WorldWideScience

Sample records for candu steam generator

  1. CANDU steam generator life management

    International Nuclear Information System (INIS)

    Tapping, R.L.; Nickerson, J.; Spekkens, P.; Maruska, C.

    1998-01-01

    Steam generators are a critical component of a nuclear power reactor, and can contribute significantly to station unavailability, as has been amply demonstrated in Pressurized Water Reactors (PWRs). CANDU steam generators are not immune to steam generator degradation, and the variety of CANDU steam generator designs and tube materials has led to some unexpected challenges. However, aggressive remedial actions, and careful proactive maintenance activities, have led to a decrease in steam generator-related station unavailability of Canadian CANDUs. AECL and the CANDU utilities have defined programs that will enable existing or new steam generators to operate effectively for 40 years. Research and development work covers corrosion and mechanical degradation of tube bundles and internals, chemistry, thermalhydraulics, fouling, inspection and cleaning, as well as provision for specially tool development for specific problem solving. A major driving force is development of CANDU-specific fitness-for-service guidelines, including appropriate inspection and monitoring technology to measure steam generator condition. Longer-range work focuses on development of intelligent on-line monitoring for the feedwater system and steam generator. New designs have reduced risk of corrosion and fouling, are more easily inspected and cleaned, and are less susceptible to mechanical damage. The Canadian CANDU utilities have developed programs for remedial actions to combat degradation of performance (Gentilly-2, Point Lepreau, Bruce A/B, Pickering A/B), and have developed strategic plans to ensure that good future operation is ensured. The research and development program, as well as operating experience, has identified where improvements in operating practices and/or designs can be made in order to ensure steam generator design life at an acceptable capacity factory. (author)

  2. Considerations in selecting tubing materials for CANDU steam generators

    International Nuclear Information System (INIS)

    Hemmings, R.L.

    1978-01-01

    Corrosion resistance is the major consideration in selecting tubing material for CANDU steam generators. Corrosion, and additional considerations, lead to the following steam generator tubing material recommendations: for CANDU-BPHWR's (boiling pressurized heavy water reactors) low-cobalt Incoloy-800; for CANDU-PHWR's (pressurized, non-boiling, heavy water reactors), low-cobalt Monel-400

  3. The ageing of CANDU steam generator due to localized corrosion

    International Nuclear Information System (INIS)

    Lucan, D.; Fulger, M.; Jinescu, Ghe.

    2001-01-01

    The principal types of corrosion are presented which can occur in CANDU steam generator. There are also presented the operation conditions, the specifications referring to the water chemistry and the construction materials of Steam Generator, the factors that have a great influence on the corrosion behaviour during the whole exploitation period of this equipment. The most important elements of CANDU Steam Generator ageing management program are also discussed. (R. P.)

  4. Technical basis for the CANDU steam generator tube fitness-for-service guidelines

    International Nuclear Information System (INIS)

    Kozluk, M.J.; Scarth, D.A.; Graham, D.B.

    2002-01-01

    Active degradation mechanisms in steam generators and preheaters in Canadian CANDU T M generating stations are managed through Steam Generator Programs that incorporate tube inspection, maintenance (cleaning), fitness-for-service assessment, and preventative plugging as part of the overall steam generator management strategy. Steam generator and preheater tubes are inspected in accordance with the CSA Standard CAN/CSA-N285.4-94[l]. When a detected flaw indication does not satisfy the criteria of acceptance by examination, CSA-N285.4-94 permits a fitness-for-service assessment to determine acceptability. In 1999 Ontario Power Generation issued, for trial use, fitness-for-service guidelines for steam generator and preheater tubes in CANDU nuclear power plants. The main objectives of the Fitness-for-Service Guidelines are to provide reasonable assurance that tube structural integrity is maintained, and to provide reasonable assurance that there are adequate margins between estimated accumulated dose and applicable site dose limits. The Fitness-for-Service Guidelines are intended to provide industry-standard acceptance criteria and evaluation procedures for assessing the condition of steam generator and preheater tubes in terms of tube structural integrity, operational leak rate, and consequential leakage during an upset or abnormal event. This paper describes the technical basis for the minimum required safety factors specified in Table IC-1 of the Fitness-for-Service Guidelines and for the flaw models used to develop the flaw stability requirements in the nonmandatory, Appendix C of the Fitness-for-Service Guidelines. (author)

  5. Preliminary analysis for u tube degradation in CANDU steam generator using CATHENA

    Energy Technology Data Exchange (ETDEWEB)

    Shin, So Eun; Lee, Jeong Hun; Park, Tong Kyu; Hwang, Su Hyun [FNC Technology Co., Seoul (Korea, Republic of); Jung, Jong Yeo [KAERI, Daejeon (Korea, Republic of)

    2012-10-15

    The interest in plant safety and integrity has been increasing due to long term operation of nuclear power plants (NPPs) and lots of efforts have been devoted to developing the degradation evaluation model for all the Structure, System, and Components (SSCs) of NPPs in these days. The efforts, however, were mainly concentrated on pressurized light water reactors (PWRs) in domestic. In contrast, the study for the aging degradation of counterparts of CANDU (CANada Deuterium Uranium) reactors has been rarely performed, even though Wolsong unit 1 (WS1), that is a CANDU 6 NPP in Korea, has been operating for almost 30 years. Therefore, the assessment of the aging degradation is required and the proper and exact evaluation model for the aging degradation of SCCs of CANDU, especially WS1, is urgently needed. In this study, the aging degradation of steam generators (SGs) in WS1 was mainly discussed. Based on cases of the aging degradation of SGs in overseas CANDU reactors, the major potential aging mechanisms of SGs were estimated since there has been no case of accident due to degradation in CANDU NPPs in Korea . Some core parameters which are indicators of the degree of degradation were calculated by CATHENA (Canadian algorithm for thermal hydraulic network analysis). In the result of comparing two calculation cases; core parameters for only aged SGs in fresh plant and those for all the aged component, it can be concluded that aging of SGs is a main component in the degradation assessment of CANDU NPPs, and keeping the integrity of steam generator (SG) tubes is important to guarantee the safety of the NPPs.

  6. CANDU steam generator tubing material service experience and allied development

    International Nuclear Information System (INIS)

    Hart, A.E.; Lesurf, J.E.

    1976-01-01

    This paper covers the following aspects for the tube materials in CANDU-PHW steam generators: inservice performance with respect to tube leaks and coolant activity attributable to boiler tube corrosion, selection of tube materials for use with non-boiling and boiling primary coolants, supporting development on corrosion, vibration, fretting wear, tube inspection, leak detection and plugging of defective tubes. (author)

  7. Maintenance and plugging technology for CANDU steam generator tubing

    International Nuclear Information System (INIS)

    Prince, J.; Nicholson, A.; Hare, J.; McGoey, L.; Stafford, T.; Gowthorpe, P.

    2006-01-01

    In order to keep aging steam generators in service and to successfully manage the life of these critical components, the capability must exist to perform tube plugging and other complex maintenance activities in-situ. In the early days of CANDU steam generator operation, the only option was to perform these activities manually, which had inherent safety and quality risks. The challenge was to be able to perform these activities remotely thus eliminating some of the confined space and radiological exposure risks. The additional challenge was to develop equipment and techniques which would result in significantly improved quality, particularly for the completed plug welds which would be returned to service. Over the past fifteen years, this technology has matured and has produced remarkable results in field application. Some 14000 tube plugs have been successfully installed to date using automated plugging techniques. This paper presents an overview of the development of techniques available to utilities for steam generator tube plugging as well as some highlights of other steam generator tube maintenance activities such as primary side tube removal and tube end damage repair. Aspects covered in the paper include plug and procedure development, automated equipment and manipulators for tool deployment, process controls and personnel requirements. Recently, the steam generator tube plugging performed by OPG has been incorporated into a formal quality program under the requirements of ASME NCA 4000. An overview of the quality program will be presented and details of some of the important aspects of the quality program will be discussed. (author)

  8. Experimental modeling of flow-induced vibration of multi-span U-tubes in a CANDU steam generator

    International Nuclear Information System (INIS)

    Mohany, A.; Feenstra, P.; Janzen, V.P.; Richard, R.

    2009-01-01

    Flow-induced vibration of the tubes in a nuclear steam generator is a concern for designers who are trying to increase the life span of these units. The dominant excitation mechanisms are fluidelastic instability and random turbulence excitation. The outermost U-bend region of the tubes is of greatest concern because the flow is almost perpendicular to the tube axis and the unsupported span is relatively long. The support system in this region must be well designed in order to minimize fretting wear of the tubes at the support locations. Much of the previous testing was conducted on straight single-span or cantilevered tubes in cross-flow. However, the dynamic response of steam generator multi-span U-tubes with clearance supports is expected to be different. Accurate modeling of the tube dynamics is important to properly simulate the dynamic interaction of the tube and supports. This paper describes a test program that was developed to measure the dynamic response of a bundle of steam generator U-tubes with Anti-Vibration Bar (AVB) supports, subjected to Freon two-phase cross-flow. The tube bundle has similar geometrical conditions to those expected for future CANDU steam generators. Future steam generators will be larger than previous CANDU steam generators, nearly twice the heat transfer area, with significant changes in process conditions in the U-bend region, such as increased steam quality and a broader range of flow velocities. This test program was initiated at AECL to demonstrate that the tube support design for future CANDU steam generators will meet the stringent requirements associated with a 60 year design life. The main objective of the tests is to address the issue of in-plane and out-of-plane fluidelastic instability and random turbulent excitation of a U-tube bundle with Anti-Vibration Bar (AVB) supports. Details of the test rig, measurement techniques and preliminary instrumentation results are described in the paper. (author)

  9. Steam generator life management

    International Nuclear Information System (INIS)

    Tapping, R.L.; Nickerson, J.; Spekkens, P.; Maruska, C.

    1998-01-01

    Steam generators are a critical component of a nuclear power reactor, and can contribute significantly to station unavailability, as has been amply demonstrated in Pressurized Water Reactors (PWRs). CANDU steam generators are not immune to steam generator degradation, and the variety of CANDU steam generator designs and tube materials has led to some unexpected challenges. However, aggressive remedial actions, and careful proactive maintenance activities, have led to a decrease in steam generator-related station unavailability of Canadian CANDUs. AECL and the CANDU utilities have defined programs that will enable existing or new steam generators to operate effectively for 40 years. Research and development work covers corrosion and mechanical degradation of tube bundles and internals, chemistry, thermal hydraulics, fouling, inspection and cleaning, as well as provision for specially tool development for specific problem solving. A major driving force is development of CANDU-specific fitness-for-service guidelines, including appropriate inspection and monitoring technology to measure steam generator condition. Longer-range work focuses on development of intelligent on-line monitoring for the feedwater system and steam generator. New designs have reduced risk of corrosion and fouling, are more easily inspected and cleaned, and are less susceptible to mechanical damage. The Canadian CANDU utilities have developed programs for remedial actions to combat degradation of performance (Gentilly-2, Point Lepreau, Bruce A/B, Pickering A/B), and have developed strategic plans to ensure that good future operation is ensured. This report shows how recent advances in cleaning technology are integrated into a life management strategy, discusses downcomer flow measurement as a means of monitoring steam generator condition, and describes recent advances in hideout return as a life management tool. The research and development program, as well as operating experience, has identified

  10. CANDU steam generator aging management: Some perspectives after 20 years in-service experience

    International Nuclear Information System (INIS)

    Tapping, R.I.; Nickerson, J.; Subash, N.; Roy, S.

    2002-01-01

    CANDU units have been placed in lay-up whilst condition assessments and rehabilitation programs are carried out. These rehabilitations, although costly, are justified economically. The economics require careful evaluation of current condition and, especially challenging, of remaining life. Review of the current condition of the SGs that have been laid up demonstrates the importance of layup chemistry control practices, and the variability introduced by the different tube materials. Questions arising from the layup condition, and its impact on future life, are difficult to address quantitatively. Further R and D is required to define the linkage between layup condition and future aging degradation. At CANDU 6 plants, there has been an excellent steam generator service record with little or no significant active degradation to date and several of the utilities are actively pursuing the option of planning for extended operation. At three of the older CANDU 6 plants, detailed and comprehensive life assessment studies of the steam generating equipment, the interfacing systems, the external support structure, the tubing, and all the key internal sub-components, has been completed. The studies involved a very thorough assessment of tubing corrosion mechanisms that can occur in various forms in nuclear steam generators. CANDU-6 SGs are tubed with Alloy 800M (M means m odified ) and have experienced relatively little SG tube corrosion to date. Despite this excellent record, it is well known that steam generators provide challenges for the assurance of continued on-going good health, as operation continues through to design life and particularly for a significant period of extended operation beyond. While the prognosis for life attainment and for extended operation of CANDU 6 Steam Generators is good, it has also been found that this conclusion is very dependent upon implementation of the recommended program enhancements of inspections, maintenance, chemistry control and

  11. Characteristics of U-tube assembly design for CANDU 6 type steam generators

    International Nuclear Information System (INIS)

    Park, Jun Su; Jeong, Seung Ha

    1996-06-01

    Since the first operation of nuclear steam generator early 1960s, its performance requirements have been met but the steam generator problems have been met but the steam generator problems have been major cause of reducing the operational reliability, plant safety and availability. U-tube assembly of steam generator forms the primary system pressure boundary of the plant and have experienced several types of tube degradation problems. Tube failure and leakage resulting from the degradation will cause radioactive contamination of secondary system by the primary coolant, and this may lead to unplanned plant outages and costly repair operations such as tube plugging or steam generator replacement. For the case of steam generators for heavy water reactors, e.g. Wolsong 2, 3, and 4 NPP, a high cost of heavy water will be imposed additionally. During the plant operation, steam generator tubes can potentially be subject to adverse environmental conditions which will cause damages to U-tube assembly. Types of the damage depend upon the combined effects of design factors, materials and chemical environment of steam generator, and they are the pure water stress corrosion cracking, intergranular attack, pitting, wastage, denting, fretting and fatigue, etc. In this report, a comprehensive review of major design factors of recirculating steam generators has been performed against the potential tube damages. Then the design characteristics of CANDU-type Wolsong steam generator were investigated in detail, including tube material, thermalhydraulic aspects, tube-to-tubesheet joint, tube supports, water chemistry and sludge management. 9 tabs., 18 figs., 38 refs. (Author) .new

  12. Eddy Currents Inspection of CANDU Steam Generator Tubes using Zetec's ZR-1 Robot. Experience in Romania

    International Nuclear Information System (INIS)

    Scott Hower; Luiza Vladu; Adrian Nichisov; Mihai Cretu

    2006-01-01

    Full text of publication follows: The commercial operation of Unit 1 of Cernavoda NPP started on 2 December, 1996. The unit's reactor type is PHWR-CANDU 6 (electrical capacity 706 MWe), using natural uranium. The nuclear fuel is manufactured in Romania. The Cernavoda nuclear power plant has four CANDU - design steam generators that have been in service since 1996. The paper introduces the new ZR-1 Robot System for Inspection and Maintenance/Repair from Zetec that combines the newest state-of-the-art robotics technology with Zetec experience - based innovation to address the needs for inspection and repair of steam generators. The multipurpose ZR-1 can be easily installed to perform the necessary eddy current inspection and remain installed ready for follow-up maintenance and repair. It has superior technical performances and a modular three axis motion of arm that enables 100% coverage of tube sheet. Automated, repeatable, and precise positioning of tool heads ensures accurate delivery and reducing costly rework and reduces inspection time by 30%. The modular, light weight, and portable design permits easy assembly and disassembly through small openings and it reduces setup/tear down time by 30%. The first deployment of the new ZR-1 Robot was made in September 2004 at the Cernavoda NPP inspection outage. The unit's reactor type is PHWR-CANDU 6 (electrical capacity 706 MWe), using natural uranium; the nuclear fuel is manufactured in Romania. The Cernavoda nuclear power plant Unit 1 has four CANDU - design steam generators that have been in service since 1996. The paper presents also the Zetec's field experience and customer experience with this system. It describes the equipment setup in Cernavoda's steam generators mock-up, functional tests and calibration. Finally, provides details on the execution of the inspection, options for standardizing the inspection techniques and conclusions. (authors)

  13. Eddy Currents Inspection of CANDU Steam Generator Tubes using Zetec's ZR-1 Robot. Experience in Romania

    Energy Technology Data Exchange (ETDEWEB)

    Scott Hower [Zetec Inc. (Romania); Luiza Vladu; Adrian Nichisov; Mihai Cretu [COMPCONTROL ING. (Romania)

    2006-07-01

    Full text of publication follows: The commercial operation of Unit 1 of Cernavoda NPP started on 2 December, 1996. The unit's reactor type is PHWR-CANDU 6 (electrical capacity 706 MWe), using natural uranium. The nuclear fuel is manufactured in Romania. The Cernavoda nuclear power plant has four CANDU - design steam generators that have been in service since 1996. The paper introduces the new ZR-1 Robot System for Inspection and Maintenance/Repair from Zetec that combines the newest state-of-the-art robotics technology with Zetec experience - based innovation to address the needs for inspection and repair of steam generators. The multipurpose ZR-1 can be easily installed to perform the necessary eddy current inspection and remain installed ready for follow-up maintenance and repair. It has superior technical performances and a modular three axis motion of arm that enables 100% coverage of tube sheet. Automated, repeatable, and precise positioning of tool heads ensures accurate delivery and reducing costly rework and reduces inspection time by 30%. The modular, light weight, and portable design permits easy assembly and disassembly through small openings and it reduces setup/tear down time by 30%. The first deployment of the new ZR-1 Robot was made in September 2004 at the Cernavoda NPP inspection outage. The unit's reactor type is PHWR-CANDU 6 (electrical capacity 706 MWe), using natural uranium; the nuclear fuel is manufactured in Romania. The Cernavoda nuclear power plant Unit 1 has four CANDU - design steam generators that have been in service since 1996. The paper presents also the Zetec's field experience and customer experience with this system. It describes the equipment setup in Cernavoda's steam generators mock-up, functional tests and calibration. Finally, provides details on the execution of the inspection, options for standardizing the inspection techniques and conclusions. (authors)

  14. Steam generator water lancing

    International Nuclear Information System (INIS)

    Kamler, F.; Schneider, W.

    1992-01-01

    The tubesheet and tube support plate deposits in CANDU steam generators are notable for their hardness. Also notable is the wide variety of steam generator access situations. Because of the sludge hardness and the difficulty of the access, traditional water lancing processes which directed jets from the central tube free lane or from the periphery of the bundle have proven unsuitable. This has led to the need for some very unique inter tube water lancing devices which could direct powerful water jets directly onto the deposits. This type of process was applied to the upper broached plates of the Bruce A steam generators, which had become severely blocked. It has since been applied to various other steam generator situations. This paper describes the flexlance equipment development, qualification, and performance in the various CANDU applications. 4 refs., 2 tabs., 7 figs

  15. CANDU steam generator life management: laboratory data and plant experience

    International Nuclear Information System (INIS)

    Tapping, R.L.; Nickerson, J.H.; Subash, N.; Wright, M.D.

    2001-10-01

    As CANDU reactors enter middle age, and the potential value of the plants in a deregulated market is realized, life management and life extension issues become increasingly important. An accurate assessment of critical components, such as the CANDU 6 steam generators (SGs), is crucial for successful life extension, and in this context, material issues are a key factor. For example, service experience with Alloy 900 tubing indicates very low levels of degradation within CANDU SGs; the same is also noted worldwide. With little field data for extrapolation, life management and life extension decisions for the tube bundles rely heavily on laboratory data. Similarly, other components of the SGs, in particular the secondary side internals, have only limited inspection data upon which to base a condition assessment. However, in this case there are also relatively little laboratory data. Decisions on life management and life extension are further complicated--not only is inspection access often restricted, but repair or replacement options for internal components are, by definition, also limited. The application of CANDU SG life management and life extension requires a judicious blend of in-service data, laboratory research and development (R and D) and materials and engineering judgment. For instance, the available laboratory corrosion and fretting wear data for Alloy 800 SG tubing have been compared with plant experience (with all types of tubing), and with crevice chemistry simulations, in order to provide an appropriate inspection guide for a 50-year SG life. A similar approach has been taken with other SG components, where the emphasis has been on known degradation mechanisms worldwide. This paper provides an outline of the CANDU SG life management program, including the results to date, a summary of the supporting R and D program showing the integration with condition assessment and life management activities, and the approach taken to life extension for a typical

  16. Babcock and Wilcox Canada steam generators past, present and future

    Energy Technology Data Exchange (ETDEWEB)

    Smith, J.C. [Babcock and Wilcox Canada, Cambridge, Ontario (Canada)

    1998-07-01

    The steam generators in all of the domestic CANDU Plants, and most of the foreign CANDU plants, were supplied by Babcock and Wilcox Canada, either on their own or in co-operation with local manufacturers. More than 200 steam generators have been supplied. In addition, Babcock and Wilcox Canada has taken the technology which evolved out of the CANDU steam generators and has adapted the technology to supply of replacement steam generators for PWR's. There is enough history and operating experience, plus laboratory experience, to point to the future directions which will be taken in steam generator design. This paper documents the steam generators which have been supplied, the experience in operation and maintenance, what has worked and not worked, and how the design, materials, and operating and maintenance philosophy have evolved. The paper also looks at future requirements in the market, and the continuing research and product development going on at Babcock and Wilcox to address the future steam generator requirements. (author)

  17. Babcock and Wilcox Canada steam generators past, present and future

    International Nuclear Information System (INIS)

    Smith, J.C.

    1998-01-01

    The steam generators in all of the domestic CANDU Plants, and most of the foreign CANDU plants, were supplied by Babcock and Wilcox Canada, either on their own or in co-operation with local manufacturers. More than 200 steam generators have been supplied. In addition, Babcock and Wilcox Canada has taken the technology which evolved out of the CANDU steam generators and has adapted the technology to supply of replacement steam generators for PWR's. There is enough history and operating experience, plus laboratory experience, to point to the future directions which will be taken in steam generator design. This paper documents the steam generators which have been supplied, the experience in operation and maintenance, what has worked and not worked, and how the design, materials, and operating and maintenance philosophy have evolved. The paper also looks at future requirements in the market, and the continuing research and product development going on at Babcock and Wilcox to address the future steam generator requirements. (author)

  18. Regulation of ageing steam generators

    International Nuclear Information System (INIS)

    Jarman, B.L.; Grant, I.M.; Garg, R.

    1998-01-01

    Recent years have seen leaks and shutdowns of Canadian CANDU plants due to steam generator tube degradation by mechanisms including stress corrosion cracking, fretting and pitting. Failure of a single steam generator tube, or even a few tubes, would not be a serious safety related event in a CANDU reactor. The leakage from a ruptured tube is within the makeup capacity of the primary heat transport system, so that as long as the operator takes the correct actions, the off-site consequences will be negligible. However, assurance that no tubes deteriorate to the point where their integrity could be seriously breached as result of potential accidents, and that any leakage caused by such an accident will be small enough to be inconsequential, can only be obtained through detailed monitoring and management of steam generator condition. This paper presents the AECB's current approach and future regulatory directions regarding ageing steam generators. (author)

  19. A survey on the corrosion susceptibility of Alloy 800 CANDU steam generator tubing materials

    International Nuclear Information System (INIS)

    Lu, Y.C.; Dupuis, M.; Burns, D.

    2008-01-01

    To provide support for a proactive steam generator (SG) aging management strategy, a survey on the corrosion susceptibility of the archived Alloy 800 tubing from CANDU SGs under plausible crevice chemistry conditions was conducted to assess the potential material degradation issues in CANDU SGs. Archived Alloy 800 samples were collected from four CANDU utilities. High-temperature electrochemical analysis was carried out to assess the corrosion susceptibility of the archived SG tubing under simulated CANDU crevice chemistry conditions at both 150 o C and 300 o C. The potentiodynamic polarization results obtained from the archived CANDU SG tubes were compared to the data from ex-service tubes removed from Darlington Nuclear Generating Station (DNGS) SGs and a reference nuclear grade Alloy 800 tubing. It was found that the removed Darlington SG tubes, with signs of in-service degradation, were more susceptible to pitting corrosion than the reference nuclear grade Alloy 800 tubing. At 150 o C, under the same neutral crevice chemistry conditions, the potentiodynamic polarization curve of the ex-service Darlington SG tubing has an active peak, which is a sign of propensity to crevice/underdeposit corrosion. This active peak was not observed in any of the potentiodynamic polarization curves of all archived Alloy 800 CANDU SG tubing indicating that archived CANDU SG tubes are less susceptible to the underdeposit corrosion under SG startup conditions. The corrosion behaviour of the archived Alloy 800 tubes from CANDU SG was similar to that of the reference nuclear grade Alloy 800 tubing. The results of this survey suggest that the Alloy 800 tubing materials used in the existing CANDU utilities (other than ex-service DNGS tubing) will continue to have reliable performance under specified CANDU operating conditions. Ex-service SG tubing from DNGS, although showing lower than average corrosion resistance, still has a wide acceptable operating margin and the in

  20. Design specifications to ensure flow-induced vibration and fretting-wear performance in CANDU steam generators and heat exchangers

    International Nuclear Information System (INIS)

    Janzen, V.P.; Han, Y.; Pettigrew, M.J.

    2009-01-01

    Preventing flow-induced vibration and fretting-wear problems in steam generators and heat exchangers requires design specifications that bring together specific guidelines, analysis methods, requirements and appropriate performance criteria. This paper outlines the steps required to generate and support such design specifications for CANDU nuclear steam generators and heat exchangers, and relates them to typical steam-generator design features and computer modeling capabilities. It also describes current issues that are driving changes to flow-induced vibration and fretting-wear specifications that can be applied to the design process for component refurbishment, replacement or new designs. These issues include recent experimental or field evidence for new excitation mechanisms, e.g., the possibility of in-plane fluidelastic instability of U-tubes, the demand for longer reactor and component lifetimes, the need for better predictions of dynamic properties and vibration response, e.g., two-phase random-turbulence excitation, and requirements to consider system 'excursions' or abnormal scenarios, e.g., a main steam line break in the case of steam generators. The paper describes steps being taken to resolve these issues. (author)

  1. Steam generators: critical components in nuclear steam supply systems

    Energy Technology Data Exchange (ETDEWEB)

    Stevens-Guille, P D

    1974-02-28

    Steam generators are critical components in power reactors. Even small internal leaks result in costly shutdowns for repair. Surveys show that leaks have affected one half of all water-cooled reactors in the world with steam generators. CANDU reactors have demonstrated the highest reliability. However, AECL is actively evolving new technology in design, manufacture, inspection and operation to maintain reliability. (auth)

  2. CATHENA analysis of CANDU 6 steam generators for steam main break at a remote location

    Energy Technology Data Exchange (ETDEWEB)

    Liu, T. [Atomic Energy of Canada Limited, Chalk River, Ontario (Canada)

    2009-07-01

    CATHENA (Canadian Algorithm for THErmalhydraulic Network Analysis) is a nonequilibrium, two-phase, two fluid network analysis code that has been in use for over two decades by various groups in Canada and around the world. It is the primary Thermalhydraulics network analysis tool used by Atomic Energy Canada Ltd. (AECL) in the design, safety and licensing analysis of power and research reactors as well as test facilities. In the thermalhydraulic model, the liquid and vapor phases may have different pressures, velocities, and temperatures. The objective of the present paper is to present the detailed modeling of a CANDU 6 Steam Generator (SG) using the transient, thermalhydraulics network code CATHENA. The model represents the secondary side, primary side and the main steam system including the main steam line up to the assumed break location. The present model is designed such that the transient pressure drops across Tube Support Plates (TSP) could be extracted. The resistances of degraded/fouled TSPs were modeled by using the increased/reduced flow area of the TSPs. CATHENA then calculates the flow resistance in two-phase flow based on the area contraction/expansion at the TSPs. Three sets of simulations were performed; one with the degraded steam generator data provided by the utility users, and the other two with waterlanced (cleaned with high pressure water jet) TSPs. One run assumed the flow area increased by 25 percent, the other run assumed the flow area increased by 50 percent. on the hot side of the SG. No significant changes in the break discharge rates were observed between the runs. However, the steam generator downcomer flow for the waterlanced case did not reverse during the blowdown as was calculated for the degraded case. As expected, the pressure drop across the TSPs was decreased in the waterlanced cases comparing with degraded cases. The CATHENA simulation provides estimates of the velocity, density, and quality in the tube bundle as well as

  3. Thermal-hydraulics in recirculating steam generators

    International Nuclear Information System (INIS)

    Carver, M.B.; Carlucci, L.N.; Inch, W.W.R.

    1981-04-01

    This manual describes the THIRST code and its use in computing three-dimensional two-phase flow and heat transfer in a steam generator under steady state operation. The manual is intended primarily to facilitate the application of the code to the analysis of steam generators typical of CANDU nuclear stations. Application to other steam generator designs is also discussed. Details of the assumptions used to formulate the model and to implement the numerical solution are also included

  4. Experimental research regarding the corrosion of incoloy-800 and SA 508 cl.2 in the CANDU steam generator

    International Nuclear Information System (INIS)

    Lucan, D.; Fulger, M.; Savu, G.; Velciu, L.

    2004-01-01

    Steam generators (SGs) are crucial components of pressurized water reactors. The failure of the steam generator as a result of tube degradation by corrosion has been a major cause of Pressurized Water Reactor (PWR) plant unavailability. Steam generator problems have caused major economic losses in terms of lost electricity production through forced unit outages and, in cases of extreme damage, as additional direct cost for large-scale repair or replacement of steam generators. Steam generator tubes are susceptible to failure by a variety of mechanisms, the vast majority of which are related a corrosion. The feedwater that enters into the steam generators under normal operating conditions is extremely pure, but nevertheless contains low levels (generally in the μg/l concentration range) of impurities such as iron, chloride, sulphate, silicate, etc. When water is converted to steam and exits the steam generator, the non-volatile impurities are left behind. As a result, their concentration in the bulk steam generator water is considerably higher than those in the feedwater. Nevertheless, the concentrations of corrosive impurities are still generally sufficiently low that the bulk water is not significantly aggressive towards steam generator materials. The excellent performance to date of CANDU steam generators can be attributed, in part, to their design and performance characteristics, which typically involve higher recirculation ratios and lower heat fluxes and temperatures. The purpose of this paper consists in assessment of generalized corrosion behaviour of the tubes materials (Incoloy-800) and tubesheet material (carbon steel SA 508 cl.2) at the normal secondary circuit parameters (temperature-260 deg C, pressure-5.1MPa). The testing environment was the demineralized water without impurities, at pH=9.5 regulated with morpholine and ciclohexilamine (all volatile treatment - AVT). The results are presented like micrographies and graphics representing loss of metal

  5. Heat exchanger tubing materials for CANDU nuclear generating stations

    International Nuclear Information System (INIS)

    Taylor, G.F.

    1977-07-01

    The performance of steam generator tubing (nickel-chromium-iron alloy in NPD and nickel-copper alloy in Douglas Point and Pickering generating stations) has been outstanding and no corrosion-induced failures have occurred. The primary coolant will be allowed to boil in the 600 MW (electrical) CANDU-PHW reactors. An iron-nickel-chromium alloy has been selected for the steam generator tubing because it will result in lower radiation fields than the alloys used before. It is also more resistant than nickel-chromium-iron alloy to stress corrosion cracking in the high purity water of the primary circuit, an unlikely but conceivable hazard associated with higher operating temperatures. Austenitic alloy and ferritic-austenitic stainless steel tubing have been selected for the moderator coolers in CANDU reactors being designed and under construction. These materials will reduce the radiation fields around the moderator circuit while retaining the good resistance to corrosion in service water that has characterized the copper-nickel alloys now in use. Brass and bronze tubes in feedwater heaters and condensers have given satisfactory service but do, however, complicate corrosion control in the steam cycle and, to reduce the transport of corrosion products from the feedtrain to the steam generator, stainless steel is preferred for feedwater heaters and stainlss steel or titanium for condensers. (author)

  6. Wet steam turbines for CANDU-Reactors

    International Nuclear Information System (INIS)

    Westmacott, C.H.L.

    1977-01-01

    The technical characteristics of 4 wet steam turbine aggregates used in the Pickering nuclear power station are reported on along with operational experience. So far, the general experience was positive. Furthermore, plans are mentioned to use this type of turbines in other CANDU reactors. (UA) [de

  7. Assessing the thermal-hydraulic behaviour of steam generators in a CANDU-6 type NPP in the event of MSSV blockage on the open-setting

    International Nuclear Information System (INIS)

    Dinca, Elena

    2004-01-01

    This work aims at achieving an analysis regarding the thermal-hydraulic behaviour of a CANDU-6 type NPP in the event of the blockage on open-setting of an MSSV (Main Steam Safety Valve) for steam relief from steam generators. The systems studied are main steam and feedwater mixture in the secondary circuit, particularly being analyzed the behaviour of the steam generators as well as the primary heat transfer and the control system of heavy water pressure and inventory in the primary system. One supposes that the MSSV blockage occurs directly after its opening in the event of an accident that led to the a steam pressure rise in the steam generators up to the threshold value of MSSV o penning. The analysis was applied to two events of initiation which lead to MSSV o penning, namely a Class IV loss of electric supply and loss of vacuum in turbine condenser. In the simulation of the events selected for analysis a long elapse of time is supposed (3600 seconds) and no operator intervention while the NPP is operating at rating power and equilibrium fuel regime. Each of the two events were analyzed for two distinct sets of conditions of event initiation and evolution. The study was focussed on the behaviour of NPP, particularly of the steam generators, and on the estimation of the amount of water in the secondary circuit released into the atmosphere during the event. The analysis is of deterministic type and supplies information required by the Probabilistic Safety Assessment (PSA) applied to nuclear facilities in establishing the operation procedures and documentation. The analysis was based on design data for a CANDU-6 NPP and the HYDN3 code for thermal-hydraulic computation in CANDU type NPPs. In the paper there are presented the analysis, methodology, models, hypotheses and the input data as well as the analyzed cases. Within the computing code some models were developed to allow simulating the event sequences chosen for analyses. The results are plotted and

  8. Predicting steam generator crevice chemistry

    International Nuclear Information System (INIS)

    Burton, G.; Strati, G.

    2006-01-01

    'Full text:' Corrosion of steam cycle components produces insoluble material, mostly iron oxides, that are transported to the steam generator (SG) via the feedwater and deposited on internal surfaces such as the tubes, tube support plates and the tubesheet. The build up of these corrosion products over time can lead to regions of restricted flow with water chemistry that may be significantly different, and potentially more corrosive to SG tube material, than the bulk steam generator water chemistry. The aim of the present work is to predict SG crevice chemistry using experimentation and modelling as part of AECL's overall strategy for steam generator life management. Hideout-return experiments are performed under CANDU steam generator conditions to assess the accumulation of impurities in hideout, and return from, model crevices. The results are used to validate the ChemSolv model that predicts steam generator crevice impurity concentrations, and high temperature pH, based on process parameters (e.g., heat flux, primary side temperature) and blowdown water chemistry. The model has been incorporated into ChemAND, AECL's system health monitoring software for chemistry monitoring, analysis and diagnostics that has been installed at two domestic and one international CANDU station. ChemAND provides the station chemists with the only method to predict SG crevice chemistry. In one recent application, the software has been used to evaluate the crevice chemistry based on the elevated, but balanced, SG bulk water impurity concentrations present during reactor startup, in order to reduce hold times. The present paper will describe recent hideout-return experiments that are used for the validation of the ChemSolv model, station experience using the software, and improvements to predict the crevice electrochemical potential that will permit station staff to ensure that the SG tubes are in the 'safe operating zone' predicted by Lu (AECL). (author)

  9. Chemical control and design considerations for CANDU-PHW steam generators

    International Nuclear Information System (INIS)

    Frost, C.R.; Churchill, B.R.

    1978-01-01

    Ontario Hydro presently operates eight nuclear power units with a total capacitiy of about 4000 MW(e) net. Operating experience has been with Monel-400 and with Inconel-600 tubed steam generators using sodium phosphate or all volatile control of the boiler steam and water system. With a heavy water Heat Transport System, steam generator tube integrity is an essential ingredient of economical power production. Only three steam generator tube failures have occurred so far in about 40 unit-years operation. None was attributable to corrosion. Factors in the good reliability are, careful engineering design, good quality control at all stages of tubing and steam generator manufacture and close chemical control. The continuing evolution of our steam generator design means that future requirements will be more stringent. (author)

  10. Steam generator tube failures

    International Nuclear Information System (INIS)

    MacDonald, P.E.; Shah, V.N.; Ward, L.W.; Ellison, P.G.

    1996-04-01

    A review and summary of the available information on steam generator tubing failures and the impact of these failures on plant safety is presented. The following topics are covered: pressurized water reactor (PWR), Canadian deuterium uranium (CANDU) reactor, and Russian water moderated, water cooled energy reactor (VVER) steam generator degradation, PWR steam generator tube ruptures, the thermal-hydraulic response of a PWR plant with a faulted steam generator, the risk significance of steam generator tube rupture accidents, tubing inspection requirements and fitness-for-service criteria in various countries, and defect detection reliability and sizing accuracy. A significant number of steam generator tubes are defective and are removed from service or repaired each year. This wide spread damage has been caused by many diverse degradation mechanisms, some of which are difficult to detect and predict. In addition, spontaneous tube ruptures have occurred at the rate of about one every 2 years over the last 20 years, and incipient tube ruptures (tube failures usually identified with leak detection monitors just before rupture) have been occurring at the rate of about one per year. These ruptures have caused complex plant transients which have not always been easy for the reactor operators to control. Our analysis shows that if more than 15 tubes rupture during a main steam line break, the system response could lead to core melting. Although spontaneous and induced steam generator tube ruptures are small contributors to the total core damage frequency calculated in probabilistic risk assessments, they are risk significant because the radionuclides are likely to bypass the reactor containment building. The frequency of steam generator tube ruptures can be significantly reduced through appropriate and timely inspections and repairs or removal from service

  11. Non-electrical CANDU applications

    International Nuclear Information System (INIS)

    Hopwood, Jerry; Kuran, Sermet; Zhou, Xi; Ivanco, Michael; Rolfe, Brian; Mancuso, Connie; Duffey, Romney

    2005-01-01

    AECL has performed studies to utilize CANDU nuclear energy in areas other than electrical generation. The studies presented in this paper include using CANDU for applications in non-traditional areas which expand the use of zero-greenhouse gas energy source. The Oil sands industry demands significant energy input and the majority of the energy required for bitumen extraction is steam and hot water. As the primary production of a CANDU plant is steam, it can satisfy the steam and hot water requirement without a major modification to the Nuclear Steam Plant (NSP). Reverse Osmosis (RO) has been identified by the IAEA as the most promising method for nuclear desalination. Since the RO desalination efficiency increases as its feedwater temperature rises, using condenser cooling water from a CANDU plant as the feedwater for a RO plant and sharing other facilities between these two plants results in significant benefits in capital and operating costs of a desalination plant. Electrolysis powered by nuclear-generated electricity is the technology currently available to produce hydrogen without greenhouse gas emissions. By using the cheaper electricity available at off-peak periods in an open electricity market, this technology could be economically competitive, improve overall energy system efficiency and reduce overall energy system carbon intensity. The paper summarizes the background, technical approaches, feasibility considerations, along with economic comparisons between CANDU nuclear energy and the traditional energy sources for each study. The results show that the CANDU technology is a promising energy source for various industries. (author)

  12. The next generation of CANDU technologies: profiling the potential for hydrogen fuel

    International Nuclear Information System (INIS)

    Hopwood, J.M.

    2001-01-01

    This report discusses the Next-generation CANDU Power Reactor technologies currently under development at AECL. The innovations introduced into proven CANDU technologies include a compact reactor core design, which reduces the size by a factor of one third for the same power output; improved thermal efficiency through higher-pressure steam turbines; reduced use of heavy water (one quarter of the heavy water required for existing plants), thus reducing the cost and eliminating many material handling concerns; use of slightly enriched uranium to extend fuel life to three times that of existing natural uranium fuel and additions to CANDU's inherent passive safety. With these advanced features, the capital cost of constructing the plant can be reduced by up to 40 per cent compared to existing designs. The clean, affordable CANDU-generated electricity can be used to produce hydrogen for fuel cells for the transportation sector, thereby reducing emissions from the transportation sector

  13. Minimize corrosion degradation of steam generator tube materials

    International Nuclear Information System (INIS)

    Lu, Y.

    2006-01-01

    As part of a coordinated program, AECL is developing a set of tools to aid with the prediction and management of steam generator performance. Although stress corrosion cracking (of Alloy 800) has not been detected in any operating steam generator, for life management it is necessary to develop mechanistic models to predict the conditions under which stress corrosion cracking is plausible. Experimental data suggest that all steam generator tube materials are susceptible to corrosion degradation under some specific off-specification conditions. The tolerance to the chemistry upset for each steam generator tube alloy is different. Electrochemical corrosion behaviors of major steam generator tube alloys were studied under the plausible aggressive crevice chemistry conditions. The potential hazardous conditions leading to steam generator tube degradation and the conditions, which can minimize steam generator tube degradation have been determined. Recommended electrochemical corrosion potential/pH zones were defined for all major steam generator tube materials, including Alloys 600, 800, 690 and 400, under CANDU steam generator operating and startup conditions. Stress corrosion cracking tests and accelerated corrosion tests were carried out to verify and revise the recommended electrochemical corrosion potential/pH zones. Based on this information, utilities can prevent steam generator material degradation surprises by appropriate steam generator water chemistry management and increase the reliability of nuclear power generating stations. (author)

  14. Steam generator life-management, reliability, maintenance and refurbishment

    International Nuclear Information System (INIS)

    Spekkens, P.

    2012-01-01

    SGC 2012 is a different kind of a conference - it has its own focus, initiatives and objectives and differs from its predecessors. It originated as the Steam Generator and Heat Exchanger Conference in 1990 - a time when premature degradation of steam generators with Alloy 600 tubes was rampant world-wide, and some CANDU steam generators had started to experience significant fouling and corrosion issues. The six previous steam generator conferences were held on a regular cycle, in a very similar format and with a similar theme. We are now in a different era in steam generators. The Alloy 600 tubing has been largely replaced by more robust materials, and the CANDU steam generators have been brought under much more intense and effective life cycle management. Performance of steam generators has improved greatly, and they are no longer considered at risk of limiting the life of the units. Indeed, most Incoloy 800 steam generators in CANDU units are considered to be capable of operating reliably through the 'second life' of the units and are not being replaced during refurbishments. Given this changing environment, the scope of this conference has been expanded from one to three areas: steam generators and heat exchangers as before, but also; controls, valves and pumps, and; reactor components and systems, Programs A, B and C, respectively. The conference is targeting to address the needs and interests of the operating utilities, and to 'focus on what needs attention'. As a means of 'focusing on what needs attention' an 'Issue-Identification and Definition' program was initiated last winter. The Issue-Identification Team operating with COG President Bob Morrison as its Executive Lead, worked to identify issues requiring attention in the three areas of interest. Of the many issues identified by the Team and elaborated on by the Program Developers of this conference, four were recommended for special attention: A. 'Operate Clean - Build Clean - Plant Wide': Despite their

  15. Next generation CANDU plants

    International Nuclear Information System (INIS)

    Hedges, K.R.; Yu, S.K.W.

    1998-01-01

    Future CANDU designs will continue to meet the emerging design and performance requirements expected by the operating utilities. The next generation CANDU products will integrate new technologies into both the product features as well as into the engineering and construction work processes associated with delivering the products. The timely incorporation of advanced design features is the approach adopted for the development of the next generation of CANDU. AECL's current products consist of 700MW Class CANDU 6 and 900 MW Class CANDU 9. Evolutionary improvements are continuing with our CANDU products to enhance their adaptability to meet customers ever increasing need for higher output. Our key product drivers are for improved safety, environmental protection and improved cost effectiveness. Towards these goals we have made excellent progress in Research and Development and our investments are continuing in areas such as fuel channels and passive safety. Our long term focus is utilizing the fuel cycle flexibility of CANDU reactors as part of the long term energy mix

  16. Advancing the CANDU reactor: From generation to generation

    International Nuclear Information System (INIS)

    Hopwood, Jerry; Duffey, Romney B.; Yu, Steven; Torgerson, Dave F.

    2006-01-01

    Emphasizing safety, reliability and economics, the CANDU reactor development strategy is one of continuous improvement, offering value and assured support to customers worldwide. The Advanced CANDU Reactor (ACR-1000) generation, designed by Atomic Energy of Canada Limited (AECL), meets the new economic expectation for low-cost power generation with high capacity factors. The ACR is designed to meet customer needs for reduced capital cost, shorter construction schedule, high plant capacity factor, low operating cost, increased operating life, simple component replacement, enhanced safety features, and low environmental impact. The ACR-1000 design evolved from the internationally successful medium-sized pressure tube reactor (PTR) CANDU 6 and incorporates operational feedback from eight utilities that operate 31 CANDU units. This technical paper provides a brief description of the main features of the ACR-1000, and its major role in the development path of the generations of the pressure tube reactor concept. The motivation, philosophy and design approach being taken for future generation of CANDU pressure tube reactors are described

  17. Steam generator replacement at Bruce A: approach, results, and lessons learned

    International Nuclear Information System (INIS)

    Tomkiewicz, W.; Savage, B.; Smith, J.

    2008-01-01

    Steam Generator Replacement is now complete in Bruce A Units 1 and 2. In each reactor, eight steam generators were replaced; these were the first CANDU steam generator replacements performed anywhere in the world. The plans for replacement were developed in 2004 and 2005, and were summarized in an earlier paper for the CNS Conference held in November, 2006. The present paper briefly summarizes the methodologies and special processes used such as metrology, cutting and welding and heavy lifting. The paper provides an update since the earlier report and focuses on the project achievements to date, such as: - A combination of engineered methodology, laser metrology and precise remote machining led to accurate first time fit-ups of each new replacement steam generator and steam drums - Lessons learned in the first unit led to schedule improvements in the second unit - Dose received was lowest recorded for any steam generator replacement project. The experience gained and lessons learned from Units 1 and 2 will be valuable in planning and executing future replacement steam generator projects. A video was presented

  18. Raman spectroscopy for in-situ characterisation of steam generator deposits

    International Nuclear Information System (INIS)

    Rochefort, P.A.; Guzonas, D.A.; Turner, C.W.

    1997-12-01

    This report describes the effort to develop in-situ characterisation of steam generator deposits using remote raman spectroscopy to determine the chemical composition and semi-quantitative measurement of their concentrations. Information on the composition of the deposits is necessary in order to establish the optimal cleaning conditions and procedures. Furthermore, the composition of the deposits also provides information on the conditions that exist within the steam generator and the feedtrain. The raman spectra of the three most common iron oxide phases found in the CANDU deposits (hematite, magnetite and nickel ferrite) are shown

  19. Severe accident analysis of a steam generator tube rupture accident using MAAP-CANDU to support level 2 PSA for the Point Lepreau Generating Station Refurbishment Project

    Energy Technology Data Exchange (ETDEWEB)

    Petoukhov, S.M.; Brown, M.J. [Canadian Nuclear Laboratories, Chalk River, ON (Canada)

    2015-07-01

    A Level 2 Probabilistic Safety Assessment was performed for the Point Lepreau Generating Station. The MAAP-CANDU code was used to simulate the progression of postulated severe core damage accidents and fission product releases. This paper discusses the results for the reference case of the Steam Generator Tube Rupture initiating event. The reference case, dictated by the Level 2 Probabilistic Safety Assessment, was extreme and assumed most safety-related plant systems were not available: all steam generator feedwater; the emergency water supply; the moderator, shield and shutdown cooling systems; and all stages of emergency core cooling. The reference case also did not credit any post Fukushima lessons or any emergency mitigating equipment. The reference simulation predicted severe core damage beginning at 3.7 h, containment failure at 6.4 h, moderator boil off by 8.2 h, and calandria vessel failure at 42 h. A total release of 5.3% of the initial inventory of radioactive isotopes of Cs, Rb and I was predicted by the end of the simulation (139 h). Almost all noble gas fission products were released to the environment, primarily after the containment failure. No hydrogen/carbon monoxide burning was predicted. (author)

  20. Steam generator tube fitness-for-service guidelines

    International Nuclear Information System (INIS)

    Gorman, J.A.; Harris, J.E.; Lowenstein, D.B.

    1995-07-01

    The objectives of this project were to characterize defect mechanisms which could affect the integrity of steam generator tubes, to review and critique state-of-the-art Canadian and international steam generator tube fitness-for-service criteria and guidelines, and to obtain recommendations for criteria that could be used to assess fitness-for service guidelines for steam generator tubes containing defects in Canadian power plant service. Degradation mechanisms, that could affect CANDU steam generator tubes in Canada, have been characterized. The design standards and safety criteria that apply to steam generator tubing in nuclear power plant service in Canada and in Belgium, France, Japan, Spain, Sweden, and the USA have been reviewed and described. The fitness-for-service guidelines used for a variety of specific defect types in Canada and internationally have been evaluated and described in detail in order to highlight the considerations involved in developing such defect specific guidelines. Existing procedures for defect assessment and disposition have been identified, including inspection and examination practices. The approaches used in Canada and in Belgium, France, Japan, Spain, Sweden, and the USA for fitness-for-service guidelines were compared and contrasted for a variety of defect mechanisms. The strengths and weaknesses of the various approaches have been assessed. The report presents recommendations on approaches that may be adopted in the development of fitness-for-service guidelines for use in the dispositioning of steam generator tubing defects in Canada. (author). 175 refs., 2 tabs., 28 figs

  1. The next generation CANDU 6

    International Nuclear Information System (INIS)

    Hopwood, J.M.

    1999-01-01

    AECL's product line of CANDU 6 and CANDU 9 nuclear power plants are adapted to respond to changing market conditions, experience feedback and technological development by a continuous improvement process of design evolution. The CANDU 6 Nuclear Power Plant design is a successful family of nuclear units, with the first four units entering service in 1983, and the most recent entering service this year. A further four CANDU 6 units are under construction. Starting in 1996, a focused forward-looking development program is under way at AECL to incorporate a series of individual improvements and integrate them into the CANDU 6, leading to the evolutionary development of the next-generation enhanced CANDU 6. The CANDU 6 improvements program includes all aspects of an NPP project, including engineering tools improvements, design for improved constructability, scheduling for faster, more streamlined commissioning, and improved operating performance. This enhanced CANDU 6 product will combine the benefits of design provenness (drawing on the more than 70 reactor-years experience of the seven operating CANDU 6 units), with the advantages of an evolutionary next-generation design. Features of the enhanced CANDU 6 design include: Advanced Human Machine Interface - built around the Advanced CANDU Control Centre; Advanced fuel design - using the newly demonstrated CANFLEX fuel bundle; Improved Efficiency based on improved utilization of waste heat; Streamlined System Design - including simplifications to improve performance and safety system reliability; Advanced Engineering Tools, -- featuring linked electronic databases from 3D CADDS, equipment specification and material management; Advanced Construction Techniques - based on open top equipment installation and the use of small skid mounted modules; Options defined for Passive Heat Sink capability and low-enrichment core optimization. (author)

  2. Steam generator life cycle management - B and W perspective

    International Nuclear Information System (INIS)

    Dhar, D.; Fluit, S.; Millman, J.

    2006-01-01

    This paper is an effort towards the B and W perspective about the effective life cycle management (LCM) of the CANDU Steam Generators (SGs) based on the identification of active and plausible degradation mechanisms for various SG components and the need to achieve a safe and economic operating interval for the station. The objective of this paper is to provide the long-term effective strategy for inspections, maintenance and design modifications as necessary for the safe and reliable operation of the SGs during the plant design life. The derived activities of this strategy need to be integrated with the station outage specific work scope plan for an effective life cycle management. The technical basis for these activities is based on the review of previous field inspection records, maintenance work and modifications at the station and operational experience (OPEX) from other CANDU steam generators with similar design. These activities need to be performed in order to ensure that the SGs perform within an acceptable level of safety and reliability as per the licensing bases, while optimizing station production and cost effectiveness. (author)

  3. Steam generator replacement in Bruce A Unit 1 and Unit 2

    International Nuclear Information System (INIS)

    Hart, R.S.

    2006-01-01

    The Bruce A Generating Station consists of four 900 MW class CANDU units. The reactor and Primary Heat Transport System for each Unit are housed within a reinforced concrete reactor vault. A large duct running below the reactor vaults accommodates the shared fuel handling system, and connects the four reactor vaults to the vacuum building. The reactor vaults, fuelling system duct and the vacuum building constitute the station vacuum containment system. Bruce A Unit 2 was shut down in 1995 and Bruce A Units 1, 3 and 4 were shutdown in 1997. Bruce A Units 3 and 4 were returned to service in late 2003 and are currently operating. Units 1 and 2 remain out of service. Bruce Power is currently undertaking a major rehabilitation of Bruce A Unit 1 and Units 2 that will extend the in-service life of these units by at least 25 years. Replacement of the Steam Generators (eight in each unit) is required; this work was awarded to SNC-Lavalin Nuclear (SLN). The existing steam drums (which house the steam separation and drying equipment) will be retained. Unit 2 is scheduled to be synchronized with the grid in 2009, followed by Unit 1 in 2009. Each Bruce A unit has two steam generating assemblies, one located above and to each end of the reactor. Each steam generating assembly consists of a horizontal cylindrical steam drum and four vertical Steam Generators. The vertical Steam Generators connect to individual nozzles that are located on the underside of the Steam Drum (SD). The steam drums are located in concrete shielding structures (steam drum enclosures). The lower sections of the Steam Generators penetrate the top of the reactor vaults: the containment pressure boundary is established by bellows assemblies that connect between the reactor vault roof slab and the Steam Generators. Each Steam Generators is supported from the bottom by a trapeze that is suspended from the reactor vault top structure. The Steam Generator Replacement (SGR) methodology developed by SLN for Unit 1

  4. Explaining the absence of Co-58 radiation fields around CANDU reactor primary circuit

    International Nuclear Information System (INIS)

    Burrill, K.A.; Guzonas, D.A.

    2002-01-01

    Radiation fields from Co-58 are rarely detected in CANDU plants. For example, Ge(Li) surveys of the Inconel 600 steam generators at some CANDU plants may show radiation attributed to Co-58 only early in plant life, and most artefacts removed from the primary circuit later in plant operation show no Co-58 present. However, Pressurized Water Reactor plants experience relatively large fields from Co-58 on their isothermal piping, e.g., steam generator channel head, and steam generators tube sampling programs do show deposits in the tubes with significant Co-58 compared to other radionuclides such as Co-60. CANDU reactors have high concentrations of dissolved iron due to the extensive use of carbon steel for the isothermal piping, e.g., feeders, headers, and steam generator channel heads. A dissolved iron transport diagram that was proposed recently for the primary circuit of CANDU plants has been validated by comparison of predicted deposit weights with plant deposit data from various components. One feature of the diagram is dissolved iron precipitation inside the steam generators tubes. An hypothesis is advanced here in which precipitating dissolved iron is proposed to occlude dissolved nickel. This removal mechanism may prevent the solubility of dissolved nickel from being exceeded anywhere around the primary circuit. In particular, this mechanism could avoid NiO precipitation in the core and the generation of large quantities of Co-58. Using this mechanism along with the known solubility behaviour of NiO with temperature, a dissolved nickel transport diagram has been proposed for CANDU plants. (authors)

  5. The CANDU 9

    International Nuclear Information System (INIS)

    Hart, R.S.

    1994-01-01

    The CANDU 9 plants are single unit versions of the Bruce B design, incorporating relevant technical advances made in CANDU 6, and the newer Darlington and CANDU 3 designs. This paper describes the CANDU 9 480/SEU, with an electrical output of about 1050 MW. In this designation, 480 refers to the number of fuel channels, and SEU to slightly enriched uranium. Emphasis is placed on evolutionary design, and the use of well proven design features, to ensure regulatory licensability and reliable operation. Safety is enhanced through simplification and improvement of key systems and components. Relatively low energy costs result from reduced specific capital cost, reduced operating and maintenance cost, and reduced radiation exposure to personnel. Standardization is emphasized inasmuch as all key components (steam generators, heat transport pumps, pressure tubes fuelling machines etc.) ar of the same design as those in operating CANDU stations. Advanced CANDU fuel cycles are readily accommodated. 1 ref., 1 tab., 11 figs

  6. Mathematical modeling of CANDU-PHWR

    Energy Technology Data Exchange (ETDEWEB)

    Gaber, F.A.; Aly, R.A.; El-Shal, A.O. [Atomic Energy Authority, Cairo (Egypt)

    2001-07-01

    The paper deals with the transient studies of CANDU 600 pressurized Heavy Water Reactor (PHWR) system. This study involved mathematical modeling of CANDU PHWR major system components and the developments of software to study the thermodynamic performances. Modeling of CANDU-PHWR was based on lumped parameter technique.The integrated CANDU-PHWR model includes the neutronic, reactivity, fuel channel heat transfer, piping and the preheater type U-tube steam generator (PUTSG). The nuclear reactor power was modelled using the point kinetics equations with six groups of delayed neutrons and reactivity feed back due to the changes in fuel temperature and coolant temperature. The complex operation of the preheater type U-tube steam generator (PUTSG) is represented by a non-linear dynamic model using a state variable, moving boundary and lumped parameter techniques. The secondary side of the PUTSG model has six separate lumps including a preheater region, a lower boiling section, a mixing region, a riser, a chimmeny section, and a down-corner. The tube side of PUTSG has three main thermal zones. The PUTSG model is based on conservation of mass, energy and momentum relation-ships. The CANDU-PHWR integrated model are coded in FORTRAN language and solved by using a standard numerical technique. The adequacy of the model was tested by assessing the physical plausibility of the obtained results. (author)

  7. CANDU technology for generation III + AND IV reactors

    International Nuclear Information System (INIS)

    Torgerson, D.F.

    2005-01-01

    Atomic Energy of Canada Limited (AECL) is the original developer of the CANDU?reactor, one of the three major commercial power reactor designs now used throughout the world. For over 60 years, AECL has continued to evolve the CANDU design from the CANDU prototypes in the 1950s and 1960s through to the second generation reactors now in operation, including the Generation II+ CANDU 6. The next phase of this evolution, the Generation III+ Advanced CANDU ReactorTM (ACRTM), continues the strategy of basing next generation technology on existing CANDU reactors. Beyond the ACR, AECL is developing the Generation IV CANDU Super Critical Water Reactor. Owing to the evolutionary nature of these advanced reactors, advanced technology from the development programs is also being applied to operating CANDU plants, for both refurbishments and upgrading of existing systems and components. In addition, AECL is developing advanced technology that covers the entire life cycle of the CANDU plant, including waste management and decommissioning. Thus, AECL maintains state-of-the-art expertise and technology to support both operating and future CANDU plants. This paper outlines the scale of the current core knowledge base that is the foundation for advancement and support of CANDU technology. The knowledge base includes advancements in materials, fuel, safety, plant operations, components and systems, environmental technology, waste management, and construction. Our approach in each of these areas is to develop the underlying science, carry out integrated engineering scale tests, and perform large-scale demonstration testing. AECL has comprehensive R and D and engineering development programs to cover all of these elements. The paper will show how the ongoing expansion of the CANDU knowledge base has led to the development of the Advanced CANDU Reactor. The ACR is a Generation III+ reactor with substantially reduced costs, faster construction, and enhanced passive safety and operating

  8. Two-phase flow induced vibrations in CANDU steam generators

    International Nuclear Information System (INIS)

    Gidi, A.

    2009-01-01

    The U-Bend region of nuclear steam generators tube bundles have suffered from two-phase cross flow induced vibrations. Tubes in this region have experienced high amplitude vibrations leading to catastrophic failures. Turbulent buffeting and fluid-elastic instability has been identified as the main causes. Previous investigations have focused on flow regime and two-phase flow damping ratio. However, tube bundles in steam generators have vapour generated on the surface of the tubes, which might affect the flow regime, void fraction distribution, turbulent intensity levels and tube-flow interaction, all of which have the potential to change the tube vibration response. A cantilevered tube bundle made of electric cartridges heaters was built and tested in a Freon-11 flow loop at McMaster University. Tubes were arranged in a parallel triangular configuration. The bundle was exposed to two-phase cross flows consisting of different combinations of void from two sources, void generated upstream of the bundle and void generated at the surface of the tubes. Tube tip vibration response was measured optically and void fraction was measured by gamma densitometry technique. It was found that tube vibration amplitude in the transverse direction was reduced by a factor of eight for void fraction generated at the tube surfaces only, when compared to the upstream only void generation case. The main explanation for this effect is a reduction in the correlation length of the turbulent buffeting forcing function. Theoretical calculations of the tube vibration response due to turbulent buffeting under the same experimental conditions predicted a similar reduction in tube amplitude. The void fraction for the fluid-elastic instability threshold in the presence of tube bundle void fraction generation was higher than that for the upstream void fraction generation case. The first explanation of this difference is the level of turbulent buffeting forces the tube bundle was exposed to

  9. Proceedings of the third international conference on CANDU maintenance

    International Nuclear Information System (INIS)

    1995-01-01

    The third international conference on Candu maintenance included sessions on the following topics: predictive maintenance, reliability improvements, steam generator monitoring, tools and instrumentation, valve performance, fuel channel inspection and maintenance, steam generator maintenance, environmental qualification, predictive maintenance, instrumentation and control, steam generator cleaning, decontamination and radiation protection, inspection techniques, maintenance program strategies and valve packing experience, remote tooling/ robotics and fuel handling. The individual papers have been abstracted separately

  10. Proceedings of the third international conference on CANDU maintenance

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-31

    The third international conference on Candu maintenance included sessions on the following topics: predictive maintenance, reliability improvements, steam generator monitoring, tools and instrumentation, valve performance, fuel channel inspection and maintenance, steam generator maintenance, environmental qualification, predictive maintenance, instrumentation and control, steam generator cleaning, decontamination and radiation protection, inspection techniques, maintenance program strategies and valve packing experience, remote tooling/ robotics and fuel handling. The individual papers have been abstracted separately.

  11. Corrosion Processes of the CANDU Steam Generator Materials in the Presence of Silicon Compounds

    International Nuclear Information System (INIS)

    Lucan, Dumitra; Fulger, Manuela; Velciu, Lucian; Lucan, Georgiana; Jinescu, Gheorghita

    2006-01-01

    The feedwater that enters the steam generators (SG) under normal operating conditions is extremely pure but, however, it contains low levels (generally in the μg/l concentration range) of impurities such as iron, chloride, sulphate, silicate, etc. When water is converted into steam and exits the steam generator, the non-volatile impurities are left behind. As a result of their concentration, the bulk steam generator water is considerably higher than the one in the feedwater. Nevertheless, the concentrations of corrosive impurities are in general sufficiently low so that the bulk water is not significantly aggressive towards steam generator materials. The impurities and corrosion products existing in the steam generator concentrate in the porous deposits on the steam generator tubesheet. The chemical reactions that take place between the components of concentrated solutions generate an aggressive environment. The presence of this environment and of the tubesheet crevices lead to localized corrosion and thus the same tubes cannot ensure the heat transfer between the fluids of the primary and secondary circuits. Thus, it becomes necessary the understanding of the corrosion process that develops into SG secondary side. The purpose of this paper is the assessment of corrosion behavior of the tubes materials (Incoloy-800) at the normal secondary circuit parameters (temperature = 2600 deg C, pressure = 5.1 MPa). The testing environment was demineralized water containing silicon compounds, at a pH=9.5 regulated with morpholine and cyclohexyl-amine (all volatile treatment - AVT). The paper presents the results of metallographic examinations as well as the results of electrochemical measurements. (authors)

  12. Experimental fretting-wear studies of steam generator materials

    International Nuclear Information System (INIS)

    Fisher, N.J.; Chow, A.B.; Weckwerth, M.K.

    1994-01-01

    Flow-induced vibration of steam generator tubes results in fretting-wear damage due to impacting and rubbing of the tubes against their supports. This damage can be predicted by computing tube response to flow-induced excitation forces using analytical techniques, and then relating this response to resultant wear damage using experimentally-derived wear coefficients. Fretting-wear of steam generator materials has been studied experimentally at Chalk River Laboratories for two decades. Tests are conducted in machines that simulate steam generator environmental conditions and tube-to-support dynamic interactions. Different tube and support materials, tube-to-support clearances and tube support geometries have been studied. As well, the effect of environmental conditions, such as temperature, oxygen content, pH and chemistry control additive, have been investigated. Early studies showed that damage was related to contact force as long as other parameters, such as geometry and motion were held constant. Later studies have shown that damage is related to a parameter called work-rate, which combines both contact force and sliding distance. Results of short- and long-term fretting-wear tests for CANDU steam generator materials at realistic environmental conditions are presented. These results demonstrate that work-rate is appropriate correlating parameter for impact-sliding interaction

  13. ANL/CANTIA code for steam generator tube integrity assessment

    International Nuclear Information System (INIS)

    Revankar, S.T.; Wolf, B.; Majumdar, S.; Riznic, J.R.

    2009-01-01

    Steam generator (SG) tubes have an important safety role in CANDU type reactors and Pressurized Water Reactors (PWR) because they constitute one of the primary barriers between the radioactive and non-radioactive sides of the nuclear plant. The SG tubes are susceptible to corrosion and damage. A failure of a single steam generator tube, or even a few tubes, would not be a serious safety-related event in a CANDU reactor. The leakage from a ruptured tube is within makeup capacity of the primary heat transport system, so that as long as the operator takes the correct actions, the off-site consequences will be negligible. A sufficient safety margin against tube rupture used to be the basis for a variety of maintenance strategies developed to maintain a suitable level of plant safety and reliability. Several through-wall flaws may remain in operation and potentially contribute to the total primary-to-secondary leak rate. Assessment of the conditional probabilities of tube failures, leak rates, and ultimately risk of exceeding licensing dose limits has been used for steam generator tube fitness-for-service assessment. The advantage of this type of analysis is that it avoids the excessive conservatism typically present in deterministic methodologies. However, it requires considerable effort and expense to develop all of the failure, leakage, probability of detection, and flaw growth distributions and models necessary to obtain meaningful results from a probabilistic model. The Canadian Nuclear Safety Commission (CNSC) recently developed the CANTIA methodology for probabilistic assessment of inspection strategies for steam generator tubes as a direct effect on the probability of tube failure and primary-to-secondary leak rate Recently Argonne National Laboratory has developed tube integrity and leak rate models under Integrated Steam Generator Tube Integrity Program (ISGTIP-2). These models have been incorporated in the ANL/CANTIA code. This paper presents the ANL

  14. Primary separator replacement for Bruce Unit 8 steam generators

    International Nuclear Information System (INIS)

    Roy, S.B.; Mewdell, C.G.; Schneider, W.G.

    2000-01-01

    During a scheduled maintenance outage of Bruce Unit 8 in 1998, it was discovered that the majority of the original primary steam separators were damaged in two steam generators. The Bruce B steam generators are equipped with GXP type primary cyclone separators of B and W supply. There were localized perforations in the upper part of the separators and large areas of generalized wall thinning. The degradation was indicative of a flow related erosion corrosion mechanism. Although the unit- restart was justified, it was obvious that corrective actions would be necessary because of the number of separators affected and the extent of the degradation. Repair was not considered to be a practical option and it was decided to replace the separators, as required, in Unit 8 steam generators during an advanced scheduled outage. GXP separators were selected for replacement to minimize the impact on steam generator operating characteristics and analysis. The material of construction was upgraded from the original carbon steel to stainless steel to maximize the assurance of full life. The replacement of the separators was a first of a kind operation not only for Ontario Power Generation and B and W but also for all CANDU plants. The paper describes the degradations observed and the assessments, the operating experience, manufacture and installation of the replacement separators. During routine inspection in 1998, many of the primary steam separators in two of steam generators at Bruce Nuclear Division B Unit 8 were observed to have through wall perforations. This paper describes assessment of this condition. It also discusses the manufacture and testing of replacement primary steam separators and the development and execution of the replacement separator installation program. (author)

  15. Steam generator design requirements for ACR-1000

    International Nuclear Information System (INIS)

    Subash, S.; Hau, K.

    2006-01-01

    Atomic Energy of Canada Limited (AECL) has developed the ACR-1000 (Advanced CANDU Reactor-1000 ) to meet market expectations for enhanced safety of plant operation, high capacity factor, low operating cost, increased operating life, simple component replacement, reduced capital cost, and shorter construction schedule. The ACR-1000 design is based on the use of horizontal fuel channels surrounded by a heavy water moderator, the same feature as in all CANDU reactors. The major innovation in the ACR-1000 is the use of low enriched uranium fuel, and light water as the coolant, which circulates in the fuel channels. This results in a compact reactor core design and a reduction of heavy water inventory, both contributing to a significant decrease in capital cost per MWe produced. The ACR-1000 plant is a two-unit, integrated plant with each unit having a nominal gross output of about 1165 MWe with a net output of approximately 1085 MWe. The plant design is adaptable to a single unit configuration, if required. This paper focuses on the technical considerations that went into developing some of the important design requirements for the steam generators for the ACR-1000 plant and how these requirements are specified in the Technical Specification, which is the governing document for the steam generator (SG) detail design. Layout of these SGs in the plant is briefly described and their impacts on the SG design. (author)

  16. Steps to Advanced CANDU 600

    International Nuclear Information System (INIS)

    Oh, Yongshick; Brooks, G. L.

    1988-01-01

    The CANDU nuclear power system was developed from merging of AECL heavy water reactor technology with Ontario Hydro electrical power station expertise. The original four units of Ontario Hydro's Pickering Generating Station are the first full-scale commercial application of the CANDU system. AECL and Ontario Hydro then moved to the next evolutionary step, a more advanced larger scale design for four units at the Bruce Generating Station. CANDU 600 followed as a single unit nuclear electric power station design derived from an amalgam of features of the multiple unit Pickering and Bruce designs. The design of the CANDU 600 nuclear steam supply system is based on the Pickering design with improvements derived from the Bruce design. For example, most CANDU 600 auxiliary systems are based on Bruce systems, whereas the fuel handling system is based on the Pickering system. Four CANDU 600 units are in operation, and five are under construction in Romania. For the additional four units at Pickering Generating Station 'B', Ontario Hydro selected a replica of the Pickering 'A' design with limited design changes to maintain a high level of standardization across all eight units. Ontario Hydro applied a similar policy for the additional four units at Bruce Generating Station 'B'. For the four unit Darlington station, Ontario Hydro selected a design based on Bruce with improvements derived from operating experience, the CANDU 600 design and development programs

  17. Key thrusts in next generation CANDU. Annex 10

    International Nuclear Information System (INIS)

    Shalaby, B.A.; Torgerson, D.F.; Duffey, R.B.

    2002-01-01

    Current electricity markets and the competitiveness of other generation options such as CCGT have influenced the directions of future nuclear generation. The next generation CANDU has used its key characteristics as the basis to leap frog into a new design featuring improved economics, enhanced passive safety, enhanced operability and demonstrated fuel cycle flexibility. Many enabling technologies spinning of current CANDU design features are used in the next generation design. Some of these technologies have been developed in support of existing plants and near term designs while others will need to be developed and tested. This paper will discuss the key principles driving the next generation CANDU design and the fuel cycle flexibility of the CANDU system which provide synergism with the PWR fuel cycle. (author)

  18. The THIRST chemistry module as a tool to determine optimal steam generator corrosion control strategies

    International Nuclear Information System (INIS)

    Heppner, K.; Laroche, S.; Pietralik, J.

    2006-01-01

    As part of a coordinated program, AECL is developing a set of tools to aid with the prediction and management of steam generator performance. Although stress corrosion cracking (of Alloy 800) has not been detected in any operating steam generator, for life management it is necessary to develop mechanistic models to predict the conditions under which stress corrosion cracking is plausible. Therefore, constant extension rate tests were carried out for Alloy 800 under various steam generator crevice chemistry conditions at applied potentials. These tests were designed to evaluate the stress corrosion cracking susceptibility of Alloy 800 under CANDU( steam generator operating conditions. Based on the experimental results, the recommended electrochemical corrosion potential/pH zone for Alloy 800 determined by electrochemical polarization measurements was verified with the respect of stress corrosion cracking susceptibility. The effects of lead contamination on the stress corrosion cracking susceptibility of Alloy 800 tubing were also evaluated. The experimental results from constant extension rate tests obtained under applied potentials suggest that Alloy 800 has good performance inside much of a previously recommended electrochemical corrosion potential/pH zone determined by electrochemical analysis. Alloy 800 is not susceptible to stress corrosion cracking under normal CANDU steam generator operating conditions. However, Alloy 800 may be susceptible to stress corrosion cracking under near-neutral crevice chemistry conditions in the presence of oxidants. In addition, stress corrosion cracking susceptibility is increased by lead contamination. This observation suggests that the previously defined electrochemical corrosion potential limit under near-neutral crevice conditions could be modified to minimize stress corrosion cracking of Alloy 800. The test results from this work also suggest that the pH dependency of the stress corrosion cracking susceptibility of Alloy 800

  19. Susceptibility of CANDU steam generator preheater to cavitation erosion

    International Nuclear Information System (INIS)

    Laroche, S.L.; Sun, L.; Pietralik, J.M.

    2012-01-01

    In 2009, Darlington Steam Generator (SG) tube inspections revealed some tubes had degraded in the preheater. The tube degradation occurred at the clearance gap between the tube and the preheater baffle and reached up to 50% through-wall depth at the baffles in the middle portion of the preheater. The general pattern of the damage and the elemental composition analysis suggested that the degradation was the result of a hydrodynamic process, such as cavitation erosion. Cavitation erosion occurs when vapour bubbles exist or form in the flowing liquid and then these bubbles collapse violently in the vicinity of the wall. These bubbles collapse when steam bubbles contact water that is sufficiently subcooled, below the saturation temperature. In the gap between the tube and the preheater baffle, low flow will exist due to the pressure difference across the baffle plate. In addition, heat transfer occurs from the primary-side fluid to the secondary-side fluid within this clearance gap that is driven by the primary-to-secondary temperature difference. Factors, such as the tube position in the baffle hole and fouling, influence the local conditions and can cause subcooled boiling that result in cavitation. This paper presents a study of flow and heat transfer phenomena to determine the factors contributing to cavitation erosion in SG preheaters. The analysis used the THIRST1 code for a 3-dimensional thermalhydraulic simulation of the steam generators and the ANSYS FLUENT®2 code for detailed calculations of flow and heat transfer in the clearance gaps. This study identifies that tubes in the preheater region are susceptible to cavitation erosion and indicates that this area should be part of the station inspection program because, regardless of preheater design, some tubes may experience the thermalhydraulic conditions and undergo degradations similar to those observed for the tubes in Darlington SGs. (author)

  20. Trends in the capital costs of CANDU generating stations

    International Nuclear Information System (INIS)

    Yu, A.M.

    1982-09-01

    This paper consolidates the actual cost experience gained by Atomic Energy of Canada Limited, Ontario Hydro, and other Canadian electric utlities in the planning, design and construction of CANDU-PHWR (CANada Deuterium Uranium-Pressurized Heavy Water Reactor) generating stations over the past 30 years. For each of the major CANDU-PHWR generating stations in operation and under construction in Canada, an analysis is made to trace the evolution of the capital cost estimates. Major technical, economic and other parameters that affect the cost trends of CANDU-PHWR generating stations are identified and their impacts assessed. An analysis of the real cost of CANDU generating stations is made by eliminating interest during construction and escalation, and the effects of planned deferment of in-service dates. An historical trend in the increase in the real cost of CANDU power plants is established. Based on the cost experience gained in the design and construction of CANDU-PHWR units in Canada, as well as on the assessment of parameters that influence the costs of such projects, the future costs of CANDU-PHWRs are presented

  1. Technologies in support of CANDU development

    International Nuclear Information System (INIS)

    Turner, C.; Tapping, B.

    2005-01-01

    Atomic Energy of Canada, Ltd. (AECL) has significant research and development (R and D) programs designed to meet the needs of both existing CANDU reactors and new and evolving CANDU plant designs. These R and D programs cover a wide range of technology, from chemistry and materials support through to inspection and life management tools. Emphasis is placed on effective technology development programs for fuel channels, feeders and steam generators to ensure their operation through design life, and beyond. This paper specifically addresses how the R and D has been applied in the production of longer-lived pressure tubes for the most recent CANDU 6 reactors, and how this technology forms the basis for the pressure tubes of the Advanced CANDU Reactor (ACR). Similarly, AECL has developed solutions for other critical components such as calandria tubes, feeder pipe and steam generators. The paper also discusses how the R and D knowledge has been integrated into aging management databases and health monitoring tools. Since 1997, AECL has been working with CANDU utilities on comprehensive and integrated CANDU Plant Life Management (PLiM) programs for successful and reliable plant operation through design life and beyond. AECL has developed and implemented an advanced chemistry monitoring and diagnostic system, called ChemAND which allows on-line access by the operators to current and past chemistry conditions enabling appropriate responses and facilitating planning of shutdown maintenance actions. An equivalent tool for monitoring, trending and diagnosing thermal and mechanical data has also been developed; this tool is called ThermAND. AECL is developing the Maintenance Information, Monitoring, and Control (MIMC) system, which provide information to the user for condition-based decision-making in maintenance. To enable more effective inspections, surveillance and data collection, AECL has developed unique one-off tooling to carry out unanticipated inspection and repair

  2. Proceedings of the fourth international conference on CANDU maintenance

    International Nuclear Information System (INIS)

    1997-01-01

    These proceedings record the information presented at the 4th International Conference on CANDU Maintenance held November 16-18,1997 in Toronto, Canada. The papers for these proceedings were prepared on component maintenance, human performance, steam generator leak detection, fuel channel inspections, rotating equipment maintenance, surveillance programs, inspection techniques, valve maintenance, steam generator repairs and performance, reactor aging management and preventative maintenance

  3. Proceedings of the fourth international conference on CANDU maintenance

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-07-01

    These proceedings record the information presented at the 4th International Conference on CANDU Maintenance held November 16-18,1997 in Toronto, Canada. The papers for these proceedings were prepared on component maintenance, human performance, steam generator leak detection, fuel channel inspections, rotating equipment maintenance, surveillance programs, inspection techniques, valve maintenance, steam generator repairs and performance, reactor aging management and preventative maintenance.

  4. Environmental codes of practice for steam electric power generation

    International Nuclear Information System (INIS)

    1985-03-01

    The Design Phase Code is one of a series of documents being developed for the steam electric power generation industry. This industry includes fossil-fuelled stations (gas, oil and coal-fired boilers), and nuclear-powered stations (CANDU heavy water reactors). In this document, environmental concerns associated with water-related and solid waste activities of steam electric plants are discussed. Design recommendations are presented that will minimize the detrimental environmental effects of once-through cooling water systems, of wastewaters discharged to surface waters and groundwaters, and of solid waste disposal sites. Recommendations are also presented for the design of water-related monitoring systems and programs. Cost estimates associated with the implementation of these recommendations are included. These technical guides for new or modified steam electric stations are the result to consultation with a federal-provincial-industry task force

  5. Electrosleeve process for in-situ nuclear steam generator repair

    International Nuclear Information System (INIS)

    Renaud, E.; Brennenstuhl, A.M.; Stewart, D.R.; Gonzalez, F.

    2000-01-01

    Degradation of steam generator tubing by localized corrosion is a widespread problem in the nuclear industry that can lead to costly forced outages, unit derating, steam generator replacement or even the permanent shutdown of a reactor. In response to the onset of steam generator degradation at Ontario Power Generation's Pickering Nuclear Generating Station (PNGS) Unit 5, and the determined unsuitability of conventional repair methods (mechanically expanded or welded sleeves) for Alloy 400, an alternative repair technology was developed. Electrosleeve is a non-intrusive, low-temperature process that involves the electrodeposition of a nanocrystalline nickel microalloy forming a continuously bonded, structural layer over the internal diameter of the degraded region. This technology is designed to provide a long-term pressure boundary repair, fully restoring the structural integrity of the damaged region to its original state. This paper describes the Electrosleeve process for steam generator tubing repair and the unique properties of the advanced sleeve material. The successful installation of fourteen Electrosleeves that have been in service for more than six years in Alloy 400 tubing at the Pickering-S CANDU unit, and the more recent (Nov. 99) extension of the technology to Alloy 600 by the installation of 57 sleeves in a U.S. pressurized water reactor (PWR) at Callaway, is presented. The Electrosleeve process has been granted a conditional license by the U.S. Nuclear Regulatory Commission (NRC). In Canada, the process of licensing Electrosleeve with the CNSC / TSSA has begun. (author)

  6. CANDU combined cycles featuring gas-turbine engines

    International Nuclear Information System (INIS)

    Vecchiarelli, J.; Choy, E.; Peryoga, Y.; Aryono, N.A.

    1998-01-01

    In the present study, a power-plant analysis is conducted to evaluate the thermodynamic merit of various CANDU combined cycles in which continuously operating gas-turbine engines are employed as a source of class IV power restoration. It is proposed to utilize gas turbines in future CANDU power plants, for sites (such as Indonesia) where natural gas or other combustible fuels are abundant. The primary objective is to eliminate the standby diesel-generators (which serve as a backup supply of class III power) since they are nonproductive and expensive. In the proposed concept, the gas turbines would: (1) normally operate on a continuous basis and (2) serve as a reliable backup supply of class IV power (the Gentilly-2 nuclear power plant uses standby gas turbines for this purpose). The backup class IV power enables the plant to operate in poison-prevent mode until normal class IV power is restored. This feature is particularly beneficial to countries with relatively small and less stable grids. Thermodynamically, the advantage of the proposed concept is twofold. Firstly, the operation of the gas-turbine engines would directly increase the net (electrical) power output and the overall thermal efficiency of a CANDU power plant. Secondly, the hot exhaust gases from the gas turbines could be employed to heat water in the CANDU Balance Of Plant (BOP) and therefore improve the thermodynamic performance of the BOP. This may be accomplished via several different combined-cycle configurations, with no impact on the current CANDU Nuclear Steam Supply System (NSSS) full-power operating conditions when each gas turbine is at maximum power. For instance, the hot exhaust gases may be employed for feedwater preheating and steam reheating and/or superheating; heat exchange could be accomplished in a heat recovery steam generator, as in conventional gas-turbine combined-cycle plants. The commercially available GateCycle power plant analysis program was applied to conduct a

  7. 6. CNS international conference on CANDU maintenance. Proceedings

    International Nuclear Information System (INIS)

    2003-01-01

    The 6th CNS International Conference on CANDU Maintenance took place in Toronto, Ontario on November 16-18, 2003. The theme for the conference was 'Maintenance for Life'. About 270 delegates attended the conference held by the Canadian Nuclear Society. The conference consisted of four parallel sessions, a pattern that continued throughout the conference. Papers were grouped under the following headings: Fuel Channels and End Fittings - Assessments; Fuel Channels and End Fittings - Inspections; Fuel Channels and End Fittings - Maintenance; Fuel Channels and End Fittings - Universal Delivery Machine; Water Upgrading; Performance and Plant Life Improvement; Steam Generator Life Management; Steam Generator Modifications; Steam Generators - Inspections; Steam Generators - Assessments; Maintenance Programs; Feeder Inspections; Feeder Assessment and Mitigation; Valve Maintenance; Instrumentation and Control; Inspection Technology; and Fuel Handling

  8. Evaluation on operation of liquid relief valves for steam line break accidents by RELAP5/CANDU+ code

    International Nuclear Information System (INIS)

    Yang, C. Y.; Bang, Y. S.; Kim, H. J.

    2001-01-01

    A development of RELAP5/CANDU+ code for regulatory audits of accident analysis of CANDU nuclear power plants is on progress. This paper is undertaken in a procedure of a verification and validation for RELAP5/CANDU+ code by analyzing main steam line break accidents of WS 2/3/4. Following the ECC injection in sequence of the steam line breaks, the mismatch in heat transfer between the primary and the secondary systems makes pressure of the primary system instantly peaked to the open setpoint of liquid relief valves. The event sequence follows the result of WS 2/3/4 FSAR, but there is a difference in pressure transient after ECC injection. Sensitivity analysis for main factors dependent on the peak pressure such as control logics of liquid relief valves. ECC flow path and feedwater flow is performed. Because the pressure increase is continued for a long time and its peaking is high, open and close of the liquid relief valves are repeated several times, which is obviously different from those of WS 2/3/4 FSAR. As a result, it is evaluated that conservative modeling for the above variables is required in the analysis

  9. Embalse steam generators - status in 2009

    International Nuclear Information System (INIS)

    Luna, P.; Yetisir, M.; Roy, S.; MacEacheron, R.

    2009-01-01

    The Embalse Nuclear Generating Station (ENGS) is a CANDU 6, a pressurized heavy water plant, with a net capacity of 648 MW. The primary heat transport system at Embalse includes four Steam Generators (SGs) manufactured by Babcock and Wilcox Canada (B and W). These steam generators are vertical recirculating heat exchangers with Incoloy 800 inverted U-tubes and an integral preheater. Embalse SGs performed very well until the late 1990s, when an increase in tube fretting was noticed in the U-bend region. In-service inspection in 2002 and 2004 confirmed that the cause of the tube fretting was flow accelerated corrosion (FAC) damage of scallop bar supports in the U-bend region. The straight leg tube support plates (TSPs) have also been degrading. Degradation was worst at the top support plates, and it was in the form of material loss on the cold leg. The hot leg TSPs were heavily fouled with deposits and flow areas were blocked. Visual inspections and subsequent studies showed that the cause of the TSP degradation was also FAC. The Embalse SGs have carbon steel supports that make them susceptible to FAC. To mitigate the effects of degraded tube support structures, three additional sets of anti-vibration bars were installed in the U-bend regions of all four steam generators in 2004. In 2007, an improved secondary-side chemistry specification was implemented to reduce the FAC rate and the hot leg TSPs was waterlanced. A root cause analysis and condition assessment was performed for the tube supports in 2007. Fitness for Service (FFS) evaluation was completed using the Canadian Industry Guidelines for steam generator tubes. The steam generators were returned to service and the plan has operated without another forced outage to date. The FAC degradation of the carbon steel U-bend tube support systems has had the most significant impact on the plant operation causing a number of forced outages. The discovery of the extent of TSP degradation and difficulties to repair TSPs

  10. Eddy currents inspection of CANDU steam generator' tubes using Zetec's ZR-1 Robot: experience in Romania

    Energy Technology Data Exchange (ETDEWEB)

    Hower, S. [Zetec Inc., Quebec, Quebec (Canada); Serban, M. [CNE-Prod U1 Cernavoda (Romania); Vladu, L. [Compcontrol Ing., Bucharest (Romania)

    2006-07-01

    'Full text:' The paper introduces the new ZR-1 Robot System for Inspection and Maintenance/Repair from Zetec that combines the newest state-of-the-art robotics technology with Zetec experience-based innovation to address the needs for inspection and repair of steam generators. The multipurpose ZR-1 can be easily installed to perform the necessary eddy current inspection and remain installed ready for follow-up maintenance and repair. It has superior technical performances and a modular three axis motion of arm that enables 100% coverage of tube sheet. Automated, repeatable, and precise positioning of toolheads, ensures accurate delivery and reducing costly rework and reduces inspection time by 30%. The modular, lightweight, and portable design permits easy assembly and disassembly through small openings and it reduces setup/tear down time by 30%. The first deployment of the new ZR-1 Robot was made in September 2004 at the Cernavoda NPP inspection outage. The Cernavoda plant has four Advanced 600 MW CANDU-design generators that have been in service since 1996. The paper presents also the Zetec's filed experience and customer experience with this system. It describes the equipment setup in Cernavoda's generator mock-up, functional testes and calibration. Finally, provides details on the execution of the inspection, options for standardizing the inspection techniques and conclusions. (author)

  11. Steam-Generator Integrity Program/Steam-Generator Group Project

    International Nuclear Information System (INIS)

    1982-10-01

    The Steam Generator Integrity Program (SGIP) is a comprehensive effort addressing issues of nondestructive test (NDT) reliability, inservice inspection (ISI) requirements, and tube plugging criteria for PWR steam generators. In addition, the program has interactive research tasks relating primary side decontamination, secondary side cleaning, and proposed repair techniques to nondestructive inspectability and primary system integrity. The program has acquired a service degraded PWR steam generator for research purposes. This past year a research facility, the Steam Generator Examination Facility (SGEF), specifically designed for nondestructive and destructive examination tasks of the SGIP was completed. The Surry generator previously transported to the Hanford Reservation was then inserted into the SGEF. Nondestructive characterization of the generator from both primary and secondary sides has been initiated. Decontamination of the channelhead cold leg side was conducted. Radioactive field maps were established in the steam generator, at the generator surface and in the SGEF

  12. Steam generator replacement in Bruce A Unit 1 and Unit 2

    International Nuclear Information System (INIS)

    Hart, R.S.

    2007-01-01

    The Bruce A Generating Station consists of four 900 MW class CANDU units. The reactor and Primary Heat Transport System for each Unit are housed within a reinforced concrete reactor vault. A large duct running below the reactor vaults accommodates the shared fuel handling system, and connects the four reactor vaults to the vacuum building. The reactor vaults, fuelling system duct and the vacuum building constitute the station vacuum containment system. Bruce A Unit 2 was shut down in 1995 and Bruce A Units 1, 3 and 4 were shutdown in 1997. Bruce A Units 3 and 4 were returned to service in late 2003 and are currently operating. Units 1 and 2 remain out of service. Bruce Power is currently undertaking a major rehabilitation of Bruce A Unit 1 and Unit 2 that will extend the in-service tile of these units by at least 25 years. Replacement of the Steam Generators (eight in each unit) is required; this work was awarded to SNC-Lavalin Nuclear (SLN). The existing steam drums (which house the steam separation and drying equipment) will be retained. Unit 2 is scheduled to be synchronized with the grid in 2009, followed by Unit 1 in 2009. Each Bruce A unit has two steam generating assemblies, one located above and to each end of the reactor. Each steam generating assembly consists of a horizontal cylindrical steam drum and four vertical Steam Generators. The vertical Steam Generators connect to individual nozzles that are located on the underside of the Steam Drum (SD). The steam drums are located in concrete shielding structures (steam drum enclosures). The lower sections of the Steam Generators penetrate the top of the reactor vaults: the containment pressure boundary is established by bellows assemblies that connect between the reactor vault roof slab and the Steam Generators. Each Steam Generators is supported from he bottom by a trapeze that is suspended from the reactor vault top structure. The Steam Generator Replacement (SGR) methodology developed by SLN for Unit 1

  13. Cost and schedule reduction for next-generation Candu

    International Nuclear Information System (INIS)

    Hopwood, J.M.; Yu, S.; Pakan, M.; Soulard, M.

    2002-01-01

    AECL has developed a suite of technologies for Candu R reactors that enable the next step in the evolution of the Candu family of heavy-water-moderated fuel-channel reactors. These technologies have been combined in the design for the Advanced Candu Reactor TM1 (ACRTM), AECL's next generation Candu power plant. The ACR design builds extensively on the existing Candu experience base, but includes innovations, in design and in delivery technology, that provide very substantial reductions in capital cost and in project schedules. In this paper, main features of next generation design and delivery are summarized, to provide the background basis for the cost and schedule reductions that have been achieved. In particular the paper outlines the impact of the innovative design steps for ACR: - Selection of slightly enriched fuel bundle design; - Use of light water coolant in place of traditional Candu heavy water coolant; - Compact core design with unique reactor physics benefits; - Optimized coolant and turbine system conditions. In addition to the direct cost benefits arising from efficiency improvement, and from the reduction in heavy water, the next generation Candu configuration results in numerous additional indirect cost benefits, including: - Reduction in number and complexity of reactivity mechanisms; - Reduction in number of heavy water auxiliary systems; - Simplification in heat transport and its support systems; - Simplified human-machine interface. The paper also describes the ACR approach to design for constructability. The application of module assembly and open-top construction techniques, based on Candu and other worldwide experience, has been proven to generate savings in both schedule durations and overall project cost, by reducing premium on-site activities, and by improving efficiency of system and subsystem assembly. AECL's up-to-date experience in the use of 3-D CADDS and related engineering tools has also been proven to reduce both engineering and

  14. Effect of condenser water in-leakage on steam generator water chemistry

    International Nuclear Information System (INIS)

    Balakrishnan, P.V.

    1978-01-01

    Corrosive environments may be generated within steam genrators from condenser cooling water in-leakage. Theoretical as well as experimental evaluation of the aggressiveness of such environments is being carried out for the condenser-cooling waters used at CANDU-PHW nuclear power stations. Calculations have shown that highly concentrated chloride solutions - acidic in the case of sea-water in-leakage, and alkaline in the rest of the cases considered - would be produced within the steam generator. Experiments in a model boiler showed that sea-water in-leakage caused rapid corrosion of carbon steel components when only AVT (all volatile treatment) was used for water chemistry control. Use of a non-volatile reagent, as in the congruent phosphate treatment, avoided the rapid corrosion of carbon steel. On the basis of our studies, congruent phosphate treatment during sea water in-leakage appears desirable. (author)

  15. Steam 80 steam generator instrumentation

    International Nuclear Information System (INIS)

    Carson, W.H.; Harris, H.H.

    1980-01-01

    This paper describes two special instrumentation packages in an integral economizer (preheater) steam generator of one of the first System 80 plants scheduled to go into commercial operation. The purpose of the instrumentation is to obtain accurate operating information from regions of the secondary side of the steam generator inaccessible to normal plant instrumentation. In addition to verification of the System 80 steam generator design predictions, the data obtained will assist in verification of steam generator thermal/hydraulic computer codes developed for generic use in the industry

  16. Flow-induced vibration analysis of heat exchanger and steam generator designs

    International Nuclear Information System (INIS)

    Pettigrew, M.J.; Sylvestre, Y.; Campagna, A.O.

    1977-08-01

    Tube and shell heat exchange components such as steam generators, heat exchangers and condensers are essential parts of CANDU nuclear power stations. Excessive flow-induced vibration may cause tube failures by fatigue or more likely by fretting-wear. Such failures may lead to station shutdowns that are very undesirable in terms of lost production. Hence good performance and reliability dictate a thorough flow-induced vibration analysis at the design stage. This paper presents our approach and techniques in this respect. (author)

  17. Modeling flow-accelerated corrosion in CANDU

    International Nuclear Information System (INIS)

    Burrill, K.A.

    1995-11-01

    Flow-accelerated corrosion (FAC) of large areas of carbon steel in various circuits of CANDU plants generates significant quantities of corrosion products. As well, the relatively rapid corrosion rate can lead to operating difficulties with some components. Three areas in the plant are identified and a simple model of mass-transfer controlled corrosion of the carbon steel is derived and applied to these areas. The areas and the significant finding for each are given below: A number of lines in the feedwater system generate sludge by FAC, which causes steam generator fouling. Prediction of the steady-state iron concentration at the feedtrain outlet compares well with measured values. Carbon steel outlet feeders connect the reactor core with the steam generators. The feeder surface provides the dissolved iron through FAC, which fouls the primary side of the steam generator tubes, and can lead to derating of the plant and difficulty in tube inspection. Segmented carbon steel divider plates in the steam generator primary head leak at an increasing rate with time. The leakage rate is strongly dependent on the tightness of the overlapping joints. which undergo FAC at an increasing rate with time. (author) 7 refs., 5 tabs., 6 figs

  18. Valve maintainability in CANDU-PHW nuclear generating stations

    International Nuclear Information System (INIS)

    Pothier, N.E.; Crago, W.A.

    1977-09-01

    Design, application, layout and administrative factors which affect valve maintainability in CANDU-PHW power reactors are identified and discussed. Some of these are illustrated by examples based on prototype reactor operation experience. Valve maintainability improvements resulting from laboratory development and maintainability analysis, have been incorporated in commercial CANDU-PHW nuclear generating stations. These, also, are discussed and illustrated. (author)

  19. Development of an automated system for CANDU secondary coolant circuit chemistry control

    International Nuclear Information System (INIS)

    Dean, J.R.; Stewart, R.B.

    1978-04-01

    This report is a summary of work done to develop a means for automated control of the secondary coolant chemistry of CANDU 600 MW(e) power reactors using on-line analyzers and a minicomputer. The development work was carried out in cooperation with Saskatchewan Power Corporation at Estevan. Results and conclusions of the program are included, as are recommendations for a prototype installation in a domestic CANDU 600 MW steam generator. (author)

  20. HTGR steam generator development

    International Nuclear Information System (INIS)

    Schuetzenduebel, W.G.; Hunt, P.S.; Weber, M.

    1976-01-01

    More than 40 gas-cooled reactor plants have produced in excess of 400 reactor years of operating experience which have proved a reasonably high rate of gas-cooled reactor steam generator availability. The steam generators used in these reactors include single U-tube and straight-tube steam generators as well as meander type and helically wound or involute tube steam generators. It appears that modern reactors are being equipped with helically wound steam generators of the once-through type as the end product of steam generator evolution in gas-cooled reactor plants. This paper provides a general overview of gas-cooled reactor steam generator evolution and operating experience and shows how design criteria and constraints, research and development, and experience data are factored into the design/development of modern helically wound tube steam generators for the present generation of gas-cooled reactors

  1. Conceptual designs for advanced, high-temperature CANDU reactors

    Energy Technology Data Exchange (ETDEWEB)

    Bushby, S.J. [Atomic Energy of Canada Ltd., Corrosion and Surface Science Branch, Chalk River Laboratories, Chalk River, ON (Canada); Dimmick, G.R. [Atomic Energy of Canada Ltd., Fuel Channel Thermmalhydraulics Branch, Chalk River, ON (Canada); Duffey, R.B. [Atomic Energy of Canada Ltd., Principal Scientist, Chalk River Laboratories, Chalk River, On (Canada); Spinks, N.J. [Atomic Energy of Canada Ltd., Researcher Emeritus, Chalk River Laboratories, Chalk River, ON (Canada); Burrill, K.A. [Atomic Energy of Canada Ltd., Chalk River Laboratories, Chalk River, ON (Canada); Chan, P.S.W. [Atomic Energy of Canada Ltd., Reactor Core Physics Branch, Mississauga, ON (Canada)

    2000-07-01

    AECL is studying advanced reactor concepts with the aim of significant cost reduction through improved thermodynamic efficiency and plant simplification. The program, generically called CANDU-X, also incorporates enhanced safety features, and flexible, proliferation-resistant fuel cycles, whilst retaining the fundamental design characteristics of CANDU: neutron economy, horizontal fuel channels, and a separate D{sub 2}O moderator that provides a passive heat sink. Where possible, proven, existing components and materials would be adopted, so that 'first-of-a-kind' costs and uncertainties are avoided. Three reactor concepts ranging in output from {approx}375 MW(e) to 1150 MW(e) are described. The modular design of a pressure tube reactor allows the plant size for each concept to be tailored to a given market through the addition or removal of fuel channels. Each concept uses supercritical water as the coolant at a nominal pressure of 25 MPa. Core outlet temperatures range from {approx}400degC to 625degC, resulting in substantial improvements in thermodynamic efficiencies compared to current nuclear stations. The CANDU-X Mark 1 concept is an extension of the present CANDU design. An indirect cycle is employed, but efficiency is increased due to higher coolant temperature, and changes to the secondary side; as well, the size and number of pumps and steam generators are reduced. Safety is enhanced through facilitation of thermo-siphoning of decay heat by increasing the temperature of the moderator. The CANDU-X NC concept is also based on an indirect cycle, but natural convection is used to circulate the primary coolant. This approach enhances cycle efficiency and safety, and is viable for reactors operating near the pseudo-critical temperature of water because of large changes in heat capacity and thermal expansion in that region. In the third concept (CANDUal-X), a dual cycle is employed. Supercritical water exits the core and feeds directly into a very high

  2. Chemical cleaning of the Bruce A steam generators

    International Nuclear Information System (INIS)

    Le Surf, J.E.; Mason, J.B.; Symmons, W.R.; Yee, F.

    1992-01-01

    Deposits consisting mostly of oxides and salts and copper metal in the secondary side of the steam generators at the Bruce A Nuclear Generating Station have caused instability in the steam flow and loss of heat capacity, resulting in derating of the units and reduction in power production. Attempts to remove the deposits by pressure pulsing were unsuccessful. Water lancing succeeded in restoring stability, but restrictions on access prevented complete lancing of the tube support plate holes. Chemical cleaning using a modified EPRI-SGOG process has been selected as the best method of removing the deposits. A complete chemical cleaning system has been designed and fabricated for Ontario Hydro by Pacific Nuclear, with support from AECL CANDU and their suppliers. The system consists of self contained modules which are easily interconnected on site. The whole process is controlled from the Control Module, where all parameters are monitored on a computer video screen. The operator can control motorized valves, pumps and heaters from the computer key board. This system incorporates all the advanced technologies and design features that have been developed by Pacific Nuclear in the design, fabrication and operation of many systems for chemical decontamination and cleaning of nuclear systems. 2 figs

  3. Advanced CANDU reactor: an optimized energy source of oil sands application

    International Nuclear Information System (INIS)

    Hopwood, J.M.; Bock, D.; Miller, A.; Kuran, S.; Keil, H.; Fiorino, L.; Duffey, R.; Dunbar, R.B.

    2003-01-01

    Atomic Energy of Canada Limited (AECL) is developing the ACR-700 TM (Advanced CANDU Reactor-700 TM ) to meet customer needs for reduced capital cost, shorter construction schedule, high capacity factor while retaining the benefits of the CANDU experience base. The ACR-700 is based on the concept of CANDU horizontal fuel channels surrounded by heavy water moderator. The major innovation of this design is the use of slightly enriched uranium fuel in a CANFLEX bundle that is cooled by light water. This ensures: higher main steam pressures and temperatures providing higher thermal efficiency; a compact and simpler reactor design with reduced capital costs and shorter construction schedules; and reduced heavy water inventory compared to existing CANDU reactors. ACR-700 is not only a technically advanced and cost effective solution for electricity generating utilities, but also a low-cost, long-life and sustainable steam source for increasing Alberta's Oil Sand production rates. Currently practiced commercial surface mining and extraction of Oil Sand resources has been well established over the last three decades. But a majority of the available resources are somewhat deeper underground require in-situ extraction. Economic removal of such underground resources is now possible through the Steam Assisted Gravity Drainage (SAGD) process developed and proto-type tested in-site. SAGD requires the injection of large quantities of high-pressure steam into horizontal wells to form reduced viscosity bitumen and condensate mixture that is then collected at the surface. This paper describes joint AECL studies with CERI (Canadian Energy Research Institute) for the ACR, supplying both electricity and medium-pressure steam to an oil sands facility. The extensive oil sands deposits in northern Alberta are a very large energy resource. Currently, 30% of Canda's oil production is from the oil sands and this is expected to expand greatly over the coming decade. The bitumen deposits in the

  4. Thermo-Economic Assessment of Advanced,High-Temperature CANDU Reactors

    International Nuclear Information System (INIS)

    Spinks, Norman J.; Pontikakis, Nikos; Duffey, Romney B.

    2002-01-01

    Research underway on the advanced CANDU examines new, innovative, reactor concepts with the aim of significant cost reduction and resource sustainability through improved thermodynamic efficiency and plant simplification. The so-called CANDU-X concept retains the key elements of the current CANDU designs, including heavy-water moderator that provides a passive heat sink and horizontal pressure tubes. Improvement in thermodynamic efficiency is sought via substantial increases in both pressure and temperature of the reactor coolant. Following on from the new Next Generation (NG) CANDU, which is ready for markets in 2005 and beyond, the reactor coolant is chosen to be light water but at supercritical operating conditions. Two different temperature regimes are being studied, Mark 1 and Mark 2, based respectively on continued use of zirconium or on stainless-steel-based fuel cladding. Three distinct cycle options have been proposed for Mark 1: the High-Pressure Steam Generator (HPSG) cycle, the Dual cycle, and the Direct cycle. For Mark 2, the focus is on simplification via a Direct cycle. This paper presents comparative thermo-economic assessments of the CANDU-X cycle options, with the ultimate goal of ascertaining which particular cycle option is the best overall in terms of thermodynamics and economics. A similar assessment was already performed for the NG CANDU. The economic analyses entail obtaining cost estimates of major plant components, such as heat exchangers, turbines and pumps. (authors)

  5. Development situation about the Canadian CANDU Nuclear Power Generating Stations

    Energy Technology Data Exchange (ETDEWEB)

    Jeon, Yu Mi; Kim, Yong Hee; Park, Joo Hwan

    2009-07-15

    The CANDU reactor is the most versatile commercial power reactor in the world. The acronym 'CANDU', a registered trademark of Atomic Energy of Canada Limited, stands for 'CANada Deuterium Uranium'. CANDU uses heavy water as moderator and uranium (originally, natural uranium) as fuel. All current power reactors in Canada are of the CANDU type. Canada exports CANDU type reactor in abroad. CANDU type is used as the nuclear power plants to produce electrical. Today, there are 41 CANDU reactors in use around the world, and the design has continuously evolved to maintain into unique technology and performance. The CANDU-6 power reactor offers a combination of proven, superior and state-of-the-art technology. CANDU-6 was designed specifically for electricity production, unlike other major reactor types. One of its characteristics is a very high operating and fuel efficiency. Canada Nuclear Power Generating Stations were succeeded in a commercial reactor of which the successful application of heavy water reactor, natural uranium method and that on-power fuelling could be achieved. It was achieved through the joint development of a major project by strong support of the federal government, public utilities and private enterprises. The potential for customization to any country's needs, with competitive development and within any level of domestic industrial infrastructure, gives CANDU technology strategic importance in the 21st century.

  6. Development situation about the Canadian CANDU Nuclear Power Generating Stations

    International Nuclear Information System (INIS)

    Jeon, Yu Mi; Kim, Yong Hee; Park, Joo Hwan

    2009-07-01

    The CANDU reactor is the most versatile commercial power reactor in the world. The acronym 'CANDU', a registered trademark of Atomic Energy of Canada Limited, stands for 'CANada Deuterium Uranium'. CANDU uses heavy water as moderator and uranium (originally, natural uranium) as fuel. All current power reactors in Canada are of the CANDU type. Canada exports CANDU type reactor in abroad. CANDU type is used as the nuclear power plants to produce electrical. Today, there are 41 CANDU reactors in use around the world, and the design has continuously evolved to maintain into unique technology and performance. The CANDU-6 power reactor offers a combination of proven, superior and state-of-the-art technology. CANDU-6 was designed specifically for electricity production, unlike other major reactor types. One of its characteristics is a very high operating and fuel efficiency. Canada Nuclear Power Generating Stations were succeeded in a commercial reactor of which the successful application of heavy water reactor, natural uranium method and that on-power fuelling could be achieved. It was achieved through the joint development of a major project by strong support of the federal government, public utilities and private enterprises. The potential for customization to any country's needs, with competitive development and within any level of domestic industrial infrastructure, gives CANDU technology strategic importance in the 21st century

  7. CANDU-BLW-250

    Energy Technology Data Exchange (ETDEWEB)

    Pon, G A

    1967-09-15

    The plant 'La Centrale nucleaire de Gentilly' is located between Montreal and Quebec City on the south shore of the St. Lawrence River and start-up is scheduled for 1971. A CANDU-BLW reactor is the nuclear steam generator. his reactor utilizes a heavy water moderator, natural uranium oxide fuel, and a boiling light water coolant. To be economic, this type of plant must have a minimum light water inventory in the reactor core. A minimum inventory is obtained (a) by reducing the cross-sectional area for coolant flow to a minimum, and (b) by operating at a low-coolant density. In CANDU-BLW-250, this is accomplished by operating a closed spaced fuel rod bundle at high steam quality. These features and others in the BLW concept lead to a number of areas of concern and they are summarized below: (1) Heat Transfer: It is intended that under normal operating conditions the fuel sheaths will always be wetted with coolant. (ii) Hydrodynamic Stability: Experiments and analysis indicate that the plant has a considerable over-power capacity before instability is predicted. (iii) Control: This plant does have a positive power coefficient and the transient performance with various disturbances are detailed. (iv) Safety: The positive power coefficient leads to concern over the loss of coolant accident. The results of some accident analysis are presented. (author)

  8. Steam generator

    International Nuclear Information System (INIS)

    Fenet, J.-C.

    1980-01-01

    Steam generator particularly intended for use in the coolant system of a pressurized water reactor for vaporizing a secondary liquid, generally water, by the primary cooling liquid of the reactor and comprising special arrangements for drying the steam before it leaves the generator [fr

  9. Evaluation of SCC susceptibility of alloy 800 under CANDU SG secondary-side conditions

    International Nuclear Information System (INIS)

    Liu, S.; Lu, Y.

    2006-01-01

    As part of a coordinated program, AECL is developing a set of tools to aid with the prediction and management of steam generator performance. Although stress corrosion cracking (of Alloy 800) has not been detected in any operating steam generator, for life management it is necessary to develop mechanistic models to predict the conditions under which stress corrosion cracking is plausible. Therefore, constant extension rate tests were carried out for Alloy 800 under various steam generator crevice chemistry conditions at applied potentials. These tests were designed to evaluate the stress corrosion cracking susceptibility of Alloy 800 under CANDU( steam generator operating conditions. Based on the experimental results, the recommended electrochemical corrosion potential/pH zone for Alloy 800 determined by electrochemical polarization measurements was verified with the respect of stress corrosion cracking susceptibility. The effects of lead contamination on the stress corrosion cracking susceptibility of Alloy 800 tubing were also evaluated. The experimental results from constant extension rate tests obtained under applied potentials suggest that Alloy 800 has good performance inside much of a previously recommended electrochemical corrosion potential/pH zone determined by electrochemical analysis. Alloy 800 is not susceptible to stress corrosion cracking under normal CANDU steam generator operating conditions. However, Alloy 800 may be susceptible to stress corrosion cracking under near-neutral crevice chemistry conditions in the presence of oxidants. In addition, stress corrosion cracking susceptibility is increased by lead contamination. This observation suggests that the previously defined electrochemical corrosion potential limit under near-neutral crevice conditions could be modified to minimize stress corrosion cracking of Alloy 800. The test results from this work also suggest that the pH dependency of the stress corrosion cracking susceptibility of Alloy 800

  10. Procedure for generating steam and steam generator for operating said procedure

    International Nuclear Information System (INIS)

    Chlique, Bernard.

    1975-01-01

    This invention concerns the generation of steam by bringing the water to be vaporised into indirect thermal exchange relation with the heating steam which condenses when passing in series, along alternate routes, through bundles of tubes immersed in a vaporising chamber. A number of steam generators working on this principle already exist. The purpose of the invention is to modify the operating method of these steam generators by means of a special disposition making it possible to build a compact unit including an additional bundle of tubes heated by the condensates collected at the outlet of each bundle through which the heating steam passes [fr

  11. The effect of steam separataor efficiency on transient following a steam line break

    International Nuclear Information System (INIS)

    Choi, J.H.; Ohn, M.Y.; Lee, N.H.; Hwang, S.T.; Lee, S.K.

    1996-01-01

    Detailed thermalhydraulic simulations for CANDU 6 steam line break inside containment are performed to predict the response of the primary and secondary circuits. The analysis is performed using the thermalhydraulic computer code, CATHENA, with a coupled primary and secondary circuit model. A two-loop representation of the primary and secondary circuits is modelled. The secondary circuit model includes the feedwater line from the deaerator storage tank, multi-node steam generators and the steam line up to the turbine. Two cases were carried out using different assumptions for the efficiency of the steam separators. Case 1 assumes the efficiency of the steam separators becomes zero when the water level in the steam drum increases to the elevation of primary cyclones, or the outlet flow from the steam generator becomes higher than 150 % of normal flow. Case 2 assumes the efficiency becomes zero only when the water level in the steam drum reaches the elevation of primary cyclones. The simulation results show that system responses are sensitive to the assumption for the efficiency of the steam separators and case 1 gives higher discharge energy. Fuel cooling is assured, since primary circuit is cooled down sufficiently by the steam generators for both cases. (author)

  12. Future generations of CANDU: advantages and development with passive safety

    International Nuclear Information System (INIS)

    Duffey, R. B.

    2006-01-01

    Atomic Energy of Canada Limited (AECL) advances water reactor and CANDLT technology using an evolutionary development strategy. This strategy ensures that innovations are based firmly on current experience and keeps our development programs focused on one reactor concept, reducing risks, development costs, and product development cycle times. It also assures our customers that our products will never become obsolete or unsupported, and the continuous line of water reactor development is secure and supported into the future. Using the channel reactor advantage of modularity, the subdivided core has the advantage of passive safety by heat removal to the low- pressure moderator. With continuous improvements, the Advanced CANDU Reactor TM (ACR-1000TM) concept will likely remain highly competitive for a number of years and leads naturally to the next phase of CANDU development, namely the Generation IV CANDU -SCWR concept. This is conventional water technology, since supercritical boilers and turbines have been operating for some time in coal-fired power plants. Significant cost, safety, and performance advantages would result from the CANDU-SCWR concept, plus the flexibility of a range of plant sizes suitable for both small and large electric grids, and the ability for co-generation of electric power, process heat, and hydrogen. In CANDU-SCWR, novel developments are included in the primary circuit layout and channel design. The R and D in Canada is integrated with the Generation IV international Forum (GIF) plans, and has started on examining replaceable insulating liners that would ensure channel life, and on providing completely passive reactor decay heat removal directly to the moderator heat sink without forced cooling. In the interests of sustainability, hydrogen production by a CANDU- SCWR is also be included as part of the system requirements, where the methods for hydrogen production will depend on the outlet temperature of the reactor

  13. Quality Products - The CANDU Approach

    International Nuclear Information System (INIS)

    Ingolfsrud, L. John

    1989-01-01

    The prime focus of the CANDU concept (natural uranium fuelled-heavy water moderated reactor) from the beginning has economy, heavy water losses and radiation exposures also were strong incentives for ensuring good design and reliable equipment. It was necessary to depart from previously accepted commercial standards and to adopt those now accepted in industries providing quality products. Also, through feedback from operating experience and specific design and development programs to eliminate problems and improve performance, CANDU has evolved into today's successful product and one from which future products will readily evolve. Many lessons have been learned along the way. On the one hand, short cuts of failures to understand basic requirements have been costly. On the other hand, sound engineering and quality equipment have yielded impressive economic advantages through superior performance and the avoidance of failures and their consequential costs. The achievement of lifetime economical performance demands quality products, good operation and good maintenance. This paper describes some of the basic approaches leading to high CANDU station reliability and overall excellent performance, particularly where difficulties have had to be overcome. Specific improvements in CANDU design and in such CANDU equipment as heat transport pumps, steam generators, valves, the reactor, fuelling machines and station computers, are described. The need for close collaboration among designers, nuclear laboratories, constructors, operators and industry is discussed. This paper has reviewed some of the key components in the CANDU system as a means of indicating the overall effort that is required to provide good designs and highly reliable equipment. This has required a significant investment in people and funding which has handsomely paid off in the excellent performance of CANDU stations. The close collaboration between Atomic Energy of Canada Limited, Canadian industry and the

  14. Corrosion of the CANDU steam generator tubesheet due to aqueous environment pH

    International Nuclear Information System (INIS)

    Lucan, D.; Fulger, M.; Velciu, L.

    2009-01-01

    There is a side environment that is known to be affected significantly by several factors dependent on the balance of plant conditions (condenser leaks, condensate polishing, and coolant system materials) as well on the operational conditions, particularly through their thermal-hydraulic effects. The presence of tube-tubesheet crevices and restricted flow areas within sludge or surface deposits provides for local concentration sites for various impurities, including the acidic ones. The generalized corrosion can occur and can affect the steam generator performances. It is very important to understand the generalized corrosion mechanism with the purpose of evaluating the amount of corrosion products which exist in the steam generator after a determined period of operation. The purpose of this work consists in the assessment of corrosion behavior of the tubesheet material (carbon steel SA508 cl.2) at normal secondary circuit parameters (temperature, 260 deg. C, pressure, 5.1 MPa). The testing environment was the demineralized water without impurities, at different pH values regulated with morpholine and cyclohexylamine (all volatile treatment - AVT). The results are presented like micrographs, potentiodynamic curves and graphics representing loss of metal by corrosion, corrosion rate, the total corrosion products, the adherent corrosion products, the released corrosion products and the release of the metal. (authors)

  15. CANDU-BLW-250

    Energy Technology Data Exchange (ETDEWEB)

    Pon, G. A. [Atomic Energy of Canada Ltd, Sheridan Park, ON (Canada)

    1968-04-15

    The plant ''La Centrale nucleaire de Gentiliy'' is located between Montreal and Quebec City on the south shore of the St. Lawrence River. Startup is scheduled for 1971. A CANDU-BLW reactor is the nuclear steam generator. This reactor utilizes a heavy-water moderator, natural uranium oxide fuel, and a boiling light-water coolant. To be economic, this type of plant must have a minimum light-water inventory in the reactor core. A minimum inventory is obtained (a) by reducing the cross-sectional area for coolant flow to a minimum, and (b) by operating at a low coolant density. In CANDU-BLW-250, this is accomplished by operating a closed spaced fuel rod bundle at high steam quality. These features and others in the BLW concept lead to a number of areas of concern and they are summarized below: (i) Heat transfer. It is intended that under normal operating conditions the fuel sheaths will always be wetted with coolant. Some experiments and backup calculations are presented to support this specification. (ii) Hydrodynamic stability. Experiments and analysis indicate that the plant has a considerable over-power capacity before instability is predicted. (iii) Control. This plant does have a positive power coefficient and the transient performance with various disturbances is detailed. (iv) Safety. The positive power coefficient leads to concern over the loss of coolant accident. The results of some accident analyses are presented. (author)

  16. Supporting CANDU operators-CANDU owners group

    International Nuclear Information System (INIS)

    Collingwood, B.R.

    1997-01-01

    The CANDU Owners Group (COG) was formed in 1984 by the Canadian CANDU owning utilities and Atomic Energy of Canada limited (AECL). Participation was subsequently extended to all CANDU owners world-wide. The mandate of the COG organization is to provide a framework for co-operation, mutual assistance and exchange of information for the successful support, development, operation, maintenance and economics of CANDU nuclear electric generating stations. To meet these objectives COG established co-operative programs in two areas: 1. Station Support. 2. Research and Development. In addition, joint projects are administered by COG on a case by case basis where CANDU owners can benefit from sharing of costs

  17. Passive heat removal in CANDU

    International Nuclear Information System (INIS)

    Hart, R.S.

    1997-01-01

    CANDU has a tradition of incorporating passive systems and passive components whenever they are shown to offer performance that is equal to or better than that of active systems, and to be economic. Examples include the two independent shutdown systems that employ gravity and stored energy respectively, the dousing subsystem of the CANDU 6 containment system, and the ability of the moderator to cool the fuel in the event that all coolant is lost from the fuel channels. CANDU 9 continues this tradition, incorporating a reserve water system (RWS) that increases the inventory of water in the reactor building and profiles a passive source of makeup water and/or heat sinks to various key process systems. The key component of the CANDU 9 reserve water system is a large (2500 cubic metres) water tank located at a high elevation in the reactor building. The reserve water system, while incorporating the recovery system functions, and the non-dousing functions of the dousing tank in CANDU 6, embraces other key systems to significantly extend the passive makeup/heat sink capability. The capabilities of the reserve water system include makeup to the steam generators secondary side if all other sources of water are lost; makeup to the heat transport system in the event of a leak in excess of the D 2 O makeup system capability; makeup to the moderator in the event of a moderator leak when the moderator heat sink is required; makeup to the emergency core cooling (ECC) system to assure NPSH to the ECC pumps during a loss of coolant accident (LOCA), and provision of a passive heat sink for the shield cooling system. Other passive designs are now being developed by AECL. These will be incorporated in future CANDU plants when their performance has been fully proven. This paper reviews the passive heat removal systems and features of current CANDU plants and the CANDU 9, and briefly reviews some of the passive heat removal concepts now being developed. (author)

  18. Horizontal steam generator thermal-hydraulics

    Energy Technology Data Exchange (ETDEWEB)

    Ubra, O. [SKODA Praha Company, Prague (Czechoslovakia); Doubek, M. [Czech Technical Univ., Prague (Czechoslovakia)

    1995-09-01

    Horizontal steam generators are typical components of nuclear power plants with pressure water reactor type VVER. Thermal-hydraulic behavior of horizontal steam generators is very different from the vertical U-tube steam generator, which has been extensively studied for several years. To contribute to the understanding of the horizontal steam generator thermal-hydraulics a computer program for 3-D steady state analysis of the PGV-1000 steam generator has been developed. By means of this computer program, a detailed thermal-hydraulic and thermodynamic study of the horizontal steam generator PGV-1000 has been carried out and a set of important steam generator characteristics has been obtained. The 3-D distribution of the void fraction and 3-D level profile as functions of load and secondary side pressure have been investigated and secondary side volumes and masses as functions of load and pressure have been evaluated. Some of the interesting results of calculations are presented in the paper.

  19. Steam generators secondary side chemical cleaning at Point Lepreau using the Siemen's high temperature process

    International Nuclear Information System (INIS)

    Verma, K.; MacNeil, C.; Odar, S.

    1996-01-01

    The secondary sides of all four steam generators at the Point Lepreau Nuclear Generating Stations were cleaned during the 1995 annual outage run-down using the Siemens high temperature chemical cleaning process. Traditionally all secondary side chemical cleaning exercises in CANDU as well as the other nuclear power stations in North America have been conducted using a process developed in conjunction with the Electric Power Research Institute (EPRI). The Siemens high temperature process was applied for the first time in North America at the Point Lepreau Nuclear Generating Station (PLGS). The paper discusses experiences related to the pre and post award chemical cleaning activities, chemical cleaning application, post cleaning inspection results and waste handling activities. (author)

  20. Identification of leaky steam generators by iodine mapping technique and development of tools for cutting of tubes of steam generators of Indian PHWRS

    International Nuclear Information System (INIS)

    Subba Rao, D.

    2006-01-01

    Kakrapar Atomic Power Station (2X220 MWe) located in Mandvi Taluka of Surat District in the state of Gujarat is the fifth Nuclear Power Station of the country. It has got an excellent record in the field of operation, safety, public awareness and emergency preparedness. KAPS Unit -1 achieved first criticality in Sep-1992 and was declared for commercial operation in may-1993. KAPS Unit -2 achieved first criticality in Jan-1995 and was declared for commercial operation in Sep-1995. So far station has generated about 30 billion units.Unit-1 achieved 98.4% and was graded as a world's No.1 in year 2002 amongst all CANDU type reactors. KAPS Unit -1 has made another record of operating continuously for more than 300 days in Indian PHWR s operating history. This paper mainly deals with the Indian PHWRs Steam Generators (SG) tube leaks, leaky steam generator identification by Iodine mapping, and development of special tool for cutting, removal and plugging of leaky tubes. These Steam Generators are designed by M/s Kraft Werke Union (KWU) of Siemens Group, West Germany, and Manufactured by M/s ENSA, SPAIN for Unit- 1 and by M/s MAN-GHH, Germany for Unit- 2. First time in October-2002 one of the Steam Generators of Unit-1 developed tube leak. To identify leaky Steam Generator, KAPS has established a method of Iodine mapping. With that the leaky SG was identified in very short time and corrective actions were taken immediately. Total three tube leaks (two in SG-4 of Unit-1 and one in SG-1 of unit-2) were experienced in both Units'. Following observations were made on SG tubes failure: All failures were in cold leg side; All Failures / deterioration locations were in front of main feed water nozzle; All Failures / deterioration locations were observed to be just above tube support plate (TSP) number 4 or 5; Deterioration ( i.e. wall thinning) observed from OD side and these tubes were adjacent to failed tubes; In all the three incidents, failed / deteriorated tubes were

  1. Steam generators - problems and prognosis

    International Nuclear Information System (INIS)

    Tapping, R.L.

    1997-05-01

    Steam-generator problems, largely a consequence of corrosion and fouling, have resulted in increased inspection requirements and more regulatory attention to steam-generator integrity. In addition, utilities have had to develop steam-generator life-management strategies, including cleaning and replacement, to achieve design life. This paper summarizes the pertinent data to 1993/1994, and presents an overview of current steam-generator management practices. (author)

  2. EPRI steam generator programs

    International Nuclear Information System (INIS)

    Martel, L.J.; Passell, T.O.; Bryant, P.E.C.; Rentler, R.M.

    1977-01-01

    The paper describes the current overall EPRI steam generator program plan and some of the ongoing projects. Because of the recent occurrence of a corrosion phenomenon called ''denting,'' which has affected a number of operating utilities, an expanded program plan is being developed which addresses the broad and urgent needs required to achieve improved steam generator reliability. The goal of improved steam generator reliability will require advances in various technologies and also a management philosophy that encourages conscientious efforts to apply the improved technologies to the design, procurement, and operation of plant systems and components that affect the full life reliability of steam generators

  3. Design of SMART steam generator cassette

    International Nuclear Information System (INIS)

    Kim, Y. W.; Kim, J. I.; Jang, M. H.

    2001-01-01

    Basic design development for the steam generator to be installed in the integral reactor SMART has been performed. Optimization of the steam generator shape, determination of the basic dimension and confirmation of the structural strength have been carried out. Individual steam generator cassette can be replaced in the optimized design concept of steam generator. Shape design of the steam generator cassette has been done on the computer based on 3-D CAE strategy. The structural integrity of the developed steam generator was investigated by performing the dynamic analysis for the steam generator cassette, flow induced vibration analysis for the tube bundle, and the thermo-mechanical analysis for the module header and tube. As for the manufacturing of steam generator, the numerical and the experimental simulation have been carried to control the amount of spring back and to eliminate residual stress. SMART steam generator cassette was developed by a sequential research of the aforementioned activities

  4. Development and verification of a space-dependent dynamic model of a natural circulation steam generator

    International Nuclear Information System (INIS)

    Mewdell, C.G.; Harrison, W.C.; Hawley, E.H.

    1980-01-01

    This paper describes the development and verification of a Non-Linear Space-Dependent Dynamic Model of a Natural Circulation Steam Generator typical of boilers used in CANDU nuclear power stations. The model contains a detailed one-dimensional dynamic description of both the primary and secondary sides of an integral pre-heater natural circulation boiler. Two-phase flow effects on the primary side are included. The secondary side uses a drift-flux model in the boiling sections and a detailed non-equilibrium point model for the steam drum. The paper presents the essential features of the final model called BOILER-2, its solution scheme, the RD-12 loop and test boiler, the boiler steady-state and transient experiments, and the comparison of the model predictions with experimental results. (author)

  5. Assessment and Management of Ageing of Major Nuclear Power Plant Components Important to Safety: Steam Generators. 2011 Update

    International Nuclear Information System (INIS)

    2011-11-01

    generator of the PWR, WWER and CANDU nuclear power plants. The objective of this report is to update and supersede IAEA-TECDOC-981 in order to provide current ageing management guidance for PWR, WWER and CANDU steam generators to all involved in the operation and regulation of nuclear power plants and thus to help ensure steam generator integrity in IAEA Member States throughout their entire service life.

  6. Conceptual designs for very high-temperature CANDU reactors

    Energy Technology Data Exchange (ETDEWEB)

    Bushby, S.J.; Dimmick, G.R.; Duffey, R.B. [Atomic Energy of Canada Ltd., Chalk River, Ontario (Canada)

    2000-07-01

    power plants ({approx}300 - 500 MWe). The steam cycle and coolant conditions are proposed to be the same as CANDU-X Mark I. The major difference between the reactors is that natural convection would be used to circulate the primary coolant around the heat transport system. This approach enhances cycle efficiency and safety, and is viable for reactors operating near the critical point of water because of the large increases in heat capacity and thermal expansion coefficient across the core. The third concept, CANDUal-X, is a dual cycle concept, with core conditions similar to the Mark 1 and NC. In this concept, coolant leaving the core is first expanded through a VHP turbine in a direct cycle. Employing a dual steam cycle avoids a high-pressure steam generator. The conditions of the core and the VHP expansion can be designed such that the exhaust from the turbine is used as the heat source for an indirect cycle; that is, the secondary side can be equivalent to that presently employed in conventional CANDU plants. An advantage of this concept over conventional direct cycle nuclear plants is that only one relatively small turbine is exposed to radioactive coolant, and it is located within containment. In summary, the reactors described above represent concepts that evolve logically from the current CANDU designs to higher efficiency, with only modest extensions of current technology. This paper presents a technical overview of the different conceptual designs, as well as a brief discussion of the enabling technologies that are common to each, which is the focus of current R and D. (author)

  7. Conceptual designs for very high-temperature CANDU reactors

    International Nuclear Information System (INIS)

    Bushby, S.J.; Dimmick, G.R.; Duffey, R.B.

    2000-01-01

    (∼300 - 500 MWe). The steam cycle and coolant conditions are proposed to be the same as CANDU-X Mark I. The major difference between the reactors is that natural convection would be used to circulate the primary coolant around the heat transport system. This approach enhances cycle efficiency and safety, and is viable for reactors operating near the critical point of water because of the large increases in heat capacity and thermal expansion coefficient across the core. The third concept, CANDUal-X, is a dual cycle concept, with core conditions similar to the Mark 1 and NC. In this concept, coolant leaving the core is first expanded through a VHP turbine in a direct cycle. Employing a dual steam cycle avoids a high-pressure steam generator. The conditions of the core and the VHP expansion can be designed such that the exhaust from the turbine is used as the heat source for an indirect cycle; that is, the secondary side can be equivalent to that presently employed in conventional CANDU plants. An advantage of this concept over conventional direct cycle nuclear plants is that only one relatively small turbine is exposed to radioactive coolant, and it is located within containment. In summary, the reactors described above represent concepts that evolve logically from the current CANDU designs to higher efficiency, with only modest extensions of current technology. This paper presents a technical overview of the different conceptual designs, as well as a brief discussion of the enabling technologies that are common to each, which is the focus of current R and D. (author)

  8. Steam generators, turbines, and condensers. Volume six

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    Volume six covers steam generators (How steam is generated, steam generation in a PWR, vertical U-tube steam generators, once-through steam generators, how much steam do steam generators make?), turbines (basic turbine principles, impulse turbines, reaction turbines, turbine stages, turbine arrangements, turbine steam flow, steam admission to turbines, turbine seals and supports, turbine oil system, generators), and condensers (need for condensers, basic condenser principles, condenser arrangements, heat transfer in condensers, air removal from condensers, circulating water system, heat loss to the circulating water system, factors affecting condenser performance, condenser auxiliaries)

  9. Repair technique for steam generator tubes using electroforming

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Seung Ho; Jeong, Hyun Kyu; Seo, Moon Hong

    2001-07-01

    Pickering B CANDU Unit 5 had experienced leakage at sleeve/tube joint due to severe and local pitting in 1992{delta}1993. One year later, OHT developed electrosleeving techniques for steam generator tube repair which was applied at Pickering B CANDU Unit 5, Oconee Unit 1 and Callaway in 1994, 1995 and 1999 respectively. In the results of electrosleeved tube test, electrosleeve materials were stronger than mother tubes in mechanical properties and corrosion resistance under design criteria. Two analytical models were originally developed for estimating the failure temperature under severe accident transients. Electrosleeve, a structural layer of fine grained nickel is electroformed onto the strike by circulating an aqueous solution of Ni sulfate or sulfamate with NiCO3. The patents published by FTI said that the electrolyte for electroforming the structural layer contains a pinning agent to inhibit growth of metal grains in the electroformed layer. The pinning agent contains phosphoric, phosphorous acid, molybdenum. In localization of electrosleeving, there are some problems like as 1)low plating rate, 2)high residual stress, 3)alloy composition, 4)low material properties at high temperature. Ni-Fe plating exhibit anomalous codeposition; that is less noble metal, Fe, deposits preferentially to the more noble metal, Ni. Ductility decrease and residual stress increase with increase of Fe content in plate layer. Addition of particle size of 10{delta}400{mu}m makes residual stress compressive in plate layer. Composite plating show excellent high temperature properties.

  10. Repair technique for steam generator tubes using electroforming

    International Nuclear Information System (INIS)

    Kim, Seung Ho; Jeong, Hyun Kyu; Seo, Moon Hong

    2001-07-01

    Pickering B CANDU Unit 5 had experienced leakage at sleeve/tube joint due to severe and local pitting in 1992δ1993. One year later, OHT developed electrosleeving techniques for steam generator tube repair which was applied at Pickering B CANDU Unit 5, Oconee Unit 1 and Callaway in 1994, 1995 and 1999 respectively. In the results of electrosleeved tube test, electrosleeve materials were stronger than mother tubes in mechanical properties and corrosion resistance under design criteria. Two analytical models were originally developed for estimating the failure temperature under severe accident transients. Electrosleeve, a structural layer of fine grained nickel is electroformed onto the strike by circulating an aqueous solution of Ni sulfate or sulfamate with NiCO3. The patents published by FTI said that the electrolyte for electroforming the structural layer contains a pinning agent to inhibit growth of metal grains in the electroformed layer. The pinning agent contains phosphoric, phosphorous acid, molybdenum. In localization of electrosleeving, there are some problems like as 1)low plating rate, 2)high residual stress, 3)alloy composition, 4)low material properties at high temperature. Ni-Fe plating exhibit anomalous codeposition; that is less noble metal, Fe, deposits preferentially to the more noble metal, Ni. Ductility decrease and residual stress increase with increase of Fe content in plate layer. Addition of particle size of 10δ400μm makes residual stress compressive in plate layer. Composite plating show excellent high temperature properties

  11. Hybrid preheat/recirculating steam generator

    International Nuclear Information System (INIS)

    Lilly, G.P.

    1985-01-01

    The patent describes a hybrid preheat/recirculating steam generator for nuclear power plants. The steam generator utilizes recirculated liquid to preheat incoming liquid. In addition, the steam generator incorporates a divider so as to limit the amount of recirculating water mixed with the feedwater. (U.K.)

  12. Models for coolant void reactivity evaluation in Candu Generation II and III+

    International Nuclear Information System (INIS)

    Popov, Alexi V.; Chambon, Richard P.; Le Tellier, Romain; Marleau, Guy; Hebert, Alain

    2008-01-01

    In the simulation of large-break loss-of-coolant accidents, homogenised cross-sections from trans- port calculations are used. These are usually computed in single cells or lattices representative for an infinite repeated pattern. Large coolant accidents in Candu, however, usually exhibit a checkerboard pattern of cooled and voided channels represented by lattices. It is reasonable, therefore, that homogenised cross-sections be produced in assemblies of lattices. This allows simulating the checkerboard voiding pat- tern and more realistically reproducing the lattice boundary conditions. The result is better simulation of the accident and more precise evaluation of coolant-void reactivity. For the present study, homogenised cross-sections are generated in a 2x2 heterogeneous assembly of four lattices for Generation II and III+ Candu designs. Results of reactivity calculations with the reactor code are compared to those using the traditional method. The difference is significant for Generation III+ Candu. (authors)

  13. Economics of CANDU-PHW

    International Nuclear Information System (INIS)

    Jackson, H.A.; Woodhead, L.W.; Fanjoy, G.R.

    1984-03-01

    The CANDU-Pressurized Heavy Water (CANDU-PHW) type of nuclear-electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This paper discusses the cost of producing electricity from CANDU, presents actual cost experience of CANDU and coal in Ontario, presents projected CANDU and coal costs in Ontario and compares CANDU and Light Water Reactor cost estimates in Ontario

  14. Economics of CANDU-PHW

    International Nuclear Information System (INIS)

    McConnell, L.G.; Woodhead, L.W.; Fanjoy, G.R.

    1982-03-01

    The CANDU-Pressurized Heavy Water (CANDU-PHW) type of nuclear-electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This paper discusses the cost of producing electricity from CANDU, presents actual cost experience of CANDU and coal in Ontario, presents projected CANDU and coal costs in Ontario and compares CANDU and Light Water Reactor cost estimates in Ontario

  15. Economics of CANDU-PHW

    International Nuclear Information System (INIS)

    Jackson, H.A.; Horton, E.P.; Woodhead, L.W.; Fanjoy, G.R.

    1985-03-01

    The CANDU-Pressurized Heavy Water (CANDU-PHW) type of nuclear-electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This paper discusses the cost of producing electricity from CANDU, presents actual cost experience of CANDU and coal in Ontario, presents projected CANDU and coal costs in Ontario and compares CANDU and Light Water Reactor cost estimates in Ontario

  16. French steam generator design developments

    International Nuclear Information System (INIS)

    Ginier, R.; Campan, J.L.; Pontier, M.; Leridon, A.; Remond, A.; Castello, G.; Holcblat, A.; Paurobally, H.

    1986-01-01

    From the outset of the French nuclear power program, a significant R and D effort has been invested in improvement of the design and operation of Pressurized Water Reactors including a special committment to improving steam generators. The steam generator enhancement program has spawned a wide variety of specific R and D resources, e.g., low temperature hydraulic models for investigation of areas with single-phase flow, and freon-filled models for simulation of areas of steam generators experiencing two-phase flow (tube bundles and moisture separators). For the moisture separators, a large scale research program using freon-filled models and highly sophisticated instrumentation was used. Tests at reactor sites during startup of both 900 MWe and 1300 MWe have been used to validate the assumptions made on the basis of loop tests. These tests also demonstrated the validity of using freon to simulate two-phase flow conditions. The wealth of knowledge accumulated by the steam generator R and D program has been used to develop a new design of steam generators for the N4 plants. The current R and D effort is aimed at qualifying the N4 steam generator model and developing more comprehensive models. One prong of the R and D effort is the Megeve program. Megeve is a 25 MW steam generator which simulates operating conditions of the N4 model. The other prong is Clotaire, a freon-filled steam generator model which will be used to qualify thermal/hydraulic design codes used for multidimensional calculations for design of tube bundles

  17. Steam generator tube integrity program

    International Nuclear Information System (INIS)

    Dierks, D.R.; Shack, W.J.; Muscara, J.

    1996-01-01

    A new research program on steam generator tubing degradation is being sponsored by the U.S. Nuclear Regulatory Commission (NRC) at Argonne National Laboratory. This program is intended to support a performance-based steam generator tube integrity rule. Critical areas addressed by the program include evaluation of the processes used for the in-service inspection of steam generator tubes and recommendations for improving the reliability and accuracy of inspections; validation and improvement of correlations for evaluating integrity and leakage of degraded steam generator tubes, and validation and improvement of correlations and models for predicting degradation in steam generator tubes as aging occurs. The studies will focus on mill-annealed Alloy 600 tubing, however, tests will also be performed on replacement materials such as thermally-treated Alloy 600 or 690. An overview of the technical work planned for the program is given

  18. Steam generator tube extraction

    International Nuclear Information System (INIS)

    Delorme, H.

    1985-05-01

    To enable tube examination on steam generators in service, Framatome has now developed a process for removing sections of steam generator tubes. Tube sections can be removed without being damaged for treating the tube section expanded in the tube sheet

  19. International examples of steam generator replacement

    International Nuclear Information System (INIS)

    Wiechmann, K.

    1993-01-01

    Since 1979-1980 a total of twelve nuclear power plants world-wide have had their steam generators replaced. The replacement of the Combustion steam generators in the Millstone-2 plant in the United States was completed very recently. Steam generator replacement activities are going on at present in four plants. In North Anna, the steam generators have been under replacement since January 1990. In Japan, preparations have been started for Genkai-1. Since January 1992, the two projects in Beznau-1, Switzerland, and Doel-3, Belgium, have bee planned and executed in parallel. Why steam generator replacement? There are a number of defect mechanisms which give rise to the need for early steam generator replacement. One of the main reasons is the use of Inconel-600 as material for the heating tubes. Steam generator heating tubes made of Inconel-600 have been known to exhibit their first defects due to stress corrosion cracking after less than one year of operation. (orig.) [de

  20. Cheaper power generation from surplus steam generating capacities

    International Nuclear Information System (INIS)

    Gupta, K.

    1996-01-01

    Prior to independence most industries had their own captive power generation. Steam was generated in own medium/low pressure boilers and passed through extraction condensing turbines for power generation. Extraction steam was used for process. With cheaper power made available in Nehru era by undertaking large hydro power schemes, captive power generation in industries was almost abandoned except in sugar and large paper factories, which were high consumers of steam. (author)

  1. Luncheon address: Development of the CANDU reactor

    International Nuclear Information System (INIS)

    Bain, A.S.

    1997-01-01

    The paper is a highlight of the some of the achievements in the development of the CANDU Reactor, taken from the book C anada Enters the Nuclear Age . The CANDU reactor is one of Canada's greatest scientific/engineering achievements, that started in the 1940's and bore fruit with the reactors of the 60's, 70's, and 80's. The Government decided in the 1950's to proceed with a demonstration nuclear power reactor (NPD), AECL invited 7 Canadian corporations to bid on a contract to design and construct the NPD plant. General Electric was selected. A utility was also essential for participation and Ontario Hydro was chosen. In May 1957 it was concluded that the minimum commercial size would be about 200MWe and it should use horizontal pressure tubes to contain the fuel and pressurized heavy water coolant. The book also talks of standard out-reactor components such as pumps, valves, steam generators and piping. A major in-reactor component of interest was the fuel, fuel channels and pressure tubes. A very high level of cooperation was required for the success of the CANDU program

  2. Candu technology: the next generation now

    International Nuclear Information System (INIS)

    Hopwood, J.M.; Duffey, R.B.; Torgerson, D.F.

    2001-01-01

    We describe the development philosophy, direction and concepts that are being utilized by AECL to refine the CANDU reactor to meet the needs of current and future competitive energy markets. The technology development path for CANDU reactors is based on the optimization of the pressure tube concept. Because of the inherent modularity and flexibility of this basis for the core design, it is possible to provide a seamless and continuous evolution of the reactor design and performance. There is no need for a drastic shift in concept, in technology or in fuel. By continual refinement of the flow and materials conditions in the channels, the basic reactor can be thermally and operationally efficient, highly competitive and economic, and highly flexible in application. Thus, the design can build on the successful construction and operating experience of the existing plants, and no step changes in development direction are needed. This approach minimizes investor, operator and development risk but still provides technological, safety and performance advances. In today's world energy markets, major drivers for the technology development are: (a) reduced capital cost; (b) improved operation; (c) enhanced safety; and (d) fuel cycle flexibility. The drivers provide specific numerical targets. Meeting these drivers ensures that the concept meets and exceeds the customer economic, performance, safety and resource use goals and requirements, including the suitable national and international standards. This logical development of the CANDU concept leads naturally to the 'Next Generation' of CANDU reactors. The major features under development include an optimized lattice for SEU (slightly enriched uranium) fuel, light water cooling coupled with heavy water moderation, advanced fuel channels and CANFLEX fuel, optimization of plant performance, enhanced thermal and BOP (balance of plant) efficiency, and the adoption of layout and construction technology adapted from successful on

  3. Steam Generator Analysis Tools and Modeling of Degradation Mechanisms

    International Nuclear Information System (INIS)

    Yetisir, M.; Pietralik, J.; Tapping, R.L.

    2004-01-01

    The degradation of steam generators (SGs) has a significant effect on nuclear heat transport system effectiveness and the lifetime and overall efficiency of a nuclear power plant. Hence, quantification of the effects of degradation mechanisms is an integral part of a SG degradation management strategy. Numerical analysis tools such as THIRST, a 3-dimensional (3D) thermal hydraulics code for recirculating SGs; SLUDGE, a 3D sludge prediction code; CHECWORKS a flow-accelerated corrosion prediction code for nuclear piping, PIPO-FE, a SG tube vibration code; and VIBIC and H3DMAP, 3D non-linear finite-element codes to predict SG tube fretting wear can be used to assess the impacts of various maintenance activities on SG thermal performance. These tools are also found to be invaluable at the design stage to influence the design by determining margins or by helping the designers minimize or avoid known degradation mechanisms. In this paper, the aforementioned numerical tools and their application to degradation mechanisms in CANDU recirculating SGs are described. In addition, the following degradation mechanisms are identified and their effect on SG thermal efficiency and lifetime are quantified: primary-side fouling, secondary-side fouling, fretting wear, and flow-accelerated corrosion (FAC). Primary-side tube inner diameter fouling has been a major contributor to SG thermal degradation. Using the results of thermalhydraulic analysis and field data, fouling margins are calculated. Individual effects of primary- and secondary-side fouling are separated through analyses, which allow station operators to decide what type of maintenance activity to perform and when to perform the maintenance activity. Prediction of the fretting-wear rate of tubes allows designers to decide on the number and locations of support plates and U-bend supports. The prediction of FAC rates for SG internals allows designers to select proper materials, and allows operators to adjust the SG maintenance

  4. Role of operator response guidelines in CANDU 9 design program

    International Nuclear Information System (INIS)

    Jaitly, R.K.

    2000-01-01

    The CANDU 9 is a large version of the CANDU Pressurized Heavy Water Reactor (PHWR) system developed in Canada. With an electrical output of approximately 935 MWe, the CANDU 9 complements the established mid-size CANDU 6 (700 MWe) and makes use of proven technology updated with state of the art features resulting from ongoing development. The CANDU 9 builds on the reactor and process system designs of the operating Darlington and Bruce B plants, and incorporates a modified CANDU 6 station layout, as well as improved construction methods and operational features. A high level of standardization has always been a feature of CANDU reactors. This theme is emphasized in the CANDU 9; all key components (reactor core, steam generators, coolant pumps, pressure tubes, etc.) are of the same design as those proven in service in the operating CANDU power stations. Including Probabilistic Safety Assessment (PSA) as part of the CANDU 9 design process from the outset of the program was seen as key to ensuring completeness of safety related requirements. The PSA work provided an in-depth understanding of the plant response to various postulated accidents. As well, the time frame for recovery and the related operator actions were identified. This information together with AECL's experience in supporting the development of Emergency Operating Procedures (EOPs) for the operating CANDU reactors are the basis for preparation of CANDU 9 Operator Response Guidelines (ORGs). Technical content, format and human factors considerations adopted for the ORGs are such that these can be readily converted to EOPs. The scope of ORGs includes generic as well as event specific ORGs. This dual approach is required to provide defense-in-depth. This paper describes the process used to prepare ORGs for the CANDU 9 reactor and discusses important benefits gained from the application of ORGs as input to the control center design and future preparation of the EOPs. (author)

  5. Diagnostic system of steam generator, especially molten metal heated steam generator

    International Nuclear Information System (INIS)

    Matal, O.; Martoch, J.

    1986-01-01

    A diagnostic system is described and graphically represented consisting of a leak detector, a medium analyzer and sensors placed on the piping connected to the indication sections of both tube plates. The advantage of the designed system consists in the possibility of detecting tube failure immediately on leak formation, especially in generators with duplex tubes. This shortens the period of steam generator shutdown for repair and reduces power losses. The design also allows to make periodical leak tests during planned steam generator shutdowns. (A.K.)

  6. Steam generator with perfected dryers

    International Nuclear Information System (INIS)

    Fenet, J.C.

    1987-01-01

    This steam generator has vertically superposed array of steam dryers. These dryers return the steam flow of 180 0 . The return of the water is made by draining channels to the steam production zone [fr

  7. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's Steam Generator Owners Group (SGOG II) will disband in December 1986 and be replaced in January 1987 by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue the emphasis on reliability and life extension that was carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems, such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation (NDE). These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and solve small problems before they become large problems

  8. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's (EPRI's) Steam Generator Owners Group (SGOG II) will disband in December 1986, and be replaced in January 1987, by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue to emphasize reliability and life extension, which were carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation. These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and to solve small problems before they become large problems

  9. 49 CFR 229.105 - Steam generator number.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 4 2010-10-01 2010-10-01 false Steam generator number. 229.105 Section 229.105..., DEPARTMENT OF TRANSPORTATION RAILROAD LOCOMOTIVE SAFETY STANDARDS Safety Requirements Steam Generators § 229.105 Steam generator number. An identification number shall be marked on the steam generator's...

  10. LMFBR steam generator development: duplex bayonet tube steam generator. Volume II

    International Nuclear Information System (INIS)

    DeFur, D.D.

    1975-04-01

    This report represents the culmination of work performed in fulfillment of ERDA Contract AT(11-1)-2426, Task Agreement 2, in which alternate steam generator designs were developed and studied. The basic bayonet tube generator design previously developed by C-E under AEC Contract AT(11-1)-3031 was expanded by incorporating duplex heat transfer tubes to enhance the unit's overall safety and reliability. The effort consisted of providing and evaluating conceptual designs of the evaporator, superheater and reheater components for a large plant LMFBR steam generator (950 MWt per heat transport loop)

  11. Advancing CANDU Technology Through R and D

    International Nuclear Information System (INIS)

    Torgerson, David F.

    1993-01-01

    CANDU reactors are evolving to meet future requirements using incremental changes as opposed to revolutionary design changes. The main elements for advancing the technology reducing capital and operating, increasing capacity factors, increasing passive safety, and enhancing fuel/fuel cycle flexibility. These elements are being addressed by carrying out research and development in the areas of safety, plant systems and components, heavy water production, information technology, fuel channels, and fuel/fuel cycle technology. In safety, the focus is on using the inherent features of CANDU to enhance passive or natural safety concepts, such as the use of the moderator as an effective heat sink, and the development of advanced fuels to improve critical heat flux and to reduce source terms. Plant systems and components work includes improvements to plant systems such as steam generators, heat exchangers, pump seals, and advanced control room technology. Heavy water processes are being developed that can be used with existing hydrogen production plants, or that can be used in a stand-alone mode. Information technology is being developed to cover all aspects of CANDU design, construction, and operation. Fuel channel improvements include elucidation and application of basic materials science for life extension, and the development of advanced non-destructive examination methods. Fuel and fuel cycle work is focusing on LWR/CANDU synergy, such as the use of recovered uranium and the direct use of spent PWR fuel in CANDU reactor, advanced fuels to improve burnup and economics (e. g., the joint AECB/KAERI Conflux program), and low void reactivity fuel to enhance passive safety. This paper gives an overview of some of the R and D supporting these activities, with particular emphasis on Alice's vision for advancing CANDU technology over the next 10 years

  12. Some aspects of primary and secondary water chemistry in CANDU reactors

    International Nuclear Information System (INIS)

    LeSurf, J.E.

    1978-09-01

    A brief review of the water chemistry in various circuits of CANDU reactors is given. Then, five particular aspects of recent work are highlighted: (i) Radiation Field Growth: in-reactor and out-reactor studies have related water chemistry to corrosion product deposition on fuel sheaths and subsequent contamination of out-core surfaces. (ii) Metal Oxide Solubility: novel techniques are being used to measure the solubilities of metal oxides at primary circuit conditions. (iii) Decontamination: the use of heavy water as coolant in CANDU reactors led to the development of a unique decontamination strategy and technique, called CAN-DECON, which has attracted the attention of operators of light-water reactors. (iv) Steam Generator Corrosion: mathematical modelling of the water chemistry in the bulk and crevice regions of nuclear steam generators, supported by chemical experiments, has shown why sea water ingress from leaking condensers can be damaging, and has provided a rapid way to evaluate alternative boiler water chemistries. (v) Automatic Control of Feedwater Chemistry: on-line automatic chemical analysis and computer control of feedwater chemistry provides All Volatile Treatment for normal operation with pure feedwater, and carefully controlled sodium phosphate addition when there is detectable sea-water ingress from leaking condensers. (author)

  13. Assessment of System Behavior and Actions Under Loss of Electric Power For CANDU

    Energy Technology Data Exchange (ETDEWEB)

    Kang, San Ha; Moon, Bok Ja; Kim, Seoung Rae [Nuclear Engineering Service and Solution Co., Ltd., Daejeon (Korea, Republic of)

    2014-05-15

    For the analysis, the CANDU-6 plant in Korea is considered and only the passive components are operable. The other systems are assumed to be at failed condition due to the loss of electric power. At this accident, only the inventories remained in the primary heat transport system (PHTS) and steam generator can be used for the decay heat removal. Due to the transfer of decay heat, the inventory of steam generator secondary side is discharged to the air through passive operation of main steam safety valves (MSSVs). After the steam generators are dried, the PHTS is over-pressurized and the coolant is discharged to fuelling machine vault through passive operation of degasser condenser tank relief valves (DCRVs). Under this situation, the maintenance of the integrity of PHTS is important for the protection of radionuclides release to the environment. Thus, deterministic analysis using CATHENA code is carried out for the simulation of the accident and the appropriate operator action is considered. The loss of electric power results in the depletion of steam generator inventory which is necessary for the decay heat removal. If only the passive system is credited, the PT can be failed after the steam generator is depleted. For the prevention of the PT failure, the feedwater should be supplied to the steam generator before 4,800s after the accident. The feedwater can be supplied using water in dousing tank if the steam generators are depressurized. The decay heat from the core is removed through natural circulation if the feedwater can be supplied continuously.

  14. Life extension, power upgrade, and return to service work for Pickering NGS and other PWR and CANDU plants

    International Nuclear Information System (INIS)

    Millman, J.; Idvorian, N.; Schneider, W.

    2002-01-01

    Work on life extension, power upgrade and return to service has been performed and is in progress for a number of PWR and CANDU plants. For PWR plants, power upgrade work has been done for the new replacement steam generators in several cases. This work consists of redoing the formal equipment qualification analysis and reports for the uprated operating conditions to support the application for license adjustment. Life extension assessments have been performed for several CANDU plants. These are highly detailed assessments in which the particular steam generator is reassessed part by part as to the ability of each to sustain full life operation and also extended life operation. Return to service work for Pickering NGSA specifically has included this type of assessment and also specific repair, cleaning and retrofit activities including secondary side inspection, waterlancing, divider plate repair, eddy current inspection, etc. Steam generator modifications and retrofit work have been performed in a number of cases. The paper discusses various life extension, power upgrade, equipment modification and return to service activities all of which are part of the renewed drive in the industry to realise the full potential of nuclear plants by getting more and better performance from the extended service of existing plants. (author)

  15. Steam generator operation and maintenance

    International Nuclear Information System (INIS)

    Lee, C.K.

    2004-01-01

    Corrosion of steam generator tube has resulted in the need for extensive repair and replacement of steam generators. Over the past two decades, steam generator problems in the United States were viewed to be one of the most significant contributor to lost generation in operating PWR plants. When the SGOG-I (Steam Generator Owners Groups) was formed in early 1977, denting was responsible for almost 90% of the tube plugging. By the end of 1982, this figure was reduced to less than 2%. During the existence of SGOG-II (from 1982 to 1986), IGA/SCC (lntergranular Attack/Stress Corrosion Cracking) in the tube sheet, primary side SCC, pitting, and fretting surfaced as the primary causes of tube degradation. Although significant process has been made with wastage and denting, the utilities experience shows that the percentage of reactors plugging tubes and the percentage of tubes being plugged each year has remained relatively constant. The diversity of the damage mechanisms means that no one solution is likely to resolve all problems. The task of maintaining steam generator integrity continues to be formidable and challenging. As the older problems were brought under control, many new problems emerged. SGOG-II (Steam Generator Owners Group program from 1982 to 1986) has focused on these problem areas such as tube stress corrosion cracking (SCC) and intergranular attack (IGA) in the open tube sheet crevice, primary side tube cracking, pitting in the lower span, and tube fretting in preheated section and anti-vibration bar (AVB) locations. Primary Water Stress Corrosion Cracking (PWSCC) in the tube to tubesheet roll transition has been a wide spread problem in the Recirculation Steam Generators (RSG) during this period. Although significant progress has been made in resolving this problem, considerable work still remains. One typical problem in the Once Through Steam Generator (OTSG) was the tube support plate broached hole fouling which affects the OTSG steam generating

  16. Options for Steam Generator Decommissioning

    International Nuclear Information System (INIS)

    Krause, Gregor; Amcoff, Bjoern; Robinson, Joe

    2016-01-01

    Selecting the best option for decommissioning steam generators is a key consideration in preparing for decommissioning PWR nuclear power plants. Steam Generators represent a discrete waste stream of large, complex items that can lend themselves to a variety of options for handling, treatment, recycling and disposal. Studsvik has significant experience in processing full size Steam Generators at its metal recycling facility in Sweden, and this paper will introduce the Studsvik steam generator treatment concept and the results achieved to date across a number of projects. The paper will outline the important parameters needed at an early stage to assess options and to help consider the balance between off-site and on-site treatment solutions, and the role of prior decontamination techniques. The paper also outlines the use of feasibility studies and demonstration projects that have been used to help customers prepare for decommissioning. The paper discusses physical, radiological and operational history data, Pro and Contra factors for on- and off-site treatment, the role of chemical decontamination prior to treatment, planning for off-site shipments as well as Studsvik experience This paper has an original focus upon the coming challenges of steam generator decommissioning and potential external treatment capacity constraints in the medium term. It also focuses on the potential during operations or initial shut-down to develop robust plans for steam generator management. (authors)

  17. Effect of lead and silicon on localized corrosion of Alloy 800 in steam generator crevice environments

    International Nuclear Information System (INIS)

    Lu, Y.C.; Wright, M.D.; Cleland, R.D.

    2001-09-01

    The Alloy 800 tubes used in CANDU 6 steam generators have not experienced significant corrosion damage to date, which may be attributed to successful water chemistry control strategies. However, it is known that Alloy 800, like other steam generator (SG) tubing materials, is not immune to corrosion, especially pitting, under some plausible but off-specification operating scenarios. Electrochemical measurements provide information on corrosion susceptibility and rate, which are known to be a function of water chemistry. Using laboratory data in combination with chemistry monitoring and diagnostic software it is possible to assess the impact of plant operating conditions on SG tube corrosion for plant life management (PLIM). In this context, this paper discusses the results of electrochemical measurements made to elucidate the corrosion behaviour of Alloy 800 SG tubes under conditions simulating those plausible in SG crevices. In addition to crevice pH, the influence of PbO, acting alone or in combination with SiO 2 , on localized corrosion such as pitting or stress corrosion-cracking (SCC) was determined. Possible transient chemistry regimes that could significantly shorten expected tube lifetimes have been identified from the data analysis. Of equal significance, the results also support the position that under normal, near neutral pH and low dissolved oxygen conditions, pitting and cracking of Alloy 800 steam generator tubing will not be initiated. (author)

  18. Thermal stability of chloroform in the steam condensate cycle of CANDU-PHW nuclear power plant

    International Nuclear Information System (INIS)

    Lepine, Louis; Gilbert, Roland; Ouellet, Lorenzo

    1992-01-01

    Analysis of samples taken at the Gentilly 2 (Quebec) CANDU-PHW (CANadian Deuterium Uranium - Pressurized Heavy Water) plant after chlorination and demineralization revealed the presence of all four trihalomethanes (THMs) (CHCl 3 , CHBrCl 2 , CHBr 2 Cl and CHBr 3 ) and other unidentified halogenated volatile compounds. Among the THMs, chloroform was the major contaminant. A study of its thermal stability in water at different temperatures confirmed the degradation of the CHCl 3 molecule according to the equation CHCl 3 + H2O → CO + 3 HCl. The reaction follows first order kinetics and has an activation energy of 100 kJ/mol. The estimated half-life is six seconds at 260 deg C, the maximum temperature of the steam condensate cycle

  19. Liquid metal steam generator

    International Nuclear Information System (INIS)

    Wolowodiuk, W.

    1975-01-01

    A liquid metal heated steam generator is described which in the event of a tube failure quickly exhausts out of the steam generator the products of the reaction between the water and the liquid metal. The steam is generated in a plurality of bayonet tubes which are heated by liquid metal flowing over them between an inner cylinder and an outer cylinder. The inner cylinder extends above the level of liquid metal but below the main tube sheet. A central pipe extends down into the inner cylinder with a centrifugal separator between it and the inner cylinder at its lower end and an involute deflector plate above the separator so that the products of a reaction between the liquid metal and the water will be deflected downwardly by the deflector plate and through the separator so that the liquid metal will flow outwardly and away from the central pipe through which the steam and gaseous reaction products are exhausted. (U.S.)

  20. Circumferential cracking of steam generator tubes

    International Nuclear Information System (INIS)

    Karwoski, K.J.

    1997-04-01

    On April 28, 1995, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 95-03, open-quote Circumferential Cracking of Steam Generator Tubes.close-quote GL 95-03 was issued to obtain information needed to verify licensee compliance with existing regulatory requirements regarding the integrity of steam generator tubes in domestic pressurized-water reactors (PWRs). This report briefly describes the design and function of domestic steam generators and summarizes the staff's assessment of the responses to GL 95-03. The report concludes with several observations related to steam generator operating experience. This report is intended to be representative of significant operating experience pertaining to circumferential cracking of steam generator tubes from April 1995 through December 1996. Operating experience prior to April 1995 is discussed throughout the report, as necessary, for completeness

  1. Steam generator sludge removal apparatus

    International Nuclear Information System (INIS)

    Schafer, B.W.; Werner, C.E.; Klahn, F.C.

    1992-01-01

    The present invention relates to equipment for cleaning steam generators and in particular to a high pressure fluid lance for cleaning sludge off the steam generator tubes away from an open tube lane. 6 figs

  2. Advanced technologies on steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Sakata, Kaoru; Nakamura, Yuuki [Mitsubishi Heavy Industry Co., Takasago (Japan); Nakamori, Nobuo; Mizutani, Toshiyuki; Uwagawa, Seiichi; Saito, Itaru [Mitsubishi Heavy Industry Co., Kobe (Japan); Matsuoka, Tsuyoshi [Mitsubishi Heavy Industry Co., Yokohama (Japan)

    1997-12-31

    The thermal-hydraulic tests for a horizontal steam generator of a next-generation PWR (New PWR-21) were performed. The purpose of these tests is to understand the thermal-hydraulic behavior in the secondary side of horizontal steam generator during the plant normal operation. A test was carried out with cross section slice model simulated the straight tube region. In this paper, the results of the test is reported, and the effect of the horizontal steam generator internals on the thermalhydraulic behavior of the secondary side and the circulation characteristics of the secondary side are discussed. (orig.). 3 refs.

  3. Advanced technologies on steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Sakata, Kaoru; Nakamura, Yuuki [Mitsubishi Heavy Industry Co., Takasago (Japan); Nakamori, Nobuo; Mizutani, Toshiyuki; Uwagawa, Seiichi; Saito, Itaru [Mitsubishi Heavy Industry Co., Kobe (Japan); Matsuoka, Tsuyoshi [Mitsubishi Heavy Industry Co., Yokohama (Japan)

    1998-12-31

    The thermal-hydraulic tests for a horizontal steam generator of a next-generation PWR (New PWR-21) were performed. The purpose of these tests is to understand the thermal-hydraulic behavior in the secondary side of horizontal steam generator during the plant normal operation. A test was carried out with cross section slice model simulated the straight tube region. In this paper, the results of the test is reported, and the effect of the horizontal steam generator internals on the thermalhydraulic behavior of the secondary side and the circulation characteristics of the secondary side are discussed. (orig.). 3 refs.

  4. Steam generating system in LMFBR type reactors

    International Nuclear Information System (INIS)

    Kurosawa, Katsutoshi.

    1984-01-01

    Purpose: To suppress the thermal shock loads to the structures of reactor system and secondary coolant system, for instance, upon plant trip accompanying turbine trip in the steam generation system of LMFBR type reactors. Constitution: Additional feedwater heater is disposed to the pipeway at the inlet of a steam generator in a steam generation system equipped with a closed loop extended from a steam generator by way of a gas-liquid separator, a turbine and a condensator to the steam generator. The separated water at high temperature and high pressure from a gas-liquid separator is heat exchanged with coolants flowing through the closed loop of the steam generation system in non-contact manner and, thereafter, introduced to a water reservoir tank. This can avoid the water to be fed at low temperature as it is to the steam generator, whereby the thermal shock loads to the structures of the reactor system and the secondary coolant system can be suppressed. (Moriyama, K.)

  5. Thermal hydraulic studies in steam generator test facility

    International Nuclear Information System (INIS)

    Vinod, V.; Suresh Kumar, V.A.; Noushad, I.B.; Ellappan, T.R.; Rajan, K.K.; Rajan, M.; Vaidyanathan, G.

    2005-01-01

    Full text of publication follows: A 500 MWe fast breeder reactor is being constructed at Kalpakkam, India. This is a sodium cooled reactor with two primary and two secondary sodium loops with total 8 steam generators. The typical advantage of fast breeder plants is the high operating temperature of steam cycles and the high plant efficiency. To produce this high pressure and high temperature steam, once through straight tube vertical sodium heated steam generators are used. The steam is generated from the heat produced in the reactor core and being transported through primary and secondary sodium circuits. The steam generator is a 25 m high middle supported steam generator with expansion bend and 23 m heat transfer length. Steam Generator Test Facility (SGTF) constructed at Indira Gandhi Centre for Atomic Research (IGCAR), Kalpakkam aims at performing various tests on a 5.5 MWt steam generator. This vertically simulated test article is similar in all respects to the proposed 157 MWt steam generator module for the Prototype Fast Breeder Reactor (PFBR), with reduced number of tubes. Heat transfer performance tests are done with this 19 tube steam generator at various load conditions. Sodium circuit for the SGTF is equipped with oil fired heater as heat source and centrifugal sodium pump, to pump sodium at 105 m 3 /hr flow rate. Other typical components like sodium to air heat exchanger, sodium purification system and hydrogen leak detection system is also present in the sodium circuit. High pressure steam produced in the steam generator is dumped in a condenser and recycled. Important tests planned in SGTF are the heat transfer performance test, stability test, endurance test and performance test of steam generator under various transients. The controlled operation of steam generator will be studied with possible control schemes. A steady state simulation of the steam generator is done with a mathematical model. This paper gives the details of heat transfer

  6. CANDU operating experience

    International Nuclear Information System (INIS)

    McConnell, L.G.; Woodhead, L.W.; Fanjoy, G.R.

    1982-03-01

    The CANDU Pressurized Heavy Water (CANDU-PHW) type of nuclear electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This paper highlights Ontario Hydro's operating experience using the CANDU-PHW system, with a focus on the operating performance and costs, reliability of system components and nuclear safety considerations both to the workers and the public

  7. Advanced CANDU reactors

    International Nuclear Information System (INIS)

    Dunn, J.T.; Finlay, R.B.; Olmstead, R.A.

    1988-12-01

    AECL has undertaken the design and development of a series of advanced CANDU reactors in the 700-1150 MW(e) size range. These advanced reactor designs are the product of ongoing generic research and development programs on CANDU technology and design studies for advanced CANDU reactors. The prime objective is to create a series of advanced CANDU reactors which are cost competitive with coal-fired plants in the market for large electricity generating stations. Specific plant designs in the advanced CANDU series will be ready for project commitment in the early 1990s and will be capable of further development to remain competitive well into the next century

  8. Steam generator tube rupture (SGTR) scenarios

    International Nuclear Information System (INIS)

    Auvinen, A.; Jokiniemi, J.K.; Laehde, A.; Routamo, T.; Lundstroem, P.; Tuomisto, H.; Dienstbier, J.; Guentay, S.; Suckow, D.; Dehbi, A.; Slootman, M.; Herranz, L.; Peyres, V.; Polo, J.

    2005-01-01

    The steam generator tube rupture (SGTR) scenarios project was carried out in the EU 5th framework programme in the field of nuclear safety during years 2000-2002. The first objective of the project was to generate a comprehensive database on fission product retention in a steam generator. The second objective was to verify and develop predictive models to support accident management interventions in steam generator tube rupture sequences, which either directly lead to severe accident conditions or are induced by other sequences leading to severe accidents. The models developed for fission product retention were to be included in severe accident codes. In addition, it was shown that existing models for turbulent deposition, which is the dominating deposition mechanism in dry conditions and at high flow rates, contain large uncertainties. The results of the project are applicable to various pressurised water reactors, including vertical steam generators (western PWR) and horizontal steam generators (VVER)

  9. Cleanliness criteria to improve steam generator performance

    International Nuclear Information System (INIS)

    Schwarz, T.; Bouecke, R.; Odar, S.

    2005-01-01

    High steam generator performance is a prerequisite for high plant availability and possible life time extension. The major opponent to that is corrosion and fouling of the heating tubes. Such steam generator degradation problems arise from the continuous ingress of non-volatile contaminants, i.e. corrosion products and salt impurities may accumulate in the steam generators. These impurities have their origin in the secondary side systems. The corrosion products generally accumulate in the steam generators and form deposits not only in the flow restricted areas, such as on top of tube sheet and tube support structure, but also build scales on the steam generator heating tubes. In addition, the tube scales in general affect the steam generator thermal performance, which ultimately causes a reduction of power output. The most effective ways of counteracting all these degradation problems, and thus of improving the steam generator performance is to keep them in clean conditions or, if judged necessary, to plan cleaning measures such as mechanical tube sheet lancing or chemical cleaning. This paper presents a methodology how to assess the cleanliness condition of a steam generator by bringing together all available operational and inspection data such as thermal performance and water chemistry data. By means of this all-inclusive approach the cleanliness condition is quantified in terms of a fouling index. The fouling index allows to monitor the condition of a specific steam generator, compare it to other plants and, finally, to serve as criterion for cleaning measures such as chemical cleaning. The application of the cleanliness criteria and the achieved field results with respect to improvements of steam generator performance will be presented. (author)

  10. Corrosion Evaluation and Corrosion Control of Steam Generators

    International Nuclear Information System (INIS)

    Maeng, W. Y.; Kim, U. C.; Sung, K. W.; Na, J. W.; Lee, Y. H.; Lee, D. H.; Kim, K. M.

    2008-06-01

    Corrosion damage significantly influences the integrity and efficiency of steam generator. Corrosion problems of steam generator are unsolved issues until now even though much effort is made around world. Especially the stress corrosion cracking of heat exchange materials is the first issue to be solved. The corrosion protection method of steam generator is important and urgent for the guarantee of nuclear plant's integrity. The objectives of this study are 1) to evaluate the corrosion properties of steam generator materials, 2) to optimize the water chemistry of steam generator and 3) to develop the corrosion protection method of primary and secondary sides of steam generator. The results will be reflected to the water chemistry guideline for improving the integrity and efficiency of steam generator in domestic power plants

  11. Thermal performances of molten salt steam generator

    International Nuclear Information System (INIS)

    Yuan, Yibo; He, Canming; Lu, Jianfeng; Ding, Jing

    2016-01-01

    Highlights: • Thermal performances of molten salt steam generator were experimentally studied. • Overall heat transfer coefficient reached maximum with optimal molten salt flow rate. • Energy efficiency first rose and then decreased with salt flow rate and temperature. • Optimal molten salt flow rate and temperature existed for good thermal performance. • High inlet water temperature benefited steam generating rate and energy efficiency. - Abstract: Molten salt steam generator is the key technology for thermal energy conversion from high temperature molten salt to steam, and it is used in solar thermal power station and molten salt reactor. A shell and tube type molten salt steam generator was set up, and its thermal performance and heat transfer mechanism were studied. As a coupling heat transfer process, molten salt steam generation is mainly affected by molten salt convective heat transfer and boiling heat transfer, while its energy efficiency is also affected by the heat loss. As molten salt temperature increased, the energy efficiency first rose with the increase of heat flow absorbed by water/steam, and then slightly decreased for large heat loss as the absorbed heat flow still rising. At very high molten salt temperature, the absorbed heat flow decreased as boiling heat transfer coefficient dropping, and then the energy efficiency quickly dropped. As the inlet water temperature increased, the boiling region in the steam generator remarkably expanded, and then the steam generation rate and energy efficiency both rose with the overall heat transfer coefficient increasing. As the molten salt flow rate increased, the wall temperature rose and the boiling heat transfer coefficient first increased and then decreased according to the boiling curve, so the overall heat transfer coefficient first increased and then decreased, and then the steam generation rate and energy efficiency of steam generator both had maxima.

  12. Basic research and industrialization of CANDU advanced fuel

    Energy Technology Data Exchange (ETDEWEB)

    Chun, Suk Ho; Park, Joo Hwan; Jun, Ji Su [and others

    2000-04-01

    Wolsong Unit 1 as the first heavy water reactor in Korea has been in service for 17 years since 1983. It would be about the time to prepare a plan for the solution of problems due to aging of the reactor. The aging of CANDU reactor could lead especially to the steam generator cruding and pressure tube sagging and creep and then decreases the operation margin to make some problems on reactor operations and safety. The counterplan could be made in two ways. One is to repair or modify reactor itself. The other is to develop new advanced fuel to increase of CANDU operation margin effectively, so as to compensate the reduced operation margin. Therefore, the first objectives in the present R and D is to develop the CANFLEX-NU (CANDU Flexible fuelling-Natural Uranium) fuel as a CANDU advanced fuel. The second objectives is to develop CANDU advanced fuel bundle to utilize advanced fuel cycles such as recovered uranium, slightly enriched uranium, etc. and so to raise adaptability for change in situation of uranium market. Also, it is to develop CANDU advanced fuel technology which improve uranium utilization to cope with a world-wide imbalance between uranium supply and demand, without significant modification of nuclear reactor design and refuelling strategies. As the implementations to achieve the above R and D goal, the work contents and scope of technology development of CANDU advanced fuel using natural uranium (CANFLEX-NU) are the fuel element/bundle designs, the nuclear design and fuel management analysis, the thermalhydraulic analysis, the safety analysis, fuel fabrication technologies, the out-pile thermalhydraulic test and in-pile irradiation tests performed. At the next, the work scopes and contents of feasibility study of CANDU advanced fuel using recycled uranium (CANFLEX-RU) are the fuel element/bundle designs, the reactor physics analysis, the thermalhydraulic analysis, the basic safety analysis of a CANDU-6 reactor with CANFLEX-RU fuel, the fabrication and

  13. Basic research and industrialization of CANDU advanced fuel

    International Nuclear Information System (INIS)

    Chun, Suk Ho; Park, Joo Hwan; Jun, Ji Su

    2000-04-01

    Wolsong Unit 1 as the first heavy water reactor in Korea has been in service for 17 years since 1983. It would be about the time to prepare a plan for the solution of problems due to aging of the reactor. The aging of CANDU reactor could lead especially to the steam generator cruding and pressure tube sagging and creep and then decreases the operation margin to make some problems on reactor operations and safety. The counterplan could be made in two ways. One is to repair or modify reactor itself. The other is to develop new advanced fuel to increase of CANDU operation margin effectively, so as to compensate the reduced operation margin. Therefore, the first objectives in the present R and D is to develop the CANFLEX-NU (CANDU Flexible fuelling-Natural Uranium) fuel as a CANDU advanced fuel. The second objectives is to develop CANDU advanced fuel bundle to utilize advanced fuel cycles such as recovered uranium, slightly enriched uranium, etc. and so to raise adaptability for change in situation of uranium market. Also, it is to develop CANDU advanced fuel technology which improve uranium utilization to cope with a world-wide imbalance between uranium supply and demand, without significant modification of nuclear reactor design and refuelling strategies. As the implementations to achieve the above R and D goal, the work contents and scope of technology development of CANDU advanced fuel using natural uranium (CANFLEX-NU) are the fuel element/bundle designs, the nuclear design and fuel management analysis, the thermalhydraulic analysis, the safety analysis, fuel fabrication technologies, the out-pile thermalhydraulic test and in-pile irradiation tests performed. At the next, the work scopes and contents of feasibility study of CANDU advanced fuel using recycled uranium (CANFLEX-RU) are the fuel element/bundle designs, the reactor physics analysis, the thermalhydraulic analysis, the basic safety analysis of a CANDU-6 reactor with CANFLEX-RU fuel, the fabrication and

  14. Testing installation for a steam generator

    International Nuclear Information System (INIS)

    Dubourg, M.

    1985-01-01

    The invention proposes a testing installation for a steam generator associated to a boiler, comprising a testing exchanger connected to a feeding circuit in secondary fluid and to a circuit to release the steam produced, and comprising a heating-tube bundle connected to a closed circuit of circulation of a primary coolant at the same temperature and at the pressure than the primary fluid. The heating-tube bundle of the testing exchanger has the same height than the primary bundle of the steam generator and the testing exchanger is at the same level and near the steam generator and is fed by the same secondary fluid such as it is subject to the same operation phases during a long period. The in - vention applies, more particularly, to the steam generators of pressurized water nuclear power plants [fr

  15. Corrosion Evaluation and Corrosion Control of Steam Generators

    Energy Technology Data Exchange (ETDEWEB)

    Maeng, W. Y.; Kim, U. C.; Sung, K. W.; Na, J. W.; Lee, Y. H.; Lee, D. H.; Kim, K. M

    2008-06-15

    Corrosion damage significantly influences the integrity and efficiency of steam generator. Corrosion problems of steam generator are unsolved issues until now even though much effort is made around world. Especially the stress corrosion cracking of heat exchange materials is the first issue to be solved. The corrosion protection method of steam generator is important and urgent for the guarantee of nuclear plant's integrity. The objectives of this study are 1) to evaluate the corrosion properties of steam generator materials, 2) to optimize the water chemistry of steam generator and 3) to develop the corrosion protection method of primary and secondary sides of steam generator. The results will be reflected to the water chemistry guideline for improving the integrity and efficiency of steam generator in domestic power plants.

  16. An expert system for steam generator maintenance

    International Nuclear Information System (INIS)

    Remond, A.

    1988-01-01

    The tube bundles in PWR steam generators are, by far, the major source of problems whether they are due to primary and secondary side corrosion mechanisms or to tube vibration-induced wear at tube support locations. Because of differences in SG operating, materials, and fabrication processes, the damage may differ from steam generator to steam generator. MPGV, an expert system for steam generator maintenance uses all steam generator data containing data on materials, fabrication processes, inservice inspection, and water chemistry. It has access to operational data for individual steam generators and contains models of possible degradation mechanisms. The objectives of the system are: · Diagnosing the most probable degradation mechanism or mechanisms by reviewing the entire steam generator history. · Identifying the tubes most exposed to future damage and evaluating the urgency of repair by simulating the probable development of the problem in time. · Establishing the appropriate preventive actions such as repair, inspection or other measures and establishing an action schedule. The system is intended for utilities either for individual plants before each inspection outage or any time an incident occurs or for a set of plants through a central MPGV center. (author)

  17. Moisture separator for steam generator level measurement system

    International Nuclear Information System (INIS)

    Cantineau, B.J.

    1987-01-01

    A steam generator level measurement system having a reference leg which is kept full of water by a condensation pot, has a liquid/steam separator in the connecting line between the condensation pot and the steam phase in the steam generator to remove excess liquid from the steam externally of the steam generator. This ensures that the connecting line does not become blocked. The separator pot has an expansion chamber which slows down the velocity of the steam/liquid mixture to aid in separation, and a baffle, to avoid liquid flow into the line connected to the condensate pot. Liquid separated is returned to the steam generator below the water level through a drain line. (author)

  18. Passive system with steam-water injector for emergency supply of NPP steam generators

    International Nuclear Information System (INIS)

    Il'chenko, A.G.; Strakhov, A.N.; Magnitskij, D.N.

    2009-01-01

    The calculation results of reliability indicators of emergency power supply system and emergency feed-water supply system of serial WWER-1000 unit are presented. To ensure safe water supply to steam generators during station blackout it was suggested using additional passive emergency feed-water system with a steam-water injector working on steam generators dump steam. Calculated analysis of steam-water injector operating capacity was conducted at variable parameters of steam at the entrance to injector, corresponding to various moments of time from the beginning of steam-and-water damping [ru

  19. Qualification of FFA treatment for the water-steam cycle as an innovative lay-up strategy for the long term outage of a CANDU-6 reactor

    International Nuclear Information System (INIS)

    Ramminger, Ute; Fandrich, Jörg; Sainz, Ricardo; Ovando, Luis; Herrera, Cecilia; Mendizabal, Maribel; Dumon, Adriana; Chocron, Mauricio

    2014-01-01

    The majority of worldwide operating Nuclear Power Plants is older than 25 years, which is accompanied with extended outage duration due to large refurbishment and upgrade programs, e.g. Steam Generator Replacement and other large component replacement. For these long term outages adequate and cost effective preservation methods are required. Normally during outages, systems and components are drained and opened to atmosphere whereas wet surfaces and moisture condensation can result in uniform corrosion of carbon steel and eventually other materials; superimposed localized corrosion is possible in presence of impurities. For those systems there are in general two different lay-up methods possible. Dry lay-up by removing all water and humidity from the components or wet lay-up with demineralized and oxygen free water and additional corrosion inhibitors. Disadvantages of these lay-up methods are: High man power and hardware efforts for performing dry lay-up. Usage of hazardous chemicals like Hydrazine. Insufficient results of both lay-up methods in case of switching between dry and wet lay-up. To improve the lay-up concept for long term outages, AREVA GmbH developed an innovative concept using FFA (Film-Forming Amines) for secondary side system lay-up. The entire water-steam cycle including the Steam Generators is treated in one step without any negative impact on the treated structural materials. This technology has been applied for the first time at NPP Embalse. Embalse Nuclear Power Station consists of a CANDU-6 reactor of 648 MWe electrical output. It is in commercial operation since 1984. The shutdown for refurbishment and preparation for the second cycle of operation that includes among other tasks the replacement of the existing steam generators and power uprating has been scheduled for 2014, which causes the necessity of a lay-up optimization in the plant. This paper deals in detail with the qualification process of the FFA treatment considering the specifics

  20. The CANDU 80

    International Nuclear Information System (INIS)

    Hart, R.S.

    1998-01-01

    AECL has completed the conceptual design of a small CANDU plant with an output, in the range of 300 MWth (called the CANDU 80), suitable for a variety of electrical and co-generation applications including desalination, oil sands oil extraction and processing, and the provision of electricity and heat to areas with low demand. This paper provides a brief overview of the CANDU 80, and discusses key features contributing to safety and operational margins

  1. Steam generator life cycle management: Ontario Power Generation (OPG) experience

    International Nuclear Information System (INIS)

    Maruska, C.C.

    2002-01-01

    A systematic managed process for steam generators has been implemented at Ontario Power Generation (OPG) nuclear stations for the past several years. One of the key requirements of this managed process is to have in place long range Steam Generator Life Cycle Management (SG LCM) plans for each unit. The primary goal of these plans is to maximize the value of the nuclear facility through safe and reliable steam generator operation over the expected life of the units. The SG LCM plans integrate and schedule all steam generator actions such as inspection, operation, maintenance, modifications, repairs, assessments, R and D, performance monitoring and feedback. This paper discusses OPG steam generator life cycle management experience to date, including successes, failures and how lessons learned have been re-applied. The discussion includes relevant examples from each of the operating stations: Pickering B and Darlington. It also includes some of the experience and lessons learned from the activities carried out to refurbish the steam generators at Pickering A after several years in long term lay-up. The paper is structured along the various degradation modes that have been observed to date at these sites, including monitoring and mitigating actions taken and future plans. (author)

  2. Non-polluting steam generators with fluidized-bed furnaces

    Energy Technology Data Exchange (ETDEWEB)

    Brandes, H [Deutsche Babcock A.G., Oberhausen (Germany, F.R.)

    1979-07-01

    The author reports on a 35 MW steam generator with hard coal fluidized-bed furnace a planned 35 MW steam generator with flotation-dirt fluidized-bed furnace, and on planned steam generators for fluidized-bed firing of hard coal up to a steam power of about 200 MW.

  3. CAREM-25 Steam Generator Stability Analysis

    International Nuclear Information System (INIS)

    Rabiti, A.; Delmastro, D.

    2003-01-01

    In this work the stability of a once-through CAREM-25 steam generator is analyzed.A fix nodes numerical model, that allows the modelling of the liquid, two-phase and superheated steam zones, is implemented.This model was checked against a mobile finite elements model under saturated steam conditions at the channel exit and a good agreement was obtained.Finally the stability of a CAREM steam generator is studied and the range of in let restrictions that a assure the system stability is analyzed

  4. X-rays diffraction characterization of corrosion products transported by secondary side of a CANDU NPP

    International Nuclear Information System (INIS)

    Dinu, A.; Tunaru, M.; Velciu, L.

    2016-01-01

    To verify the chemistry of secondary side of CANDU steam generators, Millipore filters are used to sampling from condensing extraction pump, from feed water header and blow down of steam generator. These filters retain the corrosion products as very fine particles and are used as samples in chemistry water control. X-Ray diffraction technique is the able to distinguish the different crystallographic compounds present in oxide films deposited on the Millipore filters and gives information referring to the nature of corrosion products transported in secondary side. The XRD analysis has identified the following substance in deposited layer: magnetite (Fe_3O_4), hematite (Fe_2O_3), and iron oxide hydroxide (FeOOH). By optical microscopy it was observed a brown-reddish background specific to hematite and iron oxide hydroxide, especially for filters extracted from condensing extraction pump. The black colour of crud present on filters extracted from feed water header and blow down of steam generator shows the presence of magnetite. (authors)

  5. Steam generators

    International Nuclear Information System (INIS)

    Hayden, R.L.J.

    1979-01-01

    Steam generators for nuclear reactors are designed so that deposition of solids on the surface of the inlet side of the tubesheet or the inlet header with the consequent danger of corrosion and eventual tube failure is obviated or substantially reduced. (U.K.)

  6. Define optimal conditions for steam generator tube integrity and an extended steam generator service life

    International Nuclear Information System (INIS)

    Lu, Y.C.

    2007-01-01

    Steam generator (SG) tubing materials are susceptible to corrosion degradation in certain electrochemical corrosion potential regions in the presence of some aggressive ions. Because of the hideout of impurities, the local chemistry conditions in areas under sludge and inside SG crevices may be very aggressive with high concentrations of chlorides and other impurities. These areas are the locations where SG tubing materials are susceptible to degradation such as pitting, crevice corrosion, intergranular attack (IGA) and stress corrosion cracking (SCC). The corrosion susceptibility of each SG alloy is different and is a function of the electrochemical corrosion potential (ECP) and chemical environment. Electrochemical corrosion behaviors of major SG tube alloys were studied under some plausible aggressive crevice chemistry conditions. The possible hazardous conditions leading to SG tube degradation and the conditions, which can minimize SG tube degradation have been determined. Optimal operating conditions in the form of a 'Recommended ECP/pH zone' for minimizing corrosion degradation have been defined for all major SG tube materials, including Alloys 600, 800, 690 and 400, under CANDU SG operating and startup conditions. SCC tests and accelerated corrosion tests were carried out to verify and revise the recommended ECP/pH zones. This information is being incorporated into ChemAND, a system health monitor for plant chemistry management developed by AECL, which alloys utilities to evaluate the status of the SG alloys and to minimize SG material degradation by appropriate SG water chemistry management. (author)

  7. Failure analysis of retired steam generator tubings

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Hong Pyo; Kim, J. S.; Hwang, S. S. and others

    2005-04-15

    Degradation of steam generator leads to forced outage and extension of outage, which causes increase in repair cost, cost of purchasing replacement power and radiation exposure of workers. Steam generator tube rupture incident occurred in Uljin 4 in 2002, which made public sensitive to nuclear power plant. To keep nuclear energy as a main energy source, integrity of steam generator should be demonstrated. Quantitative relationship between ECT(eddy current test) signal and crack size is needed in assesment of integrity of steam generator in pressurized water reactor. However, it is not fully established for application in industry. Retired steam generator of Kori 1 has many kinds of crack such as circumferential and axial primary water stress corrosion crack and outer diameter stress corrosion crack(ODSCC). So, it can be used in qualifying and improving ECT technology and in condition monitoring assesment for crack detected in ISI(in service inspection). In addition, examination of pulled tube of Kori 1 retired steam generator will give information about effectiveness of non welded sleeving technology which was employed to repair defect tubes and remedial action which was applied to mitigate ODSCC. In this project, hardware such as semi hot lab. for pulled tube examination and modification transportation cask for pulled tube and software such as procedure of transportation of radioactive steam generator tube and non-destructive and destructive examination of pulled tube were established. Non-destructive and destructive examination of pulled tubes from Kori 1 retired steam generator were performed in semi hot lab. Remedial actions applied to Kori 1 retired steam generator, PWSCC trend and bulk water chemistry and crevice chemistry in Kori 1 were evaluated. Electrochemical decontamination technology for pulled tube was developed to reduce radiation exposure and enhance effectiveness of pulled tube examination. Multiparameter algorithm developed at ANL, USA was

  8. Thermosyphon Phenomenon as an alternate heat sink of Shutdown Cooling System for the CANDU reactor

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Jonghyun [GNEST, Seoul (Korea, Republic of); Lee, Kwangho; Oh, Haechol; Jun, Hwangyong [KEPRI, Taejon (Korea, Republic of)

    2006-07-01

    During the outage(overhaul) of the CANDU plant, there is a period when the coolant is partially drained to the reactor header level and the coolant is cooled and depressurized by Shutdown Cooling System(SDCS) other than PHTS pump. In the postulated accident of the loss of SDCS-the PHTS pump failure, the primary coolant system should be cooled by the alternate heat sink using the thermosyphon pheonomenon(TS) through the steam generator(SG) This study was aimed at verification and analyzing the core cooling ability of the TS. And the sensitivity analysis was done for the number of SGs used in the TS. As an analysis tool, RELAP5/CANDU was used.

  9. Darlington steam generator life assurance program

    International Nuclear Information System (INIS)

    Jelinski, E.; Dymarski, M.; Maruska, C.; Cartar, E.

    1995-01-01

    The Darlington Nuclear Generating Station belonging to Ontario Hydro is one of the most modern and advanced nuclear generating stations in the world. Four reactor units each generate 881 net MW, enough to provide power to a major city, and representing approximately 20% of the Ontario grid. The nuclear generating capacity in Ontario represents approximately 60% of the grid. In order to look after this major asset, many proactive preventative and predictive maintenance programs are being put in place. The steam generators are a major component in any power plant. World wide experience shows that nuclear steam generators require specialized attention to ensure reliable operation over the station life. This paper describes the Darlington steam generator life assurance program in terms of degradation identification, monitoring and management. The requirements for chemistry control, surveillance of process parameters, surveillance of inspection parameters, and the integration of preventative and predictive maintenance programs such as water lancing, chemical cleaning, RIHT monitoring, and other diagnostics to enhance our understanding of life management issues are identified and discussed. We conclude that we have advanced proactive activities to avoid and to minimize many of the problems affecting other steam generators. An effective steam generator maintenance program must expand the knowledge horizon to understand life limiting processes and to analyze and synthesize observations with theory. (author)

  10. Materials choices for the advanced LWR steam generators

    International Nuclear Information System (INIS)

    Paine, J.P.N.; Shoemaker, C.E.; McIlree, A.R.

    1987-01-01

    Current light water reactor (LWR) steam generators have been affected by a variety of corrosion and mechanical damage degradation mechanisms. Included are wear caused by tube vibration, intergranular corrosion, pitting, and thinning or wastage of the steam generator tubing and accelerated corrosion of carbon steel supports (denting). The Electric Power Research Institute (EPRI) and the Steam Generator Owners Groups (I, II) have sponsored laboratory and field studies to provide ameliorative actions for the majority of the damage forms experienced to date. Some of the current corrosion mechanisms are aggravated or caused by unique materials choices or materials interactions. New materials have been proposed and at least partially qualified for use in replacement model steam generators, including an advanced LWR design. In so far as possible, the materials choices for the advanced LWR steam generator avoid the corrosion pitfalls seemingly inherent in the current designs. The EPRI Steam Generator Project staff has recommended materials and design choices for a new steam generator. Based on these recommendations we believe that the advanced LWR steam generators will be much less affected by corrosion and mechanical damage mechanisms than are now experienced

  11. Steam generator operating experience update, 1982-1983

    International Nuclear Information System (INIS)

    Frank, L.

    1984-06-01

    This report is a continuation of earlier reports by the staff addressing pressurized water reactor steam generator operating experience. NUREG-0886, Steam Generator Tube Experience, published in February 1982 summarized experience in domestic and foreign plants through December 1981. This report summarizes steam generator operating experience in domestic plants for the years 1982 and 1983. Included are new problems encountered with secondary-side loose parts, sulfur-induced stress-assisted corrosion cracking, and flow-induced vibrational wear in the new preheater design steam generators. The status of Unresolved Safety Issues A3, A4, and A5 is also discussed

  12. Strategic maintenance plan for Cernavoda steam generators

    International Nuclear Information System (INIS)

    Cicerone, T.; Dhar, D.; VandenBerg, J.P.

    2002-01-01

    Steam generators are among the most important pieces of equipment in a nuclear power plant. They are required full time during the plant operation and obviously no redundancy exists. Past experience has shown that those utilities which implemented comprehensive steam generator inspection and maintenance programs and strict water chemistry controls, have had good steam generator performance that supports good overall plant performance. The purpose of this paper is to discuss a strategic Life Management and Operational-monitoring program for the Cernavoda steam generators. The program is first of all to develop a base of expertise for the management of the steam generator condition; and that is to be supported by a program of actions to be accomplished over time to assess their condition, to take measures to avoid degradation and to provide for inspections, cleaning and modifications as necessary. (author)

  13. Vertical steam generator

    International Nuclear Information System (INIS)

    Cuda, F.; Kondr, M.; Kresta, M.; Kusak, V.; Manek, O.; Turon, S.

    1982-01-01

    A vertical steam generator for nuclear power plants and dual purpose power plants consists of a cylindrical vessel in which are placed heating tubes in the form upside-down U. The heating tubes lead to the jacket of the cylindrical collector placed in the lower part of the steam generator perpendicularly to its vertical axis. The cylindrical collector is divided by a longitudinal partition into the inlet and outlet primary water sections of the heating tubes. One ends of the heating tube leads to the jacket of the collector for primary water feeding and the second ends of the heating tubes into the jacket of the collector which feeds and offtakes primary water from the heating tubes. (B.S.)

  14. Digital simulation for nuclear once-through steam generators

    International Nuclear Information System (INIS)

    Chen, A.T.

    1976-01-01

    Mathematical models for calculating the dynamic response of the Oconee type once through steam generator (OTSG) and the integral economizer once through steam generator (IEOTSG) was developed and presented in this dissertation. Linear and nonlinear models of both steam generator types were formulated using the state variable, lumped parameter approach. Transient and frequency responses of system parameters were calculated for various perturbations from both the primary coolant side and the secondary side. Transients of key parameters, including primary outlet temperature, superheated steam outlet temperature, boiling length/subcooled length and steam pressure, were generated, compared and discussed for both steam generator types. Frequency responses of delta P/sub s//deltaT/sub pin/ of the linear OTSG model were validated by using the dynamic testing results obtained at the Oconee I nuclear power station. A sensitivity analysis in both the time and the frequency domains was performed. It was concluded that the mathematical and computer models developed in this dissertation for both the OTSG and the IEOTSG are suitable for overall plant performance evaluation and steam generator related component/system design analysis for nuclear plants using either type of steam generator

  15. Steam Generator Tube Integrity Program: Surry Steam Generator Project, Hanford site, Richland, Benton County, Washington: Environmental assessment

    International Nuclear Information System (INIS)

    1980-03-01

    The US Nuclear Regulatory Commission (NRC) has placed a Nuclear Regulatory Research Order with the Richland Operations Office of the US Department of Energy (DOE) for expanded investigations at the DOE Pacific Northwest Laboratory (PNL) related to defective pressurized water reactor (PWR) steam generator tubing. This program, the Steam Generator Tube Integrity (SGTI) program, is sponsored by the Metallurgy and Materials Research Branch of the NRC Division of Reactor Safety Research. This research and testing program includes an additional task requiring extensive investigation of a degraded, out-of-service steam generator from a commercial nuclear power plant. This comprehensive testing program on an out-of-service generator will provide NRC with timely and valuable information related to pressurized water reactor primary system integrity and degradation with time. This report presents the environmental assessment of the removal, transport, and testing of the steam generator along with decontamination/decommissioning plans

  16. The casebook of technical presentation on a steam generator

    International Nuclear Information System (INIS)

    1986-05-01

    This casebook consists of seven presentations, which are measures and experience of maintenance of water quality in PWR generator, corrosion in steam generator, safely evaluation by management and closing in steam generator, testing of eddy current in steam generator, unsettled problems of safety in steam generator and maintenance of water quality in PWR generator.

  17. Model of reverse steam generator

    International Nuclear Information System (INIS)

    Malasek, V.; Manek, O.; Masek, V.; Riman, J.

    1987-01-01

    The claim of Czechoslovak discovery no. 239272 is a model designed for the verification of the properties of a reverse steam generator during the penetration of water, steam-water mixture or steam into liquid metal flowing inside the heat exchange tubes. The design may primarily be used for steam generators with a built-in inter-tube structure. The model is provided with several injection devices configured in different heat exchange tubes, spaced at different distances along the model axis. The design consists in that between the pressure and the circumferential casings there are transverse partitions and that in one chamber consisting of the circumferential casings, pressure casing and two adjoining partitions there is only one passage of the injection device through the inter-tube space. (Z.M.). 1 fig

  18. Development of a steam generator lancing system

    International Nuclear Information System (INIS)

    Jeong, Woo-Tae; Kim, Seok-Tae; Hong, Sung-Yull

    2006-01-01

    It is recommended to clean steam generators of nuclear power plants during plant outages. Under normal operations, sludge is created and constantly accumulates in the steam generators. The constituents of this sludge are different depending on each power plant characteristics. The sludge of the Kori Unit 1 steam generator, for example, was found to be composed of 93% ferrous oxide, 3% carbon and 1% of silica oxide and nickel oxide each. The research to develop a lancing system that would remove sludge deposits from the tubesheet of a steam generator was started in 1998 by the Korea Electric Power Research Institute (KEPRI) of the Korea Electric Power Corporation (KEPCO). The first commercial domestic lancing system in Korea, and KALANS-I Lancing System, was completed in 2000 for Kori Unit 1 for cleaning the tubesheet of its Westinghouse Delta-60 steam generator. Thereafter, the success of the development and site implementation of the KALANS-I lancing system for YGN Units 1 and 2 and Ulchin Units 3 and 4 was also realized in 2004 for sludge removal at those sites. The upper bundle cleaning system for Westinghouse model F steam generators is now under development

  19. Method to detect steam generator tube leakage

    International Nuclear Information System (INIS)

    Watabe, Kiyomi

    1994-01-01

    It is important for plant operation to detect minor leakages from the steam generator tube at an early stage, thus, leakage detection has been performed using a condenser air ejector gas monitor and a steam generator blow down monitor, etc. In this study highly-sensitive main steam line monitors have been developed in order to identify leakages in the steam generator more quickly and accurately. The performance of the monitors was verified and the demonstration test at the actual plant was conducted for their intended application to the plants. (author)

  20. Future aspects for liquid metal heated steam generators

    International Nuclear Information System (INIS)

    Jansing, W.; Ratzel, W.; Vinzens, K.

    1975-01-01

    The present status of steam generators is shown. The experience gained until now is expressed in form of basic points. The most important design criteria for steam generator systems are outlined. On the basis of these design criteria, two possible steam generator concepts are shown. Costs in relationship to the repair concepts of two modular steam generators (thermal output 156 and 625 MW) and a pool design of 625 MW are compared. (author)

  1. Future aspects for liquid metal heated steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Jansing, W; Ratzel, W; Vinzens, K

    1975-07-01

    The present status of steam generators is shown. The experience gained until now is expressed in form of basic points. The most important design criteria for steam generator systems are outlined. On the basis of these design criteria, two possible steam generator concepts are shown. Costs in relationship to the repair concepts of two modular steam generators (thermal output 156 and 625 MW) and a pool design of 625 MW are compared. (author)

  2. Comments on US LMFBR steam generator base technology

    International Nuclear Information System (INIS)

    Simmons, W.R.

    1984-01-01

    The development of steam generators for the LMFBR was recognized from the onset by the AEC, now DOE, as a difficult, challenging, and high-priority task. The highly reactive nature of sodium with water/steam requires that the sodium-water/steam boundaries of LMFBR steam generators possess a degree of leak-tightness reliability not normally attempted on a commercial scale. In addition, the LMFBR steam generator is subjected to high fluid temperatures and severe thermal transients. These requirements place great demand on materials, fabrication processes, and inspection methods; and even greater demands on the designer to provide steam generators that can meet these demanding requirements, be fabricated without unreasonable shop requirements, and tolerate off-normal effects

  3. Steam Generator Inspection Planning Expert System

    International Nuclear Information System (INIS)

    Rzasa, P.

    1987-01-01

    Applying Artificial Intelligence technology to steam generator non-destructive examination (NDE) can help identify high risk locations in steam generators and can aid in preparing technical specification compliant eddy current test (ECT) programs. A steam Generator Inspection Planning Expert System has been developed which can assist NDE or utility personnel in planning ECT programs. This system represents and processes its information using an object oriented declarative knowledge base, heuristic rules, and symbolic information processing, three artificial intelligence based techniques incorporated in the design. The output of the system is an automated generation of ECT programs. Used in an outage inspection, this system significantly reduced planning time

  4. Moderator heat recovery of CANDU reactors

    International Nuclear Information System (INIS)

    Fath, H.E.S.; Ahmed, S.T.

    1986-01-01

    A moderator heat recovery scheme is proposed for CANDU reactors. The proposed circuit utilizes all the moderator heat to the first stages of the plant feedwater heating system. CANDU-600 reactors are considered with moderator heat load varying from 120 to 160 MWsub(th), and moderator outlet temperature (from calandria) varying from 80 to 100 0 C. The steam saved from the turbine extraction system was found to produce an additional electric power ranging from 5 to 11 MW. This additional power represents a 0.7-1.7% increase in the plant electric output power and a 0.2-0.7% increase in the plant thermal efficiency. The outstanding features and advantages of the proposed scheme are presented. (author)

  5. Operating experiences with 1 MW steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Sano, A; Kanamori, A; Tsuchiya, T

    1975-07-01

    1 MW steam generator, which was planned as the first stage of steam generator development in Power Reactor and Nuclear Fuel Corp. (PNC) in Japan, is a single-unit, once-through, integrated shell and tube type with multi-helical coil tubes. It was completed in Oarai Engineering Center of PNC in March of 1971, and the various performance tests were carried out up to April, 1972. After the dismantle of the steam generator for structural inspection and material test, it was restored with some improvements. In this second 1 MW steam generator, small leak occurred twice during normal operation. After repairing the failure, the same kind of performance tests as the first steam generator were conducted in order to verify the thermal insulation effect of argon gas in downcomer zone from March to June, 1974. In this paper the above operating experiences were presented including the outline of some performance test results. (author)

  6. Maintenance and repair of LMFBR steam generators

    International Nuclear Information System (INIS)

    Verriere, P.; Alanche, J.; Minguet, J.L.

    1984-06-01

    After some general remarks on the French fast neutron system, this paper presents the state of the program for the construction of fast reactor in France. Then, the general design of Super Phenix 1 steam generator components is outlined and, the in-service monitoring systems and protective devices with which they are equiped are briefly described. The methods used, in the event of leakage, for leak location, steam generator inspection, steam generator repair and putting the affected loop back into service, are discussed. There are two main lines of research, relating respectively to the means of water leak detection in sodium and the inspection arrangements that will be used either periodically, or following a sodium-water reaction. Finally, after a brief description of the steam generator, this paper describes the four incidents (leaks) that occurred on the Phenix steam generator in the course of 1982 and 1983, and the subsequent repair operations

  7. Response of the steam generator VVER 1000 to a steam line break

    International Nuclear Information System (INIS)

    Novotny, J.; Novotny, J. Jr.

    2003-01-01

    Dynamic effects of a steam line break in the weld of the steam pipe and the steam collector on the steam generator system are analyzed. Modelling of a steam line break may concern two cases. The steam line without a restraint and the steam line protected by a whip restraint with viscous elements applied at the postulated break cross-section. The second case is considered. Programme SYSTUS offers a special element the stiffness and viscous damping coefficients of which may be defined as dependent on the relative displacement and velocity of its nodes respectively. A circumferential crack is simulated by a sudden decrease of longitudinal and lateral stiffness coefficients of these special SYSTUS elements to zero. The computation has shown that one can simulate the pipe to behave like completely broken during a time interval of 0,0001 s or less. These elements are used to model the whip restraint with viscous elements and viscous dampers of the GERB type as well. In the case of a whip restraint model the stiffness coefficient-displacement relation and damping coefficient - velocity relation are chosen to fit the given characteristics of the restraint. The special SYSTUS elements are used to constitute Maxwell elements modelling the elasto-plastic and viscous properties of the GERB dampers applied to the steam generator. It has been ascertained that a steam line break at the postulated weld crack between the steam pipe and the steam generator collector cannot endanger the integrity of the system even in a case of the absence of a whip restraint effect. (author)

  8. US PWR steam generator management: An overview

    International Nuclear Information System (INIS)

    Welty, C.S. Jr.

    1997-01-01

    This paper provides an overview on the status of steam generator management activities in US PWRs, and includes: (1) an overview of the impact of steam generator problems; (2) a brief discussion of historical damage trends and the current damage mechanism of most concern; (3) a discussion of the elements of open-quotes steam generator managementclose quotes; and (4) a description of the approach being followed to implement a degradation-specific protocol for tubing inspection and repair. This paper was prepared in conjunction with another paper presented during the Plenary Session of this Conference, open-quotes Steam Generator Degradation: Current Mitigation Strategies for Controlling Corrosionclose quotes, and is provided as a supplement to that material

  9. Report on US-Japan 1983 meetings on steam generators

    International Nuclear Information System (INIS)

    1984-04-01

    This is a report on a trip to Japan by personnel of the US Nuclear Regulatory Commission in 1983 to exchange information on steam generators of nuclear power plants. Steam generators of Japanese pressurized water reactors have experienced nearly all of the forms of degradation that have been experienced in US recirculating-type steam generators, except for denting and pitting. More tubes have been plugged per year of reactor operation in Japanese than in US steam generators, but much of the Japanese tube plugging is preventative rather than the result of leaks experienced. The number of leaks per reactor year is much smaller for Japanese than for US steam generators. No steam generators have been replaced in Japan while several have been replaced in the US. The Japanese experience may be related to their very stringent inspection and maintenance programs for steam generators

  10. The assessment of the impurities concentration into CANDU steam generator crevices

    International Nuclear Information System (INIS)

    Lucan, D.; Fulger, M.; Florea, S.; Jinescu, Ghe.; Woinaroschy, Al.

    2001-01-01

    Crevice corrosion involves a number of simultaneous and interacting operations, including mass transfer processes, production of metal ions within the crevice and hydrolysis reactions, resulting in a very aggressive solution from the point of view of corrosion. These intermediary corrosion processes are in a complex interdependence and they imply a number of important parameters, including both the crevice gap and depth. The major goal of this paper was development of a mathematical model for the calculation of the concentrations of impurities (Na + , Cl - , Fe 2+ ) into crevices and experimental research related to this process. There were identified the important experimental parameters that require further experimental research. This model considers all the processes that interfere in the impurities concentration mechanism achieved into the crevice but it also makes some assumptions for the easy solving of mathematical equations. Because the measurement of the impurities concentration into the steam generator and/or deposition in the crevices solutions is not achievable, one cannot estimate the corrosion intensity inside these locations. The mathematical model presented in this paper may predict the impurities concentration in the crevices. Based on the results obtained in the study of corrosion one can appreciate the corrosion intensity in the materials with crevices or conceive an experimental program, which could lead to results. The predictive quality of the model may contribute to the choice of new design solutions, development of new alloys and criteria of material selection. (authors)

  11. Draining down of a nuclear steam generating system

    International Nuclear Information System (INIS)

    Jawor, J.C.

    1987-01-01

    The method is described of draining down contained reactor-coolant water from the inverted vertical U-tubes of a vertical-type steam generator in which the upper, inverted U-shaped ends of the tubes are closed and the lower ends thereof are open. The steam generator is part of a nuclear powered steam generating system wherein the reactor coolant water is normally circulated from and back into the reactor via a loop comprising the steam generator and inlet and outlet conduits connected to the lower end of the steam generator. The method comprises continuously introducing a gas which is inert to the system and which is under pressure above atmospheric pressure into at least one of the downwardly facing open ends of each of the U-tubes from below the tube sheet in which the open ends of the U-tubes are mounted adjacent the lower end of the steam generator, while permitting the water to flow out from the open ends of the U-tubes

  12. Loss of feed flow, steam generator tube rupture and steam line break thermohydraulic experiments

    International Nuclear Information System (INIS)

    Mendler, O.J.; Takeuchi, K.; Young, M.Y.

    1986-10-01

    The Westinghouse Model Boiler No. 2 (MB-2) steam generator test model at the Engineering Test Facility in Tampa, Florida, was reinstrumented and modified for performing a series of tests simulating steam generator accident transients. The transients simulated were: loss of feed flow, steam generator tube rupture, and steam line break events. This document presents a description of (1) the model boiler and the associated test facility, (2) the tests performed, and (3) the analyses of the test results

  13. Loss of feed flow, steam generator tube rupture and steam line break thermohydraulic experiments

    Energy Technology Data Exchange (ETDEWEB)

    Mendler, O J; Takeuchi, K; Young, M Y

    1986-10-01

    The Westinghouse Model Boiler No. 2 (MB-2) steam generator test model at the Engineering Test Facility in Tampa, Florida, was reinstrumented and modified for performing a series of tests simulating steam generator accident transients. The transients simulated were: loss of feed flow, steam generator tube rupture, and steam line break events. This document presents a description of (1) the model boiler and the associated test facility, (2) the tests performed, and (3) the analyses of the test results.

  14. Future CANDU nuclear power plant design requirements document executive summary

    International Nuclear Information System (INIS)

    Lee, Duk Su; Chang, Woo Hyun; Lee, Nam Young; S. A. Usmani

    1996-03-01

    The future CANDU Requirements Document (FCRED) describes a clear and complete statement of utility requirements for the next generation of CANDU nuclear power plants including those in Korea. The requirements are based on proven technology of PHWR experience and are intended to be consistent with those specified in the current international requirement documents. Furthermore, these integrated set of design requirements, incorporate utility input to the extent currently available and assure a simple, robust and more forgiving design that enhances the performance and safety. The FCRED addresses the entire plant, including the nuclear steam supply system and the balance of the plant, up to the interface with the utility grid at the distribution side of the circuit breakers which connect the switchyard to the transmission lines. Requirements for processing of low level radioactive waste at the plant site and spent fuel storage requirements are included in the FCRED. Off-site waste disposal is beyond the scope of the FCRED. 2 tabs., 1 fig. (Author) .new

  15. Ontario Hydro CANDU operating experience

    International Nuclear Information System (INIS)

    Bartholomew, R.W.; Woodhead, L.W.; Horton, E.P.; Nichols, M.J.; Daly, I.N.

    1987-01-01

    The CANDU Pressurized Heavy Water (CANDU-PHW) type of nuclear-electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This report highlights Ontario Hydro's operating experience using the CANDU-PHW system, with a focus on worker and public safety, operating performance and costs, and reliability of system components

  16. Parametric study for horizontal steam generator modelling

    Energy Technology Data Exchange (ETDEWEB)

    Ovtcharova, I. [Energoproekt, Sofia (Bulgaria)

    1995-12-31

    In the presentation some of the calculated results of horizontal steam generator PGV - 440 modelling with RELAP5/Mod3 are described. Two nodalization schemes have been used with different components in the steam dome. A study of parameters variation on the steam generator work and calculated results is made in cases with separator and branch.

  17. Parametric study for horizontal steam generator modelling

    Energy Technology Data Exchange (ETDEWEB)

    Ovtcharova, I [Energoproekt, Sofia (Bulgaria)

    1996-12-31

    In the presentation some of the calculated results of horizontal steam generator PGV - 440 modelling with RELAP5/Mod3 are described. Two nodalization schemes have been used with different components in the steam dome. A study of parameters variation on the steam generator work and calculated results is made in cases with separator and branch.

  18. R and D in support of CANDU plant life management

    International Nuclear Information System (INIS)

    Tapping, R.L.; Holt, R.A.

    1999-01-01

    One of the keys to the long-term success of CANDUs is a high capacity factor over the station design life. Considerable R and D in underway at AECL to develop technologies for assessing, monitoring and mitigating the effect of plant ageing and for improving plant performance and extending plant life. To achieve longer service life and to realize high capacity factor from CANDU stations, AECL is developing new technologies to enhance fuel channel and steam generator inspection capabilities, to monitor system health, and to allow preventive maintenance and cleaning (e.g., on-line chemical cleaning processes that produce small volumes of wastes). The life management strategy for fuel channels and steam generators requires a program to inspect components on a routine basis to identify mechanisms that could potentially affect fitness-for-service. In the case of fuel channels, the strategy includes inspections for dimensional changes, flaw detection, and deuterium concentration. New techniques are been developed to enhance these inspection capabilities; examples include accurate measurement of the gap between a pressure tube and its calandria tube and rapid full-length inspections of steam generator tubes for all known flaw types. Central to life management of components are Fitness-for-Service Guidelines (FFSG) that have been developed with the CANDU Owners Group (COG) that provide a standardized method to assess the potential for propagation of flaws detected during in-service inspections, and assessment of any change in fracture characteristics of the material. FFSG continue to be improved with the development of new technologies such as the capability to credit relaxation of stresses due to creep and non-rejectable flaws in pressure tubes. Effective management of plant systems throughout their lifetime requires much more than data acquisition and display - it requires that system health is continually monitored and managed. AECL has developed a system Health Monitor

  19. Steam generator arrangement

    International Nuclear Information System (INIS)

    Ssinegurski, E.

    1981-01-01

    A steam flow path arrangement for covering the walls of the rear gas pass of a steam generator is disclosed. The entire flow passes down the sidewalls with a minor portion then passing up through the rear wall to a superheater inlet header at an intermediate elevation. The major portion of the flow passes up the front wall and through hanger tubes to a roof header. From there the major portion passes across the roof and down the rear wall to the superheater inlet header at the intermediate elevation

  20. CRBRP steam-generator design evolution

    International Nuclear Information System (INIS)

    Geiger, W.R.; Gillett, J.E.; Lagally, H.O.

    1983-01-01

    The overall design of the CRBRP Steam Generator is briefly discussed. Two areas of particular concern are highlighted and considerations leading to the final design are detailed. Differential thermal expansion between the shell and the steam tubes is accommodated by the tubes flexing in the curved section of the shell. Support of the tubes by the internals structure is essential to permit free movement and minimize tube wear. Special spacer plate attachment and tube hole geometry promote unimpeded axial movement of the tubes by allowing individual tubes to rotate laterally and by providing lateral movement of the spacer plates relative to the adjacent support structure. The water/steam heads of the CRBRP Steam Generator are spherical heads welded to the lower and upper tubesheets. They were chosen principally because they provide a positively sealed system and result in more favorable stresses in the tubesheets when compared to mechanically attached steamheads

  1. Wavelet network controller for nuclear steam generators

    International Nuclear Information System (INIS)

    Habibiyan, H; Sayadian, A; Ghafoori-Fard, H

    2005-01-01

    Poor control of steam generator water level is the main cause of unexpected shutdowns in nuclear power plants. Particularly at low powers, it is a difficult task due to shrink and swell phenomena and flow measurement errors. In addition, the steam generator is a highly complex, nonlinear and time-varying system and its parameters vary with operating conditions. Therefore, it seems that design of a suitable controller is a necessary step to enhance plant availability factor. The purpose of this paper is to design, analyze and evaluate a water level controller for U-tube steam generators using wavelet neural networks. Computer simulations show that the proposed controller improves transient response of steam generator water level and demonstrate its superiority to existing controllers

  2. IAEA activities on steam generator life management

    International Nuclear Information System (INIS)

    Gueorguiev, B.; Lyssakov, V.; Trampus, P.

    2002-01-01

    The International Atomic Energy Agency (IAEA) carries out a set of activities in the field of Nuclear Power Plant (NPP) life management. Main activities within this area are implemented through the Technical Working Group on Life Management of NPPs, and mostly concentrated on studies of understanding mechanisms of degradation and their monitoring, optimisation of maintenance management, economic aspects, proven practices of and approaches to plant life management including decommissioning. The paper covers two ongoing activities related to steam generator life management: the International Database on NPP Steam Generators and the Co-ordinated Research Project on Verification of WWER Steam Generator Tube Integrity (WWER is the Russian designed PWR). The lifetime assessment of main components relies on an ability to assess their condition and predict future degradation trends, which to a large extent is dependent on the availability of relevant data. Effective management of ageing and degradation processes requires a large amount of data. Several years ago the IAEA started to work on the International Database on NPP Life Management. This is a multi-module database consisting of modules such as reactor pressure vessels materials, piping, steam generators, and concrete structures. At present the work on pressure vessel materials, on piping as well as on steam generator is completed. The paper will present the concept and structure of the steam generator module of the database. In countries operating WWER NPPs, there are big differences in the eddy current inspection strategy and practice as well as in the approach to steam generator heat exchanger tube structural integrity assessment. Responding to the need for a co-ordinated research to compare eddy current testing results with destructive testing using pulled out tubes from WWER steam generators, the IAEA launched this project. The main objectives of the project are to summarise the operating experiences of WWER

  3. Vibration Analysis for Steam Dryer of APR1400 Steam Generator

    Energy Technology Data Exchange (ETDEWEB)

    Han, Sung-heum; Ko, Doyoung [KHNP CRI, Daejeon (Korea, Republic of); Cho, Minki [Doosan Heavy Industry, Changwon (Korea, Republic of)

    2016-10-15

    This paper is related to comprehensive vibration assessment program for APR1400 steam generator internals. According to U.S. Nuclear Regulatory Commission, Regulatory Guide 1.20 (Rev.3, March 2007), we conducted vibration analysis for a steam dryer as the second steam separator of steam generator internals. The vibration analysis was performed at the 100 % power operating condition as the normal operation condition. The random hydraulic loads were calculated by the computational fluid dynamics and the structural responses were predicted by power spectral density analysis for the probabilistic method. In order to meet the recently revised U.S. NRC RG 1.20 Rev.3, the CVAP against the potential adverse flow effects in APR1400 SG internals should be performed. This study conducted the vibration response analysis for the SG steam dryer as the second moisture separator at the 100% power condition, and evaluated the structural integrity. The predicted alternating stress intensities were evaluated to have more than 17.78 times fatigue margin compared to the endurance limit.

  4. Dynamic modelling of nuclear steam generators

    International Nuclear Information System (INIS)

    Kerlin, T.W.; Katz, E.M.; Freels, J.; Thakkar, J.

    1980-01-01

    Moving boundary, nodal models with dynamic energy balances, dynamic mass balances, quasi-static momentum balances, and an equivalent single channel approach have been developed for steam generators used in nuclear power plants. The model for the U-tube recirculation type steam generator is described and comparisons are made of responses from models of different complexity; non-linear versus linear, high-order versus low order, detailed modeling of the control system versus a simple control assumption. The results of dynamic tests on nuclear power systems show that when this steam generator model is included in a system simulation there is good agreement with actual plant performance. (author)

  5. Future development LMFBR-steam generators SNR2

    International Nuclear Information System (INIS)

    Essebaggers, J.; Pors, J.G.

    1975-01-01

    The development work for steam generators for large LMFBR plants by Neratoom will be reviewed consisting of: 1. Development engineering information. 2. Concept select studies followed by conceptual designs of selected models. 3. Development manufacturing techniques. 4. Detail design of a prototype unit. 5. Testing of sub-constructions for prototype steam generators. In this presentation item 1 and 2 above will be high lighted, identifying the development work for the SNR-2 steam generators on short term basis. (author)

  6. Multipurpose expert-robot system model for control, diagnosis, maintenance, and repairs at the steam generators of the NPP

    International Nuclear Information System (INIS)

    Popa, I.

    1994-01-01

    The paper presents the model concept for a multipurpose expert-robot system for control, diagnosis, forecast, maintenance, and repairs at the steam generators of CANDU type nuclear power plants. The system has two separate parts: the expert system and the robot (manipulator) system. These parts compose a hierarchic structure with the expert system on the upper level. The expert system has a blackboard architecture, to which tree interfaces with the robot system, with the control system of the NPP and with the methods and techniques of control, maintenance and repairs system of the steam generator are added. Due to complex nature of its activities the expert-robot system model combines the deterministic type reasons with probabilistic, fuzzy, and neural-networks type ones. The information that enter the expert system comes from the robot system, from process, from user, and human expert. The information that enter robot system comes from the expert system, from the human operator (when connected) and from process. Control maintenance and repair operations take place by means of the robot system that can be monitored either directly by the expert system or by the human operator who follows its activity. All these activities are performed in parallel with the adequate information of the expert system directly, by the human operator, about the status parameters and, possibly, operating parameters of the steam generator components. The expert-robot system can work independently, but it can be connected and integrated in the control system of NPP, to take over and develop some of its functions. The activities concerning diagnosis and characterization of the state of steam generator components subsequent to control, as well as the forecast of their future behavior, are performed by means of the expert system. Due to these characteristics the expert-robot system can be used successfully in personnel training activities. (Author)

  7. French steam generator

    International Nuclear Information System (INIS)

    Remond, A.

    1986-01-01

    After recalling the potential damage mode of tubes of steam generator, the author recalls the safety criteria used in France. The improvements and the process of damage prejudice and reparation for tubular bundle are presented [fr

  8. Model studies of the vertical steam generator thermal-hydraulic characteristics

    International Nuclear Information System (INIS)

    Desyatun, V.F.; Moskvichev, V.F.; Ulasov, V.M.; Morozov, V.G.; Burkov, V.K.; Grebennikov, V.N.

    1984-01-01

    Results of investigations conducted to clarify the calculation technique and to test the workability of the main elements and units of the PGV-250 vertical steam generator of saturated steam are considered. The steam generating capacity of the plant is 1486 t/h, thermal power is 792 MW. Steam generation follows a multiple circulation scheme. The heat surface comprises 330-shields. The investigations are carried out with a model which reproduces all the main elements of the steam generator xcluding the economizer section. The flow rates of feed water, generated steam and coolant of the first circuit as well as temperature, pressure and humidity of the generated steam past the separator are determined. The average heat transfer factors of the heat surface are calculated on the base of the data obtained and a conclusion is drawn on the correctness of the thermohydraulic calculation technique used in development of the PGV-250 steam generator design. Temperature pulsations and heat surface steaming are not observed. The steam humidity at the outlet and steam capture into sinking tubes are within permissible values

  9. LMR steam generator blowdown with RETRAN

    International Nuclear Information System (INIS)

    Wei, T.Y.C.

    1985-01-01

    One of the transients being considered in the FSAR Chapter 15 analyses of anticipated LMR transients is the fast blowdown of a steam generator upon inadvertent actuation of the liquid metal/water reaction mitigation system. For the blowdown analysis, a stand-alone steam generator model for the IFR plant was constructed using RETRAN

  10. Station black out analysis for CANDU 6 plant

    International Nuclear Information System (INIS)

    Baburajan, P.K.; Rao, R.S.; Gupta, S.K.

    2011-01-01

    As part of International Atomic Energy Agency (IAEA) Coordinated Research Project (CRP), 'Benchmarking severe accident computer codes for pressurised heavy water reactor applications', thermal hydraulic analysis of severe accident station black out (SBO) is carried out for a generic CANDU 6 plant. The CRP is conducted in order to improve severe accident analysis capability for heavy water reactors (HWRs) through the benchmarking exercise. The plant simulation is carried out using RELAP5/Mod3.4 best estimate system thermal hydraulic code. The total thermal power of the plant is 2064 MW. There are 380 fuel channels in the core, 12 fuel bundles per channel and each bundle assembly has 37 fuel elements. The primary heat transport system (HTS) consists of two loops. Each loop consist of inlet and exit headers, feeder lines, fuel channels, hot leg and cold leg of steam generator, pumps, pump suction and discharge lines. Ninety five fuel channels in each pass of the loop are simulated as a single channel. The steam generator as the secondary side heat sink consists of annulus down-comer, riser, steam separator, steam drum, steam header and steam lines. Fuel channels (pressure tube) and calandria tube are simulated using SCDAPSIM to study the severe accident code behaviour. The SBO transient is initiated after obtaining the steady state conditions. Present analysis is carried out till the pressure tube failure. Analysis results show that the secondary inventory is lost in about 6500 seconds of the transient. The primary inventory is lost in 10370 seconds of the transient and subsequently the pressure tube failure is predicted as the tube wall temperature exceeded 900 K. Further analysis is to be carried out by incorporating changes in the calandria model and including the modeling of calandria vault and containment. (author)

  11. Use of empirically based corrosion model to aid steam generator life management

    Energy Technology Data Exchange (ETDEWEB)

    Angell, P.; Balakrishnan, P.V.; Turner, C.W

    2000-07-01

    Alloy 800 (N08800) tubes used in CANDU 6 steam generators have shown a low incidence of corrosion damage because of the good corrosion resistance of N08800 and successful water chemistry control strategies. However, N08800 is not immune to corrosion, especially pitting, under plausible SG conditions. Electrochemical potentials are critical in determining both susceptibility and rates of corrosion and are known to be a function of water-chemistry. Using laboratory data an empirical model for pitting and crevice corrosion has been developed for N08800. Combination of such a model with chemistry monitoring and diagnostic software makes it possible to arm the impact of plant operating conditions on SG tube corrosion for plant life management (PLIM). Possible transient chemistry regimes that could significantly shorten expected tube lifetimes have been identified and predictions continue to support the position dud under normal, low dissolved oxygen conditions, pitting of N08800 will not initiate. (author)

  12. Use of empirically based corrosion model to aid steam generator life management

    International Nuclear Information System (INIS)

    Angell, P.; Balakrishnan, P.V.; Turner, C.W.

    2000-01-01

    Alloy 800 (N08800) tubes used in CANDU 6 steam generators have shown a low incidence of corrosion damage because of the good corrosion resistance of N08800 and successful water chemistry control strategies. However, N08800 is not immune to corrosion, especially pitting, under plausible SG conditions. Electrochemical potentials are critical in determining both susceptibility and rates of corrosion and are known to be a function of water-chemistry. Using laboratory data an empirical model for pitting and crevice corrosion has been developed for N08800. Combination of such a model with chemistry monitoring and diagnostic software makes it possible to arm the impact of plant operating conditions on SG tube corrosion for plant life management (PLIM). Possible transient chemistry regimes that could significantly shorten expected tube lifetimes have been identified and predictions continue to support the position dud under normal, low dissolved oxygen conditions, pitting of N08800 will not initiate. (author)

  13. Ontario Hydro CANDU operating experience

    International Nuclear Information System (INIS)

    Jackson, H.A.; Woodhead, L.W.; Fanjoy, G.R.

    1984-03-01

    The CANDU Pressurized Heavy Water (CANDU-PHW) type of nuclear-electric generating station has been developed jointly by Atomic Energy of Canada Limited and Ontario Hydro. This report highlights Ontario Hydro's operating experience using the CANDU-PHW system, with a focus on the operating performance and costs, reliability of system components and nuclear safety considerations for the workers and the public

  14. Risk analysis due to the extension of STI for CANDU diesel generators

    Energy Technology Data Exchange (ETDEWEB)

    Jee, Moon Hak; Choi, Kwang Hee; Jung, Hyun Jong; Choi, Seong Soo [Korea electric Power Research Institute, Taejon (Korea, Republic of); Lim, Jae Won [Atomic Creative Technology Company, Taejon (Korea, Republic of); Song, Jin Bae [KHNP, Kyungju (Korea, Republic of)

    2005-07-01

    The purpose of this study is to provide technical rationale for the extension of the Surveillance Test Interval (STI) of the Standby Diesel Generator (SDG) and the Emergency Power Supply Diesel Generator (EPSDG) of CANDU plants in Korea in a reliability aspect. The current STI of 2 weeks aims to be extended to 4 weeks through this study.

  15. Research program plan: steam generators

    International Nuclear Information System (INIS)

    Muscara, J.; Serpan, C.Z. Jr.

    1985-07-01

    This document presents a plan for research in Steam Generators to be performed by the Materials Engineering Branch, MEBR, Division of Engineering Technology, (EDET), Office of Nuclear Regulatory Research. It is one of four plans describing the ongoing research in the corresponding areas of MEBR activity. In order to answer the questions posed, the Steam Generator Program has been organized with the three elements of non-destructive examination; mechanical integrity testing; and corrosion, cleaning and decontamination

  16. Water box for steam generator

    International Nuclear Information System (INIS)

    Lecomte, Robert; Viaud, Michel.

    1975-01-01

    This invention relates to a water box for connecting an assembly composed of a vertical steam generator and a vertical pump to the vessel of the nuclear reactor, the assembly forming the primary cooling system of a pressurised water reactor. This invention makes it easy to dismantle the pump on the water box without significant loss of water in the primary cooling system of the reactor and particularly without it being necessary to drain the water contained in the steam generator beforehand. It makes it possible to shorten the time required for dismantling the primary pump in order to service or repair it and makes dismantling safer in that the dismantling does not involve draining the steam generator and therefore the critical storage of a large amount of cooling water that has been in contact with the fuel assemblies of the nuclear reactor core [fr

  17. Three-dimensional modeling of nuclear steam generator

    International Nuclear Information System (INIS)

    Bogdan, Z.; Afgan, N.

    1985-01-01

    In this paper mathematical model for steady-state simulation of thermodynamic and hydraulic behaviour of U-tube nuclear steam generator is described. The model predicts three-dimensional distribution of temperatures, pressures, steam qualities and velocities in the steam generator secondary loop. In this analysis homogeneous two phase flow model is utilized. Foe purpose of the computer implementation of the mathematical model, a special flow distribution code NUGEN was developed. Calculations are performed with the input data and geometrical characteristics related to the D-4 (westinghouse) model of U-tube nuclear steam generator built in Krsko, operating under 100% load conditions. Results are shown in diagrams giving spatial distribution of pertinent variables in the secondary loop. (author)

  18. Steam generator tube rupture effects on a LOCA

    International Nuclear Information System (INIS)

    LaChance, J.L.

    1979-01-01

    A problem currently experienced in commercial operating pressurized water reactors (PWR) in the United States is the degradation of steam generator tubes. Safety questions have arisen concerning the effect of these degraded tubes rupturing during a postulated loss-of-coolant accident (LOCA). To determine the effect of a small number of tube ruptures on the behavior of a large PWR during a postulated LOCA, a series of computer simulations was performed. The primary concern of the study was to determine whether a small number (10 or less of steam generator tubes rupturing at the beginning surface temperatures. Additional reflood analyses were performed to determine the system behavior when from 10 to 60 tubes rupture at the beginning of core reflood. The FLOOD4 code was selected as being the most applicable code for use in this study after an extensive analysis of the capabilities of existing codes to perform simulations of a LOCA with concurrent steam generator tube ruptures. The results of the study indicate that the rupturing of 10 or less steam generator tubes in any of the steam generators during a 200% cold leg break will not result in a significant increase in the peak cladding temperature. However, because of the vaporization of the steam generator secondary water in the primary side of the steam generator, a significant increase in the core pressure occurs which retards the reflooding process

  19. Mathematical modeling of control system for the experimental steam generator

    Science.gov (United States)

    Podlasek, Szymon; Lalik, Krzysztof; Filipowicz, Mariusz; Sornek, Krzysztof; Kupski, Robert; Raś, Anita

    2016-03-01

    A steam generator is an essential unit of each cogeneration system using steam machines. Currently one of the cheapest ways of the steam generation can be application of old steam generators came from army surplus store. They have relatively simple construction and in case of not so exploited units - quite good general conditions, and functionality of mechanical components. By contrast, electrical components and control systems (mostly based on relay automatics) are definitely obsolete. It is not possible to use such units with cooperation of steam bus or with steam engines. In particular, there is no possibility for automatically adjustment of the pressure and the temperature of the generated steam supplying steam engines. Such adjustment is necessary in case of variation of a generator load. The paper is devoted to description of improvement of an exemplary unit together with construction of the measurement-control system based on a PLC. The aim was to enable for communication between the steam generator and controllers of the steam bus and steam engines in order to construction of a complete, fully autonomic and maintenance-free microcogeneration system.

  20. The structural aging assessment program: ranking methodology for CANDU nuclear generating station concrete components

    International Nuclear Information System (INIS)

    Philipose, K.E.; Muhkerjee, P.K.; McColm, E.J.

    1997-01-01

    Most of the major structural components in CANDU nuclear generating stations are constructed of reinforced concrete. Although passive in nature, these structures perform many critical safety functions in the operation of each facility. Aging can affect the structural capacity and integrity of structures. The reduction in capacity due to aging is not addressed in design codes. Thus a program is warranted to monitor the aging of safety-related CANDU plant structures and to prioritize those that require maintenance and repairs. Prioritization of monitoring efforts is best accomplished by focusing on those structures judged to be the most critical to plant performance and safety. The safety significance of each sub-element and its degradation with time can be evaluated using a numerical rating system. This will simplify the utility's efforts, thereby saving maintenance costs while providing a higher degree of assurance that performance is maintained. This paper describes the development of a rating system (ranking procedure) as part of the Plant Life Management of CANDU generating station concrete structures and illustrates its application to an operating plant. (author)

  1. Incentives for improvement of CANDU

    International Nuclear Information System (INIS)

    Hart, R.S.; Dunn, J.T.; Finlay, R.B.

    1988-12-01

    CANDU is a relatively young technology which has demonstrated many achievements as an electrical power generation system. These achievements include an unsurpassed safety record, high annual and lifetime capacity factors, low electricity cost and a broad range of other performance strengths which together indicate that the CANDU technology is fundamentally sound. Known capabilities not yet fully exploited, such as advanced fuel cycle options, indicate that CANDU technology will continue to pay strong dividends on research, development and design investment. This provides a strong incentive for the improvement of CANDU on a continuing basis

  2. Modeling and Simulation of U-tube Steam Generator

    Science.gov (United States)

    Zhang, Mingming; Fu, Zhongguang; Li, Jinyao; Wang, Mingfei

    2018-03-01

    The U-tube natural circulation steam generator was mainly researched with modeling and simulation in this article. The research is based on simuworks system simulation software platform. By analyzing the structural characteristics and the operating principle of U-tube steam generator, there are 14 control volumes in the model, including primary side, secondary side, down channel and steam plenum, etc. The model depends completely on conservation laws, and it is applied to make some simulation tests. The results show that the model is capable of simulating properly the dynamic response of U-tube steam generator.

  3. Wastage of Steam Generator Tubes by Sodium-Water Reaction

    International Nuclear Information System (INIS)

    Jeong, Ji Young; Kim, Jong Man; Kim, Tae Joon; Choi, Jong Hyeun; Kim, Byung Ho; Lee, Yong Bum; Park, Nam Cook

    2010-01-01

    The Korea Advanced LIquid MEtal Reactor (KALIMER) steam generator is a helical coil, vertically oriented, shell-and-tube type heat exchanger with fixed tube-sheet. The conceptual design and outline drawing of the steam generator are shown in Figure 1. Flow is counter-current, with sodium on the shell side and water/steam on the tube side. Sodium flow enters the steam generator through the upper inlet nozzles and then flows down through the tube bundle. Feedwater enters the steam generator through the feedwater nozzles at the bottom of steam generator. Therefore, if there is a hole or a crack in a heat transfer tube, a leakage of water/steam into the sodium may occur, resulting in a sodium-water reaction. When such a leak occurs, so-called 'wastage' is the result which may cause damage to or a failure of the adjacent tubes. If a steam generator is operated for some time in this condition, it is possible that it might create an intermediate leak state which would then give rise to the problems of a multi-target wastage in a very short time. Therefore, it is very important to predict these phenomena quantitatively from the view of designing a steam generator and its leak detection systems. For this, multi-target wastage tests for modified 9Cr-1Mo steel tube bundle by intermediate leaks are being prepared

  4. Passive safety features for next generation CANDU power plants

    International Nuclear Information System (INIS)

    Natalizio, A.; Hart, R.S.; Lipsett, J.J.; Soedijono, P.; Dick, J.E.

    1989-01-01

    CANDU offers an evolutionary approach to simpler and safer reactors. The CANDU 3, an advanced CANDU, currently in the detailed design stage, offers significant improvements in the areas of safety, design simplicity, constructibility, operability, maintainability, schedule and cost. These are being accomplished by retaining all of the well known CANDU benefits, and by relying on the use of proven components and technologies. A major safety benefit of CANDU is the moderator system which is separate from the coolant. The presence of a cold moderator reduces the consequences arising from a LOCA or loss of heat sink event. In existing CANDU plants even the severe accident - LOCA with failure of the emergency core cooling system - is a design basis event. Further advances toward a simpler and more passively safe reactor will be made using the same evolutionary approach. Building on the strength of the moderator system to mitigate against severe accidents, a passive moderator cooling system, depending only on the law of gravity to perform its function, will be the next step of development. AECL is currently investigating a number of other features that could be incorporated in future evolutionary CANDU designs to enhance protection against accidents, and to limit off-site consequences to an acceptable level, for even the worst event. The additional features being investigated include passive decay heat removal from the heat transport system, a simpler emergency core cooling system and a containment pressure suppression/venting capability for beyond design basis events. Central to these passive decay heat removal schemes is the availability of a short-term heat sink to provide a decay heat removal capability of at least three days, without any station services. Preliminary results from these investigations confirm the feasibility of these schemes. (author)

  5. Steam generator leak detection using acoustic method

    International Nuclear Information System (INIS)

    Goluchko, V.V.; Sokolov, B.M.; Bulanov, A.N.

    1982-05-01

    The main requirements to meet by a device for leak detection in sodium - water steam generators are determined. The potentialities of instrumentation designed based on the developed requirements have been tested using a model of a 550 kw steam generator [fr

  6. Mathematical modeling of control system for the experimental steam generator

    Directory of Open Access Journals (Sweden)

    Podlasek Szymon

    2016-01-01

    Full Text Available A steam generator is an essential unit of each cogeneration system using steam machines. Currently one of the cheapest ways of the steam generation can be application of old steam generators came from army surplus store. They have relatively simple construction and in case of not so exploited units – quite good general conditions, and functionality of mechanical components. By contrast, electrical components and control systems (mostly based on relay automatics are definitely obsolete. It is not possible to use such units with cooperation of steam bus or with steam engines. In particular, there is no possibility for automatically adjustment of the pressure and the temperature of the generated steam supplying steam engines. Such adjustment is necessary in case of variation of a generator load. The paper is devoted to description of improvement of an exemplary unit together with construction of the measurement-control system based on a PLC. The aim was to enable for communication between the steam generator and controllers of the steam bus and steam engines in order to construction of a complete, fully autonomic and maintenance-free microcogeneration system.

  7. Mechanical design of a sodium heated steam generator

    International Nuclear Information System (INIS)

    Chetal, S.C.

    1975-01-01

    FBTR steam generator is a once through type unit consisting of four 12.5 MW thermal modules generating a total of 74 tons per hour of steam at 125 bar and 480 0 C. This paper outlines the mechanical design of such type of steam generator with emphasis on special design problems associated with this type of sodium to water steam heat exchanger, namely, thermal cycling of transition zone where nucleate boiling changes over to film boiling, application of pressure vessel design criteria for transient pressures, thermal stress evaluation resulting from differential expansion between shell and tube in this typical configuration, sodium headers support design, thermal sleeve, design, thermal shock analysis in thick tubes, thermal stress resulting from stratification and stability of expansion bends against vibration. Some of the possible design changes for the future large size steam generator are outlined. (author)

  8. Consolidated nuclear steam generator

    International Nuclear Information System (INIS)

    Jabsen, F.S.; Schluderberg, D.C.; Paulson, A.E.

    1978-01-01

    An improved system of providing power has a unique generating means for nuclear reactors with a number of steam generators in the form of replaceable modular units of the expendable type to attain the optimum in effective and efficient vaporization of fluid during the generating power. The system is most adaptable to undrground power plants and marine usage

  9. Steam generator tube integrity program. Phase I report

    International Nuclear Information System (INIS)

    Alzheimer, J.M.; Clark, R.A.; Morris, C.J.; Vagins, M.

    1979-09-01

    The results are presented of the pressure tests performed as part of Phase I of the Steam Generator Tube Integrity (SGTI) program at Battelle Pacific Northwest Laboratory. These tests were performed to establish margin-to-failure predictions for mechanically defected Pressurized Water Reactor (PWR) steam generator tubing under operating and accident conditions. Defect geometries tested were selected because they simulate known or expected defects in PWR steam generators. These defect geometries are Electric Discharge Machining (EDM) slots, elliptical wastage, elliptical wastage plus through-wall slot, uniform thinning, denting, denting plus uniform thinning, and denting plus elliptical wastage. All defects were placed in tubing representative of that currently used in PWR steam generators

  10. LOCA assessment experiments in a full-elevation, CANDU-typical test facility

    International Nuclear Information System (INIS)

    Ingham, P.J.; McGee, G.R.; Krishnan, V.S.

    1990-01-01

    The RD-14 thermal-hydraulics test facility, located at the Whiteshell Nuclear Research Establishment, is a full-elevation model representative of a CANDU primary heat transport system. The facility is scaled to accommodate a single, full-scale (5.0 MW, 21 kg/s), electrically heated channel per pass. The steam generators, pumps, headers, feeders and heated channels are arranged in a typical CANDU figure-of-eight geometry. The loop has an emergency coolant injection system (ECI) that may be operated in several modes, including typical features of the various ECI systems found in CANDU reactors. A series of experiments has been performed in RD-14 to investigate the thermal-hydraulic behaviour during the blowdown and injection phases of a loss-of-coolant accident (LOCA). The tests were designed to cover a full range of break sizes from feeder-sized breaks to guillotine breaks in either an inlet or an outlet header. Breaks resulting in channel flow stagnation were also investigated. This paper reviews the results of some of the LOCA tests carried out in RD-14, and discusses some of the behaviour observed. Plans for future experiments in a multiple-channel RD-14 facility, modified to contain multiple flow channels, are outlined. (orig.)

  11. Perspective of the Westinghouse steam generator secondary side maintenance approach

    Energy Technology Data Exchange (ETDEWEB)

    Ramaley, D. [Westinghouse Electric Company LLC, Cranberry Township, Pennsylvania (United States)

    2012-07-01

    Historically, Westinghouse had developed a set of steam generator secondary maintenance guidelines focused around performing recurring activities each outage without direct regards to the age, deposit loading, operational status, or corrosion status of the steam generator. Through the evolution of steam generator design and steam generator condition data, Westinghouse now uses a proactive assessment and planning approach for utilities. Westinghouse works with utilities to develop steam generator secondary maintenance plans for long term steam generator viability. Westinghouse has developed a portfolio of products to allow utilities to optimize steam generator operability and develop programs aimed at maintaining the steam generator secondary side in a favorable condition for successful long term operation. Judicious use of the means available for program development should allow for corrosion free operation, long term full power operation at optimum thermal efficiency, and leveling of outage expenditures over a long period of time. This paper will review the following required elements for an effective steam generator secondary side strategy: • Assessment: In order to develop an appropriate maintenance strategy, actions must be taken to obtain an accurate picture of the SG secondary side condition. • Forecasting: Using available data predictions are developed for future steam generator conditions and required maintenance actions. • Action: Cost effective engineering and maintenance actions must be completed at the appropriate time as designated by the plan. • Evaluation of Results: Following execution of maintenance tactics, it is necessary to revise strategy and develop technology enhancements as appropriate. (author)

  12. Double wall steam generator tubing

    International Nuclear Information System (INIS)

    Padden, T.R.; Uber, C.F.

    1983-01-01

    Double-walled steam generator tubing for the steam generators of a liquid metal cooled fast breeder reactor prevents sliding between the surfaces due to a mechanical interlock. Forces resulting from differential thermal expansion between the outer tube and the inner tube are insufficient in magnitude to cause shearing of base metal. The interlock is formed by jointly drawing the tubing, with the inside wall of the outer tube being already formed with grooves. The drawing causes the outer wall of the inner tube to form corrugations locking with the grooves. (author)

  13. Impact of aging and material structure on CANDU plant performance

    International Nuclear Information System (INIS)

    Nadeau, E.; Ballyk, J.; Ghalavand, N.

    2011-01-01

    In-service behaviour of pressure tubes is a key factor in the assessment of safety margins during plant operation. Pressure tube deformation (diametral expansion) affects fuel bundle dry out characteristics resulting in reduced margin to trip for some events. Pressure tube aging mechanisms also erode design margins on fuel channels or interfacing reactor components. The degradation mechanisms of interest are primarily deformation, loss of fracture resistance and hydrogen ingress. CANDU (CANada Deuterium Uranium, a registered trademark of the Atomic Energy of Canada Limited used under exclusive licence by Candu Energy Inc.) owners and operators need to maximize plant capacity factor and meet or exceed the reactor design life targets while maintaining safety margins. The degradation of pressure tube material and geometry are characterized through a program of inspection, material surveillance and assessment and need to be managed to optimize plant performance. Candu is improving pressure tubes installed in new build and life extension projects. Improvements include changes designed to reduce or mitigate the impact of pressure tube elongation and diametral expansion rates, improvement of pressure tube fracture properties, and reduction of the implications of hydrogen ingress. In addition, Candu provides an extensive array of engineering services designed to assess the condition of pressure tubes and address the impact of pressure tube degradation on safety margins and plant performance. These services include periodic and in-service inspection and material surveillance of pressure tubes and deterministic and probabilistic assessment of pressure tube fitness for service to applicable standards. Activities designed to mitigate the impact of pressure tube deformation on safety margins include steam generator cleaning, which improves trip margins, and trip design assessment to optimize reactor trip set points restoring safety and operating margins. This paper provides an

  14. Coal fired steam generation for heavy oil recovery

    International Nuclear Information System (INIS)

    Firmin, K.

    1992-01-01

    In Alberta, some 21,000 m 3 /d of heavy oil and bitumen are produced by in-situ recovery methods involving steam injection. The steam generation requirement is met by standardized natural-gas-fired steam generators. While gas is in plentiful supply in Alberta and therefore competitively priced, significant gas price increases could occur in the future. A 1985 study investigating the alternatives to natural gas as a fuel for steam generation concluded that coal was the most economic alternative, as reserves of subbituminous coal are not only abundant in Alberta but also located relatively close to heavy oil and bitumen production areas. The environmental performance of coal is critical to its acceptance as an alternate fuel to natural gas, and proposed steam generator designs which could burn Alberta coal and control emissions satisfactorily are assessed. Considerations for ash removal, sulfur dioxide sorption, nitrogen oxides control, and particulate emission capture are also presented. A multi-stage slagging type of coal-fired combustor has been developed which is suitable for application with oilfield steam generators and is being commissioned for a demonstration project at the Cold Lake deposit. An economic study showed that the use of coal for steam generation in heavy oil in-situ projects in the Peace River and Cold Lake areas would be economic, compared to natural gas, at fuel price projections and design/cost premises for a project timing in the mid-1990s. 7 figs., 3 tabs

  15. Forming a cohesive steam generator maintenance strategy

    International Nuclear Information System (INIS)

    Poudroux, G.

    1991-01-01

    In older nuclear plants, steam generator tube bundles are the most fragile part of the reactor coolant system. Steam generator tubes are subject to numerous types of loading, which can lead to severe degradation (corrosion and wear phenomena). Preventive actions, such as reactor coolant temperature reduction or increasing the plugging limit and their associated analyses, can increase steam generator service life. Beyond these preventive actions, the number of affected tubes and the different locations of the degradations that occur often make repair campaigns necessary. Framatome has developed and qualified a wide range of treatment and repair processes. They enable careful management of the repair campaigns, to avoid reaching the maximum steam generator tube plugging limit, while optimizing the costs. Most of the available repair techniques allow a large number of affected tubes to be treated. Here we look only at those techniques that should be taken into account when defining a maintenance strategy. (author)

  16. Condensate polisher application for PWR steam generator corrosion control

    International Nuclear Information System (INIS)

    Sawochka, S.G.; Leibovitz, J.; Siegwarth, D.P.; Pearl, W.L.

    1981-01-01

    The evolution of corrosion attack modes particularly in recirculating U-tube PWR steam generators has dictated a thorough review of the advantages and disadvantages of condensate polishing. Analytical modeling techniques to qualitatively predict crevice chemistry variations resulting from steam generator bulk water variations have allowed valuable insights to be developed. Modeling results complemented by steam generator and laboratory corrosion data will be employed to set condensate demineralizer effluent specifications consistent with control of steam generator corrosion. Laboratory and plant studies are being performed to demonstrate achievability of necessary effluent specifications. (author)

  17. Conceptual design of once-through helical steam generator for SMART

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Yong Wan; Kim, J. I.; Kim, J. H. [Korea Atomic Energy Research Institute, Taejon (Korea)

    1999-12-01

    Conceptual design of once-through helical steam generator for the integral reactor SMART is developed. The once-through helical steam generator requires quite different design concepts from the steam generators used in loop type commercial reactors. In this study the design requirements satisfying the operating conditions of the steam generator are derived, and the arrangements and the dimensions of the major parts are determined. By describing the design procedure, the cost of redesign and the costs of developments of similar new steam generators are minimized. The three dimensional models developed make it possible to preview the interferences of the steam generator components and to minimize the possibility of significant design changes in the next design stage by the preliminary strength analysis of the major parts. A methodology for evaluation of flow induced vibration of steam generator tubes has been developed and a preliminary flow induced vibration analysis has been performed. 24 refs., 54 figs., 9 tabs. (Author)

  18. Dismantling of the 50 MW steam generator test facility

    International Nuclear Information System (INIS)

    Nakai, S.; Onojima, T.; Yamamoto, S.; Akai, M.; Isozaki, T.; Gunji, M.; Yatabe, T.

    1997-01-01

    We have been dismantling the 50MW Steam Generator Test Facility (50MWSGTF). The objectives of the dismantling are reuse of sodium components to a planned large scale thermal hydraulics sodium test facility and the material examination of component that have been operated for long time in sodium. The facility consisted of primary sodium loop with sodium heater by gas burner as heat source instead of reactor, secondary sodium loop with auxiliary cooling system (ACS) and water/steam system with steam temperature and pressure reducer instead of turbine. It simulated the 1 loop of the Monju cooling system. The rated power of the facility was 50MWt and it was about 1/5 of the Monju power plant. Several sodium removal methods are applied. As for the components to be dismantled such as piping, intermediate heat exchanger (IHX), air cooled heat exchangers (AC), sodium is removed by steam with nitrogen gas in the air or sodium is burned in the air. As for steam generators which material tests are planned, sodium is removed by steam injection with nitrogen gas to the steam generator. The steam generator vessel is filled with nitrogen and no air in the steam generator during sodium removal. As for sodium pumps, pump internal structure is pulled out from the casing and installed into the tank. After the installation, sodium is removed by the same method of steam generator. As for relatively small reuse components such as sodium valves, electromagnet flow meters (EMFs) etc., sodium is removed by alcohol process. (author)

  19. Chemical cleaning - essential for optimal steam generator asset management

    International Nuclear Information System (INIS)

    Ammann, Franz

    2009-01-01

    Accumulation of deposits in Steam Generator is intrinsic during the operation of Pressurized Water Reactors. Such depositions lead to reduction of thermal performance, loss of component integrity and, in some cases, to power restrictions. Accordingly, removal of such deposits is an essential part of the asset management program of Steam Generators. Every plant has specific conditions, history and constraints which must be considered when planning and performing a chemical cleaning. Typical points are: -Constitution of the deposits or sludge - Sludge load - Sludge distribution in the steam generator - Existing or expected corrosion problems - Amount and tendency of fouling for waste treatment The strategy for chemical cleaning is developed from these points. The range of chemical cleaning treatments starts with very soft cleanings which can remove approximately 100kg per steam generator and ends with full scale, i.e., hard, cleanings which can remove several thousand kilograms of deposits from a steam generator. Dependent upon the desired goal for the operating plant and the steam generator material condition, the correct cleaning method can be selected. This requires flexible cleaning methods that can be adapted to the individual needs of a plant. Such customizing of chemical cleaning methods is a crucial factor for an optimized asset management program of steam generators in a nuclear power plant

  20. Modelling of steam condensation in the primary flow channel of a gas-heated steam generator

    International Nuclear Information System (INIS)

    Kawamura, H.; Meister, G.

    1982-10-01

    A new simulation code has been developed for the analysis of steam ingress accidents in high temperatures reactors which evaluates the heat transfer in a steam generator headed by a mixture of helium and water steam. Special emphasis is laid on the analysis of steam condensation in the primary circuit of the steam generator. The code takes wall and bulk condensation into account. A new method is proposed to describe the entrainment of water droplets in the primary gas flow. Some typical results are given. Steam condensation in the primary channel may have a significant effect on temperature distributions. The effect on the heat transferred by the steam generator, however, is found to be not so prominent as might be expected. The reason is discussed. A simplified code will also be described, which gives results with reasonable accuracy within much shorter execution times. This code may be used as a program module in a program simulating the total primary circuit of a high temperature reactor. (orig.) [de

  1. Concentration processes under tubesheet sludge piles in nuclear steam generators

    International Nuclear Information System (INIS)

    Gonzalez, F.; Spekkens, P.

    1987-01-01

    The process by which bulk water solutes are concentrated under tubesheet sludge piles in nuclear steam generators was investigated in the laboratory under simulated CANDU operating conditions. Concentration rates were found to depend on the tube heat flux and pile depth, although beyond a critical depth the concentration efficiency decreased. This efficiency could be expressed by a concentration coefficient, and was found to depend also on the sludge pile porosity. Solute concentration profiles in the sludge pile suggested that the concentration mechanism in a high-porosity/permeability pile is characterized by boiling mainly near or at the tube surface, while in low-porosity piles, the change of phase may also become important in the body of the sludge pile. In all cases, the full depth of the pile was active to some extent in the concentration process. As long as the heat transfer under the pile was continued, the solute remained under the pile and slowly migrated toward the bottom. When the heat transfer was stopped, the solute diffused back into the bulk solution at a rate slower than that of the concentration process

  2. Optimum fuel allocation in parallel steam generator systems

    International Nuclear Information System (INIS)

    Bollettini, U.; Cangioli, E.; Cerri, G.; Rome Univ. 'La Sapienza'; Trento Univ.

    1991-01-01

    An optimization procedure was developed to allocate fuels into parallel steam generators. The procedure takes into account the level of performance deterioration connected with the loading history (fossil fuel allocation and maintenance) of each steam generator. The optimization objective function is the system hourly cost, overall steam demand being satisfied. Costs are due to fuel and electric power supply and to plant depreciation and maintenance as well. In order to easily updata the state of each steam generator, particular care was put in the general formulation of the steam production function by adopting a special efficiency-load curve description based on a deterioration scaling parameter. The influence of the characteristic time interval length on the optimum operation result is investigated. A special implementation of the method based on minimum cost paths is suggested

  3. The Creys Malville FBR Super Phenix steam generators

    International Nuclear Information System (INIS)

    Baque, P.; Zuber, T.; Saur, J.M.; Cambillard, E.

    1980-08-01

    After briefly recalling the French experience on sodium steam generators, the authors describe the design concepts of the Superphenix units and give their main characteristics. A short summary of the realized R and D program precedes the description of the four 750-MWt steam generators, the fabrication of which is in progress by Creusot-Loire at Chalon sur Saone (France). The studies started for the next French fast breeder reactors and their steam generators are mentioned

  4. Research perspectives on the evaluation of steam generator tube integrity

    International Nuclear Information System (INIS)

    Muscara, J.; Diercks, D. R.; Majumdar, S.; Kupperman, D. S.; Bakhtiari, S.; Shack, W. J.

    2001-01-01

    Industry effects have been largely successful in managing degradation of steam generator tubes due to wastage, pitting, and denting, but fretting, SCC and intergranular attack have proved more difficult to manage. Although steam generator replacements are proceeding there is substantial industry interest in operating with degraded steam generators, and significant numbers of plants will continue to do so. In most cases degradation of steam generator tubing by stress corrosion cracking is still managed by plug or repair on detection, because current NDE techniques for characterization of flaws are not accurate enough to permit continued operation. This paper reviews some of the historical background that underlies current steam generator degradation management strategies and outlines some of the additional research that must be done to provide more effective management of degradation in current generators and provide greater assurance of satisfactory performance in replacement steam generators

  5. Third international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-12-31

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues.

  6. Third international seminar on horizontal steam generators

    International Nuclear Information System (INIS)

    1995-01-01

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues

  7. Third international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-31

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues.

  8. Highly Flexible and Efficient Solar Steam Generation Device.

    Science.gov (United States)

    Chen, Chaoji; Li, Yiju; Song, Jianwei; Yang, Zhi; Kuang, Yudi; Hitz, Emily; Jia, Chao; Gong, Amy; Jiang, Feng; Zhu, J Y; Yang, Bao; Xie, Jia; Hu, Liangbing

    2017-08-01

    Solar steam generation with subsequent steam recondensation has been regarded as one of the most promising techniques to utilize the abundant solar energy and sea water or other unpurified water through water purification, desalination, and distillation. Although tremendous efforts have been dedicated to developing high-efficiency solar steam generation devices, challenges remain in terms of the relatively low efficiency, complicated fabrications, high cost, and inability to scale up. Here, inspired by the water transpiration behavior of trees, the use of carbon nanotube (CNT)-modified flexible wood membrane (F-Wood/CNTs) is demonstrated as a flexible, portable, recyclable, and efficient solar steam generation device for low-cost and scalable solar steam generation applications. Benefitting from the unique structural merits of the F-Wood/CNTs membrane-a black CNT-coated hair-like surface with excellent light absorbability, wood matrix with low thermal conductivity, hierarchical micro- and nanochannels for water pumping and escaping, solar steam generation device based on the F-Wood/CNTs membrane demonstrates a high efficiency of 81% at 10 kW cm -2 , representing one of the highest values ever-reported. The nature-inspired design concept in this study is straightforward and easily scalable, representing one of the most promising solutions for renewable and portable solar energy generation and other related phase-change applications. © 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim.

  9. Steam generator thermal-hydraulics

    International Nuclear Information System (INIS)

    Inch, W.W.; Scott, D.A.; Carver, M.B.

    1980-01-01

    This paper discusses a code for detailed numerical modelling of steam generator thermal-hydraulics, and describes related experimental programs designed to promote in-depth understanding of three-dimensional two-phase flow. (auth)

  10. Development of steam generator manufacturing technology

    International Nuclear Information System (INIS)

    Grant, J.A.

    1979-01-01

    In 1968 Babcock and Wilcox (Operations) Ltd., received an order from the CEGB to design, manufacture, install and commission 16 Steam Generators for 2 x 660 Mw (e) Advanced Gas Cooled Reactor Power Station at Hartlepool. This order was followed in 1970 by a similar order for the Heysham Power Station. The design and manufacture of the Steam Generators represented a major advance in technology and the paper discusses the methods by which a manufacturing facility was developed, by the Production Division of Babcock, to produce components to a quality, complexity and accuracy unique in the U.K. commercial boilermaking industry. The discussion includes a brief design background, a description of the Steam Generators and a view of the Production Division background. This is followed by a description of the organisation of the technological development and a consideration of the results. (author)

  11. The 2nd international conference on CANDU maintenance. Proceedings

    International Nuclear Information System (INIS)

    1992-01-01

    The conference mainly dealt with all aspects of the maintenance of CANDU power plants, but also included some papers on PWR plants, one on a coal-burning station, and one on robotics for fusion. Volume 1 includes sessions on the following topics: Plenary, Human performance, Maintenance planning and resourcing, Life cycle management, Maintenance cost evaluation and control, Use of special teams, Innovative maintenance techniques, Remote tooling, Reactivity maintenance, Reactor maintenance, Steam generator experience. Out of 34 papers listed under these sessions, one was published as an appendix to Vol. 2, two were published only as loose papers in a virtual supplement, and nine were not published in the proceedings at all. The individual papers have been abstracted separately

  12. The testing of a steam-water separating device used for vertical steam generators

    International Nuclear Information System (INIS)

    Ding Xunshen; Cui Baoyuan; Xue Yunkui; Liu Shixun

    1989-01-01

    The air-water screening tests of a steam-water separating device used for vertical steam generators at low pressure are introduced. The article puts emphasis on the qualification test of the steam-water separating device at hot conditions in a high temperature and pressure water test rig. The performance of the comprehensive test of the steam-water separating device indicates that the humidity of the steam at the drier exit is much less than the specified amount of 0.25%

  13. Electrosleeve process for in-situ nuclear steam generator repair

    International Nuclear Information System (INIS)

    Barton, R.A.; Moran, T.E.; Renaud, E.

    1997-01-01

    Degradation of steam generator (SG) tubing by localized corrosion is a widespread problem in the nuclear industry that can lead to costly forced out-ages, unit de-rating, SG replacement or even the permanent shutdown of a reactor. In response to the onset of SG tubing degradation at Ontario Hydro's Pickering Nuclear Generating Station (PNGS) Unit 5, and the determined unsuitability of conventional repair methods (mechanically expanded or welded sleeves) for Alloy 400, an alternative repair technology was developed. Electrosleeve is a non-intrusive, low-temperature process that involves the electrodeposition of a nanocrystalline nickel microalloy forming a continuously bonded, structural layer over the internal diameter of the degraded region. This technology is designed to provide a long-term pressure boundary repair, fully restoring the structural integrity of the damaged region to its original state. This paper describes the Electrosleeve process for SG tubing repair and the unique properties of the advanced sleeve material. The successful installation of Electrosleeves that have been in service for more than three years in Alloy 400 SG tubing at the Pickering-5 CANDU unit, the more recent extension of the technology to Alloy 600 and its demonstration in a U.S. pressurized water reactor (PWR), is presented. A number of PWR operators have requested plant operating technical specification changes to permit Electrosleeve SG tube repair. Licensing of the Electrosleeve by the U.S. Nuclear Regulatory Commission (NRC) is expected imminently. (author)

  14. Steam generator in the SNR-project

    International Nuclear Information System (INIS)

    van Westenbrugge, J.K.

    1979-01-01

    The design philosophy of steam generators for 1300 MWe LMFBR's is presented. The basis for this philosophy is the present experience with the licensing of the SNR-300. This experience is reported. The approach for the steam generators for the 1300 MWe LMFBR is elaborated on, both for accident prevention and damage limitation, for the component itself as well as for the system design. Both Design Base Accident and Hypothetical Accidents are discussed. 8 refs

  15. Inverted Steam Generators for Sodium Cooled Fast Reactors

    International Nuclear Information System (INIS)

    Matal, Oldřich; Šimo, Tomáš; Matal, Oldřich Jr.

    2013-01-01

    Conclusions: Two inverted steam generators of the Czech industry provenience have still been in successful operation with no water into sodium leaks at BOR 60 (RIAR Dimitrovgrad, Russian Federation). Micromodular inverted steam generator (MMISG) since 1981 and modular inverted steam generator (MISG) since 1991. In the framework of the CP ESFR project predesign studies of 100 MW (thermal) ISG modules were performed with the consideration of MMISG and MISG design, operational and safety benefits and experience. Development of material and technology for sodium heated steam generators components reflecting contemporary domestic industrial conditions in the Czech Republic was restarted in the years 2003 to 2004 and supported in the years 2008 to 2011 by the European CP ESFR project and by the Ministry of Industry and Trade of the Czech Republic

  16. Improvements in steam cycle electric power generating plants

    International Nuclear Information System (INIS)

    Bienvenu, Claude.

    1973-01-01

    The invention relates to a steam cycle electric energy generating plants of the type comprising a fossil or nuclear fuel boiler for generating steam and a turbo alternator group, the turbine of which is fed by the boiler steam. The improvement is characterized in that use is made of a second energy generating group in which a fluid (e.g. ammoniac) undergoes a condensation cycle the heat source of said cycle being obtained through a direct or indirect heat exchange with a portion of the boiler generated steam whereby it is possible without overloading the turbo-alternator group, to accomodate any increase of the boiler power resulting from the use of another fuel while maintaining a maximum energy output. This can be applied to electric power stations [fr

  17. A Receding Horizon Controller for the Steam Generator Water Level

    International Nuclear Information System (INIS)

    Na, Man Gyun; Lee, Yoon Joon

    2003-01-01

    In this work, the receding horizon control method was used to control the water level of nuclear steam generators and applied to two linear models and also a nonlinear model of steam generators. A receding horizon control method is to solve an optimization problem for finite future steps at current time and to implement the first optimal control input as the current control input. The procedure is then repeated at each subsequent instant. The dynamics of steam generators is very different according to power levels. The receding horizon controller is designed by using a reduced linear steam generator model fixed over a certain power range and applied to a Westinghouse-type (U-tube recirculating type) nuclear steam generator. The proposed controller designed at a fixed power level shows good performance for any other power level within this power range. The steam generator shows actually nonlinear characteristics. Therefore, the proposed algorithm is implemented for a nonlinear model of the nuclear steam generator to verify its real performance and also shows good responses

  18. Proceedings of steam generator sludge deposition in recirculating and once through steam generator upper tube bundle and support plates

    International Nuclear Information System (INIS)

    Baker, R.L.; Harvego, E.A.

    1992-01-01

    The development of remedial measures of shot peening have given nuclear utilities viable measures to address primary water stress corrosion cracking to extend steam generator life. The nuclear utility industry is now faced with potential replacement of steam generators in nuclear power plants due to stress corrosion cracking and intergranular attach in crevice locations on the secondary side of steam generators at tube support plates and at the crevice at the top of the tube sheet. Significant work has been done on developing and understanding of the effects of sludge buildup on the corrosion process at these locations. This session was envisioned to provide a forum for the development of an understanding of the mechanisms which control the transport and deposition of sludge on the secondary side of steam generators. It is hoped that this information will aid utilities in monitoring the progression of fouling of these crevices by further knowledge in where to look for the onset of support plate crevice fouling. An understanding of the progression of fouling from upper tube support plates to those lower in the steam generator where higher temperatures cause the corrosion process to initiate first can aid the nuclear utility industry in developing remedial measures for this condition and in providing a forewarning of when to apply such remedial measures

  19. Material choices for the commercial fast reactor steam generators

    International Nuclear Information System (INIS)

    Willby, C.; Walters, J.

    1978-01-01

    Experience with fast reactor steam generators has shown them to be critical components in achieving a high availability. This paper presents the designers views on the use of ferritic materials for steam generators and describes the proposed design of the steam generators for the Commercial Fast Reactor (CFR), prototype of which are to be inserted in the Prototype Fast Reactor at Dounreay. (author)

  20. Monitoring method for steam generator operation

    International Nuclear Information System (INIS)

    Tamaoki, Tetsuo

    1991-01-01

    In an LMFBR plant having an once-through steam generator, reduction of life of a heat transfer pipe caused by heat cycle fatigue is monitored by early finding for the occurrence of abnormality in the inside of the steam generator and by continuous monitoring for the position of departure from nucleate boiling (DNB), which are difficult with existent static characteristic analysis codes. That is, RMS values of fluctuations in temperature signals sent from thermocouples for measuring the fluid temperature in the vicinity of heat transfer pipe disposed along a primary channel of the once-through type steam generator. The abnormality in heat transfer performance is monitored by the distribution change of the RMS values. Subsequently, DNB point on the side of water and steam is determined by the distribution of the RMS value. Then, accumulated values of the product between the time in which the starting point stays in the DNB region and a life consumption amount per unit time given in accordance with the operation condition are monitored. Accordingly, thermal fatigue failure of the heat transfer pipe due to temperature fluctuation in the DNB region is monitored. (I.S.)

  1. Steam generator deposit control program assessment at Comanche Peak

    International Nuclear Information System (INIS)

    Stevens, J.; Fellers, B.; Orbon, S.

    2002-01-01

    Comanche Peak has employed a variety of methods to assess the effectiveness of the deposit control program. These include typical methods such as an extensive visual inspection program and detailed corrosion product analysis and trending. In addition, a recently pioneered technique, low frequency eddy current profile analysis (LFEC) has been utilized. LFEC provides a visual mapping of the magnetite deposit profile of the steam generator. Analysis of the LFEC results not only provides general area deposition rates, but can also provide local deposition patterns, which is indicative of steam generator performance. Other techniques utilized include trending of steam pressure, steam generator hideout-return, and flow assisted corrosion (FAC) results. The sum of this information provides a comprehensive assessment of the deposit control program effectiveness and the condition of the steam generator. It also provides important diagnostic and predictive information relative to steam generator life management and mitigative strategies, such as special cleaning procedures. This paper discusses the techniques employed by Comanche Peak Chemistry to monitor the effectiveness of the deposit control program and describes how this information is used in strategic planning. (authors)

  2. Corrosion aspects in steam generators of nuclear power plants

    International Nuclear Information System (INIS)

    Visoni, E.; Santos Pinto, M. dos

    1988-01-01

    Steam generators of pressurized water reactors (PWR), transfer heat from a primary coolant system to a secondary coolant system. Primary coolant water is heated in the core and passes through the steam generator that transfer heat to the secondary coolant water. However, the steam generator is dead for ionic impurities, corrosion products and fabrication/maintenence residues. These impurities concentrate between crevice and cracks. Many types of degradation mechanisms affect the tubes. The tubes are dented, craked, ovalized, wasted, etc. This paper describes the main corrosion problems in steam generators and includes the corrective actions to considered to reduce or eliminate these corrosion problems. (author) [pt

  3. PMK-2. Experimental study on steam generator behaviour

    Energy Technology Data Exchange (ETDEWEB)

    Ezsoel, G.; Szabados, L.; Trosztel, I. [KFKI Atomic Energy Research Inst., Budabest (Hungary)

    1995-12-31

    The PMK-2 is a full pressure scaled-down model of the Paks Nuclear Power Plant, with a 1:2070 scaling ratio for the volume and power. It has a steam generator model which is a vertical section of the horizontal steam generator. The model has hot and cold collectors similarly to the steam generators of the plant. The heat transfer tubes are horizontal tubes. There are 82 rows of tubes and the elevations, as well as the heat transfer surface distribution is the same as in the plant. The elevation of the feed water supply is similar to that of the plant. To study the temperature distribution in both the primary and the secondary side several thermocouples are built in, in addition to the overall instrumentation of the loop which has again a high number of measurement channels. Paper gives a description and results of SPE-4, with special respect to the steam generator behaviour in both steady state and transient conditions. Axial distribution of coolant and feedwater temperatures are given for the primary and the secondary side of hot and cold collectors and the temperature distribution in the centre of steam generator. (orig.).

  4. PMK-2. Experimental study on steam generator behaviour

    Energy Technology Data Exchange (ETDEWEB)

    Ezsoel, G; Szabados, L; Trosztel, I [KFKI Atomic Energy Research Inst., Budabest (Hungary)

    1996-12-31

    The PMK-2 is a full pressure scaled-down model of the Paks Nuclear Power Plant, with a 1:2070 scaling ratio for the volume and power. It has a steam generator model which is a vertical section of the horizontal steam generator. The model has hot and cold collectors similarly to the steam generators of the plant. The heat transfer tubes are horizontal tubes. There are 82 rows of tubes and the elevations, as well as the heat transfer surface distribution is the same as in the plant. The elevation of the feed water supply is similar to that of the plant. To study the temperature distribution in both the primary and the secondary side several thermocouples are built in, in addition to the overall instrumentation of the loop which has again a high number of measurement channels. Paper gives a description and results of SPE-4, with special respect to the steam generator behaviour in both steady state and transient conditions. Axial distribution of coolant and feedwater temperatures are given for the primary and the secondary side of hot and cold collectors and the temperature distribution in the centre of steam generator. (orig.).

  5. Horizontal steam generator PGV-1000 thermal-hydraulic analysis

    Energy Technology Data Exchange (ETDEWEB)

    Ubra, O. [Skoda Company, Prague (Switzerland); Doubek, M. [Czech Technical Univ., Prague (Switzerland)

    1995-12-31

    A computer program for the steady state thermal-hydraulic analysis of horizontal steam generator PGV-1000 is presented. The program provides the capability to analyze steam generator PGV-1000 primary side flow and temperature distribution, primary side pressure drops, heat transfer between the primary and secondary sides and multidimensional heat flux distribution. A special attention is paid to the thermal-hydraulics of the secondary side. The code predicts 3-D distribution of the void fraction at the secondary side, mass redistribution under the submerged perforated sheet and the steam generator level profile. By means of developed computer program a detailed thermal-hydraulic study of the PGV-1000 has been carried out. A wide range of calculations has been performed and a set of important steam generator characteristics has been obtained. Some of them are presented in the paper. (orig.). 5 refs.

  6. Horizontal steam generator PGV-1000 thermal-hydraulic analysis

    International Nuclear Information System (INIS)

    Ubra, O.; Doubek, M.

    1995-01-01

    A computer program for the steady state thermal-hydraulic analysis of horizontal steam generator PGV-1000 is presented. The program provides the capability to analyze steam generator PGV-1000 primary side flow and temperature distribution, primary side pressure drops, heat transfer between the primary and secondary sides and multidimensional heat flux distribution. A special attention is paid to the thermal-hydraulics of the secondary side. The code predicts 3-D distribution of the void fraction at the secondary side, mass redistribution under the submerged perforated sheet and the steam generator level profile. By means of developed computer program a detailed thermal-hydraulic study of the PGV-1000 has been carried out. A wide range of calculations has been performed and a set of important steam generator characteristics has been obtained. Some of them are presented in the paper. (orig.)

  7. Nuclear steam generator sludge lance method and apparatus

    International Nuclear Information System (INIS)

    Shirey, R.A.; Murray, D.E.

    1991-01-01

    This paper describes a sludge lancing system for removing sludge deposits from an interior region of a steam generator. It comprises: a peripheral fluid injection means for injecting a fluid at a high pressure about a periphery of the steam generator, the peripheral fluid injection means comprising at least one elongated fluid conduit, at least one injection nozzle and a joint positioned at a predetermined point along the elongated fluid conduit for permitting the peripheral fluid injection means to bend to a predetermined angle at the joint within the steam generator; a reciprocable fluid injection means for injecting a fluid at a high pressure toward the sludge deposits and dislodging the sludge deposits; and a supporting means positioned within the interior of the steam generator for supporting the reciprocable fluid injection means throughout the reciprocation of the reciprocable fluid injection means

  8. Horizontal steam generator PGV-1000 thermal-hydraulic analysis

    Energy Technology Data Exchange (ETDEWEB)

    Ubra, O [Skoda Company, Prague (Switzerland); Doubek, M [Czech Technical Univ., Prague (Switzerland)

    1996-12-31

    A computer program for the steady state thermal-hydraulic analysis of horizontal steam generator PGV-1000 is presented. The program provides the capability to analyze steam generator PGV-1000 primary side flow and temperature distribution, primary side pressure drops, heat transfer between the primary and secondary sides and multidimensional heat flux distribution. A special attention is paid to the thermal-hydraulics of the secondary side. The code predicts 3-D distribution of the void fraction at the secondary side, mass redistribution under the submerged perforated sheet and the steam generator level profile. By means of developed computer program a detailed thermal-hydraulic study of the PGV-1000 has been carried out. A wide range of calculations has been performed and a set of important steam generator characteristics has been obtained. Some of them are presented in the paper. (orig.). 5 refs.

  9. Hydrogen-based power generation from bioethanol steam reforming

    Energy Technology Data Exchange (ETDEWEB)

    Tasnadi-Asztalos, Zs., E-mail: tazsolt@chem.ubbcluj.ro; Cormos, C. C., E-mail: cormos@chem.ubbcluj.ro; Agachi, P. S. [Babes-Bolyai University, Faculty of Chemistry and Chemical Engineering, 11 Arany Janos, Postal code: 400028, Cluj-Napoca (Romania)

    2015-12-23

    This paper is evaluating two power generation concepts based on hydrogen produced from bioethanol steam reforming at industrial scale without and with carbon capture. The power generation from bioethanol conversion is based on two important steps: hydrogen production from bioethanol catalytic steam reforming and electricity generation using a hydrogen-fuelled gas turbine. As carbon capture method to be assessed in hydrogen-based power generation from bioethanol steam reforming, the gas-liquid absorption using methyl-di-ethanol-amine (MDEA) was used. Bioethanol is a renewable energy carrier mainly produced from biomass fermentation. Steam reforming of bioethanol (SRE) provides a promising method for hydrogen and power production from renewable resources. SRE is performed at high temperatures (e.g. 800-900°C) to reduce the reforming by-products (e.g. ethane, ethene). The power generation from hydrogen was done with M701G2 gas turbine (334 MW net power output). Hydrogen was obtained through catalytic steam reforming of bioethanol without and with carbon capture. For the evaluated plant concepts the following key performance indicators were assessed: fuel consumption, gross and net power outputs, net electrical efficiency, ancillary consumptions, carbon capture rate, specific CO{sub 2} emission etc. As the results show, the power generation based on bioethanol conversion has high energy efficiency and low carbon footprint.

  10. Hydrogen-based power generation from bioethanol steam reforming

    International Nuclear Information System (INIS)

    Tasnadi-Asztalos, Zs.; Cormos, C. C.; Agachi, P. S.

    2015-01-01

    This paper is evaluating two power generation concepts based on hydrogen produced from bioethanol steam reforming at industrial scale without and with carbon capture. The power generation from bioethanol conversion is based on two important steps: hydrogen production from bioethanol catalytic steam reforming and electricity generation using a hydrogen-fuelled gas turbine. As carbon capture method to be assessed in hydrogen-based power generation from bioethanol steam reforming, the gas-liquid absorption using methyl-di-ethanol-amine (MDEA) was used. Bioethanol is a renewable energy carrier mainly produced from biomass fermentation. Steam reforming of bioethanol (SRE) provides a promising method for hydrogen and power production from renewable resources. SRE is performed at high temperatures (e.g. 800-900°C) to reduce the reforming by-products (e.g. ethane, ethene). The power generation from hydrogen was done with M701G2 gas turbine (334 MW net power output). Hydrogen was obtained through catalytic steam reforming of bioethanol without and with carbon capture. For the evaluated plant concepts the following key performance indicators were assessed: fuel consumption, gross and net power outputs, net electrical efficiency, ancillary consumptions, carbon capture rate, specific CO 2 emission etc. As the results show, the power generation based on bioethanol conversion has high energy efficiency and low carbon footprint

  11. Hydrogen-based power generation from bioethanol steam reforming

    Science.gov (United States)

    Tasnadi-Asztalos, Zs.; Cormos, C. C.; Agachi, P. S.

    2015-12-01

    This paper is evaluating two power generation concepts based on hydrogen produced from bioethanol steam reforming at industrial scale without and with carbon capture. The power generation from bioethanol conversion is based on two important steps: hydrogen production from bioethanol catalytic steam reforming and electricity generation using a hydrogen-fuelled gas turbine. As carbon capture method to be assessed in hydrogen-based power generation from bioethanol steam reforming, the gas-liquid absorption using methyl-di-ethanol-amine (MDEA) was used. Bioethanol is a renewable energy carrier mainly produced from biomass fermentation. Steam reforming of bioethanol (SRE) provides a promising method for hydrogen and power production from renewable resources. SRE is performed at high temperatures (e.g. 800-900°C) to reduce the reforming by-products (e.g. ethane, ethene). The power generation from hydrogen was done with M701G2 gas turbine (334 MW net power output). Hydrogen was obtained through catalytic steam reforming of bioethanol without and with carbon capture. For the evaluated plant concepts the following key performance indicators were assessed: fuel consumption, gross and net power outputs, net electrical efficiency, ancillary consumptions, carbon capture rate, specific CO2 emission etc. As the results show, the power generation based on bioethanol conversion has high energy efficiency and low carbon footprint.

  12. Glas generator for the steam gasification of coal with nuclear generated heat

    International Nuclear Information System (INIS)

    Buchner, G.

    1980-01-01

    The use of heat from a High Temperature Reactor (HTR) for the steam gasification of coal saves coal, which otherwise is burnt to generate the necessary reaction heat. The gas generator for this process, a horizontal pressure vessel, contains a fluidized bed of coal and steam. An ''immersion-heater'' type of heat exchanger introduces the nuclear generated heat to the process. Some special design problems of this gasifier are presented. Reference is made to the present state of development of the steam gasification process with heat from high temperature reactors. (author)

  13. Chemical cleaning an essential part of steam generator asset management

    International Nuclear Information System (INIS)

    Amman, Franz

    2008-01-01

    Chemical Cleaning an essential part of Steam Generator asset management accumulation of deposits is intrinsic for the operation of Steam Generators in PWRs. Such depositions often lead to reduction of thermal performance, loss of component integrity and, in some cases to power restrictions. Accordingly removal of such deposits is an essential part of the asset management of the Steam Generators in a Nuclear Power Plant. Every plant has its individual condition, history and constraints which need to be considered when planning and performing a chemical cleaning. Typical points are: - Sludge load amount and constitution of the deposits - Sludge distribution in the steam generator - Existing or expected corrosion problems - Amount and tendency of fouling for waste treatment Depending on this points the strategy for chemical cleaning shall be evolved. the range of treatment starts with very soft cleanings with a removal of approx 100 kg per steam generator and goes to a full scale cleaning which can remove up to several thousand kilograms of deposits from a steam generator. Depending on the goal to be achieved and the steam generator present an adequate cleaning method shall be selected. This requires flexible and 'customisable' cleaning methods that can be adapted to the individual needs of a plant. Such customizing of chemical cleaning methods is an essential factor for an optimized asset management of the steam generator in a nuclear power plant

  14. Steam generator materials

    International Nuclear Information System (INIS)

    Kim, Joung Soo; Han, J. H.; Kim, H. P.; Lim, Y. S.; Lee, D. H.; Suh, J. H.; Hwang, S. S.; Hur, D. H.; Kim, D. J.; Kim, Y. H.

    2002-05-01

    In order to keep the nuclear power plant(NPP)s safe and increase their operating efficiency, axial stress corrosion cracking(SCC)(IGA/IGSCC, PWSCC, PbSCC) test techniques were developed and SCC property data of the archive steam generator tubing materials having been used in nuclear power plants operating in Korea were produced. The data obtained in this study were data-based, which will be used to clarify the damage mechanisms, to operate the plants safely, and to increase the lifetime of the tubing. In addition, the basic technologies for the improvement of the SCC property of the tubing materials, for new SCC inhibition, for damaged tube repair, and for manufacturing processes of the tubing were developed. In the 1 phase of this long term research, basic SCC test data obtained from the archive steam generator tubing materials used in NPPs operating in Korea were established. These basic technologies developed in the 1 phase will be used in developing process optimization during the 2 phase in order to develop application technologies to the field nuclear power plants

  15. Nuclear steam generator tubesheet shield

    International Nuclear Information System (INIS)

    Nickerson, J.H.D.; Ruhe, A.

    1982-01-01

    The invention involves improvements to a nuclear steam generator of the type in which a plurality of U-shaped tubes are connected at opposite ends to a tubesheet and extend between inlet and outlet chambers, with the steam generator including an integral preheater zone adjacent to the downflow legs of the U-shaped tubes. The improvement is a thermal shield disposed adjacent to an upper face of the tubesheet within the preheater zone, the shield including ductile cladding material applied directly to the upper face of the tubesheet, with the downflow legs of the U-shaped tubes extending through the cladding into the tubesheet

  16. Recent experience related to neutronic transients in Ontario Hydro CANDU nuclear generating stations

    International Nuclear Information System (INIS)

    Frescura, G.M.; Smith, A.J.; Lau, J.H.

    1991-01-01

    Ontario Hydro presently operates 18 CANDU reactors in the province of Ontario, Canada. All of these reactors are of the CANDU Pressurized Heavy Water design, although their design features differ somewhat reflecting the evolution that has taken place from 1971 when the first Pickering unit started operation to the present as the Darlington units are being placed in service. Over the last three years, two significant neutronic transients took place at the Pickering Nuclear Generating Station 'A' (NGS A) one of which resulted in a number of fuel failures. Both events provided valuable lessons in the areas of operational safety, fuel performance And accident analysis. The events and the lessons learned are discussed in this paper

  17. Steam and sodium leak simulation in a fluidized-bed steam generator

    International Nuclear Information System (INIS)

    Vaux, W.G.; Keeton, A.R.; Keairns, D.L.

    1977-01-01

    A fluidized-bed steam generator for the liquid metal fast breeder reactor enhances plant availability and minimizes the probability of a water/sodium reaction. An experimental test program was conceived to assess design criteria and fluidized-bed operation under conditions of water, steam, and sodium leaks. Sodium, steam, and water were leaked into helium-fluidized beds of metal and ceramic particles at 900 F. Test results show the effects of leaks on the heat transfer coefficient, quality of fluidization, leak detection, and cleanup procedures

  18. Steam generator replacement at Surry Power Station

    International Nuclear Information System (INIS)

    McKay, H.S.

    1982-01-01

    The purposes of the steam generator repair program at Surry Power Station were to repair the tube degradation caused by corrosion-related phenomena and to restore the integrity of the steam generators to a level equivalent to new equipment. The repair program consisted of (1) replacing the existing lower-shell assemblies with new ones and (2) adding new moisture separation equipment to the upper-shell assemblies. These tasks required that several pieces of reactor coolant piping, feedwater piping, main steam piping, and the steam generator be cut and refurbished for reinstallation after the new lower shell was in place. The safety implications and other potential effects of the repair program both during the repair work and after the unit was returned to power were part of the design basis of the repair program. The repair program has been completed on Unit 2 without any adverse effects on the health and safety of the general public or to the personnel engaged in the repair work. Before the Unit 1 repair program began, a review of work procedures and field changes for the Unit 2 repair was conducted. Several major changes were made to avoid recurrence of problems and to streamline procedures. Steam generator replacements was completed on June 1, 1981, and the unit is presently in the startup phase of the outrage

  19. Steam generator life management

    International Nuclear Information System (INIS)

    King, P.; McGillivray, R.; Reinhardt, W.; Millman, J.; King, B.; Schneider, W.

    2003-01-01

    'Full-Text:' Steam Generator Life Management responsibility embodies doing whatever is necessary to maintain the steam generation equipment of a nuclear plant in effective, reliable service. All comes together in that most critical deliverable, namely the submission of the documentation which wins approval for return to service after an outage program. Life management must address all aspects of SG reliability over the life of the plant. Nevertheless, the life management activities leading up to return to service approval is where all of it converges. Steam Generator Life Management activities entail four types of work, all equally important in supporting the objective of successful operation. These activities are i) engineering functions; including identification of inspection and maintenance requirements, outage planning and scope definition plus engineering assessment, design and analysis as necessary to support equipment operation, ii) fitness of service work; including the expert evaluation of degradation mechanisms, disposition of defects for return to service or not, and the fitness for service analysis as required to justify ongoing operation with acceptable defects, iii) inspection work; including large scale eddy current inspection of tubing, the definition of defect size and character, code inspections of pressure vessel integrity and visual inspections for integrity and iv) maintenance work; including repairs, retrofits, cleaning and modifications, all as necessary to implement the measures defined during activities i) through iii). The paper discusses the approach and execution of the program for the achievement of the above objectives and particularly of items i) and ii). (author)

  20. Emergency makeup of nuclear steam generators in blackout conditions

    International Nuclear Information System (INIS)

    Korolev, A.V.; Derevyanko, O.V.

    2014-01-01

    The paper describes an original solution for using steam energy to organize makeup of NPP steam generators in blackout conditions. The proposed solution combines a disk friction turbine and an axial turbine in a single housing to provide a high overall technical effect enabling the replenishment of nuclear steam generators with steam using the pump turbine drive assembly. The application of the design is analyzed and its efficiency and feasibility are shown

  1. A CANDU designed for more tolerance to failures in large components

    International Nuclear Information System (INIS)

    Spinks, N.J.; Barclay, F.W.; Allen, P.J.; Yee, F.

    1988-06-01

    Current designs of CANDU reactors have several groups of fuel channels each served by an upstream coolant supply-train consisting of an outlet header, a steam generator, one or more pumps in parallel and an inlet header. Postulated failures in these large components put the heaviest demands on the safety systems. For example, the rupture of a header sets the requirements for the speed of shutdown and for the speed and capacity of emergency coolant injection, and it has a large impact on containment design. A CANDU design is being investigated to reduce the impact of failures in large components. Each group of fuel channels is supplied by more than one train so that if one train fails the rest continue to work. Reverse flow limiters reduce the loss-of-coolant from the unbroken trains to a broken supply train. The paper describes several design options for making the piping connections from multi supply-trains to fuel channels. It discusses progress in design and testing of flow limiters. A preliminary analysis is given of affected accidents

  2. Fifth CNS international steam generator conference

    International Nuclear Information System (INIS)

    2006-01-01

    The Fifth CNS International Steam Generator Conference was held on November 26-29, 2006 in Toronto, Ontario, Canada. In contrast with other conferences which focus on specific aspects, this conference provided a wide ranging forum on nuclear steam generator technology from life-cycle management to inspection and maintenance, functional and structural performance characteristics to design architecture. The 5th conference has adopted the theme: 'Management of Real-Life Equipment Conditions and Solutions for the Future'. This theme is appropriate at a time of transition in the industry when plants are looking to optimize the performance of existing assets, prevent costly degradation and unavailability, while looking ahead for new steam generator investments in life-extension, replacements and new-build. More than 50 technical papers were presented in sessions that gave an insight to the scope: life management strategies; fouling, cleaning and chemistry; replacement strategies and new build design; materials degradation; condition assessment/fitness for service; inspection advancements and experience; and thermal hydraulic performance

  3. Evaluation of Oconee steam-generator debris. Final report

    International Nuclear Information System (INIS)

    Rigdon, M.A.; Rubright, M.M.; Sarver, L.W.

    1981-10-01

    Pieces of debris were observed near damaged tubes at the 14th support plate elevation in the Oconee 1-B steam generator. A project was initiated to evaluate the physical and chemical nature of the debris, to identify its source, and to determine its role in tube damage at this elevation. Various laboratory techniques were used to characterize several debris and mill scale samples. Data from these samples were then compared with each other and with literature data. It was concluded that seven of eight debris samples were probably formed in the steam generator. Six of these samples were probably formed by high temperature aqueous corrosion early in the life of the steam generator. The seventh sample was probably formed by the deposition and spalling of magnetite on the Inconel steam generator tubes. None of the debris samples resembled any of the mill scale samples

  4. Steam generators under construction for the SNR-300 power plant

    Energy Technology Data Exchange (ETDEWEB)

    Essebaggers, J

    1975-07-01

    The prototype straight tube and the helical coil-steam generator has been designed and fabricated of which the straight tube steam generator has been successfully tested for over 3000 hours at prototypical conditions and is presently being dismantled for detailed examination of critical designed features. The prototype helical coil steam generator is presently under testing in the 50 MWt test facility at TNO-Hengelo with approximately 500 hours of operation at full load conditions. In an earlier presentation the design and fabrication of the prototype steam generators have been presented, while for this presentation the production units for SNR-300 will be discussed. Some preliminary information will be presented at this meeting of the dismantling operations of the prototype straight tube steam generator. (author)

  5. Steam generators under construction for the SNR-300 power plant

    International Nuclear Information System (INIS)

    Essebaggers, J.

    1975-01-01

    The prototype straight tube and the helical coil-steam generator has been designed and fabricated of which the straight tube steam generator has been successfully tested for over 3000 hours at prototypical conditions and is presently being dismantled for detailed examination of critical designed features. The prototype helical coil steam generator is presently under testing in the 50 MWt test facility at TNO-Hengelo with approximately 500 hours of operation at full load conditions. In an earlier presentation the design and fabrication of the prototype steam generators have been presented, while for this presentation the production units for SNR-300 will be discussed. Some preliminary information will be presented at this meeting of the dismantling operations of the prototype straight tube steam generator. (author)

  6. Control system for fluid heated steam generator

    Science.gov (United States)

    Boland, J.F.; Koenig, J.F.

    1984-05-29

    A control system for controlling the location of the nucleate-boiling region in a fluid heated steam generator comprises means for measuring the temperature gradient (change in temperature per unit length) of the heating fluid along the steam generator; means for determining a control variable in accordance with a predetermined function of temperature gradients and for generating a control signal in response thereto; and means for adjusting the feedwater flow rate in accordance with the control signal.

  7. Steam generator secondary pH during a steam generator tube rupture

    International Nuclear Information System (INIS)

    Adams, J.P.; Peterson, E.S.

    1991-12-01

    The Nuclear Regulatory Commission requires utilizes to determine the response of a pressurized water reactor to a steam generator tube rupture (SGTR) as part of the safety analysis for the plant. The SGTR analysis includes assumptions regarding the partitioning of iodine between liquid and vapor in steam generator secondary. Experimental studies have determined that the partitioning of iodine in water is very sensitive to the pH. Based on this experimental evidence, the NRC requested the INEL to perform an analytical assessment of secondary coolant system (SCS) pH during an SGTR. Design basis thermal and hydraulic calculations were used together with industry standard chemistry guidelines to determine the SCS chemical concentrations during an SGTR. These were used as input to the Facility for Analysis of Chemical Thermodynamics computer system to calculate the equilibrium pH in the SCS at various discrete time during an SGTR. The results of this analysis indicate that the SCS pH decreases from the initial value of 8.8 to approximately 6.5 by the end of the transient, independent of PWR design

  8. The supply of steam from Candu reactors for heavy water production

    International Nuclear Information System (INIS)

    Robertson, R.F.S.

    1975-09-01

    By 1980, Canada's energy needs for D 2 O production will be 420 MW of electrical energy and 3600 MW of thermal energy (as steam). The nature of the process demands that this energy supply be exceptionally stable. Today, production plants are located at or close to nuclear electricity generating sites where advantage can be taken of the low cost of both the electricity and steam produced by nuclear reactors. Reliability of energy supply is achieved by dividing the load between the multiple units which comprise the sites. The present and proposed means of energy supply to the production sites at the Bruce Heavy Water Plant in Ontario and the La Prade Heavy Water Plant in Quebec are described. (author)

  9. Steam generator replacement: a story of continuous improvement

    International Nuclear Information System (INIS)

    Sills, M.S.; Wilkerson, R.

    2009-01-01

    This paper provides a review of the history of steam generator replacement in the US focusing on the last five years. From the early replacements in the 1980s, there have been major technology improvements resulting in dramatically shorter outages and reduced radiological exposure for workers. Even though the changes for the last five years have been less dramatic, the improvement trend continues. No two steam generator replacement (SGR) projects are the same and there are some major differences including; the access path for the components to containment (is a construction opening in containment required), type of containment, number of steam generators, one piece or two piece replacement, plant type (Westinghouse, CE or B and W) and plant layout. These differences along with other variables such as delays due to plant operations and other activities not related to the steam generator replacement make analysis of performance data difficult. However, trends in outage performance and owner expectations can be identified. How far this trend will go is also discussed. Along with the trend of improved performance, there is also a significant variation in performance. Some of the contributors to this variation are identified. This paper addresses what is required for a successful outage, meeting the increasing expectations and setting new records. The authors will discuss various factors that contribute to the success of a steam generator replacement. These factors include technical issues and, equally important, organizational interface and the role the customer plays. Recommendations are provided for planning a successful steam generator replacement outage. (author)

  10. Nuclear steam generator tube to tubesheet joint optimization

    International Nuclear Information System (INIS)

    McGregor, Rod

    1999-01-01

    Industry-wide problems with Stress Corrosion Cracking in the Nuclear Steam Generator tube-to-tubesheet joint have led to costly repairs, plugging, and replacement of entire vessels. To improve corrosion resistance, new and replacement Steam Generator developments typically employ the hydraulic tube expansion process (full depth) to minimize tensile residual stresses and cold work at the critical transition zone between the expanded and unexpanded tube. These variables have undergone detailed study using specialized X-ray diffraction and analytical techniques. Responding to increased demands from Nuclear Steam Generator operators and manufacturers to credit the leak-tightness and strength contributions of the hydraulic expansion, various experimental tasks with complimentary analytical modelling were applied to improve understanding and control of tube to hole contact pressure. With careful consideration to residual stress impact, design for strength/leak tightness optimization addresses: Experimentally determined minimum contact pressure levels necessary to preclude incipient leakage into the tube/hole interface. The degradation of contact pressure at surrounding expansions caused by the sequential expansion process. The transient and permanent contact pressure variation associated with tubesheet hole dilation during Steam Generator operation. An experimental/analytical simulation has been developed to reproduce cyclic Steam Generator operating strains on the tubesheet and expanded joint. Leak tightness and pullout tests were performed during and following simulated Steam Generator operating transients. The overall development has provided a comprehensive understanding of the fabrication and in-service mechanics of hydraulically expanded joints. Based on this, the hydraulic expansion process can be optimized with respect to critical residual stress/cold work and the strength/leakage barrier criteria. (author)

  11. Advanced life-cycle management for an increased steam generator performance

    International Nuclear Information System (INIS)

    Beck, J.; Schwarz, T.; Bouecke, R.; Schneider, V.

    2006-01-01

    High steam generators performance is a prerequisite for high plant availability and possible life time extension. During operation, the performance is reduced by fouling of the heating tubes and by corrosion, resulting on a reduction of the heat-exchange area. Such steam generator degradation problems arise from mechanical degradation and a continuous ingress of non-volatile contaminants, i.e. corrosion products and salt impurities accumulated in the steam generators. In addition, the tube scales in general affect the steam generator thermal performance, which ultimately cause a reduction of power output. AREVA applied an integrated service for utilities to evaluate all operational parameters influencing the steam generator performance. The evaluation is assisted by a systematic approach to evaluate the major steam generator operational data. The different data are structured and indexed in a Cleanling-Matrix. The result of this matrix is a quantified, dimensionless figure, given as the Fouling Index. The Fouling Index allows to monitor the condition of steam generators, compare it to other plants and, in combination with a life-time management applied at several German utilities, it allows verified statements on the past operation. Based on these data, an extrapolation of the potential additional life-time of the component is possible. As such, the Fouling Index is a valuable tool concerning life-time extension considerations. The application of the cleanliness criteria in combination with operational data with respect to life-time monitoring and improvements of steam generator performance are presented. (author)

  12. Steam Generator Group Project. Annual report, 1982

    International Nuclear Information System (INIS)

    Clark, R.A.; Lewis, M.

    1984-02-01

    The Steam Generator Group Project (SGGP) is an NRC program joined by additional sponsors. The SGGP utilizes a steam generator removed from service at a nuclear plant (Surry 2) as a vehicle for research on a variety of safety and reliability issues. This report is an annual summary of progress of the program for 1982. Information is presented on the Steam Generator Examination Facility (SGEF), especially designed and constructed for this research. Loading of the generator into the SGEF is then discussed. The report then presents radiological field mapping results and personnel exposure monitoring. This is followed by information on field reduction achieved by channel head decontaminations. The report then presents results of a secondary side examination through shell penetrations placed prior to transport, confirming no change in generator condition due to transport. Decontamination of the channel head is discussed followed by plans for eddy current testing and removal of the plugs placed during service. Results of a preliminary profilometry examination are then provided

  13. Functional performance of the helical coil steam generator, Consolidated Nuclear Steam Generator (CNSG) IV system. Executive summary report

    International Nuclear Information System (INIS)

    Watson, G.B.

    1975-10-01

    The objective of this project was to study the functional performance of the CNSG - IV helical steam generator to demonstrate that the generator meets steady-state and transient thermal-hydraulic performance specifications and that secondary flow instability will not be a problem. Economic success of the CNSG concepts depends to a great extent on minimizing the size of the steam generator and the reactor vessel for ship installation. Also, for marine application the system must meet stringent specifications for operating stability, transient response, and control. The full-size two-tube experimental unit differed from the CNSG only in the number of tubes and the mode of primary flow. In general, the functional performance test demonstrated that the helical steam generator concept will exceed the specified superheat of 35F at 100% load. The experimental measured superheat at comparable operating conditions was 95F. Testing also revealed that available computer codes accurately predict trends and overall performance characteristics

  14. Mushrooms as Efficient Solar Steam-Generation Devices.

    Science.gov (United States)

    Xu, Ning; Hu, Xiaozhen; Xu, Weichao; Li, Xiuqiang; Zhou, Lin; Zhu, Shining; Zhu, Jia

    2017-07-01

    Solar steam generation is emerging as a promising technology, for its potential in harvesting solar energy for various applications such as desalination and sterilization. Recent studies have reported a variety of artificial structures that are designed and fabricated to improve energy conversion efficiencies by enhancing solar absorption, heat localization, water supply, and vapor transportation. Mushrooms, as a kind of living organism, are surprisingly found to be efficient solar steam-generation devices for the first time. Natural and carbonized mushrooms can achieve ≈62% and ≈78% conversion efficiencies under 1 sun illumination, respectively. It is found that this capability of high solar steam generation is attributed to the unique natural structure of mushroom, umbrella-shaped black pileus, porous context, and fibrous stipe with a small cross section. These features not only provide efficient light absorption, water supply, and vapor escape, but also suppress three components of heat losses at the same time. These findings not only reveal the hidden talent of mushrooms as low-cost materials for solar steam generation, but also provide inspiration for the future development of high-performance solar thermal conversion devices. © 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim.

  15. CANDU 9 fuelling machine carriage

    Energy Technology Data Exchange (ETDEWEB)

    Ullrich, D J; Slavik, J F [Atomic Energy of Canada Ltd., Saskatoon, SK (Canada)

    1997-12-31

    Continuous, on-power refuelling is a key feature of all CANDU reactor designs and is essential to maintaining high station capacity factors. The concept of a fuelling machine carriage can be traced to the early CANDU designs, such as the Douglas Point Nuclear Generating Station. In the CANDU 9 480NU unit, the combination of a mobile carriage and a proven fuelling machine head design comprises an effective means of transporting fuel between the reactor and the fuel transfer ports. It is a suitable alternative to the fuelling machine bridge system that has been utilized in the CANDU 6 reactor units. The CANDU 9 480NU fuel handling system successfully combines features that meet the project requirements with respect to fuelling performance, functionality, seismic qualification and the use of proven components. The design incorporates improvements based on experience and applicable current technologies. (author). 4 figs.

  16. CANDU 9 fuelling machine carriage

    International Nuclear Information System (INIS)

    Ullrich, D.J.; Slavik, J.F.

    1996-01-01

    Continuous, on-power refuelling is a key feature of all CANDU reactor designs and is essential to maintaining high station capacity factors. The concept of a fuelling machine carriage can be traced to the early CANDU designs, such as the Douglas Point Nuclear Generating Station. In the CANDU 9 480NU unit, the combination of a mobile carriage and a proven fuelling machine head design comprises an effective means of transporting fuel between the reactor and the fuel transfer ports. It is a suitable alternative to the fuelling machine bridge system that has been utilized in the CANDU 6 reactor units. The CANDU 9 480NU fuel handling system successfully combines features that meet the project requirements with respect to fuelling performance, functionality, seismic qualification and the use of proven components. The design incorporates improvements based on experience and applicable current technologies. (author). 4 figs

  17. Fission products distributions in Candu primary heat transport and Candu containment systems during a severe accident

    International Nuclear Information System (INIS)

    Constantin, Marin; Rizoiu, Andrei

    2005-01-01

    The paper is intended to analyse the distribution of the fission products (FPs) in CANDU Primary Heat Transport (PHT) and CANDU Containment Systems by using the ASTEC code (Accident Source Term Evaluation Code). The complexity of the data required by ASTEC and the complexity both of CANDU PHT and Containment System were strong motivations to begin with a simplified geometry in order to avoid the introducing of unmanageable errors at the level of input deck. Thus only 1/4 of the PHT circuit was simulated and a simplified FPs inventory, some simplifications in the feeders geometry and containment were used. The circuit consists of 95 horizontal fuel channels connected to 95 horizontal out-feeders, then through vertical feeders to the outlet-header (a big pipe that collects the water from feeders); the circuit continues from the outlet-header with a riser and then with the steam generator and a pump. After this pump, the circuit was broken; in this point the FPs are transferred to the containment. The containment model consists of 4 rooms connected between by 6 links. The data related to the nodes' definitions, temperatures and pressure conditions were chosen as possible as real data from CANDU NPP loss of coolant accident sequence. Temperature and pressure conditions in the time of the accident were calculated by the CATHENA code and the source term of FPs introduced into the PHT was estimated by the ORIGEN code. The FPs distribution in the nodes of the circuit and the FPs mass transfer per isotope and chemical species are obtained by using SOPHAEROS module of ASTEC code. The distributions into the containment are obtained by the CPA module of ASTEC code (thermalhydraulics calculations in the containment and FPs aerosol transport). The results consist of mass distributions in the nodes of the circuit and the transferred mass to the containment through the break for different species (FPs and chemical species) and mass distributions in the different parts and

  18. A study on improving the performance of steam generator using thermal analysis

    International Nuclear Information System (INIS)

    Li, Zhen Zhe; Heo, Kwang Su; Choi, Jun Hoo; Seol, Seoung Yun

    2008-01-01

    Steam generation mechanism is the key technology of domestic steam cleaner. Not only weight and price of steam cleaner but also the performance of steam generation mechanism must be considered to improve the competitive power of the products. In order to find out the mechanism which can be used to improve the performance of steam generator, the process of steam generation was studied at first. In the following step, possibility of control, safety of mechanism and etc were compared about the two candidated steam generation mechanism. Finally, the merit and drawback of each mechanism were summarized

  19. Status of steam generator tubing integrity at Jaslovske Bohunice NPP

    International Nuclear Information System (INIS)

    Cepcek, S.

    1997-01-01

    Steam generator represents one of the most important component of nuclear power plants. Especially, loss of tubing integrity of steam generators can lead to the primary coolant leak to secondary circuit and in worse cases to the unit shut down or to the PTS events occurrence. Therefore, to ensure the steam generator tubing integrity and the current knowledge about tube degradation propagation and development is of the highest importance. In this paper the present status of steam generator tubing integrity in operated NPP in Slovak Republic is presented

  20. Steam generator assessment for sustainable power plant operation

    International Nuclear Information System (INIS)

    Drexler, Andreas; Fandrich, Joerg; Ramminger, Ute; Montaner-Garcia, Violeta

    2012-09-01

    Water and steam serve in the water-steam cycle as the energy transport and work media. These fluids shall not affect, through corrosion processes on the construction materials and their consequences, undisturbed plant operation. The main objectives of the steam water cycle chemistry consequently are: - The metal release rates of the structural materials shall be minimal - The probability of selective / localized forms of corrosion shall be minimal. - The deposition of corrosion products on heat transfer surfaces shall be minimized. - The formation of aggressive media, particularly local aggressive environments under deposits, shall be avoided. These objectives are especially important for the steam generators (SGs) because their condition is a key factor for plant performance, high plant availability, life time extension and is important to NPP safety. The major opponent to that is corrosion and fouling of the heating tubes. Effective ways of counteracting all degradation problems and thus of improving the SG performance are to keep SGs in clean conditions or if necessary to plan cleaning measures such as mechanical tube sheet lancing or chemical cleaning. Based on more than 40 years of experience in steam-water cycle water chemistry treatment AREVA developed an overall methodology assessing the steam generator cleanliness condition by evaluating all available operational and inspection data together. In order to gain a complete picture all relevant water chemistry data (e.g. corrosion product mass balances, impurity ingress), inspection data (e.g. visual inspections and tube sheet lancing results) and thermal performance data (e.g. heat transfer calculations) are evaluated, structured and indexed using the AREVA Fouling Index Tool Box. This Fouling Index Tool Box is more than a database or statistical approach for assessment of plant chemistry data. Furthermore the AREVA's approach combines manufacturer's experience with plant data and operates with an

  1. Steam generator materials performance in high temperature gas-cooled reactors

    International Nuclear Information System (INIS)

    Chafey, J.E.; Roberts, D.I.

    1980-11-01

    This paper reviews the materials technology aspects of steam generators for HTGRs which feature a graphite-moderated, uranium-thorium, all-ceramic core and utilizes high-pressure helium as the primary coolant. The steam generators are exposed to gas-side temperatures approaching 760 0 C and produce superheated steam at 538 0 C and 16.5 MPa (2400 psi). The prototype Peach Bottom I 40-MW(e) HTGR was operated for 1349 EFPD over 7 years. Examination after decommissioning of the U-tube steam generators and other components showed the steam generators to be in very satisfactory condition. The 330-MW(e) Fort St. Vrain HTGR, now in the final stages of startup, has achieved 70% power and generated more than 1.5 x 10 6 MWh of electricity. The steam generators in this reactor are once-through units of helical configuration, requiring a number of new materials factors including creep-fatigue and water chemistry control. Current designs of larger HTGRs also feature steam generators of helical once-through design. Materials issues that are important in these designs include detailed consideration of time-dependent behavior of both base metals and welds, as required by current American Society of Mechanical Engineers (ASME) Code rules, evaluation of bimetallic weld behavior, evaluation of the properties of large forgings, etc

  2. New steam generators slated for nuclear units

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This article is a brief discussion of Duke Power's plans to replace steam generators at its McGuire and Catawba nuclear units. A letter of intent to purchase (from Babcock and Wilcox) the 12 Westinghouse steam generators has been signed, but no constructor has been selected at this time. This action is brought about by the failures of more than 3000 tubes in these units

  3. Soviet steam generator technology: fossil fuel and nuclear power plants

    International Nuclear Information System (INIS)

    Rosengaus, J.

    1987-01-01

    In the Soviet Union, particular operational requirements, coupled with a centralized planning system adopted in the 1920s, have led to a current technology which differs in significant ways from its counterparts elsewhere in the would and particularly in the United States. However, the monograph has a broader value in that it traces the development of steam generators in response to the industrial requirements of a major nation dealing with the global energy situation. Specifically, it shows how Soviet steam generator technology evolved as a result of changing industrial requirements, fuel availability, and national fuel utilization policy. The monograph begins with a brief technical introduction focusing on steam-turbine power plants, and includes a discussion of the Soviet Union's regional power supply (GRES) networks and heat and power plant (TETs) systems. TETs may be described as large central co-generating stations which, in addition to electricity, provide heat in the form of steam and hot water. Plants of this type are a common feature of the USSR today. The adoption of these cogeneration units as a matter of national policy has had a central influence on Soviet steam generator technology which can be traced throughout the monograph. The six chapters contain: a short history of steam generators in the USSR; steam generator design and manufacture in the USSR; boiler and furnace assemblies for fossil fuel-fired power stations; auxiliary components; steam generators in nuclear power plants; and the current status of the Soviet steam generator industry. Chapters have been abstracted separately. A glossary is included containing abbreviations and acronyms of USSR organizations. 26 references

  4. Chemical cleaning of nuclear (PWR) steam generators

    International Nuclear Information System (INIS)

    Welty, C.S. Jr.; Mundis, J.A.

    1982-01-01

    This paper reports on a significant research program sponsored by a group of utilities (the Steam Generator Owners Group), which was undertaken to develop a process to chemically remove corrosion product deposits from the secondary side of pressurized water reactor (PWR) power plant steam generators. Results of this work have defined a process (solvent system and application methods) that is capable of removing sludge and tube-to-tube support plate crevice corrosion products generated during operation with all-volatile treatment (AVT) water chemistry. Considers a plant-specific test program that includes all materials in the steam generator to be cleaned and accounts for the physical locations (proximity and contact) of those materials. Points out that prior to applying the process in an operational unit, the utility, with the participation of the NSSR vendor, must define allowable total corrosion to the materials of construction of the unit

  5. Steam generator operating experience: Update for 1984-1986

    International Nuclear Information System (INIS)

    Frank, L.; Stokley, J.

    1988-06-01

    This report summarizes operational events and degradation mechanisms affecting pressurized water reactor steam generator integrity, provides updated inspection results reported in 1984, 1985, and 1986, and highlights both prevalent problem areas and advances in improved equipment test practices, preventive measures, repair techniques, and replacement procedures. It describes equipment design features of the three major suppliers and discusses 68 plants in detail. Steam generator degradation mechanisms include intergranular stress corrosion cracking, primary water stress corrosion cracking, pitting, intergranular attack, and vibration wear that effects tube integrity and causes leakage. Plugging, sleeving heat treatment, peening, chemical cleaning, and steam generator replacements are described and regulatory instruments and inspection guidelines for nondestructive evaluations and girth weld cracking are discusses. The report concludes that although degradation mechanisms are generally understood, the elimination of unscheduled plant shutdowns and costly repairs resulting from leaking tubes has not been achieved. Highlights of steam generator research and unresolved safety issues are discussed. 21 refs., 8 tabs

  6. Chemical-cleaning process evaluation: Westinghouse steam generators. Final report

    International Nuclear Information System (INIS)

    Cleary, W.F.; Gockley, G.B.

    1983-04-01

    The Steam Generator Owners Group (SGOG)/Electric Power Research Institute (EPRI) Steam Generator Secondary Side Chemical Cleaning Program, under develpment since 1978, has resulted in a generic process for the removal of accumulated corrosion products and tube deposits in the tube support plate crevices. The SGOG/EPRI Project S150-3 was established to obtain an evaluation of the generic process in regard to its applicability to Westinghouse steam generators. The results of the evaluation form the basis for recommendations for transferring the generic process to a plant specific application and identify chemical cleaning corrosion guidelines for the materials in Westinghouse Steam Generators. The results of the evaluation, recommendations for plant-specific applications and corrosion guidelines for chemical cleaning are presented in this report

  7. Upgraded Steam Generator Lancing System for Uljin NPP no.2

    International Nuclear Information System (INIS)

    Kim, Seok Tae; Jeong, Woo Tae; Hong, Sung Yull

    2005-01-01

    KEPRI(Korea Electric Power Research Institute) has developed various types of steam generator lancing systems since 1998. In this paper, we introduce a new lancing system with new improvements from the previous steam generator lancing system for Uljin NPP #2(nuclear power plant) constructed by KEPRI. The previous lancing system is registered as KALANS R -II and was developed for System-80 type steam generators. The previous lancing system was applied to Uljin unit #3 and it lowered radiation exposure of operators in comparison to manually operated lancing systems. And it effectively removed sludge accumulated around kidney bean zone in the Uljin unit #3 steam generators. But the previous lancing system could only clean partially the steam generators of Uljin unit #4. This was because the rail of the previous lancing system interfered with a part of the steam generator. Therefore we developed a new lancing system that can solve the interference problem. This new lancing system was upgraded from the previous lancing system. Also, a new lancing system for System-80 S/G will be introduced in this paper

  8. The progress of test and study for steam dryer in vertical steam generator

    International Nuclear Information System (INIS)

    Ding Xunshen

    1993-01-01

    Constructions, tests and test results are reviewed for three types of steam generator dryer that are concentric vertical corrugated separator, centrifugal conic separator and chevron separator. The last type is considered as the best one in comparison, which has been applied to Qinshan 300 MW steam generator. A number of pertinent remarks to draining scheme, hydraulic loss reduction, and conduct of test are given based on experiences

  9. Thermal-hydraulic characteristic of the PGV-1000 steam generator

    International Nuclear Information System (INIS)

    Ubra, O.; Doubek, M.

    1995-01-01

    Horizontal steam generators are typical parts of nuclear power plants with pressure water reactor type VVER. By means of this computer program, a detailed thermal-hydraulic study of the horizontal steam generator PGV-1000 has been carried out and a special attention has been paid to the thermal-hydraulics of the secondary side. A set of important steam generator characteristics has been obtained and analyzed. Some of the interesting results of the analysis are presented in the paper. (author)

  10. Sodium and steam leak simulation studies for fluidized bed steam generators

    International Nuclear Information System (INIS)

    Keeton, A.R.; Vaux, W.G.; Lee, P.K.; Witkowski, R.E.

    1976-01-01

    An experimental program is described which was conducted to study the effects of sodium or steam leaking into an operating fluidized bed of metal or ceramic particles at 680 to 800 0 K. This effort was part of the early development studies for a fluidized-bed steam generator concept using helium as the fluidizing gas. Test results indicated that steam and small sodium leaks had no effect on the quality of fluidization, heat transfer coefficient, temperature distribution, or fluidizing gas pressure drop across the bed. Large sodium leaks, however, immediately upset the operation of the fluidized bed. Both steam and sodium leaks were detected positively and rapidly at an early stage of a leak by instruments specifically selected to accomplish this

  11. Steam generator waterlancing at DNGS

    International Nuclear Information System (INIS)

    Seppala, D.; Malaugh, J.

    1995-01-01

    Darlington Nuclear Generating Station (DNGS) is a four 900 MW Unit nuclear station forming part of the Ontario Hydro East System. There are four identical steam generators(SGs) per reactor unit. The Darlington SGs are vertical heat exchangers with an inverted U-tube bundle in a cylindrical shell. The DNGS Nuclear Plant Life Assurance Group , a department of DNGS Engineering Services have taken a Proactive Approach to ensure long term SG integrity. Instead of waiting until the tubesheets are covered by a substantial and established hard deposit; DNGS plan to clean each steam generator's tubesheet, first half lattice tube support assembly and bottom of the thermal plate every four years. The ten year business plan provides for cleaning and inspection to be conducted on all four SGs in each unit during maintenance outages (currently scheduled for every four years)

  12. Clinch river breeder reactor plant steam generator water quality

    Energy Technology Data Exchange (ETDEWEB)

    Van Hoesen, D; Lowe, P A

    1975-07-01

    The recent problems experienced by some LWR Steam Generators have drawn attention to the importance of system water quality and water/ steam side corrosion. Several of these reactor plants have encountered steam generator failures due to accelerated tube corrosion caused, in part, by poor water quality and corrosion control. The CRBRP management is aware of these problems, and the implications that they have for the Clinch River Breeder Reactor Plant (CPBRP) Steam Generator System (SGS). Consequently, programs are being implemented which will: (1) investigate the corrosion mechanisms which may be present in the CRBRP SGS; (2) assure steam generator integrity under design and anticipated off-normal water quality conditions; and (3) assure that the design water quality levels are maintained at all times. However, in order to understand the approach being used to examine this potential problem, it is first necessary to look at the CRBRP SGS and the corrosion mechanisms which may be present.

  13. Clinch river breeder reactor plant steam generator water quality

    International Nuclear Information System (INIS)

    Van Hoesen, D.; Lowe, P.A.

    1975-01-01

    The recent problems experienced by some LWR Steam Generators have drawn attention to the importance of system water quality and water/ steam side corrosion. Several of these reactor plants have encountered steam generator failures due to accelerated tube corrosion caused, in part, by poor water quality and corrosion control. The CRBRP management is aware of these problems, and the implications that they have for the Clinch River Breeder Reactor Plant (CPBRP) Steam Generator System (SGS). Consequently, programs are being implemented which will: 1) investigate the corrosion mechanisms which may be present in the CRBRP SGS; 2) assure steam generator integrity under design and anticipated off-normal water quality conditions; and 3) assure that the design water quality levels are maintained at all times. However, in order to understand the approach being used to examine this potential problem, it is first necessary to look at the CRBRP SGS and the corrosion mechanisms which may be present

  14. Steam generator replacement at the Obrigheim nuclear power station

    International Nuclear Information System (INIS)

    Pickel, E.; Schenk, H.; Huemmler, A.

    1984-01-01

    The Obrigheim Nuclear Power Station (KWO) is equipped with a dual-loop pressurized water reactor of 345 MW electric power; it was built by Siemens in the period 1965 to 1968. By the end of 1983, KWO had produced some 35 billion kWh in 109,000 hours of operation. Repeated leaks in the heater tubes of the two steam generators had occurred since 1971. Both steam generators were replaced in the course of the 1983 annual revision. Kraftwerk Union AG (KWU) was commissioned to plant and carry out the replacement work. Despite the leakages the steam generators had been run safely and reliably over a period of 14 years until their replacement. Replacing the steam generators was completed within twelve weeks. In addition to the KWO staff and the supervising crew of KWU, some 400 external fitters were employed on the job at peak work-load periods. For the revision of the whole plant, work on the emergency systems and replacement of the steam generators a maximum number of approx. 900 external fitters were employed in the plant in addition to some 250 members of the plant crew. The exposure dose of the personnel sustained in the course of the steam generator replacement was 690 man-rem, which was clearly below previous estimates. (orig.) [de

  15. Validating eddy current array probes for inspecting steam generator tubes

    International Nuclear Information System (INIS)

    Sullivan, S.P.; Cecco, V.S.; Obrutsky, L.S.

    1997-01-01

    A CANDU nuclear reactor was shut down for over one year because steam generator (SG) tubes had failed with outer diameter stress-corrosion cracking (ODSCC) in the U-bend section. Novel, single-pass eddy current transmit-receive probes, denoted as C3, were successful in detecting all significant cracks so that the cracked tubes could be plugged and the unit restarted. Significant numbers of tubes with SCC were removed from a SG in order to validate the results of the new probe. Results from metallurgical examinations were used to obtain probability-of-detection (POD) and sizing accuracy plots to quantify the performance of this new inspection technique. Though effective, the above approach of relying on tubes removed from a reactor is expensive, in terms of both economic and radiation-exposure costs. This led to a search for more affordable methods to validate inspection techniques and procedures. Methods are presented for calculating POD curves based on signal-to-noise studies using field data. Results of eddy current scans of tubes with laboratory-induced ODSCC are presented with associated POD curves. These studies appear promising in predicting realistic POD curves for new inspection technologies. They are being used to qualify an improved eddy current array probe in preparation for field use. (author)

  16. A passive emergency heat sink for water-cooled reactors with particular application to CANDU reactors

    International Nuclear Information System (INIS)

    Spinks, N.J.

    1996-01-01

    Water in an overhead pool can serve as a general-purpose passive emergency heat sink for water-cooled reactors. It can be used for containment cooling, for emergency depressurization of the heat transport-system, or to receive any other emergency heat, such as that from the CANDU moderator. The passive emergency water system provides in-containment depressurization of steam generators and no other provision is needed for supply of low-pressure emergency water to the steam generators. For containment cooling, the pool supplies water to the tube side of elevated tube banks inside containment. The elevation with respect to the reactor heat source maximizes heat transport, by natural convection, of hot containment gases. This effective heat transport combines with the large heat-transfer coefficients of tube banks, to reduce containment overpressure during accidents. Cooled air from the tube banks is directed past the break in the heat-transport system, to facilitate removal of hydrogen using passive catalytic recombiners. (author)

  17. Three Mile Island Nuclear Station steam generator chemical cleaning

    International Nuclear Information System (INIS)

    Hansen, C.A.

    1992-01-01

    The Three Mile Island-1 steam generators were chemically cleaned in 1991 by the B and W Nuclear Service Co. (BWNS). This secondary side cleaning was accomplished through application of the EPRI/SGOG (Electric Power Research Institute - Steam Generator Owners Group) chemical cleaning iron removal process, followed by sludge lancing. BWNS also performed on-line corrosion monitoring. Corrosion of key steam generator materials was low, and well within established limits. Liquid waste, subsequently processed by BWNS was less than expected. 7 tabs

  18. Severe Accident R and D for Enhanced CANDU-6 Reactors

    International Nuclear Information System (INIS)

    Nitheanandan, Thambiayah

    2012-01-01

    CANDU reactors possess a number of inherent of inherent and designed safety features that make them resistant to core damage accidents. The unique feature is the low temperature moderator surrounding the fuel channels, which can serve as an alternate heat sink. The fuel is surrounded by three water systems: heavy water primary coolant, heavy water moderator, and light water calandria vault and shield water. In addition, the liquid inventory in the steam generators is a fourth indirect heat sink, able to cool the primary coolant. The water inventories in the emergency core cooling system and the reserve water tank at the dome of the containment can also provide fuel cooling and water makeup to prevent severe core damage or mitigate the consequences of a severe core damage accident. An assessment of the adequacy of the existing severe accident knowledge base, to confidently perform consequence analyses for the Enhanced CANDU-6 reactor in compliance with regulatory requirements, was recently completed. The assessment relied on systematic Phenomena Identification and Ranking Tables (PIRT) studies completed domestically and internationally. The assessment recommends cost-effective R and D to mitigate the consequences of severe accidents and associated risk vulnerabilities

  19. Technical development and its application on steam generator replacement

    International Nuclear Information System (INIS)

    Morita, Sadahiko; Hanzawa, Katsumi; Sato, Hajime; Kannoto, Yasuo.

    1995-01-01

    Twenty-two PWR nuclear power plants are now under commercial operation in Japan. Eight of these plants are scheduled to have their steam generators replaced by up-graded units as a social responsibility for improved reliability, economy and easier maintenance. To carry out steam generator replacement, main coolant pipe cutting and restoration techniques, remote controlled welding machines and other remote controlled equipment, templating techniques with which the new steam generator primary nozzles will fit the existing primary pipes correctly were developed. An adequate training program was carried out to establish these techniques and they were then applied in replacement work on site. The steam generators of the three plants were replaced completely in 1994. These newly developed techniques are to be applied in upcoming plants and replaced plants will be much reliable. (author)

  20. Impact of aging and material structure on CANDU plant performance

    Energy Technology Data Exchange (ETDEWEB)

    Nadeau, E.; Ballyk, J.; Ghalavand, N. [Candu Energy Inc., Mississauga, Ontario (Canada)

    2011-07-01

    In-service behaviour of pressure tubes is a key factor in the assessment of safety margins during plant operation. Pressure tube deformation (diametral expansion) affects fuel bundle dry out characteristics resulting in reduced margin to trip for some events. Pressure tube aging mechanisms also erode design margins on fuel channels or interfacing reactor components. The degradation mechanisms of interest are primarily deformation, loss of fracture resistance and hydrogen ingress. CANDU (CANada Deuterium Uranium, a registered trademark of the Atomic Energy of Canada Limited used under exclusive licence by Candu Energy Inc.) owners and operators need to maximize plant capacity factor and meet or exceed the reactor design life targets while maintaining safety margins. The degradation of pressure tube material and geometry are characterized through a program of inspection, material surveillance and assessment and need to be managed to optimize plant performance. Candu is improving pressure tubes installed in new build and life extension projects. Improvements include changes designed to reduce or mitigate the impact of pressure tube elongation and diametral expansion rates, improvement of pressure tube fracture properties, and reduction of the implications of hydrogen ingress. In addition, Candu provides an extensive array of engineering services designed to assess the condition of pressure tubes and address the impact of pressure tube degradation on safety margins and plant performance. These services include periodic and in-service inspection and material surveillance of pressure tubes and deterministic and probabilistic assessment of pressure tube fitness for service to applicable standards. Activities designed to mitigate the impact of pressure tube deformation on safety margins include steam generator cleaning, which improves trip margins, and trip design assessment to optimize reactor trip set points restoring safety and operating margins. This paper provides an

  1. Research perspectives on the evaluation of steam generator tube integrity

    International Nuclear Information System (INIS)

    Muscara, J.; Diercks, D.R.; Majumdar, S.; Kupperman, D.S.; Bakhtiari, S.; Shack, W.J.

    2002-01-01

    Industry efforts have been largely successful in managing degradation of steam generator tubes due to wastage, pitting, and denting, but fretting, stress corrosions cracking (SCC) and intergranular attack have proved more difficult to manage. Although steam generator replacements are proceeding, there is substantial industry interest in operating with degraded steam generators, and significant numbers of plants will continue to do so. In most cases degradation of steam generator tubing by stress corrosion cracking is still managed by 'plug or repair on detection' because current NDE techniques for characterization of flaws and the knowledge of SCC crack growth rates are not accurate enough to permit continued operation. Replacement generators with improved designs and materials have performed well to date, but previous experience with the appearance of some types of SCC in Alloy 600 after 10 years or more of operation and laboratory results suggest additional understanding of corrosion performance of these materials is needed. This paper reviews some of the historical background that underlies current steam generator degradation management strategies and outlines some of the additional research that must be done to provide more effective management of degradation in current generators and provide greater assurance of satisfactory performance in replacement steam generators. (author)

  2. Corrosion problems of PWR steam generators

    International Nuclear Information System (INIS)

    Urbancik, L.; Kostal, M.

    Literature data are assessed on corrosion failures of steam generator tubes made of INCONEL 600 or INCOLOY 800. It was found that both alloys with high nickel content showed good stability in a corrosion environment while being sensitive to carbide formation on grain boundaries. The gradual depletion of chromium results from the material and corrosion resistance deteriorates. INCOLOY 800 whose chromium carbide precipitation on grain boundaries in pure water and steam is negligible up to 75O degC and which is not subject to corrosion attacks in the above media and in an oxidizing environment at a temperature to about 700 degC shows the best corrosion resistance. Its favourable properties were tested in long-term operation in the Peach Bottom 1 nuclear power plant where no failures due to corrosion of this material have been recorded since 1967. In view of oxygenic-acid surface corrosion, it is necessary to work in a neutral or slightly basic environment should any one of the two alloys be used for steam generator construction. The results are summed up of an analysis conducted for the Beznau I NOK reactor. Water treatment with ash-free amines can be used as prevention against chemical corrosion mechanisms, although the treatment itself does not ensure corrosion resistance of steam generator key components. (J.B.)

  3. Dynamic simulation of steam generator failures

    Energy Technology Data Exchange (ETDEWEB)

    Meister, G [Institut fuer Nukleare Sicherheitsforschung, Kernforschungsanlage Juelich GmbH, Juelich (Germany)

    1988-07-01

    A computer program will be described which is capable to simulate severe transients in a gas heated steam generator. Such transients may arise in the safety analysis of accidents resulting from failures in the heat removal system of an HTGR power plant. Important failure modes which have to be considered are ruptures of one or more steam generator tubes leading to water or steam ejection into the primary system or anomalous operating conditions which my cause damage due to excessive thermal stress. Examples are the complete dryout as a consequence of feedwater interrupt in connection with continuing gas heating and the reflooding of the secondary channel with cold feedwater after dryout. The steam generator program which is capable to simulate accidents of this type is written as a module which can be implemented into a program system fur the simulation of the total heat rejection system. It based on an advanced mathematical model for the two phase flow taking deviations from thermal equilibrium into account. Mass, energy and momentum balances for the primary and secondary fluid and the heat diffusion equations for the heat exchanging wall form a system of coupled differential equations which is solved numerically by an algorithm which is stiffly stable and suppresses effectively oscillations of numerical origin. Results of the simulation of transients of the type mentioned above will be presented and discussed. (author)

  4. Dynamic simulation of steam generator failures

    International Nuclear Information System (INIS)

    Meister, G.

    1988-01-01

    A computer program will be described which is capable to simulate severe transients in a gas heated steam generator. Such transients may arise in the safety analysis of accidents resulting from failures in the heat removal system of an HTGR power plant. Important failure modes which have to be considered are ruptures of one or more steam generator tubes leading to water or steam ejection into the primary system or anomalous operating conditions which my cause damage due to excessive thermal stress. Examples are the complete dryout as a consequence of feedwater interrupt in connection with continuing gas heating and the reflooding of the secondary channel with cold feedwater after dryout. The steam generator program which is capable to simulate accidents of this type is written as a module which can be implemented into a program system fur the simulation of the total heat rejection system. It based on an advanced mathematical model for the two phase flow taking deviations from thermal equilibrium into account. Mass, energy and momentum balances for the primary and secondary fluid and the heat diffusion equations for the heat exchanging wall form a system of coupled differential equations which is solved numerically by an algorithm which is stiffly stable and suppresses effectively oscillations of numerical origin. Results of the simulation of transients of the type mentioned above will be presented and discussed. (author)

  5. Steam generator development in France for the Super Phenix project

    International Nuclear Information System (INIS)

    Robin, M.G.

    1975-01-01

    'Steam Generator Development for Super Phenix Project'. The development program of steam generators studied by Fives-Cail Babcock and Stein Industrie Companies, jointly with CEA end EDF, for the Super Phenix 1200 MWe Fast Breeder Power Plant, is presented. The main characteristics of both sodium heated steam generators are emphasized and experimental studies related to their key features are reported. (author)

  6. The evolution of CANDU containment design

    International Nuclear Information System (INIS)

    Pendergast, Duane R.; Meneley, Daniel A.

    1995-01-01

    This paper reviews Canadian containment design, reflects on forces which have shaped the evolving designs and contemplates future containment design subject to existing constraints of Canadian and International nuclear power regulations. The discussion mentions modifications which could play a role in easing customary restrictions on siting while meeting the intent and literal definition of Canadian licensing requirements. Many different containment concepts have been considered and deployed over the years. Professor Birkhofer points out that the earliest systems installed were 'dry containment'. These rely on large containment buildings designed to contain all the the steam from a loss of coolant. It was soon realized the large water inventory of boiling water reactors would require very large and expensive containment buildings. This led to the development of pressure suppression concepts. Various pressure suppression schemes have been devised to condense steam and thus reduce design pressure and volume requirements. Examples include the forcing of steam into condensing water pools of BWR's steam condensation by passage into arrays of ice, dousing spray systems in CANDU reactors, and the spray condenser systems of late model Soviet designed VVER - 440 reactors. The fundamental concept of energy removal by steam condensation can result in a small containment volume requiring low design pressure capability

  7. Changing the simualtor's steam generator

    International Nuclear Information System (INIS)

    Ruiz Martin, J.A.; Ortega Pascual, F.

    2006-01-01

    Two Spanish nuclear power plants (two PWR units each one) have planned to change their Westinghouse D-3 steam generators (SGo henceforth) for a new model, 61W/D3 from Siemens/KWU (SGn henceforth), during 1995/1997. This is the reason why TECNATOM has developed during 1994's last term, a new software for the full scope simulator that incorporates the modifications related to the steam generator substiution programme. This allows an anticipated training on the procedures, not only for normal, but for emergency procedures. As it is a component which has not yet been included in these plants, there are not real references or operative experience data. Therefore, the design of the validation strategy was one of the key points in this work. (author)

  8. Computer codes for simulation of Angra 1 reactor steam generator

    International Nuclear Information System (INIS)

    Pinto, A.C.

    1978-01-01

    A digital computer code is developed for the simulation of the steady-state operation of a u-tube steam generator with natural recirculation used in Pressurized Water Reactors. The steam generator is simulated with two flow channel separated by a metallic wall, with a preheating section with counter flow and a vaporizing section with parallel flow. The program permits the changes in flow patterns and heat transfer correlations, in accordance with the local conditions along the vaporizing section. Various sub-routines are developed for the determination of steam and water properties and a mathematical model is established for the simulation of transients in the same steam generator. The steady state operating conditions in one of the steam generators of ANGRA 1 reactor are determined utilizing this programme. Global results obtained agree with published values [pt

  9. Evaluation on mechanical and corrosion properties of steam generator tubing materials

    International Nuclear Information System (INIS)

    Kim, In Sup; Lee, Byong Whi; Lee, Sang Kyu; Lee, Young Ho; Kim, Jun Whan; Lee, Ju Seok; Kwon, Hyuk Sang; Kim, Su Jung

    1998-06-01

    Steam generator is one of the major components of nuclear reactor pressure boundary. It's main function os transferring heat which generated in the reactor to turbine generator through steam generator tube. In these days, steam generator tubing materials of operating plant are used Inconel 600 alloys. But according to the operation time, there are many degradation phenomena which included mechanical damage due to flow induced vibration and corrosion damage due to PWSCC, IGA/SCC and pitting etc. Recently Inconel 690 alloys are selected as new and replacement steam generator tubes for domestic nuclear power plant. But there are few study about mechanical and corrosion properties of Inconel 600 and 690. The objectives of this study is to evaluate and compare mechanical and corrosion propertied of steam generator tube materials

  10. Evaluation on mechanical and corrosion properties of steam generator tubing materials

    Energy Technology Data Exchange (ETDEWEB)

    Kim, In Sup; Lee, Byong Whi; Lee, Sang Kyu; Lee, Young Ho; Kim, Jun Whan; Lee, Ju Seok; Kwon, Hyuk Sang; Kim, Su Jung [Korea Advanced Institute of Science and Technology, Taejon (Korea, Republic of)

    1998-06-15

    Steam generator is one of the major components of nuclear reactor pressure boundary. It's main function os transferring heat which generated in the reactor to turbine generator through steam generator tube. In these days, steam generator tubing materials of operating plant are used Inconel 600 alloys. But according to the operation time, there are many degradation phenomena which included mechanical damage due to flow induced vibration and corrosion damage due to PWSCC, IGA/SCC and pitting etc. Recently Inconel 690 alloys are selected as new and replacement steam generator tubes for domestic nuclear power plant. But there are few study about mechanical and corrosion properties of Inconel 600 and 690. The objectives of this study is to evaluate and compare mechanical and corrosion propertied of steam generator tube materials.

  11. Emergency systems and protection equipment of modular steam generators for fast reactors

    International Nuclear Information System (INIS)

    Matal, O.

    The requirements are discussed for accident protection of modular steam generators for fast reactors. Accident protection is assessed for a modular through-flow steam generator and for a natural circulation modular steam generator. Benefits and constraints are shown and possible improvements are outlined for accident protection of liquid sodium fired modular steam generators. (Kr)

  12. Fretting-wear characteristics of steam generator tubes contacting with foreign object

    International Nuclear Information System (INIS)

    Jo, Jong Chull; Jhung, Myung Jo; Kim, Woong Sik; Kim, Hho Jung

    2003-01-01

    Fretting-wear characteristics of steam generator tubes contacting with foreign object has been investigated in this study. The operating steam generator shell-side flow field conditions are obtained from three-dimensional steam generator flow calculation using a well-validated steam generator thermal-hydraulic analysis computer code. Modal analyses are performed for the finite element modelings of tubes to get the natural frequency, corresponding mode shape and participation factor. The wear rate of a steam generator tube caused by foreign object is calculated using the Archard formula and the remaining life of the tube is predicted. In addition, the effects of internal pressure and flow velocity on the remaining life of the tube are discussed in this paper

  13. SWAAM code development, verification and application to steam generator design

    International Nuclear Information System (INIS)

    Shin, Y.W.; Valentin, R.A.

    1990-01-01

    This paper describes the family of SWAAM codes developed by Argonne National Laboratory to analyze the effects of sodium/water reactions on LMR steam generators. The SWAAM codes were developed as design tools for analyzing various phenomena related to steam generator leaks and to predict the resulting thermal and hydraulic effects on the steam generator and the intermediate heat transport system (IHTS). The theoretical foundations and numerical treatments on which the codes are based are discussed, followed by a description of code capabilities and limitations, verification of the codes by comparison with experiment, and applications to steam generator and IHTS design. (author). 25 refs, 14 figs

  14. Pulsed high-pressure (PHP) drain-down of steam generating system

    International Nuclear Information System (INIS)

    Petrusek, R.A.

    1991-01-01

    This patent describes an improved method of draining down contained reactor-coolant water from the inverted vertical U-tubes of at least one vertical-type steam generator in which the upper inverted U-shaped ends of the tubes are closed and the lower ends thereof are open, the steam generator having a channel head at its lower end including a vertical dividing wall defining a primary water inlet side and a primary water outlet side of the generator, the steam generator having chemical volume control system means and residual heat removal system means, and the steam generator being part of a nuclear-powered steam generating system wherein the reactor-coolant water is normally circulated from and back into the reactor via a loop comprising the steam generator and inlet and outlet conduits connected to the lower end of the steam generator, and the reactor being in communication with pressurizer means and comprising the steps of introducing a gas which is inert to the system and which is under pressure above atmospheric pressure into at least one of the downwardly facing open ends of each of the U-tubes from below the tubesheet in which the open ends of the U-tubes are mounted adjacent the lower end of the steam generator while permitting the water to flow out from the open ends of the U-tubes, the improvement in combination therewith for substantially increasing the effectiveness and efficiency of such water removal from the tubes. It includes determining the parameters effecting a first average volumetric rate of removal for a predetermined period of time, infra, of the reactor-coolant water from the inverted vertical U-tubes, the specific unit for the first average volumetric rate expressing properties identical with the properties expressed in a second average volumetric rate maintained in a later mentioned step

  15. Steam generator for use in nuclear power plants

    International Nuclear Information System (INIS)

    Cella, A.

    1980-01-01

    An improved steam generator is described for use in a nuclear power plant of the pressurized water type in which a turbine generator is driven by the steam output of the steam generator to provide electrical power therefrom. The improvement comprises providing a vertically movable grid structure vertically extending within the interior of the lower housing portion of the steam generator through which individual tubes comprising a vertically extending tube bundle extend. The tube bundle has a tube sheet at one end thereof supporting the tube bundle for the tubes extending through the tube sheet in flow through communication with a heat exchange fluid inlet. The grid structure defines grid apertures therein through which the individual tubes extend with each of the grid apertures being in surrounding relationship with a portion of an associated one of the tubes. The grid structure is movable for a predetermined vertical extent, such as by hydraulic means, such as a piston, along the tubes for vertically displacing the means defining the grid apertures by a sufficient amount for removing the previously surrounded portion of each of the tubes from the associated grid apertures whereby an enhanced reading of the condition of the tubes at the previously surrounded portion is enabled. The steam generator may comprise vertically assemblable modules which are removably mounted together in sealing relationship, with the modules comprising a base module, a tube bundle module removably mountable on the base module in sealing relationship therewith and an uppermost drier module removably mountable on the tube bundle module in sealing relationship therewith whereby ready access to removal of the tube bundle module in situ from the nuclear power plant steam generator is facilitated

  16. Corrosion problems in PWR steam generators

    International Nuclear Information System (INIS)

    Weber, J.; Suery, P.

    1976-01-01

    Examinations on pulled steam generator tubes from the Swiss nuclear power plants Beznau I and II, together with some laboratory tests, may be summarized as follows: Corrosion problems in vertical U-tube steam generators with Alloy 600 as tube material are localized towards relatively narrow regions above the tube sheet where thermohydraulic conditions and, as a consequence thereof, chemical conditions are uncontrolled. Within these zones Alloy 600 is not sufficienthy resistent to caustic or phosphate attack (caustic stress corrosion cracking and general corrosion, resp.). The mechanisms of several corrosion phenomena are not fully understood. (orig.) [de

  17. Experience with modular steam generator production and application of new testing methods

    International Nuclear Information System (INIS)

    Olesovsky

    Experience is reviewed gained at the Trebic IBZKG plant with the production of modular steam generators. The plant started producing steam generators for the Jaslovske Bohunice nuclear power plant in 1965. In addition to the steam generator for the A-1, the plant also produced a loop for the Melekess power plant and a steam generator for the BOR-60 reactor. Operating experience gained so far allowed improving the quality of the BOR steam generator, especially in the tube-tube plate joint. A double tube plate was used and the welded joint shape was changed. As a result of high requirements on the quality of welded joints, the steam generator has successfully been in operation for more then 10,000 hours. The existing experience was utilized in designing a new steam generator named Nadya. Many design and technological requirements were presented concerning the Nadya generator and many new checking operations have been included in technology. (Kr)

  18. Industrial process heat from CANDU reactors

    International Nuclear Information System (INIS)

    Hilborn, J.S.; Seddon, W.A.; Barnstaple, A.G.

    1980-08-01

    It has been demonstrated on a large scale that CANDU reactors can produce industrial process steam as well as electricity, reliably and economically. The advantages of cogeneration have led to the concept of an Industrial Energy Park adjacent to the Bruce Nuclear Power Development in the province of Ontario. For steam demands between 300,000 and 500,00 lb/h (38-63 kg/s) and an annual load factor of 80%, the estimated cost of nuclear steam at the Bruce site boundary is $3.21/MBtu ($3.04GJ), which is at least 30% cheaper than oil-fired steam at the same site. The most promising near term application of nuclear heat is likely to be found within the energy-intensive chemical industry. Nuclear energy can substitute for imported oil and coal in the eastern provinces if the price remains competitive, but low cost coal and gas in the western provinces may induce energy-intensive industries to locate near those sources of energy. In the long term it may be feasible to use nuclear heat for the mining and extraction of oil from the Alberta tar sands. (auth)

  19. Evolution of management activities and performance of the Point Lepreau Steam Generators

    International Nuclear Information System (INIS)

    Slade, J.; Keating, J.; Gendron, T.

    2007-01-01

    The Point Lepreau steam generators have been in service since 1983 when the plant was commissioned. During the first thirteen years of operation, Point Lepreau steam generator maintenance issues led to 3-4% unplanned plant incapability Steam generator fouling, corrosion, and the introduction of foreign materials during maintenance led to six tube leaks, two unplanned outages, two lengthy extended outages, and degraded thermal performance during this period. In recognition of the link between steam generator maintenance activities and plant performance, improvements to steam generator management activities have been continuously implemented since 1987. This paper reviews the evolution of steam generator management activities at Point Lepreau and the resulting improved trends in performance. Plant incapability from unplanned steam generator maintenance has been close to zero since 1996. The positive trends have provided a strong basis for the management strategies developed for post-refurbishment operation. (author)

  20. Steam generator inspection activities at the EPRI NDE Center

    International Nuclear Information System (INIS)

    Krzywosz, K.

    1988-01-01

    Various types of corrosion and mechanical damage continue to affect the availability of both recirculating and once-through steam generators. Both the tube bundle and its supporting structure are affected. Intergranular attack and stress corrosion cracking (SCC) are the corrosion-assisted tube-wall damage mechanisms of most concern at this time. Fatigue cracking and fretting at antivibration bars are currently the mechanical damage forms causing most concern. Improved NDE equipment and techniques are providing better detection and characterization of adverse conditions within the steam generators and doing it at an earlier stage. This allows timely corrective action. To maintain the projected life expectancy of existing and new steam generators, remedial measures have been implemented. These measures include shot- or roto-peening, U-bend stress relief, chemical cleaning of secondary side, and sleeving of tubes. The improved NDE technology will also be instrumental in monitoring and assessing the effectiveness of the remedial measures. The revision of guidance documents for steam generator in-service inspection (ISI) is providing more relevant information to support this complex operation. A multitasked project is described that includes evaluation of steam generator tube NDE technology, transfer of this technology to utilities, and rapid response utility assistance

  1. Large-leak sodium-water reaction analysis for steam generators

    International Nuclear Information System (INIS)

    Sakano, K.; Shindo, Y.; Hori, M.

    1975-01-01

    The guillotine rupture of 4 tubes is assumed as a design basis regarding the large-leak sodium-water reaction in the system of the MONJU steam generator. Three kinds of analyses were performed with the view to showing the integrity of the steam generator system on the reaction. The first one is the analysis of the initial pressure spike, assuming the initial guillotine rupture of 1 tube. The analysis was performed by utilizing one-dimensional sphere-cylinder model code SWAC-7 and two-dimensional axisymmetric code PISCES 2DL. The second one is the analysis of the secondary peak pressure and its propagation in the system, assuming the instantaneous guillotine rupture of 4 tubes. The third one is the analysis of the dynamic deformation of the steam generator shell. The integrity of the steam generator system was shown by the analyses. (author)

  2. Pressurizer and steam-generator behavior under PWR transient conditions

    International Nuclear Information System (INIS)

    Wahba, A.B.; Berta, V.T.; Pointner, W.

    1983-01-01

    Experiments have been conducted in the Loss-of-Fluid Test (LOFT) pressurized water reactor (PWR), at the Idaho National Engineering Laboratory, in which transient phenomena arising from accident events with and without reactor scram were studied. The main purpose of the LOFT facility is to provide data for the development of computer codes for PWR transient analyses. Significant thermal-hydraulic differences have been observed between the measured and calculated results for those transients in which the pressurizer and steam generator strongly influence the dominant transient phenomena. Pressurizer and steam generator phenomena that occurred during four specific PWR transients in the LOFT facility are discussed. Two transients were accompanied by pressurizer inflow and a reduction of the heat transfer in the steam generator to a very small value. The other two transients were accompanied by pressurizer outflow while the steam generator behavior was controlled

  3. Modular sludge collection system for a nuclear steam generator

    International Nuclear Information System (INIS)

    Appleman, R.H.; Bein, J.D.; Powasaki, F.S.

    1986-01-01

    A sludge collection system is described for a vertically oriented nuclear steam generator wherein vapors produced in the steam generator pass through means for separating entrained liquid from the vapor prior to the vapor being discharged from the steam generator. The sludge collection system comprises: an upwardly open chamber for collecting the separated liquid and feedwater entering the steam generator; upwardly open sludge collecting containers positioned within the chamber, wherein each of the containers includes a top rim encompassing an opening leading to the interior of each container; generally flat, perforated covers, each of the covers being positioned over one of the openings such that a gap is formed between the cover and the adjacent top rim; sludge agitating means on at least one of the containers; and sludge removal means on at least one of the containers

  4. Large-leak sodium-water reaction analysis for steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Sakano, K; Shindo, Y; Hori, M

    1975-07-01

    The guillotine rupture of 4 tubes is assumed as a design basis regarding the large-leak sodium-water reaction in the system of the MONJU steam generator. Three kinds of analyses were performed with the view to showing the integrity of the steam generator system on the reaction. The first one is the analysis of the initial pressure spike, assuming the initial guillotine rupture of 1 tube. The analysis was performed by utilizing one-dimensional sphere-cylinder model code SWAC-7 and two-dimensional axisymmetric code PISCES 2DL. The second one is the analysis of the secondary peak pressure and its propagation in the system, assuming the instantaneous guillotine rupture of 4 tubes. The third one is the analysis of the dynamic deformation of the steam generator shell. The integrity of the steam generator system was shown by the analyses. (author)

  5. Application of Integrated Neural Network Method to Fault Diagnosis of Nuclear Steam Generator

    International Nuclear Information System (INIS)

    Zhou Gang; Yang Li

    2009-01-01

    A new fault diagnosis method based on integrated neural networks for nuclear steam generator (SG) was proposed in view of the shortcoming of the conventional fault monitoring and diagnosis method. In the method, two neural networks (ANNs) were employed for the fault diagnosis of steam generator. A neural network, which was used for predicting the values of steam generator operation parameters, was taken as the dynamics model of steam generator. The principle of fault monitoring method using the neural network model is to detect the deviations between process signals measured from an operating steam generator and corresponding output signals from the neural network model of steam generator. When the deviation exceeds the limit set in advance, the abnormal event is thought to occur. The other neural network as a fault classifier conducts the fault classification of steam generator. So, the fault types of steam generator are given by the fault classifier. The clear information on steam generator faults was obtained by fusing the monitoring and diagnosis results of two neural networks. The simulation results indicate that employing integrated neural networks can improve the capacity of fault monitoring and diagnosis for the steam generator. (authors)

  6. TRAC analysis of steam-generator overfill transients for TMI-1

    International Nuclear Information System (INIS)

    Bassett, B.

    1983-01-01

    A reactor safety issue concerning the overfilling of once-through steam generators leading to combined primary/secondary blowdown has been raised recently. A series of six calculations, performed with the LWR best-estimate code, TRAC-PD2, on a Babcock and Wilcox Plant (TMI-1), was performed to investigate this safety issue. The base calculation assumed runaway main feedwater to one steam generator causing it to overfill and to break the main steam line. Four additional calculations build onto the base case with combinations of a pump-seal failure, a steam-generator tube rupture, and the pilot-operated relief valve not reseating. A sixth calculation involved only the rupture of a single steam-generator tube. The results of these analyses indicate that for the transients investigated, the emergency cooling system provided an adequate make-up coolant flow to mitigate the accidents

  7. Pressurized-water coolant nuclear reactor steam generator

    International Nuclear Information System (INIS)

    Mayer, H.; Schroder, H.J.

    1975-01-01

    A description is given of a pressurized-water coolant nuclear reactor steam generator having a vertical housing for the steam generating water and containing an upstanding heat exchanger to which the pressurized-water coolant passes and which is radially surrounded by a guide jacket supporting a water separator on its top. By thermosiphon action the steam generating water flows upward through and around the heat exchanger within the guide chamber to the latter's top from which it flows radially outwardly and downwardly through a down draft space formed between the outside of the jacket and the housing. The water separator discharges separated water downwardly. The housing has a feedwater inlet opening adjacent to the lower portion of the heat exchanger, providing preheating of the introduced feedwater. This preheated feedwater is conveyed by a duct upwardly to a location where it mixes with the water discharged from the water separator

  8. Transient analysis of a U-tube natural circulation steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Gaikwad, A J; Kumar, Rajesh; Bhadra, Anu; Chakraborty, G; Venkat Raj, V [Reactor Safety Division, Bhabha Atomic Research Centre, Mumbai (India)

    1994-06-01

    A computer code has been developed, for transient thermal-hydraulic analysis of proposed 500 MWe PHWR steam generator. The transient behaviour of a nuclear power plant is very much dependent on the steam generator performance, as it provides a thermal linkage between the primary and secondary systems. Study of dynamics of steam generator is essential for over all power plant dynamics as well as design of control systems for steam generator. A mathematical model has been developed for the simulation of thermal-hydraulic phenomena in a U tube natural circulation steam generator. Fluid model is based on one dimensional, nonlinear, single fluid conservation equations of mass, momentum, energy and equation of state. This model includes coupled two phase flow heat transfer and natural circulation. The model accounts for both compressibility and thermal expansion effects. The process simulation and results obtained for transients such as step change in load and total loss of feed water are presented. (author). 5 refs., 7 figs.

  9. Steam generators and fuel engineering utilizing solid, liquid, gaseous and special fuels

    Energy Technology Data Exchange (ETDEWEB)

    Thor, G

    1983-01-01

    Provided were technological specifications and details in the design of brown coal fired steam generators, produced in the German Democratic Republic. These steam generators range in their capacity between 1.6 and more than 1,000 t/h. The appropriate coal feeding systems, water supply and cleaning equipment, coal pulverizers and ash removal units are also manufactured. Various schemes show the design of a 25 to 64 t/h, a 320 t/h and an 815 t/h brown coal steam generator. Specifications are given for series of fuel pulverizers available, for the water circulation system and steam evaporators. The VEB Dampferzeugerbau Berlin also offers steam generators for saliniferous brown coal with a steam capacity up to 125 t/h, steam generators for pulverized black coal with a capacity up to 350 t/h and oil and gas fired generators up to 250 t/h. The company has experience in combustion of biomass (sugar cane waste) with oil in steam generators of more than 100 t/h capacity, and in projecting firing systems for other biofuels including rice, peanut and coconut hulls, wood and bark. Multi-biofuel firing in combination with coal for steam generation is also regarded as possible. (In English)

  10. Fourth international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Tuomisto, H. [ed.] [IVO Group, Vantaa (Finland); Purhonen, H. [ed.] [VTT, Espoo (Finland); Kouhia, V. [ed.] [Lappeenranta Univ. of Technology (Finland)

    1997-12-31

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries.

  11. Fourth international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Tuomisto, H [ed.; IVO Group, Vantaa (Finland); Purhonen, H [ed.; VTT, Espoo (Finland); Kouhia, V [ed.; Lappeenranta Univ. of Technology (Finland)

    1998-12-31

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries.

  12. Fourth international seminar on horizontal steam generators

    International Nuclear Information System (INIS)

    Tuomisto, H.; Purhonen, H.; Kouhia, V.

    1997-01-01

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries

  13. Dynamic analysis of CHASNUPP steam generator structure during shipping

    International Nuclear Information System (INIS)

    Han Liangbi; Xu Jinkang; Zhou Meiwu; He Yinbiao

    1998-07-01

    The dynamic analysis of CHASNUPP steam generator during shipping is described, including the simplified mathematical model, acceleration power spectrum of ocean wave induced random vibration, the dynamic analysis of steam generator structure under random loading, the applied computer code and calculated results

  14. Overview of the United States steam generator development programs

    Energy Technology Data Exchange (ETDEWEB)

    Kaspar, P W; Lowe, P A

    1975-07-01

    The LMFBR steam generator development program of the USA was initiated to support the development of reliable designs and meaningful performance data for these critical components. Since the steam generators include the structural boundary between heated sodium and water, the consequences of small flaws in the materials that form the boundary are significant. Successful development and demonstration of commercial LMFBR power plants requires the consideration of many factors in addition to the design, construction and operation of a particular plant. Additional factors which must be assessed include: economics, reliability, safety, environment, operability, maintainability and conservation of the resources. In terms of the steam generator these items led to the selection of a single wall tube design using a forced recirculating system for the present Clinch River Breeder Reactor. There are strong economic incentives to use a once-through steam generating system in future designs.

  15. Decontamination of Steam Generator tube using Abrasive Blasting Technology

    International Nuclear Information System (INIS)

    Min, B. Y.; Kim, G. N.; Choi, W. K.; Lee, K. W.; Kim, D. H.; Kim, K. H.; Kim, B. T.

    2010-01-01

    As a part of a technology development of volume reduction and self disposal for large metal waste project, We at KAERI and our Sunkwang Atomic Energy Safety (KAES) subcontractor colleagues are demonstrating radioactively contaminated steam generator tube by abrasive blasting technology at Kori-1 NPP. A steam generator is a crucial component in a PWR (pressurized Water Reactor). It is the crossing between the primary, contaminated, circuit and the secondary waste-steam circuit. The heat from the primary reactor coolant loop is transferred to the secondary side in thousands of small tubes. Due to several problems in the material of those tube, like SCC (Stress Corrosion Cracking), insufficient control in water chemistry, which can be cause of tube leakage, more and more steam generators are replaced today. Only in Korea, already 2 of them are replaced and will be replaced in the near future. The retired 300 ton heavy Steam generator was stored at the storage waste building of Kori NPP site. The steam generator waste has a large volume, so that it is necessary to reduce its volume by decontamination. A waste reduction effect can be obtained through decontamination of the inner surface of a steam generator. Therefore, it is necessary to develop an optimum method for decontamination of the inner surface of bundle tubes. The dry abrasive blasting is a very interesting technology for the realization of three-dimensional microstructures in brittle materials like glass or silicon. Dry abrasive blasting is applicable to most surface materials except those that might be shattered by the abrasive. It is most effective on flat surface and because the abrasive is sprayed and can also applicable on 'hard to reach' areas such as inner tube ceilings or behind equipment. Abrasive decontamination techniques have been applied in several countries, including Belgium, the CIS, France, Germany, Japan, the UK and the USA

  16. Solar energy for steam generation in Brazil

    Energy Technology Data Exchange (ETDEWEB)

    De Carvalho, Jr, A V; Orlando, A DeF; Magnoli, D

    1979-05-01

    Steam generation is a solar energy application that has not been frequently studied in Brazil, even though for example, about 10% of the national primary energy demand is utilized for processing heat generation in the range of 100 to 125/sup 0/C. On the other hand, substitution of automotive gasoline by ethanol, for instance, has received much greater attention even though primary energy demand for process heat generation in the range of 100 to 125/sup 0/C is of the same order of magnitude than for total automotive gasoline production. Generation of low-temperature steam is analyzed in this article using distributed systems of solar collectors. Main results of daily performance simulation of single flat-plate collectors and concentrating collectors are presented for 20/sup 0/S latitude, equinox, in clear days. Flat plate collectors considered are of the aluminum roll-bond absorber type, selective surface single or double glazing. Considering feedwater at 20/sup 0/C, saturated steam at 120/sup 0/C and an annual solar utilization factor of 50%, a total collector area of about 3,000 m/sup 2/ is necessary for the 10 ton/day plant, without energy storage. A fuel-oil back-up system is employed to complement the solar steam production, when necessary. Preliminary economic evaluation indicates that, although the case-study shows today a long payback period relative to subsidized fuel oil in the domestic market (over 20 years in the city of Rio de Janeiro), solar steam systems may be feasible in the medium term due to projected increase of fuel oil price in Brazil.

  17. Study on steam separation in steam generators of a NPP with the WWER-440 reactors

    International Nuclear Information System (INIS)

    Dmitriev, A.I.; Kolzov, Yu.V.; Titov, V.F.; Dubrovin, A.V.; Ilyushin, V.F.; Volkov, A.P.

    1977-01-01

    The separation characteristics as well as the actual level position in steam generators with and without a submerged holy sheet have been determined at a WWER-440 reactor nuclear power plant. It has been shown, that without changing the design of steam generators their load at the WWER-440 reactor nuclear power plant can be increased by about 10%. In this case the vapour humidity does not exceed the permissible value equal to 0.25%. The submerged holy sheet considerably decreases load irregularity and swelling of the water-steam mixture layer

  18. CANDU: study and review

    International Nuclear Information System (INIS)

    Morad, César M.; Santos, Thiago A. dos

    2017-01-01

    The CANDU (Canadian Deuterium Uranium) is a nuclear reactor developed by AECL (Atomic Energy of Canada Limited). The first small-scale reactor is known as NPD and was made in 1955 and commenced operation in 1962. It is a pressurized heavy water reactor and uses D2O as moderator and coolant and therefore uses natural uranium as fuel. There have been two major types of CANDU reactors, the original design of around 500 MWe that was intended to be used in multi-reactor installations in large plants, and the rationalized CANDU6 which has units in Argentina, South Korea, Pakistan, Romania and China. Throughout the 1980s and 90s the nuclear power market suffered a major crash, with few new plants being constructed in North America or Europe. Design work continued through, however, and a number of new design concepts were introduced that dramatically improved safety, capital costs, economics and overall performance. These Generation III+ and Generation IV machines became a topic of considerable interest in the early 2000s as it appeared a nuclear renaissance was underway and large numbers of new reactors would be built over the next decade. The present work aims to study the reactors of the CANDU type, exploring from its creation to studies directed to G-III and G-IV reactors. (author)

  19. CANDU: study and review

    Energy Technology Data Exchange (ETDEWEB)

    Morad, César M., E-mail: cesar.morad@usp.br [Universidade de São Paulo (POLI/USP), SP (Brazil). Escola Politécnica; Stefani, Giovanni L. de, E-mail: giovanni.stefani@ipen.br [Instituto de Pesquisas Energéticas e Nucleares (IPEN/CNEN-SP), São Paulo, SP (Brazil); Santos, Thiago A. dos, E-mail: thiago.santos@ufabc.edu.br [Universidade Federal do ABC (UFABC), Santo André, SP (Brazil)

    2017-07-01

    The CANDU (Canadian Deuterium Uranium) is a nuclear reactor developed by AECL (Atomic Energy of Canada Limited). The first small-scale reactor is known as NPD and was made in 1955 and commenced operation in 1962. It is a pressurized heavy water reactor and uses D2O as moderator and coolant and therefore uses natural uranium as fuel. There have been two major types of CANDU reactors, the original design of around 500 MWe that was intended to be used in multi-reactor installations in large plants, and the rationalized CANDU6 which has units in Argentina, South Korea, Pakistan, Romania and China. Throughout the 1980s and 90s the nuclear power market suffered a major crash, with few new plants being constructed in North America or Europe. Design work continued through, however, and a number of new design concepts were introduced that dramatically improved safety, capital costs, economics and overall performance. These Generation III+ and Generation IV machines became a topic of considerable interest in the early 2000s as it appeared a nuclear renaissance was underway and large numbers of new reactors would be built over the next decade. The present work aims to study the reactors of the CANDU type, exploring from its creation to studies directed to G-III and G-IV reactors. (author)

  20. On the evaluation of lifetime of evaporative tubes of once-through steam generators at steam-generating surface temperature oscillations in the burnout region

    International Nuclear Information System (INIS)

    Vorob'ev, V.A.; Loshchinin, V.M.; Remizov, O.V.

    1978-01-01

    Suggested is a method for evaluation of a stressed state of evaporation tubes of once-through steam generators at temperature oscillations in the burnout region. Calculated is the amplitude of steam-generating surface temperature oscillations in the burnout region depending on the frequency of a liquid-steam boundary transfer and on this basis determined are thermal stresses in a tube wall. Knowing a fatigue curve gives the possibility to evaluate a heat transfer tube lifetime

  1. Steam generators and furnaces

    Energy Technology Data Exchange (ETDEWEB)

    Swoboda, E

    1978-04-01

    The documents published in 1977 in the field of steam generators for conventional thermal power plants are classified according to the following subjects: power industry and number of power plants, planning and operation, design and construction, furnaces, environmental effects, dirt accumulation and corrosion, conservation and scouring, control and automation, fundamental research, and materials.

  2. Modelling of a Coil Steam Generator for CSP applications

    DEFF Research Database (Denmark)

    Pelagotti, Leonardo; Sørensen, Kim; Condra, Thomas Joseph

    2014-01-01

    The project investigates a new design for a CSP plant steam generation system, the Coil Steam Generator (CSG). This system allows faster start-ups and therefore higher daily energy production from the Sun. An analytical thermodynamic simulation model of the evaporator and a mechanical analysis...

  3. Strategy for assessment of WWER steam generator tube integrity. Report prepared within the framework of the coordinated research project on verification of WWER steam generator tube integrity

    International Nuclear Information System (INIS)

    2007-12-01

    Steam generator heat exchanger tube degradations happen in WWER Nuclear Power Plant (NPP). The situation varies from country to country and from NPP to NPP. More severe degradation is observed in WWER-1000 NPPs than in case of WWER-440s. The reasons for these differences could be, among others, differences in heat exchanger tube material (chemical composition, microstructure, residual stresses), in thermal and mechanical loadings, as well as differences in water chemistry. However, WWER steam generators had not been designed for eddy current testing which is the usual testing method in steam generators of western PWRs. Moreover, their supplier provided neither adequate methodology and criteria nor equipment for planning and implementing In-Service Inspection (ISI). Consequently, WWER steam generator ISI infrastructure was established with delay. Even today, there are still big differences in the eddy current inspection strategy and practice as well as in the approach to steam generator heat exchanger tube structural integrity assessment (plugging criteria for defective tubes vary from 40 to 90% wall thickness degradation). Recognizing this situation, the WWER operating countries expressed their need for a joint effort to develop methodology to establish reasonable commonly accepted integrity assessment criteria for the heat exchanger tubes. The IAEA's programme related to steam generator life management is embedded into the systematic activity of its Technical Working Group on Life Management of Nuclear Power Plants (TWG-LMNPP). Under the advice of the TWG-LMNPP, an IAEA coordinated research project (CRP) on Verification of WWER Steam Generator Tube Integrity was launched in 2001. It was completed in 2005. Thirteen organizations involved in in-service inspection of steam generators in WWER operating countries participated: Croatia, Czech Republic, Finland, France, Hungary, Russian Federation, Slovakia, Spain, Ukraine, and the USA. The overall objective was to

  4. PWR steam generator tubing sample library

    International Nuclear Information System (INIS)

    Anon.

    1987-01-01

    In order to compile the tubing sample library, two approaches were employed: (a) tubing sample replication by either chemical or mechanical means, based on field tube data and metallography reports for tubes already destructively examined; and (b) acquisition of field tubes removed from operating or retired steam generators. In addition, a unique mercury modeling concept is in use to guide the selection of replica samples. A compendium was compiled that summarizes field observations and morphologies of steam generator tube degradation types based on available NDE, destructive examinations, and field reports. This compendium was used in selecting candidate degradation types that were manufactured for inclusion in the tube library

  5. Modular steam generator for use in nuclear power plants

    International Nuclear Information System (INIS)

    Cella, A.

    1979-01-01

    An improved steam generator for a PWR is described. A turbine generator is driven by the steam output of the steam generator to provide electrical power. The improvement provides vertically assemblable modules which are removably mounted together in sealing relationship. The modules comprising a base module, a tube bundle module removably mountable on the base module in sealing relationship, and an uppermost dryer module removably mountable on the tube bundle module in sealing relationship. Ready access to and removal of the tube bundle module in situ from the nuclear power plant steam generator is facilitated. The dryer module contains moisture separator for drying the generated steam. The base module, upon which the associated weight of the vertically assembled dryer module and tube bundle module are supported, contains the inlet and outlet for the heat exchange fluid. The tube bundle module contains the tube bundle through which the heat exchange fluid flows as well as an inlet for feedwater. The tube sheet serves as a closure flange for the tube bundle module, with the associated weight of the vertically assembled dryer module and tube bundle module on the tube sheet closure flange effectuating the sealing relationship between the base module and the tube bundle module for facilitating closure

  6. Leak detection in Phenix and Super Phenix steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Cambillard, E [Centre d' Etudes Nucleaires de Saclay, Gif-sur-Yvette (France)

    1978-10-01

    Water leak detection Phenix and Super Phenix steam generators is based on measurement of the hydrogen produced by the reaction of sodium with water. The hydrogen evolves in the sodium in which the steam generator tubes are completely immersed. Depending on service conditions, however (sodium temperature and flow velocity), the hydrogen may appear in the argon existing above the free levels. This is why, although the Phenix steam generators do not feature free levels, measurement systems were added to measure the hydrogen concentration in the argon in the expansion tanks. Super Phenix steam generators are fitted at their outlet with systems for measuring hydrogen in the sodium, and above their free level with a system for measuring hydrogen in the argon. The measurement systems have nickel tube probes connected to circuits kept under vacuum by an ion pump. The hydrogen partial pressure is measured by a mass spectrometer. Super Phenix measurement systems differ from Phenix systems essentially in the temperature regulation of the sodium reaching the nickel tube probes, and in the centralization of the supply and measurement systems of the ion pumps and mass spectrometers. This paper deals with description, calibration and operating conditions of the hydrogen detection systems in sodium and argon in Phenix and Super Phenix steam generators. (author)

  7. Data analysis for steam generator tubing samples

    International Nuclear Information System (INIS)

    Dodd, C.V.

    1996-07-01

    The objective of the Improved Eddy-Current ISI for Steam Generators program is to upgrade and validate eddy-current inspections, including probes, instrumentation, and data processing techniques for inservice inspection of new, used, and repaired steam generator tubes; to improve defect detection, classification and characterization as affected by diameter and thickness variations, denting, probe wobble, tube sheet, tube supports, copper and sludge deposits, even when defect types and other variables occur in combination; to transfer this advanced technology to NRC's mobile NDE laboratory and staff. This report provides a description of the application of advanced eddy-current neural network analysis methods for the detection and evaluation of common steam generator tubing flaws including axial and circumferential outer-diameter stress-corrosion cracking and intergranular attack. The report describes the training of the neural networks on tubing samples with known defects and the subsequent evaluation results for unknown samples. Evaluations were done in the presence of artifacts. Computer programs are given in the appendix

  8. CASTOR - Advanced System for VVER Steam Generator Inspection

    International Nuclear Information System (INIS)

    Mateljak, Petar

    2014-01-01

    From the safety point of view, steam generator is a very important component of a nuclear power plant. Only a thin tube wall prevents leakage of radioactive material from the primary side into the environment. Therefore, it is very important to perform inspections in order to detect pipe damage and apply appropriate corrective actions during outage. Application of the nondestructive examination (NDE) technique, that can locate degradation and measure its size and orientation, is an integral part of nuclear power plant maintenance. The steam generator inspection system is consisted of remotely controlled manipulator, testing instrument and software for data acquisition and analysis. Recently, the inspection systems have evolved to a much higher level of automation, efficiency and reliability resulting in a lower cost and shorter outage time. Electronic components have become smaller and deal with more complex algorithms. These systems are very fast, precise, reliable and easy to handle. The whole inspection, from the planning, examination, data analysis and final report, is now a highly automated process, which makes inspection much easier and more reliable. This paper presents the new generation of INETEC's VVER steam generator inspection system as ultimate solution for steam generator inspection and repair. (author)

  9. Surry steam generator - examination and evaluation

    International Nuclear Information System (INIS)

    Clark, R.A.; Doctor, P.G.; Ferris, R.H.

    1985-10-01

    This report summarizes research conducted during the fourth year of the five year Steam Generator Group Project. During this period the project conducted numerous nondestructive examination (NDE) round robin inspections of the original Surry 2A steam generator. They included data acquisition/analysis and analysis-only round robins using multifrequency bobbin coil eddy current tests. In addition, the generator was nondestructively examined by alternate or advanced techniques including ultrasonics, optical fiber, profilometry and special eddy current instrumentation. The round robin interpretation data were compared. To validate the NDE results and for tube integrity testing, a selection of tubing samples, determined to be representative of the generator, was designated for removal. Initial sample removals from the generator included three sections of tube sheet, two sections of support plate and encompassed tubes, and a number of straight and U-bend tubing sections. Metallographic examination of these sections was initiated. Details of significant results are presented in the following paper. 13 figs

  10. Surry steam generator - examination and evaluation

    Energy Technology Data Exchange (ETDEWEB)

    Clark, R A; Doctor, P G; Ferris, R H

    1987-01-01

    This report summarizes research conducted during the fourth year of the five year Steam Generator Group Project. During this period the project conducted numerous nondestructive examination (NDE) round robin inspections of the original Surry 2A steam generator. They included data acquisition/analysis and analysis-only round robins using multifrequency bobbin coil eddy current tests. In addition, the generator was nondestructively examined by alternate or advanced techniques including ultrasonics, optical fiber, profilometry and special eddy current instrumentation. The round robin interpretation data were compared. To validate the NDE results and for tube integrity testing, a selection of tubing samples, determined to be representative of the generator, was designated for removal. Initial sample removals from the generator included three sections of tube sheet, two sections of support plate and encompassed tubes, and a number of straight and U-bend tubing sections. Metallographic examination of these sections was initiated. Details of significant results are presented in the following paper.

  11. Structural considerations in steam generator replacement

    International Nuclear Information System (INIS)

    Bertheau, S.R.; Gazda, P.A.

    1991-01-01

    Corrosion of the tubes and tube-support structures inside pressurized water reactor (PWR) steam generators has led many utilities to consider a replacement of the generators. Such a project is a major undertaking for a utility and must be well planned to ensure an efficient and cost-effective effort. This paper discusses various structural aspects of replacement options, such as total or partial generator replacement, along with their associated pipe cuts; major structural aspects associated with removal paths through the equipment hatch or through an opening in the containment wall, along with the related removal processes; onsite movement and storage of the generators; and the advantages and disadvantages of the removal alternatives. This paper addresses the major structural considerations associated with a steam generator replacement project. Other important considerations (e.g., licensing, radiological concerns, electrical requirements, facilities for management and onsite administrative activities, storage and fabrication activities, and offsite transportation) are not discussed in this paper, but should be carefully considered when undertaking a replacement project

  12. Reconstruction of steam generators super emergency feadwater supply system (SHNC) and steam dump stations to the atmosphere system PSA

    International Nuclear Information System (INIS)

    Kuzma, J.

    2001-01-01

    Steam Generators Super Emergency Feadwater Supply System (SHNC) and Steam Dump Stations to the Atmosphere System (PSA) are two systems which cooperate to remove residual heat from reactor core after seismic event. SHNC assure feeding of the secondary site of steam generator (Feed) where after heat removal.from primary loops, is relieved to the atmosphere by PSA (Bleed) in form of steam. (author)

  13. Heat transfer characteristics of horizontal steam generators under natural circulation conditions

    International Nuclear Information System (INIS)

    Hyvaerinen, J.

    1996-01-01

    This paper deals with the heat transfer characteristics of horizontal steam generators, particularly under natural circulation (decay heat removal) conditions on the primary side. Special emphasis is on the inherent features of horizontal steam generator behaviour. A mathematical model of the horizontal steam generator primary side is developed and qualitative results are obtained analytically. A computer code, called HSG, is developed to solve the model numerically, and its predictions are compared with experimental data. The code is employed to obtain for VVER 440 steam generators quantitative results concerning the dependence of primary-to-secondary heat transfer efficiency on the primary side flow rate, temperature and secondary level. It turns out that the depletion of the secondary inventory leads to an inherent limitation of the decay energy removal in VVER steam generators. The limitation arises as a consequence of the steam generator tube bundle geometry. As an example, it is shown that the grace period associated with pressurizer safety valve opening during a station black-out is 2 1/2-3 hours instead of the 5-6 hours reported in several earlier studies. (However, the change in core heat-up timing is much less-about 1 h at most.) The heat transfer limitation explains the fact that, in the Greifswald VVER 440 station black-out accident in 1975, the steam generators never boiled dry. In addition, the stability of single-phase natural circulation is discussed and insights on the modelling of horizontal steam generators with general-purpose thermal-hydraulic system codes are also presented. (orig.)

  14. Leakage experiences with 1 MW steam generator

    International Nuclear Information System (INIS)

    Kanamori, A.; Kawara, M.; Sano, A.

    1975-01-01

    An 1 MW steam generator was tested from October, 1971 and completed with the first series of experiments by May, 1972 after 3600 hours of operation. During these tests, unextraordinary heat absorption was experienced in the downcomer region, which led to shortage of heat transfer area to attain the rated steam temperature and to one of the reasons of flow instabilities. The steam generator was disassembled to get test pieces for structure as well as material examinations and then it was reassembled to proceed the second series of tests. Before it was done, a modification was provided to insulate the downcomer region by putting a gas space around the downcomer tube. The gas space was provided by a dual tube and spacers were welded on the inner tube and an end plate was welded on upper parts between the two to seal the gap by means of fillet welding. After the modified steam generator was put into operation, water happened to leak into a sodium side two times through these additional welding spots for the gas insulation. This paper presents operating conditions and behaviors of monitors at the time of the leakages, identifications of leaked spots, an evaluation of causes and a treatment or a precaution for them

  15. Corrosion and Rupture of Steam Generator Tubings in PWRs

    Energy Technology Data Exchange (ETDEWEB)

    Hwang, Seong Sik; Kim, Hong Pyo

    2007-08-15

    This report is intended to provide corrosion engineers in the filed of nuclear energy with information on the corrosion and rupture behavior of steam generator tubing in PWRs. Various types of corrosion in PWR steam generator tubing have been reported all around the world, and countermeasures such as the addition of corrosion inhibitors, a water chemistry control, a tube plugging and sleeving have been applied. Steam generators equipped with alloy 600 tubing, which are not so resistant to a stress corrosion cracking (SCC), have generally been replaced with new steam generators made of alloy 690 TT (Thermally treated). Pull tube examination results which were performed of KAERI are summarized. The tubes were affected by a pitting, SCC, and a denting. Nondestructive examination method for the tubes and repair techniques are also reviewed. In addition, the regulatory guidance of some countries are reviewed. As a part of a tube integrity project in Korea, some results on a tube rupture and leak behaviors for axial cracks are also mentioned.

  16. Corrosion and Rupture of Steam Generator Tubings in PWRs

    International Nuclear Information System (INIS)

    Hwang, Seong Sik; Kim, Hong Pyo

    2007-08-01

    This report is intended to provide corrosion engineers in the filed of nuclear energy with information on the corrosion and rupture behavior of steam generator tubing in PWRs. Various types of corrosion in PWR steam generator tubing have been reported all around the world, and countermeasures such as the addition of corrosion inhibitors, a water chemistry control, a tube plugging and sleeving have been applied. Steam generators equipped with alloy 600 tubing, which are not so resistant to a stress corrosion cracking (SCC), have generally been replaced with new steam generators made of alloy 690 TT (Thermally treated). Pull tube examination results which were performed of KAERI are summarized. The tubes were affected by a pitting, SCC, and a denting. Nondestructive examination method for the tubes and repair techniques are also reviewed. In addition, the regulatory guidance of some countries are reviewed. As a part of a tube integrity project in Korea, some results on a tube rupture and leak behaviors for axial cracks are also mentioned

  17. Steam generator and condenser design of WWER-1000 type of nuclear power plant

    International Nuclear Information System (INIS)

    Zare Shahneh, Abolghasem.

    1995-03-01

    Design process of steam generator and condenser at Russian nuclear power plant type WWER-1000 is identified. The four chapter of the books are organized as nuclear power plant, types of steam generators specially horizontal steam generator, process of steam generator design and the description of condenser and its process design

  18. Steam generators in indirect-cycle water-cooled reactors

    International Nuclear Information System (INIS)

    Fajeau, M.

    1976-01-01

    In the indirect cycle water-cooled nuclear reactors, the steam generators are placed between the primary circuit and the turbine. They act both as an energy transmitter and as a leaktigh barrier against fission or corrosion products. Their study is thus very important from a performance and reliability point of view. Two main types are presented here: the U-tube and the once-through steam generators [fr

  19. Acoustic leak detector in Monju steam generator

    International Nuclear Information System (INIS)

    Wachi, E.; Inoue, T.

    1990-01-01

    Acoustic leak detectors are equipped with the Monju steam generators for one of the R and D activities, which are the same type of the detectors developed in the PNC 50MW Steam Generator Test Facility. Although they are an additional leak detection system to the regular one in Monju SG, they would also detect the intermediate or large leaks of the SG tube failures. The extrapolation method of a background noise analysis is expected to be verified by Monju SG data. (author). 4 figs

  20. Stability study in one step steam generators

    International Nuclear Information System (INIS)

    Abbate, P.

    1990-01-01

    The TWO program is presented developed for the behaviour limit calculation stable in one step steam generators for the case of Density Waves phenomenom. The program is based on a nodal model which, using Laplace transformation equations, allows to study the system's transfer functions and foresee the beginning of the unstable behaviour. This program has been satisfactorily validated against channels data uniformly heated in the range from 4.0 to 6.0 Mpa. Results on the CAREM reactor's steam generator analysis are presented. (Author) [es

  1. Integrated steam generation process and system for enhanced oil recovery

    Energy Technology Data Exchange (ETDEWEB)

    Betzer-Zilevitch, M. [Ex-Tar Technologies Inc., Calgary, AB (Canada)

    2010-07-01

    A method of producing steam for the extraction of heavy bitumens was presented. The direct contact steam generation (DCSG) method is used for the direct heat transfer between combustion gas and contaminated liquid phase water to generate steam. This paper presented details of experimental and field studies conducted to demonstrate the DCSG. Results of the study demonstrated that pressure and temperature are positively correlated. As pressure increases, the flow rate of the discharged mass decreases and the steam ratio decreases. As pressure increases, the condensate and distillate flow rates increases while water vapor losses in the non-condensable gases decrease. The study indicated that for a 10 bar pressurized system producing 9.6 mt per hour of 10,000 kpa steam and 9.6 mt per hour of distillate BFW, 70 percent of the combustion energy should be recovered to generate 10,000 kpa pressure steam for EOR. Combustion energy requirements were found to decrease when pressure decreases. 11 refs., 5 tabs., 8 figs.

  2. SWAAM-code development and verification and application to steam generator designs

    International Nuclear Information System (INIS)

    Shin, Y.W.; Valentin, R.A.

    1990-01-01

    This paper describes the family of SWAAM codes which were developed by Argonne National Laboratory to analyze the effects of sodium-water reactions on LMR steam generators. The SWAAM codes were developed as design tools for analyzing various phenomena related to steam generator leaks and the resulting thermal and hydraulic effects on the steam generator and the intermediate heat transport system (IHTS). The paper discusses the theoretical foundations and numerical treatments on which the codes are based, followed by a description of code capabilities and limitations, verification of the codes and applications to steam generator and IHTS designs. 25 refs., 14 figs

  3. CATHENA simulations of steam generator tube rupture

    International Nuclear Information System (INIS)

    Abdul-Razzak, A.; Lin, M.R.; Wright, A.C.D.

    1997-01-01

    The CATHENA thermalhydraulic computer code was used to simulate various scenarios following a CANDU 9 steam generator tube rupture (SGTR) event. The analysis included cases with class IV power and emergency core cooling system (ECCS) available and other cases with subsequent loss of class IV power (LCIVP) or impairment of ECCS injection. Two main approaches were followed in the analysis of each case. In the first approach, D 2 O feed was credited to provide conservative data for input to radionuclide release and dose calculations. Also operator actions are credited. The other approach is designed to give conservative predictions with respect to the acceptance criteria of fuel and fuel channel integrity and to prove that in case of such event, the operator will have enough time to mitigate the consequences. This is done by not crediting makeup for the inventory loss and relying on the automatic operation of safety systems. The analysis of the cases of the first approach provided the required data for radionuclide release and dose calculations and gave a good insight into the required sequence of operator timely actions to mitigate the consequences of such event. On the other hand, the cases of the second approach confirmed compliance with regulatory requirements for pressure tube and fuel integrity. The runs with ECCS available, showed the ECCS injection is effective in filling and cooling the core and that regulatory requirement's for fuel and channel integrity are met. In the event of ECCS impairment, the earliest indication of late fuel heat-up is late enough to provide the operator with an adequate time to act in mitigating the consequences of this event. (author)

  4. The CANDU-PHW generating system waste arisings

    International Nuclear Information System (INIS)

    Simmons, G.R.

    1979-03-01

    In this report, the volume of material and level of contained radioactive nuclides are tabulated for wastes arising from four fuel cycles which might be operated in CANDU-PHW (CANada Deuterium Uranium - Pressurized Heavy Water) reactors. The data presented, based on Canadian experience and/or studies, cover the range of conditioned waste volumes which could be expected from steady-state (no growth), CANDU-PHW-powered electrical generating systems. The wastes arising from operation and decommissioning of facilities in each phase of each fuel cycle are estimated. Each fuel cycle is considered to operate in isolation with the data given in terms of quantities per gigawatt-year of electricity produced. Three of the fuel cycles for which data are presented, the natural uranium once-through cycle, the plutonium-enriched uranium cycle (plutonium recycle) and the low-burnup uranium-enriched thorium cycle (thorium and uranium recycle), were studied by INFCE WG.7 (the International Nuclear Fuel Cycle Evaluation, Working Group 7) as fuel cycles 4, 5 and 6. The high-burnup uranium-enriched thorium cycle is included for comparison. INFCE WG.7 selected many common reference parameters which are applied uniformly to all seven INFCE WG.7 reference fuel cycles in determining waste arisings. Where these parameters differ from the data of Canadian origin given in the body of this report, the INFCE WG.7 data are given in an appendix. The waste management costs associated with operation of each INFCE WG.7 reference fuel cycle were calculated and compared by the working group. An arbitrary set of costing parameters and disposal technologies was selected by the working group for application to each of the reference fuel cycles. The waste management and disposal costs for the PHW reactor fuel cycles based on these arbitrary cost parameters are given in an appendix. (author)

  5. Dependence of steam generator vibrations on feedwater pressure

    International Nuclear Information System (INIS)

    Sadilek, J.

    1989-01-01

    Vibration sensors are attached to the bottom of the steam generator jacket between the input and output primary circuit collectors. The effective vibration value is recorded daily. Several times higher vibrations were observed at irregular intervals; their causes were sought, and the relation between the steam generator vibrations measured at the bottom of its vessel and the feedwater pressure was established. The source of the vibrations was found to be in the feedwater tract of the steam generator. The feedwater tract is described and its hydraulic characteristics are given. Vibrations were measured on the S02 valve. It is concluded that vibrations can be eliminated by reducing the water pressure before the control valves and by replacing the control valves with ones with more suitable control characteristics. (E.J.). 3 figs., 1 tab., 3 refs

  6. Thermo-hydraulic stability study of a steam generator

    International Nuclear Information System (INIS)

    Magni, M C; Marcel, C P; Delmastro, D F

    2012-01-01

    In this work a mathematical model developed to investigate the thermalhydraulic stability of a helically coiled steam generator is presented. Such a steam generator is prone to experiment density wave oscillations. The model is therefore used to analyze the stability of the CAREM-25 reactor steam generators. The model is linear, numerically non-diffusive and nodal. In addition, it is able to represent non-uniform heat transfer fluxes between the primary and secondary coolant circuits. By using this model the marginal stability condition is found by varying the inlet friction coefficient for different conditions. The results are then compared with those obtained with a different model for which a simple uniform heat flux profiled is assumed. It is found that with such simplification the density waves instability mechanism is overestimated in a wide range of operating powers. For very low powers, in the contrary, the so-called uniform model underestimates the stabilizing inlet friction and therefore it gives non-conservative results. With the use of the more realistic non-uniform power profile model, it was possible to determine that, for a CAREM-25 steam generator, the most stable conditions is found at 60MW when the reactor operates at nominal pressure. Moreover, it is found that at high power levels the stability performance is dominated by the two-phase friction component while at low power levels the friction component originated in the over heated steam region prevail (author)

  7. A passive emergency heat sink for water cooled reactors with particular application to CANDU reg-sign reactors

    International Nuclear Information System (INIS)

    Spinks, N.J.

    1996-01-01

    Water in an overhead pool can serve as a general-purpose passive emergency heat sink for water-cooled reactors. It can be used for containment cooling, for emergency depressurization of the heat transport-system, or to receive any other emergency heat, such as that from the CANDU reg-sign moderator. The passive emergency water system provides in-containment depressurization of steam generators and no other provision is needed for supply of low-pressure emergency water to the steam generators. For containment cooling, the pool supplies water to the tube side of elevated tube banks inside containment. The elevation with respect to the reactor heat source maximizes heat transport, by natural convection, of hot containment gases. This effective heat transport combines with the large heat-transfer coefficients of tube banks, to reduce containment overpressure during accidents. Cooled air from the tube banks is directed past the break in the heat-transport system, to facilitate removal of hydrogen using passive catalytic recombiners

  8. Aerosol retention in the flooded steam generator bundle during SGTR

    International Nuclear Information System (INIS)

    Lind, Terttaliisa; Dehbi, Abdel; Guentay, Salih

    2011-01-01

    Research highlights: → High retention of aerosol particles in a steam generator bundle flooded with water. → Increasing particle inertia, i.e., particle size and velocity, increases retention. → Much higher retention of aerosol particles in the steam generator bundle flooded with water than in a dry bundle. → Much higher retention of aerosol particles in the steam generator bundle than in a bare pool. → Bare pool models have to be adapted to be applicable for flooded bundles. - Abstract: A steam generator tube rupture in a pressurized water reactor may cause accidental release of radioactive particles into the environment. Its specific significance is in its potential to bypass the containment thereby providing a direct pathway of the radioactivity from the primary circuit to the environment. Under certain severe accident scenarios, the steam generator bundle may be flooded with water. In addition, some severe accident management procedures are designed to minimize the release of radioactivity into the environment by flooding the defective steam generator secondary side with water when the steam generator has dried out. To extend our understanding of the particle retention phenomena in the flooded steam generator bundle, tests were conducted in the ARTIST and ARTIST II programs to determine the effect of different parameters on particle retention. The effects of particle type (spherical or agglomerate), particle size, gas mass flow rate, and the break submergence on particle retention were investigated. Results can be summarized as follows: increasing particle inertia was found to increase retention in the flooded bundle. Particle shape, i.e., agglomerate or spherical structure, did not affect retention significantly. Even with a very low submergence, 0.3 m above the tube break, significant aerosol retention took place underlining the importance of the jet-bundle interactions close to the tube break. Droplets were entrained from the water surface with

  9. Design and related R and D works of 'Monju' steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Nakai, Y; Imanaka, N; Hoshi, Y; Tanaka, K; Hori, M; Yoshikawa, Y

    1975-07-01

    The steam generator is considered to be one of the key components in LMFBR plant. Helical coil type steam generator is selected as a reference for the first Japanese demonstration plant 'MONJU'. The paper gives the structural and functional features of 'MONJU' steam generator together with a brief description of secondary cooling system. The related R and D works are also illustrated. (author)

  10. The CANDU 9 distributed control system design process

    International Nuclear Information System (INIS)

    Harber, J.E.; Kattan, M.K.; Macbeth, M.J.

    1997-01-01

    Canadian designed CANDU pressurized heavy water nuclear reactors have been world leaders in electrical power generation. The CANDU 9 project is AECL's next reactor design. Plant control for the CANDU 9 station design is performed by a distributed control system (DCS) as compared to centralized control computers, analog control devices and relay logic used in previous CANDU designs. The selection of a DCS as the platform to perform the process control functions and most of the data acquisition of the plant, is consistent with the evolutionary nature of the CANDU technology. The control strategies for the DCS control programs are based on previous CANDU designs but are implemented on a new hardware platform taking advantage of advances in computer technology. This paper describes the design process for developing the CANDU 9 DCS. Various design activities, prototyping and analyses have been undertaken in order to ensure a safe, functional, and cost-effective design. (author)

  11. Secondary coolant circuit operation tests: steam generator feedwater supply

    International Nuclear Information System (INIS)

    Beroux, M.

    1985-01-01

    No one important accident occurred during the start-up tests of the 1300MWe P4 series, concerning the feedwater system of steam generators (SG). This communication comments on some incidents, that the tests allowed to detect very soon and which had no consequences on the operation of units: 1) Water hammer in feedwater tubes, and incidents met in the emergency steam generator water supply circuit. The technological differences between SG 900 and 1300 are pointed out, and the measures taken to prevent this problem are presented. 2) Incidents met on the emergency feedwater supply circuit of steam generators; mechanical or functional modifications involved by these incidents [fr

  12. SNR-steam generator design with respect to large sodium water reactions

    International Nuclear Information System (INIS)

    Jong, J.J. de; Kellner, A.; Florie, C.J.L.

    1984-01-01

    This paper deals with the experiences gained during the licensing procedure for the steam generators for the SNR 300 LMFBR regarding large sodium-water reactions. A description is given of the different calculations executed to investigate the effects of large leaks on the 85 MW helical coiled and straight tube steam generators. The investigations on the helical coiled steam generators are divided in the formulations of fluid behaviour, dynamic force calculations, dynamic response calculation and finally stress analyses. Several results are shown. The investigations on the straight tube steam generators are performed using models describing fluid-structure interaction, coupled with stress analyses. Several results are presented. A description is given of the problems and necessary construction changes during the licensing process. Advises are given for future analyses and design concepts for second generation commercial size LMFBR steam generators with respect to large leaks; based on the experience, gained with SNR 300, and using some new calculations for SNR 2. (author)

  13. Expandable antivibration bar for a steam generator

    International Nuclear Information System (INIS)

    Lagally, H.O.

    1986-01-01

    A steam generator tube support structure comprises expandable antivibration bars positioned between rows of tubes in the steam generator and attached to retaining rings surrounding the bundle of tubes. The antivibration bars have adjacent bar sections with mating surfaces formed as inclined planes which upon relative longitudinal motion between the upper and lower bars provides a means to increase the overall thickness across the structure to the required value. The bar section is retained against longitudinal movement in take-up assembly whereas the bar section is movable longitudinally by rotation of a nut. (author)

  14. Thermodynamic analysis of heat recovery steam generator in combined cycle power plant

    Directory of Open Access Journals (Sweden)

    Ravi Kumar Naradasu

    2007-01-01

    Full Text Available Combined cycle power plants play an important role in the present energy sector. The main challenge in designing a combined cycle power plant is proper utilization of gas turbine exhaust heat in the steam cycle in order to achieve optimum steam turbine output. Most of the combined cycle developers focused on the gas turbine output and neglected the role of the heat recovery steam generator which strongly affects the overall performance of the combined cycle power plant. The present paper is aimed at optimal utilization of the flue gas recovery heat with different heat recovery steam generator configurations of single pressure and dual pressure. The combined cycle efficiency with different heat recovery steam generator configurations have been analyzed parametrically by using first law and second law of thermodynamics. It is observed that in the dual cycle high pressure steam turbine pressure must be high and low pressure steam turbine pressure must be low for better heat recovery from heat recovery steam generator.

  15. North Anna Power Station - Unit 1: Overview of steam generator replacement project activities

    International Nuclear Information System (INIS)

    Gettler, M.W.; Bayer, R.K.; Lippard, D.W.

    1993-01-01

    The original steam generators at Virginia Electric and Power Company's (Virginia Power) North Anna Power Station (NAPS) Unit 1 have experienced corrosion-related degradation that require periodic inspection and plugging of steam generator tubes to ensure their continued safe and reliable operation. Despite improvements in secondary water chemistry, continued tube degradation in the steam generators necessitated the removal from service of approximately 20.3 percent of the tubes by plugging, (18.6, 17.3, and 25.1 for steam generators A, B, and C, respectively). Additionally, the unit power was limited to 95 % during, its last cycle of operation. Projections of industry and Virginia Power experience indicated the possibility of mid-cycle inspections and reductions in unit power. Therefore, economic considerations led to the decision to repair the steam generators (i.e., replace the steam generator lower assemblies). Three new Model 51F Steam Generator lower assembly units were ordered from Westinghouse. Virginia Power contracted Bechtel Power Corporation to provide the engineering and construction support to repair the Unit 1 steam generators. On January 4, 1993, after an extended coastdown period, North Anna Unit 1 was brought off-line and the 110 day (breaker-to-breaker) Steam Generator Replacement Project (SGRP) outage began. As of this paper, the outage is still in progress

  16. Handling steam generator problems: the strategy for Ringhals 3 and 4

    International Nuclear Information System (INIS)

    Larsen, G.

    1992-01-01

    An examination in Sweden of twelve Pressurized Water Reactor steam generator tubes (six from Ringhals 3 and six from Ringhals 4) revealed that several had cracks in the roll transition zone, all tubes had shallow intergranular attacks at support plate (TSP) intersections, and some from Ringhals 3 had cracks in the TSP position due to intergranular stress corrosion. It was concluded that this could drastically limit the possibility of successfully operating Ringhals 3 (which entered commercial operation in 1981) to 2010, the year when all nuclear power in Sweden will be phased out. Two possible ways to deal with the problem were investigated: replace the steam generators and uprate the plant; operate with the existing steam generators and reduce the rate of degradation by lowering the primary water temperature, with most failed tubes repaired by sleeving. The analysis showed that replacement of the Ringhals 3 steam generators would be a good investment. As there were no attacks in the TSP intersections at Ringhals 4, which started commercial operation in 1983, it was assumed possible to operate this unit until 2010 without any temperature reduction. The economic evaluation for Ringhals 4 nevertheless indicated that it would be cost effective to replace the steam generators and uprate Ringhals 4 to 112%. However, a new economic study showed that it will still be cost effective to replace the steam generators at Ringhals 3, but it is not clear that there is still a case for replacement at Ringhals 4. Ringhals 3 steam generators will be replaced in 1995, while Ringhals 4 will continue to operate with the existing steam generators. (Author)

  17. Wasteless combined aggregate-coal-fired steam-generator/melting-converter

    International Nuclear Information System (INIS)

    Pioro, L.S.; Pioro, I.L.

    2003-01-01

    A method of reprocessing coal sludge and ash into granulate for the building industry in a combined wasteless aggregate-steam-generator/melting-converter was developed and tested. The method involves melting sludge and ash from coal-fired steam-generators of power plants in a melting-converter installed under the steam-generator, with direct sludge drain from the steam generator combustion chamber. The direct drain of sludge into converter allows burnup of coal with high ash levels in the steam-generator without an additional source of ignition (natural gas, heating oil, etc.). Specific to the melting process is the use of a gas-air mixture with direct combustion inside a melt. This feature provides melt bubbling and helps to achieve maximum heat transfer from combustion products to the melt, to improve mixing, to increase rate of chemical reactions and to improve the conditions for burning the carbon residue from the sludge and ash. The 'gross' thermal efficiency of the combined aggregate is about 93% and the converter capacity is about 18 t of melt in 100 min. The experimental data for different aspects of the proposed method are presented. The effective ash/charging materials feeding system is also discussed. The reprocessed coal ash and sludge in the form of granules can be used as fillers for concretes and as additives in the production of cement, bricks and other building materials

  18. Tube tightness survey during Phenix steam generator operation

    International Nuclear Information System (INIS)

    Cambillard, E.

    1976-01-01

    Phenix steam generators are once-through vessels with single-wall heat-exchange tubes. This design means that any leakage of water into the sodium must be detected as quickly as possible so that the installation can be shut down before extensive damage occurs. The detection of water leaks in Phenix steam generators is based on measurement of the concentration in the sodium, of hydrogen produced by the sodium-water reaction. Since the various modules--evaporators, superheaters, and reheaters--have no free sodium surfaces, detection of hydrogen in argon is not used in Phenix steam generators. The measurement systems employ a probe made of nickel tubes 0.3 mm thick. Hydrogen in the sodium diffuses into a chamber kept under vacuum by an ion pump. The hydrogen pressure in the chamber is measured by a quadrupole mass spectrometer. The nine measurement systems (three per steam generator) are calibrated by injecting hydrogen into the sodium of the secondary circuits. The data-processing computer calculates the hydrogen concentration in the sodium from the spectrometer signals and the probe temperatures, which are not regulated in Phenix; it generates instructions that enable the operator to act if a leak appears. So far, no leaks have been detected. These systems also make it possible to determine rates of hydrogen diffusion caused by corrosion of the steel walls on the water side

  19. Thermo hydrodynamical analyses of steam generator of nuclear power plant

    International Nuclear Information System (INIS)

    Petelin, S.; Gregoric, M.

    1984-01-01

    SMUP computer code for stationary model of a U-tube steam generator of a PWR nuclear power plant was developed. feed water flow can enter through main and auxiliary path. The computer code is based on the one dimensional mathematical model. Among the results that give an insight into physical processes along the tubes of steam generator are distribution of temperatures, water qualities, heat transfer rates. Parametric analysis permits conclusion on advantage of each design solution regarding heat transfer effects and safety of steam generator. (author)

  20. Dynamic and control of a once through steam generator

    International Nuclear Information System (INIS)

    Gomes, Arivaldo Vicente

    1979-01-01

    This paper presents a non linear distributed parameter model for the dynamics and feedback control of a large countercurrent heat exchanger used as a once through steam generator for a breeder reactor power plant. A convergent, implicit method has been developed to solve simultaneously the equations of conservation of mass, momentum and energy. The model, applicable to heat exchanger systems in general, has been used specifically to study the performance of a once-through steam generator with respect to its load following ability and stability of throttle steam temperature and pressure. (author)

  1. Evaluation of a dryer in a steam generator

    International Nuclear Information System (INIS)

    Xue Yunkui; Liu Shixun; Guandao, Xie; Chen Junliang

    1998-01-01

    The hooked-vane-type dryer is used in vertical, natural circulation steam generators used in PWR-type nuclear power stations. it separates the fine droplets of water carried by steam so that the steam generator outlet steam moisture is below 0.25%. Such low moisture is demanded to ensure a safe and economic operation of the unit. The dryer is composed of hooked vanes and a draining structure. A series of tests to screen different designs were performed using air-water mixture. The paper presents the results of the investigation of the effect of the number of drainage hooks , the bending angle , distance between two adjacent vanes, and other geometrical parameters on the performance of a hooked-vane-type steam dryer. It indicates that the dryer still works effectively when the moisture of the steam at the dryer inlet changes in a wide range, and that the performance of the dryer is closely related to the geometry of the draining structure . On the basis of the results of this program, a draining structure with an original design was selected and it is presented in the paper. The performance of the selected draining structure is better than that of similar structures in China and abroad. (author)

  2. Automation of steam generator services at public service electric & gas

    Energy Technology Data Exchange (ETDEWEB)

    Cruickshank, H.; Wray, J.; Scull, D. [Public Service Electric & Gas, Hancock`s Bridge, NJ (United States)

    1995-03-01

    Public Service Electric & Gas takes an aggressive approach to pursuing new exposure reduction techniques. Evaluation of historic outage exposure shows that over the last eight refueling outages, primary steam generator work has averaged sixty-six (66) person-rem, or, approximately tewenty-five percent (25%) of the general outage exposure at Salem Station. This maintenance evolution represents the largest percentage of exposure for any single activity. Because of this, primary steam generator work represents an excellent opportunity for the development of significant exposure reduction techniques. A study of primary steam generator maintenance activities demonstrated that seventy-five percent (75%) of radiation exposure was due to work activities of the primary steam generator platform, and that development of automated methods for performing these activities was worth pursuing. Existing robotics systems were examined and it was found that a new approach would have to be developed. This resulted in a joint research and development project between Westinghouse and Public Service Electric & Gas to develop an automated system of accomplishing the Health Physics functions on the primary steam generator platform. R.O.M.M.R.S. (Remotely Operated Managed Maintenance Robotics System) was the result of this venture.

  3. Operating experience of steam generator test facility

    International Nuclear Information System (INIS)

    Sureshkumar, V.A.; Madhusoodhanan, G.; Noushad, I.B.; Ellappan, T.R.; Nashine, B.K.; Sylvia, J.I.; Rajan, K.K.; Kalyanasundaram, P.; Vaidyanathan, G.

    2006-01-01

    Steam Generator (SG) is the vital component of a Fast Reactor. It houses both water at high pressure and sodium at low pressure separated by a tube wall. Any damage to this barrier initiates sodium water reaction that could badly affect the plant availability. Steam Generator Test Facility (SGTF) has been set up in Indira Gandhi Centre for Atomic Research (IGCAR) to test sodium heated once through steam generator of 19 tubes similar to the PFBR SG dimension and operating conditions. The facility is also planned as a test bed to assess improved designs of the auxiliary equipments used in Fast Breeder Reactors (FBR). The maximum power of the facility is 5.7 MWt. This rating is arrived at based on techno economic consideration. This paper covers the performance of various equipments in the system such as Electro magnetic pumps, Centrifugal sodium pump, in-sodium hydrogen meters, immersion heaters, and instrumentation and control systems. Experience in the system operation, minor modifications, overall safety performance, and highlights of the experiments carried out etc. are also brought out. (author)

  4. Joint studies on large CANDU

    International Nuclear Information System (INIS)

    Lee, Ikhwan; Yu, S. K. W.

    1994-01-01

    from economic, safety and strategic viewpoints. A large number of research and development programs are now in place at AECL and KAERI that will permit substantial improvements to be realized in the next generation of CANDU okabts, Furthermore, opportunities exist for engineered improvements based on the research and development in advancing the generic CANDU Technology. Final Large CANDU joint study report with technical deliverables will be issued 1994 October. Phase 2 R and D program of the joint studies will be determined this year and implemented in next year. CANDU neutron economy permits versatility in choices of fuel cycles. This allows a utility to choose fuel cycle options for lower fuelling cost, better security of supply, and ultimately for much lower spent-fuel volume, than with PWR's alone. To meet Korea's strategic requirements, CANDU should be an integral part of the electricity supply mix.

  5. The decommissioning of the BR3 steam generator

    International Nuclear Information System (INIS)

    Denissen, L.

    2006-01-01

    A steam generator is a crucial component in a PWR (Pressurized Water Reactor). It is the crossing between the primary, contaminated, circuit and the secondary water-steam circuit. The heat from the primary reactor coolant loop is transferred to the secondary side in thousands of small tubes. Due to several problems in the material of those tubes, like SCC (Stress Corrosion Cracking), insufficient control in water chemistry, which can be the cause of tube leakage, more and more steam generators are replaced today. Only in Belgium, already 17 of them are replaced. The old 300 ton heavy SGs are stored at the 2 nuclear power plants of Doel and Tihange . While it was foreseen in the BR3 strategy to dismantle the steam generator (only 30 ton), we took the opportunity to search for a complete package in the decommissioning of a steam generator. The complete management consists of a decontamination of the primary side followed by the complete dismantling. The first step, the decontamination with MEDOC (water box + tube bundle) has already been achieved in 2002. It has led to an important DF (Decontamination Factor) between 100 and 1000 and an important dose rate reduction. This hard chemical decontamination process has been described earlier in the scientific report 2002 (The BR3 steam generator decontamination with the MEDOC process - M. Ponnet). The second step, the complete dismantling of the SG has been executed in 2005. With the BR3 SG, the main goal was to dismantle it in a safe way and to free release a maximum of material. We've used two cutting tools to perform the job: A HPWJC (High Pressure Water Jet Cutting) tool in combination with a hydraulic robot and a water cooled diamond cable. The last technique was done in close collaboration with the external company Husqvarna. It was important to have an idea of the performance, the efficiency of the cable and the quantity and the type of secondary waste

  6. Steam generator for pressurized-water reactors

    International Nuclear Information System (INIS)

    Michel, E.

    1971-01-01

    In the steam generator for a PWR the central fall space of a U-tube bundel heat exchanger is used as a preliminary cyclon separator. The steam escaping upwards, which is largely free of water, can flow through the residual heating surface, i.e. the U-tube turns. In this way substantial drying and less superheating by the heat still added becomes possible. In its upper part the central fall space for the water separated in the preliminary separator, enclosed by a cylindrical guide wall and the U-tube bundle, is provided with tangential inlet slots. Through these, the water-steam mixture steams out of the section of the vertical legs of the U-tube bundle into the fall space. Above the inlet slots the rising space is closed by means of a turn-round plate. At the lower end of the guide wall outlet, slots are provided for the water flowing downwards and radially outwards into the unfilled space. (DG/PB) [de

  7. On the speed of response of an FPGA-based shutdown system in CANDU nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    She Jingke, E-mail: jshe2@uwo.ca [Department of Electrical and Computer Engineering, The University of Western Ontario, London, Ontario, N6A 5B9 (Canada); Jiang Jin, E-mail: jjiang@eng.uwo.ca [Department of Electrical and Computer Engineering, The University of Western Ontario, London, Ontario, N6A 5B9 (Canada)

    2011-06-15

    Highlights: > Design and implementation of an FPGA-based CANDU SDS1. > Hardware-in-the-loop simulation for performance evaluation involved with an NPP simulator. > Comparison of the response time between FPGA-based trip channel and software-based PLC. - Abstract: Several issues in an FPGA based implementation of shutdown systems in CANDU nuclear power plants have been investigated in this paper. A particular attention is on the response time of an FPGA implementation of safety shutdown systems in comparison with operating system based software solutions as in existing CANDU plants. The trip decision logic under 'steam generator (SG) level low' condition has been examined in detail. The design and implementation of this logic on an FPGA platform have been carried out. The functionality tests are performed in a hardware-in-the-loop (HIL) environment by connecting the FPGA based system to an NPP simulator, and replacing one channel of Shutdown System Number 1 (SDS1) in the simulator by the FPGA implementation. The response time of the designed system is also measured through multiple tests under different conditions, and statistical data analysis has been performed. The results of the response time tests are compared against those of a software-based implementation of the same trip logic.

  8. Leak detection of steam or water into sodium in steam generators of liquid-metal fast breeder reactors

    International Nuclear Information System (INIS)

    Hans, R.; Dumm, K.

    1977-01-01

    The leakage of water or steam into sodium in LMFBR steam generators, including a study of how leaks are detected and located as well as the potential damage that could be caused by such leaks, is surveyed. The most interesting steam generator designs evolving in those countries that develop and construct LMFBRs are presented. The relevant protection measures are described. Fault conditions are defined and descriptions given of possible sequences of events leading to abnormal conditions in a steam generator. Taking into account theory, the potential of the hydrogen and oxygen detection systems is discussed. Different hydrogen and oxygen detection systems are fully described. In so far as interesting technical solutions are concerned, previously developed devices have also been taken into account. The way oxygen detection supplements hydrogen detection is described by listing the available oxygen measuring devices and the relevant theory. Only a few sonic and accelerometer measurements have been made on complete steam generator units so there is little system data available. Descriptions, however, have been included to give the state of the art achieved for the sensors and the achieved sensitivities or band widths. The potential of this monitoring method is made evident by adding the technical data of the sensors. Furthermore, the available systems for monitoring medium and large leakages are described. Finally, recommendations are made concerning steam generator development and the application of hydrogen and oxygen detection systems, as well as acoustic measuring methods for small-leakage detection

  9. A reflux capsule steam generator for sodium cooled reactors

    International Nuclear Information System (INIS)

    Lantz, E.

    Pressurized water reactor plants at numerous sites have sustained significant leakage through their steam generators. The consequent shutdowns for repairs and replacements have damaged their economics. This experience suggests that if steam generators for liquid metal fast breeder reactors (LMFBR's) continue to be built as presently designed some of them will have similar problems. Because of their larger capital investment, the consequent damage to the economics of LMFBR's could be more serious. Reflux capsules provide a way to separate sodium from water and to reduce thermal stresses in steam generators for sodium cooled reactors. Their use would also eliminate the need for a primary heat exchanger and a secondary sodium loop pump. (author)

  10. 46 CFR 54.01-10 - Steam-generating pressure vessels (modifies U-1(g)).

    Science.gov (United States)

    2010-10-01

    ... 46 Shipping 2 2010-10-01 2010-10-01 false Steam-generating pressure vessels (modifies U-1(g)). 54... ENGINEERING PRESSURE VESSELS General Requirements § 54.01-10 Steam-generating pressure vessels (modifies U-1(g)). (a) Pressure vessels in which steam is generated are classed as “Unfired Steam Boilers” except as...

  11. Slurry steam generator program and baseline eddy current examination

    International Nuclear Information System (INIS)

    Clark, R.A.; Doctor, P.G.

    1985-01-01

    The Steam Generator Group Project was initiated in January 1982 with formation of consortium including NRC, EPRI, Japanese, French, and Italian participants. The project utilizes a retired-from-service nuclear steam generator established in a specially designed facility which houses the unit in its normal vertical operating position. The most important objectives deal with validation of nondestructive examination (NDE) techniques used to characterize steam generators during service. This research generator offers the first opportunity to characterize a statistically significant number of service-induced defects nondestructively followed by destructive metallographic confirmation. The project seeks to establish the reliability of defect detection and the accuracy of sizing defects via current state-of-the-art NDE. Other service degraded tubes will be burst tested to establish remaining service integrity. The integrity information and NDE reliability results will serve as inputs to establish a model for steam generator in-service inspections, and provide a data base for evaluation of tube plugging criteria. In addition to NDE validation goals, the project will use the service degraded generator as a specimen for demonstration/proof testing of repair and maintenance techniques, including chemical cleaning/decontamination technologies. In addition to the efforts associated with NDE, a multitude of other project tasks have continued through 1984, and results are presented

  12. Surry steam generator program and baseline eddy current examination

    International Nuclear Information System (INIS)

    Clark, R.A.; Doctor, P.G.

    1985-01-01

    The Steam Generator Group Project was initiated in January 1982 with formation of consortium including NRC, EPRI, Japanese, French, and Italian participants. The project utilizes a retired-from-service nuclear steam generator established in a specially designed facility which houses the unit in its normal vertical operating position. The most important objectives deal with validation of nondestructive examination (NDE) techniques used to characterize steam generators during service. This research generator offers the first opportunity to characterize a statistically significant number of service-induced defects nondestructively followed by destructive metallographic confirmation. The project seeks to establish the reliability of defect detection and the accuracy of sizing defects via current state-of-the-art NDE. Other service degraded tubes will be burst tested to establish remaining service integrity. The integrity information and NDE reliability results will serve as inputs to establish a model for steam generator in-service inspections, and provide a data base for evaluation of tube plugging criteria. In addition to NDE validation goals, the project will use the service degraded generator as a specimen for demonstration/proof testing of repair and maintenance techniques, including chemical cleaning/decontamination technologies. In addition to the efforts associated with NDE, a multitude of other project tasks have continued through 1984, and results are presented

  13. Conceptual design study of Cu bonded steam generator

    International Nuclear Information System (INIS)

    Chikazawa, Yoshitaka; Konomura, Mamoru

    2004-05-01

    In phase II of feasibility study of commercialized fast reactor cycle systems of JNC, we make a concept of a sodium cooled reactor without secondary sodium circuits. And a sodium cooled reactor with Cu bonded steam generators is one of promising concept. As the result of FY 2001 study, the construction cost of reactor cooling system with rectangular tube Cu bonded steam generators is 0.71 to 1.23 times as much as that of an ordinary sodium cooled reactor with secondary sodium circuits. In the FY 2003 study, plastic and creep analysis to evaluate life distortion are carried out and inelastic strains and creep fatigue damage are checked for full code compliance. The NNC's crack growth experiments show that there are few possibility to penetrate a crack from the steam tube side to the sodium tube side at the operating temperature. But penetration is observed in a four point bend test at the room temperature, because the notch opens widely in the bend test. In the FY 2004 study, a gas pressurized crack growth experiment is planed to confirm that there is no crack penetration in the condition of operating steam generators. (author)

  14. Steam generator tubesheet waterlancing at Bruce B

    Energy Technology Data Exchange (ETDEWEB)

    Persad, R. [Babcock and Wilcox Canada, Cambridge, Ontario (Canada); Eybergen, D. [Bruce Power, Tiverton, Ontario (Canada)

    2006-07-01

    High pressure water cleaning of steam generator secondary side tubesheet surfaces is an important and effective strategy for reducing or eliminating under-deposit chemical attack of the tubing. At the Bruce B station, reaching the interior of the tube bundle with a high-pressure water lance is particularly challenging due to the requirement to setup on-boiler equipment within the containment bellows. This paper presents how these and other design constraints were solved with new equipment. Also discussed is the application of new high-resolution inter-tube video probe capability to the Bruce B steam generator tubesheets. (author)

  15. Specialists' meeting on maintenance and repair of LMFBR steam generators. Summary report

    International Nuclear Information System (INIS)

    2002-01-01

    The purpose of the meeting was to review and discuss the experience accumulated in various countries on the general design philosophy of LMFBR steam generators from the view point of maintenance and repair, in-service inspection of steam generator tube bundles, identification and inspection of failed tubes and the cleaning and repairing of failed steam generators. The following main topic areas were discussed by participants: National review presentations on maintenance and repair of LMFBR steam generators - design philosophy for maintenance and repair; Research and Development work on maintenance and repair; Experience on steam generator maintenance and repair. During the meeting papers were presented by the participants on behalf of their countries and organizations. A final discussion session was held and summaries, general conclusions and recommendations were approved by consensus

  16. Influence of feedwater and blowdown systems on the mineral distribution in WWER steam generators

    International Nuclear Information System (INIS)

    Pappx, L.

    1994-01-01

    After modification of Dukovany NPP steam generator feedwater system, the increased concentration of minerals was measured in the cold leg of modified steam generator. Some modifications were performed on operating WWER 1000 steam generators with aim to optimize the water chemistry in the collectors area. Since the distribution of minerals can substantially affect on corrosion processes in steam generators, VITKOVICE, as a producer of WWER steam generators, has focused this attention on the optimizing of these systems. To predict the mineral distribution on the secondary side of steam generators for considered feedwater/blowdown systems, the simple model of flow distribution in the secondary side of SG was developed. (Author)

  17. Maintenance, rehabilitation, long life-the CANDU potential

    International Nuclear Information System (INIS)

    Torgerson, D.F.; Charlebois, P.; Hopkins, J.

    1998-01-01

    Plant life extension beyond the original design life is becoming an attractive economic consideration in the nuclear industry. Plant Life Management and life extension considerations have been built into the complete life cycle of the CANDU plant. The plant life management studies demonstrate that life extension for operating plants beyond 30 years is economically viable. The new CANDU designs benefit from this experience feedback and as a result, the plant design basis is now 40 years or better with potential for economical life extension. AECL is therefore confident that the new CANDU designs will exceed the performance record of the first generation CANDU 6 units and is committed to providing continued support and services during the operating life of the plant

  18. Chemical cleaning as an essential part of steam generator asset management

    International Nuclear Information System (INIS)

    Stiepani, C.; Ammann, F.; Jones, D.; Evans, S.; Harper, K.

    2010-01-01

    Accumulation of deposits is intrinsic for the operation of Steam Generators in PWRs. Such depositions often lead to reduction of thermal performance, loss of component integrity and, in some cases to power restrictions. Accordingly removal of such deposits is an essential part of the asset management of the Steam Generators in a Nuclear Power Plant. Every plant has its individual condition, history and constraints which need to be considered when planning and performing a chemical cleaning. Typical points are: Sludge load amount and constitution of the deposits; Sludge distribution in the steam generator; Existing or expected corrosion problems; Amount and treatment possibilities for the waste generated. Depending on these points the strategy for chemical cleaning shall be evolved. The range of treatment starts with very soft cleanings with a removal of approx 100 kg per steam generator and goes to a full scale cleaning which can remove up to several thousand kilograms of deposits from a steam generator. Depending on the goal to be achieved and the steam generator present an adequate cleaning method shall be selected. Flexible and 'customizable' cleaning methods that can be adapted to the individual needs of a plant are therefore a must. Particular for the application of preventive cleanings where repeated or even regular application are intended, special focus has to be put on low corrosion and easy waste handling. Therefore AREVA has developed the 'C3' concept, Customized Chemical Cleaning concept. This concept covers the entire range of steam generator cleaning. Particular for the preventive maintenance cleanings processes with extreme low corrosion rates and easy waste handling are provided which make repeated applications safe and cost efficient. (author)

  19. Influence of recycling ratio on steam generator thermal recycling

    International Nuclear Information System (INIS)

    Bassel, W.S.; Rodrigues, V.G.

    1989-01-01

    A mathematical model was developed to simulate thermal performance of steam generator. The simulation was done with 3 control volumes. The coupled non-linear algebric equations, where the heat transfer was calculated with logarithmic meam temperature difference, was solved by iterative method. The developed model is suitable for calculation the parameters which effect the performance of steam generator. (author) [pt

  20. MHTGR steam generator on-line heat balance, instrumentation and function

    International Nuclear Information System (INIS)

    Klapka, R.E.; Howard, W.W.; Etzel, K.T.; Basol, M.; Karim, N.U.

    1991-09-01

    Instrumentation is used to measure the Modular High Temperature Gas-Cooled Reactor (MHTGR) steam generator dissimilar metal weld temperature during start-up testing. Additional instrumentation is used to determine an on-line heat balance which is maintained during the 40 year module life. In the process of calibrating the on-line heat balance, the helium flow is adjusted to yield the optimum boiling level in the steam generator relative to the dissimilar metal weld. After calibration is complete the weld temperature measurement is non longer required. The reduced boiling level range results in less restrictive steam generator design constraints

  1. Progress of steam generator ageing management of Chinese NPPs

    International Nuclear Information System (INIS)

    Hongyun, L.; Chun, G.; Jun, T.; Zhigang, W.

    2012-01-01

    In China, the first two NPPs have operated over 15 years (QNPC) and 13 years (Dayabay). Now, most of Chinese NPPs have started their ageing management project. Steam generator (SG) is one of key safety important components for PWR and CANDU, which is selected as the first group of components to develop component ageing management system. QNPC and TQNPC have made some progress in this area. The basic SG ageing management system has been set up, and some application has been under way. To set up SG basic ageing management system, we start with (1) SG ageing mechanism analysis (2) Developing SG ageing management programme (3) Developing SG ageing management information system, SGAMDB (4) Ageing degradation assessment and remained life evaluation SG ageing mechanisms are classified as function degradation and material/structure degradation. The specific tables with unified format are used to analyze the ageing mechanism. The numbering requirements for ageing mechanism are developed to manage them in ageing information system. All ageing mechanisms are graded I and II and III based on its feasibility, impact on safety and operation experience, so that the key mechanisms are managed more strictly. SG ageing management programme (SGAMP), which is fundamental document for ageing management, provides the requirements for working process, what to do and when to do. SGAMP reviewing and improving requirements are as well included. SG ageing management database (SGAMDB) is the first component ageing management database for Chinese NPP, which have been installed and are in operation in QNPC and TQNPC. SG ageing degradation assessment and remained life evaluation are based on ageing mechanism, which includes integrity of tube bundle, integrity and remained fatigue life of key assemblies, and heat transfer capability degradation. Most NPPs at Chinese mainland have started their plant ageing and life management projects. Steam generator (SG), which is one of safety important

  2. PWR steam generator chemical cleaning. Phase I: solvent and process development. Volume II

    International Nuclear Information System (INIS)

    Larrick, A.P.; Paasch, R.A.; Hall, T.M.; Schneidmiller, D.

    1979-01-01

    A program to demonstrate chemical cleaning methods for removing magnetite corrosion products from the annuli between steam generator tubes and the tube support plates in vertical U-tube steam generators is described. These corrosion products have caused steam generator tube ''denting'' and in some cases have caused tube failures and support plate cracking in several PWR generating plants. Laboratory studies were performed to develop a chemical cleaning solvent and application process for demonstration cleaning of the Indian Point Unit 2 steam generators. The chemical cleaning solvent and application process were successfully pilot-tested by cleaning the secondary side of one of the Indian Point Unit 1 steam generators. Although the Indian Point Unit 1 steam generators do not have a tube denting problem, the pilot test provided for testing of the solvent and process using much of the same equipment and facilities that would be used for the Indian Point Unit 2 demonstration cleaning. The chemical solvent selected for the pilot test was an inhibited 3% citric acid-3% ascorbic acid solution. The application process, injection into the steam generator through the boiler blowdown system and agitation by nitrogen sparging, was tested in a nuclear environment and with corrosion products formed during years of steam generator operation at power. The test demonstrated that the magnetite corrosion products in simulated tube-to-tube support plate annuli can be removed by chemical cleaning; that corrosion resulting from the cleaning is not excessive; and that steam generator cleaning can be accomplished with acceptable levels of radiation exposure to personnel

  3. Wear behavior of steam generator tubes in nuclear power plant operating condition

    International Nuclear Information System (INIS)

    Kim, In-Sup; Hong, Jin-Ki; Kim, Hyung-Nam; Jang, Ki-Sang

    2003-01-01

    Reciprocating sliding wear tests were performed on steam generator tubes materials at steam generator operating temperature. The material surfaces react with oxygen to form oxides. The oxide properties such as formation rate and mechanical properties are varied with the test temperature and alloy composition. So, it is important to investigate the wear properties of each steam generator tube materials in steam generator operating condition. The tests results indicated that the wear coefficient in work rate model of alloy 690 was faster than that of alloy 800. From the scanning electron microscopy observation, the wear scars were similar each other and worn surfaces were covered with oxide layers. It seemed that the oxide layers were formed by wear debris sintering or cold welding and these layer properties affected the wear rate of steam generator tube materials. (author)

  4. Numerical modeling of secondary side thermohydraulics of horizontal steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Melikhov, V.I.; Melikhov, O.I.; Nigmatulin, B.I. [Research and Engineering Centre of LWR Nuclear Plants Safety, Moscow (Russian Federation)

    1995-12-31

    A mathematical model for the transient three-dimensional secondary side thermal hydraulics of the horizontal steam generator has been developed. The calculations of the steam generator PGV-1000 and PGV-4 nominal regimes and comparison of numerical and experimental results have been carried out. 7 refs.

  5. Numerical modeling of secondary side thermohydraulics of horizontal steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Melikhov, V I; Melikhov, O I; Nigmatulin, B I [Research and Engineering Centre of LWR Nuclear Plants Safety, Moscow (Russian Federation)

    1996-12-31

    A mathematical model for the transient three-dimensional secondary side thermal hydraulics of the horizontal steam generator has been developed. The calculations of the steam generator PGV-1000 and PGV-4 nominal regimes and comparison of numerical and experimental results have been carried out. 7 refs.

  6. Steam Generator Group Project. Task 6. Channel head decontamination

    International Nuclear Information System (INIS)

    Allen, R.P.; Clark, R.L.; Reece, W.D.

    1984-08-01

    The Steam Generator Group Project utilizes a retired-from-service pressurized-water-reactor steam generator as a test bed and source of specimens for research. An important preparatory step to primary side research activities was reduction of the radiation field in the steam generator channel head. This task report describes the channel head decontamination activities. Though not a programmatic research objective it was judged beneficial to explore the use of dilute reagent chemical decontamination techniques. These techniques presented potential for reduced personnel exposure and reduced secondary radwaste generation, over currently used abrasive blasting techniques. Two techniques with extensive laboratory research and vendors prepared to offer commercial application were tested, one on either side of the channel head. As indicated in the report, both techniques accomplished similar decontamination objectives. Neither technique damaged the generator channel head or tubing materials, as applied. This report provides details of the decontamination operations. Application system and operating conditions are described

  7. SARAPAN—A Simulated-Annealing-Based Tool to Generate Random Patterned-Channel-Age in CANDU Fuel Management Analyses

    Directory of Open Access Journals (Sweden)

    Doddy Kastanya

    2017-02-01

    Full Text Available In any reactor physics analysis, the instantaneous power distribution in the core can be calculated when the actual bundle-wise burnup distribution is known. Considering the fact that CANDU (Canada Deuterium Uranium utilizes on-power refueling to compensate for the reduction of reactivity due to fuel burnup, in the CANDU fuel management analysis, snapshots of power and burnup distributions can be obtained by simulating and tracking the reactor operation over an extended period using various tools such as the *SIMULATE module of the Reactor Fueling Simulation Program (RFSP code. However, for some studies, such as an evaluation of a conceptual design of a next-generation CANDU reactor, the preferred approach to obtain a snapshot of the power distribution in the core is based on the patterned-channel-age model implemented in the *INSTANTAN module of the RFSP code. The objective of this approach is to obtain a representative snapshot of core conditions quickly. At present, such patterns could be generated by using a program called RANDIS, which is implemented within the *INSTANTAN module. In this work, we present an alternative approach to derive the patterned-channel-age model where a simulated-annealing-based algorithm is used to find such patterns, which produce reasonable power distributions.

  8. SARAPAN-A simulated-annealing-based tool to generate random patterned-channel-age in CANDU fuel management analyses

    Energy Technology Data Exchange (ETDEWEB)

    Kastanya, Doddy [Safety and Licensing Department, Candesco Division of Kinectrics Inc., Toronto (Canada)

    2017-02-15

    In any reactor physics analysis, the instantaneous power distribution in the core can be calculated when the actual bundle-wise burnup distribution is known. Considering the fact that CANDU (Canada Deuterium Uranium) utilizes on-power refueling to compensate for the reduction of reactivity due to fuel burnup, in the CANDU fuel management analysis, snapshots of power and burnup distributions can be obtained by simulating and tracking the reactor operation over an extended period using various tools such as the *SIMULATE module of the Reactor Fueling Simulation Program (RFSP) code. However, for some studies, such as an evaluation of a conceptual design of a next-generation CANDU reactor, the preferred approach to obtain a snapshot of the power distribution in the core is based on the patterned-channel-age model implemented in the *INSTANTAN module of the RFSP code. The objective of this approach is to obtain a representative snapshot of core conditions quickly. At present, such patterns could be generated by using a program called RANDIS, which is implemented within the *INSTANTAN module. In this work, we present an alternative approach to derive the patterned-channel-age model where a simulated-annealing-based algorithm is used to find such patterns, which produce reasonable power distributions.

  9. Thermal-Hydraulic Analysis of a Once-Through Steam Generator Considering Performance Degradation

    International Nuclear Information System (INIS)

    Han, Hun Sik; Kang, Han Ok; Yoon, Ju Hyeon; Kim, Young In; Song, Jae Seung; Kim, Keung Koo

    2016-01-01

    Several countries have entered into a global race for the commercialization of SMRs, and considerable research and development have been implemented. Among the various reactor designs, many SMRs have adopted an integral type pressurized water reactor (PWR) to enhance the nuclear safety and system reliability. In the integral reactor design, a single reactor pressure vessel contains primary system components such as fuel and core, steam generators, pumps, and a pressurizer. For the component integration into a reactor vessel, it is important to design each component as small as possible. Thus, it is a common practice to employ a once-through steam generator in the integral reactor design due to its advantages in compactness. In general, gradual degradation in thermal-hydraulic performance of the steam generator occurs with time, and it changes slowly the operating point of the steam generator during plant lifetime. Numerical solutions are acquired to evaluate the thermal-hydraulic performance of the steam generator at various AUFs. The design results obtained show that the average tube length of the steam generator is augmented with the increase of design margin to compensate for the design uncertainties and heat transfer area reduction by plugging, fouling, etc. A helically coiled tube once-through steam generator with 30% design margin is considered for comparison of thermal-hydraulic performances according to the degradation rate

  10. Thermal-Hydraulic Analysis of a Once-Through Steam Generator Considering Performance Degradation

    Energy Technology Data Exchange (ETDEWEB)

    Han, Hun Sik; Kang, Han Ok; Yoon, Ju Hyeon; Kim, Young In; Song, Jae Seung; Kim, Keung Koo [KAERI, Daejeon (Korea, Republic of)

    2016-05-15

    Several countries have entered into a global race for the commercialization of SMRs, and considerable research and development have been implemented. Among the various reactor designs, many SMRs have adopted an integral type pressurized water reactor (PWR) to enhance the nuclear safety and system reliability. In the integral reactor design, a single reactor pressure vessel contains primary system components such as fuel and core, steam generators, pumps, and a pressurizer. For the component integration into a reactor vessel, it is important to design each component as small as possible. Thus, it is a common practice to employ a once-through steam generator in the integral reactor design due to its advantages in compactness. In general, gradual degradation in thermal-hydraulic performance of the steam generator occurs with time, and it changes slowly the operating point of the steam generator during plant lifetime. Numerical solutions are acquired to evaluate the thermal-hydraulic performance of the steam generator at various AUFs. The design results obtained show that the average tube length of the steam generator is augmented with the increase of design margin to compensate for the design uncertainties and heat transfer area reduction by plugging, fouling, etc. A helically coiled tube once-through steam generator with 30% design margin is considered for comparison of thermal-hydraulic performances according to the degradation rate.

  11. Steam generators for nuclear power plants

    International Nuclear Information System (INIS)

    Tillequin, Jean

    1975-01-01

    The role and the general characteristics of steam generators in nuclear power plants are indicated, and particular types are described according to the coolant nature (carbon dioxide, helium, light water, heavy water, sodium) [fr

  12. 76 FR 74834 - Interim Staff Guidance on Aging Management Program for Steam Generators

    Science.gov (United States)

    2011-12-01

    ... for Steam Generators AGENCY: Nuclear Regulatory Commission. ACTION: Interim staff guidance; issuance... (LR-ISG), LR-ISG-2011-02, ``Aging Management Program for Steam Generators.'' This LR-ISG provides the...) document, NEI 97-06, ``Steam Generator Program Guidelines,'' (NRC's Agencywide Documents Access and...

  13. Feasibility and application on steam injector for next-generation reactor

    International Nuclear Information System (INIS)

    Narabayashi, Tadashi; Ishiyama, Takenori; Miyano, Hiroshi; Nei, Hiromichi; Shioiri, Akio

    1991-01-01

    A feasibility study has been conducted on steam injector for a next generation reactor. The steam injector is a simple, compact passive device for water injection, such as Passive Core Injection System (PCIS) of Passive Containment Cooling System (PCCS), because of easy start-up without an AC power. An analysis model for a steam injector characteristics has been developed, and investigated with a visualized fundamental test for a two-stage Steam Injector System (SIS) for PCIS and a one-stage low pressure SIS for PCCS. The test results showed good agreement with the analysis results. The analysis and the test results showed the SIS could work over a very wide range of the steam pressure, and is applicable for PCIS or PCCS in the next generation reactors. (author)

  14. Steam-generator replacement sets new marks

    International Nuclear Information System (INIS)

    Beck, R.L.

    1995-01-01

    This article describes how, in one of the most successful steam-generator replacement experiences at PWRs worldwide, the V C Summer retrofit exceeded plant goals for critical-path duration, radiation, exposure, and radwaste generation. Intensive planning and teamwork, combined with the firm support of station management and the use of mockups to prepare the work crews for activity in a radiological environment, were key factors in the record performance achieved by South Carolina Electric and Gas Co (SCE and G) in replacing three steam generators at V C Summer nuclear station. The 97-day, two-hour breaker-to-breaker replacement outage -- including an eight-day delay for repair of leak in a small-bore seal-injection line of a reactor coolant pump (unrelated to the replacement activities) -- surpassed the project goal by over one day. Moreover, the outage was only 13 hours shy of the world record held by Virginia Power Co's North Anna Unit 1

  15. Steam generation at Rihand STPP Stage 1

    Energy Technology Data Exchange (ETDEWEB)

    1987-12-01

    The steam generation plant at Rihand in India has two 500 MW boilers. The boilers are of the balanced draught, single cell, radiant furnace type, and are controlled automatically. Cochran Thermax shell type auxillary steam boilers are used for preheating air to the main boilers and for heating fuel oil during storage and pumping. Electrostatic precipitators and ash handling plants are provided to keep dust and ash within limits. 2 figs.

  16. Acoustic noises of the BOR-60 reactor steam generators when simulating leaks with argon and steam

    International Nuclear Information System (INIS)

    Sokolov, V.M.; Golushko, V.V.; Afanas'ev, V.A.; Grebenkin, Yu.P.; Muralev, A.B.

    1985-01-01

    Background acoustic noises of stea generators in different operational regimes and noises of argon and steam small leads (about 0.1 g/s) are studied to determine the possibility of designing the acoustic system for leak detection in sodium-water steamgenerators. Investigations are carried out at the 30 MW micromodule steam generator being in operation at the BOR-60 reactor as well as at the 20 MW tank type steam generator. Immersed ransduceres made of lithium niobate 6 mm in-diameter and waveguide transducers made of a stainless steel in the form of rods 10 mm in-diameter and 500 mm long are used as acoustic monitors. It is shown that the leak noise is more wide-band than the background noise of the steam generator and both high and low frequencies appear in the spectrum. The use of monitors of different types results in similar conslusions inrelation to the character of background noises and leak signals (spectral density, signal to-noise ratio) in the ase of similar bandroidths of the transduceres. A conclusion is made that the change of operational regimes leads to changes of background noise level, which can be close to the reaction of

  17. Integrity Analysis of Damaged Steam Generator Tubes

    International Nuclear Information System (INIS)

    Stanic, D.

    1998-01-01

    Variety of degradation mechanisms affecting steam generator tubes makes steam generators as one of the critical components in the nuclear power plants. Depending of their nature, degradation mechanisms cause different types of damages. It requires performance of extensive integrity analysis in order to access various conditions of crack behavior under operating and accidental conditions. Development and application of advanced eddy current techniques for steam generator examination provide good characterization of found damages. Damage characteristics (shape, orientation and dimensions) may be defined and used for further evaluation of damage influence on tube integrity. In comparison with experimental and analytical methods, numerical methods are also efficient tools for integrity assessment. Application of finite element methods provides relatively simple modeling of different type of damages and simulation of various operating conditions. The stress and strain analysis may be performed for elastic and elasto-plastic state with good ability for visual presentation of results. Furthermore, the fracture mechanics parameters may be calculated. Results obtained by numerical analysis supplemented with experimental results are the base for definition of alternative plugging criteria which may significantly reduce the number of plugged tubes. (author)

  18. Electric power generating plant having direct-coupled steam and compressed-air cycles

    Science.gov (United States)

    Drost, M.K.

    1981-01-07

    An electric power generating plant is provided with a Compressed Air Energy Storage (CAES) system which is directly coupled to the steam cycle of the generating plant. The CAES system is charged by the steam boiler during off peak hours, and drives a separate generator during peak load hours. The steam boiler load is thereby levelized throughout an operating day.

  19. Electric power generating plant having direct coupled steam and compressed air cycles

    Science.gov (United States)

    Drost, Monte K.

    1982-01-01

    An electric power generating plant is provided with a Compressed Air Energy Storage (CAES) system which is directly coupled to the steam cycle of the generating plant. The CAES system is charged by the steam boiler during off peak hours, and drives a separate generator during peak load hours. The steam boiler load is thereby levelized throughout an operating day.

  20. Development of steam generators for combustion of biofuels up to 10 t/h

    Energy Technology Data Exchange (ETDEWEB)

    Bentzin, H

    1985-01-01

    Combustion parameters are compared for raw brown coal, rice hulls and coconut shells as fuel in small steam generators. Combustion of native biofuel is seen as a power generation alternative in developing countries. Experiments were conducted on a 6.5 t/h moving grate steam generator with a firing grate surface of 7.2 m/sup 2/. Combustion results are shown in a table. Technological modifications carried out in adapting brown coal-fired steam generators to biofuels are also listed. A series of small steam generators for combustion of brown coal, biofuels including wood chips, as well as heating oil as back-up has been developed by the Karl-Marx-Stadt Dampfkesselbau Plant, GDR, with steam capacities ranging from 3.2 to 10 t/h. Technical specifications and diagrams of this series design (DGK-3, DGK-45, DWK 2S) are given. A larger steam generator with 20 t/h steam capacity for combustion of raw brown coal, bagasse, wood chips with heating oil and for rice hulls as support fuels is being developed by the Berlin Dampferzeugerbau Plant, GDR. 5 references.

  1. Optimum thermal sizing and operating conditions for once through steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Yi, Kunwoo; Ju, Kyongin; Im, Inyoung; Kim, Eunkee [KEPCO Engineering and Construction Company., Inc., Daejeon (Korea, Republic of)

    2014-10-15

    The steam generator is designed to be optimized so as to remove heat and to produce steam vapor. Because of its importance, theoretical and experimental researches have been performed on forced convection boiling heat transfer. The purpose of this study is to predict the thermal behavior and to perform optimum thermal sizing of once through steam generator. To estimate the tube thermal sizing and operating conditions of the steam generator, the analytical modeling is employed on the basis of the empirical correlation equations and theory. The optimized algorithm model, Non-dominated Sorting Genetic Algorithm (NSGA)-II, uses for this analysis. This research is focused on the design of in-vessel steam generator. An one dimensional analysis code is developed to evaluate previous researches and to optimize steam generator design parameters. The results of one-dimensional analysis need to be verified with experimental data. Goals of multi-objective optimization are to minimize tube length, pressure drop and tube number. Feedwater flow rate up to 115.425kg/s is selected so as to have margin of feedwater temperature 20 ..deg. C. For the design of 200MWth once through steam generator, it is evaluated that the tube length shall be over 12.0m for the number of tubes, 2500ea, and the length of the tube shall be over 8.0m for the number of tubes, 4500ea. The parallel coordinates chart can be provided to determine the optimal combination of number of tube, pressure drop, tube diameter and length.

  2. SGTR Project: Separate Effect Studies for Vertical Steam Generators

    Energy Technology Data Exchange (ETDEWEB)

    Peyres, V.; Polo, J.; Herranz, L. E.

    2003-07-01

    The SGTR project has been carried out within the fifth EURATOM Framework Programme (Contract No FIKS-CT-1999-0007). Its main objective was to provide an experimental database and to develop and/or verify models to support definition of accident management measures in the hypothetical case of a Steam Generator tube Rupture (SGTR) sequence. The project addressed both vertical and horizontal steam generator designs. This report summarises the main results obtained in the intermediate scale experimentation that addressed Western type steam generators. The specific goal of this test programme was to investigate aerosol retention in the break stage of the secondary side of a water-empty steam generator. The test matrix consisted of 12 tests that explored the influence of variables such as break type and orientation and inlet gas flow rate. This work was performed in the PECA facility of the Laboratory for Analysis of Safety Systems (LASS). Aerosol retention at the break stage of a dry steam generator was observed to be low and non-uniform. Neither break type nor orientation affected results significantly whenever gas flowrates exceeded about 100 kg/h. However, deposition patterns guillotine breaks and fish mouth ones showed remarkable differences. For flowrates above 100 kg/hm the higher the gas flow velocity, the lower the total mass depleted on tube bundle surfaces; however, at lower flowrates this trend was not maintained. An attempt to measure gas injection velocity at the break exit by Particle Image Velocity (PIV) was done but data were highly uncertain. (Author) 2 refs.

  3. Steam generator tube integrity program: Phase II, Final report

    Energy Technology Data Exchange (ETDEWEB)

    Kurtz, R.J.; Bickford, R.L.; Clark, R.A.; Morris, C.J.; Simonen, F.A.; Wheeler, K.R.

    1988-08-01

    The Steam Generator Tube Integrity Program (SGTIP) was a three phase program conducted for the US Nuclear Regulatory Commission (NRC) by Pacific Northwest Laboratory (PNL). The first phase involved burst and collapse testing of typical steam generator tubing with machined defects. The second phase of the SGTIP continued the integrity testing work of Phase I, but tube specimens were degraded by chemical means rather than machining methods. The third phase of the program used a removed-from-service steam generator as a test bed for investigating the reliability and effectiveness of in-service nondestructive eddy-current inspection methods and as a source of service degraded tubes for validating the Phase I and Phase II data on tube integrity. This report describes the results of Phase II of the SGTIP. The object of this effort included burst and collapse testing of chemically defected pressurized water reactor (PWR) steam generator tubing to validate empirical equations of remaining tube integrity developed during Phase I. Three types of defect geometries were investigated: stress corrosion cracking (SCC), uniform thinning and elliptical wastage. In addition, a review of the publicly available leak rate data for steam generator tubes with axial and circumferential SCC and a comparison with an analytical leak rate model is presented. Lastly, nondestructive eddy-current (EC) measurements to determine accuracy of defect depth sizing using conventional and alternate standards is described. To supplement the laboratory EC data and obtain an estimate of EC capability to detect and size SCC, a mini-round robin test utilizing several firms that routinely perform in-service inspections was conducted.

  4. Steam generator tube integrity program: Phase II, Final report

    International Nuclear Information System (INIS)

    Kurtz, R.J.; Bickford, R.L.; Clark, R.A.; Morris, C.J.; Simonen, F.A.; Wheeler, K.R.

    1988-08-01

    The Steam Generator Tube Integrity Program (SGTIP) was a three phase program conducted for the US Nuclear Regulatory Commission (NRC) by Pacific Northwest Laboratory (PNL). The first phase involved burst and collapse testing of typical steam generator tubing with machined defects. The second phase of the SGTIP continued the integrity testing work of Phase I, but tube specimens were degraded by chemical means rather than machining methods. The third phase of the program used a removed-from-service steam generator as a test bed for investigating the reliability and effectiveness of in-service nondestructive eddy-current inspection methods and as a source of service degraded tubes for validating the Phase I and Phase II data on tube integrity. This report describes the results of Phase II of the SGTIP. The object of this effort included burst and collapse testing of chemically defected pressurized water reactor (PWR) steam generator tubing to validate empirical equations of remaining tube integrity developed during Phase I. Three types of defect geometries were investigated: stress corrosion cracking (SCC), uniform thinning and elliptical wastage. In addition, a review of the publicly available leak rate data for steam generator tubes with axial and circumferential SCC and a comparison with an analytical leak rate model is presented. Lastly, nondestructive eddy-current (EC) measurements to determine accuracy of defect depth sizing using conventional and alternate standards is described. To supplement the laboratory EC data and obtain an estimate of EC capability to detect and size SCC, a mini-round robin test utilizing several firms that routinely perform in-service inspections was conducted

  5. Development of data management system for steam generator inspection

    International Nuclear Information System (INIS)

    Jung, Yong Moo; Im, Chang Jae; Lee, Yoon Sang; Kang, Soon Joo; An, Jong Kwan

    1994-06-01

    The data communications environment for transferring Nuclear Power Plant Steam Generator Eddy Current testing data was investigated and after connecting LAN to Hinet-F network, the remote data transfer with the speed of 56 kbps was tested successfully. Data management system for Steam Generator Eddy current testing was also developed by using HP-UX, RMB (Rock Mountain Basic) 21 figs, 13 tabs, 5 refs. (Author)

  6. Development of data management system for steam generator inspection

    Energy Technology Data Exchange (ETDEWEB)

    Jung, Yong Moo; Im, Chang Jae; Lee, Yoon Sang; Kang, Soon Joo; An, Jong Kwan [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    1994-06-01

    The data communications environment for transferring Nuclear Power Plant Steam Generator Eddy Current testing data was investigated and after connecting LAN to Hinet-F network, the remote data transfer with the speed of 56 kbps was tested successfully. Data management system for Steam Generator Eddy current testing was also developed by using HP-UX, RMB (Rock Mountain Basic) 21 figs, 13 tabs, 5 refs. (Author).

  7. Future steam generator designs. Single wall designs

    International Nuclear Information System (INIS)

    Hayden, O.

    1978-01-01

    The easily removable 'U' tube design style adopted in the UK for the existing PFR Steam Generators, the Replacement Units now in production and for the future CDFR, gives the operator an extremely valuable option in the event of a water/steam leak occurring inside the Steam Generator. He can choose to shut-down, attempt to find the leak, assess damage, repair, revalidate and return to service in situ, or he can elect to remove the defect unit and replace with a 'proven' spare before returning the circuit to power. With the latter approach the resultant outage time is a known entity of about two weeks. If a repair is attempted in situ, predictions of outage time can become a matter of guesswork since one has no 'guaranteed' method of leak location and the assessment of secondary damage may be very time consuming, depending on the size and type of the original leak together with the particular design style of the Steam Generator. A further significant advantage of the removable 'U' tube design concept is that periodic interchanging of bundles with a spare enables routine chemical cleaning and thorough scheduled tube inspections, with specimen tube sample removal if required for monitoring purposes. If necessary, bundle decontamination can be undertaken to assess engineering deterioration to various degrees of thoroughness ranging from 100% equivalent factory final assembly inspection, to partial decontamination operating via a glovebox type of maintenance bag arrangement, examining local points of both shell and tube areas of the bundle. Many lessons from the last five years' experience of PFR will be incorporated into the design of the CDFR and PFR Steam Generators have two very good examples of how the designer can ease or severely handicap the operator in coping with sodium/water leakages. Good, quick access to tube ends is achieved in the existing PFR Evaporator by simply unbolting the steam/water closure head, but on the superheater and reheater hand-caps have

  8. Future steam generator designs. Single wall designs

    Energy Technology Data Exchange (ETDEWEB)

    Hayden, O [Nuclear Power Company Ltd, Warrington, Cheshire (United Kingdom)

    1978-10-01

    The easily removable 'U' tube design style adopted in the UK for the existing PFR Steam Generators, the Replacement Units now in production and for the future CDFR, gives the operator an extremely valuable option in the event of a water/steam leak occurring inside the Steam Generator. He can choose to shut-down, attempt to find the leak, assess damage, repair, revalidate and return to service in situ, or he can elect to remove the defect unit and replace with a 'proven' spare before returning the circuit to power. With the latter approach the resultant outage time is a known entity of about two weeks. If a repair is attempted in situ, predictions of outage time can become a matter of guesswork since one has no 'guaranteed' method of leak location and the assessment of secondary damage may be very time consuming, depending on the size and type of the original leak together with the particular design style of the Steam Generator. A further significant advantage of the removable 'U' tube design concept is that periodic interchanging of bundles with a spare enables routine chemical cleaning and thorough scheduled tube inspections, with specimen tube sample removal if required for monitoring purposes. If necessary, bundle decontamination can be undertaken to assess engineering deterioration to various degrees of thoroughness ranging from 100% equivalent factory final assembly inspection, to partial decontamination operating via a glovebox type of maintenance bag arrangement, examining local points of both shell and tube areas of the bundle. Many lessons from the last five years' experience of PFR will be incorporated into the design of the CDFR and PFR Steam Generators have two very good examples of how the designer can ease or severely handicap the operator in coping with sodium/water leakages. Good, quick access to tube ends is achieved in the existing PFR Evaporator by simply unbolting the steam/water closure head, but on the superheater and reheater hand-caps have

  9. Composite electric generator equipped with steam generator for heating reactor coolant

    International Nuclear Information System (INIS)

    Watabe, Masaharu; Soman, Yoshindo; Kawanishi, Kohei; Ota, Masato.

    1997-01-01

    The present invention concerns a composite electric generator having coolants, as a heating source, of a PWR type reactor or a thermonuclear reactor. An electric generator driving gas turbine is disposed, and a superheater using a high temperature exhaust gas of the gas turbine as a heating source is disposed, and main steams are superheated by the superheater to elevate the temperature at the inlet of the turbine. This can increase the electric generation capacity as well as increase the electric generation efficiency. In addition, since the humidity in the vicinity of the exit of the steam turbine is reduced, occurrence of loss and erosion can be suppressed. When cooling water of the thermonuclear reactor is used, the electric power generated by the electric generator driven by the gas turbine can be used upon start of the thermonuclear reactor, and it is not necessary to dispose a large scaled special power source in the vicinity, which is efficient. (N.H.)

  10. PACTEL: Experiments on the behaviour of the new horizontal steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Kouhia, J.; Riikonen, V.; Purhonen, H. [VTT Energy, Lappeenranta (Finland)

    1995-12-31

    Experiments were performed to study the behaviour of the PACTEL facility, a medium scale integral test loop simulating VVER 440 pressurized water reactors. The study focused on the operation of the new horizontal steam generator model installed in PACTEL. Three experiments were conducted: a small-break test to observe the steam generator behaviour over a range of primary coolant inventories, a hot leg loop seal experiment to study the cyclic behaviour of a loop seal and a loss of secondary side feedwater test to examine the effect of uncovered tubes in the steam generator. A reverse flow was observed in the lower part of the U-tube bundle of the steam generator during natural circulation. The flow reversal point dropped when the tubes uncovered, during secondary inventory reduction. (orig.). 5 refs.

  11. Analysis of induced steam generator tube rupture using MAAP 4.0

    International Nuclear Information System (INIS)

    Kenton, M.; Epstein, M.; Henry, R.E.; Paik, C.; Fuller, E.

    1996-01-01

    The nuclear industry has initiated a program of Steam Generator Degradation Specific Management (SGDSM) to cope with the various types of corrosion that have been observed in pressurized water reactor (PWR) steam generators. In parallel, the U.S. Nuclear Regulatory Commission is promulgating revised rules on steam generator tube integrity. To support these efforts, the Electric Power Research Institute has sponsored calculations with the MAAP 4 code. The principal objective of these calculations is to estimate the peak temperatures experienced by the steam generator tubes during high-pressure severe accidents. These results are used to evaluate the potential for degraded tubes to leak or rupture. Attention was focused on station blackout (SBO) accidents with loss of turbine-driven auxiliary feedwater because these generally result in the greatest threat to the tubes

  12. PACTEL: Experiments on the behaviour of the new horizontal steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Kouhia, J; Riikonen, V; Purhonen, H [VTT Energy, Lappeenranta (Finland)

    1996-12-31

    Experiments were performed to study the behaviour of the PACTEL facility, a medium scale integral test loop simulating VVER 440 pressurized water reactors. The study focused on the operation of the new horizontal steam generator model installed in PACTEL. Three experiments were conducted: a small-break test to observe the steam generator behaviour over a range of primary coolant inventories, a hot leg loop seal experiment to study the cyclic behaviour of a loop seal and a loss of secondary side feedwater test to examine the effect of uncovered tubes in the steam generator. A reverse flow was observed in the lower part of the U-tube bundle of the steam generator during natural circulation. The flow reversal point dropped when the tubes uncovered, during secondary inventory reduction. (orig.). 5 refs.

  13. Reliability of eddy current examination of steam generator tubes

    International Nuclear Information System (INIS)

    Birks, A.S.; Ferris, R.H.; Doctor, P.G.; Clark, R.A.; Spanner, G.E.

    1985-04-01

    A unique study of nondestructive examination reliability is underway at the Pacific Northwest Laboratory under US Nuclear Regulatory Commission sponsorship. Project participants include the Electric Power Research Institute and consortiums from France, Italy, and Japan. This study group has conducted a series of NDE examinations of tubes from a retired-from-service steam generator, using commercially available multifrequency eddy current equipment and ASME procedures. The examination results have been analyzed to identify factors contributing to variations in NDE inspection findings. The reliability of these examinations will then be validated by destructive analyses of the steam generator tubes. The program is expected to contribute to development of a model for steam generator inservice inspection sampling plans and inspection periods, as well as to improved regulatory guidelines for tube plugging

  14. Estimating probable flaw distributions in PWR steam generator tubes

    International Nuclear Information System (INIS)

    Gorman, J.A.; Turner, A.P.L.

    1997-01-01

    This paper describes methods for estimating the number and size distributions of flaws of various types in PWR steam generator tubes. These estimates are needed when calculating the probable primary to secondary leakage through steam generator tubes under postulated accidents such as severe core accidents and steam line breaks. The paper describes methods for two types of predictions: (1) the numbers of tubes with detectable flaws of various types as a function of time, and (2) the distributions in size of these flaws. Results are provided for hypothetical severely affected, moderately affected and lightly affected units. Discussion is provided regarding uncertainties and assumptions in the data and analyses

  15. Probabilistic methodology for assessing steam generator tube inspection - Phase II: CANTIA - a probabilistic method for assessing steam generator tube inspections

    International Nuclear Information System (INIS)

    Harris, J.E.; Gorman, J.A.; Turner, A.P.L.

    1997-03-01

    The objectives of this project were to develop a computer-based method for probabilistic assessment of inspection strategies for steam generator tubes, and to document the source code and to provide a user's manual for it. The program CANTIA was created to fulfill this objective, and the documentation and verification of the code is provided in this volume. The user's manual for CANTIA is provided as a separate report. CANTIA uses Monte Carlo techniques to determine approximate probabilities of steam generator tube failures under accident conditions and primary-to-secondary leak rates under normal and accident conditions at future points in time. The program also determines approximate future flaw distributions and non-destructive examination results from the input data. The probabilities of failure and leak rates and the future flaw distributions can be influenced by performing inspections of the steam generator tubes at some future points in time, and removing defective tubes from the population. The effect of different inspection and maintenance strategies can therefore be determined as a direct effect on the probability of tube failure and primary-to-secondary leak rate

  16. The residual stress evaluation for expansion process of steam generator tubes

    International Nuclear Information System (INIS)

    King, C.-S.; Lee, S.-C.; Shim, D.-N.

    2004-01-01

    The reliability of a nuclear power plant is affected by the reliability of steam generator tube and the reliability of steam generator tube is affected by stress corrosion cracking(SCC). Many steam generator tubes were experiencing stress corrosion cracking and stress corrosion cracking is affected material characteristics, corrosive environments and added stresses. The added stresses have the manufacturing stresses and operating stresses, the manufacturing stresses include the residual stresses generating in the tube manufacture and tube expanding procedure. We will investigate for influence which affected to residual stresses with tube plastic deformation method and measurement region. (author)

  17. Results of the secondary side chemical cleaning of the steam generators

    International Nuclear Information System (INIS)

    Doma, A.; Patek, G.

    2001-01-01

    A significant amount of deposit has developed on the secondary side of the heat transfer tubes of the steam generators (SG) of the Paks Nuclear Power Plant units in course of the years. More than 99.5% of the deposit is made up of magnetite (Fe 3 O 4 ) generated in the secondary circuit of the power plant. Those deposits lead to the decrease of the heat transfer. Even more important is its role from the point of view of operational reliability of the steam generators, leak tightness between the primary and secondary sides. The first series of cleaning took place following 8-9 years of operation of the units. Following the first cleaning cycle the transport of the corrosion products into the steam generators did not change, and thus obviously new cleaning was required. Periodical cleaning of the steam generators shall be assured. (R.P.)

  18. Design and Activation of a LOX/GH Chemical Steam Generator

    Science.gov (United States)

    Saunders, G. P.; Mulkey, C. A.; Taylor, S. A.

    2009-01-01

    The purpose of this paper is to give a detailed description of the design and activation of the LOX/GH fueled chemical steam generator installed in Cell 2 of the E3 test facility at Stennis Space Center, MS (SSC). The steam generator uses a liquid oxygen oxidizer with gaseous hydrogen fuel. The combustion products are then quenched with water to create steam at pressures from 150 to 450 psig at temperatures from 350 to 750 deg F (from saturation to piping temperature limits).

  19. Planning of the steam generators for nuclear applications using optimization techniques

    International Nuclear Information System (INIS)

    Sakai, M.; Silvares, O.M.

    1978-01-01

    Procedure for the maximization of the net power of a nuclear power plant through the application of the optimal control theory of dynamic systems is presented. The problem is formulated in the steam generator which links the primary and the secondary cycle. The solution of the steam generator, optimization problem is obtained simultaneously with the heat balance in both primary and secondary cycle, through an iterative process. By this way the optimal parameters are obtained for the steam generator, the vapor and the cooling gas cycle [pt

  20. Effects of Chemistry Parameters of Primary Water affecting Leakage of Steam Generator Tube Cracks

    Energy Technology Data Exchange (ETDEWEB)

    Shin, D. M.; Cho, N. C.; Kang, Y. S.; Lee, K. H. [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    Degradation of steam generator (SG) tubes can affect pressure boundary tightness. As a defense-in-depth measure, primary to secondary leak monitoring program for steam generators is implemented, and operation is allowed under leakage limits in nuclear power plants. Chemistry parameters that affect steam generator tube leakage due to primary water stress corrosion cracking (PWSCC) are investigated in this study. Tube sleeves were installed to inhibit leakage and improve tube integrity as a part of maintenance methods. Steam generators occurred small leak during operation have been replaced with new steam generators according to plant maintenance strategies. The correlations between steam generator leakage and chemistry parameters are presented. Effects of primary water chemistry parameters on leakage from tube cracks were investigated for the steam generators experiencing small leak. Unit A experienced small leakage from steam generator tubes in the end of operation cycle. It was concluded that increased solubility of oxides due to high pHT could make leakage paths, and low boron concentration lead to less blockage in cracks. Increased dissolved hydrogen may retard crack propagations, but it did not reduce leak rate of the leaking steam generator. In order to inhibit and reduce leakage, pH{sub T} was controlled by servicing cation bed operation. The test results of decreasing pHT indicate low pHT can reduce leak rate of PWSCC cracks in the end of cycle.

  1. Prediction of localized flow velocities and turbulence in a PWR steam generator: Final report

    International Nuclear Information System (INIS)

    Stuhmiller, J.H.

    1988-05-01

    The Steam Generator Project Office (SGPO) of the Steam Generator Owners Group and Electric Power Research Institute has developed a methodology for prediction of steam generator tube buffeting and associated material wear. Turbulent buffeting of steam generator tubes causes low amplitude vibratory response which results in fretting wear at support locations. Concerns raised at the Zion Nuclear Power Plant regarding the useful life of their steam generators prompted this study, in which the SGPO methodology is applied to analysis of the Westinghouse Model 51 steam generator. The specific intent of this project was to calculate turbulent buffeting forces within the tube bank of an operating Model 51 steam generator as a first step in the overall SGPO tube vibration and wear prediction strategy. Attention is focused on flow in the vicinity of anti-vibration bars (U-bend region) and on the flow that leaves the downcomer to impact against peripheral tubes. Other projects utilized the buffeting forces calculated here to determine tube vibratory response, tube-support plate impact statistics, and material wear rates. Besides successfully calculating hydraulic buffeting loads within the tube bank, the present project has enhanced the SGPO methodology and has identified hitherto unnoticed flow phenomena that occur in the steam generator. Experiments have also been carried out to validate numerical computations of the steam generator flow field

  2. Effects of Chemistry Parameters of Primary Water affecting Leakage of Steam Generator Tube Cracks

    International Nuclear Information System (INIS)

    Shin, D. M.; Cho, N. C.; Kang, Y. S.; Lee, K. H.

    2016-01-01

    Degradation of steam generator (SG) tubes can affect pressure boundary tightness. As a defense-in-depth measure, primary to secondary leak monitoring program for steam generators is implemented, and operation is allowed under leakage limits in nuclear power plants. Chemistry parameters that affect steam generator tube leakage due to primary water stress corrosion cracking (PWSCC) are investigated in this study. Tube sleeves were installed to inhibit leakage and improve tube integrity as a part of maintenance methods. Steam generators occurred small leak during operation have been replaced with new steam generators according to plant maintenance strategies. The correlations between steam generator leakage and chemistry parameters are presented. Effects of primary water chemistry parameters on leakage from tube cracks were investigated for the steam generators experiencing small leak. Unit A experienced small leakage from steam generator tubes in the end of operation cycle. It was concluded that increased solubility of oxides due to high pHT could make leakage paths, and low boron concentration lead to less blockage in cracks. Increased dissolved hydrogen may retard crack propagations, but it did not reduce leak rate of the leaking steam generator. In order to inhibit and reduce leakage, pH_T was controlled by servicing cation bed operation. The test results of decreasing pHT indicate low pHT can reduce leak rate of PWSCC cracks in the end of cycle

  3. Plutonium dispositioning in CANDU

    International Nuclear Information System (INIS)

    Boczar, P.G.; Feinroth, H.; Luxat, J.C.

    1995-07-01

    Recently, the U.S. Department of Energy (DOE) sponsored Atomic Energy of Canada Limited (AECL) to evaluate salient technical, strategic, schedule, and cost-related parameters of using CANDU reactors for dispositioning of weapons-grade plutonium in the form of Mixed OXide (MOX) fuel. A study team, consisting of key staff from the CANDU reactor designers and researchers (AECL), operators (Ontario Hydro) and fuel suppliers, analyzed all significant factors involved in such application, with the objective of identifying an arrangement that would permit the burning of MOX in CANDU at the earliest date. One of Ontario Hydro's multi-unit stations, Bruce A nuclear generating station (4x769 MW(e)), was chosen as the reference for the study. The assessment showed that no significant modifications of reactor or process systems are necessary to operate with a full MOX core. Plant modifications would be limited to fuel handling and modifications necessary to accommodate enhanced security and safeguards requirements. No safety limitations were identified

  4. A model predictive controller for the water level of nuclear steam generators

    International Nuclear Information System (INIS)

    Na, Man Gyun

    2001-01-01

    In this work, the model predictive control method was applied to a linear model and a nonlinear model of steam generators. The parameters of a linear model for steam generators are very different according to the power levels. The model predictive controller was designed for the linear steam generator model at a fixed power level. The proposed controller designed at the fixed power level showed good performance for any other power levels by changing only the input-weighting factor. As the input-weighting factor usually increases, its relative stability does so. The stem generator has some nonlinear characteristics. Therefore, the proposed algorithm has been implemented for a nonlinear model of the nuclear steam generator to verify its real performance and also, showed good performance. (author)

  5. Acoustic detection for water/steam leak from a tube of LMFBR steam generator

    International Nuclear Information System (INIS)

    Sonoda, Masataka; Shindo, Yoshihisa

    1989-01-01

    Acoustic leak detector is useful for detecting more quickly intermediate leak than the existing hydrogen detector and is available for identification of leak location on the accident of water/steam leak from a tube of LMFBR steam generator. This paper presents the overview of HALD (High frequency Acoustics Leak Detection) system, which is more sensitive for leak detection and lower cost of equipment for identification of leak location than a low frequency type detector. (author)

  6. Steam as turbine blade coolant: Experimental data generation

    Energy Technology Data Exchange (ETDEWEB)

    Wilmsen, B.; Engeda, A.; Lloyd, J.R. [Michigan State Univ., East Lansing, MI (United States)

    1995-10-01

    Steam as a coolant is a possible option to cool blades in high temperature gas turbines. However, to quantify steam as a coolant, there exists practically no experimental data. This work deals with an attempt to generate such data and with the design of an experimental setup used for the purpose. Initially, in order to guide the direction of experiments, a preliminary theoretical and empirical prediction of the expected experimental data is performed and is presented here. This initial analysis also compares the coolant properties of steam and air.

  7. A fault detection and diagnosis in a PWR steam generator

    International Nuclear Information System (INIS)

    Park, Seung Yub

    1991-01-01

    The purpose of this study is to develop a fault detection and diagnosis scheme that can monitor process fault and instrument fault of a steam generator. The suggested scheme consists of a Kalman filter and two bias estimators. Method of detecting process and instrument fault in a steam generator uses the mean test on the residual sequence of Kalman filter, designed for the unfailed system, to make a fault decision. Once a fault is detected, two bias estimators are driven to estimate the fault and to discriminate process fault and instrument fault. In case of process fault, the fault diagnosis of outlet temperature, feed-water heater and main steam control valve is considered. In instrument fault, the fault diagnosis of steam generator's three instruments is considered. Computer simulation tests show that on-line prompt fault detection and diagnosis can be performed very successfully.(Author)

  8. Steam generator design for solar towers using solar salt as heat transfer fluid

    Science.gov (United States)

    González-Gómez, Pedro Ángel; Petrakopoulou, Fontina; Briongos, Javier Villa; Santana, Domingo

    2017-06-01

    Since the operation of a concentrating solar power plant depends on the intermittent character of solar energy, the steam generator is subject to daily start-ups, stops and load variations. Faster start-up and load changes increase the plant flexibility and the daily energy production. However, it involves high thermal stresses on thick-walled components. Continuous operational conditions may eventually lead to a material failure. For these reasons, it is important to evaluate the transient behavior of the proposed designs in order to assure the reliability. The aim of this work is to analyze different steam generator designs for solar power tower plants using molten salt as heat transfer fluid. A conceptual steam generator design is proposed and associated heat transfer areas and steam drum size are calculated. Then, dynamic models for the main parts of the steam generator are developed to represent its transient performance. A temperature change rate that ensures safe hot start-up conditions is studied for the molten salt. The thermal stress evolution on the steam drum is calculated as key component of the steam generator.

  9. PWR steam generator chemical cleaning. Phase I: Final report, Volume I

    International Nuclear Information System (INIS)

    1978-07-01

    Two chemical cleaning solvent systems and two application methods were developed to remove the sludge in nuclear steam generators and to remove the corrosion products in the annuli between the steam generator tubes and the support plates. Laboratory testing plus subsequent pilot testing has demonstrated that, in a reasonable length of time, both solvents are capable of dissolving significant amounts of sludge, and of dissolving tightly packed magnetite in tube/support plate crevices. Further, tests have demonstrated that surface losses of the materials of construction in steam generators can be controlled to acceptable limits for the duration of the required cleaning period. Areas requiring further study and test have been identified, and a preliminary procedure for chemical cleaning nuclear steam generators has been chosen subject to quantification based on additional tests prior to actual in-plant demonstration

  10. AGE RELATED DEGRADATION OF STEAM GENERATOR INTERNALS BASED ON INDUSTRY RESPONSES TO GENERIC LETTER 97-06

    International Nuclear Information System (INIS)

    SUBUDHI, M.; SULLIVAN, JR. E.J.

    2002-01-01

    THIS PAPER PRESENTS THE RESULTS OF AN AGING ASSESSMENT OF THE NUCLEAR POWER INDUSTRY RESPONSES TO NRC GENERIC LETTER 97-06 ON THE DEGRADATION OF STEAM GENERATOR INTERNALS EXPERIENCED AT ELECTRICITE DE FRANCE (EDF) PLANTS IN FRANCE AND AT A UNITED STATES PRESSURIZED WATER REACTOR (PWR). WESTINGHOUSE (W), COMBUSTION ENGINEERING (CE), AND BABCOCK AND WILCOX (BW) STEAM GENERATOR MODELS, CURRENTLY IN SERVICE AT U.S. NUCLEAR POWER PLANTS, POTENTIALLY COULD EXPERIENCE DEGRADATION SIMILAR TO THATFOUND AT EDF PLANTS AND THE U.S. PLANT. THE STEAM GENERATORS IN MANY OF THE U.S. PWRS HAVE BEEN REPLACED WITH STEAM GENERATORS WITH STEAM GENERATORS WITH IMPROVED DESIGNS AND MATERIALS. THESE REPLACEMENT STEAM GENERATORS HAVE BEEN MANUFACTURED IN THE U.S. AND ABROAD. DURING THIS ASSESSMENT, EACH OF THE THREE OWNERS GROUPS (W,CE, AND BW) IDENTIFIED FOR ITS STEAM GENERATOR, MODELS ALL THE POTENTIAL INTERNAL COMPONENTS THAT ARE VULNERABLE TO DEGRADATION WHILE IN SERVICE. EACH OWNERS GROUPDEVELOPED INSPEC TION AND MONITORING GUIDANCE AND RECOMMENDATIONS FOR ITS PARTICULAR STEAM GENERATOR MODELS. THE NUCLEAR ENERGY INSTITUTE INCORPORATED IN NEI 97-06 STEAM GENERATOR PROGRAM GUIDELINES, A REQUIREMENT TO MONITOR SECONDARY SIDE STEAM GENERATOR COMPONENTS IF THEIR FAILURE COULD PREVENT THE STEAM GENERATOR FROM FULFILLING ITS INTENDED SAFETY-RELATED FUNCTION. LICENSEES INDICATED THAT THEY IMPLEMENTED OR PLANNED TO IMPLEMENT, AS APPROPRIATE FOR THEIR STEAM GENERATORS, THEIR OWNERS GROUPRECOMMENDATIONS TO ADDRESS THE LONG-TERM EFFECTS OF THE POTENTIAL DEGRADATION MECHANISMS ASSOCIATED WITH THE STEAM GENERATOR INTERNALS

  11. Commercially Available Activated Carbon Fiber Felt Enables Efficient Solar Steam Generation.

    Science.gov (United States)

    Li, Haoran; He, Yurong; Hu, Yanwei; Wang, Xinzhi

    2018-03-21

    Sun-driven steam generation is now possible and has the potential to help meet future energy needs. Current technologies often use solar condensers to increase solar irradiance. More recently, a technology for solar steam generation that uses heated surface water and low optical concentration is reported. In this work, a commercially available activated carbon fiber felt is used to generate steam efficiently under one sun illumination. The evaporation rate and solar conversion efficiency reach 1.22 kg m -2 h -1 and 79.4%, respectively. The local temperature of the evaporator with a floating activated carbon fiber felt reaches 48 °C. Apart from the high absorptivity (about 94%) of the material, the evaporation performance is enhanced thanks to the well-developed pores for improved water supply and steam escape and the low thermal conductivity, which enables reduced bulk water temperature increase. This study helps to find a promising material for solar steam generation using a water evaporator that can be produced economically (∼6 $/m 2 ) with long-term stability.

  12. Estimation of Aging Effects on LOHS for CANDU-6

    Energy Technology Data Exchange (ETDEWEB)

    Yoon, Yong Ki; Moon, Bok Ja; Kim, Seoung Rae [Nuclear Engineering Service and Solution Co. Ltd., Daejeon (Korea, Republic of)

    2014-05-15

    To evaluate the Wolsong Unit 1's capacity to respond to large-scale natural disaster exceeding design, the loss of heat sink(LOHS) accident accompanied by loss of all electric power is simulated as a beyond design basis accident. This analysis is considered the aging effects of plant as the consequences of LOHS accident. Various components of primary heat transport system(PHTS) get aged and some of the important aging effects of CANDU reactor are pressure tube(PT) diametral creep, steam generator(SG) U-tube fouling, increased feeder roughness, and feeder orifice degradation. These effects result in higher inlet header temperatures, reduced flows in some fuel channels, and higher void fraction in fuel channel outlets. Fresh and aged models are established for the analysis where fresh model is the circuit model simulating the conditions at retubing and aged model corresponds to the model reflecting the aged condition at 11 EFPY after retubing. CATHENA computer code[1] is used for the analysis of the system behavior under LOHS condition. The LOHS accident is analyzed for fresh and aged models using CATHENA thermal hydraulic computer code. The decay heat removal is one of the most important factors for mitigation of this accident. The major aging effect on decay heat removal is the reduction of heat transfer efficiency by steam generator. Thus, the channel failure time cannot be conservatively estimated if aged model is applied for the analysis of this accident.

  13. Heat exchanging tube behaviour in steam generators of pressurized water reactors

    International Nuclear Information System (INIS)

    Pastor, D.; Oertel, K.

    1979-01-01

    Based on a comprehensive failure statistics, materials corrosion chemistry and thermohydraulics problems of the tubings of steam generators are considered. A historical review of failures in the tubings of steam generators in pressurized water reactors reflects the often successless measures by designers, manufacturers and operating organizations for preventing failures, especially with regard to materials selection and water regime. It is stated that laboratory tests could not give sufficient information about safe and stable operation of nuclear steam generators unless real constructive, hydrodynamic, thermodynamical and chemical conditions of operation had been taken into account. (author)

  14. Flow-induced vibration in LMFBR steam generators: a state-of-the-art review

    International Nuclear Information System (INIS)

    Shin, Y.S.; Wambsganss, M.W.

    1975-05-01

    This state-of-the-art review identifies and discusses existing methods of flow-induced vibration analysis applicable to steam generators, their limitations, and base-technology needs. Also included are discussions of five different LMFBR steam-generator configurations and important design considerations, failure experiences, possible flow-induced excitation mechanisms, vibration testing, and available methods of vibration analysis. The objectives are to aid LMFBR steam-generator designers in making the best possible evaluation of potential vibration in steam-generator internals, and to provide the basis for development of design guidelines to avoid detrimental flow-induced vibration

  15. Leak suppression at steam generator man-, hand-, and eyeholes

    International Nuclear Information System (INIS)

    Sylvain, C.; Sutz, P.; Gemma, A.

    1988-01-01

    Plant unavailability associated with primary and secondary holes is approximately the same as that caused by steam generator tube defects, i.e., 0.5%. Problems encountered with steam generator man-, hand-, and eyeholes during plant operation have led Electricite de France (EdF) and Framatome to improve hole seal design and to develop robots for closing and cleaning them. The data base available in France in this field on some 150 steam generators in 900- and 1300-MW(electric) pressurized water reactors (the equivalent of 300 reactor-yr of operation) has been the base of the developments described in this paper. Incidents occurring in operation primarily concern had-and inspection holes located on the steam generator's secondary side. They include four kinds: (1) leakage detected in operation, requiring forced outages, (2) leakage detected during plant restart after a scheduled shutdown and resulting in a restart delay, (3) pitting of seal mating surfaces, not inducing any leakage but jeopardizing subsequent compliance and requiring difficult and costly repairs, and (4) seizing of screws or bolts. New primary and secondary hole stud tightening and maintenance machines help to improve the efficiency of the in-service closing operations. They provide savings of up to 80% on labor, duration of operations, and exposure

  16. Design of jet manipulator for sludge lancing for steam generators

    International Nuclear Information System (INIS)

    Kumar, Kundan; Nathani, D.K.; Kayal, J.N.; Rupani, B.B.

    2006-01-01

    The sludge accumulation in secondary side of mushroom type steam generators of Indian Pressurised Heavy Water Reactors (PHWRs) may lead to loss of thermal efficiency and corrosion. Sludge removal is required to minimise such effects for safe and enhanced operating life of the steam generators. A sludge lancing system has been developed for sludge removal from the secondary side of the steam generators. Jet Manipulator is one of the various modules of the sludge lancing system. The JM consists of three modules namely walker, elevator and nozzle heads. Each module is designed to pass through hand hole, having 180 mm diameter and 100 mm wide gap between steam generator shell and shroud. These three modules are connected to each other by quick connecting type joints and are having their specific functions. The walker crawls by step of single pitch of the tube along the central no-tube lane of the steam generator by taking lateral supports on the nearest tubes. The elevator is capable of lifting the nozzle head to a suitable height required for lancing operation of entire tube sheet of the steam generator. The nozzle head directs the multiple jets along the narrow inter tube lanes having 3 mm width, on both sides of the central no-tube lane. The nozzle can be set to move at different elevations such that the multiple jets will graze along the narrow tube lane to create the sludge lancing action. The provision exists for movement of JM in both directions, i.e. forward and reverse. This paper highlights the objective, design and development, selection of nozzles, qualification and performance evaluation of JM. The manipulator is remotely operable by compressed air in the forward and reverse direction in the central no-tube lane to position the nozzle head in the horizontal direction. (author)

  17. Pressure drop-flow rate curves for single-phase steam in Combustion Engineering type steam generator U-tubes during severe accidents

    Energy Technology Data Exchange (ETDEWEB)

    Fynan, Douglas A.; Ahn, Kwang-Il, E-mail: kiahn@kaeri.re.kr

    2016-12-15

    Highlights: • Pressure drop-flow rate curves for superheated steam in U-tubes were generated. • Forward flow of hot steam is favored in the longer and taller U-tubes. • Reverse flow of cold steam is favored in short U-tubes. • Steam generator U-tube bundle geometry and tube diameter are important. • Need for correlation development for natural convention heat transfer coefficient. - Abstract: Characteristic pressure drop-flow rate curves are generated for all row numbers of the OPR1000 steam generators (SGs), representative of Combustion Engineering (CE) type SGs featuring square bend U-tubes. The pressure drop-flow rate curves are applicable to severe accident natural circulations of single-phase superheated steam during high pressure station blackout sequences with failed auxiliary feedwater and dry secondary side which are closely related to the thermally induced steam generator tube rupture event. The pressure drop-flow rate curves which determine the recirculation rate through the SG tubes are dependent on the tube bundle geometry and hydraulic diameter of the tubes. The larger CE type SGs have greater variation of tube length and height as a function of row number with forward flow of steam favored in the longer and taller high row number tubes and reverse flow favored in the short low row number tubes. Friction loss, natural convection heat transfer coefficients, and temperature differentials from the primary to secondary side are dominant parameters affecting the recirculation rate. The need for correlation development for natural convection heat transfer coefficients for external flow over tube bundles currently not modeled in system codes is discussed.

  18. Steam generator tube integrity requirements and operating experience in the United States

    International Nuclear Information System (INIS)

    Karwoski, K.J.

    2009-01-01

    Steam generator tube integrity is important to the safe operation of pressurized-water reactors. For ensuring tube integrity, the U.S. Nuclear Regulatory Commission uses a regulatory framework that is largely performance based. This performance-based framework is supplemented with some prescriptive requirements. The framework recognizes that there are three combinations of tube materials and heat treatments currently used in the United States and that the operating experience depends, in part, on the type of material used. This paper summarizes the regulatory framework for ensuring steam generator tube integrity, it highlights the current status of steam generators, and it highlights some of the steam generator issues and challenges that exist in the United States. (author)

  19. Replacement of steam generators at arkansas nuclear one, unit-2 (ano-2)

    International Nuclear Information System (INIS)

    Wilson, R.M.; Buford, A.

    2001-01-01

    The Arkansas Nuclear One, Unit-2 steam generators, originally supplied by Combustion Engineering, began commercial operation in 1980 producing a gross electrical output of 958 MW. After several years of successful operation, the owner decided that the tube degradation rates of the original steam generators were too high for the plant to meet the performance requirements for the full 40-year license period. The contract to supply replacement steam generators (RSGs) was awarded to Westinghouse Electric Company in 1996. Installation of these RSGs took place in the last months of 2000. This paper compares the design features of the original and re-placement steam generators with emphasis on design and reliability enhancements achieved. (author)

  20. Forced circulation type steam generator simulation code: HT4

    International Nuclear Information System (INIS)

    Okamoto, Masaharu; Tadokoro, Yoshihiro

    1982-08-01

    The purpose of this code is a understanding of dynamic characteristics of the steam generator, which is a component of High-temperature Heat Transfer Components Test Unit. This unit is a number 4th test section of Helium Engineering Demonstration Loop (HENDEL). Features of this report are as follows, modeling of the steam generator, a basic relationship for the continuity equation, numerical analysis techniques of a non-linear simultaneous equation and computer graphics output techniques. Forced circulation type steam generator with strait tubes and horizontal cut baffles, applied in this code, have be designed at the Over All System Design of the VHTRex. The code is for use with JAERI's digital computer FACOM M200. About 1.5 sec required for each time step reiteration, then about 40 sec cpu time required for a standard problem. (author)

  1. Design and operating experiences with 50MW steam generator

    International Nuclear Information System (INIS)

    Kawara, M.; Yamaki, H.; Kanamori, A.; Tanaka, K.; Takahashi, T.

    1975-01-01

    The main purpose of the 50 MW steam generator is to have experiences of manufacturing and operation with large scale steam generator including necessary research and development works which can be reflected on the design and fabrication of 'Monju' (Japan 300 MWe prototype LMFBR). The detailed design of the 50 MW steam, generator was begun on March, 1972 and succeeded in the demonstration of 72 hours continuous operation with full power on June, 1974. It has been successfully operated since then, the performances of which have been evaluated through various kinds of tests. In this paper, the following items are mainly discussed system design, thermal and hydraulic design, structure and fabrication and some experiences on testing operation including cleaning and sodium flushing of equipment, sodium level control system, the behavior of hydrogen detection system and general outlook of the performance. (author)

  2. Design and operating experiences with 50MW steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Kawara, M; Yamaki, H; Kanamori, A; Tanaka, K; Takahashi, T

    1975-07-01

    The main purpose of the 50 MW steam generator is to have experiences of manufacturing and operation with large scale steam generator including necessary research and development works which can be reflected on the design and fabrication of 'Monju' (Japan 300 MWe prototype LMFBR). The detailed design of the 50 MW steam, generator was begun on March, 1972 and succeeded in the demonstration of 72 hours continuous operation with full power on June, 1974. It has been successfully operated since then, the performances of which have been evaluated through various kinds of tests. In this paper, the following items are mainly discussed system design, thermal and hydraulic design, structure and fabrication and some experiences on testing operation including cleaning and sodium flushing of equipment, sodium level control system, the behavior of hydrogen detection system and general outlook of the performance. (author)

  3. Depth-Sizing Technique for Crack Indications in Steam Generator Tubing

    International Nuclear Information System (INIS)

    Cho, Chan Hee; Lee, Hee Jeong; Kim, Hong Deok

    2009-01-01

    The nuclear power plants have been safely operated by plugging the steam generator tubes which have the crack indications. Tube rupture events can occur if analysts fail to detect crack indications during in-service inspection. There are various types of crack indication in steam generator tubes and they have been detected by the eddy current test. The integrity assessment should be performed using the crack-sizing results from eddy current data when the crack indication is detected. However, it is not easy to evaluate the crack-depth precisely and consistently due to the complexity of the methods. The current crack-sizing methods were reviewed in this paper and the suitable ones were selected through the laboratory tests. The retired steam generators of Kori Unit 1 were used for this study. The round robin tests by the domestic qualified analysts were carried out and the statistical models were introduced to establish the appropriate depth-sizing techniques. It is expected that the proposed techniques in this study can be utilized in the Steam Generator Management Program

  4. Effect of heat transfer tube leak on dynamic characteristic of steam generator

    International Nuclear Information System (INIS)

    Sun Baozhi; Shi Jianxin; Li Na; Zheng Lusong; Liu Shanghua; Lei Yu

    2015-01-01

    Taking the steam generator of Daya Bay Nuclear Power Station as the research object, one-dimensional dynamic model of the steam generator based on drift flux theory and leak model of heat transfer tube were established. Steady simulation of steam generator under different conditions was carried out. Based on verifying the drift flux model and leak model of heat transfer tube, the effect of leak location and flow rate under different conditions on steam generator's key parameters was studied. The results show that the drift flux model and leak model can reflect the law of key parameter change accurately such as vapor mass fraction and steam pressure under different leak cases. The variation of the parameters is most apparent when the leak is at the entrance of boiling section and vapor mass fraction varies from 0.261 to 0.163 when leakage accounts for 5% of coolant flow rate. The successful prediction of the effect of heat transfer tube leak on dynamic characteristics of the steam generator based on drift flux theory supplies some references for monitoring and taking precautionary measures to prevent heat transfer tube leak accident. (authors)

  5. Condition monitoring of steam generator by estimating the overall heat transfer coefficient

    International Nuclear Information System (INIS)

    Furusawa, Hiroaki; Gofuku, Akio

    2013-01-01

    This study develops a technique for monitoring in on-line the state of the steam generator of the fast-breeder reactor (FBR) “Monju”. Because the FBR uses liquid sodium as coolant, it is necessary to handle liquid sodium with caution due to its chemical characteristics. The steam generator generates steam by the heat of secondary sodium coolant. The sodium-water reaction may happen if a pinhole or crack occurs at the thin metal tube wall that separates the secondary sodium coolant and water/steam. Therefore, it is very important to detect an anomaly of the wall of heat transfer tubes at an early stage. This study aims at developing an on-line condition monitoring technique of the steam generator by estimating overall heat transfer coefficient from process signals. This paper describes simplified mathematical models of superheater and evaporator to estimate the overall heat transfer coefficient and a technique to diagnose the state of the steam generator. The applicability of the technique is confirmed by several estimations using simulated process signals with artificial noises. The results of the estimations show that the developed technique can detect the occurrence of an anomaly. (author)

  6. Steam generator of FBR type reactor

    International Nuclear Information System (INIS)

    Hashiguchi, Ko.

    1992-01-01

    Liquid metal (for example, mercury) which is scarcely reactive with metal sodium is contained and cover gases which are scarcely reactive with the liquid metal are filled in a steam generator of an FBR type reactor and it is closed. The heat of primary sodium is transferred to the liquid metal, which is not reactive with sodium, in a primary thermal conduction portion. Since the temperature of the primary thermal conduction portion is high, the density is extremely low. On the other hand, since a second thermal conduction portion is kept at a single phase and the temperature is lower compared with that of the first thermal conduction portion, the density is kept high. since the density difference and gas jetting speed generate a great circulating force to liquid metal passing the opening of a partition plate, heat can be conducted on the side of water without disposing pumps. The steam concentration in the liquid metal is low being in a single phase of steams, corrosion caused from the outside of pipes of the primary thermal conduction pipe is scarcely promoted. Even if sodium leaks should be caused, since the sodium concentration in the liquid metal is extremely low and the reactivity is low, the temperature of the liquid metal is not elevated. (N.H.)

  7. Steam generators in PWR's

    International Nuclear Information System (INIS)

    Michel, R.

    1974-01-01

    The steam generator of the PWR operates according to the principle of natural circulation. It consists of a U-shaped tube bundle whose free ends are welded to a bottom plate. The tube bundle is surrounded by a cylinder jacket which has slots closely above the bottom or tube plate. The feed water mixed with boiling water enters the tube bundle through these slots. Because of its buoyancy, the steam-water mixture flows upwards. Below the tube plate there are chambers for distributing and collecting pressurized water separated by means of a partition wall. By omitting some tubes, a free alloy is created so that the tubes in the center get sufficient water, too. By asymmetrical arrangement of the partition wall it is further possible to limit the tube alloy only to the inlet side for pressurized water. The flow over the tube plate is thus improved on the inlet side. (DG) [de

  8. Primary manway shielding and exhaust covers for a steam generator

    International Nuclear Information System (INIS)

    Wallace, W.R.; Immel, A.K.; Boro, I.; Lester, W.E. II.

    1990-01-01

    This paper discusses a radiation emission shielding cover in combination with a steam generator of a nuclear reactor for covering at least a portion of a manway of the steam generator for protecting an operator from radiation emission. It comprises a plate; a mounting assembly including a mounting flange for securing the mounting assembly adjacent the manway of the steam generator and a mounting bracket; a slide means mounted on the mounting bracket adjacent the manway; and guide means mounted on the plate for receiving the slide means such that the plate can be moved from an open position adjacent the manway to a closed position over at least a portion of the manway

  9. Steam Generator Owners Group PWR secondary water chemistry guidelines

    International Nuclear Information System (INIS)

    Welty, C.S. Jr.; Green, S.J.

    1985-01-01

    In 1981 the Steam Generator Owners Group (SGOG), a group of domestic and foreign pressurized water reactor (PWR) owners, developed and issued the PWR secondary water chemistry guidelines. The guidelines were prepared in response to the growing recognition that a majority of the problems causing reduced steam generator reliability (e.g., denting, wasteage, pitting, etc.) were related to secondary (steam) side water purity. The guidelines were subsequently issued as an Electric Power Research Institute (EPRI) report. In 1984 they were revised to reflect industry experience in adopting the original issuance and to incorporate new information on causes of corrosion damage. The guidelines have been endorsed and their adoption recommended by the SGOG

  10. Dryout in sodium-heated helically-coiled steam generator tubes

    International Nuclear Information System (INIS)

    Tomita, Y.; Kosugi, T.; Kubota, J.; Nakajima, K.; Tsuchiya, T.

    1984-01-01

    Experimental research on the dryout phenomenon in sodium heated, helically coiled steam generator tubes was carried out. The fluctuation of the tube wall temperature caused by dryout was measured with thermocouples installed in the center of the tube wall. Empirical correlations of dryout quality were developed as functions of critical heat flux, water mass velocity and saturation pressure. These correlations confirmed that the design criterion of the MONJU steam generator was reasonable. (author)

  11. Design and construction of a steam generator with feedback

    International Nuclear Information System (INIS)

    Camargo, Camila C.; Placco, Guilherme M.; Guimaraes, Lamartine N.F.

    2013-01-01

    The EARTH project aims to develop technologies to design and build systems that generate electricity in space, using microreactors. One of the activities within the TERRA project aims to build a closed thermal cycle Rankine type in order to test a Tesla turbine type. The objective of this work is to design and build a steam generator with feedback, which should ensure a satisfactory range of steam supply, security system, feedback system and heating system

  12. Dynamic instability forecasting for through-out sodium steam generators

    International Nuclear Information System (INIS)

    Aleksandrov, V.V.; Rassokhin, N.G.

    1985-01-01

    Simplified technique for determining boundaries of dynamic instability of through-out sodium steam generators is presented. The technique is based on the application of autoresonance concept to autooscillating model of dynamic instability of a steam-generating channel. Estimated model parameters and basic investigational results for different conditions are given. Assessment is performed according to the instability degree. Use of the technique is effective for multiversion studying of SG design at early designing stages

  13. Reliability study: steam generation and distribution system, Portsmouth Gaseous Diffusion Plant

    International Nuclear Information System (INIS)

    Baker, F.E.; Davis, E.L.; Dent, J.T.; Walters, D.E.; West, R.M.

    1982-10-01

    A reliability study for determining the ability of the Steam Generation and Distribution System to provide reliable and adequate service through the year 2000 has been completed. This study includes an evaluation of the X-600 Steam Plant and the steam distribution system. The Steam Generation and Distribution System is in good overall condition, but to maintain this condition, the reliability study team made twelve recommendations. Eight of the recommendations are for repair or replacement of existing equipment and have a total estimated cost of $540,000. The other four recommendations are for additional testing, new procedure implementation, or continued investigations

  14. Fracture toughness determination in steam generator tubes

    International Nuclear Information System (INIS)

    Bergant M; Yawny, A; Perez Ipina, J

    2012-01-01

    The assessment of the structural integrity of steam generator tubes in nuclear power plants deserved increasing attention in the last years due to the negative impact related to their failures. In this context, elastic plastic fracture mechanics (EPFM) methodology appears as a potential tool for the analysis. The application of EPFM requires, necessarily, knowledge of two aspects, i.e., the driving force estimation in terms of an elastic plastic toughness parameter (e.g., J) and the experimental measurement of the fracture toughness of the material (e.g., the material J-resistance curve). The present work describes the development of a non standardized experimental technique aimed to determine J-resistance curves for steam generator tubes with circumferential through wall cracks. The tubes were made of Incoloy 800 (Ni: 30.0-35.0; Cr: 19.0-23.0; Fe: 35.5 min, % in weight). Due to its austenitic microstructure, this alloy shows very high toughness and is widely used in applications where a good corrosion resistance in aqueous environment or an excellent oxidation resistance in high temperature environment is required. Finally, a procedure for the structural integrity analysis of steam generator tubes with crack-like defects, based on a FAD diagram (Failure Assessment Diagram), is briefly described (author)

  15. A study on the steam generator data base and the evaluation of chemical environment

    International Nuclear Information System (INIS)

    Yang, Kyung Rin; Yoo, Je Hyoo; Lee, Eun He; Hong, Kwang Pum

    1990-01-01

    In order to make steam generator data base, the basic plant information and water quality control data on the steam generators of the PWR nuclear power plant operating in the world have been collected by EPRI. In this project, the basic information and water quality control data of the domestic PWR nuclear power plants were collected to make steam generator data base on the basic of the EPRI format table, and the computerization of them was performed. Also, the technical evaluation of chemical environments on steam generator of the Kori 2 plant chemists. Workers and researchers working at the research institute and universities and so on. Especially, it is able to be used as a basic plant information in order to develop an artificial intellegence development system in the field on the technical development of the chemical environment. The scope and content of the project are following. The data base on the basic information data in domestic PWR plant. The steam generator data base on water quality control data. The evaluation on the chemical environment in the steam generators of the Kori 2 plant. From previous data, it is concluded as follows. The basic plant information on the domestic PWR power plant were computerized. The steam generator data base were made on the basis of EPRI format table. The chemical environment of the internal steam generators could be estimated from the analytical evaluation of water quality control data of the steam generator blowdown. (author)

  16. Process for superheating the steam generated by a light water nuclear reactor

    International Nuclear Information System (INIS)

    Vakil, H.B.; Brown, D.H.

    1976-01-01

    A process is submitted for superheating the pressurised steam generated in a light water nuclear reactor in which the steam is brought to 340 0 C at least. This superheated steam is used to operate a turbo-generator unit. The characteristic of the process is that an exothermal chemical reaction is used to generate the heat utilised during the superheating stage. The chemical reaction is a mechanisation, oxidation-reduction or hydrogenation reaction [fr

  17. Influence of feedwater and blowdown systems on the mineral distribution in WWER steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Papp, L. [Inst. of Material Engineering, Ostrava (Switzerland)

    1995-12-31

    After modification of Dukovany NPP steam generator (SG) feedwater system, the increased concentration of minerals was measured in the cold leg of modified SG. Some modifications were performed on operating WWER 1000 steam generators with aim to optimize the water chemistry in the collectors area. Since the distribution of minerals can substantially affect on corrosion processes in steam generators, VITKOVICE, as a producer of WWER steam generators has focused the attention to the optimizing of these systems. To predict the mineral distribution on the secondary side of steam generators for considered feedwater/blowdown systems, the simple model of the flow distribution in the secondary side of SG was developed.

  18. Influence of feedwater and blowdown systems on the mineral distribution in WWER steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Papp, L [Inst. of Material Engineering, Ostrava (Switzerland)

    1996-12-31

    After modification of Dukovany NPP steam generator (SG) feedwater system, the increased concentration of minerals was measured in the cold leg of modified SG. Some modifications were performed on operating WWER 1000 steam generators with aim to optimize the water chemistry in the collectors area. Since the distribution of minerals can substantially affect on corrosion processes in steam generators, VITKOVICE, as a producer of WWER steam generators has focused the attention to the optimizing of these systems. To predict the mineral distribution on the secondary side of steam generators for considered feedwater/blowdown systems, the simple model of the flow distribution in the secondary side of SG was developed.

  19. Influence of feedwater and blowdown systems on the mineral distribution in WWER steam generators

    International Nuclear Information System (INIS)

    Papp, L.

    1995-01-01

    After modification of Dukovany NPP steam generator (SG) feedwater system, the increased concentration of minerals was measured in the cold leg of modified SG. Some modifications were performed on operating WWER 1000 steam generators with aim to optimize the water chemistry in the collectors area. Since the distribution of minerals can substantially affect on corrosion processes in steam generators, VITKOVICE, as a producer of WWER steam generators has focused the attention to the optimizing of these systems. To predict the mineral distribution on the secondary side of steam generators for considered feedwater/blowdown systems, the simple model of the flow distribution in the secondary side of SG was developed

  20. Reevaluation of steam generator level trip set point

    Energy Technology Data Exchange (ETDEWEB)

    Shim, Yoon Sub; Soh, Dong Sub; Kim, Sung Oh; Jung, Se Won; Sung, Kang Sik; Lee, Joon [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    1994-06-01

    The reactor trip by the low level of steam generator water accounts for a substantial portion of reactor scrams in a nuclear plant and the feasibility of modification of the steam generator water level trip system of YGN 1/2 was evaluated in this study. The study revealed removal of the reactor trip function from the SG water level trip system is not possible because of plant safety but relaxation of the trip set point by 9 % is feasible. The set point relaxation requires drilling of new holes for level measurement to operating steam generators. Characteristics of negative neutron flux rate trip and reactor trip were also reviewed as an additional work. Since the purpose of the trip system modification for reduction of a reactor scram frequency is not to satisfy legal requirements but to improve plant performance and the modification yields positive and negative aspects, the decision of actual modification needs to be made based on the results of this study and also the policy of a plant owner. 37 figs, 6 tabs, 14 refs. (Author).