WorldWideScience

Sample records for cercla remedial investigation

  1. RCRA corrective action ampersand CERCLA remedial action reference guide

    International Nuclear Information System (INIS)

    1994-07-01

    This reference guide provides a side-by-side comparison of RCRA corrective action and CERCLA Remedial Action, focusing on the statutory and regulatory requirements under each program, criterial and other factors that govern a site's progress, and the ways in which authorities or requirements under each program overlap and/or differ. Topics include the following: Intent of regulation; administration; types of sites and/or facilities; definition of site and/or facility; constituents of concern; exclusions; provisions for short-term remedies; triggers for initial site investigation; short term response actions; site investigations; remedial investigations; remedial alternatives; clean up criterial; final remedy; implementing remedy; on-site waste management; completion of remedial process

  2. Integrating NEPA (National Environmental Policy Act) and CERCLA (Comprehensive Environmental Response, Compensation, and Liability Act) requirements during remedial responses at DOE facilities

    Energy Technology Data Exchange (ETDEWEB)

    Levine, M.B.; Smith, E.D.; Sharples, F.E.; Eddlemon, G.K.

    1990-07-01

    US Department of Energy (DOE) Order 5400.4, issued October 6, 1989, calls for integrating the requirements of the National Environmental Policy Act (NEPA) with those of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for DOE remedial actions under CERCLA. CERCLA requires that decisions on site remediation be made through a formal process called a Remedial Investigation/Feasibility Study (RI/FS). According to the DOE order, integration is to be accomplished by conducting the NEPA and CERCLA environmental planning and review procedures concurrently. The primary instrument for integrating the processes is to be the RI/FS process, which will be supplemented as needed to meet the procedural and documentational requirements of NEPA. The final product of the integrated process will be a single, integrated set of documents; namely, an RI report and an FS-EIS that satisfy the requirements of both NEPA and CERCLA. The contents of the report include (1) an overview and comparison of the requirements of the two processes; (2) descriptions of the major tasks included in the integrated RI/FS-EIS process; (3) recommended contents for integrated RI/FS-EIS documents; and (4)a discussion of some potential problems in integrating NEPA and CERCLA that fall outisde the scope of the RI/FS-EIS process, with suggestions for resolving some of these problems. 15 refs.

  3. Integrating NEPA [National Environmental Policy Act] and CERCLA [Comprehensive Environmental Response, Compensation, and Liability Act] requirements during remedial responses at DOE facilities

    International Nuclear Information System (INIS)

    Levine, M.B.; Smith, E.D.; Sharples, F.E.; Eddlemon, G.K.

    1990-07-01

    US Department of Energy (DOE) Order 5400.4, issued October 6, 1989, calls for integrating the requirements of the National Environmental Policy Act (NEPA) with those of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for DOE remedial actions under CERCLA. CERCLA requires that decisions on site remediation be made through a formal process called a Remedial Investigation/Feasibility Study (RI/FS). According to the DOE order, integration is to be accomplished by conducting the NEPA and CERCLA environmental planning and review procedures concurrently. The primary instrument for integrating the processes is to be the RI/FS process, which will be supplemented as needed to meet the procedural and documentational requirements of NEPA. The final product of the integrated process will be a single, integrated set of documents; namely, an RI report and an FS-EIS that satisfy the requirements of both NEPA and CERCLA. The contents of the report include (1) an overview and comparison of the requirements of the two processes; (2) descriptions of the major tasks included in the integrated RI/FS-EIS process; (3) recommended contents for integrated RI/FS-EIS documents; and (4)a discussion of some potential problems in integrating NEPA and CERCLA that fall outisde the scope of the RI/FS-EIS process, with suggestions for resolving some of these problems. 15 refs

  4. Cost estimating for CERCLA remedial alternatives a unit cost methodology

    International Nuclear Information System (INIS)

    Brettin, R.W.; Carr, D.J.; Janke, R.J.

    1995-06-01

    The United States Environmental Protection Agency (EPA) Guidance for Conducting Remedial Investigations and Feasibility Studies Under CERCLA, Interim Final, dated October 1988 (EPA 1988) requires a detailed analysis be conducted of the most promising remedial alternatives against several evaluation criteria, including cost. To complete the detailed analysis, order-of-magnitude cost estimates (having an accuracy of +50 percent to -30 percent) must be developed for each remedial alternative. This paper presents a methodology for developing cost estimates of remedial alternatives comprised of various technology and process options with a wide range of estimated contaminated media quantities. In addition, the cost estimating methodology provides flexibility for incorporating revisions to remedial alternatives and achieves the desired range of accuracy. It is important to note that the cost estimating methodology presented here was developed as a concurrent path to the development of contaminated media quantity estimates. This methodology can be initiated before contaminated media quantities are estimated. As a result, this methodology is useful in developing cost estimates for use in screening and evaluating remedial technologies and process options. However, remedial alternative cost estimates cannot be prepared without the contaminated media quantity estimates. In the conduct of the feasibility study for Operable Unit 5 at the Fernald Environmental Management Project (FEMP), fourteen remedial alternatives were retained for detailed analysis. Each remedial alternative was composed of combinations of remedial technologies and processes which were earlier determined to be best suited for addressing the media-specific contaminants found at the FEMP site, and achieving desired remedial action objectives

  5. Guide to ground water remediation at CERCLA response action and RCRA corrective action sites

    International Nuclear Information System (INIS)

    1995-10-01

    This Guide contains the regulatory and policy requirements governing remediation of ground water contaminated with hazardous waste [including radioactive mixed waste (RMW)], hazardous substances, or pollutants/contaminants that present (or may present) an imminent and substantial danger. It was prepared by the Office of Environmental Policy and Assistance, RCRA/CERCLA Division (EH-413), to assist Environmental Program Managers (ERPMs) who often encounter contaminated ground water during the performance of either response actions under CERCLA or corrective actions under Subtitle C of RCRA. The Guide begins with coverage of the regulatory and technical issues that are encountered by ERPM's after a CERCLA Preliminary Assessment/Site Investigation (PA/SI) or the RCRA Facility Assessment (RFA) have been completed and releases into the environment have been confirmed. It is based on the assumption that ground water contamination is present at the site, operable unit, solid waste management unit, or facility. The Guide's scope concludes with completion of the final RAs/corrective measures and a determination by the appropriate regulatory agencies that no further response action is necessary

  6. Remedying CERCLA's natural resource damages provision: Incorporation of the public trust doctrine into natural resource damage actions

    International Nuclear Information System (INIS)

    Chase, A.R.

    1992-01-01

    When Congress enacted the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), it ushered in a sweeping approach to controlling the environmental effects of improper hazardous waste disposal. CERCLA's cleanup provisions, which focus on removal and remediation of hazardous substances from inactive hazardous waste sites, have progressed through more than a decade of litigation and a great deal of public debate. However, CERCLA's natural resource damage provisions have not shared this same degree of progress

  7. Complying with Land Disposal Restrictions (LDR) for CERCLA remedial actions involving contaminated soil and debris

    International Nuclear Information System (INIS)

    Bascietto, J.

    1991-01-01

    CERCLA Sect. 121(e) requires that remedial actions must comply with at least the minimum standards of all ''applicable or relevant and appropriate requirements'' (ARARs) of federal and state laws. EPA has determined that RCRA land disposal restrictions may be ARAR for certain CERCLA remedial actions involving soil and debris. This means that soil and debris contaminated with prohibited or restricted wastes cannot be land disposed if (1) these wastes have not attained the treatment standards set by EPA for a specified waste or (2) have been the subject of a case-by-case extension, national capacity variance, or successful ''no migration'' petition. RCRA LDR treatment standards are based on ''Best Demonstrated Available Technology'' (BDAT), not on health-based concentrations. Because the treatment of the soil and debris matrix presents technological difficulties not yet addressed by EPA (BDAT standards are generally set for industrial process wastes), compliance options such as obtaining a Treatability Variance, are available and will generally be necessary for soil and debris wastes. In the recently promulgated revisions to the National Contingency Plan (NCP) for CERCLA implementation, EPA provides important information for CERCLA project managers regarding LDR compliance, particularly for obtaining a treatability variance for land disposal of contaminated soil and debris

  8. 75 FR 7591 - Guidance on Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA and...

    Science.gov (United States)

    2010-02-22

    ... ENVIRONMENTAL PROTECTION AGENCY [EPA-HQ-SFUND-2009-0907; FRL-9114-6] RIN 2050-ZA05 Guidance on Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA and RCRA Sites; Extension of... Interim Preliminary Remediation Goals for Dioxin in Soil at Comprehensive Environmental Response...

  9. A Cercla-Based Decision Model to Support Remedy Selection for an Uncertain Volume of Contaminants at a DOE Facility

    Energy Technology Data Exchange (ETDEWEB)

    Christine E. Kerschus

    1999-03-31

    The Paducah Gaseous Diffusion Plant (PGDP) operated by the Department of Energy is challenged with selecting the appropriate remediation technology to cleanup contaminants at Waste Area Group (WAG) 6. This research utilizes value-focused thinking and multiattribute preference theory concepts to produce a decision analysis model designed to aid the decision makers in their selection process. The model is based on CERCLA's five primary balancing criteria, tailored specifically to WAG 6 and the contaminants of concern, utilizes expert opinion and the best available engineering, cost, and performance data, and accounts for uncertainty in contaminant volume. The model ranks 23 remediation technologies (trains) in their ability to achieve the CERCLA criteria at various contaminant volumes. A sensitivity analysis is performed to examine the effects of changes in expert opinion and uncertainty in volume. Further analysis reveals how volume uncertainty is expected to affect technology cost, time and ability to meet the CERCLA criteria. The model provides the decision makers with a CERCLA-based decision analysis methodology that is objective, traceable, and robust to support the WAG 6 Feasibility Study. In addition, the model can be adjusted to address other DOE contaminated sites.

  10. A Cercla-Based Decision Model to Support Remedy Selection for an Uncertain Volume of Contaminants at a DOE Facility

    International Nuclear Information System (INIS)

    Christine E. Kerschus

    1999-01-01

    The Paducah Gaseous Diffusion Plant (PGDP) operated by the Department of Energy is challenged with selecting the appropriate remediation technology to cleanup contaminants at Waste Area Group (WAG) 6. This research utilizes value-focused thinking and multiattribute preference theory concepts to produce a decision analysis model designed to aid the decision makers in their selection process. The model is based on CERCLA's five primary balancing criteria, tailored specifically to WAG 6 and the contaminants of concern, utilizes expert opinion and the best available engineering, cost, and performance data, and accounts for uncertainty in contaminant volume. The model ranks 23 remediation technologies (trains) in their ability to achieve the CERCLA criteria at various contaminant volumes. A sensitivity analysis is performed to examine the effects of changes in expert opinion and uncertainty in volume. Further analysis reveals how volume uncertainty is expected to affect technology cost, time and ability to meet the CERCLA criteria. The model provides the decision makers with a CERCLA-based decision analysis methodology that is objective, traceable, and robust to support the WAG 6 Feasibility Study. In addition, the model can be adjusted to address other DOE contaminated sites

  11. Incorporating ecological risk assessment into remedial investigation/feasibility study work plans

    International Nuclear Information System (INIS)

    1994-06-01

    This guidance document (1) provides instructions on preparing the components of an ecological work plan to complement the overall site remedial investigation/feasibility study (RI/FS) work plan and (2) directs the user on how to implement ecological tasks identified in the plan. Under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA), and RI/FS work plan will have to be developed as part of the site-remediation scoping process. Specific guidance on the RI/FS process and the preparation of work plans has been developed by the US Environmental Protection Agency (EPA 1988a). This document provides guidance to US Department of Energy (DOE) staff and contractor personnel for incorporation of ecological information into environmental remediation planning and decision making at CERCLA sites

  12. Incorporating ecological risk assessment into remedial investigation/feasibility study work plans

    Energy Technology Data Exchange (ETDEWEB)

    1994-06-01

    This guidance document (1) provides instructions on preparing the components of an ecological work plan to complement the overall site remedial investigation/feasibility study (RI/FS) work plan and (2) directs the user on how to implement ecological tasks identified in the plan. Under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA), and RI/FS work plan will have to be developed as part of the site-remediation scoping process. Specific guidance on the RI/FS process and the preparation of work plans has been developed by the US Environmental Protection Agency (EPA 1988a). This document provides guidance to US Department of Energy (DOE) staff and contractor personnel for incorporation of ecological information into environmental remediation planning and decision making at CERCLA sites.

  13. Remedial investigation/feasibility study of the Clinch River/Poplar Creek operable unit. Volume 1, main text

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This document is the combined Remedial Investigation/Feasibility Study (RI/FS) Report for the Clinch River/Poplar Creek Operable Unit (CR/PC OU), an off-site OU associated with environmental restoration activities at the U.S. Department of Energy (DOE) Oak Ridge Reservation (ORR). As a result of past, present, and potential future releases of hazardous substances into the environment, the ORR was placed on the National Priorities List in December 1989 (54 FR 48184). Sites on this list must be investigated for possible remedial action, as required by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA, 42 U.S.C. 9601, et seq.). This report documents the findings of the remedial investigation of this OU and the feasibility of potential remedial action alternatives. These studies are authorized by Sect. 117 of CERCLA and were conducted in accordance with the requirements of the National Contingency Plan (40 CFR Part 300). DOE, the U.S. Environmental Protection Agency (EPA), and the Tennessee Department of Environment and Conservation (TDEC) have entered into a Federal Facility Agreement (FFA), as authorized by Sect. 120 of CERCLA and Sects. 3008(h) and 6001 of the Resource Conservation and Recovery Act (RCRA) (42 U.S.C. 6901, et seq.). The purpose of this agreement is to ensure a coordinated and effective response for all environmental restoration activities occurring at the ORR. In addition to other responsibilities, the FFA parties mutually define the OU boundaries, set remediation priorities, establish remedial investigation priorities and strategies, and identify and select remedial actions. A copy of this FFA is available from the DOE Information Resource Center in Oak Ridge, Tennessee.

  14. Remedial investigation/feasibility study of the Clinch River/Poplar Creek operable unit. Volume 1, main text

    International Nuclear Information System (INIS)

    1996-03-01

    This document is the combined Remedial Investigation/Feasibility Study (RI/FS) Report for the Clinch River/Poplar Creek Operable Unit (CR/PC OU), an off-site OU associated with environmental restoration activities at the U.S. Department of Energy (DOE) Oak Ridge Reservation (ORR). As a result of past, present, and potential future releases of hazardous substances into the environment, the ORR was placed on the National Priorities List in December 1989 (54 FR 48184). Sites on this list must be investigated for possible remedial action, as required by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA, 42 U.S.C. 9601, et seq.). This report documents the findings of the remedial investigation of this OU and the feasibility of potential remedial action alternatives. These studies are authorized by Sect. 117 of CERCLA and were conducted in accordance with the requirements of the National Contingency Plan (40 CFR Part 300). DOE, the U.S. Environmental Protection Agency (EPA), and the Tennessee Department of Environment and Conservation (TDEC) have entered into a Federal Facility Agreement (FFA), as authorized by Sect. 120 of CERCLA and Sects. 3008(h) and 6001 of the Resource Conservation and Recovery Act (RCRA) (42 U.S.C. 6901, et seq.). The purpose of this agreement is to ensure a coordinated and effective response for all environmental restoration activities occurring at the ORR. In addition to other responsibilities, the FFA parties mutually define the OU boundaries, set remediation priorities, establish remedial investigation priorities and strategies, and identify and select remedial actions. A copy of this FFA is available from the DOE Information Resource Center in Oak Ridge, Tennessee

  15. Remedial Investigation/Feasibility Study (RI/FS) process, elements and techniques guidance

    Energy Technology Data Exchange (ETDEWEB)

    1993-12-01

    This manual provides detailed guidance on Remedial Investigation/Feasibility Studies (RI/FSs) conducted pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) at Department of Energy (DOE) facilities. The purpose of the RI/FS, to assess the risk posed by a hazardous waste site and to determine the best way to reduce that risk, and its structure (site characterization, risk assessment, screening and detailed analysis of alternatives, etc.) is defined in the National Oil and Hazardous Substances Pollution Contingency Plan (NCP) and further explained in the Environmental Protection Agency`s (EPA`s) Guidance for Conducting Remedial Investigations and Feasibility Studies Under CERCLA (Interim Final) 540/G-89/004, OSWER Directive 9355.3-01, October 1988. Though issued in 1988, the EPA guidance remains an excellent source of information on the conduct and structure of an RI/FS. This document makes use of supplemental RI/FS-related guidance that EPA has developed since its initial document was issued in 1988, incorporates practical lessons learned in more than 12 years of experience in CERCLA hazardous site remediation, and drawing on those lessons, introduces the Streamlined Approach For Environmental Restoration (SAFER), developed by DOE as a way to proceed quickly and efficiently through the RI/FS process at DOE facilities. Thus as its title implies, this guidance is intended to describe in detail the process and component elements of an RI/FS, as well as techniques to manage the RI/FS effectively.

  16. Determinations of TSD facility acceptability under the CERCLA Off-Site Rule

    International Nuclear Information System (INIS)

    1997-06-01

    On September 22, 1993, the US Environmental Protection Agency (EPA) published the ''Off-Site Rule'' to implement section 121(d)(3) of the Comprehensive Environmental Response Compensation and Liability Act (CERCLA). CERCLA section 121(d)(3) requires that wastes generated as a result of remediation activities taken under CERCLA authority and transferred off-site be managed only at facilities that comply with the Resource Conservation and Recovery Act. In 1994, the DOE's Office of Environmental Policy and Assistance (OEPA), RCRA/CERCLA Division (EH-413) published a CERCLA Information Brief titled ''The Off-Site Rule'' which describes the content of the Off-Site Rule and clarifies some of its implications for DOE remedial actions under CERCLA. Additionally, EH-413 published the Guide on Selecting Compliant Off-Site Hazardous Waste Treatment, Storage and Disposal Facilities which provides a regulatory roadmap for accomplishing off-site transfers of environmental restoration and process hazardous waste at DOE facilities in a manner compliant with the Off-Site Rule and other relevant Federal regulations. Those guidance documents concentrate primarily on DOE's perspective as a hazardous waste generator. The purpose of this Information Brief is to address the implications of the Off-Site Rule for DOE-owned hazardous waste treatment, storage or disposal facilities that accept CERCLA remediation wastes from off-site locations

  17. Remedial investigation/feasibility study of the Clinch River/Poplar Creek operable unit. Volume 1: Main text

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the US Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  18. Reference manual for toxicity and exposure assessment and risk characterization. CERCLA Baseline Risk Assessment

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-03-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA, 1980) (CERCLA or Superfund) was enacted to provide a program for identifying and responding to releases of hazardous substances into the environment. The Superfund Amendments and Reauthorization Act (SARA, 1986) was enacted to strengthen CERCLA by requiring that site clean-ups be permanent, and that they use treatments that significantly reduce the volume, toxicity, or mobility of hazardous pollutants. The National Oil and Hazardous Substances Pollution Contingency Plan (NCP) (USEPA, 1985; USEPA, 1990) implements the CERCLA statute, presenting a process for (1) identifying and prioritizing sites requiring remediation and (2) assessing the extent of remedial action required at each site. The process includes performing two studies: a Remedial Investigation (RI) to evaluate the nature, extent, and expected consequences of site contamination, and a Feasibility Study (FS) to select an appropriate remedial alternative adequate to reduce such risks to acceptable levels. An integral part of the RI is the evaluation of human health risks posed by hazardous substance releases. This risk evaluation serves a number of purposes within the overall context of the RI/FS process, the most essential of which is to provide an understanding of ``baseline`` risks posed by a given site. Baseline risks are those risks that would exist if no remediation or institutional controls are applied at a site. This document was written to (1) guide risk assessors through the process of interpreting EPA BRA policy and (2) help risk assessors to discuss EPA policy with regulators, decision makers, and stakeholders as it relates to conditions at a particular DOE site.

  19. Reference manual for toxicity and exposure assessment and risk characterization. CERCLA Baseline Risk Assessment

    International Nuclear Information System (INIS)

    1995-03-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA, 1980) (CERCLA or Superfund) was enacted to provide a program for identifying and responding to releases of hazardous substances into the environment. The Superfund Amendments and Reauthorization Act (SARA, 1986) was enacted to strengthen CERCLA by requiring that site clean-ups be permanent, and that they use treatments that significantly reduce the volume, toxicity, or mobility of hazardous pollutants. The National Oil and Hazardous Substances Pollution Contingency Plan (NCP) (USEPA, 1985; USEPA, 1990) implements the CERCLA statute, presenting a process for (1) identifying and prioritizing sites requiring remediation and (2) assessing the extent of remedial action required at each site. The process includes performing two studies: a Remedial Investigation (RI) to evaluate the nature, extent, and expected consequences of site contamination, and a Feasibility Study (FS) to select an appropriate remedial alternative adequate to reduce such risks to acceptable levels. An integral part of the RI is the evaluation of human health risks posed by hazardous substance releases. This risk evaluation serves a number of purposes within the overall context of the RI/FS process, the most essential of which is to provide an understanding of ''baseline'' risks posed by a given site. Baseline risks are those risks that would exist if no remediation or institutional controls are applied at a site. This document was written to (1) guide risk assessors through the process of interpreting EPA BRA policy and (2) help risk assessors to discuss EPA policy with regulators, decision makers, and stakeholders as it relates to conditions at a particular DOE site

  20. Remedial investigation work plan for the Upper East Fork Poplar Creek Characterization Area, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-03-01

    More than 200 contaminated sites created by past waste management practices have been identified at the Y-12 Plant. Many of the sites have been grouped into operable units based on priority and on investigative and remediation requirements. The Y-12 Plant is one of three major facilities on the ORR. The ORR contains both hazardous and mixed-waste sites that are subject to regulations promulgated under the Resource Conservation and Recovery Act of 1976 (RCRA) and the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of 1986. Under RCRA guidelines and requirements from the Tennessee Department of Environment and Conservation (TDEC), the Y-12 Plant initiated investigation and monitoring of various sites within its boundaries in the mid-1980s. The entire ORR was placed on the National Priorities List (NPL) of CERCLA sites in November 1989. Following CERCLA guidelines, sites under investigation require a remedial investigation (RI) to define the nature and extent of contamination, evaluate the risks to public health and the environment, and determine the goals for a feasibility study (FS) of potential remedial actions

  1. Remedial investigation/feasibility study of the Clinch River/Poplar Creek Operable Unit. Volume 3. Risk assessment information. Appendixes E, F

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is Volume 3 of the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  2. Remedial investigation work plan for Bear Creek Valley Operable Unit 2 (Rust Spoil Area, SY-200 Yard, Spoil Area 1) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-05-01

    The enactment of the Resource Conservation and Recovery Act (RCRA) in 1976 and the Hazardous and Solid Waste Amendments (HSWA) to RCRA in 1984 created management requirements for hazardous waste facilities. The facilities within the Oak Ridge Reservation (ORR) were in the process of meeting the RCRA requirements when ORR was placed on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) National Priorities List (NPL) on November 21, 1989. Under RCRA, the actions typically follow the RCRA Facility Assessment (RFA)/RCRA Facility Investigation (RFI)/Corrective Measures Study (CMS)/Corrective Measures implementation process. Under CERCLA the actions follow the PA/SI/Remedial Investigation (RI)/Feasibility Study (FS)/Remedial Design/Remedial Action process. The development of this document will incorporate requirements under both RCRA and CERCLA into an RI work plan for the characterization of Bear Creek Valley (BCV) Operable Unit (OU) 2

  3. Remedial investigation/feasibility study of the Clinch River/Poplar Creek operable unit. Volume 3: Appendixes E and F -- Risk assessment information

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the US Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  4. Phase 1 remedial investigation report for 200-BP-1 operable unit

    International Nuclear Information System (INIS)

    1993-09-01

    The US Department of Energy (DOE) Hanford Site, in Washington State is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989 included the 200 Areas of the Hanford Site on the National Priority List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA). Inclusion on the NPL initiated the remedial investigation (RD process for the 200-BP-1 operable unit. These efforts are being addressed through the Hanford Federal Facility Agreement and Consent Order (Ecology et al. 1989) which was negotiated and approved by the DOE, the EPA, and the State of Washington Department of Ecology (Ecology) in May 1989. This agreement, known as the Tri-Party Agreement, governs all CERCLA efforts at Hanford. In March of 1990, the Department of Energy, Richland Operations (DOE-RL) issued a Remedial Investigation/Feasibility Study (RI/FS) work plan (DOE-RL 1990a) for the 200-BP-1 operable unit. The work plan initiated the first phase of site characterization activities associated with the 200-BP-1 operable unit. The purpose of the 200-BP-1 operable unit RI is to gather and develop the necessary information to adequately understand the risks to human health and the environment posed by the site and to support the development and analysis of remedial alternatives during the FS. The RI analysis will, in turn, be used by Tri-Party Agreement signatories to make a risk-management-based selection of remedies for the releases of hazardous substances that have occurred from the 200-BP-1 operable unit

  5. Remedial investigation report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text

    International Nuclear Information System (INIS)

    1994-08-01

    The enactment of the Resource Conservation and Recovery Act (RCRA) in 1976 and the Hazardous and Solid Waste Amendments (HSWA) to RCRA in 1984 created management requirements for hazardous waste facilities. The facilities within the Oak Ridge Reservation (ORR) were in the process of meeting the RCRA requirements when the ORR was placed on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) National Priorities List (NPL) on November 21, 1989. Under RCRA, the actions typically follow the RCRA Facility Assessment/RCRA Facility Investigation (RFI)/Corrective Measures Study (CMS)/Corrective Measures Implementation process. Under CERCLA, the actions follow the preliminary assessment/site investigation/Remedial Investigation (RI)/Feasibility Study (FS)/Remedial Design/Remedial Action process. This document incorporates requirements under both RCRA and CERCLA in the form of an RI report for the characterization of Bear Creek Valley (BCV) Operable Unit (OU) 2

  6. Remedial investigation report for J-Field, Aberdeen Proving Ground, Maryland. Volume 1: Remedial investigation results

    International Nuclear Information System (INIS)

    Yuen, C. R.; Martino, L. E.; Biang, R. P.; Chang, Y. S.; Dolak, D.; Van Lonkhuyzen, R. A.; Patton, T. L.; Prasad, S.; Quinn, J.; Rosenblatt, D. H.; Vercellone, J.; Wang, Y. Y.

    2000-01-01

    This report presents the results of the remedial investigation (RI) conducted at J-Field in the Edgewood Area of Aberdeen Proving Ground (APG), a U.S. Army installation located in Harford County, Maryland. Since 1917, activities in the Edgewood Area have included the development, manufacture, and testing of chemical agents and munitions and the subsequent destruction of these materials at J-Field by open burning and open detonation. These activities have raised concerns about environmental contamination at J-Field. This RI was conducted by the Environmental Conservation and Restoration Division, Directorate of Safety, Health and Environmental Division of APG, pursuant to requirements outlined under the Comprehensive Environmental Response, Compensation, and Liability Act, as amended (CERCLA). The RI was accomplished according to the procedures developed by the U.S. Environmental Protection Agency (EPA 1988). The RI provides a comprehensive evaluation of the site conditions, nature of contaminants present, extent of contamination, potential release mechanisms and migration pathways, affected populations, and risks to human health and the environment. This information will be used as the basis for the design and implementation of remedial actions to be performed during the remedial action phase, which will follow the feasibility study (FS) for J-Field

  7. Remedial investigation report for J-Field, Aberdeen Proving Ground, Maryland. Volume 1: Remedial investigation results

    Energy Technology Data Exchange (ETDEWEB)

    Yuen, C. R.; Martino, L. E.; Biang, R. P.; Chang, Y. S.; Dolak, D.; Van Lonkhuyzen, R. A.; Patton, T. L.; Prasad, S.; Quinn, J.; Rosenblatt, D. H.; Vercellone, J.; Wang, Y. Y.

    2000-03-14

    This report presents the results of the remedial investigation (RI) conducted at J-Field in the Edgewood Area of Aberdeen Proving Ground (APG), a U.S. Army installation located in Harford County, Maryland. Since 1917, activities in the Edgewood Area have included the development, manufacture, and testing of chemical agents and munitions and the subsequent destruction of these materials at J-Field by open burning and open detonation. These activities have raised concerns about environmental contamination at J-Field. This RI was conducted by the Environmental Conservation and Restoration Division, Directorate of Safety, Health and Environmental Division of APG, pursuant to requirements outlined under the Comprehensive Environmental Response, Compensation, and Liability Act, as amended (CERCLA). The RI was accomplished according to the procedures developed by the U.S. Environmental Protection Agency (EPA 1988). The RI provides a comprehensive evaluation of the site conditions, nature of contaminants present, extent of contamination, potential release mechanisms and migration pathways, affected populations, and risks to human health and the environment. This information will be used as the basis for the design and implementation of remedial actions to be performed during the remedial action phase, which will follow the feasibility study (FS) for J-Field.

  8. Remedial investigation work plan for Bear Creek Valley Operable Unit 2 (Rust Spoil Area, SY-200 Yard, Spoil Area 1) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environmental Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    1993-05-01

    The enactment of the Resource Conservation and Recovery Act (RCRA) in 1976 and the Hazardous and Solid Waste Amendments (HSWA) to RCRA in 1984 created management requirements for hazardous waste facilities. The facilities within the Oak Ridge Reservation (ORR) were in the process of meeting the RCRA requirements when ORR was placed on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) National Priorities List (NPL) on November 21, 1989. Under RCRA, the actions typically follow the RCRA Facility Assessment (RFA)/RCRA Facility Investigation (RFI)/Corrective Measures Study (CMS)/Corrective Measures implementation process. Under CERCLA the actions follow the PA/SI/Remedial Investigation (RI)/Feasibility Study (FS)/Remedial Design/Remedial Action process. The development of this document will incorporate requirements under both RCRA and CERCLA into an RI work plan for the characterization of Bear Creek Valley (BCV) Operable Unit (OU) 2.

  9. Ecological risk assessment guidance for preparation of remedial investigation/feasibility study work plans

    International Nuclear Information System (INIS)

    Pentecost, E.D.; Vinikour, W.S.

    1993-08-01

    This guidance document (1) provides instructions on preparing the components of an ecological work plan to complement the overall site remedial assessment investigation/feasibility study (RI/FS) work plan and (2) directs the user on how to implement ecological tasks identified in the plan. Under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), as amended by the Superfired Amendments and Reauthorization Act of 1986 (SARA), an RI/FS work plan win have to be developed as part of the site-remediation scoping the process. Specific guidance on the RI/FS process and the preparation of work plans has been developed by the US Environmental Protection Agency (EPA 1988a). This document provides guidance to US Department of Energy (DOE) staff and contractor personnel for incorporation of ecological information into environmental remediation planning and decision making at CERCLA sites. An overview analysis of early ecological risk assessment methods (i.e., in the 1980s) at Superfund sites was conducted by the EPA (1989a). That review provided a perspective of attention given to ecological issues in some of the first RI/FS studies. By itself, that reference is of somewhat limited value; it does, however, establish a basis for comparison of past practices in ecological risk with current, more refined methods

  10. Remedial investigation/feasibility study of the Clinch River/Poplar Creek Operable Unit. Volume 5. Appendixes J, K, L, M, and N-other supporting information

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is Volume 5 of the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  11. Development of exposure scenarios for CERCLA risk assessments at the Savannah River Site (U)

    International Nuclear Information System (INIS)

    Nix, D.W.; Immel, J.W.; Phifer, M.A.

    1992-01-01

    Environmental Restoration (ER) activities at the Savannah River Site (SRS) begin with the characterization of inactive hazardous, radioactive and mixed waste disposal areas by a combined Resource Conservation Recovery Act (RCRA) Facility Investigation (RFI)/Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) Remedial Investigation (Rl) followed by evaluation of remedial alternatives in a RCRA Corrective Measures Study (CMS)/CERCLA Feasibility Study (FS). A CERCLA Baseline Risk Assessment (BRA) is performed during the RFVRI characterization to determine if there are any potential risks to human health or the environment from the waste unit. If it is determined that there is need for remedial action, a Risk Evaluation of Remedial Alternatives (RERA) is performed as part of the CMS/FS to provide a basis for selecting a remedy that is protective of human health and the environment. The SRS has numerous waste units to evaluate in the RFI/RI and CMS/FS programs and, in order to provide a consistent approach, four standard exposure scenarios were developed for exposure assessments to be used in human health risk assessments. The standard exposure scenarios are divided into two temporal categories: (a) Current Land Use in the BRA, and (b) Future Land Use in the RERA. The Current Land Use scenarios consist of the evaluation of human health risk for Industrial Exposure (of a worker not involved in waste unit characterization or remediation), a Trespasser, a hypothetical current On-site Resident, and an Off-site Resident. The Future Land Use scenario considers exposure to an On-site Resident following termination of institutional control in the absence of any remedial action (No Action Alternative), as well as evaluating potential remedial alternatives against the four scenarios from the BRA. A critical facet in the development of a BRA or RERA is the seeping of exposure scenarios that reflect actual conditions at a waste unit, rather than using

  12. Remedial investigation/feasibility study of the Clinch River/Poplar Creek Operable Unit. Volume 2. Biota and representative concentrations of contaminants. Appendixes A, B, C, D

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OU`s). This document is the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  13. Phase 1 remedial investigation report for 200-BP-1 operable unit. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    1993-09-01

    The US Department of Energy (DOE) Hanford Site, in Washington State is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989 included the 200 Areas of the Hanford Site on the National Priority List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA). Inclusion on the NPL initiated the remedial investigation (RD process for the 200-BP-1 operable unit. These efforts are being addressed through the Hanford Federal Facility Agreement and Consent Order (Ecology et al. 1989) which was negotiated and approved by the DOE, the EPA, and the State of Washington Department of Ecology (Ecology) in May 1989. This agreement, known as the Tri-Party Agreement, governs all CERCLA efforts at Hanford. In March of 1990, the Department of Energy, Richland Operations (DOE-RL) issued a Remedial Investigation/Feasibility Study (RI/FS) work plan (DOE-RL 1990a) for the 200-BP-1 operable unit. The work plan initiated the first phase of site characterization activities associated with the 200-BP-1 operable unit. The purpose of the 200-BP-1 operable unit RI is to gather and develop the necessary information to adequately understand the risks to human health and the environment posed by the site and to support the development and analysis of remedial alternatives during the FS. The RI analysis will, in turn, be used by Tri-Party Agreement signatories to make a risk-management-based selection of remedies for the releases of hazardous substances that have occurred from the 200-BP-1 operable unit.

  14. Remedial investigation/feasibility study of the Clinch River/Poplar Creek operable unit. Volume 4. Information related to the feasibility study and ARARs. Appendixes G, H, I

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  15. Remedial investigation/feasibility study of the Clinch River/Poplar Creek Operable Unit. Volume 2. Appendixes A, B, C, and D-Biota and representative concentrations of contaminants

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is Volume 2 of the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  16. 75 FR 984 - Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA and RCRA Sites

    Science.gov (United States)

    2010-01-07

    ...The Environmental Protection Agency (EPA or the Agency) is announcing a 50-day public comment period for draft recommended interim preliminary remediation goals (PRGs) developed in the Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) Sites. EPA's Office of Solid Waste and Emergency and Emergency Response (OSWER) has developed the draft recommended interim PRGs for dioxin in soil. These draft recommended interim PRGs were calculated using existing, peer- reviewed toxicity values and current EPA equations and default exposure assumptions. This Federal Register notice is intended to provide an opportunity for public comment on the draft recommended interim PRGs. EPA will consider any public comments submitted in accordance with this notice and may revise the draft recommended interim PRGs thereafter.

  17. ICDF Complex Remedial Action Report

    Energy Technology Data Exchange (ETDEWEB)

    W. M. Heileson

    2007-09-26

    This Idaho CERCLA Disposal Facility (ICDF) Remedial Action Report has been prepared in accordance with the requirements of Section 6.2 of the INEEL CERCLA Disposal Facility Remedial Action Work Plan. The agency prefinal inspection of the ICDF Staging, Storage, Sizing, and Treatment Facility (SSSTF) was completed in June of 2005. Accordingly, this report has been developed to describe the construction activities completed at the ICDF along with a description of any modifications to the design originally approved for the facility. In addition, this report provides a summary of the major documents prepared for the design and construction of the ICDF, a discussion of relevant requirements and remedial action objectives, the total costs associated with the development and operation of the facility to date, and identification of necessary changes to the Agency-approved INEEL CERCLA Disposal Facility Remedial Action Work Plan and the ICDF Complex Operations and Maintenance Plan.

  18. Work plan for the remedial investigation/feasibility study-environmental assessment for the Colonie site, Colonie, New York

    International Nuclear Information System (INIS)

    1990-06-01

    This work plan has been prepared to document the scoping and planning process performed by the US Department of Energy (DOE) to support remedial action activities at the Colonie site. The site is located in eastern New York State in the town of Colonie near the city of Albany. Remedial action of the Colonie site is being planned as part of DOE's Formerly Utilized Sites Remedial Action Program. The DOE is responsible for controlling the release of all radioactive and chemical contaminants from the site. Under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), a remedial investigation/feasibility study (RI/FS) must be prepared to support the decision-making process for evaluating remedial action alternatives. This work plan contains a summary of information known about the site as of January 1988, presents a conceptual site model that identifies potential routes of human exposure to site containments, identifies data gaps, and summarizes the process and proposed studies that will be used to fill the data gaps. In addition, DOE activities must be conducted in compliance with the National Environmental Policy Act (NEPA), which requires consideration of the environmental consequences of a proposed action as part of its decision-making process. This work also describes the approach that will be used to evaluate potential remedial action alternatives and includes a description of the organization, project controls, and task schedules that will be employed to fulfill the requirements of both CERCLA and NEPA. 48 refs., 18 figs., 25 tabs

  19. Strategy for integrated CERCLA/NEPA risk assessments

    International Nuclear Information System (INIS)

    MacDonell, M.M.; Haroun, L.A.; Peterson, J.M.; Blunt, D.A.; Fingleton, D.J.; Picel, M.H.

    1991-01-01

    The US Department of Energy (DOE) has established a policy whereby, for remedial actions, the procedural and documentational requirements of the National Environmental Policy Act (NEPA) are integrated with those of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. However, the objectives of risk assessment under NEPA and CERCLA differ somewhat. Until its recent application at contaminated sites, NEPA analysis has typically been applied to impacts from taking actions at clean sites (e.g., for construction activities), and a somewhat loosely structured process has historically been used to estimate relative risks for NEPA analyses. Decisions such as cleanup levels were not made on the basis of the risk estimates, and they therefore tended to be conservative and were not discussed in detail. In contrast, risks estimated for Superfund (CERCLA) sites are used to focus the decision-making process for those sites and support national prioritization for cleanup, and the US Environmental Protection Agency (EPA) has developed a detailed framework for preparing baseline health risk assessments for these sites. The purpose of this paper is to discuss issues related to intergrating the CERCLA and NEPA approaches into the risk assessments that have been prepared for a DOE remedial action project at the Weldon Spring site near St. Charles, Missouri. These issues are grouped into three basic categories: general assumptions for the impact evaluation, data management, and presentation of the methodology and results. This paper is not intended to represent DOE policy and guidance, nor does it represent the only approach that can be used for integrated risk assessments. It merely discusses the process that was used for the Weldon Spring project, articulating the issues that were encountered and how they were addressed

  20. Remedial investigation/feasibility study of the Clinch River/Poplar Creek Operable Unit. Volume 4. Appendixes G, H, and I and information related to the feasibility study and ARARs

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-06-01

    This report presents the findings of an investigation into contamination of the Clinch River and Poplar Creek near the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation (ORR) in eastern Tennessee. For more than 50 years, various hazardous and radioactive substances have been released to the environment as a result of operations and waste management activities at the ORR. In 1989, the ORR was placed on the National Priorities List (NPL), established and maintained under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under CERCLA, NPL sites must be investigated to determine the nature and extent of contamination at the site, assess the risk to human health and the environment posed by the site, and, if necessary, identify feasible remedial alternatives that could be used to clean the site and reduce risk. To facilitate the overall environmental restoration effort at the ORR, CERCLA activities are being implemented individually as distinct operable units (OUs). This document is Volume 4 of the combined Remedial Investigation and Feasibility Study Report for the Clinch River/Poplar Creek OU.

  1. 300-FF-1 remedial design report/remedial action work plan

    Energy Technology Data Exchange (ETDEWEB)

    Gustafson, F.W.

    1997-02-01

    The 300 Area has been divided into three operable units 300-FF-1, 300-FF-2, and 300-FF-5 all of which are in various stages of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) process. The 300-FF-1 Operable Unit, the subject of this report, includes liquid waste disposal sites, landfills, and a burial ground. This Remedial Design Report/Remedial Action Work Plan (RDR/RAWP) provides a summary description of each waste site included in the 300-FF-1 Operable Unit, the basis for remedial actions to be taken, and the remedial action approach and management process for implementing these actions. The remedial action approach and management sections provide a description of the remedial action process description, the project schedule, the project team, required planning documentation, the remedial action change process, the process for verifying attainment of the remedial action goals, and the required CERCLA and RCRA closeout documentation. Appendix A provides additional details on each waste site. In addition to remediation of the waste sites, waste generated during the remedial investigation/feasibility study portions of the project will also be disposed at the Environmental Restoration Disposal Facility (ERDF). Appendix B provides a summary of the modeling performed in the 300-FF-1 Phase 3 FS and a description of the modeling effort to be used to show attainment of the remedial action goals. Appendix C provides the sampling and analysis plan (SAP) for all sampling and field-screening activities performed during remediation and for verification of attainment with the remedial action goals. Appendix D provides the public involvement plan, prepared to ensure information is provided to the public during remedial design and remedial action processes.

  2. 300-FF-1 remedial design report/remedial action work plan

    International Nuclear Information System (INIS)

    Gustafson, F.W.

    1997-02-01

    The 300 Area has been divided into three operable units 300-FF-1, 300-FF-2, and 300-FF-5 all of which are in various stages of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) process. The 300-FF-1 Operable Unit, the subject of this report, includes liquid waste disposal sites, landfills, and a burial ground. This Remedial Design Report/Remedial Action Work Plan (RDR/RAWP) provides a summary description of each waste site included in the 300-FF-1 Operable Unit, the basis for remedial actions to be taken, and the remedial action approach and management process for implementing these actions. The remedial action approach and management sections provide a description of the remedial action process description, the project schedule, the project team, required planning documentation, the remedial action change process, the process for verifying attainment of the remedial action goals, and the required CERCLA and RCRA closeout documentation. Appendix A provides additional details on each waste site. In addition to remediation of the waste sites, waste generated during the remedial investigation/feasibility study portions of the project will also be disposed at the Environmental Restoration Disposal Facility (ERDF). Appendix B provides a summary of the modeling performed in the 300-FF-1 Phase 3 FS and a description of the modeling effort to be used to show attainment of the remedial action goals. Appendix C provides the sampling and analysis plan (SAP) for all sampling and field-screening activities performed during remediation and for verification of attainment with the remedial action goals. Appendix D provides the public involvement plan, prepared to ensure information is provided to the public during remedial design and remedial action processes

  3. Remedial investigation/feasibility study work plan for the 100-BC-5 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-07-01

    Four areas of the Hanford Site (the 100, 200, 300, and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). The Tri-Party Agreement requires that the cleanup programs at the Hanford Site integrate the requirements of CERCLA, RCRA, and Washington State's dangerous waste (the state's RCRA-equivalent) program. This work plan and the attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-BC-5 operable unit. The 100-B/C Area consists of the 100-BC-5 groundwater operable unit and four source operable units. The 100-BC-5 operable unit includes all contamination found in the aquifer soils and water beneath the 100-B/C Area. Source operable units include facilities and unplanned release sites that are potential sources of contamination

  4. Remedial investigation report for J-Field, Aberdeen Proving Ground, Maryland. Volume 3: Ecological risk assessment

    Energy Technology Data Exchange (ETDEWEB)

    Hlohowskyj, I.; Hayse, J.; Kuperman, R.; Van Lonkhuyzen, R.

    2000-02-25

    The Environmental Management Division of the U.S. Army Aberdeen Proving Ground (APG), Maryland, is conducting a remedial investigation (RI) and feasibility study (FS) of the J-Field area at APG, pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. As part of that activity, Argonne National Laboratory (ANL) conducted an ecological risk assessment (ERA) of the J-Field site. This report presents the results of that assessment.

  5. Remedial investigation report for J-Field, Aberdeen Proving Ground, Maryland. Volume 3: Ecological risk assessment

    International Nuclear Information System (INIS)

    Hlohowskyj, I.; Hayse, J.; Kuperman, R.; Van Lonkhuyzen, R.

    2000-01-01

    The Environmental Management Division of the U.S. Army Aberdeen Proving Ground (APG), Maryland, is conducting a remedial investigation (RI) and feasibility study (FS) of the J-Field area at APG, pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. As part of that activity, Argonne National Laboratory (ANL) conducted an ecological risk assessment (ERA) of the J-Field site. This report presents the results of that assessment

  6. Remedial investigation for the 200-BP-1 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    Buckmaster, M.A.

    1991-01-01

    The Hanford Site, Richland, Washington, contains over 1500 identified waste sites that will be characterized and remediated over the next 30 years. In support of the ''Hanford Federal Facility Agreement and Consent Order,'' the US Department of Energy has initiated a remedial investigation/feasibility study (RI/FS) at the 200-BP-1 operable unit. The 200-BP-1 RI is the first Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) investigation on the Hanford Site that involves drilling into highly radioactive and chemically contaminated soils. The initial phase of the site characterization is oriented toward determining the nature and extent of any contamination present in the vicinity of the 200-BP-1 operable unit. The major focus of the Phase I RI is the drilling and sampling of 10 inactive waste disposal units which received low level radioactive liquid waste

  7. ICDF Complex Remedial Action Work Plan

    Energy Technology Data Exchange (ETDEWEB)

    W. M. Heileson

    2006-12-01

    This Remedial Action Work Plan provides the framework for operation of the Idaho Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Disposal Facility Complex (ICDF). This facility includes (a) an engineered landfill that meets the substantial requirements of DOE Order 435.1, Resource Conservation and Recovery Act Subtitle C, Idaho Hazardous Waste Management Act, and Toxic Substances Control Act polychlorinated biphenyl landfill requirements; (b) centralized receiving, inspections, administration, storage/staging, and treatment facilities necessary for CERCLA investigation-derived, remedial, and removal waste at the Idaho National Laboratory (INL) prior to final disposition in the disposal facility or shipment off-Site; and (c) an evaporation pond that has been designated as a corrective action management unit. The ICDF Complex, including a buffer zone, will cover approximately 40 acres, with a landfill disposal capacity of approximately 510,000 yd3. The ICDF Complex is designed and authorized to accept INL CERCLA-generated wastes, and includes the necessary subsystems and support facilities to provide a complete waste management system. This Remedial Action Work Plan presents the operational approach and requirements for the various components that are part of the ICDF Complex. Summaries of the remedial action work elements are presented herein, with supporting information and documents provided as appendixes to this work plan that contain specific detail about the operation of the ICDF Complex. This document presents the planned operational process based upon an evaluation of the remedial action requirements set forth in the Operable Unit 3-13 Final Record of Decision.

  8. Sampling and analysis plan for volatile organic compounds in storm drain for the Upper East Fork Poplar Creek characterization area remedial investigation at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1997-03-01

    The Oak Ridge Y-12 Plant, located within the Oak Ridge Reservation (ORR), is owned by the US Department of Energy and managed by Lockheed Martin Energy Systems, Inc. The Y-12 Plant is one of three major facilities on the ORR. The ORR contains both hazardous- and mixed-waste sites that are subject to regulations promulgated under the Resource Conservation and Recovery Act of 1976 (RCRA) and the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) as amended by the Superfund Amendments and Reauthorization Act of 1986. Under RCRA guidelines and requirements from the Tennessee Department of Environment and Conservation, the Y-12 Plant initiated investigation and monitoring of various sites within its boundaries in the mid-1980s. The entire ORR was placed on the National Priorities List of CERCLA sites in November 1989. Following CERCLA guidelines, sites under investigation require a remedial investigation (RI) to define the nature and extent of contamination, evaluate the risks to public health and the environment, and determine the goals for a feasibility study (FS) of potential remedial actions

  9. Hazard Ranking System evaluation of CERCLA [Comprehensive Environmental Response, Compensation, and Liability Act] inactive waste sites at Hanford: Volume 1, Evaluation methods and results

    International Nuclear Information System (INIS)

    Stenner, R.D.; Cramer, K.H.; Higley, K.A.; Jette, S.J.; Lamar, D.A.; McLaughlin, T.J.; Sherwood, D.R.; Van Houten, N.C.

    1988-10-01

    The purpose of this report is to formally document the individual site Hazard Ranking System (HRS) evaluations conducted as part of the preliminary assessment/site inspection (PA/SI) activities at the US Department of Energy (DOE) Hanford Site. These activities were carried out pursuant to the DOE orders that describe the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Program addressing the cleanup of inactive waste sites. These orders incorporate the US Environmental Protection Agency methodology, which is based on the Superfund Amendments and Reauthorization Act of 1986 (SARA). The methodology includes six parts: PA/SI, remedial investigation/feasibility study, record of decision, design and implementation of remedial action, operation and monitoring, and verification monitoring. Volume 1 of this report discusses the CERCLA inactive waste-site evaluation process, assumptions, and results of the HRS methodology employed. Volume 2 presents the data on the individual CERCLA engineered-facility sites at Hanford, as contained in the Hanford Inactive Site Surveillance (HISS) Data Base. Volume 3 presents the data on the individual CERCLA unplanned-release sites at Hanford, as contained in the HISS Data Base. 34 refs., 43 figs., 47 tabs

  10. Hazard Ranking System evaluation of CERCLA (Comprehensive Environmental Response, Compensation, and Liability Act) inactive waste sites at Hanford: Volume 1, Evaluation methods and results

    Energy Technology Data Exchange (ETDEWEB)

    Stenner, R.D.; Cramer, K.H.; Higley, K.A.; Jette, S.J.; Lamar, D.A.; McLaughlin, T.J.; Sherwood, D.R.; Van Houten, N.C.

    1988-10-01

    The purpose of this report is to formally document the individual site Hazard Ranking System (HRS) evaluations conducted as part of the preliminary assessment/site inspection (PA/SI) activities at the US Department of Energy (DOE) Hanford Site. These activities were carried out pursuant to the DOE orders that describe the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Program addressing the cleanup of inactive waste sites. These orders incorporate the US Environmental Protection Agency methodology, which is based on the Superfund Amendments and Reauthorization Act of 1986 (SARA). The methodology includes six parts: PA/SI, remedial investigation/feasibility study, record of decision, design and implementation of remedial action, operation and monitoring, and verification monitoring. Volume 1 of this report discusses the CERCLA inactive waste-site evaluation process, assumptions, and results of the HRS methodology employed. Volume 2 presents the data on the individual CERCLA engineered-facility sites at Hanford, as contained in the Hanford Inactive Site Surveillance (HISS) Data Base. Volume 3 presents the data on the individual CERCLA unplanned-release sites at Hanford, as contained in the HISS Data Base. 34 refs., 43 figs., 47 tabs.

  11. Remedial investigation/feasibility study work plan for the 100-KR-4 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-09-01

    Four areas of the Hanford Site (the 100, 200, 300, and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). This work plan and the attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-KR-4 operable unit. The 100-K Area consists of the 100-KR-4 groundwater operable unit and three source operable units. The 100-KR-4 operable unit includes all contamination found in the aquifer soils and water beneath the 100-K Area. Source operable units include facilities and unplanned release sites that are potential sources of contamination

  12. Remedial investigation/feasibility study work plan for the 100-KR-4 operable unit, Hanford Site, Richland, Washington

    Energy Technology Data Exchange (ETDEWEB)

    1992-09-01

    Four areas of the Hanford Site (the 100, 200, 300, and 1100 Areas) have been included on the US Environmental Protection Agency`s (EPA`s) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). This work plan and the attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-KR-4 operable unit. The 100-K Area consists of the 100-KR-4 groundwater operable unit and three source operable units. The 100-KR-4 operable unit includes all contamination found in the aquifer soils and water beneath the 100-K Area. Source operable units include facilities and unplanned release sites that are potential sources of contamination.

  13. Phase I remedial investigation report for the 300-FF-5 operable unit, Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-01-01

    The focus of this remedial investigation (RI) is the 300-FF-5 operable unit, one of five operable units associated with the 300 Area aggregate of the U.S. Department of Energy`s (DOE`s) Hanford Site. The 300-FF-5 operable unit is a groundwater operable unit beneath the 300-FF-1, 300-FF-2, and 300-FF-3 source operable units. This operable unit was designated to include all contamination detected in the groundwater and sediments below the water table that emanates from the 300-FF-1, 300-FF-2, and 300-FF-3 operable units (DOE-RL 1990a). In November 1989, the U.S. Environmental Protection Agency (EPA) placed the 300 Area on the National Priorities List (NPL) contained within Appendix B of the National Oil and Hazardous Substance Pollution Contingency Plan (NCP, 53 FR 51391 et seq.). The EPA took this action pursuant to their authority under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA, 42 USC 9601 et seq.). The DOE Richland Operations Office (DOE-RL), the EPA and Washington Department of Ecology (Ecology) issued the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), in May 1989 (Ecology et al. 1992, Rev. 2). This agreement, among other matters, governs all CERCLA efforts at the Hanford Site. In June 1990, a remedial investigation/feasibility study (RI/FS) workplan for the 300-FF-5 operable unit was issued pursuant to the Tri-Party Agreement.

  14. Phase I remedial investigation report for the 300-FF-5 operable unit, Volume 1

    International Nuclear Information System (INIS)

    1994-01-01

    The focus of this remedial investigation (RI) is the 300-FF-5 operable unit, one of five operable units associated with the 300 Area aggregate of the U.S. Department of Energy's (DOE's) Hanford Site. The 300-FF-5 operable unit is a groundwater operable unit beneath the 300-FF-1, 300-FF-2, and 300-FF-3 source operable units. This operable unit was designated to include all contamination detected in the groundwater and sediments below the water table that emanates from the 300-FF-1, 300-FF-2, and 300-FF-3 operable units (DOE-RL 1990a). In November 1989, the U.S. Environmental Protection Agency (EPA) placed the 300 Area on the National Priorities List (NPL) contained within Appendix B of the National Oil and Hazardous Substance Pollution Contingency Plan (NCP, 53 FR 51391 et seq.). The EPA took this action pursuant to their authority under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA, 42 USC 9601 et seq.). The DOE Richland Operations Office (DOE-RL), the EPA and Washington Department of Ecology (Ecology) issued the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), in May 1989 (Ecology et al. 1992, Rev. 2). This agreement, among other matters, governs all CERCLA efforts at the Hanford Site. In June 1990, a remedial investigation/feasibility study (RI/FS) workplan for the 300-FF-5 operable unit was issued pursuant to the Tri-Party Agreement

  15. Role of institutional controls in selection of remedial measures

    International Nuclear Information System (INIS)

    Bakr, A.A.; Agoston, E.N.; McLeod, R.V.; Hicks, H.T.

    1992-01-01

    This paper explores the regulatory intent of CERCLA's definition and applicability of institutional controls at hazardous substance release sites undergoing remedial action and institutional controls that have been defined and implemented at selected CERCLA (Superfund) sites in the United States. Under provisions of CERCLA, institutional controls can be components of, or supplements to, interim or final remedial measures for hazardous substance [as defined under CERCLA 101(14)] releases. The use of institutional controls has been proposed in a number of RODs for large Superfund sites (e.g., Times Beach, Missouri; the Clothier Disposal Site in Oswego County, New York; and the Wildcat Landfill in Kent County, Delaware). In these cases, the selected remedial actions combine active response measures with institutional controls to protect human health and the environment. These RODs provide insight to how widely the concept of institutional controls is used and under what conditions. The use of institutional controls at large federal facilities is also discussed

  16. Taking interim actions: Integrating CERCLA and NEPA to move ahead with site cleanup

    International Nuclear Information System (INIS)

    MacDonell, M.M.; Peterson, J.M.; Valett, G.L.; McCracken, S.H.

    1991-01-01

    The cleanup of contaminated sites can be expedited by using interim response actions in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, and the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). In fact, a major portion of some Superfund sites can be cleaned up using interim actions. For CERCLA sites being remediated by the US Department of Energy (DOE), such actions must also comply with the National Environmental Policy Act (NEPA) because the DOE has established a policy for integrating CERCLA and NEPA requirements. A strategy for the integrated documentation with implementation of interim actions has been applied successfully at the Weldon Spring site, and major cleanup projects are currently underway. This paper discusses some of the issues associated with integrating CERCLA and NEPA for interim actions and summarizes those actions that have been identified for the Weldon Spring site

  17. Taking interim actions: Integrating CERCLA and NEPA to move ahead with site cleanup

    International Nuclear Information System (INIS)

    MacDonell, M.M.; Peterson, J.M.; Valett, G.L.; McCracken, S.H.

    1991-01-01

    The cleanup of contaminated sites can be expedited by using interim response actions in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, and the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). In fact, a major portion of some Superfund sites can be cleaned up using interim actions. For CERCLA sites being remediated by the US Department of Energy (DOE), such actions must also comply with the National Environmental Policy Act (NEPA) because the DOE has established a policy for integrating CERCLA and NEPA requirements. A strategy for the integrated documentation and implementation of interim actions has been applied successfully at the Weldon Spring site, and major cleanup projects are currently underway. This paper discusses some of the issues associated with integrating CERCLA and NEPA for interim actions and summarizes those actions that have been identified for the Weldon Spring site

  18. CERCLA-linked environmental impact and benefit analysis: Evaluating remedial alternatives for the Portland Harbor Superfund Site, Portland, Oregon, USA.

    Science.gov (United States)

    McNally, Amanda D; Fitzpatrick, Anne G; Mirchandani, Sera; Salmon, Matthew; Edwards, Deborah A

    2018-01-01

    This analysis focused on evaluating the environmental consequences of remediation, providing indicators for the environmental quality pillar of 3 "pillars" of the Portland Harbor Sustainability Project (PHSP) framework (the other 2 pillars are economic viability and social equity). The project an environmental impact and benefit analysis (EIBA) and an EIBA-based cost-benefit analysis. Metrics developed in the EIBA were used to quantify and compare remedial alternatives' environmental benefits and impacts in the human and ecological domains, as a result of remedial actions (relative to no action). The cost-benefit results were used to evaluate whether remediation costs were proportionate or disproportionate to the environmental benefits. Alternatives B and D had the highest overall benefit scores, and Alternative F was disproportionately costly relative to its achieved benefits when compared to the other remedial alternatives. Indeed, the costlier alternatives with larger remedial footprints had lower overall EIBA benefit scores-because of substantially more air emissions, noise, and light impacts, and more disturbance to business, recreational access, and habitat during construction-compared to the less costly and smaller alternatives. Put another way, the adverse effects during construction tended to outweigh the long-term benefits, and the net environmental impacts of the larger remedial alternatives far outweighed their small incremental improvements in risk reduction. Results of this Comprehensive Environmental Response Compensation and Liability Act (CERCLA)-linked environmental analysis were integrated with indicators of economic and social impacts of remediation in a stakeholder values-based sustainability framework. These tools (EIBA, EIBA-based cost-benefit analysis, economic impact assessment, and the stakeholder values-based integration) provide transparent and quantitative evaluations of the benefits and impacts associated with remedial alternatives

  19. CERCLA site assessment workbook, Volume 1

    International Nuclear Information System (INIS)

    1994-08-01

    This workbook provides instructions for planning, implementing, and reporting site assessments under CERCLA, commonly referred to as Superfund. Site assessment consists of two information-gathering steps: the remedial preliminary assessment (PA) and the site inspection (SI). The information obtained is then used to estimate, or score, a site's relative risk to public health and the environment. The score is derived via the hazard ranking system (HRS). Although the workbook and its exercises can be adapted to group study, it is designed primarily for use by an individual

  20. Work plan for the remedial investigation/feasibility study-environmental assessment for the quarry residuals operable unit at the Weldon Spring Site

    Energy Technology Data Exchange (ETDEWEB)

    1994-01-01

    The US Department of Energy (DOE) is conducting cleanup activities at the Weldon Spring site, which is located in St. Charles County, Missouri, about 48 km (30 mi) west of St. Louis. The Weldon Spring site consists of two noncontiguous areas -- the chemical plant area, which includes four raffinate pits, and the quarry. Cleanup activities at the Weldon Spring site are conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, incorporating the values of the National Environmental Policy Act (NEPA). The contents of the documents prepared for the project are not intended to represent a statement regarding the legal applicability of NEPA to remedial actions conducted under CERCLA. In accordance with the integrated CERCLA/NEPA approach, a remedial investigation/feasibility study-environmental assessment (RI/FS-EA) is being conducted to evaluate conditions and potential responses for the quarry residuals operable unit (QROU). This operable unit consists of the following areas and/or media: the residual material remaining at the Weldon Spring quarry after removal of the pond water and bulk waste; underlying groundwater; and other media located in the surrounding vicinity of the quarry, including adjacent soil, surface water, and sediment in Femme Osage Slough. This work plan identifies the activities within the RI/FS-EA process that are being proposed to address contamination remaining at the quarry area.

  1. Work plan for the remedial investigation/feasibility study-environmental assessment for the quarry residuals operable unit at the Weldon Spring Site

    International Nuclear Information System (INIS)

    1994-01-01

    The US Department of Energy (DOE) is conducting cleanup activities at the Weldon Spring site, which is located in St. Charles County, Missouri, about 48 km (30 mi) west of St. Louis. The Weldon Spring site consists of two noncontiguous areas -- the chemical plant area, which includes four raffinate pits, and the quarry. Cleanup activities at the Weldon Spring site are conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, incorporating the values of the National Environmental Policy Act (NEPA). The contents of the documents prepared for the project are not intended to represent a statement regarding the legal applicability of NEPA to remedial actions conducted under CERCLA. In accordance with the integrated CERCLA/NEPA approach, a remedial investigation/feasibility study-environmental assessment (RI/FS-EA) is being conducted to evaluate conditions and potential responses for the quarry residuals operable unit (QROU). This operable unit consists of the following areas and/or media: the residual material remaining at the Weldon Spring quarry after removal of the pond water and bulk waste; underlying groundwater; and other media located in the surrounding vicinity of the quarry, including adjacent soil, surface water, and sediment in Femme Osage Slough. This work plan identifies the activities within the RI/FS-EA process that are being proposed to address contamination remaining at the quarry area

  2. K basins interim remedial action health and safety plan

    Energy Technology Data Exchange (ETDEWEB)

    DAY, P.T.

    1999-09-14

    The K Basins Interim Remedial Action Health and Safety Plan addresses the requirements of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as they apply to the CERCLA work that will take place at the K East and K West Basins. The provisions of this plan become effective on the date the US Environmental Protection Agency issues the Record of Decision for the K Basins Interim Remedial Action, currently planned in late August 1999.

  3. Briefing paper -- Remedial Action Assessment System

    International Nuclear Information System (INIS)

    Buelt, J.L.

    1990-04-01

    Congress has mandated a more comprehensive management of hazardous wastes with the Resource Conservation and Recovery Act (RCRA), the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or ''Superfund'') and the Superfund Amendment and Reauthorization Act (SARA). This mandate includes restoration of disposal sites contaminated through past disposal practices. This mandate applies to facilities operated for and by the Department of Energy (DOE), just as it does to industrial and other institutions. To help implement the CERCLA/SARA remedial investigation and feasibility study (RI/FS) process in a consistent, timely, and cost-effective manner, a methodology needs to be developed that will allow definition, sorting, and screening of remediation technologies for each operable unit (waste site). This need is stated specifically in Section 2.2.2.1 of the October 1989 Applied Research, Development, Demonstration, Testing, and Evaluation (RDDT ampersand E) Plan of the DOE. This Briefing Paper is prepared to respond to this need. 1 fig

  4. CENTRAL PLATEAU REMEDIATION OPTIMIZATION STUDY

    Energy Technology Data Exchange (ETDEWEB)

    BERGMAN, T. B.; STEFANSKI, L. D.; SEELEY, P. N.; ZINSLI, L. C.; CUSACK, L. J.

    2012-09-19

    THE CENTRAL PLATEAU REMEDIATION OPTIMIZATION STUDY WAS CONDUCTED TO DEVELOP AN OPTIMAL SEQUENCE OF REMEDIATION ACTIVITIES IMPLEMENTING THE CERCLA DECISION ON THE CENTRAL PLATEAU. THE STUDY DEFINES A SEQUENCE OF ACTIVITIES THAT RESULT IN AN EFFECTIVE USE OF RESOURCES FROM A STRATEGIC PERSPECTIVE WHEN CONSIDERING EQUIPMENT PROCUREMENT AND STAGING, WORKFORCE MOBILIZATION/DEMOBILIZATION, WORKFORCE LEVELING, WORKFORCE SKILL-MIX, AND OTHER REMEDIATION/DISPOSITION PROJECT EXECUTION PARAMETERS.

  5. Record of Decision Remedial Alternative Selection for the Gunsite 113 Access Road (631-24G) Operable Unit: Final Action

    International Nuclear Information System (INIS)

    Palmer, E.

    1997-01-01

    This decision document presents the selected remedial action for the Gunsite 113 Access Road Unit located at the Savannah River Site near Aiken, SC. The selected action was developed in accordance with CERCLA, as amended, and to the extent practicable, the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). The selected remedy satisfies both CERCLA and RCRA 3004(U) requirements. This decision is based ont he Administrative Record File for this specific RCRA/CERCLA Unit

  6. Remedial investigation/feasibility study report for Lower Watts Bar Reservoir Operable Unit

    International Nuclear Information System (INIS)

    1995-03-01

    This document is the combined Remedial Investigation and Feasibility Study Report for the lower Watts Bar Reservoir (LWBR) Operable Unit (OU). The LWBR is located in Roane, Rhea, and Meigs counties, Tennessee, and consists of Watts Bar Reservoir downstream of the Clinch river. This area has received hazardous substances released over a period of 50 years from the US Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). As required by this law, the ORR and all off-site areas that have received contaminants, including LWBR, must be investigated to determine the risk to human health and the environment resulting from these releases, the need for any remedial action to reduce these risks, and the remedial actions that are most feasible for implementation in this OU. Contaminants from the ORR are primarily transported to the LWBR via the Clinch River. There is little data regarding the quantities of most contaminants potentially released from the ORR to the Clinch River, particularly for the early years of ORR operations. Estimates of the quantities released during this period are available for most radionuclides and some inorganic contaminants, indicating that releases 30 to 50 years ago were much higher than today. Since the early 1970s, the release of potential contaminants has been monitored for compliance with environmental law and reported in the annual environmental monitoring reports for the ORR

  7. Remedial investigation/feasibility study report for Lower Watts Bar Reservoir Operable Unit

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-03-01

    This document is the combined Remedial Investigation and Feasibility Study Report for the lower Watts Bar Reservoir (LWBR) Operable Unit (OU). The LWBR is located in Roane, Rhea, and Meigs counties, Tennessee, and consists of Watts Bar Reservoir downstream of the Clinch river. This area has received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). As required by this law, the ORR and all off-site areas that have received contaminants, including LWBR, must be investigated to determine the risk to human health and the environment resulting from these releases, the need for any remedial action to reduce these risks, and the remedial actions that are most feasible for implementation in this OU. Contaminants from the ORR are primarily transported to the LWBR via the Clinch River. There is little data regarding the quantities of most contaminants potentially released from the ORR to the Clinch River, particularly for the early years of ORR operations. Estimates of the quantities released during this period are available for most radionuclides and some inorganic contaminants, indicating that releases 30 to 50 years ago were much higher than today. Since the early 1970s, the release of potential contaminants has been monitored for compliance with environmental law and reported in the annual environmental monitoring reports for the ORR.

  8. Application of Clean Water (CWA) Section 404 compensatory wetland mitigation under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)

    International Nuclear Information System (INIS)

    Abbott, D.J.; Straub, C.A.

    1994-01-01

    Pursuant to Section 404 of the Clean Water Act (CWA), activities resulting in the discharge of dredge or fill material into waters of the US, including wetlands, require permit authorization from the US Army Corps of Engineers (ACOE). As part of the Section 404 permitting process, compensatory wetland mitigation in the form of wetland enhancement, restoration, or construction may be required to off-set impacts sustained under a Section 404 permit. Under normal circumstances, compensatory mitigation is a relatively straight forward process; however, issues associated with mitigation become more complex at sites undergoing remediation under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), because on-site response/remedial actions involving dredged and fill material are not subject to the formal Section 404 permitting process. These actions are conducted in accordance with the substantive permitting requirements of the ACOE's Nationwide and individual permitting programs. Wetland mitigatory requirements are determined through application of the US Environmental Protection Agency's (USEPA's) 040(b) (1) Guidelines promulgated in 40 CFR Part 230 and are implemented through compliance with substantive permitting requirements during the conduct of response/remedial actions. A programmatic approach for implementing wetland mitigatory requirements is being developed at a former US Department of Energy (DOE) uranium refinery undergoing CERCLA remediation in southwestern Ohio. The approach is designed to define the regulatory mechanism that will be used to integrate CWA driven wetland mitigatory requirements into the CERCLA process

  9. Methodology to remediate a mixed waste site

    International Nuclear Information System (INIS)

    Berry, J.B.

    1994-08-01

    In response to the need for a comprehensive and consistent approach to the complex issue of mixed waste management, a generalized methodology for remediation of a mixed waste site has been developed. The methodology is based on requirements set forth in the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Resource Conservation and Recovery Act (RCRA) and incorporates ''lessons learned'' from process design, remediation methodologies, and remediation projects. The methodology is applied to the treatment of 32,000 drums of mixed waste sludge at the Oak Ridge K-25 Site. Process technology options are developed and evaluated, first with regard to meeting system requirements and then with regard to CERCLA performance criteria. The following process technology options are investigated: (1) no action, (2) separation of hazardous and radioactive species, (3) dewatering, (4) drying, and (5) solidification/stabilization. The first two options were eliminated from detailed consideration because they did not meet the system requirements. A quantitative evaluation clearly showed that, based on system constraints and project objectives, either dewatering or drying the mixed waste sludge was superior to the solidification/stabilization process option. The ultimate choice between the drying and the dewatering options will be made on the basis of a technical evaluation of the relative merits of proposals submitted by potential subcontractors

  10. Methodology to remediate a mixed waste site

    Energy Technology Data Exchange (ETDEWEB)

    Berry, J.B.

    1994-08-01

    In response to the need for a comprehensive and consistent approach to the complex issue of mixed waste management, a generalized methodology for remediation of a mixed waste site has been developed. The methodology is based on requirements set forth in the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Resource Conservation and Recovery Act (RCRA) and incorporates ``lessons learned`` from process design, remediation methodologies, and remediation projects. The methodology is applied to the treatment of 32,000 drums of mixed waste sludge at the Oak Ridge K-25 Site. Process technology options are developed and evaluated, first with regard to meeting system requirements and then with regard to CERCLA performance criteria. The following process technology options are investigated: (1) no action, (2) separation of hazardous and radioactive species, (3) dewatering, (4) drying, and (5) solidification/stabilization. The first two options were eliminated from detailed consideration because they did not meet the system requirements. A quantitative evaluation clearly showed that, based on system constraints and project objectives, either dewatering or drying the mixed waste sludge was superior to the solidification/stabilization process option. The ultimate choice between the drying and the dewatering options will be made on the basis of a technical evaluation of the relative merits of proposals submitted by potential subcontractors.

  11. Remedial investigation/feasibility study work plan for the 100-FR-3 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-09-01

    Four areas of the Hanford Site (the 100, 200, 300, and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Figure 1-1 shows the location of these areas. Under the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et al. 1990a), signed by the Washington State Department of Ecology (Ecology), EPA, and the US Department of Energy (DOE), more than 1,000 inactive waste disposal and unplanned release sites on the Hanford Site have been grouped into a number of source and groundwater operable units. These operable units contain contamination in the form of hazardous waste, radioactive/hazardous mixed waste, and other CERCLA hazardous substances. This work plan and the attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-FR-3 operable unit. The 100-K Area consists of the 100-FR-3 groundwater operable unit and two source operable units. The 100-FR-3 operable unit includes all contamination found in the aquifer soils and water beneath the 100-F Area. Source operable units include facilities and unplanned release sites that are potential sources of contamination. A separate work plan has been initiated for the 100-FR-1 source operable unit (DOE-RL 1992a)

  12. Remedial investigation/feasibility study work plan for the 100-FR-1 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-08-01

    Four areas of the Hanford Site (the 100, 200,300, and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Under the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et al. 1990a), signed by the Washington State Department of Ecology (Ecology), EPA, and the US Department of Energy (DOE), more than 1,000 inactive waste disposal and unplanned release sites on the Hanford Site have been grouped into a number of source and groundwater operable units. These operable units contain contamination in the form of hazardous waste, radioactive/hazardous mixed waste, and other CERCLA hazardous substances. This work plan and the attached supporting project plans establish the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-FR-1 operable unit. The 100-FR-1 source operable unit is one of two source operable units in the 100-F Area. Source operable units include facilities and unplanned release sites that are potential sources of hazardous substance contamination. The groundwater affected or potentially affected by the entire 100-F Area is considered as a separate operable unit, the 100-FR-3 groundwater operable unit. A separate work plan has been initiated for the 100-FR-3 operable unit (DOE/RL 1992a)

  13. Final record of decision for remedial actions at Operable Unit 4

    International Nuclear Information System (INIS)

    1994-12-01

    This decision document presents the selected remedial action for Operable Unit 4 of the Fernald Site in Fernald, Ohio. This remedial action was selected in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA), and to the extent practicable 40 Code of Federal Regulations (CFR) Part 300, the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). For Operable Unit 4 at the FEMP, DOE has chosen to complete an integrated CERCLA/NEPA process. This decision was based on the longstanding interest on the part of local stakeholders to prepare an Environmental Impact Statement (EIS) on the restoration activities at the FEMP and on the recognition that the draft document was issued and public comments received. Therefore, this single document is intended to serve as DOE's Record of Decision (ROD) for Operable Unit 4 under both CERCLA and NEPA; however, it is not the intent of the DOE to make a statement on the legal applicability of NEPA to CERCLA actions

  14. Integrating NRDA and CERCLA environmental evaluations at the Rocky Flats Plant: A case study

    International Nuclear Information System (INIS)

    Knudsen, T.L.

    1993-01-01

    The purpose of this paper is to briefly review cleanup regulations in reference to natural resource liability, protection, and restoration; to present a case study on the Rocky Flats Plant (RFP) showing how this DOE facility is approaching the task of integrating the ecological assessment/impact portion of three major regulatory mandates: Resource Conservation and Recovery Act (RCRA), Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), and the National Environmental Policy Act (NEPA) with the Natural Resource Damage Assessment (NRDA) regulations using a flow chart depicting RCRA/CERCLA interim and final actions; to present what has and has not worked at the RFP; and, finally to suggest some technical strategies when planning for remediation and restoration in the NRD process that should be considered

  15. Remedial investigation report on Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 3, Appendix B, Technical findings and conclusions

    International Nuclear Information System (INIS)

    1995-03-01

    This Remedial Investigation Report on Waste Area Grouping, (NVAG) 5 at Oak Ridge National Laboratory was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting, the results of a site chacterization for public review. This work was performed under Work Breakdown Structure 1.4.12.6.1.05.40.02 (Activity Data Sheet 3305, ''WAG 5''). Publication of this document meets a Federal Facility Agreement milestone of March 31, 1995. This document provides the Environmental Restoration Program with information about the results of investigations performed at WAG 5. It includes information on risk assessments that have evaluated long-term impacts to human health and the environment. Information provided in this document forms the basis for decisions regarding, the need for subsequent remediation work at WAG 5

  16. Remedial investigation report on Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 3, Appendix B, Technical findings and conclusions

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-03-01

    This Remedial Investigation Report on Waste Area Grouping, (NVAG) 5 at Oak Ridge National Laboratory was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting, the results of a site chacterization for public review. This work was performed under Work Breakdown Structure 1.4.12.6.1.05.40.02 (Activity Data Sheet 3305, ``WAG 5``). Publication of this document meets a Federal Facility Agreement milestone of March 31, 1995. This document provides the Environmental Restoration Program with information about the results of investigations performed at WAG 5. It includes information on risk assessments that have evaluated long-term impacts to human health and the environment. Information provided in this document forms the basis for decisions regarding, the need for subsequent remediation work at WAG 5.

  17. Remedial investigation work plan for the Upper East Fork Poplar Creek characterization area, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-09-01

    The Oak Ridge Y-12 Plant, located within the Oak Ridge Reservation (ORR), is owned by the US Department of Energy (DOE) and managed by Lockheed Martin Energy Systems, Inc. The entire ORR was placed on the National Priorities List (NPL) of CERCLA sites in November 1989. Following CERCLA guidelines, sites under investigation require a remedial investigation (RI) to define the nature and extent of contamination, evaluate the risks to public health and the environment, and determine the goals for a feasibility study (FS) of potential remedial actions. The need to complete RIs in a timely manner resulted in the establishment of the Upper East Fork Poplar Creek (UEFPC) Characterization Area (CA) and the Bear Creek CA. The CA approach considers the entire watershed and examines all appropriate media within it. The UEFPC CA, which includes the main Y-12 Plant area, is an operationally and hydrogeologically complex area that contains numerous contaminants and containment sources, as well as ongoing industrial and defense-related activities. The UEFPC CA also is the suspected point of origin for off-site groundwater and surface-water contamination. The UEFPC CA RI also will address a carbon-tetrachloride/chloroform-dominated groundwater plume that extends east of the DOE property line into Union Valley, which appears to be connected with springs in the valley. In addition, surface water in UEFPC to the Lower East Fork Poplar Creek CA boundary will be addressed. Through investigation of the entire watershed as one ''site,'' data gaps and contaminated areas will be identified and prioritized more efficiently than through separate investigations of many discrete units.

  18. 100 Areas CERCLA ecological investigations

    Energy Technology Data Exchange (ETDEWEB)

    Landeen, D.S.; Sackschewsky, M.R.; Weiss, S.

    1993-09-01

    This document reports the results of the field terrestrial ecological investigations conducted by Westinghouse Hanford Company during fiscal years 1991 and 1992 at operable units 100-FR-3, 100-HR-3, 100-NR-2, 100-KR-4, and 100-BC-5. The tasks reported here are part of the Remedial Investigations conducted in support of the Comprehensive Environmental Response, compensation, and Liability Act of 1980 studies for the 100 Areas. These ecological investigations provide (1) a description of the flora and fauna associated with the 100 Areas operable units, emphasizing potential pathways for contaminants and species that have been given special status under existing state and/or federal laws, and (2) an evaluation of existing concentrations of heavy metals and radionuclides in biota associated with the 100 Areas operable units.

  19. 100 Areas CERCLA ecological investigations

    International Nuclear Information System (INIS)

    Landeen, D.S.; Sackschewsky, M.R.; Weiss, S.

    1993-09-01

    This document reports the results of the field terrestrial ecological investigations conducted by Westinghouse Hanford Company during fiscal years 1991 and 1992 at operable units 100-FR-3, 100-HR-3, 100-NR-2, 100-KR-4, and 100-BC-5. The tasks reported here are part of the Remedial Investigations conducted in support of the Comprehensive Environmental Response, compensation, and Liability Act of 1980 studies for the 100 Areas. These ecological investigations provide (1) a description of the flora and fauna associated with the 100 Areas operable units, emphasizing potential pathways for contaminants and species that have been given special status under existing state and/or federal laws, and (2) an evaluation of existing concentrations of heavy metals and radionuclides in biota associated with the 100 Areas operable units

  20. CERCLA document flow: Compressing the schedule, saving costs, and expediting review at the Savannah River Site

    International Nuclear Information System (INIS)

    Hoffman, W.D.

    1991-01-01

    The purpose of this paper is to convey the logic of the CERCLA document flow including Work Plans, Characterization Studies, Risk Assessments, Remedial Investigations, Feasibility Studies, proposed plans, and Records of Decision. The intent is to show how schedules at the Savannah River Site are being formulated to accomplish work using an observational approach where carefully planned tasks can be initiated early and carried out in parallel. This paper will share specific proactive experience in working with the EPA to expedite projects, begin removal actions, take interim actions, speed document flow, and eliminate unnecessary documents from the review cycle

  1. Screening of Potential Remediation Methods for the 200-ZP-1 Operable Unit at the Hanford Site

    Energy Technology Data Exchange (ETDEWEB)

    Truex, Michael J.; Nimmons, Michael J.; Johnson, Christian D.; Dresel, P EVAN.; Murray, Christopher J.

    2006-08-07

    A screening-level evaluation of potential remediation methods for application to the contaminants of concern (COC) in the 200-ZP-1 Operable Unit at the Hanford Site was conducted based on the methods outlined in the Guidance for Conducting Remedial Investigations and Feasibility Studies under CERCLA Interim Final. The scope of this screening was to identify the most promising remediation methods for use in the more detailed analysis of remediation alternatives that will be conducted as part of the full feasibility study. The screening evaluation was conducted for the primary COC (potential major risk drivers). COC with similar properties were grouped for the screening evaluation. The screening evaluation was conducted in two primary steps. The initial screening step evaluated potential remediation methods based on whether they can be effectively applied within the environmental setting of the 200-ZP-1 Operable Unit for the specified contaminants. In the second step, potential remediation methods were screened using scoping calculations to estimate the scale of infrastructure, overall quantities of reagents, and conceptual approach for applying the method for each defined grouping of COC. Based on these estimates, each method was screened with respect to effectiveness, implementability, and relative cost categories of the CERCLA feasibility study screening process defined in EPA guidance.

  2. Remedial investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1992-12-01

    The enactment of the Resource Conservation and Recovery Act (RCRA) in 1976 and the Hazardous and Solid Waste Amendments (HSWA) to RCRA in 1984 created management requirements for hazardous waste fadities. The facilities within the Oak Ridge Reservation (ORR) were in the process of meeting the RCRA requirements when ORR was placed on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCIA) National Priorities List (NPL) on November 21, 1989. Under RCRA, the actions typically follow the RCRA Facility Assessment (RIFA)/RCRA Facility Investigation (RFI)/Coffective Measures Study (CMS)/Corrective Measures Implementation process. Under CERCLA, the actions follow the Pre at sign ary Assessment/Site Investigation (PA/Sl) Remedial Investigation Feasibility Study (RI/FS)/Remedial Design/Remedial Action process. The development of this document will incorporate requirements under both RCRA and CERCIA into an RI Work Plan for the lint phase of characterization of Bear Creek Valley (BCV) Operable Unit (OU) 4

  3. Remedial investigation/feasibility study work plan for the 100-KR-1 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-07-01

    Four areas of the Hanford Site (the 100, 200, 300, and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Figure 1-1 shows the location of these areas. Under the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et al. 1990a), signed by the Washington State Department of Ecology (Ecology), EPA, and the US Department of Energy (DOE), more than 1,000 inactive waste disposal and unplanned release sites on the Hanford Site have been grouped into a number of source and groundwater operable units. These operable units contain contamination in the form of hazardous waste, radioactive/hazardous mixed waste, and other CERCLA hazardous substances. Also included in the Tri-Party Agreement are 55 Resource Conservation and Recovery Act (RCRA) treatment, storage, or disposal (TSD) facilities that will be closed or permitted to operate in accordance with RCRA regulations, under the authority of Chapter 173-303 Washington Administrative Code (WAC). Some of the TSD facilities are included in the operable units. This work plan and the attached supporting project plans establish the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-KR-1 operable unit. The 100-KR-1 source operable unit is one of three source operable units in the 100-K Area. Source operable units include facilities and unplanned release sites that are potential sources of hazardous substance contamination

  4. Threatened and endangered wildlife species of the Hanford Site related to CERCLA characterization activities

    Energy Technology Data Exchange (ETDEWEB)

    Fitzner, R.E. [Pacific Northwest Lab., Richland, WA (United States); Weiss, S.G.; Stegen, J.A. [Westinghouse Hanford Co., Richland, WA (United States)

    1994-06-01

    The US Department of Energy`s (DOE) Hanford Site has been placed on the National Priorities List, which requires that it be remediated under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or Superfund. Potentially contaminated areas of the Hanford Site were grouped into operable units, and detailed characterization and investigation plans were formulated. The DOE Richland Operations Office requested Westinghouse Hanford Company (WHC) to conduct a biological assessment of the potential impact of these characterization activities on the threatened, endangered, and sensitive wildlife species of the Hanford Site. Additional direction for WHC compliances with wildlife protection can be found in the Environmental Compliance Manual. This document is intended to meet these requirements, in part, for the CERCLA characterization activities, as well as for other work comparable in scope. This report documents the biological assessment and describes the pertinent components of the Hanford Site as well as the planned characterization activities. Also provided are accounts of endangered, threatened, and federal candidate wildlife species on the Hanford Site and information as to how human disturbances can affect these species. Potential effects of the characterization activities are described with recommendations for mitigation measures.

  5. An analysis of the CERCLA response program and the RCRA corrective action program in determining cleanup strategies for federal facilities which have been proposed for listing on the National Priorities List

    International Nuclear Information System (INIS)

    Baker, P.; Vinson, R.

    1994-01-01

    This document was prepared as an issue paper for the Department of Energy to serve in the decision-making process for environmental restoration activities. The paper compares cleanup requirements under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) and those currently proposed under Subpart S of the Resource Conservation and Recovery Act (RCRA). The history and regulatory framework for both laws is discussed, and the process for environmental restoration actions under both regulatory programs is compared and contrasted. Contaminants regulated under CERCLA and RCRA differ significantly in that radioactive contaminants are subject to Environmental Protection Agency jurisdiction only under CERCLA. The DOE has the jurisdiction to implement radioactive waste management and cleanup levels under the Atomic Energy Act (AEA) at nuclear weapons facilities. For sites with significant amounts of contaminants which are radioactive only, cleanup under RCRA can present significant advantages, since the DOE can then manage restoration activities under its own authority. There are, conversely several significant advantages for a remedial action being conducted at a CERCLA site recognized on the National Priorities List (NPL). Other provisions in the CERCLA remediation and the RCRA corrective action process offer both advantages and disadvantages related to DOE environmental restoration programs. This paper presents a discussion of significant issues which should be considered in such negotiations

  6. Petroleum exclusion under CERCLA: A defense to liability

    International Nuclear Information System (INIS)

    Landreth, L.W.

    1991-01-01

    When CERCLA was originally passed in 1980, the petroleum industry lobbied successfully to exclude the term open-quotes petroleumclose quotes from the definition of a CERCLA section 101 (14) hazardous substance. Under CERCLA section 101 (33), petroleum is also excluded from the definition of a open-quotes pollutant or contaminant.close quotes Exclusion from the designation as a defined hazardous substance has provided a defense to liability under CERCLA section 107 when the release of petroleum occurs. The scope of the petroleum exclusion under CERCLA has been a critical and recurring issue arising in the context of Superfund response activities. Specifically, oil that is contaminated by hazardous substances during the refining process is considered open-quotes petroleumclose quotes under CERCLA and thus excluded from CERCLA response authority and liability unless specifically listed under RCRA or some other statute. The U.S. EPAs position is that contaminants present in used oil, or any other petroleum substance, do not fall within the petroleum exclusion. open-quotes Contaminants,close quotes as discussed here, are substances not normally found in refined petroleum fractions or present at levels which exceed those normally found in such fractions. If these contaminants are CERCLA hazardous substances, they are subject to CERCLA response authority and liability. This paper discusses the parameters of the CERCLA open-quotes Petroleum Exclusion.close quotes It briefly examines selected state laws, RCRA, the Clean Water Act (CWA) and the Safe Drinking Water Act (SDWA) for treatment of petroleum and petroleum products. And, finally, this paper discusses new legislation regarding oil pollution liability and compensation

  7. Remedial investigation concept plan for the groundwater operable units at the chemical plant area and the ordnance works area, Weldon Spring, Missouri

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-07-15

    The U.S. Department of Energy (DOE) and the U.S. Department of the Army (DA) are conducting cleanup activities at two properties--the DOE chemical plant area and the DA ordnance works area (the latter includes the training area)--located in the Weldon Spring area in St. Charles County, Missouri. These areas are on the National Priorities List (NPL), and cleanup activities at both areas are conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. DOE and DA are conducting a joint remedial investigation (RI) and baseline risk assessment (BRA) as part of the remedial investigation/feasibility study (RI/FS) for the groundwater operable units for the two areas. This joint effort will optimize further data collection and interpretation efforts and facilitate overall remedial decision making since the aquifer of concern is common to both areas. A Work Plan issued jointly in 1995 by DOE and the DA discusses the results of investigations completed at the time of preparation of the report. The investigations were necessary to provide an understanding of the groundwater system beneath the chemical plant area and the ordnance works area. The Work Plan also identifies additional data requirements for verification of the evaluation presented.

  8. Remedial investigation concept plan for the groundwater operable units at the chemical plant area and the ordnance works area, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1999-01-01

    The U.S. Department of Energy (DOE) and the U.S. Department of the Army (DA) are conducting cleanup activities at two properties--the DOE chemical plant area and the DA ordnance works area (the latter includes the training area)--located in the Weldon Spring area in St. Charles County, Missouri. These areas are on the National Priorities List (NPL), and cleanup activities at both areas are conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. DOE and DA are conducting a joint remedial investigation (RI) and baseline risk assessment (BRA) as part of the remedial investigation/feasibility study (RI/FS) for the groundwater operable units for the two areas. This joint effort will optimize further data collection and interpretation efforts and facilitate overall remedial decision making since the aquifer of concern is common to both areas. A Work Plan issued jointly in 1995 by DOE and the DA discusses the results of investigations completed at the time of preparation of the report. The investigations were necessary to provide an understanding of the groundwater system beneath the chemical plant area and the ordnance works area. The Work Plan also identifies additional data requirements for verification of the evaluation presented

  9. Remedial investigation/feasibility study work plan for the 100-BC-5 Operable Unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1992-04-01

    Four areas of the Hanford Site (the 100, 200, 300 and 1100 Areas) have been included on the US Environmental Protection Agency's (EPA's) National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Figure 1-1 shows the location of these areas. Under the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et al. 1990a), signed by the Washington State Department of Ecology (Ecology), EPA, and the US Department of Energy (DOE), more than 1,000 inactive waste disposal and unplanned release sites on the Hanford Site have been grouped into a number of source and groundwater operable units. These operable units contain contamination in the form of hazardous waste, radioactive/hazardous mixed waste and other CERCLA hazardous substances. Also included in the Tri-Party Agreement are 55 Resource Conservation and Recovery Act (RCRA) treatment, storage, or disposal (TSD) facilities that will be closed or permitted to operate in accordance with RCRA regulations, under the authority of Chapter 173-303 Washington Administrative Code (WAC). Some of the TSD facilities are included in the operable units. This work plant and the attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the CERCLA remedial investigation/feasibility study (RI/FS) for the 100-BC-5 operable unit. The 100-B/C Area consists of the 100-BC-5 groundwater operable unit and four source operable units. The 100-BC-5 operable unit includes all contamination found in the aquifer soils and water beneath the 100-B/C Area. Source operable units include facilities and unplanned release sites that are potential sources of contamination

  10. Remedial investigation/feasibility study report for lower Watts Bar Reservoir Operable Unit

    International Nuclear Information System (INIS)

    1994-08-01

    This document is the combined Remedial Investigation and Feasibility Study Report for the Lower Watts Bar Reservoir (LWBR) Operable Unit (OU). The LWBR is located in Roane, Rhea, and Meigs counties, Tennessee, and consists of Watts Bar Reservoir downstream of the Clinch River. This area has received hazardous substances released over a period of 50 years from the U.S. Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). As required by this law, the ORR and all off-site areas that have received containments, including LWBR, must be investigated to determine the risk to human health and the environment resulting from these releases, the need for any remedial action to reduce these risks, and the remedial actions that are most feasible for implementation in this OU. Contaminants from the ORR are primarily transported to the LWBR via the Clinch River. Water-soluble contaminants released to ORR surface waters are rapidly diluted upon entering the Clinch River and then quickly transported downstream to the Tennessee River where further dilution occurs. Almost the entire quantity of these diluted contaminants rapidly flows through LWBR. In contrast, particle-associated contaminants tend to accumulate in the lower Clinch River and in LWBR in areas of sediment deposition. Those particle-associated contaminants that were released in peak quantities during the early years of ORR operations (e.g., mercury and 137 Cs) are buried under as much as 80 cm of cleaner sediment in LWBR. Certain contaminants, most notably polychlorinated biphenyls (PCBs), have accumulated in LWBR biota. The contamination of aquatic biota with PCBs is best documented for certain fish species and extends to reservoirs upstream of the ORR, indicating a contamination problem that is regional in scope and not specific to the ORR

  11. Sitewide soil and debris management program for a DOE site under remediation

    International Nuclear Information System (INIS)

    Harvey, B.F.

    1993-01-01

    In 1986, the United States Department of Energy (DOE) and the United States Environmental Protection Agency (US EPA) entered into a Federal Facility Compliance Agreement (FFCA). The agreement included provisions to investigate and define the nature and extent of contamination and to determine the necessity for remediation at the Fernald Environmental Management Project (FEMP) near Cincinnati, Ohio. The agreement is also pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Uranium enrichment production activities at the facility ceased in 1989. The FEMP mission is now environmental clean-up and remediation under the management of the Fernald Environmental Restoration Management Corporation. This report describes objectives and activities of remediation efforts at FEMP

  12. Remedial Investigation of Hanford Site Releases to the Columbia River - 13603

    Energy Technology Data Exchange (ETDEWEB)

    Lerch, J.A.; Hulstrom, L.C. [Washington Closure Hanford, LLC, Richland, Washington 99354 (United States); Sands, J.P. [U.S Department of Energy, Richland Operations Office, Richland, Washington 99352 (United States)

    2013-07-01

    In south-central Washington State, the Columbia River flows through the U.S. Department of Energy Hanford Site. A primary objective of the Hanford Site cleanup mission is protection of the Columbia River, through remediation of contaminated soil and groundwater that resulted from its weapons production mission. Within the Columbia River system, surface water, sediment, and biota samples related to potential Hanford Site hazardous substance releases have been collected since the start of Hanford operations. The impacts from release of Hanford Site radioactive substances to the Columbia River in areas upstream, within, and downstream of the Hanford Site boundary have been previously investigated as mandated by the U.S. Department of Energy requirements under the Atomic Energy Act. The Remedial Investigation Work Plan for Hanford Site Releases to the Columbia River [1] was issued in 2008 to initiate assessment of the impacts under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 [2]. The work plan established a phased approach to characterize contaminants, assess current risks, and determine whether or not there is a need for any cleanup actions. Field investigation activities over a 120-mile stretch of the Columbia River began in October 2008 and were completed in 2010. Sampled media included surface water, pore water, surface and core sediment, island soil, and fish (carp, walleye, whitefish, sucker, small-mouth bass, and sturgeon). Information and sample results from the field investigation were used to characterize current conditions within the Columbia River and assess whether current conditions posed a risk to ecological or human receptors that would merit additional study or response actions under CERCLA. The human health and ecological risk assessments are documented in reports that were published in 2012 [3, 4]. Conclusions from the risk assessment reports are being summarized and integrated with remedial investigation

  13. Remedial investigation plan for Waste Area Grouping 1 at Oak Ridge National Laboratory, Oak Ridge, Tennessee: Responses to regulator comments

    International Nuclear Information System (INIS)

    1991-05-01

    This document, ES/ER-6 ampersand D2, is a companion document to ORNL/RAP/Sub-87/99053/4 ampersand R1, Remedial Investigation Plan for ORNL Waste Area Grouping 1, dated August 1989. This document lists comments received from the Environmental Protection Agency, Region 4 (EPA) and the Tennessee Department of Health and Environment (TDHE) and responses to each of these comments. As requested by EPA, a revised Remedial Investigation (RI) Plan for Waste Area Grouping (WAG) 1 will not be submitted. The document is divided into two Sections and Appendix. Section I contains responses to comments issued on May 22, 1990, by EPA's Region 4 program office responsible for implementing the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Section 2 contains responses to comments issued on April 7, 1989, by EPA's program office responsible for implementing the Resource Conservation and Recovery Act (RCRA); these comments include issues raised by the TDHE. The Appendix contains the attachments referenced in a number of the responses. 35 refs

  14. Argonne's Expedited Site Characterization: An integrated approach to cost- and time-effective remedial investigation

    International Nuclear Information System (INIS)

    Burton, J.C.; Walker, J.L.; Aggarwal, P.K.; Meyer, W.T.

    1995-01-01

    Argonne National Laboratory has developed a methodology for remedial site investigation that has proven to be both technically superior to and more cost- and time-effective than traditional methods. This methodology is referred to as the Argonne Expedited Site Characterization (ESC). Quality is the driving force within the process. The Argonne ESC process is abbreviated only in time and cost and never in terms of quality. More usable data are produced with the Argonne ESC process than with traditional site characterization methods that are based on statistical-grid sampling and multiple monitoring wells. This paper given an overview of the Argonne ESC process and compares it with traditional methods for site characterization. Two examples of implementation of the Argonne ESC process are discussed to illustrate the effectiveness of the process in CERCLA (Comprehensive Environmental Response, Compensation, and Liability Act) and RCRA (Resource Conservation and Recovery Act) programs

  15. Status report: Fernald site remediation

    International Nuclear Information System (INIS)

    Craig, J.R. Jr.; Saric, J.A.; Schneider, T.; Yates, M.K.

    1995-01-01

    The Fernald site is rapidly transitioning from a Remedial Investigation/ Feasibility Study (RI/FS) site to one where design and construction of the remedies dominates. Fernald is one of the first sites in the Department of Energy (DOE) complex to accomplish this task and real physical progress is being made in moving the five operable units through the CERCLA process. Two of the required Records of Decision (ROD) are in hand and all five operable units will have received their RODs (IROD for OU3) by the end of 1995. Pre-design investigations, design work or construction are now in progress on the operable units. The lessons learned from the work done to date include implementing innovations in the RI and FS process as well as effective use of Removal Actions to begin the actual site remediation. Also, forging close working relationships with the Federal and State Regulators, citizens action groups and the Fernald Citizens Task Force has helped move the program forward. The Fernald successes have been achieved by close coordination and cooperation among all groups working on the projects and by application of innovative technologies within the decision making process

  16. Proposed plan for remedial action at the quarry residuals operable unit of the Weldon Spring Site

    International Nuclear Information System (INIS)

    1998-03-01

    This proposed plan addresses the management of contamination present in various components of the quarry residuals operable unit (QROU) of the Weldon Spring site, which is located in St. Charles County, Missouri. The QROU consists of (1) residual waste at the quarry proper; (2) the Femme Osage Slough, Little Femme Osage Creek, and Femme Osage Creek; and (3) quarry groundwater located primarily north of the slough. Potential impacts to the St. Charles County well field downgradient of the quarry area are also being addressed as part of the evaluations for this operable unit. Remedial activities for the QROU will be conducted by the US Department of Energy (DOE) in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. As part of the remedial investigation/feasibility study (RI/FS) process required for the QROU under CERCLA, three major evaluation documents have been prepared to support cleanup decisions for this operable unit. decisions for this operable unit

  17. Interim action record of decision remedial alternative selection: TNX area groundwater operable unit

    International Nuclear Information System (INIS)

    Palmer, E.R.

    1994-10-01

    This document presents the selected interim remedial action for the TNX Area Groundwater Operable Unit at the Savannah River Site (SRS), which was developed in accordance with CERCLA of 1980, as amended by the Superfund Amendments and Reauthorization Act (SARA) of 1986, and to the extent practicable, the National Oil and Hazardous Substances Pollution contingency Plan (NCP). This decision is based on the Administrative Record File for this specific CERCLA unit

  18. Remedial design work plan for Lower East Fork Poplar Creek Operable Unit, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-10-01

    The Remedial Design Work Plan (RDWP) for Lower East Fork Poplar Creek (EFPC) Operable Unit (OU) in Oak Ridge, Tennessee. This remedial action fits into the overall Oak Ridge Reservation (ORR) cleanup strategy by addressing contaminated floodplain soil. The objective of this remedial action is to minimize the risk to human health and the environment from contaminated soil in the Lower EFPC floodplain pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Federal Facility Agreement (FFA) (1992). In accordance with the FFA, a remedial investigation (RI) (DOE 1994a) and a feasibility study (DOE 1994b) were conducted to assess contamination of the Lower EFPC and propose remediation alternatives. The remedial investigation determined that the principal contaminant is mercury, which originated from releases during Y-12 Plant operations, primarily between 1953 and 1963. The recommended alternative by the feasibility study was to excavate and dispose of floodplain soils contaminated with mercury above the remedial goal option. Following the remedial investigation/feasibility study, and also in accordance with the FFA, a proposed plan was prepared to more fully describe the proposed remedy.

  19. Remedial design and remedial action guidance for the Idaho National Engineering Laboratory

    International Nuclear Information System (INIS)

    1993-10-01

    The US Department of Energy, Idaho Operations Office (DOE-ID), the US Environmental Protection Agency, Region X (EPA), and the Idaho Department of Health and Welfare (IDHW) have developed this guidance on the remedial design and remedial action (RD/RA) process. This guidance is applicable to activities conducted under the Idaho National Engineering Laboratory (INEL) Federal Facility Agreement and Consent Order (FFA/CO) and Action Plan. The INEL FFA/CO and Action Plan provides the framework for performing environmental restoration according to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). The guidance is intended for use by the DOE-ID, the EPA, and the IDHW Waste Area Group (WAG) managers and others involved in the planning and implementation of CERCLA environmental restoration activities. The scope of the guidance includes the RD/RA strategy for INEL environmental restoration projects and the approach to development and review of RD/RA documentation. Chapter 2 discusses the general process, roles and responsibilities, and other elements that define the RD/RA strategy. Chapters 3 through 7 describe the RD/RA documents identified in the FFA/CO and Action Plan. Chapter 8 provides examples of how this guidance can be applied to restoration projects. Appendices are included that provide excerpts from the FFA/CO pertinent to RD/RA (Appendix A), a applicable US Department of Energy (DOE) orders (Appendix B), and an EPA Engineering ''Data Gaps in Remedial Design'' (Appendix C)

  20. The National Historic Preservation Act is Not Your Problem, But How You are Addressing it for Your CERCLA Project May Be - 12344

    Energy Technology Data Exchange (ETDEWEB)

    Cusick, Lesley T. [Restoration Services, Inc. (RSI), Oak Ridge, Tennessee (United States)

    2012-07-01

    The 1995 Environmental Protection Agency (EPA) and U.S. Department of Energy (DOE) joint 'Policy on Decommissioning of Department of Energy Facilities Under CERCLA was developed so that decommissioning could occur in a manner that ensures protection of worker and public health and the environment, that is consistent with Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), that provides for stakeholder involvement, and that achieves risk reduction without unnecessary delay'. The source of the 'unnecessary delays' the joint policy intended to avert could be attributed to numerous factors such as obtaining permits, conducting administrative activities, or implementing regulatory processes that could yield, among other things, differing preferred alternatives. Why, you might ask, more than fifteen years later, does DOE continue to struggle through CERCLA projects with unnecessary delays? From problem identification, to determination of nature and extent, to alternative analysis and ultimately remedy selection and implementation, reaching a compliant and effective clean-up end-point can be a process that seems to mimic geologic timescales. The source of these delays is often the failure to use all of the tools the CERCLA process offers. As one example, renewed commitment to follow the CERCLA process to address the regulatory reviews pursuant to the National Historic Preservation Act (NHPA) is called for. Project managers implementing CERCLA actions in any agency, not only DOE, do not need to be apprehensive about using the CERCLA process for NHPA review but should welcome it. It is critical that methods are used that address substantive NHPA requirements clearly and consistently, and that they are shared and communicated as frequently as needed to interested and questioning stakeholders. (author)

  1. Proposed plan for remedial action for the Groundwater Operable Unit at the Chemical Plant Area of the Weldon Spring Site, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1999-01-01

    This Proposed Plan addresses the remediation of groundwater contamination at the chemical plant area of the Weldon Spring site in Weldon Spring, Missouri. The site is located approximately 48 km (30 mi) west of St. Louis in St. Charles County . Remedial activities at the site will be conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). The U.S. Department of Energy (DOE), in conjunction with the U.S. Department of the Army (DA), conducted a joint remedial investigation/feasibility study (RI/FS) to allow for a comprehensive evaluation of groundwater conditions at the Weldon Spring chemical plant area and the Weldon Spring ordnance works area, which is an Army site adjacent to the chemical plant area. Consistent with DOE policy, National Environmental Policy Act (NEPA) values have been incorporated into the CERCLA process. That is, the analysis conducted and presented in the RVFS reports included an evaluation of environmental impacts that is comparable to that performed under NEPA. This Proposed Plan summarizes information about chemical plant area groundwater that is presented in the following documents: (1) The Remedial Investigation (RI), which presents information on the nature and extent of contamination; (2) The Baseline Risk Assessment (BRA), which evaluates impacts to human health and the environment that could occur if no cleanup action of the groundwater were taken (DOE and DA 1997a); and (3) The Feasibility Study (FS) and the Supplemental FS, which develop and evaluate remedial action alternatives for groundwater remediation

  2. Remedial investigation/feasibility study work plan for the 100-BC-2 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1993-05-01

    This work plan and attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) remedial investigation/feasibility study (RI/FS) for the 100-BC-2 operable unit in the 100 Area of the Hanford Site. The 100 Area is one of four areas at the Hanford Site that are on the US Environmental Protection Agency's (EPA) National Priorities List under CERCLA. The 100-BC-2 operable unit is one of two source operable units in the 100-B/C Area (Figure ES-1). Source operable units are those that contain facilities and unplanned release sites that are potential sources of hazardous substance contamination. The 100-BC-2 source operable unit contains waste sites that were formerly in the 100-BC-2, 100-BC-3, and 100-BC-4 operable units. Because of their size and geographic location, the waste sites from these two operable units were added to 100-BC-2. This allows for a more efficient and effective investigation of the remaining 100-B/C Reactor area waste sites. The investigative approach to waste sites associated with the 100-BC-2 operable unit are listed in Table ES-1. The waste sites fall into three general categories: high priority liquid waste disposal sites, low priority liquid waste disposal sites, and solid waste burial grounds. Several sites have been identified as candidates for conducting an IRM. Two sites have been identified as warranting additional limited field sampling. The two sites are the 116-C-2A pluto crib, and the 116-C-2C sand filter

  3. Source evaluation report phase 2 investigation: Limited field investigation. Final report: United States Air Force Environmental Restoration Program, Eielson Air Force Base, Alaska

    Energy Technology Data Exchange (ETDEWEB)

    1994-10-01

    This report describes the limited field investigation work done to address issues and answer unresolved questions regarding a collection of potential contaminant sources at Eielson Air Force Base (AFB), near Fairbanks, Alaska. These sources were listed in the Eielson AFB Federal Facility Agreement supporting the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) cleanup of the base. The limited field investigation began in 1993 to resolve all remaining technical issues and provide the data and analysis required to evaluate the environmental hazard associated with these sites. The objective of the limited field investigation was to allow the remedial project managers to sort each site into one of three categories: requiring remedial investigation/feasibility study, requiring interim removal action, or requiring no further remedial action.

  4. CERCLA integration with site operations the Fernald experience

    International Nuclear Information System (INIS)

    Coyle, S.W.; Shirley, R.S.; Varchol, B.D.

    1991-01-01

    A major transition in the Fernald Environmental Management Project (FEMP) site mission has occurred over the past few years. The production capabilities formally provided by the FEMP are being transferred to private industry through a vendor qualification program. Environmental compliance and site cleanup are now the primary focus. In line with this program, the production of uranium products at the site was suspended in July 1989 in order to concentrate resources on the environmental mission. Formal termination of the FEMP production mission was accomplished on June 19, 1991. Environmental issues such as stored inventories of process residues materials and equipment are being addressed under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA). The diversity of these hazards complicates the strategic planning for an integrated site cleanup program. The FEMP is one of the first Department of Energy (DOE) facilities to transition from an active production mission guided by Defense Programs (DP) to an environmental mission guided by Environmental Management (EM) under Leo Duffy. Westinghouse Environmental Management Company of Ohio (WEMCO) has been charged with integrating all site activities to carry out the cleanup. A new management structure has been formulated, and an integration approach initiated. Analyses are under way to evaluate all site activities such as waste management, safe shutdown, product material disposition and routine environmental monitoring in view of CERCLA requirements. Site activities are being broken down into three categories: (a) CERCLA driven - restoration work required under CERCLA, (b) CERCLA covered - other environmental requirements which must be integrated with CERCLA, and (c) CERCLA exempt (if any). The approach to comply with these categorized activities must be negotiated with state and federal regulatory agencies

  5. Integrating innovative technology into remedial action at a US Department of Energy facility

    International Nuclear Information System (INIS)

    Diggs, I.W.

    1992-01-01

    The US Atomic Energy Commission (AEC), predecessor to the US Department Energy (DOE), established a production complex in the early 1950's for processing uranium and its compounds from natural uranium ore concentrates for the purpose of producing high purity uranium metal for various uses in defense reactor and nuclear weapons programs. This complex, previously known as the Feed Materials Production Center (FMPC), is now known as the Fernald Environmental Management Project (FEMP). In 1989, production was stopped at the feed materials facility due to a decision by the DOE. In December of 1989, the site was placed on the US EPA's National Priorities List (NPL) of sites requiring environmental cleanup. As a result, in April of 1990 the DOE and the US EPA signed a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Consent Agreement which augmented the FFCA. The DOE recently decided that production at the facility would not be resumed, and therefore, the main scope of work would change to remediation and closure of the site. In response to the FFCA and consistent with the modifications agreed to in the amended Consent Agreement, a Remedial Investigation/Feasibility Study (RI/FS) is in progress pursuant to CERCLA, as amended by the Superfund Amendments and Reauthorization Act (SARA). A RI/FS is a comprehensive environmental investigation systematically conducted according to US EPA regulations and guidelines used to identify and select an action plan for the cleanup of CERCLA sites. The RI phase incorporates a broad-based study to evaluate as completely as possible existing environmental and public health risks associated with past or existing facility operations. The FS phase develops and evaluates corrective action alternatives to mitigate identified environmental concerns

  6. Guidance for performing site inspections under CERCLA

    Energy Technology Data Exchange (ETDEWEB)

    1992-09-01

    This guidance presents EPA`s site inspection (SI) strategy. The strategy discusses procedural guidelines to investigate potential Superfund (CERCLA) sites for evaluation pursuant to the Hazard Ranking System (HRS), revised in accordance with the Superfund Amendments and Reauthorization Act of 1986. The HRS is the primary means by which EPA evaluates sites for superfund`s National Priorities List (NPL).

  7. Preliminary data report of investigations conducted at the Salmon Site, Lamar County, Mississippi

    International Nuclear Information System (INIS)

    1994-04-01

    The US Department of Energy (DOE) conducted ecological studies at the Salmon Site (SS), Lamar County, Mississippi, from the middle of June 1992 to the end of April 1993. The studies are part of the Remedial Investigation and Feasibility Study (RI/FS) being conducted by the DOE. The RI/FS is the methodology under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, as amended by the Superfund Amendments and Reauthorization Act of 1986 (CERCLA/SARA) for evaluating hazardous waste sites on the National Priorities List (NPL). The Salmon Site is not listed on the NPL but DOE has voluntarily elected to conduct the evaluation of the SS in accordance with CERCLA/SARA. As part of the remedial investigation, baseline human health and ecological risk assessments will be conducted. These baseline risk assessments will evaluate the potential impact on human health and the environment if remedial actions are not conducted, identify locations where additional information needs to be collected, help determine whether remedial actions are necessary, and provide justification for performing remedial actions. This report describes the sampling activities conducted between February and April 1993 to aid in evaluating the possible environmental impacts at the SS tailored to the specific circumstances and conditions found there. The initial investigations included identification of the flora and fauna in and around the SS, with particular emphasis on identifying sensitive environments, endangered species and their habitats, and those species consumed by humans or found in human food chains

  8. Potential CERCLA reauthorization issues relevant to US DOE's Environmental Restoration Program

    International Nuclear Information System (INIS)

    Siegel, M.R.; McKinney, M.D.; Jaksch, J.A.; Dailey, R.L.

    1993-02-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) is currently scheduled to be reauthorized in 1994. The US Department of Energy (DOE) has a significant stake in CERCLA reauthorization. CERCLA, along with its implementing regulation, the National Contingency Plan (NCP), is the principal legal authority governing DOE's environmental restoration program. The manner in which CERCLA-related issues are identified, evaluated, and dispatched may have a substantial impact on DOE's ability to conduct its environmental restoration program. A number of issues that impact DOE's environmental restoration program could be addressed through CERCLA reauthorization. These issues include the need to (1) address how the National Environmental Policy Act (NEPA) should be integrated into DOE CERCLA actions, (2) facilitate the streamlining of the Superfund process at DOE sites, (3) address the conflicts between the requirements of CERCLA and the Resource Conservation and Recovery Act (RCRA) that are especially relevant to DOE, (4) examine the criteria for waiving applicable or relevant and appropriate requirements (ARARs) at DOE sites, and (5) delineate the appropriate use of institutional controls at DOE sites

  9. Record of decision remedial alternative selection for the F-area burning/rubble pits (231-F, 231-1F, and 231-2F)

    International Nuclear Information System (INIS)

    Palmer, E.

    1997-02-01

    This decision document presents the selected remedial alternative for the FBRP located at the SRS in Aiken, South Carolina. The selected alternative was developed in accordance with CERCLA, as amended, and to the extent practicable, the National Oil and Hazardous Substances Pollution Contingency Plan. This decision is based on the Administrative Record File for this specific RCRA/CERCLA unit

  10. Preliminary remediation goals for ecological endpoints

    International Nuclear Information System (INIS)

    Efroymson, R.A.; Suter, G.W. II; Sample, B.E.; Jones, D.S.

    1996-07-01

    Preliminary remediation goals (PRGs) are useful for risk assessment and decision making at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites. PRGs are upper concentration limits for specific chemicals in specific environmental media that are anticipated to protect human health or the environment. They can be used for multiple remedial investigations at multiple facilities. In addition to media and chemicals of potential concern, the development of PRGs generally requires some knowledge or anticipation of future land use. In Preliminary Remediation Goals for Use at the U.S. Department of Energy Oak Ridge Operations Office (Energy Systems 1995), PRGs intended to protect human health were developed with guidance from Risk Assessment Guidance for Superfund: Volume I - Human Health Evaluation Manual, Part B (RAGS) (EPA 1991). However, no guidance was given for PRGs based on ecological risk. The numbers that appear in this volume have, for the most part, been extracted from toxicological benchmarks documents for Oak Ridge National Laboratory (ORNL) and have previously been developed by ORNL. The sources of the quantities, and many of the uncertainties associated with their derivation, are described in this technical memorandum

  11. Preliminary remediation goals for ecological endpoints

    International Nuclear Information System (INIS)

    Efroymson, R.A.; Suter, G.W. II.

    1995-09-01

    Preliminary remediation goals (PRGs) are useful for risk assessment and decision making at Comprehensive Environmental Response, compensation, and Liability Act (CERCLA) sites. PRGs are upper concentration limits for specific chemicals in specific environmental media that are anticipated to protect human health or the environment. They can be used for multiple remedial investigations at multiple facilities. In addition to media and chemicals of potential concern, the development of PRGs generally requires some knowledge or anticipation of future land use. In Preliminary Remediation Goals for Use at the US Department of Energy Oak Ridge Operations Office (Energy Systems 1995), PRGs intended to protect human health were developed with guidance from Risk Assessment Guidance for Superfund: Volume I-Human Health Evaluation Manual, Part B (RAGS) (EPA 1991). However, no guidance was given for PRGs based on ecological risk. The numbers that appear in this volume have, for the most part, been extracted from toxicological benchmarks documents for Oak Ridge National Laboratory (ORNL) and have previously been developed by ORNL. The sources of the quantities, and many of the uncertainties associated with their derivation, are described in this technical memorandum

  12. Inactive Tanks Remediation Program Batch I, Series I tanks 3001-B, 3004-B, 3013, and T-30 technical memorandum. Environmental Restoration Program

    International Nuclear Information System (INIS)

    1995-05-01

    This technical memorandum provides information that can be used to make decisions concerning the disposition of four inactive tank systems that have been designated Batch 1, Series 1, by the Inactive Tanks Remediation Program team. The Batch I, Series 1, tanks are 3001-B, 3004-B, 3013, and T-30. The report offers viable alternatives for tank system disposition. The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requires a Federal Facility Agreement (FFA) for federal facilities placed on the National Priorities List. The Oak Ridge Reservation was placed on that list on December 21, 1989, and the agreement was signed in November 1991 by DOE's Oak Ridge Operations Office, the US Environmental Protection Agency-Region IV, and the Tennessee Department of Environment and Conservation. The effective date of the FFA is January 1, 1992. One objective of the FFA is to ensure that inactive liquid low-level radioactive waste tank systems are evaluated and, if appropriate, remediated through the CERCLA process. The Inactive Tanks Remediation Program and the Gunite and Associated Tanks Project (GAAT) are the two efforts that will meet this FFA objective. This memorandum addresses tank systems within the Inactive Tanks Remediation Program. Separate CERCLA documentation addresses the tank systems within the GAAT Project

  13. NEPA/CERCLA integration at Rocky Flats

    International Nuclear Information System (INIS)

    Schassburger, R.J.

    1991-01-01

    Integration of two laws, the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the National Environmental Policy Act (NEPA) was mandated by the US Department of Energy (DOE) with issuance of DOE Order 5400.4 in October 6, 1989. NEPA documentation is required for all federal actions to thereby consider the impacts of such actions prior to the action taking place. On the other hand, CERCLA actions taken by the US Environmental Protection Agency (EPA) at non-federal and federal sites do not normally take NEPA into consideration, although it is not exempted at federal sites. EPA claims that CERCLA is functionally equivalent to N-EPA and therefore NEPA is not required. Although EPA maintains the functional equivalency of the two laws and formerly resisted to recognize NEPA even in Inter-Agency Agreements (IAGs), Rocky Flats has been integrating the two laws within documents to avoid duplication of information and effort

  14. 2011 Remediation Effectiveness Report for the U.S. Department of Energy Oak Ridge Reservation, Oak Ridge, Tennessee - Data and Evaluations

    Energy Technology Data Exchange (ETDEWEB)

    Bechtel Jacobs

    2011-03-01

    Under the requirements of the Oak Ridge Reservation (ORR) Federal Facility Agreement (FFA) established between the U.S. Department of Energy (DOE), the U.S. Environmental Protection Agency, (EPA) and the Tennessee Department of Environment and Conservation (TDEC) in 1992, all environmental restoration activities on the ORR are performed in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Since the 1990s, the environmental restoration activities have experienced a gradual shift from characterization to remediation. As this has occurred, it has been determined that the assessment of the individual and cumulative performance of all ORR CERCLA remedial actions (RAs) is most effectively tracked in a single document. The Remediation Effectiveness Report (RER) is an FFA document intended to collate all ORR CERCLA decision requirements, compare pre- and post-remediation conditions at CERCLA sites, and present the results of any required post-decision remediation effectiveness monitoring. First issued in 1997, the RER has been reissued annually to update the performance histories of completed actions and to add descriptions of new CERCLA actions. Monitoring information used in the 2011 RER to assess remedy performance was collected and/or compiled by DOE's Water Resources Restoration Program (WRRP). Only data used to assess performance of completed actions are provided. In addition to collecting CERCLA performance assessment data, the WRRP also collects baseline data to be used to gauge the effectiveness of future actions once implemented. These baseline data are maintained in the Oak Ridge Environmental Information System and will be reported in future RERs, as necessary, once the respective actions are completed. However, when insufficient data exist to assess the impact of the RAs, e.g., when the RA was only recently completed, a preliminary evaluation is made of early indicators of effectiveness at the

  15. 2010 Remediation Effectiveness Report for the U.S. Department of Energy Oak Ridge Reservation, Oak Ridge, Tennessee - Data and Evaluations

    Energy Technology Data Exchange (ETDEWEB)

    Bechtel Jacobs

    2010-09-01

    Under the requirements of the Oak Ridge Reservation (ORR) Federal Facility Agreement (FFA) established between the U.S. Department of Energy (DOE), the U.S. Environmental Protection Agency, (EPA) and the Tennessee Department of Environment and Conservation (TDEC) in 1992, all environmental restoration activities on the ORR are performed in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Since the 1990s, the environmental restoration activities have experienced a gradual shift from characterization to remediation. As this has occurred, it has been determined that the assessment of the individual and cumulative performance of all ORR CERCLA remedial actions (RAs) is most effectively tracked in a single document. The Remediation Effectiveness Report (RER) is an FFA document intended to collate all ORR CERCLA decision requirements, compare pre- and post-remediation conditions at CERCLA sites, and present the results of any required post-decision remediation effectiveness monitoring. First issued in 1997, the RER has been reissued annually to update the performance histories of completed actions and to add descriptions of new CERCLA actions. Monitoring information used in the 2010 RER to assess remedy performance was collected and/or compiled by DOE's Water Resources Restoration Program (WRRP). Only data used to assess performance of completed actions are provided. In addition to collecting CERCLA performance assessment data, the WRRP also collects baseline data to be used to gauge the effectiveness of future actions once implemented. These baseline data are maintained in the Oak Ridge Environmental Information System and will be reported in future RERs, as necessary, once the respective actions are completed. However, when insufficient data exist to assess the impact of the RAs, e.g., when the RA was only recently completed, a preliminary evaluation is made of early indicators of effectiveness at the

  16. Identification and evaluation of areas of interest (AOIs): A screening tool for CERCLA preliminary assessments

    International Nuclear Information System (INIS)

    Autry, A.R.; Allen, K.L.; Smith, L.A.; Schumacher, J.; McDermott, M.

    1994-01-01

    A cost-effective alternative to the traditional Preliminary Assessment (PA) procedure is to identify and evaluate potential Areas of Interest (AOIs) that may become Comprehensive Environmental Response, Liability and Compensation Act of 1980 (CERCLA) sites prior to entry into Comprehensive Environmental Response, Liability Information System (CERCLIS) and the execution of a PA. AOIs would be identified by using much of the same methodology as would be used for site discovery in a CERCLA investigation, including aerial photograph review, reviews of building drawings, a limited review of historical records, and limited interviews and site visits. Once AOIs have been identified in this manner, decision criteria can be used to ascertain the regulatory status of the AOI and, based on regulatory guidance, whether the site should be considered for further investigation under CERCLA. This approach was used at Griffiss Air Force Base to identify 463 AOIs, where the primary problem was petroleum spills

  17. Idaho CERCLA Disposal Facility Complex Compliance Demonstration for DOE Order 435.1

    Energy Technology Data Exchange (ETDEWEB)

    J. Simonds

    2006-09-01

    This compliance demonstration document provides an analysis of the Idaho CERCLA Disposal Facility (ICDF) Complex compliance with DOE Order 435.1. The ICDF Complex includes the disposal facility (landfill), evaporation pond, admin facility, weigh scale, decon building, treatment systems, and various staging/storage areas. These facilities were designed and are being constructed to be compliant with DOE Order 435.1, Resource Conservation and Recovery Act Subtitle C, and Toxic Substances Control Act polychlorinated biphenyl design and construction standards. The ICDF Complex is designated as the central Idaho National Laboratory (INL) facilityyy for the receipt, staging/storage, treatment, and disposal of INL Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) waste streams. This compliance demonstration document discusses the conceptual site model for the ICDF Complex area. Within this conceptual site model, the selection of the area for the ICDF Complex is discussed. Also, the subsurface stratigraphy in the ICDF Complex area is discussed along with the existing contamination beneath the ICDF Complex area. The designs for the various ICDF Complex facilities are also included in this compliance demonstration document. These design discussions are a summary of the design as presented in the Remedial Design/Construction Work Plans for the ICDF landfill and evaporation pond and the Staging, Storage, Sizing, and Treatment Facility. Each of the major facilities or systems is described including the design criteria.

  18. RCRA Facility Investigation/Remedial Investigation Report for the Gunsite 113 Access Road Unit (631-24G) - March 1996

    Energy Technology Data Exchange (ETDEWEB)

    Palmer, E. [Westinghouse Savannah River Company, AIKEN, SC (United States)

    1996-03-01

    Gunsite 113 Access Road Unit is located in the northeast corner of SRS. In the mid 1980`s, sparse vegetation, dead trees, and small mounds of soil were discovered on a portion of the road leading to Gunsite 113. This area became the Gunsite 113 Access Road Unit (Gunsite 113). The unit appears to have been used as a spoil dirt and / or road construction debris disposal area. There is no documentation or record of any hazardous substance management, disposal, or any type of waste disposal at this unit. Based upon the available evidence, there are no potential contaminants of concern available for evaluation by a CERCLA baseline risk assessment. Therefore, there is no determinable health risk associated with Gunsite 113. In addition, it is also reasonable to conclude that, since contamination is below risk-based levels, the unit presents no significant ecological risk. It is recommended that no further remedial action be performed at this unit.

  19. RCRA Facility Investigation/Remedial Investigation Report for the Gunsite 113 Access Road Unit (631-24G) - March 1996

    International Nuclear Information System (INIS)

    Palmer, E.

    1996-03-01

    Gunsite 113 Access Road Unit is located in the northeast corner of SRS. In the mid 1980's, sparse vegetation, dead trees, and small mounds of soil were discovered on a portion of the road leading to Gunsite 113. This area became the Gunsite 113 Access Road Unit (Gunsite 113). The unit appears to have been used as a spoil dirt and / or road construction debris disposal area. There is no documentation or record of any hazardous substance management, disposal, or any type of waste disposal at this unit. Based upon the available evidence, there are no potential contaminants of concern available for evaluation by a CERCLA baseline risk assessment. Therefore, there is no determinable health risk associated with Gunsite 113. In addition, it is also reasonable to conclude that, since contamination is below risk-based levels, the unit presents no significant ecological risk. It is recommended that no further remedial action be performed at this unit

  20. Responsiveness summary for the remedial investigation/feasibility study for management of the bulk wastes at the Weldon Spring quarry, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    Peterson, J.M.; MacDonell, M.M.

    1990-08-01

    The US Department of Energy (DOE) is responsible for conducting remedial actions at the Weldon Spring site in St. Charles County, Missouri, under its Surplus Facilities Management Program. The site consists of a quarry and a chemical plant area located about 6.4 km (4 mi) northeast of the quarry. The quarry is surrounded by the Weldon Spring Wildfire Area and is near an alluvial well field that constitutes a major source of potable water for St. Charles County; the nearest supply well is located about 0.8 km (0.5 mi) southeast of the quarry. From 1942 to 1969, the quarry was used for the disposal of various radioactively and chemically contaminated materials. Bulk wastes in the quarry consist of contaminated soils and sediments, rubble, metal debris, and equipment. As part of overall site remediation, DOE is proposing to conduct an interim remedial action at the quarry to manage the radioactively and chemically contaminated bulk wastes contained therein. Potential remedial action alternatives for managing the quarry bulk wastes have been evaluated consistent with US Environmental Protection Agency (EPA) guidance for conducting remedial actions under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. The contents of these documents were developed in consultation with EPA Region VII and the state of Missouri and reflect the focused scope defined for this interim remedial action. 9 refs

  1. Characterization and remediation of highly radioactive contaminated soil at Hanford

    International Nuclear Information System (INIS)

    Buckmaster, M.A.; Erickson, J.K.

    1993-09-01

    The Hanford Site, Richland, Washington, contains over 1,500 identified waste sites and numerous groundwater plumes that will be characterized and remediated over the next 30 years. As a result of the Hanford Federal Facility Agreement and Consent Order, the US Department of Energy (DOE) has initiated a remedial investigation/feasibility study (RI/FS) at the 200-BP-1 operable unit. The 200-BP-1 RI/FS is the first Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) investigation on the Hanford Site that involves highly radioactive and chemically contaminated soils. The initial phase of site characterization was designed to assess the nature and extent of contamination associated with the source waste sites within the 200-BP-1 operable unit. Characterization activities consisted of drilling and sampling, chemical and physical analysis of samples, and development of a conceptual vadose zone model. These data were then used. to develop remedial alternatives during the FS evaluation. The preferred alternative resulting from the RI/FS process for the 200-BP-1 operable unit is to construct a surface isolation barrier. The multi-layered earthen barrier will be designed to prevent migration of contaminants resulting from water infiltration, biointrusion, and wind and water erosion

  2. Savannah River Site RCRA/CERCLA/NEPA integrated investigation case study

    International Nuclear Information System (INIS)

    Clark, D.R.; Thomas, R.; Wilson, M.P.

    1992-01-01

    The Savannah River Site (SRS) is a US Department of Energy facility placed on the Superfund National Priority List in 1989. Numerous past disposal facilities and contaminated areas are undergoing the integrated regulatory remediation process detailed in the draft SRS Federal Facility Agreement. This paper will discuss the integration of these requirements by highlighting the investigation of the D-Area Burning/Rubble Pits, a typical waste unit at SRS

  3. Remediation of a large contaminated reactor cooling reservoir: Resolving and environmental/regulatory paradox

    Energy Technology Data Exchange (ETDEWEB)

    Bowers, J.A.: Gladden, J.B.; Hickey, H.M.; Jones, M.P.; Mackey, H.E.; Mayer, J.J. [Westinghouse Savannah River Co., Aiken, SC (United States); Doswell, A. [USDOE, Washington, DC (United States)

    1994-05-01

    This paper presents a case study of a former reactor cooling water reservoir, PAR Pond, located Savannah River Site. PAR Pond, a 2640 acre, man-made reservoir was built in 1958 and until 1988, received cooling water from two DOE nuclear production reactors, P and R. The lake sediments were contaminated with low levels of radiocesium (CS-137) and transuranics in the late 1950s and early 1960s because of leaking fuel elements. Elevated levels of mercury accumulated in the sediments from pumping water from the Savannah River to maintain a full pool. PAR Ponds` stability, size, and nutrient content made a significant, unique, and highly studied ecological resource for fish and wildlife populations until it was partially drained in 1991 due to a depression in the downslope of the earthen dam. The drawdown, created 1340 acres of exposed, radioactively contaminated sediments along 33 miles of shoreline. This led US EPA to declare PAR Pond as a CERCLA operable unit subject to remediation. The drawdown also raised concerns for the populations of aquatic plants, fish, alligators, and endangered species and increased the potential for off-site migration of contaminated wildlife from contact with the exposed sediments. Applicable regulations, such as NEPA and CERCLA, require wetland loss evaluations, human health and ecological risk assessments, and remediation feasibility studies. DOE is committed to spending several million dollars to repair the dam for safety reasons, even though the lake will probably not be used for cooling purposes. At the same time, DOE must make decisions whether to refill and expend additional public funds to maintain a full pool to reduce the risks defined under CERCLA or spend hundreds of millions in remediation costs to reduce the risks of the exposed sediments.

  4. Remediation of a large contaminated reactor cooling reservoir: Resolving an environmental/regulatory paradox

    International Nuclear Information System (INIS)

    Marcy, B.C.; Doswell, A.C.; Bowers, J.A.; Gladden, J.B.; Hickey, H.M.; Jones, M.P.; Mackey, H.E.; Mayer, J.J.

    1994-01-01

    This is a case study of a former reactor cooling water reservoir, PAR Pond, located at the U.S. Department of Energy's (DOE) Savannah River Site (SRS) in South Carolina. PAR Pond, a 2,640 acre, man-made reservoir was built in 1958 and until 1988, received cooling water from two DOE nuclear production reactors, P and R. The lake sediments were contaminated with low levels of mercury accumulated in the sediments from pumping water from the Savannah River. PAR Ponds' stability, size, and nutrient content made a significant, unique, and highly studied ecological resource for fish and wildlife populations in the southeast until it was partially drained in 1991 for safety reasons, to about one-third of its historic volume. The drawdown created 1340 acres of exposed, radioactively contaminated sediments along 33 miles of shoreline. EPA declared PAR Pond as a CERCLA operable unit subject to remediation. The drawdown also raised concerns for the populations of aquatic plants, fish, alligators, and endangered species and increased the potential for off-site migration of contaminated wildlife. Because of the paradox of this ecologically valuable, yet contaminated ecosystem, the lake's future ecological and operational management is uncertain. Applicable regulations, such as NEPA and CERCLA, require wetland loss evaluations, human health and ecological risk assessments, and remediation feasibility studies. DOE is committed to spending several million dollars to repair the dam for safety reasons, even though the lake will probably not be used for cooling purposes. At the same time, DOE must make decisions whether to refill and expend additional public funds to maintain a full pool to reduce the risks defined under CERCLA or spend hundreds of millions in remediation costs. This case represents the types of issues and conflicts that will need to be addressed within the DOE complex and globally as nuclear production facilities are transitioned to inactive status

  5. Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or Superfund, Section 104(k); and CERCLA Section 104(d); ‘‘ ‘Discounted Loans’ Under Brownfields Revolving Loan Fund Grants’

    Science.gov (United States)

    Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or Superfund, Section 104(k); and CERCLA Section 104(d); ‘‘ ‘Discounted Loans’ Under Brownfields Revolving Loan Fund Grants’`

  6. Direct liability of corporations and their personnel under CERCLA

    International Nuclear Information System (INIS)

    Landreth, L.W.

    1991-01-01

    The prevailing liability theory applied to those persons who have caused, through their action or inaction, the release of a hazardous substance is that CERCLA provides a statutory basis for direct personal liability This direct avenue to liability is in conflict with well-settled principles of corporate limited liability. This paper discusses the impact CERCLA has had on the common law concepts of liability for corporations and their members

  7. Feasibility study report for Operable Unit 4: Fernald Environmental Management Project, Fernald, Ohio: Remedial investigation and feasibility study: Volume 3: Final report

    International Nuclear Information System (INIS)

    1994-02-01

    This report documents the Feasibility Study (FS) phase of the Fernald Environmental Management Project (FEMP) Operable Unit 4 Remedial Investigation/Feasibility Study (RI/FS) Program. The FEMP, formerly known as the Feed Materials Production Center (FMPC), is a US Department of Energy (DOE) facility that operated from 1952 to 1989. The facility's primarily function was to provide high purity uranium metal products to support United States defense programs. Production operations were suspended in 1989 to focus on environmental restoration and waste management activities at the facility. The RI/FS is being conducted pursuant to the terms of a Consent Agreement between DOE and the US Environmental Protection Agency (EPA) under Sections 120 and 106(a) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. The Ohio Environmental Protection Agency (OEPA) is also participating in the RI/FS process at the FEMP through direct involvement in program review meetings and technical review of project documentation. The objective of the RI/FS process is to gather information to support an informed risk management decision regarding which remedy appears to be the most appropriate action for addressing the environmental concerns identified at the FEMP. This volume contains appendices F--J

  8. Glossary of CERCLA-related terms and acronyms

    International Nuclear Information System (INIS)

    1991-10-01

    This glossary contains CERCLA-related terms that are most often encountered in the US Department of Energy (DOE) Environmental Restoration and Emergency Preparedness activities. Detailed definitions are included for key terms. The definitions included in this glossary are taken from the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as amended, related federal rulemakings (e.g., 40 CFR 300, National Oil and Hazardous Substances Pollution Contingency Plan), assorted guidance documents prepared by the US Environmental Protection Agency (EPA), and DOE Order 5400.4. The source of each term is noted after the term. Terms presented in this document reflect revised and new definitions published before June 1, 1991. 20 refs

  9. Remedial Investigation Work Plan for Chestnut Ridge Operable Unit 1 (Chestnut Ridge Security Pits) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1993-09-01

    This Remedial Investigation (RI) Work Plan specifically addresses Chestnut Ridge Operable Unit 1, (OU1) which consists of the Chestnut Ridge Security Pits (CRSP). The CRSP are located {approximately}800 ft southeast of the central portion of the Y-12 Plant atop Chestnut Ridge, which is bounded to the northwest by Bear Creek Valley and to the southeast by Bethel Valley. Operated from 1973 to 1988, the CRSP consisted of a series of trenches used for the disposal of classified hazardous and nonhazardous waste materials. Disposal of hazardous waste materials was discontinued in December 1984, while nonhazardous waste disposal ended on November 8, 1988. An RI is being conducted at this site in response to CERCLA regulations. The overall objectives of the RI are to collect data necessary to evaluate the nature and extent of contaminants of concern (COC), support an ecological risk assessment (ERA) and a human health risk assessment (HHRA), support the evaluation of remedial alternatives, and ultimately develop a Record of Decision for the site. The purpose of this Work Plan is to outline RI activities necessary to define the nature and extent of suspected contaminants at Chestnut Ridge OU1. Potential migration pathways also will be investigated. Data collected during the RI will be used to evaluate the overall risk posed to human health and the environment by OU1.

  10. Remedial Investigation Work Plan for Chestnut Ridge Operable Unit 1 (Chestnut Ridge Security Pits) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-09-01

    This Remedial Investigation (RI) Work Plan specifically addresses Chestnut Ridge Operable Unit 1, (OU1) which consists of the Chestnut Ridge Security Pits (CRSP). The CRSP are located ∼800 ft southeast of the central portion of the Y-12 Plant atop Chestnut Ridge, which is bounded to the northwest by Bear Creek Valley and to the southeast by Bethel Valley. Operated from 1973 to 1988, the CRSP consisted of a series of trenches used for the disposal of classified hazardous and nonhazardous waste materials. Disposal of hazardous waste materials was discontinued in December 1984, while nonhazardous waste disposal ended on November 8, 1988. An RI is being conducted at this site in response to CERCLA regulations. The overall objectives of the RI are to collect data necessary to evaluate the nature and extent of contaminants of concern (COC), support an ecological risk assessment (ERA) and a human health risk assessment (HHRA), support the evaluation of remedial alternatives, and ultimately develop a Record of Decision for the site. The purpose of this Work Plan is to outline RI activities necessary to define the nature and extent of suspected contaminants at Chestnut Ridge OU1. Potential migration pathways also will be investigated. Data collected during the RI will be used to evaluate the overall risk posed to human health and the environment by OU1

  11. Oak Ridge National Laboratory remedial investigation/feasibility study

    International Nuclear Information System (INIS)

    Glenn, R.D.; Hoffman, J.M.; Hyde, L.D.

    1988-01-01

    The Oak Ridge National Laboratory (ORNL) Remedial Investigation/ Feasibility Study (RI/FS) began in June 1987 to evaluate 13 contaminated waste area groupings (WAGs) to determine the feasibility and benefits of potential remedial action. The RI/FS and any future remedial action at ORNL will be of national significance and will likely lead to developments that will become models for environmental investigations and cleanups. Bechtel National, Inc. and a team of subcontractors will be working with Martin Marietta Energy systems to conduct intensive field investigations to obtain data required to evaluate the WAGs. The RI/F project continued in FY 1988 with project planning and preparation for field activities. Remedial Investigation (RI) Plans were prepared for 10 of the 13 WAGs. These plans were developed with sufficient information to ensure compliance with regulatory requirements, with intensive attention given to environmental, safety, and health protection; waste management; data management; and quality assurance. This paper reports on the progress made during FY 1988 and discusses activities planned for FY 1989

  12. Inactive Tanks Remediation Program strategy and plans for Oak Ridge National Laboratory, Oak Ridge, Tennessee. Environmental Restoration Program

    International Nuclear Information System (INIS)

    1995-06-01

    The overall objective of the Inactive Tank Remediation Program is to remediate all LLLW tanks that have been removed fimn service to the extent practicable in accordance with the FFA and CERCLA requirements. Applicable or relevant and appropriate requirements (ARARs) will be addressed in choosing a remediation alternative. Preference will be given to remedies that are highly reliable and provide long-term protection. Efforts will be directed toward permanently and significantly reducing the volume, toxicity, or mobility of hazardous substances, pollutants, and contaminants associated with the tank systems. Where indicated by operational or other restraints, interim measures short of full and complete remediation may be taken to maintain human health and ecological risks at acceptable levels until full remediation can be accomplished

  13. Risks to humans and wildlife from metal contamination in soils/sediments at CERCLA sites

    International Nuclear Information System (INIS)

    Hitch, J.P.; Hovatter, P.S.; Opresko, D.M.; Sample, B.; Young, R.A.

    1994-01-01

    A common problem that occurs at DOD and DOE CERCLA sites is metal contamination in soils and aquatic sediments and the protection of humans and wildlife from potential exposure to this contamination. Consequently, the authors have developed a site-specific reference dose for mercury in sediments at the Oak Ridge Reservation and site-specific cleanup levels for certain metals, including arsenic and nickel, in soils at an Army ammunition plant. Another concern during remediation of these sites is that limited data are available to determine the direct risks to indigenous wildlife. Therefore, the authors have developed toxicological benchmarks for certain metals and metal compounds to be used as screening tools to determine the potential hazard of a contaminant to representative mammalian and avian wildlife species. These values should enable the Army and DOE to more accurately determine the risks to humans and wildlife associated with exposure to these contaminated media at their sites in order to achieve a more effective remediation. This effort is ongoing at ORNL with toxicological benchmarks also being developed for metal compounds and other chemicals of concern to DOD and DOE in order to address the potential hazard to

  14. Environmental compliance at U.S. Department of Energy FUSRAP (Formerly Utilized Sites Remedial Action Program) sites

    International Nuclear Information System (INIS)

    Liedle, S.D.; Clemens, B.W.

    1988-01-01

    With the promulgation of the Superfund Amendments and Reauthorization Act (SARA), federal facilities were required to comply with the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) in the same manner as any non-government entity. This presented challenges for the Department of Energy (DOE) and other federal agencies involved in remedial action work because there are many requirements under SARA that overlap other laws requiring DOE compliance, e.g., the National Environmental Policy Act (NEPA). This paper outlines the options developed to comply with CERCLA and NEPA as part of active, multi-site remedial action program. The program, the Formerly Utilized Sites Remedial Action Program (FUSRAP), was developed to identify, clean up, or control sites containing residual radioactive or chemical contamination as a result of the nation's early development of nuclear power. During the Manhattan Project, uranium was extracted from ores and resulted in mill concentrates, purified metals, and waste products that were transported for use or disposal at other locations. Figure 1 shows the steps for producing uranium metal during the Manhattan Project. As a result of these activities materials, equipment, buildings, and land became contaminated, primarily with naturally occurring radionuclides. Currently, FUSRAP includes 29 sites; three are on the Environmental Protection Agency's (EPA's) National Priorities List (NPL) of hazardous waste sites

  15. 200-ZP-1 IRM phase 2 and 3 remedial design report, Revision 1

    International Nuclear Information System (INIS)

    1996-07-01

    This 200-ZP-1 remedial design report presents the objectives and rationale developed for the design and implementation of the selected interim remedial measure (IRM) for the 200-ZP-1 Operable Unit, located in the 200 West Area of the Hanford Site.The IRM was chosen in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of 1986, the Hanford Federal Facility Agreement and Consent Order (also known as the Tri- party Agreement), and the National Oil and Hazardous Substance Pollution Contingency Plan

  16. Voluntary program promotes equitable and expedited remediation of contaminated properties

    Energy Technology Data Exchange (ETDEWEB)

    Wolfenden, A.K.; Cambridge, M. [California Environmental Protection Agency, Sacramento, CA (United States). Dept. of Toxic Substances Control

    1995-12-31

    In California, the California Environmental Protection Agency (Cal/EPA) has developed a more equitable and expedited approach for the redevelopment of sites contaminated with hazardous substances. Senate Bill 923 enacted in 1994, established the Expedited Remedial Action Program (ERAP) under Chapter 6.85 of the California Health and Safety Code. This bill responds to a nationwide demand to reform Superfund laws and promote the restoration of blighted and contaminated parcels--often referred to as Brownfields. The program was designed as an alternative to CERCLA, which has come under criticism for being inefficient, unfair and restricting opportunities for effective cleanups. Cal/EPA`s Department of Toxic Substances Control will implement this pilot program. This pilot program, which will eventually comprise 30 sites, provides incentives for voluntary remediation by addressing key economic issues associated with the remediation and redevelopment of contaminated properties.

  17. Salmon Site Remedial Investigation Report

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  18. Environmental restoration and remediation technical data management plan

    International Nuclear Information System (INIS)

    Key, K.T.; Fox, R.D.

    1994-02-01

    The tasks performed in the Remedial Investigation/Feasibility Study (RI/FS) work plan for each Hanford Site operable unit must meet the requirements of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) and the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et. al 1992). An extensive amount of data will be generated in the evaluation and remediation of hazardous waste sites at the Site. The data must be of sufficient quality, as they will be used to evaluate the need, select the method(s), and support the full remediation of the waste sites as stipulated in the Tri-Party Agreement. In particular, a data management plan (DMP) is to be included in an RI/FS work plan for managing the technical data obtained during the characterization of an operable unit, as well as other data related to the study of the operable unit. Resource Conservation and Recovery Act of 1976 (RCRA) sites are involved in the operable unit. Thus, the data management activities for the operable unit should be applied consistently to RCRA sites in the operable unit as well. This DMP provides common direction for managing-the environmental technical data of all defined operable units at the Hanford Site during the RI/FS activities. Details specific to an operable unit will be included in the actual work plan of that operable unit

  19. Applicable or Relevant and Appropriate Requirements (ARARs) for Remedial Action at the Oak Ridge Reservation: A compendium of major environmental laws

    International Nuclear Information System (INIS)

    Etnier, E.L.; McDonald, E.P.; Houlberg, L.M.

    1993-07-01

    Section 121 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980 specifies that remedial actions for cleanup of hazardous substances must comply with applicable or relevant and appropriate requirements (ARARS) or standards under federal and state environmental laws. The US Department of Energy (DOE) Oak Ridge Reservation (ORR) was placed on the National Priorities List by the US Environmental Protection Agency (EPA) on November 21, 1989, effective December 21, 1989. As a result of this listing, DOE, EPA, and the Tennessee Department of Environment and Conservation have signed a Federal Facility Agreement (FFA) for the environmental restoration of the ORR. Section XXI(F) of the FFA calls for the preparation of a draft listing of all ARARs as mandated by CERCLA section 121. This report supplies a preliminary list of available federal and state ARARs that might be considered for remedial response at the ORR. A description of the terms ''applicable'' and ''relevant and appropriate'' is provided, as well as definitions of chemical-, location-, and action-specific ARARS. ARARs promulgated by the federal government and by the state of Tennessee are listed in tables. In addition, the major provisions of the Resource Conservation and Recovery Act, the Safe Drinking Water Act, the Clean Water Act, the Clean Air and other acts, as they apply to hazardous waste cleanup, are discussed. In the absence of ARARS, CERCLA section 121 provides for the use of nonpromulgated federal criteria, guidelines, and advisories in evaluating the human risk associated with remedial action alternatives. Such nonpromulgated standards are classified as ''to-be-considered'' (TBC) guidance. A ion of available guidance is given; summary tables fist the available federal standards and guidance information. In addition, the substantive contents of the DOE orders as they apply to remediation of radioactively contaminated sites are discussed as TBC guidance

  20. Successful community relations efforts at the Weldon Spring Site Remedial Action Project

    International Nuclear Information System (INIS)

    McKee, James E. Jr.; Meyer, Linda L.

    1992-01-01

    The Weldon Spring Site Remedial Action Project (WSSRAP) Community Relations Program involves many participants from the U.S. Department of Energy (DOE) and the Prime Management Contractor (PMC) composed of M.K. Ferguson and Jacobs Engineering. The proactive community relations plan exceeds the compliance requirements of NEPA and CERCLA and is coordinated by a three-person staff of professional communicators. The program permeates many of the operating decisions and the result has been public acceptance of the Project and its actions to date, which has been to conduct remedial actions that will place the site in a radiologically and chemically safe condition, eliminating potential hazards to the public and environment. (author)

  1. Development of exposure scenarios for CERCLA risk assessments at the Savannah River Site

    International Nuclear Information System (INIS)

    Nix, D.W.; Immel, J.W.; Phifer, M.A.

    1992-01-01

    A CERCLA Baseline Risk Assessment (BRA) is performed to determine if there are any potential risks to human health and the environment from waste unit at SRS. The SRS has numerous waste units to evaluate in the RFMU and CMS/FS programs and, in order to provide a consistent approach, four standard exposure scenarios were developed for exposure assessments to be used in human health risk assessments. The standard exposure scenarios are divided into two temporal categories: (a) Current Land Use in the BRA, and (b) Future Land Use in the RERA. The Current Land Use scenarios consist of the evaluation of human health risk for Industrial Exposure (of a worker not involved in waste unit characterization or remediation), a Trespasser, a hypothetical current On-site Resident, and an Off-site Resident. The Future Land Use scenario considers exposure to an On-site Resident following termination of institutional control in the absence of any remedial action (No Action Alternative), as well as evaluating potential remedial alternatives against the four scenarios from the BRA. A critical facet in the development of a BRA or RERA is the scoping of exposure scenarios that reflect actual conditions at a waste unit, rather than using factors such as EPA Standard Default Exposure Scenarios (OSWER Directive 9285.6-03) that are based on upper-bound exposures that tend to reflect worst case conditions. The use of site-specific information for developing risk assessment exposure scenarios will result in a more realistic estimate of Reasonable Maximum Exposure for SRS waste units

  2. Development of exposure scenarios for CERCLA risk assessments at the Savannah River Site

    Energy Technology Data Exchange (ETDEWEB)

    Nix, D.W.; Immel, J.W. [Westinghouse Savannah River Co., Aiken, SC (United States); Phifer, M.A. [Tennessee Univ., Knoxville, TN (United States). Dept. of Civil Engineering

    1992-12-31

    A CERCLA Baseline Risk Assessment (BRA) is performed to determine if there are any potential risks to human health and the environment from waste unit at SRS. The SRS has numerous waste units to evaluate in the RFMU and CMS/FS programs and, in order to provide a consistent approach, four standard exposure scenarios were developed for exposure assessments to be used in human health risk assessments. The standard exposure scenarios are divided into two temporal categories: (a) Current Land Use in the BRA, and (b) Future Land Use in the RERA. The Current Land Use scenarios consist of the evaluation of human health risk for Industrial Exposure (of a worker not involved in waste unit characterization or remediation), a Trespasser, a hypothetical current On-site Resident, and an Off-site Resident. The Future Land Use scenario considers exposure to an On-site Resident following termination of institutional control in the absence of any remedial action (No Action Alternative), as well as evaluating potential remedial alternatives against the four scenarios from the BRA. A critical facet in the development of a BRA or RERA is the scoping of exposure scenarios that reflect actual conditions at a waste unit, rather than using factors such as EPA Standard Default Exposure Scenarios (OSWER Directive 9285.6-03) that are based on upper-bound exposures that tend to reflect worst case conditions. The use of site-specific information for developing risk assessment exposure scenarios will result in a more realistic estimate of Reasonable Maximum Exposure for SRS waste units.

  3. Feasibility study for remedial action for the groundwater operable units at the chemical plant area and the ordnance works area, Weldon Spring, Missouri

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-07-15

    The U.S. Department of Energy (DOE) and the U.S. Department of Army (DA) are conducting an evaluation to identify the appropriate response action to address groundwater contamination at the Weldon Spring Chemical Plant (WSCP) and the Weldon Spring Ordnance Works (WSOW), respectively. The two areas are located in St. Charles County, about 48 km (30 rni) west of St. Louis. The groundwater operable unit (GWOU) at the WSCP is one of four operable units being evaluated by DOE as part of the Weldon Spring Site Remedial Action Project (WSSRAP). The groundwater operable unit at the WSOW is being evaluated by the DA as Operable Unit 2 (OU2); soil and pipeline contamination are being managed under Operable Unit 1 (OU1). Remedial activities at the WSCP and the WSOW are being conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Consistent with DOE policy, National Environmental Policy Act (NEPA) values have been incorporated into the CERCLA process. A remedial investigation/feasibility study (RI/FS) work plan summarizing initial site conditions and providing site hydrogeological and exposure models was published in August of 1995 (DOE 1995). The remedial investigation (RI) and baseline risk assessment (BRA) have also recently been completed. The RI (DOE and DA 1998b) discusses in detail the nature, extent, fate, and transport of groundwater and spring water contamination. The BRA (DOE and DA 1998a) is a combined baseline assessment of potential human health and ecological impacts and provides the estimated potential health risks and ecological impacts associated with groundwater and springwater contamination if no remedial action were taken. This feasibility study (FS) has been prepared to evaluate potential options for addressing groundwater contamination at the WSCP and the WSOW. A brief description of the history and environmental setting of the sites is presented in Section 1.1, key information relative to the

  4. Phase 2 sampling and analysis plan, Quality Assurance Project Plan, and environmental health and safety plan for the Clinch River Remedial Investigation: An addendum to the Clinch River RCRA Facility Investigation plan

    International Nuclear Information System (INIS)

    Cook, R.B.; Adams, S.M.; Beauchamp, J.J.; Bevelhimer, M.S.; Blaylock, B.G.; Brandt, C.C.; Etnier, E.L.; Ford, C.J.; Frank, M.L.; Gentry, M.J.; Greeley, M.S.; Halbrook, R.S.; Harris, R.A.; Holladay, S.K.; Hook, L.A.; Howell, P.L.; Kszos, L.A.; Levine, D.A.; Skiles, J.L.; Suter, G.W.

    1992-12-01

    This document contains a three-part addendum to the Clinch River Resource Conservation and Recovery Act (RCRA) Facility Investigation Plan. The Clinch River RCRA Facility Investigation began in 1989, as part of the comprehensive remediation of facilities on the US Department of Energy Oak Ridge Reservation (ORR). The ORR was added to the National Priorities List in December 1989. The regulatory agencies have encouraged the adoption of Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) terminology; therefore, the Clinch River activity is now referred to as the Clinch River Remedial Investigation (CRRI), not the Clinch River RCRA Facility Investigation. Part 1 of this document is the plan for sampling and analysis (S ampersand A) during Phase 2 of the CRRI. Part 2 is a revision of the Quality Assurance Project Plan for the CRRI, and Part 3 is a revision of the Environmental Health and Safety Plan for the CRRI. The Clinch River RI (CRRI) is designed to address the transport, fate, and distribution of waterborne contaminants (radionuclides, metals, and organic compounds) released from the DOE Oak Ridge Reservation (ORR) and to assess potential risks to human health and the environment associated with these contaminants. Primary areas of investigation are Melton Hill Reservoir, the Clinch River from Melton Hill Dam to its confluence with the Tennessee River, Poplar Creek, and Watts Bar Reservoir. The contaminants identified in the Clinch River/Watts Bar Reservoir (CR/WBR) downstream of the ORR are those associated with the water, suspended particles, deposited sediments, aquatic organisms, and wildlife feeding on aquatic organisms. The purpose of the Phase 2 S ampersand A Plan is to describe the proposed tasks and subtasks developed to meet the primary objectives of the CRRI

  5. Phase 2 sampling and analysis plan, Quality Assurance Project Plan, and environmental health and safety plan for the Clinch River Remedial Investigation: An addendum to the Clinch River RCRA Facility Investigation plan

    Energy Technology Data Exchange (ETDEWEB)

    Cook, R.B.; Adams, S.M.; Beauchamp, J.J.; Bevelhimer, M.S.; Blaylock, B.G.; Brandt, C.C.; Etnier, E.L.; Ford, C.J.; Frank, M.L.; Gentry, M.J.; Greeley, M.S.; Halbrook, R.S.; Harris, R.A.; Holladay, S.K.; Hook, L.A.; Howell, P.L.; Kszos, L.A.; Levine, D.A.; Skiles, J.L.; Suter, G.W.

    1992-12-01

    This document contains a three-part addendum to the Clinch River Resource Conservation and Recovery Act (RCRA) Facility Investigation Plan. The Clinch River RCRA Facility Investigation began in 1989, as part of the comprehensive remediation of facilities on the US Department of Energy Oak Ridge Reservation (ORR). The ORR was added to the National Priorities List in December 1989. The regulatory agencies have encouraged the adoption of Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) terminology; therefore, the Clinch River activity is now referred to as the Clinch River Remedial Investigation (CRRI), not the Clinch River RCRA Facility Investigation. Part 1 of this document is the plan for sampling and analysis (S A) during Phase 2 of the CRRI. Part 2 is a revision of the Quality Assurance Project Plan for the CRRI, and Part 3 is a revision of the Environmental Health and Safety Plan for the CRRI. The Clinch River RI (CRRI) is designed to address the transport, fate, and distribution of waterborne contaminants (radionuclides, metals, and organic compounds) released from the DOE Oak Ridge Reservation (ORR) and to assess potential risks to human health and the environment associated with these contaminants. Primary areas of investigation are Melton Hill Reservoir, the Clinch River from Melton Hill Dam to its confluence with the Tennessee River, Poplar Creek, and Watts Bar Reservoir. The contaminants identified in the Clinch River/Watts Bar Reservoir (CR/WBR) downstream of the ORR are those associated with the water, suspended particles, deposited sediments, aquatic organisms, and wildlife feeding on aquatic organisms. The purpose of the Phase 2 S A Plan is to describe the proposed tasks and subtasks developed to meet the primary objectives of the CRRI.

  6. Remedial investigation work plan for Chestnut Ridge Operable Unit 4 (Rogers Quarry/Lower McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1993-09-01

    The Oak Ridge Y-12 Plant includes - 800 acres near the northeast comer of the reservation and adjacent to the city of Oak Ridge (Fig. 1-1). The plant is a manufacturing and developmental engineering facility that produced components for various nuclear weapons systems and provides engineering support to other Energy Systems facilities. More than 200 contaminated sites have been identified at the Y-12 Plant that resulted from past waste management practices. Many of the sites have operable units (OUs) based on priority and on investigative and remediation requirements. This Remedial Investigation RI work plan specifically addresses Chestnut Ridge OU 4. Chestnut Ridge OU 4 consists of Rogers Quarry and Lower McCoy Branch (MCB). Rogers Quarry, which is also known as Old Rogers Quarry or Bethel Valley Quarry was used for quarrying from the late 1940s or early 1950s until about 1960. Since that time, the quarry has been used for disposal of coal ash and materials from Y-12 production operations, including classified materials. Disposal of coal ash ended in July 1993. An RI is being conducted at this site in response to CERCLA regulations. The overall objectives of the RI are to collect data necessary to evaluate the nature and extent of contaminants of concern, support an Ecological Risk Assessment and a Human Health Risk Assessment, support the evaluation of remedial alternatives, and ultimately develop a Record of Decision for the site. The purpose of this work plan is to outline RI activities necessary to define the nature and extent of suspected contaminants at Chestnut Ridge OU 4. Potential migration pathways also will be investigated. Data collected during the RI will be used to evaluate the risk posed to human health and the environment by OU 4.

  7. Catalog of CERCLA applicable or relevant and appropriate requirements (ARARs) - fact sheets

    Energy Technology Data Exchange (ETDEWEB)

    1990-07-01

    Section 121(d) of the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA), requires attainment of federal and state applicable or relevant and appropriate requirements (ARARs). Subpart E, Section 300.400(g) {open_quotes}Identification of applicable or relevant and appropriate requirements{close_quotes} of the National Oil and Hazardous Substances Pollution Contingency Plan (NCP)(55 FR 8666, March 8, 1990) describes the process for attaining ARARs. The purpose of this catalog is to provide DOE Program Offices and Field Organizations with all of the {open_quotes}Quick Reference Fact Sheets{close_quotes} on attaining ARARS. These fact sheets provide overviews of ARARs for CERCLA cleanup actions pertinent to DOE environmental restoration activities. All of the fact sheets in this catalog were prepared by the Environmental Protection Agency`s Office of Solid Waste and Emergency Response. Fact sheets 1-7 discuss land disposal restrictions (LDRs) and their applicability. LDRs may pertain to a number of CERCLA response actions at DOE facilities. Fact Sheets 8-13 are based on the CERCLA Compliance with Other Laws Manual: Parts I and II and provide an overview of many other CERCLA ARARs. Overview of ARARs-Focus on ARAR Waivers (fact sheet 11), provides a good introduction to ARARS. The last two fact sheets, 14 and 15, are periodic reports that describe additional fact sheets and clarify issues.

  8. Environmental compliance plan for the Lower East Fork Poplar Creek Remedial Action Project at Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-07-01

    Remedial action for Lower East Fork Poplar Creek, as defined by the Record of Decision, requires that soil contaminated with >400 ppM mercury be excavated and disposed. Based on the remediation goal, soil will be excavated from areas located at the NOAA site and the Bruner site and disposed at the Industrial Landfill V at the Y-12 Plant. Objective is to minimize the risk to human health and the environment from contaminated soil in the lower EFPC floodplain pursuant to CERCLA and the Federal Facility Agreement (DOE 1992)

  9. Responses to comments on the remedial investigation/feasibility study-environmental impact statement for remedial action at the Chemical Plant area of the Weldon Spring site (November 1992)

    International Nuclear Information System (INIS)

    1993-06-01

    The US Department of Energy (DOE) is responsible for cleanup activities at the Weldon Spring site in St. Charles County, Missouri. The site consists of a chemical plant area and a noncontiguous limestone quarry; both areas are radioactively and chemically contaminated as a result of past processing and disposal activities. Explosives were produced by the US Army at the chemical plant in the 1940s, and uranium and thorium materials were processed by DOE's predecessor agency in the 1950s and 1960s. During that time, various wastes were disposed of at both areas of the site. The DOE is conducting cleanup activities at the site under its Environmental Restoration and Waste Management Program. The integrated remedial investigation/feasibility study-environmental impact statement (RI/FS-EIS) documents for the chemical plant area were issued to the public in November 1992 as the draft RI/FS-EIS. (The CERCLA RI/FS is considered final when issued to the public, whereas per the NEPA process, an EIS is initially issued as a draft and is finalized after substantive public comments have been addressed.) Four documents made up the draft RI/FS-EIS, which is hereafter referred to as the RI/FS-EIS: (1) the RI (DOE 1992d), which presents general information on the site environment and the nature and extent of contamination; (2) the baseline assessment (BA) (DOE 1992a), which evaluates human health and environmental effects that might occur if no cleanup actions were taken; (3) the FS (DOE 1992b), which develops and evaluates alternatives for site cleanup; and (4) the proposed plan (PP) (DOE 1992c), which summarizes key information from the RI, BA, and FS reports and identifies DOE's preferred alternative for remedial action. This comment response document combined with those four documents constitutes the final RI/FS-EIS for the chemical plant area

  10. Responses to comments on the remedial investigation/feasibility study-environmental impact statement for remedial action at the Chemical Plant area of the Weldon Spring site (November 1992)

    Energy Technology Data Exchange (ETDEWEB)

    1993-06-01

    The US Department of Energy (DOE) is responsible for cleanup activities at the Weldon Spring site in St. Charles County, Missouri. The site consists of a chemical plant area and a noncontiguous limestone quarry; both areas are radioactively and chemically contaminated as a result of past processing and disposal activities. Explosives were produced by the US Army at the chemical plant in the 1940s, and uranium and thorium materials were processed by DOE`s predecessor agency in the 1950s and 1960s. During that time, various wastes were disposed of at both areas of the site. The DOE is conducting cleanup activities at the site under its Environmental Restoration and Waste Management Program. The integrated remedial investigation/feasibility study-environmental impact statement (RI/FS-EIS) documents for the chemical plant area were issued to the public in November 1992 as the draft RI/FS-EIS. (The CERCLA RI/FS is considered final when issued to the public, whereas per the NEPA process, an EIS is initially issued as a draft and is finalized after substantive public comments have been addressed.) Four documents made up the draft RI/FS-EIS, which is hereafter referred to as the RI/FS-EIS: (1) the RI (DOE 1992d), which presents general information on the site environment and the nature and extent of contamination; (2) the baseline assessment (BA) (DOE 1992a), which evaluates human health and environmental effects that might occur if no cleanup actions were taken; (3) the FS (DOE 1992b), which develops and evaluates alternatives for site cleanup; and (4) the proposed plan (PP) (DOE 1992c), which summarizes key information from the RI, BA, and FS reports and identifies DOE`s preferred alternative for remedial action. This comment response document combined with those four documents constitutes the final RI/FS-EIS for the chemical plant area.

  11. Work Plan for the Feasibility Study for Remedial Action at J-Field, Aberdeen Proving Ground, Maryland

    Energy Technology Data Exchange (ETDEWEB)

    Benioff, P.; Biang, C.; Haffenden, R.; Goyette, M.; Martino, L.; Patton, T.; Yuen, C.

    1995-05-01

    The purpose of the feasibility study is to gather sufficient information to develop and evaluate alternative remedial actions to address contamination at J-Field in compliance with the NCP, CERCLA, and SARA. This FS Work Plan summarizes existing environmental data for each AOC and outlines the tasks to be performed to evaluate and select remedial technologies. The tasks to be performed will include (1) developing remedial action objectives and identifying response actions to meet these objectives; (2) identifying and screening remedial action technologies on the basis of effectiveness, implementability, and cost; (3) assembling technologies into comprehensive alternatives for J-Field; (4) evaluating, in detail, each alternative against the nine EPA evaluation criteria and comparing the alternatives to identify their respective strengths and weaknesses; and (5) selecting the preferred alternative for each operable unit.

  12. Applicable or Relevant and Appropriate Requirements (ARARs) for Remedial Action at the Oak Ridge Reservation: A compendium of major environmental laws. Environmental Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    Etnier, E.L.; McDonald, E.P.; Houlberg, L.M.

    1993-07-01

    Section 121 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980 specifies that remedial actions for cleanup of hazardous substances must comply with applicable or relevant and appropriate requirements (ARARS) or standards under federal and state environmental laws. The US Department of Energy (DOE) Oak Ridge Reservation (ORR) was placed on the National Priorities List by the US Environmental Protection Agency (EPA) on November 21, 1989, effective December 21, 1989. As a result of this listing, DOE, EPA, and the Tennessee Department of Environment and Conservation have signed a Federal Facility Agreement (FFA) for the environmental restoration of the ORR. Section XXI(F) of the FFA calls for the preparation of a draft listing of all ARARs as mandated by CERCLA {section}121. This report supplies a preliminary list of available federal and state ARARs that might be considered for remedial response at the ORR. A description of the terms ``applicable`` and ``relevant and appropriate`` is provided, as well as definitions of chemical-, location-, and action-specific ARARS. ARARs promulgated by the federal government and by the state of Tennessee are listed in tables. In addition, the major provisions of the Resource Conservation and Recovery Act, the Safe Drinking Water Act, the Clean Water Act, the Clean Air and other acts, as they apply to hazardous waste cleanup, are discussed. In the absence of ARARS, CERCLA {section}121 provides for the use of nonpromulgated federal criteria, guidelines, and advisories in evaluating the human risk associated with remedial action alternatives. Such nonpromulgated standards are classified as ``to-be-considered`` (TBC) guidance. A ion of available guidance is given; summary tables fist the available federal standards and guidance information. In addition, the substantive contents of the DOE orders as they apply to remediation of radioactively contaminated sites are discussed as TBC guidance.

  13. Environmental assessment for 881 Hillside (High Priority Sites) interim remedial action

    International Nuclear Information System (INIS)

    1990-01-01

    This Environmental Assessment evaluates the impact of an interim remedial action proposed for the High Priority Sites (881 Hillside Area) at the Rocky Flats Plant (RFP). This interim action is to be conducted to minimize the release of hazardous substances from the 881 Hillside Area that pose a potential long-term threat to public health and the environment. This document integrates current site characterization data and environmental analyses required by the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or ''Superfund'' process, into an environmental assessment pursuant to the National Environmental Policy Act (NEPA). Characterization of the 881 Hillside Area is continuing. Consequently, a final remedial action has not yet been proposed. Environmental impacts associated with the proposed interim remedial action and reasonable alternatives designed to remove organic and inorganic contaminants, including radionuclides, from alluvial groundwater in the 881 Hillside Area are addressed. 24 refs., 5 figs., 23 tabs

  14. Program management strategies for following EPA guidance for remedial design/remedial action at DOE sites

    International Nuclear Information System (INIS)

    Hopper, J.P.; Chew, J.R.; Kowalski, T.E.

    1991-01-01

    At the US Department of Energy (DOE) facilities, environmental restoration is being conducted in accordance with Federal Facilities Compliance Agreements (or Interagency Agreements). These agreements establish a cooperative working relationship and often define roles, responsibilities and authorities for conduct and oversight of the Remedial Action Programs. The US Environmental Protection Agency (EPA) has guidelines on how to initiate and perform remedial actions for sites they are remediating under the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) as amended by the Superfund Amendments and Re-Authorization Act (SARA). This paper addresses some of the difference and commonalities between the DOE project management procedures and EPA guidance documents. This report covers only the RD/RA phase of environmental restoration. On the surface, there are many apparent differences between the DOE and EPA project management processes. Upon closer review, however, many of the differences are the result of applying different terminology to the same phase of a project. By looking for the similarities in the two processes rather than hunting for differences, many communication problems are avoided. Understanding both processes also aids in figuring out when, how and to what extent EPA should participate in the RD/RA phase for DOE lead cleanup activities. The DOE Remedial Design and Remedial Action process is discussed in a stepwise manner and compared to the EPA process. Each element of the process is defined. Activities common to both the EPA and DOE are correlated. The annual DOE budget cycle for remediation projects and the four-year cycle for appropriation of remediation funds are discussed, and the constraints of this process examined. DOE orders as well as other requirements for RD/RA activities are summarized and correlated to EPA regulations where this is possible

  15. Remediation activities at the Fernald Environmental Management Project (FEMP)

    International Nuclear Information System (INIS)

    Walsh, T.J.; Danner, R.

    1996-01-01

    The Fernald Environmental Management Project (FEMP) is a United States Department of Energy (DOE) facility located in southwestern Ohio. The facility began manufacturing uranium products in the early 1950's and continued processing uranium ore concentrates until 1989. The facility used a variety of chemical and metallurgical processes to produce uranium metals for use at other DOE sites across the country. Since the facility manufactured uranium metals for over thirty years, various amounts of radiological contamination exists at the site. Because of the chemical and metallurgical processes employed at the site, some hazardous wastes as defined by the Resource Conservation and Recovery Act (RCRA) were also generated at the site. In 1989. the FEMP was placed on the National Priorities List (NPL) requiring cleanup of the facility's radioactive and chemical contamination under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). This paper discusses the proposed remediation activities at the five Operable Units (OUs) designated at the FEMP. In addition, the paper also examines the ongoing CERCLA response actions and RCRA closure activities at the facility

  16. Glossary of CERCLA, RCRA and TSCA related terms and acronyms

    International Nuclear Information System (INIS)

    1993-10-01

    This glossary contains CERCLA, RCRA and TSCA related terms that are most often encountered in the US Department of Energy (DOE) Environmental Restoration and Emergency Preparedness activities. Detailed definitions are included for key terms. The CERCLA definitions included in this glossary are taken from the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as amended and related federal rulemakings. The RCRA definitions included in this glossary are taken from the Resource Conservation and Recovery Act (RCRA) and related federal rulemakings. The TSCA definitions included in this glossary are taken from the Toxic Substances and Control Act (TSCA) and related federal rulemakings. Definitions related to TSCA are limited to those sections in the statute and regulations concerning PCBs and asbestos.Other sources for definitions include additional federal rulemakings, assorted guidance documents prepared by the US Environmental Protection Agency (EPA), guidance and informational documents prepared by the US Department of Energy (DOE), and DOE Orders. The source of each term is noted beside the term. Terms presented in this document reflect revised and new definitions published before July 1, 1993

  17. Remedial Investigation of Hanford Site Releases to the Columbia River

    International Nuclear Information System (INIS)

    Lerch, J.A.

    2009-01-01

    In south-central Washington State, the Columbia River flows through the U.S. Department of Energy Hanford Site. A primary objective of the Hanford Site cleanup mission is protection of the Columbia River, through remediation of contaminated soil and groundwater that resulted from its weapons production mission. Within the Columbia River system, surface water, sediment, and biota samples related to potential Hanford Site hazardous substance releases have been collected since the start of Hanford operations. The impacts of Hanford Site hazardous substance releases to the Columbia River in areas upstream, within, and downstream of the Hanford Site boundary have been previously investigated as mandated by the U.S. Department of Energy requirements under the Atomic Energy Act. The impacts are now being assessed under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 via a remedial investigation. The Remedial Investigation Work Plan for Hanford Site Releases to the Columbia River has been developed and issued to initiate the remedial investigation. The work plan establishes a phased approach to characterize contaminants, assess current risks, and determine whether or not there is a need for any cleanup actions. Field investigation activities began in October 2008 and are anticipated to continue into Fall 2009 over a 120 mile stretch of the Columbia River. Information gained from performing this remedial investigation will ultimately be used to help make final regulatory decisions for cleaning up Hanford Site contamination that exists in and along the Columbia River. (authors)

  18. Remedial investigation work plan for Bear Creek (Y02-S600) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Turner, R.R.; Bogle, M.A.; Clapp, R.B.; Dearstone, K.; Dreier, R.B.; Early, T.O.; Herbes, S.E.; Loar, J.M.; Parr, P.D.; Southworth, G.R.

    1991-07-01

    As part of its response to Resource Conservation and Recovery Act (RCRA), the US Department of Energy had agreed to further investigate contamination of Bear Creek and its floodplain resulting from releases of hazardous waste or hazardous constituents from the Y-12 Plant solid waste management units (SWMU) located in the Bear Creek watershed. That proposed RCRA Facility Investigation has been modified to incorporate the requirements of Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) into a Remedial Investigation (RI) Plan for Bear Creek. This document is the RI Plan for Bear Creek and its flood-of-record floodplain. The following assumptions were made in the preparation of this RI Plan: (1) That source-area groundwater monitoring will be conducted as a part of the comprehensive groundwater monitoring plan for the Bear Creek Hydrogeologic Regime; and (2) that postclosure activities associated with each SWMU do not explicitly include a comprehensive assessment of surface water, sediment, and floodplain soil contamination in Bear Creek and its tributaries. The RI Plan is thus intended to provide a more comprehensive evaluation of Bear Creek and its floodplain than that provided by the investigative monitoring and risk assessment activities associated with the ten individual SWMUs. RI activities will be carefully coordinated with other monitoring and assessment activities to avoid redundancy and to maximize the utility of data gathered during the investigation. 121 refs., 61 figs., 46 tabs

  19. Chaos and remedial investigations

    International Nuclear Information System (INIS)

    Galbraith, R.M.

    1991-01-01

    Current research into the nature of chaos indicates that even for systems that are well known and easily modeled, slight changes in the scale used to measure the input have unpredictable results in the model output. The conduct of a remedial investigation (RI) is dictated by well-established rules of investigation and management, yet small changes in project orientation, regulatory environment, or site conditions have unpredictable consequences to the project. The consequences can lead to either brilliant success or utter failure. The chaotic effect of a change in scale is most often illustrated by an exercise in measuring the length of the coast of Great Britain. If a straight ruler 10-kilometers long is used, the sum of the 10-kilometer increments gives the length of the coast. If the ruler is changed to five kilometers long and the exercise is repeated, the sum of the five-kilometer increments will not be the same as the sum of the 10-kilometer increments. Nor is there a way to predict what the length of the coast will be using any other scale. Several examples from the Fernald Project RI are used to illustrate open-quotes changes in scaleclose quotes in both technical and management situations. Given that there is no way to predict the outcome of scale changes in a RI, technical and project management must be alert to the fact that a scale has changed and the investigation is no longer on the path it was thought to be on. The key to success, therefore, is to develop specific units of measure for a number of activities, in addition to cost and schedule, and track them regularly. An example for tracking a portion of the field investigation is presented. The determination of effective units of measure is perhaps the most difficult aspect of any project. Changes in scale sometimes go unnoticed until suddenly the budget is expended and only a portion of the work is completed. Remedial investigations on large facilities provide new and complex challenges

  20. CERCLA site assessment workbook

    International Nuclear Information System (INIS)

    1994-08-01

    This contains comments for each chapter of exercises (in Vol. 1) which illustrate how to conduct site assessments for CERCLA regulation. A through analysis of the exercises is provided so that work and solutions from Vol 1 can be critiqued and comments are also included on the strategy of site assessment whereas the exercises illustrate the principles involved. Covered exercises include the following: A preliminary assessment of a ground water site; waste characteristics and characterization of sources; documentation of observed releases and actual contamination of targets; the strategy of an SI at a surface water site; the soil exposure pathway; the air pathway

  1. RCRA and CERCLA requirements affecting cleanup activities at a federal facility superfund site

    International Nuclear Information System (INIS)

    Walsh, T.J.

    1994-01-01

    The Fernald Environmental Management Project (FEMP) achieved success on an integrated groundwater monitoring program which addressed both RCRA and CERCLA requirements. The integrated plan resulted in a cost savings of approximately $2.6 million. At present, the FEMP is also working on an integrated closure process to address Hazardous Waste Management Units (HWMUs) at the site. To date, Ohio EPA seems willing to discuss an integrated program with some stipulations. If an integrated program is implemented, a cost savings of several million dollars will be realized since the CERCLA documents can be used in place of a RCRA closure plan. The success of an integrated program at the FEMP is impossible without the support of DOE and the regulators. Since DOE is an owner/operator of the facility and Ohio EPA regulates hazardous waste management activities at the FEMP, both parties must be satisfied with the proposed integration activities. Similarly, US EPA retains CERCLA authority over the site along with a signed consent agreement with DOE, which dictates the schedule of the CERCLA activities. Another federal facility used RCRA closure plans to satisfy CERCLA activities. This federal facility was in a different US EPA Region than the FEMP. While this approach was successful for this site, an integrated approach was required at the FEMP because of the signed Consent Agreement and Consent Decree. For federal facilities which have a large number of HWMUs along with OUs, an integrated approach may result in a timely and cost-effective cleanup

  2. Feasibility study for remedial action for the groundwater operable units at the chemical plant area and the ordnance works area at the Weldon Spring Site, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1999-01-01

    The U.S. Department of Energy (DOE) and the U.S. Department of Army (DA) are conducting an evaluation to identify the appropriate response action to address groundwater contamination at the Weldon Spring Chemical Plant (WSCP) and the Weldon Spring Ordnance Works (WSOW), respectively. The two areas are located in St. Charles County, about 48 km (30 rni) west of St. Louis. The groundwater operable unit (GWOU) at the WSCP is one of four operable units being evaluated by DOE as part of the Weldon Spring Site Remedial Action Project (WSSRAP). The groundwater operable unit at the WSOW is being evaluated by the DA as Operable Unit 2 (OU2); soil and pipeline contamination are being managed under Operable Unit 1 (OU1). Remedial activities at the WSCP and the WSOW are being conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Consistent with DOE policy, National Environmental Policy Act (NEPA) values have been incorporated into the CERCLA process. A remedial investigation/feasibility study (RI/FS) work plan summarizing initial site conditions and providing site hydrogeological and exposure models was published in August of 1995 (DOE 1995). The remedial investigation (RI) and baseline risk assessment (BRA) have also recently been completed. The RI (DOE and DA 1998b) discusses in detail the nature, extent, fate, and transport of groundwater and spring water contamination. The BRA (DOE and DA 1998a) is a combined baseline assessment of potential human health and ecological impacts and provides the estimated potential health risks and ecological impacts associated with groundwater and springwater contamination if no remedial action were taken. This feasibility study (FS) has been prepared to evaluate potential options for addressing groundwater contamination at the WSCP and the WSOW. A brief description of the history and environmental setting of the sites is presented in Section 1.1, key information relative to the

  3. Fiscal year 1995 progress in implementing Section 120 of the Comprehensive Environmental Response, Compensation, and Liability Act. Ninth annual report to Congress

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-09-01

    Congress passed the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (Public Law 96-510), commonly known as Superfund, in 1980. The Superfund Amendments and Reauthorization Act (SARA) which amended CERCLA in 1986, added Section 120 regarding the cleanup of contaminated sites at Federal facilities. Under Section 120(e)(5) of CERCLA, each department, agency, or instrumentality of the Federal government responsible for compliance with Section 120 must submit an annual report to Congress concerning its progress in implementing the requirements of Section 120. The report must include information on the progress in reaching Interagency Agreements (IAGs), conducting Remedial Investigation and Feasibility Studies (RI/FSs), and performing remedial action. Federal agencies that own or operate facilities on the National priorities List (NPL) are required to begin an RI/FS for these facilities within 6 months after being placed on the NPL. Remediation of these facilities is addressed in an IAG between the Federal agency, the US Environmental Protection Agency (EPA), and in some instances the state within which the facility is located. This report provides the status of ongoing activities being performed in support of CERCLA Section 120 at DOE facilities. This includes activities conducted to reach IAGs and progress in conducting remedial actions.

  4. Fiscal year 1995 progress in implementing Section 120 of the Comprehensive Environmental Response, Compensation, and Liability Act. Ninth annual report to Congress

    International Nuclear Information System (INIS)

    1996-09-01

    Congress passed the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (Public Law 96-510), commonly known as Superfund, in 1980. The Superfund Amendments and Reauthorization Act (SARA) which amended CERCLA in 1986, added Section 120 regarding the cleanup of contaminated sites at Federal facilities. Under Section 120(e)(5) of CERCLA, each department, agency, or instrumentality of the Federal government responsible for compliance with Section 120 must submit an annual report to Congress concerning its progress in implementing the requirements of Section 120. The report must include information on the progress in reaching Interagency Agreements (IAGs), conducting Remedial Investigation and Feasibility Studies (RI/FSs), and performing remedial action. Federal agencies that own or operate facilities on the National priorities List (NPL) are required to begin an RI/FS for these facilities within 6 months after being placed on the NPL. Remediation of these facilities is addressed in an IAG between the Federal agency, the US Environmental Protection Agency (EPA), and in some instances the state within which the facility is located. This report provides the status of ongoing activities being performed in support of CERCLA Section 120 at DOE facilities. This includes activities conducted to reach IAGs and progress in conducting remedial actions

  5. Remedial action assessment system (RAAS) - A computer-based methodology for conducting feasibility studies

    International Nuclear Information System (INIS)

    Buelt, J.L.; Stottlemyre, J.A.; White, M.K.

    1991-01-01

    Because of the great complexity and number of potential waste sites facing the US Department of Energy (DOE) for potential cleanup, the DOE is supporting the development of a computer-based methodology to streamline the remedial investigation/feasibility study process required for DOE operable units. DOE operable units are generally more complex in nature because of the existence of multiple waste sites within many of the operable units and the presence of mixed radioactive and hazardous chemical wastes. Consequently, Pacific Northwest Laboratory (PNL) is developing the Remedial Action Assessment System (RAAS), which is aimed at screening, linking, and evaluating established technology process options in support of conducting feasibility studies under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). It is also intended to do the same in support of corrective measures studies required by the Resource Conservation and Recovery Act (RCRA). One of the greatest attributes of the RAAS project is that the computer interface with the user is being designed to be friendly, intuitive, and interactive. Consequently, the user interface employs menus, windows, help features, and graphical information while RAAS is in operation. During operation, each technology process option is represented by an open-quotes objectclose quotes module. Object-oriented programming is then used to link these unit processes into remedial alternatives. In this way, various object modules representing technology process options can communicate so that a linked set of compatible processes form an appropriate remedial alternative. Once the remedial alternatives are formed, they can be evaluated in terms of effectiveness, implementability, and cost

  6. Z Plant source aggregate area management study report

    International Nuclear Information System (INIS)

    1992-10-01

    The US Department of Energy (DOE) Hanford Site in Washington State is or into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989, included the 200 Areas of the Hanford Site on the National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) of 1980. Inclusion on the NPL initiates the Remedial Investigation (RI) and Feasibility Study (FS) process for characterizing the nature and extent of contamination, assessing risks to human health and the environment, and selection of remedial actions. This report presents the insults of an aggregate area management study (AAMS) for the Z Plant Aggregate Area located m the 200 Areas. The study provides the basis for initiating RIIFS under CERCLA or under the Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS). This report also integrates RCRA treatment, storage, or disposed (TSD) closure activities with CERCLA and RCRA past-practice investigations

  7. Salmon Site Remedial Investigation Report, Appendix C

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  8. Salmon Site Remedial Investigation Report, Exhibit 2

    Energy Technology Data Exchange (ETDEWEB)

    USDOE NV

    1999-09-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  9. Salmon Site Remedial Investigation Report, Appendix D

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  10. Salmon Site Remediation Investigation Report, Appendix A

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  11. Salmon Site Remedial Investigation Report, Main Body

    Energy Technology Data Exchange (ETDEWEB)

    US DOE/NV

    1999-09-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  12. Salmon Site Remedial Investigation Report, Exhibit 2

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  13. Salmon Site Remedial Investigation Report, Appendix C

    Energy Technology Data Exchange (ETDEWEB)

    US DOE/NV

    1999-09-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  14. Salmon Site Remedial Investigation Report, Exhibit 5

    Energy Technology Data Exchange (ETDEWEB)

    USDOE/NV

    1999-09-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  15. Salmon Site Remedial Investigation Report, Exhibit 5

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  16. Simulant composition for the Mixed Waste Management Facility (MWMF) groundwater remediation project

    International Nuclear Information System (INIS)

    Siler, J.L.

    1992-01-01

    A project has been initiated at the request of ER to study and remediate the groundwater contamination at the Mixed Waste Management Facility (MWMF). This water contains a wide variety of both inorganics (e.g., sodium) and organics (e.g., benzene, trichloroethylene). Most compounds are present in the ppB range, and certain components (e.g., trichloroethylene, silver) are present at concentrations that exceed the primary drinking water standards (PDWS). These compounds must be reduced to acceptable levels as per RCRA and CERCLA orders. This report gives a listing of the important constituents which are to be included in a simulant to model the MWMF aquifer. This simulant will be used to evaluate the feasibility of various state of the art separation/destruction processes for remediating the aquifer

  17. Applicable or relevant and appropriate requirements (ARARs) for remedial actions at the Portsmouth Gaseous Diffusion Plant: A compendium of environmental laws and guidance

    International Nuclear Information System (INIS)

    Houlberg, L.M.; Eaton, L.A.; Martin, J.A.; McDonald, E.P.; Etnier, E.L.

    1992-02-01

    Section 121 of the Comprehensive Environmental Response, Compensation, and Liability Act of 1990 (CERCLA) specifies that remedial actions for cleanup of hazardous substances must comply with applicable or relevant and appropriate requirements (ARARs) or standards under federal and state environmental laws. Although the US Department of Energy (DOE) Portsmouth Gaseous Diffusion Plant (PORTS) has not at this time been proposed for inclusion on the US Environmental Protection Agency National Priorities List, under Sect. I of an administrative consent order signed by DOE and the US Environmental Protection Agency on September 29, 1989, effective October 4, 1989, any necessary response actions at PORTS stipulated in the administrative consent order must be performed in a manner consistent with the Resource Conservation and Recovery Act of 1976 and CERCLA. Section 121 of CERCLA calls for the preparation of a draft listing of all ARARs. This report supplies a preliminary list of available federal and state ARARs that might be considered for remedial response at PORTS. A description of the terms ''applicable'' and ''relevant and appropriate'' is provided, as well as definitions of chemical-, location-, and action-specific ARARs. ARARs promulgated by the federal government and by the state of Ohio are listed in tables. In addition, the major provisions of the Resource Conservation and Recovery Act, Safe Drinking Water Act, Clean Water Act, and other acts, as they apply to hazardous waste cleanup, are discussed

  18. The CAMU Rule: A tool for implementing a protective, cost-effective remedy at the Fernald Environmental Management Project

    International Nuclear Information System (INIS)

    Dupuis-Nouille, E.M.; Goidell, L.C.; Strimbu, M.J.

    1995-01-01

    The Fernald Environmental Management Project (FEMP) is a former uranium processing facility currently under remediation pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act as amended (CERCLA). Contamination at the FEMP consists of low-level radioactivity, hazardous substances, hazardous wastes and/or mixed wastes. Regulations promulgated under the Resource Conservation and Recovery Act as amended (RCRA) are evaluated as applicable or relevant and appropriate requirements (ARARs) for remediation of the FEMP. Historically, joint CERCLA-RCRA guidance dictated that hazardous waste could not be treated, or moved out of the designated area of contiguous contamination (AOC), without triggering land disposal restrictions (LDRs) or minimum technology requirements (MTRs). To avoid invoking these stringent requirements, in situ capping was chosen as the lower cost remedy at many sites, although on-site disposal and/or treatment of hazardous wastes would have been more protective. The Corrective Action Management Units (CAMUs) and Temporary Units (TUs) Final Rule [58 FR 8658, Vol. 58, No. 29, hereinafter the open-quotes CAMU Ruleclose quotes], promulgated on February 16, 1993, provides facilities regulated under RCRA corrective action authority with greater flexibility to move, treat, and dispose of wastes on site without triggering LDRs or MTRs, thereby encouraging application of innovative technologies and more protective remedies. The waste acceptance criteria for the on-site disposal facility is based on site-specific considerations including the mobility of the contaminants through the underlying site geology and the protectiveness of the engineered liners. Application of the open-quotes CAMU Ruleclose quotes allows for disposition in the on-site facility based on these technical considerations rather than on regulatory classifications

  19. Characterization and remediation of soil prior to construction of an on-site disposal facility at Fernald

    International Nuclear Information System (INIS)

    Hunt, A.; Jones, G.; Nelson, K.

    1998-03-01

    During the production years at the Feed Materials Production Center (FMPC), the soil of the site and the surrounding areas was surficially impacted by airborne contamination. The volume of impacted soil is estimated at 2.2 million cubic yards. During site remediation, this contamination will be excavated, characterized, and disposed of. In 1986 the US Environmental Protection Agency (EPA) and the Department of Energy (DOE) entered into a Federal Facility Compliance Agreement (FFCA) covering environmental impacts associated with the FMPC. A site wide Remedial Investigation/Feasibility Study (RI/FS) was initiated pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act, as amended by the Superfund Amendments and Reauthorization Act (CERCLA). The DOE has completed the RI/FS process and has received approval of the final Records of Decision. The name of the facility was changed to the Fernald Environmental Management Project (FEMP) to emphasize the change in mission to environmental restoration. Remedial actions which address similar scopes of work or types of contaminated media have been grouped into remedial projects for the purpose of managing the remediation of the FEMP. The Soil Characterization and Excavation Project (SCEP) will address the remediation of FEMP soils, certain waste units, at- and below-grade material, and will certify attainment of the final remedial limits (FRLs) for the FEMP. The FEMP will be using an on-site facility for low level radioactive waste disposal. The facility will be an above-ground engineered structure constructed of geological material. The area designated for construction of the base of the on-site disposal facility (OSDF) is referred to as the footprint. Contaminated soil within the footprint must be identified and remediated. Excavation of Phase 1, the first of seven remediation areas, is complete

  20. Unique issues concerning ''placement'' vs ''movement'' of contaminated soils at ORNL's CERCLA sites

    International Nuclear Information System (INIS)

    Greer, J.K. Jr.; Schrof, C.A.

    1992-01-01

    At Oak Ridge National Laboratory, which is owned and operated by the US Department of Energy (DOE), there are several areas where hazardous wastes and/or radioactive materials have been placed in shallow land burial trenches or ''auger'' holes for disposal. Since Oak Ridge Reservation (ORR) has been placed on the National Priority List (NPL) by the US Environmental Protection Agency (EPA), the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) applies to waste disposal sites at ORNL. Under CERCLA, the RCRA regulations, pertaining to the LDRs, apply to CERCLA activities if the regulations are deemed ''applicable or relevant and appropriate'' (ARARS) by the lead agency or by the EPA. This report discusses the following issue: Under what conditions will contaminated soil and debris generated at a Superfund site be subject to the Resource Conservation and Recovery Act (RCRA) land disposal restrictions (LDRs) treatment standards?

  1. Proposed plan for interim remedial measures at the 100-KR-1 Operable Unit. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    This proposed plan identifies the preferred alternative for interim remedial measures for remedial action of radioactive liquid waste disposal sites that include contaminated soils and structures at the 100-KR-1 Operable Unit, located at the Hanford Site. It also summarizes other remedial alternatives evaluated for interim remedial measures in this Operable Unit. The intent of interim remedial measures is to speed up actions to address contaminated areas that pose potential threats to human health and the environment. This proposed plan is being issued by the US Environmental Protection Agency (EPA), the lead regulatory agency; the Washington State Department of Ecology (Ecology), the support regulatory agency; and the US Department of Energy (DOE), the responsible agency. The EPA, Ecology, and the DOE are issuing this proposed plan as part of their public participation responsibilities under Section 117(a) of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), commonly known as the ''Superfund Law.'' This proposed plan is intended to be a fact sheet for public review which briefly describes the remedial alternatives analyzed, identifies a preferred alternative, and summarizes the information relied upon to recommend the preferred alternative

  2. Remediating the INEL's buried mixed waste tanks

    International Nuclear Information System (INIS)

    Kuhns, D.J.; Matthern, G.E.; Reese, C.L.

    1996-01-01

    The Idaho National Engineering Laboratory (INEL), formerly the National Reactor Testing Station (NRTS), encompasses 890 square miles and is located in southeast Idaho. In 1949, the United States Atomic Energy Commission, now the Department of Energy (DOE), established the NRTS as a site for the building and testing of nuclear facilities. Wastes generated during the building and testing of these nuclear facilities were disposed within the boundaries of the site. These mixed wastes, containing radionuclides and hazardous materials, were often stored in underground tanks for future disposal. The INEL has 11 buried mixed waste storage tanks regulated under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) ranging in size from 400 to 50,000 gallons. These tanks are constructed of either stainless or carbon steel and are located at 3 distinct geographic locations across the INEL. These tanks have been grouped based on their similarities in an effort to save money and decrease the time required to complete the necessary remediation. Environmental Restoration and Technology Development personnel are teaming in an effort to address the remediation problem systematically

  3. Glossary of CERCLA, RCRA and TSCA related terms and acronyms. Environmental Guidance

    Energy Technology Data Exchange (ETDEWEB)

    1993-10-01

    This glossary contains CERCLA, RCRA and TSCA related terms that are most often encountered in the US Department of Energy (DOE) Environmental Restoration and Emergency Preparedness activities. Detailed definitions are included for key terms. The CERCLA definitions included in this glossary are taken from the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as amended and related federal rulemakings. The RCRA definitions included in this glossary are taken from the Resource Conservation and Recovery Act (RCRA) and related federal rulemakings. The TSCA definitions included in this glossary are taken from the Toxic Substances and Control Act (TSCA) and related federal rulemakings. Definitions related to TSCA are limited to those sections in the statute and regulations concerning PCBs and asbestos.Other sources for definitions include additional federal rulemakings, assorted guidance documents prepared by the US Environmental Protection Agency (EPA), guidance and informational documents prepared by the US Department of Energy (DOE), and DOE Orders. The source of each term is noted beside the term. Terms presented in this document reflect revised and new definitions published before July 1, 1993.

  4. Remedial investigation for the chemical plant area of the Weldon Spring Site

    International Nuclear Information System (INIS)

    1992-11-01

    The US Department of Energy (DOE) is responsible for management of the Weldon Spring Site Remedial Action Project (WSSRAP) under its Environmental Restoration and Waste Management Program. Major goals include eliminating potential public and environmental hazards due to site contamination and releasing the property for alternate uses to the maximum extent practicable. The purpose of the remedial investigation described in this report was to determine the extent of contamination associated with the portion of the Weldon Spring site known as the chemical plant and raffinate pit area. The DOE has assumed responsibility for investigating and remediating all on-site soil contamination and off-site soil which is radiologically contaminated as a result of uranium and thorium processing operations. The DOE has also assumed the responsibility for radiologically contaminated groundwater on and off site. The Weldon Spring site remedial investigation also involved the evaluation of the sources, nature and extent, and environmental fate and transport of contaminants to provide a basis for defining the risks that the contaminants may pose to human health and the environment. Data are included in this report to support the screening of remedial technologies and to permit the development and detailed analysis of alternatives for remedial action at the site during the feasibility study process

  5. Draft Hanford Remedial Action Environmental Impact Statement and Comprehensive Land Use Plan: Volume 2 of 4

    International Nuclear Information System (INIS)

    1996-08-01

    This appendix discusses the scope of actions addressed in the Draft Hanford Remedial Action Environmental Impact Statement and Comprehensive Land Use Plan. To address the purpose and need for agency action identified in Chapter 2.0 of the HRA-EIS, the scope includes an evaluation of the potential environmental impacts associated with the remedial actions to be conducted by the US Department of Energy (DOE) under the provisions of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) (Ecology et al. 1989). These remedial actions would bring the Hanford Site into compliance with the applicable requirements of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) and the Resource Conservation and Recovery Act of 1976 (RCRA). The DOE program responsible for conducting remedial actions at the Hanford Site is referred to as the Richland Environmental Restoration (ER) Project. The Richland ER Project encompasses the following projects: radiation area remedial actions and underground storage tanks (UST); RCRA closures; single-shell tank (SST) closures; past-practice waste site operable unit (source and groundwater) remedial actions; surplus facility decommissioning; and waste storage and disposal facilities

  6. Preliminary Investigations Of Effectiveness Of Herbal Remedies ...

    African Journals Online (AJOL)

    This study analysed some of the widely publicised herbal remedies in use for HIV infection in Nigeria, and investigated their efficacy scientifically. Those found to be efficacious will be subjected to further analysis to identify their active chemical components. The research deals directly with patients living with HIV/AIDS that ...

  7. 75 FR 5715 - Identification of Additional Classes of Facilities for Development of Financial Responsibility...

    Science.gov (United States)

    2010-02-04

    ... as facilities engaged in the recycling of materials containing CERCLA hazardous substances as... addition, the Agency identified the Waste Management and Remediation Services industry (NAICS 562), the... Liability Act (CERCLA). In addition, the Agency identified the Waste Management and Remediation Services...

  8. RCRA Facility Investigation/Remedial Investigation Report for the Grace Road Site (631-22G)

    Energy Technology Data Exchange (ETDEWEB)

    Palmer, E.

    1998-10-02

    This report summarizes the activities and documents the results of a Resource Conservation and Recovery Act Facility Investigation/Remedial Investigation conducted at Grace Road Site on the Savannah River Site near Aiken, South Carolina.

  9. RCRA Facility Investigation/Remedial Investigation Report for the Grace Road Site (631-22G)

    International Nuclear Information System (INIS)

    Palmer, E.

    1998-01-01

    This report summarizes the activities and documents the results of a Resource Conservation and Recovery Act Facility Investigation/Remedial Investigation conducted at Grace Road Site on the Savannah River Site near Aiken, South Carolina

  10. CERCLA integration with site operations the Fernald experience

    International Nuclear Information System (INIS)

    Coyle, S.W.; Shirley, R.S.; Varchol, B.D.

    1991-01-01

    A major transition in the Fernald Environmental Management Project (FEMP) site mission has occurred over the past few years. The production capabilities formally provided by the FEMP are being transferred to private industry through a vendor qualification program. Environmental compliance and site cleanup are now the primary focus. In line with this program, the production of uranium products at the site was suspended in July 1989 in order to concentrate resources on the environmental mission. Formal termination of the FEMP production mission was accomplished on June 19, 1991. Environmental issues such as stored inventories of process residues materials and equipment are being addressed under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA). The diversity of these hazards complicates the strategic planning for an integrated site cleanup program. This paper will discuss the programmatic approach which is being implemented to ensure activities such as waste management, site utility and support services, health and safety programs, and Resource Conservation and Recovery Act (RCRA) programs are being integrated with CERCLA. 6 figs., 3 tabs

  11. Idaho CERCLA Disposal Facility Complex Compliance Demonstration for DOE Order 435.1

    Energy Technology Data Exchange (ETDEWEB)

    Simonds, J.

    2007-11-06

    This compliance demonstration document provides an analysis of the Idaho CERCLA Disposal Facility (ICDF) Complex compliance with DOE Order 435.1. The ICDF Complex includes the disposal facility (landfill), evaporation pond, administration facility, weigh scale, and various staging/storage areas. These facilities were designed and constructed to be compliant with DOE Order 435.1, Resource Conservation and Recovery act Subtitle C, and Toxic Substances Control Act polychlorinated biphenyl design and construction standards. The ICDF Complex is designated as the Idaho National Laboratory (INL) facility for the receipt, staging/storage, treatment, and disposal of INL Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) waste streams.

  12. U Plant source aggregate area management study report

    International Nuclear Information System (INIS)

    1992-09-01

    The US Department of Energy (DOE) Hanford Site in Washington State is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989, included the 200 Areas of the Hanford Site on the National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) of 1980. Inclusion on the NPL initiates the Remedial Investigation (RI) and Feasibility Study (FS) process for characterizing the nature and extent of contamination, assessing risks to human health and the environment, and selection of remedial actions. This report presents the results of an aggregate area management study (AAMS) for the U Plant Aggregate Area located in the 200 Areas. The study provides the basis for initiating RI/FS under CERCLA or under the Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS). This report also integrates RCRA treatment, storage, or disposal (TSD) closure activities with CERCLA and RCRA past-practice investigations

  13. T Plant source aggregate area management study report

    International Nuclear Information System (INIS)

    1992-11-01

    The US Department of Energy (DOE) Hanford Site in Washington State is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989, included the 200 Areas of the Hanford Site on the National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) of 1980. Inclusion on the NPL initiates the Remedial Investigation (RI) and Feasibility Study (FS) process for characterizing the nature and extent of contamination, assessing risks to human health and the environment, and selection of remedial actions. This report presents the results of an aggregate area management study (AAMS) for the T Plant Aggregate Area located in the 200 Areas. The study provides the basis for initiating RI/FS under CERCLA or under the Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS). This report also integrates RCRA treatment, storage, or disposal (TSD) closure activities with CERCLA and RCRA past-practice investigations

  14. Record of Decision Remedial Alternative Selection for the D-Area Burning/Rubble Pits (431-D and 431-1D)

    Energy Technology Data Exchange (ETDEWEB)

    Palmer, E.R. [Westinghouse Savannah River Company, AIKEN, SC (United States); Mason, J.T.

    1997-02-01

    The D-Area Burning/Rubble Pits (DBRP) (431-D and 431-1D) Waste Unit is listed as a Resource Conservation and Recovery Act (RCRA) 3004(U) Solid Waste Management Unit/Comprehensive Environmental Response Compensation and Liability Act (CERCLA) unit in Appendix C of the Federal Facility Agreement (FFA) for the Savannah River Site (SRS). This decision document presents the selected remedial alternative for the DBRP located at the SRS in Aiken, South Carolina.

  15. Quality Assurance Plan for the Upper East Fork Poplar Creek Characterization Area, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-12-01

    This quality assurance plan summarizes requirements for conducting work on the Upper East 9 Fork Poplar Creek (UEFPC) Characterization Area (CA). The reader is referred to the Expanded Task Work Agreement for Upper East Fork Poplar Creek Characterization Area, Remedial Investigation/Feasibility Study (RI/FS) for details regarding the activities, roles, and responsibilities summarized here. UEFPC is designated a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) site and thus requires a remedial investigation (RI) and a feasibility study (FS). The RI objectives are to evaluate the nature and extent of known and suspected contaminates, to provide data to perform baseline ecological and human health risk assessments, and to support development and evaluation of remedial alternatives for the FS,. Existing data will be used as much as possible. Additional sampling may be required to fill data gaps. The goal of the RI is to prioritize the major sources of contaminants to exit pathways and to understand their characteristics for risk characterization and development of remedial alternatives. The FS objectives are to investigate technologies and develop and evaluate alternatives based on 2031 CERCLA guidance

  16. Integrating removal actions and remedial actions: Soil and debris management at the Fernald Environmental Management Project

    International Nuclear Information System (INIS)

    Goidell, L.C.; Hagen, T.D.; Strimbu, M.J.; Dupuis-Nouille, E.M.; Taylor, A.C.; Weese, T.E.; Yerace, P.J.

    1996-01-01

    Since 1991, excess soil and debris generated at the Fernald Environmental management Project (FEMP) have been managed in accordance with the principles contained in a programmatic Removal Action (RvA) Work Plan (WP). This plan provides a sitewide management concept and implementation strategy for improved storage and management of excess soil and debris over the period required to design and construct improved storage facilities. These management principles, however, are no longer consistent with the directions in approved and draft Records of Decision (RODs) and anticipated in draft RODs other decision documents. A new approach has been taken to foster improved management techniques for soil and debris that can be readily incorporated into remedial design/remedial action plans. Response, Compensation and Liability Act (CERCLA) process. This paper describes the methods that were applied to address the issues associated with keeping the components of the new work plan field implementable and flexible; this is especially important as remedial design is either in its initial stages or has not been started and final remediation options could not be precluded

  17. Remedial investigation sampling and analysis plan for J-Field, Aberdeen Proving Ground, Maryland. Volume 1: Field Sampling Plan

    Energy Technology Data Exchange (ETDEWEB)

    Benioff, P.; Biang, R.; Dolak, D.; Dunn, C.; Martino, L.; Patton, T.; Wang, Y.; Yuen, C.

    1995-03-01

    The Environmental Management Division (EMD) of Aberdeen Proving Ground (APG), Maryland, is conducting a remedial investigation and feasibility study (RI/FS) of the J-Field area at APG pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. J-Field is within the Edgewood Area of APG in Harford County, Maryland (Figure 1. 1). Since World War II activities in the Edgewood Area have included the development, manufacture, testing, and destruction of chemical agents and munitions. These materials were destroyed at J-Field by open burning and open detonation (OB/OD). Considerable archival information about J-Field exists as a result of efforts by APG staff to characterize the hazards associated with the site. Contamination of J-Field was first detected during an environmental survey of the Edgewood Area conducted in 1977 and 1978 by the US Army Toxic and Hazardous Materials Agency (USATHAMA) (predecessor to the US Army Environmental Center [AEC]). As part of a subsequent USATHAMA -environmental survey, 11 wells were installed and sampled at J-Field. Contamination at J-Field was also detected during a munitions disposal survey conducted by Princeton Aqua Science in 1983. The Princeton Aqua Science investigation involved the installation and sampling of nine wells and the collection and analysis of surficial and deep composite soil samples. In 1986, a Resource Conservation and Recovery Act (RCRA) permit (MD3-21-002-1355) requiring a basewide RCRA Facility Assessment (RFA) and a hydrogeologic assessment of J-Field was issued by the US Environmental Protection Agency (EPA). In 1987, the US Geological Survey (USGS) began a two-phased hydrogeologic assessment in data were collected to model, groundwater flow at J-Field. Soil gas investigations were conducted, several well clusters were installed, a groundwater flow model was developed, and groundwater and surface water monitoring programs were established that continue today.

  18. Fiscal year 1996 progress in implementing Section 120 of the Comprehensive Environmental Response, Compensation, and Liability Act. Tenth annual report to Congress

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-12-01

    Congress passed the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (Public Law 96-510), commonly known as Superfund, in 1980. The Superfund Amendments and Reauthorization Act (SARA) (Public Law 99-499), which amended CERCLA in 1986, added Section 120 regarding the cleanup of contaminated sites at Federal facilities. Under Section 120(e)(5) of CERCLA, each department, agency, or instrumentality of the Federal government responsible for compliance with Section 120 must submit an annual report to Congress concerning its progress in implementing the requirements of Section 120. The report must include information on the progress in reaching Interagency Agreements (IAGs), conducting remedial investigation and feasibility studies (RI/FSs), and performing remedial actions. Federal agencies that own or operate facilities on the National Priorities List (NPL) are required to begin an RI/FS for these facilities within 6 months after being placed on the NPL. Remediation of these facilities is addressed in an IAG between the Federal agency, the US Environmental Protection Agency (EPA), and in some instances the state within which the facility is located.

  19. 40 CFR 35.6340 - Disposal of CERCLA-funded property.

    Science.gov (United States)

    2010-07-01

    ... has stopped supporting the project. (b) Supplies. (1) If supplies have an aggregate fair market value.... (2) If the supplies remaining at the end of the project period have an aggregate fair market value of... actions at the direction of EPA: (i) Use the supplies on another CERCLA project and reimburse the original...

  20. Verification of EPA's " Preliminary remediation goals for radionuclides" (PRG) electronic calculator

    Energy Technology Data Exchange (ETDEWEB)

    Stagich, B. H. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL)

    2017-03-29

    The U.S. Environmental Protection Agency (EPA) requested an external, independent verification study of their “Preliminary Remediation Goals for Radionuclides” (PRG) electronic calculator. The calculator provides information on establishing PRGs for radionuclides at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites with radioactive contamination (Verification Study Charge, Background). These risk-based PRGs set concentration limits using carcinogenic toxicity values under specific exposure conditions (PRG User’s Guide, Section 1). The purpose of this verification study is to ascertain that the computer codes has no inherit numerical problems with obtaining solutions as well as to ensure that the equations are programmed correctly.

  1. Feasibility study for remedial action for the Quarry Residuals Operable Unit at the Weldon Spring Site, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1998-03-01

    The U.S. Department of Energy (DOE) is conducting cleanup activities at the Weldon Spring site, which is located in St. Charles County, Missouri, about 48 km (30 mi) west of St. Louis (Figure 1.1). Cleanup of the Weldon Spring site consists of several integrated components. The quarry residuals operable unit (QROU) is one of four operable units being evaluated. In accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, a remedial investigation/feasibility study (RI/FS) is being conducted to evaluate conditions and potential responses for the following areas and/or media that constitute the QROU: (1) the residual material (soil and sediment) remaining at the Weldon Spring quarry after removal of the bulk waste (about 11 million L [3 million gal] of uranium-contaminated ponded water was also addressed previous to bulk waste removal); (2) other media located in the surrounding vicinity of the quarry, including adjacent soil, surface water, and sediment in Femme Osage Slough and several creeks; and (3) quarry groundwater located primarily north of Femme Osage Slough. Potential impacts to the St. Charles County well field downgradient of the quarry area are also being addressed as part of QROU RI/FS evaluations. For remedial action sites, it is DOE policy to integrate values associated with the National Environmental Policy Act (NEPA) into the CERCLA decision-making process. The analyses contained herein address NEPA values as appropriate to the actions being considered for the QROU. A work plan summarizing initial site conditions and providing conceptual site hydrogeological and exposure models was published in January 1994. The RI and baseline risk assessment (BRA) reports have been completed. The RI discusses in detail the nature and extent and the fate and transport of contamination at the quarry area

  2. Feasibility study for remedial action for the Quarry Residuals Operable Unit at the Weldon Spring Site, Weldon Spring, Missouri

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-03-01

    The U.S. Department of Energy (DOE) is conducting cleanup activities at the Weldon Spring site, which is located in St. Charles County, Missouri, about 48 km (30 mi) west of St. Louis (Figure 1.1). Cleanup of the Weldon Spring site consists of several integrated components. The quarry residuals operable unit (QROU) is one of four operable units being evaluated. In accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, a remedial investigation/feasibility study (RI/FS) is being conducted to evaluate conditions and potential responses for the following areas and/or media that constitute the QROU: (1) the residual material (soil and sediment) remaining at the Weldon Spring quarry after removal of the bulk waste (about 11 million L [3 million gal] of uranium-contaminated ponded water was also addressed previous to bulk waste removal); (2) other media located in the surrounding vicinity of the quarry, including adjacent soil, surface water, and sediment in Femme Osage Slough and several creeks; and (3) quarry groundwater located primarily north of Femme Osage Slough. Potential impacts to the St. Charles County well field downgradient of the quarry area are also being addressed as part of QROU RI/FS evaluations. For remedial action sites, it is DOE policy to integrate values associated with the National Environmental Policy Act (NEPA) into the CERCLA decision-making process. The analyses contained herein address NEPA values as appropriate to the actions being considered for the QROU. A work plan summarizing initial site conditions and providing conceptual site hydrogeological and exposure models was published in January 1994. The RI and baseline risk assessment (BRA) reports have been completed. The RI discusses in detail the nature and extent and the fate and transport of contamination at the quarry area.

  3. Postconstruction report of the United Nuclear Corporation Disposal Site at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environmental Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    Oakley, L.B.; Siberell, J.K.; Voskuil, T.L.

    1993-06-01

    Remedial actions conducted under the auspices of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) were completed at the Y-12 United Nuclear Corporation (UNC) Disposal Site in August 1992. The purpose of this Postconstruction Report is to summarize numerous technical reports and provide CERCLA documentation for completion of the remedial actions. Other CERCLA reports, such as the Feasibility Study for the UNC Disposal Site, provide documentation leading up to the remedial action decision. The remedial action chosen, placement of a modified RCRA cap, was completed successfully, and performance standards were either met or exceeded. This remedial action provided solutions to two environmentally contaminated areas and achieved the goal of minimizing the potential for contamination of the shallow groundwater downgradient of the site, thereby providing protection of human health and the environment. Surveillance and maintenance of the cap will be accomplished to ensure cap integrity, and groundwater monitoring downgradient of the site will continue to confirm the acceptability of the remedial action chosen.

  4. Postconstruction report of the United Nuclear Corporation Disposal Site at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Oakley, L.B.; Siberell, J.K.; Voskuil, T.L.

    1993-06-01

    Remedial actions conducted under the auspices of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) were completed at the Y-12 United Nuclear Corporation (UNC) Disposal Site in August 1992. The purpose of this Postconstruction Report is to summarize numerous technical reports and provide CERCLA documentation for completion of the remedial actions. Other CERCLA reports, such as the Feasibility Study for the UNC Disposal Site, provide documentation leading up to the remedial action decision. The remedial action chosen, placement of a modified RCRA cap, was completed successfully, and performance standards were either met or exceeded. This remedial action provided solutions to two environmentally contaminated areas and achieved the goal of minimizing the potential for contamination of the shallow groundwater downgradient of the site, thereby providing protection of human health and the environment. Surveillance and maintenance of the cap will be accomplished to ensure cap integrity, and groundwater monitoring downgradient of the site will continue to confirm the acceptability of the remedial action chosen

  5. Environmental guidance regulatory bulletin

    International Nuclear Information System (INIS)

    1994-12-01

    On September 22,1993, the Environmental Protection Agency (EPA) published [58 Federal Register (FR) 492001 the final OffSite Rule, which defines criteria for approving facilities for receiving waste from response actions taken under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). The off-site requirements apply to the off-site management of hazardous substances, pollutants, and contaminants, as defined under CERCLA, that are generated from remedial and removal actions funded or authorized, at least in part, by CERCLA. CERCLA-authorized cleanups include those taken under lead-agency authority, Section 106 Consent Orders, Consent Agreements, Consent Degrees, and Records of Decision (RODs). EPA requires that remedial actions at Federal facilities taken under Sections 104, 106, or 120 of CERCLA comply with the Off-Site Rule for all cleanups enacted through DOE's lead-agency authority

  6. Applicability of Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) to releases of radioactive substances

    International Nuclear Information System (INIS)

    Miller, S.R.

    1987-01-01

    The Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), commonly called Superfund, provided a $1.6 billion fund (financed by a tax on petrochemical feedstocks and crude oil and by general revenues) for the cleanup of releases of hazardous substances, including source, special nuclear or byproduct material, and other radioactive substances, from mostly inactive facilities. The US Environmental Protection Agency (EPA) is authorized to require private responsible parties to clean up releases of hazardous substances, or EPA, at its option, may undertake the cleanup with monies from the Fund and recover the monies through civil actions brought against responsible parties. CERCLA imposes criminal penalties for noncompliance with its reporting requirements. This paper will overview the key provisions of CERCLA which apply to the cleanup of radioactive materials

  7. Fiscal Year 1994 progress in implementing Section 120 of the Comprehensive Environmental Rresponse, Compensation, and Liability Act. Eighth annual report to Congress

    International Nuclear Information System (INIS)

    1995-07-01

    Congress passed the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (Public Law 96-510), commonly known as Superfund, in 1980. The Superfund Amendments and Reauthorization Act (SARA) (Public Law 99-499), which amended CERCLA in 1986, added Section 120 regarding the cleanup of contaminated sites at Federal facilities. Under Section 120(e)(5) of CERCLA, each department, agency, or instrumentality of the Federal government responsible for compliance with Section 120 must submit an annual report to Congress concerning its progress in implementing the requirements of Section 120. The report must include information on the progress in reaching Interagency Agreements (IAGs), conducting Remedial Investigation and Feasibility Studies (RI/FSs), and performing remedial actions. Federal agencies that own or operate facilities on the National Priorities List (NPL) are required to begin an RI/FS for these facilities within 6 months after being placed on the NPL. Remediation of these facilities is addressed in an IAG between the Federal agency, the U.S. Environmental Protection Agency (EPA), and in some instances the state within which the facility is located. This report, prepared by the U.S. Department of Energy's (DOE's) Office of Environmental Management, is being submitted to Congress in accordance with Section 120(e)(5) of CERCLA. It is DOE's Eighth Annual Report to Congress and provides information on DOE's progress in implementing CERCLA Section 120 in Fiscal Year 1994 (FY 94), i.e., from October 1, 1993, to September 30, 1994. In this report the words open-quotes siteclose quotes and open-quotes facilityclose quotes are used interchangeably

  8. Salmon Site Remedial Investigation Report, Appendix B (Part 2)

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  9. Salmon Site Remedial Investigation Report, Appendix B (Part 1)

    International Nuclear Information System (INIS)

    1999-01-01

    This Salmon Site Remedial Investigation Report provides the results of activities initiated by the U.S. Department of Energy (DOE) to determine if contamination at the Salmon Site poses a current or future risk to human health and the environment. These results were used to develop and evaluate a range of risk-based remedial alternatives. Located in Lamar County, Mississippi, the Salmon Site was used by the U.S. Atomic Energy Commission (predecessor to the DOE) between 1964 and 1970 for two nuclear and two gas explosions conducted deep underground in a salt dome. The testing resulted in the release of radionuclides into the salt dome. During reentry drilling and other site activities, liquid and solid wastes containing radioactivity were generated resulting in surface soil and groundwater contamination. Most of the waste and contaminated soil and water were disposed of in 1993 during site restoration either in the cavities left by the tests or in an injection well. Other radioactive wastes were transported to the Nevada Test Site for disposal. Nonradioactive wastes were disposed of in pits at the site and capped with clean soil and graded. The preliminary investigation showed residual contamination in the Surface Ground Zero mud pits below the water table. Remedial investigations results concluded the contaminant concentrations detected present no significant risk to existing and/or future land users, if surface institutional controls and subsurface restrictions are maintained. Recent sampling results determined no significant contamination in the surface or shallow subsurface. The test cavity resulting from the experiments is contaminated and cannot be economically remediated with existing technologies. The ecological sampling did not detect biological uptake of contaminants in the plants or animals sampled. Based on the current use of the Salmon Site, the following remedial actions were identified to protect both human health and the environment: (1) the

  10. Remedial Investigation Work Plan for J-Field, Aberdeen Proving Ground, Maryland

    Energy Technology Data Exchange (ETDEWEB)

    Benioff, P.; Biang, R.; Dolak, D.; Dunn, C.; Haffenden, R.; Martino, L.; Patton, T.; Wang, Y.; Yuen, C.

    1995-03-01

    The purpose of an RI/FS is to characterize the nature and extent of the risks posed by contaminants present at a site and to develop and evaluate options for remedial actions. The overall objective of the RI is to provide a comprehensive evaluation of site conditions, types and quantities of contaminants present, release mechanisms and migration pathways, target populations, and risks to human health and the environment. The information developed during the RI provides the basis for the design and implementation of remedial actions during the FS. The purpose of this RI Work Plan is to define the tasks that will direct the remedial investigation of the J-Field site at APG.

  11. In situ vitrification on buried waste

    International Nuclear Information System (INIS)

    Bates, S.O.

    1992-01-01

    In situ vitrification (ISV) is being evaluated as a remedial treatment technology for buried mixed and transuranic (TRU) wastes at the Subsurface Disposal Area (SDA) at Idaho National Engineering Laboratory (INEL) and can be related to buried wastes at other Department of Energy (DOE) sites. There are numerous locations around the DOE Complex where wastes were buried in the ground or stored for future burial. The Buried Waste Program (BWP) is conducting a comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) remedial investigation/feasibility study (RI/FS) for the Department of Energy - Field Office Idaho (DOE-ID). As part of the RI/FS, an ISV scoping study on the treatability of the SDA mixed low-level and mixed TRU waste is being performed for applicability to remediation of the waste at the Radioactive Waste Management Complex (RWMC). The ISV project being conducted at the INEL by EG ampersand G Idaho, Inc. consists of a treatability investigation to collect data to satisfy nine CERCLA criteria with regards to the SDA. This treatability investigation involves a series of experiments and related efforts to study the feasibility of ISV for remediation of mixed and TRU waste disposed of at the SDA

  12. Corrective action management unit application for the Environmental Restoration Disposal Facility

    Energy Technology Data Exchange (ETDEWEB)

    Evans, G.C.

    1994-06-01

    The Environmental Restoration Disposal Facility (ERDF) is to accept both CERCLA (EPA-regulated) and RCRA (Ecology-regulated) remediation waste. The ERDF is considered part of the overall remediation strategy on the Hanford Site, and as such, determination of ERDF viability has followed both RCRA and CERCLA decision making processes. Typically, determination of the viability of a unit, such as the ERDF, would occur as part of record of decision (ROD) or permit modification for each remediation site before construction of the ERDF. However, because construction of the ERDF may take a significant amount of time, it is necessary to begin design and construction of the ERDF before final RODs/permit modifications for the remediation sites. This will allow movement of waste to occur quickly once the final remediation strategy for the RCRA and CERCLA past-practice units is determined. Construction of the ERDF is a unique situation relative to Hanford Facility cleanup, requiring a Hanford Facility specific process be developed for implementing the ERDF that would satisfy both RCRA and CERCLA requirements. While the ERDF will play a significant role in the remediation process, initiation of the ERDF does not preclude the evaluation of remedial alternatives at each remediation site. To facilitate this, the January 1994 amendment to the Tri-Party Agreement recognizes the necessity for the ERDF, and the Tri-Party Agreement states: ``Ecology, EPA, and DOE agree to proceed with the steps necessary to design, approve, construct, and operate such a ... facility.`` The Tri-Party Agreement requires the DOE-RL to prepare a comprehensive ``package`` for the EPA and Ecology to consider in evaluating the ERDF. The package is to address the criteria listed in 40 CFR 264.552(c) for corrective action management unit (CAMU) designation and a CERCLA ROD. This CAMU application is submitted as part of the Tri-Party Agreement-required information package.

  13. Corrective action management unit application for the Environmental Restoration Disposal Facility

    International Nuclear Information System (INIS)

    Evans, G.C.

    1994-06-01

    The Environmental Restoration Disposal Facility (ERDF) is to accept both CERCLA (EPA-regulated) and RCRA (Ecology-regulated) remediation waste. The ERDF is considered part of the overall remediation strategy on the Hanford Site, and as such, determination of ERDF viability has followed both RCRA and CERCLA decision making processes. Typically, determination of the viability of a unit, such as the ERDF, would occur as part of record of decision (ROD) or permit modification for each remediation site before construction of the ERDF. However, because construction of the ERDF may take a significant amount of time, it is necessary to begin design and construction of the ERDF before final RODs/permit modifications for the remediation sites. This will allow movement of waste to occur quickly once the final remediation strategy for the RCRA and CERCLA past-practice units is determined. Construction of the ERDF is a unique situation relative to Hanford Facility cleanup, requiring a Hanford Facility specific process be developed for implementing the ERDF that would satisfy both RCRA and CERCLA requirements. While the ERDF will play a significant role in the remediation process, initiation of the ERDF does not preclude the evaluation of remedial alternatives at each remediation site. To facilitate this, the January 1994 amendment to the Tri-Party Agreement recognizes the necessity for the ERDF, and the Tri-Party Agreement states: ''Ecology, EPA, and DOE agree to proceed with the steps necessary to design, approve, construct, and operate such a ... facility.'' The Tri-Party Agreement requires the DOE-RL to prepare a comprehensive ''package'' for the EPA and Ecology to consider in evaluating the ERDF. The package is to address the criteria listed in 40 CFR 264.552(c) for corrective action management unit (CAMU) designation and a CERCLA ROD. This CAMU application is submitted as part of the Tri-Party Agreement-required information package

  14. CERCLA and RCRA requirements affecting cleanup of a hazardous waste management unit at a Superfund site: A case study

    International Nuclear Information System (INIS)

    Walsh, T.J.

    1995-03-01

    The Fernald Environmental Management Project (FEMP) attempted to address both RCRA and CERCLA requirements at the fire training facility (FTF) by integrating a CERCLA removal action work plan with a RCRA closure plan. While the regulatory agencies involved with the FTF cleanup agreed the integrated document was a good idea, implementation proved complicated, owing to disposition of clean debris from a Superfund site, treatment of contaminated media, duration of cleanup activities, and cleanup certification. While all the complications have not been resolved, solutions to all have been proposed to Ohio EPA and U.S. EPA. Both agencies have worked closely with FEMP to find the most effective fulfillment of RCRA and CERCLA requirements

  15. Selected remedy at the Queen City Farms superfund site: A risk management approach

    International Nuclear Information System (INIS)

    Weber, E.F.; Wilson, J.; Kirk, M.; Tochko, S.

    1994-01-01

    A risk management approach at a former industrial waste disposal site in western Washington resulted in a selected remedy that is cost-effective and that meets the CERCLA threshold criterion of protecting human health and the environment. The proposed remedy, which addresses contamination in soil and groundwater, does not require an ARARs waiver and received state and community acceptance. By analyzing the current and potential risk at the site, a proposed remedy was chosen that would control the source and naturally attenuate the groundwater plume. Source control will include removal and treatment of some light nonaqueous phase liquid (LNAPL) and some soil, followed by isolation of the remaining soil and LNAPL within a slurry wall and beneath a multilayer cap. A contingent groundwater extraction and treatment system was included to address uncertainty in the risk characterization. Implementing source control is predicted to result in a steady decline in volatile organic compound levels in the drinking water aquifer through adsorption, degradation, and dispersion. Exposure to groundwater during the period of natural attenuation will be controlled by monitoring, institutional controls, and a thorough characterization of the plume and receptors. 7 figs., 1 tab

  16. Environmental Restoration Disposal Facility waste acceptance criteria. Revision 1

    International Nuclear Information System (INIS)

    Corriveau, C.E.

    1996-01-01

    The Environmental Restoration Disposal Facility (ERDF) is designed to be an isolation structure for low-level radioactive remediation waste, chemically contaminated remediation waste, and remediation waste that contains both chemical and radioactive constituents (i.e., mixed remediation waste) produced during environmental remediation of Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) past-practice units at the Hanford Site. Remedial action wastes, which will become a structural component of the ERDF, include bulk soil, demolition debris, and miscellaneous wastes from burial grounds. These wastes may originate from CERCLA past-practice sites (i.e., operable units) in the 100 Areas, the 200 Areas, and the 300 Area of the Hanford Site

  17. 200 West Groundwater Aggregate Area management study report

    International Nuclear Information System (INIS)

    1993-01-01

    This report presents the results of an aggregate area management study (AAMS) for the 200 West Groundwater Aggregate Area in the 200 Areas of the US Department of Energy (DOE) Hanford Site in Washington State. This scoping level study provides the basis for initiating Remedial Investigation/Feasibility Study (RI/FS) activities under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or Resource Conservation and Recovery Act (RCRA), Facility Investigations (Rlq) and Corrective Measures Studies (CMS) under RCRA. This report also integrates select RCRA treatment, storage or disposal (TSD) closure activities with CERCLA and RCRA past practice investigations

  18. 200 North Aggregate Area source AAMS report

    International Nuclear Information System (INIS)

    1993-06-01

    This report presents the results of an aggregate area management study (AAMS) for the 200 North Aggregate Area in the 200 Areas of the US Department of Energy (DOE) Hanford Site in Washington State. This scoping level study provides the basis for initiating Remedial Investigation/Feasibility Study (RI/FS) activities under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) or Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS) under RCRA. This report also integrates select RCRA treatment, storage, or disposal (TSD) closure activities with CERCLA and RCRA past practice investigations

  19. PUREX source Aggregate Area management study report

    International Nuclear Information System (INIS)

    1993-03-01

    This report presents the results of an aggregate area management study (AAMS) for the PUREX Plant Aggregate Area in the 200 Areas of the US Department of Energy (DOE)Hanford Site in Washington State. This scoping level study provides the basis for initiating Remedial Investigation/Feasibility Study (RI/FS) activities under the comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) or Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS) under RCRA. This report also integrates select RCRA treatment, storage, or disposal (TSD) closure activities with CERCLA and RCRA past-practice investigations

  20. 200 North Aggregate Area source AAMS report

    Energy Technology Data Exchange (ETDEWEB)

    1993-06-01

    This report presents the results of an aggregate area management study (AAMS) for the 200 North Aggregate Area in the 200 Areas of the US Department of Energy (DOE) Hanford Site in Washington State. This scoping level study provides the basis for initiating Remedial Investigation/Feasibility Study (RI/FS) activities under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) or Resource Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS) under RCRA. This report also integrates select RCRA treatment, storage, or disposal (TSD) closure activities with CERCLA and RCRA past practice investigations.

  1. Analysis of abandoned potential CERCLA hazardous waste sites using historic aerial photographs

    International Nuclear Information System (INIS)

    Rosowitz, D.W.; Franzen, P.A.; Green, D.J.

    1993-01-01

    Aerial photographs of varying scale from federal agencies and commercial aerial service companies covering the years 1938, 1942, 1948, 1952, 1957, 1960, 1970, 1971, 1977, and 1986 of the Edgewood Area of Aberdeen Proving Ground (APG), Maryland, (Gunpowder Neck 7.5 Minute United States Geological Survey Topographic Quadrangle Map) were evaluated for identification of potential Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) hazardous waste sites and land use changes for approximately 1500 acres (610 hectares) used in the testing of military-related chemicals and munitions on Carroll Island and Graces Quarters. Detailed testing records exist only for July 1964 to December 1971, thus making the interpretation of aerial photographs a valuable tool in reconstructing past activities from the late 1930s to June 1964 and guiding future sampling locations in the multiphased CERCLA process. Many potential test sites were activated by either clear-cutting tracks of vegetation or using existing cleared land until final abandonment of the site(s) circa 1974-1975. Ground inspection of open-quotes land scarringclose quotes at either known or suspected sites was essential for verifying the existence, location, and subsequent sampling of potential CERCLA sites. Photomorphic mapping techniques are described to delineate and compare different land use changes in past chemical and munitions handling and testing. Delineation of features was based on photographic characteristics of tone, pattern, texture, shape, shadow, size, and proximity to known features. 7 refs., 9 figs

  2. Waste Management Plan for the Lower East Fork Poplar Creek Remedial Action Project Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-08-01

    The Lower East Fork Poplar Creek (LEFPC) Remedial Action project will remove mercury-contaminated soils from the floodplain of LEFPC, dispose of these soils at the Y-12 Landfill V, and restore the affected floodplain upon completion of remediation activities. This effort will be conducted in accordance with the Record of Decision (ROD) for LEFPC as a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) action. The Waste Management Plan addresses management and disposition of all wastes generated during the remedial action for the LEFPC Project Most of the solid wastes will be considered to be sanitary or construction/demolition wastes and will be disposed of at existing Y-12 facilities for those types of waste. Some small amounts of hazardous waste are anticipated, and the possibility of low- level or mixed waste exists (greater than 35 pCi/g), although these are not expected. Liquid wastes will be generated which will be sanitary in nature and which will be capable of being disposed 0214 of at the Oak Ridge Sewage Treatment Plant.

  3. Waste Management Plan for the Lower East Fork Poplar Creek Remedial Action Project Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-08-01

    The Lower East Fork Poplar Creek (LEFPC) Remedial Action project will remove mercury-contaminated soils from the floodplain of LEFPC, dispose of these soils at the Y-12 Landfill V, and restore the affected floodplain upon completion of remediation activities. This effort will be conducted in accordance with the Record of Decision (ROD) for LEFPC as a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) action. The Waste Management Plan addresses management and disposition of all wastes generated during the remedial action for the LEFPC Project Most of the solid wastes will be considered to be sanitary or construction/demolition wastes and will be disposed of at existing Y-12 facilities for those types of waste. Some small amounts of hazardous waste are anticipated, and the possibility of low- level or mixed waste exists (greater than 35 pCi/g), although these are not expected. Liquid wastes will be generated which will be sanitary in nature and which will be capable of being disposed 0214 of at the Oak Ridge Sewage Treatment Plant

  4. Remedial investigation report on waste area grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 4, Appendix C, Risk assessment

    International Nuclear Information System (INIS)

    1995-09-01

    Waste Area Grouping (WAG) 5 is part of Oak Ridge National Laboratory (ORNL) and is located on the United States Department of Energy's Oak Ridge Reservation (DOE-ORR). The site lies southeast of Haw Ridge in Melton Valley and comprises approximately 32 ha (80 ac) [12 ha (30 ac) of forested area and the balance in grassed fields]. Waste Area Grouping 5 consists of several contaminant source areas for the disposal of low-level radioactive, transuranic (TRU), and fissile wastes (1959 to 1973) as well as inorganic and organic chemical wastes. Wastes were buried in trenches and auger holes. Radionuclides from buried wastes are being transported by shallow groundwater to Melton Branch and White Oak Creek. Different chemicals of potential concern (COPCs) were identified (e.g., cesium-137, strontium-90, radium-226, thorium-228, etc.); other constituents and chemicals, such as vinyl chloride, bis(2-ethylhexyl)phthalate, trichloroethene, were also identified as COPCs. Based on the results of this assessment contaminants of concern (COCs) were subsequently identified. The objectives of the WAG 5 Baseline Human Health Risk Assessment (BHHRA) are to document the potential health hazards (i.e., risks) that may result from contaminants on or released from the site and provide information necessary for reaching informed remedial decisions. As part of the DOE-Oak Ridge Operations (ORO), ORNL and its associated waste/contamination sites fall under the auspices of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), also known as Superfund under the Superfund Amendments and Reauthorization Act (SARA). The results of the BHHRA will (1) document and evaluate risks to human health, (2) help determine the need for remedial action, (3) determine chemical concentrations protective of current and future human receptors, and (4) help select and compare various remedial alternatives.

  5. Defining the role of risk assessment in the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) remedial investigation process at the DOE-OR

    International Nuclear Information System (INIS)

    Miller, P.D.; McGinn, C.W.; Purucker, S.T.; White, R.K.

    1994-08-01

    The risk assessment strategy that will be implemented on the Oak Ridge Reservation has been standardized to ensure consistency and technical defensibility in all risk assessment activities and is presented within this document. The strategy emphasizes using existing environmental data in screening risk analyses to aid in identifying chemicals of potential concern, operable units that could pursue a no further investigation determination, and operable units that may warrant early response actions. The screening risk analyses include a comparison of measured chemical concentrations to preliminary remediation goals, performing a most likely exposure and integration point assessment, and performing a screening ecological risk assessment. This document focuses heavily on the screening risk analyses and relies on existing U.S. Environmental Protection Agency risk assessment guidance to provide specific details on conducting baseline risk assessments. However, the document does contain a section on the baseline risk assessment process that details the exposure pathways to be evaluated on the Oak Ridge Reservation. This document will be used in conjunction with existing Martin Marietta Energy Systems, Inc. Environmental Restoration risk assessment standards, policies, procedures, and technical memoranda. The material contained herein will be periodically updated as the strategy is tried and tested and as the risk assessment methodology is revised. The primary purpose for this document is to present the proposed strategy to the Tennessee Department of Environment and Conservation and the U.S. Environmental Protection Agency, Region IV and receive concurrence or additional comments on the material presented herein

  6. 76 FR 73622 - Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or Superfund...

    Science.gov (United States)

    2011-11-29

    ... tribe'' is defined in this document as it is defined in CERCLA section 101(36). Intertribal consortia... print at libraries, or other community gathering places. \\7\\ For further information on latitude and...

  7. Laboratory open-quotes proof of principleclose quotes investigation for the acoustically enhanced remediation technology

    International Nuclear Information System (INIS)

    Iovenitti, J.L.; Spencer, J.W.; Hill, D.G.

    1995-01-01

    This document describes a three phase program of Weiss Associates which investigates the systematics of using acoustic excitation fields (AEFs) to enhance the in-situ remediation of contaminated soil and ground water under both saturated and unsaturated conditions. The focus in this particular paper is a laboratory proof of principle investigation. The field deployment and engineering viability of acoustically enhanced remediation technology is also examined

  8. 77 FR 69827 - Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or Superfund...

    Science.gov (United States)

    2012-11-21

    ... defined in CERCLA section 101(36). Intertribal consortia, as defined in the Federal Register Notice at 67... record including making it available on-line, in print at libraries, or other community gathering places...

  9. Vicinity Property Assessments at Formerly Utilized Sites Remedial Action Program Project Sites in the New York District - 13420

    Energy Technology Data Exchange (ETDEWEB)

    Ewy, Ann; Hays, David [U.S. Army Corps of Engineers (United States)

    2013-07-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) has addressed sites across the nation for almost 4 decades. Multiple stake holder pressures, multiple regulations, and process changes occur over such long time periods. These result in many challenges to the FUSRAP project teams. Initial FUSRAP work was not performed under Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Records of Decision (ROD). The ROD identifies the remedy decision and ultimately the criteria to be used to release a site. Early FUSRAP projects used DOE Orders or the Uranium Mill Tailings Radiation Control Act (UMTRCA) standards. Under current RODs, regulations may differ, resulting in different cleanup criteria than that used in prior Vicinity Property (VP) remediation. The USACE, in preparation for closeout of Sites, conducts reviews to evaluate whether prior actions were sufficient to meet the cleanup criteria specified in the current ROD. On the basis of these reviews, USACE has conducted additional sampling, determined that prior actions were sufficient, or conducted additional remediation consistent with the selected remedy in the ROD. As the public pressures, regulations, and processes that the FUSRAP encounters continue to change, the program itself continues to evolve. Assessment of VPs at FUSRAP sites is a necessary step in the life cycle of our site management. (authors)

  10. Vicinity Property Assessments at Formerly Utilized Sites Remedial Action Program Project Sites in the New York District - 13420

    International Nuclear Information System (INIS)

    Ewy, Ann; Hays, David

    2013-01-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) has addressed sites across the nation for almost 4 decades. Multiple stake holder pressures, multiple regulations, and process changes occur over such long time periods. These result in many challenges to the FUSRAP project teams. Initial FUSRAP work was not performed under Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Records of Decision (ROD). The ROD identifies the remedy decision and ultimately the criteria to be used to release a site. Early FUSRAP projects used DOE Orders or the Uranium Mill Tailings Radiation Control Act (UMTRCA) standards. Under current RODs, regulations may differ, resulting in different cleanup criteria than that used in prior Vicinity Property (VP) remediation. The USACE, in preparation for closeout of Sites, conducts reviews to evaluate whether prior actions were sufficient to meet the cleanup criteria specified in the current ROD. On the basis of these reviews, USACE has conducted additional sampling, determined that prior actions were sufficient, or conducted additional remediation consistent with the selected remedy in the ROD. As the public pressures, regulations, and processes that the FUSRAP encounters continue to change, the program itself continues to evolve. Assessment of VPs at FUSRAP sites is a necessary step in the life cycle of our site management. (authors)

  11. Long range planning, scheduling and budgeting for the environmental compliance program at the Rocky Flats Plant

    International Nuclear Information System (INIS)

    McKinley, K.B.; Nielsen, T.H.

    1989-01-01

    This paper reports how the Rocky Flats RCRA/CERCLA group at the Rocky Flats Plant in Golden, Colorado is developing a computerized schedule and budget management system. The system will aggregate schedule, budgets, and regulatory commitments provided by RCRA/CERCLA program managers. The system will provide tabular and graphical representations of the schedule and budget information at various levels of detail. The system will perform a variety of analyses on the schedule and budget. The RCRA/CERCLA group will use the results to develop realistic compliance schedules and the budgets necessary to meet them. Presentation of the schedules and budgets in a consistent graphical and tabular form will give a good appreciation of the remediation costs as understood by the RCRA/CERCLA group. The system will then be used to test resource availability and remediation period scenarios, differing from the optimal combination as determined by the RCRA/CERCLA group

  12. Applicable or relevant and appropriate requirements (ARARs) for remedial actions at the Paducah Gaseous Diffusion Plant: A compendium of environmental laws and guidance

    International Nuclear Information System (INIS)

    Etnier, E.L.; Eaton, L.A.

    1992-03-01

    Section 121 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980 specifies that remedial actions for cleanup of hazardous substances found at sites placed on the National Priorities List (NPL) by the US Environmental Protection Agency (EPA) must comply with applicable or relevant and appropriate requirements (ARARs) or standards under federal and state environmental laws. To date, the US Department of Energy (DOE) Paducah Gaseous Diffusion Plant (PGDP) has not been on the NPL. Although DOE and EPA have entered into an Administrative Consent Order (ACO), the prime regulatory authority for cleanup at PGDP will be the Resource Conservation and Recovery Act (RCRA). This report supplies a preliminary list of available federal and state ARARs that might be considered for remedial response at PGDP in the event that the plant becomes included on the NPL or the ACO is modified to include CERCLA cleanup. A description of the terms ''applicable'' and ''relevant and appropriate'' is provided, as well as definitions of chemical-, location-, and action-specific ARARS. ARARs promulgated by the federal government and by the state of Kentucky are listed in tables. In addition, the major provisions of RCRA, the Safe Drinking Water Act, the Clean Water Act, the Clean Air Act, and other acts, as they apply to hazardous and radioactive waste cleanup, are discussed

  13. Completion report for the isolation and remediation of inactive liquid low-level radioactive waste tanks WC-5, WC-6, WC-8, WC-19, 3002-A, 7560, and 7562 at Oak Ridge National Laboratory Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1997-12-01

    The Federal Facility Agreement (FFA) between the U.S. Environmental Protection Agency (EPA), Tennessee Department of Environment and Conservation (TDEC), and U.S. Department of Energy (DOE) requires that all liquid low-level waste tanks at Oak Ridge National Laboratory removed from service, designated in the FFA as Category D, be remediated in accordance with Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements. A human health risk screening assessment was conducted for inactive Tanks WC-5, WC-6, WC-8, WC-19, 3002-A, 7560, and 7562 as part of an evaluation to determine the method of remediation necessary to safely and permanently isolate and remediate the tanks. Risk screening assessment results indicated that the health risks associated with these tanks were within or below the EPA range of concern of 1 x 10 -4 to 1 x 10 -6 . On the basis of these results and with regulators concurrence, it was determined that either no action or in-place stabilization of the tanks would satisfy risk-based remediation goals. Therefore, decisions were made and approved by DOE to remediate these tanks in-place as maintenance actions rather than actions under the CERCLA process. Letters documenting these decisions were approved by DOE and subsequently submitted to TDEC and EPA, who concurred with the maintenance actions. Tanks WC-5, WC-6, WC-8, WC-19, 3002-A, 7560, and 7562 were isolated from associated piping, electrical systems, and instrumentation and were grouted in-place. Tank 7562 was originally isolated from associated piping and instrumentation and left in-place empty for future remedial consideration. Upon further consideration, the decision was made by DOE, with concurrence by the regulators, to complete the maintenance action of Tank 7562 by grouting it in-place in March 1997

  14. Real-Time Remediation Utilizing The Backpack Sodium Iodide System And The U.S. EPA Triad Approach

    International Nuclear Information System (INIS)

    John R. Giles; Michael V. Carpenter; Lyle G. Roybal; C. P. Oertel; J. J. Jacobson; D. L. Eaton; G. L. Schwendiman

    2006-01-01

    Real-time characterization during remediation activities is being accomplished at the Idaho National Laboratory (INL) with the use of the backpack sodium iodide system (BaSIS). The BaSIS is comprised of a 3-in. by 5-in. sodium iodide (NaI) detector, differential corrected global positioning system (GPS), and portable computer, integrated into a lightweight backpack deployment platform. The system is operated with specialized software that allows the operator and/or remediation field manager to view data as they are collected. Upon completion of planned excavation stages, the area is surveyed for residual radiological contamination. After data collection is complete, data is available to the remediation field manager as a contour map showing the area(s) that require further excavation. The use of real-time measurement systems, rapid turn-around time of data, and dynamic work strategy support the U.S. Environmental Protection Agency's (EPA) Triad approach. Decisions are made in real-time as to the need for further remediation. This paper describes the BaSIS system calibration, testing and use, and outlines negotiations with the appropriate CERCLA regulatory agencies (U.S. Environmental Protection Agency, Idaho Department of Environmental Quality, and U.S. Department of Energy Idaho Operations Office) to allow the use of real-time instrumentation during the remediation process, and for confirmation surveys. By using the BaSIS in such a manner, the INL seeks to demonstrate compliance with remediation objectives

  15. The 300 area waste acid treatment system closure plan

    International Nuclear Information System (INIS)

    Luke, S.N.

    1996-01-01

    The 300 Area Waste Acid Treatment System (WATS) is located within operable units 300-FF-2 (source) and 300-FF-5 (groundwater), as designated in the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) . Operable units 300-FF-2 and 300-FF-5 are scheduled to be remediated using the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) Remedial Investigation/Feasibility Study (RI/FS) process. Thus, any remediation of the 300 Area WATS with respect to contaminants not produced by those facilities and soils and groundwater will be deferred to the CERCLA RI/FS process. Final closure activities will be completed in 3 phases and certified in accordance with the 300 Area WATS closure plan by the Washington State Department of Ecology (Ecology) and the U.S. Environmental Protection Agency (EPA). It is anticipated that the 300 Area WATS closure would take 2 years to complete

  16. Petroleum refining and the national priorities list: The preemption of CERCLA

    International Nuclear Information System (INIS)

    Hart, D.G.

    1991-01-01

    The petroleum refining industry has preempted aspects of the implementation of CERCLA through a clause in the original legislation that makes the listing of petroleum refining sites on the NPL more difficult than it would be otherwise. The NPL, which was mandated in CERCLA, is a list of sites open-quotes where a hazardous substance has been deposited, stored, disposed of, placed, or otherwise come to be located. The petroleum exclusion clause, Section 101(14)(F) of CERCLA, states that the term hazardous substance open-quotes does not include petroleum, including crude oil or any fraction thereof which is not otherwise specifically listed or designated as a hazardous substance.close quotes This clause has been interpreted to mean that a site where petroleum products are found may not be listed on the NPL on the basis of the petroleum products; a hazardous substance that is not a normal constituent of petroleum products also must be found at the site. Regression analysis shows that the petroleum refining industry is significantly positively correlated with discovered sites (where a possibility exists that hazardous substances may be present) and significantly negatively correlated with sites that are proposed to the NPL. These, findings suggest that sites that meet the technical criteria for NPL listing are not proposed because of the petroleum exclusion clause. Although the chemical industry also produces substances that are considered hazardous, it is significantly correlated only with proposed sites, and that correlation is positive. The purpose of this paper is to present evidence suggesting that this clause was a response by Congress to an organized interest-the petroleum refining industry, which possessed a political power not available to the less-focused chemical industry

  17. Work plan for the remedial investigation/feasibility study for the groundwater operable units at the Chemical Plant Area and the Ordnance Works Area, Weldon Spring, Missouri

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-08-01

    US Department of Energy (DOE) and the US Army Corps of Engineers (CE) are conducting cleanup activities at two properties, the chemical plant area and the ordnance works area, located adjacent to one another in St. Charles County, Missouri. In accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, DOE and CE are evaluating conditions and potential responses at the chemical plant area and at the ordnance works area, respectively, to address groundwater and surface water contamination. This work plan provides a comprehensive evaluation of areas that are relevant to the (GWOUs) of both the chemical plant and the ordnance works area. Following areas or media are addressed in this work plan: groundwater beneath the chemical plant area (including designated vicinity properties described in Section 5 of the RI for the chemical plant area [DOE 1992d]) and beneath the ordnance works area; surface water and sediment at selected springs, including Burgermeister Spring. The organization of this work plan is as follows: Chapter 1 discusses the objectives for conducting the evaluation, including a summary of relevant site information and overall environmental compliance activities to be undertaken; Chapter 2 presents a history and a description of the site and areas addressed within the GWOUs, along with currently available data; Chapter 3 presents a preliminary evaluation of areas included in the GWOUs, which is based on information given in Section 2, and discusses data requirements; Chapter 4 presents rationale for data collection or characterization activities to be carried out in the remedial investigation (RI) phase, along with brief summaries of supporting documents ancillary to this work plan; Chapter 5 discusses the activities planned for GWOUs under each of the 14 tasks for an remedial (RI/FS); Chapter 6 presents proposed schedules for RI/FS for the GWOUS; and Chapter 7 explains the project management structure.

  18. Work plan for the remedial investigation/feasibility study for the groundwater operable units at the Chemical Plant Area and the Ordnance Works Area, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1995-08-01

    US Department of Energy (DOE) and the US Army Corps of Engineers (CE) are conducting cleanup activities at two properties, the chemical plant area and the ordnance works area, located adjacent to one another in St. Charles County, Missouri. In accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, DOE and CE are evaluating conditions and potential responses at the chemical plant area and at the ordnance works area, respectively, to address groundwater and surface water contamination. This work plan provides a comprehensive evaluation of areas that are relevant to the (GWOUs) of both the chemical plant and the ordnance works area. Following areas or media are addressed in this work plan: groundwater beneath the chemical plant area (including designated vicinity properties described in Section 5 of the RI for the chemical plant area [DOE 1992d]) and beneath the ordnance works area; surface water and sediment at selected springs, including Burgermeister Spring. The organization of this work plan is as follows: Chapter 1 discusses the objectives for conducting the evaluation, including a summary of relevant site information and overall environmental compliance activities to be undertaken; Chapter 2 presents a history and a description of the site and areas addressed within the GWOUs, along with currently available data; Chapter 3 presents a preliminary evaluation of areas included in the GWOUs, which is based on information given in Section 2, and discusses data requirements; Chapter 4 presents rationale for data collection or characterization activities to be carried out in the remedial investigation (RI) phase, along with brief summaries of supporting documents ancillary to this work plan; Chapter 5 discusses the activities planned for GWOUs under each of the 14 tasks for an remedial (RI/FS); Chapter 6 presents proposed schedules for RI/FS for the GWOUS; and Chapter 7 explains the project management structure

  19. Remedial investigation/feasibility study for the David Witherspoon, Inc., 901 Site, Knoxville, Tennessee: Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-10-01

    This remedial investigation (RI)/feasibility study (FS) supports the selection of remedial actions for the David Witherspoon, Inc. 901 Maryville Pike Site in Knoxville, Tennessee. Operations at the site, used as a recycling center, have resulted in past, present, and potential future releases of hazardous substances in to the environment. This Site is a Tennessee Superfund site. A phased approach was planned to (1) gather existing data from previous investigations managed by the Tenn. Dept. of Environment and Conservation; (2) perform a preliminary RI, including risk assessments, and an FS with existing data to identify areas where remedial action may be necessary; (3) gather additional field data to adequately define the nature and extent of risk-based contaminants that present identifiable threats to human and/or ecological receptors; and (4) develop remedial action alternatives to reduce risks to acceptable levels.

  20. Remedial investigation/feasibility study for the David Witherspoon, Inc., 901 Site, Knoxville, Tennessee: Volume 1

    International Nuclear Information System (INIS)

    1996-10-01

    This remedial investigation (RI)/feasibility study (FS) supports the selection of remedial actions for the David Witherspoon, Inc. 901 Maryville Pike Site in Knoxville, Tennessee. Operations at the site, used as a recycling center, have resulted in past, present, and potential future releases of hazardous substances in to the environment. This Site is a Tennessee Superfund site. A phased approach was planned to (1) gather existing data from previous investigations managed by the Tenn. Dept. of Environment and Conservation; (2) perform a preliminary RI, including risk assessments, and an FS with existing data to identify areas where remedial action may be necessary; (3) gather additional field data to adequately define the nature and extent of risk-based contaminants that present identifiable threats to human and/or ecological receptors; and (4) develop remedial action alternatives to reduce risks to acceptable levels

  1. Proposed plan for interim remedial measures at the 100-HR-1 Operable Unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1995-01-01

    This proposed plan identifies the preferred alternative for interim remedial measures for remedial action of radioactive liquid waste disposal sites at the 100-HR-1 Operable Unit, located at the Hanford Site. It also summarizes other remedial alternatives evaluated for interim remedial measures in this operable unit. The intent of interim remedial measures is to speed up actions to address contaminated areas that historically received radioactive liquid waste discharges that pose a potential threat to human health and the environment. This proposed plan is being issued by the Washington State Department of Ecology (Ecology), the lead regulatory agency; the US Environmental Protection Agency (EPA), the support regulatory agency; and the US Department of Energy (DOE), the responsible agency. Ecology, EPA, and DOE are issuing this proposed plan as part of their public participation responsibilities under Section 117(a) of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), commonly known as the ''Superfund Program.'' The proposed plan is intended to be a fact sheet for public review that (1) briefly describes the remedial alternatives analyzed; (2) proposes a preferred alternative; (3) summarizes the information relied upon to recommend the preferred alternative; and (4) provides a basis for an interim action record of decision (ROD). The preferred alternative presented in this proposed plan is removal, treatment (as appropriate), and disposal of contaminated soil and associated structures. Treatment will be conducted if there is cost benefit

  2. Hanfor site past practice investigation strategy

    International Nuclear Information System (INIS)

    Thompson, K.M.

    1991-01-01

    The US Department of Energy (DOE), US Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) have negotiated a strategy for performing Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) Past Practice investigations in a more streamlined manner with a bias-for-action. This strategy provides new concepts for (1) accelerating decision-making by maximizing the use of existing data consistent with data quality objectives and (2) undertaking expedited response actions and/or interim remedial measures as appropriate to either remove threats to human health and welfare and the environment or to reduce risk by reducing toxicity, mobility or volume of contaminants. Since the goal of the program is cleanup, much more emphasis will be placed on initiating and completing waste site cleanups through interim measures. While investigations and studies are important in meeting long-range goals, there is now agreement by the parties that an appropriate and significant portion of the near-term funding resources can and should be dedicated to remedial work, where there is sufficient information from which to plan and implement interim remedial measures. The initial stages of Hanford clean-up will optimize the use of interim cleanup actions when justified and practicable. Existing data will be evaluated as the initial basis for decision-making. If the data are found to be insufficient, additional essential data will be collected to support the IRM in a limited field investigation (LFI). Only data needed to formulate a conceptual model (source to pathway to receptor) and qualitative risk assessment would be obtained. The data quality objectives of the LFI will be established based on the use of the data in deciding on IRMs

  3. SACM and the RCRA stabilization initiative: Similarities of principles and applicability

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-01-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the corrective action provisions of the Resource Conservation and Recovery Act (RCRA) provide standards for the remediation of environmental media contaminated with hazardous substances or hazardous waste, respectively. In both cases, prior to the US Environmental Protection Agency`s (EPA) development of the two subject reform initiatives, existing formal processes specified the level of site investigation required, the process for reaching a decision on the method of remediation, public participation in the decision process, and enforcement authorities that include orders and schedules of compliance. Traditionally, implementation of these processes has resulted in a great amount of time, effort, and money being expended before actual remediation began. Following criticism from the public and the regulated community, the EPA has proposed streamlining reforms for hazardous waste site cleanup under both CERCLA and RCRA that will begin remediation sooner with lower costs. The purpose of this Information Brief is to discuss the common goals, processes, and strategies of the Superfund Accelerated Cleanup Model (SACM) and the RCRA Stabilization Initiative.

  4. Rail transportation of Fernald remediation waste

    International Nuclear Information System (INIS)

    Fellman, R.T.; Lojek, D.A.; Motl, G.P.; Weddendorf, W.K.

    1995-01-01

    Remediation of the Department of Energy (DOE) Fernald site located north of Cincinnati will generate large quantities of low-level radwaste. This volume includes approximately 1,050,000 tons of material to be removed from eight waste pits comprising Operable Unit 1 (OU-1). The remedial alternative selected includes waste material excavation, drying and transportation by rail to a burial site in the arid west for disposal. Rail transportation was selected not only because rail transportation is safer than truck transportation, but also because of the sheer magnitude of the project and the availability of bulk rail car unloading facilities at a representative disposal site. Based upon current waste quantity estimates as presented in the Feasibility Study for OUI, a fully-loaded 47-car unit train would depart the Fernald site weekly for five years. This paper illustrates the steps taken to obtain agency and public acceptance of the Record of Decision for the remedy which hinged on rail transportation. A preliminary, but detailed, rail transportation plan was prepared for the project to support a series of CERCLA public meetings conducted in late 1994. Some of the major issues addressed in the plan included the following: (1) Scope of project leading to selection of rail transportation; (2) Waste classification; (3) Rail Company overview; (4) Train configuration and rail car selection; (5) Routing; (6) Safety; (7) Prior Notification Requirements (8) Emergency Response. A series of three public meetings identified a number of issues of prime concern to Fernald stakeholders. Following resolution of these issues during the public comment period, a Record of Decision (ROD) approving implementation of the rail transportation strategy was approved pending incorporation of EPA and State of Ohio comments on December 22, 1994

  5. Completion report for the Inactive Liquid Low-Level Waste Tank Remediation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-02-01

    This report documents the results of the Inactive Liquid Low-Level Waste Tank Remediation Project at Oak Ridge National Laboratory (ORNL). The work performed is compared with that proposed in the statement of work and the service contract specification for the maintenance action to remediate tanks 3013, 3004-B, T-30, and 3001-B. The Federal Facility Agreement (FFA) among the U.S. Environmental Protection Agency (EPA), the Tennessee Department of Environment and Conservation (TDEC), and the U.S. Department of Energy (DOE) requires that all tanks, which have been removed from service and are designated in the FFA as Category D, must be remediated in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements. The Environmental Restoration Program's inactive tank removal program strategy and plans for remediating the inactive LLLW tanks were documented in a report issued in January 1995 (Inactive Tanks Remediation Program Strategy and Plans for Oak Ridge National Laboratory, Oak Ridge, Tennessee, ORNL/ER-297). The inactive (Category D) tanks were initially screened for remediation according to risk, remediation technology required, level of instrumentation available, interferences with other piping and equipment, location, and available sludge removal techniques and storage requirements. On the basis of this preliminary screening, the tanks were assigned to one of five batches (I through V) for consideration of remedial action alternatives, and these batches were tentatively scheduled for remedial actions. The eight links tentatively assigned to Batch I were divided into two groups (Series I and Series II)

  6. Environmental Compliance and Protection Program Description Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    Bechtel Jacobs

    2009-02-26

    The objective of the Environmental Compliance and Protection (EC and P) Program Description (PD) is to establish minimum environmental compliance requirements and natural resources protection goals for the Bechtel Jacobs Company LLC (BJC) Oak Ridge Environmental Management Cleanup Contract (EMCC) Contract Number DE-AC05-98OR22700-M198. This PD establishes the work practices necessary to ensure protection of the environment during the performance of EMCC work activities on the US Department of Energy's (DOE's) Oak Ridge Reservation (ORR) in Oak Ridge, Tennessee, by BJC employees and subcontractor personnel. Both BJC and subcontractor personnel are required to implement this PD. A majority of the decontamination and demolition (D and D) activities and media (e.g., soil and groundwater) remediation response actions at DOE sites on the ORR are conducted under the authority of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). CERCLA activities are governed by individual CERCLA decision documents (e.g., Record of Decision [ROD] or Action Memorandum) and according to requirements stated in the Federal Facility Agreement for the Oak Ridge Reservation (DOE 1992). Applicable or relevant and appropriate requirements (ARARs) for the selected remedy are the requirements for environmental remediation responses (e.g., removal actions and remedial actions) conducted under CERCLA.

  7. In-Situ Radiological Surveys to Address Nuclear Criticality Safety Requirements During Remediation Activities at the Shallow Land Disposal Area, Armstrong County, Pennsylvania - 12268

    Energy Technology Data Exchange (ETDEWEB)

    Norris, Phillip; Mihalo, Mark; Eberlin, John; Lambert, Mike [Cabrera Services (United States); Matthews, Brian [Nuclear Safety Associates (United States)

    2012-07-01

    Cabrera Services Inc. (CABRERA) is the remedial contractor for the Shallow Land Disposal Area (SLDA) Site in Armstrong County Pennsylvania, a United States (US) Army Corps of Engineers - Buffalo District (USACE) contract. The remediation is being completed under the USACE's Formerly Utilized Sites Remedial Action Program (FUSRAP) which was established to identify, investigate, and clean up or control sites previously used by the Atomic Energy Commission (AEC) and its predecessor, the Manhattan Engineer District (MED). As part of the management of the FUSRAP, the USACE is overseeing investigation and remediation of radiological contamination at the SLDA Site in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 US Code (USC), Section 9601 et. seq, as amended and, the National Oil and Hazardous Substance Pollution Contingency Plan (NCP), Title 40 of the Code of Federal Regulations (CFR) Section 300.430(f) (2). The objective of this project is to clean up radioactive waste at SLDA. The radioactive waste contains special nuclear material (SNM), primarily U-235, in 10 burial trenches, Cabrera duties include processing, packaging and transporting the waste to an offsite disposal facility in accordance with the selected remedial alternative as defined in the Final Record of Decision (USACE, 2007). Of particular importance during the remediation is the need to address nuclear criticality safety (NCS) controls for the safe exhumation and management of waste containing fissile materials. The partnership between Cabrera Services, Inc. and Measutronics Corporation led to the development of a valuable survey tool and operating procedure that are essential components of the SLDA Criticality Safety and Material Control and Accountability programs. Using proven existing technologies in the design and manufacture of the Mobile Survey Cart, the continued deployment of the Cart will allow for an efficient and reliable

  8. Evolution of EPA/DOE technical cooperation in remediation of radiation/mixed waste contaminated sites

    International Nuclear Information System (INIS)

    Dyer, Robert S.; Garcia-Frias, Beverly; Wolbarst, Anthony B.; Coe, Larry J.

    1992-01-01

    The EPA Office of Radiation Programs (ORP) and the DOE Office of Environmental Restoration and Waste Management (EM) are cooperating in efforts related to restoration of radioactive and mixed waste sites. The impetus for these efforts derived from DOE's need to perform restoration activities according to CERCLA/RCRA requirements, and from ORP's role as a supplier of radiation expertise to federal agencies. These activities include: assessing remediation technology, developing radioanalytical protocols; matching cleanup technologies to soil characteristics; developing a process for the evaluation, selection, and appropriate use of groundwater models; reviewing incinerator practices; and addressing technical issues associated with the WIPP. Cooperative projects planned for the future include: evaluation of methodologies for streamlining the restoration process; assessment of the applicability of process knowledge for waste characterization; evaluation of recycling of radioactive metals; and expansion of selected environmental protection initiatives at the International Atomic Energy Agency (IAEA). Public acceptance is a crucial component of the remediation process. An underlying objective of these cooperative initiatives is to address issues of concern to the public in an open and honest fashion. (author)

  9. Waste area Grouping 2 Phase I remedial investigation: Sediment and Cesium-137 transport modeling report

    International Nuclear Information System (INIS)

    Clapp, R.B.; Bao, Y.S.; Moore, T.D.; Brenkert, A.L.; Purucker, S.T.; Reece, D.K.; Burgoa, B.B.

    1996-06-01

    This report is one of five reports issued in 1996 that provide follow-up information to the Phase I Remedial Investigation (RI) Report for Waste Area Grouping (WAG) 2 at Oak Ridge National Laboratory (ORNL). The five reports address areas of concern that may present immediate risk to public health at the Clinch River and ecological risk within WAG 2 at ORNL. A sixth report, on groundwater, in the series documenting WAG 2 RI Phase I results were part of project activities conducted in FY 1996. The five reports that complete activities conducted as part of Phase I of the Remedial Investigation (RI) for WAG 2 are as follows: (1) Waste Area Grouping 2, Phase I Task Data Report: Seep Data Assessment, (2) Waste Area Grouping 2, Phase I Task Data Report: Tributaries Data Assessment, (3) Waste Area Grouping 2, Phase I Task Data Report: Ecological Risk Assessment, (4) Waste Area Grouping 2, Phase I Task Data Report: Human Health Risk Assessment, (5) Waste Area Grouping 2, Phase I Task Data Report: Sediment and 137 Cs Transport Modeling In December 1990, the Remedial Investigation Plan for Waste Area Grouping 2 at Oak Ridge National Laboratory was issued (ORNL 1990). The WAG 2 RI Plan was structured with a short-term component to be conducted while upgradient WAGs are investigated and remediated, and a long-term component that will complete the RI process for WAG 2 following remediation of upgradient WAGs. RI activities for the short-term component were initiated with the approval of the Environmental Protection Agency, Region IV (EPA), and the Tennessee Department of Environment and Conservation (TDEC). This report presents the results of an investigation of the risk associated with possible future releases of 137 Cs due to an extreme flood. The results are based on field measurements made during storms and computer model simulations

  10. RCRA Facility Investigation/Remedial Investigation Report with Baseline Risk Assessment for the Fire Department Hose Training Facility (904-113G)

    Energy Technology Data Exchange (ETDEWEB)

    Palmer, E. [Westinghouse Savannah River Company, AIKEN, SC (United States)

    1997-04-01

    This report documents the Resource Conservation and Recovery Act (RCRA) Facility Investigation/Remedial Investigation/Baseline Risk Assessment (RFI/RI/BRA) for the Fire Department Hose Training Facility (FDTF) (904-113G).

  11. Tank 241-Z-361 vapor sampling and analysis plan

    Energy Technology Data Exchange (ETDEWEB)

    BANNING, D.L.

    1999-02-23

    Tank 241-Z-361 is identified in the Hanford Federal Facility Agreement and Consent Order (commonly referred to as the Tri-Party Agreement), Appendix C, (Ecology et al. 1994) as a unit to be remediated under the authority of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). As such, the U.S. Environmental Protection Agency will serve as the lead regulatory agency for remediation of this tank under the CERCLA process. At the time this unit was identified as a CERCLA site under the Tri-Party Agreement, it was placed within the 200-ZP-2 Operable Unit. In 1997, The Tri-parties redefined 200 Area Operable Units into waste groupings (Waste Site Grouping for 200 Areas Soils Investigations [DOE-RL 1992 and 1997]). A waste group contains waste sites that share similarities in geological conditions, function, and types of waste received. Tank 241-Z-361 is identified within the CERCLA Plutonium/Organic-rich Process Condensate/Process Waste Group (DOE-RL 1992). The Plutonium/Organic-rich Process Condensate/Process Waste Group has been prioritized for remediation beginning in the year 2004. Results of Tank 216-Z-361 sampling and analysis described in this Sampling and Analysis Plan (SAP) and in the SAP for sludge sampling (to be developed) will determine whether expedited response actions are required before 2004 because of the hazards associated with tank contents. Should data conclude that remediation of this tank should occur earlier than is planned for the other sites in the waste group, it is likely that removal alternatives will be analyzed in a separate Engineering Evaluation/Cost Analysis (EE/CA). Removal actions would proceed after the U.S. Environmental Protection Agency (EPA) signs an Action Memorandum describing the selected removal alternative for Tank 216-Z-361. If the data conclude that there is no immediate threat to human health and the environment from this tank, remedial actions for the tank will be defined in a

  12. Work plan for support to Upper East Fork Poplar Creek east end VOC plumes well installation project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1998-03-01

    Under the Resource Conservation and Recovery Act of 1976 guidelines and requirements from the Tennessee Department of Environment and Conservation (TDEC), the Y-12 Plant initiated investigation and monitoring of various sites within its boundaries in the mid-1980s. The entire Oak Ridge Reservation (ORR) was placed on the National Priorities List of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) sites in November 1989. Following CERCLA guidelines, sites within the ORR require a remedial investigation (RI) to define the nature and extent of contamination, evaluate the risks to public health and the environment, and determine the goals for a feasibility study (FS) or an engineering evaluation/cost analysis (EE/CA) of potential remedial actions. Data from monitoring wells at the east end of the Y-12 Plant have identified an area of groundwater contamination dominated by the volatile organic compound (VOC) carbon tetrachloride; other VOCs include chloroform, tetrachloroethene, and trichloroethene

  13. Work plan for support to Upper East Fork Poplar Creek east end VOC plumes well installation project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-03-01

    Under the Resource Conservation and Recovery Act of 1976 guidelines and requirements from the Tennessee Department of Environment and Conservation (TDEC), the Y-12 Plant initiated investigation and monitoring of various sites within its boundaries in the mid-1980s. The entire Oak Ridge Reservation (ORR) was placed on the National Priorities List of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) sites in November 1989. Following CERCLA guidelines, sites within the ORR require a remedial investigation (RI) to define the nature and extent of contamination, evaluate the risks to public health and the environment, and determine the goals for a feasibility study (FS) or an engineering evaluation/cost analysis (EE/CA) of potential remedial actions. Data from monitoring wells at the east end of the Y-12 Plant have identified an area of groundwater contamination dominated by the volatile organic compound (VOC) carbon tetrachloride; other VOCs include chloroform, tetrachloroethene, and trichloroethene.

  14. Risk assessment and optimization (ALARA) analysis for the environmental remediation of Brookhaven National Laboratory's hazardous waste management facility

    International Nuclear Information System (INIS)

    Dionne, B.J.; Morris, S. III; Baum, J.W.

    1998-03-01

    The Department of Energy's (DOE) Office of Environment, Safety, and Health (EH) sought examples of risk-based approaches to environmental restoration to include in their guidance for DOE nuclear facilities. Extensive measurements of radiological contamination in soil and ground water have been made at Brookhaven National Laboratory's Hazardous Waste Management Facility (HWMF) as part of a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) remediation process. This provided an ideal opportunity for a case study. This report provides a risk assessment and an open-quotes As Low as Reasonably Achievableclose quotes (ALARA) analysis for use at other DOE nuclear facilities as an example of a risk-based decision technique

  15. RFI/RI work plan for the Road A Chemical Basin 904-111G

    International Nuclear Information System (INIS)

    Kmetz, T.F.

    2000-01-01

    This Resource Conservation and Recovery Act (RCRA) Facility Investigation (RFI)/Remedial Investigation (RI) Work Plan has been prepared for the Road A Chemical Basin Operable Unit (RdACB OU) (904-111G). This unit is subject to the requirements of both RCRA and the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). This Work Plan presents the initial evaluation of existing unit data, applicable background data, the regulatory framework for the unit investigation, and the evaluations and decisions made during the determination of the scope and objectives of the planned Remedial Investigation/Feasibility Study (RI/FS) activities

  16. RFI/RI work plan for the Road A Chemical Basin 904-111G

    Energy Technology Data Exchange (ETDEWEB)

    Kmetz, T.F.

    2000-03-07

    This Resource Conservation and Recovery Act (RCRA) Facility Investigation (RFI)/Remedial Investigation (RI) Work Plan has been prepared for the Road A Chemical Basin Operable Unit (RdACB OU) (904-111G). This unit is subject to the requirements of both RCRA and the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). This Work Plan presents the initial evaluation of existing unit data, applicable background data, the regulatory framework for the unit investigation, and the evaluations and decisions made during the determination of the scope and objectives of the planned Remedial Investigation/Feasibility Study (RI/FS) activities.

  17. What's an ARAR?exclamation point: Regulatory requirements for CERCLA remedial activities at D ampersand D sites on the Oak Ridge Reservation

    International Nuclear Information System (INIS)

    Houlberg, L.M.; Etnier, E.L.

    1994-01-01

    Many government-owned facilities that supported early nuclear energy research and defense programs have no current use and have been retired. Some of these facilities have residual radioactive or chemical contamination that require remediation. The Department of Energy (DOE) Decontamination and Decommissioning (D ampersand D) Program is responsible for managing these surplus facilities. Remedial activities for contaminated environs and inactive land-based units (e.g., landfills, surface impoundments) at the Oak Ridge Reservation (ORR) are conducted under the direction of the Environmental Restoration (ER) Program

  18. Idaho CERCLA Disposal Facility Complex Waste Acceptance Criteria

    Energy Technology Data Exchange (ETDEWEB)

    W. Mahlon Heileson

    2006-10-01

    The Idaho Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Disposal Facility (ICDF) has been designed to accept CERCLA waste generated within the Idaho National Laboratory. Hazardous, mixed, low-level, and Toxic Substance Control Act waste will be accepted for disposal at the ICDF. The purpose of this document is to provide criteria for the quantities of radioactive and/or hazardous constituents allowable in waste streams designated for disposal at ICDF. This ICDF Complex Waste Acceptance Criteria is divided into four section: (1) ICDF Complex; (2) Landfill; (3) Evaporation Pond: and (4) Staging, Storage, Sizing, and Treatment Facility (SSSTF). The ICDF Complex section contains the compliance details, which are the same for all areas of the ICDF. Corresponding sections contain details specific to the landfill, evaporation pond, and the SSSTF. This document specifies chemical and radiological constituent acceptance criteria for waste that will be disposed of at ICDF. Compliance with the requirements of this document ensures protection of human health and the environment, including the Snake River Plain Aquifer. Waste placed in the ICDF landfill and evaporation pond must not cause groundwater in the Snake River Plain Aquifer to exceed maximum contaminant levels, a hazard index of 1, or 10-4 cumulative risk levels. The defined waste acceptance criteria concentrations are compared to the design inventory concentrations. The purpose of this comparison is to show that there is an acceptable uncertainty margin based on the actual constituent concentrations anticipated for disposal at the ICDF. Implementation of this Waste Acceptance Criteria document will ensure compliance with the Final Report of Decision for the Idaho Nuclear Technology and Engineering Center, Operable Unit 3-13. For waste to be received, it must meet the waste acceptance criteria for the specific disposal/treatment unit (on-Site or off-Site) for which it is destined.

  19. Superfund record of decision (EPA Region 4): Savannah River Site (USDOE) D-Area Oil Seepage Basin (631-G), Aiken, SC, August 14, 1998

    International Nuclear Information System (INIS)

    1999-03-01

    The D-Area Oil Seepage Basin (D-Area OSB) Operable Unit (OU) is listed as a Resource Conservation and Recovery Act (RCRA) 3004(u) Solid Waste Management Unit/Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) unit in Appendix C of the Federal Facility Agreement (FFA) for the Savannah River Site (SRS). No Action is the selected remedy for shallow soil, surface water and sediment, because no constituents of concern (COCs) were identified for them in the RCRA Facility Investigation/Remedial Investigation/Baseline Risk Assessment (RFI/RI/BRA). The selected remedy for D-Area OSB groundwater is Alternative GW-2: Natural Attenuation/Groundwater Mixing Zone (GWMZ) with Institutional Controls

  20. Semiworks source aggregate area management study report

    International Nuclear Information System (INIS)

    1993-05-01

    This report presents the results of an aggregate area management study (AAMS) for the Semi-Works Aggregate Area in the 200 Areas of the US Department of Energy (DOE) . Hanford Site in Washington State. This scoping level study provides the basis for initiating Remedial Investigation/Feasibility Study (RI/FS) activities under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) or Resource Conservation and Recovery Act (RCRA) Facility Investigations WD and Corrective Measures Studies (CMS) under RCRA. This report also integrates select RCRA treatment storage, or disposal (TSD) closure activities with CERCLA and RCRA past-practice investigations. This approach is described and justified in The Hanford Federal Facility Agreement and Consent Order Change Package. This strategy provides new concepts for: accelerating decision-malting by maximizing the use of existing data consistent with data quality objectives (DQOs); and undertaking expedited response actions (ERAS) and/or interim remedial measures (IRMs), as appropriate, to either remove threats to human health and welfare and the environment, or to reduce risk by reducing toxicity, mobility, or volume of contaminants

  1. 40 CFR 300.440 - Procedures for planning and implementing off-site response actions.

    Science.gov (United States)

    2010-07-01

    ... unless the Remedial Project Manager or OSC assures the proper management of the CERCLA waste samples or... OIL AND HAZARDOUS SUBSTANCES POLLUTION CONTINGENCY PLAN Hazardous Substance Response § 300.440... § 300.440(d). (5) Off-site transfers of those laboratory samples and treatability study CERCLA wastes...

  2. Addendum to the Phase 2 Sampling and Analysis Plan for the Clinch River Remedial Investigation

    International Nuclear Information System (INIS)

    1994-03-01

    This document is an addendum to the Phase 2 Sampling and Analysis Plan for the Clinch River Remedial Investigation (DOE 1993). The Department of Energy--Oak Ridge Operations (DOE-ORO) is proposing this addendum to the US Envianmental Protection Agency, Region IV (EPA-IV), and the Tennessee Department of Environment and Conservation (TDEC) as a reduced sampling program on the Clinch River arm of Watts Bar Reservoir and on Poplar Creek. DOE-ORO is proposing to maximize the use of existing data and minimize the collection of new data for water, sediment, and biota during Phase 2 of the Clinch River Remedial Investigation. The existing data along with the additional data collected in Phase 2 would be used to perform a baseline risk assessment and make remedial decisions. DOE-ORO considers that the existing data, the additional data collected in Phase 2, and on-site remedial investigation data would be sufficient to understand the nature and extent of the contamination problem in the Clinch River, perform a baseline risk assessment,and make remedial decisions. This addendum is organized in three sections. The first section provides background information and describes a rationale for modifying the Phase 2 Sampling and Analysis Plan. Section 2 presents a summary of the existing data for the Clinch River arm of Watts Bar Reservoir and an evaluation of the sufficiency of this data for a baseline human health and ecological risk assessment. Section 3 describes the revised Phase 2 Sampling and Analysis Plan for surface water, sediment, and biota in the Clinch River OU and in the Poplar Creek OU

  3. Remedial investigation/feasibility study work plan for the 300-FF-1 operable unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1990-03-01

    Over 1,400 waste facilities have been identified on the Hanford Site. Most of the waste facilities are located within geographic areas on the Hanford Site that are referred to as the 100, 200, 300, 400, and 1100 areas. The purpose of this work plan is to document the project scoping process and to outline all remedial investigation/feasibility study (RI/FS) activities, to determine the nature and extent of the threat presented by releases of hazardous substances from the operable unit, and to evaluate proposed remedies for such releases. The goal of the 300-FF-1 remedial investigation (RI) is to provide sufficient information needed to conduct the feasibility study (FS), by determining the nature and extent of the threat to public health and the environment posed by releases of hazardous substances from 300-FF-1, and the performance of specific remedial technologies. 62 refs., 28 figs., 48 tabs

  4. Five-Year Review of CERCLA Response Actions at the Idaho National Laboratory

    Energy Technology Data Exchange (ETDEWEB)

    W. L. Jolley

    2007-02-01

    This report summarizes the documentation submitted in support of the five-year review or remedial actions implemented under the Comprehensive Environmental Response, Compensation, and Liability Act Sitewide at the Idaho National Laboratory. The report also summarizes documentation and inspections conducted at the no-further-action sites. This review covered actions conducted at 9 of the 10 waste area groups at the Idaho National Laboratory, i.e. Waste Area Groups 1, 2, 3, 4, 5, 6, 7, 9, and 10. Waste Area Group 8 was not subject to this review, because it does not fall under the jurisdiction of the U.S. Department of Energy Idaho Operations Office. The review included past site inspections and monitoring data collected in support of the remedial actions. The remedial actions have been completed at Waste Area Groups 2, 4, 5, 6, and 9. Remedial action reports have been completed for Waste Area Groups 2 and 4, and remedial action reports are expected to be completed during 2005 for Waste Area Groups 1, 5, and 9. Remediation is ongoing at Waste Area Groups 3, 7, and 10. Remedial investigations are yet to be completed for Operable Units 3-14, 7-13/14, and 10-08. The review showed that the remedies have been constructed in accordance with the requirements of the Records of Decision and are functioning as designed. Immediate threats have been addressed, and the remedies continue to be protective. Potential short-term threats are being addressed though institutional controls. Soil cover and cap remedies are being maintained properly and inspected in accordance with the appropriate requirements. Soil removal actions and equipment or system removals have successfully achieved remedial action objectives identified in the Records of Decision. The next Sitewide five-year review is scheduled for completion by 2011.

  5. Cost benefit analysis of remediation alternatives for controlling the flux of strontium-90 into the Columbia River

    International Nuclear Information System (INIS)

    Gustafson, F.W.; Todd, M.E.

    1993-09-01

    The release of large volumes of water to waste disposal cribs at the Hanford Site's 100-N Area caused contaminants, principally strontium-90, to be carried toward the Columbia River through the groundwater. Since shutdown of the N Reactor, these releases have been discontinued, although small water flows continue to be discharged to the 1325-N crib. Most of the contamination which is now transported to the river is occurring as a result of the natural groundwater movement. The contaminated groundwater at N Springs flows into the river through seeps and springs along the river's edge. An expedited response action (ERA) has been proposed to eliminate or restrict the flux of strontium-90 into the river. A cost benefit analysis of potential remedial alternatives was completed that recommends the alternative which best meets given selection criteria prescribed by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). The methodology used for evaluation, cost analysis, and alternative recommendation is the engineering evaluation/cost analysis (EE/CA). Complete remediation of the contaminated groundwater beneath 100-N Area was not a principal objective of the analysis. The objective of the cost benefit analysis was to identify a remedial alternative that optimizes the degree of benefit produced for the costs incurred

  6. FY 1995 Remedial Investigation Work Plan for Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Watkins, D.R.; Herbes, S.E.

    1994-12-01

    The purpose of this project is to provide key information needed by decision makers to expedite the process of environmental restoration and to provide the data base required by the Remedial Investigation/Feasibility Study (RI/FS) for Waste Area Grouping (WAG) 2 at Oak Ridge National Laboratory (ORNL). WAG 2 is the major drainage system downgradient of other WAGs that contain significant sources of contamination at ORNL. Field activities to support the remedial investigation for the RI portion include characterization of the nature and extent of contamination in WAG 2 [consisting of White Oak Creek (WOC) and associated tributaries and floodplain, White Oak Lake (WOL), and White Oak Creek Embayment (WOCE)], specifically to support risk-based remediation decisions. The project consists of three phases: Phase 1, initial scoping characterization to determine the need for early action; Phase 2, interim activities during remediation of upslope WAGs to evaluate potential changes in the contamination status of WAG 2 that would necessitate revaluation of the need for early action; and Phase 3, completion of the RI process following remediation of upslope WAGs. Overall RI objectives, consistent with ORNL Environmental Restoration (ER) Program strategic objectives to reduce risks and comply with environmental regulations, are discussed in the WAG 2 Remedial Investigation Plan

  7. 78 FR 76143 - Proposed CERCLA Settlement Relating to the Paul's Tank Cleaning Service Superfund Site...

    Science.gov (United States)

    2013-12-16

    ... Paul's Tank Cleaning Service Superfund Site, Burlington County, New Jersey AGENCY: Environmental.... (``Settling Party''). The Settling Party is a potentially responsible party, pursuant to Section 107(a) of CERCLA, and thus is potentially liable for response costs incurred at or in connection Paul's Tank...

  8. Risk assessment and optimization (ALARA) analysis for the environmental remediation of Brookhaven National Laboratory's hazardous waste management facility

    International Nuclear Information System (INIS)

    Dionne, B.J.; Morris, S.C. III; Baum, J.W.

    1998-01-01

    The Department of Energy's (DOE) Office of Environment, Safety, and Health (EH) sought examples of risk-based approaches to environmental restoration to include in their guidance for DOE nuclear facilities. Extensive measurements of radiological contamination in soil and ground water have been made at Brookhaven National Laboratory's Hazardous Waste Management Facility (HWMF) as part of a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) remediation process. This provided an ideal opportunity for a case study. This report provides a risk assessment and an open-quotes As Low as Reasonably Achievableclose quotes (ALARA) analysis for use at other DOE nuclear facilities as an example of a risk-based decision technique. This document contains the Appendices for the report

  9. Interim Action Proposed Plan for the old radioactive waste burial ground (643-E)

    International Nuclear Information System (INIS)

    McFalls, S.

    1995-12-01

    This Interim Action Proposed (IAPP) is issued by the U.S. Department of Energy (DOE), which functions as the lead agency for SRS remedial activities, and with concurrence by the U.S. Environmental Protection Agency (EPA) and the South Carolina Department of Health and Environmental Control (SCDHEC). The purpose of this IAPP is to describe the preferred interim remedial action for addressing the Old Radioactive Waste Burial Ground (ORWBG) unit located in the Burial Ground Complex (BGC) at the Savannah River Site (SRS) in Aiken, South Carolina. On December 21, 1989, SRS was included on the National Priorities List (NPL). In accordance with Section 120 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), DOE has negotiated a Federal Facility Agreement (FFA, 1993) with EPA and SCDHEC to coordinate remedial activities at SRS. Public participation requirements are listed in Sections 113 and 117 of CERCLA. These requirements include establishment of an Administrative Record File that documents the selection of remedial alternatives and allows for review and comment by the public regarding those alternatives. The SRS Public Involvement Plan (PIP) (DOE, 1994) is designed to facilitate public involvement in the decision-making process for permitting closure, and the selection of remedial alternatives. Section 117(a) of CERCLA, 1980, as amended, requires publication of a notice of any proposed remedial action

  10. Regulator Interface Strategies Implemented at the Y-12 National Security Complex Old Salvage Yard Soils Remediation Project, Oak Ridge, TN - 12162

    Energy Technology Data Exchange (ETDEWEB)

    Albrecht, Linda [Alliant Corporation (United States); Wilkerson, Laura; Skinner, Ralph [US DOE-ORO EM (United States); Birchfield, Joseph W. III [Link Technologies (United States)

    2012-07-01

    The Oak Ridge Y-12 National Security Complex housed an area known as the Old Salvage Yard (OSY) that was approximately 7 acres. The OSY was used as an area for the accumulation, processing and storage of scrap metal and equipment from Y-12 operations extending from 1968 until 2009. Areas in the northern sections of OSY also have been used for the storage of used oils containing solvents and the accumulation and recycling or de-heading and crushing of 55-gal metal drums. Scrap metal operations historically involved the accumulation, sorting, storage, public sale or disposal of scrap metal and equipment. Non-containerised storage of scrap metal was routine until 1995 when scrap metal received at OSY was placed in B-24 and B-25 boxes. Under the American Recovery and Reinvestment Act (ARRA), approximately 26,759 cubic meters of scrap metal and debris were removed and disposed at both on and off-site disposal facilities including the on-site, Oak Ridge Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) landfill in 2010 and 2011. This removal action was performed in accordance with a CERCLA Record of Decision (ROD) and a close working relationship with both the U.S. Environmental Protection Agency (EPA) Region IV and Tennessee Department of Environment and Conservation (TDEC). Due to efficiencies and the excellent cooperative relationship forged with EPA Region IV and TDEC for Y-12 ARRA Cleanup Projects, a surplus of funding was available for additional remediation work that was completed in fiscal year (FY) 2011. The underlying OSY soils were targeted for characterization and potential remediation. To expedite these important activities, the U.S. Department of Energy Oak Ridge Environmental Management partnered with the regulators during detailed planning sessions through a variety of means to quickly and efficiently characterize and pinpoint areas requiring remediation according to previous ROD commitments. Data Quality Objectives (DQOs

  11. Stakeholder value-linked sustainability assessment: Evaluating remedial alternatives for the Portland Harbor Superfund Site, Portland, Oregon, USA.

    Science.gov (United States)

    Apitz, Sabine E; Fitzpatrick, Anne G; McNally, Amanda; Harrison, David; Coughlin, Conor; Edwards, Deborah A

    2018-01-01

    Regulatory decisions on remediation should consider affected communities' needs and values, and how these might be impacted by remedial options; this process requires that diverse stakeholders are able to engage in a transparent consideration of value trade-offs and of the distribution of risks and benefits associated with remedial actions and outcomes. The Stakeholder Values Assessment (SVA) tool was developed to evaluate remedial impacts on environmental quality, economic viability, and social equity in the context of stakeholder values and priorities. Stakeholder values were linked to the pillars of sustainability and also to a range of metrics to evaluate how sediment remediation affects these values. Sediment remedial alternatives proposed by the US Environmental Protection Agency (USEPA) for the Portland Harbor Superfund Site were scored for each metric, based upon data provided in published feasibility study (FS) documents. Metric scores were aggregated to generate scores for each value; these were then aggregated to generate scores for each pillar of sustainability. In parallel, the inferred priorities (in terms of regional remediation, restoration, planning, and development) of diverse stakeholder groups (SGs) were used to evaluate the sensitivity and robustness of the values-based sustainability assessment to diverse SG priorities. This approach, which addresses social indicators of impact and then integrates them with indicators of environmental and economic impacts, goes well beyond the Comprehensive Environmental Response, Compensation and Liability Act's (CERCLA) 9 criteria for evaluating remedial alternatives because it evaluates how remedial alternatives might be ranked in terms of the diverse values and priorities of stakeholders. This approach identified trade-offs and points of potential contention, providing a systematic, semiquantitative, transparent valuation tool that can be used in community engagement. Integr Environ Assess Manag 2018

  12. The Aftermath of Remedial Math: Investigating the Low Rate of Certificate Completion among Remedial Math Students

    Science.gov (United States)

    Bahr, Peter Riley

    2013-01-01

    Nationally, a majority of community college students require remedial assistance with mathematics, but comparatively few students who begin the remedial math sequence ultimately complete it and achieve college-level math competency. The academic outcomes of students who begin the sequence but do not complete it are disproportionately unfavorable:…

  13. 75 FR 8346 - Proposed CERCLA Administrative Settlement; Anderson-Calhoun Mine and Mill Site, Leadpoint, WA

    Science.gov (United States)

    2010-02-24

    ...-Calhoun Mine and Mill Site, Leadpoint, WA AGENCY: Environmental Protection Agency (EPA). ACTION: Notice...-Calhoun Mine and Mill Site in Leadpoint, Washington, with settling party Blue Tee Corporation. The... Anderson-Calhoun Mine and Mill Site in Leadpoint, Washington, EPA Docket No. CERCLA-10-2010-0105 and should...

  14. Risk assessment and optimization (ALARA) analysis for the environmental remediation of Brookhaven National Laboratory`s hazardous waste management facility

    Energy Technology Data Exchange (ETDEWEB)

    Dionne, B.J.; Morris, S. III; Baum, J.W. [and others

    1998-03-01

    The Department of Energy`s (DOE) Office of Environment, Safety, and Health (EH) sought examples of risk-based approaches to environmental restoration to include in their guidance for DOE nuclear facilities. Extensive measurements of radiological contamination in soil and ground water have been made at Brookhaven National Laboratory`s Hazardous Waste Management Facility (HWMF) as part of a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) remediation process. This provided an ideal opportunity for a case study. This report provides a risk assessment and an {open_quotes}As Low as Reasonably Achievable{close_quotes} (ALARA) analysis for use at other DOE nuclear facilities as an example of a risk-based decision technique.

  15. Ammonium citrate as enhancement for electrodialytic soil remediation and investigation of soil solution during the process

    DEFF Research Database (Denmark)

    Dias-Ferreira, Celia; Kirkelund, Gunvor Marie; Ottosen, Lisbeth M.

    2015-01-01

    Seven electrodialytic experiments were conducted using ammonium citrate as enhancing agent to remediate copper and chromium-contaminated soil from a wood-preservation site. The purpose was to investigate the effect of current density (0.2, 1.0 and 1.5 mA cm−2), concentration of enhancing agent (0...... to remediate metal polluted soils at neutral to alkaline pH by choosing a good enhancement solution....

  16. Lab-scale investigation on remediation of diesel-contaminated aquifer using microwave energy.

    Science.gov (United States)

    Falciglia, Pietro P; Maddalena, Riccardo; Mancuso, Giuseppe; Messina, Valeria; Vagliasindi, Federico G A

    2016-02-01

    Aquifer contamination with diesel fuel is a worldwide environmental problem, and related available remediation technologies may not be adequately efficient, especially for the simultaneous treatment of both solid and water phases. In this paper, a lab-scale 2.45 GHz microwave (MW) treatment of an artificially diesel-contaminated aquifer was applied to investigate the effects of operating power (160, 350 and 500 W) and time on temperature profiles and contaminant removal from both solid and water phases. Results suggest that in diesel-contaminated aquifer MW remediation, power significantly influences the final reachable temperature and, consequently, contaminant removal kinetics. A maximum temperature of about 120 °C was reached at 500 W. Observed temperature values depended on the simultaneous irradiation of both aquifer grains and groundwater. In this case, solid phase heating is limited by the maximum temperature that interstitial water can reach before evaporation. A minimal residual diesel concentration of about 100 mg kg(-1) or 100 mg L(-1) was achieved by applying a power of 500 W for a time of 60 min for the solid or water phase, respectively. Measured residual TPH fractions showed that MW heating resulted in preferential effects of the removal of different TPH molecular weight fractions and that the evaporation-stripping phenomena plays a major role in final contaminant removal processes. The power low kinetic equation shows an excellent fit (r(2) > 0.993) with the solid phase residual concentration observed for all the powers investigated. A maximum diesel removal of 88 or 80% was observed for the MW treatment of the solid or water phase, respectively, highlighting the possibility to successfully and simultaneously remediate both the aquifer phases. Consequently, MW, compared to other biological or chemical-physical treatments, appears to be a better choice for the fast remediation of diesel-contaminated aquifers. Copyright © 2015 Elsevier

  17. 77 FR 58989 - Proposed CERCLA Administrative Cost Recovery Settlement for the Buckbee-Mears Co. Superfund Site...

    Science.gov (United States)

    2012-09-25

    ... paid $150,000 attributable to the costs of marketing and selling the Properties; (b) The Bank will pay... ENVIRONMENTAL PROTECTION AGENCY [FRL-9720-7] Proposed CERCLA Administrative Cost Recovery... costs concerning the Buckbee-Mears Co. Superfund Site located in Cortland, Cortland County, New York...

  18. Remedial investigation/feasibility study for the David Witherspoon, Inc., 901 Site, Knoxville, Tennessee: Volume 2, Appendixes

    International Nuclear Information System (INIS)

    1996-10-01

    This document contains the appendixes for the remedial investigation and feasibility study for the David Witherspoon, Inc., 901 site in Knoxville, Tennessee. The following topics are covered in the appendixes: (A) David Witherspoon, Inc., 901 Site Historical Data, (B) Fieldwork Plans for the David Witherspoon, Inc., 901 Site, (C) Risk Assessment, (D) Remediation Technology Discussion, (E) Engineering Support Documentation, (F) Applicable or Relevant and Appropriate Requirements, and (G) Cost Estimate Documentation

  19. Remedial investigation/feasibility study for the David Witherspoon, Inc., 901 Site, Knoxville, Tennessee: Volume 2, Appendixes

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-10-01

    This document contains the appendixes for the remedial investigation and feasibility study for the David Witherspoon, Inc., 901 site in Knoxville, Tennessee. The following topics are covered in the appendixes: (A) David Witherspoon, Inc., 901 Site Historical Data, (B) Fieldwork Plans for the David Witherspoon, Inc., 901 Site, (C) Risk Assessment, (D) Remediation Technology Discussion, (E) Engineering Support Documentation, (F) Applicable or Relevant and Appropriate Requirements, and (G) Cost Estimate Documentation.

  20. Savannah River Site plan for performing maintenance in Federal Facility Agreement areas (O and M Plan)

    International Nuclear Information System (INIS)

    Morris, D.R.

    1996-01-01

    The Savannah River Site was placed on the National Priority List (NPL) in December 1989 and became subject to comprehensive remediation in accordance with CERCLA. The FFA, effective August 16, 1993, establishes the requirements for Site investigation and remediation of releases and potential releases of hazardous substances, and interim status corrective action for releases of hazardous wastes or hazardous constituents. It was determined that further direction was needed for the Operating Departments regarding operation and maintenance activities within those areas listed in the FFA. The Plan for Performing Maintenance (O and M Plan) provides this additional direction. Section 4.0 addresses the operation and maintenance activities necessary for continued operation of the facilities in areas identified as RCRA/CERCLA Units or Site Evaluation Areas. Certain types of the O and M activity could be construed as a remedial or removal action. The intent of this Plan is to provide direction for conducting operation and maintenance activities that are not intended to be remedial or removal actions. The Plan identifies the locations of the units and areas, defines intrusive O and M activities, classifies the intrusive activity as either minor or major, and identifies the requirements, approvals, and documentation necessary to perform the activity in a manner that is protective of human health and the environment; and minimizes any potential impact to any future removal and remedial actions

  1. 78 FR 5801 - Operating Industries, Inc. Superfund Site, Monterey Park, CA; Notice of Proposed CERCLA...

    Science.gov (United States)

    2013-01-28

    ... Metals Corporation, R.R. Kellogg, Inc., Ralphs Grocery Company, RCG Electronics Corp., dba Washington... (CERCLA), 42 U.S.C. 9622(i) and Section 7003(d) of the Resource Conservation and Recovery Act, as amended (RCRA), 42 U.S.C. 6973, notice is hereby given of a proposed administrative settlement with 47 de...

  2. Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study

    International Nuclear Information System (INIS)

    1988-04-01

    In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document

  3. Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study

    Energy Technology Data Exchange (ETDEWEB)

    1988-04-01

    In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document.

  4. ICD Complex Operations and Maintenance Plan

    Energy Technology Data Exchange (ETDEWEB)

    Gibson, P. L.

    2007-06-25

    This Operations and Maintenance (O&M) Plan describes how the Idaho National Laboratory (INL) conducts operations, winterization, and startup of the Idaho CERCLA Disposal Facility (ICDF) Complex. The ICDF Complex is the centralized INL facility responsible for the receipt, storage, treatment (as necessary), and disposal of INL Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) remediation waste.

  5. Record of Decision for the Ford Building Waste Unit (643-11G) Operable Unit; FINAL

    International Nuclear Information System (INIS)

    Fraley, S.

    2002-01-01

    This decision document presents the selected remedial for the Ford Building Waste Unit (FBWU), in Aiken, South Carolina, which was chosen in accordance with CERCLA, as amended by SARA, and, to the extent practical, the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). This decision is based on the Administrative Record File for this specific RCRA/CERCLA site

  6. Petroleum hydrocarbon contaminated sites: a review of investigation and remediation regulations and processes

    Energy Technology Data Exchange (ETDEWEB)

    Epelbaum, Michel; Claudio, Jair R [Bureau Veritas do Brasil Sociedade Classificadora e Certificadora Ltda., Sao Paulo, SP (Brazil)

    1994-12-31

    This paper discusses alternatives on remediation of petroleum hydrocarbon contaminated sites which include groundwater remediation techniques and soil remediation techniques. Finally, the work points out some trends of sites remediation in Brazil and abroad. 6 refs., 1 fig., 7 tabs.

  7. Petroleum hydrocarbon contaminated sites: a review of investigation and remediation regulations and processes

    Energy Technology Data Exchange (ETDEWEB)

    Epelbaum, Michel; Claudio, Jair R. [Bureau Veritas do Brasil Sociedade Classificadora e Certificadora Ltda., Sao Paulo, SP (Brazil)

    1993-12-31

    This paper discusses alternatives on remediation of petroleum hydrocarbon contaminated sites which include groundwater remediation techniques and soil remediation techniques. Finally, the work points out some trends of sites remediation in Brazil and abroad. 6 refs., 1 fig., 7 tabs.

  8. Risk assessment and optimization (ALARA) analysis for the environmental remediation of Brookhaven National Laboratory`s hazardous waste management facility

    Energy Technology Data Exchange (ETDEWEB)

    Dionne, B.J.; Morris, S.C. III; Baum, J.W. [and others

    1998-01-01

    The Department of Energy`s (DOE) Office of Environment, Safety, and Health (EH) sought examples of risk-based approaches to environmental restoration to include in their guidance for DOE nuclear facilities. Extensive measurements of radiological contamination in soil and ground water have been made at Brookhaven National Laboratory`s Hazardous Waste Management Facility (HWMF) as part of a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) remediation process. This provided an ideal opportunity for a case study. This report provides a risk assessment and an {open_quotes}As Low as Reasonably Achievable{close_quotes} (ALARA) analysis for use at other DOE nuclear facilities as an example of a risk-based decision technique. This document contains the Appendices for the report.

  9. Being a potentially responsible party

    International Nuclear Information System (INIS)

    Ronan, J.T.

    1989-01-01

    This paper reports on CERCLA II- ability for the unlucky potentially responsible parties (PRPs) which is a Draconian form of strict, joint and several liability with limited statutory defenses that in most cases are impossible to establish. CERCLA vigorously employs these legal concepts, stretching a PRP's financial exposure to the limits necessary to meet the enormous financial costs of remediation

  10. Field Sampling and Analysis Plan for the Remedial Investigation of Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1992-10-01

    This report provides responses to US Environmental Protection Agency Region IV EPA-M and Tennessee Department of Environment and Conservation Oversite Division (TDEC-O) comments on report ORNL/ER-58, Field Sampling and Analysis Plan for the Remedial Investigation of Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Waste Area Grouping (WAG) 2 consists of the White Oak Creek (WOC) drainage system downgradient of the major ORNL WAGs in the WOC watershed. A strategy for the remedial investigation (RI) of WAG2 was developed in report ES/ER-14 ampersand Dl, Remedial Investigation Plan for Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. This strategy takes full advantage of WAG2's role as an integrator of contaminant releases from the ORNL WAGs in the WOC watershed, and takes full advantage of WAG2's role as a conduit for contaminants from the ORNL site to the Clinch River. The strategy calls for a multimedia environmental monitoring and characterization program to be conducted in WAG2 while upgradient contaminant sources are being remediated. This monitoring and characterization program will (1) identify and quantify contaminant fluxes, (2) identify pathways of greatest concern for human health and environmental risk, (3) improve conceptual models of contaminant movement, (4) support the evaluation of remedial alternatives, (5) support efforts to prioritize sites for remediation, (6) document the reduction in contaminant fluxes following remediation, and (7) support the eventual remediation of WAG2. Following this strategy, WAG2 has been termed an ''integrator WAG,'' and efforts in WAG2 over the short term are directed toward supporting efforts to remediate the contaminant ''source WAGS'' at ORNL

  11. Implementation plan for liquid low-level radioactive waste tank systems at Oak Ridge National Laboratory under the Federal Facility Agreement, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-06-01

    This document is an annual revision of the plans and schedules for implementing the Federal Facility Agreement (FFA) compliance program, originally submitted in ES/ER-17 ampersand D1, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste Tank Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee. This document summarizes the progress that has been made to date in implementing the plans and schedules for meeting the FFA commitments for the Liquid Low-Level Waste (LLLW) System at Oak Ridge National Laboratory (ORNL). Information presented in this document provides a comprehensive summary to facilitate understanding of the FFA compliance program for LLLW tank systems and to present plans and schedules associated with remediation, through the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process, of LLLW tank systems that have been removed from service. ORNL has a comprehensive program underway to upgrade the LLLW system as necessary to meet the FFA requirements. The tank systems that are removed from service are being investigated and remediated through the CERCLA process. Waste and risk characterizations have been submitted. Additional data will be prepared and submitted to EPA/TDEC as tanks are taken out of service and as required by the remedial investigation/feasibility study (RI/FS) process. Chapter 1 provides general background information and philosophies that lead to the plans and schedules that appear in Chapters 2 through 5

  12. Reporting continuous releases of hazardous and extremely hazardous substances under CERCLA and EPCRA

    International Nuclear Information System (INIS)

    1995-01-01

    This guidance is designed to provide basic instruction to US DOE and DOE operations contractor personnel on how to characterize CERCLA and EPCRA hazardous substance releases as continuous and how to prepare and deliver continuousreleasee reports to Federal, State, and local authorities. DOE staff should use this guidance as an overview of the continuous release requirements, a quick ready reference guide for specific topics concerning continuous releases and a step-by-step guide for the process of identifying and reporting continuous releases

  13. Regulatory and management requirements for investigation-derived waste generated during environmental investigations and cleanups

    International Nuclear Information System (INIS)

    Clary, M.B.

    1994-01-01

    Environmental cleanup efforts often result in the generation of waste materials, such as soil samples, drill cuttings, decontamination water, drilling muds, personal protective equipment, and disposable sampling equipment. The management of associated with site characterization and remediation issues is a complicated issue at many CERCLA/RCRA facilities throughout the country, primarily because of the federal hazardous waste regulations. The hazardous waste regulations were intended to apply to the active generation of hazardous waste at industrial facilities and do not often make sense when applied to sites con by poor disposal practices of the past. In order to manage investigation derived waste in a more rational, logical manner, EPA issued guidance on the management of investigation-derived waste (IDW) at Superfund sites in January, 1992. The basic intent of the EPA guidance is to provide Superfund Site Managers with options for handling, managing, and disposing of IDW. The second part of this paper provides a detailed analysis of current IDW practices at various Department of Energy (DOE) facilities and Superfund sites across the nation. Some sites, particularly the DOE facilities, with more complicated on-going cleanup efforts have developed site-specific written procedures for managing IDW, often incorporating risk assessment. In come cases, these site-specific policies are going farther than the current EPA and Colorado policies in terms of conservatively managing IDW

  14. Addendum to the remedial investigation report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant Oak Ridge, Tennessee. Volume 1: Main text

    International Nuclear Information System (INIS)

    1995-04-01

    This addendum to the Remedial Investigation (RI) Report on Bear Creek Valley Operable Unit (OU) 2 at the Oak Ridge Y-12 Plant was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting the results of a site characterization for public review. This addendum is a supplement to a document that was previously issued in January 1995 and that provided the Environmental Restoration Program with information about the results of the 1993 investigation performed at OU 2. The January 1995 D2 version of the RI Report on Bear Creek Valley OU 2 included information on risk assessments that have evaluated impacts to human health and the environment. Information provided in the document formed the basis for the development of the Feasibility Study Report. This addendum includes revisions to four chapters of information that were a part of the document issued in January 1995. Specifically, it includes revisions to Chaps. 2, 3, 4, and 9. Volume 1 of this document is not being reissued in its entirety as a D3 version because only the four chapters just mentioned have been affected by requested changes. Note also that Volume 2 of this RI Report on Bear Creek Valley OU 2 is not being reissued in conjunction with Volume 1 of this document because there have been no changes requested or made to the previously issued version of Volume 2 of this document.

  15. WAG 2 remedial investigation and site investigation site-specific work plan/health and safety checklist for the soil and sediment task

    International Nuclear Information System (INIS)

    Holt, V.L.; Burgoa, B.B.

    1993-12-01

    This document is a site-specific work plan/health and safety checklist (WP/HSC) for a task of the Waste Area Grouping 2 Remedial Investigation and Site Investigation (WAG 2 RI ampersand SI). Title 29 CFR Part 1910.120 requires that a health and safety program plan that includes site- and task-specific information be completed to ensure conformance with health- and safety-related requirements. To meet this requirement, the health and safety program plan for each WAG 2 RI ampersand SI field task must include (1) the general health and safety program plan for all WAG 2 RI ampersand SI field activities and (2) a WP/HSC for that particular field task. These two components, along with all applicable referenced procedures, must be kept together at the work site and distributed to field personnel as required. The general health and safety program plan is the Health and Safety Plan for the Remedial Investigation and Site Investigation of Waste Area Grouping 2 at the Oak Ridge National Laboratory, Oak Ridge, Tennessee (ORNL/ER-169). The WP/HSCs are being issued as supplements to ORNL/ER-169

  16. Ammonium citrate as enhancement for electrodialytic soil remediation and investigation of soil solution during the process.

    Science.gov (United States)

    Dias-Ferreira, Celia; Kirkelund, Gunvor M; Ottosen, Lisbeth M

    2015-01-01

    Seven electrodialytic experiments were conducted using ammonium citrate as enhancing agent to remediate copper and chromium-contaminated soil from a wood-preservation site. The purpose was to investigate the effect of current density (0.2, 1.0 and 1.5 mA cm(-2)), concentration of enhancing agent (0.25, 0.5 and 1.0 M) and remediation times (21, 42 and 117 d) for the removal of Cu and Cr from a calcareous soil. To gain insight on metal behavior, soil solution was periodically collected using suction cups. It was seen that current densities higher than 1.0 mA cm(-2) did not increase removal and thus using too high current densities can be a waste of energy. Desorption rate is important and both remediation time and ammonium citrate concentration are relevant parameters. It was possible to collect soil solution samples following an adaptation of the experimental set-up to ensure continuous supply of ammonium citrate to the soil in order to keep it saturated during the remediation. Monitoring soil solution gives valuable information on the evolution of remediation and helps deciding when the soil is remediated. Final concentrations in the soil ranged from 220 to 360 mg Cu kg(-1) (removals: 78-86%) and 440-590 mg Cr kg(-1) (removals: 35-51%), being within the 500 mg kg(-1) limit for a clean soil only for Cu. While further optimization is still required for Cr, the removal percentages are the highest achieved so far, for a real Cu and Cr-contaminated, calcareous soil. The results highlight EDR potential to remediate metal polluted soils at neutral to alkaline pH by choosing a good enhancement solution. Copyright © 2014 Elsevier Ltd. All rights reserved.

  17. Field Investigation Plan for 1301-N and 1325-N Facilities Sampling to Support Remedial Design

    International Nuclear Information System (INIS)

    Weiss, S. G.

    1998-01-01

    This field investigation plan (FIP) provides for the sampling and analysis activities supporting the remedial design planning for the planned removal action for the 1301-N and 1325-N Liquid Waste Disposal Facilities (LWDFs), which are treatment, storage,and disposal (TSD) units (cribs/trenches). The planned removal action involves excavation, transportation, and disposal of contaminated material at the Environmental Restoration Disposal Facility (ERDF).An engineering study (BHI 1997) was performed to develop and evaluate various options that are predominantly influenced by the volume of high- and low-activity contaminated soil requiring removal. The study recommended that additional sampling be performed to supplement historical data for use in the remedial design

  18. An overview of the hazardous waste remedial actions program: hazardous and mixed waste activities for the U.S. Departments of energy and defense

    International Nuclear Information System (INIS)

    Craig, Robert B.; Rothermich, Nancy E.

    1991-01-01

    In May 1987 all mixed waste generated at the U.S. Department of Energy (DOE) facilities became jointly regulated by the U.S. Environmental Protection Agency (EPA) and DOE. The Department of Defense (DOD) generates hazardous wastes and is also regulated by the EPA. To maintain or attain compliance, both DOE and DOD have initiated compliance activities on all hazardous and mixed waste streams. This compliance includes the development of innovative technologies and processes to avoid the generation of hazardous and mixed wastes, development of technologies to treat the process wastes that are unavoidably generated, development of technologies to restore the environment where wastes have been released to the environment, the cleanup of asbestos and the monitoring of radon in federal facilities, the completion of remedial investigation/feasibility studies, and development of the data systems that are necessary to compile this information. This paper will describe each of these activities as they relate to compliance with the Resource Conservation and Recovery Act and/or CERCLA and their implementing regulations

  19. FY 1995 remedial investigation work plan for Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Watkins, D.R.; Herbes, S.E.

    1994-09-01

    Field activities to support the remedial investigation (RI) of Waste Area Grouping (WAG) 2 at Oak Ridge National Laboratory (ORNL) include characterization of the nature and extent of contamination in WAG 2, specifically to support risk-based remediation decisions. WAG 2 is the major drainage system downgradient of other WAGs containing significant sources of contamination at ORNL. The RI of WAG 2 is developed in three phases: Phase 1, initial scoping characterization to determine the need for early action; Phase 2, interim activities during remediation of upgradient WAGs to evaluate potential changes in the contamination status of WAG 2 that would necessitate reevaluation of the need for early action; and Phase 3, completion of the RI process following remediation of upslope WAGs. Specifically, Phase 2 activities are required to track key areas to determine if changes have occurred in WAG 2 that would require (1) interim remedial action to protect human health and the environment or (2) changes in remedial action plans and schedules for WAG2 because of changing contaminant release patterns in upslope WAGs or because of the effects of interim remedial or removal actions in other WAGs. This report defines activities to be conducted in FY 1995 for completion of the Phase 1 RI and initiation of limited Phase 2 field work

  20. Fiscal year 1991 100 Areas CERCLA ecological investigations

    International Nuclear Information System (INIS)

    Sackschewsky, M.R.; Landeen, D.S.

    1992-04-01

    This report discusses the status of the ecological investigations conducted by Westinghouse Hanford Company during Fiscal Year 1991. These ecological investigations provide a basic description of the flora and fauna that inhabit the operable units, emphasizing species that have been given special status under existing state and/or federal laws. The 1991 Westinghouse Hanford Company field investigations have concentrated on the following: (1) bird surveys, (2) mammal and insect surveys, (3) vegetation surveys, and (4) vegetation sampling. Work being conducted as part of the vegetation surveys includes a biological assessment of threatened and endangered plants, which is being prepared as a separate document. Similar ecological investigations will be conducted at 100- N, K, and F operable units in 1992

  1. Reporting releases of hazardous substances under CERCLA and EPCRA

    International Nuclear Information System (INIS)

    Dailey, R.

    1990-04-01

    Several federal environmental laws requires that ''release of hazardous substances to the environment'' above certain threshold amounts -- Reportable Quantities or RQs -- be reported. Current and proposed regulations under these statutes are unclear and make full compliance difficult. Nevertheless, failure to comply could result in civil or criminal penalties. In response to questions raised by several DOE Field Elements, this Information Brief is part of a series that will provide updated information on this and other CERCLA issues. The Environmental Guidance Division (EH-231) has responded to those questions relating the reporting of releases for which EPA has a clearly articulated position. EPA's position on other questions raised by Field Elements has been equivocal; DOE is working with EPA to resolve these outstanding issues. Additional information briefs on reporting releases will be issued as a clear position is defined

  2. Phase I remedial investigation report of Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Miller, D.E.

    1995-07-01

    This report presents the activities and findings of the first phase of a three-phase remedial investigation (RI) of Waste Area Grouping (WAG) 2 at Oak Ridge National Laboratory (ORNL) in Oak Ridge, Tennessee, and updates the scope and strategy for WAG-2-related efforts. WAG 2 contains White Oak Creek (WOC) and its tributaries downstream of the ORNL main plant area, White Oak Lake, White Oak Creek Embayment on the Clinch River, and the associated floodplain and subsurface environment. Water, sediment, soil, and biota in WAG 2 are contaminated and continue to receive contaminants from upgradient WAGs. This report includes field activities completed through October 1992. The remediation of WAG 2 is scheduled to follow the cessation of contaminant input from hydrologically upgradient WAGs. While upgradient areas are being remediated, the strategy for WAG 2 is to conduct a long-term monitoring and investigation program that takes full advantage of WAG 2's role as an integrator of contaminant fluxes from other ORNL WAGs and focuses on four key goals: (1) Implement, in concert with other programs, long-term, multimedia environmental monitoring and tracking of contaminants leaving other WAGs, entering WAG 2, and being transported off-site. (2) Provide a conceptual framework to integrate and develop information at the watershed-level for pathways and processes that are key to contaminant movement, and so support remedial efforts at ORNL. (3) Provide periodic updates of estimates of potential risk (both human health and ecological) associated with contaminants accumulating in and moving through WAG 2 to off-site areas. (4) Support the ORNL Environmental Restoration Program efforts to prioritize, remediate, and verify remedial effectiveness for contaminated sites at ORNL, through long-term monitoring and continually updated risk assessments

  3. Investigation of Remedial Education Course Scores as a Predictor of Introduction-Level Course Performances

    Science.gov (United States)

    Ulmer, Ward; Means, Darris R.; Cawthon, Tony W.; Kristensen, Sheryl A.

    2016-01-01

    This study explores whether performance in remedial English and remedial math is a predictor of success in a college-level introduction English or college-level math class; and whether demographic variables increase the likelihood of remedial English and remedial math as a predictor of success in a college-level introduction English or…

  4. Mercury issues related to NPDES and the CERCLA watershed project at the Oak Ridge Y-12 Plant

    International Nuclear Information System (INIS)

    1996-11-01

    The purpose of this document is to present the current understanding of the issues and options surrounding compliance with the current National Pollutant Discharge Elimination System (NPDES) permit conditions. This is a complicated issue that directly impacts, and will be directly impacted by, ongoing CERCLA activities in Lower East Fork Poplar Creek and the Clinch River/Poplar Creek. It may be necessary to reconstitute the whole and combine actions and decisions regarding the entire creek (origin to confluence with the Clinch River) to develop a viable long-term strategy that meets regulatory goals and requirements as well as those of DOE's 10-Year Plan and the new watershed management permitting approach. This document presents background information on the Reduction of Mercury in Plant Effluents (RMPE) and NPDES programs insofar as it is needed to understand the issues and options. A tremendous amount of data has been collected to support the NPDES/RMPE and CERCLA programs. These data are not presented, although they may be referenced and conclusions based on them may be presented, as necessary, to support discussion of the options

  5. The role of risk assessment in project planning at the Weldon Spring Quarry, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    Haroun, L.A.; Peterson, J.M.

    1989-01-01

    This paper presents the methodology used to prepare a baseline risk evaluation of the bulk wastes at the quarry. The DOE is proposing to remove these bulk wastes and transport them approximately 6.4 km (4 mi) to a temporary storage facility at the chemical plant area of the Weldon Spring site. The DOE has responsibility for cleanup activities at the Weldon Spring site under its Surplus Facilities Management Program (SFMP). A baseline risk evaluation is an evaluation of the potential impacts on human health and the environment that may result from exposure to releases of contaminants from a site in the absence of site remediation. This evaluation is a key component of the remedial investigation (RI) process, as identified in guidance from the US Environmental Protection Agency (EPA) that addresses sites subject to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980, as amended by the Superfund Amendments and Reauthorization Act of 1986. Response actions at the Weldon Spring quarry are subject to CERCLA requirements because the quarry is listed on the EPA's National Priorities List

  6. Investigating biochar as a tool for environmental remediation

    Science.gov (United States)

    Biochar is being proposed as a cost-effective, carbon negative soil amendment for environmental remediation. Research has demonstrated the efficacy of biochar to sorb heavy metals and agricultural chemicals from contaminated soils, thus effectively reducing the potential for met...

  7. Wearable Cameras Are Useful Tools to Investigate and Remediate Autobiographical Memory Impairment: A Systematic PRISMA Review.

    Science.gov (United States)

    Allé, Mélissa C; Manning, Liliann; Potheegadoo, Jevita; Coutelle, Romain; Danion, Jean-Marie; Berna, Fabrice

    2017-03-01

    Autobiographical memory, central in human cognition and every day functioning, enables past experienced events to be remembered. A variety of disorders affecting autobiographical memory are characterized by the difficulty of retrieving specific detailed memories of past personal events. Owing to the impact of autobiographical memory impairment on patients' daily life, it is necessary to better understand these deficits and develop relevant methods to improve autobiographical memory. The primary objective of the present systematic PRISMA review was to give an overview of the first empirical evidence of the potential of wearable cameras in autobiographical memory investigation in remediating autobiographical memory impairments. The peer-reviewed literature published since 2004 on the usefulness of wearable cameras in research protocols was explored in 3 databases (PUBMED, PsycINFO, and Google Scholar). Twenty-eight published studies that used a protocol involving wearable camera, either to explore wearable camera functioning and impact on daily life, or to investigate autobiographical memory processing or remediate autobiographical memory impairment, were included. This review analyzed the potential of wearable cameras for 1) investigating autobiographical memory processes in healthy volunteers without memory impairment and in clinical populations, and 2) remediating autobiographical memory in patients with various kinds of memory disorder. Mechanisms to account for the efficacy of wearable cameras are also discussed. The review concludes by discussing certain limitations inherent to using cameras, and new research perspectives. Finally, ethical issues raised by this new technology are considered.

  8. Remedial Investigation/Feasibility Study Work Plan for the 200-UP-1 Groundwater Operable Unit, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1994-01-01

    This work plan identifies the objectives, tasks, and schedule for conducting a Remedial Investigation/Feasibility Study for the 200-UP-1 Groundwater Operable Unit in the southern portion of the 200 West Groundwater Aggregate Area of the Hanford Site. The 200-UP-1 Groundwater Operable Unit addresses contamination identified in the aquifer soils and groundwater within its boundary, as determined in the 200 West Groundwater Aggregate Area Management Study Report (AAMSR) (DOE/RL 1992b). The objectives of this work plan are to develop a program to investigate groundwater contaminants in the southern portion of the 200 West Groundwater Aggregate Area that were designated for Limited Field Investigations (LFIs) and to implement Interim Remedial Measures (IRMs) recommended in the 200 West Groundwater AAMSR. The purpose of an LFI is to evaluate high priority groundwater contaminants where existing data are insufficient to determine whether an IRM is warranted and collect sufficient data to justify and implement an IRM, if needed. A Qualitative Risk Assessment (QRA) will be performed as part of the LFI. The purpose of an IRM is to develop and implement activities, such as contaminant source removal and groundwater treatment, that will ameliorate some of the more severe potential risks of groundwater contaminants prior to the RI and baseline Risk Assessment (RA) to be conducted under the Final Remedy Selection (FRS) at a later date. This work plan addresses needs of a Treatability Study to support the design and implementation of an interim remedial action for the Uranium- 99 T c -Nitrate multi-contaminant IRM plume identified beneath U Plant

  9. Proposed plan for the Tank 105-C Hazardous Waste Management Facility. Revision 1

    International Nuclear Information System (INIS)

    Miles, W.C. Jr.

    1994-01-01

    This Proposed Plan was developed to describe the remedial action selected at the Tank 105-C Hazardous Waste Management Facility (HWMF) source-specific unit within the C-Area Fundamental Study Area (FSA) at the Savannah River Site (SRS) and to fulfill Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements. This 8,400 gallon capacity tank was certified and accepted closed according to a closure plan approved by the state of South Carolina under the Resource Conservation and Recovery Act (RCRA) authority in January 1991. As a result of the closure, previously performed under RCRA, the unit poses no current or potential threat to human health or the environment. Accordingly, no further remedial action is necessary under CERCLA

  10. Targeted Health Assessment for Wastes Contained at the Niagara Falls Storage Site to Guide Planning for Remedial Action Alternatives - 13428

    Energy Technology Data Exchange (ETDEWEB)

    Busse, John; Keil, Karen; Staten, Jane; Miller, Neil; Barker, Michelle [U.S. Army Corps of Engineers, Buffalo District, 1776 Niagara Street, Buffalo, NY (United States); MacDonell, Margaret; Peterson, John; Chang, Young-Soo; Durham, Lisa [Argonne National Laboratory, Environmental Science Division, 9700 S. Cass Ave., Argonne, IL 60439 (United States)

    2013-07-01

    The U.S. Army Corps of Engineers (USACE) is evaluating potential remedial alternatives at the 191-acre Niagara Falls Storage Site (NFSS) in Lewiston, New York, under the Formerly Utilized Sites Remedial Action Program (FUSRAP). The Manhattan Engineer District (MED) and Atomic Energy Commission (AEC) brought radioactive wastes to the site during the 1940's and 1950's, and the U.S. Department of Energy (US DOE) consolidated these wastes into a 10-acre interim waste containment structure (IWCS) in the southwest portion of the site during the 1980's. The USACE is evaluating remedial alternatives for radioactive waste contained within the IWCS at the NFSS under the Feasibility Study phase of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process. A preliminary evaluation of the IWCS has been conducted to assess potential airborne releases associated with uncovered wastes, particularly during waste excavation, as well as direct exposures to uncovered wastes. Key technical issues for this assessment include: (1) limitations in waste characterization data; (2) representative receptors and exposure routes; (3) estimates of contaminant emissions at an early stage of the evaluation process; (4) consideration of candidate meteorological data and air dispersion modeling approaches; and (5) estimates of health effects from potential exposures to both radionuclides and chemicals that account for recent updates of exposure and toxicity factors. Results of this preliminary health risk assessment indicate if the wastes were uncovered and someone stayed at the IWCS for a number of days to weeks, substantial doses and serious health effects could be incurred. Current controls prevent such exposures, and the controls that would be applied to protect onsite workers during remedial action at the IWCS would also effectively protect the public nearby. This evaluation provides framing context for the upcoming development and detailed

  11. Management and Data Management Plan for Remedial Investigation at Fort George G. Meade Landfill and Preliminary Assessment/Site Investigation at the Former Gaithersburg NIKE Control and Launch Areas

    National Research Council Canada - National Science Library

    Edwards, D

    1989-01-01

    Work assignments under this contract will include a Preliminary Assessment/Site Investigation at the former Gaithersburg NIKE Control and Launch Areas and a Remedial Investigation at the Fort Meade...

  12. Records Management in the Formerly Used Sites Remedial Action Program (FUSRAP)

    International Nuclear Information System (INIS)

    Morekas, G.N.; Pape, M.B.

    2006-01-01

    The U.S. Army Corps of Engineers' (USACE's) performance of site investigation and remediation under the Formerly Used Sites Remedial Action Program (FUSRAP) requires the use of a records management system in order to effectively capture and manage data, document the decision making process, and allow communication of project information to regulators, congress, and the public. The USACE faces many challenges in managing the vast amount of data, correspondence, and reports generated under this program, including: management of data and reports in a variety of paper, electronic, and microfilm formats; incorporation of records generated by the Department of Energy (DOE) prior to 1997; ensuring smooth flow of information among numerous internal Project Managers and regulators; and facilitating public access to information through the development of CERCLA Administrative Records and response to Freedom of Information Act (FOIA) requests. In 2004-2005, the USACE Buffalo District contracted with Dynamac Corporation to adapt the records management system developed for the Formerly Used Defense Sites (FUDS) Program to the records for the Luckey and Painesville FUSRAP sites. The system, known as the FUDS Information Improvement Plan (FIIP), was jointly developed by the USACE Hazardous, Toxic, and Radioactive Waste Center of Expertise (HTRW-CX), USACE Rock Island District, and several FUDS contractors (including Dynamac Corporation) in 2003. The primary components of the FIIP which address the challenges faced by the FUSRAP Program include: the development of a standardized document organization system; the standardization of electronic conversion processes; the standardization of file naming conventions; and the development of an automated data capture system to speed the process and reduce errors in indexing. The document organization system allows for the assignment of each individual document to one of approximately 150 categories. The categories are based upon a

  13. EPA/Navy CERCLA Remedial Action Technology Guide

    Science.gov (United States)

    1993-11-01

    Vendor (MM BTU/Hr) Site, Location (tons) Waste Type Rotary Kiln 35 Lauder Salvage, Beardstown, IL 8,500 Metal scrap salvage Weston Paxton Ave., Chicago...nology from the perspective of the Comprehensive Environ- ° Additional time and money may be required to determine the mental Response, Compensation

  14. Implementation plan for liquid low-level radioactive waste tank systems for fiscal year 1995 at Oak Ridge National Laboratory under the Federal Facility Agreement, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-06-01

    This document is the third annual revision of the plans and schedules for implementing the Federal Facility Agreement (FFA) compliance program, originally submitted in 1992 as ES/ER-17 ampersand D1, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste Tank Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee. This document summarizes the progress that has been made to date in implementing the plans and schedules for meeting the FFA commitments for the Liquid Low-Level Waste (LLLW) System at Oak Ridge National Laboratory (ORNL). Information presented in this document provides a comprehensive summary to facilitate understanding of the FFA compliance program for LLLW tank systems and to present plans and schedules associated with remediation, through the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process, of LLLW tank systems that have been removed from service. ORNL has a comprehensive program underway to upgrade the LLLW System as necessary to meet the FFA requirements. The tank systems that are removed from service are being investigated and remediated through the CERCLA process. Waste and risk characterizations have been submitted. Additional data will be prepared and submitted to EPA/TDEC as tanks are taken out of service and as required by the remedial investigation/feasibility study (RI/FS) process. Chapter 1 provides general background information and philosophies that led to the plans and schedules that appear in Chaps. 2 through 5

  15. 78 FR 48868 - Proposed Cercla Administrative Cost Recovery Settlement; MassDOT, MassDOT Route 1 Right-of-Way...

    Science.gov (United States)

    2013-08-12

    ... Settlement; MassDOT, MassDOT Route 1 Right-of-Way Site, Chelsea, MA AGENCY: Environmental Protection Agency... (``CERCLA''), 42 U.S.C. 9622(h)(1), concerning the MassDOT Route 1 Right-of-Way Site in Chelsea... (OES04-3), Boston, MA 02109-3912 (Telephone No. 617-918-1886) and should refer to: In re: MassDOT Route 1...

  16. Thermal treatment and competing technologies for remediation of MGP (manufactured gas plant) sites

    International Nuclear Information System (INIS)

    McGowan, T.F.; Greer, B.A.; Lawless, M.

    1995-01-01

    More than 1,500 MGP (manufactured gas plant) sites exist throughout the US. Many are contaminated with coal tar from coal-fueled gas works which produced ''town gas'' from the mid-1800s through the 1950s. Virtually all old US cities have such sites. Most are in downtown areas, as they were installed for central distribution of manufactured gas. While a few sites are CERCLA/Superfund, most are not. However, the contaminants and methods used for remediation are similar to those used for Superfund cleanups of coal tar contamination from wood-treating and coke oven facilities. Clean-up of sites is triggered by property transfers and re-development as well as releases to the environment--in particular, via ground water migration. This paper describes recent experience with high capacity/low cost thermal desorption process for this waste. It also reviews competing non-thermal technology, such as bio-treatment, capping, recycling, and dig and haul. Cost data are provided for all technologies, and a case study for thermal treatment is also presented

  17. 200 Areas Remedial Investigation/Feasibility Study Implementation Plan - Environmental Restoration Program

    International Nuclear Information System (INIS)

    Knepp, A. J.

    1999-01-01

    The 200 Areas Remedial Investigation/Feasibility Study Implementation Plan - Environmental Restoration Program (Implementation Plan) addresses approximately 700 soil waste sites (and associated structures such as pipelines) resulting from the discharge of liquids and solids from processing facilities to the ground (e.g., ponds, ditches, cribs,burial grounds) in the 200 Areas and assigned to the Environmental Restoration Program. The Implementation Plan outlines the framework for implementing assessment activities in the 200 Areas to ensure consistency in documentation, level of characterization, and decision making. The Implementation Plan also consolidates background information and other typical work plan materials, to serve as a single referenceable source for this type of information

  18. Remedial investigation of the High-Explosives (HE) Process Area, Lawrence Livermore National Laboratory Site 300

    Energy Technology Data Exchange (ETDEWEB)

    Crow, N.B.; Lamarre, A.L.

    1990-08-01

    This report presents the results of a Remedial Investigation (RI) to define the extent of high explosives (HE) compounds and volatile organic compounds (VOCs) found in the soil, rocks, and ground water of the HE Process Area of Lawrence Livermore National Laboratory's (LLNL) Site 300 Facility. The report evaluates potential public health environmental risks associated with these compounds. Hydrogeologic information available before February 15, 1990, is included; however, chemical analyses and water-level data are reported through March 1990. This report is intended to assist the California Regional Water Quality Control Board (RWQCB)--Central Valley Region and the US Environmental Protection Agency (EPA) in evaluating the extent of environmental contamination of the LLNL HE Process Area and ultimately in designing remedial actions. 90 refs., 20 figs., 7 tabs.

  19. FEASIBILITY STUDY REPORT FOR THE 200-ZP-1 GROUNDWATER OPERABLE UNIT

    Energy Technology Data Exchange (ETDEWEB)

    BYRNES ME

    2008-07-18

    , and groundwater particle-tracking analysis. The purpose of this FS is to develop and evaluate alternatives for remediation of the groundwater in the 200-ZP-1 OU. The alternatives considered provide a range of potential response actions (i.e., no action; institutional controls and monitored natural attenuation [MNA]; and pump-and-treat with MNA, flow-path control, and institutional controls) that are appropriate to address site-specific conditions. The alternatives are evaluated against seven of the nine CERCLA evaluation criteria defined in Guidance for Conducting Remedial Investigations and Feasibility Studies Under CERCLA (EPA/540/G-891004). The remaining two CERCLA criteria will be formally assessed during the public comment period. The FS evaluation serves as the basis for identifying a remedy to mitigate potential risks to human health and the environment. A preferred alternative (or alternatives) will be presented to the public for review and comment in the proposed plan.

  20. WAG 2 remedial investigation and site investigation site-specific work plan/health and safety checklist for the sediment transport modeling task

    International Nuclear Information System (INIS)

    Holt, V.L.; Baron, L.A.

    1994-05-01

    This site-specific Work Plan/Health and Safety Checklist (WP/HSC) is a supplement to the general health and safety plan (HASP) for Waste Area Grouping (WAG) 2 remedial investigation and site investigation (WAG 2 RI ampersand SI) activities [Health and Safety Plan for the Remedial Investigation and Site Investigation of Waste Area Grouping 2 at the Oak Ridge National Laboratory, Oak Ridge, Tennessee (ORNL/ER-169)] and provides specific details and requirements for the WAG 2 RI ampersand SI Sediment Transport Modeling Task. This WP/HSC identifies specific site operations, site hazards, and any recommendations by Oak Ridge National Laboratory (ORNL) health and safety organizations [i.e., Industrial Hygiene (IH), Health Physics (HP), and/or Industrial Safety] that would contribute to the safe completion of the WAG 2 RI ampersand SI. Together, the general HASP for the WAG 2 RI ampersand SI (ORNL/ER-169) and the completed site-specific WP/HSC meet the health and safety planning requirements specified by 29 CFR 1910.120 and the ORNL Hazardous Waste Operations and Emergency Response (HAZWOPER) Program Manual. In addition to the health and safety information provided in the general HASP for the WAG 2 RI ampersand SI, details concerning the site-specific task are elaborated in this site-specific WP/HSC, and both documents, as well as all pertinent procedures referenced therein, will be reviewed by all field personnel prior to beginning operations

  1. Verification of EPA's ''Preliminary Remediation Goals for radionuclides'' (PRG) electronic calculator

    Energy Technology Data Exchange (ETDEWEB)

    Jannik, Tim [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Stagich, Brooke [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL)

    2015-08-28

    The U.S. Environmental Protection Agency (EPA) requested an external, independent verification study of their updated “Preliminary Remediation Goals for Radionuclides” (PRG) electronic calculator. The calculator provides PRGs for radionuclides that are used as a screening tool at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) sites. These risk-based PRGs establish concentration limits under specific exposure scenarios. The purpose of this verification study is to determine that the calculator has no inherit numerical problems with obtaining solutions as well as to ensure that the equations are programmed correctly. There are 167 equations used in the calculator. To verify the calculator, all equations for each of seven receptor types (resident, construction worker, outdoor and indoor worker, recreator, farmer, and composite worker) were hand calculated using the default parameters. The same four radionuclides (Am-241, Co-60, H-3, and Pu-238) were used for each calculation for consistency throughout.

  2. Offpost Operable Unit Remedial Investigation and Chemical Specific Applicable or Relevant and Appropriate Requirements, Version 3.1. Volume 3

    Science.gov (United States)

    1988-12-01

    dried eggs and processed herbs and spices;... (iii) 250 parts per million in or on concentrated tomato products and dried figs; and (iv) 125 parts...eggplant, peppers, potatoes, summer squash and tomatoes . 4 4 4 H-25 4 38. PRIMARY NAME: Ethyl benzene (Ethylbenzene) CERCLA Hazardous Substance: Yes...C’. .R. § 141. 12 and the aquatic life standard as poenrtial ’\\ RAIZS reqa ire no( further discus~it n in this" con text. I8 Q h )tn omen ts ()n Fthfi

  3. Functional remediation components: A conceptual method of evaluating the effects of remediation on risks to ecological receptors.

    Science.gov (United States)

    Burger, Joanna; Gochfeld, Michael; Bunn, Amoret; Downs, Janelle; Jeitner, Christian; Pittfield, Taryn; Salisbury, Jennifer

    2016-01-01

    Governmental agencies, regulators, health professionals, tribal leaders, and the public are faced with understanding and evaluating the effects of cleanup activities on species, populations, and ecosystems. While engineers and managers understand the processes involved in different remediation types such as capping, pump and treat, and natural attenuation, there is often a disconnect between (1) how ecologists view the influence of different types of remediation, (2) how the public perceives them, and (3) how engineers understand them. The overall goal of the present investigation was to define the components of remediation types (= functional remediation). Objectives were to (1) define and describe functional components of remediation, regardless of the remediation type, (2) provide examples of each functional remediation component, and (3) explore potential effects of functional remediation components in the post-cleanup phase that may involve continued monitoring and assessment. Functional remediation components include types, numbers, and intensity of people, trucks, heavy equipment, pipes, and drill holes, among others. Several components may be involved in each remediation type, and each results in ecological effects, ranging from trampling of plants, to spreading invasive species, to disturbing rare species, and to creating fragmented habitats. In some cases remediation may exert a greater effect on ecological receptors than leaving the limited contamination in place. A goal of this conceptualization is to break down functional components of remediation such that managers, regulators, and the public might assess the effects of timing, extent, and duration of different remediation options on ecological systems.

  4. Environmental, Safety, and Health Plan for the remedial investigation/feasibility study at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-05-01

    This Environmental, Safety, and Health (ES ampersand H) Plan presents the concepts and methodologies to be followed during the remedial investigation/feasibility study (RI/FS) for Oak Ridge National Laboratory (ORNL) to protect the health and safety of employees, the public, and the environment. This ES ampersand H Plan acts as a management extension for ORNL and Martin Marietta Energy Systems, Inc. (Energy Systems) to direct and control implementation of the project ES ampersand H program. The subsections that follow describe the program philosophy, requirements, quality assurance measures, and methods for applying the ES ampersand H program to individual waste area grouping (WAG) remedial investigations. Hazardous work permits (HWPs) will be used to provide task-specific health and safety requirements

  5. Implementation Plan for Liquid Low-Level Radioactive Waste tank systems at Oak Ridge National Laboratory under the Federal Facility Agreement, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1994-09-01

    This document summarizes the progress that has been made to date in implementing the plans and schedules for meeting the Federal Facility Agreement (FFA) commitments for the Liquid Low-Level Waste (LLLW) System at Oak Ridge National Laboratory (ORNL). These commitments were initially submitted in ES/ER-17 ampersand Dl, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste Tank Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Information presented in this document provides a comprehensive summary to facilitate understanding of the FFA compliance program for LLLW tank systems and to present plans and schedules associated with remediation, through the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process, of LLLW tank systems that have been removed from service. ORNL has a comprehensive program underway to upgrade the LLLW system as necessary to meet the FFA requirements. The tank systems that are removed from service are being investigated and remediated through the CERCLA process. Waste and risk characterizations have been submitted. Additional data will be prepared and submitted to EPA/TDEC as tanks are taken out of service and as required by the remedial investigation/feasibility study (RI/FS) process. The plans and schedules for implementing the FFA compliance program that were submitted in ES/ER-17 ampersand Dl, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste tanks Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee, are updated in this document. Chapter 1 provides general background information and philosophies that lead to the plans and schedules that appear in Chaps. 2 through 5

  6. To fail is human: remediating remediation in medical education.

    Science.gov (United States)

    Kalet, Adina; Chou, Calvin L; Ellaway, Rachel H

    2017-12-01

    Remediating failing medical learners has traditionally been a craft activity responding to individual learner and remediator circumstances. Although there have been moves towards more systematic approaches to remediation (at least at the institutional level), these changes have tended to focus on due process and defensibility rather than on educational principles. As remediation practice evolves, there is a growing need for common theoretical and systems-based perspectives to guide this work. This paper steps back from the practicalities of remediation practice to take a critical systems perspective on remediation in contemporary medical education. In doing so, the authors acknowledge the complex interactions between institutional, professional, and societal forces that are both facilitators of and barriers to effective remediation practices. The authors propose a model that situates remediation within the contexts of society as a whole, the medical profession, and medical education institutions. They also outline a number of recommendations to constructively align remediation principles and practices, support a continuum of remediation practices, destigmatize remediation, and develop institutional communities of practice in remediation. Medical educators must embrace a responsible and accountable systems-level approach to remediation if they are to meet their obligations to provide a safe and effective physician workforce.

  7. Remedial investigation work plan for the Groundwater Operable Unit at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    This Remedial Investigation (RI) Work Plan has been developed as part of the US Department of Energy`s (DOE`s) investigation of the Groundwater Operable Unit (GWOU) at Oak Ridge National Laboratory (ORNL) located near Oak Ridge, Tennessee. The first iteration of the GWOU RI Work Plan is intended to serve as a strategy document to guide the ORNL GWOU RI. The Work Plan provides a rationale and organization for groundwater data acquisition, monitoring, and remedial actions to be performed during implementation of environmental restoration activities associated with the ORNL GWOU. It Is important to note that the RI Work Plan for the ORNL GWOU is not a prototypical work plan. The RI will be conducted using annual work plans to manage the work activities, and task reports will be used to document the results of the investigations. Sampling and analysis results will be compiled and reported annually with a review of data relative to risk (screening level risk assessment review) for groundwater. This Work Plan outlines the overall strategy for the RI and defines tasks which are to be conducted during the initial phase of investigation. This plan is presented with the understanding that more specific addenda to the plan will follow.

  8. Remedial investigation work plan for the Groundwater Operable Unit at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1994-03-01

    This Remedial Investigation (RI) Work Plan has been developed as part of the US Department of Energy's (DOE's) investigation of the Groundwater Operable Unit (GWOU) at Oak Ridge National Laboratory (ORNL) located near Oak Ridge, Tennessee. The first iteration of the GWOU RI Work Plan is intended to serve as a strategy document to guide the ORNL GWOU RI. The Work Plan provides a rationale and organization for groundwater data acquisition, monitoring, and remedial actions to be performed during implementation of environmental restoration activities associated with the ORNL GWOU. It Is important to note that the RI Work Plan for the ORNL GWOU is not a prototypical work plan. The RI will be conducted using annual work plans to manage the work activities, and task reports will be used to document the results of the investigations. Sampling and analysis results will be compiled and reported annually with a review of data relative to risk (screening level risk assessment review) for groundwater. This Work Plan outlines the overall strategy for the RI and defines tasks which are to be conducted during the initial phase of investigation. This plan is presented with the understanding that more specific addenda to the plan will follow

  9. Remedial investigation report on Waste Area Group 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 1: Technical summary

    International Nuclear Information System (INIS)

    1995-03-01

    A remedial investigation (RI) was performed to support environmental restoration activities for Waste Area Grouping (WAG) 5 at the Oak Ridge National Laboratory (ORNL) in Oak Ridge, Tennessee. The WAG 5 RI made use of the observational approach, which concentrates on collecting only information needed to assess site risks and support future cleanup work. This information was interpreted and is presented using the framework of the site conceptual model, which relates contaminant sources and release mechanisms to migration pathways and exposure points that are keyed to current and future environmental risks for both human and ecological receptors. The site conceptual model forms the basis of the WAG 5 remedial action strategy and remedial action objectives. The RI provided the data necessary to verify this model and allows recommendations to be made to accomplish those objectives

  10. Remedial investigation report on Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 1: Technical summary

    International Nuclear Information System (INIS)

    1995-09-01

    A remedial investigation (RI) was performed to support environmental restoration activities for Waste Area Grouping (WAG) 5 at the Oak Ridge National Laboratory (ORNL) in Oak Ridge, Tennessee. The WAG 5 RI made use of the observational approach, which concentrates on collecting only information needed to assess site risks and support future cleanup work. This information was interpreted and is presented using the framework of the site conceptual model, which relates contaminant sources and release mechanisms to migration pathways and exposure points that are keyed to current and future environmental risks for both human and ecological receptors. The site conceptual model forms the basis of the WAG 5 remedial action strategy and remedial action objectives. The RI provided the data necessary to verify this model and allows recommendations to be made to accomplish those objectives.

  11. Hazardous Substance Release Reporting Under CERCLA, EPCR {section}304 and DOE Emergency Management System (EMS) and DOE Occurrence Reporting Requirements. Environmental Guidance

    Energy Technology Data Exchange (ETDEWEB)

    Traceski, T.T.

    1994-06-01

    Releases of various substances from DOE facilities may be subject to reporting requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Emergency Planning and Community Right-to-Know Act (EPCRA), as well as DOE`s internal ``Occurrence Reporting and Processing of Operations Information`` and the ``Emergency Management System`` (EMS). CERCLA and EPCPA are Federal laws that require immediate reporting of a release of a Hazardous Substance (HS) and an Extremely Hazardous Substance (EHS), respectively, in a Reportable Quantity (RQ) or more within a 24-hour period. This guidance uses a flowchart, supplemental information, and tables to provide an overview of the process to be followed, and more detailed explanations of the actions that must be performed, when chemical releases of HSs, EHSs, pollutants, or contaminants occur at DOE facilities. This guidance should be used in conjunction with, rather than in lieu of, applicable laws, regulations, and DOE Orders. Relevant laws, regulations, and DOE Orders are referenced throughout this guidance.

  12. Operable Unit 1 remedial investigation report, Eielson Air Force Base, Alaska

    International Nuclear Information System (INIS)

    Gilmore, T.J.; Fruland, R.M.; Liikala, T.L.

    1994-06-01

    This remedial investigation report for operable Unit 1 (OU-1) at Eielson Air Force Base presents data, calculations, and conclusions as to the nature and extent of surface and subsurface contamination at the eight source areas that make up OU-1. The information is based on the 1993 field investigation result and previous investigations. This report is the first in a set of three for OU-1. The other reports are the baseline risk assessment and feasibility study. The information in these reports will lead to a Record of Decision that will guide and conclude the environmental restoration effort for OU-1 at Eielson Air Force Base. The primary contaminants of concern include fuels and fuel-related contaminants (diesel; benzene, toluene, ethylbenzene, and xylene; total petroleum hydrocarbon; polycyclic aromatic hydrocarbons), maintenance-related solvents and cleaners (volatile chlorinated hydrocarbons such as trichloroothylene), polychlorinated biphenyls, and dichlorodiphenyltrichloroethane (DDT). The origins of contaminants of concern include leaks from storage tanks, drums and piping, and spills. Ongoing operations and past sitewide practices also contribute to contaminants of concern at OU-1 source areas. These include spraying mixed oil and solvent wastes on unpaved roads and aerial spraying of DDT

  13. The use of institutional controls at Department of Energy Oak Ridge Field Office environmental restoration sites

    International Nuclear Information System (INIS)

    White, R.K.; Swindle, D.W.; Redfearn, A.; King, A.D.

    1992-01-01

    This report summarizes some of the major issues related to the use of institutional controls at hazardous waste sites under the auspices of the Department of Energy Field Office, Oak Ridge/Environmental Restoration (DOE-OR/ER) Division. In particular, the report addresses the impacts that assumptions regarding institutional controls have on the results and interpretation of the risk assessment, both in the Remedial Investigation (RI) and the Feasibility Study (FS). Environmental restoration activities at DOE-OR/ER sites are primarily driven by CERCLA. Therefore, the report focuses on the approaches and assumptions relating to institutional controls under CERCLA. Also the report briefly outlines approaches adopted under other authorities such as RCRA and radiation regulatory authorities (such as NRC regulations/guidance, DOE orders, and EPA standards) in order to contrast these approaches to those adopted under CERCLA. In order to demonstrate the implications of the use of institutional controls at DOE facilities, this report summarizes the approaches and results of the recent baseline risk assessment for Solid Waste Storage Area 6 at Oak Ridge National Laboratory. The report concludes with possible options on the use of institutional controls at DOE-OR/ER sites

  14. Sampling and Analysis Plan for White Oak Creek Watershed Remedial Investigation supplemental sampling, Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-05-01

    This Sampling and Analysis (SAP) presents the project requirements for proposed soil sampling to support the White Oak Creek Remedial Investigation/Feasibility Study at Oak Ridge National Laboratory. During the Data Quality Objectives process for the project, it was determined that limited surface soils sampling is need to supplement the historical environmental characterization database. The primary driver for the additional sampling is the need to identify potential human health and ecological risks at various sites that have not yet proceeded through a remedial investigation. These sites include Waste Area Grouping (WAG)3, WAG 4, WAG 7, and WAG 9. WAG 4 efforts are limited to nonradiological characterization since recent seep characterization activities at the WAG have defined the radiological problem there

  15. The remedial investigation/feasibility study process at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    1993-01-01

    Martin Marietta Energy Systems, Inc. (Energy Systems), manages and operates the Oak Ridge National Laboratory (ORNL), Oak Ridge, Tennessee, under a cost-plus-award-fee contract administered by the Department of Energy's (DOE) Oak Ridge Field office (Field Office). Energy Systems' environmental restoration program is responsible for eliminating or reducing to prescribed safe levels the risks to the environment or to human health and safety posed by inactive and surplus sites and facilities that have been contaminated with radioactive, hazardous, or mixed wastes. Energy Systems subcontracted to perform the remedial investigation and feasibility study (RI/FS) at ORNL. The objective of our audit was to determine if the RI/FS at ORNL had been implemented in a manner that ensured accomplishment of the goals and objectives of the DOE Environmental Restoration Program. The audit disclosed that the subcontractor did not fully meet its contractual requirements. Specifically, environmental data produced by the subcontractor is of questionable value for meeting its contractual requirement to provide data supporting permanent remedial action. This condition occurred because neither the subcontractor nor Energy Systems adequately implemented all essential management controls, and neither Energy Systems nor DOE provided adequate contract administration. As a result, DOE has received little value for its RI/FS expenditures. We have recommended that DOE determine the allowability of an estimated $45 million of subcontractor RI/FS cost at ORNL, plus the cost of Energy Systems administering the subcontract. Furthermore, DOE will continue to pay unnecessary costs and experience cost growth and project delays until effective project management controls are implemented

  16. Drama, dissensus, remediation and a fluttering butterfly

    DEFF Research Database (Denmark)

    Kusk, Hanne

    2017-01-01

    Why is it important to pay attention to democracy and polyphony when working with remediation in a multimodal drama project in introductory schooling? This question is elucidated and investigated in this article on the basis of a drama project case study conducted at Hundborg Friskole. The study...... is analysed on the basis of the concepts of remediation (Bolter and Grusin 1999; Christoffersen 2009), dissensus (Biesta 2013; Rancière 2013), dialogue and polyphony (Dysthe, Bernhardt and Esbjørn 2012). The examples in the investigation show how dialogue, polyphony and dissensus influence the art......-based process of remediation, and how this impacts children’s democratic education....

  17. 76 FR 77528 - Proposed CERCLA Administrative Cost Recovery Settlement; North Hollywood Operable Unit of the San...

    Science.gov (United States)

    2011-12-13

    ...In accordance with Section 122(i) of the Comprehensive Environmental Response, Compensation, and Liability Act, as amended (``CERCLA''), 42 U.S.C. 9622(i), notice is hereby given of a proposed administrative settlement for recovery of response costs concerning the North Hollywood Operable Unit of the San Fernando Valley Area 1 Superfund Site, located in the vicinity of Los Angeles, California, with the following settling parties: Pick-Your-Part Auto Wrecking; Hayward Associates, LLC; and PNM Properties, LLC. The settlement requires the settling parties to pay a total of $102,161 to the North Hollywood Operable Unit Special Account within the Hazardous Substance Superfund. The settlement also includes a covenant not to sue the settling parties pursuant to Section 107(a) of CERCLA, 42 U.S.C. 9607(a). For thirty (30) days following the date of publication of this notice, the Agency will receive written comments relating to the settlement. The Agency will consider all comments received and may modify or withdraw its consent to the settlement if comments received disclose facts or considerations which indicate that the settlement is inappropriate, improper, or inadequate. The Agency's response to any comments received will be available for public inspection at the City of Los Angeles Central Library, Science and Technology Department, 630 West 5th Street, Los Angeles, CA 90071 and at the EPA Region 9 Superfund Records Center, Mail Stop SFD-7C, 95 Hawthorne Street, Room 403, San Francisco, CA 94105.

  18. 76 FR 79678 - Proposed CERCLA Administrative Cost Recovery Settlement; North Hollywood Operable Unit of the San...

    Science.gov (United States)

    2011-12-22

    ...In accordance with Section 122(i) of the Comprehensive Environmental Response, Compensation, and Liability Act, as amended (``CERCLA''), 42 U.S.C. 9622(i), notice is hereby given of a proposed administrative settlement for recovery of response costs concerning the North Hollywood Operable Unit of the San Fernando Valley Area 1 Superfund Site, located in the vicinity of Los Angeles, California, with the following settling parties: Pick-Your-Part Auto Wrecking; Hayward Associates, LLC; and PNM Properties, LLC. The settlement requires the settling parties to pay a total of $102,161 to the North Hollywood Operable Unit Special Account within the Hazardous Substance Superfund. The settlement also includes a covenant not to sue the settling parties pursuant to Section 107(a) of CERCLA, 42 U.S.C. 9607(a). For thirty (30) days following the date of publication of this notice, the Agency will receive written comments relating to the settlement. The Agency will consider all comments received and may modify or withdraw its consent to the settlement if comments received disclose facts or considerations which indicate that the settlement is inappropriate, improper, or inadequate. The Agency's response to any comments received will be available for public inspection at the City of Los Angeles Central Library, Science and Technology Department, 630 West 5th Street, Los Angeles, CA 90071 and at the EPA Region 9 Superfund Records Center, Mail Stop SFD-7C, 95 Hawthorne Street, Room 403, San Francisco, CA 94105.

  19. 77 FR 123 - Proposed CERCLA Administrative Cost Recovery Settlement; North Hollywood Operable Unit of the San...

    Science.gov (United States)

    2012-01-03

    ...In accordance with Section 122(i) of the Comprehensive Environmental Response, Compensation, and Liability Act, as amended (``CERCLA''), 42 U.S.C. 9622(i), notice is hereby given of a proposed administrative settlement for recovery of response costs concerning the North Hollywood Operable Unit of the San Fernando Valley Area 1 Superfund Site, located in the vicinity of Los Angeles, California, with the following settling party: Waste Management Recycling & Disposal Services of California, Inc., dba Bradley Landfill & Recycling Center. The settlement requires the settling party to pay a total of $185,734 to the North Hollywood Operable Unit Special Account within the Hazardous Substance Superfund. The settlement also includes a covenant not to sue the settling party pursuant to Section 107(a) of CERCLA, 42 U.S.C. 9607(a). For thirty (30) days following the date of publication of this notice, the Agency will receive written comments relating to the settlement. The Agency will consider all comments received and may modify or withdraw its consent to the settlement if comments received disclose facts or considerations which indicate that the settlement is inappropriate, improper, or inadequate. The Agency's response to any comments received will be available for public inspection at the City of Los Angeles Central Library, Science and Technology Department, 630 West 5th Street, Los Angeles CA 90071 and at the EPA Region 9 Superfund Records Center, Mail Stop SFD-7C, 95 Hawthorne Street, Room 403, San Francisco, CA 94105.

  20. Investigations of Cu, Pb and Zn partitioning by sequential extraction in harbour sediments after electrodialytic remediation

    DEFF Research Database (Denmark)

    Kirkelund, Gunvor Marie; Ottosen, Lisbeth M.; Villumsen, Arne

    2010-01-01

    remediation time. A three step sequential extraction scheme (BCR), with an extra residual step, was used to evaluate the heavy metal distribution in the sediments before and after electrodialytic remediation. Cu was mainly associated with the oxidisable phase of the sediment, both before and after remediation...

  1. Requirements for quality control of analytical data

    International Nuclear Information System (INIS)

    Westmoreland, R.D.; Bartling, M.H.

    1990-07-01

    The National Contingency Plan (NCP) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) provides procedures for the identification, evaluation, and remediation of past hazardous waste disposal sites. The Hazardous Materials Response section of the NCP consists of several phases: Preliminary Assessment, Site Inspection, Remedial Investigation, Feasibility Study, Remedial Design, and Remedial Action. During any of these phases, analysis of soil, water, and waste samples may be performed. The Hazardous Waste Remedial Actions Program (HAZWRAP) is involved in performing field investigations and sample analyses pursuant to the NCP for the US Department of Energy and other federal agencies. The purpose of this document is to specify the requirements of Martin Marietta Energy Systems, Inc., for the control of accuracy, precision, and completeness of samples and data from the point of collection through analysis. Requirements include data reduction and reporting of resulting environmentally related data. Because every instance and concern may not be addressed in this document, HAZWRAP subcontractors are encouraged to discuss any questions with the Analytical Quality Control Specialist (AQCS) and the HAZWRAP Project Manager. This revision supercedes all other versions of this document

  2. Hanford site past practice investigation strategy: Lessons learned

    International Nuclear Information System (INIS)

    Thompson, K. Michael

    1992-01-01

    The U. S. Department of Energy (DOE), U. S. Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) have negotiated a strategy for performing Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) Past Practice investigations in a more streamlined manner with a bias-for-action. This strategy provides new concepts for 1) accelerating decision-making by maximizing the use of existing data consistent with data quality objectives and 2) undertaking expedited response actions and/or interim remedial measures as appropriate to either remove threats to human health and welfare and the environment or to reduce risk by reducing toxicity, mobility or volume of contaminants. Since the goal of the program is cleanup, much more emphasis will be placed on initiating and completing waste site cleanups through interim measures. While investigations and studies are important in meeting long-range goals, there is now agreement by the parties that an appropriate and significant portion of the near-term funding resources can and should be dedicated to remedial work, where there is sufficient information from which to plan and implement interim remedial measures. The initial stages of Hanford clean-up will optimize the use of interim cleanup actions when justified and practicable. Existing data will be evaluated as the initial basis for decision-making. If the data are found to be insufficient, additional essential data will be collected to support the IRM in a limited field investigation (LFI). Only data needed to formulate a conceptual model (source to pathway to receptor) and qualitative risk assessment would be obtained. The data quality objectives of the LFI will be established based on the use of the data in deciding on IRMs. The data might not need to be of the same quality needed to support final RODs, since the IRM itself would yield valuable information for

  3. Hydrogeological site investigation for the efficient remediation of uranium mining sites -- an integrated approach

    International Nuclear Information System (INIS)

    Biehler, D.; Jaquet, O.; Croise, J.; Lavanchy, J.-M.

    2002-01-01

    The currently practised remediation of former uranium mines in Eastern Germany involves the flooding of underground and open pit mines, and the stabilization of waste rock dumps and tailings ponds, e.g. by dewatering, covering, improving dams, cleaning effluents. This article presents examples demonstrating that the remediation concepts developed and implemented have failed their targets, resulting in uncontrolled flow behaviour and migration of contaminated water, leading to increased costs and additional threats to the environment. A generic series of steps for an improved remediation management with respect to financial efforts and environmental safety are proposed in terms of an integrated approach. (author)

  4. Site enforcement tracking system (SETS): PRP listing by site for region 9

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  5. Site enforcement tracking system (SETS): PRP listing by site for region 8

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  6. Site enforcement tracking system (SETS): PRP listing by site for region 10

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  7. Site enforcement tracking system (SETS): PRP listing by site for region 3

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  8. Site enforcement tracking system (SETS): PRP listing by site for region 2

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  9. Site enforcement tracking system (SETS): PRP listing by site for region 5

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  10. Site enforcement tracking system (SETS): PRP listing by site for region 6

    International Nuclear Information System (INIS)

    1993-04-01

    When expending Superfund monies at a CERCLA (Comprehensive Environmental Response, Compensation and Liability Act) site, EPA must conduct a search to identify parties with potential financial responsibility for remediation of uncontrolled hazardous waste sites. EPA regional Superfund Waste Management Staff issue a notice letter to the potentially responsible party (PRP). Data from the notice letter is used to form the Site Enforcement Tracking System (SETS). The data includes PRP name and address, a company contact person, the date the notice was issued, and the related CERCLA site name and identification number

  11. Role of decision-tree analysis in the performance of a complex feasibility study

    International Nuclear Information System (INIS)

    Dworkin, D.; Sarkar, A.; Motwani, J.

    1991-01-01

    This report presents the results of the Feasibility Study (FS) of a National Priorities List (NPL) site in New Jersey and the decision tree that made this FS possible. The development of the decision tree and the remedial action alternatives that address the hazards at the site are presented. The FS efforts were performed in accordance with U.S. EPA guidance under the authority of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA). A Record of Decision (ROD) is expected in mid-1990. The subject site, the Myers Property site in Franklin Township, New Jersey, has been owned by several individuals and companies since 1811. Uses have included the production of DDT. A Remedial Investigation (RI) was performed by WESTON, the lead technical firm for this feasibility study, which identified soils/sediments, groundwater and buildings on the site as areas of concern. The major chemicals of concern are DDT and its metabolites, polynuclear aromatic compounds, various chlorinated benzenes, dioxin/furan homologues and heavy metals such as arsenic, cadmium, copper, lead, chromium and nickel. While this FS was developed in accordance with current CERCLA FS guidance and procedures, it was expanded to accommodate several outstanding technical and policy issues. Outstanding technical issues focused on uncertainties with respect to hydrogeologic conditions, and policy issues centered upon the development of the site-specific remedial action goals. A decision tree was established to facilitate the development of remedial strategies. The decision tree formed the basis for the FS and allowed remedial alternatives to be identified and evaluated based on key policy decisions. Site media were addressed as contaminated soils/sediments, groundwater and the on-site buildings

  12. Alternative Endpoints and Approaches for the Remediation of Contaminated Groundwater at Complex Sites - 13426

    International Nuclear Information System (INIS)

    Deeb, Rula A.; Hawley, Elisabeth L.

    2013-01-01

    alternative endpoints for groundwater remediation at complex sites. A statistical analysis of Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) sites receiving TI waivers will be presented as well as case studies of other types of alternative endpoints and alternative remedial strategies that illustrate the variety of approaches used at complex sites and the technical analyses used to predict and document cost, time frame, and potential remedial effectiveness. This presentation is intended to inform DOE program managers, state regulators, practitioners and other stakeholders who are evaluating technical cleanup challenges within their own programs, and establishing programmatic approaches to evaluating and implementing long-term management approaches. Case studies provide examples of long-term management designations and strategies to manage and remediate groundwater at complex sites. At least 13 states consider some designation for groundwater containment in their corrective action policies, such as groundwater management zones, containment zones, and groundwater classification exemption areas. Long-term management designations are not a way to 'do nothing' or walk away from a site. Instead, soil and groundwater within the zone is managed to be protective of human health and the environment. Understanding when and how to adopt a long-term management approach can lead to cost savings and the more efficient use of resources across DOE and at numerous other industrial and military sites across the U.S. This presentation provides context for assessing the use and appropriate role of alternative endpoints and supporting long-term management designations in final remedies. (authors)

  13. Alternative Endpoints and Approaches for the Remediation of Contaminated Groundwater at Complex Sites - 13426

    Energy Technology Data Exchange (ETDEWEB)

    Deeb, Rula A.; Hawley, Elisabeth L. [ARCADIS, U.S., 2000 Powell St., 7th Floor, Emeryville, California 94608 (United States)

    2013-07-01

    to evaluate alternative endpoints for groundwater remediation at complex sites. A statistical analysis of Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) sites receiving TI waivers will be presented as well as case studies of other types of alternative endpoints and alternative remedial strategies that illustrate the variety of approaches used at complex sites and the technical analyses used to predict and document cost, time frame, and potential remedial effectiveness. This presentation is intended to inform DOE program managers, state regulators, practitioners and other stakeholders who are evaluating technical cleanup challenges within their own programs, and establishing programmatic approaches to evaluating and implementing long-term management approaches. Case studies provide examples of long-term management designations and strategies to manage and remediate groundwater at complex sites. At least 13 states consider some designation for groundwater containment in their corrective action policies, such as groundwater management zones, containment zones, and groundwater classification exemption areas. Long-term management designations are not a way to 'do nothing' or walk away from a site. Instead, soil and groundwater within the zone is managed to be protective of human health and the environment. Understanding when and how to adopt a long-term management approach can lead to cost savings and the more efficient use of resources across DOE and at numerous other industrial and military sites across the U.S. This presentation provides context for assessing the use and appropriate role of alternative endpoints and supporting long-term management designations in final remedies. (authors)

  14. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 4. Appendix F

    International Nuclear Information System (INIS)

    1995-09-01

    This section contains ecotoxicological profiles for the COPECs for the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The ecotoxicological information is presented for only those endpoints for which the chemicals are COPECs. The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include 137 Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and 137 Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River

  15. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 4. Appendix F

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    This section contains ecotoxicological profiles for the COPECs for the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The ecotoxicological information is presented for only those endpoints for which the chemicals are COPECs. The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include {sup 137}Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and {sup 137}Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River.

  16. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 3. Appendix E

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    This document contains Appendix E: Toxicity Information and Uncertainty Analysis, description of methods, from the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include {sup 137}Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and {sup 137}Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River.

  17. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 1. Main text

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    This is the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include {sup 137}Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and {sup 137}Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River.

  18. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 3. Appendix E

    International Nuclear Information System (INIS)

    1995-09-01

    This document contains Appendix E: Toxicity Information and Uncertainty Analysis, description of methods, from the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include 137 Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and 137 Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River

  19. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 1. Main text

    International Nuclear Information System (INIS)

    1995-09-01

    This is the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include 137 Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and 137 Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River

  20. Remediation of PAH-contaminated soil using Achromobacter sp

    International Nuclear Information System (INIS)

    Cutright, T.J.; Lee, S.

    1994-01-01

    Several technologies have the potential to effectively remediate soil contaminated with polycyclic aromatic hydrocarbons (PAHs): solvent extraction, coal-oil agloflotation, supercritical extraction, and bioremediation. Due to the cost effectiveness and in-situ treatment capabilities of bioremediation, studies were conducted to determine the efficiency of Achromobacter sp. to remediate an industrial contaminated soil sample. Specifically, the use of three different mineral salt solutions in conjunction with the Achromobacter sp. was investigated. The molecular identification of the contaminants and their respective levels after remediation were determined using a Hewlett-Packard 1050 HPLC. Preliminary results show a 92% remediation for the use of two of the mineral salt solutions after 20 days' treatment. After 8 weeks, the remediation efficiency reached 99%. Bioremediation was also critically compared to the other potential remediation technologies

  1. Implementation plan for Liquid Low-Level Radioactive Waste Tank Systems at Oak Ridge National Laboratory under the Federal Facility Agreement, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1994-06-01

    Plans and schedules for meeting the Federal Facility Agreement (FFA) commitments for the Liquid Low-Level Waste (LLLW) System at Oak Ridge National Laboratory (ORNL) were initially submitted in ES/ER-17 ampersand D1, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste Tank Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee. The information presented in the current document summarizes the progress that has been made to date and provides a comprehensive summary to facilitate understanding of the FFA compliance program for LLLW tank systems and to present the plans and schedules associated with the remediation, through the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process, of LLLW tank systems that have been removed from service. A comprehensive program is under way at ORNL to upgrade the LLLW system as necessary to meet the FFA requirements. The tank systems that are removed from service are being investigated and remediated through the CERCLA process. Waste and risk characterizations have been submitted. Additional data will be submitted to the US Environmental Protection Agency and the Tennessee Department of Environment and Conservation (EPA/TDEC) as tanks are taken out of service and as required by the remedial investigation/feasibility study (RI/FS) process. The plans and schedules for implementing the FFA compliance program that were originally submitted in ES/ER-17 ampersand D 1, Federal Facility Agreement Plans and Schedules for Liquid Low-Level Radioactive Waste tanks Systems at Oak Ridge National Laboratory, Oak Ridge, Tennessee, are updated in the present document. Chapter I provides general background information and philosophies that lead to the plans and schedules that appear in Chaps. 2 through 5

  2. Remediation trials of crude oil contaminated soil using different ...

    African Journals Online (AJOL)

    A 3 month remediation trial of the use of detergent and sawdust in different combination forms in the restoration of a crude oil contaminated tropical soil was investigated. 8 remediation treatments labeled A – H in addition to the control (I) were used in 10 kg soil artificially polluted with 300 ml crude oil each. Remediation ...

  3. 48 CFR 22.1504 - Violations and remedies.

    Science.gov (United States)

    2010-10-01

    ... to cooperate as required in accordance with the clause at 52.222-19, Child Labor Cooperation with Authorities and Remedies, with an investigation of the use of forced or indentured child labor by an Inspector... contractor knew of the violation. (b) Remedies. (1) The contracting officer may terminate the contract. (2...

  4. Status of remedial investigation activities in the Hanford Site 300 Area groundwater operable unit

    International Nuclear Information System (INIS)

    Hulstrom, L.C.; Innis, B.E.; Frank, M.A.

    1993-09-01

    The Phase 1 remedial investigation (RI) and Phase 1 and 2 feasibility studies (FS) for the 300-FF-5 groundwater operable unit underlying the 300 Area on the Hanford Site have been completed. Analysis and evaluation of soil, sediment, and surface water, and biotic sampling data, groundwater chemistry, and radiological data gathered over the past 3 years has been completed. Risk assessment calculations have been performed. Use of the data gathered, coupled with information from an automated water level data collection system, has enabled engineers to track three plumes that represent the most significant contamination of the groundwater

  5. Electrodialytic remediation of soil polluted with heavy metals

    DEFF Research Database (Denmark)

    Hansen, Henrik K.; Ottosen, Lisbeth M.; Hansen, Lene

    1999-01-01

    In this paper, the importance of some parameters for the efficiency of electrodialytic soil remediation are evaluated. The parameters investigated are pH, the limiting current density and the adding of desorbing agents to the soil. Three parameters are found to be of greatest importance. Results...... show that the electrodialytic soil remediation can be optimized by understanding and adjusting of these parameters. For scaling up of the remediation method these parameters are of crucial importance....

  6. Remedial Investigation Report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-01-01

    This report on the BCV OU 2 at the Y-12 Plant, was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting the results of a site characterization for public review. It provides the Environmental Restoration Program with information about the results of the 1993 investigation. It includes information on risk assessments that have evaluated impacts to human health and the environment. Field activities included collection of subsurface soil samples, groundwater and surface water samples, and sediments and seep at the Rust Spoil Area (RSA), SY-200 Yard, and SA-1.

  7. Remedial Investigation Report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text

    International Nuclear Information System (INIS)

    1995-01-01

    This report on the BCV OU 2 at the Y-12 Plant, was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting the results of a site characterization for public review. It provides the Environmental Restoration Program with information about the results of the 1993 investigation. It includes information on risk assessments that have evaluated impacts to human health and the environment. Field activities included collection of subsurface soil samples, groundwater and surface water samples, and sediments and seep at the Rust Spoil Area (RSA), SY-200 Yard, and SA-1

  8. B Plant source aggregate area management study report

    International Nuclear Information System (INIS)

    1993-03-01

    The US Department of Energy (DOE) Hanford Site in Washington state is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 100 Areas (Figure 1--1). The US Environmental Protection Agency (EPA), in November 1989, included the 200 Areas of the Hanford KLSite on the National Priorities List (NPL), included the 200 Areas of the Hanford Site on the National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act of Feasibility Study (FS) process for characterizing the nature and extent of contamination, assessing risks to human health and the environment, and selection of remedial actions. This report presents the results of an aggregate area management study (AIMS) for the B Plant Aggregate Area located in the 200 Areas. The study provides the basis for initiating RI/FS under CERCLA or under the Resource which contain reactor fuel processing and waste management Conservation and Recovery Act (RCRA) Facility Investigations (RFI) and Corrective Measures Studies (CMS). This report also integrates RCRA treatment, storage or disposal (TSD) closure activities with CERCLA and RCRA past-practice investigations

  9. Best management practices plan for the Lower East Fork Poplar Creek Operable Unit, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-04-01

    This plan was prepared in support of the Phase II Remedial Design Report (DOE/OR/01-1449 ampersand D1) and in accordance with requirements under CERCLA to present the plan for best management practices to be followed during the remediation. This document provides the Environmental Restoration Program with information about spill prevention and control, water quality monitoring, good housekeeping practices, sediment and erosion control measures, and inspections and environmental compliance practices to be used during Phase II of the remediation project for the Lower East Fork Poplar Creek Operable Unit

  10. Remedial investigation/feasibility study Work Plan and addenda for Operable Unit 4-12: Central Facilities Area Landfills II and III at the Idaho National Engineering Laboratory

    Energy Technology Data Exchange (ETDEWEB)

    Keck, K.N.; Stormberg, G.J.; Porro, I.; Sondrup, A.J.; McCormick, S.H.

    1993-07-01

    This document is divided into two main sections -- the Work Plan and the addenda. The Work Plan describes the regulatory history and physical setting of Operable Unit 4-12, previous sampling activities, and data. It also identifies a preliminary conceptual model, preliminary remedial action alternatives, and preliminary applicable or relevant and appropriate requirements. In addition, the Work Plan discusses data gaps and data quality objectives for proposed remedial investigation activities. Also included are tasks identified for the remedial investigation/feasibility study (RI/FS) and a schedule of RI/FS activities. The addenda include details of the proposed field activities (Field Sampling Plan), anticipated quality assurance activities (Quality Assurance Project Plan), policies and procedures to protect RI/FS workers and the environment during field investigations (Health and Safety Plan), and policies, procedures, and activities that the Department of Energy will use to involve the public in the decision-making process concerning CFA Landfills II and III RI/FS activities (Community Relations Plan).

  11. Remedial investigation/feasibility study Work Plan and addenda for Operable Unit 4-12: Central Facilities Area Landfills II and III at the Idaho National Engineering Laboratory

    International Nuclear Information System (INIS)

    Keck, K.N.; Stormberg, G.J.; Porro, I.; Sondrup, A.J.; McCormick, S.H.

    1993-07-01

    This document is divided into two main sections -- the Work Plan and the addenda. The Work Plan describes the regulatory history and physical setting of Operable Unit 4-12, previous sampling activities, and data. It also identifies a preliminary conceptual model, preliminary remedial action alternatives, and preliminary applicable or relevant and appropriate requirements. In addition, the Work Plan discusses data gaps and data quality objectives for proposed remedial investigation activities. Also included are tasks identified for the remedial investigation/feasibility study (RI/FS) and a schedule of RI/FS activities. The addenda include details of the proposed field activities (Field Sampling Plan), anticipated quality assurance activities (Quality Assurance Project Plan), policies and procedures to protect RI/FS workers and the environment during field investigations (Health and Safety Plan), and policies, procedures, and activities that the Department of Energy will use to involve the public in the decision-making process concerning CFA Landfills II and III RI/FS activities (Community Relations Plan)

  12. The Challenges Of Investigating And Remediating Port Hope's Small-Scale Urban Properties - 13115

    Energy Technology Data Exchange (ETDEWEB)

    Veen, Walter van; Case, Glenn; Benson, John; Herod, Judy [Atomic Energy of Canada Limited, Port Hope, Ontario (Canada); Yule, Adam [Public Works and Government Services Canada, Port Hope, Ontario (Canada)

    2013-07-01

    An important component of the Port Hope Project, the larger of the two projects comprising the Port Hope Area Initiative (PHAI), is the investigation of all 4,800 properties in the Municipality of Port Hope for low level radioactive waste (LLRW) and the remediation of approximately 10% of these. Although the majority of the individual properties are not expected to involve technically sophisticated remediation programs, the large number of property owners and individually unique properties are expected to present significant logistic challenges that will require a high degree of planning, organization and communication. The protocol and lessons learned described will be of interest to those considering similar programs. Information presented herein is part of a series of papers presented by the PHAI Management Office (PHAI MO) at WM Symposium '13 describing the history of the Port Hope Project and current project status. Other papers prepared for WM Symposium '13 address the large-scale site cleanup and the construction of the long-term waste management facility (LTWMF) where all of the LLRW will be consolidated and managed within an engineered, above-ground mound. (authors)

  13. Source zone remediation by zero valent iron technologies

    DEFF Research Database (Denmark)

    Fjordbøge, Annika Sidelmann

    at a fifth of these contaminated sites. These source zones pose a serious threat to soil and groundwater quality. Remediation of the heterogeneous source zones is challenging due to irregular downwards migration patterns in the subsurface, low aqueous solubility and matrix diffusion. To protect the soil...... and groundwater resources from long-term deterioration, the development of in situ technologies suitable for remediation of DNAPL is warranted. Currently, an array of aggressive in situ remediation technologies remediation exists. These technologies may be suitable under various site specific conditions; however......, most of them are limited by subsurface heterogeneities and/or the risk of inadvertent DNAPL displacement during field application. This thesis presents the results of an investigation of the potential for remediation of chlorinated solvent source zones by emerging zero valent iron (ZVI) based...

  14. The marriage of RCRA and CERCLA at the Rocky Flats Environmental Technology Site

    International Nuclear Information System (INIS)

    Shelton, D.C.; Brooks, L.M.

    1998-01-01

    A key goal of the Rocky Flats Cleanup Agreement (RFCA) signed in July of 1996 was to provide a seamless marriage of the Resource Conservation and Recovery Act (RCRA) (and other media specific programs) and the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) and the implementing agencies of each. This paper examines the two years since the signing of RFCA and identifies the successes, failures, and stresses of the marriage. RFCA has provided an excellent vehicle for regulatory and substantive progress at the Department of Energy's Rocky Flats facility. The key for a fully successful marriage is to build on the accomplishments to date and to continually improve the internal and external systems and relationships. To date, the parties can be proud of both the substantial accomplishment of substantive environmental work and the regulatory systems that have enabled the work

  15. Remediation of a contaminated thin aquifer by horizontal wells

    Energy Technology Data Exchange (ETDEWEB)

    Breh, W.; Suttheimer, J.; Hoetzl, H. [Univ. of Karlsruhe (Germany); Frank, K. [GEO-Service GmbH, Rheinmuenster (Germany)

    1997-12-31

    At an industrial site in Bruchsal (Germany) a huge trichloroethene contamination was found. After common remedial actions proved to be widely ineffective, new investigations led to a highly contaminated thin aquifer above the main aquifer. The investigation and the beginning of the remediation of the thin aquifer by two horizontal wells is described in this paper. Special attention was given to the dependence between precipitation and the flow direction in the thin aquifer and to hydraulic connections between the thin and the main aquifer. Also a short introduction into a new remedial technique by horizontal wells and first results of the test phase of the horizontal wells are given.

  16. Basewide Groundwater Operable Unit. Groundwater Operable Unit Remedial Investigation/Feasibility Study Report. Volume 1

    Science.gov (United States)

    1994-06-01

    units would be reused in the remedy. Contingency measures to be included in the remedy are potential metals removal prior to water end use, potential...onbase reuse of a portion of the water, and wellhead treatment on offbase supply wells. The contingency measures will only be implemented if necessary...94 LEGEND Ouatmar aluvi dposts agua Frmaion(cosoldatd aluval epoits W iead rdetilnsMhte omtin(neitccnlmeae ansoe9ndkeca F 70 Quvatei-lernayalvu e pk

  17. 32 CFR 634.10 - Remedial driver training programs.

    Science.gov (United States)

    2010-07-01

    ... 32 National Defense 4 2010-07-01 2010-07-01 true Remedial driver training programs. 634.10 Section 634.10 National Defense Department of Defense (Continued) DEPARTMENT OF THE ARMY (CONTINUED) LAW ENFORCEMENT AND CRIMINAL INVESTIGATIONS MOTOR VEHICLE TRAFFIC SUPERVISION Driving Privileges § 634.10 Remedial driver training programs. (a) Navy...

  18. Superfund tio videos: Set A. Overview of superfund, response activities and responsibilities, site discovery, notification, and evaluation. Part 1. Audio-Visual

    International Nuclear Information System (INIS)

    1990-01-01

    The videotape is divided into three sections. Section 1 discusses the development and framework of CERCLA and the Superfund Program and outlines the implementing rules that guide Superfund site cleanups. The Superfund response actions - remedial, removal, and enforcement - are reviewed. Section 2 outlines On-Scene Coordinator's (OSC) and Remedial Project Manager's (RPM) roles and responsibilities in Superfund removal, remedial, and enforcement activities. The other players involved in Superfund response activities also are identified. Section 3 describes how EPA learns of potential Superfund sites and lists the authorities that determine the requirements for site discovery. The procedures used to prioritize the sites and to identify and select sites for remediation are discussed

  19. An integrated building demolition and waste planning model for the Fernald Site

    International Nuclear Information System (INIS)

    Hampshire, L.H.; Clark, T.R.; Frost, M.L.; Reising, J.W.

    1995-01-01

    The Fernald DOE site will begin full-scale remediation of buildings under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) during the 1995 fiscal year pursuant to a signed Record of Decision. This effort is currently estimated to cost $350 million and span a minimum duration of 8 years, if funding is not a constraint. The identification of the most viable sequence and schedule for the effort involved the development of an integrated planning model and the commissioning of a sitewide planning team. The resulting work product represents the best combination of assumptions and calculations possible at this time and provides information necessary for compliance with the CERCLA Remedial Design documentation requirements for the over 230 component structures governed by the decision. Sequence and integrated schedule development for the decontamination and dismantlement (D ampersand D) of Fernald structures has involved evaluation of current and future utilization of structures, availability of waste storage and staging space, the needs and impacts of other on-going Fernald projects, Resource Conservation and Recovery Act (RCRA) waste management and remediation projects, the layout of site utilities, site hydrology, and the potential sizing, location, and construction rates for an on-property disposal cell

  20. Case study of an approved corrective action integrating active remediation with intrinsic remediation

    International Nuclear Information System (INIS)

    Teets, D.B.; Guest, P.R.; Blicker, B.R.

    1996-01-01

    Parsons Engineering Science, Inc., performed UST removals and/or site assessments at UST system locations at a former US Air Force Base (AFB) in Denver, Colorado. Four UST systems, incorporating 17 USTs, were located within the petroleum, oils, and lubricants bulk storage yard (POL Yard) of the former AFB. During the tank removals and subsequent site investigations, petroleum hydrocarbon contamination was found in soils at each site. Significant releases from two of the UST systems resulted in a dissolved benzene, toluene, ethylbenzene, and xylenes (BTEX) plume in the groundwater, and smear-zone contamination of soils beneath the majority of the POL Yard. Because of the close proximity of the UST systems, and the presence of the groundwater plume beneath the POL Yard, a corrective action plan (CAP) was prepared that encompassed all four UST systems. An innovative, risk-based CAP integrated active remediation of petroleum-contaminated soils with intrinsic remediation of groundwater. A natural attenuation evaluation for the dissolved BTEX was performed to demonstrate that natural attenuation processes are providing adequate remediation of groundwater and to predict the fate of the groundwater plume. BTEX concentrations versus distance were regressed to obtain attenuation rates, which were then used to calculate BTEX degradation rates using a one-dimensional, steady-state analytical solution. Additionally, electron acceptor concentrations in groundwater were compared to BTEX concentrations to provide evidence that natural attenuation of BTEX compounds was occurring. The natural attenuation evaluation was used in the CAP to support the intrinsic remediation with long-term monitoring alternative for groundwater, thereby avoiding the installation of an expensive groundwater remediation system

  1. An assessment of baseline ecological risks at the Fernald Environmental Management Project, Fernald, Ohio

    International Nuclear Information System (INIS)

    Duke, C.S.; Meyers-Schone, L.; Glum, S.R.; Quaider, W.

    1991-01-01

    The Fernald Environmental Management Project (FEMP), formerly the Feed Materials Production Center (FMPC), is a Department of Energy (DOE) facility located near Cincinnati, Ohio, which produced pure uranium metals from the early 1950s until 1989. DOE is currently conducting a Remedial Investigation/Feasibility Study (RI/FS) under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), in order to remediate environmental impacts at the site. DOE is also preparing an environmental impact statement under the National Environmental Policy Act (NEPA) to evaluate environmental impacts of proposed remedial actions. Both CERCLA and NEPA require evaluation of ecological risks of baseline conditions and proposed remedial actions. A preliminary assessment of ecological risks examined the potential effects of FEMP contaminants in one operable unit (OU) at the site, OU5, Environmental Media. Radionuclides of potential concern in OU5 soils include uranium, cesium, radium, strontium, technetium, and thorium. Chemicals detected in terrestrial organisms include aluminum, arsenic, barium, cadmium, lead, mercury, vanadium, and zinc, as well as radionuclides. Chemicals of potential concern in surface water include a variety of metals as well as uranium and technetium. Radionuclides in OU5 do not appear to pose a hazard to terrestrial organisms. Estimated radiation doses to aquatic organisms continually exposed to the maximum uranium concentrations observed in on-property drainages ranged from 40 to 4000 rad per year. However, off-property radionuclide concentrations are very low, and it is unlikely that organisms in streams adjacent to the FEMP are exposed to toxic levels. Maximum arsenic levels in vegetation collected from the FEMP are consistent with values reported in the literature to be toxic to certain plants. However, signs of stress have not been observed in vegetation on or adjacent to the FEMP

  2. Cost benefit analysis for remediation of a nuclear industry landfill

    International Nuclear Information System (INIS)

    Parker, Tom; Hardisty, Paul; Dennis, Frank; Liddiard, Mark; McClelland, Paul

    2006-01-01

    An old landfill site, licensed to receive inert construction waste, is situated on the top of hard rock cliffs adjacent to the sea at the Dounreay nuclear facility in Scotland. During restoration and investigation work at the landfill, radioactively contaminated material and asbestos was identified. UKAEA subsequently investigated the feasibility of remediating the landfill with the aim of removing any remaining radioactive or otherwise-contaminated material. The cost of landfill remediation would be considerable, making Cost Benefit Analysis (CBA) an ideal tool for assessing remediation options. The overall conclusion of the CBA, from a remedial decision making point of view, is that the remediation objective for the landfill should be to reduce any impacts to the current receptors through a comprehensive pathway control scheme. This would be considerably less expensive than even a limited source removal approach. Aggressive source removal objectives are not likely to be economic, even under the most conservative assumptions. A natural monitored attenuation approach will not be economic. All remediation options are considered assuming compliance with the existing regulatory requirements to monitor and cap the landfill before and after closure

  3. Cost benefit analysis for remediation of a nuclear industry landfill

    Energy Technology Data Exchange (ETDEWEB)

    Parker, Tom; Hardisty, Paul [WorleyParsons Komex, Bristol (United Kingdom); Dennis, Frank; Liddiard, Mark; McClelland, Paul [UKAEA, Dounreay (United Kingdom)

    2006-09-15

    An old landfill site, licensed to receive inert construction waste, is situated on the top of hard rock cliffs adjacent to the sea at the Dounreay nuclear facility in Scotland. During restoration and investigation work at the landfill, radioactively contaminated material and asbestos was identified. UKAEA subsequently investigated the feasibility of remediating the landfill with the aim of removing any remaining radioactive or otherwise-contaminated material. The cost of landfill remediation would be considerable, making Cost Benefit Analysis (CBA) an ideal tool for assessing remediation options. The overall conclusion of the CBA, from a remedial decision making point of view, is that the remediation objective for the landfill should be to reduce any impacts to the current receptors through a comprehensive pathway control scheme. This would be considerably less expensive than even a limited source removal approach. Aggressive source removal objectives are not likely to be economic, even under the most conservative assumptions. A natural monitored attenuation approach will not be economic. All remediation options are considered assuming compliance with the existing regulatory requirements to monitor and cap the landfill before and after closure.

  4. Environmental, Safety, and Health Plan for the remedial investigation/feasibility study at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Revision 1, Environmental Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    Davis, C. M.; El-Messidi, O. E.; Cowser, D. K.; Kannard, J. R.; Carvin, R. T.; Will, III, A. S.; Clark, Jr., C.; Garland, S. B.

    1993-05-01

    This Environmental, Safety, and Health (ES&H) Plan presents the concepts and methodologies to be followed during the remedial investigation/feasibility study (RI/FS) for Oak Ridge National Laboratory (ORNL) to protect the health and safety of employees, the public, and the environment. This ES&H Plan acts as a management extension for ORNL and Martin Marietta Energy Systems, Inc. (Energy Systems) to direct and control implementation of the project ES&H program. The subsections that follow describe the program philosophy, requirements, quality assurance measures, and methods for applying the ES&H program to individual waste area grouping (WAG) remedial investigations. Hazardous work permits (HWPs) will be used to provide task-specific health and safety requirements.

  5. The role of historical operations information for supporting remedial investigation work at the former Harshaw Chemical Site

    International Nuclear Information System (INIS)

    Johnson, R.; Peterson, J.; Picel, K.; Kolhoff, A.; Devaughn, J.

    2008-01-01

    In the early stages of hazardous, toxic, and radioactive waste (HTRW) site investigations, basic record searches are performed to help direct the agencies investigating contaminated sites to areas of concern and to identify contaminants of interest (COI). Plans developed on the basis of this preliminary research alone are often incomplete and result in unexpected discoveries either while in the field investigating the site or after the reports have been written. Many of the sites investigated under the Formerly Utilized Sites Remedial Action program (FUSRAP) have complex histories that are slowly uncovered over the life of the project. Because of programmatic constraints, nuances of these sites are often discovered late in their programs and result in increased expenditures in order to fully characterize the site, perform a robust feasibility study, and recommend appropriate alternatives for remediation. By identifying resources for public records, classified records, historic aerial photographs, and other sources of site-specific historical information, a process can be established to optimize the collection of information and to develop efficient and complete project plans. In many cases, interviews with past site employees are very useful tools. In combining what is found in the records, observed on historic aerial photographs, and heard from former employees and family members, teams investigating these sites can begin to compile sound and more complete conceptual site models (CSMs). The former Harshaw Chemical Site (HCS) illustrates this discovery process. HCS is part of FUSRAP. Preliminary investigations by the US Department of Energy (DOE) in the 1970s provided an initial CSM of activities that had taken place that may have resulted in contamination. The remedial investigation (RI) conducted by the US Army Corps of Engineers (USACE) was designed around this CSM. The RI work, however, identified a number of site conditions that were unexpected, including new

  6. Data Base Management Plan for the remedial investigation of Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1992-07-01

    The remedial investigation (RI) for Waste Area Grouping (WAG) 5 will involve gathering, verifying, analyzing, reporting, and archiving numerous types of field and analytical data. Field investigations will produce data documenting surficial and geophysical surveys, geologic and hydrogeologic logs, aquifer tests, water level measurements, geophysical logs, and stream and seepage flow measurements. Laboratory analyses will be performed on soil, surface water, groundwater, and sediment samples collected during field investigations. All data resulting from these activities will be contained in the Bechtel RI/feasibility study (FS) project data base and will be managed in accordance with the RI/FS Data Base Management Plan and this WAG-specific plan. This Data Base Management Plan describes the gathering, verifying, analyzing, reporting, and archiving of data generated during Bechtel's remedial investigation of Waste Area Grouping 5. This investigation will produce data documenting surficial surveys, geophysical surveys, geologic and hydrologic logs, aquifer tests, water level measurements, geophysical logs, and stream and seep flow measurements. Also, laboratory analyses will be performed on soil, surface water, groundwater, and sediment samples. The 1500 series of Bechtel project procedures, ''Data Base Management,'' and the project Data Base Management Plan will be used to ensure that data are handled properly

  7. Environmental restoration disposal facility applicable or relevant and appropriate requirements study report. Revision 00

    International Nuclear Information System (INIS)

    Roeck, F.V.; Vedder, B.L.; Rugg, J.E.

    1995-10-01

    The Environmental Restoration Disposal Facility (ERDF) will be a landfill authorized under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) and will comply with the Resource Conservation and Recovery Act of 1976 (RCRA) substantive requirements. The facility will also comply with applicable or relevant and appropriate requirements (ARAR), including portions of the U.S. Environmental Protection Agency (EPA) regulations, Washington Administrative Code (WAC), and to-be-considered (TBC) elements such as U.S. Department of Energy (DOE) Orders. In considering the requirements of CERCLA, a detailed analysis of various alternatives for ERDF was completed using the nine CERCLA criteria, National Environmental Policy Act of 1969 (NEPA), and public comments. The ERDF record of decision (ROD) selected an alternative that includes a RCRA-compliant double-lined trench for the disposal of radioactive, hazardous, and mixed wastes resulting from the remediation of operable units (OU) within the National Priorities List (NPL) sites in the 100, 200, and 300 Areas. Only wastes resulting from the remediation of Hanford NPL sites will be allowed in the ERDF. Of the various siting and design alternatives proposed for ERDF, the selected alternative provides the best combination of features by balancing the nine CERCLA criteria, ARAR compliance, environmentally protective site, and various stakeholder and public recommendations. The ERDF trench design, compliant with RCRA Subtitle C minimum technical requirements (MTR), will be double lined and equipped with a leachate collection system. This design provides a more reliable system to protect groundwater than other proposed alternatives. The ERDF is located on the Hanford Site Central Plateau, southeast of the 200 West Area

  8. Department of Energy Hazardous Waste Remedial Actions Program

    International Nuclear Information System (INIS)

    Franco, P.J.

    1989-01-01

    This paper discusses the hazardous waste remedial actions program (HAZWRAP) which manages approximately 200 hazardous waste projects. These projects include preliminary assessments, site inspections, and remedial investigation/feasibility studies. The author describes the procedures HAZWRAP follows to ensure quality. The discussion covers the quality assurance aspects of project management, project planning, site characterization, document control and technical teamwork

  9. Focused feasibility study of engineered barriers for waste management units in the 200 areas

    International Nuclear Information System (INIS)

    1996-05-01

    The U.S. Department of Energy (DOE) at the Hanford Site in Washington State is organized into numerically designated operational areas consisting of the 100, 200, 300, 400, 600, and 1100 Areas. In November 1989, the U.S. Environmental Protection Agency (EPA) included the 200 Areas (as well as the 100, 300, and 1,100 Areas) of the Hanford Site on the National Priorities List (NPL) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Inclusion on the NPL initiates the remedial investigation (RI) and feasibility study (FS) process to characterize the nature and extent of contamination, assess risks to human health and the environment, and select remedial actions. The Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) was developed and signed by representatives from the EPA, Washington State Department of Ecology (Ecology), and DOE in May 1989 to provide a framework to implement and integrate cleanup activities. The scope of the agreement covers CERCLA past-practice, Resource Conservation and Recovery Act of 1976 (RCRA) past-practice, and RCRA treatment, storage, and disposal (TSD) activities on the Hanford Site. The 1991 revision to the Tri-Party Agreement required that an aggregate area approach be implemented in the 200 Areas based on the Hanford Site Past-Practice Strategy (HPPS) and established a milestone (M-27-00) to complete 10 Aggregate Area Management Study (AAMS) Reports in 1992

  10. RCRA Facility Investigation/Remedial Investigation Report with Baseline Risk Assessment for the Central Shops Burning/Rubble Pit (631-6G), Volume 1 Final

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-04-01

    The Burning/Rubble Pits at the Savannah River Site were usually shallow excavations approximately 3 to 4 meters in depth. Operations at the pits consisted of collecting waste on a continuous basis and burning on a monthly basis. The Central Shops Burning/Rubble Pit 631- 6G (BRP6G) was constructed in 1951 as an unlined earthen pit in surficial sediments for disposal of paper, lumber, cans and empty galvanized steel drums. The unit may have received other materials such as plastics, rubber, rags, cardboard, oil, degreasers, or drummed solvents. The BRP6G was operated from 1951 until 1955. After disposal activities ceased, the area was covered with soil. Hazardous substances, if present, may have migrated into the surrounding soil and/or groundwater. Because of this possibility, the United States Environmental Protection Agency (EPA) has designated the BRP6G as a Solid Waste Management Unit (SWMU) subject to the Resource Conservation Recovery Act/Comprehensive Environmental Response, Compensation and Liability Act (RCRA/CERCLA) process.

  11. 40 CFR 35.419 - Purpose.

    Science.gov (United States)

    2010-07-01

    ... enhance the response program of the State; capitalize a revolving loan fund for Brownfield remediation under section 104(k)(3) of CERCLA; or purchase insurance or develop a risk sharing pool, an indemnity pool, or insurance mechanism to provide financing for response actions under a State response program. ...

  12. 40 CFR 35.736 - Purpose.

    Science.gov (United States)

    2010-07-01

    ... establish or enhance the response program of the Tribe; capitalize a revolving loan fund for brownfield remediation under section 104(k)(3) of CERCLA; or purchase insurance or develop a risk sharing pool, an indemnity pool, or insurance mechanism to provide financing for response actions under a Tribal response...

  13. White Oak Creek Watershed: Melton Valley Area Remedial Investigation Report, Oak Ridge National Laboratory, Oak Ridge, Tennessee: Volume 1 Main Text

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-11-01

    The purpose of this Remedial Investigation (RI) report is to present an analysis of the Melton Valley portion of the White Oak Creek (WOC) watershed, which will enable the US Department of Energy (DOE) to pursue a series of cost-effective remedial actions resulting in site cleanup and stabilization. In this RI existing levels of contamination and radiological exposure are compared to levels acceptable for future industrial and potential recreational use levels at the site. This comparison provides a perspective for the magnitude of remedial actions required to achieve a site condition compatible with relaxed access restrictions over existing conditions. Ecological risk will be assessed to evaluate measures required for ecological receptor protection. For each subbasin, this report will provide site-specific analyses of the physical setting including identification of contaminant source areas, description of contaminant transport pathways, identification of release mechanisms, analysis of contaminant source interactions with groundwater, identification of secondary contaminated media associated with the source and seepage pathways, assessment of potential human health and ecological risks from exposure to contaminants, ranking of each source area within the subwatershed, and outline the conditions that remedial technologies must address to stop present and future contaminant releases, prevent the spread of contamination and achieve the goal of limiting environmental contamination to be consistent with a potential recreational use of the site.

  14. White Oak Creek Watershed: Melton Valley Area Remedial Investigation Report, Oak Ridge National Laboratory, Oak Ridge, Tennessee: Volume 1 Main Text

    International Nuclear Information System (INIS)

    1996-11-01

    The purpose of this Remedial Investigation (RI) report is to present an analysis of the Melton Valley portion of the White Oak Creek (WOC) watershed, which will enable the US Department of Energy (DOE) to pursue a series of cost-effective remedial actions resulting in site cleanup and stabilization. In this RI existing levels of contamination and radiological exposure are compared to levels acceptable for future industrial and potential recreational use levels at the site. This comparison provides a perspective for the magnitude of remedial actions required to achieve a site condition compatible with relaxed access restrictions over existing conditions. Ecological risk will be assessed to evaluate measures required for ecological receptor protection. For each subbasin, this report will provide site-specific analyses of the physical setting including identification of contaminant source areas, description of contaminant transport pathways, identification of release mechanisms, analysis of contaminant source interactions with groundwater, identification of secondary contaminated media associated with the source and seepage pathways, assessment of potential human health and ecological risks from exposure to contaminants, ranking of each source area within the subwatershed, and outline the conditions that remedial technologies must address to stop present and future contaminant releases, prevent the spread of contamination and achieve the goal of limiting environmental contamination to be consistent with a potential recreational use of the site

  15. The effect of CO2 on the plasma remediation of NxOy

    Science.gov (United States)

    Gentile, Ann C.; Kushner, Mark J.

    1996-04-01

    Plasma remediation is being investigated for the removal of oxides of nitrogen (NxOy) from atmospheric pressure gas streams. In previous works we have investigated the plasma remediation of NxOy from N2/O2/H2O mixtures using repetitively pulsed dielectric barrier discharges. As combustion effluents contain large percentages of CO2, in this paper we discuss the consequences of CO2 in the gas mixture on the efficiency of remediation and on the end products. We find that there is a small increase in the efficiency of total NxOy remediation (molecules/eV) with increasing CO2 fraction, however the efficiency of NO remediation alone generally decreases with increasing CO2. This differential is more pronounced at low energy deposition per pulse. More remediation occurs through the reduction channel with increasing CO2 while less NO2 and HNOx are produced through the oxidation channel. CO is produced by electron impact of CO2 though negligible amounts of cyanides are generated.

  16. Successful completion of a RCRA closure for the Fernald Environmental Management Project

    International Nuclear Information System (INIS)

    Lippitt, J.M.; Kolthoff, K.

    1995-01-01

    This paper discusses the successful completion of a RCRA (Resource Conservation and Recovery Act) closure of a HF (hydrofluoric acid) tank car at FEMP, which is on the national priorities list of hazardous waste sites and is undergoing CERCLA remediation. The HF tank car closure was conducted by FERMCO. Through a combination of sound planning and team work, the HF tank car was closed safely and ahead of schedule. During > 22,000 hr field work required for construction modifications and neutralization of 9,600 gallons of HF and decontamination rinseates, there were no OSHA recordable incidents. The system design avoided additional costs by maximizing use of existing equipment and facilities. This successful closure of the HF tank car demonstrates FEMP's commitment to reducing risks and cleaning up the facility in a manner consistent with objectives of RCRA regulations and the Ohio EPA hazardous waste rules. This in turn facilitated ongoing negotiations with Ohio EPA to integrate RCRA closure and the ongoing CERCLA remediation activities. This paper addresses why the unit was clean closed under an approved RCRA Closure Plan. Integration of EPA regulations for RCRA and CERCLA programs and the DOE-Orders impacting design, construction and operation of an acid neutralization system is also reviewed. The paper concludes with a discussion of lessons learned in the process in preparing the closure plant and through final project close out

  17. Remedial investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-07-01

    To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODs) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regimes, which are labeled as integrator OUs. This remedial investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the feasibility study to evaluate all probable or likely alternatives

  18. Remedial Investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-09-01

    To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODS) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regime's, which are labeled as integrator OUs. This Remedial Investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the Feasibility Study to evaluate all probable or likely alternatives

  19. Remedial Investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1993-09-01

    To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODS) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regime`s, which are labeled as integrator OUs. This Remedial Investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the Feasibility Study to evaluate all probable or likely alternatives.

  20. Remedial investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1993-07-01

    To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODs) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regimes, which are labeled as integrator OUs. This remedial investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the feasibility study to evaluate all probable or likely alternatives.

  1. Procedures for ground-water investigations

    International Nuclear Information System (INIS)

    1989-09-01

    This manual was developed by the Pacific Northwest Laboratory (PNL) to document the procedures used to carry out and control the technical aspects of ground-water investigations at the PNL. Ground-water investigations are carried out to fulfill the requirements for the US Department of Energy (DOE) to meet the requirements of DOE Orders. Investigations are also performed for various clients to meet the requirements of the Resource Conservation and Recovery Act of 1976 (RCRA) and the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA). National standards including procedures published by the American Society for Testing and Materials (ASTM) and the US Geological Survey were utilized in developing the procedures contained in this manual

  2. Pit 9 project: A private sector initiative

    International Nuclear Information System (INIS)

    Macdonald, D.W.; Hughes, F.P.; Burton, B.N.

    1993-01-01

    This report discusses the Pit 9 Comprehensive Demonstration which is intended to demonstrate a cost-effective approach to remediate an Idaho National Engineering Laboratory (INEL) waste disposal pit through a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Interim Action. The remediation will include additional requirements, if needed, to provide high confidence that only minor additional work would be necessary to accomplish the final closure as part of the overall final closure strategy for the INEL's Subsurface Disposal Area (SDA)

  3. In-situ remediation of TCE by ERD in clay tills. Feasibility and performance of full-scale application insights gained through an integrated investigative approach for 2 sites

    DEFF Research Database (Denmark)

    Broholm, Mette Martina; Damgaard, Ida; Chambon, Julie Claire Claudia

    -scale applications of ERD in clay tills were investigated in a research project in-cluding 2 sites in Denmark undergoing remediation since 2006. Site remediation approach. At the Sortebrovej site an emulsified oil donor (EOS) and a bio-augmentation culture (KB1®) with specific degraders Dehalococcoides were injected......Background/Objectives. Remediation of trichloroethene (TCE) in clay and other low permeabil-ity geologic media, where groundwater flow occurs preferentially in higher permeability sand lenses or fractures, is a significant challenge. At older sites, much of the contaminant mass is pre......-sent as a sorbed phase in the matrix due to matrix diffusion. The principal challenge for in situ remediation in clay is to achieve effective contact between contaminant and bioremediation addi-tives (e.g., organic electron donors and bioaugmentation cultures). The feasibility and perfor-mance of full...

  4. Managerial response to stockouts: the effect of remedies on consumer behavior

    Directory of Open Access Journals (Sweden)

    Ester Quirino Dias Sampaio

    2016-03-01

    Full Text Available Abstract Stockouts remain a significant problem for retail firms. Estimates of stockout rates in the past fifty years consistently averaged approximately 8 percent. The consequences of stockouts transcend the retail store to include its supporting supply chain. In addition to the effect on the behavior of consumers, stockouts can impact the firm’s replenishment policy, the level and location of inventories and the cost of emergency shipments required to replenish out-of-stock items. Although there is a substantive literature in logistics that measures the frequency of and the consumer response to stockouts, investigation of the effect of remedies on consumer response is sparse. To address this problem, the effectiveness of five remedies as tools to manage retail stockouts was investigated: apology, raincheck, home delivery, trade-up and discount. A remedy is an incentive to induce consumers to not leave a store in response to a stockout. In addition the influence of consumer characteristics (i.e., brand loyalty and shopping situations (i.e., urgency of purchase on the effect of each remedy on consumer behavior was examined. The results suggest that the remedies are usually effective. The most effective remedy is home delivery. The least effective remedy is a simple apology, which may actually increase the percentage of consumers leaving the store. The results also indicate that the urgency of the purchase and store loyalty have the most impact on remedy effectiveness. These results suggest that there are significant opportunities to use remedies as tools to manage the effect of stockouts on retail stores and their supporting supply chains.

  5. RCRA Facility Investigation report for Waste Area Grouping 6 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1991-09-01

    WAG 6 comprises a shallow land burial facility used for disposal of low-level radioactive wastes (LLW) and, until recently, chemical wastes. As such, the site is subject to regulation under RCRA and the Comprehensive Environmental Response Compensation and Liability Act (CERCLA). To comply with these regulations, DOE, in conjunction with the Environmental Protection Agency (EPA) and the Tennessee Department of Environment and Conservation (TDEC), developed a strategy for closure and remediation of WAG 6 by 1997. A key component of this strategy was to complete an RFI by September 1991. The primary objectives of the RFI were to evaluate the site's potential human health and environmental impacts and to develop a preliminary list of alternatives to mitigate these impacts. The WAG 6 one of three solid waste management units evaluated Oak Ridge National Laboratory (ORNL) existing waste disposal records and sampling data and performed the additional sampling and analysis necessary to: describe the nature and extent of contamination; characterize key contaminant transport pathways; and assess potential risks to human health and the environment by developing and evaluating hypothetical receptor scenarios. Estimated excess lifetime cancer risks as a result for exposure to radionuclides and chemicals were quantified for each hypothetical human receptor. For environmental receptors, potential impacts were qualitatively assessed. Taking into account regulatory requirements and base line risk assessment results, preliminary site closure and remediation objectives were identified, and a preliminary list of alternatives for site closure and remediation was developed

  6. Bald eagle site management plan for the Hanford Site, south-central Washington

    International Nuclear Information System (INIS)

    Fitzner, R.F.; Weiss, S.G.

    1994-12-01

    The CERCLA remedial investigations of waste sites on the Hanford Site will involve lands containing or adjacent to a bald eagle nest, winter concentration areas, or communal night roost. Because these CERCLA investigations may affect bald eagles, the DOE has prepared this Bald Eagle Site Management Plan (BESMP). However, it is intended that this BESMP be used or updated so as to be also applicable to future activities that affect bald eagles on the Hanford Site. Bald eagles regularly use the US Department of Energy's (DOE) Hanford Site in south-central Washington State during winter months for roosting, perching, and foraging. Each of these activities requires buffer zones to protect eagles from human disturbances. Buffer zones developed in this plan follow recommended guidelines and are intended to be used in planning. If Hanford Site activities in the vicinity of identified bald eagle use areas are carried out in accordance with this plan, such actions are not likely to adversely affect the eagles or their habitat. Activities that may be exceptions will involve informal or formal (whichever is appropriate) consultation with the US Fish and Wildlife Service as required by the Endangered Species Act

  7. WAG 2 remedial investigation and site investigation site-specific work plan/health and safety checklist for the ecological assessment task, Kingfisher Study

    International Nuclear Information System (INIS)

    Holt, V.L.; Baron, L.A.

    1994-05-01

    This report provides specific details and requirements for the WAG 2 remedial investigation and site investigation Ecological Assessment Task, Kingfisher Study, including information that will contribute to safe completion of the project. The report includes historical background; a site map; project organization; task descriptions and hazard evaluations; controls; and monitoring, personal protective equipment, decontamination, and medical surveillance program requirements. The report also includes descriptions of site personnel and their certifications as well as suspected WAG 2 contaminants and their characteristics. The primary objective of the WAG 2 Kingfisher Study is to assess the feasibility of using kingfishers as biological monitors of contaminants on the Oak Ridge Reservation (ORR). Kingfisher sample collection will be used to determine the levels of contaminants and degree of bioaccumulation within a common piscivorous bird feeding on contaminated fish from streams on the ORR

  8. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 2. Appendixes A, B, C, D

    International Nuclear Information System (INIS)

    1995-09-01

    This document contains appendices A (water characterization), B (sediment characterization), C (biota Characterization), D (applicable or relevant and appropriate requirements) from the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy's Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include 137 Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and 137 Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River

  9. Remedial investigation/feasibility study for the Clinch River/Poplar Creek operable unit. Volume 2. Appendixes A, B, C, D

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    This document contains appendices A (water characterization), B (sediment characterization), C (biota Characterization), D (applicable or relevant and appropriate requirements) from the combined Remedial Investigation/Feasibility Study Report for the Clinch River/Poplar Crack (CR/PC) Operable Unit (OU). The CR/PC OU is located in Anderson and Roane Counties, Tennessee and consists of the Clinch River and several of its embayments in Melton Hill and Watts Bar Reservoirs. These waters have received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act. A remedial investigation has been conducted to determine the current nature and extent of any contamination and to assess the resulting risk to human health and the environment. The feasibility study evaluates remedial action alternatives to identify any that are feasible for implementation and that would effectively reduce risk. Historical studies had indicated that current problems would likely include {sup 137}Cs in sediment of the Clinch River, mercury in sediment and fish of Poplar Creek and PCBs and pesticides in fish from throughout the OU. Peak releases of mercury and {sup 137}Cs occurred over 35 years ago, and current releases are low. Past releases of PCBs from the ORR are poorly quantified, and current releases are difficult to quantify because levels are so low. The site characterization focused on contaminants in surface water, sediment, and biota. Contaminants in surface water were all found to be below Ambient Water Quality Criteria. Other findings included the following: elevated metals including cesium 137 and mercury in McCoy Branch sediments; PCBs and chlordane elevated in several fish species, presenting the only major human health risk, significant ecological risks in Poplar Creek but not in the Clinch River.

  10. Phase 1 and 2 feasibility study report for the 300-FF-1 Operable Unit

    Energy Technology Data Exchange (ETDEWEB)

    1993-11-01

    The 300-FF-1 Operable Unit (OU) feasibility study (FS) presented in this document completes the FS process only through the first two study phases: Phase I, Remedial Alternatives Development, and Phase II, Remedial Alternatives Screening in accordance with CERCIA guidance for performing Remedial Investigations and Feasibility Studies (RI/FS) (EPA 1988a). This Phase I/II study provides a generalized view of workable remedial technologies as applied to the site contamination problems as a whole. Phase III, Detailed Analysis of Alternatives, will be performed at a later date to further evaluate screened alternatives based on the nine criteria in the CERCLA RI/FS guidance. The purpose of this Phase I/II FS is to develop and screen a range of alternatives for remediation of contamination present in the vadose zone of the 300-FF-1 OU. The scope of work for this Phase I/II FS includes five primary tasks: 1. Review existing documents and their associated data from relevant investigations and studies; 2. Establish remedial action objectives (RAO) and general response actions (GRA); 3. Identify applicable or relevant and appropriate requirements (ARARS) pertinent to all general response actions (including waste disposal); 4. Develop remedial alternatives (Phase I) applicable to the 300-FF-1 OU including identification and screening of technologies and process options, and assembly of remedial alternatives from representative technology types; 5. Screen alternatives (Phase II) developed in Phase I for implementability, effectiveness, and cost to identify those alternatives which warrant advancement to the detailed analysis phase (Phase III) of the FS.

  11. Natural resources damage assessments at Department of Energy facilities - using the CERCLA process to minimize natural resources injuries

    International Nuclear Information System (INIS)

    Bascietto, J.J.; Martin, J.F.; Duke, C.S.; Gray, S.I.

    1991-01-01

    Fifty years of research, development and production in support of national defense have left the Department of Energy (DOE) with numerous radioactive, hazardous and mixed waste sites requiring environmental restoration and remediation. The responsibilities for DOE associated with releases of these wastes into the environment are driving major efforts to characterize contamination problems and identify and implement environmental restoration and remediation alternatives. The subject of this paper is the recently issued DOE guidance to minimize the basis for damage claims for injuries to natural resources on, over and under lands owned or controlled by DOE associated with the releases of hazardous substances from DOE facilities. Depending on the regulatory authority governing the facility, the preferred means of evaluating the possibility of injury to natural resources is the preparation of an ecological risk assessment or an environmental evaluation. As both the natural resource trustee and lead agency at facilities under its control, DOE receives dual responsibility requiring site remediation if necessary, and that any injured natural resources be restored, or that compensation for the injuries is made. Several executive and legislative sources of authority and responsibility with regard to lead agencies and trustees of natural resources will be detailed. Also, ongoing remedial investigation/feasibility study work at the DOE Fernald Environmental Management Project near Fernald, Ohio will be described as an example of how this guidance can be applied

  12. Investigation on reusing water treatment residuals to remedy soil contaminated with multiple metals in Baiyin, China

    International Nuclear Information System (INIS)

    Wang, Changhui; Zhao, Yuanyuan; Pei, Yuansheng

    2012-01-01

    Highlights: ► Fe/Al water treatment residuals (FARs) can stabilize As, Pb, Ni, Zn, Cr and Cu. ► FARs cannot stabilize Ba and Cd. ► The properties of FARs and soil affect the FARs’ ability of stabilizing metals. - Abstract: In this work, the remediation of soils contaminated with multiple metals using ferric and alum water treatment residuals (FARs) in Baiyin, China, was investigated. The results of metals fractionation indicated that after the soil was treated with FARs, arsenic (As), lead (Pb), nickel (Ni), zinc (Zn) and copper (Cu) could be transformed into more stable forms, i.e., As bound in crystalline Fe/Al oxides and other metals in the oxidable and residual forms. However, the forms of chromium (Cr) and cadmium (Cd) were unaffected. Interestingly, due to the effect of FARs, barium (Ba) was predominantly transformed into more mobile forms. The bioaccessibility extraction test demonstrated that the FARs reduced the bioaccessibility of As by 25%, followed by Cu, Cr, Zn, Ni and Pb. The bioaccessibility of Cd and Ba were increased; in particular, there was an increase of 41% for Ba at the end of the test. In conclusion, the FARs can be used to remedy soil contaminated with multiple metals, but comprehensive studies are needed before practical applications of this work.

  13. Hanford Site Groundwater Monitoring for Fiscal Year 2002

    Energy Technology Data Exchange (ETDEWEB)

    Hartman, Mary J.; Morasch, Launa F.; Webber, William D.

    2003-02-28

    This report presents the results of groundwater and vadose zone monitoring and remediation for fiscal year 2002 on the U.S. Department of Energy's Hanford Site in Washington State. This report is written to meet the requirements in CERCLA, RCRA, the Atomic Energy Act of 1954, and Washington State Administrative Code.

  14. Meeting the requirements for a DOE environmental restoration project. The Fernald strategy

    International Nuclear Information System (INIS)

    Vanoss, R.L.; Risenhoover, G.M.

    1994-01-01

    Environmental Restoration (ER) of five Operable Units (OU) at Fernald Environmental Management Project (FEMP) includes compliance with the requirements of Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), Resource Conservation Recovery Act (RCRA), National Environmental Policy Act (NEPA), and DOE Orders. Each regulatory driver has differing procedural requirements for documenting calculations, decisions, and actions involved in site cleanup. Integration of documentation and avoidance of duplication can save time and money. Such savings are being achieved by OU specific application of supporting studies, revised procedures, and guidance documents. Each OU is seeking appropriate opportunities to produce single documents that simultaneously fulfill the important requirements of the other regulations and DOE orders. These opportunities are evaluated at all phases of decision making, remedial design, and remedial action. Three essential processes precede environmental restoration/remedial action at a DOE site/project: 1. Completion of decision-making documents required by governing or applicable statutes. 2. Completion of important scientific and engineering analyses of remedial alternatives, and design and implementation of the remedial solution established in the CERCLA Record of Decision (ROD). 3. Preparation of DOE-mandated documentation to record engineering evaluations and cost estimates required for budgeting, decision making, and project management. Methodology and requirements for each process have developed from long, successful practice, but independently of each other. FERMCO, as new DOE contractor at Fernald and first Environmental Restoration Management Contractor (ERMC), is committed to a process of Continuous Performance Improvement (CPI). A major reevaluation of documentation and processes for support of environmental decision-making and design of cleanup activities to remediate the five OUs at the FEMP is being undertaken

  15. 32 CFR 516.64 - Comprehensive remedies plan.

    Science.gov (United States)

    2010-07-01

    ... AND PUBLIC RELATIONS LITIGATION Remedies in Procurement Fraud and Corruption § 516.64 Comprehensive... investigation involving fraud or corruption that relates to Army procurement activities. When possible, these... participation of the appropriate criminal investigators and other relevant personnel such as the contracting...

  16. Microbial fuel cell driving electrokinetic remediation of toxic metal contaminated soils.

    Science.gov (United States)

    Habibul, Nuzahat; Hu, Yi; Sheng, Guo-Ping

    2016-11-15

    An investigation of the feasibility of in-situ electrokinetic remediation for toxic metal contaminated soil driven by microbial fuel cell (MFC) is presented. Results revealed that the weak electricity generated from MFC could power the electrokinetic remediation effectively. The metal removal efficiency and its influence on soil physiological properties were also investigated. With the electricity generated through the oxidation of organics in soils by microorganisms, the metals in the soils would mitigate from the anode to the cathode. The concentrations of Cd and Pb in the soils increased gradually through the anode to the cathode regions after remediation. After about 143days and 108 days' operation, the removal efficiencies of 31.0% and 44.1% for Cd and Pb at the anode region could be achieved, respectively. Soil properties such as pH and soil conductivity were also significantly redistributed from the anode to the cathode regions. The study shows that the MFC driving electrokinetic remediation technology is cost-effective and environmental friendly, with a promising application in soil remediation. Copyright © 2016 Elsevier B.V. All rights reserved.

  17. 19 CFR 210.67 - Remedy, the public interest, and bonding.

    Science.gov (United States)

    2010-04-01

    ... 19 Customs Duties 3 2010-04-01 2010-04-01 false Remedy, the public interest, and bonding. 210.67 Section 210.67 Customs Duties UNITED STATES INTERNATIONAL TRADE COMMISSION INVESTIGATIONS OF UNFAIR PRACTICES IN IMPORT TRADE ADJUDICATION AND ENFORCEMENT Temporary Relief § 210.67 Remedy, the public interest...

  18. FUSRAP adapts to the amendments of Superfund

    International Nuclear Information System (INIS)

    Atkin, R.G.; Liedle, S.D.; Clemens, B.W.

    1988-01-01

    With the promulgation of the Superfund Amendments and Reauthorization Act (SARA) federal facilities were required to comply with the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) in the same manner as any non-government entity. This situation presented challenges for the Department of Energy (DOE) and other federal agencies involved in remedial action work because of the requirements under SARA that overlap other laws requiring DOE compliance, e.g., the National Environmental Policy Act (NEPA). This paper outlines options developed to comply with CERCLA and NEPA as part of an active, multi-site remedial action program. The program, the Formerly Utilized Sites Remedial Action Program (FUSRAP), was developed to identify, clean up, or control sites containing residual radioactive contamination resulting from the nation's early development of nuclear power. During the Manhattan Project, uranium was extracted from domestic and foreign ores and resulted in mill concentrates, purified metals, and waste products that were transported for use or disposal at other locations. Figure 1 shows the steps for producing uranium metal during the Manhattan Project. As a result of these activities materials equipment, buildings, and land became contaminated, primarily with naturally occurring radionuclides. Currently, FUSRAP includes 29 sites; three are on the Environmental Protection Agency's (EPA's) National Priorities List (NPL) of hazardous waste sites

  19. Electrodialytic soil remediation

    DEFF Research Database (Denmark)

    Karlsmose, Bodil; Ottosen, Lisbeth M.; Hansen, Lene

    1999-01-01

    The paper gives an overview of how heavy metals can be found in the soil and the theory of electrodialytic remediation. Basically electrodialytic remediation works by passing electric current through the soil, and the heavy metals in ionic form will carry some of the current. Ion-exchange membranes...... prevents the protons and the hydroxides ions from the electrode processes to enter the soil. The heavy metals are collected in a concentration compartment, which is separated from the soil by ion-exchange membranes. Examples from remediation experiments are shown, and it is demonstrated that it is possible...... to remediate soil polluted with heavy metals be this method. When adding desorbing agents or complexing agents, chosing the right current density, electrolyte and membranes, the proces can be optimised for a given remediation situation. Also electroosmosis is influencing the system, and if extra water...

  20. Comparison of the environmental impacts of two remediation technologies used at hydrocarbon contaminated sites

    International Nuclear Information System (INIS)

    Viikala, R.; Kuusola, J.

    2000-01-01

    Investigation and remediation of contaminated sites has rapidly increased in Finland during the last decade. Public organisations as well as private companies are investigating and remediating their properties, e.g. redevelopment or business transactions. Also numerous active and closed gasoline stations have been investigated and remediated during the last few years. Usually the contaminated sites are remediated to limit values regardless of the risk caused by contamination. The limit values currently used in Finland for hydrocarbon remediation at residential or ground water areas are 300 mg/kg of total hydrocarbons and 100 mg/kg of volatile hydrocarbons (boiling point < appr. 200 deg C). Additionally, compounds such as aromatic hydrocarbons have specific limit values. Remediation of hydrocarbon contaminated sites is most often carried out by excavating the contaminated soil and taking it to a landfill by lorries. As distances from the sites to landfills are generally rather long, from tens of kilometres to few hundred kilometres, it is evident that this type of remediation has environmental impacts. Another popular technology used at sites contaminated by volatile hydrocarbons is soil vapour extraction (SVE). SVE is a technique of inducing air flow through unsaturated soils by vapour extraction wells or pipes to remove organic contaminants with an off-gas treatment system. The purpose of this study was to evaluate some of the environmental impacts caused by remediation of hydrocarbon contaminated soil. Energy consumption and air emissions related remedial activities of the two methods were examined in this study. Remediation of the sites used in this study were carried out by Golder Associates Oy in different parts of Finland in different seasons. Evaluation was made by using life cycle assessment based approach

  1. Radon remedial actions in schools of Friuli Venezia Giulia region (NE Italy)

    International Nuclear Information System (INIS)

    Giovani, C.; Cappelletto, C.; Garavaglia, M.; Pividore, S.; Villalta, R.

    2004-01-01

    In the last four years the Regional Agency of Environmental Protection (ARPA) of Friuli Venezia Giulia carried out a survey to determine the radon concentration in the schools of the area. During the survey all the 1320 schools and kindergartens of the region were investigated with more than 5000 measurements. In about 2% of cases, radon concentrations exceeded the reference levels of Italian law and remedial actions were performed. In collaboration with the Building Engineering Department of Udine University, ARPA FVG edited a manual concerning indications and proposals for building protection against radon. The environmental physics section of ARPA FVG, was heavily involved in the remedial action, both in the design of the action and in the investigation of effectiveness. In more than 20 schools the owners following ARPA indications solved the problem of high radon concentrations. In this paper the authors report the main type of applied remedial actions grouped taking into account the different remedial methodology. In Friuli Venezia Giulia region the main radon source is represented by soil. The contribution of building materials to high radon concentrations is negligible. The most common remedial actions consisted in natural or artificial depressurization of the soil or the crawlspace with respect to indoor building. Sometimes air was pumped into the building or air exchange number was increased. The authors show in detail the design of the performed investigations: these involved different measurement sets with passive electrets and active instruments for continuous data collection. Measurements usually last 3 contiguous weeks and are followed by long period measurements with solid track detectors. Optimization of remedial action performance was investigated when remedial action consisted in active air extraction from the soil under the buildings and fan time regulation was possible. Very often simple and cheap actions allowed a reduction of 90% in radon

  2. Strategic planning for remediation projects

    International Nuclear Information System (INIS)

    Tapp, J.W.

    1995-01-01

    Remediation projects may range from a single leaking storage tank to an entire plant complex or producing oil and gas field. Strategic planning comes into play when the contamination of soil and groundwater is extensive. If adjacent landowners have been impacted or the community at large is concerned about the quality of drinking water, then strategic planning is even more important. (1) To manage highly complex interrelated issues--for example, the efforts expended on community relations can alter public opinion, which can impact regulatory agency decisions that affect cleanup standards, which can...and so on. (2) To ensure that all potential liabilities are managed--for example, preparation for the defense of future lawsuits is essential during site investigation and remediation. (3) To communicate with senior management--when the remediation team provides a strategic plan that includes both technical and business issues, senior management has the opportunity to become more involved and make sound policy decisions. The following discusses the elements of a strategic plan, who should participate in it, and the issues that should be considered

  3. 40 CFR 35.6570 - Use of the same engineer during subsequent phases of response.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Use of the same engineer during... Agreement § 35.6570 Use of the same engineer during subsequent phases of response. (a) If the public notice... CERCLA remedial response Cooperative Agreement may use the engineer procured to conduct any or all of the...

  4. WSSRAP chemical plant geotechnical investigations for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1990-12-01

    This document has been prepared for the United states Department of Energy (DOE) Weldon Spring Site Remedial Action Project (WSSRAP) by the Project Management Contractor (PMC), which consists of MK-Ferguson Company (MKF) and Morrison Knudsen Corporation Environmental Services Group (MKES) with Jacobs Engineering Group (JEG) as MKF's predesignated subcontractor. This report presents the results of site geotechnical investigations conducted by the PMC in the vicinity of the Weldon Spring chemical plant and raffinate pits (WSCP/RP) and in potential on-site and off-site clayey material borrow sources. The WSCP/RP is the proposed disposal cell (DC) site. 39 refs., 24 figs., 12 tabs

  5. Geostatistical approach for assessing soil volumes requiring remediation: validation using lead-polluted soils underlying a former smelting works.

    Science.gov (United States)

    Demougeot-Renard, Helene; De Fouquet, Chantal

    2004-10-01

    Assessing the volume of soil requiring remediation and the accuracy of this assessment constitutes an essential step in polluted site management. If this remediation volume is not properly assessed, misclassification may lead both to environmental risks (polluted soils may not be remediated) and financial risks (unexpected discovery of polluted soils may generate additional remediation costs). To minimize such risks, this paper proposes a geostatistical methodology based on stochastic simulations that allows the remediation volume and the uncertainty to be assessed using investigation data. The methodology thoroughly reproduces the conditions in which the soils are classified and extracted at the remediation stage. The validity of the approach is tested by applying it on the data collected during the investigation phase of a former lead smelting works and by comparing the results with the volume that has actually been remediated. This real remediated volume was composed of all the remediation units that were classified as polluted after systematic sampling and analysis during clean-up stage. The volume estimated from the 75 samples collected during site investigation slightly overestimates (5.3% relative error) the remediated volume deduced from 212 remediation units. Furthermore, the real volume falls within the range of uncertainty predicted using the proposed methodology.

  6. Report on investigation of remedial measures for the radiation reduction and radioactive decontamination of Elliot Lake, Ontario

    International Nuclear Information System (INIS)

    1981-02-01

    This is the fourth annual report on a program to monitor and reduce radon daughter exposures in the town of Elliot Lake, Ontario. Twelve month's WL survey measurements were completed in 1980 and showed that 22 houses exceeded the remedial action criterion of 0.02 WL. In a few cases gamma radiation levels were high enough to require remedial action in driveways and public areas, but not inside houses. During 1980 remedial work was carried out on 85 buildings; work was completed on 58. The most frequent routes of entry for radon and radon daughters were untrapped weeping tile connected to a floor drain or sump, and the wall to floor joint

  7. The innovative application of surface geophysical techniques for remedial investigations

    Energy Technology Data Exchange (ETDEWEB)

    Saunders, W.R. [OYO Geospace, Fort Myers, FL (United States); Smith, S. [ICF Kaiser Engineers, Boston, MA (United States); Gilmore, P. [Fishbeck, Thomson, Carr and Huber, Aida, MI (United States); Cox, S. [Blasland, Bouck, and Lee, Edison, NJ (United States)

    1993-03-01

    When researchers are investigating potential subsurface contamination at hazardous waste landfills, the surface geophysical techniques they may use are often limited. Many geophysical surveys are concerned with areas next to and not directly within the landfill units. The highly variable properties of the materials within the landfill may result in geophysical data that are either difficult or impossible to interpret. Therefore, contamination at these sites may not be detected until substantial lateral migration away from the unit has occurred. In addition, because of the poor resolution of some techniques, the landfill as a whole must be considered as a source, where discrete disposal areas within landfill units may be the actual point sources of contaminants. In theory, if specific sources within the landfill are identified and isolated, then reduced time, effort, and expenditures will be required for remediation activities. In the summer of 1989, the Idaho National Engineering Laboratory (INEL) investigated a small potentially hazardous waste landfill to determine if contaminant hot spots could be identified within the landfill and to determine if significant vertical and lateral migration of contaminants was occurring away from these locations. Based on the present hydrogeologic conditions, researchers anticipated that subsurface flow would be primarily vertical, with the zone of saturation at a depth greater than 150 meters. This necessitated that the survey be performed, for the most part, directly on the capped portion of the landfill. Focused geophysical surveys conducted off the landfill would not have provided useful information concerning conditions directly beneath the landfill. This paper discusses the planning, application, and analysis of four combined sensing methods: two methods of electromagnetic induction [low induction (Em) and time domain (TEM)], ground penetrating radar (GPR), and soil gas.

  8. Topical Day on Site Remediation

    Energy Technology Data Exchange (ETDEWEB)

    Vandenhove, H [ed.

    1996-09-18

    Ongoing activities at the Belgian Nuclear Research Centre relating to site remediation and restoration are summarized. Special attention has been paid to the different phases of remediation including characterization, impact assessment, evaluation of remediation actions, and execution of remediation actions.

  9. Electrodialytic Remediation of Soil Fines (<63μm) in Suspension

    DEFF Research Database (Denmark)

    Jensen, Pernille Erland; Ottosen, Lisbeth M.; Ferreira, Célia

    2007-01-01

    Current treatment of the remaining soil fines from soil wash is onerous and expensive, and therefore, in this work, we investigated the feasibility of electrodialytic remediation (EDR) as an alternative treatment. The study focuses on EDR efficiency as a function of current strength, liquid......-exchange membrane increased the pH, and this resulted in decreased remediation efficiency. It was shown that complete remediation of the soil-fines is possible, with the majority of the Pb being transported into the catholyte and precipitated at the cathode. Based on the results it is recommended that EDR...

  10. Investigation on reusing water treatment residuals to remedy soil contaminated with multiple metals in Baiyin, China

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Changhui; Zhao, Yuanyuan [The Key Laboratory of Water and Sediment Sciences, Ministry of Education, School of Environment, Beijing Normal University, Beijing 100875 (China); Pei, Yuansheng, E-mail: yspei@bnu.edu.cn [The Key Laboratory of Water and Sediment Sciences, Ministry of Education, School of Environment, Beijing Normal University, Beijing 100875 (China)

    2012-10-30

    Highlights: Black-Right-Pointing-Pointer Fe/Al water treatment residuals (FARs) can stabilize As, Pb, Ni, Zn, Cr and Cu. Black-Right-Pointing-Pointer FARs cannot stabilize Ba and Cd. Black-Right-Pointing-Pointer The properties of FARs and soil affect the FARs' ability of stabilizing metals. - Abstract: In this work, the remediation of soils contaminated with multiple metals using ferric and alum water treatment residuals (FARs) in Baiyin, China, was investigated. The results of metals fractionation indicated that after the soil was treated with FARs, arsenic (As), lead (Pb), nickel (Ni), zinc (Zn) and copper (Cu) could be transformed into more stable forms, i.e., As bound in crystalline Fe/Al oxides and other metals in the oxidable and residual forms. However, the forms of chromium (Cr) and cadmium (Cd) were unaffected. Interestingly, due to the effect of FARs, barium (Ba) was predominantly transformed into more mobile forms. The bioaccessibility extraction test demonstrated that the FARs reduced the bioaccessibility of As by 25%, followed by Cu, Cr, Zn, Ni and Pb. The bioaccessibility of Cd and Ba were increased; in particular, there was an increase of 41% for Ba at the end of the test. In conclusion, the FARs can be used to remedy soil contaminated with multiple metals, but comprehensive studies are needed before practical applications of this work.

  11. Demonstration of risk-based decision analysis in remedial alternative selection and design

    International Nuclear Information System (INIS)

    Evans, E.K.; Duffield, G.M.; Massmann, J.W.; Freeze, R.A.; Stephenson, D.E.

    1993-01-01

    This study demonstrates the use of risk-based decision analysis (Massmann and Freeze 1987a, 1987b) in the selection and design of an engineering alternative for groundwater remediation at a waste site at the Savannah River Site, a US Department of Energy facility in South Carolina. The investigation focuses on the remediation and closure of the H-Area Seepage Basins, an inactive disposal site that formerly received effluent water from a nearby production facility. A previous study by Duffield et al. (1992), which used risk-based decision analysis to screen a number of ground-water remediation alternatives under consideration for this site, indicated that the most attractive remedial option is ground-water extraction by wells coupled with surface water discharge of treated effluent. The aim of the present study is to demonstrate the iterative use of risk-based decision analysis throughout the design of a particular remedial alternative. In this study, we consider the interaction between two episodes of aquifer testing over a 6-year period and the refinement of a remedial extraction well system design. Using a three-dimensional ground-water flow model, this study employs (1) geostatistics and Monte Carlo techniques to simulate hydraulic conductivity as a stochastic process and (2) Bayesian updating and conditional simulation to investigate multiple phases of aquifer testing. In our evaluation of a remedial alternative, we compute probabilistic costs associated with the failure of an alternative to completely capture a simulated contaminant plume. The results of this study demonstrate the utility of risk-based decision analysis as a tool for improving the design of a remedial alternative through the course of phased data collection at a remedial site

  12. Provincial labour market study : mould remediation industry

    International Nuclear Information System (INIS)

    2003-06-01

    Indoor exposure to mold can be problematic to human health, and some molds are considered to be toxigenic. The emergent mold remediation industry in Ontario is fragmented, with various different standards, training and certification processes. This report investigated the labour market for mold remediation workers, with particular reference to training needs and priorities. Research was derived from a literature review in order to analyze the economic, legal, technical and social context of the mold remediation industry. Data on the organized work force were obtained from records of the International Union of Painters and Allied Trades, the Labour Force Historical Review 2002, and various publications. Population data from the Ontario government and Statistics Canada were also used. Surveys of workers and employers were conducted with questionnaires. Results of the surveys indicated that mold remediation projects currently constitute a minority share of most companies' business. However, the importance of mold remediation projects is expected to increase, and industry self-regulation is the most likely scenario for the development of standards and related training programs. It was suggested that the creation of an industry body representing key stakeholder constituencies or the legitimization of an existing industry organization will reduce fragmentation and facilitate research, standard setting and certification, as well as improve marketing and education. If the demand for mold remediation services increases as anticipated, the industry will face the challenge of remaining competitive in the province's projected labour market due to shortages in personnel. There was a strong consensus between employers and workers in the mold remediation industry regarding the need for skills upgrading and compulsory certification. It was concluded that leadership is needed in the development and delivery of training programs, standard setting, recruitment and retention and

  13. REVIEW REPORT: BUILDING C-400 THERMAL TREATMENT 90 PERCENT REMEDIAL DESIGN REPORT AND SITE INVESTIGATION, PGDP, PADUCAH, KENTUCKY

    International Nuclear Information System (INIS)

    Looney, B; Jed Costanza, J; Eva Davis, E; Joe Rossabi, J; Lloyd Stewart, L; Hans Stroo, H

    2007-01-01

    On 9 April 2007, the U.S. Department of Energy (DOE) Headquarters, Office of Soil and Groundwater Remediation (EM-22) initiated an Independent Technical Review (ITR) of the 90% Remedial Design Report (RDR) and Site Investigation (RDSI) for thermal treatment of trichloroethylene (TCE) in the soil and groundwater in the vicinity of Building C-400 at the Paducah Gaseous Diffusion Plant (PGDP). The general ITR goals were to assess the technical adequacy of the 90% RDSI and provide recommendations sufficient for DOE to determine if modifications are warranted pertaining to the design, schedule, or cost of implementing the proposed design. The ultimate goal of the effort was to assist the DOE Paducah/Portsmouth Project Office (PPPO) and their contractor team in ''removing'' the TCE source zone located near the C-400 Building. This report provides the ITR findings and recommendations and supporting evaluations as needed to facilitate use of the recommendations. The ITR team supports the remedial action objective (RAO) at C-400 to reduce the TCE source area via subsurface Electrical Resistance Heating (ERH). Further, the ITR team commends PPPO, their contractor team, regulators, and stakeholders for the significant efforts taken in preparing the 90% RDR. To maximize TCE removal at the target source area, several themes emerge from the review which the ITR team believes should be considered and addressed before implementing the thermal treatment. These themes include the need for: (1) Accurate and site-specific models as the basis to verify the ERH design for full-scale implementation for this challenging hydrogeologic setting; (2) Flexible project implementation and operation to allow the project team to respond to observations and data collected during construction and operation; (3) Defensible performance metrics and monitoring, appropriate for ERH, to ensure sufficient and efficient clean-up; and (4) Comprehensive (creative and diverse) contingencies to address the

  14. 76 FR 53898 - Proposed Administrative Settlement Agreement and Order on Consent; In Re: Ely Copper Mine...

    Science.gov (United States)

    2011-08-30

    ..., as amended (``CERCLA''), 42 U.S.C. 9622(i), and Section 7003(d) of the Resource Conservation and... efforts to market and sell the site property, allow EPA to remove and use borrow material located on the... Director, Office of Site Remediation and Restoration, U.S. EPA, Region I. [FR Doc. 2011-21991 Filed 8-29-11...

  15. The Remedial Action Priority System (RAPS): Mathematical formulations

    International Nuclear Information System (INIS)

    Whelan, G.; Strenge, D.L.; Droppo, J.G. Jr.; Steelman, B.L.; Buck, J.W.

    1987-08-01

    The Remedial Action Priority System (RAPS) represents a methodology that prioritizes inactive hazardous and radioactive mixed-waste disposal sites in a scientific and objective manner based on limited site information. This methodology is intended to bridge the technology gap between the initial site evaluation using the Hazard Ranking System (HRS) and the time-consuming process of actual field site characterization, assessment, and remediation efforts. The RAPS methodology provides the US Department of Energy with a management tool for assistance in prioritizing funding and human resource allocations for further investigations and possible remediations at its inactive waste sites. Use of RAPS will help DOE ensure that those sites posing the highest potential risk are addressed first. Chapters 1 through 10 were processed separately for the Energy Data Base

  16. Strategy paper. Remedial design/remedial action 100 Area. Revision 2

    International Nuclear Information System (INIS)

    Donahoe, R.L.

    1995-10-01

    This strategy paper identifies and defines the approach for remedial design and remedial action (RD/RA) for source waste sites in the 100 Area of the Hanford Site, located in southeastern Washington State. This paper provides the basis for the US Department of Energy (DOE) to assess and approve the Environmental Restoration Contractor's (ERC) approach to RD/RA. Additionally, DOE is requesting review/agreement from the US Environmental Protection Agency (EPA) and Washington State Department of Ecology (Ecology) on the strategy presented in this document in order to expedite remedial activities

  17. Removal Site Evaluation Report to the C-Reactor Seepage Basins (904-066, -067 and -068G)

    Energy Technology Data Exchange (ETDEWEB)

    Palmer, E.R. [Westinghouse Savannah River Company, AIKEN, SC (United States)

    1997-07-01

    Removal Site Evaluation Reports are prepared in accordance with Section 300.410 of the National Contingency Plan (NCP) and Section X of the Federal Facility Agreement (FFA). The C-Reactor Seepage Basins (904-066G,-067G,-068G) are listed in Appendix C, Resource Conservation and Recovery Act (RCRA)/Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Units List, of the FFA. The purpose of this investigation is to report information concerning conditions at this unit sufficient to assess the threat (if any) posed to human health and the environment and to determine the need for additional CERCLA action. The scope of the investigation included a review of past survey and investigation data, the files, and a visit to the unit.Through this investigation unacceptable conditions of radioactive contaminant uptake in on-site vegetation were identified. This may have resulted in probable contaminant migration and become introduced into the local ecological food chain. As a result, the SRS will initiate a time critical removal action in accordance with Section 300.415 of the NCP and FFA Section XIV to remove, treat (if required), and dispose of contaminated vegetation from the C-Reactor Seepage Basins. Erosion in the affected areas will be managed by an approved erosion control plan. further remediation of this unit will be conducted in accordance with the FFA.

  18. Removal Site Evaluation Report to the C-Reactor Seepage Basins (904-066, -067 and -068G)

    International Nuclear Information System (INIS)

    Palmer, E.R.

    1997-07-01

    Removal Site Evaluation Reports are prepared in accordance with Section 300.410 of the National Contingency Plan (NCP) and Section X of the Federal Facility Agreement (FFA). The C-Reactor Seepage Basins (904-066G,-067G,-068G) are listed in Appendix C, Resource Conservation and Recovery Act (RCRA)/Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Units List, of the FFA. The purpose of this investigation is to report information concerning conditions at this unit sufficient to assess the threat (if any) posed to human health and the environment and to determine the need for additional CERCLA action. The scope of the investigation included a review of past survey and investigation data, the files, and a visit to the unit.Through this investigation unacceptable conditions of radioactive contaminant uptake in on-site vegetation were identified. This may have resulted in probable contaminant migration and become introduced into the local ecological food chain. As a result, the SRS will initiate a time critical removal action in accordance with Section 300.415 of the NCP and FFA Section XIV to remove, treat (if required), and dispose of contaminated vegetation from the C-Reactor Seepage Basins. Erosion in the affected areas will be managed by an approved erosion control plan. further remediation of this unit will be conducted in accordance with the FFA

  19. Remedial Design/Remedial Action Work Plan for Operable Units 6-05 and 10-04, Phase III

    Energy Technology Data Exchange (ETDEWEB)

    R. P. Wells

    2006-09-19

    The remedial design/remedial action for Operable Unit 6-05 (Waste Area Group 6) and Operable Unit 10-04 (Waste Area Group 10) - collectively called Operable Unit 10-04 has been divided into four phases. Phase I consists of developing and implementing institutional controls at Operable Unit 10-04 sites and developing and implementing Idaho National Laboratory-wide plans for both institutional controls and ecological monitoring. Phase II will remediate sites contaminated with trinitrotoluene and Royal Demolition Explosive. Phase III will remediate lead contamination at a gun range, and Phase IV will remediate hazards from unexploded ordnance. This Phase III remedial Design/Remedial Action Work Plan addresses the remediation of lead-contaminated soils found at the Security Training Facility (STF)-02 Gun Range located at the Idaho National Laboratory. Remediation of the STF-02 Gun Range will include excavating contaminated soils; physically separating copper and lead for recycling; returning separated soils below the remediation goal to the site; stabilizing contaminated soils, as required, and disposing of the separated soils that exceed the remediation goal; encapsulating and disposing of creosote-contaminated railroad ties and power poles; removing and disposing of the wooden building and asphalt pads found at the STF-02 Gun Range; sampling and analyzing soil to determine the excavation requirements; and when the remediation goals have been met, backfilling and contouring excavated areas and revegetating the affected area.

  20. Developing a programmatic approach to investigating and remediating many unrelated comprehensive environmental response, compensation, and liability act sites at Kelly Air Force Base

    International Nuclear Information System (INIS)

    Kamp, G.; Regan, P.; Ninesteel, R.; Martin, R.

    1988-01-01

    Kelly Air Force Base (AFB), which was founded in 1917, is involved in logistics and maintenance activities supporting the Air Logistics Command. In addition, Kelly AFB hosts over 50 tenant organizations representing the Air Force, Department of Defense, and other government agencies. Over the years waste disposal from this complex was conducted in a manner that led to the identification of over 30 sites to be included in the Installation Restoration Program (IRP) after the Phase 1 investigation. A methodology was needed to prioritize the Remedial Investigations and Feasibility Study (RI/FS) activities for the sites. A Strategy Plan was developed that involved reviewing and interpreting existing data, identifying data voids relative to site specific RI/FS activities, and developing methodology to prioritize activities. Sites were prioritized, and a comprehensive IRP planning document was developed. One data deficiency was revealed -- the lack of understanding of the Basewide hydrogeologic conditions necessary to establish an effective restoration program. A Hydrogeologic Investigation was initiated to provide this data. This data will allow better interpretation of the interaction of the sites, particularly those in close proximity, and improved planning of remediation activities

  1. Data Base Management Plan for the remedial investigation of Waste Area Grouping 10, Operable Unit 3, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1993-10-01

    This Data Base Management Plan describes the gathering, verifying, analyzing, reporting, and archiving of data generated during the remedial investigation of Waste Area Grouping 10, Operable Unit 3. This investigation will produce data documenting wellhead surveys, well headspace gas pressure measurements, geophysical surveys, water level measurements, and borehole geophysical logs. Close Support Laboratory analyses will be performed on well headspace gas and well water samples

  2. Predictors of change in life skills in schizophrenia after cognitive remediation.

    Science.gov (United States)

    Kurtz, Matthew M; Seltzer, James C; Fujimoto, Marco; Shagan, Dana S; Wexler, Bruce E

    2009-02-01

    Few studies have investigated predictors of response to cognitive remediation interventions in patients with schizophrenia. Predictor studies to date have selected treatment outcome measures that were either part of the remediation intervention itself or closely linked to the intervention with few studies investigating factors that predict generalization to measures of everyday life-skills as an index of treatment-related improvement. In the current study we investigated the relationship between four measures of neurocognitive function, crystallized verbal ability, auditory sustained attention and working memory, verbal learning and memory, and problem-solving, two measures of symptoms, total positive and negative symptoms, and the process variables of treatment intensity and duration, to change on a performance-based measure of everyday life-skills after a year of computer-assisted cognitive remediation offered as part of intensive outpatient rehabilitation treatment. Thirty-six patients with schizophrenia or schizoaffective disorder were studied. Results of a linear regression model revealed that auditory attention and working memory predicted a significant amount of the variance in change in performance-based measures of everyday life skills after cognitive remediation, even when variance for all other neurocognitive variables in the model was controlled. Stepwise regression revealed that auditory attention and working memory predicted change in everyday life-skills across the trial even when baseline life-skill scores, symptoms and treatment process variables were controlled. These findings emphasize the importance of sustained auditory attention and working memory for benefiting from extended programs of cognitive remediation.

  3. Baseline risk evaluation for exposure to bulk wastes at the Weldon Spring Quarry, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    Haroun, L.A.; Peterson, J.M.; MacDonell, M.M.; Hlohowskyj, I.

    1990-01-01

    The US Department of Energy (DOE), under its Surplus Facilities Management Program (SFMP), is responsible for cleanup activities at the Weldon Spring site, Weldon Spring, Missouri. The site consists of a raffinate pits and chemical plant area and a quarry. This baseline risk evaluation has been prepared to support a proposed response action for management of contaminated bulk wastes in the quarry. The quarry became chemically and radioactively contaminated as a result of various wastes that were disposed of there between 1942 and 1969. This risk evaluation assesses potential impacts on human health and the environment that may result from exposure to releases of contaminants from the quarry under current site conditions. Risk assessment is a key component of the remedial investigation/feasibility study (RI/FS) process, as identified in guidance from the US Environmental Protection Agency (EPA); this process addresses sites subject to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980, as amended by the Superfund Amendments and Reauthorization Act of 1986. Response actions at the Weldon Spring quarry are subject to CERCLA requirements because the quarry is listed on the EPA's National Priorities List. The DOE is also responsible for complying with the requirements of the National Environmental Policy Act (NEPA) of 1969, which requires federal agencies to consider the environmental consequences of a proposed action as part of the decision-making process for that action. Although this document has not been prepared to fulfill specific NEPA requirements, the analyses contained herein --- along with the analyses provided in the remedial investigation, feasibility study, and other supporting documents --- are intended to meet the environmental assessment requirements of NEPA

  4. Geotechnical engineering considerations in the NRC's review of uranium mill tailings remedial action plans

    International Nuclear Information System (INIS)

    Gillen, D.M.

    1985-01-01

    To reduce potential health hazards associated with inactive uranium mill tailings sites, the Department of Energy (DOE) is presently investigating and implementing remedial actions at 24 sites in the Uranium Mill Tailings Remedial Action Program (UMTRAP). All remedial actions must be selected and performed with the concurrence of the Nuclear Regulatory Commission (NRC). This paper provides a discussion of geotechnical engineering considerations during the NRC's preconcurrence review of proposed remedial action plans. In order for the NRC staff to perform an adequate geotechnical engineering review, DOE documents must contain a presentation of the properties and stability of all in-situ and engineered soil and rock which may affect the ability of the remedial action plans to meet EPA standards for long-term stability and control. Site investigations, laboratory testing, and remedial action designs must be adequate in scope and technique to provide sufficient data for the NRC staff to independently evaluate static and dynamic stability, settlement, radon attenuation through the soil cover, durability of rock for erosion protection, and other geotechnical engineering factors

  5. Environmental Restoration Program pollution prevention performance measures for FY 1993 and 1994 remedial investigations

    International Nuclear Information System (INIS)

    1993-03-01

    The Martin Marietta Energy Systems, Inc., Environmental Restoration (ER) Program adopted a Pollution Prevention Program in March 1991. The program's mission is to minimize waste and prevent pollution in remedial investigations (RI), feasibility studies (FS), decontamination and decommissioning (D ampersand D), and surveillance and maintenance (S ampersand M) site program activities. Mission success will result in volume and/or toxicity reduction of generated waste. Energy Systems is producing a fully developed a Numerical Scoring System (NSS) and actually scoring the generators of Investigation Derived Waste (IDW) at six ER sites: Oak Ridge National Laboratory (ORNL), the Oak Ridge Y-12 Plant, the Oak Ridge K-25 site, Paducah Gaseous Diffusion Plant (Paducah), and Portsmouth Uranium Enrichment Complex (Portsmouth). This report summarizes the findings of this initial numerical scoring evaluation and shows where improvements in the overall ER Pollution prevention program may be required. This report identifies a number of recommendations that, if implemented, would help to improve site-performance measures. The continued development of the NSS will support generators in maximizing their Pollution Prevention/Waste Minimization efforts. Further refinements of the NSS, as applicable suggest comments and/or recommendations for improvement

  6. evaluation of different remediation methods of polluted soils using nuclear technique

    International Nuclear Information System (INIS)

    Moussa, I.E.A.

    2012-01-01

    Remediation of heavy metal contaminated has become a considerable task to introduce such marginal or waste lands into productive systems. Various techniques, i.e. chemical and organic agents, bio- and Phyto remediation including microorganisms and/or phyto plants are used to remediate such contaminated soils. The contamination of the soil with metals has become a widespread environmental problem in many industrialized countries. The fact that the Earth's surface is becoming increasingly polluted by human activities challenges society to develop strategies for sustainability that conserve nonrenewable natural resources such as soil. The aim of the present study is to investigate the effectiveness of (I) some chemical and organic amendments in remediation of heavy metals contaminated soil. At the same time, a follow up the effects of interaction between amendment concentration and incubation time intervals on bioavailability of tested heavy metals was taken into consideration. (II) Fungi inoculation in remediation of heavy metals contaminated soils. (III) Calcium carbonate on the potentiality of panikum and sudan grass (as hyper accumulators) in remediation of heavy metals contaminated soil. To fulfill this task, it was suggested to conduct three experiments, namely; (1) Chemical remediation of Contaminated Soils experiment (2) Bioremediation experiment (3) Phyto remediation Experiment

  7. Investigations involving oxidation-reduction (REDOX) pretreatment in conjunction with biological remediation of contaminated soils

    International Nuclear Information System (INIS)

    Montemagno, C.D.; Peters, R.W.; Tyree, A.

    1991-01-01

    Oxidation-reduction (REDOX) reactions are among the most important reactions involved in the environmental engineering field. Oxidation is a reaction in which the oxidation state of the treated compound is increased, i.e., the material loses electrons. Reduction involves the addition of a chemical (reducing) agent which lowers the oxidation state of a substance, i.e., the material gains electrons. Both processes of oxidation and reduction occur together. All REDOX reactions are thermodynamically based. There are a number of oxidizing agents which have been reported in the technical literature for treatment of refractory organic compounds. Common oxidizing agents include: hydrogen peroxide, ozone, ultraviolet (UV) irradiation, and combinations thereof, such as UV/ozone and UV/peroxide. A gradient of REDOX reactions is possible, depending on such factors as the oxidation-reduction reaction conditions, the availability of electron donors and acceptors, and the nature of the organic compounds involved. A review of the technical literature revealed that the majority of the oxidation-reduction applications have been in the areas of wastewater treatment and groundwater remediation, with very little attention devoted to the potential of using REDOX technologies for remediation of hydrocarbon contaminated soils. In this particular study, feasibility studies were performed on gasoline- contaminated soil. These studies focused on three major phases: 1) containment of the contamination by addition of tailoring agents to the soil, 2) biological remediation either performed in situ or on-site (using a slurry reactor system), and 3) pretreatment of the contaminated soils using REDOX systems, prior to biological remediation. This particular paper focuses on the third phase of the project, aimed at ''softening'' the refractory organics resulting in the formation of organic compounds which are more amenable to biological degradation. This paper focuses its attention on the use of

  8. Investigations involving oxidation-reduction (REDOX) pretreatment in conjunction with biological remediation of contaminated soils

    Energy Technology Data Exchange (ETDEWEB)

    Montemagno, C. D. [Argonne National Laboratory, Argonne, IL (United States); Peters, R. W.; Tyree, A.

    1991-07-01

    Oxidation-reduction (REDOX) reactions are among the most important reactions involved in the environmental engineering field. Oxidation is a reaction in which the oxidation state of the treated compound is increased, i.e., the material loses electrons. Reduction involves the addition of a chemical (reducing) agent which lowers the oxidation state of a substance, i.e., the material gains electrons. Both processes of oxidation and reduction occur together. All REDOX reactions are thermodynamically based. There are a number of oxidizing agents which have been reported in the technical literature for treatment of refractory organic compounds. Common oxidizing agents include: hydrogen peroxide, ozone, ultraviolet (UV) irradiation, and combinations thereof, such as UV/ozone and UV/peroxide. A gradient of REDOX reactions is possible, depending on such factors as the oxidation-reduction reaction conditions, the availability of electron donors and acceptors, and the nature of the organic compounds involved. A review of the technical literature revealed that the majority of the oxidation-reduction applications have been in the areas of wastewater treatment and groundwater remediation, with very little attention devoted to the potential of using REDOX technologies for remediation of hydrocarbon contaminated soils. In this particular study, feasibility studies were performed on gasoline- contaminated soil. These studies focused on three major phases: 1) containment of the contamination by addition of tailoring agents to the soil, 2) biological remediation either performed in situ or on-site (using a slurry reactor system), and 3) pretreatment of the contaminated soils using REDOX systems, prior to biological remediation. This particular paper focuses on the third phase of the project, aimed at ''softening'' the refractory organics resulting in the formation of organic compounds which are more amenable to biological degradation. This paper focuses its attention on the use of

  9. Biota Modeling in EPA's Preliminary Remediation Goal and Dose Compliance Concentration Calculators for Use in EPA Superfund Risk Assessment: Explanation of Intake Rate Derivation, Transfer Factor Compilation, and Mass Loading Factor Sources

    International Nuclear Information System (INIS)

    Manning, Karessa L.; Dolislager, Fredrick G.; Bellamy, Michael B.

    2016-01-01

    The Preliminary Remediation Goal (PRG) and Dose Compliance Concentration (DCC) calculators are screening level tools that set forth Environmental Protection Agency's (EPA) recommended approaches, based upon currently available information with respect to risk assessment, for response actions at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites, commonly known as Superfund. The screening levels derived by the PRG and DCC calculators are used to identify isotopes contributing the highest risk and dose as well as establish preliminary remediation goals. Each calculator has a residential gardening scenario and subsistence farmer exposure scenarios that require modeling of the transfer of contaminants from soil and water into various types of biota (crops and animal products). New publications of human intake rates of biota; farm animal intakes of water, soil, and fodder; and soil to plant interactions require updates be implemented into the PRG and DCC exposure scenarios. Recent improvements have been made in the biota modeling for these calculators, including newly derived biota intake rates, more comprehensive soil mass loading factors (MLFs), and more comprehensive soil to tissue transfer factors (TFs) for animals and soil to plant transfer factors (BV's). New biota have been added in both the produce and animal products categories that greatly improve the accuracy and utility of the PRG and DCC calculators and encompass greater geographic diversity on a national and international scale.

  10. BWID System Design Study

    International Nuclear Information System (INIS)

    O'Brien, M.C.; Rudin, M.J.; Morrison, J.L.; Richardson, J.G.

    1991-01-01

    The mission of the Buried Waste Integrated Demonstration (BWID) System Design Study is to identify and evaluate technology process options for the cradle-to-grave remediation of Transuranic (TRU)-Contaminated Waste Pits and Trenches buried at the Idaho National Engineering Laboratory (INEL). Emphasis is placed upon evaluating system configuration options and associated functional and operational requirements for retrieving and treating the buried wastes. A Performance-Based Technology Selection Filter was developed to evaluate the identified remediation systems and their enabling technologies based upon system requirements and quantification of technical Comprehensive Environmental Response, Compensation, and Liability (CERCLA) balancing criteria. Remediation systems will also be evaluated with respect to regulatory and institutional acceptance and cost-effectiveness

  11. Combining expedited cleanup with innovative technology demonstrations

    International Nuclear Information System (INIS)

    Hagood, M.C.; Rohay, V.J.; Valcich, P.J.; Brouns, T.M.; Cameron, R.J.

    1993-04-01

    A Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) expedited response action (ERA) has been initiated at the Hanford Site, Washington, for the removal of carbon tetrachloride from contaminated soils to mitigate further contamination of the groundwater. Soil vapor extraction with aboveground collection and treatment was chosen as the preferred remedial technology for the first phase of the ERA. At the same time, innovative technology demonstrations are being conducted in coordination with the ERA to determine the viability of emerging technologies that can be used to characterize, remediate, and monitor carbon tetrachloride and cocontaminants. The overall goal is to improve the performance and decrease the costs of carbon tetrachloride remediation while maintaining a safe working environment

  12. Remedial Investigation Work Plan for Chestnut Ridge Operable Unit 1 (Chestnut Ridge Security Pits) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1994-03-01

    This document outlines the activities necessary to conduct a Remedial Investigation (RI) of the Chestnut Ridge Security Pits (CRSP) at the Oak Ridge Y-12 Plant. The CRSP, also designated Chestnut Ridge Operable Unit (OU) 1, is one of four OUs along Chestnut Ridge on the Oak Ridge Reservation (ORR). The purpose of the RI is to collect data to (1) evaluate the nature and extent of known and suspected contaminants, (2) support an Ecological Risk Assessment (ERA) and a Human Health Risk Assessment (HHRA), (3) support the feasibility study in the development and analysis of remedial alternatives, and (4) ultimately, develop a Record of Decision (ROD) for the site. This chapter summarizes the regulatory background of environmental investigation on the ORR and the approach currently being followed and provides an overview of the RI to be conducted at the CRSP. Subsequent chapters provide details on site history, sampling activities, procedures and methods, quality assurance (QA), health and safety, and waste management related to the RI

  13. Remedial Investigation Work Plan for Chestnut Ridge Operable Unit 1 (Chestnut Ridge Security Pits) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    This document outlines the activities necessary to conduct a Remedial Investigation (RI) of the Chestnut Ridge Security Pits (CRSP) at the Oak Ridge Y-12 Plant. The CRSP, also designated Chestnut Ridge Operable Unit (OU) 1, is one of four OUs along Chestnut Ridge on the Oak Ridge Reservation (ORR). The purpose of the RI is to collect data to (1) evaluate the nature and extent of known and suspected contaminants, (2) support an Ecological Risk Assessment (ERA) and a Human Health Risk Assessment (HHRA), (3) support the feasibility study in the development and analysis of remedial alternatives, and (4) ultimately, develop a Record of Decision (ROD) for the site. This chapter summarizes the regulatory background of environmental investigation on the ORR and the approach currently being followed and provides an overview of the RI to be conducted at the CRSP. Subsequent chapters provide details on site history, sampling activities, procedures and methods, quality assurance (QA), health and safety, and waste management related to the RI.

  14. Integrating intrusive and nonintrusive characterization methods to achieve a conceptual site model for the SLDA FUSRAP site

    International Nuclear Information System (INIS)

    Durham, L.A.; Peterson, J.M.; Frothingham, D.G.; Frederick, W.T.; Lenart, W.

    2008-01-01

    The US Army Corps of Engineers (USACE) is addressing radiological contamination following Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements at the Shallow Land Disposal Area (SLDA) site, which is a radiologically contaminated property that is part of the Formerly utilized Sites Remedial Action Program (FUSRAP). The SLDA is an 18-hectare (44-acre) site in Parks township, Armstrong County, Pennsylvania, about 37 kilometers (23 miles) east-northeast of Pittsburgh. According to historical record, radioactive wastes were disposed of at the SLDA in a series of trenches by the Nuclear Materials and Equipment Company (NUMEC) in the 1960s. The wastes originated from the nearby Apollo nuclear fuel fabrication facility, which began operations under NUMEC in the late 1950s and fabricated enriched uranium into naval reactor fuel elements. It is believed that the waste materials were buried in a series of pits constructed adjacent to one another in accordance with an Atomic Energy Commission (AEC) regulation that has since been rescinded. A CERCLA remedial investigation/feasibility study (RI/FS) process was completed for the SLDA site, and the results of the human health risk assessment indicated that the radiologically contaminated wastes could pose a risk to human health in the future. There are no historical records that provide the exact location of these pits. However, based on geophysical survey results conducted in the 1980s, these pits were defined by geophysical anomalies and were depicted on historical site drawings as trenches. At the SLDA site, a combination of investigative methods and tools was used in the RI/FS and site characterization activities. The SLDA site provides an excellent example of how historical documents and data, historical aerial photo analysis, physical sampling, and nonintrusive geophysical and gamma walkover surveys were used in combination to reduce the uncertainty in the location of the trenches. The

  15. Evaluation of Final Radiological Conditions at Areas of the Niagara Falls Storage Site Remediated under the Formerly Utilized Sites Remedial Action Program -12184

    Energy Technology Data Exchange (ETDEWEB)

    Clayton, Christopher [U.S Department of Energy Office of Legacy Management, Washington, DC; Kothari, Vijendra [U.S Department of Energy Office of Legacy Management, Morgantown, West Virginia; Starr, Ken [U.S Department of Energy Office of Legacy Management, Westminster, Colorado; Widdop, Michael; Gillespie, Joey [SM Stoller Corporation, Grand Junction, Colorado

    2012-02-26

    The U. S. Department of Energy (DOE) methods and protocols allow evaluation of remediation and final site conditions to determine if remediated sites remain protective. Two case studies are presented that involve the Niagara Falls Storage Site (NFSS) and associated vicinity properties (VPs), which are being remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). These properties are a part of the former Lake Ontario Ordnance Works (LOOW). In response to stakeholders concerns about whether certain remediated NFSS VPs were putting them at risk, DOE met with stakeholders and agreed to evaluate protectiveness. Documentation in the DOE records collection adequately described assessed and final radiological conditions at the completed VPs. All FUSRAP wastes at the completed sites were cleaned up to meet DOE guidelines for unrestricted use. DOE compiled the results of the investigation in a report that was released for public comment. In conducting the review of site conditions, DOE found that stakeholders were also concerned about waste from the Separations Process Research Unit (SPRU) at the Knolls Atomic Power Laboratory (KAPL) that was handled at LOOW. DOE agreed to determine if SPRU waste remained at that needed to be remediated. DOE reviewed records of waste characterization, historical handling locations and methods, and assessment and remediation data. DOE concluded that the SPRU waste was remediated on the LOOW to levels that pose no unacceptable risk and allow unrestricted use and unlimited exposure. This work confirms the following points as tenets of an effective long-term surveillance and maintenance (LTS&M) program: Stakeholder interaction must be open and transparent, and DOE must respond promptly to stakeholder concerns. DOE, as the long-term custodian, must collect and preserve site records in order to demonstrate that remediated sites pose no unacceptable risk. DOE must continue to maintain constructive relationships with the U

  16. Electrokinetic remediation of copper mine tailings

    DEFF Research Database (Denmark)

    Hansen, Henrik K.; Rojo, Adrián; Ottosen, Lisbeth M.

    2007-01-01

    Important process parameters to optimize in electrokinetic soil remediation are those influencing remediation time and power consumption since these directly affect the cost of a remediation action. This work shows how the electrokinetic remediation (EKR) process could be improved by implementing...... bipolar electrodes in the porous material. The bipolar electrodes in EKR meant two improvements: (1) a shorter migration pathway for the contaminant, and (2) an increased electrical conductivity in the remediation system. All together the remediation proceeded faster with lower electrical resistance than...... in similar experiments but without the bipolar electrodes. The new electrokinetic remediation design was tested on copper mine tailings with different applied electric fields, remediation times and pre-treatment. The results showed that the copper removal was increased from 8% (applying 20V for 8 days...

  17. Cortical Signatures of Dyslexia and Remediation: An Intrinsic Functional Connectivity Approach

    Science.gov (United States)

    Koyama, Maki S.; Di Martino, Adriana; Kelly, Clare; Jutagir, Devika R.; Sunshine, Jessica; Schwartz, Susan J.; Castellanos, Francisco X.; Milham, Michael P.

    2013-01-01

    This observational, cross-sectional study investigates cortical signatures of developmental dyslexia, particularly from the perspective of behavioral remediation. We employed resting-state fMRI, and compared intrinsic functional connectivity (iFC) patterns of known reading regions (seeds) among three dyslexia groups characterized by (a) no remediation (current reading and spelling deficits), (b) partial remediation (only reading deficit remediated), and (c) full remediation (both reading and spelling deficits remediated), and a group of age- and IQ-matched typically developing children (TDC) (total N = 44, age range = 7–15 years). We observed significant group differences in iFC of two seeds located in the left posterior reading network – left intraparietal sulcus (L.IPS) and left fusiform gyrus (L.FFG). Specifically, iFC between L.IPS and left middle frontal gyrus was significantly weaker in all dyslexia groups, irrespective of remediation status/literacy competence, suggesting that persistent dysfunction in the fronto-parietal attention network characterizes dyslexia. Additionally, relative to both TDC and the no remediation group, the remediation groups exhibited stronger iFC between L.FFG and right middle occipital gyrus (R.MOG). The full remediation group also exhibited stronger negative iFC between the same L.FFG seed and right medial prefrontal cortex (R.MPFC), a core region of the default network These results suggest that behavioral remediation may be associated with compensatory changes anchored in L.FFG, which reflect atypically stronger coupling between posterior visual regions (L.FFG-R.MOG) and greater functional segregation between task-positive and task-negative regions (L.FFG-R.MPFC). These findings were bolstered by significant relationships between the strength of the identified functional connections and literacy scores. We conclude that examining iFC can reveal cortical signatures of dyslexia with particular promise for monitoring

  18. Remediating Remediation: From Basic Writing to Writing across the Curriculum

    Science.gov (United States)

    Faulkner, Melissa

    2013-01-01

    This article challenges faculty members and administrators to rethink current definitions of remediation. First year college students are increasingly placed into basic writing courses due to a perceived inability to use English grammar correctly, but it must be acknowledged that all students will encounter the need for remediation as they attempt…

  19. Remediation planning and risk assessment support through data fusion technology

    International Nuclear Information System (INIS)

    1996-01-01

    Coleman Research's Data Fusion Modeling (DFM) services gives one the ability to use large geophysical and hydrological data sets, which include direct and indirect measurements, to obtain a unified mathematical model of the geology and hydrology at one's site. Coleman Research (CRC) has adapted highly stable and efficient statistical inversion techniques, developed over the past 20 years, to provide a 3D site model with quantified uncertainty based on state-of-the-art modeling codes. This site model supports risk assessment and remediation planning with enhanced numerical accuracy for tradeoff studies of alternate remediation strategies. Further, DFM supports real time model updates during remediation and site investigation

  20. Integrated approach to planning the remediation of sites undergoing decommissioning

    International Nuclear Information System (INIS)

    2009-01-01

    Responding to the needs of Member States, the IAEA has launched an environmental remediation guidance initiative dealing with the issues of radioactive contamination world wide. Its aim is to collate and disseminate information concerning the key issues affecting environmental remediation of contaminated sites. This IAEA initiative includes the development of documents that report on remediation technologies available, best practices, and information and guidance concerning (a) Strategy development for environmental remediation; (b) Characterization and remediation of contaminated sites and contaminated groundwater; (c) Management of waste and residues from mining and milling of uranium and thorium; (d) Decommissioning of buildings; (e) A database for contaminated sites. The subject of this present report concerns the integration of decommissioning and remediation activities at sites undergoing decommissioning and this fits within the first category of guidance documentation (strategy development). This document addresses key strategic planning issues. It is intended to provide practical advice and complement other reports that focus on decommissioning and remediation at nuclear facilities. The document is designed to encourage site remediation activities that take advantage of synergies with decommissioning in order to reduce the duplication of effort by various parties and minimize adverse impacts on human health, the environment, and costs through the transfer of experience and knowledge. To achieve this objective, the document is designed to help Member States gain perspective by summarizing available information about synergies between decommissioning and remediation, strategic planning and project management and planning tools and techniques to support decision making and remediation. Case studies are also presented as to give concrete examples of the theoretical elements elaborated in the documents. This publication investigates the potential synergies

  1. Hydrocarbon impacts and remedial action at an active service station

    Energy Technology Data Exchange (ETDEWEB)

    Haidar, S.A. [Keystone Environmental, Burnaby, BC (Canada); Linke, J. [Chevron Canada Ltd., Vancouver, BC (Canada)

    2006-07-01

    This presentation discussed a project that examined the hydrocarbon impacts and remedial action at an active service station. The presentation identified the project partners, discussed the background on the project and project goals. Chevron Canada was the site involved in the study and Keystone Environmental was responsible for testing soil samples, developing the detailed conceptual site model, and for conducting indoor air quality monitoring. The presentation also provided illustrations of the site layout, investigated areas, and soil and groundwater plume. The evaluation and selection of remedial options were also discussed as well as other project planning activities such as assembling the project team, obtaining agreement with stakeholders, and coordinating with the municipality, utility companies, residents, and neighbours. Remediation efforts that were described and illustrated in the presentation included: underpinning and shoring; excavation; and, barrier wall installation. Last, post remediation activities were identified including the installation of post remediation confirmatory wells; reinstating structures; reinstating rear yards, fences, and garages; reconnecting utilities; performance monitoring of barrier wall; and, preparing closure reports for certificates of compliance on off-site properties. 6 figs.

  2. Development of site remediation technologies in European countries

    International Nuclear Information System (INIS)

    Nunno, T.J.; Hyman, J.A.; Pheiffer, T.

    1988-01-01

    Site remediation is a pressing issue in European countries due to limited availability of land. Therefore, much progress is being made in the development of effective technologies for remediating contaminated sites. The purpose of this program was to investigate the most successful and innovative technologies for potential application into US markets. This EPA-sponsored project was based on a 9-month research effort which identified 95 innovative technologies in use or being researched in foreign countries. The most promising technologies were studied in-depth through personal interviews with the engineers who research and apply these technologies, and tours of laboratory models and full-scale installations. The most successful full-scale technologies investigated were developed in Holland, West Germany and Belgium. These technologies include vacuum extraction of hydrocarbons from soil, in situ washing of cadmium-polluted soil, rotating biocontractors for treating pesticides in ground water, high-temperature slagging incineration of low-level radioactive wastes, in situ steam stripping, and a number of landfarming and soil washing operations. The paper provides description of 13 site remediation techniques that have shown such promise in laboratory studies or in practice to warrant consideration of their use in the US

  3. Remedial investigation report on Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 3 -- Appendix B: Technical findings and conclusions

    International Nuclear Information System (INIS)

    1995-09-01

    This document provides the Environmental Restoration Program with information about the results of investigations performed at Waste Area Grouping (WAG) 5. It includes information on risk assessments that have evaluated long-term impacts to human health and the environment. Information provided in this document forms the basis for decisions regarding the need for subsequent remediation work at WAG 5. Sections B1.1 through B1.4 present an overview of the environmental setting of WAG 5, including location, population, land uses, ecology, and climate, and Sects. B1.5 through B1.7 give site-specific details (e.g., topography, soils, geology, and hydrology). The remediation investigation (RI) of WAG 5 did not entail en exhaustive characterization of all physical attributes of the site; the information presented here focuses on those most relevant to the development and verification of the WAG 5 conceptual model. Most of the information presented in this appendix was derived from the RI field investigation, which was designed to complement the existing data base from earlier, site-specific studies of Solid Waste Storage Area (SWSA) 5 and related areas.

  4. Qualitative risk assessment as a remediation management tool

    International Nuclear Information System (INIS)

    Knutson, D.E.

    1991-01-01

    The technique used to complete this thesis utilizes existing NRC and EPA guidance on health-based risk to qualitatively prioritize preliminary assessments and provide a tool for the direction and management of remediation activities. This method is intended as a decision making tool to aid in prioritizing the remediation effort and manage the remedial investigation and feasibility study (RI/FS) process. It is not a replacement for the RI/FS. The methodology for qualitative risk assessment utilizes data gathered in preliminary assessments and calculates the health-based hazards and consequences from contaminants found at each individual location. The health-based qualitative risk indicated that number-sign 6 fuel oil, carbon tetrachloride, depleted uranium, and enriched uranium were the contaminants of major concern, in that order. Plutonium ranked approximately sixth in the contaminant of concern priority. 38 refs., 1 fig., 9 tabs

  5. Waste Area Group 10, Operable Unit 10-08, Remedial Investigation/Feasibility Study Annual Status Report for Fiscal Year 2006

    Energy Technology Data Exchange (ETDEWEB)

    R. P. Wells

    2007-05-09

    This report provides a status of the progress made in Fiscal Year 2006 on tasks identified in the Waste Area Group 10, Operable Unit 10-08, Remedial Investigation/Feasibility Study Work Plan. Major accomplishments include: (1) groundwater sampling and review of the groundwater monitoring data, (2) installation of a Sitewide groundwater-level monitoring network, (3) update of the Groundwater Monitoring and Field Sampling Plan of Operable Unit 10-08, (4) re-evaluation of the risk at Site TSF-08, (5) progress on the Operable Unit 10-08 Sitewide Groundwater Model.

  6. Biota Modeling in EPA's Preliminary Remediation Goal and Dose Compliance Concentration Calculators for Use in EPA Superfund Risk Assessment: Explanation of Intake Rate Derivation, Transfer Factor Compilation, and Mass Loading Factor Sources

    Energy Technology Data Exchange (ETDEWEB)

    Manning, Karessa L. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Dolislager, Fredrick G. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Bellamy, Michael B. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)

    2016-11-01

    The Preliminary Remediation Goal (PRG) and Dose Compliance Concentration (DCC) calculators are screening level tools that set forth Environmental Protection Agency's (EPA) recommended approaches, based upon currently available information with respect to risk assessment, for response actions at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites, commonly known as Superfund. The screening levels derived by the PRG and DCC calculators are used to identify isotopes contributing the highest risk and dose as well as establish preliminary remediation goals. Each calculator has a residential gardening scenario and subsistence farmer exposure scenarios that require modeling of the transfer of contaminants from soil and water into various types of biota (crops and animal products). New publications of human intake rates of biota; farm animal intakes of water, soil, and fodder; and soil to plant interactions require updates be implemented into the PRG and DCC exposure scenarios. Recent improvements have been made in the biota modeling for these calculators, including newly derived biota intake rates, more comprehensive soil mass loading factors (MLFs), and more comprehensive soil to tissue transfer factors (TFs) for animals and soil to plant transfer factors (BV's). New biota have been added in both the produce and animal products categories that greatly improve the accuracy and utility of the PRG and DCC calculators and encompass greater geographic diversity on a national and international scale.

  7. Innovative technology for expedited site remediation of extensive surface and subsurface contamination

    International Nuclear Information System (INIS)

    Audibert, J.M.E.; Lew, L.R.

    1994-01-01

    Large scale surface and subsurface contamination resulted from numerous releases of feed stock, process streams, waste streams, and final product at a major chemical plant. Soil and groundwater was contaminated by numerous compounds including lead, tetraethyl lead, ethylene dibromide, ethylene dichloride, and toluene. The state administrative order dictated that the site be investigated fully, that remedial alternative be evaluated, and that the site be remediated within a year period. Because of the acute toxicity and extreme volatility of tetraethyl lead and other organic compounds present at the site and the short time frame ordered by the regulators, innovative approaches were needed to carry out the remediation while protecting plant workers, remediation workers, and the public

  8. Research factors of the electrochemical remediation clay soils from the nitrates

    Energy Technology Data Exchange (ETDEWEB)

    Korolev, V.A.; Babakina, O.A. [Moscow State Univ. (Russian Federation)

    2001-07-01

    The electrokinetic's methods are prevalent [1, 2], but abilities of the method for remediation nitrates contaminated soils are studied insufficiently. The investigations of effectiveness electrochemical remediation are complicated by processes of reduction nitrates to nitrites (that are more toxic) and then to nitrogen in soil under the constant electric current. Therefore, the objectives of the research was following: - Evaluate mechanism of electrokinetic's removing nitrates from soil; - Evaluate basic value of moisture and alkalinity influence for electrochemical remediation of soil from nitrates; - Determine flow-through regime effect on electrokinetic's treating. (orig.)

  9. Remediation plans in family medicine residency

    Science.gov (United States)

    Audétat, Marie-Claude; Voirol, Christian; Béland, Normand; Fernandez, Nicolas; Sanche, Gilbert

    2015-01-01

    Abstract Objective To assess use of the remediation instrument that has been implemented in training sites at the University of Montreal in Quebec to support faculty in diagnosing and remediating resident academic difficulties, to examine whether and how this particular remediation instrument improves the remediation process, and to determine its effects on the residents’ subsequent rotation assessments. Design A multimethods approach in which data were collected from different sources: remediation plans developed by faculty, program statistics for the corresponding academic years, and students’ academic records and rotation assessment results. Setting Family medicine residency program at the University of Montreal. Participants Family medicine residents in academic difficulty. Main outcome measures Assessment of the content, process, and quality of remediation plans, and students’ academic and rotation assessment results (successful, below expectations, or failure) both before and after the remediation period. Results The framework that was developed for assessing remediation plans was used to analyze 23 plans produced by 10 teaching sites for 21 residents. All plans documented cognitive problems and implemented numerous remediation measures. Although only 48% of the plans were of good quality, implementation of a remediation plan was positively associated with the resident’s success in rotations following the remediation period. Conclusion The use of remediation plans is well embedded in training sites at the University of Montreal. The residents’ difficulties were mainly cognitive in nature, but this generally related to deficits in clinical reasoning rather than knowledge gaps. The reflection and analysis required to produce a remediation plan helps to correct many academic difficulties and normalize the academic career of most residents in difficulty. Further effort is still needed to improve the quality of plans and to support teachers.

  10. Remedial investigation report on Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 2 -- Appendix A: Characterization methods and data summary

    International Nuclear Information System (INIS)

    1995-09-01

    This document provides the Environmental Restoration Program with information about the results of investigations performed at Waste Area Grouping (WAG) 5. It includes information on risk assessments that have evaluated long-term impacts to human health and the environment. Information provided in this document forms the basis for decisions regarding the need for subsequent remediation work at WAG 5. This appendix presents background regulatory and technical information regarding the solid waste management units (SWMUs) at WAG 5 to address requirements established by the Federal Facility Agreement (FFA) for the Oak Ridge Reservation (ORR). The US Department of Energy (DOE) agreed to conduct remedial investigations (RIs) under the FFA at various sites at Oak Ridge National Laboratory (ORNL), including SWMUs and other areas of concern on WAG 5. The appendix gives an overview of the regulatory background to provide the context in which the WAG 5 RI was planned and implemented and documents how historical sources of data, many of which are SWMU-specific, were evaluated and used.

  11. New IAEA guidelines on environmental remediation

    Energy Technology Data Exchange (ETDEWEB)

    Fesenko, Sergey [International Atomic Energy Agency, A2444, Seibersdorf (Austria); Howard, Brenda [Centre for Ecology and Hydrology, Lancaster Environment Centre, LA1 4AP, Lancaster (United Kingdom); Kashparov, Valery [Ukrainian Institute of Agricultural Radiology, 08162, 7, Mashinobudivnykiv str., Chabany, Kyivo-Svyatoshin region, Kyiv (Ukraine); Sanzharova, Natalie [Russian Institute of Agricultural Radiology and Agroecology, Russian Federation, 249032, Obninsk (Russian Federation); Vidal, Miquel [Analytical Chemistry Department-Universitat de Barcelona, Barcelona, 08028 Barcelona (Spain)

    2014-07-01

    In response to the needs of its Member States, the International Atomic Energy Agency (IAEA) has published many documents covering different aspects of remediation of contaminated environments. These documents range from safety fundamentals and safety requirements to technical documents describing remedial technologies. Almost all the documents on environmental remediation are related to uranium mining areas and decommissioning of nuclear facilities. IAEA radiation safety standards on remediation of contaminated environments are largely based on these two types of remediation. The exception is a document related to accidents, namely the IAEA TRS No. 363 'Guidelines for Agricultural Countermeasures Following an Accidental Release of Radionuclides'. Since the publication of TRS 363, there has been a considerable increase in relevant information. In response, the IAEA initiated the development of a new document, which incorporated new knowledge obtained during last 20 years, lessons learned and subsequent changes in the regulatory framework. The new document covers all aspects related to the environmental remediation from site characterisation to a description of individual remedial actions and decision making frameworks, covering urban, agricultural, forest and freshwater environments. Decisions taken to commence remediation need to be based on an accurate assessment of the amount and extent of contamination in relevant environmental compartments and how they vary with time. Major aspects of site characterisation intended for remediation are described together with recommendations on effective sampling programmes and data compilation for decision making. Approaches for evaluation of remedial actions are given in the document alongside the factors and processes which affect their implementation for different environments. Lessons learned following severe radiation accidents indicate that remediation should be considered with respect to many different

  12. Proposed plan for the United Nuclear Corporation Disposal Site at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1991-03-01

    The US Department of Energy (DOE) in compliance with Section 117(a) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980, as amended by the Superfund Amendments and Reauthorization Act (SARA) of 1986, is releasing the proposed plan for remedial action at the United Nuclear Corporation (UNC) Disposal Site located at the DOE Oak Ridge Operations (ORO) Y-12 Plant, Oak Ridge, Tennessee. The purpose of this document is to present and solicit for comment to the public and all interested parties the ''preferred plan'' to remediate the UNC Disposal Site. However, comments on all alternatives are invited

  13. Some Similarities and Differences Between Compositions Written by Remedial and Non-Remedial College Freshmen.

    Science.gov (United States)

    House, Elizabeth B.; House, William J.

    The essays composed by 84 remedial and 77 nonremedial college freshmen were analyzed for some features proposed by Mina Shaughnessy as being characteristic of basic writers. The students were enrolled in either a beginning remedial class (098), a class at the next level of remediation (099), or a regular English class (101). The essays were…

  14. Soil sorting, new approach to site remediation management

    International Nuclear Information System (INIS)

    Bramlitt, E.T.; Woods, J.A.; Dillon, M.J.

    1996-01-01

    Soil sorting is the technology which conveys soil beneath contaminant detectors and, based on contaminant signal, automatically toggles a gate at the conveyor end to send soil with contamination above a guideline to a separate location from soil which meets the guideline. The technology was perfected for remediation of sites having soils with radioactive contamination, but it is applicable to other contaminants when instrumental methods exist for rapid contaminant detection at levels of concern. This paper examines the three methods for quantifying contamination in soil in support of site remediation management. Examples are discussed where the primary contaminant is plutonium, a radioactive substance and source of nuclear energy which can be hazardous to health when in the environment without controls. Field survey instruments are very sensitive to plutonium and can detect it in soil at levels below a part per billion, and there are a variety of soils which have been contaminated by plutonium and thoroughly investigated. The lessons learned with plutonium are applicable to other types of contaminants and site remediations. The paper concludes that soil sorting can be the most cost effective approach to site remediation, and it leads to the best overall cleanup

  15. Object reasoning for waste remediation

    International Nuclear Information System (INIS)

    Pennock, K.A.; Bohn, S.J.; Franklin, A.L.

    1991-08-01

    A large number of contaminated waste sites across the United States await size remediation efforts. These sites can be physically complex, composed of multiple, possibly interacting, contaminants distributed throughout one or more media. The Remedial Action Assessment System (RAAS) is being designed and developed to support decisions concerning the selection of remediation alternatives. The goal of this system is to broaden the consideration of remediation alternatives, while reducing the time and cost of making these considerations. The Remedial Action Assessment System is a hybrid system, designed and constructed using object-oriented, knowledge- based systems, and structured programming techniques. RAAS uses a combination of quantitative and qualitative reasoning to consider and suggest remediation alternatives. The reasoning process that drives this application is centered around an object-oriented organization of remediation technology information. This paper describes the information structure and organization used to support this reasoning process. In addition, the paper describes the level of detail of the technology related information used in RAAS, discusses required assumptions and procedural implications of these assumptions, and provides rationale for structuring RAAS in this manner. 3 refs., 3 figs

  16. In-situ remediation of brine impacted soils and groundwater using hydraulic fracturing, desalinization and recharge wells

    Energy Technology Data Exchange (ETDEWEB)

    Robertson, C. [Wiebe Environmental Services Inc., Calgary, AB (Canada); Ratiu, I. [GeoGrid Environmental Inc., Calgary, AB (Canada)

    2006-07-01

    This conference presentation focused on the in-stu remediation of brine impacted soils and groundwater using hydraulic fracturing, desalinization and recharge wells. A former oil battery was established in the 1940s, decommissioned in the late 1960s with a reclamation certificate issued in 1972. The land owner reported poor vegetative growth in the former battery area. The purpose of the study was to investigate the cause of poor growth and delineate contaminants of concern and to remediate impacted soil and groundwater associated with the former battery site. The investigation involved agrological, geophysical and hydrogeological investigation into the extent of anthropogenic impacts as well as the development of remediation options and plans to deal with issues of concern. The presentation provided the results of the investigation, options identified, and discussed limitation on salt remediation and treatment of saline soils. Other topics included hydraulic fracturing, injection wells that were installed to re-circulate treated groundwater though the salt plume, desalinization processes, and next steps. figs.

  17. Inclusion of social indicators in decision support tools for the selection of sustainable site remediation options.

    Science.gov (United States)

    Cappuyns, Valérie

    2016-12-15

    Sustainable remediation requires a balanced decision-making process in which environmental, economic and social aspects of different remediation options are all considered together and the optimum remediation solution is selected. More attention has been paid to the evaluation of environmental and economic aspects, in particular to reduce the human and environmental risks and the remediation costs, to the exclusion of social aspects of remediation. This paper investigates how social aspects are currently considered in sustainability assessments of remediation projects. A selection of decision support tools (DSTs), used for the sustainability assessment of a remediation project, is analyzed to define how social aspects are considered in those tools. The social indicator categories of the Sustainable Remediation Forum - United Kingdom (SuRF-UK), are used as a basis for this evaluation. The consideration of social aspects in the investigated decision support tools is limited, but a clear increase is noticed in more recently developed tools. Among the five social indicator categories defined by SuRF-UK to facilitate a holistic consideration of social aspects of a remediation project only "Human health and safety" is systematically taken into account. "Neighbourhood and locality" is also often addressed, mostly emphasizing the potential disturbance caused by the remediation activities. However, the evaluation of 'Ethics and Equality', Communities and community involvement', and 'Uncertainty and evidence' is often neglected. Nevertheless, concrete examples can be found in some of the investigated tools. Specific legislation, standard procedures, and guidelines that have to be followed in a region or country are mainly been set up in the context of protecting human and ecosystem health, safety and prevention of nuisance. However, they sometimes already include some of the aspects addressed by the social indicators. In this perspective the use of DST to evaluate the

  18. The harm of petroleum-polluted soil and its remediation research

    Science.gov (United States)

    Wang, Shuguang; Xu, Yan; Lin, Zhaofeng; Zhang, Jishi; Norbu, Namkha; Liu, Wei

    2017-08-01

    Land resources are the foundation of human's survival and development, and it's one of the most valuable natural resources of each country. In view of the serious problems of petroleum pollution to soil caused during the exploration and development processes, this article based on a large number of literature researches, firstly discussed the compositions and properties of petroleum contaminants, secondly investigated some restoration methods for the current situation of petroleum polluted soil, compared and analyzed the advantages and disadvantages of three kinds of bioremediation technologies. Finally, according to the deficiencies of previous research and existing problems, made an outlook of the physical and chemical remediation, bioremediation, and microbe-plant remediation, to provide some enlightenments for petroleum-contaminated soil remediation.

  19. Summary performance assessment of in situ remediation technologies demonstrated at Savannah River

    International Nuclear Information System (INIS)

    Rosenberg, N.D.; Robinson, B.A.; Birdsell, K.H.; Travis, B.J.

    1994-06-01

    The Office of Technology Development (OTD) in the Department of Energy's (DOE) Office of Environmental Restoration and Waste Management is investigating new technologies for ''better, faster, cheaper, safer'' environmental remediation. A program at DOE's Savannah River site was designed to demonstrate innovative technologies for the remediation of volatile organic compounds (VOCs) at nonarid sites. Two remediation technologies, in situ air stripping and in situ bioremediation--both using horizontal wells, were demonstrated at the site between 1990--1993. This brief report summarizes the conclusions from three separate modeling studies on the performance of these technologies

  20. Investigation of Novel Electrode Materials for Electrochemically-Based Remediation of High- and Low-Level Mixed Wastes in the DOE Complex - Final Report

    Energy Technology Data Exchange (ETDEWEB)

    Lewis, N.S.; Anderson, M.

    2000-12-01

    New materials are investigated, based on degenerately-doped titanias, for use in the electrochemical degradation of organics and nitrogen-containing compounds in sites of concern to the DOE remediation effort. The data collected in this project appear to provide a rational approach for design of more efficient nanoporous electrodes. Also, osmium complexes appear to be promising candidates for further optimization in operating photo electrochemical cells for solar energy conversion applications.

  1. Investigation of Novel Electrode Materials for Electrochemically-Based Remediation of High- and Low-Level Mixed Wastes in the DOE Complex - Final Report

    International Nuclear Information System (INIS)

    Lewis, N.S.; Anderson, M.

    2000-01-01

    New materials are investigated, based on degenerately-doped titanias, for use in the electrochemical degradation of organics and nitrogen-containing compounds in sites of concern to the DOE remediation effort. The data collected in this project appear to provide a rational approach for design of more efficient nanoporous electrodes. Also, osmium complexes appear to be promising candidates for further optimization in operating photo electrochemical cells for solar energy conversion applications

  2. Air-Based Remediation Workshop - Section 8 Air-Based Remediation Technology Selection Logic

    Science.gov (United States)

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites," the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Environ...

  3. Thermal treatment and non-thermal technologies for remediation of manufactured gas plant sites

    International Nuclear Information System (INIS)

    McGowan, T.F.; Greer, B.A.; Lawless, M.

    1996-01-01

    More than 1,500 manufactured gas plant (MGP) sites exist throughout the US. Many are contaminated with coal tar from coal-fueled gas works which produced town gas from the mid-1800s through the 1950s. Virtually all old US cities have such sites. Most are in downtown areas as they were installed for central distribution of manufactured gas. While a few sites are CERCLA/Superfund, most are not. However, the contaminants and methods used for remediation are similar to those used for Superfund clean-ups of coal tar contamination from wood-treating and coke oven facilities. Clean-up of sites is triggered by regulatory pressure, property transfers and re-development as well as releases to the environment--in particular, via groundwater migration. Due to utility de-regulation, site clean-ups may also be triggered by sale of a utility or of a specific utility site to other utilities. Utilities have used two approaches in dealing with their MGP sites. The first is do nothing and hope for the best. History suggests that, sooner or later, these sites become a bigger problem via a release, citizen lawsuit or regulatory/public service commission intervention. The second, far better approach is to define the problem now and make plans /for waste treatment or immobilization. This paper describes recent experience with a high capacity/low cost thermal desorption process for this waste and reviews non-thermal technology, such as bio-treatment, capping, recycling, and dig and haul. Cost data are provided for all technologies, and a case study for thermal treatment is also presented

  4. Innovative mathematical modeling in environmental remediation

    Energy Technology Data Exchange (ETDEWEB)

    Yeh, Gour T. [Taiwan Typhoon and Flood Research Institute (Taiwan); National Central Univ. (Taiwan); Univ. of Central Florida (United States); Gwo, Jin Ping [Nuclear Regulatory Commission (NRC), Rockville, MD (United States); Siegel, Malcolm D. [Sandia National Laboratories, Albuquerque, NM (United States); Li, Ming-Hsu [National Central Univ. (Taiwan); ; Fang, Yilin [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States); Zhang, Fan [Inst. of Tibetan Plateau Research, Chinese Academy of Sciences (China); Luo, Wensui [Inst. of Tibetan Plateau Research, Chinese Academy of Sciences (China); Yabusaki, Steven B. [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)

    2013-05-01

    There are two different ways to model reactive transport: ad hoc and innovative reaction-based approaches. The former, such as the Kd simplification of adsorption, has been widely employed by practitioners, while the latter has been mainly used in scientific communities for elucidating mechanisms of biogeochemical transport processes. It is believed that innovative mechanistic-based models could serve as protocols for environmental remediation as well. This paper reviews the development of a mechanistically coupled fluid flow, thermal transport, hydrologic transport, and reactive biogeochemical model and example-applications to environmental remediation problems. Theoretical bases are sufficiently described. Four example problems previously carried out are used to demonstrate how numerical experimentation can be used to evaluate the feasibility of different remediation approaches. The first one involved the application of a 56-species uranium tailing problem to the Melton Branch Subwatershed at Oak Ridge National Laboratory (ORNL) using the parallel version of the model. Simulations were made to demonstrate the potential mobilization of uranium and other chelating agents in the proposed waste disposal site. The second problem simulated laboratory-scale system to investigate the role of natural attenuation in potential off-site migration of uranium from uranium mill tailings after restoration. It showed inadequacy of using a single Kd even for a homogeneous medium. The third example simulated laboratory experiments involving extremely high concentrations of uranium, technetium, aluminum, nitrate, and toxic metals (e.g.,Ni, Cr, Co).The fourth example modeled microbially-mediated immobilization of uranium in an unconfined aquifer using acetate amendment in a field-scale experiment. The purposes of these modeling studies were to simulate various mechanisms of mobilization and immobilization of radioactive wastes and to illustrate how to apply reactive transport models

  5. Innovative mathematical modeling in environmental remediation

    International Nuclear Information System (INIS)

    Yeh, Gour T.; Gwo, Jin Ping; Siegel, Malcolm D.; Li, Ming-Hsu; Fang, Yilin; Zhang, Fan; Luo, Wensui; Yabusaki, Steven B.

    2013-01-01

    There are two different ways to model reactive transport: ad hoc and innovative reaction-based approaches. The former, such as the Kd simplification of adsorption, has been widely employed by practitioners, while the latter has been mainly used in scientific communities for elucidating mechanisms of biogeochemical transport processes. It is believed that innovative mechanistic-based models could serve as protocols for environmental remediation as well. This paper reviews the development of a mechanistically coupled fluid flow, thermal transport, hydrologic transport, and reactive biogeochemical model and example-applications to environmental remediation problems. Theoretical bases are sufficiently described. Four example problems previously carried out are used to demonstrate how numerical experimentation can be used to evaluate the feasibility of different remediation approaches. The first one involved the application of a 56-species uranium tailing problem to the Melton Branch Subwatershed at Oak Ridge National Laboratory (ORNL) using the parallel version of the model. Simulations were made to demonstrate the potential mobilization of uranium and other chelating agents in the proposed waste disposal site. The second problem simulated laboratory-scale system to investigate the role of natural attenuation in potential off-site migration of uranium from uranium mill tailings after restoration. It showed inadequacy of using a single Kd even for a homogeneous medium. The third example simulated laboratory experiments involving extremely high concentrations of uranium, technetium, aluminum, nitrate, and toxic metals (e.g.,Ni, Cr, Co). The fourth example modeled microbially-mediated immobilization of uranium in an unconfined aquifer using acetate amendment in a field-scale experiment. The purposes of these modeling studies were to simulate various mechanisms of mobilization and immobilization of radioactive wastes and to illustrate how to apply reactive transport models

  6. Treatability Study Operational Testing Program and Implementation Plan for the Gunite and Associated Tanks at the Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-09-01

    To support future decision making of the Gunite and Associated Tanks (GAAT) Operable Unit (OU) remedy selection, the Department of Energy (DOE) is performing a Treatability Study (TS), consistent with the EPA guidance for Comprehensive Environmental Response, compensation, and Liability Act (CERCLA) treatability studies. The study will inform stakeholders about various waste removal technologies and the cost of potential remediation approaches, particularly the cost associated with sluicing and the reduction in risk to human health and the environment from tank content removal. As part of the GAAT OU remedy, a series of studies and technology tests will be preformed. These may address one or more of the following areas, characterization, removal, treatment, and transfer of wastes stored in the GAAT OU

  7. Treatability Study Operational Testing Program and Implementation Plan for the Gunite and Associated Tanks at the Oak Ridge National Laboratory, Oak Ridge, Tennessee

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-09-01

    To support future decision making of the Gunite and Associated Tanks (GAAT) Operable Unit (OU) remedy selection, the Department of Energy (DOE) is performing a Treatability Study (TS), consistent with the EPA guidance for Comprehensive Environmental Response, compensation, and Liability Act (CERCLA) treatability studies. The study will inform stakeholders about various waste removal technologies and the cost of potential remediation approaches, particularly the cost associated with sluicing and the reduction in risk to human health and the environment from tank content removal. As part of the GAAT OU remedy, a series of studies and technology tests will be preformed. These may address one or more of the following areas, characterization, removal, treatment, and transfer of wastes stored in the GAAT OU.

  8. 200-UP-1 groundwater remedial design/remedial action work plan. Revision 1

    International Nuclear Information System (INIS)

    1997-07-01

    This 200-UP-1 remedial design report presents the objective and rationale developed for the design and implementation of the selected interim remedial measure for the 200-UP-1 Operable Unit, located in the 200 West Area of the Hanford Site

  9. Genealogy Remediated

    DEFF Research Database (Denmark)

    Marselis, Randi

    2007-01-01

    Genealogical websites are becoming an increasingly popular genre on the Web. This chapter will examine how remediation is used creatively in the construction of family history. While remediation of different kinds of old memory materials is essential in genealogy, digital technology opens new...... possibilities. Genealogists use their private websites to negotiate family identity and hereby create a sense of belonging in an increasingly complex society. Digital technologies enhance the possibilities of coorporation between genealogists. Therefore, the websites are also used to present archival...

  10. An Investigation of Social Factors Affecting on Personnel Job Satisfaction of Remedial Service Insurance Department

    Directory of Open Access Journals (Sweden)

    Sayyed Yaser Ebrahimian Jolodar

    2012-01-01

    Full Text Available Because of the paramount importance of job satisfaction and due to its main consequences such as reduction of work absence and resignation, personnel promotion and society‟s health, and more importantly, its role in achievement of organization goals, this study aimed at investigating the effects of six social factors including personnel‟s belief, salary and benefits, participation in organizational decision-making, sense of job security, interaction with colleagues and meeting the basic needs of personnel on job satisfaction. The statistical population of this study was the personnel of Remedial Service Insurance Department in Sari and the questionnaire was distributed among them. The results showed that there is a significant and positive correlation among all these factors and they have meaningful effects on personnel job satisfaction based on multiple regression analysis. Furthermore, findings revealed that personnel‟s belief about their job has the most effects on job satisfaction.

  11. Challenges for Deep Vadose Zone Remediation at the Hanford Site

    International Nuclear Information System (INIS)

    Morse, John G.; Charboneau, Briant L.; Lober, Robert W.; Triplett, Mark B.

    2008-01-01

    The 'deep vadose zone' is defined as the region below the practical depth of surface remedy influence (e.g., excavation or barrier). At the Hanford Site, this region of the Central Plateau poses unique challenges for characterization and remediation. The contaminants in this region also pose a potentially significant continuing or future threat to groundwater. Currently, deep vadose zone characterization efforts and remedy selection are spread over multiple waste site Operable Units and tank farm Waste Management Areas. A particular challenge for this effort is the situation in which past leaks from single-shell tanks have become commingled with discharges from nearby liquid disposal sites. The Hanford Site is working with all affected parties, including the Washington State Department of Ecology, the Environmental Protection Agency, DOE-RL, DOE-ORP, and multiple contractor organizations to develop a unified approach to conducting work and reaching remediation decisions. This effort addresses the complex and challenging technical and regulatory issues within this environment. A true inter-Agency effort is evaluating the best strategy or combination of strategies for focusing technical investigations, including treatability studies, and for attaining remedy decisions on the Hanford Site

  12. Pre- and post-remediation characterization of acid-generating fluvial tailings material

    Science.gov (United States)

    Smith, Kathleen S.; Walton-Day, Katherine; Hoal, Karin O.; Driscoll, Rhonda L.; Pietersen, K.

    2012-01-01

    The upper Arkansas River south of Leadville, Colorado, USA, contains deposits of fluvial tailings from historical mining operations in the Leadville area. These deposits are potential non-point sources of acid and metal contamination to surface- and groundwater systems. We are investigating a site that recently underwent in situ remediation treatment with lime, fertilizer, and compost. Pre- and post-remediation fluvial tailings material was collected from a variety of depths to examine changes in mineralogy, acid generation, and extractable nutrients. Results indicate sufficient nutrient availability in the post-remediation near-surface material, but pyrite and acid generation persist below the depth of lime and fertilizer addition. Mineralogical characterization performed using semi-quantitative X-ray diffraction and quantitative SEM-based micro-mineralogy (Mineral Liberation Analysis, MLA) reveal formation of gypsum, jarosite, and complex coatings surrounding mineral grains in post-remediation samples.

  13. Remediating sites contaminated with heavy metals

    International Nuclear Information System (INIS)

    Swartzbaugh, J.; Sturgill, J.; Cormier, B.; Williams, H.D.

    1992-01-01

    This article is intended to serve as a reference for decision makers who must choose an approach to remediate sites contaminated with heavy metals. Its purpose is to explain pertinent chemical and physical characteristics of heavy metals, how to use these characteristics to select remedial technologies, and how to interpret and use data from field investigations. Different metal species are typically associated with different industrial processes. The contaminant species behave differently in various media (i.e., groundwater, soils, air), and require different technologies for containment and treatment. We focus on the metals that are used in industries that generate regulated waste. These include steelmaking, paint and pigment manufacturing, metal finishing, leather tanning, papermaking, aluminum anodizing, and battery manufacturing. Heavy metals are also present in refinery wastes as well as in smelting wastes and drilling muds

  14. Electrochemical soil remediation - accelerated soil weathering?

    Energy Technology Data Exchange (ETDEWEB)

    Ottosen, L.M.; Villumsen, A.; Hansen, H.K.; Jensen, P.E.; Pedersen, A.J. [Dept. of Civil Engineering, Technical Univ. of Denmark, Lyngby (Denmark); Ribeiro, A.B. [Dept. of Environmental Sciences and Engineering, New Univ. of Lisbon, Monte da Caparica (Portugal)

    2001-07-01

    In electrochemical soil remediation systems, where enhancement solutions and complexing agents are not used, a developing acidic front is mobilizing the heavy metals and the electric current is removing the mobilized elements from the soil. The hypotheses investigated in this paper is whether this process may be comparable to the chemical soil weathering that occurs in the environment due to the acidic rain, where the mobilized elements are removed from the soil by the penetrating water. Even through the weathering process is highly accelerated in the electrochemical cell. This paper shows results from electrodialytic remediation experiments performed with four different Danish heavy metal polluted soils. The main emphasis is laid on the relation between the developing acidic front and electromigration of Cu, Zn, Mn, Mg, Fe and Ca. (orig.)

  15. Mold: Cleanup and Remediation

    Science.gov (United States)

    ... National Center for Environmental Health (NCEH) Cleanup and Remediation Recommend on Facebook Tweet Share Compartir On This ... CDC and EPA on mold cleanup, removal and remediation. Cleanup information for you and your family Homeowner’s ...

  16. Description of codes and models to be used in risk assessment

    International Nuclear Information System (INIS)

    1991-09-01

    Human health and environmental risk assessments will be performed as part of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) remedial investigation/feasibility study (RI/FS) activities at the Hanford Site. Analytical and computer encoded numerical models are commonly used during both the remedial investigation (RI) and feasibility study (FS) to predict or estimate the concentration of contaminants at the point of exposure to humans and/or the environment. This document has been prepared to identify the computer codes that will be used in support of RI/FS human health and environmental risk assessments at the Hanford Site. In addition to the CERCLA RI/FS process, it is recommended that these computer codes be used when fate and transport analyses is required for other activities. Additional computer codes may be used for other purposes (e.g., design of tracer tests, location of observation wells, etc.). This document provides guidance for unit managers in charge of RI/FS activities. Use of the same computer codes for all analytical activities at the Hanford Site will promote consistency, reduce the effort required to develop, validate, and implement models to simulate Hanford Site conditions, and expedite regulatory review. The discussion provides a description of how models will likely be developed and utilized at the Hanford Site. It is intended to summarize previous environmental-related modeling at the Hanford Site and provide background for future model development. The modeling capabilities that are desirable for the Hanford Site and the codes that were evaluated. The recommendations include the codes proposed to support future risk assessment modeling at the Hanford Site, and provides the rational for the codes selected. 27 refs., 3 figs., 1 tab

  17. Surveillance and maintenance report on decontamination and decommissioning and remedial action activities at the Oak Ridge Y-12 plant, Oak Ridge, Tennessee. Fiscal year 1996

    International Nuclear Information System (INIS)

    King, H.L.; Sollenberger, M.L.; Sparkman, D.E.; Reynolds, R.M.; Wayland, G.S.

    1996-12-01

    The Oak Ridge Y-12 Plant Decontamination and Decommissioning (D ampersand D) and Remedial Action (RA) programs are part of the Environmental Restoration (ER) Division and are funded by the Office of Environmental Management (EM-40). Building 9201-4 (known as Alpha-4), three sites located within Building 9201-3 (the Oil Storage Tank, the Molten Salt Reactor Experiment Fuel Handling Facility, and the Coolant Salt Technology Facility), and Building 9419-1 (the Decontamination Facility) are currently the facilities at the Y-12 Plant included in the D ampersand D program. The RA program provides surveillance and maintenance (S ampersand M) and program management of ER sites at the Y-12 Plant, including selected sites listed in Appendix C of the Federal Facilities Agreement (FFA), sites listed in the Hazardous and Solid Waste Amendment (HSWA) permit Solid Waste Management Unit (SWM-U) list, and sites currently closed or undergoing post-closure activities under the Resource Conservation and Recovery Act of 1976 (RCRA) or the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). This report communicates the status of the program plans and specific S ampersand M activities for the D ampersand D and RA programs

  18. The Department of Energy's Remedial Action Assessment System (RAAS): Decision support tools for performing streamlined feasibility studies

    International Nuclear Information System (INIS)

    White, M.K.

    1994-06-01

    The United States Department of Energy (DOE) faces the major task of cleaning up hundreds of waste sites across the nation, which will require completion of a large number of remedial investigation/feasibility studies (RI/FSs). The intent of each RI/FS is to characterize the waste problems and environmental conditions at the operable unit level, segment the remediation problem into manageable medium-specific and contaminant-specific pieces, define corresponding remediation objectives, and identify remedial response actions to satisfy those objectives. The RI/FS team can then identify combinations of remediation technologies that will meet the remediation objectives. Finally, the team must evaluate these remedial alternatives in terms of effectiveness, implementability, cost, and acceptability. The Remedial Action Assessment System (RAAS) is being developed by Pacific Northwest Laboratory (PNL) to support DOE in this effort

  19. Strategy paper. Remedial design/remedial action 100 Area. Revision 1

    International Nuclear Information System (INIS)

    Donahoe, R.L.

    1995-07-01

    The purpose of this planning document is to identify and define the approach for remedial design and remedial action (RD/RA) in the 100 Area of the Hanford Site, located in southeastern Washington State. Additionally, this document will support the Hanford Site Environmental Restoration Contract (ERC) team, the US Department of Energy (DOE), and regulatory agencies in identifying and agreeing upon the complete process for expedited cleanup of the 100 Area

  20. Electrodialytic Remediation of Copper Mine Tailings

    DEFF Research Database (Denmark)

    Hansen, H.K.; Rojo, A.; Ottosen, L.M.

    2012-01-01

    This work compares and evaluates sixteen electrodialytic laboratory remediation experiments on copper mine tailings. Different parameters were analysed, such as remediation time, addition of desorbing agents, and the use of pulsed electrical fields.......This work compares and evaluates sixteen electrodialytic laboratory remediation experiments on copper mine tailings. Different parameters were analysed, such as remediation time, addition of desorbing agents, and the use of pulsed electrical fields....