WorldWideScience

Sample records for 1000kw on-site pafc

  1. Development of on-site PAFC stacks

    Hotta, K.; Matsumoto, Y. [Kansai Electric Power Co., Amagasaki (Japan); Horiuchi, H.; Ohtani, T. [Mitsubishi Electric Corp., Kobe (Japan)

    1996-12-31

    PAFC (Phosphoric Acid Fuel Cell) has been researched for commercial use and demonstration plants have been installed in various sites. However, PAFC don`t have a enough stability yet, so more research and development must be required in the future. Especially, cell stack needs a proper state of three phases (liquid, gas and solid) interface. It is very difficult technology to keep this condition for a long time. In the small size cell with the electrode area of 100 cm{sup 2}, gas flow and temperature distributions show uniformity. But in the large size cell with the electrode area of 4000 cm{sup 2}, the temperature distributions show non-uniformity. These distributions would cause to be shorten the cell life. Because these distributions make hot-spot and gas poverty in limited parts. So we inserted thermocouples in short-stack for measuring three-dimensional temperature distributions and observed effects of current density and gas utilization on temperature.

  2. 1000kW on-site PAFC power plant development and demonstration

    Satomi, Tomohide; Koike, Shunichi [Phosphoric Acid Fuel Cell Technology Research Association (PAFC-TRA), Osaka (Japan); Ishikawa, Ryou [New Energy and Industrial Technology Development Organization (NEDO), Tokyo (Japan)

    1996-12-31

    Phosphoric Acid Fuel Cell Technology Research Association (PAFC-TRA) and New Energy and Industrial Technology Development Organization (NEDO) have been conducting a joint project on development of a 5000kW urban energy center type PAFC power plant (pressurized) and a 1000kW on-site PAFC power plant (non-pressurized). The objective of the technical development of 1000kW on-site PAFC power plant is to realize a medium size power plant with an overall efficiency of over 70% and an electrical efficiency of over 36%, that could be installed in a large building as a cogeneration system. The components and system integration development work and the plant design were performed in 1991 and 1992. Manufacturing of the plant and installation at the test site were completed in 1994. PAC test was carried out in 1994, and generation test was started in January 1995. Demonstration test is scheduled for 1995 and 1996.

  3. Demonstration of an on-site PAFC cogeneration system with waste heat utilization by a new gas absorption chiller

    Urata, Tatsuo [Tokyo Gas Company, LTD, Tokyo (Japan)

    1996-12-31

    Analysis and cost reduction of fuel cells is being promoted to achieve commercial on-site phosphoric acid fuel cells (on-site FC). However, for such cells to be effectively utilized, a cogeneration system designed to use the heat generated must be developed at low cost. Room heating and hot-water supply are the most simple and efficient uses of the waste heat of fuel cells. However, due to the short room-heating period of about 4 months in most areas in Japan, the sites having demand for waste heat of fuel cells throughout the year will be limited to hotels and hospitals Tokyo Gas has therefore been developing an on-site FC and the technology to utilize tile waste heat of fuel cells for room cooling by means of an absorption refrigerator. The paper describes the results of fuel cell cogeneration tests conducted on a double effect gas absorption chiller heater with auxiliary waste heat recovery (WGAR) that Tokyo Gas developed in its Energy Technology Research Laboratory.

  4. Development of a 50 kW PAFC power generation system

    Yang, J. C.; Park, Y. S.; Seo, S. H.; Lee, H. J.; Noh, J. S.

    LG-Caltex Oil Corp. developed a 50 kW PAFC stack during 1994-1999. The aim of this study was the preparation of a 50 kW PAFC stack for the application of on-site power generation system. To manufacture the large-size electrodes (4225 cm 2), automated manufacturing facilities were used. These facilities provided uniformity and reproducibility of manufacturing of the electrodes. These electrodes showed high current density (400 mA/cm 2 at 0.65 V) in the unit cell measurement. Only 3% of degradation of cell voltage was observed in the unit cell test over the cumulative operation of 6000 h. The 50 kW PAFC stack was composed of 109 unit cells and 19 cooling plates. The 50 kW stack showed 85% of hydrogen utilization rate and 40% of electrical efficiency (LHV). Uniform voltage distribution among cells (within 5%) was observed during operation. LG-Caltex Oil Corp. is developing the prototype 50 kW PAFC power generation system during the years 2000-2002. This prototype will be composed of reformer, inverter, stack and control systems. The prototype will be tested for the commercial application of on-site power generation. The long run, reliability and economic feasibility of the prototype will be analyzed for commercial power generation.

  5. Influence of impurity gases and operating conditions on PAFC performance

    Hirai, K.; Iwasa, N.; Suzuki, M.; Okada, O. [Osaka Gas Co., Ltd. (Japan)] [and others

    1996-12-31

    On-site Phosphoric Acid Fuel Cell (PAFC) Cogeneration system is installed at various test sites, such as at underground parking lot, within chemical plant premises and near urban streets. Since in the current PAFC system, cathode air is supplied to the cell with no particular pretreatment, impurity gases in the air might influence on cell performance. We have investigated the influence of various impurity gases in the cathode gas, on sub-scale single cells, and have found that NO{sub 2}, SO{sub 2} and toluene affect negatively on cell performance. The results of these experiments and the conceivable mechanism of these effects on cell degradation are reported. We have also investigated the influence of other operating parameters, such as temperature, current density, fuel utilization on cell performance. From these experiments, we have found that operating temperature is a significant factor, which mainly determines cell voltage decline rate. The results of sub-scale single cell tests and a short-stack verification test are also reported.

  6. Evaluation of polyaluminium ferric chloride (PAFC) as a composite coagulant for water and wastewater treatment.

    Gao, B; Yue, Q; Miao, J

    2003-01-01

    Coal gangue is a kind of waste from coal mine processing. Polyaluminium ferric chloride (PAFC), a new type of inorganic composite coagulant, was prepared by using the waste from the Mineral Bureau of Yanzhou, China, hydrochloric acid and calcium carbonate as raw materials. The relationship between the stability of ferric ion and the ionic strength of solution was investigated. The zeta potential of PAFC hydrolysis products of PAFC and the coagulation performances under different pH value were discussed. The turbidity removal properties of PAFC, polyaluminium (PAC) and polyferric sulfate (PFS) were compared, and the color removal effect of PAFC for the wastewater containing suspended dyes was also tested. In addition, the coagulation performance of PAFC for actual wastewaters from petrochemical plant, iron and steel plant, and coal mining processing was evaluated. The experimental results suggest that PAFC took a maximum value of zeta potential at about pH 5.8 on the positive side. Compared with PAC, PAFC gives better turbidity removal performance in the range of pH from 7.0 to 8.4. PAFC gives good color removal performance on suspension dyes. PAFC also gives good wastewater purifying results for the actual wastewater. Therefore, PAFC is a high-effect and stable water treatment agent. PMID:12578184

  7. Evaluation of the performance degradation at PAFC effect of catalyst degradation on electrode performance

    Nishizaki, K.; Uchida, H.; Watanabe, M. [Yamanashi Univ., Kofu (Japan)] [and others

    1996-12-31

    Aiming commercialization of Phosphoric Acid Fuel Cell (PAFC) power plant, many researches and developments have been contributed. Over 20000 hours operations have been demonstrated by many PAFC power plants. But there is no effective method for the estimation of lifetime of electrochemical cells without a practical long-term operation. Conducted by New Energy and Industrial Technology Development Organization (NEDO), cooperative research projects aiming development of PAFC lifetime estimation method have started since 1995 FY in Japan. As part of this project, this work has been performed to clarify basic phenomena of the performance degradation at PAFCs jointly by Yamanashi University, Phosphoric Acid Fuel Cell Technology Research Association (PAFC-TRA) and PAFC manufacturers (Toshiba Co., Mitsubishi Electric Co, Fuji Electric Co.). Among several main causes of the cell performance degradation, effects of catalyst degradation (reduction in metal surface area, dealloying, changes in catalyst support) on PAFC cathode performances are discussed in this work.

  8. Development of the electric utility dispersed use PAFC stack

    Horiuchi, Hiroshi; Kotani, Ikuo [Mitsubishi Electric Co., Kobe (Japan); Morotomi, Isamu [Kansai Electric Power Co., Hyogo (Japan)] [and others

    1996-12-31

    Kansai Electric Power Co. and Mitsubishi Electric Co. have been developing the electric utility dispersed use PAFC stack operated under the ambient pressure. The new cell design have been developed, so that the large scale cell (1 m{sup 2} size) was adopted for the stack. To confirm the performance and the stability of the 1 m{sup 2} scale cell design, the short stack study had been performed.

  9. Estimation of current density distribution of PAFC by analysis of cell exhaust gas

    Kato, S.; Seya, A. [Fuji Electric Co., Ltd., Ichihara-shi (Japan); Asano, A. [Fuji Electric Corporate, Ltd., Yokosuka-shi (Japan)

    1996-12-31

    To estimate distributions of Current densities, voltages, gas concentrations, etc., in phosphoric acid fuel cell (PAFC) stacks, is very important for getting fuel cells with higher quality. In this work, we leave developed a numerical simulation tool to map out the distribution in a PAFC stack. And especially to Study Current density distribution in the reaction area of the cell, we analyzed gas composition in several positions inside a gas outlet manifold of the PAFC stack. Comparing these measured data with calculated data, the current density distribution in a cell plane calculated by the simulation, was certified.

  10. Evaluation of the performance degradation at PAFC effect of electrolyte fill-level on electrode performance

    Kitai, Takashi; Uchida, Hiroyuki; Watanabe, Masahiro [Yamanashi Univ., Kofu (Japan)] [and others

    1996-12-31

    As a complimentary research project to the demonstration project of 5MW and 1MW PAFC plants, the mechanism and rate of deterioration of the cells and stacks have been studied from 1995 FY, with the objective of establishing an estimation method for the service life-time of the cell stacks. This work has been performed in the Basic Research Project, as part of that project on PAFC`s, selecting four subjects (Electrocatalysts degradation, Electrolyte fill-level, Cell material corrosion, Electrolyte loss) as the essential factors relating to the life-time. In this report, we will exhibit the effect of the electrolyte fill-level on the electrode performances.

  11. Evaluation of the performance degradation at PAFC effect of operating conditions on acid loss

    Miyoshi, Hideaki; Uchida, Hiroyuki; Watanabe, Masahiro [Yamanashi Univ., Kofu (Japan)] [and others

    1996-12-31

    As a complimentary research project to the demonstration project of 5MW and 1 MW PAFC plants, the mechanism and rate of deterioration of the cells and stacks have been studied from 1995 FY conducted by NEDO, with the objective of establishing an estimation method for the service life-time of the cell stacks. As part of this project, this work has been performed to clarify basic phenomena of the performance degradation at PAFCs jointly by Yamanashi University, PAFC-TRA and PAFC manufacturers. The acid loss into exhaust gases is one of life limiting factors in PAFCs. To design the cells of long-life, it is important to estimate the phosphoric acid loss and to contrive ideas eliminating it. With the objective of obtaining basic data for simulating the acid loss in the large size cells, the effect of the operating conditions on the acid loss into exhaust gases has been studied experimentally by using a single cell with an active electrode area of 100 cm{sup 2}.

  12. PAFC PDMDAAC复合絮凝剂在地表水处理中的絮凝特性%Coagulation Performance of Composite Flocculant of PAFC PDMDAAC for Surface Water Treatment

    孙翠珍; 朱大伟; 李杰瑞

    2015-01-01

    混凝沉淀法相较其他水处理方法具有多种优点,被广泛应用于地表水处理中,该方法的决定性因素之一是絮凝剂性能的优劣。为了提高絮凝剂处理地表水的效果,以PAFC和PDMDAAC为原料合成PAFC PDMDAAC。研究了在模拟地表水处理中PAFC PDMDAAC投加量、碱化度、( Al+Fe)/PDMDAAC质量比和特性黏度对PAFC PDMDAAC混凝性能的影响。结果表明PAFC PDMDAAC优于PAFC的絮凝效果,PAFC PDMDAAC的最佳絮凝条件:( Al+Fe)/PDMDAAC质量比为10、碱化度为1.0。%Coagulation sedimentation process is widely applied in surface water treatment because of its advantages against other process, and coagulant property is one of the key factors of the process.In order to improve flocculation efficiency of treatment for surface water, a new composite flocculants combined PAFC with PDMDAAC was created.The effect of PAFC PDMDAAC, mass ratio of ( Al +Fe)/PDMDAAC, alkalization degree and intrinsic viscosity on coagulation of surface water were studied.The results show flocculation effect of PAFC PDMDAAC is better than that of PAFC, and the best flocculation conditions of PAFC PDMDAAC are as follows:mass ratio of (Al+Fe)/PDMDAAC is 10, degree of alkalization is 1.0.

  13. Development of a 200kW multi-fuel type PAFC power plant

    Take, Tetsuo; Kuwata, Yutaka; Adachi, Masahito; Ogata, Tsutomu [NTT Integrated Information & Energy System Labs., Tokyo (Japan)

    1996-12-31

    Nippon Telegraph and Telephone Corporation (NFT) has been developing a 200 kW multi-fuel type PAFC power plant which can generate AC 200 kW of constant power by switching fuel from pipeline town gas to liquefied propane gas (LPG) and vice versa. This paper describes the outline of the demonstration test plant and test results of its fundamental characteristics.

  14. Evaluation of the performance degradation at PAFC investigation of dealloying process of electrocatalysts with in-situ XRD

    Nakajima, Noriyuki; Uchida, Hiroyuki; Watanabe, Masahiro [Yamanashi Univ., Kofu (Japan)] [and others

    1996-12-31

    As a complementary research project to the demonstration project of 5MW and 1 MW PAFC plants, the mechanism and rate of deterioration of the cells and stacks have been studied from 1995 FY, with the objective of establishing an estimation method for the service life-time of the cell stacks. This work has been performed in the Basic Research Project, as part of that project on PAFC`s, selecting four subjects (Electrocatalysts degradation, Electrolyte fill-level, Cell material corrosion, Electrolyte loss) as the essential factors relating to the life-time. In this study, the effect of temperature and potential on the dealloying process of electrocatalysts was examined in H{sub 3}PO{sub 4} electrolyte with X-ray diffraction measurement.

  15. Long-term commitment of Japanese gas utilities to PAFCs and SOFCs

    Matsumoto, Kiyokazu; Kasahara, Komei

    Tokyo Gas and Osaka Gas have been committed to addressing the energy- and environment-related issues of Japan through promotion of natural gas, an energy friendly to the environment. Being aware of the diversifying market needs (e.g. efficient energy utilization, rising demand for electricity, etc.), active efforts have been made in marketing gas-fired air-conditioning and co-generation systems. In this process, a high priority has also been placed on fuel cells, particularly for realizing their market introduction. Since their participation in the TARGET Program in USA in 1972, the two companies have been involved with the field testing and operation of phosphoric acid fuel cells (PAFCs), whose total capacity has amounted to 12.4 MW. The two companies have played a vital role in promoting and accelerating fuel cell development through the following means: (1) giving incentives to manufacturers through purchase of units and testing, (2) giving feedback on required specifications and technical problems in operation, and (3) verifying and realizing long-term operation utilizing their maintenance techniques. It has been expected that the primary goal of the cumulative operation time of 40 000 h shall be achieved in the near future. Work has also been in progress to develop SOFC. In the joint R&D of a 25-kW solid oxide fuel cell (SOFC) with Westinghouse, the record operation time of 13 000 h has been achieved. Though still twice as much as the average price of competing equipment, the commercialization of PAFCs is close at hand. By utilizing government spending and subsidies for field testing, work will be continued to verify reliability and durability of PAFCs installed at users' sites. These activities have been expected to contribute to realizing economically viable systems and enhance market introduction. The superlative advantages of fuel cells, particularly their environment-friendly qualities, should be best taken advantage of at an appropriate time. In

  16. Evaluation of the electrode performance for PAFC by using acid absorption, acceleration and ac-impedance measurement

    Kim, Chang-Soo; Song, Rak-Hyun; Choi, Byung-Woo [Korea Institute of Energy Research, Taejon (Korea, Republic of)] [and others

    1996-12-31

    In PAFC, the degradation on cathode electrode caused by carbon corrosion, platinum dissolution and growth is especially severe. An acceleration test is a good technique for evaluating the degradation of electrode performance, because it does not need long time. Coleman et al used thermal cycling and on-off cycling as an acceleration test. Song et al showed that hydrogen shortage decreased the electrode performance more rapidly than that of air shortage in gas shortage test. Honji et al reported that the rate of coarsening of Pt particle is rapid in open circuit potential and this is one of major causes on the performance degradation of electrode. The cathode performance has been studied by using acid absorption, acceleration and ac-impedance measurements as functions of the polytetrafluoroethylene (PTFE) contents and sintering temperatures of the electrode.

  17. Proteasome Accessory Factor C (pafC) Is a novel gene Involved in Mycobacterium Intrinsic Resistance to broad-spectrum antibiotics - Fluoroquinolones

    Qiming Li; Longxiang Xie; Quanxin Long; Jinxiao Mao; Hui Li; Mingliang Zhou; Jianping Xie

    2015-01-01

    Antibiotics resistance poses catastrophic threat to global public health. Novel insights into the underlying mechanisms of action will inspire better measures to control drug resistance. Fluoroquinolones are potent and widely prescribed broad-spectrum antibiotics. Bacterial protein degradation pathways represent novel druggable target for the development of new classes of antibiotics. Mycobacteria proteasome accessory factor C (pafC), a component of bacterial proteasome, is involved in fluoro...

  18. Present on Site

    Ingemann, Bruno

    Why are exhibitions and museums so important? What can they be used for? Who determines relevance in a transformative process? Transforming exhibitions is not just something you do, it is something that gets better the more you do it. This book looks at the intersection of the visitor or user, wh...... • Invisibles – The exhibition design processes • Openings – Category, objects and communication Present on site is relevant not only for students and researchers in the field of museum communication, media and design studies, but also for exhibition and museum practitioners....

  19. ON - SITE MATERIAL MANAGEMENT

    Sahil.R.Choure

    2015-06-01

    Full Text Available Site material management is a process for controlling field and office activities on construction site related to the materials. The site material management system attempts to insure that the right quality and quantity of materials are appropriately delivered and handled onsite in a timely manner. Planning a nd controlling all of the efforts necessary to ensure that the correct quality and quantity of materials are properly specified in a timely manner and most importantly are available at the point of use when required. Materials management is the system whic h represents a major expense in construction, so improving site material management improves opportunities for reducing the overall project costs. Poor management can result in increased costs during construction. Efficient management of materials can resu lt in substantial savings in project costs. This project is about on - site material control and the aim is to minimize delays, wastage of material and indirectly the cost. The project’s focus is on material quality control, proper storage facility, materia l accounting on site of Amanora future towers. The project concentrated on the products that contribute the most to construction organization revenue. Study will be done to understand and analyze the above practices on the construction project of Amanora f uture towers.

  20. Efficient on-site construction

    Thuesen, Christian Langhoff; Hvam, Lars

    2011-01-01

    Purpose – This research aims to analyse the implementation of a German platform for housing projects through a successful case on modern methods of construction featuring efficient on-site construction. Through continuous development, the platform has been carefully designed to suit a carefully...... costing); and incremental rather than radical innovation. Originality/value – The findings challenge the predominant understanding of industrialisation of the construction processes, illustrating how substantial improvements can be achieved through platform thinking, on-site production and traditional...... construction practices....

  1. CTBT on-site inspections

    Zucca, J. J. [Principal Deputy, Global Security Directorate, Lawrence Livermore National Laboratory, Livermore, California (United States)

    2014-05-09

    On-site inspection (OSI) is a critical part of the verification regime for the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The OSI verification regime provides for international inspectors to make a suite of measurements and observations on site at the location of an event of interest. The other critical component of the verification regime is the International Monitoring System (IMS), which is a globally distributed network of monitoring stations. The IMS along with technical monitoring data from CTBT member countries, as appropriate, will be used to trigger an OSI. After the decision is made to carry out an OSI, it is important for the inspectors to deploy to the field site rapidly to be able to detect short-lived phenomena such as the aftershocks that may be observable after an underground nuclear explosion. The inspectors will be on site from weeks to months and will be working with many tens of tons of equipment. Parts of the OSI regime will be tested in a field exercise in the country of Jordan late in 2014. The build-up of the OSI regime has been proceeding steadily since the CTBT was signed in 1996 and is on track to becoming a deterrent to someone considering conducting a nuclear explosion in violation of the Treaty.

  2. Training Artisans On-Site

    Edoghogho Ogbeifun

    2011-09-01

    Full Text Available The decline in apprenticeship in both the public and private sectors, the increasing use of sub-contractors as well as the uncoordinated approach in the informal sector are contributing factors to the shortage of skilled artisans in the construction industry. Artisans training can be introduced and implemented through the adoption of progressive implementation of construction processes commencing work from areas requiring low skill demands to areas of high skill demand. The success of this principle hinges on the collaborative effort of the key project stakeholders. The client should be willing to absorb extra cost and delays in the project; the design and contract documentation should facilitate on-site training, and  the consultant actively guide the contractor and the construction processes to achieve the training objectives. The exploratory research method was adopted in this study and research revealed that this principle was used in a project in the UK and in the development of infrastructure in the tourism industry of South Africa .It is being recommended that the principle be adapted by the public sector for the development of small size infrastructures that can be repeated in many places. This will boost the quality and quantity of artisans, enhance employability, reduce rural urban migration and alleviate poverty.Keywords: Skilled artisans, on-site training, progressive construction processes, project stakeholders, contract documentation. 

  3. Requirements of on-site facilities

    1) Requirements of on-site facilities: a) brief description of supplying the site with electricity and water; communication facilities, b) necessary facilities for containment and pipeline installation, c) necessary facilities for storage, safety, accommodation of personnel, housing; workshops; 2) Site management: a) Organisation schedules for 'turn-key-jobs' and 'single commission', b) Duties of the supervisory staff. (orig.)

  4. Recommendations for on-site vibration standards

    Unless certain common sense precautions are observed, the luminosity of the Collider may be adversely affected by otherwise preventable ground vibrations. Previous work indicates that ground vibrations can be thought of as being caused by the sum of (a) natural and (b) cultural (i.e., man-made) effects, of which the latter can be further divided into uncontrollable and controllable. Examples of category (b) include: traffic, both on site and off site; construction activity on site and off site; assembly of equipment in nearby I.R. Halls, even footsteps in the tunnel; or continuously operating machinery. This note addresses question with respect to category (b) iv., only. As a guide, the order of magnitude of amplitudes and frequencies of presently, (on site) known noise polluters is described in relation to naturally occurring disturbances and to the tolerances required for successful Collider operation. Some methods of mitigating the effects of on site machinery are suggested. Finally, a vibration tolerance level specification is recommended as well as a mechanism to police adherence to such standards. 6 figures

  5. SICOM: On-site inspection systems

    As the irradiation conditions become more demanding for the fuel than in the past, there is a need for surveillance programs to gather in-reactor operating experience. The data obtained in these programs can be used to assess the performance of current fuel designs and the improvements incorporated to the fuel assembly design, the performance of the advanced cladding alloys, etc. In these regards, valuable data is obtained from on-site fuel inspections. These on-site data comprise fuel assembly dimensional data such as length and distortion (tilt, twist and bow) and fuel rod data such as length and oxide thickness. These data have to be reliable and accurate to be useful thus, demanding a high precision inspection equipment. However, the inspection equipment has to be also robust and flexible enough to operate in the plant spent fuel pool and, sometimes, without interfering in the works carried out during a plant outage. To meet these requirements, during the past years ENUSA and TECNATOM have developed two on-site inspection systems. While the first system can perform most of the typical measurements in a stand-alone manner thus, without interfering with the critical path of the reload, the second one reduces the inspection time but requires using the plant capabilities. The paper describes both equipment for fuel on-site inspection, their characteristics and main features. (author)

  6. On site monitoring of concrete reinforcement corrosion

    Reinforcement corrosion is the result of the penetration through the concrete cover of the carbon dioxide (carbonation) and of chlorides. It is not a usual event in nuclear plants due to the relatively short service life required. However, in waste storage facilities with much longer target service life.. it may be one of the most relevant deterioration processes. Therefore. its detection and measurement should be one of the aspects to be taken into account in the overall management of these kind of installations. In present paper, the most usual electrochemical techniques to measure reinforcement corrosion are described. The aims of the application of these techniques is. 1) to control the performance of new constructions (embedded sensors). 2) to detect corroding areas in existing structures (by on-site measurements or by installing external sensors) and implement these values in models to recalculate the structural performance and 3) to control the efficiency of repair techniques. In the paper is as well presented the evolution from 1995 of corrosion parameters (corrosion rate, corrosion potential, electrical resistivity, concrete strains, oxygen availability) obtained in a pilot container buried in real conditions in the repository of El-Carbril-Spain. The results indicate that the temperature is the most relevant variable influencing the measurements. In conclusion: Corrosion of reinforcement can be approximately model and accurately measured on-site. The periodical corrosion rate measurements on its monitoring seems very necessary to assess present conditions of concrete structures and is a very useful tool in the case of cooling towers of power plants. Techniques based in the measurement of Polarization Resistance have been implemented in portable corrosion rate meters to obtain corrosion rate values, and corrosion-data-loggers are now operative in different structures to monitor corrosion related parameters. (authors)

  7. Liability for on-site nuclear property damage

    Typically, liability for on-site property addressed in contracts between operator and its suppliers. Nuclear power plant operators ordinarily protect themselves against risk of nuclear damage to on-site property by insurance. Nuclear liability laws do not specifically address liability for nuclear damage to on-site property. Nuclear plant owners should address risk of damage to on-site property when developing risk management program

  8. DBE on site public relations tasks

    Full text: Thesis: There is no 'golden rule' for an immediate increase in acceptance of nuclear facility sites - this applies to nuclear power plants as well as waste management facilities. The German Company for the Construction and Operation of Repositories for Waste Products (DBE - entrusted on behalf of the Federal Government with the management of all three German waste repository sites (projects), Morsleben, Konrad, Gorleben - concentrates in the field of public relations work on the following: - caring for (and informing) visitors from home and abroad; - cooperation with local and regional authorities and their representatives, press, media, etc. including associate editing of the GORLEBEN-information leaflet which appears monthly or every second month in cooperation with the Federal Board for Radiation Protection (BfS), as well as press releases if required; - responding to inquiries and visit requests of press, radio and TV. Basic work: - early and comprehensive information of the public at the sites about progress of work and possible exceptional events with special involvement of local politicians and representatives as well as press agencies. Close contacts exist to the local paper and to a national paper; - municipal representatives and the media are regularly directly informed on site or sporadically at their own request; - special emphasis is placed on the spoken, explaining word, namely that communication and discussion are valued more highly than written material. Of course, transparencies, films and brochures are available to support the spoken word; - continual availability for discussion and information presentations e.g., also at weekends; - maintenance of casual contacts to opponents of the plant. In Gorleben - the site of further waste management facilities beside the exploration mine - there is close cooperation with representatives of the other important companies and institutions hence, visitors are generally pooled, i.e., the majority

  9. On-site monitoring of plutonium workers

    Full text: As part of the Maralinga rehabilitation program it is necessary to implement a system of on-site monitoring for the workers in order to ensure that they do not exceed recommended dose limits. The main problem in the rehabilitation work is the inhalation of dusts which contain micron sized plutonium particles. Using the new ICRP lung model and available data derived from measurements on contaminated soils, the intake for a dose of 20 mSv was calculated to be 1200 Bq. Four methods are available for direct measurements on workers; nasal swabs, faecal analysis, urine analysis and lung monitoring. The first two techniques are sensitive but will give varying results depending of the time interval between exposure and sampling. They are also difficult to implement on a routine basis. For the second two techniques, the activity in the lungs and the activity excreted per day in the urine remain relatively constant for several years following an intake, making more accurate dose estimates possible. The ICRP lung model predicts deposition in the lung of the order of 5% of intake and urinary excretion models predict approximately 10-5 of this will be excreted daily in the urine. Lung monitoring of workers will be performed routinely at Maralinga in a partly enclosed room constructed from 10cm of steel, using two 50 mm diameter germanium detectors shielded with lead collimators. The detectors will measure 241Am, which has grown in following the decay of 241Pu, and the minimum detectable activity will be 15 - 20 Bq depending on the chest thickness and chest wall thickness of the individual being measured. Urine will be collected routinely and selected samples will be measured. The minimum detectable activity will be 2001μBq of 239Pu in a daily urine sample

  10. On-site contingency planning at Pt. Lepreau NGS

    On-site contingency plans are required as part of the licensing process for Canadian nuclear power plants. The objective of these plans is to mitigate the consequences of an emergency and to provide assurance that all reasonable measures will be taken to protect health and safety and minimize property damage. This paper describes the on-site contingency plans that have been prepared for the Pt. Lepreau Generating Station. The interaction between the on-site and off-site plans is also discussed

  11. Managing the risks of on-site health centers.

    Gorman, Kathleen M; Miller, Ross M

    2011-11-01

    This review sought to assess compliance concerns, determine risk management strategies, and identify opportunities for future research to contribute to employers' understanding of the laws and regulations that apply to on-site care. A comprehensive review of databases, professional organizations' websites, and journals resulted in 22 publications reporting on the consequences of noncompliance among on-site health centers accepted for inclusion. None of those studies reported a study design or quantifiable outcome data. Two noncompliance themes were repeated among the publications. First, direct penalties included fines, civil actions, loss of licensure, and, potentially, criminal charges. Second, noncompliance also resulted in indirect costs such as employee mistrust and lowered standards of care, which jeopardize on-site health centers' ability to demonstrate a return on investment. Further research with rigorous methodology is needed to inform employer decisions about on-site health services and associated risk management. PMID:22017191

  12. Predicting on-site environmental impacts of municipal engineering works

    Gangolells Solanellas, Marta; Casals Casanova, Miquel; Forcada Matheu, Núria; Macarulla Martí, Marcel

    2014-01-01

    The research findings fill a gap in the body of knowledge by presenting an effective way to evaluate the significance of on-site environmental impacts of municipal engineering works prior to the construction stage. First, 42 on-site environmental impacts of municipal engineering works were identified by means of a process-oriented approach. Then, 46 indicators and their corresponding significance limits were determined on the basis of a statistical analysis of 25 new-build and remodelling mun...

  13. Anaerobic on-site wastewater treatment at low temperatures

    Luostarinen, Sari

    2005-01-01

    Anaerobic on-site wastewater treatment at low temperaturesAnaerobic treatment stabilises the treated waste(water), and enables production of renewable energy (methane, hydrogen), and preservation of valuable resources (nutrients). Decentralised, on-site application of anaerobic treatment for communities or individual households may thus provide combined waste(water) management, energy production, and nutrient recovery. Two-phased UASB-septic tanks were feasible for treatment of synthetic blac...

  14. Predicting on-site environmental impacts of municipal engineering works

    Gangolells, Marta, E-mail: marta.gangolells@upc.edu; Casals, Miquel, E-mail: miquel.casals@upc.edu; Forcada, Núria, E-mail: nuria.forcada@upc.edu; Macarulla, Marcel, E-mail: marcel.macarulla@upc.edu

    2014-01-15

    The research findings fill a gap in the body of knowledge by presenting an effective way to evaluate the significance of on-site environmental impacts of municipal engineering works prior to the construction stage. First, 42 on-site environmental impacts of municipal engineering works were identified by means of a process-oriented approach. Then, 46 indicators and their corresponding significance limits were determined on the basis of a statistical analysis of 25 new-build and remodelling municipal engineering projects. In order to ensure the objectivity of the assessment process, direct and indirect indicators were always based on quantitative data from the municipal engineering project documents. Finally, two case studies were analysed and found to illustrate the practical use of the proposed model. The model highlights the significant environmental impacts of a particular municipal engineering project prior to the construction stage. Consequently, preventive actions can be planned and implemented during on-site activities. The results of the model also allow a comparison of proposed municipal engineering projects and alternatives with respect to the overall on-site environmental impact and the absolute importance of a particular environmental aspect. These findings are useful within the framework of the environmental impact assessment process, as they help to improve the identification and evaluation of on-site environmental aspects of municipal engineering works. The findings may also be of use to construction companies that are willing to implement an environmental management system or simply wish to improve on-site environmental performance in municipal engineering projects. -- Highlights: • We present a model to predict the environmental impacts of municipal engineering works. • It highlights significant on-site environmental impacts prior to the construction stage. • Findings are useful within the environmental impact assessment process. • They also

  15. On-site disposal as a decommissioning strategy

    On-site disposal is not a novel decommissioning strategy in the history of the nuclear industry. Several projects based on this strategy have been implemented. Moreover, a number of studies and proposals have explored variations within the strategy, ranging from in situ disposal of entire facilities or portions thereof to disposal within the site boundary of major components such as the reactor pressure vessel or steam generators. Regardless of these initiatives, and despite a significant potential for dose, radioactive waste and cost reduction, on-site disposal has often been disregarded as a viable decommissioning strategy, generally as the result of environmental and other public concerns. Little attention has been given to on-site disposal in previous IAEA publications in the field of decommissioning. The objective of this report is to establish an awareness of technical factors that may or may not favour the adoption of on-site disposal as a decommissioning strategy. In addition, this report presents an overview of relevant national experiences, studies and proposals. The expected end result is to show that, subject to safety and environmental protection assessment, on-site disposal can be a viable decommissioning option and should be taken into consideration in decision making

  16. Experiences with on-site power sources at KCB

    The design of the nuclear power station is of the late sixties. The experiences with the on-site power sources, signal processing and some of the resulting modifications of the design of the power plant are mentioned. In order to let the design satisfy as much as possible present ideas about safety, it was decided to realize a total new and Independent decay heat removal System. With this system a second independent on-site power System is at disposal in case of accident situations. (author)

  17. Number of on-site personnel and their functions

    After the definition of the general tasks, the development of an organization chart for on-site personnel is shown, the number and qualifications are indicated relating to the specific jobs. The functions of the different people are explained in detail. (orig.)

  18. On-site inspections: The ultimate verification measure

    Having existed for a mere six weeks in 2008, the State of Arcania was short-lived. The fictitious state helped to test on-site inspections, a key element of a global alarm system that monitors the Earth for signs of nuclear explosions. The Preparatory Commission for the Comprehensive Nuclear-Test-Ban Treaty Organization (CTBTO) is mandated to build this system to verify States' compliance with the Comprehensive Nuclear-Test-Ban Treaty (CTBT). On-site inspections (OSI ) complement the verification regime's other elements: the International Monitoring System with its network of 337 facilities, the International Data Centre with its extensive data analysis capacities, and the Global Communications Infrastructure. On-site inspections can be invoked only after the Treaty's entry into force. A Member State may request an inspection should the analysis of monitoring data indicate that a nuclear explosion was carried out in violation of the CT BT. Facts gathered directly on the ground during an inspection will help States to establish whether or not a nuclear explosion did indeed take place. Thus, on-site inspections constitute the final verification measure under the Treaty.

  19. On-site early-warning system for Bishkek (Kyrgyzstan

    Dino Bindi

    2015-04-01

    Full Text Available In this work, the development of an on-site early warning system for Bishkek (Kyrgyzstan is outlined. Several low cost sensors equipped with MEMS accelerometers are installed in eight buildings distributed within the urban area. The different sensing units communicate each other via wireless links and the seismic data are streamed in real-time to the data center using internet. Since each single sensing unit has computing capabilities, software for data processing can be installed to perform decentralized actions. In particular, each sensing unit can perform event detection task and run software for on-site early warning. If a description for the vulnerability of the building is uploaded in the sensing unit, this piece of information can be exploited to introduce the expected probability of damage in the early-warning protocol customized for a specific structure.

  20. The feasibility of mobile computing for on-site inspection.

    Horak, Karl Emanuel; DeLand, Sharon Marie; Blair, Dianna Sue

    2014-09-01

    With over 5 billion cellphones in a world of 7 billion inhabitants, mobile phones are the most quickly adopted consumer technology in the history of the world. Miniaturized, power-efficient sensors, especially video-capable cameras, are becoming extremely widespread, especially when one factors in wearable technology like Apples Pebble, GoPro video systems, Google Glass, and lifeloggers. Tablet computers are becoming more common, lighter weight, and power-efficient. In this report the authors explore recent developments in mobile computing and their potential application to on-site inspection for arms control verification and treaty compliance determination. We examine how such technology can effectively be applied to current and potential future inspection regimes. Use cases are given for both host-escort and inspection teams. The results of field trials and their implications for on-site inspections are discussed.

  1. On-site tests on the nuclear power plants

    On-site tests and experiments are performed by EDF Research and Development Division on the nuclear power plants to assess the behaviour of major components submitted to thermal and vibratory solicitations. On-going studies deal with the qualification of new nuclear power plant standard and with the feedback of plants under operation. The tests, particularly the investigation tests, correspond to large investments and entail an important data volume which must ensure the continuity over a long period of the order of magnitude of the in-service plant life (around 40 years). This paper addresses the on-site experimental activities, describes the means to be used, and gives an example: the qualification of SG of new 1450 MW nuclear power plants. (author)

  2. AB005. Genomics on site of detection of malaria

    Sugano, Sumio; Yamagishi, Junya; Mongan, Arthur E.; Tuda, Joesf; Suzuki, Yutaka

    2015-01-01

    Nanopore sequencer, MinION, has enabled sequencing analysis without pre-installation of expensive conventional sequencers or pre-requisite of specific skills in biological experiments. Even electric supply is not always necessary, by connecting MinION to a laptop PC. These features of MinION have opened the opportunity to enable precise genotyping of pathogens on site. In this study, we conducted genotyping of presumed drug resistance-causing SNVs in malaria parasites, Plasmodium falciparum. ...

  3. Consideration of accident events during on-site waste handling

    The safe on-site transport of spent nuclear fuel must rely on the structural integrity of the transport container and the system of transport. Regard for safe and efficient on-site transport routes are important and manageable using well thought-out planning. Difficulties arise when non-manageable incidences occur such as flying debris from tornado-force winds that may result in high velocity impact on the transport system. Part of the site Nuclear Safety Design Guide considers design basis tornado (Level F0) incidents. A Dry Storage Container (DSC) is used to transport and store spent fuel. A DSC is loaded with spent fuel and typically travels on-site to a processing building for permanent lid attachment. During on-site transport a lid clamp is utilized to ensure the container lid remains in place. This paper consists of simulations that consider several wind borne projectiles impacting the DSC. These types of postulated accident scenarios are analysed using detailed nonlinear finite element techniques. A state-of-the-art, large deformation, non-linear, finite element code is used in the simulations. Projectile impact poses two concerns. Large object impact (large poles, piping) in the vicinity of the lid/container interface may result in damage to the lid clamp and dislodging of the lid. Small object impact (slender solid rods) may result in through-wall penetration and loss of shielding. Impact simulation results for these two types of objects show that for large projectiles the lid clamp retains the lid/body interface and for small projectiles there is no penetration of the container wall, ensuring safe containment of spent fuel under tornado conditions. (author)

  4. On-site testing of crop drying fans

    Winkelman, Paul M.

    1988-01-01

    The commercial peanut dryers used today were first conceived when energy was relatively inexpensive. Since then, energy costs have increased significantly, and more efficient peanuts dryers are desirable. To evaluate dryer efficiency, a mobile fan test facility was designed, built and calibrated for on-site fan airflow and energy measurements. Four-, six-, and eight-trailer peanut dryers were tested for performance. The characteristics observed were delivery of fan airflow as compared to m...

  5. Continuous feed, on-site composting of kitchen garbage.

    Hwang, Eung-Ju; Shin, Hang-Sik; Tay, Joo-Hwa

    2002-04-01

    Kitchen garbage generated at a school cafeteria was treated and stabilised in a controlled on-site composting unit for volume reduction and on-site utilisation of processed garbage. The on-site composter was fed with the garbage on a daily basis during the two-months experimental period. Compost was not removed from the unit but was entirely reused as a bulking agent in order to minimise the need for additional bulking agent and compost handling. Performance of the composter tinder this condition was investigated. Most of the easily degradable organic matter (EDM) in the garbage was biodegraded rapidly, and the final product had a low content of EDM. Lipids, total sugar, and hemi-cellulose were degraded 96%, 81%, and 66% respectively. Free air space (FAS) was higher than 0.5 all the time, so accumulation of dry matter in the unit was not significant in reducing reaction efficiency. Other reaction parameters such as pH and MC were kept within a suitable range; however, it was advisable to maintain MC at over 46%. As a result, this method of operation was able to stabilise the garbage with low sawdust demand and little compost production. PMID:12058817

  6. Effective hydrogen generator testing for on-site small engine

    Chaiwongsa, Praitoon; Pornsuwancharoen, Nithiroth; Yupapin, Preecha P.

    2009-07-01

    We propose a new concept of hydrogen generator testing for on-site small engine. In general, there is a trade-off between simpler vehicle design and infrastructure issues, for instance, liquid fuels such as gasoline and methanol for small engine use. In this article we compare the hydrogen gases combination the gasoline between normal systems (gasoline only) for small engine. The advantage of the hydrogen combines gasoline for small engine saving the gasoline 25%. Furthermore, the new concept of hydrogen combination for diesel engine, bio-diesel engine, liquid petroleum gas (LPG), natural gas vehicle (NGV), which is discussed in details.

  7. On-site hydrogen generation from biodiesel and diesel

    Martin, Stefan

    2015-01-01

    The lack of hydrogen infrastructure and distribution poses an obstacle for the introduction of fuel cell vehicles to the market. Therefore it is reasonable to consider using liquid fuels for on-board or on-site hydrogen generation. Within the FP7 project NEMESIS2+ (01/2012-06/2015, www.nemesis-project.eu) a small-scale hydrogen generator capable of producing 50 Nm3h-1 from biodiesel and diesel is currently being developed. Reduction of hydrogen production costs (< 5.0 € per kg), high overall...

  8. The On-Site Analysis of the Cherenkov Telescope Array

    Bulgarelli, Andrea; Zoli, Andrea; Aboudan, Alessio; Rodríguez-Vázquez, Juan José; De Cesare, Giovanni; De Rosa, Adriano; Maier, Gernot; Lyard, Etienne; Bastieri, Denis; Lombardi, Saverio; Tosti, Gino; Bergamaschi, Sonia; Beneventano, Domenico; Lamanna, Giovanni; Jacquemier, Jean; Kosack, Karl; Antonelli, Lucio Angelo; Boisson, Catherine; Borkowski, Jerzy; Buson, Sara; Carosi, Alessandro; Conforti, Vito; Colomé, Pep; Reyes, Raquel de los; Dumm, Jon; Evans, Phil; Fortson, Lucy; Fuessling, Matthias; Gotz, Diego; Graciani, Ricardo; Gianotti, Fulvio; Grandi, Paola; Hinton, Jim; Humensky, Brian; Inoue, Susumu; Knödlseder, Jürgen; Flour, Thierry Le; Lindemann, Rico; Malaguti, Giuseppe; Markoff, Sera; Marisaldi, Martino; Neyroud, Nadine; Nicastro, Luciano; Ohm, Stefan; Osborne, Julian; Oya, Igor; Rodriguez, Jerome; Rosen, Simon; Ribo, Marc; Tacchini, Alessandro; Schüssler, Fabian; Stolarczyk, Thierry; Torresi, Eleonora; Testa, Vincenzo; Wegner, Peter

    2015-01-01

    The Cherenkov Telescope Array (CTA) observatory will be one of the largest ground-based very high-energy gamma-ray observatories. The On-Site Analysis will be the first CTA scientific analysis of data acquired from the array of telescopes, in both northern and southern sites. The On-Site Analysis will have two pipelines: the Level-A pipeline (also known as Real-Time Analysis, RTA) and the level-B one. The RTA performs data quality monitoring and must be able to issue automated alerts on variable and transient astrophysical sources within 30 seconds from the last acquired Cherenkov event that contributes to the alert, with a sensitivity not worse than the one achieved by the final pipeline by more than a factor of 3. The Level-B Analysis has a better sensitivity (not be worse than the final one by a factor of 2) and the results should be available within 10 hours from the acquisition of the data: for this reason this analysis could be performed at the end of an observation or next morning. The latency (in part...

  9. Status of small reactor designs without on-site refuelling

    There is an ongoing interest in member states in the development and application of small and medium sized reactors (SMRs). In the near term, most new NPPs are likely to be evolutionary designs building on proven systems while incorporating technological advances and often the economics of scale, resulting from the reactor outputs of up to 1600 MW(e). For the longer term, the focus is on innovative designs aiming to provide increased benefits in the areas of safety and security, non-proliferation, waste management, resource utilization and economy, as well as to offer a variety of energy products and flexibility in design, siting and fuel cycle options. Many innovative designs are reactors within the small-to-medium size range, having an equivalent electric power less than 700 MW(e) or even less than 300 MW(e). A distinct trend in design and technology development, accounting for about half of the SMR concepts developed worldwide, is represented by small reactors without on-site refuelling. Such reactors, also known as battery-type reactors, could operate without reloading and shuffling of fuel in the core over long periods, from 5 to 25 years and beyond. Upon the advice and with the support of IAEA member states, within its Programme 1 'Nuclear Power, Fuel Cycle, and Nuclear Science', the IAEA provides a forum for the exchange of information by experts and policy makers from industrialized and developing countries on the technical, economic, environmental, and social aspects of SMRs development and implementation in the 21st century, and makes this information available to all interested Member States by producing status reports and other publications dedicated to advances in SMR technology. The objective of this report is to provide Member States, including those just considering the initiation of nuclear power programmes and those already having practical experience in nuclear power, with a balanced and objective information on important development trends and

  10. Utilizing the fluidized bed to initiate water treatment on site

    Escalating wastewater disposal costs coupled with enforcement of stricter regulations push industrial sites previously without water treatment to treat on site. These sites, inexperienced in water treatment, require a treatment technology that is easily installed, operated, and maintained. The aerobic granular activated carbon (GAC) fluidized bed incorporates biological and adsorptive technologies into a simple, cost-effective process capable of meeting strict effluent requirements. Two case studies at industrial sites illustrate the installation and operation of the fluidized bed and emphasize the ability to use the fluidized bed singularly or as an integral component of a treatment system capable of achieving treatment levels that allow surface discharge and reinjection. Attention is focused on BTEX (benzene, toluene, ethylbenzene, and xylenes)

  11. Technical considerations of on-site spent fuel storage

    As more time is spent on power generation, more nuclear plants will face the dilemma of finding spent fuel storage space. Presently, there are numerous options available to nuclear power plant owners. The most common options are wet storage, such as fuel consolidation in a spent fuel pool, and dry storage, such as vault and cask storage. Choosing the most suitable option for a particular power plant is not an easy task. The primary selection considerations are licensing and financial. To achieve the optimum licensing and financial goals, a thorough technical evaluation of plant design, environmental requirements, and safety significance are essential. The purpose of this presentation is to benefit other nuclear plant owners by sharing the knowledge gained in selecting and evaluating the on-site spent fuel storage plan implemented at Power Company's Palisades Plant

  12. CASDAC system: On-Site Multiplexer user's guide

    The CASDAC (Containment and Surveillance Data Authenticated Communication) system has been developed by JAERI for nuclear safeguards and physical protection of nuclear material. This system is a remote monitoring system for continual verification of security and safeguards status of nuclear material. The CASDAC system consists of two subsystems, one of them is a Grand Command Center (GCC) subsystem and the other is a facility subsystem. This report describes the outline and usage of the On-Site Multiplexer (OSM), which controls all other equipments in a facility subsystem and communicates with the GCC. This work has been carried out in the framework of Japan Support Programme for Agency Safeguards (JASPAS) as a project, JA-1. (author)

  13. Greenhouse gas emissions from on-site wastewater treatment systems

    Somlai-Haase, Celia; Knappe, Jan; Gill, Laurence

    2016-04-01

    Nearly one third of the Irish population relies on decentralized domestic wastewater treatment systems which involve the discharge of effluent into the soil via a percolation area (drain field). In such systems, wastewater from single households is initially treated on-site either by a septic tank and an additional packaged secondary treatment unit, in which the influent organic matter is converted into carbon dioxide (CO2) and methane (CH4) by microbial mediated processes. The effluent from the tanks is released into the soil for further treatment in the unsaturated zone where additional CO2 and CH4 are emitted to the atmosphere as well as nitrous oxide (N2O) from the partial denitrification of nitrate. Hence, considering the large number of on-site systems in Ireland and internationally, these are potential significant sources of greenhouse gas (GHG) emissions, and yet have received almost no direct field measurement. Here we present the first attempt to quantify and qualify the production and emissions of GHGs from a septic tank system serving a single house in the County Westmeath, Ireland. We have sampled the water for dissolved CO2, CH4 and N2O and measured the gas flux from the water surface in the septic tank. We have also carried out long-term flux measurements of CO2 from the drain field, using an automated soil gas flux system (LI-8100A, Li-Cor®) covering a whole year semi-continuously. This has enabled the CO2 emissions from the unsaturated zone to be correlated against different meteorological parameters over an annual cycle. In addition, we have integrated an ultraportable GHG analyser (UGGA, Los Gatos Research Inc.) into the automated soil gas flux system to measure CH4 flux. Further, manual sampling has also provided a better understanding of N2O emissions from the septic tank system.

  14. On-site intermediate storage facilities in Germany

    Full text: In 2002 German utilities and the federal government agreed on the future of nuclear power in Germany. Part of this 'consensus' are site specific phase out periods, termination of reprocessing and the erection of on-site storage facilities. Shipment of spent fuel to reprocessing plants is only allowed until 2005, shipments to the German joint storage facilities of Ahaus and Gorleben have to be minimized. Each nuclear power plant has to create its own spent fuel storage with appropriate capacity. The necessary storage capacity is about 20 to 40 t/a and per plant, corresponding to 40 to 80 PWR- and 140 to 180 BWR-fuel bundles, depending on plant power and discharge burnup. Wet storage capacity inside the reactor building of most German NPPs was increased (compact storage) when shipments of spent fuel were ceased, following discussions about surface contaminations on casks. To avoid shut-down some plants even built short term storage facilities. Whereas short-term storage is to guarantee undisturbed operation of plants on an intermediate time scale, long term storage - until final nuclear waste disposal after 2030 is available - is also driven by economical considerations. Of the existing storage techniques wet and dry storage were analyzed with respect to costs and time for design, licensing and construction. Both techniques fulfill the safety requirements, but wet storage turns out to be more costly because of the necessary heat removing devices and operating expense. Total costs for construction, operation and decommissioning of a wet storage facility - as it was built in Obrigheim in 1998 on a smaller scale - rank from 80 to 250 million Euro, 1,4 million Euro annually and 45 million Euro for decommissioning (price index of 2003), respectively. Compared to that, dry storage needs about 26 million Euro for construction, annually 0,3 million Euro plus 2 - 3 casks (e.g. of the CASTOR type) with around 1,2 million Euro per flask and about 12 million Euro for

  15. On-site digital heritage inventory development at Bat, Oman

    Kondo, Y.; Miki, T.; Kuronuma, T.; Oguchi, T.

    2015-08-01

    This paper reports on the on-site development of a local-scale digital heritage inventory (DHI) of the Bronze Age site at Bat in the interior of Oman. The goal of this inventory project was to share geospatial and archaeological information of tombs and other built structures with researchers and government agents to conduct cultural heritage management, scientific research, outreach, and education. To this end, the Bat Digital Heritage Inventory (BatDHI) was compiled at the local office by incorporating previous survey records, which were concurrently crosschecked and updated by ground-truth surveys. The current version of the BatDHI was implemented using a combination of a network-access-ready database application, open source geographical information system, and web-based map engine. This system assisted both fieldwork and management works including decision making and planning. This inventory project exemplified a transdisciplinary research, in which researchers and societal stakeholders collaborated for co-design of research agendas, co-production of knowledge, and co-dissemination of outcomes.

  16. On site inspection for nuclear test ban verirication

    P. D. Marschall

    1994-06-01

    Full Text Available The problem of verifying compliance with a nuclear test ban treaty is mainly a technical one. However the problem of detecting, locating and identifying nuclear explosions has, since the late 1950s, been intimately involved with the political problems associated with negotiating a treaty. In fact there are few other areas in which policy, diplomacy and science have been so interwoven. This paper attempts to illustrate how technology can. be applied to solve some of the political problems which arise when considering the role of an On Site Inspection (OSI to determine whether or not a nuclear explosion, in violation of a treaty, has occurred or not. It is hoped that the reader, with a scientific background, but with little or no experience of treaty negotiations, will gain an. insight as to how technical matters can interact with political requirements. The demands made on scientists to provide technical support for negotiating and rnonitoring compliance of a treaty have increased significanfly over the last 40 years. This is a period in which a number of major treaties have contained a significant technical component e.g. the Limited Test Ban Treaty (Threshold Treaty and the Chemical Weapon Convention. This paper gives an indication of some of the political decisions which will have to be made and suggests some of the technical methods which are of value in the identification of a clandestine nuclear explosion.

  17. On-site attractive multiorbital Hamiltonian for d -wave superconductors

    Bishop, Christopher B.; Liu, Guangkun; Dagotto, Elbio; Moreo, Adriana

    2016-06-01

    We introduce a two-orbital Hamiltonian on a square lattice that contains on-site attractive interactions involving the two eg orbitals. Via a canonical mean-field procedure similar to the one applied to the well-known negative-U Hubbard model, it is shown that the model develops d -wave (B1 g) superconductivity with nodes along the diagonal directions of the square Brillouin zone. This result is also supported by exact diagonalization of the model in a small cluster. The expectation is that this relatively simple attractive model could be used to address the properties of multiorbital d -wave superconductors in the same manner that the negative-U Hubbard model is widely applied to the study of the properties of s -wave single-orbital superconductors. In particular, we show that by splitting the eg orbitals and working at three-quarters filling, such that the x2-y2 orbital dominates at the Fermi level but the 3 z2-r2 orbital contribution is nonzero, the d -wave pairing state found here phenomenologically reproduces several properties of the superconducting state of the high Tc cuprates.

  18. 13 CFR 120.1050 - On-site reviews and examinations.

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false On-site reviews and examinations. 120.1050 Section 120.1050 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Risk-Based Lender Oversight Supervision § 120.1050 On-site reviews and examinations. (a) On-site reviews. SBA may conduct on-site reviews of the...

  19. 78 FR 54487 - Abbott Laboratories; Diagnostic-Hematology; Including On-Site Leased Workers From Manpower...

    2013-09-04

    ... Employment and Training Administration Abbott Laboratories; Diagnostic--Hematology; Including On-Site Leased... on-site at the Santa Clara, California location of Abbott Laboratories, Diagnostic--Hematology... International, reporting to Abbott Laboratories, Diagnostic--Hematology division, including on-site...

  20. 13 CFR 120.1051 - Frequency of on-site reviews and examinations.

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false Frequency of on-site reviews and examinations. 120.1051 Section 120.1051 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Risk-Based Lender Oversight Supervision § 120.1051 Frequency of on-site reviews and examinations. SBA may conduct on-site reviews...

  1. International Symposium on Site Characterization for CO2Geological Storage

    Tsang, Chin-Fu

    2006-02-23

    Several technological options have been proposed to stabilize atmospheric concentrations of CO{sub 2}. One proposed remedy is to separate and capture CO{sub 2} from fossil-fuel power plants and other stationary industrial sources and to inject the CO{sub 2} into deep subsurface formations for long-term storage and sequestration. Characterization of geologic formations for sequestration of large quantities of CO{sub 2} needs to be carefully considered to ensure that sites are suitable for long-term storage and that there will be no adverse impacts to human health or the environment. The Intergovernmental Panel on Climate Change (IPCC) Special Report on Carbon Dioxide Capture and Storage (Final Draft, October 2005) states that ''Site characterization, selection and performance prediction are crucial for successful geological storage. Before selecting a site, the geological setting must be characterized to determine if the overlying cap rock will provide an effective seal, if there is a sufficiently voluminous and permeable storage formation, and whether any abandoned or active wells will compromise the integrity of the seal. Moreover, the availability of good site characterization data is critical for the reliability of models''. This International Symposium on Site Characterization for CO{sub 2} Geological Storage (CO2SC) addresses the particular issue of site characterization and site selection related to the geologic storage of carbon dioxide. Presentations and discussions cover the various aspects associated with characterization and selection of potential CO{sub 2} storage sites, with emphasis on advances in process understanding, development of measurement methods, identification of key site features and parameters, site characterization strategies, and case studies.

  2. Global Scale Methane Emissions from On-Site Wastewater Management

    Reid, M. C.; Guan, K.; Mauzerall, D. L.

    2013-12-01

    Pit latrines and other on-site sanitation methods are important forms of wastewater management at the global scale, providing hygienic and low-cost sanitation for more than 1.7 billion people in developing and middle-income regions. Latrines have also been identified as major sources of the greenhouse gas methane (CH4) from the anaerobic decomposition of organic waste in pits. Understanding the greenhouse gas footprint of different wastewater systems is essential for sustainable water resource development and management. Despite this importance, CH4 emissions from decentralized wastewater treatment have received little attention in the scientific literature, and the rough calculations underlying government inventories and integrated assessment models do not accurately capture variations in emissions within and between countries. In this study, we improve upon earlier efforts and develop the first spatially explicit approach to quantifying latrine CH4 emissions, combining a high-resolution geospatial analysis of population, urbanization, and water table (as an indicator of anaerobic decomposition pathways) with CH4 emissions factors from the 2006 IPCC Guidelines for National Greenhouse Gas Inventories. Country-level health and sanitation surveys were used to determine latrine utilization in 2000 and predict usage in 2015. 18 representative countries in Asia, Africa, and Latin America were selected for this analysis to illustrate regional variations in CH4 emissions and to include the greatest emitting nations. Our analysis confirms that pit latrines are a globally significant anthropogenic CH4 source, emitting 4.7 Tg CH4 yr-1 in the countries considered here. This total is projected to decrease ~25% by 2015, however, driven largely by rapid urbanization in China and decreased reliance on latrines in favor of flush toilets. India has the greatest potential for large growth in emissions in the post-2015 period, since public health campaigns to end open defecation

  3. REPORT OF ON-SITE INSPECTION WORKSHOP-16

    Sweeney, J J

    2009-07-07

    The central issue addressed by this workshop was the task of making the on-site inspection (OSI) part of the Comprehensive Nuclear-Test-Ban Treaty verification system operationally ready at entry into force of the Treaty. It is recognized, and this was emphasized by the 2008 OSI Integrated Field Exercise (IFE), that it is not possible to develop every part of the OSI regime simultaneously. Therefore, it is necessary to prioritize the approach to OSI readiness. The reviews of the IFE have pointed to many elements of OSI readiness that still need development. The objective of this workshop was to provide priorities for the path forward for Working Group B to consider. Several critical areas have been identified that are related to the development of OSI readiness: (1) Technology development: Priorities are radionuclide and noble gas sampling and analysis, visual observation, multispectral/infrared imaging methods, active seismic methods and the recognition of the importance of signatures. (2) Organizational development: Priorities are health and safety, the Operations Support Centre, the Equipment Storage and Maintenance Facility, information technology data flow and communications. (3) Resources: The expertise to develop key parts of the OSI regime is not available within the current OSI Division staff. To develop these aspects of the regime will require more staff or supplements to the staff with cost-free experts or other means. Aspects of the system that could benefit from more staff include radionuclide and noble gas detection methods, data flow and communications, visual observation, multispectral/infrared methods and health and safety. As the path forward, participants of this workshop recognized a need to optimize the development of OSI priorities. The outcome of this workshop is to suggest for consideration an operational approach to OSI readiness that utilizes results of an evaluation of the relative effectiveness of OSI elements versus their relative

  4. Distribution of mental health professionals working on site in English and Welsh general practices.

    Kendrick, T.; Sibbald, B; Addington-Hall, J.; Brenneman, D; Freeling, P.

    1993-01-01

    OBJECTIVE--To describe the nature and distribution of mental health professionals working on site in general practices. DESIGN--Postal questionnaire and telephone interview survey. SETTING--English and Welsh general practices. SUBJECTS--1880 general practitioners, of whom 1542 (82%) responded. MAIN OUTCOME MEASURES--Prevalence, types, and distribution of mental health professionals working on site among general practices. Factors predicting the presence of mental health professionals on site....

  5. On-site or off-site treatment of medical waste: a challenge

    Taghipour, Hassan; Mohammadyarei, Taher; Asghari Jafarabadi, Mohamad; Asl Hashemi, Ahmad

    2014-01-01

    Treating hazardous-infectious medical waste can be carried out on-site or off-site of health-care establishments. Nevertheless, the selection between on-site and off-site locations for treating medical waste sometimes is a controversial subject. Currently in Iran, due to policies of Health Ministry, the hospitals have selected on-site-treating method as the preferred treatment. The objectives of this study were to assess the current condition of on-site medical waste treatment facilities, com...

  6. 75 FR 11922 - Apria Healthcare, Including On-Site Leased Workers From Corestaff, Ultimate Staffing (Roth...

    2010-03-12

    ... Employment and Training Administration Apria Healthcare, Including On-Site Leased Workers From Corestaff... Healthcare, including on-site leased workers from Corestaff, Cromwell, Connecticut. The notice was published in the Federal Register on January 25, 2010 (75 FR 3938). At the request of the State agency,...

  7. 76 FR 13663 - Celestica, Including On-Site Leased Workers From Adecco, Aerotek, Purchasing Professionals...

    2011-03-14

    ... 3, 2009, applicable to workers of Celestica, including on-site leased workers from Adecco, Aerotek and Purchasing Professionals. The notice was published in the Federal Register on March 3, 2009 (74 FR... Employment and Training Administration Celestica, Including On-Site Leased Workers From Adecco,...

  8. 75 FR 69469 - LSI Corporation, 1110 American Parkway, Including On-Site Leased Workers From Spinnaker...

    2010-11-12

    ... From the Federal Register Online via the Government Publishing Office DEPARTMENT OF LABOR Employment and Training Administration LSI Corporation, 1110 American Parkway, Including On-Site Leased Workers From Spinnaker, Allentown, PA; LSI Corporation, 555 Union Boulevard, Including On-Site Leased Workers From Spinnaker, Allentown, PA;...

  9. 7 CFR 3560.353 - Scheduling of on-site monitoring reviews.

    2010-01-01

    ... 7 Agriculture 15 2010-01-01 2010-01-01 false Scheduling of on-site monitoring reviews. 3560.353 Section 3560.353 Agriculture Regulations of the Department of Agriculture (Continued) RURAL HOUSING....353 Scheduling of on-site monitoring reviews. Generally, the Agency will provide the borrower...

  10. 78 FR 48468 - Delphi Corporation, Electronics and Safety Division, Including On-Site Leased Workers From...

    2013-08-08

    ... determination was published in the Federal Register on June 10, 2013 (Volume 78 FR Pages 34672-34674). At the... Employment and Training Administration Delphi Corporation, Electronics and Safety Division, Including On-Site... to workers of Delphi Corporation, Electronics and Safety Division, including on-site leased...

  11. 75 FR 28295 - Cummins Filtration, Including On-Site Leased Workers From Manpower and Spherion Staffing...

    2010-05-20

    ... workers of Cummins Filtration, including on-site leased workers from Manpower, Lake Mills, Iowa. The notice was published in the Federal Register on December 11, 2009 (74 FR 65798). At the request of the... Employment and Training Administration Cummins Filtration, Including On-Site Leased Workers From Manpower...

  12. On-Site Detection as a Countermeasure to Chemical Warfare/Terrorism.

    Seto, Y

    2014-01-01

    On-site monitoring and detection are necessary in the crisis and consequence management of wars and terrorism involving chemical warfare agents (CWAs) such as sarin. The analytical performance required for on-site detection is mainly determined by the fatal vapor concentration and volatility of the CWAs involved. The analytical performance for presently available on-site technologies and commercially available on-site equipment for detecting CWAs interpreted and compared in this review include: classical manual methods, photometric methods, ion mobile spectrometry, vibrational spectrometry, gas chromatography, mass spectrometry, sensors, and other methods. Some of the data evaluated were obtained from our experiments using authentic CWAs. We concluded that (a) no technologies perfectly fulfill all of the on-site detection requirements and (b) adequate on-site detection requires (i) a combination of the monitoring-tape method and ion-mobility spectrometry for point detection and (ii) a combination of the monitoring-tape method, atmospheric pressure chemical ionization mass spectrometry with counterflow introduction, and gas chromatography with a trap and special detectors for continuous monitoring. The basic properties of CWAs, the concept of on-site detection, and the sarin gas attacks in Japan as well as the forensic investigations thereof, are also explicated in this article. PMID:26226969

  13. Development of the on-site power supply in German nuclear power plants

    The design of the on-site power supply is different in German Nuclear Power Plants, depending on age and size of the plant. The cause for this is the evolution of the safety requirements. The general development of the design of safety Systems, which resulted in a strict separation of redundant trains is also reflected in the design of the emergency power system and even the complete on-site power supply System. This will be demonstrated by different examples. The advantages of this design with respect to the availability of on-site power will be explained and verified by means of operating experience. (author)

  14. A sensitive rapid on-site immunoassay for heavy metal contamination

    Blake, R.; Blake, D.; Flowers, G.

    1996-05-02

    This project concerns the development of immunoassays for heavy metals that will permit the rapid on-site analysis of specific heavy metals, including lead and chromium in water and soil samples. 2 refs.

  15. 77 FR 4368 - Abbott Laboratories, Diagnostics Division, Including On-Site Leased Workers From Manpower...

    2012-01-27

    ... Employment and Training Administration Abbott Laboratories, Diagnostics Division, Including On-Site Leased... for Worker Adjustment Assistance on February 24, 2011, applicable to workers of Abbott Laboratories... location of Abbott Laboratories, Diagnostics Division. The Department has determined that these...

  16. On-site toxicity of irrigation drainwater from Stillwater National Wildlife Refuge to aquatic organisms

    US Fish and Wildlife Service, Department of the Interior — The toxicity of water from seven locations in the Stillwater Wildlife Management Area was evaluated in a series of on-site tests conducted over a 10 day period with...

  17. 78 FR 69878 - First Advantage Corporation, Including On-Site Leased Workers From Tapfin, Staffworks, Aerotek...

    2013-11-21

    ... Employment and Training Administration First Advantage Corporation, Including On-Site Leased Workers From... Staffing, St. Petersburg, Florida; First Advantage Corporation, Charlotte, North Carolina, First Advantage Corporation, Bolingbrook, Illinois; First Advantage Corporation, Dallas, Texas; First Advantage...

  18. Postulated accident scenarios for the on-site transport of spent nuclear fuel

    Once a spent fuel container is loaded with spent fuel it typically travels on-site to a processing building for permanent lid attachment. During on-site transport a lid clamp is utilized to ensure the container lid remains in place. The safe on-site transport of spent nuclear fuel must rely on the structural integrity of the transport container and system of transport. Regard for on-site traffic and safe, efficient travel routes are important and manageable with well thought-out planning. Non-manageable incidences, such as flying debris from tornado force winds or postulated blasts in proximity to the transport container, that may result in high velocity impact and shock loading on the transport system must be considered. This paper consists of simulations that consider these types of postulated accident scenarios using detailed nonlinear finite element techniques

  19. Bed filters for phosphorus removal in on-site wastewater treatment : Removal mechanisms and sustainability

    Eveborn, David

    2010-01-01

    For many surface waters, phosphorus (P) leaching is a serious problem that should be minimized to prevent eutrophication. In Sweden there is a demand for physical and technical development of high-performance P removal techniques to reduce phosphorus leaching from on-site wastewater treatment systems to the Baltic Sea. However, although these systems are designed to reduce eutrophication there are also other environmental impacts to be considered when implementing them in on-site systems; ene...

  20. New Technological Charts for Concreting Operations on Site for Civil Constructions

    René Antonio Puig Martínez; Juan José Howland Albear

    2014-01-01

    The on site concreting of constructions, require some regulations to guide the construction companiesto execute the concreting operations according to the status and potential of existing technologies.In Cuba were used for a long time many regulations and construction technical standards issued bythe Ministry of Construction and relating companies, and was published in 1990 the only one versionof Technological Charts for concreting operations on site, about the existing constructions in Cuba,...

  1. Explanation of procedure on site medical emergency response for nuclear accident

    National occupational health standard-Procedure on Site Medical Emergency Response for Nuclear Accident has been approved and issued by the Ministry of Health. This standard is formulated according to the Emergency Response Law of the People's Republic of China, Law of the People 's Republic of China on Prevention and Control of Occupational Diseases, Regulations on Emergency Measures for Nuclear Accidents at Nuclear Power Plants, and Health Emergency Plans for Nuclear and Radiological Accidents of Ministry of Health, supporting the use of On-site Medical Emergency Planning and Preparedness for Nuclear Accidents and Off-site Medical Emergency Planning and Preparedness for Nuclear Accidents. Nuclear accident on-site medical response procedure is a part of the on-site emergency plan. The standard specifies the basic content and requirements of the nuclear accident on-site medical emergency response procedures of nuclear facilities operating units to guide and regulate the work of nuclear accident on-site medical emergency response of nuclear facilities operating units. The criteria-related contents were interpreted in this article. (authors)

  2. Value of biomedical scientists providing on-site specimen adequacy assessment for fine-needle aspirations.

    Narine, N; Rana, D N; Perera, D M; Irshad, A

    2012-01-01

    Fine-needle aspiration (FNA) is accepted as a first-line investigation in patients with superficial or deep-seated mass lesions. One of the fundamental principles of successful aspiration is harvesting sufficient numbers of cells that are representative of the lesion being investigated. Central Manchester University Hospitals NHS Foundation Trust provides FNA services to Christie Hospital, including non-attended and biomedical scientist-attended aspirations, some of which are assessed on-site for specimen adequacy. This study audits the FNA coverage provided to Christie Hospital by exploring the contribution of biomedical scientist on-site specimen adequacy assessment to successful aspirations and identifies potential areas for service improvement such that unsatisfactory sampling is reduced. Satisfactory sampling rates varied between biomedical scientist-attended (79%) and non-attended (70%) procedures. Within the former group, 100% satisfactory sampling was achieved with on-site assessment, falling to 77% without on-site assessment. The highest unsatisfactory sampling rate was identified at 33% for thyroid aspirations in endocrinology, while rates elsewhere varied between 21% and 23%. This audit demonstrated the value of on-site specimen adequacy assessment as the ultimate goal of any FNA is to negate the need for more invasive procedures. In terms of flexibility and economic value, having adequately trained biomedical scientists to perform on-site assessment is quite feasible. Extending this biomedical scientist-led service to other departments would reduce unsatisfactory sample rates and the requirement for more invasive procedures. PMID:23057157

  3. Assessment of On-Site Power Opportunities in the Industrial Sector

    Bryson, T.

    2001-10-08

    The purpose of this report is to identify the potential for on-site power generation in the U.S. industrial sector with emphasis on nine industrial groups called the ''Industries of the Future'' (IOFs) by the U.S. Department of Energy (DOE). Through its Office of Industrial Technologies (OIT), the DOE has teamed with the IOFs to develop collaborative strategies for improving productivity, global competitiveness, energy usage and environmental performance. Total purchases for electricity and steam for the IOFs are in excess of $27 billion annually. Energy-related costs are very significant for these industries. The nine industrial groups are (1) Agriculture (SIC 1); (2) Forest products; (3) Lumber and wood products (SIC 24); (4) Paper and allied products (SIC 26); (5) Mining (SIC 11, 12, 14); (6) Glass (SIC 32); (7) Petroleum (SIC 29); (8) Chemicals (SIC 28); and (9) Metals (SIC 33): Steel, Aluminum, and Metal casting. Although not currently part of the IOF program, the food industry is included in this report because of its close relationship to the agricultural industry and its success with on-site power generation. On-site generation provides an alternative means to reduce energy costs, comply with environmental regulations, and ensure a reliable power supply. On-site generation can ease congestion in the local utility's electric grid. Electric market restructuring is exacerbating the price premium for peak electricity use and for reliability, creating considerable market interest in on-site generation.

  4. Assessment of On-Site Power Opportunities in the Industrial Sector; TOPICAL

    The purpose of this report is to identify the potential for on-site power generation in the U.S. industrial sector with emphasis on nine industrial groups called the ''Industries of the Future'' (IOFs) by the U.S. Department of Energy (DOE). Through its Office of Industrial Technologies (OIT), the DOE has teamed with the IOFs to develop collaborative strategies for improving productivity, global competitiveness, energy usage and environmental performance. Total purchases for electricity and steam for the IOFs are in excess of$27 billion annually. Energy-related costs are very significant for these industries. The nine industrial groups are: (1) Agriculture (SIC 1); (2) Forest products; (3) Lumber and wood products (SIC 24); (4) Paper and allied products (SIC 26); (5) Mining (SIC 11, 12, 14); (6) Glass (SIC 32); (7) Petroleum (SIC 29); (8) Chemicals (SIC 28); and (9) Metals (SIC 33)-Steel, Aluminum, Metal casting. Although not currently part of the IOF program, the food industry is included in this report because of its close relationship to the agricultural industry and its success with on-site power generation. On-site generation provides an alternative means to reduce energy costs, comply with environmental regulations, and ensure a reliable power supply. On-site generation can ease congestion in the local utility's electric grid. Electric market restructuring is exacerbating the price premium for peak electricity use and for reliability, creating considerable market interest in on-site generation

  5. 75 FR 5147 - Acushnet Company a Subsidiary of Fortune Brands Including On-Site Leased Workers From Olsten...

    2010-02-01

    ... Employment and Training Administration Acushnet Company a Subsidiary of Fortune Brands Including On-Site... Brands Including On-Site Leased Workers From Olsten Staffing Services New Bedford, MA; Acushnet Company a Subsidiary of Fortune Brands Including On-Site Leased Workers From Olsten Staffing Services Dartmouth,...

  6. On-Site Inspection RadioIsotopic Spectroscopy (Osiris) System Development

    Caffrey, Gus J. [Idaho National Laboratory, Idaho Falls, ID (United States); Egger, Ann E. [Idaho National Laboratory, Idaho Falls, ID (United States); Krebs, Kenneth M. [Idaho National Laboratory, Idaho Falls, ID (United States); Milbrath, B. D. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Jordan, D. V. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Warren, G. A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Wilmer, N. G. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)

    2015-09-01

    We have designed and tested hardware and software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy—Osiris—software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,132I. A set of over 100 fission-product spectra was employed for Osiris testing. These spectra were measured, where possible, or generated by modeling. The synthetic test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, Osiris correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.The Osiris gamma-ray spectrometer is a mechanically-cooled, battery-powered ORTEC Transpec-100, chosen to avoid the need for liquid nitrogen during on-site inspections. The spectrometer was used successfully during the recent 2014 CTBT Integrated Field Exercise in Jordan. The spectrometer is controlled and the spectral data analyzed by a Panasonic Toughbook notebook computer. To date, software development has been the main focus of the Osiris project. In FY2016-17, we plan to modify the Osiris hardware, integrate the Osiris software and hardware, and conduct rigorous field tests to ensure that the Osiris system will function correctly during CTBT on-site inspections. The planned development will raise Osiris to technology readiness level TRL-8; transfer the Osiris technology to a commercial manufacturer, and demonstrate Osiris to potential CTBT on-site inspectors.

  7. On-Site Inspection RadioIsotopic Spectroscopy (Osiris) System Development

    We have designed and tested hardware and software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy-Osiris-software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,132I. A set of over 100 fission-product spectra was employed for Osiris testing. These spectra were measured, where possible, or generated by modeling. The synthetic test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, Osiris correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.The Osiris gamma-ray spectrometer is a mechanically-cooled, battery-powered ORTEC Transpec-100, chosen to avoid the need for liquid nitrogen during on-site inspections. The spectrometer was used successfully during the recent 2014 CTBT Integrated Field Exercise in Jordan. The spectrometer is controlled and the spectral data analyzed by a Panasonic Toughbook notebook computer. To date, software development has been the main focus of the Osiris project. In FY2016-17, we plan to modify the Osiris hardware, integrate the Osiris software and hardware, and conduct rigorous field tests to ensure that the Osiris system will function correctly during CTBT on-site inspections. The planned development will raise Osiris to technology readiness level TRL-8; transfer the Osiris technology to a commercial manufacturer, and demonstrate Osiris to potential CTBT on-site inspectors.

  8. Analytical evaluation of a rapid on-site oral fluid drug test

    Goessaert, An-Sofie; Pil, Kristof; Veramme, Jolien; Verstraete, Alain

    2010-01-01

    There is a need for a reliable rapid on-site oral fluid test that can be used in police controls to detect impaired drivers. We evaluated the Varian OralabA (R) 6 and collected two oral fluid samples from 250 subjects, one with the Varian OralabA (R) 6 and one with the StatSure (TM) SalivaaEuro cent Sampler (TM). The OralabA (R) 6 can detect six drug types: amphetamines, methamphetamine, cocaine, opiates, delta9-tetrahydrocannabinol (THC), and phencyclidine (PCP). On-site results were obtaine...

  9. On Site Raman Analysis of the earliest known Meissen Porcelain and Stoneware

    Colomban, Philippe; Milande, Véronique

    2006-01-01

    On Site Raman analyses were performed at the Musée national de Céramique, Sèvres, France, on selected rare items of the earliest known European hard-paste porcelains and stonewares, produced from ~1710 to ~1750 in the Meissen workshop (Saxony) founded by J.F. Böttger and E.W. von Tschirnhaus. Characteristic on-site Raman signatures have been obtained for white Sake bottles from ~1715, a green bowl, depicting a purple landscape and dated 27th August 1726, a middle of the 18th century produced ...

  10. 78 FR 12358 - UBS Financial Services, Inc., Wealth Management Americas Operations, Including On-Site Leased...

    2013-02-22

    ... Employment and Training Administration UBS Financial Services, Inc., Wealth Management Americas Operations..., applicable to workers of UBS Financial Services, Inc., Wealth Management Americas Operations (UBS), Weehawken... Department's certification is to include all leased workers on-site at UBS Financial Services, Inc.,...

  11. Rapid on-site evaluation of axillary fine-needle aspiration cytology in breast cancer.

    O'Leary, D P

    2012-06-01

    Axillary ultrasonography (AUS) and fine-needle aspiration cytology (FNAC) can establish axillary lymph node status before surgery, although this technique is hampered by poor adequacy rates. To achieve consistently high rates of FNAC adequacy, rapid on-site evaluation (ROSE) of FNAC samples was introduced.

  12. On-site and off-site forensic analysis capabilities for proliferation and terrorism prevention

    Full text: We will present current on-site technologies that can be utilized for the screening of explosives, chemical agents, and environmental contaminants. These techniques must have the capability to detect various hazardous materials at very low levels, since they pose a major challenge for first responders. Specifically, the technology must detect concealed explosives or chemical agents on-site rapidly. Lawrence Livermore National Laboratory (LLNL) is currently developing several different high explosive screening and detection technologies for field use. Two technologies that have demonstrated an ability to screen for explosives at low levels are colorimetric spot tests and thin layer chromatography (TLC). Another technology that has demonstrated usefulness for the on-site analysis of unknowns is portable gas chromatography-mass spectrometry (GC-MS) with solid phase micro-extraction (SPME) sampling. Several examples utilizing these technologies and their usefulness will be presented. In addition to developing on-site screening methods, LLNL is an Organization for the Prohibition of Chemical Weapons (OPCW) designated laboratory and is certified to accept CW suspect samples. Currently, LLNL is expanding its ISO-17025 certification to include nuclear forensics and explosives. These off-site forensic analysis capabilities and certified procedures will support the needs for homeland security. We will highlight some of the ISO-17025 requirements to accredit procedures, handle samples, and reports. Work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under contract W-7405-ENG-48

  13. ON-SITE GC/MS ANALYSIS OF CHAPMAN GASIFICATION SEPARATOR LIQUOR

    The report gives results of a characterization of a wastewater stream from a coal gasification plant, using on-site extraction and GC/MS analysis. Extractable material in the wastewater was primarily phenols and alkylphenols, accounting for about 99% of the total mass identified....

  14. On-Site Renewable Energy and Green Buildings: A System-Level Analysis.

    Al-Ghamdi, Sami G; Bilec, Melissa M

    2016-05-01

    Adopting a green building rating system (GBRSs) that strongly considers use of renewable energy can have important environmental consequences, particularly in developing countries. In this paper, we studied on-site renewable energy and GBRSs at the system level to explore potential benefits and challenges. While we have focused on GBRSs, the findings can offer additional insight for renewable incentives across sectors. An energy model was built for 25 sites to compute the potential solar and wind power production on-site and available within the building footprint and regional climate. A life-cycle approach and cost analysis were then completed to analyze the environmental and economic impacts. Environmental impacts of renewable energy varied dramatically between sites, in some cases, the environmental benefits were limited despite the significant economic burden of those renewable systems on-site and vice versa. Our recommendation for GBRSs, and broader policies and regulations, is to require buildings with higher environmental impacts to achieve higher levels of energy performance and on-site renewable energy utilization, instead of fixed percentages. PMID:27031788

  15. On-site denitrification beds could reduce indirect greenhouse gas emissions from agricultural drainage waters

    Nitrate (NO3-) laden agricultural drainage waters are non-point sources of indirect nitrous oxide (N2O) emissions, which represent a significant fraction of total N2O emissions in the USA. On-site denitrification beds filled with woodchips were used to reduce NO3- under carbon rich anaerobic conditi...

  16. 76 FR 81986 - Honeywell International, Inc., Automation and Control Solutions Division, Including On-Site...

    2011-12-29

    ..., 2010 (75 FR 49531). The notice was amended on December 7, 2010 to include several on-site leased worker firms. The amended notice was published in the Federal Register on December 13, 2010 (75 FR 77664-77665... Employment and Training Administration Honeywell International, Inc., Automation and Control...

  17. Artificial neural network for on-site quantitative analysis of soils using laser induced breakdown spectroscopy

    Nowadays, due to environmental concerns, fast on-site quantitative analyses of soils are required. Laser induced breakdown spectroscopy is a serious candidate to address this challenge and is especially well suited for multi-elemental analysis of heavy metals. However, saturation and matrix effects prevent from a simple treatment of the LIBS data, namely through a regular calibration curve. This paper details the limits of this approach and consequently emphasizes the advantage of using artificial neural networks well suited for non-linear and multi-variate calibration. This advanced method of data analysis is evaluated in the case of real soil samples and on-site LIBS measurements. The selection of the LIBS data as input data of the network is particularly detailed and finally, resulting errors of prediction lower than 20% for aluminum, calcium, copper and iron demonstrate the good efficiency of the artificial neural networks for on-site quantitative LIBS of soils. - Highlights: ► We perform on-site quantitative LIBS analysis of soil samples. ► We demonstrate that univariate analysis is not convenient. ► We exploit artificial neural networks for LIBS analysis. ► Spectral lines other than the ones from the analyte must be introduced

  18. On-Site Enzyme Production by Trichoderma asperellum for the Degradation of Duckweed

    Bech, Lasse; Herbst, Florian-Alexander; Grell, Morten Nedergaard;

    2015-01-01

    The on-site production of cell wall degrading enzymes is an important strategy for the development of sustainable bio-refinery processes. This study concerns the optimization of production of plant cell wall-degrading enzymes produced by Trichoderma asperellum. A comparative secretome analysis was...

  19. Decision precision or holistic heuristic?: Insights on on-site selection of student nurses and midwives.

    Macduff, Colin; Stephen, Audrey; Taylor, Ruth

    2016-01-01

    Concerns about quality of care delivery in the UK have led to more scrutiny of criteria and methods for the selection of student nurses. However few substantive research studies of on-site selection processes exist. This study elicited and interpreted perspectives on interviewing processes and related decision making involved in on-site selection of student nurses and midwives. Individual and focus group interviews were undertaken with 36 lecturers, 5 clinical staff and 72 students from seven Scottish universities. Enquiry focused primarily on interviewing of candidates on-site. Qualitative content analysis was used as a primary strategy, followed by in-depth thematic analysis. Students had very mixed experiences of interview processes. Staff typically took into account a range of candidate attributes that they valued in order to achieve holistic assessments. These included: interpersonal skills, team working, confidence, problem-solving, aptitude for caring, motivations, and commitment. Staff had mixed views of the validity and reliability of interview processes. A holistic heuristic for overall decision making predominated over belief in the precision of, and evidence base for, particular attribute measurement processes. While the development of measurement tools for particular attributes continues apace, tension between holism and precision is likely to persist within on-site selection procedures. PMID:26213147

  20. The interactive on-site inspection system: An information management system to support arms control inspections

    DeLand, S.M.; Widney, T.W.; Horak, K.E.; Caudell, R.B.; Grose, E.M.

    1996-12-01

    The increasing use of on-site inspection (OSI) to meet the nation`s obligations with recently signed treaties requires the nation to manage a variety of inspection requirements. This document describes a prototype automated system to assist in the preparation and management of these inspections.

  1. Operations manual: On Site Monitor (OSM), solar heating and cooling systems

    1977-01-01

    The on-site monitor is a portable device which, when connected to a solar system site data acquisition subsystem; allows readouts of clock and sensor data in voltage or engineering units at instrumented solar heating and cooling sites. The unit is described and procedures for its proper operation are presented.

  2. Subsystem design package for the on-site monitor at solar heating and cooling sites

    1977-01-01

    The on-site monitor is a portable device which can be easily connected to a Site Data Acquisition Subsystem to allow readouts of realtime sensor data in voltage or engineering units at instrumented solar heating and cooling sites. The design package consists of the performance specification, performance requirements cross reference, and the acceptance test procedure.

  3. Alternative Wastewater Treatment: On-Site Bio-treatment Wetlands at the Fernald Preserve Visitors Center

    This paper describes the design and operation of a constructed on-site bio-treatment wetland at the Fernald Preserve Visitors Center. The use of constructed wetlands for treatment of domestic wastewater at the Fernald Preserve contributed to the award of Leadership in Energy and Environmental Design platinum certification from the U.S. Green Building Council. (authors)

  4. Rapid on-site detection of Acidovorax citrulli by cross-priming amplification.

    Zhang, Jing; Tian, Qian; Zhu, Shui-fang; Zhao, Wen-jun; Liu, Feng-quan

    2012-08-01

    Cross-priming amplification (CPA) for Acidovorax citrulli detection was evaluated in this study. The sensitivity of CPA assay for pure bacterial culture was 3.7 × 10(3) CFU/ml. Bacteria on naturally infected watermelon seeds were detected using CPA assay, suggesting this method is suitable for A. citrulli on-site detection from watermelon seeds. PMID:22507851

  5. On-site and off-site forensic analysis capabilities for proliferation and terrorism prevention

    We present current on-site technologies that can be utilized for the screening of explosives, chemical agents, and environmental contaminants. These techniques must have the capability to detect various hazardous materials at very low levels, since they pose a major challenge for first responders. Specifically, the technology must detect concealed explosives or chemical agents on-site rapidly. Lawrence Livermore National Laboratory (LLNL) is currently developing several different high explosive screening and detection technologies for field use. Two technologies that have demonstrated an ability to screen for explosives at low levels are colorimetric spot tests and thin layer chromatography (TLC). Another technology that has demonstrated usefulness for the on-site analysis of unknowns is portable gas chromatography-mass spectrometry (GC-MS) with solid phase micro-extraction (SPME) sampling. Several examples utilizing these technologies and their usefulness will be presented. In addition to developing on-site screening methods, LLNL is an Organization for the Prohibition of Chemical Weapons (OPCW) designated laboratory and is certified to accept CW suspect samples. Currently, LLNL is expanding its ISO-17025 certification to include nuclear forensics and explosives. These off-site forensic analysis capabilities and certified procedures will support the needs for homeland security. We will highlight some of the ISO-17025 requirements to accredit procedures, handle samples, and reports. Work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under contract W-7405-ENG-48. (author)

  6. Analysis of acoustic-seismic coupling behaviour for CTBT on-site inspection performance improvement

    Liebsch, Mattes; Knoop, Jan-Frederik [Technische Univ. Dortmund (Germany)

    2013-07-01

    After teleseismic detection of a big underground explosion, during on-site inspections under the Comprehensive Nuclear Test-Ban Treaty (CTBT) weak seismic signals from aftershocks are to be detected. These, however, can be masked by soil vibrations which are caused by acoustic waves which couple to the ground. To analyse the coupling behaviour between acoustic waves and soil vibrations several experiments with different acoustic sources (helicopters, firecrackers, loudspeaker) were performed. Of special interest is the influence of surface waves, excited in a larger area around the sensor, which can superpose constructively at the position of the sensor and can increase the measured seismic signal. A better understanding of the acoustic-seismic coupling can be used to develop guidelines for seismic aftershock measurements, such as a suitable sensor setup, with the goal of reducing or even preventing disturbing signals to improve the performance of on-site inspections for the CTBT.

  7. Analysis of acoustic-seismic coupling behaviour for CTBT on-site inspection performance improvement

    After teleseismic detection of a big underground explosion, during on-site inspections under the Comprehensive Nuclear Test-Ban Treaty (CTBT) weak seismic signals from aftershocks are to be detected. These, however, can be masked by soil vibrations which are caused by acoustic waves which couple to the ground. To analyse the coupling behaviour between acoustic waves and soil vibrations several experiments with different acoustic sources (helicopters, firecrackers, loudspeaker) were performed. Of special interest is the influence of surface waves, excited in a larger area around the sensor, which can superpose constructively at the position of the sensor and can increase the measured seismic signal. A better understanding of the acoustic-seismic coupling can be used to develop guidelines for seismic aftershock measurements, such as a suitable sensor setup, with the goal of reducing or even preventing disturbing signals to improve the performance of on-site inspections for the CTBT.

  8. Field sampling and selecting on-site analytical methods for explosives in soil

    Crockett, A.B.; Craig, H.D.; Jenkins, T.F.; Sisk, W.E.

    1996-12-01

    A large number of defense-related sites are contaminated with elevated levels of secondary explosives. Levels of contamination range from barely detectable to levels above 10% that need special handling because of the detonation potential. Characterization of explosives-contaminated sites is particularly difficult because of the very heterogeneous distribution of contamination in the environment and within samples. To improve site characterization, several options exist including collecting more samples, providing on-site analytical data to help direct the investigation, compositing samples, improving homogenization of the samples, and extracting larger samples. This publication is intended to provide guidance to Remedial Project Managers regarding field sampling and on-site analytical methods for detecting and quantifying secondary explosive compounds in soils, and is not intended to include discussions of the safety issues associated with sites contaminated with explosive residues.

  9. On-site transfer system for remote handling of low-level radioactive waste

    Increased uncertainties regarding the future availability of low-level radioactive waste (LLW) disposal sites have caused many commercial nuclear power utilities to investigate and implement alternatives to radwaste storage and disposal. Nuclear Packaging, Inc., under contract to Southern California Edison has developed an on-site radioactive waste transfer system (OTS), which allows shielded handling of LLW at the San Onofre Nuclear Generating Station. The system is designed to remotely transfer multiconfigured radwaste containers into shielded storage modules, on-site radioactive waste storage facilities, or shipping casks. The OTS consists of three primary components: (a) a shielded transfer cask, (b) a transport trailer, and (c) a mobile straddle crane for remote handling and positioning of the transfer cask during container transfer operations

  10. Experience in verification regimes. United States On-Site Inspection Agency

    Experiences are described of the United States On-site Inspection Agency in verification regimes all over the world where it has been applied in the last 30 years. The challenge for the future is to extend the benefits of the applied tools to all states in all regions to enhance stability and to create conditions for peace at lower levels of armaments than currently exist. The USA need to engage states currently caught in cycles of violence and arms escalation. They must examine technologies which together with on-site aspects of verification or transparency regimes can provide a comprehensive picture at affordable costs. They foresee a growth in combined training with new states entering for the first time into regime that include arms control and transparency measure

  11. On-site approximation for spin-orbit coupling in LCAO density functional methods

    Fernandez-Seivane, Lucas; Oliveira, Miguel A; Sanvito, Stefano; Ferrer, Jaime

    2006-01-01

    We propose a computational method that simplifies drastically the inclusion of spin-orbit interaction in density functional theory implemented on localised atomic orbital basis sets. Our method is based on a well-known procedure for obtaining pseudopotentials from atomic relativistic 'ab initio' calculations and on an on-site approximation for the spin-orbit matrix elements. We have implemented the technique in the SIESTA code, and we show that it provides accurate results for the overall ban...

  12. A Review of On-Site Wastewater Treatment Systems in Western Australia from 1997 to 2011

    Maria Gunady; Natalia Shishkina; Henry Tan; Clemencia Rodriguez

    2015-01-01

    On-site wastewater treatment systems (OWTS) are widely used in Western Australia (WA) to treat and dispose of household wastewater in areas where centralized sewerage systems are unavailable. Septic tanks, aerobic treatment units (ATUs), and composting toilets with greywater systems are among the most well established and commonly used OWTS. However, there are concerns that some OWTS installed in WA are either performing below expected standards or failing. Poorly performing OWTS are often at...

  13. Devices for on-site maintenance allows an increased availability of supplies of orbital welding systems

    Until now, energy supplies of orbital welding systems had to be shipped for maintenance. As described in this article, technological advances like portable calibration units allow the owners of such systems to perform themselves maintenance operations. On-site calibration results in a reduction of costs and off-site maintenance, therefore in an increased availability. The article describes the main functions of these portable calibration units which are used to calibrate welding critical variables

  14. On-site interim storage of spent nuclear fuel: Emerging public issues

    Failure to consummate plans for a permanent repository or above- ground interim Monitored Retrievable Storage (MRS) facility for spent nuclear fuel has spurred innovative efforts to ensure at-reactor storage in an environmentally safe and secure manner. This article examines the institutional and socioeconomic impacts of Dry Cask Storage Technology (DCST)-an approach to spent fuel management that is emerging as the preferred method of on-site interim spent fuel storage by utilities that exhaust existing storage capacity

  15. Optimal selection of on-site generation with combined heat andpower applications

    Siddiqui, Afzal S.; Marnay, Chris; Bailey, Owen; HamachiLaCommare, Kristina

    2004-11-30

    While demand for electricity continues to grow, expansion of the traditional electricity supply system, or macrogrid, is constrained and is unlikely to keep pace with the growing thirst western economies have for electricity. Furthermore, no compelling case has been made that perpetual improvement in the overall power quality and reliability (PQR)delivered is technically possible or economically desirable. An alternative path to providing high PQR for sensitive loads would generate close to them in microgrids, such as the Consortium for Electricity Reliability Technology Solutions (CERTS) Microgrid. Distributed generation would alleviate the pressure for endless improvement in macrogrid PQR and might allow the establishment of a sounder economically based level of universal grid service. Energy conversion from available fuels to electricity close to loads can also provide combined heat and power (CHP) opportunities that can significantly improve the economics of small-scale on-site power generation, especially in hot climates when the waste heat serves absorption cycle cooling equipment that displaces expensive on-peak electricity. An optimization model, the Distributed Energy Resources Customer Adoption Model (DER-CAM), developed at Berkeley Lab identifies the energy bill minimizing combination of on-site generation and heat recovery equipment for sites, given their electricity and heat requirements, the tariffs they face, and a menu of available equipment. DER-CAM is used to conduct a systemic energy analysis of a southern California naval base building and demonstrates atypical current economic on-site power opportunity. Results achieve cost reductions of about 15 percent with DER, depending on the tariff.Furthermore, almost all of the energy is provided on-site, indicating that modest cost savings can be achieved when the microgrid is free to select distributed generation and heat recovery equipment in order to minimize its over all costs.

  16. Framatome recent developments and application on site in NDE of steam generator tubes

    The increasing needs concerning the follow up and expertise of PWR steam generator (SG) tubing have led Framatome to develop a quick on-site intervention mobile unit, which could implement any current technique and equipment. Besides, Framatome has developed several non destructrive examination methods to solve the specific problems encountered in service on the SG tubes: profilometry of the SG tubes by eddy current. Inside and above the tube sheet, eddy current inspection of tube sleeving by ultrasonic testing and eddy current

  17. Potential impacts of regional climate change on site productivity of Larix olgensis plantations in northeast China

    Shen C; Lei X; Liu H.; Wang L; Liang W

    2015-01-01

    Climate change is expected to substantially affect forest site productivity. However, its effects may vary depending on the climate scenario, region and tree species. We chose Larix olgensis in northeast China to investigate the responses of forest site productivity to regional climate change using a generalized additive model (GAM). Based on site index data and climate variables from 335 townships across the Jilin Province, we developed a climate-sensitive forest site index model, which acco...

  18. On-site staffing requirements for a simplified boiling water reactor (SBWR)

    In 1992 the total generating costs were estimated by EPRI for a baseload, nth-of-a-kind advanced reactor with the following cost distribution: capital cost 62%, operation and maintenance (O and M) cost 20%, fuel cost 16%, and decommissioning cost 2%. Thus the O and M cost is a significant component of the total cost of electricity, second only to the capital cost. The O and M cost in turn can be split into: cost for on-site staff, maintenance materials, supplies and expenses, off-site technical support, regulatory fees, insurance premiums and administration. The costs for on-site staff is about 30% of the total O and M cost. In 1992, the US Council for Energy Awareness (USCEA) estimated the on-site staffing for a typical 600 MWe advanced reactor to be about 330 with 25 (full time equivalent, FTE) contractors. This estimate was reevaluated by EPRI, and the staffing was modified based on a reengineering of the organizational structure that eliminated unnecessary layers of vertical management. As a result of this review, the on-site staffing was decreased to 259 with 25 (FTE) contractors, for a total of 284 people. The Dodewaard power plant (GKN) in The Netherlands is a 60 MWe facility with a natural circulating reactor. Since the 600 MWe Simplified Boiling Water Reactor (SBWR), an advanced reactor, also utilizes a natural circulating reactor with other passive safety features it was desired to extrapolate the GKN staffing to the SBWR. Also, some of the European O and M practices that utilize fewer skilled labor are reflected. This paper provides the results of the comparison between the EPRI recommendations and the staffing based on GKN experience

  19. Performance evaluation of telemetry stations based on site selection (Short Communication)

    M. Goswami; B. Sucharita; P. Arya

    2003-01-01

    In a test range, selection of sites for deployment of mobile telemetry stations plays a crucial role for acquiring and tracking any airborne vehicle under test. Efforts have been made to correlate the tracking performance of the auto track stations based on site selection for various test flights conducted from different launching pads. Some of the tracking methodologies discussed in this paper are single channel amplitude comparison monopulse (SCACMP) technique and E-SCAN technique. A...

  20. Using Automated On-Site Monitoring to Calibrate Empirical Models of Trihalomethanes Concentrations in Drinking Water

    Thomas E. Watts III; Robyn A. Snow; Brown, Aaron W.; J. C. York; Greg Fantom; Paul S. Simone Jr.; Gary L. Emmert

    2015-01-01

    An automated, on-site trihalomethanes concentration data set from a conventional water treatment plant was used to optimize powdered activated carbon and pre-chlorination doses. The trihalomethanes concentration data set was used with commonly monitored water quality parameters to improve an empirical model of trihalomethanes formation. A calibrated model was used to predict trihalomethanes concentrations the following year. The agreement between the models and measurements was evaluated. The...

  1. Recent chemical engineering requirements as the result of TMI on-site experience

    From the experiences gained from the on-site experience at TMI, it is apparent that the role of chemical engineers should increase in order for the nuclear option to proceed in a safe and efficient fashion. It is also obvious that as the results of the reports investigating the causes and effects of the accident come to light and attempts to backfit system designs to prevent a recurrence are studied, more technical demands will be placed on the profession

  2. Problems Of Senior Teacher Students In On-Site School Training

    AYDIN, Furkan; AKGÜN, Özcan Erkan

    2014-01-01

    Training qualified teachers is a very important goal to increase quality of education. Today, Educational faculties are responsible for teacher training to sustain education system. School experience and on-site teaching practice courses are key factors in teacher training to nurture students in order to know their job and get necessary knowledge and skills. These courses have very important functions in teacher training but there are some problems about them. In this study we have investigat...

  3. Shielding requirements on-site loading and acceptance testing on the Leksell gamma knife.

    Maitz, A H; Lunsford, L D; Wu, A; Lindner, G; Flickinger, J C

    1990-02-01

    On August 14, 1987, the first stereotactic radiosurgical procedure using the gamma knife was performed in North America. Located in a self-contained radiosurgical suite in the basement of Presbyterian-University Hospital in Pittsburgh, Pennsylvania. This device uses 201 highly focused beams 60Co for the single-treatment closed-skull irradiation of brain lesions localized by stereotactic techniques (radiosurgery). One hundred and fifty-two patients with intracranial arteriovenous malformations or brain tumors were treated in the first year of operation. The Presbyterian University Hospital of Pittsburgh gamma knife is the first such unit in which the 60Co sources were loaded on-site. This effort required us to solve some difficult and unusual problems encountered during site preparation, delivery, and loading of the unit in a busy hospital setting. The solutions developed enabled installation and use of the gamma knife with minimal disruption of hospital activities while maintaining acceptable levels of exposure to radiation. Environmental surveys performed during the loading of the 201 radioactive sources (total, 219 TBq) confirmed that on-site loading is possible and practical. Our experience in the design, construction, and implementation of the first North American gamma knife supports the practicality and safety of on-site loading and may be of value in the planning and development of future gamma knife installations. PMID:2406231

  4. Shielding requirements on-site loading and acceptance testing on the Leksell gamma knife

    On August 14, 1987, the first stereotactic radiosurgical procedure using the gamma knife was performed in North America. Located in a self-contained radiosurgical suite in the basement of Presbyterian-University Hospital in Pittsburgh, Pennsylvania. This device uses 201 highly focused beams 60Co for the single-treatment closed-skull irradiation of brain lesions localized by stereotactic techniques (radiosurgery). One hundred and fifty-two patients with intracranial arteriovenous malformations or brain tumors were treated in the first year of operation. The Presbyterian University Hospital of Pittsburgh gamma knife is the first such unit in which the 60Co sources were loaded on-site. This effort required us to solve some difficult and unusual problems encountered during site preparation, delivery, and loading of the unit in a busy hospital setting. The solutions developed enabled installation and use of the gamma knife with minimal disruption of hospital activities while maintaining acceptable levels of exposure to radiation. Environmental surveys performed during the loading of the 201 radioactive sources (total, 219 TBq) confirmed that on-site loading is possible and practical. Our experience in the design, construction, and implementation of the first North American gamma knife supports the practicality and safety of on-site loading and may be of value in the planning and development of future gamma knife installations

  5. Reliability of on-site greywater treatment systems in Mediterranean and arid environments - a case study.

    Alfiya, Y; Gross, A; Sklarz, M; Friedler, E

    2013-01-01

    On-site greywater (GW) treatment and reuse is gaining popularity. However, a main point of concern is that inadequate treatment of such water may lead to negative environmental and health effects. Maintenance of single-family home GW systems is usually performed by home owners with limited professional support. Therefore, unless GW systems are reliable, environmental and public health might be compromised. This study is aimed at investigating the reliability of on-site recirculated vertical flow constructed wetlands (RVFCW) in 20 single-family homes. In order to ensure reliability, the failure-tree approach was adopted during the design and construction of the systems. The performance of the systems was monitored for 1.5 years, by evaluating treated GW flow and quality, and by recording all malfunctions and maintenance work. Only 39 failures occurred during this period, of which four caused irrigation with impaired quality GW, while the rest led to no irrigation. The mean time between failures (MTBF) was 305 days; two out of the 20 systems suffered from seven malfunctions (each), while nine systems did not fail at all. Thus, it can be postulated that if on-site GW treatment systems are designed with the right controls, and if scheduled (basic and relatively infrequent) maintenance is performed, GW reuse can be safe to the environment and human health. PMID:23508166

  6. Conceptual design for an on-site spent-fuel transfer system

    Transnuclear, Inc. has developed two conceptual designs for transferring spent fuel from a nuclear plant's fuel storage pool to large storage casks by means of a small transfer cask. The transfer of spent fuel would be performed external to the nuclear plant, rather than within the plant's fuel building or transport bay. The systems can also be used to transfer fuel between storage casks and transport casks. Both systems meet the design considerations for on-site spent-fuel transfer systems outlined in EPRI Report NP-6425, ''Design Considerations for On-Site Spent-Fuel Transfer Systems.'' One of the designs involves a dry transfer into the storage cask, while the other uses a wet transfer method. Both systems have been evaluated for economic and technical feasibility, licensability and practicality. This report describes each of the conceptual designs and outlines the operating procedures for each system. In addition, a risk and accident assessment, a logistical evaluation, and an economic analysis including target cost evaluations and system cost estimates are included. This report shows that it is technically feasible and that costs are economically justifiable to perform on-site spent-fuel transfers using small transfer casks. However, the final design selection for the transfer system could depend on the individual utility's operational preferences and the unique facility features that already exist at each nuclear plant. 9 tabs

  7. New Technological Charts for Concreting Operations on Site for Civil Constructions

    René Antonio Puig Martínez

    2014-03-01

    Full Text Available The on site concreting of constructions, require some regulations to guide the construction companiesto execute the concreting operations according to the status and potential of existing technologies.In Cuba were used for a long time many regulations and construction technical standards issued bythe Ministry of Construction and relating companies, and was published in 1990 the only one versionof Technological Charts for concreting operations on site, about the existing constructions in Cuba,that are in obsolescence in this moment. During more than two decades, the country has experimentedvery rapidly develop of on site concreting technologies according with the development achieved bythe construction industry, importing or producing new efficient and productive equipments. The newtechnological charts are the result of the authors research project. They have proposed the suitableprocedures for the preparation, transportation, pouring, compaction and curing of the concrete mix incorrespondence with the country "state of the art", and the consumption normative of workers,equipments, time and costs of these activities, using the "concreting flow" as a regulator of theconcreting system.

  8. ALERTES-SC3 Early Warning System prototype for South Iberian Peninsula: on-site approach.

    Pazos, Antonio; Lopez de Mesa, Mireya; Gallego Carrasco, Javier; Martín Davila, José; Rioja del Rio, Carlos; Morgado, Arturo; Vera, Angel; Ciberia, Angel; Cabieces, Roberto; Strollo, Angelo; Hanka, Winfried; Carranza, Marta

    2016-04-01

    In recent years several Earthquake Early Warning Systems (EEWS) have been developed for different parts of the world. The area between SW Cape St. Vicente and the Strait of Gibraltar is one of the most seismically active zones in the Ibero-Maghrebian region, with predominantly moderate and superficial seismicity, but also big events with associated tsunamis are well documented in the area, like the 1755 Lisbon earthquake. In the frame of the ALERT-ES (2011-2013) and ALERTES-RIM (2014-2016) Spanish projects, the ALERTES-SC3 EEWS, regional approach, prototype has been developed at the Royal Spanish Navy Observatory (ROA) and is being tested in near real time for south Iberia. This prototype, based on the SeisComP3 software package, is largely based on algorithms derived from the analysis of the first seconds of the P wave records. Calculation of several parameters are carried out, mainly the characteristic period (τc) and the displacement peak (Pd), but also the velocity peak (Pv), the maximum period (τPmáx), among others. In order to warm the areas closest to the hypocentre, places located inside the "blind zone", a on-site EEWS has also been developed by ROA and integrated in the ALERTES-SC3 prototype. From the on-site approach, a warm level is declared from one station as a function of the estimated characteristic period (τc) and the displacement Peak (Pd), although the earthquake location and therefore the lead time available remains unknown. This on-site EEWS is being tested in several Western Mediterranean net (WM) stations as ARNO (Arenosillo, Huelva,Spain) or CHAS (Chafarinas island, North Africa, Spain). Also an on-site low cost station is being developed based in low cost accelerometers. In this work the current state of the on-site EEWS developed, its integration in the ALERTES-SC3 EEWS system and the low cost seismic stations are shown.

  9. Testing the applicability of rapid on-site enzymatic activity detection for surface water monitoring

    Stadler, Philipp; Vogl, Wolfgang; Juri, Koschelnik; Markus, Epp; Maximilian, Lackner; Markus, Oismüller; Monika, Kumpan; Peter, Strauss; Regina, Sommer; Gabriela, Ryzinska-Paier; Farnleitner Andreas, H.; Matthias, Zessner

    2015-04-01

    On-site detection of enzymatic activities has been suggested as a rapid surrogate for microbiological pollution monitoring of water resources (e.g. using glucuronidases, galactosidases, esterases). Due to the possible short measuring intervals enzymatic methods have high potential as near-real time water quality monitoring tools. This presentation describes results from a long termed field test. For twelve months, two ColiMinder devices (Vienna Water Monitoring, Austria) for on-site determination of enzymatic activity were tested for stream water monitoring at the experimental catchment HOAL (Hydrological Open Air Laboratory, Center for Water Resource Systems, Vienna University of Technology). The devices were overall able to follow and reflect the diverse hydrological and microbiological conditions of the monitored stream during the test period. Continuous data in high temporal resolution captured the course of enzymatic activity in stream water during diverse rainfall events. The method also proofed sensitive enough to determine diurnal fluctuations of enzymatic activity in stream water during dry periods. The method was able to capture a seasonal trend of enzymatic activity in stream water that matches the results gained from Colilert18 analysis for E. coli and coliform bacteria of monthly grab samples. Furthermore the comparison of ColiMinder data with measurements gained at the same test site with devices using the same method but having different construction design (BACTcontrol, microLAN) showed consistent measuring results. Comparative analysis showed significant differences between measured enzymatic activity (modified fishman units and pmol/min/100ml) and cultivation based analyses (most probable number, colony forming unit). Methods of enzymatic activity measures are capable to detect ideally the enzymatic activity caused by all active target bacteria members, including VBNC (viable but nonculturable) while cultivation based methods cannot detect VBNC

  10. 75 FR 38128 - Ceva Freight, LLC, Dell Logistics Division, Including On-Site Leased Workers From Prologistix and...

    2010-07-01

    ..., LLC, Dell Logistics Division, including on-site leased workers from Prologistix, Winston-Salem, North Carolina. The notice was published in the Federal Register on April 23, 2010 (75 FR 21357). At the request... Employment and Training Administration Ceva Freight, LLC, Dell Logistics Division, Including On-Site...

  11. 75 FR 41522 - Hewlett Packard, Technical Support Call Center, Including On-Site Leased Workers From Manpower...

    2010-07-16

    ... Employment and Training Administration Hewlett Packard, Technical Support Call Center, Including On-Site... workers of Hewlett Packard, Technical Support Call Center, including on-site leased workers from Manpower, Volt, and Adecco, Boise, Idaho. The notice was published in the Federal Register March 12, 2010 (75...

  12. 77 FR 6586 - GE Oil & Gas Operations, LLC Including On-Site Leased Workers From Adecco, Argus Technical, Inc...

    2012-02-08

    ... oil and gas industry. The notice was published in the Federal Register on October 20, 2011 (76 FR... Employment and Training Administration GE Oil & Gas Operations, LLC Including On-Site Leased Workers From... 28, 2011, applicable to workers of GE Oil & Gas Operations, LLC, including on-site leased...

  13. 75 FR 11921 - Heritage Aviation, Ltd., Including On-Site Leased Workers From Global Technical Services and...

    2010-03-12

    ... the Federal Register on February 16, 2010 (75 FR 7033). At the request of the State Agency, the... Employment and Training Administration Heritage Aviation, Ltd., Including On-Site Leased Workers From Global... workers of Heritage Aviation, including on-site leased workers from Heritage Aviation, Ltd, including...

  14. 76 FR 37154 - Covidien, Formerly Aspect Medical, R & MS Division, Including On-Site Leased Workers From Kelly...

    2011-06-24

    ... Employment and Training Administration Covidien, Formerly Aspect Medical, R & MS Division, Including On- Site..., 2011, applicable to workers of Covidien, formerly Aspect Medical, R & MS Division, including on-site...-site at the Norwood, Massachusetts location of Covidien, formerly Aspect Medical, R & MS Division....

  15. 76 FR 61740 - Geneon Entertainment (USA) Including On-Site Leased Workers From Interplace, Inc., Apple One and...

    2011-10-05

    ... production of DVD masters. The notice was published in the Federal Register on July 8, 2011 (76 FR 40401). At... Employment and Training Administration Geneon Entertainment (USA) Including On-Site Leased Workers From..., applicable to workers of Geneon Entertainment (USA), including on-site leased workers from Interplace,...

  16. 77 FR 21588 - Hart and Cooley, Inc., A Subsidiary of Tomkins, PLC Including On-Site Leased Workers from...

    2012-04-10

    ... of determination was published in the Federal Register on April 23, 2010 (75 FR 21354). At the... Employment and Training Administration Hart and Cooley, Inc., A Subsidiary of Tomkins, PLC Including On- Site... subsidiary of Tomkins, PLC, including on-site leased workers from Reliable, Masiello Employment...

  17. 75 FR 452 - Tenneco, Inc.; Including On-Site Workers From Elite Staffing, Inc.; Cozad, NE; Tenneco, Inc...

    2010-01-05

    ... Federal Register on February 2, 2009 (74 FR Number 5871). The Department issued an amended certification... Employment and Training Administration Tenneco, Inc.; Including On-Site Workers From Elite Staffing, Inc.; Cozad, NE; Tenneco, Inc.; Including On-Site Leased Workers of Elite Staffing, Inc.; Monroe, MI;...

  18. 76 FR 16447 - ETHICON, a Subsidiary of Johnson & Johnson Including On-Site Leased Workers From Kelly Temporary...

    2011-03-23

    ... Employment and Training Administration ETHICON, a Subsidiary of Johnson & Johnson Including On-Site Leased... and Johnson Company, San Angelo, Texas, separated from employment on or after June 9, 2007 through... Johnson & Johnson, including on-site leased workers from Kelly Temporary Services, San Angelo, Texas....

  19. 40 CFR 262.212 - Making the hazardous waste determination at an on-site interim status or permitted treatment...

    2010-07-01

    ....212 Making the hazardous waste determination at an on-site interim status or permitted treatment... hazardous waste permit or interim status as soon as it arrives in the on-site treatment, storage or disposal... permitted treatment, storage or disposal facility. (e) If the unwanted material is a hazardous waste,...

  20. 76 FR 79221 - Android Industries Belvidere, LLC, Including On-Site Leased Workers From QPS Employment Group...

    2011-12-21

    ... notice was published in the Federal Register on July 16, 2010 (75 FR 41526). At the request of the State... Employment and Training Administration Android Industries Belvidere, LLC, Including On-Site Leased Workers... Android Industries Belvidere, LLC, including on-site leased workers from QPS Employment Group and...

  1. Lessons Learned from the On-Site Disposal Facility at Fernald Closure Project

    The On-Site Disposal Facility (OSDF) at the U.S. Department of Energy's (DOE) Fernald Closure Project near Cincinnati, Ohio is an engineered above-grade waste disposal facility being constructed to permanently store low level radioactive waste (LLRW) and treated mixed LLRW generated during Decommissioning and Demolition (D and D) and soil remediation performed in order to achieve the final land use goal at the site. The OSDF is engineered to store 2.93 million cubic yards of waste derived from the remediation activities. The OSDF is intended to isolate its LLRW from the environment for at least 200 years and for up to 1,000 years to the extent practicable and achievable. Construction of the OSDF started in 1997 and waste placement activities will complete by the middle of April 2006 with the final cover (cap) placement over the last open cell by the end of Spring 2006. An on-site disposal alternative is considered critical to the success of many large-scale DOE remediation projects throughout the United States. However, for various reasons this cost effective alternative is not readily available in many cases. Over the last ten years Fluor Fernald Inc. has cumulated many valuable lessons learned through the complex engineering, construction, operation, and closure processes of the OSDF. Also in the last several years representatives from other DOE sites, State agencies, as well as foreign government agencies have visited the Fernald site to look for proven experiences and practices, which may be adapted for their sites. This paper present a summary of the major issues and lessons leaned at the Fernald site related to engineering, construction, operation, and closure processes for the disposal of remediation waste. The purpose of this paper is to share lessons learned and to benefit other projects considering or operating similar on-site disposal facilities from our successful experiences. (authors)

  2. A business case for on-site generation: The BD biosciences pharmingen project

    Firestone, Ryan; Creighton, Charles; Bailey, Owen; Marnay, Chris; Stadler, Michael

    2003-09-01

    Deregulation is haltingly changing the United States electricity markets. The resulting uncertainty and/or rising energy costs can be hedged by generating electricity on-site and other benefits, such as use of otherwise wasted heat, can be captured. The Public Utility Regulatory Policy Act (PURPA) of 1978 first invited relatively small-scale generators ({ge} 1 MW) into the electricity market. The advent of efficient and reliable small scale and renewable equipment has spurred an industry that has, in recent years, made even smaller (business scale) electricity generation an economically viable option for some consumers. On-site energy capture and/or conversion, known as distributed energy resources (DER), offers consumers many benefits, such as economic savings and price predictability, improved reliability, control over power quality, and emissions reductions. Despite these benefits, DER adoption can be a daunting move to a customer accustomed to simply paying a monthly utility bill. San Diego is in many ways an attractive location for DER development: It has high electricity prices typical of California and a moderate climate i.e. energy loads are consistent throughout the year. Additionally, the price shock to San Diego Gas and Electric (SDG&E) customers during the summer of 2000 has interested many in alternatives to electricity price vulnerability. This report examines the business case for DER at the San Diego biotechnology supply company, BD Biosciences Pharmingen, which considered DER for a building with 200-300 kW base-load, much of which accommodates the refrigerators required to maintain chemicals. Because of the Mediterranean climate of the San Diego area and the high rate of air changes required due to on-site use of chemicals, modest space heating is required throughout the year. Employees work in the building during normal weekday business hours, and daily peak loads are typically about 500 kW.

  3. On-Site or Off-Site Renewable Energy Supply Options?

    Marszal, Anna Joanna; Heiselberg, Per; Jensen, Rasmus Lund;

    2012-01-01

    into consideration the limited area of roof and/or façade, primarily in the dense city areas, the Danish weather conditions, the growing interest and number of wind turbine co-ops, the off-site renewable energy supply options could become a meaningful solution for reaching ‘zero’ energy goal in the...... analysis includes five technologies, i.e., two on-site options: (1) photovoltaic, (2) micro combined heat and power, and three off-site options: (1) off-site windmill, (2) share of a windmill farm and (3) purchase of green energy from the 100% renewable utility grid. The results indicate that in case of...

  4. On-site treatment and landfilling of MSWI air pollution control residues

    Lundtorp, Kasper; Jensen, Dorthe Lærke; Sørensen, Mette Abildgaard;

    2003-01-01

    Air pollution control (APC) residues from municipal solid waste incineration (MSWI) are difficult to landfill due to substantial leaching of trace metals. An on-site pretreatment prior to landfilling of APC-residues was investigated in terms of bench-scale experiments with a semidry APC-residue and...... a fly ash. The treatment involved mixing of the residues with a ferrous sulphate solution and subsequent oxidation of the suspension. Afterwards, the suspension was spread on a dedicated landfill section and allowed to drain by gravity through the drainage system of the landfill. The wastewater from...

  5. Recommended criteria for the evaluation of on-site nuclear power plant emergency exercises

    A review of existing Canadian and International emergency exercise evaluation criteria and approaches has been conducted. Based on the results of the review, criteria are proposed for the evaluation of on-site emergency exercises for Canadian nuclear power stations. The proposed criteria are performance-based. They are comprehensive, yet remain adaptable to all stations and accident scenarios. They are primarily aimed at radiological emergency exercises, but are entirely applicable to fire or other conventional exercises. This report also addresses evaluation preparation and methodology. (author). 21 refs., 6 tabs

  6. Evaluation of the Institutional Conservation Program: results of on-site analyses. Final report

    1983-04-30

    In October 1981, the US Department of Energy (DOE) contracted to evaluate Cycles I and II of the Institutional Conservation Program (ICP). The Program provides assistance and matching funds to help four types of non-profit institutions reduce their energy consumption. On the basis of analyses of institutional records, on-site assessments, and interviews with state and institution administrators, evaluators assessed the implementation of the program, the impacts of the ICP and estimated the energy savings participating institutions achieved using data collected from Cycles I and II participants. The findings and conclusions of the ICP evaluation are presented.

  7. Construction of helical coil winding machine for LHD and on-site winding

    On-site winding of two helical coils of LHD started at the beginning of 1995, using a numerically controlled winding machine. They are large-scale pool-cooled superconducting coils which are designed to satisfy fully stabilized criterion. The conductor consists of Nb-Ti/Cu strands with a pure aluminum stabilizer and copper sheath. The main demanded values for winding the coils are 2.0 mm and 6.5 microm for the accuracy of coil and the average gap between layers, respectively. A winding method was established by trial of winding

  8. On-site Atractive Multiorbital Hamiltonian for $d$-Wave Superconductors

    Bishop, Christopher B.; Liu, Guangkun; Dagotto, Elbio; Moreo, Adriana

    2016-01-01

    We introduce a two-orbital Hamiltonian on a square lattice that contains on-site attractive interactions involving the two $e_g$ orbitals. Via a canonical mean-field procedure similar to the one applied to the well-known negative-$U$ Hubbard model, it is shown that the new model develops $d$-wave ($B_{1g}$) superconductivity with nodes along the diagonal directions of the square Brillouin zone. This result is also supported by exact diagonalization of the model in a small cluster. The expecta...

  9. Using Automated On-Site Monitoring to Calibrate Empirical Models of Trihalomethanes Concentrations in Drinking Water

    Thomas E. Watts III

    2015-10-01

    Full Text Available An automated, on-site trihalomethanes concentration data set from a conventional water treatment plant was used to optimize powdered activated carbon and pre-chlorination doses. The trihalomethanes concentration data set was used with commonly monitored water quality parameters to improve an empirical model of trihalomethanes formation. A calibrated model was used to predict trihalomethanes concentrations the following year. The agreement between the models and measurements was evaluated. The original model predicted trihalomethanes concentrations within ~10 μg·L−1 of the measurement. Calibration improved model prediction by a factor of three to five times better than the literature model.

  10. Solitary heat waves in nonlinear lattices with squared on-site potential

    Rovinita Perseus; M M Latha

    2013-06-01

    A model Hamiltonian is proposed for heat conduction in a nonlinear lattice with squared on-site potential using the second quantized operators and averaging the same using a suitable wave function, equations are derived in discrete form for the field amplitude and the properties of heat transfer are examined theoretically. Numerical analysis shows that the propagation of heat is in the form of solitons. Furthermore, a systemized version of tanh method is carried out to extract solutions for the resulting nonlinear equations in the continuum case and the effect of inhomogeneity is studied for different temperatures.

  11. Lectotype optimization of mid-highrise residential building based on site conditions and seismic fortification intensity

    2006-01-01

    A multi-objective lectotype optimization model based on site conditions and seismic fortification intensity is presented for mid-highrise residential buildings taking into account multiple items such as the original investment, disaster losses and maintenance cost, the integral stiffness, the total ductility, the construction period, and so on. A Three-Scale Fuzzy Analytical Hierarchy process is proposed by introducing the Three-Scale Analytical Hierarchy process and the trapezoid fuzzy number. The result of a calculation example shows that the T-FAHP is practical.

  12. Analysis of acoustic-seismic coupling for CTBT on-site inspection support

    The measurements of weak seismic signals, e.g. aftershock measurements during an on-site inspection for the Comprehensive Nuclear Test-Ban Treaty (CTBT), can be masked by man-made disturbances. These can be caused by airborne signals, like the noises of aircraft or helicopters, which couple to the ground and excite soil vibrations. We have measured sound pressure and corresponding soil vibrations caused by aircraft and by signals produced artificially with a speaker. Methods of acoustic deadening were applied to reduce the incident acoustic power locally. The influence on soil vibrations in different depths below the surface is investigated. The underlying question was whether the coupling of sound happens locally or soil vibrations created in a wide area around the sensor sum up to the total seismic signal. A better understanding of acoustic-seismic coupling can be used to develop guidelines for seismic aftershock measurements in order to improve the performance of on-site inspections for the CTBT.

  13. Waste of Felling and On-Site Production of Teak Squarewood of the Community Forest

    Ahmad Budiaman

    2012-12-01

    Full Text Available Major suppliers of teak wood for the raw material of furniture industry in Indonesia are Perum Perhutani, community forests, and private forests.  Community teak forest management produce roundwood or squarewood, in which squarewood is produced on the felling site by the use of chainsaw after felling and bucking activities. Utilization of teak wood from community forest has been practiced for decades, however information on the extent of utilization and the quantity of wood waste have not been published to a greater extent. The present research was intended to determine and analyze the extent of utilization and teak wood waste produced from felling and bucking, and on-site squarewood production of community forests.  Quantification of wood waste from felling and bucking was based on the whole tree method, while that of squarewood production was based on the percentage of yield. It was found that the quantity of teak felling and bucking wood waste in community forest was reaching 28% of felled wood volume that consisted of branch and twig (46.15%, upper trunk (30.77%, short cut off (15.38%, and stumps (7.69%. The largest part of the wood waste of teak felling and bucking satisfied the requirement as raw material of wood working industry according to Indonesian National Standard. On-site production of squarewood increased the quantity of wood waste in the forests (in the form of slabs and sawdust.Keywords: wood waste, felling, bucking, squarewood, community forest

  14. Customer adoption of small-scale on-site power generation

    The electricity supply system is undergoing major regulatory and technological change with significant implications for the way in which the sector will operate (including its patterns of carbon emissions) and for the policies required to ensure socially and environmentally desirable outcomes. One such change stems from the rapid emergence of viable small-scale (i.e., smaller than 500 kW) generators that are potentially competitive with grid delivered electricity, especially in combined heat and power configurations. Such distributed energy resources (DER) may be grouped together with loads in microgrids. These clusters could operate semi-autonomously from the established power system, or macrogrid, matching power quality and reliability more closely to local end-use requirements. In order to establish a capability for analyzing the effect that microgrids may have on typical commercial customers, such as office buildings, restaurants, shopping malls, and grocery stores, an economic mod el of DER adoption is being developed at Berkeley Lab. This model endeavors to indicate the optimal quantity and type of small on-site generation technologies that customers could employ given their electricity requirements. For various regulatory schemes and general economic conditions, this analysis produces a simple operating schedule for any installed generators. Early results suggest that many commercial customers can benefit economically from on-site generation, even without considering potential combined heat and power and reliability benefits, even though they are unlikely to disconnect from the established power system

  15. A reliable aptamer array prepared by repeating inkjet-spotting toward on-site measurement.

    Inoue, Suzuyo; Seyama, Michiko; Miura, Toru; Horiuchi, Tsutomu; Iwasaki, Yuzuru; Takahashi, Jun-Ichi; Hayashi, Katsuyoshi; Tamechika, Emi

    2016-11-15

    A preparation protocol is proposed for a reliable aptamer array utilizing an ink-jet spotter. We accumulated streptavidin and biotinylated-aptamer in this order on a biotinylated-polyethylene glycol-coated gold substrate to prepare an aptamer array. The aptamer array was prepared with an alternate spotting structure where each aptamer spot was placed between reference spots formed with blocking solution thus suppressing contamination from neighboring spots during the blocking and washing processes. Four aptamer spots were prepared in a small area of 1×4.8mm(2) with five reference spots made of blocking solution. We evaluated the thrombin binding ability of the spotted aptamer array using a multi-analysis surface plasmon resonance sensor. We prepared a disposable capillary-driven flow chip designed for on-site measurement (Miura et al., 2010) with our aptamer array and detected thrombin from phosphate-buffered saline at concentrations of 50ngmL(-1) and 1μgmL(-1) (equivalent to 1.35 and 27nM, respectively). A correlation was observed between the refractive index shift and thrombin concentration. This implies that our array preparation protocol meets the requirement for the preparation of a one-time-use chip for on-site measurement. PMID:27315520

  16. Combination of in situ preconcentration and on-site analysis for phosphate monitoring in fresh waters.

    Li, Weijia; Lee, Lai Yoke; Yung, Lin Yue Lanry; He, Yiliang; Ong, Choon Nam

    2014-08-01

    Excess nutrients of phosphorus and nitrogen would lead to adverse impacts on a water body. It is important that their concentrations in a dynamic water ecosystem are measured accurately and constantly for an early warning before occurrences of algal blooms and for environmental management. Nevertheless, on-site measurements by existing technologies are often limited by the inherent sensitivities. In this study, a portable system for dissolved phosphate monitoring in freshwater based on the diffusive gradients in thin films (DGT) technique was developed. A polydiallydimethylammonium chloride (PDA) aqueous solution and a dialysis membrane were used as a binding phase and a diffusive layer in this preconcentration device, respectively. The binding properties of the PDA solution were evaluated in solutions of different pH (3 to 9) and varying concentrations of anions (2.0-20 mM). The amount of phosphates preconcentrated in the devices was measured by ultraviolet-visible (UV) spectroscopy to obtain the concentrations in waters without elution steps. The devices were validated in synthetic river water with good agreement with the theoretical prediction and in natural river water. A system combining this preconcentration device and a compact detection chamber equipped with a pair of light emitting diodes (LED) was studied in lab synthetic solutions for on-site monitoring of phosphate concentrations and their fluctuations. PMID:25011428

  17. Loch Linnhe `94: Test operations description and on-site analysis, US activities

    Mantrom, D.D.

    1994-11-01

    A field experiment named Loch Linnhe `94 (LL94) is described. This experiment was conducted in upper Loch Linnhe, Scotland, in September 1994, as an exercise involving UK and US investigators, under the Joint UK/US Radar Ocean Imaging Program. This experiment involved a dual-frequency, dual-polarization hillside real aperture radar operated by the UK, Lawrence Livermore National Laboratory`s (LLNL) current meter array (CMA), in-water hydrodynamic sensors, and meteorological measurements. The primary measurements involved imaging ship-generated and ambient internal waves by the radar and the CMA. This report documents test operations from a US perspective and presents on-site analysis results derived by US investigators. The rationale underlying complementary radar and CMA measurements is described. Descriptions of the test site, platforms, and major US instrument systems are given. A summary of test operations and examples of radar, CMA, water column profile, and meteorological data are provided. A description of the rather extensive analysis of these data performed at the LL94 test site is presented. The products of this analysis are presented and some implications for further analysis and future experiments are discussed. All experimental objectives were either fully or partially met. Powerful on-site analysis capabilities generated many useful products and helped improve subsequent data collection. Significant further data analysis is planned.

  18. On-site storage of high level nuclear waste: Attitudes and perceptions of local residents

    No public policy issue has been as difficult as high-level nuclear waste. Debates continue regarding Yucca Mountain as a disposal site, and - more generally - the appropriateness of geologic disposal and the need to act quickly. Previous research has focused on possible social, political, and economic consequences of a facility in Nevada. Impacts have been predicted to be potentially large and to emanate mainly from stigmatization of the region due to increased perceptions of risk. Analogous impacts from leaving waste at power plants have been either ignored or assumed to be negligible. This paper presents survey results on attitudes of residents in three countries where nuclear waste is currently stored. Topics include perceived risk, knowledge of nuclear waste and radiation, and impacts on jobs, tourism, and housing values from leaving waste on site. Results are similar to what has been reported for Nevada; the public is concerned about possible adverse effects from on-site storage of waste. 24 refs., 7 figs., 5 tabs

  19. User's manual for applicants proposing on-site burial of self-generated radioactive waste

    It is the primary purpose of this document to describe for medical and research institutions as well as industrial generators of low-level radioactive waste the NRC or state submittal requirements for authorizing the on-site burial of self-generated radioactive waste. Authorization is given to an applicant to dispose of its own radioactive waste by burial in soil on its private property, and this general burial procedure will, in this study, be referred to as the ''operation of an on-site radioactive waste burial ground'' even though operations are fairly limited to occasional disposals. This manual is designed for use by medical and research institutions and industrial low-level radioactive waste generators. This manual includes requirements and costs for site selection, preparation and maintenance as well as a discussion of general procedures necessary for operation and closure of such a disposal site in a manner minimizing risks of hazardous or unexpected exposures. Recommendations for obtaining technical assistance are also included. 19 refs., 3 figs., 4 tabs

  20. On-site Labour Productivity of New Zealand Construction Industry: Key Constraints and Improvement Measures

    Serdar Durdyev

    2011-09-01

    Full Text Available Productivity is key to the survival and growth of any organisation, industry or nation. Some factors constrain the achievement of the set project objectives in the New Zealand building and construction industry and are responsible for the reported steady decline of productivity and performance. This study aims to identify the key constraints to on-site labour productivity and improvement measures. Using the descriptive survey method, views of some project managers, contractors and subcontractors in New Zealand were canvassed via pilot interviews and questionnaire surveys at the qualitative and quantity data gathering stages, respectively. Multi-attribute technique was used to analyse the quantitative data. Results showed that the key external constraints to on-site labour productivity comprise, in order of decreasing impact, statutory compliance, unforeseen events and wider external dynamics. The internal constraints, which contribute 67 percent of the onsite productivity issues, comprise reworks, level of skill and experience of the workforce, adequacy of method of construction, buildability issues, and inadequate supervision and coordination. . The factors underlying each broad category of external and internal constraints are reported. The relative levels of impact of the identified constraints are expected to guide the project team in addressing the constraints in a cost-effective manner.

  1. On-site semi-quantitative analysis for ammonium nitrate detection using digital image colourimetry.

    Choodum, Aree; Boonsamran, Pichapat; NicDaeid, Niamh; Wongniramaikul, Worawit

    2015-12-01

    Digital image colourimetry was successfully applied in the semi-quantitative analysis of ammonium nitrate using Griess's test with zinc reduction. A custom-built detection box was developed to enable reproducible lighting of samples, and was used with the built-in webcams of a netbook and an ultrabook for on-site detection. The webcams were used for colour imaging of chemical reaction products in the samples, while the netbook was used for on-site colour analysis. The analytical performance was compared to a commercial external webcam and a digital single-lens reflex (DSLR) camera. The relationship between Red-Green-Blue intensities and ammonium nitrate concentration was investigated. The green channel intensity (IG) was the most sensitive for the pink-violet products from ammonium nitrate that revealed a spectrometric absorption peak at 546 nm. A wide linear range (5 to 250 mgL⁻¹) with a high sensitivity was obtained with the built-in webcam of the ultrabook. A considerably lower detection limit (1.34 ± 0.05mgL⁻¹) was also obtained using the ultrabook, in comparison with the netbook (2.6 ± 0.2 mgL⁻¹), the external web cam (3.4 ± 0.1 mgL⁻¹) and the DSLR (8.0 ± 0.5 mgL⁻¹). The best inter-day precision (over 3 days) was obtained with the external webcam (0.40 to 1.34%RSD), while the netbook and the ultrabook had 0.52 to 3.62% and 1.25 to 4.99% RSDs, respectively. The relative errors were +3.6, +5.6 and -7.1%, on analysing standard ammonium nitrate solutions of known concentration using IG, for the ultrabook, the external webcam, and the netbook, respectively, while the DSLR gave -4.4% relative error. However, the IG of the pink-violet reaction product suffers from interference by soil, so that blank subtraction (|IG-IGblank| or |AG-AGblank|) is recommended for soil sample analysis. This method also gave very good accuracies of -0.11 to -5.61% for spiked soil samples and the results presented for five seized samples showed good correlations between

  2. Analytical quality control concept in the Euratom On-Site laboratories

    Safeguarding the large reprocessing plants poses undoubtedly a challenge to the Safeguards Authorities. The size of the plants and the high material throughput require a significant effort in verification activities. In order to achieve the required high level of detection probability, the safeguards inspectors need to take a high number of samples which have to be subjected to independent analysis. Evidently, the results of these analyses need to be highly reliable, reporting times have to be short and costs have to be kept at a reasonably low level. Based on the latter two aspects, the Euratom Safeguards Office (ESO) decided in the early 1990's to conceive, develop, install and operate safeguards analytical laboratories at the site of the two large European reprocessing plants at Sellafield (UK) and La Hague (France). The analytical concept of these 'On-Site Laboratories' was developed jointly between ESO and the Institute for Transuranium Elements (ITU). Already at this conceptual stage, the aspects related to analytical quality control were discussed and incorporated in the analytical strategy. The present paper summarises the analytical challenges, describes some operational aspects and explains the analytical concept, highlighting the measures and tools that are implemented for assuring a high degree of reliability of measurements results. The quality control concept implemented in the on-site laboratories forms an integral part of the laboratories' measurement strategy. The concept is arranged in five independent levels and assures a comprehensive check of all measurement results produced in the on-site laboratories. The fact that the quality control is integrated in the laboratory information management system imposes a stringent control on each individual measurement and on each technique. The existing system ensures that the standards set in the International Target Values are met. The analysts consider the quality control as a tool to improve the overall

  3. Analytical quality control concept in the Euratom on-site laboratories

    Full text: Two on-site laboratories have been developed, installed, commissioned and put into routine operation by the Euratom safeguards office (ESO), jointly with the Institute for Transuranium Elements (ITU). These laboratories are operated by ITU staff and provide verification measurement results on samples taken by Euratom inspectors. The analysts work in weekly changing shift teams, manage the laboratories and operate the various analytical techniques. Operating such a laboratory at a remote location, without a senior scientist immediately available in case of problems, The existing boundary conditions challenge the robustness of the entire laboratory, i.e. comprising staff and instrumentation. In order to continuously ensure a high degree of reliability of the measurement results, a stringent quality control system was implemented. The quality control concept for the two on-site laboratories was developed at a very early stage and implemented in the pre-OSL training facility at ITU. This enabled to thoroughly test and develop further the concept. At the same time the analysts get acquainted with the quality control procedures in place and they are instilled with the principles. The quality control concept makes use of a fully computerized data management and data acquisition system. All measurement devices, including balances, density meters, mass spectrometers, passive neutron counter, hybrid K-edge instrument, gamma spectrometers and alpha spectrometers are networked and data exchange is performed on electronic basis. A specifically developed laboratory information management system collects individual measurement data, calculates intermediate and final result and shares the information with a quality control module. In order to ensure the reliability of the results, which are reported to the ESO inspectorate, five levels of quality control were implemented. The present paper describes in detail the different levels of quality control, which check the

  4. Operating experience relating to on-site electric power sources. Proceedings of a Specialist Meeting

    The reliability of on-site electric power sources of nuclear power plants usually consisting of diesel generators, gas turbine generators and DC power sources, has been a matter of concern during reactor operations. The frequent recurrence and the important consequences of failures relating to on-site electric power sources have led to a general consensus that they form one of the most significant features influencing the total performance of the safety Systems. This has also been confirmed by surveys performed on the incidents reported through the NEA Incident Reporting System (IRS). Accordingly, a recommendation to organise a Specialist Meeting on the subject was made at the third annual meeting of CSNI Principal Working Group No. 1 (Operating Experience and Human Factors). At the 12. meeting of the CSNI held in November 1984. the Committee endorsed the proposal and accepted an offer by the United Kingdom to host and organise the Specialist Meeting. The Specialist Meeting, sponsored by the CSNI, was held in London, United Kingdom from 16 to 18 October 1985. It was hosted by H.M. Nuclear Installations Inspectorate of the Health and Safety Executive. The purpose of the meeting was to promote the exchange of Information on operating experience relating to on-site electric power sources and to look for measures to further improve their reliability In the areas of design, operation and licensing. The meeting was organised by a Programme Group which included nominated members of CSNI PWG No. 1. the Programme Group met in May and June 1985 in Paris to agree on the programme and practical arrangements for the meeting. As a result of the review of the abstracts which had been contributed in response to the Call for Papers, 28 papers were accepted for presentation during the meeting. Approximately 60 delegates from 13 Member countries, and the NEA Secretariat, attended the meeting. Session summaries prepared by the respective session chairmen are Included prior to the

  5. Heat-flow properties of systems with alternate masses or alternate on-site potentials

    Pereira, Emmanuel; Santana, Leonardo M.; Ávila, Ricardo

    2011-07-01

    We address a central issue of phononics: the search of properties or mechanisms to manage the heat flow in reliable materials. We analytically study standard and simple systems modeling the heat flow in solids, namely, the harmonic, self-consistent harmonic and also anharmonic chains of oscillators, and we show an interesting insulating effect: While in the homogeneous models the heat flow decays as the inverse of the particle mass, in the chain with alternate masses it decays as the inverse of the square of the mass difference, that is, it decays essentially as the mass ratio (between the smaller and the larger one) for a large mass difference. A similar effect holds if we alternate on-site potentials instead of particle masses. The existence of such behavior in these different systems, including anharmonic models, indicates that it is a ubiquitous phenomenon with applications in the heat flow control.

  6. Operational experiences of on-site transport of spent nuclear fuels in Korea

    Since 1990 more than 800 PWR spent nuclear fuel assemblies has been on-site transported using two kinds of transport casks from one unit to nearby another unit in order to secure the storage capacity of spent nuclear fuel of the Kori nuclear power plant in Korea. The complete on-site transport system, which includes two transport casks, the related equipment and two transport vehicles, had been provided. Considerable amount of modification to the existing power plant equipment and facilities had been carried out. Two kinds of the KSC-4 cask and the CASTOR KN-12 cask were developed and licensed in accordance with the Korea and the IAEA's safe transport regulations. From 1990 to the first half of 2002 two KSC-4 casks were used and more than 420 spent nuclear fuels were transported. From the second half of 2002 two CASTOR KN-12 cask have been used to transport more than 400 spent nuclear fuels. About 180 spent nuclear fuels of Kori site are transported using the CASTOR KN-12 cask this year, and the KSC-4 casks are no longer used. The CASTOR KN-12 cask was designed to transport twelve spent nuclear fuel assemblies from pressure water reactors and to comply with the requirements of the Korea and the IAEA regulations for Type B(U)F package. PWR spent nuclear fuels with maximum initial enrichment of 5.0wt.%, maximum average burn-up of 50,000MWD/MTU and minimum cooling time of 7 years are loaded and subsequently transported under dry and wet conditions. The loaded weight of the cask with impact limiters is 85 tons. Two casks were fabricated in accordance with ASME B and PV code Section III Division 3. The related equipment to handle the cask and to perform on-site transport are cask lifting devices, cask lid handling tools, crane adapters, vacuum drying and helium back-filling equipment and cask cool-down equipment, spent nuclear fuel handling tool, decontamination equipment using high pressure water and transport vehicles. However, spent nuclear fuels of the Kori site has

  7. On-site methanol production plant from natural gas with modular HTR

    The consumption of natural gas has been increasing year by year due to its relatively low level of CO2 emissions and low cost. All of the natural gas consumed in Japan is imported from foreign countries in the form of liquid natural gas (LNG). Therefore, liquefaction, transportation and storage equipment costs are large. On the other hand, handling methanol is as easy as handling oil. If a plant for producing methanol from natural gas is sited near a natural gas field, transportation and storage costs are expected to be significantly lower than such costs for LNG production. From the above viewpoint, the concept of an on-site methanol production plant with a modular HTR (High Temperature Reactor) was studied. (author)

  8. On-site habitability in the event of an accident at a nuclear facility

    This publication is intended to provide technical guidance and a methodology for regulatory bodies, designers, constructors and operators of nuclear facilities to assist them in assessing the current situation as regards on-site habitability for their specific nuclear facilities. Initially, the aim will be to ensure that the ''vital areas'' of the facility which are necessary for the safe operation and shutdown of the facility will remain habitable, in some cases continuously and in others transiently, in the event of an accident inside or outside the installation. The assessment procedure can be used not only for potential radiation accidents but also to consider the effects on habitability of those probable non-radiological events which, if not correctly and effectively countered, could lead to the development of potentially unsafe conditions in the facility itself. 30 refs, 4 figs, 8 tabs

  9. On-site field test on groundwater re-flooding (2)

    NONE

    1999-02-01

    A mini-dome (an underground structure to be closed; ground level: - 50 m to - 82.5 m) situated on a diluvium along the Sagami River, Kanagawa prefecture, Japan, was used to perform an on-site field tests on groundwater re-flooding for 11 months after the mini-dome was filled up with sand, mortar, and fluidized soil consisting of cement and mudwater. The present report includes monitoring data of the environmental groundwater at the surrounding bed rocks and of the groundwater in the deep mudstone beneath the site. Change with time at various test points in water pressure, water temperature, pH, electric conductivity, and the temperature of the wall of the structure making the mini-dome is reported. Furthermore, some isotopic abundance and the monitoring results on chemical analysis were also included. (S. Ohno)

  10. Validation of on-site job-built guardrails with shoring jack as supports

    Lan, A.

    2014-06-01

    Full Text Available To protect themselves against fall hazards in a slab-column frame, workers use the row of shoring jacks installed at 1 m from the edge as supports for on-site built guardrails. Inspectors of the Quebec Workers Compensation Board (Commission de la santé et de la sécurité du travail (CSST have expressed concern about the safety and compliance of these on-site built guardrails with the Quebec Safety Code for the Construction Industry (S-2.1, r.4. Some workers have also inquired if the shoring jack can be used as an anchor for a travel restraint system. The present study describes how an evaluation method and a test protocol have been used to verify if guardrails built on-site, with shoring jacks as supports, are safe and comply with the requirements of S-2.1, r.4 and if the shoring jack can be used as an anchor point for a travel restraint system. The results of the study show 1 guardrails built on site with shoring jacks as supports, are safe and comply with S-2.1, r.4 and 2 shoring jacks used as supports for guardrails must not be used as an anchor for a travel restraint system.Para la protección contra el peligro de caída en altura durante la ejecución de la estructura de un edificio, los trabajadores utilizan puntales acodalados a dos forjados y situados a 1 metro del borde de forjado como apoyo de las barandillas de seguridad. Inspectores de la Quebec Workers Compensation Board (Commision de la santé et de la sécurité du travail (CSST han expresado su preocupación por la seguridad y el cumplimiento de estos sistemas de protección en la construcción conforme al Código de Seguridad de Quebec para la industria de la construcción (S-2.1, R.6. Así mismo algunos trabajadores han mostrado su inquietud sobre la utilización de los puntales como sistemas para limitar el desplazamiento. El presente estudio describe un método de evaluación y un procedimiento de ensayo que se han utilizado para verificar si las barandillas de seguridad

  11. Methods and apparatus for the on-site production of hydrogen peroxide

    Buschmann, Wayne E. (Inventor); James, Patrick I. (Inventor)

    2010-01-01

    Methods, apparatus, and applications for the on-site production of hydrogen peroxide are described. An embodiment of the apparatus comprises at least one anolyte chamber coupled to at least one anode, at least one catholyte chamber, wherein the at least one catholyte chamber is coupled to at least one cathode, at least one anode membrane and at least one cathode membrane, wherein the anode membrane is adjacent to the at least one anode, wherein the cathode membrane is adjacent to the at least one cathode, at least one central chamber disposed between the at least one anolyte chamber and the at least one catholyte chamber. Hydrogen peroxide is produced by reduction of an oxygen-containing gas at the cathode.

  12. Operating experience and licensing criteria relating to on-site electric power systems in Italy

    The most significant events of on-site electrical power supply degradation in Italian plants took place in coincidence with severe atmospheric conditions or with the propagation of disturbances by lightning stroke inside the plant. Essential instrumentation was lost in two cases so that, for some time, no indication of the plant status was allowed. In both cases the recovery of the plant was achieved by restoration of external power supply. Corrective actions included both improvement in immunity to disturbances, redundancy, capability and physical separation and DG's reliability demonstration. Design and safety analysis of new plants are now carried out with the help of reliability studies and probabilistic risk assessment. As a result, design changes were performed on new plants to improve the reliability of DGs start-up and the independence of the electrical emergency divisions. (authors)

  13. Evaluation of reliability of on-site A.C. power systems based on maintenance records

    To the end of ascertain in what extent the evaluation of reliability of emergency diesel generators (D.G.) can be improved by means of a deeper knowledge of their operating history a study has been carried-out on 21 D.G. sets: 4 D.G. of the Caorso nuclear plant (BWR, 870 MWe) and 17 D.G. in service at 6 steam-electric fossil-fuelled plants. The major points of interest resulting from this study are: 1) reliability assessments of A.C. on-site power Systems, made on the basis of outcomes of surveillance tests, may lead to results which overestimate the real performance. 2) the unreliability of a redundant System of stand-by components is determined in large extent by unavailabilities due to scheduled and unscheduled maintenance, latent failures, tests. (authors)

  14. Experiences as an observer of the CTBT on-site-inspection exercise DE07 in Chernobyl

    The directed exercise DE07 took place in the Chernobyl exclusion zone in the Ukraine from 4. June 2007 to 14. June 2007. The aim of the exercise was to train several aspects of an on-site-inspection (OSI) to provide evidence of a forbidden nuclear weapons test in the context of the preparation of the comprehensive test ban treaty (CTBT). I had the opportunity to join the exercise as an observer. 25 experts from 22 state parties took part in the exercise. In addition 4 observers from 4 countries participated. The aim of the directed exercise was to measure radioactivity levels in a simulated inspection area and to identify the nuclides. The following aspects of an OSI were trained: carborne and airborne gamma survey; environmental sampling and analysis in a field laboratory; safety of work, personal protection and decontamination; communication and navigation in the field; data preparation and data handling

  15. On-site vs off-site management of environmental restoration waste: A cost effectiveness analysis

    The Sandia National Laboratories Environmental Restoration Project is expected to generate relatively large volumes of hazardous waste as a result of cleanup operations. These volumes will exceed the Laboratories existing waste management capacity. This paper presents four options for managing remediation wastes, including three alternatives for on-site waste management utilizing a corrective action management unit (CAMU). Costs are estimated for each of the four options based on current volumetric estimates of hazardous waste. Cost equations are derived for each of the options with the variables being waste volumes, the major unknowns in the analysis. These equations provide a means to update cost estimates as volume estimates change. This approach may be helpful to others facing similar waste management decisions

  16. Utility investment in on-site solar: risk and return analysis for capitalization and financing

    Kahn, E.; Schutz, S.

    1978-09-01

    A set of financial strategies designed to accelerate the penetration of on-site solar heating and cooling systems are studied. The approach of portfolio theory or the capital asset pricing model (CAPM) is used. The major features of the CAPM is summarized including a survey of those applications which are most relevant to the analysis. These include utility return on equity calculations and project evaluation techniques. How to apply empirical results is discussed based on CAPM methods. In particular, applications to the capitalization variant of the utility investment strategy and the financing variant are distinguished. Subsidization rationales are also discussed. Empirical results to date are summarized, including estimation problems for the various risk measures. The general problem of financial risk assessment for energy technologies is reviewed. (MHR)

  17. On-site power generation in Italy: Regulatory and commercial interface problems

    This paper first briefly assesses the potential in Italy for auto-production of electricity by private firms making use of various renewable energy sources - hydroelectric, wind, solar and biomass energy. It then discusses the impacts of current national normatives governing on-site power generation (especially those which specify minimum plant power ratings and air pollution control requirements), the severity of marketing constraints for auto-produced power, as well as, the compatibility of this practice with the future development plans of ENEL (Italian National Electricity Board). Attention is given to power pooling and common carrier problematics, relative national fiscal policies regarding the use of conventional energy sources, and rate structure for the case of power sharing with the national grid

  18. Recent developments in on-site nuclear engineering graduate programs at the University of Cincinnati

    The University of Cincinnati (UC) Department of Mechanical, Industrial, and Nuclear Engineering with the sponsorship of the Toledo-Edison Company (TED) has undertaken a new multiyear on-site graduate program at the Davis-Besse nuclear power plant. The program enables TED employees with the proper academic background to earn a master of science (MS) degree in nuclear engineering (mechanical engineering option). In addition, with management approval, selected individual courses may be taken without enrolling in the overall program. One objective of the program is to enhance the understanding and engineering skills of the participants so that this knowledge may be applied to their professional positions. To this end, appropriate plant-specific examples and problems are incorporated into each course, enhancing the technical staff's understanding of the practical applications of the principles presented

  19. User's manual for applicants proposing on-site burial of self-generated radioactive waste

    This document describes, for medical and research institutions as well as industrial generators of low-level radioactive waste, the NRC or state submittal requirements for authorizing the on-site burial of self-generated radioactive waste. An important part of completing the license application for operation justifying this alternative for waste disposal over other alternatives. Reasons that might be considered acceptable might include the need to dispose of large volumes of low activity waste that would otherwise take up valuable space in commercial sites; the ability to demonstrate that this method of disposal will result in reduced exposures to the public; the ability to show that the prohibitive costs of other methods of disposal would be detrimental to the progress of significant research which generates radioactive waste. 19 refs., 3 figs., 4 tabs

  20. Joint federal initiative for demonstration of on-site innovative technologies

    The Federal Government needs to develop and implement new technologies to support its environmental and waste management programs. The incentive is threefold: First, new technologies are needed to accomplish many cleanup and waste management tasks. Second, the development and implementation of new technologies is expected to reduce significantly total cleanup costs. Third, the development of new environmental technologies can help secure national economic advantages by making U.S. industry more competitive in terms of global environmental markets. The Federal Advisory Committee to Develop On-Site Innovative Technologies (DOIT) initiative reinvents inter-governmental relations by stressing the solving of environmental problems through partnerships rather than through confrontation. This overview -- which is essentially a shortened and slightly modified version of the recent Coordinating Group Report to the DOIT Committee --describes the waste management challenges facing the Nation, discusses the innovative solutions offered by DOIT, outlines progress of the initiative to date, and identifies critical next steps

  1. Novel On-Site Cupric Oxide Recovery Process from Waste Containing Copper

    Kobayashi, Takuya; Kano, Kazunori; Suzuki, Toshihiro; Kobayashi, Atsushi

    2013-05-01

    Although the copper-containing waste from semiconductor or printed circuit board (PCB) manufacturing contains a high concentration of copper, it is usually transported and treated outside of the factories. We studied a novel treatment technology for on-site recycling in the factories. In this technology, cupric oxide with a low-chloride-content was obtained from waste with a high copper concentration, such as cupric chloride etchant waste and cupric sulfate plating waste. In the proposed method, copper-containing waste mixed with H2O2 solution is added to NaOH solution by stepwise addition. In laboratory experiments, we optimized the reaction conditions and obtained low-chloride-content CuO from actual cupric chloride etchant waste and cupric sulfate plating waste. Based on the laboratory experiments, we constructed the first practical plant at a PCB factory and obtained low-chloride-content CuO.

  2. Corrosion rate of steel in concrete - Evaluation of confinement techniques for on-site corrosion rate

    Nygaard, Peter Vagn; Geiker, Mette Rica; Elsener, Bernhard

    2009-01-01

    Earlier on-site investigations and laboratory studies have shown that varying corrosion rates are obtained when different commercially available instruments are used. The different confinement techniques, rather than the different electrochemical techniques used in the instruments, are considered...... to be the main reason for the discrepancies. This paper presents a method for the quantitative assessment of confinement techniques based on monitoring the operation of the corrosion rate instrument and the current distribution between the electrode assembly on the concrete surface and a segmented...... reinforcement bar embedded in the concrete. The applicability of the method was demonstrated on two commercially available corrosion rate instruments based on different confinement techniques. The method provided an explanation of the differences in performance of the two instruments. Correlated measurements of...

  3. Revaluation of breast cytology with pathologist on-site of lesions with suspicious sonographic features

    Capalbo, Emanuela, E-mail: emanuelacapalbo@tiscalinet.it [Scuola di Specializzazione di Radiologia Diagnostica ed Interventistica, Università degli Studi di Milano Via Di Rudinì, Milano, 20142 Italy (Italy); Sajadidehkordi, Farideh, E-mail: faridehit@yahoo.it [Scuola di Specializzazione di Radiologia Diagnostica ed Interventistica, Università degli Studi di Milano Via Di Rudinì, Milano, 20142 Italy (Italy); Colombi, Claudio; Ticha, Vladimira; Moretti, Angela, E-mail: info.radiologia@sancarlo.mi.it [Dipartimento di Scienze Diagnostiche, UOC di Radiologia Diagnostica ed Interventistica, A.O San Carlo Borromeo. Via Pio II, 3, 20153 Milano (Italy); Peli, Michela, E-mail: peli.michela@gmail.com [Scuola di Specializzazione di Radiologia Diagnostica ed Interventistica, Università degli Studi di Milano Via Di Rudinì, Milano, 20142 Italy (Italy); Cosentino, Maria, E-mail: maria-cosentino@tiscali.it [Scuola di Specializzazione di Radiologia Diagnostica ed Interventistica, Università degli Studi di Milano Via Di Rudinì, Milano, 20142 Italy (Italy); Lovisatti, Maria, E-mail: marialovisatti@hotmail.com [Scuola di Specializzazione di Radiologia Diagnostica ed Interventistica, Università degli Studi di Milano Via Di Rudinì, Milano, 20142 Italy (Italy); Berti, Elisabetta, E-mail: eliberti@hotmail.it [Dipartimento di Scienze Diagnostiche, UOC di Anatomia Patologica, A.O San Carlo Borromeo. Via Pio II, 3, Milano 20153 (Italy); Cariati, Maurizio, E-mail: info.radiologia@sancarlo.mi.it [Dipartimento di Scienze Diagnostiche, UOC di Radiologia Diagnostica ed Interventistica, A.O San Carlo Borromeo. Via Pio II, 3, 20153 Milano (Italy)

    2013-09-15

    Objective: Evaluating correlation estimation between diagnostic ultrasound (U.S.) of breast lesions and fine needle aspiration cytology (FNAC), and the correlation between cytology and histology (I) of these lesions undergo surgery. Materials and methods: In 2010 we performed 1589 ultrasound breast. We identified 210 suspicious lesions to be subjected to FNAC, which was performed with pathologist on site, and extemporaneous analysis of the sample to assess their appropriateness. We classified the lesions in 5 ultrasound (U) classes according to the criteria defined by Echographic BIRADS Lexicon. The results of cytology were classified in 5 classes (C) according to the guidelines of F.O.N.Ca.M. Then we evaluated the diagnostic correlation between U.S. and FNAC, and between FNAC and Histology. Results: The distribution of lesions in U classes was: 57U2, 55U3, 36U4 and 62U5. The diagnostic concordance between U and FNAC was 96.7%, with a sensitivity of 98%, specificity 93%, negative and positive predictive value respectively of 94.9% and 97.3%, and diagnostic accuracy of 96.6%. The 98 patients with C4-C5 lesions were subjected to surgery and the histology confirmed high-grade malignancy of lesions with a concordance of 99.7%. Conclusions: Having achieved high diagnostic concordance between U and FNAC, and then between FNAC and histology, we may say that the FNAC, less invasive and traumatic for the patient than needle biopsy (CB), may be still a valid method when performed with pathologist on-site to assess the adequacy of the sample taken.

  4. On-site characterization and verification for removal of cesium contamination along an active rail spur

    A rapid, cost-effective sampling and analysis approach was used to conduct on-site analysis of soil and ballast for 137Cs contamination along an active rail spur in Oak Ridge, Tennessee. Savings in time and analytical costs were realized for both the characterization and cleanup phases of this project. For characterization, a procedure was developed to conduct gamma-logging of shallow boreholes. Portable gamma radiation survey instruments consisting of a 5- by 5-cm NaI detector coupled to a digital ratemeter/scaler with a single-channel analyzer were calibrated to a 137Cs source, then used for both surface and subsurface gamma radiation surveys. A correlation was made between the direct radiation measurements and 137Cs concentrations in surface and subsurface soil and ballast. Borehole logs of gamma-ray activity as a function of depth were used to estimate vertical profiles of the subsurface distribution of 137Cs. Information from these surveys was used to develop accurate 3-dimensional isopleths of contaminated areas, including estimates of waste volumes. After a remedial alternative was selected, on-site analytical methods were again used to verify that the cleanup level was achieved. Samples from excavated areas were analyzed for 137Cs by comparative gamma-ray counting using a multi-channel pulse height analyzer and a 3-in. diameter by 2-in. thick NaI crystal. The counting system was housed in a mobile field laboratory. To better direct ongoing excavation, a correlation factor between samples analyzed by gamma spectroscopy and measurements made by field instruments was determined. In both the characterization and the cleanup phases, sample results were verified by independent off-site laboratory analyses

  5. 77 FR 62535 - Hydro Aluminum North America, Inc., Midwest Region, Including On-Site Leased Workers From...

    2012-10-15

    ... Employment and Training Administration Hydro Aluminum North America, Inc., Midwest Region, Including On- Site Leased Workers From Employment Group, Aerotek, and Manpower, Kalamazoo, Michigan; Hydro Aluminum North... and former workers of Hydro Aluminum North America, Inc., Kalamazoo, Michigan. The subject...

  6. On-site investigations of hydrocarbon contaminated soil by the Pollut-Eval methodology

    lack of sample pre-treatment and the adaptation of a cooled auto-sampler, short time analysis suited for light petroleum pollutant such as gasoline and kerosene. The simple protocol applied to the soil appeared rapidly suitable for keeping the track of depollution process efficiency. During its qualification, the analyser has been involved in rehabilitation process evaluation by analysing various contaminated soils before and after clean-up treatment. From 1999, IFP was frequently asked for on-site diagnosis involving Pollut-Eval methodology. So, IFP installed this lab equipment in a mobile van in order to qualify the methodology through real time and on-site diagnosis. In addition to the qualification program, the aim of the project was also to identify the analytical parameters available in the method and sufficient for field contaminated soil characterisation. During 2 years, all over France, IFP, Gester and Vinci Technologies gathered their effort to ensure 10-site diagnosis. The variety of pollutants encountered has enriched a data base that has been included in a user guide. The gathered experience ended by the design of a compact apparatus dedicated to field analyses. Its small size and weight (less than 20 kg) was designed to perform on-site and autonomous characterisations. (authors)

  7. Lead-cooled fast reactor (BREST) with an on-site fuel cycle

    Full text: Out of a great many of new power technologies, fission nuclear power is the only realistic way to stop the growth in extraction and combustion of fossil fuel. However, this is something to be achieved only through the nuclear power to have by the mid-21st century the capacity an order of magnitude as high as the current level. Nuclear power of such a scale will necessitate a new nuclear technology which is required to provide: transition to power with unlimited fuel resources; economically competitive nuclear power through reducing the cost of building and operating NPPs of a high inherent safety level with highly efficient utilization of fuel and generated heat; elimination of severe accidents with radioactive release which require evacuation of population, to be achieved primarily through combining inherent safety, passive protection features and impossible loss of lead coolant; an environmentally safe closed fuel cycle with in-pile combustion of minor actinides and radiation-equivalent disposal of radioactive waste; creation of nuclear proliferation barriers by way of eliminating uranium enrichment and plutonium separation facilities. These problems are solved in the BREST lead-cooled fast reactor. The initial stage plan is to build an NPP with a demonstration reactor and an on-site fuel cycle to verify designs, try out processes involving lead using as the coolant and study the behavior of the reactor and its systems and components in different modes, including resistance to anticipated operational occurrences and accidents simulated on the reactor. This will be followed by a rapid transition to a fast lead-cooled power reactor of 1200 MW(e) featuring two- circuit heat removal from the core to the turbine with supercritical steam parameters. The state of the activities to develop the NPP with lead-cooled fast reactors and an on-site fuel cycle is presented. A core with a moderate power rating has been considered. This will have a uranium

  8. A P-wave based, on-site method for Earthquake Early Warning

    Zollo, Aldo

    2016-04-01

    Can we rapidly predict the potential damage of earthquakes by-passing the estimation of its location and magnitude? One possible approach is to predict the expected peak ground shaking at the site and the earthquake magnitude from the initial P-peak amplitude and characteristic period, respectively. The idea, first developed by Wu and Kanamori (2005), is to combine the two parameters for declaring the alert once the real-time measured quantities have passed pre-defined thresholds. Our proposed on-site early warning method generalized this approach, based on the analysis of strong motion data from modern accelerograph networks in Japan, Taiwan and Italy (Zollo et al., 2010). It is based on the real-time measurement of the period (τc) and peak displacement (Pd) parameters at one or more co-located stations at a given target site to be protected against the earthquake effects. By converting these real-time proxies in predicted values of Peak Ground Velocity (PGV) or instrumental intensity (IMM) and magnitude, an alert level is issued at the recording site based on a decisional table with four entries defined upon threshold values of the parameters Pd and Tc. The latter ones are set according to the error bounds estimated on the derived prediction equations. A near-source network of stations running the onsite method can provide the event location and transmit the information about the alert levels recorded at near-source stations to more distant sites, before the arrival of the most destructive phase. The network-based approach allows for the rapid and robust estimation of the Potential Damage Zone (PDZ), that is the area where most of earthquake damage is expected (Colombelli et al., 2012). A new strategy for a P-wave based, on-site earthquake early warning system has been developed and tested on Japanese strong motion data and under testing on Italian data. The key elements are the real-time, continuous measurement of three peak amplitude parameters and their

  9. Cocaine and benzoylecgonine oral fluid on-site screening and confirmation.

    Ellefsen, Kayla N; Concheiro, Marta; Pirard, Sandrine; Gorelick, David A; Huestis, Marilyn A

    2016-03-01

    Accurate on-site devices to screen for drug intake are critical for establishing whether an individual is driving under the influence of drugs (DUID); however, on-site oral fluid (OF) cocaine device performance is variable. We evaluated the performance of a newly developed benzoylecgonine (BE) test-strip for the Draeger® DrugTest 5000 device (20 µg/L cut-off) with equivalent cross reactivity for cocaine and BE. Ten cocaine users provided OF, collected with the Draeger cassette and Oral-Eze® and StatSure Saliva Sampler(TM) devices, up to 69 h following 25 mg intravenous cocaine administration. All screening results were confirmed by a validated two-dimensional-gas chromatography-mass spectrometry (2D-GC-MS) method for cocaine and/or BE. Cocaine test-strip median Tlast for screening only results was 6.5 h, and 6.5 h with Oral-Eze® and 4 h for StatSure OF confirmation for cocaine and/or BE at 1, 8, and 10 µg/L; sensitivity, specificity, and efficiency ranged from 85.5 to 100% and 83.3 to 100% for cocaine only confirmation at 8 and 10 µg/L. For the BE test-strip, median Tlast was 12.5 h for screening only and confirmation for cocaine and/or BE at all three cut-offs; sensitivity, specificity, and efficiency ranged from 85.5 to 97.5% and 78.4 to 97.4% with cocaine and/or BE confirmation at 8 and 10 µg/L cut-offs, respectively. The Draeger cocaine test-strip with cocaine only confirmation offers a useful option for monitoring the acute intoxication phase of DUID; additionally the BE test-strip with cocaine and/or BE confirmation increases the length of detection of cocaine intake for workplace drug testing, drug court, parole, pain management, drug treatment programs and both the acute cocaine intoxication and cocaine crash/fatigue phase of DUID. Copyright © 2016 John Wiley & Sons, Ltd. PMID:26968560

  10. Stormwater Management Criteria for On-Site Pollution Control: A Comparative Assessment of International Practices

    Sage, Jérémie; Berthier, Emmanuel; Gromaire, Marie-Christine

    2015-07-01

    Over the last decade, a growing interest has been shown toward innovative stormwater management practices, breaking away from conventional "end of pipe" approaches (based on conveying water offsite to centralized detention facilities). Innovative strategies, referred to as sustainable urban drainage systems, low impact development (LID) or green infrastructures, advocating for management of runoff as close to its origin as possible, have therefore gained a lot of popularity among practitioners and public authorities. However, while the need for pollution control is generally well accepted, there is no wide agreement about management criteria to be given to developers. This article hence aims to compare these criteria through literature analysis of different state or local stormwater management manuals or guidelines, investigating both their suitability for pollution control and their influence on best management practices selection and design. Four categories of criteria were identified: flow-rate limitations, "water quality volumes" (to be treated), volume reduction (through infiltration or evapotranspiration), and non-hydrologic criteria (such as loads reduction targets or maximum effluent concentrations). This study suggests that hydrologic criteria based on volume reduction (rather than treatment) might generally be preferable for on-site control of diffuse stormwater pollution. Nonetheless, determination of an appropriate management approach for a specific site is generally not straightforward and presents a variety of challenges for site designers seeking to satisfy local requirements in addressing stormwater quantity and quality issues. The adoption of efficient LID solution may therefore strongly depend on the guidance given to practitioners to account for these management criteria.

  11. The Cherenkov Telescope Array On-Site integral sensitivity: observing the Crab

    Fioretti, Valentina; Schussler, Fabian

    2016-01-01

    The Cherenkov Telescope Array (CTA) is the future large observatory in the very high energy (VHE) domain. Operating from 20 GeV to 300 TeV, it will be composed of tens of Imaging Air Cherenkov Telescopes (IACTs) displaced in a large area of a few square kilometers in both the southern and northern hemispheres. The CTA/DATA On-Site Analysis (OSA) is the system devoted to the development of dedicated pipelines and algorithms to be used at the CTA site for the reconstruction, data quality monitoring, science monitoring and realtime science alerting during observations. The OSA integral sensitivity is computed here for the most studied source at Gamma-rays, the Crab Nebula, for a set of exposures ranging from 1000 seconds to 50 hours, using the full CTA Southern array. The reason for the Crab Nebula selection as the first example of OSA integral sensitivity is twofold: (i) this source is characterized by a broad spectrum covering the entire CTA energy range; (ii) it represents, at the time of writing, the standar...

  12. Visual Sample Plan (VSP) Statistical Software as Related to the CTBTO's On-Site Inspection Procedure

    In the event of a potential nuclear weapons test the Comprehensive Nuclear-Test-Ban Treaty Organization (CTBTO) is commissioned to conduct an on-site investigation (OSI) of the suspected test site in an effort to find confirmatory evidence of the nuclear test. The OSI activities include collecting air, surface soil, and underground samples to search for indications of a nuclear weapons test - these indicators include radionuclides and radioactive isotopes Ar and Xe. This report investigates the capability of the Visual Sample Plan (VSP) software to contribute to the sampling activities of the CTBTO during an OSI. VSP is a statistical sampling design software, constructed under data quality objectives, which has been adapted for environmental remediation and contamination detection problems for the EPA, US Army, DoD and DHS among others. This report provides discussion of a number of VSP sample designs, which may be pertinent to the work undertaken during an OSI. Examples and descriptions of such designs include hot spot sampling, combined random and judgment sampling, multiple increment sampling, radiological transect surveying, and a brief description of other potentially applicable sampling methods. Further, this work highlights a potential need for the use of statistically based sample designs in OSI activities. The use of such designs may enable canvassing a sample area without full sampling, provide a measure of confidence that radionuclides are not present, and allow investigators to refocus resources in other areas of concern.

  13. Stormwater management criteria for on-site pollution control: a comparative assessment of international practices.

    Sage, Jérémie; Berthier, Emmanuel; Gromaire, Marie-Christine

    2015-07-01

    Over the last decade, a growing interest has been shown toward innovative stormwater management practices, breaking away from conventional "end of pipe" approaches (based on conveying water offsite to centralized detention facilities). Innovative strategies, referred to as sustainable urban drainage systems, low impact development (LID) or green infrastructures, advocating for management of runoff as close to its origin as possible, have therefore gained a lot of popularity among practitioners and public authorities. However, while the need for pollution control is generally well accepted, there is no wide agreement about management criteria to be given to developers. This article hence aims to compare these criteria through literature analysis of different state or local stormwater management manuals or guidelines, investigating both their suitability for pollution control and their influence on best management practices selection and design. Four categories of criteria were identified: flow-rate limitations, "water quality volumes" (to be treated), volume reduction (through infiltration or evapotranspiration), and non-hydrologic criteria (such as loads reduction targets or maximum effluent concentrations). This study suggests that hydrologic criteria based on volume reduction (rather than treatment) might generally be preferable for on-site control of diffuse stormwater pollution. Nonetheless, determination of an appropriate management approach for a specific site is generally not straightforward and presents a variety of challenges for site designers seeking to satisfy local requirements in addressing stormwater quantity and quality issues. The adoption of efficient LID solution may therefore strongly depend on the guidance given to practitioners to account for these management criteria. PMID:25855072

  14. On-site laboratory support of Oak Ridge National Laboratory environmental restoration field activities

    A remedial investigation/feasibility study has been undertaken at Oak Ridge National Laboratory (ORNL). Bechtel National, Inc. and partners CH2M Hill, Ogden Environmental and Energy Services, and PEER Consultants are contracted to Lockheed Martin Energy Systems, performing this work for ORNL's Environmental Restoration (ER) Program. An on-site Close Support Laboratory (CSL) established at the ER Field Operations Facility has evolved into a laboratory where quality analytical screening results can be provided rapidly (e.g., within 24 hours of sampling). CSL capabilities include three basic areas: radiochemistry, chromatography, and wet chemistry. Radiochemical analyses include gamma spectroscopy, tritium and carbon-14 screens using liquid scintillation analysis, and gross alpha and beta counting. Cerenkov counting and crown-ether-based separation are the two rapid methods used for radiostrontium determination in water samples. By extending count times where appropriate, method detection limits can match those achieved by off-site contract laboratories. Volatile organic compounds are detected by means of gas chromatography using either headspace or purge and trap sample introduction (based on EPA 601/602). Ionic content of water samples is determined using ion chromatography and alkalinity measurement. Ion chromatography is used to quantify both anions (based on EPA 300) and cations. Wet chemistry procedures performed at the CSL include alkalinity, pH (water and soil), soil resistivity, and dissolved/suspended solids. Besides environmental samples, the CSL routinely screens health and safety and waste management samples. The cost savings of the CSL are both direct and indirect

  15. Influence of Palythoa caribaeorum (Anthozoa, Cnidaria) zonation on site-attached reef fishes.

    Mendonça-Neto, José P; Ferreira, Carlos E L; Chaves, Laís C T; Pereira, Renato C

    2008-09-01

    This work aimed to test the influence of Palythoa caribeorum, a widely distributed zoanthid in the Atlantic, on site-attached reef fish in a subtropical rocky shore. Density, richness and vertical distribution of reef fish inside (ID) and outside (OD) previously chosen P. caribaeorum dominance patches were compared through stationary visual censuses along three different periods. Fishes were grouped in different trophic guilds to evidence differences in resources uses in both treatments. A complexity index was estimated by the chain link method and percentage covering of benthic organisms was obtained analyzing random points from replicated photo-quadrats. We observed thirty-eight species of fishes, belonging to twenty-five families. Reef fish communities between studied patches were similar,both in terms of species composition and vertical distribution. Considering only the most site-attached fishes, which were the most frequent and abundant species, data showed that ID sustains higher diversity and abundance than OD. Results showed that benthic composition differ significantly among patches whereas complexity remained without differences. Otherwise, results indicated that these areas might play an important role in space limitation, structuring neighboring benthic community and consequently reef fish assemblages. PMID:18797801

  16. Single house on-site grey water treatment using a submerged membrane bioreactor for toilet flushing.

    Fountoulakis, M S; Markakis, N; Petousi, I; Manios, T

    2016-05-01

    Wastewater recycling has been and continues to be practiced all over the world for a variety of reasons including: increasing water availability, combating water shortages and drought, and supporting environmental and public health protection. Nowadays, one of the most interesting issues for wastewater recycling is the on-site treatment and reuse of grey water. During this study the efficiency of a compact Submerged Membrane Bioreactor (SMBR) system to treat real grey water in a single house in Crete, Greece, was examined. In the study, grey water was collected from a bathtub, shower and washing machine containing significant amounts of organic matter and pathogens. Chemical oxygen demand (COD) removal in the system was approximately 87%. Total suspended solids (TSS) were reduced from 95mgL(-1) in the influent to 8mgL(-1) in the effluent. The efficiency of the system to reduce anionic surfactants was about 80%. Fecal and total coliforms decreased significantly using the SMBR system due to rejection, by the membrane, used in the study. Overall, the SMBR treatment produces average effluent values that would satisfy international guidelines for indoor reuse applications such as toilet flushing. PMID:26901745

  17. On-site monitoring of fish spoilage using vanadium pentoxide xerogel modified interdigitated gold electrodes

    Helali, S.; Abdelghani, A. [Unite de Recherche de Physique des Semiconducteurs et Capteurs, IPEST (Tunisia); Jaffrezic-Renault, N. [Laboratoire de Sciences Analytiques, Universite de Claude Bernard, Lyon (France); Trikalitis, P.N. [Department of Chemistry, University of Crete, 71 003, Heraklion Crete (Greece); Efstathiou, C.E. [Department of Chemistry, University of Athens, 157 71, Athens (Greece); Prodromidis, M.I., E-mail: mprodrom@cc.uoi.g [Department of Chemistry, University of Ioannina, 45 110, Ioannina (Greece)

    2010-05-30

    The development of a vanadium pentoxide xerogel (VXG)-based sensor for the detection of volatile inorganic (ammonia) and organic (dimethylamine, etc.) amines is described. The xerogel film was deposited on interdigitated gold electrodes by dip-coating using an aqueous solution of VXG. The morphology of the sensing layer, its interaction with ammonia, which was used as a model analyte throughout this work, as well as the regeneration of the surface of the sensor electrodes with vapors of HCl were examined with scanning electron microscopy and FTIR spectroscopy. Signal changes, due to changes of the RC-product of the electrochemical cell (Au-VXG-Au), as a result of its interactions with ammonia vapors, were probed with a portable, homemade charge meter, the Multipulser. Exposing the sensor electrodes to various concentrations of ammonia vapors resulted in proportional changes in the signal output. Finally, the proposed sensors were successfully used for on-site, real-time monitoring of fish spoilage in ambient conditions.

  18. [Research progress on site-oriented and three-dimensional immobilization of proteins].

    Wang, C; Feng, B

    2015-01-01

    In today's post-genome era, the goals of research are geared toward understanding the meaning of information in sequenced DNA, namely, understanding the functional characteristics of proteins encoded by genomes of living beings. Protein array technologies, particularly miniaturized high-throughput platforms such as micro- or nano-fluidic chips that allow the parallel detection of thousands of proteins simultaneously, are playing increasing important roles as discovery tools in proteomics. These technologies are based on principles of molecular recognition and consist of a support surface, such as a glass slide, bead, or microtiter plate, to which an array of captured proteins is bound. However, immobilized proteins often lose their immunoactivity and suffer from low surface density, which results in inefficient signal response. In this review, we mainly provide an introduction about the research progress on site-oriented adsorption of protein at solid-liquid interfaces, especially the three-dimensional immobilization of protein, whose objective is to retain immobilized proteins in an active state at great density. PMID:25916107

  19. Application of On-Site Wastewater Treatment in Ireland and Perspectives on Its Sustainability

    Donata Dubber

    2014-03-01

    Full Text Available The wastewater of one third of Ireland’s population is treated on-site using domestic treatment systems (DWWTSs that usually consist of a septic tank and soil attenuation system. Within the past four years, the legislative framework for these systems has undergone a major change with a registration and inspection regime being introduced to identify legacy sites that will require remediation work, particularly in areas of the country underlain by subsoils of very low permeability. Against this background this study aims to assess the overall sustainability of existing DWWTSs as well as alternative treatment and disposal options. The results show that main CO2eq emissions are from the methane production in septic tanks. The reduced methane production in mechanically aerated secondary treatment systems was found to counterbalance the related emissions due to the additional energy requirements. In contrast, septic tank systems have the lowest construction and operational costs representing the most economically sustainable solution. Pressurised disposal systems are slightly more expensive but have the potential to reduce environmental impact on surface water and reduce greenhouse gas emissions. Clustered decentralised treatment solutions could be environmentally and economically sustainable but ownership, management and related financial and legal issues will need to be addressed and developed.

  20. Training of medical teams on-site for individual and coordinated response in emergency management

    Andersen, Verner

    2003-01-01

    A system for training of coordination and cooperation of decision makers in emergency management has been under construction for some time. A first prototype of the system was developed in the MUSTER system. The system is being developed modularly with one module for each of the suborganisations ...... system for specific training set-ups for specific groups of trainees. The first module completed as a commercial system, "Training of medical teams on site", will be presented.......A system for training of coordination and cooperation of decision makers in emergency management has been under construction for some time. A first prototype of the system was developed in the MUSTER system. The system is being developed modularly with one module for each of the suborganisations...... involved in the complete preparedness: fire brigade, police, medical team, civil defence, etc. All these modules will in the end be integrated on a common integration platform, either to a fully-fledged system covering all aspects of training for the complete preparedness, or for creating a dedicated...

  1. An Explosion Aftershock Model with Application to On-Site Inspection

    Ford, Sean R.; Labak, Peter

    2016-01-01

    An estimate of aftershock activity due to a theoretical underground nuclear explosion is produced using an aftershock rate model. The model is developed with data from the Nevada National Security Site, formerly known as the Nevada Test Site, and the Semipalatinsk Test Site, which we take to represent soft-rock and hard-rock testing environments, respectively. Estimates of expected magnitude and number of aftershocks are calculated using the models for different testing and inspection scenarios. These estimates can help inform the Seismic Aftershock Monitoring System (SAMS) deployment in a potential Comprehensive Test Ban Treaty On-Site Inspection (OSI), by giving the OSI team a probabilistic assessment of potential aftershocks in the Inspection Area (IA). The aftershock assessment, combined with an estimate of the background seismicity in the IA and an empirically derived map of threshold magnitude for the SAMS network, could aid the OSI team in reporting. We apply the hard-rock model to a M5 event and combine it with the very sensitive detection threshold for OSI sensors to show that tens of events per day are expected up to a month after an explosion measured several kilometers away.

  2. A C. elegans-based foam for rapid on-site detection of residual live virus.

    Negrete, Oscar A.; Branda, Catherine; Hardesty, Jasper O. E. (Sandia National Laboratories, Albuquerque, NM); Tucker, Mark David (Sandia National Laboratories, Albuquerque, NM); Kaiser, Julia N. (Global Product Management, Hilden, Germany); Kozina, Carol L.; Chirica, Gabriela S.

    2012-02-01

    In the response to and recovery from a critical homeland security event involving deliberate or accidental release of biological agents, initial decontamination efforts are necessarily followed by tests for the presence of residual live virus or bacteria. Such 'clearance sampling' should be rapid and accurate, to inform decision makers as they take appropriate action to ensure the safety of the public and of operational personnel. However, the current protocol for clearance sampling is extremely time-intensive and costly, and requires significant amounts of laboratory space and capacity. Detection of residual live virus is particularly problematic and time-consuming, as it requires evaluation of replication potential within a eukaryotic host such as chicken embryos. The intention of this project was to develop a new method for clearance sampling, by leveraging Sandia's expertise in the biological and material sciences in order to create a C. elegans-based foam that could be applied directly to the entire contaminated area for quick and accurate detection of any and all residual live virus by means of a fluorescent signal. Such a novel technology for rapid, on-site detection of live virus would greatly interest the DHS, DoD, and EPA, and hold broad commercial potential, especially with regard to the transportation industry.

  3. Oxygen profile and clogging in vertical flow sand filters for on-site wastewater treatment.

    Petitjean, A; Forquet, N; Boutin, C

    2016-04-01

    13 million people (about 20% of the population) use on-site wastewater treatment in France. Buried vertical sand filters are often built, especially when the soil permeability is not sufficient for septic tank effluent infiltration in undisturbed soil. Clogging is one of the main problems deteriorating the operation of vertical flow filters for wastewater treatment. The extent of clogging is not easily assessed, especially in buried vertical flow sand filters. We suggest examining two possible ways of detecting early clogging: (1) NH4-N/NO3-N outlet concentration ratio, and (2) oxygen measurement within the porous media. Two pilot-scale filters were equipped with probes for oxygen concentration measurements and samples were taken at different depths for pollutant characterization. Influent and effluent grab-samples were taken three times a week. The systems were operated using batch-feeding of septic tank effluent. Qualitative description of oxygen transfer processes under unclogged and clogged conditions is presented. NH4-N outlet concentration appears to be useless for early clogging detection. However, NO3-N outlet concentration and oxygen content allows us to diagnose the early clogging of the system. PMID:26775157

  4. Testing in support of on-site storage of residues in the Pipe Overpack Container

    The disposition of the large back-log of plutonium residues at the Rocky Flats Environmental Technology Site (Rocky Flats) will require interim storage and subsequent shipment to a waste repository. Current plans call for disposal at the Waste Isolation Pilot Plant (WIPP) and the transportation to WIPP in the TRUPACT-II. The transportation phase will require the residues to be packaged in a container that is more robust than a standard 55-gallon waste drum. Rocky Flats has designed the Pipe Overpack Container to meet this need. It is desirable to use this same waste packaging for interim on-site storage in non-hardened buildings. To meet the safety concerns for this storage the Pipe Overpack Container has been subjected to a series of tests at Sandia National Laboratories in Albuquerque, New Mexico. In addition to the tests required to qualify the Pipe Overpack Container as a waste container for shipment in the TRUPACT-II several tests were performed solely for the purpose of qualifying the container for interim storage. This report will describe these tests and the packages response to the tests. 12 figs., 3 tabs

  5. BIPM direct on-site Josephson voltage standard comparisons: 20 years of results

    The discovery of the Josephson effect has for the first time given national metrology institutes (NMIs) the possibility of maintaining voltage references which are stable in time. In addition, the introduction in 1990 of a conventional value for the Josephson constant, KJ-90, has greatly improved world-wide consistency among representations of the volt. For 20 years, the Bureau International des Poids et Mesures (BIPM) has conducted an ongoing, direct, on-site key comparison of Josephson voltage standards among NMIs under the denominations BIPM.EM-K10.a (1 V) and BIPM.EM-K10.b (10 V) in the framework of the mutual recognition arrangement (CIPM MRA). The results of 41 comparisons illustrate the consistency among primary voltage standards and have demonstrated that a relative total uncertainty of a few parts in 1010 is achievable if a few precautions are taken with regard to the measurement set-up. Of particular importance are the grounding, efficient filters and high insulation resistance of the measurement leads, and clean microwave distribution along the propagation line to the Josephson array. This paper reviews the comparison scheme and technical issues that need to be taken into account to achieve a relative uncertainty at the level of a few parts in 1010 or even a few parts in 1011 in the best cases. (paper)

  6. Investigation of the optimum on-site storage option of HIC packed with dried spent resin

    In order to treat spent resin, Youngkwang NPP has introduced a Spent Resin Drying(SRDS) of which volume reduction ratio is much higher than that of cementation process. However High Integrity Container(HIC), which is used for the packaging of dried spent resin from SRDS, has larger size and much higher radioactivity than those of the present 55gal drum. Therefore, the modification of drum handling devices and drum storage facilities, and new drum handling procedure may be required. In order to determine the optimum option for the on-site storage of the HIC at Youngkwang NPP site, the yearly generation amount of the spent resin and it's surface dose rate have been investigated. And the current system used for drum handling and storage, and basic requirements for the storage of HIC have been also investigated. The yearly amount of HIC generated from Youngkwang NPP site is expected to be 18. The highest surface dose rate of HIC is anticipated to be about 60R/h. From the Investigated results, three options for the storage of HIC was suggested. Among the three options, the sequential storage option has been selected as the most realistic option for the storage of HIC. Finally radiation safety analysis result for the optimum option showed that outside surface dose rate of the two storage facilities would meet the requirement of 0.5 mR/h

  7. Distributed Energy Resources On-Site Optimization for Commercial Buildings with Electric and Thermal Storage Technologies

    The addition of storage technologies such as flow batteries, conventional batteries, and heat storage can improve the economic as well as environmental attractiveness of on-site generation (e.g., PV, fuel cells, reciprocating engines or microturbines operating with or without CHP) and contribute to enhanced demand response. In order to examine the impact of storage technologies on demand response and carbon emissions, a microgrid's distributed energy resources (DER) adoption problem is formulated as a mixed-integer linear program that has the minimization of annual energy costs as its objective function. By implementing this approach in the General Algebraic Modeling System (GAMS), the problem is solved for a given test year at representative customer sites, such as schools and nursing homes, to obtain not only the level of technology investment, but also the optimal hourly operating schedules. This paper focuses on analysis of storage technologies in DER optimization on a building level, with example applications for commercial buildings. Preliminary analysis indicates that storage technologies respond effectively to time-varying electricity prices, i.e., by charging batteries during periods of low electricity prices and discharging them during peak hours. The results also indicate that storage technologies significantly alter the residual load profile, which can contribute to lower carbon emissions depending on the test site, its load profile, and its adopted DER technologies

  8. PORTSMOUTH ON-SITE DISPOSAL CELL HIGH DENSITY POLYETHYLENE GEOMEMBRANE LONGEVITY

    Phifer, M.

    2012-01-31

    It is anticipated that high density polyethylene (HDPE) geomembranes will be utilized within the liner and closure cap of the proposed On-Site Disposal Cell (OSDC) at the Portsmouth Gaseous Diffusion Plant. The likely longevity (i.e. service life) of HDPE geomembranes in OSDC service is evaluated within the following sections of this report: (1) Section 2.0 provides an overview of HDPE geomembranes, (2) Section 3.0 outlines potential HDPE geomembranes degradation mechanisms, (3) Section 4.0 evaluates the applicability of HDPE geomembrane degradation mechanisms to the Portsmouth OSDC, (4) Section 5.0 provides a discussion of the current state of knowledge relative to the longevity (service life) of HDPE geomembranes, including the relation of this knowledge to the Portsmouth OSDC, and (5) Section 6.0 provides summary and conclusions relative to the anticipated service life of HDPE geomembranes in OSDC service. Based upon this evaluation it is anticipated that the service life of HDPE geomembranes in OSDC service would be significantly greater than the 200 year service life assumed for the OSDC closure cap and liner HDPE geomembranes. That is, a 200 year OSDC HDPE geomembrane service life is considered a conservative assumption.

  9. OSIRIS—Gamma-ray spectroscopy software for on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty

    Caffrey, A.J., E-mail: Gus.Caffrey@inl.gov [Idaho National Laboratory, Idaho Falls, ID (United States); Bowyer, T.W. [Pacific Northwest National Laboratory, Richland, WA (United States); Egger, A.E. [Idaho National Laboratory, Idaho Falls, ID (United States); Hall, J.C. [Pacific Northwest National Laboratory, Richland, WA (United States); Kelly, S.M.; Krebs, K.M. [Idaho National Laboratory, Idaho Falls, ID (United States); Kreek, S.A. [Lawrence Livermore National Laboratory, Livermore, CA (United States); Jordan, D.V.; Milbrath, B.D. [Pacific Northwest National Laboratory, Richland, WA (United States); Padgett, S.W. [Lawrence Livermore National Laboratory, Livermore, CA (United States); Wharton, C.J. [Idaho National Laboratory, Idaho Falls, ID (United States); Wimer, N.G. [Lawrence Livermore National Laboratory, Livermore, CA (United States)

    2015-06-01

    We have designed and tested software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy—OSIRIS—software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,{sup 131}I. A set of over 100 fission-product spectra was employed for OSIRIS testing. These spectra were measured where possible, or generated by modeling. The test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, OSIRIS correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.

  10. OSIRIS—Gamma-ray spectroscopy software for on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty

    We have designed and tested software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy—OSIRIS—software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,131I. A set of over 100 fission-product spectra was employed for OSIRIS testing. These spectra were measured where possible, or generated by modeling. The test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, OSIRIS correctly identifies CTBT-relevant fission product isotopes at the 95% level or better

  11. Oscillating multidromion excitations in higher-dimensional nonlinear lattice with intersite and external on-site potentials using symbolic computation

    We show by an extensive method of quasi-discrete multiple-scale approximation that nonlinear multi-dimensional lattice waves subjected to intersite and external on-site potentials are found to be governed by (N + 1)-dimensional nonlinear Schrödinger (NLS) equation. In particular, the resonant mode interaction of (2+1)-dimensional NLS equation has been identified and the theory allows the inclusion of transverse effect. We apply the exponential function method to the (2+1)-dimensional NLS equation and obtain the class of soliton solutions with a purely algebraic computational method. Notably, we discuss in detail the effects of the external on-site potentials on the explicit form of the soliton solution generated recursively. Under the action of the external on-site potentials, the model presents a rich variety of oscillating multidromion patterns propagating in the system. (general)

  12. OSIRIS-Gamma-ray spectroscopy software for on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty

    Caffrey, A. J.; Bowyer, T. W.; Egger, A. E.; Hall, J. C.; Kelly, S. M.; Krebs, K. M.; Kreek, S. A.; Jordan, D. V.; Milbrath, B. D.; Padgett, S. W.; Wharton, C. J.; Wimer, N. G.

    2015-06-01

    We have designed and tested software for the acquisition and analysis of high-resolution gamma-ray spectra during on-site inspections under the Comprehensive Nuclear-Test-Ban Treaty (CTBT). The On-Site Inspection RadioIsotopic Spectroscopy-OSIRIS-software filters the spectral data to display only radioisotopic information relevant to CTBT on-site inspections, e.g.,131I. A set of over 100 fission-product spectra was employed for OSIRIS testing. These spectra were measured where possible, or generated by modeling. The test spectral compositions include non-nuclear-explosion scenarios, e.g., a severe nuclear reactor accident, and nuclear-explosion scenarios such as a vented underground nuclear test. Comparing its computer-based analyses to expert visual analyses of the test spectra, OSIRIS correctly identifies CTBT-relevant fission product isotopes at the 95% level or better.

  13. Detection of Anomalous Gamma-Ray Spectra for On-Site Inspection

    This work aims to solve some of the technical and logistical challenges inherent in performing On Site Inspection activities under the authority of the Comprehensive Nuclear-Test-Ban Treaty. Inspectors require equipment that can reliably identify the radionuclide signatures of nuclear test explosions amid a background of environmental contamination. Detection of these radiation anomalies by mobile search teams in the air or on the ground can narrow the search field and target specific areas for more detailed inspection or sampling. The need to protect confidential information of the inspected State Party, especially regarding past nuclear testing activities, suggests that full access to measured gamma-ray spectra should be limited. Spectral blinding techniques - in which only a fraction of the information derived from the spectra is displayed and stored - have the potential to meet the needs of both the OSI team and the State Party. In this paper, we describe one such algorithm that we have developed for identifying anomalous spectra from handheld, mobile, or aerial sensors. The algorithm avoids potential sensitivities by reducing the gamma-ray spectrum into a single number that is displayed and stored. A high value indicates that the spectrum is anomalous. The proposed technique does not rely on identifying specific radionuclides, operates well in the presence of high background variability, and can be configured to ignore specific spectral components. In previous work, the algorithm has proven very effective in classifying gamma-ray spectra as anomalous or not, even with poor statistical information. We performed a limited simulation of an airborne search scenario to demonstrate the potential algorithm for OSI missions. The technique successfully detected an injected source of interest whose count rate was an order of magnitude below background levels. We also configured the algorithm to ignore 137Cs as irrelevant to the mission. The resulting alarm metrics were

  14. Balloon Coating with Rapamycin Using an On-site Coating Device

    Purpose. The efficacy of drug-eluting balloons has been demonstrated in clinical trials. The drug predominantly used is paclitaxel because of its lipophilic properties and the rapid onset of action. The aim of the investigation was to evaluate the feasibility and efficacy of an alternative balloon coating with rapamycin that can be applied on site.MethodsThe balloon coating (3.0/18 and 3.0/12 mm, Cathy No. 4, Translumina GmbH) with rapamycin was conducted with a coating machine (Translumina GmbH). Concentrations were 2, 2 × 2, 3, and 4 %. Measurements regarding the amount of substance released to the vessel wall were carried out on explanted porcine coronaries by means of ultraviolet and visible-light spectroscopy. Inflation time varied between 30 and 120 s. The biological effect of the coating was evaluated in a porcine peripheral overstretch and stent implantation model. Results. The amount of rapamycin on the balloon surface ranged from 558 ± 108 μg for the 2 % solution to 1,441 ± 228 μg in the 4 % solution. An amount of 95 ± 63–193 ± 113 μg was released into the vessel wall. The quantitative measurements of the angiographic examinations 4 weeks after treatment revealed a reduction of diameter stenosis from 20.6 ± 17.4 % in the control group to 11.6 ± 5.5 % in the drug-eluting balloon group. Conclusion. A balloon coating with rapamycin omitting an excipient is possible with a dose-adjustable coating machine. However, the biological effects are moderate, which make further optimization of the coating process and evaluation of appropriate excipients necessary.

  15. The project on site - setting the scene for successful industrial relations

    The site construction performance at Torness and Heysham 2 has been described in various other papers during the Conference and in common with other large projects undertaken over the last 20 years a final judgement will be made as to whether, in simple terms, they were ''good'' or ''bad'' sites. Although there are many individuals or organisations who may make this judgement, it is unlikely that the basic conclusion will differ. What may differ however is the list of reasons that will be advanced to explain the final result. Looking at the investigations made into past projects, the reasons advanced for their success or otherwise can range from the geographical location of the site to material delivery problems, design changes, safety issues, or even the state of the overall national economic climate during the period under scrutiny. Where industrial relations problems are singled out, they can usually be linked to one or more of the factors mentioned. When looking at the complexity of projects such as Torness and Heysham, it is to be expected that unlooked for difficulties and problems will always arise but it is equally true that there is sufficient experience and expertise available in the industry for many possible problem areas to be anticipated and ''designed'' out before work even commences on site. This paper will be looking at the clients' role in creating a suitable environment for contractors to fully manage all aspects of their site operation and to ensure that acute problems can receive the full attention of all parties and not have to be set against a continuing background of unnecessary irritations. (author)

  16. Trona and sodium bicarbonate in beef cattle diets: effects on site and extent of digestion.

    Boerner, B J; Byers, F M; Schelling, G T; Coppock, C E; Greene, L W

    1987-07-01

    Six yearling Hereford X Angus steers (avg 272 kg), each with ruminal, duodenal and ileal cannulas were used in a 6 X 6 Latin-square metabolism trial to evaluate the impact of NaHCO3 and trona (a ground, nonrefined ore with chemical composition NaHCO3-Na2CO3-2H2O) on site and extent of digestion of nutrients in the digestive tract. The diets were 50:50 or 90:10 (cracked corn-based concentrate:cottonseed hulls) with no buffer, 1% NaHCO3, or 1% trona. Intake, across all treatments, averaged 2.4% of body weight. Dry matter (DM) and starch digestibility (via indigestible acid detergent fiber) before the duodenum was decreased (P less than .10) with trona in the 50:50 diet. Digestibility of DM, crude protein and starch before the ileum were greater (P less than .05) in the 90:10 diet vs 50:50 diet. Total tract digestibility was similar across buffer treatments in the 90:10 diet. Addition of NaHCO3 increased (P less than .05) digestibility of dry matter and cell solubles in the 50:50 diet. Organic matter and crude protein digestibility were also increased (P less than .10) with NaHCO3. Apparent crude protein and cell solubles digestibility were greater (P less than .10) with trona than NaHCO3 in the 50:50 diet. This trial indicates that buffers provide overall enhancement of diet digestibility in mixed grain/roughage diets. PMID:3038822

  17. Residential on site solar heating systems: a project evaluation using the capital asset pricing model

    Schutz, S.R.

    1978-12-01

    An energy source ready for immediate use on a commercial scale is solar energy in the form of On Site Solar Heating (OSSH) systems. These systems collect solar energy with rooftop panels, store excess energy in water storage tanks and can, in certain circumstances, provide 100% of the space heating and hot water required by the occupants of the residential or commercial structure on which the system is located. Such systems would take advantage of a free and inexhaustible energy source--sunlight. The principal drawback of such systems is the high initial capital cost. The solution would normally be a carefully worked out corporate financing plan. However, at the moment it is individual homeowners and not corporations who are attempting to finance these systems. As a result, the terms of finance are excessively stringent and constitute the main obstacle to the large scale market penetration of OSSH. This study analyzes the feasibility of OSSH as a private utility investment. Such systems would be installed and owned by private utilities and would displace other investment projects, principally electric generating plants. The return on OSSH is calculated on the basis of the cost to the consumer of the equivalent amount of electrical energy that is displaced by the OSSH system. The hurdle rate for investment in OSSH is calculated using the Sharpe--Lintner Capital Asset Pricing Model. The results of this study indicate that OSSH is a low risk investment having an appropriate hurdle rate of 7.9%. At this rate, OSSH investment appears marginally acceptable in northern California and unambiguously acceptable in southern California. The results also suggest that utility investment in OSSH should lead to a higher degree of financial leverage for utility companies without a concurrent deterioration in the risk class of utility equity.

  18. On-site evaluation of crud build-up and clad oxidation level

    The general trend in the late 1980's is to move toward longer operating cycles and extended burn-up. Among the questions raised by this increased performance PWR's waterside corrosion could be a potentially life-limiting problem. Therefore a large on site surveillance programme has been set up to collect data in various conditions: different plants and cycles, local burn-up up to 60 GWd/MTU, load follow operation, nucleate boiling... For that purpose FRAGEMA has developed a simple device, which can be easily installed in the spent fuel pit, featuring jointly a crud scrapping system and an Eddy-current probe for oxide thickness measurements: this makes possible correlation between clad corrosion and crud thickness. A telescopic pole is hanged along the wall of the pit, an X-Y carriage allows its movement in two perpendicular directions. At the bottom part either a scrapping head or an Eddy-current probe can be mounted. Both selection of the areas to be examined and monitoring during scrapping and measurements are made with the help of a T.V. camera. Design of the tool has been focused on safety aspect to avoid any deterioration of the fuel assembly and to minimize radiation exposure during crud collection and filtration. The positioning and the touching of the eddy-current probe on the rod have been carefully studied to ensure reliable data collection. For calibration, oxidized zircaloy tubes with well known oxide thickness, are used. Detailed description of the complete device and experience obtained through several campaigns are presented in this paper. (author)

  19. Static and dynamic stress analyses of the prototype high head Francis runner based on site measurement

    More efforts are put on hydro-power to balance voltage and frequency within seconds for primary control in modern smart grids. This requires hydraulic turbines to run at off-design conditions. especially at low load or speed-no load. Besides. the tendency of increasing power output and decreasing weight of the turbine runners has also led to the high level vibration problem of the runners. especially high head Francis runners. Therefore. it is important to carry out the static and dynamic stress analyses of prototype high head Francis runners. This paper investigates the static and dynamic stresses on the prototype high head Francis runner based on site measurements and numerical simulations. The site measurements are performed with pressure transducers and strain gauges. Based on the measured results. computational fluid dynamics (CFD) simulations for the flow channel from stay vane to draft tube cone are performed. Static pressure distributions and dynamic pressure pulsations caused by rotor-stator interaction (RSI) are obtained under various operating conditions. With the CFD results. static and dynamic stresses on the runner at different operating points are calculated by means of the finite element method (FEM). The agreement between simulation and measurement is analysed with linear regression method. which indicates that the numerical result agrees well with that of measurement. Furthermore. the maximum static and dynamic stresses on the runner blade are obtained at various operating points. The relations of the maximum stresses and the power output are discussed in detail. The influences of the boundary conditions on the structural behaviour of the runner are also discussed

  20. Authentication and sample chemistry: A new approach at the Rokkasho Reprocessing Plant on-site laboratory

    Full text: The On-Site Laboratory (OSL) has the commitment to provide IAEA safeguards with reliable, accurate and timely results of the inspection samples taken at the Rokkasho Reprocessing Plant (RRP). The Laboratory is an important part of the effort to safeguard adequately this large reprocessing plant and is located on the premises of the RRP which facilitates solving the timeliness dilemma. The OSL is operated jointly by the analysts of IAEA and NMCC (Nuclear Material Control Center)/JSGO (Japan Safeguards Office). This joint task requires solving new challenges in destructive analysis (DA), sharing instruments, space and procedures in order to reach the best analytical results possible. While great efforts are made by the inspector analysts (IA) to achieve excellence in the sample chemistry no minor effort is made by the IAEA to ensure that the results are adequately authenticated. Due to the fact that the instruments are jointly used, new approaches for the implementation of measures for authentication and continuity of knowledge (CoK) have been designed and put into practice. The authentication measures include securing the instruments and the data produced. Additionally, maintaining CoK of the samples that undergo different chemical analysis, securing the procedures and considering measures of deterrence have been given special attention. All which build a relative solid frame for independent DA. It must be understood from the beginning that a 100% assurance for a tamper free operation is a great challenge, and that the best achievable authentication under the given situation is the target for the IAEA. The implementation of authentication in the routine sample chemistry requires additional efforts on part of the IA and has an impact on the time needed to do the work if compared to the activities of a normal nuclear Laboratory. This paper describes the authentication policy in the OSL, the specific measures that are implemented and the range of confidence

  1. Authentication and sample chemistry: A new approach at the Rokkasho Reprocessing Plant on-site laboratory

    The On-Site Laboratory (OSL) is committed to providing the IAEA with reliable, accurate and timely results of the inspection samples taken at the Rokkasho Reprocessing Plant (RRP). The OSL is an important part of the efforts to safeguard adequately this large reprocessing plant. It is located on the premises of the RRP, which helps to resolve the timeliness dilemma. The OSL is operated jointly by the IAEA, the Nuclear Material Control Center (NMCC) and Japan Safeguards Office (JSGO). This joint task requires addressing new challenges in destructive analysis (DA) and the sharing of instruments, space and procedures in order to reach the best analytical results possible. The inspector-analysts make great efforts to achieve excellence in the sample chemistry and to ensure that the procedures and results are adequately authenticated. Because the instruments are jointly used, new approaches for the implementation of measures for authentication and continuity of knowledge have been designed and put into practice. The authentication measures include securing the instruments and the data produced. Additionally, special attention is given to maintaining continuity of knowledge of the samples that undergo chemical analyses, securing the procedures and considering measures of deterrence. All these measures build a relatively solid framework for independent DA. It must be understood that a 100% assurance for a tamper-free operation is a great challenge, and the IAEA aims to achieve the best authentication under the given situation. The implementation of authentication in the routine sample chemistry requires additional efforts on the part of the IAEA and has an impact on the time needed to perform the work, compared to the activities of a normal nuclear laboratory. This paper describes the authentication policy in the OSL, the specific measures implemented and the range of confidence expected in different procedures. (author)

  2. A small-scale flow alkaline fuel cell for on-site production of hydrogen peroxide

    The behavior of a small-scale flow alkaline fuel cell (AFC) built-up for on-site production of HO2- using commercial gas-diffusion electrodes has been studied. It produces a spontaneous current due to the oxidation of H2 to H2O at the H2-diffusion anode and the reduction of O2 to HO2- at the O2-diffusion cathode, while a fresh 1.0-6.0 mol dm-3 KOH electrolyte at 15.0-45.0 deg. C is injected through it. Under circulation of HO2-+KOH solutions in open circuit, the flow AFC behaves as a two-electron reversible system. When it is shorted with an external load (Rext), steady cell voltage-current density curves are found. The use of O2/N2 mixtures to fed the cathode causes a loss of its performance, being required to supply pure O2 to yield a maximum HO2- electrogeneration. The current density and HO2- productivity increase with raising OH- concentration, temperature and pressure of O2 fed. At Rext=0.10 Ω, a current efficiency close to 100% is obtained, and current densities >100 mA cm-2 are achieved for 1.0 mol dm-3 KOH at 45.0 deg. C and for higher KOH concentrations at 25.0 deg. C. The flow AFC can work under optimum conditions up to 6.0 mol dm-3 KOH and 45.0 deg. C for possible industrial applications

  3. Static and dynamic stress analyses of the prototype high head Francis runner based on site measurement

    Huang, X.; Oram, C.; Sick, M.

    2014-03-01

    More efforts are put on hydro-power to balance voltage and frequency within seconds for primary control in modern smart grids. This requires hydraulic turbines to run at off-design conditions. especially at low load or speed-no load. Besides. the tendency of increasing power output and decreasing weight of the turbine runners has also led to the high level vibration problem of the runners. especially high head Francis runners. Therefore. it is important to carry out the static and dynamic stress analyses of prototype high head Francis runners. This paper investigates the static and dynamic stresses on the prototype high head Francis runner based on site measurements and numerical simulations. The site measurements are performed with pressure transducers and strain gauges. Based on the measured results. computational fluid dynamics (CFD) simulations for the flow channel from stay vane to draft tube cone are performed. Static pressure distributions and dynamic pressure pulsations caused by rotor-stator interaction (RSI) are obtained under various operating conditions. With the CFD results. static and dynamic stresses on the runner at different operating points are calculated by means of the finite element method (FEM). The agreement between simulation and measurement is analysed with linear regression method. which indicates that the numerical result agrees well with that of measurement. Furthermore. the maximum static and dynamic stresses on the runner blade are obtained at various operating points. The relations of the maximum stresses and the power output are discussed in detail. The influences of the boundary conditions on the structural behaviour of the runner are also discussed.

  4. Experience feedback from on-site inspections of small owners of nuclear materials in France

    Small quantities of nuclear materials are used beside the nuclear industry, in the industrial, medical and research sectors. Those materials are covered by detailed and comprehensive regulations set up by the French government in the Law no 80-572 of 25 July 1980 concerning protection and control of nuclear materials. This paper focuses on on-site inspections, carried out by sworn and accredited inspectors under the authority of the Ministry for Industry, with a view to checking the enforcement of regulations and also to providing comprehensive information to the operator about those regulations. The first part of the paper deals with the legal framework regarding the use of nuclear materials by small owners. Emphasis is put on the declaration which must be prepared and submitted each year. This declaration provides to the competent authority data related to inventory and inventory changes of all nuclear materials held by the operator. It also describes the main features concerning facility layout related to physical protection of nuclear materials. The second part shows how this declaration may provide guidance to the inspectors from French national safeguards to control the proper application of regulatory requirements. A brief description of the different inspection phases is given and illustrated by practical examples. The third part highlights the experience feedback arising from more than 120 inspections made during the last four years. Those inspections have permitted, through a verification of the annual physical inventory declared by the operators, to replace several items in a controlled environment. Moreover a new global approach for the management of nuclear materials is now appearing in the industrial or medical sectors. Finally, demonstration is made that good practices in the field of control and physical protection of nuclear materials held by small owners, not only reduce the occurrence of incidents related to losses or thefts of equipment or

  5. Validation of Self-Reported Power Take-Off Shielding Using On-Site Farm Audits.

    Chapel, D B; Sorensen, J A; Tinc, P J; Fiske, T; Wyckoff, S; Mellors, P W; Jenkins, P

    2015-04-01

    Despite the substantial contribution of power take-off (PTO) entanglements to workplace morbidity and mortality among agricultural workers, the degree of proper PTO shielding on U.S. farms remains poorly characterized. Sampling from the New York data of the USDA National Agricultural Statistical Service (NASS), at least 200 each of dairy, livestock, crop, fruit, and vegetable farms were surveyed by phone to determine the extent of proper PTO shielding. In the same year, on-site audits were performed at 211 randomly selected New York livestock and dairy farms using a four-point scale to assess PTO shielding. Supplemental data were gathered on farm acreage, number of livestock, principal commodity, and operator experience. The phone survey data for livestock and dairy farms were then compared to the on-farm audit data. In the phone survey, 72.5% of farms reported having shields on all implements. The mean percentage of implements reported to be shielded was 90.2%. By on-farm audit, 10% of farms had all implements properly shielded, and the mean percentage of properly shielded implements was 56.7%, with shielding rates differing widely for different classes of implements. No significant predictors of PTO shielding were identified. The phone survey greatly overestimated proper PTO shielding rates when compared with the on-farm audits. These data suggest a lower level of proper shielding among farmers than is mandated by current industry safety standards. The results also identify a principal weakness of phone surveys in accurately assessing the true magnitude of on-farm risk for PTO entanglement. PMID:26204785

  6. Qualification methodologies for mechanical components, I and C, piping using on-site testing

    A qualification procedure shall confirm that the equipment is capable of meeting, throughout its design operational life, the requirements for performing safety functions while subject to the environmental conditions prevailing at the time of need. (The Safety of Nuclear Power Plant: Design IAEA Safety Guide). IEC 780 gives the following definition: Qualification is the generation and maintenance of evidence to ensure that the equipment will operate on demand to meet the system performance requirements. When it should be used on-site testing? Seismic design and qualification for nuclear power plants IAEA Safety Guide is requiring periodic safety review. (Maintenance throughout the design operational life.) Inspection and Testing for Acceptance IAEA Q4 Safety Guide requires that in some circumstances final acceptance of a supplied item is only possible after it has been installed. Testing methodology includes: low impedance tests (mechanical excitation impact, soil blast). Mechanical excitation: small exciters (electro-dynamic shakers or servo-hydraulic actuators) are used. Impulse technique is used for structural frequency response testing. The flowing examples are presented: in-situ dynamic test on reactor tank, in-situ dynamic test on cabinets; in-situ soil explosion test on NPP. Qualification by in-situ testing is more or less always a qualification by combination of tests and analyses. In situ testing can be performed only with low level excitation and then very special attention should be paid to non linear behaviour of structures and components. When dealing with components with bolted connections the behaviour can be very different from low and high level excitation both due to changing of restraint conditions and energy dissipating mechanisms. Piping restraints allowing thermal expansion can have a very different behaviour from low to high level excitation

  7. Balloon Coating with Rapamycin Using an On-site Coating Device

    Schmehl, Joerg, E-mail: joerg.schmehl@med.uni-tuebingen.de [Department of Diagnostic and Interventional Radiology, University Hospital of Tuebingen (Germany); Ruhr, Juergen von der [Institute of Anatomy, University of Tuebingen (Germany); Dobratz, Markus; Kehlbach, Rainer [Department of Diagnostic and Interventional Radiology, University Hospital of Tuebingen (Germany); Braun, Isabelle [Translumina GmbH (Germany); Greiner, Tim-Oliver [Clinic of Thoracic and Cardiovascular Surgery, University Hospital of Tuebingen (Germany); Claussen, Claus D. [Department of Diagnostic and Interventional Radiology, University Hospital of Tuebingen (Germany); Behnisch, Boris [Translumina GmbH (Germany)

    2013-06-15

    Purpose. The efficacy of drug-eluting balloons has been demonstrated in clinical trials. The drug predominantly used is paclitaxel because of its lipophilic properties and the rapid onset of action. The aim of the investigation was to evaluate the feasibility and efficacy of an alternative balloon coating with rapamycin that can be applied on site.MethodsThe balloon coating (3.0/18 and 3.0/12 mm, Cathy No. 4, Translumina GmbH) with rapamycin was conducted with a coating machine (Translumina GmbH). Concentrations were 2, 2 Multiplication-Sign 2, 3, and 4 %. Measurements regarding the amount of substance released to the vessel wall were carried out on explanted porcine coronaries by means of ultraviolet and visible-light spectroscopy. Inflation time varied between 30 and 120 s. The biological effect of the coating was evaluated in a porcine peripheral overstretch and stent implantation model. Results. The amount of rapamycin on the balloon surface ranged from 558 {+-} 108 {mu}g for the 2 % solution to 1,441 {+-} 228 {mu}g in the 4 % solution. An amount of 95 {+-} 63-193 {+-} 113 {mu}g was released into the vessel wall. The quantitative measurements of the angiographic examinations 4 weeks after treatment revealed a reduction of diameter stenosis from 20.6 {+-} 17.4 % in the control group to 11.6 {+-} 5.5 % in the drug-eluting balloon group. Conclusion. A balloon coating with rapamycin omitting an excipient is possible with a dose-adjustable coating machine. However, the biological effects are moderate, which make further optimization of the coating process and evaluation of appropriate excipients necessary.

  8. Hand-Held Devices for the Detection of Clandestine Nuclear Material on Site

    means for detecting undeclared nuclear material and activities on-site. It is not sufficient to have measuring devices at hand with the best and most advanced technology but it is at least of the same importance to apply them correctly and in best manner. (author)

  9. ALL-PATHWAYS DOSE ANALYSIS FOR THE PORTSMOUTH ON-SITE WASTE DISPOSAL FACILITY

    Smith, F.; Phifer, M.

    2014-04-10

    A Portsmouth On-Site Waste Disposal Facility (OSWDF) All-Pathways analysis has been conducted that considers the radiological impacts to a resident farmer. It is assumed that the resident farmer utilizes a farm pond contaminated by the OSWDF to irrigate a garden and pasture and water livestock from which food for the resident farmer is obtained, and that the farmer utilizes groundwater from the Berea sandstone aquifer for domestic purposes (i.e. drinking water and showering). As described by FBP 2014b the Hydrologic Evaluation of Landfill Performance (HELP) model (Schroeder et al. 1994) and the Surface Transport Over Multiple Phases (STOMP) model (White and Oostrom 2000, 2006) were used to model the flow and transport from the OSWDF to the Points of Assessment (POAs) associated with the 680-ft elevation sandstone layer (680 SSL) and the Berea sandstone aquifer. From this modeling the activity concentrations radionuclides were projected over time at the POAs. The activity concentrations were utilized as input to a GoldSimTM (GTG 2010) dose model, described herein, in order to project the dose to a resident farmer over time. A base case and five sensitivity cases were analyzed. The sensitivity cases included an evaluation of the impacts of using a conservative inventory, an uncased well to the Berea sandstone aquifer, a low waste zone uranium distribution coefficient (Kd), different transfer factors, and reference person exposure parameters (i.e. at 95 percentile). The maximum base case dose within the 1,000 year assessment period was projected to be 1.5E-14 mrem/yr, and the maximum base case dose at any time less than 10,000 years was projected to be 0.002 mrem/yr. The maximum projected dose of any sensitivity case was approximately 2.6 mrem/yr associated with the use of an uncased well to the Berea sandstone aquifer. This sensitivity case is considered very unlikely because it assumes leakage from the location of greatest concentration in the 680 SSL in to the

  10. Dynamic telecytopathology of on site rapid cytology diagnoses for pancreatic carcinoma

    Chhieng David

    2006-01-01

    Full Text Available Abstract Background Diagnosis of pancreatic lesions can be accurately performed by endoscopic ultrasound guided fine needle aspiration (EUS-FNA with onsite cytopathologists to assess specimen adequacy and to determine a preliminary diagnosis. Considerable time is needed to perform on-site assessments. This takes away work time of cytopathologists and prohibits them from serving remote locations. It is therefore logical to ask if real-time telecytopathology could be used to assess specimen adequacy and if telecytopathology diagnosis has the same level of agreement to the final diagnosis as that of onsite evaluation. In this study, we compare agreement between cytodiagnoses rendered using telecytopathology with onsite and final interpretations. Method 40 Diff-Quik-stained EUS-FNA were re-evaluated retrospectively (patient ages 31–62, 19:21 male:female, 15 non-malignant lesions, 25 malignant lesions as classified by final diagnosis. Each previously assessed by a cytopathologist and finally reviewed by the same or different cytopathologist. Blinded to the final diagnosis, a resident pathologist re-screened all slides for each case, selected a slide and marked the diagnostic cells most representative of the lesion. Blinded to the diagnosis, one cytopathologist assessed the marked cells through a real time remotely operated telecytopathology system (MedMicroscopy. Diagnosis and time spent were recorded. Kappa statistic was used to compare agreements between telecytopathology vs. original onsite vs. final diagnoses. Results Time spent for prescreening ranged from 1 to 5 minutes (mean 2.6 +/- 1.3 minutes and time spent for telecytopathology diagnosis ranged from 2–20 minutes (mean 7.5 +/- 4.5 minutes. Kappa statistics, K, was as follows: telecytopathology versus onsite diagnosis K, 95% CI = 0.65, 0.41–0.88, for telecytopathology versus final K, 95% CI = 0.61, 0.37–0.85 and for onsite diagnosis versus final K, 95% CI = 0.79, 0.61–0.98. There is

  11. Thyroid fine needle aspiration biopsy: Do we really need an on-site cytopathologist?

    Purpose: The aim of this single center study is to evaluate the effectiveness of performing ultrasound-guided thyroid fine-needle aspiration biopsies (FNAB) performed by the radiologist alone without an on-site cytopathologist. Materials and methods: In this prospective randomized study, 203 patients with single nodules measuring 10 mm or more underwent ultrasound-guided FNAB: 102 patients underwent FNAB performed by the radiologist accompanied by a cytopathologist (control group); 101 patients underwent FNAB by the radiologist alone (study group). In both groups biopsy time, specimen adequacy ratio, total aspiration number, cytopathologist's cytological diagnosis time (t1), cytopathologist's total time consumption (t2) were evaluated. Results: Mean total biopsy time was 8.74 ± 2.31 min in the study group and was significantly shorter than the control group's 11.97 ± 6.75 min (p = 0.004). The average number of aspirations per patient in the study group was 4.00 ± 0; compared to the control group's 3.56 ± 1.23 this was significantly higher (p = 0.001). t1 of the study group was 307.48 ± 226.32 s; compared to 350.14 ± 247.64 s in the control group, there was no statistically significant difference (p = 0.137). t2 of the study group was 672.93 ± 270.45 s; compared to the control group (707.03 ± 258.78 s) there was no statistically significant difference (p = 0.360). Diagnostic adequacy of aspirated specimens was reassessed in the pathology laboratory. In the study group, 84 out of 101 aspirations and in the control group 89 out of 102 aspirations was determined as adequate with no statistically significant difference (p = 0.302). Conclusions: We believe that in centers where a cytopathologist is not available, ultrasound-guided thyroid FNAB can be adequately performed by an experienced radiologist who was effectively trained in smear preparation

  12. Evaluation of snow-glide risk by modelling and on-site assessment

    Leitinger, Georg; Meusburger, Katrin; Rüdisser, Johannes; Tasser, Erich; Höller, Peter

    2015-04-01

    Abandonment of agricultural practices on alpine grasslands lead to increasing snow-glide intensities due to lower surface roughness of the vegetation. Beneath the danger of snow-glide avalanches snow gliding leads to soil erosion and damaging of young trees at afforested sites. Especially in high altitudes afforestation is important to protect settlements and infrastructure against snow-gliding and glide avalanches. Snow-glide damages are therefore of particular danger for these afforestation sites. In the light of future climate change and warmer winter periods, studies already state increasing snow-glide risk and the occurrence of glide avalanches. This study presents an approach to evaluate snow-glide risk by combining the refined Spatial Snow Glide Model (SSGM) first published by Leitinger et al. (2008) and the Guidelines to Identify Snow-Glide Areas (GISGA) proposed by Höller (2012), an on-site risk analyses approach. First, GISGA was validated on the basis of corresponding snow-glide measurements. Second, a potential snow-glide map for an area in the Eastern Alps covering 20000 km² was modelled. The results revealed considerable areas of high snow-glide risk. Using the average amount of winter precipitation between 1990 and 2010 in the SSGM shows higher vulnerability for the northern part of the study area (Tyrol, Austria) than in the southern part (South Tyrol, Italy) because of lower winter precipitation. However, running the SSGM based on the highest winter precipitation registered in the study area between 1801 and 2003 exhibits the possibility of very high snow-glide risk for most parts of the study area with significant increasing risk in the southern part. Given the very probable future climate during winter periods with increasing temperatures but uncertain development of precipitation patterns, snow-glide activity and linked glide avalanches might further increase at least in areas and altitudes with solid precipitation. In combination with the

  13. NG09 And CTBT On-Site Inspection Noble Gas Sampling and Analysis Requirements

    Carrigan, Charles R.; Tanaka, Junichi

    2010-05-01

    A provision of the Comprehensive Test Ban Treaty (CTBT) allows on-site inspections (OSIs) of suspect nuclear sites to determine if the occurrence of a detected event is nuclear in origin. For an underground nuclear explosion (UNE), the potential success of an OSI depends significantly on the containment scenario of the alleged event as well as the application of air and soil-gas radionuclide sampling techniques in a manner that takes into account both the suspect site geology and the gas transport physics. UNE scenarios may be broadly divided into categories involving the level of containment. The simplest to detect is a UNE that vents a significant portion of its radionuclide inventory and is readily detectable at distance by the International Monitoring System (IMS). The most well contained subsurface events will only be detectable during an OSI. In such cases, 37 Ar and radioactive xenon cavity gases may reach the surface through either "micro-seepage" or the barometric pumping process and only the careful siting of sampling locations, timing of sampling and application of the most site-appropriate atmospheric and soil-gas capturing methods will result in a confirmatory signal. The OSI noble gas field tests NG09 was recently held in Stupava, Slovakia to consider, in addition to other field sampling and analysis techniques, drilling and subsurface noble gas extraction methods that might be applied during an OSI. One of the experiments focused on challenges to soil-gas sampling near the soil-atmosphere interface. During withdrawal of soil gas from shallow, subsurface sample points, atmospheric dilution of the sample and the potential for introduction of unwanted atmospheric gases were considered. Tests were designed to evaluate surface infiltration and the ability of inflatable well-packers to seal out atmospheric gases during sample acquisition. We discuss these tests along with some model-based predictions regarding infiltration under different near

  14. 75 FR 22629 - Kenco Logistic Services, LLC, Electrolux Webster City, Including On-Site Leased Workers From...

    2010-04-29

    ... February 16, 2010 (75 FR 7037). At the request of the State agency, the Department reviewed the... Employment and Training Administration Kenco Logistic Services, LLC, Electrolux Webster City, Including On... of Kenco Logistic Services, LLC, Electrolux Webster City, including on-site leased workers...

  15. Applying the 5 WHYs to Identify Root Causes to Non-completions in On-Site Construction

    Lindhard, Søren Munch

    2014-01-01

    In on-site production, mass-customized subproducts are assembled through standardized processes. The production is pushing mass customization to the edge by producing unique and complex products. Due to the project structure, it has proven difficult to avoid repetitions of problems and to learn f...

  16. 76 FR 27366 - CEVA Freight, LLC, Dell Logistics Division, Including On-Site Leased Workers From Prologistix...

    2011-05-11

    ... Carolina. The notice was published in the Federal Register on April 23, 2010 (75 FR 21357). The notice was... notice was published in the Federal Register on July 1, 2010 (75 FR 38128-38129). At the request of the... Employment and Training Administration CEVA Freight, LLC, Dell Logistics Division, Including On-Site...

  17. 76 FR 35025 - Nokia, Inc.; a Subsidiary of Nokia Group; Including On-Site Leased Workers From ATC Logistics and...

    2011-06-15

    ... phone equipment. The notice was published in the Federal Register on March 10, 2011 (76 FR 13229). At... Workers From ATC Logistics and Electronics and Adecco Fort Worth, TX; Amended Certification Regarding...., a subsidiary of Nokia Group, including on-site leased workers from ATC Logistics and...

  18. 77 FR 44685 - ConocoPhillips Company, Trainer Refinery, Including On-Site Leased Workers From Shrack, Young...

    2012-07-30

    ... Employment and Training Administration ConocoPhillips Company, Trainer Refinery, Including On-Site Leased Workers From Shrack, Young, and Associates, Inc., and Project Control Associates, Trainer, PA; Notice of... of ConocoPhillips Company, Trainer Refinery, Trainer, Pennsylvania (subject firm). The subject...

  19. RECONCILING ON-SITE STORMWATER BEST MANAGEMENT PRACTICE (BMP) EFFECTIVENESS AND PERFORMANCE WITH CURRENT HYDROLOGIC AND ECONOMIC PERCEPTIONS

    There is currently a dearth of data characterizing best management practice impacts on runoff production at the parcel-level. This data is of critical importance insofar as judging the effectiveness and reliability of on-site stormwater BMPs, with significant implications for bot...

  20. 77 FR 43368 - Joerns Healthcare, LLC, Stevens Point, Wisconsin Division, Including On-Site Leased Workers From...

    2012-07-24

    ... Employment and Training Administration Joerns Healthcare, LLC, Stevens Point, Wisconsin Division, Including... Federal Register on June 6, 2012 (77 FR 33493). At the request of a state workforce official, the... Healthcare, LLC, Stevens Point, Wisconsin Division, Stevens Point, Wisconsin, including on-site...

  1. TREATMENT OF COMBINED SEWER OVERFLOWS BY HIGH GRADIENT MAGNETIC SEPARATION. ON-SITE TESTING WITH MOBILE PILOT PLANT TRAILER

    Seeded water treatment using a SALA high gradient magnetic separator pilot plant system was conducted on combined sewer overflows and raw sewage at SALA Magnetics in Cambridge, MA and at on-site locations in the Boston area. Special emphasis was placed on specific design and oper...

  2. 76 FR 13227 - Continental Structural Plastics, Including On-Site Leased Workers From Kelly Services and Doepker...

    2011-03-10

    ... published in the Federal Register on January 26, 2009 (74 FR 4463). The notice was amended on December 17..., 2011 (76 FR 175) At the request of the State agency, the Department reviewed the certification for... Employment and Training Administration Continental Structural Plastics, Including On-Site Leased Workers...

  3. 75 FR 16514 - Bayer Material Science, LLC, Formally Known as Sheffield Plastics, Including On-Site Leased...

    2010-04-01

    ... 25, 2010 (75 FR 3934). At the request of the State Agency, the Department reviewed the certification... Employment and Training Administration Bayer Material Science, LLC, Formally Known as Sheffield Plastics... Material Science, LLC, formally known as Sheffield Plastics, including on-site leased workers...

  4. 76 FR 175 - Continental Structural Plastics Including On-Site Leased Workers From Kelly Services and Time...

    2011-01-03

    ... of Continental Structural Plastics, North Baltimore, Ohio. The notice was published in the Federal Register on January 26, 2009 (74 FR 4463). At the request of the UAW, Local 1889, the Department reviewed... Employment and Training Administration Continental Structural Plastics Including On-Site Leased Workers...

  5. An Empirical Study of the Effectiveness of Publicly-Funded "Structured On-Site Training": Implications for Policy and Practice

    Gorman, Phil; Moore, Richard; Blake, Daniel; Phillips, Michael G.

    2004-01-01

    This article reports findings from an assessment of the effectiveness of privately administered "structured on-site training" (SOST) programs funded by the California Employment Training Panel. It reports on the characteristics of SOST programs that increased trainees' competitiveness in the internal and external labor markets. In addition, it…

  6. 75 FR 45158 - Holcim (US) Inc. Corporate Division Including On-Site Leased Workers From Manpower, Office Team...

    2010-08-02

    ...., Corporate Division, including on-site leased workers from Manpower and Office Team, Dundee, Michigan. The notice was published in the Federal Register on June 7, 2010 (75 FR 32223). At the request of the State... From Manpower, Office Team and Advance Temporary Services; Dundee, MI; Amended Certification...

  7. 75 FR 26793 - Beam Global Spirits & Wine, Including On-Site Leased Workers from Adecco, St. Elizabeth Business...

    2010-05-12

    ... in the Federal Register April 23, 2010 (75 FR 21354). At the request of the State Agency, the... Employment and Training Administration Beam Global Spirits & Wine, Including On-Site Leased Workers from... Eligibility to apply for Worker Adjustment Assistance on March 26, 2010, applicable to workers of Beam...

  8. 78 FR 31593 - Aleris Recycling Bens Run, LLC, Including On-Site Leased Workers From Winans Extras Support...

    2013-05-24

    ... From the Federal Register Online via the Government Publishing Office DEPARTMENT OF LABOR Employment and Training Administration Aleris Recycling Bens Run, LLC, Including On-Site Leased Workers From... Recycling Bens Run, LLC, Friendly, West Virginia. The determination was issued on March 13, 2013....

  9. 76 FR 73684 - Tiger Drylac USA, Inc., Including On-Site Leased Workers From Berks and Beyond Employment...

    2011-11-29

    ... notice was published in the Federal Register on November 3, 2011 (76 FR 68220). At the request of the... Employment and Training Administration Tiger Drylac USA, Inc., Including On-Site Leased Workers From Berks... Adjustment Assistance on October 19, 2011, applicable to workers of Tiger Drylac USA, Inc.,...

  10. 77 FR 67399 - State Street Corporation, Putnam Cash Reconciliations Team, Including On-Site Leased Workers From...

    2012-11-09

    ... Employment and Training Administration State Street Corporation, Putnam Cash Reconciliations Team, Including..., applicable to workers and former workers of State Street Corporation, Putnam Cash Reconciliation Team, Quincy..., doing business as (D/B/A) ZeroChaos, were employed on-site at State Street Corporation, Putnam...