WorldWideScience

Sample records for acceptance test procedure

  1. Void fraction instrument acceptance test procedure

    This acceptance test procedure (ATP) was written to test the void fraction instrument (VFI) and verify that the unit is ready for field service. The procedure verifies that the mechanical and electrical features (not specifically addressed in the software ATP) and software alarms are operating as designed

  2. W-087 Acceptance test procedure. Revision 1

    Joshi, A.W.

    1997-06-10

    This Acceptance Test Procedure/Operational Test Procedure (ATP/OTP) has been prepared to demonstrate that the Electrical/Instrumentation and Mechanical systems function as required by project criteria and to verify proper operation of the integrated system including the interlocks.

  3. Diesel generator trailer acceptance test procedure

    This Acceptance Test Procedure (ATP) will document compliance with the requirements of WHC-S-0252 Rev. 1 and ECNs 609271, and 609272. The equipment being tested is a 150KW Diesel Generator mounted on a trailer with switchgear. The unit was purchased as a Design and Fabrication procurement activity. The ATP was written by the Seller and will be performed by the Seller with representatives of the Westinghouse Hanford Company witnessing the test at the Seller's location

  4. Gas characterization system software acceptance test procedure

    This document details the Software Acceptance Testing of gas characterization systems. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases

  5. Void fraction instrument acceptance test procedure

    This document presents the results of the acceptance test for the mechanical and electrical features (not specifically addressed by the software ATP) of the void fraction instrument (VFI). Acceptance testing of the VFI, control console, and decontamination spray assembly was conducted in the 306E building high bay and area adjacent to the facility. The VFI was tested in the horizontal position supported in multiple locations on rolling tables. The control console was located next to the VFI pneumatic control assembly. The VFI system was operated exactly as is expected in the tank farm, with the following exceptions: power was provided from a building outlet and the VFI was horizontal. The testing described in this document verifies that the mechanical and electrical features are operating as designed and that the unit is ready for field service

  6. Enraf Series 854 advanced technology gauge (ATG) acceptance test procedure

    This Acceptance Test Procedure was written to test the Enraf Series 854 Advanced Technology Gauge (ATG) prior to installation in the Tank Farms. The procedure sets various parameters and verifies that the gauge is functional

  7. Factory Acceptance Test Procedure Westinghouse 100 ton Hydraulic Trailer

    This Factory Acceptance Test Procedure (FAT) is for the Westinghouse 100 Ton Hydraulic Trailer. The trailer will be used for the removal of the 101-SY pump. This procedure includes: safety check and safety procedures; pre-operation check out; startup; leveling trailer; functional/proofload test; proofload testing; and rolling load test

  8. Operator coil monitoring Acceptance Test Procedure

    The readiness of the Data Acquisition and Control System (DACS) to provide monitoring and control of the Programmable Logic Controller (PLC) abort coils from the Master and RSS stations will be systematically tested during performance of this procedure. It should be noted that these are not physical abort coils but software coils controlled by the software's ladder logic. The readiness of the DACS to properly interface with the ENRAF wire level gauge installed in the SY-101 storage tank will also be tested. During this test, a verification of all abort coil indications will be conducted at the DACS Development Facility in the 306E Building by injecting an input signal for each DACS sensor that has an associated abort coil until the abort coil actuates, and then ensuring that the status of the abort coil indicated at the Master and RSS stations is correct. Each abort coil will also be tested to ensure that the ''ENABLE'' and ''DISABLE'' controls from the Master and RSS stations function correctly, and only with the use of proper passwords

  9. Acceptance test procedure for High Pressure Water Jet System

    The overall objective of the acceptance test is to demonstrate a combined system. This includes associated tools and equipment necessary to perform cleaning in the 105 K East Basin (KE) for achieving optimum reduction in the level of contamination/dose rate on canisters prior to removal from the KE Basin and subsequent packaging for disposal. Acceptance tests shall include necessary hardware to achieve acceptance of the cleaning phase of canisters. This acceptance test procedure will define the acceptance testing criteria of the high pressure water jet cleaning fixture. The focus of this procedure will be to provide guidelines and instructions to control, evaluate and document the acceptance testing for cleaning effectiveness and method(s) of removing the contaminated surface layer from the canister presently identified in KE Basin. Additionally, the desired result of the acceptance test will be to deliver to K Basins a thoroughly tested and proven system for underwater decontamination and dose reduction. This report discusses the acceptance test procedure for the High Pressure Water Jet

  10. Surface moisture measurement system hardware acceptance test procedure

    The purpose of this acceptance test procedure is to verify that the mechanical and electrical features of the Surface Moisture Measurement System are operating as designed and that the unit is ready for field service. This procedure will be used in conjunction with a software acceptance test procedure, which addresses testing of software and electrical features not addressed in this document. Hardware testing will be performed at the 306E Facility in the 300 Area and the Fuels and Materials Examination Facility in the 400 Area. These systems were developed primarily in support of Tank Waste Remediation System (TWRS) Safety Programs for moisture measurement in organic and ferrocyanide watch list tanks

  11. ENRAF Series 854 Advanced Technology Gauge (ATG) Acceptance Test Procedure

    This procedure provides acceptance testing for Enraf Series 854 level gauges used to monitor levels in Hanford Waste Storage Tanks. The test will verify that the gauge functions according to the manufacturer's instructions and specifications and is properly setup prior to being delivered to the tank farm area. This ATP does not set up the gauge for any specific tank, but is generalized to permit testing the gauge prior to installation package preparation

  12. Project W-049H instrument and control Acceptance Test Procedure

    The purpose of this Acceptance Test Procedure (ATP) for the Project W-049H, Treated Effluent Disposal Facility, is to verify that the instrument and control systems have been installed in accordance with the design documents and function as required by the project criteria. The instrument and control system includes three operator control stations, modems, and general purpose LAN interface cabinets in the Effluent Treatment Facility control room; two pump stations; disposal station pumping building; and all local control units installed in the fold. Testing will be performed using actual signals when available and simulated signals when actual signals are unavailable

  13. Project W-049H collection system Acceptance Test Procedure

    The purpose of this Acceptance Test Procedure (ATP) for the Project W-049H, Treated Effluent Disposal Facility, is to verify that the collection system equipment installed as Pump Station No. 1 (225-W) and Pump Station No. 2 (225-E) have been installed in accordance with the design documents and function as required by the project criteria. This will be a wet test with potable water being introduced into the pump pits to test for leakage. Potable water will also be employed in the testing of the pumps and related mechanical equipment. All Instrument and Control equipment related to the pump stations will be checked electronically with simulated inputs/outputs when actual input/output signals are unavailable. Water from Pump Station 1 will be moved through the TEDF piping system and discharged into the disposal ponds. This will check the proper function of the air/vac valves not tested during construction, and the automated samplers

  14. Loss on Ignition Furnace Acceptance and Operability Test Procedure

    JOHNSON, D.C.

    2000-06-01

    The purpose of this Acceptance Test Procedure and Operability Test Procedure (ATP/OTP)is to verify the operability of newly installed LOI equipment, including a model 1608FL CM{trademark} Furnace, a dessicator, and balance. The operability of the furnace will be verified. The arrangement of the equipment placed in Glovebox 157-3/4 to perform Loss on Ignition (LOI) testing on samples supplied from the Thermal Stabilization line will be verified. In addition to verifying proper operation of the furnace, this ATP/OTP will also verify the air flow through the filters, verify a damper setting to establish and maintain the required differential pressure between the glovebox and the room pressure, and test the integrity of the newly installed HEPA filter. In order to provide objective evidence of proper performance of the furnace, the furnace must heat 15 crucibles, mounted on a crucible rack, to 1000 C, according to a program entered into the furnace controller located outside the glovebox. The glovebox differential pressure will be set to provide the 0.5 to 2.0 inches of water (gauge) negative pressure inside the glovebox with an airflow of 100 to 125 cubic feet per minute (cfm) through the inlet filter. The glovebox inlet Glfilter will he flow tested to ensure the integrity of the filter connections and the efficiency of the filter medium. The newly installed windows and glovebox extension, as well as all disturbed joints, will be sonically tested via ultra probe to verify no leaks are present. The procedure for DOS testing of the filter is found in Appendix A.

  15. Acceptance test procedure for Project W-049H

    The Acceptance Test Procedure (ATP) program for Project W-049H (200 Area Treated Effluent Disposal Facility [TEDF]) covers three activities as follows: (1) Disposal System; (2) Collection System; and (3) Instrumentation and Control System. Each activity has its own ATP. The purpose of the ATPs is to reverify that the systems have been constructed in accordance with the construction documents and to demonstrate that the systems function as required by the Project criteria. The Disposal System ATP covers the testing of the following: disposal line flowmeters, room air temperatures in the Disposal Station Sampling Building, effluent valves and position indicators, disposal pond level monitors, automated sampler, pressure relief valves, and overflow diversion sluice gates. The Collection System ATP covers the testing of the two pump stations and all equipment installed therein. The Instrumentation and Control (I and C) ATP covers the testing of the entire TEDF I and C system. This includes 3 OCS units, modem, and GPLI cabinets in the ETC control room; 2 pump stations; disposal station sampling building; and all LCUs installed in the field

  16. Acceptance test procedure MICON software exhaust fan control modifications

    This acceptance test verifies the MICON program changes for the new automatic transfer switch ATS-2 alarms, the Closed Loop Cooling isolator status, the CB-3 position alarm, and the alarms for the new emergency fan damper backup air compressor

  17. Test Report for Acceptance Test Procedure for Pumping and Instrumentation Control Skid ''K''

    This is a Test Report for Acceptance Test Procedure (ATP) HNF-4276. This test report provides the results of the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''K''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document

  18. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid L

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5055. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''L''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document

  19. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid N

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5489. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''N''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document

  20. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid M

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5073. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''M''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document

  1. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid L

    KOCH, M.R.

    1999-11-09

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5055. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''L''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  2. Test Report for Acceptance Test Procedure for Pumping and Instrumentation Control Skid ''K''

    Johns, B R

    1999-01-01

    This is a Test Report for Acceptance Test Procedure (ATP) HNF-4276. This test report provides the results of the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''K''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  3. Acceptance test procedure for the 105-KW isolation barrier leak rate

    This acceptance test procedure shall be used to: First establish a basin water loss rate prior to installation of the two isolation barriers between the main basin and the discharge chute in K-Basin West. Second, perform an acceptance test to verify an acceptable leakage rate through the barrier seals. This Acceptance Test Procedure (ATP) has been prepared in accordance with CM-6-1 EP 4.2, Standard Engineering Practices

  4. Acceptance test procedure for the 105-KW isolation barrier leak rate

    McCracken, K.J.

    1995-05-19

    This acceptance test procedure shall be used to: First establish a basin water loss rate prior to installation of the two isolation barriers between the main basin and the discharge chute in K-Basin West. Second, perform an acceptance test to verify an acceptable leakage rate through the barrier seals. This Acceptance Test Procedure (ATP) has been prepared in accordance with CM-6-1 EP 4.2, Standard Engineering Practices.

  5. Acceptance Test Procedure: SY101 air pallet system

    The purpose of this test procedure is to verify that the system(s) procured to load the SY-101 Mitigation Test Pump package fulfills its functional requirements. It will also help determine the man dose expected due to handling of the package during the actual event. The scope of this procedure focuses on the ability of the air pallets and container saddles to carry the container package from the new 100 foot concrete pad into 2403-WD where it will be stored awaiting final disposition. This test attempts to simulate the actual event of depositing the SY-101 hydrogen mitigation test pump into the 2403-WD building. However, at the time of testing road modifications required to drive the 100 ton trailer into CWC were not performed. Therefore a flatbed trailer will be use to transport the container to CWC. The time required to off load the container from the 100 ton trailer will be recorded for man dose evaluation on location. The cranes used for this test will also be different than the actual event. This is not considered to be an issue due to minimal effects on man dose

  6. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid W

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''W''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  7. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid L

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''L''. The ATP will be performed after the construction of the PIC skid in the shop

  8. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''P''

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''P''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  9. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''V''

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designated as ''V''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  10. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''U''

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''U''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  11. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid T

    This Acceptance Test Procedure (ATP) provides for the inspection and testing Of the new Pumping Instrumentation and Control (PIC) skid designed as ''T''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  12. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''R''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  13. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''Q''

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''Q''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  14. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''T''

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designated as ''T''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  15. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid N

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''N''. The ATP will be performed after the construction of the PIC skid in the shop

  16. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid V

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control. (PIC) skid designed as ''V''. The ATP will be performed after the construction of the PIC skid in the fabrication shop

  17. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid sup L sup

    Koch, M R

    1999-01-01

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''L''. The ATP will be performed after the construction of the PIC skid in the shop.

  18. PDSS/IMC qualification test software acceptance procedures

    1984-01-01

    Tests to be performed for qualifying the payload development support system image motion compensator (IMC) are identified. The performance of these tests will verify the IMC interfaces and thereby verify the qualification test software.

  19. Tank Monitoring and Control System (TMACS) Acceptance Test Procedure

    This document is intended to test the software portion of TMACS. The tests will be performed on the development system. The software to be tested is the TMACS knowledge bases (KB) and the I/O driver devices. The development system will not be talking to field equipment; instead, the field equipment is simulated using emulators or multiplexers in the lab

  20. Tank Monitoring and Control System (TMACS) Acceptance Test Procedure

    The purpose of this document is to describe tests performed to validate Revision 12.0 of the TMACS Monitor and Control System (TMACS) and verify that the software functions as intended by design. This document is intended to test the software portion of TMACS. The tests will be performed on the development system. The software to be tested is the TMACS knowledge bases (KB) and the I/O driver/services. The development system will not be communicating to field equipment; instead, the field equipment is simulated using emulators or multiplexers in the lab

  1. Tank Monitoring and Control System (TMACS) Acceptance Test Procedure

    BARNES, D.A.

    2000-06-01

    The purpose of this document is to describe tests performed to validate Revision 12.0 of the TMACS Monitor and Control System (TMACS) and verify that the software functions as intended by design. This document is intended to test the software portion of TMACS. The tests will be performed on the development system. The software to be tested is the TMACS knowledge bases (KB) and the I/O driver/services. The development system will not be communicating to field equipment; instead, the field equipment is simulated using emulators or multiplexers in the lab.

  2. Tank Monitoring and Control System (TMACS) Acceptance Test Procedure

    The purpose of this document is to describe tests performed to validate Revision 11.2 of the TMACS Monitor and Control System (TMCACS) and verify that the software functions as intended by design. The tests will be performed on the development system. The software to be tested is the TMACS knowledge bases (KB) and the I/O driver/services. The development system will not be talking to field equipment; instead, the field equipment is simulated using emulators or multiplexers in the lab

  3. MAC mini acceptance test procedures, software Version 3.3

    The K Basins Materials Accounting (MAC) programs had some improvements made to it to to change slightly the access authorized users had to the modification of critical data. This ATP describes how the code was to be tested to verify its correctness

  4. MBA acceptance test procedures, software Version 1.4

    The Mass Balance Program (MBA) is an adjunct to the Materials Accounting database system, Version 3.4. MBA was written to equip the personnel performing K-Basin encapsulation tasks with a conservative estimate of accumulated sludge during the processing of canisters into and out of the chute. The K Basins Materials Balance programs had some minor improvements made to it to feedback the chute processing status to the operator better. This ATP describes how the code was to be tested to verify its correctness

  5. Project B610 process control configuration acceptance test procedure

    The purpose of this test is to verify the Westinghouse configuration of the MICON A/S Distributed Control System for project B610. The following will be verified: proper assignment and operation of all field inputs to and outputs from the MICON Termination panels; proper operation of all display data on the operator's console; proper operation of all required alarms; and proper operation of all required interlocks. The MICON A/S control system is configured to replace all the control, indication, and alarm panels now located in the Power Control Room. Nine systems are covered by this control configuration, 2736-ZB HVAC, 234-5Z HVAC, Process Vacuum, Dry Air, 291-Z Closed Loop Cooling, Building Accelerometer, Evacuation Siren, Stack CAMs, and Fire. The 2736-ZB HVAC system consists of the ventilation controls for 2736-ZB and 2736-Z as well as alarms for the emergency generators and 232-Z. The 234-5Z HVAC system is the ventilation controls for 235-5Z and 236-Z buildings. Process Vacuum covers the controls for the 26 inch vacuum system. Dry Air covers the controls for the steam and electric air dryers. The 291-Z Closed Loop Cooling system consists of the status indications and alarms for the 291-Z compressor and vacuum pump closed loop cooling system. The rest of closed loop cooling was tested earlier. The Building Accelerometer system consists of the status indications for the two seismic system accelerometers. The Evacuation Siren system includes the controls for the evacuation and take cover sirens. Stack CAMs cover the alarms for the various building ventilation stack continuous air monitors. Finally, the Fire system covers the various fire alarms now located in Room 321-A

  6. Enraf series 854 Advanced Technology Gauge (ATG) acceptance test procedure. Revision 3

    This procedure provides acceptance testing for Enraf Series 854 level gauges used to monitor levels in Hanford Waste Storage Tanks. The test will verify that the gauge functions according to the manufacturer's instructions and specifications and is properly setup prior to being delivered to the tank farm area

  7. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''V''

    This Acceptance Test Procedure (ATP) verifies proper construction per the design drawings and tests for proper functioning of the Pumping Instrumentation and Control (PIC) skid ''V''. The scope section lists the systems and functions to be checked. This ATP will be performed at the Site Fabrication Services (SFS) shop upon completion of the construction of the PIC skid

  8. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid M

    This Acceptance Test Procedure (ATP) verifies proper construction per the design drawings and tests for proper functioning of the Pumping and Instrumentation Control (PIC) skid ''M''. The Scope section lists the systems and functions to be checked. This ATP will be performed at the Site Fabrication Service's (SFS) shop upon completion of construction of the PIC skid

  9. Test Report for Acceptance Test Procedure for Pumping and Instrumentation Control Skid ''K''

    JOHNS, B.R.

    1999-10-28

    This is a Test Report for Acceptance Test Procedure (ATP) HNF-4276. This test report provides the results of the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''K''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  10. ENRAF Series 854 Advanced Technology Gauge (ATG) with SPU II card for Leak Detector Use Acceptance Test Procedure

    The following Acceptance Test Procedure was written to test the ENRAF series 854 ATG with SPU II card prior to installation in the Tank Farms. The procedure sets various parameters and verifies the gauge and alarms functionality

  11. ENRAF Series 854 Advanced Technology Gauge (ATG) with SPU ll Card for Leak Detector Use Acceptance Test Procedure

    The following Acceptance Test Procedure was written to test the Enraf Series 854 ATG with SPU-II card prior to installation in the Tank Farms. The procedure sets various parameters and verifies the gauge and the alarms functionality

  12. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid ''P''

    This Acceptance Test Report (ATR) provides the test results for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''P''. The ATR summaries the results and provides a copy of the ATP and inspections in the Appendix

  13. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid Q

    This Acceptance Test Report (ATR) provides the test results for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''Q''. The ATR summaries the results and provides a copy of the ATP and inspections in the Appendix

  14. Acceptance test procedure for a portable, self-contained nitrogen supply

    This Acceptance Test Procedure (ATP) will document compliance with the requirements of WHC-S-0249 Rev. 1 and ECN 606112. The equipment being tested is a Portable, Self-Contained Nitrogen Supply. The unit was purchased as a Design and Fabrication procurement activity. The Functional Test was written by the Seller and is contained in Appendix A. The Functional test will be performed by the Seller with representatives of the Westinghouse Hanford Company performing inspection and witnessing the functional test at the Seller's location

  15. Acceptance test procedure, 241-SY-101/241-C-106 shot loading system

    This Acceptance Test Procedure is for the 241-SY-101/241-C-106 Shot Loading System. The procedure will test the components of the Shot Loading System and its capability of adequately loading shot into the annular space of the Container. The loaded shot will provide shielding as required for transporting and storage of a contaminated pump after removal from the tank. This test serves as verification that the SLS is acceptable for use in the pump removal operations for Tanks 241-SY-101, 241-C-106 and 241-AY-102. The pump removal operation for these three tanks will be performed by two different organizations with different equipment, but the Shot Loading System will be compatible between the two operations

  16. Acceptance test procedure for K basins dose reduction project clean and coat equipment

    This document is the Acceptance Test Procedure (ATP) for the clean and coat equipment designed by Oceaneering Hanford, Inc. under purchase order MDK-XVC-406988 for use in the 105 K East Basin. The ATP provides the guidelines and criteria to test the equipment's ability to clean and coat the concrete perimeter, divider walls, and dummy elevator pit above the existing water level. This equipment was designed and built in support of the Spent Nuclear Fuel, Dose Reduction Project. The ATP will be performed at the 305 test facility in the 300 Area at Hanford. The test results will be documented in WHC-SD-SNF-ATR-020

  17. Acceptance test procedure for K basins dose reduction project clean and coat equipment

    Creed, R.F.

    1996-03-11

    This document is the Acceptance Test Procedure (ATP) for the clean and coat equipment designed by Oceaneering Hanford, Inc. under purchase order MDK-XVC-406988 for use in the 105 K East Basin. The ATP provides the guidelines and criteria to test the equipment`s ability to clean and coat the concrete perimeter, divider walls, and dummy elevator pit above the existing water level. This equipment was designed and built in support of the Spent Nuclear Fuel, Dose Reduction Project. The ATP will be performed at the 305 test facility in the 300 Area at Hanford. The test results will be documented in WHC-SD-SNF-ATR-020.

  18. Building Energy Simulation Test for Existing Homes (BESTEST-EX): Instructions for Implementing the Test Procedure, Calibration Test Reference Results, and Example Acceptance-Range Criteria

    Judkoff, R.; Polly, B.; Bianchi, M.; Neymark, J.; Kennedy, M.

    2011-08-01

    This publication summarizes building energy simulation test for existing homes (BESTEST-EX): instructions for implementing the test procedure, calibration tests reference results, and example acceptance-range criteria.

  19. Acceptance/operational test procedure 241-AN-107 Video Camera System

    This procedure will document the satisfactory operation of the 241-AN-107 Video Camera System. The camera assembly, including camera mast, pan-and-tilt unit, camera, and lights, will be installed in Tank 241-AN-107 to monitor activities during the Caustic Addition Project. The camera focus, zoom, and iris remote controls will be functionally tested. The resolution and color rendition of the camera will be verified using standard reference charts. The pan-and-tilt unit will be tested for required ranges of motion, and the camera lights will be functionally tested. The master control station equipment, including the monitor, VCRs, printer, character generator, and video micrometer will be set up and performance tested in accordance with original equipment manufacturer's specifications. The accuracy of the video micrometer to measure objects in the range of 0.25 inches to 67 inches will be verified. The gas drying distribution system will be tested to ensure that a drying gas can be flowed over the camera and lens in the event that condensation forms on these components. This test will be performed by attaching the gas input connector, located in the upper junction box, to a pressurized gas supply and verifying that the check valve, located in the camera housing, opens to exhaust the compressed gas. The 241-AN-107 camera system will also be tested to assure acceptable resolution of the camera imaging components utilizing the camera system lights

  20. CENRTC Project number-sign 2F3EOA, OCB A-376, acceptance test procedure

    This test procedure provides the steps necessary to verify correct functional operation of controls, annunciators, alarms, protective relays and related systems impacted by CENRTC number-sign 2F3E0A, Microwave Transfer Trip Project, modification work performed under work package 6B-93-00041/M. This procedure separates three tests into separate sections: energization of A-376 duplex panel and circuits; SCADA tests; and A-376 local trip tests

  1. Acceptance test procedure for C-018H, 242-A evaporator/PUREX plant process condensate treatment facility

    This Acceptance Test Procedure (ATP) has been prepared to demonstrate that the Electrical/Instrumentation system function as required for this facility. Each company or organization participating in this ATP will designate personnel to assume the responsibilities and duties as defined herein for their respective roles

  2. CENRTC Project No. 2F3EOA, OCB A-372, acceptance test procedure

    Akerson, A.W.

    1995-01-01

    This test procedure provides the steps necessary to verify correct functional operation of controls, annunciators, alarms, protective relays and related systems impacted by CENRTC No. 2F3EOA, Microwave Transfer Trip Project, modification work performed under work package 6B-93-00038/M (CENRTC 2F3EOA MWTT OCB A-372 PACKAGE).

  3. CENRTC Project No. 2F3EOA, OCB A-372, acceptance test procedure

    This test procedure provides the steps necessary to verify correct functional operation of controls, annunciators, alarms, protective relays and related systems impacted by CENRTC No. 2F3EOA, Microwave Transfer Trip Project, modification work performed under work package 6B-93-00038/M (CENRTC 2F3EOA MWTT OCB A-372 PACKAGE)

  4. 105KE Basin Area Radiation Monitor System (ARMS) Acceptance Test Procedure

    KINKEL, C.C.

    1999-12-14

    This procedure is intended for the Area Radiation Monitoring System, ARMS, that is replacing the existing Programmable Input-Output Processing System, PIOPS, radiation monitoring system in the 105KE basin. The new system will be referred to as the 105KE ARMS, 105KE Area Radiation Monitoring System. This ATP will ensure calibration integrity of the 105KE radiation detector loops. Also, this ATP will test and document the display, printing, alarm output, alarm acknowledgement, upscale check, and security functions. This ATP test is to be performed after completion of the 105KE ARMS installation. The alarm outputs of the 105KE ARMS will be connected to the basin detector alarms, basin annunciator system, and security Alarm Monitoring System, AMS, located in the 200 area Central Alarm Station (CAS).

  5. 105KE Basin Area Radiation Monitor System (ARMS) Acceptance Test Procedure

    Kinkel, C C

    1999-01-01

    This procedure is intended for the Area Radiation Monitoring System, ARMS, that is replacing the existing Programmable Input-Output Processing System, PIOPS, radiation monitoring system in the 105KE basin. The new system will be referred to as the 105KE ARMS, 105KE Area Radiation Monitoring System. This ATP will ensure calibration integrity of the 105KE radiation detector loops. Also, this ATP will test and document the display, printing, alarm output, alarm acknowledgement, upscale check, and security functions. This ATP test is to be performed after completion of the 105KE ARMS installation. The alarm outputs of the 105KE ARMS will be connected to the basin detector alarms, basin annunciator system, and security Alarm Monitoring System, AMS, located in the 200 area Central Alarm Station (CAS).

  6. Human Factors Process Task Analysis Liquid Oxygen Pump Acceptance Test Procedure for the Advanced Technology Development Center

    Diorio, Kimberly A.

    2002-01-01

    A process task analysis effort was undertaken by Dynacs Inc. commencing in June 2002 under contract from NASA YA-D6. Funding was provided through NASA's Ames Research Center (ARC), Code M/HQ, and Industrial Engineering and Safety (IES). The John F. Kennedy Space Center (KSC) Engineering Development Contract (EDC) Task Order was 5SMA768. The scope of the effort was to conduct a Human Factors Process Failure Modes and Effects Analysis (HF PFMEA) of a hazardous activity and provide recommendations to eliminate or reduce the effects of errors caused by human factors. The Liquid Oxygen (LOX) Pump Acceptance Test Procedure (ATP) was selected for this analysis. The HF PFMEA table (see appendix A) provides an analysis of six major categories evaluated for this study. These categories include Personnel Certification, Test Procedure Format, Test Procedure Safety Controls, Test Article Data, Instrumentation, and Voice Communication. For each specific requirement listed in appendix A, the following topics were addressed: Requirement, Potential Human Error, Performance-Shaping Factors, Potential Effects of the Error, Barriers and Controls, Risk Priority Numbers, and Recommended Actions. This report summarizes findings and gives recommendations as determined by the data contained in appendix A. It also includes a discussion of technology barriers and challenges to performing task analyses, as well as lessons learned. The HF PFMEA table in appendix A recommends the use of accepted and required safety criteria in order to reduce the risk of human error. The items with the highest risk priority numbers should receive the greatest amount of consideration. Implementation of the recommendations will result in a safer operation for all personnel.

  7. Verification/acceptance test plan/procedure for Acromag calibration system

    Fordham, C.R.

    1994-12-01

    The purpose of this document is to describe and document the test of the Acromag calibration system software. The purpose of this test is to verify that the Acromag Calibration System (ACS) will reliably test the Acromag thermocouple (TC) type input modules and provide a file showing the temperatures at which the modules are tested, the response rom the Acromag station, instrument data, technician data, and date and time of the test. The ACS consists of a thermocouple calibration unit (TCU), a DOS based computer, a hand held resistance temperature detector (RTD) surface probe and connects to a field installed or a bench Acromag unit.

  8. Tank monitor and control system (TMACS) revision 11 acceptance test procedure

    The purpose of this document is to describe tests performed to validate Revision 11 of the Tank Monitor and Control System (TMACS) and verify that the software functions as intended by design. This document is intended to test the software portion of TMACS. The tests will be performed on the development system. The software to be tested is the TMACS knowledge bases (KB) and the I/O driver/services. The development system will not be talking to field equipment; instead, the field equipment is simulated using emulators or multiplexers in the lab

  9. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''P''

    This Test Plan provides a test method to dedicate the leak detection relays used on the new Pumping Instrumentation and Control (PIC) skids. The new skids are fabricated on-site. The leak detection system is a safety class system per the Authorization Basis

  10. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q

    This Test Plan provides a test method to dedicate the leak detection relays used on the new Pumping Instrumentation and Control (PIC) skids. The new skids are fabricated on-site. The leak detection system is a safety class system per the Authorization Basis

  11. Feasibility of the gamma camera acceptance testing procedure introduced by the Swiss Federal Office of public health

    Like in the field of radiology, digital systems are also becoming the standard in the field of nuclear medicine. This offers not only the possibility to process, transmit and archive data from patients more easily but also to introduce quantitative measurements for quality controls. In this framework, standards concerning the qualification of gamma camera systems have been updated and appeared to be useful to set legal requirements, in spite of the fact, that this is not their goals. The aim of this study was first to choose a set of tests described in standards to define measurements to be performed at the acceptance of the systems and after the regular maintenance (at least once every six months). Reference values are then established to control the stability of the system. To verify the feasibility, from a technical and a time requirements points of view, the tests proposed for the quality assurance programme have been applied on three gamma camera systems. The results of this study show that new requirements concerning the quality assurance of gamma camera of the Swiss Federal Office of Public Health based on international standards required to slightly modify some procedures to reduce the time necessary for the acceptance and status tests. (authors)

  12. Feasibility of the gamma camera acceptance testing procedure introduced by the Swiss Federal Office of public health

    Baechler, S.; Bochud, F.; Verdun, F.R. [University Institute for Radiation Physics, Lausanne (Switzerland); Corminboeuf, F. [Klinik and Poliklinik fur Nuklearmedizin der Universitat, Inselspital, Bern (Switzerland); Linder, R.; Trueb, Ph. [Swiss Federal Office of Public Health, Bern (Switzerland); Malterre, J.; Bischof Delaloye, A. [University Hospital of Lausanne (CHUV), Nuclear Medicine Dept., Lausanne (Switzerland)

    2006-07-01

    Like in the field of radiology, digital systems are also becoming the standard in the field of nuclear medicine. This offers not only the possibility to process, transmit and archive data from patients more easily but also to introduce quantitative measurements for quality controls. In this framework, standards concerning the qualification of gamma camera systems have been updated and appeared to be useful to set legal requirements, in spite of the fact, that this is not their goals. The aim of this study was first to choose a set of tests described in standards to define measurements to be performed at the acceptance of the systems and after the regular maintenance (at least once every six months). Reference values are then established to control the stability of the system. To verify the feasibility, from a technical and a time requirements points of view, the tests proposed for the quality assurance programme have been applied on three gamma camera systems. The results of this study show that new requirements concerning the quality assurance of gamma camera of the Swiss Federal Office of Public Health based on international standards required to slightly modify some procedures to reduce the time necessary for the acceptance and status tests. (authors)

  13. Human Factors Process Task Analysis: Liquid Oxygen Pump Acceptance Test Procedure at the Advanced Technology Development Center

    Diorio, Kimberly A.; Voska, Ned (Technical Monitor)

    2002-01-01

    This viewgraph presentation provides information on Human Factors Process Failure Modes and Effects Analysis (HF PFMEA). HF PFMEA includes the following 10 steps: Describe mission; Define System; Identify human-machine; List human actions; Identify potential errors; Identify factors that effect error; Determine likelihood of error; Determine potential effects of errors; Evaluate risk; Generate solutions (manage error). The presentation also describes how this analysis was applied to a liquid oxygen pump acceptance test.

  14. Mini-DACS acceptance test report

    The attached document is the acceptance test summary report, of the mini-DACS, that was used to test the spare mixer pump for tank 241-SY-101, at the maintenance and storage facility (MASF). It includes a copy of the acceptance test procedure (ATP) and all pertaining ECNS

  15. Cone penetrometer moisture probe acceptance test report

    This Acceptance Test Report (ATR) documents the results of WHC-SD-WM-ATP-146 (Prototype Cone Penetrometer Moisture Probe Acceptance Test Procedure) and WHC-SD-WM-ATP-145 (Cone Penetrometer Moisture Probe Acceptance Test Procedure). The master copy of WHC-SD-WM-ATP-145 can be found in Appendix A and the master copy of WHC-SD-WM-ATP-146 can be found in Appendix B. Also included with this report is a matrix showing design criteria of the cone penetrometer moisture probe and the verification method used (Appendix C)

  16. Acceptance/operational test procedure 101-AW tank camera purge system and 101-AW video camera system

    This procedure will document the satisfactory operation of the 101-AW Tank Camera Purge System (CPS) and the 101-AW Video Camera System. The safety interlock which shuts down all the electronics inside the 101-AW vapor space, during loss of purge pressure, will be in place and tested to ensure reliable performance. This procedure is separated into four sections. Section 6.1 is performed in the 306 building prior to delivery to the 200 East Tank Farms and involves leak checking all fittings on the 101-AW Purge Panel for leakage using a Snoop solution and resolving the leakage. Section 7.1 verifies that PR-1, the regulator which maintains a positive pressure within the volume (cameras and pneumatic lines), is properly set. In addition the green light (PRESSURIZED) (located on the Purge Control Panel) is verified to turn on above 10 in. w.g. and after the time delay (TDR) has timed out. Section 7.2 verifies that the purge cycle functions properly, the red light (PURGE ON) comes on, and that the correct flowrate is obtained to meet the requirements of the National Fire Protection Association. Section 7.3 verifies that the pan and tilt, camera, associated controls and components operate correctly. This section also verifies that the safety interlock system operates correctly during loss of purge pressure. During the loss of purge operation the illumination of the amber light (PURGE FAILED) will be verified

  17. TMACS Test Procedure TP011: Panalarm Interface

    The TMACS Software Test Procedures translate the project's acceptance criteria into test steps. The TMACS Test Plan (WHC-SD-WM-TP-148) is fulfilled when all Test Cases are approved. This Test Procedure tests the TMACS Panalarm Interface functions

  18. L-286, Acceptance Test Record

    This document provides a detailed account of how the acceptance testing was conducted for Project L-286, ''200E Area Sanitary Water Plant Effluent Stream Reduction''. The testing of the L-286 instrumentation system was conducted under the direct supervision

  19. Nitrogen trailer acceptance test report

    This Acceptance Test Report documents compliance with the requirements of specification WHC-S-0249. The equipment was tested according to WHC-SD-WM-ATP-108 Rev.0. The equipment being tested is a portable contained nitrogen supply. The test was conducted at Norco's facility

  20. Nitrogen trailer acceptance test report

    Kostelnik, A.J.

    1996-02-12

    This Acceptance Test Report documents compliance with the requirements of specification WHC-S-0249. The equipment was tested according to WHC-SD-WM-ATP-108 Rev.0. The equipment being tested is a portable contained nitrogen supply. The test was conducted at Norco`s facility.

  1. Acceptance test procedure for the ultra high pressure bore head for use in the self-installing liquid observation well

    In order to monitor waste stored in single-shell tanks, liquid observation wells (LOWs) are installed to permit periodic insertion of instrumentation probes to evaluate the waste cross sections. An ultra high pressure water bore head, developed for installing instrument trees, was adapted for use with the LOWs. The modification facilitates the removal of the high pressure water feed system after installation. This document describes a series of tests that ensures that the design meets all the functional requirements

  2. Acceptance tests and commissioning measurements

    Following the installation of a therapy machine, be it an orthovoltage X ray unit, cobalt unit, linac or brachytherapy machine, in a radiotherapy clinic, the medical physicist must perform a series of measurements and tasks prior to placing the unit into clinical operation. These duties include acceptance testing and commissioning. Various dosimetric and radiation measuring instruments and techniques are discussed

  3. Acceptance test of LANTIS system

    Acceptance tests of radiotherapy equipment are very important. It is essential for the quality control of the equipment. Quality assurance checks for LANTIS was done during the installation and also periodically. QA involves checks for individual workstations, as well as for overall system. In modern radiotherapy centers, transferring data from one workstation to another via networking improves the quality of the treatment, reduces the errors and reduces the overall treatment time. In this hospital, Local Area Network Therapy Information system (LANTIS) from Siemens, is available for patient data transfer. Here, some of the acceptance checks carried out are presented

  4. Physics acceptance and QA procedures for IMRT

    QA program for DMLC. We distinguish between the preliminary preparations for clinical DMLC implementation (i.e., acceptance testing and commissioning), the routine QA of DMLC performance (machine QA), and the verification of patient-specific IM fields using DMLC (treatment QA). Since our initial DMLC implementation in 1995, there have been a number of incremental improvements to our overall QA program. These include methods of mechanical and dosimetric measurements, and software tools developed either by us or by the manufacturer. The use of EPID (electronic portal imaging devise), which potentially provide a more efficient, but certainly not 'cost-free' method, awaits improvements in the speed of data acquisition and in spatial resolution. Our current approach integrates existing methods, combining periodic QA and computer verification, to provide the necessary quality assurance in a safe and efficient manner. Copyright (2001) Australasian College of Physical Scientists and Engineers in Medicine

  5. TMACS Test Procedure TP002: Trending

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure tests the TMACS Trending functions

  6. TMACS Test Procedure TP009: Acromag Driver

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure tests the TMACS Acromag Software Driver (Bridge Code)

  7. TMACS Test Procedure TP007: System administration

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure tests the TMACS System Administration functions

  8. 105-KE Isolation Barrier Leak Rate Acceptance Test Report

    McCracken, K.J.

    1995-06-14

    This Acceptance Test Report (ATR) contains the completed and signed Acceptance Procedure (ATP) for the 105-KE Isolations Barrier Leak Rate Test. The Test Engineer`s log, the completed sections of the ATP in the Appendix for Repeat Testing (Appendix K), the approved WHC J-7s (Appendix H), the data logger files (Appendices T and U), and the post test calibration checks (Appendix V) are included.

  9. 105-KE Isolation Barrier Leak Rate Acceptance Test Report

    This Acceptance Test Report (ATR) contains the completed and signed Acceptance Procedure (ATP) for the 105-KE Isolations Barrier Leak Rate Test. The Test Engineer's log, the completed sections of the ATP in the Appendix for Repeat Testing (Appendix K), the approved WHC J-7s (Appendix H), the data logger files (Appendices T and U), and the post test calibration checks (Appendix V) are included

  10. Editorial: acceptance criteria and editorial procedures for Optics Letters

    Zhang, Xi-Cheng; Andersen, Peter E.; Justus, Brian L.; Galtarossa, Andrea

    2014-01-01

    Optics Letters Editors strive to provide timely reviews and decisions for authors while bringing top quality papers to the optics community. The purpose of this editorial is to explain Optics Letters' acceptance criteria and editorial procedures. Our hope is that greater transparency concerning the...... decision-making process will increase understanding as well as acceptance of our criteria and procedures....

  11. PUREX SAMCONS uninterruptible power supply (UPS) acceptance test report

    This Acceptance Test Report for the PUREX Surveillance and Monitoring and Control System (SAMCONS) Uninterruptible Power Supply (UPS) Acceptance Test Procedure validates the operation of the UPS, all alarming and display functions and the ability of the UPS to supply power to the SAMCONS as designed. The proper installation of the PUREX SAMCONS Trailer UPS components and wiring will be systematically evaluated by performance of this procedure. Proper operation of the SAMCONS computer UPS will be verified by performance of a timed functional load test, and verification of associated alarms and trouble indications. This test procedure will be performed in the SAMCONS Trailer and will include verification of receipt of alarms at the SAMCONS computer stations. This test may be performed at any time after the completion of HNF-SD-CP-ATP-083, PUREX Surveillance and Monitoring and Control System (SAMCONS) Acceptance Test Procedure, when computer display and alarm functions have been proven to operate correctly

  12. Acceptance test report for the Westinghouse 100 ton hydraulic trailer

    The SY-101 Equipment Removal System 100 Ton Hydraulic Trailer was designed and built by KAMP Systems, Inc. Performance of the Acceptance Test Procedure at KAMP's facility in Ontario, California (termed Phase 1 in this report) was interrupted by discrepancies noted with the main hydraulic cylinder. The main cylinder was removed and sent to REMCO for repair while the trailer was sent to Lampson's facility in Pasco, Washington. The Acceptance Test Procedure was modified and performance resumed at Lampson (termed Phase 2 in this report) after receipt of the repaired cylinder. At the successful conclusion of Phase 2 testing the trailer was accepted as meeting all the performance criteria specified

  13. Toddler test or procedure preparation

    Preparing toddler for test/procedure; Test/procedure preparation - toddler; Preparing for a medical test or procedure - toddler ... about the procedure to 5 or 10 minutes. Toddlers have a short attention span. Any preparation should ...

  14. SPECT: How much acceptance testing is reasonable?

    Full text: Whereas in radiology national standards for acceptance testing of medical instrumentation are available, in nuclear medicine this is not the case. This resulted in some kind of uncertainty, so that the Austrian Societies for Nuclear Medicine and for Medical Physics decided to establish a task group for developing guidelines for acceptance testing. One important item that has to be kept in mind is the fact that acceptance testing of radiological equipment has to assure the observation of prescribed limits of radiation. Otherwise there would arise the risk of increased radiation exposure of the patient. On the other hand, the aim of acceptance testing of gamma cameras is only to assure that the specifications are observed. There are no prescribed limits and there is no risk for the patient. There are two standards for defining specifications of gamma cameras: the NEMA standards and the IEC standards. Most of the manufacturers determine the specifications of their gamma cameras according to the NEMA standards, so if we want to check the specifications in the field, we have to use the same methods as the manufacturer, that is the NEMA standards. The questions are: Should we check all parameters defined in the NEMA standards? That would not be possible in the field. Which parameters should we select? In which extent and how precisely should we check? In any case, there must be a reasonable balance between time and financial effort and technical information obtained. Facing these problems our task group decided to propose the following procedure: First, we apply all tests which are called 'primary tests' in the NEMA standards: 1. Intrinsic spatial resolution 2. Intrinsic energy resolution 3. Intrinsic flood field uniformity 4. System spatial resolution without scatter 5. System alignment 6. SPECT reconstructed spatial resolution without scatter 7. Whole body system spatial resolution without scatter. All these tests are basically performed according to the

  15. Toddler test or procedure preparation

    Preparing toddler for test/procedure; Test/procedure preparation - toddler; Preparing for a medical test or procedure - toddler ... Before the test, know that your child will probably cry. Even if you prepare, your child may feel some discomfort or ...

  16. Acceptance testing of photographic film dosemeters

    The reports describes a system for acceptance testing of photographic film dosemeters in customary use in personal dosimetry. The system comprises a test of some of the fundamental dosimetric properties of the film. The acceptance test will be performed in connection with the semi-annual purchases of dosemeter film to the National Institute of Radiation Hygiene. The test program comprises both constancy tests and absolute requirements. The latter refer mainly to ISO 1757 - Personal photographic dosemeters. 2 refs

  17. Nevada Test Site Waste Acceptance Criteria (NTSWAC)

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive (LLW) and LLW Mixed Waste (MW) for disposal

  18. Nevada Test Site Waste Acceptance Criteria (NTSWAC)

    NNSA/NSO Waste Management Project

    2008-06-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive (LLW) and LLW Mixed Waste (MW) for disposal.

  19. Acceptance testing and QA in interventional cardiology

    Interventional radiology has seen rapid growth in the field of cardiology over the past decade. This growth has been facilitated by advances in imaging technology and the development of increasingly sophisticated dedicated radiological equipment. Interventional cardiology (IC) procedures are complex and may involve prolonged irradiations, which may subject patients and operators to higher levels of risk than those, which normally prevail. Currently interventional cardiology contributes over 10% to annual collective dose in the UK in spite of contributing to a total annual frequency of 0.68%. The EU Medical Exposures Directive, 97/43/Euratom, identifies interventional radiology as an area of special concern. Acceptance testing and routine quality assurance (QA) programmes are particularly important in the field of interventional cardiology given the above. The requirements for acceptance testing and QA are underpinned in the EU Medical Exposures Directive and consequent national legislation. A QA survey of 16 interventional cardiology systems in Ireland was carried out by the Department of Medical Physics and Bioengineering, St. James's Hospital, Dublin. This is the continuation of a recently published survey and represents over half of the interventional cardiology systems in Ireland including new technology digital flat panel systems and dedicated mobile equipment in trailors. Acceptance testing and QA protocols were developed and reviewed in accordance with current international and national guidelines, standards and literature. Testing included assessing the performance of the X ray tube and generator, the automatic exposure control (AEC) device in fluoroscopy and digital acquisition modes and a subjective assessment of image quality using the Leeds test objects. Radiation shielding calculations and measurements were performed to determine the structural shielding required by new installations and electrical, mechanical and general radiation safety was also

  20. Acceptance test report for core sample trucks 3 and 4

    The purpose of this Acceptance Test Report is to provide documentation for the acceptance testing of the rotary mode core sample trucks 3 and 4, designated as HO-68K-4600 and HO-68K-4647, respectively. This report conforms to the guidelines established in WHC-IP-1026, ''Engineering Practice Guidelines,'' Appendix M, ''Acceptance Test Procedures and Reports.'' Rotary mode core sample trucks 3 and 4 were based upon the design of the second core sample truck (HO-68K-4345) which was constructed to implement rotary mode sampling of the waste tanks at Hanford. Successful completion of acceptance testing on June 30, 1995 verified that all design requirements were met. This report is divided into four sections, beginning with general information. Acceptance testing was performed on trucks 3 and 4 during the months of March through June, 1995. All testing was performed at the ''Rock Slinger'' test site in the 200 West area. The sequence of testing was determined by equipment availability, and the initial revision of the Acceptance Test Procedure (ATP) was used for both trucks. Testing was directed by ICF-KH, with the support of WHC Characterization Equipment Engineering and Characterization Project Operations. Testing was completed per the ATP without discrepancies or deviations, except as noted

  1. TMACS Test Procedure TP010: Integration summary. Revision 5

    The TMACS Soft Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes

  2. Acceptance Test Plan for ANSYS Software

    This plan governs the acceptance testing of the ANSYS software (Full Mechanical Release 5.5) for use on Project Word Management Contract (PHMC) computer systems (either UNIX or Microsoft Windows/NT). There are two phases to the acceptance testing covered by this test plan: program execution in accordance with the guidance provided in installation manuals; and ensuring results of the execution are consistent with the expected physical behavior of the system being modeled

  3. Generator acceptance test and inspection report

    This Acceptance Test Report(ATR) is the completed testing and inspection of the new portable generator. The testing and inspection is to verify that the generator provided by the vendor meets the requirements of specification WHC-S-0252, Revision 2. Attached is various other documentation to support the inspection and testing

  4. DACS upgrade acceptance test report

    The DACS, which is housed in a trailer located just outside of the north fence at the SY tank farm, receives input signals from a variety of sensors located in and around the SY-101 tank. These sensors provide information such as: (1) tank vapor space and ventilation system H2 concentration; (2) tank waste temperature; (3) tank pressure; (4) waste density; (5) operating pump parameters such as speed, flow, rotational position, discharge pressure, and internal temperature; (6) strain (for major equipment); and (7) waste level. The output of these sensors is conditioned and transmitted to the DACS computers where these signals are displayed, recorded, and monitored for out-of-specification conditions. If abnormal conditions are detected, then, in certain situations, the DACS automatically generates alarms and causes the system to abort pump operations. The report documents testing performed per WHC-SD-WM-ATP-082. Rev. 0-13

  5. Acceptance test report, plutonium finishing plant life safety upgrade

    Hodge, S.G.

    1994-12-02

    This acceptance Test Procedure (ATP) has been prepared to demonstrate that modifications to the Fir Protection systems function as required by project criteria. The ATP will test the Fire Alarm Control Panels, Flow Alarm Pressure Switch, Heat Detectors, Smoke Detectors, Flow Switches, Manual Pull Stations, and Gong/Door By Pass Switches.

  6. Acceptance testing protocol for magnetic resonance imaging systems

    Objective: to develop an acceptance testing protocol for magnetic resonance imaging systems and to show which and how phantoms could be used to collect data. Materials and methods: the definition, procedure, analysis and the acceptation criteria were created for each of 15 selected tests. Results: These tests allow the evaluation of technical specifications stated on the manufacturer's sales proposal and to establish reference values to be used in subsequent constancy tests. Conclusion: future quality assurance programs in magnetic resonance imaging should consider employing tests similar or equal to the ones described in this paper. (author)

  7. Acceptance test report for the AY-102 ENRAF densitometer

    On February 11, 1998, the AY-1 02, Riser 15E ENRAF Densitometer was acceptance tested per HNF-SD-WM-ATP-077. The test was performed at the Department of Energy's Hanford Site, 200 East Area, building MO-407. The test validated the functionality of the Densitometer for use by project W-320, C-1 06 Retrieval. The purpose of the test procedure was to verify the functionality of the ENRAF Series 854 ATG densitometer. Typically, all ENRAF Series 854 ATGs are acceptance tested before transport to the field. The ATP, as performed for level gauges, sets default program values within the gauge and verifies the gauge's force transducer calibration

  8. W-026, acceptance test report LLW supercompactor (submittal number 567)

    The purpose of this acceptance test report was to verify the assembly is correct and complete and meets all the specification and performance requirements. On May 15--16, 1996, the LLW Supercompactor functional demonstrations and performance tests were carried out. These tests were carried out in accordance with the Acceptance Test Procedure, submittal 565, dated 5/3/96. The tests were performed by Herman Miller and Gene Rice of INET Corporation and Richard Lawrence and other PCL personnel. The VIHC representative on May 15, 1996 was Doug Dunlap and on May 16, 1996 the representative was Ken Leist

  9. Gas characterization system software acceptance test report

    This document details the results of software acceptance testing of gas characterization systems. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases

  10. Acceptance tests of a new gamma camera

    For best patient service, a QA programme is needed to produce quantitative/qualitative data and keep records of the results and equipment faults. Gamma cameras must be checked against the manufacturer's specifications.The service manual is usually useful to achieve this goal. Acceptance tests are very important not only to accept a new gamma camera system for routine clinical use but also to have a role in a reference for future measurements. In this study, acceptance tests were performed for a new gamma camera in our department. It is a General Electric MG system with two detectors, two collimators. They are low energy general purpose (LEGP) and medium energy general purpose (MEGP). All intrinsic calibrations and corrections were done by the service engineer at installation (PM tune, dynamic correction, energy calibration, geometric calibration, energy correction, linearity correction and second order corrections).After installation, calibrations and corrections, a close physical inspection of the mechanical and electrical safety aspects of the cameras were done by the responsible physicist of the department. The planar system is based on measurement of system uniformity, resolution/linearity and multiple window spatial registration. All test procedures were performed according to NEMA procedures developed by the manufacturer. Intrinsic uniformity: NEMA uniformity was done first by using service manual and then other isotope uniformities were acquired with 99mTc, 131I, 201Tl and 67Ga. They were evaluated qualitatively and quantitatively, but non-uniformities were observed, especially for detector II, The service engineers repeated all tests and made necessary corrections. We repeated all the intrinsic uniformity tests. 99mTc intrinsic images were also performed at 'no correction', 'no energy correction', 'no linearity correction', 'all correction' and '±10% off peak', and compared. Extrinsic uniformity: At the beginning, collimators were checked for defects

  11. Conditions for acceptance and usage of mobile payment procedures

    Pousttchi, Key

    2003-01-01

    Mobile payment (MP) is crucial for, but not limited to mobile commerce. The key to mobile payment acceptance is in the hands of customers. In this paper we examine the conditions for acceptance and actual usage of MP procedures by the customer. We identify essential conditions which belong to the categories costs, security and convenience. Different preferences lead to an individual set of essential conditions for any single user. We propose a scheme for their representation and comparison an...

  12. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA

    This document establishes the U. S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive and mixed waste for disposal. Mixed waste generated within the State of Nevada by NNSA/NSO activities is accepted for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the Nevada Test Site Area 3 and Area 5 Radioactive Waste Management Site for storage or disposal

  13. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA

    U.S. DEPARTMENT OF ENERGY, NATIONAL NUCLEAR SECURITY ADMINISTRATION, NEVADA SITE OFFICE

    2005-07-01

    This document establishes the U. S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive and mixed waste for disposal. Mixed waste generated within the State of Nevada by NNSA/NSO activities is accepted for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the Nevada Test Site Area 3 and Area 5 Radioactive Waste Management Site for storage or disposal.

  14. Automated Acceptance Testing : Why and How to Implement?

    Muroma, Sebastian

    2015-01-01

    The goal of this thesis was to investigate why manual acceptance tests should be automated in a software project and how the automation should be carried out. The topic is of relevance because automated testing is one way to improve the quality of software. Different methods, procedures, types and tools can be used to create automated testing. The challenges of automated testing are implementation, setting the right objectives and choosing the right tool. The benef...

  15. Procedural justice in children: Preschoolers accept unequal resource distributions if the procedure provides equal opportunities.

    Grocke, Patricia; Rossano, Federico; Tomasello, Michael

    2015-12-01

    When it is not possible to distribute resources equitably to everyone, people look for an equitable or just procedure. In the current study, we investigated young children's sense of procedural justice. We tested 32 triads of 5-year-olds in a new resource allocation game. Triads were confronted with three unequal reward packages and then agreed on a procedure to allocate them among themselves. To allocate the rewards, they needed to use a "wheel of fortune." Half of the groups played with a fair wheel (where each child had an equal chance of obtaining each reward package), and the other half played with an unfair wheel. We analyzed children's interactions when using the wheel and conducted an interview with each child after the game was over. Children using the unfair wheel often decided to change the rules of the game, and they also rated it as an unfair procedure in the interview. In contrast, children who played with the fair wheel were mostly accepting of both the outcome and the procedure. Overall, we found that children as young as preschool age are already sensitive not only to distributive justice but to procedural justice as well. PMID:26255603

  16. First experiences with acceptance testing of multiple head SPECT cameras

    User acceptance testing of newly installed gamma cameras is mandatory in order to verify manufacturers' specifications and to ensure optimal image quality. Acceptance test procedures are widely standardized today and are carried out following commonly accepted test protocols. Two new triple head gamma cameras have been installed during the last year at the Department of Nuclear Medicine of the Vienna University Hospital. For acceptance testing of these cameras a modified and expanded version of the commonly used test protocol for single head SPECT systems has been employed. Details of the tests that have been carried out and a comparison of the results obtained for both cameras are presented. Furthermore, some specific problems that are encountered during acceptance testing of multiple head systems are discussed. In particular it has been noted that some important tests of intrinsic camera parameters cannot be carried out, which makes a complete verification of vendors' specifications impossible. In spite of these problems the acceptance test system for multiple head cameras presented in this work was sufficient for establishing proper working conditions for clinical use. (authors)

  17. W-026, transuranic waste (TRU) glovebox acceptance test report

    Leist, K.J.

    1998-03-11

    On July 18, 1997, the Transuranic (TRU) glovebox was tested using glovebox acceptance test procedure 13021A-86. The primary focus of the glovebox acceptance test was to examine control system interlocks, display menus, alarms, and operator messages. Limited mechanical testing involving the drum ports, hoists, drum lifter, compacted drum lifter, drum tipper, transfer car, conveyors, sorting table, lidder/delidder device and the TRU empty drum compactor were also conducted. As of February 25, 1998, 10 of the 102 test exceptions that affect the TRU glovebox remain open. These items will be tracked and closed via the WRAP Master Test Exception Database. As part of Test Exception resolution/closure the responsible individual closing the Test Exception performs a retest of the affected item(s) to ensure the identified deficiency is corrected, and, or to test items not previously available to support testing. Test exceptions are provided as appendices to this report.

  18. WRAP low level waste (LLW) glovebox acceptance test report

    Leist, K.J.

    1998-02-17

    In June 28, 1997, the Low Level Waste (LLW) glovebox was tested using glovebox acceptance test procedure 13031A-85. The primary focus of the glovebox acceptance test was to examine control system interlocks, display menus, alarms, and operator messages. Limited mechanical testing involving the drum ports, hoists, drum lifter, compacted drum lifter, drum tipper, transfer car, conveyors, lidder/delidder device and the supercompactor were also conducted. As of November 24, 1997, 2 of the 131 test exceptions that affect the LLW glovebox remain open. These items will be tracked and closed via the WRAP Master Test Exception Database. As part of Test Exception resolution/closure the responsible individual closing the Test Exception performs a retest of the affected item(s) to ensure the identified deficiency is corrected, and, or to test items not previously available to support testing. Test Exceptions are provided as appendices to this report.

  19. W-026, transuranic waste (TRU) glovebox acceptance test report

    On July 18, 1997, the Transuranic (TRU) glovebox was tested using glovebox acceptance test procedure 13021A-86. The primary focus of the glovebox acceptance test was to examine control system interlocks, display menus, alarms, and operator messages. Limited mechanical testing involving the drum ports, hoists, drum lifter, compacted drum lifter, drum tipper, transfer car, conveyors, sorting table, lidder/delidder device and the TRU empty drum compactor were also conducted. As of February 25, 1998, 10 of the 102 test exceptions that affect the TRU glovebox remain open. These items will be tracked and closed via the WRAP Master Test Exception Database. As part of Test Exception resolution/closure the responsible individual closing the Test Exception performs a retest of the affected item(s) to ensure the identified deficiency is corrected, and, or to test items not previously available to support testing. Test exceptions are provided as appendices to this report

  20. WRAP low level waste (LLW) glovebox acceptance test report

    In June 28, 1997, the Low Level Waste (LLW) glovebox was tested using glovebox acceptance test procedure 13031A-85. The primary focus of the glovebox acceptance test was to examine control system interlocks, display menus, alarms, and operator messages. Limited mechanical testing involving the drum ports, hoists, drum lifter, compacted drum lifter, drum tipper, transfer car, conveyors, lidder/delidder device and the supercompactor were also conducted. As of November 24, 1997, 2 of the 131 test exceptions that affect the LLW glovebox remain open. These items will be tracked and closed via the WRAP Master Test Exception Database. As part of Test Exception resolution/closure the responsible individual closing the Test Exception performs a retest of the affected item(s) to ensure the identified deficiency is corrected, and, or to test items not previously available to support testing. Test Exceptions are provided as appendices to this report

  1. Breathing air trailer acceptance test report

    This Acceptance Test Report documents compliance with the requirements of specification WHC-S-0251, Rev.0 and ECNs 613530 and 606113. The equipment was tested according to WHC-SD-WM-ATP-104. The equipment tested is a Breathing Air Supply Trailer purchased as a design and fabrication procurement activity. The ATP was written by the Seller and was performed by the Seller with representatives of the Westinghouse Hanford Company witnessing portions of the test at the Seller's location

  2. Acceptance test report: Backup power system

    Acceptance Test Report for construction functional testing of Project W-030 Backup Power System. Project W-030 provides a ventilation upgrade for the four Aging Waste Facility tanks. Backup power includes a single 125 KW diesel generator, three 10-kva uninterruptible power supply units, and all necessary control

  3. Customer Acceptance Procedure for Clinac (21EX-Platinum)

    For qualify improvement in radiotherapy, it is important to set up and evaluate equipment (linac) accurately. In addition, technicians are needed to be fully aware of the equipment's detailed quality and its manual. Therefore, the result of ATP is evaluated and introduced, in order that the technicians are skilled by participating in quality assurance (QA) and understanding the quality of the equipment before clinical use. QA for LINAC 21EX (Varian, US) was done with suppliers its procedure was divided into radiation survey, mechanical test, radiation isocenter test, bean performance, dosimetry, and enhanced dynamic wedge and using X-omat film (Kodak), multidata, densitometer, and electrometer. QA of MLC (Millennium, 120 leaf) attached to LINAC and EPID (Portal vision) were done separately. The leakage dose by survey meter was below the tolerance. In mechanical test, collimater, gantry, and couch rotation were less than 1 mm, and the angles were ±0.1 degree for digital and ±0.5 degree for mechanical. The alignment test of the light field and crosshair were evaluated less than 1 mm. The (a)symmetrical jaw field was less than ±0.5 mm. The radiation isocenter test using X-mat film was less than 1 mm. The consistency of light field and radiation field was less than ±0.1 mm. PDD for photon energy was less than ±1% and for electron energy of 90%, 80%, 50%, and 30% were evaluated within the tolerance. Flatness for photon and electron energy was evaluated 2.3% (tolerance 3%) and 3% (tolerance 4.5%), respectively, and symmetry was 0.45% (tolerance 2%) and 0.3% (tolerance 2%), respectively. Dosimetry test for short term, MU setting, rep rate, and dose rate accuracy of photon and electron energy was within the tolerance depending on energy, MU, and gantry angle. Accuracy and safety for clinical use of Clinac 21EX was verified through customer acceptance procedure and the quality of the equipment was found out. These can reduce the difficulties in using the equipment

  4. Initial acceptance test experience with FFTF plant equipment

    The purpose of this paper is to examine the initial acceptance test experience of certain pieces of auxiliary equipment of the Fast Flux Test Facility (FFTF). The scope focuses on the DHX blowers and drive train, inert gas blowers, H and V containment isolation valves, and the Surveillance and In-service Inspection (SISI) transporter and trolley. For each type of equipment, the discussion includes a summary of the design and system function, installation history, preoperational acceptance testing procedures and results, and unusual events and resolutions

  5. Acceptance testing of fluoroscopy systems used for interventional purposes

    This study presents the results of acceptance testing on 18 interventional fluoroscopy systems in Ireland. Acceptance testing and routine quality assurance (QA) of X-ray systems are the requirements of the EU Medical Exposures Directive (MED) and these requirements were subsequently implemented into Irish legislation. The MED states that special consideration should be given to the QA and dose assessment of high dose procedures such as interventional fluoroscopy. Owing to the advances in fluoroscopy technology, it has been found that comprehensive testing of interventional systems proves challenging in a busy hospital environment. A number of recurrent problems have been identified and are presented. (authors)

  6. TMACS Test Procedure TP008: SACS Interface. Revision 5

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure tests the TMACS SACS Interface functions

  7. TMACS test procedure TP009: Acromag driver. Revision 5

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addresses the testing of the functionality of the TMACS Acromag driver software in conjunction with a new bridge for the Panalarm Annunciator system

  8. User Acceptance of YouTube for Procedural Learning: An Extension of the Technology Acceptance Model

    Lee, Doo Young; Lehto, Mark R.

    2013-01-01

    The present study was framed using the Technology Acceptance Model (TAM) to identify determinants affecting behavioral intention to use YouTube. Most importantly, this research emphasizes the motives for using YouTube, which is notable given its extrinsic task goal of being used for procedural learning tasks. Our conceptual framework included two…

  9. AZ-101 Mixer Pump Test Qualification Test Procedures (QTP)

    Describes the Qualification test procedure for the AZ-101 Mixer Pump Data Acquisition System (DAS). The purpose of this Qualification Test Procedure (QTP) is to confirm that the AZ-101 Mixer Pump System has been properly programmed and hardware configured correctly. This QTP will test the software setpoints for the alarms and also check the wiring configuration from the SIMcart to the HMI. An Acceptance Test Procedure (ATP), similar to this QTP will be performed to test field devices and connections from the field

  10. GERDA phase II detectors and acceptance tests

    The GERDA collaboration aims at searching for the neutrinoless double beta decay of 76Ge into 76Se. It uses enriched Ge detectors that are operated in liquid argon. Phase I of the experiment started with a target mass of approximately 20 kg on November 1, 2011, and it will last for 1 year. Phase II is in preparation and envisions the installation of at least 25 new Broad Energy Ge detectors (BEGe) that will increase the target mass by nearly 20 kg. These detectors, however, have to be extensively tested prior to their usage. The talk briefly reviews the preparation of the detector screening campaign and focuses on the corresponding acceptance test strategy. The tests include energy resolution and leakage current measurements, dead layer and active volume determination, as well as the pulse shape discrimination efficiencies of the detectors. Finally we present results obtained with depleted BEGe detectors that are used for the optimization of the enriched ones during the acceptance tests.

  11. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal

  12. Nevada Test Site Waste Acceptance Criteria

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal

  13. Nevada Test Site Waste Acceptance Criteria

    U. S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2005-10-01

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal.

  14. Acceptance Testing Of Web Applications With Test Description Language

    Łukasz Olek; Bartosz Alchimowicz; Jerzy Nawrocki

    2014-01-01

    Acceptance tests are usually created by a client after a part of a system is implemented. However, some methodologies propose the elaboration of test cases before implementing a system. This approach increases the probability of system implementation that fulfills requirements, but may be problematic for customers and testers. To allow acceptance testing in such conditions, we propose to define test cases by recording them on an interactive mockup (a low detailed user-interface prototype). Th...

  15. Tests and Procedures

    ... procedure is being done. How the results will influence treatment. What your child will experience during the ... Understanding Children’s Cancer About Cancer What is Cancer? Childhood Cancer Statistics Childhood Cancer Statistics Overview Number of ...

  16. Specification and acceptance testing of radiotherapy treatment planning systems

    Quality assurance (QA) in the radiation therapy treatment planning process is essential to ensure accurate dose delivery to the patient and to minimize the possibility of accidental exposure. The computerized radiotherapy treatment planning systems (RTPSs) are now widely available in industrialized and developing countries and it is of special importance to support hospitals in Member States in developing procedures for acceptance testing, commissioning and QA of their RTPSs. Responding to these needs, a group of experts developed an IAEA publication with such recommendations, which was published in 2004 as IAEA Technical Reports Series No. 430. This report provides a general framework and describes a large number of tests and procedures that should be considered by the users of new RTPSs. However, small hospitals with limited resources or large hospitals with high patient load and limited staff are not always able to perform complete characterization, validation and software testing of algorithms used in RTPSs. Therefore, the IAEA proposed more specific guidelines that provide a step-by-step recommendation for users at hospitals or cancer centres how to implement acceptance and commissioning procedures for newly purchased RTPSs. The current publication was developed in the framework of the Coordinated Research Project on Development of Procedures for Quality Assurance for Dosimetry Calculations in Radiotherapy and uses the International Electrotechnical Commission (IEC) standard IEC 62083, Requirements for the Safety of Radiotherapy Treatment Planning Systems as its basis. The report addresses the procedures for specification and acceptance testing of RTPSs to be used by both manufacturers and users at the hospitals. Recommendations are provided for specific tests to be performed at the manufacturing facility known as type tests, and for acceptance tests to be performed at the hospital known as site tests. The purpose of acceptance testing is to demonstrate to the

  17. W-026, acceptance test report manipulator system

    Watson, T.L.

    1997-04-15

    The purpose of the WRAP Manipulator System Acceptance Test Plan (ATP) is to verify that the 4 glovebox sets of WRAP manipulator components, including rail/carriage, slave arm, master controller and auxiliary equipment, meets the requirements of the functional segments of 14590 specification. The demonstration of performance elements of the ATP are performed as a part of the Assembly specifications. Manipulator integration is integrated in the performance testing of the gloveboxes. Each requirement of the Assembly specification will be carried out in conjunction with glovebox performance tests.

  18. 105K West Isolation Barrier Acceptance Test results

    The objective of this document is to report and interpret the findings of the isolation barrier acceptance tests performed in 105KW/100K. The tests were performed in accordance with the test plan and acceptance test procedure. The test report contains the test data. This document compares the test data against the criteria. A discussion of the leak rate analytical characterization describes how the flow characteristics flow rate will be determined using the test data from the test report. Two modes of water loss were considered; basin and/or discharge chute leakage, and evaporation. An initial test established baseline leakage data and instrumentation performance. Test 2 evaluated the sealing performance of the isolation barrier by inducing an 11 in. (27.9 cm) level differential across the barrier. The leak rate at this 11 in. (27.9 cm) level is extrapolated to the 16 ft. (4.9 m) level differential postulated in the DBE post seismic event. If the leak rate, adjusted for evaporation and basin leakage (determined from Test 1), is less than the SAR limit of 1,500 gph (5,680 lph) at a 16 ft (4.9 m) level differential, the barriers pass the acceptance test

  19. Acceptance Testing Of Web Applications With Test Description Language

    Łukasz Olek

    2014-01-01

    Full Text Available Acceptance tests are usually created by a client after a part of a system is implemented. However, some methodologies propose the elaboration of test cases before implementing a system. This approach increases the probability of system implementation that fulfills requirements, but may be problematic for customers and testers. To allow acceptance testing in such conditions, we propose to define test cases by recording them on an interactive mockup (a low detailed user-interface prototype. The paper focuses on Test Description Language, a notation used to store test cases.

  20. Acceptance test report: Field test of mixer pump for 241-AN-107 caustic addition project

    The field acceptance test of a 75 HP mixer pump (Hazleton serial number N-20801) installed in Tank 241-AN-107 was conducted from October 1995 thru February 1996. The objectives defined in the acceptance test were successfully met, with two exceptions recorded. The acceptance test encompassed field verification of mixer pump turntable rotation set-up and operation, verification that the pump instrumentation functions within established limits, facilitation of baseline data collection from the mixer pump mounted ultrasonic instrumentation, verification of mixer pump water flush system operation and validation of a procedure for its operation, and several brief test runs (bump) of the mixer pump

  1. TMACS test procedure TP010: Integration summary. Revision 6

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure verifies that Test Procedures 1, 2, 3, 5 and 9 (WHC-SD-WM-TRP-105, 106, 107, 109 and 113) of TMACS Software Release 4.1 have been successfully completed

  2. Project W-049H Collection System Acceptance Test

    The Acceptance Test Procedure (ATP) Program for Project W-049H covers the following activities: Disposal system, Collection system, Instrumentation and control system. Each activity has its own ATP. The purpose of the ATPs is to verify that the systems have been constructed in accordance with the construction documents and to demonstrate that the systems function as required by the Project criteria. This ATP has been prepared to demonstrate that the Collection System Instrumentation functions as required by project criteria

  3. Nevada test site waste acceptance criteria

    This document provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the NTS. Review each section of this document. This document is not intended to include all of the requirements; rather, it is meant as a guide toward meeting the regulations. All references in this document should be observed to avoid omission of requirements on which acceptance or rejection of waste will be based. The Department of Energy/Nevada Operations Office (DOE/NV) and support contractors are available to assist you in understanding or interpreting this document

  4. Payload test philosophy. [JPL views on qualification/acceptance testing

    Gindorf, T.

    1979-01-01

    The general philosophy of how JPL views payload qualification/acceptance testing for programs that are done either in-house or by contractors is described. Particular attention is given to mission risk classifications, preliminary critical design reviews, environmental design requirements, the thermal and dynamics development tests, and the flight spacecraft system test.

  5. Acceptance Test Plan for Fourth-Generation Corrosion Monitoring Cabinet

    This Acceptance Test Plan (ATP) will document the satisfactory operation of the third-generation corrosion monitoring cabinet (Hiline Engineering Part No.0004-CHM-072-C01). This ATP will be performed by the manufacturer of the cabinet prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion monitoring cabinet. The test will consist of a continuity test of the cabinet wiring from the end of cable to be connected to corrosion probe, through the appropriate intrinsic safety barriers and out to the 15 pin D-shell connectors to be connected to the corrosion monitoring instrument. Additional testing will be performed using a constant current and voltage source provided by the corrosion monitoring hardware manufacturer to verify proper operation of corrosion monitoring instrumentation

  6. 242A Distributed Control System Year 2000 Acceptance Test Report

    This report documents acceptance test results for the 242-A Evaporator distributive control system upgrade to D/3 version 9.0-2 for year 2000 compliance. This report documents the test results obtained by acceptance testing as directed by procedure HNF-2695. This verification procedure will document the initial testing and evaluation of the potential 242-A Distributed Control System (DCS) operating difficulties across the year 2000 boundary and the calendar adjustments needed for the leap year. Baseline system performance data will be recorded using current, as-is operating system software. Data will also be collected for operating system software that has been modified to correct year 2000 problems. This verification procedure is intended to be generic such that it may be performed on any D/3(trademark) (GSE Process Solutions, Inc.) distributed control system that runs with the VMSTM (Digital Equipment Corporation) operating system. This test may be run on simulation or production systems depending upon facility status. On production systems, DCS outages will occur nine times throughout performance of the test. These outages are expected to last about 10 minutes each

  7. Acceptance Test Report for the 241-AZ-101 Ultrasonic Interface Level Analyzer

    This document comprises the Acceptance Test Report for the 241-AZ-101 Ultrasonic Interface Level Analyzer. This document presents the results of Acceptance Testing of the 241-AZ-101 Ultrasonic Interface Level Analyzers (URSILLAs). Testing of the URSILLAs was performed in accordance with ATP-260-001, ''URSILLA Pre-installation Acceptance Test Procedure''. The objective of the testing was to verify that all equipment and components function in accordance with design specifications and original equipment manufacturer's specifications

  8. Acceptance Test Report for 241-U compressed air system

    This Acceptance Test Report (ATR) documents the results of acceptance testing of a newly upgraded compressed air system at 241-U Farm. The system was installed and the test successfully performed under work package 2W-92-01027

  9. MITG test procedure and results

    Elements and modules for Radioisotope Thermoelectric Generator have been performance tested since the inception of the RTG program. These test articles seldom resembled flight hardware and often lacked adequate diagnostic instrumentation. Because of this, performance problems were not identified in the early stage of program development. The lack of test data in an unexpected area often hampered the development of a problem solution. A procedure for conducting the MITG Test was developed in an effort to obtain data in a systematic, unambiguous manner. This procedure required the development of extensive data acquisition software and test automation. The development of a facility to implement the test procedure, the facility hardware and software requirements, and the results of the MITG testing are the subject of this paper

  10. System turnover and acceptance procedure of Qingshan NPP

    Turnover and acceptance process of nuclear power plant has direct influence on construction scheduling. The authors describe organization, conditions and implementation of system turnover and acceptance. The paper also gives some suggestions as reference of turnover and acceptance work

  11. TMACS test procedure TP004: Reporting. Revision 4

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addressed the report generation capability of the TMACS. The features to be tested are generation of the alarm history report, equipment failure report, single-shell tank report and double-shell tank report

  12. TMACS test procedure TP003: Graphics. Revision 6

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addresses the graphics requirements of the TMACS. The features to be tested are the data display graphics and the graphic elements that provide for operator control and selection of displays

  13. TMACS test procedure TP001: Alarm management. Revision 6

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addresses the Alarm Management requirements of the TMACS. The features to be tested are: real-time alarming on high and low level and discrete alarms, equipment alarms, dead-band filtering, alarm display color coding, alarm acknowledgement, and alarm logging

  14. TMACS test procedure TP003: Graphics. Revision 5

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addresses the graphics requirements of the TMACS. The features to be tested are the data display graphics and the graphic elements that provide for operator control and selection of displays

  15. Acceptance Test Report for the 241-AN-107 Enraf Advanced Technology Gauges

    This Acceptance Test Report covers the results of the execution of the Acceptance Test Procedure for the 241-AN-107 Enraf Advanced Technology Gauges. The test verified the proper operation of the gauges to measure waste density and level in the 241-AN-107 tank

  16. Acceptance Test Report for the 241-AN-107 Enraf Advanced Technology Gauges

    Dowell, J.L.; Enderlin, V.R.

    1995-06-01

    This Acceptance Test Report covers the results of the execution of the Acceptance Test Procedure for the 241-AN-107 Enraf Advanced Technology Gauges. The test verified the proper operation of the gauges to measure waste density and level in the 241-AN-107 tank.

  17. Special diagnostic tests and procedures

    The purpose of this article is to provide the physical therapist with a clinically useful description of diagnostic tests commonly used for patients in cardiac rehabilitation. I reviewed five diagnostic tests: coronary angiography, thallium 201 myocardial perfusion imaging, radionuclide ventriculography, echocardiography, and Holter monitoring. The procedural techniques, indications, diagnostic capabilities, limitations, and comparisons of these tests are discussed. I present the applicability of these tests relative to the therapist's roles as clinician, educator, and cardiac rehabilitation team member. 84 references

  18. Swiss requirements concerning gamma camera acceptance and status testing

    Like in the field of radiology, digital systems are also becoming the standard in the field of nuclear medicine. This offers not only the possibility to process, transmit and archive data from patients more easily but also to introduce quantitative measurements for quality controls. In this framework standards concerning the qualification of gamma camera systems have been updated and appeared to be useful to set legal requirements, in spite of the fact that this is not their goal. The aim of this study was first to choose a set of tests described in standards to define measurements to be performed at the acceptance of the systems, after the regular maintenances (at least once every six months; status test) and for assuring the stability of the systems. To verify the feasibility, from the point of view of technical and a time requirements, the quality assurance programme proposed has been applied on three gamma camera systems. The results of this study show that, based on international standards, new requirements concerning the quality assurance of the gamma camera of the Swiss Public Health Authority make it necessary to slightly modify some procedures to reduce the time required for the acceptance and status tests. In the Ordinance related to the use of unsealed radioactive sources (November 1997) the Swiss Public Health Authority requires the supplier to carry out a reception test on all imaging devices used in the field of nuclear medicine before they can be used on patients. Moreover, a maintenance procedure of the imaging device has to be performed at least every six months by properly trained staff. This maintenance has to be followed by a status test that assures the integrity of the system before it can be used for further clinical applications. Daily and weekly stability tests, under the responsibility of the users of the system, are also defined. According to the Swiss Ordinance, all the measurements required for the acceptance and status tests should

  19. Acceptance test report for ENRAF control panel software

    On March 5, 1998, the ENRAF Control Panel Software program was acceptance tested per HNF-1991 Revision 0. The test was performed at the Department of Energy's Hanford Site, 200 West Area, building MO-281. The test validated the functionality of the software for use by project W-320, C-1 06 Retrieval. The purpose of the test procedure was to partially verify the functionality of the ENRAF Control Panel Software. The test cycled through the majority of functions within the program. Functions not tested will be tested per Operational Test Procedure OTP-320-01 0 at a later date. The following criteria was used to determine whether the software passed or failed the test. The gauge responds correctly (as described in vendor documentation, Reference 1) to all commands sent through the program. If gauge related error codes are encountered, they may be cleared either through the PET or the program. However, the program, while running, must provide some indication of all gauge related errors encountered. If any of the pass criteria are not met and cannot be immediately resolved. If the system crashes for reasons that are clearly related to program performance and cannot be immediately resolved

  20. Acceptance-test specifications for Test Number Four: process sensor and display test

    This document provides the general instructions for performing acceptance Test Number Four as indicated in the Acceptance Test Index (TI-022-130-003). Also indicated are the plant conditions and special equipment required to conduct the test. The acceptance criteria for each portion of the test are specified

  1. Acceptance testing and QA in dental radiology

    The HPA (UK) reported in 2002 that although the effective dose from dental examinations is low, dental imaging is the most frequent type of X ray examination undertaken (approx. 30%); a similar situation is likely to exist in Ireland. It is most likely that this will increase further in the future as the dental X ray technology moves from film to digital equipment. Dental X rays are taken more frequently with digital equipment than film based technology. The Department of Medical Physics and Bioengineering, St. James's Hospital, Dublin is particularly interested in the area of dental quality assurance (QA) as a result of a significant medical radiation safety incident in Ireland occurring with a faulty dental X ray installation. The implementation of a QA programme in Ireland has been enforced not only by the publication of the Dental Code of Practice by the Irish Regulatory Authority in the 1990s but also by the publication of the European Medical Exposures Directive. The current QA programme, which includes site visits in order to perform acceptance testing and routine QA checks on dental X ray equipment has been implemented in approximately 250 dental health centres to which the Department has provided radiation protection advisory services for approximately twenty years. In addition to the technical evaluation of the equipment, an assessment of the adequacy of the shielding in the X ray room and of the radiation protection facilities is performed. This paper identifies the findings from the dental radiology QA assessments. QA test protocols were developed in accordance with current national and internationally accepted guidelines. The tests include exposure time and kVp accuracy, radiation output consistency, filtration, irradiated field size, mechanical and electrical safety checks and measurement of tube output for specific X ray examinations to aid in the establishment of a national diagnostic reference levels, a requirement of the Medical Exposures

  2. Inspection system performance test procedure

    This procedure establishes requirements to administer a performance demonstration test. The test is to demonstrate that the double-shell tank inspection system (DSTIS) supplied by the contractor performs in accordance with the WHC-S-4108, Double-Shell Tank Ultrasonic Inspection Performance Specification, Rev. 2-A, January, 1995. The inspection system is intended to provide ultrasonic (UT) and visual data to determine integrity of the Westinghouse Hanford Company (WHC) site underground waste tanks. The robotic inspection system consists of the following major sub-systems (modules) and components: Mobile control center; Deployment module; Cable management assembly; Robot mechanism; Ultrasonic testing system; Visual testing system; Pneumatic system; Electrical system; and Control system

  3. The Murmansk Initiative - RF: Acceptance Testing

    Czajkowski, C.; Wester, D. W.; Dyer, R. S.; Soerlie, A. A.; Moller, B.; Barnes, E.

    2002-02-26

    The Murmansk Initiative-RF (MI) was conceived to provide the Russian Federation (RF) with the capacity to manage low-level liquid radioactive waste (LLRW) and comply with the requirements of the London Convention that prohibit ocean dumping. The trilateral project among Norway, the RF, and the United States of America (U.S.) began in 1994 and was the first to utilize exclusively Russian subcontractors to upgrade and expand an existing LLRW treatment plant on the premises of RTP Atomflot in Murmansk, Russia. The project moved quickly through the design phase. Progress during the construction phase was somewhat slower because of difficulties with acquisition of hardware, inexperience with automated instrumentation and control equipment, and unexpected design changes in the cementation unit. The project advanced into the test-operation phase, which is currently underway, in June 2001. Initial runs with liquid waste have revealed that procedures for unloading spent ion-exchange sorbents could be improved and that sludges formed during removal of alkaline-earth metals should be compacted in order for the facility to operate at its full potential. Resolution of these issues is expected within the next few months.

  4. Acceptance test plan for fourth generation Hanford corrosion monitoring system

    This Acceptance Test Plan (ATP) will document the satisfactory operation of the corrosion probe cabinets destined for installation on tanks 241-AN-102 and 241-AN-107. This ATP will be performed by the manufacturer on each cabinet prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion monitoring cabinets to be installed on tanks 241-AN-102 and 241-AN-107. One cabinet will be installed on each tank. Each cabinet will contain corrosion monitoring hardware to be connected to existing corrosion probes already installed in each tank. The test will consist of a continuity test of the cabinet wiring from the end of cable to be connected to corrosion probe, through the appropriate intrinsic safety barriers and out to the 15 pin D-shell connectors to be connected to the corrosion monitoring instrument. Additional testing will be performed using a constant current and voltage source provided by the corrosion monitoring hardware manufacturer to verify proper operation of corrosion monitoring instrumentation (input a known signal and see if the instrumentation records the proper value)

  5. Acceptance Test Report for Fourth Generation Hanford Corrosion Monitoring System

    This Acceptance Test Report (ATR) will document the satisfactory operation of the corrosion probe cabinets destined for installation on tanks 241-AN-102 and 241-AN-107. This ATR will be performed by the manufacturer on each cabinet prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion monitoring cabinets to be installed on tanks 241-AN-102 and 241-AN-107. One cabinet will be installed on each tank. Each cabinet will contain corrosion monitoring hardware to be connected to existing corrosion probes already installed in each tank. The test will consist of a continuity test of the cabinet wiring from the end of cable to be connected to corrosion probe, through the appropriate intrinsic safety barriers and out to the 15 pin D-shell connectors to be connected to the corrosion monitoring instrument. Additional testing will be performed using a constant current and voltage source provided by the corrosion monitoring hardware manufacturer to verify proper operation of corrosion monitoring instrumentation (input a known signal and see if the instrumentation records the proper value)

  6. TMACS Test Procedure TP005: Sensor configuration, logging, and data conversion

    The TMACS Software Project Test Procedures translate the projects acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes

  7. On acceptance criteria for Mochovce startup physical tests

    Paper is focused on new acceptance criteria for physical startup tests of Mochovce Units 1, 2. The acceptance criteria are discussed at the stage of their development. The acceptance criteria determination is based on statistical processing of differences between the experimental and theoretical values of neutron-physical characteristics. The experimental values were taken from physical startup tests of Bohunice Unit 1, 2 and 4 and Dukovany Unit 1 - 4. The theoretical values were calculated by code BIPR-7. The acceptance criteria were established for critical boron concentration, core loading symmetry measurement, boric acid worth, temperature reactivity coefficient, 'ejected' control rod worth, pressure reactivity coefficient and power reactivity coefficient. The new acceptance criteria were applied to evaluate results of physical startup tests of Mochovce Unit 1 in June 1998. The acceptance criteria showed to be adequate. The summary results of statistical processing and the comparison of earlier, new and US acceptance criteria for physical startup tests are presented.(Authors)

  8. 2022 candidature acceptance procedure: XXIV Olympic Winter Games

    2013-01-01

    La Procédure d’acceptation des candidatures est le document remis aux villes requérantes par le CIO durant la première phase du processus de candidature. Cette publication contient des explications concernant les différentes échéances de la phase d’acceptation jusqu’à la sélection des villes candidates par la commission exécutive du CIO en juillet 2014.

  9. 2018 candidature acceptance procedure: XXIII Olympic Winter Games

    2010-01-01

    La Procédure d’acceptation des candidatures est le document remis aux villes requérantes par le CIO durant la première phase du processus de candidature. Cette publication contient des explications concernant les différentes échéances de la phase d’acceptation jusqu’à la sélection des villes candidates par la commission exécutive du CIO en juin 2010.

  10. 2020 candidature acceptance procedure: Games of the XXXII Olympiad

    2011-01-01

    La Procédure d’acceptation des candidatures est le document remis aux villes requérantes par le CIO durant la première phase du processus de candidature. Cette publication contient des explications concernant les différentes échéances de la phase d’acceptation jusqu’à la sélection des villes candidates par la Commission exécutive du CIO en mai 2012.

  11. 242-A MCS Logic Acceptance Test Report for Year 2000 Upgrade

    242-A Evaporator distributive control system upgrade to D/3 version 9.0-2 for year 2000 compliance. Testing was performed per test procedure HNF-3568. There were no unresolved exceptions. The system responded correctly to all testing and meets the requirements to operate the 242-A This report documents the acceptance test results for the Evaporator facility

  12. Acceptance and Divergence from Engineering Design Procedures Implicating Knowledge Flow

    Jensen, Ole Kjeldal; Ahmed, Saeema

    2009-01-01

    When developing procedures such as tools, methods and frameworks to support the development of new products, one of the challenges is ensuring their successful implementation. This paper describes a study of the development and use of such design-procedures with primary focus on the new product...... development process-model, its supporting methods and handling of knowledge. Semi-structured interviews with 20 participants have been carried out to understand the use of procedures. All the interviews were conducted in a company, which develops large complex equipment for oil rigs. The findings suggest that...... a complex understanding of procedures and reasons for divergence needs to be adopted, where implicit as well as explicit procedures are recognised and managed. Three distinct types of implicit procedures were uncovered through the study: 1) historical implicit procedures; 2) social interpretations...

  13. User acceptance testing a step-by-step guide

    Hambling, Brian

    2013-01-01

    Every information system brought into service in every type of organisation requires user acceptance testing. This book is a hands-on manual for non-testing specialists to plan and carry out an effective acceptance test of an information system. It also identifies ways of making the process as simple and cost-effective as possible.

  14. Probabilistic Requirements (Partial) Verification Methods Best Practices Improvement. Variables Acceptance Sampling Calculators: Empirical Testing. Volume 2

    Johnson, Kenneth L.; White, K. Preston, Jr.

    2012-01-01

    The NASA Engineering and Safety Center was requested to improve on the Best Practices document produced for the NESC assessment, Verification of Probabilistic Requirements for the Constellation Program, by giving a recommended procedure for using acceptance sampling by variables techniques as an alternative to the potentially resource-intensive acceptance sampling by attributes method given in the document. In this paper, the results of empirical tests intended to assess the accuracy of acceptance sampling plan calculators implemented for six variable distributions are presented.

  15. Candidature acceptance procedure: XXI Olympic Winter Games 2010

    2010-01-01

    La Procédure d'acceptation des candidatures est le document donné aux villes requérantes par le CIO dans la première phase du processus de candidature. Cette publication contient des explications concernant les différentes échéances de la phase d'acceptation jusqu'à la sélection des villes candidates par la Commission Exécutive du CIO en août 2002.

  16. On acceptance criteria for Mochovce startup physical tests

    New acceptance criteria are discussed for physical startup tests of Mochovce Units 1, 2, at the stage of their development. The acceptance criteria determination is based on statistical processing of differences between the experimental and theoretical values of neutron-physical characteristics. The experimental values were taken from physical startup tests of Bohunice Unit 1, 2 and 4 and Dukovany Unit 1 - 4. The theoretical values were calculated by code BIPR-7. The acceptance criteria were established for critical boron concentration, core loading symmetry measurement, boric acid worth, temperature reactivity coefficient, 'ejected' control rod worth, pressure reactivity coefficient and power reactivity coefficient. The new acceptance criteria were applied to evaluate results of physical startup tests of Mochove Unit 1 in June 1998. The acceptance criteria showed to be adequate. The summary results of statistical processing and the comparison of earlier, new and US acceptance criteria for physical startup tests are presented. (author)

  17. Nevada Test Site Waste Acceptance Criteria, December 2000

    NONE

    2000-12-01

    This document establishes the US Department of Energy, Nevada Operations Office waste acceptance criteria. The waste acceptance criteria provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive waste and mixed waste for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the Nevada Test Site Area 3 and Area 5 Radioactive Waste Management Sites for storage or disposal.

  18. Nevada Test Site Waste Acceptance Criteria, December 2000

    This document establishes the US Department of Energy, Nevada Operations Office waste acceptance criteria. The waste acceptance criteria provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive waste and mixed waste for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the Nevada Test Site Area 3 and Area 5 Radioactive Waste Management Sites for storage or disposal

  19. Two-stage sampling for acceptance testing

    Atwood, C.L.; Bryan, M.F.

    1992-09-01

    Sometimes a regulatory requirement or a quality-assurance procedure sets an allowed maximum on a confidence limit for a mean. If the sample mean of the measurements is below the allowed maximum, but the confidence limit is above it, a very widespread practice is to increase the sample size and recalculate the confidence bound. The confidence level of this two-stage procedure is rarely found correctly, but instead is typically taken to be the nominal confidence level, found as if the final sample size had been specified in advance. In typical settings, the correct nominal [alpha] should be between the desired P(Type I error) and half that value. This note gives tables for the correct a to use, some plots of power curves, and an example of correct two-stage sampling.

  20. Two-stage sampling for acceptance testing

    Atwood, C.L.; Bryan, M.F.

    1992-09-01

    Sometimes a regulatory requirement or a quality-assurance procedure sets an allowed maximum on a confidence limit for a mean. If the sample mean of the measurements is below the allowed maximum, but the confidence limit is above it, a very widespread practice is to increase the sample size and recalculate the confidence bound. The confidence level of this two-stage procedure is rarely found correctly, but instead is typically taken to be the nominal confidence level, found as if the final sample size had been specified in advance. In typical settings, the correct nominal {alpha} should be between the desired P(Type I error) and half that value. This note gives tables for the correct a to use, some plots of power curves, and an example of correct two-stage sampling.

  1. Acceptance/Operational Test Report for Tank 241-AN-104 camera and camera purge control system

    This Acceptance/Operational Test Procedure (ATP/OTP) will document the satisfactory operation of the camera purge panel, purge control panel, color camera system and associated control components destined for installation. The final acceptance of the complete system will be performed in the field. The purge panel and purge control panel will be tested for its safety interlock which shuts down the camera and pan-and-tilt inside the tank vapor space during loss of purge pressure and that the correct purge volume exchanges are performed as required by NFPA 496. This procedure is separated into seven sections. This Acceptance/Operational Test Report documents the successful acceptance and operability testing of the 241-AN-104 camera system and camera purge control system

  2. WRAP low level waste restricted waste management (LLW RWM) glovebox acceptance test report

    Leist, K.J.

    1997-11-24

    On April 22, 1997, the Low Level Waste Restricted Waste Management (LLW RWM) glovebox was tested using acceptance test procedure 13027A-87. Mr. Robert L. Warmenhoven served as test director, Mr. Kendrick Leist acted as test operator and test witness, and Michael Lane provided miscellaneous software support. The primary focus of the glovebox acceptance test was to examine glovebox control system interlocks, operator Interface Unit (OIU) menus, alarms, and messages. Basic drum port and lift table control sequences were demonstrated. OIU menus, messages, and alarm sequences were examined, with few exceptions noted. Barcode testing was bypassed, due to the lack of installed equipment as well as the switch from basic reliance on fixed bar code readers to the enhanced use of portable bar code readers. Bar code testing was completed during performance of the LLW RWM OTP. Mechanical and control deficiencies were documented as Test Exceptions during performance of this Acceptance Test. These items are attached as Appendix A to this report.

  3. WRAP low level waste restricted waste management (LLW RWM) glovebox acceptance test report

    On April 22, 1997, the Low Level Waste Restricted Waste Management (LLW RWM) glovebox was tested using acceptance test procedure 13027A-87. Mr. Robert L. Warmenhoven served as test director, Mr. Kendrick Leist acted as test operator and test witness, and Michael Lane provided miscellaneous software support. The primary focus of the glovebox acceptance test was to examine glovebox control system interlocks, operator Interface Unit (OIU) menus, alarms, and messages. Basic drum port and lift table control sequences were demonstrated. OIU menus, messages, and alarm sequences were examined, with few exceptions noted. Barcode testing was bypassed, due to the lack of installed equipment as well as the switch from basic reliance on fixed bar code readers to the enhanced use of portable bar code readers. Bar code testing was completed during performance of the LLW RWM OTP. Mechanical and control deficiencies were documented as Test Exceptions during performance of this Acceptance Test. These items are attached as Appendix A to this report

  4. Acceptance testing and commissioning of a new model HDR afterloader

    We have recently performed acceptance testing procedures and have commissioned a new model HDR afterloader, the Varian VariSource with ''Intelligent Drive.'' Our site was one of the first installations worldwide. It is our intent to describe our tests and the results of the tests particularly as they may differ from other afterloaders. The Ir-192 source is unique among afterloaders marketed in the US in that it is very slender (OD of source wire is 0.59 mm) and relatively long (two 0.5 cm sources for a total active length of 1.0 cm). A check of source homogeneity by autoradiograph as urged by the US Nuclear Regulatory Commission demonstrates no detectable source inhomogeneity. Reentrant well ionization chambers are calibrated in the US with a 3.5 mm long source at Accredited Dosimetry Calibration Laboratories. Therefore calibration needs to be considered with some care. Calibration of the first delivered source with a well ionization chamber indicated agreement with the manufacturer's stated activity to within 0.5%. Source positioning is checked with a device called a 'cam scale'. Tests have been carried out on this system and it has been found to accurately indicate source position to within ±0.5 mm. Timer accuracy has been found to be better than 0.1% for dwell times of several hundred seconds. The intelligent drive system and the small source diameter allow the source wire to negotiate paths with small radius of curvature. A series of tests have been made in which the source is forced to negotiate 'U' turns of decreasing radius of curvature. A 4.7 F, 100 cm long catheter was used for these tests and the 'U' turn was positioned at approximately 90 cm. Under these conditions, the VariSource was consistently able to traverse a 1.25 cm radius of curvature, which is better than the manufacturer's stated limit of 1.5 cm

  5. Test Plan and Test Procedures Document - Prague Phase II

    Jakobi, Jörn

    2003-01-01

    This document, D16a-TPP, is the output of BETA WP5100 and describes the specific test procedures for Prague airport. It is one of three parts of the “Test Plan and Test Procedures” series of documents. A document is available for each of the test airports to be used in the BETA project: • D16a-TPP Test Plan and Test Procedures document, test procedures for Prague (PRG). • D16b-TPP Test Plan and Test Procedures document, test procedures for Hamburg (HAM). • D16c-TPP Test Plan and Tes...

  6. Product acceptance environmental and destructive testing for reliability.

    Dvorack, Michael A.; Kerschen, Thomas J.; Collins, Elmer W.

    2007-08-01

    To determine whether a component is meeting its reliability requirement during production, acceptance sampling is employed in which selected units coming off the production line are subjected to additional environmental and/or destructive tests that are within the normal environment space to which the component is expected to be exposed throughout its life in the Stockpile. This report describes what these tests are and how they are scored for reliability purposes. The roles of screens, Engineering Use Only tests, and next assembly product acceptance testing are also discussed, along with both the advantages and disadvantages of environmental and destructive testing.

  7. Example Procedures for Developing Acceptance-Range Criteria for BESTEST-EX

    Judkoff, Ron [National Renewable Energy Lab. (NREL), Golden, CO (United States); Polly, Ben [National Renewable Energy Lab. (NREL), Golden, CO (United States); Bianchi, Marcus [National Renewable Energy Lab. (NREL), Golden, CO (United States); Neymark, Joel [J. Neymark & Associates, Golden, CO (United States)

    2010-08-01

    This document provides an example procedure for establishing acceptance-range criteria to assess results from software undergoing BESTEST-EX. This example method for BESTEST-EX is a modified version of the method described in HERS BESTEST.

  8. Two Types of Test Assembly Checked and Accepted for CEFR

    2002-01-01

    The detail design of two types of test assembly used in the simulating transportation, and themounting and hydraulic test were completed in 2002. This two types of test assembly are manufactured inshanghai No.1 machine tool works, and checked and accepted in March 2003. The former is used in the

  9. Acceptance testing protocol for magnetic resonance imaging systems; Protocolo de testes de aceitacao em equipamentos de imagem por ressonancia magnetica

    Mazzola, Alessandro Andre [Universidade Federal, Rio de Janeiro, RJ (Brazil). Faculdade de Medicina. Programa de Pos-graduacao em Radiologia]. E-mail: aam.ez@terra.com.br; Herdade, Silvio Bruni [Sao Paulo Univ., SP (Brazil). Inst. de Fisica; Koch, Hilton Augusto; Carvalho, Antonio Carlos Pires [Universidade Federal, Rio de Janeiro, RJ (Brazil). Faculdade de Medicina. Dept. de Radiologia

    2005-05-15

    Objective: to develop an acceptance testing protocol for magnetic resonance imaging systems and to show which and how phantoms could be used to collect data. Materials and methods: the definition, procedure, analysis and the acceptation criteria were created for each of 15 selected tests. Results: These tests allow the evaluation of technical specifications stated on the manufacturer's sales proposal and to establish reference values to be used in subsequent constancy tests. Conclusion: future quality assurance programs in magnetic resonance imaging should consider employing tests similar or equal to the ones described in this paper. (author)

  10. Research on control rod drive mechanism seismic test acceptance criteria

    Background: There is no clear requirement on the rod drop performance of Control Rod Drive Mechanism (CRDM) in seismic condition. Purpose: Acceptance criteria of AP1OOO CRDM seismic test need to be determined. Methods: Related regulations and the safety function of AP1000 CRDM are investigated, as well as the conclusions drawn from the CRDM seismic tests worldwide. Results: Acceptance criteria of this test should be in accordance with the limit is in AP1OOO Nuclear Plant Safety Analysis Report. Conclusions: Drop time of control rods in AP1000 CRDM seismic test at the room temperature without flow is 2.7 s before and after Safe Shutdown Earthquake (SSE). (authors)

  11. 40 CFR 205.54 - Test procedures.

    2010-07-01

    ... 40 Protection of Environment 24 2010-07-01 2010-07-01 false Test procedures. 205.54 Section 205.54 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) NOISE ABATEMENT PROGRAMS TRANSPORTATION EQUIPMENT NOISE EMISSION CONTROLS Medium and Heavy Trucks § 205.54 Test procedures. The procedures...

  12. Summary of functional and performance test procedures

    Mitzel, Jens; Gülzow, Erich; Friedrich, K. Andreas; Araya, Samuel; Kaer, Soeren

    2015-01-01

    The EU-funded research project Stack-Test has developed different test procedures for the functional and performance characterization of PEMFC stacks. The different test procedures are pointed out in the current form and the example Performance Mapping Test program is introduced.

  13. Neutron absorber qualification and acceptance testing from the designer's perspective

    Starting in the mid 1990's, the USNRC began to require less than 100% credit for the 10B present in fixed neutron absorbers spent fuel transport packages. The current practice in the US is to use only 75% of the specified 10B in criticality safety calculations unless extensive acceptance testing demonstrates both the presence of the 10B and uniformity of its distribution. In practice, the NRC has accepted no more than 90% credit for 10B in recent years, while other national competent authorities continue to accept 100%. More recently, with the introduction of new neutron absorber materials, particularly aluminum / boron carbide metal matrix composites, the NRC has also expressed expectations for qualification testing, based in large part on Transnuclear's successful application to use a new composite material in the TN-68 storage / transport cask. The difficulty is that adding more boron than is really necessary to a metal has some negative effects on the material, reducing the ductility and the thermal conductivity, and increasing the cost. Excessive testing requirements can have the undesired effect of keeping superior materials out of spent fuel package designs, without a corresponding justification based on public safety. In European countries and especially in France, 100% credit has been accepted up to now with materials controls specified in the Safety Analysis Report (SAR): Manufacturing process approved by qualification testing Materials manufacturing controlled under a Quality Assurance system. During fabrication, acceptance testing directly on products or on representative samples. Acceptance criteria taking into account a statistical uncertainty corresponding to 3σ. The original and current bases for the reduced 10B credit, the design requirements for neutron absorber materials, and the experience of Transnuclear and Cogema Logistics with neutron absorber testing are examined. Guidelines for qualification and acceptance testing and process controls

  14. Adolescent test or procedure preparation

    ... else) during the procedure Playing hand-held video games Using guided imagery Trying other distractions, such as ... Alexander M. Managing patient stress in pediatric radiology. Radiol Technol . ... . Bray L, Callery P, Kirk S. A qualitative study ...

  15. Adolescent test or procedure preparation

    ... someone else) during the procedure Playing hand-held video games Using guided imagery Trying other distractions, such as listening to music through headphones, if allowed When possible, let your adolescent make some decisions, such as deciding the time ...

  16. A general design for energy test procedures

    Appliances are increasingly controlled by microprocessors. Unfortunately, energy test procedures have not been modified to capture the positive and negative contributions of the microprocessor to the appliance's energy use. A new test procedure is described which captures both the mechanical and logical features present in many new appliances. We developed an energy test procedure for refrigerators that incorporates most aspects of the proposed new approach. Some of the strengths and weaknesses of the new test are described

  17. Handbook of mutagenicity test procedures

    This book consists of 39 chapters. Some of the titles are: Bacillus subtilis repair test, Induced reversion using human adenovirus, The fluctuation test in bacteria, Chemical mutagenesis with diploid human fibroblasts, The specific locus test in the mouse, The bone marrow micronucleus test, and Sperm morphology in testing in mice

  18. Type of Speech Material Affects Acceptable Noise Level Test Outcome

    Koch, Xaver; Dingemanse, Gertjan; Goedegebure, André; Janse, Esther

    2016-01-01

    The acceptable noise level (ANL) test, in which individuals indicate what level of noise they are willing to put up with while following speech, has been used to guide hearing aid fitting decisions and has been found to relate to prospective hearing aid use. Unlike objective measures of speech perception ability, ANL outcome is not related to individual hearing loss or age, but rather reflects an individual’s inherent acceptance of competing noise while listening to speech. As such, the measu...

  19. Type of speech material affects Acceptable Noise Level test outcome

    Xaver eKoch; Gertjan eDingemanse; André eGoedegebure; Esther eJanse

    2016-01-01

    The Acceptable Noise Level (ANL) test, in which individuals indicate what level of noise they are willing to put up with while following speech, has been used to guide hearing aid fitting decisions and has been found to relate to prospective hearing aid use. Unlike objective measures of speech perception ability, ANL outcome is not related to individual hearing loss or age, but rather reflects an individual's inherent acceptance of competing noise while listening to speech. As such, the measu...

  20. ISOLOK VALVE ACCEPTANCE TESTING FOR DWPF SME SAMPLING PROCESS

    Edwards, T.; Hera, K.; Coleman, C.; Jones, M.; Wiedenman, B.

    2011-12-05

    the two locations were compared to determine if the contents of the tank were well mixed. The Coliwasa sampler is a tube with a stopper at the bottom and is designed to obtain grab samples from specific locations within the drum contents. A position paper (4) was issued to address the prototypic flow loop issues and simulant selections. A statistically designed plan (5) was issued to address the total number of samples each sampler needed to pull, to provide the random order in which samples were pulled and to group samples for elemental analysis. The TTR required that the Isolok sampler perform as well as the Hydragard sampler during these tests to ensure the acceptability of the Isolok sampler for use in the DWPF sampling cells. Procedure No.L9.4-5015 was used to document the sample parameters and process steps. Completed procedures are located in R&D Engineering job folder 23269.

  1. Isolok Valve Acceptance Testing For DWPF SME Sampling Process

    locations were compared to determine if the contents of the tank were well mixed. The Coliwasa sampler is a tube with a stopper at the bottom and is designed to obtain grab samples from specific locations within the drum contents. A position paper (4) was issued to address the prototypic flow loop issues and simulant selections. A statistically designed plan (5) was issued to address the total number of samples each sampler needed to pull, to provide the random order in which samples were pulled and to group samples for elemental analysis. The TTR required that the Isolok sampler perform as well as the Hydragard sampler during these tests to ensure the acceptability of the Isolok sampler for use in the DWPF sampling cells. Procedure No.L9.4-5015 was used to document the sample parameters and process steps. Completed procedures are located in R and D Engineering job folder 23269.

  2. Test report - caustic addition system operability test procedure

    This Operability Test Report documents the test results of test procedure WHC-SD-WM-OTP-167 ''Caustic Addition System Operability Test Procedure''. The Objective of the test was to verify the operability of the 241-AN-107 Caustic Addition System. The objective of the test was met

  3. Acceptance test report for portable exhauster POR-007/Skid E

    This document describes Acceptance Testing performed on Portable Exhauster POR-007/Skid E. It includes measurements of bearing vibration levels, pressure decay testing, programmable logic controller interlocks, high vacuum, flow and pressure control functional testing. The purpose of Acceptance testing documented by this report was to demonstrate compliance of the exhausters with the performance criteria established within HNF-0490, Rev. 1 following a repair and upgrade effort at Hanford. In addition, data obtained during this testing is required for the resolution of outstanding Non-conformance Reports (NCR), and finally, to demonstrate the functionality of the associated software for the pressure control and high vacuum exhauster operating modes provided for by W-320. Additional testing not required by the ATP was also performed to assist in the disposition and close out of receiving inspection report and for application design information (system curve). Results of this testing are also captured within this document

  4. Standard-B auto grab sampler hydrogen monitoring system, Acceptance Test Report

    Project W-369, Watch List Tank Hydrogen Monitors, installed a Standard-C Hydrogen Monitoring System (SHMS) on the Flammable gas waste tank AN-104. General Support Projects (8K510) was support by Test Engineering (7CH30) in the performance of the Acceptance Test Procedures (ATP) to qualify the SHMS cabinets on the waste tank. The ATP's performance was controlled by Tank Farm work package. This completed ATP is transmitted by EDT-601748 as an Acceptance Test Report (ATR) in accordance with WHC-6-1, EP 4.2 and EP 1.12

  5. Multiport riser and flange assemblies acceptance test report

    This document presents the results of the acceptance test for the multiport riser (MPR) and multiport flange (MPF) assemblies. The accepted MPR and MPF assemblies will be used in support of the hydrogen mitigation project for double-shell waste tank 241-SY-101 and other related projects. The testing described in this document verifies that the mechanical and interface features are operating as designed and that the unit is ready for field service. The objectives of the acceptance testing were as follows: Basic equipment functions and mechanical interfaces were verified; Installation and removal of equipment were demonstrated to the degree possible; Operation of the decon spray system and all valving was confirmed; and the accumulated leak rate of the MPR and MPF assemblies was determined

  6. Acceptance test for graphite components and construction status of HTTR

    In March, 1991, the Japan Atomic Energy Research Institute (JAERI) started to constructed the High Temperature engineering Test Reactor(HTTR) which is a 30-MW(thermal) helium gas-cooled reactor with a core composed of prismatic graphite blocks piled on the core support graphite structures. Two types of graphite materials are used in the HTTR. One is the garde IG-110, isotropic fine grain graphite, another is the grade PGX, medium-to-fine grained molded graphite. These materials were selected on the basis of the appropriate properties required by the HTTR reactor design. Industry-wide standards for an acceptance test of graphite materials used as main components of a nuclear reactor had not been established. The acceptance standard for graphite components of the HTTR, therefore, was drafted by JAERI and reviewed by specialists outside JAERI. The acceptance standard consists of the material testing, non-destructive examination such as the ultrasonic and eddy current testings, dimensional and visual inspections and assembly test. Ultrasonic and eddy current testings are applied to graphite logs to detect an internal flaw and to graphite components to detect a surface flaw, respectively. The assembly test is performed at the works, prior to their installation in the reactor pressure vessel, to examine fabricating precision of each component and alignment of piled-up structures. The graphite components of the HTTR had been tested on the basis of the acceptance standard. It was confirmed that the graphite manufacturing process was well controlled and high quality graphite components were provided to the HTTR. All graphite components except for the fuel graphite blocks are to be installed in the reactor pressure vessel of the HTTR in September 1995. The paper describes the construction status of the HTTR focusing on the graphite components. The acceptance test results are also presented in this paper. (author). Figs

  7. Project W-320 acceptance test report for AY-farm electrical distribution

    This Acceptance Test Procedure (ATP) has been prepared to demonstrate that the AY-Farm Electrical Distribution System functions as required by the design criteria. This test is divided into three parts to support the planned construction schedule; Section 8 tests Mini-Power Pane AY102-PPI and the EES; Section 9 tests the SSS support systems; Section 10 tests the SSS and the Multi-Pak Group Control Panel. This test does not include the operation of end-use components (loads) supplied from the distribution system. Tests of the end-use components (loads) will be performed by other W-320 ATPs

  8. 40 CFR 53.66 - Test procedure: Volatility test.

    2010-07-01

    ... 40 Protection of Environment 5 2010-07-01 2010-07-01 false Test procedure: Volatility test. 53.66... Characteristics of Class II Equivalent Methods for PM2.5 § 53.66 Test procedure: Volatility test. (a) Overview. This test is designed to ensure that the candidate method's losses due to volatility when sampling...

  9. Caustic addition system operability test procedure

    This test procedure provides instructions for performing operational testing of the major components of the 241-AN-107 Caustic Addition System by WHC and Kaiser personnel at the Rotating Equipment Shop run-in pit (Bldg. 272E)

  10. SEP BIMOD variable conductance heat pipes acceptance and characterization tests

    Hemminger, J. A.

    1981-08-01

    A series of six heat pipes, similar in design to those flown on the Comunications Technology Satellite Hermes, for use in a prototype Solar Electric Propulsion BIMOD thrust module are evaluated. The results of acceptance and characterization tests performed on the heat pipe subassemble are reported. The performance of all the heat pipes met, or exceeded, design specifications.

  11. Acceptance test report MICON software exhaust fan control modifications

    This report documents the results the acceptance test HNF-4108 which verifies the MICON program changes for the new automatic transfer switch ATS-2 alarms, the Closed Loop Cooling isolator status, the CB-3 position alarm, the alarms for the new emergency fan damper backup air compressor, and the generator sequencer logic

  12. Automatically generated acceptance test: A software reliability experiment

    Protzel, Peter W.

    1988-01-01

    This study presents results of a software reliability experiment investigating the feasibility of a new error detection method. The method can be used as an acceptance test and is solely based on empirical data about the behavior of internal states of a program. The experimental design uses the existing environment of a multi-version experiment previously conducted at the NASA Langley Research Center, in which the launch interceptor problem is used as a model. This allows the controlled experimental investigation of versions with well-known single and multiple faults, and the availability of an oracle permits the determination of the error detection performance of the test. Fault interaction phenomena are observed that have an amplifying effect on the number of error occurrences. Preliminary results indicate that all faults examined so far are detected by the acceptance test. This shows promise for further investigations, and for the employment of this test method on other applications.

  13. W-026 acceptance test report system integration equipment (SIE)(submittal {number_sign} 018.6.A)

    Watson, T.L.

    1997-01-27

    Acceptance testing of the System Integration Equipment (SIE) at Hanford was performed in two stages. The first was inconclusive, and resulted in a number of findings. These finding. are summarized as part of this report. The second stage of testing addressed these findings, and performed full system testing per the approved test procedure. This report includes summaries of all testing, results and finding.. Although the SIE did not in some cases perform as required for plant operations, it did perform per the system specification. (These discrepancies were noted and are addressed elsewhere.) Following testing, the system was formaLLy accepted. Documentation of this acceptance is incLuded in this report.

  14. 40 CFR 53.65 - Test procedure: Loading test.

    2010-07-01

    ... operating manual referred to in section 7.4.18 of 40 CFR part 50, appendix L. (3) Determine the preweight of... 40 Protection of Environment 5 2010-07-01 2010-07-01 false Test procedure: Loading test. 53.65... Characteristics of Class II Equivalent Methods for PM2.5 § 53.65 Test procedure: Loading test. (a) Overview....

  15. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA, JUNE 2006

    U.S. DEPARTMENT OF ENERGY, NATIONAL NUCLEAR SECURITY ADMINISTRATION NEVADA SITE OFFICE

    2006-06-01

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal.

  16. W-026, acceptance test report TRU empty drum compactor (submittal number-sign 634)

    On 10/19/96 and 10/21/96, the 06/04/96 version of the Empty Drum Compactor Acceptance Test Procedure was used to perform tests by INET Corporation at the Hanford WRAP facility. The INET compaction components were installed in the Diversified glovebox. The Diversified glovebox and cart and the INET compaction components, EDC HPU and drum centering device constitute the Empty Drum Compactor

  17. Startup of the FFTF sodium cooled reactor. [Acceptance Test Program

    Redekopp, R.D.; Umek, A.M.

    1981-03-01

    The Fast Flux Test Facility (FFTF), located on the Department of Energy (DOE) Hanford Reservation near Richland, Washington, is a 3 Loop 400 MW(t) sodium cooled fast reactor with a primary mission to test fuels and materials for development of the Liquid Metal Fast Breeder Reactor (LMFBR). Bringing FFTF to a condition to accomplish this mission is the goal of the Acceptance Test Program (ATP). This program was the mechanism for achieving startup of the FFTF. Highlights of the ATP involving the system inerting, liquid metal and inerted cell testing and initial ascent to full power are discussed.

  18. Acceptance of genetic testing in a general population

    Aro, A R; Hakonen, A; Hietala, M;

    1997-01-01

    The aim of the study was to analyze effects of age, education and gender on acceptance of genetic testing. Subjects, n = 1967 aged 15-69, were a stratified random sample of the Finnish population. One thousand, one hundred and sixty nine subjects, 530 men and 639 women, returned the questionnaire....... The majority of the respondents approved of the availability of genetic testing. Young, aged 15-24, were more favourable towards testing and more willing to undergo suggested tests, but they were also more worried than others about the misuse of test results. Men aged 45-69 with only basic education...... were more in favour of mandatory genetic testing than other respondents. Respondents with university education were more critical towards genetic testing and expressed their worry about eugenics more often than other education groups. In conclusion, there are age, education and gender related...

  19. Central Acceptance Testing for Camera Technologies for CTA

    Bonardi, A; Chadwick, P; Dazzi, F; Förster, A; Hörandel, J R; Punch, M

    2015-01-01

    The Cherenkov Telescope Array (CTA) is an international initiative to build the next generation ground based very-high energy gamma-ray observatory. It will consist of telescopes of three different sizes, employing several different technologies for the cameras that detect the Cherenkov light from the observed air showers. In order to ensure the compliance of each camera technology with CTA requirements, CTA will perform central acceptance testing of each camera technology. To assist with this, the Camera Test Facilities (CTF) work package is developing a detailed test program covering the most important performance, stability, and durability requirements, including setting up the necessary equipment. Performance testing will include a wide range of tests like signal amplitude, time resolution, dead-time determination, trigger efficiency, performance testing under temperature and humidity variations and several others. These tests can be performed on fully-integrated cameras using a portable setup at the came...

  20. TMACS test procedure TP005: Sensor configuration, logging, and data conversion. Revision 4

    The TMACS Software Project Test Procedures translate the project's acceptance criteria into test steps. Software releases are certified when the affected Test Procedures are successfully performed and the customers authorize installation of these changes. This Test Procedure addresses the sensor configuration, conversion and logging requirements of the TMACS. The features to be tested are as follows: sensor configuration data; conversion of continuous sensor data to engineering units; conversion of digital data to discrete states; discrete sensor data logging; and continuous sensor data logging

  1. MCO combustible gas management leak test acceptance criteria

    Existing leak test acceptance criteria for mechanically sealed and weld sealed multi-canister overpacks (MCO) were evaluated to ensure that MCOs can be handled and stored in stagnant air without compromising the Spent Nuclear Fuel Project's overall strategy to prevent accumulation of combustible gas mixtures within MCO's or within their surroundings. The document concludes that the integrated leak test acceptance criteria for mechanically sealed and weld sealed MCOs (1 x 10-5 std cc/sec and 1 x 10-7 std cc/sec, respectively) are adequate to meet all current and foreseeable needs of the project, including capability to demonstrate compliance with the NFPA 60 Paragraph 3-3 requirement to maintain hydrogen concentrations [within the air atmosphere CSB tubes] t or below 1 vol% (i.e., at or below 25% of the LFL)

  2. Acceptance test plan for the Waste Information Control System

    Flynn, D.F.

    1994-09-14

    This document describes the acceptance test plan for the WICS system. The Westinghouse Hanford Company (WHC) Hazardous Material Control Group (HMC) of the 222-S Laboratory has requested the development of a system to help resolve many of the difficulties associated with tracking and data collection of containers and drums of waste. This system has been identified as Waste Information and Control System (WICS). The request for developing and implementing WICS has been made to the Automation and Simulation Engineering Group (ASE).

  3. Central Acceptance Testing for Camera Technologies for CTA

    Bonardi, A.; T. Buanes; Chadwick, P.; Dazzi, F.; A. Förster(CERN, Geneva, Switzerland); Hörandel, J. R.; Punch, M.; Consortium, R. M. Wagner for the CTA

    2015-01-01

    The Cherenkov Telescope Array (CTA) is an international initiative to build the next generation ground based very-high energy gamma-ray observatory. It will consist of telescopes of three different sizes, employing several different technologies for the cameras that detect the Cherenkov light from the observed air showers. In order to ensure the compliance of each camera technology with CTA requirements, CTA will perform central acceptance testing of each camera technology. To assist with thi...

  4. Acceptance test report for portable exhauster POR-008/Skid F

    Portable Exhauster POR-008 was procured via HNF-0490, Specification for a Portable Exhausted System for Waste Tank Ventilation. Prior to taking ownership, acceptance testing was performed at the vendors. However at the conclusion of testing a number of issues remained that required resolution before the exhausters could be used by Project W-320. The purpose of acceptance testing documented by this report was to demonstrate compliance of the exhausters with the performance criteria established within HNF-O49O, Rev. 1 following a repair and upgrade effort at Hanford. In addition, data obtained during this testing is required for the resolution of outstanding Non-conformance Reports (NCR), and finally, to demonstrate the functionality of the associated software for the pressure control and high vacuum exhauster operating modes provided for by W-320. Additional testing not required by the ATP was also performed to assist in the disposition and close out of receiving inspection report and for application design information (system curve). Results of this testing are also captured within this document

  5. Planning and acceptance testing of MV therapy installations

    Purpose: This course is designed for practitioners and beginners in brachytherapy. The aim is to review biological principles equipment are aware of all aspects involved. The object is to cover in a broad overview the considerations that go into selecting, installing, testing and accepting megavoltage therapy equipment and to provide a resource for more detailed information. Planning and acceptance testing of a megavoltage therapy installation is a major undertaking for any size group, institution or department. It can take approximately two years from the time a decision is made to get a machine to where the first patient is treated. Because the equipment and site preparation are expensive, and most of the machines are complex and can be supplied by several different manufacturers, it is imperative that a great deal of thought and care go into the decision: the aim being that the specifications of the machine that is installed meet the immediate need of the department and the needs for the projected lifetime of the equipment. A general survey of the types of equipment available will be presented. This will concentrate on general purpose linear accelerators, although Cobalt 60 machines, microtrons and special purpose machines (intra-operative equipment) will also be covered. General descriptions of the machines along with typical specifications will be given. Selecting the best machine to meet specific needs can be quite complex and criteria for making the selection are presented in a series of twelve steps. site selection and room design, including the console area, are also critical. The general principles for shielding calculations will be provided. Critical to any installation is the acceptance testing of the equipment including material and radiation oncology performance tests. These tests will be outlined. A reading list of suitable references describing in detail many of the aspects of this course will be provided

  6. Planning and acceptance testing of Mv therapy installations

    Purpose/Objective: The purpose of this course is to ensure that the individuals responsible for acquiring megavoltage therapy equipment are aware of all aspects involved. The object is to cover in a broad overview the considerations that go into selecting, installing, testing and accepting megavoltage therapy equipment and to provide a resource for more detailed information. Planning and acceptance testing of a megavoltage therapy installation is a major undertaking for any size group, institution or department. It can take approximately two years from the time a decision is made to get a machine to where the first patient is treated. Because the equipment and site preparation are expensive, and most of the machines are complex and can be supplied by several different manufacturers, it is imperative that a great deal of thought and care go into the decision: the aim being that the specifications of the machine that is installed meet the immediate need of the department and the needs for the projected lifetime of the equipment. A general survey of the types of equipment available will be presented. This will concentrate on general purpose linear accelerators, although Cobalt 60 machines, microtrons and special purpose machines (intra-operative equipment) will also be covered. General descriptions of the machines along with typical specifications will be given. Selecting the best machine to meet specific needs can be quite complex and criteria for making the selection are presented in a series of twelve steps. Site selection and room design, including the console area, are also critical. The general principles for shielding calculations will be provided. Critical to any installation is the acceptance testing of the equipment including material and radiation oncology performance tests. These tests will be outlined. A reading list of suitable references describing in detail many of the aspects of this course will be provided

  7. Planning and acceptance testing of MV therapy installations

    Purpose/Objective: The purpose of this course is to ensure that the individuals responsible for acquiring megavoltage therapy equipment are aware of all aspects involved. The object is to cover in a broad overview the considerations that go into selecting, installing, testing and accepting megavoltage therapy equipment and to provide a resource for more detailed information. Planning and acceptance testing of a megavoltage therapy installation is a major undertaking for any size group, institution or department. It can take approximately two years from the time a decision is made to get a machine to where the first patient is treated. Because the equipment and site preparation are expensive, and most of the machines are complex and can be supplied by several different manufacturers, it is imperative that a great deal of thought and care go into the decision: the aim being that the specifications of the machine that is installed meet the immediate need of the department and the needs for the projected lifetime of the equipment. A general survey of the types of equipment available will be presented. This will concentrate on general purpose linear accelerators, although Cobalt 60 machines, microtrons and special purpose machines (intra-operative equipment) will also be covered. General descriptions of the machines along with typical specifications will be given. Selecting the best machine to meet specific needs can be quite complex and criteria for making the selection are presented in a series of twelve steps. Site selection and room design, including the console area, are also critical. The general principles for shielding calculations will be provided. Critical to any installation is the acceptance testing of the equipment including material and radiation oncology performance tests. These tests will be outlined. A reading list of suitable references describing in detail many of the aspects of this course will be provided

  8. Test procedure for boxed waste assay system

    This document, prepared by Los Alamos National Laboratory's NMT-4 group, details the test methodology and requirements for Acceptance/Qualification testing of a Boxed Waste Assay System (BWAS) designed and constructed by Pajarito Scientific Corporation. Testing of the BWAS at the Plutonium Facility (TA55) at Los Alamos National Laboratory will be performed to ascertain system adherence to procurement specification requirements. The test program shall include demonstration of conveyor handling capabilities, gamma ray energy analysis, and imaging passive/active neutron accuracy and sensitivity. Integral to these functions is the system's embedded operating and data reduction software

  9. Nevada Test Site waste acceptance criteria [Revision 1

    Revision one updates the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the NTS. Review each section of this document. This document is not intended to include all of the requirements; rather, it is meant as a guide toward meeting the regulations. All references in this document should be observed to avoid omission of requirements on which acceptance or rejection of waste will be based. The Department of Energy/Nevada Operations Office (DOE/NV) and support contractors are available to assist you in understanding or interpreting this document

  10. Nevada Test Site waste acceptance criteria [Revision 1

    None

    1997-08-01

    Revision one updates the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the NTS. Review each section of this document. This document is not intended to include all of the requirements; rather, it is meant as a guide toward meeting the regulations. All references in this document should be observed to avoid omission of requirements on which acceptance or rejection of waste will be based. The Department of Energy/Nevada Operations Office (DOE/NV) and support contractors are available to assist you in understanding or interpreting this document.

  11. Acceptance test report for project C-157 ''T-Plant electrical upgrade''

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ''Acceptance Test Proceedure for Project C-157 'T Plant Electrical Upgrade''' The test was completed and approved without any problems or exceptions

  12. Acceptance Test Report for Fourth-Generation Hanford Corrosion Monitoring Cabinet

    This Acceptance Test Plan (ATP) will document the satisfactory operation of the third-generation corrosion monitoring cabinet (Hiline Engineering Part No.0004-CHM-072-C01). This ATP will be performed by the manufacturer of the cabinet prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion monitoring cabinet. The test will consist of a continuity test of the cabinet wiring from the end of cable to be connected to corrosion probe, through the appropriate intrinsic safety barriers and out to the 15 pin D-shell connectors to be connected to the corrosion monitoring instrument. Additional testing will be performed using a constant current and voltage source provided by the corrosion monitoring hardware manufacturer to verify proper operation of corrosion monitoring instrumentation

  13. Acceptability of prenatal testing and termination of pregnancy in Pakistan.

    Jafri, H; Hewison, J; Sheridan, E; Ahmed, S

    2015-01-01

    This study aimed to assess acceptability of prenatal testing (PNT) and termination of pregnancy (TOP) for a range of conditions in Pakistani parents with and without a child with a genetic condition. A structured questionnaire assessing acceptability of PNT and TOP for 30 conditions was completed by 400 Pakistani participants: 200 parents with a child with a genetic condition (100 fathers and 100 mothers) and 200 parents without an affected child (100 fathers and 100 mothers). There was a high level of interest in PNT, where over 80 % of parents in all four study groups would want PNT for the majority of the conditions. There was comparatively less interest in TOP for the same conditions (ranging from 5 to 70 % of parents, with mothers of an affected child being most interested). Parents were most likely to be interested in TOP for conditions at the serious end of the continuum. More than half of the participants in each group would consider TOP for anencephaly and quadriplegia. The interest in PNT and TOP for a range of conditions suggests that rapidly developing PNT technologies are likely to be acceptable in Pakistan, a low-middle income level and Muslim country. The comparatively lower level of interest in TOP for the same conditions highlights ethical dilemmas that such technologies are likely to raise. PMID:25081227

  14. Could quantitative liver function tests gain wide acceptance among hepatologists?

    Giovanni Tarantino

    2009-01-01

    It has been emphasized that the assessment of residual liver function is of paramount importance to determine the following: severity of acute or chronic liver diseases independent of etiology; long-term prognosis; step-bystep disease progression; surgical risk; and efficacy of antiviral treatment. The most frequently used tools are the galactose elimination capacity to asses hepatocyte cytosol activity, plasma clearance of indocyanine green to assess excretory function, and antipyrine clearance to estimate microsomal activity. However, a widely accepted liver test (not necessarily a laboratory one) to assess quantitative functional hepatic reserve still needs to be established, although there have been various proposals. Furthermore, who are the operators that should order these tests? Advances in analytic methods are expected to allow quantitative liver function tests to be used in clinical practice.

  15. [Clinical trial data validation and user acceptance testing].

    Sun, Hua-long; Dai, Nan

    2015-11-01

    For pharmaceutical industries, clinical data is one of the most valuable deliverables. It is also the basis of analysis, submission, approval, labeling and marketing of a drug product. To ensure the integrity and reliability of clinical data, a scientific standardized quality control (QC) has to be established at each step of a clinical trial. Data validation is conducted to ensure the reasonability and compliance of clinical data by checking data quality before the data is statistically analyzed. This paper focuses on purpose of data validation, creation of data validation plan, rationale of data validation, types of data validation and performance of user acceptance testing on clinical database. PMID:26911047

  16. Waste retrieval sluicing system data acquisition system acceptance test report

    This document describes the test procedure for the Project W-320 Tank C-106 Sluicing Data Acquisition System (W-320 DAS). The Software Test portion will test items identified in the WRSS DAS System Description (SD), HNF-2115. Traceability to HNF-2115 will be via a reference that follows in parenthesis, after the test section title. The Field Test portion will test sensor operability, analog to digital conversion, and alarm setpoints for field instrumentation. The W-320 DAS supplies data to assist thermal modeling of tanks 241-C-106 and 241-AY-102. It is designed to be a central repository for information from sources that would otherwise have to be read, recorded, and integrated manually. Thus, completion of the DAS requires communication with several different data collection devices and output to a usable PC data formats. This test procedure will demonstrate that the DAS functions as required by the project requirements stated in Section 3 of the W-320 DAS System Description, HNF-2115

  17. Trust, confidence, procedural fairness, outcome fairness, moral conviction, and the acceptance of GM field experiments.

    Siegrist, Michael; Connor, Melanie; Keller, Carmen

    2012-08-01

    In 2005, Swiss citizens endorsed a moratorium on gene technology, resulting in the prohibition of the commercial cultivation of genetically modified crops and the growth of genetically modified animals until 2013. However, scientific research was not affected by this moratorium, and in 2008, GMO field experiments were conducted that allowed us to examine the factors that influence their acceptance by the public. In this study, trust and confidence items were analyzed using principal component analysis. The analysis revealed the following three factors: "economy/health and environment" (value similarity based trust), "trust and honesty of industry and scientists" (value similarity based trust), and "competence" (confidence). The results of a regression analysis showed that all the three factors significantly influenced the acceptance of GM field experiments. Furthermore, risk communication scholars have suggested that fairness also plays an important role in the acceptance of environmental hazards. We, therefore, included measures for outcome fairness and procedural fairness in our model. However, the impact of fairness may be moderated by moral conviction. That is, fairness may be significant for people for whom GMO is not an important issue, but not for people for whom GMO is an important issue. The regression analysis showed that, in addition to the trust and confidence factors, moral conviction, outcome fairness, and procedural fairness were significant predictors. The results suggest that the influence of procedural fairness is even stronger for persons having high moral convictions compared with persons having low moral convictions. PMID:22150405

  18. Biomonitoring test procedures and biological criteria

    Kszos, L.A. [Oak Ridge National Lab., TN (United States); Lipschultz, M.J. [City of Las Vegas, NV (United States); Foster, W.E. [Saint Mary`s Coll., Winona, MN (United States)

    1997-10-01

    The Water Environment Federation recently issued a special publication, Biomonitoring in the Water Environment. In this paper, the authors highlight the contents of the chapter 3, Biomonitoring Test Procedures, identify current trends in test procedures and introduce the concept of biological criteria (biocriteria). The book chapter (and this paper) focuses on freshwater and marine chronic and acute toxicity tests used in the National Pollutant Discharge Elimination System (NPDES) permits program to identify effluents and receiving waters containing toxic materials in acutely or chronically toxic concentrations. The two major categories of toxicity tests include acute tests and chronic tests. The USEPA chronic tests required in NPDEs permits have been shortened to 7 days by focusing on the most sensitive life-cycle stages; these tests are often referred to as short-term chronic tests. The type of test(s) required depend on NPDES permit requirements, objectives of the test, available resources, requirements of the test organisms, and effluent characteristics such as variability in flow or toxicity. The permit writer will determine the requirements for toxicity test(s) by considering such factors as dilution, effluent variability, and exposure variability. Whether the required test is acute or chronic, the objective of the test is to estimate the safe or no effect concentration which is defined as the concentration which will permit normal propagation of fish and other aquatic life in the receiving waters. In this paper, the authors review the types of toxicity tests, the commonly used test organisms, and the uses of toxicity test data. In addition, they briefly describe research on new methods and the use of biological criteria.

  19. Standard-E hydrogen monitoring system shop acceptance test procedure

    Schneider, T.C.

    1997-10-02

    The purpose of this report is to document that the Standard-E Hydrogen Monitoring Systems (SHMS-E), fabricated by Mid-Columbia Engineering (MCE) for installation on the Waste Tank Farms in the Hanford 200 Areas, are constructed as intended by the design. The ATP performance will verify proper system fabrication.

  20. Acceptance testing and quality assurance of Simulix evolution radiotherapy simulator

    The success of radiotherapy depends on precise treatment simulation and proper patient positioning. The simulator is a conventional radiographic and fluoroscopic system which emulates the geometrical positions of radiotherapy treatment unit. Hence, the acceptance tests and quality assurance (QA) of the simulator are important prior to its commissioning for the safe and precise clinical use. The verification of mechanical and optical readouts, field size, isocenter, optical and radiation field congruence were performed. The X-ray beam parameters were tested for kVp, mAs and consistency of radiation output. The flat panel detector performance was checked with respect to resolution, low contrast sensitivity (LCS), automatic dose rate control (ADRC), and gray image resolution (GIR). Gantry, table, and imaging system collision possibility was checked. Radiation survey around the room was also performed. The field size test for digital readout and on graph paper, the results of isocenter checkup for rotation of gantry, collimator, and couch, and the deviations observed in auto stop for various movements were found within the tolerance limits. Optical field and radiation field was found congruent. All the lasers were found aligned with the established isocenter. Maximum deviation for set and measured kV was found to be 3% in fluoro mode. The maximum deviation observed in mAs was 1.5% in 3-point as well as in 2-point film exposed mode. The X-ray output was found consistent. The results of tests for resolution, LCS, ADRC, and GIR of the flat panel detector were within tolerance limits. All the six safety interlocks were found working. Radiation level around the room was found within the acceptable limits. All the tests carried out were found within the tolerance limits. The data which has been taken in this study will provide basic support to the routine QA of the simulator. (author)

  1. Topographical mapping system for radiological and hazardous environments acceptance testing

    During the summer of 1996, the Topographical Mapping System (TMS) for hazardous and radiological environments and its accompanying three-dimensional (3-D) visualization tool, the Interactive Computer-Enhanced Remote-Viewing System (ICERVS), were delivered to Oak Ridge National Laboratory (ORNL). ORNL and Mechanical Technology, Inc., performed final acceptance testing of the TMS during the next eight months. The TMS was calibrated and characterized during this period. This paper covers the calibration, characterization, and acceptance testing of the TMS. Development of the TMS and ICERVS was initiated by the US Department of Energy (DOE) for the purpose of characterization and remediation of underground storage tanks (USTs) at DOE sites across the country. DOE required a 3-D, topographical mapping system suitable for use in hazardous and radiological environments. The intended application is the mapping of the interior of USTs as part of DOE's waste characterization and remediation efforts and to obtain baseline data on the content of the storage tank interiors as well as data on changes in the tank contents and levels brought about by waste remediation steps. Initially targeted for deployment at the Hanford Washington site, the TMS is designed to be a self-contained, compact, and reconfigurable system that is capable of providing rapid, variable-resolution mapping information in poorly characterized workspaces with a minimum of operator intervention

  2. 16 CFR 1512.18 - Tests and test procedures.

    2010-01-01

    ... 1512.18 Commercial Practices CONSUMER PRODUCT SAFETY COMMISSION FEDERAL HAZARDOUS SUBSTANCES ACT.... (j) Rim test. (Ref. §§ 1512.10 and 1512.11(c)): (1) Procedure. Only one wheel need be tested if the.... (o) Reflective tire and rim test (Ref. § 1512.16(h) and (i)): (1) Apparatus. Arrangements for...

  3. Parametric Sensitivity Tests- European PEM Fuel Cell Stack Test Procedures

    Araya, Samuel Simon; Andreasen, Søren Juhl; Kær, Søren Knudsen

    2014-01-01

    As fuel cells are increasingly commercialized for various applications, harmonized and industry-relevant test procedures are necessary to benchmark tests and to ensure comparability of stack performance results from different parties. This paper reports the results of parametric sensitivity tests...

  4. Type of speech material affects Acceptable Noise Level test outcome

    Xaver eKoch

    2016-02-01

    Full Text Available The Acceptable Noise Level (ANL test, in which individuals indicate what level of noise they are willing to put up with while following speech, has been used to guide hearing aid fitting decisions and has been found to relate to prospective hearing aid use. Unlike objective measures of speech perception ability, ANL outcome is not related to individual hearing loss or age, but rather reflects an individual's inherent acceptance of competing noise while listening to speech. As such, the measure may predict aspects of hearing aid success. Crucially, however, recent studies have questioned its repeatability (test-retest reliability. The first question for this study was whether the inconsistent results regarding the repeatability of the ANL test may be due to differences in speech material types used in previous studies. Second, it is unclear whether meaningfulness and semantic coherence of the speech modify ANL outcome. To investigate these questions, we compared ANLs obtained with three types of materials: the International Speech Test Signal (ISTS, which is non-meaningful and semantically non-coherent by definition, passages consisting of concatenated meaningful standard audiology sentences, and longer fragments taken from conversational speech. We included conversational speech as this type of speech material is most representative of everyday listening. Additionally, we investigated whether ANL outcomes, obtained with these three different speech materials, were associated with self-reported limitations due to hearing problems and listening effort in everyday life, as assessed by a questionnaire. ANL data were collected for 57 relatively good-hearing adult participants with an age range representative for hearing aid users. Results showed that meaningfulness, but not semantic coherence of the speech material affected ANL. Less noise was accepted for the non-meaningful ISTS signal than for the meaningful speech materials. ANL repeatability was

  5. Type of Speech Material Affects Acceptable Noise Level Test Outcome.

    Koch, Xaver; Dingemanse, Gertjan; Goedegebure, André; Janse, Esther

    2016-01-01

    The acceptable noise level (ANL) test, in which individuals indicate what level of noise they are willing to put up with while following speech, has been used to guide hearing aid fitting decisions and has been found to relate to prospective hearing aid use. Unlike objective measures of speech perception ability, ANL outcome is not related to individual hearing loss or age, but rather reflects an individual's inherent acceptance of competing noise while listening to speech. As such, the measure may predict aspects of hearing aid success. Crucially, however, recent studies have questioned its repeatability (test-retest reliability). The first question for this study was whether the inconsistent results regarding the repeatability of the ANL test may be due to differences in speech material types used in previous studies. Second, it is unclear whether meaningfulness and semantic coherence of the speech modify ANL outcome. To investigate these questions, we compared ANLs obtained with three types of materials: the International Speech Test Signal (ISTS), which is non-meaningful and semantically non-coherent by definition, passages consisting of concatenated meaningful standard audiology sentences, and longer fragments taken from conversational speech. We included conversational speech as this type of speech material is most representative of everyday listening. Additionally, we investigated whether ANL outcomes, obtained with these three different speech materials, were associated with self-reported limitations due to hearing problems and listening effort in everyday life, as assessed by a questionnaire. ANL data were collected for 57 relatively good-hearing adult participants with an age range representative for hearing aid users. Results showed that meaningfulness, but not semantic coherence of the speech material affected ANL. Less noise was accepted for the non-meaningful ISTS signal than for the meaningful speech materials. ANL repeatability was comparable across

  6. Electrical/instrumentation acceptance test report for Project C-018H, 242-A Evaporator/PUREX Plant condensate treatment facility

    This project is part of the 200 Area Effluent Treatment Facility. The acceptance test procedure describes test methods for leak detection units, pump flow switches, pump level control valves, room air temperature monitor, leachate pump status contacts, basin pump status contacts, catch basin leak detector, leachate level monitors, and basin level monitors. These are all components of the C-018H Collection System

  7. The Cloze Procedure as a Progress Test.

    Stansfield, Charles

    This paper reports on a pilot study conducted to determine the possible use of the cloze procedure as a substitute measure of achievement in a second-year Spanish culture and civilization class. Twenty students enrolled in a third-semester Spanish class at the University of Colorado were simultaneously given multiple choice tests and cloze tests…

  8. 40 CFR 91.607 - Test procedures.

    2010-07-01

    ... 40 Protection of Environment 20 2010-07-01 2010-07-01 false Test procedures. 91.607 Section 91.607 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) CONTROL OF EMISSIONS FROM MARINE SPARK-IGNITION ENGINES Selective Enforcement Auditing Regulations § 91.607...

  9. 40 CFR 89.508 - Test procedures.

    2010-07-01

    ... 40 Protection of Environment 20 2010-07-01 2010-07-01 false Test procedures. 89.508 Section 89.508 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) CONTROL OF EMISSIONS FROM NEW AND IN-USE NONROAD COMPRESSION-IGNITION ENGINES Selective Enforcement Auditing §...

  10. 40 CFR 90.508 - Test procedures.

    2010-07-01

    ... 40 Protection of Environment 20 2010-07-01 2010-07-01 false Test procedures. 90.508 Section 90.508 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) CONTROL OF EMISSIONS FROM NONROAD SPARK-IGNITION ENGINES AT OR BELOW 19 KILOWATTS Selective Enforcement Auditing §...

  11. Groebner Basis Procedures for Testing Petri Nets

    Chandler, Angie; Heyworth, Anne

    2000-01-01

    This paper contains introductory material on Petri nets and Groebner basis theory and makes some observations on the relation between the two areas. The aim of the paper is to show how Groebner basis procedures can be applied to the problem of reachability in Petri nets, and to give details of an application to testing models of navigational systems.

  12. Fair play in energy policy decisions: Procedural fairness, outcome fairness and acceptance of the decision to rebuild nuclear power plants

    To raise public acceptance of new energy policies, promoting the fairness of the outcomes and of the decision-making procedure has been suggested. Very few studies have examined the role of fairness in public acceptance of rebuilding nuclear power plants. Therefore, using a large mail survey, we investigated the public’s acceptance of the decision to rebuild nuclear power plants in Switzerland by 2020. The study examined the influence of procedural fairness and outcome fairness on the acceptance of this decision, as well as other factors such as risk perception and benefit perception. Additionally, we investigated the moderating influence of general attitudes towards nuclear power on the relation between fairness and decision acceptance. Results indicated that outcome fairness strongly increased decision acceptance, along with general attitudes towards nuclear power and perceived economic benefits. Procedural fairness had only a small impact on decision acceptance. The influence of fairness on decision acceptance did not seem to depend on general nuclear attitudes. Our findings imply that, in the case of rebuilding nuclear power plants, perceived benefits and outcome fairness are important determinants of acceptance of the decision, while procedural fairness only has a limited impact. - Highlights: ► We investigated the role of fairness in the acceptance of a nuclear policy decision. ► Outcome fairness strongly influenced decision acceptance regarding nuclear power plants. ► The role of procedural fairness was relatively small in this respect. ► Also, nuclear attitudes and perceived economic benefits affected decision acceptance. ► Outcome fairness seems more relevant for decision acceptance than procedural fairness.

  13. Report on COTECH test procedure and characterization techniques

    Islam, Mohammad Aminul

    .Characterization techniques and test procedure requirements for innovative self-ligating dental brackets (EO) Section 5.Characterization techniques and test procedure requirements for smart diagnostic chips comprising a microfluidic channel system (GBO) Section 6.Characterization techniques and test procedure...

  14. Acceptance tests of cryogenic components for SST-1

    The cryogenics system is one of the critical sub-systems in SST-1. The role of cryogenics systems is to facilitate the smooth cool-down, warm up and steady state operation as well as to take care about any abnormal events in safe mode during the operation. As a part of SST-1 machine shell, the cryogenics division is responsible for cold helium (at 4.5 K) and liquid nitrogen (at 77 K) hydraulics. This hydraulic network consists of headers, 80 K embossed shields, interconnecting loops, ceramic feed through at the vacuum barrier, flexible hoses and electrical breaks for cold helium as well as liquid nitrogen circuits. Before installation of individual components in SST-1, the performance validation tests were mandatory as part of mandatory stringent protocols fulfillment. The performance validation tests were conducted from individual components to integrated assembly level. In this paper, we report the essence of procedures followed and the performance test results. (author)

  15. Test marketing and consumer acceptance of irradiated meat products

    This study consists of two parts: irradiation processing of cooked meat and irradiation preservation of prepackaged chilled fresh cut meats. Irradiation of prepackaged pickled meat products dipped in grains stillage at a dose 6-8 kGy eliminated common food-borne microorganisms, such as E. Coli and other microbial pathogens and extended the shelf life of the product to 10 days at 5 deg. C. Test marketing of 40,000 bags (about 10,000 kg) of the product in more than 100 supermarkets in the city of Shanghai showed no untoward problem with consumer acceptance. Irradiation of prepackaged chilled fresh cut pork at a dose 3 kGy led to inactivation of microbial pathogens and parasites with a concomitant reduction in numbers of common spoilage microorganisms and extension of shelf life of the product for 30 days at 5 deg. C. The cost benefit and marketing applications were evaluated. (author)

  16. Acceptance test of graphite components in nuclear reactor

    The HTTR is the first high temperature gas-cooled reactor in Japan. It is a test reactor with thermal power of 30 MW and coolant outlet temperature of 950degC at maximum. To achieve high temperature coolant core internals were made of graphite and carbon materials due to their excellent thermal resistivity. After fabrication of graphite and carbon components at works they were installed in the HTTR, and now it is in the power up testing stage. Concerning the inspection standard of the graphite and carbon components, nondomestic standard exists as main components in the nuclear reactor. It is necessary, therefore, to prescribe the inspection standards for the HTTR graphite components. Many research and developments in relation to the inspection standard, e.g. in the research field of nondestructive examination of the graphite material, had been performed, and then the JAERI established the inspection standard. The acceptance test of the graphite and carbon components was carried out based on the inspection standard. This paper prescribes the outline of the established inspection standard. (author)

  17. 40 CFR 53.64 - Test procedure: Static fractionator test.

    2010-07-01

    ... sampler's operating manual referred to in section 7.4.18 of 40 CFR part 50, appendix L. (2) Generate... 40 Protection of Environment 5 2010-07-01 2010-07-01 false Test procedure: Static fractionator test. 53.64 Section 53.64 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)...

  18. Solar panel acceptance testing using a pulsed solar simulator

    Hershey, T. L.

    1977-01-01

    Utilizing specific parameters as area of an individual cell, number in series and parallel, and established coefficient of current and voltage temperature dependence, a solar array irradiated with one solar constant at AMO and at ambient temperature can be characterized by a current-voltage curve for different intensities, temperatures, and even different configurations. Calibration techniques include: uniformity in area, depth and time, absolute and transfer irradiance standards, dynamic and functional check out procedures. Typical data are given for individual cell (2x2 cm) to complete flat solar array (5x5 feet) with 2660 cells and on cylindrical test items with up to 10,000 cells. The time and energy saving of such testing techniques are emphasized.

  19. Acceptance test report, 241-SY-101 Flexible Receiver System, Phase 3 testing

    This document summarizes the results of the phase 3 acceptance test of the 241-SY-101 Flexible Receiver System (FRS). The purpose of this acceptance test is to verify the sealing integrity of the FRS to ensure that the release of waste and aerosols will be minimized during the removal of the test mixer pump from Tank 241-SY-101. The FRS is one of six major components of the Equipment Removal System, which has been designed to retrieve, transport, and store the mixer pump. This acceptance test was performed at the 306E Facility in the 300 area from January 10, 1995 to January 17, 1995. The Phase 3 test consisted of two parts. Part one was a water leak test of the seal between the blast shield and mock load distribution frame (LDF) to ensure that significant contamination of the pump pit and waste interaction with the aluminum impact-limiting material under the LDF are prevented during the pump removal operation. The second part of this acceptance test was an air leak test of the assembled flexible receiver system. The purpose of this test was to verify that the release of hazardous aerosols will be minimized if the tank dome pressure becomes slightly positive during the decontamination of the mixer pump

  20. 118-B-1 excavation treatability test procedures

    This treatability study has two purposes: to support development of the approach to be used for burial ground remediation, and to provide specific engineering information for the design of burial grounds receiving waste generated from the 100 Area removal actions. Data generated from this test will also provide performance and cost information necessary for detailed analysis of alternatives for burial ground remediation. Further details on the test requirements, milestones and data quality objectives are described in detail in the 118-B-1 Excavation Treatability Test Plan (DOE/RL-94-43). These working procedures are intended for use by field personnel to implement the requirements of the milestone. A copy of the detailed Test Plan will be kept on file at the on-site field support trailer, and will be available for review by field personnel

  1. Chemical Compatibility Testing Final Report Including Test Plans and Procedures

    This report provides an independent assessment of information on mixed waste streams, chemical compatibility information on polymers, and standard test methods for polymer properties. It includes a technology review of mixed low-level waste (LLW) streams and material compatibilities, validation for the plan to test the compatibility of simulated mixed wastes with potential seal and liner materials, and the test plan itself. Potential packaging materials were reviewed and evaluated for compatibility with expected hazardous wastes. The chemical and physical property measurements required for testing container materials were determined. Test methodologies for evaluating compatibility were collected and reviewed for applicability. A test plan to meet US Department of Energy and Environmental Protection Agency requirements was developed. The expected wastes were compared with the chemical resistances of polymers, the top-ranking polymers were selected for testing, and the most applicable test methods for candidate seal and liner materials were determined. Five recommended solutions to simulate mixed LLW streams are described. The test plan includes descriptions of test materials, test procedures, data collection protocols, safety and environmental considerations, and quality assurance procedures. The recommended order of testing to be conducted is specified

  2. Overcoming Denial through the Group: A Test of Acceptance Theory.

    Rugel, Robert P.; Barry, Denise

    1990-01-01

    Found participants (N=28) in alcohol treatment groups showed decreases in denial of drinking problems and decreases in psychopathology following 12 weeks of group counseling. Determined greater self-acceptance was associated with experiencing acceptance by group and with greater decreases in denial; decreases in denial and psychopathology were…

  3. Specification and acceptance testing of nuclear medicine equipment

    The purchase of nuclear medicine equipment is of prime importance in the operation of a clinical service. Failure to properly evaluate the potential uses of the instrumentation and the various operational characteristics of the equipment can often result in the purchase of inappropriate or inferior instruments. The magnitude of the purchase in terms of time and financial investments make it imperative that the purchase be approached in a systematic manner. Consideration of both the intended clinical functions and personnel requirements is important. It is necessary also to evaluate the ability of the equipment vendor to support the instrumentation after the purchase has been completed and the equipment installed in the clinical site. The desired specifications of the instrument characteristics should be stated in terms that can be verified by acceptance testing. The complexity of modern instrumentation and the sensitivity of it to the environment require the buyer to take into account the potential problems of controlling the temperature, humidity, and electrical power of the installation site. If properly and systematically approached, the purchase of new nuclear medicine instrumentation can result in the acquisition of a powerful diagnostic tool which will have a useful lifetime of many years. If not so approached, it may result in the expenditure of a large amount of money and personnel time without the concomitant return in useful clinical service. (author)

  4. Procedure guideline for radioiodine test. Version

    The version 2 of the procedure guideline for radioiodine test is an update of the guideline published in 1999. The following statements were added or modified: The procedure guideline discusses the pros and cons of a single measurement or of repeated measurements of the iodine-131 uptake and their optimal timing. Different formulas are described when one, two or three values of the radioiodine kinetic are available. The probe with a sodium iodide crystal, alternative or additionally the gamma-camera using the ROI-technique are instrumentations for the measurement of iodine-131 uptake. A possible source of error is an inappropriate measurement (sonography) of the target volume. The patients' preparation includes the withdrawal of antithyroid drugs 2-3 days before radioiodine administration. The patient has to avoid iodine-containing medication and the possibility of additives of iodide in vitamin- or electrolyte-supplementation has to be considered. (orig.)

  5. Procedure guideline for radioiodine test (version 3)

    The version 3 of the procedure guideline for radioiodine test is an update of the guideline previously published in 2003. The procedure guideline discusses the pros and cons of a single measurement or of repeated measurements of the iodine-131 uptake and their optimal timing. Different formulas are described when one, two or three values of the radioiodine kinetic are available. The probe with a sodium-iodine crystal, alternatively or additionally the gamma camera using the ROI-technique are instrumentations for the measurement of iodine-131 uptake. A possible source of error is an inappropriate measurement (sonography) of the target volume. The patients' preparation includes the withdrawal of antithyroid drugs 2-3 days before radioiodine administration. The patient has to avoid iodine-containing medication and the possibility of additives of iodine in vitamin- and electrolyte-supplementation has to be considered. (orig.)

  6. In situ vitrification large-scale operational acceptance test analysis

    A thermal treatment process is currently under study to provide possible enhancement of in-place stabilization of transuranic and chemically contaminated soil sites. The process is known as in situ vitrification (ISV). In situ vitrification is a remedial action process that destroys solid and liquid organic contaminants and incorporates radionuclides into a glass-like material that renders contaminants substantially less mobile and less likely to impact the environment. A large-scale operational acceptance test (LSOAT) was recently completed in which more than 180 t of vitrified soil were produced in each of three adjacent settings. The LSOAT demonstrated that the process conforms to the functional design criteria necessary for the large-scale radioactive test (LSRT) to be conducted following verification of the performance capabilities of the process. The energy requirements and vitrified block size, shape, and mass are sufficiently equivalent to those predicted by the ISV mathematical model to confirm its usefulness as a predictive tool. The LSOAT demonstrated an electrode replacement technique, which can be used if an electrode fails, and techniques have been identified to minimize air oxidation, thereby extending electrode life. A statistical analysis was employed during the LSOAT to identify graphite collars and an insulative surface as successful cold cap subsidence techniques. The LSOAT also showed that even under worst-case conditions, the off-gas system exceeds the flow requirements necessary to maintain a negative pressure on the hood covering the area being vitrified. The retention of simulated radionuclides and chemicals in the soil and off-gas system exceeds requirements so that projected emissions are one to two orders of magnitude below the maximum permissible concentrations of contaminants at the stack

  7. Social trust, risk perceptions and public acceptance of recycled water: testing a social-psychological model.

    Ross, Victoria L; Fielding, Kelly S; Louis, Winnifred R

    2014-05-01

    Faced with a severe drought, the residents of the regional city of Toowoomba, in South East Queensland, Australia were asked to consider a potable wastewater reuse scheme to supplement drinking water supplies. As public risk perceptions and trust have been shown to be key factors in acceptance of potable reuse projects, this research developed and tested a social-psychological model of trust, risk perceptions and acceptance. Participants (N = 380) were surveyed a few weeks before a referendum was held in which residents voted against the controversial scheme. Analysis using structural equation modelling showed that the more community members perceived that the water authority used fair procedures (e.g., consulting with the community and providing accurate information), the greater their sense of shared identity with the water authority. Shared social identity in turn influenced trust via increased source credibility, that is, perceptions that the water authority is competent and has the community's interest at heart. The findings also support past research showing that higher levels of trust in the water authority were associated with lower perceptions of risk, which in turn were associated with higher levels of acceptance, and vice versa. The findings have a practical application for improving public acceptance of potable recycled water schemes. PMID:24603028

  8. Dispersant testing : a study on analytical test procedures

    Crude oil is a complex mixture of hydrocarbons, ranging from small, volatile compounds to very large, non-volatile compounds. Analysis of the dispersed oil is crucial. This paper described Environment Canada's ongoing studies on various traits of dispersants. In particular, it describes small studies related to dispersant effectiveness and methods to improve analytical procedures. The study also re-evaluated the analytical procedure for the Swirling Flask Test, which is now part of the ASTM standard procedure. There are new and improved methods for analyzing oil-in-water using gas chromatography (GC). The methods could be further enhanced by integrating the entire chromatogram rather than just peaks. This would result in a decrease in maximum variation from 5 per cent to about 2 per cent. For oil-dispersant studies, the surfactant-dispersed oil hydrocarbons consist of two parts: GC-resolved hydrocarbons and GC-unresolved hydrocarbons. This study also tested a second feature of the Swirling Flask Test in which the side spout was tested and compared with a new vessel with a septum port instead of a side spout. This decreased the variability as well as the energy and mixing in the vessel. Rather than being a variation of the Swirling Flask Test, it was suggested that a spoutless vessel might be considered as a completely separate test. 7 refs., 2 tabs., 4 figs

  9. Comparison of acceptance, preference and efficacy between pressure anesthesia and classical needle infiltration anesthesia for dental restorative procedures in adult patients

    Chetana Sachin Makade

    2014-01-01

    Full Text Available Introduction: Intraoral local anesthesia is essential for delivering dental care. Needless devices have been developed to provide anesthesia without injections. Little controlled research is available on its use in dental restorative procedures in adult patients. The aims of this study were to compare adult patients acceptability and preference for needleless jet injection with classical local infiltration as well as to evaluate the efficacy of the needleless anesthesia. Materials and Methods: Twenty non fearful adults with no previous experience of dental anesthesia were studied using split-mouth design. The first procedure was performed with classical needle infiltration anesthesia. The same amount of anesthetic solution was administered using MADA jet needleless device in a second session one week later, during which a second dental restorative procedure was performed. Patients acceptance was assessed using Universal pain assessment tool while effectiveness was recorded using soft tissue anesthesia and pulpal anesthesia. Patients reported their preference for the anesthetic method at the third visit. The data was evaluated using chi square test and student′s t-test. Results: Pressure anesthesia was more accepted and preferred by 70% of the patients than traditional needle anesthesia (20%. Both needle and pressure anesthesia was equally effective for carrying out the dental procedures. Conclusion: Patients experienced significantly less pain and fear (p<0.01 during anesthetic procedure with pressure anesthesia. However, for more invasive procedures needle anesthesia will be more effective.

  10. 49 CFR 232.505 - Pre-revenue service acceptance testing plan.

    2010-10-01

    ... 49 Transportation 4 2010-10-01 2010-10-01 false Pre-revenue service acceptance testing plan. 232... § 232.505 Pre-revenue service acceptance testing plan. (a) General; submission of plan. Except as... its system the operating railroad or railroads shall submit a pre-revenue service acceptance...

  11. 7 CFR 1755.400 - RUS standard for acceptance tests and measurements of telecommunications plant.

    2010-01-01

    ... 7 Agriculture 11 2010-01-01 2010-01-01 false RUS standard for acceptance tests and measurements of telecommunications plant. 1755.400 Section 1755.400 Agriculture Regulations of the Department of Agriculture..., ACCEPTABLE MATERIALS, AND STANDARD CONTRACT FORMS § 1755.400 RUS standard for acceptance tests...

  12. Acceptance test report, 241-SY-101 Flexible Receiver System, Phase 2 testing

    This document summarizes the results of the Phase 2 acceptance test of the 241-SY-101 Flexible Receiver System (FRS). The FRS is one of six major components of the Equipment Removal System, which has been designed to retrieve, transport, and store the test mixer pump currently installed in Tank 241-SY-101. The purpose of this acceptance test is to verify the strength of the containment bag and bag bottom cinching mechanism. It is postulated that 68 gallons of waste could be trapped inside the pump internals. The bag must be capable of supporting this waste if it shakes loose and drains to the bottom of the bag after the bag bottom has been cinched closed. This acceptance test was performed at the Maintenance and Storage Facility (MASF) Facility in the 400 area on January 23, 1995. The bag assembly supported the weight of 920 kg (2,020 lbs) of water with no leakage or damage to the bag. This value meets the acceptance criteria of 910 kg of water and therefore the results were found to be acceptable. The maximum volume of liquid expected to be held up in the pump internals is 258 L (68 gallons), which corresponds to 410 kg. This test weight gives just over a safety factor of 2. The bag also supported a small shock load while it was filled with water when the crane hoisted the bag assembly up and down. Based on the strength rating of the bag components, the bag assembly should support 2--3 times the test weight of 910 kg

  13. Utility-Scale Parabolic Trough Solar Systems: Performance Acceptance Test Guidelines, April 2009 - December 2010

    Kearney, D.

    2011-05-01

    Prior to commercial operation, large solar systems in utility-size power plants need to pass a performance acceptance test conducted by the engineering, procurement, and construction (EPC) contractor or owners. In lieu of the present absence of ASME or other international test codes developed for this purpose, the National Renewable Energy Laboratory has undertaken the development of interim guidelines to provide recommendations for test procedures that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. The Guidelines contained here are specifically written for parabolic trough collector systems with a heat-transport system using a high-temperature synthetic oil, but the basic principles are relevant to other CSP systems.

  14. The Careful Puppet Master: Reducing risk and fortifying acceptance testing with Jenkins CI

    Smith, Jason A.; Richman, Gabriel; DeStefano, John; Pryor, James; Rao, Tejas; Strecker-Kellogg, William; Wong, Tony

    2015-12-01

    Centralized configuration management, including the use of automation tools such as Puppet, can greatly increase provisioning speed and efficiency when configuring new systems or making changes to existing systems, reduce duplication of work, and improve automated processes. However, centralized management also brings with it a level of inherent risk: a single change in just one file can quickly be pushed out to thousands of computers and, if that change is not properly and thoroughly tested and contains an error, could result in catastrophic damage to many services, potentially bringing an entire computer facility offline. Change management procedures can—and should—be formalized in order to prevent such accidents. However, like the configuration management process itself, if such procedures are not automated, they can be difficult to enforce strictly. Therefore, to reduce the risk of merging potentially harmful changes into our production Puppet environment, we have created an automated testing system, which includes the Jenkins CI tool, to manage our Puppet testing process. This system includes the proposed changes and runs Puppet on a pool of dozens of RedHat Enterprise Virtualization (RHEV) virtual machines (VMs) that replicate most of our important production services for the purpose of testing. This paper describes our automated test system and how it hooks into our production approval process for automatic acceptance testing. All pending changes that have been pushed to production must pass this validation process before they can be approved and merged into production.

  15. Project W-314 acceptance test report HNF-4651 for HNF-4650 SN-268 encasement leak detection ANA-WT-LDSTA-335 for project W-314

    The purpose of the test was to verify that the AN Tank Farm Encasement Leak Detector components are functionally integrated and operate in accordance with engineering design specifications The Acceptance Test Procedure HNF-4650, SN-268 Encasement Leak Detection ANA-W-LDSTA-335, was conducted between 22 June and 01 July 1999 at the 200E AN Tank Farm. The test has been completed with no open test exceptions The test was conducted prior to final engineering ''as built'' activities being completed this had no impact on the procedure or test results. All components, identified in the procedure, were found to be labeled and identified as written in the procedure

  16. A data base and a standard material for use in acceptance testing of low-activity waste products

    The authors have conducted replicate dissolution tests following the product consistency test (PCT) procedure to measure the mean and standard deviation of the solution concentrations of B, Na, and Si at various combinations of temperature, duration, and glass/water mass ratio. Tests were conducted with a glass formulated to be compositionally similar to low-activity waste products anticipated for Hanford to evaluate the adequacy of test methods that have been designated in privatization contracts for use in product acceptance. An important finding from this set of tests is that the solution concentrations generated in tests at 20 C will likely be too low to measure the dissolution rates of waste products reliably. Based on these results, the authors recommend that the acceptance test be conducted at 40 C. Tests at 40 C generated higher solution concentrations, were more easily conducted, and the measured rates were easily related to those at 20 C. Replicate measurements of other glass properties were made to evaluate the possible use of LRM-1 as a standard material. These include its composition, homogeneity, density, compressive strength, the Na leachability index with the ANSI/ANS 16.1 leach test, and if the glass is characteristically hazardous with the toxicity characteristic leach procedure. The values of these properties were within the acceptable limits identified for Hanford low-activity waste products. The reproducibility of replicate tests and analyses indicates that the glass would be a suitable standard material

  17. Laboratory procedures for waste form testing

    Mast, E.S.

    1994-09-19

    The 100 and 300 areas of the Hanford Site are included on the US Environmental Protection Agencies (EPA) National Priorities List under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Soil washing is a treatment process that is being considered for the remediation of the soil in these areas. Contaminated soil washing fines can be mixed or blended with cementations materials to produce stable waste forms that can be used for beneficial purposes in mixed or low-level waste landfills, burial trenches, environmental restoration sites, and other applications. This process has been termed co-disposal. The Co-Disposal Treatability Study Test Plan is designed to identify a range of cement-based formulations that could be used in disposal efforts in Hanford in co-disposal applications. The purpose of this document is to provide explicit procedural information for the testing of co-disposal formulations. This plan also provides a discussion of laboratory safety and quality assurance necessary to ensure safe, reproducible testing in the laboratory.

  18. Laboratory procedures for waste form testing

    The 100 and 300 areas of the Hanford Site are included on the US Environmental Protection Agencies (EPA) National Priorities List under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Soil washing is a treatment process that is being considered for the remediation of the soil in these areas. Contaminated soil washing fines can be mixed or blended with cementations materials to produce stable waste forms that can be used for beneficial purposes in mixed or low-level waste landfills, burial trenches, environmental restoration sites, and other applications. This process has been termed co-disposal. The Co-Disposal Treatability Study Test Plan is designed to identify a range of cement-based formulations that could be used in disposal efforts in Hanford in co-disposal applications. The purpose of this document is to provide explicit procedural information for the testing of co-disposal formulations. This plan also provides a discussion of laboratory safety and quality assurance necessary to ensure safe, reproducible testing in the laboratory

  19. Acceptance tests for electrometers used in radiotherapy; Pruebas de aceptacion para electrometros usados en radioterapia

    Moreno-Torres, M.; Tornero-Lopez, A. M.; Ruiz-Arrebola, S.; Guirado, D.; Vilches, M.

    2015-05-01

    We present a set of tests designed to check the compliance of the requirements established in the standard IEC 60731:19972 and TRS 3981 technical report for reference class electrometers using the material normally available in a medical physics department. The characteristics under exam are: stability in the start-up, zero shift, zero drift, leakage current, linearity and repeatability. The method is applied to 4 electrometers: PTW UNIDOS, Sun Nuclear PC-Electrometer, Scanditronix-Wellhofer DOSE1 and Standard Imaging MAX4000. We checked that the electrometers comply with the requirements, although we detected some differences in the performance between them. The method proved itself precise enough and efficient to provide with reliable results for these tests and we consider it could be used to establish an internal procedure for the acceptance of this kind of equipment. (Author)

  20. Evaluation of a standard test method and material for low-activity waste product acceptance

    The dissolution behavior of a candidate reference glass has been measured under a range of test conditions. The data base from these tests can be used to evaluate the credibility and validity of test results reported by Private Contractors as part of the acceptance process for immobilized low-activity waste (ILAW) products for DOE wastes. The LRM-1 glass that was used in the tests was formulated to be compositionally representative of anticipated ILAW products for Hanford and other Department of Energy sites. Replicate tests with this glass were used to measure the variability in the response (i.e., the solution concentrations of B, Na, and Si) under different test conditions. The glass was further evaluated for possible use as a standard material by analysis of its composition, microstructure, density, and compressive strength. In addition, the Na leachability index was measured with the ANS 16.1 test, and the Toxicity Characteristic Leach Procedure was run. The results of those tests and analyses are summarized

  1. For your interest? The ethical acceptability of using non-invasive prenatal testing to test 'purely for information'.

    Deans, Zuzana; Clarke, Angus J; Newson, Ainsley J

    2015-01-01

    Non-invasive prenatal testing (NIPT) is an emerging form of prenatal genetic testing that provides information about the genetic constitution of a foetus without the risk of pregnancy loss as a direct result of the test procedure. As with other prenatal tests, information from NIPT can help to make a decision about termination of pregnancy, plan contingencies for birth or prepare parents to raise a child with a genetic condition. NIPT can also be used by women and couples to test purely 'for information'. Here, no particular action is envisaged following the test; it is motivated entirely by an interest in the result. The fact that NIPT can be performed without posing a risk to the pregnancy could give rise to an increase in such requests. In this paper, we examine the ethical aspects of using NIPT 'purely for information', including the competing interests of the prospective parents and the future child, and the acceptability of testing for 'frivolous' reasons. Drawing on several clinical scenarios, we claim that arguments about testing children for genetic conditions are relevant to this debate. In addition, we raise ethical concerns over the potential for objectification of the child. We conclude that, in most cases, using NIPT to test for adult-onset conditions, carrier status or non-serious traits presenting in childhood would be unacceptable. PMID:25521970

  2. School age test or procedure preparation

    ... may be able to identify concerns through your child's art. DURING THE PROCEDURE If the procedure is performed at the hospital or at your child's health care provider's office, you will most likely ...

  3. 40 CFR 401.13 - Test procedures for measurement.

    2010-07-01

    ... 40 Protection of Environment 28 2010-07-01 2010-07-01 true Test procedures for measurement. 401.13... AND STANDARDS GENERAL PROVISIONS § 401.13 Test procedures for measurement. The test procedures for measurement which are prescribed at part 136 of this chapter shall apply to expressions of pollutant...

  4. SU-E-P-46: Clinical Acceptance Testing and Implementation of a Portable CT Unit

    Purpose: Planning for the first installation in New England of a new portable CT unit to be used in the Operating Room required the integration of many departments including Surgery, Neurosurgery, Information Services, Clinical Engineering, Radiology and Medical Physics/Radiation Safety. Acceptance testing and the quality assurance procedures were designed to optimize image quality and patient and personnel radiation exposure. Methods: The vendor’s protocols were tested using the CT Dosimetry phantoms. The system displayed the CTDIw instead of the CTDIvol while testing the unit. Radiation exposure was compared to existing CT scanners from installed CT units throughout the facility. Brainlab measures all 4 periphery slots on the CT Dosimetry phantom. The ACR measures only the superior slot for the periphery measurement. A comprehensive radiation survey was also performed for several locations. Results: The CTDIvol measurements were comparable for the following studies: brain, C-Spine, and sinuses. However, the mobile CT measurements were slightly higher than other CT units but within acceptable tolerance if measured using the ACR method.Based on scatter measurements, it was determined if any personnel were to stay in the OR Suite during image acquisition that the appropriate lead apron and thyroid shields had to be worn.In addition, to reduce unnecessary scatter, there were two mobile 6 foot wide shields (1/16″ lead equivalent) available to protect personnel in the room and adjacent areas. Conclusion: Intraoperative CT provides the physician new opportunities for evaluation of the progression of surgical resections and device placement at the cost of increasing the amount of trained personnel required to perform this procedure. It also brings with it challenges to keep the radiation exposure to the patients and staff within reasonable limits

  5. SU-E-P-46: Clinical Acceptance Testing and Implementation of a Portable CT Unit

    LaFrance, M; Marsh, S; Hicks, R; O’Donnell-Moran, G [Baystate Health Systems, Inc., Springfield, MA (United States)

    2015-06-15

    Purpose: Planning for the first installation in New England of a new portable CT unit to be used in the Operating Room required the integration of many departments including Surgery, Neurosurgery, Information Services, Clinical Engineering, Radiology and Medical Physics/Radiation Safety. Acceptance testing and the quality assurance procedures were designed to optimize image quality and patient and personnel radiation exposure. Methods: The vendor’s protocols were tested using the CT Dosimetry phantoms. The system displayed the CTDIw instead of the CTDIvol while testing the unit. Radiation exposure was compared to existing CT scanners from installed CT units throughout the facility. Brainlab measures all 4 periphery slots on the CT Dosimetry phantom. The ACR measures only the superior slot for the periphery measurement. A comprehensive radiation survey was also performed for several locations. Results: The CTDIvol measurements were comparable for the following studies: brain, C-Spine, and sinuses. However, the mobile CT measurements were slightly higher than other CT units but within acceptable tolerance if measured using the ACR method.Based on scatter measurements, it was determined if any personnel were to stay in the OR Suite during image acquisition that the appropriate lead apron and thyroid shields had to be worn.In addition, to reduce unnecessary scatter, there were two mobile 6 foot wide shields (1/16″ lead equivalent) available to protect personnel in the room and adjacent areas. Conclusion: Intraoperative CT provides the physician new opportunities for evaluation of the progression of surgical resections and device placement at the cost of increasing the amount of trained personnel required to perform this procedure. It also brings with it challenges to keep the radiation exposure to the patients and staff within reasonable limits.

  6. Eddy current testing on structures of nuclear-grade PGX graphite for acceptance test in HTTR

    Acceptance test with eddy current testing is planned to be applied to the core support graphite structures made of PGX graphite, nuclear-grade near-isotropic graphite, in the HTTR. The eddy current testing widely applied to metallic components is not applicable to porous graphite materials due to different characteristics compared with metallic ones. Hence, the eddy current testing method for the fine-grained, nuclear-grade IG-110 graphite had been established. However, this method is also not applicable to the PGX graphite owing to the different flaw detectability because the PGX consists of larger grains and pores than the IG-110. Therefore the eddy current testing method and condition for the PGX graphite were established on the bases of the experimental investigation. (author)

  7. Formulation of a candidate glass for use as an acceptance test standard material

    In this report, the authors discuss the formulation of a glass that will be used in a laboratory testing program designed to measure the precision of test methods identified in the privatization contracts for the immobilization of Hanford low-activity wastes. Tests will be conducted with that glass to measure the reproducibility of tests and analyses that must be performed by glass producers as a part of the product acceptance procedure. Test results will be used to determine if the contractually required tests and analyses are adequate for evaluating the acceptability of likely immobilized low-activity waste (ILAW) products. They will also be used to evaluate if the glass designed for use in these tests can be used as an analytical standard test material for verifying results reported by vendors for tests withg ILAW products. The results of those tests and analyses will be presented in a separate report. The purpose of this report is to document the strategy used to formulate the glass to be used in the testing program. The low-activity waste reference glass LRM that will be used in the testing program was formulated to be compositionally similar to ILAW products to be made with wastes from Hanford. Since the ILAW product compositions have not been disclosed by the vendors participating in the Hanford privatization project, the composition of LRM was formulated based on simulated Hanford waste stream and amounts of added glass forming chemicals typical for vitrified waste forms. The major components are 54 mass % SiO2, 20 mass % Na2O, 10 mass % Al2O3, 8 mass % B2O3, and 1.5 mass % K2O. Small amounts of other chemicals not present in Hanford wastes were also included in the glass, since they may be included as chemical additives in ILAW products. This was done so that the use of LRM as a composition standard could be evaluated. Radionuclides were not included in LRM because a nonradioactive material was desired

  8. Project W-151 flexible receiver radiation detector system acceptance test plan. Revision 1

    The attached document is the Acceptance Test Plan for the portion of Project W-151 dealing with acceptance of gamma-ray detectors and associated electronics manufactured at the Idaho National Engineering Laboratory (INEL). The document provides a written basis for testing the detector system, which will take place in the 305 building (300 Area)

  9. 49 CFR 238.111 - Pre-revenue service acceptance testing plan.

    2010-10-01

    ... 49 Transportation 4 2010-10-01 2010-10-01 false Pre-revenue service acceptance testing plan. 238... and General Requirements § 238.111 Pre-revenue service acceptance testing plan. (a) Passenger equipment that has previously been used in revenue service in the United States. For passenger...

  10. Determining the acceptance of the Brookhaven EBIS Test Stand for primary ions by computer simulation

    We report on computer studies to determine the acceptance of the Electron Beam Ion Source Test Stand (EBTS) at BNL. Knowledge of the acceptance is a useful guide in selecting a source of primary ions, and in designing a transfer line which best matches the primary ion beam to the acceptance of the EBTS. In this work, an ion beam with suitable parameters is tracked out of the EBIS, to a plane where knowledge of the acceptance is wanted. The emittance of the extracted beam in this plane gives a starting point for determining a more reliable value of acceptance. The result will be compared with a theoretical estimate

  11. A review of acceptance testing of the Los Alamos, Canberra Alpha Sentry Continuous Air Monitor (CAM)

    Los Alamos National Laboratory (LANL) undertook the design and development of a new generation of alpha continuous air monitor (CAM) instrumentation that would incorporate advanced technologies in the design of the sampling inlet, multi-channel analyzer (MCA) electronics, solid state alpha detectors, radon background interference suppression, background interference compensation and based on spectral analysis, and microcomputer based data communication, processing, storage, and retrieval. The ANSI air monitoring instrument standards (Performance Specifications for Health Physics Instrumentation -- Occupational Airborne Radioactivity Monitoring Instrumentation, N42.17B) specify performance criteria and testing procedures for instruments and instrument systems designed to continuously sample and quantify airborne radioactivity in the workplace. Although the intent of the standard is to provide performance testing criteria for type testing, it is appropriate to evaluate the performance of a new instrument such as the Alpha Sentry against certain of these criteria for purposes of an acceptance test based on stated specifications and the Los Alamos CAM Requirements document. This report provides an overview of the results of these tests, as they pertain to instruments designed to detect alpha-emitting radionuclides in particulate form

  12. Project B610 process control configuration acceptance test report

    The purpose of this test is to verify the Westinghouse configuration of the MICON A/S Distributed Control System for project B610. The following will be verified: (1) proper assignment and operation of all field inputs to and outputs from the MICON Termination panels; (2) proper operation of all display data on the operators' console; (3) proper operation of all required alarms; and (4) proper operation of all required interlocks. This test only verifies the proper operation of the Westinghouse control configuration (or program). It will not be responsible for verifying proper operation of the MICON hardware or operating software. Neither does it test any of the B610 instrument. The MICON hardware and software has been tested as part of the equipment procurement. Instrumentation and wiring installed under project B620 will be tested under a separate functional test. In some cases, precise transmitter ranges, alarm setpoints, and controller tuning parameters are not available at this time. Therefore, approximate values are used during the test. This should not affect the proper operation of the configuration or the validity of this test. Final values will be assigned during operability testing

  13. Acceptance test report for the 241-SY-101 Flexible Receiver Gamma Detector System

    This Acceptance Test Report is for the 241-SY-101 Flexible Receiver Gamma Detector System. This test verified that the data logger and data converter for the gamma detector system functions as intended

  14. Test and acceptance from the AE point of view

    The power industry has undergone the transition from utilizing construction engineers for startup activities to utilizing test engineers who are responsible for the preparation or execution of a formal test program. This has come about because testing has been given sufficient importance to justify those participating within the industry to establish it as a specialty phase apart from engineering/design and construction. Presently testing is being conducted by those organizations that have either engineered and/or constructed the unit which may be a position of conflict in regards to unbiased test. The tester (third party) concept promotes the repetition, independence, and expertise of a test organization responsible to the utility for certifying that each system has been tested to the design criteria established by others. A move to this concept should result in better generating stations with higher availability because it has been completely tested by an organization with this sole contractual responsibility. The AE, NSSS, and utility would all benefit with possibly no additional costs incurred

  15. 49 CFR 572.123 - Neck assembly and test procedure.

    2010-10-01

    ... 49 Transportation 7 2010-10-01 2010-10-01 false Neck assembly and test procedure. 572.123 Section...-year-old Child Test Dummy, Beta Version § 572.123 Neck assembly and test procedure. (a) The neck... extension tests, measured by an accelerometer mounted on the pendulum as shown in Figure 22 of 49 CFR 572...

  16. Community acceptability of use of rapid diagnostic tests for malaria by community health workers in Uganda

    Waiswa Peter

    2010-07-01

    Full Text Available Abstract Background Many malarious countries plan to introduce artemisinin combination therapy (ACT at community level using community health workers (CHWs for treatment of uncomplicated malaria. Use of ACT with reliance on presumptive diagnosis may lead to excessive use, increased costs and rise of drug resistance. Use of rapid diagnostic tests (RDTs could address these challenges but only if the communities will accept their use by CHWs. This study assessed community acceptability of the use of RDTs by Ugandan CHWs, locally referred to as community medicine distributors (CMDs. Methods The study was conducted in Iganga district using 10 focus group discussions (FGDs with CMDs and caregivers of children under five years, and 10 key informant interviews (KIIs with health workers and community leaders. Pre-designed FGD and KII guides were used to collect data. Manifest content analysis was used to explore issues of trust and confidence in CMDs, stigma associated with drawing blood from children, community willingness for CMDs to use RDTs, and challenges anticipated to be faced by the CMDs. Results CMDs are trusted by their communities because of their commitment to voluntary service, access, and the perceived effectiveness of anti-malarial drugs they provide. Some community members expressed fear that the blood collected could be used for HIV testing, the procedure could infect children with HIV, and the blood samples could be used for witchcraft. Education level of CMDs is important in their acceptability by the community, who welcome the use of RDTs given that the CMDs are trained and supported. Anticipated challenges for CMDs included transport for patient follow-up and picking supplies, adults demanding to be tested, and caregivers insisting their children be treated instead of being referred. Conclusion Use of RDTs by CMDs is likely to be acceptable by community members given that CMDs are properly trained, and receive regular technical

  17. Record and Verify Systems for Radiation Treatment of Cancer: Acceptance Testing, Commissioning and Quality Control

    Quality assurance (QA) in the radiation therapy treatment planning and delivery process is essential to ensure accurate dose delivery to the patient and to minimize the possibility of accidental exposure. To support this, computerized record and verify systems (RVSs) are now widely available in both industrialized and low and middle income countries. Recent publications of errors in radiation therapy have demonstrated that the lack of proper QA procedures for RVSs can result in severe accidents, including death, as a result of accidental exposure. Furthermore, the use of RVSs can have a higher risk of repeated errors due to a false sense of security out of belief that a computerized RVS will generate safer treatment procedures. It is widely acknowledged that there are very few reports in the peer reviewed literature and no guidance documents available that professionals can follow for a systematic verification of all functionalities of RVSs and their related interfaces with imaging systems, treatment planning computers and treatment delivery systems. The need to develop specific guidelines for acceptance testing, commissioning and quality control of RVSs has been identified through the increased interest of Member States in efficient and safe radiotherapy treatment. To meet this need, the IAEA has convened several consultants meetings to prepare a publication for establishing QA for RVSs. A draft report was generated by the consultants and was submitted for review by manufacturers of RVSs. Furthermore, the draft report was field tested at the General Hospital (Allgemeines Krankenhaus) in Vienna, Austria. The comments of the manufacturers and field testing were incorporated in the revised document where appropriate. This report is intended mainly for radiotherapy medical physicists, but the information is also useful for radiation oncologists and therapy radiographers working in radiotherapy hospitals. In addition, the guidance given in this report is highly

  18. CSI computer system/remote interface unit acceptance test results

    Sparks, Dean W., Jr.

    1992-01-01

    The validation tests conducted on the Control/Structures Interaction (CSI) Computer System (CCS)/Remote Interface Unit (RIU) is discussed. The CCS/RIU consists of a commercially available, Langley Research Center (LaRC) programmed, space flight qualified computer and a flight data acquisition and filtering computer, developed at LaRC. The tests were performed in the Space Structures Research Laboratory (SSRL) and included open loop excitation, closed loop control, safing, RIU digital filtering, and RIU stand alone testing with the CSI Evolutionary Model (CEM) Phase-0 testbed. The test results indicated that the CCS/RIU system is comparable to ground based systems in performing real-time control-structure experiments.

  19. The Northern Regional Programme for the acceptance testing of X-ray equipment

    Since 1984 the Regional Medical Physics Department has participated in a regional acceptance testing programme for all X-ray equipment from mobile units to computed tomography scanners. The organizational and radiation physics aspects of the programme are described. Three levels of tests are performed by physicists: the first on installation, the second after 3 months, and the final visit just prior to the end of the manufacturer's warranty. The second test is only performed if any aspect of performance requires rechecking as a result of the first visit. Acceptance test protocols are based on those published by the Institute of Physical Sciences in Medicine. Details of the limiting values for the acceptance test measurements are given. The results of the programme are discussed. In some instances the testing has resulted in modifications to the design and construction of X-ray equipment. Acceptance testing is important in determining a baseline standard of performance against which routine quality assurance may be assessed. (author)

  20. Acceptance tests of the BEPC II RF transmitter and the circulator

    The high power RF transmitter and the circulator with 500 MHz/250 kW which will be operated in Beijing Electron-Positron Collider Upgrade (BEPC II) project have been installed on site, and adjustments and acceptance test have been finished, which is the first transmitter system of 500 MHz/250 kW in China. In this paper, the test principle and all measurements as well as commissioning result in the acceptance test are introduced in details, and the actual machine technical parameters and performance are presented. An acceptance test conclusion by comparing with the design requirements is given. (authors)

  1. Evaluation of test procedures for hydrogen environment embrittlement

    Nelson, H. G.

    1974-01-01

    Report presents discussion of three common and primary influences on embrittlement process. Application of theoretical considerations to design of test coupons and methods is illustrated for both internal and external hydrogen embrittlement. Acceptable designs and methods are indicated.

  2. A Procedure for Uncovering Acceptable and Nonacceptable Mortgage Applications through Discriminant Analysis Using Ranked Data

    Larry G. Perry; Timothy P. Cronan; Donald A. Epley

    1987-01-01

    The procedure developed in this paper uses a less biased statistical technique than conventional discriminant analysis and parallels the ranking procedure used by loan officers. A variety of univariate and multivariate statistical procedures as well as comprehensive validation methods are used to develop a "best" model. The resulting model provides more accurate classification than other studies have shown, without violating federal law regarding discrimination.

  3. Acceptance test report for the Tank 241-C-106 in-tank imaging system

    This document presents the results of Acceptance Testing of the 241-C-106 in-tank video camera imaging system. The purpose of this imaging system is to monitor the Project W-320 sluicing of Tank 241-C-106. The objective of acceptance testing of the 241-C-106 video camera system was to verify that all equipment and components function in accordance with procurement specification requirements and original equipment manufacturer's (OEM) specifications. This document reports the results of the testing

  4. 46 CFR 61.40-10 - Test procedure details.

    2010-10-01

    ... 46 Shipping 2 2010-10-01 2010-10-01 false Test procedure details. 61.40-10 Section 61.40-10 Shipping COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED) MARINE ENGINEERING PERIODIC TESTS AND... details. (a) Test procedure documents must be in a step-by-step or checkoff list format. Each...

  5. 40 CFR 60.123 - Test methods and procedures.

    2010-07-01

    ... 40 Protection of Environment 6 2010-07-01 2010-07-01 false Test methods and procedures. 60.123 Section 60.123 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS... Smelters § 60.123 Test methods and procedures. (a) In conducting the performance tests required in §...

  6. Test report for run-in acceptance testing of hydrogen mitigation test pump-2

    This document provides the results of the run-in test of the replacement mixer pump for the Tank 241-SY-101. The test was conducted at the 400 Area MASF facility between August 12 and September 29, 1994. The report includes findings, analysis, recommendations, and corrective actions taken

  7. TMACS test procedure TP012: Panalarm software bridge

    This Test Procedure addresses the testing of the functionality of the Tank Monitor and Control System (TMACS) Panalarm bridge software. The features to be tested are: Bridge Initialization Options; Bridge Communication; Bridge Performance; Testing Checksum Errors; and Testing Command Reject Errors. Only the first three could be tested; the last two have been deferred to a later date

  8. Acceptance of Genetic Testing in a General Population: Age, Education and Gender Differences.

    Aro, A. R.; Hakonen, A.; Hietala, M.; Lonnqvist, J.; Niemela, P.; Peltonen, L; Aula, P.

    1997-01-01

    Effects of age, education, and gender on acceptance of genetic testing were studied. Finnish participants responded to a questionnaire presenting reasons for and against genetic testing (N=1,967). Intentions to take genetic tests, worries, and experience of genetic test or hereditary disease were also assessed. Results are presented and discussed.…

  9. Acceptance Test Report for the high pressure water jet system canister cleaning fixture

    This Acceptance Test confirmed the test results and recommendations, documented in WHC-SD-SNF-DTR-001, Rev. 0 Development Test Report for the High Pressure Water Jet System Nozzles, for decontaminating empty fuel canisters in KE-Basin. Optimum water pressure, water flow rate, nozzle size and overall configuration were tested

  10. Affect and technology acceptance: A test of two mechanisms

    Scholderer, Joachim; Grunert, Klaus G.; Søndergaard, Helle Alsted

    Commercialization of new technologies may be hampered by stakeholder resistance and a sceptical public. Genetic modification (GM) has suffered particularly from such problems. At present, for example, practically no products exist on the shelves of European retailers that are labelled as containing...... resistant to all forms of communicative interventions. A study is presented in which the effectiveness and mechanisms of direct-experience interventions are experimentally tested. Results indicate that the positive affect evoked by a single trial of a high-quality genetically modified food can lead to...... practice, focusing on point-of-sale promotions that could be the key element in the launch of the first genetically modified foods in markets that are as yet GM-free....

  11. 40 CFR 60.285 - Test methods and procedures.

    2010-07-01

    ... rate correction factor, integrated sampling and analysis procedure of Method 3B shall be used to... factor, integrated sampling and analysis procedure of Method 3B shall be used to determine the oxygen... 40 Protection of Environment 6 2010-07-01 2010-07-01 false Test methods and procedures....

  12. Use of the Coombs Elimination Procedure in Classroom Tests.

    Bradbard, David A.; Green, Samuel B.

    1986-01-01

    The effectiveness of the Coombs elimination procedure was evaluated with 29 college students enrolled in a statistics course. Five multiple-choice tests were employed and scored using the Coombs procedure. Results suggest that the Coombs procedure decreased guessing, and this effect increased over the grading period. (Author/LMO)

  13. 16 CFR 1201.4 - Test procedures.

    2010-01-01

    ... durability test equipment—(i) Boil test. Two containers of water shall be provided with means to maintain one at 150° ±5 °F (66° ±2 °C) and the second at a slow boil at atmospheric pressure. The containers shall... specimens—(i) Boil test. Three pieces 12 inches by 12 inches (30 centimeters by 30 centimeters) with...

  14. Some procedures for computerized ability testing

    Linden, van der Wim J.; Zwarts, Michel A.

    1989-01-01

    For computerized test systems to be operational, the use of item response theory is a prerequisite. As opposed to classical test theory, in item response models the abilities of the examinees and the properties of the items are parameterized separately. Hence, when measuring the abilities of examine

  15. 16 CFR 1615.4 - Test procedure.

    2010-01-01

    ... 5 U.S.C. 552(a) and 1 CFR part 51. Items which do not withstand 50 launderings shall be tested at... height that the bottom of the specimen holder is 1.7 cm. ( 3/4 in.) above the highest point of the barrel... Standards, part 24, published by the American Society for Testing and Materials, 1916 Race...

  16. Panel expertise for an Angoff standard setting procedure in progress testing : item writers compared to recently graduated students

    Verhoeven, BH; Verwijnen, GM; Muijtjens, AMM; Scherpbier, AJJA; van der Vleuten, CPM

    2002-01-01

    Introduction An earlier study showed that an Angoff procedure with greater than or equal to 10 recently graduated students as judges can be used to estimate the passing score of a progress test. As the acceptability and feasibility of this approach are questionable, we conducted an Angoff procedure

  17. Delinquency and Peer Acceptance in Adolescence: A Within-Person Test of Moffitt’s Hypotheses

    Rulison, Kelly L.; Kreager, Derek A.; Osgood, D. Wayne

    2014-01-01

    We tested two hypotheses derived from Moffitt’s (1993) taxonomic theory of antisocial behavior, both of which are central to her explanation for the rise in delinquency during adolescence. Specifically, we tested whether persistently delinquent individuals become more accepted by their peers during adolescence and whether individuals who abstain from delinquent behavior become less accepted. Participants were 4,359 adolescents from 14 communities in the PROSPER study, which assessed friendshi...

  18. Integrated Performance Testing Workshop - Supplemental Materials (Scripts and Procedures)

    Baum, Gregory A.

    2014-02-01

    A variety of performance tests are described relating to: Material Transfers; Emergency Evacuation; Alarm Response Assessment; and an Enhanced Limited Scope Performance Test (ELSPT). Procedures are given for: nuclear material physical inventory and discrepancy; material transfers; and emergency evacuation.

  19. Results of the NASA Kennedy Space Center 50-MHz Doppler Radar Wind Profiler Operational Acceptance Test

    Barbre', Robert E., Jr.; Decker, Ryan K.; Leahy, Frank B.; Huddleston, Lisa

    2016-01-01

    This paper presents results of the new Kennedy Space Center (KSC) 50-MHz Doppler Radar Wind Profiler (DRWP) Operational Acceptance Test (OAT). The goal of the OAT was to verify the data quality of the new DRWP against the performance of the previous DRWP in order to use wind data derived by the new DRWP for space launch vehicle operations support at the Eastern Range. The previous DRWP was used as a situational awareness asset for mission operations to identify rapid changes in the wind environment that weather balloons cannot depict. The Marshall Space Flight Center's Natural Environments Branch assessed data from the new DRWP collected during Jan-Feb 2015 against a specified set of test criteria. Data examination verified that the DRWP provides complete profiles every five minutes from 1.8-19.5 km in vertical increments of 150 m. Analysis of 49 concurrent DRWP and balloon profiles presented root mean square wind component differences around 2.0 m/s. Evaluation of the DRWP's coherence between five-minute wind pairs found the effective vertical resolution to be Nyquist-limited at 300 m for both wind components. In addition, the sensitivity to rejecting data that do not have adequate signal was quantified. This paper documents the data, quality control procedures, methodology, and results of each analysis.

  20. 40 CFR 87.62 - Test procedure (propulsion engines).

    2010-07-01

    ... 40 Protection of Environment 20 2010-07-01 2010-07-01 false Test procedure (propulsion engines). 87.62 Section 87.62 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR... Exhaust Gaseous Emissions (Aircraft and Aircraft Gas Turbine Engines) § 87.62 Test procedure...

  1. 40 CFR 86.127-12 - Test procedures; overview.

    2010-07-01

    ... 40 Protection of Environment 18 2010-07-01 2010-07-01 false Test procedures; overview. 86.127-12 Section 86.127-12 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS... determined by the procedure described in § 86.139. This testing requires a dilution tunnel as well as...

  2. 40 CFR 86.127-96 - Test procedures; overview.

    2010-07-01

    ... 40 Protection of Environment 18 2010-07-01 2010-07-01 false Test procedures; overview. 86.127-96 Section 86.127-96 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS... determined by the procedure described in § 86.139. This testing requires a dilution tunnel as well as...

  3. HOT WATER COMFORT TEST PROCEDURE FOR SOLAR COMBISYSTEMS: PROPOSAL

    Furbo, Simon

    1999-01-01

    A proposal for a test procedure for hot water comfort for solar heating systems for combined space heating and domestic hot water supply was worked out.......A proposal for a test procedure for hot water comfort for solar heating systems for combined space heating and domestic hot water supply was worked out....

  4. 40 CFR 205.160-4 - Testing procedures.

    2010-07-01

    ... 40 Protection of Environment 24 2010-07-01 2010-07-01 false Testing procedures. 205.160-4 Section 205.160-4 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) NOISE ABATEMENT PROGRAMS TRANSPORTATION EQUIPMENT NOISE EMISSION CONTROLS Motorcycles § 205.160-4 Testing procedures....

  5. 40 CFR 86.1840-01 - Special test procedures.

    2010-07-01

    ... Compliance Provisions for Control of Air Pollution From New and In-Use Light-Duty Vehicles, Light-Duty Trucks... periodically regenerating trap oxidizer systems must propose a procedure for testing and certifying such... operation of the trap oxidizer system and the proposed certification and testing procedure. (d)...

  6. Test report for the run-in acceptance testing of the hydrogen mitigation retrieval Pump-3

    This report will provide the findings of the demonstration test conducted on the Double-Shell Tank (DST) 241-SY-101 HMR Pump-3 in accordance with WHC-SDWM-TP-434 ''Test plan for run-in acceptance testing of hydrogen mitigation/retrieval pump-3'' at the 400 Area Maintenance and Storage Facility (MASF) building from 7 June 1996 through 30 July 1996 per work package 4A-96-92/W. The DST 241-SY-101 hydrogen mitigation retrieval Pump-3 is a 200-HP submersible electric driven pump that has been modified for use in the DST 241-SY-101 containing mixed waste located in the 200W area. The pump has a motor driven rotation mechanism that allows the pump column to rotate through 355 degree. Prior to operation, pre-operational checks were performed which included loop calibration grooming and alignment of instruments, learning how plumb HMR-3 assembly hung in a vertical position and bump test of the motor to determine rotation direction. The pump was tested in the MASF Large Diameter Cleaning Vessel (LDCV) with process water at controlled temperatures and levels. In addition, the water temperature of the cooling water to the motor oil heat exchanger was recorded during testing. A 480-volt source powered a Variable Frequency Drive (VFD). The VFD powered the pump at various frequencies and voltages to control speed and power output of the pump. A second VFD powered the oil cooling pump. A third VFD was not available to operate the rotational drive motor during the 72 hour test, so it was demonstrated as operational before and after the test. A Mini Acquisition and Control System (Mini-DACS) controls pump functions and monitoring of the pump parameters. The Mini-DACS consists of three computers, software and some Programmable Logic Controllers (PLC). Startup and shutdown of either the pump motor or the oil cooling pump can be accomplished by the Mini-DACS. When the pump was in operation, the Mini-DACS monitors automatically collects data electronically. However, some required data

  7. Full-Scale Cask Testing and Public Acceptance of Spent Nuclear Fuel Shipments - 12254

    Full-scale physical testing of spent fuel shipping casks has been proposed by the National Academy of Sciences (NAS) 2006 report on spent nuclear fuel transportation, and by the Presidential Blue Ribbon Commission (BRC) on America's Nuclear Future 2011 draft report. The U.S. Nuclear Regulatory Commission (NRC) in 2005 proposed full-scale testing of a rail cask, and considered 'regulatory limits' testing of both rail and truck casks (SRM SECY-05-0051). The recent U.S. Department of Energy (DOE) cancellation of the Yucca Mountain project, NRC evaluation of extended spent fuel storage (possibly beyond 60-120 years) before transportation, nuclear industry adoption of very large dual-purpose canisters for spent fuel storage and transport, and the deliberations of the BRC, will fundamentally change assumptions about the future spent fuel transportation system, and reopen the debate over shipping cask performance in severe accidents and acts of sabotage. This paper examines possible approaches to full-scale testing for enhancing public confidence in risk analyses, perception of risk, and acceptance of spent fuel shipments. The paper reviews the literature on public perception of spent nuclear fuel and nuclear waste transportation risks. We review and summarize opinion surveys sponsored by the State of Nevada over the past two decades, which show consistent patterns of concern among Nevada residents about health and safety impacts, and socioeconomic impacts such as reduced property values along likely transportation routes. We also review and summarize the large body of public opinion survey research on transportation concerns at regional and national levels. The paper reviews three past cask testing programs, the way in which these cask testing program results were portrayed in films and videos, and examines public and official responses to these three programs: the 1970's impact and fire testing of spent fuel truck casks at Sandia National Laboratories, the 1980's

  8. Full-Scale Cask Testing and Public Acceptance of Spent Nuclear Fuel Shipments - 12254

    Dilger, Fred [Black Mountain Research, Henderson, NV 81012 (United States); Halstead, Robert J. [State of Nevada Agency for Nuclear Projects Carson City, NV 80906 (United States); Ballard, James D. [Department of Sociology, California State University, Northridge Northridge, CA 91330 (United States)

    2012-07-01

    Full-scale physical testing of spent fuel shipping casks has been proposed by the National Academy of Sciences (NAS) 2006 report on spent nuclear fuel transportation, and by the Presidential Blue Ribbon Commission (BRC) on America's Nuclear Future 2011 draft report. The U.S. Nuclear Regulatory Commission (NRC) in 2005 proposed full-scale testing of a rail cask, and considered 'regulatory limits' testing of both rail and truck casks (SRM SECY-05-0051). The recent U.S. Department of Energy (DOE) cancellation of the Yucca Mountain project, NRC evaluation of extended spent fuel storage (possibly beyond 60-120 years) before transportation, nuclear industry adoption of very large dual-purpose canisters for spent fuel storage and transport, and the deliberations of the BRC, will fundamentally change assumptions about the future spent fuel transportation system, and reopen the debate over shipping cask performance in severe accidents and acts of sabotage. This paper examines possible approaches to full-scale testing for enhancing public confidence in risk analyses, perception of risk, and acceptance of spent fuel shipments. The paper reviews the literature on public perception of spent nuclear fuel and nuclear waste transportation risks. We review and summarize opinion surveys sponsored by the State of Nevada over the past two decades, which show consistent patterns of concern among Nevada residents about health and safety impacts, and socioeconomic impacts such as reduced property values along likely transportation routes. We also review and summarize the large body of public opinion survey research on transportation concerns at regional and national levels. The paper reviews three past cask testing programs, the way in which these cask testing program results were portrayed in films and videos, and examines public and official responses to these three programs: the 1970's impact and fire testing of spent fuel truck casks at Sandia National

  9. A new approach to household appliance energy test procedures

    Ernebrant, S.; Wihlborg, M.

    1999-03-01

    Energy test procedures provides the industry with a method to measure its products energy consumption. The energy test procedures are the technical foundation to every energy standard and labelling system. Depending on which country the product is going to be sold in, the manufacturers must follow different standards. This report concentrates on appliance test procedures, with the main focus on refrigerators. Recently, a new technology -microcontrollers- is undermining the credibility of the test procedures. New features, saving energy in real-life, are not picked up by the test procedures. It is estimated that as much as 30% of energy could be saved with this technology. Microcontrollers have also led to the possibility to circumvent tests. A new model is presented in the report, which handles these energy savings and make it harder cheating on tests. The model divides the test procedure in two parts; hardware tests and software tests, and uses a Matlab/Simulink computer model to calculate the energy consumption. Examples of hardware- and software test methods for refrigerators are described. A refrigerator is used as an example to present the model. The possibility to harmonize the energy standards to one global standard, which could mean substantial savings and make international trade more efficient, is also discussed 24 refs, 30 figs. Examination paper

  10. 16 CFR 1630.4 - Test procedure.

    2010-01-01

    ... Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. (2) Cutting. Cut....) wall thickness. The flat bottom of the box shall be made of the same material as the sides and shall be... for Testing and Materials, 1916 Race Street, Philadelphia, Pa. 19103.) (6) Desiccating cabinet....

  11. 16 CFR 1631.4 - Test procedure.

    2010-01-01

    ... Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. (2) Cutting. Cut.../4 in.) wall thickness. The flat bottom of the box shall be made of the same material as the sides..., published by the American Society for Testing and Materials, 1916 Race Street, Philadelphia, PA 19103.)...

  12. 16 CFR 1616.5 - Test procedure.

    2010-01-01

    ... approved by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51... holder over the center of the base of the cabinet at such a height that the bottom of the specimen is 1.7... Society for Testing and Materials, 1916 Race Street, Philadelphia, Pa. 19103). (10) Desiccator. An...

  13. 40 CFR 90.707 - Test procedures.

    2010-07-01

    ... good engineering judgment to obtain emission results representative of production line engines. (d... EMISSIONS FROM NONROAD SPARK-IGNITION ENGINES AT OR BELOW 19 KILOWATTS Manufacturer Production Line Testing... manufacturer on every production line engine or unless this adjustment, repair, preparation, modification...

  14. CHIRONOMIDAE TOXICITY TESTS--BIOLOGICAL BACKGROUND AND PROCEDURES

    Toxicity tests must be based on an understanding of the test animal's life cycle. The first section of this report describes the biological information needed to develop toxicity test procedures. The second section describes three categories of toxicity test systems - short-expos...

  15. Quality assurance of radiopharmaceuticals-specifications and test procedures

    This report is a compilation of test methods used and specifications adopted for the Radiopharmaceutical Quality Assurance Test Programme conducted by the Australian Radiation Laboratory. In some cases test procedures described have been taken from various Pharmacopoeias or methods published in the literature. In other cases test methods have been developed at the ARL

  16. Test procedure for cation exchange chromatography

    The purpose of this test plan is to demonstrate the synthesis of inorganic antimonate ion exchangers and compare their performance against the standard organic cation exchangers. Of particular interest is the degradation rate of both inorganic and organic cation exchangers. This degradation rate will be tracked by determining the ion exchange capacity and thermal stability as a function of time, radiation dose, and chemical reaction

  17. A systematic testing procedure for MWPC readout electronic

    The paper discusses a systematic procedure to test and evaluate readout electronic for MWPC (Multi-Wire Proportional Counter) which is used widely in neutron scattering instrumentation. The main goal of this procedure is to test the functionality and suitability of the readout electronic and related it to the characteristic of the MWPC. Test carried out during this experiment are DC Offset, Dynamic range and Gain spread, Noise and ToT (Time over threshold) measurements. (Author)

  18. New energy test procedures for refrigerators and other appliances; FINAL

    Many innovations in refrigerator design rely on microprocessors, sensors, and algorithms to control automatic defrost, variable speed,and other features. Even though these features strongly influence energy consumption, the major energy test procedures presently test only a refrigerator's mechanical efficiency and ignore the ''software'' aspects. We describe a new test procedure where both ''hardware'' and ''software'' tests are fed into a dynamic simulation model. A wide range of conditions can be tested and simulated. This approach promotes international harmonization because the simulation model can also be programmed to estimate energy use for the ISO, DOE, or JIS test. The approach outlined for refrigerators can also be applied to other appliances

  19. Hanford spent nuclear fuel hot conditioning system test procedure

    This document provides the test procedures for cold testing of the prototype Hot Conditioning System (HCS) at the 306E Facility. The primary objective of this testing is to confirm design choices and provide data for the detailed design package prior to procurement of the process equipment. The current scope of testing in this document includes a fabricability study of the HCS, equipment performance testing of the HCS components, heat-up and cool-down cycle simulation, and robotic arm testing

  20. Community acceptability of use of rapid diagnostic tests for malaria by community health workers in Uganda

    Waiswa Peter; Pariyo George W; Kiguli Juliet; Tibenderana James K; Mukanga David; Bajunirwe Francis; Mutamba Brian; Counihan Helen; Ojiambo Godfrey; Kallander Karin

    2010-01-01

    Abstract Background Many malarious countries plan to introduce artemisinin combination therapy (ACT) at community level using community health workers (CHWs) for treatment of uncomplicated malaria. Use of ACT with reliance on presumptive diagnosis may lead to excessive use, increased costs and rise of drug resistance. Use of rapid diagnostic tests (RDTs) could address these challenges but only if the communities will accept their use by CHWs. This study assessed community acceptability of the...

  1. Understanding Student Teachers’ Behavioural Intention to Use Technology: Technology Acceptance Model (TAM) Validation and Testing

    Kung-Teck, Wong; Rosma bt Osman; Pauline Swee Choo, Goh; Mohd Khairezan Rahmat

    2013-01-01

    This study sets out to validate and test the Technology Acceptance Model (TAM) in the context of Malaysian student teachers’ integration of their technology in teaching and learning. To establish factorial validity, data collected from 302 respondents were tested against the TAM using confirmatory factor analysis (CFA), and structural equation modelling (SEM) was used for model comparison and hypotheses testing. The goodness-of-fit test of the analysis shows partial support of the applicabili...

  2. Delinquency and peer acceptance in adolescence: a within-person test of Moffitt's hypotheses.

    Rulison, Kelly L; Kreager, Derek A; Osgood, D Wayne

    2014-11-01

    We tested 2 hypotheses derived from Moffitt's (1993) taxonomic theory of antisocial behavior, both of which are central to her explanation for the rise in delinquency during adolescence. We tested whether persistently delinquent individuals become more accepted by their peers during adolescence and whether individuals who abstain from delinquent behavior become less accepted. Participants were 4,359 adolescents from 14 communities in the PROSPER study, which assessed friendship networks and delinquency from 6th (M = 11.8 years) to 9th (M = 15.3 years) grade. We operationalized peer acceptance as number of nominations received (indegree centrality), attractiveness as a friend (adjusted indegree centrality), and network bridging potential (betweenness centrality) and tested the hypotheses with multilevel modeling. Contrary to Moffitt's hypothesis, persistently delinquent youths did not become more accepted between early and middle adolescence, and although abstainers were less accepted in early adolescence, they became more accepted over time. Results were similar for boys and girls; when differences occurred, they provided no support for Moffitt's hypotheses for boys and were opposite of her hypotheses for girls. Sensitivity analyses in which alternative strategies and additional data were used to identify persistently delinquent adolescents produced similar results. We explore the implications of these results for Moffitt's assertions that social mimicry of persistently antisocial adolescents leads to increases in delinquency and that social isolation leads to abstention. (PsycINFO Database Record (c) 2014 APA, all rights reserved). PMID:25243328

  3. Delinquency and Peer Acceptance in Adolescence: A Within-Person Test of Moffitt’s Hypotheses

    Rulison, Kelly L; Kreager, Derek A.; Osgood, D. Wayne

    2015-01-01

    We tested two hypotheses derived from Moffitt’s (1993) taxonomic theory of antisocial behavior, both of which are central to her explanation for the rise in delinquency during adolescence. Specifically, we tested whether persistently delinquent individuals become more accepted by their peers during adolescence and whether individuals who abstain from delinquent behavior become less accepted. Participants were 4,359 adolescents from 14 communities in the PROSPER study, which assessed friendship networks and delinquency from 6th (M = 11.8 years) to 9th (M = 15.3 years) grade. We operationalized peer acceptance as: number of nominations received (indegree centrality), attractiveness as a friend (adjusted indegree centrality), and network bridging potential (betweenness centrality) and tested the hypotheses using multilevel modeling. Contrary to Moffitt’s hypothesis, persistently delinquent youth did not become more accepted between early and middle adolescence, and although abstainers were less accepted in early adolescence, they became more accepted over time. Results were similar for boys and girls; when differences occurred, they provided no support for Moffitt’s hypotheses for boys and were opposite of her hypotheses for girls. Sensitivity analyses using alternative strategies and additional data to identify persistently delinquent adolescents produced similar results. We explore the implications of these results for Moffitt’s assertions that social mimicry of persistently antisocial adolescents leads to increases in delinquency and that social isolation leads to abstention. PMID:25243328

  4. Project W-314 updated acceptance test report HNF-4649 for HNF-4648 241-A pit leak detection ANA-WT-LDSTA-331 for project W-314

    The purpose of the test was to verify that the AN Tank Farm AN-A Pit Leak Detector components are functionally integrated and operate in accordance with engineering design specifications. The Acceptance Test Procedure HNF-4648,24l-AN-A-Pit Leak Detection ANA-WT-LDSTA-331 was conducted between 23 June and 01 July 1999 at the 200E AN Tank Farm. The test has been completed with no open test exceptions. The test was conducted prior to final engineering ''as built'' activities being completed this had no impact on the procedure or test results. All components, identified in the procedure were found to be labeled and identified as written in the procedure

  5. Project W-314 acceptance test report HNF-4647 for HNF-4646 241-B pit leak detection ANB-WT-LDSTA-231 for project W-314

    The purpose of the test was to verify that the AN Tank Farm B Pit Leak Detector components are functionally integrated and operate in accordance with engineering design specifications. The Acceptance Test Procedure HNF-4646,241-AN-B-Pit Leak Detection ANB-WT-LDSTA-231 was conducted between 26 June and 02 July 1999 at the 200E AN Tank Farm. The test has been completed with no open test exceptions. The test was conducted prior to final engineering ''as built'' activities being completed this had no impact on the procedure or test results. All components, identified in the procedure were found to be labeled and identified as written in the procedure

  6. Biaxial testing for fabrics and foils optimizing devices and procedures

    Beccarelli, Paolo

    2015-01-01

    This book offers a well-structured, critical review of current design practice for tensioned membrane structures, including a detailed analysis of the experimental data required and critical issues relating to the lack of a set of design codes and testing procedures. The technical requirements for biaxial testing equipment are analyzed in detail, and aspects that need to be considered when developing biaxial testing procedures are emphasized. The analysis is supported by the results of a round-robin exercise comparing biaxial testing machines that involved four of the main research laboratories in the field. The biaxial testing devices and procedures presently used in Europe are extensively discussed, and information is provided on the design and implementation of a biaxial testing rig for architectural fabrics at Politecnico di Milano, which represents a benchmark in the field. The significance of the most recent developments in biaxial testing is also explored.

  7. CANFLEX fuel bundle strength tests during normal and abnormal refuelling procedure

    As one of verifications of the CANFLEX fuel bundle, the strength tests were performed by the double side-stop test for the simulation of normal fuel loading and the single side-stop test for the simulation of abnormal fuel loading. In both tests the load was applied by controlling the flow to obtain a desired pressure drop across the whole fuel string resulting in a specified hydraulic drag force on the test bundle. The test rig conditions for each test were 120 .deg. C and 11.2 MPa for 15 minutes. The test bundles against the side-stop simulators were measured and inspected carefully after the tests according to the measurement procedures. The inspection results showed the test bundles were intact and met the acceptance criteria

  8. 40 CFR 53.62 - Test procedure: Full wind tunnel test.

    2010-07-01

    ... 40 Protection of Environment 5 2010-07-01 2010-07-01 false Test procedure: Full wind tunnel test... Performance Characteristics of Class II Equivalent Methods for PM2.5 § 53.62 Test procedure: Full wind tunnel test. (a) Overview. The full wind tunnel test evaluates the effectiveness of the candidate sampler at...

  9. The Testing Effect for Learning Principles and Procedures from Texts

    Dirkx, Kim J. H.; Kester, Liesbeth; Kirschner, Paul A.

    2014-01-01

    The authors explored whether a testing effect occurs not only for retention of facts but also for application of principles and procedures. For that purpose, 38 high school students either repeatedly studied a text on probability calculations or studied the text, took a test on the content, restudied the text, and finally took the test a second…

  10. Test Procedure - pumping system for caustic addition project

    This test procedure provides the requirements for sub-system testing and integrated operational testing of the submersible mixer pump and caustic addition equipment by WHC and Kaiser personnel at the Rotating Equipment Shop run-in pit (Bldg. 272E)

  11. 49 CFR 572.163 - Neck assembly and test procedure.

    2010-10-01

    ... assembly is assembled and tested as specified in 49 CFR 572.123 (Subpart N). ... 49 Transportation 7 2010-10-01 2010-10-01 false Neck assembly and test procedure. 572.163 Section... TRAFFIC SAFETY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED) ANTHROPOMORPHIC TEST...

  12. 16 CFR 1700.20 - Testing procedure for special packaging.

    2010-01-01

    ... informed consent as defined in 16 CFR 1028.116. Examples of the forms used by the Commission staff for... test of 16 CFR 1700.20(a)(3) or the younger-adult test of 16 CFR 1700.20(a)(4) has resecured the... 16 Commercial Practices 2 2010-01-01 2010-01-01 false Testing procedure for special...

  13. Developing a Cloze Procedure as a Reading Comprehension Achievement Test

    I Ketut Seken

    2004-01-01

    The project was concerned with developing a cloze procedure as a reading comprehension achievement test. The subjects were students of the English Department of the Faculty of Letters, State University of Malang, who were halfway in the semester to complete Reading II course. The test was planned and constructed on the foundation of existing theory of cloze test construction. A review of theory concerning reading comprehension, testing reading comprehension, and cloze testing led to the const...

  14. Lagoon Seepage Testing Procedures for Central Facilities Area (CFA) Sewage Lagoons at Idaho National Laboratory Butte County, Idaho April 2014

    Alan Giesbrecht

    2014-05-01

    The lagoon seepage testing procedures are documented herein as required by the Wastewater Rules (IDAPA 58.01.16.493). The Wastewater Rules and Wastewater Reuse Permit LA-000141-03 require that the procedure used for performing a seepage test be approved by IDEQ prior to conducting the seepage test. The procedures described herein are based on a seepage testing plan that was developed by J-U-B ENGINEERS, Inc. (J-U-B) and has been accepted by several IDEQ offices for lagoons in Idaho.

  15. 40 CFR 86.090-27 - Special test procedures.

    2010-07-01

    ...-Duty Engines, and for 1985 and Later Model Year New Gasoline Fueled, Natural Gas-Fueled, Liquefied Petroleum Gas-Fueled and Methanol-Fueled Heavy-Duty Vehicles § 86.090-27 Special test procedures. (a)...

  16. CEL Working procedures for WRAP 2A formulation development test

    The WRAP 2A facility will encapsulate retrieved, stored, and newly generated contact-handled mixed low level waste (MLLW) into 55-500 gal cementitous forms. Standardized test procedures will be required to facilitate this process. Cementitous specimens will be prepared from simulated drum wastes and will be tested in the Chemical Engineering Laboratory using the laboratory operating/working procedures encorporated into this document

  17. 16 CFR 1632.4 - Mattress test procedure.

    2010-01-01

    ... Specification HH-I-558B is acceptable. Under this specification, the board must be Form A, Class 1, and plain... room. (ii) Tape edge. Each burning cigarette shall be placed in the depression between the mattress top... mattress tests. If there is only a seam or no depression at the edge, support the cigarettes in place...

  18. High acceptance of an early dyslexia screening test involving genetic analyses in Germany.

    Wilcke, Arndt; Müller, Bent; Schaadt, Gesa; Kirsten, Holger; Boltze, Johannes

    2016-02-01

    Dyslexia is a developmental disorder characterized by severe problems in the acquisition of reading and writing skills. It has a strong neurobiological basis. Genetic influence is estimated at 50-70%. One of the central problems with dyslexia is its late diagnosis, normally not before the end of the 2nd grade, resulting in the loss of several years for early therapy. Currently, research is focusing on the development of early tests for dyslexia, which may be based on EEG and genetics. Our aim was to determine the acceptance of such a future test among parents. We conducted a representative survey in Germany with 1000 parents of children aged 3-7 years, with and without experience of dyslexia. 88.7% of the parents supported the introduction of an early test for dyslexia based on EEG and genetics; 82.8% would have their own children tested, and 57.9% were willing to pay for the test if health insurance did not cover the costs. Test acceptance was significantly higher if parents had prior experience with dyslexia. The perceived benefits of such a test were early recognition and remediation and, preventing deficits. Concerns regarded the precision of the test, its potentially stigmatizing effect and its costs. The high overall support for the test leads to the conclusion that parents would accept a test for dyslexia based on EEG and genetics. PMID:26036858

  19. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Rev. 7-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive waste and mixed low-level waste for disposal. The NTSWAC includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex for disposal.

  20. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Rev. 7-01

    NSTec Environmental Management

    2009-05-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive waste and mixed low-level waste for disposal. The NTSWAC includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex for disposal.

  1. W-026 acceptance test report plant control system hardware (submittal {number_sign} 220.C)

    Watson, T.L., Fluor Daniel Hanford

    1997-02-14

    Acceptance Testing of the WRAP1 Plant Control System Hardware was conducted throughout the construction of WRAPI with the final testing on the Process Area hardware being completed in November 1996. The hardware tests were broken out by the following functional areas; Local Control Units, Operator Control Stations in the WRAP Control Room, DMS Server, PCS Server, Operator Interface Units, printers, DMS terminals, WRAP Local Area Network/Communications, and bar code equipment. This document contains a completed copy of each of the hardware tests along with the applicable test logs and completed test exception reports.

  2. W-026 acceptance test plan plant control system hardware (submittal {number_sign} 216)

    Watson, T.L., Fluor Daniel Hanford

    1997-02-14

    Acceptance Testing of the WRAP 1 Plant Control System Hardware will be conducted throughout the construction of WRAP I with the final testing on the Process Area hardware being completed in November 1996. The hardware tests will be broken out by the following functional areas; Local Control Units, Operator Control Stations in the WRAP Control Room, DMS Server, PCS Server, Operator Interface Units, printers, DNS terminals, WRAP Local Area Network/Communications, and bar code equipment. This document will contain completed copies of each of the hardware tests along with the applicable test logs and completed test exception reports.

  3. KE basin recirculation/skimmer/IX systems restart acceptance test report

    The 105 KE Basin Recirculation System and Skimmer Loop have been upgraded to provide the flexibility to run the Ion Exchange Modules on either system to support spent fuel removal for the Spent Nuclear Fuel Project. This Acceptance Test Report Provides the documentation of the leak Testing for the construction work associated with the IXM inlet and outlet piping, places the cartridge filters back in service and provides the functional testing of the IXM's on the recirculation and skimmer systems

  4. 105 K east ion exchange and cartridge filter restart instrumentation acceptance test report

    Acceptance Test Report following the completion of ATP-012 for the 105KE CP-A and CP-A Computer and PLC Panels. The test was conducted from 11/13/95 to 12/11/95. Three test discrepancies were generated during the ATP and all were dispositioned and closed. All sections were completed except Section 5.9 which was deleted per ECN 190556

  5. MAC Version 3.3, MBA Version 1.3 acceptance test summary report

    The K Basins Materials Accounting (MAC) and Materials Balance (MBA) programs had the Paradox Code Cleanup ATP run to check out the systems. This report describes the results of the test and provides the signoff sheets associated with the testing. The Acceptance Test results indicate that the MAC and MBA systems are ready for operation using the cleaned up code. The final codes were removed to the production space on the customer server on April 15th

  6. 40 CFR 1065.520 - Pre-test verification procedures and pre-test data collection.

    2010-07-01

    ... 40 Protection of Environment 32 2010-07-01 2010-07-01 false Pre-test verification procedures and pre-test data collection. 1065.520 Section 1065.520 Protection of Environment ENVIRONMENTAL PROTECTION... Specified Duty Cycles § 1065.520 Pre-test verification procedures and pre-test data collection. (a) If...

  7. Round-robin testing of Soleq EV cort according to the SAE J1634 test procedure dated May 1993

    Cole, G.H.

    1993-05-01

    The Society of Automotive Engineers Recommended Practice, SAE J1634, {open_quotes}Electric Vehicle Energy Consumption and Range Test Procedure{close_quotes}, May 1993, describes a standard method of determining the range and energy consumption for electric vehicles. Consequent to the U.S. Department of Energy`s (DOE) rulemaking released on February 4, 1994, the EPA is currently considering factoring electric vehicles into the Corporate Average Fuel Economy (CAFE) calculations using the SAE J1634 procedure. The purpose of this project is to provide information regarding the suitability of this recommended practice for determining the energy economy value to be factored into the CAFE. Issues leading to possible inconsistent results (such as the repeatability of the procedure, thoroughness of the procedure`s methods, and variance between different laboratories using different dynamometers) need to be resolved prior to passing legislation which will mandate use of this test in determining the electric vehicle CAFE credit. To this end, separate tests were performed on a Soleq EVcort vehicle by the INEL, the EPA, Ford Motor Company, Southwest Research Institute, and the California Air Resources Board using their own facilities and personnel. Acceptable departures from the driving profile prescribed by SAEJ1634 are not well defined. This deficiency in the procedure is even more noticeable due to the EVcort`s marginal acceleration performance.

  8. Utility-Scale Power Tower Solar Systems: Performance Acceptance Test Guidelines

    Kearney, D.

    2013-03-01

    The purpose of these Guidelines is to provide direction for conducting performance acceptance testing for large power tower solar systems that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. The recommendations have been developed under a National Renewable Energy Laboratory (NREL) subcontract and reviewed by stakeholders representing concerned organizations and interests throughout the concentrating solar power (CSP) community. An earlier NREL report provided similar guidelines for parabolic trough systems. These Guidelines recommend certain methods, instrumentation, equipment operating requirements, and calculation methods. When tests are run in accordance with these Guidelines, we expect that the test results will yield a valid indication of the actual performance of the tested equipment. But these are only recommendations--to be carefully considered by the contractual parties involved in the Acceptance Tests--and we expect that modifications may be required to fit the particular characteristics of a specific project.

  9. Accepting test-anxiety-related thoughts increases academic performance among undergraduate students

    Senay Ibrahim

    2012-01-01

    Full Text Available Given that unwanted thoughts are enhanced when suppressed, we tested among college freshmen who were about to take an academic exam if an acceptance strategy consisting of not suppressing intrusive thoughts will improve test performance. This strategy proved superior to students’ own default strategies as much as a modified, alternative strategy, avoiding the antecedents of intrusive thoughts. Moreover, the combination of the two strategies counteracted a stronger, negative effect of test anxiety on test performance as compared with each strategy used alone. The results suggest that not only intrusive thoughts per se but also the suppression of these thoughts can disrupt test performance, and hint that approaching such thoughts with acceptance may not interfere with simultaneously working toward avoiding the antecedents of these thoughts.

  10. The Qualification of Welding Procedure on DCF Test Rig Fabrication

    Joung, Chang Young; Ahn, Sung Ho; Hong, Jin Tae; Lee, Chul Yong; Jeong, Hwang Young [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2012-05-15

    Dual cooled fuel (DCF) is reactor fuel with a geometry allowing cooling water on the inner and outer surfaces of an annular fuel rod. Its concept was proposed for use in gas-cooled reactors during the 1960's and has recently been considered for utilization in PWRs. The main advantage of DCF is an increased heat transfer surface and a reduced fuel temperature, which result in less fission gas release, as well as an increased departure from nucleate boiling (DNB) and margins against fuel melting compared to standard type fuel. Another beneficial consequence is lower stored energy and lower peak cladding temperatures during a loss of coolant accident (LOCA). Welding of the test pieces is needed for a approval of welding procedure specifications and has to be carried out as a preliminary step. If standard requirements are fulfilled, the welding procedure specifications become a document providing in detail the required variables for a specific application to assure repeatability. Qualification of the welding procedures serves to demonstrate that production operations fully comply with the agreed welding procedure, including preliminary and subsequent treatment. Before a particular welding procedure is used in a production operation, the manufacturer should determine and document the suitability of the welding procedure specification (WPS) to produce a weld of the required quality. This paper will give an overview of the work done with the qualification of the welding procedure to weld a DCF rod and an insulated test channel assembly in a DCF test rig fabrication

  11. 14 CFR 34.62 - Test procedure (propulsion engines).

    2010-01-01

    ... 14 Aeronautics and Space 1 2010-01-01 2010-01-01 false Test procedure (propulsion engines). 34.62 Section 34.62 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION AIRCRAFT... (propulsion engines). (a)(1) The engine shall be tested in each of the following engine operating modes...

  12. Operational test procedure for SY tank farm replacement exhauster unit

    This operational test procedure will verify that the remaining functions not tested per WHC-SD-WM-ATP-080, or components disturbed during final installation, as well as interfaces with other tank farm equipment and remote monitoring stations are operating correctly

  13. European wind turbine procedure development blade test methods and techniques

    Bulder, B.H.; Dam, J.J.D. van; Delft, D.R.V. van [and others

    1999-03-01

    In this paper the preliminary results obtained by performing the second task of the `European Wind Turbine Testing Procedure Development` project are presented. This project is performed within and with financial support of the Standards, Measurements and Testing programme of the European Commission. (au)

  14. 40 CFR 86.1227-96 - Test procedures; overview.

    2010-07-01

    ... Emission Test Procedures for New Gasoline-Fueled, Natural Gas-Fueled, Liquefied Petroleum Gas-Fueled and... evaporative emissions. (b) The evaporative emission test (gasoline-fueled, natural gas-fueled, liquefied petroleum gas-fueled, and methanol-fueled vehicles) is designed to determine hydrocarbon and/or...

  15. 49 CFR 325.59 - Measurement procedure; stationary test.

    2010-10-01

    ... Stationary Test, 40 CFR 202.21. (Table 1 in § 325.7 lists the range of maximum permissible sound level... 49 Transportation 5 2010-10-01 2010-10-01 false Measurement procedure; stationary test. 325.59... CARRIER SAFETY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION GENERAL REGULATIONS COMPLIANCE WITH...

  16. 14 CFR 91.1071 - Crewmember: Tests and checks, grace provisions, training to accepted standards.

    2010-01-01

    ... performance to the person conducting the check, the program manager may not use the pilot, nor may the pilot... OPERATING AND FLIGHT RULES Fractional Ownership Operations Program Management § 91.1071 Crewmember: Tests... provisions, training to accepted standards. 91.1071 Section 91.1071 Aeronautics and Space FEDERAL...

  17. Integrating Telemedicine for Disaster Response: Testing the Emergency Telemedicine Technology Acceptance Model

    Davis, Theresa M.

    2013-01-01

    Background: There is little evidence that technology acceptance is well understood in healthcare. The hospital environment is complex and dynamic creating a challenge when new technology is introduced because it impacts current processes and workflows which can significantly affect patient care delivery and outcomes. This study tested the effect…

  18. Acceptance Test Report for the Modular Automation System (MAS) Manufactured by Honeywell Inc

    This document details the performance of the acceptance test of the Honeywell MAS Control System for equipment to be installed in gloveboxes HA-20MB and HA-211 at a later date. Equipment that was anticipated included 6 stabilization furnaces, only three and their associated equipment were installed

  19. A FORTRAN IV Program for Multiple-choice Tests with Predetermined Minimal Acceptable Performance Levels

    Noe, Michael J.

    1976-01-01

    A Fortran IV multiple choice test scoring program for an IBM 370 computer is described that computes minimally acceptable performance levels and compares student scores to these levels. The program accomodates up to 500 items with no more than nine alternatives from a group of examinees numbering less than 10,000. (Author)

  20. Rein tension acceptance in young horses in a voluntary test situation

    Christensen, Janne Winther; zharkikh, T.L.; Antoine, A.;

    2011-01-01

    inexperienced horses are willing to accept in order to obtain a food reward; whether the tension acceptance changes during 3 consecutive test days; and whether rein tension correlates with the expression of conflict behaviour and heart rate. Hypotheses: Pressure-naïve horses will apply only little rein tension...... bar) to obtain a food reward in a voluntary test situation. On each test day, each horse was exposed to 2 control sessions (loose reins), an intermediate and a short rein session (1 min/session). Rein tension, heart rate and behaviour were recorded. Results: The horses applied significantly more...... tension on the first day (mean rein tension: 10.2 N), compared to the second and third test day (Day 2: 6.0 and Day 3: 5.7 N). The horses showed significantly more conflict behaviour in the short rein treatment. There was no treatment effect on heart rate. Conclusions and potential relevance: The horses...

  1. Quality Assurance Plan for the AL3 Test Procedure

    Béjar-Alonso, Isabel

    1999-01-01

    This paper describes the new quality assurance plan for the Alarms-of-Level-3 (AL3) test. The aim of the plan is to introduce engineering techniques and to standardise and simplify the procedures for carrying out tests following Safety Instruction 37 (IS37). The procedures are to co-ordinate all the services involved (fire brigade, maintenance and computer support) and to create a consistent documentation. When the procedures are implemented, it will be possible to determine with confidence how field actions are carried out and to measure actual performance. The focus will be on personnel training and documentation. It is important however to keep documentation and procedures to a reasonable level that can be maintained at appropriate intervals. The plan is the result of an internal requirement from ST/MC and a formal request from Installations Nucléaires de Base (INB).

  2. Developing a Cloze Procedure as a Reading Comprehension Achievement Test

    I Ketut Seken

    2004-01-01

    Full Text Available The project was concerned with developing a cloze procedure as a reading comprehension achievement test. The subjects were students of the English Department of the Faculty of Letters, State University of Malang, who were halfway in the semester to complete Reading II course. The test was planned and constructed on the foundation of existing theory of cloze test construction. A review of theory concerning reading comprehension, testing reading comprehension, and cloze testing led to the construction of the test, including the decision concerning how to score the test and to interpret the scores. Using a class of 28 students, the test was tried out a week after the mid-semester test was administered by the Reading II teacher. It was found that the test is sufficienty reliable on the basis of a reliability coefficient of .79 through split-half procedure and a coefficient value of .78 by K-R 20. The test also showed high inter-section correlation. The validity of the test was viewed in terms of face, content, and construct. The test scores correlate moderately with those obtained from the mid-semester test by the teacher. Some problems are discussed and a suggestion made with regard to a possible solution to these problems.

  3. Testing Procedure for the Single Fiber Fragmentation Test

    Feih, Stefanie; Wonsyld, Karen; Minzari, Daniel; Westermann, Peter; Lilholt, Hans

    2004-01-01

    This report describes the details of the single fiber fragmentation test as conducted at the materials research department (AFM) at Risø. The equipment and specimen manufacture is described in detail. Furthermore, examples of results interpretation are given. For the experiments in this report, specimens with one E-glass fiber placed inside an epoxy or polyester matrix were used. Elongating the specimens with a mini tensile tester, which was placed under a microscope, leads to fiber fragmenta...

  4. Accepting test-anxiety-related thoughts increases academic performance among undergraduate students

    Senay Ibrahim; Cetinkaya Mustafa; Usak Muhammet

    2012-01-01

    Given that unwanted thoughts are enhanced when suppressed, we tested among college freshmen who were about to take an academic exam if an acceptance strategy consisting of not suppressing intrusive thoughts will improve test performance. This strategy proved superior to students’ own default strategies as much as a modified, alternative strategy, avoiding the antecedents of intrusive thoughts. Moreover, the combination of the two strategies counteracted a stronger, negative effect of te...

  5. Improved tank test procedures for scaled floating offshore wind turbines

    Müller, Kolja; Sandner, Frank; Bredmose, Henrik; Azcona, José; Manjock, Andreas; Pereira, Ricardo

    2014-01-01

    This study collects issues from previous tank test campaigns of scaled Floating Offshore Wind Turbines (FOWT), compares the different scaling methodologies, points out critical aspects and shows possible alternatives and recommendations for future tests depending on the specific objective. Furthermore, it gives practical recommendations for the modeling and construction of scaled rotors. The presented scaling procedure will be applied in tank tests within the EU Seventh Framework Program InnW...

  6. Testing Procedure for the Single Fiber Fragmentation Test

    Feih, Stefanie; Wonsyld, Karen; Minzari, Daniel;

    This report describes the details of the single fiber fragmentation test as conducted at the materials research department (AFM) at Risø. The equipment and specimen manufacture is described in detail. Furthermore, examples of results interpretation are given. For the experiments in this report......, specimens with one E-glass fiber placed inside an epoxy or polyester matrix were used. Elongating the specimens with a mini tensile tester, which was placed under a microscope, leads to fiber fragmentations. Different bonding strengths between fiber and matrix result in differences in the critical fracture...

  7. Operability test procedure [Tank] 241-SY-101 equipment removal system

    The 241-SY-101 equipment removal system (ERS) consists of components, equipment, instrumentation and procedures that will provide the means to disconnect, retrieve, contain, load and transport the Mitigation Pump Assembly (MPA) from waste Tank 241-SY-101 to the Central Waste Complex (CWC). The Operability Test Procedure (OTP) will test the interfaces between ERS components and will rehearse the procedure for MPA removal and transportation to the extent they can be mocked-up at the CTF (Cold Test Facility). At the conclusion of the OTP, the ERS components and equipment will be removed from the CTF, entered into the Component Based Recall System (CBRS), and stored until needed for actual MPA removal and transportation

  8. European wind turbine testing procedure developments. Task 2: Power quality

    Sørensen, Poul Ejnar; Friis Pedersen, Troels; Gerdes, G.; Klosse, R.; Santier, F.; Robertson, N.; Davy, W.; Koulouvari, M.; Morfiadakis, E.; Larsson, Å.

    2001-01-01

    quality measuremnet procedure in the Measnet cooperation of European test stations for wind turbines. The first working item of the project has been toverify the state of the art of the measurement procedures by analyses and comparisons of the measurements and data processing software of the participating......The present report describes the work done in the power quality subtask of the European Wind Turbine Testing Procedure Developments project funded by the EU SMT program. The objective of the power quality subtask has been to make recommendations andprovide background for new standards for...... measurement and testing of wind turbine power quality. The focus in the work has been to support the ongoing standardisation work in IEC with a new standard IEC61400-21 for measurement and assessment of powerquality characteristics of grid connected wind turbines. The work has also been based on the power...

  9. The deformable secondary mirror of VLT: final electro-mechanical and optical acceptance test results

    Briguglio, Runa; Biasi, Roberto; Xompero, Marco; Riccardi, Armando; Andrighettoni, Mario; Pescoller, Dietrich; Angerer, Gerald; Gallieni, Daniele; Vernet, Elise; Kolb, Johann; Arsenault, Robin; Madec, Pierre-Yves

    2014-07-01

    The Deformable Secondary Mirror (DSM) for the VLT ended the stand-alone electro-mechanical and optical acceptance process, entering the test phase as part of the Adaptive Optics Facility (AOF) at the ESO Headquarter (Garching). The VLT-DSM currently represents the most advanced already-built large-format deformable mirror with its 1170 voice-coil actuators and its internal metrology based on co-located capacitive sensors to control the shape of the 1.12m-diameter 2mm-thick convex shell. The present paper reports the final results of the electro-mechanical and optical characterization of the DSM executed in a collaborative effort by the DSM manufacturing companies (Microgate s.r.l. and A.D.S. International s.r.l.), INAF-Osservatorio Astrofisico di Arcetri and ESO. The electro-mechanical acceptance tests have been performed in the company premises and their main purpose was the dynamical characterization of the internal control loop response and the calibration of the system data that are needed for its optimization. The optical acceptance tests have been performed at ESO (Garching) using the ASSIST optical test facility. The main purpose of the tests are the characterization of the optical shell flattening residuals, the corresponding calibration of flattening commands, the optical calibration of the capacitive sensors and the optical calibration of the mirror influence functions.

  10. The adaptive secondary mirror for the Large Binocular Telescope: optical acceptance test and preliminary on-sky commissioning results

    Riccardi, Armando; Xompero, Marco; Briguglio, Runa; Quirós-Pacheco, Fernando; Busoni, Lorenzo; Fini, Luca; Puglisi, Alfio; Esposito, Simone; Arcidiacono, Carmelo; Pinna, Enrico; Ranfagni, Piero; Salinari, Piero; Brusa, Guido; Demers, Richard; Biasi, Roberto; Gallieni, Daniele

    2010-07-01

    The Large Binocular Telescope (LBT) has two adaptive secondary mirrors based on 672 voice-coil force actuators. The shape of the mirror is controlled using internal metrology based on co-located capacitive sensors. The first mirror unit is currently mounted on LBT for on-sky commissioning as part of the First Light Adaptive Optics System (FLAO). During spring-time 2009 the optical acceptance test was performed using the 14-m optical test tower at the Osservatorio Astrofisico di Arcetri (INAF) showing the capability of flattening the shell at the level of 14nm rms residual surface error. This paper reports the optical layout, calibration procedures and results of the optical acceptance test. Moreover we report the first results obtained during the early runs of FLAO commissioning showing the ability of the mirror to compensate for atmospheric turbulence with extremely high Strehl ratio values (better than 80% in H-band) as permitted by the largest number of correcting degrees of freedom currently available on-sky for astronomical telescopes.

  11. Preliminary evaluation of an analog procedure to assess acceptability of intimate partner violence against women: the Partner Violence Acceptability Movie Task

    Gracia, Enrique; Rodriguez, Christina M.; Lila, Marisol

    2015-01-01

    Acceptability of partner violence against women is a risk factor linked to its perpetration, and to public, professionals’ and victims’ responses to this behavior. Research on the acceptability of violence in intimate partner relationships is, however, limited by reliance solely on self-reports that often provide distorted or socially desirable accounts that may misrepresent respondents’ attitudes. This study presents data on the development and initial validation of a new analog task assessi...

  12. Preliminary evaluation of an analog procedure to assess acceptability of intimate partner violence against women: The Partner Violence Acceptability Movie Task (PVAM)

    Enrique eGracia; Rodriguez, Christina M.; Marisol eLila

    2015-01-01

    Acceptability of partner violence against women is a risk factor linked to its perpetration, and to public, professionals’ and victims’ responses to this behavior. Research on the acceptability of violence in intimate partner relationships is, however, limited by reliance solely on self-reports that often provide distorted or socially desirable accounts that may misrepresent respondents’ true attitudes. This study presents data on the development and initial validation of a new analog task as...

  13. Endurance test for non-instrumented capsule of advanced PWR fuel pellet (test procedure)

    This test procedure details the test loop, test method, and test procedure for pressure drop, vibration and endurance test of Non-instrumented Capsule of Advanced PWR Fuel Pellet. From the pressure drop test, the hydraulic design requirements of the capsule are verified. HANARO limit condition is checked and the compatibility with HANARO core is verified. From flow induced vibration test vibration frequency, vibration displacement are investigated. The wear of Non-instrumented Capsule of Advanced PWR Fuel Pellet is investigated through endurance test, and these data are used to evaluate the expected wear of during maximum resident time of Non-instrumented Capsule

  14. New procedures for testing whether stock price processes are martingales

    Kei Takeuchi; Akimichi Takemura; Masayuki Kumon

    2009-01-01

    We propose procedures for testing whether stock price processes are martingales based on limit order type betting strategies. We first show that the null hypothesis of martingale property of a stock price process can be tested based on the capital process of a betting strategy. In particular with high frequency Markov type strategies we find that martingale null hypotheses are rejected for many stock price processes.

  15. AP-102/104 Retrieval control system qualification test procedure

    RIECK, C.A.

    1999-05-18

    This Qualification Test Procedure documents the results of the qualification testing that was performed on the Project W-211, ''Initial Tank Retrieval Systems,'' retrieval control system (RCS) for tanks 241-AP-102 and 241-AP-104. The results confirm that the RCS has been programmed correctly and that the two related hardware enclosures have been assembled in accordance with the design documents.

  16. 40 CFR 60.534 - Test methods and procedures.

    2010-07-01

    ... 40 Protection of Environment 6 2010-07-01 2010-07-01 false Test methods and procedures. 60.534 Section 60.534 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS... concentrations may be measured with either: (1) Method 5G, if a dilution tunnel sampling location is used, or...

  17. Empirical testing of forecast update procedure forseasonal products

    Wong, Chee Yew; Johansen, John

    2008-01-01

    a toy supply chain. The theoretical simulation involves historical weekly consumer demand data for 122 toy products. The empirical test is then carried out in real-time with 291 toy products. The results show that the proposed forecast updating procedure: 1) reduced forecast errors of the annual...

  18. Statistical approach for collaborative tests, reference material certification procedures

    The first part introduces the different aspects in organizing and executing intercomparison tests of chemical or physical quantities. It follows a description of a statistical procedure to handle the data collected in a circular analysis. Finally, an example demonstrates how the tool can be applied and which conclusion can be drawn of the results obtained

  19. 40 CFR 205.57-4 - Testing procedures.

    2010-07-01

    ... 40 Protection of Environment 24 2010-07-01 2010-07-01 false Testing procedures. 205.57-4 Section 205.57-4 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) NOISE ABATEMENT PROGRAMS TRANSPORTATION EQUIPMENT NOISE EMISSION CONTROLS Medium and Heavy Trucks § 205.57-4...

  20. 40 CFR 63.1046 - Test methods and procedures.

    2010-07-01

    ..., the background level value must be determined according to the procedures in Method 21 of 40 CFR part... one or more floating roof levels when the roof is floating off the roof supports. (3) Seal gaps, if...) National Emission Standards for Oil-Water Separators and Organic-Water Separators § 63.1046 Test...

  1. Interim qualification tests and procedures for terrestrial photovoltaic thin-film flat-plate modules

    Deblasio, R.; Mrig, L.; Waddington, D.

    1990-01-01

    This document provides recommended procedures and specifications for qualification tests that are structured to evaluate terrestrial thin-film flat-plate photovoltaic nonconcentrating modules intended for power generation applications. The qualification tests provided in this document are designed to evaluate flat-plate thin-film photovoltaic (PV) module design performance and susceptibility to known failure mechanisms. Emphasis is placed on testing and evaluating module performance characteristics and design features that will affect possible degradation of module performance and physical properties resulting from solar exposure, environmental weathering, mechanical loading, corrosion, and module shadowing. Because of limited thin-film module field operation experience and the evolutionary nature of new thin-film module material technologies and designs, these tests should not be considered definitive or complete, nor do they provide a basis to predict 30-year field life. Current understanding of failure and degradation mechanisms and the relationship between accelerated tests and field reliability is not sufficient to allow accurate estimation of life-expectancy, nor are the cycling tests given in this document considered to be equivalent to a full 30-year field exposure. However, the test and evaluation procedures given in this document provide a common approach for conducting qualification tests. Acceptable results from these tests should provide reasonable assurance that the modules that pass these tests will perform reliably in the field but for an unspecified period of time.

  2. Mixed Variables-Attributes Test Plans for Single and DoubleAcceptance Sampling under Exponential Distribution

    Dongdong Xiang; Xiaolong Pu; Yan Li

    2011-01-01

    The mixed variables-attributes test plans for single acceptance sampling are proposed to protect “good lots” from attributes aspect and to optimize sample sizes from variables aspect. For the single and double mixed plans, exact formulas of the operating characteristic and average sample number are developed for the exponential distribution. Numerical illustrations show that the mixed sampling plans have some advantages over the variables plans or attributes plans alone.

  3. Test report for run-in acceptance testing of Project W-151 300 HP mixing pumps

    This report documents the results of a performance demonstration and operational checkout of three 300 HP mixer pumps in accordance with WHC-SD-WI51-TS-001 ''Mixer Pump Test Specification for Project W-151'' and Statement of Work 8K520-EMN-95-004 ''Mixer Pump Performance Demonstration at MASF'' in the 400 Area Maintenance and Storage Facility (MASF) building. Testing of the pumps was performed by Fast Flux Test Facility (FFTF) Engineering and funded by the Tank Waste Remediation System (TWRS) Project W-151. Testing began with the first pump on 04-01-95 and ended with the third pump on 11-01-96. Prior to testing, the MASF was modified and prepared to meet the pump testing requirements set forth by the Test Specification and the Statement of Work

  4. Biological and chemical tests of contaminated soils to determine bioavailability and environmentally acceptable endpoints (EAE)

    The understanding of the concept of bioavailability of soil contaminants to receptors and its use in supporting the development of EAE is growing but still incomplete. Nonetheless, there is increased awareness of the importance of such data to determine acceptable cleanup levels and achieve timely site closures. This presentation discusses a framework for biological and chemical testing of contaminated soils developed as part of a Gas Research Institute (GRI) project entitled ''Environmentally Acceptable Endpoints in Soil Using a Risk Based Approach to Contaminated Site Management Based on Bioavailability of Chemicals in Soil.'' The presentation reviews the GRI program, and summarizes the findings of the biological and chemical testing section published in the GRI report. The three primary components of the presentation are: (1) defining the concept of bioavailability within the existing risk assessment paradigm, (2) assessing the usefulness of the existing tests to measure bioavailability and test frameworks used to interpret these measurements, and (3) suggesting how a small selection of relevant tests could be incorporated into a flexible testing scheme for soils to address this issue

  5. Halogen occultation experiment (HALOE) performance verification test procedure

    Mauldin, L. E., III

    1986-01-01

    The Performance Verification Test Procedure is given for the Halogen Occultation Experiment (HALOE) instrument, which is being developed in house at the Langley Research Center for the Upper Atmosphere Research Satellite (UARS). This procedure is used for comprehensive performance testing of the HALOE instrument which occurs before, during, and after flight environmental tests. The radiometric performance tests include noise, drift, linearity, instantaneous field-of-view, cal wheel gas cell characterization, and self thermal emissions. Pointer/tracker performance tests include sun sensor performance, gimbal performance, control system performance, and boresight alignment. In addition, the instrument is tested functionally in simulated orbit sequences and all command operating modes are exercised. The data analysis required for each test is specified and pass/fail criteria are given where applicable. This test will fully demonstrate the HALOE instrument's ability to achieve science mission requirements. The HALOE instrument is a gas correlation radiometer that measures vertical distribution of eight upper atmospheric constituents: O3, HCl, HF, NO, CH4, H2O, NO2, and CO2.

  6. Evaluations of the Optimal Discovery Procedure for Multiple Testing.

    Rubin, Daniel B

    2016-05-01

    The Optimal Discovery Procedure (ODP) is a method for simultaneous hypothesis testing that attempts to gain power relative to more standard techniques by exploiting multivariate structure [1]. Specializing to the example of testing whether components of a Gaussian mean vector are zero, we compare the power of the ODP to a Bonferroni-style method and to the Benjamini-Hochberg method when the testing procedures aim to respectively control certain Type I error rate measures, such as the expected number of false positives or the false discovery rate. We show through theoretical results, numerical comparisons, and two microarray examples that when the rejection regions for the ODP test statistics are chosen such that the procedure is guaranteed to uniformly control a Type I error rate measure, the technique is generally less powerful than competing methods. We contrast and explain these results in light of previously proven optimality theory for the ODP. We also compare the ordering given by the ODP test statistics to the standard rankings based on sorting univariate p-values from smallest to largest. In the cases we considered the standard ordering was superior, and ODP rankings were adversely impacted by correlation. PMID:27227716

  7. Project W-320, operational test procedure OTP-320-003 test report

    This report documents and summarizes the results of OTP-320-003 Project W-320 Operational Testing of the WRSS Supernate Transfer System. Project W-320 Operational Test OTP-320-003 was performed to verify components of the Waste Retrieval Sluicing System (WRSS) supernate transfer system functioned as designed following construction completion and turnover to operations. All equipment operation was performed by Tank Farms Operations personnel following the operational test procedure and referenced operating procedures. Supernate Transfer line Flushing System Testing was completed over the course of approximately 4 weeks as tank farm conditions and configuration, equipment availability, and operations resources allowed. All testing was performed with the 702-AZ ventilation system and the 296-P-16 ventilation systems in operation. Test procedure OTP-320-003 required two revisions during testing to incorporate Procedure Changes Authorizations (PCAs) necessary to facilitate testing. Various sections of testing are documented on each procedure revision. The completed test procedure is included as Attachment A. Exception Reports generated during the course of testing are included as Attachment B

  8. 100 Area soil washing bench-scale test procedures

    Freeman, H.D.; Gerber, M.A.; Mattigod, S.V.; Serne, R.J.

    1993-03-01

    This document describes methodologies and procedures for conducting soil washing treatability tests in accordance with the 100 Area Soil Washing Treatability Test Plan (DOE-RL 1992, Draft A). The objective of this treatability study is to evaluate the use of physical separation systems and chemical extraction methods as a means of separating chemically and radioactively contaminated soil fractions from uncontaminated soil fractions. These data will be primarily used for determining feasibility of the individual unit operations and defining the requirements for a system, or systems, for pilot-scale testing.

  9. 100 Area soil washing bench-scale test procedures

    This document describes methodologies and procedures for conducting soil washing treatability tests in accordance with the 100 Area Soil Washing Treatability Test Plan (DOE-RL 1992, Draft A). The objective of this treatability study is to evaluate the use of physical separation systems and chemical extraction methods as a means of separating chemically and radioactively contaminated soil fractions from uncontaminated soil fractions. These data will be primarily used for determining feasibility of the individual unit operations and defining the requirements for a system, or systems, for pilot-scale testing

  10. Cassini RTG acceptance test results and RTG performance on Galileo and Ulysses

    Flight acceptance testing has been completed for the RTGs to be used on the Cassini spacecraft which is scheduled for an October 6, 1997 launch to Saturn. The acceptance test program includes vibration tests, magnetic field measurements, mass properties (weight and c.g.) and thermal vacuum test. This paper presents the thermal vacuum test results. Three RTGs are to be used, F-2, F-6, and F-7. F-5 is the backup RTG, as it was for the Galileo and Ulysses missions launched in 1989 and 1990, respectively. RTG performance measured during the thermal vacuum tests carried out at the Mound Laboratory facility met all specification requirements. Beginning of mission (BOM) and end of mission (EOM) power predictions have been made based on these tests results. BOM power is predicted to be 888 watts compared to the minimum requirement of 826 watts. Degradation models predict the EOM power after 16 years is to be 640 watts compared to a minimum requirement of 596 watts. Results of small scale module tests are also shown. The modules contain couples from the qualification and flight production runs. The tests have exceeded 28,000 hours (3.2 years) and are continuing to provide increased confidence in the predicted long term performance of the Cassini RTGs. All test results indicate that the power requirements of the Cassini spacecraft will be met. BOM and EOM power margins of over 5% are predicted. Power output from telemetry for the two Galileo RTGs are shown from the 1989 launch to the recent Jupiter encounter. Comparisons of predicted, measured and required performance are shown. Telemetry data are also shown for the RTG on the Ulysses spacecraft which completed its planned mission in 1995 and is now in the extended mission

  11. Cassini RTG acceptance test results and RTG performance on Galileo and Ulysses

    Flight acceptance testing has been completed for the RTGs to be used on the Cassini spacecraft which is scheduled for an October 6, 1997 launch to Saturn. The acceptance test program includes vibration tests, magnetic field measurements, properties (weight and c.g.) and thermal vacuum test. This paper presents The thermal vacuum test results. Three RTGs are to be used, F-2, F-6, and F-7. F-5 is tile back-up RTG, as it was for the Galileo and Ulysses missions launched in 1989 and 1990, respectively. RTG performance measured during the thermal vacuum tests carried out at die Mound Laboratory facility met all specification requirements. Beginning of mission (BOM) and end of mission (EOM) power predictions have been made based on than tests results. BOM power is predicted to be 888 watts compared to the minimum requirement of 826 watts. Degradation models predict the EOM power after 16 years is to be 640 watts compared to a minimum requirement of 596 watts. Results of small scale module tests are also showing. The modules contain couples from the qualification and flight production runs. The tests have exceeded 28,000 hours (3.2 years) and are continuing to provide increased confidence in the predicted long term performance of the Cassini RTGs. All test results indicate that the power requirements of the Cassini spacecraft will be met. BOM and EOM power margins of over five percent are predicted. Power output from telemetry for the two Galileo RTGs are shown from the 1989 launch to the recent Jupiter encounter. Comparisons of predicted, measured and required performance are shown. Telemetry data are also shown for the RTG on the Ulysses spacecraft which completed its planned mission in 1995 and is now in the extended mission

  12. Space Suit Portable Life Support System (PLSS) 2.0 Pre-Installation Acceptance (PIA) Testing

    Anchondo, Ian; Cox, Marlon; Meginnis, Carly; Westheimer, David; Vogel, Matt R.

    2016-01-01

    Following successful completion of the space suit Portable Life Support System (PLSS) 1.0 development and testing in 2011, the second system-level prototype, PLSS 2.0, was developed in 2012 to continue the maturation of the advanced PLSS design. This advanced PLSS is intended to reduce consumables, improve reliability and robustness, and incorporate additional sensing and functional capabilities over the current Space Shuttle/International Space Station Extravehicular Mobility Unit (EMU) PLSS. PLSS 2.0 represents the first attempt at a packaged design comprising first generation or later component prototypes and medium fidelity interfaces within a flight-like representative volume. Pre-Installation Acceptance (PIA) is carryover terminology from the Space Shuttle Program referring to the series of test sequences used to verify functionality of the EMU PLSS prior to installation into the Space Shuttle airlock for launch. As applied to the PLSS 2.0 development and testing effort, PIA testing designated the series of 27 independent test sequences devised to verify component and subsystem functionality, perform in situ instrument calibrations, generate mapping data, define set-points, evaluate control algorithms, evaluate hardware performance against advanced PLSS design requirements, and provide quantitative and qualitative feedback on evolving design requirements and performance specifications. PLSS 2.0 PIA testing was carried out in 2013 and 2014 using a variety of test configurations to perform test sequences that ranged from stand-alone component testing to system-level testing, with evaluations becoming increasingly integrated as the test series progressed. Each of the 27 test sequences was vetted independently, with verification of basic functionality required before completion. Because PLSS 2.0 design requirements were evolving concurrently with PLSS 2.0 PIA testing, the requirements were used as guidelines to assess performance during the tests; after the

  13. A Procedure for Controlling General Test Overlap in Computerized Adaptive Testing

    Chen, Shu-Ying

    2010-01-01

    To date, exposure control procedures that are designed to control test overlap in computerized adaptive tests (CATs) are based on the assumption of item sharing between pairs of examinees. However, in practice, examinees may obtain test information from more than one previous test taker. This larger scope of information sharing needs to be…

  14. Quality assurance in diagnostic radiology in Hungary - first experiences in acceptance testing

    It is a general experience that optimum imaging with minimum patient doses, moreover, the safe operation and long life of X-ray equipment can be assured by regular measurement of technical parameters and checking of their constancy (routine performance testing) only. These tests are generally known as quality control, while together with the so-called corrective actions and its management it is called (physical-technical) quality assurance (QA). In the European Union, Directive 97/43/EURATOM about radiation protection of patients requires - among others - the good practice of (physical-technical) quality assurance. In Hungary, Decree No. 31/2001. (X.3.) of the Minister of Health harmonizes all of its requirements. Acceptance testing of new diagnostic X-ray equipment is assigned to NPHC-NRIRR. QA has been a daily practice in radiation therapy and nuclear medicine for a long time. A National Patient Dose Assessment Programme has also successfully run since 1989. We had, however, only few preliminaries in QA in diagnostic radiology in the second half of the eighties. Nowadays there are running QA programmes in some hospitals and mammography centres. he testing activity of our institute is independent from manufacturers, it is run within the frame of an accredited testing laboratory, using calibrated measuring instruments and based on valid international standards. So the started way of implementing QA in diagnostic radiology needs a lot of further efforts, adapting experiences of other countries, and also some financial help to reach an acceptable level in the EU. (authors)

  15. User Acceptance Test of Computer-Assisted Problem-Based Learning Assessment Tool (CAPBLAT

    Muhammad Qomaruddin

    2014-02-01

    Full Text Available Problem-based Learning (PBL is an instructional design method that is used by many lecturers to create more efficient and meaningful learning experiences. PBL emphasizes the lecturer in facilitating in collaborative learning. They conventionally play a little role in the formal assessment process. Peer-assessment and self-assessment are the most frequent methods of assessment employed by the lecturers in conducting PBL approach. This paper presents acceptance testing of a computer-based tool for peer-assessment and self-assessment in PBL approach, which called Computer-Assisted Problem-Based Learning Assessment Tool (CAPBLAT. The tool was designed to assist a lecturer in conducting PBL teaching method and assess students learning progress. Two PBL classes participated in the testing of the tool. During the study, questionnaires were administered to students. The results concerning the assessment tool acceptance demonstrate that using CAPBLAT in the PBL assessment process received better acceptance from both the students and lecturers.

  16. Consumer acceptance, market test and market development of irradiated rice, dehydrated vegetables and spices

    Establishment of irradiation processing parameters, a quality assurance system, consumer acceptance, market test and market development of irradiated rice, dehydrated vegetables and spices were the activities carried out in this project by the Chinese Agricultural Irradiation Center. The results of the studies showed that the process dose for rice was 0.2-0.5 kGy when the non-uniformity was lower than 2.5, dose range for dehydrated vegetables was 5-7 kGy, dose for spices was 7-8 kGy. The system for quality assurance was established. The processing standards for several irradiated food items were set up. Market test showed that more than 70-80% of consumers accepted irradiated food. Industrial companies also accepted irradiated dehydrated vegetables and spices. The latter were successfully introduced to the markets and successful commercialization of irradiated garlic was followed. The economic benefit of operating the Chinese Agricultural Irradiation Center was analyzed and found attractive, especially for low dose irradiation of foods in sufficient supply. (author)

  17. Geoscience Laser Altimeter System (GLAS) Instrument: Flight Loop Heat Pipe (LHP) Acceptance Thermal Vacuum Test

    Baker, Charles; Butler, Dan; Ku, Jentung; Grob, Eric; Swanson, Ted; Nikitkin, Michael; Powers, Edward I. (Technical Monitor)

    2001-01-01

    Two loop heat pipes (LHPs) are to be used for tight thermal control of the Geoscience Laser Altimeter System (GLAS) instrument, planned for flight in late 2001. The LHPs are charged with Propylene as a working fluid. One LHP will be used to transport 110 W from a laser to a radiator, the other will transport 160 W from electronic boxes to a separate radiator. The application includes a large amount of thermal mass in each LHP system and low initial startup powers. The initial design had some non-ideal flight design compromises, resulted in a less than ideal charge level for this design concept with a symmetrical secondary wick. This less than ideal charge was identified as the source of inadequate performance of the flight LHPs during the flight thermal vacuum test in October of 2000. We modified the compensation chamber design, re-built and charged the LHPs for a final LHP acceptance thermal vacuum test. This test performed March of 2001 was 100% successful. This is the last testing to be performed on the LHPs prior to instrument thermal vacuum test. This sensitivity to charge level was shown through varying the charge on a Development Model Loop Heat Pipe (DM LHP) and evaluating performance at various fill levels. At lower fills similar to the original charge in the flight units, the same poor performance was observed. When the flight units were re-designed and filled to the levels similar to the initial successful DM LHP test, the flight units also successfully fulfilled all requirements. This final flight Acceptance test assessed performance with respect to startup, low power operation, conductance, and control heater power, and steady state control. The results of the testing showed that both LHPs operated within specification. Startup on one of the LHPs was better than the other LHP because of the starter heater placement and a difference in evaporator design. These differences resulted in a variation in the achieved superheat prior to startup. The LHP with

  18. Home-based voluntary HIV counselling and testing found highly acceptable and to reduce inequalities

    Michelo Charles

    2010-06-01

    Full Text Available Abstract Background Low uptake of voluntary HIV counselling and testing (VCT in sub-Saharan Africa is raising acceptability concerns which might be associated with ways by which it is offered. We investigated the acceptability of home-based delivery of counselling and HIV testing in urban and rural populations in Zambia where VCT has been offered mostly from local clinics. Methods A population-based HIV survey was conducted in selected communities in 2003 (n = 5035. All participants stating willingness to be HIV tested were offered VCT at home and all counselling was conducted in the participants' homes. In the urban area post-test counselling and giving of results were done the following day whereas in rural areas this could take 1-3 weeks. Results Of those who indicated willingness to be HIV tested, 76.1% (95%CI 74.9-77.2 were counselled and received the test result. Overall, there was an increase in the proportion ever HIV tested from 18% before provision of home-based VCT to 38% after. The highest increase was in rural areas; among young rural men aged 15-24 years up from 14% to 42% vs. for urban men from 17% to 37%. Test rates by educational attainment changed from being positively associated to be evenly distributed after home-based VCT. Conclusions A high uptake was achieved by delivering HIV counselling and testing at home. The highest uptakes were seen in rural areas, in young people and groups with low educational attainment, resulting in substantial reductions in existing inequalities in accessing VCT services.

  19. Project W-314 acceptance test report HNF-4643 for HNF-4642 241-AN-A valve pit manifold valves and position indication for project W-314

    HAMMERS, J.S.

    1999-09-22

    The purpose of the test was to verify that the AN Tank Farm Manifold Valves can be manually manipulated to the required operating position and that the electrical and visual indications accurately reflect that position. Physical locking devices were also verified to function. The Acceptance Test Procedure HNF-4642, 241-AN-A Valve Pit Manifold Valves and Position Indication was conducted between 23 June and 10 August 1999 at the 200E AN Tank Farm. The test has no open test exceptions. The test was conducted prior to final engineering ''as built'' activities being completed, this had an impact on the procedure and test results, ECN 653752 was written to correct the mismatch between the procedure and actual field conditions. P&ID H-14-100941 was changed via ECN-W-314-4C-120. All components, identified in the procedure, were not found to be labeled and identified as written in the procedure, temporary tags were used for operational identification. A retest of valve ANA-WT-V 318 was required because it was removed from its installed position and modified after testing was completed.

  20. Project W-314 acceptance test report HNF-4643 for HNF-4642 241-AN-A valve pit manifold valves and position indication for project W-314

    The purpose of the test was to verify that the AN Tank Farm Manifold Valves can be manually manipulated to the required operating position and that the electrical and visual indications accurately reflect that position. Physical locking devices were also verified to function. The Acceptance Test Procedure HNF-4642, 241-AN-A Valve Pit Manifold Valves and Position Indication was conducted between 23 June and 10 August 1999 at the 200E AN Tank Farm. The test has no open test exceptions. The test was conducted prior to final engineering ''as built'' activities being completed, this had an impact on the procedure and test results, ECN 653752 was written to correct the mismatch between the procedure and actual field conditions. P and ID H-14-100941 was changed via ECN-W-314-4C-120. All components, identified in the procedure, were not found to be labeled and identified as written in the procedure, temporary tags were used for operational identification. A retest of valve ANA-WT-V 318 was required because it was removed from its installed position and modified after testing was completed

  1. Ten years experience in acceptance testing of diagnostic radiology equipment in Hungary

    The EURATOM directive for the radiation protection of patients, which declares the mandatory evaluation of the performance of diagnostic X-ray machines, took effect in 1997. In Hungary, this became a harmonized act, the 31/2001. (X. 3.) decree of the Minister of Health. The most highlighted segment of the evaluation of technical performance is acceptance testing. The NRIRR Department of Radiohygiene performs acceptance tests since 2002. From then on we have performed more than 400 examinations on different modalities such as radiographic, fluoroscopic, DSA, mammographic, CT and dental panoramic X-rays. The tests were performed according to IEC = EN = MSZ EN international, European and at the same time Hungarian standards. This presentation discusses our experience and gives a comprehensive overview of the examinations by the evaluation of the measurement data. Our results show the importance of testing, done independently from the manufacturer and installer: in est. 25 % of the cases overall we have found inadequacies which required remedial action on the part of the service

  2. Using case-based reasoning for generating functional test procedures

    Martha Dunia Delgado Dapena

    2010-10-01

    Full Text Available This paper presents a proposal for storage structure and retrieval mechanisms used for implementing case-based reasoning (CBR in generating functional test procedures in software projects. This proposal was based on software project t functional requirements and sets out the proposed algorithms for considering the similarity between each pair of projects as well as those leading to adapting the solution found in the case base.

  3. Using case-based reasoning for generating functional test procedures

    Martha Dunia Delgado Dapena; Yucely López Trujillo; Indira Chávez Valiente

    2010-01-01

    This paper presents a proposal for storage structure and retrieval mechanisms used for implementing case-based reasoning (CBR) in generating functional test procedures in software projects. This proposal was based on software project t functional requirements and sets out the proposed algorithms for considering the similarity between each pair of projects as well as those leading to adapting the solution found in the case base.

  4. European wind turbine testing procedure developments. Task 2: Power quality

    Soerensen, P.; Friis Pedersen, T. [Risoe National Lab., Roskilde (Denmark); Gerdes, G.; Klosse, R.; Santier, F. [DEWI, Wilhelmshaven (Germany); Robertson, N.; Davy, W. [NEL, Glasgow (United Kingdom); Koulouvari, M.; Morfiadakis, E. [CRES, Pikermi (Greece); Larsson, Aa. [Chalmers Univ. of Technology, Goeteborg (Sweden)

    2001-05-01

    The present report describes the work done in the power quality subtask of the European Wind Turbine Testing Procedure Developments project funded by the EU SMT program. The objective of the power quality subtask has been to make recommendations and provide background for new standards for measurement and testing of wind turbine power quality. The focus in the work has been to support the ongoing standardisation work in IEC with a new standard IEC61400-21 for measurement and assessment of power quality characteristics of grid connected wind turbines. The work has also been based on the power quality measuremnet procedure in the Measnet cooperation of European test stations for wind turbines. The first working item of the project has been to verify the state of the art of the measurement procedures by analyses and comparisons of the measurements and data processing software of the participating partners. The next item has been to investigate the influence of terrain, grid properties and wind farm summation on the power quality of wind turbines, considering both wind turbines with fixed rotor speed(s) and wind turbines with variable speed drives. (au)

  5. Quality assurance of radiopharmaceuticals - specifications and test procedures

    The authors report on a Radiopharmaceutical Quality Assurance Test Programme carried out by the Australian Radiation Laboratory in which radiopharmaceuticals used in nuclear medicine in Australia are tested for compliance with specifications. Where the radiopharmaceutical is the subject of a monograph in the British Pharmacopoeia or the European Pharmacopoeia, then the specifications given in the Pharmacopoeia are adopted. In other cases the specifications given have been adopted by this Laboratory and have no legal status. In some cases test procedures described have been taken from various Pharmacopoeias or methods published in the literature. In other cases test methods described have been developed at this Laboratory. It should be noted that, unless stated otherwise, specifications listed apply at all times up until product expire

  6. Study on service test procedure for SMES systems

    Ren, L., E-mail: rl8868@126.co [R and D Center of Applied Superconductivity, Huazhong University of Science and Technology, Wuhan 430074 (China); Tang, Y.; Li, J.; Shi, J. [R and D Center of Applied Superconductivity, Huazhong University of Science and Technology, Wuhan 430074 (China); Hu, Y. [State Grid Electric Power Research Institute, Wuhan 430074 (China); Guo, F.; Chen, L.; Cheng, S. [R and D Center of Applied Superconductivity, Huazhong University of Science and Technology, Wuhan 430074 (China)

    2009-10-15

    Some superconducting magnetic energy storage (SMES) systems have been developed successfully, and the function of them was verified by experiment. Considering the impact on the system security and stability when they are connected to the power system, it is important to build a standard test procedure and propose the main experimental contents for some representative superconducting devices. Based on the experimental results of a 35 kJ/7 kW conduction-cooled high-T{sub c} SMES system, which was developed by Huazhong University of Science and Technology, the test items and methods for a conduction-cooled high-T{sub c} SMES system are studied. For performance evaluation of this high-T{sub c} SMES, three superconducting magnet performance tests, power conditioning characteristic test and dynamic experiment in a simulated power system were fulfilled.

  7. Study on service test procedure for SMES systems

    Ren, L.; Tang, Y.; Li, J.; Shi, J.; Hu, Y.; Guo, F.; Chen, L.; Cheng, S.

    2009-10-01

    Some superconducting magnetic energy storage (SMES) systems have been developed successfully, and the function of them was verified by experiment. Considering the impact on the system security and stability when they are connected to the power system, it is important to build a standard test procedure and propose the main experimental contents for some representative superconducting devices. Based on the experimental results of a 35 kJ/7 kW conduction-cooled high- T c SMES system, which was developed by Huazhong University of Science and Technology, the test items and methods for a conduction-cooled high- T c SMES system are studied. For performance evaluation of this high- T c SMES, three superconducting magnet performance tests, power conditioning characteristic test and dynamic experiment in a simulated power system were fulfilled.

  8. Development of test procedures for hybrid/electric vehicles

    Burke, A. F.

    1992-07-01

    The development of procedures for testing of hybrid/electric vehicles to determine their energy consumption and emissions characteristics is addressed. Special emphasis is given to hybrid vehicles, which can be operated above some minimum battery state-of-charge in an all-electric mode for all types of driving (city and highway). When the all-electric range of these vehicles is exceeded, the vehicles are operated in the hybrid mode, in which an engine/generator is turned on to generate electricity on-board the vehicle. Key issues in testing hybrid vehicles are identified and discussed. These issues include the test cycles to be used, the instrumentation required, the effect of battery state-of-charge and control strategy in the hybrid mode on the need for repeated test cycles, and the data to be collected and how that data from repeated cycles is interpreted to determine the vehicle energy consumption and emissions characteristics.

  9. Multi-Canister Overpack (MCO) Combustible Gas Management Leak Test Acceptance Criteria (OCRWM)

    The purpose of this document is to support the Spent Nuclear Fuel Project's combustible gas management strategy while avoiding the need to impose any requirements for oxygen free atmospheres within storage tubes that contain multi-canister overpacks (MCO). In order to avoid inerting requirements it is necessary to establish and confirm leak test acceptance criteria for mechanically sealed and weld sealed MCOs that are adequte to ensure that, in the unlikely event the leak test results for any MCO were to approach either of those criteria, it could still be handled and stored in stagnant air without compromising the SNF Project's overall strategy to prevent accumulation of combustible gas mixtures within MCOs or within their surroundings. To support that strategy, this document: (1) establishes combustible gas management functions and minimum functional requirements for the MCO's mechanical seals and closure weld(s); (2) establishes a maximum practical value for the minimum required initial MCO inert backfill gas pressure; and (3) based on items 1 and 2, establishes and confirms leak test acceptance criteria for the MCO's mechanical seal and final closure weld(s)

  10. Factory acceptance test of COLDDIAG: A cold vacuum chamber for diagnostics

    Gerstl, Stefan; Baumbach, Tilo; Casalbuoni, Sara; Grau, Andreas; Hagelstein, Michael; Saez de Jauregui, David; Holubek, Tomas [Karlsruhe Institute of Technology, Karlsruhe (Germany); Boffo, Cristian; Sikler, Guenther [Babcock Noell GmbH, Wuerzburg (Germany); Baglin, Vincent [CERN, Geneva (Switzerland); Cox, Matthew; Schouten, Jos [Diamond Light Source, Oxfordshire (United Kingdom); Cimino, Roberto; Commisso, Mario; Spataro, Bruno [INFN/LNF, Frascatti (Italy); Mostacci, Andrea [Rome University La Sapienza, Rome (Italy); Wallen, Eric [MAX-Lab, Lund (Sweden); Weigel, Ralf [Max-Planck Institute for Metal Research, Stuttgart (Germany); Clarke, Jim; Scott, Duncan [STFC/ASTeC, Daresbury (United Kingdom); Bradshaw, Tom [STFC/RAL, Chilton (United Kingdom); Jones, Roger; Shinton, Ian [University Manchester (United Kingdom)

    2011-07-01

    Superconductive insertion devices (IDs) have higher fields for a given gap and period length compared with the state of the art technology of permanent magnet IDs. This technological solution is very interesting for synchrotron light sources since it permits to increase the brilliance and/or the photon energy at moderate costs. One of the key issues for the development of superconducting IDs is the understanding of the beam heat load to the cold vacuum chamber. Therefore a cold vacuum chamber for diagnostic was built. Here we report about the design, planned measurements and the factory acceptance test of COLDDIAG.

  11. Factory acceptance test of COLDDIAG: A cold vacuum chamber for diagnostics

    Superconductive insertion devices (IDs) have higher fields for a given gap and period length compared with the state of the art technology of permanent magnet IDs. This technological solution is very interesting for synchrotron light sources since it permits to increase the brilliance and/or the photon energy at moderate costs. One of the key issues for the development of superconducting IDs is the understanding of the beam heat load to the cold vacuum chamber. Therefore a cold vacuum chamber for diagnostic was built. Here we report about the design, planned measurements and the factory acceptance test of COLDDIAG.

  12. The Rapid Integration and Test Environment - A Process for Achieving Software Test Acceptance

    Rick Jack

    2010-01-01

    The Rapid Integration and Test Environment (RITE) initiative, implemented by the Program Executive Office, Command, Control, Communications, Computers and Intelligence, Command and Control Program Office (PMW-150), was born of necessity. Existing processes for requirements definition and management, as well as those for software development, did not consistently deliver high-quality Navy command and control (C2) systems on time and within budget. Navy C2 software programs experienced an inc...

  13. Evaluation of WES one-dimensional dynamic soil testing procedures

    Seaman, L.

    1983-06-01

    The Geomechanics Division of the Waterways Experiment Station (WES) tests soils to provide material property data for ground motion calculations in support of high explosives experiments. Thus, the validity of the ground motion predictions depends greatly on the WES material properties used. The usual WES experiments are uniaxial strain (UX) and triaxial shear (TX) tests that can be performed at static testing rates and at dynamic rates with rise times down to about one millisecond. However, in the field experiments being simulated, the measured rise times are often 0.01 ms up to 0.1 ms. Recently, an effort has been made to obtain test data in UX and TX devices with rise times of about 0.1 ms. Some of the test data obtained at these very high rates have appeared to be anomalous, suggesting that wave propagation or other effects may be invalidating the data. Because of these questions about the high rate soils test data, WES asked SRI to evaluate the testing methods used at WES and the data reduction device. This report documents an evaluation of laboratory test data obtained from the explosive-loaded uniaxial strain device developed at WES and the data analysis procedures currently being used.

  14. Testing heated flint palaeodose protocols using dose recovery procedures

    Thermoluminescence (TL) dating of materials from archaeological contexts has been shown to be an accurate method when comparisons are made with other chronometric dating methods; however, little has been published on the verification of the measurement protocols used to determine the equivalent dose (palaeodose). Instead of testing TL dating protocols for heated flint using archaeological material with unknown thermal and radiation history, dose recovery tests for three samples of different geological origin are presented. These samples exhibit TL emission in the UV, blue and orange-red wavelengths. In addition to the two multiple aliquot protocols (standard additive-regeneration and normalization) generally used to determine the palaeodose, the single-aliquot-regenerative-dose (SAR) TL and OSL procedure, a 'short' SAR-TL and isothermal luminescence (IT) decay procedures are applied using detection windows limited to these emissions. Accurate dose recovery is obtained for the standard and normalization protocols in the commonly employed detection window (UV-blue), the 'short' SAR in the orange-red window and some IT measurements. While the standard techniques give the most accurate and precise results, detection of the TL and IT orange-red emission in connection with a 'short' SAR protocol also gave accurate and precise results. Such procedures are especially suitable for samples too small for standard multiple aliquot techniques, which require large samples

  15. Accuracy and user-acceptability of HIV self-testing using an oral fluid-based HIV rapid test.

    Oon Tek Ng

    Full Text Available BACKGROUND: The United States FDA approved an over-the-counter HIV self-test, to facilitate increased HIV testing and earlier linkage to care. We assessed the accuracy of self-testing by untrained participants compared to healthcare worker (HCW testing, participants' ability to interpret sample results and user-acceptability of self-tests in Singapore. METHODOLOGY/PRINCIPAL FINDINGS: A cross-sectional study, involving 200 known HIV-positive patients and 794 unknown HIV status at-risk participants was conducted. Participants (all without prior self-test experience performed self-testing guided solely by visual instructions, followed by HCW testing, both using the OraQuick ADVANCE Rapid HIV 1/2 Antibody Test, with both results interpreted by the HCW. To assess ability to interpret results, participants were provided 3 sample results (positive, negative, and invalid to interpret. Of 192 participants who tested positive on HCW testing, self-testing was positive in 186 (96.9%, negative in 5 (2.6%, and invalid in 1 (0.5%. Of 794 participants who tested negative on HCW testing, self-testing was negative in 791 (99.6%, positive in 1 (0.1%, and invalid in 2 (0.3%. Excluding invalid tests, self-testing had sensitivity of 97.4% (95% CI 95.1% to 99.7% and specificity of 99.9% (95% CI: 99.6% to 100%. When interpreting results, 96%, 93.1% and 95.2% correctly read the positive, negative and invalid respectively. There were no significant demographic predictors for false negative self-testing or wrongly interpreting positive or invalid sample results as negative. Eighty-seven percent would purchase the kit over-the-counter; 89% preferred to take HIV tests in private. 72.5% and 74.9% felt the need for pre- and post-test counseling respectively. Only 28% would pay at least USD15 for the test. CONCLUSIONS/SIGNIFICANCE: Self-testing was associated with high specificity, and a small but significant number of false negatives. Incorrectly identifying model results as

  16. Lightning arrestor connector lead magnesium niobate qualification pellet test procedures.

    Tuohig, W. (Honeywell FM& T, Kansas City, MO); Mahoney, Patrick A.; Tuttle, Bruce Andrew; Wheeler, Jill Susanne

    2009-02-01

    Enhanced knowledge preservation for DOE DP technical component activities has recently received much attention. As part of this recent knowledge preservation effort, improved documentation of the sample preparation and electrical testing procedures for lead magnesium niobate--lead titanate (PMN/PT) qualification pellets was completed. The qualification pellets are fabricated from the same parent powders used to produce PMN/PT lightning arrestor connector (LAC) granules at HWF&T. In our report, the procedures for fired pellet surface preparation, electrode deposition, electrical testing and data recording are described. The dielectric measurements described in our report are an information only test. Technical reasons for selecting the electrode material, electrode size and geometry are presented. The electrical testing is based on measuring the dielectric constant and dissipation factor of the pellet during cooling from 280 C to 220 C. The most important data are the temperature for which the peak dielectric constant occurs (Curie Point temperature) and the peak dielectric constant magnitude. We determined that the peak dielectric constant for our procedure would be that measured at 1 kHz at the Curie Point. Both the peak dielectric constant and the Curie point parameters provide semi-quantitative information concerning the chemical and microstructural homogeneity of the parent material used for the production of PMN/PT granules for LACs. Finally, we have proposed flag limits for the dielectric data for the pellets. Specifically, if the temperature of the peak dielectric constant falls outside the range of 250 C {+-} 30 C we propose that a flag limit be imposed that will initiate communication between production agency and design agency personnel. If the peak dielectric constant measured falls outside the range 25,000 {+-} 10,000 we also propose that a flag limit be imposed.

  17. Evaluation Of ARG-1 Samples Prepared By Cesium Carbonate Dissolution During The Isolok SME Acceptability Testing

    Evaluation of Defense Waste Processing Facility (DWPF) Chemical Process Cell (CPC) cycle time identified several opportunities to improve the CPC processing time. The Mechanical Systems and Custom Equipment Development (MS and CED) Section of the Savannah River National Laboratory (SRNL) recently completed the evaluation of one of these opportunities - the possibility of using an Isolok sampling valve as an alternative to the Hydragard valve for taking DWPF process samples at the Slurry Mix Evaporator (SME). The use of an Isolok for SME sampling has the potential to improve operability, reduce maintenance time, and decrease CPC cycle time. The SME acceptability testing for the Isolok was requested in Task Technical Request (TTR) HLW-DWPF-TTR-2010-0036 and was conducted as outlined in Task Technical and Quality Assurance Plan (TTQAP) SRNLRP-2011-00145. RW-0333P QA requirements applied to the task, and the results from the investigation were documented in SRNL-STI-2011-00693. Measurement of the chemical composition of study samples was a critical component of the SME acceptability testing of the Isolok. A sampling and analytical plan supported the investigation with the analytical plan directing that the study samples be prepared by a cesium carbonate (Cs2CO3) fusion dissolution method and analyzed by Inductively Coupled Plasma - Optical Emission Spectroscopy (ICP-OES). The use of the cesium carbonate preparation method for the Isolok testing provided an opportunity for an additional assessment of this dissolution method, which is being investigated as a potential replacement for the two methods (i.e., sodium peroxide fusion and mixed acid dissolution) that have been used at the DWPF for the analysis of SME samples. Earlier testing of the Cs2CO3 method yielded promising results which led to a TTR from Savannah River Remediation, LLC (SRR) to SRNL for additional support and an associated TTQAP to direct the SRNL efforts. A technical report resulting from this work was

  18. EVALUATION OF ARG-1 SAMPLES PREPARED BY CESIUM CARBONATE DISSOLUTION DURING THE ISOLOK SME ACCEPTABILITY TESTING

    Edwards, T.; Hera, K.; Coleman, C.

    2011-12-05

    Evaluation of Defense Waste Processing Facility (DWPF) Chemical Process Cell (CPC) cycle time identified several opportunities to improve the CPC processing time. The Mechanical Systems & Custom Equipment Development (MS&CED) Section of the Savannah River National Laboratory (SRNL) recently completed the evaluation of one of these opportunities - the possibility of using an Isolok sampling valve as an alternative to the Hydragard valve for taking DWPF process samples at the Slurry Mix Evaporator (SME). The use of an Isolok for SME sampling has the potential to improve operability, reduce maintenance time, and decrease CPC cycle time. The SME acceptability testing for the Isolok was requested in Task Technical Request (TTR) HLW-DWPF-TTR-2010-0036 and was conducted as outlined in Task Technical and Quality Assurance Plan (TTQAP) SRNLRP-2011-00145. RW-0333P QA requirements applied to the task, and the results from the investigation were documented in SRNL-STI-2011-00693. Measurement of the chemical composition of study samples was a critical component of the SME acceptability testing of the Isolok. A sampling and analytical plan supported the investigation with the analytical plan directing that the study samples be prepared by a cesium carbonate (Cs{sub 2}CO{sub 3}) fusion dissolution method and analyzed by Inductively Coupled Plasma - Optical Emission Spectroscopy (ICP-OES). The use of the cesium carbonate preparation method for the Isolok testing provided an opportunity for an additional assessment of this dissolution method, which is being investigated as a potential replacement for the two methods (i.e., sodium peroxide fusion and mixed acid dissolution) that have been used at the DWPF for the analysis of SME samples. Earlier testing of the Cs{sub 2}CO{sub 3} method yielded promising results which led to a TTR from Savannah River Remediation, LLC (SRR) to SRNL for additional support and an associated TTQAP to direct the SRNL efforts. A technical report resulting

  19. Dispersant tank testing : a review of procedures and considerations

    This paper described 17 critical factors that are relevant for the proper measurement of dispersant effectiveness in tanks. The factors include: mass balance; proper controls; analytic method; time land and length of time plume followed; mathematics of calculation and integration; lower and upper limits of analytical methods; thickness measurement; behaviour of oil with surfactant content; surfactant stripping; recovering the surface oil; background levels of hydrocarbons; fluorescence of dispersant; herding; heterogeneity of slick and plume; true analytical standards; weathering of the oil; and, temperature and salinity. The paper also presented lessons learned over a 7 year period of detailed tank testing at the Imperial Oil tank in Calgary, Alberta and the SERF tank in Corpus Christi, Texas. The 17 critical factors address the many concerns about the behaviour of oil and dispersants regarding tank testing. The procedures proposed in this paper reasonably estimate the effectiveness of dispersants in a large test tank. 22 refs., 1 tab

  20. multiple test procedures and the closure principle: a new look at multiple hypotheses testing in the linear regression model

    Alt, Raimund

    1991-01-01

    summary: in this paper we show how to apply the closure test principle in case of testing linear hypotheses within the classical linear regression model. the closure test principle which was introduced by marcus/peritz/gabriel (1976) results in the construction of test procedures which are in general much more powerful than conventional test procedures like the bonferroni procedure or the scheffe procedure. a small simulation study provides some evidence of the superiority of closed test proc...

  1. Waste acceptance and the DWPF Startup Test Program: Impacts of process changes

    The DWPF is currently carrying out a Startup Test Program which will lead to radioactive operations in the facility. The objective of a significant portion of this program is to demonstrate that the DWPF can reliably make glass which satisfies DOE's product specifications. This objective will be achieved through a series of integrated process campaigns using feeds of various compositions (the Qualification Runs).2 During these campaigns, the DWPF Glass Product Control Programs (GPCP) will be used to ensure that glass is made which meets specifications. The GPCP uses a correlation between glass composition and leach test results to determine whether a particular batch of feed will make acceptable glass (i.e., glass which will meet the specifications)

  2. Waste acceptance and the DWPF Startup Test Program: Impacts of process changes

    Plodinec, M.J.

    1992-08-24

    The DWPF is currently carrying out a Startup Test Program which will lead to radioactive operations in the facility. The objective of a significant portion of this program is to demonstrate that the DWPF can reliably make glass which satisfies DOE's product specifications. This objective will be achieved through a series of integrated process campaigns using feeds of various compositions (the Qualification Runs).2 During these campaigns, the DWPF Glass Product Control Programs (GPCP) will be used to ensure that glass is made which meets specifications. The GPCP uses a correlation between glass composition and leach test results to determine whether a particular batch of feed will make acceptable glass (i.e., glass which will meet the specifications).

  3. Waste acceptance and the DWPF Startup Test Program: Impacts of process changes

    Plodinec, M.J.

    1992-08-24

    The DWPF is currently carrying out a Startup Test Program which will lead to radioactive operations in the facility. The objective of a significant portion of this program is to demonstrate that the DWPF can reliably make glass which satisfies DOE`s product specifications. This objective will be achieved through a series of integrated process campaigns using feeds of various compositions (the Qualification Runs).2 During these campaigns, the DWPF Glass Product Control Programs (GPCP) will be used to ensure that glass is made which meets specifications. The GPCP uses a correlation between glass composition and leach test results to determine whether a particular batch of feed will make acceptable glass (i.e., glass which will meet the specifications).

  4. Dispersant field testing : a review of procedures and considerations

    The effectiveness of a dispersant is defined by the amount of oil that the dispersant puts into the water column compared to the amount of oil that was initially spilled. Effectiveness is generally determined visually in plumes of dispersed oil that are visible from ships and aircraft. This paper describes 25 specific issues and technical concerns regarding field testing of dispersant effectiveness. Recent field tests were reviewed and literature that relates to testing procedures was sited. The 25 factors that are important for the appropriate outcome of dispersant field experiments include: mass balance; proper controls; analytical method; differential plume movement; time lag and length of time followed; mathematics of calculation and integration; lower and upper limits of analytical methods; use of remote sensing; thickness measurement; behaviour of oil with surfactant content; surfactant stripping; tracking surface oil and dispersed oil; recovering surface oil; visibility of oil from the surface; background levels of hydrocarbons; fluorescence of dispersant; herding; emulsion breaking; application success; heterogeneity of slick and plume; deposition measurements; true analytical standards; effect of wind on dispersant and slick; dispersant run-off; and weathering of the oil. It was concluded that the most important factors are the ability to determine mass balance, use proper controls, analytical methods and to avoid procedures that give incorrect results. 34 refs., 4 tabs., 1 fig

  5. 10 CFR 26.91 - Acceptable devices for conducting initial and confirmatory tests for alcohol and methods of use.

    2010-01-01

    ... or that has passed its expiration date. (3) For ASDs that test breath specimens and meet EBT.... Alcohol screening devices (ASDs), including devices that test specimens of oral fluids or breath, must be...) Acceptable evidential breath testing devices. Evidential breath testing devices listed in the NHTSA CPL...

  6. Operational test procedure for Bldg 241-A-701 air compressor

    This document is an Operability Test Procedure (OTP) which will verify and record that the 241-A-701 air compressor and associated equipment operates within their intended design parameters. The activities defined in this OTP will be performed to ensure the daily operation of the new compressed air system can be reliable and efficient. The Compressed Air System (CAS) for 241-A-701 supplies process and instrument air to the A, AX, AY, and AZ tank farms. The primary use of the CAS is for tank farms instrumentation, air operated valves, and air lift circulators

  7. Acceptance test report for tank bottom thermocouples on Tank 241-SY-101

    This test report documents testing performed per WHC-SD-WM-ATP-069, Rev. 2. The proper monitoring of the 241-SY-101 Tank Bottom and Side Thermocouples (TBSTC) by the Data Acquisition and Control System (DACS) will be tested to establish continued operability of the system. During this test, an end-to-end verification of all of the sensor circuits associated with the TBSTCs, which provide signals both to the DACS computer system and an installed temporary Data Logger, shall be performed by injecting a signal at the appropriate field terminal and verifying the circuit completely through the system to the computer in the DACS trailer and the computer monitor used to display the output of the Data Logger. Each injected signal will be adjusted for appropriate 'near zero', 'mid range' and 'near full scale' values for the sensor being tested. The TBSTC screen, which provides for operator interface with the TBSTCs, will be utilized to monitor testing at the DACS computers. Testing per this procedure shall be conducted after the installation of the temporary Data Logger for the TBSTCs is complete. The temporary Data Logger will be installed to monitor the temperature readings of 13 of the 26 Tank Bottom Thermocouples in support of SY-101 excavation testing

  8. 40 CFR 86.165-12 - Air conditioning idle test procedure.

    2010-07-01

    ... 40 Protection of Environment 18 2010-07-01 2010-07-01 false Air conditioning idle test procedure... Complete Heavy-Duty Vehicles; Test Procedures § 86.165-12 Air conditioning idle test procedure. (a) Applicability. This section describes procedures for determining air conditioning-related CO2 emissions...

  9. Compliance with the Nevada Test Site's waste acceptance criteria for vitrified cesium-loaded crystalline silicotitanates

    As part of a joint project between the Oak Ridge National Laboratory (ORNL) and the Savannah River Technology Center (SRTC), Cs-137 loaded crystalline silicotitanate (CST) sorbent will be vitrified in a joule-heated melter. Glass formulation development for this CST sorbent is discussed in an accompanying abstract for this conference. One of the objectives for this project was to ensure that the vitrified waste form could be disposed of at the Nevada Test Site (NTS). To accomplish this objective, the waste form must meet the NTS Waste Acceptance Criteria (WAC). This paper presents SRTC's efforts at ensuring that the glass waste form produced as a result of vitrification of CST will meet all of the criteria of the WAC. The producer must demonstrate that the waste is neither TRU nor mixed, and that the glass has a radionuclide content which is less than the Class C limit of 4,600 Ci/m3. The impact of this requirement on the CST loading in the glass is discussed along with the benefits to the producer which result if greater than Class C waste is accepted by NTS since this limit may be relaxed in the near future. This paper demonstrates that vitrification leads to a waste form which meets all of the criteria of the NTS WAC

  10. Acceptance test for 900 MWe PWR unit replacement steam generators; Essai de reception des generateurs de vapeur de remplacement des tranches REP 900

    Gourguechon, B.

    1993-12-31

    During the first half of 1994, the Gravelines 1 steam generators will be replaced (SG replacement procedure). The new SG`s differ from the former components notably by the alloy used for the tube bundle, in this case, the high chromium content Inconel 690. So, from this standpoint, they are to be considered as PWR 900 replacement SG first models and their thermal efficiency has consequently to be assessed. This will provide an opportunity of ensuring that the performance of the components delivered is in compliance with requirements and of making the necessary provisions if significant deviations are observed. The EFMT branch, which has been in charge of the instrumentation and acceptance of the different SG first models since the first PWR plants were commissioned, will be responsible for the acceptance tests and the ultimate validation of a performance assessment procedure applicable to the future replacement steam generators. The methods and tests proposed for SG expert appraisal are based on consideration of the importance of primary measurement quality for satisfactory SG assessment and of the new test facilities with which the 900 and 1 300 PWR plants are gradually being equipped. These facilities provide an on-site computer environment for tests compatible with the tools (PATTERN, etc.) used at EFMT and in other departments. This test is the first of this kind performed by EFMT and the test facility of a nuclear power plant. (author). 6 figs.

  11. Acceptance tests on the first micro multi-leaf collimator (mMLC) for stereotactic radiosurgery and radiotherapy in India

    The micro multi-Leaf Collimator from BrainLAB integrated on Varian 2100 C/D Linear Accelerator underwent stringent commissioning and acceptance procedures. Excellent agreement was found with the specification standards recommended by national and international bodies. The use of mMLC for SRS and SRT is expected to result in good treatment outcome

  12. Understanding Student Teachers’ Behavioural Intention to Use Technology: Technology Acceptance Model (TAM Validation and Testing

    Kung-Teck, Wong

    2013-01-01

    Full Text Available This study sets out to validate and test the Technology Acceptance Model (TAM in the context of Malaysian student teachers’ integration of their technology in teaching and learning. To establish factorial validity, data collected from 302 respondents were tested against the TAM using confirmatory factor analysis (CFA, and structural equation modelling (SEM was used for model comparison and hypotheses testing. The goodness-of-fit test of the analysis shows partial support of the applicability of the TAM in a Malaysian context. Overall, the TAM accounted for 37.3% of the variance in intention to use technology among student teachers and of the five hypotheses formulated, four are supported. Perceived usefulness is a significant influence on attitude towards computer use and behavioural intention. Perceived ease of use significantly influences perceived usefulness, and finally, behavioural intention is found to be influenced by attitude towards computer use. The findings of this research contribute to the literature by validating the TAM in the Malaysian context and provide several prominent implications for the research and practice of technology integration development.

  13. Embedding Procedure Assistance into Mission Control Tools Project

    National Aeronautics and Space Administration — Procedures are the accepted means of commanding spacecraft. Procedures encode the operational knowledge of a system as derived from system experts, testing,...

  14. Recommended procedures for performance testing of radiobioassay laboratories: Volume 3, In vivo test phantoms

    Draft American National Standards Institute (ANSI) Standard N13.30 (Performance Criteria for Radiobioassay) was developed for the US Department of Energy and the US Nuclear Regulatory Commission to help ensure that bioassay laboratories provide accurate and consistent results. The draft standard describes the procedures necessary to establish a bioassay performance-testing laboratory and program. The bioassay performance-testing laboratory will conduct tests to evaluate the performance of service laboratories. Pacific Northwest Laboratory helped develop testing procedures as part of an effort to evaluate the draft ANSI N13.30 performance criteria by testing the existing measurement capabilities of various bioassay laboratories. This report recommends guidelines for the preparation, handling, storage, distribution, shipping, and documentation of test phantoms used for calibration of measurement systems for direct bioassay. The data base and recommended records system for documenting radiobioassay performance at the service laboratories are also presented

  15. Source test of the prototype neutron detector for the large-acceptance multipurpose spectrometer at RAON

    Lee, Kisoo; Lee, Kyong Sei; Mulilo, Benard; Hong, Byungsik

    2013-05-01

    A neutron detector array will be essential for the study of the nuclear symmetry energy in the large-acceptance multipurpose spectrometer (LAMPS) at the planned rare-isotope beam facility RAON in Korea. We have built the prototype neutron detector for LAMPS and examined its performance by using radiation sources. For data taking, we tested the voltage-threshold discriminator (VTD) and the constant-fraction discriminator (CFD) modules for the pulse process. The intrinsic time resolution of the prototype detector is estimated to be 723 ps for VTD and 488 ps for CFD. The fission neutrons and gammas emitted from 252Cf can be clearly separated in the time distribution. We reconstruct the energy spectrum of the spontaneous fission neutrons from 252Cf, which can be described well by using the empirical Watt spectrum.

  16. Department of Defense picture archiving and communication system acceptance testing: results and identification of problem components.

    Allison, Scott A; Sweet, Clifford F; Beall, Douglas P; Lewis, Thomas E; Monroe, Thomas

    2005-09-01

    The PACS implementation process is complicated requiring a tremendous amount of time, resources, and planning. The Department of Defense (DOD) has significant experience in developing and refining PACS acceptance testing (AT) protocols that assure contract compliance, clinical safety, and functionality. The DOD's AT experience under the initial Medical Diagnostic Imaging Support System contract led to the current Digital Imaging Network-Picture Archiving and Communications Systems (DIN-PACS) contract AT protocol. To identify the most common system and component deficiencies under the current DIN-PACS AT protocol, 14 tri-service sites were evaluated during 1998-2000. Sixteen system deficiency citations with 154 separate types of limitations were noted with problems involving the workstation, interfaces, and the Radiology Information System comprising more than 50% of the citations. Larger PACS deployments were associated with a higher number of deficiencies. The most commonly cited systems deficiencies were among the most expensive components of the PACS. PMID:15924273

  17. Shielding requirements on-site loading and acceptance testing on the Leksell gamma knife.

    Maitz, A H; Lunsford, L D; Wu, A; Lindner, G; Flickinger, J C

    1990-02-01

    On August 14, 1987, the first stereotactic radiosurgical procedure using the gamma knife was performed in North America. Located in a self-contained radiosurgical suite in the basement of Presbyterian-University Hospital in Pittsburgh, Pennsylvania. This device uses 201 highly focused beams 60Co for the single-treatment closed-skull irradiation of brain lesions localized by stereotactic techniques (radiosurgery). One hundred and fifty-two patients with intracranial arteriovenous malformations or brain tumors were treated in the first year of operation. The Presbyterian University Hospital of Pittsburgh gamma knife is the first such unit in which the 60Co sources were loaded on-site. This effort required us to solve some difficult and unusual problems encountered during site preparation, delivery, and loading of the unit in a busy hospital setting. The solutions developed enabled installation and use of the gamma knife with minimal disruption of hospital activities while maintaining acceptable levels of exposure to radiation. Environmental surveys performed during the loading of the 201 radioactive sources (total, 219 TBq) confirmed that on-site loading is possible and practical. Our experience in the design, construction, and implementation of the first North American gamma knife supports the practicality and safety of on-site loading and may be of value in the planning and development of future gamma knife installations. PMID:2406231

  18. Shielding requirements on-site loading and acceptance testing on the Leksell gamma knife

    On August 14, 1987, the first stereotactic radiosurgical procedure using the gamma knife was performed in North America. Located in a self-contained radiosurgical suite in the basement of Presbyterian-University Hospital in Pittsburgh, Pennsylvania. This device uses 201 highly focused beams 60Co for the single-treatment closed-skull irradiation of brain lesions localized by stereotactic techniques (radiosurgery). One hundred and fifty-two patients with intracranial arteriovenous malformations or brain tumors were treated in the first year of operation. The Presbyterian University Hospital of Pittsburgh gamma knife is the first such unit in which the 60Co sources were loaded on-site. This effort required us to solve some difficult and unusual problems encountered during site preparation, delivery, and loading of the unit in a busy hospital setting. The solutions developed enabled installation and use of the gamma knife with minimal disruption of hospital activities while maintaining acceptable levels of exposure to radiation. Environmental surveys performed during the loading of the 201 radioactive sources (total, 219 TBq) confirmed that on-site loading is possible and practical. Our experience in the design, construction, and implementation of the first North American gamma knife supports the practicality and safety of on-site loading and may be of value in the planning and development of future gamma knife installations

  19. Test plan/procedure for the checkout of the USA cable communications test configuration for the electromagnetic compatibility (EMC) tests

    Perry, J. C.

    1975-01-01

    A series of electromagnetic compatibility (EMC) tests were conducted in May, 1975 in the Soviet Union. The purpose of the EMC tests was to determine the effects of the operating environment of the Soviet aircraft, Soyuz, upon the electrical performance of the USA's cable communications equipment located in Soyuz. The test procedures necessary to check out the cable communications test configuration in preparation for the EMC tests are presented.

  20. Factors associated with willingness to accept oral fluid HIV rapid testing among most-at-risk populations in China.

    Huanmiao Xun

    Full Text Available BACKGROUND: The availability of oral fluid HIV rapid testing provides an approach that may have the potential to expand HIV testing in China, especially among most-a-risk populations. There are few investigations about the acceptability of oral fluid HIV testing among most-at-risk populations in China. METHOD: A cross-sectional study with men who have sex with men (MSM, female sex workers (FSW and voluntary counseling and testing (VCT clients was conducted in three cities of Shandong province, China from 2011 to 2012. Data were collected by face-to-face questionnaire. RESULTS: About 71% of participants were willing to accept the oral fluid HIV rapid testing, and home HIV testing was independently associated with acceptability of the new testing method among MSM, FSW and VCT clients (AOR of 4.46, 3.19 and 5.74, respectively. Independent predictors of oral fluid HIV rapid testing acceptability among MSM were having ever taken an oral fluid HIV rapid test (AOR= 15.25, having ever taken an HIV test (AOR= 2.07, and education level (AOR= 1.74. Engagement in HIV-related risk behaviors (AOR= 1.68 was an independent predictor of acceptability for FSW. Having taken an HIV test (AOR= 2.85 was an independent predictor of acceptability for VCT clients. The primary concern about the oral fluid HIV testing was accuracy. The median price they would pay for the testing ranged from 4.8 to 8.1 U.S. dollars. CONCLUSION: High acceptability of oral fluid HIV rapid testing was shown among most-at-risk populations. Findings provide support for oral rapid HIV testing as another HIV prevention tool, and provide a backdrop for the implementation of HIV home testing in the near future. Appropriate pricing and increased public education through awareness campaigns that address concerns about the accuracy and safety of the oral fluid HIV rapid testing may help increase acceptability and use among most-at-risk populations in China.

  1. Refractory Metal Heat Pipe Life Test - Test Plan and Standard Operating Procedures

    Martin, J. J.; Reid, R. S.

    2010-01-01

    Refractory metal heat pipes developed during this project shall be subjected to various operating conditions to evaluate life-limiting corrosion factors. To accomplish this objective, various parameters shall be investigated, including the effect of temperature and mass fluence on long-term corrosion rate. The test series will begin with a performance test of one module to evaluate its performance and to establish the temperature and power settings for the remaining modules. The performance test will be followed by round-the-clock testing of 16 heat pipes. All heat pipes shall be nondestructively inspected at 6-month intervals. At longer intervals, specific modules will be destructively evaluated. Both the nondestructive and destructive evaluations shall be coordinated with Los Alamos National Laboratory. During the processing, setup, and testing of the heat pipes, standard operating procedures shall be developed. Initial procedures are listed here and, as hardware is developed, will be updated, incorporating findings and lessons learned.

  2. Acceptability and feasibility of HIV self-testing among men who have sex with men in Peru and Brazil.

    Volk, Jonathan E; Lippman, Sheri A; Grinsztejn, Beatriz; Lama, Javier R; Fernandes, Nilo M; Gonzales, Pedro; Hessol, Nancy A; Buchbinder, Susan

    2016-06-01

    HIV self-testing has the potential to increase testing frequency and uptake. This pilot study assessed the feasibility and acceptability of HIV self-testing in a sample of sexually active men who have sex with men (MSM) in Peru and Brazil. Participants were trained to use a whole blood rapid HIV self-test and instructed to use the self-test monthly during this three-month study. Test acceptability was measured with self-reported use of the test at the one-month and three-month study visits, and test feasibility was assessed by direct observation of self-test administration at the final three-month visit. A total of 103 participants (52 in Peru and 51 in Brazil) were enrolled, and 86% completed the three-month study. Nearly all participants reported use of the self-test (97% at one-month and 98% at three-month visit), and all participants correctly interpreted the self-administered test results when observed using the test at the final study visit. HIV self-testing with a blood-based assay was highly acceptable and feasible. HIV self-testing may have the potential to increase testing frequency and to reach high-risk MSM not currently accessing HIV-testing services. PMID:25971262

  3. Acceptance test procedure for the master equipment list (MEL)database system -- phase I

    The Waste Remediation System/.../Facilities Configuration Management Integration group has requested development of a system to help resolve many of the difficulties associated with management of master equipment list information. This project has been identified as Master Equipment List (MEL) database system. Further definition is contained in the system requirements specification (SRS), reference 7

  4. Acceptance test procedure (ATP) for the master equipment list(MEL) database system -- phase I

    Thornton, M.W.

    1997-01-08

    The Waste Remediation System Facilities Configuration Management Integration group has requested development of a system to help resolve many of the difficulties associated with management of master equipment list information. This project has been identified as Master Equipment List (MEL) database system. Further definition is contained in the system requirements specification (SRS).

  5. Procedural development for nuclear waste canister impact testing

    Double containment requirements for transporting nuclear waste in glass form are costly and may not be necessary for some waste forms. To allow single containment, a procedure for examining particle size distribution and the amount of respirable particles generated under accident conditions was needed. A statistically designed experiment was conducted to examine the effects of glass temperature, fill rate and canister drop orientation upon the amount of sub-ten micron particles generated under simulated accident conditions. Measuring such small particles is somewhat inaccurate because of material loss in handling. By assuming a lognormal particle size distribution, the amount of sub-ten micron particles was estimated from the results for the larger measurable particles. Analyses revealed no temperature or fill rate effect but indicated that the amount of respirable particles is affected by drop orientation. This led to identification of a worst case drop orientation to be used in qualification testing. 4 refs., 2 figs

  6. An Application of Graphical Approach to Construct Multiple Testing Procedure in a Hypothetical Phase III Design

    Naitee eTing

    2014-01-01

    Full Text Available Many multiple testing procedures (MTP have been developed in recent years. Among these new procedures, the graphical approach is flexible and easy to communicate with non-statisticians. A hypothetical Phase III clinical trial design is introduced in this manuscript to demonstrate how graphical approach can be applied in clinical product development. In this design, an active comparator is used. It is thought that this test drug under development could potentially be superior to this comparator. For comparison of efficacy, the primary endpoint is well established and widely accepted by regulatory agencies. However, an important secondary endpoint based on Phase II findings looks very promising. The target dose may have a good opportunity to deliver superiority to the comparator. Furthermore, a lower dose is included in case the target dose may demonstrate potential safety concerns. This Phase III study is designed as a non-inferiority trial with two doses, and two endpoints. This manuscript will illustrate how graphical approach is applied to this design in handling multiple testing issues.

  7. Acceptability of rapid oral fluid HIV testing among male injection drug users in Taiwan, 1997 and 2007.

    Lyu, Shu-Yu; Morisky, Donald E; Yeh, Ching-Ying; Twu, Shiing-Jer; Peng, Eugene Yu-Chang; Malow, Robert M

    2011-04-01

    Rapid oral fluid HIV testing (rapid oral testing) is in the process of being adapted in Taiwan and elsewhere given its advantages over prior HIV testing methods. To guide this process, we examined the acceptability of rapid oral testing at two time points (i.e., 1997 and 2007) among one of the highest risk populations, male injection drug users (IDUs). For this purpose, an anonymous self-administered survey was completed by HIV-negative IDUs involved in the criminal justice system in 1997 (N (1)=137 parolees) and 2007 (N (2)=106 prisoners). A social marketing model helped guide the design of our questionnaire to assess the acceptability of rapid oral testing. This included assessing a new product, across four marketing dimensions: product, price, promotion, and place. Results revealed that in both 1997 and 2007, over 90% indicated that rapid oral testing would be highly acceptable, particularly if the cost was under US$6, and that a pharmacy would be the most appropriate and accessible venue for selling the rapid oral testing kits. The vast majority of survey respondents believed that the cost of rapid oral testing should be federally subsidized and that television and newspaper advertisements would be the most effective media to advertise for rapid oral testing. Both the 1997 and 2007 surveys suggested that rapid oral HIV testing would be particularly accepted in Taiwan by IDUs after release from the criminal justice system. PMID:21271392

  8. Scaling of Lift Degradation Due to Anti-Icing Fluids Based Upon the Aerodynamic Acceptance Test

    Broeren, Andy P.; Riley, James T.

    2012-01-01

    In recent years, the FAA has worked with Transport Canada, National Research Council Canada (NRC) and APS Aviation, Inc. to develop allowance times for aircraft operations in ice-pellet precipitation. These allowance times are critical to ensure safety and efficient operation of commercial and cargo flights. Wind-tunnel testing with uncontaminated anti-icing fluids and fluids contaminated with simulated ice pellets had been carried out at the NRC Propulsion and Icing Wind Tunnel (PIWT) to better understand the flowoff characteristics and resulting aerodynamic effects. The percent lift loss on the thin, high-performance wing model tested in the PIWT was determined at 8 angle of attack and used as one of the evaluation criteria in determining the allowance times. Because it was unclear as to how performance degradations measured on this model were relevant to an actual airplane configuration, some means of interpreting the wing model lift loss was deemed necessary. This paper describes how the lift loss was related to the loss in maximum lift of a Boeing 737-200ADV airplane through the Aerodynamic Acceptance Test (AAT) performed for fluids qualification. A loss in maximum lift coefficient of 5.24 percent on the B737-200ADV airplane (which was adopted as the threshold in the AAT) corresponds to a lift loss of 7.3 percent on the PIWT model at 8 angle of attack. There is significant scatter in the data used to develop the correlation related to varying effects of the anti-icing fluids that were tested and other factors. A statistical analysis indicated the upper limit of lift loss on the PIWT model was 9.2 percent. Therefore, for cases resulting in PIWT model lift loss from 7.3 to 9.2 percent, extra scrutiny of the visual observations is required in evaluating fluid performance with contamination.

  9. Phased Startup Initiative Phase 3 Test Procedure (OCRWM)

    PAJUNEN, A.L.

    2000-05-10

    The purpose of this test procedure is to safely operate the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) with specific fuel canisters, and show that canisters containing fuel can be retrieved from the canister queue, decapped in the Canister Decapper, loaded into the Primary Clean Machine (PCM) for fuel cleaning, fuel sorted on the Process Table, then loaded back into fuel canisters and relocated in Basin Storage. Additional Data are collected during this test, beyond that collected during production operations. These data support qualifying the cleaning performance of the PCM, assessing the quantity of scrap generated during the cleaning, and evaluating the impact of fuel retrieval operations on the Basin water quality. The additional data collected primarily consist of weighing fuel and scrap at selected points in the operation, as well as photographing fuel and scrap as it is processed. The time to perform operations is also monitored for comparison with design predictions. Water quality data are collected to establish a base line to predict the effectiveness of equipment design for control of contamination and visibility during production operation.

  10. Phased Startup Initiative Phase 3 and 4 Test Procedure (OCRWM)

    The purpose of this test procedure is to safely operate the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) with specific fuel canisters, and show that canisters containing fuel can be retrieved from the canister queue, decapped in the Canister Decapper, and loaded into the Primary Clean Machine (PCM) for fuel cleaning; and that fuel can be sorted on the Process Table, then loaded back into fuel canisters and relocated in basin storage. An option is included to load selected elements into multi-canister overpack (MCO) Fuel Baskets. Additional Data are collected during this test, beyond that collected during production operations. These data support qualifying the cleaning performance of the PCM, assessing the quantity of scrap generated during the cleaning, and evaluating the impact of fuel retrieval operations on the Basin water quality. The additional data collected primarily consist of weighing fuel and scrap at selected points in the operation, as well as photographing fuel and scrap as it is processed. The time to perform operations is also monitored for comparison with design predictions. Water quality data are collected to establish a baseline to predict the effectiveness of equipment design for control of contamination and visibility during production operation

  11. Expose : procedure and results of the joint experiment verification tests

    Panitz, C.; Rettberg, P.; Horneck, G.; Rabbow, E.; Baglioni, P.

    The International Space Station will carry the EXPOSE facility accommodated at the universal workplace URM-D located outside the Russian Service Module. The launch will be affected in 2005 and it is planned to stay in space for 1.5 years. The tray like structure will accomodate 2 chemical and 6 biological PI-experiments or experiment systems of the ROSE (Response of Organisms to Space Environment) consortium. EXPOSE will support long-term in situ studies of microbes in artificial meteorites, as well as of microbial communities from special ecological niches, such as endolithic and evaporitic ecosystems. The either vented or sealed experiment pockets will be covered by an optical filter system to control intensity and spectral range of solar UV irradiation. Control of sun exposure will be achieved by the use of individual shutters. To test the compatibility of the different biological systems and their adaptation to the opportunities and constraints of space conditions a profound ground support program has been developed. The procedure and first results of this joint Experiment Verification Tests (EVT) will be presented. The results will be essential for the success of the EXPOSE mission and have been done in parallel with the development and construction of the final hardware design of the facility. The results of the mission will contribute to the understanding of the organic chemistry processes in space, the biological adaptation strategies to extreme conditions, e.g. on early Earth and Mars, and the distribution of life beyond its planet of origin.

  12. Ageing tests and recovery procedures of silica aerogel

    Silica aerogel has been extensively used in RICH detectors for the identification of charged particles over the momentum range between 1 and 10GeV/c. Tiles of hygroscopic aerogel with large transverse dimensions (20x20cm2) and refractive index n=1.03 have recently been produced for use in the LHCb experiment, allowing pion-kaon identification up to 10GeV/c. The tiles have excellent optical properties (clarity factor better than 0.006μm4/cm and homogeneity σ(n-1)/(n-1)∼1% within the tile). Extensive R and D tests on aerogel samples have been performed. Samples have been exposed to intense irradiation (proton, neutron and gamma), to humid air, to standard black varnish (used to paint the inner surface of RICH detectors), and to C4F10 and CO2 gases. The optical properties of the aerogel have been monitored during these tests and, when required, recovery procedures have been investigated and applied. In particular, regeneration of the tiles has been realized through exposure to dry atmosphere (gaseous N2) or through baking for several hours at 500 deg. C. The measurements demonstrate that the optical properties have been successfully restored to their values at the production stage, and in no case permanent degradation has been observed

  13. 40 CFR 60.46 - Test methods and procedures.

    2010-07-01

    ...). (ii) The emission rate correction factor, integrated or grab sampling and analysis procedure of Method... correction factor, integrated sampling and analysis procedure of Method 3B of appendix A of this part shall... sample, the emission rate correction factor, grab sampling and analysis procedure of Method 3B...

  14. Waste Acceptance Testing of Secondary Waste Forms: Cast Stone, Ceramicrete and DuraLith

    Mattigod, Shas V.; Westsik, Joseph H.; Chung, Chul-Woo; Lindberg, Michael J.; Parker, Kent E.

    2011-08-12

    To support the selection of a waste form for the liquid secondary wastes from WTP, Washington River Protection Solutions has initiated secondary-waste-form testing work at Pacific Northwest National Laboratory (PNNL). In anticipation of a down-selection process for a waste form for the Solidification Treatment Unit to be added to the ETF, PNNL is conducting tests on four candidate waste forms to evaluate their ability to meet potential waste acceptance criteria for immobilized secondary wastes that would be placed in the IDF. All three waste forms demonstrated compressive strengths above the minimum 3.45 MPa (500 psi) set as a target for cement-based waste forms. Further, none of the waste forms showed any significant degradation in compressive strength after undergoing thermal cycling (30 cycles in a 10 day period) between -40 C and 60 C or water immersion for 90 days. The three leach test methods are intended to measure the diffusion rates of contaminants from the waste forms. Results are reported in terms of diffusion coefficients and a leachability index (LI) calculated based on the diffusion coefficients. A smaller diffusion coefficient and a larger LI are desired. The NRC, in its Waste Form Technical Position (NRC 1991), provides recommendations and guidance regarding methods to demonstrate waste stability for land disposal of radioactive waste. Included is a recommendation to conduct leach tests using the ANS 16.1 method. The resulting leachability index (LI) should be greater than 6.0. For Hanford secondary wastes, the LI > 6.0 criterion applies to sodium leached from the waste form. For technetium and iodine, higher targets of LI > 9 for Tc and LI > 11 for iodine have been set based on early waste-disposal risk and performance assessment analyses. The results of these three leach tests conducted for a total time between 11days (ASTM C1308) to 90 days (ANS 16.1) showed: (1) Technetium diffusivity: ANSI/ANS 16.1, ASTM C1308, and EPA 1315 tests indicated that

  15. Waste Acceptance Testing of Secondary Waste Forms: Cast Stone, Ceramicrete and DuraLith

    To support the selection of a waste form for the liquid secondary wastes from WTP, Washington River Protection Solutions has initiated secondary-waste-form testing work at Pacific Northwest National Laboratory (PNNL). In anticipation of a down-selection process for a waste form for the Solidification Treatment Unit to be added to the ETF, PNNL is conducting tests on four candidate waste forms to evaluate their ability to meet potential waste acceptance criteria for immobilized secondary wastes that would be placed in the IDF. All three waste forms demonstrated compressive strengths above the minimum 3.45 MPa (500 psi) set as a target for cement-based waste forms. Further, none of the waste forms showed any significant degradation in compressive strength after undergoing thermal cycling (30 cycles in a 10 day period) between -40 C and 60 C or water immersion for 90 days. The three leach test methods are intended to measure the diffusion rates of contaminants from the waste forms. Results are reported in terms of diffusion coefficients and a leachability index (LI) calculated based on the diffusion coefficients. A smaller diffusion coefficient and a larger LI are desired. The NRC, in its Waste Form Technical Position (NRC 1991), provides recommendations and guidance regarding methods to demonstrate waste stability for land disposal of radioactive waste. Included is a recommendation to conduct leach tests using the ANS 16.1 method. The resulting leachability index (LI) should be greater than 6.0. For Hanford secondary wastes, the LI > 6.0 criterion applies to sodium leached from the waste form. For technetium and iodine, higher targets of LI > 9 for Tc and LI > 11 for iodine have been set based on early waste-disposal risk and performance assessment analyses. The results of these three leach tests conducted for a total time between 11days (ASTM C1308) to 90 days (ANS 16.1) showed: (1) Technetium diffusivity: ANSI/ANS 16.1, ASTM C1308, and EPA 1315 tests indicated that

  16. Client characteristics and acceptability of a home-based HIV counselling and testing intervention in rural South Africa

    Naik, Reshma; Tabana, Hanani; Doherty, Tanya; Zembe, Wanga; Jackson, Debra

    2012-01-01

    Background HIV counselling and testing (HCT) is a critical gateway for addressing HIV prevention and linking people to treatment, care, and support. Since national testing rates are often less than optimal, there is growing interest in expanding testing coverage through the implementation of innovative models such as home-based HIV counselling and testing (HBHCT). With the aim of informing scale up, this paper discusses client characteristics and acceptability of an HBHCT intervention impleme...

  17. Client characteristics and acceptability of a home-based HIV counselling and testing intervention in rural South Africa

    Naik Reshma; Tabana Hanani; Doherty Tanya; Zembe Wanga; Jackson Debra

    2012-01-01

    Abstract Background HIV counselling and testing (HCT) is a critical gateway for addressing HIV prevention and linking people to treatment, care, and support. Since national testing rates are often less than optimal, there is growing interest in expanding testing coverage through the implementation of innovative models such as home-based HIV counselling and testing (HBHCT). With the aim of informing scale up, this paper discusses client characteristics and acceptability of an HBHCT interventio...

  18. Experimental procedures for testing the performance of rail dampers

    Squicciarini, G.; Toward, M. G. R.; Thompson, D. J.

    2015-12-01

    Rail dampers work by increasing the attenuation with distance of vibration transmitted along the rail, a quantity known as the track decay rate. Currently, there are no standardized procedures to measure their effectiveness in reducing rolling noise without the need for in-track installation and time-consuming tests. This paper describes and evaluates experimental procedures for assessing rail dampers. Instead of field measurements it is proposed to use laboratory measurements of vertical and lateral decay rates on a free rail equipped with dampers. These are combined with in-situ measurements on an undamped track. The decay rates of a damped track can be approximated by adding the results of the damped free rail to those of the undamped track. Three different methods are studied to measure the decay rates of damped free rails: (i) using a long rail, in the present work 32 m long, from frequency response functions measured at intervals along the rail; (ii) using a short rail, in the present work 6 m long, from the modal properties of the rail; and (iii) directly from the point and transfer frequency response functions at both ends of the short rail. The latter two are complementary: the modal method is more suited to low frequencies while the direct method is more suited to high frequencies. These methods are evaluated theoretically and by comparison with experimental results. Good agreement is found between the various methods, for vibration in both vertical and lateral directions, between 300 Hz and 5 kHz. In practice, the direct short-rail method is likely to be sufficient for most applications. The limitations of the methods are identified and corrections are proposed for the effect of near-field waves in the rail.

  19. Delinquency and Peer Acceptance in Adolescence: A Within-Person Test of Moffitt's Hypotheses

    Rulison, Kelly L.; Kreager, Derek A.; Osgood, D. Wayne

    2014-01-01

    We tested 2 hypotheses derived from Moffitt's (1993) taxonomic theory of antisocial behavior, both of which are central to her explanation for the rise in delinquency during adolescence. We tested whether persistently delinquent individuals become more accepted by their peers during adolescence and whether individuals who abstain from…

  20. Test plan/procedure for the SPM-1 shipping container system. Revision 0

    The 49 CFR 173.465 Type A packaging tests will verify that SPM-1 will provide adequate protection and pass as a Type A package. Test will determine that the handle of the Pig will not penetrate through the plywood spacer and rupture the shipping container. Test plan/procedure provides planning, pre-test, setup, testing, and post-testing guidelines and procedures for conducting the open-quotes Free Drop Testclose quotes procedure for the SPM-1 package

  1. 9 CFR 147.9 - Standard test procedures for avian influenza.

    2010-01-01

    ... 9 Animals and Animal Products 1 2010-01-01 2010-01-01 false Standard test procedures for avian influenza. 147.9 Section 147.9 Animals and Animal Products ANIMAL AND PLANT HEALTH INSPECTION SERVICE... Blood Testing Procedures § 147.9 Standard test procedures for avian influenza. (a) The agar...

  2. 76 FR 58345 - Energy Conservation Program: Test Procedures for Residential Dishwashers, Dehumidifiers, and...

    2011-09-20

    ... descriptor for each covered product, unless the Secretary determines that-- (i) The current test procedures.... 42 FR 39964 (August 8, 1977). Since that time, the dishwasher test procedure has undergone a number... F inlet water. 48 FR 9202 (March 3, 1983). DOE amended the test procedure again in 1984 to...

  3. Application of ultrasonic testing as acceptance test for the graphite component of HTTR (High Temperature Test Reactor)

    Ultrasonic testing method for the nuclear grade graphite was established. The effectiveness of this method was demonstrated through the application for the graphite component of the HTTR. The characteristics of noise echo were also investigated by relating with mechanical properties. (author). 2 refs., 6 figs., 3 tabs

  4. Value Acceptance on Adolescent Socialization: A Test of a Cognitive-Functional Theory of Television Effects.

    Tan, Alexis; Nelson, Leigh; Dong, Qingwen; Tan, Gerdean

    1997-01-01

    Presents a cognitive-functional explanation of television's influence on Anglo-American, Native American, and Hispanic adolescents' acceptance of values. Finds that adolescents accepted values observed in television when they recognized them (a measure of learning) and when they evaluated the values to be important in "being successful" in the…

  5. Acceptance of referral for partners by clients testing positive for human immunodeficiency virus

    Netsanet F

    2013-01-01

    Full Text Available Fetene Netsanet,1 Ayalew Dessie21IMA World Health SuddHealth Multi Donor Trust Fund-Basic Package of Health Services Project, Juba, South Sudan; 2United States Agency for International Development, Private Health Sector Program, Abt Associates Inc, Addis Ababa, EthiopiaBackground: Human immunodeficiency virus (HIV-positive individuals who do not disclose their HIV status to their partners are more likely to present late for HIV and acquired immune deficiency syndrome (AIDS care than those who have disclosed their HIV status to their partners. A major area of challenge with regards to HIV counseling for clients is disclosure of their HIV status to their partners. The main methods of partner notification are patient referral, provider referral, contract referral, and outreach assistance. The emphasis on a plausible and comprehensive partner referral strategy for widespread positive case detection in resource-limited countries needs to be thought out and developed.Methods: A qualitative study was conducted among newly HIV-positive clients to identify partners for notification and acceptance of referral by their partners. Health service providers working in HIV testing and counseling clinics were also provided with semistructured questionnaires in order to assess their view towards partner notification strategies for clients testing positive for HIV.Results: Fifteen newly diagnosed HIV-positive clients were counseled to provide referral slips to their partners. All clients agreed and took the referral card. However, only eight were willing and actually provided the card to their partners. Five of the eight partners of clients who tested HIV-positive and who were provided with referral cards responded to the referral and were tested for HIV. Three were positive and two were negative. Nine of 11 counselors did not agree to requesting partner locator information from HIV-positive clients for contractual referral and/or outreach assistance. The findings

  6. W-026 acceptance test report plant control system software(submittal {number_sign}223.02)

    Watson, T.L.

    1997-02-14

    Acceptance Testing of the WRAP 1 Plant Control System software was conducted throughout the construction of WRAP 1 with final testing on the glovebox software being completed in December 1996. The software tests were broken out into five sections; one for each of the four Local Control Units and one for the supervisory software modules. This document contains a completed copy of the software tests along with the applicable test log and completed Exception Test Reports. The ETRs outside the scope of the contractor are not signed off. These will be resolved by the Buyer and all 1280 open issues will be tracked on Buyer`s ETR database pending resolution.

  7. Optimization of the general acceptability though affective tests and response surface methodology of a dry cacao powder mixture based beverage

    Elena Chau Loo Kung

    2013-09-01

    Full Text Available This research work had as main objective optimizing the general acceptability though affective tests and response surface methodology of a dry cacao powder mixture based beverage. We obtained formulations of mixtures of cacao powder with different concentrations of 15%, 17.5% and 20%, as well as lecithin concentrations of 0.1%; 0.3%; and 0.5% maintaining a constant content of sugar (25 %, Vanillin (1% that included cacao powder with different pH values: natural (pH 5 and alkalinized (pH 6.5 and pH 8 and water by difference to 100%, generating a total of fifteen treatments to be evaluated, according to the Box-Behnen design for three factors. The treatments underwent satisfaction level tests to establish the general acceptability. The treatment that included cacao powder with a concentration of 17.5 %, pH 6.5 and lecithin concentration of 0.3 % obtained the best levels of acceptability. The software Statgraphics Plus 5.1 was used to obtain the treatment with maximum acceptability that corresponded to cacao powder with pH 6.81, with a concentration of 18.24 % and soy lecithin in 0.28% with a tendency to what was obtained in the satisfaction levels tests. Finally we characterized in a physical-chemistry and microbiological way the optimum formulation as well as evaluated sensitively obtaining an acceptability of 6.17.

  8. Acceptability of using electronic vending machines to deliver oral rapid HIV self-testing kits: a qualitative study.

    Sean D Young

    Full Text Available Rates of unrecognized HIV infection are significantly higher among Latino and Black men who have sex with men (MSM. Policy makers have proposed that HIV self-testing kits and new methods for delivering self-testing could improve testing uptake among minority MSM. This study sought to conduct qualitative assessments with MSM of color to determine the acceptability of using electronic vending machines to dispense HIV self-testing kits.African American and Latino MSM were recruited using a participant pool from an existing HIV prevention trial on Facebook. If participants expressed interest in using a vending machine to receive an HIV self-testing kit, they were emailed a 4-digit personal identification number (PIN code to retrieve the test from the machine. We followed up with those who had tested to assess their willingness to participate in an interview about their experience.Twelve kits were dispensed and 8 interviews were conducted. In general, participants expressed that the vending machine was an acceptable HIV test delivery method due to its novelty and convenience.Acceptability of this delivery model for HIV testing kits was closely associated with three main factors: credibility, confidentiality, and convenience. Future research is needed to address issues, such as user-induced errors and costs, before scaling up the dispensing method.

  9. A proposed rationale and test methodology for establishment of acceptance criteria for vacuum integrity testing of pharmaceutical freeze dryers.

    Hardwick, Lisa M; Nail, Steven L; Jarman, James; Hasler, Kai; Hense, Thomas

    2013-10-01

    A scientific rationale is proposed for the establishment of acceptance criteria for leak rates in pharmaceutical freeze dryers. A method was developed to determine the quantity of air that could leak into any lyophilizer from the outside while still maintaining Class 100/Grade A microbial conditions. A lyophilizing product is assumed most vulnerable to microbial contamination during secondary drying, when mass transfer of water vapor from product to condenser is minimal. Using the void volume of the dryer, calculated from change in internal pressure when a known volume of air is introduced, and the potential maximum bioburden of the leaked air (based on measured values), calculations can determine the allowable leaked volume of air, the flow rate required to admit that volume in a given time frame, and the pressure rise that would result from the leak over a given testing period. For the dryers in this study, using worst-case air quality conditions, it was determined that a leak resulting in a pressure rise of 0.027 mbar over a 30 min period would allow the dryers to remain in secondary drying conditions for 62 h before the established action level of one colony forming unit for each cubic meter of air space would be reached. PMID:23899644

  10. AIChe equipment testing procedure centrifugal compressors : a guide to performance evaluation and site testing

    AIChE

    2013-01-01

    With its engineer-tested procedures and thorough explanations, Centrifugal Compressors is an essential text for anyone engaged in implementing new technology in equipment design, identifying process problems, and optimizing equipment performance.  This condensed book presents a step by step approach to preparing for, planning, executing, and analyzing tests of centrifugal compressors, with an emphasis on methods that can be conducted on-site and with an acknowledgement of the strengths and limitations of these methods. The book opens with an extensive and detailed section offering definitions

  11. South African physicians’ acceptance of e-prescribing technology: an empirical test of a modified UTAUT model

    Jason Cohen

    2013-07-01

    Full Text Available E-prescribing systems hold promise for improving the quality and efficiency of the scripting process. Yet, the use of the technology has been associated with a number of challenges. The diffusion of e-prescribing into physician practices and the consequent realisation of its potential benefits will depend on whether physicians are willing to accept and engage with the technology. This study draws on the Unified Theory of Acceptance and Use of Technology (UTAUT and recent literature on user trust in technology to develop and test a model of the factors influencing South African physicians’ acceptance of e-prescribing. Data was collected from a sample of 72 physicians. Results indicate a general acceptance of e-prescribing amongst physicians who on average reported strong intentions to use e-prescribing technologies if given the opportunity. PLS analysis revealed that physicians’ performance expectancies and perceptions of facilitating conditions had significant direct effects on acceptance whilst trust and effort expectancy had important indirect effects. Social influence and price value perceptions did not add additional explanatory power. The model explained 63% of the variation in physician acceptance.

  12. 9 CFR 147.8 - Procedures for preparing egg yolk samples for diagnostic tests.

    2010-01-01

    ... 9 Animals and Animal Products 1 2010-01-01 2010-01-01 false Procedures for preparing egg yolk samples for diagnostic tests. 147.8 Section 147.8 Animals and Animal Products ANIMAL AND PLANT HEALTH... IMPROVEMENT PLAN Blood Testing Procedures § 147.8 Procedures for preparing egg yolk samples for...

  13. Market testing and consumer acceptance of irradiated rice (Oryza sativa indica Linn.)

    Special grade A fragrant rice (Jasmine rice) of 13% moisture content was obtained from a local miller in Bangkok. Low density polyethylene, 29.5 cm in width x 45 cm in length and 200 micron in thickness, was used to pack the rice with a net weight of 5 kg. The irradiated food label was printed on one side of the bag to comply with food control regulations. The color and the ink for marking were tested for gamma radiation compatibility. A total of 800 bags of rice, with a total gross weight of 4,000 kg, were irradiated at a minimum absorbed dose at 0.5 kGy for insect disinfestation. Radiation treatment was carried out using a multi-purpose, carrier type gamma irradiator (Model JS-8900, Serial No. IR-155) located at the Thai Irradiation Center. Irradiated rice was distributed on a weekly basis to food stores in Bangkok and Pathum Thani, as well as to various governmental organizations and interested individuals. The product was sold at 60 bahts per bag (approx. US$ 2.4) to retailers. Various commercial brands of non-irradiated rice of 5 kg size, were available in the market at 52 to 78 bahts per bag (approx. US $ 2.08 to 3.12), depending on quality and brand name. During the distribution, a leaflet of educational information was given to the consumer. A simple questionnaire used in the marketing trial indicated that 72% of the consumers bought irradiated rice because of the good quality of the product based on visual inspection, and 28% of them were willing to try the new product. Most consumers preferred irradiated rice to chemical treatment (fumigation) for insect disinfestation. However, most consumers were not sure if they would like to buy irradiated rice again unless its cooking quality was acceptable. Market testing of irradiated rice in the upper-class market or supermarket was unsuccessful because of limitations in the sale and service conditions. To meet the requirement of the supermarket retailer, irradiated rice had to be supplied on a monthly basis, with

  14. Statistical method for the determination of equivalence of automated test procedures

    Norman Wiggins; Gorko, Mary A.; Jennifer Llewelyn; K. Rick Lung

    2003-01-01

    In the development of test methods for solid dosage forms, manual test procedures for assay and content uniformity often precede the development of automated test procedures. Since the mode of extraction for automated test methods is often slightly different from that of the manual test method, additional validation of an automated test method is usually required. In addition to compliance with validation guidelines, developers of automated test methods are often asked to demonstrate equivale...

  15. Leach test of six 192-iridium pellets based on the IAEA 'special form' test procedures

    The designation 'special form' may be applied to indispersible solid radioactive material if the material meets the requirements of the tests described in the International Atomic Energy Agency Regulations for the Safe Transport of Radioactive Type Materials. This report presents the procedures and results of a leach test performed as specified in the regulations on 6 'as received' active 192-iridium pellets. Mechanical tests were not carried out prior to or following the leach test. The activity of each of the first 6 water baths was found to be between 2.3 and 12.6 μCi, (8.5 x 104 and 4.7 x 105 Bq) and of the second 6, between 1.3 to 6.0 μCi, (4.8 x 104 to 2.2 x 105 Bq) thus exceeding the allowable limit

  16. Test procedure for the moisture measurement in tyre carcasses

    The present invention pertains generally to a procedure for the moisture measurement in tyre carcasses with textile insertions by means of neutrons. It allows a permanent control during manufacturing. The invention is applicable to the retreading of tyres

  17. A Randomized Controlled Trial of Acceptance-Based Behavior Therapy and Cognitive Therapy for Test Anxiety: A Pilot Study

    Brown, Lily A.; Forman, Evan M.; Herbert, James D.; Hoffman, Kimberly L.; Yuen, Erica K.; Goetter, Elizabeth M.

    2011-01-01

    Many university students suffer from test anxiety that is severe enough to impair performance. Given mixed efficacy results of previous cognitive-behavior therapy (CBT) trials and a theoretically driven rationale, an acceptance-based behavior therapy (ABBT) approach was compared to traditional CBT (i.e., Beckian cognitive therapy; CT) for the…

  18. Empirical Testing of a Theoretical Extension of the Technology Acceptance Model: An Exploratory Study of Educational Wikis

    Liu, Xun

    2010-01-01

    This study extended the technology acceptance model and empirically tested the new model with wikis, a new type of educational technology. Based on social cognitive theory and the theory of planned behavior, three new variables, wiki self-efficacy, online posting anxiety, and perceived behavioral control, were added to the original technology…

  19. Testing procedural justice theory in Belgium and Sweden

    Van Damme, Anjuli; Pauwels, Lieven

    2013-01-01

    Procedural justice theory assumes that trust in procedural justice and in the effectiveness of the police are important issues for building the legitimacy of the aforementioned institution. Additionally, the perception of police legitimacy, as a result of public trust, is necessary for the recognition of police authority. When citizens recognize the right of the police to determine authority, they are assumed to feel the obligation to obey the police and ultimately comply with the law and coo...

  20. Operability test procedure for the Rotary Mode Core Sampling System Exhausters 3 and 4

    This document provides a procedure for performing operability testing of the Rotary Mode Core Sampling System Exhausters 3 ampersand 4. Upon completion of testing activities an operability testing report will be issued