil/sediment, and biota monitoring can be found in the site-specific tabbed sections in Appendix D or in site-specific documents. The procedures in the Environmental Procedures Catalog are intended as general guidance and require additional detail from planning documents in order to be complete; the following sections fulfill that function and specify additional procedural requirements to form SOPs. Routine revision of this Sampling and Analysis Plan will be conducted annually at the

  20. Inspection Methods in Programming: Cliches and Plans.

    Science.gov (United States)

    1987-12-01

    part of the definition of the data plan. 44 THE PLAN (ALCULUS old:indexed-sequence I base: index: *sequence integer bump: oneplus update: new- term A...select-in dexred- sele¢ t-in dexed- sequence- base sequence-index,!’ sSdbump:. . oneplus ’,U a ," .update: " alter-term make: alter-indexed- sequence-index

  1. Fast Industrial Inspection of Optical Thin Film Using Optical Coherence Tomography

    Directory of Open Access Journals (Sweden)

    Muhammad Faizan Shirazi

    2016-09-01

    Full Text Available An application of spectral domain optical coherence tomography (SD-OCT was demonstrated for a fast industrial inspection of an optical thin film panel. An optical thin film sample similar to a liquid crystal display (LCD panel was examined. Two identical SD-OCT systems were utilized for parallel scanning of a complete sample in half time. Dual OCT inspection heads were utilized for transverse (fast scanning, while a stable linear motorized translational stage was used for lateral (slow scanning. The cross-sectional and volumetric images of an optical thin film sample were acquired to detect the defects in glass and other layers that are difficult to observe using visual inspection methods. The rapid inspection enabled by this setup led to the early detection of product defects on the manufacturing line, resulting in a significant improvement in the quality assurance of industrial products.

  2. Sequential Sampling Plan of Anthonomus grandis (Coleoptera: Curculionidae) in Cotton Plants.

    Science.gov (United States)

    Grigolli, J F J; Souza, L A; Mota, T A; Fernandes, M G; Busoli, A C

    2017-04-01

    The boll weevil, Anthonomus grandis grandis Boheman (Coleoptera: Curculionidae), is one of the most important pests of cotton production worldwide. The objective of this work was to develop a sequential sampling plan for the boll weevil. The studies were conducted in Maracaju, MS, Brazil, in two seasons with cotton cultivar FM 993. A 10,000-m2 area of cotton was subdivided into 100 of 10- by 10-m plots, and five plants per plot were evaluated weekly, recording the number of squares with feeding + oviposition punctures of A. grandis in each plant. A sequential sampling plan by the maximum likelihood ratio test was developed, using a 10% threshold level of squares attacked. A 5% security level was adopted for the elaboration of the sequential sampling plan. The type I and type II error used was 0.05, recommended for studies with insects. The adjustment of the frequency distributions used were divided into two phases, so that the model that best fit to the data was the negative binomial distribution up to 85 DAE (Phase I), and from there the best fit was Poisson distribution (Phase II). The equations that define the decision-making for Phase I are S0 = -5.1743 + 0.5730N and S1 = 5.1743 + 0.5730N, and for the Phase II are S0 = -4.2479 + 0.5771N and S1 = 4.2479 + 0.5771N. The sequential sampling plan developed indicated the maximum number of sample units expected for decision-making is ∼39 and 31 samples for Phases I and II, respectively. © The Authors 2017. Published by Oxford University Press on behalf of Entomological Society of America. All rights reserved. For Permissions, please email: journals.permissions@oup.com.

  3. A plan for safety and integrity of research reactor components

    International Nuclear Information System (INIS)

    Moatty, Mona S. Abdel; Khattab, M.S.

    2013-01-01

    Highlights: ► A plan for in-service inspection of research reactor components is put. ► Section XI of the ASME Code requirements is applied. ► Components subjected to inspection and their classes are defined. ► Flaw evaluation and its acceptance–rejection criteria are reviewed. ► A plan of repair or replacement is prepared. -- Abstract: Safety and integrity of a research reactor that has been operated over 40 years requires frequent and thorough inspection of all the safety-related components of the facility. The need of increasing the safety is the need of improving the reliability of its systems. Diligent and extensive planning of in-service inspection (ISI) of all reactor components has been imposed for satisfying the most stringent safety requirements. The Safeguards Officer's responsibilities of Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code ASME Code have been applied. These represent the most extensive and time-consuming part of ISI program, and identify the components subjected to inspection and testing, methods of component classification, inspection and testing techniques, acceptance/rejection criteria, and the responsibilities. The paper focuses on ISI planning requirements for welded systems such as vessels, piping, valve bodies, pump casings, and control rod-housing parts. The weld in integral attachments for piping, pumps, and valves are considered too. These are taken in consideration of safety class (1, 2, 3, etc.), reactor age, and weld type. The parts involve in the frequency of inspection, the examination requirements for each inspection, the examination method are included. Moreover the flaw evaluation, the plan of repair or replacement, and the qualification of nondestructive examination personnel are considered

  4. Terahertz Radome Inspection

    Directory of Open Access Journals (Sweden)

    Fabian Friederich

    2018-01-01

    Full Text Available Radomes protecting sensitive radar, navigational, and communications equipment of, e.g., aircraft, are strongly exposed to the environment and have to withstand harsh weather conditions and potential impacts. Besides their significance to the structural integrity of the radomes, it is often crucial to optimize the composite structures for best possible radio performance. Hence, there exists a significant interest in non-destructive testing techniques, which can be used for defect inspection of radomes in field use as well as for quality inspection during the manufacturing process. Contactless millimeter-wave and terahertz imaging techniques provide millimeter resolution and have the potential to address both application scenarios. We report on our development of a three-dimensional (3D terahertz imaging system for radome inspection during industrial manufacturing processes. The system was designed for operation within a machining center for radome manufacturing. It simultaneously gathers terahertz depth information in adjacent frequency ranges, from 70 to 110 GHz and from 110 to 170 GHz by combining two frequency modulated continuous-wave terahertz sensing units into a single measurement device. Results from spiraliform image acquisition of a radome test sample demonstrate the successful integration of the measurement system.

  5. Restaurant inspection frequency: The RestoFreq Study.

    Science.gov (United States)

    Medu, Olanrewaju; Turner, Hollie; Cushon, Jennifer A; Melis, Deborah; Rea, Leslie; Abdellatif, Treena; Neudorf, Cory O; Schwandt, Michael

    2017-03-01

    Foodborne illness is an important contributor to morbidity and health system costs in Canada. Using number of critical hazards as a proxy for food safety, we sought to better understand how to improve food safety in restaurants. We compared the current standard of annual inspections to twice-yearly inspections among restaurants "at risk" for food safety infractions. These were restaurants that had three or more elevated-risk inspection ratings in the preceding 36 months. We conducted a two-arm randomized controlled trial between November 2012 and October 2014. The intervention was twice-yearly routine restaurant inspection compared to standard once-yearly routine inspection. Included were all restaurants within Saskatoon Health Region that were assessed as "at risk", with 73 restaurants in the intervention arm and 78 in the control arm. Independent sample t-tests were conducted between groups to compare: i) average number of critical hazards per inspection; and ii) proportion of inspections resulting in a rating indicating an elevated hazard. Over time we noted statistically significant improvements across both study arms, in number of both critical food safety hazards (decreased by 61%) and elevated-risk inspection ratings (decreased by 45%) (p < 0.0001). We observed no significant differences between the two groups pre- or post-intervention. Results suggest increasing the number of annual routine inspections in high-risk restaurants was not associated with a significant difference in measures of compliance with food safety regulations. Findings of this study do not provide evidence supporting increased frequency of restaurant inspection from annually to twice annually.

  6. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2009

    International Nuclear Information System (INIS)

    2010-01-01

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2009 and includes inspection and repair activities completed at the following seven CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 407: Roller Coaster RadSafe Area (TTR); (3) CAU 424: Area 3 Landfill Complexes (TTR); (4) CAU 426: Cactus Spring Waste Trenches (TTR); (5) CAU 453: Area 9 UXO Landfill (TTR); (6) CAU 484: Surface Debris, Waste Sites, and Burn Area (TTR); and (7) CAU 487: Thunderwell Site (TTR). The annual post-closure inspections were conducted May 5-6, 2009. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2009, and the vegetation monitoring report is included in Attachment F. Maintenance was performed at CAU 453. Animal burrows observed during the annual inspection were backfilled, and a depression was restored to grade on June 25, 2009. Post-closure site inspections should continue as scheduled. Vegetation survey inspections have been conducted annually at CAUs 400, 404, 407, and 426. Discontinuation of vegetation surveys is recommended at the CAU 400 Bomblet Pit and CAU 426, which have been successfully revegetated. Discontinuation of vegetation surveys is also recommended at CAU 404, which has been changed to an administrative closure with no inspections

  7. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2009

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2010-05-28

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2009 and includes inspection and repair activities completed at the following seven CAUs: · CAU 400: Bomblet Pit and Five Points Landfill (TTR) · CAU 407: Roller Coaster RadSafe Area (TTR) · CAU 424: Area 3 Landfill Complexes (TTR) · CAU 426: Cactus Spring Waste Trenches (TTR) · CAU 453: Area 9 UXO Landfill (TTR) · CAU 484: Surface Debris, Waste Sites, and Burn Area (TTR) · CAU 487: Thunderwell Site (TTR) The annual post-closure inspections were conducted May 5–6, 2009. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in June 2009, and the vegetation monitoring report is included in Attachment F. Maintenance was performed at CAU 453. Animal burrows observed during the annual inspection were backfilled, and a depression was restored to grade on June 25, 2009. Post-closure site inspections should continue as scheduled. Vegetation survey inspections have been conducted annually at CAUs 400, 404, 407, and 426. Discontinuation of vegetation surveys is recommended at the CAU 400 Bomblet Pit and CAU 426, which have been successfully revegetated. Discontinuation of vegetation surveys is also recommended at CAU 404, which has been changed to an administrative closure with no inspections required. Vegetation

  8. A scalable method for parallelizing sampling-based motion planning algorithms

    KAUST Repository

    Jacobs, Sam Ade; Manavi, Kasra; Burgos, Juan; Denny, Jory; Thomas, Shawna; Amato, Nancy M.

    2012-01-01

    This paper describes a scalable method for parallelizing sampling-based motion planning algorithms. It subdivides configuration space (C-space) into (possibly overlapping) regions and independently, in parallel, uses standard (sequential) sampling-based planners to construct roadmaps in each region. Next, in parallel, regional roadmaps in adjacent regions are connected to form a global roadmap. By subdividing the space and restricting the locality of connection attempts, we reduce the work and inter-processor communication associated with nearest neighbor calculation, a critical bottleneck for scalability in existing parallel motion planning methods. We show that our method is general enough to handle a variety of planning schemes, including the widely used Probabilistic Roadmap (PRM) and Rapidly-exploring Random Trees (RRT) algorithms. We compare our approach to two other existing parallel algorithms and demonstrate that our approach achieves better and more scalable performance. Our approach achieves almost linear scalability on a 2400 core LINUX cluster and on a 153,216 core Cray XE6 petascale machine. © 2012 IEEE.

  9. A scalable method for parallelizing sampling-based motion planning algorithms

    KAUST Repository

    Jacobs, Sam Ade

    2012-05-01

    This paper describes a scalable method for parallelizing sampling-based motion planning algorithms. It subdivides configuration space (C-space) into (possibly overlapping) regions and independently, in parallel, uses standard (sequential) sampling-based planners to construct roadmaps in each region. Next, in parallel, regional roadmaps in adjacent regions are connected to form a global roadmap. By subdividing the space and restricting the locality of connection attempts, we reduce the work and inter-processor communication associated with nearest neighbor calculation, a critical bottleneck for scalability in existing parallel motion planning methods. We show that our method is general enough to handle a variety of planning schemes, including the widely used Probabilistic Roadmap (PRM) and Rapidly-exploring Random Trees (RRT) algorithms. We compare our approach to two other existing parallel algorithms and demonstrate that our approach achieves better and more scalable performance. Our approach achieves almost linear scalability on a 2400 core LINUX cluster and on a 153,216 core Cray XE6 petascale machine. © 2012 IEEE.

  10. Spatial Distribution and Sampling Plans for Grapevine Plant Canopy-Inhabiting Scaphoideus titanus (Hemiptera: Cicadellidae) Nymphs.

    Science.gov (United States)

    Rigamonti, Ivo E; Brambilla, Carla; Colleoni, Emanuele; Jermini, Mauro; Trivellone, Valeria; Baumgärtner, Johann

    2016-04-01

    The paper deals with the study of the spatial distribution and the design of sampling plans for estimating nymph densities of the grape leafhopper Scaphoideus titanus Ball in vine plant canopies. In a reference vineyard sampled for model parameterization, leaf samples were repeatedly taken according to a multistage, stratified, random sampling procedure, and data were subjected to an ANOVA. There were no significant differences in density neither among the strata within the vineyard nor between the two strata with basal and apical leaves. The significant differences between densities on trunk and productive shoots led to the adoption of two-stage (leaves and plants) and three-stage (leaves, shoots, and plants) sampling plans for trunk shoots- and productive shoots-inhabiting individuals, respectively. The mean crowding to mean relationship used to analyze the nymphs spatial distribution revealed aggregated distributions. In both the enumerative and the sequential enumerative sampling plans, the number of leaves of trunk shoots, and of leaves and shoots of productive shoots, was kept constant while the number of plants varied. In additional vineyards data were collected and used to test the applicability of the distribution model and the sampling plans. The tests confirmed the applicability 1) of the mean crowding to mean regression model on the plant and leaf stages for representing trunk shoot-inhabiting distributions, and on the plant, shoot, and leaf stages for productive shoot-inhabiting nymphs, 2) of the enumerative sampling plan, and 3) of the sequential enumerative sampling plan. In general, sequential enumerative sampling was more cost efficient than enumerative sampling.

  11. Sampling and Analysis Plan for K Basins Debris

    International Nuclear Information System (INIS)

    WESTCOTT, J.L.

    2000-01-01

    This Sampling and Analysis Plan presents the rationale and strategy for sampling and analysis activities to support removal of debris from the K-East and K-West Basins located in the 100K Area at the Hanford Site. This project is focused on characterization to support waste designation for disposal of waste at the Environmental Restoration Disposal Facility (ERDF). This material has previously been dispositioned at the Hanford Low-Level Burial Grounds or Central Waste Complex. The structures that house the basins are classified as radioactive material areas. Therefore, all materials removed from the buildings are presumed to be radioactively contaminated. Because most of the materials that will be addressed under this plan will be removed from the basins, and because of the cost associated with screening materials for release, it is anticipated that all debris will be managed as low-level waste. Materials will be surveyed, however, to estimate radionuclide content for disposal and to determine that the debris is not contaminated with levels of transuranic radionuclides that would designate the debris as transuranic waste

  12. Usability improvement of x-ray food inspection equipment

    International Nuclear Information System (INIS)

    Ohira, Norihiro; Yamaguchi, Takashi; Ohara, Mamoru; Shimizu, Hideaki; Kamimura, Kunio; Saiki, Hideo

    2010-01-01

    To properly set up X-ray inspection equipment of foreign bodies in foods properly has become more and more complicated and time-consuming, because digital image processing used in it has more parameters for more precise inspecting. In this paper, it is reported some methods to lighten the work load of workers who set up the parameters. Using Statistical methods, we construct an auto setting lookup table for adjusting contrast and parameters of inspection algorithm. With the former we confirmed an expansion of a range of grey levels that include domain of foreign bodies in sample data. Furthermore, with we constructed in our former research, we can set automatically limit of parameters that judge input product's image to be not including foreign bodies. It is suitable for food inspection system, since users prefer severely inspecting of foreign products. (author)

  13. Sampling and Analysis Plan for the 216-A-29 Ditch

    International Nuclear Information System (INIS)

    Petersen, S.W.

    1998-06-01

    This sampling and analysis plan defines procedures to be used for collecting and handling samples to be obtained from the 216-A-29 Ditch, and identifies requirements for field and laboratory measurements. The sampling strategy describes here is derived from a Data Quality Objectives workshop conducted in January 1997 to support sampling to assure worker safety during construction and to assess the validity of a 1988 ditch sampling campaign and the effectiveness of subsequent stabilization. The purpose of the proposed sampling and analysis activities is to characterize soil contamination in the vicinity of a proposed road over the 216-A-29 Ditch

  14. Hydro-Quebec inspection robot RIT-LRG

    International Nuclear Information System (INIS)

    Champagne, D.; Rinfret, F.; Bourgault, Y.G.

    2008-01-01

    Hydro Quebec's Research Centre (IREQ), has developed a variety of inspection tools over the years. The Metar bracelet for the feeder tubes, the REC robot for the heat exchanger and the RIT robot for the Delayed Neutron system just to name a few. This paper discusses with the successful deployment of the Camera Probe Positioning robot for Visual Inspection of the sample lines of the delayed neutron system of CANDU power plants. This RIT robot has three possible configurations (Face, Cabinet and LRG configurations) and has remained a prototype version although it has been used over the years in many outage inspection campaigns since 1997. The main advantages of using this robot are: the significant reduction in radiation exposure, the high quality of the data collected and the archiving of inspection data for further analysis and reports. In 2007, Gentilly-2 (G-2), decided to industrialize the LRG configuration of the RIT robot and to designate it the standard tool for the inspection of the Delayed Neutron System. An improved RIT-LRG robot, along with its control box and command station was developed. The software had to be rewritten requiring an ergonomics analysis of user tasks, work station and interface display. These issues included both physical and cognitive requirements aspects. The two principal topics of this paper will be on the Inspection Robot Technology developed and highlights of the 2008 outage inspection campaign. (author)

  15. Hydro-Quebec inspection robot RIT-LRG

    Energy Technology Data Exchange (ETDEWEB)

    Champagne, D., E-mail: champagne.dominique@ireq.ca [Inst. de recherche d' Hydro-Quebec, Quebec (Canada); Rinfret, F.; Bourgault, Y.G., E-mail: rinfret.francois@hydro.qc.ca, E-mail: bourgault.yves.g@hydro.qc.ca [Hydro-Quebec, Becancour, Quebec (Canada)

    2008-07-01

    Hydro Quebec's Research Centre (IREQ), has developed a variety of inspection tools over the years. The Metar bracelet for the feeder tubes, the REC robot for the heat exchanger and the RIT robot for the Delayed Neutron system just to name a few. This paper discusses with the successful deployment of the Camera Probe Positioning robot for Visual Inspection of the sample lines of the delayed neutron system of CANDU power plants. This RIT robot has three possible configurations (Face, Cabinet and LRG configurations) and has remained a prototype version although it has been used over the years in many outage inspection campaigns since 1997. The main advantages of using this robot are: the significant reduction in radiation exposure, the high quality of the data collected and the archiving of inspection data for further analysis and reports. In 2007, Gentilly-2 (G-2), decided to industrialize the LRG configuration of the RIT robot and to designate it the standard tool for the inspection of the Delayed Neutron System. An improved RIT-LRG robot, along with its control box and command station was developed. The software had to be rewritten requiring an ergonomics analysis of user tasks, work station and interface display. These issues included both physical and cognitive requirements aspects. The two principal topics of this paper will be on the Inspection Robot Technology developed and highlights of the 2008 outage inspection campaign. (author)

  16. An intelligent inspection and survey robot. Volume 1

    International Nuclear Information System (INIS)

    1995-01-01

    ARIES number-sign 1 (Autonomous Robotic Inspection Experimental System), has been developed for the Department of Energy to survey and inspect drums containing low-level radioactive waste stored in warehouses at DOE facilities. The drums are typically stacked four high and arranged in rows with three-foot aisle widths. The robot will navigate through the aisles and perform an inspection operation, typically performed by a human operator, making decisions about the condition of the drums and maintaining a database of pertinent information about each drum. A new version of the Cybermotion series of mobile robots is the base mobile vehicle for ARIES. The new Model K3A consists of an improved and enhanced mobile platform and a new turret that will permit turning around in a three-foot aisle. Advanced sonar and lidar systems were added to improve navigation in the narrow drum aisles. Onboard computer enhancements include a VMEbus computer system running the VxWorks real-time operating system. A graphical offboard supervisory UNIX workstation is used for high-level planning, control, monitoring, and reporting. A camera positioning system (CPS) includes primitive instructions for the robot to use in referencing and positioning the payload. The CPS retracts to a more compact position when traveling in the open warehouse. During inspection, the CPS extends up to deploy inspection packages at different heights on the four-drum stacks of 55-, 85-, and 110-gallon drums. The vision inspection module performs a visual inspection of the waste drums. This system will locate and identify each drum, locate any unique visual features, characterize relevant surface features of interest and update a data-base containing the inspection data

  17. An intelligent inspection and survey robot. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-12-15

    ARIES {number_sign}1 (Autonomous Robotic Inspection Experimental System), has been developed for the Department of Energy to survey and inspect drums containing low-level radioactive waste stored in warehouses at DOE facilities. The drums are typically stacked four high and arranged in rows with three-foot aisle widths. The robot will navigate through the aisles and perform an inspection operation, typically performed by a human operator, making decisions about the condition of the drums and maintaining a database of pertinent information about each drum. A new version of the Cybermotion series of mobile robots is the base mobile vehicle for ARIES. The new Model K3A consists of an improved and enhanced mobile platform and a new turret that will permit turning around in a three-foot aisle. Advanced sonar and lidar systems were added to improve navigation in the narrow drum aisles. Onboard computer enhancements include a VMEbus computer system running the VxWorks real-time operating system. A graphical offboard supervisory UNIX workstation is used for high-level planning, control, monitoring, and reporting. A camera positioning system (CPS) includes primitive instructions for the robot to use in referencing and positioning the payload. The CPS retracts to a more compact position when traveling in the open warehouse. During inspection, the CPS extends up to deploy inspection packages at different heights on the four-drum stacks of 55-, 85-, and 110-gallon drums. The vision inspection module performs a visual inspection of the waste drums. This system will locate and identify each drum, locate any unique visual features, characterize relevant surface features of interest and update a data-base containing the inspection data.

  18. Sampling and analysis plan for the former Atomic Energy Commission bus lot property

    International Nuclear Information System (INIS)

    Nielson, R.R.

    1998-07-01

    This sampling and analysis plan (SAP) presents the rationale and strategy for the sampling and analysis activities proposed in support of an initial investigation of the former Atomic Energy Commission (AEC) bus lot property currently owned by Battelle Memorial Institute. The purpose of the proposed sampling and analysis activity is to investigate the potential for contamination above established action levels. The SAP will provide defensible data of sufficient quality and quantity to support recommendations of whether any further action within the study area is warranted. To assist in preparing sampling plans and reports, the Washington State Department of Ecology (Ecology) has published Guidance on Sampling and Data Analysis Methods. To specifically address sampling plans for petroleum-contaminated sites, Ecology has also published Guidance for Remediation of Petroleum Contaminated Sites. Both documents were used as guidance in preparing this plan. In 1992, a soil sample was taken within the current study area as part of a project to remove two underground storage tanks (USTs) at Battelle's Sixth Street Warehouse Petroleum Dispensing Station (Section 1.3). The results showed that the sample contained elevated levels of total petroleum hydrocarbons (TPH) in the heavy distillate range. This current study was initiated in part as a result of that discovery. The following topics are considered: the historical background of the site, current site conditions, previous investigations performed at the site, an evaluation based on the available data, and the contaminants of potential concern (COPC)

  19. Sampling and analysis plan for the former Atomic Energy Commission bus lot property

    Energy Technology Data Exchange (ETDEWEB)

    Nielson, R.R.

    1998-07-01

    This sampling and analysis plan (SAP) presents the rationale and strategy for the sampling and analysis activities proposed in support of an initial investigation of the former Atomic Energy Commission (AEC) bus lot property currently owned by Battelle Memorial Institute. The purpose of the proposed sampling and analysis activity is to investigate the potential for contamination above established action levels. The SAP will provide defensible data of sufficient quality and quantity to support recommendations of whether any further action within the study area is warranted. To assist in preparing sampling plans and reports, the Washington State Department of Ecology (Ecology) has published Guidance on Sampling and Data Analysis Methods. To specifically address sampling plans for petroleum-contaminated sites, Ecology has also published Guidance for Remediation of Petroleum Contaminated Sites. Both documents were used as guidance in preparing this plan. In 1992, a soil sample was taken within the current study area as part of a project to remove two underground storage tanks (USTs) at Battelle`s Sixth Street Warehouse Petroleum Dispensing Station (Section 1.3). The results showed that the sample contained elevated levels of total petroleum hydrocarbons (TPH) in the heavy distillate range. This current study was initiated in part as a result of that discovery. The following topics are considered: the historical background of the site, current site conditions, previous investigations performed at the site, an evaluation based on the available data, and the contaminants of potential concern (COPC).

  20. IP Sample Plan #1 | NCI Technology Transfer Center | TTC

    Science.gov (United States)

    Sample letter that shows how Universities including co-investigators, consultants, and collaborators can describe a data and research tool sharing plan and procedures for exercising intellectual property rights. The letter is to be used as part of the University's application. 

  1. Visual Sample Plan Version 7.0 User's Guide

    Energy Technology Data Exchange (ETDEWEB)

    Matzke, Brett D. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Newburn, Lisa LN [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Hathaway, John E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Bramer, Lisa M. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Wilson, John E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Dowson, Scott T. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Sego, Landon H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Pulsipher, Brent A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2014-03-01

    User's guide for VSP 7.0 This user's guide describes Visual Sample Plan (VSP) Version 7.0 and provides instructions for using the software. VSP selects the appropriate number and location of environmental samples to ensure that the results of statistical tests performed to provide input to risk decisions have the required confidence and performance. VSP Version 7.0 provides sample-size equations or algorithms needed by specific statistical tests appropriate for specific environmental sampling objectives. It also provides data quality assessment and statistical analysis functions to support evaluation of the data and determine whether the data support decisions regarding sites suspected of contamination. The easy-to-use program is highly visual and graphic. VSP runs on personal computers with Microsoft Windows operating systems (XP, Vista, Windows 7, and Windows 8). Designed primarily for project managers and users without expertise in statistics, VSP is applicable to two- and three-dimensional populations to be sampled (e.g., rooms and buildings, surface soil, a defined layer of subsurface soil, water bodies, and other similar applications) for studies of environmental quality. VSP is also applicable for designing sampling plans for assessing chem/rad/bio threat and hazard identification within rooms and buildings, and for designing geophysical surveys for unexploded ordnance (UXO) identification.

  2. Ground-water sample collection and analysis plan for the ground-water surveillance project

    International Nuclear Information System (INIS)

    Bryce, R.W.; Evans, J.C.; Olsen, K.B.

    1991-12-01

    The Pacific Northwest Laboratory performs ground-water sampling activities at the US Department of Energy's (DOE's) Hanford Site in support of DOE's environmental surveillance responsibilities. The purpose of this document is to translate DOE's General Environmental Protection Program (DOE Order 5400.1) into a comprehensive ground-water sample collection and analysis plan for the Hanford Site. This sample collection and analysis plan sets forth the environmental surveillance objectives applicable to ground water, identifies the strategy for selecting sample collection locations, and lists the analyses to be performed to meet those objectives

  3. Advanced inspection technology for non intrusive inspection (NII) program

    International Nuclear Information System (INIS)

    Zamir Mohamed Daud

    2003-01-01

    In the current economic environment, plants and facilities are under pressure to introduced cost saving as well as profit maximising measures. Among the many changes in the way things are run is a move towards Risk Based Inspection (RBI), with an emphasis on longer operating periods between shutdowns as well as to utilise components to their maximum capability. Underpinning and RBI program requires good data from an effective online inspections program, which would not require the shutdown of critical components. One methodology of online inspection is known as Non Intrusive Inspection (NII), an inspection philosophy with the objective of replacing internal inspection of a vessel by doing Non Destructive Testing (NDT) and inspections externally. To this end, a variety of advanced NDT techniques are needed to provide accurate online measurements. (Author)

  4. Cost-effective degradation test plan for a nonlinear random-coefficients model

    International Nuclear Information System (INIS)

    Kim, Seong-Joon; Bae, Suk Joo

    2013-01-01

    The determination of requisite sample size and the inspection schedule considering both testing cost and accuracy has been an important issue in the degradation test. This paper proposes a cost-effective degradation test plan in the context of a nonlinear random-coefficients model, while meeting some precision constraints for failure-time distribution. We introduce a precision measure to quantify the information losses incurred by reducing testing resources. The precision measure is incorporated into time-varying cost functions to reflect real circumstances. We apply a hybrid genetic algorithm to general cost optimization problem with reasonable constraints on the level of testing precision in order to determine a cost-effective inspection scheme. The proposed method is applied to the degradation data of plasma display panels (PDPs) following a bi-exponential degradation model. Finally, sensitivity analysis via simulation is provided to evaluate the robustness of the proposed degradation test plan.

  5. Liquid effluent Sampling and Analysis Plan (SAP) implementation summary report

    International Nuclear Information System (INIS)

    Lueck, K.J.

    1995-01-01

    This report summarizes liquid effluent analytical data collected during the Sampling and Analysis Plan (SAP) Implementation Program, evaluates whether or not the sampling performed meets the requirements of the individual SAPs, compares the results to the WAC 173-200 Ground Water Quality Standards. Presented in the report are results from liquid effluent samples collected (1992-1994) from 18 of the 22 streams identified in the Consent Order (No. DE 91NM-177) requiring SAPs

  6. Planning Considerations Related to Collecting and Analyzing Samples of the Martian Soils

    Science.gov (United States)

    Liu, Yang; Mellon, Mike T.; Ming, Douglas W.; Morris, Richard V.; Noble, Sarah K.; Sullivan, Robert J.; Taylor, Lawrence A.; Beaty, David W.

    2014-01-01

    The Mars Sample Return (MSR) End-to-End International Science Analysis Group (E2E-iSAG [1]) established scientific objectives associ-ated with Mars returned-sample science that require the return and investigation of one or more soil samples. Soil is defined here as loose, unconsolidated materials with no implication for the presence or absence of or-ganic components. The proposed Mars 2020 (M-2020) rover is likely to collect and cache soil in addition to rock samples [2], which could be followed by future sample retrieval and return missions. Here we discuss key scientific consid-erations for sampling and caching soil samples on the proposed M-2020 rover, as well as the state in which samples would need to be preserved when received by analysts on Earth. We are seeking feedback on these draft plans as input to mission requirement formulation. A related planning exercise on rocks is reported in an accompanying abstract [3].

  7. Ultra-low field MRI food inspection system prototype

    Energy Technology Data Exchange (ETDEWEB)

    Kawagoe, Satoshi, E-mail: s133413@edu.tut.ac.jp; Toyota, Hirotomo; Hatta, Junichi; Ariyoshi, Seiichiro; Tanaka, Saburo, E-mail: tanakas@ens.tut.ac.jp

    2016-11-15

    Highlights: • We have developed a ULF-MRI system using HTS-SQUID for food inspection. • We developed a compact magnetically shielded box to attenuate environmental noise. • The 2D-MR image was reconstructed from the grid processing data using 2D-FFT method. • The 2D-MR images of a disk-shaped and a multiple cell water sample were obtained. • The results showed the possibility of applying the ULF-MRI system to food inspection. - Abstract: We develop an ultra-low field (ULF) magnetic resonance imaging (MRI) system using a high-temperature superconducting quantum interference device (HTS-SQUID) for food inspection. A two-dimensional (2D)-MR image is reconstructed from the grid processing raw data using the 2D fast Fourier transform method. In a previous study, we combined an LC resonator with the ULF-MRI system to improve the detection area of the HTS-SQUID. The sensitivity was improved, but since the experiments were performed in a semi-open magnetically shielded room (MSR), external noise was a problem. In this study, we develop a compact magnetically shielded box (CMSB), which has a small open window for transfer of a pre-polarized sample. Experiments were performed in the CMSB and 2D-MR images were compared with images taken in the semi-open MSR. A clear image of a disk-shaped water sample is obtained, with an outer dimension closer to that of the real sample than in the image taken in the semi-open MSR. Furthermore, the 2D-MR image of a multiple cell water sample is clearly reconstructed. These results show the applicability of the ULF-MRI system in food inspection.

  8. On the efforts (man-day) concerned with inspection in uranium fuel fabrication facility

    International Nuclear Information System (INIS)

    Watanabe, T.; Tanaka, T.; Seki, Y.

    1990-01-01

    Taking notice of inspection efforts (man·day) of STA·IAEA and those of MNF concerned with them, their change and various factors affecting the change have been studied. Namely, first, main topics concerning inspection in our Tokai plant are mentioned and secondly the relation between the inspection efforts and such factors as PIV period, number of items, number of DA sampling and NDA measurements, and so forth is studied. According to our study, though efforts of STA·IAEA and MNF required for both routine FLOW inspection and PIT have been nearly unchanged each year, our efforts for PIV have been increasing gradually. The factors relating to this increase of our efforts are the PIV period, inspection efforts of STA·IAEA for PIV and the number of DA sampling and NDA measurements. Finally, a suggestion on the future inspection system has been mentioned and then some items for improvement under the current inspection system have been exemplified. (author)

  9. A risk-informed approach to optimising in-service inspection of piping

    International Nuclear Information System (INIS)

    Billington, A.; Monette, P.

    1999-01-01

    Traditional criteria for the selection of in-service inspection locations in piping, have come to be regarded as being out-of-touch with current knowledge of piping failures and with current measures of safety importance. An alternative , risk-informed, method has been developed and successfully licensed, that systematically establishes an inspection plan addressing all safety-related piping systems, in a way that is optimized with respect to the safety gain achieved through in-service inspection. The principles of the method are discussed and the results of several applications are summarized, all of which demonstrate that the risk-informed program would lead to significant improvements in the overall level of plant safety, while at the same time re-distributing the inspections in such a way that reduces both plant costs and radiation exposure to personnel.(author)

  10. Examples of in-service inspections and typical maintenance schedule for low-power research reactors

    International Nuclear Information System (INIS)

    Boeck, H.

    1997-01-01

    In-service inspection methods for low-power research reactors are described which have been developed during the past 37 years of the operation of the TRIGA reactor Vienna. Special tools have been developed during this period and their application for maintenance and in-serve inspection is discussed. Two practical in-service inspections at a TRIGA reactor and at a MTR reactor are presented. Further a typical maintenance plan for a TRIGA reactor is listed in the annex. (author)

  11. IP Sample Plan #3 | NCI Technology Transfer Center | TTC

    Science.gov (United States)

    Sample Research Resources and Intellectual Property Plan for use by an Institution and its Collaborators for intellectual property protection strategies covering pre-existing intellectual property, agreements with commercial sources, privacy, and licensing.  | [google6f4cd5334ac394ab.html

  12. Cecil gives in-bundle access for inspection and lancing [steam generators

    International Nuclear Information System (INIS)

    Trovato, S.A.; Ruggieri, S.K.

    1989-01-01

    Cecil (Consolidated Edison Combined Inspection and Lancing System) is a robotic device which makes it possible to take inspection and sludge lancing equipment deep inside steam generator tube bundles. Cecil is teleoperated to perform tube bundle inspections, sludge sampling and sludge lancing. The first field test of Cecil at Indian Point 2 reactor, successfully demonstrated its capability for high quality inspection, and its potential for improved sludge removal, both with reduced personnel radiation exposure. (U.K.)

  13. Image acquisition, transmission and assignment in 60Co container inspection system

    International Nuclear Information System (INIS)

    Wu Zhifang; Zhou Liye; Liu Ximing; Wang Liqiang

    1999-01-01

    The author describes the data acquisition mode and image reconstruction method in 60 Co container inspection system, analyzes the relationship between line pick period and geometry distortion, makes clear the demand to data transmitting rate. It discusses several data communication methods, draws up a plan for network, realizes automatic direction and reasonable assignment of data in the system, cooperation of multi-computer and parallel processing, thus greatly improves the systems inspection efficiency

  14. UMTRA Project water sampling and analysis plan, Canonsburg, Pennsylvania. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    Surface remedial action was completed at the US Department of Energy (DOE) Canonsburg and Burrell Uranium Mill Tailings Remedial Action (UMTRA) Project sites in southwestern Pennsylvania in 1985 and 1987, respectively. The Burrell disposal site, included in the UMTRA Project as a vicinity property, was remediated in conjunction with the remedial action at Canonsburg. On 27 May 1994, the Nuclear Regulatory Commission (NRC) accepted the DOE final Long-Term Surveillance Plan (LTSP) (DOE, 1993) for Burrell thus establishing the site under the general license in 10 CFR section 40.27 (1994). In accordance with the DOE guidance document for long-term surveillance (DOE, 1995), all NRC/DOE interaction on the Burrell site's long-term care now is conducted with the DOE Grand Junction Projects Office in Grand Junction, Colorado, and is no longer the responsibility of the DOE UMTRA Project Team in Albuquerque, New Mexico. Therefore, the planned sampling activities described in this water sampling and analysis plan (WSAP) are limited to the Canonsburg site. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequencies for routine monitoring at the Canonsburg site for calendar years 1995 and 1996. Currently, the analytical data further the site characterization and demonstrate that the disposal cell's initial performance is in accordance with design requirements

  15. Sampling and analysis plan for Wayne Interim Storage Site (WISS), Wayne, New Jersey

    International Nuclear Information System (INIS)

    Brown, K.S.; Murray, M.E.; Rodriguez, R.E.

    1998-10-01

    This field sampling plan describes the methodology to perform an independent radiological verification survey and chemical characterization of a remediated area of the subpile at the Wayne Interim Storage Site, Wayne, New Jersey.Data obtained from collection and analysis of systematic and biased soil samples will be used to assess the status of remediation at the site and verify the final radiological status. The objective of this plan is to describe the methods for obtaining sufficient and valid measurements and analytical data to supplement and verify a radiological profile already established by the Project Remediation Management Contractor (PMC). The plan describes the procedure for obtaining sufficient and valid analytical data on soil samples following remediation of the first layer of the subpile. Samples will be taken from an area of the subpile measuring approximately 30 m by 80 m from which soil has been excavated to a depth of approximately 20 feet to confirm that the soil beneath the excavated area does not exceed radiological guidelines established for the site or chemical regulatory limits for inorganic metals. After the WISS has been fully remediated, the Department of Energy will release it for industrial/commercial land use in accordance with the Record of Decision. This plan provides supplemental instructions to guidelines and procedures established for sampling and analysis activities. Procedures will be referenced throughout this plan as applicable, and are available for review if necessary

  16. Design of an aid to visual inspection workstation

    Science.gov (United States)

    Tait, Robert; Harding, Kevin

    2016-05-01

    Visual Inspection is the most common means for inspecting manufactured parts for random defects such as pits, scratches, breaks, corrosion or general wear. The reason for the need for visual inspection is the very random nature of what might be a defect. Some defects may be very rare, being seen once or twice a year, but May still be critical to part performance. Because of this random and rare nature, even the most sophisticated image analysis programs have not been able to recognize all possible defects. Key to any future automation of inspection is obtaining good sample images of what might be a defect. However, most visual check take no images and consequently generate no digital data or historical record beyond a simple count. Any additional tool to captures such images must be able to do so without taking addition time. This paper outlines the design of a potential visual inspection station that would be compatible with current visual inspection methods, but afford the means for reliable digital imaging and in many cases augmented capabilities to assist the inspection. Considerations in this study included: resolution, depth of field, feature highlighting, and ease of digital capture, annotations and inspection augmentation for repeatable registration as well as operator assistance and training.

  17. NG09 And CTBT On-Site Inspection Noble Gas Sampling and Analysis Requirements

    Science.gov (United States)

    Carrigan, Charles R.; Tanaka, Junichi

    2010-05-01

    A provision of the Comprehensive Test Ban Treaty (CTBT) allows on-site inspections (OSIs) of suspect nuclear sites to determine if the occurrence of a detected event is nuclear in origin. For an underground nuclear explosion (UNE), the potential success of an OSI depends significantly on the containment scenario of the alleged event as well as the application of air and soil-gas radionuclide sampling techniques in a manner that takes into account both the suspect site geology and the gas transport physics. UNE scenarios may be broadly divided into categories involving the level of containment. The simplest to detect is a UNE that vents a significant portion of its radionuclide inventory and is readily detectable at distance by the International Monitoring System (IMS). The most well contained subsurface events will only be detectable during an OSI. In such cases, 37 Ar and radioactive xenon cavity gases may reach the surface through either "micro-seepage" or the barometric pumping process and only the careful siting of sampling locations, timing of sampling and application of the most site-appropriate atmospheric and soil-gas capturing methods will result in a confirmatory signal. The OSI noble gas field tests NG09 was recently held in Stupava, Slovakia to consider, in addition to other field sampling and analysis techniques, drilling and subsurface noble gas extraction methods that might be applied during an OSI. One of the experiments focused on challenges to soil-gas sampling near the soil-atmosphere interface. During withdrawal of soil gas from shallow, subsurface sample points, atmospheric dilution of the sample and the potential for introduction of unwanted atmospheric gases were considered. Tests were designed to evaluate surface infiltration and the ability of inflatable well-packers to seal out atmospheric gases during sample acquisition. We discuss these tests along with some model-based predictions regarding infiltration under different near

  18. Development of automatic inspection robot for nuclear power plants

    International Nuclear Information System (INIS)

    Yamada, K.; Suzuki, K.; Saitoh, K.; Sakaki, T.; Ohe, Y.; Mizutani, T.; Segawa, M.; Kubo, K.

    1987-01-01

    This robot system has been developed for automatic inspection of nuclear power plants. The system configuration is composed of vehicle that runs on monorail, the sensors on the vehicle, an image processer that processes the image information from the sensors, a computer that creates the inspection planning of the robot and an operation panel. This system has two main features, the first is the robot control system. The vehicle and the sensors are controlled by the output data calculated in the computer with the three dimensional plant data. The malfunction is recognized by the combination of the results of image processing, information from the microphone and infrared camera. Tests for a prototype automatic inspection robot system have been performed in the simulated main steam piping room of a nuclear power plant

  19. Calculation of frequency of optimal inspection in non-notice inspection game

    International Nuclear Information System (INIS)

    Kumakura, Shinichi; Gotoh, Yoshiki; Kikuchi, Masahiro

    2011-01-01

    We consider a non-notice inspection game between an inspection party, who verifies absence of diversion of nuclear materials and misuse of nuclear facility, and a facility operator, who tries them in a nuclear facility. In the game, the payoff for each player, inspection party and facility operator, is composed of various elements (parameters) such as facility type, a type of nuclear material, number of inspection and others. Their payoffs consist of profits and costs (minus profit). Because of random nature by non-notice inspection, its deterrence effect and inspection number could have the potential to affect their payoffs. In this paper, their payoffs taking into consideration of the inspection environment above are represented as a function of inspection number. Then, the optimal number is calculated from a condition on their payoffs for number of inspection. Comparable statics analysis is performed in order to observe the change of inspection number which is equilibrium point by changing these parameters including deterrence effect, because the number derived depends on each parameter within the inspection environment. Based on the analysis results, necessary conditions to reduce the inspection number keeping inspection effect are pointed out. (author)

  20. IP Sample Plan #4 | NCI Technology Transfer Center | TTC

    Science.gov (United States)

    Sample letter from Research Institutes and their principal investigator and consultants, describing a data and research tool sharing plan and procedures for sharing data, research materials, and patent and licensing of intellectual property. This letter is designed to be included as part of an application.

  1. Proceedings of the workshop for exchange of technology for CWC inspections

    Energy Technology Data Exchange (ETDEWEB)

    McGuire, R.R.

    1993-04-01

    With the signing of the Chemical Weapons Convention (CWC), the work of the Preparatory Commission in defining the modalities of on-site verification inspections will begin early in 1993. One of the methods for increasing the effectiveness of inspections is the collection of samples for chemical analysis. The CWC allows for this analysis to be performed either at the site of the inspection or in a dedicated off-site laboratory. The decision as to where samples are to be analyzed in any specific instance may involve a consideration of the threat, real or perceived, to the compromise of legitimate sensitive host-party information. The ability to perform efficient chemical analysis at the inspection site, where samples remain in joint (host-inspector) custody and the analytical procedures can be observed by the host, can alleviate much of the concern over possible loss of confidential information in both government and industry. This workshop was designed to encourage the exchange of information among participants with experience in the use of analytical equipment for on-site sample collection and analysis. Individual projects are processed separately for the databases.

  2. Operable Unit 3-13, Group 3, Other Surface Soils (Phase II) Field Sampling Plan

    Energy Technology Data Exchange (ETDEWEB)

    G. L. Schwendiman

    2006-07-27

    This Field Sampling Plan describes the Operable Unit 3-13, Group 3, Other Surface Soils, Phase II remediation field sampling activities to be performed at the Idaho Nuclear Technology and Engineering Center located within the Idaho National Laboratory Site. Sampling activities described in this plan support characterization sampling of new sites, real-time soil spectroscopy during excavation, and confirmation sampling that verifies that the remedial action objectives and remediation goals presented in the Final Record of Decision for Idaho Nuclear Technology and Engineering Center, Operable Unit 3-13 have been met.

  3. 105-F and DR Phase 1 Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    Curry, L.R.

    1998-06-01

    This SAP presents the rationale and strategy for characterization of specific rooms within the 105-F and 105-DR reactor buildings. Figures 1-1 and 1-2 identify the rooms that are the subject of this SAP. These rooms are to be decontaminated and demolished as an initial step (Phase 1 ) in the Interim Safe Storage process for these reactors. Section 1.0 presents the background and sites history for the reactor buildings and summarizes the data quality objective process, which provides the logical basis for this SAP. Preliminary surveys indicate that little radiochemical contamination is present. Section 2.0 presents the quality assurance project plan, which includes a project management structure, sampling methods and quality control, and oversight of the sampling process. Section 2.2.1 summarizes the sampling methods, reflecting the radiological and chemical sampling designs presented in Tables 1-17 and 1-18. Section 3.0 presents the Field Sampling Plan for Phase 1. The sampling design is broken into two stages. Stage 1 will verify the list of radioactive constituents of concern and generate the isotopic distribution. The objectives of Stage 2 are to estimate the radionuclide inventories of room debris, quantify chemical contamination, and survey room contents for potential salvage or recycle. Table 3-1 presents the sampling activities to be performed in Stage 1. Tables 1-17 and 1-18 identify samples to be collected in Stage 2. Stage 2 will consist primarily of survey data collection, with fixed laboratory samples to be collected in areas showing visible stains. Quality control sampling requirements are presented in Table 3-2

  4. Guide to the periodic inspection of nuclear reactor steel pressure vessels

    International Nuclear Information System (INIS)

    1969-01-01

    This Guide is intended to provide general information and guidance to reactor owners or operators, inspection authorities, certifying authorities or regulatory bodies who are responsible for establishing inspection procedures for specific reactors or reactor types, and for the preparation of national codes or standards. The recommendations of the Guide apply primarily to water-cooled steel reactor vessels which are at a sufficiently early stage of design so that recommendations to provide accessibility for inspection can be incorporated into the early stages of design and inspection planning. However, much of the contents of the Guide are also applicable in part to vessels for other reactor types, such as gas-cooled, pressure-tube, or liquid-metal-cooled reactors, and also to some existing water-cooled reactors and reactors which are in advanced stage of design or construction. 46 refs, figs, 1 tab

  5. Pressure vessel inspection criteria based on fitness-for-purpose assessment

    International Nuclear Information System (INIS)

    Grover, J.L.; Cipolla, R.C.

    1985-01-01

    The paper on pressure vessel inspection investigates the methodology required to establish an inspection strategy consistent with fracture mechanics analysis, i.e. to define allowable flaw sizes based on location within the vessel. The methodology is demonstrated using a sample problem for a typical pressurised water reactor pressure vessel, and shows the impact of certain assumptions on the inspection strategy. The results indicate that the flaw size varies with the shape of the assumed residual stress field and the through-thickness location. Also in general, the fracture mechanics evaluation allows flaws much larger than are allowed by the inspection acceptance criteria. (UK)

  6. Factors to consider when planning a pipeline inspection: making an informed best choice

    Energy Technology Data Exchange (ETDEWEB)

    Scott, Ben [GE Oil and Gas, PII Pipeline Solutions, Cramlington Northumberland (United Kingdom)

    2009-07-01

    When managing pipeline integrity, the quality of inspection information is critical to determining the true condition of the pipeline, and predicting its future condition over time. The cost of a pipeline failure is nearly always much more than the cost of using a quality inspection service to obtain accurate information on the condition of the line. With pressure to reduce costs for all services, the focus often falls on the two most visible areas, tool selection and short-term service cost. These are important factors, but what is equally important is the quality and reliability of the data obtained and its effect on pipeline integrity. Without reliable data our information on pipeline condition is uncertain at best. These issues of data quality are often not well understood since many specialist technical factors are involved. This paper highlights some of the issues that need to be considered so that their importance and the effort that goes into them can be appreciated better. At the end of the day, the prime requirement is a safe, accurate and reliable inspection, delivering a good specification over a wide range of pipeline conditions and flow velocities. (author)

  7. Good clinical practice regulatory inspections: Lessons for Indian investigator sites

    Directory of Open Access Journals (Sweden)

    R Marwah

    2010-01-01

    Full Text Available Regulatory inspections are important to evaluate the integrity of the data submitted to health authorities (HAs, protect patient safety, and assess adequacy of site/sponsor quality systems to achieve the same. Inspections generally occur after submission of data for marketing approval of an investigational drug. In recent years, there has been a significant increase in number of inspections by different HAs, including in India. The assessors/inspectors generally do a thorough review of site data before inspections. All aspects of ICH-GCP, site infrastructure, and quality control systems are assessed during the inspection. Findings are discussed during the close out meeting and a detailed inspection report issued afterward, which has to be responded to within 15-30 days with effective Corrective and Preventive Action Plan (CAPA. Protocol noncompliance, inadequate/inaccurate records, inadequate drug accountability, informed consent issues, and adverse event reporting were some of the most common findings observed during recent Food and Drug Administration (FDA inspections. Drug development is being increasingly globalized and an increased number of patients enrolled in studies submitted as part of applications come from all over the world including India. Because of the steep increase in research activity in the country, inexperienced sites, and more stakeholders, increased efforts will be required to ensure continuous quality and compliance. HAs have also made clear that enforcement will be increased and be swift, aggressive, and effective.

  8. Tank 241-B-203 push mode core sampling and analysis plan. Revision 1

    International Nuclear Information System (INIS)

    Jo, J.

    1995-01-01

    This Sampling and Analysis Plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for two push-mode core samples from tank 241-B-203 (B-203)

  9. Tank 241-B-204 push mode core sampling and analysis plan. Revision 1

    International Nuclear Information System (INIS)

    Sasaki, L.M.

    1995-01-01

    This Sampling and Analysis Plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for two push-mode core samples from tank 241-B-204 (B-204)

  10. Pathology Residents Comprise Inspection Team for a CAP Self-Inspection

    Directory of Open Access Journals (Sweden)

    Stacy G. Beal MD

    2017-03-01

    Full Text Available We report our experience at the University of Florida in which residents and fellows served as the inspection team for a College of American Pathologists (CAP self-inspection. We aimed to determine whether the CAP self-inspection could serve as a learning opportunity for pathology residents and fellows. To prepare for the inspection, we provided a series of 4 lunchtime seminars covering numerous laboratory management topics relating to inspections and laboratory quality. Preparation for the inspection began approximately 4 months prior to the date of the inspection. The intent was to simulate a CAP peer inspection, with the exception that the date was announced. The associate residency program director served as the team leader. All residents and fellows completed inspector training provided by CAP, and the team leader completed the team leader training. A 20 question pre- and posttest was administered; additionally, an anonymous survey was given after the inspection. The residents’ and fellows’ posttest scores were an average of 15% higher than on the pretest ( P < .01. The surveys as well as subjective comments were overwhelmingly positive. In conclusion, the resident’s and fellow’s experience as an inspector during a CAP self-inspection was a useful tool to learn accreditation and laboratory management.

  11. Test plan for surface and subsurface examinations of K-east and K-west fuel elements

    International Nuclear Information System (INIS)

    Pitner, A.L.

    1997-01-01

    The test plan for subsurface examinations on damaged K East and K West Basin fuel elements is presented. The purpose of these examinations is to inspect damaged areas on the fuel elements for the presence of voids, sludge, or broken fuel, and to obtain samples from the damaged areas for subsequent characterization tests

  12. Test plan for K Basin Sludge Canister and Floor Sampling Device

    International Nuclear Information System (INIS)

    Meling, T.A.

    1995-01-01

    This document provides the test plan and procedure forms for conducting the functional and operational acceptance testing of the K Basin Sludge Canister and Floor Sampling Device(s). These samplers samples sludge off the floor of the 100K Basins and out of 100K fuel storage canisters

  13. Efficient sampling algorithms for Monte Carlo based treatment planning

    International Nuclear Information System (INIS)

    DeMarco, J.J.; Solberg, T.D.; Chetty, I.; Smathers, J.B.

    1998-01-01

    Efficient sampling algorithms are necessary for producing a fast Monte Carlo based treatment planning code. This study evaluates several aspects of a photon-based tracking scheme and the effect of optimal sampling algorithms on the efficiency of the code. Four areas were tested: pseudo-random number generation, generalized sampling of a discrete distribution, sampling from the exponential distribution, and delta scattering as applied to photon transport through a heterogeneous simulation geometry. Generalized sampling of a discrete distribution using the cutpoint method can produce speedup gains of one order of magnitude versus conventional sequential sampling. Photon transport modifications based upon the delta scattering method were implemented and compared with a conventional boundary and collision checking algorithm. The delta scattering algorithm is faster by a factor of six versus the conventional algorithm for a boundary size of 5 mm within a heterogeneous geometry. A comparison of portable pseudo-random number algorithms and exponential sampling techniques is also discussed

  14. Multi-Canister overpack inservice inspection and maintenance

    International Nuclear Information System (INIS)

    SMITH, K.E.

    1998-01-01

    The factors to be considered in establishing inservice inspection and maintenance requirements for the Multi-Canister Overpack (MCO) include evaluating the likelihood of degradation to the MCO pressure boundary due to erosion and corrosion, reviewing commercial practice for NRC licensed spent nuclear fuel storage systems, and examining the individual MCO components for maintenance needs. Reviews of the potential for MCO erosion and corrosion conclude that neither will pose a threat to the MCO pressure boundary. Consistent with commercial practice for spent fuel storage systems, the MCO closure weld will be helium leak tested prior to placement in interim storage. Beyond the CSB facility related monitoring plans (radiological monitoring, emissions monitoring, vault cooling data, etc.), no inservice inspection or maintenance of the MCO is required during interim storage

  15. Reactive inspection response of NRC Region III to potential technical deficiencies identified in recent Nuclear Air Cleaning Conference papers

    International Nuclear Information System (INIS)

    Gill, C.F.

    1987-01-01

    In order to effectively meet its responsibility to protect the public health and safety, the Nuclear Regulatory Commission (NRC) nuclear power plant licensing and inspection programs respond to potential technical deficiencies identified by conference and professional society meeting papers when deemed appropriate. The NRC staff's response mechanisms for such technical deficiencies include: generic letters, Bulletins, Information Notices, Standard Review Plan (NUREG-0800) revisions, docketed Final Safety Analysis Report (FSAR) questions, special studies, special (reactive) inspection, and inspection program revisions. This paper describes reactive inspection efforts by Region III in response to potential technical deficiencies identified in recent air cleaning conference papers, including: post-accident effluent sample line deposition losses; failure to implement good engineering practices in the design, construction, and testing of Nuclear Air Treatment Systems (NATS); filter bypass via filter housing drain lines; spinster carbon degradation; use of silicone sealants and other temporary patching material in NATS; filter housing fire protection deluge system problems; lack of charcoal batch traceability; Quality Assurance records problems involving equipment, vendor, filter, and personnel qualifications; inadequate ANSI/ASME N510 acceptance criteria and tests; and failure to adequately demonstrate control room habitability per 10 CFR 50, Appendix A, General Design Criterion-19. Region III inspections indicate that many of these deficiencies appear to be prevalent. Inspection findings and utility responses to the findings are discussed. NRC Region III and Headquarters programmatic reactions to the identified generic problem areas are also discussed

  16. Tank 241-TX-113 rotary mode core sampling and analysis plan

    International Nuclear Information System (INIS)

    McCain, D.J.

    1998-01-01

    This sampling and analysis plan (SAP) identities characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for push mode core samples from tank 241-TX-113 (TX-113). The Tank Characterization Technical Sampling Basis document identities Retrieval, Pretreatment and Immobilization as an issue that applies to tank TX-113. As a result, a 150 gram composite of solids shall be made and archived for that program. This tank is not on a Watch List

  17. Gas and liquid sampling for closed canisters in KW Basin - Work Plan

    International Nuclear Information System (INIS)

    Pitkoff, C.C.

    1995-01-01

    Work Plan for the design and fabrication of gas/liquid sampler for closed canister sampling in KW Basin. This document defines the tasks associated with the design, fabrication, assembly, and acceptance testing equipment necessary for gas and liquid sampling of the Mark I and Mark II canisters in the K-West basin. The sampling of the gas space and the remaining liquid inside the closed canisters will be used to help understand any changes to the fuel elements and the canisters. Specifically, this work plan will define the scope of work and required task structure, list the technical requirements, describe design configuration control and verification methodologies, detail quality assurance requirements, and present a baseline estimate and schedule

  18. A preventive maintenance model with a two-level inspection policy based on a three-stage failure process

    International Nuclear Information System (INIS)

    Wang, Wenbin; Zhao, Fei; Peng, Rui

    2014-01-01

    Inspection is always an important preventive maintenance (PM) activity and can have different depths and cover all or part of plant systems. This paper introduces a two-level inspection policy model for a single component plant system based on a three-stage failure process. Such a failure process divides the system′s life into three stages: good, minor defective and severe defective stages. The first level of inspection, the minor inspection, can only identify the minor defective stage with a certain probability, but can always reveal the severe defective stage. The major inspection can however identify both defective stages perfectly. Once the system is found to be in the minor defective stage, a shortened inspection interval is adopted. If however the system is found to be in the severe defective stage, we may delay the maintenance action if the time to the next planned PM window is less than a threshold level, but otherwise, replace immediately. This corresponds to the well adopted maintenance policy in practice such as periodic inspections with planned PMs. A numerical example is presented to demonstrate the proposed model by comparing with other models. - Highlights: • The system′s deterioration goes through a three-stage process, namely, normal, minor defective and severe defective. • Two levels of inspections are proposed, e.g., minor and major inspections. • Once the minor defective stage is found, instead of taking a maintenance action, a shortened inspection interval is recommended. • When the severe defective stage is found, we delay the maintenance according to the threshold to the next PM. • The decision variables are the inspection intervals and the threshold to PM

  19. Ultrasonic inspection

    International Nuclear Information System (INIS)

    Satittada, Gannaga

    1984-01-01

    Ultrasonic inspection is one of the most widely used methods for nondestructive inspection. The beam of high-frequency sound wave, ultrasonic wave, is introduced into the material. It travels through the material with some attendant loss of energy and can be reflected at interfaces. The reflected beam is detected and analyzed. Ultrasonic inspection is used to detect flaws in metal parts as well as in welded, brazed and bonded joints during research work and developing production and service. It is also used to detect and locate porosity, pipe, and flakes. In addition, it can be used for the measurement of metal thickness. Ultrasonic inspection is therefore used for quality control and material inspection in all major industries

  20. SmartInspect: Smart Contract Inspection Technical Report

    OpenAIRE

    Bragagnolo , Santiago; Rocha , Henrique ,; Denker , Marcus; Ducasse , Stéphane

    2017-01-01

    Smart contracts are embedded procedures stored with the data they act upon. Debugging deployed Smart Contracts is a difficult task since once deployed, the code cannot be reexecuted and inspecting a simple attribute is not easily possible because data is encoded. In this technical report, we present SmartInspect to address the lack of inspectability of a deployed contract. Our solution analyses the contract state by using decompilation techniques and a mirror-based architecture to represent t...

  1. Tank 241-AY-101 Privatization Push Mode Core Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    TEMPLETON, A.M.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AY-101. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AY-101 required to satisfy ''Data Quality Objectives For RPP Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For High-Level Waste Feed Batch X(HLW DQO)' (Nguyen 1999a), ''Data Quality Objectives For TWRS Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For Low-Activity Waste Feed Butch X (LAW DQO) (Nguyen 1999b)'', ''Low Activity Waste and High-Level Waste Feed Data Quality Objectives (L and H DQO)'' (Patello et al. 1999), and ''Characterization Data Needs for Development, Design, and Operation of Retrieval Equipment Developed through the Data Quality Objective Process (Equipment DQO)'' (Bloom 1996). Special instructions regarding support to the LAW and HLW DQOs are provided by Baldwin (1999). Push mode core samples will be obtained from risers 15G and 150 to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples; composite the liquids and solids; perform chemical analyses on composite and segment samples; archive half-segment samples; and provide sub-samples to the Process Chemistry Laboratory. The Process Chemistry Laboratory will prepare test plans and perform process tests to evaluate the behavior of the 241-AY-101 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. Requirements for analyses of samples originating in the process tests will be documented in the corresponding test plans and are not within the scope of this SAP

  2. Audit and Evaluation Plan FY 2002

    National Research Council Canada - National Science Library

    2002-01-01

    .... These projects also have been coordinated in the joint audit and inspection planning groups that address coverage in each major functional area. The plan also includes audit policy and oversight projects planned to start in FY 2002; however, intelligence coverage will be addressed separately.

  3. Development of a two-stage inspection process for the assessment of deteriorating infrastructure

    International Nuclear Information System (INIS)

    Sheils, Emma; O'Connor, Alan; Breysse, Denys; Schoefs, Franck; Yotte, Sylvie

    2010-01-01

    Inspection-based maintenance strategies can provide an efficient tool for the management of ageing infrastructure subjected to deterioration. Many of these methods rely on quantitative data from inspections, rather than qualitative and subjective data. The focus of this paper is on the development of an inspection-based decision scheme, incorporating analysis on the effect of the cost and quality of NDT tools to assess the condition of infrastructure elements/networks during their lifetime. For the first time the two aspects of an inspection are considered, i.e. detection and sizing. Since each stage of an inspection is carried out for a distinct purpose, different parameters are used to represent each procedure and both have been incorporated into a maintenance management model. The separation of these procedures allows the interaction between the two inspection techniques to be studied. The inspection for detection process acts as a screening exercise to determine which defects require further inspection for sizing. A decision tool is developed that allows the owner/manager of the infrastructural element/network to choose the most cost-efficient maintenance management plan based on his/her specific requirements.

  4. Risk-based inspection and maintenance systems for steam turbines

    International Nuclear Information System (INIS)

    Fujiyama, Kazunari; Nagai, Satoshi; Akikuni, Yasunari; Fujiwara, Toshihiro; Furuya, Kenichiro; Matsumoto, Shigeru; Takagi, Kentaro; Kawabata, Taro

    2004-01-01

    The risk-based maintenance (RBM) system has been developed for steam turbine plants coupled with the quick inspection systems. The RBM system utilizes the field failure and inspection database accumulated over 30 years. The failure modes are determined for each component of steam turbines and the failure scenarios are described as event trees. The probability of failure is expressed in the form of unreliability functions of operation hours or start-up cycles through the cumulative hazard function method. The posterior unreliability is derived from the field data analysis according to the inspection information. Quick inspection can be conducted using air-cooled borescope and heat resistant ultrasonic sensors even if the turbine is not cooled down sufficiently. Another inspection information comes from degradation and damage measurement. The probabilistic life assessment using structural analysis and statistical material properties, the latter is estimated from hardness measurement, replica observation and embrittlement measurement. The risk function is calculated as the sum product of unreliability functions and expected monetary loss as the consequence of failure along event trees. The optimum maintenance plan is determined among simulated scenarios described through component breakdown trees, life cycle event trees and risk functions. Those methods are effective for total condition assessment and economical maintenance for operating plants

  5. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2007

    International Nuclear Information System (INIS)

    NSTec Environmental Restoration

    2008-01-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2007 and includes inspection and repair activities completed at the following nine CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 404: Roller Coaster Lagoons and Trench (TTR); (3) CAU 407: Roller Coaster RadSafe Area (TTR); (4) CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); (5) CAU 424: Area 3 Landfill Complexes (TTR); (6) CAU 426: Cactus Spring Waste Trenches (TTR); (7) CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); (8) CAU 453: Area 9 UXO Landfill (TTR); and (9) CAU 487: Thunderwell Site (TTR). In a letter from the Nevada Division of Environmental Protection (NDEP) dated December 5, 2006, NDEP concurred with the request to reduce the frequency of post-closure inspections of CAUs at TTR to an annual frequency. This letter is included in Attachment B. Post-closure inspections were conducted on May 15-16, 2007. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in May 2007, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 453. Animal burrows observed during the annual inspection at CAU 453 were backfilled on August 1, 2007. At this time, the TTR post-closure site inspections should continue as

  6. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2007

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2008-06-01

    This report provides the results of the semiannual post-closure inspections conducted at the closed Corrective Action Unit (CAU) sites located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2007 and includes inspection and repair activities completed at the following nine CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 404: Roller Coaster Lagoons and Trench (TTR); (3) CAU 407: Roller Coaster RadSafe Area (TTR); (4) CAU 423: Area 3 Underground Discharge Point, Building 0360 (TTR); (5) CAU 424: Area 3 Landfill Complexes (TTR); (6) CAU 426: Cactus Spring Waste Trenches (TTR); (7) CAU 427: Area 3 Septic Waste Systems 2, 6 (TTR); (8) CAU 453: Area 9 UXO Landfill (TTR); and (9) CAU 487: Thunderwell Site (TTR). In a letter from the Nevada Division of Environmental Protection (NDEP) dated December 5, 2006, NDEP concurred with the request to reduce the frequency of post-closure inspections of CAUs at TTR to an annual frequency. This letter is included in Attachment B. Post-closure inspections were conducted on May 15-16, 2007. All inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Attachment B, with the exception of CAU 400. CAU 400 does not require post-closure inspections, but inspections of the vegetation and fencing are conducted as a best management practice. The inspection checklists for each site inspection are included in Attachment C, the field notes are included in Attachment D, and the site photographs are included in Attachment E. Vegetation monitoring of CAU 400, CAU 404, CAU 407, and CAU 426 was performed in May 2007, and the vegetation monitoring report is included in Attachment F. Maintenance and/or repairs were performed at CAU 453. Animal burrows observed during the annual inspection at CAU 453 were backfilled on August 1, 2007. At this time, the TTR post-closure site inspections should continue as

  7. Receipt and Inspection of Chemical - Biological (CB) Materiel

    Science.gov (United States)

    2017-08-31

    TOP provides guidance on how to plan and conduct receipt inspection. The TOP provides specific procedures and data collection sheets . 15. SUBJECT...Unclassified Unclassified Unclassified 19b. TELEPHONE NUMBER (include area code ) Standard Form 298 (Rev. 8-98) Prescribed by ANSI Std. Z39-18...10 APPENDIX A. DATA COLLECTION SHEET ............................................ A-1 B. ABBREVIATIONS

  8. 7 CFR 52.35 - Accessibility for sampling.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 2 2010-01-01 2010-01-01 false Accessibility for sampling. 52.35 Section 52.35... PROCESSED FOOD PRODUCTS 1 Regulations Governing Inspection and Certification Sampling § 52.35 Accessibility for sampling. Each applicant shall cause the processed products for which inspection is requested to...

  9. 7 CFR 29.110 - Method of sampling.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 2 2010-01-01 2010-01-01 false Method of sampling. 29.110 Section 29.110 Agriculture Regulations of the Department of Agriculture AGRICULTURAL MARKETING SERVICE (Standards, Inspections, Marketing... INSPECTION Regulations Inspectors, Samplers, and Weighers § 29.110 Method of sampling. In sampling tobacco...

  10. Monitoring Well Installation and Groundwater Sampling and Analysis Plan at the USARC Training Reserve, 84th Division, Milwaukee, Wisconsin

    Science.gov (United States)

    1988-11-01

    paint chips at the sampling site. 0 Clean water tanks, pumps, mud pans, hoses, including hoses and tanks used to transfer water from source to drill rig...TO’ LCA , Filll I F’APCr,;I~- € C/ " rKL2PIrlA , ATTFNrIGN TO SMOKING. ALCOHOLF MFDrICATIONP AND FXPOSI.RE TO CARCINOGENS.1 ENERAL MEDICAl. HISTORY...A. General: 1. Place samples in core trough for visual inspection. After logging, place selected samples in sample jars or wood core boxes. 2. Seal

  11. THE NUCLEAR MATERIAL MEASUREMENT PROGRAM PLAN FOR GOSATOMNADZOR OF RUSSIA

    International Nuclear Information System (INIS)

    Bokov, Dmitry; Byers, Kenneth R.

    2003-01-01

    As the Russian State regulatory agency responsible for oversight of nuclear material control and accounting (MC and A), Gosatomnadzor of Russia determines the status of the MC and A programs at Russian facilites by testing the nuclear material inventory for accounting record accuracy. Currently, Gosatomnadzor is developing and implementing an approach to planning and conducting MC and A inspections using non-destructive assay (NDA) instruments that will provide for consistent application of MC and A measurement inspection objectives throughtout Russia. This Gosatomnadzor NDA Program Plan documents current NDA measurement capability in all regions of Gosatomnadzor; provides justification for upgrades to equipment, procedures and training; and defines the inspector-facility operator interface as it relates to NDA measurement equipment use. This plan covers a three-year measurement program cycle, but will be reviewed and updated annually to ensure that adequate inspection resources are available to meet the demands of the inspection schedule. This paper presents the elements of this plan and describes the process by which Gosatomnadzor ensures that its NDA instruments are effectively utilized, procedures are developed and certified, and inspection personnel are properly trained to provide assurance that Russian nuclear facilities are in compliance with Russian MC and A regulations.

  12. UMTRA project water sampling and analysis plan, Falls City, Texas. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    Planned, routine ground water sampling activities at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site near Falls City, Texas, are described in this water sampling and analysis plan (WSAP). The following plan identifies and justifies the sampling locations, analytical parameters, and sampling frequency for the routine monitoring stations at the site. The ground water data are used for site characterization and risk assessment. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US Environmental Protection Agency (EPA) regulations in 40 CFR Part 192. Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site. The Falls City site is in Karnes County, Texas, approximately 8 miles [13 kilometers southwest of the town of Falls City and 46 mi (74 km) southeast of San Antonio, Texas. Before surface remedial action, the tailings site consisted of two parcels. Parcel A consisted of the mill site, one mill building, five tailings piles, and one tailings pond south of Farm-to-Market (FM) Road 1344 and west of FM 791. A sixth tailings pile designated Parcel B was north of FM 791 and east of FM 1344

  13. Inspection vehicle

    International Nuclear Information System (INIS)

    Takahashi, Masaki; Omote, Tatsuyuki; Yoneya, Yutaka; Tanaka, Keiji; Waki, Tetsuro; Yoshida, Tomiji; Kido, Tsuyoshi.

    1993-01-01

    An inspection vehicle comprises a small-sized battery directly connected with a power motor or a direct power source from trolly lines and a switching circuit operated by external signals. The switch judges advance or retreat by two kinds of signals and the inspection vehicle is recovered by self-running. In order to recover the abnormally stopped inspection vehicle to the targeted place, the inspection vehicle is made in a free-running state by using a clutch mechanism and is pushed by an other vehicle. (T.M.)

  14. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2011

    International Nuclear Information System (INIS)

    2012-01-01

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2011 and includes inspection and repair activities completed at the following CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 407: Roller Coaster RadSafe Area (TTR); (3) CAU 424: Area 3 Landfill Complexes (TTR); (4) CAU 453: Area 9 UXO Landfill (TTR); and (5) CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Appendix B. The inspection checklists are included in Appendix C, field notes are included in Appendix D, and photographs taken during inspections are included in Appendix E. The annual post-closure inspections were conducted May 3 and 4, 2011. Maintenance was performed at CAU 424, CAU 453, and CAU 487. At CAU 424, two surface grade monuments at Landfill Cell A3-3 could not be located during the inspection. The two monuments were located and marked with lava rock on July 13, 2011. At CAU 453, there was evidence of animal burrowing. Animal burrows were backfilled on July 13, 2011. At CAU 487, one use restriction warning sign was missing, and wording was faded on the remaining signs. A large animal burrow was also present. The signs were replaced, and the animal burrow was backfilled on July 12, 2011. As a best management practice, the use restriction warning signs at CAU 407 were replaced with standard Federal Facility Agreement and Consent Order signs on July 13, 2011. Vegetation monitoring was performed at the CAU 400 Five Points Landfill and CAU 407 in June 2011, and the vegetation monitoring report is included in Appendix F.

  15. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, For Calendar Year 2011

    Energy Technology Data Exchange (ETDEWEB)

    NSTec Environmental Restoration

    2012-02-21

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2011 and includes inspection and repair activities completed at the following CAUs: (1) CAU 400: Bomblet Pit and Five Points Landfill (TTR); (2) CAU 407: Roller Coaster RadSafe Area (TTR); (3) CAU 424: Area 3 Landfill Complexes (TTR); (4) CAU 453: Area 9 UXO Landfill (TTR); and (5) CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved Closure Reports. The post-closure inspection plan for each CAU is included in Appendix B. The inspection checklists are included in Appendix C, field notes are included in Appendix D, and photographs taken during inspections are included in Appendix E. The annual post-closure inspections were conducted May 3 and 4, 2011. Maintenance was performed at CAU 424, CAU 453, and CAU 487. At CAU 424, two surface grade monuments at Landfill Cell A3-3 could not be located during the inspection. The two monuments were located and marked with lava rock on July 13, 2011. At CAU 453, there was evidence of animal burrowing. Animal burrows were backfilled on July 13, 2011. At CAU 487, one use restriction warning sign was missing, and wording was faded on the remaining signs. A large animal burrow was also present. The signs were replaced, and the animal burrow was backfilled on July 12, 2011. As a best management practice, the use restriction warning signs at CAU 407 were replaced with standard Federal Facility Agreement and Consent Order signs on July 13, 2011. Vegetation monitoring was performed at the CAU 400 Five Points Landfill and CAU 407 in June 2011, and the vegetation monitoring report is included in Appendix F.

  16. Pre-service inspection and in-service inspection in Japan

    International Nuclear Information System (INIS)

    Uebayashi, T.; Miyake, Y.

    1985-01-01

    To ensure the safety of nuclear power plant, pre-service inspection/in-service inspection (PSI/ISI) has an important role, and informations obtained from various inspections during plant shut-down period are contributing to establish effective preventive maintenance activities for plant facilities. It might be said that the high level of availability of Japanese light-water nuclear power plants in these two or three years has been achieved by those efforts. In case of Japan, inspections to be carried out during scheduled plant shut-down period are not limited to code requirements but include many other inspections which are mostly reflected from troubles experienced in both domestic and overseas plants. Usually, those additional inspections are performed by Ministry of Trade and Industries' (MITI's) regulator and/or tentative requirement and considered as ISI in broad meaning. To achieve high availability of plant, it is essential to avoid unscheduled shut-down and to shorten inspection period. The developments of new technology to perform effective ISI for operating plants are continued, but on the other hand it is also very important to pay a great consideration to inspectability of the plants at the stage of plant engineering. With the leadership of MITI, improvement and standardization of light-water nuclear power plant has been proceeded and newly constructed plants have great advantage from the point of view on ISI

  17. Tank 241-AY-101 Privatization Push Mode Core Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    TEMPLETON, A.M.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AY-101. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AY-101 required to satisfy Data Quality Objectives For RPP Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For High-Level Waste Feed Batch X(HLW DQO) (Nguyen 1999a), Data Quality Objectives For TWRS Privatization Phase I : Confirm Tank T Is An Appropriate Feed Source For Low-Activity Waste Feed Batch X (LAW DQO) (Nguyen 1999b), Low Activity Waste and High-Level Waste Feed Data Quality Objectives (L and H DQO) (Patello et al. 1999), and Characterization Data Needs for Development, Design, and Operation of Retrieval Equipment Developed through the Data Quality Objective Process (Equipment DQO) (Bloom 1996). Special instructions regarding support to the LAW and HLW DQOs are provided by Baldwin (1999). Push mode core samples will be obtained from risers 15G and 150 to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples; composite the liquids and solids; perform chemical analyses on composite and segment samples; archive half-segment samples; and provide subsamples to the Process Chemistry Laboratory. The Process Chemistry Laboratory will prepare test plans and perform process tests to evaluate the behavior of the 241-AY-101 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. Requirements for analyses of samples originating in the process tests will be documented in the corresponding test plans and are not within the scope of this SAP

  18. Post-Closure Inspection Report for the Tonopah Test Range, Nevada, for Calendar Year 2013

    Energy Technology Data Exchange (ETDEWEB)

    Silvas, A. J.

    2014-03-03

    This report provides the results of the annual post-closure inspections conducted at the closed Corrective Action Units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2013 and includes inspection and repair activities completed at the following CAUs: • CAU 400: Bomblet Pit and Five Points Landfill (TTR) • CAU 407: Roller Coaster RadSafe Area (TTR) • CAU 424: Area 3 Landfill Complexes (TTR) • CAU 453: Area 9 UXO Landfill (TTR) • CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved Closure Reports and subsequent correspondence with the Nevada Division of Environmental Protection. The post-closure inspection plans and subsequent correspondence modifying the requirements for each CAU are included in Appendix B. The inspection checklists are included in Appendix C. Field notes are included in Appendix D. Photographs taken during inspections are included in Appendix E. The annual post-closure inspections were conducted on May 14, 2013. Maintenance was performed at CAU 400, CAU 424, and CAU 453. At CAU 400, animal burrows were backfilled. At CAU 424, erosion repairs were completed at Landfill Cell A3-3, subsidence was repaired at Landfill Cell A3-4, and additional lava rock was placed in high-traffic areas to mark the locations of the surface grade monuments at Landfill Cell A3-3 and Landfill Cell A3-8. At CAU 453, two areas of subsidence were repaired and animal burrows were backfilled. Vegetation monitoring was performed at the CAU 400 Five Points Landfill and CAU 407 in June 2013. The vegetation monitoring report is included in Appendix F.

  19. Supplement to the UMTRA Project water sampling and analysis plan, Mexican Hat, Utah

    International Nuclear Information System (INIS)

    1995-09-01

    This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Mexican Hat, Utah, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Mexican Hat (DOE, 1994). Further, the supplement serves to confirm our present understanding of the site relative to the hydrogeology and contaminant distribution as well as our intention to continue to use the sampling strategy as presented in the 1994 WSAP document for Mexican Hat. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 (1991) and 60 FR 2854 (1995). Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Mexican Hat site are the Mexican Hat Long-Term Surveillance Plan (currently in progress), and the Mexican Hat Site Observational Work Plan (currently in progress)

  20. The Toggle Local Planner for sampling-based motion planning

    KAUST Repository

    Denny, Jory

    2012-05-01

    Sampling-based solutions to the motion planning problem, such as the probabilistic roadmap method (PRM), have become commonplace in robotics applications. These solutions are the norm as the dimensionality of the planning space grows, i.e., d > 5. An important primitive of these methods is the local planner, which is used for validation of simple paths between two configurations. The most common is the straight-line local planner which interpolates along the straight line between the two configurations. In this paper, we introduce a new local planner, Toggle Local Planner (Toggle LP), which extends local planning to a two-dimensional subspace of the overall planning space. If no path exists between the two configurations in the subspace, then Toggle LP is guaranteed to correctly return false. Intuitively, more connections could be found by Toggle LP than by the straight-line planner, resulting in better connected roadmaps. As shown in our results, this is the case, and additionally, the extra cost, in terms of time or storage, for Toggle LP is minimal. Additionally, our experimental analysis of the planner shows the benefit for a wide array of robots, with DOF as high as 70. © 2012 IEEE.

  1. Implementation of Mass Spectrometry for Bulk Analysis of Environmental and Nuclear Material Inspection Samples

    International Nuclear Information System (INIS)

    Bulyha, S.; Cunningham, A.; Koepf, A.; Macsik, Z.; Poths, J.

    2015-01-01

    In the frame of the ECAS project (Enhancing Capabilities of Safeguards Analytical Services) the IAEA Office of Safeguards Analytical Services has implemented the latest-generation inductively coupled plasma mass spectrometers, or ICP-MS, for (i) bulk analysis of uranium and plutonium isotopes in environmental inspection samples and (ii) impurity analyzes in uranium samples. The measurement accuracy for n(U-235)/ n(U-238) ratios has been improved by approximately five times with the new multi-collector ICP-MS equipment. Use of modern ICP-MS enabled also an improvement of instrumental detection limits for U-233 and U-236 and Pu isotopes by at least one order of magnitude in comparison to the values, which had been achieved with the previously used methods. The improved accuracy and precision for isotope ratio measurements is mainly due to the higher sensitivity and the possibility to simultaneously detect several U isotopes with a multi-collector detector block. Implementation of the ICP-MS has also demonstrated a possibility for an increased sample throughput. In parallel to the implementation of the ICP-MS, a new version of the ''modified total evaporation'' (MTE) method has been developed for isotopic analysis of uranium samples by multi-collector thermal ionization mass spectrometry (TIMS). The MTE method provides a measurement performance which is, in particular for minor uranium isotopes, by several orders of magnitude superior compared to the commonly used ''total evaporation'' method. The new mass spectrometric techniques significantly improve the capability of the IAEA safeguards laboratories to detect the presence of non-natural uranium and plutonium isotopes in environmental swipe samples and to identify previously imperceptible differences in nuclear ''signatures''. Thus, they enhance the IAEA's ability to obtain independent, timely and quality-assured safeguards-relevant data and ensure

  2. Inspection by docking of nuclear-powered ship 'Mutsu'

    International Nuclear Information System (INIS)

    1989-01-01

    Japan Atomic Energy Research Institute carried out the docking and inspection of the nuclear-powered ship 'Mutsu' at Sekinehama Port, Mutsu City, Aomori Prefecture, from the middle of June to late in July, 1989. In this inspection, the Mutsu was mounted on a floating dock off the coast, the dock was towed by tugboats into the port and moored at the pier, and after completing the works in the dock, the dock was towed to the outside of the port, and the Mutsu was launched. The Mutsu was built as a nuclear power experiment ship, and length 130 m, breadth 19 m, depth 13.2 m, design draft at full load 6.9 m, 8242 GT. One PWR of 36 MWt and one steam turbine of 10000 ps are installed, and velocity is 16.5 knots. In September, 1974, after the first criticality, the leak of radioactivity occurred. The repair of shield and general inspection on safety were carried out in Sasebo Shipyard from August, 1980 to August, 1982. Thereafter, the Mutsu stayed in Ominato, but in January, 1988, after the completion of Sekinehama Port, the Mutsu was brought there. The Sekinehama Port, the test and inspection of the Mutsu carried out so far and the plan of hereafter are reported. (K.I.)

  3. Gas liquid sampling for closed canisters in KW Basin - test plan

    International Nuclear Information System (INIS)

    Pitkoff, C.C.

    1995-01-01

    Test procedures for the gas/liquid sampler. Characterization of the Spent Nuclear Fuel, SNF, sealed in canisters at KW-Basin is needed to determine the state of storing SNF wet. Samples of the liquid and the gas in the closed canisters will be taken to gain characterization information. Sampling equipment has been designed to retrieve gas and liquid from the closed canisters in KW basin. This plan is written to outline the test requirements for this developmental sampling equipment

  4. Project Specific Quality Assurance Plan

    International Nuclear Information System (INIS)

    Pedersen, K.S.

    1995-01-01

    This Quality Assurance Project Plan (QAPP) identifies the Westinghouse Hanford Co. (WHC) Quality Assurance (QA) program requirements for all contractors involved in the planning and execution of the design, construction, testing and inspection of the 200 Area Effluent BAT/AKART Implementation, Project W-291

  5. Development of in-service inspection system for core support graphite structures in the high temperature engineering test reactor (HTTR)

    Energy Technology Data Exchange (ETDEWEB)

    Sumita, Junya; Hanawa, Satoshi; Kikuchi, Takayuki; Ishihara, Masahiro [Japan Atomic Energy Research Inst., Oarai, Ibaraki (Japan). Oarai Research Establishment

    2003-03-01

    Visual inspection of core support graphite structures using TV camera as in-service inspection and measurement of material characteristics using surveillance test specimens are planned in the High Temperature Engineering Test Reactor (HTTR) to confirm structural integrity of the core support graphite structures. For the visual inspection, in-service inspection system developed from September 1996 to June 1998, and pre-service inspection using the system was carried out. As the result of the pre-service inspection, it was validated that high quality of visual inspection with TV camera can be carried out, and also structural integrity of the core support graphite structures at the initial stage of the HTTR operation was confirmed. (author)

  6. 49 CFR 234.201 - Location of plans.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 4 2010-10-01 2010-10-01 false Location of plans. 234.201 Section 234.201..., Inspection, and Testing Maintenance Standards § 234.201 Location of plans. Plans required for proper maintenance and testing shall be kept at each highway-rail grade crossing warning system location. Plans shall...

  7. 77 FR 58091 - Risk-Based Sampling of Beef Manufacturing Trimmings for Escherichia coli (E. coli) O157:H7 and...

    Science.gov (United States)

    2012-09-19

    ... for exposure of carcasses and parts to any contamination or food safety hazard during the removal of... DEPARTMENT OF AGRICULTURE Food Safety and Inspection Service [Docket No. FSIS-2012-0020] Risk-Based Sampling of Beef Manufacturing Trimmings for Escherichia coli (E. coli) O157:H7 and Plans for Beef...

  8. Failure-censored accelerated life test sampling plans for Weibull distribution under expected test time constraint

    International Nuclear Information System (INIS)

    Bai, D.S.; Chun, Y.R.; Kim, J.G.

    1995-01-01

    This paper considers the design of life-test sampling plans based on failure-censored accelerated life tests. The lifetime distribution of products is assumed to be Weibull with a scale parameter that is a log linear function of a (possibly transformed) stress. Two levels of stress higher than the use condition stress, high and low, are used. Sampling plans with equal expected test times at high and low test stresses which satisfy the producer's and consumer's risk requirements and minimize the asymptotic variance of the test statistic used to decide lot acceptability are obtained. The properties of the proposed life-test sampling plans are investigated

  9. Software Formal Inspections Guidebook

    Science.gov (United States)

    1993-01-01

    The Software Formal Inspections Guidebook is designed to support the inspection process of software developed by and for NASA. This document provides information on how to implement a recommended and proven method for conducting formal inspections of NASA software. This Guidebook is a companion document to NASA Standard 2202-93, Software Formal Inspections Standard, approved April 1993, which provides the rules, procedures, and specific requirements for conducting software formal inspections. Application of the Formal Inspections Standard is optional to NASA program or project management. In cases where program or project management decide to use the formal inspections method, this Guidebook provides additional information on how to establish and implement the process. The goal of the formal inspections process as documented in the above-mentioned Standard and this Guidebook is to provide a framework and model for an inspection process that will enable the detection and elimination of defects as early as possible in the software life cycle. An ancillary aspect of the formal inspection process incorporates the collection and analysis of inspection data to effect continual improvement in the inspection process and the quality of the software subjected to the process.

  10. 33 CFR 157.148 - COW system: Evidence for inspections.

    Science.gov (United States)

    2010-07-01

    ... 33 Navigation and Navigable Waters 2 2010-07-01 2010-07-01 false COW system: Evidence for... CARRYING OIL IN BULK Crude Oil Washing (COW) System on Tank Vessels Inspections § 157.148 COW system... inspector evidence that the COW system has been installed in accordance with the plans accepted under § 157...

  11. The optimal amount and allocation of of sampling effort for plant health inspection

    NARCIS (Netherlands)

    Surkov, I.; Oude Lansink, A.G.J.M.; Werf, van der W.

    2009-01-01

    Plant import inspection can prevent the introduction of exotic pests and diseases, thereby averting economic losses. We explore the optimal allocation of a fixed budget, taking into account risk differentials, and the optimal-sized budget to minimise total pest costs. A partial-equilibrium market

  12. Transuranic waste characterization sampling and analysis plan

    International Nuclear Information System (INIS)

    1994-01-01

    Los Alamos National Laboratory (the Laboratory) is located approximately 25 miles northwest of Santa Fe, New Mexico, situated on the Pajarito Plateau. Technical Area 54 (TA-54), one of the Laboratory's many technical areas, is a radioactive and hazardous waste management and disposal area located within the Laboratory's boundaries. The purpose of this transuranic waste characterization, sampling, and analysis plan (CSAP) is to provide a methodology for identifying, characterizing, and sampling approximately 25,000 containers of transuranic waste stored at Pads 1, 2, and 4, Dome 48, and the Fiberglass Reinforced Plywood Box Dome at TA-54, Area G, of the Laboratory. Transuranic waste currently stored at Area G was generated primarily from research and development activities, processing and recovery operations, and decontamination and decommissioning projects. This document was created to facilitate compliance with several regulatory requirements and program drivers that are relevant to waste management at the Laboratory, including concerns of the New Mexico Environment Department

  13. Path Planning & Measurement Registration for Robotic Structural Asset Monitoring

    OpenAIRE

    Pierce , Stephen Gareth; Macleod , Charles Norman; Dobie , Gordon; Summan , Rahul

    2014-01-01

    International audience; The move to increased levels of autonomy for robotic delivery of inspection for asset monitoring, demands a structured approach to path planning and measurement data presentation that greatly surpasses the more ad‐,hoc approach typically employed by remotely controlled, but manually driven robotic inspection vehicles. The authors describe a traditional CAD/CAM approach to motion planning (as used in machine tool operation) which has numerous benefits including the...

  14. Development of In-situation radioactivity Inspection system

    International Nuclear Information System (INIS)

    Min, Sujung; Lee, Sanghun; Kim, Miyoung; Kim, Myungjin; Lee, Unjang; Park, Jungkyun

    2015-01-01

    Many Korean people worry about radioactive contamination of Japanese and Korean marine products. Radioactive contamination of processed foodstuffs, livestock, marine products, farm products imported from Japan and fishes caught in coastal waters of Korea has become an important social issue. Radioactivity inspections of those foods are executed manually with portable measuring instruments or at labs using their samples. In consequence, there are some problem of time delay and low reliability. To protect the health of citizens from radioactivity contained in Japanese marine products imported to Korea, a system to inspect radioactivity in real time will be developed. The system is to measure the radioactivity level of farm and marine products continuously and automatically at inspection sites of an agency checking radiation of imported foodstuffs to determine radioactive contamination. Product performance assessment and tests will be conducted later. When the system develops and its commercialization begins, people's anxiety about radioactive contamination of foods after the Fukushima nuclear accident will be eased and people will be able to trust the radioactive inspection

  15. Development of In-situation radioactivity Inspection system

    Energy Technology Data Exchange (ETDEWEB)

    Min, Sujung; Lee, Sanghun; Kim, Miyoung; Kim, Myungjin; Lee, Unjang [ORIONENC Co., Seoul (Korea, Republic of); Park, Jungkyun [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    Many Korean people worry about radioactive contamination of Japanese and Korean marine products. Radioactive contamination of processed foodstuffs, livestock, marine products, farm products imported from Japan and fishes caught in coastal waters of Korea has become an important social issue. Radioactivity inspections of those foods are executed manually with portable measuring instruments or at labs using their samples. In consequence, there are some problem of time delay and low reliability. To protect the health of citizens from radioactivity contained in Japanese marine products imported to Korea, a system to inspect radioactivity in real time will be developed. The system is to measure the radioactivity level of farm and marine products continuously and automatically at inspection sites of an agency checking radiation of imported foodstuffs to determine radioactive contamination. Product performance assessment and tests will be conducted later. When the system develops and its commercialization begins, people's anxiety about radioactive contamination of foods after the Fukushima nuclear accident will be eased and people will be able to trust the radioactive inspection.

  16. Regulatory inspection of nuclear facilities and enforcement by the regulatory body. Safety guide

    International Nuclear Information System (INIS)

    2002-01-01

    The purpose of this Safety Guide is to provide recommendations for regulatory bodies on the inspection of nuclear facilities, regulatory enforcement and related matters. The objective is to provide the regulatory body with a high level of confidence that operators have the processes in place to ensure compliance and that they do comply with legal requirements, including meeting the safety objectives and requirements of the regulatory body. However, in the event of non-compliance, the regulatory body should take appropriate enforcement action. This Safety Guide covers regulatory inspection and enforcement in relation to nuclear facilities such as: enrichment and fuel manufacturing plants; nuclear power plants; other reactors such as research reactors and critical assemblies; spent fuel reprocessing plants; and facilities for radioactive waste management, such as treatment, storage and disposal facilities. This Safety Guide also covers issues relating to the decommissioning of nuclear facilities, the closure of waste disposal facilities and site rehabilitation. Section 2 sets out the objectives of regulatory inspection and enforcement. Section 3 covers the management of regulatory inspections. Section 4 covers the performance of regulatory inspections, including internal guidance, planning and preparation, methods of inspection and reports of inspections. Section 5 deals with regulatory enforcement actions. Section 6 covers the assessment of regulatory inspections and enforcement activities. The Appendix provides further details on inspection areas for nuclear facilities

  17. UMTRA project water sampling and analysis plan, Salt Lake City, Utah

    International Nuclear Information System (INIS)

    1994-06-01

    Surface remedial action was completed at the Salt Lake City, Utah, Uranium Mill Tailings Remedial Action (UMTRA) Project site in the fall of 1987. Results of water sampling for the years 1992 to 1994 indicate that site-related ground water contamination occurs in the shallow unconfined aquifer (the uppermost aquifer). With respect to background ground water quality, contaminated ground water in the shallow, unconfined aquifer has elevated levels of chloride, sodium, sulfate, total dissolved solids, and uranium. No contamination associated with the former tailings pile occurs in levels exceeding background in ground water in the deeper confined aquifer. This document provides the water sampling and analysis plan for ground water monitoring at the former uranium processing site in Salt Lake City, Utah (otherwise known as the ''Vitro'' site, named after the Vitro Chemical Company that operated the mill). All contaminated materials removed from the processing site were relocated and stabilized in a disposal cell near Clive, Utah, some 85 miles west of the Vitro site (known as the ''Clive'' disposal site). No ground water monitoring is being performed at the Clive disposal site, since concurrence of the remedial action plan by the US Nuclear Regulatory Commission and completion of the disposal cell occurred before the US Environmental Protection Agency issued draft ground water standards in 1987 (52 FR 36000) for cleanup, stabilization, and control of residual radioactive materials at the disposal site. In addition, the likelihood of post-closure impact on the ground water is minimal to nonexistent, due to the naturally poor quality of the ground water. Water sampling activities planned for calendar year 1994 consist of sampling ground water from nine monitor wells to assess the migration of contamination within the shallow unconfined aquifer and sampling ground water from two existing monitor wells to assess ground water quality in the confined aquifer

  18. Shell Inspection History and Current CMM Inspection Efforts

    Energy Technology Data Exchange (ETDEWEB)

    Montano, Joshua Daniel [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2017-01-26

    The following report provides a review of past and current CMM Shell Inspection efforts. Calibration of the Sheffield rotary contour gauge has expired and the primary inspector, Matthew Naranjo, has retired. Efforts within the Inspection team are transitioning from maintaining and training new inspectors on Sheffield to off-the-shelf CMM technology. Although inspection of a shell has many requirements, the scope of the data presented in this report focuses on the inner contour, outer contour, radial wall thickness and mass comparisons.

  19. Statistical sampling plan for the TRU waste assay facility

    International Nuclear Information System (INIS)

    Beauchamp, J.J.; Wright, T.; Schultz, F.J.; Haff, K.; Monroe, R.J.

    1983-08-01

    Due to limited space, there is a need to dispose appropriately of the Oak Ridge National Laboratory transuranic waste which is presently stored below ground in 55-gal (208-l) drums within weather-resistant structures. Waste containing less than 100 nCi/g transuranics can be removed from the present storage and be buried, while waste containing greater than 100 nCi/g transuranics must continue to be retrievably stored. To make the necessary measurements needed to determine the drums that can be buried, a transuranic Neutron Interrogation Assay System (NIAS) has been developed at Los Alamos National Laboratory and can make the needed measurements much faster than previous techniques which involved γ-ray spectroscopy. The previous techniques are reliable but time consuming. Therefore, a validation study has been planned to determine the ability of the NIAS to make adequate measurements. The validation of the NIAS will be based on a paired comparison of a sample of measurements made by the previous techniques and the NIAS. The purpose of this report is to describe the proposed sampling plan and the statistical analyses needed to validate the NIAS. 5 references, 4 figures, 5 tables

  20. Tank 241-AZ-102 Privatization Push Mode Core Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    RASMUSSEN, J.H.

    1999-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AZ-102. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AZ-102 required to satisfy the Data Quality Objectives For TWRS Privatization Phase I : Confirm Tank TIS An Appropriate Feed Source For High-Level Waste Feed Batch X(HLW DQO) (Nguyen 1999a), Data Quality Objectives For TWRS Privatization Phase 1: Confirm Tank TIS An Appropriate Feed Source For Low-Activity Waste Feed Batch X (LAW DQO) (Nguyen 1999b), Low Activity Waste and High Level Waste Feed Data Quality Objectives (L and H DQO) (Patello et al. 1999) and Characterization Data Needs for Development, Design, and Operation of Retrieval Equipment Developed through the Data Quality Objective Process (Equipment DQO) (Bloom 1996). The Tank Characterization Technical Sampling Basis document (Brown et al. 1998) indicates that these issues, except the Equipment DQO apply to tank 241-AZ-102 for this sampling event. The Equipment DQO is applied for shear strength measurements of the solids segments only. Poppiti (1999) requires additional americium-241 analyses of the sludge segments. Brown et al. (1998) also identify safety screening, regulatory issues and provision of samples to the Privatization Contractor(s) as applicable issues for this tank. However, these issues will not be addressed via this sampling event. Reynolds et al. (1999) concluded that information from previous sampling events was sufficient to satisfy the safety screening requirements for tank 241-AZ-102. Push mode core samples will be obtained from risers 15C and 24A to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples, composite the liquids and solids, perform chemical analyses

  1. Randomization of inspections

    International Nuclear Information System (INIS)

    Markin, J.T.

    1989-01-01

    As the numbers and complexity of nuclear facilities increase, limitations on resources for international safeguards may restrict attainment of safeguards goals. One option for improving the efficiency of limited resources is to expand the current inspection regime to include random allocation of the amount and frequency of inspection effort to material strata or to facilities. This paper identifies the changes in safeguards policy, administrative procedures, and operational procedures that would be necessary to accommodate randomized inspections and identifies those situations where randomization can improve inspection efficiency and those situations where the current nonrandom inspections should be maintained. 9 refs., 1 tab

  2. Practical experience and problems in the inspection work during test and routine operation of nuclear power plants

    International Nuclear Information System (INIS)

    Backstroem, T.

    1977-01-01

    A brief description is given of the Swedish Nuclear Power Inspectorate (SNPI) and its working methods in the field of licensing procedures and inspection activities. SNPI has introduced a system to be kept continuously informed about the operation of the nuclear power plants. This information is used in the preparation work preceding the inspections. Experience obtained from the inspection activities show that inspection frequency has been lower than planned. Documentation can be improved and that good relations between the authority and the utilities, including the operating personnel, is to the benefit of the nuclear safety. (author)

  3. Inspection methods for safeguards systems at nuclear facilities

    International Nuclear Information System (INIS)

    Minichino, C.; Richard, E.W.

    1981-01-01

    A project team at Lawrence Livermore National Laboratory has been developing inspection procedures and training materials for the NRC inspectors of safeguards systems at licensed nuclear facilities. This paper describes (1) procedures developed for inspecting for compliance with the Code of Federal Regulations, (2) training materials for safeguards inspectors on technical topics related to safeguards systems, such as computer surety, alarm systems, sampling techniques, and power supplies, and (3) an inspector-oriented methodology for evaluating the overall effectiveness of safeguards systems

  4. Field Investigation Plan for 1301-N and 1325-N Facilities Sampling to Support Remedial Design

    International Nuclear Information System (INIS)

    Weiss, S. G.

    1998-01-01

    This field investigation plan (FIP) provides for the sampling and analysis activities supporting the remedial design planning for the planned removal action for the 1301-N and 1325-N Liquid Waste Disposal Facilities (LWDFs), which are treatment, storage,and disposal (TSD) units (cribs/trenches). The planned removal action involves excavation, transportation, and disposal of contaminated material at the Environmental Restoration Disposal Facility (ERDF).An engineering study (BHI 1997) was performed to develop and evaluate various options that are predominantly influenced by the volume of high- and low-activity contaminated soil requiring removal. The study recommended that additional sampling be performed to supplement historical data for use in the remedial design

  5. Development of inspection and maintenance program for reactor and reactivity control units in HANARO

    International Nuclear Information System (INIS)

    Cho, Yeong-Garp

    1998-01-01

    This paper summarizes the overall program for inspection and maintenance of reactor structure and Reactivity Control Units (RCU) of HANARO during lifetime. The long-term plan for in-service inspection is introduced in the viewpoint of the structural integrity of reactor and RCU, and the operability of RCU mechanism. This program includes the list of components to be inspected, the schedule of inspection and maintenance, and the development of special tools and test rig that are required for the remote inspection and maintenance of reactor and RCU components. Preliminary results of the evaluation on the lifetime of RCU components are summarized based on the operation history since the installation of reactor. A test rig will be designed and constructed for the purposes of verifying the prolonged lifetime of RCU components being used, the performance of special tools, and the rehearsal of maintenance work as well. (author)

  6. The non-proliferation experiment and gas sampling as an on-site inspection activity: A progress report

    International Nuclear Information System (INIS)

    Carrigan, C.R.

    1994-03-01

    The Non-proliferation Experiment (NPE) is contributing to the development of gas sampling methods and models that may be incorporated into future on-site inspection (OSI) activities. Surface gas sampling and analysis, motivated by nuclear test containment studies, have already demonstrated the tendency for the gaseous products of an underground nuclear test to flow hundreds of meters to the surface over periods ranging from days to months. Even in the presence of a uniform sinusoidal pressure variation, there will be a net flow of cavity gas toward the surface. To test this barometric pumping effect at Rainier Mesa, gas bottles containing sulfur hexaflouride and 3 He were added to the pre-detonation cavity for the 1 kt chemical explosives test. Pre-detonation measurements of the background levels of both gases were obtained at selected sites on top of the mesa. The background levels of both tracers were found to be at or below mass spectrographic/gas chromatographic sensitivity thresholds in the parts-per-trillion range. Post-detonation, gas chromatographic analyses of samples taken during barometric pressure lows from the sampling sites on the mesa indicate the presence of significant levels (300--600 ppt) of sulfur hexaflouride. However, mass spectrographic analyses of gas samples taken to date do not show the presence of 3 He. To explain these observations, several possibilities are being explored through additional sampling/analysis and numerical modeling. For the NPE, the detonation point was approximately 400 m beneath the surface of Rainier Mesa and the event did not produce significant fracturing or subsidence on the surface of the mesa. Thus, the NPE may ultimately represent an extreme, but useful example for the application and tuning of cavity gas detection techniques

  7. A novel visual pipework inspection system

    Science.gov (United States)

    Summan, Rahul; Jackson, William; Dobie, Gordon; MacLeod, Charles; Mineo, Carmelo; West, Graeme; Offin, Douglas; Bolton, Gary; Marshall, Stephen; Lille, Alexandre

    2018-04-01

    The interior visual inspection of pipelines in the nuclear industry is a safety critical activity conducted during outages to ensure the continued safe and reliable operation of plant. Typically, the video output by a manually deployed probe is viewed by an operator looking to identify and localize surface defects such as corrosion, erosion and pitting. However, it is very challenging to estimate the nature and extent of defects by viewing a large structure through a relatively small field of view. This work describes a new visual inspection system employing photogrammetry using a fisheye camera and a structured light system to map the internal geometry of pipelines by generating a photorealistic, geometrically accurate surface model. The error of the system output was evaluated through comparison to a ground truth laser scan (ATOS GOM Triple Scan) of a nuclear grade split pipe sample (stainless steel 304L, 80mm internal diameter) containing defects representative of the application - the error was found to be submillimeter across the sample.

  8. Actinic inspection of EUV reticles with arbitrary pattern design

    Science.gov (United States)

    Mochi, Iacopo; Helfenstein, Patrick; Rajeev, Rajendran; Fernandez, Sara; Kazazis, Dimitrios; Yoshitake, Shusuke; Ekinci, Yasin

    2017-10-01

    The re ective-mode EUV mask scanning lensless imaging microscope (RESCAN) is being developed to provide actinic mask inspection capabilities for defects and patterns with high resolution and high throughput, for 7 nm node and beyond. Here we, will report on our progress and present the results on programmed defect detection on random, logic-like patterns. The defects we investigated range from 200 nm to 50 nm size on the mask. We demonstrated the ability of RESCAN to detect these defects in die-to-die and die-to-database mode with a high signal to noise ratio. We also describe future plans for the upgrades to increase the resolution, the sensitivity, and the inspection speed of the demo tool.

  9. Inspection of internal tank welds using the ACFM inspection method

    International Nuclear Information System (INIS)

    Topp, D.A.; Lugg, M.C.

    2009-01-01

    The paper describes recent developments of the ACFM technique and describes several case studies where ACFM has been used to inspect the internal plate welds on large steel storage tanks in refineries. For weld inspection, conventional methods such as magnetic particle inspection or vacuum box testing are generally used. This paper presents comparisons of the results from ACFM with those from the conventional methods, from which conclusions are drawn as to the benefits this technique offers in terms of cost, time savings and inspection reliability. (author)

  10. Recent Ultrasonic Guided Wave Inspection Development Efforts

    International Nuclear Information System (INIS)

    Rose, Joseph L.; Tittmann, Bernhard R.

    2001-01-01

    The recognition of such natural wave guides as plates, rods, hollow cylinders, multi-layer structures or simply an interface between two materials combined with an increased understanding of the physics and wave mechanics of guided wave propagation has led to a significant increase in the number of guided wave inspection applications being developed each year. Of primary attention Is the ability to inspect partially hidden structures, hard to access areas, and treated or insulated structures. An introduction to some physical consideration of guided waves followed by some sample problem descriptions in pipe, ice detection, fouling detection in the foods industry, aircraft, tar coated structures and acoustic microscopy is presented in this paper. A sample problem in Boundary Element Modeling is also presented to illustrate the move in guided wave analysis beyond detection and location analysis to quantification

  11. Compatibility Grab Sampling and Analysis Plan for FY 2000

    International Nuclear Information System (INIS)

    SASAKI, L.M.

    1999-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for grab samples obtained to address waste compatibility. It is written in accordance with requirements identified in Data Quality Objectives for Tank Farms Waste Compatibility Program (Mulkey et al. 1999) and Tank Farm Waste Transfer Compatibility Program (Fowler 1999). In addition to analyses to support Compatibility, the Waste Feed Delivery program has requested that tank samples obtained for Compatibility also be analyzed to confirm the high-level waste and/or low-activity waste envelope(s) for the tank waste (Baldwin 1999). The analytical requirements to confirm waste envelopes are identified in Data Quality Objectives for TWRS Privatization Phase I: Confirm Tank T is an Appropriate Feed Source for Low-Activity Waste Feed Batch X (Nguyen 1999a) and Data Quality Objectives for RPP Privatization Phase I: Confirm Tank T is an Appropriate Feed Source for High-Level Waste Feed Batch X (Nguyen 1999b)

  12. The ultrasonic shop map and its use in preservice inspection

    International Nuclear Information System (INIS)

    Caplan, J.S.

    1975-01-01

    Prior to the introduction of Section X1 of the ASME Code on Inservice Inspection, a plan was introduced by Westinghouse to perform ultrasonic examinations of areas of high stress and high fluence of reactor pressure vessels in the manufacturer's shop and subsequent to the shop hydrostatic test. The tests provided a shop reference map of ultrasonic responses to use in subsequent preservice and inservice inspections, and attempted to locate any ultrasonic reflections beyond the acceptance standards of ASME Section III and, later, of Section X1. The history of the program is reviewed. Thirty-six vessels were examined during 1970 to 1973. As a result of indications discovered during ultrasonic examination repairs were carried out on five of these. Details are given of inspections and repairs. A summary is also given of the indications detected and of the correlations between the ultrasonic evaluation and actual flow characteristics. (U.K.)

  13. Planning Related to the Curation and Processing of Returned Martian Samples

    Science.gov (United States)

    McCubbin, F. M.; Harrington, A. D.

    2018-04-01

    Many of the planning activities in the NASA Astromaterials Acquisition and Curation Office at JSC are centered around Mars Sample Return. The importance of contamination knowledge and the benefits of a mobile/modular receiving facility are discussed.

  14. Unannounced inspection for integrated safeguards: A theoretical perspective

    International Nuclear Information System (INIS)

    Canty, M.J.; Avenhaus, R.

    2001-01-01

    Full text: The application of a safeguards verification regime based on existing agreements under INFCIRC/153 and on the Additional Protocol, INFCIRC/540, has the potential to allow the International Atomic Energy Agency (IAEA) to relax its traditional facility and material-oriented inspection procedures. The relaxation will take into account the IAEA's enhanced access to information as well as complementary access to locations gained through the application of extended measures foreseen under the Additional Protocol. It will reflect the associated confidence achieved at the State level. It is generally agreed that such a trade-off between the new strengthening measures and the traditional measures is reasonable and desirable, both from the point of view of the inspected State, which would like to receive tangible credit for providing increased openness and transparency in its peaceful nuclear activities, and from the viewpoint of the IAEA, which must apportion its limited inspection resources efficiently. An often-discussed proposal to reduce routine inspection effort while maintaining safeguards effectiveness is to replace scheduled interim inspections with a smaller number of random, unannounced visits. Intuitively, the unpredictability aspect is appealing, as it places the potential diverter in a permanent state of uncertainty. There are also some disadvantages, however, such as the difficulty of planning and implementing truly random inspections and the burden experienced by facility operators obliged to accommodate them. An objective evaluation of a randomized inspection regime vis-a-vis conventional routine inspections requires an objective measure of effectiveness and a means of optimizing that measure - in other words a theoretical framework for analyzing verification problems. In our paper we provide such a framework by quantifying the notion of timely detection and by treating the problem consistently a strategic one. We present a series of models which

  15. General inspection strategy for fault diagnosis-minimizing the inspection costs

    International Nuclear Information System (INIS)

    Reinertsen, Rune; Wang Xiaozhong

    1995-01-01

    In this paper, a general inspection strategy for system fault diagnosis is presented. The procedure presented in this paper, is an improvement of methods described in papers by , and . This general strategy provides the optimal inspection procedure when the inspections require unequal effort and the minimum cut set probabilities are unequal. This feature makes the procedure described in this paper more useful for practical applications than the most recent procedure presented in the paper by Najmus-Saqib and Ishaque, which requires the minimum cut set probabilities to be equal. The inspection strategy described in this paper is based on first inspecting the basic event that will provide the maximum information gain per unit cost invested. The information gain is measured by the decrease of Shannon entropy. A detailed tutorial example is presented

  16. Cargo container inspection test program at ARPA's Nonintrusive Inspection Technology Testbed

    Science.gov (United States)

    Volberding, Roy W.; Khan, Siraj M.

    1994-10-01

    An x-ray-based cargo inspection system test program is being conducted at the Advanced Research Project Agency (ARPA)-sponsored Nonintrusive Inspection Technology Testbed (NITT) located in the Port of Tacoma, Washington. The test program seeks to determine the performance that can be expected from a dual, high-energy x-ray cargo inspection system when inspecting ISO cargo containers. This paper describes an intensive, three-month, system test involving two independent test groups, one representing the criminal smuggling element and the other representing the law enforcement community. The first group, the `Red Team', prepares ISO containers for inspection at an off-site facility. An algorithm randomly selects and indicates the positions and preparation of cargoes within a container. The prepared container is dispatched to the NITT for inspection by the `Blue Team'. After in-gate processing, it is queued for examination. The Blue Team inspects the container and decides whether or not to pass the container. The shipment undergoes out-gate processing and returns to the Red Team. The results of the inspection are recorded for subsequent analysis. The test process, including its governing protocol, the cargoes, container preparation, the examination and results available at the time of submission are presented.

  17. Inspection Database

    Data.gov (United States)

    U.S. Department of Health & Human Services — FDA is disclosing the final inspection classification for inspections related to currently marketed FDA-regulated products. The disclosure of this information is not...

  18. Supplement to the UMTRA Project water sampling and analysis plan, Maybell, Colorado

    International Nuclear Information System (INIS)

    1995-09-01

    This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Maybell, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Maybell (DOE, 1994a). Further, this supplement serves to confirm our present understanding of the site relative to the hydrogeology and contaminant distribution as well as our intention to continue to use the sampling strategy as presented in the 1994 WSAP document for Maybell. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 (1994) and 60 CFR 2854 (1 995). Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Maybell site are the Maybell Baseline Risk Assessment (currently in progress), the Maybell Remedial Action Plan (RAP) (DOE, 1994b), and the Maybell Environmental Assessment (DOE, 1995)

  19. Results from a new 193nm die-to-database reticle inspection platform

    Science.gov (United States)

    Broadbent, William H.; Alles, David S.; Giusti, Michael T.; Kvamme, Damon F.; Shi, Rui-fang; Sousa, Weston L.; Walsh, Robert; Xiong, Yalin

    2010-05-01

    A new 193nm wavelength high resolution reticle defect inspection platform has been developed for both die-to-database and die-to-die inspection modes. In its initial configuration, this innovative platform has been designed to meet the reticle qualification requirements of the IC industry for the 22nm logic and 3xhp memory generations (and shrinks) with planned extensions to the next generation. The 22nm/3xhp IC generation includes advanced 193nm optical lithography using conventional RET, advanced computational lithography, and double patterning. Further, EUV pilot line lithography is beginning. This advanced 193nm inspection platform has world-class performance and the capability to meet these diverse needs in optical and EUV lithography. The architecture of the new 193nm inspection platform is described. Die-to-database inspection results are shown on a variety of reticles from industry sources; these reticles include standard programmed defect test reticles, as well as advanced optical and EUV product and product-like reticles. Results show high sensitivity and low false and nuisance detections on complex optical reticle designs and small feature size EUV reticles. A direct comparison with the existing industry standard 257nm wavelength inspection system shows measurable sensitivity improvement for small feature sizes

  20. Results of calendar year 1995 Well Inspection and Maintenance Program Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    McMaster, B.W.

    1996-07-01

    This document is a compendium of results of the 1995 Monitor Well Inspection and Maintenance Program at the US Department of Energy's Oak Ridge Y-12 Plant. This report documents the work relating to well inspections and maintenance requests. Inspections are implemented in order to better assess the condition and maintenance needs of wells that are actively being monitored. Currently this approach calls for inspecting all wells on a routine (annual or triennial) basis which are: (1) in an active sampling program; (2) included in a hydrologic study; or (3) not in service, but not scheduled for plugging and abandonment. Routine inspections help to ensure that representative groundwater samples and hydrologic data are being collected, and contribute to the effective longevity of each well. This report formally presents well inspection and maintenance activities that were conducted at the Y-12 Plant from August through December 1995

  1. Optical fiber inspection system

    Science.gov (United States)

    Moore, Francis W.

    1987-01-01

    A remote optical inspection system including an inspection head. The inspection head has a passageway through which pellets or other objects are passed. A window is provided along the passageway through which light is beamed against the objects being inspected. A plurality of lens assemblies are arranged about the window so that reflected light can be gathered and transferred to a plurality of coherent optical fiber light guides. The light guides transfer the light images to a television or other image transducer which converts the optical images into a representative electronic signal. The electronic signal can then be displayed on a signal viewer such as a television monitor for inspection by a person. A staging means can be used to support the objects for viewing through the window. Routing means can be used to direct inspected objects into appropriate exit passages for accepted or rejected objects. The inspected objects are advantageously fed in a singular manner to the staging means and routing means. The inspection system is advantageously used in an enclosure when toxic or hazardous materials are being inspected.

  2. Inspection of rotor bores, retaining rings and turbine discs utilizing UDRPS

    International Nuclear Information System (INIS)

    Quinn, J.R.

    1990-01-01

    New construction in the U.S. utility industry is at a very low level. The average age of plants in increasing almost linearly with time, many units will pass nominal end of life in the next decade. Planned new construction now takes ten years to effect at a minimum. The need for more reliable inspection of high stress utility components is and will continue to be a subject of increased emphasis. Dynacon Systems Inc. has recently introduced into commercial service, a fully automated ultrasonic inspection instrumentation package designed to significantly increase the reliability of turbine/generator rotor shaft, LP disc and generator retaining ring inspections. The package is designed to automate to a very high degree, the entire analysis process, thus eliminating operator error sources. The automated process begins at the ultrasonic pulse generator and ends with the input to fracture mechanics analysis

  3. Office of Inspector General fiscal year 1996 annual work plan

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-10-01

    This FY 1996 Office of Inspector General (OIG) Annual Work Plan is a summary and distillation of information contained in annual work plans, and includes audits and inspections that are carried over from FY 1995 as well as audits and inspections scheduled to start during FY 1996. Audits and inspections included in this consolidated OIG Annual Work Plan will be performed by OIG staff. Specialized expertise available through a Certified Public Accounting firm will be used to assist in auditing the Department`s financial statements. As part of the OIG Cooperative Audit Strategy, additional audit coverage of the Department`s programs is provided by internal auditors of the Department`s integrated contractors. Through the Cooperative Audit Strategy, the OIG ensures that the internal auditors satisfy audit standards, provides planning guidance to the internal auditors, coordinates work to avoid duplication, and tracks the work of internal auditors to ensure that needed audits are performed. Applicable portions of the four annual work plans issued for Fiscal Year 1996 by the Deputy/Assistant Inspectors General have been combined to form a major part of this overall OIG Annual Work Plan. Also included are portions of the most recent OIG Semiannual Reports to Congress to give an overview of the OIG`s mission/organization, resource status, and the environment in which the OIG currently operates. The OIG Annual Work Plan also lists ongoing and planned audits and inspections, and it presents investigative statistics which have been previously reported in the two OIG Semiannual Reports to Congress which cover Fiscal Year 1995. Furthermore, included in this work plan are descriptions of several innovations developed by the OIG to streamline its operations and to conserve as much efficiency and economy as possible in a time of resource reductions.

  4. Regulatory inspection of the egyptian gamma irradiator using a proposed inspection checklist

    International Nuclear Information System (INIS)

    Abdel-Ghani, A.H.

    2000-01-01

    Regulatory inspections are one of the most important elements of a regulatory programme. It shall be performed in all areas of the regulatory responsibility and during all phases of siting, design, construction, commissioning, operation, maintenance and decommissioning of an irradiator facility. The egyptian mega gamma irradiator operating since december 1979 has a Co-60 source of about 400 kilo curies and is used mainly for sterilization of medical supplies and pharmaceuticals and for preservation of some food stuffs. The constructor (Nordion international Inc.) recommended an extensive inspection programme. In accordance with the international and national (2.3) regulations as well as the licensing conditions, the competent authority (NCNSRC) shall perform regulatory inspections both announced and unannounced. In order to facilitate the inspection task and to harmonize the inspection reports a checklist for inspection is proposed which can be used also as an inspection report form

  5. 77 FR 76815 - Handling of Animals; Contingency Plans

    Science.gov (United States)

    2012-12-31

    ... DEPARTMENT OF AGRICULTURE Animal and Plant Health Inspection Service 9 CFR Parts 2 and 3 [Docket No. APHIS-2006-0159] RIN 0579-AC69 Handling of Animals; Contingency Plans AGENCY: Animal and Plant Health Inspection Service, USDA. ACTION: Final rule. SUMMARY: We are amending the Animal Welfare Act...

  6. Engineering Task Plan to Expand the Environmental Operational Envelope of Core Sampling

    International Nuclear Information System (INIS)

    BOGER, R.M.

    1999-01-01

    This Engineering Task Plan authorizes the development of an Alternative Generation and Analysis (AGA). The AGA will determine how to expand the environmental operating envelope during core sampling operations

  7. Results of calendar year 1994 monitor well inspection and maintenance program, Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    McMaster, B.W.; Jones, S.B.; Sitzler, J.L.

    1995-06-01

    This document is a compendium of results of the calendar year 1994 Monitor Well Inspection and Maintenance Program at the Department of Energy Y-12 Plant in Oak Ridge, Tennessee. This report documents the work relating to well inspections and maintenance requests. Inspections are implemented in order to better assess the condition and maintenance needs of wells that are actively being monitored. Currently this approach calls for inspecting all wells on a routine (annual or triennial) basis which are: (1) in an active sampling program; (2) included in a hydrologic study; or (3) not in service, but not scheduled for plugging and abandonment. Routine inspections help to ensure that representative groundwater samples and hydrologic data are being collected, and contribute to the life expectancy of each well. This report formally presents well inspection and maintenance activities that were conducted at the Y-12 Plant during 1994. All inspections were conducted between April and December

  8. Results of calendar year 1994 monitor well inspection and maintenance program, Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    McMaster, B.W. [Univ. of Tennessee, Knoxville, TN (United States); Jones, S.B.; Sitzler, J.L. [Oak Ridge National Lab., TN (United States)

    1995-06-01

    This document is a compendium of results of the calendar year 1994 Monitor Well Inspection and Maintenance Program at the Department of Energy Y-12 Plant in Oak Ridge, Tennessee. This report documents the work relating to well inspections and maintenance requests. Inspections are implemented in order to better assess the condition and maintenance needs of wells that are actively being monitored. Currently this approach calls for inspecting all wells on a routine (annual or triennial) basis which are: (1) in an active sampling program; (2) included in a hydrologic study; or (3) not in service, but not scheduled for plugging and abandonment. Routine inspections help to ensure that representative groundwater samples and hydrologic data are being collected, and contribute to the life expectancy of each well. This report formally presents well inspection and maintenance activities that were conducted at the Y-12 Plant during 1994. All inspections were conducted between April and December.

  9. 78 FR 54861 - Inspection, Repair, and Maintenance; Driver-Vehicle Inspection Report

    Science.gov (United States)

    2013-09-06

    ... No. FMCSA-2012-0336] RIN 2126-AB46 Inspection, Repair, and Maintenance; Driver-Vehicle Inspection... Federal Register of August 7, 2013, regarding driver vehicle inspection reports. The corrections involve..., Vehicle and Roadside Operations Division, Office of Bus and Truck Standards and Operations, Federal Motor...

  10. Additive Manufacturing Infrared Inspection

    Science.gov (United States)

    Gaddy, Darrell; Nettles, Mindy

    2015-01-01

    The Additive Manufacturing Infrared Inspection Task started the development of a real-time dimensional inspection technique and digital quality record for the additive manufacturing process using infrared camera imaging and processing techniques. This project will benefit additive manufacturing by providing real-time inspection of internal geometry that is not currently possible and reduce the time and cost of additive manufactured parts with automated real-time dimensional inspections which deletes post-production inspections.

  11. Health products inspection

    International Nuclear Information System (INIS)

    Stoltz, M.

    2009-01-01

    To protect public health, the Health Products Inspection is a public service mission where the application of regulations concerning activities on human health products and cosmetic products is verified. This mission permits a global approach to assess the health products risk-based benefit and, in monitoring by laboratory testing and by on site inspections, to verify their compliance with appropriate regulations. The seventy five inspectors perform about eight hundred inspections per year, in France and abroad. These inspections are related to data provided in the health products assessment and also to manufacturing and delivery practices. The French inspection body is also involved in the training of foreign inspectors and in the harmonization of national, European and international practices either for operators than for the competent authorities. (author)

  12. 48 CFR 1852.236-73 - Hurricane plan.

    Science.gov (United States)

    2010-10-01

    ... 48 Federal Acquisition Regulations System 6 2010-10-01 2010-10-01 true Hurricane plan. 1852.236-73... Hurricane plan. As prescribed in 1836.570(c), insert the following clause: Hurricane Plan (DEC 1988) In the event of a hurricane warning, the Contractor shall— (a) Inspect the area and place all materials...

  13. Optimal sample size for probability of detection curves

    International Nuclear Information System (INIS)

    Annis, Charles; Gandossi, Luca; Martin, Oliver

    2013-01-01

    Highlights: • We investigate sample size requirement to develop probability of detection curves. • We develop simulations to determine effective inspection target sizes, number and distribution. • We summarize these findings and provide guidelines for the NDE practitioner. -- Abstract: The use of probability of detection curves to quantify the reliability of non-destructive examination (NDE) systems is common in the aeronautical industry, but relatively less so in the nuclear industry, at least in European countries. Due to the nature of the components being inspected, sample sizes tend to be much lower. This makes the manufacturing of test pieces with representative flaws, in sufficient numbers, so to draw statistical conclusions on the reliability of the NDT system under investigation, quite costly. The European Network for Inspection and Qualification (ENIQ) has developed an inspection qualification methodology, referred to as the ENIQ Methodology. It has become widely used in many European countries and provides assurance on the reliability of NDE systems, but only qualitatively. The need to quantify the output of inspection qualification has become more important as structural reliability modelling and quantitative risk-informed in-service inspection methodologies become more widely used. A measure of the NDE reliability is necessary to quantify risk reduction after inspection and probability of detection (POD) curves provide such a metric. The Joint Research Centre, Petten, The Netherlands supported ENIQ by investigating the question of the sample size required to determine a reliable POD curve. As mentioned earlier manufacturing of test pieces with defects that are typically found in nuclear power plants (NPPs) is usually quite expensive. Thus there is a tendency to reduce sample sizes, which in turn increases the uncertainty associated with the resulting POD curve. The main question in conjunction with POS curves is the appropriate sample size. Not

  14. Chemical Hygiene Plan for Onsite Measurement and Sample Shipping Facility Activities

    International Nuclear Information System (INIS)

    Price, W.H.

    1998-01-01

    This chemical hygiene plan presents the requirements established to ensure the protection of employee health while performing work in mobile laboratories, the sample shipping facility, and at the onsite radiological counting facility. This document presents the measures to be taken to promote safe work practices and to minimize worker exposure to hazardous chemicals. Specific hazardous chemicals present in the mobile laboratories, the sample shipping facility, and in the radiological counting facility are presented in Appendices A through G

  15. UMTRA project water sampling and analysis plan -- Shiprock, New Mexico

    International Nuclear Information System (INIS)

    1994-02-01

    Water sampling and analysis plan (WSAP) is required for each U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site to provide a basis for ground water and surface water sampling at disposal and former processing sites. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the monitoring stations at the Navaho Reservation in Shiprock, New Mexico, UMTRA Project site. The purposes of the water sampling at Shiprock for fiscal year (FY) 1994 are to (1) collect water quality data at new monitoring locations in order to build a defensible statistical data base, (2) monitor plume movement on the terrace and floodplain, and (3) monitor the impact of alluvial ground water discharge into the San Juan River. The third activity is important because the community of Shiprock withdraws water from the San Juan River directly across from the contaminated alluvial floodplain below the abandoned uranium mill tailings processing site

  16. Supplement to the UMTRA Project water sampling and analysis plan, Monument Valley, Arizona

    International Nuclear Information System (INIS)

    1995-09-01

    This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Riverton, Wyoming, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Riverton (DOE, 1994). Further, the supplement serves to confirm the Project's present understanding of the site relative to the hydrogeology and contaminant distribution as well as the intent to continue to use the sampling strategy as presented in the 1994 WSAP document for Riverton. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 and 60 FR 2854. Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Riverton site are the Riverton Baseline Risk Assessment (BLRA) (DOE, 1995a) and the Riverton Site Observational Work Plan (SOWP) (DOE, 1995b)

  17. C-018H Pre-Operational Baseline Sampling Plan

    International Nuclear Information System (INIS)

    Guzek, S.J.

    1993-01-01

    The objective of this task is to field characterize and sample the soil at selected locations along the proposed effluent line routes for Project C-018H. The overall purpose of this effort is to meet the proposed plan to discontinue the disposal of contaminated liquids into the Hanford soil column as described by DOE (1987). Detailed information describing proposed transport pipeline route and associated Kaiser Engineers Hanford Company (KEH) preliminary drawings (H288746...755) all inclusive, have been prepared by KEH (1992). The information developed from field monitoring and sampling will be utilized to characterize surface and subsurface soil along the proposed C-018H effluent pipeline and it's associated facilities. Potentially existing contaminant levels may be encountered therefore, soil characterization will provide a construction preoperational baseline reference, develop personnel safety requirements, and determine the need for any changes in the proposed routes prior to construction of the pipeline

  18. Food safety assurance systems: Microbiological testing, sampling plans, and microbiological criteria

    NARCIS (Netherlands)

    Zwietering, M.H.; Ross, T.; Gorris, L.G.M.

    2014-01-01

    Microbiological criteria give information about the quality or safety of foods. A key component of a microbiological criterion is the sampling plan. Considering: (1) the generally low level of pathogens that are deemed tolerable in foods, (2) large batch sizes, and (3) potentially substantial

  19. EUV mask defect inspection and defect review strategies for EUV pilot line and high volume manufacturing

    Science.gov (United States)

    Chan, Y. David; Rastegar, Abbas; Yun, Henry; Putna, E. Steve; Wurm, Stefan

    2010-04-01

    Reducing mask blank and patterned mask defects is the number one challenge for extreme ultraviolet lithography. If the industry succeeds in reducing mask blank defects at the required rate of 10X every year for the next 2-3 years to meet high volume manufacturing defect requirements, new inspection and review tool capabilities will soon be needed to support this goal. This paper outlines the defect inspection and review tool technical requirements and suggests development plans to achieve pilot line readiness in 2011/12 and high volume manufacturing readiness in 2013. The technical specifications, tooling scenarios, and development plans were produced by a SEMATECH-led technical working group with broad industry participation from material suppliers, tool suppliers, mask houses, integrated device manufacturers, and consortia. The paper summarizes this technical working group's assessment of existing blank and mask inspection/review infrastructure capabilities to support pilot line introduction and outlines infrastructure development requirements and tooling strategies to support high volume manufacturing.

  20. 10 CFR Appendix A to Subpart U of... - Sampling Plan for Enforcement Testing of Electric Motors

    Science.gov (United States)

    2010-01-01

    ... 10 Energy 3 2010-01-01 2010-01-01 false Sampling Plan for Enforcement Testing of Electric Motors A Appendix A to Subpart U of Part 431 Energy DEPARTMENT OF ENERGY ENERGY CONSERVATION ENERGY EFFICIENCY... to Subpart U of Part 431—Sampling Plan for Enforcement Testing of Electric Motors Step 1. The first...

  1. Fuel inspection device

    International Nuclear Information System (INIS)

    Tsuji, Tadashi.

    1990-01-01

    The fuel inspection device of the present invention has a feature of obtaining an optimum illumination upon fuel rod interval inspection operation in a fuel pool. That is, an illumination main body used underwater is connected to a cable which is led out on a floor. A light control device is attached to the other end of the cable and an electric power cable is connected to the light control device. A light source (for example, incandescent lamp) is incorporated in the casing of the illumination main body, and a diffusion plate is disposed at the front to provide a plane light source. The light control device has a light control knob capable of remote-controlling the brightness of the light of the illumination main body. In the fuel inspection device thus constituted, halation is scarcely caused on the image screen upon inspection of fuels by a submerged type television camera to facilitate control upon inspection. Accordingly, efficiency of the fuel inspection can be improved to shorten the operation time. (I.S.)

  2. Non-periodic inspection optimization of multi-component and k-out-of-m systems

    International Nuclear Information System (INIS)

    Hajipour, Yassin; Taghipour, Sharareh

    2016-01-01

    This paper proposes a model to find the optimal non-periodic inspection interval over a finite planning horizon for two types of multi-component repairable systems. The first system contains hard-type and soft-type components, and the second system is a k-out-of-m system with m identical components. The failures of components in both systems follow a non-homogeneous Poisson process. A component can be a single part such as battery or line cord, or a subsystem, such as circuit breaker or charger in an infusion pump, which depending on their failures could be either replaced or minimally repaired according to their ages at failure. The systems are inspected at scheduled inspections or when an event of opportunistic inspection or a system failure occur. We develop a model to find the optimal inspection scheme for each system, which results in the minimum total expected cost over the system's lifecycle. We first develop a simulation model to obtain the total expected cost for a given non-periodic inspection scheme, and then integrate the simulation model with a genetic algorithm to obtain the optimal scheme more efficiently. - Highlights: • Non-periodic inspection optimization of two complex systems. • One system consists of soft-type and hard-type components. • The second system is a k-out-of-m system. • Integration of a simulation model and the genetic algorithm. • The model can be used when inspection is challenging or costly.

  3. Double-Shell Tank (DST) Ventilation System Vapor Sampling and Analysis Plan

    International Nuclear Information System (INIS)

    SASAKI, L.M.

    2000-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples from the primary ventilation systems of the AN, AP, AW, and AY/AZ tank farms. Sampling will be performed in accordance with Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Air DQO) (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications. Vapor samples will be obtained from tank farm ventilation systems, downstream from the tanks and upstream of any filtration. Samples taken in support of the DQO will consist of SUMMA(trademark) canisters, triple sorbent traps (TSTs), sorbent tube trains (STTs), polyurethane foam (PUF) samples. Particulate filter samples and tritium traps will be taken for radiation screening to allow the release of the samples for analysis. The following sections provide the general methodology and procedures to be used in the preparation, retrieval, transport, analysis, and reporting of results from the vapor samples

  4. Flight route Designing and mission planning Of power line inspecting system Based On multi-sensor UAV

    International Nuclear Information System (INIS)

    Xiaowei, Xie; Zhengjun, Liu; Zhiquan, Zuo

    2014-01-01

    In order to obtain various information of power facilities such as spatial location, geometry, images data and video information in the infrared and ultraviolet band and so on, Unmanned Aerial Vehicle (UAV) power line inspecting system needs to integrate a variety of sensors for data collection. Low altitude and side-looking imaging are required for UAV flight to ensure sensors to acquire high-quality data and device security. In this paper, UAV power line inspecting system is deferent from existing ones that used in Surveying and Mapping. According to characteristics of UAV for example equipped multiple sensor, side-looking imaging, working at low altitude, complex terrain conditions and corridor type flight, this paper puts forward a UAV power line inspecting scheme which comprehensively considered of the UAV performance, sensor parameters and task requirements. The scheme is finally tested in a region of Guangdong province, and the preliminary results show that the scheme is feasible

  5. Inspection of training activities by the NRC's Office of Inspection and Enforcement

    International Nuclear Information System (INIS)

    Ruhlman, W.A.

    1975-01-01

    New requirements in the Code of Federal Regulations, the issuance of new Regulatory Guides and ANSI Standards, have indicated the increased emphasis being placed on training by forces in the Nuclear Industry and the Nuclear Regulatory Commission. A brief description is presented of the functions of the Office of Inspection and Enforcement in the training areas. Three areas are examined: general inspection techniques; training inspection scope; and training inspection bases

  6. OSE inspection of protection program operations field perspective of inspections

    International Nuclear Information System (INIS)

    Brown, R.W.; Martin, H.R.

    1987-01-01

    Protection Program Operations includes three functional areas: Physical Protection Systems, Protective Forces, and System Performance Testing. The Office of Security Evaluations (OSE) inspects field offices in these areas by evaluating programs relative to Standards and Criteria and by performing a variety of exercises and other types of tests to assure protective systems are effective and maintained at a proper level to meet the defined threat. Their perception of the OSE inspections has been positive. The approach taken by ID, with key areas/activities emphasized, during each phase of the field inspection process is described in this report. The most important areas for field offices to concentrate are: inspection preparations through self-evaluation, improving communications, assigning knowledgeable trusted agents, increasing awareness of facility procedures and operations, and assuring daily validations of inspected areas. Emphasis is placed on striving for a balance in reporting both positive and negative findings, and for consistency between ratings and the importance of report findings. OSE efforts to develop improved rating methodologies are encouraged

  7. 46 CFR 44.01-13 - Heavy weather plan.

    Science.gov (United States)

    2010-10-01

    ... 46 Shipping 2 2010-10-01 2010-10-01 false Heavy weather plan. 44.01-13 Section 44.01-13 Shipping... VOYAGES Administration § 44.01-13 Heavy weather plan. (a) Each heavy weather plan under § 44.01-12(b) must... Inspection. Approval of a heavy weather plan is limited to the current hurricane season. (b) The cognizant...

  8. Development of data acquisition and processing system for In-service inspection of nuclear power plants

    International Nuclear Information System (INIS)

    Takama, Shinkichi; Kobayashi, Koji; Satoh, Yoshio; Koga, Yoshihiro; Shimizu, Takakazu

    1981-01-01

    In-service inspection (ISI) is required during the plant outage to assure the reliability of the components of a nuclear power plant. IHI has developed the advanced ISI system which consists of remote controlled and mechanized ultrasonic inspection devices for reactor pressure vessel examination, semi-automatic inspection instruments for piping examination with manual scan and automatic recording, data acquisition and processing system with microprocessor and mini-computer. By this system, ISI can be performed fully satisfying the requirement of ASME Code Sec. XI and minimizing operation in the high radioactive areas. All ultrasonic information is processed by the computer and the examination results such as size and location of ultrasonic indication are printed out in the form of sectional and plan view of the part examined, reproduced screen image and polar plot, etc. as well as the evaluation sheet. This system saves the elaborate work of inspection personnel and is expected to contribute to the improvement of inspection quality and to the reduction of radiation exposure of inspection personnel. (author)

  9. Centralized vs. decentralized thermal IR inspection policy: experience from a major Brazilian electric power company

    Science.gov (United States)

    dos Santos, Laerte; da Costa Bortoni, Edson; Barbosa, Luiz C.; Araujo, Reyler A.

    2005-03-01

    Furnas Centrais Elétricas S.A is one of the greatest companies of the Brazilian electric power sector and a pioneer in using infrared thermography. In the early 70s, the maintenance policy used was a centralized approach, with only one inspection team to cover all the company"s facilities. In the early 90s, FURNAS decided to decentralize the thermography inspections creating several inspection teams. This new maintenance policy presented several advantages when compared to the previous one. However the credibility of the results obtained with the thermal inspection was frequently being questioned, in part due to the lack of a detailed planning to carry out the transition from the centralized inspection to the decentralized one. In some areas of the company it was suggested the inactivation of the thermography. This paper presents the experience of FURNAS with these different maintenance policies and details the procedures which have been taken that nowadays the infrared thermal inspection has become one of the most important techniques of predictive maintenance in the company.

  10. Phytosanitary inspection of woody plants for planting at european union entry points: A practical enquiry

    OpenAIRE

    Eschen, René; Rigaux, Ludovic; Sukovata, Lidia; Vettraino, Anna Maria; Marzano, Mariella; Grégoire, Jean-Claude

    2015-01-01

    Phytosanitary import inspections are important to avoid entry of harmful pests on live plants. In the European Union (EU), all consignments of live plants must be inspected at the first point of entry, and plants allowed entry can be moved without further inspection among the 28 Member States and Switzerland. It is important that inspections in EU countries adhere to the same standard to avoid introduction of harmful organisms through countries with weaker methods. We tested whether sampling ...

  11. Development of innovative inspection tools for higher reliability of PHWR fuel

    International Nuclear Information System (INIS)

    Kamalesh Kumar, B.; Viswanathan, B.; Laxminarayana, B.; Ganguly, C.

    2003-01-01

    'Full text:' Advent of Computer aided manufacturing systems has led to very high rate of production with greater reliability. The conventional inspection tools and systems, which are often manual based do not complement with output of highly automated production line. In order to overcome the deficiency, a strategic plan was developed for having automated inspection facility for PHWR fuel assembly line. Laser based systems with their inherently high accuracy and quick response times are a favorite for metrology purpose. Non-contact nature of laser-based measurement ensures minimal contamination, low wear and tear and good repeatability. So far two laser-based systems viz. Pellet density measurement systems and triangulation sensors have been developed. Laser based fuel pellet inspection system and PHWR fuel bundle metric station are under development. Machine vision-based systems have been developed to overcome certain limitations when inspection has to be carried out on such a large scale manually. These deficiencies arise from limitations of resolution, accessibility, fatigue and absence of quantification ability. These problems get further compounded in inspection of fuel components because of their relatively small sizes, close tolerances required and the reflective surfaces. PC based vision system has been developed for inspecting components and fuel assemblies. The paper would touch upon the details of the various laser systems and vision systems that have been indigenously developed for PHWR Fuel Metrology and their impact on the assembly production line. (author)

  12. Post-Closure Inspection Report for Corrective Action Unit 427: Septic Waste Systems 2 and 6 Tonopah Test Range, Nevada Calendar Year 2000; TOPICAL

    International Nuclear Information System (INIS)

    K. B. Campbell

    2001-01-01

    Post-closure inspection requirements for the Area 3 Septic Waste Systems 2 and 6 (Corrective Action Unit[CAU] 427) (Figure 1) are described in Closure Report for Corrective Action Unit 427. Area 3 Septic Waste Systems 2 and 6. Tonopah Test Range, Nevada, report number DOE/NV-561. The Closure Report (CR) was submitted to the Nevada Division of Environmental Protection (NDEP) on August 16, 1999. The CR (containing the Post-Closure Inspection Plan) was approved by the NDEP on August 27, 1999. The annual post-closure inspection at CAU 427 consists of the following: Verification of the presence of all leachfield and septic tank below-grade markers; Verification that the warning signs are in-place, intact, and readable; and Visual observation of the soil and asphalt cover for indications of subsidence, erosion, and unauthorized use. The site inspections were conducted on June 20, 2000, and November 21, 2000. All inspections were made after NDEP approval of the CR and were conducted in accordance with the Post-Closure Inspection Plan in the NDEP-approved CR. No maintenance or repairs were conducted at the site. This report includes copies of inspection checklists, photographs, recommendations, and conclusions. Copies of the Post-Closure Inspection Checklists are found in Attachment A, a copy of the field notes is found in Attachment B, and a copy of the inspection photographs is found in Attachments C

  13. ASME development of risk-based inspection guidelines for nuclear power plants

    International Nuclear Information System (INIS)

    Gore, B.F.; Balkey, K.R.

    1992-08-01

    A methodology has been developed for use in preparing guidelines for the in-service inspection of nuclear power plant pressure boundary and structural components. This methodology is a further development of a general methodology previously published by the task force for application to any industry. It is unique in that it utilizes probabilistic risk assessment (PRA) information to improve the quantification of risks associated with component ruptures. A procedure has also been recommended for using the resulting quantified risk estimates to determine target component rupture probability values to be maintained by inspection activities. Characteristics which an inspection strategy must possess in order to maintain target rupture probabilities are being determined by structural risk and reliability analysis (SRRA) calculations. The major features of this methodology are described in this paper, and example applications are briefly discussed. Plans for additional work in developing and applying the methodology are described

  14. Technical regulation of nondestructive inspection

    International Nuclear Information System (INIS)

    1995-01-01

    It starts with the explanation of definition of nondestructive inspection and qualifications for a inspection. It lists the technical regulations of nondestructive inspections which are radiographic testing, ultrasonic flaw detecting test, liquid penetrant test, magnetic particle inspection, eddy current test visual inspection and leakage test.

  15. Development of the radiation inspection system for food materials

    Energy Technology Data Exchange (ETDEWEB)

    Min, Sujung; Kim, Heeyoung; Kim, Myungjin; Lee, Unjang [ORIONENC Co., Seoul (Korea, Republic of)

    2015-10-15

    Radioactive contamination of processed foodstuffs, livestock, marine products, farm products imported from Japan and fishes caught in coastal waters of Korea has become an important social issue. Recently, there are also needs of inspection system for monitoring of public meals such like school feedings of kindergarten, elementary school, middle school, high school and university. Radioactivity inspections of those foods are executed manually with portable measuring instruments or at labs using their samples. But, radioactivity inspections of those foods should execute field survey in real time. In consequence, there are some problem of time delay and low reliability. To protect the health of citizens from radioactivity contained in Japanese marine products imported to Korea, a system to inspect radioactivity in real time is developed. The system is to measure the radioactivity level of farm and marine products and public meals continuously and automatically at inspection sites of an agency checking radiation of imported foodstuffs to determine radioactive contamination. Performance was identified through the performance test (Cs-137 30, 50, 300, 900Bq/kg) at Korea Research Institute of Standards and Science (KRISS). NaI(Tl) detector was satisfied the performance for measurement.

  16. Development of the radiation inspection system for food materials

    International Nuclear Information System (INIS)

    Min, Sujung; Kim, Heeyoung; Kim, Myungjin; Lee, Unjang

    2015-01-01

    Radioactive contamination of processed foodstuffs, livestock, marine products, farm products imported from Japan and fishes caught in coastal waters of Korea has become an important social issue. Recently, there are also needs of inspection system for monitoring of public meals such like school feedings of kindergarten, elementary school, middle school, high school and university. Radioactivity inspections of those foods are executed manually with portable measuring instruments or at labs using their samples. But, radioactivity inspections of those foods should execute field survey in real time. In consequence, there are some problem of time delay and low reliability. To protect the health of citizens from radioactivity contained in Japanese marine products imported to Korea, a system to inspect radioactivity in real time is developed. The system is to measure the radioactivity level of farm and marine products and public meals continuously and automatically at inspection sites of an agency checking radiation of imported foodstuffs to determine radioactive contamination. Performance was identified through the performance test (Cs-137 30, 50, 300, 900Bq/kg) at Korea Research Institute of Standards and Science (KRISS). NaI(Tl) detector was satisfied the performance for measurement

  17. Quality and Improvement in Scottish Education: Trends in Inspection Findings 2008-2011

    Science.gov (United States)

    Education Scotland, 2012

    2012-01-01

    The findings of Education Scotland's sectoral programme of inspections, which sample the providers of education at every stage from the early years to adult learning, provide a key source of evidence on how effectively one of its core public services is performing. The last published summary of inspection findings was produced in 2009 when Her…

  18. Amchitka Mud Pit Sites 2006 Post-Closure Monitoring and Inspection Report, Amchitka Island, Alaska, Rev. No.: 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick

    2006-09-01

    In 2001, the U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA/NSO) remediated six areas associated with Amchitka mud pit release sites located on Amchitka Island, Alaska. This included the construction of seven closure caps. To ensure the integrity and effectiveness of remedial action, the mud pit sites are to be inspected every five years as part of DOE's long-term monitoring and surveillance program. In August of 2006, the closure caps were inspected in accordance with the ''Post-Closure Monitoring and Inspection Plan for Amchitka Island Mud Pit Release Sites'' (Rev. 0, November 2005). This post-closure monitoring report provides the 2006 cap inspection results.

  19. Evaluation of flaw characteristics and their influence on inservice inspection reliability

    International Nuclear Information System (INIS)

    Becker, F.L.

    1980-01-01

    This report describes the results of the first year's effort of a five year program which is being conducted by Battelle, Pacific Northwest Laboratories, on behalf of the US Nuclear Regulatory Commission. This initial effort was directed toward identification and quantification of inspection uncertainties, which are likely to occur during inservice inspection of LWR primary piping systems, and their influence on inspection reliability. These experiments were conducted on 304 stainless steel samples, however, the results are equally applicable to other materials. Later portions of the program will extend these measurements and evaluations to other materials and conditions

  20. Pipeline rehabilitation planning

    Energy Technology Data Exchange (ETDEWEB)

    Palmer-Jones, Roland; Hopkins, Phil; Eyre, David [PENSPEN (United Kingdom)

    2005-07-01

    An operator faced with an onshore pipeline that has extensive damage must consider the need for rehabilitation, the sort of rehabilitation to be used, and the rehabilitation schedule. This paper will consider pipeline rehabilitation based on the authors' experiences from recent projects, and recommend a simple strategy for planning pipeline rehabilitation. It will also consider rehabilitation options: external re-coating; internal lining; internal painting; programmed repairs. The main focus will be external re-coating. Consideration will be given to rehabilitation coating types, including tape wraps, epoxy, and polyurethane. Finally it will discuss different options for scheduling the rehabilitation of corrosion damage including: the statistical comparison of signals from inspection pigs; statistical comparison of selected measurements from inspection pigs and other inspections; the use of corrosion rates estimated for the mechanisms and conditions; expert judgement. (author)

  1. Experimental modeling of eddy current inspection capabilities

    International Nuclear Information System (INIS)

    Junker, W.R.; Clark, W.G.

    1984-01-01

    This chapter examines the experimental modeling of eddy current inspection capabilities based upon the use of liquid mercury samples designed to represent metal components containing discontinuities. A brief summary of past work with mercury modeling and a detailed discussion of recent experiments designed to further evaluate the technique are presented. The main disadvantages of the mercury modeling concept are that mercury is toxic and must be handled carefully, liquid mercury can only be used to represent nonferromagnetic materials, and wetting and meniscus problems can distort the effective size of artificial discontinuities. Artificial discontinuities placed in a liquid mercury sample can be used to represent discontinuities in solid metallic structures. Discontinuity size and type cannot be characterized from phase angle and signal amplitude data developed with a surface scanning, pancake-type eddy current probe. It is concluded that the mercury model approach can greatly enhance the overall understanding and applicability of eddy current inspection techniques

  2. Machine vision method for online surface inspection of easy open can ends

    Science.gov (United States)

    Mariño, Perfecto; Pastoriza, Vicente; Santamaría, Miguel

    2006-10-01

    Easy open can end manufacturing process in the food canning sector currently makes use of a manual, non-destructive testing procedure to guarantee can end repair coating quality. This surface inspection is based on a visual inspection made by human inspectors. Due to the high production rate (100 to 500 ends per minute) only a small part of each lot is verified (statistical sampling), then an automatic, online, inspection system, based on machine vision, has been developed to improve this quality control. The inspection system uses a fuzzy model to make the acceptance/rejection decision for each can end from the information obtained by the vision sensor. In this work, the inspection method is presented. This surface inspection system checks the total production, classifies the ends in agreement with an expert human inspector, supplies interpretability to the operators in order to find out the failure causes and reduce mean time to repair during failures, and allows to modify the minimum can end repair coating quality.

  3. Optimal sampling plan for clean development mechanism energy efficiency lighting projects

    International Nuclear Information System (INIS)

    Ye, Xianming; Xia, Xiaohua; Zhang, Jiangfeng

    2013-01-01

    Highlights: • A metering cost minimisation model is built to assist the sampling plan for CDM projects. • The model minimises the total metering cost by the determination of optimal sample size. • The required 90/10 criterion sampling accuracy is maintained. • The proposed metering cost minimisation model is applicable to other CDM projects as well. - Abstract: Clean development mechanism (CDM) project developers are always interested in achieving required measurement accuracies with the least metering cost. In this paper, a metering cost minimisation model is proposed for the sampling plan of a specific CDM energy efficiency lighting project. The problem arises from the particular CDM sampling requirement of 90% confidence and 10% precision for the small-scale CDM energy efficiency projects, which is known as the 90/10 criterion. The 90/10 criterion can be met through solving the metering cost minimisation problem. All the lights in the project are classified into different groups according to uncertainties of the lighting energy consumption, which are characterised by their statistical coefficient of variance (CV). Samples from each group are randomly selected to install power meters. These meters include less expensive ones with less functionality and more expensive ones with greater functionality. The metering cost minimisation model will minimise the total metering cost through the determination of the optimal sample size at each group. The 90/10 criterion is formulated as constraints to the metering cost objective. The optimal solution to the minimisation problem will therefore minimise the metering cost whilst meeting the 90/10 criterion, and this is verified by a case study. Relationships between the optimal metering cost and the population sizes of the groups, CV values and the meter equipment cost are further explored in three simulations. The metering cost minimisation model proposed for lighting systems is applicable to other CDM projects as

  4. Post-Closure Inspection Report for the Tonopah Test Range, Nevada. For Calendar Year 2015, Revision 0

    International Nuclear Information System (INIS)

    Matthews, Patrick; Petrello, Jaclyn

    2016-01-01

    This report provides the results of the annual post-closure inspections conducted at the closed corrective action units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2015 and includes inspection and repair activities completed at the following CAUs; CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved closure reports and subsequent correspondence with the Nevada Division of Environmental Protection. The post-closure inspection plans and subsequent correspondence modifying the requirements for each CAU are included in Appendix B. The inspection checklists are included in Appendix C. Field notes are included in Appendix D. The annual post-closure inspections were conducted on May 12, 2015. Maintenance was required at CAU 453. Cracking along the north trench was repaired. One monument is missing at CAU 424; it will be replaced in 2016. Postings at CAUs 407, 424, 453, and 487 contain contact information for TTR Security. It was noted that protocols may not be in place to ensure that the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) is notified if access is needed at these sites. NNSA/NFO is working with the U.S. Air Force and Sandia to determine whether more appropriate contact information or new protocols are warranted for each CAU. Based on these inspections, there has not been a significant change in vegetation, and vegetation monitoring was not recommended at CAU 400 or CAU 407 in 2015.

  5. Post-Closure Inspection Report for the Tonopah Test Range, Nevada. For Calendar Year 2015, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick [Navarro, Las Vegas, NV (United States); Petrello, Jaclyn [Navarro, Las Vegas, NV (United States)

    2016-03-01

    This report provides the results of the annual post-closure inspections conducted at the closed corrective action units (CAUs) located on the Tonopah Test Range (TTR), Nevada. This report covers calendar year 2015 and includes inspection and repair activities completed at the following CAUs; CAU 400: Bomblet Pit and Five Points Landfill (TTR); CAU 407: Roller Coaster RadSafe Area (TTR); CAU 424: Area 3 Landfill Complexes (TTR); CAU 453: Area 9 UXO Landfill (TTR); and CAU 487: Thunderwell Site (TTR) Inspections were conducted according to the post-closure plans in the approved closure reports and subsequent correspondence with the Nevada Division of Environmental Protection. The post-closure inspection plans and subsequent correspondence modifying the requirements for each CAU are included in Appendix B. The inspection checklists are included in Appendix C. Field notes are included in Appendix D. The annual post-closure inspections were conducted on May 12, 2015. Maintenance was required at CAU 453. Cracking along the north trench was repaired. One monument is missing at CAU 424; it will be replaced in 2016. Postings at CAUs 407, 424, 453, and 487 contain contact information for TTR Security. It was noted that protocols may not be in place to ensure that the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) is notified if access is needed at these sites. NNSA/NFO is working with the U.S. Air Force and Sandia to determine whether more appropriate contact information or new protocols are warranted for each CAU. Based on these inspections, there has not been a significant change in vegetation, and vegetation monitoring was not recommended at CAU 400 or CAU 407 in 2015.

  6. Hygiene inspections on passenger ships in Europe - an overview

    Directory of Open Access Journals (Sweden)

    Bartlett Christopher LR

    2010-03-01

    Full Text Available Abstract Background Hygiene inspections on passenger ships are important for the prevention of communicable diseases. The European Union (EU countries conduct hygiene inspections on passenger ships in order to ensure that appropriate measures have been taken to eliminate potential sources of contamination which could lead to the spread of communicable diseases. This study was implemented within the framework of the EU SHIPSAN project and it investigates the legislation applied and practices of hygiene inspections of passenger ships in the EU Member States (MS and European Free Trade Association countries. Methods Two questionnaires were composed and disseminated to 28 countries. A total of 92 questionnaires were completed by competent authorities responsible for hygiene inspections (n = 48 and the creation of legislation (n = 44; response rates were 96%, and 75.9%, respectively. Results Out of the 48 responding authorities responsible for hygiene inspections, a routine programme was used by 19 (39.6% of these to conduct inspections of ships on national voyages and by 26 (54.2% for ships on international voyages. Standardised inspection forms are used by 59.1% of the authorities. A scoring inspection system is applied by five (11.6% of the 43 responding authorities. Environmental sampling is conducted by 84.1% of the authorities (37 out of 44. The inspection results are collected and analysed by 54.5% (24 out of 44 of the authorities, while 9 authorities (20.5% declared that they publish the results. Inspections are conducted during outbreak investigations by 75% and 70.8% of the authorities, on ships on national and international voyages, respectively. A total of 31 (64.6% and 39 (81.3% authorities conducted inspections during complaint investigations on ships on international and on national voyages, respectively. Port-to-port communication between the national port authorities was reported by 35.4% (17 out of 48 of the responding authorities

  7. Hygiene inspections on passenger ships in Europe - an overview.

    Science.gov (United States)

    Mouchtouri, Varvara A; Westacott, Sandra; Nichols, Gordon; Riemer, Tobias; Skipp, Mel; Bartlett, Christopher L R; Kremastinou, Jenny; Hadjichristodoulou, Christos

    2010-03-10

    Hygiene inspections on passenger ships are important for the prevention of communicable diseases. The European Union (EU) countries conduct hygiene inspections on passenger ships in order to ensure that appropriate measures have been taken to eliminate potential sources of contamination which could lead to the spread of communicable diseases. This study was implemented within the framework of the EU SHIPSAN project and it investigates the legislation applied and practices of hygiene inspections of passenger ships in the EU Member States (MS) and European Free Trade Association countries. Two questionnaires were composed and disseminated to 28 countries. A total of 92 questionnaires were completed by competent authorities responsible for hygiene inspections (n = 48) and the creation of legislation (n = 44); response rates were 96%, and 75.9%, respectively. Out of the 48 responding authorities responsible for hygiene inspections, a routine programme was used by 19 (39.6%) of these to conduct inspections of ships on national voyages and by 26 (54.2%) for ships on international voyages. Standardised inspection forms are used by 59.1% of the authorities. A scoring inspection system is applied by five (11.6%) of the 43 responding authorities. Environmental sampling is conducted by 84.1% of the authorities (37 out of 44). The inspection results are collected and analysed by 54.5% (24 out of 44) of the authorities, while 9 authorities (20.5%) declared that they publish the results. Inspections are conducted during outbreak investigations by 75% and 70.8% of the authorities, on ships on national and international voyages, respectively. A total of 31 (64.6%) and 39 (81.3%) authorities conducted inspections during complaint investigations on ships on international and on national voyages, respectively. Port-to-port communication between the national port authorities was reported by 35.4% (17 out of 48) of the responding authorities and 20.8% (10 out of 48) of the port

  8. Hygiene inspections on passenger ships in Europe - an overview

    Science.gov (United States)

    2010-01-01

    Background Hygiene inspections on passenger ships are important for the prevention of communicable diseases. The European Union (EU) countries conduct hygiene inspections on passenger ships in order to ensure that appropriate measures have been taken to eliminate potential sources of contamination which could lead to the spread of communicable diseases. This study was implemented within the framework of the EU SHIPSAN project and it investigates the legislation applied and practices of hygiene inspections of passenger ships in the EU Member States (MS) and European Free Trade Association countries. Methods Two questionnaires were composed and disseminated to 28 countries. A total of 92 questionnaires were completed by competent authorities responsible for hygiene inspections (n = 48) and the creation of legislation (n = 44); response rates were 96%, and 75.9%, respectively. Results Out of the 48 responding authorities responsible for hygiene inspections, a routine programme was used by 19 (39.6%) of these to conduct inspections of ships on national voyages and by 26 (54.2%) for ships on international voyages. Standardised inspection forms are used by 59.1% of the authorities. A scoring inspection system is applied by five (11.6%) of the 43 responding authorities. Environmental sampling is conducted by 84.1% of the authorities (37 out of 44). The inspection results are collected and analysed by 54.5% (24 out of 44) of the authorities, while 9 authorities (20.5%) declared that they publish the results. Inspections are conducted during outbreak investigations by 75% and 70.8% of the authorities, on ships on national and international voyages, respectively. A total of 31 (64.6%) and 39 (81.3%) authorities conducted inspections during complaint investigations on ships on international and on national voyages, respectively. Port-to-port communication between the national port authorities was reported by 35.4% (17 out of 48) of the responding authorities and 20.8% (10 out

  9. Benchmarking on Inspection Practices. First Triennial Report of the Working Group on Inspection Practices

    International Nuclear Information System (INIS)

    2017-01-01

    The WGIP Nuclear Power Plant (NPP) Observed Inspection Practices Program is intended to promote co-operation and learning among member countries and to collect and provide them with information for improving the effectiveness of existing regulatory inspection practices. This is accomplished by observing how inspections are carried out by other member countries and issuing a WGIP observed inspection report that includes observations (e.g. inspection techniques, obstacles encountered), lessons learnt and potential commendable practices that could be used by a regulatory body. This first triennial report documents the results of a consistency check performed between all six WGIP observed inspection reports and ratifies certain observations, lessons learnt and potential commendable practices identified by WGIP observed inspection participants

  10. A pilot application of risk-based methods to establish in-service inspection priorities for nuclear components at Surry Unit 1 Nuclear Power Station

    International Nuclear Information System (INIS)

    Vo, T.; Gore, B.; Simonen, F.; Doctor, S.

    1994-08-01

    As part of the Nondestructive Evaluation Reliability Program sponsored by the US Nuclear Regulatory Commission, the Pacific Northwest Laboratory is developing a method that uses risk-based approaches to establish in-service inspection plans for nuclear power plant components. This method uses probabilistic risk assessment (PRA) results and Failure Modes and Effects Analysis (FEMA) techniques to identify and prioritize the most risk-important systems and components for inspection. The Surry Nuclear Power Station Unit 1 was selected for pilot applications of this method. The specific systems addressed in this report are the reactor pressure vessel, the reactor coolant, the low-pressure injection, and the auxiliary feedwater. The results provide a risk-based ranking of components within these systems and relate the target risk to target failure probability values for individual components. These results will be used to guide the development of improved inspection plans for nuclear power plants. To develop inspection plans, the acceptable level of risk from structural failure for important systems and components will be apportioned as a small fraction (i.e., 5%) of the total PRA-estimated risk for core damage. This process will determine target (acceptable) risk and target failure probability values for individual components. Inspection requirements will be set at levels to assure that acceptable failure probabilistics are maintained

  11. Health plan auditing: 100-percent-of-claims vs. random-sample audits.

    Science.gov (United States)

    Sillup, George P; Klimberg, Ronald K

    2011-01-01

    The objective of this study was to examine the relative efficacy of two different methodologies for auditing self-funded medical claim expenses: 100-percent-of-claims auditing versus random-sampling auditing. Multiple data sets of claim errors or 'exceptions' from two Fortune-100 corporations were analysed and compared to 100 simulated audits of 300- and 400-claim random samples. Random-sample simulations failed to identify a significant number and amount of the errors that ranged from $200,000 to $750,000. These results suggest that health plan expenses of corporations could be significantly reduced if they audited 100% of claims and embraced a zero-defect approach.

  12. Pipe degradation investigations for optimization of flow-accelerated corrosion inspection location selection

    International Nuclear Information System (INIS)

    Chandra, S.; Habicht, P.; Chexal, B.; Mahini, R.; McBrine, W.; Esselman, T.; Horowitz, J.

    1995-01-01

    A large amount of piping in a typical nuclear power plant is susceptible to Flow-Accelerated Corrosion (FAC) wall thinning to varying degrees. A typical PAC monitoring program includes the wall thickness measurement of a select number of components in order to judge the structural integrity of entire systems. In order to appropriately allocate resources and maintain an adequate FAC program, it is necessary to optimize the selection of components for inspection by focusing on those components which provide the best indication of system susceptibility to FAC. A better understanding of system FAC predictability and the types of FAC damage encountered can provide some of the insight needed to better focus and optimize the inspection plan for an upcoming refueling outage. Laboratory examination of FAC damaged components removed from service at Northeast Utilities' (NU) nuclear power plants provides a better understanding of the damage mechanisms involved and contributing causes. Selected results of this ongoing study are presented with specific conclusions which will help NU to better focus inspections and thus optimize the ongoing FAC inspection program

  13. Application of risk-based methods for inspection of nuclear power plant components

    International Nuclear Information System (INIS)

    Balkey, K.R.

    1992-01-01

    In-service inspections (ISIs) can play a significant role in minimizing equipment and structural failures. All aspects of inspections, i.e., objectives, method, timing, and the acceptance criteria for detected flaws can affect the probability of component failure. Where ISI programs exist, they are primarily based on prior experience and engineering judgment. At best, some include an implicit consideration of risk (probability of failure multiplied by consequence). Since late 1988, a multidisciplined American Society of Mechanical Engineers (ASME) Research Task Force on Risk-Based Inspection Guidelines has been addressing the general question of how to formally incorporate risk considerations into plans and requirements for the ISI of components and structural systems. The task force and steering committee that guided the project have concluded that appropriate analytical methods exist for evaluating and quantifying risks associated with pressure boundary and structural failures. With the support of about a dozen industry and government organizations, the research group has recommended a general methodology for establishing a risk-based inspection program that could be applied to any nuclear system or structural system

  14. Reliability Assessment and Reliability-Based Inspection and Maintenance of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Ramirez, José Rangel

    actions are the most relevant and effective means of control of deterioration. The risk-based inspection planning methodology, based on Bayesian decision theory, represents an important tool to identify the suitable strategy to inspect and control the deterioration in structures such as offshore wind...... performance during the life cycle. The deterioration processes, such as fatigue and corrosion, are typically affecting offshore structural systems. This damage decreases the system performance and increases the risk of failure, thus not fulfilling the established safety criteria. Inspection and maintenance...... to their offshore location, no pollution risks and low human risks since they are unmanned. This allows the allocation of lower reliability level compared to e.g. oil & gas installations. With the incursion to water depths between 20 and 50 meters, the use of jacket and tripod structures represents a feasible...

  15. Development of an accelerator for X-ray inspection apparatus with high clairvoyance

    CERN Document Server

    Onishi, T

    2002-01-01

    At present, there is no portable X-ray generator usable for non-destructive inspection of thick concretes used for bridges, and so on. To enable on non-destructive inspection of such thick concrete materials with more than 300 mm in thickness, authors developed a new small size accelerator with same acceleration principle as that of betatron. And, the authors also developed two types of new induction accelerators such as 'spiral orbit type' and 'cylindrical type'. Furthermore, development of a detector with excellent sensitivity to X-ray with wavelength suitable for inspection and software for image processing are planned. Here was described acceleration principles of new accelerators, test results on prototypes of the accelerators, and development states on field emission array considering new electron gun alternating thermal one and cold cathode type electron gun using carbon nano-tubes. (G.K.)

  16. Compatibility grab sampling and analysis plan for fiscal year 1999

    International Nuclear Information System (INIS)

    SASAKI, L.M.

    1999-01-01

    This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for grab samples obtained to address waste compatibility. Analytical requirements are taken from two revisions of the Compatibility data quality objectives (DQOs). Revision 1 of the DQO (Fowler 1995) listed analyses to be performed to meet both safety and operational data needs for the Compatibility program. Revision 2A of the DQO (Mulkey and Miller 1998) addresses only the safety-related requirements; the operational requirements of Fowler (1995) have not been superseded by Mulkey and Miller (1998). Therefore, safety-related data needs are taken from Mulkey and Miller (1998) and operational-related data needs are taken from Fowler (1995). Ammonia and total alpha analyses are also performed in accordance with Fowler (1998a, 1998b)

  17. Crack characterization for in-service inspection planning

    International Nuclear Information System (INIS)

    Waale, J.; Ekstroem, P.

    1995-12-01

    During in-service inspection by non destructive testing the reliability is highly dependent on how the equipment is adjusted to the specific object and to the anticipated crack feature.The crack feature and morphology vary widely between different cracking mechanisms and between material types in which the cracks appear. The major objective of this study was to characterize a number of morphology parameters for common crack mechanism and structure material combinations. Critical morphology parameters are crack orientation, shape, width, surface roughness and branching. The crack parameters were evaluated from failure analyses reported from the nuclear and non-nuclear industry. In addition, a literature review was carried out on crack parameter reports and on failure analysis reports, which were further evaluated. The evaluated crack parameters were plotted and statistically processed in data groups with respect to crack mechanism and material type. The fatigue crack mechanism were classified as mechanical, thermal or corrosion fatigue and stress corrosion crack mechanism as intergranular, transgranular or inter dendritic stress corrosion cracking. Furthermore, some common weld defects were characterized for comparison. The materials were divided into three broad groups, ferritic low alloy steels, stainless steels and nickel base alloys. The results indicate significant differences between crack parameters when comparing data from different crack mechanism/material type combinations. Typical parameter values and scatter were derived for several combinations where the data was sufficient for statistical significance. 10 refs, 105 figs, 14 tabs

  18. Crack characterization for in-service inspection planning

    Energy Technology Data Exchange (ETDEWEB)

    Waale, J [SAQ Inspection Ltd, Stockholm (Sweden); Ekstroem, P [ABB Atom AB, Vaesteraas (Sweden)

    1995-12-01

    During in-service inspection by non destructive testing the reliability is highly dependent on how the equipment is adjusted to the specific object and to the anticipated crack feature.The crack feature and morphology vary widely between different cracking mechanisms and between material types in which the cracks appear. The major objective of this study was to characterize a number of morphology parameters for common crack mechanism and structure material combinations. Critical morphology parameters are crack orientation, shape, width, surface roughness and branching. The crack parameters were evaluated from failure analyses reported from the nuclear and non-nuclear industry. In addition, a literature review was carried out on crack parameter reports and on failure analysis reports, which were further evaluated. The evaluated crack parameters were plotted and statistically processed in data groups with respect to crack mechanism and material type. The fatigue crack mechanism were classified as mechanical, thermal or corrosion fatigue and stress corrosion crack mechanism as intergranular, transgranular or inter dendritic stress corrosion cracking. Furthermore, some common weld defects were characterized for comparison. The materials were divided into three broad groups, ferritic low alloy steels, stainless steels and nickel base alloys. The results indicate significant differences between crack parameters when comparing data from different crack mechanism/material type combinations. Typical parameter values and scatter were derived for several combinations where the data was sufficient for statistical significance. 10 refs, 105 figs, 14 tabs.

  19. Inspection, maintenance, and repair of large pumps and piping systems using advanced robotic tools

    International Nuclear Information System (INIS)

    Lewis, R.K.; Radigan, T.M.

    1998-01-01

    Operating and maintaining large pumps and piping systems can be an expensive proposition. Proper inspections and monitoring can reduce costs. This was difficult in the past, since detailed pump inspections could only be performed by disassembly and many portions of piping systems are buried or covered with insulation. Once these components were disassembled, a majority of the cost was already incurred. At that point, expensive part replacement usually took place whether it was needed or not. With the completion of the Pipe Walkertrademark/LIP System and the planned development of the Submersible Walkertrademark, this situation is due to change. The specifications for these inspection and maintenance robots will ensure that. Their ability to traverse both horizontal and vertical, forward and backward, make them unique tools. They will open the door for some innovative approaches to inspection and maintenance of large pumps and piping systems

  20. Evaluation of piping reliability and failure data for use in risk-based inspections of nuclear power plants

    International Nuclear Information System (INIS)

    Vasconcelos, V. de; Soares, W.A.; Costa, A.C.L. da; Rabello, E.G.; Marques, R.O.

    2016-01-01

    During operation of industrial facilities, components and systems can deteriorate over time, thus increasing the possibility of accidents. Risk-Based Inspection (RBI) involves inspection planning based on information about risks, through assessing of probability and consequence of failures. In-service inspections are used in nuclear power plants, in order to ensure reliable and safe operation. Traditional deterministic inspection approaches investigate generic degradation mechanisms on all systems. However, operating experience indicates that degradation occurs where there are favorable conditions for developing a specific mechanism. Inspections should be prioritized at these places. Risk-Informed In-service Inspections (RI-ISI) are types of RBI that use Probabilistic Safety Assessment results, increasing reliability and plant safety, and reducing radiation exposure. These assessments use both available generic reliability and failure data, as well as plant specific information. This paper proposes a method for evaluating piping reliability and failure data important for RI-ISI programs, as well as the techniques involved. (author)